AB 2126: Public contracts: Construction Manager/General Contractor contracts.
- Session Year: 2015-2016
- House: Assembly
- Latest Version Date: 2016-09-28
Existing law authorizes the Department of Transportation to use the Construction Manager/General Contractor method on no more than 6 projects, and requires 4 out of the 6 projects to use department employees or consultants under contract with the department to perform all project design and engineering services, as specified. Existing law requires specified information provided to the department pursuant to these provisions to be verified under oath.
This bill would authorize the department to use this method on 12 projects and would require 8 out of the 12 projects to use department employees or consultants under contract with the department to perform all project design and engineering services. By expanding this authorization, the bill would expand the scope of the crime of perjury, thus imposing a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law authorizes the Department of Transportation to use the Construction Manager/General Contractor method on no more than 6 projects, and requires 4 out of the 6 projects to use department employees or consultants under contract with the department to perform all project design and engineering services, as specified. Existing law requires specified information provided to the department pursuant to these provisions to be verified under oath.
This bill would authorize the department to use this method on 12 projects and would require 8 out of the 12 projects to use department employees or consultants under contract with the department to perform all project design and engineering services. By expanding this authorization, the bill would expand the scope of the crime of perjury, thus imposing a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law authorizes the Department of Transportation to use the Construction Manager/General Contractor method on no more than 6 projects, and requires 4 out of the 6 projects to use department employees or consultants under contract with the department to perform all project design and engineering services, as specified. Existing law requires specified information provided to the department pursuant to these provisions to be verified under oath.
This bill would authorize the department to use this method on 12 projects and would require 8 out of the 12 projects to use department employees or consultants under contract with the department to perform all project design and engineering services. By expanding this authorization, the bill would expand the scope of the crime of perjury, thus imposing a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
(a)The Construction Manager/General Contractor method provided by this chapter may be used by the department, but is not limited to, when it is anticipated that it will reduce project costs or expedite project completion in a manner that is not achievable through the design-bid-build method. Notwithstanding any other law, for projects utilizing the Construction Manager/General Contractor method provided by this chapter, the department shall advertise, award, and administer the Construction Manager/General Contractor contract. The department shall not delegate the contracting authority.
(b)The department may use the Construction Manager/General Contractor method on no more than 12 projects, at least 10 of which shall have construction costs greater than ten million dollars ($10,000,000).
(c)On at least eight of the projects utilizing the Construction Manager/General Contractor method provided by this chapter, the department shall use department employees or consultants under contract with the department to perform all project design and engineering services related to design required for Construction Manager/General Contractor project delivery consistent with Article XXII of the California Constitution. On all 12 projects, the department shall use department employees or consultants under contract with the department to perform all construction inspection services required for Construction Manager/General Contractor project delivery consistent with Article XXII of the California Constitution. Department resources, including personnel requirements, necessary to perform all services described in this subdivision shall be included in the departments capital outlay support program for workload purposes in the annual Budget Act.
(d)(1)The department shall prepare and submit to the Legislature, no later than July 1 of each year during which any project using the Construction Manager/General Contractor method is ongoing, a report that describes each project and provides relevant data, including, but not limited to, the stage of completion, district, cost, description, status, and estimated time to completion.
(2)The department shall prepare and submit to the Legislature, no later than July 1 of the year after any project using the Construction Manager/General Contractor method has been completed, a report that includes, in addition to the data in paragraph (1), all of the following:
(A)Data on initial cost estimates, actual cost upon completion, and the reasons for any difference.
(B)Estimated time for completion, actual time of completion, and the reasons for any difference.
(C)The number and dollar value of any change orders for all projects completed using the Construction Manager/General Contractor method.
(e)(1)A report to be submitted pursuant to subdivision (d) shall be submitted in compliance with Section 9795 of the Government Code.
(2)Notwithstanding Section 10231.5 of the Government Code, the requirement for submitting a report imposed under subdivision (d) is inoperative on July 1 of the year following the submission of the final report upon completion of the fourth project of the department that uses the Construction Manager/General Contractor method.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
(a)The Construction Manager/General Contractor method provided by this chapter may be used by the department, but is not limited to, when it is anticipated that it will reduce project costs or expedite project completion in a manner that is not achievable through the design-bid-build method. Notwithstanding any other law, for projects utilizing the Construction Manager/General Contractor method provided by this chapter, the department shall advertise, award, and administer the Construction Manager/General Contractor contract. The department shall not delegate the contracting authority.
(b)The department may use the Construction Manager/General Contractor method on no more than 12 projects, at least 10 of which shall have construction costs greater than ten million dollars ($10,000,000).
(c)On at least eight of the projects utilizing the Construction Manager/General Contractor method provided by this chapter, the department shall use department employees or consultants under contract with the department to perform all project design and engineering services related to design required for Construction Manager/General Contractor project delivery consistent with Article XXII of the California Constitution. On all 12 projects, the department shall use department employees or consultants under contract with the department to perform all construction inspection services required for Construction Manager/General Contractor project delivery consistent with Article XXII of the California Constitution. Department resources, including personnel requirements, necessary to perform all services described in this subdivision shall be included in the departments capital outlay support program for workload purposes in the annual Budget Act.
(d)(1)The department shall prepare and submit to the Legislature, no later than July 1 of each year during which any project using the Construction Manager/General Contractor method is ongoing, a report that describes each project and provides relevant data, including, but not limited to, the stage of completion, district, cost, description, status, and estimated time to completion.
(2)The department shall prepare and submit to the Legislature, no later than July 1 of the year after any project using the Construction Manager/General Contractor method has been completed, a report that includes, in addition to the data in paragraph (1), all of the following:
(A)Data on initial cost estimates, actual cost upon completion, and the reasons for any difference.
(B)Estimated time for completion, actual time of completion, and the reasons for any difference.
(C)The number and dollar value of any change orders for all projects completed using the Construction Manager/General Contractor method.
(e)(1)A report to be submitted pursuant to subdivision (d) shall be submitted in compliance with Section 9795 of the Government Code.
(2)Notwithstanding Section 10231.5 of the Government Code, the requirement for submitting a report imposed under subdivision (d) is inoperative on July 1 of the year following the submission of the final report upon completion of the fourth project of the department that uses the Construction Manager/General Contractor method.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
(a)The Construction Manager/General Contractor method provided by this chapter may be used by the department, but is not limited to, when it is anticipated that it will reduce project costs or expedite project completion in a manner that is not achievable through the design-bid-build method. Notwithstanding any other law, for projects utilizing the Construction Manager/General Contractor method provided by this chapter, the department shall advertise, award, and administer the Construction Manager/General Contractor contract. The department shall not delegate the contracting authority.
(b)The department may use the Construction Manager/General Contractor method on no more than six 12 projects, at least five 10 of which shall have construction costs greater than ten million dollars ($10,000,000).
(c)On at least four eight of the projects utilizing the Construction Manager/General Contractor method provided by this chapter, the department shall use department employees or consultants under contract with the department to perform all project design and engineering services related to design required for Construction Manager/General Contractor project delivery consistent with Article XXII of the California Constitution. On all six 12 projects, the department shall use department employees or consultants under contract with the department to perform all construction inspection services required for Construction Manager/General Contractor project delivery consistent with Article XXII of the California Constitution. Department resources, including personnel requirements, necessary to perform all services described in this subdivision shall be included in the departments capital outlay support program for workload purposes in the annual Budget Act.
(d)(1)The department shall prepare and submit to the Legislature, no later than July 1 of each year during which any project using the Construction Manager/General Contractor method is ongoing, a report that describes each project and provides relevant data, including, but not limited to, the stage of completion, district, cost, description, status, and estimated time to completion.
(2)The department shall prepare and submit to the Legislature, no later than July 1 of the year after any project using the Construction Manager/General Contractor method has been completed, a report that includes, in addition to the data in paragraph (1), all of the following:
(A)Data on initial cost estimates, actual cost upon completion, and the reasons for any difference.
(B)Estimated time for completion, actual time of completion, and the reasons for any difference.
(C)The number and dollar value of any change orders for all projects completed using the Construction Manager/General Contractor method.
(e)(1)A report to be submitted pursuant to subdivision (d) shall be submitted in compliance with Section 9795 of the Government Code.
(2)Notwithstanding Section 10231.5 of the Government Code, the requirement for submitting a report imposed under subdivision (d) is inoperative on July 1 of the year following the submission of the final report upon completion of the fourth project of the department that uses the Construction Manager/General Contractor method.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
|
Date
|
Status
|
|---|---|
| May 19, 2016 | Referred to Com. on T. & H. |
| Aug 25, 2016 | Enrolled and presented to the Governor at 5 p.m. |
| Aug 19, 2016 | In Assembly. Ordered to Engrossing and Enrolling. |
| Aug 18, 2016 | Read third time. Passed. Ordered to the Assembly. (Ayes 36. Noes 0.). |
| Aug 18, 2016 | Read third time. Passed. Ordered to the Assembly. (Ayes 36. Noes 0. Page 5139.). |
| Aug 18, 2016 | Read third time. Passed. Ordered to the Assembly. |
| Aug 11, 2016 | Ordered to special consent calendar. |
| Aug 3, 2016 | Read second time. Ordered to third reading. |
| Aug 2, 2016 | From committee: Do pass. (Ayes 7. Noes 0.) (August 1). |
| Jun 22, 2016 | From committee: Do pass and re-refer to Com. on APPR. with recommendation: To Consent Calendar. (Ayes 11. Noes 0.) (June 21). Re-referred to Com. on APPR. |
| Feb 17, 2016 | Read first time. To print. |
| May 9, 2016 | Read third time. Passed. Ordered to the Senate. (Ayes 77. Noes 0. Page 4718.) |
| May 9, 2016 | Read third time. Passed. Ordered to the Senate. |
| May 9, 2016 | In Senate. Read first time. To Com. on RLS. for assignment. |
| Apr 28, 2016 | Read second time. Ordered to third reading. |
| Apr 27, 2016 | From committee: Do pass. (Ayes 19. Noes 0.) (April 27). |
| Apr 12, 2016 | From committee: Do pass and re-refer to Com. on APPR. (Ayes 16. Noes 0.) (April 11). Re-referred to Com. on APPR. |
| Mar 17, 2016 | Referred to Com. on TRANS. |
| Feb 18, 2016 | From printer. May be heard in committee March 19. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Aug 18, 2016 | Special Consent AB2126 Mullin | Senate Floor |
Passed |
|
| Aug 1, 2016 | Do pass | Senate Standing Committee on Appropriations |
Passed |
|
| Jun 21, 2016 | Do pass, but first be re-referred to the Committee on [Appropriations] with the recommendation: To Consent Calendar | Senate Standing Committee on Transportation and Housing |
Passed |
|
| May 9, 2016 | AB 2126 MULLIN Assembly Third Reading | Assembly Floor |
Passed |
|
| Apr 27, 2016 | Do pass. | Assembly Standing Committee on Appropriations |
Passed |
|
| Apr 11, 2016 | Do pass and be re-referred to the Committee on [Appropriations] | Assembly Standing Committee on Transportation |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| Associated General Contractors | ** Support | Aug 1, 2016 |
| Bay Area Council | ** Support | Aug 1, 2016 |
| California Association Of Local Conservation Corps | * Support | Jun 26, 2018 |
| California Forestry Association | * Support | Jun 26, 2018 |
| California Transportation Commission | ** Support | Aug 1, 2016 |
| City | ** Support | Aug 1, 2016 |
| County Association of Governments of San Mateo County | ** Support | Aug 1, 2016 |
| County Association of San Mateo County | ** Support | Apr 11, 2016 |
| Greater Valley Conservation Corps | * Support | Jun 26, 2018 |
| Humboldt Redwood Company | * Support | Jun 26, 2018 |
| Mendocino Redwood Company | * Support | Jun 26, 2018 |
| San Joaquin County Office Of Education | * Support | Jun 26, 2018 |
| San Mateo County Economic Development Association | ** Support | Aug 1, 2016 |
| San Mateo County Transportation Authority | * Support | Aug 1, 2016 |
Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | AB |
THIRD READING
Bill No: AB 2126
:
SENATE TRANS. & HOUSING COMMITTEE: 11-0, 6/21/16
AYES: Beall, Cannella, Allen, Bates, Gaines, Galgiani, Leyva, McGuire, Mendoza, Roth, Wieckowski
SENATE APPROPRIATIONS COMMITTEE: 7-0, 8/1/16
AYES: Lara, Bates, Beall, Hill, McGuire, Mendoza, Nielsen
ASSEMBLY FLOOR: 77-0, 5/9/16 - See last page for vote
DIGEST: This bill increases the number of authorized Construction Manager/General Contractor (CM/GC) projects from six projects to 12, as specified.
Existing law:
- Sets forth provisions governing public works contracting. These provisions generally prohibit public agencies from contracting with the same firm for both the design and the construction phases of a project.
- Requires, generally, public works construction contracts to be awarded to the lowest responsible bidder.
- Describes the CM/GC procurement method and makes legislative findings and declarations regarding benefits related to risk transfer and project phasing using CM/GC.
- Authorizes the California Department of Transportation (Caltrans) to use CM/GC on no more than six projects, at least five of which must have construction costs greater than $10 million.
- Authorizes the Santa Clara County Valley Transportation Authority, the San Mateo County Transit District, and the San Diego Association of Governments to use CM/GC for transit projects.
- Authorizes a regional transportation agency (RTA) to use the CM/GC project delivery method to design and construct projects on expressways that are not on the state highway system if the projects are developed in accordance with an expenditure plan approved by the voters.
- Defines key terms relative to the authority granted to RTAs to use CM/GC, as specified.
- Provides that the entity responsible for maintenance of local streets and roads within the same jurisdiction of the expressway shall be responsible for the maintenance of the expressway.
- Sets forth provisions governing the process for procuring CM/GC services.
This bill expands, from six to 12, the number of projects for which Caltrans is authorized to use the CM/GC procurement method. Further specifies that of the 12 projects, at least 10 projects must have construction costs greater than $10 million and at least eight projects are required to use Caltrans employees or Caltrans consultants, as specified.
Comments
- Purpose. The author notes that “this bill will extend CM/GC authorization by increasing the number of projects that Caltrans can build using CM/GC delivery method from six to 12, thus increasing the opportunities to reduce costs and expedite congestion relief projects in the state.”
- Traditional project delivery. Traditionally, state and local entities develop and construct transportation projects with a process known as the design-bid-build (DBB) delivery method. This method requires the public agency to fully design a project and then ask general contractors to bid on the construction contract based on the agency’s design. DBB procurement results in project risks being largely borne by the agency that designs the project, because the agency bears the financial burden if the plans are inadequate or unanticipated construction issues arise.
- What is CM/GC? The CM/GC project-delivery method allows an agency to engage a construction manager during the design process to provide assistance to the design team, which can ultimately lead to a more constructible project. When design is nearly complete, the agency and the construction manager negotiate a guaranteed maximum price for the construction of the project based on the defined scope and schedule. If this price is acceptable to both parties, they execute a contract for construction services, and the construction manager becomes the general contractor. Studies suggest CM/GC often leads to less costly or more expediently delivered projects because of the construction manager’s involvement in the design process.
- Why pursue alternative project delivery approaches? For decades, state and local agencies have relied on the DBB procurement method for transportation projects. DBB reduces the risk for the construction contractor because the state or local agency has a completed design, procured right-of-way, and achieved environmental clearance before letting the contract. Agencies using this traditional method generally receive the lowest initial-cost construction contracts for a given project, because contractors are competitively bidding on a relatively risk-free project. Drawbacks to DBB can include longer completion times, constructability challenges unforeseen by the designers, and increasing costs over time due to change orders and claims.
The CM/GC process is meant to provide continuity and collaboration between the design and construction phases of the project. Construction managers have an incentive to provide input during the design phase that will enhance constructability of the project later, because they know that they will have the opportunity to become the general contractor for the project. Furthermore, CM/GC promises to save project delivery time, provide earlier cost certainty, transfer some risks from the public agency to the contractor, and ensure project constructability. Finally, it allows each agency to design the project to complement the general contractor’s strengths and capabilities, thereby providing maximum competitiveness in a low-bid procurement.
- Prior authorization. AB 2498 (Gordon, Chapter 752, Statutes of 2012) authorized Caltrans to use CM/GC on no more than six projects, at least five of which must have construction costs greater than $10 million. At that time, the author introduced AB 2498 to authorize Caltrans to use CM/GC to start evaluating the effectiveness of this emerging project-delivery method that combined the best of both DBB and design-build. To date, all six authorized slots have been granted and the projects are moving forward to completion. This bill proposes to double the amount of authorized CM/GC projects from six to 12; however, it preserves all the design, engineering, inspection, and reporting requirements established in AB 2498.
FISCAL EFFECT: Appropriation: Fiscal Com.: Local:
According to the Senate Appropriations Committee, unknown project costs or savings related to Caltrans’ expanded authority to use a new project delivery method (State Highway Account and federal funds). Caltrans anticipates significant long term savings, based on the experience of other states, local entities, and early feedback related to the current CM/GC authority. Senate Appropriations staff notes, however, that currently authorized CM/GC projects have not been completed or evaluated for cost efficiency.
In addition, since a contract for preconstruction and construction services for CMGC is a negotiated process with the most qualified construction manager, rather than a traditional “lowest responsible bidder” process, it is difficult to determine whether the negotiated price would be lower or higher than project delivery costs through a traditional DBB process. It is expected that use of the CM/GC method minimizes change orders, which is currently a significant factor in unexpected cost escalation on Caltrans projects.
Associated General Contractors
Bay Area Council
California Transportation Commission
City/County Association of Governments of San Mateo County
San Mateo County Economic Development Association
San Mateo County Transportation Authority
None received
ASSEMBLY FLOOR: 77-0, 5/9/16
AYES: Achadjian, Alejo, Travis Allen, Arambula, Atkins, Baker, Bigelow, Bloom, Bonilla, Bonta, Brough, Brown, Burke, Calderon, Campos, Chang, Chau, Chávez, Chiu, Chu, Cooley, Cooper, Dababneh, Dahle, Daly, Dodd, Eggman, Frazier, Gallagher, Cristina Garcia, Gatto, Gipson, Gomez, Gonzalez, Gordon, Gray, Grove, Hadley, Harper, Roger Hernández, Holden, Irwin, Jones-Sawyer, Kim, Lackey, Levine, Linder, Lopez, Low, Maienschein, Mathis, Mayes, McCarty, Medina, Melendez, Mullin, Nazarian, Obernolte, O'Donnell, Olsen, Patterson, Quirk, Ridley-Thomas, Rodriguez, Salas, Santiago, Steinorth, Mark Stone, Thurmond, Ting, Wagner, Waldron, Weber, Wilk, Williams, Wood, Rendon
NO VOTE RECORDED: Beth Gaines, Eduardo Garcia, Jones
8/3/16 19:26:05
**** END ****
SENATE COMMITTEE ON
Senator Ricardo Lara, Chair
2015 - 2016 Regular Session
AB 2126 (Mullin) - Public contracts: Construction Manager/General Contractor contracts
Version: | Policy Vote: |
Urgency: | Mandate: |
Hearing Date: | Consultant: |
This bill may meet the criteria for referral to the Suspense File.
Bill Summary:
AB 2126 would expand the authority for the Department of Transportation (Caltrans) to use the Construction Manager/General Contractor (CMGC) procurement method. Specifically, the bill would double the number of projects that may be constructed using CMGC from six to12, as specified.
Fiscal Impact:
Unknown project costs or savings related to Caltrans’ expanded authority to use a new project delivery method (State Highway Account and federal funds). Caltrans anticipates significant long term savings, based on the experience of other states, local entities, and early feedback related to the current CMGC authority. Staff notes, however, that currently authorized CMGC projects have not been completed or evaluated for cost efficiency. (see staff comments)
In addition, since a contract for preconstruction and construction services for CMGC is a negotiated process with the most qualified construction manager, rather than a traditional “lowest responsible bidder” process, it is difficult to determine whether the negotiated price would be lower or higher than project delivery costs through a traditional design-bid-build process. It is expected that use of the CMGC method minimizes change orders, which is currently a significant factor in unexpected cost escalation on Caltrans projects.
Background:
The traditional project delivery process is the design-bid-build method, whereby complete plans and specifications are prepared prior to the advertising, bidding, and awarding of any construction contracts. The agency awards the contract to the lowest responsible bidder. Although this method is structured to ensure a project is built for the lowest cost, oftentimes project costs escalate dramatically as change orders are necessary to address unforeseen problems encountered during the construction phase. In addition, the bulk of project risk remains with the sponsoring agency.
In recent years, public agencies have adopted alternative project delivery methods, including design-build, design-sequencing, and CMGC. The principle reasons for using alternate methods are to shift construction risk from the agency/owner to the project contractor, minimize change order and cost escalation, and to expedite project completion.
The CMGC project delivery method allows an agency to engage a construction manager during the design process to provide assistance to the design team, including advice regarding scheduling, pricing, phasing, and other input that helps the owner design a more constructible project. The agency selects the construction manager on the basis of qualifications, past experience, or a best-value basis. According to the Federal Highway Administration, when design reaches approximately 60 to 90 percent completion, the agency and the construction manager negotiate a guaranteed maximum price for the construction of the project based on the defined scope and schedule. If this price is acceptable to both parties, a contract is executed for construction services, and the construction manager becomes the general contractor. The benefits of this procurement method are that the public agency does not sacrifice control over the design of the project and the contractor is familiar with the project design during the construction phase, resulting in fewer change orders and disputes over design issues.
Existing law authorizes Caltrans to use the CMGC method on no more than six projects, five of which must have construction costs of over $10 million. On at least four of the projects, Caltrans must use Caltrans employees or consultants under contract with the department for project design and engineering services. In addition, Caltrans must use its own employees or consultants to perform all construction inspection services. The existing CMGC authorization requires annual reports that provide data on the stage of completion, the district, costs, description, status, and estimated time to completion. Once projects are completed, the annual reports must also include information on the differences between initial cost estimates and actual costs, estimated and actual dates of completion, the reason for any differences, and the number and dollar value of any change orders for all projects completed using CMGC.
Proposed Law:
AB 2126 would increase the number of projects, from six to 12, for which Caltrans may use the CMGC procurement method. The bill also requires at least 10 of the projects to have construction costs of over $10 million and requires at least eight projects to use Caltrans employees or contracted consultants for project design and engineering services, as specified.
Related Legislation:
AB 2498 (Gordon), Chap. 752/2012, authorized Caltrans to use CMGC on up to six projects, five of which must have costs of at least $10 million.
Staff Comments:
The Legislature has generally taken a measured approach to authorizing the use of new project delivery methods. This usually involves some limited authorization initially, either through a fixed number of projects or period of time, which provides the opportunity for evaluation through data collection and analysis. Caltrans has selected projects and construction managers for all six projects authorized under current law, with estimated costs ranging from $52 million to $606 million, and estimated completion dates from March 2018 through Summer of 2020. Contracts have been awarded for parts of three of the projects and are under construction, while the other three are in the preconstruction phase. To date only one construction package related to one of the projects has been completed (San Francisco/Oakland Bay Bridge Foundation Removal).
Caltrans anticipates it will realize substantial savings through the use of CMGC on these projects. Since no projects have been completed, however, Caltrans has not reported on the differences between estimated and actual costs, estimated and actual completion dates, or the number of change orders. Absent this data, it is unclear whether total projects costs will be higher or lower than estimated costs, whether CMGC results in accelerated project delivery, or whether CMGC project delivery costs would be lower than project costs under the design-bid-build method. The Committee may wish to consider whether it is prudent to expand CMGC authority until the Legislature has adequate data to evaluate the pilot program.
-- END --
SENATE COMMITTEE ON TRANSPORTATION AND HOUSING
Senator Jim Beall, Chair
2015 - 2016 Regular
Bill No: AB 2126 Hearing Date: 6/21/ 2016
Author: | Mullin | ||
Version: | 2/17/2016 | ||
Urgency: | No | Fiscal: | Yes |
Consultant: | Manny Leon | ||
SUBJECT: Public contracts: Construction Manager/General Contractor contracts
DIGEST: This bill increases the number of authorized Construction Manager/General Contractor (CM/GC) projects from six projects to twelve, as specified.
ANALYSIS:
Existing law:
- Sets forth provisions governing public works contracting. These provisions generally prohibit public agencies from contracting with the same firm for both the design and the construction phases of a project.
- Generally requires public works construction contracts to be awarded to the lowest responsible bidder.
- Describes the CM/GC procurement method and makes legislative findings and declarations regarding benefits related to risk transfer and project phasing using CM/GC.
- Authorizes the California Department of Transportation (Caltrans) to use CM/GC on no more than six projects, at least five of which must have construction costs greater than $10 million.
- Authorizes the Santa Clara County Valley Transportation Authority, the San Mateo County Transit District, and the San Diego Association of Governments to use CM/GC for transit projects.
- Authorizes a regional transportation agency (RTA) to use the CM/GC project delivery method to design and construct projects on expressways that are not on the state highway system if the projects are developed in accordance with an expenditure plan approved by the voters.
- Defines key terms relative to the authority granted to RTA’s to use CM/GC, as specified.
- Provides that the entity responsible for maintenance of local streets and roads within the same jurisdiction of the expressway shall be responsible for the maintenance of the expressway.
- Sets forth provisions governing the process for procuring CM/GC services.
This bill expands, from six to 12, the number of projects for which Caltrans is authorized to use the CM/GC procurement method. Further specifies that of the 12 projects, at least 10 projects must have construction costs greater than $10 million and at least eight projects are required to use Caltrans employees or Caltrans consultants, as specified.
COMMENTS:
- Purpose. The author notes that “this bill will extend CM/GC authorization by increasing the number of projects that Caltrans can build using CM/GC delivery method from six to twelve, thus increasing the opportunities to reduce costs and expedite congestion relief projects in the state.”
- Traditional project delivery. Traditionally, state and local entities develop and construct transportation projects with a process known as the design-bid-build (DBB) delivery method. This method requires the public agency to fully design a project and then ask general contractors to bid on the construction contract based on the agency’s design. DBB procurement results in project risks being largely borne by the agency that designs the project, because the agency bears the financial burden if the plans are inadequate or unanticipated construction issues arise.
- What is CM/GC? The CM/GC project-delivery method allows an agency to engage a construction manager during the design process to provide assistance to the design team, which can ultimately lead to a more constructible project. When design is nearly complete, the agency and the construction manager negotiate a guaranteed maximum price for the construction of the project based on the defined scope and schedule. If this price is acceptable to both parties, they execute a contract for construction services, and the construction manager becomes the general contractor. Studies suggest CM/GC often leads to less costly or more expediently delivered projects because of the construction manager’s involvement in the design process.
- Why pursue alternative project delivery approaches? For decades, state and local agencies have relied on the DBB procurement method for transportation projects. DBB reduces the risk for the construction contractor because the state or local agency has a completed design, procured right-of-way, and achieved environmental clearance before letting the contract. Agencies using this traditional method generally receive the lowest initial-cost construction contracts for a given project, because contractors are competitively bidding on a relatively risk-free project. Drawbacks to DBB can include longer completion times, constructability challenges unforeseen by the designers, and increasing costs over time due to change orders and claims.
The CM/GC process is meant to provide continuity and collaboration between the design and construction phases of the project. Construction managers have an incentive to provide input during the design phase that will enhance constructability of the project later, because they know that they will have the opportunity to become the general contractor for the project. Furthermore, CM/GC promises to save project delivery time, provide earlier cost certainty, transfer some risks from the public agency to the contractor, and ensure project constructability. Finally, it allows each agency to design the project to complement the general contractor’s strengths and capabilities, thereby providing maximum competitiveness in a low-bid procurement.
- Prior authorization. AB 2498 (Gordon, Chapter 752, Statutes of 2012) authorized Caltrans to use CM/GC on no more than six projects, at least five of which must have construction costs greater than $10 million. At that time, the author introduced AB 2498 to authorize Caltrans to use CM/GC to start evaluating the effectiveness of this emerging project-delivery method that combined the best of both design-bid-build and design-build. To date, all six authorized slots have been granted and the projects are moving forward to completion. This bill proposes to double the amount of authorized CM/GC projects from six to twelve; however, preserves all the design, engineering, inspection, and reporting requirements established in AB 2498.
- Current status. Regarding current CMGC projects underway, while none of the projects have yet been completed, no significant problems have been reported. As these projects move toward completion, a more thorough examination of the advantages and disadvantages of CM/GC contracting will be required. However, as the pros and cons continue to be evaluated; utilizing CM/GC for various types of transportation projects may be beneficial for evaluation purposes.
Related Legislation:
AB 2374 (Chiu) — extends existing authority for regional transportation agencies to use the CM/GC procurement method to include ramp projects that are not on the state highway system, as specified. AB 2374 will be heard by the Committee at the same hearing as AB 2126.
AB 1171 (Linder, Chapter 413, Statutes of 2015) — provided limited authority for regional transportation agencies to use CM/GC on expressway projects that are not on the state highway system but are in sales tax measure expenditure plans.
AB 1724 (Frazier, 2014) — would have granted regional transportation agencies broad authority to use CM/GC. This bill was held in this committee.
AB 2498 (Gordon, Chapter 752, Statutes of 2012) — authorized Caltrans to use CM/GC on no more than six projects, at least five of which must have construction costs greater than $10 million.
SB 1549 (Vargas, Chapter 767, Statutes of 2012) — authorized SANDAG to use CM/GC contracting on transit projects.
AB 797 (Gordon, Chapter 320, Statutes of 2013) — authorized the VTA and the San Mateo County Transit District to use CM/GC contracting on transit projects.
FISCAL EFFECT: Appropriation: Fiscal Com.: Local:
Assembly votes:
Floor: 77-0
Appr: 19-0
Trans: 16-0
POSITIONS: (Communicated to the committee before noon on Wednesday,
June 15, 2016.)
SUPPORT:
Associated General Contractors
Bay Area Council
City/County Association of Governments of San Mateo County
California Transportation Commission
San Mateo County Economic Development Association
San Mateo County Transportation Authority
OPPOSITION:
None received
-- END --
ASSEMBLY THIRD READING
ATR Bill Id:AB 2126
Author:(Mullin)
As Introduced Ver:February 17, 2016
Majority vote
Committee | Votes | Ayes | Noes |
Transportation | 16-0 | Frazier, Linder, Baker, Bloom, Brown, Chu, Daly, Dodd, Eduardo Garcia, Gomez, Kim, Mathis, Medina, Melendez, Nazarian, O'Donnell | |
Appropriations | 19-0 | Gonzalez, Bigelow, Bloom, Bonilla, Bonta, Calderon, Chang, Daly, Eggman, Gallagher, Eduardo Garcia, Holden, Jones, Obernolte, Quirk, Santiago, Wagner, Weber, Wood |
|
SUMMARY: Expands from six to 12 the number of projects for which the California Department of Transportation (Caltrans) is authorized to use the Construction Manager/General Contractor (CMGC) procurement method. Of the 12 projects, at least 10 projects have to have construction costs greater than $10 million and at least eight projects have to use Caltrans employees or Caltrans consultants.
FISCAL EFFECT: According to the Assembly Appropriations Committee, based on Caltrans experience to date, potential significant savings could be realized from additional CMGC projects.
COMMENTS: For decades, the traditional process for procuring public works projects has been the design-bid-build process. This process relies on the project owner: 1) preparing, or causing to be prepared, complete project design specifications and estimates; 2) putting the complete package out to bid for construction; and 3) awarding the construction contract to the lowest responsible bidder. The design-bid-build process was developed to protect taxpayers from extravagance, corruption, and other improper practices by public officials as well as to secure a fair and reasonable price for public works construction by injecting competition amongst bidders into the process.
In the early 1990s, public works agencies grew frustrated with design-bid-build and began experimenting with more innovative project delivery methods, namely design-build. Design-build is an alternate method for procuring design and construction services that provides for the delivery of public works projects from a single entity. Design-build combines project design, permit, and construction schedules in order to streamline the traditional design-bid-build environment.
The CMGC process, as provided for in this bill, is yet another method of contracting that provides continuity and collaboration between the design and construction phases of the project. Construction managers have an incentive to provide input during the design phase that will enhance constructability of the project later because they know that they will have the opportunity to become the general contractor for the project. Furthermore, CMGC promises to save project delivery time, provide earlier cost certainty, transfer risks from the department to the contractor, and ensure project constructability. Additionally, CMGC allows Caltrans to have greater control of design decisions. It also allows the department to design the project to compliment the CMGC's strengths and capabilities, thereby avoiding the need to over-design the project to provide maximum competitiveness in a low-bid procurement.
There are potential drawbacks of using CMGC contracts. According to guidance published by the City of Seattle, CMGC contracts carry risks, including:
- They are difficult and complex.
- The procurement process takes longer and consumes greater project staff time than traditional design-bid-build contracts.
- Project teams face steep learning curves.
- Successful construction cost negotiations require experienced staff.
Other literature on the use of CMGC contracts is generally consistent with Seattle's guidance regarding concerns for risks associated with CMGC contracts and cautions that CMGC is not appropriate for every project. However, the same literature suggests that, if carefully implemented, CMGC has the potential to significantly improve project delivery.
This bill increases the number of projects for which Caltrans can use CMGC from 6 to 12. The author introduced the bill to increase the opportunities to reduce costs and expedite highway congestion relief projects in the state.
Committee comments: As a part of the authority granted in AB 2498 (Gordon), Chapter 752, Statutes of 2012, Caltrans is required to report each year on the progress of its CMGC contracts. Last year, Caltrans reported that, although it was still early in the process, it appears that the department will realize substantial savings through the use of CMGC on these projects. These early indications are consistent with those reported by other transportation agencies that have been granted statutory authority to use CMGC in recent years. Consequently, modestly increasing the number of projects for which Caltrans can gain additional experience with the use of CMGC seems reasonable and prudent.
Please see the policy committee analysis for full discussion of this bill.
Analysis Prepared by: Janet Dawson / TRANS. / (916) 319-2093 FN: 0002824
Date of Hearing: April 27, 2016
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Lorena Gonzalez, Chair
ABPCA Bill Id:AB 2126
Author:(Mullin) – As Introduced Ver:February 17, 2016
Policy Committee: | Transportation | Vote: | 16 - 0 |
|
|
Urgency: No State Mandated Local Program: Yes Reimbursable: No
SUMMARY:
This bill expands from 6 to 12 the number of projects for which the Caltrans is authorized to use the Construction Manager/General Contractor (CM/GC) procurement method. Of the 12 projects, at least 10 projects must have construction costs greater than $10 million and at least 8 projects must use Caltrans employees or Caltrans consultants to provide project design and engineering services.
FISCAL EFFECT:
Based on Caltrans experience to date, potential significant savings could be realized from additional CM/GC projects.
Caltrans indicates that a project manager has been procured for the six currently authorized CM/CG projects, which range in value from $50 million to $600 million. According to Caltrans, use of this method has allowed the department to partner with contractors to identify risks and in many cases eliminate those risks when designing the projects. To date, comments from the industry have been very positive and supportive of the pilot program, and Caltrans is currently estimating project savings of 10% from using CM/GC.
COMMENTS:
- Background and Purpose. The traditional public works contracting method is known as design-bid-build, whereby project design is done under contract by an architectural/engineering firm (or in Caltrans' case, mainly in-house), then upon completion of the design phase, the construction phase is put out to bid and the contract is awarded to the lowest responsible bidder.
In the last 15 years, the state has selectively used an alternative contracting method known as design/build, whereby entities with both design and construction management capabilities compete for a single contract for both project phases, typically for a fixed price. The intent of the design/build alternative is to reduce the contracting agency's risk with regard to project costs and schedule, expedite project completion, and minimize change orders and claims. Design/build has some drawbacks, however, including that the contracting agency relinquishes significant control the details of project design. In addition, at the point when the design/build entity bids on a project, there are still many unknowns, and thus a degree of risk, which are factored into their bids. Therefore, even though the contracting agency is transferring risk, they are still paying for it in some manner.
Use of CM/GC seeks to achieve the best of both worlds, i.e maintaining design control while minimizing overall risk. Under CM/GC, Caltrans performs the design in-house, thus maintaining control, but rather than designing in a vacuum, this work is done in partnership with the construction firm that has the right of first refusal to construct the project, assuming a mutually agreed upon price can be negotiated. The design progresses to a significant stage of completion prior to negotiating a final price, so that rather than just transferring risk, which Caltrans still pays for in the bid, CM/GC can actually mitigate much of the risk from the eventual project cost.
- Purpose. AB 2498 (Gordon), Chapter 752, Statutes of 2012, authorized Caltrans to use CMGC on no more than six projects, at least five of which must have construction costs greater than $10 million. AB 2126 increases the number of projects for which Caltrans can use CMGC from 6 to 12. The author seeks to increase the opportunities to reduce costs and expedite highway congestion relief projects in the state.
- Related Legislation. The Administration is proposing trailer bill language that would increase from 6 to 12 the number of contracts for which Caltrans can use CMGC. As implementation of the budget is not dependent on enacting such a change, consideration of this policy is more appropriate through AB 2126 and the legislative bill process.
Analysis Prepared by: Chuck Nicol / APPR. / (916) 319-2081
Date of Hearing: April 11, 2016
ASSEMBLY COMMITTEE ON TRANSPORTATION
Jim Frazier, Chair
ABPCA Bill Id:AB 2126 (
Author:Mullin) – As Introduced Ver:February 17, 2016
SUBJECT: Public contracts: Construction Manager/General Contractor contracts
SUMMARY: Expands from 6 to 12 the number of projects for which the California Department of Transportation (Caltrans) is authorized to use the Construction Manager/General Contractor (CMGC) procurement method. Of the 12 projects, at least 10 projects have to have construction costs greater than $10 million and at least 8 projects have to use Caltrans employees or Caltrans consultants.
EXISTING LAW:
- Sets forth provisions governing public works contracting. These provisions generally prohibit public agencies from contracting with the same firm for both the design and the construction phases of a project.
- Generally requires public works construction contracts to be awarded to the lowest responsible bidder.
- Describes the CMGC procurement method and makes legislative findings and declarations regarding benefits related to risk transfer and project phasing using CMGC.
- Authorizes the Caltrans to use CMGC on no more than six projects, at least five of which must have construction costs greater than $10,000,000, and at least four of which have to use Caltrans employees or Caltrans consultants.
- Defines key terms as follows relative to authority granted to Caltrans to use CMGC:
- "Construction manager/general contractor method" to mean a project delivery method in which a construction manager is procured to provide preconstruction services during the design phase of the project and construction services during the construction phase of the project. The contract for construction services may be entered into at the same time as the contract for preconstruction services, or at a later time. The execution of the design and the construction of the project may be in sequential phases or concurrent phases;
- "Preconstruction services" to mean advice given during the design phase of a project related to, for example, scheduling, pricing, and phasing to assist the department design a more constructible project; and,
- "Project" to mean the construction of a highway, bridge, or tunnel.
- Sets forth provisions governing the process for procuring CMGC services.
FISCAL EFFECT: Unknown
COMMENTS: For decades, the traditional process for procuring public works projects has been the design-bid-build process. This process relies on the project owner: 1) preparing, or causing to be prepared, complete project design specifications and estimates; 2) putting the complete package out to bid for construction; and 3) awarding the construction contract to the lowest responsible bidder. The design-bid-build process was developed to protect taxpayers from extravagance, corruption, and other improper practices by public officials as well as to secure a fair and reasonable price for public works construction by injecting competition amongst bidders into the process.
Although design-bid-build generally results in the lowest cost construction contract, it is not without its drawbacks, including:
- Projects generally take longer to complete because designs must be entirely completed, permits obtained, and right-of-way acquired before the construction contract can be bid and awarded.
- Designs prepared for a competitive low-bid procurement are developed to allow for a broad range of construction approaches. As a result, low-bid designs do not always equate to the most efficient designs possible, depending on a particular contractor's strengths or capabilities.
- Because the project designer does not have the benefit of consulting with the entity that will ultimately be responsible for construction of the project, there may be significant issues that the designer does not anticipate, particularly constructability issues. This can result in change orders that ultimately drive up the price of the contract.
- Low-bid is not always the least expensive option, once change orders and contractor claims are factored into the overall project costs.
In the early 1990s, public works agencies grew frustrated with design-bid-build and began experimenting with more innovative project delivery methods, namely design-build. Design-build is an alternate method for procuring design and construction services that provides for the delivery of public works projects from a single entity. Design-build combines project design, permit, and construction schedules in order to streamline the traditional design-bid-build environment.
Design-build differs from design-bid-build in some key areas, including:
- Overall elapsed project delivery times are shorter because construction can begin before final design is complete.
- Project costs and schedule risks are more heavily borne by the design-build contractor.
- Construction claims and change orders are minimized.
- Designs can be developed to take advantage of a particular contractor's strengths and abilities, thereby reducing the need to "over-design" for generic use as in design-bid-build.
- Project specifications are typically based on definitive performance criteria, which may or may not be well established by the project owner, rather than established specifications.
- Contracts are awarded based on best-value analyses rather than low-bid.
Design-build contracts are not without their drawbacks as well. For example, with a design-build project, the project owner must give up a good deal of control over the details of the project design. Additionally, design-build contractors are typically selected using qualifications-based selection criteria or best value analysis. These approaches are more subjective than a low-bid approach, potentially subjecting the public works owner to greater contract challenges and higher costs.
In 2012, AB 2498 (Gordon), Chapter 752, Statutes of 2012, authorized Caltrans to use CMGC on no more than six projects, at least five of which must have construction costs greater than $10 million. CMGC is an emerging project delivery method that potentially combines the best of both design-bid-build and design-build. Using CMGC, Caltrans can engage a design and construction management consultant (construction manager) to act as its consultant during the pre-construction phase and as the general contractor during construction. During the design phase, the construction manager acts in an advisory role, providing constructability reviews, value engineering suggestions, construction estimates, and other construction-related recommendations. Later, Caltrans and the construction manager can agree that the project design has progressed to a sufficient enough point that construction may begin. The two parties then work out mutually agreeable terms and conditions for the construction contract, and, if all goes well, the construction manager becomes the general contractor and construction on the project commences, well before design is entirely complete.
The CMGC process provides continuity and collaboration between the design and construction phases of the project. Construction managers have an incentive to provide input during the design phase that will enhance constructability of the project later because they know that they will have the opportunity to become the general contractor for the project. Furthermore, CMGC promises to save project delivery time, provide earlier cost certainty, transfer risks from the department to the contractor, and ensure project constructability. Additionally, CMGC allows Caltrans to have greater control of design decisions. It also allows the department to design the project to compliment the CMGC's strengths and capabilities, thereby avoiding the need to over-design the project to provide maximum competitiveness in a low-bid procurement.
There are potential drawbacks of using CMGC contracts. According to guidance published by the City of Seattle, CMGC contracts carry risks, including:
- They are difficult and complex.
- The procurement process takes longer and consumes greater project staff time than traditional design-bid-build contracts.
- Project teams face steep learning curves.
- Successful construction cost negotiations require experienced staff.
Other literature on the use of CMGC contracts is generally consistent with Seattle's guidance regarding concerns for risks associated with CMGC contracts and cautions that CMGC is not appropriate for every project. However, the same literature suggests that, if carefully implemented, CMGC has the potential to significantly improve project delivery.
AB 2126 increases the number of projects for which Caltrans can use CMGC from 6 to 12. The author introduced the bill to increase the opportunities to reduce costs and expedite highway congestion relief projects in the state.
Committee comments: As a part of the authority granted in AB 2498, Caltrans is required to report each year on the progress of its CMGC contracts. Last year, Caltrans reported that, although it was still early in the process, it appears that the department will realize substantial savings through the use of CMGC on these projects. These early indications are consistent with those reported by other transportation agencies that have been granted statutory authority to use CMGC in recent years. Consequently, modestly increasing the number of projects for which Caltrans can gain additional experience with the use of CMGC seems reasonable and prudent.
Related legislation: The Administration is proposing trailer bill language that would increase from 6 to 12 the number of contracts for which Caltrans can use CMGC.
AB 2374 (Chiu), Extends existing authority for regional transportation agencies to use the CMGC procurement method to include ramp projects that are not on the state highway system and removes the limitation that a CMGC project is in a sales tax measure expenditure plan.
Previous legislation: AB 2498 (Gordon), Chapter 752, Statutes of 2012, authorized Caltrans to use CMGC on no more than six projects, at least five of which must have construction costs greater than $10 million.
REGISTERED SUPPORT / OPPOSITION:
Support
Associated General Contractors
Bay Area Council
California Transportation Commission
City/County Association of San Mateo County
San Mateo County Economic Development Association
Opposition
None on file
Analysis Prepared by: Janet Dawson / TRANS. / (916) 319-2093
Discussed in Hearing
Senate Standing Committee on Natural Resources and Water
Senate Standing Committee on Appropriations
Assembly Floor
Assembly Standing Committee on Appropriations
Senate Standing Committee on Transportation and Housing
Bill Author
Bill Co-Author(s):