AB 2861: Electricity: distribution grid interconnection dispute resolution process.
- Session Year: 2015-2016
- House: Assembly
Existing law places various duties upon the Public Utilities Commission with respect to distributed generation and requires each electrical corporation to submit to the commission for its approval a distribution resources plan proposal to identify optimal locations for the deployment of distributed resources, as defined. Pursuant to existing law, the commission has established operational and metering requirements for a generation facility to be interconnected to an electrical corporations distribution grid.
This bill would authorize the commission to establish an expedited distribution grid interconnection dispute resolution process, as specified, with the goal of resolving disputes over interconnection applications within the jurisdiction of the commission in no more than 60 days from the time the dispute is formally brought to the commission. The bill would require the commission to appoint a qualified electrical systems engineer with substantial interconnection expertise to advise the director of the energy division and to provide adequate commission staff to assist in resolving interconnection disputes.
Discussed in Hearing
Assembly Floor
Senate Floor
Assembly Floor
Assembly Standing Committee on Utilities and Commerce
Bill Author