AB 3265: California Environmental Quality Act: environmental leadership media campus projects: judicial streamlining.
- Session Year: 2023-2024
- House: Assembly
- Latest Version Date: 2024-09-14
Current Status:
Passed
(2024-09-14: Chaptered by Secretary of State - Chapter 255, Statutes of 2024.)
Introduced
In Committee
First Chamber
In Committee
Second Chamber
Enacted
The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of an environmental impact report (EIR) on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment. CEQA establishes administrative procedures for the review and certification of the EIR for a project and judicial review procedures for any action or proceeding brought to challenge the lead agencys decision to certify the EIR or to grant project approvals.
This bill would establish streamlined procedures for the administrative and judicial review of the environmental review and approvals granted for an environmental leadership media campus project, defined by the bill as a construction or renovation project on a film and television media campus in the County of Los Angeles, under certain conditions. The bill would require a city within the County of Los Angeles that is the lead agency for an environmental leadership media campus project to certify the project for the streamlined judicial review, as specified, if the lead agency finds the project will meet those conditions. The bill would require the project applicant of the environmental leadership media campus project to take certain actions in order for those specified procedures to apply to the project. The bill would require the Judicial Council, on or before July 1, 2025, to adopt rules of court establishing procedures requiring actions or proceedings seeking judicial review of the certification of an environmental impact report for an environmental leadership media campus project or the granting of any project approval, including any appeals to the court of appeal or the Supreme Court, to be resolved, to the extent feasible, within 365 calendar days of the filing of the certified record of proceedings with the court. The bill would require the lead agency to prepare the EIR for an environmental leadership media campus project in a specified manner and would require the concurrent preparation of the record of proceedings.
Because the bill would impose additional duties on a lead agency and on a local agency, this bill would impose a state-mandated local program.
This bill would make legislative findings and declarations as to the necessity of a special statute for the County of Los Angeles.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of an environmental impact report (EIR) on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment. CEQA establishes administrative procedures for the review and certification of the EIR for a project and judicial review procedures for any action or proceeding brought to challenge the lead agencys decision to certify the EIR or to grant project approvals.
This bill would establish streamlined procedures for the administrative and judicial review of the environmental review and approvals granted for an environmental leadership media campus project, defined by the bill as a construction or renovation project on a film and television media campus in the County of Los Angeles, under certain conditions. The bill would require a city within the County of Los Angeles that is the lead agency for an environmental leadership media campus project to certify the project for the streamlined judicial review, as specified, if the lead agency finds the project will meet those conditions. The bill would require the project applicant of the environmental leadership media campus project to take certain actions in order for those specified procedures to apply to the project. The bill would require the Judicial Council, on or before July 1, 2025, to adopt rules of court establishing procedures requiring actions or proceedings seeking judicial review of the certification of an environmental impact report for an environmental leadership media campus project or the granting of any project approval, including any appeals to the court of appeal or the Supreme Court, to be resolved, to the extent feasible, within 365 calendar days of the filing of the certified record of proceedings with the court. The bill would require the lead agency to prepare the EIR for an environmental leadership media campus project in a specified manner and would require the concurrent preparation of the record of proceedings.
Because the bill would impose additional duties on a lead agency and on a local agency, this bill would impose a state-mandated local program.
This bill would make legislative findings and declarations as to the necessity of a special statute for the County of Los Angeles.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of an environmental impact report (EIR) on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment. CEQA establishes administrative procedures for the review and certification of the EIR for a project and judicial review procedures for any action or proceeding brought to challenge the lead agencys decision to certify the EIR or to grant project approvals.
This bill would establish streamlined procedures for the administrative and judicial review of the environmental review and approvals granted for an environmental leadership media campus project, defined by the bill as a construction or renovation project on a film and television media campus in the County of Los Angeles, under certain conditions. The bill would require a city within the County of Los Angeles that is the lead agency for an environmental leadership media campus project to certify the project for the streamlined judicial review, as specified, if the lead agency finds the project will meet those conditions. The bill would require the project applicant of the environmental leadership media campus project to take certain actions in order for those specified procedures to apply to the project. The bill would require the Judicial Council, on or before July 1, 2025, to adopt rules of court establishing procedures requiring actions or proceedings seeking judicial review of the certification of an environmental impact report for an environmental leadership media campus project or the granting of any project approval, including any appeals to the court of appeal or the Supreme Court, to be resolved, to the extent feasible, within 365 calendar days of the filing of the certified record of proceedings with the court. The bill would require the environmental leadership media campus project to meet certain labor requirements. The bill would require the lead agency to prepare the EIR for an environmental leadership media campus project in a specified manner and would require the concurrent preparation of the record of proceedings. Because the bill would impose additional duties on a lead agency and on a local agency, this bill would impose a state-mandated local program.
This bill would make legislative findings and declarations as to the necessity of a special statute for the County of Los Angeles.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of an environmental impact report (EIR) on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment. CEQA establishes administrative procedures for the review and certification of the EIR for a project and judicial review procedures for any action or proceeding brought to challenge the lead agencys decision to certify the EIR or to grant project approvals.
This bill would establish streamlined procedures for the administrative and judicial review of the environmental review and approvals granted for an environmental leadership media campus project, defined by the bill as a construction or renovation project on a film and television media campus in the County of Los Angeles, under certain conditions. The bill would require a city within the County of Los Angeles that is the lead agency for an environmental leadership media campus project to certify the project for the streamlined judicial review, as specified, if the lead agency finds the project will meet those conditions. The bill would require the project applicant of the environmental leadership media campus project to take certain actions in order for those specified procedures to apply to the project. The bill would require the Judicial Council, on or before July 1, 2025, to adopt rules of court establishing procedures requiring actions or proceedings seeking judicial review of the certification of an environmental impact report for an environmental leadership media campus project or the granting of any project approval, including any appeals to the court of appeal or the Supreme Court, to be resolved, to the extent feasible, within 365 calendar days of the filing of the certified record of proceedings with the court. The bill would require the environmental leadership media campus project to meet certain labor requirements. The bill would require the lead agency to prepare the EIR for an environmental leadership media campus project in a specified manner and would require the concurrent preparation of the record of proceedings. Because the bill would impose additional duties on a lead agency and on a local agency, this bill would impose a state-mandated local program.
This bill would make legislative findings and declarations as to the necessity of a special statute for the County of Los Angeles.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of an environmental impact report (EIR) on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment. CEQA establishes administrative procedures for the review and certification of the EIR for a project and judicial review procedures for any action or proceeding brought to challenge the lead agencys decision to certify the EIR or to grant project approvals.
This bill would establish specified streamlined procedures for the administrative and judicial review of the environmental review and approvals granted for an environmental leadership media campus project, as defined, and project, defined by the bill as a construction or renovation project on a film and television media campus in the County of Los Angeles, under certain conditions. The bill would require a city within the County of Los Angeles where an environmental leadership media campus project is to be constructed that is the lead agency for an environmental leadership media campus project to certify the project for the streamlined judicial review, as specified, if the lead agency finds the project meets certain will meet those conditions. The bill would require the project applicant of the environmental leadership media campus project to take certain actions in order for those specified procedures to apply to the project. The bill would require the Judicial Council, on or before July 1, 2025, to adopt rules of court establishing procedures requiring actions or proceedings seeking judicial review of the certification of an environmental impact report for an environmental leadership media campus project or the granting of any project approval, including any appeals to the court of appeal or the Supreme Court, to be resolved, to the extent feasible, within 365 calendar days of the filing of the certified record of proceedings with the court to an action or proceeding seeking judicial review of the lead agencys action related to an environmental leadership media campus project. court. The bill would require the environmental leadership media campus project to meet certain labor requirements. The bill would require the lead agency to prepare the EIR for an environmental leadership media campus project in a specified manner and would require the concurrent preparation of the record of proceedings. Because the bill would impose additional duties on a lead agency and on a local agency, this bill would impose a state-mandated local program.
This bill would make legislative findings and declarations as to the necessity of a special statute for the County of Los Angeles.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of an environmental impact report (EIR) on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment. CEQA establishes administrative procedures for the review and certification of the EIR for a project and judicial review procedures for any action or proceeding brought to challenge the lead agencys decision to certify the EIR or to grant project approvals.
This bill would establish specified procedures for the administrative and judicial review of the environmental review and approvals granted for an environmental leadership media campus project, as defined, and would require a city within the County of Los Angeles where an environmental leadership media campus project is to be constructed to certify the project for streamlined judicial review, as specified, if the project meets certain conditions. The bill would require the project applicant of the environmental leadership media campus project to take certain actions in order for those specified procedures to apply to the project. The bill would require the Judicial Council, on or before July 1, 2025, to adopt rules of court establishing procedures requiring actions or proceedings seeking judicial review of the certification of an environmental impact report for an environmental leadership media campus project or the granting of any project approval, including any appeals to the court of appeal or the Supreme Court, to be resolved, to the extent feasible, within 365 calendar days of the filing of the certified record of proceedings with the court to an action or proceeding seeking judicial review of the lead agencys action related to an environmental leadership media campus project. The bill would require the environmental leadership media campus project to meet certain labor requirements. The bill would require the lead agency to prepare the EIR for an environmental leadership media campus project in a specified manner and would require the concurrent preparation of the record of proceedings. Because the bill would impose additional duties on a lead agency and on a local agency, this bill would impose a state-mandated local program.
This bill would make legislative findings and declarations as to the necessity of a special statute for the County of Los Angeles.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
(a)The Legislature finds and declares all of the following:
(1)The entertainment industry is a rich part of Californias history and the state is committed to retaining its status as the worlds film and television production capital.
(2)Attractive tax credit incentives from other states and countries to produce film and television are on the rise.
(3)There are large projects under consideration that would replace old and outmoded facilities, use innovative technologies, and help the state meet the increased demand for film and television production.
(4)These projects will generate thousands of full-time construction jobs and thousands more of permanent jobs once constructed and operating.
(5)New construction and renovation at California media production campuses can provide environmental benefits.
(b)It is the intent of the Legislature to incentivize construction and renovation at Californias media production campuses in order to ensure business and creative success, stimulate the creation of new employment opportunities, and keep the production of film, scripted television, and streaming content in California for decades to come.
(c)The Legislature further finds and declares that it is in the interest of the state to expedite judicial review of media production campus construction and renovation projects, as appropriate, while protecting the environment and the rights of the public to review, comment on, and, if necessary, seek judicial review of the adequacy of an environmental impact report for the project.
SEC. 2.Section 21168.6.6 is added to the Public Resources Code, immediately following Section 21168.6, to read:21168.6.6.(a)For purposes of this section, the following terms have the following meanings:
(1)Disadvantaged community means an area identified by the California Environmental Protection Agency pursuant to Section 39711 of the Health and Safety Code or an area that is a disadvantaged unincorporated community pursuant to Section 65302.10 of the Government Code.
(2)Environmental leadership media campus project or project means a construction or renovation project on a film and television media campus in the County of Los Angeles.
(b) A city within the County of Los Angeles that is the lead agency for the project shall certify an environmental leadership media campus project for streamlining pursuant to this section if the lead agency finds that all of the following conditions will be met:
(1)The project will result in an investment of at least one billion dollars ($1,000,000,000) in California upon completion of the construction.
(2)(A)The project will obtain certification as Leadership in Energy and Environmental Design (LEED) gold standard or better from the United States Green Building Council for all new construction that is eligible for LEED certification.
(B)Any new construction or major renovation of existing buildings that is not eligible for LEED certification will achieve comparable standards for energy and water efficiency, including, but not limited to, meeting Tier 1 energy efficiency standards.
(3)The project will achieve a reduction in vehicle miles traveled per capita of at least 15 percent compared to existing development consistent with the Office of Planning and Researchs technical advisory on evaluating transportation impacts in CEQA and at least 50 percent of any greenhouse gas emissions reductions necessary to achieve zero net additional greenhouse gas emissions as required by paragraph (4) will be from onsite and local reduction measures.
(4)The project does not result in any net additional greenhouse gas emissions, including, but not limited to, from employee transportation. A project is deemed to meet the requirements of this paragraph if the project applicant demonstrates to the lead agency that the project applicant has a binding commitment that it will mitigate impacts resulting from the greenhouse gas emissions, if any, in accordance with Section 21183.6.
(5)If measures are required to mitigate significant environmental impacts in a disadvantaged community, those impacts will be mitigated consistent with this division, including Section 21002, and the mitigation measures required under this subdivision will be undertaken in, and directly benefit, the affected community.
(6)The project will generate at least 1,000 jobs during construction.
(7)(A)(i)The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, employs a skilled and trained workforce, as defined in subdivision (d) of Section 2601 of the Public Contract Code, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment. For purposes of this subdivision, jobs that pay prevailing wages means that all construction workers employed in the execution of the project will receive at least the general prevailing rate of per diem wages for the type of work and geographic area, as determined by the Director of Industrial Relations pursuant to Sections 1773 and 1773.9 of the Labor Code. If the project is certified for streamlining, the project applicant shall include this requirement in all contracts for the performance of the work.
(ii)Clause (i) does not apply to a contractor or subcontractor performing the work on the project that is subject to a project labor agreement requiring the payment of prevailing wages to all construction workers employed in the execution of the project and providing for enforcement of that obligation through an arbitration procedure. For purposes of this clause, project labor agreement has the same meaning as set forth in paragraph (1) of subdivision (b) of Section 2500 of the Public Contract Code.
(B)(i)If the project is certified pursuant to this subdivision, contractors and subcontractors shall pay to all construction workers employed in the execution of the project at least the general prevailing rate of per diem wages.
(ii)Except as provided in clause (iii), the obligation of the contractors and subcontractors to pay prevailing wages pursuant to subparagraph (A) may be enforced by the Labor Commissioner through the issuance of a civil wage and penalty assessment pursuant to Section 1741 of the Labor Code, which may be reviewed pursuant to Section 1742 of the Labor Code, within 18 months after the completion of the project, or by an underpaid worker through an administrative complaint or civil action. If a civil wage and penalty assessment is issued, the contractor, subcontractor, and surety on a bond or bonds issued to secure the payment of wages covered by the assessment shall be liable for liquidated damages pursuant to Section 1742.1 of the Labor Code.
(iii)Clause (ii) does not apply if all contractors and subcontractors performing work on the project are subject to a project labor agreement that requires the payment of prevailing wages to all construction workers employed in the execution of the project and provides for enforcement of that obligation through an arbitration procedure. For purposes of this subparagraph, project labor agreement has the same meaning as set forth in paragraph (1) of subdivision (b) of Section 2500 of the Public Contract Code.
(8)The project applicant demonstrates compliance with the requirements of Chapters 12.8 (commencing with Section 42649) and 12.9 (commencing with Section 42649.8) of Part 3 of Division 30, as applicable.
(9)The project applicant agrees that all mitigation measures required pursuant to this division and any other environmental measures required by this section to certify the project under this section shall be conditions of approval of the project, and those conditions will be fully enforceable by the lead agency or another agency designated by the lead agency. In the case of environmental mitigation measures and any other environmental measures required by this section, the project applicant agrees, as an ongoing obligation, that those measures will be monitored and enforced by the lead agency for the life of the obligation. The project applicant shall submit to the lead agency an annual status report on the implementation of the environmental mitigation measures and any other environmental measures required by this section.
(10)The project applicant agrees to pay any additional costs incurred by the courts in hearing and deciding any case subject to this section, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council, as provided in the California Rules of Court adopted by the Judicial Council.
(11)The project applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with review and consideration of the project pursuant to this division, in a form and manner specified by the lead agency for the project.
(c)On or before July 1, 2025, the Judicial Council shall adopt rules of court that apply to any action or proceeding brought to attack, review, set aside, void, or annul the certification of an environmental impact report for an environmental leadership media campus project or the granting of any project approval that requires the action or proceeding, including any potential appeals to the court of appeal or the Supreme Court, to be resolved, to the extent feasible, within 365 calendar days of the filing of the certified record of proceedings with the court.
(d)(1) The draft and final environmental impact report for an environmental leadership media campus project shall include a notice in not less than 12-point type stating the following:
THIS ENVIRONMENTAL IMPACT REPORT IS SUBJECT TO SECTION 21168.6.6 OF THE PUBLIC RESOURCES CODE, WHICH PROVIDES, AMONG OTHER THINGS, THAT THE LEAD AGENCY NEED NOT CONSIDER CERTAIN COMMENTS FILED AFTER THE CLOSE OF THE PUBLIC COMMENT PERIOD, IF ANY, FOR THE DRAFT ENVIRONMENTAL IMPACT REPORT. ANY JUDICIAL ACTION CHALLENGING THE CERTIFICATION OR ADOPTION OF THE ENVIRONMENTAL IMPACT REPORT OR THE APPROVAL OF THE PROJECT DESCRIBED IN SECTION 21168.6.6 OF THE PUBLIC RESOURCES CODE IS SUBJECT TO THE PROCEDURES SET FORTH IN THAT SECTION. A COPY OF SECTION 21168.6.6 OF THE PUBLIC RESOURCES CODE IS INCLUDED IN THE APPENDIX TO THIS ENVIRONMENTAL IMPACT REPORT.
(2)The draft environmental impact report and final environmental impact report shall contain, as an appendix, the full text of this section.
(3)Within 10 calendar days after the release of the draft environmental impact report, the lead agency shall conduct an informational workshop to inform the public of the key analyses and conclusions of that document, as applicable.
(4)Within 10 calendar days before the close of the public comment period, the lead agency shall hold a public hearing to receive testimony on the draft environmental impact report. A transcript of the hearing shall be included as an appendix to the final environmental impact report, as applicable.
(5)(A)Within five calendar days following the close of the public comment period, a commenter on the draft environmental impact report may submit to the lead agency a written request for nonbinding mediation, as applicable. The lead agency shall participate in nonbinding mediation with all commenters who submitted timely comments on the draft environmental impact report and who requested the mediation. Mediation conducted pursuant to this paragraph shall end no later than 35 calendar days after the close of the public comment period.
(B)A request for mediation shall identify all areas of dispute raised in the comment submitted by the commenter that are to be mediated.
(C)The lead agency shall select one or more mediators who shall be retired judges or recognized experts with at least five years experience in land use and environmental law or science, or mediation. The lead agency shall bear the costs of mediation.
(D)A mediation session shall be conducted on each area of dispute with the parties requesting mediation on that area of dispute.
(E)The lead agency shall adopt, as a condition of approval, any measures agreed upon by the lead agency and any commenter who requested mediation. A commenter who agrees to a measure pursuant to this subparagraph shall not raise the issue addressed by that measure as a basis for an action or proceeding challenging the lead agencys decision to certify the environmental impact report or to grant project approval.
(6)The lead agency need not consider written comments on the draft environmental impact report submitted after the close of the public comment period, unless those comments address any of the following:
(A)New issues raised in the response to comments by the lead agency.
(B)New information released by the lead agency subsequent to the release of the draft environmental impact report, such as new information set forth or embodied in a staff report, proposed permit, proposed resolution, ordinance, or similar documents.
(C)Changes made to the project after the close of the public comment period.
(D)Proposed conditions for approval, mitigation measures, or proposed findings required by Section 21081 or a proposed reporting or monitoring program required by paragraph (1) of subdivision (a) of Section 21081.6, if the lead agency releases those documents subsequent to the release of the draft environmental impact report.
(E)New information that was not reasonably known and could not have been reasonably known during the public comment period.
(7)The lead agency shall file the notice required by subdivision (a) of Section 21152 within five calendar days after the last initial project approval.
(e)(1)The lead agency shall prepare and certify the record of proceedings in accordance with this subdivision and in accordance with Rule 3.2205 of the California Rules of Court.
(2)No later than three business days following the date of the release of the draft environmental impact report, the lead agency shall make available to the public in a readily accessible electronic format the draft environmental impact report and all other documents relied on by the lead agency in the preparation of the draft environmental impact report. A document prepared by the lead agency after the date of the release of the draft environmental impact report that is a part of the record of proceedings shall be made available to the public in a readily accessible electronic format within five business days after the document is prepared by the lead agency.
(3)Notwithstanding paragraph (2), documents relied on by the lead agency that were not prepared specifically for the project and are copyright protected are not required to be made readily accessible in an electronic format. For those copyright protected documents, the lead agency shall make an index of the documents available in an electronic format no later than the date of the release of the draft environmental impact report, or within five business days if the document is received or relied on by the lead agency after the release of the draft environmental impact report. The index shall specify the libraries or lead agency offices in which hardcopies of the copyrighted materials are available for public review.
(4)The lead agency shall encourage written comments on the project to be submitted in a readily accessible electronic format, and shall make any such comments available to the public in a readily accessible electronic format within five calendar days of their receipt.
(5)Within seven business days after the receipt of any comment that is not in an electronic format, the lead agency shall convert that comment into a readily accessible electronic format and make it available to the public in that format.
(6)The lead agency shall indicate in the record of proceedings comments received that were not considered by the lead agency and need not include the content of the comments as a part of the record of proceedings.
(7)Within five calendar days after the filing of the notice required by subdivision (a) of Section 21152, the lead agency shall certify the record of proceedings for the approval or determination and shall provide an electronic copy of the record of proceedings to a party that has submitted a written request for a copy. The lead agency may charge and collect a reasonable fee from a party requesting a copy of the record of proceedings for the electronic copy, which shall not exceed the reasonable cost of reproducing that copy.
(8)Within 10 calendar days after being served with a complaint or a petition for a writ of mandate, the lead agency shall lodge a copy of the certified record of proceedings with the superior court.
(9)Any dispute over the content of the record of proceedings shall be resolved by the superior court. Unless the superior court directs otherwise, a party disputing the content of the record of proceedings shall file a motion to augment the record of proceedings at the time it files its initial brief.
(10)The contents of the record of proceedings shall be as set forth in subdivision (e) of Section 21167.6.
SEC. 3.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the unique circumstances described in Section 1 of this act regarding media production campuses in the County of Los Angeles, including that incentivizing construction and renovation at Californias media production campuses will ensure business and creative success, stimulate the creation of new employment opportunities, and keep the production of film, scripted television, and streaming content in California for decades to come.
SEC. 4.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
(a)The Legislature finds and declares all of the following:
(1)The entertainment industry is a rich part of Californias history and the state is committed to retaining its status as the worlds film and television production capital.
(2)Attractive tax credit incentives from other states and countries to produce film and television are on the rise.
(3)There are large projects under consideration that would replace old and outmoded facilities, use innovative technologies, and help the state meet the increased demand for film and television production.
(4)These projects will generate thousands of full-time construction jobs and thousands more of permanent jobs once constructed and operating.
(5)New construction and renovation at California media production campuses can provide environmental benefits.
(b)It is the intent of the Legislature to incentivize construction and renovation at Californias media production campuses in order to ensure business and creative success, stimulate the creation of new employment opportunities, and keep the production of film, scripted television, and streaming content in California for decades to come.
(c)The Legislature further finds and declares that it is in the interest of the state to expedite judicial review of media production campus construction and renovation projects, as appropriate, while protecting the environment and the rights of the public to review, comment on, and, if necessary, seek judicial review of the adequacy of an environmental impact report for the project.
SEC. 2.Section 21168.6.6 is added to the Public Resources Code, immediately following Section 21168.6, to read:21168.6.6.(a)For purposes of this section, the following terms have the following meanings:
(1)Disadvantaged community means an area identified by the California Environmental Protection Agency pursuant to Section 39711 of the Health and Safety Code or an area that is a disadvantaged unincorporated community pursuant to Section 65302.10 of the Government Code.
(2)Environmental leadership media campus project or project means a construction or renovation project on a film and television media campus in the County of Los Angeles.
(b) A city within the County of Los Angeles that is the lead agency for the project shall certify an environmental leadership media campus project for streamlining pursuant to this section if the lead agency finds that all of the following conditions will be met:
(1)The project will result in an investment of at least one billion dollars ($1,000,000,000) in California upon completion of the construction.
(2)(A)The project will obtain certification as Leadership in Energy and Environmental Design (LEED) gold standard or better from the United States Green Building Council for all new construction that is eligible for LEED certification.
(B)Any new construction or major renovation of existing buildings that is not eligible for LEED certification will achieve comparable standards for energy and water efficiency, including, but not limited to, meeting Tier 1 energy efficiency standards.
(3)The project will achieve a reduction in vehicle miles traveled per capita of at least 15 percent compared to existing development consistent with the Office of Planning and Researchs technical advisory on evaluating transportation impacts in CEQA and at least 50 percent of any greenhouse gas emissions reductions necessary to achieve zero net additional greenhouse gas emissions as required by paragraph (4) will be from onsite and local reduction measures.
(4)The project does not result in any net additional greenhouse gas emissions, including, but not limited to, from employee transportation. A project is deemed to meet the requirements of this paragraph if the project applicant demonstrates to the lead agency that the project applicant has a binding commitment that it will mitigate impacts resulting from the greenhouse gas emissions, if any, in accordance with Section 21183.6.
(5)If measures are required to mitigate significant environmental impacts in a disadvantaged community, those impacts will be mitigated consistent with this division, including Section 21002, and the mitigation measures required under this subdivision will be undertaken in, and directly benefit, the affected community.
(6)The project will generate at least 1,000 jobs during construction.
(7)(A)(i)The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, employs a skilled and trained workforce, as defined in subdivision (d) of Section 2601 of the Public Contract Code, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment. For purposes of this subdivision, jobs that pay prevailing wages means that all construction workers employed in the execution of the project will receive at least the general prevailing rate of per diem wages for the type of work and geographic area, as determined by the Director of Industrial Relations pursuant to Sections 1773 and 1773.9 of the Labor Code. If the project is certified for streamlining, the project applicant shall include this requirement in all contracts for the performance of the work.
(ii)Clause (i) does not apply to a contractor or subcontractor performing the work on the project that is subject to a project labor agreement requiring the payment of prevailing wages to all construction workers employed in the execution of the project and providing for enforcement of that obligation through an arbitration procedure. For purposes of this clause, project labor agreement has the same meaning as set forth in paragraph (1) of subdivision (b) of Section 2500 of the Public Contract Code.
(B)(i)If the project is certified pursuant to this subdivision, contractors and subcontractors shall pay to all construction workers employed in the execution of the project at least the general prevailing rate of per diem wages.
(ii)Except as provided in clause (iii), the obligation of the contractors and subcontractors to pay prevailing wages pursuant to subparagraph (A) may be enforced by the Labor Commissioner through the issuance of a civil wage and penalty assessment pursuant to Section 1741 of the Labor Code, which may be reviewed pursuant to Section 1742 of the Labor Code, within 18 months after the completion of the project, or by an underpaid worker through an administrative complaint or civil action. If a civil wage and penalty assessment is issued, the contractor, subcontractor, and surety on a bond or bonds issued to secure the payment of wages covered by the assessment shall be liable for liquidated damages pursuant to Section 1742.1 of the Labor Code.
(iii)Clause (ii) does not apply if all contractors and subcontractors performing work on the project are subject to a project labor agreement that requires the payment of prevailing wages to all construction workers employed in the execution of the project and provides for enforcement of that obligation through an arbitration procedure. For purposes of this subparagraph, project labor agreement has the same meaning as set forth in paragraph (1) of subdivision (b) of Section 2500 of the Public Contract Code.
(8)The project applicant demonstrates compliance with the requirements of Chapters 12.8 (commencing with Section 42649) and 12.9 (commencing with Section 42649.8) of Part 3 of Division 30, as applicable.
(9)The project applicant agrees that all mitigation measures required pursuant to this division and any other environmental measures required by this section to certify the project under this section shall be conditions of approval of the project, and those conditions will be fully enforceable by the lead agency or another agency designated by the lead agency. In the case of environmental mitigation measures and any other environmental measures required by this section, the project applicant agrees, as an ongoing obligation, that those measures will be monitored and enforced by the lead agency for the life of the obligation. The project applicant shall submit to the lead agency an annual status report on the implementation of the environmental mitigation measures and any other environmental measures required by this section.
(10)The project applicant agrees to pay any additional costs incurred by the courts in hearing and deciding any case subject to this section, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council, as provided in the California Rules of Court adopted by the Judicial Council.
(11)The project applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with review and consideration of the project pursuant to this division, in a form and manner specified by the lead agency for the project.
(c)On or before July 1, 2025, the Judicial Council shall adopt rules of court that apply to any action or proceeding brought to attack, review, set aside, void, or annul the certification of an environmental impact report for an environmental leadership media campus project or the granting of any project approval that requires the action or proceeding, including any potential appeals to the court of appeal or the Supreme Court, to be resolved, to the extent feasible, within 365 calendar days of the filing of the certified record of proceedings with the court.
(d)(1) The draft and final environmental impact report for an environmental leadership media campus project shall include a notice in not less than 12-point type stating the following:
THIS ENVIRONMENTAL IMPACT REPORT IS SUBJECT TO SECTION 21168.6.6 OF THE PUBLIC RESOURCES CODE, WHICH PROVIDES, AMONG OTHER THINGS, THAT THE LEAD AGENCY NEED NOT CONSIDER CERTAIN COMMENTS FILED AFTER THE CLOSE OF THE PUBLIC COMMENT PERIOD, IF ANY, FOR THE DRAFT ENVIRONMENTAL IMPACT REPORT. ANY JUDICIAL ACTION CHALLENGING THE CERTIFICATION OR ADOPTION OF THE ENVIRONMENTAL IMPACT REPORT OR THE APPROVAL OF THE PROJECT DESCRIBED IN SECTION 21168.6.6 OF THE PUBLIC RESOURCES CODE IS SUBJECT TO THE PROCEDURES SET FORTH IN THAT SECTION. A COPY OF SECTION 21168.6.6 OF THE PUBLIC RESOURCES CODE IS INCLUDED IN THE APPENDIX TO THIS ENVIRONMENTAL IMPACT REPORT.
(2)The draft environmental impact report and final environmental impact report shall contain, as an appendix, the full text of this section.
(3)Within 10 calendar days after the release of the draft environmental impact report, the lead agency shall conduct an informational workshop to inform the public of the key analyses and conclusions of that document, as applicable.
(4)Within 10 calendar days before the close of the public comment period, the lead agency shall hold a public hearing to receive testimony on the draft environmental impact report. A transcript of the hearing shall be included as an appendix to the final environmental impact report, as applicable.
(5)(A)Within five calendar days following the close of the public comment period, a commenter on the draft environmental impact report may submit to the lead agency a written request for nonbinding mediation, as applicable. The lead agency shall participate in nonbinding mediation with all commenters who submitted timely comments on the draft environmental impact report and who requested the mediation. Mediation conducted pursuant to this paragraph shall end no later than 35 calendar days after the close of the public comment period.
(B)A request for mediation shall identify all areas of dispute raised in the comment submitted by the commenter that are to be mediated.
(C)The lead agency shall select one or more mediators who shall be retired judges or recognized experts with at least five years experience in land use and environmental law or science, or mediation. The lead agency shall bear the costs of mediation.
(D)A mediation session shall be conducted on each area of dispute with the parties requesting mediation on that area of dispute.
(E)The lead agency shall adopt, as a condition of approval, any measures agreed upon by the lead agency and any commenter who requested mediation. A commenter who agrees to a measure pursuant to this subparagraph shall not raise the issue addressed by that measure as a basis for an action or proceeding challenging the lead agencys decision to certify the environmental impact report or to grant project approval.
(6)The lead agency need not consider written comments on the draft environmental impact report submitted after the close of the public comment period, unless those comments address any of the following:
(A)New issues raised in the response to comments by the lead agency.
(B)New information released by the lead agency subsequent to the release of the draft environmental impact report, such as new information set forth or embodied in a staff report, proposed permit, proposed resolution, ordinance, or similar documents.
(C)Changes made to the project after the close of the public comment period.
(D)Proposed conditions for approval, mitigation measures, or proposed findings required by Section 21081 or a proposed reporting or monitoring program required by paragraph (1) of subdivision (a) of Section 21081.6, if the lead agency releases those documents subsequent to the release of the draft environmental impact report.
(E)New information that was not reasonably known and could not have been reasonably known during the public comment period.
(7)The lead agency shall file the notice required by subdivision (a) of Section 21152 within five calendar days after the last initial project approval.
(e)(1)The lead agency shall prepare and certify the record of proceedings in accordance with this subdivision and in accordance with Rule 3.2205 of the California Rules of Court.
(2)No later than three business days following the date of the release of the draft environmental impact report, the lead agency shall make available to the public in a readily accessible electronic format the draft environmental impact report and all other documents relied on by the lead agency in the preparation of the draft environmental impact report. A document prepared by the lead agency after the date of the release of the draft environmental impact report that is a part of the record of proceedings shall be made available to the public in a readily accessible electronic format within five business days after the document is prepared by the lead agency.
(3)Notwithstanding paragraph (2), documents relied on by the lead agency that were not prepared specifically for the project and are copyright protected are not required to be made readily accessible in an electronic format. For those copyright protected documents, the lead agency shall make an index of the documents available in an electronic format no later than the date of the release of the draft environmental impact report, or within five business days if the document is received or relied on by the lead agency after the release of the draft environmental impact report. The index shall specify the libraries or lead agency offices in which hardcopies of the copyrighted materials are available for public review.
(4)The lead agency shall encourage written comments on the project to be submitted in a readily accessible electronic format, and shall make any such comments available to the public in a readily accessible electronic format within five calendar days of their receipt.
(5)Within seven business days after the receipt of any comment that is not in an electronic format, the lead agency shall convert that comment into a readily accessible electronic format and make it available to the public in that format.
(6)The lead agency shall indicate in the record of proceedings comments received that were not considered by the lead agency and need not include the content of the comments as a part of the record of proceedings.
(7)Within five calendar days after the filing of the notice required by subdivision (a) of Section 21152, the lead agency shall certify the record of proceedings for the approval or determination and shall provide an electronic copy of the record of proceedings to a party that has submitted a written request for a copy. The lead agency may charge and collect a reasonable fee from a party requesting a copy of the record of proceedings for the electronic copy, which shall not exceed the reasonable cost of reproducing that copy.
(8)Within 10 calendar days after being served with a complaint or a petition for a writ of mandate, the lead agency shall lodge a copy of the certified record of proceedings with the superior court.
(9)Any dispute over the content of the record of proceedings shall be resolved by the superior court. Unless the superior court directs otherwise, a party disputing the content of the record of proceedings shall file a motion to augment the record of proceedings at the time it files its initial brief.
(10)The contents of the record of proceedings shall be as set forth in subdivision (e) of Section 21167.6.
SEC. 3.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the unique circumstances described in Section 1 of this act regarding media production campuses in the County of Los Angeles, including that incentivizing construction and renovation at Californias media production campuses will ensure business and creative success, stimulate the creation of new employment opportunities, and keep the production of film, scripted television, and streaming content in California for decades to come.
SEC. 4.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
(a)The Legislature finds and declares all of the following:
(1)The entertainment industry is a rich part of Californias history and the state is committed to retaining its status as the worlds film and television production capital.
(2)Attractive tax credit incentives from other states and countries to produce film and television are on the rise.
(3)There are large projects under consideration that would replace old and outmoded facilities, use innovative technologies, and help the state meet the increased demand for film and television production.
(4)These projects will generate thousands of full-time construction jobs and thousands more of permanent jobs once constructed and operating.
(5)New construction and renovation at California media production campuses can provide environmental benefits.
(b)It is the intent of the Legislature to incentivize construction and renovation at Californias media production campuses in order to ensure business and creative success, stimulate the creation of new employment opportunities, and keep the production of film, scripted television, and streaming content in California for decades to come.
(c)The Legislature further finds and declares that it is in the interest of the state to expedite judicial review of media production campus construction and renovation projects, as appropriate, while protecting the environment and the rights of the public to review, comment on, and, if necessary, seek judicial review of the adequacy of an environmental impact report for the project.
SEC. 2.Section 21168.6.6 is added to the Public Resources Code, immediately following Section 21168.6, to read:21168.6.6.(a)For purposes of this section, the following terms have the following meanings:
(1)Disadvantaged community means an area identified by the California Environmental Protection Agency pursuant to Section 39711 of the Health and Safety Code or an area that is a disadvantaged unincorporated community pursuant to Section 65302.10 of the Government Code.
(2)Environmental leadership media campus project or project means a construction or renovation project on a film and television media campus in the County of Los Angeles.
(b) A city within the County of Los Angeles that is the lead agency for the project shall certify an environmental leadership media campus project for streamlining pursuant to this section if the lead agency finds that all of the following conditions will be met:
(1)The project will result in an investment of at least one billion dollars ($1,000,000,000) in California upon completion of the construction.
(2)(A)The project will obtain certification as Leadership in Energy and Environmental Design (LEED) gold standard or better from the United States Green Building Council for all new construction that is eligible for LEED certification.
(B)Any new construction or major renovation of existing buildings that is not eligible for LEED certification will achieve comparable standards for energy and water efficiency, including, but not limited to, meeting Tier 1 energy efficiency standards.
(3)The project will achieve a reduction in vehicle miles traveled per capita of at least 15 percent compared to existing development as determined by consistent with the Office of Planning and Research, Researchs technical advisory on evaluating transportation impacts in CEQA and at least 50 percent of any greenhouse gas emissions reductions necessary to achieve zero net additional greenhouse gas emissions as required by paragraph (4) will be from onsite and local reduction measures.
(4)The project does not result in any net additional greenhouse gas emissions, including, but not limited to, from employee transportation. A project is deemed to meet the requirements of this paragraph if the project applicant demonstrates to the lead agency that the project applicant has a binding commitment that it will mitigate impacts resulting from the greenhouse gas emissions, if any, in accordance with Section 21183.6.
(5)If measures are required to mitigate significant environmental impacts in a disadvantaged community, those impacts will be mitigated consistent with this division, including Section 21002, and the mitigation measures required under this subdivision will be undertaken in, and directly benefit, the affected community.
(6)The project will generate at least 1,000 jobs during construction.
(7)(A)(i)The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, employs a skilled and trained workforce, as defined in subdivision (d) of Section 2601 of the Public Contract Code, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment. For purposes of this subdivision, jobs that pay prevailing wages means that all construction workers employed in the execution of the project will receive at least the general prevailing rate of per diem wages for the type of work and geographic area, as determined by the Director of Industrial Relations pursuant to Sections 1773 and 1773.9 of the Labor Code. If the project is certified for streamlining, the project applicant shall include this requirement in all contracts for the performance of the work.
(ii)Clause (i) does not apply to a contractor or subcontractor performing the work on the project that is subject to a project labor agreement requiring the payment of prevailing wages to all construction workers employed in the execution of the project and providing for enforcement of that obligation through an arbitration procedure. For purposes of this clause, project labor agreement has the same meaning as set forth in paragraph (1) of subdivision (b) of Section 2500 of the Public Contract Code.
(B)(i)If the project is certified pursuant to this subdivision, contractors and subcontractors shall pay to all construction workers employed in the execution of the project at least the general prevailing rate of per diem wages.
(ii)Except as provided in clause (iii), the obligation of the contractors and subcontractors to pay prevailing wages pursuant to subparagraph (A) may be enforced by the Labor Commissioner through the issuance of a civil wage and penalty assessment pursuant to Section 1741 of the Labor Code, which may be reviewed pursuant to Section 1742 of the Labor Code, within 18 months after the completion of the project, or by an underpaid worker through an administrative complaint or civil action. If a civil wage and penalty assessment is issued, the contractor, subcontractor, and surety on a bond or bonds issued to secure the payment of wages covered by the assessment shall be liable for liquidated damages pursuant to Section 1742.1 of the Labor Code.
(iii)Clause (ii) does not apply if all contractors and subcontractors performing work on the project are subject to a project labor agreement that requires the payment of prevailing wages to all construction workers employed in the execution of the project and provides for enforcement of that obligation through an arbitration procedure. For purposes of this subparagraph, project labor agreement has the same meaning as set forth in paragraph (1) of subdivision (b) of Section 2500 of the Public Contract Code.
(8)The project applicant demonstrates compliance with the requirements of Chapters 12.8 (commencing with Section 42649) and 12.9 (commencing with Section 42649.8) of Part 3 of Division 30, as applicable.
(9)The project applicant agrees that all mitigation measures required pursuant to this division and any other environmental measures required by this section to certify the project under this section shall be conditions of approval of the project, and those conditions will be fully enforceable by the lead agency or another agency designated by the lead agency. In the case of environmental mitigation measures and any other environmental measures required by this section, the project applicant agrees, as an ongoing obligation, that those measures will be monitored and enforced by the lead agency for the life of the obligation. The project applicant shall submit to the lead agency an annual status report on the implementation of the environmental mitigation measures and any other environmental measures required by this section.
(10)The project applicant agrees to pay any additional costs incurred by the courts in hearing and deciding any case subject to this section, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council, as provided in the California Rules of Court adopted by the Judicial Council.
(11)The project applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with review and consideration of the project pursuant to this division, in a form and manner specified by the lead agency for the project.
(c)On or before July 1, 2025, the Judicial Council shall adopt rules of court that apply to any action or proceeding brought to attack, review, set aside, void, or annul the certification of an environmental impact report for an environmental leadership media campus project or the granting of any project approval that requires the action or proceeding, including any potential appeals to the court of appeal or the Supreme Court, to be resolved, to the extent feasible, within 365 calendar days of the filing of the certified record of proceedings with the court.
(d)(1) The draft and final environmental impact report for an environmental leadership media campus project shall include a notice in not less than 12-point type stating the following:
THIS ENVIRONMENTAL IMPACT REPORT IS SUBJECT TO SECTION 21168.6.6 OF THE PUBLIC RESOURCES CODE, WHICH PROVIDES, AMONG OTHER THINGS, THAT THE LEAD AGENCY NEED NOT CONSIDER CERTAIN COMMENTS FILED AFTER THE CLOSE OF THE PUBLIC COMMENT PERIOD, IF ANY, FOR THE DRAFT ENVIRONMENTAL IMPACT REPORT. ANY JUDICIAL ACTION CHALLENGING THE CERTIFICATION OR ADOPTION OF THE ENVIRONMENTAL IMPACT REPORT OR THE APPROVAL OF THE PROJECT DESCRIBED IN SECTION 21168.6.6 OF THE PUBLIC RESOURCES CODE IS SUBJECT TO THE PROCEDURES SET FORTH IN THAT SECTION. A COPY OF SECTION 21168.6.6 OF THE PUBLIC RESOURCES CODE IS INCLUDED IN THE APPENDIX TO THIS ENVIRONMENTAL IMPACT REPORT.
(2)The draft environmental impact report and final environmental impact report shall contain, as an appendix, the full text of this section.
(3)Within 10 calendar days after the release of the draft environmental impact report, the lead agency shall conduct an informational workshop to inform the public of the key analyses and conclusions of that document, as applicable.
(4)Within 10 calendar days before the close of the public comment period, the lead agency shall hold a public hearing to receive testimony on the draft environmental impact report. A transcript of the hearing shall be included as an appendix to the final environmental impact report, as applicable.
(5)(A)Within five calendar days following the close of the public comment period, a commenter on the draft environmental impact report may submit to the lead agency a written request for nonbinding mediation, as applicable. The lead agency shall participate in nonbinding mediation with all commenters who submitted timely comments on the draft environmental impact report and who requested the mediation. Mediation conducted pursuant to this paragraph shall end no later than 35 calendar days after the close of the public comment period.
(B)A request for mediation shall identify all areas of dispute raised in the comment submitted by the commenter that are to be mediated.
(C)The lead agency shall select one or more mediators who shall be retired judges or recognized experts with at least five years experience in land use and environmental law or science, or mediation. The lead agency shall bear the costs of mediation.
(D)A mediation session shall be conducted on each area of dispute with the parties requesting mediation on that area of dispute.
(E)The lead agency shall adopt, as a condition of approval, any measures agreed upon by the lead agency and any commenter who requested mediation. A commenter who agrees to a measure pursuant to this subparagraph shall not raise the issue addressed by that measure as a basis for an action or proceeding challenging the lead agencys decision to certify the environmental impact report or to grant project approval.
(6)The lead agency need not consider written comments on the draft environmental impact report submitted after the close of the public comment period, unless those comments address any of the following:
(A)New issues raised in the response to comments by the lead agency.
(B)New information released by the lead agency subsequent to the release of the draft environmental impact report, such as new information set forth or embodied in a staff report, proposed permit, proposed resolution, ordinance, or similar documents.
(C)Changes made to the project after the close of the public comment period.
(D)Proposed conditions for approval, mitigation measures, or proposed findings required by Section 21081 or a proposed reporting or monitoring program required by paragraph (1) of subdivision (a) of Section 21081.6, if the lead agency releases those documents subsequent to the release of the draft environmental impact report.
(E)New information that was not reasonably known and could not have been reasonably known during the public comment period.
(7)The lead agency shall file the notice required by subdivision (a) of Section 21152 within five calendar days after the last initial project approval.
(e)(1)The lead agency shall prepare and certify the record of proceedings in accordance with this subdivision and in accordance with Rule 3.2205 of the California Rules of Court.
(2)No later than three business days following the date of the release of the draft environmental impact report, the lead agency shall make available to the public in a readily accessible electronic format the draft environmental impact report and all other documents relied on by the lead agency in the preparation of the draft environmental impact report. A document prepared by the lead agency after the date of the release of the draft environmental impact report that is a part of the record of proceedings shall be made available to the public in a readily accessible electronic format within five business days after the document is prepared by the lead agency.
(3)Notwithstanding paragraph (2), documents relied on by the lead agency that were not prepared specifically for the project and are copyright protected are not required to be made readily accessible in an electronic format. For those copyright protected documents, the lead agency shall make an index of the documents available in an electronic format no later than the date of the release of the draft environmental impact report, or within five business days if the document is received or relied on by the lead agency after the release of the draft environmental impact report. The index shall specify the libraries or lead agency offices in which hardcopies of the copyrighted materials are available for public review.
(4)The lead agency shall encourage written comments on the project to be submitted in a readily accessible electronic format, and shall make any such comments available to the public in a readily accessible electronic format within five calendar days of their receipt.
(5)Within seven business days after the receipt of any comment that is not in an electronic format, the lead agency shall convert that comment into a readily accessible electronic format and make it available to the public in that format.
(6)The lead agency shall indicate in the record of proceedings comments received that were not considered by the lead agency and need not include the content of the comments as a part of the record of proceedings.
(7)Within five calendar days after the filing of the notice required by subdivision (a) of Section 21152, the lead agency shall certify the record of proceedings for the approval or determination and shall provide an electronic copy of the record of proceedings to a party that has submitted a written request for a copy. The lead agency may charge and collect a reasonable fee from a party requesting a copy of the record of proceedings for the electronic copy, which shall not exceed the reasonable cost of reproducing that copy.
(8)Within 10 calendar days after being served with a complaint or a petition for a writ of mandate, the lead agency shall lodge a copy of the certified record of proceedings with the superior court.
(9)Any dispute over the content of the record of proceedings shall be resolved by the superior court. Unless the superior court directs otherwise, a party disputing the content of the record of proceedings shall file a motion to augment the record of proceedings at the time it files its initial brief.
(10)The contents of the record of proceedings shall be as set forth in subdivision (e) of Section 21167.6.
SEC. 3.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the unique circumstances described in Section 1 of this act regarding media production campuses in the County of Los Angeles, including that incentivizing construction and renovation at Californias media production campuses will ensure business and creative success, stimulate the creation of new employment opportunities, and keep the production of film, scripted television, and streaming content in California for decades to come.
SEC. 4.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
(a)The Legislature finds and declares all of the following:
(1)The entertainment industry is a rich part of Californias history and the state is committed to retaining its status as the worlds film and television production capital.
(2)Attractive tax credit incentives from other states and countries to produce film and television are on the rise.
(3)There are large projects under consideration that would replace old and outmoded facilities, use innovative technologies, and help the state meet the increased demand for film and television production.
(4)These projects will generate thousands of full-time construction jobs and thousands more of permanent jobs once constructed and operating.
(5)New construction and renovation at California media production campuses can provide environmental benefits.
(b)It is the intent of the Legislature to incentivize construction and renovation at Californias media production campuses in order to ensure business and creative success, stimulate the creation of new employment opportunities, and keep the production of film, scripted television, and streaming content in California for decades to come.
(c)The Legislature further finds and declares that it is in the interest of the state to expedite judicial review of media production campus construction and renovation projects, as appropriate, while protecting the environment and the rights of the public to review, comment on, and, if necessary, seek judicial review of the adequacy of an environmental impact report for the project.
SEC. 2.Section 21168.6.6 is added to the Public Resources Code, immediately following Section 21168.6, to read:21168.6.6.(a)For purposes of this section, environmental leadership media campus project or project means a construction or renovation project on a film and television media campus in the County of Los Angeles. the following terms have the following meanings:
(1)Disadvantaged community means an area identified by the California Environmental Protection Agency pursuant to Section 39711 of the Health and Safety Code or an area that is a disadvantaged unincorporated community pursuant to Section 65302.10 of the Government Code.
(2)Environmental leadership media campus project or project means a construction or renovation project on a film and television media campus in the County of Los Angeles.
(b) A city within the County of Los Angeles that is the lead agency for the project shall certify an environmental leadership media campus project for streamlining pursuant to this section if the lead agency finds that all of the following conditions will be met:
(1)The project will result in an investment of at least one billion dollars ($1,000,000,000) in California upon completion of the construction.
(2)(A)The project will obtain certification as Leadership in Energy and Environmental Design (LEED) gold standard or better from the United States Green Building Council for all new construction that is eligible for LEED certification.
(B)Any new construction or major renovation of existing buildings that is not eligible for LEED certification will achieve comparable standards for energy and water efficiency. efficiency, including, but not limited to, meeting Tier 1 energy efficiency standards.
(3)The project will achieve a reduction in vehicle miles traveled per capita of at least 15 percent compared to existing development as determined by the Office of Planning and Research, and at least 50 percent of any greenhouse gas emissions reductions necessary to achieve zero net additional greenhouse gas emissions as required by paragraph (4) will be from onsite and local reduction measures.
(3)(4)The project does not result in any net additional greenhouse gas emissions, including, but not limited to, from employee transportation. A project is deemed to meet the requirements of this paragraph if the project applicant demonstrates to the lead agency that the project applicant has a binding commitment that it will mitigate impacts resulting from the greenhouse gas emissions, if any, in accordance with Section 21183.6.
(5)If measures are required to mitigate significant environmental impacts in a disadvantaged community, those impacts will be mitigated consistent with this division, including Section 21002, and the mitigation measures required under this subdivision will be undertaken in, and directly benefit, the affected community.
(4)(6)The project will generate at least 1,000 jobs during construction.
(5)(7)(A)(i)The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, employs a skilled and trained workforce, as defined in subdivision (d) of Section 2601 of the Public Contract Code, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment. For purposes of this subdivision, jobs that pay prevailing wages means that all construction workers employed in the execution of the project will receive at least the general prevailing rate of per diem wages for the type of work and geographic area, as determined by the Director of Industrial Relations pursuant to Sections 1773 and 1773.9 of the Labor Code. If the project is certified for streamlining, the project applicant shall include this requirement in all contracts for the performance of the work.
(ii)Clause (i) does not apply to a contractor or subcontractor performing the work on the project that is subject to a project labor agreement requiring the payment of prevailing wages to all construction workers employed in the execution of the project and providing for enforcement of that obligation through an arbitration procedure. For purposes of this clause, project labor agreement has the same meaning as set forth in paragraph (1) of subdivision (b) of Section 2500 of the Public Contract Code.
(B)(i)If the project is certified pursuant to this subdivision, contractors and subcontractors shall pay to all construction workers employed in the execution of the project at least the general prevailing rate of per diem wages.
(ii)Except as provided in clause (iii), the obligation of the contractors and subcontractors to pay prevailing wages pursuant to subparagraph (A) may be enforced by the Labor Commissioner through the issuance of a civil wage and penalty assessment pursuant to Section 1741 of the Labor Code, which may be reviewed pursuant to Section 1742 of the Labor Code, within 18 months after the completion of the project, or by an underpaid worker through an administrative complaint or civil action. If a civil wage and penalty assessment is issued, the contractor, subcontractor, and surety on a bond or bonds issued to secure the payment of wages covered by the assessment shall be liable for liquidated damages pursuant to Section 1742.1 of the Labor Code.
(iii)Clause (ii) does not apply if all contractors and subcontractors performing work on the project are subject to a project labor agreement that requires the payment of prevailing wages to all construction workers employed in the execution of the project and provides for enforcement of that obligation through an arbitration procedure. For purposes of this subparagraph, project labor agreement has the same meaning as set forth in paragraph (1) of subdivision (b) of Section 2500 of the Public Contract Code.
(6)(8)The project applicant demonstrates compliance with the requirements of Chapters 12.8 (commencing with Section 42649) and 12.9 (commencing with Section 42649.8) of Part 3 of Division 30, as applicable.
(7)(9)The project applicant agrees that all mitigation measures required pursuant to this division and any other environmental measures required by this section to certify the project under this section shall be conditions of approval of the project, and those conditions will be fully enforceable by the lead agency or another agency designated by the lead agency. In the case of environmental mitigation measures and any other environmental measures required by this section, the project applicant agrees, as an ongoing obligation, that those measures will be monitored and enforced by the lead agency for the life of the obligation. The project applicant shall submit to the lead agency an annual status report on the implementation of the environmental mitigation measures and any other environmental measures required by this section.
(8)(10)The project applicant agrees to pay any additional costs incurred by the courts in hearing and deciding any case subject to this section, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council, as provided in the California Rules of Court adopted by the Judicial Council.
(9)(11)The project applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with review and consideration of the project pursuant to this division, in a form and manner specified by the lead agency for the project.
(c)On or before July 1, 2025, the Judicial Council shall adopt rules of court that apply to any action or proceeding brought to attack, review, set aside, void, or annul the certification of an environmental impact report for an environmental leadership media campus project or the granting of any project approval that requires the action or proceeding, including any potential appeals to the court of appeal or the Supreme Court, to be resolved, to the extent feasible, within 365 calendar days of the filing of the certified record of proceedings with the court.
(d)(1) The draft and final environmental impact report for an environmental leadership media campus project shall include a notice in not less than 12-point type stating the following:
THIS ENVIRONMENTAL IMPACT REPORT IS SUBJECT TO SECTION 21168.6.6 OF THE PUBLIC RESOURCES CODE, WHICH PROVIDES, AMONG OTHER THINGS, THAT THE LEAD AGENCY NEED NOT CONSIDER CERTAIN COMMENTS FILED AFTER THE CLOSE OF THE PUBLIC COMMENT PERIOD, IF ANY, FOR THE DRAFT ENVIRONMENTAL IMPACT REPORT. ANY JUDICIAL ACTION CHALLENGING THE CERTIFICATION OR ADOPTION OF THE ENVIRONMENTAL IMPACT REPORT OR THE APPROVAL OF THE PROJECT DESCRIBED IN SECTION 21168.6.6 OF THE PUBLIC RESOURCES CODE IS SUBJECT TO THE PROCEDURES SET FORTH IN THAT SECTION. A COPY OF SECTION 21168.6.6 OF THE PUBLIC RESOURCES CODE IS INCLUDED IN THE APPENDIX TO THIS ENVIRONMENTAL IMPACT REPORT.
(2)The draft environmental impact report and final environmental impact report shall contain, as an appendix, the full text of this section.
(3)Within 10 calendar days after the release of the draft environmental impact report, the lead agency shall conduct an informational workshop to inform the public of the key analyses and conclusions of that document, as applicable.
(4)Within 10 calendar days before the close of the public comment period, the lead agency shall hold a public hearing to receive testimony on the draft environmental impact report. A transcript of the hearing shall be included as an appendix to the final environmental impact report, as applicable.
(5)(A)Within five calendar days following the close of the public comment period, a commenter on the draft environmental impact report may submit to the lead agency a written request for nonbinding mediation, as applicable. The lead agency shall participate in nonbinding mediation with all commenters who submitted timely comments on the draft environmental impact report and who requested the mediation. Mediation conducted pursuant to this paragraph shall end no later than 35 calendar days after the close of the public comment period.
(B)A request for mediation shall identify all areas of dispute raised in the comment submitted by the commenter that are to be mediated.
(C)The lead agency shall select one or more mediators who shall be retired judges or recognized experts with at least five years experience in land use and environmental law or science, or mediation. The lead agency shall bear the costs of mediation.
(D)A mediation session shall be conducted on each area of dispute with the parties requesting mediation on that area of dispute.
(E)The lead agency shall adopt, as a condition of approval, any measures agreed upon by the lead agency and any commenter who requested mediation. A commenter who agrees to a measure pursuant to this subparagraph shall not raise the issue addressed by that measure as a basis for an action or proceeding challenging the lead agencys decision to certify the environmental impact report or to grant project approval.
(6)The lead agency need not consider written comments on the draft environmental impact report submitted after the close of the public comment period, unless those comments address any of the following:
(A)New issues raised in the response to comments by the lead agency.
(B)New information released by the lead agency subsequent to the release of the draft environmental impact report, such as new information set forth or embodied in a staff report, proposed permit, proposed resolution, ordinance, or similar documents.
(C)Changes made to the project after the close of the public comment period.
(D)Proposed conditions for approval, mitigation measures, or proposed findings required by Section 21081 or a proposed reporting or monitoring program required by paragraph (1) of subdivision (a) of Section 21081.6, if the lead agency releases those documents subsequent to the release of the draft environmental impact report.
(E)New information that was not reasonably known and could not have been reasonably known during the public comment period.
(7)The lead agency shall file the notice required by subdivision (a) of Section 21152 within five calendar days after the last initial project approval.
(e)(1)The lead agency shall prepare and certify the record of proceedings in accordance with this subdivision and in accordance with Rule 3.2205 of the California Rules of Court.
(2)No later than three business days following the date of the release of the draft environmental impact report, the lead agency shall make available to the public in a readily accessible electronic format the draft environmental impact report and all other documents relied on by the lead agency in the preparation of the draft environmental impact report. A document prepared by the lead agency after the date of the release of the draft environmental impact report that is a part of the record of proceedings shall be made available to the public in a readily accessible electronic format within five business days after the document is prepared by the lead agency.
(3)Notwithstanding paragraph (2), documents relied on by the lead agency that were not prepared specifically for the project and are copyright protected are not required to be made readily accessible in an electronic format. For those copyright protected documents, the lead agency shall make an index of the documents available in an electronic format no later than the date of the release of the draft environmental impact report, or within five business days if the document is received or relied on by the lead agency after the release of the draft environmental impact report. The index shall specify the libraries or lead agency offices in which hardcopies of the copyrighted materials are available for public review.
(4)The lead agency shall encourage written comments on the project to be submitted in a readily accessible electronic format, and shall make any such comments available to the public in a readily accessible electronic format within five calendar days of their receipt.
(5)Within seven business days after the receipt of any comment that is not in an electronic format, the lead agency shall convert that comment into a readily accessible electronic format and make it available to the public in that format.
(6)The lead agency shall indicate in the record of proceedings comments received that were not considered by the lead agency and need not include the content of the comments as a part of the record of proceedings.
(7)Within five calendar days after the filing of the notice required by subdivision (a) of Section 21152, the lead agency shall certify the record of proceedings for the approval or determination and shall provide an electronic copy of the record of proceedings to a party that has submitted a written request for a copy. The lead agency may charge and collect a reasonable fee from a party requesting a copy of the record of proceedings for the electronic copy, which shall not exceed the reasonable cost of reproducing that copy.
(8)Within 10 calendar days after being served with a complaint or a petition for a writ of mandate, the lead agency shall lodge a copy of the certified record of proceedings with the superior court.
(9)Any dispute over the content of the record of proceedings shall be resolved by the superior court. Unless the superior court directs otherwise, a party disputing the content of the record of proceedings shall file a motion to augment the record of proceedings at the time it files its initial brief.
(10)The contents of the record of proceedings shall be as set forth in subdivision (e) of Section 21167.6.
SEC. 3.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the unique circumstances described in Section 1 of this act regarding media production campuses in the County of Los Angeles, including that incentivizing construction and renovation at Californias media production campuses will ensure business and creative success, stimulate the creation of new employment opportunities, and keep the production of film, scripted television, and streaming content in California for decades to come.
SEC. 4.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
(a)The Legislature finds and declares all of the following:
(1)The entertainment industry is a rich part of Californias history and the state is committed to retaining its status as the worlds film and television production capital.
(2)Attractive tax credit incentives from other states and countries to produce film and television are on the rise.
(3)There are large projects under consideration that would replace old and outmoded facilities, use innovative technologies, and help the state meet the increased demand for film and television production.
(4)These projects will generate thousands of full-time construction jobs and thousands more of permanent jobs once constructed and operating.
(5)New construction and renovation at California media production campuses can provide environmental benefits.
(b)It is the intent of the Legislature to incentivize construction and renovation at Californias media production campuses in order to ensure business and creative success, stimulate the creation of new employment opportunities, and keep the production of film, scripted television, and streaming content in California for decades to come.
(c)The Legislature further finds and declares that it is in the interest of the state to expedite judicial review of media production campus construction and renovation projects, as appropriate, while protecting the environment and the rights of the public to review, comment on, and, if necessary, seek judicial review of the adequacy of an environmental impact report for the project.
SEC. 2.Section 21168.6.6 is added to the Public Resources Code, immediately following Section 21168.6, to read:21168.6.6.(a)For purposes of this section, environmental leadership media campus project or project means a construction or renovation project on a film and television media campus in the County of Los Angeles.
(b) A city within the County of Los Angeles where an environmental leadership media campus project is to be constructed that is the lead agency for the project shall certify an environmental leadership media campus project for streamlining pursuant to this section if the lead agency finds that all of the following conditions are will be met:
(1)The project will result in an investment of at least one billion dollars ($1,000,000,000) in California upon completion of the construction.
(2)(A)The project contains at least 250,000 square feet of new construction that qualifies to be certified at the will obtain certification as Leadership in Energy and Environmental Design (LEED) gold standard or better by from the United States Green Building Council. Council for all new construction that is eligible for LEED certification.
(B)Any new construction or major renovation of existing buildings that is not eligible for LEED certification will achieve comparable standards for energy and water efficiency.
(3)The project does not result in any net additional greenhouse gas emissions, including, but not limited to, from employee transportation. A project is deemed to meet the requirements of this paragraph if the project applicant demonstrates to the lead agency that the project applicant has a binding commitment that it will mitigate impacts resulting from the greenhouse gas emissions, if any, in accordance with Section 21183.6.
(3)(4)The project will generate at least 1,000 jobs during construction.
(4)(5)(A)(i)The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, employs a skilled and trained workforce, as defined in subdivision (d) of Section 2601 of the Public Contract Code, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment. For purposes of this subdivision, jobs that pay prevailing wages means that all construction workers employed in the execution of the project will receive at least the general prevailing rate of per diem wages for the type of work and geographic area, as determined by the Director of Industrial Relations pursuant to Sections 1773 and 1773.9 of the Labor Code. If the project is certified for streamlining, the project applicant shall include this requirement in all contracts for the performance of the work.
(ii)Clause (i) does not apply to a contractor or subcontractor performing the work on the project that is subject to a project labor agreement requiring the payment of prevailing wages to all construction workers employed in the execution of the project and providing for enforcement of that obligation through an arbitration procedure. For purposes of this clause, project labor agreement has the same meaning as set forth in paragraph (1) of subdivision (b) of Section 2500 of the Public Contract Code.
(B)(i)If the project is certified pursuant to this subdivision, contractors and subcontractors shall pay to all construction workers employed in the execution of the project at least the general prevailing rate of per diem wages.
(ii)Except as provided in clause (iii), the obligation of the contractors and subcontractors to pay prevailing wages pursuant to subparagraph (A) may be enforced by the Labor Commissioner through the issuance of a civil wage and penalty assessment pursuant to Section 1741 of the Labor Code, which may be reviewed pursuant to Section 1742 of the Labor Code, within 18 months after the completion of the project, or by an underpaid worker through an administrative complaint or civil action. If a civil wage and penalty assessment is issued, the contractor, subcontractor, and surety on a bond or bonds issued to secure the payment of wages covered by the assessment shall be liable for liquidated damages pursuant to Section 1742.1 of the Labor Code.
(iii)Clause (ii) does not apply if all contractors and subcontractors performing work on the project are subject to a project labor agreement that requires the payment of prevailing wages to all construction workers employed in the execution of the project and provides for enforcement of that obligation through an arbitration procedure. For purposes of this subparagraph, project labor agreement has the same meaning as set forth in paragraph (1) of subdivision (b) of Section 2500 of the Public Contract Code.
(5)(6)The project applicant demonstrates compliance with the requirements of Chapters 12.8 (commencing with Section 42649) and 12.9 (commencing with Section 42649.8) of Part 3 of Division 30, as applicable.
(6)(7)The project applicant agrees that all mitigation measures required pursuant to this division and any other environmental measures required by this section to certify the project under this section shall be conditions of approval of the project, and those conditions will be fully enforceable by the lead agency or another agency designated by the lead agency. In the case of environmental mitigation measures and any other environmental measures required by this section, the project applicant agrees, as an ongoing obligation, that those measures will be monitored and enforced by the lead agency for the life of the obligation. The project applicant shall submit to the lead agency an annual status report on the implementation of the environmental mitigation measures and any other environmental measures required by this section.
(7)(8)The project applicant agrees to pay any additional costs incurred by the courts in hearing and deciding any case subject to this section, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council, as provided in the California Rules of Court adopted by the Judicial Council.
(8)(9)The project applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with review and consideration of the project pursuant to this division, in a form and manner specified by the lead agency for the project.
(c)On or before July 1, 2025, the Judicial Council shall adopt rules of court that apply to any action or proceeding brought to attack, review, set aside, void, or annul the certification of an environmental impact report for an environmental leadership media campus project or the granting of any project approval that requires the action or proceeding, including any potential appeals to the court of appeal or the Supreme Court, to be resolved, to the extent feasible, within 365 calendar days of the filing of the certified record of proceedings with the court.
(d)(1) The draft and final environmental impact report for an environmental leadership media campus project shall include a notice in not less than 12-point type stating the following:
THIS ENVIRONMENTAL IMPACT REPORT IS SUBJECT TO SECTION 21168.6.6 OF THE PUBLIC RESOURCES CODE, WHICH PROVIDES, AMONG OTHER THINGS, THAT THE LEAD AGENCY NEED NOT CONSIDER CERTAIN COMMENTS FILED AFTER THE CLOSE OF THE PUBLIC COMMENT PERIOD, IF ANY, FOR THE DRAFT ENVIRONMENTAL IMPACT REPORT. ANY JUDICIAL ACTION CHALLENGING THE CERTIFICATION OR ADOPTION OF THE ENVIRONMENTAL IMPACT REPORT OR THE APPROVAL OF THE PROJECT DESCRIBED IN SECTION 21168.6.6 OF THE PUBLIC RESOURCES CODE IS SUBJECT TO THE PROCEDURES SET FORTH IN THAT SECTION. A COPY OF SECTION 21168.6.6 OF THE PUBLIC RESOURCES CODE IS INCLUDED IN THE APPENDIX TO THIS ENVIRONMENTAL IMPACT REPORT.
(2)The draft environmental impact report and final environmental impact report shall contain, as an appendix, the full text of this section.
(3)Within 10 calendar days after the release of the draft environmental impact report, the lead agency shall conduct an informational workshop to inform the public of the key analyses and conclusions of that document, as applicable.
(4)Within 10 calendar days before the close of the public comment period, the lead agency shall hold a public hearing to receive testimony on the draft environmental impact report. A transcript of the hearing shall be included as an appendix to the final environmental impact report, as applicable.
(5)(A)Within five calendar days following the close of the public comment period, a commenter on the draft environmental impact report may submit to the lead agency a written request for nonbinding mediation, as applicable. The lead agency shall participate in nonbinding mediation with all commenters who submitted timely comments on the draft environmental impact report and who requested the mediation. Mediation conducted pursuant to this paragraph shall end no later than 35 calendar days after the close of the public comment period.
(B)A request for mediation shall identify all areas of dispute raised in the comment submitted by the commenter that are to be mediated.
(C)The lead agency shall select one or more mediators who shall be retired judges or recognized experts with at least five years experience in land use and environmental law or science, or mediation. The lead agency shall bear the costs of mediation.
(D)A mediation session shall be conducted on each area of dispute with the parties requesting mediation on that area of dispute.
(E)The lead agency shall adopt, as a condition of approval, any measures agreed upon by the lead agency and any commenter who requested mediation. A commenter who agrees to a measure pursuant to this subparagraph shall not raise the issue addressed by that measure as a basis for an action or proceeding challenging the lead agencys decision to certify the environmental impact report or to grant project approval.
(6)The lead agency need not consider written comments on the draft environmental impact report submitted after the close of the public comment period, unless those comments address any of the following:
(A)New issues raised in the response to comments by the lead agency.
(B)New information released by the lead agency subsequent to the release of the draft environmental impact report, such as new information set forth or embodied in a staff report, proposed permit, proposed resolution, ordinance, or similar documents.
(C)Changes made to the project after the close of the public comment period.
(D)Proposed conditions for approval, mitigation measures, or proposed findings required by Section 21081 or a proposed reporting or monitoring program required by paragraph (1) of subdivision (a) of Section 21081.6, if the lead agency releases those documents subsequent to the release of the draft environmental impact report.
(E)New information that was not reasonably known and could not have been reasonably known during the public comment period.
(7)The lead agency shall file the notice required by subdivision (a) of Section 21152 within five calendar days after the last initial project approval.
(e)(1)The lead agency shall prepare and certify the record of proceedings in accordance with this subdivision and in accordance with Rule 3.2205 of the California Rules of Court.
(2)No later than three business days following the date of the release of the draft environmental impact report, the lead agency shall make available to the public in a readily accessible electronic format the draft environmental impact report and all other documents relied on by the lead agency in the preparation of the draft environmental impact report. A document prepared by the lead agency after the date of the release of the draft environmental impact report that is a part of the record of proceedings shall be made available to the public in a readily accessible electronic format within five business days after the document is prepared by the lead agency.
(3)Notwithstanding paragraph (2), documents relied on by the lead agency that were not prepared specifically for the project and are copyright protected are not required to be made readily accessible in an electronic format. For those copyright protected documents, the lead agency shall make an index of the documents available in an electronic format no later than the date of the release of the draft environmental impact report, or within five business days if the document is received or relied on by the lead agency after the release of the draft environmental impact report. The index shall specify the libraries or lead agency offices in which hardcopies of the copyrighted materials are available for public review.
(4)The lead agency shall encourage written comments on the project to be submitted in a readily accessible electronic format, and shall make any such comments available to the public in a readily accessible electronic format within five calendar days of their receipt.
(5)Within seven business days after the receipt of any comment that is not in an electronic format, the lead agency shall convert that comment into a readily accessible electronic format and make it available to the public in that format.
(6)The lead agency shall indicate in the record of proceedings comments received that were not considered by the lead agency and need not include the content of the comments as a part of the record of proceedings.
(7)Within five calendar days after the filing of the notice required by subdivision (a) of Section 21152, the lead agency shall certify the record of proceedings for the approval or determination and shall provide an electronic copy of the record of proceedings to a party that has submitted a written request for a copy. The lead agency may charge and collect a reasonable fee from a party requesting a copy of the record of proceedings for the electronic copy, which shall not exceed the reasonable cost of reproducing that copy.
(8)Within 10 calendar days after being served with a complaint or a petition for a writ of mandate, the lead agency shall lodge a copy of the certified record of proceedings with the superior court.
(9)Any dispute over the content of the record of proceedings shall be resolved by the superior court. Unless the superior court directs otherwise, a party disputing the content of the record of proceedings shall file a motion to augment the record of proceedings at the time it files its initial brief.
(10)The contents of the record of proceedings shall be as set forth in subdivision (e) of Section 21167.6.
SEC. 3.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the unique circumstances described in Section 1 of this act regarding media production campuses in the County of Los Angeles, including that incentivizing construction and renovation at Californias media production campuses will ensure business and creative success, stimulate the creation of new employment opportunities, and keep the production of film, scripted television, and streaming content in California for decades to come.
SEC. 4.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
(a)The Legislature finds and declares all of the following:
(1)The entertainment industry is a rich part of Californias history and the state is committed to retaining its status as the worlds film and television production capital.
(2)Attractive tax credit incentives from other states and countries to produce film and television are on the rise.
(3)There are large projects under consideration that would replace old and outmoded facilities, use innovative technologies, and help the state meet the increased demand for film and television production.
(4)These projects will generate thousands of full-time construction jobs and thousands more of permanent jobs once constructed and operating.
(5)New construction and renovation at California media production campuses can provide environmental benefits.
(b)It is the intent of the Legislature to incentivize construction and renovation at Californias media production campuses in order to ensure business and creative success, stimulate the creation of new employment opportunities, and keep the production of film, scripted television, and streaming content in California for decades to come.
(c)The Legislature further finds and declares that it is in the interest of the state to expedite judicial review of media production campus construction and renovation projects, as appropriate, while protecting the environment and the rights of the public to review, comment on, and, if necessary, seek judicial review of the adequacy of an environmental impact report for the project.
SEC. 2.Section 21168.6.6 is added to the Public Resources Code, immediately following Section 21168.6, to read:21168.6.6.(a)For purposes of this section, environmental leadership media campus project or project means a construction or renovation project on a film and television media campus in the County of Los Angeles.
(b) A city within the County of Los Angeles where an environmental leadership media campus project is to be constructed shall certify an environmental leadership media campus project for streamlining pursuant to this section if all of the following conditions are met:
(1)The project will result in an investment of at least one billion dollars ($1,000,000,000) in California upon completion of the construction.
(2)The project contains at least 250,000 square feet of new construction that qualifies to be certified at the Leadership in Energy and Environmental Design (LEED) gold standard or better by the United States Green Building Council.
(3)The project will generate at least 1,000 jobs during construction.
(4)(A)(i)The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, employs a skilled and trained workforce, as defined in subdivision (d) of Section 2601 of the Public Contract Code, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment. For purposes of this subdivision, jobs that pay prevailing wages means that all construction workers employed in the execution of the project will receive at least the general prevailing rate of per diem wages for the type of work and geographic area, as determined by the Director of Industrial Relations pursuant to Sections 1773 and 1773.9 of the Labor Code. If the project is certified for streamlining, the project applicant shall include this requirement in all contracts for the performance of the work.
(ii)Clause (i) does not apply to a contractor or subcontractor performing the work on the project that is subject to a project labor agreement requiring the payment of prevailing wages to all construction workers employed in the execution of the project and providing for enforcement of that obligation through an arbitration procedure. For purposes of this clause, project labor agreement has the same meaning as set forth in paragraph (1) of subdivision (b) of Section 2500 of the Public Contract Code.
(B)(i)If the project is certified pursuant to this subdivision, contractors and subcontractors shall pay to all construction workers employed in the execution of the project at least the general prevailing rate of per diem wages.
(ii)Except as provided in clause (iii), the obligation of the contractors and subcontractors to pay prevailing wages pursuant to subparagraph (A) may be enforced by the Labor Commissioner through the issuance of a civil wage and penalty assessment pursuant to Section 1741 of the Labor Code, which may be reviewed pursuant to Section 1742 of the Labor Code, within 18 months after the completion of the project, or by an underpaid worker through an administrative complaint or civil action. If a civil wage and penalty assessment is issued, the contractor, subcontractor, and surety on a bond or bonds issued to secure the payment of wages covered by the assessment shall be liable for liquidated damages pursuant to Section 1742.1 of the Labor Code.
(iii)Clause (ii) does not apply if all contractors and subcontractors performing work on the project are subject to a project labor agreement that requires the payment of prevailing wages to all construction workers employed in the execution of the project and provides for enforcement of that obligation through an arbitration procedure. For purposes of this subparagraph, project labor agreement has the same meaning as set forth in paragraph (1) of subdivision (b) of Section 2500 of the Public Contract Code.
(5)The project applicant demonstrates compliance with the requirements of Chapters 12.8 (commencing with Section 42649) and 12.9 (commencing with Section 42649.8) of Part 3 of Division 30, as applicable.
(6)The project applicant agrees that all mitigation measures required pursuant to this division and any other environmental measures required by this section to certify the project under this section shall be conditions of approval of the project, and those conditions will be fully enforceable by the lead agency or another agency designated by the lead agency. In the case of environmental mitigation measures and any other environmental measures required by this section, the project applicant agrees, as an ongoing obligation, that those measures will be monitored and enforced by the lead agency for the life of the obligation. The project applicant shall submit to the lead agency an annual status report on the implementation of the environmental mitigation measures and any other environmental measures required by this section.
(7)The project applicant agrees to pay any additional costs incurred by the courts in hearing and deciding any case subject to this section, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council, as provided in the California Rules of Court adopted by the Judicial Council.
(8)The project applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with review and consideration of the project pursuant to this division, in a form and manner specified by the lead agency for the project.
(c)On or before July 1, 2025, the Judicial Council shall adopt rules of court that apply to any action or proceeding brought to attack, review, set aside, void, or annul the certification of an environmental impact report for an environmental leadership media campus project or the granting of any project approval that requires the action or proceeding, including any potential appeals to the court of appeal or the Supreme Court, to be resolved, to the extent feasible, within 365 calendar days of the filing of the certified record of proceedings with the court.
(d)(1) The draft and final environmental impact report for an environmental leadership media campus project shall include a notice in not less than 12-point type stating the following:
THIS ENVIRONMENTAL IMPACT REPORT IS SUBJECT TO SECTION 21168.6.6 OF THE PUBLIC RESOURCES CODE, WHICH PROVIDES, AMONG OTHER THINGS, THAT THE LEAD AGENCY NEED NOT CONSIDER CERTAIN COMMENTS FILED AFTER THE CLOSE OF THE PUBLIC COMMENT PERIOD, IF ANY, FOR THE DRAFT ENVIRONMENTAL IMPACT REPORT. ANY JUDICIAL ACTION CHALLENGING THE CERTIFICATION OR ADOPTION OF THE ENVIRONMENTAL IMPACT REPORT OR THE APPROVAL OF THE PROJECT DESCRIBED IN SECTION 21168.6.6 OF THE PUBLIC RESOURCES CODE IS SUBJECT TO THE PROCEDURES SET FORTH IN THAT SECTION. A COPY OF SECTION 21168.6.6 OF THE PUBLIC RESOURCES CODE IS INCLUDED IN THE APPENDIX TO THIS ENVIRONMENTAL IMPACT REPORT.
(2)The draft environmental impact report and final environmental impact report shall contain, as an appendix, the full text of this section.
(3)Within 10 calendar days after the release of the draft environmental impact report, the lead agency shall conduct an informational workshop to inform the public of the key analyses and conclusions of that document, as applicable.
(4)Within 10 calendar days before the close of the public comment period, the lead agency shall hold a public hearing to receive testimony on the draft environmental impact report. A transcript of the hearing shall be included as an appendix to the final environmental impact report, as applicable.
(5)(A) Within five calendar days following the close of the public comment period, a commenter on the draft environmental impact report may submit to the lead agency a written request for nonbinding mediation, as applicable. The lead agency shall participate in nonbinding mediation with all commenters who submitted timely comments on the draft environmental impact report and who requested the mediation. Mediation conducted pursuant to this paragraph shall end no later than 35 calendar days after the close of the public comment period.
(B)A request for mediation shall identify all areas of dispute raised in the comment submitted by the commenter that are to be mediated.
(C)The lead agency shall select one or more mediators who shall be retired judges or recognized experts with at least five years experience in land use and environmental law or science, or mediation. The lead agency shall bear the costs of mediation.
(D)A mediation session shall be conducted on each area of dispute with the parties requesting mediation on that area of dispute.
(E)The lead agency shall adopt, as a condition of approval, any measures agreed upon by the lead agency and any commenter who requested mediation. A commenter who agrees to a measure pursuant to this subparagraph shall not raise the issue addressed by that measure as a basis for an action or proceeding challenging the lead agencys decision to certify the environmental impact report or to grant project approval.
(6)The lead agency need not consider written comments on the draft environmental impact report submitted after the close of the public comment period, unless those comments address any of the following:
(A)New issues raised in the response to comments by the lead agency.
(B)New information released by the lead agency subsequent to the release of the draft environmental impact report, such as new information set forth or embodied in a staff report, proposed permit, proposed resolution, ordinance, or similar documents.
(C)Changes made to the project after the close of the public comment period.
(D)Proposed conditions for approval, mitigation measures, or proposed findings required by Section 21081 or a proposed reporting or monitoring program required by paragraph (1) of subdivision (a) of Section 21081.6, if the lead agency releases those documents subsequent to the release of the draft environmental impact report.
(E)New information that was not reasonably known and could not have been reasonably known during the public comment period.
(7)The lead agency shall file the notice required by subdivision (a) of Section 21152 within five calendar days after the last initial project approval.
(e)(1) The lead agency shall prepare and certify the record of proceedings in accordance with this subdivision and in accordance with Rule 3.2205 of the California Rules of Court.
(2)No later than three business days following the date of the release of the draft environmental impact report, the lead agency shall make available to the public in a readily accessible electronic format the draft environmental impact report and all other documents relied on by the lead agency in the preparation of the draft environmental impact report. A document prepared by the lead agency after the date of the release of the draft environmental impact report that is a part of the record of proceedings shall be made available to the public in a readily accessible electronic format within five business days after the document is prepared by the lead agency.
(3)Notwithstanding paragraph (2), documents relied on by the lead agency that were not prepared specifically for the project and are copyright protected are not required to be made readily accessible in an electronic format. For those copyright protected documents, the lead agency shall make an index of the documents available in an electronic format no later than the date of the release of the draft environmental impact report, or within five business days if the document is received or relied on by the lead agency after the release of the draft environmental impact report. The index shall specify the libraries or lead agency offices in which hardcopies of the copyrighted materials are available for public review.
(4)The lead agency shall encourage written comments on the project to be submitted in a readily accessible electronic format, and shall make any such comments available to the public in a readily accessible electronic format within five calendar days of their receipt.
(5)Within seven business days after the receipt of any comment that is not in an electronic format, the lead agency shall convert that comment into a readily accessible electronic format and make it available to the public in that format.
(6)The lead agency shall indicate in the record of proceedings comments received that were not considered by the lead agency and need not include the content of the comments as a part of the record of proceedings.
(7)Within five calendar days after the filing of the notice required by subdivision (a) of Section 21152, the lead agency shall certify the record of proceedings for the approval or determination and shall provide an electronic copy of the record of proceedings to a party that has submitted a written request for a copy. The lead agency may charge and collect a reasonable fee from a party requesting a copy of the record of proceedings for the electronic copy, which shall not exceed the reasonable cost of reproducing that copy.
(8)Within 10 calendar days after being served with a complaint or a petition for a writ of mandate, the lead agency shall lodge a copy of the certified record of proceedings with the superior court.
(9)Any dispute over the content of the record of proceedings shall be resolved by the superior court. Unless the superior court directs otherwise, a party disputing the content of the record of proceedings shall file a motion to augment the record of proceedings at the time it files its initial brief.
(10)The contents of the record of proceedings shall be as set forth in subdivision (e) of Section 21167.6.
SEC. 3.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the unique circumstances described in Section 1 of this act regarding media production campuses in the County of Los Angeles, including that incentivizing construction and renovation at Californias media production campuses will ensure business and creative success, stimulate the creation of new employment opportunities, and keep the production of film, scripted television, and streaming content in California for decades to come.
SEC. 4.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
|
Date
|
Status
|
|---|---|
| Sep 14, 2024 | Chaptered by Secretary of State - Chapter 255, Statutes of 2024. |
| Sep 14, 2024 | Approved by the Governor. |
| Sep 6, 2024 | Enrolled and presented to the Governor at 4 p.m. |
| Aug 28, 2024 | Senate amendments concurred in. To Engrossing and Enrolling. (Ayes 75. Noes 0.). |
| Aug 28, 2024 | In Assembly. Concurrence in Senate amendments pending. May be considered on or after August 30 pursuant to Assembly Rule 77. |
| Aug 28, 2024 | Assembly Rule 77 suspended. |
| Aug 27, 2024 | Read third time. Passed. Ordered to the Assembly. (Ayes 38. Noes 0.). |
| Aug 26, 2024 | Read second time. Ordered to third reading. |
| Aug 22, 2024 | Read third time and amended. Ordered to second reading. |
| Aug 19, 2024 | Read second time. Ordered to third reading. |
| Aug 15, 2024 | From committee: Do pass. (Ayes 7. Noes 0.) (August 15). |
| Aug 5, 2024 | In committee: Referred to suspense file. |
| Jul 3, 2024 | From committee: Do pass and re-refer to Com. on APPR. (Ayes 10. Noes 0.) (July 2). Re-referred to Com. on APPR. |
| Jun 20, 2024 | Read second time and amended. Re-referred to Com. on JUD. |
| Jun 19, 2024 | From committee: Amend, and do pass as amended and re-refer to Com. on JUD. (Ayes 6. Noes 0.) (June 19). |
| May 22, 2024 | Referred to Coms. on E.Q. and JUD. |
| May 9, 2024 | In Senate. Read first time. To Com. on RLS. for assignment. |
| May 9, 2024 | Read third time. Passed. Ordered to the Senate. (Ayes 64. Noes 0. Page 5162.) |
| May 2, 2024 | Read second time. Ordered to Consent Calendar. |
| May 1, 2024 | From committee: Do pass. To Consent Calendar. (Ayes 14. Noes 0.) (May 1). |
| Apr 23, 2024 | From committee: Do pass and re-refer to Com. on APPR. with recommendation: To Consent Calendar. (Ayes 11. Noes 0.) (April 23). Re-referred to Com. on APPR. |
| Apr 16, 2024 | From committee: Do pass and re-refer to Com. on JUD. with recommendation: To Consent Calendar. (Ayes 10. Noes 0.) (April 15). Re-referred to Com. on JUD. |
| Apr 10, 2024 | Re-referred to Com. on NAT. RES. |
| Apr 9, 2024 | From committee chair, with author's amendments: Amend, and re-refer to Com. on NAT. RES. Read second time and amended. |
| Mar 11, 2024 | Referred to Coms. on NAT. RES. and JUD. |
| Feb 17, 2024 | From printer. May be heard in committee March 18. |
| Feb 16, 2024 | Read first time. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Aug 28, 2024 | AB 3265 Bryan Concurrence in Senate Amendments | Assembly Floor |
Passed |
|
| Aug 27, 2024 | Assembly 3rd Reading AB3265 Bryan By Durazo | Senate Floor |
Passed |
|
| Aug 15, 2024 | Do pass | Senate Standing Committee on Appropriations |
Passed |
|
| Aug 5, 2024 | Placed on suspense file | Senate Standing Committee on Appropriations |
Passed |
|
| Jul 2, 2024 | Do pass, but first be re-referred to the Committee on [Appropriations] | Senate Standing Committee on Judiciary |
Passed |
|
| Jun 19, 2024 | Do pass as amended, but first amend, and re-refer to the Committee on [Judiciary] | Senate Standing Committee on Environmental Quality |
Passed |
|
| May 9, 2024 | AB 3265 Bryan Consent Calendar Second Day Regular Session | Assembly Floor |
Passed |
|
| May 1, 2024 | Do pass. To Consent Calendar. | Assembly Standing Committee on Appropriations |
Passed |
|
| Apr 23, 2024 | Do pass and be re-referred to the Committee on [Appropriations] with recommendation: To Consent Calendar | Assembly Standing Committee on Judiciary |
Passed |
|
| Apr 15, 2024 | Do pass and be re-referred to the Committee on [Judiciary] with recommendation: To Consent Calendar | Assembly Standing Committee on Natural Resources |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| Fox Corporation | ** Support | |
| Fox Entertainment Group Inc | ** Support | |
| Judicial Council of California | ** Against | |
| Western Electrical Contractors Association | ** Against |
CONCURRENCE IN SENATE AMENDMENTS
CSA1 Bill Id:AB 3265
Author:(Bryan)
As Amended Ver:August 22, 2024
Majority vote
SUMMARY
Establishes expedited administrative and judicial review procedures under the California Environmental Quality Act (CEQA) for "environmental leadership media campus projects" (ELMCP) in Los Angeles, requiring the courts to resolve lawsuits within 365 days, to the extent feasible.
Senate Amendments
- Require projects to achieve a 15% reduction in vehicle miles traveled.
- Require at least 50% of greenhouse gas emissions (GHG) reductions necessary to achieve net zero GHG to be from onsite and local reduction measures.
- Require any measures required to mitigation significant environmental impacts in a disadvantaged community, as defined, to be undertaken in, and directly benefit, the affected community.
COMMENTS
Generally, CEQA actions taken by public agencies can be challenged in superior court once the agency approves or determines to carry out the project. CEQA appeals are subject to unusually short statutes of limitations. Under current law, court challenges of CEQA decisions generally must be filed within 30-35 days, depending on the type of decision. The courts are required to give CEQA actions preference over all other civil actions. However, the schedules for briefing, hearing, and decision are less definite. The petitioner must request a hearing within 90 days of filing the petition and, generally, briefing must be completed within 90 days of the request for hearing. There is no deadline specified for the court to render a decision.
In 2011, AB 900 and SB 292 (Padilla), Chapter 353, Statutes of 2011, established expedited CEQA judicial review procedures for a limited number of projects. For AB 900, it was large-scale projects meeting extraordinary environmental standards and providing significant jobs and investment. For SB 292, it was a proposed downtown Los Angeles football stadium and convention center project achieving specified traffic and air quality mitigations. For these eligible projects, the bills provided for original jurisdiction by the Court of Appeal and a compressed schedule requiring the court to render a decision on any lawsuit within 175 days. This promised to reduce the existing judicial review timeline by 100 days or more, while creating new burdens for the courts and litigants to meet the compressed schedule. AB 900’s provision granting original jurisdiction to the Court of Appeal was invalidated in 2013 by a decision in Alameda Superior Court in Planning and Conservation League v. State of California. AB 900 was subsequently revised to restore jurisdiction to superior courts and require resolution of lawsuits within 270 days, to the extent feasible.
As part of their expedited judicial review procedures, these bills required the lead agency to prepare and certify the record of proceedings concurrently with the administrative process and required the applicant to pay for it. It was commonly agreed that this would expedite preparation of the record for trial. Since 2011, several additional bills have provided similar project-specific concurrent preparation procedures. In addition, SB 122 (Jackson), Chapter 476, Statutes of 2016, established an optional concurrent preparation procedure for any CEQA project, subject to the lead agency agreeing, and the applicant paying the agency's costs.
To date, approximately 30 projects have been eligible for expedited review under AB 900 and the several project-specific bills enacted since 2011. Many of these projects have not proceeded to final approval and construction, and only four projects have been challenged in court. Of those four cases, two were high-profile arena projects, one was a luxury condominium tower, and one is the reconstruction of the Capitol Annex. A review by the Senate Office of Research indicates the following timelines for final resolution of three of the cases:
- Golden1 Center (Sacramento Kings arena): 243 business days/352 calendar days.
- Chase Center (Golden State Warriors arena): 257 business days/376 calendar days.
- 8150 Sunset Boulevard (Hollywood condo tower): 395 business days/578 calendar days.
Whether calendar days or business days, “to the extent feasible,” as well as the inherent authority of the independent judicial branch, provides a court discretion, and no direct consequence, if it is unable to meet the 365-day deadline.
According to the Author
The construction of soundstages in California has not kept pace with the recent growth in the production of film, scripted television and streaming content which forces more production outside of California. The segment of entertainment production that has had the most detrimental effect on California's infrastructure is the loss of big-budget feature films which require the use of many large sound stages building complex sets.
Adding to the need for updating the state's film and television production facilities is the arrival of digital technology. New cinematography, sound recording and editing tools have provided sophisticated visual and audio effects for filmmakers during production and post production. While technology has revolutionized the creative brilliance of the film and television industry, its deployment requires infrastructure improvements for high-speed internet connections and cloud-based storage solutions at California’s media production campuses.
These projects will generate thousands of full-time jobs during construction and thousands of additional permanent jobs once they are constructed and operating. AB 3265 will meet the highest environmental standards set in prior streamlined environmental bills that have been signed into law. In addition, the bill contains language that will assure the creation of high paying jobs throughout the construction of the project.
Arguments in Support
According to Fox Corporation, AB 3265 will be a catalyst for sustained job growth by streamlining the process for renovating sound stages, and updating production facilities to incorporate the latest graphics and audio technology. These investments will provide environmental benefits and keep productions in-state for decades to come. AB 3265 will meet the highest environmental standards set in prior streamlined environmental bills that have been signed into law. In addition, the bill contains language that will assure the creation of high paying jobs throughout the construction of the project through Labor Peace Agreements.
Arguments in Opposition
According to Judicial Council, (i)mposing an expedited 365-day judicial review timeline on top of existing CEQA calendar preferences is unworkable for several reasons:
- The 365-day timeline is problematic in practice. CEQA cases are inherently complex and time-consuming. Even in an unrealistic scenario in which no extensions of time were requested or granted for any aspect of a case, such a CEQA case would take an estimated six months just to get to a hearing, not to mention a decision. The reason this is an unrealistic scenario is because parties almost always request – and even stipulate to – continuances, delays, or other procedural extensions. Assuming a court was able to issue its decision within six months, that would leave only 185 days for proceedings in the Court of Appeal and the Supreme Court.
- CEQA cases often include ancillary administrative and non-CEQA judicial causes of action. Expediting review of CEQA causes of action does not necessarily lead to a faster resolution of the entire case, as non-CEQA causes of actions are frequently brought together with CEQA claims. These non-CEQA causes of action proceed under the usual civil procedure rules and timelines and can cause delays to the principal CEQA action.
- The expedited judicial review requirements for two additional infrastructure projects in AB 3265 will likely have an adverse impact on other cases with calendar preferences. Like other types of court calendar preferences, which the Judicial Council has opposed, setting an extremely tight timeline for deciding these complex cases has the practical effect of pushing other cases on the courts’ dockets to the back of the line, even those with their own statutorily mandated calendar preferences. This means that juvenile cases, criminal cases, wage theft cases, and civil cases in which a party is at risk of dying will take longer to resolve.
FISCAL COMMENTS
According to the Senate Appropriations Committee, unknown but potentially significant cost pressure (General Fund) to the state-funded court system to process and hear challenges to the project's environmental review within the timeframes prescribed by the bill.
VOTES:
ASM NATURAL RESOURCES: 10-0-1
YES: Bryan, Flora, Bauer-Kahan, Friedman, Hoover, Kalra, Muratsuchi, Pellerin, Wicks, Wood
ABS, ABST OR NV: Mathis
ASM JUDICIARY: 11-0-1
YES: Kalra, Dixon, Bauer-Kahan, Bryan, Connolly, Haney, Maienschein, McKinnor, Pacheco, Reyes, Sanchez
ABS, ABST OR NV: Waldron
ASM APPROPRIATIONS: 14-0-1
YES: Wicks, Sanchez, Arambula, Bryan, Calderon, Wendy Carrillo, Dixon, Mike Fong, Grayson, Haney, Hart, Pellerin, Ta, Villapudua
ABS, ABST OR NV: Jim Patterson
ASSEMBLY FLOOR: 64-0-16
YES: Addis, Aguiar-Curry, Alanis, Alvarez, Arambula, Bauer-Kahan, Bennett, Berman, Bonta, Bryan, Calderon, Juan Carrillo, Wendy Carrillo, Chen, Connolly, Davies, Dixon, Essayli, Mike Fong, Vince Fong, Friedman, Gallagher, Garcia, Gipson, Hart, Holden, Hoover, Irwin, Jackson, Jones-Sawyer, Kalra, Lackey, Lee, Lowenthal, Maienschein, McCarty, McKinnor, Muratsuchi, Ortega, Pacheco, Papan, Jim Patterson, Joe Patterson, Pellerin, Quirk-Silva, Ramos, Rendon, Reyes, Rodriguez, Blanca Rubio, Sanchez, Santiago, Soria, Ta, Valencia, Villapudua, Waldron, Ward, Weber, Wicks, Wilson, Wood, Zbur, Robert Rivas
ABS, ABST OR NV: Bains, Boerner, Cervantes, Megan Dahle, Flora, Gabriel, Grayson, Haney, Low, Mathis, Stephanie Nguyen, Petrie-Norris, Luz Rivas, Schiavo, Ting, Wallis
SENATE FLOOR: 38-0-2
YES: Allen, Alvarado-Gil, Archuleta, Ashby, Atkins, Becker, Blakespear, Bradford, Caballero, Cortese, Dahle, Dodd, Durazo, Eggman, Glazer, Gonzalez, Grove, Hurtado, Jones, Laird, McGuire, Menjivar, Min, Newman, Nguyen, Niello, Padilla, Portantino, Roth, Rubio, Seyarto, Skinner, Smallwood-Cuevas, Stern, Umberg, Wahab, Wiener, Wilk
ABS, ABST OR NV: Limón, Ochoa Bogh
UPDATED
VERSION: August 22, 2024
CONSULTANT: Lawrence Lingbloom / NAT. RES. / (916) 319-2092 FN: 0004841
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | AB 3265 |
THIRD READING
Bill No: AB 3265
Author: Bryan (D)
Amended: 8/22/24 in Senate
Vote: 21
SENATE ENVIRONMENTAL QUALITY COMMITTEE: 6-0, 6/19/24
AYES: Allen, Gonzalez, Hurtado, Menjivar, Nguyen, Skinner
NO VOTE RECORDED: Dahle
SENATE JUDICIARY COMMITTEE: 10-0, 7/2/24
AYES: Umberg, Wilk, Allen, Ashby, Caballero, Durazo, Laird, Niello, Roth, Stern
NO VOTE RECORDED: Wahab
SENATE APPROPRIATIONS COMMITTEE: 7-0, 8/15/24
AYES: Caballero, Jones, Ashby, Becker, Bradford, Seyarto, Wahab
ASSEMBLY FLOOR: 64-0, 5/9/24 (Consent) - See last page for vote
SUBJECT: California Environmental Quality Act: environmental leadership media campus projects: judicial streamlining
SOURCE: Author
DIGEST:
This bill authorizes a lead agency that is a city within Los Angeles to certify a media campus for an expedited administrative and 365-day judicial review process for litigation involving the California Environmental Quality Act (CEQA) if the project meets certain criteria.
ANALYSIS:
Existing law:
- Provides that, under CEQA, a lead agency determines whether a project is exempt from CEQA, or if it must do an initial study to determine if a project will have significant effects on the environment. If a project has no effect on the environment or effects that can be mitigated, the lead agency prepares a negative declaration (ND) or mitigated ND (MND). If the project will have significant impacts, the lead agency prepares an environmental impact report (EIR) to evaluate and propose mitigation measures for any effects on the environment, including impacts or likely impacts to land, air, water, minerals, flora, fauna, ambient noise, and historic or aesthetic significance. (Public Resources Code (PRC) §§21000 et seq.)
- Establishes processes and timelines for lawsuits that challenge a public agency's compliance with the requirements of CEQA including:
- Challenges must be filed in the superior court within 30 days of filing the notice of approval.
- The courts are required to give CEQA actions preference over all other civil actions.
- Requires the court to regulate the briefing schedule so that, to the extent feasible, hearings commence within one year of the filing of the appeal.
- Requires the plaintiff to request a hearing within 90 days of filing the petition.
- Requires the court to establish a briefing schedule and a hearing date, requires briefing to be completed within 90 days of the plaintiff’s request for hearing, and requires the hearing, to the extent feasible, to be held within 30 days thereafter. (PRC 21167 et seq.)
- Established CEQA administrative and judicial streamlining for specified “environmental leadership” projects through the Jobs and Economic Improvement Through Environmental Leadership Act (Act) of 2011 (AB 900, Buchanan, Chapter 354, Statutes of 2011). The Act was later extended and modified in 2021 (SB 7, Atkins, Chapter 19, Statutes of 2021). (PRC §21178 et seq.)
- Establishes expedited judicial and administrative CEQA processes for a broad swath of energy, transportation, water, and semiconductor projects eligible for expedited judicial review under CEQA in SB 149 (Caballero, Chapter 60, Statutes of 2023). Projects must meet certain environmental and labor criteria to be eligible for this certification. The streamlining certification ends January 1, 2033.
This bill:
- Establishes administrative and judicial CEQA streamlining for environmental leadership media campus projects (ELMCPs) where the lead agency is a city within Los Angeles and the lead agency certifies the project following its determination and the ensuing criteria are met:
- The project will result in an investment of at least one billion dollars in California.
- The project will be Leadership in Energy and Environmental Design (LEED) gold certified or better for all new construction. Any new construction or major renovation of existing buildings that is not eligible for LEED certification will achieve comparable standards for energy and water efficiency.
- The project does not result in any net additional greenhouse gas (GHG) emissions, including, but not limited to, from employee transportation, as specified.
- The project will generate at least 1,000 jobs during construction.
- The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, employs a skilled and trained workforce, as defined, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment. These requirements do not apply to a contractor or subcontractor performing work that is subject to a project labor agreement.
- The project applicant demonstrates compliance with specified recycling requirements.
- If the project is located in a disadvantaged community, the project shall mitigate any impacts within the community.
- The project will achieve a reduction in vehicle miles traveled per capita of at least 15 percent compared to existing development, to align with the Office of Planning and Research (OPR’s) technical advisory on transportation impacts in CEQA.
- The project applicant agrees that all mitigation measures required pursuant to CEQA and any other environmental measures required by this bill shall be conditions of approval of the project, and those conditions will be fully enforceable by the lead agency.
- The project applicant agrees to pay any additional costs incurred by the courts in hearing and deciding any case subject to this section, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council.
- The project applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with review and consideration of the project pursuant to this division, in a form and manner specified by the lead agency for the project.
- Requires the Judicial Council to adopt a rule of court to establish procedures that require resolution, to the extent feasible, within 365 days, including any appeals, of a lawsuit challenging the certification of the EIR or any project approvals for a certified ELMCP.
- Prohibits these procedures from applying if the applicant fails to notify a lead agency prior to the release of the draft EIR for public comment.
- Makes related findings.
Background
- The A, B, C’s of CEQA. CEQA is designed to (a) make government agencies and the public aware of the environmental impacts of a proposed project, (b) ensure the public can take part in the review process, and (c) identify and implement measures to mitigate or eliminate any negative impact the project may have on the environment. CEQA is enforced by civil lawsuits that can challenge any project’s environmental review. Nonprofits, private individuals, public agencies, advocacy groups, and other organizations can all file lawsuits under CEQA.
Under CEQA, projects (unless they have a specific exemption) must undergo environmental analysis. This process starts with an initial study which determines what level of further environmental review is needed for a given project. If a project has no significant effects on the environment, or if those effects can be fully mitigated, the project can move forward with a negative declaration (ND) or mitigated negative declaration (MND). If the initial study finds that the project has potential significant effects on the environment, then a full EIR is conducted. An EIR provides a thorough environmental review of a proposed project, analyzing the significant direct and indirect environmental impacts of a proposed project on water quality, transportation, air quality and greenhouse gas emissions, terrestrial and aquatic biological resources, surface and subsurface hydrology, land use and agricultural resources, aesthetics, geology and soils, recreation, public services and utilities such as water supply and wastewater disposal, and cultural resources, among other factors. The EIR also includes proposed mitigation measures for any significant effects that it identifies and considers alternatives to the proposed project.
- CEQA streamlining. The Legislature has developed streamlining measures to speed CEQA lawsuits against certain projects through the courts. In current law, CEQA streamlining entails both judicial and administrative streamlining. Judicial streamlining requires that a CEQA lawsuit be heard in 270 days, including all appeals, as feasible. Administrative streamlining requires projects to prepare the administrative record, the comprehensive document at the heart of a CEQA case, at the same time as the environmental review documents are prepared. Preparing these documents concurrently, instead of sequentially, saves time if there is a lawsuit. These streamlining measures shorten what is potentially the lengthiest portion of the CEQA process—litigation—while retaining the environmental review and public engagement offered under CEQA.
In 2011, the Legislature passed the first CEQA streamlining certification program with the Jobs and Economic Improvement Through Environmental Leadership Act (Leadership Act), which created CEQA streamlining for residential, retail, commercial, sports, and recreational use projects that were certified as Environmental Leadership Development Projects (ELDP) by the Governor (AB 900, Buchanan, Chapter 354, Statutes of 2011). The ELDP program was further extended and modified in 2021 with (SB 7, Atkins, Chapter 19, Statutes of 2021). In 2023, The Legislature expanded these same streamlining provisions for certain energy, transportation, and water infrastructure projects (SB 149, Caballero, Chapter 60, Statutes of 2023).
- Streamlining Stadiums. In addition to streamlining programs for certain types of projects, the Legislature has also created CEQA streamlining for a number of one-off projects for stadiums including:
- SB 292 (Padilla, Chapter 353, Statutes of 2011) proposed a downtown Los Angeles football stadium and convention center that would achieve specified traffic and air quality mitigations. This project has not proceeded.
- SB 743 (Steinberg, Chapter 386, Statutes of 2013) established special CEQA procedures modeled after SB 292 for the Sacramento Kings arena project and included specified traffic and air quality mitigations.
- AB 734 (Bonta, Chapter 959, Statutes of 2018) authorized the Governor to certify and establish special CEQA procedures modeled after AB 900 for, the Oakland Sports and Mixed-Use Project if the project met specified conditions. Unlike AB 900, AB 734 required that 50% of the GHG emissions reductions necessary to achieve the zero-net additional GHG emissions requirement be from on-site and local reduction measures, limited the type of GHG offset credits that can be purchased to achieve the other 50% of the necessary GHG emissions reductions and required a transportation demand management plan that achieves a 20% reduction in vehicle trips.
- AB 987 (Kamlager-Dove, Chapter 961, Statutes of 2018) was similar to AB 734 but applied to a proposed basketball arena for the Los Angeles Clippers in Inglewood.
The specific criteria that projects must meet to be eligible for CEQA streamlining varies by project and process, but all are intended to ensure that projects meet high environmental and labor standards. In current law environmental criteria for streamlining includes requirements such as achieving Leadership in Energy and Environmental Design (LEED) Gold certification and being greenhouse gas neutral. SB 149 (Caballero, Chapter 60, Statutes of 2023) also includes a specific equity provision that requires that projects both minimize significant environmental impacts in disadvantaged communities and take mitigation measures that directly benefit the affected community. In offering CEQA streamlining for projects that meet these high standards, California has been able to promote projects that align with the State’s environmental, climate, and labor goals.
Comments
- Purpose of Bill. According to the author, “California has a rich history as the entertainment capital of the world. However, the construction of soundstages in California has not kept pace with the recent growth in the production of film, scripted television and streaming content which forces more production outside of California. AB 3265 would allow a streamlined review and approval process for “environmental leadership media campus projects” that will foster studio construction and renovation within Los Angeles County. These projects will generate thousands of full-time jobs during construction and thousands of additional permanent jobs once they are constructed and operating.”
- Everyone to the front? By adding a new project type to the front of the queue for judicial review, this bill may result in longer judicial review times for existing projects. When new projects are added to the “front of the line”, that designation becomes less meaningful to all the projects in the queue. Judicial review for ELDP-certified projects already takes longer than 270 days, and, to date, there have been only a small number of projects that have used this streamlining. By giving expedited judicial review to another project type without changing the capacity of the courts to support this expedited review, this proposal may slow judicial review for other projects, including important new housing and infrastructure projects.
This bill may not be as disruptive to other CEQA streamlined projects since it establishes a longer expedited judicial timeline of 365 instead of 270 days which is more typical for CEQA streamlining measures.
- Does CEQA streamlining work? A 2019 report by the Senate Office of Research entitled “Review of Environmental Leadership Development Projects” tracked the timeline of ELDP projects from 2011 to 2018. According to the report, 19 projects were submitted for certification during AB 900’s operation. Of those that were selected for certification and moved forward with the project, the report found that no ELDP project was actually reviewed within 270 days. However, the report also found that projects were reviewed under a faster timeline compared to other similar projects. According to the report, the average time for an ELDP-comparable project to wind its way through the judicial review process was 3-5 years, meaning that the 1-2-year timeline for ELDP projects represents significant time savings.
Based on data provided by the Judicial Council, of the 30 projects that have qualified for expedited CEQA review since 2011, only four projects have needed expedited legal review to defend against a lawsuit. Of those four cases, three were high-profile stadium projects that, in some cases, utilized taxpayer money to build a private facility. Notably, in addition to the relatively low rate of litigation, of those 19 projects that qualified for expedited review another four were either terminated or withdrawn, and thus never built, due to financial or other business considerations and not environmentally-related legal exposure.
Related/Prior Legislation
SB 1342 (Atkins, 2024) adds two infrastructure projects in San Diego County to the list of infrastructure projects eligible for California Environmental Quality Act (CEQA) judicial and administrative streamlining under SB 149 (Caballero, Chapter 60, Statutes of 2023). This bill is awaiting hearing on the Assembly Floor.
SB 149 (Caballero, Chapter 60, Statutes of 2023) made a broad swath of energy, transportation, water, and semiconductor projects eligible for expedited judicial review under CEQA. Projects must meet certain environmental and labor criteria to be eligible for certification. The streamlining certification ends January 1, 2033.
SB 7 (Atkins, Chapter 19, Statutes of 2021) extended and expanded expedited CEQA administrative and judicial review procedures in the Leadership Act for ELDPs. Additionally, this bill expands the Leadership Act to include smaller housing projects.
SB 44 (Allen, Chapter 633, Statutes of 2021) established, until January 1, 2025, a 365-day expedited administrative and judicial review of environmental review and approvals granted for “environmental leadership transit projects” located within the County of Los Angeles that meet specified requirements.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
According to the Senate Appropriations Committee, this bill has:
• Unknown but potentially significant cost pressure (General Fund) to the state-funded court system to process and hear challenges to the project's environmental review within the timeframes prescribed by the bill. (See staff comments for details.)
SUPPORT: (Verified 8/22/24)
Fox Entertainment Group, INC
OPPOSITION: (Verified 8/22/24)
Judicial Council of California
Western Electrical Contractors Association
ARGUMENTS IN SUPPORT: Fox studio writes in support: “AB 3265 will be a catalyst for sustained job growth by streamlining the process for renovating sound stages, and updating production facilities to incorporate the latest graphics and audio technology. These investments will provide environmental benefits and keep productions in-state for decades to come. AB 3265 will meet the highest environmental standards set in prior streamlined environmental bills that have been signed into law. In addition, the bill contains language that will assure the creation of high paying jobs throughout the construction of the project through Labor Peace Agreements”
ARGUMENTS IN OPPOSITION: Judicial Council writes in Opposition to the bill: “Imposing an expedited 365-day judicial review timeline on top of existing CEQA calendar preferences is unworkable for several reasons.
• The 365-day timeline is problematic in practice. CEQA cases are inherently complex and time-consuming. Even in an unrealistic scenario in which no extensions of time were requested or granted for any aspect of a case, such a CEQA case would take an estimated six months just to get to a hearing, not to mention a decision. The reason this is an unrealistic scenario is because parties almost always request – and even stipulate to – continuances, delays, or other procedural extensions. Assuming a court was able to issue its decision within six months, that would leave only 185 days for proceedings in the Court of Appeal and the Supreme Court.
• CEQA cases often include ancillary administrative and non-CEQA judicial causes of action. Expediting review of CEQA causes of action does not necessarily lead to a faster resolution of the entire case, as non-CEQA causes of actions are frequently brought together with CEQA claims. These non-CEQA causes of action proceed under the usual civil procedure rules and timelines and can cause delays to the principal CEQA action.
• The expedited judicial review requirements for two additional infrastructure projects in AB 3265 will likely have an adverse impact on other cases with calendar preferences. Like other types of court calendar preferences, which the Judicial Council has opposed, setting an extremely tight timeline for deciding these complex cases has the practical effect of pushing other cases on the courts’ dockets to the back of the line, even those with their own statutorily mandated calendar preferences. This means that juvenile cases, criminal cases, wage theft cases, and civil cases in which a party is at risk of dying will take longer to resolve.”
ASSEMBLY FLOOR: 64-0, 5/9/24
AYES: Addis, Aguiar-Curry, Alanis, Alvarez, Arambula, Bauer-Kahan, Bennett, Berman, Bonta, Bryan, Calderon, Juan Carrillo, Wendy Carrillo, Chen, Connolly, Davies, Dixon, Essayli, Mike Fong, Vince Fong, Friedman, Gallagher, Garcia, Gipson, Hart, Holden, Hoover, Irwin, Jackson, Jones-Sawyer, Kalra, Lackey, Lee, Lowenthal, Maienschein, McCarty, McKinnor, Muratsuchi, Ortega, Pacheco, Papan, Jim Patterson, Joe Patterson, Pellerin, Quirk-Silva, Ramos, Rendon, Reyes, Rodriguez, Blanca Rubio, Sanchez, Santiago, Soria, Ta, Valencia, Villapudua, Waldron, Ward, Weber, Wicks, Wilson, Wood, Zbur, Robert Rivas
NO VOTE RECORDED: Bains, Boerner, Cervantes, Megan Dahle, Flora, Gabriel, Grayson, Haney, Low, Mathis, Stephanie Nguyen, Petrie-Norris, Luz Rivas, Schiavo, Ting, Wallis
Prepared by: Brynn Cook / E.Q. / (916) 651-4108
8/23/24 21:36:42
**** END ****
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | AB 3265 |
THIRD READING
Bill No: AB 3265
Author: Bryan (D)
Amended: 6/20/24 in Senate
Vote: 21
SENATE ENVIRONMENTAL QUALITY COMMITTEE: 6-0, 6/19/24
AYES: Allen, Gonzalez, Hurtado, Menjivar, Nguyen, Skinner
NO VOTE RECORDED: Dahle
SENATE JUDICIARY COMMITTEE: 10-0, 7/2/24
AYES: Umberg, Wilk, Allen, Ashby, Caballero, Durazo, Laird, Niello, Roth, Stern
NO VOTE RECORDED: Wahab
SENATE APPROPRIATIONS COMMITTEE: 7-0, 8/15/24
AYES: Caballero, Jones, Ashby, Becker, Bradford, Seyarto, Wahab
ASSEMBLY FLOOR: 64-0, 5/9/24 (Consent) - See last page for vote
SUBJECT: California Environmental Quality Act: environmental leadership media campus projects: judicial streamlining
SOURCE: Fox Entertainment Group, INC
DIGEST:
This bill authorizes a lead agency that is a city within Los Angeles to certify a media campus for an expedited administrative and 365-day judicial review process for litigation involving the California Environmental Quality Act (CEQA) if the project meets certain criteria.
ANALYSIS:
Existing law:
- Provides that, under CEQA, a lead agency determines whether a project is exempt from CEQA, or if it must do an initial study to determine if a project will have significant effects on the environment. If a project has no effect on the environment or effects that can be mitigated, the lead agency prepares a negative declaration (ND) or mitigated ND (MND). If the project will have significant impacts, the lead agency prepares an environmental impact report (EIR) to evaluate and propose mitigation measures for any effects on the environment, including impacts or likely impacts to land, air, water, minerals, flora, fauna, ambient noise, and historic or aesthetic significance. (Public Resources Code (PRC) §§21000 et seq.)
- Establishes processes and timelines for lawsuits that challenge a public agency's compliance with the requirements of CEQA including:
- Challenges must be filed in the superior court within 30 days of filing the notice of approval.
- The courts are required to give CEQA actions preference over all other civil actions.
- Requires the court to regulate the briefing schedule so that, to the extent feasible, hearings commence within one year of the filing of the appeal.
- Requires the plaintiff to request a hearing within 90 days of filing the petition.
- Requires the court to establish a briefing schedule and a hearing date, requires briefing to be completed within 90 days of the plaintiff’s request for hearing, and requires the hearing, to the extent feasible, to be held within 30 days thereafter. (PRC 21167 et seq.)
- Established CEQA administrative and judicial streamlining for specified “environmental leadership” projects through the Jobs and Economic Improvement Through Environmental Leadership Act (Act) of 2011 (AB 900, Buchanan, Chapter 354, Statutes of 2011). The Act was later extended and modified in 2021 (SB 7, Atkins, Chapter 19, Statutes of 2021). (PRC §21178 et seq.)
- Establishes expedited judicial and administrative CEQA processes for a broad swath of energy, transportation, water, and semiconductor projects eligible for expedited judicial review under CEQA in SB 149 (Caballero, Chapter 60, Statutes of 2023). Projects must meet certain environmental and labor criteria to be eligible for this certification. The streamlining certification ends January 1, 2033.
This bill:
- Establishes administrative and judicial CEQA streamlining for environmental leadership media campus projects (ELMCPs) where the lead agency is a city within Los Angeles and the lead agency certifies the project following its determination and the ensuing criteria are met:
- The project will result in an investment of at least one billion dollars in California.
- The project will be Leadership in Energy and Environmental Design (LEED) gold certified or better for all new construction. Any new construction or major renovation of existing buildings that is not eligible for LEED certification will achieve comparable standards for energy and water efficiency.
- The project does not result in any net additional greenhouse gas (GHG) emissions, including, but not limited to, from employee transportation, as specified.
- The project will generate at least 1,000 jobs during construction.
- The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, employs a skilled and trained workforce, as defined, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment. These requirements do not apply to a contractor or subcontractor performing work that is subject to a project labor agreement.
- The project applicant demonstrates compliance with specified recycling requirements.
- If the project is located in a disadvantaged community, the project shall mitigate any impacts within the community.
- The project will achieve a reduction in vehicle miles traveled per capita of at least 15 percent compared to existing development.
- The project applicant agrees that all mitigation measures required pursuant to CEQA and any other environmental measures required by this bill shall be conditions of approval of the project, and those conditions will be fully enforceable by the lead agency.
- The project applicant agrees to pay any additional costs incurred by the courts in hearing and deciding any case subject to this section, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council.
- The project applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with review and consideration of the project pursuant to this division, in a form and manner specified by the lead agency for the project.
- Requires the Judicial Council to adopt a rule of court to establish procedures that require resolution, to the extent feasible, within 365 days, including any appeals, of a lawsuit challenging the certification of the EIR or any project approvals for a certified ELMCP.
- Prohibits these procedures from applying if the applicant fails to notify a lead agency prior to the release of the draft EIR for public comment.
- Makes related findings.
Background
- The A, B, C’s of CEQA. CEQA is designed to (a) make government agencies and the public aware of the environmental impacts of a proposed project, (b) ensure the public can take part in the review process, and (c) identify and implement measures to mitigate or eliminate any negative impact the project may have on the environment. CEQA is enforced by civil lawsuits that can challenge any project’s environmental review. Nonprofits, private individuals, public agencies, advocacy groups, and other organizations can all file lawsuits under CEQA.
Under CEQA, projects (unless they have a specific exemption) must undergo environmental analysis. This process starts with an initial study which determines what level of further environmental review is needed for a given project. If a project has no significant effects on the environment, or if those effects can be fully mitigated, the project can move forward with a negative declaration (ND) or mitigated negative declaration (MND). If the initial study finds that the project has potential significant effects on the environment, then a full EIR is conducted. An EIR provides a thorough environmental review of a proposed project, analyzing the significant direct and indirect environmental impacts of a proposed project on water quality, transportation, air quality and greenhouse gas emissions, terrestrial and aquatic biological resources, surface and subsurface hydrology, land use and agricultural resources, aesthetics, geology and soils, recreation, public services and utilities such as water supply and wastewater disposal, and cultural resources, among other factors. The EIR also includes proposed mitigation measures for any significant effects that it identifies and considers alternatives to the proposed project.
- CEQA streamlining. The Legislature has developed streamlining measures to speed CEQA lawsuits against certain projects through the courts. In current law, CEQA streamlining entails both judicial and administrative streamlining. Judicial streamlining requires that a CEQA lawsuit be heard in 270 days, including all appeals, as feasible. Administrative streamlining requires projects to prepare the administrative record, the comprehensive document at the heart of a CEQA case, at the same time as the environmental review documents are prepared. Preparing these documents concurrently, instead of sequentially, saves time if there is a lawsuit. These streamlining measures shorten what is potentially the lengthiest portion of the CEQA process—litigation—while retaining the environmental review and public engagement offered under CEQA.
In 2011, the Legislature passed the first CEQA streamlining certification program with the Jobs and Economic Improvement Through Environmental Leadership Act (Leadership Act), which created CEQA streamlining for residential, retail, commercial, sports, and recreational use projects that were certified as Environmental Leadership Development Projects (ELDP) by the Governor (AB 900, Buchanan, Chapter 354, Statutes of 2011). The ELDP program was further extended and modified in 2021 with (SB 7, Atkins, Chapter 19, Statutes of 2021). In 2023, The Legislature expanded these same streamlining provisions for certain energy, transportation, and water infrastructure projects (SB 149, Caballero, Chapter 60, Statutes of 2023).
- Streamlining Stadiums. In addition to streamlining programs for certain types of projects, the Legislature has also created CEQA streamlining for a number of one-off projects for stadiums including:
- SB 292 (Padilla, Chapter 353, Statutes of 2011) proposed a downtown Los Angeles football stadium and convention center that would achieve specified traffic and air quality mitigations. This project has not proceeded.
- SB 743 (Steinberg, Chapter 386, Statutes of 2013) established special CEQA procedures modeled after SB 292 for the Sacramento Kings arena project and included specified traffic and air quality mitigations.
- AB 734 (Bonta, Chapter 959, Statutes of 2018) authorized the Governor to certify and establish special CEQA procedures modeled after AB 900 for, the Oakland Sports and Mixed-Use Project if the project met specified conditions. Unlike AB 900, AB 734 required that 50% of the GHG emissions reductions necessary to achieve the zero-net additional GHG emissions requirement be from on-site and local reduction measures, limited the type of GHG offset credits that can be purchased to achieve the other 50% of the necessary GHG emissions reductions and required a transportation demand management plan that achieves a 20% reduction in vehicle trips.
- AB 987 (Kamlager-Dove, Chapter 961, Statutes of 2018) was similar to AB 734 but applied to a proposed basketball arena for the Los Angeles Clippers in Inglewood.
The specific criteria that projects must meet to be eligible for CEQA streamlining varies by project and process, but all are intended to ensure that projects meet high environmental and labor standards. In current law environmental criteria for streamlining includes requirements such as achieving Leadership in Energy and Environmental Design (LEED) Gold certification and being greenhouse gas neutral. SB 149 (Caballero, Chapter 60, Statutes of 2023) also includes a specific equity provision that requires that projects both minimize significant environmental impacts in disadvantaged communities and take mitigation measures that directly benefit the affected community. In offering CEQA streamlining for projects that meet these high standards, California has been able to promote projects that align with the State’s environmental, climate, and labor goals.
Comments
- Purpose of Bill. According to the author, “California has a rich history as the entertainment capital of the world. However, the construction of soundstages in California has not kept pace with the recent growth in the production of film, scripted television and streaming content which forces more production outside of California. AB 3265 would allow a streamlined review and approval process for “environmental leadership media campus projects” that will foster studio construction and renovation within Los Angeles County. These projects will generate thousands of full-time jobs during construction and thousands of additional permanent jobs once they are constructed and operating.”
- Everyone to the front? By adding a new project type to the front of the queue for judicial review, this bill may result in longer judicial review times for existing projects. When new projects are added to the “front of the line”, that designation becomes less meaningful to all the projects in the queue. Judicial review for ELDP-certified projects already takes longer than 270 days, and, to date, there have been only a small number of projects that have used this streamlining. By giving expedited judicial review to another project type without changing the capacity of the courts to support this expedited review, this proposal may slow judicial review for other projects, including important new housing and infrastructure projects.
This bill may not be as disruptive to other CEQA streamlined projects since it establishes a longer expedited judicial timeline of 365 instead of 270 days which is more typical for CEQA streamlining measures.
- Does CEQA streamlining work? A 2019 report by the Senate Office of Research entitled “Review of Environmental Leadership Development Projects” tracked the timeline of ELDP projects from 2011 to 2018. According to the report, 19 projects were submitted for certification during AB 900’s operation. Of those that were selected for certification and moved forward with the project, the report found that no ELDP project was actually reviewed within 270 days. However, the report also found that projects were reviewed under a faster timeline compared to other similar projects. According to the report, the average time for an ELDP-comparable project to wind its way through the judicial review process was 3-5 years, meaning that the 1-2-year timeline for ELDP projects represents significant time savings.
Based on data provided by the Judicial Council, of the 30 projects that have qualified for expedited CEQA review since 2011, only four projects have needed expedited legal review to defend against a lawsuit. Of those four cases, three were high-profile stadium projects that, in some cases, utilized taxpayer money to build a private facility. Notably, in addition to the relatively low rate of litigation, of those 19 projects that qualified for expedited review another four were either terminated or withdrawn, and thus never built, due to financial or other business considerations and not environmentally-related legal exposure.
Related/Prior Legislation
SB 1342 (Atkins, 2024) adds two infrastructure projects in San Diego County to the list of infrastructure projects eligible for California Environmental Quality Act (CEQA) judicial and administrative streamlining under SB 149 (Caballero, Chapter 60, Statutes of 2023). This bill is awaiting hearing on the assembly floor.
SB 149 (Caballero, Chapter 60, Statutes of 2023) makes a broad swath of energy, transportation, water, and semiconductor projects eligible for expedited judicial review under CEQA. Projects must meet certain environmental and labor criteria to be eligible for certification. The streamlining certification ends January 1, 2033.
SB 7 (Atkins, Chapter 19, Statutes of 2021) extends and expands expedited CEQA administrative and judicial review procedures in the Leadership Act for ELDPs. Additionally, this bill expands the Leadership Act to include smaller housing projects.
SB 44 (Allen, Chapter 633, Statutes of 2021) establishes, until January 1, 2025, a 365-day expedited administrative and judicial review of environmental review and approvals granted for “environmental leadership transit projects” located within the County of Los Angeles that meet specified requirements.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
SUPPORT: (Verified 8/15/24)
Fox Entertainment Group, INC (source)
OPPOSITION: (Verified 8/15/24)
Judicial Council of California
Western Electrical Contractors Association
ARGUMENTS IN SUPPORT: Fox studio writes in support: “AB 3265 will be a catalyst for sustained job growth by streamlining the process for renovating sound stages, and updating production facilities to incorporate the latest graphics and audio technology. These investments will provide environmental benefits and keep productions in-state for decades to come. AB 3265 will meet the highest environmental standards set in prior streamlined environmental bills that have been signed into law. In addition, the bill contains language that will assure the creation of high paying jobs throughout the construction of the project through Labor Peace Agreements”
ARGUMENTS IN OPPOSITION: Judicial Council writes in Opposition to the bill: “Imposing an expedited 365-day judicial review timeline on top of existing CEQA calendar preferences is unworkable for several reasons.
• The 365-day timeline is problematic in practice. CEQA cases are inherently complex and time-consuming. Even in an unrealistic scenario in which no extensions of time were requested or granted for any aspect of a case, such a CEQA case would take an estimated six months just to get to a hearing, not to mention a decision. The reason this is an unrealistic scenario is because parties almost always request – and even stipulate to – continuances, delays, or other procedural extensions. Assuming a court was able to issue its decision within six months, that would leave only 185 days for proceedings in the Court of Appeal and the Supreme Court.
• CEQA cases often include ancillary administrative and non-CEQA judicial causes of action. Expediting review of CEQA causes of action does not necessarily lead to a faster resolution of the entire case, as non-CEQA causes of actions are frequently brought together with CEQA claims. These non-CEQA causes of action proceed under the usual civil procedure rules and timelines and can cause delays to the principal CEQA action.
• The expedited judicial review requirements for two additional infrastructure projects in AB 3265 will likely have an adverse impact on other cases with calendar preferences. Like other types of court calendar preferences, which the Judicial Council has opposed, setting an extremely tight timeline for deciding these complex cases has the practical effect of pushing other cases on the courts’ dockets to the back of the line, even those with their own statutorily mandated calendar preferences. This means that juvenile cases, criminal cases, wage theft cases, and civil cases in which a party is at risk of dying will take longer to resolve.”
ASSEMBLY FLOOR: 64-0, 5/9/24
AYES: Addis, Aguiar-Curry, Alanis, Alvarez, Arambula, Bauer-Kahan, Bennett, Berman, Bonta, Bryan, Calderon, Juan Carrillo, Wendy Carrillo, Chen, Connolly, Davies, Dixon, Essayli, Mike Fong, Vince Fong, Friedman, Gallagher, Garcia, Gipson, Hart, Holden, Hoover, Irwin, Jackson, Jones-Sawyer, Kalra, Lackey, Lee, Lowenthal, Maienschein, McCarty, McKinnor, Muratsuchi, Ortega, Pacheco, Papan, Jim Patterson, Joe Patterson, Pellerin, Quirk-Silva, Ramos, Rendon, Reyes, Rodriguez, Blanca Rubio, Sanchez, Santiago, Soria, Ta, Valencia, Villapudua, Waldron, Ward, Weber, Wicks, Wilson, Wood, Zbur, Robert Rivas
NO VOTE RECORDED: Bains, Boerner, Cervantes, Megan Dahle, Flora, Gabriel, Grayson, Haney, Low, Mathis, Stephanie Nguyen, Petrie-Norris, Luz Rivas, Schiavo, Ting, Wallis
Prepared by: Brynn Cook / E.Q. / (916) 651-4108
8/19/24 17:46:35
SENATE COMMITTEE ON APPROPRIATIONS
Senator Anna Caballero, Chair
2023 - 2024 Regular Session
AB 3265 (Bryan) - California Environmental Quality Act: environmental leadership media campus projects: judicial streamlining
Version: June 20, 2024 | Policy Vote: E.Q. 6 - 0, JUD. 10 - 0 |
Urgency: No | Mandate: Yes |
Hearing Date: August 5, 2024 | Consultant: Ashley Ames |
Bill Summary:
This bill would authorize a lead agency that is a city within the County of Los Angeles to certify a media campus for an expedited administrative and 365-day judicial review process for litigation involving the California Environmental Quality Act (CEQA) if the project meets certain criteria.
Fiscal Impact:
- Unknown but potentially significant cost pressure (General Fund) to the state-funded court system to process and hear challenges to the project's environmental review within the timeframes prescribed by the bill. (See staff comments for details.)
Background:
The Legislature has developed streamlining measures to speed CEQA lawsuits against certain projects through the courts. In current law, CEQA streamlining entails both judicial and administrative streamlining. Judicial streamlining requires that a CEQA lawsuit be heard in 270 days, including all appeals, as feasible. Administrative streamlining requires projects to prepare the administrative record, the comprehensive document at the heart of a CEQA case, at the same time as the environmental review documents are prepared. Preparing these documents concurrently, instead of sequentially, saves time if there is a lawsuit. These streamlining measures shorten what is potentially the lengthiest portion of the CEQA process—litigation—while retaining the environmental review and public engagement offered under CEQA.
In 2011, the Legislature passed the first CEQA streamlining certification program with the Jobs and Economic Improvement Through Environmental Leadership Act (Leadership Act), which created CEQA streamlining for residential, retail, commercial, sports, and recreational use projects that were certified as Environmental Leadership Development Projects (ELDP) by the Governor (AB 900, Buchanan, Chapter 354, Statutes of 2011). The ELDP program was further extended and modified in 2021 with (SB 7, Atkins, Chapter 19, Statutes of 2021). In 2023, The Legislature expanded these same streamlining provisions for certain energy, transportation, and water infrastructure projects (SB 149, Caballero, Chapter 60, Statutes of 2023).
Streamlining Stadiums. In addition to streamlining programs for certain types of projects, the Legislature has also created CEQA streamlining for a number of one-off projects for stadiums including:
- SB 292 (Padilla, Chapter 353, Statutes of 2011) proposed a downtown Los Angeles football stadium and convention center that would achieve specified traffic and air quality mitigations. This project has not proceeded.
- SB 743 (Steinberg, Chapter 386, Statutes of 2013) established special CEQA procedures modeled after SB 292 for the Sacramento Kings arena project and included specified traffic and air quality mitigations.
- AB 734 (Bonta, Chapter 959, Statutes of 2018) authorized the Governor to certify and establish special CEQA procedures modeled after AB 900 for, the Oakland Sports and Mixed-Use Project if the project met specified conditions. Unlike AB 900, AB 734 required that 50% of the GHG emissions reductions necessary to achieve the zero-net additional GHG emissions requirement be from on-site and local reduction measures, limited the type of GHG offset credits that can be purchased to achieve the other 50% of the necessary GHG emissions reductions and required a transportation demand management plan that achieves a 20% reduction in vehicle trips.
- AB 987 (Kamlager-Dove, Chapter 961, Statutes of 2018) was similar to AB 734 but applied to a proposed basketball arena for the Los Angeles Clippers in Inglewood.
The specific criteria that projects must meet to be eligible for CEQA streamlining varies by project and process, but all are intended to ensure that projects meet high environmental and labor standards. In current law environmental criteria for streamlining includes requirements such as achieving Leadership in Energy and Environmental Design (LEED) Gold certification and being greenhouse gas neutral. SB 149 (Caballero, Chapter 60, Statutes of 2023) also includes a specific equity provision that requires that projects both minimize significant environmental impacts in disadvantaged communities and take mitigation measures that directly benefit the affected community. In offering CEQA streamlining for projects that meet these high standards, California has been able to promote projects that align with the State’s environmental, climate, and labor goals.
Proposed Law:
This bill would authorize a lead agency that is a city within the County of Los Angeles to certify a media campus for an expedited administrative and 365-day judicial review process for litigation involving CEQA if the project meets certain criteria. Specifically, this bill would:
- For CEQA-based challenges to an EIR or approval for “environmental leadership media campus projects” (ELMCPs), require that the Judicial Council adopt rules of court that require the challenge, including any potential appeals to the Court of Appeal or Supreme Court, to be resolved, to the extent feasible, within 365 days of the filing of the certified record of proceedings with the court. Requires the Judicial Council to adopt a rule of court to establish procedures to implement these provisions.
- Provide an ELMCP must be certified by a lead agency within the County of Los Angeles and meet specified criteria, including, among others:
- The project will result in an investment of at least one billion dollars in California.
- The project does not result in any net additional greenhouse gas (GHG) emissions, including, but not limited to, from employee transportation, as specified.
- The project will generate at least 1,000 jobs during construction.
- The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, employs a skilled and trained workforce, as defined, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment. These requirements do not apply to a contractor or subcontractor performing work that is subject to a project labor agreement.
- The project applicant demonstrates compliance with specified recycling requirements.
- The project applicant agrees to pay any additional costs incurred by the courts in hearing and deciding any case subject to this bill, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council.
- The project applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with review and consideration of the project pursuant to CEQA, in a form and manner specified by the lead agency for the project.
- Establish requirements and timeframes for the preparation of an EIR, submission of public comment, the public hearing on the EIR, nonbinding mediation between the lead agency and the commenters, and preparation, certification, and submission to a court in a CEQA lawsuit, of the record of administrative proceedings.
Related Legislation:
SB 1342 (Atkins) would add two infrastructure projects in San Diego County to the list of infrastructure projects eligible for California Environmental Quality Act (CEQA) judicial and administrative streamlining under SB 149 (Caballero, Chapter 60, Statutes of 2023).
SB 149 (Caballero, Chapter 60, Statutes of 2023) makes a broad swath of energy, transportation, water, and semiconductor projects eligible for expedited judicial review under CEQA. Projects must meet certain environmental and labor criteria to be eligible for certification.
SB 7 (Atkins, Chapter 19, Statutes of 2021) extends and expands expedited CEQA administrative and judicial review procedures in the Leadership Act for ELDPs. Additionally, this bill expands the Leadership Act to include smaller housing projects.
SB 44 (Allen, Chapter 633, Statutes of 2021) establishes, until January 1, 2025, a 365-day expedited administrative and judicial review of environmental review and approvals granted for “environmental leadership transit projects” located within the County of Los Angeles that meet specified requirements.
Staff Comments:
This bill would result in potential cost pressure of an unknown amount to the state-funded court system to process and hear challenges to a project's environmental review within the timeframes prescribed by the bill. It is possible that, absent this bill, the state would face similar costs resulting from challenges to a project that would occur over a period longer than timeframes prescribed by this bill. However, the acceleration of some cases due to this bill could result in the need for extra personnel and resources in order for the courts to hear them within the required period.
The Judicial Council has studied the workload costs created by expedited CEQA judicial review requirements and determined that trial and appellate courts expend a combined average of $340,000 in workload costs on each case eligible for expedited judicial review.
-- END --
Senator Thomas Umberg, Chair
2023-2024 Regular Session
Bill No: AB 3265 (Author:Bryan)
Version: June 20, 2024
Hearing Date: July 2, 2024
Fiscal: Yes
Urgency: No
Consultant: AM
SUBJECT
California Environmental Quality Act: environmental leadership media campus projects: judicial streamlining
DIGEST
This bill authorizes a lead agency that is a city within the County of Los Angeles to certify a media campus for an expedited administrative and 365-day judicial review process for litigation involving the California Environmental Quality Act (CEQA) if the project meets certain criteria.
EXECUTIVE SUMMARY
For a handful of major projects that meet certain environmental standards, existing law provides for accelerated CEQA review and requires courts, to the extent feasible, to resolve judicial challenges arising from that process within 270 days of the filing of the administrative record. These provisions are intended to expedite beneficial development but entail potential tradeoffs with respect to the sufficiency of environmental review, the burden on courts, and access to justice for other litigants, a concern magnified by the judicial backlog arising from the COVID-19 pandemic.
This bill provides for expedited CEQA administrative and 365-day judicial review, including all appeals, for environmental leadership media campus projects that meet certain criteria and are certified by a lead agency that is a city within the County of Los Angeles. The bill is author sponsored and supported by the Fox Corporation. The bill is opposed by the Judicial Council of California and Western Electrical Contractors Association (WECA). The bill passed the Senate Environmental Quality Committee on a vote of 6 to 0.
PROPOSED CHANGES TO THE LAW
Existing law:
- Requires lead agencies with the principal responsibility for carrying out or approving a proposed discretionary project to prepare a negative declaration, mitigated declaration, or environmental impact report (EIR) for this action, unless the project is exempt from CEQA (CEQA includes various statutory exemptions, as well as categorical exemptions in the CEQA Guidelines). (Pub. Res. Code § 21100 et seq.)[1]
- Sets requirements relating to the preparation, review, comment, approval and certification of environmental documents, as well as procedures relating to an action or proceeding to attack, review, set aside, void, or annul various actions of a public agency on the grounds of noncompliance with CEQA. (§ 21165 et seq.)
- Established the Jobs and Economic Improvement through Environmental Leadership Act, which established CEQA administrative and judicial review procedures for an “environmental leadership” project. These provisions sunset on January 1, 2034. (§ 21178 et seq.)
- Authorizes certain transit projects to be eligible for expedited administrative and judicial review under CEQA. (§ 21168.6.9.)
This bill:
- For CEQA-based challenges to an EIR or approval for “environmental leadership media campus projects” (ELMCPs), requires that the Judicial Council adopt rules of court that require the challenge, including any potential appeals to the Court of Appeal or Supreme Court, to be resolved, to the extent feasible, within 365 days of the filing of the certified record of proceedings with the court. Requires the Judicial Council to adopt a rule of court to establish procedures to implement these provisions.
- Provides an ELMCP must be certified by a lead agency within the County of Los Angeles and meet specified criteria, including, among others:
- The project will result in an investment of at least one billion dollars in California.
- The project does not result in any net additional greenhouse gas (GHG) emissions, including, but not limited to, from employee transportation, as specified.
- The project will generate at least 1,000 jobs during construction.
- The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, employs a skilled and trained workforce, as defined, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment. These requirements do not apply to a contractor or subcontractor performing work that is subject to a project labor agreement.
- The project applicant demonstrates compliance with specified recycling requirements.
- The project applicant agrees to pay any additional costs incurred by the courts in hearing and deciding any case subject to this bill, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council.
- The project applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with review and consideration of the project pursuant to CEQA, in a form and manner specified by the lead agency for the project.
- Establishes requirements and timeframes for the preparation of an EIR, submission of public comment, the public hearing on the EIR, nonbinding mediation between the lead agency and the commenters, and preparation, certification, and submission to a court in a CEQA lawsuit, of the record of administrative proceedings.
COMMENTS
- Stated need for the bill
The author writes:
California has a rich history as the entertainment capital of the world. However, the construction of soundstages in California have not kept pace with the recent growth in the production of film, scripted television and streaming content which forces more production outside of California. AB 3265 would allow a streamlined review and approval process for “environmental leadership media campus projects” that will foster studio construction and renovation within Los Angeles County. These projects will generate thousands of full-time jobs during construction and thousands of additional permanent jobs once they are constructed and operating.
- CEQA
Enacted in 1970, CEQA requires state and local agencies to follow a set protocol to disclose and evaluate the significant environmental impacts of proposed projects and to adopt feasible measures to mitigate those impacts. CEQA itself applies to projects undertaken or requiring approval by public agencies, and, if more than one agency is involved, CEQA requires one of the agencies to be designated as the “lead agency.” The environmental review process required by CEQA consists of: (1) determining if the activity is a project; (2) determining if the project is exempt from CEQA; and (3) performing an initial study to identify the environmental impacts and, depending on the findings, preparing either a Negative Declaration (for projects with no significant impacts), a Mitigated Negative Declaration (for projects with significant impacts but that are revised in some form to avoid or mitigate those impacts), or an EIR (for projects with significant impacts).
An EIR must accurately describe the proposed project, identify and analyze each significant environmental impact expected to result from the proposed project, identify mitigation measures to reduce those impacts to the extent feasible, and evaluate a range of reasonable alternatives to the proposed project. Before approving any project that has received environmental review, an agency must make certain findings pertaining to the project’s environmental impact and any associated mitigation measures. If mitigation measures are required or incorporated into a project, the public agency must adopt a reporting or monitoring program to ensure compliance with those measures. To enforce the requirements of CEQA, a civil action may be brought under several code sections to attack, review, set aside, void, or annul the acts or decisions of a public agency for noncompliance with the act.
“CEQA operates, not by dictating proenvironmental outcomes, but rather by mandating that ‘decision makers and the public’ study the likely environmental effects of contemplated government actions and thus make fully informed decisions regarding those actions. … In other words, CEQA does not care what decision is made as long as it is an informed one.” (Citizens Coalition Los Angeles v. City of Los Angeles (2018) 26 Cal. App. 5th 561, 577.)
- Expedited judicial review under CEQA
Unlike other environmental laws specific to air resources, water resources, or the control of toxic substances, there is no statewide bureaucracy charged with enforcement of CEQA. Rather, it is enforced through citizen participation and litigation if necessary. Arguably, this makes the implementation of CEQA more efficient and expeditious than if a state agency were created to administer the law. Thus, CEQA litigation could more appropriately be characterized as mere enforcement.
Several provisions streamline judicial review of challenges to projects under CEQA, including:
- discovery is generally not allowed, as CEQA cases are generally restricted to review of the record;[2]
- concurrent preparation of the record of proceedings to enable judicial review to occur sooner;[3]
- counties with a population of over 200,000 must designate one or more judges to develop expertise on CEQA and hear CEQA cases (§ 21167.1 (b));
- both the Superior Court and the Court of Appeal must give CEQA lawsuits preference over all other civil actions (§ 21167.1(a)); and
- if feasible, the Court of Appeal must hear a CEQA appeal within one year of filing (§ 21167.1(a)).
Additionally, several bills have provided for a 270-day judicial review period for environmental leadership projects,[4] as well as for specified stadium projects,[5] and a San Diego transit and transportation facilities project.[6]
The principal framework associated with these provisions is AB 900 (Buchanan, Ch. 354, Stats. 2011), which were extended and revised by SB 7 (Atkins, Ch. 19; Stats. 2021). These provisions establish procedures for 270-day expedited judicial review for “environmental leadership” projects with a minimum investment of $100,000,000 that are certified by the Governor and meet specified conditions. Such projects include clean renewable energy projects, clean energy manufacturing projects, and LEED Gold-certified infill site projects with transportation efficiency 15 percent greater than comparable projects and zero net additional GHG emissions, and housing development projects with a minimum investment of $15,000,000.
A 2019 report entitled Review of Environmental Leadership Development Projects from the Senate Office of Research reviewed litigation under AB 900 and SB 743 (Steinberg, Ch. 386, Stats. 2013), which provided for 270-day review for the Sacramento Kings arena. The report found the following timelines, which under then-existing law began when the administrative record was certified[7] and include the trial court, court of appeal, and the Supreme Court’s denial of review, for those cases:
Project | Business days | Calendar days |
Kings arena | 243 | 352 |
Warriors arena | 257 | 376 |
8150 Sunset Boulevard | 395 | 578 |
The report concludes that these projects were reviewed under a faster timeline than normally would apply, benefiting the developers and providing upfront financial security. The report also states that “the impacts to the court from such a short timeline also should be taken into consideration when determining how fast the Legislature would like [AB 900] cases resolved,” and suggests a longer timeline may be appropriate.[8] In 2021, the Legislature enacted SB 44 (Allen, Ch. 663, Stats. 2021) to make certain transit projects eligible for expedited administrative and judicial review under CEQA within 365 calendar days, to the extent feasible. This bill includes the same 365-timeline for expedited judicial review.
- Statements in support
The Fox Corporation writes in support, stating:
According to a recent studio production space case study, Los Angeles has the largest number of stages, square footage, and talent pool (384, 5.2M, and 198K respectively), strong tech innovation, and is therefore well suited to form production bubbles for COVID precautions. The construction of soundstages in California has not kept pace with the recent growth in the production of film, scripted television and streaming content which forces more production outside of California. The segment of entertainment production that has had the most detrimental effect on California’s infrastructure is the loss of big-budget feature films which require the use of several large sound stages building complex sets.
Adding to the need for updating the State’s film and television production facilities is the arrival of digital technology. New cinematography, sound recording and editing tools have provided sophisticated visual and audio effects for filmmakers during production and post production. While technology has revolutionized the creative brilliance of the film and television industry, its deployment requires infrastructure improvements for high-speed internet connections and cloud-based storage solutions at California’s “media production campuses.”
Though the Los Angeles area has the largest number of soundstages of any city in the world, studios are operating near 100% capacity with waiting lists as long as five film productions deep for those spaces, financial advisor Deloitte said in a 2021 report. As a result, a number of studios and media production campuses are making hundreds of millions of dollars in investments to expand and improve their historic production facilities.
AB 3265 will be a catalyst for sustained job growth by streamlining the process for renovating sound stages, and updating production facilities to incorporate the latest graphics and audio technology. These investments will provide environmental benefits and keep productions in-state for decades to come. AB 3265 will meet the highest environmental standards set in prior streamlined environmental bills that have been signed into law. In addition, the bill contains language that will assure the creation of high paying jobs throughout the construction of the project through Labor Peace Agreements.
- Statements in opposition
Under separation of powers principles, the Legislature cannot constitutionally mandate that courts resolve cases on any particular timeframe. (See Saltonstall v. City of Sacramento (2014) 231 Cal.App.4th 837, 855-856 [upholding a similar 270-day expedited review provision for the Sacramento Kings arena only because it contained a “to the extent feasible” provision].) Writing in opposition, the Judicial Council argues that compliance with the 270-day review provision is not feasible, stating:
• The 365-day timeline is problematic in practice. CEQA cases are inherently complex and time-consuming. Even in an unrealistic scenario in which no extensions of time were requested or granted for any aspect of a case, such a CEQA case would take an estimated six months just to get to a hearing, not to mention a decision. The reason this is an unrealistic scenario is because parties almost always request – and even stipulate to – continuances, delays, or other procedural extensions. Assuming a court was able to issue its decision within six months, that would leave only 185 days for proceedings in the Court of Appeal and the Supreme Court. In a typical civil appeal, it takes more than 95 days from when a trial court decision becomes final just for the record on appeal to be prepared and filed in the Court of Appeal. This does not include any time for briefing, oral argument, analysis of the issues, or preparation of a decision by the court.
• CEQA cases often include ancillary administrative and non-CEQA judicial causes of action. Expediting review of CEQA causes of action does not necessarily lead to a faster resolution of the entire case, as non-CEQA causes of actions are frequently brought together with CEQA claims. These non-CEQA causes of action proceed under the usual civil procedure rules and timelines and can cause delays to the principal CEQA action.
These concerns are compounded by the congestion courts have experienced as a result of the COVID-19 pandemic, leaving some litigants without access to justice. This Committee held a joint hearing in February 2021 with the Assembly Judiciary Committee that sought to address this crisis. The background paper for the hearing stated: “For many of these litigants, their cases arise from critical needs and interests, such as eviction, domestic violence, child custody disputes, health care, and debt collection.”[9] The Judicial Council, in opposition, points out that expedited review provisions such as the one in this bill may entail zero-sum tradeoffs that could further delay justice for some:
[…] setting an extremely tight timeline for deciding these complex cases has the practical effect of pushing other cases on the courts’ dockets to the back of the line, even those with their own statutorily mandated calendar preferences. This means that juvenile cases, criminal cases, wage theft cases, and civil cases in which a party is at risk of dying will take longer to resolve.[10]
The Western Electrical Contractors Association (WECA), a self-titled “Merit Shop Employer Association,” opposes provisions in the bill related to project labor agreements. WECA writes that it “staunchly opposes project labor agreements (PLAs), considering them wasteful and discriminatory. In light of this, WECA strongly opposes including these provisions in AB 3265.”
SUPPORT
Fox Corporation
OPPOSITION
Judicial Council of California
Western Electrical Contractors Association (WECA)
RELATED LEGISLATION
Pending Legislation: None known.
Prior Legislation:
SB 7 (Atkins, Ch. 19; Stats. 2021) see Comment 3), above.
SB 44 (Allen, Ch. 663; Stats. 2021) see Comment 3), above.
AB 900 (Buchanan, Ch. 354, Stats. 2011) see Comment 3), above.
PRIOR VOTES
Senate Environmental Quality Committee (Ayes 6, Noes 0)
Assembly Floor (Ayes 64, Noes 0)
Assembly Appropriations Committee (Ayes 14, Noes 0)
Assembly Judiciary Committee (Ayes 11, Noes 0)
Assembly Natural Resources Committee (Ayes 10, Noes 0)
**************
All further references are to the Public Resources Code unless otherwise indicated. ↑
See Cadiz Land Co. v. Rail Cycle, LP (2000) 83 Cal.App.4th 74, 122. ↑
SB 122 (Jackson, Ch. 476, Stats. 2016). ↑
AB 900 (Buchanan, Ch. 354, Stats. 2011); SB 7 (Atkins, Ch. 19; Stats. 2021). ↑
SB 292 (Padilla, Ch. 353, Stats. 2011); SB 743 (Steinberg, Ch. 386, Stats. 2013) (see Saltonstall v. City of Sacramento (2014) 231 Cal.App.4th 837, 855-856); AB 734 (Bonta, Ch. 959, Stats. 2018); AB 987 (Kamlager-Dove, Ch. 961, Stats. 2018). ↑
AB 2731 (Gloria, Ch. 291, Stats. 2020). ↑
See id. at pp. 6-8 (noting some uncertainties in the calculation methodology). ↑
Id. at p. 15. ↑
Joint Informational Hearing of Assembly and Senate Committees on Judiciary: COVID and the Courts: Assessing the Impact on Access to Justice, Identifying Best Practices, and Plotting the Path Forward (Feb. 23, 2021) Background Paper, https://sjud.senate.ca.gov/content/2020-21-informationaloversight-hearings (as of Mar. 21, 2021). ↑
Under existing law, certain parties are entitled to calendar preference, including a party that is at least 70 years old and in ill health, a party in a personal injury or wrongful death matter who is under the age of 14, or a party that is unlikely to survive beyond another six months. (Code of Civ. Proc. § 36). Additionally, certain actions receive calendar preference, including appeals in probate proceedings, contested election cases, and actions for libel or slander by a person who holds any elective public office or a candidate for any such office alleged to have occurred during the course of an election campaign. (Code of Civ. Proc. § 44.) In fact, existing law already provides that both the Superior Court and the Court of Appeal must give CEQA lawsuits preference over all other civil actions. (§ 21167.1(a).) ↑
SENATE COMMITTEE ON ENVIRONMENTAL QUALITY
Senator Allen, Chair
2023 - 2024 Regular
Bill No: AB 3265
Author: | Bryan | ||
Version: | 4/9/2024 | Hearing Date: | 6/19/2024 |
Urgency: | No | Fiscal: | Yes |
Consultant: | Brynn Cook | ||
SUBJECT: California Environmental Quality Act: environmental leadership media campus projects: judicial streamlining
DIGEST: This bill authorizes a lead agency that is a city within Los Angeles to certify a media campus for an expedited administrative and 365-day judicial review process for litigation involving the California Environmental Quality Act (CEQA) if the project meets certain criteria.
ANALYSIS:
Existing law:
- Under CEQA, a lead agency determines whether a project is exempt from CEQA, or if it must do an initial study to determine if a project will have significant effects on the environment. If a project has no effect on the environment or effects that can be mitigated, the lead agency prepares a negative declaration (ND) or mitigated ND (MND). If the project will have significant impacts, the lead agency prepares an environmental impact report (EIR) to evaluate and propose mitigation measures for any effects on the environment, including impacts or likely impacts to land, air, water, minerals, flora, fauna, ambient noise, and historic or aesthetic significance. (Public Resources Code (PRC) §§21000 et seq.)
- Establishes processes and timelines for lawsuits that challenge a public agency's compliance with the requirements of CEQA including:
- Challenges must be filed in the superior court within 30 days of filing the notice of approval.
- The courts are required to give CEQA actions preference over all other civil actions.
- Requires the court to regulate the briefing schedule so that, to the extent feasible, hearings commence within one year of the filing of the appeal.
- Requires the plaintiff to request a hearing within 90 days of filing the petition.
- Requires the court to establish a briefing schedule and a hearing date, requires briefing to be completed within 90 days of the plaintiff’s request for hearing, and requires the hearing, to the extent feasible, to be held within 30 days thereafter. (PRC 21167 et seq.)
- Established CEQA administrative and judicial streamlining for specified “environmental leadership” projects through the Jobs and Economic Improvement Through Environmental Leadership Act (Act) of 2011 (AB 900, Buchanan, Chapter 354, Statutes of 2011). The Act was later extended and modified in 2021 (SB 7, Atkins, Chapter 19, Statutes of 2021). (PRC §21178 et seq.)
- Establishes expedited judicial and administrative CEQA processes for a broad swath of energy, transportation, water, and semiconductor projects eligible for expedited judicial review under CEQA in SB 149 (Caballero, Chapter 60, Statutes of 2023). Projects must meet certain environmental and labor criteria to be eligible for this certification. The streamlining certification ends January 1, 2033.
This bill:
- Establishes administrative and judicial CEQA streamlining for environmental leadership media campus projects (ELMCPs) where the lead agency is a city within Los Angeles and the lead agency certifies the project following its determination and the ensuing criteria are met:
- The project will result in an investment of at least one billion dollars in California.
- The project will be Leadership in Energy and Environmental Design (LEED) gold certified or better for all new construction. Any new construction or major renovation of existing buildings that is not eligible for LEED certification will achieve comparable standards for energy and water efficiency.
- The project does not result in any net additional greenhouse gas (GHG) emissions, including, but not limited to, from employee transportation, as specified.
- The project will generate at least 1,000 jobs during construction.
- The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, employs a skilled and trained workforce, as defined, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment. These requirements do not apply to a contractor or subcontractor performing work that is subject to a project labor agreement.
- The project applicant demonstrates compliance with specified recycling requirements.
- The project applicant agrees that all mitigation measures required pursuant to CEQA and any other environmental measures required by this bill shall be conditions of approval of the project, and those conditions will be fully enforceable by the lead agency.
- The project applicant agrees to pay any additional costs incurred by the courts in hearing and deciding any case subject to this section, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council.
- The project applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with review and consideration of the project pursuant to this division, in a form and manner specified by the lead agency for the project.
- Requires the Judicial Council to adopt a rule of court to establish procedures that require resolution, to the extent feasible, within 365 days, including any appeals, of a lawsuit challenging the certification of the EIR or any project approvals for a certified ELMCP.
- Prohibits these procedures from applying if the applicant fails to notify a lead agency prior to the release of the draft EIR for public comment.
- Makes related findings.
Background
- The A, B, C’s of CEQA. CEQA is designed to (a) make government agencies and the public aware of the environmental impacts of a proposed project, (b) ensure the public can take part in the review process, and (c) identify and implement measures to mitigate or eliminate any negative impact the project may have on the environment. CEQA is enforced by civil lawsuits that can challenge any project’s environmental review. Nonprofits, private individuals, public agencies, advocacy groups, and other organizations can all file lawsuits under CEQA.
Under CEQA, projects (unless they have a specific exemption) must undergo environmental analysis. This process starts with an initial study which determines what level of further environmental review is needed for a given project. If a project has no significant effects on the environment, or if those effects can be fully mitigated, the project can move forward with a negative declaration (ND) or mitigated negative declaration (MND). If the initial study finds that the project has potential significant effects on the environment, then a full EIR is conducted. An EIR provides a thorough environmental review of a proposed project, analyzing the significant direct and indirect environmental impacts of a proposed project on water quality, transportation, air quality and greenhouse gas emissions, terrestrial and aquatic biological resources, surface and subsurface hydrology, land use and agricultural resources, aesthetics, geology and soils, recreation, public services and utilities such as water supply and wastewater disposal, and cultural resources, among other factors. The EIR also includes proposed mitigation measures for any significant effects that it identifies and considers alternatives to the proposed project.
- CEQA streamlining. The Legislature has developed streamlining measures to speed CEQA lawsuits against certain projects through the courts. In current law, CEQA streamlining entails both judicial and administrative streamlining. Judicial streamlining requires that a CEQA lawsuit be heard in 270 days, including all appeals, as feasible. Administrative streamlining requires projects to prepare the administrative record, the comprehensive document at the heart of a CEQA case, at the same time as the environmental review documents are prepared. Preparing these documents concurrently, instead of sequentially, saves time if there is a lawsuit. These streamlining measures shorten what is potentially the lengthiest portion of the CEQA process—litigation—while retaining the environmental review and public engagement offered under CEQA.
In 2011, the Legislature passed the first CEQA streamlining certification program with the Jobs and Economic Improvement Through Environmental Leadership Act (Leadership Act), which created CEQA streamlining for residential, retail, commercial, sports, and recreational use projects that were certified as Environmental Leadership Development Projects (ELDP) by the Governor (AB 900, Buchanan, Chapter 354, Statutes of 2011). The ELDP program was further extended and modified in 2021 with (SB 7, Atkins, Chapter 19, Statutes of 2021). In 2023, The Legislature expanded these same streamlining provisions for certain energy, transportation, and water infrastructure projects (SB 149, Caballero, Chapter 60, Statutes of 2023).
- Streamlining Stadiums. In addition to streamlining programs for certain types of projects, the Legislature has also created CEQA streamlining for a number of one-off projects for stadiums including:
- SB 292 (Padilla, Chapter 353, Statutes of 2011) proposed a downtown Los Angeles football stadium and convention center that would achieve specified traffic and air quality mitigations. This project has not proceeded.
- SB 743 (Steinberg, Chapter 386, Statutes of 2013) established special CEQA procedures modeled after SB 292 for the Sacramento Kings arena project and included specified traffic and air quality mitigations.
- AB 734 (Bonta, Chapter 959, Statutes of 2018) authorized the Governor to certify and establish special CEQA procedures modeled after AB 900 for, the Oakland Sports and Mixed-Use Project if the project met specified conditions. Unlike AB 900, AB 734 required that 50% of the GHG emissions reductions necessary to achieve the zero-net additional GHG emissions requirement be from on-site and local reduction measures, limited the type of GHG offset credits that can be purchased to achieve the other 50% of the necessary GHG emissions reductions and required a transportation demand management plan that achieves a 20% reduction in vehicle trips.
- AB 987 (Kamlager-Dove, Chapter 961, Statutes of 2018) was similar to AB 734 but applied to a proposed basketball arena for the Los Angeles Clippers in Inglewood.
The specific criteria that projects must meet to be eligible for CEQA streamlining varies by project and process, but all are intended to ensure that projects meet high environmental and labor standards. In current law environmental criteria for streamlining includes requirements such as achieving Leadership in Energy and Environmental Design (LEED) Gold certification and being greenhouse gas neutral. SB 149 (Caballero, Chapter 60, Statutes of 2023) also includes a specific equity provision that requires that projects both minimize significant environmental impacts in disadvantaged communities and take mitigation measures that directly benefit the affected community. In offering CEQA streamlining for projects that meet these high standards, California has been able to promote projects that align with the State’s environmental, climate, and labor goals.
Comments
- Purpose of Bill. According to the author, “California has a rich history as the entertainment capital of the world. However, the construction of soundstages in California has not kept pace with the recent growth in the production of film, scripted television and streaming content which forces more production outside of California. AB 3265 would allow a streamlined review and approval process for “environmental leadership media campus projects” that will foster studio construction and renovation within Los Angeles County. These projects will generate thousands of full-time jobs during construction and thousands of additional permanent jobs once they are constructed and operating.”
- Follow the Leaders. Previous legislation to streamline specified stadium projects has established strong environmental criteria, including that projects be LEED gold, mitigate GHGs, and mitigate transportation impacts. AB 3265 includes many of these environmental criteria but notably does not explicitly consider transportation impacts.
Two sports arena projects (the Oakland Sports and mixed-use project and the Los Angeles Clippers basketball arena) established strong clear transportation reduction requirements. AB 987 for the Clippers basketball arena required that the project have a transportation demand management plan that achieves a 15% reduction in vehicle trips by 2030 and required a transportation demand management plan that achieves a 20% reduction in vehicle trips. AB 734 for the Oakland Sports and Mixed Use project required a transportation demand management plan that achieves a 20% reduction in vehicle trips in addition to requiring the project achieve zero-net additional GHGs and specified that only 50% of these GHG reductions could come from offsets. Requiring both transportation planning to reduce vehicle miles traveled (VMT) and capping on-site GHG emissions ensures that benefits stay localized. This includes the benefits associated with reducing traffic, congestion, and related GHG and air pollution emissions.
The author and committee may wish to specify that in order to be eligible for CEQA streamlining, ELMCP’s must achieve a 15% reduction in vehicle miles traveled per capita compared to existing development, as determined by the Governor’s Office of Planning and Research, and that 50% of the GHG emissions reductions necessary to achieve the zero-net additional GHG emissions requirement be from on-site and local reduction measures.
Existing CEQA streamlining provisions require that projects, where applicable, meet a LEED Gold standards. AB 3265 mirrors that requirement for ELMCPS, with exclusion for structures on a ELCMP campus that may not be eligible for USGBC LEED certification because they do not map onto the traditional form of building structure that LEED certification checklists were designed for. F For example, ELCMP’s may include sound stages, production basecamp facilities, and other facilities which the author’s office notes do not easily fit the checklist for LEED certification.To account for this, the bill specifies that any new construction or renovation that is not eligible for LEED certification will achieve comparable standards for energy and water efficiency. AB 3265 does not specify what entity would determine whether or not a project is readily LEED certified or what specific criteria would qualify as LEED comparable standards. To clarify this point, the author and committee may wish to specify that non-LEED projects must meet Tier 1 energy efficiency standards, as described in the California Green Building Standards Code.
Finally, the significant and recent CEQA streamlining measure adopted for a large swath of energy, water, and transportation infrastructure projects in 2023 (SB 149, Caballero, Chapter 60, Statutes of 2023), added an explicit equity provision that requires that projects both minimize significant environmental impacts in disadvantaged communities and take mitigation measures that directly benefit affected communities. SB 149 set the bar for equity consideration for projects receiving CEQA streamlining: the author and committee may wish to add these equity provisions to AB 3265.
- Everyone to the front? By adding a new project type to the front of the queue for judicial review, AB 3265 may result in longer judicial review times for existing projects. When new projects are added to the “front of the line”, that designation becomes less meaningful to all the projects in the queue. Judicial review for ELDP-certified projects already takes longer than 270 days, and, to date, there have been only a small number of projects that have used this streamlining. By giving expedited judicial review to another project type without changing the capacity of the courts to support this expedited review, this proposal may slow judicial review for other projects, including important new housing and infrastructure projects.
AB 3265 may not be as disruptive to other CEQA streamlined projects since it establishes a longer expedited judicial timeline of 365 instead of 270 days which is more typical for CEQA streamlining measures.
- Does CEQA streamlining work? A 2019 report by the Senate Office of Research entitled “Review of Environmental Leadership Development Projects” tracked the timeline of ELDP projects from 2011 to 2018. According to the report, 19 projects were submitted for certification during AB 900’s operation. Of those that were selected for certification and moved forward with the project, the report found that no ELDP project was actually reviewed within 270 days. However, the report also found that projects were reviewed under a faster timeline compared to other similar projects. According to the report, the average time for an ELDP-comparable project to wind its way through the judicial review process was 3-5 years, meaning that the 1-2-year timeline for ELDP projects represents significant time savings.
Based on data provided by the Judicial Council, of the 30 projects that have qualified for expedited CEQA review since 2011, only four projects have needed expedited legal review to defend against a lawsuit. Of those four cases, three were high-profile stadium projects that, in some cases, utilized taxpayer money to build a private facility. Notably, in addition to the relatively low rate of litigation, of those 19 projects that qualified for expedited review another four were either terminated or withdrawn, and thus never built, due to financial or other business considerations and not environmentally-related legal exposure.
- Committee amendments. Staff recommends the committee adopt the bolded amendments contained in comment 2.
DOUBLE REFERRAL:
If this measure is approved by the Senate Environmental Quality Committee, the do pass motion must include the action to re-refer the bill to the Senate Judiciary Committee.
Related/Prior Legislation
SB 1342 (Atkins) adds two infrastructure projects in San Diego County to the list of infrastructure projects eligible for California Environmental Quality Act (CEQA) judicial and administrative streamlining under SB 149 (Caballero, Chapter 60, Statutes of 2023). This bill passed out of the Senate and is currently awaiting hearing in Assembly Natural Resources Committee.
SB 149 (Caballero, Chapter 60, Statutes of 2023) makes a broad swath of energy, transportation, water, and semiconductor projects eligible for expedited judicial review under CEQA. Projects must meet certain environmental and labor criteria to be eligible for certification. The streamlining certification ends January 1, 2033.
SB 7 (Atkins, Chapter 19, Statutes of 2021) extends and expands expedited CEQA administrative and judicial review procedures in the Leadership Act for ELDPs. Additionally, this bill expands the Leadership Act to include smaller housing projects.
SB 44 (Allen, Chapter 633, Statutes of 2021) establishes, until January 1, 2025, a 365-day expedited administrative and judicial review of environmental review and approvals granted for “environmental leadership transit projects” located within the County of Los Angeles that meet specified requirements.
Arguments in Support: Fox studio writes in support: “AB 3265 will be a catalyst for sustained job growth by streamlining the process for renovating sound stages, and updating production facilities to incorporate the latest graphics and audio technology. These investments will provide environmental benefits and keep productions in-state for decades to come. AB 3265 will meet the highest environmental standards set in prior streamlined environmental bills that have been signed into law. In addition, the bill contains language that will assure the creation of high paying jobs throughout the construction of the project through Labor Peace Agreements”
Arguments in Opposition: Judcial Council writes in Opposition to the bill: “Imposing an expedited 365-day judicial review timeline on top of existing CEQA alendar preferences is unworkable for several reasons.
• The 365-day timeline is problematic in practice. CEQA cases are inherently complex and time-consuming. Even in an unrealistic scenario in which no extensions of time were requested or granted for any aspect of a case, such a CEQA case would take an estimated six months just to get to a hearing, not to mention a decision. The reason this is an unrealistic scenario is because parties almost always request – and even stipulate to – continuances, delays, or other procedural extensions. Assuming a court was able to issue its decision within six months, that would leave only 185 days for proceedings in the Court of Appeal and the Supreme Court.
• CEQA cases often include ancillary administrative and non-CEQA judicial causes of action. Expediting review of CEQA causes of action does not necessarily lead to a faster resolution of the entire case, as non-CEQA causes of actions are frequently brought together with CEQA claims. These non-CEQA causes of action proceed under the usual civil procedure rules and timelines and can cause delays to the principal CEQA action.
• The expedited judicial review requirements for two additional infrastructure projects in AB 3265 will likely have an adverse impact on other cases with calendar preferences. Like other types of court calendar preferences, which the Judicial Council has opposed, setting an extremely tight timeline for deciding these complex cases has the practical effect of pushing other cases on the courts’ dockets to the back of the line, even those with their own statutorily mandated calendar preferences. This means that juvenile cases, criminal cases, wage theft cases, and civil cases in which a party is at risk of dying will take longer to resolve.”
SUPPORT:
Fox Entertainment Group, INC.
OPPOSITION:
Judicial Council of California
Western Electrical Contractors Association
Positions reflect letters received by noon one week prior to the hearing.
-- END --
Date of Hearing: May 1, 2024
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Buffy Wicks, Chair
ABPCA Bill Id:AB 3265
Author:(Bryan) – As Amended Ver:April 9, 2024
Policy Committee: | Natural Resources | Vote: | 10 - 0 |
Judiciary | 11 - 0 | ||
|
|
Urgency: No State Mandated Local Program: Yes Reimbursable: No
SUMMARY:
This bill establishes expedited administrative and judicial review procedures under the California Environmental Quality Act (CEQA) for “environmental leadership media campus projects” (ELMCP) in Los Angeles County (LA County).
Specifically, this bill, among other things:
- Requires a city within LA County that is the lead agency for an ELMCP to certify the project for streamlining pursuant to this bill if the city finds that a number of specified conditions will be met.
- Requires, on or before July 1, 2025, the Judicial Council to adopt a rule of court to establish procedures that require resolution, to the extent feasible, within 365 days, including any appeals, of a lawsuit challenging the certification of an environmental impact report (EIR) or any project approvals for a certified ELMCP.
- Prohibits these procedures from applying if an applicant fails to notify a lead agency prior to the release of a draft EIR for public comment.
- Establishes minimum and other format requirements for the draft and final EIR for an ELMCP.
FISCAL EFFECT:
1) Likely absorbable costs to the courts. This bill requires a project applicant to pay any additional costs incurred by the courts in hearing and deciding any case subject to this bill, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by Judicial Council. Judicial Council notes that expedited cases create cost and staffing pressures on the courts. However, as the projects authorized under this bill are similar to those included in previous CEQA-related bills, Judicial Council expects it would amend the existing rule of court 3.2240 – which provides a $180,000 filing fee for specific streamlined CEQA projects – to include ELMCPs. This per-case fee is expected to cover any additional expenses incurred by a court related to ELMCP filings.
2) Judicial Council estimates minor and absorbable costs to create or amend rules of court.
COMMENTS:
1) Purpose. According to the author:
California has a rich history as the entertainment capital of the world. However, the construction of soundstages in California have not kept pace with the recent growth in the production of film, scripted television and streaming content which forces more production outside of California. AB 3265 would allow a streamlined review and approval process for “environmental leadership media campus projects” that will foster studio construction and renovation within Los Angeles County. These projects will generate thousands of full-time jobs during construction and thousands of additional permanent jobs once they are constructed and operating.
- Background. CEQA provides a process for evaluating the environmental effects of applicable projects undertaken or approved by public agencies. If a project is not exempt from CEQA, the lead agency prepares an initial study to determine whether the project may have a significant effect on the environment. If the initial study shows the project would not have a significant effect on the environment, the lead agency must prepare a negative declaration. If the initial study shows that project may have a significant effect, the lead agency must prepare an EIR.
Generally, an EIR must accurately describe the proposed project, identify and analyze each significant environmental impact expected to result from the proposed project, identify mitigation measures to reduce those impacts to the extent feasible, and evaluate a range of reasonable alternatives to the proposed project. Prior to approving any project that has received environmental review, the lead agency must make certain findings. If mitigation measures are required or incorporated into a project, the lead agency must adopt a reporting or monitoring program to ensure compliance with those measures. Once a final EIR is certified, and a project is subsequently approved, any litigation over the environmental review of the project can begin.
Over the past decade, the state has adopted several measures that permit cases involving CEQA to obtain preferred, fast-track treatment in the courts. According to the Assembly Natural Resources Committee analysis of this bill, to date, approximately 30 projects have been eligible for expedited judicial review. Many of these projects have not proceeded to final approval and construction, and only four projects have been challenged in court.
This bill seeks to boost the development of state-of-the-art film and television production facilities by providing these facilities access to streamlined CEQA review should the projects be challenged. Among other conditions, to ensure these projects do not pose major environmental risks, the projects must be able to achieve LEED gold certification, must not result in any net additional greenhouse gas emissions, and must generate at least 1,000 skilled construction jobs.
Analysis Prepared by: Nikita Koraddi / APPR. / (916) 319-2081
Date of Hearing: April 23, 2024
ASSEMBLY COMMITTEE ON JUDICIARY
Ash Kalra, Chair
ABPCA Bill Id:AB 3265
Author:(Bryan) – As Amended Ver:April 9, 2024
PROPOSED CONSENT
SUBJECT: California Environmental Quality Act: environmental leadership media campus projects: judicial streamlining
KEY ISSUE: should a 365-day expedited judicial review procedure be provided to environmental leadership media campus projects that face legal challenges for noncompliance with the California environmental quality act?
SYNOPSIS
Over the past decade, California has adopted several measures that permit cases involving the California Environmental Quality Act to obtain preferred, fast-track treatment in the courts. Although only four of the roughly 30 projects that have been eligible to utilize streamlined review have availed themselves of this privilege, the Legislature continues to approve measures expediting review under the California Environmental Quality Act as these measures serve to provide businesses and developers the appearance of legal certainty before proceeding with a project.
This noncontroversial measure would apply a 365-day expedited judicial review process for environmental leadership media campus projects, essentially film and television studio projects that meet specified environmental requirements, facing challenges under the California Environmental Quality Act. Similar to the only judicial review streamlining measure to successfully pass this Committee in the last decade, SB 44 (Allen) Chap. 633, Stats. 2021, this bill adopts a 365-day review standard and not the outdated 270-day timeline included in many early California Environmental Quality Act streamlining bills.
This measure is supported by Fox Entertainment Group who highlights the need to build state of the art film and television production facilities in California in order to keep up with the massive growth of new technologies in the entertainment industry. This bill has no opposition and was previously approved by the Committee on Natural Resources on consent.
SUMMARY: Authorizes an expedited 365-day judicial review process for litigation involving the California Environmental Quality Act and specified “environmental leadership media campus” projects. Specifically, this bill:
- Authorizes any city within Los Angeles County that serves as the lead agency approving an environmental leadership media campus project to certify the project for judicial streamlining pursuant to the California Environmental Quality Act if the following conditions are met:
- The project will result in an investment of at least one billion dollars in California upon completion;
- The project will obtain certification as LEED gold standard or better for all new construction that is eligible for LEED certification, or any new construction or major renovation of existing buildings that is not eligible for LEED certification will achieve comparable standards for energy and water efficiency;
- The project does not result in any net additional greenhouse gas emissions, including, but not limited to, from employee transportation, as specified.
- The project will generate at least 1,000 jobs during construction;
- The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, employs a skilled and trained workforce, as defined, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment. These requirements do not apply to a contractor or subcontractor performing work that is subject to a project labor agreement;
- The project applicant demonstrates compliance with specified recycling requirements;
- The project applicant agrees that all mitigation measures required pursuant to the California Environmental Quality Act and any other environmental measures required by this bill shall be conditions of approval of the project, and those conditions will be fully enforceable by the lead agency;
- The project applicant agrees to pay any additional costs incurred by the courts in hearing and deciding any case subject to this section, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council; and
- The project applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with review and consideration of the project pursuant to this division, in a form and manner specified by the lead agency for the project.
- Requires the Judicial Council to adopt a rule of court to establish procedures that require resolution, to the extent feasible, within 365 days, including any appeals, of a lawsuit challenging the certification of the environmental impact report or any project approvals for a certified environmental leadership media campus project.
- Prohibits these procedures from applying if the applicant fails to notify a lead agency prior to the release of the draft environmental impact report for public comment.
- Establishes basic minimum and other format requirements for the draft and final environmental impact report for an environmental leadership media campus project.
- Makes various findings and declarations.
EXISTING LAW:
- Establishes the California Environmental Quality Act that, generally, requires a public agency to prepare, or cause to be prepared, and to certify the completion of, an environmental impact report on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have significant effects. (Public Resources Code Section 21100 et seq.)
- Defines a “project” for the purpose of the California Environmental Quality Act as an activity that may cause either a direct physical change in the environment, or a reasonably foreseeable indirect physical change in the environment, and includes any of the following:
- An activity directly undertaken by any public agency;
- An activity undertaken by a person which is supported, in whole or in part, through contracts, grants, subsidies, loans, or other forms of assistance from one or more public agencies; or
- An activity that involves the issuance to a person of a lease, permit, license, certificate, or other entitlement for use by one or more public agencies. (Public Resources Code Section 21065.)
- Provides that an action or proceeding to attack, review, set aside, void, or annul the acts or decisions of a public agency on the grounds of noncompliance with the California Environmental Quality Act may be commenced when it is alleged that:
- A public agency is carrying out or has approved a project that may have a significant effect on the environment without having determined whether the project may have a significant effect on the environment;
- A public agency has improperly determined whether a project may have a significant effect on the environment;
- An environmental impact report prepared by, or caused to be prepared by, a public agency does not comply with the California Environmental Quality Act;
- A public agency has improperly determined that a project is not subject to the California Environmental Quality Act; or
- Any other act or omission of a public agency does not comply with the California Environmental Quality Act. (Public Resources Code Section 21167.)
- Requires the superior court and court of appeal to provide lawsuits related to the California Environmental Quality Act preference over all other civil actions therein, in the matter of setting the same for hearing or trial, and in hearing the same, to the end that the action or proceeding shall be quickly heard and determined. (Public Resources Code Section 21167.1 (a).)
- Requires counties with a population of over 200,000 to designate one or more judges to develop expertise concerning the California Environmental Quality Act and related land-use and environmental matters, and then assign such matters to that judge or those judges. (Public Resources Code Section 21167.1 (b).)
- Provides for categorical exemptions to the California Environmental Quality Act for actions that include the following:
- Ministerial projects proposed to be carried out or approved by public agencies;
- Emergency repairs to public service facilities necessary to maintain service;
- Projects undertaken, carried out, or approved by a public agency to maintain, repair, restore, demolish, or replace property or facilities damaged or destroyed as a result of a disaster in a disaster-stricken area in which a state of emergency has been proclaimed by the Governor;
- Specified actions necessary to prevent or mitigate an emergency;
- Actions undertaken by a public agency relating to any thermal power plant site or facility, as specified;
- Activities or approvals necessary to the bidding for, hosting or staging of, and funding or carrying out of, an Olympic games under the authority of the International Olympic Committee, except for the construction of facilities necessary for the Olympic games;
- The establishment, modification, structuring, restructuring, or approval of rates, tolls, fares, or other charges by public agencies, as specified;
- A project for the institution or increase of passenger or commuter services on rail or highway rights-of-way already in use, including modernization of existing stations and parking facilities;
- A project for the institution or increase of passenger or commuter service on high-occupancy vehicle lanes already in use, including the modernization of existing stations and parking facilities; and
- A project for the development of a regional transportation improvement program, the state transportation improvement program, or a congestion management program. (Public Resources Code Section 21080 (b).)
- Provides that the California Environmental Quality Act does not apply to urban infill projects, as specified. (Public Resources Code Section 15332.)
- Enables the Governor to authorize specified “energy infrastructure” projects to utilize judicial streaming of California Environmental Quality Act litigation. (Public Resources Code Section 21189.82.)
- Provides that a public entity may use, enter into, or require contractors to enter into, a project labor agreement for a construction project only if the agreement includes all of the following taxpayer protection provisions:
- The agreement prohibits discrimination based on race, national origin, religion, sex, sexual orientation, political affiliation, or membership in a labor organization in hiring and dispatching workers for the project;
- The agreement permits all qualified contractors and subcontractors to bid for and be awarded work on the project without regard to whether they are otherwise parties to collective bargaining agreements;
- The agreement contains an agreed-upon protocol concerning drug testing for workers who will be employed on the project;
- The agreement contains guarantees against work stoppages, strikes, lockouts, and similar disruptions of the project; and
- The agreement provides that disputes arising from the agreement shall be resolved by a neutral arbitrator. (Public Contract Code Section 2500.)
- Establishes the criteria for deeming a party to have a “skilled and trained workforce.” (Public Contract Code Section 2600 et seq.)
FISCAL EFFECT: As currently in print this bill is keyed fiscal.
COMMENTS: Thanks to a combination of tax incentives and other state and local programs, California-based film and television is growing at a rate not seen in years. Furthermore, the growing use of technology to enhance filmmaking necessitates the construction of new, state of the art, recording facilities. This measure recognizes that California needs additional film and recording facilities to remain competitive in attracting film and television production to California and protecting the jobs the industry generates. This bill would adopt procedures to streamline judicial review of claims brought against new film and television production infrastructure should those projects face a challenge for violating the California Environmental Quality Act (CEQA). In support of this measure, the author states:
California has a rich history as the entertainment capital of the world. However, the construction of soundstages in California have not kept pace with the recent growth in the production of film, scripted television and streaming content which forces more production outside of California.
AB 3265 would allow a streamlined review and approval process for “environmental leadership media campus projects” that will foster studio construction and renovation within Los Angeles County. These projects will generate thousands of full-time jobs during construction and thousands of additional permanent jobs once they are constructed and operating.
The CEQA process and potential court challenges. At its core, CEQA seeks to ensure that public agencies do not approve projects without considering the negative impacts a project may inflict on the environment. Although CEQA is too often, and incorrectly, viewed as a tool to skew outcomes in a manner that favors environmentalists and deters development, in reality, “CEQA operates, not by dictating proenvironmental outcomes, but rather by mandating that ‘decision makers and the public’ study the likely environmental effects of contemplated government actions and thus make fully informed decisions regarding those actions.” (Citizens Coalition Los Angeles v. City of Los Angeles (2018) 26 Cal. App. 5th 561, 577.) Thus, the primary objective of the environmental review required by CEQA is to steer agency decision makers into approving projects in a manner that utilizes feasible alternatives and mitigation measures to lessen the project’s impact on the environment. The consideration of the impacts of a project is to be analyzed in the agency’s environmental impact report. The failure to properly consider a project’s impacts is what typically results in litigation.
The process of finalizing an environmental impact report requires several steps. First, the local lead agency must determine if a project qualifies for one of the many exemptions to CEQA provided in statute and the Office of Planning and Research’s regulations, more commonly known as the CEQA Guidelines. If no exemption exists, the lead agency must then begin to initially study the project in order to determine the scope of the project and associated environmental review. At this point if the agency believes no environmental impacts exist they may opt to file a negative declaration stating as much and proceed to approve the project. Once the scope of the project and review is properly determined, the environmental review is conducted and a draft environmental impact report is submitted for public comment. A lead agency must respond to all written comments on the environmental impact report received during the public comment period, and revise the environmental impact report as necessary. The responses to comments should explain why the comments are rejected or if the comment resulted in the adoption of a mitigation measure. Once the public review is completed the agency can certify the final environmental impact report.
Once a final environmental impact report is certified, and a project is subsequently approved, any litigation over the environmental review of the project can begin. Courts require an environmental impact report to make a good faith effort at fully disclosing the impacts of the project, provide a detailed set of information about project impacts and serve as the foundation for agency review. The court must review the environmental impact report in two ways. First, a court must determine if the environmental impact report was prepared in a procedurally sufficient manner, as described above, and contains the proper content as required by law. Secondly, the court must determine the substantive aspect of its review and determine whether the conclusions and decisions made by the lead agency are based on substantial evidence in the record. (Vineyard Area Citizens v. City of Rancho Cordova (2007) 40 Cal.4th 412.)
Believing that CEQA slows development, several litigation streamlining measures have been enacted over the past decade. The Legislature’s first foray into expediting the review of CEQA cases was the passage of AB 900 (Buchanan) Chap. 354, Stats. 2011. That measure provided that “environmental leadership” projects, projects meeting specified environmental and labor requirements, would be granted immediate appellate-level review within 175 days of a case being filed. Those provisions were ultimately struck down as unconstitutional. (Planning and Conservation League v. State of California (2012) RG12626904 (Alameda Sup. Ct.).) Moving away from the strict timeline and original appellate jurisdiction provisions, the Legislature began adopting project-specific CEQA streamlining bills that adopted a 270-day hearing timeline at the superior courts if such a timeline was “feasible.” (See, e.g. SB 743 (Steinberg) Chap. 386, Stats. 2013.) In addition to the project-specific CEQA exemptions, the Legislature has repeatedly reenacted provisions of AB 900 adopting the “if feasible” 270-day timeline approach. Indeed, an extension of the AB 900 framework was just adopted with the passage of SB 7 (Atkins) Chap. 19, Stats. 2021.
When examining both “environmental leadership” bills and those for specific projects, since 2011, at least a dozen CEQA litigation streamlining bills have been adopted by the Legislature, with dozens more having been introduced for favored projects. These bills simply boost the idea that CEQA, and related litigation stifles development. However, research suggests that actual litigation is exceedingly rare. Between 2002 and 2015 no single year saw more than 250 CEQA-related cases filed statewide. (BAE Urban Economics, CEQA in the 21st Century (Aug. 2016), p. 19, available at https://rosefdn.org/wp-content/uploads/2016/08/CEQA-in-the-21st-Century.pdf.) Additionally, a 2012 study by the Attorney General’s office suggests that the actual rate of litigation over matters related to CEQA may be as low as 0.3 percent of all projects approved in California. (Office of the Attorney General, Quantifying the Rate of Litigation Under the California Environmental Quality Act: A Case Study (2012).) Given the low rate at which projects subject to CEQA are actually litigated, it appears that the real deterrence to large-scale development is California is more likely local zoning laws, land use policies, construction costs, and the general lack of open space in this state’s largest cities. Nonetheless, the Legislature continues to pass CEQA streamlining measure. Most recently, in response to a high pressure budget request from the Governor, the Legislature approved SB 149 (Caballero) Chap. 60, Stats. 2023, to authorize the Governor to approve various energy reliability and large infrastructure projects for judicial streamlining.
Despite their purported benefits, in reality expedited CEQA review procedures are rarely utilized and do not always prevent a project from being terminated. As noted above less than one percent of all projects reviewed pursuant to CEQA result in litigation. Similarly, data suggests projects that have been given CEQA-streamlining by the Legislature, much like projects overall, rarely are litigated in court. Based on data provided by the Judicial Council, of the 30 projects that have qualified for expedited CEQA review since 2011, only four projects have needed expedited legal review to defend against a lawsuit. Of those four cases, three were high-profile stadium projects that, in some cases, utilized taxpayer money to build a private facility. Notably, in addition to the relatively low-rate of litigation, of those 19 projects that qualified for expedited review another four were either terminated or withdrawn, and thus never built, due to financial or other business considerations and not environmentally-related legal exposure. (California Senate Office of Research, Review of Environmental Leadership Projects, (Apr. 2019) at p. 5.) Of these four, none were projects made eligible for expedited review by SB 149. Accordingly, despite the Legislature’s use of CEQA-streamlining, an equal number of qualified projects benefited from these laws as those that failed under the weight of their own financial difficulties.
This bill seeks to boost the development of state-of-art film and television production facilities by providing these facilities access to streamlined CEQA review should the projects be challenged. To ensure that these projects do not pose major environmental risks, the projects must be able to achieve LEED Gold certification, must not result in any new greenhouse gas emissions, and must generate at least 1,000 skilled construction jobs. The bill also requires a project applicant to bear the costs of expediting CEQA review as well as the cost of preparing the record for the court. Most notably, modeling the sole CEQA streamlining measure to pass this Committee in the last decade (SB 44 (Allen) Chap. 633, Stats. 2021), this bill utilizes a 365-day review timeline instead of the 270-day timeline many prior CEQA streamlining measures utilized.
ARGUMENTS IN SUPPORT: This measure is supported by the Fox Entertainment Group, one of the largest film and television producers in the state. In support of the bill Fox writes:
According to a recent studio production space case study, Los Angeles has the largest number of stages, square footage, and talent pool (384, 5.2M, and 198K respectively), strong tech innovation, and is therefore well suited to form production bubbles for COVID precautions. The construction of soundstages in California has not kept pace with the recent growth in the production of film, scripted television and streaming content which forces more production outside of California. The segment of entertainment production that has had the most detrimental effect on California’s infrastructure is the loss of big-budget feature films which require the use of several large sound stages building complex sets.
Adding to the need for updating the State’s film and television production facilities is the arrival of digital technology. New cinematography, sound recording and editing tools have provided sophisticated visual and audio effects for filmmakers during production and post production. While technology has revolutionized the creative brilliance of the film and television industry, its deployment requires infrastructure improvements for high-speed internet connections and cloud-based storage solutions at California’s “media production campuses.”
AB 3265 will be a catalyst for sustained job growth by streamlining the process for renovating sound stages, and updating production facilities to incorporate the latest graphics and audio technology. These investments will provide environmental benefits and keep productions in-state for decades to come. AB 3265 will meet the highest environmental standards set in prior streamlined environmental bills that have been signed into law. In addition, the bill contains language that will assure the creation of high paying jobs throughout the construction of the project through Labor Peace Agreements.
REGISTERED SUPPORT / OPPOSITION:
Support
Fox Entertainment Group, Inc.
Opposition
None on file
Analysis Prepared by: Nicholas Liedtke / JUD. / (916) 319-2334
Date of Hearing: April 15, 2024
ASSEMBLY COMMITTEE ON NATURAL RESOURCES
Isaac G. Bryan, Chair
ABPCA Bill Id:AB 3265 (
Author:Bryan) – As Amended Ver:April 9, 2024
SUBJECT: California Environmental Quality Act: environmental leadership media campus projects: judicial streamlining
SUMMARY: Establishes expedited administrative and judicial review procedures under the California Environmental Quality Act (CEQA) for “environmental leadership media campus projects” (ELMCP) in Los Angeles, requiring the courts to resolve lawsuits within 365 days, to the extent feasible.
EXISTING LAW:
- CEQA requires lead agencies with the principal responsibility for carrying out or approving a proposed project to prepare a negative declaration, mitigated negative declaration, or environmental impact report (EIR) for this action, unless the project is exempt from CEQA (CEQA includes various statutory exemptions, as well as categorical exemptions in the CEQA guidelines). (Public Resources Code (PRC) 21000 et seq.)
- Authorizes judicial review of CEQA actions taken by public agencies, following the agency's decision to carry out or approve the project. Challenges alleging improper determination that a project may have a significant effect on the environment, or alleging an EIR does not comply with CEQA, must be filed in the superior court within 30 days of filing of the notice of approval. The courts are required to give CEQA actions preference over all other civil actions. Requires the court to regulate the briefing schedule so that, to the extent feasible, hearings commence within one year of the filing of the appeal. Requires the plaintiff to request a hearing within 90 days of filing the petition. Requires the court to establish a briefing schedule and a hearing date, requires briefing to be completed within 90 days of the plaintiff’s request for hearing, and requires the hearing, to the extent feasible, to be held within 30 days thereafter. (PRC 21167 et seq.)
- Pursuant to AB 900 (Buchanan), Chapter 354, Statutes of 2011, as reenacted by SB 7 (Atkins), Chapter 19, Statutes of 2021, establishes procedures for expedited judicial review (i.e., requiring the courts to resolve lawsuits within 270 days, to the extent feasible) for “environmental leadership development projects” certified by the Governor and meeting specified conditions, including Leadership in Energy and Environmental Design (LEED) Gold-certified infill site projects achieving transportation efficiency 15% greater than comparable projects and zero net additional greenhouse gas (GHG) emissions, clean renewable energy projects, and clean energy manufacturing projects. SB 7 sunsets these provisions on January 1, 2026. (PRC 21178 et seq.)
THIS BILL:
- Requires a city within Los Angeles County, that is the lead agency for an ELMCP, to certify the project for streamlining (i.e., expedited administrative and judicial review) if the agency finds the following conditions will be met:
- The project will result in an investment of at least one billion dollars in California upon completion.
- The project will obtain certification as LEED gold standard or better for all new construction that is eligible for LEED certification. Any new construction or major renovation of existing buildings that is not eligible for LEED certification will achieve comparable standards for energy and water efficiency.
- The project does not result in any net additional GHG emissions, including, but not limited to, from employee transportation, as specified.
- The project will generate at least 1,000 jobs during construction.
- The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, employs a skilled and trained workforce, as defined, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment. These requirements do not apply to a contractor or subcontractor performing work that is subject to a project labor agreement.
- The project applicant demonstrates compliance with specified recycling requirements.
- The project applicant agrees that all mitigation measures required pursuant to CEQA and any other environmental measures required by this bill shall be conditions of approval of the project, and those conditions will be fully enforceable by the lead agency.
- The project applicant agrees to pay any additional costs incurred by the courts in hearing and deciding any case subject to this section, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council.
- The project applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with review and consideration of the project pursuant to this division, in a form and manner specified by the lead agency for the project.
- Requires the Judicial Council to adopt a rule of court to establish procedures that require resolution, to the extent feasible, within 365 days, including any appeals, of a lawsuit challenging the certification of the EIR or any project approvals for a certified ELMCP.
- Prohibits these procedures from applying if the applicant fails to notify a lead agency prior to the release of the draft EIR for public comment.
- Requires the draft and final EIR to include a specified notice in no less than 12-point type regarding the draft and final EIR being subject to ELMCP procedures.
- Makes related findings.
FISCAL EFFECT: Unknown
COMMENTS:
- Background. CEQA provides a process for evaluating the environmental effects of applicable projects undertaken or approved by public agencies. If a project is not exempt from CEQA, an initial study is prepared to determine whether the project may have a significant effect on the environment. If the initial study shows that there would not be a significant effect on the environment, the lead agency must prepare a negative declaration. If the initial study shows that the project may have a significant effect on the environment, the lead agency must prepare an EIR.
An EIR must accurately describe the proposed project, identify and analyze each significant environmental impact expected to result from the proposed project, identify mitigation measures to reduce those impacts to the extent feasible, and evaluate a range of reasonable alternatives to the proposed project. If mitigation measures are required or incorporated into a project, the agency must adopt a reporting or monitoring program to ensure compliance with those measures.
Generally, CEQA actions taken by public agencies can be challenged in superior court once the agency approves or determines to carry out the project. CEQA appeals are subject to unusually short statutes of limitations. Under current law, court challenges of CEQA decisions generally must be filed within 30-35 days, depending on the type of decision. The courts are required to give CEQA actions preference over all other civil actions. However, the schedules for briefing, hearing, and decision are less definite. The petitioner must request a hearing within 90 days of filing the petition and, generally, briefing must be completed within 90 days of the request for hearing. There is no deadline specified for the court to render a decision.
In 2011, AB 900 and SB 292 (Padilla), Chapter 353, Statutes of 2011, established expedited CEQA judicial review procedures for a limited number of projects. For AB 900, it was large-scale projects meeting extraordinary environmental standards and providing significant jobs and investment. For SB 292, it was a proposed downtown Los Angeles football stadium and convention center project achieving specified traffic and air quality mitigations. For these eligible projects, the bills provided for original jurisdiction by the Court of Appeal and a compressed schedule requiring the court to render a decision on any lawsuit within 175 days. This promised to reduce the existing judicial review timeline by 100 days or more, while creating new burdens for the courts and litigants to meet the compressed schedule. AB 900’s provision granting original jurisdiction to the Court of Appeal was invalidated in 2013 by a decision in Alameda Superior Court in Planning and Conservation League v. State of California. AB 900 was subsequently revised to restore jurisdiction to superior courts and require resolution of lawsuits within 270 days, to the extent feasible.
As part of their expedited judicial review procedures, these bills required the lead agency to prepare and certify the record of proceedings concurrently with the administrative process and required the applicant to pay for it. It was commonly agreed that this would expedite preparation of the record for trial. Since 2011, several additional bills have provided similar project-specific concurrent preparation procedures. In addition, SB 122 (Jackson), Chapter 476, Statutes of 2016, established an optional concurrent preparation procedure for any CEQA project, subject to the lead agency agreeing, and the applicant paying the agency’s costs.
To date, approximately 30 projects have been eligible for expedited review under AB 900 and the several project-specific bills enacted since 2011. Many of these projects have not proceeded to final approval and construction, and only four projects have been challenged in court. Of those four cases, two were high-profile arena projects, one was a luxury condominium tower, and one is the reconstruction of the Capitol Annex. A review by the Senate Office of Research indicates the following timelines for final resolution of three of the cases:
- Golden1 Center (Sacramento Kings arena): 243 business days/352 calendar days.
- Chase Center (Golden State Warriors arena): 257 business days/376 calendar days.
- 8150 Sunset Boulevard (Hollywood condo tower): 395 business days/578 calendar days.
Whether calendar days or business days, “to the extent feasible,” as well as the inherent authority of the independent judicial branch, provides a court discretion, and no direct consequence, if it is unable to meet the 365-day deadline
- According to the author:
The construction of soundstages in California has not kept pace with the recent growth in the production of film, scripted television and streaming content which forces more production outside of California. The segment of entertainment production that has had the most detrimental effect on California’s infrastructure is the loss of big-budget feature films which require the use of many large sound stages building complex sets.
Adding to the need for updating the state’s film and television production facilities is the arrival of digital technology. New cinematography, sound recording and editing tools have provided sophisticated visual and audio effects for filmmakers during production and post production. While technology has revolutionized the creative brilliance of the film and television industry, its deployment requires infrastructure improvements for high-speed internet connections and cloud-based storage solutions at California’s media production campuses.
These projects will generate thousands of full-time jobs during construction and thousands of additional permanent jobs once they are constructed and operating. AB 3265 will meet the highest environmental standards set in prior streamlined environmental bills that have been signed into law. In addition, the bill contains language that will assure the creation of high paying jobs throughout the construction of the project.
- Double referral. This bill has been double-referred to the Judiciary Committee.
REGISTERED SUPPORT / OPPOSITION:
Support
Fox Corporation
Opposition
None on file
Analysis Prepared by: Lawrence Lingbloom / NAT. RES. /