AB 2493: Electrical corporations: interconnection: transmission: permitting: auditor.
- Session Year: 2025-2026
- House: Assembly
- Latest Version Date: 2026-04-13
Current Status:
In Progress
(2026-04-13: Read second time and amended.)
Introduced
In Committee
First Chamber
In Committee
Second Chamber
Enacted
Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations. Existing law requires the commission, if it determines that the rules, practices, equipment, appliances, facilities, or service of a public utility, or the methods of manufacture, distribution, transmission, storage, or supply used by the public utility, are unjust, unreasonable, unsafe, improper, inadequate, or insufficient, to determine and fix the rules, practices, equipment, appliances, facilities, service, or methods to be observed, furnished, constructed, enforced, or employed.
This bill would, within one year following the adoption of each transmission plan produced by the Independent System Operator through the transmission planning process, or a successor process, and within one year following the execution of a generator interconnection agreement, require each large electrical corporation that is assigned or obligated to construct a project that requires approval by the commission to initiate permitting for the project by filing an application or other notice, as applicable, pursuant to a specific general order. The bill would authorize a large electrical corporation to request an extension of the filing deadline by demonstrating good cause in a written notice to the commission, as provided. If a large electrical corporation fails to adhere to these timelines, or to make a timely extension request, the bill would require the commission to take appropriate enforcement action, as specified.
This bill would require, beginning January 1, 2027, the commission to require each large electrical corporation, as defined, to retain an independent third-party auditor to review certain transmission- and interconnection-related submissions made by the large electrical corporation, the large electrical corporations progress on completing network upgrades following approval in a generator interconnection agreement or transmission plan approved by the Independent System Operator, the large electrical corporations compliance with the above-described permitting deadlines, and the large electrical corporations compliance with any remedial actions ordered by the commission, as specified. The bill would require the third-party auditor to report to the commission on an annual basis, as provided. Within 90 days of receiving the auditors report, the bill would require the commission to issue a resolution directing a large electrical corporation to take remedial actions to address any and all deficiencies identified by the auditor, as specified.
Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.
Because the above-described provisions would be part of the act and a violation of a commission action implementing the above-described provisions would be a crime, this bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Discussed in Hearing