AB 1026: Electricity: interconnection rules.
- Session Year: 2019-2020
- House: Assembly
- Latest Version Date: 2019-10-02
|
Date
|
Status
|
|---|---|
| Oct 2, 2019 | Chaptered by Secretary of State - Chapter 446, Statutes of 2019. |
| Oct 2, 2019 | Approved by the Governor. |
| Sep 13, 2019 | Enrolled and presented to the Governor at 3:30 p.m. |
| Sep 9, 2019 | Senate amendments concurred in. To Engrossing and Enrolling. (Ayes 78. Noes 0.). |
| Sep 5, 2019 | In Assembly. Concurrence in Senate amendments pending. May be considered on or after September 7 pursuant to Assembly Rule 77. |
| Sep 4, 2019 | Read third time. Passed. Ordered to the Assembly. |
| Aug 27, 2019 | Read second time. Ordered to third reading. |
| Aug 26, 2019 | From committee: Be ordered to second reading pursuant to Senate Rule 28.8. |
| Aug 20, 2019 | From committee chair, with author's amendments: Amend, and re-refer to committee. Read second time, amended, and re-referred to Com. on APPR. |
| Aug 15, 2019 | In committee: Hearing postponed by committee. |
| Aug 13, 2019 | Read second time and amended. Re-referred to Com. on APPR. |
| Aug 12, 2019 | From committee: Amend, and do pass as amended and re-refer to Com. on APPR. (Ayes 12. Noes 0.) (July 10). |
| Jun 27, 2019 | In committee: Set, second hearing. Hearing canceled at the request of author. |
| Jun 24, 2019 | From committee chair, with author's amendments: Amend, and re-refer to committee. Read second time, amended, and re-referred to Com. on E., U. & C. |
| Jun 11, 2019 | In committee: Set, first hearing. Hearing canceled at the request of author. |
| May 29, 2019 | Referred to Com. on E., U. & C. |
| May 16, 2019 | In Senate. Read first time. To Com. on RLS. for assignment. |
| May 16, 2019 | Read third time. Passed. Ordered to the Senate. |
| May 9, 2019 | Read second time. Ordered to Consent Calendar. |
| May 8, 2019 | From committee: Do pass. To Consent Calendar. (Ayes 18. Noes 0.) (May 8). |
| May 1, 2019 | Re-referred to Com. on APPR. |
| Apr 30, 2019 | Read second time and amended. |
| Apr 29, 2019 | From committee: Amend, and do pass as amended and re-refer to Com. on APPR. (Ayes 15. Noes 0.) (April 24). |
| Mar 21, 2019 | Re-referred to Com. on U. & E. |
| Mar 20, 2019 | From committee chair, with author's amendments: Amend, and re-refer to Com. on U. & E. Read second time and amended. |
| Mar 18, 2019 | Referred to Com. on U. & E. |
| Feb 22, 2019 | From printer. May be heard in committee March 24. |
| Feb 21, 2019 | Read first time. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Sep 9, 2019 | AB 1026 Wood Concurrence in Senate Amendments | Assembly Floor |
Passed |
|
| Sep 4, 2019 | Assembly 3rd Reading AB1026 Wood By Wiener | Senate Floor |
Passed |
|
| Jul 10, 2019 | Do pass as amended, but first amend, and re-refer to the Committee on [Appropriations] | Senate Standing Committee on Energy, Utilities and Communications |
Passed |
|
| May 16, 2019 | AB 1026 Wood Consent Calendar Second Day Regular Session | Assembly Floor |
Passed |
|
| May 8, 2019 | Do pass. To Consent Calendar. | Assembly Standing Committee on Appropriations |
Passed |
|
| Apr 24, 2019 | Do pass as amended and be re-referred to the Committee on [Appropriations] | Assembly Standing Committee on Utilities and Energy |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
CONCURRENCE IN SENATE AMENDMENTS
CSA1 Bill Id:AB 1026
Author:(Wood)
As Amended Ver:August 20, 2019
Majority vote
SUMMARY:
This bill requires an electrical or gas corporation (IOU) to apply only those construction and design specifications, standards, terms, and conditions that are applicable to a new extension of service project for the 18 months following the date the application for a new extension of service project is approved. It also authorizes an IOU to adopt modifications, as specified, of the construction and design specifications, standards, terms, and conditions of a new extension of service project.
The Senate Amendments:
- Specify three circumstances or actions in which an IOU can adopt modifications to an extension of service project after it has been approved and defines terms. The conditions which can trigger a project modification are:
- An order or decision of the California Public Utilities Commission or any other state or federal agency;
- A change in the scope of work by the customer; and
- A change needed by the IOU to remedy a construction-related defect that could pose a safety-risk.
COMMENTS:
This bill seeks to extend the policy of local building permits – that the building standards in place on the date a permit application is submitted, remain the standards to which the project must comply even if there are changes in those standards – to IOU service connection applications. This bill requires that the interconnection rules in place on the date the project is approved by the IOU, remain for 18 months.
There have long been reports of frustration with the IOUs for interconnection of many different types of electric service. Frequently grumpy project applicants include wholesale generators, customers with rooftop solar, and, in this case, builders of housing developments. Service interconnection rule interpretations can vary between utilities and even among the staff of the same utility. As a consequence builders report that the "rules of the game" can change well after construction has already started and in extreme cases when construction is nearing completion. This can result in extremely costly changes during the construction process which in turns results in serious project delays."
According to the Author:
For over thirty years, state law has required builders to comply with the fire and life-safety building standards that are in effect on the date the application for a building permit is submitted to the local building department. With regards to building standards, this statute has provided much-needed clarity for designers, builders, and local enforcement officials.
Unfortunately, the same level of clarity does not exist for utility line extensions which provide service from an electrical or gas corporation. This means that the "rules of the game" can change well after construction has already started and in extreme cases when construction is nearing completion. This can result in extremely costly changes during the construction process which in turn results in serious project delays. At a time when California is experiencing a serious housing crisis, this is simply unacceptable.
Arguments in Support:
The California Building Industry Association writes in support of the bill that it will "establish the same level of clarity in the design and construction of utility line extensions as currently exists for the fire and life-safety building standards that apply to our homes and buildings. The language as proposed makes it clear that once an electrical or gas corporation approves the construction design and specifications for a specific utility line extension, they have officially determined the rules to which that construction must comply."
Arguments in Opposition:
There is no registered opposition to this bill.
FISCAL COMMENTS:
According to the Assembly Appropriations Committee, there are no state costs associated with this bill.
VOTES:
ASM UTILITIES AND ENERGY: 15-0-0
YES: Holden, Patterson, Burke, Carrillo, Chen, Cunningham, Eggman, Cristina Garcia, Rodriguez, Mayes, Muratsuchi, Quirk, Reyes, Santiago, Ting
ASM APPROPRIATIONS: 18-0-0
YES: Gonzalez, Bigelow, Bloom, Bonta, Brough, Calderon, Carrillo, Chau, Diep, Eggman, Fong, Gabriel, Eduardo Garcia, Maienschein, Obernolte, Petrie-Norris, Quirk, Robert Rivas
ASSEMBLY FLOOR: 74-0-6
YES: Aguiar-Curry, Bauer-Kahan, Berman, Bigelow, Bloom, Boerner Horvath, Bonta, Brough, Calderon, Carrillo, Cervantes, Chau, Chen, Chiu, Choi, Chu, Cooper, Cunningham, Dahle, Daly, Diep, Eggman, Flora, Fong, Frazier, Gabriel, Gallagher, Eduardo Garcia, Gipson, Gloria, Gonzalez, Gray, Grayson, Holden, Irwin, Jones-Sawyer, Kalra, Kamlager-Dove, Kiley, Lackey, Levine, Limón, Low, Maienschein, Mathis, Mayes, McCarty, Medina, Melendez, Mullin, Muratsuchi, Nazarian, O'Donnell, Obernolte, Patterson, Petrie-Norris, Quirk, Quirk-Silva, Ramos, Reyes, Luz Rivas, Robert Rivas, Rodriguez, Blanca Rubio, Salas, Santiago, Smith, Mark Stone, Voepel, Waldron, Weber, Wicks, Wood, Rendon
ABS, ABST OR NV: Arambula, Burke, Cooley, Friedman, Cristina Garcia, Ting
SENATE FLOOR: 40-0-0
YES: Allen, Archuleta, Atkins, Bates, Beall, Borgeas, Bradford, Caballero, Chang, Dahle, Dodd, Durazo, Galgiani, Glazer, Lena Gonzalez, Grove, Hertzberg, Hill, Hueso, Hurtado, Jackson, Jones, Leyva, McGuire, Mitchell, Monning, Moorlach, Morrell, Nielsen, Pan, Portantino, Roth, Rubio, Skinner, Stern, Stone, Umberg, Wieckowski, Wiener, Wilk
UPDATED:
VERSION: August 20, 2019
CONSULTANT: Kellie Smith / U. & E. / (916) 319-2083 FN: 0001985
Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | AB 1026 |
THIRD READING
Bill No: AB 1026
Amended: 8/20/19 in Senate
SENATE ENERGY, U. & C. COMMITTEE: 12-0, 7/10/19
AYES: Hueso, Moorlach, Bradford, Chang, Dodd, Hertzberg, Hill, McGuire, Rubio, Stern, Stone, Wiener
NO VOTE RECORDED: Skinner
SENATE APPROPRIATIONS COMMITTEE: Senate Rule 28.8
ASSEMBLY FLOOR: 74-0, 5/16/19 (Consent) - See last page for vote
SUBJECT: Electricity: interconnection rules
SOURCE: California Building Industry Association
DIGEST:
This bill requires an electrical or gas corporation to apply only those construction and design specifications, standards, terms, and conditions that are applicable to a new extension of service project for the 18 months following the date the application for a new extension of service project is approved. Authorizes an electrical or gas corporation to adopt modifications, as specified, of the construction and design specifications, standards, terms, and conditions of a new extension of service project.
Existing law:
- Requires the California Public Utilities Commission (CPUC) to enforce the rules governing the extension of service by a gas or electrical corporation to new residential, commercial, agricultural, and industrial customers. Requires an electrical or gas corporation to permit a new or existing customer who applies for an extension of service from that corporation to install the extension in accordance with the regulations of the CPUC and any applicable specification of the corporation. (Public Utilities Code §783)
- Authorizes the CPUC to establish an expedited distribution grid interconnection dispute resolution process with the goal of resolving disputes over interconnection applications that are within the jurisdiction of the CPUC in no more than 60 days from the time the dispute is formally brought to the CPUC. If the CPUC establishes an expedited distribution grid interconnection dispute resolution process, the CPUC may provide exceptions to the 60-day time period when more than 60 days are needed, to fairly and safely address a dispute. (Public Utilities Code §769.5)
- Limits the application of state and local building standards to those in effect on the date an application for a building permit is submitted to a local building department. (Health & Safety Code §18938.5)
- Requires that a local building permit remain valid for 12 months after it is issued, if the work on the site is commenced within 12 months; and allows a permittee to apply for extensions. (Health & Safety Code §18938.6)
This bill:
- Provides that only those construction and design specifications, terms, and conditions that are applicable to a new extension of service project by an electrical or gas corporation on the date the application is approved for the extension of service apply for to the new project for the 18 months following the approval date of the application.
- Authorizes an electrical or gas corporation to adopt modifications to those construction and design specifications, standards, terms, and conditions applicable to a new extension-of-service project in accordance with any of the following:
- An emergency order or decision of the CPUC or any other state or federal agency with jurisdiction.
- A work order issued by the electrical or gas corporation to implement construction or design changes necessitated by a customer-driven scope of work modification.
- A material-related design change identified by the electrical or gas corporation to remedy a construction material defect that could pose a risk to public safety.
- Defines the following terms:
- “The date of application is approved” to mean the earlier of either the effective date of the contract for the extension of gas or electric service or the date when the utility first invoices the customer for the extension of gas or electric service.
- “Customer-driven scope of work modification” to mean those modifications required to accommodate the construction and design needs of a new extension-of-service project for a specific customer.
- “Invoice” to mean when an electrical or gas corporation presents an offer to the customer for the extension of service in response to an application for an extension of service submitted pursuant to the regulations of the CPUC and applicable specifications of the given electrical or gas corporation.
Background
Interconnection to the electrical and gas system. Rules governing the ability of entities to connect to the electrical or gas system are generally determined by statute, CPUC rules, and tariffs for each of the gas and electrical corporations. Electric Rules 15 and 16 establish the guidelines for design, cost allocation, and responsibilities of a project applicant and a utility for electric distribution line extensions. Gas Rules 15 and 16 provide similar rules for extensions of gas service. Each electrical and gas corporation establishes its own process and procedures to address requests for extensions of service projects, however, all in accordance with CPUC rules. The ability of a project, such as a new housing development, to interconnect to the larger electrical or gas distribution system can take months (if not, years, in some cases) as the process can entail the need for designs, assessments on costs allocations associated with improvements on the system to allow for the interconnection, and other issues. In the case of new building developments, particularly housing developments, the need for gas or electric service extensions may be needed in phases over months, or years, depending on the size of the development. A building developer may have been approved for particular requirements during the initial application for an extension of service project but have later found they need to make changes in the midst of a project development due to new specifications, terms, or standards.
Model approach. For over 30 years, the Health & Safety Code §18938.5 has required builders to comply with the state and local fire, and life-safety building standards that are in effect on the date the application for a building permit is submitted to the local building department. With regards to building standards, the sponsors of this bill state that this statute has provided much-needed clarity for designers, builders, and local enforcement officials. They state that, unfortunately, the same level of clarity does not exist for utility line extensions which provide service from an electrical or gas corporation. This means that the terms, standards, specifications, can change well after construction for a project has already started and in extreme cases when construction is nearing completion. These changes can result in extremely costly changes during the construction process which in turns results in project delays.
Comments
Need for certainty. This bill seeks to apply the policy of local building permits – that the building standards in place on the date a permit application is submitted, remain the standards to which the project must comply even if there are changes in those standards – to investor-owned utility gas and electric service connection applications. This bill requires that the interconnection standards, terms, specifications, and rules in place on the date the application for an extension of service project is approved, remain for the 18 months following the date of the approval. Such an approach provides applicants for extension of service projects, including the building industry, greater certainty in the process to better manage costs and avoid unnecessary delays in constructing their projects.
Defining “application is approved.” As currently drafted, this bill attempts to account for the varied approaches each of the electrical and gas corporations use to process requests for extension of service projects. As noted above, the CPUC provides some rules, but largely defers to each utility in how those rules are to be implemented as parted of the noted tariffs. As such, not all electrical or gas corporations issue contracts or invoices for each request for extension of service project. In general, gas or electrical corporations issue either a contract or invoice with specified terms, including payment deadlines by which an applicant must pay for the project. If the applicant does not pay as specified on the invoice or contract, then the gas or electrical corporation may deem the contract to be no longer valid. This bill preserves the ability of each gas or electrical corporation to establish these terms within the contract or invoice provided. As an example, if a customer does not pay for the project within the specified time included in the invoice or contract – generally 90 days – the offer may no longer be valid, even if the 18 month clock pursuant to this bill began. Additionally, the term “invoice” as used in this bill may be more commonly understood as a price quote, but issued by the utilities in an invoice-like document with the specified terms and conditions of the requested extension of service project.
Ratepayers protected with flexibility afforded to utilities. While providing added certainty for applicants who request extension of service projects, the language of this bill appropriately provides that the utility may adopt modifications to construction and design specifications, terms, conditions, in accordance with a myriad of conditions. These conditions include: an emergency order or decision of the CPUC, or any other state or federal agency; changes necessitated by a customer-driven scope of work modification; and efforts to address material defects that could pose safety risks. As such, this bill seems to provide a reasonable level of flexibility to account for changes that may be needed for safety and other concerns which may also better protect utility ratepayers from absorbing the added costs associated with modifications that are necessary to implement the extension of service project.
Related/Prior Legislation
SB 48 (Vuich, Chapter 1229, Statutes of 1983) established rules governing the extension of service by gas and electrical corporations to new residential, commercial, agricultural, and industrial customers.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
California Building Industry Association (source)
Pacific Gas and Electric Company
OPPOSITION: (Verified 8/26/19)
None received
ARGUMENTS IN SUPPORT: According to the author:
For over thirty years, state law (Health & Safety Code 18938.5) has required builders to comply with the fire and life-safety building standards that are in effect on the date the application for a building permit is submitted to the local building department. … Unfortunately, the same level of clarity does not exist for utility line extensions which provide service from an electrical or gas corporation. This means that the “rules of the game” can change well after construction has already started and in extreme cases when construction is nearing completion. …AB 1026 seeks to establish the same level of clarity in the design and construction of utility line extensions as currently exists for the fire and life-safety building standards that apply to our homes and buildings. The language of the bill makes it clear that once an electrical or gas corporation approves the construction design and specifications for a specific utility line extension, they have officially determined the rules to which that construction must comply for 18 months following the date of application approval.
ASSEMBLY FLOOR: 74-0, 5/16/19
AYES: Aguiar-Curry, Bauer-Kahan, Berman, Bigelow, Bloom, Boerner Horvath, Bonta, Brough, Calderon, Carrillo, Cervantes, Chau, Chen, Chiu, Choi, Chu, Cooper, Cunningham, Dahle, Daly, Diep, Eggman, Flora, Fong, Frazier, Gabriel, Gallagher, Eduardo Garcia, Gipson, Gloria, Gonzalez, Gray, Grayson, Holden, Irwin, Jones-Sawyer, Kalra, Kamlager-Dove, Kiley, Lackey, Levine, Limón, Low, Maienschein, Mathis, Mayes, McCarty, Medina, Melendez, Mullin, Muratsuchi, Nazarian, Obernolte, O'Donnell, Patterson, Petrie-Norris, Quirk, Quirk-Silva, Ramos, Reyes, Luz Rivas, Robert Rivas, Rodriguez, Blanca Rubio, Salas, Santiago, Smith, Mark Stone, Voepel, Waldron, Weber, Wicks, Wood, Rendon
NO VOTE RECORDED: Arambula, Burke, Cooley, Friedman, Cristina Garcia, Ting
Prepared by: Nidia Bautista / E., U., & C. / (916) 651-4107
8/29/19 11:26:57
**** END ****
SENATE COMMITTEE ON ENERGY, UTILITIES AND COMMUNICATIONS
Senator Ben Hueso, Chair
2019 - 2020 Regular
Bill No: AB 1026 Hearing Date: 7/10/2019
Author: | Wood | ||
Version: | 6/24/2019 As Amended | ||
Urgency: | No | Fiscal: | Yes |
Consultant: | Nidia Bautista | ||
SUBJECT: Electricity: interconnection rules
DIGEST: This bill prohibits a gas or electric corporation from applying new standards to, or changing the standards for, the design and construction of a project requiring gas or electric service or distribution line extensions during the 18 months following the date the customer signs the service extension agreement.
ANALYSIS:
Existing law:
- Requires the California Public Utilities Commission (CPUC) to enforce the rules governing the extension of service by a gas or electrical corporation to new residential, commercial, agricultural, and industrial customers. Requires an electrical or gas corporation to permit a new or existing customer who applies for an extension of service from that corporation to install the extension in accordance with the regulations of the CPUC and any applicable specification of the corporation. (Public Utilities Code §783)
- Authorizes the CPUC to establish an expedited distribution grid interconnection dispute resolution process with the goal of resolving disputes over interconnection applications that are within the jurisdiction of the CPUC in no more than 60 days from the time the dispute is formally brought to the CPUC. If the CPUC establishes an expedited distribution grid interconnection dispute resolution process, the CPUC may provide exceptions to the 60-day time period when more than 60 days are needed, to fairly and safely address a dispute. (Public Utilities Code §769.5)
- Limits the application of state and local building standards to those in effect on the date an application for a building permit is submitted to a local building department. (Health & Safety Code §18938.5)
- Requires that a local building permit remain valid for 12 months after it is issued, if the work on the site is commenced within 12 months; allows a permittee to apply for extensions. (Health & Safety Code §18938.6)
This bill:
- Requires an electrical or gas corporation to provide written notice of the date that it approves an application for an extension of service to the customer.
- Provides that only those construction and design specifications, terms, and conditions that are applicable to a new extension of service project by an electrical or gas corporation at the time the customer signs an agreement for the extension of service apply to the new project for the 18 months following the date the agreement is signed.
- Authorizes an electrical or gas corporation to adopt modifications to those construction and design specifications, terms, and conditions in accordance with an emergency order or decision of the CPUC or any other state or federal agency with jurisdiction.
Background
Interconnection to the electrical and gas system. Rules governing the ability of entities to connect to the electrical or gas system are generally determined by statute, CPUC rules, and tariffs for each of the gas and electrical corporations. Electric Rule 15 and 16 establish the guidelines for design, cost allocation, and responsibilities of a project applicant and a utility for electric distribution line extensions. Gas Rules 15 and 16 provide similar rules for extensions of gas service. The ability to interconnect to the larger system can take months (if not, years, in some cases) as the process can entail the need for designs, assessments on costs allocations associated with improvements on the system to allow for the interconnection, and other issues. In the case of new building developments, particularly housing developments, depending on the size of the development, the need for gas or electric service extensions may be needed in phases over months, or years. The building developers may have been approved for particular requirements during the initial application but have later found they need to make changes as they are in the midst of a project development.
Model approach. For over thirty years, the Health & Safety Code §18938.5 has required builders to comply with the state and local fire, and life-safety building standards that are in effect on the date the application for a building permit is submitted to the local building department. With regards to building standards, the sponsors of this bill state that this statute has provided much-needed clarity for designers, builders, and local enforcement officials. Unfortunately, the same level of clarity does not exist for utility line extensions which provide service from an electrical or gas corporation. This means that the “rules of the game” can change well after construction has already started and in extreme cases when construction is nearing completion. This can result in extremely costly changes during the construction process which in turns results in project delays.
Comments
Need for certainty. This bill seeks to extend the policy of local building permits – that the building standards in place on the date a permit application is submitted, remain the standards to which the project must comply even if there are changes in those standards – to investor-owned utility gas and electric service connection applications. This bill would require that the interconnection rules in place on the date the project is approved, remain for the 18 months following the date the agreement is signed between the utility and the applicant requesting the extension of service. The building industry seeks certainty in the process to better manage costs and avoid unnecessary delays in constructing their projects.
Flexibility provided. The language of this proposed bill provides that the utility may adopt modifications to construction and design specifications, terms, conditions, in accordance with an emergency order or decision of the CPUC, or any other state or federal agency. As such, this bill seems to provide a reasonable level of flexibility to account for changes that may be needed for safety and other concerns.
Need for amendments. Based on conversations with gas and electric utilities, it seems each utility has a different process to address applications for service extensions. Specifically, some of the utilities do not process the application based on a signature as currently used in this bill. The author and committee may wish to amend this bill to incorporate an appropriate trigger for the 18-month clock to begin that accounts for the varied approaches of each of the gas and electric utilities.
Prior/Related Legislation
SB 48 (Vuich, Chapter 1229, Statutes of 1983) established rules governing the extension of service by gas and electrical corporations to new residential, commercial, agricultural, and industrial customers.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
SUPPORT:
California Building Industry Association (Sponsor)
OPPOSITION:
None received
ARGUMENTS IN SUPPORT: According to the author:
For over thirty years, state law (Health & Safety Code 18938.5) has required builders to comply with the fire and life-safety building standards that are in effect on the date the application for a building permit is submitted to the local building department. … Unfortunately, the same level of clarity does not exist for utility line extensions which provide service from an electrical or gas corporation. This means that the “rules of the game” can change well after construction has already started and in extreme cases when construction is nearing completion. …AB 1026 seeks to establish the same level of clarity in the design and construction of utility line extensions as currently exists for the fire and life-safety building standards that apply to our homes and buildings. The language of the bill makes it clear that once an electrical or gas corporation approves the construction design and specifications for a specific utility line extension, they have officially determined the rules to which that construction must comply for 18 months following the date of application approval.
-- END --
Date of Hearing: May 8, 2019
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Lorena Gonzalez, Chair
ABPCA Bill Id:AB 1026
Author:(Wood) – As Amended Ver:April 30, 2019
Policy Committee: | Utilities and Energy | Vote: | 15 - 0 |
|
| ||
|
|
Urgency: No State Mandated Local Program: Yes Reimbursable: No
SUMMARY:
This bill requires an electrical or gas corporation to provide an applicant for extension of service to provide the customer, at the time of approval, written notice of the date of the approval. In addition, the bill states that only those construction and design laws, specifications, terms and conditions that are in effect at the time an extension of service application is approved shall apply to the new project for 18 months following the date of approval.
FISCAL EFFECT:
No state costs.
COMMENTS:
The CPUC establishes the rules governing requests to electrical or gas corporations for an extension of service. The author notes that many developers of housing, for example, complain the “rules of the game” for utility services extension change during a project’s development, adding cost and delay and creating frustration. The author compares this situation to state law regarding building safety code standards, asserting such law makes the standards in effect on the date an application for a building permit is submitted to the local building department remain in effect for the life of the project. This bill makes a similar, though more limited requirement of the applicability of the rules regarding extensions of electric and gas service.
Analysis Prepared by: Jay Dickenson / APPR. / (916) 319-2081
Date of Hearing: April 24, 2019
ASSEMBLY COMMITTEE ON UTILITIES AND ENERGY
Chris Holden, Chair
ABPCA Bill Id:AB 1026 (
Author:Wood) – As Amended Ver:March 20, 2019
SUBJECT: Electricity: interconnection rules
SUMMARY: Prohibits a gas or electric corporation (IOU) from applying new standards to, or changing the standards for, the design and construction of a project requiring gas or electric service or distribution line extensions after the project is approved by the utility.
EXISTING LAW:
- Requires an IOU to permit any new or existing customer who applies for an extension of service from that IOU to install a gas or electric extension in accordance with the regulations of the commission and any applicable specifications of that electrical or gas corporation. (Public Utilities Code § 783)
- Limits the application of state and local building standards to those in effect on the date an application for a building permit is submitted to a local building department. (Health & Safety Code § 18938.5)
- Requires that a local building permit remain valid for 12 months after it is issued, if the work on the site is commenced within 12 months; allows a permittee to apply for extensions. (Health & Safety Code § 18938.6)
- Establishes guidelines for the design, cost allocation, and responsibilities of a project applicant and a utility for electric distribution line extensions necessary to furnish permanent electric service. (Electric Rule 15)
- Establishes guidelines for the design, cost allocation, and responsibilities of a project applicant and a utility for the extension of electric service from an IOU distribution line. (Electric Rule 16)
FISCAL EFFECT: This bill is keyed fiscal and will be referred to the Appropriations Committee for its review of the fiscal effect of this bill.
COMMENTS:
- Author’s Statement. According to the author, for over thirty years, state law (Health & Safety Code 18938.5) has required builders to comply with the fire and life-safety building standards that are in effect on the date the application for a building permit is submitted to the local building department. With regards to building standards, this statute has provided much-needed clarity for designers, builders, and local enforcement officials.
Unfortunately, the same level of clarity does not exist for utility line extensions which provide service from an electrical or gas corporation. This means that the “rules of the game” can change well after construction has already started and in extreme cases when construction is nearing completion. This can result in extremely costly changes during the construction process which in turn results in serious project delays. At a time when California is experiencing a serious housing crisis, this is simply unacceptable.
AB 1026 seeks to establish the same level of clarity in the design and construction of utility line extensions as currently exists for the fire and life-safety building standards that apply to our homes and buildings. The language of the bill makes it clear that once an electrical or gas corporation approves the construction design and specifications for a specific utility line extension, they have officially determined the rules to which that construction must comply.
- Moving Target? There have long been reports of frustration with the IOUs for interconnection of many different types of electric service. Frequently grumpy project applicants include wholesale generators, customers with rooftop solar, and, in this case, builders of housing projects. Service interconnection rule interpretations can vary between utilities and even among the staff of the same utility. As a consequence builders report that the “rules of the game” can change well after construction has already started and in extreme cases when construction is nearing completion. This can result in extremely costly changes during the construction process which in turns results in serious project delays.”
- Certainty. This bill seeks to extend the policy of local building permits – that the building standards in place on the date a permit application is submitted, remain the standards to which the project must comply even if there are changes in those standards – to IOU service connection applications.
This bill would require that the interconnection rules in place on the date the project is approved, remain through project completion. This provision goes a bit further than the building permit policy. Local building permits do expire in 12 months if the project has not commenced construction; the permit holder can however apply for extensions.
Many applications for extensions of distribution lines or service connections concern subdivisions with phases of development and hundreds of houses. Construction could continue for a number of years and in the meantime, safety standards could change as well as costs. The recession saw developers shelve approved projects for years. A more typical experience is a builder which has an application accepted for 500 houses. It takes four years to reach build-out. Under this bill the utility could not require the builder to address changes in safety standards at any time during those four years.
To balance the need for builder certainty while ensuring that projects stay reasonably current with new safety standards, the Committee may wish to consider amending the bill to require that project terms and standards will remain in effect for 18 months and that the IOU provide the project applicant written and dated notice when the project is been approved.