AB 1981: Los Angeles Unified School District: best value procurement.
- Session Year: 2019-2020
- House: Assembly
- Latest Version Date: 2020-09-09
|
Date
|
Status
|
|---|---|
| Sep 9, 2020 | Chaptered by Secretary of State - Chapter 46, Statutes of 2020. |
| Sep 9, 2020 | Approved by the Governor. |
| Aug 27, 2020 | Enrolled and presented to the Governor at 3:30 p.m. |
| Aug 24, 2020 | In Assembly. Ordered to Engrossing and Enrolling. |
| Aug 24, 2020 | Read third time. Passed. Ordered to the Assembly. (Ayes 31. Noes 5. Page 4288.). |
| Jul 30, 2020 | Read second time. Ordered to third reading. |
| Jul 29, 2020 | From committee: Do pass. (Ayes 7. Noes 0.) (July 29). |
| Jul 1, 2020 | Referred to Com. on ED. |
| Jun 11, 2020 | In Senate. Read first time. To Com. on RLS. for assignment. |
| Jun 10, 2020 | Read third time. Passed. Ordered to the Senate. (Ayes 66. Noes 4. Page 4749.) |
| May 12, 2020 | Read second time. Ordered to third reading. |
| May 11, 2020 | Read second time and amended. Ordered returned to second reading. |
| May 7, 2020 | From committee: Amend, and do pass as amended. (Ayes 5. Noes 0.) (May 6). |
| Mar 16, 2020 | In committee: Hearing postponed by committee. |
| Feb 25, 2020 | Re-referred to Com. on ED. |
| Feb 24, 2020 | From committee chair, with author's amendments: Amend, and re-refer to Com. on ED. Read second time and amended. |
| Feb 6, 2020 | Referred to Com. on ED. |
| Jan 24, 2020 | From printer. May be heard in committee February 23. |
| Jan 23, 2020 | Read first time. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Aug 24, 2020 | Assembly 3rd Reading AB1981 Nazarian By Leyva | Senate Floor |
Passed |
|
| Jul 29, 2020 | Do pass | Senate Standing Committee on Education |
Passed |
|
| Jun 10, 2020 | AB 1981 Nazarian Assembly Third Reading | Assembly Floor |
Passed |
|
| May 6, 2020 | Do pass as amended. | Assembly Standing Committee on Education |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | AB 1981 |
THIRD READING
Bill No: AB 1981
Author: Nazarian (D)
Amended: 5/11/20 in Assembly
Vote: 21
SENATE EDUCATION COMMITTEE: 7-0, 7/29/20
AYES: Leyva, Wilk, Chang, Durazo, Glazer, McGuire, Pan
ASSEMBLY FLOOR: 66-4, 6/10/20 - See last page for vote
SUBJECT: Los Angeles Unified School District: best value procurement
SOURCE: Author
DIGEST:
This bill extends the authority for the Los Angeles Unified School District (LAUSD) to use the best value procurement method by five years, from January 1, 2021, to January 1, 2026.
ANALYSIS:
Existing law:
- Requires the governing board of a school district to competitively bid and award to the lowest bidder contracts involving the following:
- An expenditure of $50,000 or more for the purchase of equipment, materials, or supplies, services (except for construction services), and repairs.
- An expenditure of $15,000 or more for a public contract project defined as construction, reconstruction, erection, alteration, renovation, improvement, demolition, repair, painting or repainting of any publicly owned, leased, or operated facility. (Public Contract Code § 20111 and 22002)
- Authorizes, until January 1, 2021, the LAUSD to use the best value procurement method. (PCC § 20119.1)
- Requires the LAUSD to submit an interim report by July 1, 2018, and a final report by January 1, 2020, prepared by an independent third party, to the appropriate policy and fiscal committees of the Legislature with specified information on the district’s use of the best value procurement method. (PCC § 20119.5)
- Establishes a process, until January 1, 2025, for school district governing boards to enter into a design-build contract for both the design and construction of education facility projects over $1 million. (Education Code § 17250.20)
- Specifies the elements required to be included in a design-build request for proposal (including significant factors, subfactors, methodology, rating and weighting schemes for evaluating proposals) and establishes, among others, prequalification, bonding and labor compliance program requirements. (EC § 17250.10 – 17250.55)
- Requires a school district with an average daily attendance of more than 2,500 using state school facility bond funds for a public project with an expenditure of $1 million or more to require prospective bidders, and if utilized, all electrical, mechanical, and plumbing subcontractors, to complete and submit a standardized prequalification questionnaire and financial statement. (PCC § 20111.6)
- Authorizes the University of California (UC) to utilize the best value method to award contracts for projects over $1 million. (PCC § 10506.4)
This bill:
- Extends the authority for the LAUSD to use the best value procurement method by five years, from January 1, 2021, to January 1, 2026.
- Updates the date by which the district has extended or renewed a project labor agreement from January 1, 2017 to January 1, 2020, in order to be exempt from the requirement to use a skilled and trained workforce.
- Requires the LAUSD to submit a report, paid for by the school district and conducted by an independent entity, to the appropriate policy and fiscal committees of the Legislature by January 1, 2025.
Comments
- Need for the bill. According to the author, “AB 1981 simply extends the sunset on LAUSD"s ability to use this [best value procurement] method by five years so the state can continue to evaluate this model for other school districts. It also modifies the reporting dates to reflect this extension."
- What is the best value method? The best value method is defined as a procurement process whereby a bidder may be selected on the basis of objective evaluation criteria representing the best combination of price and qualifications. This method allows the district to consider “values” in addition to cost in awarding construction contracts, such as relevant experience and safety record. The authorization only applies to projects over $1 million. Expected benefits of best value include reduction in contract delays, change orders, and claims, resulting in contracting and administrative savings.
AB 1185 (Ridley-Thomas, Chapter 786, Statutes of 2015) established a pilot program, until January 1, 2021, authorizing LAUSD to use the best value procurement method. LAUSD’s authority to use design build was modeled after authorization given to the UC. LAUSD is required to adopt procedures and guidelines for evaluating the qualifications of bidders to ensure that the process is fair and impartial, and procedures for protesting and resolving a contract award. A prequalification process based on a questionnaire and a rating scale is required. The solicitation for bids invites prequalified bidders to submit sealed bids. The district evaluates the bids based on answers to a separate best value questionnaire and assigns a qualification score. The bidder's price is then divided by its qualification score. The lowest resulting cost per quality point represents the best value bid.
- Most recent report to the Legislature. LAUSD was required to complete an interim report by July 1, 2018, and a final report by January 1, 2020, conducted by an independent entity. The final report, completed in November, 2019, concluded that the LAUSD complied with the statutory requirements for implementation of the best value procurement method and the “completed projects generally realized expected benefits.” Some of the highlights from the report include the following:
- The district awarded 16 best value contracts, two of which were later terminated. The 14 remaining contracts represents 5 percent of the total number of contracts awarded and 19 percent of the total dollar value awarded for all construction contracts between January 1, 2016, and October 31, 2019.
- As of the date of the report, four of the 14 projects had been completed and four were near completion.
- In comparison with non-best value projects, best value projects received minimal scheduling delays. One best value project that received more significant delays was due to design errors and not the contracting process.
- The district received four award protests and generally resolved the protests in a timely manner. Three of the protests were deemed to be without merit. One was found to have merit and the project was subsequently re-scoped and rebid.
- Change orders were below general industry standard of 10 percent of total awarded costs.
FISCAL EFFECT: Appropriation: No Fiscal Com.: No Local: No
SUPPORT: (Verified 7/30/20)
California Legislative Conference of Plumbing, Heating & Piping Industry
Los Angeles Unified School District
National Electrical Contractors Association
Northern California Allied Trades
Southern California Glass Management Association
State Building & Construction Trades Council of California
OPPOSITION: (Verified 7/30/20)
None received
ASSEMBLY FLOOR: 66-4, 6/10/20
AYES: Aguiar-Curry, Arambula, Bauer-Kahan, Berman, Bloom, Boerner Horvath, Bonta, Burke, Calderon, Carrillo, Cervantes, Chau, Chiu, Chu, Cooley, Cooper, Cunningham, Daly, Diep, Eggman, Flora, Frazier, Friedman, Gabriel, Gallagher, Cristina Garcia, Eduardo Garcia, Gipson, Gloria, Gonzalez, Gray, Grayson, Holden, Irwin, Jones-Sawyer, Kalra, Kamlager, Lackey, Levine, Limón, Low, Maienschein, Mayes, McCarty, Medina, Mullin, Muratsuchi, Nazarian, O'Donnell, Petrie-Norris, Quirk-Silva, Ramos, Reyes, Luz Rivas, Robert Rivas, Rodriguez, Blanca Rubio, Salas, Santiago, Smith, Mark Stone, Ting, Weber, Wicks, Wood, Rendon
NOES: Bigelow, Mathis, Obernolte, Voepel
NO VOTE RECORDED: Brough, Chen, Choi, Megan Dahle, Fong, Kiley, Patterson, Quirk, Waldron
Prepared by: Ian Johnson / ED. /
7/31/20 17:54:47
**** END ****
SENATE COMMITTEE ON EDUCATION
Senator Connie Leyva, Chair
2019 - 2020 Regular
Bill No: Hearing Date: July 29, 2020
Author: | Nazarian | ||
Version: |
| ||
Urgency: | Fiscal: | ||
Consultant: | |||
Subject:
SUMMARY
This bill extends the authority for the Los Angeles Unified School District (LAUSD) to use the best value procurement method by five years, from January 1, 2021, to January 1, 2026.
BACKGROUND
Existing law:
- Requires the governing board of a school district to competitively bid and award to the lowest bidder contracts involving the following:
- An expenditure of $50,000 or more for the purchase of equipment, materials, or supplies, services (except for construction services), and repairs.
- An expenditure of $15,000 or more for a public contract project defined as construction, reconstruction, erection, alteration, renovation, improvement, demolition, repair, painting or repainting of any publicly owned, leased, or operated facility. (Public Contract Code § 20111 and 22002)
- Authorizes, until January 1, 2021, the LAUSD to use the best value procurement method. (PCC § 20119.1)
- Requires the LAUSD to submit an interim report by July 1, 2018, and a final report by January 1, 2020, prepared by an independent third party, to the appropriate policy and fiscal committees of the Legislature with specified information on the district’s use of the best value procurement method. (PCC § 20119.5)
- Establishes a process, until January 1, 2025, for school district governing boards to enter into a design-build contract for both the design and construction of education facility projects over $1 million. (Education Code § 17250.20)
- Specifies the elements required to be included in a design-build request for proposal (including significant factors, subfactors, methodology, rating and weighting schemes for evaluating proposals) and establishes, among others, prequalification, bonding and labor compliance program requirements. (EC § 17250.10 – 17250.55)
- Requires a school district with an average daily attendance of more than 2,500 using state school facility bond funds for a public project with an expenditure of $1 million or more to require prospective bidders, and if utilized, all electrical, mechanical, and plumbing subcontractors, to complete and submit a standardized prequalification questionnaire and financial statement. (PCC § 20111.6)
- Authorizes the University of California (UC) to utilize the best value method to award contracts for projects over $1 million. (PCC § 10506.4)
ANALYSIS
This bill:
- Extends the authority for the LAUSD to use the best value procurement method by five years, from January 1, 2021, to January 1, 2026.
- Updates the date by which the district has extended or renewed a project labor agreement from January 1, 2017 to January 1, 2020, in order to be exempt from the requirement to use a skilled and trained workforce.
- Requires the LAUSD to submit a report, paid for by the school district and conducted by an independent entity, to the appropriate policy and fiscal committees of the Legislature by January 1, 2025.
STAFF COMMENTS
- Need for the bill. According to the author, “AB 1981 simply extends the sunset on LAUSD"s ability to use this [best value procurement] method by five years so the state can continue to evaluate this model for other school districts. It also modifies the reporting dates to reflect this extension."
- What is the best value method? The best value method is defined as a procurement process whereby a bidder may be selected on the basis of objective evaluation criteria representing the best combination of price and qualifications. This method allows the district to consider “values” in addition to cost in awarding construction contracts, such as relevant experience and safety record. The authorization only applies to projects over $1 million. Expected benefits of best value include reduction in contract delays, change orders, and claims, resulting in contracting and administrative savings.
AB 1185 (Ridley-Thomas), Chapter 786, Statutes of 2015, established a pilot program, until January 1, 2021, authorizing LAUSD to use the best value procurement method. LAUSD’s authority to use design build was modeled after authorization given to the UC. LAUSD is required to adopt procedures and guidelines for evaluating the qualifications of bidders to ensure that the process is fair and impartial, and procedures for protesting and resolving a contract award. A prequalification process based on a questionnaire and a rating scale is required. The solicitation for bids invites prequalified bidders to submit sealed bids. The district evaluates the bids based on answers to a separate best value questionnaire and assigns a qualification score. The bidder's price is then divided by its qualification score. The lowest resulting cost per quality point represents the best value bid.
- Most recent report to the Legislature. LAUSD was required to complete an interim report by July 1, 2018, and a final report by January 1, 2020, conducted by an independent entity. The final report, completed in November, 2019, concluded that the LAUSD complied with the statutory requirements for implementation of the best value procurement method and the “completed projects generally realized expected benefits.” Some of the highlights from the report include the following:
- The district awarded 16 best value contracts, two of which were later terminated. The 14 remaining contracts represents 5 percent of the total number of contracts awarded and 19 percent of the total dollar value awarded for all construction contracts between January 1, 2016, and October 31, 2019.
- As of the date of the report, four of the 14 projects had been completed and four were near completion.
- In comparison with non-best value projects, best value projects received minimal scheduling delays. One best value project that received more significant delays was due to design errors and not the contracting process.
- The district received four award protests and generally resolved the protests in a timely manner. Three of the protests were deemed to be without merit. One was found to have merit and the project was subsequently re-scoped and rebid.
- Change orders were below general industry standard of 10 percent of total awarded costs.
SUPPORT
California Legislative Conference of Plumbing, Heating & Piping Industry
Los Angeles Unified School District
National Electrical Contractors Association
Northern California Allied Trades
Southern California Glass Management Association
State Building & Construction Trades Council of California
OPPOSITION
None received
-- END --
ASSEMBLY THIRD READING
ATR Bill Id:AB 1981
Author:(Nazarian)
As Amended Ver:May 11, 2020
Majority vote
SUMMARY:
Extends the sunset of the authorization for the Los Angeles Unified School District (LAUSD) to use the best value procurement method by five years, from January 1, 2021, to January 1, 2026.
Major Provisions
- Updates the date by which the district has extended or renewed a project labor agreement from January 1, 2017, to January 1, 2020, in order to be exempt from the requirement to use a skilled and trained workforce.
- Requires the LAUSD to submit a report, paid for by the school district and conducted by an independent entity, to the appropriate policy and fiscal committees of the Legislature by January 1, 2025.
- Strikes obsolete provisions.
COMMENTS:
Background. Under current law, K-12 school districts are required to competitively bid any public works contract over $15,000 and award the contract to the lowest responsible bidder. Under the traditional method for school facility construction, a school district would first hire an architect to design a school facility and then issue a bid for the construction phase, awarding the contract to the lowest bidder. This process is commonly called "design-bid-build."
Best value pilot program. AB 1185 (Ridley-Thomas), Chapter 786, Statutes of 2015, established a pilot program, until January 1, 2021, authorizing LAUSD to use the "best value" procurement method. Best value is defined as a procurement process whereby the selected bidder may be selected on the basis of objective criteria for evaluating the qualifications of bidders with the resulting selection representing the best combination of price and qualifications. This method allows the district to consider "values" in addition to cost in awarding construction contracts, such as relevant experience and safety record. The authorization applies only to projects over $1 million. Expected benefits of best value include reduction in contract delays, change orders, and claims, resulting in contracting and administrative savings.
LAUSD is required to adopt procedures and guidelines for evaluating the qualifications of bidders to ensure that the process is fair and impartial, and procedures for protesting and resolving a contract award. A prequalification process based on a questionnaire and a rating scale is required. The solicitation for bids invites prequalified bidders to submit sealed bids. The district evaluates the bids based on answers to a separate best value questionnaire and assigns a qualification score. The bidder"s price is then divided by its qualification score. The lowest resulting cost per quality point represents the best value bid.
Since 2015, other alternative means of contracting, including lease-leaseback and design build, have incorporated best value components.
Report to the Legislature. LAUSD was required to complete an interim report by July 1, 2018, and a final report by January 1, 2020, conducted by an independent entity. The final report, completed in November 2019, concluded that the LAUSD complied with the statutory requirements for implementation of the best value procurement method and the "completed projects generally realized expected benefits." Some of the highlights from the report include the following:
- In comparison with non-best value projects, best value projects received minimal scheduling delays. One best value project that received more significant delays was due to design errors and not the contracting process.
- Change orders (8.5% of total awarded costs) were below general industry standard of 10%.
- Other benefits identified by the district:
- Interest from a larger pool of firms and more qualified firms.
- Better communication on project approach due to interviews conducted with potential bidders.
- Increase in quality subcontractors due to subcontractor scoring.
According to the Author:
"AB 1981 simply extends the sunset on LAUSD"s ability to use this [best value procurement] method by five years so the state can continue to evaluate this model for other school districts. It also modifies the reporting dates to reflect this extension."
Arguments in Support:
The sponsor, LAUSD, states, "With billions of dollars in state and local funds being spent on school construction projects at Los Angeles Unified, it is imperative that the district has the necessary tools to reduce risk and maximize efficiencies. The best value procurement process creates transparent and objective criteria that will result in the selection of a quality contractor with a good history at a competitive price."
Arguments in Opposition:
None received.
FISCAL COMMENTS:
This bill has been keyed non-fiscal by the Office of Legislative Counsel.
VOTES:
ASM EDUCATION: 5-0-2
YES: O'Donnell, Kalra, McCarty, Smith, Weber
ABS, ABST OR NV: Kiley, Megan Dahle
UPDATED:
VERSION: May 11, 2020
CONSULTANT: Sophia Kwong Kim / ED. / (916) 319-2087 FN: 0002750
Date of Hearing: May 6, 2020
ASSEMBLY COMMITTEE ON EDUCATION
Patrick O'Donnell, Chair
ABPCA Bill Id:AB 1981 (
Author:Nazarian) – As Amended Ver:February 24, 2020
SUBJECT: Los Angeles Unified School District: best value procurement
SUMMARY: Extends the sunset of the authorization for the Los Angeles Unified School District (LAUSD) to use the best value procurement method by five years, from January 1, 2021, to January 1, 2026. Specifically, this bill:
- Finds and declares that the best value procurement method has provided the benefits of more qualified contractors applying and an open dialogue on project approach, according to the Los Angeles Unified School District’s interim report to the Legislature from June 2018, titled “Los Angeles Unified School District, Interim Report on Best Value Procurement Method.”
- Updates the date by which the district has extended or renewed a project labor agreement from January 1, 2017 to January 1, 2020, in order to be exempt from the requirement to use a skilled and trained workforce.
- Requires the LAUSD to submit a report, paid for by the school district and conducted by an independent entity, to the appropriate policy and fiscal committees of the Legislature by January 1, 2025.
- Strikes obsolete provisions.
EXISTING LAW:
- Requires the governing board of a school district to competitively bid and award to the lowest bidder contracts involving the following:
- An expenditure of $50,000 or more for the purchase of equipment, materials, or supplies, services (except for construction services), and repairs.
- An expenditure of $15,000 or more for a public contract project defined as construction, reconstruction, erection, alteration, renovation, improvement, demolition, repair, painting or repainting of any publicly owned, leased, or operated facility. (Public Contract Code (PCC) 20111 and 22002)
- Authorizes, until January 1, 2021, the LAUSD to use the best value procurement method. (PC 20119.1)
- Requires the LAUSD to submit an interim report by July 1, 2018, and a final report by January 1, 2020, prepared by an independent third party, to the appropriate policy and fiscal committees of the Legislature with specified information on the district’s use of the best value procurement method. (PCC 20119.5)
- Establishes a process, until January 1, 2025, for school district governing boards to enter into a design-build contract for both the design and construction of education facility projects over $1 million. (Education Code (EC) 17250.20)
- Specifies the elements required to be included in a design-build request for proposal (including significant factors, subfactors, methodology, rating and weighting schemes for evaluating proposals) and establishes, among others, prequalification, bonding and labor compliance program requirements. (EC 17250.10 – 17250.55)
- Requires a school district with an average daily attendance of more than 2,500 using state school facility bond funds for a public project with an expenditure of $1 million or more to require prospective bidders, and if utilized, all electrical, mechanical, and plumbing subcontractors, to complete and submit a standardized prequalification questionnaire and financial statement. (PCC Section 20111.6)
- Authorizes the University of California (UC) to utilize the best value method to award contracts for projects over $1 million. (PCC 10506.4)
FISCAL EFFECT: This bill has been keyed non-fiscal by the Office of Legislative Counsel.
COMMENTS:
Background. Under current law, K-12 school districts are required to competitively bid any public works contract over $15,000 and award the contract to the lowest responsible bidder. Under the traditional method for school facility construction, a school district would first hire an architect to design a school facility and then issue a bid for the construction phase, awarding the contract to the lowest bidder. This process is commonly called "design-bid-build."
Best value pilot program. AB 1185 (Ridley-Thomas), Chapter 786, Statutes of 2015, established a pilot program, until January 1, 2021, authorizing LAUSD to use the "best value" procurement method. Best value is defined as a procurement process whereby the selected bidder may be selected on the basis of objective criteria for evaluating the qualifications of bidders with the resulting selection representing the best combination of price and qualifications. This method allows the district to consider “values” in addition to cost in awarding construction contracts, such as relevant experience and safety record. The authorization applies only to projects over $1 million. Expected benefits of best value include reduction in contract delays, change orders, and claims, resulting in contracting and administrative savings.
LAUSD’s authority to use design build was modeled after authorization given to the UC. LAUSD is required to adopt procedures and guidelines for evaluating the qualifications of bidders to ensure that the process is fair and impartial, and procedures for protesting and resolving a contract award. A prequalification process based on a questionnaire and a rating scale is required. The solicitation for bids invites prequalified bidders to submit sealed bids. The district evaluates the bids based on answers to a separate best value questionnaire and assigns a qualification score. The bidder's price is then divided by its qualification score. The lowest resulting cost per quality point represents the best value bid.
Since 2015, other alternative means of contracting, including lease-leaseback and design build, have incorporated best value components.
Report to the Legislature. LAUSD was required to complete an interim report by July 1, 2018, and a final report by January 1, 2020, conducted by an independent entity. The final report, completed in November, 2019, concluded that the LAUSD complied with the statutory requirements for implementation of the best value procurement method and the “completed projects generally realized expected benefits.” Some of the highlights from the report include the following:
- The LAUSD awarded 16 best value contracts, two of which were later terminated. The 14 remaining contracts represents 5% of the total number of contracts awarded and 19% of the total dollar value awarded for all LAUSD construction contracts between January 1, 2016, and October 31, 2019.
- As of the date of the report, four of the 14 projects had been completed and four were near completion.
- In comparison with non-best value projects, best value projects received minimal scheduling delays. One best value project that received more significant delays was due to design errors and not the contracting process.
- LAUSD received four award protests and generally resolved the protests in a timely manner. Three of the protests were deemed to be without merit. One was found to have merit and the project was subsequently re-scoped and rebid.
- Change orders (8.5% of total awarded costs) were below general industry standard of 10%.
- Other benefits identified by the district:
- Interest from a larger pool of firms and more qualified firms.
- Better communication on project approach due to interviews conducted with potential bidders.
- Increase in quality subcontractors due to subcontractor scoring.
This bill extends the January 1, 2021, sunset by five years, to January 1, 2026, and requires LAUSD to submit a report, paid for by the school district and conducted by an independent entity, to the appropriate policy and fiscal committees of the Legislature by January 1, 2025. The authority for the UC to use best value is available to all UC campuses.
The Committee may wish to consider whether the best value authorization should be expanded to all school districts. Districts would not be required to utilize alternative means of contracting, but would be provided with an additional option to seek qualified contractors and subcontractors.
Recommended Committee Amendments. Staff recommends an amendment in the findings section to change the reference of the report submitted by LAUSD from “interim report” to “final report.”
Arguments in support. The author states, “AB 1981 simply extends the sunset on LAUSD’s ability to use this [best value procurement] method by five years so the state can continue to evaluate this model for other school districts. It also modifies the reporting dates to reflect this extension. With billions of dollars in state and local funds being spent on school construction projects throughout the state, it is imperative school districts have the necessary tools to reduce risk and maximize efficiencies. The best value procurement method creates transparent and objective criteria that will result in the selection of a quality contractor with a good history at a competitive price.”
Related legislation. AB 1185 (Ridley-Thomas), Chapter 786, Statutes of 2015, authorized the LAUSD to utilize the best value procurement method.
AB 1971 (Bocanegra) of 2014, held by the author on the Senate floor, was similar to AB 1185.
REGISTERED SUPPORT / OPPOSITION:
Support
Los Angeles Unified School District
State Building & Construction Trades Council of California
Opposition
None on file
Analysis Prepared by: Sophia Kwong Kim / ED. / (916) 319-2087