SB 199: Public Utilities Commission: Office of the Safety Advocate.
- Session Year: 2019-2020
- House: Senate
- Latest Version Date: 2019-09-13
Under existing law, the Public Utilities Commission has regulatory authority over public utilities, including electrical corporations, gas corporations, and water corporations. Existing law requires the commission to appoint an executive director who is responsible for the commissions executive and administrative duties and is required to organize, coordinate, supervise, and direct the operations and affairs of the commission and expedite all matters within the commissions jurisdiction. Existing law establishes the Office of the Safety Advocate within the commission, until January 1, 2020, to advocate for the continuous, cost-effective improvement of the safety management and safety performance of public utilities. Existing law requires the office to undertake specific actions, including that it recommend improvements to the commissions safety management policy and procedures and the commissions safety culture.
This bill would extend the operation of the Office of the Safety Advocate until January 1, 2025, and would require the office to conduct safety trainings for commission staff, as specified. The bill would move from the office to the commission the requirement to recommend improvements to the commissions safety management policy and procedures and its safety culture, would require those recommendations to be made annually, as specified, and would require the executive director to report the commissions findings and recommendations to a subcommittee of the commission. The bill would authorize the commission to contract with an independent entity to audit the effectiveness of the commissions safety performance.
Existing law requires the commission to report on various subjects to the Legislature.
This bill would require the commission to annually report to the chairperson of the appropriate policy committee of each house of the Legislature on the actions taken by the commission in response to recommended improvements to the commissions safety management policy and procedures and its safety culture, and on the impact of commission safety trainings, with appropriate assessments, surveys, and interviews of staff pertaining to their understanding and implementation of the commissions safety management system and safety culture. The bill would require the office, by February 1 of each year, to provide to the appropriate policy committee of each house of the Legislature information on the actions taken by the office to recommend improvements to public utility safety management policy and procedures and safety culture, and information on proceedings in which the office participated and a brief description of the testimony it filed.
(a)There is hereby established within the commission the Office of the Safety Advocate to advocate for the continuous, cost-effective improvement of the safety management and safety performance of public utilities.
(b)The office shall promote public utility safety by doing all of the following:
(1)Advocating, as a party to commission proceedings and on behalf of the interests of public utility customers, for effective public utility safety management and infrastructure improvements and for the transparency of safety information, including, but not limited to, information relating to past performance.
(2)Informing the official record on safety-related risks in applicable commission proceedings and assisting the commission in its efforts to hold public utilities accountable for their safe operation.
(3)Conducting safety trainings for commission staff to bolster the safety management policies and safety culture at the commission.
(c)This section shall remain in effect only until January 1, 2025, and as of that date is repealed.
SEC. 2.Section 309.9 is added to the Public Utilities Code, to read:309.9.(a)The commission shall annually recommend improvements to its safety management policy and procedures and its safety culture, including, but not limited to, all of the following:
(1)Improvements to overhaul and reform commission procedures to implement safety-related initiatives and requirements more efficiently.
(2)Improvements based upon gap analysis of the commissions safety structure and programs against a safety management system framework in order to assess the existence and maturity of existing safety elements.
(3)Improvements based upon evaluation of high-risk industry models to compare against the commissions safety structure and processes.
(4)Improvements based upon assessing the impact and retention of commission staff safety trainings and making recommendations to improve such trainings.
(b)The executive director shall report the commissions findings and recommendations pursuant to subdivision (a) directly to a subcommittee of the commission.
(c)The commission may contract with an independent entity to audit the effectiveness of the commissions safety performance pursuant to this section. The hiring of an independent entity shall not relieve commissioners nor managers from responsibility for safety. It is the intent of the Legislature that the requirements of this section provide accountability for the commissions safety management system and safety culture. It is the further intent of the Legislature that safety knowledge and accountability are to be shared throughout the commission.
SEC. 3.Section 911.5 is added to the Public Utilities Code, to read:911.5.(a)The commission shall annually provide the following information to the chairperson of the appropriate policy committee of each house of the Legislature:
(1)The actions taken by the commission in response to recommended improvements to the commissions safety management policy and procedures and its safety culture made pursuant to Section 309.9.
(2)The impact of commission safety trainings, with appropriate assessments, surveys, and interviews of staff pertaining to their understanding and implementation of the commissions safety management system and safety culture.
(b)On or before February 1 of each year, the Office of the Safety Advocate shall provide the following information to the appropriate policy committee of each house of the Legislature:
(1)The actions taken by the office to recommend improvements to public utility safety management policy and procedures and safety culture.
(2)The proceedings in which the office participated and a brief description of the testimony it filed.
|
Date
|
Status
|
|---|---|
| Jan 13, 2020 | Stricken from file. |
| Oct 12, 2019 | In Senate. Consideration of Governor's veto pending. |
| Oct 12, 2019 | Vetoed by the Governor. |
| Sep 18, 2019 | Enrolled and presented to the Governor at 4 p.m. |
| Sep 11, 2019 | Assembly amendments concurred in. (Ayes 40. Noes 0.) Ordered to engrossing and enrolling. |
| Sep 9, 2019 | In Senate. Concurrence in Assembly amendments pending. |
| Sep 9, 2019 | Read third time. Passed. Ordered to the Senate. |
| Sep 5, 2019 | Read third time and amended. |
| Sep 3, 2019 | Read second time. Ordered to third reading. |
| Aug 30, 2019 | From committee: Do pass. (Ayes 18. Noes 0.) (August 30). |
| Aug 14, 2019 | August 14 set for first hearing. Placed on APPR. suspense file. |
| Jul 11, 2019 | From committee: Do pass and re-refer to Com. on APPR. with recommendation: To consent calendar. (Ayes 15. Noes 0.) (July 10). Re-referred to Com. on APPR. |
| Jul 1, 2019 | July 3 hearing postponed by committee. |
| Jun 6, 2019 | Referred to Com. on U. & E. |
| May 24, 2019 | In Assembly. Read first time. Held at Desk. |
| May 23, 2019 | Read third time. Passed. (Ayes 38. Noes 0.) Ordered to the Assembly. |
| May 21, 2019 | Ordered to special consent calendar. |
| May 16, 2019 | From committee: Do pass. (Ayes 6. Noes 0.) (May 16). |
| May 14, 2019 | Set for hearing May 16. |
| May 13, 2019 | May 13 hearing: Placed on APPR. suspense file. |
| May 3, 2019 | Set for hearing May 13. |
| Apr 24, 2019 | From committee: Do pass and re-refer to Com. on APPR. (Ayes 13. Noes 0.) (April 24). Re-referred to Com. on APPR. |
| Apr 8, 2019 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on E., U. & C. |
| Apr 3, 2019 | Set for hearing April 24. |
| Feb 13, 2019 | Referred to Com. on E., U. & C. |
| Feb 1, 2019 | From printer. May be acted upon on or after March 3. |
| Jan 31, 2019 | Introduced. Read first time. To Com. on RLS. for assignment. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Sep 11, 2019 | Unfinished Business SB199 Hill Concurrence | Senate Floor |
Passed |
|
| Sep 9, 2019 | SB 199 Hill Senate Third Reading By Holden | Assembly Floor |
Passed |
|
| Aug 30, 2019 | Do pass. | Assembly Standing Committee on Appropriations |
Passed |
|
| Jul 10, 2019 | Do pass and be re-referred to the Committee on [Appropriations] with recommendation: To Consent Calendar | Assembly Standing Committee on Utilities and Energy |
Passed |
|
| May 23, 2019 | Special Consent SB199 | Senate Floor |
Passed |
|
| May 16, 2019 | Do pass | Senate Standing Committee on Appropriations |
Passed |
|
| May 13, 2019 | Placed on suspense file | Senate Standing Committee on Appropriations |
Passed |
|
| Apr 24, 2019 | Do pass, but first be re-referred to the Committee on [Appropriations] | Senate Standing Committee on Energy, Utilities and Communications |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 199 |
VETO
Bill No: SB 199
Amended: 9/5/19
SENATE ENERGY, U. & C. COMMITTEE: 13-0, 4/24/19
AYES: Hueso, Moorlach, Bradford, Chang, Dodd, Hertzberg, Hill, McGuire, Rubio, Skinner, Stern, Stone, Wiener
SENATE APPROPRIATIONS COMMITTEE: 6-0, 5/16/19
AYES: Portantino, Bates, Bradford, Hill, Jones, Wieckowski
SENATE FLOOR: 38-0, 5/23/19
AYES: Allen, Archuleta, Atkins, Bates, Beall, Borgeas, Bradford, Caballero, Chang, Dodd, Durazo, Galgiani, Glazer, Grove, Hertzberg, Hill, Hueso, Hurtado, Jackson, Jones, Leyva, McGuire, Mitchell, Monning, Moorlach, Morrell, Nielsen, Pan, Portantino, Roth, Rubio, Skinner, Stern, Stone, Umberg, Wieckowski, Wiener, Wilk
SENATE FLOOR: 40-0, 9/11/19
AYES: Allen, Archuleta, Atkins, Bates, Beall, Borgeas, Bradford, Caballero, Chang, Dahle, Dodd, Durazo, Galgiani, Glazer, Lena Gonzalez, Grove, Hertzberg, Hill, Hueso, Hurtado, Jackson, Jones, Leyva, McGuire, Mitchell, Monning, Moorlach, Morrell, Nielsen, Pan, Portantino, Roth, Rubio, Skinner, Stern, Stone, Umberg, Wieckowski, Wiener, Wilk
ASSEMBLY FLOOR: 79-0, 9/9/19 - See last page for vote
SUBJECT: Public Utilities Commission: Office of the Safety Advocate
DIGEST:
This bill extends the sunset date for the California Public Utilities Commission (CPUC) Office of the Safety Advocate (OSA) from January 1, 2020, to January 1, 2025. This bill also modifies the OSA’s duties to include safety trainings for CPUC staff and requires the CPUC and OSA to report to the Legislature annually on their activities under this bill.
Existing law:
- Requires the CPUC to establish rules for a public utility and revise those requirements through an order or rule whenever the CPUC, after a hearing, finds that existing rules, practices, equipment, appliances, facilities or service of any public utility or manufacturing, distribution, transmission, storage or supply methods employed by the public utility are unjust, unreasonable, unsafe, improper, inadequate, or insufficient. (Public Utilities Code §761)
- Establishes the OSA within the CPUC to support continuous, cost-effective improvement of the safety management and safety performance of public utilities. (Public Utilities Code §309.8(a))
- Requires the OSA to do the following:
- Advocate at CPUC in proceedings on behalf of public utility customers to support effective utility safety management and infrastructure upgrades and enhance safety information transparency.
- Make recommendations for improving the CPUC’s safety management policies and procedures and the CPUC’s safety culture.
- Provide information for CPUC proceeding official records on safety-related risks and support the CPUC in holding public utilities accountable for safe operations. (Public Utilities Code §309.8(b))
- Requires the OSA to annually report the following information to the Chair of the relevant legislative policy committees:
- OSA recommendations made to improve CPUC safety management policies and procedures and safety culture.
- OSA recommendations to improve public utility safety management policies and procedures and safety culture.
- Proceedings in which OSA participated and a description of OSA’s testimony in those proceedings. (Public Utilities Code §309.8(c))
- Sunsets the OSA on January 1, 2020. (Public Utilities Code §309.8(d))
- Requires the CPUC to appoint a chief internal auditor and requires the auditor to perform the following duties:
- Plan, initiate, and conduct audits of key financial, management, operational, and information technology functions within the CPUC to improve accountability and transparency.
- Report the audit findings and recommendations to a CPUC audit subcommittee.
- Comply with requirements for internal audits of public agencies. (Public Utilities Code §307.6)
This bill:
- Extends the sunset of the OSA from January 1, 2020, to January 1, 2025.
- Expands OSA’s duties to include conducting safety trainings for CPUC staff to support safety management policies and safety culture.
- Requires the CPUC to annually make recommendations to improve its safety management policy and procedures and safety culture. These recommendations must include at least the following:
- Improvements to reform CPUC procedures to implement safety requirements more efficiently.
- Improvements based on a gap analysis comparing the CPUC’s safety programs against a safety management system framework.
- Improvements based on a comparison of high-risk industry models against the CPUC’s safety structure and processes.
- Improvements based on assessments of the impact of safety trainings for CPUC staff and recommendations for improving these trainings.
- Requires the CPUC’s executive director to report the CPUC’s findings and recommendations to a subcommittee within the CPUC.
- Authorizes the CPUC to contract with an independent entity to audit the CPUC’s safety performance.
- Requires the CPUC to annually report the following information to the relevant policy committees of the Legislature:
- Actions taken by the CPUC in response to safety improvement recommendations
- Impact of CPUC safety trainings based on information from CPUC regarding their understanding and implementation of safety principles.
- Requires the OSA to provide the appropriate policy committees of the Legislature with the following information by February 1 each year:
- Actions taken by OSA to recommend safety improvements
- CPUC proceedings in which OSA participated and a brief description of its testimony in those proceedings.
Background
A brief history of CPUC safety management. On September 9, 2010, a Pacific Gas and Electric Company (PG&E) natural gas transmission pipeline ruptured in San Bruno. Gas from the rupture ignited, resulting in eight deaths, injuries to 58 people, destruction of 38 homes, and damage to 70 additional homes. The San Bruno explosion led to multiple investigations and reports on safety issues associated with California’s natural gas infrastructure and oversight of the utilities that own and operate that infrastructure. A National Transportation Safety Board (NTSB) report stated that the probable cause of the explosion was a lack of quality assurance and pipeline integrity management from PG&E; however, the NTSB report also cited CPUC’s lack of effective oversight over natural gas utility operations as a contributing factor.
Concerns about natural gas safety oversight continued to surface following the 2015 natural gas leak at the Southern California Gas Company’s Aliso Canyon Natural Gas Storage Facility. Following the Aliso Canyon leak, the CPUC submitted a budget change proposal (BCP) for the 2016-17 state fiscal year to establish a Division of Safety Advocates within the CPUC, which would advocate for the prioritization and protection of Californians’ safety as a party to CPUC hearings. This BCP specifically cited the Aliso Canyon leak an example of a utility safety issue for which there was an absence of stakeholder groups advocating to prioritize Californians’ safety. The BCP stated the following:
The leak at the Aliso Canyon Storage Facility cannot be considered an isolated incident. Rather, it highlights the much larger issue that much of California's gas and electric utility infrastructure was installed prior to 1970, and this aging infrastructure needs to be constantly monitored, inspected, and evaluated for potential threats. In 2015 alone, the CPUC investigated 522 separate gas and electric incidents resulting from this aging infrastructure. Utility requests for infrastructure upgrades and related maintenance, inspection, and monitoring are increasing rapidly. Such requests are considered in General Rate Case applications… There are no stakeholder groups that are solely dedicated to public safety that are willing to appear before the Commission and actively participate in relevant proceedings. The lack of such groups and the increasing number of incidents due to aging utility infrastructure compel the Commission to create a new Division of Safety Advocates within its own body to highlight safety.
In 2017, the Legislature passed SB 62 (Hill, Chapter 421, Statutes of 2017), which established the OSA and provided the CPUC with funding to support the safety advocacy goals outlined in the CPUC’s 2016-17 BCP. Under existing law, the OSA is scheduled to sunset on January 1, 2020. This bill extends OSA’s sunset to January 1, 2025.
How many offices are needed at the CPUC? The CPUC’s 2016-17 BCP envisioned that the Division of Safety Advocates would function in a manner similar to the Office of Ratepayer Advocates (ORA), which was established to advocate for “…the lowest possible rate for service consistent with reliable and safe service levels.” However, since the creation of the OSA, legislation has renamed the ORA as the Public Advocate’s Office (PAO). While existing law continues to require the PAO to advocate for lower rates, the renaming raises the question of whether the PAO will expand its mission to encompass advocacy beyond ratepayer savings, including utility safety. To the extent that PAO also advocates for utility safety, PAO and OSA may have overlapping advocacy roles.
Catastrophic wildfires and SB 901 (Dodd, Chapter 626, Statutes of 2018). Utility infrastructure has been associated with catastrophic fires in the past; however, catastrophic wildfires enhanced concerns related to electric infrastructure. In 2017, California experienced some of the largest and most destructive wildfires in its modern history. California Department of Fire and Forestry Protection (CAL FIRE) reports indicated that at least 18 of the 170 fires that formed the 2017 North Bay Fire Siege were caused by utility equipment. The 2017 Thomas Fire in Ventura and Santa Barbara Counties burned over 281,000 acres, destroying over 1,000 buildings and killing two people. The Thomas Fire also indirectly resulted in the deaths of 21 people who died in a debris flow created by heavy rains fell on the area burned by the fire. CAL FIRE reports also indicated that utility infrastructure was associated with the ignition of the Thomas Fire.
While the 2017 fires occurred, the CPUC issued a decision denying cost recovery for uninsured utility costs associated with 2007 fires in San Diego. As part of its decision, the CPUC urged the Legislature to consider issues of utility fault for wildfires associated with utility ignitions. In 2018, the Legislature passed SB 901, which established a number of wildfire prevention and mitigation requirements, including safety requirements that must be included in wildfire mitigation plans (WMPs).
CPUC’s 2019-20 OSA budget request. This bill’s current fiscal estimate does not appear to reflect the current version of this bill. This bill no longer requires the re-establishment of the OSA as an independent office. Instead, many of this bill’s requirements are consistent with duties that the CPUC envisioned for the OSA its its initial and subsequent BCPs, including the BCP it submitted this year for the OSA. Following the passage of SB 901, the CPUC submitted a BCP to support utility safety and wildfire mitigation duties codified by the legislation. This BCP includes a request for four staff positions for the OSA. The CPUC’s BCP states that SB 901 significantly increases the OSA’s duties. In the BCP, the CPUC says the following. “SB 901 creates substantial new work for OSA. OSA staffing levels are currently insufficient to fulfill the duties required to participate in the WMP processes established by the bill. OSA requires additional staff to fulfill these new duties.“
The CPUC can act on its own motion, but timeliness and consistency is an issue. The CPUC’s role in regulating utilities has evolved over time. Since its establishment as the railroad commission in 1911, the statutory and constitutional role of the CPUC as an active regulator has been affirmed. In 1940, the California Supreme Court noted that the CPUC has the authority to take action on its own accord in Sale v. Railroad Commission. In its decision, the Court stated, “…the railroad commission, unlike a court, may act sua sponte and is not dependent upon the appearance of a party to ‘invoke’ its jurisdiction.”
While offices at the CPUC can advocate for a safety culture and specific safety management practices, this advocacy does not supplant the duty of the CPUC to exercise its authority to ensure that policies and procedures for utilities are safe. Existing law requires the CPUC to exercise its utility regulatory powers to adjust utility requirements whenever it finds existing utility practices to be unsafe. However, some CPUC decisions regarding utility safety indicate that the CPUC has taken a reactive approach in the past and focused on establishing requirements specific to individual utilities instead of establishing consistent requirements across utilities. For example, following San Diego’s Witch, Rice and Guejito fires, the CPUC adopted new vegetation management, clearance, ignition prevention, and facility inspection requirements for locations in southern. However, until recently, similar requirements did not apply to PG&E territory. Even as these requirements are applied to PG&E, they are adopted piecemeal through multiple decisions and resolutions at later dates.
This bill authorizes the CPUC to contract with an independent entity to conduct an audit of the CPUC’s safety performance; however, it makes clear that this audit does not supplant the CPUC’s responsibility as a regulator over utility safety. This bill would require the CPUC to report on the effectiveness of the OSA’s trainings of CPUC staff to determine the extent to which these duties are supporting safety improvements. This bill also requires the OSA to report on its participating in CPUC proceedings. This information can help the Legislature determine the extent to which OSA is effectively advocating for utility safety improvements on behalf of Californians before the CPUC.
Related/Prior Legislation
SB 901 (Dodd, Chapter 626, Statutes of 2018) established a number of utility safety requirements, including requirements for electric utilities to create and submit wildfire mitigation plans that identify mechanisms for preventing, combatting, and responding to wildfires within each utility service territory.
SB 19 (Hill, Chapter 421, Statutes of 2017) required the CPUC to appoint a chief internal auditor and specified the duties of the auditor.
SB 62 (Hill, Chapter 806, Statutes of 2016) codified the OSA within the CPUC until January 1, 2020, to advocate for the continuous, cost-effective improvement of the safety management and safety performance of public utilities.
SB 900 (Hill, Chapter 552, Statutes of 2014) required the CPUC to consider safety in electrical and gas general rate cases.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: No
According to the Assembly Appropriations Committee, ongoing annual costs in the low millions of dollars (special fund) to continue the work of the office.
According to an analysis prepared by the Department of Finance (Finance), continuation of the office—as the office is currently constituted—would cost approximately $2 million per year. However, Finance objects to this bill as written, in that this bill establishes the office as an “independent” entity within the CPUC. Finance contends the office currently is an integral part of the CPUC’s Safety and Enforcement Division and, as such, is an effective and efficient element of the CPUC’s safety efforts. Conversely, Finance asserts establishment of the office as an independent entity within the CPUC will create a barrier between the office and the CPUC, thereby diminishing the office’s efficiency and effectiveness.
More relevant to this analysis, Finance contends it will cost tens of millions of dollars annually to operate the office as an independent entity. Finance bases this cost estimate on the cost to operate the Public Advocate’s Office (formerly and more accurately known as the Office of Ratepayer Advocate), which statute also establishes as “independent.” According to Finance, the Public Advocate’s budget was approximately $35 million last year and included resources for central administrative services such as payroll and human resources, along with space and other necessities currently provided to the office by the CPUC.
Rural County Representatives of California
OPPOSITION: (Verified 10/14/19)
None received
ARGUMENTS IN SUPPORT: According to the author, “SB 199 clarifies the role of the OSA at the CPUC, and removes the program sunset currently in statute. The Legislature created OSA in 2016 under SB 62 (Hill). Since its creation in January 2017, OSA has provided valuable contributions at the CPUC advocating for improved utility safety and stronger CPUC safety oversight. During this time, California has experienced devastating loss through wildfire and mudslides, with utility infrastructure largely suspected to be a factor or cause. Extensive focus on utility safety and accountability has understandably resulted. The extension of OSA’s expertise, as proposed by SB 199, provides enormous value to these efforts to ensure its mission of improving ‘the safety management and safety performance of public utilities to prevent accidents, injuries, and to save lives’ persists.”
GOVERNOR'S VETO MESSAGE:
I am returning Senate Bill 199 without my signature.
This bill extends the sunset date for the California Public Utilities Commission (CPUC) Office of the Safety Advocate (OSA) from January 1, 2020, to January 1, 2025. This bill also modifies the OSA’s duties to include safety trainings for CPUC staff and requires the CPUC and OSA to report to the Legislature annually on their activities under this bill.
OSA was created in 2016 to advocate for and recommend improvements to utility safety policies adopted by the CPUC. Over the past few years, several measures aimed at improving utility safety and oversight, leading to the establishment and improvement of offices or divisions within the CPUC strictly focused on this critical mission. At this juncture, the CPUC is working to implement these new requirements, and the OSA is now duplicative of the many duties of the Office of the Energy Infrastructure Safety. Allowing the OSA to sunset does not mean that its important work will not continue. Rather, those duties will be effectively integrated into CPUC.
ASSEMBLY FLOOR: 79-0, 9/9/19
AYES: Aguiar-Curry, Arambula, Bauer-Kahan, Berman, Bigelow, Bloom, Boerner Horvath, Bonta, Brough, Burke, Calderon, Carrillo, Cervantes, Chau, Chen, Chiu, Choi, Chu, Cooley, Cooper, Cunningham, Daly, Diep, Eggman, Flora, Fong, Frazier, Friedman, Gabriel, Gallagher, Cristina Garcia, Eduardo Garcia, Gipson, Gloria, Gonzalez, Gray, Grayson, Holden, Irwin, Jones-Sawyer, Kalra, Kamlager-Dove, Kiley, Lackey, Levine, Limón, Low, Maienschein, Mathis, Mayes, McCarty, Medina, Melendez, Mullin, Muratsuchi, Nazarian, Obernolte, O'Donnell, Patterson, Petrie-Norris, Quirk, Quirk-Silva, Ramos, Reyes, Luz Rivas, Robert Rivas, Rodriguez, Blanca Rubio, Salas, Santiago, Smith, Mark Stone, Ting, Voepel, Waldron, Weber, Wicks, Wood, Rendon
Prepared by: Sarah Smith / E., U., & C. / (916) 651-4107
10/21/19 11:31:58
**** END ****
Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 199 |
UNFINISHED BUSINESS
Bill No: SB 199
Amended: 9/5/19
SENATE ENERGY, U. & C. COMMITTEE: 13-0, 4/24/19
AYES: Hueso, Moorlach, Bradford, Chang, Dodd, Hertzberg, Hill, McGuire, Rubio, Skinner, Stern, Stone, Wiener
SENATE APPROPRIATIONS COMMITTEE: 6-0, 5/16/19
AYES: Portantino, Bates, Bradford, Hill, Jones, Wieckowski
SENATE FLOOR: 38-0, 5/23/19
AYES: Allen, Archuleta, Atkins, Bates, Beall, Borgeas, Bradford, Caballero, Chang, Dodd, Durazo, Galgiani, Glazer, Grove, Hertzberg, Hill, Hueso, Hurtado, Jackson, Jones, Leyva, McGuire, Mitchell, Monning, Moorlach, Morrell, Nielsen, Pan, Portantino, Roth, Rubio, Skinner, Stern, Stone, Umberg, Wieckowski, Wiener, Wilk
ASSEMBLY FLOOR: 79-0, 9/9/19 - See last page for vote
SUBJECT: Public Utilities Commission: Office of the Safety Advocate
DIGEST:
This bill extends the sunset date for the California Public Utilities Commission (CPUC) Office of the Safety Advocate (OSA) from January 1, 2020, to January 1, 2025. This bill also modifies the OSA’s duties to include safety trainings for CPUC staff and requires the CPUC and OSA to report to the Legislature annually on their activities under this bill.
Assembly Amendments
delete re-establishment of the OSA as an independent office and instead extend the OSA’s sunset to 2025; require OSA to conduct safety trainings for CPUC staff; and require the CPUC and OSA to annually report specified information to the relevant policy committees of the Legislature.
Existing law:
- Requires the CPUC to establish rules for a public utility and revise those requirements through an order or rule whenever the CPUC, after a hearing, finds that existing rules, practices, equipment, appliances, facilities or service of any public utility or manufacturing, distribution, transmission, storage or supply methods employed by the public utility are unjust, unreasonable, unsafe, improper, inadequate, or insufficient. (Public Utilities Code §761)
- Establishes the OSA within the CPUC to support continuous, cost-effective improvement of the safety management and safety performance of public utilities. (Public Utilities Code §309.8(a))
- Requires the OSA to do the following:
- Advocate at CPUC in proceedings on behalf of public utility customers to support effective utility safety management and infrastructure upgrades and enhance safety information transparency.
- Make recommendations for improving the CPUC’s safety management policies and procedures and the CPUC’s safety culture.
- Provide information for CPUC proceeding official records on safety-related risks and support the CPUC in holding public utilities accountable for safe operations. (Public Utilities Code §309.8(b))
- Requires the OSA to annually report the following information to the Chair of the relevant legislative policy committees:
- OSA recommendations made to improve CPUC safety management policies and procedures and safety culture.
- OSA recommendations to improve public utility safety management policies and procedures and safety culture.
- Proceedings in which OSA participated and a description of OSA’s testimony in those proceedings. (Public Utilities Code §309.8(c))
- Sunsets the OSA on January 1, 2020. (Public Utilities Code §309.8(d))
- Requires the CPUC to appoint a chief internal auditor and requires the auditor to perform the following duties:
- Plan, initiate, and conduct audits of key financial, management, operational, and information technology functions within the CPUC to improve accountability and transparency.
- Report the audit findings and recommendations to a CPUC audit subcommittee.
- Comply with requirements for internal audits of public agencies. (Public Utilities Code §307.6)
This bill:
- Extends the sunset of the OSA from January 1, 2020, to January 1, 2025.
- Expands OSA’s duties to include conducting safety trainings for CPUC staff to support safety management policies and safety culture.
- Requires the CPUC to annually make recommendations to improve its safety management policy and procedures and safety culture. These recommendations must include at least the following:
- Improvements to reform CPUC procedures to implement safety requirements more efficiently.
- Improvements based on a gap analysis comparing the CPUC’s safety programs against a safety management system framework.
- Improvements based on a comparison of high-risk industry models against the CPUC’s safety structure and processes.
- Improvements based on assessments of the impact of safety trainings for CPUC staff and recommendations for improving these trainings.
- Requires the CPUC’s executive director to report the CPUC’s findings and recommendations to a subcommittee within the CPUC.
- Authorizes the CPUC to contract with an independent entity to audit the CPUC’s safety performance.
- Requires the CPUC to annually report the following information to the relevant policy committees of the Legislature:
- Actions taken by the CPUC in response to safety improvement recommendations
- Impact of CPUC safety trainings based on information from CPUC regarding their understanding and implementation of safety principles.
- Requires the OSA to provide the appropriate policy committees of the Legislature with the following information by February 1 each year:
- Actions taken by OSA to recommend safety improvements
- CPUC proceedings in which OSA participated and a brief description of its testimony in those proceedings.
Background
A brief history of CPUC safety management. On September 9, 2010, a Pacific Gas and Electric Company (PG&E) natural gas transmission pipeline ruptured in San Bruno. Gas from the rupture ignited, resulting in eight deaths, injuries to 58 people, destruction of 38 homes, and damage to 70 additional homes. The San Bruno explosion led to multiple investigations and reports on safety issues associated with California’s natural gas infrastructure and oversight of the utilities that own and operate that infrastructure. A National Transportation Safety Board (NTSB) report stated that the probable cause of the explosion was a lack of quality assurance and pipeline integrity management from PG&E; however, the NTSB report also cited CPUC’s lack of effective oversight over natural gas utility operations as a contributing factor.
Concerns about natural gas safety oversight continued to surface following the 2015 natural gas leak at the Southern California Gas Company’s Aliso Canyon Natural Gas Storage Facility. Following the Aliso Canyon leak, the CPUC submitted a budget change proposal (BCP) for the 2016-17 state fiscal year to establish a Division of Safety Advocates within the CPUC, which would advocate for the prioritization and protection of Californians’ safety as a party to CPUC hearings. This BCP specifically cited the Aliso Canyon leak an example of a utility safety issue for which there was an absence of stakeholder groups advocating to prioritize Californians’ safety. The BCP stated the following:
The leak at the Aliso Canyon Storage Facility cannot be considered an isolated incident. Rather, it highlights the much larger issue that much of California's gas and electric utility infrastructure was installed prior to 1970, and this aging infrastructure needs to be constantly monitored, inspected, and evaluated for potential threats. In 2015 alone, the CPUC investigated 522 separate gas and electric incidents resulting from this aging infrastructure. Utility requests for infrastructure upgrades and related maintenance, inspection, and monitoring are increasing rapidly. Such requests are considered in General Rate Case applications… There are no stakeholder groups that are solely dedicated to public safety that are willing to appear before the Commission and actively participate in relevant proceedings. The lack of such groups and the increasing number of incidents due to aging utility infrastructure compel the Commission to create a new Division of Safety Advocates within its own body to highlight safety.
In 2017, the Legislature passed SB 62 (Hill, Chapter 421, Statutes of 2017), which established the OSA and provided the CPUC with funding to support the safety advocacy goals outlined in the CPUC’s 2016-17 BCP. Under existing law, the OSA is scheduled to sunset on January 1, 2020. This bill extends OSA’s sunset to January 1, 2025.
How many offices are needed at the CPUC? The CPUC’s 2016-17 BCP envisioned that the Division of Safety Advocates would function in a manner similar to the Office of Ratepayer Advocates (ORA), which was established to advocate for “…the lowest possible rate for service consistent with reliable and safe service levels.” However, since the creation of the OSA, legislation has renamed the ORA as the Public Advocate’s Office (PAO). While existing law continues to require the PAO to advocate for lower rates, the renaming raises the question of whether the PAO will expand its mission to encompass advocacy beyond ratepayer savings, including utility safety. To the extent that PAO also advocates for utility safety, PAO and OSA may have overlapping advocacy roles.
Catastrophic wildfires and SB 901 (Dodd, Chapter 626, Statutes of 2018). Utility infrastructure has been associated with catastrophic fires in the past; however, catastrophic wildfires enhanced concerns related to electric infrastructure. In 2017, California experienced some of the largest and most destructive wildfires in its modern history. California Department of Fire and Forestry Protection (CAL FIRE) reports indicated that at least 18 of the 170 fires that formed the 2017 North Bay Fire Siege were caused by utility equipment. The 2017 Thomas Fire in Ventura and Santa Barbara Counties burned over 281,000 acres, destroying over 1,000 buildings and killing two people. The Thomas Fire also indirectly resulted in the deaths of 21 people who died in a debris flow created by heavy rains fell on the area burned by the fire. CAL FIRE reports also indicated that utility infrastructure was associated with the ignition of the Thomas Fire.
While the 2017 fires occurred, the CPUC issued a decision denying cost recovery for uninsured utility costs associated with 2007 fires in San Diego. As part of its decision, the CPUC urged the Legislature to consider issues of utility fault for wildfires associated with utility ignitions. In 2018, the Legislature passed SB 901, which established a number of wildfire prevention and mitigation requirements, including safety requirements that must be included in wildfire mitigation plans (WMPs).
CPUC’s 2019-20 OSA budget request. This bill’s current fiscal estimate does not appear to reflect the current version of this bill. This bill no longer requires the re-establishment of the OSA as an independent office. Instead, many of this bill’s requirements are consistent with duties that the CPUC envisioned for the OSA its its initial and subsequent BCPs, including the BCP it submitted this year for the OSA. Following the passage of SB 901, the CPUC submitted a BCP to support utility safety and wildfire mitigation duties codified by the legislation. This BCP includes a request for four staff positions for the OSA. The CPUC’s BCP states that SB 901 significantly increases the OSA’s duties. In the BCP, the CPUC says the following. “SB 901 creates substantial new work for OSA. OSA staffing levels are currently insufficient to fulfill the duties required to participate in the WMP processes established by the bill. OSA requires additional staff to fulfill these new duties.“
The CPUC can act on its own motion, but timeliness and consistency is an issue. The CPUC’s role in regulating utilities has evolved over time. Since its establishment as the railroad commission in 1911, the statutory and constitutional role of the CPUC as an active regulator has been affirmed. In 1940, the California Supreme Court noted that the CPUC has the authority to take action on its own accord in Sale v. Railroad Commission. In its decision, the Court stated, “…the railroad commission, unlike a court, may act sua sponte and is not dependent upon the appearance of a party to ‘invoke’ its jurisdiction.”
While offices at the CPUC can advocate for a safety culture and specific safety management practices, this advocacy does not supplant the duty of the CPUC to exercise its authority to ensure that policies and procedures for utilities are safe. Existing law requires the CPUC to exercise its utility regulatory powers to adjust utility requirements whenever it finds existing utility practices to be unsafe. However, some CPUC decisions regarding utility safety indicate that the CPUC has taken a reactive approach in the past and focused on establishing requirements specific to individual utilities instead of establishing consistent requirements across utilities. For example, following San Diego’s Witch, Rice and Guejito fires, the CPUC adopted new vegetation management, clearance, ignition prevention, and facility inspection requirements for locations in southern. However, until recently, similar requirements did not apply to PG&E territory. Even as these requirements are applied to PG&E, they are adopted piecemeal through multiple decisions and resolutions at later dates.
This bill authorizes the CPUC to contract with an independent entity to conduct an audit of the CPUC’s safety performance; however, it makes clear that this audit does not supplant the CPUC’s responsibility as a regulator over utility safety. This bill would require the CPUC to report on the effectiveness of the OSA’s trainings of CPUC staff to determine the extent to which these duties are supporting safety improvements. This bill also requires the OSA to report on its participating in CPUC proceedings. This information can help the Legislature determine the extent to which OSA is effectively advocating for utility safety improvements on behalf of Californians before the CPUC.
Related/Prior Legislation
SB 901 (Dodd, Chapter 626, Statutes of 2018) established a number of utility safety requirements, including requirements for electric utilities to create and submit wildfire mitigation plans that identify mechanisms for preventing, combatting, and responding to wildfires within each utility service territory.
SB 19 (Hill, Chapter 421, Statutes of 2017) required the CPUC to appoint a chief internal auditor and specified the duties of the auditor.
SB 62 (Hill, Chapter 806, Statutes of 2016) codified the OSA within the CPUC until January 1, 2020, to advocate for the continuous, cost-effective improvement of the safety management and safety performance of public utilities.
SB 900 (Hill, Chapter 552, Statutes of 2014) required the CPUC to consider safety in electrical and gas general rate cases.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: No
According to the Assembly Appropriations Committee, ongoing annual costs in the low millions of dollars (special fund) to continue the work of the office.
According to an analysis prepared by the Department of Finance (Finance), continuation of the office—as the office is currently constituted—would cost approximately $2 million per year. However, Finance objects to this bill as written, in that this bill establishes the office as an “independent” entity within the CPUC. Finance contends the office currently is an integral part of the CPUC’s Safety and Enforcement Division and, as such, is an effective and efficient element of the CPUC’s safety efforts. Conversely, Finance asserts establishment of the office as an independent entity within the CPUC will create a barrier between the office and the CPUC, thereby diminishing the office’s efficiency and effectiveness.
More relevant to this analysis, Finance contends it will cost tens of millions of dollars annually to operate the office as an independent entity. Finance bases this cost estimate on the cost to operate the Public Advocate’s Office (formerly and more accurately known as the Office of Ratepayer Advocate), which statute also establishes as “independent.” According to Finance, the Public Advocate’s budget was approximately $35 million last year and included resources for central administrative services such as payroll and human resources, along with space and other necessities currently provided to the office by the CPUC.
Rural County Representatives of California
None received
ARGUMENTS IN SUPPORT: According to the author, “SB 199 clarifies the role of the OSA at the CPUC, and removes the program sunset currently in statute. The Legislature created OSA in 2016 under SB 62 (Hill). Since its creation in January 2017, OSA has provided valuable contributions at the CPUC advocating for improved utility safety and stronger CPUC safety oversight. During this time, California has experienced devastating loss through wildfire and mudslides, with utility infrastructure largely suspected to be a factor or cause. Extensive focus on utility safety and accountability has understandably resulted. The extension of OSA’s expertise, as proposed by SB 199, provides enormous value to these efforts to ensure its mission of improving ‘the safety management and safety performance of public utilities to prevent accidents, injuries, and to save lives’ persists.”
ASSEMBLY FLOOR: 79-0, 9/9/19
AYES: Aguiar-Curry, Arambula, Bauer-Kahan, Berman, Bigelow, Bloom, Boerner Horvath, Bonta, Brough, Burke, Calderon, Carrillo, Cervantes, Chau, Chen, Chiu, Choi, Chu, Cooley, Cooper, Cunningham, Daly, Diep, Eggman, Flora, Fong, Frazier, Friedman, Gabriel, Gallagher, Cristina Garcia, Eduardo Garcia, Gipson, Gloria, Gonzalez, Gray, Grayson, Holden, Irwin, Jones-Sawyer, Kalra, Kamlager-Dove, Kiley, Lackey, Levine, Limón, Low, Maienschein, Mathis, Mayes, McCarty, Medina, Melendez, Mullin, Muratsuchi, Nazarian, Obernolte, O'Donnell, Patterson, Petrie-Norris, Quirk, Quirk-Silva, Ramos, Reyes, Luz Rivas, Robert Rivas, Rodriguez, Blanca Rubio, Salas, Santiago, Smith, Mark Stone, Ting, Voepel, Waldron, Weber, Wicks, Wood, Rendon
Prepared by: Sarah Smith / E., U., & C. / (916) 651-4107
9/9/19 23:01:45
**** END ****
SENATE THIRD READING
STR Bill Id:SB 199
Author:(Hill)
As Amended Ver:September 5, 2019
Majority vote
SUMMARY:
This bill extends the sunset date for the Office of the Safety Advocate (OSA) at the California Public Utilities Commission (CPUC) and modifies the mission and reporting requirements of the OSA.
Major Provisions
- Eliminate the charge to the OSA that it recommend improvements to the safety management and procedures and safety culture of the CPUC and a related element in its annual report to the Legislature.
- Add to the mission statement of the OSA that it conduct safety trainings for CPUC staff.
- Require that the CPUC annually recommend specified improvements to its safety management policy and procedures and safety culture, that the CPUC executive director report those recommendations to a subcommittee of commissioners, and authorize the CPUC to contract for an audit of the effectiveness of the CPUC's safety performance.
- Require specified and separate annual reports by the CPUC to legislative policy committees related to safety culture and proceedings.
- Extend the sunset of the OSA from January 1, 2020 to January 1, 2025.
COMMENTS:
The CPUC's Safety and Enforcement Division (SED) has five units: Rail Safety, Electric Safety & Reliability; Gas Safety & Reliability; Risk Assessment; and the Office of Utility Safety. These units are all direct reports to the SED director and the CPUC executive director. The OSA is statutorily required to recommend "improvements to the commission's safety management policy and procedures and its safety culture." The CPUC recently placed the OSA under the SED which could dampen its advocacy role in CPUC proceedings. The author's intent in this bill is to ensure that the OSA's work continue.
According to the Author:
This bill clarifies the role of the OSA and extends the January 1, 2020 sunset of the OSA by five years. The OSA was established by the Legislature in 2016, and has provided valuable contributions at the CPUC advocating for improved utility safety and stronger CPUC safety oversight. During this time, California has experienced devastating loss through wildfires and mudslides, with utility infrastructure largely suspected to be a factor or cause in several of those fires. Extensive focus on utility safety and accountability has understandably resulted. The extension of OSA's expertise provides enormous value to these efforts to ensure its mission of improving "the safety management and safety performance of public utilities to prevent accidents, injuries, and to save lives" persists. Its role has never been more critical as the State urgently needs safe utility service.
Arguments in Support:
The Rural County Representatives of California broadly "supports efforts to enhance safety and reduce the risk of wildfires." They have observed the work of the OSA and in support of this bill opine that the OSA has played "a vital role in advocating for safety improvements in utility operations."
Arguments in Opposition:
There is no registered opposition to this bill.
FISCAL COMMENTS:
According to the Assembly Appropriations Committee, this bill will result in ongoing annual costs in the low millions of dollars (special fund) to continue the work of the office.
VOTES:
SENATE FLOOR: 38-0-0
YES: Allen, Archuleta, Atkins, Bates, Beall, Borgeas, Bradford, Caballero, Chang, Dodd, Durazo, Galgiani, Glazer, Grove, Hertzberg, Hill, Hueso, Hurtado, Jackson, Jones, Leyva, McGuire, Mitchell, Monning, Moorlach, Morrell, Nielsen, Pan, Portantino, Roth, Rubio, Skinner, Stern, Stone, Umberg, Wieckowski, Wiener, Wilk
ASM UTILITIES AND ENERGY: 15-0-0
YES: Holden, Patterson, Burke, Carrillo, Chen, Cunningham, Eggman, Cristina Garcia, Eduardo Garcia, Mayes, Muratsuchi, Quirk, Reyes, Santiago, Ting
ASM APPROPRIATIONS: 18-0-0
YES: Gonzalez, Bigelow, Bloom, Bonta, Brough, Calderon, Carrillo, Chau, Diep, Eggman, Fong, Gabriel, Eduardo Garcia, Maienschein, Obernolte, Petrie-Norris, Quirk, Robert Rivas
UPDATED:
VERSION: September 5, 2019
CONSULTANT: Kellie Smith / U. & E. / (916) 319-2083 FN: 0001797
SENATE THIRD READING
STR Bill Id:SB 199
Author:(Hill)
As Amended Ver:April 8, 2019
Majority vote
SUMMARY:
This bill permanently establishes the Office of the Safety Advocate (OSA) at the California Public Utilities Commission (CPUC) by removing the sunset date and makes other structural changes.
Major Provisions
- Eliminates the January 1, 2020, sunset date for the OSA.
- Requires the director of the OSA to be appointed by the Governor and confirmed by the Senate and to annually appear before relevant legislative policy committees to report on the OSA's activities.
COMMENTS:
The CPUC's Safety and Enforcement Division (SED) has five units: Rail Safety, Electric Safety & Reliability; Gas Safety & Reliability; Risk Assessment; and the Office of Utility Safety. These units are all direct reports to the SED director and the CPUC executive director. The OSA is statutorily required to recommend "improvements to the commission's safety management policy and procedures and its safety culture." The CPUC recently placed the OSA under the SED which could dampen its advocacy role in CPUC proceedings.
The author's intent in this bill is to ensure that the OSA's work continue and be independent much like the Public Advocates Office (formerly the Office of the Ratepayer Advocate) with a director appointed by the Governor and confirmed by the Senate. This bill also requires the director of OSA to appear annually before the relevant policy committees of the Legislature to report on OSA's activities. This reporting requirement is similar to requirements established for the PAO
According to the Author:
SB 199 clarifies the role of the OSA at the CPUC, and removes the program sunset currently in statute. The Legislature created OSA in 2016 under SB 62 (Hill, Chapter 806). Since its creation in January 2017, OSA has provided valuable contributions at the CPUC advocating for improved utility safety and stronger CPUC safety oversight. During this time, California has experienced devastating loss through wildfire and mudslides, with utility infrastructure largely suspected to be a factor or cause. Extensive focus on utility safety and accountability has understandably resulted. The extension of OSA's expertise, as proposed by SB 199, provides enormous value to these efforts to ensure its mission of improving "the safety management and safety performance of public utilities to prevent accidents, injuries, and to save lives" persists.
Arguments in Support:
The Rural County Representatives of California broadly "supports efforts to enhance safety and reduce the risk of wildfires." They have observed the work of the OSA and in support of this bill opine that the OSA has played "a vital role in advocating for safety improvements in utility operations. Given that Governor Newsom's Wildfire Strike Force recently suggested expanding CPUC's safety expertise and considering the need for utilities to continue focusing on safety, RCRC strongly supports repealing OSA's sunset date and increasing its independence."
Arguments in Opposition:
There is no registered opposition to this bill.
FISCAL COMMENTS:
According to the Assembly Appropriations Committee, this bill will result in ongoing annual costs in the low millions of dollars (special fund) to continue the work of the office.
VOTES:
SENATE FLOOR: 38-0-0
YES: Allen, Archuleta, Atkins, Bates, Beall, Borgeas, Bradford, Caballero, Chang, Dodd, Durazo, Galgiani, Glazer, Grove, Hertzberg, Hill, Hueso, Hurtado, Jackson, Jones, Leyva, McGuire, Mitchell, Monning, Moorlach, Morrell, Nielsen, Pan, Portantino, Roth, Rubio, Skinner, Stern, Stone, Umberg, Wieckowski, Wiener, Wilk
ASM UTILITIES AND ENERGY: 15-0-0
YES: Holden, Patterson, Burke, Carrillo, Chen, Cunningham, Eggman, Cristina Garcia, Eduardo Garcia, Mayes, Muratsuchi, Quirk, Reyes, Santiago, Ting
ASM APPROPRIATIONS: 18-0-0
YES: Gonzalez, Bigelow, Bloom, Bonta, Brough, Calderon, Carrillo, Chau, Diep, Eggman, Fong, Gabriel, Eduardo Garcia, Maienschein, Obernolte, Petrie-Norris, Quirk, Robert Rivas
UPDATED:
VERSION: April 8, 2019
CONSULTANT: Kellie Smith / U. & E. / (916) 319-2083 FN: 0001783
Date of Hearing: August 14, 2019
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Lorena Gonzalez, Chair
SBPCA Bill Id:SB 199
Author:(Hill) – As Amended Ver:April 8, 2019
Policy Committee: | Utilities and Energy | Vote: | 15 - 0 |
|
| ||
|
|
Urgency: No State Mandated Local Program: No Reimbursable: No
SUMMARY:
This bill recasts the Office of the Safety Advocate—which existing law establishes within the California Public Utilities Commission (CPUC)—as an “independent” office, requires the director of the office to be appointed by, and serve at the pleasure of, the Governor, subject to Senate confirmation, and deletes existing statute that repeals the authority of the office to operate as of January 1, 2020.
The bill also modifies procedures affecting the work of the office. Specifically, the bill (a) requires the CPUC to adopt a timeline by which it is to complete its evaluation of a recommendation made by the office; (b) requires a decision to adopt a recommendation of the office be made by a vote of the CPUC commissioners and, where applicable, adoption of a timeline for implementation of the recommendation; (c) directs the office to work with the chief internal officer of the CPUC to ensure the CPUC complies with the statutory requirements regarding the office; and (d) requires the director of the office to appear annually before the appropriate policy committees of the Assembly and the Senate.
FISCAL EFFECT:
Ongoing annual costs in the low millions of dollars (special fund) to continue the work of the office.
According to an analysis prepared by the Department of Finance (Finance), continuation of the office—as the office is currently constituted—would cost approximately $2 million per year. However, Finance objects to the bill as written, in that the bill establishes the office as an “independent” entity within the CPUC. Finance contends the office currently is an integral part of the CPUC’s Safety and Enforcement Division and, as such, is an effective and efficient element of the commission’s safety efforts. Conversely, Finance asserts establishment of the office as an independent entity within the CPUC will create a barrier between the office and the CPUC, thereby diminishing the office’s efficiency and effectiveness.
More relevant to this analysis, Finance contends it will cost tens of millions of dollars annually to operate the office as an independent entity. Finance bases this cost estimate on the cost to operate the Public Advocate’s Office (formerly and more accurately known as the Office of Ratepayer Advocate), which statute also establishes as “independent.” According to Finance, the Public Advocate’s budget was approximately $35 million last year and included resources for central administrative services such as payroll and human resources, along with space and other necessities currently provided to the office by the CPUC.
COMMENTS:
Background and Purpose. Following catastrophic, deadly failures of Pacific Gas and Electric’s (PGE’s) equipment, as well as investigations and audits critical of the CPUC’s basic administration and oversight of the safety of natural gas infrastructure, the CPUC advocated for establishment of an independent safety office. At the time, the CPUC acknowledged its obligation to consider utility safety, as manifest by the existence of the CPUC’s Safety Enforcement Division (SED). However, the CPUC contended SED focused on enforcement of existing regulations and rules and had limited capacity to participate in the rate-making process. What was needed, the then-president of the CPUC asserted, was an independent office focused on advocating for safety issues within CPUC general rate-making proceedings, a focus not held by other proceeding participants. As a result, the 2016-17 Budget Act authorized 11 permanent positions and $1.694 million in funding to create a Division of Safety Advocates, an independent division within the CPUC to establish a safety focus, testify at hearings and exclusively prioritize and advocate for the protection and safety of Californians as a party to CPUC proceedings.
Subsequently, the Legislature passed SB 62 (Hill), Chapter 802, Statutes of 2016, which established the Office of Safety Advocate within the CPUC, until January 1, 2020, to advocate for the continuous, cost-effective improvement of the safety management and safety performance of public utilities. According to the author of SB 62, the legislation was needed to fix “problems” with the CPUC’s budget proposal:
As the funding for the proposal was approved in this year’s Budget, the Legislature must provide statutory policy direction to: 1) ensure that the CPUC cannot shift responsibility for safety onto this advocate, as responsibility lies ultimately with the CPUC, to 2) advocate for the transparency of safety-related performance, and to 3) sunset the advocate, so that it can’t limp on in perpetuity without action by the Legislature.
With the office’s statutory expiration nearing, the author asserts the office should be made permanent.
SB 199 clarifies the role of the OSA at the CPUC, and removes the program sunset currently in statute. The Legislature created OSA in 2016 under SB 62 (Hill, Chapter 806). Since its creation in January 2017, OSA has provided valuable contributions at the CPUC advocating for improved utility safety and stronger CPUC safety oversight. During this time, California has experienced devastating loss through wildfire and mudslides, with utility infrastructure largely suspected to be a factor or cause. Extensive focus on utility safety and accountability has understandably resulted. The extension of OSA’s expertise, as proposed by SB 199, provides enormous value to these efforts to ensure its mission of improving “the safety management and safety performance of public utilities to prevent accidents, injuries, and to save lives” persists.
However, this bill does not simply remove the sunset on the statute that creates the Office of Safety Advocate. It modifies the statute, too, recasting the office as “independent” and requiring the director of the office to be appointed by the Governor and confirmed by the Senate.
It is important for the Legislature to consider what it expects of the office. As noted above, Finance describes value in the office operating as “an integral part of SED.” However, the legislative history strongly suggests the Legislature in general and the author specifically (and the then-president of the CPUC) envisioned the office as an independent advocate for safety, not an integrated component of CPUC’s overall safety efforts. Whether the office is integrated or independent has implications for both function and cost (even if one assumes Finance’s estimate of the cost to implement this bill is exaggerated).
Analysis Prepared by: Jay Dickenson / APPR. / (916) 319-2081
Date of Hearing: July 10, 2019
ASSEMBLY COMMITTEE ON UTILITIES AND ENERGY
Chris Holden, Chair
SBPCA Bill Id:SB 199
Author:(Hill) – As Amended Ver:April 8, 2019
SENATE VOTE: 38-0
SUBJECT: Public Utilities Commission: Office of the Safety Advocate
SUMMARY: Permanently establishes the Office of the Safety Advocate (OSA) at the California Public Utilities Commission (CPUC) and makes other structural changes. Specifically, this bill:
- Requires the director of the OSA to be appointed by the Governor and confirmed by the Senate and to annually appear before relevant legislative policy committees to report on the OSA’s activities.
- Requires the CPUC to adopt timelines for evaluating and implementing OSA recommendations.
- Requires the OSA to work with the CPUC’s internal auditor to ensure that the CPUC complies with requirements regarding timelines for evaluating and adopting OSA recommendations.
- Eliminates the January 1, 2020, sunset date for the OSA.
EXISTING LAW:
- Establishes the OSA within the CPUC to support continuous, cost-effective improvement of the safety management and safety performance of public utilities. (Public Utilities Code § 309.8 [a])
- Requires the OSA to participate in CPUC proceedings to advocate on behalf ratepayers; for effective public utility safety management and infrastructure improvements and for the transparency of safety information; recommend improvements to the CPUC’s safety management policy and procedures and its safety culture. (Public Utilities Code § 309.8 [b])
- Requires the OSA to annually report to the chairs of the relevant policy committees with recommendations improve CPUC safety management policies and procedures and safety culture; (Public Utilities Code § 309.8 [c]) and
- Sunsets the OSA on January 1, 2020. (Public Utilities Code § 309.8 [d])
FISCAL EFFECT: According to the Senate Appropriations Committee, based on the OSA’s existing budget, this bill would result a minimum cost of approximately $1 million to fund nine positions. However, this amount (and the number of positions) could be higher since the OSA would now be an independent office and may require additional resources for central administrative services such as payroll and human resources. (Public Utilities Reimbursement Account)
BACKGROUND:
Office of the Safety Advocate – According to the OSA’s annual report, it advocates and recommends improvements in utility safety management, safety culture, and utility infrastructure. As utilities, technology, and best practices rapidly evolve, OSA seeks to identify both best practices and program gaps, and to recommend improvements to close those gaps. OSA reviews utility programs as elements of a safety management system in which safety culture forms the foundation. OSA efforts complement and augment the CPUC’s core safety work of conducting audits and inspections of utility compliance with general orders and regulations. OSA works with and leverages audit and inspection data from the it’s Safety and Enforcement Division (SED) in support of OSA’s work.
OSA participates in CPUC proceedings, including rate cases, to advocate for safety and to seek to identify gaps in proposed utility programs. Other intervenors in proceedings may include ratepayer advocates and municipalities focusing on several other concerns including ratepayer costs.
In some cases, OSA may advocate for increased utility investments to address gaps and to prevent incidents. As one example, OSA opposed a gas utility’s rate case “Project Substitution” proposal because it could drop lower priority pipeline safety projects in favor of higher priority pipeline safety projects to ensure that the company did not spend more than revenue authorized in its rate case. OSA recommended instead that even when higher priority urgent safety work emerges, all identified safety projects should be implemented, and that the utility be permitted to request reimbursement in the event it exceeded the amount authorized. OSA believes that safety should be treated as a profit center, in that safety mitigation investment can save utilities and ratepayers from the enormous expense in both lives and damage of a catastrophic failure.
OSA prioritizes its work, focusing on utility safety management programs and infrastructure that staff assess as presenting the greatest risks to the public. OSA plans to continue to advocate in support of utility safety management systems to address risks. As OSA grows, it intends to expand and deepen its efforts to identify other significant risks with the potential for catastrophic failure.
COMMENTS:
- Author’s Statement. According to the author, SB 199 clarifies the role of the OSA at the CPUC, and removes the program sunset currently in statute. The Legislature created OSA in 2016 under SB 62 (Hill, Chapter 806). Since its creation in January 2017, OSA has provided valuable contributions at the CPUC advocating for improved utility safety and stronger CPUC safety oversight. During this time, California has experienced devastating loss through wildfire and mudslides, with utility infrastructure largely suspected to be a factor or cause. Extensive focus on utility safety and accountability has understandably resulted. The extension of OSA’s expertise, as proposed by SB 199, provides enormous value to these efforts to ensure its mission of improving “the safety management and safety performance of public utilities to prevent accidents, injuries, and to save lives” persists.
- OSA Independence. The Safety and Enforcement Division (SED) has five units: Rail Safety, Electric Safety & Reliability; Gas Safety & Reliability; Risk Assessment; and the Office of Utility Safety. These units are all direct reports to the SED director and CPUC executive director. The OSA is statutorily required to recommend “improvements to the commission’s safety management policy and procedures and its safety culture.” The CPUC recently placed the OSA under the SED which could dampen its advocacy role in CPUC proceedings.
The author’s intent in this bill is to ensure that the OSA be independent much like the Public Advocates Office (PAO, formerly the Office of the Ratepayer Advocate) with a director appointed by the Governor and confirmed by the Senate. This bill also requires the director of OSA to appear annually before the relevant policy committees of the Legislature to report on OSA’s activities. This reporting requirement is similar to requirements established for the PAO. - Expansion of Safety Oversight? Pending legislation will establish a new Division of Wildfire Safety within the CPUC to build safety expertise and a Wildfire Safety Advisory Board that will provide guidance to the new division. The division will oversee and enforce IOU safety compliance, develop and recommend performance metrics, establish a field audit program to evaluate compliance with wildfire mitigation plans, and assist with other wildfire safety initiatives. In 2021, the division and advisory council would be transferred to the Office of Energy Infrastructure Safety within the Natural Resources Agency.
The new division would basically be limited to poles and wires. All other safety programs would remain at the CPUC.\ But its work would also extend to oversight of the electrical infrastructure of the local publicly owned utilities.
- Related Legislation. AB 1054 (Holden, Burke, Mayes) and SB 111 (Committee on Budget) Together, the bills establish a new Wildfire Safety Division within the CPUC to be advised by an appointed advisory council of individuals experienced in the design, operation and engineering of electrical infrastructure.
- Prior Legislation. SB 62 (Hill) Established the OSA within the CPUC, until January 1, 2020, to advocate for the continuous, cost-effective improvement of the safety management and safety performance of public utilities. Chapter 806, Statutes of 2016
REGISTERED SUPPORT / OPPOSITION:
Support
Rural County Representatives of California
Opposition
None on file.
Analysis Prepared by: Kellie Smith / U. & E. /
Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 199 |
THIRD READING
Bill No: SB 199
Amended: 4/8/19
SENATE ENERGY, U. & C. COMMITTEE: 13-0, 4/24/19
AYES: Hueso, Moorlach, Bradford, Chang, Dodd, Hertzberg, Hill, McGuire, Rubio, Skinner, Stern, Stone, Wiener
SENATE APPROPRIATIONS COMMITTEE: 6-0, 5/16/19
AYES: Portantino, Bates, Bradford, Hill, Jones, Wieckowski
SUBJECT: Public Utilities Commission: Office of the Safety Advocate
DIGEST:
This bill re-establishes the California Public Utilities Commission (CPUC) Office of the Safety Advocate (OSA) as an independent office within the CPUC and requires the CPUC to adopt a timeline for evaluating and adopting OSA recommendations regarding safety management policies and procedures.
Existing law:
- Requires the CPUC to establish rules for a public utility and revise those requirements through an order or rule whenever the CPUC, after a hearing, finds that existing rules, practices, equipment, appliances, facilities or service of any public utility or manufacturing, distribution, transmission, storage or supply methods employed by the public utility are unjust, unreasonable, unsafe, improper, inadequate, or insufficient. (Public Utilities Code §761)
- Establishes the OSA within the CPUC to support continuous, cost-effective improvement of the safety management and safety performance of public utilities. (Public Utilities Code §309.8(a))
- Requires the OSA to do the following:
- Advocate at CPUC in proceedings on behalf of public utility customers to support effective utility safety management and infrastructure upgrades and enhance safety information transparency.
- Make recommendations for improving the CPUC’s safety management policies and procedures and the CPUC’s safety culture.
- Provide information for CPUC proceeding official records on safety-related risks and support the CPUC in holding public utilities accountable for safe operations. (Public Utilities Code §309.8(b))
- Requires the OSA to annually report the following information to the Chair of the relevant legislative policy committees:
- OSA recommendations made to improve CPUC safety management policies and procedures and safety culture.
- OSA recommendations to improve public utility safety management policies and procedures and safety culture.
- Proceedings in which OSA participated and a description of OSA’s testimony in those proceedings. (Public Utilities Code §309.8(c))
- Sunsets the OSA on January 1, 2020. (Public Utilities Code §309.8(d))
- Requires the CPUC to appoint a chief internal auditor and requires the auditor to perform the following duties:
- Plan, initiate, and conduct audits of key financial, management, operational, and information technology functions within the CPUC to improve accountability and transparency.
- Report the audit findings and recommendations to a CPUC audit subcommittee.
- Comply with requirements for internal audits of public agencies. (Public Utilities Code §307.6)
This bill:
- Re-establishes the OSA as an independent office within the CPUC and specifies that the OSA’s director will be appointed by the Governor, subject to confirmation by the Senate.
- Requires the director of OSA to annually appear before the relevant legislative policy committees and report on the OSA’s activities.
- Requires the CPUC to adopt timelines for evaluating and implementing OSA recommendations.
- Requires the OSA to work with the CPUC’s internal auditor to ensure that the CPUC complies with requirements regarding timelines for evaluating and adopting OSA recommendations.
- Eliminates the January 1, 2020, sunset date for the OSA.
Background
A brief history of CPUC safety management. On September 9, 2010, a Pacific Gas and Electric Company (PG&E) natural gas transmission pipeline ruptured in San Bruno. Gas from the rupture ignited, resulting in eight deaths, injuries to 58 people, destruction of 38 homes, and damage to 70 additional homes. The San Bruno explosion led to multiple investigations and reports on safety issues associated with California’s natural gas infrastructure and oversight of the utilities that own and operate that infrastructure. A National Transportation Safety Board (NTSB) report stated that the probable cause of the explosion was a lack of quality assurance and pipeline integrity management from PG&E; however, the NTSB report also cited CPUC’s lack of effective oversight over natural gas utility operations as a contributing factor.
Concerns about natural gas safety oversight continued to surface following the 2015 natural gas leak at the Southern California Gas Company’s Aliso Canyon Natural Gas Storage Facility. Following the Aliso Canyon leak, the CPUC submitted a budget change proposal (BCP) for the 2016-17 state fiscal year to establish an independent Division of Safety Advocates within the CPUC, which would advocate for the prioritization and protection of Californians’ safety as a party to CPUC hearings. This BCP specifically cited the Aliso Canyon leak an example of a utility safety issue for which there was an absence of stakeholder groups advocating to prioritize Californians’ safety. The BCP stated the following:
The leak at the Aliso Canyon Storage Facility cannot be considered an isolated incident. Rather, it highlights the much larger issue that much of California's gas and electric utility infrastructure was installed prior to 1970, and this aging infrastructure needs to be constantly monitored, inspected, and evaluated for potential threats. In 2015 alone, the CPUC investigated 522 separate gas and electric incidents resulting from this aging infrastructure. Utility requests for infrastructure upgrades and related maintenance, inspection, and monitoring are increasing rapidly. Such requests are considered in General Rate Case applications… There are no stakeholder groups that are solely dedicated to public safety that are willing to appear before the Commission and actively participate in relevant proceedings. The lack of such groups and the increasing number of incidents due to aging utility infrastructure compel the Commission to create a new Division of Safety Advocates within its own body to highlight safety.
In 2017, the Legislature passed SB 62 (Hill, Chapter 421, Statutes of 2017), which established the OSA and provided the CPUC with funding to support the safety advocacy goals outlined in the CPUC’s 2016-17 BCP. Under existing law, the OSA is scheduled to sunset on January 1, 2020. This bill clarifies certain OSA duties and eliminate the existing sunset date for OSA.
How many independent offices are needed? Existing law does not explicitly establish the OSA as an independent office of the CPUC. This bill re-establishes the OSA as an independent office with a director appointed by the Governor and confirmed by the Senate. This bill also requires the director of OSA to appear annually before the relevant policy committees of the Legislature to report on OSA’s activities. This reporting requirement is similar to requirements established for the Office of the Ratepayer Advocate (ORA). The CPUC’s 2016-17 BCP envisioned that the Division of Safety Advocates would function in a manner similar to the ORA, which was established to advocate for “…the lowest possible rate for service consistent with reliable and safe service levels.” However, since the creation of the OSA, legislation has renamed the ORA as the Public Advocate’s Office (PAO). While existing law continues to require the PAO to advocate for lower rates, the renaming raises the question of whether the PAO will expand its mission to encompass advocacy beyond ratepayer savings, including utility safety. To the extent that PAO also advocates for utility safety, PAO and OSA may have overlapping advocacy roles.
Catastrophic wildfires and SB 901 (Dodd, Chapter 626, Statutes of 2018). Utility infrastructure has been associated with catastrophic fires in the past; however, catastrophic wildfires enhanced concerns related to electric infrastructure. In 2017, California experienced some of the largest and most destructive wildfires in its modern history. California Department of Fire and Forestry Protection (CAL FIRE) reports indicated that at least 18 of the 170 fires that formed the 2017 North Bay Fire Siege were caused by utility equipment. The 2017 Thomas Fire in Ventura and Santa Barbara Counties burned over 281,000 acres, destroying over 1,000 buildings and killing two people. The Thomas Fire also indirectly resulted in the deaths of 21 people who died in a debris flow created by heavy rains fell on the area burned by the fire. CAL FIRE reports also indicated that utility infrastructure was associated with the ignition of the Thomas Fire.
While the 2017 fires occurred, the CPUC issued a decision denying cost recovery for uninsured utility costs associated with 2007 fires in San Diego. As part of its decision, the CPUC urged the Legislature to consider issues of utility fault for wildfires associated with utility ignitions. In 2018, the Legislature passed SB 901, which established a number of wildfire prevention and mitigation requirements, including safety requirements that must be included in wildfire mitigation plans (WMPs).
CPUC’s 2019-20 OSA budget request. Following the passage of SB 901, the CPUC submitted a BCP to support utility safety and wildfire mitigation duties codified by the legislation. This BCP includes a request for four staff positions for the OSA. The CPUC’s BCP states that SB 901 significantly increases the OSA’s duties. In the BCP, the CPUC says the following. “SB 901 creates substantial new work for OSA. OSA staffing levels are currently insufficient to fulfill the duties required to participate in the WMP processes established by the bill. OSA requires additional staff to fulfill these new duties.“
The BCP indicates that eight of the 11 OSA positions approved by the Legislature in 2017 have been filled. The 2019-20 BCP also requests four positions in addition to the 11 positions previously authorized. The additional four positions are intended to support SB 901 implementation.
The CPUC can act on its own motion, but timeliness and consistency is an issue. The CPUC’s role in regulating utilities has evolved over time. Since its establishment as the railroad commission in 1911, the statutory and constitutional role of the CPUC as an active regulator has been affirmed. In 1940, the California Supreme Court noted that the CPUC has the authority to take action on its own accord in Sale v. Railroad Commission. In its decision, the Court stated, “…the railroad commission, unlike a court, may act sua sponte and is not dependent upon the appearance of a party to ‘invoke’ its jurisdiction.”
While an independent office can advocate for utility safety on behalf of Californians, this advocacy does not supplant the duty of the CPUC to exercise its authority to ensure that policies and procedures for utilities are safe. Existing law requires the CPUC to exercise its utility regulatory powers to adjust utility requirements whenever it finds existing utility practices to be unsafe. However, some CPUC decisions regarding utility safety indicate that the CPUC has taken a reactive approach in the past and focused on establishing requirements specific to individual utilities instead of establishing consistent requirements across utilities. For example, following San Diego’s Witch, Rice and Guejito fires, the CPUC adopted new vegetation management, clearance, ignition prevention, and facility inspection requirements for locations in southern. However, until recently, similar requirements did not apply to PG&E territory. Even as these requirements are applied to PG&E, they are adopted piecemeal through multiple decisions and resolutions at later dates.
This bill requires the CPUC to establish timelines for the evaluation and implementation of OSA recommendations. This bill also requires the OSA to work with the CPUC’s internal auditor to ensure that the CPUC complies with requirements regarding the timelines. These requirements can help build accountability for the timely adoption of appropriate recommendations from OSA.
Related/Prior Legislation
SB 901 (Dodd, Chapter 626, Statutes of 2018) established a number of utility safety requirements, including requirements for electric utilities to create and submit wildfire mitigation plans that identify mechanisms for preventing, combatting, and responding to wildfires within each utility service territory.
SB 19 (Hill, Chapter 421, Statutes of 2017) required the CPUC to appoint a chief internal auditor and specified the duties of the auditor.
SB 62 (Hill, Chapter 806, Statutes of 2016) codified the OSA within the CPUC until January 1, 2020, to advocate for the continuous, cost-effective improvement of the safety management and safety performance of public utilities.
SB 900 (Hill, Chapter 552, Statutes of 2014) required the CPUC to consider safety in electrical and gas general rate cases.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: No
According to the Senate Appropriations Committee, this bill establishes the OSA as an independent office, which would otherwise sunset on January 1, 2020. Based on the OSA’s existing budget, this bill will result in a minimum cost of approximately $1 million to fund nine positions. However, this amount (and the number of positions) could be higher since the OSA would now be an independent office and may require additional resources for central administrative services such as payroll and human resources. (Public Utilities Reimbursement Account)
Rural County Representatives of California
OPPOSITION: (Verified 5/16/19)
None received
ARGUMENTS IN SUPPORT: According to the author:
SB 199 clarifies the role of the OSA at the CPUC, and removes the program sunset currently in statute. The Legislature created OSA in 2016 under SB 62 (Hill). Since its creation in January 2017, OSA has provided valuable contributions at the CPUC advocating for improved utility safety and stronger CPUC safety oversight. During this time, California has experienced devastating loss through wildfire and mudslides, with utility infrastructure largely suspected to be a factor or cause. Extensive focus on utility safety and accountability has understandably resulted. The extension of OSA’s expertise, as proposed by SB 199, provides enormous value to these efforts to ensure its mission of improving “the safety management and safety performance of public utilities to prevent accidents, injuries, and to save lives” persists.
Prepared by: Sarah Smith / E., U., & C. / (916) 651-4107
5/18/19 12:53:11
**** END ****
SENATE COMMITTEE ON APPROPRIATIONS
Senator Anthony Portantino, Chair
2019 - 2020 Regular Session
SB 199 (Hill) - Public Utilities Commission: Office of the Safety Advocate
Version: April 8, 2019 | Policy Vote: E., U., & C. 13 - 0 |
Urgency: No | Mandate: No |
Hearing Date: May 13, 2019 | Consultant: Lenin Del Castillo |
Bill Summary:
This bill permanently establishes the Office of the Safety Advocate as an independent office within the California Public Utilities Commission (CPUC) and requires the CPUC to adopt a timeline for evaluating and adopting OSA recommendations regarding safety management policies and procedures.
Fiscal Impact:
This bill would establish the OSA as an independent office which would otherwise sunset on January 1, 2020. Based on the OSA’s existing budget, this bill would result a minimum cost of approximately $1 million to fund nine positions. However, this amount (and the number of positions) could be higher since the OSA would now be an independent office and may require additional resources for central administrative services such as payroll and human resources. (Public Utilities Reimbursement Account)
Background:
Existing law requires the CPUC to establish rules for a public utility and revise those requirements through an order or rule whenever the CPUC, after a hearing, finds that existing rules, practices, equipment, appliances, facilities or service of any public utility or manufacturing, distribution, transmission, storage or supply methods employed by the public utility are unjust, unreasonable, unsafe, improper, inadequate, or insufficient.
Existing law establishes the OSA within the CPUC to support continuous, cost-effective improvement of the safety management and safety performance of public utilities. The OSA is required to do the following:
- Advocate at CPUC in proceedings on behalf of public utility customers to support effective utility safety management and infrastructure upgrades and enhance safety information transparency.
- Make recommendations for improving the CPUC’s safety management policies and procedures and the CPUC’s safety culture.
- Provide information for CPUC proceeding official records on safety-related risks and support the CPUC in holding public utilities accountable for safe operations.
The OSA is required to annually report the following information to the Chair of the relevant legislative policy committees:
- OSA recommendations made to improve CPUC safety management policies and procedures and safety culture.
- OSA recommendations to improve public utility safety management policies and procedures and safety culture.
Existing law sunsets the OSA on January 1, 2020.
Proposed Law:
This bill eliminates the January 1, 2020, sunset date for the OSA and re-establishes it as an independent office within the CPUC. The bill specifies that the OSA’s director will be appointed by the Governor, subject to confirmation by the Senate.
This bill requires the director of OSA to annually appear before the relevant legislative policy committees and report on the OSA’s activities.
This bill requires the CPUC to adopt timelines for evaluating and implementing OSA recommendations, and requires the OSA to work with the CPUC’s internal auditor to ensure that the CPUC complies with requirements regarding timelines for evaluating and adopting OSA recommendations.
Related Legislation:
SB 901 (Dodd, Chapter 626, Statutes of 2018) established a number of utility safety requirements, including requirements for electric utilities to create and submit wildfire mitigation plans that identify mechanisms for preventing, combatting, and responding to wildfires within each utility service territory.
SB 19 (Hill, Chapter 421, Statutes of 2017) required the CPUC to appoint a chief internal auditor and specified the duties of the auditor.
SB 62 (Hill, Chapter 806, Statutes of 2016) codified the OSA within the CPUC until January 1, 2020, to advocate for the continuous, cost-effective improvement of the safety management and safety performance of public utilities.
-- END --
SENATE COMMITTEE ON ENERGY, UTILITIES AND COMMUNICATIONS
Senator Ben Hueso, Chair
2019 - 2020 Regular
Bill No: SB 199 Hearing Date: 4/24/2019
Author: | Hill | ||
Version: | 4/8/2019 As Amended | ||
Urgency: | No | Fiscal: | Yes |
Consultant: | Sarah Smith | ||
SUBJECT: Public Utilities Commission: Office of the Safety Advocate
DIGEST: This bill re-establishes the California Public Utilities Commission (CPUC) Office of the Safety Advocate (OSA) as an independent office within the CPUC and requires the CPUC to adopt a timeline for evaluating and adopting OSA recommendations regarding safety management policies and procedures.
ANALYSIS:
Existing law:
- Requires the CPUC to establish rules for a public utility and revise those requirements through an order or rule whenever the CPUC, after a hearing, finds that existing rules, practices, equipment, appliances, facilities or service of any public utility or manufacturing, distribution, transmission, storage or supply methods employed by the public utility are unjust, unreasonable, unsafe, improper, inadequate, or insufficient. (Public Utilities Code §761)
- Establishes the OSA within the CPUC to support continuous, cost-effective improvement of the safety management and safety performance of public utilities. (Public Utilities Code §309.8(a))
- Requires the OSA to do the following:
- Advocate at CPUC in proceedings on behalf of public utility customers to support effective utility safety management and infrastructure upgrades and enhance safety information transparency.
- Make recommendations for improving the CPUC’s safety management policies and procedures and the CPUC’s safety culture.
- Provide information for CPUC proceeding official records on safety-related risks and support the CPUC in holding public utilities accountable for safe operations. (Public Utilities Code §309.8(b))
- Requires the OSA to annually report the following information to the Chair of the relevant legislative policy committees:
- OSA recommendations made to improve CPUC safety management policies and procedures and safety culture.
- OSA recommendations to improve public utility safety management policies and procedures and safety culture.
- Proceedings in which OSA participated and a description of OSA’s testimony in those proceedings. (Public Utilities Code §309.8(c))
- Sunsets the OSA on January 1, 2020. (Public Utilities Code §309.8(d))
- Requires the CPUC to appoint a chief internal auditor and requires the auditor to perform the following duties:
- Plan, initiate, and conduct audits of key financial, management, operational, and information technology functions within the CPUC to improve accountability and transparency.
- Report the audit findings and recommendations to a CPUC audit subcommittee.
- Comply with requirements for internal audits of public agencies. (Public Utilities Code §307.6)
This bill:
- Re-establishes the OSA as an independent office within the CPUC and specifies that the OSA’s director will be appointed by the Governor, subject to confirmation by the Senate.
- Requires the director of OSA to annually appear before the relevant legislative policy committees and report on the OSA’s activities.
- Requires the CPUC to adopt timelines for evaluating and implementing OSA recommendations.
- Requires the OSA to work with the CPUC’s internal auditor to ensure that the CPUC complies with requirements regarding timelines for evaluating and adopting OSA recommendations.
- Eliminates the January 1, 2020, sunset date for the OSA.
Background
A brief history of CPUC safety management. On September 9, 2010, a Pacific Gas and Electric Company (PG&E) natural gas transmission pipeline ruptured in San Bruno. Gas from the rupture ignited, resulting in eight deaths, injuries to 58 people, destruction of 38 homes, and damage to 70 additional homes. The San Bruno explosion led to multiple investigations and reports on safety issues associated with California’s natural gas infrastructure and oversight of the utilities that own and operate that infrastructure. A National Transportation Safety Board (NTSB) report stated that the probable cause of the explosion was a lack of quality assurance and pipeline integrity management from PG&E; however, the NTSB report also cited CPUC’s lack of effective oversight over natural gas utility operations as a contributing factor.
Concerns about natural gas safety oversight continued to surface following the 2015 natural gas leak at the Southern California Gas Company’s Aliso Canyon Natural Gas Storage Facility. Following the Aliso Canyon leak, the CPUC submitted a budget change proposal (BCP) for the 2016-17 state fiscal year to establish an independent Division of Safety Advocates within the CPUC, which would advocate for the prioritization and protection of Californians’ safety as a party to CPUC hearings. This BCP specifically cited the Aliso Canyon leak an example of a utility safety issue for which there was an absence of stakeholder groups advocating to prioritize Californians’ safety. The BCP stated the following:
“The leak at the Aliso Canyon Storage Facility cannot be considered an isolated incident. Rather, it highlights the much larger issue that much of California's gas and electric utility infrastructure was installed prior to 1970, and this aging infrastructure needs to be constantly monitored, inspected, and evaluated for potential threats. In 2015 alone, the CPUC investigated 522 separate gas and electric incidents resulting from this aging infrastructure. Utility requests for infrastructure upgrades and related maintenance, inspection, and monitoring are increasing rapidly. Such requests are considered in General Rate Case applications… There are no stakeholder groups that are solely dedicated to public safety that are willing to appear before the Commission and actively participate in relevant proceedings. The lack of such groups and the increasing number of incidents due to aging utility infrastructure compel the Commission to create a new Division of Safety Advocates within its own body to highlight safety.”
In 2017, the Legislature passed SB 62 (Hill, Chapter 421, Statutes of 2017), which established the OSA and provided the CPUC with funding to support the safety advocacy goals outlined in the CPUC’s 2016-17 BCP. Under existing law, the OSA is scheduled to sunset on January 1, 2020. This bill would clarify certain OSA duties and eliminate the existing sunset date for OSA.
How many independent offices are needed? Existing law does not explicitly establish the OSA as an independent office of the CPUC. This bill would re-establish the OSA as an independent office with a director appointed by the Governor and confirmed by the Senate. This bill also requires the director of OSA to appear annually before the relevant policy committees of the Legislature to report on OSA’s activities. This reporting requirement is similar to requirements established for the Office of the Ratepayer Advocate (ORA). The CPUC’s 2016-17 BCP envisioned that the Division of Safety Advocates would function in a manner similar to the ORA, which was established to advocate for “…the lowest possible rate for service consistent with reliable and safe service levels.” However, since the creation of the OSA, legislation has renamed the ORA as the Public Advocate’s Office (PAO). While existing law continues to require the PAO to advocate for lower rates, the renaming raises the question of whether the PAO will expand its mission to encompass advocacy beyond ratepayer savings, including utility safety. To the extent that PAO also advocates for utility safety, PAO and OSA may have overlapping advocacy roles.
Catastrophic wildfires and SB 901. Utility infrastructure has been associated with catastrophic fires in the past; however, catastrophic wildfires enhanced concerns related to electric infrastructure. In 2017, California experienced some of the largest and most destructive wildfires in its modern history. California Department of Fire and Forestry Protection (Cal FIRE) reports indicated that at least 18 of the 170 fires that formed the 2017 North Bay Fire Siege were caused by utility equipment. The 2017 Thomas Fire in Ventura and Santa Barbara Counties burned over 281,000 acres, destroying over 1,000 buildings and killing two people. The Thomas Fire also indirectly resulted in the deaths of 21 people who died in a debris flow created by heavy rains fell on the area burned by the fire. Cal FIRE reports also indicated that utility infrastructure was associated with the ignition of the Thomas Fire.
While the 2017 fires occurred, the CPUC issued a decision denying cost recovery for uninsured utility costs associated with 2007 fires in San Diego. As part of its decision, the CPUC urged the Legislature to consider issues of utility fault for wildfires associated with utility ignitions. In 2018, the Legislature passed SB 901 (Dodd, Chapter 626, Statutes of 2018), which established a number of wildfire prevention and mitigation requirements, including safety requirements that must be included in wildfire mitigation plans (WMPs).
CPUC’s 2019-20 OSA budget request. Following the passage of SB 901, the CPUC submitted a BCP to support utility safety and wildfire mitigation duties codified by the legislation. This BCP includes a request for four staff positions for the OSA. The CPUC’s BCP states that SB 901 significantly increases the OSA’s duties. In the BCP, the CPUC says the following. “SB 901 creates substantial new work for OSA. OSA staffing levels are currently insufficient to fulfill the duties required to participate in the WMP processes established by the bill. OSA requires additional staff to fulfill these new duties.“
The BCP indicates that eight of the 11 OSA positions approved by the Legislature in 2017 have been filled. The 2019-20 BCP also requests four positions in addition to the 11 positions previously authorized. The additional four positions are intended to support SB 901 implementation.
The CPUC can act on its own motion, but timeliness and consistency is an issue. The CPUC’s role in regulating utilities has evolved over time. Since its establishment as the railroad commission in 1911, the statutory and constitutional role of the CPUC as an active regulator has been affirmed. In 1940, the California Supreme Court noted that the CPUC has the authority to take action on its own accord in Sale v. Railroad Commission. In its decision, the Court stated, “…the railroad commission, unlike a court, may act sua sponte and is not dependent upon the appearance of a party to ‘invoke’ its jurisdiction.”
While an independent office can advocate for utility safety on behalf of Californians, this advocacy does not supplant the duty of the CPUC to exercise its authority to ensure that policies and procedures for utilities are safe. Existing law requires the CPUC to exercise its utility regulatory powers to adjust utility requirements whenever it finds existing utility practices to be unsafe. However, some CPUC decisions regarding utility safety indicate that the CPUC has taken a reactive approach in the past and focused on establishing requirements specific to individual utilities instead of establishing consistent requirements across utilities. For example, following San Diego’s Witch, Rice and Guejito fires, the CPUC adopted new vegetation management, clearance, ignition prevention, and facility inspection requirements for locations in southern. However, until recently, similar requirements did not apply to PG&E territory. Even as these requirements are applied to PG&E, they are adopted piecemeal through multiple decisions and resolutions at later dates.
This bill requires the CPUC to establish timelines for the evaluation and implementation of OSA recommendations. This bill also requires the OSA to work with the CPUC’s internal auditor to ensure that the CPUC complies with requirements regarding the timelines. These requirements can help build accountability for the timely adoption of appropriate recommendations from OSA.
Prior/Related Legislation
SB 901 (Dodd, Chapter 626, Statutes of 2018) established a number of utility safety requirements, including requirements for electric utilities to create and submit wildfire mitigation plans that identify mechanisms for preventing, combatting, and responding to wildfires within each utility service territory.
SB 19 (Hill, Chapter 421, Statutes of 2017) required the CPUC to appoint a chief internal auditor and specified the duties of the auditor.
SB 62 (Hill, Chapter 806, Statutes of 2016) codified the OSA within the CPUC until January 1, 2020, to advocate for the continuous, cost-effective improvement of the safety management and safety performance of public utilities.
SB 900 (Hill, Chapter 552, Statutes of 2014) required the CPUC to consider safety in electrical and gas general rate cases.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: No
SUPPORT:
Rural County Representatives of California
OPPOSITION:
None received
ARGUMENTS IN SUPPORT: According to the author:
“SB 199 clarifies the role of the OSA at the CPUC, and removes the program sunset currently in statute. The Legislature created OSA in 2016 under SB 62 (Hill). Since its creation in January 2017, OSA has provided valuable contributions at the CPUC advocating for improved utility safety and stronger CPUC safety oversight. During this time, California has experienced devastating loss through wildfire and mudslides, with utility infrastructure largely suspected to be a factor or cause. Extensive focus on utility safety and accountability has understandably resulted. The extension of OSA’s expertise, as proposed by SB 199, provides enormous value to these efforts to ensure its mission of improving “the safety management and safety performance of public utilities to prevent accidents, injuries, and to save lives” persists.”
-- END --
Bill Author
Bill Co-Author(s):