SB 548: Electricity: transmission facilities: inspection.
- Session Year: 2019-2020
- House: Senate
- Latest Version Date: 2019-02-22
|
Date
|
Status
|
|---|---|
| Sep 6, 2019 | Ordered to inactive file on request of Assembly Member Bonta. |
| Aug 15, 2019 | Read second time. Ordered to third reading. |
| Aug 14, 2019 | From committee: Do pass. (Ayes 18. Noes 0.) (August 14). |
| Jul 11, 2019 | From committee: Do pass and re-refer to Com. on APPR. with recommendation: To consent calendar. (Ayes 15. Noes 0.) (July 10). Re-referred to Com. on APPR. |
| Jun 24, 2019 | June 26 hearing postponed by committee. |
| May 24, 2019 | Referred to Com. on U. & E. |
| May 9, 2019 | In Assembly. Read first time. Held at Desk. |
| May 9, 2019 | Read third time. Passed. (Ayes 37. Noes 0.) Ordered to the Assembly. |
| May 7, 2019 | Read second time. Ordered to third reading. |
| May 6, 2019 | From committee: Be ordered to second reading pursuant to Senate Rule 28.8. |
| Apr 26, 2019 | Set for hearing May 6. |
| Apr 2, 2019 | From committee: Do pass and re-refer to Com. on APPR. (Ayes 13. Noes 0.) (April 2). Re-referred to Com. on APPR. |
| Mar 21, 2019 | Set for hearing April 2. |
| Mar 7, 2019 | Referred to Com. on E., U. & C. |
| Feb 25, 2019 | Read first time. |
| Feb 25, 2019 | From printer. May be acted upon on or after March 27. |
| Feb 22, 2019 | Introduced. To Com. on RLS. for assignment. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Aug 14, 2019 | Do pass. | Assembly Standing Committee on Appropriations |
Passed |
|
| Jul 10, 2019 | Do pass and be re-referred to the Committee on [Appropriations] with recommendation: To Consent Calendar | Assembly Standing Committee on Utilities and Energy |
Passed |
|
| May 9, 2019 | Senate 3rd Reading SB548 Hill | Senate Floor |
Passed |
|
| Apr 2, 2019 | Do pass, but first be re-referred to the Committee on [Appropriations] | Senate Standing Committee on Energy, Utilities and Communications |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
SENATE THIRD READING
STR Bill Id:SB 548
Author:(Hill)
As Introduced Ver:February 22, 2019
Majority vote
SUMMARY:
This bill requires the California Public Utilities Commission (CPUC) to establish a schedule of inspection of transmission facilities by electrical corporations (IOUs) of their transmission facilities.
COMMENTS:
There are three entities at the state and federal level that directly impact transmission lines – the Federal Energy Regulatory Commission (focused primarily on economics), the California Independent System Operation (primarily focused on markets and dispatch), and the CPUC. (The North American Electric Reliability Corporation is also involved but it sets operational standards related to reliability, not safety). Each of the three entities however give great deference to the transmission owner's maintenance plans and procedures. This bill requires the CPUC to take the helm and establish minimum requirements for transmission facility inspection cycles. These inspections are for facilities – i.e. the poles and circuits and towers that make up the transmission grid. These minimum requirements are currently absent from existing law or regulations, and are left to the utilities to establish at their discretion which has resulted in no clear, comprehensive maintenance or inspection requirements of transmission owners.
According to the Author:
This bill requires the CPUC to establish minimum timelines for electric transmission inspections. The CPUC adopted minimum timelines for distribution facility inspections in 2012, but did not extend these timelines to transmission facility inspections. As a result, utilities carry out transmission facility inspections when they deem necessary. Recent news reports signal utilities may go too long between inspections or overlook key equipment failures due to limitations of aerial patrols. The Camp Fire in Paradise last year points to this possibility. A faulty connector hook on a transmission tower is reported to have led to the blaze. Previous aerial inspections of the tower failed to identify this risk. This bill simply requires baseline standards for transmission facility inspections to be established, in order to help identify these risks sooner.
Arguments in Support:
The Utility Reform Network (TURN) writes in support of this bill that the CPUC has established a clear inspection schedule for distribution facilities which must be inspected once every three or five years, depending on if the facilities are in an urban or rural location. NO schedule exists for transmission facilities which has led to utilities carrying out transmission facility inspections when they deem necessary. With the growing threat of wildfires throughout the state, it is important that utilities not go too long between Inspections.
Arguments in Opposition:
There is no opposition to this bill.
FISCAL COMMENTS:
According to the Assembly Appropriations Committee, there are minor costs to the CPUC, which could absorb the work required by this bill as part of its considerable wildfire and safety activities and proceedings.
VOTES:
SENATE FLOOR: 38-0-0
YES: Allen, Archuleta, Atkins, Bates, Beall, Borgeas, Bradford, Caballero, Chang, Dodd, Durazo, Galgiani, Glazer, Grove, Hertzberg, Hill, Hueso, Hurtado, Jackson, Jones, Leyva, McGuire, Mitchell, Monning, Moorlach, Morrell, Nielsen, Pan, Portantino, Roth, Rubio, Skinner, Stern, Stone, Umberg, Wieckowski, Wiener, Wilk
ASM UTILITIES AND ENERGY: 15-0-0
YES: Holden, Patterson, Burke, Carrillo, Chen, Cunningham, Eggman, Cristina Garcia, Eduardo Garcia, Mayes, Muratsuchi, Quirk, Reyes, Santiago, Ting
ASM APPROPRIATIONS: 18-0-0
YES: Gonzalez, Bigelow, Bloom, Bonta, Brough, Calderon, Carrillo, Chau, Diep, Eggman, Fong, Gabriel, Eduardo Garcia, Maienschein, Obernolte, Petrie-Norris, Quirk, Robert Rivas
UPDATED:
VERSION: February 22, 2019
CONSULTANT: Kellie Smith / U. & E. / (916) 319-2083 FN: 0001394
Date of Hearing: August 14, 2019
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Lorena Gonzalez, Chair
SBPCA Bill Id:SB 548
Author:(Hill) – As Introduced Ver:February 22, 2019
Policy Committee: | Utilities and Energy | Vote: | 15 - 0 |
|
| ||
|
|
Urgency: No State Mandated Local Program: Yes Reimbursable: No
SUMMARY:
This bill requires the California Public Utilities Commission (CPUC) to adopt a new, or revise an existing, general order (GO) to establish a schedule of inspection by electrical corporations of their transmission facilities.
FISCAL EFFECT:
Minor costs to the CPUC, which could absorb the work required by this bill as part of its considerable wildfire and safety activities and proceedings.
COMMENTS:
Background and Purpose. The CPUC issues GOs to the entities it regulates to specify requirements and procedures the entities are to follow. One such GO is GO 165, which governs each electrical utility’s electrical equipment, including transmission lines—that is, higher voltage lines that carry electricity across long distances—and distribution lines—that is, lower voltage lines that distribute electricity in a local area.
Following a particularly conflagrant fire season in Southern California, the CPUC updated GO 165 to make additional, specific requirements regarding utility inspection of its distribution lines. However, the CPUC did not make similar requirements of utility inspection of its transmission lines.
The fire seasons of 2017 and 2018 were especially destructive, and deadly. Investigations into some of the largest and most harmful blazes continue. Nonetheless, there is suspicion at least one of the fires was started by a transmission line. Given the state’s fire risk, and the thousands of miles of transmission lines in the state, it makes sense to direct the CPUC to require electric utilities to inspect their transmission lines and to provide parameters for doing so.
Analysis Prepared by: Jay Dickenson / APPR. / (916) 319-2081
Date of Hearing: July 10, 2019
ASSEMBLY COMMITTEE ON UTILITIES AND ENERGY
Chris Holden, Chair
SBPCA Bill Id:SB 548
Author:(Hill) – As Introduced Ver:February 22, 2019
SENATE VOTE: 38-0
SUBJECT: Electricity: transmission facilities: inspection
SUMMARY: Requires the California Public Utilities Commission (CPUC) to establish a schedule of inspection of transmission facilities by electrical corporations (IOUs) of their transmission facilities
EXISTING LAW:
- Requires the California Independent System Operator (CAISO) to adopt inspection, maintenance, repair, and replacement standards for transmission facilities under its control which consider cost, local geography, weather, applicable codes, national electric industry practices, sound engineering judgement, and experience. (Public Utilities Code § 348)
- Defines electrical corporation as every corporation or person owning, controlling, operating, or managing any electric plant for compensation within this state, except where electricity is generated on or distributed by the producer through private property solely for its own use or the use of its tenants and not for sale or transmission to others. (Public Utilities Code § 218)
- Defines electric plant as including all real estate, fixtures and personal property owned, controlled, operated, or managed in connection with or to facilitate the production, generation, transmission, delivery, or furnishing of electricity for light, heat, or power, and all conduits, ducts, or other devices, materials, apparatus, or property for containing, holding, or carrying conductors used or to be used for the transmission of electricity for light, heat, or power. (Public Utilities Code § 217)
- Requires each IOU to prepare and follow procedures for conducting inspection and maintenance activities for transmission lines that come within the CPUC’s jurisdiciton, and maintain records of inspection and maintenance activities. (CPUC General Order 165)
FISCAL EFFECT: According to the Senate Appropriations Committee, this bill was not heard per rule 28.8 because it was found to cause no significant reduction in revenues, or additional state costs are not significant and do not require the appropriation of additional state funds.
BACKGROUND:
Transmission vs. Distribution. Generally, electricity is created at generation facilities across the state. Transformers at substations either step power up to a higher voltage for transmission or a lower voltage for distribution. Transmission lines generally carry electricity for longer distances at higher voltages. Distribution lines generally carry power locally at a lower voltage. Both transmission and distribution facilities have safety risks that must be mitigated. While the higher voltage of transmission lines and their role in transporting energy over long distances through challenging terrain can pose special safety management challenges, electrical corporations typically own and maintain more distribution lines than transmission lines.
A review of data published by the California Energy Commission reflects more than 35,000 miles of transmission lines in the state which are owned by investor-owned and publicly-owned electric utilities, private transmission owners, and federal authorities such as the Western Area Power Administration. A map of California’s major transmission lines is available at the California Energy Commission at: https://ww2.energy.ca.gov/maps/infrastructure/transmission_lines.html
COMMENTS:
- Author’s Statement. SB 548 requires the CPUC to establish minimum timelines for electric transmission inspections. The CPUC adopted minimum timelines for distribution facility inspections in 2012, but did not extend these timelines to transmission facility inspections. As a result, utilities carry out transmission facility inspections when they deem necessary. Recent news reports signal utilities may go too long between inspections or overlook key equipment failures due to limitations of aerial patrols. The Camp Fire in Paradise last year points to this possibility. A faulty connector hook on a transmission tower is reported to have led to the blaze. Previous aerial inspections of the tower failed to identify this risk. SB 548 simply requires baseline standards for transmission facility inspections to be established, in order to help identify these risks sooner.
- Who’s On First? There are three entities at the state and federal level that directly impact transmission lines – the Federal Energy Regulatory Commission (focused primarily on economics), the California Independent System Operation (primarily focused on markets and dispatch), and the CPUC. (The North American Electric Reliability Corporation is also involved but it sets operational standards related to reliability, not safety). Each of the three entities however give great deference to the transmission owner’s maintenance plans and procedures. This bill requires the CPUC to take the helm and establish minimum requirements for transmission facility inspection cycles. These inspections are for facilities – i.e. the poles and circuits and towers that make up the transmission grid. These minimum requirements are currently absent from existing law or regulations, and are left to the utilities to establish at their discretion which has resulted in no clear, comprehensive maintenance or inspection requirements of transmission owners.
According to the Senate Appropriations Committee, this bill was not heard per rule 28.8 because it was found to cause no significant reduction in revenues, or additional state costs are not significant and do not require the appropriation of additional state funds.
REGISTERED SUPPORT / OPPOSITION:
Support
Sierra Club
Sierra Club California
The Utility Reform Network
Opposition
None on file.
Analysis Prepared by: Kellie Smith / U. & E. /
Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 548 |
THIRD READING
Bill No: SB 548
Introduced: 2/22/19
SENATE ENERGY, U. & C. COMMITTEE: 13-0, 4/2/19
AYES: Hueso, Moorlach, Bradford, Chang, Dodd, Hertzberg, Hill, McGuire, Rubio, Skinner, Stern, Stone, Wiener
SENATE APPROPRIATIONS COMMITTEE: Senate Rule 28.8
SUBJECT: Electricity: transmission facilities: inspection
DIGEST:
This bill requires the California Public Utilities Commission (CPUC) to establish a schedule for electrical corporations to conduct transmission facility inspections.
Existing law:
- Requires the CPUC to establish rules for a public utility and revise those requirements through an order or rule whenever the CPUC, after a hearing, finds that existing rules, practices, equipment, appliances, facilities or service of any public utility or manufacturing, distribution, transmission, storage or supply methods employed by the public utility are unjust, unreasonable, unsafe, improper, inadequate, or insufficient. (Public Utilities Code §761)
- Requires the CPUC to adopt inspection, maintenance, repair, and replacement standards and must consider adopting rules to address the physical security risks to the distribution systems of electrical corporations. The standards or rules must be prescriptive and/or performance based and may be based on risk management, for each type of distribution equipment or facility. The standards or rules must provide for high-quality, safe, and reliable service. When setting these standards or rules, the CPUC shall consider the following: cost, local geography and weather, applicable codes, potential physical security risks, national electric industry practices, sound engineering judgment, and experience. The CPUC shall also adopt standards for operation, reliability, and safety during periods of emergency and disaster. (Public Utilities Code §364)
- Requires the California Independent System Operator (CAISO) to adopt inspection, maintenance, repair, and replacement standards for transmission facilities under its control. In adopting these standards, the CAISO must consider cost, local geography, weather, applicable codes, national electric industry practices, sound engineering judgement, and experience. The CAISO must also require each transmission facility owner or operator to report annually on its compliance with the standard, and that report must be available to the public. (Public Utilities Code §348)
This bill requires the CPUC to establish a schedule for electrical corporations to conduct transmission facility inspections. This schedule may be adopted through a new order or revisions to an existing order.
Background
Transmission vs. Distribution. Generally, electricity is created at generation facilities across the state. Transformers at substations either step power up to a higher voltage for transmission or a lower voltage for distribution. Transmission lines carry electricity for longer distances at higher voltages. Distribution lines generally carry power locally at a lower voltage. Both transmission and distribution facilities have safety risks that must be mitigated. While the higher voltage of transmission lines and their role in transporting energy over long distances through challenging terrain can pose special safety management challenges, electrical corporations typically own and maintain more distribution lines than transmission lines. For example, Pacific Gas and Electric (PG&E) is responsible for 106,681 circuit miles of distribution lines and 18,466 circuit miles of transmission lines.
Transmission facility safety: Who’s on first? Under existing law, the CPUC is required to develop inspection, maintenance, repair, and replacement standards for electrical corporations’ distribution facilities. Existing law also requires the CAISO to adopt inspection, maintenance, repair, and replacement standards for transmission facilities under its control. However, the CAISO’s role in transmission maintenance is largely focused on ensuring reliability; the statute establishing its authority (AB 1890, Brulte, Chapter 854, Statutes of 1996) states that the CAISO’s authority to adopt transmission maintenance standards is intended to reduce the potential for outages and encourage participation in the operation of the CAISO. The CAISO’s transmission maintenance program consists of the following:
- Availability Measures: measures that track the availability of utility transmission facilities over time.
- Utility-Specific Maintenance Practices: utilities submit plans to the CAISO, and the CAISO reviews them to ensure that they are consistent with federal reliability standards and good utility practice.
- Maintenance Activity Review: the CAISO conducts a review of each utility’s performance activities, including a review of a sample of the utility’s maintenance records and physical site inspections of a subset of that sample.
While the CAISO’s transmission maintenance role primarily emphasizes reliability, the CPUC has broader statutory authority to establish utility safety requirements. The CPUC has more strict regulatory authority over public utilities, and existing law requires the CPUC to establish requirements for public utilities and revise those requirements whenever it determines that existing rules and practices are unjust, unreasonable, unsafe, improper, inadequate, or insufficient. The CPUC’s authority to regulate public utilities extends beyond state law; existing federal law (47 United States Code §§224 and 253) affirm the CPUC’s authority to regulate poles, ducts, conduits and rights of way as well as the CPUC’s authority to adopt regulations to protect public safety and welfare. State legislation has added additional specification to CPUC’s utility safety role, including requirements for wildfire mitigation. This bill further specifies that CPUC’s regulatory duties must include establishing a schedule for electrical corporation transmission inspection.
CPUC General Order (GO) 165. The CPUC first established transmission and distribution inspection requirements by adopting GO 165 in 1997 through a commission decision (D. 97-03-070). Since the establishment of the initial requirements, the CPUC has revised GO 165 twice. The most recent revision occurred in 2012, when the CPUC revised the inspection requirements in response to findings that the 2007 Witch, Rice, and Guejito fires in San Diego were caused by a combination of electric utility and telecommunications lines. In its 2012 revisions to GO 165, the CPUC expanded distribution infrastructure maintenance requirements, including establishing reporting requirements and minimum timeless for inspecting all distribution equipment. However, these amendments to GO 165 did not extend these minimum inspection timeline requirements to transmission infrastructure. Instead, GO 165 required electrical corporations to prepare and follow procedures for transmission facility maintenance and inspection.
Catastrophic wildfires of 2017 and 2018. In the past two years, California has experienced several of its largest and most destructive wildfires in the state’s modern history. Utility infrastructure has been the ignition point for a number of these fires. The Thomas Fire in Ventura and Santa Barbara Counties burned over 281,000 acres, destroying over 1,000 buildings and killing two people. The Thomas Fire also indirectly resulted in the deaths of 21 people who died in a debris flow created by heavy rains fell on the area burned by the fire. California Department of Forestry and Fire Protection (CAL FIRE) reports indicated that utility infrastructure was associated with the ignition of the Thomas Fire. Reports by CAL FIRE also indicated that at least 18 of the 170 fires that formed the 2017 North Bay Fire Siege were caused by PG&E equipment. However, CAL FIRE reports indicate that that the deadliest of the North Bay fires, the Tubbs Fire, was caused by a private electrical system, which was not attributed to PG&E.
While California’s 2017 fire season was historically destructive, the state’s 2018 fire season was even larger and more destructive. The Woolsey Fire in Los Angeles and Ventura counties resulted in the destruction of 1500 structures, and three deaths. The Camp Fire in Butte County became the deadliest fire in the state’s history, destroying over 18,800 buildings and killing 85 people. The Mendocino Complex fire, the largest fire in California history, crossed into four counties, destroyed 280 buildings, and killed one firefighter. These fires are still under investigation, and CAL FIRE has not determined causes of ignition.
Several investigative reports have indicated that PG&E may have delayed repairs to its Caribou-Palermo transmission line, which runs in the North Valley area of PG&E territory. Potential upgrades to the line have been noted in CPUC and CAISO documents since 2010; however, some of these improvements may have been part of a long-term reliability upgrade plan known as the South of Palermo Reinforcement Project.
Reports on potential delayed repairs to PG&E infrastructure also indicate that a timeline for inspections may be warranted. The CAISO’s transmission upgrade observations are largely focused on the need to prevent outages, and reports indicate that CPUC responded to questions from investigative journalists about transmission upgrade delays by noting that an inspection time frame for transmission infrastructure is not required by law. This bill requires the CPUC to adopt, through a new or existing order, a timeline for electrical corporations to conduct transmission facility inspections. This requirement is consistent with CPUC’s role as a regulator with broad authority to establish safety requirements for utilities and it requires the CPUC to exercise that role for transmission inspections.
Related/Prior Legislation
SB 247 (Dodd, 2019) requires CAL FIRE to generate and maintain a “trim list”, then audit the compliance of the utilities to that trim list. The bill also requires the CPUC to establish a two-way balancing account for each electrical corporation for all costs incurred by the corporation for vegetation management. The bill is pending in the Senate Committee on Appropriations.
SB 291 (Hill, Chapter 601, Statutes of 2013) required the CPUC to develop and implement a safety enforcement program for gas and electrical corporations by July 1, 2014, and January 1, 2015, respectively.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
Sierra Club California
None received
ARGUMENTS IN SUPPORT: According to the author:
SB 548 requires the CPUC to establish minimum timelines for electric transmission inspections. The CPUC adopted minimum timelines for distribution facility inspections in 2012, but did not extend these timelines to transmission facility inspections. As a result, utilities carry out transmission facility inspections when they deem necessary.
Recent news reports signal utilities may go too long between inspections or overlook key equipment failures due to limitations of aerial patrols. The Camp Fire in Paradise last year points to this possibility. A faulty connector hook on a transmission tower is suspected to have led to the blaze. Previous aerial inspections of the tower failed to identify this risk. SB 548 simply requires baseline standards for transmission facility inspections to be established, in order to help identify these risks sooner.
Prepared by: Sarah Smith / E., U., & C. / (916) 651-4107
5/8/19 10:51:30
**** END ****
SENATE COMMITTEE ON ENERGY, UTILITIES AND COMMUNICATIONS
Senator Ben Hueso, Chair
2019 - 2020 Regular
Bill No: SB 548 Hearing Date: 4/2/2019
Author: | Hill | ||
Version: | 2/22/2019 As Introduced | ||
Urgency: | No | Fiscal: | Yes |
Consultant: | Sarah Smith | ||
SUBJECT: Electricity: transmission facilities: inspection
DIGEST: This bill requires the California Public Utilities Commission (CPUC) to establish a schedule for electrical corporations to conduct transmission facility inspections.
ANALYSIS:
Existing law:
- Requires the CPUC to establish rules for a public utility and revise those requirements through an order or rule whenever the CPUC, after a hearing, finds that existing rules, practices, equipment, appliances, facilities or service of any public utility or manufacturing, distribution, transmission, storage or supply methods employed by the public utility are unjust, unreasonable, unsafe, improper, inadequate, or insufficient. (Public Utilities Code §761)
- Requires the CPUC to adopt inspection, maintenance, repair, and replacement standards and must consider adopting rules to address the physical security risks to the distribution systems of electrical corporations. The standards or rules must be prescriptive and/or performance based and may be based on risk management, for each type of distribution equipment or facility. The standards or rules must provide for high-quality, safe, and reliable service. When setting these standards or rules, the CPUC shall consider the following: cost, local geography and weather, applicable codes, potential physical security risks, national electric industry practices, sound engineering judgment, and experience. The CPUC shall also adopt standards for operation, reliability, and safety during periods of emergency and disaster. (Public Utilities Code §364)
- Requires the California Independent System Operator (CAISO) to adopt inspection, maintenance, repair, and replacement standards for transmission facilities under its control. In adopting these standards, the CAISO must consider cost, local geography, weather, applicable codes, national electric industry practices, sound engineering judgement, and experience. The CAISO must also require each transmission facility owner or operator to report annually on its compliance with the standard, and that report must be available to the public. (Public Utilities Code §348)
This bill requires the CPUC to establish a schedule for electrical corporations to conduct transmission facility inspections. This schedule may be adopted through a new order or revisions to an existing order.
Background
Transmission vs. Distribution. Generally, electricity is created at generation facilities across the state. Transformers at substations either step power up to a higher voltage for transmission or a lower voltage for distribution. Transmission lines generally carry electricity for longer distances at higher voltages. Distribution lines generally carry power locally at a lower voltage. Both transmission and distribution facilities have safety risks that must be mitigated. While the higher voltage of transmission lines and their role in transporting energy over long distances through challenging terrain can pose special safety management challenges, electrical corporations typically own and maintain more distribution lines than transmission lines. For example, Pacific Gas and Electric (PG&E) is responsible for 106,681 circuit miles of distribution lines and 18,466 circuit miles of transmission lines.
Transmission Facility Safety: Who’s on first? Under existing law, the CPUC is required to develop inspection, maintenance, repair, and replacement standards for electrical corporations’ distribution facilities. Existing law also requires the CAISO to adopt inspection, maintenance, repair, and replacement standards for transmission facilities under its control. However, the CAISO’s role in transmission maintenance is largely focused on ensuring reliability; the statute establishing its authority (AB 1890, Brulte, Chapter 854, Statutes of 1996) states that the CAISO’s authority to adopt transmission maintenance standards is intended to reduce the potential for outages and encourage participation in the operation of the CAISO. The CAISO’s transmission maintenance program consists of the following:
- Availability Measures: measures that track the availability of utility transmission facilities over time.
- Utility-Specific Maintenance Practices: utilities submit plans to the CAISO, and the CAISO reviews them to ensure that they are consistent with federal reliability standards and good utility practice.
- Maintenance Activity Review: the CAISO conducts a review of each utility’s performance activities, including a review of a sample of the utility’s maintenance records and physical site inspections of a subset of that sample.
While the CAISO’s transmission maintenance role primarily emphasizes reliability, the CPUC has broader statutory authority to establish utility safety requirements. The CPUC has more strict regulatory authority over public utilities, and existing law requires the CPUC to establish requirements for public utilities and revise those requirements whenever it determines that existing rules and practices are unjust, unreasonable, unsafe, improper, inadequate, or insufficient. The CPUC’s authority to regulate public utilities extends beyond state law; existing federal law (47 United States Code §§224 and 253) affirm the CPUC’s authority to regulate poles, ducts, conduits and rights of way as well as the CPUC’s authority to adopt regulations to protect public safety and welfare. State legislation has added additional specification to CPUC’s utility safety role, including requirements for wildfire mitigation. This bill further specifies that CPUC’s regulatory duties must include establishing a schedule for electrical corporation transmission inspection.
CPUC General Order (GO) 165. The CPUC first established transmission and distribution inspection requirements by adopting GO 165 in 1997 through a commission decision (D. 97-03-070). Since the establishment of the initial requirements, the CPUC has revised GO 165 twice. The most recent revision occurred in 2012, when the CPUC revised the inspection requirements in response to findings that the 2007 Witch, Rice, and Guejito fires in San Diego were caused by a combination of electric utility and telecommunications lines. In its 2012 revisions to GO 165, the CPUC expanded distribution infrastructure maintenance requirements, including establishing reporting requirements and minimum timeless for inspecting all distribution equipment. However, these amendments to GO 165 did not extend these minimum inspection timeline requirements to transmission infrastructure. Instead, GO 165 required electrical corporations to prepare and follow procedures for transmission facility maintenance and inspection.
Catastrophic wildfires of 2017 and 2018. In the past two years, California has experienced several of its largest and most destructive wildfires in the state’s modern history. Utility infrastructure has been the ignition point for a number of these fires. The Thomas Fire in Ventura and Santa Barbara Counties burned over 281,000 acres, destroying over 1,000 buildings and killing two people. The Thomas Fire also indirectly resulted in the deaths of 21 people who died in a debris flow created by heavy rains fell on the area burned by the fire. CalFire reports indicated that utility infrastructure was associated with the ignition of the Thomas Fire. Reports by the California Department of Fire and Forestry Protection (CalFire) also indicated that at least 18 of the 170 fires that formed the 2017 North Bay Fire Siege were caused by Pacific, Gas & Electric (PG&E) equipment. However, CalFire reports indicate that that the deadliest of the North Bay fires, the Tubbs Fire, was caused by a private electrical system, which was not attributed to PG&E.
While California’s 2017 fire season was historically destructive, the state’s 2018 fire season was even larger and more destructive. The Woolsey Fire in Los Angeles and Ventura counties resulted in the destruction of 1500 structures, and three deaths. The Camp Fire in Butte County became the deadliest fire in the state’s history, destroying over 18,800 buildings and killing 85 people. The Mendocino Complex fire, the largest fire in California history, crossed into four counties, destroyed 280 buildings, and killed one firefighter. These fires are still under investigation, and CalFire has not determined causes of ignition.
Several investigative reports have indicated that PG&E may have delayed repairs to its Caribou-Palermo transmission line, which runs in the North Valley area of PG&E territory. Upgrades to the line have been noted in CPUC and CAISO documents since 2010; however, some of these improvements may have been part of a long-term reliability upgrade plan known as the South of Palermo Reinforcement Project.
Reports on potential delayed repairs to PG&E infrastructure also indicate that a timeline for inspections may be warranted. The CAISO’s transmission upgrade observations are largely focused on the need to prevent outages, and reports indicate that CPUC responded to questions from investigative journalists about transmission upgrade delays by noting that an inspection time frame for transmission infrastructure is not required by law. This bill would require the CPUC to adopt, through a new or existing order, a timeline for electrical corporations to conduct transmission facility inspections. This requirement is consistent with CPUC’s role as a regulator with broad authority to establish safety requirements for utilities and it requires the CPUC to exercise that role for transmission inspections.
Prior/Related Legislation
SB 247 (Dodd, 2019) requires CalFire to generate and maintain a “trim list”, then audit the compliance of the utilities to that trim list. The bill also requires the CPUC to establish a two-way balancing account for each electrical corporation for all costs incurred by the corporation for vegetation management. The bill is pending in the Senate Committee on Energy, Utilities and Communications.
SB 291 (Hill, Chapter 601, Statutes of 2013) required the CPUC to develop and implement a safety enforcement program for gas and electrical corporations by July 1, 2014, and January 1, 2015, respectively.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
SUPPORT:
Sierra Club California
OPPOSITION:
None received
ARGUMENTS IN SUPPORT: According to the author:
“SB 548 requires the CPUC to establish minimum timelines for electric transmission inspections. The CPUC adopted minimum timelines for distribution facility inspections in 2012, but did not extend these timelines to transmission facility inspections. As a result, utilities carry out transmission facility inspections when they deem necessary.
Recent news reports signal utilities may go too long between inspections or overlook key equipment failures due to limitations of aerial patrols. The Camp Fire in Paradise last year points to this possibility. A faulty connector hook on a transmission tower is suspected to have led to the blaze. Previous aerial inspections of the tower failed to identify this risk. SB 548 simply requires baseline standards for transmission facility inspections to be established, in order to help identify these risks sooner.”
-- END --
Bill Author
Bill Co-Author(s):