| Oct 2, 2019 | Chaptered by Secretary of State. Chapter 409, Statutes of 2019. |
| Oct 2, 2019 | Approved by the Governor. |
| Sep 20, 2019 | Enrolled and presented to the Governor at 10 a.m. |
| Sep 13, 2019 | Assembly amendments concurred in. (Ayes 39. Noes 1.) Ordered to engrossing and enrolling. |
| Sep 12, 2019 | From committee: That the Assembly amendments be concurred in. (Ayes 11. Noes 0.) |
| Sep 11, 2019 | Set for hearing September 12. |
| Sep 11, 2019 | From committee: Be re-referred to Com. on E., U. & C. pursuant to Senate Rule 29.10(d). (Ayes 5. Noes 0.) Re-referred to Com. on E., U. & C. |
| Sep 11, 2019 | Re-referred to Com. on RLS. pursuant to Senate Rule 29.10(d). |
| Sep 10, 2019 | In Senate. Concurrence in Assembly amendments pending. |
| Sep 10, 2019 | Read third time. Passed. Ordered to the Senate. |
| Sep 6, 2019 | Ordered to third reading. |
| Aug 22, 2019 | Read second time. Ordered to third reading. |
| Aug 21, 2019 | From committee: Do pass. (Ayes 17. Noes 0.) (August 21). |
| Aug 13, 2019 | Read second time and amended. Re-referred to Com. on APPR. |
| Aug 12, 2019 | (Received at desk July 17 pursuant to JR 61(a)(10)). |
| May 30, 2019 | Referred to Com. on U. & E. |
| May 22, 2019 | In Assembly. Read first time. Held at Desk. |
| May 21, 2019 | Read third time. Passed. (Ayes 33. Noes 3.) Ordered to the Assembly. |
| May 16, 2019 | Read second time. Ordered to third reading. |
| May 10, 2019 | Set for hearing May 16. |
| May 6, 2019 | May 6 hearing: Placed on APPR. suspense file. |
| Apr 30, 2019 | Set for hearing May 6. |
| Apr 24, 2019 | From committee: Do pass and re-refer to Com. on APPR. (Ayes 12. Noes 1.) (April 24). Re-referred to Com. on APPR. |
| Apr 3, 2019 | Set for hearing April 24. |
| Apr 2, 2019 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on E., U. & C. |
| Mar 7, 2019 | Referred to Com. on E., U. & C. |
| Feb 25, 2019 | Read first time. |
| Feb 25, 2019 | From printer. May be acted upon on or after March 27. |
| Feb 22, 2019 | Introduced. To Com. on RLS. for assignment. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Sep 13, 2019 | Unfinished Business SB550 Hill et al. Concurrence | Senate Floor |
Passed |
|
| Sep 12, 2019 | That the Assembly amendments be concurred in | Senate Standing Committee on Energy, Utilities and Communications |
Passed |
|
| Sep 10, 2019 | SB 550 Hill Senate Third Reading By Holden | Assembly Floor |
Passed |
|
| Aug 21, 2019 | Do pass. | Assembly Standing Committee on Appropriations |
Passed |
|
| Jul 10, 2019 | Do pass as amended and be re-referred to the Committee on [Appropriations] | Assembly Standing Committee on Utilities and Energy |
Passed |
|
| May 21, 2019 | Senate 3rd Reading SB550 Hill | Senate Floor |
Passed |
|
| May 16, 2019 | Do pass | Senate Standing Committee on Appropriations |
Passed |
|
| May 6, 2019 | Placed on suspense file | Senate Standing Committee on Appropriations |
Passed |
|
| Apr 24, 2019 | Do pass, but first be re-referred to the Committee on [Appropriations] | Senate Standing Committee on Energy, Utilities and Communications |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 550 |
UNFINISHED BUSINESS
Bill No: SB 550
Amended: 9/6/19
SENATE ENERGY, U. & C. COMMITTEE: 12-1, 4/24/19
AYES: Hueso, Bradford, Chang, Dodd, Hertzberg, Hill, McGuire, Rubio, Skinner, Stern, Stone, Wiener
NOES: Moorlach
SENATE APPROPRIATIONS COMMITTEE: 4-1, 5/16/19
AYES: Portantino, Bradford, Hill, Wieckowski
NOES: Jones
NO VOTE RECORDED: Bates
SENATE FLOOR: 34-3, 5/21/19
AYES: Allen, Archuleta, Atkins, Beall, Borgeas, Bradford, Caballero, Chang, Dodd, Durazo, Galgiani, Glazer, Grove, Hertzberg, Hill, Hueso, Hurtado, Jackson, Leyva, McGuire, Mitchell, Monning, Nielsen, Pan, Portantino, Roth, Rubio, Skinner, Stern, Stone, Umberg, Wieckowski, Wiener, Wilk
NOES: Jones, Moorlach, Morrell
NO VOTE RECORDED: Bates
SENATE ENERGY, U. & C. COMMITTEE: 11-0, 9/12/19 (Pursuant to Senate Rule 29.10)
AYES: Hueso, Moorlach, Bradford, Chang, Dodd, Hill, McGuire, Rubio, Stern, Stone, Wiener
NO VOTE RECORDED: Hertzberg, Skinner
ASSEMBLY FLOOR: 79-0, 9/10/19 - See last page for vote
SUBJECT: Public utilities: merger, acquisition, or control of electrical or gas corporations
DIGEST:
This bill requires the California Public Utilities Commission (CPUC) to review specified safety elements for any proposed merger, acquisition or change in control of an electrical or gas investor owned utility (IOU) and conditions approval on a finding that, on balance, the transaction is in the public interest relative to those safety elements. This bill also clarifies the reviews required by the CPUC for any other asset transactions between a public utility and any other person or entity whether public or private.
Assembly Amendments
authorize the CPUC to implement the safety review requirements by July 1, 2021, set the threshold for the safety review to an entity with gross annual revenues to $400 million, amend language adopted in AB 1054 related to the change of control provisions and the review needed when assets of an IOU are transferred to a public entity, and make other changes.
Existing law:
- Establishes the CPUC has regulatory authority over public utilities, including electrical corporations and gas corporations. (California Constitution Article 12)
- Prohibits a public utility, other than certain common carriers, from selling, leasing, assigning, mortgaging, or otherwise disposing of, or encumbering its assets that are necessary or useful in the performance of its duties to the public by any means with any other public utility, unless the public utility has secured an order from the CPUC to do so for a qualified transaction above $5 million or an approval from the CPUC through the filing of an advice letter for a qualified transaction at or below $5 million. (Public Utilities Code §851)
- Prohibits a person or corporation, including a public entity, from merging, acquiring, or controlling, as described, either directly or indirectly, any public utility organized and doing business in this state without first securing authorization to do so from the CPUC. Before authorizing the merger, acquisition, or control of any electrical, gas, or telephone corporation organized and doing business in this state, where any of the entities that are parties to the proposed transaction has gross annual California revenues exceeding $500 million, existing law requires the CPUC to consider specified criteria and to find that the merger, acquisition, or control proposal meets certain requirements and is in the public interest, as specified. (Public Utilities Code §854)
- Defines a change of control to include the voluntary or involuntary change in ownership of assets from an electrical or gas corporation to a public entity. Requires specified workforce protections when a change of control occurs. (Public Utilities Code §854.2)
This bill:
- Eliminates the requirements sales, leases, assignments, mortgages, or other transactions be with another public utility to be subject to those conditions on approval.
- Requires explicitly the CPUC to approve or reject any voluntary or involuntary change in ownership of assets from an electrical or gas corporation to ownership by a public entity and would require the CPUC to determine whether that transaction is fair and reasonable to the affected public utility employees as part of that review.
- Requires the CPUC, before authorizing a merger, acquisition, or change in control of an electrical or gas corporation, where an entity to the proposed transaction has gross annual California revenues exceeding $400 million , to additionally consider specified elements relating to the safety activities of an electrical or gas corporation, including a nonpunitive system for reporting potential safety incidents to the CPUC, and find, on balance, that the proposal is in the public interest.
- Authorizes the CPUC to delay the requirement that the CPUC consider these specified elements and find, on balance, that the proposal is in the public interest, until July 1, 2021, or until the CPUC adopts rules implementing this requirement, whichever is earlier.
- Prohibits subjecting an employee of, or the employee of a contractor performing work for, the electrical or gas corporation to demotion, discharge, or any other form of retaliation or discrimination for participating in the nonpunitive system for reporting potential safety incidents.
- Eliminates the requirements for these reviews for a change in ownership in the assets of an electrical or gas corporation to ownership by a public entity.
Background
Pacific Gas & Electric (PG&E) files for Chapter 11 Bankruptcy protection. On January 29, 2019, PG&E Corp., the holding company of the state’s largest utility, voluntarily filed for bankruptcy protection under Chapter 11 of the United States Bankruptcy Code. PG&E filed their case in the Northern California District Court San Francisco Division (Case No. 19-30088-DM). The case has been assigned to the same judge, Honorable Dennis Montali, who handled PG&E’s previous reorganization bankruptcy case in connection with the 2001 energy crisis. According to PG&E’s first day filings, in a declaration filed by PG&E’s Senior Vice President and Chief Financial Officer Jason Wells, PG&E’s decision to seek relief under Chapter 11 “were necessitated by a confluence of factors resulting from the catastrophic and tragic wildfires that occurred in Northern California in 2017 and 2018, and PG&E’s potential liabilities arising therefrom.” The declaration specifically cites PG&E’s potential liability related to the fires could exceed $30 billion. PG&E’s decision to voluntarily file for bankruptcy protection has raised numerous questions about the process entailed under a Chapter 11 reorganization and the potential implications for the numerous stakeholders that could be affected, including wildfire victims, ratepayers, the utility workforce, energy and other suppliers, local governments, and many others. The bankruptcy filing and wildfire incidents have also increased interest by some local governments, including the City and County of San Francisco, as a possible opportunity to purchase part of the existing PG&E distribution system in an effort to municipalize a portion of the service territory.
CPUC approval needed. CPUC must review any transactions involving the selling, buying, merging, or otherwise changing control of a public utility’s assets. Section 854 of the Public Utilities Code establishes the criteria by which the CPUC must review any IOU merger, acquisition, or sale. Among the criteria are a CPUC determination that the merger or acquisition will provide long-term economic benefits to ratepayers, does not adversely affect competition, be beneficial on an overall basis to the state and local economies, and others. Interestingly, the criteria in Section 854 (b) and (c) were added in 1989 by the State Legislature (Chapter 390, Statutes of 1989). According to a CPUC staff analysis for a bill, SB 1389 (Padilla) dated April 24, 2008, at that time, Southern California Edison was attempting to purchase San Diego Gas & Electric, and several other utility–related mergers were being contemplated. The Senate Committee on Energy, Utilities and Communications and the Assembly Committee on Utilities and Commerce held a joint hearing titled “Utility Merger Mania: Benefits and Risks to Ratepayers and Shareholders” (October 24, 1988). Then-CPUC President Mitch Wilk testified at the hearing. When he was asked by Committee members what criteria the CPUC might use in reviewing a merger, he ran through a list of criteria. Those criteria were subsequently put into proposed legislation by members of the Legislature.
Need for safety. This bill expands on the list of items the CPUC must review as part of any merger, acquisition, or change in control of any electrical or gas corporation, including PG&E. The need to ensure safety has continued to remain very high on the list of concerns related to PG&E dating back to the 2010 San Bruno natural gas pipeline explosion through the recent fires ignited by their electrical lines. Earlier this year, former- CPUC President Picker suggested the CPUC could revoke PG&E’s license to operate in the state – its certificate of public convenience and necessity – if the selection of PG&E’s board does not demonstrate the company’s commitment to safety. As such, the provisions included in the Section 854 by this bill seem largely consistent with the calls for increased safety.
AB 1054 (Holden, Chapter 79, Statutes of 2019). AB 1054 made numerous changes related to electric utilities and wildfires liability and mitigation. With respect to mergers, acquisitions, and change of control, the bill expanded the definition of change of control to include the voluntary or involuntary transfer of an IOU’s assets to a public entity and made changes to the definition for change of control that included specified criteria and thresholds related to the treatment of the workforce. These changes were deemed concerning and too expansive by those interested in the municipalizing some of the PG&E distribution network, including the City and County of San Francisco, and others.
SB 550. This bill requires the CPUC to review specified safety elements for any proposed merger, acquisition or change in control of an electrical or gas IOU and conditions approval on a finding that, on balance, the transaction is in the public interest relative to those safety elements. This bill also clarifies the reviews required by the CPUC for any other asset transactions between a public utility and any other person or entity whether public or private. This bill further clarifies the considerations required of the CPUC in any asset sale or change of control between a public utility and a public entity, which is intended to include any transfer that may be entailed in a transaction to municipalize a portion of an IOU’s service territory. The growing interest of municipalities to purchase the distribution infrastructure of electrical corporations was the primary transaction of concern which prompted the additional changes in this bill. Those changes largely preserve the additional protections added by AB 1054, while exempting voluntary or involuntary transfer of assets of an IOU to ownership by a public entity from the change of control while more broadly requiring the CPUC’s review of these transactions determines whether the transaction is fair and reasonable to affected IOU employees. As this bill is drafted the provisions related to safety authorize the CPUC to delay implementation until July 1, 2021 or until the CPUC adopts rules implementing the requirements, whichever is earlier. As such, it is possible that the safety criteria added by this bill for a review of a merger, acquisition, or control proposal may not be applied to the a potential reorganization of PG&E who is likely aiming to exit bankruptcy by June 2020, in light of the passage of AB 1054 and the opportunity to participate in the corresponding Wildfire Fund.
Related/Prior Legislation
SB 549 (Hill, 2019) requires the Legislature to approve a capital change structure or increase in rates for the energy utility, PG&E Company. The bill was held in the Senate Appropriations Committee.
SB 52 (Rosenthal, Chapter 484, Statutes of 1989) established criteria that the CPUC must consider in reviewing a merger, acquisition, or change of control related to an IOU.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
According to the Assembly Appropriations Committee, this bill would have negligible costs to the CPUC as existing law already requires the CPUC to extensively review and approve the merger, acquisition or change in control of any IOU. This bill adds elements the CPUC is to consider when reviewing an IOU change in ownership or control, but it does not create the requirement the CPUC conduct such a review.
City and County of San Francisco Mayor, London N. Breed
The Utility Reform Network
OPPOSITION: (Verified 9/10/19)
None received
ARGUMENTS IN SUPPORT: According to the author:
SB 550 requires the CPUC to ensure safe utility service results from any merger, acquisition, or change of control of an electrical or gas corporation. These times of corporate change provide an important opportunity to evaluate the safety processes at a corporation, and ensure the successor entity has the proper safeguards in place for both their employee safety and public safety. The change of ownership at the Gill Ranch Storage facility located in Fresno and Madera Counties provides an example of a successful safety review during such corporate change. Gill Ranch agreed to designating a Chief Safety Officer, creating a Pipeline Safety Management System, and creating a Safety Council to propose risk mitigation as part of their change in ownership. SB 550 seeks to expand the important changes at Gill Ranch to any gas or electric utility undergoing a merger, acquisition, or change of control.
ASSEMBLY FLOOR: 79-0, 9/10/19
AYES: Aguiar-Curry, Arambula, Bauer-Kahan, Berman, Bigelow, Bloom, Boerner Horvath, Bonta, Brough, Burke, Calderon, Carrillo, Cervantes, Chau, Chen, Chiu, Choi, Chu, Cooley, Cooper, Cunningham, Daly, Diep, Eggman, Flora, Fong, Frazier, Friedman, Gabriel, Gallagher, Cristina Garcia, Eduardo Garcia, Gipson, Gloria, Gonzalez, Gray, Grayson, Holden, Irwin, Jones-Sawyer, Kalra, Kamlager-Dove, Kiley, Lackey, Levine, Limón, Low, Maienschein, Mathis, Mayes, McCarty, Medina, Melendez, Mullin, Muratsuchi, Nazarian, Obernolte, O'Donnell, Patterson, Petrie-Norris, Quirk, Quirk-Silva, Ramos, Reyes, Luz Rivas, Robert Rivas, Rodriguez, Blanca Rubio, Salas, Santiago, Smith, Mark Stone, Ting, Voepel, Waldron, Weber, Wicks, Wood, Rendon
Prepared by: Nidia Bautista / E., U., & C. / (916) 651-4107
9/12/19 16:10:28
**** END ****
SENATE COMMITTEE ON ENERGY, UTILITIES AND COMMUNICATIONS
Senator Ben Hueso, Chair
2019 - 2020 Regular
Bill No: SB 550 Hearing Date: 9/12/2019
Author: | Hill | ||
Version: | 9/6/2019 As Amended | ||
Urgency: | No | Fiscal: | Yes |
Consultant: | Nidia Bautista | ||
SUBJECT: Public utilities: merger, acquisition, or control of electrical or gas corporations
DIGEST: This bill would require the California Public Utilities Commission (CPUC) to review specified safety elements for any proposed merger, acquisition or change in control of an electrical or gas investor owned utility (IOU) and conditions approval on a finding that, on balance, the transaction is in the public interest relative to those safety elements. This bill also clarifies the reviews required by the CPUC for any other asset transactions between a public utility and any other person or entity whether public or private.
ANALYSIS:
Existing law:
- Establishes the CPUC has regulatory authority over public utilities, including electrical corporations and gas corporations. (California Constitution Article 12)
- Existing law prohibits a public utility, other than certain common carriers, from selling, leasing, assigning, mortgaging, or otherwise disposing of, or encumbering its assets that are necessary or useful in the performance of its duties to the public by any means with any other public utility, unless the public utility has secured an order from the CPUC to do so for a qualified transaction above $5,000,000 or an approval from the CPUC through the filing of an advice letter for a qualified transaction at or below $5,000,000. (Public Utilities Code §851)
- Existing law prohibits a person or corporation, including a public entity, from merging, acquiring, or controlling, as described, either directly or indirectly, any public utility organized and doing business in this state without first securing authorization to do so from the CPUC. Before authorizing the merger, acquisition, or control of any electrical, gas, or telephone corporation organized and doing business in this state, where any of the entities that are parties to the proposed transaction has gross annual California revenues exceeding $500,000,000, existing law requires the CPUC to consider specified criteria and to find that the merger, acquisition, or control proposal meets certain requirements and is in the public interest, as specified. (Public Utilities Code §854)
- Defines a change of control to include the voluntary or involuntary change in ownership of assets from an electrical or gas corporation to a public entity. Requires specified workforce protections when a change of control occurs. (Public Utilities Code §854.2)
This bill:
- Eliminates the requirements sales, leases, assignments, mortgages, or other transactions be with another public utility to be subject to those conditions on approval.
- Explicitly requires the CPUC to approve or reject any voluntary or involuntary change in ownership of assets from an electrical or gas corporation to ownership by a public entity and would require the CPUC to determine whether that transaction is fair and reasonable to the affected public utility employees as part of that review.
- Requires the CPUC, before authorizing a merger, acquisition, or change in control of an electrical or gas corporation, where an entity to the proposed transaction has gross annual California revenues exceeding $400,000,000, to additionally consider specified elements relating to the safety activities of an electrical or gas corporation, including a nonpunitive system for reporting potential safety incidents to the CPUC, and find, on balance, that the proposal is in the public interest.
- Authorizes the CPUC to delay the requirement that the CPUC consider these specified elements and find, on balance, that the proposal is in the public interest, until July 1, 2021, or until the CPUC adopts rules implementing this requirement, whichever is earlier.
- Prohibits subjecting an employee of, or the employee of a contractor performing work for, the electrical or gas corporation to demotion, discharge, or any other form of retaliation or discrimination for participating in the nonpunitive system for reporting potential safety incidents.
- Eliminates the requirements for these reviews for a change in ownership in the assets of an electrical or gas corporation to ownership by a public entity.
Background
Pacific Gas & Electric (PG&E) files for Chapter 11 Bankruptcy protection. On January 29, 2019, PG&E Corp., the holding company of the state’s largest utility, voluntarily filed for bankruptcy protection under Chapter 11 of the United States Bankruptcy Code. PG&E filed their case in the Northern California District Court San Francisco Division (Case No. 19-30088-DM). The case has been assigned to the same judge, Honorable Dennis Montali, who handled PG&E’s previous reorganization bankruptcy case in connection with the 2001 energy crisis. According to PG&E’s first day filings, in a declaration filed by PG&E’s Senior Vice President and Chief Financial Officer Jason Wells, PG&E’s decision to seek relief under Chapter 11 “were necessitated by a confluence of factors resulting from the catastrophic and tragic wildfires that occurred in Northern California in 2017 and 2018, and PG&E’s potential liabilities arising therefrom.” The declaration specifically cites PG&E’s potential liability related to the fires could exceed $30 billion. PG&E’s decision to voluntarily file for bankruptcy protection has raised numerous questions about the process entailed under a Chapter 11 reorganization and the potential implications for the numerous stakeholders that could be affected, including wildfire victims, ratepayers, the utility workforce, energy and other suppliers, local governments, and many others. The bankruptcy filing and wildfire incidents have also increased interest by some local governments, including the City and County of San Francisco, as a possible opportunity to purchase part of the existing PG&E distribution system in an effort to municipalize a portion of the service territory.
CPUC approval needed. CPUC must review any transactions involving the selling, buying, merging, or otherwise changing control of a public utility’s assets. Section 854 of the Public Utilities Code establishes the criteria by which the CPUC must review any IOU merger, acquisition, or sale. Among the criteria are a CPUC determination that the merger or acquisition will provide long-term economic benefits to ratepayers, does not adversely affect competition, be beneficial on an overall basis to the state and local economies, and others. Interestingly, the criteria in Section 854 (b) and (c) were added in 1989 by the State Legislature (Statues of 1989, Chapter 390). According to a CPUC staff analysis for a bill, SB 1389 (Padilla) dated April 24, 2008, at that time, Southern California Edison (SCE) was attempting to purchase San Diego Gas & Electric (SDG&E), and several other utility–related mergers were being contemplated. The Senate Committee on Energy, Utilities and Communications (SEUC) and the Assembly Committee on Utilities and Commerce (U&C) held a joint hearing titled “Utility Merger Mania: Benefits and Risks to Ratepayers and Shareholders” (October 24, 1988). Then-CPUC President Mitch Wilk testified at the hearing. When he was asked by Committee members what criteria the CPUC might use in reviewing a merger, he ran through a list of criteria. Those criteria were subsequently put into proposed legislation by members of the Legislature.
Need for safety. This bill expands on the list of items the CPUC must review as part of any merger, acquisition, or change in control of any electrical or gas corporation, including PG&E. The need to ensure safety has continued to remain very high on the list of concerns related to PG&E dating back to the 2010 San Bruno natural gas pipeline explosion through the recent fires ignited by their electrical lines. Earlier this year, former- CPUC President Picker suggested the CPUC could revoke PG&E’s license to operate in the state – its certificate of public convenience and necessity – if the selection of PG&E’s board does not demonstrate the company’s commitment to safety. As such, the provisions included in the Section 854 by this bill seem largely consistent with the calls for increased safety.
AB 1054 (Holden, Chapter 79, Statutes of 2019). AB 1054 made numerous changes related to electric utilities and wildfires liability and mitigation. With respect to mergers, acquisitions, and change of control, the bill expanded the definition of change of control to include the voluntary or involuntary transfer of an IOU’s assets to a public entity and made changes to the definition for change of control that included specified criteria and thresholds related to the treatment of the workforce. These changes were deemed concerning and too expansive by those interested in the municipalizing some of the PG&E distribution network, including the City and County of San Francisco, and others.
SB 550. This bill would require the CPUC to review specified safety elements for any proposed merger, acquisition or change in control of an electrical or gas IOU and conditions approval on a finding that, on balance, the transaction is in the public interest relative to those safety elements. This bill also clarifies the reviews required by the CPUC for any other asset transactions between a public utility and any other person or entity whether public or private. This bill further clarifies the considerations required of the CPUC in any asset sale or change of control between a public utility and a public entity, which is intended to include any transfer that may be entailed in a transaction to municipalize a portion of an IOU’s service territory. The growing interest of municipalities to purchase the distribution infrastructure of electrical corporations was the primary transaction of concern which prompted the additional changes in this bill. Those changes largely preserve the additional protections added by AB 1054, while exempting voluntary or involuntary transfer of assets of an IOU to ownership by a public entity from the change of control while more broadly requiring the CPUC’s review of these transactions determines whether the transaction is fair and reasonable to affected IOU employees. As this bill is drafted the provisions related to safety authorize the CPUC to delay implementation until July 1, 2021 or until the CPUC adopts rules implementing the requirements, whichever is earlier. As such, it is possible that the safety criteria added by this bill for a review of a merger, acquisition, or control proposal may not be applied to the a potential reorganization of PG&E who is likely aiming to exit bankruptcy by June 2020, in light of the passage of AB 1054 and the opportunity to participate in the corresponding Wildfire Fund.
Prior/Related Legislation
SB 549 (Hill, 2019) requires the Legislature to approve a capital change structure or increase in rates for the energy utility, PG&E Company. The bill was held in the Senate Committee on Appropriations.
SB 52 (Rosenthal, Chapter 484, Statutes of 1989) established criteria that the CPUC must consider in reviewing a merger, acquisition, or change of control related to an IOU.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
SUPPORT:
City and County of San Francisco Mayor, London N. Breed
The Utility Reform Network
OPPOSITION:
None received
ARGUMENTS IN SUPPORT: According to the author:
SB 550 requires the CPUC to ensure safe utility service results from any merger, acquisition, or change of control of an electrical or gas corporation. These times of corporate change provide an important opportunity to evaluate the safety processes at a corporation, and ensure the successor entity has the proper safeguards in place for both their employee safety and public safety. The change of ownership at the Gill Ranch Storage facility located in Fresno and Madera Counties provides an example of a successful safety review during such corporate change. Gill Ranch agreed to designating a Chief Safety Officer, creating a Pipeline Safety Management System, and creating a Safety Council to propose risk mitigation as part of their change in ownership. SB 550 seeks to expand the important changes at Gill Ranch to any gas or electric utility undergoing a merger, acquisition, or change of control.
-- END --
SENATE THIRD READING
STR Bill Id:SB 550
Author:(Hill)
As Amended Ver:September 6, 2019
Majority vote
SUMMARY:
Requires the California Public Utilities Commission (CPUC) to review specified safety elements for any proposed merger, acquisition or change in control of an electrical or gas corporation (IOU) and conditions approval on a finding that, on balance, the transaction is in the public interest relative to those safety elements. The bill also clarifies the reviews required by the CPUC for any other asset transactions between a public utility and any other person or entity whether public or private.
Major Provisions
- Clarify that the CPUC is required to review the sale of any utility assets to any person or entity, whether public or private consistent with current and historical CPUC policies.
- Specifically require that the CPUC review the sale of an asset by a public utility to a public entity, which is intended to include locally owned public utilities (POUs), whether the asset is being sold voluntarily or involuntarily (eminent domain) thus clarifying provisions of AB 1054 (Holden, Chapter 95, Statutes of 2019).
- Clarify that, for any transaction by a public entity, which is intended to include POUs, whether voluntary or involuntary, the CPUC shall determine whether the transaction is fair and reasonable to affected public utility employees, including both union and nonunion employees, thus clarifying provisions of AB 1054 (Holden, Chapter 95, Statutes of 2019).
- Eliminate the requirement the CPUC review any merger, acquisition, or change of control of a public utility by a public entity, which is intended to include POUs, to determine whether that transaction is in the public interest, thus clarifying provisions of AB 1054 (Holden, Chapter 95, Statutes of 2019).
- Specify eight safety elements that must be considered by the CPUC and result in a finding that the transaction is, on balance, in the public interest.
- Limit the requirement that the CPUC review mergers, acquisitions or changes in control of a public utility, for impacts on different safety policies and programs, to those transactions with an entity with annual gross revenues exceeding $400 million.
COMMENTS:
Current law requires the CPUC to review all mergers, acquisitions, or changes in control of any electric, gas or telephone corporation where the party seeking the assets has gross annual revenues exceeding $500,000 and ensure that the proposal is in the public and/or ratepayer interest based on specified considerations. Safety management and practices are not among the elements the CPUC is required to consider before the proposal is approved. This bill adds a number of safety-related elements the CPUC must consider before authorizing the merger, acquisition or change in control of a gas or electric corporation with an entity that has more than $400,000 in gross annual revenues.
More broadly, this bill clarifies the considerations required of the CPUC in any asset sale or change of control between a public utility and a public entity, which is intended to include POUs. Several changes were made to the CPUC's review requirements in AB 1054 (Holden, Chapter 95, Statutes of 2019) which broadened the considerations required was deemed by some to be more far-reaching than necessary. The growing interest of municipalities to purchase the distribution infrastructure of electrical corporations was the primary transaction of concern which prompted these changes.
According to the Author:
SB 550 requires the CPUC to ensure safe utility service results from any merger, acquisition, or change of control of an electrical or gas corporation. These times of corporate change provide an important opportunity to evaluate the safety processes at a corporation, and ensure the successor entity has the proper safeguards in place for both their employee safety and public safety. The change of ownership at the Gill Ranch Storage facility located in Fresno and Madera Counties provides an example of a successful safety review during such corporate change. Gill Ranch agreed to designating a Chief Safety Officer, creating a Pipeline Safety Management System, and creating a Safety Council to propose risk mitigation as part of their change in ownership. SB 550 seeks to expand the important changes at Gill Ranch to any gas or electric utility undergoing a merger, acquisition, or change of control.
Arguments in Support:
The Utility Reform Network (TURN), "this bill requires specified safety-related actions before the CPUC authorizes a merger or sale of an investor owned utility. TURN strongly believes that any merger or sale of an investor owned utility should not compromise safe utility service. During these kinds of critical junctures for a utility, it is important that safety processes are evaluated and that the successor entity has proper safeguards in place. By setting out safety criteria and laying out protections for whistleblowers, SB 550 takes a crucial step towards ensuring public safety."
Arguments in Opposition:
There is no registered opposition to this bill.
FISCAL COMMENTS:
According to Assembly Appropriations Committee, this bill would have negligible costs to the CPUC as existing law already requires the CPUC to extensively review and approve the merger, acquisition or change in control of any IOU. This bill adds elements the CPUC is to consider when reviewing an IOU change in ownership or control, but it does not create the requirement the CPUC conduct such a review.
VOTES:
SENATE FLOOR: 34-3-1
YES: Allen, Archuleta, Atkins, Beall, Borgeas, Bradford, Caballero, Chang, Dodd, Durazo, Galgiani, Glazer, Grove, Hertzberg, Hill, Hueso, Hurtado, Jackson, Leyva, McGuire, Mitchell, Monning, Nielsen, Pan, Portantino, Roth, Rubio, Skinner, Stern, Stone, Umberg, Wieckowski, Wiener, Wilk
NO: Jones, Moorlach, Morrell
ABS, ABST OR NV: Bates
ASM UTILITIES AND ENERGY: 14-0-1
YES: Holden, Patterson, Burke, Carrillo, Chen, Eggman, Cristina Garcia, Eduardo Garcia, Mayes, Muratsuchi, Quirk, Reyes, Santiago, Ting
ABS, ABST OR NV: Cunningham
ASM APPROPRIATIONS: 17-0-1
YES: Gonzalez, Bigelow, Bloom, Bonta, Brough, Calderon, Carrillo, Chau, Diep, Eggman, Fong, Gabriel, Maienschein, Obernolte, Petrie-Norris, Quirk, Robert Rivas
ABS, ABST OR NV: Eduardo Garcia
UPDATED:
VERSION: September 6, 2019
CONSULTANT: Mary McDonald / U. & E. / (916) 319-2083 FN: 0002082
SENATE THIRD READING
STR Bill Id:SB 550
Author:(Hill)
As Amended Ver:August 13, 2019
Majority vote
SUMMARY:
This bills adds a number of safety-related elements the California Public Utilities Commission (CPUC) must consider before authorizing the merger, acquisition or change in control of any electrical or gas corporation investor-owned utility (IOU). The bill allows the CPUC to delay implementation of its provisions until July 1, 2021, or until the CPUC adopts rules implementing the requirements of the bill, whichever is earlier.
Major Provisions:
Before authorizing the merger, acquisition, or change in control of any electrical or gas corporation, the CPUC is mandated to consider the following elements and find, on balance, that the proposal is in the public interest:
- Comprehensive, system-wide safety plan;
- Plans to maintain or improve equipment records;
- Metrics to measure and active audits to ensure safety performance;
- Evaluation of safety expertise in qualifications used to select corporate leadership; and,
- System for reporting potential safety incidents to the CPUC.
COMMENTS:
Existing law does not allow a person or entity to merge with or acquire an IOU without first receiving permission to do so from the CPUC. The law directs the CPUC to make a number of findings to ensure the change in IOU ownership is in the public and ratepayer interest. Safety is not explicitly included among findings the CPUC must make.
This bill adds a number of safety-related elements the CPUC must consider before authorizing an electrical or gas corporation merger, acquisition or change in control. The bill allows the CPUC to temporarily delay implementation of the bill's requirements to allow the CPUC time to develop the funding, staff and regulatory structure needed to implement the bill, so as to not delay any pending mergers or acquisitions.
According to the Author:
"SB 550 requires the CPUC to ensure safe utility service results from any merger, acquisition, or change of control of an electrical or gas corporation. These times of corporate change provide an important opportunity to evaluate the safety processes at a corporation, and ensure the successor entity has the proper safeguards in place for both their employee safety and public safety. The change of ownership at the Gill Ranch Storage facility located in Fresno and Madera Counties provides an example of a successful safety review during such corporate change. Gill Ranch agreed to designating a Chief Safety Officer, creating a Pipeline Safety Management System, and creating a Safety Council to propose risk mitigation as part of their change in ownership. SB 550 seeks to expand the important changes at Gill Ranch to any gas or electric utility undergoing a merger, acquisition, or change of control."
Arguments in Support:
The Utility Reform Network (TURN), "This bill requires specified safety-related actions before the California Public Utilities Commission authorizes a merger or sale of an investor owned utility. TURN strongly believes that any merger or sale of an investor owned utility should not compromise safe utility service. During these kinds of critical junctures for a utility, it is important that safety processes are evaluated and that the successor entity has proper safeguards in place. By setting out safety criteria and laying out protections for whistleblowers, SB 550 takes a crucial step towards ensuring public safety."
Arguments in Opposition:
None on file.
FISCAL COMMENTS:
According to Assembly Appropriations Committee, this bill would have negligible costs to the CPUC as existing law already requires the CPUC to extensively review and approve the merger, acquisition or change in control of any IOU. This bill adds elements the CPUC is to consider when reviewing an IOU change in ownership or control, but it does not create the requirement the CPUC conduct such a review.
VOTES:
SENATE FLOOR: 34-3-1
YES: Allen, Archuleta, Atkins, Beall, Borgeas, Bradford, Caballero, Chang, Dodd, Durazo, Galgiani, Glazer, Grove, Hertzberg, Hill, Hueso, Hurtado, Jackson, Leyva, McGuire, Mitchell, Monning, Nielsen, Pan, Portantino, Roth, Rubio, Skinner, Stern, Stone, Umberg, Wieckowski, Wiener, Wilk
NO: Jones, Moorlach, Morrell
ABS, ABST OR NV: Bates
ASM UTILITIES AND ENERGY: 14-0-1
YES: Holden, Patterson, Burke, Carrillo, Chen, Eggman, Cristina Garcia, Eduardo Garcia, Mayes, Muratsuchi, Quirk, Reyes, Santiago, Ting
ABS, ABST OR NV: Cunningham
ASM APPROPRIATIONS: 17-0-1
YES: Gonzalez, Bigelow, Bloom, Bonta, Brough, Calderon, Carrillo, Chau, Diep, Eggman, Fong, Gabriel, Maienschein, Obernolte, Petrie-Norris, Quirk, Robert Rivas
ABS, ABST OR NV: Eduardo Garcia
UPDATED:
VERSION: August 13, 2019
CONSULTANT: Mary McDonald / U. & E. / (916) 319-2083. FN: 0001472
Date of Hearing: August 21, 2019
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Lorena Gonzalez, Chair
SBPCA Bill Id:SB 550
Author:(Hill) – As Amended Ver:August 13, 2019
Policy Committee: | Utilities and Energy | Vote: | 14 - 0 |
|
| ||
|
|
Urgency: No State Mandated Local Program: Yes Reimbursable: No
SUMMARY:
This bills adds a number of safety-related elements the California Public Utilities Commission (CPUC) must consider before authorizing the merger, acquisition or change in control of any electrical or gas corporation (also known as an investor-owned utility, or IOU). The bill allows the CPUC to delay implementation of its provisions until July 1, 2021, or until the CPUC adopts rules implementing the requirements of the bill, whichever is earlier.
FISCAL EFFECT:
Negligible costs to the CPUC as existing law already requires the CPUC to extensively review and approve the merger, acquisition or change in control of any IOU. This bill adds elements the CPUC is to consider when reviewing an IOU change in ownership or control, but it does not create the requirement the CPUC conduct such a review.
COMMENTS:
Background and Purpose. Existing law does not allow a person or entity to merge with or acquire an IOU without first receiving permission to do so from the CPUC. And the law directs the CPUC to make a number of findings to ensure the change in IOU ownership is in the public and ratepayer interest. Safety operation of the IOU, however, is not explicitly included among findings the CPUC must make.
This bill adds a number of safety-related elements the CPUC must make before authorizing an IOU change of ownership. The bill allows the CPUC to temporarily delay implementation of the bill’s requirements to allow the CPUC time to develop the funding, staff and regulatory structure needed to implement the bill, so as to not delay any pending mergers or acquisitions.
According to the author:
SB 550 requires the CPUC to ensure safe utility service results from any merger, acquisition, or change of control of an electrical or gas corporation. These times of corporate change provide an important opportunity to evaluate the safety processes at a corporation, and ensure the successor entity has the proper safeguards in place for both their employee safety and public safety.
The author’s statement is undoubtedly true. So true that, as noted in the policy committee analysis, the CPUC should not wait until it receives a proposed change in IOU ownership to ensure the IOU adequately plans for and is operated safely.
Analysis Prepared by: Jay Dickenson / APPR. / (916) 319-2081
Date of Hearing: July 10, 2019
ASSEMBLY COMMITTEE ON UTILITIES AND ENERGY
Chris Holden, Chair
SBPCA Bill Id:SB 550
Author:(Hill) – As Amended Ver:April 2, 2019
SENATE VOTE: 34-3
SUBJECT: Public utilities: merger, acquisition, or control of electrical or gas corporations
SUMMARY: This bill requires the California Public Utilities Commission (CPUC), before authorizing a merger, acquisition, or change in control of an electrical or gas corporation, to ensure that seven specific elements of the plan, on balance, improve the safety of the utility service provided by the electrical or gas corporation. The elements are as follows:
1) Safety management system.
2) A comprehensive, system-wide safety plan.
3) Plan to maintain or improve records, including necessary audits to update incorrect or incomplete records of the electrical or gas corporation.
4) Metrics to measure safety.
5) Safety expertise in corporate leadership.
6) Both metrics to measure and active audits to ensure safety performance.
7) A system for reporting actual and potential safety incidents to the CPUC.
EXISTING LAW:
- Prohibits a person or corporation from merging, acquiring, or controlling either directly or indirectly any public utility organized and doing business in this state without first securing authorization to do so from the CPUC. Requires that any merger, acquisition, or control without that prior authorization is void and of no effect.
- Requires the CPUC to consider specified criteria and to find that the merger, acquisition, or control proposal meets certain requirements. The merger, acquisition, or control of any electrical, gas, or telephone corporation organized and doing business in this state must be found by the CPUC to be in the public interest. These provisions apply where any of the entities that are parties to the proposed transaction has gross annual California revenues exceeding $500,000,000, existing law. (Public Utilities Code §854).
FISCAL EFFECT: According to Senate Appropriations Committee:
Ongoing annual special fund costs (PUC Utilities Reimbursement Account) of around $200,000 for CPUC to implement the requirements in the bill.
BACKGROUND:
Transfer or Encumbrance of Utility Property – Existing law (Section 854 of the Public Utilities Code) vests the CPUC with the authority to establish definitions of what constitutes merger, acquisition, or control activities. The origins of that section date back to 1951 and it was most recently amended with the passage of (SB 901, Dodd, Chapter 626, Statutes of 2018). Under the provisions of this section, any merger, acquisition or control of an electrical, gas or telephone corporation are void without CPUC approval. The CPUC must determine that the merger or acquisition will provide long-term economic benefits to ratepayers, not adversely affect competition, be beneficial on an overall basis to the state and local economy.
CPUC review of mergers and sales of utilities - Section 854 of the Public Utilities Code establishes the criteria by which the CPUC must review any investor-owned utility IOU merger, acquisition, or sale. Among the criteria are a CPUC determination that the merger or acquisition will provide long-term economic benefits to ratepayers, does not adversely affect competition, be beneficial on an overall basis to the state and local economies, and others. Interestingly, the criteria in Section 854 (b) and (c) were added in 1989 by the State Legislature (Statues of 1989, Chapter 390). According to a CPUC staff analysis for a bill, SB 1389 (Padilla) dated April 24, 2008, at that time, Southern California Edison (SCE) was attempting to purchase San Diego Gas & Electric (SDG&E), and several other utility–related mergers were being contemplated.
Chapter 11 - On January 29th, 2019 PG&E filed for Chapter 11 protection in the Northern District of California Bankruptcy Court (No.19-30088-DM) which allows PG&E to propose a plan of reorganization to keep its business alive and pay creditors over time. In that filing, PG&E claimed $51.7 billion in total debt versus approximately $71 billion in assets. According to the company’s first day filings, in a declaration filed by the company’s Senior Vice President and Chief Financial Officer Jason Wells, PG&E’s decision to seek relief under Chapter 11 was “necessitated by a confluence of factors resulting from the catastrophic and tragic wildfires that occurred in Northern California in 2017 and 2018, and PG&E’s potential liabilities arising therefrom.” The declaration specifically cites the company’s potential liability related to the fires could exceed $30 billion. PG&E asserts that its bond ratings dropped so precipitously that it was unable to maintain the cash flow needed to operate as the markets anticipated that the utility would have to book billions of dollars in liability
COMMENTS:
- According to the author: “SB 550 requires the CPUC to ensure safe utility service results from any merger, acquisition, or change of control of an electrical or gas corporation. These times of corporate change provide an important opportunity to evaluate the safety processes at a corporation, and ensure the successor entity has the proper safeguards in place for both their employee safety and public safety. The change of ownership at the Gill Ranch Storage facility located in Fresno and Madera Counties provides an example of a successful safety review during such corporate change. Gill Ranch agreed to designating a Chief Safety Officer, creating a Pipeline Safety Management System, and creating a Safety Council to propose risk mitigation as part of their change in ownership. SB 550 seeks to expand the important changes at Gill Ranch to any gas or electric utility undergoing a merger, acquisition, or change of control.”
- Prior to CPUC authorization. This bill would expand on the list of items the CPUC is mandated to find prior to approving a merger, acquisition, or change in control of any electrical or gas corporation. The CPUC must in fact ensure that each of the seven elements are included in the merger, acquisition, or control proposal and find, on balance, that the proposal improves the safety of the utility service provided by the electrical or gas corporation. Many of the criteria of this bill are presently required in PG&E’s Safety Culture proceeding {OII 15-08-019} and adopted for PG&E to implement in D. 18-11-050. In SB 901, safety culture assessments – like that conducted for PG&E in its Safety Culture proceeding - were required for all electrical corporations. It is therefore logical to presume that many of these recommendations will be adopted soon (if not already) for the other utilities. However, it is unclear that the seven criteria are uniformly applied to all corporations that are regulated by the CPUC.
- Continuing to raise the bar on safety. It is within the CPUC’s current authority to mandate the criteria in SB 550 for all gas and electric utilities. In fact, they could open a rulemaking tomorrow should they choose to do so. Without a doubt, the provisions described in this measure are important, and as such it is incongruent to wait until there is a triggering event, such as a merger, acquisition or change in control to ensure that the provisions are in place. With that said, when a utility undergoes a merger or acquisition, they enter a period of transition may create a unique opportunity to be reflective not only on financials but also on corporate structure – and hopefully, on safety. However, the CPUC must have the staff and regulatory structure in place to successfully implement the provisions of this measure.
As such, the Committee may wish to consider amending the bill in recognition of the fact that the CPUC must have the funding, staff and a regulatory structure in place to administer the provisions of this section so as not to impede mergers, acquisitions or changes in control of electrical or gas corporations under their jurisdiction.
The Commission may delay the implementation of this subdivision until July 1, 2021 or until the Commission adopts regulations implementing elements (1) to (7) for all gas and electric corporations under the Commission’s jurisdiction, whichever is earlier.
Given the scope of the mandate associated with this measure, the Committee may wish to consider amending the measure to provide flexibility in the CPUC’s approval process:
(d) Before authorizing the merger, acquisition, or change in control of any electrical or gas corporation organized and doing business in this state, the commission shall ensure consider each of the elements in paragraphs (1) to (7), inclusive, are included in the merger, acquisition, or control proposal and find, on balance, that the proposal improves the safety of the utility service provided by the electrical or gas corporation is in the public interest authorization standard from shall ensure to shall consider each of the elements and find, on balance, that the proposal is in the public interest.
- Prior/Related Legislation.
SB 549 (Hill, 2019) would require the Legislature to approve a capital change structure or increase in rates for the energy utility, PG&E Company. Status: Held in Senate Appropriations Committee.
SB 901 (Dodd, Chapter 626, Statutes of 2018) addresses numerous issues concerning wildfire and utilities; but additionally included two changes to public utility mergers, acquisitions and changes of control.
SB 52 (Rosenthal, Chapter 484, Statutes of 1989) established criteria that the CPUC must consider in reviewing a merger, acquisition, or change of control related to an IOU.
REGISTERED SUPPORT / OPPOSITION:
Support
None on file.
Opposition
None on file.
Analysis Prepared by: Mary McDonald / U. & E. /
Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 550 |
THIRD READING
Bill No: SB 550
Amended: 4/2/19
SENATE ENERGY, U. & C. COMMITTEE: 12-1, 4/24/19
AYES: Hueso, Bradford, Chang, Dodd, Hertzberg, Hill, McGuire, Rubio, Skinner, Stern, Stone, Wiener
NOES: Moorlach
SENATE APPROPRIATIONS COMMITTEE: 4-1, 5/16/19
AYES: Portantino, Bradford, Hill, Wieckowski
NOES: Jones
NO VOTE RECORDED: Bates
SUBJECT: Public utilities: merger, acquisition, or control of electrical or gas corporations
DIGEST:
This bill requires specified safety-related actions before the California Public Utilities Commission (CPUC) authorizes a merger or sale of an investor-owned utility (IOU).
Existing law:
- Establishes the CPUC has regulatory authority over public utilities, including electrical corporations and gas corporations. (California Constitution, Article XII)
- Prohibits a person or corporation from merging, acquiring, or controlling either directly or indirectly any public utility organized and doing business in this state without first securing authorization to do so from the CPUC. Requires that any merger, acquisition, or control without that prior authorization is void and of no effect. Requires the CPUC to consider specified criteria and to find that the merger, acquisition, or control proposal meets certain requirements and is in the public interest, as specified, before authorizing the merger, acquisition, or control of any electrical, gas, or telephone corporation organized and doing business in this state, where any of the entities that are parties to the proposed transaction has gross annual California revenues exceeding $500 million, existing law. (Public Utilities Code §854)
This bill:
- Requires the CPUC, before authorizing a merger, acquisition, or change in control of an electrical or gas corporation, to additionally ensure the proposal includes specified
elements, including a non-punitive system for reporting potential safety incidents to the CPUC, and find, on balance, that the proposal improves the safety of the utility service provided by the electrical or gas corporation. - Prohibits subjecting an employee of, or the employee of a contractor performing work for, the electrical or gas corporation to demotion, discharge, or any other form of retaliation or discrimination for participating in the non-punitive system for reporting potential safety incidents.
Background
Pacific Gas & Electric (PG&E) files for Chapter 11 Bankruptcy protection. On January 29, 2019, PG&E Corp., the holding company of the state’s largest utility, voluntarily filed for bankruptcy protection under Chapter 11 of the United States Bankruptcy Code. PG&E filed their case in the Northern California District Court San Francisco Division (Case No. 19-30088-DM). The case has been assigned to the same judge, Honorable Dennis Montali, who handled PG&E’s previous reorganization bankruptcy case in connection with the 2001 energy crisis. According to PG&E’s first day filings, in a declaration filed by PG&E’s Senior Vice President and Chief Financial Officer Jason Wells, PG&E’s decision to seek relief under Chapter 11 “were necessitated by a confluence of factors resulting from the catastrophic and tragic wildfires that occurred in Northern California in 2017 and 2018, and PG&E’s potential liabilities arising therefrom.” The declaration specifically cites PG&E’s potential liability related to the fires could exceed $30 billion. PG&E’s decision to voluntarily file for bankruptcy protection has raised numerous questions about the process entailed under a Chapter 11 reorganization and the potential implications for the numerous stakeholders that could be affected, including wildfire victims, ratepayers, the utility workforce, energy and other suppliers, local governments, and many others.
CPUC review of mergers and sales of utilities. Section 854 of the Public Utilities Code establishes the criteria by which the CPUC must review any IOU merger, acquisition, or sale. Among the criteria are a CPUC determination that the merger or acquisition will provide long-term economic benefits to ratepayers, does not adversely affect competition, be beneficial on an overall basis to the state and local economies, and others. Interestingly, the criteria in Section 854 (b) and (c) were added in 1989 by the State Legislature (Statues of 1989, Chapter 390). According to a CPUC staff analysis for a bill, SB 1389 (Padilla) dated April 24, 2008, at that time, Southern California Edison (SCE) was attempting to purchase San Diego Gas & Electric (SDG&E), and several other utility–related mergers were being contemplated. The Senate Committee on Energy, Utilities and Communications (SEUC) and the Assembly Committee on Utilities and Commerce (U&C) held a joint hearing titled “Utility Merger Mania: Benefits and Risks to Ratepayers and Shareholders” (October 24, 1988). Then-CPUC President Mitch Wilk testified at the hearing. When he was asked by Committee members what criteria the CPUC might use in reviewing a merger, he ran through a list of criteria. Those criteria were subsequently put into proposed legislation by members of the Legislature.
Need for safety. This bill expands on the list of items the CPUC must review as part of any merger, acquisition, or change in control of any electrical or gas corporation, including PG&E. The need to ensure safety has continued to remain very high on the list of concerns related to PG&E dating back to the 2008 San Bruno natural gas pipeline explosion through the recent fires ignited by their electrical lines. CPUC President Picker has also suggested the CPUC could revoke PG&E’s license to operate in the state – its certificate of public convenience and necessity – if the selection of PG&E’s board does not demonstrate the company’s commitment to safety. As such, the provisions included in the Section 854 by this bill seem largely consistent with the calls for increased safety. Nonetheless, there may be specific items that may result in an unnecessary delay of a potential reorganization of PG&E which may not be included in a reorganization plan, such as: a comprehensive safety plan that includes a system-wide strategic approach for safety and active audits for safety controls. As such, the author may wish to assess which of the requirements could be reasonably included in the reorganization plan and in advance of any merger, acquisition, or change of control.
Related/Prior Legislation
SB 549 (Hill, 2019) requires the Legislature to approve a capital change structure or increase in rates for the energy utility, PG&E Company. The bill was held in the Senate Committee on Appropriations.
SB 52 (Rosenthal, Chapter 484, Statutes of 1989) established criteria that the CPUC must consider in reviewing a merger, acquisition, or change of control related to an IOU.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
According to the Senate Appropriations Committee, ongoing special fund costs (PUC Utilities Reimbursement Account) in the low hundreds of thousands of dollars annually for the CPUC to provide reports to the Legislature detailing any changes to PG&E’s capital structure or rate increases.
None received
OPPOSITION: (Verified 5/16/19)
None received
ARGUMENTS IN SUPPORT: According to the author, “SB 550 requires the CPUC to ensure safe utility service results from any merger, acquisition, or change of control of an electrical or gas corporation. These times of corporate change provide an important opportunity to evaluate the safety processes at a corporation, and ensure the successor entity has the proper safeguards in place for both their employee safety and public safety. The change of ownership at the Gill Ranch Storage facility located in Fresno and Madera Counties provides an example of a successful safety review during such corporate change. Gill Ranch agreed to designating a Chief Safety Officer, creating a Pipeline Safety Management System, and creating a Safety Council to propose risk mitigation as part of their change in ownership. SB 550 seeks to expand the important changes at Gill Ranch to any gas or electric utility undergoing a merger, acquisition, or change of control.”
Prepared by: Nidia Bautista / E., U., & C. / (916) 651-4107
5/18/19 11:57:54
**** END ****
SENATE COMMITTEE ON APPROPRIATIONS
Senator Anthony Portantino, Chair
2019 - 2020 Regular Session
SB 550 (Hill) - Public utilities: merger, acquisition, or control of electrical or gas corporations
Version: April 2, 2019 | Policy Vote: E., U., & C. 12 - 1 |
Urgency: No | Mandate: Yes |
Hearing Date: May 6, 2019 | Consultant: Paul Jacobs |
Bill Summary:
This bill would require specified safety-related actions before the California Public Utilities Commission (CPUC) authorizes a merger or sale of an investor-owned utility (IOU).
Fiscal Impact:
Ongoing annual special fund costs (PUC Utilities Reimbursement Account) of around $200,000 for CPUC to implement the requirements in the bill.
Background:
On January 29, 2019, PG&E voluntarily filed for bankruptcy protection under Chapter 11 of the United States Bankruptcy Code. PG&E’s decision to seek relief under Chapter 11 “were necessitated by a confluence of factors resulting from the catastrophic and tragic wildfires that occurred in Northern California in 2017 and 2018, and PG&E’s potential liabilities arising therefrom.” PG&E’s decision to voluntarily file for bankruptcy protection has raised numerous questions about the process entailed under a Chapter 11 reorganization and the potential implications for the numerous stakeholders that could be affected, including wildfire victims, ratepayers, the utility workforce, energy and other suppliers, local governments, and many others.
Currently, CPUC is required to use certain criteria when reviewing IOU mergers, acquisitions, or sales. These include determining whether the merger will provide long-term economic benefits to ratepayers, does not adversely affect competition, and be beneficial on an overall basis to the state and local economies, among others.
Proposed Law:
This bill would expand on the list of items CPUC must review as part of any merger, acquisition, or change in control of any electrical or gas corporation, including PG&E. Specifically, this bill requires CPUC to additionally consider a non-punitive system for reporting potential safety incidents to the commission, and find, on balance, that the proposal improves the safety of the utility service provided by the electrical or gas corporation. This bill also prohibits subjecting an employee of, or the employee of a contractor performing work for, the electrical or gas corporation to demotion, discharge, or any other form of retaliation or discrimination for participating in the non-punitive system for reporting potential safety incidents.
Related Legislation:
SB 52 (Rosenthal), Chapter 484, Statutes of 1989 established criteria that the CPUC must consider in reviewing a merger, acquisition, or change of control related to an IOU.
Staff Comments:
According to CPUC, implementing this bill creates new workload for the Office of the Safety Advocate (OSA) that is not absorbable with current resources. According to CPUC, the OSA would need to hire one permanent Senior Utilities Engineer with the following tasks:
- Provide technical input and advocate for safety measures in any and all proceedings implementing the requirements imposed by this bill.
- Issue data requests and review the proposal by an electric or gas IOU to determine if the merger, acquisition or change in control meets the safety elements and criteria that would be established by this bill and advise the Commission on potential improvements or modifications to such proposal, if applicable.
- Manage and oversee safety audits of the electric and gas IOU to ensure compliance with the requirements established by this bill, which includes but is not limited to submitting subsequent data requests, performing additional safety analyses, identifying safety gaps, and advising the Commission on potential improvements or enforcement action if found to be out of compliance.
Additionally, CPUC states that adding this new position to OSA would also trigger the need for one permanent Program and Project Supervisor because the current reporting structure of OSA is not sustainable and the expanded workload and staff that would be triggered by this bill necessitates the addition of this new supervisor position. OSA currently has around 12 staff that report to the Director without any other intermediary supervisors. However, although it might be likely that OSA is in need of a new supervisor position, staff did not include this position in the fiscal analysis for this bill because it is unclear whether OSA already is in need of a supervisor even without this bill.
-- END --
SENATE COMMITTEE ON ENERGY, UTILITIES AND COMMUNICATIONS
Senator Ben Hueso, Chair
2019 - 2020 Regular
Bill No: SB 550 Hearing Date: 4/24/2019
Author: | Hill | ||
Version: | 4/2/2019 As Amended | ||
Urgency: | No | Fiscal: | Yes |
Consultant: | Nidia Bautista | ||
SUBJECT: Public utilities: merger, acquisition, or control of electrical or gas corporations
DIGEST: This bill would require specified safety-related actions before the California Public Utilities Commission (CPUC) authorizes a merger or sale of an investor-owned utility.
ANALYSIS:
Existing law:
- Establishes the CPUC has regulatory authority over public utilities, including electrical corporations and gas corporations.(California Constitution, Article XII)
- Prohibits a person or corporation from merging, acquiring, or controlling either directly or indirectly any public utility organized and doing business in this state without first securing authorization to do so from the CPUC. Requires that any merger, acquisition, or control without that prior authorization is void and of no effect. Requires the CPUC to consider specified criteria and to find that the merger, acquisition, or control proposal meets certain requirements and is in the public interest, as specified, before authorizing the merger, acquisition, or control of any electrical, gas, or telephone corporation organized and doing business in this state, where any of the entities that are parties to the proposed transaction has gross annual California revenues exceeding $500,000,000, existing law. (Public Utilities Code §854)
This bill:
- Requires the CPUC, before authorizing a merger, acquisition, or change in control of an electrical or gas corporation, to additionally ensure the proposal includes specified
elements, including a non-punitive system for reporting potential safety incidents to the commission, and find, on balance, that the proposal improves the safety of the utility service provided by the electrical or gas corporation. - Prohibits subjecting an employee of, or the employee of a contractor performing work for, the electrical or gas corporation to demotion, discharge, or any other form of retaliation or discrimination for participating in the non-punitive system for reporting potential safety incidents.
Background
Pacific Gas & Electrict (PG&E) files for Chapter 11 Bankruptcy protection. On January 29, 2019, PG&E Corp., the holding company of the state’s largest utility, voluntarily filed for bankruptcy protection under Chapter 11 of the United States Bankruptcy Code. PG&E filed their case in the Northern California District Court San Francisco Division (Case No. 19-30088-DM). The case has been assigned to the same judge, Honorable Dennis Montali, who handled PG&E’s previous reorganization bankruptcy case in connection with the 2001 energy crisis. According to PG&E’s first day filings, in a declaration filed by PG&E’s Senior Vice President and Chief Financial Officer Jason Wells, PG&E’s decision to seek relief under Chapter 11 “were necessitated by a confluence of factors resulting from the catastrophic and tragic wildfires that occurred in Northern California in 2017 and 2018, and PG&E’s potential liabilities arising therefrom.” The declaration specifically cites PG&E’s potential liability related to the fires could exceed $30 billion. PG&E’s decision to voluntarily file for bankruptcy protection has raised numerous questions about the process entailed under a Chapter 11 reorganization and the potential implications for the numerous stakeholders that could be affected, including wildfire victims, ratepayers, the utility workforce, energy and other suppliers, local governments, and many others.
CPUC review of mergers and sales of utilities. Section 854 of the Public Utilities Code establishes the criteria by which the CPUC must review any investor-owned utility (IOU) merger, acquisition, or sale. Among the criteria are a CPUC determination that the merger or acquisition will provide long-term economic benefits to ratepayers, does not adversely affect competition, be beneficial on an overall basis to the state and local economies, and others. Interestingly, the criteria in Section 854 (b) and (c) were added in 1989 by the State Legislature (Statues of 1989, Chapter 390). According to a CPUC staff analysis for a bill, SB 1389 (Padilla) dated April 24, 2008, at that time, Southern California Edison (SCE) was attempting to purchase San Diego Gas & Electric (SDG&E), and several other utility–related mergers were being contemplated. The Senate Committee on Energy, Utilities & Communications (SEUC) and the Assembly Committee on Utilities and Commerce (U&C) held a joint hearing titled “Utility Merger Mania: Benefits and Risks to Ratepayers and Shareholders” (October 24, 1988). Then-CPUC President Mitch Wilk testified at the hearing. When he was asked by committee members what criteria the CPUC might use in reviewing a merger, he ran through a list of criteria. Those criteria were subsequently put into proposed legislation by members of the Legislature.
Need for safety. This bill would expand on the list of items the CPUC must review as part of any merger, acquisition, or change in control of any electrical or gas corporation, including PG&E. The need to ensure safety has continued to remain very high on the list of concerns related to PG&E dating back to the 2008 San Bruno natural gas pipeline explosion through the recent fires ignited by their electrical lines. CPUC President Picker has also suggested the CPUC could revoke PG&E’s license to operate in the state – it’s certificate of public convenience and necessity (CPCN) – if the selection of PG&E’s board does not demonstrates the company’s commitment to safety. As such, the provisions included in the Section 854 by this bill seem largely consistent with the calls for increased safety. Nonetheless, there may be specific items that may result in an unnecessary delay of a potential reorganization of PG&E which may not be included in a reorganization plan, such as: a comprehensive safety plan that includes a system-wise strategic approach for safety and active audits for safety controls. As such, the author may wish to assess which of the requirements could be reasonably included in the reorganization plan and in advance of any merger, acquisition, or change of control.
Prior/Related Legislation
SB 549 (Hill, 2019) would require the Legislature to approve a capital change structure or increase in rates for the energy utility, PG&E Company. The bill is pending consideration before this committee.
SB 52 (Rosenthal, Chapter 484, Statutes of 1989) established criteria that the CPUC must consider in reviewing a merger, acquisition, or change of control related to an IOU.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
SUPPORT:
None received
OPPOSITION:
None received
ARGUMENTS IN SUPPORT: According to the author:
“SB 550 requires the CPUC to ensure safe utility service results from any merger, acquisition, or change of control of an electrical or gas corporation. These times of corporate change provide an important opportunity to evaluate the safety processes at a corporation, and ensure the successor entity has the proper safeguards in place for both their employee safety and public safety. The change of ownership at the Gill Ranch Storage facility located in Fresno and Madera Counties provides an example of a successful safety review during such corporate change. Gill Ranch agreed to designating a Chief Safety Officer, creating a Pipeline Safety Management System, and creating a Safety Council to propose risk mitigation as part of their change in ownership. SB 550 seeks to expand the important changes at Gill Ranch to any gas or electric utility undergoing a merger, acquisition, or change of control.”