SB 70: Electricity: undergrounding of electrical infrastructure.
- Session Year: 2019-2020
- House: Senate
- Latest Version Date: 2019-10-02
(1)Under existing law, the Public Utilities Commission has jurisdiction over public utilities, including electrical corporations. Under its existing authority, the commission requires certain electrical corporations to implement the California Overhead Conversion Program to provide financial assistance to local governments to facilitate projects that are in the public interest and replace overhead infrastructure with infrastructure in underground trenches. Existing law requires each electrical corporation to annually prepare and submit a wildfire mitigation plan to the Wildfire Safety Division of the commission for review and approval. Existing law also requires the division to oversee and complete a review of each electrical corporations compliance with its plan.
This bill would require each electrical corporations wildfire mitigation plan to additionally include a description of where and how the electrical corporation considered undergrounding electrical distribution lines within those areas of its service territory identified to have the highest wildfire risk in a commission fire threat map.
(2)This bill would incorporate additional changes to Section 8386 of the Public Utilities Code proposed by SB 167 and SB 560, contingent on the prior enactment of one or both of those bills.
(3)Under existing law, a violation of any order, decision, rule, direction, demand, or requirement of the commission is a crime.
Because a violation of an order, decision, rule, direction, demand, or requirement of the commission implementing the above provisions would be a crime, this bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
(a)Each electrical corporation shall construct, maintain, and operate its electrical lines and equipment in a manner that will minimize the risk of catastrophic wildfire posed by those electrical lines and equipment.
(b)Each electrical corporation shall annually prepare and submit a wildfire mitigation plan to the Wildfire Safety Division for review and approval. In calendar year 2020, and thereafter, the plan shall cover at least a three-year period. The division shall establish a schedule for the submission of subsequent comprehensive wildfire mitigation plans, which may allow for the staggering of compliance periods for each electrical corporation. In its discretion, the division may allow the annual submissions to be updates to the last approved comprehensive wildfire mitigation plan; provided, that each electrical corporation shall submit a comprehensive wildfire mitigation plan at least once every three years.
(c)The wildfire mitigation plan shall include all of the following:
(1)An accounting of the responsibilities of persons responsible for executing the plan.
(2)The objectives of the plan.
(3)A description of the preventive strategies and programs to be adopted by the electrical corporation to minimize the risk of its electrical lines and equipment causing catastrophic wildfires, including consideration of dynamic climate change risks.
(4)A description of the metrics the electrical corporation plans to use to evaluate the plans performance and the assumptions that underlie the use of those metrics.
(5)A discussion of how the application of previously identified metrics to previous plan performances has informed the plan.
(6)Protocols for disabling reclosers and deenergizing portions of the electrical distribution system that consider the associated impacts on public safety, as well as protocols related to mitigating the public safety impacts of those protocols, including impacts on critical first responders and on health and communication infrastructure.
(7)Appropriate and feasible procedures for notifying a customer who may be impacted by the deenergizing of electrical lines. The procedures shall consider the need to notify, as a priority, critical first responders, health care facilities, and operators of telecommunications infrastructure.
(8)Plans for vegetation management.
(9)Plans for inspections of the electrical corporations electrical infrastructure.
(10)A list that identifies, describes, and prioritizes all wildfire risks, and drivers for those risks, throughout the electrical corporations service territory, including all relevant wildfire risk and risk mitigation information that is part of the Safety Model Assessment Proceeding and the Risk Assessment Mitigation Phase filings. The list shall include, but not be limited to, both of the following:
(A)Risks and risk drivers associated with design, construction, operations, and maintenance of the electrical corporations equipment and facilities.
(B)Particular risks and risk drivers associated with topographic and climatological risk factors throughout the different parts of the electrical corporations service territory.
(11)A description of how the plan accounts for the wildfire risk identified in the electrical corporations Risk Assessment Mitigation Phase filing.
(12)A description of the actions the electrical corporation will take to ensure its system will achieve the highest level of safety, reliability, and resiliency, and to ensure that its system is prepared for a major event, including hardening and modernizing its infrastructure with improved engineering, system design, standards, equipment, and facilities, such as undergrounding, insulation of distribution wires, and pole replacement.
(13)A description of where and how the electrical corporation considered undergrounding electrical distribution lines within those areas of its service territory identified to have the highest wildfire risk in a commission fire threat map.
(14)A showing that the electrical corporation has an adequately sized and trained workforce to promptly restore service after a major event, taking into account employees of other utilities pursuant to mutual aid agreements and employees of entities that have entered into contracts with the electrical corporation.
(15)Identification of any geographic area in the electrical corporations service territory that is a higher wildfire threat than is currently identified in a commission fire threat map, and where the commission should consider expanding the high fire threat district based on new information or changes in the environment.
(16)A methodology for identifying and presenting enterprisewide safety risk and wildfire-related risk that is consistent with the methodology used by other electrical corporations unless the commission determines otherwise.
(17)A description of how the plan is consistent with the electrical corporations disaster and emergency preparedness plan prepared pursuant to Section 768.6, including both of the following:
(A)Plans to prepare for, and to restore service after, a wildfire, including workforce mobilization and prepositioning equipment and employees.
(B)Plans for community outreach and public awareness before, during, and after a wildfire, including language notification in English, Spanish, and the top three primary languages used in the state other than English or Spanish, as determined by the commission based on the United States Census data.
(18)A statement of how the electrical corporation will restore service after a wildfire.
(19)Protocols for compliance with requirements adopted by the commission regarding activities to support customers during and after a wildfire, outage reporting, support for low-income customers, billing adjustments, deposit waivers, extended payment plans, suspension of disconnection and nonpayment fees, repair processing and timing, access to electrical corporation representatives, and emergency communications.
(20)A description of the processes and procedures the electrical corporation will use to do all of the following:
(A)Monitor and audit the implementation of the plan.
(B)Identify any deficiencies in the plan or the plans implementation and correct those deficiencies.
(C)Monitor and audit the effectiveness of electrical line and equipment inspections, including inspections performed by contractors, carried out under the plan and other applicable statutes and commission rules.
(21)Any other information that the Wildfire Safety Division may require.
(d)The Wildfire Safety Division shall post all wildfire mitigation plans and annual updates on the commissions internet website for no less than two months before the divisions decision regarding approval of the plan. The division shall accept comments on each plan from the public, other local and state agencies, and interested parties, and verify that the plan complies with all applicable rules, regulations, and standards, as appropriate.
SEC. 1.1.Section 8386 of the Public Utilities Code is amended to read:8386.(a)Each electrical corporation shall construct, maintain, and operate its electrical lines and equipment in a manner that will minimize the risk of catastrophic wildfire posed by those electrical lines and equipment.
(b)Each electrical corporation shall annually prepare and submit a wildfire mitigation plan to the division for review and approval. In calendar year 2020, and thereafter, the plan shall cover at least a three-year period. The Wildfire Safety Division shall establish a schedule for the submission of subsequent comprehensive wildfire mitigation plans, which may allow for the staggering of compliance periods for each electrical corporation. In its discretion, the division may allow the annual submissions to be updates to the last approved comprehensive wildfire mitigation plan; provided, that each electrical corporation shall submit a comprehensive wildfire mitigation plan at least once every three years.
(c)The wildfire mitigation plan shall include all of the following:
(1)An accounting of the responsibilities of persons responsible for executing the plan.
(2)The objectives of the plan.
(3)A description of the preventive strategies and programs to be adopted by the electrical corporation to minimize the risk of its electrical lines and equipment causing catastrophic wildfires, including consideration of dynamic climate change risks.
(4)A description of the metrics the electrical corporation plans to use to evaluate the plans performance and the assumptions that underlie the use of those metrics.
(5)A discussion of how the application of previously identified metrics to previous plan performances has informed the plan.
(6)Protocols for disabling reclosers and deenergizing portions of the electrical distribution system that consider the associated impacts on public safety. As part of these protocols, each electrical corporation shall include protocols related to mitigating the public safety impacts of disabling reclosers and deenergizing portions of the electrical distribution system that consider the impacts on all of the following:
(A)Critical first responders.
(B)Health and communication infrastructure.
(C)Customers who receive medical baseline allowances pursuant to subdivision (c) of Section 739. The electrical corporation may deploy backup electrical resources or provide financial assistance for backup electrical resources to a customer receiving a medical baseline allowance for a customer who meets all of the following requirements:
(i)The customer relies on life-support equipment that operates on electricity to sustain life.
(ii)The customer demonstrates financial need, including through enrollment in the California Alternative Rates for Energy program created pursuant to Section 739.1.
(iii)The customer is not eligible for backup electrical resources provided through medical services, medical insurance, or community resources.
(D)Subparagraph (C) shall not be construed as preventing an electrical corporation from deploying backup electrical resources or providing financial assistance for backup electrical resources under any other authority.
(7)Appropriate and feasible procedures for notifying a customer who may be impacted by the deenergizing of electrical lines including procedures for those customers receiving a medical baseline allowance as described in paragraph (6). The procedures shall consider the need to notify, as a priority, critical first responders, health care facilities, and operators of telecommunications infrastructure.
(8)Plans for vegetation management.
(9)Plans for inspections of the electrical corporations electrical infrastructure.
(10)A list that identifies, describes, and prioritizes all wildfire risks, and drivers for those risks, throughout the electrical corporations service territory, including all relevant wildfire risk and risk mitigation information that is part of the Safety Model Assessment Proceeding and the Risk Assessment Mitigation Phase filings. The list shall include, but not be limited to, both of the following:
(A)Risks and risk drivers associated with design, construction, operations, and maintenance of the electrical corporations equipment and facilities.
(B)Particular risks and risk drivers associated with topographic and climatological risk factors throughout the different parts of the electrical corporations service territory.
(11)A description of how the plan accounts for the wildfire risk identified in the electrical corporations Risk Assessment Mitigation Phase filing.
(12)A description of the actions the electrical corporation will take to ensure its system will achieve the highest level of safety, reliability, and resiliency, and to ensure that its system is prepared for a major event, including hardening and modernizing its infrastructure with improved engineering, system design, standards, equipment, and facilities, such as undergrounding, insulation of distribution wires, and pole replacement.
(13)A description of where and how the electrical corporation considered undergrounding electrical distribution lines within those areas of its service territory identified to have the highest wildfire risk in a commission fire threat map.
(14)A showing that the electrical corporation has an adequately sized and trained workforce to promptly restore service after a major event, taking into account employees of other utilities pursuant to mutual aid agreements and employees of entities that have entered into contracts with the electrical corporation.
(15)Identification of any geographic area in the electrical corporations service territory that is a higher wildfire threat than is currently identified in a commission fire threat map, and where the commission should consider expanding the high fire threat district based on new information or changes in the environment.
(16)A methodology for identifying and presenting enterprisewide safety risk and wildfire-related risk that is consistent with the methodology used by other electrical corporations unless the commission determines otherwise.
(17)A description of how the plan is consistent with the electrical corporations disaster and emergency preparedness plan prepared pursuant to Section 768.6, including both of the following:
(A)Plans to prepare for, and to restore service after, a wildfire, including workforce mobilization and prepositioning equipment and employees.
(B)Plans for community outreach and public awareness before, during, and after a wildfire, including language notification in English, Spanish, and the top three primary languages used in the state other than English or Spanish, as determined by the commission based on the United States Census data.
(18)A statement of how the electrical corporation will restore service after a wildfire.
(19)Protocols for compliance with requirements adopted by the commission regarding activities to support customers during and after a wildfire, outage reporting, support for low-income customers, billing adjustments, deposit waivers, extended payment plans, suspension of disconnection and nonpayment fees, repair processing and timing, access to electrical corporation representatives, and emergency communications.
(20)A description of the processes and procedures the electrical corporation will use to do all of the following:
(A)Monitor and audit the implementation of the plan.
(B)Identify any deficiencies in the plan or the plans implementation and correct those deficiencies.
(C)Monitor and audit the effectiveness of electrical line and equipment inspections, including inspections performed by contractors, carried out under the plan and other applicable statutes and commission rules.
(21)Any other information that the Wildfire Safety Division may require.
(d)The Wildfire Safety Division shall post all wildfire mitigation plans and annual updates on the commissions internet website for no less than two months before the divisions decision regarding approval of the plan. The division shall accept comments on each plan from the public, other local and state agencies, and interested parties, and verify that the plan complies with all applicable rules, regulations, and standards, as appropriate.
SEC. 1.2.Section 8386 of the Public Utilities Code is amended to read:8386.(a)Each electrical corporation shall construct, maintain, and operate its electrical lines and equipment in a manner that will minimize the risk of catastrophic wildfire posed by those electrical lines and equipment.
(b)Each electrical corporation shall annually prepare and submit a wildfire mitigation plan to the Wildfire Safety Division for review and approval. In calendar year 2020, and thereafter, the plan shall cover at least a three-year period. The division shall establish a schedule for the submission of subsequent comprehensive wildfire mitigation plans, which may allow for the staggering of compliance periods for each electrical corporation. In its discretion, the division may allow the annual submissions to be updates to the last approved comprehensive wildfire mitigation plan; provided, that each electrical corporation shall submit a comprehensive wildfire mitigation plan at least once every three years.
(c)The wildfire mitigation plan shall include all of the following:
(1)An accounting of the responsibilities of persons responsible for executing the plan.
(2)The objectives of the plan.
(3)A description of the preventive strategies and programs to be adopted by the electrical corporation to minimize the risk of its electrical lines and equipment causing catastrophic wildfires, including consideration of dynamic climate change risks.
(4)A description of the metrics the electrical corporation plans to use to evaluate the plans performance and the assumptions that underlie the use of those metrics.
(5)A discussion of how the application of previously identified metrics to previous plan performances has informed the plan.
(6)Protocols for disabling reclosers and deenergizing portions of the electrical distribution system that consider the associated impacts on public safety, as well as protocols related to mitigating the public safety impacts of those protocols, including impacts on critical first responders and on health and communication infrastructure.
(7)Appropriate and feasible procedures for notifying a customer who may be impacted by the deenergizing of electrical lines. The procedures shall direct notification to all public safety offices, critical first responders, health care facilities, and operators of telecommunications infrastructure with premises within the footprint of potential deenergization for a given event.
(8)Plans for vegetation management.
(9)Plans for inspections of the electrical corporations electrical infrastructure.
(10)Protocols for the deenergization of the electrical corporations transmission infrastructure, for instances when the deenergization may impact customers who, or entities that, are dependent upon the infrastructure.
(11)A list that identifies, describes, and prioritizes all wildfire risks, and drivers for those risks, throughout the electrical corporations service territory, including all relevant wildfire risk and risk mitigation information that is part of the Safety Model Assessment Proceeding and the Risk Assessment Mitigation Phase filings. The list shall include, but not be limited to, both of the following:
(A)Risks and risk drivers associated with design, construction, operations, and maintenance of the electrical corporations equipment and facilities.
(B)Particular risks and risk drivers associated with topographic and climatological risk factors throughout the different parts of the electrical corporations service territory.
(12)A description of how the plan accounts for the wildfire risk identified in the electrical corporations Risk Assessment Mitigation Phase filing.
(13)A description of the actions the electrical corporation will take to ensure its system will achieve the highest level of safety, reliability, and resiliency, and to ensure that its system is prepared for a major event, including hardening and modernizing its infrastructure with improved engineering, system design, standards, equipment, and facilities, such as undergrounding, insulation of distribution wires, and pole replacement.
(14)A description of where and how the electrical corporation considered undergrounding electrical distribution lines within those areas of its service territory identified to have the highest wildfire risk in a commission fire threat map.
(15)A showing that the electrical corporation has an adequately sized and trained workforce to promptly restore service after a major event, taking into account employees of other utilities pursuant to mutual aid agreements and employees of entities that have entered into contracts with the electrical corporation.
(16)Identification of any geographic area in the electrical corporations service territory that is a higher wildfire threat than is currently identified in a commission fire threat map, and where the commission should consider expanding the high fire threat district based on new information or changes in the environment.
(17)A methodology for identifying and presenting enterprisewide safety risk and wildfire-related risk that is consistent with the methodology used by other electrical corporations unless the commission determines otherwise.
(18)A description of how the plan is consistent with the electrical corporations disaster and emergency preparedness plan prepared pursuant to Section 768.6, including both of the following:
(A)Plans to prepare for, and to restore service after, a wildfire, including workforce mobilization and prepositioning equipment and employees.
(B)Plans for community outreach and public awareness before, during, and after a wildfire, including language notification in English, Spanish, and the top three primary languages used in the state other than English or Spanish, as determined by the commission based on the United States Census data.
(19)A statement of how the electrical corporation will restore service after a wildfire.
(20)Protocols for compliance with requirements adopted by the commission regarding activities to support customers during and after a wildfire, outage reporting, support for low-income customers, billing adjustments, deposit waivers, extended payment plans, suspension of disconnection and nonpayment fees, repair processing and timing, access to electrical corporation representatives, and emergency communications.
(21)A description of the processes and procedures the electrical corporation will use to do all of the following:
(A)Monitor and audit the implementation of the plan.
(B)Identify any deficiencies in the plan or the plans implementation and correct those deficiencies.
(C)Monitor and audit the effectiveness of electrical line and equipment inspections, including inspections performed by contractors, carried out under the plan and other applicable statutes and commission rules.
(22)Any other information that the Wildfire Safety Division may require.
(d)The Wildfire Safety Division shall post all wildfire mitigation plans and annual updates on the commissions internet website for no less than two months before the divisions decision regarding approval of the plan. The division shall accept comments on each plan from the public, other local and state agencies, and interested parties, and verify that the plan complies with all applicable rules, regulations, and standards, as appropriate.
SEC. 1.3.Section 8386 of the Public Utilities Code is amended to read:8386.(a)Each electrical corporation shall construct, maintain, and operate its electrical lines and equipment in a manner that will minimize the risk of catastrophic wildfire posed by those electrical lines and equipment.
(b)Each electrical corporation shall annually prepare and submit a wildfire mitigation plan to the Wildfire Safety Division for review and approval. In calendar year 2020, and thereafter, the plan shall cover at least a three-year period. The division shall establish a schedule for the submission of subsequent comprehensive wildfire mitigation plans, which may allow for the staggering of compliance periods for each electrical corporation. In its discretion, the division may allow the annual submissions to be updates to the last approved comprehensive wildfire mitigation plan; provided, that each electrical corporation shall submit a comprehensive wildfire mitigation plan at least once every three years.
(c)The wildfire mitigation plan shall include all of the following:
(1)An accounting of the responsibilities of persons responsible for executing the plan.
(2)The objectives of the plan.
(3)A description of the preventive strategies and programs to be adopted by the electrical corporation to minimize the risk of its electrical lines and equipment causing catastrophic wildfires, including consideration of dynamic climate change risks.
(4)A description of the metrics the electrical corporation plans to use to evaluate the plans performance and the assumptions that underlie the use of those metrics.
(5)A discussion of how the application of previously identified metrics to previous plan performances has informed the plan.
(6)Protocols for disabling reclosers and deenergizing portions of the electrical distribution system that consider the associated impacts on public safety. As part of these protocols, each electrical corporation shall include protocols related to mitigating the public safety impacts of disabling reclosers and deenergizing portions of the electrical distribution system that consider the impacts on all of the following:
(A)Critical first responders.
(B)Health and communication infrastructure.
(C)Customers who receive medical baseline allowances pursuant to subdivision (c) of Section 739. The electrical corporation may deploy backup electrical resources or provide financial assistance for backup electrical resources to a customer receiving a medical baseline allowance for a customer who meets all of the following requirements:
(i)The customer relies on life-support equipment that operates on electricity to sustain life.
(ii)The customer demonstrates financial need, including through enrollment in the California Alternate Rates for Energy program created pursuant to Section 739.1.
(iii)The customer is not eligible for backup electrical resources provided through medical services, medical insurance, or community resources.
(D)Subparagraph (C) shall not be construed as preventing an electrical corporation from deploying backup electrical resources or providing financial assistance for backup electrical resources under any other authority.
(7)Appropriate and feasible procedures for notifying a customer who may be impacted by the deenergizing of electrical lines including procedures for those customers receiving a medical baseline allowance as described in paragraph (6). The procedures shall direct notification to all public safety offices, critical first responders, health care facilities, and operators of telecommunications infrastructure with premises within the footprint of potential deenergization for a given event.
(8)Plans for vegetation management.
(9)Plans for inspections of the electrical corporations electrical infrastructure.
(10)Protocols for the deenergization of the electrical corporations transmission infrastructure, for instances when the deenergization may impact customers who, or entities that, are dependent upon the infrastructure.
(11)A list that identifies, describes, and prioritizes all wildfire risks, and drivers for those risks, throughout the electrical corporations service territory, including all relevant wildfire risk and risk mitigation information that is part of the Safety Model Assessment Proceeding and the Risk Assessment Mitigation Phase filings. The list shall include, but not be limited to, both of the following:
(A)Risks and risk drivers associated with design, construction, operations, and maintenance of the electrical corporations equipment and facilities.
(B)Particular risks and risk drivers associated with topographic and climatological risk factors throughout the different parts of the electrical corporations service territory.
(12)A description of how the plan accounts for the wildfire risk identified in the electrical corporations Risk Assessment Mitigation Phase filing.
(13)A description of the actions the electrical corporation will take to ensure its system will achieve the highest level of safety, reliability, and resiliency, and to ensure that its system is prepared for a major event, including hardening and modernizing its infrastructure with improved engineering, system design, standards, equipment, and facilities, such as undergrounding, insulation of distribution wires, and pole replacement.
(14)A description of where and how the electrical corporation considered undergrounding electrical distribution lines within those areas of its service territory identified to have the highest wildfire risk in a commission fire threat map.
(15)A showing that the electrical corporation has an adequately sized and trained workforce to promptly restore service after a major event, taking into account employees of other utilities pursuant to mutual aid agreements and employees of entities that have entered into contracts with the electrical corporation.
(16)Identification of any geographic area in the electrical corporations service territory that is a higher wildfire threat than is currently identified in a commission fire threat map, and where the commission should consider expanding the high fire threat district based on new information or changes in the environment.
(17)A methodology for identifying and presenting enterprisewide safety risk and wildfire-related risk that is consistent with the methodology used by other electrical corporations unless the commission determines otherwise.
(18)A description of how the plan is consistent with the electrical corporations disaster and emergency preparedness plan prepared pursuant to Section 768.6, including both of the following:
(A)Plans to prepare for, and to restore service after, a wildfire, including workforce mobilization and prepositioning equipment and employees.
(B)Plans for community outreach and public awareness before, during, and after a wildfire, including language notification in English, Spanish, and the top three primary languages used in the state other than English or Spanish, as determined by the commission based on the United States Census data.
(19)A statement of how the electrical corporation will restore service after a wildfire.
(20)Protocols for compliance with requirements adopted by the commission regarding activities to support customers during and after a wildfire, outage reporting, support for low-income customers, billing adjustments, deposit waivers, extended payment plans, suspension of disconnection and nonpayment fees, repair processing and timing, access to electrical corporation representatives, and emergency communications.
(21)A description of the processes and procedures the electrical corporation will use to do all of the following:
(A)Monitor and audit the implementation of the plan.
(B)Identify any deficiencies in the plan or the plans implementation and correct those deficiencies.
(C)Monitor and audit the effectiveness of electrical line and equipment inspections, including inspections performed by contractors, carried out under the plan and other applicable statutes and commission rules.
(22)Any other information that the Wildfire Safety Division may require.
(d)The Wildfire Safety Division shall post all wildfire mitigation plans and annual updates on the commissions internet website for no less than two months before the divisions decision regarding approval of the plan. The division shall accept comments on each plan from the public, other local and state agencies, and interested parties, and verify that the plan complies with all applicable rules, regulations, and standards, as appropriate.
SEC. 2.(a)Section 1.1 of this bill incorporates amendments to Section 8386 of the Public Utilities Code proposed by both this bill and Senate Bill 167. That section of this bill shall only become operative if (1) both bills are enacted and become effective on or before January 1, 2020, (2) each bill amends Section 8386 of the Public Utilities Code, (3) Senate Bill 560 is not enacted or as enacted does not amend that section, and (4) this bill is enacted after Senate Bill 167, in which case Sections 1, 1.2, and 1.3 of this bill shall not become operative.
(b)Section 1.2 of this bill incorporates amendments to Section 8386 of the Public Utilities Code proposed by both this bill and Senate Bill 560. That section of this bill shall only become operative if (1) both bills are enacted and become effective on or before January 1, 2020, (2) each bill amends Section 8386 of the Public Utilities Code, (3) Senate Bill 167 is not enacted or as enacted does not amend that section, and (4) this bill is enacted after Senate Bill 560, in which case Sections 1, 1.1, and 1.3 of this bill shall not become operative.
(c)Section 1.3 of this bill incorporates amendments to Section 8386 of the Public Utilities Code proposed by this bill, Senate Bill 167, and Senate Bill 560. That section of this bill shall only become operative if (1) all three bills are enacted and become effective on or before January 1, 2020, (2) all three bills amend Section 8386 of the Public Utilities Code, and (3) this bill is enacted after Senate Bill 167 and Senate Bill 560, in which case Sections 1, 1.1, and 1.2 shall not become operative.
SEC. 3.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
|
Date
|
Status
|
|---|---|
| Oct 2, 2019 | Chaptered by Secretary of State. Chapter 400, Statutes of 2019. |
| Oct 2, 2019 | Approved by the Governor. |
| Sep 18, 2019 | Enrolled and presented to the Governor at 4 p.m. |
| Sep 11, 2019 | Assembly amendments concurred in. (Ayes 39. Noes 0.) Ordered to engrossing and enrolling. |
| Sep 11, 2019 | Ordered to special consent calendar. |
| Sep 10, 2019 | In Senate. Concurrence in Assembly amendments pending. |
| Sep 10, 2019 | Read third time. Passed. Ordered to the Senate. |
| Sep 5, 2019 | Read third time and amended. |
| Aug 20, 2019 | Read second time. Ordered to third reading. |
| Aug 19, 2019 | Read second time and amended. Ordered to second reading. |
| Aug 15, 2019 | From committee: Do pass as amended. (Ayes 18. Noes 0.) (August 14). |
| Jul 2, 2019 | Read second time and amended. Re-referred to Com. on APPR. |
| Jul 1, 2019 | From committee: Do pass as amended and re-refer to Com. on APPR. with recommendation: To consent calendar. (Ayes 14. Noes 0.) (June 26). |
| Jun 11, 2019 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on U. & E. |
| Jun 10, 2019 | Referred to Com. on U. & E. |
| May 22, 2019 | In Assembly. Read first time. Held at Desk. |
| May 21, 2019 | Read third time. Passed. (Ayes 37. Noes 0.) Ordered to the Assembly. |
| May 20, 2019 | Read second time. Ordered to third reading. |
| May 17, 2019 | From committee: Do pass as amended. (Ayes 6. Noes 0.) (May 16). |
| May 16, 2019 | May 16 set for first hearing. Reconsideration of favorable vote granted. |
| May 14, 2019 | Set for hearing May 16. |
| May 13, 2019 | May 13 hearing: Placed on APPR. suspense file. |
| May 3, 2019 | Set for hearing May 13. |
| Apr 30, 2019 | Read second time and amended. Re-referred to Com. on APPR. |
| Apr 29, 2019 | From committee: Do pass as amended and re-refer to Com. on APPR. (Ayes 13. Noes 0.) (April 24). |
| Apr 4, 2019 | Set for hearing April 24. |
| Apr 3, 2019 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on E., U. & C. |
| Mar 27, 2019 | Re-referred to Com. on E., U. & C. |
| Mar 19, 2019 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on RLS. |
| Jan 16, 2019 | Referred to Com. on RLS. |
| Jan 10, 2019 | From printer. May be acted upon on or after February 9. |
| Jan 9, 2019 | Introduced. Read first time. To Com. on RLS. for assignment. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Sep 11, 2019 | Unfinished Business SB70 Nielsen Concurrence | Senate Floor |
Passed |
|
| Sep 10, 2019 | SB 70 Nielsen Senate Third Reading By Bloom | Assembly Floor |
Passed |
|
| Aug 14, 2019 | Do pass as amended. | Assembly Standing Committee on Appropriations |
Passed |
|
| Jun 26, 2019 | Do pass as amended, and be re-referred to the Committee on [Appropriations] with recommendation: To Consent Calendar | Assembly Standing Committee on Utilities and Energy |
Passed |
|
| May 21, 2019 | Senate 3rd Reading SB70 Nielsen | Senate Floor |
Passed |
|
| May 16, 2019 | Do pass as amended | Senate Standing Committee on Appropriations |
Passed |
|
| May 16, 2019 | [05-16-2019] set for [First] hearing: Reconsideration of favorable vote granted | Senate Standing Committee on Appropriations |
Passed |
|
| May 16, 2019 | Do pass | Senate Standing Committee on Appropriations |
Passed |
|
| May 13, 2019 | Placed on suspense file | Senate Standing Committee on Appropriations |
Passed |
|
| Apr 24, 2019 | Do pass as amended, but first amend, and re-refer to the Committee on [Appropriations] | Senate Standing Committee on Energy, Utilities and Communications |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 70 |
UNFINISHED BUSINESS
Bill No: SB 70
Amended: 9/5/19
SENATE ENERGY, U. & C. COMMITTEE: 13-0, 4/24/19
AYES: Hueso, Moorlach, Bradford, Chang, Dodd, Hertzberg, Hill, McGuire, Rubio, Skinner, Stern, Stone, Wiener
SENATE APPROPRIATIONS COMMITTEE: 6-0, 5/16/19
AYES: Portantino, Bates, Bradford, Hill, Jones, Wieckowski
SENATE FLOOR: 38-0, 5/21/19
AYES: Allen, Archuleta, Atkins, Bates, Beall, Borgeas, Bradford, Caballero, Chang, Dodd, Durazo, Galgiani, Glazer, Grove, Hertzberg, Hill, Hueso, Hurtado, Jackson, Jones, Leyva, McGuire, Mitchell, Monning, Moorlach, Morrell, Nielsen, Pan, Portantino, Roth, Rubio, Skinner, Stern, Stone, Umberg, Wieckowski, Wiener, Wilk
ASSEMBLY FLOOR: 79-0, 9/10/19 - See last page for vote
SUBJECT: Electricity: undergrounding of electrical distribution infrastructure
DIGEST:
This bill requires each electrical corporation’s wildfire mitigation plan to additionally include a description of where and how the electrical corporation considered undergrounding electrical distribution lines within those areas of its service territory identified to have the highest wildfire risk in a specified fire threat map.
Assembly Amendments
delete provisions that would have established a working group on joint trenching activities and established several findings and declarations. The amendments also address chaptering issues with SB 167 (Dodd) and SB 560 (McGuire).
Existing law:
- Provides that the California Public Utilities Commission (CPUC) has regulatory authority over public utilities, including investor-owned utilities (IOUs). (California Constitution, Article 12)
- Declares that it is the policy of the state to achieve, whenever feasible and not inconsistent with sound environmental planning, the undergrounding of all future electric and communication distribution facilities which are proposed to be erected in proximity to any highway designated a state scenic highway and which would be visible from such scenic highways if erected above ground. (Public Utilities Code §320)
- Requires the CPUC to develop formal procedures to incorporate safety in a rate case application by an IOU or gas corporations. (Public Utilities Code §750)
- Requires each IOU to construct, maintain, and operate its electrical lines and equipment in a manner that will minimize the risk of catastrophic wildfire posed by those electrical lines and equipment. Requires each IOU to annually prepare and submit a wildfire mitigation plan to the CPUC for review and approval. Requires those wildfire mitigation plans to include specified information, including protocols for disabling reclosers and deenergizing portions of the electrical distribution system that consider the associated impacts on public safety, as well as protocols related to mitigating the public safety impacts of those protocols, including impacts on critical first responders and on health and communication infrastructure. (Public Utilities Code §8386)
- Establishes the Wildfire Safety Division of the CPUC to Oversee and enforce electrical corporations’ compliance with wildfire safety, as specified. (Public Utilities Code §326)
This bill requires each electrical corporation’s wildfire mitigation plan to additionally include a description of where and how the electrical corporation considered undergrounding electrical distribution lines within those areas of its service territory identified to have the highest wildfire risk in a specified fire threat map.
Background
Undergrounding of electric facilities. Undergrounding is the process of replacing overhead lines that provide services such as electricity or communications with lines located underground. The undergrounding of electrical and communications lines is typically done for aesthetic or safety purposes in order to remove the visible overhead lines and poles or to reduce the risk of damage or fire from being exposed to the elements. Undergrounding is generally much more expensive relative to overhead infrastructure – on the order of 10 times or more. However, operating costs may be less assuming the underground results in a reduced need to repair damaged lines. Nonetheless, the costs for undergrounding lines can vary depending on the location of the lines: rural, urban, or suburban communities.
California Overhead Conversion Program, Electric Tariff Rule 20. The CPUC requires IOUs to allocate a certain amount of ratepayer funds each year for undergrounding conversion projects. The electric utility annually allocates funds via credits under Electric Tariff Rule 20 to communities, either cities or unincorporated areas of counties, to convert overhead electric lines to underground facilities. Since ratepayers contribute the bulk of the costs of Rule 20A programs through utility rates, the projects must be in the public interest, meeting specified criteria. The CPUC instituted the current undergrounding program in 1967 and has made mostly slight adjustments to the program over the 50 years. In 2014, the CPUC authorized San Diego Gas and Electric (SDG&E) the ability to consider wildfires when converting electric facilities to underground. The CPUC agreed with SDG&E that undergrounding could mitigate the risks of wildfires in the more fire-prone areas of SDG&E’s service territory. The CPUC approved a SDG&E specific version of Rule 20D that is modeled on Rule 20A, but targeted to the most fire-prone areas.
Local jurisdiction contributions. Under the Improvement Act (Act) of 1911, cities, counties and other municipal governments are authorized to designate areas within which public agencies officials and individual property owners may enter into contractual assessments to finance a wide range of public infrastructure projects. An assessment district is formed as an alternative method for financing public improvements by a sponsoring local government agency. One type of assessment district that the Act authorizes is an underground utility district (UUD), which is formed for the purposes of converting above ground infrastructure to below ground. UUDs are formed via petition or by a determination of the legislative body. Current law requires a legislative body to determine that the city or a public utility has voluntarily agreed to pay over 50 percent of all costs of conversion, excluding costs of users' connections to underground electric or communication facilities in order to initiate proceedings.
CPUC High Fire-Threat District. The CPUC’s efforts to map high-fire threat stem from the catastrophic wildfires caused by utility infrastructure in San Diego County in the 2000s. The CPUC mapping efforts combine the Tree Mortality Taskforce Map with CPUC/Cal FIRE Tier 2 and Tier 3 designations. Tier 2 fire-threat areas depict areas where there is an elevated risk (including likelihood and potential impacts on people and property) from utility associated wildfires. Tier 3 fire-threat areas depict areas where there is an extreme risk (including likelihood and potential impacts on people and property) from utility associated wildfires.
Wildfire mitigation plans. Per statute, electric utilities must file wildfire mitigation plans with specified information. In the recently filed plans, some of the electric utilities considered the potential to underground some electric lines as part of their wildfire mitigation efforts. However, in most instances, the electric utilities’ wildfire mitigation plans included the potential to underground lines but recommended an assessment to identify what electric lines were both feasible and made financial sense to underground. As one electric corporation’s plan noted: “While underground systems can help reduce the risk of wildfires and increase reliability during high winds and storms, they also take longer and costs much more to construct, maintain, and repair – particularly in mountainous regions and those with steep terrain.” In general, the electric utilities are incorporating other wildfire mitigation efforts that are more cost-effective, including conductor covers, replacing wooden poles with poles made of more fire-resistant materials, and other mitigation actions.
SB 70. This bill requires each electrical corporation’s wildfire mitigation plan to additionally include a description of where and how the electrical corporation considered undergrounding electrical distribution lines within those areas of its service territory identified to have the highest wildfire risk in the CPUC high fire threat district map.
Impact to ratepayers? This bill does not require any undergrounding of electrical infrastructure activities. However, to the extent undergrounding electric infrastructure is identified as a mitigation strategy within the wildfire mitigation plan, it is possible that electric utility ratepayers for the given utility may have to pay a portion or all of the costs – which could be substantial – to underground those lines. However, to the extent undergrounding prevents wildfires and the associated costs of the wildfires, ratepayers could benefit from the decreased risk of a wildfire ignited by the electrical lines.
Related/Prior Legislation
AB 1054 (Holden, Chapter 79, Statutes of 2019) included numerous provisions related to addressing wildfires caused by electric utility infrastructure, including: bolstering safety oversight and processes, such as required updates to each electric corporation’s wildfire mitigation plans, recasting recovery of costs from damages to third-parties, including the authorization for an electrical corporation and ratepayer jointly funded Wildfire Fund to address future damages, and changes to provisions concerning the workforce of a change of ownership of a full or portion of an electrical or gas corporation.
SB 584 (Moorlach, 2019) would have made changes to programs that help fund conversion projects to replace overhead electrical infrastructure with underground electrical infrastructure in specified areas of the service territory of IOUs. The bill was held in the Senate Committee on Appropriations.
SB 901 (Dodd, Chapter 626, Statutes of 2018) addressed numerous issues concerning wildfire prevention, response and recovery, including funding for mutual aid, fuel reduction and forestry policies, wildfire mitigation plans by electric utilities, and cost recovery by electric corporations of wildfire-related damages.
SB 1028 (Hill, Chapter 598, Statutes of 2016) required electric CPUC-regulated utilities to file annual wildfire mitigation plans and requires the CPUC to review and comment on those plans.
SB 1463 (Moorlach, 2016) would have required the CPUC, in consultation with the Cal FIRE, to prioritize areas where communities are subject to conditions that increase fire hazards associated with overhead utility facilities when determining areas which it will require enhanced mitigation measures for wildfire hazards posed by overhead electrical lines and equipment. The bill was vetoed.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
According to the Assembly Appropriations Committee, negligible costs to the CPUC. Existing statute already requires each electrical corporation to annually prepare and submit a wildfire mitigation plan to the CPUC, requires the CPUC, in consultation with Cal FIRE, to review and approve. Inclusion of an additional element in the plan on the corporation’s consideration of undergrounding should not increase CPUC’s workload beyond what the CPUC could accommodate within existing resources.
City of Malibu
None received
ARGUMENTS IN SUPPORT: According to the author:
As a matter of public safety to California residents as well as electrical utility reliability, something must be done to address threatening aboveground lines in high fire hazard severity zones.
Undergrounding distribution lines may be the answer. Underground electrical lines have many benefits: they are better insulated than overhead electrical lines, are less likely to be affected by hazardous weather conditions and animals, and are better protected from wildfires.
ASSEMBLY FLOOR: 79-0, 9/10/19
AYES: Aguiar-Curry, Arambula, Bauer-Kahan, Berman, Bigelow, Bloom, Boerner Horvath, Bonta, Brough, Burke, Calderon, Carrillo, Cervantes, Chau, Chen, Chiu, Choi, Chu, Cooley, Cooper, Cunningham, Daly, Diep, Eggman, Flora, Fong, Frazier, Friedman, Gabriel, Gallagher, Cristina Garcia, Eduardo Garcia, Gipson, Gloria, Gonzalez, Gray, Grayson, Holden, Irwin, Jones-Sawyer, Kalra, Kamlager-Dove, Kiley, Lackey, Levine, Limón, Low, Maienschein, Mathis, Mayes, McCarty, Medina, Melendez, Mullin, Muratsuchi, Nazarian, Obernolte, O'Donnell, Patterson, Petrie-Norris, Quirk, Quirk-Silva, Ramos, Reyes, Luz Rivas, Robert Rivas, Rodriguez, Blanca Rubio, Salas, Santiago, Smith, Mark Stone, Ting, Voepel, Waldron, Weber, Wicks, Wood, Rendon
Prepared by: Nidia Bautista / E., U., & C. / (916) 651-4107
9/10/19 22:08:23
**** END ****
SENATE THIRD READING
STR Bill Id:SB 70
Author:(Nielsen)
As Amended Ver:September 5, 2019
Majority vote
SUMMARY:
This bill requires all investor-owned electric utilities (IOUs) to include in their wildfire mitigation plans (WMPs) a description of where and how the IOU considered undergrounding electrical distribution lines within those areas of its service territory identified to have the highest wildfire risk in a commission fire threat map. It also contains provisions to avoid chaptering issues associated with two other Senate bills.
Major Provisions
COMMENTS:
The WMPs are at the core of the CPUC's efforts to actually reduce the risk and occurrence of catastrophic wildfires caused by utility infrastructure which have devastated California in recent years. Undergrounding is referenced as a hardening measure for use in WMPs but it is not mandated. The IOUs may request funding within general rate cases to convert existing overhead electric system equipment to undergrounding if there is a compelling risk reduction reason for such an investment. Application of those elements through the WMP is unique for each utility, its regions, and its wildfire risk exposure. This bill would require the IOUs to, in essence, "show their work" and include a description of where and how the IOU considered undergrounding electrical distribution lines within areas of highest fire threat.
According to the Author:
In recent years, California's catastrophic wildfires have caused grave damage to aboveground electrical infrastructure, disrupting electrical grid reliability and threatening the transmission and distribution of electricity. More frequently, some of the most devastating fires have been ignited by the same aboveground infrastructure. Just a few of these fires include the Camp Fire, which ravaged the communities of Paradise, Magalia, and the Ridge in Butte County.
As a matter of public safety to California residents as well as electrical utility reliability, something must be done to address threatening aboveground lines in high fire hazard severity zones. Undergrounding distribution lines may be the answer. Californians must harden their utility infrastructure, in order to live with wildfires and to reduce the risk of future catastrophic wildfires. Undergrounding is not just an investment in reliable infrastructure, but an investment in lives,
Arguments in Support:
There is no registered support for this version of this bill.
Arguments in Opposition:
There is no registered opposition for this version of this bill.
FISCAL COMMENTS:
According to the Assembly Appropriations Committee, negligible costs to the CPUC. Existing statute already requires each IOU to annually prepare and submit a WMP to the CPUC, requires the CPUC, in consultation with the Department of Forestry and Fire Protection (CalFire), to review and approve. Inclusion of an additional element in the plan on the IOU's consideration of undergrounding should not increase CPUC's workload beyond what the CPUC could accommodate within existing resources.
VOTES:
SENATE FLOOR: 38-0-0
YES: Allen, Archuleta, Atkins, Bates, Beall, Borgeas, Bradford, Caballero, Chang, Dodd, Durazo, Galgiani, Glazer, Grove, Hertzberg, Hill, Hueso, Hurtado, Jackson, Jones, Leyva, McGuire, Mitchell, Monning, Moorlach, Morrell, Nielsen, Pan, Portantino, Roth, Rubio, Skinner, Stern, Stone, Umberg, Wieckowski, Wiener, Wilk
ASM UTILITIES AND ENERGY: 14-0-1
YES: Holden, Patterson, Burke, Carrillo, Chen, Cunningham, Eggman, Cristina Garcia, Mayes, Muratsuchi, Quirk, Reyes, Santiago, Ting
ABS, ABST OR NV: Eduardo Garcia
ASM APPROPRIATIONS: 18-0-0
YES: Gonzalez, Bigelow, Bloom, Bonta, Brough, Calderon, Carrillo, Chau, Diep, Eggman, Fong, Gabriel, Eduardo Garcia, Maienschein, Obernolte, Petrie-Norris, Quirk, Robert Rivas
UPDATED:
VERSION: September 5, 2019
CONSULTANT: Kellie Smith / U. & E. / (916) 319-2083 FN: 0001749
SENATE THIRD READING
STR Bill Id:SB 70
Author:(Nielsen)
As Amended Ver:August 19, 2019
Majority vote
SUMMARY:
This bill requires all investor-owned electric utilities (IOUs) to include in their wildfire mitigation plans (WMPs) a description of where and how the IOU considered undergrounding electrical distribution lines within those areas of its service territory identified to have the highest wildfire risk in a commission fire threat map.
COMMENTS:
The WMPs are at the core of the California Public Utilities Commission (CPUC's) efforts to actually reduce the risk and occurrence of catastrophic wildfires caused by utility infrastructure which have devastated California in recent years. Undergrounding is referenced as a hardening measure for use in WMPs but it is not mandated. The IOUs may request funding within general rate cases to convert existing overhead electric system equipment to undergrounding if there is a compelling risk reduction reason for such an investment. Application of those elements through the WMP is unique for each utility, its regions, and its wildfire risk exposure. This bill would require the IOUs to, in essence, "show their work" and include a description of where and how the IOU considered undergrounding electrical distribution lines within areas of highest fire threat.
According to the Author:
In recent years, California's catastrophic wildfires have caused grave damage to aboveground electrical infrastructure, disrupting electrical grid reliability and threatening the transmission and distribution of electricity. More frequently, some of the most devastating fires have been ignited by the same aboveground infrastructure. Just a few of these fires include the Camp Fire, which ravaged the communities of Paradise, Magalia, and the Ridge in Butte County.
As a matter of public safety to California residents as well as electrical utility reliability, something must be done to address threatening aboveground lines in high fire hazard severity zones. Undergrounding distribution lines may be the answer. Californians must harden their utility infrastructure, in order to live with wildfires and to reduce the risk of future catastrophic wildfires. Undergrounding is not just an investment in reliable infrastructure, but an investment in lives.
Arguments in Support:
There is no registered support for this version of this bill.
Arguments in Opposition:
There is no registered opposition for this version of this bill.
FISCAL COMMENTS:
According to the Assembly Appropriations Committee, negligible costs to the CPUC. Existing statute already requires each IOU to annually prepare and submit a WMP to the CPUC, requires the CPUC, in consultation with the Department of Forestry and Fire Protection (CalFire), to review and approve. Inclusion of an additional element in the plan on the IOU's consideration of undergrounding should not increase CPUC's workload beyond what the CPUC could accommodate within existing resources.
VOTES:
SENATE FLOOR: 38-0-0
YES: Allen, Archuleta, Atkins, Bates, Beall, Borgeas, Bradford, Caballero, Chang, Dodd, Durazo, Galgiani, Glazer, Grove, Hertzberg, Hill, Hueso, Hurtado, Jackson, Jones, Leyva, McGuire, Mitchell, Monning, Moorlach, Morrell, Nielsen, Pan, Portantino, Roth, Rubio, Skinner, Stern, Stone, Umberg, Wieckowski, Wiener, Wilk
ASM UTILITIES AND ENERGY: 14-0-1
YES: Holden, Patterson, Burke, Carrillo, Chen, Cunningham, Eggman, Cristina Garcia, Mayes, Muratsuchi, Quirk, Reyes, Santiago, Ting
ABS, ABST OR NV: Eduardo Garcia
ASM APPROPRIATIONS: 18-0-0
YES: Gonzalez, Bigelow, Bloom, Bonta, Brough, Calderon, Carrillo, Chau, Diep, Eggman, Fong, Gabriel, Eduardo Garcia, Maienschein, Obernolte, Petrie-Norris, Quirk, Robert Rivas
UPDATED:
VERSION: August 19, 2019
CONSULTANT: Kellie Smith / U. & E. / (916) 319-2083 FN: 0001407
Date of Hearing: August 14, 2019
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Lorena Gonzalez, Chair
SBPCA Bill Id:SB 70
Author:(Nielsen) – As Amended Ver:July 2, 2019
Policy Committee: | Utilities and Energy | Vote: | 14 - 0 |
|
| ||
|
|
Urgency: No State Mandated Local Program: Yes Reimbursable: No
SUMMARY:
This bill requires each electrical corporation to report on its consideration of undergrounding electrical wires in high fire-risk areas.
Specifically, this bill requires each electrical corporation to include in its annual wildfire mitigation plan, to be submitted to the California Public Utilities Commission (CPUC) pursuant to existing law, a description of where and how the electrical corporation considered undergrounding electrical distribution lines within those areas of the corporation’s service territory identified in a CPUC fire threat map to have the highest wildfire risk. The bill also makes several findings and declarations asserting the properties and fire-risk benefits of undergrounding electrical wires, the harms caused by wildfires and calling for fuel breaks and hardening of infrastructure to better fight, and to reduce the risk of, catastrophic wildfires.
FISCAL EFFECT:
Negligible costs to the CPUC. Existing statute already requires each electrical corporation to annually prepare and submit a wildfire mitigation plan to the CPUC, requires the CPUC, in consultation with the Department of Forestry and Fire Protection (Calfire), to review and approve. Inclusion of an additional element in the plan on the corporation’s consideration of undergrounding should not increase CPUC’s workload beyond what the CPUC could accommodate within existing resources.
COMMENTS:
Background and Purpose. In 2016, the Legislature passed legislation—SB 1028 (Hill), Chapter 598, Statutes of 2016—to require the state’s electrical corporations, such as Pacific Gas and Electric (PG&E), Southern California Edison (SCE) and San Diego Gas and Electric (SDG&E), to annually file wildfire mitigation plans with the CPUC. Subsequent legislation—SB 901 (Dodd), Chapter 626, Statutes of 2018—modified the planning requirement to include additional and more detailed information. Among that additional information is “system hardening,” though statute does not specifically require the plan to discuss consideration of undergrounding of electrical lines.
The CPUC has a process by which an electrical corporation my convert overhead lines to underground lines. Traditionally, the process has considered environmental and aesthetic aspects of electrical lines. The CPUC has an open proceeding to consider its rules and procedures regarding converting overhead lines to underground lines.
The bill asserts the Legislature finds and declares a number of factual statements regarding the attributes and characteristics of underground electrical lines, about wildfires and the location of ignition sources of wildfires in 2017 and 2018, and actions Californians will need to take to adapt to and mitigate the risk of wildfires. The author provided the committee with no substantiation of any of these factual claims. According to the CPUC, these findings are largely unfounded, other than the claim in subparagraph (d), which states: wildfires disrupt electrical grid reliability and threaten the transmission and distribution of electricity.
The scope of this bill is narrow. The bill’s operative provision—that electrical utilities report on their consideration of undergrounding electrical distribution lines in fire prone areas—are wholly independent of the bill’s findings and declarations.
The relative efficacy—and cost effectiveness—of undergrounding of an electrical line as a wildfire prevention measure is highly dependent upon real-world conditions. The electrical corporations and others are considering the undergrounding of electrical lines as a fire prevention measure and as a general safety measure in the case of, for example, emergency evacuation. Some communities are pushing such undergrounding as a general rule. The CPUC, along with the state emergency preparation and response agencies will consider specific proposals in their specific contexts and determine whether, in each specific case, undergrounding indeed decreases the risk or wildfires, whether it is the most cost-effective means of mitigating wildfire risk and whether it is reasonable to pass the costs of undergrounding on to electrical utility ratepayers.
The Legislature should be cautious about making general declarations about attributes and efficacy of undergrounding in the absence of empirical evidence. With such caution in mind, the committee may wish to consider striking the findings and declarations from the bill.
Analysis Prepared by: Jay Dickenson / APPR. / (916) 319-2081
Date of Hearing: June 26, 2019
ASSEMBLY COMMITTEE ON UTILITIES AND ENERGY
Chris Holden, Chair
SBPCA Bill Id:SB 70
Author:(Nielsen) – As Amended Ver:June 11, 2019
SENATE VOTE: 38-0
SUBJECT: Electricity: undergrounding of electrical infrastructure
SUMMARY: Establishes the Electrical Infrastructure Undergrounding Working Group (Group) to promote undergrounding of electrical infrastructure and implementation of a statewide joint trenching policy. Specifically, this bill:
- Creates the Group, contingent on funding by the Legislature, generally in state government, consisting of representatives from the following entities:
- California Public Utilities Commission (CPUC)
- The Department of Forestry and Fire Protection (CAL FIRE)
- Office of Emergency Services
- Department of Transportation
- California State Association of Counties
- League of California Cities
- Rural County Representatives of California
- California Underground Facilities Safe Excavation Board.
- Directs the Group to develop a statewide joint trenching policy and prioritize undergrounding of distribution lines along streets and highways that serve as county-designated evacuation routes with a focus on areas affected by wildfires from 2013 to 2020 during the rebuilding and restoration phases of those areas.
- Adds a requirement to wildfire mitigation plans (WMPs), filed annually by electrical corporations (IOUs), that the plan describe where and how the IOU considered undergrounding electrical distribution lines within those areas of its service territory identified to have the highest wildfire risk in a CPUC fire threat map.
- Makes a number of findings and declarations related to the benefits of undergrounding electrical lines.
EXISTING LAW:
- Declares that it is the policy of the state to achieve, whenever feasible and not inconsistent with sound environmental planning, the undergrounding of all future electric and communication distribution facilities which are proposed to be erected in proximity to any highway designated a state scenic highway and which would be visible from such scenic highways if erected above ground. (Public Utilities Code § 320)
- Requires IOUs to implement the California Overhead Conversion Program to provide financial assistance to local governments to facilitate undergrounding of distribution lines which are in the public interest and meet specified criteria. (CPUC Electric Tariff Rule 20)
- Requires IOUs to construct, maintain, and operate electrical lines and equipment in a manner that minimizes risk of catastrophic wildfire and annually submit WMPs to the CPUC for review and approval. (Public Utilities Code § 8386)
- Requires IOU WMPs to include a description of the actions the IOU will take to ensure its system will achieve the highest level of safety, reliability, and resiliency, and to ensure that its system is prepared for a major event, including hardening and modernizing its infrastructure with improved engineering, system design, standards, equipment, and facilities, such as undergrounding, insulation of distribution wires, and pole replacement (Public Utilities Code § 8386 [c][12])
- Requires the undergrounding of all distribution line extensions for all new residential subdivisions and developments, commercial developments, industrial developments, and locations that are in proximity to and visible from designated scenic areas, except as specified. (CPUC Electric Tariff Rules 15 & 16)
FISCAL EFFECT: According to the Senate Appropriations Committee, while the establishment of the Group would be subject to an appropriation, the bill could result in one-time General Fund cost pressure of about $1 million for the CPUC to convene and lead the statewide working group.
BACKGROUND:
Wildfire Mitigation Plans – A wildfire mitigation plan (WMP) represents future activity to reduce the likelihood that utility infrastructure is the source of a catastrophic wildfire ignition and to make utility infrastructure more resistant to wildfire. The plans were first mandated for IOUs by the Legislature in 2016. Senate Bill 1029 (Hill) required IOUs to file annual WMPs and required the CPUC to review and comment on those plans. Local publicly owned utilities (POU) and electrical cooperatives were also required to determine the risk of catastrophic wildfire that could be caused by their electric lines and equipment and, if a risk existed, submit WMPs to their respective governing boards for approval.
Senate Bill 901 in 2018 modified WMP requirements in a number of ways, including requiring a more nuanced and detailed list of information that the IOUs must provide in their annual filings. A minimum of nineteen elements are required which were specified in SB 901 and can be expanded by the CPUC. The central elements are:
- Inspection and maintenance;
- Vegetation management;
- System hardening;
- Situational awareness;
- De-energization;
- Disaster preparedness and customer outreach; and
- Metrics for evaluation.
Overhead Line Conversion, Rule 20 – The CPUC promulgated the first rules concerning service connections and overhead conversion based on the desires and priorities of local communities in the late 1960s. For IOUs, these rules became Rule 20, and Rule 20A specifically concerns the Overhead Utility Conversion Program for the three largest IOUs.
The program was initially viewed as an environmental initiative – a means for environmental improvement and beautification, enabling overhead conversion projects in a consistent manner throughout California in public areas blighted by urban congestion. When first developed, Rule 20A was recognized as a new and unique program but with uncertainty over its implementation and impact.
Under Rule 20A all planning, design and construction work is performed by the IOU and once completed, the IOU is compensated based on the project costs, which are to be covered using the local government’s Rule 20A credits. The IOUs then receive compensation for the credits through subsequent general rate case proceedings.
In order for a project to qualify for the Rule 20A program, in addition to meeting the requirements of having a conversion plan and underground utility district, the project itself must have a public benefit and meet the following criteria:
- Eliminate an unusually heavy concentration of overhead lines;
- Involve a street or road with a high volume of public traffic;
- Benefit a civic or public recreation area or area of unusual scenic interest; and,
- Be listed as an arterial street or major collector as defined in the Governor’s Office of Planning and Research (OPR) Guidelines.
In a 2016 report, the CPUC reported that while Rule 20A has been effective in meeting its original goal of facilitating conversion projects that are in the public interest, credits have been allocated annually to municipalities over many years using a formula that does not take into account whether a municipality has any planned overhead conversion projects. As a result, sizable credit balances have built up over the years, cumulatively totaling over $1 billion in liabilities and pose a potential financial risk to IOU ratepayers.
In response the CPUC initiated a rulemaking in 2017 (R.17-05-010) to address program deficiencies. That rulemaking remains open and will consider changes to Electric Tariff Rule 20 in order to enhance the fair, efficient allocation of ratepayer funds to communities for the undergrounding of electric infrastructure. The proceeding is also examining whether to modify the “public interest” criteria to balance the trade-offs between promoting safety and reliability versus concerns of resiliency and recovery.
COMMENTS:
- Author’s Statement. According to the author, in recent years, California’s catastrophic wildfires have caused grave damage to aboveground electrical infrastructure, disrupting electrical grid reliability and threatening the transmission and distribution of electricity. More frequently, some of the most devastating fires have been ignited by the same aboveground infrastructure. Just a few of these fires include the Camp Fire, which ravaged the communities of Paradise, Magalia, and the Ridge in Butte County.
As a matter of public safety to California residents as well as electrical utility reliability, something must be done to address threatening aboveground lines in high fire hazard severity zones. Undergrounding distribution lines may be the answer. Underground electrical lines have many benefits: they are better insulated than overhead electrical lines, are less likely to be affected by hazardous weather conditions and animals, and are better protected from wildfires.
Underground lines also generally have a longer lifespan and create less interference with other communication infrastructure, than overhead electrical lines.
Californians must harden their utility infrastructure, in order to live with wildfires and to reduce the risk of future catastrophic wildfires. Undergrounding is not just an investment in reliable infrastructure, but an investment in lives.
- Wildfire Mitigation Plans. The plans are at the core of the CPUC’s efforts to actually reduce the risk and occurrence of catastrophic wildfires caused by utility infrastructure which have devastated California in recent years. Undergrounding is referenced as a hardening measure for use in WMPs but it is not mandated. The IOUs may request funding within general rate cases to convert existing overhead electric system equipment to undergrounding if there is a compelling risk reduction reason for such an investment. Application of those elements through the WMP is unique for each utility, its regions, and its wildfire risk exposure. This bill would require the IOUs to, in essence, “show their work” and include a description of where and how the IOU considered undergrounding electrical distribution lines within areas of highest fire threat.
- New Safety Consideration – Evacuations. Some local governments have expressed an interest in having poles and wires undergrounded to facilitate evacuations in emergency situations such as wildfires. Reports from the November 2018 Camp Fire were that distribution poles and wires fell across roads causing roadblocks and adversely impacting evacuation. The safety work of the IOUs through the WMPs does not address this issue. As mandated in SB 901, the safety work of utilities is now focused on preventing ignition of fires. However, the IOUs Rule 20A program is under review by the CPUC and among the issues being addressed is an additional program element of safety which would afford local governments an avenue to address undergrounding for safety relative to evacuations.
- Group Value? The author expresses very real concerns about fire safety and utility infrastructure. However, the committee has received no information as to what exact value, training or expertise a group of statewide representatives would add to the development and implementation of wildfire safety measures by the IOUs to be deployed in its different regions to address myriad fire risks. The pros and cons and costs of undergrounding are known; the technical implementation of undergrounding, is known. Nor is it apparent that the representatives of this Group have the technical background or time to weigh the many variables that go into the deployment of different safety measures on the ground.
There may be a very real need for local governments to consider where undergrounding or other safety measures are needed to facilitate evacuations, regardless of the source of ignition of a fire. The CPUC has under consideration expansion of Rule 20 to address safety needs which could allow those local communities to use Rule 20 to seek undergrounding for safety needs it identifies.
Consideration of undergrounding among the safety measures to be deployed by IOUs, is an ongoing part of annual WMP development. Consequently, the committee may wish to consider striking the creation of the Electrical Infrastructure Undergrounding Working Group which would be mandated by this bill.
- Skilled Workforce Restrictions. This bill presents the opportunity to make the committee aware of workforce constraints on the ground relative to the safety of utility infrastructure. Electric linesmen do the bulk of the work needed to harden electrical infrastructure including undergrounding and insulation of lines, replacement of wooden poles with steel poles, and repair and replacement of equipment to address ongoing safety and after an equipment failure caused by, for example, extreme weather events. These skilled trades are stretched thin as a result of the aggressive safety work being implemented by the utilities. We have heard anecdotal reports that workers are coming into the state from all over the west due to the significant demand for these workers, and linesmen are migrating from the POUs to the IOUs due to higher wage opportunities.
- Related Legislation.
AB 281 (Frazier) Requires IOUs to develop and administer programs to replace overhead electric facilities along public streets and roads, and on other public or private properties in high fire threat districts, as determined by the commission, with underground electric facilities. Status: Held in Assembly Utilities & Energy Committee
SB 584 (Moorlach) Establishes a program to provide grants to local jurisdictions for overhead line conversion projects in Tier 3 High Fire Threat Districts; funded from Greenhouse Gas Reduction Funds. Status: Held in Senate Appropriations Committee.
- Prior Legislation.
SB 1463 (Moorlach) would have required the CPUC, in consultation with the Cal FIRE, to prioritize areas where communities are subject to conditions that increase fire hazards associated with overhead utility facilities when determining areas which it will require enhanced mitigation measures for wildfire hazards posed by overhead electrical lines and equipment. Status: Vetoed, 2016.
SB 901 (Dodd) Establishes a comprehensive framework to address and prevent catastrophic wildfires including prevention and planning by the state's electric utilities, management of the state's forests, chaparrals, and other lands to prevent and defend against wildfires, and standards to stabilize IOUs in the event of extensive liability resulting from claims under inverse condemnation. Status: Chapter 626, Statutes of 2018.
SB 1028 (Hill) Requires IOUs to file annual wildfire mitigation plans and requires the CPUC to review and comment on those plans. Also required POUs and electrical co-ops to determine their risk of catastrophic wildfire that can be caused by their electric lines and equipment and, if a risk exists, submit wildfire mitigation plans to their governing board for approval. Status: Chapter 598, Statutes of 2016.
REGISTERED SUPPORT / OPPOSITION:
Support
City of Malibu
Opposition
None on file.
Analysis Prepared by: Kellie Smith / U. & E. /
Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 70 |
THIRD READING
Bill No: SB 70
Amended: 5/17/19
SENATE ENERGY, U. & C. COMMITTEE: 13-0, 4/24/19
AYES: Hueso, Moorlach, Bradford, Chang, Dodd, Hertzberg, Hill, McGuire, Rubio, Skinner, Stern, Stone, Wiener
SENATE APPROPRIATIONS COMMITTEE: 6-0, 5/16/19
AYES: Portantino, Bates, Bradford, Hill, Jones, Wieckowski
SUBJECT: Electricity: undergrounding of electrical distribution infrastructure
DIGEST:
This bill establishes an Electrical Infrastructure Undergrounding Working Group (EIUWG) to focus undergrounding activities for areas affected by wildfires, during the rebuilding and restoration phases. This bill also requires each electrical corporation’s wildfire mitigation plan to additionally include a description of where and how the electrical corporation considered undergrounding electrical distribution lines within those areas identified with the highest wildfire risk.
Existing law:
- Provides that the California Public Utilities Commission (CPUC) has regulatory authority over public utilities, including investor-owned utilities (IOUs). (California Constitution, Article 12)
- Declares that it is the policy of the state to achieve, whenever feasible and not inconsistent with sound environmental planning, the undergrounding of all future electric and communication distribution facilities which are proposed to be erected in proximity to any highway designated a state scenic highway and which would be visible from such scenic highways if erected above ground. (Public Utilities Code §320)
- Requires the CPUC to develop formal procedures to incorporate safety in a rate case application by an IOU or gas corporations. (Public Utilities Code §750)
- Requires each IOU to construct, maintain, and operate its electrical lines and equipment in a manner that will minimize the risk of catastrophic wildfire posed by those electrical lines and equipment. Requires each IOU to annually prepare and submit a wildfire mitigation plan to the CPUC for review and approval. Requires those wildfire mitigation plans to include specified information, including protocols for disabling reclosers and deenergizing portions of the electrical distribution system that consider the associated impacts on public safety, as well as protocols related to mitigating the public safety impacts of those protocols, including impacts on critical first responders and on health and communication infrastructure. (Public Utilities Code §8386)
This bill:
- Makes a number of findings and declarations related to the benefits of undergrounding electrical lines.
- Establishes the EIUWG in state government, upon appropriation by the Legislature, to promote the undergrounding of electrical infrastructure and the implementation of a statewide joint trenching policy. Requires the EIUWG to focus on areas affected by wildfires from 2013 to 2020 during the rebuilding and restoration phases of those areas. Requires the EIUWG to prioritize undergrounding along those streets and highways that serve as county-designated evacuation routes.
- Requires EIUWG to consist of representatives from all of the following entities:
- CPUC
- Cal FIRE
- Office of Emergency Services
- Department of Transportation
- California State Association of Counties
- League of California Cities
- Rural County Representatives of California
- Requires each electrical corporation, as part of their annual wildfire mitigation plan, to include a description of where and how the electrical corporation considered undergrounding electrical distribution lines within those areas of its service territory identified to have the highest wildfire risk in a CPUC fire threat map.
Background
Undergrounding of electric facilities. Undergrounding is the process of replacing overhead lines that provide services such as electricity or communications with lines located underground. The undergrounding of electrical and communications lines is typically done for aesthetic or safety purposes in order to remove the visible overhead lines and poles or to reduce the risk of damage or fire from being exposed to the elements. Undergrounding is generally much more expensive relative to overhead infrastructure – on the order of 10 times or more. However, operating costs may be less assuming the underground results in a reduced need to repair damaged lines. Nonetheless, the costs for undergrounding lines can vary depending on the location of the lines: rural, urban, or suburban communities.
California Overhead Conversion Program, Electric Tariff Rule 20. The CPUC requires IOUs to allocate a certain amount of ratepayer funds each year for undergrounding conversion projects. The electric utility annually allocates funds via credits under Electric Tariff Rule 20 to communities, either cities or unincorporated areas of counties, to convert overhead electric lines to underground facilities. Since ratepayers contribute the bulk of the costs of Rule 20A programs through utility rates, the projects must be in the public interest, meeting specified criteria. The CPUC instituted the current undergrounding program in 1967 and has made mostly slight adjustments to the program over the 50 years. In 2014, the CPUC authorized San Diego Gas & Electric (SDG&E) the ability to consider wildfires when converting electric facilities to underground. The CPUC agreed with SDG&E that undergrounding could mitigate the risks of wildfires in the more fire-prone areas of SDG&E’s service territory. The CPUC approved a SDG&E specific version of Rule 20D that is modeled on Rule 20A, but targeted to the most fire-prone areas.
Local jurisdiction contributions. Under the Improvement Act (Act) of 1911, cities, counties and other municipal governments are authorized to designate areas within which public agencies officials and individual property owners may enter into contractual assessments to finance a wide range of public infrastructure projects. An assessment district is formed as an alternative method for financing public improvements by a sponsoring local government agency. One type of assessment district that the Act authorizes is an underground utility district (UUD), which is formed for the purposes of converting above ground infrastructure to below ground. UUDs are formed via petition or by a determination of the legislative body. Current law requires a legislative body to determine that the city or a public utility has voluntarily agreed to pay over 50 percent of all costs of conversion, excluding costs of users' connections to underground electric or communication facilities in order to initiate proceedings.
CPUC High Fire-Threat District. The CPUC’s efforts to map high-fire threat stem from the catastrophic wildfires caused by utility infrastructure in San Diego County in the 2000s. The CPUC mapping efforts combine the Tree Mortality Taskforce Map with CPUC/Cal FIRE Tier 2 and Tier 3 designations. Tier 2 fire-threat areas depict areas where there is an elevated risk (including likelihood and potential impacts on people and property) from utility associated wildfires. Tier 3 fire-threat areas depict areas where there is an extreme risk (including likelihood and potential impacts on people and property) from utility associated wildfires.
Wildfire mitigation plans. Per statute, electric utilities must file wildfire mitigation plans with specified information. In the recently filed plans, some of the electric utilities considered the potential to underground some lines as part of their wildfire mitigation efforts. However, in most instances, the electric utilities’ wildfire mitigation plans included the potential to underground lines but recommended an assessment to identify what electric lines made feasible and financial sense to underground. As one electric corporation’s plan noted: “While underground systems can help reduce the risk of wildfires and increase reliability during high winds and storms, they also take longer and costs much more to construct, maintain, and repair – particularly in mountainous regions and those with steep terrain.” In general, the electric utilities are incorporating other wildfire mitigation efforts that are more cost-effective, including conductor covers, replacing wooden poles with poles made of more fire-resistant materials, and other mitigation actions.
SB 70. This bill establishes a new undergrounding working group to help coordinate joint trenching for areas that experienced wildfire that occurred in 2013 to 2020. It is not fully clear what additional work the new working group would be conducting that is not today done in relation to coordinating activities to undergrounding infrastructure from multiple services (telecommunications, sewer, electrical, etc.). To the extent the working group is intended to provide additional level of coordination for communities that have been destroyed by fires and are rebuilding, as is the case in the Town of Paradise, it is possible that such an entity could be useful. However, the dates are not necessary, and may arbitrarily limit the efforts of this new working group.
Impact to ratepayers? This bill does not require any undergrounding of electrical infrastructure activities. However, to the extent undergrounding electric infrastructure is identified as a mitigation strategy within the wildfire mitigation plan, it is possible that electric utility ratepayers for the given utility may have to pay a portion or all of the costs to underground those lines which could be substantial. However, to the extent undergrounding prevents wildfires and the associated costs of the wildfires, ratepayers could benefit from the decreased risk of a wildfire ignited by the electrical lines.
Related/Prior Legislation
SB 584 (Moorlach, 2019) makes changes to programs that help fund conversion projects to replace overhead electrical infrastructure with underground electrical infrastructure in specified areas of the service territory of IOUs. The bill was held in the Senate Committee on Appropriations.
SB 1463 (Moorlach, 2016) would have required the CPUC, in consultation with the Cal FIRE, to prioritize areas where communities are subject to conditions that increase fire hazards associated with overhead utility facilities when determining areas which it will require enhanced mitigation measures for wildfire hazards posed by overhead electrical lines and equipment. The bill was vetoed.
SB 901 (Dodd, Chapter 626, Statutes of 2018) addressed numerous issues concerning wildfire prevention, response and recovery, including funding for mutual aid, fuel reduction and forestry policies, wildfire mitigation plans by electric utilities, and cost recovery by electric corporations of wildfire-related damages.
SB 1028 (Hill, Chapter 598, Statutes of 2016) required electric CPUC-regulated utilities to file annual wildfire mitigation plans and requires the CPUC to review and comment on those plans.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
According to the Senate Committee on Appropriations, while the establishment of the Electrical Infrastructure Undergrounding Working Group would be subject to an appropriation, this bill could result in one-time General Fund cost pressure of about $1 million for the CPUC to convene and lead the statewide working group.
City of Malibu
OPPOSITION: (Verified 5/16/19)
None received
ARGUMENTS IN SUPPORT: According to the author:
As a matter of public safety to California residents as well as electrical utility reliability, something must be done to address threatening aboveground lines in high fire hazard severity zones.
Undergrounding distribution lines may be the answer. Underground electrical lines have many benefits: they are better insulated than overhead electrical lines, are less likely to be affected by hazardous weather conditions and animals, and are better protected from wildfires.
Prepared by: Nidia Bautista / E., U., & C. / (916) 651-4107
5/20/19 11:04:18
**** END ****
SENATE COMMITTEE ON APPROPRIATIONS
Senator Anthony Portantino, Chair
2019 - 2020 Regular Session
SB 70 (Nielsen) - Electricity: undergrounding of electrical infrastructure
Version: April 30, 2019 | Policy Vote: E., U., & C. 13 - 0 |
Urgency: No | Mandate: Yes |
Hearing Date: May 16, 2019 | Consultant: Lenin Del Castillo |
Bill Summary:
This bill establishes the Electrical Infrastructure Undergrounding Working Group (EIUWG) to promote the undergrounding of electrical infrastructure and the implementation of a statewide joint trenching policy.
*********** ANALYSIS ADDENDUM – SUSPENSE FILE ***********
The following information is revised to reflect amendments
adopted by the committee on May 16, 2019
Fiscal Impact:
While the establishment of the Electrical Infrastructure Undergrounding Working Group would be subject to an appropriation, this bill could result in one-time General Fund cost pressure of about $1 million for the California Public Utilities Commission (CPUC) to convene and lead the statewide working group.
Committee Amendments:
Delete the unspecified appropriation and provide that the establishment of the working group would be contingent upon an appropriation.
-- END --
SENATE COMMITTEE ON APPROPRIATIONS
Senator Anthony Portantino, Chair
2019 - 2020 Regular Session
SB 70 (Nielsen) - Electricity: undergrounding of electrical infrastructure
Version: April 30, 2019 | Policy Vote: E., U., & C. 13 - 0 |
Urgency: No | Mandate: Yes |
Hearing Date: May 13, 2019 | Consultant: Lenin Del Castillo |
Bill Summary:
This bill establishes the Electrical Infrastructure Undergrounding Working Group (EIUWG) to promote the undergrounding of electrical infrastructure and the implementation of a statewide joint trenching policy.
Fiscal Impact:
This bill includes an unspecified appropriation from the General Fund to the Electrical Infrastructure Undergrounding Working Group for its administration. However, the California Public Utilities Commission (CPUC) estimates one-time costs of about $1 million and five new positions to convene and lead the statewide working group.
Background:
Existing law provides that the CPUC has regulatory authority over public utilities, including IOUs. Under its existing authority, the CPUC requires IOUs to implement the California Overhead Conversion Program, Rule 20A, to provide financial assistance to local governments to facilitate projects that are in the public interest and that remove overhead infrastructure, replacing it with infrastructure in underground trenches. Existing law requires the CPUC to develop formal procedures to incorporate safety in a rate case application by an IOU or gas corporations.
Existing law requires each IOU to construct, maintain, and operate its electrical lines and equipment in a manner that will minimize the risk of catastrophic wildfire posed by those electrical lines and equipment. Requires each IOU to annually prepare and submit a wildfire mitigation plan to the CPUC for review and approval. The law requires those wildfire mitigation plans to include specified information, including protocols for disabling reclosers and deenergizing portions of the electrical distribution system that consider the associated impacts on public safety, as well as protocols related to mitigating the public safety impacts of those protocols, including impacts on critical first responders and on health and communication infrastructure.
Proposed Law:
This bill establishes the EIUWG to promote the undergrounding of electrical infrastructure and the implementation of a statewide joint trenching policy. The bill requires the EIUWG to focus on areas affected by wildfires from 2013 to 2020 during the rebuilding and restoration phases of those areas, and to prioritize undergrounding along those streets and highways that serve as county-designated evacuation routes. The EIUWG shall consist of representatives from all of the following entities:
- CPUC
- Cal FIRE
- Office of Emergency Services (OES)
- Department of Transportation (DOT)
- California State Association of Counties (CSAC)
- League of Cities
- Rural County Representatives of California
This bill requires wildfire mitigation plans to include a description of where and how the electrical corporation considered undergrounding electrical distribution lines within those areas of its service territory identified to have the highest wildfire risk in a commission fire threat map.
Related Legislation:
SB 584 (Moorlach, 2019) would make changes to programs that help fund conversion projects to replace overhead electrical infrastructure with underground electrical infrastructure in specified areas of the service territory of IOUs. The bill is scheduled to be heard in the Senate Appropriations Committee on May 13, 2019.
SB 1463 (Moorlach, 2016) would have required the CPUC, in consultation with the Cal FIRE, to prioritize areas where communities are subject to conditions that increase fire hazards associated with overhead utility facilities when determining areas which it will require enhanced mitigation measures for wildfire hazards posed by overhead electrical lines and equipment. The bill was vetoed.
SB 901 (Dodd, Chapter 626, Statutes of 2018) addressed numerous issues concerning wildfire prevention, response and recovery, including funding for mutual aid, fuel reduction and forestry policies, wildfire mitigation plans by electric utilities, and cost recovery by electric corporations of wildfire-related damages.
SB 1028 (Hill, Chapter 598, Statutes of 2016) required electric CPUC-regulated utilities to file annual wildfire mitigation plans and requires the CPUC to review and comment on those plans.
-- END --
SENATE COMMITTEE ON ENERGY, UTILITIES AND COMMUNICATIONS
Senator Ben Hueso, Chair
2019 - 2020 Regular
Bill No: SB 70 Hearing Date: 4/24/2019
Author: | Nielsen | ||
Version: | 4/3/2019 As Amended | ||
Urgency: | No | Fiscal: | Yes |
Consultant: | Nidia Bautista | ||
SUBJECT: Electricity: undergrounding of electrical distribution infrastructure
DIGEST: This bill would require the California Public Utilities Commission (CPUC) to require each investor-owned utility (IOU) to underground electric distribution infrastructure in specified situations, including areas destroyed as a result of fire in very high fire hazard severity zones and overhead infrastructure removed due to an accident. This bill would also establish an Electrical Infrastructure Undergrounding Working Group (EIUWG) to focus undergrounding activities for areas affected by wildfires from 2013 to 2020.
ANALYSIS:
Existing law:
- Provides that the CPUC has regulatory authority over public utilities, including IOUs. (California Constitution, Article 12)
- Declares that it is the policy of the state to achieve, whenever feasible and not inconsistent with sound environmental planning, the undergrounding of all future electric and communication distribution facilities which are proposed to be erected in proximity to any highway designated a state scenic highway and which would be visible from such scenic highways if erected above ground. (Public Utilities Code §320)
- Under its existing authority, the CPUC requires IOUs to implement the California Overhead Conversion Program, Rule 20A, to provide financial assistance to local governments to facilitate projects that are in the public interest and that remove overhead infrastructure, replacing it with infrastructure in underground trenches.
- Requires the CPUC to develop formal procedures to incorporate safety in a rate case application by an IOU or gas corporations. (Public Utilities Code §750)
- Requires each IOU to construct, maintain, and operate its electrical lines and equipment in a manner that will minimize the risk of catastrophic wildfire posed by those electrical lines and equipment. Requires each IOU to annually prepare and submit a wildfire mitigation plan to the CPUC for review and approval. Requires those wildfire mitigation plans to include specified information, including protocols for disabling reclosers and deenergizing portions of the electrical distribution system that consider the associated impacts on public safety, as well as protocols related to mitigating the public safety impacts of those protocols, including impacts on critical first responders and on health and communication infrastructure. (Public Utilities Code §8386)
This bill:
- Makes a number of findings and declarations related to the benefits of undergrounding electrical lines.
- Requires the CPUC, on or after January 1, 2021, to require each IOU to do both of the following:
- Replace overhead electrical distribution infrastructure in a very high fire hazard severity zone, as determined by the California Department of Forestry and Fire Protection (Cal FIRE), in the electrical corporation’s territory that is destroyed as a result of fire with underground electrical distribution infrastructure.
- Convert overhead electrical distribution infrastructure that is removed due to an accident to underground electrical distribution infrastructure.
- Prohibits the CPUC from requiring the construction of underground electrical distribution infrastructure where it finds that the construction of underground electrical distribution infrastructure is physically infeasible, including due to weather conditions such as the presence of heavy snow or terrain conditions such as the presence of bedrock, or if the CPUC finds that there is an immediate need to construct overhead electrical distribution infrastructure to restore electrical service following an outage.
- Prohibits an IOU that has not complied with its wildfire mitigation plans submitted pursuant to Section 8386 from recovering from ratepayers that costs of complying with the requirements of this section except for those costs specifically related to the permitting process, including costs relating to the California Environmental Quality Act, staff time, permit fees, and consulting fees.
- Establishes the EIUWG in state government to promote the undergrounding of electrical infrastructure and the implementation of a statewide joint trenching policy. Requires the EIUWG to focus on areas affected by wildfires from 2013 to 2020 during the rebuilding and restoration phases of those areas. Requires the EIUWG to prioritize undergrounding along those streets and highways that serve as county-designated evacuation routes.
- Requires EIUWG to consist of representatives from all of the following entities:
- CPUC
- Cal FIRE
- Office of Emergency Services (OES)
- Department of Transportation (DOT)
- California State Association of Counties (CSAC)
- League of Cities
- Rural County Representatives of California
- Appropriates the sum of one million dollars from the General Fund to the EIUWG in the 2019-20 fiscal year for its administration.
Background
Undergrounding of electric facilities. Undergrounding is the process of replacing overhead lines that provide services such as electricity or communications with lines located underground. The undergrounding of electrical and communications lines is typically done for aesthetic or safety purposes in order to remove the visible overhead lines and poles or to reduce the risk of damage or fire from being exposed to the elements. Undergrounding is generally much more expensive relative to overhead infrastructure – on the order of 10 times or more. However, operating costs may be less assuming the underground results in a reduced need to repair damaged lines. Nonetheless, the costs for undergrounding lines can vary depending on the location of the lines: rural, urban, or suburban communities.
California Overhead Conversion Program, Rule 20. The CPUC requires IOUs to allocate a certain amount of ratepayer funds each year for undergrounding conversion projects. The electric utility annually allocates funds via credits under Electric Tariff Rule 20 to communities, either cities or unincorporated areas of counties, to convert overhead electric lines to underground facilities. The local jurisdiction may either accumulate their allocated credits, or borrow future undergrounding allocations for up to five years. Tariff Rule 20 provides three levels (A, B, and C) of progressively diminishing ratepayer funding for the projects, based on specified criteria. Once a project is completed, the electric utility records its costs in its electric plant account for recovery through the utility’s rate base. The CPUC authorizes the utility to recover the costs from ratepayers until the project is fully depreciated. Since ratepayers contribute the bulk of the costs of Rule 20A programs through utility rates, the projects must be in the public interest, meeting specified criteria. The CPUC instituted the current undergrounding program in 1967 and has made mostly slight adjustments to the program over the 50 years.
San Diego Gas & Electric (SDG&E) Rule 20D. In 2014, the CPUC authorized SDG&E the ability to consider wildfires when converting electric facilities to underground. The CPUC agreed with SDG&E that undergrounding could mitigate the risks of wildfires in the more fire-prone areas of SDG&E’s service territory. The CPUC approved a SDG&E specific version of Rule 20D that is modeled on Rule 20A, but targeted to the most fire-prone areas. Under Rule 20D, the governing body has determined that undergrounding will occur in the SDG&E Fire Threat Zone, as identified, and SDG&E has determined that undergrounding is a preferred method to reduce fire risk and enhance the reliability of the facilities to be undergrounded.
The table below notes the Electric Tariff Rule 20 programs and the ratepayer contribution for each:
Electric Tariff Rule 20 | |||
Rule | Ratepayer Contribution | Municipality or Third Party Contribution | Criteria |
20A | 80-100% | Max. of 20% cost from street to meter Min. 0% if use main line funds | Public interest |
20B | 20% | 80% | N/A |
20C | Minimal | 100% | Typically small projects |
20D | 80% | Max. 20% cost from street to meter Min. 0% if use main line funds | Facilities within SDG&E Fire Threat Zone |
Local jurisdiction contributions. Under the Improvement Act (Act) of 1911, cities, counties and other municipal governments are authorized to designate areas within which public agencies officials and individual property owners may enter into contractual assessments to finance a wide range of public infrastructure projects. An assessment district is formed as an alternative method for financing public improvements by a sponsoring local government agency. One type of assessment district that the Act authorizes is an underground utility district (UUD), which is formed for the purposes of converting above ground infrastructure to below ground. UUDs are formed via petition or by a determination of the legislative body. Current law requires a legislative body to determine that the city or a public utility has voluntarily agreed to pay over 50 percent of all costs of conversion, excluding costs of users' connections to underground electric or communication facilities in order to initiate proceedings.
Mapping fire. The state has three different maps related to mapping fire threats. This bill references the Cal FIRE Hazard Severity Zone Map. However, Cal FIRE developed another map, the CPUC High Fire-Threat District Map, to address the intersection of electric utility infrastructure and wildfires.
Cal FIRE Hazard Severity Zone Map. Cal FIRE identifies moderate, high, and very high fire threat zones in order to classify lands in the state where a very high fire hazard is present so that public officials, especially local officials, are able to identify and adopt measures to mitigate against fire risk, pursuant to Government Code §§51175 and 51177. These maps have been used to inform mitigation and regulatory requirements in local responsibility areas and state responsibility areas.
CPUC High Fire-Threat District. The CPUC’s efforts to map high-fire threat stem from the catastrophic wildfires caused by utility infrastructure in San Diego County in the 2000s. The CPUC mapping efforts combine the Tree Mortality Taskforce Map with CPUC/Cal FIRE Tier 2 and Tier 3 designations. Tier 2 fire-threat areas depict areas where there is an elevated risk (including likelihood and potential impacts on people and property) from utility associated wildfires. Tier 3 fire-threat areas depict areas where there is an extreme risk (including likelihood and potential impacts on people and property) from utility associated wildfires.
Wildfire mitigation plans. As a requirement of SB 901, electric utilities must file wildfire mitigation plans with specified information. In the recently filed plans, some of the electric utilities considered the potential to underground some lines as part of their wildfire mitigation efforts. However, in most instances, the electric utilities’ wildfire mitigation plans included the potential to underground lines but recommended an assessment to identify what electric lines made sense to underground. As one plan noted: “While underground systems can help reduce the risk of wildfires and increase reliability during high winds and storms, they also take longer and costs much more to construct, maintain, and repair – particularly in mountainous regions and those with steep terrain.” In general, the electric utilities are incorporating other wildfire mitigation efforts that are more cost-effective, including conductor covers, replacing wooden poles with poles made of more fire-resistant materials, and other mitigation actions.
SB 70. This bill would largely require an IOU to underground electrical infrastructure in a high fire severity zone that had experienced wildfire or had an accident, as long as it was physically feasible to do so. As noted above, undergrounding electrical infrastructure is a very costly endeavor. As such, efforts to require undergrounding of infrastructure must also consider the costs, which in this case could be borne largely by utility ratepayers, depending on whether the utility complied with its wildfire mitigation plan. However, it is unclear exactly how the utility must comply with its wildfire mitigation plan. Additionally, the inclusion of undergrounding infrastructure due to an accident could result in undergrounding activities that may not have much to do with reducing wildfire risks.
This bill also establishes a new undergrounding working group and requires an appropriation of one million dollars for the purposes of this working group’s efforts to help coordinate joint trenching for areas that experienced wildfire that occurred in 2013 to 2020. It is not fully clear what additional work the new working group would be conducting that is not today done in relation to coordinating activities to undergrounding infrastructure from multiple services (telecommunications, sewer, electrical, etc.). To the extent the working group is intended to provide additional level of coordination for communities that have been destroyed by fires, as is the case in the Town of Paradise, and are rebuilding, it is possible that such an entity could be useful. However, the dates are not necessary, and may arbitrarily limit the efforts of this new working group. The author and committee may wish to amend this bill to delete the specific mention of the dates (2013 to 2020) and the amount to be appropriated for the new working group.
Impact to ratepayers? As currently drafted, this bill would likely result in hundreds of millions of dollars, and potentially more, in impacts to ratepayers to pay for the undergrounding activities. This committee recently heard a bill that also encouraged undergrounding activities, SB 584 (Moorlach, 2019). In that bill, this committee amended the bill to limit the use of ratepayer funds to pay for the undergrounding of electrical lines only for instances where the CPUC determined it was the preferred method to address wildfire risks. The author and committee may wish to strike Section 2 of this bill and replace with language in the required wildfire mitigation plans that would require the electric utilities to note where and how undergrounding of electrical infrastructure was considered within the plan.
Prior/Related Legislation
SB 584 (Moorlach, 2019) would make changes to programs that help fund conversion projects to replace overhead electrical infrastructure with underground electrical infrastructure in specified areas of the service territory of IOUs. The bill is scheduled to be heard in Senate Committee on Natural Resources and Water on April 23, 2019.
SB 1463 (Moorlach, 2016) would have required the CPUC, in consultation with the Cal FIRE, to prioritize areas where communities are subject to conditions that increase fire hazards associated with overhead utility facilities when determining areas which it will require enhanced mitigation measures for wildfire hazards posed by overhead electrical lines and equipment. The bill was vetoed.
SB 901 (Dodd, Chapter 626, Statutes of 2018) addressed numerous issues concerning wildfire prevention, response and recovery, including funding for mutual aid, fuel reduction and forestry policies, wildfire mitigation plans by electric utilities, and cost recovery by electric corporations of wildfire-related damages.
SB 1028 (Hill, Chapter 598, Statutes of 2016) required electric CPUC-regulated utilities to file annual wildfire mitigation plans and requires the CPUC to review and comment on those plans.
FISCAL EFFECT: Appropriation: Yes Fiscal Com.: Yes Local: Yes
SUPPORT:
None received
OPPOSITION:
California Chamber of Commerce
ARGUMENTS IN SUPPORT: According to the author:
“As a matter of public safety to California residents as well as electrical utility reliability, something must be done to address threatening aboveground lines in high fire hazard severity zones.
Undergrounding distribution lines may be the answer. Underground electrical lines have many benefits: they are better insulated than overhead electrical lines, are less likely to be affected by hazardous weather conditions and animals, and are better protected from wildfires.
Underground lines also generally have a longer lifespan and create less interference with other communication infrastructure, than overhead electrical lines.
Californians must harden their utility infrastructure, in order to live with wildfires and to reduce the risk of future catastrophic wildfires. Undergrounding is not just an investment in reliable infrastructure, but an investment in lives.”
ARGUMENTS IN OPPOSITION: In opposition to this bill, the California Chamber of Commerce expresses concerns about the potential for significant increases to energy rates by requiring electric utilities to underground their lines as this bill proposes. The Chamber notes that “wildfire mitigation is a complex solution, not easily subjected to a one-size fits all approach such as burying lines.” The Chamber further acknowledges that the requirements of SB 901 wildfire mitigation plans already require consideration of undergrounding. “Where appropriate, strategic undergrounding is being proposed by the utilities as a portion of the wildfire prevention approach.”
-- END --