SB 833: Community Energy Resilience Act of 2022.
- Session Year: 2021-2022
- House: Senate
- Latest Version Date: 2022-06-30
Existing law establishes within the Natural Resources Agency the State Energy Resources Conservation and Development Commission. Existing law assigns the commission various duties, including applying for and accepting grants, contributions, and appropriations, and awarding grants consistent with the goals and objectives of a program or activity the commission is authorized to implement or administer.
This bill, the Community Energy Resilience Act of 2022, would require the commission to develop and implement a grant program to award grants through a noncompetitive process for local governments to develop community energy resilience plans that help achieve energy resilience objectives and state clean energy and air quality goals. The bill would require a plan to, among other things, identify critical facilities, facilities where the construction of microgrids or other distributed energy sources could meet local resilience needs, and potential funding sources for implementing projects in the plan, include a process for the expedited permit review of distributed energy resources by the local government, and demonstrate consistency with the city, county, or city and county general plan and other local government planning documents, as specified. As a condition of receiving grant funding, the bill would require a local government to submit its plan to the commission within 6 months of adopting the plan. The bill would require grant funds to be encumbered within 2 years, and liquidated within 4 years, of the date of an award.
The bill would require the commission to maintain a publicly available and searchable database of all local governments receiving a grant, annually submit a program summary to the Legislature, and post the summary on its internet website. The bill also would require the commission to develop and maintain on its internet website a publicly available community energy resilience planning toolkit, a directory of prequalified consultants, and a resilience valuation index, as defined, to assist local governments in community energy resilience planning. The bill would require the commission to periodically update the index.
Existing law establishes within the Natural Resources Agency the State Energy Resources Conservation and Development Commission. Existing law assigns the commission various duties, including applying for and accepting grants, contributions, and appropriations, and awarding grants consistent with the goals and objectives of a program or activity the commission is authorized to implement or administer.
This bill, the Community Energy Resilience Act of 2022, would require the commission to develop and implement a grant program for local governments to develop community energy resilience plans that help achieve energy resilience objectives and state clean energy and air quality goals. The bill would require a plan to, among other things, identify critical facilities, locations and facilities where the construction of microgrids or other distributed energy sources could meet local resilience needs, and potential funding sources for implementing projects in the plan, include a process for the expedited permit review of distributed energy resources by the local government, and demonstrate consistency with the city, county, or city and county general plan and other local government planning documents, as specified. As a condition of receiving grant funding, the bill would require a local government to submit its plan to the commission within 6 months of adopting the plan.
The bill would require the commission to maintain a publicly available and searchable database of all local governments receiving a grant, annually submit a program summary to the Legislature, and post the summary on its internet website. The bill also would require the commission to develop and maintain on its internet website a publicly available community energy resilience planning toolkit, a directory of prequalified consultants, and a resilience valuation index, as defined, to assist local governments in community energy resilience planning. The bill would require the commission to annually periodically update the index.
Existing law establishes within the Natural Resources Agency the State Energy Resources Conservation and Development Commission. Existing law assigns the commission various duties, including applying for and accepting grants, contributions, and appropriations, and awarding grants consistent with the goals and objectives of a program or activity the commission is authorized to implement or administer.
This bill, the Community Energy Resilience Act of 2022, would require the commission to develop and implement a grant program for local governments to develop community energy resilience plans and expedite permit review of distributed energy resources by local governments. The bill would require the plans to be consistent with the city, county, or city and county general plan and other local government planning documents. that help achieve energy resilience objectives and state clean energy and air quality goals. The bill would require a plan to, among other things, identify critical facilities, locations and facilities where the construction of microgrids or other distributed energy sources could meet local resilience needs, and potential funding sources for implementing projects in the plan, include a process for the expedited permit review of distributed energy resources by the local government, and demonstrate consistency with the city, county, or city and county general plan and other local government planning documents, as specified. As a condition of receiving grant funding, the bill would require a local government to submit its plan to the commission within 6 months of adopting the plan.
The bill would require the commission to maintain a publicly available and searchable database of all local governments receiving a grant, annually submit a program summary to the Legislature, and post the summary on its internet website. The bill also would require the commission to develop and maintain on its internet website a publicly available library of community energy resilience planning tools and toolkit, a directory of prequalified consultants, as specified. and a resilience valuation index, as defined, to assist local governments in community energy resilience planning. The bill would require the commission to annually update the index.
Existing law establishes within the Natural Resources Agency the State Energy Resources Conservation and Development Commission. Existing law assigns the commission various duties, including applying for and accepting grants, contributions, and appropriations, and awarding grants consistent with the goals and objectives of a program or activity the commission is authorized to implement or administer.
This bill, the Community Energy Resilience Act of 2022, would require the commission to develop and implement a grant program for local governments to develop community energy resilience plans and expedite permit review of distributed energy resources by local governments. The bill would require the plans to be consistent with the city, county, or city and county general plan and other local government planning documents. The bill would require a plan to, among other things, identify critical facilities, locations and facilities where the construction of microgrids or other distributed energy sources could meet local resilience needs, and potential funding sources for implementing projects in the plan, as specified. As a condition of receiving grant funding, the bill would require a local government to submit its plan to the commission within 6 months of adopting the plan.
The bill would require the commission to maintain a publicly available and searchable database of all local governments receiving a grant, annually submit a program summary to the Legislature, and post the summary on its internet website. The bill also would require the commission to develop and maintain on its internet website a publicly available library of community energy resilience planning tools and a directory of prequalified consultants, as specified.
(a)This act shall be known, and may be cited, as the Community Energy Resilience Act of 2022.
(b)The Legislature finds and declares all of the following:
(1)Development of community energy resilience plans will help ensure continuous electricity service during electrical outages, which in recent years have imposed enormous costs on California communities.
(2)Developing reliable and resilient electrical systems for critical facilities is a paramount public safety priority and is necessary to protect the health and well-being of California residents and businesses.
(3)Local governments typically lack the resources or expertise needed for community energy resilience planning sufficient to increase the usage of distributed clean energy resources.
(4)Local governments are best able to identify, working in collaboration with community-based organizations, which facilities are most important to local residents and necessary to maintain public health and safety, and can most effectively integrate the permitting and development of distributed energy resources capable of providing electricity to these facilities during electrical outages.
(5)With proper engineering and planning, local governments are capable of accelerating the deployment of resilient clean backup electrical systems by taking advantage of state, federal, and other funding sources.
(c)It is the intent of the Legislature to direct the State Energy Resources Conservation and Development Commission to develop procedures necessary for implementation of a new program to provide technical guidance and financial assistance for local governments to develop community energy resilience plans.
SEC. 2.Division 16.7 (commencing with Section 26450) is added to the Public Resources Code, to read:16.7.Community Energy Resilience Planning26450.For purposes of this division, the following definitions apply:
(a)Commission means the State Energy Resources Conservation and Development Commission.
(b)Community energy resilience means the capability of a local community, local government, tribal authority, or other municipality to provide and maintain stable electricity supply to identified critical facilities under changing conditions, including, but not limited to, outages of utility grid service.
(c)Community energy resilience plan means a planning document prepared by a local government pursuant to this division that sets forth a strategy for meeting local electrical loads achieving community energy resilience with local clean distributed energy resources. Unless the context requires otherwise, plan means a community energy resilience plan.
(d)Electrical corporation has the same meaning as defined in Section 218 of the Public Utilities Code.
(e)Local government means a city, county, city and county, or California Native American tribe, as defined in Section 21073.
(f)Local publicly owned electric utility has the same meaning as defined in Section 224.3 of the Public Utilities Code.
(g)Resilience Valuation Index means a standardized, data-driven tool that assists local governments in conducting cost-benefit analyses of community energy resilience investments, such as distributed energy resources or microgrids. Unless the context requires otherwise, index means the Resilience Valuation Index.
26451.(a)Pursuant to this division, the commission shall develop and implement a grant program to award grants to local governments through a noncompetitive process for the development of community energy resilience plans that help achieve local energy resilience objectives and state clean energy and air quality goals.
(b)In developing the guidelines and application process for the grant program, the commission shall do all of the following:
(1)Prioritize applications from low-income communities that are most likely to experience power outages, disadvantaged communities that are most likely to experience power outages, or low-income and disadvantaged communities that are most likely to experience power outages first, followed by communities that are most likely to experience power outages.
(2)Make the application process as simple as possible.
(3)Conduct a minimum of two public meetings to receive and consider public comment before approving the guidelines and application process.
(c)Grant funds awarded pursuant to this division shall be encumbered within two years, and liquidated within four years, of the date of the award.
(c)(d)For local governments located within the service territory of a local publicly owned electric utility, only the local publicly owned electric utility shall be eligible to apply for grant funding on behalf of the local government.
(d)(e)Grant funds awarded pursuant to this division may be used for plan development, including, but not limited to, all of the following activities:
(1)Hiring outside consultants or technical assistance providers to help with coordinating and drafting the plan.
(2)Identifying and coordinating with appropriate local government staff to draft the plan. A local government may hire a resilience manager to manage the plan development process.
(3)Convening and facilitating one or more community workshops enlisting local stakeholders, including, but not limited to, labor representatives, representatives from community-based organizations, community members, representatives from related technology vendors, local government staff in departments relating to emergency services, planning, and public works, disability rights advocates, and representatives from special districts, load-serving entities, school districts, environmental justice communities, communities of color, local tribes, and other marginalized groups, to ensure that a diversity of perspectives and input is incorporated into the plan.
(e)(f)(1)A plan for which a local government is awarded a grant shall do all of the following:
(A)Identify critical facilities, including publicly available and accessible facilities that can serve as community resilience hubs to accommodate and provide basic services, including water, restrooms, basic first aid, disaster information, and access to electricity to charge telephones and medical equipment, to people who have lost power to their homes.
(B)Identify facilities where the construction of microgrids or other distributed energy resources could meet local resilience needs.
(C)Identify critical facilities that are in greatest need of backup energy generation and potential backup energy systems that may meet the needs of those facilities.
(D)Identify potential funding sources for implementation of projects included in the plan.
(E)Include a model ordinance template that may be adopted by a local government to establish a process for the expedited permit review of distributed energy resources by the local government.
(F)Demonstrate consistency with the city, county, or city and county general plan and other local government planning documents.
(2)The plan shall be developed in collaboration with the relevant electrical corporation or local publicly owned electric utility operational and technical subject matter experts.
(f)(g)Subject to any restrictions or limitations placed by outside funding programs, grants awarded to a local government pursuant to this division do not affect the local governments eligibility to receive other incentives available from federal, state, or other local governments, electrical corporations, local publicly owned electric utilities, or any other source, or to leverage the grant funding awarded pursuant to this division with any other incentive.
(g)(h)As a condition of being awarded a grant pursuant to this division, a local government shall submit its plan to the commission within six months of adopting its plan.
(h)(i)The commission shall maintain a publicly available and searchable database of all local governments awarded a grant pursuant to this division. The database shall include relevant metrics to be determined by the commission, including the grant award amount and the community served.
(i)(j)(1)The commission shall prepare an annual summary of statewide program expenditures.
(2)Pursuant to Section 9795 of the Government Code, the commission shall annually submit the summary to the Legislature and post the summary on its internet website.
26452.(a)The commission shall develop and maintain, on its internet website, a community energy resilience planning toolkit to support local governments development of community energy resilience plans. The toolkit shall include detailed information on typical planning steps, including, but not limited to, community asset mapping, stakeholder identification, community engagement, and technical and economic feasibility.
(b)The commission shall develop and maintain, on its internet website, a directory of prequalified consultants with energy resilience planning expertise who may assist grant recipients in plan development.
(c)(1)The commission shall develop and maintain a publicly available Resilience Valuation Index to assist local governments in community energy resilience planning and support data-driven investment decisions.
(2)The index shall identify entities and populations within communities that are vulnerable to power outages or other climate disruptions, including, but not limited to, any of the following:
(A)Critical facilities, including, but not limited to, the types of facilities described in Public Utilities Commission Decision 19-05-042, Decision Adopting De-Energization Guidelines, and other related decisions.
(B)Public agencies.
(C)Small businesses.
(D)Commercial and industrial facilities.
(E)Education and childcare facilities.
(F)Food production and distribution facilities.
(G)Access and functional needs populations.
(H)Medically vulnerable populations.
(I)Disadvantaged or low-income populations.
(J)Rural or remote populations.
(K)Other communities or populations that the commission determines may be severely impacted by the loss of continuous electrical service.
(3)(A)The index shall catalog and quantify a range of potential resiliency values for each identified constituency or population.
(B)The index shall use publicly available information on the value of lost load, socioeconomic analyses, and other power outage resources, from reputable academic institutions, including from the Lawrence Berkeley National Laboratorys Interruption Cost Estimate Calculator.
(4)The commission shall post, and periodically update, the index on its internet website.
(a)This act shall be known, and may be cited, as the Community Energy Resilience Act of 2022.
(b)The Legislature finds and declares all of the following:
(1)Development of community energy resilience plans will help ensure continuous electricity service during electrical outages, which in recent years have imposed enormous costs on California communities.
(2)Developing reliable and resilient electrical systems for critical facilities is a paramount public safety priority and is necessary to protect the health and well-being of California residents and businesses.
(3)Local governments typically lack the resources or expertise needed for community energy resilience planning sufficient to increase the usage of distributed clean energy resources.
(4)Local governments have the greatest degree of local political accountability, are best able to identify, working in collaboration with community-based organizations, which facilities are most important to local residents and necessary to maintain public health and safety, and can most effectively integrate the permitting and development of distributed energy resources capable of providing electricity to these facilities during electrical outages.
(5)With proper engineering and planning, local governments are capable of accelerating the deployment of resilient clean backup electrical systems by taking advantage of state, federal, and other funding sources.
(c)It is the intent of the Legislature to direct the State Energy Resources Conservation and Development Commission to develop procedures necessary for implementation of a new program to provide technical guidance and financial assistance for local governments to develop community energy resilience plans.
SEC. 2.Division 16.7 (commencing with Section 26450) is added to the Public Resources Code, to read:16.7.Community Energy Resilience Planning26450.For purposes of this division, the following definitions apply:
(a)Commission means the State Energy Resources Conservation and Development Commission.
(b)Community energy resilience means the capability of a local community, local government, tribal authority, or other municipality to provide and maintain stable electricity supply to identified critical facilities under changing conditions, including, but not limited to, outages of utility grid service.
(c)Community energy resilience plan means a planning document prepared by a local government pursuant to this division that sets forth a strategy for meeting local electrical loads with local clean distributed energy resources. Unless the context requires otherwise, plan means a community energy resilience plan.
(d)Electrical corporation has the same meaning as defined in Section 218 of the Public Utilities Code.
(e)Local government means a city, county, city and county, or California Native American tribe, as defined in Section 21073.
(f)Local publicly owned electric utility has the same meaning as defined in Section 224.3 of the Public Utilities Code.
(g)Resilience Valuation Index means a standardized, data-driven tool that assists local governments in conducting cost-benefit analyses of community energy resilience investments, such as distributed energy resources or microgrids. Unless the context requires otherwise, index means the Resilience Valuation Index.
26451.(a)Pursuant to this division, the commission shall develop and implement a grant program to award grants to local governments for the development of community energy resilience plans that help achieve local energy resilience objectives and state clean energy and air quality goals.
(b)In developing the guidelines and application process for the grant program, the commission shall do all of the following:
(1)Prioritize applications from low-income communities that are most likely to experience power outages, disadvantaged communities that are most likely to experience power outages, or low-income and disadvantaged communities that are most likely to experience power outages first, followed by communities that are most likely to experience power outages.
(2)Make the application process as simple as possible.
(3)Conduct a minimum of two public meetings to receive and consider public comment before approving the guidelines and application process.
(c)For local governments located within the service territory of a local publicly owned electric utility, only the local publicly owned electric utility shall be eligible to apply for grant funding on behalf of the local government.
(d)Grant funds awarded pursuant to this division may be used for plan development, including, but not limited to, all of the following activities:
(1)Hiring outside consultants or technical assistance providers to help with coordinating and drafting the plan.
(2)Identifying and coordinating with appropriate local government staff to draft the plan. A local government may hire a resilience manager to manage the plan development process.
(3)Convening and facilitating one or more community workshops enlisting local stakeholders, including, but not limited to, labor representatives, representatives from community-based organizations, community members, representatives from related technology vendors, local government staff in departments relating to emergency services, planning, and public works, disability rights advocates, and representatives from special districts, load-serving entities, school districts, environmental justice communities, communities of color, local tribes, and other marginalized groups, to ensure that a diversity of perspectives and input is incorporated into the plan.
(e)(1)A plan for which a local government is awarded a grant shall do all of the following:
(A)Identify critical facilities, including publicly available and accessible facilities that can serve as community resilience hubs to accommodate and provide basic services services, including water, restrooms, basic first aid, disaster information, and access to electricity to charge telephones and medical equipment, to people who have lost power to their homes.
(B)Identify locations and facilities where the construction of microgrids or other distributed energy resources could meet local resilience needs.
(C)Identify critical facilities that are in greatest need of backup energy generation and potential backup energy systems that may meet the needs of those facilities.
(D)Identify potential funding sources for implementation of projects included in the plan.
(E)Include a model ordinance template that may be adopted by a local government to establish a process for the expedited permit review of distributed energy resources by the local government.
(F)Demonstrate consistency with the city, county, or city and county general plan and other local government planning documents.
(2)The plan shall be developed in collaboration with the relevant electrical corporation or local publicly owned electric utility operational and technical subject matter experts.
(f)Subject to any restrictions or limitations placed by outside funding programs, grants awarded to a local government pursuant to this division do not affect the local governments eligibility to receive other incentives available from federal, state, or other local governments, electrical corporations, local publicly owned electric utilities, or any other source, or to leverage the grant funding awarded pursuant to this division with any other incentive.
(g)As a condition of being awarded a grant pursuant to this division, a local government shall submit its plan to the commission within six months of adopting its plan.
(h)The commission shall maintain a publicly available and searchable database of all local governments awarded a grant pursuant to this division. The database shall include relevant metrics to be determined by the commission. commission, including the grant award amount and the community served.
(i)(1)The commission shall prepare an annual summary of statewide program expenditures and hire an independent, third-party evaluator to quantify and evaluate the effects of the grant program. expenditures.
(2)Pursuant to Section 9795 of the Government Code, the commission shall annually submit the summary to the Legislature and post the summary on its internet website.
26452.(a)The commission shall develop and maintain, on its internet website, a community energy resilience planning toolkit to support local governments development of community energy resilience plans. The toolkit shall include detailed information on typical planning steps, including, but not limited to, community asset mapping, stakeholder identification, community engagement, and technical and economic feasibility.
(b)The commission shall develop and maintain, on its internet website, a directory of prequalified consultants with energy resilience planning expertise who may assist grant recipients in plan development.
(c)(1)The commission shall develop and maintain a publicly available Resilience Valuation Index to assist local governments in community energy resilience planning and support data-driven investment decisions.
(2)The index shall identify entities and populations within communities that are vulnerable to power outages or other climate disruptions, including, but not limited to, any of the following:
(A)Critical facilities, including, but not limited to, the types of facilities described in Public Utilities Commission Decision 19-05-042, Decision Adopting De-Energization Guidelines, and other related decisions.
(B)Public agencies.
(C)Small businesses.
(D)Commercial and industrial facilities.
(E)Education and childcare facilities.
(F)Food production and distribution facilities.
(G)Access and functional needs populations.
(H)Medically vulnerable populations.
(I)Disadvantaged or low-income populations.
(J)Rural or remote populations.
(K)Other communities or populations that the commission determines may be severely impacted by the loss of continuous electrical service.
(3)(A)The index shall catalog and quantify a range of potential resiliency values for each identified constituency or population.
(B)The index shall use publicly available information on the value of lost load, socioeconomic analyses, and other power outage resources, from reputable academic institutions, including from the Lawrence Berkeley National Laboratorys Interruption Cost Estimate Calculator.
(4)The commission shall post post, and periodically update, the index on its internet website and update the index annually. website.
(a)This act shall be known, and may be cited, as the Community Energy Resilience Act of 2022.
(b)The Legislature finds and declares all of the following:
(1)Development of community energy resilience plans will help ensure continuous electricity service during electrical outages, which in recent years have imposed enormous costs on California communities.
(2)Developing reliable and resilient electrical systems for critical facilities is a paramount public safety priority and is necessary to protect the health and well-being of California residents and businesses.
(3)Local governments typically lack the resources or expertise needed for community energy resilience planning sufficient to increase the usage of distributed clean energy resources.
(4)Local governments have the greatest degree of local political accountability, are best able to identify, working in collaboration with community-based organizations, which facilities are most important to local residents and necessary to maintain public health and safety, and can most effectively integrate the permitting and development of distributed energy resources capable of providing electricity during electrical outages.
(5)With proper engineering and planning, local governments are capable of accelerating the deployment of resilient clean electrical systems by taking advantage of state, federal, and other funding sources.
(c)It is the intent of the Legislature to direct the State Energy Resources Conservation and Development Commission to develop procedures necessary for implementation of a new program to provide technical guidance and financial assistance for local governments to develop community energy resilience plans.
SEC. 2.Division 16.7 (commencing with Section 26450) is added to the Public Resources Code, to read:16.7.Community Energy Resilience Planning26450.For purposes of this division, the following definitions apply:
(a)Commission means the State Energy Resources Conservation and Development Commission.
(b)Community energy resilience means the capability of a local community, local government, tribal authority, or other municipality to provide and maintain stable electricity supply under changing conditions, including, but not limited to, outages of utility grid service.
(b)(c)Community energy resilience plan means a planning document prepared by a local government pursuant to this division that sets forth a strategy for reducing the adverse impacts associated with electrical outages. meeting local electrical loads with local clean distributed energy resources. Unless the context requires otherwise, plan means a community energy resilience plan.
(d)Electrical corporation has the same meaning as defined in Section 218 of the Public Utilities Code.
(c)(e)Local government means a city, county, city and county, or California Native American tribe, as defined in Section 21073.
(d)Public utility means an electrical corporation, as defined in Section 218 of the Public Utilities Code, or a local publicly owned electric utility, as defined in Section 224.3 of the Public Utilities Code.(f)Local publicly owned electric utility has the same meaning as defined in Section 224.3 of the Public Utilities Code.
(g)Resilience Valuation Index means a standardized, data-driven tool that assists local governments in conducting cost-benefit analyses of community energy resilience investments, such as distributed energy resources or microgrids. Unless the context requires otherwise, index means the Resilience Valuation Index.
26451.(a)Pursuant to this division, the commission shall develop and implement a grant program to award grants to local governments for the development of community energy resilience plans and for expediting local governments review of permits for distributed energy resources. that help achieve local energy resilience objectives and state clean energy and air quality goals.
(b)Before awarding grants pursuant to this division, the commission shall do both of the following:(1)Develop and adopt simple solicitation and evaluation procedures for applicants to submit a community energy resilience plan grant proposal to do both of the following:(A)Develop a community energy resilience plan, including a prioritization of funds for critical facilities in low-income or disadvantaged communities that are most likely to experience disproportionate adverse impacts from more frequent future electrical outages, followed in priority by other critical facilities in the planning area.(B)Develop a process for the expedited permit review of distributed energy resources by local governments.(2)Conduct a minimum of two public meetings to consider public comment.(c)The plan solicitation and evaluation procedures shall prioritize proposals for funding that would support equitable collaboration between public utilities, local governments, community-based organizations, and state agencies to yield plans that help achieve local energy resilience objectives and state renewable energy goals.(d)A community energy resiliency plan shall be consistent with the city, county, or city and county general plan and other local government planning documents. The plan shall include provisions to facilitate the expedited local permitting of distributed energy resources.(b)In developing the guidelines and application process for the grant program, the commission shall do all of the following:
(1)Prioritize applications from low-income communities that are most likely to experience power outages, disadvantaged communities that are most likely to experience power outages, or low-income and disadvantaged communities that are most likely to experience power outages first, followed by communities that are most likely to experience power outages.
(2)Make the application process as simple as possible.
(3)Conduct a minimum of two public meetings to receive and consider public comment before approving the guidelines and application process.
(c)For local governments located within the service territory of a local publicly owned electric utility, only the local publicly owned electric utility shall be eligible to apply for grant funding on behalf of the local government.
(e)(d)Grant funds awarded pursuant to this division may be used for plan development, including, but not limited to, all of the following activities:
(1)Hiring outside consultants or technical assistance providers to help with coordinating and drafting the plan.
(2)Identifying and coordinating with appropriate local government staff to draft the plan. A local government may hire a resilience manager to manage the plan development process and the implementation of projects identified in the plan. process.
(3)Convening and facilitating one or more community workshops enlisting local stakeholders, including, but not limited to, labor representatives, representatives from community-based organizations, community members, representatives from related technology vendors, local government staff in departments relating to emergency services, planning, and public works, disability rights advocates, and representatives from special districts, load-serving entities, school districts, environmental justice communities, communities of color, and other marginalized groups, to ensure that a diversity of perspectives and input is incorporated into the plan.
(4)Soliciting and using input from public utility operational and technical subject matter experts.(5)Providing guidance and support to each local government awarded a grant to designate a diverse plan steering committee to ensure robust and meaningful public participation. (f)(e)(1)A plan for which a local government is awarded a grant shall do all of the following:
(1)(A)Identify critical facilities, including facilities that can serve as community resilience hubs to accommodate and provide basic services to people who have lost power to their homes.
(2)(B)Identify locations and facilities where the construction of microgrids or other distributed energy resources could meet local resilience needs.
(3)(C)Identify critical facilities that are in greatest need of backup energy generation and potential backup energy systems that may meet the needs of those facilities.
(4)(D)Identify potential funding sources for implementation of projects included in the plan.
(E)Include a model ordinance template that may be adopted by a local government to establish a process for the expedited permit review of distributed energy resources by the local government.
(F)Demonstrate consistency with the city, county, or city and county general plan and other local government planning documents.
(2)The plan shall be developed in collaboration with the relevant electrical corporation or local publicly owned electric utility operational and technical subject matter experts.
(g)(f)Subject to any restrictions or limitations placed by outside funding programs, grants awarded to a local government pursuant to this division do not affect the local governments eligibility to receive other incentives available from federal, state, or other local governments, public utilities, electrical corporations, local publicly owned electric utilities, or any other source, or to leverage the grant funding awarded pursuant to this division with any other incentive.
(h)(g)As a condition of being awarded a grant pursuant to this division, a local government shall submit its plan to the commission within six months of adopting its plan.
(h)The commission shall maintain a publicly available and searchable database of all local governments awarded a grant pursuant to this division. The database shall include relevant metrics to be determined by the commission.
(i)(1)The commission shall prepare an annual summary of statewide program expenditures and hire an independent, third-party evaluator to quantify and evaluate the effects of the grant program.
(2)Pursuant to Section 9795 of the Government Code, the commission shall annually submit the summary to the Legislature and post the summary on its internet website.
26452.(a)The commission shall maintain a publicly available and searchable database of all local governments awarded a grant pursuant to this division. The database shall include relevant metrics to be determined by the commission. develop and maintain, on its internet website, a community energy resilience planning toolkit to support local governments development of community energy resilience plans. The toolkit shall include detailed information on typical planning steps, including, but not limited to, community asset mapping, stakeholder identification, community engagement, and technical and economic feasibility.
(b)The commission shall develop and maintain, on its internet website, a publicly available library of community energy resilience planning tools compiled from best planning practices, and a directory of prequalified consultants with energy resilience planning expertise who may assist grant recipients in plan development.
(c)(1)The commission shall prepare an annual summary of statewide program expenditures and hire an independent, third-party evaluator to quantify and evaluate the effects of the grant program.(2)Pursuant to Section 9795 of the Government Code, the commission shall annually submit the summary to the Legislature and post the summary on its internet website.(c)(1)The commission shall develop and maintain a publicly available Resilience Valuation Index to assist local governments in community energy resilience planning and support data-driven investment decisions.
(2)The index shall identify entities and populations within communities that are vulnerable to power outages or other climate disruptions, including, but not limited to, any of the following:
(A)Critical facilities, including, but not limited to, the types of facilities described in Public Utilities Commission Decision 19-05-042, Decision Adopting De-Energization Guidelines, and other related decisions.
(B)Public agencies.
(C)Small businesses.
(D)Commercial and industrial facilities.
(E)Education and childcare facilities.
(F)Food production and distribution facilities.
(G)Access and functional needs populations.
(H)Medically vulnerable populations.
(I)Disadvantaged or low-income populations.
(J)Rural or remote populations.
(K)Other communities or populations that the commission determines may be severely impacted by the loss of continuous electrical service.
(3)(A)The index shall catalog and quantify a range of potential resiliency values for each identified constituency or population.
(B)The index shall use publicly available information on the value of lost load, socioeconomic analyses, and other power outage resources, from reputable academic institutions, including from the Lawrence Berkeley National Laboratorys Interruption Cost Estimate Calculator.
(4)The commission shall post the index on its internet website and update the index annually.
(a)This act shall be known, and may be cited, as the Community Energy Resilience Act of 2022.
(b)The Legislature finds and declares all of the following:
(1)Development of community energy resilience plans will help ensure continuous electricity service during electrical outages, which in recent years have imposed enormous costs on California communities.
(2)Developing reliable and resilient electrical systems for critical facilities is a paramount public safety priority and is necessary to protect the health and well-being of California residents and businesses.
(3)Local governments typically lack the resources or expertise needed for community energy resilience planning sufficient to increase the usage of distributed clean energy resources.
(4)Local governments have the greatest degree of local political accountability, are best able to identify, working in collaboration with community-based organizations, which facilities are most important to local residents and necessary to maintain public health and safety, and can most effectively integrate the permitting and development of distributed energy resources capable of providing electricity during electrical outages.
(5)With proper engineering and planning, local governments are capable of accelerating the deployment of resilient clean electrical systems by taking advantage of state, federal, and other funding sources.
(c)It is the intent of the Legislature to direct the State Energy Resources Conservation and Development Commission to develop procedures necessary for implementation of a new program to provide technical guidance and financial assistance for local governments to develop community energy resilience plans.
SEC. 2.Division 16.7 (commencing with Section 26450) is added to the Public Resources Code, to read:16.7.Community Energy Resilience Planning26450.For purposes of this division, the following definitions apply:
(a)Commission means the State Energy Resources Conservation and Development Commission.
(b)Community energy resilience plan means a planning document prepared by a local government pursuant to this division that sets forth a strategy for reducing the adverse impacts associated with electrical outages. Unless the context requires otherwise, plan means a community energy resilience plan.
(c)Local government means a city, county, city and county, or California Native American tribe, as defined in Section 21073.
(d)Public utility means an electrical corporation, as defined in Section 218 of the Public Utilities Code, or a local publicly owned electric utility, as defined in Section 224.3 of the Public Utilities Code.
26451.(a)Pursuant to this division, the commission shall develop and implement a grant program to award grants to local governments for the development of community energy resilience plans and for expediting local governments review of permits for distributed energy resources.
(b)Before awarding grants pursuant to this division, the commission shall do both of the following:
(1)Develop and adopt simple solicitation and evaluation procedures for applicants to submit a community energy resilience plan grant proposal to do both of the following:
(A)Develop a community energy resilience plan, including a prioritization of funds for critical facilities in low-income or disadvantaged communities that are most likely to experience disproportionate adverse impacts from more frequent future electrical outages, followed in priority by other critical facilities in the planning area.
(B)Develop a process for the expedited permit review of distributed energy resources by local governments.
(2)Conduct a minimum of two public meetings to consider public comment.
(c)The plan solicitation and evaluation procedures shall prioritize proposals for funding that would support equitable collaboration between public utilities, local governments, community-based organizations, and state agencies to yield plans that help achieve local energy resilience objectives and state renewable energy goals.
(d)A community energy resiliency plan shall be consistent with the city, county, or city and county general plan and other local government planning documents. The plan shall include provisions to facilitate the expedited local permitting of distributed energy resources.
(e)Grant funds awarded pursuant to this division may be used for plan development, including, but not limited to, all of the following activities:
(1)Hiring outside consultants or technical assistance providers to help with coordinating and drafting the plan.
(2)Identifying and coordinating with appropriate local government staff to draft the plan. A local government may hire a resilience manager to manage the plan development process and the implementation of projects identified in the plan.
(3)Convening and facilitating one or more community workshops enlisting local stakeholders, including, but not limited to, labor representatives, representatives from community-based organizations, community members, representatives from related technology vendors, local government staff in departments relating to emergency services, planning, and public works, disability rights advocates, and representatives from special districts, load-serving entities, school districts, environmental justice communities, communities of color, and other marginalized groups, to ensure that a diversity of perspectives and input is incorporated into the plan.
(4)Soliciting and using input from public utility operational and technical subject matter experts.
(5)Providing guidance and support to each local government awarded a grant to designate a diverse plan steering committee to ensure robust and meaningful public participation.
(f)A plan for which a local government is awarded a grant shall do all of the following:
(1)Identify critical facilities, including facilities that can serve as community resilience hubs to accommodate and provide basic services to people who have lost power to their homes.
(2)Identify locations and facilities where the construction of microgrids or other distributed energy resources could meet local resilience needs.
(3)Identify critical facilities that are in greatest need of backup energy generation and potential backup energy systems that may meet the needs of those facilities.
(4)Identify potential funding sources for implementation of projects included in the plan.
(g)Subject to any restrictions or limitations placed by outside funding programs, grants awarded to a local government pursuant to this division do not affect the local governments eligibility to receive other incentives available from federal, state, or other local governments, public utilities, or any other source, or to leverage the grant funding awarded pursuant to this division with any other incentive.
(h)As a condition of being awarded a grant pursuant to this division, a local government shall submit its plan to the commission within six months of adopting its plan.
26452.(a)The commission shall maintain a publicly available and searchable database of all local governments awarded a grant pursuant to this division. The database shall include relevant metrics to be determined by the commission.
(b)The commission shall develop and maintain, on its internet website, a publicly available library of community energy resilience planning tools compiled from best planning practices, and a directory of prequalified consultants with energy resilience planning expertise who may assist grant recipients in plan development.
(c)(1)The commission shall prepare an annual summary of statewide program expenditures and hire an independent, third-party evaluator to quantify and evaluate the effects of the grant program.
(2)Pursuant to Section 9795 of the Government Code, the commission shall annually submit the summary to the Legislature and post the summary on its internet website.
|
Date
|
Status
|
|---|---|
| Aug 11, 2022 | August 11 hearing: Held in committee and under submission. |
| Aug 3, 2022 | August 3 set for first hearing. Placed on suspense file. |
| Jun 30, 2022 | Read second time and amended. Re-referred to Com. on APPR. |
| Jun 29, 2022 | From committee: Do pass as amended and re-refer to Com. on APPR. with recommendation: To consent calendar. (Ayes 13. Noes 0.) (June 29). |
| Jun 15, 2022 | June 22 hearing postponed by committee. |
| Jun 2, 2022 | Referred to Com. on U. & E. |
| May 26, 2022 | In Assembly. Read first time. Held at Desk. |
| May 25, 2022 | Read third time. Passed. (Ayes 39. Noes 0. Page 3928.) Ordered to the Assembly. |
| May 23, 2022 | Ordered to special consent calendar. |
| May 19, 2022 | From committee: Do pass. (Ayes 7. Noes 0. Page 3770.) (May 19). |
| May 13, 2022 | Set for hearing May 19. |
| Apr 4, 2022 | April 4 hearing: Placed on APPR suspense file. |
| Mar 25, 2022 | Set for hearing April 4. |
| Mar 21, 2022 | Read second time and amended. Re-referred to Com. on APPR. |
| Mar 17, 2022 | From committee: Do pass as amended and re-refer to Com. on APPR. (Ayes 13. Noes 0. Page 3094.) (March 14). |
| Mar 7, 2022 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on E., U. & C. |
| Mar 4, 2022 | Set for hearing March 14. |
| Jan 19, 2022 | Referred to Com. on E., U. & C. |
| Jan 5, 2022 | From printer. May be acted upon on or after February 4. |
| Jan 4, 2022 | Introduced. Read first time. To Com. on RLS. for assignment. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| May 25, 2022 | Special Consent SB833 Dodd et al. | Senate Floor |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
Bill Author
Bill Co-Author(s):