AB 2079: Groundwater extraction: large-diameter, high-capacity water wells: permits.
- Session Year: 2023-2024
- House: Assembly
- Latest Version Date: 2024-06-03
Current Status:
Failed
(2024-06-11: In committee: Set, first hearing. Failed passage.)
Introduced
In Committee
First Chamber
In Committee
Second Chamber
Enacted
Existing law, the Sustainable Groundwater Management Act, requires all groundwater basins designated as high- or medium-priority basins by the Department of Water Resources to be managed under a groundwater sustainability plan or coordinated groundwater sustainability plans, except as specified. Existing law authorizes any local agency or combination of local agencies overlying a groundwater basin to decide to become a groundwater sustainability agency for that basin and imposes specified duties upon that agency or combination of agencies, as provided.
Existing law requires the State Water Resources Control Board to adopt a model water well, cathodic protection well, and monitoring well drilling and abandonment ordinance implementing certain standards for water well construction, maintenance, and abandonment and requires each county, city, or water agency, where appropriate, to adopt a water well, cathodic protection well, and monitoring well drilling and abandonment ordinance that meets or exceeds certain standards. Under existing law, if a county, city, or water agency, where appropriate, fails to adopt an ordinance establishing water well, cathodic protection well, and monitoring well drilling and abandonment standards, the model ordinance adopted by the state board is required to take effect, and is required to be enforced by the county or city and have the same force and effect as if adopted as a county or city ordinance.
This bill would require a local enforcement agency, as defined, to perform specified activities at least 30 days before determining whether to approve a permit for a new large-diameter, high-capacity well, as defined. By imposing additional requirements on a local enforcement agency, the bill would impose a state-mandated local program. The bill would require, if the proposed large-diameter, high-capacity well is to be located in an area subject to management by a groundwater sustainability agency, the applicable groundwater sustainability agency, upon notice of a permit application, upon adoption or amendment of a groundwater sustainability plan, the groundwater sustainability agency to provide specified information to the local enforcement agency, including, but not limited to, the name of the applicable groundwater sustainability agency, the agency manager and contact information, and the applicable sustainable management criteria related to groundwater levels, including the groundwater level measurable objectives and minimum thresholds. The bill would require a local enforcement agency, before approving a permit for a large-diameter, high capacity well, to provide specified information to the applicant. The bill would prescribe certain standards a local enforcement agency would be required to follow in the approval or denial of the permit, including the location of the proposed large-diameter, high capacity well and specified geological and water supply considerations. The bill would provide exemptions for its provisions for specified water wells. The bill would provide that its provisions apply only to applications for permits for the construction, maintenance, abandonment, or destruction of water wells in basins identified in the Department of Water Resources Bulletin 118.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law, the Sustainable Groundwater Management Act, requires all groundwater basins designated as high- or medium-priority basins by the Department of Water Resources to be managed under a groundwater sustainability plan or coordinated groundwater sustainability plans, except as specified. Existing law authorizes any local agency or combination of local agencies overlying a groundwater basin to decide to become a groundwater sustainability agency for that basin and imposes specified duties upon that agency or combination of agencies, as provided.
Existing law requires the State Water Resources Control Board to adopt a model water well, cathodic protection well, and monitoring well drilling and abandonment ordinance implementing certain standards for water well construction, maintenance, and abandonment and requires each county, city, or water agency, where appropriate, to adopt a water well, cathodic protection well, and monitoring well drilling and abandonment ordinance that meets or exceeds certain standards. Under existing law, if a county, city, or water agency, where appropriate, fails to adopt an ordinance establishing water well, cathodic protection well, and monitoring well drilling and abandonment standards, the model ordinance adopted by the state board is required to take effect, and is required to be enforced by the county or city and have the same force and effect as if adopted as a county or city ordinance.
This bill would require a local enforcement agency, as defined, to perform specified activities at least 30 days before determining whether to approve a permit for a new large-diameter, high-capacity well, as defined. By imposing additional requirements on a local enforcement agency, the bill would impose a state-mandated local program. The bill would require, upon notice, a groundwater sustainability agency with oversight for the area of the basin where the proposed large-diameter, high-capacity well is to be located if the proposed large-diameter, high-capacity well is to be located in an area subject to management by a groundwater sustainability agency, the applicable groundwater sustainability agency, upon notice of a permit application, to provide specified information to the local enforcement agency, including, but not limited to, the name of the applicable groundwater sustainability agency, the agency manager and contact information, and the applicable sustainable management criteria related to groundwater levels, including the groundwater level measurable objectives and minimum thresholds. The bill would require a local enforcement agency, before approving a permit for a large-diameter, high capacity well, to provide specified information to the applicant. The bill would prescribe certain standards a local enforcement agency would be required to follow in the approval or denial of the permit, including the location of the proposed large-diameter, high capacity well and specified geological and water supply considerations. The bill would provide exemptions for its provisions for specified water wells. The bill would provide that its provisions apply only to applications for permits for the construction, maintenance, abandonment, or destruction of water wells in basins identified in the Department of Water Resources Bulletin 118.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law, the Sustainable Groundwater Management Act, requires all groundwater basins designated as high- or medium-priority basins by the Department of Water Resources to be managed under a groundwater sustainability plan or coordinated groundwater sustainability plans, except as specified. Existing law authorizes any local agency or combination of local agencies overlying a groundwater basin to decide to become a groundwater sustainability agency for that basin and imposes specified duties upon that agency or combination of agencies, as provided.
Existing law requires the State Water Resources Control Board to adopt a model water well, cathodic protection well, and monitoring well drilling and abandonment ordinance implementing certain standards for water well construction, maintenance, and abandonment and requires each county, city, or water agency, where appropriate, not later than January 15, 1990, to adopt a water well, cathodic protection well, and monitoring well drilling and abandonment ordinance that meets or exceeds certain standards. Under existing law, if a county, city, or water agency, where appropriate, fails to adopt an ordinance establishing water well, cathodic protection well, and monitoring well drilling and abandonment standards, the model ordinance adopted by the state board is required to take effect on February 15, 1990, effect, and is required to be enforced by the county or city and have the same force and effect as if adopted as a county or city ordinance.
This bill would require a local enforcement agency, as defined, to perform specified activities at least 30 days before determining whether to approve a permit for a new large-diameter, high-capacity well, as defined. By imposing additional requirements on a local enforcement agency, the bill would impose a state-mandated local program. The bill would require require, upon notice, a groundwater sustainability agency with oversight for the area of the basin where the local enforcement agency has well permitting jurisdiction proposed large-diameter, high-capacity well is to be located to provide specified information to the local enforcement agency, including, but not limited to, the name of the applicable groundwater sustainability agency, the agency manager and contact information, and the applicable sustainable management criteria related to groundwater levels, including the groundwater level measurable objectives and minimum thresholds. The bill would provide various requirements for the local enforcement agency to consider before approving or denying a permit. require a local enforcement agency, before approving a permit for a large-diameter, high capacity well, to provide specified information to the applicant. The bill would prescribe certain standards a local enforcement agency would be required to follow in the approval or denial of the permit, including the location of the proposed large-diameter, high capacity well and specified geological and water supply considerations. The bill would provide exemptions for its provisions for specified wells if they are proposed to be constructed with well screens and pump depths below the applicable minimum thresholds for groundwater levels as reported by the groundwater sustainability agency. water wells. The bill would provide that its provisions apply only to applications for permits for the construction, maintenance, abandonment, or destruction of water wells in basins identified in the Department of Water Resources Bulletin 118.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law, the Sustainable Groundwater Management Act, requires all groundwater basins designated as high- or medium-priority basins by the Department of Water Resources to be managed under a groundwater sustainability plan or coordinated groundwater sustainability plans, except as specified. Existing law authorizes any local agency or combination of local agencies overlying a groundwater basin to decide to become a groundwater sustainability agency for that basin and imposes specified duties upon that agency or combination of agencies, as provided.
Existing law requires the State Water Resources Control Board to adopt a model water well, cathodic protection well, and monitoring well drilling and abandonment ordinance implementing certain standards for water well construction, maintenance, and abandonment and requires each county, city, or water agency, where appropriate, not later than January 15, 1990, to adopt a water well, cathodic protection well, and monitoring well drilling and abandonment ordinance that meets or exceeds certain standards. Under existing law, if a county, city, or water agency, where appropriate, fails to adopt an ordinance establishing water well, cathodic protection well, and monitoring well drilling and abandonment standards, the model ordinance adopted by the state board is required to take effect on February 15, 1990, and is required to be enforced by the county or city and have the same force and effect as if adopted as a county or city ordinance.
This bill would require a local enforcement agency, as defined, to perform specified activities at least 30 days before determining whether to approve a permit for a new large-diameter, high-capacity well, as defined. By imposing additional requirements on a local enforcement agency, the bill would impose a state-mandated local program. The bill would require a groundwater sustainability agency with oversight for the area of the basin where the local enforcement agency has well permitting jurisdiction to provide specified information to the local enforcement agency, including, but not limited to, the name of the applicable groundwater sustainability agency, the agency manager and contact information, and the applicable sustainable management criteria related to groundwater levels, including the groundwater level measurable objectives and minimum thresholds. The bill would provide various requirements for the local enforcement agency to consider before approving or denying a permit. The bill would provide exemptions for its provisions for specified wells if they are proposed to be constructed with well screens and pump depths below the applicable minimum thresholds for groundwater levels as reported by the groundwater sustainability agency. The bill would provide that its provisions apply only to applications for permits for the construction, maintenance, abandonment, or destruction of water wells in basins identified in the Department of Water Resources Bulletin 118.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law, the Sustainable Groundwater Management Act, authorizes the State Water Resources Control Board to designate a groundwater basin as a probationary basin if the state board makes a certain determination and to develop an interim plan for the probationary basin. The act requires that a local agency or groundwater sustainability agency have 180 days to remedy the deficiency if the board designates the basin as a probationary basin.This bill would make nonsubstantive changes to the latter provision.Existing law, the Sustainable Groundwater Management Act, authorizes the State Water Resources Control Board to designate a groundwater basin as a probationary basin if the state board makes a certain determination and to develop an interim plan for the probationary basin. The act requires that a local agency or groundwater sustainability agency have 180 days to remedy the deficiency if the board designates the basin as a probationary basin.
This bill would make nonsubstantive changes to the latter provision.
The Legislature finds and declares all of the following:
(a)The groundwater extraction from large-diameter, high-capacity wells can interfere with nearby drinking water wells and result in impacts to critical infrastructure from subsidence.
(b)It is in the public interest to ensure that the permitting of new wells extracting groundwater will be conducted to minimize the impacts to drinking water wells and subsidence.
(c)Sustainable groundwater management in many parts of the state requires coordination between local agencies permitting water wells and groundwater sustainability agencies managing groundwater basins.
(d)People, businesses, and industries seeking to construct or operate water wells should be adequately informed about groundwater conditions and groundwater management programs that may affect the current or future use and operation of their wells.
(e)Applicants seeking, and agencies permitting, the construction and operation of water wells should take into account the reliability and sustainability of the groundwater sources intended to be used to avoid unexpected or unplanned well dewatering or loss of well production capacity, which could lead to higher rates of unexpected, unplanned, or premature well abandonment and dereliction that could pose additional threats to groundwater quality.
(f)Agencies issuing permits for the construction and operation of water wells should consider the potential for those wells to cause or contribute to land subsidence, which can have impacts on water quality by adversely affecting the concentration of naturally or artificially occurring chemical constituents of concern and posing other serious public health and economic problems.
SEC. 2.Article 5 (commencing with Section 13807) is added to Chapter 10 of Division 7 of the Water Code, to read:5.Well Sustainability13807.This article shall apply only to applications for permits for the construction, maintenance, abandonment, or destruction of water wells in basins identified in the Department of Water Resources Bulletin 118.
13807.1.The following definitions shall apply to this article:
(a)Community water system has the same meaning as provided in Section 116275 of the Health and Safety Code.
(b)Domestic well has the same meaning as provided in Section 116681 of the Health and Safety Code.
(c)Large-diameter, high-capacity well means any water well with a diameter of more than eight inches and intended to produce greater than two acre-feet annually. or greater.
(d)Local enforcement agency means any city, county, or water agency that has adopted and is administering an ordinance for the construction, maintenance, abandonment, or destruction of a water well pursuant to this chapter.
(e)Public water system has the same meaning as defined in Section 116275 of the Health and Safety Code.
(f)State small water system has the same meaning as provided in Section 116275 of the Health and Safety Code.
(g)Urban retail water supplier has the same meaning as provided in Section 10608.12.
13807.2.(a)A local enforcement agency shall perform all of the following activities at least 30 days before determining whether to approve a permit for a new large-diameter, high-capacity well:
(1)Provide electronic notice to the general public by posting notice of receipt of the application and the contents of the application on the local enforcement agencys internet website.
(2)Provide electronic notice to all relevant groundwater sustainability agencies managing within a 10-mile radius of a proposed well, including those in adjacent basins or counties, as applicable. agencies.
(3)Provide notice to all other local enforcement agencies, if any, administering well permitting programs within the basin in which the activities covered in the application would occur.(4)(3)Provide written notice through the United States Postal Service to the registered owners or agents of all parcels within a one-mile radius of the site where the activities covered in the application would occur and any relevant information on the well permitting process.
(5)(4)Provide electronic notice to the state board if the well is to be located within a groundwater basin that is designated as a probationary basin.
(b)If the proposed large-diameter, high-capacity well is to be located in an area subject to management by a groundwater sustainability agency, the applicable groundwater sustainability agency shall, upon notice of a permit application, Upon adoption or amendment of a groundwater sustainability plan, the groundwater sustainability agency shall provide all of the following information to the local enforcement agency:
(1)The name of the applicable groundwater sustainability plan being implemented and where an electronic copy of the plan may be accessed.
(2)The name of the applicable groundwater sustainability agency, the agency manager and contact information, and the applicable sustainable management criteria related to groundwater levels, including the groundwater level measurable objectives and minimum thresholds.
(3)The estimated depth to the groundwater level based on the most recent monitoring conducted by the groundwater sustainability agency for the area of the basin where the proposed activities covered by the application would occur.(3)Where the most recent groundwater level monitoring data can be obtained for the basin.
(4)Any Notice of fees, allocation, metering, spacing determinations, or other regulations or ordinances that the groundwater sustainability agency has adopted.
(5)Any updates to the information provided pursuant to this subdivision as necessary within 30 days, should changes occur.(6)(5)Notice of an inadequate determination, if applicable, by the department of the groundwater sustainability plan and the status of any action of the state board resulting from the department determination.
(c)Before approving any well permit for a large-diameter, high-capacity well, a local enforcement agency shall provide all both of the following to the applicant:
(1)The basin name, number, and priority as assigned by the department in its most recent Bulletin 118.
(2)The name of all groundwater sustainability agencies, if any, managing the basin in which the activities covered in the application would occur.
(3)Information on regulations or ordinances adopted by the groundwater sustainability agency relevant to the construction and operation of the proposed well, if applicable.(4)If applicable, notice to the applicant that the approval of the application and granting of any associated permit is subject to the regulatory authority of any groundwater sustainability agency managing the portion of the basin in which the activities covered in the application would occur. The notice shall specifically inform the applicant that in addition to any regulatory authority already being exercised, a groundwater sustainability agency or the state board for a probationary groundwater basin may exercise authority to limit groundwater extraction, the imposition of fees, and metering.13807.3.(a)A local enforcement agency shall not approve a permit for a large-diameter, high-capacity well if that well is proposed to be located within one-quarter mile of a well used for supplying domestic water to one or more persons or to a community.
(b)(1)A local enforcement agency shall not approve a permit for a large-diameter, high-capacity well if that well is proposed to be located within one-quarter mile of an area that has subsided greater than 0.5 feet in total since January 1, 2015, as reported and defined by the department based upon provided InSAR subsidence data report posted on the Natural Resources Agency open data portal and department internet websites.
(2)A local enforcement agency may approve a permit for a large-diameter, high-capacity well if the area identified in paragraph (1) has not had subsidence of more than 0.1 feet over the preceding four years, is consistent with the local groundwater sustainability plan, and is screened above geologic units known to be susceptible to compaction. plan.
(c)For areas subject to the Sustainable Groundwater Management Act (Part 2.74 (commencing with Section 10720) of Division 6), a local enforcement agency shall not approve a permit for any well unless that well is screened below the minimum thresholds applicable to that portion of the basin as established by the groundwater sustainability agency pursuant to paragraph (2) of subdivision (b) of Section 13807.2.(d)(c)To ensure the reliability and long-term operation of water wells within its jurisdiction, a local enforcement agency may determine not to approve an application or grant a permit based on criteria that are more stringent than those provided in this section.
13807.4.This article does not apply to applications or permits for any of the following:
(a)Water wells that will draw less than two acre-feet per year.
(b)Water wells that will be located on a parcel of five acres or fewer that is in an area that has been zoned by the local land use authority for rural residential use.
(c)Drinking water wells of an urban retail water supplier, state small water system, or a community water system.
(d)Large-diameter, high-capacity wells for the replacement or reconstruction of an existing large-diameter, high-capacity well that meets all of the following conditions:
(1)The replacing or reconstructed well shall not have a larger diameter or diameter, or shall not be used to pump more water annually than the previous well.
(2)The well being replaced shall be abandoned prior to initial operation of the replacement well.
(3)The replacement well is in substantially the same location as the well it is replacing or is to be moved to a location that would lessen impacts to domestic wells and wells that provide water for state small water systems or community water systems.
(e)Water wells associated with, or part of, a conjunctive use or water banking program, or a project that has approved environmental documents consistent with the California Environmental Quality Act (Division 13 (commencing with Section 21000) of the Public Resources Code).
(f)Water wells that are part of a groundwater remediation or protection project that aims to address groundwater contamination, water quality, or seawater intrusion.
(g)Injections well associated with the water wells described in subdivisions (e) and (f).
(h)(1)Water wells closer that one-quarter mile to a well used for supplying domestic water if the local enforcement agency has developed a well permitting ordinance or a well spacing ordinance that minimizes well interference impacts on drinking water wells and take into consideration local geologic conditions and anticipated pumping rates of the proposed well, including, but not limited to, well design and well seals.
(2)A local enforcement agency permitting wells described in this subdivision shall provide a copy of the well permitting ordinance to the department.
SEC. 3.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
The Legislature finds and declares all of the following:
(a)The groundwater extraction from large-diameter, high-capacity wells can interfere with nearby drinking water wells and result in impacts to critical infrastructure from subsidence.
(b)It is in the public interest to ensure that the permitting of new wells extracting groundwater will be conducted to minimize the impacts to drinking water wells and subsidence.
(c)Sustainable groundwater management in many parts of the state requires coordination between local agencies permitting water wells and groundwater sustainability agencies managing groundwater basins.
(d)People, businesses, and industries seeking to construct or operate water wells should be adequately informed about groundwater conditions and groundwater management programs that may affect the current or future use and operation of their wells.
(e)Applicants seeking, and agencies permitting, the construction and operation of water wells should take into account the reliability and sustainability of the groundwater sources intended to be used to avoid unexpected or unplanned well dewatering or loss of well production capacity, which could lead to higher rates of unexpected, unplanned, or premature well abandonment and dereliction that could pose additional threats to groundwater quality.
(f)Agencies issuing permits for the construction and operation of water wells should consider the potential for those wells to cause or contribute to land subsidence, which can have impacts on water quality by adversely affecting the concentration of naturally or artificially occurring chemical constituents of concern and posing other serious public health and economic problems.
SEC. 2.Article 5 (commencing with Section 13807) is added to Chapter 10 of Division 7 of the Water Code, to read:5.Well Sustainability13807.This article shall apply only to applications for permits for the construction, maintenance, abandonment, or destruction of water wells in basins identified in the Department of Water Resources Bulletin 118.
13807.1.The following definitions shall apply to this article:
(a)Community water system has the same meaning as provided in Section 116275 of the Health and Safety Code.
(b)Domestic well has the same meaning as provided in Section 116681 of the Health and Safety Code.
(c)Large-diameter, high-capacity well means any water well with a diameter of more than eight inches and intended to produce greater than two acre-feet annually.
(d)Local enforcement agency means any city, county, or water agency that has adopted and is administering an ordinance for the construction, maintenance, abandonment, or destruction of a water well pursuant to this chapter.
(e)Public water system has the same meaning as defined in Section 116275 of the Health and Safety Code.
(f)State small water system has the same meaning as provided in Section 116275 of the Health and Safety Code.
(g)Urban retail water supplier has the same meaning as provided in Section 10608.12.
13807.2.(a)A local enforcement agency shall perform all of the following activities at least 30 days before determining whether to approve a permit for a new large-diameter, high-capacity well:
(1)Provide electronic notice to the general public by posting notice of receipt of the application and the contents of the application on the local enforcement agencys internet website.
(2)Provide notice to all groundwater sustainability agencies managing within a 10-mile radius of a proposed well, including those in adjacent basins or counties, as applicable.
(3)Provide notice to all other local enforcement agencies, if any, administering well permitting programs within the basin in which the activities covered in the application would occur.
(4)Provide written notice through the United States Postal Service to the registered owners or agents of all parcels within a one-mile radius of the site where the activities covered in the application would occur and any relevant information on the well permitting process.
(5)Provide notice to the state board if the well is to be located within a groundwater basin that is designated as a probationary basin.
(b)Upon notice, a groundwater sustainability agency with oversight for the area of the basin where the proposed large-diameter, high-capacity well is to be located shall If the proposed large-diameter, high-capacity well is to be located in an area subject to management by a groundwater sustainability agency, the applicable groundwater sustainability agency shall, upon notice of a permit application, provide all of the following information to the local enforcement agency:
(1)The name of the applicable groundwater sustainability plan being implemented and where an electronic copy of the plan may be accessed.
(2)The name of the applicable groundwater sustainability agency, the agency manager and contact information, and the applicable sustainable management criteria related to groundwater levels, including the groundwater level measurable objectives and minimum thresholds.
(3)The estimated depth to the groundwater level based on the most recent monitoring conducted by the groundwater sustainability agency for the area of the basin where the proposed activities covered by the application would occur.
(4)Any fees, allocation, metering, spacing determinations, or other regulations or ordinances that the groundwater sustainability agency has adopted.
(5)Any updates to the information provided pursuant to this subdivision as necessary within 30 days, should changes occur.
(6)Notice of an inadequate determination, if applicable, by the department of the groundwater sustainability plan and the status of any action of the state board resulting from the department determination.
(c)Before approving any well permit for a large-diameter, high-capacity well, a local enforcement agency shall provide all of the following information to the applicant:
(1)The basin name, number, and priority as assigned by the department in its most recent Bulletin 118.
(2)The name of all groundwater sustainability agencies, if any, managing the basin in which the activities covered in the application would occur.
(3)Information on regulations or ordinances adopted by the groundwater sustainability agency relevant to the construction and operation of the proposed well. well, if applicable.
(4)Notice If applicable, notice to the applicant that the approval of the application and granting of any associated permit is subject to the regulatory authority of any groundwater sustainability agency managing the portion of the basin in which the activities covered in the application would occur. The notice shall specifically inform the applicant that in addition to any regulatory authority already being exercised, a groundwater sustainability agency or the state board for a probationary groundwater basin may exercise authority to limit groundwater extraction, the imposition of fees, and metering.
13807.3.(a)A local enforcement agency shall not approve a permit for a large-diameter, high-capacity well if that well is proposed to be located within one-quarter mile of a well used for supplying domestic water to one or more persons or to a community.
(b)(1)A local enforcement agency shall not approve a permit for a large-diameter, high-capacity well if that well is proposed to be located within one-quarter mile of an area that has subsided greater than 0.5 feet in total since January 1, 2015, as reported and defined by the department based upon provided InSAR subsidence data report posted on the Natural Resources Agency open data portal and department internet websites.
(2)A local enforcement agency may approve a permit for a large-diameter, high-capacity well if the area identified in paragraph (1) has not had subsidence of more than 0.1 feet over the preceding four years, is consistent with the local groundwater sustainability plan, and is screened above geologic units known to be susceptible to compaction.
(c)For areas subject to the Sustainable Groundwater Management Act (Part 2.74 (commencing with Section 10720) of Division 6), a local enforcement agency shall not approve a permit for any well unless that well is screened below the minimum thresholds applicable to that portion of the basin as established by the groundwater sustainability agency pursuant to paragraph (2) of subdivision (b) of Section 13807.2.
(d)To ensure the reliability and long-term operation of water wells within its jurisdiction, a local enforcement agency may determine not to approve an application or grant a permit based on criteria that are more stringent than those provided in this section.
13807.4.This article does not apply to applications or permits for any of the following water wells: following:
(a)Wells Water wells that will draw less than two acre-feet per year.
(b)Wells Water wells that will be located on a parcel of five acres or fewer that is in an area that has been zoned by the local land use authority for rural residential use.
(c)Drinking water wells of a public water system, an urban retail water supplier, state small water system, or a community water system.
(d)Large-diameter, high-capacity wells for the replacement or reconstruction of an existing large-diameter, high-capacity well that meets all of the following conditions:
(1)The replacing or reconstructed well shall not have a larger diameter or be used to pump more water annually than the previous well.
(2)The well being replaced shall be abandoned prior to initial operation of the replacing replacement well.
(3)The replacing replacement well is in substantially the same location as the well it is replacing or is to be moved to a location that would lessen impacts to domestic wells and wells that provide water for state small water systems or community water systems.
(e)Water wells associated with, or part of, a conjunctive use or water banking program, or a project that has approved environmental documents consistent with the California Environmental Quality Act (Division 13 (commencing with Section 21000) of the Public Resources Code).
(f)Water wells that are part of a groundwater remediation or protection project that aims to address groundwater contamination, water quality, or seawater intrusion.
SEC. 3.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
The Legislature finds and declares all of the following:
(a)The groundwater extraction from large-diameter, high-capacity wells can interfere with nearby drinking water wells and result in impacts to critical infrastructure from subsidence.
(b)It is in the public interest to ensure that the permitting of new wells extracting groundwater will be conducted to minimize the impacts to drinking water wells and subsidence.
(c)Sustainable groundwater management in many parts of the state requires coordination between local agencies permitting water wells and groundwater sustainability agencies managing groundwater basins.
(d)People, businesses, and industries seeking to construct or operate water wells should be adequately informed about groundwater conditions and groundwater management programs that may affect the current or future use and operation of their wells.
(e)Applicants seeking, and agencies permitting, the construction and operation of water wells should take into account the reliability and sustainability of the groundwater sources intended to be used to avoid unexpected or unplanned well dewatering or loss of well production capacity, which could lead to higher rates of unexpected, unplanned, or premature well abandonment and dereliction that could pose additional threats to groundwater quality.
(f)Agencies issuing permits for the construction and operation of water wells should consider the potential for those wells to cause or contribute to land subsidence, which can have impacts on water quality by adversely affecting the concentration of naturally or artificially occurring chemical constituents of concern and posing other serious public health and economic problems.
SECTION 1.SEC. 2.Article 5 (commencing with Section 13807) is added to Chapter 10 of Division 7 of the Water Code, to read:5.Well Sustainability13807.This article shall apply only to applications for permits for the construction, maintenance, abandonment, or destruction of water wells in basins identified in the Department of Water Resources Bulletin 118.
13807.5.The Legislature finds and declares all of the following:(a)The groundwater extraction from large-diameter, high-capacity wells can interfere with nearby drinking water wells and result in impacts to critical infrastructure from subsidence.(b)It is in the public interest to ensure that the permitting of new wells extracting groundwater will be conducted to minimize the impacts to drinking water wells and subsidence.(c)Sustainable groundwater management in many parts of the state requires coordination between local agencies permitting water wells and groundwater sustainability agencies managing groundwater basins.(d)People, businesses, and industries seeking to construct or operate water wells should be adequately informed about groundwater conditions and groundwater management programs that may affect the current or future use and operation of their wells.(e)Applicants seeking, and agencies permitting, the construction and operation of water wells should take into account the reliability and sustainability of the groundwater sources intended to be used to avoid unexpected or unplanned well dewatering or loss of well production capacity, which could lead to higher rates of unexpected, unplanned, or premature well abandonment and dereliction that could pose additional threats to groundwater quality.(f)Agencies permitting for the construction and operation of water wells should consider the potential for those wells to cause or contribute to land subsidence, which can have impacts on water quality by adversely affecting the concentration of naturally or artificially occurring chemical constituents of concern and posing other serious public health and economic problems.13808.13807.1.The following definitions shall apply to this article:
(a)Community water system has the same meaning as provided in Section 116275 of the Health and Safety Code.
(b)Domestic well has the same meaning as provided in Section 116681 of the Health and Safety Code.
(a)(c)Large-diameter, high-capacity well means any water well with a diameter of more than eight inches and intended to produce greater than two acre-feet annually.
(b)(d)Local enforcement agency means any city, county, or water agency that has adopted and is administering an ordinance for the construction, maintenance, abandonment, or destruction of a water well pursuant to this chapter.
(e)Public water system has the same meaning as defined in Section 116275 of the Health and Safety Code.
(f)State small water system has the same meaning as provided in Section 116275 of the Health and Safety Code.
13808.5.13807.2.(a)A local enforcement agency shall perform all of the following activities at least 30 days before determining whether to approve a permit for a new large-diameter, high-capacity well:
(1)Provide electronic notice to the general public by posting notice of receipt of the application and the contents of the application on the local enforcement agencys internet website.
(2)Provide notice to all groundwater sustainability agencies managing within a 10-mile radius of a proposed well, including those in adjacent basins or counties, as applicable.
(3)Provide notice to all other local enforcement agencies, if any, administering well permitting programs within the basin in which the activities covered in the application would occur.
(4)Provide written notice through the United States Postal Service to the registered owners or agents of all parcels within a one-mile radius of the site where the activities covered in the application would occur and any relevant information on the well permitting process.
(5)Provide notice to the state board if the well is to be located within a groundwater basin that is designated as a probationary basin.
(b)The Upon notice, a groundwater sustainability agency with oversight for the area of the basin where the local enforcement agency has well permitting jurisdiction proposed large-diameter, high-capacity well is to be located shall provide all of the following information to the local enforcement agency:
(1)The name of the applicable groundwater sustainability plan being implemented and where an electronic copy of the plan may be accessed.
(2)The name of the applicable groundwater sustainability agency, the agency manager and contact information, and the applicable sustainable management criteria related to groundwater levels, including the groundwater level measurable objectives and minimum thresholds.
(3)The estimated depth to the groundwater level based on the most recent monitoring conducted by the groundwater sustainability agency for the area of the basin where the proposed activities covered by the application would occur.
(4)Any fees, allocation, metering, spacing determinations, or other regulations or ordinances that the groundwater sustainability agency has adopted.
(5)Any updates to the information provided pursuant to this subdivision as necessary, necessary within 30 days, should changes occur.
(6)Notice of an inadequate determination, if applicable, by the department of the groundwater sustainability plan and the status of any action of the state board resulting from the department determination.
(c)Before approving any well permit for a large-diameter, high-capacity well, a local enforcement agency shall provide all of the following information to the applicant:
(1)The basin name, number, and priority as assigned by the department in its most recent Bulletin 118.
(2)The name of all groundwater sustainability agencies, if any, managing the basin in which the activities covered in the application would occur.
(3)Information on regulations or ordinances adopted by the groundwater sustainability agency relevant to the construction and operation of the proposed well.
(4)Notice to the applicant that the approval of the application and granting of any associated permit is subject to the regulatory authority of any groundwater sustainability agency managing the portion of the basin in which the activities covered in the application would occur. The notice shall specifically inform the applicant that in addition to any regulatory authority already being exercised, a groundwater sustainability agency or the state board for a probationary groundwater basin may exercise authority to limit groundwater extraction, the imposition of fees, and metering.
13809.13807.3.(a)A local enforcement agency shall not approve a permit for a large-diameter, high-capacity well if that well is proposed to be located within one-quarter mile of a well used for supplying domestic water to one or more persons or to a community.
(b)(1)A local enforcement agency shall not approve a permit for a large-diameter, high-capacity well if that well is proposed to be located within one-quarter mile of an area that has subsided greater than 0.5 feet in total since January 1, 2015, as reported and defined by the department based upon provided InSAR subsidence data report posted on the Natural Resources Agency open data portal and department internet websites.
(2)A local enforcement agency may approve a permit for a large-diameter, high-capacity well if the area identified in paragraph (1) has not had subsidence of over more than 0.1 feet for four consecutive years, over the preceding four years, is consistent with the local groundwater sustainability plan, and is screened above geologic units known to be susceptible to compaction.
(c)A For areas subject to the Sustainable Groundwater Management Act (Part 2.74 (commencing with Section 10720) of Division 6), a local enforcement agency shall not approve a permit for any well unless that well is screened below the minimum thresholds applicable to that portion of the basin as established by the groundwater sustainability agency pursuant to paragraph (2) of subdivision (b) of Section 13808.5. 13807.2.
(d)To ensure the reliability and long-term operation of water wells within its jurisdiction, a local enforcement agency may determine not to approve an application or grant a permit based on criteria that are more stringent than those provided in this section.
13809.5.13807.4.This article does not apply to applications or permits for any of the following wells if they are proposed to be constructed with well screens and pump depths below the applicable minimum thresholds for groundwater levels as reported by the groundwater sustainability agency pursuant to paragraph (2) of subdivision (b) of Section 13808.5 or otherwise provided to the local enforcement agency by the groundwater sustainability agency: water wells:
(a)Wells that will draw less than two acre-feet per acre. year.
(b)Wells that will be located on a parcel of five acres or fewer that is in an area that has been zoned by the local land use authority for rural residential use.
(c)Public supply wells or Drinking water wells of a public water system, state small water system, or a community water systems. system.
(d)Large-diameter, high-capacity wells for the replacement or reconstruction of an existing large-diameter, high-capacity well that meets all of the following conditions:
(1)The replacing or reconstructed well shall not have a larger diameter or be used to pump more water annually than the previous well.
(2)The well being replaced shall be abandoned prior to initial operation of the replacing well.
(3)The replacing well is in substantially the same location as the well it is replacing or is to be moved to a location that would lessen impacts to domestic wells and wells that provide water for state small water systems or community water systems.
SEC. 2.SEC. 3.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
This article shall apply only to applications for permits for the construction, maintenance, abandonment, or destruction of water wells in basins identified in the Department of Water Resources Bulletin 118.
13807.5.The Legislature finds and declares all of the following:
(a)The groundwater extraction from large-diameter, high-capacity wells can interfere with nearby drinking water wells and result in impacts to critical infrastructure from subsidence.
(b)It is in the public interest to ensure that the permitting of new wells extracting groundwater will be conducted to minimize the impacts to drinking water wells and subsidence.
(c)Sustainable groundwater management in many parts of the state requires coordination between local agencies permitting water wells and groundwater sustainability agencies managing groundwater basins.
(d)People, businesses, and industries seeking to construct or operate water wells should be adequately informed about groundwater conditions and groundwater management programs that may affect the current or future use and operation of their wells.
(e)Applicants seeking, and agencies permitting, the construction and operation of water wells should take into account the reliability and sustainability of the groundwater sources intended to be used to avoid unexpected or unplanned well dewatering or loss of well production capacity, which could lead to higher rates of unexpected, unplanned, or premature well abandonment and dereliction that could pose additional threats to groundwater quality.
(f)Agencies permitting for the construction and operation of water wells should consider the potential for those wells to cause or contribute to land subsidence, which can have impacts on water quality by adversely affecting the concentration of naturally or artificially occurring chemical constituents of concern and posing other serious public health and economic problems.
13808.The following definitions shall apply to this article:
(a)Large-diameter, high-capacity well means any water well with a diameter of more than eight inches and intended to produce greater than two acre-feet annually.
(b)Local enforcement agency means any city, county, or water agency that has adopted and is administering an ordinance for the construction, maintenance, abandonment, or destruction of a water well pursuant to this chapter.
13808.5.(a)A local enforcement agency shall perform all of the following activities at least 30 days before determining whether to approve a permit for a new large-diameter, high-capacity well:
(1)Provide electronic notice to the general public by posting notice of receipt of the application and the contents of the application on the local enforcement agencys internet website.
(2)Provide notice to all groundwater sustainability agencies managing within a 10-mile radius of a proposed well, including those in adjacent basins or counties, as applicable.
(3)Provide notice to all other local enforcement agencies, if any, administering well permitting programs within the basin in which the activities covered in the application would occur.
(4)Provide written notice through the United States Postal Service to the registered owners or agents of all parcels within a one-mile radius of the site where the activities covered in the application would occur and any relevant information on the well permitting process.
(b)The groundwater sustainability agency with oversight for the area of the basin where the local enforcement agency has well permitting jurisdiction shall provide all of the following information to the local enforcement agency:
(1)The name of the applicable groundwater sustainability plan being implemented and where an electronic copy of the plan may be accessed.
(2)The name of the applicable groundwater sustainability agency, the agency manager and contact information, and the applicable sustainable management criteria related to groundwater levels, including the groundwater level measurable objectives and minimum thresholds.
(3)The estimated depth to the groundwater level based on the most recent monitoring conducted by the groundwater sustainability agency for the area of the basin where the proposed activities covered by the application would occur.
(4)Any fees, allocation, metering, spacing determinations, or other regulations or ordinances that the groundwater sustainability agency has adopted.
(5)Any updates to the information provided pursuant to this subdivision as necessary, should changes occur.
(c)Before approving any well permit for a large-diameter, high-capacity well, a local enforcement agency shall provide all of the following information to the applicant:
(1)The basin name, number, and priority as assigned by the department in its most recent Bulletin 118.
(2)The name of all groundwater sustainability agencies, if any, managing the basin in which the activities covered in the application would occur.
(3)Information on regulations or ordinances adopted by the groundwater sustainability agency relevant to the construction and operation of the proposed well.
(4)Notice to the applicant that the approval of the application and granting of any associated permit is subject to the regulatory authority of any groundwater sustainability agency managing the portion of the basin in which the activities covered in the application would occur. The notice shall specifically inform the applicant that in addition to any regulatory authority already being exercised, a groundwater sustainability agency may exercise authority to limit groundwater extraction, the imposition of fees, and metering.
13809.(a)A local enforcement agency shall not approve a permit for a large-diameter, high-capacity well if that well is proposed to be located within one-quarter mile of a well used for supplying domestic water to one or more persons or to a community.
(b)(1)A local enforcement agency shall not approve a permit for a large-diameter, high-capacity well if that well is proposed to be located within one-quarter mile of an area that has subsided greater than 0.5 feet in total since January 1, 2015, as reported and defined by the department based upon provided InSAR subsidence data report posted on the Natural Resources Agency open data portal and department internet websites.
(2)A local enforcement agency may approve a permit for a large-diameter, high-capacity well if the area identified in paragraph (1) has not had subsidence of over 0.1 feet for four consecutive years, is consistent with the local groundwater sustainability plan, and is screened above geologic units known to be susceptible to compaction.
(c)A local enforcement agency shall not approve a permit for any well unless that well is screened below the minimum thresholds applicable to that portion of the basin as established by the groundwater sustainability agency pursuant to paragraph (2) of subdivision (b) of Section 13808.5.
(d)To ensure the reliability and long-term operation of wells within its jurisdiction, a local enforcement agency may determine not to approve an application or grant a permit based on criteria that are more stringent than those provided in this section.
13809.5.This article does not apply to applications or permits for the following wells if they are proposed to be constructed with well screens and pump depths below the applicable minimum thresholds for groundwater levels as reported by the groundwater sustainability agency pursuant to paragraph (2) of subdivision (b) of Section 13808.5 or otherwise provided to the local enforcement agency by the groundwater sustainability agency:
(a)Wells that will draw less than two acre-feet per acre.
(b)Wells that will be located on a parcel of five acres or fewer that is in an area that has been zoned by the local land use authority for rural residential use.
(c)Public supply wells or state small or community water systems.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
SECTION 1.Section 10735.4 of the Water Code is amended to read:10735.4.(a)If the board designates a basin a probationary basin pursuant to paragraph (1), (2), or (4) of subdivision (a) of Section 10735.2, a local agency or groundwater sustainability agency shall have 180 days to remedy the deficiency. The board may appoint a mediator or other facilitator, after consultation with affected local agencies, to assist in resolving disputes, and identifying and implementing actions that will remedy the deficiency.(b)After the 180-day period provided by subdivision (a), the board may provide additional time to remedy the deficiency if it finds that a local agency is making substantial progress toward remedying the deficiency.(c)The board may develop an interim plan pursuant to Section 10735.8 for the probationary basin at the end of the period provided by subdivision (a) or any extension provided pursuant to subdivision (b), if the board, in consultation with the department, determines that a local agency has not remedied the deficiency that resulted in designating the basin a probationary basin.(a)If the board designates a basin as a probationary basin pursuant to paragraph (1), (2), or (4) of subdivision (a) of Section 10735.2, a local agency or groundwater sustainability agency shall have 180 days to remedy the deficiency. The board may appoint a mediator or other facilitator, after consultation with affected local agencies, to assist in resolving disputes, and identifying and implementing actions that will remedy the deficiency.
(b)After the 180-day period provided by subdivision (a), the board may provide additional time to remedy the deficiency if it finds that a local agency is making substantial progress toward remedying the deficiency.
(c)The board may develop an interim plan pursuant to Section 10735.8 for the probationary basin at the end of the period provided by subdivision (a) or any extension provided pursuant to subdivision (b), if the board, in consultation with the department, determines that a local agency has not remedied the deficiency that resulted in designating the basin as a probationary basin.
|
Date
|
Status
|
|---|---|
| Jun 11, 2024 | In committee: Set, first hearing. Failed passage. |
| Jun 3, 2024 | From committee chair, with author's amendments: Amend, and re-refer to committee. Read second time, amended, and re-referred to Com. on N.R. & W. |
| May 29, 2024 | Referred to Coms. on N.R. & W. and L. GOV. |
| May 21, 2024 | In Senate. Read first time. To Com. on RLS. for assignment. |
| May 20, 2024 | Read third time. Passed. Ordered to the Senate. (Ayes 41. Noes 17. Page 5326.) |
| May 9, 2024 | Read second time. Ordered to third reading. |
| May 8, 2024 | From committee: Do pass. (Ayes 10. Noes 4.) (May 8). |
| Apr 29, 2024 | Re-referred to Com. on APPR. |
| Apr 25, 2024 | Read second time and amended. |
| Apr 24, 2024 | From committee: Amend, and do pass as amended and re-refer to Com. on APPR. (Ayes 10. Noes 3.) (April 23). |
| Apr 17, 2024 | Re-referred to Com. on W., P., & W. |
| Apr 16, 2024 | From committee chair, with author's amendments: Amend, and re-refer to Com. on W., P., & W. Read second time and amended. |
| Apr 1, 2024 | Re-referred to Com. on W., P., & W. |
| Mar 21, 2024 | From committee chair, with author's amendments: Amend, and re-refer to Com. on W., P., & W. Read second time and amended. |
| Mar 21, 2024 | Referred to Com. on W., P., & W. |
| Feb 6, 2024 | From printer. May be heard in committee March 7. |
| Feb 5, 2024 | Read first time. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Jun 11, 2024 | Do pass as amended, but first amend, and re-refer to the Committee on [Local Government] | Senate Standing Committee on Natural Resources and Water |
Failed |
|
| May 20, 2024 | AB 2079 Bennett Assembly Third Reading | Assembly Floor |
Passed |
|
| May 8, 2024 | Do pass. | Assembly Standing Committee on Appropriations |
Passed |
|
| Apr 23, 2024 | Do pass as amended and be re-referred to the Committee on [Appropriations] | Assembly Standing Committee on Water, Parks, and Wildlife |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| Agricultural Council Of California | ** Against | |
| Association Of California Water Agencies | ** Against | |
| California Apple Commission | ** Against | |
| California Association Of Wheat Growers | ** Against | |
| California Association Of Winegrape Growers | ** Against | |
| California Bean Shippers Association | ** Against | |
| California Blueberry Association | ** Against | |
| California Blueberry Commission | ** Against | |
| California Cattlemen'S Association | ** Against | |
| California Chamber Of Commerce | ** Against | |
| California Citrus Mutual | ** Against | |
| California Coastkeeper Alliance | ** Support | |
| California Cotton Ginners and Growers Association | ** Against | |
| California Farm Bureau Federation | ** Against | |
| California Fresh Fruit Association | ** Against | |
| California Groundwater Association | ** Against | |
| California League of Food Producers | ** Against | |
| California Municipal Utilities Association | ** Against | |
| california pear grower association | ** Against | |
| California Rural Legal Assistance Foundation | ** Support | |
| California Seed Association | ** Against | |
| California State Association Of Counties | ** Against | |
| California Walnut Commission | ** Against | |
| CivicWell | ** Support | |
| cleanearth4kids.org | ** Support | |
| Clean Water Action | ** Support | |
| Community Water Center | ** Support | |
| Cucamonga Valley Water District | ** Against | |
| Desert Water Agency | ** Against | |
| Eastern Municipal Water District | ** Against | |
| Environmental Law Foundation | ** Support | |
| Grower-Shipper Association of Central California | ** Against | |
| Inland Empire Utilities Agency | ** Against | |
| Jurupa Community Services District | ** Against | |
| Kern County Water Agency | ** Against | |
| Kings River Conservation District | ** Against | |
| Leadership Counsel for Justice & Accountability | ** Support | |
| Modesto Irrigation District | ** Against | |
| Natural Resources Defense Council | ** Support | |
| Northern California Water Association | ** Against | |
| Olive Growers Council of California | ** Against | |
| Rancho Water | ** Against | |
| Regional Water Authority | ** Against | |
| Restore Hetch Hetchy | ** Support | |
| Sierra Club California | ** Support | |
| Solano County Water Agency | ** Against | |
| Southern California Water Coalition | ** Against | |
| South San Joaquin Irrigation District | ** Against | |
| united ag | ** Against | |
| United Water Conservation District | ** Against | |
| Valley Ag Water Coalition | ** Against | |
| Water Replenishment District Of Southern California | ** Against | |
| We Advocate Through Environmental Review | ** Support | |
| Western Agricultural Processors Association | ** Against | |
| Western Growers Association | ** Against | |
| Western Municipal Water District | ** Against | |
| Wine Institute | ** Against |
SENATE COMMITTEE ON NATURAL RESOURCES AND WATER
Senator Dave Min, Chair
2023 - 2024 Regular
Bill No: AB Hearing Date: June 11, 2024
Author: | Bennett | ||
Version: | June 3, 2024 Amended | ||
Urgency: | No | Fiscal: | Yes |
Consultant: | Paul Jacobs | ||
Subject: Groundwater extraction: large-diameter, high-capacity water wells: permits
SUMMARY
This bill would require greater interagency coordination and public notice regarding applications to drill water wells and prohibit a local agency from approving new “large-diameter, high-capacity” wells within one-quarter mile of domestic wells and areas of significant land subsidence, unless specifically exempted.
BACKGROUND AND EXISTING LAW
Background:
Sustainable Groundwater Management Act. Passed in 2014, the Sustainable Groundwater Management Act (SGMA) provides a comprehensive framework to manage groundwater resources in overdrafted groundwater basins (i.e., those basins deemed high- or medium-priority). To comply with SGMA, local agencies in overdrafted basins had to form a groundwater sustainability agencies (GSA) by 2017 and develop groundwater sustainability plans (GSPs) by 2020 or 2022 that will lead to sustainable groundwater management over 20 years. SGMA defines sustainable groundwater management as the avoidance of “undesirable results,” as defined, and SGMA’s explicit intent is to keep management of groundwater resources at the local level while allowing for state intervention if local agencies are unsuccessful or get off track in meeting their sustainability goals. SGMA also intends for GSAs to have flexibility to address conditions unique to their particular basin and states that it does not alter groundwater rights.
Groundwater Wells. The Department of Water Resources (DWR) estimates there are two million groundwater wells in California at present and indicates that between 7,000 and 15,000 new wells are constructed each year. Permitting for construction, alteration, or destruction of groundwater wells is handled by local enforcement agencies (LEAs); typically this is a county department of environmental health, but cities and water agencies also exercise this authority in some cases. LEAs ensure compliance with well standards set by DWR (in Bulletin 74) before issuing a permit. Some agencies adopt standards for wells that surpass DWR guidelines. Others may require the application for a new well to be reviewed by an expert consultant to determine the likelihood of drinking well interference and other impacts.
A permitting decision can be either discretionary or ministerial, depending on whether the agency is required to exercise judgment in the approval process. Currently, most groundwater well permits are issued ministerially in compliance with well construction standards that primarily address protections for groundwater quality. There is often a lack of coordination between local well-permitting entities and the GSAs tasked with managing the basin sustainably.
Governor’s Executive Orders. In the spring of 2022, the state was in the midst of a deep drought, and groundwater pumping was causing domestic wells to dry up and increased land subsidence. In response to worsening drought conditions, Governor Newsom issued Executive Order (EO) N-7-22 with the intent to lessen the number of wells that were permitted that could impact domestic wells or increase subsidence during the drought emergency. Specifically, paragraph nine prohibited a local or public agency from issuing a permit for a new groundwater well or the alteration of an existing well in a groundwater basin subject to SGMA “without first obtaining written verification from a [GSA] managing the basin or area of the basin where the well is proposed to be located that groundwater extraction by the proposed well would not be inconsistent with any sustainable groundwater management program established in any applicable [GSP] adopted by that [GSA] and would not decrease the likelihood of achieving a sustainability goal for the basin covered by such a plan.” Furthermore, the EO required that an LEA determine that a proposed new well or modification of an existing well would not likely interfere with nearby wells and would not cause subsidence that would harm infrastructure before issuing a permit.
EO N-3-23 extended the provisions related to groundwater well permitting and added an exemption for permits issued for equivalent replacement wells.
Observations and Analysis of Executive Orders N-7-22 and N-3-23 (EO report). In March of 2024, DWR released a report that drew on a survey conducted in the spring of 2023. The report summarizes the various approaches LEAs took to comply with the EOs, observations of groundwater conditions that occurred while these actions were taken, and policy recommendations that can be used to develop future solutions to align land use planning and well permitting with groundwater management and use.
In the eighteen months since the EOs were enacted, DWR found that almost 2,000 wells were reported to DWR’s Dry Well Reporting System, with the largest concentration of reports coming from the San Joaquin and Tulare basins. Land subsidence of up to 1 foot or more was observed in the San Joaquin Valley, mainly in Tulare and Kings Counties. Seven of the top ten counties with the greatest number of permits overlie basins which have historically exhibited the greatest extent and rate of land subsidence in the state. The report also notes that well interference and increased subsidence from new wells can occur in non-drought years, so enacting well permitting standards should apply to all water year types and basins.
The report concluded that the EOs increased coordination among the local agencies and broadened the considerations to include sustainable management of the groundwater basin. The EOs provided direction to local agencies on how SGMA requirements should be considered and included in the well-permitting process.
However, the EOs had no mechanism to ensure compliance and continued subsidence and well permitting in vulnerable areas indicate that the EOs ultimately failed to achieve its goal.
Among DWR’s recommendations are to require public disclosure about well-permitting applications, develop standards for well spacing and well depth, set minimum standards, and exempt certain domestic wells based on size and volume.
Existing law:
- Requires, under SGMA, local agencies to sustainably manage groundwater in high- or medium-priority basins by 2040. Defines sustainable management of groundwater as the avoidance of the following six “undesirable results:” (a) chronic lowering of groundwater levels; (b) reduction of groundwater storage; (c) seawater intrusion; (d) degraded water quality; (e) land subsidence; and (f) depletions of interconnected surface water. Water Code (WC) §10720 et seq.
- Permits a GSA to require registration of any groundwater extraction facility (e.g., groundwater well) within its management area. WC §10725.6.
- Prohibits a GSA from issuing a permit for the construction, modification, or abandonment of a groundwater well unless authorized by a county to do so. Permits a GSA to request that a county forward permit applications for construction, modification, or reactivation of groundwater wells to the GSA before approval and requires counties to consider such a request from a GSA. WC §10726.4 (b).
- Defines “well” or “water well” as any artificial excavation for the purpose of extracting water from, or injecting water into, the underground. Excludes oil and gas wells, geothermal wells, and wells used to dewater during destruction or stabilize hillsides or earth embankments from the definition of “well” and “water well.” WC §13710.
- Requires every person who drills, expands, or destroys a water well, cathodic protection well, groundwater monitoring well, or geothermal heat exchange well to file a well completion report with DWR containing specified information within 60 days of completing the construction, alteration, abandonment, or destruction of the well. WC §13751.
- Defines “domestic well” as a groundwater well used to supply water for the domestic needs of an individual residence or water system that is not a public water system and has no more than four connections. Health and Safety Code (HSC) §116681(i).
- Defines “Urban retail water supplier” as a water supplier, either publicly or privately owned, that directly provides potable municipal water to more than 3,000 end users or that supplies more than 3,000 acre-feet of potable water annually at retail for municipal purposes. WC §10608.12(af).
PROPOSED LAW
This bill:
- Provides that this bill shall apply to the 515 groundwater basins identified by the DWR in Bulletin 118.
- Defines “large-diameter, high-capacity well” as any water well with a diameter of eight inches or greater.
- Defines “local enforcement agency” (LEA) as any city, county, or water agency that has adopted and is administering an ordinance for the construction, maintenance, abandonment, or destruction of a water well.
- Requires an LEA to do the following at least 30 days prior to approving a permit for a large-diameter, high capacity water well:
- Provide notice to the public by posting the application on the LEA’s website;
- Provide electronic notice to all relevant GSAs;
- Provide a written notice via U.S. Postal Service to all registered owners or agents of parcels within a one-mile radius of the proposed well. The notice shall include information about the well permitting process; and
- Provide electronic notice to the State Water Resources Control Board (State Water Board) if the proposed well is to be located in a probationary basin.
- Upon adoption or amendment of a GSP, requires a GSA to provide the following information to the LEA:
- The name of the applicable GSP and where an electronic copy of the GSP may be accessed;
- The name of the applicable GSA, the GSA manager and contact information, and applicable sustainable groundwater sustainable management criteria;
- Where the most recent groundwater level monitoring data can be obtained for the basin;
- Notice of fees, allocation, metering, spacing determinations, or other regulations or ordinances that the GSA has adopted; and
- Notice of an inadequate determination by DWR, if applicable, and the status of any action by the State Water Board pertaining to the inadequate determination.
- Requires the LEA to provide the following information to an applicant before approving a permit for a large-diameter, high-capacity well:
- The basin’s name, number, and priority as designated by DWR; and
- The name of all GSAs managing the basin, if any, where the well will be located.
- Prohibits an LEA that has not developed a well permitting ordinance from approving a large diameter, high-capacity well within one-quarter of a mile of a domestic well. LEAs are exempt from this restriction if they have developed a well permitting ordinance or a well spacing ordinance that minimizes well interference impacts on drinking water wells and take into consideration local geologic conditions and anticipated pumping rates of the proposed well, including, but not limited to, well design and well seals. LEAs that permit wells through this exemption are required to provide a copy of their well permitting ordinance to DWR.
- Prohibits an LEA from approving a large diameter, high-capacity well within one-quarter of a mile of an area that DWR has reported as having subsided more than 0.5 feet since January 1, 2015 based on subsidence data. Provides, however, that an LEA may approve a well in such an area if the area has not had more than 0.1 feet of subsidence over the preceding four years and if the well is consistent with an applicable GSP.
- Provides that an LEA may deny an application to approve a well based on criteria that is more stringent than that outlined in this bill.
- Provides that this bill does not apply to applications or permits for any of the following:
- Wells that pump less than two acre-feet (AF) annually;
- Wells that will be located on a parcel five acres or less that is zoned rural-residential;
- Drinking water wells of an urban retail water supplier, state small water system, or a community water system;
- Large-diameter, high-capacity wells for the replacement of an existing well so long as it shall not pump more water annually than the well being replaced, is substantially in the same location as the well being replaced, and meets other specified conditions;
- Water wells that are part of a conjunctive use or water banking program that have an approved environmental document;
- Water wells that are part of a groundwater remediation project; and
- Injection wells associated with the water wells described in e) and f) above.
- Provides that no reimbursement by the state is required by this bill because local agencies have the authority to levy service charges, fees, or assessments sufficient to cover the implementation costs.
ARGUMENTS IN SUPPORT
According to the author, “AB 2079 requires a county, city, or water agency (local enforcement agency) with jurisdiction over well-permitting to provide notice to the public of any wells proposed within its jurisdiction. Specifically the bill requires electronic notification to the public via a posting on the appropriate entity’s public website, notice to agencies in a 10-mile radius of the proposed well, notice to any other agencies administering well permitting programs, and physical notices to be sent to owners of parcels within a 1-mile radius of the proposed well.”
“Additionally, the bill requires a groundwater sustainability agency with jurisdiction to provide the local enforcement agency with information regarding the local groundwater sustainability plan, the information for the GSA manager, estimated depth of groundwater levels, any ordinances or rules established relating to groundwater sustainability/well permitting, and a notice to the well applicant of the rules and fees they may be subject to.”
“Finally, AB 2079 prohibits a local enforcement agency from approving wells with a diameter of 8 inches or more, and intended to extract more than 2 acre-feet per year, if that well is in an area with subsidence, or within a quarter mile of a domestic well.”
According to a coalition of environmental and drinking water advocacy groups, “During the recent dry periods from 2011-2017 and 2018-2022, many California groundwater basins saw the rapid drawdown of groundwater levels due to unchecked permitting of new groundwater extraction sites, leading to subsidence, wells running dry, and other undesirable results. Impacts are likely to continue as large, high-capacity wells can have impacts to drinking water, even during wet periods, or when groundwater basins achieve sustainability as envisioned by the Sustainable Groundwater Management Act (SGMA).”
“Local Groundwater Sustainability Agencies do not have the power to stop new wells from being drilled, regardless of how those wells may limit their ability to meet goals under SGMA. Currently, the responsibility and authority to issue well permits lies solely at the county level. However, counties are not tasked with reaching groundwater sustainability and typically issue permits without consideration of undesirable impacts or permanent damage to aquifers, communities, and infrastructure.”
ARGUMENTS IN OPPOSITION
A coalition that includes the California State Association of Counties, CalChamber, agricultural associations, and water agencies are opposed to the bill unless it is amended. According to the coalition letter submitted to the Committee, their concerns are “…primarily focused on two key issues: (1) the directive that no well permits can be issued for a well proposed to be located within a quarter mile of an area that has subsided more than 6 inches since January 2015; and (2) the requirement that new wells be very deep in order to gain approval. We are concerned that this bill is currently too restrictive and may impede ways to achieve groundwater sustainability. We also disagree with the approach of solving subsidence with blocking new wells rather than the bigger picture approach advanced in the Sustainable Groundwater Management Act (SGMA).”
The letter mentions that rather than focusing on new wells as this bill does, “Continued focus on sufficient GSPs and compliance with those GSPs is necessary to ensuring that SGMA’s goals are reached and negative consequences like subsidence are reduced.” The letter also discusses issues related to supporting local control rather than top-down directives, undermining important water storage efforts, completely restricting new wells in the entire Southern San Joaquin Valley, and requirements that will hurt small farmers and small operations most. The coalition provides requested amendments that they say will make this bill workable and protect California businesses and communities. Their requests include that the bill be amended “…to focus on increasing communication between GSAs, LEAs, and well applicants. The bill should also further support GSAs in exercising their authorities to impose reasonable extraction limitations to protect against subsidence and well spacing requirements.”
COMMENTS
Dual referral. This bill is referred to this Committee and the Senate Local Government Committee. Elements of the bill under the latter Committee’s jurisdiction will be discussed before that Committee and are included here for completeness and context only.
Finding the Right Balance. The DWR report makes clear that wells permitted near domestic wells risk leaving communities without any drinking water and the impact of new wells risks increasing subsidence, thus damaging infrastructure and risking public safety. Requiring communication and notification between LEAs, GSAs, and well applicants before a permitting agency approves a permit for a new well or for alteration of an existing well supports the principal purpose of SGMA – to ensure basins are managed in a sustainable manner. If permitting agencies issue permits without consideration of its impact to a GSP, the likelihood of undesirable results, such as drinking well interference or subsidence, will only increase. This extra communication and coordination will help GSAs ensure the basin is managed in a sustainable manner.
The well permitting restrictions in this bill provides prescriptive ways to protect drinking water and prevent subsidence. AB 2079 implements the recommendations made by DWR, although the report did not recommend specific details for restrictions. It is understandable that standards need to be set, however finding the right balance between local control, nuanced flexibility based on local conditions, and consistent statewide restrictions to protect drinking water wells and reduce subsidence is a delicate endeavor to achieve.
In consultation with DWR, the author’s office has recently made efforts to achieve this balance in recent amendments, particularly by adding the exemption to the quarter-mile distance from drinking well restriction for LEAs who have a well permitting ordinance. This allows for the protection of drinking wells while retaining local control and accounting for nuanced local conditions. The recent amendments also removed and clarified many of the notification requirements.
However, there is likely more progress to be made in finding the right balance in this bill, particularly with the subsidence restriction. While the current 0.5 feet of subsidence restriction since 2015 allows LEAs to approve a well in an area if the area has not had more than 0.1 feet of subsidence over the preceding four years, it is not clear why these numbers have been chosen as the limits. Could a different subsidence restriction over a different time period also protect against further subsidence and infrastructure damage? Could another type of carveout other than the 0.1 feet of subsidence exemption provide more local control and flexible nuance while still protecting against further subsidence?
As the bill moves forward, the author may want to consider further negotiations with DWR, this Committee, and stakeholders to seek the right balance between protecting drinking water wells and preventing subsidence, and maintaining local control and flexible nuances for local conditions.
The Committee may wish to reserve the right to re-hear the bill should aspects of the bill within its jurisdiction be amended substantially in the future.
Triggering CEQA? The California Environmental Quality Act (CEQA) only applies to projects where (1) there is a discretionary action of a public agency and (2) that action is likely to lead to significant environmental impacts. Unless the project meets both of these tests, CEQA is not applied. Ministerial review means that an agency does not have discretionary power over whether to approve or disapprove a project. If the project meets certain objective requirements, the agency must approve it. Certain elements of this bill, particularly those within WC §13807.3, may change what has been a ministerial review of well permitting into a discretionary one, and potentially trigger CEQA.
Author Amendments. There are a couple technical clean up items from the recent author amendments that the Committee may wish to consider to approve on behalf of the author.
- Add clarification that injection wells used for the purposes of groundwater recharge are also exempt from this bill. Author amendments clarify that injection wells were included in the exemptions added by the Assembly Water, Parks, and Wildlife Committee related to water banking and groundwater remediation, but the part on groundwater recharge was accidentally left out. There is also technical clean up needed for this amendment. See Amendment 1.
- Technical amendment. The new section on LEA exemptions for having a well permitting ordinance needs minor changes. See Amendment 2.
Committee Amendments. The Committee may wish to consider the following amendments:
- Remove definition of “Public Water System.” This definition is no longer needed after the Assembly Water, Parks, and Wildlife Committee amendments removed all references to these water systems in the bill. See Amendment 3.
- Add “Urban Wholesale Water Supplier” to list of exempted entities and add definition. Clarify that the Assembly Water, Parks, and Wildlife Committee exemption for urban retail water suppliers also should include urban wholesale water suppliers. The intent of these amendments are to exclude drinking water wells from this bill. See Amendment 3 and 4.
- Expand replacement well exemption to allow a former production well to be used as a monitoring well. Some GSAs convert production wells for monitoring purposes. To add more flexibility to this bill, rather than require a replaced well to be abandoned, this amendment will clarify that a prior well needs to be destroyed per well standards or allow for that well to be converted for monitoring purposes. See Amendment 4.
Prior legislation.
AB 1563 (Bennett, 2023) would have prohibited a county, city, or any other well permitting agency from approving a permit for a new groundwater well or for alteration of an existing well in a critically overdrafted basin subject to SGMA unless certain conditions are met. AB 1563 is pending before the Senate Local Government Committee.
AB 429 (Bennett, 2023) was substantially similar to AB 1563. AB 429 was referred to the Assembly Water Parks and Wildlife Committee but never heard.
AB 2201 (Bennett, 2022) would have required local agencies that permit groundwater wells to obtain written verification stating that a proposed well will not undermine sustainable groundwater management or cause well interference prior to approving a permit application for a groundwater well, unless the well was exempted. AB 2201 returned to the Assembly for a concurrence vote, but was never taken up.
SB 1317 (Wolk, 2016) would have required a city or county overlying a high- or medium-priority basin to prohibit the issuance of a permit for a new groundwater extraction facility or require a permit applicant to demonstrate that extraction of groundwater from the proposed facility would not contribute to, or create, an undesirable result. SB 1317 was referred to the Assembly Water Parks and Wildlife Committee but never heard.
SUGGESTED AMENDMENTS
AMENDMENT 1:
13807.4. (g) Injections well Injection wells associated with the water wells described in subdivisions (e) and (f), or that are used for the purposes of groundwater recharge.
AMENDMENT 2:
13807.4. (h) (1) Water wells closer that than one-quarter mile to a well used for supplying domestic water if the local enforcement agency has developed a well permitting ordinance or a well spacing ordinance that minimizes well interference impacts on drinking water wells and take takes into consideration local geologic conditions and anticipated pumping rates of the proposed well, including, but not limited to, well design and well seals.
AMENDMENT 3:
13807.1. (e) “Public water system” has the same meaning as defined in Section 116275 of the Health and Safety Code.
(f) (e) “State small water system” has the same meaning as provided in Section 116275 of the Health and Safety Code.
(g) (f) “Urban retail water supplier” has the same meaning as provided in Section 10608.12.
(g) “Urban wholesale water supplier” has the same meaning as provided in Section 10608.12.
AMENDMENT 4:
13807.4. (c) Drinking water wells of an urban retail water supplier, urban wholesale water supplier, state small water system, or a community water system.
(d) (2) Within 180 days of the completion of a replacement well the The well being replaced shall be destroyed in accordance with Part III, Section 23 of the California Well Standards, or converted to a monitoring well. abandoned prior to initial operation of the replacement well.
SUPPORT
California Climate and Agriculture Network
California Coastkeeper Alliance
California Environmental Voters
California Rural Legal Assistance Foundation
Civicwell
Clean Earth 4 Kids
Clean Water Action
Community Alliance with Family Farmers
Community Water Center
Environmental Law Foundation
Junior Philanthropists Foundation
Leadership Counsel for Justice & Accountability
Natural Resources Defense Council
Restore Hetch Hetchy
We Advocate Thorough Environmental Review
OPPOSITION
Agricultural Council of California (unless amended)
Association of California Water Agencies (ACWA) (unless amended)
California Apple Commission (unless amended)
California Association of Wheat Growers (unless amended)
California Association of Winegrape Growers (unless amended)
California Bean Shippers Association (unless amended)
California Blueberry Association (unless amended)
California Blueberry Commission (unless amended)
California Cattlemen's Association (unless amended)
California Chamber of Commerce (unless amended)
California Citrus Mutual (unless amended)
California Cotton Ginners and Growers Association (unless amended)
California Farm Bureau Federation (unless amended)
California Fresh Fruit Association (unless amended)
California Groundwater Association (unless amended)
California Groundwater Coalition
California League of Food Producers (unless amended)
California Manufacturers & Technology Association (unless amended)
California Municipal Utilities Association (unless amended)
California Pear Grower Association (unless amended)
California Seed Association (unless amended)
California State Association of Counties (CSAC) (unless amended)
California Walnut Commission (unless amended)
Coachella Valley Water District (unless amended)
Corning Sub-basin Groundwater Sustainability Agency (unless amended)
County of Del Norte
County of Fresno
County of Stanislaus
Desert Water Agency (unless amended)
Elsinore Valley Municipal Water District (unless amended)
Grower-shipper Association of Central California (unless amended)
Kern County Water Agency (unless amended)
Kings River Conservation District (unless amended)
League of California Cities (unless amended)
Modesto Irrigation District (unless amended)
Northern California Water Association (unless amended)
Olive Growers Council of California (unless amended)
Orange County Water District
Rural County Representatives of California (RCRC) (unless amended)
San Joaquin River Exchange Contractors Water Authority (unless amended)
San Luis Delta-Mendota Water Authority (unless amended)
Santa Clara Valley Water District (unless amended)
Solano County Board of Supervisors
Solano County Water Agency (unless amended)
Turlock Irrigation District (unless amended)
United Ag (unless amended)
United Water Conservation District (unless amended)
Water Replenishment District of Southern California (unless amended)
Western Agricultural Processors Association (unless amended)
Western Growers Association (unless amended)
Westlands Water District (unless amended)
Wine Institute (unless amended)
-- END --
ASSEMBLY THIRD READING
ATR Bill Id:AB 2079
Author:(Bennett)
As Amended Ver:April 25, 2024
Majority vote
SUMMARY
Requires greater inter-agency coordination and public notice regarding applications to drill water wells and prohibits a local agency from approving new "large-diameter, high-capacity" wells within one-quarter mile of domestic wells and in areas experiencing significant land subsidence.
Major Provisions
- Defines "large-diameter, high-capacity well" as any water well with a diameter greater than eight inches and that pumps more than two acre-feet (AF) of water annually.
- Defines "local enforcement agency" (LEA) as any city, county, or water agency that has adopted and is administering an ordinance for the construction, maintenance, abandonment, or destruction of a water well.
- Requires an LEA to notify the public, other local agencies involved in groundwater management, and land owners at least 30 days prior to approving a permit for a large-diameter, high capacity water well.
- Requires, upon notice, a groundwater sustainability agency (GSA) with oversight of the area where a proposed large-diameter, high-capacity well is to be located to provide specified information regarding groundwater management, groundwater regulations, groundwater fees, and groundwater level thresholds to an LEA.
- Requires an LEA to provide specified information to an applicant regarding groundwater management and groundwater regulations before approving a permit to drill a large-diameter, high-capacity well.
- Prohibits an LEA from approving a large diameter, high-capacity well within one-quarter of a mile of a domestic well.
- Prohibits an LEA from approving a large diameter, high-capacity well within one-quarter mile of an area that the Department of Water Resources (DWR) has reported as having subsided more than 0.5 feet since January 1, 2015 based on data provided in the InSAR subsidence data report. Provides, however, that an LEA may approve a well in such an area if the area has not had more than 0.1 feet of subsidence over the preceding four years and if the well is consistent with an applicable GSP and is screened above geologic units know to be susceptible to compaction.
- Prohibits, in basins subject to the Sustainable Groundwater Management Act (SGMA), an LEA from approving a permit for any well unless it is screened below the minimum thresholds established in the groundwater sustainability plan (GSP) applicable to the area of the basin where the well is to be located.
- Provides that an LEA may deny an application to approve a well based on criteria that is more stringent than that outlined in this bill.
- Provides that this bill does not apply to applications or permits for any of the following:
- Wells that pump less than two AF annually;
- Wells that will be located on a parcel five acres or less that is zoned rural-residential;
- Drinking water wells of an urban retail water supplier, state small water system, or a community water system;
- Large-diameter, high-capacity wells for the replacement of an existing large-diameter, high capacity well so long as it will not pump more water annually than the well being replaced and is in a similar location as the well being replaced.
- Water wells that are part of a conjunctive use or water banking program that have an approved environmental document; and
- Water wells that are part of a groundwater remediation project.
COMMENTS
According to DWR, groundwater provides approximately 40% of California's water supply in a "normal" year and as much as 60% in dry years. DWR estimates there are two million groundwater wells in California at present and indicates that between 7,000 and 15,000 new wells are constructed each year. Permitting for construction, alteration, or destruction of groundwater wells is handled by local agencies; typically this is a county department of environmental health, but cities and water agencies also exercise this authority in some cases. LEAs at a minimum, ensure compliance with well standards set by DWR (in Bulletin 74) before issuing a permit. Some LEAs adopt standards for wells that surpass DWR guidelines.
Currently, a permit for a groundwater well is typically deemed a "ministerial" action by an LEA. Ministerial actions do not require the exercise of any discretion by the LEA: "'ministerial' describes a governmental decision involving little or no personal judgement by the public official as to the wisdom or manner of carrying out the project. The public official merely applies the law to the facts as presented but uses no special discretion or judgement in reaching a decision" (14 California Code of Regulations Section 15369).
Governor's drought executive orders (EO). The Governor issued EO N-7022 on March 28, 2022, to extend the then existing drought emergency measures and require various administrative responses to the previous drought. Among these actions, paragraph nine of EO N-7-22 prohibited a local or public agency from issuing a permit for a new groundwater well or the alteration of an existing well in a groundwater basin subject to SGMA "without first obtaining written verification from a [GSA] managing the basin or area of the basin where the well is proposed to be located that groundwater extraction by the proposed well would not be inconsistent with any sustainable groundwater management program established in any applicable [GSP] adopted by that [GSA] and would not decrease the likelihood of achieving a sustainability goal for the basin covered by such a plan." Furthermore, the EO required that an LEA determine that a proposed new well or modification of an existing well would not likely interfere with nearby wells and would not cause subsidence that would harm infrastructure before issuing a permit. EO N-3-23 issued on February 13, 2023 again extended the then existing drought emergency and the provisions related to groundwater well permitting with minor changes to address any wells that must be moved related to the construction of high-speed rail.
Groundwater Well Permitting: Observations and Analysis of Executive Orders N-7-22 and N-3-23 (EO report). Completed in March 2024, this report notes that local agencies adopted various approaches to complying with the well permitting requirements of the EOs. These approaches included individual consultation on a permit-by-permit basis, reliance on existing requirements deemed sufficient, reliance on information submitted by applicants, passage of a broad resolution claiming any new well was consistent with relevant GSPs, and reliance on a report by a licensed professional. In some cases, GSAs and LEAs were simply unwilling to perform the verification process mandated in the EOs. There was little that DWR could do for those opting to not comply; as the EO report notes, "there is also no mechanism in the EOs to ensure compliance." The EO report notes that at least 1,911 wells were reported as going dry via the voluntary Dry Well Reporting System from March 2022 through August 28, 2023 and that there were several areas of land subsidence of up to one foot in parts of the Sacramento Valley and San Joaquin Valley. The EO report includes DWR recommendations for statutory concepts to replace the EOs: 1) require disclosures; 2) set minimum standards; 3) exempt certain discrete types of wells and procedures; and 4) establish applicability of requirements (i.e., specify to groundwater basins are subject to requirements). This bill is based on the recommendations contained in the EO report.
Interferometric Synthetic Aperture Radar (InSAR) subsidence data report. This dataset is derived from satellite imagery collected and processed a under contract with DWR. DWR makes this subsidence data available to GSAs as part of its SGMA technical assistance program for GSP development and implementation. Data collection began in late 2014. The dataset includes point data that represent average vertical displacement values for 100 meter by 100 meter areas. The data was updated in 2018, 2019, and 2020 and has been updated quarterly since October 2021 (with the latest update in January 2024). This bill prohibits permitting a new large-diameter, high-capacity well within one-quarter mile of an area identified as having greater than 0.5 feet of land subsidence since January 1, 2015 based on InSAR data and interpretation.
According to the Author
"SGMA was passed to establish a statewide framework to help protect groundwater basins from over-pumping and have them reach long-term sustainable pumping levels. In March of 2022, the Governor signed Executive Order (EO) N-7-22 to establish new well permitting requirements in order to ensure new wells were evaluated for their impact on neighboring wells and land subsidence. Thousands of wells were permitted, with only a cursory ministerial approval process between the 2014 passage of SGMA and the governor's 2022 [EO]. Thousands of drinking water wells that often times served disadvantage communities went dry during that same period. [DWR] performed an extensive review followed by a thorough report on the implementation and effectiveness of the Governor's [EO]. [This bill] now implements the recommendations from DWR to ensure that new wells are evaluated for their impact on neighboring wells and land subsidence."
Arguments in Support
CleanEarth4Kids.org supports this bill asserting that many California communities face serious shortages of drinking water due in part to unregulated overpumping of groundwater. CleanEarth4Kids.org observes that groundwater levels plummeted during droughts experienced over the past decade and a half and that "high-capacity wells were drilled with no oversight or thought to the impacts to our drinking water." CleanEarth4Kids.org argues this bill is necessary to protect our children's health and future.
Arguments in Opposition
The Valley Ag Water Coalition (VAWC) opposes this bill "because it represents an unnecessary intrusion into local control, interferes with the regulatory authority granted to [GSAs] under [SGMA], and adds burdensome requirements on GSAs at a time when they are focused on implementation of [GSPs]—the majority of which have been approved by [DWR]." VAWC further asserts the approach contained in this bill is contrary to the principle of SGMA that groundwater should be managed locally and tailored to unique local conditions which DWR has embraced when evaluating GSPs. Finally, VAWC contends that this bill "threatens state and local investments in groundwater banks and indirect potable reuse projects by prohibiting or interfering with the withdrawal of water placed into aquifers throughout the state."
FISCAL COMMENTS
The State Water Resources Control Board and DWR anticipate minor and absorbable costs resulting from the implementation of this bill.
VOTES
ASM WATER, PARKS, AND WILDLIFE: 10-3-2
YES: Papan, Addis, Alvarez, Bennett, Bonta, Garcia, Hart, Luz Rivas, Schiavo, Weber
NO: Alanis, Gallagher, Davies
ABS, ABST OR NV: Mathis, Villapudua
ASM APPROPRIATIONS: 10-4-1
YES: Wicks, Arambula, Bryan, Calderon, Wendy Carrillo, Mike Fong, Friedman, Haney, Hart, Pellerin
NO: Sanchez, Dixon, Jim Patterson, Ta
ABS, ABST OR NV: Villapudua
UPDATED
VERSION: April 25, 2024
CONSULTANT: Pablo Garza / W., P., & W. / (916) 319-2096 FN: 0002923
Date of Hearing: May 8, 2024
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Buffy Wicks, Chair
ABPCA Bill Id:AB 2079
Author:(Bennett) – As Amended Ver:April 25, 2024
Policy Committee: | Water, Parks and Wildlife | Vote: | 10 - 3 |
|
| ||
|
|
Urgency: No State Mandated Local Program: Yes Reimbursable: No
SUMMARY:
This bill requires greater interagency coordination and public notice regarding applications to drill water wells and prohibits a local agency from approving a new “large-diameter, high-capacity” (LDHCW) well within one-quarter mile of a domestic well or an area of significant land subsidence.
Specifically, this bill, among other things:
- Requires a local enforcement agency (LEA) to perform numerous specified activities at least 30 days before determining whether to approve a permit for an LDHCW.
- Requires the applicable groundwater sustainability agency (GSA), if the proposed LDHCW is to be located in an area subject to management by the GSA, upon notice of a permit application, to provide specified information to the LEA.
- Requires an LEA to provide specified information to an applicant before approving any well permit for an LDHCW.
- Prohibits an LEA from approving an LDHCW if that well is proposed to be located within one-quarter mile of a well used for supplying domestic water to one or more persons or to a community.
- Prohibits an LEA from approving an LDHCW within one-quarter of a mile of an area that has subsided greater than 0.5 feet in total since January 1, 2015, as specified.
- Prohibits an LEA, for areas subject to the Sustainable Groundwater Management Act (SGMA), from approving a permit for any well unless it is screened below the minimum thresholds applicable to that portion of the basin as established by the GSA, as specified.
- Provides that an LEA may deny an application to approve a well based on criteria that are more stringent than those outlined in this bill.
- Exempts applications or permits for specified types of wells from the requirements of this bill.
For a more detailed summary of this bill’s provisions, please see the Assembly Water, Parks, and Wildlife Committee analysis of this bill.
FISCAL EFFECT:
The State Water Resources Control Board and the Department of Water Resources (DWR) anticipate minor and absorbable costs.
COMMENTS:
1) Purpose. According to the author:
In March of 2022, the Governor signed Executive Order (EO) N-7-22 to establish new well permitting requirements in order to ensure new wells were evaluated for their impact on neighboring wells and land subsidence. Thousands of wells were permitted, with only a cursory ministerial approval process between the 2014 passage of SGMA and the governor's 2022 [EO]. Thousands of drinking water wells that often times served disadvantaged communities went dry during that same period. [DWR] performed an extensive review followed by a thorough report on the implementation and effectiveness of the Governor's [EO]. [This bill] now implements the recommendations from DWR to ensure that new wells are evaluated for their impact on neighboring wells and land subsidence.
2) Background. Permitting for construction, alteration, or destruction of groundwater wells is handled by local agencies; typically this is a county department of environmental health but, in some cases, cities and water agencies also exercise this authority. LEAs at a minimum, ensure compliance with well standards set by DWR before issuing a permit. Some LEAs adopt standards for wells that surpass DWR guidelines. Often, a permit for a groundwater well is deemed a “ministerial” action by an LEA. Ministerial actions do not require the exercise of any discretion by the LEA.
The Governor issued Executive Order (EO) N-7022 on March 28, 2022, to extend the then existing drought emergency and require various administrative responses to the previous drought. Among these actions, the EO prohibited a local or public agency from issuing a permit for a new groundwater well or the alteration of an existing well in a groundwater basin subject to SGMA without first obtaining written verification from a GSA managing the basin or area of the basin where the well is proposed to be located that groundwater extraction by the proposed well would not be inconsistent with any sustainable groundwater management program established in any applicable groundwater sustainability plan (GSP) adopted by that GSA and would not decrease the likelihood of achieving a sustainability goal for the basin covered by such a plan. Further, the EO required that an LEA determine that a proposed new well or modification of an existing well would not likely interfere with nearby wells and would not cause subsidence that would harm infrastructure before issuing a permit. EO N-3-23 issued on February 13, 2023, again extended the then existing drought emergency and the provisions related to groundwater well permitting with minor changes.
A March 2024 DWR report titled “Groundwater Well Permitting: Observations and Analysis of Executive Orders N-7-22 and N-3-23” (EO report) notes that local agencies adopted various approaches to complying with the well permitting requirements of the aforementioned EOs. These approaches included individual consultation on a permit-by-permit basis, reliance on existing requirements deemed sufficient, reliance on information submitted by applicants, passage of a broad resolution claiming any new well was consistent with relevant GSPs, and reliance on a report by a licensed professional. In some cases, GSAs and LEAs were simply unwilling to perform the verification process mandated in the EOs. There was little DWR could do for those opting not to comply; as the EO report notes, “there is also no mechanism in the EOs to ensure compliance.” The EO report notes that at least 1,911 wells were reported as going dry via the voluntary Dry Well Reporting System from March 2022 through August 2023, and that there were several areas of land subsidence of up to one foot in parts of the Sacramento Valley and San Joaquin Valley. The EO report includes DWR’s recommendations for statutory concepts to replace the EOs, and this bill is based on DWR’s recommendations.
Writing in support, a coalition of environmental and equity organizations notes:
AB 2079’s protections are needed to protect drinking water, prevent land subsidence, and ensure land use decisions do not delay or halt progress to meet groundwater sustainability. AB 2079 protects communities, and limits subsidence by preventing new, large-diameter and high-capacity wells in sensitive areas, such as within one-quarter mile of drinking water sources…We cannot continue an unregulated race to the bottom of our precious groundwater resources. The result of this path would be to leave entire communities throughout the state without a reliable source of clean, safe, and affordable drinking water.
Writing in an oppose-unless-amended position, a coalition of agricultural, water, and business organizations argue, among other things, that SGMA was designed to govern groundwater based on the relative use of groundwater, not based on the number of wells. They contend, “This bill’s pure focus on new wells is misplaced.” They further argue that this bill serves as “an end-run around SGMA, placing a widespread moratorium on new wells throughout much of the state in an attempt to resolve issues GSAs are already addressing.”
Analysis Prepared by: Nikita Koraddi / APPR. / (916) 319-2081
Date of Hearing: April 23, 2024
ASSEMBLY COMMITTEE ON WATER, PARKS, AND WILDLIFE
Diane Papan, Chair
ABPCA Bill Id:AB 2079 (
Author:Bennett) – As Amended Ver:April 16, 2024
SUBJECT: Groundwater extraction: large-diameter, high-capacity water wells: permits
SUMMARY: Requires greater interagency coordination and public notice regarding applications to drill water wells and prohibits a local agency from approving new “large-diameter, high-capacity” wells within one-quarter mile of domestic wells and areas of significant land subsidence. Specifically, this bill:
- Provides that this bill shall only apply to the 515 groundwater basins identified by the Department of Water Resources (DWR) in Bulletin 118.
- Defines “large-diameter, high-capacity well” as any water well with a diameter greater than eight inches and that pumps more than two acre-feet (AF) of water annually.
- Defines “local enforcement agency” (LEA) as any city, county, or water agency that has adopted and is administering an ordinance for the construction, maintenance, abandonment, or destruction of a water well.
- Requires an LEA to do the following at least 30 days prior to approving a permit for a large-diameter, high capacity water well:
- Notify the public by posting the application on the LEA’s website;
- Notify all groundwater sustainability agencies (GSA) within a 10-mile radius of the proposed well;
- Notify all other LEA’s in the groundwater basin, if any;
- Notify via U.S. Postal Service all registered owners or agents of parcels within a one-mile radius of the proposed well. The notice shall include information about the well permitting process; and
- Notify the State Water Resources Control Board (State Water Board) if the proposed well is to be located in a probationary basin.
- Requires, upon notice, a GSA with oversight of the area where a proposed large-diameter, high-capacity well is to be located to provide the following information to the LEA:
- The name of the applicable groundwater sustainability plan (GSP) and where an electronic copy of the GSP may be accessed;
- The name of the applicable GSA, the GSA manager and contact information, and applicable sustainable groundwater sustainable management criteria;
- The estimated depth to the groundwater level based on most recent monitoring for the area where the large-diameter, high-capacity well is to be located;
- Any fees, allocation, metering, spacing determinations, or other regulations or ordinances that the GSA has adopted;
- Any updates to the information provided [i.e., information described in (a) through (d) and (f)] should changes occur; and
- Notice of an inadequate determination, if applicable, and the status of any action by the State Water Board pertaining to the inadequate determination.
- Requires the LEA to provide the following information to an applicant before approving a permit for a large-diameter, high-capacity well:
- The basin’s name, number, and priority as designated by DWR;
- The name of all GSAs managing the basin, if any, where the well will be located;
- Any regulations or ordinances adopted by the GSA relative to the construction and operation of the well;
- Notice that the well is subject to the regulatory authority of a GSA or State Water Board, if applicable. Specifically that such authority may include limiting groundwater pumping, imposing fees, and requiring metering.
- Prohibits an LEA from approving a large diameter, high-capacity well within one-quarter of a mile of a domestic well.
- Prohibits an LEA from approving a large diameter, high-capacity well within one-quarter of a mile of an area that DWR has reported as having subsided more than 0.5 feet since January 1, 2015 based on data provided in the InSAR subsidence data report. Provides, however, that an LEA may approve a well in such an area if the area has not had more than 0.1 feet of subsidence over the preceding four years and if the well is consistent with an applicable GSP and is screened above geologic units know to be susceptible to compaction.
- Prohibits, in basins subject to the Sustainable Groundwater Management Act (SGMA), an LEA from approving a permit for any well unless it is screened below the minimum thresholds established in the GSP applicable to the area of the basin where the well is to be located.
- Provides that an LEA may deny an application to approve a well based on criteria that is more stringent than that outlined in this bill.
- Provides that this bill does not apply to applications or permits for any of the following:
- Wells that pump less than two AF annually;
- Wells that will be located on a parcel five acres or less that is zoned rural-residential;
- Drinking water wells of a public water system, state small water system, or a community water system;
- Large-diameter, high-capacity wells for the replacement of an existing large-diameter, high capacity well so long as it will not pump more water annually than the well being replaced, is substantially in the same location as the well being replaced and meets other specified conditions.
- Provides that no reimbursement by the state is required by this bill because local agencies have the authority to levy service charges, fees, or assessments sufficient to cover the implementation costs.
EXISTING LAW:
- Requires, under SGMA, local agencies to sustainably manage groundwater in high- or medium-priority basins by 2040. Defines sustainable management of groundwater as the avoidance of the following six “undesirable results:” (a) chronic lowering of groundwater levels; (b) reduction of groundwater storage; (c) seawater intrusion; (d) degraded water quality; (e) land subsidence; and (f) depletions of interconnected surface water (Water Code § 10720 et seq.).
- Requires DWR to designate groundwater basins as high-, medium-, low-, or very low-priority and requires that the designation be based on specified criteria, including population of the overlying basin, number of wells in the basin, and irrigated acreage in the basin (Water Code § 10722.4).
- Permits a GSA to require registration of any groundwater extraction facility (e.g., groundwater well) within its management area (Water Code § 10725.6).
- Prohibits a GSA from issuing a permit for the construction, modification, or abandonment of a groundwater well unless authorized by a county to do so. Permits a GSA to request that a county forward permit applications for construction, modification, or reactivation of groundwater wells to the GSA before approval and requires counties to consider such a request from a GSA [Water Code § 10726.4 (b)].
- Defines “well” or “water well” as any artificial excavation for the purpose of extracting water from, or injecting water into, the underground. Excludes oil and gas wells, geothermal wells, and wells used to dewater during destruction or stabilize hillsides or earth embankments from the definition of “well” and “water well” (Water Code § 13710).
- Requires every person who drills, expands, or destroys a water well, cathodic protection well, groundwater monitoring well, or geothermal heat exchange well to file a well completion report with DWR containing specified information within 60 days of completing the construction, alteration, abandonment, or destruction of the well (Water Code § 13751).
- Defines “domestic well” as a groundwater well used to supply water for the domestic needs of an individual residence or water system that is not a public water system and has no more than four connections [Health and Safety Code § 116681(i)].
FISCAL EFFECT: Unknown. This bill is keyed fiscal.
COMMENTS:
- Purpose of this bill. This bill requires disclosure of information regarding permit applications for large-diameter, high-capacity wells and prohibits such wells where excessive land subsidence is occurring and near existing domestic wells. According to the author, “SGMA was passed to establish a statewide framework to help protect groundwater basins from over-pumping and have them reach long-term sustainable pumping levels. In March of 2022, the Governor signed Executive Order (EO) N-7-22 to establish new well permitting requirements in order to ensure new wells were evaluated for their impact on neighboring wells and land subsidence. Thousands of wells were permitted, with only a cursory ministerial approval process between the 2014 passage of SGMA and the governor's 2022 [EO]. Thousands of drinking water wells that often times served disadvantage communities went dry during that same period. [DWR] performed an extensive review followed by a thorough report on the implementation and effectiveness of the Governor's [EO]. [This bill] now implements the recommendations from DWR to ensure that new wells are evaluated for their impact on neighboring wells and land subsidence.”
- Background. According to DWR, groundwater provides approximately 40% of California’s water supply in a “normal” year and as much as 60% in dry years. DWR estimates there are two million groundwater wells in California at present and indicates that between 7,000 and 15,000 new wells are constructed each year. Permitting for construction, alteration, or destruction of groundwater wells is handled by local agencies; typically this is a county department of environmental health, but cities and water agencies also exercise this authority in some cases. LEAs at a minimum, ensure compliance with well standards set by DWR (in Bulletin 74) before issuing a permit. Some LEAs adopt standards for wells that surpass DWR guidelines.
Oftentimes, a permit for a groundwater well is deemed a “ministerial” action by an LEA. Ministerial actions do not require the exercise of any discretion by the LEA: “‘ministerial’ describes a governmental decision involving little or no personal judgement by the public official as to the wisdom or manner of carrying out the project. The public official merely applies the law to the facts as presented but uses no special discretion or judgement in reaching a decision” (14 California Code of Regulations § 15369).
Governor’s drought EOs. The Governor issued EO N-7022 on March 28, 2022, to extend the then existing drought emergency and require various administrative responses to the previous drought. Among these actions, paragraph nine of EO N-7-22 prohibited a local or public agency from issuing a permit for a new groundwater well or the alteration of an existing well in a groundwater basin subject to SGMA “without first obtaining written verification from a [GSA] managing the basin or area of the basin where the well is proposed to be located that groundwater extraction by the proposed well would not be inconsistent with any sustainable groundwater management program established in any applicable [GSP] adopted by that [GSA] and would not decrease the likelihood of achieving a sustainability goal for the basin covered by such a plan.” Furthermore, the EO required that an LEA determine that a proposed new well or modification of an existing well would not likely interfere with nearby wells and would not cause subsidence that would harm infrastructure before issuing a permit. EO N-3-23 issued on February 13, 2023 again extended the then existing drought emergency and the provisions related to groundwater well permitting with minor changes to address any wells that must be moved related to the construction of high-speed rail.
Groundwater Well Permitting: Observations and Analysis of Executive Orders N-7-22 and N-3-23 (EO report). Completed in March 2024, this report notes that local agencies adopted various approaches to complying with the well permitting requirements of the EOs. These approaches included individual consultation on a permit-by-permit basis, reliance on existing requirements deemed sufficient, reliance on information submitted by applicants, passage of a broad resolution claiming any new well was consistent with relevant GSPs, and reliance on a report by a licensed professional. In some cases, GSAs and LEAs were simply unwilling to perform the verification process mandated in the EOs. There was little that DWR could do for those opting to not comply; as the EO report notes, “there is also no mechanism in the EOs to ensure compliance.” The EO report notes that at least 1,911 wells were reported as going dry via the voluntary Dry Well Reporting System from March 2022 through August 28, 2023 and that there were several areas of land subsidence of up to one foot in parts of the Sacramento Valley and San Joaquin Valley. The EO report includes DWR recommendations for statutory concepts to replace the EOs: 1) require disclosures; 2) set minimum standards; 3) exempt certain discrete types of wells and procedures; and 4) establish applicability of requirements (i.e., specify to groundwater basins are subject to requirements). This bill is based on the recommendations contained in the EO report.
Interferometric Synthetic Aperture Radar (InSAR) subsidence data report. This dataset is derived from satellite imagery collected by the European Space Agency ESA Sentinel-1A satellite and processed by TRE ALTAMIRA, Inc. under contract with DWR. DWR makes this subsidence data available to GSAs as part of its SGMA technical assistance program for GSP development and implementation. Data collection began in late 2014. The dataset includes point data that represent average vertical displacement values for 100 meter by 100 meter areas. The data was updated in 2018, 2019, and 2020 and has been updated quarterly since October 2021 (with the latest update in January 2024). This bill prohibits permitting a new large-diameter, high-capacity well within one-quarter mile of an area identified as having greater than 0.5 feet of land subsidence since January 1, 2015 based on InSAR data and interpretation. - Arguments in support. CleanEarth4Kids.org supports this bill asserting that many California communities face serious shortages of drinking water due in part to unregulated overpumping of groundwater. CleanEarth4Kids.org observes that groundwater levels plummeted during droughts experienced over the past decade and a half and that “high-capacity wells were drilled with no oversight or thought to the impacts to our drinking water.” CleanEarth4Kids.org argues this bill is necessary to protect our children’s health and future.
- Arguments in opposition. The Valley Ag Water Coalition (VAWC) opposes this bill “because it represents an unnecessary intrusion into local control, interferes with the regulatory authority granted to [GSAs] under [SGMA], and adds burdensome requirements on GSAs at a time when they are focused on implementation of [GSPs]—the majority of which have been approved by [DWR].” VAWC further asserts the approach contained in this bill is contrary to the principle of SGMA that groundwater should be managed locally and tailored to unique local conditions which DWR has embraced when evaluating GSPs. Finally, VAWC contends that this bill “threatens state and local investments in groundwater banks and indirect potable reuse projects by prohibiting or interfering with the withdrawal of water placed into aquifers throughout the state.”
- Oppose unless amended. The California Chamber of Commerce (CalChamber) and a number of agricultural trade associations have taken an “oppose unless amended” position on this bill arguing “that a stringent limitation on essentially any new non-drinking water well is [not] the appropriate way to address a decades-long and complex issue” and that “when SGMA was developed, the focus on achieving groundwater sustainability was rightfully on the relative use of groundwater: on how much water is used. It did not focus on how many wells are or may be in existence.” CalChamber et al. maintain this bill should focus on communication between GSAs, LEAs, and well permit applicants. In addition, CalChamber et al. seek several amendments to: 1) limit notifications of permit applications to only properties with wells; and 2) exempt adjudicated basins and basins with a statutorily designated groundwater agency [Water Code § 10723(c)] from this bill.
- Proposed committee amendments. The Committee may wish to request that the author to somewhat narrow the application of this bill so that water wells for recharge, water quality, and municipal purposes are excluded and to make clarifying and technical amendments:
Amendment 1 – exclude drinking water wells, wells that are part of a conjunctive use or water banking program, and wells used for groundwater remediation from this bill and make technical and clarifying changes:
13807.4. This article does not apply to applications or permits for any of the following water wells:
(a) Wells that will draw less than two acre-feet per year.
(b) Wells that will be located on a parcel of five acres or fewer that is in an area that has been zoned by the local land use authority for rural residential use.
(c) Drinking water wells of an urban retail water supplier a public water system, state small water system, or a community water system.
(d) Large-diameter, high-capacity wells for the replacement or reconstruction of an existing large-diameter, high-capacity well that meets all of the following conditions:
(1) The replacing or reconstructed well shall not have a larger diameter or be used to pump more water annually than the previous well.
(2) The well being replaced shall be abandoned prior to initial operation of the replacement replacing well.
(3) The replacing replacement well is in substantially the same location as the well it is replacing or is to be moved to a location that would lessen impacts to domestic wells and wells that provide water for state small water systems or community water systems.
(e) Wells associated with or part of a conjunctive use or water banking program or project that has approved environmental document consistent with Public Resources Code section 21000 et seq.
(f) Wells that are part of a groundwater remediation or protection project that aims to address groundwater contamination, water quality, or sea water intrusion.
Amendment 2 – Add definition of urban retail water supplier:
13807.1. The following definitions shall apply to this article:
(a) “Community water system” has the same meaning as provided in Section 116275 of the Health and Safety Code.
(b) “Domestic well” has the same meaning as provided in Section 116681 of the Health and Safety Code.
(c) “Large-diameter, high-capacity well” means any water well with a diameter of more than eight inches and intended to produce greater than two acre-feet annually.
(d) “Local enforcement agency” means any city, county, or water agency that has adopted and is administering an ordinance for the construction, maintenance, abandonment, or destruction of a water well pursuant to this chapter.
(e) “Public water system” has the same meaning as defined in Section 116275 of the Health and Safety Code.
(f) “State small water system” has the same meaning as provided in Section 116275 of the Health and Safety Code.
(g) “Urban retail water supplier” has the same meaning as provided in Section 10608.12 of the Water Code.
Amendment 3 – make technical and clarifying changes:
13807.2. … (b) If the proposed large-diameter, high-capacity well is to be located in an area subject to management by a groundwater sustainability agency, the applicable Upon notice, a groundwater sustainability agency with oversight for the area of the basin where the proposed large-diameter, high-capacity well is to be located shall, upon notice of a permit application, provide all of the following information to the local enforcement agency:
(1) The name of the applicable groundwater sustainability plan being implemented and where an electronic copy of the plan may be accessed.
(2) The name of the applicable groundwater sustainability agency, the agency manager and contact information, and the applicable sustainable management criteria related to groundwater levels, including the groundwater level measurable objectives and minimum thresholds.
(3) The estimated depth to the groundwater level based on the most recent monitoring conducted by the groundwater sustainability agency for the area of the basin where the proposed activities covered by the application would occur.
(4) Any fees, allocation, metering, spacing determinations, or other regulations or ordinances that the groundwater sustainability agency has adopted.
(5) Any updates to the information provided pursuant to this subdivision as necessary within 30 days, should changes occur.
(6) Notice of an inadequate determination, if applicable, by the department of the groundwater sustainability plan and the status of any action of the state board resulting from the department determination.
(c) Before approving any well permit for a large-diameter, high-capacity well, a local enforcement agency shall provide all of the following information to the applicant:
(1) The basin name, number, and priority as assigned by the department in its most recent Bulletin 118.
(2) The name of all groundwater sustainability agencies, if any, managing the basin in which the activities covered in the application would occur.
(3) Information on regulations or ordinances adopted by the groundwater sustainability agency relevant to the construction and operation of the proposed well, if applicable.
(4) If applicable, notice Notice to the applicant that the approval of the application and granting of any associated permit is subject to the regulatory authority of any groundwater sustainability agency managing the portion of the basin in which the activities covered in the application would occur. The notice shall specifically inform the applicant that in addition to any regulatory authority already being exercised, a groundwater sustainability agency or the state board for a probationary groundwater basin may exercise authority to limit groundwater extraction, the imposition of fees, and metering.
- Related legislation. AB 1563 (Bennett) of 2023 would have prohibited a county, city, or any other well permitting agency from approving a permit for a new groundwater well or for alteration of an existing well in a critically overdrafted basin subject to SGMA unless certain conditions are met. AB 1563 died in the Senate Natural Resources and Water Committee.
AB 429 (Bennett) of 2023 was substantially similar to AB 1563. AB 429 was referred to this Committee but never heard.
AB 2201 (Bennett) of 2022 would have required local agencies that permit groundwater wells to obtain written verification stating that a proposed well will not undermine sustainable groundwater management or cause well interference prior to approving a permit application for a groundwater well, unless the well was exempted. AB 2201 returned to the Assembly for a concurrence vote, but was never taken up.
SB 1317 (Wolk) of 2016 would have required a city or county overlying a high- or medium-priority basin to prohibit the issuance of a permit for a new groundwater extraction facility or require a permit applicant to demonstrate that extraction of groundwater from the proposed facility would not contribute to, or create, an undesirable result. SB 1317 was referred to this committee but never heard.
REGISTERED SUPPORT / OPPOSITION:
Support
California Coastkeeper Alliance
California Rural Legal Assistance Foundation
Civicwell
Clean Water Action
Cleanearth4kids.org
Community Water Center
Environmental Law Foundation
Leadership Counsel for Justice & Accountability
Natural Resources Defense Council
Restore Hetch Hetchy
Sierra Club California
We Advocate Through Environmental Review
Opposition
South San Joaquin Irrigation District
Valley Ag Water Coalition
Oppose Unless Amended
Agricultural Council of California
Association of California Water Agencies
California Apple Commission
California Association of Wheat Growers
California Association of Winegrape Growers
California Bean Shippers Association
California Blueberry Association
California Blueberry Commission
California Cattlemen's Association
California Chamber of Commerce
California Citrus Mutual
California Cotton Ginners and Growers Association
California Farm Bureau Federation
California Fresh Fruit Association
California Groundwater Association
California League of Food Producers
California Municipal Utilities Association
California Pear Grower Association
California Seed Association
California State Association of Counties
California Walnut Commission
Cucamonga Valley Water District
Desert Water Agency
Eastern Municipal Water District
Grower-Shipper Association of Central California
Inland Empire Utilities Agency
Jurupa Community Services District
Kern County Water Agency
Kings River Conservation District
Modesto Irrigation District
Northern California Water Association
Olive Growers Council of California
Rancho Water
Regional Water Authority
Solano County Water Agency
Southern California Water Coalition
United Ag
United Water Conservation District
Water Replenishment District of Southern California
Western Agricultural Processors Association
Western Growers Association
Western Municipal Water District
Wine Institute
Analysis Prepared by: Pablo Garza / W., P., & W. / (916) 319-2096
Discussed in Hearing
Senate Standing Committee on Natural Resources and Water
Assembly Floor
Assembly Standing Committee on Appropriations
Assembly Standing Committee on Water, Parks, and Wildlife
Bill Author
Bill Co-Author(s):