Existing law, the Planning and Zoning law, generally requires that an action or proceeding challenging a public agencys decision on a variance, conditional use permit, or any other permit, among other decisions, be commenced, and service made on the legislative body of the agency, within 90 days after the legislative bodys decision.
This bill, for purposes of determining the period of time before a variance, conditional use permit, or any other development permit or project approval issued by a city, county, or state agency expires, would exclude the period of time during which an action or proceeding involving the approval or conditional approval of the permit or project approval is or was pending, except as specified. By extending the expiration date of local development permits and project approvals, this bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law, the Planning and Zoning law, generally requires that an action or proceeding challenging a public agencys decision on a variance, conditional use permit, or any other permit, among other decisions, be commenced, and service made on the legislative body of the agency, within 90 days after the legislative bodys decision.
This bill, for purposes of determining the period of time before a variance, conditional use permit, or any other development permit or project approval issued by a city, county, or state agency expires, would exclude the period of time during which an action or proceeding involving the approval or conditional approval of the permit or project approval is or was pending, except as specified. By extending the expiration date of local development permits and project approvals, this bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law, the Planning and Zoning law, generally requires that an action or proceeding challenging specified decisions of a public agency agencys decision on a variance, conditional use permit, or any other permit, among other decisions, be commenced, and service made on the legislative body of the agency, within 90 days after the legislative bodys decision.
This bill, for purposes of determining the period of time before a variance, conditional use permit, or any other development permit or project approval issued by a city, county, or state agency expires, would exclude the period of time during which an action or proceeding involving the approval or conditional approval of the permit or project approval is or was pending. pending, except as specified. By extending the expiration date of local development permits and project approvals, this bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law, the Planning and Zoning law, generally requires that an action or proceeding challenging specified decisions of a public agency be commenced, and service made on the legislative body of the agency, within 90 days after the legislative bodys decision.
This bill, for purposes of determining the period of time before a variance, conditional use permit, or any other development permit or project approval issued by a city, county, or state agency expires, would exclude the period of time during which an action or proceeding involving the approval or conditional approval of the permit or project approval is or was pending. By extending the expiration date of local development permits and project approvals, this bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
(a)(1)The Legislature finds and declares that there currently is a housing crisis in California and it is essential to reduce delays and restraints upon expeditiously completing housing projects.
(2)The Legislature further finds and declares that a legal action or proceeding challenging a decision of a city, county, or city and county has a chilling effect on the confidence with which property owners and local governments can proceed with projects. Legal actions or proceedings filed to attack, review, set aside, void, or annul a decision of a city, county, or city and county pursuant to this division, including, but not limited to, the implementation of general plan goals and policies that provide incentives for affordable housing, open-space and recreational opportunities, and other related public benefits, can prevent the completion of needed developments even though the projects have received required governmental approvals.
(3)The purpose of this section is to provide certainty for property owners and local governments regarding decisions made pursuant to this division.
(b)(1)In an action or proceeding to attack, review, set aside, void, or annul a finding, determination, or decision of a public agency made pursuant to this title at a properly noticed public hearing, the issues raised shall be limited to those raised in the public hearing or in written correspondence delivered to the public agency prior to, or at, the public hearing, except where the court finds either of the following:
(A)The issue could not have been raised at the public hearing by persons exercising reasonable diligence.
(B)The body conducting the public hearing prevented the issue from being raised at the public hearing.
(2)If a public agency desires the provisions of this subdivision to apply to a matter, it shall include in any public notice issued pursuant to this title a notice substantially stating all of the following: If you challenge the (nature of the proposed action) in court, you may be limited to raising only those issues you or someone else raised at the public hearing described in this notice, or in written correspondence delivered to the (public entity conducting the hearing) at, or prior to, the public hearing.
(3)The application of this subdivision to causes of action brought pursuant to subdivision (d) applies only to the final action taken in response to the notice to the city or clerk of the board of supervisors. If no final action is taken, then the issue raised in the cause of action brought pursuant to subdivision (d) shall be limited to those matters presented at a properly noticed public hearing or to those matters specified in the notice given to the city or clerk of the board of supervisors pursuant to subdivision (d), or both.
(c)(1)Except as provided in subdivision (d), no action or proceeding shall be maintained in any of the following cases by any person unless the action or proceeding is commenced and service is made on the legislative body within 90 days after the legislative bodys decision:
(A)To attack, review, set aside, void, or annul the decision of a legislative body to adopt or amend a general or specific plan. This paragraph does not apply where an action is brought based upon the complete absence of a general plan or a mandatory element thereof, but does apply to an action attacking a general plan or mandatory element thereof on the basis that it is inadequate.
(B)To attack, review, set aside, void, or annul the decision of a legislative body to adopt or amend a zoning ordinance.
(C)To determine the reasonableness, legality, or validity of any decision to adopt or amend any regulation attached to a specific plan.
(D)To attack, review, set aside, void, or annul the decision of a legislative body to adopt, amend, or modify a development agreement. An action or proceeding to attack, review, set aside, void, or annul the decisions of a legislative body to adopt, amend, or modify a development agreement shall only extend to the specific portion of the development agreement that is the subject of the adoption, amendment, or modification. This paragraph applies to development agreements, amendments, and modifications adopted on or after January 1, 1996.
(E)To attack, review, set aside, void, or annul any decision on the matters listed in Sections 65901 and 65903, or to determine the reasonableness, legality, or validity of any condition attached to a variance, conditional use permit, or any other permit.
(F)Concerning any of the proceedings, acts, or determinations taken, done, or made prior to any of the decisions listed in subparagraphs (A), (B), (C), (D), and (E).
(2)In the case of an action or proceeding challenging the adoption or revision of a housing element pursuant to this subdivision, the action or proceeding may, in addition, be maintained if it is commenced and service is made on the legislative body within 60 days following the date that the Department of Housing and Community Development reports its findings pursuant to subdivision (h) of Section 65585.
(d)(1)An action or proceeding shall be commenced and the legislative body served after the accrual of the cause of action as provided in this subdivision, if the action or proceeding meets both of the following requirements:
(A)It is brought in support of or to encourage or facilitate the development of housing that would increase the communitys supply of housing affordable to persons and families with low or moderate incomes, as defined in Section 50079.5 of the Health and Safety Code, or with very low incomes, as defined in Section 50105 of the Health and Safety Code, or middle-income households, as defined in Section 65008 of this code. This subdivision is not intended to require that the action or proceeding be brought in support of or to encourage or facilitate a specific housing development project.
(B)It is brought with respect to the adoption or revision of a housing element pursuant to Article 10.6 (commencing with Section 65580) of Chapter 3, actions taken pursuant to Section 65863.6, or Chapter 4.2 (commencing with Section 65913), or to challenge the adequacy of an ordinance adopted pursuant to Section 65915.
(2)(A)An action or proceeding challenging the adoption or revision of a housing element that the Department of Housing and Community Development has found to substantially comply with the requirements of Article 10.6 (commencing with Section 65580) of Chapter 3 shall be commenced, and the legislative body shall be served, within six months after the accrual of the cause of action as provided in this subdivision.
(B)An action or proceeding challenging the adoption or revision of a housing element that the Department of Housing and Community Development has found does not substantially comply with the requirements of Article 10.6 (commencing with Section 65580) of Chapter 3, where the legislative body has failed to change the draft element or amendment to substantially comply with the requirements of Article 10.6 or has adopted the draft element or amendment without change and made findings pursuant to subdivision (f) of Section 65585, shall be commenced, and the legislative body shall be served, within one year after the accrual of the cause of action as provided in this subdivision.
(C)An action or proceeding challenging an action taken pursuant to Section 65863.6, or Chapter 4.2 (commencing with Section 65913), or to challenge the adequacy of an ordinance adopted pursuant to Section 65915 shall be served within 180 days after the accrual of the cause of action as provided in this subdivision.
(3)(A)A cause of action brought pursuant to this subdivision shall not be maintained until 60 days have expired following notice to the city or clerk of the board of supervisors by the party bringing the cause of action, or the partys representative, specifying the deficiencies of the general plan, specific plan, zoning ordinance, or other action described in subparagraph (B) of paragraph (1). A cause of action brought pursuant to this subdivision shall accrue 60 days after notice is filed or the legislative body takes a final action in response to the notice, whichever occurs first.
(B)This notice may be filed at any time within 270 days after an action described in subparagraph (A) of paragraph (2), two years after an action described in subparagraph (B) of paragraph (2), or 180 days after an action described in subparagraph (C) of paragraph (2).
(4)A notice or cause of action brought by one party pursuant to this subdivision shall not bar filing of a notice and initiation of a cause of action by any other party.
(5)After the adoption of a housing element covering the current planning period, no action shall be filed pursuant to this subdivision to challenge a housing element covering a prior planning period.
(e)Upon the expiration of the time limits provided for in this section, all persons are barred from any further action or proceeding.
(f)(1)The period of time before a permit or project approval issued by a city, county, or state agency expires shall not include the period of time during which an action or proceeding involving the approval or conditional approval of the permit or project approval is or was pending.
(2)For purposes of this subdivision:
(A)Pending means the same as described in Section 1049 of the Code of Civil Procedure.
(B)Permit means a variance, conditional use permit, or any other development permit, but does not include any of the following:
(i)A building permit or other permit issued under the California Building Standards Code (Title 24 of the California Code of Regulations) or any applicable local building code for the construction, demolition, or alteration of buildings, whether discretionary or nondiscretionary.
(ii)A permit for minor or standard excavation and grading.
(iii)A permit for demolition.
(iv)A permit for minor or standard excavation and grading.
(v)Any nondiscretionary permit or review that is required or issued by the local agency after the entitlement process has been completed to begin construction.
(g)Notwithstanding Sections 65700 and 65803, or any other provision of law, this section shall apply to charter cities.
(h)Except as provided in subdivision (d), this section shall not affect any law prescribing or authorizing a shorter period of limitation than that specified herein.
(i)Except as provided in subparagraph (D) of paragraph (1) of subdivision (c), this section shall be applicable to those decisions of the legislative body of a city, county, or city and county made pursuant to this division on or after January 1, 1984.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
(a)(1)The Legislature finds and declares that there currently is a housing crisis in California and it is essential to reduce delays and restraints upon expeditiously completing housing projects.
(2)The Legislature further finds and declares that a legal action or proceeding challenging a decision of a city, county, or city and county has a chilling effect on the confidence with which property owners and local governments can proceed with projects. Legal actions or proceedings filed to attack, review, set aside, void, or annul a decision of a city, county, or city and county pursuant to this division, including, but not limited to, the implementation of general plan goals and policies that provide incentives for affordable housing, open-space and recreational opportunities, and other related public benefits, can prevent the completion of needed developments even though the projects have received required governmental approvals.
(3)The purpose of this section is to provide certainty for property owners and local governments regarding decisions made pursuant to this division.
(b)(1)In an action or proceeding to attack, review, set aside, void, or annul a finding, determination, or decision of a public agency made pursuant to this title at a properly noticed public hearing, the issues raised shall be limited to those raised in the public hearing or in written correspondence delivered to the public agency prior to, or at, the public hearing, except where the court finds either of the following:
(A)The issue could not have been raised at the public hearing by persons exercising reasonable diligence.
(B)The body conducting the public hearing prevented the issue from being raised at the public hearing.
(2)If a public agency desires the provisions of this subdivision to apply to a matter, it shall include in any public notice issued pursuant to this title a notice substantially stating all of the following: If you challenge the (nature of the proposed action) in court, you may be limited to raising only those issues you or someone else raised at the public hearing described in this notice, or in written correspondence delivered to the (public entity conducting the hearing) at, or prior to, the public hearing.
(3)The application of this subdivision to causes of action brought pursuant to subdivision (d) applies only to the final action taken in response to the notice to the city or clerk of the board of supervisors. If no final action is taken, then the issue raised in the cause of action brought pursuant to subdivision (d) shall be limited to those matters presented at a properly noticed public hearing or to those matters specified in the notice given to the city or clerk of the board of supervisors pursuant to subdivision (d), or both.
(c)(1)Except as provided in subdivision (d), no action or proceeding shall be maintained in any of the following cases by any person unless the action or proceeding is commenced and service is made on the legislative body within 90 days after the legislative bodys decision:
(A)To attack, review, set aside, void, or annul the decision of a legislative body to adopt or amend a general or specific plan. This paragraph does not apply where an action is brought based upon the complete absence of a general plan or a mandatory element thereof, but does apply to an action attacking a general plan or mandatory element thereof on the basis that it is inadequate.
(B)To attack, review, set aside, void, or annul the decision of a legislative body to adopt or amend a zoning ordinance.
(C)To determine the reasonableness, legality, or validity of any decision to adopt or amend any regulation attached to a specific plan.
(D)To attack, review, set aside, void, or annul the decision of a legislative body to adopt, amend, or modify a development agreement. An action or proceeding to attack, review, set aside, void, or annul the decisions of a legislative body to adopt, amend, or modify a development agreement shall only extend to the specific portion of the development agreement that is the subject of the adoption, amendment, or modification. This paragraph applies to development agreements, amendments, and modifications adopted on or after January 1, 1996.
(E)To attack, review, set aside, void, or annul any decision on the matters listed in Sections 65901 and 65903, or to determine the reasonableness, legality, or validity of any condition attached to a variance, conditional use permit, or any other permit.
(F)Concerning any of the proceedings, acts, or determinations taken, done, or made prior to any of the decisions listed in subparagraphs (A), (B), (C), (D), and (E).
(2)In the case of an action or proceeding challenging the adoption or revision of a housing element pursuant to this subdivision, the action or proceeding may, in addition, be maintained if it is commenced and service is made on the legislative body within 60 days following the date that the Department of Housing and Community Development reports its findings pursuant to subdivision (h) of Section 65585.
(d)(1)An action or proceeding shall be commenced and the legislative body served after the accrual of the cause of action as provided in this subdivision, if the action or proceeding meets both of the following requirements:
(A)It is brought in support of or to encourage or facilitate the development of housing that would increase the communitys supply of housing affordable to persons and families with low or moderate incomes, as defined in Section 50079.5 of the Health and Safety Code, or with very low incomes, as defined in Section 50105 of the Health and Safety Code, or middle-income households, as defined in Section 65008 of this code. This subdivision is not intended to require that the action or proceeding be brought in support of or to encourage or facilitate a specific housing development project.
(B)It is brought with respect to the adoption or revision of a housing element pursuant to Article 10.6 (commencing with Section 65580) of Chapter 3, actions taken pursuant to Section 65863.6, or Chapter 4.2 (commencing with Section 65913), or to challenge the adequacy of an ordinance adopted pursuant to Section 65915.
(2)(A)An action or proceeding challenging the adoption or revision of a housing element that the Department of Housing and Community Development has found to substantially comply with the requirements of Article 10.6 (commencing with Section 65580) of Chapter 3 shall be commenced, and the legislative body shall be served, within six months after the accrual of the cause of action as provided in this subdivision.
(B)An action or proceeding challenging the adoption or revision of a housing element that the Department of Housing and Community Development has found does not substantially comply with the requirements of Article 10.6 (commencing with Section 65580) of Chapter 3, where the legislative body has failed to change the draft element or amendment to substantially comply with the requirements of Article 10.6 or has adopted the draft element or amendment without change and made findings pursuant to subdivision (f) of Section 65585, shall be commenced, and the legislative body shall be served, within one year after the accrual of the cause of action as provided in this subdivision.
(C)An action or proceeding challenging an action taken pursuant to Section 65863.6, or Chapter 4.2 (commencing with Section 65913), or to challenge the adequacy of an ordinance adopted pursuant to Section 65915 shall be served within 180 days after the accrual of the cause of action as provided in this subdivision.
(3)(A)A cause of action brought pursuant to this subdivision shall not be maintained until 60 days have expired following notice to the city or clerk of the board of supervisors by the party bringing the cause of action, or the partys representative, specifying the deficiencies of the general plan, specific plan, zoning ordinance, or other action described in subparagraph (B) of paragraph (1). A cause of action brought pursuant to this subdivision shall accrue 60 days after notice is filed or the legislative body takes a final action in response to the notice, whichever occurs first.
(B)This notice may be filed at any time within 270 days after an action described in subparagraph (A) of paragraph (2), two years after an action described in subparagraph (B) of paragraph (2), or 180 days after an action described in subparagraph (C) of paragraph (2).
(4)A notice or cause of action brought by one party pursuant to this subdivision shall not bar filing of a notice and initiation of a cause of action by any other party.
(5)After the adoption of a housing element covering the current planning period, no action shall be filed pursuant to this subdivision to challenge a housing element covering a prior planning period.
(e)Upon the expiration of the time limits provided for in this section, all persons are barred from any further action or proceeding.
(f)(1)The period of time before a permit or project approval issued by a city, county, or state agency expires shall not include the period of time during which an action or proceeding involving the approval or conditional approval of the permit or project approval is or was pending.
(2)For purposes of this subdivision:
(A)Pending means the same as described in Section 1049 of the Code of Civil Procedure.
(B)Permit means a variance, conditional use permit, or any other development permit, but does not include any of the following:
(i)A building permit or other permit issued under the California Building Standards Code (Title 24 of the California Code of Regulations) or any applicable local building code for the construction, demolition, or alteration of buildings, whether discretionary or nondiscretionary.
(ii)A permit for minor or standard excavation and grading.
(iii)A permit for demolition.
(iv)A permit for minor or standard excavation and grading.
(v)Any nondiscretionary permit or review that is required or issued by the local agency after the entitlement process has been completed to begin construction.
(g)Notwithstanding Sections 65700 and 65803, or any other provision of law, this section shall apply to charter cities.
(h)Except as provided in subdivision (d), this section shall not affect any law prescribing or authorizing a shorter period of limitation than that specified herein.
(i)Except as provided in subparagraph (D) of paragraph (1) of subdivision (c), this section shall be applicable to those decisions of the legislative body of a city, county, or city and county made pursuant to this division on or after January 1, 1984.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
(a)(1)The Legislature finds and declares that there currently is a housing crisis in California and it is essential to reduce delays and restraints upon expeditiously completing housing projects.
(2)The Legislature further finds and declares that a legal action or proceeding challenging a decision of a city, county, or city and county has a chilling effect on the confidence with which property owners and local governments can proceed with projects. Legal actions or proceedings filed to attack, review, set aside, void, or annul a decision of a city, county, or city and county pursuant to this division, including, but not limited to, the implementation of general plan goals and policies that provide incentives for affordable housing, open-space and recreational opportunities, and other related public benefits, can prevent the completion of needed developments even though the projects have received required governmental approvals.
(3)The purpose of this section is to provide certainty for property owners and local governments regarding decisions made pursuant to this division.
(b)(1)In an action or proceeding to attack, review, set aside, void, or annul a finding, determination, or decision of a public agency made pursuant to this title at a properly noticed public hearing, the issues raised shall be limited to those raised in the public hearing or in written correspondence delivered to the public agency prior to, or at, the public hearing, except where the court finds either of the following:
(A)The issue could not have been raised at the public hearing by persons exercising reasonable diligence.
(B)The body conducting the public hearing prevented the issue from being raised at the public hearing.
(2)If a public agency desires the provisions of this subdivision to apply to a matter, it shall include in any public notice issued pursuant to this title a notice substantially stating all of the following: If you challenge the (nature of the proposed action) in court, you may be limited to raising only those issues you or someone else raised at the public hearing described in this notice, or in written correspondence delivered to the (public entity conducting the hearing) at, or prior to, the public hearing.
(3)The application of this subdivision to causes of action brought pursuant to subdivision (d) applies only to the final action taken in response to the notice to the city or clerk of the board of supervisors. If no final action is taken, then the issue raised in the cause of action brought pursuant to subdivision (d) shall be limited to those matters presented at a properly noticed public hearing or to those matters specified in the notice given to the city or clerk of the board of supervisors pursuant to subdivision (d), or both.
(c)(1)Except as provided in subdivision (d), no action or proceeding shall be maintained in any of the following cases by any person unless the action or proceeding is commenced and service is made on the legislative body within 90 days after the legislative bodys decision:
(A)To attack, review, set aside, void, or annul the decision of a legislative body to adopt or amend a general or specific plan. This paragraph does not apply where an action is brought based upon the complete absence of a general plan or a mandatory element thereof, but does apply to an action attacking a general plan or mandatory element thereof on the basis that it is inadequate.
(B)To attack, review, set aside, void, or annul the decision of a legislative body to adopt or amend a zoning ordinance.
(C)To determine the reasonableness, legality, or validity of any decision to adopt or amend any regulation attached to a specific plan.
(D)To attack, review, set aside, void, or annul the decision of a legislative body to adopt, amend, or modify a development agreement. An action or proceeding to attack, review, set aside, void, or annul the decisions of a legislative body to adopt, amend, or modify a development agreement shall only extend to the specific portion of the development agreement that is the subject of the adoption, amendment, or modification. This paragraph applies to development agreements, amendments, and modifications adopted on or after January 1, 1996.
(E)To attack, review, set aside, void, or annul any decision on the matters listed in Sections 65901 and 65903, or to determine the reasonableness, legality, or validity of any condition attached to a variance, conditional use permit, or any other permit.
(F)Concerning any of the proceedings, acts, or determinations taken, done, or made prior to any of the decisions listed in subparagraphs (A), (B), (C), (D), and (E).
(2)In the case of an action or proceeding challenging the adoption or revision of a housing element pursuant to this subdivision, the action or proceeding may, in addition, be maintained if it is commenced and service is made on the legislative body within 60 days following the date that the Department of Housing and Community Development reports its findings pursuant to subdivision (h) of Section 65585.
(d)(1)An action or proceeding shall be commenced and the legislative body served after the accrual of the cause of action as provided in this subdivision, if the action or proceeding meets both of the following requirements:
(A)It is brought in support of or to encourage or facilitate the development of housing that would increase the communitys supply of housing affordable to persons and families with low or moderate incomes, as defined in Section 50079.5 of the Health and Safety Code, or with very low incomes, as defined in Section 50105 of the Health and Safety Code, or middle-income households, as defined in Section 65008 of this code. This subdivision is not intended to require that the action or proceeding be brought in support of or to encourage or facilitate a specific housing development project.
(B)It is brought with respect to the adoption or revision of a housing element pursuant to Article 10.6 (commencing with Section 65580) of Chapter 3, actions taken pursuant to Section 65863.6, or Chapter 4.2 (commencing with Section 65913), or to challenge the adequacy of an ordinance adopted pursuant to Section 65915.
(2)(A)An action or proceeding challenging the adoption or revision of a housing element that the Department of Housing and Community Development has found to substantially comply with the requirements of Article 10.6 (commencing with Section 65580) of Chapter 3 shall be commenced, and the legislative body shall be served, within six months after the accrual of the cause of action as provided in this subdivision.
(B)An action or proceeding challenging the adoption or revision of a housing element that the Department of Housing and Community Development has found does not substantially comply with the requirements of Article 10.6 (commencing with Section 65580) of Chapter 3, where the legislative body has failed to change the draft element or amendment to substantially comply with the requirements of Article 10.6 or has adopted the draft element or amendment without change and made findings pursuant to subdivision (f) of Section 65585, shall be commenced, and the legislative body shall be served, within one year after the accrual of the cause of action as provided in this subdivision.
(C)An action or proceeding challenging an action taken pursuant to Section 65863.6, or Chapter 4.2 (commencing with Section 65913), or to challenge the adequacy of an ordinance adopted pursuant to Section 65915 shall be served within 180 days after the accrual of the cause of action as provided in this subdivision.
(3)(A)A cause of action brought pursuant to this subdivision shall not be maintained until 60 days have expired following notice to the city or clerk of the board of supervisors by the party bringing the cause of action, or the partys representative, specifying the deficiencies of the general plan, specific plan, zoning ordinance, or other action described in subparagraph (B) of paragraph (1). A cause of action brought pursuant to this subdivision shall accrue 60 days after notice is filed or the legislative body takes a final action in response to the notice, whichever occurs first.
(B)This notice may be filed at any time within 270 days after an action described in subparagraph (A) of paragraph (2), two years after an action described in subparagraph (B) of paragraph (2), or 180 days after an action described in subparagraph (C) of paragraph (2).
(4)A notice or cause of action brought by one party pursuant to this subdivision shall not bar filing of a notice and initiation of a cause of action by any other party.
(5)After the adoption of a housing element covering the current planning period, no action shall be filed pursuant to this subdivision to challenge a housing element covering a prior planning period.
(e)Upon the expiration of the time limits provided for in this section, all persons are barred from any further action or proceeding.
(f)(1)The period of time before a permit or project approval issued by a city, county, or state agency expires shall not include the period of time during which an action or proceeding involving the approval or conditional approval of the permit or project approval is or was pending.
(2)For purposes of this subdivision:
(A)Pending means the same as described in Section 1049 of the Code of Civil Procedure.
(B)Permit means a variance, conditional use permit, or any other development permit. permit, but does not include any of the following:
(i)A building permit or other permit issued under the California Building Standards Code (Title 24 of the California Code of Regulations) or any applicable local building code for the construction, demolition, or alteration of buildings, whether discretionary or nondiscretionary.
(ii)A permit for minor or standard excavation and grading.
(iii)A permit for demolition.
(iv)A permit for minor or standard excavation and grading.
(v)Any nondiscretionary permit or review that is required or issued by the local agency after the entitlement process has been completed to begin construction.
(g)Notwithstanding Sections 65700 and 65803, or any other provision of law, this section shall apply to charter cities.
(h)Except as provided in subdivision (d), this section shall not affect any law prescribing or authorizing a shorter period of limitation than that specified herein.
(i)Except as provided in subparagraph (D) of paragraph (1) of subdivision (c), this section shall be applicable to those decisions of the legislative body of a city, county, or city and county made pursuant to this division on or after January 1, 1984.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
(a)(1)The Legislature finds and declares that there currently is a housing crisis in California and it is essential to reduce delays and restraints upon expeditiously completing housing projects.
(2)The Legislature further finds and declares that a legal action or proceeding challenging a decision of a city, county, or city and county has a chilling effect on the confidence with which property owners and local governments can proceed with projects. Legal actions or proceedings filed to attack, review, set aside, void, or annul a decision of a city, county, or city and county pursuant to this division, including, but not limited to, the implementation of general plan goals and policies that provide incentives for affordable housing, open-space and recreational opportunities, and other related public benefits, can prevent the completion of needed developments even though the projects have received required governmental approvals.
(3)The purpose of this section is to provide certainty for property owners and local governments regarding decisions made pursuant to this division.
(b)(1)In an action or proceeding to attack, review, set aside, void, or annul a finding, determination, or decision of a public agency made pursuant to this title at a properly noticed public hearing, the issues raised shall be limited to those raised in the public hearing or in written correspondence delivered to the public agency prior to, or at, the public hearing, except where the court finds either of the following:
(A)The issue could not have been raised at the public hearing by persons exercising reasonable diligence.
(B)The body conducting the public hearing prevented the issue from being raised at the public hearing.
(2)If a public agency desires the provisions of this subdivision to apply to a matter, it shall include in any public notice issued pursuant to this title a notice substantially stating all of the following: If you challenge the (nature of the proposed action) in court, you may be limited to raising only those issues you or someone else raised at the public hearing described in this notice, or in written correspondence delivered to the (public entity conducting the hearing) at, or prior to, the public hearing.
(3)The application of this subdivision to causes of action brought pursuant to subdivision (d) applies only to the final action taken in response to the notice to the city or clerk of the board of supervisors. If no final action is taken, then the issue raised in the cause of action brought pursuant to subdivision (d) shall be limited to those matters presented at a properly noticed public hearing or to those matters specified in the notice given to the city or clerk of the board of supervisors pursuant to subdivision (d), or both.
(c)(1)Except as provided in subdivision (d), no action or proceeding shall be maintained in any of the following cases by any person unless the action or proceeding is commenced and service is made on the legislative body within 90 days after the legislative bodys decision:
(A)To attack, review, set aside, void, or annul the decision of a legislative body to adopt or amend a general or specific plan. This paragraph does not apply where an action is brought based upon the complete absence of a general plan or a mandatory element thereof, but does apply to an action attacking a general plan or mandatory element thereof on the basis that it is inadequate.
(B)To attack, review, set aside, void, or annul the decision of a legislative body to adopt or amend a zoning ordinance.
(C)To determine the reasonableness, legality, or validity of any decision to adopt or amend any regulation attached to a specific plan.
(D)To attack, review, set aside, void, or annul the decision of a legislative body to adopt, amend, or modify a development agreement. An action or proceeding to attack, review, set aside, void, or annul the decisions of a legislative body to adopt, amend, or modify a development agreement shall only extend to the specific portion of the development agreement that is the subject of the adoption, amendment, or modification. This paragraph applies to development agreements, amendments, and modifications adopted on or after January 1, 1996.
(E)To attack, review, set aside, void, or annul any decision on the matters listed in Sections 65901 and 65903, or to determine the reasonableness, legality, or validity of any condition attached to a variance, conditional use permit, or any other permit.
(F)Concerning any of the proceedings, acts, or determinations taken, done, or made prior to any of the decisions listed in subparagraphs (A), (B), (C), (D), and (E).
(2)In the case of an action or proceeding challenging the adoption or revision of a housing element pursuant to this subdivision, the action or proceeding may, in addition, be maintained if it is commenced and service is made on the legislative body within 60 days following the date that the Department of Housing and Community Development reports its findings pursuant to subdivision (h) of Section 65585.
(d)(1)An action or proceeding shall be commenced and the legislative body served after the accrual of the cause of action as provided in this subdivision, if the action or proceeding meets both of the following requirements:
(A)It is brought in support of or to encourage or facilitate the development of housing that would increase the communitys supply of housing affordable to persons and families with low or moderate incomes, as defined in Section 50079.5 of the Health and Safety Code, or with very low incomes, as defined in Section 50105 of the Health and Safety Code, or middle-income households, as defined in Section 65008 of this code. This subdivision is not intended to require that the action or proceeding be brought in support of or to encourage or facilitate a specific housing development project.
(B)It is brought with respect to the adoption or revision of a housing element pursuant to Article 10.6 (commencing with Section 65580) of Chapter 3, actions taken pursuant to Section 65863.6, or Chapter 4.2 (commencing with Section 65913), or to challenge the adequacy of an ordinance adopted pursuant to Section 65915.
(2)(A)An action or proceeding challenging the adoption or revision of a housing element that the Department of Housing and Community Development has found to substantially comply with the requirements of Article 10.6 (commencing with Section 65580) of Chapter 3 shall be commenced, and the legislative body shall be served, within six months after the accrual of the cause of action as provided in this subdivision.
(B)An action or proceeding challenging the adoption or revision of a housing element that the Department of Housing and Community Development has found does not substantially comply with the requirements of Article 10.6 (commencing with Section 65580) of Chapter 3, where the legislative body has failed to change the draft element or amendment to substantially comply with the requirements of Article 10.6 or has adopted the draft element or amendment without change and made findings pursuant to subdivision (f) of Section 65585, shall be commenced, and the legislative body shall be served, within one year after the accrual of the cause of action as provided in this subdivision.
(C)An action or proceeding challenging an action taken pursuant to Section 65863.6, or Chapter 4.2 (commencing with Section 65913), or to challenge the adequacy of an ordinance adopted pursuant to Section 65915 shall be served within 180 days after the accrual of the cause of action as provided in this subdivision.
(3)(A)A cause of action brought pursuant to this subdivision shall not be maintained until 60 days have expired following notice to the city or clerk of the board of supervisors by the party bringing the cause of action, or his or her the partys representative, specifying the deficiencies of the general plan, specific plan, zoning ordinance, or other action described in subparagraph (B) of paragraph (1). A cause of action brought pursuant to this subdivision shall accrue 60 days after notice is filed or the legislative body takes a final action in response to the notice, whichever occurs first.
(B)This notice may be filed at any time within 270 days after an action described in subparagraph (A) of paragraph (2), two years after an action described in subparagraph (B) of paragraph (2), or 180 days after an action described in subparagraph (C) of paragraph (2).
(4)A notice or cause of action brought by one party pursuant to this subdivision shall not bar filing of a notice and initiation of a cause of action by any other party.
(5)After the adoption of a housing element covering the current planning period, no action shall be filed pursuant to this subdivision to challenge a housing element covering a prior planning period.
(e)Upon the expiration of the time limits provided for in this section, all persons are barred from any further action or proceeding.
(f)(1)The period of time before a permit or project approval issued by a city, county, or state agency expires shall not include the period of time during which an action or proceeding involving the approval or conditional approval of the permit or project approval is or was pending.
(2)For purposes of this subdivision:
(A)Pending means the same as described in Section 1049 of the Code of Civil Procedure.
(B)Permit means a variance, conditional use permit, or any other development permit.
(f)(g)Notwithstanding Sections 65700 and 65803, or any other provision of law, this section shall apply to charter cities.
(g)(h)Except as provided in subdivision (d), this section shall not affect any law prescribing or authorizing a shorter period of limitation than that specified herein.
(h)(i)Except as provided in subparagraph (D) of paragraph (4) (1) of subdivision (c), this section shall be applicable to those decisions of the legislative body of a city, county, or city and county made pursuant to this division on or after January 1, 1984.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
|
Date
|
Status
|
|---|---|
| Sep 19, 2024 | Chaptered by Secretary of State - Chapter 270, Statutes of 2024. |
| Sep 19, 2024 | Approved by the Governor. |
| Aug 23, 2024 | Enrolled and presented to the Governor at 4 p.m. |
| Aug 15, 2024 | Senate amendments concurred in. To Engrossing and Enrolling. (Ayes 76. Noes 0. Page 6307.). |
| Aug 12, 2024 | In Assembly. Concurrence in Senate amendments pending. May be considered on or after August 14 pursuant to Assembly Rule 77. |
| Aug 12, 2024 | Read third time. Passed. Ordered to the Assembly. (Ayes 38. Noes 0. Page 5043.). |
| Aug 6, 2024 | Read second time. Ordered to Consent Calendar. |
| Aug 5, 2024 | From committee: Be ordered to second reading file pursuant to Senate Rule 28.8 and ordered to Consent Calendar. |
| Jul 3, 2024 | From committee: Do pass and re-refer to Com. on APPR with recommendation: To Consent Calendar. (Ayes 10. Noes 0.) (July 2). Re-referred to Com. on APPR. |
| Jun 12, 2024 | Read second time and amended. Re-referred to Com. on HOUSING. |
| Jun 11, 2024 | From committee: Amend, and do pass as amended and re-refer to Com. on HOUSING with recommendation: To Consent Calendar. (Ayes 7. Noes 0.) (June 11). |
| May 29, 2024 | Referred to Coms. on L. GOV. and HOUSING. |
| May 16, 2024 | In Senate. Read first time. To Com. on RLS. for assignment. |
| May 16, 2024 | Read third time. Passed. Ordered to the Senate. (Ayes 71. Noes 0.) |
| May 9, 2024 | Read second time. Ordered to Consent Calendar. |
| May 8, 2024 | From committee: Do pass. To Consent Calendar. (Ayes 15. Noes 0.) (May 8). |
| Apr 25, 2024 | From committee: Do pass and re-refer to Com. on APPR. with recommendation: To Consent Calendar. (Ayes 8. Noes 0.) (April 24). Re-referred to Com. on APPR. |
| Apr 17, 2024 | From committee: Do pass and re-refer to Com. on L. GOV. with recommendation: To Consent Calendar. (Ayes 9. Noes 0.) (April 17). Re-referred to Com. on L. GOV. |
| Apr 3, 2024 | In committee: Hearing postponed by committee. |
| Feb 20, 2024 | Referred to Coms. on H. & C.D. and L. GOV. |
| Feb 6, 2024 | From printer. May be heard in committee March 7. |
| Feb 5, 2024 | Read first time. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Aug 15, 2024 | AB 2117 Joe Patterson Concurrence in Senate Amendments | Assembly Floor |
Passed |
|
| Aug 12, 2024 | Consent Calendar 2nd AB2117 Joe Patterson et al. | Senate Floor |
Passed |
|
| Jul 2, 2024 | Do pass, but first be re-referred to the Committee on [Appropriations] with the recommendation: To Consent Calendar | Senate Standing Committee on Housing |
Passed |
|
| Jun 11, 2024 | Do pass as amended, but first amend, and re-refer to the Committee on [Housing] with the recommendation: To Consent Calendar | Senate Standing Committee on Local Government |
Passed |
|
| May 16, 2024 | AB 2117 Joe Patterson Consent Calendar Second Day Regular Session | Assembly Floor |
Passed |
|
| May 8, 2024 | Do pass. To Consent Calendar. | Assembly Standing Committee on Appropriations |
Passed |
|
| Apr 24, 2024 | Do pass and be re-referred to the Committee on [Appropriations] with recommendation: To Consent Calendar | Assembly Standing Committee on Local Government |
Passed |
|
| Apr 17, 2024 | Do pass and be re-referred to the Committee on [Local Government] with recommendation: To Consent Calendar | Assembly Standing Committee on Housing and Community Development |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| Buildcasa | ** Support | |
| California Builders Alliance | ** Support | |
| California Building Industry Association | ** Support | |
| Chico Builders Association | ** Support | |
| chico chamber of commerce | ** Support | |
| County of Butte | ** Support | |
| East Bay Leadership Council | ** Support | |
| International Interior Design Association Northern California Chapter Inc | ** Support | |
| International Interior Design Association Southern California Chapter | ** Support | |
| North Valley Property Owners Association | ** Support | |
| Sacramento Regional Builders Exchange | ** Support | |
| Sand Hill Property Company | ** Support | |
| SPUR | ** Support | |
| The Two Hundred | ** Support | |
| Valley Contractors Exchange | ** Support | |
| Valley Contractors Workforce Foundation | ** Support | |
| Yimby Action | ** Support |
CONCURRENCE IN SENATE AMENDMENTS
CSA1 Bill Id:AB 2117
Author:(Joe Patterson)
As Amended Ver:June 12, 2024
Majority vote
SUMMARY
Excludes time spent in litigation from the timeframe in which a permit or other local project approval can expire.
Senate Amendments
Excludes the following from the definition of a "permit" for purposes of this bill:
- A building permit or other permit issued pursuant to the building standards code or other applicable local building code for the construction, demolition, or alteration of building, whether discretionary or nondiscretionary;
- A permit for demolition;
- A permit of minor or standard excavation and grading; and
- Any non discretionary permit or review that is required or issued by the local agency after the entitlement process has been completed to begin construction.
COMMENTS
Permit and Entitlement Expiration: California's Building Standards Codes (CBSC) are published in their entirety every three years. Intervening code adoption cycles produce supplement pages half-way (18 months) into each triennial period. Amendments to California's building standards are subject to a lengthy and transparent public participation process throughout each code adoption cycle. There are a few exemptions which allow a local governing body, city, or county to modify state building standards. A local governing body, city, or county can adopt an ordinance or a resolution in a public meeting that finds that a local building standard must be modified from the state building standard because of local climatic, geological or topographical conditions, and must file that ordinance with the CBSC. The CBSC reviews the findings of the ordinance to determine if the local governing body followed the correct procedure.
A developer is subject to the state's building standards and any local changes made through an ordinance to the state's building standards at the time the permit is issued. Unless there is a local ordinance setting forth different local timelines, building permits are deemed expired twelve months after issuance if the work has not begun or if the permittee has suspended or abandoned work any time after the permit is issued. Building officials have discretion to grant one or more extensions for time periods of not more than 180 days if the permittee requests an extension and provides a written demonstrable justifiable cause for the extension. Any subsequent building permits are subject to building standards in place at the time the permit is issued. This bill would exclude building permits or other permits issued pursuant to relevant building codes from its provisions, as well as demolition permits, excavation and grading permits, and other post-entitlement permits.
Local governments set their own timelines for planning approval and entitlement expiration through local Municipal Codes, unless specific timelines are set for certain housing projects via state legislation, as is the case in SB 423 (Wiener, Chapter 778, Statutes of 2023). These types of approvals include variances, conditional use permits, and other local approvals. There is typically language in the local Municipal Code stating that a certain action must be taken (e.g. site or building permit issued or tentative map approved) within a period of time or the approval will expire or require an extension of time from the authorizing body. The local policies and procedures surrounding the granting of these extensions vary from jurisdiction to jurisdiction.
SB 423, among other provisions, provides for a streamlined, ministerial approval for housing developments in jurisdictions that are not on track to meet their Regional Housing Needs Allocation (RHNA). For projects approved via that streamlined, ministerial pathway, statute mandates that the local government approval remains valid for three years from the date of final judgment upholding the approval. If litigation is filed on a project approved under SB 423 while the developer is requesting a modification request, the original project approval shall remain valid and shall be further extended during litigation. In doing so, SB 423 sets the precedent for state law to supersede permit and planning approval expiration timelines when a project is subject to litigation, as is proposed by this bill.
Litigation during the approvals process: In California, housing approvals are often subject to litigation, a phenomenon that has become a hurdle in addressing the state's housing crisis. Developers seeking to construct new housing projects must navigate a complex regulatory landscape that includes not only obtaining necessary approvals from local governments but also preparing for potential legal challenges. Legal challenges may arise during the various stages of the local approvals process. They may include environmental lawsuits under the California Environmental Quality Act (CEQA); land use and zoning lawsuits, including litigation brought against zoning approvals, variances, conditional use permits, or other local authorizations; lawsuits over fees assessed to a proposed development; lawsuits over building permits issued – or those not obtained – to name a few examples.
These challenges may arise from community groups or individuals who oppose the development for various reasons, such as concerns about environmental impact, traffic congestion, or changes to neighborhood character. Regardless of the intent behind the lawsuit, all lawsuits add time and costs to the development. In some instances, these lawsuits can last for years, if not decades, and they may be used as a tactic to stall, or indefinitely delay, certain developments. Since the state and local governments set timelines under which planning approvals and building permits expire, it is not uncommon for the approval to expire while a project proponent is held up in litigation.
Litigation under CEQA is one of the most notorious legal challenges that a development proponent may face when proposing a new housing development in California. CEQA was enacted in 1970, and it requires state and local agencies to assess and disclose the environmental impacts of development proposals and to mitigate those impacts whenever feasible. CEQA applies to any development project that requires a public agency's discretionary approval. While the Governor's Office of Planning and Research does issue statewide CEQA guidelines for implementation, no state agency oversees the CEQA process, and as such, citizen suits are the primary enforcement mechanism of CEQA compliance.[1] The nature of CEQA, including the lack of state-level governmental oversight and the broad nature of the statute, make CEQA lawsuits one of the more common tools that opponents use to challenge a proposed development. Critics of CEQA claim that CEQA lawsuits are primarily intended to stall proposed developments, rather than addressing legitimate environmental concerns.
CEQA is also inconsistently applied from jurisdiction to jurisdiction, resulting in increased uncertainty and risk associated with projects that are subject to CEQA, depending on where the project is located.[2] While research has shown that administrative appeals are a more common pathway for project opponents to challenge a CEQA decision, litigation under CEQA does still occur.[3] In a 2014-2017 analysis of five jurisdictions in the Bay Area, UC Berkeley researchers found that 6% of all units approved, or nearly 2,000 homes, were subjected to CEQA lawsuits. There was also significant variation by jurisdiction, with 13% of the units approved in San Francisco undergoing CEQA litigation compared to no CEQA litigation in Palo Alto. A more recent study found that in 2020 alone, CEQA lawsuits sought to block approximately 48,000 approved housing units statewide, representing slightly less than half of the state's total housing pipeline.[4]
The added risk and delays associated with any litigation brought against a proposed development has implications for overall project costs and timelines. These delays may result in local planning and building permit approvals expiring while litigation is ongoing, thus necessitating additional project costs and processes, and subjecting the potential for permit extension to the whims of the local building official, or other local processes in place building permit and planning entitlement timeframes.
The threat of lengthy litigation is a constraint to the state's housing pipeline, and in some instances, results in approved homes never being built. AB 2117 would provide certainty to developers that they will not lose their project approvals simply because their projects are sued by opponents, some of whom may not want to see that development proposal ever be constructed. While there is currently a system in place for developers to request extensions to approved building permits or planning entitlements, those are typically subjected to the approval of local officials, such as the Chief Building Official or local Zoning Administrator. The requests may also involve a public hearing or other local processes. AB 2117 protects approvals already in place when a project is subjected to litigation, with a few exceptions for certain types of permit approvals.
According to the Author
"Assembly Bill 2117 is a simple bill. All it does is ensures that local and state permits do not expire on an approved project while a CEQA challenge is taking place."
Arguments in Support
According to the Chico Builders Association, the sponsor, "This policy change helps represent a crucial step towards protecting applicants, builders, and developers from the detrimental effects of meritless litigation and facilitating the timely commencement and completion of much-needed development projects."
Arguments in Opposition
None on file.
FISCAL COMMENTS
The Senate Committee on Appropriations, pursuant to Rule 28.8, determined that this bill does not possess significant fiscal impact and advanced the bill to the Senate Floor without a vote.
VOTES:
ASM HOUSING AND COMMUNITY DEVELOPMENT: 9-0-0
YES: Ward, Joe Patterson, Grayson, Kalra, Lee, Quirk-Silva, Reyes, Sanchez, Wilson
ASM LOCAL GOVERNMENT: 8-0-1
YES: Juan Carrillo, Waldron, Valencia, Kalra, Pacheco, Ramos, Ward, Wilson
ABS, ABST OR NV: Essayli
ASM APPROPRIATIONS: 15-0-0
YES: Wicks, Sanchez, Arambula, Bryan, Calderon, Wendy Carrillo, Dixon, Mike Fong, Friedman, Haney, Hart, Jim Patterson, Pellerin, Ta, Villapudua
ASSEMBLY FLOOR: 71-0-9
YES: Aguiar-Curry, Alanis, Arambula, Bains, Bauer-Kahan, Bennett, Berman, Boerner, Bonta, Bryan, Calderon, Juan Carrillo, Wendy Carrillo, Chen, Connolly, Davies, Dixon, Essayli, Mike Fong, Friedman, Gabriel, Gallagher, Garcia, Grayson, Haney, Hart, Holden, Hoover, Jackson, Jones-Sawyer, Kalra, Lackey, Lee, Low, Lowenthal, Maienschein, McCarty, McKinnor, Muratsuchi, Stephanie Nguyen, Ortega, Pacheco, Papan, Jim Patterson, Joe Patterson, Pellerin, Petrie-Norris, Quirk-Silva, Ramos, Rendon, Reyes, Luz Rivas, Rodriguez, Blanca Rubio, Sanchez, Santiago, Schiavo, Soria, Ta, Ting, Valencia, Villapudua, Waldron, Wallis, Ward, Weber, Wicks, Wilson, Wood, Zbur, Robert Rivas
ABS, ABST OR NV: Addis, Alvarez, Cervantes, Megan Dahle, Flora, Vince Fong, Gipson, Irwin, Mathis
SENATE FLOOR: 38-0-2
YES: Alvarado-Gil, Archuleta, Ashby, Atkins, Becker, Blakespear, Bradford, Caballero, Cortese, Dahle, Dodd, Durazo, Eggman, Glazer, Gonzalez, Grove, Hurtado, Jones, Laird, Limón, McGuire, Menjivar, Min, Newman, Nguyen, Niello, Ochoa Bogh, Padilla, Portantino, Roth, Rubio, Seyarto, Skinner, Smallwood-Cuevas, Stern, Wahab, Wiener, Wilk
ABS, ABST OR NV: Allen, Umberg
UPDATED
VERSION: June 12, 2024
CONSULTANT: Dori Ganetsos / H. & C.D. / (916) 319-2085 FN: 0003843
Moira O’Neill, Giulia Gualco-Nelson, and Eric Biber, Developing Policy from the Ground Up: Examining Entitlement in the Bay Area to Inform California’s Housing Policy Debates, 2019 ↑
IBID. ↑
IBID. ↑
Jennifer Hernandez, In the Name of The Environment Part III: CEQA, Housing, and the Rule of Law, 2023. ↑
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | AB 2117 |
CONSENT
Bill No: AB 2117
Author: Joe Patterson (R), et al.
Amended: 6/12/24 in Senate
Vote: 21
SENATE LOCAL GOVERNMENT COMMITTEE: 7-0, 6/11/24
AYES: Durazo, Seyarto, Dahle, Glazer, Skinner, Wahab, Wiener
SENATE HOUSING COMMITTEE: 10-0, 7/2/24
AYES: Skinner, Ochoa Bogh, Blakespear, Caballero, Cortese, Menjivar, Padilla, Seyarto, Umberg, Wahab
SENATE APPROPRIATIONS COMMITTEE: Senate Rule 28.8
ASSEMBLY FLOOR: 71-0, 5/16/24 (Consent) - See last page for vote
SUBJECT: Development permit expirations: actions or proceedings
SOURCE: Chico Builders Association
DIGEST:
This bill delays expiration of a development approval for the duration of any litigation over the project.
ANALYSIS:
Existing law:
- Establishes procedures through which someone can challenge a decision related to a proposed development in court, including limiting that legal challenge to issues brought up at the public hearing or prior to the hearing.
- Establishes a 90-day timeframe from the time of decision by a legislative body in which legal actions or proceedings related to the legislative body’s decision surrounding development agreements, variances, conditional use permits (CUPs), or any other permit can be brought forward. After that, no further legal actions or proceedings can be brought against the decision.
- Mandates that every permit shall remain valid if work on the site authorized begins within 12 months of permit issuance, unless the permittee has abandoned the work.
- Allows a permittee to request one or more permit extensions of not more than 180 days per extension, to be granted by the local building official.
- Provides for a streamlined, ministerial approval process pursuant to SB 35 (Wiener, Chapter 366, Statutes of 2017) for infill projects with two or more residential units in jurisdictions that are not on track to meet their Regional Housing Needs Assessment. For projects approved pursuant to that streamlined, ministerial process, the local government approval remains valid for three years from the date of final judgment upholding the approval. If litigation is filed against a project approved while the developer is requesting a modification request, the original project approval shall remain valid and shall be further extended during the pendency of the litigation.
This bill:
- Excludes the time when litigation over a permit approval is pending from counting towards the period of time before a permit or project approval issued by a city, county, or state agency expires.
- Defines “permit” as a variance, CUP, or any other development permit but does not include any of the following:
- A building permit or other permit issued pursuant to the building standards code or other applicable local building code for the construction, demolition, or alteration of building, whether discretionary or nondiscretionary;
- A permit for demolition;
- A permit of minor or standard excavation and grading; or
- Any non discretionary permit or review that is required or issued by the local agency after the entitlement process has been completed to begin construction.
Background
Local governments generally set their own timelines for planning approval and entitlement expiration through local municipal codes. The local policies and procedures surrounding the granting of these extensions vary from jurisdiction to jurisdiction. However, in some cases, state law establishes timelines for the validity of approvals, such the Subdivision Map Act, which establishes a minimum life for subdivision maps that may be extended by the local agency, or streamlined, ministerial housing approvals under SB 35 (Wiener, Chapter 366, Statutes of 2017).
Litigation timelines. State law sets out a variety of procedures for challenging local agency land use decisions in the courts. A plaintiff can only raise issues brought up during the public hearing process or in writing before the decision, except if the issue couldn’t have been raised by someone exercising reasonable diligence, or if the local agency stopped the issue from being raised. State law also places time limits by which someone must bring an action to litigate local agency land use decisions, including:
- 30 days from publishing the notice of certain actions under the California Environmental Quality Act (CEQA), unless there was no notification of the agency’s action under CEQA, in which case the limitation is 180 days following the agency’s determination;
- 90 days from the local agency’s decision, for decisions related to general plans, zoning ordinances, specific plans, development agreements, conditional use permits, variances, subdivisions, and others; and
- Six months after approval of a housing element by the Department of Housing and Community Development (HCD), or one year after HCD has found a housing element isn’t in compliance and the local agency fails to make required changes to make the housing element comply.
The 90-day timeline for challenging most land use approvals is much shorter than for challenging other state or local actions, with the express intent of the Legislature to provide certainty for property owners and local governments regarding land use decisions.
Litigation often targets housing approvals in particular. According to the Little Hoover Commission on CEQA, CEQA: Targeted Reforms for California’s Core Environmental Law, “approximately a quarter of CEQA suits target some form of housing development, the most common single type of project challenged by CEQA litigation.”
While some land use statutes, such as the Subdivision Map Act and SB 35, exclude time spent in litigation from counting towards the expiration of a development approval, the Chico Builders Association wants to ensure other project approvals don’t expire as a result of litigation.
Comments
Purpose of the bill. According to the author, “Assembly Bill 2117 is a simple bill. All it does is ensures that local and state permits do not expire on an approved project while a CEQA challenge is taking place.”
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
SUPPORT: (Verified 8/5/24)
Chico Builders Association (source)
Buildcasa
California Builders Alliance
California Building Industry Association
Chico Chamber of Commerce
County of Butte
East Bay Leadership Council
International Interior Design Association Northern California Chapter
International Interior Design Association Southern California Chapter
North Valley Property Owners Association
Sacramento Regional Builders Exchange
Sand Hill Property Company
Spur
The Two Hundred
Valley Contractors Exchange
Valley Contractors Workforce Foundation
Yimby Action
OPPOSITION: (Verified 8/5/24)
None received
ASSEMBLY FLOOR: 71-0, 5/16/24
AYES: Aguiar-Curry, Alanis, Arambula, Bains, Bauer-Kahan, Bennett, Berman, Boerner, Bonta, Bryan, Calderon, Juan Carrillo, Wendy Carrillo, Chen, Connolly, Davies, Dixon, Essayli, Mike Fong, Friedman, Gabriel, Gallagher, Garcia, Grayson, Haney, Hart, Holden, Hoover, Jackson, Jones-Sawyer, Kalra, Lackey, Lee, Low, Lowenthal, Maienschein, McCarty, McKinnor, Muratsuchi, Stephanie Nguyen, Ortega, Pacheco, Papan, Jim Patterson, Joe Patterson, Pellerin, Petrie-Norris, Quirk-Silva, Ramos, Rendon, Reyes, Luz Rivas, Rodriguez, Blanca Rubio, Sanchez, Santiago, Schiavo, Soria, Ta, Ting, Valencia, Villapudua, Waldron, Wallis, Ward, Weber, Wicks, Wilson, Wood, Zbur, Robert Rivas
NO VOTE RECORDED: Addis, Alvarez, Cervantes, Megan Dahle, Flora, Vince Fong, Gipson, Irwin, Mathis
Prepared by: Anton Favorini-Csorba / L. GOV. / (916) 651-4119
8/7/24 17:51:16
**** END ****
SENATE COMMITTEE ON HOUSING
Senator Nancy Skinner, Chair
2023 - 2024 Regular
Bill No: AB 2117 Hearing Date: 7/2/2024
Author: | Joe Patterson | ||
Version: | 6/12/2024 | ||
Urgency: | No | Fiscal: | Yes |
Consultant: | Alison Hughes | ||
SUBJECT: Development permit expirations: actions or proceedings.
DIGEST: This bill delays the expiration of specified development approvals for the duration of any litigation over the project.
ANALYSIS:
Existing law:
- Establishes procedures through which someone can challenge a decision related to a proposed development in court, including limiting that legal challenge to issues brought up at the public hearing or prior to the hearing.
- Establishes a 90-day timeframe from the time of decision by a legislative body in which legal actions or proceedings related to the legislative body’s decision surrounding development agreements, variances, conditional use permits (CUPs), or any other permit can be brought forward. After that, no further legal actions or proceedings can be brought against the decision.
- Mandates that every permit shall remain valid if work on the site authorized begins within 12 months of permit issuance, unless the permittee has abandoned the work.
- Allows a permittee to request one or more permit extensions of not more than 180 days per extension, to be granted by the local building official.
- Provides for a streamlined, ministerial approval process pursuant to SB 35 (Wiener, Chapter 366, Statutes of 2017) for infill projects with two or more residential units in jurisdictions that are not on track to meet their Regional Housing Needs Assessment. For projects approved pursuant to that streamlined, ministerial process, the local government approval remains valid for three years from the date of final judgment upholding the approval. If litigation is filed against a project approved while the developer is requesting a modification request, the original project approval shall remain valid and shall be further extended during the pendency of the litigation.
This bill:
- Defines “permit” as a variance, CUP, or any other development permit but does not include: (1) a building permit or other permit issued pursuant to the building standards code or other applicable local building code for the construction, demolition, or alteration of building, whether discretionary or nondiscretionary; a permit for minor or standard excavation and grading; (3) a permit for demolition; (4) a permit of minor or standard excavation and grading; or (5) any non discretionary permit or review that is required or issued by the local agency after the entitlement process has been completed to begin construction.
- Provides that the period-of-time before a permit or project approval issued by a local government or state agency expires shall not include the period-of-time during which an action or proceeding involving the approval or conditional approval of the permit to project approval is or was pending.
COMMENTS:
- Author’s statement. “Assembly Bill 2117 is a simple bill. All it does is ensures that local and state permits do not expire on an approved project while a CEQA challenge is taking place.”
- Housing planning and zoning. Cities and counties enact zoning ordinances to implement their general plans. Zoning determines the type of developments, such as the type of housing that can be built on properties within the zone. In addition, before building new housing, housing developers must obtain one or more permits from the city or county.
Some housing projects can be permitted by city or county planning staff ministerially or without further approval from elected officials. Projects reviewed ministerially require only an administrative review designed to ensure they are consistent with existing general plan and zoning rules, as well as meet standards for building quality, health, and safety. Most large housing projects are not allowed ministerial review. Instead, these projects are vetted through both public hearings and administrative review. Most housing projects that require discretionary review and approval are subject to review under the California Environmental Quality Act (CEQA), while projects permitted ministerially generally are not.
- Housing entitlements and permitting process. In general, constructing a housing development project requires local government approval at multiple stages; this approval process is often referred to as the entitlement process. An approval is generally considered an entitlement when it locks in the regulatory standards that a local government or state agency can apply to a project. Entitlements are powerful documents as they provide certainty to developers, which can help them secure financing for a project. However, entitlements also constrain the ability of local governments and state agencies to adjust for new conditions. Additionally, when an issued entitlement is outstanding, it alters the ability of the local government or state agency to approve other projects that could potentially be impacted by the pending project. Therefore, various entitlements are subject to expiration, although many may be extended at the discretion of the local government or state agency.
According to a study conducted by Berkeley Law School and others, Getting It Right: Examining the Local Land Use Entitlement Process in California to Inform Policy and Process, in which local government land use and review processes across selected cities in the Bay Area and Southern California were examined, “the processes by which local governments review residential development projects under their zoning ordinances and under CEQA varies from city to city. As a result, developers seeking to construct residential projects often must learn to navigate very different and complicated land use systems, even if they work in the same region.” In addition, developers of affordable housing projects must navigate a web of overlapping eligibility criteria and application deadlines for various state and local housing programs, which often results in project delays as developers work to line up various funding sources.
Local governments generally set their own timelines for planning approval and entitlement expiration through local municipal codes. The local policies and procedures surrounding the granting of these extensions vary from jurisdiction to jurisdiction. However, in some cases, state law establishes timelines for the validity of approvals, such the Subdivision Map Act, which establishes a minimum life for subdivision maps that may be extended by the local agency, the Permit Streamlining Act which establishes timelines for local officials to act on a project approval within a specified timeframe following completion of environmental review under the CEQA, or streamlined, ministerial housing approvals under SB 35 (Wiener, 2017).
- Timelines for litigation. State law sets out a variety of procedures for challenging local agency land use decisions in the courts. A plaintiff can only raise issues brought up during the public hearing process or in writing before the decision, except if the issue couldn’t have been raised by someone exercising reasonable diligence, or if the local agency stopped the issue from being raised. State law also places time limits by which someone must bring an action to litigate local agency land use decisions.
Litigation often targets housing approvals in particular. According to the Little Hoover Commission on CEQA, CEQA: Targeted Reforms for California’s Core Environmental Law, “approximately a quarter of CEQA suits target some form of housing development, the most common single type of project challenged by CEQA litigation.”
Some land use statutes, such as the Subdivision Map Act and SB 35 (Wiener, Chapter 366, Statutes of 2017), exclude time spent in litigation from counting towards the expiration of a development approval, others do not.
This bill excludes the time when litigation over a permit approval is pending from counting towards the period of time before a permit or project approval issued by a city, county, or state agency expires.
- Incoming! This bill was heard on June 11, 2024 in the Local Government Committee and passed out on a 7-0 vote.
FISCAL EFFECT: Appropriation: Fiscal Com.: Local:
POSITIONS: (Communicated to the committee before noon on Wednesday,
June 26, 2024.)
SUPPORT:
BuildCasa
California Builders Alliance
California Building Industry Association
County of Butte
International Interior Design Association Northern California Chapter
International Interior Design Association Southern California Chapter
Sacramento Regional Builders Exchange
Sand Hill Property Company
SPUR
The Two Hundred
YIMBY Action
OPPOSITION:
None received.
-- END --
SENATE COMMITTEE ON LOCAL GOVERNMENT
Senator María Elena Durazo, Chair
2023 - 2024 Regular
Bill No: | AB 2117 | Hearing Date: | 6/11/24 |
Author: | Joe Patterson | Fiscal: | Yes |
Version: | 2/5/24 | Consultant: | Favorini-Csorba |
Development permit expirations: actions or proceedings
Delays expiration of a development approval for the duration of any litigation over the project.
Background
The California Constitution allows cities and counties to “make and enforce within its limits, all local, police, sanitary and other ordinances and regulations not in conflict with general laws.” It is from this fundamental power (commonly called the police power) that cities and counties derive their authority to regulate behavior to preserve the health, safety, and welfare of the public—including land use authority.
Planning and Zoning Law. State law provides additional powers and duties for cities and counties regarding land use. The Planning and Zoning Law requires every county and city to adopt a general plan that sets out planned uses for all of the area that it covers. A general plan must include specified mandatory “elements,” including a housing element that establishes the locations and densities of housing, among other requirements. Cities’ and counties’ major land use decisions—including most zoning ordinances and other aspects of development permitting—must be consistent with their general plans.
Zoning and approval processes. Local governments use their police power to enact zoning ordinances that establish the types of land uses that are allowed or authorized in an area. Zoning often identifies a primary use for parcels in the area, as well as other uses that are allowed if they meet conditions imposed by the local government. For example, an agricultural area may be zoned to allow agricultural uses “by right”—without local discretion—but also allow development of a single family home as an ancillary use, so that the farmer has a house to inhabit. Zoning ordinances also contain provisions to physically shape development and impose other requirements, such as setting maximum heights and densities for housing units, minimum numbers of required parking spaces, setbacks, and lot coverage ratios. These ordinances can also include conditions on development to address aesthetics, community impacts, or other particular site-specific considerations.
Local governments have broad authority to define the specific approval processes needed to satisfy these considerations. Some housing projects can be permitted by city or county planning staff “ministerially” or without further approval from elected officials, but most large housing projects require “discretionary” approvals from local governments, such as a conditional use permit or a change in zoning laws. This process requires hearings by the local planning commission and public notice and may require additional approvals.
Local governments generally set their own timelines for planning approval and entitlement expiration through local municipal codes. The local policies and procedures surrounding the granting of these extensions vary from jurisdiction to jurisdiction. However, in some cases, state law establishes timelines for the validity of approvals, such the Subdivision Map Act, which establishes a minimum life for subdivision maps that may be extended by the local agency, or streamlined, ministerial housing approvals under SB 35 (Wiener, 2017).
Litigation timelines. State law sets out a variety of procedures for challenging local agency land use decisions in the courts. A plaintiff can only raise issues brought up during the public hearing process or in writing before the decision, except if the issue couldn’t have been raised by someone exercising reasonable diligence, or if the local agency stopped the issue from being raised. State law also places time limits by which someone must bring an action to litigate local agency land use decisions, including:
- 30 days from publishing the notice of certain actions under the California Environmental Quality Act (CEQA), unless there was no notification of the agency’s action under CEQA, in which case the limitation is 180 days following the agency’s determination;
- 90 days from the local agency’s decision, for decisions related to general plans, zoning ordinances, specific plans, development agreements, conditional use permits, variances, subdivisions, and others; and
- Six months after approval of a housing element by the Department of Housing and Community Development (HCD), or one year after HCD has found a housing element isn’t in compliance and the local agency fails to make required changes to make the housing element comply.
The 90-day timeline for challenging most land use approvals is much shorter than for challenging other state or local actions, with the express intent of the Legislature to provide certainty for property owners and local governments regarding land use decisions.
Litigation often targets housing approvals in particular. According to the Little Hoover Commission on CEQA, CEQA: Targeted Reforms for California’s Core Environmental Law, “approximately a quarter of CEQA suits target some form of housing development, the most common single type of project challenged by CEQA litigation.”
While some land use statutes, such as the Subdivision Map Act and SB 35, exclude time spent in litigation from counting towards the expiration of a development approval, the Chico Builders Association wants to ensure other project approvals don’t expire as a result of litigation.
Proposed Law
Assembly Bill 2117 excludes the time when litigation over a permit approval is pending from counting towards the period of time before a permit or project approval issued by a city, county, or state agency expires.
The bill defines:
- “Pending” as the time of the litigation’s commencement until its final determination upon appeal, or until the time for appeal has passed, unless the judgment is sooner satisfied; and
- “Permit” as a variance, conditional use permit, or any other development permit.
Comments
1. Purpose of the bill. According to the author, “Assembly Bill 2117 is a simple bill. All it does is ensures that local and state permits do not expire on an approved project while a CEQA challenge is taking place.”
2. Let’s be clear. AB 2117 prevents permits from expiring during litigation, and broadly applies to “any other development permit.” It is unclear whether this would include building permits or other life safety permits that are sought by developers after receiving their approval from the planning commission, city council, or board of supervisors. These “postentitlement permits” ensure compliance with the most up to date safety requirements for building construction promulgated by the state and local agencies. For example, the state’s building standards are updated every three years to reflect new information on building safety, and accordingly, building permit approvals under state law generally expire after one year. To ensure developments are constructed to the latest safety standards, the Committee may wish to consider amending AB 2117 to expressly exclude postentitlement permits from its provisions.
3. Mandate. The California Constitution requires the state to reimburse local governments for the costs of new or expanded state mandated local programs. Because AB 2117 extends the expiration date of local development permits and project approvals, Legislative Counsel says it imposes a new state mandate. AB 2117 disclaims the state's responsibility for providing reimbursement by citing local governments’ authority to charge for the costs of implementing the bill’s provisions.
4. Related legislation. SB 937 (Wiener), which the Committee approved on a 6-0 vote at its April 3rd hearing, extends by 24 months the time frame for any housing entitlement for a priority residential development project, as defined, that was issued to and was in effect on January 1, 2024, and will expire prior to December 31, 2025, and imposes certain limitations on the collection of impact fees. SB 937 is currently pending in the Assembly.
AB 1152 (Patterson, 2023) was similar to this bill. AB 1152 was referred to the Assembly Local Government Committee but never heard.
5. Coming and going. The Senate Rules Committee has ordered a double referral of AB 2117: first to the Committee on Local Government to hear issues related to local permitting, and then to the Committee on Housing.
Assembly Actions
Assembly Housing and Community Development Committee: 9-0
Assembly Local Government Committee: 8-0
Assembly Appropriations Committee: 15-0
Assembly Floor: 71-0
Support and Opposition
(6/7/24)
Support: Chico Builders Association (sponsor)
Buildcasa
California Builders Alliance
California Building Industry Association
Chico Chamber of Commerce
County of Butte
North Valley Property Owners Association
Sacramento Regional Builders Exchange
Sand Hill Property Company
Spur
The Two Hundred
Valley Contractors Exchange
Valley Contractors Workforce Foundation
Yimby Action
Opposition: None received.
-- END --
Date of Hearing: May 8, 2024
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Buffy Wicks, Chair
ABPCA Bill Id:AB 2117
Author:(Joe Patterson) – As Introduced Ver:February 5, 2024
Policy Committee: | Housing and Community Development | Vote: | 9 - 0 |
Local Government | 8 - 0 | ||
|
|
Urgency: No State Mandated Local Program: Yes Reimbursable: No
SUMMARY:
This bill excludes time spent in litigation from the timeframe in which a housing permit or other project approval can expire.
Specifically, this bill:
- Specifies the period of time before a permit or project approval issued by a city, county, or state agency expires does not include the period of time during which an action or proceeding involving the approval or conditional approval of the permit or project approval is or was pending.
- Defines “pending” as the time of the action’s or proceeding’s commencement until its final determination upon appeal, or until the time for appeal has passed, unless the judgment is satisfied sooner.
- Defines “permit” as a variance, conditional use permit, or any other development permit.
FISCAL EFFECT:
No state costs. Local costs resulting from extending the expiration date of a development permit or project approval are not reimbursable by the state because local agencies have general authority to charge and adjust planning and permitting fees to cover their administrative expenses associated with new planning mandates.
COMMENTS:
- Purpose. According to the author, “All [this bill] does is ensure that local and state permits do not expire on an approved project while a CEQA challenge is taking place.”
- Background. In California, housing approvals are often subject to litigation, a phenomenon housing advocates say has become a hurdle in addressing the state's housing crisis. Legal challenges may arise during various stages of the local approval process over a variety of issues, including, perhaps most notably, environmental lawsuits under the California Environmental Quality Act (CEQA). Challenges may arise from community groups or individuals who oppose the development for various reasons, such as concerns about environmental impact, traffic congestion, or changes to neighborhood character. In some instances, lawsuits can last for years, if not decades, and can be used as a tactic to stall, or indefinitely delay, certain developments. Since the state and local governments set timelines under which planning approvals and building permits expire, it is not uncommon for the approval to expire while a project proponent is held up in litigation. This bill suspends the expiration period for permits or project approvals during litigation.
Analysis Prepared by: Jennifer Swenson / APPR. / (916) 319-2081
Date of Hearing: April 24, 2024
ASSEMBLY COMMITTEE ON LOCAL GOVERNMENT
Juan Carrillo, Chair
ABPCA Bill Id:AB 2117 (
Author:Joe Patterson) – As Introduced Ver:February 5, 2024
SUBJECT: Development permit expirations: actions or proceedings.
SUMMARY: Excludes time spent in litigation from the timeframe in which a housing permit or other project approval can expire. Specifically, this bill:
- Defines the time that an action is “pending” as the time of its commencement until its final determination upon appeal, or until the time for appeal has passed, unless the judgment is sooner satisfied.
- Defines “permit” as a variance, conditional use permit, or any other development permit.
- Specifies that the period of time before a permit or project approval issued by a city, county, or state agency expires shall not include the period of time during which an action or proceeding involving the approval or conditional approval of the permit or project approval is or was pending.
- Provides that no reimbursement is required by this bill because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay the program or level of service mandated by this bill.
EXISTING LAW:
- Recognizes that there is a housing crisis in California, affirms the importance of reducing delays in completing housing projects, and acknowledges that legal challenges against decisions made by cities or counties can discourage project applicants from proceeding with projects, even if the necessary approvals are in place. (Government Code (GOV) § 65009)
- Establishes procedures through which someone can challenge a decision related to a proposed development in court, including limiting that legal challenge to issues that were brought up at the public hearing or in written correspondence prior to the hearing. (GOV § 65009)
- Establishes a 90 day timeframe from the time of decision by a legislative body in which legal actions or proceedings related to the legislative body’s decision surrounding development agreements, variances, conditional use permits, or any other permit can be brought forward. After that, no further legal actions or proceedings can be brought against the decision. (GOV § 65009)
- Mandates that every permit shall remain valid if work on the site authorized begins within 12 months of permit issuance, unless the permittee has abandoned the work. (Health and Safety Code (HSC) § 18938.6)
- Allows a permittee to request one or more permit extensions of not more than 180 days per extension, to be granted by the local building official. (HSC § 18938.6)
- Authorizes local governments to adopt local amendments to the California Building Standards Code. (HSC § 18941.5)
- Generally requires state and local government agencies to inform decision makers and the public about the potential environmental impacts of proposed projects, and to reduce those environmental impacts to the extent feasible. (Public Resources Code (PRC) § 21000)
- Exempts certain housing projects from the provisions of CEQA by subjecting them to a streamlined and ministerial approval process. (GOV §§ 65852.2, 65852.22, 65852.23, and 65852.26, 65913.4, 65912.100-65912.140, 65913.16)
- Provides for a streamlined, ministerial approval process [via SB 423 (Wiener), Chapter 778, Statutes of 2023] for infill projects with two or more residential units in jurisdictions that are not on track to meet their Regional Housing Needs Assessment (RHNA). For projects approved via that streamlined, ministerial pathway, the local government approval remains valid for three years from the date of final judgment upholding the approval. If litigation is filed on a project approved under SB 423 while the developer is requesting a modification request, the original project approval shall remain valid and shall be further extended during the pendency of the litigation. (GOV § 65913.4)
FISCAL EFFECT: This bill is keyed fiscal and contains a state mandated local program.
COMMENTS:
- Bill Summary and Author’s Statement. This bill specifies that the period of time before a permit or project approval issued by a city, county, or state agency expires must not include the period of time during which an action or proceeding involving the approval or conditional approval of the permit or project approval is or was pending. The Chico Builders Association is the sponsor of this bill.
According to the author, “Assembly Bill 2117 is a simple bill. All it does is ensures that local and state permits do not expire on an approved project while a CEQA challenge is taking place.”
- Permit and Entitlement Expiration. California’s Building Standards Codes (CBSC) are published in their entirety every three years. Intervening code adoption cycles produce supplement pages half-way (18 months) into each triennial period. Amendments to California’s building standards are subject to a lengthy and transparent public participation process throughout each code adoption cycle. There are a few exemptions which allow a local governing body, city, or county to modify state building standards. A local governing body, city, or county can adopt an ordinance or a resolution in a public meeting that finds that a local building standard must be modified from the state building standard because of local climatic, geological or topographical conditions, and must file that ordinance with the California Building Standards Commission (commission). The commission reviews the findings of the ordinance to determine if the local governing body followed the correct procedure.
A developer is subject to the state's building standards and any local changes made through an ordinance to the state's building standards at the time the permit is issued. Unless there is a local ordinance setting forth different local timelines, building permits are deemed expired twelve months after issuance if the work has not begun or if the permittee has suspended or abandoned work any time after the permit is issued. Building officials have discretion to grant one or more extensions for time periods of not more than 180 days if the permittee requests an extension and provides a written demonstrable and justifiable cause for the extension. Any subsequent building permits are subject to building standards in place at the time the permit is issued.
Local governments set their own timelines for planning approval and entitlement expiration through local Municipal Codes, unless specific timelines are set for certain housing projects via state legislation, as is the case in SB 423. There is typically language in the local Municipal Code stating that a certain action must be taken (e.g. site or building permit issued or tentative map approved) within a period of time or the approval will expire or require an extension of time from the authorizing body. The local policies and procedures surrounding the granting of these extensions vary from jurisdiction to jurisdiction.
SB 423, among other provisions, provides for a streamlined, ministerial approval for housing developments in jurisdictions that are not on track to meet their RHNA. For projects approved via that streamlined, ministerial pathway, statute mandates that the local government approval remains valid for three years from the date of final judgment upholding the approval. If litigation is filed on a project approved under SB 423 while the developer is requesting a modification request, the original project approval shall remain valid and shall be further extended during litigation. In doing so, SB 423 sets the precedent for state law to supersede permit and planning approval expiration timelines when a project is subject to litigation, as is proposed by this bill.
- Litigation During the Approvals Process. In California, housing approvals are often subject to litigation, a phenomenon that has become a hurdle in addressing the state's housing crisis. Developers seeking to construct new housing projects must navigate a complex regulatory landscape that includes not only obtaining necessary approvals from local governments but also preparing for potential legal challenges. Legal challenges may arise during the various stages of the local approvals process. They may include environmental lawsuits under the California Environmental Quality Act (CEQA); land use and zoning lawsuits, including litigation brought against zoning approvals, variances, conditional use permits, or other local authorizations; lawsuits over fees assessed to a proposed development; lawsuits over building permits issued – or those not obtained – to name a few examples.
These challenges may arise from community groups or individuals who oppose the development for various reasons, such as concerns about environmental impact, traffic congestion, or changes to neighborhood character. Regardless of the intent behind the lawsuit, all lawsuits add time and costs to the development. In some instances, these lawsuits can last for years, if not decades, and they may be used as a tactic to stall, or indefinitely delay, certain developments. Since the state and local governments set timelines under which planning approvals and building permits expire, it is not uncommon for the approval to expire while a project proponent is held up in litigation.
- Previous Legislation. AB 1152 (Patterson) of 2023 was similar to this bill. AB 1152 was referred to this committee but never heard.
SB 423 (Wiener), Chapter 778, Statutes of 2023, provided for a streamlined, ministerial approval process for housing developments in jurisdictions that are not on track to meet their RHNA.
- Arguments in Support. According to the bill’s sponsor, Chico Builders Association, “This policy change helps represent a crucial step towards protecting applicants, builders, and developers from the detrimental effects of meritless litigation and facilitating the timely commencement and completion of much-needed development projects. According to the California Department of Housing and Community Development during the last ten years, housing production averaged fewer than 80,000 new homes each year, and ongoing production continues to fall far below the projected need of 180,000 additional homes annually. One reason behind this delay as many are aware, is the fact that the development process often faces significant challenges, including legal actions that can lead to delays, uncertainty, and increased costs. In many cases, these legal challenges are unfounded and serve only to hinder progress without any legitimate basis. Assembly Bill 2117 addresses this issue by providing a mechanism to suspend the expiration period for permits or entitlements during litigation, ensuring that applicants are not unfairly penalized for circumstances beyond their control.
“Furthermore, AB 2117 promotes efficiency and expediency in the development process by allowing applicants to resume development promptly following the conclusion of litigation. Without the burden of reapplying for permits lost due to litigation delays, applicants can focus their resources on advancing their projects, ultimately benefiting the communities they serve. In conclusion, Assembly Bill 2117 represents a sensible and equitable approach to addressing the challenges posed by meritless litigation in the development process. By safeguarding permits and entitlements during litigation and promoting the timely completion of development projects, AB 2117 will contribute to the overall well-being and prosperity of our state.”
- Arguments in Opposition. None on file.
- Double-Referred. This bill is double-referred to the Assembly Housing and Community Development Committee where it passed on a 9-0 vote on April 17, 2024.
REGISTERED SUPPORT / OPPOSITION:
Support
Chico Builders Association [SPONSOR]
BuildCasa
California Building Industry Association
Chico Chamber of Commerce
North Valley Property Owners Association
Sand Hill Property Company
SPUR
The Two Hundred for Homeownership
Valley Contractors Exchange
Valley Contractors Workforce Foundation
YIMBY Action
Opposition
None on file
Analysis Prepared by: Linda Rios / L. GOV. / (916) 319-3958
Date of Hearing: April 17, 2024
ASSEMBLY COMMITTEE ON HOUSING AND COMMUNITY DEVELOPMENT
Christopher M. Ward, Chair
ABPCA Bill Id:AB 2117 (
Author:Joe Patterson) – As Introduced Ver:February 5, 2024
SUBJECT: Development permit expirations: actions or proceedings
SUMMARY: Excludes time spent in litigation from the timeframe in which a housing permit or other project approval can expire. Specifically, this bill:
- Defines the time that an action is “pending” as the time of its commencement until its final determination upon appeal, or until the time for appeal has passed, unless the judgment is satisfied sooner.
- Defines “permit” as a variance, conditional use permit, or any other development permit.
- Specifies that the period of time before a permit or project approval issued by a city, county, or state agency expires shall not include the period of time during which an action or proceeding involving the approval or conditional approval of the permit or project approval is or was pending.
EXISTING LAW:
- Recognizes that there is a housing crisis in California, affirms the importance of reducing delays in completing housing projects, and acknowledges that legal challenges against decisions made by cities or counties can discourage project applicants from proceeding with projects, even if the necessary approvals are in place. (Government Code (GOV) Section 65009)
- Establishes procedures through which someone can challenge a decision related to a proposed development in court, including limiting that legal challenge to issues that were brought up at the public hearing or in written correspondence prior to the hearing. (GOV 65009)
- Establishes a 90 day timeframe from the time of decision by a legislative body in which legal actions or proceedings related to the legislative body’s decision surrounding development agreements, variances, conditional use permits, or any other permit can be brought forward. After that, no further legal actions or proceedings can be brought against the decision. (GOV 65009)
- Mandates that every permit shall remain valid if work on the site authorized begins within 12 months of permit issuance, unless the permittee has abandoned the work. (Health and Safety Code (HSC) 18938.6)
- Allows a permittee to request one or more permit extensions of not more than 180 days per extension, to be granted by the local building official. (HSC 18938.6)
- Authorizes local governments to adopt local amendments to the California Building Standards Code. (HSC 18941.5)
- Generally requires state and local government agencies to inform decision makers and the public about the potential environmental impacts of proposed projects, and to reduce those environmental impacts to the extent feasible. (Public Resources Code (PRC) Section 21000)
- Exempts certain housing projects from the provisions of CEQA by subjecting them to a streamlined and ministerial approvals process. (GOV 65852.2, 65852.22, 65852.23, and 65852.26, 65913.4, 65912.100-65912.140, 65913.16)
- Provides for a streamlined, ministerial approvals process (SB 423) for housing developments in jurisdictions that are not on track to meet their Regional Housing Needs Assessment (RHNA). For projects approved via that streamlined, ministerial pathway, the local government approval remains valid for three years from the date of final judgment upholding the approval. If litigation is filed on a project approved under SB 423 while the developer is requesting a modification request, the original project approval shall remain valid and shall be further extended during the pendency of the litigation. (GOV 65913.4)
FISCAL EFFECT: Unknown.
COMMENTS:
Author’s Statement: According to the author, “Assembly Bill 2117 is a simple bill. All it does is ensures that local and state permits do not expire on an approved project while a CEQA challenge is taking place.”
Permit and Entitlement Expiration: California’s Building Standards Codes (CBSC) are published in their entirety every three years. Intervening code adoption cycles produce supplement pages half-way (18 months) into each triennial period. Amendments to California’s building standards are subject to a lengthy and transparent public participation process throughout each code adoption cycle. There are a few exemptions which allow a local governing body, city, or county to modify state building standards. A local governing body, city, or county can adopt an ordinance or a resolution in a public meeting that finds that a local building standard must be modified from the state building standard because of local climatic, geological or topographical conditions, and must file that ordinance with the CBSC. The CBSC reviews the findings of the ordinance to determine if the local governing body followed the correct procedure.
A developer is subject to the state's building standards and any local changes made through an ordinance to the state's building standards at the time the permit is issued. Unless there is a local ordinance setting forth different local timelines, building permits are deemed expired twelve months after issuance if the work has not begun or if the permittee has suspended or abandoned work any time after the permit is issued. Building officials have discretion to grant one or more extensions for time periods of not more than 180 days if the permittee requests an extension and provides a written demonstrable justifiable cause for the extension. Any subsequent building permits are subject to building standards in place at the time the permit is issued.
Local governments set their own timelines for planning approval and entitlement expiration through local Municipal Codes, unless specific timelines are set for certain housing projects via state legislation, as is the case in SB 423 (Wiener, Chapter 778, Statutes of 2023). There is typically language in the local Municipal Code stating that a certain action must be taken (e.g. site or building permit issued or tentative map approved) within a period of time or the approval will expire or require an extension of time from the authorizing body. The local policies and procedures surrounding the granting of these extensions vary from jurisdiction to jurisdiction.
SB 423, among other provisions, provides for a streamlined, ministerial approval for housing developments in jurisdictions that are not on track to meet their Regional Housing Needs Assessment (RHNA). For projects approved via that streamlined, ministerial pathway, statute mandates that the local government approval remains valid for three years from the date of final judgment upholding the approval. If litigation is filed on a project approved under SB 423 while the developer is requesting a modification request, the original project approval shall remain valid and shall be further extended during litigation. In doing so, SB 423 sets the precedent for state law to supersede permit and planning approval expiration timelines when a project is subject to litigation, as is proposed by this bill.
Litigation during the approvals process: In California, housing approvals are often subject to litigation, a phenomenon that has become a hurdle in addressing the state's housing crisis. Developers seeking to construct new housing projects must navigate a complex regulatory landscape that includes not only obtaining necessary approvals from local governments but also preparing for potential legal challenges. Legal challenges may arise during the various stages of the local approvals process. They may include environmental lawsuits under the California Environmental Quality Act (CEQA); land use and zoning lawsuits, including litigation brought against zoning approvals, variances, conditional use permits, or other local authorizations; lawsuits over fees assessed to a proposed development; lawsuits over building permits issued – or those not obtained – to name a few examples.
These challenges may arise from community groups or individuals who oppose the development for various reasons, such as concerns about environmental impact, traffic congestion, or changes to neighborhood character. Regardless of the intent behind the lawsuit, all lawsuits add time and costs to the development. In some instances, these lawsuits can last for years, if not decades, and they may be used as a tactic to stall, or indefinitely delay, certain developments. Since the state and local governments set timelines under which planning approvals and building permits expire, it is not uncommon for the approval to expire while a project proponent is held up in litigation.
Litigation under CEQA is one of the most notorious legal challenges that a development proponent may face when proposing a new housing development in California. CEQA was enacted in 1970, and it requires state and local agencies to assess and disclose the environmental impacts of development proposals and to mitigate those impacts whenever feasible. CEQA applies to any development project that requires a public agency’s discretionary approval. While the Governor’s Office of Planning and Research does issue statewide CEQA guidelines for implementation, no state agency oversees the CEQA process, and as such, citizen suits are the primary enforcement mechanism of CEQA compliance.[1] The nature of CEQA, including the lack of state-level governmental oversight and the broad nature of the statute, make CEQA lawsuits one of the more common tools that opponents use to challenge a proposed development. Critics of CEQA claim that CEQA lawsuits are primarily intended to stall proposed developments, rather than addressing legitimate environmental concerns.
CEQA is also inconsistently applied from jurisdiction to jurisdiction, resulting in increased uncertainty and risk associated with projects that are subject to CEQA, depending on where the project is located.[2] While research has shown that administrative appeals are a more common pathway for project opponents to challenge a CEQA decision, litigation under CEQA does still occur.[3] In a 2014-2017 analysis of five jurisdictions in the Bay Area, UC Berkeley researchers found that 6% of all units approved, or nearly 2,000 homes, were subjected to CEQA lawsuits. There was also significant variation by jurisdiction, with 13% of the units approved in San Francisco undergoing CEQA litigation compared to no CEQA litigation in Palo Alto. A more recent study found that in 2020 alone, CEQA lawsuits sought to block approximately 48,000 approved housing units statewide, representing slightly less than half of the state’s total housing pipeline.[4]
The added risk and delays associated with any litigation brought against a proposed development has implications for overall project costs and timelines. These delays may result in local planning and building permit approvals expiring while litigation is ongoing, thus necessitating additional project costs and processes, and subjecting the potential for permit extension to the whims of the local building official, or other local processes in place building permit and planning entitlement timeframes.
Clearly the threat of lengthy litigation is a constraint to the state’s housing pipeline, and in some instances, results in approved homes never being built. AB 2117 would provide certainty to developers that they will not lose their project approvals simply because their projects are sued by opponents, some of whom may not want to see that housing ever be constructed. While there is currently a system in place for developers to request extensions to approved building permits or planning entitlements, those are typically subjected to the approval of local officials, such as the Chief Building Official or local Zoning Administrator. The requests may also involve a public hearing or other local processes. AB 2117 protects approvals already in place when a project is subjected to litigation.
Arguments in Support: According to the bill sponsor, Chico Builders Association, “this policy change helps represent a crucial step towards protecting applicants, builders, and developers from the detrimental effects of meritless litigation and facilitating the timely commencement and completion of much-needed development projects. According to the California Department of Housing and Community Development during the last ten years, housing production averaged fewer than 80,000 new homes each year, and ongoing production continues to fall far below the projected need of 180,000 additional homes annually. One reason behind this delay as many are aware, is the fact that the development process often faces significant challenges, including legal actions that can lead to delays, uncertainty, and increased costs. In many cases, these legal challenges are unfounded and serve only to hinder progress without any legitimate basis. Assembly Bill 2117 addresses this issue by providing a mechanism to suspend the expiration period for permits or entitlements during litigation, ensuring that applicants are not unfairly penalized for circumstances beyond their control.
Furthermore, AB 2117 promotes efficiency and expediency in the development process by allowing applicants to resume development promptly following the conclusion of litigation. Without the burden of reapplying for permits lost due to litigation delays, applicants can focus their resources on advancing their projects, ultimately benefiting the communities they serve.”
Arguments in Opposition: None on file.
Related Legislation:
AB 1152 (Patterson), (2023) Similar to AB 2117, AB 1152 would have required the permit expiration timelines and conditional of approval to be stayed during legal challenges. It was referred to both the Committees of Natural Resources and Local Government, but did not receive a hearing.
SB 423 (Wiener), Chapter 778, Statutes of 2023. Provides for a streamlined, ministerial approvals process for housing developments in jurisdictions that are not on track to meet their Regional Housing Needs Assessment (RHNA). For projects approved via that streamlined, ministerial pathway, the local government approval remains valid for three years from the date of final judgment upholding the approval. If litigation is filed on a project approved under SB 423 while the developer is requesting a modification request, the original project approval shall remain valid and shall be further extended during the pendency of the litigation.
Double referred: This bill was also referred to the Assembly Committee on Local Government, where it will be heard should it pass out of this committee.
REGISTERED SUPPORT / OPPOSITION:
Support
Chico Builders Association (Sponsor)
BuildCasa
California Building Industry Association
Chico Chamber of Commerce
North Valley Property Owners Association
Sand Hill Property Company
SPUR
The Two Hundred
Valley Contractors Exchange
Valley Contractors Workforce Foundation
YIMBY Action
Opposition
None on file.
Analysis Prepared by: Dori Ganetsos / H. & C.D. / (916) 319-2085
Moira O’Neill, Giulia Gualco-Nelson, and Eric Biber, Developing Policy from the Ground Up: Examining Entitlement in the Bay Area to Inform California’s Housing Policy Debates, 2019 ↑
IBID. ↑
IBID. ↑
Jennifer Hernandez, In the Name of The Environment Part III: CEQA, Housing, and the Rule of Law, 2023. ↑
Bill Author