Failed
(2024-05-16: In committee: Held under submission.)
Introduced
In Committee
First Chamber
In Committee
Second Chamber
Enacted
Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations. Existing law requires every electric utility, defined to include electrical corporations, local publicly owned electric utilities, and electrical cooperatives, to develop a standard contract or tariff for net energy metering, as defined, for generation by a renewable electrical generation facility, as defined, and to make this contract or tariff available to eligible customer-generators, as defined, upon request on a first-come-first-served basis until the time that the total rated generating capacity used by eligible customer-generators exceeds 5% of the electric utilitys aggregate customer peak demand.
Existing law requires the commission to have developed a 2nd standard contract or tariff for each large electrical corporation, as defined, to provide net energy metering to additional eligible customer-generators in the electrical corporations service territory and imposes no limitation on the number of new eligible customer-generators entitled to receive service pursuant to this 2nd standard contract or tariff. Existing law requires the commission, in developing the 2nd standard contract or tariff, to ensure that customer-sited renewable distributed generation continues to grow sustainably and to include specific alternatives designed for growth among residential customers in disadvantaged communities. Existing law authorizes the commission to revise the 2nd standard contract or tariff as appropriate. Pursuant to that authorization, the commission has instituted rulemakings and issued decisions relating to the 2nd standard contract or tariff.
This bill would require the commission, as appropriate, to revise the above-described standard contract or tariff to, among other things: ensure that customer-sited renewable distributed generation continues to grow at a pace identified by the state as needed to meet the states climate goals, rather than sustainably; ensure that the standard contract or tariff is based on an independent assessment of the cost of service analysis and the total benefits of the renewable electrical generation facility, including quantifiable nonenergy benefits, as defined; and, ensure that the total benefits of the standard contract or tariff to all customers and the electrical system are approximately equal to or greater than the total costs. The bill would prohibit that cost consideration from compromising the states climate goals or quantifiable nonenergy benefits, as specified. The bill would require every large electrical corporation to make the standard contract or tariff, as revised, available to all new eligible customer-generators upon that revision.Under existing law, a violation of any order, decision, rule, direction, demand, or requirement of the commission is a crime.Because this bill would require a commission action to implement its requirements, the violation of which is a crime, the bill would impose a state-mandated local program.The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.This bill would provide that no reimbursement is required by this act for a specified reason.This bill would require the commission to conduct an independent cost-of-service analysis evaluating the standard contract or tariff developed by the commission in a specified decision.
Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations. Existing law requires every electric utility, defined to include electrical corporations, local publicly owned electric utilities, and electrical cooperatives, to develop a standard contract or tariff for net energy metering, as defined, for generation by a renewable electrical generation facility, as defined, and to make this contract or tariff available to eligible customer-generators, as defined, upon request on a first-come-first-served basis until the time that the total rated generating capacity used by eligible customer-generators exceeds 5% of the electric utilitys aggregate customer peak demand.
Existing law requires the commission to have developed a 2nd standard contract or tariff for each large electrical corporation, as defined, to provide net energy metering to additional eligible customer-generators in the electrical corporations service territory and imposes no limitation on the number of new eligible customer-generators entitled to receive service pursuant to this 2nd standard contract or tariff. Existing law requires the commission, in developing the 2nd standard contract or tariff, to ensure that customer-sited renewable distributed generation continues to grow sustainably and to include specific alternatives designed for growth among residential customers in disadvantaged communities. Existing law authorizes the commission to revise the 2nd standard contract or tariff as appropriate. Pursuant to that authorization, the commission has instituted rulemakings and issued decisions relating to the 2nd standard contract or tariff.
This bill would require the commission, on or before July 1, 2026, and periodically thereafter, commission, as appropriate, to revise the above-described standard contract or tariff to, among other things, things: ensure that customer-sited renewable distributed generation continues to grow at a pace identified by the state as needed to meet the states climate goals, rather than sustainably; ensure that the standard contract or tariff is based on an independent assessment of the cost of service analysis and the total benefits of the renewable electrical generation facility, including quantifiable nonenergy benefits, as defined; and and, ensure that the total benefits of the standard contract or tariff to all customers and the electrical system are approximately equal to or greater than the total costs. The bill would prohibit that cost consideration from compromising the states climate goals or quantifiable nonenergy benefits, as specified. The bill would require every large electrical corporation to make the standard contract or tariff tariff, as revised, available to all new eligible customer-generators beginning on July 1, 2026. upon that revision.
Under existing law, a violation of any order, decision, rule, direction, demand, or requirement of the commission is a crime.
Because this bill would require a commission action to implement its requirements, the violation of which is a crime, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations. Existing law requires every electric utility, defined to include electrical corporations, local publicly owned electric utilities, and electrical cooperatives, to develop a standard contract or tariff for net energy metering, as defined, for generation by a renewable electrical generation facility, as defined, and to make this contract or tariff available to eligible customer-generators, as defined, upon request on a first-come-first-served basis until the time that the total rated generating capacity used by eligible customer-generators exceeds 5% of the electric utilitys aggregate customer peak demand.
Existing law requires the commission to have developed a 2nd standard contract or tariff for each large electrical corporation, as defined, to provide net energy metering to additional eligible customer-generators in the electrical corporations service territory and imposes no limitation on the number of new eligible customer-generators entitled to receive service pursuant to this 2nd standard contract or tariff. Existing law requires the commission, in developing the 2nd standard contract or tariff, to ensure that customer-sited renewable distributed generation continues to grow sustainably and to include specific alternatives designed for growth among residential customers in disadvantaged communities. Existing law authorizes the commission to revise the 2nd standard contract or tariff as appropriate. Pursuant to that authorization, the commission has instituted rulemakings and issued decisions relating to the 2nd standard contract or tariff.
This bill would require the commission, on or before July 1, 2026, and periodically thereafter, to revise the above-described standard contract or tariff to, among other things, ensure that customer-sited renewable distributed generation continues to grow at a pace identified by the state as needed to meet the states climate goals, rather than sustainably; that the standard contract or tariff is based on an independent assessment of the cost of service analysis and the total benefits of the renewable electrical generation facility, including quantifiable nonenergy benefits, as defined; and that the total benefits of the standard contract or tariff to all customers and the electrical system are approximately equal to or greater than the total costs. The bill would prohibit that cost consideration from compromising the states climate goals or quantifiable nonenergy benefits, as specified. The bill would require every large electrical corporation to make the standard contract or tariff available to all new eligible customer-generators beginning on July 1, 2026.
Under existing law, a violation of any order, decision, rule, direction, demand, or requirement of the commission is a crime.
Because this bill would require a commission action to implement its requirements, the violation of which is a crime, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law vests the Public Utilities Commission with regulatory authority over public utilities and authorizes the commission to establish its own procedures, subject to statutory limitations or directions and constitutional requirements of due process. Existing law establishes a Low-Income Oversight Board to advise the commission on low-income electricity, gas, and water customer issues and to serve as a liaison for the commission to low-income ratepayers and representatives. Existing law requires the board to take specified actions to advise the commission regarding the commissions duties and sets out the membership of the board.This bill would make nonsubstantive changes to those provisions relating to the Low-Income Oversight Board.Existing law vests the Public Utilities Commission with regulatory authority over public utilities and authorizes the commission to establish its own procedures, subject to statutory limitations or directions and constitutional requirements of due process. Existing law establishes a Low-Income Oversight Board to advise the commission on low-income electricity, gas, and water customer issues and to serve as a liaison for the commission to low-income ratepayers and representatives. Existing law requires the board to take specified actions to advise the commission regarding the commissions duties and sets out the membership of the board.
This bill would make nonsubstantive changes to those provisions relating to the Low-Income Oversight Board.
(a)The commission shall conduct an independent cost-of-service analysis evaluating the standard contract or tariff developed by the commission in Decision 2212056 (December 15, 2022), Decision Revising Net Energy Metering Tariff and Subtariffs.
(b)This section does not require the commission to revise or update a standard contract or tariff made available to eligible customer-generators.
SECTION 1.Section 2827.1 of the Public Utilities Code is amended to read:2827.1.(a)For purposes of this section, eligible customer-generator, large electrical corporation, and renewable electrical generation facility have the same meanings as defined in Section 2827.(b)Notwithstanding any other law, the commission shall develop a standard contract or tariff, which may include net energy metering, for eligible customer-generators with a renewable electrical generation facility that is a customer of a large electrical corporation no later than December 31, 2015. The commission may develop the standard contract or tariff before December 31, 2015, and may require a large electrical corporation that has reached the net energy metering program limit of subparagraph (B) of paragraph (4) of subdivision (c) of Section 2827 to offer the standard contract or tariff to eligible customer-generators. A large electrical corporation shall offer the standard contract or tariff to an eligible customer-generator beginning July 1, 2017, or before that date if ordered to do so by the commission because it has reached the net energy metering program limit of subparagraph (B) of paragraph (4) of subdivision (c) of Section 2827. The commission may revise the standard contract or tariff as appropriate to achieve the objectives of this section. In developing the standard contract or tariff, the commission shall do all of the following:(1)Ensure that the standard contract or tariff made available to eligible customer-generators ensures that customer-sited renewable distributed generation continues to grow sustainably and include specific alternatives designed for growth among residential customers in disadvantaged communities.(2)Establish terms of service and billing rules for eligible customer-generators.(3)Ensure that the standard contract or tariff made available to eligible customer-generators is based on the costs and benefits of the renewable electrical generation facility.(4)Ensure that the total benefits of the standard contract or tariff to all customers and the electrical system are approximately equal to the total costs.(5)Allow projects greater than one megawatt that do not have significant impact on the distribution grid to be built to the size of the onsite load if the projects with a capacity of more than one megawatt are subject to reasonable interconnection charges established pursuant to the commissions Electric Rule 21 and applicable state and federal requirements.(6)Establish a transition period during which eligible customer-generators taking service under a net energy metering tariff or contract before July 1, 2017, or until the electrical corporation reaches its net energy metering program limit pursuant to subparagraph (B) of paragraph (4) of subdivision (c) of Section 2827, whichever is earlier, shall be eligible to continue service under the previously applicable net energy metering tariff for a length of time to be determined by the commission by March 31, 2014. Any rules adopted by the commission shall consider a reasonable expected payback period based on the year the customer initially took service under the tariff or contract authorized by Section 2827.(7)The commission shall determine which rates and tariffs are applicable to customer-generators only during a rulemaking proceeding. Any fixed charges for residential customer-generators that differ from the fixed charges allowed pursuant to subdivision (e) of Section 739.9 shall be authorized only in a rulemaking proceeding involving every large electrical corporation. The commission shall ensure customer-generators are provided electric service at rates that are just and reasonable.(c)(1)Beginning July 1, 2017, or when ordered to do so by the commission because the large electrical corporation has reached its capacity limitation of subparagraph (B) of paragraph (4) of subdivision (c) of Section 2827, all new eligible customer-generators shall be subject to the standard contract or tariff developed by the commission and any rules, terms, and rates developed pursuant to subdivision (b). There shall be no limitation on the amount of generating capacity or number of new eligible customer-generators entitled to receive service pursuant to the standard contract or tariff after July 1, 2017. An eligible customer-generator that has received service under a net energy metering standard contract or tariff pursuant to Section 2827 that is no longer eligible to receive service shall be eligible to receive service pursuant to the standard contract or tariff developed by the commission pursuant to this section.(2)Notwithstanding paragraph (1), upon the commission revising the standard contract or tariff pursuant to Section 2827.2, all new eligible customer-generators shall be subject to the revised contract or tariff.SEC. 2.Section 2827.2 is added to the Public Utilities Code, to read:2827.2.(a)For purposes of this section, the following definitions apply:(1)Eligible customer-generator, large electrical corporation, and renewable electrical generation facility have the same meanings as defined in Section 2827.(2)Nonenergy benefit means any benefit of energy resources and programs to program participants, nonparticipating customers, and society beyond a large electrical corporations marginal costs of providing electrical service to customers, including, but not limited to, lower energy costs for participants, improved public health, local air quality benefits, water quality and quantity improvements, increased resiliency, protection, or preservation of open-space resources and wildlife habitats, and local economic development.(b)Notwithstanding any other law, the commission shall, as appropriate, revise the standard contract or tariff developed pursuant to Section 2827.1 for an eligible customer-generator with a renewable electrical generation facility that also is a customer of a large electrical corporation to achieve the objectives of this section. In revising the standard contract or tariff, the commission shall do all of the following:(1)Ensure that the standard contract or tariff made available to eligible customer-generators ensures that customer-sited renewable distributed generation continues to grow sustainably at a pace identified by the state as needed to meet the states climate goals and include specific alternatives designed for growth among residential customers in disadvantaged communities.(2)Establish terms of service and billing rules for eligible customer-generators.(3)Ensure that the standard contract or tariff made available to eligible customer-generators is based on an independent assessment of the cost of service analysis and the total benefits of the renewable electrical generation facility, including quantifiable nonenergy benefits.(4)(A)Ensure that the total benefits of the standard contract or tariff to all customers and the electrical system are approximately equal to or greater than the total costs.(B)The commissions achievement of the objective described in subparagraph (A) shall not compromise the achievement of the objectives described in paragraphs (1) and (3).(C)This paragraph does not require nonparticipating ratepayer indifference.(5)Allow a project with a capacity of more than one megawatt that does not have a significant impact on the distribution grid to be built to the size of the onsite load if the project is subject to a reasonable interconnection charge established pursuant to the commissions Electric Rule 21 and applicable state and federal requirements.(6)Determine which rates and tariffs are applicable to customer-generators only during a rulemaking proceeding. Any fixed charges for residential customer-generators that differ from the fixed charges allowed pursuant to subdivision (e) of Section 739.9 shall be authorized only in a rulemaking proceeding involving every large electrical corporation. The commission shall ensure customer-generators are provided electrical service at rates that are just and reasonable.(c)Each large electrical corporation shall make the standard contract or tariff, as revised pursuant to subdivision (b), available to all new eligible customer-generators upon that revision.SEC. 3.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.(a)For purposes of this section, eligible customer-generator, large electrical corporation, and renewable electrical generation facility have the same meanings as defined in Section 2827.
(b)Notwithstanding any other law, the commission shall develop a standard contract or tariff, which may include net energy metering, for eligible customer-generators with a renewable electrical generation facility that is a customer of a large electrical corporation no later than December 31, 2015. The commission may develop the standard contract or tariff before December 31, 2015, and may require a large electrical corporation that has reached the net energy metering program limit of subparagraph (B) of paragraph (4) of subdivision (c) of Section 2827 to offer the standard contract or tariff to eligible customer-generators. A large electrical corporation shall offer the standard contract or tariff to an eligible customer-generator beginning July 1, 2017, or before that date if ordered to do so by the commission because it has reached the net energy metering program limit of subparagraph (B) of paragraph (4) of subdivision (c) of Section 2827. The commission may revise the standard contract or tariff as appropriate to achieve the objectives of this section. In developing the standard contract or tariff, the commission shall do all of the following:
(1)Ensure that the standard contract or tariff made available to eligible customer-generators ensures that customer-sited renewable distributed generation continues to grow sustainably and include specific alternatives designed for growth among residential customers in disadvantaged communities.
(2)Establish terms of service and billing rules for eligible customer-generators.
(3)Ensure that the standard contract or tariff made available to eligible customer-generators is based on the costs and benefits of the renewable electrical generation facility.
(4)Ensure that the total benefits of the standard contract or tariff to all customers and the electrical system are approximately equal to the total costs.
(5)Allow projects greater than one megawatt that do not have significant impact on the distribution grid to be built to the size of the onsite load if the projects with a capacity of more than one megawatt are subject to reasonable interconnection charges established pursuant to the commissions Electric Rule 21 and applicable state and federal requirements.
(6)Establish a transition period during which eligible customer-generators taking service under a net energy metering tariff or contract before July 1, 2017, or until the electrical corporation reaches its net energy metering program limit pursuant to subparagraph (B) of paragraph (4) of subdivision (c) of Section 2827, whichever is earlier, shall be eligible to continue service under the previously applicable net energy metering tariff for a length of time to be determined by the commission by March 31, 2014. Any rules adopted by the commission shall consider a reasonable expected payback period based on the year the customer initially took service under the tariff or contract authorized by Section 2827.
(7)The commission shall determine which rates and tariffs are applicable to customer-generators only during a rulemaking proceeding. Any fixed charges for residential customer-generators that differ from the fixed charges allowed pursuant to subdivision (e) of Section 739.9 shall be authorized only in a rulemaking proceeding involving every large electrical corporation. The commission shall ensure customer-generators are provided electric service at rates that are just and reasonable.
(c)(1)Beginning July 1, 2017, or when ordered to do so by the commission because the large electrical corporation has reached its capacity limitation of subparagraph (B) of paragraph (4) of subdivision (c) of Section 2827, and until July 1, 2026, all new eligible customer-generators shall be subject to the standard contract or tariff developed by the commission and any rules, terms, and rates developed pursuant to subdivision (b). There shall be no limitation on the amount of generating capacity or number of new eligible customer-generators entitled to receive service pursuant to the standard contract or tariff after July 1, 2017. An eligible customer-generator that has received service under a net energy metering standard contract or tariff pursuant to Section 2827 that is no longer eligible to receive service shall be eligible to receive service pursuant to the standard contract or tariff developed by the commission pursuant to this section.
(2)Beginning July 1, 2026, Notwithstanding paragraph (1), upon the commission revising the standard contract or tariff pursuant to Section 2827.2, all new eligible customer-generators shall be subject to the standard contract or tariff developed pursuant to Section 2827.2. revised contract or tariff.
SEC. 3.SEC. 2.Section 2827.2 is added to the Public Utilities Code, to read:2827.2.(a)For purposes of this section, the following definitions apply:
(1)Eligible customer-generator, large electrical corporation, and renewable electrical generation facility have the same meanings as defined in Section 2827.
(2)Nonenergy benefit means any benefit of energy resources and programs to program participants, nonparticipating customers, and society beyond a large electrical corporations marginal costs of providing electrical service to customers, including, but not limited to, lower energy costs for participants, improved public health, local air quality benefits, water quality and quantity improvements, increased resiliency, protection, or preservation of open-space resources and wildlife habitats, and local economic development.
(b)Notwithstanding any other law, the commission shall, on or before July 1, 2026, and periodically thereafter as appropriate, revise the standard contract or tariff developed pursuant to Section 2827.1 for an eligible customer-generator with a renewable electrical generation facility that also is a customer of a large electrical corporation to achieve the objectives of this section. In revising the standard contract or tariff, the commission shall do all of the following:
(1)Ensure that the standard contract or tariff made available to eligible customer-generators ensures that customer-sited renewable distributed generation continues to grow sustainably at a pace identified by the state as needed to meet the states climate goals and include specific alternatives designed for growth among residential customers in disadvantaged communities.
(2)Establish terms of service and billing rules for eligible customer-generators.
(3)Ensure that the standard contract or tariff made available to eligible customer-generators is based on an independent assessment of the cost of service analysis and the total benefits of the renewable electrical generation facility, including quantifiable nonenergy benefits.
(4)(A)Ensure that the total benefits of the standard contract or tariff to all customers and the electrical system are approximately equal to or greater than the total costs.
(B)The commissions achievement of the objective described in subparagraph (A) shall not compromise the achievement of the objectives described in paragraphs (1) and (3).
(C)This paragraph does not require nonparticipating ratepayer indifference.
(5)Allow a project with a capacity of more than one megawatt that does not have a significant impact on the distribution grid to be built to the size of the onsite load if the project is subject to a reasonable interconnection charge established pursuant to the commissions Electric Rule 21 and applicable state and federal requirements.
(6)Determine which rates and tariffs are applicable to customer-generators only during a rulemaking proceeding. Any fixed charges for residential customer-generators that differ from the fixed charges allowed pursuant to subdivision (e) of Section 739.9 shall be authorized only in a rulemaking proceeding involving every large electrical corporation. The commission shall ensure customer-generators are provided electrical service at rates that are just and reasonable.
(c)Each large electrical corporation shall make the standard contract or tariff developed tariff, as revised pursuant to subdivision (b) (b), available to all new eligible customer-generators beginning on July 1, 2026. upon that revision.
SEC. 4.SEC. 3.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
(a)The Legislature finds and declares that a program to provide net energy metering combined with net surplus compensation, co-energy metering, and wind energy co-metering for eligible customer-generators is one way to encourage substantial private investment in renewable energy resources, stimulate in-state economic growth, reduce demand for electricity during peak consumption periods, help stabilize Californias energy supply infrastructure, enhance the continued diversification of Californias energy resource mix, reduce interconnection and administrative costs for electricity suppliers, and encourage conservation and efficiency.
(b)As used in this section, the following terms have the following meanings:
(1)Co-energy metering means a program that is the same in all other respects as a net energy metering program, except that the local publicly owned electric utility has elected to apply a generation-to-generation energy and time-of-use credit formula as provided in subdivision (i).
(2)Electrical cooperative means an electrical cooperative as defined in Section 2776.
(3)Electric utility means an electrical corporation, a local publicly owned electric utility, or an electrical cooperative, or any other entity, except an electric service provider, that offers electrical service. This section shall not apply to a local publicly owned electric utility that serves more than 750,000 customers and that also conveys water to its customers.
(4)(A)Eligible customer-generator means a residential customer, small commercial customer as defined in subdivision (h) of Section 331, or commercial, industrial, or agricultural customer of an electric utility, who uses a renewable electrical generation facility, or a combination of those facilities, with a total capacity of not more than one megawatt, that is located on the customers owned, leased, or rented premises, and is interconnected and operates in parallel with the electrical grid, and is intended primarily to offset part or all of the customers own electrical requirements.
(B)(i)Notwithstanding subparagraph (A), eligible customer-generator includes the Department of Corrections and Rehabilitation using a renewable electrical generation technology, or a combination of renewable electrical generation technologies, with a total capacity of not more than eight megawatts, that is located on the departments owned, leased, or rented premises, and is interconnected and operates in parallel with the electrical grid, and is intended primarily to offset part or all of the facilitys own electrical requirements. The amount of any wind generation exported to the electrical grid shall not exceed 1.35 megawatt at any time.
(ii)Notwithstanding paragraph (2) of subdivision (e), an electrical corporation shall be afforded a prudent but necessary time, as determined by the executive director of the commission, to study the impacts of a request for interconnection of a renewable generator with a capacity of greater than one megawatt under this subparagraph. If the study reveals the need for upgrades to the transmission or distribution system arising solely from the interconnection, the electrical corporation shall be afforded the time necessary to complete those upgrades before the interconnection and those costs shall be borne by the customer-generator. Upgrade projects shall comply with applicable state and federal requirements, including requirements of the Federal Energy Regulatory Commission.
(C)(i)For purposes of this subparagraph, a United States Armed Forces base or facility is an establishment under the jurisdiction of the United States Army, Navy, Air Force, Marine Corps, Space Force, or Coast Guard.
(ii)Notwithstanding subparagraph (A), a United States Armed Forces base or facility is an eligible customer-generator if the base or facility uses a renewable electrical generation facility, or a combination of those facilities, the renewable electrical generation facility is located on premises owned, leased, or rented by the United States Armed Forces base or facility, the renewable electrical generation facility is interconnected and operates in parallel with the electrical grid, the renewable electrical generation facility is intended primarily to offset part or all of the base or facilitys own electrical requirements, and the renewable electrical generation facility has a generating capacity that does not exceed the lesser of 12 megawatts or one megawatt greater than the minimum load of the base or facility over the prior 36 months. Unless prohibited by federal law, a renewable electrical generation facility shall not be eligible for net energy metering for privatized military housing pursuant to this subparagraph if the renewable electrical generation facility was procured using a sole source process. A renewable electrical generation facility procured using best value criteria, if otherwise eligible, may be used for net energy metering for privatized military housing pursuant to this subparagraph. For these purposes, best value criteria means a value determined by objective criteria and may include, but is not limited to, price, features, functions, and life-cycle costs.
(iii)A United States Armed Forces base or facility that is an eligible customer generator customer-generator pursuant to this subparagraph shall not receive compensation for exported generation.
(iv)Notwithstanding paragraph (2) of subdivision (e), an electrical corporation shall be afforded a prudent but necessary time, as determined by the executive director of the commission but not less than 60 working days, to study the impacts of a request for interconnection of a renewable electrical generation facility with a capacity of greater than one megawatt pursuant to this subparagraph. If the study reveals the need for upgrades to the transmission or distribution system arising solely from the interconnection, the electrical corporation shall be afforded the time necessary to complete those upgrades before the interconnection and the costs of those upgrades shall be borne by the eligible customer-generator. Upgrade projects shall comply with applicable state and federal requirements, including requirements of the Federal Energy Regulatory Commission. For any a renewable generation facility that interconnects directly to the transmission grid or that requires transmission upgrades, the United States Armed Forces base or facility shall comply with all Federal Energy Regulatory Commission interconnection procedures and requirements.
(v)An electrical corporation shall make a tariff, as approved by the commission, available pursuant to this subparagraph by November 1, 2015.
(vi)This subparagraph shall not apply to a tariff made available pursuant to Section 2827.1.
(5)Large electrical corporation means an electrical corporation with more than 100,000 service connections in California.
(6)Net energy metering means measuring the difference between the electricity supplied through the electrical grid and the electricity generated by an eligible customer-generator and fed back to the electrical grid over a 12-month period as described in subdivisions (c) and (h).
(7)Net surplus customer-generator means an eligible customer-generator that generates more electricity during a 12-month period than is supplied by the electric utility to the eligible customer-generator during the same 12-month period.
(8)Net surplus electricity means all electricity generated by an eligible customer-generator measured in kilowatthours over a 12-month period that exceeds the amount of electricity consumed by that eligible customer-generator.
(9)Net surplus electricity compensation means a per kilowatthour rate offered by the electric utility to the net surplus customer-generator for net surplus electricity that is set by the ratemaking authority pursuant to subdivision (h).
(10)Ratemaking authority means, for an electrical corporation, the commission, for an electrical cooperative, its ratesetting body selected by its shareholders or members, and for a local publicly owned electric utility, the local elected body responsible for setting the rates of the local publicly owned utility.
(11)Renewable electrical generation facility means a facility that generates electricity from a renewable source listed in paragraph (1) of subdivision (a) of Section 25741 of the Public Resources Code. A small hydroelectric generation facility is not an eligible renewable electrical generation facility if it will cause an adverse impact on instream beneficial uses or cause a change in the volume or timing of streamflow.
(12)Wind energy co-metering means any wind energy project greater than 50 kilowatts, but not exceeding one megawatt, where the difference between the electricity supplied through the electrical grid and the electricity generated by an eligible customer-generator and fed back to the electrical grid over a 12-month period is as described in subdivision (h). Wind energy co-metering shall be accomplished pursuant to Section 2827.8.
(c)(1)Except as provided in paragraph (4) and in Section 2827.1, every electric utility shall develop a standard contract or tariff providing for net energy metering, and shall make this standard contract or tariff available to eligible customer-generators, upon request, on a first-come-first-served basis until the time that the total rated generating capacity used by eligible customer-generators exceeds 5 percent of the electric utilitys aggregate customer peak demand. Net energy metering shall be accomplished using a single meter capable of registering the flow of electricity in two directions. An additional meter or meters to monitor the flow of electricity in each direction may be installed with the consent of the eligible customer-generator, at the expense of the electric utility, and the additional metering shall be used only to provide the information necessary to accurately bill or credit the eligible customer-generator pursuant to subdivision (h), or to collect generating system performance information for research purposes relative to a renewable electrical generation facility. If the existing electrical meter of an eligible customer-generator is not capable of measuring the flow of electricity in two directions, the eligible customer-generator shall be responsible for all expenses involved in purchasing and installing a meter that is able to measure electricity flow in two directions. If an additional meter or meters are installed, the net energy metering calculation shall yield a result identical to that of a single meter. An eligible customer-generator that is receiving service other than through the standard contract or tariff may elect to receive service through the standard contract or tariff until the electric utility reaches the generation limit set forth in this paragraph. Once the generation limit is reached, only eligible customer-generators that had previously elected to receive service pursuant to the standard contract or tariff have a right to continue to receive service pursuant to the standard contract or tariff. Eligibility for net energy metering does not limit an eligible customer-generators eligibility for any other rebate, incentive, or credit provided by the electric utility, or pursuant to any governmental program, including rebates and incentives provided pursuant to the California Solar Initiative.
(2)An electrical corporation shall include a provision in the net energy metering contract or tariff requiring that any customer with an existing electrical generating facility and meter who enters into a new net energy metering contract shall provide an inspection report to the electrical corporation, unless the electrical generating facility and meter have been installed or inspected within the previous three years. The inspection report shall be prepared by a California licensed contractor who is not the owner or operator of the facility and meter. A California licensed electrician shall perform the inspection of the electrical portion of the facility and meter.
(3)(A)On an annual basis, every electric utility shall make available to the ratemaking authority information on the total rated generating capacity used by eligible customer-generators that are customers of that provider in the providers service area and the net surplus electricity purchased by the electric utility pursuant to this section.
(B)An electric service provider operating pursuant to Section 394 shall make available to the ratemaking authority the information required by this paragraph for each eligible customer-generator that is their customer for each service area of an electrical corporation, local publicly owned electrical utility, or electrical cooperative, in which the eligible customer-generator has net energy metering.
(C)The ratemaking authority shall develop a process for making the information required by this paragraph available to electric utilities, and for using that information to determine when, pursuant to paragraphs (1) and (4), an electric utility is not obligated to provide net energy metering to additional eligible customer-generators in its service area.
(4)(A)An electric utility that is not a large electrical corporation is not obligated to provide net energy metering to additional eligible customer-generators in its service area when the combined total peak demand of all electricity used by eligible customer-generators served by all the electric utilities in that service area furnishing net energy metering to eligible customer-generators exceeds 5 percent of the aggregate customer peak demand of those electric utilities.
(B)The commission shall require every large electrical corporation to make the standard contract or tariff available to eligible customer-generators, continuously and without interruption, until such times as the large electrical corporation reaches its net energy metering program limit or July 1, 2017, whichever is earlier. A large electrical corporation reaches its program limit when the combined total peak demand of all electricity used by eligible customer-generators served by all the electric utilities in the large electrical corporations service area furnishing net energy metering to eligible customer-generators exceeds 5 percent of the aggregate customer peak demand of those electric utilities. For purposes of calculating a large electrical corporations program limit, aggregate customer peak demand means the highest sum of the noncoincident peak demands of all of the large electrical corporations customers that occurs in any calendar year. To determine the aggregate customer peak demand, every large electrical corporation shall use a uniform method approved by the commission. The program limit calculated pursuant to this paragraph shall not be less than the following:
(i)For San Diego Gas and Electric Company, when it has made 607 megawatts of nameplate generating capacity available to eligible customer-generators.
(ii)For Southern California Edison Company, when it has made 2,240 megawatts of nameplate generating capacity available to eligible customer-generators.
(iii)For Pacific Gas and Electric Company, when it has made 2,409 megawatts of nameplate generating capacity available to eligible customer-generators.
(C)Every large electrical corporation shall file a monthly report with the commission detailing the progress toward the net energy metering program limit established in subparagraph (B). The report shall include separate calculations on progress toward the limits based on operating solar energy systems, cumulative numbers of interconnection requests for net energy metering eligible systems, and any other criteria required by the commission.
(D)(i)Beginning July 1, 2017, or upon reaching the net metering program limit of subparagraph (B), whichever is earlier, and until July 1, 2026, the obligation of a large electrical corporation to provide service pursuant to a standard contract or tariff shall be pursuant to Section 2827.1 and applicable state and federal requirements.
(ii)Beginning July 1, 2026, the obligation of an electric utility to provide service pursuant to a standard contract or tariff shall be pursuant to Section 2827.2 and applicable state and federal requirements.
(d)Every electric utility shall make all necessary forms and contracts for net energy metering and net surplus electricity compensation service available for download from the Internet. internet.
(e)(1)Every electric utility shall ensure that requests for establishment of net energy metering and net surplus electricity compensation are processed in a time period not exceeding that for similarly situated customers requesting new electric service, but not to exceed 30 working days from the date it receives a completed application form for net energy metering service or net surplus electricity compensation, including a signed interconnection agreement from an eligible customer-generator and the electric inspection clearance from the governmental authority having jurisdiction.
(2)Every electric utility shall ensure that requests for an interconnection agreement from an eligible customer-generator are processed in a time period not to exceed 30 working days from the date it receives a completed application form from the eligible customer-generator for an interconnection agreement.
(3)If an electric utility is unable to process a request within the allowable timeframe pursuant to paragraph (1) or (2), it shall notify the eligible customer-generator and the ratemaking authority of the reason for its inability to process the request and the expected completion date.
(f)(1)If a customer participates in direct transactions pursuant to paragraph (1) of subdivision (b) of Section 365, or Section 365.1, with an electric service provider that does not provide distribution service for the direct transactions, the electric utility that provides distribution service for the eligible customer-generator is not obligated to provide net energy metering or net surplus electricity compensation to the customer.
(2)If a customer participates in direct transactions pursuant to paragraph (1) of subdivision (b) of Section 365 or 365.1 with an electric service provider, and the customer is an eligible customer-generator, the electric utility that provides distribution service for the direct transactions may recover from the customers electric service provider the incremental costs of metering and billing service related to net energy metering and net surplus electricity compensation in an amount set by the ratemaking authority.
(g)Except for the time-variant kilowatthour pricing portion of any tariff adopted by the commission pursuant to paragraph (4) of subdivision (a) of Section 2851, each net energy metering contract or tariff shall be identical, with respect to rate structure, all retail rate components, and any monthly charges, to the contract or tariff to which the same customer would be assigned if the customer did not use a renewable electrical generation facility, except that eligible customer-generators shall not be assessed standby charges on the electrical generating capacity or the kilowatthour production of a renewable electrical generation facility. The charges for all retail rate components for eligible customer-generators shall be based exclusively on the customer-generators net kilowatthour consumption over a 12-month period, without regard to the eligible customer-generators choice as to from whom it purchases electricity that is not self-generated. Any new or additional demand charge, standby charge, customer charge, minimum monthly charge, interconnection charge, or any other charge that would increase an eligible customer-generators costs beyond those of other customers who are not eligible customer-generators in the rate class to which the eligible customer-generator would otherwise be assigned if the customer did not own, lease, rent, or otherwise operate a renewable electrical generation facility is contrary to the intent of this section, and shall not form a part of net energy metering contracts or tariffs.
(h)For eligible customer-generators, the net energy metering calculation shall be made by measuring the difference between the electricity supplied to the eligible customer-generator and the electricity generated by the eligible customer-generator and fed back to the electrical grid over a 12-month period. The following rules shall apply to the annualized net metering calculation:
(1)The eligible residential or small commercial customer-generator, at the end of each 12-month period following the date of final interconnection of the eligible customer-generators system with an electric utility, and at each anniversary date thereafter, shall be billed for electricity used during that 12-month period. The electric utility shall determine if the eligible residential or small commercial customer-generator was a net consumer or a net surplus customer-generator during that period.
(2)At the end of each 12-month period, where the electricity supplied during the period by the electric utility exceeds the electricity generated by the eligible residential or small commercial customer-generator during that same period, the eligible residential or small commercial customer-generator is a net electricity consumer and the electric utility shall be owed compensation for the eligible customer-generators net kilowatthour consumption over that 12-month period. The compensation owed for the eligible residential or small commercial customer-generators consumption shall be calculated as follows:
(A)For all eligible customer-generators taking service under contracts or tariffs employing baseline and over baseline rates, any net monthly consumption of electricity shall be calculated according to the terms of the contract or tariff to which the same customer would be assigned to, or be eligible for, if the customer was not an eligible customer-generator. If those same customer-generators are net generators over a billing period, the net kilowatthours generated shall be valued at the same price per kilowatthour as the electric utility would charge for the baseline quantity of electricity during that billing period, and and, if the number of kilowatthours generated exceeds the baseline quantity, the excess shall be valued at the same price per kilowatthour as the electric utility would charge for electricity over the baseline quantity during that billing period.
(B)For all eligible customer-generators taking service under contracts or tariffs employing time-of-use rates, any net monthly consumption of electricity shall be calculated according to the terms of the contract or tariff to which the same customer would be assigned, or be eligible for, if the customer was not an eligible customer-generator. When those same customer-generators are net generators during any discrete time-of-use period, the net kilowatthours produced shall be valued at the same price per kilowatthour as the electric utility would charge for retail kilowatthour sales during that same time-of-use period. If the eligible customer-generators time-of-use electrical meter is unable to measure the flow of electricity in two directions, paragraph (1) of subdivision (c) shall apply.
(C)For all eligible residential and small commercial customer-generators and for each billing period, the net balance of moneys owed to the electric utility for net consumption of electricity or credits owed to the eligible customer-generator for net generation of electricity shall be carried forward as a monetary value until the end of each 12-month period. For all eligible commercial, industrial, and agricultural customer-generators, the net balance of moneys owed shall be paid in accordance with the electric utilitys normal billing cycle, except that if the eligible commercial, industrial, or agricultural customer-generator is a net electricity producer over a normal billing cycle, any excess kilowatthours generated during the billing cycle shall be carried over to the following billing period as a monetary value, calculated according to the procedures set forth in this section, and appear as a credit on the eligible commercial, industrial, or agricultural customer-generators account, until the end of the annual period when paragraph (3) shall apply.
(3)At the end of each 12-month period, where the electricity generated by the eligible customer-generator during the 12-month period exceeds the electricity supplied by the electric utility during that same period, the eligible customer-generator is a net surplus customer-generator and the electric utility, upon an affirmative election by the net surplus customer-generator, shall either (A) provide net surplus electricity compensation for any net surplus electricity generated during the prior 12-month period, or (B) allow the net surplus customer-generator to apply the net surplus electricity as a credit for kilowatthours subsequently supplied by the electric utility to the net surplus customer-generator. For an eligible customer-generator that does not affirmatively elect to receive service pursuant to net surplus electricity compensation, the electric utility shall retain any excess kilowatthours generated during the prior 12-month period. The eligible customer-generator not affirmatively electing to receive service pursuant to net surplus electricity compensation shall not be owed any compensation for the net surplus electricity unless the electric utility enters into a purchase agreement with the eligible customer-generator for those excess kilowatthours. Every electric utility shall provide notice to eligible customer-generators that they are eligible to receive net surplus electricity compensation for net surplus electricity, that they must elect to receive net surplus electricity compensation, and that the 12-month period commences when the electric utility receives the eligible customer-generators election. For an electric utility that is an electrical corporation or electrical cooperative, the commission may adopt requirements for providing notice and the manner by which eligible customer-generators may elect to receive net surplus electricity compensation.
(4)(A)An eligible customer-generator with multiple meters may elect to aggregate the electrical load of the meters located on the property where the renewable electrical generation facility is located and on all property adjacent or contiguous to the property on which the renewable electrical generation facility is located, if those properties are solely owned, leased, or rented by the eligible customer-generator. If the eligible customer-generator elects to aggregate the electric load pursuant to this paragraph, the electric utility shall use the aggregated load for the purpose of determining whether an eligible customer-generator is a net consumer or a net surplus customer-generator during a 12-month period.
(B)If an eligible customer-generator chooses to aggregate pursuant to subparagraph (A), the eligible customer-generator shall be permanently ineligible to receive net surplus electricity compensation, and the electric utility shall retain any kilowatthours in excess of the eligible customer-generators aggregated electrical load generated during the 12-month period.
(C)If an eligible customer-generator with multiple meters elects to aggregate the electrical load of those meters pursuant to subparagraph (A), and different rate schedules are applicable to service at any of those meters, the electricity generated by the renewable electrical generation facility shall be allocated to each of the meters in proportion to the electrical load served by those meters. For example, if the eligible customer-generator receives electric service through three meters, two meters being at an agricultural rate that each provide service to 25 percent of the customers total load, and a third meter, at a commercial rate, that provides service to 50 percent of the customers total load, then 50 percent of the electrical generation of the eligible renewable generation facility shall be allocated to the third meter that provides service at the commercial rate and 25 percent of the generation shall be allocated to each of the two meters providing service at the agricultural rate. This proportionate allocation shall be computed each billing period.
(D)This paragraph shall not become operative for an electrical corporation unless the commission determines that allowing eligible customer-generators to aggregate their load from multiple meters will not result in an increase in the expected revenue obligations of customers who are not eligible customer-generators. The commission shall make this determination by September 30, 2013. In making this determination, the commission shall determine if there are any public purpose or other noncommodity charges that the eligible customer-generators would pay pursuant to the net energy metering program as it exists prior to aggregation, that the eligible customer-generator would not pay if permitted to aggregate the electrical load of multiple meters pursuant to this paragraph.
(E)A local publicly owned electric utility or electrical cooperative shall only allow eligible customer-generators to aggregate their load if the utilitys ratemaking authority determines that allowing eligible customer-generators to aggregate their load from multiple meters will not result in an increase in the expected revenue obligations of customers that are not eligible customer-generators. The ratemaking authority of a local publicly owned electric utility or electrical cooperative shall make this determination within 180 days of the first request made by an eligible customer-generator to aggregate their load. In making the determination, the ratemaking authority shall determine if there are any public purpose or other noncommodity charges that the eligible customer-generator would pay pursuant to the net energy metering or co-energy metering program of the utility as it exists prior to before aggregation, that the eligible customer-generator would not pay if permitted to aggregate the electrical load of multiple meters pursuant to this paragraph. If the ratemaking authority determines that load aggregation will not cause an incremental rate impact on the utilitys customers that are not eligible customer-generators, the local publicly owned electric utility or electrical cooperative shall permit an eligible customer-generator to elect to aggregate the electrical load of multiple meters pursuant to this paragraph. The ratemaking authority may reconsider any determination made pursuant to this subparagraph in a subsequent public proceeding.
(F)For purposes of this paragraph, parcels that are divided by a street, highway, or public thoroughfare are considered contiguous, provided they are otherwise contiguous and under the same ownership.
(G)An eligible customer-generator may only elect to aggregate the electrical load of multiple meters if the renewable electrical generation facility, or a combination of those facilities, has a total generating capacity of not more than one megawatt.
(H)Notwithstanding subdivision (g), an eligible customer-generator electing to aggregate the electrical load of multiple meters pursuant to this subdivision shall remit service charges for the cost of providing billing services to the electric utility that provides service to the meters.
(5)(A)The ratemaking authority shall establish a net surplus electricity compensation valuation to compensate the net surplus customer-generator for the value of net surplus electricity generated by the net surplus customer-generator. The commission shall establish the valuation in a ratemaking proceeding. The ratemaking authority for a local publicly owned electric utility shall establish the valuation in a public proceeding. The net surplus electricity compensation valuation shall be established so as to provide the net surplus customer-generator just and reasonable compensation for the value of net surplus electricity, while leaving other ratepayers unaffected. The ratemaking authority shall determine whether the compensation will include, where appropriate justification exists, either or both of the following components:
(i)The value of the electricity itself.
(ii)The value of the renewable attributes of the electricity.
(B)In establishing the rate pursuant to subparagraph (A), the ratemaking authority shall ensure that the rate does not result in a shifting of costs between eligible customer-generators and other bundled service customers.
(6)(A)Upon adoption of the net surplus electricity compensation rate by the ratemaking authority, any renewable energy credit, as defined in Section 399.12, for net surplus electricity purchased by the electric utility shall belong to the electric utility. Any renewable energy credit associated with electricity generated by the eligible customer-generator that is utilized used by the eligible customer-generator shall remain the property of the eligible customer-generator.
(B)Upon adoption of the net surplus electricity compensation rate by the ratemaking authority, the net surplus electricity purchased by the electric utility shall count toward the electric utilitys renewables portfolio standard annual procurement targets for the purposes of paragraph (1) of subdivision (b) of Section 399.15, or for a local publicly owned electric utility, the renewables portfolio standard annual procurement targets established pursuant to Section 399.30.
(7)The electric utility shall provide every eligible residential or small commercial customer-generator with net electricity consumption and net surplus electricity generation information with each regular bill. That information shall include the current monetary balance owed the electric utility for net electricity consumed, or the net surplus electricity generated, since the last 12-month period ended. Notwithstanding this subdivision, an electric utility shall permit that customer to pay monthly for net energy consumed.
(8)If an eligible residential or small commercial customer-generator terminates the customer relationship with the electric utility, the electric utility shall reconcile the eligible customer-generators consumption and production of electricity during any part of a 12-month period following the last reconciliation, according to the requirements set forth in this subdivision, except that those requirements shall apply only to the months since the most recent 12-month bill.
(9)If an electric service provider or electric utility providing net energy metering to a residential or small commercial customer-generator ceases providing that electric service to that customer during any 12-month period, and the customer-generator enters into a new net energy metering contract or tariff with a new electric service provider or electric utility, the 12-month period, with respect to that new electric service provider or electric utility, shall commence on the date on which the new electric service provider or electric utility first supplies electric service to the customer-generator.
(i)Notwithstanding any other provisions provision of this section, paragraphs (1), (2), and (3) shall apply to an eligible customer-generator with a capacity of more than 10 kilowatts, but not exceeding one megawatt, that receives electric service from a local publicly owned electric utility that has elected to utilize use a co-energy metering program unless the local publicly owned electric utility chooses to provide service for eligible customer-generators with a capacity of more than 10 kilowatts in accordance with subdivisions (g) and (h):
(1)The eligible customer-generator shall be required to utilize use a meter, or multiple meters, capable of separately measuring electricity flow in both directions. All meters shall provide time-of-use measurements of electricity flow, and the customer shall take service on a time-of-use rate schedule. If the existing meter of the eligible customer-generator is not a time-of-use meter or is not capable of measuring total flow of electricity in both directions, the eligible customer-generator shall be responsible for all expenses involved in purchasing and installing a meter that is both time-of-use and able to measure total electricity flow in both directions. This subdivision shall not restrict the ability of an eligible customer-generator to utilize use any economic incentives provided by a governmental agency or an electric utility to reduce its costs for purchasing and installing a time-of-use meter.
(2)The consumption of electricity from the local publicly owned electric utility shall result in a cost to the eligible customer-generator to be priced in accordance with the standard rate charged to the eligible customer-generator in accordance with the rate structure to which the customer would be assigned if the customer did not use a renewable electrical generation facility. The generation of electricity provided to the local publicly owned electric utility shall result in a credit to the eligible customer-generator and shall be priced in accordance with the generation component, established under the applicable structure to which the customer would be assigned if the customer did not use a renewable electrical generation facility.
(3)All costs and credits shall be shown on the eligible customer-generators bill for each billing period. In any months in which the eligible customer-generator has been a net consumer of electricity calculated on the basis of value determined pursuant to paragraph (2), the customer-generator shall owe to the local publicly owned electric utility the balance of electricity costs and credits during that billing period. In any billing period in which the eligible customer-generator has been a net producer of electricity calculated on the basis of value determined pursuant to paragraph (2), the local publicly owned electric utility shall owe to the eligible customer-generator the balance of electricity costs and credits during that billing period. Any net credit to the eligible customer-generator of electricity costs may be carried forward to subsequent billing periods, provided that a local publicly owned electric utility may choose to carry the credit over as a kilowatthour credit consistent with the provisions of any applicable contract or tariff, including any differences attributable to the time of generation of the electricity. At the end of each 12-month period, the local publicly owned electric utility may reduce any net credit due to the eligible customer-generator to zero.
(j)A renewable electrical generation facility used by an eligible customer-generator shall meet all applicable safety and performance standards established by the National Electrical Code, the Institute of Electrical and Electronics Engineers, and accredited testing laboratories, including Underwriters Laboratories Incorporated and, where applicable, rules of the commission regarding safety and reliability. A customer-generator whose renewable electrical generation facility meets those standards and rules shall not be required to install additional controls, perform or pay for additional tests, or purchase additional liability insurance.
(k)If the commission determines that there are cost or revenue obligations for an electrical corporation that may not be recovered from customer-generators acting pursuant to this section, those obligations shall remain within the customer class from which any shortfall occurred and shall not be shifted to any other customer class. Net energy metering and co-energy metering customers shall not be exempt from the public goods charges imposed pursuant to Article 7 (commencing with Section 381), Article 8 (commencing with Section 385), or Article 15 (commencing with Section 399) of Chapter 2.3 of Part 1.
(l)A net energy metering, co-energy metering, or wind energy co-metering customer shall reimburse the Department of Water Resources for all charges that would otherwise be imposed on the customer by the commission to recover bond-related costs pursuant to an agreement between the commission and the Department of Water Resources pursuant to Section 80110 of the Water Code, as well as and the costs of the department equal to the share of the departments estimated net unavoidable power purchase contract costs attributable to the customer. The commission shall incorporate the determination into an existing proceeding before the commission, and shall ensure that the charges are nonbypassable. Until the commission has made a determination regarding the nonbypassable charges, net energy metering, co-energy metering, and wind energy co-metering shall continue under the same rules, procedures, terms, and conditions as were applicable on December 31, 2002.
(m)In implementing the requirements of subdivisions (k) and (l), an eligible customer-generator shall not be required to replace its existing meter except as set forth in paragraph (1) of subdivision (c), nor shall and the electric utility shall not require additional measurement of usage beyond that which is necessary for customers in the same rate class as the eligible customer-generator.
(n)It is the intent of the Legislature that the Treasurer incorporate net energy metering, including net surplus electricity compensation, co-energy metering, and wind energy co-metering projects undertaken pursuant to this section as sustainable building methods or distributive energy technologies for purposes of evaluating low-income housing projects.
SEC. 2.Section 2827.1 of the Public Utilities Code is amended to read:2827.1.(a)For purposes of this section, eligible customer-generator, large electrical corporation, and renewable electrical generation facility have the same meanings as defined in Section 2827.
(b)Notwithstanding any other law, the commission shall develop a standard contract or tariff, which may include net energy metering, for eligible customer-generators with a renewable electrical generation facility that is a customer of a large electrical corporation no later than December 31, 2015. The commission may develop the standard contract or tariff prior to before December 31, 2015, and may require a large electrical corporation that has reached the net energy metering program limit of subparagraph (B) of paragraph (4) of subdivision (c) of Section 2827 to offer the standard contract or tariff to eligible customer-generators. A large electrical corporation shall offer the standard contract or tariff to an eligible customer-generator beginning July 1, 2017, or prior to before that date if ordered to do so by the commission because it has reached the net energy metering program limit of subparagraph (B) of paragraph (4) of subdivision (c) of Section 2827. The commission may revise the standard contract or tariff as appropriate to achieve the objectives of this section. In developing the standard contract or tariff, the commission shall do all of the following:
(1)Ensure that the standard contract or tariff made available to eligible customer-generators ensures that customer-sited renewable distributed generation continues to grow sustainably and include specific alternatives designed for growth among residential customers in disadvantaged communities.
(2)Establish terms of service and billing rules for eligible customer-generators.
(3)Ensure that the standard contract or tariff made available to eligible customer-generators is based on the costs and benefits of the renewable electrical generation facility.
(4)Ensure that the total benefits of the standard contract or tariff to all customers and the electrical system are approximately equal to the total costs.
(5)Allow projects greater than one megawatt that do not have significant impact on the distribution grid to be built to the size of the onsite load if the projects with a capacity of more than one megawatt are subject to reasonable interconnection charges established pursuant to the commissions Electric Rule 21 and applicable state and federal requirements.
(6)Establish a transition period during which eligible customer-generators taking service under a net energy metering tariff or contract prior to before July 1, 2017, or until the electrical corporation reaches its net energy metering program limit pursuant to subparagraph (B) of paragraph (4) of subdivision (c) of Section 2827, whichever is earlier, shall be eligible to continue service under the previously applicable net energy metering tariff for a length of time to be determined by the commission by March 31, 2014. Any rules adopted by the commission shall consider a reasonable expected payback period based on the year the customer initially took service under the tariff or contract authorized by Section 2827.
(7)The commission shall determine which rates and tariffs are applicable to customer generators customer-generators only during a rulemaking proceeding. Any fixed charges for residential customer generators customer-generators that differ from the fixed charges allowed pursuant to subdivision (e) of Section 739.9 shall be authorized only in a rulemaking proceeding involving every large electrical corporation. The commission shall ensure customer generators customer-generators are provided electric service at rates that are just and reasonable.
(c)(1)Beginning July 1, 2017, or when ordered to do so by the commission because the large electrical corporation has reached its capacity limitation of subparagraph (B) of paragraph (4) of subdivision (c) of Section 2827, and until July 1, 2026, all new eligible customer-generators shall be subject to the standard contract or tariff developed by the commission and any rules, terms, and rates developed pursuant to subdivision (b). There shall be no limitation on the amount of generating capacity or number of new eligible customer-generators entitled to receive service pursuant to the standard contract or tariff after July 1, 2017. An eligible customer-generator that has received service under a net energy metering standard contract or tariff pursuant to Section 2827 that is no longer eligible to receive service shall be eligible to receive service pursuant to the standard contract or tariff developed by the commission pursuant to this section.
(2)Beginning July 1, 2026, all new eligible customer-generators shall be subject to the standard contract or tariff developed pursuant to Section 2827.2.
SEC. 3.Section 2827.2 is added to the Public Utilities Code, to read:2827.2.(a)For purposes of this section, the following definitions apply:
(1)Eligible customer-generator, large electrical corporation, and renewable electrical generation facility have the same meanings as defined in Section 2827.
(2)Nonenergy benefit means any benefit of energy resources and programs to program participants, nonparticipating customers, and society beyond a large electrical corporations marginal costs of providing electrical service to customers, including, but not limited to, lower energy costs for participants, improved public health, local air quality benefits, water quality and quantity improvements, increased resiliency, protection, or preservation of open-space resources and wildlife habitats, and local economic development.
(b)Notwithstanding any other law, the commission shall, on or before July 1, 2026, and periodically thereafter as appropriate, revise the standard contract or tariff developed pursuant to Section 2827.1 for an eligible customer-generator with a renewable electrical generation facility that also is a customer of a large electrical corporation to achieve the objectives of this section. In revising the standard contract or tariff, the commission shall do all of the following:
(1)Ensure that the standard contract or tariff made available to eligible customer-generators ensures that customer-sited renewable distributed generation continues to grow sustainably at a pace identified by the state as needed to meet the states climate goals and include specific alternatives designed for growth among residential customers in disadvantaged communities.
(2)Establish terms of service and billing rules for eligible customer-generators.
(3)Ensure that the standard contract or tariff made available to eligible customer-generators is based on an independent assessment of the cost of service analysis and the total benefits of the renewable electrical generation facility, including quantifiable nonenergy benefits.
(4)(A)Ensure that the total benefits of the standard contract or tariff to all customers and the electrical system are approximately equal to or greater than the total costs.
(B)The commissions achievement of the objective described in subparagraph (A) shall not compromise the achievement of the objectives described in paragraphs (1) and (3).
(C)This paragraph does not require nonparticipating ratepayer indifference.
(5)Allow a project with a capacity of more than one megawatt that does not have a significant impact on the distribution grid to be built to the size of the onsite load if the project is subject to a reasonable interconnection charge established pursuant to the commissions Electric Rule 21 and applicable state and federal requirements.
(6)Determine which rates and tariffs are applicable to customer-generators only during a rulemaking proceeding. Any fixed charges for residential customer-generators that differ from the fixed charges allowed pursuant to subdivision (e) of Section 739.9 shall be authorized only in a rulemaking proceeding involving every large electrical corporation. The commission shall ensure customer-generators are provided electrical service at rates that are just and reasonable.
(c)Each large electrical corporation shall make the standard contract or tariff developed pursuant to subdivision (b) available to all new eligible customer-generators beginning on July 1, 2026.
SEC. 4.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
SECTION 1.Section 382.1 of the Public Utilities Code is amended to read:382.1.(a)There is hereby established a Low-Income Oversight Board that shall advise the commission on low-income electricity, gas, and water customer issues and shall serve as a liaison for the commission to low-income ratepayers and representatives. The Low-Income Oversight Board shall replace the Low-Income Advisory Board in existence on January 1, 2000. The Low-Income Oversight Board shall do all of the following to advise the commission regarding the commissions duties:(1)Monitor and evaluate implementation of all programs provided to low-income electricity, gas, and water customers.(2)Assist in the development and analysis of assessments of low-income customer need.(3)Encourage collaboration between state and utility programs for low-income electricity and gas customers to maximize the leverage of state and federal energy efficiency funds to both lower the bills and increase the comfort of low-income customers.(4)Provide reports to the Legislature, as requested, summarizing the assessment of need, audits, and analysis of program implementation.(5)Assist in streamlining the application and enrollment process of programs for low-income electricity and gas customers with general low-income programs, including, but not limited to, the Universal Lifeline Telephone Service (ULTS) program and, including compliance with Section 739.1.(6)Encourage the usage of the network of community service providers in accordance with Section 381.5.(b)The Low-Income Oversight Board shall be comprised of 11 members to be selected as follows:(1)Five members selected by the commission who have expertise in the low-income community and who are not affiliated with any state agency or utility group. These members shall be selected in a manner to ensure an equitable geographic distribution.(2)One member selected by the Governor.(3)One member selected by the commission who is a commissioner or commissioner designee.(4)One member selected by the Department of Community Services and Development.(5)One member selected by the commission who is a representative of private weatherization contractors.(6)One member selected by the commission who is a representative of an electrical or gas corporation.(7)One member selected by the commission who is a representative of a water corporation.(c)The Low-Income Oversight Board shall alternate meeting locations between northern, central, and southern California.(d)The Low-Income Oversight Board may establish a technical advisory committee, consisting of low-income service providers, utility representatives, consumer organizations, and commission staff, to assist the board and may request utility representatives and commission staff to assist the technical advisory committee.(e)The commission shall do all of the following in conjunction with the board:(1)Work with the board, interested parties, and community-based organizations to increase participation in programs for low-income customers.(2)Provide technical support to the board.(3)Ensure that the energy burden of low-income electricity and gas customers is reduced.(4)Provide formal notice of board meetings in the commissions daily calendar.(f)(1)Members of the board and members of the technical advisory committee shall be eligible for compensation in accordance with state guidelines for necessary travel.(2)Members of the board and members of the technical advisory committee who are not salaried state service employees shall be eligible for reasonable compensation for attendance at board meetings.(3)All reasonable costs incurred by the board in carrying out its duties pursuant to subdivision (a), including staffing, travel, and administrative costs, shall be reimbursed through the Public Utilities Commission Utilities Reimbursement Account and shall be part of the budget of the commission and the commission shall consult with the board in the preparation of that portion of the commissions annual proposed budget.(a)There is hereby established a Low-Income Oversight Board that shall advise the commission on low-income electric, electricity, gas, and water customer issues and shall serve as a liaison for the commission to low-income ratepayers and representatives. The Low-Income Oversight Board shall replace the Low-Income Advisory Board in existence on January 1, 2000. The Low-Income Oversight Board shall do all of the following to advise the commission regarding the commissions duties:
(1)Monitor and evaluate implementation of all programs provided to low-income electricity, gas, and water customers.
(2)Assist in the development and analysis of any assessments of low-income customer need.
(3)Encourage collaboration between state and utility programs for low-income electricity and gas customers to maximize the leverage of state and federal energy efficiency funds to both lower the bills and increase the comfort of low-income customers.
(4)Provide reports to the Legislature, as requested, summarizing the assessment of need, audits, and analysis of program implementation.
(5)Assist in streamlining the application and enrollment process of programs for low-income electricity and gas customers with general low-income programs, including, but not limited to, the Universal Lifeline Telephone Service (ULTS) program and, including compliance with Section 739.1.
(6)Encourage the usage of the network of community service providers in accordance with Section 381.5.
(b)The Low-Income Oversight Board shall be comprised of 11 members to be selected as follows:
(1)Five members selected by the commission who have expertise in the low-income community and who are not affiliated with any state agency or utility group. These members shall be selected in a manner to ensure an equitable geographic distribution.
(2)One member selected by the Governor.
(3)One member selected by the commission who is a commissioner or commissioner designee.
(4)One member selected by the Department of Community Services and Development.
(5)One member selected by the commission who is a representative of private weatherization contractors.
(6)One member selected by the commission who is a representative of an electrical or gas corporation.
(7)One member selected by the commission who is a representative of a water corporation.
(c)The Low-Income Oversight Board shall alternate meeting locations between northern, central, and southern California.
(d)The Low-Income Oversight Board may establish a technical advisory committee committee, consisting of low-income service providers, utility representatives, consumer organizations, and commission staff, to assist the board and may request utility representatives and commission staff to assist the technical advisory committee.
(e)The commission shall do all of the following in conjunction with the board:
(1)Work with the board, interested parties, and community-based organizations to increase participation in programs for low-income customers.
(2)Provide technical support to the board.
(3)Ensure that the energy burden of low-income electricity and gas customers is reduced.
(4)Provide formal notice of board meetings in the commissions daily calendar.
(f)(1)Members of the board and members of the technical advisory committee shall be eligible for compensation in accordance with state guidelines for necessary travel.
(2)Members of the board and members of the technical advisory committee who are not salaried state service employees shall be eligible for reasonable compensation for attendance at board meetings.
(3)All reasonable costs incurred by the board in carrying out its duties pursuant to subdivision (a), including staffing, travel, and administrative costs, shall be reimbursed through the public utilities reimbursement account Public Utilities Commission Utilities Reimbursement Account and shall be part of the budget of the commission and the commission shall consult with the board in the preparation of that portion of the commissions annual proposed budget.
|
Date
|
Status
|
|---|---|
| May 16, 2024 | In committee: Held under submission. |
| May 16, 2024 | Joint Rule 62(a), file notice suspended. (Page 5215.) |
| May 15, 2024 | In committee: Set, first hearing. Referred to APPR. suspense file. |
| Apr 30, 2024 | Re-referred to Com. on APPR. |
| Apr 29, 2024 | Read second time and amended. |
| Apr 25, 2024 | From committee: Amend, and do pass as amended and re-refer to Com. on APPR. (Ayes 14. Noes 0.) (April 24). |
| Apr 17, 2024 | In committee: Hearing postponed by committee. |
| Apr 2, 2024 | Re-referred to Com. on U. & E. |
| Apr 1, 2024 | From committee chair, with author's amendments: Amend, and re-refer to Com. on U. & E. Read second time and amended. |
| Mar 12, 2024 | Re-referred to Com. on U. & E. |
| Mar 11, 2024 | From committee chair, with author's amendments: Amend, and re-refer to Com. on U. & E. Read second time and amended. |
| Mar 11, 2024 | Referred to Com. on U. & E. |
| Feb 9, 2024 | From printer. May be heard in committee March 10. |
| Feb 8, 2024 | Read first time. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Apr 24, 2024 | Do pass as amended and be re-referred to the Committee on [Appropriations] | Assembly Standing Committee on Utilities and Energy |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| 350 Bay Area Action | ** Support | |
| 350 Conejo | ** Support | |
| 350 Conejo / San Fernando Valley | ** Support | |
| 350 Humboldt | ** Support | |
| 350 South Bay Los Angeles | ** Support | |
| 350 Southland Legislative Alliance | ** Support | |
| 350 Ventura County Climate Hub | ** Support | |
| Acterra: Action for A Healthy Planet | ** Support | |
| Active San Gabriel Valley | ** Support | |
| Adopt a Charger | ** Support | |
| Advanced Energy Economy | ** Support | |
| Alliance of Nurses for Healthy Environments | ** Support | |
| American Solar Energy Society | ** Support | |
| Ballona Institute | ** Support | |
| Ban SUP | ** Support | |
| California Alliance for Community Energy | ** Support | |
| California Center For Sustainable Energy | ** Support | |
| California Climate Voters | ** Support | |
| California Interfaith Power and Light | ** Support | |
| Californians for Energy Choice | ** Support | |
| Californians for Western Wilderness | ** Support | |
| California Solar & Storage Association | ** Support | |
| California State Association Of Electrical Workers | ** Against | |
| California Wind Energy Association | ** Against | |
| CALPIRG | ** Support | |
| CALPIRG Students | ** Support | |
| Catholic Charities, Diocese of Stockton | ** Support | |
| Center For Biological Diversity | ** Support | |
| Center For Biological Diversity, Inc. | ** Support | |
| Center for Community Energy | ** Support | |
| Center for Progressive Reform | ** Support | |
| Change Begins With Me | ** Support | |
| Clean Coalition | ** Support | |
| Clean Earth 4 Kids | ** Support | |
| cleanearth4kids.org | ** Support | |
| Climate Hawks Vote | ** Support | |
| Cloverdale Indivisible | ** Support | |
| Coalition of California Utility Employees | ** Against | |
| Coastal Lands Action Network | ** Support | |
| Consejo de Federaciones Mexicanas | ** Support | |
| Contra Costa Move On | ** Support | |
| Courageous Resistance of The Desert | ** Support | |
| Culver City Democratic Club | ** Support | |
| Custom Power Solar | ** Support | |
| Defend Ballona Wetlands | ** Support | |
| East Valley Indivisibles | ** Support | |
| Edison International And Affiliates, Including Southern California Edison | ** Against | |
| Elders Climate Action, Northern California Chapter | ** Support | |
| Elders Climate Action, Southern California Chapter | ** Support | |
| Environmental Protection Information Center | ** Support | |
| Environmental Working Group | ** Support | |
| Environment CA | ** Support | |
| Environment California | ** Support | |
| Episcopal Diocese of Northern California | ** Support | |
| Extinction Rebellion San Francisco Bay Area | ** Support | |
| Feminists In Action | ** Support | |
| Fridays for Future Orange County | ** Support | |
| Friends Committee On Legislation Of California | ** Support | |
| Glendale Environmental Coalition | ** Support | |
| Habitable Designs | ** Support | |
| Hammond Climate Solutions | ** Support | |
| Hammond Climate Solutions Foundation | ** Support | |
| Hang Out Do Good | ** Support | |
| Hillcrest Indivisible | ** Support | |
| Independent Energy Producers Association | ** Against | |
| Indian Valley Indivisibles | ** Support | |
| Indivisible 36 | ** Support | |
| Indivisible 41 | ** Support | |
| Indivisible 43 | ** Support | |
| Indivisible Alta Pasadena | ** Support | |
| Indivisible Auburn Ca | ** Support | |
| Indivisible Beach Cities | ** Support | |
| Indivisible Ca-25 Simi Valley Porter Ranch | ** Support | |
| Indivisible CA 45 | ** Support | |
| Indivisible California Green Team | ** Support | |
| Indivisible Claremont / Inland Valley | ** Support | |
| Indivisible Colusa County | ** Support | |
| Indivisible East Bay | ** Support | |
| Indivisible El Dorado Hills | ** Support | |
| Indivisible Elmwood | ** Support | |
| Indivisible Euclid | ** Support | |
| Indivisible Manteca | ** Support | |
| Indivisible Marin | ** Support | |
| Indivisible Media City Burbank | ** Support | |
| Indivisible Mendocino | ** Support | |
| Indivisible Normal Heights | ** Support | |
| Indivisible OC 46 | ** Support | |
| Indivisible OC 48 | ** Support | |
| Indivisible Petaluma | ** Support | |
| Indivisible Resistance San Diego | ** Support | |
| Indivisible Resisters Walnut Creek | ** Support | |
| Indivisible Ross Valley | ** Support | |
| Indivisible Sacramento | ** Support | |
| Indivisible San Diego Central | ** Support | |
| Indivisible San Jose | ** Support | |
| Indivisible San Pedro | ** Support | |
| Indivisible Santa Barbara | ** Support | |
| Indivisible Santa Cruz County | ** Support | |
| Indivisible Sausalito | ** Support | |
| Indivisible Sebastopol | ** Support | |
| Indivisible Sf | ** Support | |
| Indivisible Sf Peninsula And Ca-14 | ** Support | |
| Indivisible Sonoma County | ** Support | |
| Indivisible South Bay LA | ** Support | |
| Indivisible Stanislaus | ** Support | |
| indivisible ventura | ** Support | |
| Indivisible Westside L.a. | ** Support | |
| Indivisible Yolo | ** Support | |
| Livermore Indivisible | ** Support | |
| Local Clean Energy Alliance | ** Support | |
| Long Beach Alliance for Clean Energy | ** Support | |
| Long Beach Environmental Alliance | ** Support | |
| Los Angeles Indivisible | ** Support | |
| Lutheran Office Of Public Policy - California | ** Support | |
| mill valley community action network | ** Support | |
| North County Climate Change Alliance | ** Support | |
| Orchard City Indivisible | ** Support | |
| our revolution, long beach | ** Support | |
| Pacific Gas And Electric Company | ** Against | |
| People Power Solar Cooperative | ** Support | |
| Progressive Democrats of America, California | ** Support | |
| Progressive Democrats Of Santa Monica Mountains | ** Support | |
| Progressive Zionists of California | ** Support | |
| recolte energy | ** Support | |
| Rooted in Resistance | ** Support | |
| Samuel Lawrence Foundation | ** Support | |
| San Diego Gas and Electric Company | ** Against | |
| San Joaquin Valley Democratic Club | ** Support | |
| San Jose Community Energy Advocates | ** Support | |
| San Luis Obispo Mothers for Peace | ** Support | |
| Santa Barbara; City of | ** Support | |
| Santa Cruz Climate Action Network | ** Support | |
| Santa Monica Democratic Club | ** Support | |
| SFV Indivisible | ** Support | |
| Silicon Valley Youth Climate Action | ** Support | |
| Socal 350 | ** Support | |
| SoCal 350 Climate Action | ** Support | |
| Solar United Neighbors | ** Support | |
| Sonoma County Democratic Party | ** Support | |
| Sunflower Alliance | ** Support | |
| Sunnova Energy Corporation | ** Support | |
| Sunrise Movement Orange County | ** Support | |
| Sustainable Systems Research Foundation | ** Support | |
| The Climate Alliance of Santa Cruz County | ** Support | |
| The Climate Center | ** Support | |
| The Climate Reality Project, Silicon Valley | ** Against | |
| The Resistance Northridge-indivisible | ** Support | |
| The Utility Reform Network | ** Against | |
| Together We Will Contra Costa | ** Support | |
| Tww/indivisible - Los Gatos | ** Support | |
| UC Santa Cruz Climate Coalition | ** Support | |
| USC Schwarzenegger Institute | ** Support | |
| Valley Women's Club of San Lorenzo Valley | ** Support | |
| Venice Resistance | ** Support | |
| Vote Solar | ** Support | |
| West LA Democratic Club | ** Support | |
| Women's Alliance Los Angeles | ** Support | |
| Women'S Energy Matters | ** Support | |
| Yalla Indivisible | ** Support |
Date of Hearing: May 15, 2024
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Buffy Wicks, Chair
ABPCA Bill Id:AB 2256
Author:(Friedman) – As Amended Ver:April 29, 2024
Policy Committee: | Utilities and Energy | Vote: | 14 - 0 |
|
| ||
|
|
Urgency: No State Mandated Local Program: No Reimbursable: No
SUMMARY:
This bill directs the California Public Utilities Commission (CPUC) to conduct an independent cost-of-service analysis evaluating the standard contract or tariff developed by the CPUC’s decision, “Decision Revising Net Energy Metering Tariff and Subtariffs,” issued December 15, 2022.
FISCAL EFFECT:
The CPUC indicates its staff is already engaged in a cost-of-service analysis of its net-energy metering (NEM) tariff, and that the analysis will satisfy the requirements of this bill. The CPUC reports it has dedicated $2 million to the analysis.
The CPUC has undertaken the cost-of-service analysis of its own volition. Presumably, the CPUC could stop the effort, it wanted to do so, in which case it would no longer incur the cost to conduct the analysis. Were this bill to become law, the CPUC would be obligated to undertake and complete the analysis, so this bill analysis attributes such costs to this bill.
COMMENTS:
- Purpose. The author intends this bill to require the CPUC to provide for what the author views as a full accounting of the benefits of rooftop solar. According to the author:
AB 2256 requires the California Public Utilities Commission (CPUC) to consider the total costs and benefits of rooftop solar, including “non-energy benefits” which are environmental or public health benefits of rooftop solar that accrue to society as a whole, including improved local air and water quality, and avoided land use impacts. The CPUC currently only considers some economic benefits of rooftop solar. As NEM is not simply a rate structure but rather, a far-reaching policy initiative with goals and outcomes that will shape the future of clean energy and climate change in California, it is critical for policy makers to consider all relevant information in re-designing the tariff that has proven integral to meet our climate goals.
- Background. Investor-owned utility (IOU) ratepayers have long subsidized the cost of customer-sited electricity generation from renewable resources, which has overwhelmingly meant electricity generated by rooftop solar. One of the primary forms of subsidy has been the availability of NEM tariffs, which state law requires each electrical IOU to offer to any customer with rooftop solar (or other on-site renewable generating facility). Under the tariff, such a customer is to be compensated by the IOU for the electricity the customer exports to the electric grid in excess the electricity of the customer draws from the grid.
The NEM tariff has undergone several iterations. Under the original NEM tariff, often referred to as NEM 1.0, a participating customer received a credit on their monthly utility bill for generation not consumed onsite, equal to the retail electricity rate in effect at the time of generation. The customer could use such credits to offset most of the customer’s electric bill, including fixed charges and transmission and generation charges.
The tariff was not meant to be cost-effective. Rather, the NEM tariff, and the larger state program, was meant to encourage adoption of rooftop solar so that manufacturing and installation costs could come down. And the program achieved its goal: rooftop solar installation grew considerably from 2006 through 2012.
The Legislature passed AB 327 (Perea), Chapter 611, Statutes of 2013, which directed the CPUC to make a number of reforms to the NEM tariff. Principal among the reforms was the requirement the CPUC base the NEM tariff on electrical system costs and benefits to nonparticipating ratepayers. In response, the CPUC, in January 2016, issued a decision (Decision 16-01-044) to require a customer on the NEM tariff to: (a) pay one-time interconnection fee to cover the costs of interconnection to the electric grid; (b) pay monthly nonbypassable charges that support “public-purpose programs,” such as low-income rate subsidies; and (c) be on a time-of-use (TOU) rate schedule, so that the customer is compensated for the electricity the customer exports to the grid in an amount equal to the retail price of electricity when the electricity is generated. In 2016, the CPUC issued a revised NEM tariff, known as NEM 2.0, which decreased the value of the NEM tariff substantially.
Nonetheless, installation of rooftop solar continued to grow, considerably.
Critics of past NEM subsidy amounts assert the cost of the subsidy to ratepayers who do not have rooftop solar exceeds the benefits those ratepayers receive from the existence of NEM-subsidized rooftop solar. In addition, many note that ratepayers who install rooftop solar and enjoy the NEM-subsidized rates tend to be more affluent than ratepayers in general. Several independent studies have substantiated these claims.
Representatives of the rooftop solar industry and its supporters object, contending the CPUC-commissioned studies are based on faulty assumptions and fail to adequately consider the values provided by rooftop solar installation, such as avoided transmission costs, resiliency and avoided land use.
In 2019, the CPUC ordered testing of a societal cost test in the Integrated Resource Planning proceeding to evaluate the potential effects of societal costs on procurement of both supply-side energy resources and demand-side energy resources. The evaluation found the addition of the societal cost test results in “minimal changes to the supply-side portfolio,” and minimal changes to the cost-effectiveness of distributed energy resources, such as rooftop solar.
The CPUC again revised the NEM tariff in December 15, 2022. This revision, known as NEM 3.0, again reduced the value of the NEM tariff and incentivized installation of rooftop solar paired with on-site energy storage.
Analysis Prepared by: Jay Dickenson / APPR. / (916) 319-2081
Date of Hearing: April 24, 2024
ASSEMBLY COMMITTEE ON UTILITIES AND ENERGY
Cottie Petrie-Norris, Chair
ABPCA Bill Id:AB 2256 (
Author:Friedman) – As Amended Ver:April 1, 2024
SUBJECT: Net energy metering
SUMMARY: Requires the California Public Utilities Commission (CPUC) to revise, as appropriate, the net energy metering (NEM) tariff, to include – among other considerations – ensuring the tariff is based on the cost of service analysis and the total benefits, including nonenergy benefits (as defined), of the NEM facility. Explicitly states the CPUC is not required to ensure nonparticipating ratepayer indifference in implementing this bill.
EXISTING LAW:
- Requires every electric utility, defined to include electrical corporations, local publicly owned electric utilities, and electrical cooperatives, to develop a standard contract or tariff for NEM, for generation by a renewable electrical generation facility, and to make this contract or tariff available to eligible customer-generators, upon request on a first-come-first-served basis until the time that the total rated generating capacity used by eligible customer generators exceeds five percent of the electric utility’s aggregate customer peak demand. (Public Utilities Code § 2827)
- Requires the CPUC, for a large electrical corporation, as defined, to have developed a second standard contract or tariff to provide NEM to additional eligible customer-generators in the electrical corporation’s service territory and imposes no limitation on the number of new eligible customer-generators entitled to receive service pursuant to this second standard contract or tariff. (Public Utilities Code § 2827.1)
- Requires the CPUC to ensure that the second standard contract or tariff made available to eligible customer-generators by large electrical corporations ensures that customer-sited renewable distributed generation continues to grow sustainably. Requires the CPUC, in developing this standard contract or tariff, to include specific alternatives designed for growth among residential customers in disadvantaged communities. (Public Utilities Code § 2827.1(b)(1))
- Establishes the policy that all of the state's retail electricity be supplied with a mix of RPS-eligible and zero-carbon resources by December 31, 2045, and 100% of electricity procured to serve all state agencies by December 31, 2035, for a total of 100% clean energy. Requires the California Public Utilities Commission (CPUC), in consultation with the California Energy Commission (CEC), California Air Resources Board (CARB), and all California balancing authorities, to issue a joint report to the Legislature by January 1, 2021, reviewing and evaluating the 100% clean energy policy. (Public Utilities Code § 454.53)
FISCAL EFFECT: Unknown. This bill is keyed fiscal and will be referred to the Committee on Appropriations for its review.
BACKGROUND:
Net Energy Metering (NEM) – California’s NEM program started in 1997, prompted by SB 656 (Alquist, Chapter 369, Statutes of 1995). It allows customers who install eligible renewable electrical generation facilities to serve onsite energy needs and receive credits on their electric bills for surplus energy sent to the electric grid. Most customer-sited, grid-connected solar in California is interconnected through NEM tariffs. Enrollment in the first NEM program, now colloquially known as “NEM 1.0”, continued and was phased out between 2016 and 2017.
The Legislature called for the revision of NEM 1.0 per AB 327 (Perea, Chapter 611, Statutes of 2013) primarily to address the cost associated with the full retail credits available under the tariff. The CPUC responded with what is commonly referred to as NEM 2.0 in 2016. Customers taking service under that tariff – NEM 2.0 – pay the cost to connect to the grid; take service on a “time-of-use” rate plan; and pay “non-bypassable” charges that are not offset with surplus energy credits. On August 27, 2020, the CPUC initiated Rulemaking 20-08-020 to develop a successor to the NEM 2.0 tariff, as part of the requirement in statute and a commitment in a previous decision to review the current tariff to address the shift in costs to nonparticipating customers. The CPUC released a proposed decision in December 2021.[1] However, the final decision was delayed while the CPUC considered party comments and evaluated alternatives. On December 15, 2022 the CPUC adopted a new decision establishing the NBT, or colloquially NEM 3.0.[2]
The NBT applied to customers who submit an interconnection application on or after April 15, 2023. The NBT made a number of changes from NEM 2.0, replacing export compensation tied to the retail rate with the avoided cost calculator, and financially incentivizing customers to install battery storage paired with their solar. Moreover, the NBT decision did not affect existing rooftop solar customers; those legacy NEM 1.0 and NEM 2.0 customers remain on their tariff. The NBT decision also did not include any charges unique to solar customers (despite early draft decisions doing that). The result of these changes led to a drop in the compensation rooftop solar customers will receive, increasing the payback period to 9 years.[3]
According to the CPUC, as of 2021, the NEM program had enabled 1.3 million customer installations, equating to roughly 10 gigawatts (GWs) of customer-sited renewable generation, almost all of which is rooftop solar. Now, NEM systems reduce the demand on the electric grid by as much as 25% during midday when the sun is shining.[4]
COMMENTS:
- Author’s Statement. According to the author, “AB 2256 requires the California Public Utilities Commission (CPUC) to consider the total costs and benefits of rooftop solar, including “non-energy benefits” which are environmental or public health benefits of rooftop solar that accrue to society as a whole, including improved local air and water quality, and avoided land use impacts. The CPUC currently only considers some economic benefits of rooftop solar. As NEM is not simply a rate structure but rather, a far-reaching policy initiative with goals and outcomes that will shape the future of clean energy and climate change in California, it is critical for policy makers to consider all relevant information in re-designing the tariff that has proven integral to meet our climate goals.”
- The Cost Shift. The controversy associated with NEM is that the customers with NEM (most of whom have roof-top solar) are subsidized by customers without NEM (i.e. “non-participants”). Extensive study has occurred for several years describing and categorizing the cost shift. According to a recent report by the Public Advocates Office (PAO), the annual cost of NEM on non-participants has approximately doubled since 2021, resulting in an estimated $6.5 billion for the program in 2024 alone.[5] For reference, PAO notes the cost of NEM was approximately $3.4 billion in 2021.
The CPUC in its annual utility cost report has noted “three critical and overlapping policy fronts must be actively managed to address the risk of high electric rates.” These include ballooning wildfire expenses, the need to ensure low-income customers benefit from electrification, and the need to mitigate cost shifts from DER incentives.[6]
Supporters of this bill, however, note the “so-called ‘cost-shift’ is a utility fabrication.”[7] They raise issue with the use of retail energy rates in the calculations used by PAO and others to quantify the cost shift. Instead, they point to “cost of service” as a better metric by which to judge NEM. A cost of service analysis compares an estimate of the utility cost of servicing a customer with an estimate of the customer’s bill. The cost of servicing a customer is based on the customer’s use of the grid and an allocation of the fixed costs of service. Unlike the CPUC’s cost-effectiveness tests, which evaluate both the cost-effectiveness to NEM-participants and non-participating ratepayers, the cost of service analysis focuses exclusively on the benefits to the NEM customer.
A 2021 analysis commissioned by the CPUC examined NEM cost shifts through the cost of service metric. [8] The study notes, “Comparing estimates of bills and cost of service prior to the installation of NEM-eligible technologies to the post-installation values, however, will provide evidence of whether the installation of NEM-eligible technologies is causing cost shifts.”[9] The study noted that “residential NEM customers’ aggregate utility bills were substantially less than their cost of service,”[10] finding that prior to NEM 2.0 installation, customers paid approximately $200 million more in their utility bills than the estimated cost for the utility to provide them service; after installing their NEM systems, residential customers paid $500 million less in their utility bills than the utility’s cost to serve them.[11] This $500 million deficit results in non-participating ratepayers seeing increased rates; i.e. a cost shift.[12]
While the cost shift measured via a cost of service metric is significant, it is two orders of magnitude less than that measured by the cost-effectiveness test. The same 2021 analysis found that “the NEM 2.0 tariff is cost-effective to participants. However, NEM 2.0 projects are not cost-effective from the perspective of ratepayers and result in a cost shift of more than $12 billion from program participants to non-participants.”[13] It is this distinction in how to value the system, and from whose perspective to evaluate that value, that has driven much of the controversy around NEM policy.
- Nonenergy Benefits. This bill seeks to examine the cost shift calculation even further by requiring the CPUC, as appropriate, to revise the NEM tariff to not only a cost of service basis but also the total benefits, including “quantifiable” nonenergy benefits of the solar system. The bill then defines nonenergy benefits as metrics that may be difficult to quantify. For example, some land-use benefits are listed, including improved water quality and quantity, and the protection or preservation of open-space resources and wildlife habitats. It is unclear whether there is an agreed upon standard or valuation for these nonenergy benefits upon which the CPUC could draw, or if the bill seeks the CPUC to develop the monetary amounts for each. The latter could be highly ambiguous and variable.
In 2019, the CPUC ordered the testing of a Societal Cost Test (SCT) in the Integrated Resource Planning (IRP) proceeding.[14] The testing of an SCT was assigned to the IRP model so that the impact of societal costs on both supply and demand side resource procurement could be considered. An SCT is one of the five cost tests envisioned in the California Standard Practice Manual and used for evaluating DER. The IRP scenario incorporated the central estimates for all societal cost components, including the social cost of carbon, air quality impacts, methane leakage, and a social discount rate. The evaluation found the addition of the SCT results in “minimal changes to the supply-side portfolio,” and minimal changes to the cost-effectiveness of DERs.[15] In other words, when the SCT was applied across all resource types, DERs were not selected.
In their March 13, 2024, Business Meeting, the CEC opened an order instituting informational proceedings to serve as a forum to discuss nonenergy benefits. They also held a joint agency workshop on Tuesday, April 16, 2024, to discuss the approach and implications of examining nonenergy benefits for resource selection in the SB 100 Report.[16] It is unclear to the committee at this time which metrics are included in the nonenergy benefit evaluation at the CEC versus those listed in this measure versus those included in the SCT.
These efforts highlight the challenge in evaluating the cost-effectiveness or societal benefits of a particular resource. Certainly, the absence of adequate accounting of costs and benefits can distort energy planning; but so can the inclusion of too vague or too assumptive metrics. Moreover, if development of benefits tests occurs scattered across the various state agencies, different results could arise for the same resource, leading to further confusion, disagreement, or venue shopping.
- Need for Amendments. This bill seeks an assessment of the full suite of DER benefits, including societal benefits as specified. Such an evaluation aligns with past and current work at state energy agencies, and recognizes that DERs can provide benefits beyond electricity generation, including their speed to get online, load modifications, and potential reduction in needed infrastructure or land use conflicts. However, there does not appear to be agreement on which benefits should apply nor their value. As such, it would be premature to prescribe changes to a tariff with undefined criteria. Therefore, the committee recommends striking the provisions of this bill revising the NEM tariff, and instead amending this bill to require the CPUC to conduct an independent cost of service analysis of the recent NEM 3.0 tariff. In this way, supporters of NEM policy may have an accounting of the benefits the NEM 3.0 tariff provides to participants – similar to what was conducted for NEM 2.0. Such an evaluation will be especially telling given the changes to financing that have occurred since the new tariff came online; namely, higher interest rates and higher IOU electric rates.
- Related Legislation.
AB 2619 (Connolly) requires the CPUC to develop, by 2027, a new solar tariff to replace the current net billing tariff. Requires that the new tariff be structured to ensure achievement of an annual rate of rooftop solar installation sufficient to meet anticipated needs described in the Joint SB 100 Report. Reverts all NBT customer-generators to the prior net energy metering (NEM) tariff, until the new tariff is available in 2027. Status: set for hearing in this committee on April 17, 2024.
- Prior Legislation.
AB 1139 (Lorena Gonzalez) directed the CPUC to adopt a new NEM standard contract or tariff, which the bill defines as the "replacement tariff," by August 1, 2022, and requires an electrical IOU to offer the replacement tariff to an eligible customer-generator by December 31, 2023. If the CPUC fails to act, the CPUC is required to adopt a new tariff under terms prescribed by this bill. Status: Died – Assembly Inactive file.
AB 327 (Perea) instituted several rate reforms and required the CPUC to adopt a successor NEM tariff no later than December 31, 2015. Status: Chapter 611, Statutes of 2013
REGISTERED SUPPORT / OPPOSITION:
Support
350 Bay Area Action
350 Conejo
350 Conejo / San Fernando Valley
350 Humboldt
350 South Bay Los Angeles
350 Southland Legislative Alliance
350 Ventura County Climate Hub
Acterra: Action for A Healthy Planet
Active San Gabriel Valley
Adopt a Charger
Advanced Energy Economy
Alliance of Nurses for Healthy Environments
American Solar Energy Society
Ballona Institute
Ban Sup (single Use Plastic)
California Alliance for Community Energy
California Center for Sustainable Energy
California Climate Voters
California Interfaith Power and Light
California Solar & Storage Association
Californians for Energy Choice
Californians for Western Wilderness
CalPIRG
CalPIRG Students
Catholic Charities, Diocese of Stockton
Center for Biological Diversity
Center for Biological Diversity, INC.
Center for Community Energy
Center for Progressive Reform
Change Begins With Me (INDIVISIBLE)
Clean Coalition
Clean Earth 4 Kids
Cleanearth4kids.org
Climate Hawks Vote
Cloverdale Indivisible
Coastal Lands Action Network (CLAN)
Consejo De Federaciones Mexicanas (COFEM)
Contra Costa Moveon
Courageous Resistance of The Desert
Culver City Democratic Club
Custom Power Solar
Defend Ballona Wetlands
East Valley Indivisibles
Elders Climate Action Northern California Chapter
Elders Climate Action Southern California Chapter
Environment CA
Environment California
Environmental Protection Information Center
Environmental Working Group
Episcopal Diocese of Northern California
Extinction Rebellion San Francisco Bay Area
Feminists in Action (formerly Indivisible CA 34 Womens)
Fridays for Future Orange County
Friends Committee on Legislation of California
Glendale Environmental Coalition
Habitable Designs
Hammond Climate Solutions
Hammond Climate Solutions Foundation
Hang Out Do Good
Hillcrest Indivisible
Indian Valley Indivisibles
Indivisible 36
Indivisible 41
Indivisible 43
Indivisible Alta Pasadena
Indivisible Auburn CA
Indivisible Beach Cities
Indivisible CA 45
Indivisible Ca-25 Simi Valley Porter Ranch
Indivisible California Green Team
Indivisible Claremont / Inland Valley
Indivisible Colusa County
Indivisible East Bay
Indivisible El Dorado Hills
Indivisible Elmwood
Indivisible Euclid
Indivisible Manteca
Indivisible Marin
Indivisible Media City Burbank
Indivisible Mendocino
Indivisible Normal Heights
Indivisible Oc 46
Indivisible Oc 48
Indivisible Petaluma
Indivisible Resistance San Diego
Indivisible Resisters Walnut Creek
Indivisible Ross Valley
Indivisible Sacramento
Indivisible San Diego Central
Indivisible San Jose
Indivisible San Pedro
Indivisible Santa Barbara
Indivisible Santa Cruz County
Indivisible Sausalito
Indivisible Sebastopol
Indivisible Sf
Indivisible Sf Peninsula and Ca-14
Indivisible Sonoma County
Indivisible South Bay LA
Indivisible Stanislaus
Indivisible Ventura
Indivisible Westside L.A.
Indivisible Yolo
Livermore Indivisible
Local Clean Energy Alliance
Long Beach Alliance for Clean Energy
Long Beach Environmental Alliance
Los Angeles Indivisible
Lutheran Office of Public Policy - California
Mill Valley Community Action Network
North County Climate Change Alliance
Orchard City Indivisible
Our Revolution Long Beach
People Power Solar Cooperative
Progressive Democrats of America, California
Progressive Democrats of Santa Monica Mountains
Progressive Zionists of California
Recolte Energy
Rooted in Resistance
Samuel Lawrence Foundation
San Joaquin Valley Democratic Club
San Jose Community Energy Advocates
San Luis Obispo Mothers for Peace
Santa Barbara; City of
Santa Cruz Climate Action Network
Santa Monica Democratic Club
Sfv Indivisible
Silicon Valley Youth Climate Action
Socal 350
Socal 350 Climate Action
Solar United Neighbors
Sonoma County Democratic Party
Sunflower Alliance
Sunnova Energy Corporation
Sunrise Movement Orange County
Sustainable Systems Research Foundation
The Climate Alliance of Santa Cruz County
The Climate Center
The Resistance Northridge-indivisible
Together We Will Contra Costa
Tww/indivisible - Los Gatos
UC Santa Cruz Climate Coalition
Usc Schwarzenegger Institute
Valley Women's Club of San Lorenzo Valley
Venice Resistance
Vote Solar
West LA Democratic Club
Womeen's Energy Matters
Women's Alliance Los Angeles
Yalla Indivisible
Oppose
California State Association of Electrical Workers
California Wind Energy Association
Coalition of California Utility Employees
Edison International and Affiliates, Including Southern California Edison
Independent Energy Producers Association
Pacific Gas and Electric Company
San Diego Gas and Electric Company
The Climate Reality Project: Silicon Valley
The Utility Reform Network (TURN)
Analysis Prepared by: Laura Shybut / U. & E. / (916) 319-2083
See Decision Revising Net Energy Metering and Subtariffs, CPUC, December 13, 2021, at: https://docs.cpuc.ca.gov/PublishedDocs/Efile/G000/M430/K903/430903088.PDF ↑
D. 22-12-056 ↑
CPUC, “Fact Sheet: Modernizing NEM to Meet California’s Reliability and Climate Goals;” November 10, 2022. https://www.cpuc.ca.gov/-/media/cpuc-website/divisions/energy-division/documents/net-energy-metering-nem/nemrevisit/final-fact-sheet-nem.pdf ↑
CPUC Fact Sheet; “Modernizing California’s Net Energy Metering Program to Meet our Clean Energy Goals.” December 13, 2021. ↑
CalPAO, “Rooftop solar incentive to cost customers without solar an estimated $6.5 billion in 2024.” February 28, 2024. ↑
Pg. 17, CPUC, 2022 Senate Bill 695 Report, May 2022. https://www.cpuc.ca.gov/-/media/cpuc-website/divisions/office-of-governmental-affairs-division/reports/2022/2022-sb-695-report.pdf ↑
Coalition support letter, April 9th, 2024. ↑
Verdant, NEM 2.0 Lookback Study; July 21, 2021. https://www.cpuc.ca.gov/-/media/cpuc-website/divisions/energy-division/documents/net-energy-metering-nem/nem-evaluation/nem-2_lookback_study.pdf ↑
Pg. 95, Verdant, NEM 2.0 Lookback Study; July 21, 2021. https://www.cpuc.ca.gov/-/media/cpuc-website/divisions/energy-division/documents/net-energy-metering-nem/nem-evaluation/nem-2_lookback_study.pdf ↑
Ibid. ↑
Marin, William; Shelton, Jean; Rufo, Mike; and Robinson, Lauren; Verdant Associates; “Are California’s Net Metering Tariffs Fair, and How Can We Avoid a Cost-Shift?” 2022 International Energy Program Evaluation Conference, San Diego, CA. https://verdantassoc.com/wp-content/uploads/IEPEC-2022_NEM-Cost-Shift.pdf ↑
Pg. 1, Ibid. ↑
Marin, et al., pg. 1; Ibid. ↑
D. 19-05-019 ↑
Pg. 5, CPUC, “Societal Cost Test Impact Evaluation,” January 2022. ↑
https://www.energy.ca.gov/event/workshop/2024-04/2025-senate-bill-100-report-non-energy-benefits-workshop ↑
Date of Hearing: April 17, 2024
ASSEMBLY COMMITTEE ON UTILITIES AND ENERGY
Cottie Petrie-Norris, Chair
ABPCA Bill Id:AB 2256 (
Author:Friedman) – As Amended Ver:April 1, 2024
SUBJECT: Net energy metering
SUMMARY: Requires the California Public Utilities Commission (CPUC) to revise, as appropriate, the net energy metering (NEM) tariff, to include – among other considerations – ensuring the tariff is based on the cost of service analysis and the total benefits, including nonenergy benefits (as defined), of the NEM facility. Explicitly states the CPUC is not required to ensure nonparticipating ratepayer indifference in implementing this bill.
EXISTING LAW:
- Requires every electric utility, defined to include electrical corporations, local publicly owned electric utilities, and electrical cooperatives, to develop a standard contract or tariff for NEM, for generation by a renewable electrical generation facility, and to make this contract or tariff available to eligible customer-generators, upon request on a first-come-first-served basis until the time that the total rated generating capacity used by eligible customer generators exceeds five percent of the electric utility’s aggregate customer peak demand. (Public Utilities Code § 2827)
- Requires the CPUC, for a large electrical corporation, as defined, to have developed a second standard contract or tariff to provide NEM to additional eligible customer-generators in the electrical corporation’s service territory and imposes no limitation on the number of new eligible customer-generators entitled to receive service pursuant to this second standard contract or tariff. (Public Utilities Code § 2827.1)
- Requires the CPUC to ensure that the second standard contract or tariff made available to eligible customer-generators by large electrical corporations ensures that customer-sited renewable distributed generation continues to grow sustainably. Requires the CPUC, in developing this standard contract or tariff, to include specific alternatives designed for growth among residential customers in disadvantaged communities. (Public Utilities Code § 2827.1(b)(1))
- Establishes the policy that all of the state's retail electricity be supplied with a mix of RPS-eligible and zero-carbon resources by December 31, 2045, and 100% of electricity procured to serve all state agencies by December 31, 2035, for a total of 100% clean energy. Requires the California Public Utilities Commission (CPUC), in consultation with the California Energy Commission (CEC), California Air Resources Board (CARB), and all California balancing authorities, to issue a joint report to the Legislature by January 1, 2021, reviewing and evaluating the 100% clean energy policy. (Public Utilities Code § 454.53)
FISCAL EFFECT: Unknown. This bill is keyed fiscal and will be referred to the Committee on Appropriations for its review.
BACKGROUND:
Net Energy Metering (NEM) – California’s NEM program started in 1997, prompted by SB 656 (Alquist, Chapter 369, Statutes of 1995). It allows customers who install eligible renewable electrical generation facilities to serve onsite energy needs and receive credits on their electric bills for surplus energy sent to the electric grid. Most customer-sited, grid-connected solar in California is interconnected through NEM tariffs. Enrollment in the first NEM program, now colloquially known as “NEM 1.0”, continued and was phased out between 2016 and 2017.
The Legislature called for the revision of NEM 1.0 per AB 327 (Perea, Chapter 611, Statutes of 2013) primarily to address the cost associated with the full retail credits available under the tariff. The CPUC responded with what is commonly referred to as NEM 2.0 in 2016. Customers taking service under that tariff – NEM 2.0 – pay the cost to connect to the grid; take service on a “time-of-use” rate plan; and pay “non-bypassable” charges that are not offset with surplus energy credits. On August 27, 2020, the CPUC initiated Rulemaking 20-08-020 to develop a successor to the NEM 2.0 tariff, as part of the requirement in statute and a commitment in a previous decision to review the current tariff to address the shift in costs to nonparticipating customers. The CPUC released a proposed decision in December 2021.[1] However, the final decision was delayed while the CPUC considered party comments and evaluated alternatives. On December 15, 2022 the CPUC adopted a new decision establishing the NBT, or colloquially NEM 3.0.[2]
The NBT applied to customers who submit an interconnection application on or after April 15, 2023. The NBT made a number of changes from NEM 2.0, replacing export compensation tied to the retail rate with the avoided cost calculator, and financially incentivizing customers to install battery storage paired with their solar. Moreover, the NBT decision did not affect existing rooftop solar customers; those legacy NEM 1.0 and NEM 2.0 customers remain on their tariff. The NBT decision also did not include any charges unique to solar customers (despite early draft decisions doing that). The result of these changes led to a drop in the compensation rooftop solar customers will receive, increasing the payback period to 9 years.[3]
According to the CPUC, as of 2021, the NEM program had enabled 1.3 million customer installations, equating to roughly 10 gigawatts (GWs) of customer-sited renewable generation, almost all of which is rooftop solar. Now, NEM systems reduce the demand on the electric grid by as much as 25% during midday when the sun is shining.[4]
COMMENTS:
- Author’s Statement. According to the author, “AB 2256 requires the California Public Utilities Commission (CPUC) to consider the total costs and benefits of rooftop solar, including “non-energy benefits” which are environmental or public health benefits of rooftop solar that accrue to society as a whole, including improved local air and water quality, and avoided land use impacts. The CPUC currently only considers some economic benefits of rooftop solar. As NEM is not simply a rate structure but rather, a far-reaching policy initiative with goals and outcomes that will shape the future of clean energy and climate change in California, it is critical for policy makers to consider all relevant information in re-designing the tariff that has proven integral to meet our climate goals.”
- The Cost Shift. The controversy associated with NEM is that the customers with NEM (most of whom have roof-top solar) are subsidized by customers without NEM (i.e. “non-participants”). Extensive study has occurred for several years describing and categorizing the cost shift. According to a recent report by the Public Advocates Office (PAO), the annual cost of NEM on non-participants has approximately doubled since 2021, resulting in an estimated $6.5 billion for the program in 2024 alone.[5] For reference, PAO notes the cost of NEM was approximately $3.4 billion in 2021.
The CPUC in its annual utility cost report has noted “three critical and overlapping policy fronts must be actively managed to address the risk of high electric rates.” These include ballooning wildfire expenses, the need to ensure low-income customers benefit from electrification, and the need to mitigate cost shifts from DER incentives.[6]
Supporters of this bill, however, note the “so-called ‘cost-shift’ is a utility fabrication.” They raise issue with the use of retail energy rates in the calculations used by PAO and others to quantify the cost shift. Instead, they point to “cost of service” as a better metric. A 2021 analysis commissioned by the CPUC examined NEM cost shifts through the cost of service metric. [7] The study notes, “Comparing estimates of bills and cost of service prior to the installation of NEM-eligible technologies to the post-installation values, however, will provide evidence of whether the installation of NEM-eligible technologies is causing cost shifts.”[8] The study found that “residential NEM customers’ aggregate utility bills were substantially less than their cost of service,”[9] resulting in non-participating ratepayers seeing increased rates.[10]
- Nonenergy Benefits. This bill seeks to examine the cost shift calculation even further by requiring the CPUC, as appropriate, to revise the NEM tariff to not only a cost of service basis but also the total benefits, including “quantifiable” nonenergy benefits of the solar system. The bill then defines nonenergy benefits as metrics that may be difficult to quantify. For example, some land-use benefits are listed, including improved water quality and quantity, and the protection or preservation of open-space resources and wildlife habitats. It is unclear whether there is an agreed upon standard or valuation for these nonenergy benefits upon which the CPUC could draw, or if the bill seeks the CPUC to develop the monetary amounts for each. The latter could be highly ambiguous and variable.
In 2019, the CPUC ordered the testing of a Societal Cost Test (SCT) in the Integrated Resource Planning (IRP) proceeding.[11] The testing of an SCT was assigned to the IRP model so that the impact of societal costs on both supply and demand side resource procurement could be considered. An SCT is one of the five cost tests envisioned in the California Standard Practice Manual and used for evaluating DER. The IRP scenario incorporated the central estimates for all societal cost components, including the social cost of carbon, air quality impacts, methane leakage, and a social discount rate. The evaluation found the addition of the SCT results in “minimal changes to the supply-side portfolio,” and minimal changes to the cost-effectiveness of DERs.[12] In other words, when the SCT was applied across all resource types, DERs were not selected.
In their March 13, 2024, Business Meeting, the CEC opened an order instituting informational proceeding to serve as a forum to discuss nonenergy benefits. They also held a joint agency workshop on Tuesday, April 16, 2024, to discuss the approach and implications of examining nonenergy benefits for resource selection in the SB 100 Report.[13] It is unclear to committee at this time which metrics are included in the nonenergy benefit evaluation at the CEC versus those listed in this measure versus those included in the SCT.
These efforts highlight the challenge in evaluating the cost-effectiveness or societal benefits of a particular resource. Certainly, the absence of adequate accounting of costs and benefits can distort energy planning; but so can the inclusion of too vague or too assumptive metrics. Moreover, if development of benefits tests occur scattered across the various state agencies, different results could arise for the same resource, leading to further confusion, disagreement, or venue shopping.
- Need for Amendments. This bill seeks an assessment of the full suite of DER benefits, including societal benefits as specified. Such an evaluation aligns with past and current work at state energy agencies, and recognizes that DERs can provide benefit beyond electricity generation, including their speed to get online, load modifications, and potential reduction in needed infrastructure or land use conflicts. However there does not appear to be agreement on which benefits should apply nor their value. As such, it would be premature to prescribe changes to a tariff with undefined criteria. Therefore, the committee recommends amending this bill to require the CPUC to evaluate the impact of nonenergy benefits to both supply and demand side resources, by directing them to work collaboratively with the CEC in their development of nonenergy benefits for future system planning, to incorporate the results of that collaboration into IRP sensitivities and future SB 100 models, and then to evaluate how changes to the NEM tariff would impact both participating and non-participating customers.
- Related Legislation.
AB 2619 (Connolly) requires the CPUC to develop, by 2027, a new solar tariff to replace the current net billing tariff. Requires that the new tariff be structured to ensure achievement of an annual rate of rooftop solar installation sufficient to meet anticipated need described in the Joint SB 100 Report. Reverts all NBT customer-generators to the prior net energy metering (NEM) tariff, until the new tariff is available in 2027. Status: set for hearing in this committee on April 17, 2024.
- Prior Legislation.
AB 1139 (Lorena Gonzalez) directed the CPUC to adopt a new NEM standard contract or tariff, which the bill defines as the "replacement tariff," by August 1, 2022, and requires an electrical IOU to offer the replacement tariff to an eligible customer-generator by December 31, 2023. If the CPUC fails to act, the CPUC is required to adopt a new tariff under terms prescribed by this bill. Status: Died – Assembly Inactive file.
AB 327 (Perea) instituted several rate reforms and required the CPUC to adopt a successor NEM tariff no later than December 31, 2015. Status: Chapter 611, Statutes of 2013
REGISTERED SUPPORT / OPPOSITION:
Support
350 Bay Area Action
350 Conejo
350 Conejo / San Fernando Valley
350 Humboldt
350 South Bay Los Angeles
350 Southland Legislative Alliance
350 Ventura County Climate Hub
Acterra: Action for A Healthy Planet
Active San Gabriel Valley
Adopt a Charger
Advanced Energy Economy
Alliance of Nurses for Healthy Environments
American Solar Energy Society
Ballona Institute
Ban Sup (single Use Plastic)
California Alliance for Community Energy
California Center for Sustainable Energy
California Climate Voters
California Interfaith Power and Light
California Solar & Storage Association
Californians for Energy Choice
Californians for Western Wilderness
Calpirg
Calpirg Students
Catholic Charities, Diocese of Stockton
Center for Biological Diversity
Center for Biological Diversity, INC.
Center for Community Energy
Center for Progressive Reform
Change Begins With Me (INDIVISIBLE)
Clean Coaliton
Clean Earth 4 Kids
Cleanearth4kids.org
Climate Hawks Vote
Cloverdale Indivisible
Coastal Lands Action Network (CLAN)
Consejo De Federaciones Mexicanas (COFEM)
Contra Costa Moveon
Courageous Resistance of The Desert
Culver City Democratic Club
Custom Power Solar
Defend Ballona Wetlands
East Valley Indivisibles
Elders Climate Action Northern California Chapter
Elders Climate Action Southern California Chapter
Environment CA
Environment California
Environmental Protection Information Center
Environmental Working Group
Episcopal Diocese of Northern California
Extinction Rebellion San Francisco Bay Area
Feminists in Action (formerly Indivisible CA 34 Womens)
Fridays for Future Orange County
Friends Committee on Legislation of California
Glendale Environmental Coaltion
Habitable Designs
Hammond Climate Solutions
Hammond Climate Solutions Foundation
Hang Out Do Good
Hillcrest Indivisible
Indian Valley Indivisibles
Indivisible 36
Indivisible 41
Indivisible 43
Indivisible Alta Pasadena
Indivisible Auburn CA
Indivisible Beach Cities
Indivisible CA 45
Indivisible Ca-25 Simi Valley Porter Ranch
Indivisible California Green Team
Indivisible Claremont / Inland Valley
Indivisible Colusa County
Indivisible East Bay
Indivisible El Dorado Hills
Indivisible Elmwood
Indivisible Euclid
Indivisible Manteca
Indivisible Marin
Indivisible Media City Burbank
Indivisible Mendocino
Indivisible Normal Heights
Indivisible Oc 46
Indivisible Oc 48
Indivisible Petaluma
Indivisible Resistance San Diego
Indivisible Resisters Walnut Creek
Indivisible Ross Valley
Indivisible Sacramento
Indivisible San Diego Central
Indivisible San Jose
Indivisible San Pedro
Indivisible Santa Barbara
Indivisible Santa Cruz County
Indivisible Sausalito
Indivisible Sebastopol
Indivisible Sf
Indivisible Sf Peninsula and Ca-14
Indivisible Sonoma County
Indivisible South Bay LA
Indivisible Stanislaus
Indivisible Ventura
Indivisible Westside L.a.
Indivisible Yolo
Livermore Indivisible
Local Clean Energy Alliance
Long Beach Alliance for Clean Energy
Long Beach Environmental Alliance
Los Angeles Indivisible
Lutheran Office of Public Policy - California
Mill Valley Community Action Network
North County Climate Change Alliance
Orchard City Indivisible
Our Revolution Long Beach
People Power Solar Cooperative
Progressive Democrats of America, California
Progressive Democrats of Santa Monica Mountains
Progressive Zionists of California
Recolte Energy
Rooted in Resistance
Samuel Lawrence Foundation
San Joaquin Valley Democratic Club
San Jose Community Energy Advocates
San Luis Obispo Mothers for Peace
Santa Barbara; City of
Santa Cruz Climate Action Network
Santa Monica Democratic Club
Sfv Indivisible
Silicon Valley Youth Climate Action
Socal 350
Socal 350 Climate Action
Solar United Neighbors
Sonoma County Democratic Party
Sunflower Alliance
Sunnova Energy Corporation
Sunrise Movement Orange County
Sustainable Systems Research Foundation
The Climate Alliance of Santa Cruz County
The Climate Center
The Resistance Northridge-indivisible
Together We Will Contra Costa
Tww/indivisible - Los Gatos
UC Santa Cruz Climate Coalition
Usc Schwarzenegger Institute
Valley Women's Club of San Lorenzo Valley
Venice Resistance
Vote Solar
West LA Democratic Club
Womeen's Energy Matters
Women's Alliance Los Angeles
Yalla Indivisible
Oppose
California State Association of Electrical Workers
California Wind Energy Association
Coalition of California Utility Employees
Edison International and Affiliates, Including Southern California Edison
Independent Energy Producers Association
Pacific Gas and Electric Company
San Diego Gas and Electric Company
The Climate Reality Project: Silicon Valley
The Utility Reform Network (TURN)
Analysis Prepared by: Laura Shybut / U. & E. / (916) 319-2083
See Decision Revising Net Energy Metering and Subtariffs, CPUC, December 13, 2021, at: https://docs.cpuc.ca.gov/PublishedDocs/Efile/G000/M430/K903/430903088.PDF ↑
D. 22-12-056 ↑
CPUC, “Fact Sheet: Modernizing NEM to Meet California’s Reliability and Climate Goals;” November 10, 2022. https://www.cpuc.ca.gov/-/media/cpuc-website/divisions/energy-division/documents/net-energy-metering-nem/nemrevisit/final-fact-sheet-nem.pdf ↑
CPUC Fact Sheet; “Modernizing California’s Net Energy Metering Program to Meet our Clean Energy Goals.” December 13, 2021. ↑
CalPAO, “Rooftop solar incentive to cost customers without solar an estimated $6.5 billion in 2024.” February 28, 2024. ↑
Pg. 17, CPUC, 2022 Senate Bill 695 Report, May 2022. https://www.cpuc.ca.gov/-/media/cpuc-website/divisions/office-of-governmental-affairs-division/reports/2022/2022-sb-695-report.pdf ↑
Verdant, NEM 2.0 Lookback Study; July 21, 2021. https://www.cpuc.ca.gov/-/media/cpuc-website/divisions/energy-division/documents/net-energy-metering-nem/nem-evaluation/nem-2_lookback_study.pdf ↑
Pg. 95, Verdant, NEM 2.0 Lookback Study; July 21, 2021. https://www.cpuc.ca.gov/-/media/cpuc-website/divisions/energy-division/documents/net-energy-metering-nem/nem-evaluation/nem-2_lookback_study.pdf ↑
Ibid. ↑
Pg. 1, Ibid. ↑
D. 19-05-019 ↑
Pg. 5, CPUC, “Societal Cost Test Impact Evaluation,” January 2022. ↑
https://www.energy.ca.gov/event/workshop/2024-04/2025-senate-bill-100-report-non-energy-benefits-workshop ↑
Discussed in Hearing
Assembly Standing Committee on Utilities and Energy
Bill Author
Bill Co-Author(s):