The Zberg-Nejedly Forest Practice Act of 1973 prohibits a person from conducting timber operations, as defined, unless a timber harvesting plan prepared by a registered professional forester has been submitted to, and approved by, the Department of Forestry and Fire Protection. The act authorizes the State Board of Forestry and Fire Protection to exempt from some or all of those provisions of the act a person engaging in specified forest management activities, as prescribed, including: (1), for a period of 5 years following the adoption of emergency regulations, the cutting or removal of trees on the persons property that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break, known as the Small Timberland Owner Exemption, (2), until January 1, 2026, the harvesting of those trees that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for specified purposes, known as the Forest Fire Prevention Exemption, (3), until January 1, 2026, the cutting or removal of trees on the persons property in compliance with specified defensible space requirements, as provided, and (4) the cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands.
This bill would (1) repeal the Small Timberland Owner Exemption, (2) rename the Forest Fire Prevention Exemption the Forest Resilience Exemption, revise the standards and criteria for qualifying for that exemption, and extend that exemption until January 1, 2031, and (3) extend until January 1, 2031, the other exemption described above. The bill would also revise requirements governing compliance with the cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands. The bill would require the board to adopt emergency regulations that the board considers necessary to implement and ensure compliance with these requirements and with the Forest Resilience Exemption requirements. The bill would also make conforming changes.
This bill would incorporate additional changes to Section 399.20.3 of the Public Utilities Code proposed by AB 2750 to be operative only if this bill and AB 2750 are enacted and this bill is enacted last.
The Zberg-Nejedly Forest Practice Act of 1973 prohibits a person from conducting timber operations, as defined, unless a timber harvesting plan prepared by a registered professional forester has been submitted to, and approved by, the Department of Forestry and Fire Protection. The act authorizes the State Board of Forestry and Fire Protection to exempt from some or all of those provisions of the act a person engaging in specified forest management activities, as prescribed, including: (1), for a period of 5 years following the adoption of emergency regulations, the cutting or removal of trees on the persons property that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break, known as the Small Timberland Owner Exemption, (2), until January 1, 2026, the harvesting of those trees that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for specified purposes, known as the Forest Fire Prevention Exemption, (3), until January 1, 2026, the cutting or removal of trees on the persons property in compliance with specified defensible space requirements, as provided, and (4) the cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands.
This bill would (1) repeal the Small Timberland Owner Exemption, (2) rename the Forest Fire Prevention Exemption the Forest Resilience Exemption, revise the standards and criteria for qualifying for that exemption, and extend that exemption until January 1, 2031, and (3) extend until January 1, 2031, the other exemption described above. The bill would also revise requirements governing compliance with the cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands. The bill would require the board to adopt emergency regulations that the board considers necessary to implement and ensure compliance with these requirements and with the Forest Resilience Exemption requirements. The bill would also make conforming changes.
This bill would incorporate additional changes to Section 399.20.3 of the Public Utilities Code proposed by AB 2750 to be operative only if this bill and AB 2750 are enacted and this bill is enacted last.
The Zberg-Nejedly Forest Practice Act of 1973 prohibits a person from conducting timber operations, as defined, unless a timber harvesting plan prepared by a registered professional forester has been submitted to, and approved by, the Department of Forestry and Fire Protection. The act authorizes the State Board of Forestry and Fire Protection to exempt from some or all of those provisions of the act a person engaging in specified forest management activities, as prescribed, including: (1), for a period of 5 years following the adoption of emergency regulations, the cutting or removal of trees on the persons property that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break, known as the Small Timberland Owner Exemption, (2), until January 1, 2026, the harvesting of those trees that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for specified purposes, known as the Forest Fire Prevention Exemption, (3), until January 1, 2026, the cutting or removal of trees on the persons property in compliance with specified defensible space requirements, as provided, and (4) the cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands.
This bill would (1) repeal the Small Timberland Owner Exemption, (2) rename the Forest Fire Prevention Exemption the Forest Resilience Exemption, revise the standards and criteria for qualifying for that exemption, extend that exemption until January 1, 2031, and (3) extend until January 1, 2031, the other exemption described above. The bill would also revise requirements governing compliance with cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands. The bill would require the board to adopt emergency regulations that the board considers necessary to implement and ensure compliance with these requirements and with the Forest Resilience Exemption requirements. The bill would also make conforming changes.
This bill would incorporate additional changes to Section 399.20.3 of the Public Utilities Code proposed by AB 2750 to be operative only if this bill and AB 2750 are enacted and this bill is enacted last.
The Zberg-Nejedly Forest Practice Act of 1973 prohibits a person from conducting timber operations, as defined, unless a timber harvesting plan prepared by a registered professional forester has been submitted to, and approved by, the Department of Forestry and Fire Protection. The act authorizes the State Board of Forestry and Fire Protection to exempt from some or all of those provisions of the act a person engaging in specified forest management activities, as prescribed, including: (1), for a period of 5 years following the adoption of emergency regulations, the cutting or removal of trees on the persons property that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break, known as the Small Timberland Owner Exemption, (2), until January 1, 2026, the harvesting of those trees that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for specified purposes, known as the Forest Fire Prevention Exemption, (3), until January 1, 2026, the cutting or removal of trees on the persons property in compliance with specified defensible space requirements, as provided, and (4) the cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands.
This bill would (1) repeal the Small Timberland Owner Exemption, (2) rename the Forest Fire Prevention Exemption the Forest Resilience Exemption, revise the standards and criteria for qualifying for that exemption, extend that exemption until January 1, 2031, and (3) extend until January 1, 2031, the other exemption described above. The bill would also revise requirements governing compliance with cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands. The bill would require the board to adopt emergency regulations that the board considers necessary to implement and ensure compliance with these requirements and with the Forest Resilience Exemption requirements. The bill would also make conforming changes.
The Zberg-Nejedly Forest Practice Act of 1973 prohibits a person from conducting timber operations, as defined, unless a timber harvesting plan prepared by a registered professional forester has been submitted to, and approved by, the Department of Forestry and Fire Protection. The act authorizes the State Board of Forestry and Fire Protection to exempt from some or all of those provisions of the act a person engaging in specified forest management activities, as prescribed, including: (1), for a period of 5 years following the adoption of emergency regulations, the cutting or removal of trees on the persons property that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break, known as the Small Timberland Owner Exemption, (2), until January 1, 2026, the harvesting of those trees that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for specified purposes, known as the Forest Fire Prevention Exemption, and (3), until January 1, 2026, the cutting or removal of trees on the persons property in compliance with specified defensible space requirements, as provided. provided, and (4) the cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands.
This bill would (1) repeal the Small Timberland Owner Exemption, (2) rename the Forest Fire Prevention Exemption the Forest Resilience Exemption, revise the standards and criteria for qualifying for that exemption, and extend that exemption until January 1, 2031, and (3) extend until January 1, 2031, the other exemption described above. The bill would also revise requirements governing compliance with cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands. The bill would require the board to adopt emergency regulations that the board considers necessary to implement and ensure compliance with these requirements and with the Forest Resilience Exemption requirements. The bill would also make conforming changes.
The Zberg-Nejedly Forest Practice Act of 1973 prohibits a person from conducting timber operations, as defined, unless a timber harvesting plan prepared by a registered professional forester has been submitted to, and approved by, the Department of Forestry and Fire Protection. The act authorizes the State Board of Forestry and Fire Protection to exempt from some or all of those provisions of the act a person engaging in specified forest management activities, as prescribed, including: (1), for a period of 5 years following the adoption of emergency regulations, the cutting or removal of trees on the persons property that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break, known as the Small Timberland Owner Exemption, (2), until January 1, 2026, the harvesting of those trees that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for specified purposes, known as the Forest Fire Prevention Exemption, and (3), until January 1, 2026, the cutting or removal of trees on the persons property in compliance with specified defensible space requirements, as provided.
This bill would extend those exemptions until January 1, 2031. (1) repeal the Small Timberland Owner Exemption, (2) rename the Forest Fire Prevention Exemption the Forest Resilience Exemption, revise the standards and criteria for qualifying for that exemption, and extend that exemption until January 1, 2031, and (3) extend until January 1, 2031, the other exemption described above. The bill would also make conforming changes.
The Zberg-Nejedly Forest Practice Act of 1973 prohibits a person from conducting timber operations, as defined, unless a timber harvesting plan prepared by a registered professional forester has been submitted to, and approved by, the Department of Forestry and Fire Protection. The act authorizes the State Board of Forestry and Fire Protection to exempt from some or all of those provisions of the act a person engaging in specified forest management activities, as prescribed, including: (1), for a period of 5 years following the adoption of emergency regulations, the cutting or removal of trees on the persons property that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break, known as the Small Timberland Owner Exemption, (2), until January 1, 2026, the harvesting of those trees that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for specified purposes, known as the Forest Fire Prevention Exemption, and (3), until January 1, 2026, the cutting or removal of trees on the persons property in compliance with specified defensible space requirements, as provided.
This bill would extend those exemptions until January 1, 2031.
The California Clean Energy Jobs Act, an initiative approved by the voters as Proposition 39 at the November 6, 2012, statewide general election, made changes to corporate income taxes and, except as specified, provided for the transfer of $550,000,000 annually from the General Fund to the Clean Energy Job Creation Fund for 5 fiscal years beginning with the 201314 fiscal year. Moneys in the Clean Energy Job Creation Fund are available, upon appropriation by the Legislature, for purposes of funding eligible projects that create jobs in California improving energy efficiency and expanding clean energy generation. Existing law provides for the allocation of those moneys to local educational agencies and community college districts. Existing law requires the State Energy Resources Conservation and Development Commission to maintain information on the local educational agencies and community college districts that receive the funding in a publicly available and searchable database that includes relevant metrics, as specified.This bill would make a nonsubstantive change to the provision concerning the commissions duty to maintain this information.The California Clean Energy Jobs Act, an initiative approved by the voters as Proposition 39 at the November 6, 2012, statewide general election, made changes to corporate income taxes and, except as specified, provided for the transfer of $550,000,000 annually from the General Fund to the Clean Energy Job Creation Fund for 5 fiscal years beginning with the 201314 fiscal year. Moneys in the Clean Energy Job Creation Fund are available, upon appropriation by the Legislature, for purposes of funding eligible projects that create jobs in California improving energy efficiency and expanding clean energy generation. Existing law provides for the allocation of those moneys to local educational agencies and community college districts. Existing law requires the State Energy Resources Conservation and Development Commission to maintain information on the local educational agencies and community college districts that receive the funding in a publicly available and searchable database that includes relevant metrics, as specified.
This bill would make a nonsubstantive change to the provision concerning the commissions duty to maintain this information.
Upon determining that this exemption is consistent with the purposes of this chapter, the board may exempt from this chapter, or portions of this chapter, a person engaged in forest management whose activities are limited to any of the following:
(a)The cutting or removal of trees for the purpose of constructing or maintaining a right-of-way for utility lines.
(b)The planting, growing, nurturing, shaping, shearing, removal, or harvest of immature trees for Christmas trees or other ornamental purposes or minor forest products, including fuelwood.
(c)The cutting or removal of dead, dying, or diseased trees of any size.
(d)Site preparation.
(e)Maintenance of drainage facilities and soil stabilization treatments.
(f)Timber operations on land managed by the Department of Parks and Recreation.
(g)(1)The one-time conversion of less than three acres to a nontimber use. A person, whether acting as an individual, as a member of a partnership, or as an officer or employee of a corporation or other legal entity, shall not obtain more than one exemption pursuant to this subdivision in a five-year period. If a partnership has as a member, or if a corporation or other legal entity has as an officer or employee, a person who has received this exemption within the past five years, whether as an individual, as a member of a partnership, or as an officer or employee of a corporation or other legal entity, then that partnership, corporation, or other legal entity is not eligible for this exemption. Person, for purposes of this subdivision, means an individual, partnership, corporation, or other legal entity.
(2)(A)Notwithstanding Section 4554.5, the board shall adopt regulations that do all of the following:
(i)Identify the required documentation of a bona fide intent to complete the conversion that an applicant will need to submit in order to be eligible for the exemption in paragraph (1).
(ii)Authorize the department to inspect the sites approved in conversion applications that have been approved on or after January 1, 2002, in order to determine that the conversion was completed within the two-year period described in subparagraph (B) of paragraph (2) of subdivision (a) of Section 1104.1 of Title 14 of the California Code of Regulations.
(iii)Require the exemption pursuant to this subdivision to expire if there is a change in timberland ownership. The person who originally submitted an application for an exemption pursuant to this subdivision shall notify the department of a change in timberland ownership on or before five calendar days after a change in ownership.
(iv)The board may adopt regulations allowing a waiver of the five-year limitation described in paragraph (1) upon finding that the imposition of the five-year limitation would impose an undue hardship on the applicant for the exemption. The board may adopt a process for an appeal of a denial of a waiver.
(v)The board may adopt regulations allowing a waiver of the one-time limitation described in paragraph (1) upon finding that the imposition of the one-time limitation would impose an undue hardship on the applicant. The board may adopt a process for an appeal of a denial of a waiver.
(B)The application form for the exemption pursuant to paragraph (1) shall prominently advise the public that a violation of the conversion exemption, including a conversion applied for in the name of someone other than the person or entity implementing the conversion in bona fide good faith, is a violation of this chapter and penalties may accrue up to ten thousand dollars ($10,000) for each violation pursuant to Article 8 (commencing with Section 4601).
(h)An easement granted by a right-of-way construction agreement administered by the federal government if timber sales and operations within or affecting the area are reviewed and conducted pursuant to the federal National Environmental Policy Act of 1969 (42 U.S.C. Sec. 4321 et seq.).
(i)(1)The cutting or removal of trees in compliance with Sections 4290 and 4291 that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break for a distance of not more than 150 feet on each side from an approved and legally permitted structure that complies with the California Building Standards Code, when that cutting or removal is conducted in compliance with this subdivision. For purposes of this subdivision, an approved and legally permitted structure includes only structures that are designed for human occupancy, garages, barns, stables, and structures used to enclose fuel tanks.
(2)(A)The cutting or removal of trees pursuant to this subdivision is limited to cutting or removal that will result in a reduction in the rate of fire spread, fire duration and intensity, fuel ignitability, or ignition of the tree crowns and shall be in accordance with any regulations adopted by the board pursuant to this section.
(B)Trees shall not be cut or removed pursuant to this subdivision by the clearcutting regeneration method, by the seed tree removal step of the seed tree regeneration method, or by the shelterwood removal step of the shelterwood regeneration method.
(3)(A)All fuel treatments conducted pursuant to this subdivision that do not comply with board rules and regulations may be determined to be a nuisance and subject to abatement by the department or the city or county having jurisdiction.
(B)The costs incurred by the department, city, or county, as the case may be, to abate the nuisance upon a parcel of land subject to the timber operations, including, but not limited to, investigation, boundary determination, measurement, and other related costs, may be recovered by special assessment and lien against the parcel of land by the department, city, or county. The assessment may be collected at the same time and in the same manner as ordinary ad valorem taxes, and shall be subject to the same penalties and the same procedure and sale in case of delinquency as is provided for ad valorem taxes.
(4)All timber operations conducted pursuant to this subdivision shall conform to applicable city or county general plans, city or county implementing ordinances, and city or county zoning ordinances. This paragraph does not authorize the cutting, removal, or sale of timber or other solid wood forest products within an area where timber harvesting is prohibited or otherwise restricted pursuant to the rules or regulations adopted by the board.
(5)(A)The board shall adopt regulations, initially as emergency regulations in accordance with subparagraph (B), that the board considers necessary to implement and to obtain compliance with this subdivision.
(B)The emergency regulations adopted pursuant to subparagraph (A) shall be adopted in accordance with the Administrative Procedure Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code). The adoption of emergency regulations shall be deemed to be an emergency and necessary for the immediate preservation of the public peace, health, and safety, or general welfare.
(j)(1)(A)The harvesting of trees, limited to those trees that eliminate the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns, for the purpose of reducing the rate of fire spread, duration and intensity, fuel ignitability, or ignition of tree crowns. An exemption pursuant to this paragraph shall be known as the Forest Resilience Exemption.
(B)The board may authorize an exemption pursuant to subparagraph (A) only if the tree harvesting will decrease fuel continuity and increase the quadratic mean diameter of the stand, and the tree harvesting area will not exceed 500 acres. Increases in quadratic mean diameter shall only consider trees greater than eight inches in diameter at breast height. The notice of exemption may be authorized only if all of the conditions specified in subparagraphs (C) to (I), inclusive, are met.
(C)A registered professional forester shall prepare the notice of exemption and submit it to the director.
(D)(i)The submitted notice of exemption shall include a description of the preharvest stand structure and a statement of the postharvest stand stocking levels and the expected postharvest increase in quadratic mean diameter.
(ii)The level of residual stocking shall be consistent with maximum sustained production of high-quality timber products. The residual stand shall consist primarily of healthy and vigorous dominant and codominant trees from the preharvest stand. Stocking shall not be reduced below the standards required by the following provisions that apply to the exemption at issue:
(I)Clauses 1 to 4, inclusive, of subparagraph (A) of paragraph (1) of subdivision (a) of Sections 913.3, 933.3, and 953.3 of Title 14 of the California Code of Regulations, or clauses 1 to 4, inclusive, of subparagraph (A) of paragraph (2) of subdivision (a) of Sections 913.2, 933.2, and 953.2 of Title 14 of the California Code of Regulations.
(II)The registered professional forester responsible for preparing the notice of exemption shall identify the designated postharvest stocking within the notice of exemption. The selected stocking shall be applicable to, and consistent with, silviculture that would apply to the preharvest stand condition provided pursuant to clause (i).
(III)Additional information on preharvest stand conditions, including, but not limited to, stand ages, stand structure, past management activities, and landowner goals and objectives shall also be provided by the registered professional forester preparing and submitting the exemption that substantiates the selection of postharvest stocking.
(iii)Within the coast district, if the preharvest dominant and codominant crown canopy is occupied by trees less than 14 inches in diameter at breast height, a minimum of 100 trees over 4 inches in diameter at breast height shall be retained per acre for Site I, II, and III lands, and a minimum of 75 trees over 4 inches in diameter at breast height shall be retained per acre for Site IV and V lands.
(iv)Within the northern district and southern district, if the preharvest dominant and codominant crown canopy is occupied by trees less than 14 inches in diameter at breast height, a minimum of 65 trees per acre over 4 inches in diameter at breast height shall be retained.
(v)All trees that are harvested or all trees that are retained shall be marked or sample marked by, or under the supervision of, a registered professional forester before felling operations begin. The board shall adopt regulations for sample marking for this section in Title 14 of the California Code of Regulations. Sample marking shall be limited to homogenous forest stand conditions typical of plantations.
(vi)The board may adopt specific regulations for the removal of dead and dying trees in amounts less than 10 percent of the average volume per acre for trees up to 36 inches in diameter at breast height. Regulations adopted by the board shall consider safety, fuel hazard abatement, mortality capture, the adequacy and retention of wildlife trees, especially those trees over 30 inches in diameter at breast height, and standards of enforceability for the department. All trees over 30 inches in diameter at breast height that are harvested pursuant to this paragraph shall be marked by, or under the supervision of, a registered professional forester before felling. The registered professional forester shall consult with the director before felling any dead or dying trees in excess of 30 inches in diameter at breast height.
(vii)All trees harvested pursuant to this paragraph shall be marked by, or under the supervision of, a registered professional forester before felling operations begin.
(viii)The six largest trees per acre within the boundaries of a notice of exemption submitted pursuant to this subdivision shall not be harvested.
(ix)No trees of the genus Quercus that are greater than 22 inches in diameter at breast height shall be harvested under a notice of exemption submitted pursuant to this subdivision, except for those trees that need to be removed to mitigate safety.
(x)The postharvest composition of tree species shall be representative of the preharvest stand condition and demonstrate progression towards climax forest conditions, unless the registered professional forester provides information explaining how modification of species diversity will benefit forest health and resiliency.
(E)(i)The board shall adopt regulations for the treatment of understory vegetation and standing dead fuels, canopy closure, clearance to base of live crown, or ladder fuels, that could promote the spread of wildfire.
(ii)Slash and woody debris within 50 feet of a public road or critical infrastructure, as defined by the board, shall be chipped, burned, or removed.
(iii)The standards required by clauses (i) and (ii) shall be achieved on approximately 80 percent of the treated area.
(F) Before the submission of a notice of exemption to the department, the registered professional forester responsible for submitting the notice shall designate temporary road locations, landing locations, tractor road crossings of Class III watercourses, unstable areas, or connected headwall swales on the ground and map their locations.
(G)The construction or reconstruction of temporary roads on slopes of 30 percent or less shall be allowed if all of the following conditions are met:
(i)Temporary roads or landings shall not be located on unstable areas, as defined in Section 895.1 of Title 14 of the California Code of Regulations.
(ii)Temporary roads shall be single-lane in width.
(iii)Temporary roads shall not be located across a connected headwall swale, as defined in Section 895.1 of Title 14 of the California Code of Regulations.
(iv)Construction or reconstruction of temporary roads, landings, or watercourse crossings shall not occur during the winter operating period. Pursuant to subdivision (g) of Sections 923.6, 943.6, and 963.6, as applicable, of Title 14 of the California Code of Regulations, roads and landings used for log hauling or other heavy equipment uses during the winter period shall occur on a stable operating surface and, where necessary, be surfaced with rock to a depth and quantity sufficient to maintain the stable operating surface. Use shall be prohibited on roads that are not hydrologically disconnected and exhibit saturated soil conditions. Timber operations during the winter period shall comply with paragraphs (1) and (2) of subdivision (c) of Sections 914.7, 934.7, and 954.7, as applicable, of Title 14 of the California Code of Regulations.
(v)Use of temporary roads shall comply with the operational provisions of Article 12 (commencing with Section 923) of Subchapter 4 of Chapter 4 of Division 1.5 of Title 14 of the California Code of Regulations, and recognize guidance on hydrologic disconnection in Technical Rule Addendum Number 5.
(vi)No logging road or landings construction or reconstruction activities of any kind shall occur within 200 feet of Class I and Class II watercourses or within 50 feet of a Class III watercourse.
(vii)The landowner shall retain a registered professional forester who is available to provide professional advice to the licensed timber operator and timberland owner throughout the active timber operations. The name, address, telephone number, and registration number of the retained registered professional forester shall be provided on the submitted notice of exemption. This professional advice shall include overseeing the construction or reconstruction of any temporary roads or landings and advising on necessary mitigation to avoid potential impacts to associated watershed and forest resources. The registered professional forester shall also comply with Section 1035.2 of Title 14 of the California Code of Regulations, relating to interaction between the licensed timber operator and the registered professional forester.
(viii)The registered professional forester responsible for submitting the notice of exemption shall affirm that the construction or reconstruction of each temporary road is necessary to provide access to harvest areas where no feasible alternative exists. The submitted notice of exemption shall include the number and cumulative length of temporary roads that will be constructed or reconstructed.
(ix)(I)Temporary road construction or reconstruction shall be limited to no more than two miles of road per ownership in a planning watershed per any five-year period.
(II)For each exemption affecting less than 40 acres, all temporary roads constructed or reconstructed under this exemption shall not exceed a cumulative length of 300 feet.
(III)For each exemption affecting between 40 and 80 acres, all temporary roads constructed or reconstructed under this exemption shall not exceed a cumulative length of between 300 and 600 feet, as determined on a pro rata basis by the total acreage affected by the exemption.
(IV)For each exemption affecting over 80 acres, all temporary roads constructed or reconstructed under the exemption shall not exceed a cumulative length of 600 feet. The submitted notice of exemption shall list the number of acres affected and the cumulative length of the road in feet.
(V)Temporary roads constructed or reconstructed under this exemption shall not be connected to other temporary roads constructed under previous or subsequent exemptions filed under this paragraph.
(VI)All temporary roads shall be abandoned using proactive measures that have been applied to effectively remove them from the permanent road network, in accordance with the definition of abandoned road as defined in Section 895.1 of Title 14 of the California Code of Regulations.
(VII)This paragraph shall not be interpreted to permit road construction or reconstruction except as authorized under the Forest Resilience Exemption, pursuant to this subparagraph.
(VIII)No trees larger than 30 inches in diameter at breast height shall be removed for the purposes of road construction or reconstruction under a notice of exemption submitted pursuant to this subdivision.
(H)Only trees less than 30 inches in diameter at breast height may be removed. The board, in consultation with the department, shall develop clearly written guidance documents on inspection and enforceability standards relating to standards set forth in this paragraph.
(I)All timber operations conducted pursuant to this subdivision shall only occur within the most recent version of the departments Fire Hazard Severity Zone Map in the moderate, high, and very high fire threat zones.
(J)If pesticides or herbicides will be used within the boundaries of an area covered by a notice of exemption pursuant to this subparagraph within one year of director acceptance, the timberland owner shall notify the appropriate regional water quality control board 10 days before application of any pesticides or herbicides.
(K)After the timber operations are complete, the department shall conduct an onsite inspection to determine compliance with this subdivision and whether appropriate enforcement action should be initiated. The department shall notify the appropriate regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey seven days prior to conducting the onsite inspection. The regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey may conduct an inspection with the department.
(2)(A)The board shall adopt regulations, initially as emergency regulations in accordance with subparagraph (B), that the board considers necessary to implement and to obtain compliance with this subdivision.
(B)The emergency regulations adopted pursuant to subparagraph (A) shall be adopted in accordance with the Administrative Procedure Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code). The adoption of emergency regulations shall be deemed to be an emergency and necessary for the immediate preservation of the public peace, health, and safety, or general welfare.
(3)This subdivision shall become inoperative on January 1, 2031.
(k)(1)The cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands, if all of the following requirements are met:
(A)A registered professional forester shall prepare the notice of exemption and submit it to the director. The notice shall include both of the following:
(i)A certification signed by the registered professional forester that the timber operation is designed to restore and conserve California black and Oregon white oak woodlands and associated grasslands encroached upon by conifers and that a minimum of 35 square feet of basal area per acre, or as determined by the board, of California black or Oregon white oak, or both, occupy the proposed treatment area at the time the notice is prepared.
(ii)A description of the preharvest stand structure and a statement of the postharvest stand stocking levels.
(B)No tree larger than 30 inches in diameter at breast height shall be harvested for commercial purposes. If necessary to achieve the oak woodland restoration goal of the exemption, trees larger than 30 inches in diameter at breast height may be harvested. The registered professional forester shall provide information on the need to remove these trees, and consult with the director before felling any tree in excess of 30 inches in diameter at breast height.
(C)Only conifers within 300 feet of a California black or Oregon white oak may be harvested.
(D)The total area exempted pursuant to this subdivision shall not exceed 300 acres per ownership in a planning watershed per five-year period.
(E)Conifer shall be reduced to less than 25 percent of the combined hardwood and conifer postharvest stand stocking levels. Decadent and deformed trees of wildlife value that are retained shall not count toward basal area requirements.
(F)No more than 20 percent of the total basal area of preexisting oak stock shall be cut or removed during harvest. The board may establish minimum postharvest basal area requirements for California black or Oregon white oak.
(G)Slash shall be configured to minimize the risk of fire mortality to the remaining oak trees.
(2)(A)The board shall adopt regulations, initially as emergency regulations in accordance with subparagraph (B), that the board considers necessary to implement and to obtain compliance with this subdivision.
(B)The emergency regulations adopted pursuant to subparagraph (A) shall be adopted in accordance with the Administrative Procedure Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code). The adoption of emergency regulations shall be deemed to be an emergency and necessary for the immediate preservation of the public peace, health, and safety, or general welfare.
(l)(1)The board may exempt from this chapter, or portions of this chapter, a person engaged in forest management whose activities are limited to the cutting or removal of trees on the persons property in compliance with Sections 4290 and 4291 that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break for a distance of not more than 300 feet on each side from an approved and legally permitted habitable structure, when that cutting or removal is conducted in compliance with this subdivision and all of the following conditions are met:
(A)The notice of exemption is prepared, signed, and submitted by a registered professional forester to the department.
(B)For the areas between 150 and 300 feet from the habitable structure, the operations meet all of the following provisions:
(i)The residual stocking standards are consistent with Sections 913.2, 933.2, and 953.2 of Title 14 of the California Code of Regulations, as appropriate.
(ii)Activities within this area will increase the quadratic mean diameter of the stand.
(iii)The residual stand consists primarily of healthy and vigorous dominant and codominant trees from the preharvest stand, well distributed throughout the harvested area.
(iv)Postharvest slash treatment and stand conditions will lead to more moderate fire behavior in the professional judgment of the registered professional forester who submits the notice of exemption.
(v)Any additional guidance for slash treatment and postharvest stand conditions and any other issues deemed necessary that are consistent with this section, as established by the board.
(2)For purposes of this subdivision, habitable structure means a building that contains one or more dwelling units or that can be occupied for residential use. Buildings occupied for residential use include single-family homes, multidwelling structures, mobile and manufactured homes, and condominiums. For purposes of this subdivision, habitable structure does not include commercial, industrial, or incidental buildings such as detached garages, barns, outdoor sanitation facilities, and sheds.
(3)This subdivision shall become inoperative on January 1, 2031.
SEC. 2.Section 4584.1 of the Public Resources Code is amended to read:4584.1.Rules and regulations adopted by the board pursuant to Section 4584, except subdivision (k) of Section 4584, shall comply with the following standards, as determined appropriate and necessary by the board:
(a)Notices of exemption that are prepared and submitted to the director shall include a map of the area of operations that complies with the requirements of paragraphs (1), (3), and (4), subparagraphs (A), (B), (D), and (E) of paragraph (5), paragraphs (7) to (12), inclusive, and paragraph (14) of subdivision (x) of Section 1034 of Title 14 of the California Code of Regulations.
(b)Notices of exemption that are prepared and submitted to the director shall provide a confidential archaeological letter that includes all the information required by paragraphs (2) and (7) to (11), inclusive, of subdivision (c) of Sections 929.1, 949.1 and 969.1, as applicable, of Title 14 of the California Code of Regulations, and site records if required pursuant to subdivision (g) of that section or pursuant to Section 929.5 of Title 14 of the California Code of Regulations. This subdivision shall not apply to activities described in subdivision (i) or (m) of Section 4584.
(c)All fuel treatments required by the board shall be completed within one year from the date the director receives the notice, with the exception of burning. This shall include treatment of surface fuels, wood debris, and slash, which shall be lopped, removed, chipped, piled for burning, or otherwise treated. Burning shall be completed within two years from the date the director receives the notice of exemption.
(d)Slash and woody debris shall be treated to achieve a maximum postharvest depth of 18 inches above the ground except within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code. Surface fuels, slash, and woody debris within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code shall be chipped, piled, and burned, or removed.
(e)Timber operations shall comply with the requirements of paragraphs (1) to (10), inclusive, of subdivision (b) of Section 1038 of Title 14 of the California Code of Regulations.
(f)All timber operations conducted in Lake Tahoe Region shall have a valid Tahoe Basin Tree Removal Permit, as defined by the Tahoe Regional Planning Agency (TRPA), or shall be conducted under a valid TRPA Memorandum of Understanding, when such a permit is required by TRPA.
(g)The submitted notice of exemption shall include selection criteria for the trees to be harvested or the trees to be retained.
(h)The department shall provide the appropriate regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey with copies of notices of exemption when they are submitted.
(i)The submitted notice of exemption shall include the tentative commencement date of timber operations.
(j)Within a 15-day period, the registered professional forester or person responsible for the submittal of the notice of exemption shall notify the department, the Department of Fish and Wildlife, the appropriate regional water quality control board, and the California Geologic Survey of the actual date of commencement of timber operations.
(k)Timber operations pursuant to an exemption may not commence for 10 working days from the date of the directors receipt of the notice of exemption unless this delay is waived by the director. The director shall determine whether the notice of exemption is complete, and if so, shall send a copy of a notice of acceptance to the submitter. If the notice of exemption is not complete and accurate, it shall be returned to the submitter and the timber operator may not proceed. If the director does not act within 10 days of receipt of the notice of exemption, timber operations may commence.
(l)(1)No large old trees, defined as a tree that existed before 1800 AD or is greater than 60 inches in diameter at stump height for Sierra or Coast Redwoods, and 48 inches in diameter at stump height for all other tree species or Decadent and Deformed Trees with Value to Wildlife, as defined in Section 895.1 of Title 14 of the California Code of Regulations, shall be harvested unless the following apply:
(A)The tree is not critical for the maintenance of a Late Successional Stand.
(B)A registered professional forester attached to the submitted notice of exemption a written explanation and justification for the harvest of the tree based on the registered professional foresters finding of any of the following:
(i)The tree is a hazard to safety or property.
(ii)The removal of the tree is necessary for the construction of a building as approved by the appropriate local jurisdiction and shown on the county or city approved site plan, which shall be attached to the submitted notice of exemption.
(iii)The tree is dead or likely to die within one year of the date of the proposed removal, as determined by a registered professional forester.
(2)A registered professional forester-written explanation or justification need not be attached to the submitted notice of exemption if an approved Habitat Conservation Plan, Sustained Yield Plan, or plan, as that term is defined in Section 895.1 of Title 14 of the California Code of Regulations addresses large old tree retention for the area in which the large old tree is proposed for removal and the removal is in compliance with the retention standards of that document.
(3)Any tree harvested pursuant to this subdivision shall be shown on a map provided with the submitted notice of exemption to the department.
(4)This subdivision shall not apply to or be used in conjunction with the Forest Resilience Exemption created pursuant to subdivision (j) of Section 4584.
(m)Helicopter yarding shall be prohibited.
(n)All applicable provisions of the Professional Foresters Law, including, but not limited to, Sections 775 to 779, inclusive, of this code, as well as all applicable provisions of Registration of Professional Forester Rules, including, but not limited to, Sections 1612 to 1614, inclusive, of Title 14 of the California Code of Regulations, shall apply to the practice of professional forestry as it relates to this section.
SEC. 3.Section 4584.2 of the Public Resources Code is amended to read:4584.2.Rules and regulations adopted by the board pursuant to subdivision (j) of Section 4584, shall comply with the following standards:
(a)Notices of exemption that are prepared and submitted to the director shall include a map of the area of operations that complies with the requirements of paragraphs (1), (3), and (4), subparagraphs (A), (B), (D), and (E) of paragraph (5), paragraphs (7) to (12), inclusive, and paragraph (14) of subdivision (x) of Section 1034 of Title 14 of the California Code of Regulations.
(b)Notices of exemption that are prepared and submitted to the director shall provide a confidential archaeological letter that includes all the information required by paragraphs (2) and (7) to (11), inclusive, of subdivision (c) of Sections 929.1, 949.1 and 969.1, as applicable, of Title 14 of the California Code of Regulations, and site records if required pursuant to subdivision (g) of that section or pursuant to Section 929.5 of Title 14 of the California Code of Regulations.
(c)All fuel treatments required by the board shall be completed within one year from the date the director receives the notice, with the exception of burning. This shall include treatment of surface fuels, wood debris, and slash, which shall be lopped, removed, chipped, piled for burning, or otherwise treated. Burning shall be completed within two years from the date the director receives the notice of exemption.
(d)Slash and woody debris shall be treated to achieve a maximum postharvest depth of 18 inches above the ground except within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code. Surface fuels, slash, and woody debris within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code shall be chipped, burned, or removed.
(e)Timber operations shall comply with the requirements of paragraphs (1) to (4), inclusive, and (6) to (10), inclusive, of subdivision (b) of Section 1038 of Title 14 of the California Code of Regulations.
(f)All timber operations conducted in Lake Tahoe Region must have a valid Tahoe Basin Tree Removal Permit, as defined by the Tahoe Regional Planning Agency (TRPA), or shall be conducted under a valid TRPA Memorandum of Understanding, when such a permit is required by TRPA.
(g)The submitted notice of exemption shall include selection criteria for the trees to be harvested or the trees to be retained.
(h)The department shall provide the appropriate regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey with copies of notices of exemption when they are submitted.
(i)The submitted notice of exemption shall include the tentative commencement date of timber operations.
(j)Within a 15-day period, the registered professional forester responsible for the submittal of the notice of exemption shall notify the department, the Department of Fish and Wildlife, the appropriate regional water quality control board, and the California Geologic Survey of the actual date of commencement of timber operations.
(k)Operations pursuant to an exemption may not commence for 10 working days from the date of the directors receipt of the notice of exemption unless this delay is waived by the director. The director shall determine whether the notice of exemption is complete, and if so, shall send a copy of a notice of acceptance to the submitter. If the notice of exemption is not complete and accurate, it shall be returned to the submitter and the timber operator may not proceed. If the director does not act within five days of receipt of the notice of exemption, timber operations may commence.
(l)(1)No Decadent and Deformed Trees with Value to Wildlife, as defined in Section 895.1 of Title 14 of the California Code of Regulations, shall be harvested unless all the following apply:
(A)The tree is not critical for the maintenance of a Late Successional Stand.
(B)A registered professional forester attached to the submitted notice of exemption a written explanation and justification for the harvest of the tree based on the registered professional foresters finding of any of the following:
(i)The tree is a hazard to safety or property.
(ii)The removal of the tree is necessary for the construction of a building as approved by the appropriate local jurisdiction and shown on the county or city approved site plan which shall be attached to the submitted notice of exemption.
(iii)The tree is dead or likely to die within one year of the date of the proposed removal, as determined by a registered professional forester.
(2)A registered professional foresters written explanation or justification need not be attached to the submitted notice of exemption if an approved Habitat Conservation Plan, Sustained Yield Plan, or plan as that term is defined in Section 895.1 of Title 14 of the California Code of Regulations addresses large old tree retention for the area in which the large old tree is proposed for removal and the removal is in compliance with the retention standards of that document.
(3)Any tree harvested pursuant to this subdivision shall be shown on a map provided with the submitted notice of exemption to the department.
(4)This subdivision shall not apply to or be used in conjunction with the Forest Resilience Exemption created pursuant to subdivision (j) of Section 4584.
(m)Helicopter yarding shall be prohibited.
(n)All applicable provisions of the Professional Foresters Law, including, but not limited to, Sections 775 to 779, inclusive, of this code, as well as all applicable provisions of Registration of Professional Forester Rules, including, but not limited to, Sections 1612 to 1614, inclusive, of Title 14 of the California Code of Regulations apply to the practice of professional forestry as it relates to this section.
SEC. 4.Section 4589 of the Public Resources Code is amended to read:4589.(a)The department and board, in consultation with the Department of Fish and Wildlife, and the State Water Resources Control Board, shall, commencing December 31, 2019, and annually thereafter, review and submit a report to the Legislature on the trends in the use of, compliance with, and effectiveness of, the exemptions and emergency notice provisions described in Sections 4584 and 4592 of this code and Sections 1038 and 1052 of Title 14 of the California Code of Regulations. The report shall include an analysis of exemption use and whether the exemptions are having the intended effect. The report shall also include recommendations to improve the use of those exemptions and emergency notice provisions, information on the linear distance of road constructed or reconstructed under notices of exemption by individual ownerships, within a representative sample of planning watersheds from each forest practice district as defined in Sections 907 to 909, inclusive, of Title 14 of the California Code of Regulations, and violations associated with road reconstruction. The report shall include information on the number and type of violations and enforcement actions taken on each notice of exemption and emergency notice. The report shall also contain the number of posttreatment onsite inspections that occur and whether those inspections were attended by a representative of the Department of Fish and Wildlife and a representative of the State Water Resources Control Board. The report submitted on December 31, 2025, shall include recommendations necessary for revisions to diameter limits at stump heights of harvestable trees under subdivisions (j) and (k) of Section 4584, as those subdivisions read on January 1, 2024.
(b)The public shall be provided opportunities to participate in the review and the development of the report.
(c)The report shall be submitted pursuant to Section 9795 of the Government Code.
(d)(A)This section shall be operative for a period of five years after the effective date of emergency regulations as adopted by the board and as of that date is inoperative.
(B)The board shall notify the Secretary of State when emergency regulations have been adopted.
SEC. 5.Section 399.20.3 of the Public Utilities Code is amended to read:399.20.3.(a)For purposes of this section, the following definitions apply:
(1)Bioenergy has the same meaning as set forth in paragraph (6) of subdivision (f) of Section 399.20.
(2)Tier 1 high hazard zone includes areas where wildlife and falling trees threaten electrical transmission and distribution lines, roads, and other evacuation corridors, critical community infrastructure, or other existing structures, as designated by the Department of Forestry and Fire Protection pursuant to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(3)Tier 2 high hazard zone includes watersheds that have significant tree mortality combined with community and natural resource assets, as designated by the Department of Forestry and Fire Protection pursuant to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(b)(1)In addition to the requirements of subdivision (f) of Section 399.20, by December 1, 2023, electrical corporations shall collectively procure, through financial commitments of 5 to 15 years, inclusive, their proportionate share of 125 megawatts of cumulative rated generating capacity from existing bioenergy projects that commenced operations before June 1, 2013. At least 80 percent of the feedstock of an eligible facility, on an annual basis, shall be a byproduct of sustainable forestry management, which includes removal of dead and dying trees from Tier 1 and Tier 2 high hazard zones and is not that from lands that have been clear cut. At least 60 percent of this feedstock shall be from Tier 1 and Tier 2 high hazard zones.
(2)Paragraph (1) shall not apply to a utility subject to subdivision (g) if both of the following apply:
(A)The utility, either directly or through a joint powers authority, entered into five-year financial commitments for its proportionate share of 125 megawatts of cumulative rated generating capacity from existing bioenergy projects pursuant to this section as it was enacted by Chapter 368 of the Statutes of 2016.
(B)The utilitys financial commitments referenced in subparagraph (A) include, (1) a contract with a facility operator that was, on June 1, 2022, in a bankruptcy or other insolvency proceeding, or (2) a contract for a project that does not deliver energy to the utility.
(c)For the purpose of contracts entered into pursuant to subdivision (b), commission Resolution E-4770 (March 17, 2016), and commission Resolution E-4805 (October 13, 2016), Tier 1 and Tier 2 high hazard zone fuel or feedstock shall also include biomass fuels removed from fuel reduction operations exempt from timber harvesting plan requirements pursuant to subdivisions (a), (f), (j), and (k) of Section 4584 of the Public Resources Code, as those subdivisions read on January 1, 2024.
(d)The commission shall require an electrical corporation that has entered into a contract pursuant to subdivision (b), commission Resolution E-4770 (March 17, 2016), or commission Resolution E-4805 (October 13, 2016) to allow fuel or feedstock reporting requirements to be based on a monthly or annual basis, and a bioenergy facility providing generation pursuant to that contract shall have the right to opt out of the mandated fuel or feedstock usage levels in any particular month upon providing written notice to the electrical corporation in the month of operation. For months in which a bioenergy facility opts out of the mandated fuel or feedstock usage levels or misses the mandated fuel or feedstock targets, that facility shall be paid the alternate price adopted by the commission in commission Resolution E-4770 for all megawatthours generated during that month. Contracts shall continue in force through the end of the contracted term without creating an event of default for missing mandated fuel or feedstock usage levels and without giving rise to a termination right in favor of the electrical corporation.
(e)(1)For each electrical corporation, the commission shall allocate its proportionate share of the 125 megawatts based on the ratio of the electrical corporations peak demand to the total statewide peak demand.
(2)Procurement by an electrical corporation of generation capacity pursuant to a contract under the commissions Resolution E-4770 (March 17, 2016) that is in excess of the requirement of that electrical corporation under that resolution shall count towards meeting the electrical corporations proportionate share allocated pursuant to paragraph (1).
(f)The commission may direct each electrical corporation to develop standard contract terms and conditions that reflect the operational characteristics of the bioenergy projects and to provide a streamlined contracting process or may require the electrical corporations to use the mechanism established pursuant to the commissions Resolution E-4770 (March 17, 2016) to meet the requirements of subdivision (e). The procurement pursuant to the developed standard contract shall occur on an expedited basis due to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(g)A local publicly owned electric utility serving more than 100,000 customers shall procure its proportionate share, based on the ratio of the utilitys peak demand to the total statewide peak demand, of 125 megawatts of cumulative rated capacity from existing bioenergy projects described in subdivision (b) subject to terms of at least five years.
(h)The commission shall ensure that the costs of any contract procured by an electrical corporation to satisfy the requirements of this section are recoverable from all customers on a nonbypassable basis.
(i)The Procurement Review Group within the commission shall advise the commission on the cost of the generation procured pursuant to this section and its impact on ratepayers.
(j)For purposes of this section, any incremental procurement of electricity products from bioenergy resources by a new contract or contract extension of five years or longer in duration shall be from a resource that meets emission limits equivalent to, or more stringent than, the applicable best available retrofit control technology, as determined by the local air pollution control district or air quality management district. The determination shall be made before the start of the operating period under the new contract or contract extension.
SEC. 5.5.Section 399.20.3 of the Public Utilities Code is amended to read:399.20.3.(a)For purposes of this section, the following definitions apply:
(1)Bioenergy has the same meaning as set forth in paragraph (6) of subdivision (f) of Section 399.20.
(2)Tier 1 high hazard zone includes areas where wildlife and falling trees threaten electrical transmission and distribution lines, roads, and other evacuation corridors, critical community infrastructure, or other existing structures, as designated by the Department of Forestry and Fire Protection pursuant to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(3)Tier 2 high hazard zone includes watersheds that have significant tree mortality combined with community and natural resource assets, as designated by the Department of Forestry and Fire Protection pursuant to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(b)(1)In addition to the requirements of subdivision (f) of Section 399.20, on or before July 1, 2025, electrical corporations shall collectively procure, through financial commitments of 5 to 15 years, inclusive, their proportionate share of 125 megawatts of cumulative rated generating capacity from existing bioenergy projects that commenced operations before June 1, 2013. At least 80 percent of the feedstock of an eligible facility, on an annual basis, shall be a byproduct of sustainable forestry management, which includes removal of dead and dying trees from Tier 1 and Tier 2 high hazard zones and is not that from lands that have been clear cut. At least 60 percent of this feedstock shall be from Tier 1 and Tier 2 high hazard zones.
(2)Paragraph (1) does not apply to a utility subject to subdivision (g) if both of the following apply:
(A)The utility, either directly or through a joint powers authority, entered into five-year financial commitments for its proportionate share of 125 megawatts of cumulative rated generating capacity from existing bioenergy projects pursuant to this section as it was enacted by Chapter 368 of the Statutes of 2016.
(B)The utilitys financial commitments referenced in subparagraph (A) include either: (i) a contract with a facility operator that was, on June 1, 2022, in a bankruptcy or other insolvency proceeding; or (ii) a contract for a project that does not deliver energy to the utility.
(c)For the purpose of contracts entered into pursuant to subdivision (b), commission Resolution E-4770 (March 17, 2016), and commission Resolution E-4805 (October 13, 2016), Tier 1 and Tier 2 high hazard zone fuel or feedstock shall also include biomass fuels removed from fuel reduction operations exempt from timber harvesting plan requirements pursuant to subdivisions (a), (f), (j), and (k) of Section 4584 of the Public Resources Code, as those subdivisions read on January 1, 2024.
(d)The commission shall require an electrical corporation that has entered into a contract pursuant to subdivision (b), commission Resolution E-4770 (March 17, 2016), or commission Resolution E-4805 (October 13, 2016) to allow fuel or feedstock reporting requirements to be based on a monthly or annual basis, and a bioenergy facility providing generation pursuant to that contract shall have the right to opt out of the mandated fuel or feedstock usage levels in any particular month upon providing written notice to the electrical corporation in the month of operation. For months in which a bioenergy facility opts out of the mandated fuel or feedstock usage levels or misses the mandated fuel or feedstock targets, that facility shall be paid the alternate price adopted by the commission in commission Resolution E-4770 for all megawatthours generated during that month. Contracts shall continue in force through the end of the contracted term without creating an event of default for missing mandated fuel or feedstock usage levels and without giving rise to a termination right in favor of the electrical corporation.
(e)(1)For each electrical corporation, the commission shall allocate its proportionate share of the 125 megawatts based on the ratio of the electrical corporations peak demand to the total statewide peak demand.
(2)Procurement by an electrical corporation of generation capacity pursuant to a contract under the commissions Resolution E-4770 (March 17, 2016) that is in excess of the requirement of that electrical corporation under that resolution shall count towards meeting the electrical corporations proportionate share allocated pursuant to paragraph (1).
(f)The commission may direct each electrical corporation to develop standard contract terms and conditions that reflect the operational characteristics of the bioenergy projects and to provide a streamlined contracting process or may require the electrical corporations to use the mechanism established pursuant to the commissions Resolution E-4770 (March 17, 2016) to meet the requirements of subdivision (e). The procurement pursuant to the developed standard contract shall occur on an expedited basis due to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(g)A local publicly owned electric utility serving more than 100,000 customers shall procure its proportionate share, based on the ratio of the utilitys peak demand to the total statewide peak demand, of 125 megawatts of cumulative rated capacity from existing bioenergy projects described in subdivision (b) subject to terms of at least five years.
(h)The commission shall ensure that the costs of any contract procured by an electrical corporation to satisfy the requirements of this section are recoverable from all customers on a nonbypassable basis.
(i)The Procurement Review Group within the commission shall advise the commission on the cost of the generation procured pursuant to this section and its impact on ratepayers.
(j)For purposes of this section, any incremental procurement of electricity products from bioenergy resources by a new contract or contract extension of five years or longer in duration shall be from a resource that meets emission limits equivalent to, or more stringent than, the applicable best available retrofit control technology, as determined by the local air pollution control district or air quality management district. The determination shall be made before the start of the operating period under the new contract or contract extension.
SEC. 6.Section 5.5 of this bill incorporates amendments to Section 399.20.3 of the Public Utilities Code proposed by both this bill and Assembly Bill 2750. That section of this bill shall only become operative if (1) both bills are enacted and become effective on or before January 1, 2025, (2) each bill amends Section 399.20.3 of the Public Utilities Code, and (3) this bill is enacted after Assembly Bill 2750, in which case Section 5 of this bill shall not become operative.
Upon determining that this exemption is consistent with the purposes of this chapter, the board may exempt from this chapter, or portions of this chapter, a person engaged in forest management whose activities are limited to any of the following:
(a)The cutting or removal of trees for the purpose of constructing or maintaining a right-of-way for utility lines.
(b)The planting, growing, nurturing, shaping, shearing, removal, or harvest of immature trees for Christmas trees or other ornamental purposes or minor forest products, including fuelwood.
(c)The cutting or removal of dead, dying, or diseased trees of any size.
(d)Site preparation.
(e)Maintenance of drainage facilities and soil stabilization treatments.
(f)Timber operations on land managed by the Department of Parks and Recreation.
(g)(1)The one-time conversion of less than three acres to a nontimber use. A person, whether acting as an individual, as a member of a partnership, or as an officer or employee of a corporation or other legal entity, shall not obtain more than one exemption pursuant to this subdivision in a five-year period. If a partnership has as a member, or if a corporation or other legal entity has as an officer or employee, a person who has received this exemption within the past five years, whether as an individual, as a member of a partnership, or as an officer or employee of a corporation or other legal entity, then that partnership, corporation, or other legal entity is not eligible for this exemption. Person, for purposes of this subdivision, means an individual, partnership, corporation, or other legal entity.
(2)(A)Notwithstanding Section 4554.5, the board shall adopt regulations that do all of the following:
(i)Identify the required documentation of a bona fide intent to complete the conversion that an applicant will need to submit in order to be eligible for the exemption in paragraph (1).
(ii)Authorize the department to inspect the sites approved in conversion applications that have been approved on or after January 1, 2002, in order to determine that the conversion was completed within the two-year period described in subparagraph (B) of paragraph (2) of subdivision (a) of Section 1104.1 of Title 14 of the California Code of Regulations.
(iii)Require the exemption pursuant to this subdivision to expire if there is a change in timberland ownership. The person who originally submitted an application for an exemption pursuant to this subdivision shall notify the department of a change in timberland ownership on or before five calendar days after a change in ownership.
(iv)The board may adopt regulations allowing a waiver of the five-year limitation described in paragraph (1) upon finding that the imposition of the five-year limitation would impose an undue hardship on the applicant for the exemption. The board may adopt a process for an appeal of a denial of a waiver.
(v)The board may adopt regulations allowing a waiver of the one-time limitation described in paragraph (1) upon finding that the imposition of the one-time limitation would impose an undue hardship on the applicant. The board may adopt a process for an appeal of a denial of a waiver.
(B)The application form for the exemption pursuant to paragraph (1) shall prominently advise the public that a violation of the conversion exemption, including a conversion applied for in the name of someone other than the person or entity implementing the conversion in bona fide good faith, is a violation of this chapter and penalties may accrue up to ten thousand dollars ($10,000) for each violation pursuant to Article 8 (commencing with Section 4601).
(h)An easement granted by a right-of-way construction agreement administered by the federal government if timber sales and operations within or affecting the area are reviewed and conducted pursuant to the federal National Environmental Policy Act of 1969 (42 U.S.C. Sec. 4321 et seq.).
(i)(1)The cutting or removal of trees in compliance with Sections 4290 and 4291 that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break for a distance of not more than 150 feet on each side from an approved and legally permitted structure that complies with the California Building Standards Code, when that cutting or removal is conducted in compliance with this subdivision. For purposes of this subdivision, an approved and legally permitted structure includes only structures that are designed for human occupancy, garages, barns, stables, and structures used to enclose fuel tanks.
(2)(A)The cutting or removal of trees pursuant to this subdivision is limited to cutting or removal that will result in a reduction in the rate of fire spread, fire duration and intensity, fuel ignitability, or ignition of the tree crowns and shall be in accordance with any regulations adopted by the board pursuant to this section.
(B)Trees shall not be cut or removed pursuant to this subdivision by the clearcutting regeneration method, by the seed tree removal step of the seed tree regeneration method, or by the shelterwood removal step of the shelterwood regeneration method.
(3)(A)All fuel treatments conducted pursuant to this subdivision that do not comply with board rules and regulations may be determined to be a nuisance and subject to abatement by the department or the city or county having jurisdiction.
(B)The costs incurred by the department, city, or county, as the case may be, to abate the nuisance upon a parcel of land subject to the timber operations, including, but not limited to, investigation, boundary determination, measurement, and other related costs, may be recovered by special assessment and lien against the parcel of land by the department, city, or county. The assessment may be collected at the same time and in the same manner as ordinary ad valorem taxes, and shall be subject to the same penalties and the same procedure and sale in case of delinquency as is provided for ad valorem taxes.
(4)All timber operations conducted pursuant to this subdivision shall conform to applicable city or county general plans, city or county implementing ordinances, and city or county zoning ordinances. This paragraph does not authorize the cutting, removal, or sale of timber or other solid wood forest products within an area where timber harvesting is prohibited or otherwise restricted pursuant to the rules or regulations adopted by the board.
(5)(A)The board shall adopt regulations, initially as emergency regulations in accordance with subparagraph (B), that the board considers necessary to implement and to obtain compliance with this subdivision.
(B)The emergency regulations adopted pursuant to subparagraph (A) shall be adopted in accordance with the Administrative Procedure Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code). The adoption of emergency regulations shall be deemed to be an emergency and necessary for the immediate preservation of the public peace, health, and safety, or general welfare.
(j)(1)(A)The harvesting of trees, limited to those trees that eliminate the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns, for the purpose of reducing the rate of fire spread, duration and intensity, fuel ignitability, or ignition of tree crowns. An exemption pursuant to this paragraph shall be known as the Forest Resilience Exemption.
(B)The board may authorize an exemption pursuant to subparagraph (A) only if the tree harvesting will decrease fuel continuity and increase the quadratic mean diameter of the stand, and the tree harvesting area will not exceed 500 acres. Increases in quadratic mean diameter shall only consider trees greater than eight inches in diameter at breast height. The notice of exemption may be authorized only if all of the conditions specified in subparagraphs (C) to (I), inclusive, are met.
(C)A registered professional forester shall prepare the notice of exemption and submit it to the director.
(D)(i)The submitted notice of exemption shall include a description of the preharvest stand structure and a statement of the postharvest stand stocking levels and the expected postharvest increase in quadratic mean diameter.
(ii)The level of residual stocking shall be consistent with maximum sustained production of high-quality timber products. The residual stand shall consist primarily of healthy and vigorous dominant and codominant trees from the preharvest stand. Stocking shall not be reduced below the standards required by the following provisions that apply to the exemption at issue:
(I)Clauses 1 to 4, inclusive, of subparagraph (A) of paragraph (1) of subdivision (a) of Sections 913.3, 933.3, and 953.3 of Title 14 of the California Code of Regulations, or clauses 1 to 4, inclusive, of subparagraph (A) of paragraph (2) of subdivision (a) of Sections 913.2, 933.2, and 953.2 of Title 14 of the California Code of Regulations.
(II)The registered professional forester responsible for preparing the notice of exemption shall identify the designated postharvest stocking within the notice of exemption. The selected stocking shall be applicable to, and consistent with, silviculture that would apply to the preharvest stand condition provided pursuant to clause (i).
(III)Additional information on preharvest stand conditions, including, but not limited to, stand ages, stand structure, past management activities, and landowner goals and objectives shall also be provided by the registered professional forester preparing and submitting the exemption that substantiates the selection of postharvest stocking.
(iii)Within the coast district, if the preharvest dominant and codominant crown canopy is occupied by trees less than 14 inches in diameter at breast height, a minimum of 100 trees over 4 inches in diameter at breast height shall be retained per acre for Site I, II, and III lands, and a minimum of 75 trees over 4 inches in diameter at breast height shall be retained per acre for Site IV and V lands.
(iv)Within the northern district and southern district, if the preharvest dominant and codominant crown canopy is occupied by trees less than 14 inches in diameter at breast height, a minimum of 65 trees per acre over 4 inches in diameter at breast height shall be retained.
(v)All trees that are harvested or all trees that are retained shall be marked or sample marked by, or under the supervision of, a registered professional forester before felling operations begin. The board shall adopt regulations for sample marking for this section in Title 14 of the California Code of Regulations. Sample marking shall be limited to homogenous forest stand conditions typical of plantations.
(vi)The board may adopt specific regulations for the removal of dead and dying trees in amounts less than 10 percent of the average volume per acre for trees up to 36 inches in diameter at breast height. Regulations adopted by the board shall consider safety, fuel hazard abatement, mortality capture, the adequacy and retention of wildlife trees, especially those trees over 30 inches in diameter at breast height, and standards of enforceability for the department. All trees over 30 inches in diameter at breast height that are harvested pursuant to this paragraph shall be marked by, or under the supervision of, a registered professional forester before felling. The registered professional forester shall consult with the director before felling any dead or dying trees in excess of 30 inches in diameter at breast height.
(vii)All trees harvested pursuant to this paragraph shall be marked by, or under the supervision of, a registered professional forester before felling operations begin.
(viii)The six largest trees per acre within the boundaries of a notice of exemption submitted pursuant to this subdivision shall not be harvested.
(ix)No trees of the genus Quercus that are greater than 22 inches in diameter at breast height shall be harvested under a notice of exemption submitted pursuant to this subdivision, except for those trees that need to be removed to mitigate safety.
(x)The postharvest composition of tree species shall be representative of the preharvest stand condition and demonstrate progression towards climax forest conditions, unless the registered professional forester provides information explaining how modification of species diversity will benefit forest health and resiliency.
(E)(i)The board shall adopt regulations for the treatment of understory vegetation and standing dead fuels, canopy closure, clearance to base of live crown, or ladder fuels, that could promote the spread of wildfire.
(ii)Slash and woody debris within 50 feet of a public road or critical infrastructure, as defined by the board, shall be chipped, burned, or removed.
(iii)The standards required by clauses (i) and (ii) shall be achieved on approximately 80 percent of the treated area.
(F) Before the submission of a notice of exemption to the department, the registered professional forester responsible for submitting the notice shall designate temporary road locations, landing locations, tractor road crossings of Class III watercourses, unstable areas, or connected headwall swales on the ground and map their locations.
(G)The construction or reconstruction of temporary roads on slopes of 30 percent or less shall be allowed if all of the following conditions are met:
(i)Temporary roads or landings shall not be located on unstable areas, as defined in Section 895.1 of Title 14 of the California Code of Regulations.
(ii)Temporary roads shall be single-lane in width.
(iii)Temporary roads shall not be located across a connected headwall swale, as defined in Section 895.1 of Title 14 of the California Code of Regulations.
(iv)Construction or reconstruction of temporary roads, landings, or watercourse crossings shall not occur during the winter operating period. Pursuant to subdivision (g) of Sections 923.6, 943.6, and 963.6, as applicable, of Title 14 of the California Code of Regulations, roads and landings used for log hauling or other heavy equipment uses during the winter period shall occur on a stable operating surface and, where necessary, be surfaced with rock to a depth and quantity sufficient to maintain the stable operating surface. Use shall be prohibited on roads that are not hydrologically disconnected and exhibit saturated soil conditions. Timber operations during the winter period shall comply with paragraphs (1) and (2) of subdivision (c) of Sections 914.7, 934.7, and 954.7, as applicable, of Title 14 of the California Code of Regulations.
(v)Use of temporary roads shall comply with the operational provisions of Article 12 (commencing with Section 923) of Subchapter 4 of Chapter 4 of Division 1.5 of Title 14 of the California Code of Regulations, and recognize guidance on hydrologic disconnection in Technical Rule Addendum Number 5.
(vi)No logging road or landings construction or reconstruction activities of any kind shall occur within 200 feet of Class I and Class II watercourses or within 50 feet of a Class III watercourse.
(vii)The landowner shall retain a registered professional forester who is available to provide professional advice to the licensed timber operator and timberland owner throughout the active timber operations. The name, address, telephone number, and registration number of the retained registered professional forester shall be provided on the submitted notice of exemption. This professional advice shall include overseeing the construction or reconstruction of any temporary roads or landings and advising on necessary mitigation to avoid potential impacts to associated watershed and forest resources. The registered professional forester shall also comply with Section 1035.2 of Title 14 of the California Code of Regulations, relating to interaction between the licensed timber operator and the registered professional forester.
(viii)The registered professional forester responsible for submitting the notice of exemption shall affirm that the construction or reconstruction of each temporary road is necessary to provide access to harvest areas where no feasible alternative exists. The submitted notice of exemption shall include the number and cumulative length of temporary roads that will be constructed or reconstructed.
(ix)(I)Temporary road construction or reconstruction shall be limited to no more than two miles of road per ownership in a planning watershed per any five-year period.
(II)For each exemption affecting less than 40 acres, all temporary roads constructed or reconstructed under this exemption shall not exceed a cumulative length of 300 feet.
(III)For each exemption affecting between 40 and 80 acres, all temporary roads constructed or reconstructed under this exemption shall not exceed a cumulative length of between 300 and 600 feet, as determined on a pro rata basis by the total acreage affected by the exemption.
(IV)For each exemption affecting over 80 acres, all temporary roads constructed or reconstructed under the exemption shall not exceed a cumulative length of 600 feet. The submitted notice of exemption shall list the number of acres affected and the cumulative length of the road in feet.
(V)Temporary roads constructed or reconstructed under this exemption shall not be connected to other temporary roads constructed under previous or subsequent exemptions filed under this paragraph.
(VI)All temporary roads shall be abandoned using proactive measures that have been applied to effectively remove them from the permanent road network, in accordance with the definition of abandoned road as defined in Section 895.1 of Title 14 of the California Code of Regulations.
(VII)This paragraph shall not be interpreted to permit road construction or reconstruction except as authorized under the Forest Resilience Exemption, pursuant to this subparagraph.
(VIII)No trees larger than 30 inches in diameter at breast height shall be removed for the purposes of road construction or reconstruction under a notice of exemption submitted pursuant to this subdivision.
(H)Only trees less than 30 inches in diameter at breast height may be removed. The board, in consultation with the department, shall develop clearly written guidance documents on inspection and enforceability standards relating to standards set forth in this paragraph.
(I)All timber operations conducted pursuant to this subdivision shall only occur within the most recent version of the departments Fire Hazard Severity Zone Map in the moderate, high, and very high fire threat zones.
(J)If pesticides or herbicides will be used within the boundaries of an area covered by a notice of exemption pursuant to this subparagraph within one year of director acceptance, the timberland owner shall notify the appropriate regional water quality control board 10 days before application of any pesticides or herbicides.
(K)After the timber operations are complete, the department shall conduct an onsite inspection to determine compliance with this subdivision and whether appropriate enforcement action should be initiated. The department shall notify the appropriate regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey seven days prior to conducting the onsite inspection. The regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey may conduct an inspection with the department.
(2)(A)The board shall adopt regulations, initially as emergency regulations in accordance with subparagraph (B), that the board considers necessary to implement and to obtain compliance with this subdivision.
(B)The emergency regulations adopted pursuant to subparagraph (A) shall be adopted in accordance with the Administrative Procedure Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code). The adoption of emergency regulations shall be deemed to be an emergency and necessary for the immediate preservation of the public peace, health, and safety, or general welfare.
(3)This subdivision shall become inoperative on January 1, 2031.
(k)(1)The cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands, if all of the following requirements are met:
(A)A registered professional forester shall prepare the notice of exemption and submit it to the director. The notice shall include both of the following:
(i)A certification signed by the registered professional forester that the timber operation is designed to restore and conserve California black and Oregon white oak woodlands and associated grasslands encroached upon by conifers and that a minimum of 35 square feet of basal area per acre, or as determined by the board, of California black or Oregon white oak, or both, occupy the proposed treatment area at the time the notice is prepared.
(ii)A description of the preharvest stand structure and a statement of the postharvest stand stocking levels.
(B)No tree larger than 30 inches in diameter at breast height shall be harvested for commercial purposes. If necessary to achieve the oak woodland restoration goal of the exemption, trees larger than 30 inches in diameter at breast height may be harvested. The registered professional forester shall provide information on the need to remove these trees, and consult with the director before felling any tree in excess of 30 inches in diameter at breast height.
(C)Only conifers within 300 feet of a California black or Oregon white oak may be harvested.
(D)The total area exempted pursuant to this subdivision shall not exceed 300 acres per ownership in a planning watershed per five-year period.
(E)Conifer shall be reduced to less than 25 percent of the combined hardwood and conifer postharvest stand stocking levels. Decadent and deformed trees of wildlife value that are retained shall not count toward basal area requirements.
(F)No more than 20 percent of the total basal area of preexisting oak stock shall be cut or removed during harvest. The board may establish minimum postharvest basal area requirements for California black or Oregon white oak.
(G)Slash shall be configured to minimize the risk of fire mortality to the remaining oak trees.
(2)(A)The board shall adopt regulations, initially as emergency regulations in accordance with subparagraph (B), that the board considers necessary to implement and to obtain compliance with this subdivision.
(B)The emergency regulations adopted pursuant to subparagraph (A) shall be adopted in accordance with the Administrative Procedure Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code). The adoption of emergency regulations shall be deemed to be an emergency and necessary for the immediate preservation of the public peace, health, and safety, or general welfare.
(l)(1)The board may exempt from this chapter, or portions of this chapter, a person engaged in forest management whose activities are limited to the cutting or removal of trees on the persons property in compliance with Sections 4290 and 4291 that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break for a distance of not more than 300 feet on each side from an approved and legally permitted habitable structure, when that cutting or removal is conducted in compliance with this subdivision and all of the following conditions are met:
(A)The notice of exemption is prepared, signed, and submitted by a registered professional forester to the department.
(B)For the areas between 150 and 300 feet from the habitable structure, the operations meet all of the following provisions:
(i)The residual stocking standards are consistent with Sections 913.2, 933.2, and 953.2 of Title 14 of the California Code of Regulations, as appropriate.
(ii)Activities within this area will increase the quadratic mean diameter of the stand.
(iii)The residual stand consists primarily of healthy and vigorous dominant and codominant trees from the preharvest stand, well distributed throughout the harvested area.
(iv)Postharvest slash treatment and stand conditions will lead to more moderate fire behavior in the professional judgment of the registered professional forester who submits the notice of exemption.
(v)Any additional guidance for slash treatment and postharvest stand conditions and any other issues deemed necessary that are consistent with this section, as established by the board.
(2)For purposes of this subdivision, habitable structure means a building that contains one or more dwelling units or that can be occupied for residential use. Buildings occupied for residential use include single-family homes, multidwelling structures, mobile and manufactured homes, and condominiums. For purposes of this subdivision, habitable structure does not include commercial, industrial, or incidental buildings such as detached garages, barns, outdoor sanitation facilities, and sheds.
(3)This subdivision shall become inoperative on January 1, 2031.
SEC. 2.Section 4584.1 of the Public Resources Code is amended to read:4584.1.Rules and regulations adopted by the board pursuant to Section 4584, except subdivision (k) of Section 4584, shall comply with the following standards, as determined appropriate and necessary by the board:
(a)Notices of exemption that are prepared and submitted to the director shall include a map of the area of operations that complies with the requirements of paragraphs (1), (3), and (4), subparagraphs (A), (B), (D), and (E) of paragraph (5), paragraphs (7) to (12), inclusive, and paragraph (14) of subdivision (x) of Section 1034 of Title 14 of the California Code of Regulations.
(b)Notices of exemption that are prepared and submitted to the director shall provide a confidential archaeological letter that includes all the information required by paragraphs (2) and (7) to (11), inclusive, of subdivision (c) of Sections 929.1, 949.1 and 969.1, as applicable, of Title 14 of the California Code of Regulations, and site records if required pursuant to subdivision (g) of that section or pursuant to Section 929.5 of Title 14 of the California Code of Regulations. This subdivision shall not apply to activities described in subdivision (i) or (m) of Section 4584.
(c)All fuel treatments required by the board shall be completed within one year from the date the director receives the notice, with the exception of burning. This shall include treatment of surface fuels, wood debris, and slash, which shall be lopped, removed, chipped, piled for burning, or otherwise treated. Burning shall be completed within two years from the date the director receives the notice of exemption.
(d)Slash and woody debris shall be treated to achieve a maximum postharvest depth of 18 inches above the ground except within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code. Surface fuels, slash, and woody debris within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code shall be chipped, piled, and burned, or removed.
(e)Timber operations shall comply with the requirements of paragraphs (1) to (10), inclusive, of subdivision (b) of Section 1038 of Title 14 of the California Code of Regulations.
(f)All timber operations conducted in Lake Tahoe Region shall have a valid Tahoe Basin Tree Removal Permit, as defined by the Tahoe Regional Planning Agency (TRPA), or shall be conducted under a valid TRPA Memorandum of Understanding, when such a permit is required by TRPA.
(g)The submitted notice of exemption shall include selection criteria for the trees to be harvested or the trees to be retained.
(h)The department shall provide the appropriate regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey with copies of notices of exemption when they are submitted.
(i)The submitted notice of exemption shall include the tentative commencement date of timber operations.
(j)Within a 15-day period, the registered professional forester or person responsible for the submittal of the notice of exemption shall notify the department, the Department of Fish and Wildlife, the appropriate regional water quality control board, and the California Geologic Survey of the actual date of commencement of timber operations.
(k)Timber operations pursuant to an exemption may not commence for 10 working days from the date of the directors receipt of the notice of exemption unless this delay is waived by the director. The director shall determine whether the notice of exemption is complete, and if so, shall send a copy of a notice of acceptance to the submitter. If the notice of exemption is not complete and accurate, it shall be returned to the submitter and the timber operator may not proceed. If the director does not act within 10 days of receipt of the notice of exemption, timber operations may commence.
(l)(1)No large old trees, defined as a tree that existed before 1800 AD or is greater than 60 inches in diameter at stump height for Sierra or Coast Redwoods, and 48 inches in diameter at stump height for all other tree species or Decadent and Deformed Trees with Value to Wildlife, as defined in Section 895.1 of Title 14 of the California Code of Regulations, shall be harvested unless the following apply:
(A)The tree is not critical for the maintenance of a Late Successional Stand.
(B)A registered professional forester attached to the submitted notice of exemption a written explanation and justification for the harvest of the tree based on the registered professional foresters finding of any of the following:
(i)The tree is a hazard to safety or property.
(ii)The removal of the tree is necessary for the construction of a building as approved by the appropriate local jurisdiction and shown on the county or city approved site plan, which shall be attached to the submitted notice of exemption.
(iii)The tree is dead or likely to die within one year of the date of the proposed removal, as determined by a registered professional forester.
(2)A registered professional forester-written explanation or justification need not be attached to the submitted notice of exemption if an approved Habitat Conservation Plan, Sustained Yield Plan, or plan, as that term is defined in Section 895.1 of Title 14 of the California Code of Regulations addresses large old tree retention for the area in which the large old tree is proposed for removal and the removal is in compliance with the retention standards of that document.
(3)Any tree harvested pursuant to this subdivision shall be shown on a map provided with the submitted notice of exemption to the department.
(4)This subdivision shall not apply to or be used in conjunction with the Forest Resilience Exemption created pursuant to subdivision (j) of Section 4584.
(m)Helicopter yarding shall be prohibited.
(n)All applicable provisions of the Professional Foresters Law, including, but not limited to, Sections 775 to 779, inclusive, of this code, as well as all applicable provisions of Registration of Professional Forester Rules, including, but not limited to, Sections 1612 to 1614, inclusive, of Title 14 of the California Code of Regulations, shall apply to the practice of professional forestry as it relates to this section.
SEC. 3.Section 4584.2 of the Public Resources Code is amended to read:4584.2.Rules and regulations adopted by the board pursuant to subdivision (j) of Section 4584, shall comply with the following standards:
(a)Notices of exemption that are prepared and submitted to the director shall include a map of the area of operations that complies with the requirements of paragraphs (1), (3), and (4), subparagraphs (A), (B), (D), and (E) of paragraph (5), paragraphs (7) to (12), inclusive, and paragraph (14) of subdivision (x) of Section 1034 of Title 14 of the California Code of Regulations.
(b)Notices of exemption that are prepared and submitted to the director shall provide a confidential archaeological letter that includes all the information required by paragraphs (2) and (7) to (11), inclusive, of subdivision (c) of Sections 929.1, 949.1 and 969.1, as applicable, of Title 14 of the California Code of Regulations, and site records if required pursuant to subdivision (g) of that section or pursuant to Section 929.5 of Title 14 of the California Code of Regulations.
(c)All fuel treatments required by the board shall be completed within one year from the date the director receives the notice, with the exception of burning. This shall include treatment of surface fuels, wood debris, and slash, which shall be lopped, removed, chipped, piled for burning, or otherwise treated. Burning shall be completed within two years from the date the director receives the notice of exemption.
(d)Slash and woody debris shall be treated to achieve a maximum postharvest depth of 18 inches above the ground except within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code. Surface fuels, slash, and woody debris within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code shall be chipped, burned, or removed.
(e)Timber operations shall comply with the requirements of paragraphs (1) to (4), inclusive, and (6) to (10), inclusive, of subdivision (b) of Section 1038 of Title 14 of the California Code of Regulations.
(f)All timber operations conducted in Lake Tahoe Region must have a valid Tahoe Basin Tree Removal Permit, as defined by the Tahoe Regional Planning Agency (TRPA), or shall be conducted under a valid TRPA Memorandum of Understanding, when such a permit is required by TRPA.
(g)The submitted notice of exemption shall include selection criteria for the trees to be harvested or the trees to be retained.
(h)The department shall provide the appropriate regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey with copies of notices of exemption when they are submitted.
(i)The submitted notice of exemption shall include the tentative commencement date of timber operations.
(j)Within a 15-day period, the registered professional forester responsible for the submittal of the notice of exemption shall notify the department, the Department of Fish and Wildlife, the appropriate regional water quality control board, and the California Geologic Survey of the actual date of commencement of timber operations.
(k)Operations pursuant to an exemption may not commence for 10 working days from the date of the directors receipt of the notice of exemption unless this delay is waived by the director. The director shall determine whether the notice of exemption is complete, and if so, shall send a copy of a notice of acceptance to the submitter. If the notice of exemption is not complete and accurate, it shall be returned to the submitter and the timber operator may not proceed. If the director does not act within five days of receipt of the notice of exemption, timber operations may commence.
(l)(1)No Decadent and Deformed Trees with Value to Wildlife, as defined in Section 895.1 of Title 14 of the California Code of Regulations, shall be harvested unless all the following apply:
(A)The tree is not critical for the maintenance of a Late Successional Stand.
(B)A registered professional forester attached to the submitted notice of exemption a written explanation and justification for the harvest of the tree based on the registered professional foresters finding of any of the following:
(i)The tree is a hazard to safety or property.
(ii)The removal of the tree is necessary for the construction of a building as approved by the appropriate local jurisdiction and shown on the county or city approved site plan which shall be attached to the submitted notice of exemption.
(iii)The tree is dead or likely to die within one year of the date of the proposed removal, as determined by a registered professional forester.
(2)A registered professional foresters written explanation or justification need not be attached to the submitted notice of exemption if an approved Habitat Conservation Plan, Sustained Yield Plan, or plan as that term is defined in Section 895.1 of Title 14 of the California Code of Regulations addresses large old tree retention for the area in which the large old tree is proposed for removal and the removal is in compliance with the retention standards of that document.
(3)Any tree harvested pursuant to this subdivision shall be shown on a map provided with the submitted notice of exemption to the department.
(4)This subdivision shall not apply to or be used in conjunction with the Forest Resilience Exemption created pursuant to subdivision (j) of Section 4584.
(m)Helicopter yarding shall be prohibited.
(n)All applicable provisions of the Professional Foresters Law, including, but not limited to, Sections 775 to 779, inclusive, of this code, as well as all applicable provisions of Registration of Professional Forester Rules, including, but not limited to, Sections 1612 to 1614, inclusive, of Title 14 of the California Code of Regulations apply to the practice of professional forestry as it relates to this section.
SEC. 4.Section 4589 of the Public Resources Code is amended to read:4589.(a)The department and board, in consultation with the Department of Fish and Wildlife, and the State Water Resources Control Board, shall, commencing December 31, 2019, and annually thereafter, review and submit a report to the Legislature on the trends in the use of, compliance with, and effectiveness of, the exemptions and emergency notice provisions described in Sections 4584 and 4592 of this code and Sections 1038 and 1052 of Title 14 of the California Code of Regulations. The report shall include an analysis of exemption use and whether the exemptions are having the intended effect. The report shall also include recommendations to improve the use of those exemptions and emergency notice provisions, information on the linear distance of road constructed or reconstructed under notices of exemption by individual ownerships, within a representative sample of planning watersheds from each forest practice district as defined in Sections 907 to 909, inclusive, of Title 14 of the California Code of Regulations, and violations associated with road reconstruction. The report shall include information on the number and type of violations and enforcement actions taken on each notice of exemption and emergency notice. The report shall also contain the number of posttreatment onsite inspections that occur and whether those inspections were attended by a representative of the Department of Fish and Wildlife and a representative of the State Water Resources Control Board. The report submitted on December 31, 2025, shall include recommendations necessary for revisions to diameter limits at stump heights of harvestable trees under subdivisions (j) and (k) of Section 4584, as those subdivisions read on January 1, 2024.
(b)The public shall be provided opportunities to participate in the review and the development of the report.
(c)The report shall be submitted pursuant to Section 9795 of the Government Code.
(d)(A)This section shall be operative for a period of five years after the effective date of emergency regulations as adopted by the board and as of that date is inoperative.
(B)The board shall notify the Secretary of State when emergency regulations have been adopted.
SEC. 5.Section 399.20.3 of the Public Utilities Code is amended to read:399.20.3.(a)For purposes of this section, the following definitions apply:
(1)Bioenergy has the same meaning as set forth in paragraph (6) of subdivision (f) of Section 399.20.
(2)Tier 1 high hazard zone includes areas where wildlife and falling trees threaten electrical transmission and distribution lines, roads, and other evacuation corridors, critical community infrastructure, or other existing structures, as designated by the Department of Forestry and Fire Protection pursuant to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(3)Tier 2 high hazard zone includes watersheds that have significant tree mortality combined with community and natural resource assets, as designated by the Department of Forestry and Fire Protection pursuant to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(b)(1)In addition to the requirements of subdivision (f) of Section 399.20, by December 1, 2023, electrical corporations shall collectively procure, through financial commitments of 5 to 15 years, inclusive, their proportionate share of 125 megawatts of cumulative rated generating capacity from existing bioenergy projects that commenced operations before June 1, 2013. At least 80 percent of the feedstock of an eligible facility, on an annual basis, shall be a byproduct of sustainable forestry management, which includes removal of dead and dying trees from Tier 1 and Tier 2 high hazard zones and is not that from lands that have been clear cut. At least 60 percent of this feedstock shall be from Tier 1 and Tier 2 high hazard zones.
(2)Paragraph (1) shall not apply to a utility subject to subdivision (g) if both of the following apply:
(A)The utility, either directly or through a joint powers authority, entered into five-year financial commitments for its proportionate share of 125 megawatts of cumulative rated generating capacity from existing bioenergy projects pursuant to this section as it was enacted by Chapter 368 of the Statutes of 2016.
(B)The utilitys financial commitments referenced in subparagraph (A) include, (1) a contract with a facility operator that was, on June 1, 2022, in a bankruptcy or other insolvency proceeding, or (2) a contract for a project that does not deliver energy to the utility.
(c)For the purpose of contracts entered into pursuant to subdivision (b), commission Resolution E-4770 (March 17, 2016), and commission Resolution E-4805 (October 13, 2016), Tier 1 and Tier 2 high hazard zone fuel or feedstock shall also include biomass fuels removed from fuel reduction operations exempt from timber harvesting plan requirements pursuant to subdivisions (a), (f), (j), and (k) of Section 4584 of the Public Resources Code, as those subdivisions read on January 1, 2024.
(d)The commission shall require an electrical corporation that has entered into a contract pursuant to subdivision (b), commission Resolution E-4770 (March 17, 2016), or commission Resolution E-4805 (October 13, 2016) to allow fuel or feedstock reporting requirements to be based on a monthly or annual basis, and a bioenergy facility providing generation pursuant to that contract shall have the right to opt out of the mandated fuel or feedstock usage levels in any particular month upon providing written notice to the electrical corporation in the month of operation. For months in which a bioenergy facility opts out of the mandated fuel or feedstock usage levels or misses the mandated fuel or feedstock targets, that facility shall be paid the alternate price adopted by the commission in commission Resolution E-4770 for all megawatthours generated during that month. Contracts shall continue in force through the end of the contracted term without creating an event of default for missing mandated fuel or feedstock usage levels and without giving rise to a termination right in favor of the electrical corporation.
(e)(1)For each electrical corporation, the commission shall allocate its proportionate share of the 125 megawatts based on the ratio of the electrical corporations peak demand to the total statewide peak demand.
(2)Procurement by an electrical corporation of generation capacity pursuant to a contract under the commissions Resolution E-4770 (March 17, 2016) that is in excess of the requirement of that electrical corporation under that resolution shall count towards meeting the electrical corporations proportionate share allocated pursuant to paragraph (1).
(f)The commission may direct each electrical corporation to develop standard contract terms and conditions that reflect the operational characteristics of the bioenergy projects and to provide a streamlined contracting process or may require the electrical corporations to use the mechanism established pursuant to the commissions Resolution E-4770 (March 17, 2016) to meet the requirements of subdivision (e). The procurement pursuant to the developed standard contract shall occur on an expedited basis due to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(g)A local publicly owned electric utility serving more than 100,000 customers shall procure its proportionate share, based on the ratio of the utilitys peak demand to the total statewide peak demand, of 125 megawatts of cumulative rated capacity from existing bioenergy projects described in subdivision (b) subject to terms of at least five years.
(h)The commission shall ensure that the costs of any contract procured by an electrical corporation to satisfy the requirements of this section are recoverable from all customers on a nonbypassable basis.
(i)The Procurement Review Group within the commission shall advise the commission on the cost of the generation procured pursuant to this section and its impact on ratepayers.
(j)For purposes of this section, any incremental procurement of electricity products from bioenergy resources by a new contract or contract extension of five years or longer in duration shall be from a resource that meets emission limits equivalent to, or more stringent than, the applicable best available retrofit control technology, as determined by the local air pollution control district or air quality management district. The determination shall be made before the start of the operating period under the new contract or contract extension.
SEC. 5.5.Section 399.20.3 of the Public Utilities Code is amended to read:399.20.3.(a)For purposes of this section, the following definitions apply:
(1)Bioenergy has the same meaning as set forth in paragraph (6) of subdivision (f) of Section 399.20.
(2)Tier 1 high hazard zone includes areas where wildlife and falling trees threaten electrical transmission and distribution lines, roads, and other evacuation corridors, critical community infrastructure, or other existing structures, as designated by the Department of Forestry and Fire Protection pursuant to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(3)Tier 2 high hazard zone includes watersheds that have significant tree mortality combined with community and natural resource assets, as designated by the Department of Forestry and Fire Protection pursuant to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(b)(1)In addition to the requirements of subdivision (f) of Section 399.20, on or before July 1, 2025, electrical corporations shall collectively procure, through financial commitments of 5 to 15 years, inclusive, their proportionate share of 125 megawatts of cumulative rated generating capacity from existing bioenergy projects that commenced operations before June 1, 2013. At least 80 percent of the feedstock of an eligible facility, on an annual basis, shall be a byproduct of sustainable forestry management, which includes removal of dead and dying trees from Tier 1 and Tier 2 high hazard zones and is not that from lands that have been clear cut. At least 60 percent of this feedstock shall be from Tier 1 and Tier 2 high hazard zones.
(2)Paragraph (1) does not apply to a utility subject to subdivision (g) if both of the following apply:
(A)The utility, either directly or through a joint powers authority, entered into five-year financial commitments for its proportionate share of 125 megawatts of cumulative rated generating capacity from existing bioenergy projects pursuant to this section as it was enacted by Chapter 368 of the Statutes of 2016.
(B)The utilitys financial commitments referenced in subparagraph (A) include either: (i) a contract with a facility operator that was, on June 1, 2022, in a bankruptcy or other insolvency proceeding; or (ii) a contract for a project that does not deliver energy to the utility.
(c)For the purpose of contracts entered into pursuant to subdivision (b), commission Resolution E-4770 (March 17, 2016), and commission Resolution E-4805 (October 13, 2016), Tier 1 and Tier 2 high hazard zone fuel or feedstock shall also include biomass fuels removed from fuel reduction operations exempt from timber harvesting plan requirements pursuant to subdivisions (a), (f), (j), and (k) of Section 4584 of the Public Resources Code, as those subdivisions read on January 1, 2024.
(d)The commission shall require an electrical corporation that has entered into a contract pursuant to subdivision (b), commission Resolution E-4770 (March 17, 2016), or commission Resolution E-4805 (October 13, 2016) to allow fuel or feedstock reporting requirements to be based on a monthly or annual basis, and a bioenergy facility providing generation pursuant to that contract shall have the right to opt out of the mandated fuel or feedstock usage levels in any particular month upon providing written notice to the electrical corporation in the month of operation. For months in which a bioenergy facility opts out of the mandated fuel or feedstock usage levels or misses the mandated fuel or feedstock targets, that facility shall be paid the alternate price adopted by the commission in commission Resolution E-4770 for all megawatthours generated during that month. Contracts shall continue in force through the end of the contracted term without creating an event of default for missing mandated fuel or feedstock usage levels and without giving rise to a termination right in favor of the electrical corporation.
(e)(1)For each electrical corporation, the commission shall allocate its proportionate share of the 125 megawatts based on the ratio of the electrical corporations peak demand to the total statewide peak demand.
(2)Procurement by an electrical corporation of generation capacity pursuant to a contract under the commissions Resolution E-4770 (March 17, 2016) that is in excess of the requirement of that electrical corporation under that resolution shall count towards meeting the electrical corporations proportionate share allocated pursuant to paragraph (1).
(f)The commission may direct each electrical corporation to develop standard contract terms and conditions that reflect the operational characteristics of the bioenergy projects and to provide a streamlined contracting process or may require the electrical corporations to use the mechanism established pursuant to the commissions Resolution E-4770 (March 17, 2016) to meet the requirements of subdivision (e). The procurement pursuant to the developed standard contract shall occur on an expedited basis due to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(g)A local publicly owned electric utility serving more than 100,000 customers shall procure its proportionate share, based on the ratio of the utilitys peak demand to the total statewide peak demand, of 125 megawatts of cumulative rated capacity from existing bioenergy projects described in subdivision (b) subject to terms of at least five years.
(h)The commission shall ensure that the costs of any contract procured by an electrical corporation to satisfy the requirements of this section are recoverable from all customers on a nonbypassable basis.
(i)The Procurement Review Group within the commission shall advise the commission on the cost of the generation procured pursuant to this section and its impact on ratepayers.
(j)For purposes of this section, any incremental procurement of electricity products from bioenergy resources by a new contract or contract extension of five years or longer in duration shall be from a resource that meets emission limits equivalent to, or more stringent than, the applicable best available retrofit control technology, as determined by the local air pollution control district or air quality management district. The determination shall be made before the start of the operating period under the new contract or contract extension.
SEC. 6.Section 5.5 of this bill incorporates amendments to Section 399.20.3 of the Public Utilities Code proposed by both this bill and Assembly Bill 2750. That section of this bill shall only become operative if (1) both bills are enacted and become effective on or before January 1, 2025, (2) each bill amends Section 399.20.3 of the Public Utilities Code, and (3) this bill is enacted after Assembly Bill 2750, in which case Section 5 of this bill shall not become operative.
Upon determining that this exemption is consistent with the purposes of this chapter, the board may exempt from this chapter, or portions of this chapter, a person engaged in forest management whose activities are limited to any of the following:
(a)The cutting or removal of trees for the purpose of constructing or maintaining a right-of-way for utility lines.
(b)The planting, growing, nurturing, shaping, shearing, removal, or harvest of immature trees for Christmas trees or other ornamental purposes or minor forest products, including fuelwood.
(c)The cutting or removal of dead, dying, or diseased trees of any size.
(d)Site preparation.
(e)Maintenance of drainage facilities and soil stabilization treatments.
(f)Timber operations on land managed by the Department of Parks and Recreation.
(g)(1)The one-time conversion of less than three acres to a nontimber use. A person, whether acting as an individual, as a member of a partnership, or as an officer or employee of a corporation or other legal entity, shall not obtain more than one exemption pursuant to this subdivision in a five-year period. If a partnership has as a member, or if a corporation or other legal entity has as an officer or employee, a person who has received this exemption within the past five years, whether as an individual, as a member of a partnership, or as an officer or employee of a corporation or other legal entity, then that partnership, corporation, or other legal entity is not eligible for this exemption. Person, for purposes of this subdivision, means an individual, partnership, corporation, or other legal entity.
(2)(A)Notwithstanding Section 4554.5, the board shall adopt regulations that do all of the following:
(i)Identify the required documentation of a bona fide intent to complete the conversion that an applicant will need to submit in order to be eligible for the exemption in paragraph (1).
(ii)Authorize the department to inspect the sites approved in conversion applications that have been approved on or after January 1, 2002, in order to determine that the conversion was completed within the two-year period described in subparagraph (B) of paragraph (2) of subdivision (a) of Section 1104.1 of Title 14 of the California Code of Regulations.
(iii)Require the exemption pursuant to this subdivision to expire if there is a change in timberland ownership. The person who originally submitted an application for an exemption pursuant to this subdivision shall notify the department of a change in timberland ownership on or before five calendar days after a change in ownership.
(iv)The board may adopt regulations allowing a waiver of the five-year limitation described in paragraph (1) upon finding that the imposition of the five-year limitation would impose an undue hardship on the applicant for the exemption. The board may adopt a process for an appeal of a denial of a waiver.
(v)The board may adopt regulations allowing a waiver of the one-time limitation described in paragraph (1) upon finding that the imposition of the one-time limitation would impose an undue hardship on the applicant. The board may adopt a process for an appeal of a denial of a waiver.
(B)The application form for the exemption pursuant to paragraph (1) shall prominently advise the public that a violation of the conversion exemption, including a conversion applied for in the name of someone other than the person or entity implementing the conversion in bona fide good faith, is a violation of this chapter and penalties may accrue up to ten thousand dollars ($10,000) for each violation pursuant to Article 8 (commencing with Section 4601).
(h)An easement granted by a right-of-way construction agreement administered by the federal government if timber sales and operations within or affecting the area are reviewed and conducted pursuant to the federal National Environmental Policy Act of 1969 (42 U.S.C. Sec. 4321 et seq.).
(i)(1)The cutting or removal of trees in compliance with Sections 4290 and 4291 that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break for a distance of not more than 150 feet on each side from an approved and legally permitted structure that complies with the California Building Standards Code, when that cutting or removal is conducted in compliance with this subdivision. For purposes of this subdivision, an approved and legally permitted structure includes only structures that are designed for human occupancy, garages, barns, stables, and structures used to enclose fuel tanks.
(2)(A)The cutting or removal of trees pursuant to this subdivision is limited to cutting or removal that will result in a reduction in the rate of fire spread, fire duration and intensity, fuel ignitability, or ignition of the tree crowns and shall be in accordance with any regulations adopted by the board pursuant to this section.
(B)Trees shall not be cut or removed pursuant to this subdivision by the clearcutting regeneration method, by the seed tree removal step of the seed tree regeneration method, or by the shelterwood removal step of the shelterwood regeneration method.
(3)(A)All fuel treatments conducted pursuant to this subdivision that do not comply with board rules and regulations may be determined to be a nuisance and subject to abatement by the department or the city or county having jurisdiction.
(B)The costs incurred by the department, city, or county, as the case may be, to abate the nuisance upon a parcel of land subject to the timber operations, including, but not limited to, investigation, boundary determination, measurement, and other related costs, may be recovered by special assessment and lien against the parcel of land by the department, city, or county. The assessment may be collected at the same time and in the same manner as ordinary ad valorem taxes, and shall be subject to the same penalties and the same procedure and sale in case of delinquency as is provided for ad valorem taxes.
(4)All timber operations conducted pursuant to this subdivision shall conform to applicable city or county general plans, city or county implementing ordinances, and city or county zoning ordinances. This paragraph does not authorize the cutting, removal, or sale of timber or other solid wood forest products within an area where timber harvesting is prohibited or otherwise restricted pursuant to the rules or regulations adopted by the board.
(5)(A)The board shall adopt regulations, initially as emergency regulations in accordance with subparagraph (B), that the board considers necessary to implement and to obtain compliance with this subdivision.
(B)The emergency regulations adopted pursuant to subparagraph (A) shall be adopted in accordance with the Administrative Procedure Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code). The adoption of emergency regulations shall be deemed to be an emergency and necessary for the immediate preservation of the public peace, health, and safety, or general welfare.
(j)(1)(A)The harvesting of trees, limited to those trees that eliminate the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns, for the purpose of reducing the rate of fire spread, duration and intensity, fuel ignitability, or ignition of tree crowns. An exemption pursuant to this paragraph shall be known as the Forest Resilience Exemption.
(B)The board may authorize an exemption pursuant to subparagraph (A) only if the tree harvesting will decrease fuel continuity and increase the quadratic mean diameter of the stand, and the tree harvesting area will not exceed 500 acres. Increases in quadratic mean diameter shall only consider trees greater than eight inches in diameter at breast height. The notice of exemption may be authorized only if all of the conditions specified in subparagraphs (C) to (I), inclusive, are met.
(C)A registered professional forester shall prepare the notice of exemption and submit it to the director.
(D)(i)The submitted notice of exemption shall include a description of the preharvest stand structure and a statement of the postharvest stand stocking levels and the expected postharvest increase in quadratic mean diameter.
(ii)The level of residual stocking shall be consistent with maximum sustained production of high-quality timber products. The residual stand shall consist primarily of healthy and vigorous dominant and codominant trees from the preharvest stand. Stocking shall not be reduced below the standards required by the following provisions that apply to the exemption at issue:
(I)Clauses 1 to 4, inclusive, of subparagraph (A) of paragraph (1) of subdivision (a) of Sections 913.3, 933.3, and 953.3 of Title 14 of the California Code of Regulations, or clauses 1 to 4, inclusive, of subparagraph (A) of paragraph (2) of subdivision (a) of Sections 913.2, 933.2, and 953.2 of Title 14 of the California Code of Regulations.
(II)The registered professional forester responsible for preparing the notice of exemption shall identify the designated postharvest stocking within the notice of exemption. The selected stocking shall be applicable to, and consistent with, silviculture that would apply to the preharvest stand condition provided pursuant to clause (i).
(III)Additional information on preharvest stand conditions, including, but not limited to, stand ages, stand structure, past management activities, and landowner goals and objectives shall also be provided by the registered professional forester preparing and submitting the exemption that substantiates the selection of postharvest stocking.
(iii)Within the coast district, if the preharvest dominant and codominant crown canopy is occupied by trees less than 14 inches in diameter at breast height, a minimum of 100 trees over 4 inches in diameter at breast height shall be retained per acre for Site I, II, and III lands, and a minimum of 75 trees over 4 inches in diameter at breast height shall be retained per acre for Site IV and V lands.
(iv)Within the northern district and southern district, if the preharvest dominant and codominant crown canopy is occupied by trees less than 14 inches in diameter at breast height, a minimum of 65 trees per acre over 4 inches in diameter at breast height shall be retained.
(v)All trees that are harvested or all trees that are retained shall be marked or sample marked by, or under the supervision of, a registered professional forester before felling operations begin. The board shall adopt regulations for sample marking for this section in Title 14 of the California Code of Regulations. Sample marking shall be limited to homogenous forest stand conditions typical of plantations.
(vi)The board may adopt specific regulations for the removal of dead and dying trees in amounts less than 10 percent of the average volume per acre for trees up to 36 inches in diameter at breast height. Regulations adopted by the board shall consider safety, fuel hazard abatement, mortality capture, the adequacy and retention of wildlife trees, especially those trees over 30 inches in diameter at breast height, and standards of enforceability for the department. All trees over 30 inches in diameter at breast height that are harvested pursuant to this paragraph shall be marked by, or under the supervision of, a registered professional forester before felling. The registered professional forester shall consult with the director before felling any dead or dying trees in excess of 30 inches in diameter at breast height.
(vii)All trees harvested pursuant to this paragraph shall be marked by, or under the supervision of, a registered professional forester before felling operations begin.
(viii)The six largest trees per acre within the boundaries of a notice of exemption submitted pursuant to this subdivision shall not be harvested.
(ix)No trees of the genus Quercus that are greater than 22 inches in diameter at breast height shall be harvested under a notice of exemption submitted pursuant to this subdivision, except for those trees that need to be removed to mitigate safety.
(x)The postharvest composition of tree species shall be representative of the preharvest stand condition and demonstrate progression towards climax forest conditions, unless the registered professional forester provides information explaining how modification of species diversity will benefit forest health and resiliency.
(E)(i)The board shall adopt regulations for the treatment of understory vegetation and standing dead fuels, canopy closure, clearance to base of live crown, or ladder fuels, that could promote the spread of wildfire.
(ii)Slash and woody debris within 50 feet of a public road or critical infrastructure, as defined by the board, shall be chipped, burned, or removed.
(iii)The standards required by clauses (i) and (ii) shall be achieved on approximately 80 percent of the treated area.
(F) Before the submission of a notice of exemption to the department, the registered professional forester responsible for submitting the notice shall designate temporary road locations, landing locations, tractor road crossings of Class III watercourses, unstable areas, or connected headwall swales on the ground and map their locations.
(G)The construction or reconstruction of temporary roads on slopes of 30 percent or less shall be allowed if all of the following conditions are met:
(i)Temporary roads or landings shall not be located on unstable areas, as defined in Section 895.1 of Title 14 of the California Code of Regulations.
(ii)Temporary roads shall be single-lane in width.
(iii)Temporary roads shall not be located across a connected headwall swale, as defined in Section 895.1 of Title 14 of the California Code of Regulations.
(iv)Construction or reconstruction of temporary roads, landings, or watercourse crossings shall not occur during the winter operating period. Pursuant to subdivision (g) of Sections 923.6, 943.6, and 963.6, as applicable, of Title 14 of the California Code of Regulations, roads and landings used for log hauling or other heavy equipment uses during the winter period shall occur on a stable operating surface and, where necessary, be surfaced with rock to a depth and quantity sufficient to maintain the stable operating surface. Use shall be prohibited on roads that are not hydrologically disconnected and exhibit saturated soil conditions. Timber operations during the winter period shall comply with paragraphs (1) and (2) of subdivision (c) of Sections 914.7, 934.7, and 954.7, as applicable, of Title 14 of the California Code of Regulations.
(v)Use of temporary roads shall comply with the operational provisions of Article 12 (commencing with Section 923) of Subchapter 4 of Chapter 4 of Division 1.5 of Title 14 of the California Code of Regulations, and recognize guidance on hydrologic disconnection in Technical Rule Addendum Number 5.
(vi)No logging road or landings construction or reconstruction activities of any kind shall occur within 200 feet of Class I and Class II watercourses or within 50 feet of a Class III watercourse.
(vii)The landowner shall retain a registered professional forester who is available to provide professional advice to the licensed timber operator and timberland owner throughout the active timber operations. The name, address, telephone number, and registration number of the retained registered professional forester shall be provided on the submitted notice of exemption. This professional advice shall include overseeing the construction or reconstruction of any temporary roads or landings and advising on necessary mitigation to avoid potential impacts to associated watershed and forest resources. The registered professional forester shall also comply with Section 1035.2 of Title 14 of the California Code of Regulations, relating to interaction between the licensed timber operator and the registered professional forester.
(viii)The registered professional forester responsible for submitting the notice of exemption shall affirm that the construction or reconstruction of each temporary road is necessary to provide access to harvest areas where no feasible alternative exists. The submitted notice of exemption shall include the number and cumulative length of temporary roads that will be constructed or reconstructed.
(ix)(I)Temporary road construction or reconstruction shall be limited to no more than two miles of road per ownership in a planning watershed per any five-year period.
(II)For each exemption affecting less than 40 acres, all temporary roads constructed or reconstructed under this exemption shall not exceed a cumulative length of 300 feet.
(III)For each exemption affecting between 40 and 80 acres, all temporary roads constructed or reconstructed under this exemption shall not exceed a cumulative length of between 300 and 600 feet, as determined on a pro rata basis by the total acreage affected by the exemption.
(IV)For each exemption affecting over 80 acres, all temporary roads constructed or reconstructed under the exemption shall not exceed a cumulative length of 600 feet. The submitted notice of exemption shall list the number of acres affected and the cumulative length of the road in feet.
(V)Temporary roads constructed or reconstructed under this exemption shall not be connected to other temporary roads constructed under previous or subsequent exemptions filed under this paragraph.
(VI)All temporary roads shall be abandoned using proactive measures that have been applied to effectively remove them from the permanent road network, in accordance with the definition of abandoned road as defined in Section 895.1 of Title 14 of the California Code of Regulations.
(VII)This paragraph shall not be interpreted to permit road construction or reconstruction except as authorized under the Forest Resilience Exemption, pursuant to this subparagraph.
(VIII)No trees larger than 30 inches in diameter at breast height shall be removed for the purposes of road construction or reconstruction under a notice of exemption submitted pursuant to this subdivision.
(H)Only trees less than 30 inches in diameter at breast height may be removed. The board, in consultation with the department, shall develop clearly written guidance documents on inspection and enforceability standards relating to standards set forth in this paragraph.
(I)All timber operations conducted pursuant to this subdivision shall only occur within the most recent version of the departments Fire Hazard Severity Zone Map in the moderate, high, and very high fire threat zones.
(J)If pesticides or herbicides will be used within the boundaries of an area covered by a notice of exemption pursuant to this subparagraph within one year of director acceptance, the timberland owner shall notify the appropriate regional water quality control board 10 days before application of any pesticides or herbicides.
(K)After the timber operations are complete, the department shall conduct an onsite inspection to determine compliance with this subdivision and whether appropriate enforcement action should be initiated. The department shall notify the appropriate regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey seven days prior to conducting the onsite inspection. The regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey may conduct an inspection with the department.
(2)(A)The board shall adopt regulations, initially as emergency regulations in accordance with subparagraph (B), that the board considers necessary to implement and to obtain compliance with this subdivision.
(B)The emergency regulations adopted pursuant to subparagraph (A) shall be adopted in accordance with the Administrative Procedure Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code). The adoption of emergency regulations shall be deemed to be an emergency and necessary for the immediate preservation of the public peace, health, and safety, or general welfare.
(3)This subdivision shall become inoperative on January 1, 2031.
(k)(1)The cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands, if all of the following requirements are met:
(A)A registered professional forester shall prepare the notice of exemption and submit it to the director. The notice shall include both of the following:
(i)A certification signed by the registered professional forester that the timber operation is designed to restore and conserve California black and Oregon white oak woodlands and associated grasslands encroached upon by conifers and that a minimum of 35 square feet of basal area per acre, or as determined by the board, of California black or Oregon white oak, or both, occupy the proposed treatment area at the time the notice is prepared.
(ii)A description of the preharvest stand structure and a statement of the postharvest stand stocking levels.
(B)No tree larger than 30 inches in diameter at breast height shall be harvested for commercial purposes. If necessary to achieve the oak woodland restoration goal of the exemption, trees larger than 30 inches in diameter at breast height may be harvested. The registered professional forester shall provide information on the need to remove these trees, and consult with the director before felling any tree in excess of 30 inches in diameter at breast height.
(C)Only conifers within 300 feet of a California black or Oregon white oak may be harvested.
(D)The total area exempted pursuant to this subdivision shall not exceed 300 acres per ownership in a planning watershed per five-year period.
(E)Conifer shall be reduced to less than 25 percent of the combined hardwood and conifer postharvest stand stocking levels. Decadent and deformed trees of wildlife value that are retained shall not count toward basal area requirements.
(F)No more than 20 percent of the total basal area of preexisting oak stock shall be cut or removed during harvest. The board may establish minimum postharvest basal area requirements for California black or Oregon white oak.
(G)Slash shall be configured to minimize the risk of fire mortality to the remaining oak trees.
(2)(A)The board shall adopt regulations, initially as emergency regulations in accordance with subparagraph (B), that the board considers necessary to implement and to obtain compliance with this subdivision.
(B)The emergency regulations adopted pursuant to subparagraph (A) shall be adopted in accordance with the Administrative Procedure Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code). The adoption of emergency regulations shall be deemed to be an emergency and necessary for the immediate preservation of the public peace, health, and safety, or general welfare.
(l)(1)The board may exempt from this chapter, or portions of this chapter, a person engaged in forest management whose activities are limited to the cutting or removal of trees on the persons property in compliance with Sections 4290 and 4291 that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break for a distance of not more than 300 feet on each side from an approved and legally permitted habitable structure, when that cutting or removal is conducted in compliance with this subdivision and all of the following conditions are met:
(A)The notice of exemption is prepared, signed, and submitted by a registered professional forester to the department.
(B)For the areas between 150 and 300 feet from the habitable structure, the operations meet all of the following provisions:
(i)The residual stocking standards are consistent with Sections 913.2, 933.2, and 953.2 of Title 14 of the California Code of Regulations, as appropriate.
(ii)Activities within this area will increase the quadratic mean diameter of the stand.
(iii)The residual stand consists primarily of healthy and vigorous dominant and codominant trees from the preharvest stand, well distributed throughout the harvested area.
(iv)Postharvest slash treatment and stand conditions will lead to more moderate fire behavior in the professional judgment of the registered professional forester who submits the notice of exemption.
(v)Any additional guidance for slash treatment and postharvest stand conditions and any other issues deemed necessary that are consistent with this section, as established by the board.
(2)For purposes of this subdivision, habitable structure means a building that contains one or more dwelling units or that can be occupied for residential use. Buildings occupied for residential use include single-family homes, multidwelling structures, mobile and manufactured homes, and condominiums. For purposes of this subdivision, habitable structure does not include commercial, industrial, or incidental buildings such as detached garages, barns, outdoor sanitation facilities, and sheds.
(3)This subdivision shall become inoperative on January 1, 2031.
SEC. 2.Section 4584.1 of the Public Resources Code is amended to read:4584.1.Rules and regulations adopted by the board pursuant to Section 4584, except subdivision (k) of Section 4584, shall comply with the following standards, as determined appropriate and necessary by the board:
(a)Notices of exemption that are prepared and submitted to the director shall include a map of the area of operations that complies with the requirements of paragraphs (1), (3), and (4), subparagraphs (A), (B), (D), and (E) of paragraph (5), paragraphs (7) to (12), inclusive, and paragraph (14) of subdivision (x) of Section 1034 of Title 14 of the California Code of Regulations.
(b)Notices of exemption that are prepared and submitted to the director shall provide a confidential archaeological letter that includes all the information required by paragraphs (2) and (7) to (11), inclusive, of subdivision (c) of Sections 929.1, 949.1 and 969.1, as applicable, of Title 14 of the California Code of Regulations, and site records if required pursuant to subdivision (g) of that section or pursuant to Section 929.5 of Title 14 of the California Code of Regulations. This subdivision shall not apply to activities described in subdivision (i) or (m) of Section 4584.
(c)All fuel treatments required by the board shall be completed within one year from the date the director receives the notice, with the exception of burning. This shall include treatment of surface fuels, wood debris, and slash, which shall be lopped, removed, chipped, piled for burning, or otherwise treated. Burning shall be completed within two years from the date the director receives the notice of exemption.
(d)Slash and woody debris shall be treated to achieve a maximum postharvest depth of 18 inches above the ground except within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code. Surface fuels, slash, and woody debris within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code shall be chipped, piled, and burned, or removed.
(e)Timber operations shall comply with the requirements of paragraphs (1) to (10), inclusive, of subdivision (b) of Section 1038 of Title 14 of the California Code of Regulations.
(f)All timber operations conducted in Lake Tahoe Region shall have a valid Tahoe Basin Tree Removal Permit, as defined by the Tahoe Regional Planning Agency (TRPA), or shall be conducted under a valid TRPA Memorandum of Understanding, when such a permit is required by TRPA.
(g)The submitted notice of exemption shall include selection criteria for the trees to be harvested or the trees to be retained.
(h)The department shall provide the appropriate regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey with copies of notices of exemption when they are submitted.
(i)The submitted notice of exemption shall include the tentative commencement date of timber operations.
(j)Within a 15-day period, the registered professional forester or person responsible for the submittal of the notice of exemption shall notify the department, the Department of Fish and Wildlife, the appropriate regional water quality control board, and the California Geologic Survey of the actual date of commencement of timber operations.
(k)Timber operations pursuant to an exemption may not commence for 10 working days from the date of the directors receipt of the notice of exemption unless this delay is waived by the director. The director shall determine whether the notice of exemption is complete, and if so, shall send a copy of a notice of acceptance to the submitter. If the notice of exemption is not complete and accurate, it shall be returned to the submitter and the timber operator may not proceed. If the director does not act within 10 days of receipt of the notice of exemption, timber operations may commence.
(l)(1)No large old trees, defined as a tree that existed before 1800 AD or is greater than 60 inches in diameter at stump height for Sierra or Coast Redwoods, and 48 inches in diameter at stump height for all other tree species or Decadent and Deformed Trees with Value to Wildlife, as defined in Section 895.1 of Title 14 of the California Code of Regulations, shall be harvested unless the following apply:
(A)The tree is not critical for the maintenance of a Late Successional Stand.
(B)A registered professional forester attached to the submitted notice of exemption a written explanation and justification for the harvest of the tree based on the registered professional foresters finding of any of the following:
(i)The tree is a hazard to safety or property.
(ii)The removal of the tree is necessary for the construction of a building as approved by the appropriate local jurisdiction and shown on the county or city approved site plan, which shall be attached to the submitted notice of exemption.
(iii)The tree is dead or likely to die within one year of the date of the proposed removal, as determined by a registered professional forester.
(2)A registered professional forester-written explanation or justification need not be attached to the submitted notice of exemption if an approved Habitat Conservation Plan, Sustained Yield Plan, or plan, as that term is defined in Section 895.1 of Title 14 of the California Code of Regulations addresses large old tree retention for the area in which the large old tree is proposed for removal and the removal is in compliance with the retention standards of that document.
(3)Any tree harvested pursuant to this subdivision shall be shown on a map provided with the submitted notice of exemption to the department.
(4)This subdivision shall not apply to or be used in conjunction with the Forest Resilience Exemption created pursuant to subdivision (j) of Section 4584.
(m)Helicopter yarding shall be prohibited.
(n)All applicable provisions of the Professional Foresters Law, including, but not limited to, Sections 775 to 779, inclusive, of this code, as well as all applicable provisions of Registration of Professional Forester Rules, including, but not limited to, Sections 1612 to 1614, inclusive, of Title 14 of the California Code of Regulations, shall apply to the practice of professional forestry as it relates to this section.
SEC. 3.Section 4584.2 of the Public Resources Code is amended to read:4584.2.Rules and regulations adopted by the board pursuant to subdivision (j) of Section 4584, shall comply with the following standards:
(a)Notices of exemption that are prepared and submitted to the director shall include a map of the area of operations that complies with the requirements of paragraphs (1), (3), and (4), subparagraphs (A), (B), (D), and (E) of paragraph (5), paragraphs (7) to (12), inclusive, and paragraph (14) of subdivision (x) of Section 1034 of Title 14 of the California Code of Regulations.
(b)Notices of exemption that are prepared and submitted to the director shall provide a confidential archaeological letter that includes all the information required by paragraphs (2) and (7) to (11), inclusive, of subdivision (c) of Sections 929.1, 949.1 and 969.1, as applicable, of Title 14 of the California Code of Regulations, and site records if required pursuant to subdivision (g) of that section or pursuant to Section 929.5 of Title 14 of the California Code of Regulations.
(c)All fuel treatments required by the board shall be completed within one year from the date the director receives the notice, with the exception of burning. This shall include treatment of surface fuels, wood debris, and slash, which shall be lopped, removed, chipped, piled for burning, or otherwise treated. Burning shall be completed within two years from the date the director receives the notice of exemption.
(d)Slash and woody debris shall be treated to achieve a maximum postharvest depth of 18 inches above the ground except within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code. Surface fuels, slash, and woody debris within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code shall be chipped, burned, or removed.
(e)Timber operations shall comply with the requirements of paragraphs (1) to (4), inclusive, and (6) to (10), inclusive, of subdivision (b) of Section 1038 of Title 14 of the California Code of Regulations.
(f)All timber operations conducted in Lake Tahoe Region must have a valid Tahoe Basin Tree Removal Permit, as defined by the Tahoe Regional Planning Agency (TRPA), or shall be conducted under a valid TRPA Memorandum of Understanding, when such a permit is required by TRPA.
(g)The submitted notice of exemption shall include selection criteria for the trees to be harvested or the trees to be retained.
(h)The department shall provide the appropriate regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey with copies of notices of exemption when they are submitted.
(i)The submitted notice of exemption shall include the tentative commencement date of timber operations.
(j)Within a 15-day period, the registered professional forester responsible for the submittal of the notice of exemption shall notify the department, the Department of Fish and Wildlife, the appropriate regional water quality control board, and the California Geologic Survey of the actual date of commencement of timber operations.
(k)Operations pursuant to an exemption may not commence for 10 working days from the date of the directors receipt of the notice of exemption unless this delay is waived by the director. The director shall determine whether the notice of exemption is complete, and if so, shall send a copy of a notice of acceptance to the submitter. If the notice of exemption is not complete and accurate, it shall be returned to the submitter and the timber operator may not proceed. If the director does not act within five days of receipt of the notice of exemption, timber operations may commence.
(l)(1)No Decadent and Deformed Trees with Value to Wildlife, as defined in Section 895.1 of Title 14 of the California Code of Regulations, shall be harvested unless all the following apply:
(A)The tree is not critical for the maintenance of a Late Successional Stand.
(B)A registered professional forester attached to the submitted notice of exemption a written explanation and justification for the harvest of the tree based on the registered professional foresters finding of any of the following:
(i)The tree is a hazard to safety or property.
(ii)The removal of the tree is necessary for the construction of a building as approved by the appropriate local jurisdiction and shown on the county or city approved site plan which shall be attached to the submitted notice of exemption.
(iii)The tree is dead or likely to die within one year of the date of the proposed removal, as determined by a registered professional forester.
(2)A registered professional foresters written explanation or justification need not be attached to the submitted notice of exemption if an approved Habitat Conservation Plan, Sustained Yield Plan, or plan as that term is defined in Section 895.1 of Title 14 of the California Code of Regulations addresses large old tree retention for the area in which the large old tree is proposed for removal and the removal is in compliance with the retention standards of that document.
(3)Any tree harvested pursuant to this subdivision shall be shown on a map provided with the submitted notice of exemption to the department.
(4)This subdivision shall not apply to or be used in conjunction with the Forest Resilience Exemption created pursuant to subdivision (j) of Section 4584.
(m)Helicopter yarding shall be prohibited.
(n)All applicable provisions of the Professional Foresters Law, including, but not limited to, Sections 775 to 779, inclusive, of this code, as well as all applicable provisions of Registration of Professional Forester Rules, including, but not limited to, Sections 1612 to 1614, inclusive, of Title 14 of the California Code of Regulations apply to the practice of professional forestry as it relates to this section.
SEC. 4.Section 4589 of the Public Resources Code is amended to read:4589.(a)The department and board, in consultation with the Department of Fish and Wildlife, and the State Water Resources Control Board, shall, commencing December 31, 2019, and annually thereafter, review and submit a report to the Legislature on the trends in the use of, compliance with, and effectiveness of, the exemptions and emergency notice provisions described in Sections 4584 and 4592 of this code and Sections 1038 and 1052 of Title 14 of the California Code of Regulations. The report shall include an analysis of exemption use and whether the exemptions are having the intended effect. The report shall also include recommendations to improve the use of those exemptions and emergency notice provisions, information on the linear distance of road constructed or reconstructed under notices of exemption by individual ownerships, within a representative sample of planning watersheds from each forest practice district as defined in Sections 907 to 909, inclusive, of Title 14 of the California Code of Regulations, and violations associated with road reconstruction. The report shall include information on the number and type of violations and enforcement actions taken on each notice of exemption and emergency notice. The report shall also contain the number of posttreatment onsite inspections that occur and whether those inspections were attended by a representative of the Department of Fish and Wildlife and a representative of the State Water Resources Control Board. The report submitted on December 31, 2025, shall include recommendations necessary for revisions to diameter limits at stump heights of harvestable trees under subdivisions (j) and (k) of Section 4584, as those subdivisions read on January 1, 2024.
(b)The public shall be provided opportunities to participate in the review and the development of the report.
(c)The report shall be submitted pursuant to Section 9795 of the Government Code.
(d)(A)This section shall be operative for a period of five years after the effective date of emergency regulations as adopted by the board and as of that date is inoperative.
(B)The board shall notify the Secretary of State when emergency regulations have been adopted.
SEC. 5.Section 399.20.3 of the Public Utilities Code is amended to read:399.20.3.(a)For purposes of this section, the following definitions apply:
(1)Bioenergy has the same meaning as set forth in paragraph (6) of subdivision (f) of Section 399.20.
(2)Tier 1 high hazard zone includes areas where wildlife and falling trees threaten electrical transmission and distribution lines, roads, and other evacuation corridors, critical community infrastructure, or other existing structures, as designated by the Department of Forestry and Fire Protection pursuant to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(3)Tier 2 high hazard zone includes watersheds that have significant tree mortality combined with community and natural resource assets, as designated by the Department of Forestry and Fire Protection pursuant to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(b)(1)In addition to the requirements of subdivision (f) of Section 399.20, by December 1, 2023, electrical corporations shall collectively procure, through financial commitments of 5 to 15 years, inclusive, their proportionate share of 125 megawatts of cumulative rated generating capacity from existing bioenergy projects that commenced operations before June 1, 2013. At least 80 percent of the feedstock of an eligible facility, on an annual basis, shall be a byproduct of sustainable forestry management, which includes removal of dead and dying trees from Tier 1 and Tier 2 high hazard zones and is not that from lands that have been clear cut. At least 60 percent of this feedstock shall be from Tier 1 and Tier 2 high hazard zones.
(2)Paragraph (1) shall not apply to a utility subject to subdivision (g) if both of the following apply:
(A)The utility, either directly or through a joint powers authority, entered into five-year financial commitments for its proportionate share of 125 megawatts of cumulative rated generating capacity from existing bioenergy projects pursuant to this section as it was enacted by Chapter 368 of the Statutes of 2016.
(B)The utilitys financial commitments referenced in subparagraph (A) include, (1) a contract with a facility operator that was, on June 1, 2022, in a bankruptcy or other insolvency proceeding, or (2) a contract for a project that does not deliver energy to the utility.
(c)For the purpose of contracts entered into pursuant to subdivision (b), commission Resolution E-4770 (March 17, 2016), and commission Resolution E-4805 (October 13, 2016), Tier 1 and Tier 2 high hazard zone fuel or feedstock shall also include biomass fuels removed from fuel reduction operations exempt from timber harvesting plan requirements pursuant to subdivisions (a), (f), (j), and (k) of Section 4584 of the Public Resources Code, as those subdivisions read on January 1, 2024.
(d)The commission shall require an electrical corporation that has entered into a contract pursuant to subdivision (b), commission Resolution E-4770 (March 17, 2016), or commission Resolution E-4805 (October 13, 2016) to allow fuel or feedstock reporting requirements to be based on a monthly or annual basis, and a bioenergy facility providing generation pursuant to that contract shall have the right to opt out of the mandated fuel or feedstock usage levels in any particular month upon providing written notice to the electrical corporation in the month of operation. For months in which a bioenergy facility opts out of the mandated fuel or feedstock usage levels or misses the mandated fuel or feedstock targets, that facility shall be paid the alternate price adopted by the commission in commission Resolution E-4770 for all megawatthours generated during that month. Contracts shall continue in force through the end of the contracted term without creating an event of default for missing mandated fuel or feedstock usage levels and without giving rise to a termination right in favor of the electrical corporation.
(e)(1)For each electrical corporation, the commission shall allocate its proportionate share of the 125 megawatts based on the ratio of the electrical corporations peak demand to the total statewide peak demand.
(2)Procurement by an electrical corporation of generation capacity pursuant to a contract under the commissions Resolution E-4770 (March 17, 2016) that is in excess of the requirement of that electrical corporation under that resolution shall count towards meeting the electrical corporations proportionate share allocated pursuant to paragraph (1).
(f)The commission may direct each electrical corporation to develop standard contract terms and conditions that reflect the operational characteristics of the bioenergy projects and to provide a streamlined contracting process or may require the electrical corporations to use the mechanism established pursuant to the commissions Resolution E-4770 (March 17, 2016) to meet the requirements of subdivision (e). The procurement pursuant to the developed standard contract shall occur on an expedited basis due to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(g)A local publicly owned electric utility serving more than 100,000 customers shall procure its proportionate share, based on the ratio of the utilitys peak demand to the total statewide peak demand, of 125 megawatts of cumulative rated capacity from existing bioenergy projects described in subdivision (b) subject to terms of at least five years.
(h)The commission shall ensure that the costs of any contract procured by an electrical corporation to satisfy the requirements of this section are recoverable from all customers on a nonbypassable basis.
(i)The Procurement Review Group within the commission shall advise the commission on the cost of the generation procured pursuant to this section and its impact on ratepayers.
(j)For purposes of this section, any incremental procurement of electricity products from bioenergy resources by a new contract or contract extension of five years or longer in duration shall be from a resource that meets emission limits equivalent to, or more stringent than, the applicable best available retrofit control technology, as determined by the local air pollution control district or air quality management district. The determination shall be made before the start of the operating period under the new contract or contract extension.
SEC. 5.5.Section 399.20.3 of the Public Utilities Code is amended to read:399.20.3.(a)For purposes of this section, the following definitions apply:
(1)Bioenergy has the same meaning as set forth in paragraph (6) of subdivision (f) of Section 399.20.
(2)Tier 1 high hazard zone includes areas where wildlife and falling trees threaten electrical transmission and distribution lines, roads, and other evacuation corridors, critical community infrastructure, or other existing structures, as designated by the Department of Forestry and Fire Protection pursuant to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(3)Tier 2 high hazard zone includes watersheds that have significant tree mortality combined with community and natural resource assets, as designated by the Department of Forestry and Fire Protection pursuant to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(b)(1)In addition to the requirements of subdivision (f) of Section 399.20, by December 1, 2023, on or before July 1, 2025, electrical corporations shall collectively procure, through financial commitments of 5 to 15 years, inclusive, their proportionate share of 125 megawatts of cumulative rated generating capacity from existing bioenergy projects that commenced operations before June 1, 2013. At least 80 percent of the feedstock of an eligible facility, on an annual basis, shall be a byproduct of sustainable forestry management, which includes removal of dead and dying trees from Tier 1 and Tier 2 high hazard zones and is not that from lands that have been clear cut. At least 60 percent of this feedstock shall be from Tier 1 and Tier 2 high hazard zones.
(2)Paragraph (1) shall does not apply to a utility subject to subdivision (g) if both of the following apply:
(A)The utility, either directly or through a joint powers authority, entered into five-year financial commitments for its proportionate share of 125 megawatts of cumulative rated generating capacity from existing bioenergy projects pursuant to this section as it was enacted by Chapter 368 of the Statutes of 2016.
(B)The utilitys financial commitments referenced in subparagraph (A) include, (1) include either: (i) a contract with a facility operator that was, on June 1, 2022, in a bankruptcy or other insolvency proceeding, or (2) proceeding; or (ii) a contract for a project that does not deliver energy to the utility.
(c)For the purpose of contracts entered into pursuant to subdivision (b), commission Resolution E-4770 (March 17, 2016), and commission Resolution E-4805 (October 13, 2016), Tier 1 and Tier 2 high hazard zone fuel or feedstock shall also include biomass fuels removed from fuel reduction operations exempt from timber harvesting plan requirements pursuant to subdivisions (a), (f), (j), and (k) of Section 4584 of the Public Resources Code. Code, as those subdivisions read on January 1, 2024.
(d)The commission shall require an electrical corporation that has entered into a contract pursuant to subdivision (b), commission Resolution E-4770 (March 17, 2016), or commission Resolution E-4805 (October 13, 2016) to allow fuel or feedstock reporting requirements to be based on a monthly or annual basis, and a bioenergy facility providing generation pursuant to that contract shall have the right to opt out of the mandated fuel or feedstock usage levels in any particular month upon providing written notice to the electrical corporation in the month of operation. For months in which a bioenergy facility opts out of the mandated fuel or feedstock usage levels or misses the mandated fuel or feedstock targets, that facility shall be paid the alternate price adopted by the commission in commission Resolution E-4770 for all megawatthours generated during that month. Contracts shall continue in force through the end of the contracted term without creating an event of default for missing mandated fuel or feedstock usage levels and without giving rise to a termination right in favor of the electrical corporation.
(e)(1)For each electrical corporation, the commission shall allocate its proportionate share of the 125 megawatts based on the ratio of the electrical corporations peak demand to the total statewide peak demand.
(2)Procurement by an electrical corporation of generation capacity pursuant to a contract under the commissions Resolution E-4770 (March 17, 2016) that is in excess of the requirement of that electrical corporation under that resolution shall count towards meeting the electrical corporations proportionate share allocated pursuant to paragraph (1).
(f)The commission may direct each electrical corporation to develop standard contract terms and conditions that reflect the operational characteristics of the bioenergy projects and to provide a streamlined contracting process or may require the electrical corporations to use the mechanism established pursuant to the commissions Resolution E-4770 (March 17, 2016) to meet the requirements of subdivision (e). The procurement pursuant to the developed standard contract shall occur on an expedited basis due to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(g)A local publicly owned electric utility serving more than 100,000 customers shall procure its proportionate share, based on the ratio of the utilitys peak demand to the total statewide peak demand, of 125 megawatts of cumulative rated capacity from existing bioenergy projects described in subdivision (b) subject to terms of at least five years.
(h)The commission shall ensure that the costs of any contract procured by an electrical corporation to satisfy the requirements of this section are recoverable from all customers on a nonbypassable basis.
(i)The Procurement Review Group within the commission shall advise the commission on the cost of the generation procured pursuant to this section and its impact on ratepayers.
(j)For purposes of this section, any incremental procurement of electricity products from bioenergy resources by a new contract or contract extension of five years or longer in duration shall be from a resource that meets emission limits equivalent to, or more stringent than, the applicable best available retrofit control technology, as determined by the local air pollution control district or air quality management district. The determination shall be made before the start of the operating period under the new contract or contract extension.
SEC. 6.Section 5.5 of this bill incorporates amendments to Section 399.20.3 of the Public Utilities Code proposed by both this bill and Assembly Bill 2750. That section of this bill shall only become operative if (1) both bills are enacted and become effective on or before January 1, 2025, (2) each bill amends Section 399.20.3 of the Public Utilities Code, and (3) this bill is enacted after Assembly Bill 2750, in which case Section 5 of this bill shall not become operative.
Upon determining that this exemption is consistent with the purposes of this chapter, the board may exempt from this chapter, or portions of this chapter, a person engaged in forest management whose activities are limited to any of the following:
(a)The cutting or removal of trees for the purpose of constructing or maintaining a right-of-way for utility lines.
(b)The planting, growing, nurturing, shaping, shearing, removal, or harvest of immature trees for Christmas trees or other ornamental purposes or minor forest products, including fuelwood.
(c)The cutting or removal of dead, dying, or diseased trees of any size.
(d)Site preparation.
(e)Maintenance of drainage facilities and soil stabilization treatments.
(f)Timber operations on land managed by the Department of Parks and Recreation.
(g)(1)The one-time conversion of less than three acres to a nontimber use. A person, whether acting as an individual, as a member of a partnership, or as an officer or employee of a corporation or other legal entity, shall not obtain more than one exemption pursuant to this subdivision in a five-year period. If a partnership has as a member, or if a corporation or other legal entity has as an officer or employee, a person who has received this exemption within the past five years, whether as an individual, as a member of a partnership, or as an officer or employee of a corporation or other legal entity, then that partnership, corporation, or other legal entity is not eligible for this exemption. Person, for purposes of this subdivision, means an individual, partnership, corporation, or other legal entity.
(2)(A)Notwithstanding Section 4554.5, the board shall adopt regulations that do all of the following:
(i)Identify the required documentation of a bona fide intent to complete the conversion that an applicant will need to submit in order to be eligible for the exemption in paragraph (1).
(ii)Authorize the department to inspect the sites approved in conversion applications that have been approved on or after January 1, 2002, in order to determine that the conversion was completed within the two-year period described in subparagraph (B) of paragraph (2) of subdivision (a) of Section 1104.1 of Title 14 of the California Code of Regulations.
(iii)Require the exemption pursuant to this subdivision to expire if there is a change in timberland ownership. The person who originally submitted an application for an exemption pursuant to this subdivision shall notify the department of a change in timberland ownership on or before five calendar days after a change in ownership.
(iv)The board may adopt regulations allowing a waiver of the five-year limitation described in paragraph (1) upon finding that the imposition of the five-year limitation would impose an undue hardship on the applicant for the exemption. The board may adopt a process for an appeal of a denial of a waiver.
(v)The board may adopt regulations allowing a waiver of the one-time limitation described in paragraph (1) upon finding that the imposition of the one-time limitation would impose an undue hardship on the applicant. The board may adopt a process for an appeal of a denial of a waiver.
(B)The application form for the exemption pursuant to paragraph (1) shall prominently advise the public that a violation of the conversion exemption, including a conversion applied for in the name of someone other than the person or entity implementing the conversion in bona fide good faith, is a violation of this chapter and penalties may accrue up to ten thousand dollars ($10,000) for each violation pursuant to Article 8 (commencing with Section 4601).
(h)An easement granted by a right-of-way construction agreement administered by the federal government if timber sales and operations within or affecting the area are reviewed and conducted pursuant to the federal National Environmental Policy Act of 1969 (42 U.S.C. Sec. 4321 et seq.).
(i)(1)The cutting or removal of trees in compliance with Sections 4290 and 4291 that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break for a distance of not more than 150 feet on each side from an approved and legally permitted structure that complies with the California Building Standards Code, when that cutting or removal is conducted in compliance with this subdivision. For purposes of this subdivision, an approved and legally permitted structure includes only structures that are designed for human occupancy, garages, barns, stables, and structures used to enclose fuel tanks.
(2)(A)The cutting or removal of trees pursuant to this subdivision is limited to cutting or removal that will result in a reduction in the rate of fire spread, fire duration and intensity, fuel ignitability, or ignition of the tree crowns and shall be in accordance with any regulations adopted by the board pursuant to this section.
(B)Trees shall not be cut or removed pursuant to this subdivision by the clearcutting regeneration method, by the seed tree removal step of the seed tree regeneration method, or by the shelterwood removal step of the shelterwood regeneration method.
(3)(A)All fuel treatments conducted pursuant to this subdivision that do not comply with board rules and regulations may be determined to be a nuisance and subject to abatement by the department or the city or county having jurisdiction.
(B)The costs incurred by the department, city, or county, as the case may be, to abate the nuisance upon a parcel of land subject to the timber operations, including, but not limited to, investigation, boundary determination, measurement, and other related costs, may be recovered by special assessment and lien against the parcel of land by the department, city, or county. The assessment may be collected at the same time and in the same manner as ordinary ad valorem taxes, and shall be subject to the same penalties and the same procedure and sale in case of delinquency as is provided for ad valorem taxes.
(4)All timber operations conducted pursuant to this subdivision shall conform to applicable city or county general plans, city or county implementing ordinances, and city or county zoning ordinances. This paragraph does not authorize the cutting, removal, or sale of timber or other solid wood forest products within an area where timber harvesting is prohibited or otherwise restricted pursuant to the rules or regulations adopted by the board.
(5)(A)The board shall adopt regulations, initially as emergency regulations in accordance with subparagraph (B), that the board considers necessary to implement and to obtain compliance with this subdivision.
(B)The emergency regulations adopted pursuant to subparagraph (A) shall be adopted in accordance with the Administrative Procedure Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code). The adoption of emergency regulations shall be deemed to be an emergency and necessary for the immediate preservation of the public peace, health, and safety, or general welfare.
(j)(1)(A)The harvesting of trees, limited to those trees that eliminate the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns, for the purpose of reducing the rate of fire spread, duration and intensity, fuel ignitability, or ignition of tree crowns. An exemption pursuant to this paragraph shall be known as the Forest Resilience Exemption.
(B)The board may authorize an exemption pursuant to subparagraph (A) only if the tree harvesting will decrease fuel continuity and increase the quadratic mean diameter of the stand, and the tree harvesting area will not exceed 500 acres. Increases in quadratic mean diameter shall only consider trees greater than eight inches in diameter at breast height. The notice of exemption may be authorized only if all of the conditions specified in subparagraphs (C) to (I), inclusive, are met.
(C)A registered professional forester shall prepare the notice of exemption and submit it to the director.
(D)(i)The submitted notice of exemption shall include a description of the preharvest stand structure and a statement of the postharvest stand stocking levels and the expected postharvest increase in quadratic mean diameter.
(ii)The level of residual stocking shall be consistent with maximum sustained production of high-quality timber products. The residual stand shall consist primarily of healthy and vigorous dominant and codominant trees from the preharvest stand. Stocking shall not be reduced below the standards required by the following provisions that apply to the exemption at issue:
(I)Clauses 1 to 4, inclusive, of subparagraph (A) of paragraph (1) of subdivision (a) of Sections 913.3, 933.3, and 953.3 of Title 14 of the California Code of Regulations, or clauses 1 to 4, inclusive, of subparagraph (A) of paragraph (2) of subdivision (a) of Sections 913.2, 933.2, and 953.2 of Title 14 of the California Code of Regulations.
(II)The registered professional forester responsible for preparing the notice of exemption shall identify the designated postharvest stocking within the notice of exemption. The selected stocking shall be applicable to, and consistent with, silviculture that would apply to the preharvest stand condition provided pursuant to clause (i).
(III)Additional information on preharvest stand conditions, including, but not limited to, stand ages, stand structure, past management activities, and landowner goals and objectives shall also be provided by the registered professional forester preparing and submitting the exemption that substantiates the selection of postharvest stocking.
(iii)Within the coast district, if the preharvest dominant and codominant crown canopy is occupied by trees less than 14 inches in diameter at breast height, a minimum of 100 trees over 4 inches in diameter at breast height shall be retained per acre for Site I, II, and III lands, and a minimum of 75 trees over 4 inches in diameter at breast height shall be retained per acre for Site IV and V lands.
(iv)Within the northern district and southern district, if the preharvest dominant and codominant crown canopy is occupied by trees less than 14 inches in diameter at breast height, a minimum of 65 trees per acre over 4 inches in diameter at breast height shall be retained.
(v)All trees that are harvested or all trees that are retained shall be marked or sample marked by, or under the supervision of, a registered professional forester before felling operations begin. The board shall adopt regulations for sample marking for this section in Title 14 of the California Code of Regulations. Sample marking shall be limited to homogenous forest stand conditions typical of plantations.
(vi)The board may adopt specific regulations for the removal of dead and dying trees in amounts less than 10 percent of the average volume per acre for trees up to 36 inches in diameter at breast height. Regulations adopted by the board shall consider safety, fuel hazard abatement, mortality capture, the adequacy and retention of wildlife trees, especially those trees over 30 inches in diameter at breast height, and standards of enforceability for the department. All trees over 30 inches in diameter at breast height that are harvested pursuant to this paragraph shall be marked by, or under the supervision of, a registered professional forester before felling. The registered professional forester shall consult with the director before felling any dead or dying trees in excess of 30 inches in diameter at breast height.
(vii)All trees harvested pursuant to this paragraph shall be marked by, or under the supervision of, a registered professional forester before felling operations begin.
(viii)The six largest trees per acre within the boundaries of a notice of exemption submitted pursuant to this subdivision shall not be harvested.
(ix)No trees of the genus Quercus that are greater than 22 inches in diameter at breast height shall be harvested under a notice of exemption submitted pursuant to this subdivision, except for those trees that need to be removed to mitigate safety.
(x)The postharvest composition of tree species shall be representative of the preharvest stand condition and demonstrate progression towards climax forest conditions, unless the registered professional forester provides information explaining how modification of species diversity will benefit forest health and resiliency.
(E)(i)The board shall adopt regulations for the treatment of understory vegetation and standing dead fuels, canopy closure, clearance to base of live crown, or ladder fuels, that could promote the spread of wildfire. The board may adopt regulations pertaining to canopy closure if determined appropriate and necessary.
(ii)Slash and woody debris within 50 feet of a public road or critical infrastructure, as defined by the board, shall be chipped, burned, or removed.
(iii)The standards required by clauses (i) and (ii) shall be achieved on approximately 80 percent of the treated area.
(F) Before the submission of a notice of exemption to the department, the registered professional forester responsible for submitting the notice shall designate temporary road locations, landing locations, tractor road crossings of Class III watercourses, unstable areas, or connected headwall swales on the ground and map their locations.
(G)The construction or reconstruction of temporary roads on slopes of 30 percent or less shall be allowed if all of the following conditions are met:
(i)Temporary roads or landings shall not be located on unstable areas, as defined in Section 895.1 of Title 14 of the California Code of Regulations.
(ii)Temporary roads shall be single-lane in width.
(iii)Temporary roads shall not be located across a connected headwall swale, as defined in Section 895.1 of Title 14 of the California Code of Regulations.
(iv)Construction or reconstruction of temporary roads, landings, or watercourse crossings shall not occur during the winter operating period. Pursuant to subdivision (g) of Sections 923.6, 943.6, and 963.6, as applicable, of Title 14 of the California Code of Regulations, roads and landings used for log hauling or other heavy equipment uses during the winter period shall occur on a stable operating surface and, where necessary, be surfaced with rock to a depth and quantity sufficient to maintain the stable operating surface. Use shall be prohibited on roads that are not hydrologically disconnected and exhibit saturated soil conditions. Timber operations during the winter period shall comply with paragraphs (1) and (2) of subdivision (c) of Sections 914.7, 934.7, and 954.7, as applicable, of Title 14 of the California Code of Regulations.
(v)Use of temporary roads shall comply with the operational provisions of Article 12 (commencing with Section 923) of Subchapter 4 of Chapter 4 of Division 1.5 of Title 14 of the California Code of Regulations, and recognize guidance on hydrologic disconnection in Technical Rule Addendum Number 5.
(vi)No logging road or landings construction or reconstruction activities of any kind shall occur within 200 feet of Class I and Class II watercourses or within 50 feet of a Class III watercourse.
(vii)The landowner shall retain a registered professional forester who is available to provide professional advice to the licensed timber operator and timberland owner throughout the active timber operations. The name, address, telephone number, and registration number of the retained registered professional forester shall be provided on the submitted notice of exemption. This professional advice shall include overseeing the construction or reconstruction of any temporary roads or landings and advising on necessary mitigation to avoid potential impacts to associated watershed and forest resources. The registered professional forester shall also comply with Section 1035.2 of Title 14 of the California Code of Regulations, relating to interaction between the licensed timber operator and the registered professional forester.
(viii)The registered professional forester responsible for submitting the notice of exemption shall affirm that the construction or reconstruction of each temporary road is necessary to provide access to harvest areas where no feasible alternative exists. The submitted notice of exemption shall include the number and cumulative length of temporary roads that will be constructed or reconstructed.
(ix)(I)Temporary road construction or reconstruction shall be limited to no more than two miles of road per ownership in a planning watershed per any five-year period.
(II)For each exemption affecting less than 40 acres, all temporary roads constructed or reconstructed under this exemption shall not exceed a cumulative length of 300 feet.
(III)For each exemption affecting between 40 and 80 acres, all temporary roads constructed or reconstructed under this exemption shall not exceed a cumulative length of between 300 and 600 feet, as determined on a pro rata basis by the total acreage affected by the exemption.
(IV)For each exemption affecting over 80 acres, all temporary roads constructed or reconstructed under the exemption shall not exceed a cumulative length of 600 feet. The submitted notice of exemption shall list the number of acres affected and the cumulative length of the road in feet.
(V)Temporary roads constructed or reconstructed under this exemption shall not be connected to other temporary roads constructed under previous or subsequent exemptions filed under this paragraph.
(VI)All temporary roads shall be abandoned using proactive measures that have been applied to effectively remove them from the permanent road network, in accordance with the definition of abandoned road as defined in Section 895.1 of Title 14 of the California Code of Regulations.
(VII)This paragraph shall not be interpreted to permit road construction or reconstruction except as authorized under the Forest Resilience Exemption, pursuant to this subparagraph.
(VIII)No trees larger than 30 inches in diameter at breast height shall be removed for the purposes of road construction or reconstruction under a notice of exemption submitted pursuant to this subdivision.
(H)Only trees less than 30 inches in diameter at breast height may be removed. The board, in consultation with the department, shall develop clearly written guidance documents on inspection and enforceability standards relating to standards set forth in this paragraph.
(I)All timber operations conducted pursuant to this subdivision shall only occur within the most recent version of the departments Fire Hazard Severity Zone Map in the moderate, high, and very high fire threat zones.
(J)If pesticides or herbicides will be used within the boundaries of an area covered by a notice of exemption pursuant to this subparagraph within one year of director acceptance, the timberland owner shall notify the appropriate regional water quality control board 10 days before application of any pesticides or herbicides.
(K)After the timber operations are complete, the department shall conduct an onsite inspection to determine compliance with this subdivision and whether appropriate enforcement action should be initiated. The department shall notify the appropriate regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey seven days prior to conducting the onsite inspection. The regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey may conduct an inspection with the department.
(2)(A)The board shall adopt regulations, initially as emergency regulations in accordance with subparagraph (B), that the board considers necessary to implement and to obtain compliance with this subdivision.
(B)The emergency regulations adopted pursuant to subparagraph (A) shall be adopted in accordance with the Administrative Procedure Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code). The adoption of emergency regulations shall be deemed to be an emergency and necessary for the immediate preservation of the public peace, health, and safety, or general welfare.
(3)This subdivision shall become inoperative on January 1, 2031.
(k)(1)The cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands, if all of the following requirements are met:
(A)A registered professional forester shall prepare the notice of exemption and submit it to the director. The notice shall include both of the following:
(i)A certification signed by the registered professional forester that the timber operation is designed to restore and conserve California black and Oregon white oak woodlands and associated grasslands encroached upon by conifers and that a minimum of 35 square feet of basal area per acre, or as determined by the board, of California black or Oregon white oak, or both, occupy the proposed treatment area at the time the notice is prepared.
(ii)A description of the preharvest stand structure and a statement of the postharvest stand stocking levels.
(B)No tree larger than 30 inches in diameter at breast height shall be harvested for commercial purposes. If necessary to achieve the oak woodland restoration goal of the exemption, trees larger than 30 inches in diameter at breast height may be harvested. The registered professional forester shall provide information on the need to remove these trees, and consult with the director before felling any tree in excess of 30 inches in diameter at breast height.
(C)Only conifers within 300 feet of a California black or Oregon white oak may be harvested.
(D)The total area exempted pursuant to this subdivision shall not exceed 300 acres per ownership in a planning watershed per five-year period.
(E)Conifer shall be reduced to less than 25 percent of the combined hardwood and conifer postharvest stand stocking levels. Decadent and deformed trees of wildlife value that are retained shall not count toward basal area requirements.
(F)No more than 20 percent of the total basal area of preexisting oak stock shall be cut or removed during harvest. The board may establish minimum postharvest basal area requirements for California black or Oregon white oak.
(G)Slash shall be configured to minimize the risk of fire mortality to the remaining oak trees.
(2)(A)The board shall adopt regulations, initially as emergency regulations in accordance with subparagraph (B), that the board considers necessary to implement and to obtain compliance with this subdivision.
(B)The emergency regulations adopted pursuant to subparagraph (A) shall be adopted in accordance with the Administrative Procedure Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code). The adoption of emergency regulations shall be deemed to be an emergency and necessary for the immediate preservation of the public peace, health, and safety, or general welfare.
(l)(1)The board may exempt from this chapter, or portions of this chapter, a person engaged in forest management whose activities are limited to the cutting or removal of trees on the persons property in compliance with Sections 4290 and 4291 that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break for a distance of not more than 300 feet on each side from an approved and legally permitted habitable structure, when that cutting or removal is conducted in compliance with this subdivision and all of the following conditions are met:
(A)The notice of exemption is prepared, signed, and submitted by a registered professional forester to the department.
(B)For the areas between 150 and 300 feet from the habitable structure, the operations meet all of the following provisions:
(i)The residual stocking standards are consistent with Sections 913.2, 933.2, and 953.2 of Title 14 of the California Code of Regulations, as appropriate.
(ii)Activities within this area will increase the quadratic mean diameter of the stand.
(iii)The residual stand consists primarily of healthy and vigorous dominant and codominant trees from the preharvest stand, well distributed throughout the harvested area.
(iv)Postharvest slash treatment and stand conditions will lead to more moderate fire behavior in the professional judgment of the registered professional forester who submits the notice of exemption.
(v)Any additional guidance for slash treatment and postharvest stand conditions and any other issues deemed necessary that are consistent with this section, as established by the board.
(2)For purposes of this subdivision, habitable structure means a building that contains one or more dwelling units or that can be occupied for residential use. Buildings occupied for residential use include single-family homes, multidwelling structures, mobile and manufactured homes, and condominiums. For purposes of this subdivision, habitable structure does not include commercial, industrial, or incidental buildings such as detached garages, barns, outdoor sanitation facilities, and sheds.
(3)This subdivision shall become inoperative on January 1, 2031.
SEC. 2.Section 4584.1 of the Public Resources Code is amended to read:4584.1.Rules and regulations adopted by the board pursuant to Section 4584, except subdivision (k) of Section 4584, shall comply with the following standards, as determined appropriate and necessary by the board:
(a)Notices of exemption that are prepared and submitted to the director shall include a map of the area of operations that complies with the requirements of paragraphs (1), (3), and (4), subparagraphs (A), (B), (D), and (E) of paragraph (5), paragraphs (7) to (12), inclusive, and paragraph (14) of subdivision (x) of Section 1034 of Title 14 of the California Code of Regulations.
(b)Notices of exemption that are prepared and submitted to the director shall provide a confidential archaeological letter that includes all the information required by paragraphs (2) and (7) to (11), inclusive, of subdivision (c) of Sections 929.1, 949.1 and 969.1, as applicable, of Title 14 of the California Code of Regulations, and site records if required pursuant to subdivision (g) of that section or pursuant to Section 929.5 of Title 14 of the California Code of Regulations. This subdivision shall not apply to activities described in subdivision (i) or (m) of Section 4584.
(c)All fuel treatments required by the board shall be completed within one year from the date the director receives the notice, with the exception of burning. This shall include treatment of surface fuels, wood debris, and slash, which shall be lopped, removed, chipped, piled for burning, or otherwise treated. Burning shall be completed within two years from the date the director receives the notice of exemption.
(d)Slash and woody debris shall be treated to achieve a maximum post harvest postharvest depth of 18 inches above the ground except within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code. Surface fuels, slash, and woody debris within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code shall be chipped, piled, and burned, or removed.
(e)Timber operations shall comply with the requirements of paragraphs (1) to (10), inclusive, of subdivision (b) of Section 1038 of Title 14 of the California Code of Regulations.
(f)All timber operations conducted in Lake Tahoe Region shall have a valid Tahoe Basin Tree Removal Permit, as defined by the Tahoe Regional Planning Agency (TRPA), or shall be conducted under a valid TRPA Memorandum of Understanding, when such a permit is required by TRPA.
(g)The submitted notice of exemption shall include selection criteria for the trees to be harvested or the trees to be retained.
(h)The department shall provide the appropriate regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey with copies of notices of exemption when they are submitted.
(i)The submitted notice of exemption shall include the tentative commencement date of timber operations.
(j)Within a 15-day period, the registered professional forester or person responsible for the submittal of the notice of exemption shall notify the department, the Department of Fish and Wildlife, the appropriate regional water quality control board, and the California Geologic Survey of the actual date of commencement of timber operations.
(k)Timber operations pursuant to an exemption may not commence for 10 working days from the date of the directors receipt of the notice of exemption unless this delay is waived by the director. The director shall determine whether the notice of exemption is complete, and if so, shall send a copy of a notice of acceptance to the submitter. If the notice of exemption is not complete and accurate, it shall be returned to the submitter and the timber operator may not proceed. If the director does not act within 10 days of receipt of the notice of exemption, timber operations may commence.
(l)(1)No large old trees, defined as a tree that existed before 1800 AD or is greater than 60 inches in diameter at stump height for Sierra or Coast Redwoods, and 48 inches in diameter at stump height for all other tree species or Decadent and Deformed Trees with Value to Wildlife, as defined in Section 895.1 of Title 14 of the California Code of Regulations, shall be harvested unless the following apply:
(A)The tree is not critical for the maintenance of a Late Successional Stand.
(B)A registered professional forester attached to the submitted notice of exemption a written explanation and justification for the harvest of the tree based on the registered professional foresters finding of any of the following:
(i)The tree is a hazard to safety or property.
(ii)The removal of the tree is necessary for the construction of a building as approved by the appropriate local jurisdiction and shown on the county or city approved site plan, which shall be attached to the submitted notice of exemption.
(iii)The tree is dead or likely to die within one year of the date of the proposed removal, as determined by a registered professional forester.
(2)A registered professional forester-written explanation or justification need not be attached to the submitted notice of exemption if an approved Habitat Conservation Plan, Sustained Yield Plan, or plan, as that term is defined in Section 895.1 of Title 14 of the California Code of Regulations addresses large old tree retention for the area in which the large old tree is proposed for removal and the removal is in compliance with the retention standards of that document.
(3)Any tree harvested pursuant to this subdivision shall be shown on a map provided with the submitted notice of exemption to the department.
(4)This subdivision shall not apply to or be used in conjunction with the Forest Resilience Exemption created pursuant to subdivision (j) of Section 4584.
(m)Helicopter yarding shall be prohibited.
(n)All applicable provisions of the Professional Foresters Law, including, but not limited to, Sections 775 to 779, inclusive, of this code, as well as all applicable provisions of Registration of Professional Forester Rules, including, but not limited to, Sections 1612 to 1614, inclusive, of Title 14 of the California Code of Regulations, shall apply to the practice of professional forestry as it relates to this section.
SEC. 3.Section 4584.2 of the Public Resources Code is amended to read:4584.2.Rules and regulations adopted by the board pursuant to subdivision (j) of Section 4584, shall comply with the following standards:
(a)Notices of exemption that are prepared and submitted to the director shall include a map of the area of operations that complies with the requirements of paragraphs (1), (3), and (4), subparagraphs (A), (B), (D), and (E) of paragraph (5), paragraphs (7) to (12), inclusive, and paragraph (14) of subdivision (x) of Section 1034 of Title 14 of the California Code of Regulations.
(b)Notices of exemption that are prepared and submitted to the director shall provide a confidential archaeological letter that includes all the information required by paragraphs (2) and (7) to (11), inclusive, of subdivision (c) of Sections 929.1, 949.1 and 969.1, as applicable, of Title 14 of the California Code of Regulations, and site records if required pursuant to subdivision (g) of that section or pursuant to Section 929.5 of Title 14 of the California Code of Regulations.
(c)All fuel treatments required by the board shall be completed within one year from the date the director receives the notice, with the exception of burning. This shall include treatment of surface fuels, wood debris, and slash, which shall be lopped, removed, chipped, piled for burning, or otherwise treated. Burning shall be completed within two years from the date the director receives the notice of exemption.
(d)Slash and woody debris shall be treated to achieve a maximum post harvest postharvest depth of 18 inches above the ground except within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code. Surface fuels, slash, and woody debris within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code shall be chipped, burned, or removed.
(e)Timber operations shall comply with the requirements of paragraphs (1) to (4), inclusive, and (6) to (10), inclusive, of subdivision (b) of Section 1038 of Title 14 of the California Code of Regulations.
(f)All timber operations conducted in Lake Tahoe Region must have a valid Tahoe Basin Tree Removal Permit, as defined by the Tahoe Regional Planning Agency (TRPA), or shall be conducted under a valid TRPA Memorandum of Understanding, when such a permit is required by TRPA.
(g)The submitted notice of exemption shall include selection criteria for the trees to be harvested or the trees to be retained.
(h)The department shall provide the appropriate regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey with copies of notices of exemption when they are submitted.
(i)The submitted notice of exemption shall include the tentative commencement date of timber operations.
(j)Within a 15-day period, the registered professional forester responsible for the submittal of the notice of exemption shall notify the department, the Department of Fish and Wildlife, the appropriate regional water quality control board, and the California Geologic Survey of the actual date of commencement of timber operations.
(k)Operations pursuant to an exemption may not commence for 10 working days from the date of the directors receipt of the notice of exemption unless this delay is waived by the director. The director shall determine whether the notice of exemption is complete, and if so, shall send a copy of a notice of acceptance to the submitter. If the notice of exemption is not complete and accurate, it shall be returned to the submitter and the timber operator may not proceed. If the director does not act within five days of receipt of the notice of exemption, timber operations may commence.
(l)(1)No Decadent and Deformed Trees with Value to Wildlife, as defined in Section 895.1 of Title 14 of the California Code of Regulations, shall be harvested unless all the following apply:
(A)The tree is not critical for the maintenance of a Late Successional Stand.
(B)A registered professional forester attached to the submitted notice of exemption a written explanation and justification for the harvest of the tree based on the registered professional foresters finding of any of the following:
(i)The tree is a hazard to safety or property.
(ii)The removal of the tree is necessary for the construction of a building as approved by the appropriate local jurisdiction and shown on the county or city approved site plan which shall be attached to the submitted notice of exemption.
(iii)The tree is dead or likely to die within one year of the date of the proposed removal, as determined by a registered professional forester.
(2)A registered professional foresters written explanation or justification need not be attached to the submitted notice of exemption if an approved Habitat Conservation Plan, Sustained Yield Plan, or plan as that term is defined in Section 895.1 of Title 14 of the California Code of Regulations addresses large old tree retention for the area in which the large old tree is proposed for removal and the removal is in compliance with the retention standards of that document.
(3)Any tree harvested pursuant to this subdivision shall be shown on a map provided with the submitted notice of exemption to the department.
(4)This subdivision shall not apply to or be used in conjunction with the Forest Resilience Exemption created pursuant to subdivision (j) of Section 4584.
(m)Helicopter yarding shall be prohibited.
(n)All applicable provisions of the Professional Foresters Law, including, but not limited to, Sections 775 to 779, inclusive, of this code, as well as all applicable provisions of Registration of Professional Forester Rules, including, but not limited to, Sections 1612 to 1614, inclusive, of Title 14 of the California Code of Regulations apply to the practice of professional forestry as it relates to this section.
SEC. 4.Section 4589 of the Public Resources Code is amended to read:4589.(a)The department and board, in consultation with the Department of Fish and Wildlife, and the State Water Resources Control Board, shall, commencing December 31, 2019, and annually thereafter, review and submit a report to the Legislature on the trends in the use of, compliance with, and effectiveness of, the exemptions and emergency notice provisions described in Sections 4584 and 4592 of this code and Sections 1038 and 1052 of Title 14 of the California Code of Regulations. The report shall include an analysis of exemption use and whether the exemptions are having the intended effect. The report shall also include recommendations to improve the use of those exemptions and emergency notice provisions, information on the linear distance of road constructed or reconstructed under notices of exemption by individual ownerships, within a representative sample of planning watersheds from each forest practice district as defined in Sections 907 to 909, inclusive, of Title 14 of the California Code of Regulations, and violations associated with road reconstruction. The report shall include information on the number and type of violations and enforcement actions taken on each notice of exemption and emergency notice. The report shall also contain the number of posttreatment onsite inspections that occur and whether those inspections were attended by a representative of the Department of Fish and Wildlife and a representative of the State Water Resources Control Board. The report submitted on December 31, 2025, shall include recommendations necessary for revisions to diameter limits at stump heights of harvestable trees under subdivisions (j) and (k) of Section 4584, as those subdivisions read on January 1, 2024.
(b)The public shall be provided opportunities to participate in the review and the development of the report.
(c)The report shall be submitted pursuant to Section 9795 of the Government Code.
(d)(A)This section shall be operative for a period of five years after the effective date of emergency regulations as adopted by the board and as of that date is inoperative.
(B)The board shall notify the Secretary of State when emergency regulations have been adopted.
SEC. 5.Section 399.20.3 of the Public Utilities Code is amended to read:399.20.3.(a)For purposes of this section, the following definitions apply:
(1)Bioenergy has the same meaning as set forth in paragraph (6) of subdivision (f) of Section 399.20.
(2)Tier 1 high hazard zone includes areas where wildlife and falling trees threaten electrical transmission and distribution lines, roads, and other evacuation corridors, critical community infrastructure, or other existing structures, as designated by the Department of Forestry and Fire Protection pursuant to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(3)Tier 2 high hazard zone includes watersheds that have significant tree mortality combined with community and natural resource assets, as designated by the Department of Forestry and Fire Protection pursuant to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(b)(1)In addition to the requirements of subdivision (f) of Section 399.20, by December 1, 2023, electrical corporations shall collectively procure, through financial commitments of 5 to 15 years, inclusive, their proportionate share of 125 megawatts of cumulative rated generating capacity from existing bioenergy projects that commenced operations before June 1, 2013. At least 80 percent of the feedstock of an eligible facility, on an annual basis, shall be a byproduct of sustainable forestry management, which includes removal of dead and dying trees from Tier 1 and Tier 2 high hazard zones and is not that from lands that have been clear cut. At least 60 percent of this feedstock shall be from Tier 1 and Tier 2 high hazard zones.
(2)Paragraph (1) shall not apply to a utility subject to subdivision (g) if both of the following apply:
(A)The utility, either directly or through a joint powers authority, entered into five-year financial commitments for its proportionate share of 125 megawatts of cumulative rated generating capacity from existing bioenergy projects pursuant to this section as it was enacted by Chapter 368 of the Statutes of 2016.
(B)The utilitys financial commitments referenced in subparagraph (A) include, (1) a contract with a facility operator that was, on June 1, 2022, in a bankruptcy or other insolvency proceeding, or (2) a contract for a project that does not deliver energy to the utility.
(c)For the purpose of contracts entered into pursuant to subdivision (b), commission Resolution E-4770 (March 17, 2016), and commission Resolution E-4805 (October 13, 2016), Tier 1 and Tier 2 high hazard zone fuel or feedstock shall also include biomass fuels removed from fuel reduction operations exempt from timber harvesting plan requirements pursuant to subdivisions (a), (f), (j), and (k) of Section 4584 of the Public Resources Code, as those subdivisions read on January 1, 2024.
(d)The commission shall require an electrical corporation that has entered into a contract pursuant to subdivision (b), commission Resolution E-4770 (March 17, 2016), or commission Resolution E-4805 (October 13, 2016) to allow fuel or feedstock reporting requirements to be based on a monthly or annual basis, and a bioenergy facility providing generation pursuant to that contract shall have the right to opt out of the mandated fuel or feedstock usage levels in any particular month upon providing written notice to the electrical corporation in the month of operation. For months in which a bioenergy facility opts out of the mandated fuel or feedstock usage levels or misses the mandated fuel or feedstock targets, that facility shall be paid the alternate price adopted by the commission in commission Resolution E-4770 for all megawatthours generated during that month. Contracts shall continue in force through the end of the contracted term without creating an event of default for missing mandated fuel or feedstock usage levels and without giving rise to a termination right in favor of the electrical corporation.
(e)(1)For each electrical corporation, the commission shall allocate its proportionate share of the 125 megawatts based on the ratio of the electrical corporations peak demand to the total statewide peak demand.
(2)Procurement by an electrical corporation of generation capacity pursuant to a contract under the commissions Resolution E-4770 (March 17, 2016) that is in excess of the requirement of that electrical corporation under that resolution shall count towards meeting the electrical corporations proportionate share allocated pursuant to paragraph (1).
(f)The commission may direct each electrical corporation to develop standard contract terms and conditions that reflect the operational characteristics of the bioenergy projects and to provide a streamlined contracting process or may require the electrical corporations to use the mechanism established pursuant to the commissions Resolution E-4770 (March 17, 2016) to meet the requirements of subdivision (e). The procurement pursuant to the developed standard contract shall occur on an expedited basis due to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(g)A local publicly owned electric utility serving more than 100,000 customers shall procure its proportionate share, based on the ratio of the utilitys peak demand to the total statewide peak demand, of 125 megawatts of cumulative rated capacity from existing bioenergy projects described in subdivision (b) subject to terms of at least five years.
(h)The commission shall ensure that the costs of any contract procured by an electrical corporation to satisfy the requirements of this section are recoverable from all customers on a nonbypassable basis.
(i)The Procurement Review Group within the commission shall advise the commission on the cost of the generation procured pursuant to this section and its impact on ratepayers.
(j)For purposes of this section, any incremental procurement of electricity products from bioenergy resources by a new contract or contract extension of five years or longer in duration shall be from a resource that meets emission limits equivalent to, or more stringent than, the applicable best available retrofit control technology, as determined by the local air pollution control district or air quality management district. The determination shall be made before the start of the operating period under the new contract or contract extension.
Upon determining that this exemption is consistent with the purposes of this chapter, the board may exempt from this chapter, or portions of this chapter, a person engaged in forest management whose activities are limited to any of the following:
(a)The cutting or removal of trees for the purpose of constructing or maintaining a right-of-way for utility lines.
(b)The planting, growing, nurturing, shaping, shearing, removal, or harvest of immature trees for Christmas trees or other ornamental purposes or minor forest products, including fuelwood.
(c)The cutting or removal of dead, dying, or diseased trees of any size.
(d)Site preparation.
(e)Maintenance of drainage facilities and soil stabilization treatments.
(f)Timber operations on land managed by the Department of Parks and Recreation.
(g)(1)The one-time conversion of less than three acres to a nontimber use. A person, whether acting as an individual, as a member of a partnership, or as an officer or employee of a corporation or other legal entity, shall not obtain more than one exemption pursuant to this subdivision in a five-year period. If a partnership has as a member, or if a corporation or other legal entity has as an officer or employee, a person who has received this exemption within the past five years, whether as an individual, as a member of a partnership, or as an officer or employee of a corporation or other legal entity, then that partnership, corporation, or other legal entity is not eligible for this exemption. Person, for purposes of this subdivision, means an individual, partnership, corporation, or other legal entity.
(2)(A)Notwithstanding Section 4554.5, the board shall adopt regulations that do all of the following:
(i)Identify the required documentation of a bona fide intent to complete the conversion that an applicant will need to submit in order to be eligible for the exemption in paragraph (1).
(ii)Authorize the department to inspect the sites approved in conversion applications that have been approved on or after January 1, 2002, in order to determine that the conversion was completed within the two-year period described in subparagraph (B) of paragraph (2) of subdivision (a) of Section 1104.1 of Title 14 of the California Code of Regulations.
(iii)Require the exemption pursuant to this subdivision to expire if there is a change in timberland ownership. The person who originally submitted an application for an exemption pursuant to this subdivision shall notify the department of a change in timberland ownership on or before five calendar days after a change in ownership.
(iv)The board may adopt regulations allowing a waiver of the five-year limitation described in paragraph (1) upon finding that the imposition of the five-year limitation would impose an undue hardship on the applicant for the exemption. The board may adopt a process for an appeal of a denial of a waiver.
(v)The board may adopt regulations allowing a waiver of the one-time limitation described in paragraph (1) upon finding that the imposition of the one-time limitation would impose an undue hardship on the applicant. The board may adopt a process for an appeal of a denial of a waiver.
(B)The application form for the exemption pursuant to paragraph (1) shall prominently advise the public that a violation of the conversion exemption, including a conversion applied for in the name of someone other than the person or entity implementing the conversion in bona fide good faith, is a violation of this chapter and penalties may accrue up to ten thousand dollars ($10,000) for each violation pursuant to Article 8 (commencing with Section 4601).
(h)An easement granted by a right-of-way construction agreement administered by the federal government if timber sales and operations within or affecting the area are reviewed and conducted pursuant to the federal National Environmental Policy Act of 1969 (42 U.S.C. Sec. 4321 et seq.).
(i)(1)The cutting or removal of trees in compliance with Sections 4290 and 4291 that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break for a distance of not more than 150 feet on each side from an approved and legally permitted structure that complies with the California Building Standards Code, when that cutting or removal is conducted in compliance with this subdivision. For purposes of this subdivision, an approved and legally permitted structure includes only structures that are designed for human occupancy, garages, barns, stables, and structures used to enclose fuel tanks.
(2)(A)The cutting or removal of trees pursuant to this subdivision is limited to cutting or removal that will result in a reduction in the rate of fire spread, fire duration and intensity, fuel ignitability, or ignition of the tree crowns and shall be in accordance with any regulations adopted by the board pursuant to this section.
(B)Trees shall not be cut or removed pursuant to this subdivision by the clearcutting regeneration method, by the seed tree removal step of the seed tree regeneration method, or by the shelterwood removal step of the shelterwood regeneration method.
(3)(A)All fuel treatments conducted pursuant to this subdivision that do not comply with board rules and regulations may be determined to be a nuisance and subject to abatement by the department or the city or county having jurisdiction.
(B)The costs incurred by the department, city, or county, as the case may be, to abate the nuisance upon a parcel of land subject to the timber operations, including, but not limited to, investigation, boundary determination, measurement, and other related costs, may be recovered by special assessment and lien against the parcel of land by the department, city, or county. The assessment may be collected at the same time and in the same manner as ordinary ad valorem taxes, and shall be subject to the same penalties and the same procedure and sale in case of delinquency as is provided for ad valorem taxes.
(4)All timber operations conducted pursuant to this subdivision shall conform to applicable city or county general plans, city or county implementing ordinances, and city or county zoning ordinances. This paragraph does not authorize the cutting, removal, or sale of timber or other solid wood forest products within an area where timber harvesting is prohibited or otherwise restricted pursuant to the rules or regulations adopted by the board.
(5)(A)The board shall adopt regulations, initially as emergency regulations in accordance with subparagraph (B), that the board considers necessary to implement and to obtain compliance with this subdivision.
(B)The emergency regulations adopted pursuant to subparagraph (A) shall be adopted in accordance with the Administrative Procedure Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code). The adoption of emergency regulations shall be deemed to be an emergency and necessary for the immediate preservation of the public peace, health, and safety, or general welfare.
(j)(1)(A)The harvesting of trees, limited to those trees that eliminate the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns, for the purpose of reducing the rate of fire spread, duration and intensity, fuel ignitability, or ignition of tree crowns. An exemption pursuant to this paragraph shall be known as the Forest Resilience Exemption.
(2)(B)The board may authorize an exemption pursuant to paragraph (1) subparagraph (A) only if the tree harvesting will decrease fuel continuity and increase the quadratic mean diameter of the stand, and the tree harvesting area will not exceed 500 acres. Increases in quadratic mean diameter shall only consider trees greater than eight inches in diameter at breast height. The notice of exemption may be authorized only if all of the conditions specified in paragraphs (3) to (9), subparagraphs (C) to (I), inclusive, are met.
(3)(C)A registered professional forester shall prepare the notice of exemption and submit it to the director.
(4)(A)(D)(i)The submitted notice of exemption shall include a description of the preharvest stand structure and a statement of the postharvest stand stocking levels and the expected postharvest increase in quadratic mean diameter.
(B)(ii)The level of residual stocking shall be consistent with maximum sustained production of high-quality timber products. The residual stand shall consist primarily of healthy and vigorous dominant and codominant trees from the preharvest stand. Stocking shall not be reduced below the standards required by the following provisions that apply to the exemption at issue:
(i)(I)Clauses 1 to 4, inclusive, of subparagraph (A) of paragraph (1) of subdivision (a) of Sections 913.3, 933.3, and 953.3 of Title 14 of the California Code of Regulations, or clauses 1 to 4, inclusive, of subparagraph (A) of paragraph (2) of subdivision (a) of Sections 913.2, 933.2, and 953.2 of Title 14 of the California Code of Regulations.
(ii)(II)The registered professional forester responsible for preparing the notice of exemption shall identify the designated postharvest stocking within the notice of exemption. The selected stocking shall be applicable to, and consistent with, silviculture that would apply to the preharvest stand condition provided pursuant to subparagraph (A). clause (i).
(iii)(III)Additional information on preharvest stand conditions, including, but not limited to, stand ages, stand structure, past management activities, and landowner goals and objectives shall also be provided by the registered professional forester preparing and submitting the exemption that substantiates the selection of postharvest stocking.
(C)(iii)Within the coast district, if the preharvest dominant and codominant crown canopy is occupied by trees less than 14 inches in diameter at breast height, a minimum of 100 trees over 4 inches in diameter at breast height shall be retained per acre for Site I, II, and III lands, and a minimum of 75 trees over 4 inches in diameter at breast height shall be retained per acre for Site IV and V lands.
(D)(iv)Within the northern district and southern district, if the preharvest dominant and codominant crown canopy is occupied by trees less than 14 inches in diameter at breast height, a minimum of 65 trees over 4 inches in diameter at breast height shall be retained.
(E)(v)All trees that are harvested or all trees that are retained shall be marked or sample marked by, or under the supervision of, a registered professional forester before felling operations begin. The board shall adopt regulations for sample marking for this section in Title 14 of the California Code of Regulations. Sample marking shall be limited to homogenous forest stand conditions typical of plantations.
(F)(vi)The board may adopt specific regulations for the removal of dead and dying trees in amounts less than 10 percent of the average volume per acre for trees up to 36 inches in diameter at breast height. Regulations adopted by the board shall consider safety, fuel hazard abatement, mortality capture, the adequacy and retention of wildlife trees, especially those trees over 30 inches in diameter at breast height, and standards of enforceability for the department. All trees over 30 inches in diameter at breast height that are harvested pursuant to this paragraph shall be marked by, or under the supervision of, a registered professional forester before felling. The registered professional forester shall consult with the director before felling any dead or dying trees in excess of 30 inches in diameter at breast height.
(G)(vii)All trees harvested pursuant to this paragraph shall be marked by, or under the supervision of, a registered professional forester before felling operations begin.
(H)(viii)The six largest trees per acre within the boundaries of a notice of exemption submitted pursuant to this subdivision shall not be harvested.
(I)(ix)No trees of the genus Quercus that are greater than 22 inches in diameter at breast height shall be harvested under a notice of exemption submitted pursuant to this subdivision, except for those trees that need to be removed to mitigate safety.
(5)(A)(E)(i)The board shall adopt regulations for the treatment of understory vegetation and standing dead fuels, clearance to base of live crown, or ladder fuels, that could promote the spread of wildfire. The board may adopt regulations pertaining to canopy closure if determined appropriate and necessary.
(B)(ii)Slash and woody debris within 50 feet of a public road or critical infrastructure, as defined by the board, shall be chipped, burned, or removed.
(C)(iii)The standards required by subparagraphs (A) and (B) clauses (i) and (ii) shall be achieved on approximately 80 percent of the treated area.
(6)(F) Before the submission of a notice of exemption to the department, the registered professional forester responsible for submitting the notice shall designate temporary road locations, landing locations, tractor road crossings of Class III watercourses, unstable areas, or connected headwall swales on the ground and map their locations.
(7)(G)The construction or reconstruction of temporary roads on slopes of 30 percent or less shall be allowed if all of the following conditions are met:
(A)(i)Temporary roads or landings shall not be located on unstable areas, as defined in Section 895.1 of Title 14 of the California Code of Regulations.
(B)(ii)Temporary roads shall be single-lane in width.
(C)(iii)Temporary roads shall not be located across a connected headwall swale, as defined in Section 895.1 of Title 14 of the California Code of Regulations.
(D)(iv)Construction or reconstruction of temporary roads, landings, or watercourse crossings shall not occur during the winter operating period. Pursuant to subdivision (g) of Sections 923.6, 943.6, and 963.6, as applicable, of Title 14 of the California Code of Regulations, roads and landings used for log hauling or other heavy equipment uses during the winter period shall occur on a stable operating surface and, where necessary, be surfaced with rock to a depth and quantity sufficient to maintain the stable operating surface. Use shall be prohibited on roads that are not hydrologically disconnected and exhibit saturated soil conditions. Timber operations during the winter period shall comply with paragraphs (1) and (2) of subdivision (c) of Sections 914.7, 934.7, and 954.7, as applicable, of Title 14 of the California Code of Regulations.
(E)(v)Use of temporary roads shall comply with the operational provisions of Article 12 (commencing with Section 923) of Subchapter 4 of Chapter 4 of Division 1.5 of Title 14 of the California Code of Regulations, and recognize guidance on hydrologic disconnection in Technical Rule Addendum Number 5.
(F)(vi)No logging road or landings construction or reconstruction activities of any kind shall occur within 200 feet of Class I and Class II watercourses or within 50 feet of a Class III watercourse.
(G)(vii)The landowner shall retain a registered professional forester who is available to provide professional advice to the licensed timber operator and timberland owner throughout the active timber operations. The name, address, telephone number, and registration number of the retained registered professional forester shall be provided on the submitted notice of exemption. This professional advice shall include overseeing the construction or reconstruction of any temporary roads or landings and advising on necessary mitigation to avoid potential impacts to associated watershed and forest resources. The registered professional forester shall also comply with Section 1035.2 of Title 14 of the California Code of Regulations, relating to interaction between the licensed timber operator and the registered professional forester.
(H)(viii)The registered professional forester responsible for submitting the notice of exemption shall affirm that the construction or reconstruction of each temporary road is necessary to provide access to harvest areas where no feasible alternative exists. The submitted notice of exemption shall include the number and cumulative length of temporary roads that will be constructed or reconstructed.
(I)(i)(ix)(I)Temporary road construction or reconstruction shall be limited to no more than two miles of road per ownership in a planning watershed per any five-year period.
(ii)(II)For each exemption affecting less than 40 acres, all temporary roads constructed or reconstructed under this exemption shall not exceed a cumulative length of 300 feet.
(iii)(III)For each exemption affecting between 40 and 80 acres, all temporary roads constructed or reconstructed under this exemption shall not exceed a cumulative length of between 300 and 600 feet, as determined on a pro rata basis by the total acreage affected by the exemption.
(iv)(IV)For each exemption affecting over 80 acres, all temporary roads constructed or reconstructed under the exemption shall not exceed a cumulative length of 600 feet. The submitted notice of exemption shall list the number of acres affected and the cumulative length of the road in feet.
(v)(V)Temporary roads constructed or reconstructed under this exemption shall not be connected to other temporary roads constructed under previous or subsequent exemptions filed under this paragraph.
(vi)(VI)All temporary roads shall be abandoned using proactive measures that have been applied to effectively remove them from the permanent road network, in accordance with the definition of abandoned road as defined in Section 895.1 of Title 14 of the California Code of Regulations.
(vii)(VII)This paragraph shall not be interpreted to permit road construction or reconstruction except as authorized under the Forest Resilience Exemption, pursuant to this paragraph. subparagraph.
(viii)(VIII)No trees larger than 30 inches in diameter at breast height shall be removed for the purposes of road construction or reconstruction under a notice of exemption submitted pursuant to this subdivision.
(8)(H)Only trees less than 30 inches in diameter at breast height may be removed. The board, in consultation with the department, shall develop clearly written guidance documents on inspection and enforceability standards relating to standards set forth in this paragraph.
(9)(I)All timber operations conducted pursuant to this subdivision shall only occur within the most recent version of the departments Fire Hazard Severity Zone Map in the moderate, high, and very high fire threat zones.
(10)(J)If pesticides or herbicides will be used within the boundaries of an area covered by a notice of exemption pursuant to this paragraph subparagraph within one year of director acceptance, the timberland owner shall notify the appropriate regional water quality control board 10 days before application of any pesticides or herbicides.
(11)(K)After the timber operations are complete, the department shall conduct an onsite inspection to determine compliance with this subdivision and whether appropriate enforcement action should be initiated. The department shall notify the appropriate regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey seven days prior to conducting the onsite inspection. The regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey may conduct an inspection with the department.
(12)This subdivision shall become inoperative on January 1, 2031.(2)(A)The board shall adopt regulations, initially as emergency regulations in accordance with subparagraph (B), that the board considers necessary to implement and to obtain compliance with this subdivision.
(B)The emergency regulations adopted pursuant to subparagraph (A) shall be adopted in accordance with the Administrative Procedure Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code). The adoption of emergency regulations shall be deemed to be an emergency and necessary for the immediate preservation of the public peace, health, and safety, or general welfare.
(3)This subdivision shall become inoperative on January 1, 2031.
(k)(1)The cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands, if all of the following requirements are met:
(1)(A)A registered professional forester shall prepare the notice of exemption and submit it to the director. The notice shall include all both of the following:
(A)(i)A certification signed by the registered professional forester that the timber operation is designed to restore and conserve California black and Oregon white oak woodlands and associated grasslands encroached upon by conifers and that a minimum of 35 square feet of basal area per acre acre, or as determined by the board, of California black or Oregon white oak, or both, occupy the proposed treatment area at the time the notice is prepared and the timber operation is designed to restore and conserve California black and Oregon white oak woodlands and associated grasslands. prepared.
(B)(ii)A description of the preharvest stand structure and a statement of the postharvest stand stocking levels.
(2)(B)No tree larger than 26 30 inches in diameter at stump breast height shall be harvested for commercial purposes, which includes use for saw logs, posts and poles, fuel wood, biomass, or other forest products. purposes. If necessary to achieve the oak woodland restoration goal of the exemption, trees larger than 30 inches in diameter at breast height may be harvested. The registered professional forester shall provide information on the need to remove these trees, and consult with the director before felling any tree in excess of 30 inches in diameter at breast height.
(3)(C)Only conifers within 300 feet of a California black or Oregon white oak that are at minimum four inches in diameter at breast height may be harvested.
(4)(D)The total area exempted pursuant to this subdivision shall not exceed 300 acres per property ownership in a planning watershed per five-year period.
(5)(E)Conifer shall be reduced to less than 25 percent of the combined hardwood and conifer postharvest stand stocking levels. Decadent and deformed trees of wildlife value that are retained shall not count toward basal area requirements.
(6)(F)No more than 20 percent of the total basal area of preexisting oak stock shall be cut or removed during harvest and a minimum of 35 square feet of basal area per acre of California black or Oregon white oak, or both, shall be maintained postharvest. harvest. The board may establish minimum postharvest basal area requirements for California black or Oregon white oak.
(7)(G)Slash shall be configured so as to minimize the risk of fire mortality to the remaining oak trees.
(8)This subdivision shall not apply to the Southern Subdistrict of the Coast Forest District, as defined in Section 895.1 of Title 14 of the California Code of Regulations, or the Southern Forest District, as defined in Section 909 of Title 14 of the California Code of Regulations.(2)(A)The board shall adopt regulations, initially as emergency regulations in accordance with subparagraph (B), that the board considers necessary to implement and to obtain compliance with this subdivision.
(B)The emergency regulations adopted pursuant to subparagraph (A) shall be adopted in accordance with the Administrative Procedure Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code). The adoption of emergency regulations shall be deemed to be an emergency and necessary for the immediate preservation of the public peace, health, and safety, or general welfare.
(l)(1)The board may exempt from this chapter, or portions of this chapter, a person engaged in forest management whose activities are limited to the cutting or removal of trees on the persons property in compliance with Sections 4290 and 4291 that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break for a distance of not more than 300 feet on each side from an approved and legally permitted habitable structure, when that cutting or removal is conducted in compliance with this subdivision and all of the following conditions are met:
(A)The notice of exemption is prepared, signed, and submitted by a registered professional forester to the department.
(B)For the areas between 150 and 300 feet from the habitable structure, the operations meet all of the following provisions:
(i)The residual stocking standards are consistent with Sections 913.2, 933.2, and 953.2 of Title 14 of the California Code of Regulations, as appropriate.
(ii)Activities within this area will increase the quadratic mean diameter of the stand.
(iii)The residual stand consists primarily of healthy and vigorous dominant and codominant trees from the preharvest stand, well distributed throughout the harvested area.
(iv)Postharvest slash treatment and stand conditions will lead to more moderate fire behavior in the professional judgment of the registered professional forester who submits the notice of exemption.
(v)Any additional guidance for slash treatment and postharvest stand conditions and any other issues deemed necessary that are consistent with this section, as established by the board.
(2)For purposes of this subdivision, habitable structure means a building that contains one or more dwelling units or that can be occupied for residential use. Buildings occupied for residential use include single-family homes, multidwelling structures, mobile and manufactured homes, and condominiums. For purposes of this subdivision, habitable structure does not include commercial, industrial, or incidental buildings such as detached garages, barns, outdoor sanitation facilities, and sheds.
(3)This subdivision shall become inoperative on January 1, 2031.
SEC. 2.Section 4584.1 of the Public Resources Code is amended to read:4584.1.Rules and regulations adopted by the board pursuant to Section 4584, except subdivision (k) of Section 4584, shall comply with the following standards, as determined appropriate and necessary by the board:
(a)Notices of exemption that are prepared and submitted to the director shall include a map of the area of operations that complies with the requirements of paragraphs (1), (3), and (4), subparagraphs (A), (B), (D), and (E) of paragraph (5), paragraphs (7) to (12), inclusive, and paragraph (14) of subdivision (x) of Section 1034 of Title 14 of the California Code of Regulations.
(b)Notices of exemption that are prepared and submitted to the director shall provide a confidential archaeological letter that includes all the information required by paragraphs (2) and (7) to (11), inclusive, of subdivision (c) of Sections 929.1, 949.1 and 969.1, as applicable, of Title 14 of the California Code of Regulations, and site records if required pursuant to subdivision (g) of that section or pursuant to Section 929.5 of Title 14 of the California Code of Regulations. This subdivision shall not apply to activities described in subdivision (i) or (m) of Section 4584.
(c)All fuel treatments required by the board shall be completed within one year from the date the director receives the notice, with the exception of burning. This shall include treatment of surface fuels, wood debris, and slash, which shall be lopped, removed, chipped, piled for burning, or otherwise treated. Burning shall be completed within two years from the date the director receives the notice of exemption.
(d)Slash and woody debris shall be treated to achieve a maximum post harvest depth of 18 inches above the ground except within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code. Surface fuels, slash, and woody debris within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code shall be chipped, piled, and burned, or removed.
(e)Timber operations shall comply with the requirements of paragraphs (1) to (10), inclusive, of subdivision (b) of Section 1038 of Title 14 of the California Code of Regulations.
(f)All timber operations conducted in Lake Tahoe Region shall have a valid Tahoe Basin Tree Removal Permit, as defined by the Tahoe Regional Planning Agency (TRPA), or shall be conducted under a valid TRPA Memorandum of Understanding, when such a permit is required by TRPA.
(g)The submitted notice of exemption shall include selection criteria for the trees to be harvested or the trees to be retained.
(h)The department shall provide the appropriate regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey with copies of notices of exemption when they are submitted.
(i)The submitted notice of exemption shall include the tentative commencement date of timber operations.
(j)Within a 15-day period, the registered professional forester or person responsible for the submittal of the notice of exemption shall notify the department, the Department of Fish and Wildlife, the appropriate regional water quality control board, and the California Geologic Survey of the actual date of commencement of timber operations.
(k)Timber operations pursuant to an exemption may not commence for 10 working days from the date of the directors receipt of the notice of exemption unless this delay is waived by the director. The director shall determine whether the notice of exemption is complete, and if so, shall send a copy of a notice of acceptance to the submitter. If the notice of exemption is not complete and accurate, it shall be returned to the submitter and the timber operator may not proceed. If the director does not act within 10 days of receipt of the notice of exemption, timber operations may commence.
(l)(1)No large old trees, defined as a tree that existed before 1800 AD or is greater than 60 inches in diameter at stump height for Sierra or Coast Redwoods, and 48 inches in diameter at stump height for all other tree species or Decadent and Deformed Trees with Value to Wildlife, as defined in Section 895.1 of Title 14 of the California Code of Regulations, shall be harvested unless the following apply:
(A)The tree is not critical for the maintenance of a Late Successional Stand.
(B)A registered professional forester attached to the submitted notice of exemption a written explanation and justification for the harvest of the tree based on the registered professional foresters finding of any of the following:
(i)The tree is a hazard to safety or property.
(ii)The removal of the tree is necessary for the construction of a building as approved by the appropriate local jurisdiction and shown on the county or city approved site plan, which shall be attached to the submitted notice of exemption.
(iii)The tree is dead or likely to die within one year of the date of the proposed removal, as determined by a registered professional forester.
(2)A registered professional forester-written explanation or justification need not be attached to the submitted notice of exemption if an approved Habitat Conservation Plan, Sustained Yield Plan, or plan, as that term is as defined in Section 895.1 of Title 14 of the California Code of Regulations addresses large old tree retention for the area in which the large old tree is proposed for removal and the removal is in compliance with the retention standards of that document.
(3)Any tree harvested pursuant to this subdivision shall be shown on a map provided with the submitted notice of exemption to the department.
(4)This subdivision shall not apply to or be used in conjunction with the Forest Resilience Exemption created pursuant to subdivision (j) of Section 4584.
(m)Helicopter yarding shall be prohibited.
(n)All applicable provisions of the Professional Foresters Law, including, but not limited to, Sections 775 to 779, inclusive, of this code, as well as all applicable provisions of Registration of Professional Forester Rules, including, but not limited to, Sections 1612 to 1614, inclusive, of Title 14 of the California Code of Regulations, shall apply to the practice of professional forestry as it relates to this section.
SEC. 3.Section 4584.2 of the Public Resources Code is amended to read:4584.2.Rules and regulations adopted by the board pursuant to subdivision (j) of Section 4584, shall comply with the following standards:
(a)Notices of exemption that are prepared and submitted to the director shall include a map of the area of operations that complies with the requirements of paragraphs (1), (3), and (4), subparagraphs (A), (B), (D), and (E) of paragraph (5), paragraphs (7) to (12), inclusive, and paragraph (14) of subdivision (x) of Section 1034 of Title 14 of the California Code of Regulations.
(b)Notices of exemption that are prepared and submitted to the director shall provide a confidential archaeological letter that includes all the information required by paragraphs (2) and (7) to (11), inclusive, of subdivision (c) of Sections 929.1, 949.1 and 969.1, as applicable, of Title 14 of the California Code of Regulations, and site records if required pursuant to subdivision (g) of that section or pursuant to Section 929.5 of Title 14 of the California Code of Regulations.
(c)All fuel treatments required by the board shall be completed within one year from the date the director receives the notice, with the exception of burning. This shall include treatment of surface fuels, wood debris, and slash, which shall be lopped, removed, chipped, piled for burning, or otherwise treated. Burning shall be completed within two years from the date the director receives the notice of exemption.
(d)Slash and woody debris shall be treated to achieve a maximum post harvest depth of 18 inches above the ground except within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code. Surface fuels, slash, and woody debris within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code shall be chipped, burned, or removed.
(e)Timber operations shall comply with the requirements of paragraphs (1) to (4), inclusive, and (6) to (10), inclusive, of subdivision (b) of Section 1038 of Title 14 of the California Code of Regulations.
(f)All timber operations conducted in Lake Tahoe Region must have a valid Tahoe Basin Tree Removal Permit, as defined by the Tahoe Regional Planning Agency (TRPA), or shall be conducted under a valid TRPA Memorandum of Understanding, when such a permit is required by TRPA.
(g)The submitted notice of exemption shall include selection criteria for the trees to be harvested or the trees to be retained.
(h)The department shall provide the appropriate regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey with copies of notices of exemption when they are submitted.
(i)The submitted notice of exemption shall include the tentative commencement date of timber operations.
(j)Within a 15-day period, the registered professional forester responsible for the submittal of the notice of exemption shall notify the department, the Department of Fish and Wildlife, the appropriate regional water quality control board, and the California Geologic Survey of the actual date of commencement of timber operations.
(k)Operations pursuant to an exemption may not commence for 10 working days from the date of the directors receipt of the notice of exemption unless this delay is waived by the director. The director shall determine whether the notice of exemption is complete, and if so, shall send a copy of a notice of acceptance to the submitter. If the notice of exemption is not complete and accurate, it shall be returned to the submitter and the timber operator may not proceed. If the director does not act within five days of receipt of the notice of exemption, timber operations may commence.
(l)(1)No Decadent and Deformed Trees with Value to Wildlife, as defined in Section 895.1 of Title 14 of the California Code of Regulations, shall be harvested unless all the following apply:
(A)The tree is not critical for the maintenance of a Late Successional Stand.
(B)A registered professional forester attached to the submitted notice of exemption a written explanation and justification for the harvest of the tree based on the registered professional foresters finding of any of the following:
(i)The tree is a hazard to safety or property.
(ii)The removal of the tree is necessary for the construction of a building as approved by the appropriate local jurisdiction and shown on the county or city approved site plan which shall be attached to the submitted notice of exemption.
(iii)The tree is dead or likely to die within one year of the date of the proposed removal, as determined by a registered professional forester.
(2)A registered professional foresters written explanation or justification need not be attached to the submitted notice of exemption if an approved Habitat Conservation Plan, Sustained Yield Plan, or plan as that term is defined in Section 895.1 of Title 14 of the California Code of Regulations addresses large old tree retention for the area in which the large old tree is proposed for removal and the removal is in compliance with the retention standards of that document.
(3)Any tree harvested pursuant to this subdivision shall be shown on a map provided with the submitted notice of exemption to the department.
(4)This subdivision shall not apply to or be used in conjunction with the Forest Resilience Exemption created pursuant to subdivision (j) of Section 4584.
(m)Helicopter yarding shall be prohibited.
(n)All applicable provisions of the Professional Foresters Law, including, but not limited to, Sections 775 to 779, inclusive, of this code, as well as all applicable provisions of Registration of Professional Forester Rules, including, but not limited to, Sections 1612 to 1614, inclusive, of Title 14 of the California Code of Regulations apply to the practice of professional forestry as it relates to this section.
SEC. 4.Section 4589 of the Public Resources Code is amended to read:4589.(a)The department and board, in consultation with the Department of Fish and Wildlife, and the State Water Resources Control Board, shall shall, commencing December 31, 2019, and annually thereafter, review and submit a report to the Legislature on the trends in the use of, compliance with, and effectiveness of, the exemptions and emergency notice provisions described in Sections 4584 and 4592 of this code and Sections 1038 and 1052 of Title 14 of the California Code of Regulations. The report shall include an analysis of exemption use and whether the exemptions are having the intended effect. The report shall also include recommendations to improve the use of those exemptions and emergency notice provisions, information on the linear distance of road constructed or reconstructed under notices of exemption by individual ownerships, within a representative sample of planning watersheds from each forest practice district as defined in Sections 907 to 909, inclusive, of Title 14 of the California Code of Regulations, and violations associated with road reconstruction. The report shall include information on the number and type of violations and enforcement actions taken on each notice of exemption and emergency notice. The report shall also contain the number of posttreatment onsite inspections that occur and whether those inspections were attended by a representative of the Department of Fish and Wildlife and a representative of the State Water Resources Control Board. The report submitted on December 31, 2025, shall include recommendations necessary for revisions to diameter limits at stump heights of harvestable trees under subdivisions (j) and (k) of Section 4584, as those subdivisions read on January 1, 2024.
(b)The public shall be provided opportunities to participate in the review and the development of the report.
(c)The report shall be submitted pursuant to Section 9795 of the Government Code.
(d)(A)This section shall be operative for a period of five years after the effective date of emergency regulations as adopted by the board and as of that date is inoperative.
(B)The board shall notify the Secretary of State when emergency regulations have been adopted.
SEC. 5.Section 399.20.3 of the Public Utilities Code is amended to read:399.20.3.(a)For purposes of this section, the following definitions apply:
(1)Bioenergy has the same meaning as set forth in paragraph (6) of subdivision (f) of Section 399.20.
(2)Tier 1 high hazard zone includes areas where wildlife and falling trees threaten electrical transmission and distribution lines, roads, and other evacuation corridors, critical community infrastructure, or other existing structures, as designated by the Department of Forestry and Fire Protection pursuant to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(3)Tier 2 high hazard zone includes watersheds that have significant tree mortality combined with community and natural resource assets, as designated by the Department of Forestry and Fire Protection pursuant to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(b)(1)In addition to the requirements of subdivision (f) of Section 399.20, by December 1, 2023, electrical corporations shall collectively procure, through financial commitments of 5 to 15 years, inclusive, their proportionate share of 125 megawatts of cumulative rated generating capacity from existing bioenergy projects that commenced operations before June 1, 2013. At least 80 percent of the feedstock of an eligible facility, on an annual basis, shall be a byproduct of sustainable forestry management, which includes removal of dead and dying trees from Tier 1 and Tier 2 high hazard zones and is not that from lands that have been clear cut. At least 60 percent of this feedstock shall be from Tier 1 and Tier 2 high hazard zones.
(2)Paragraph (1) shall not apply to a utility subject to subdivision (g) if both of the following apply:
(A)The utility, either directly or through a joint powers authority, entered into five-year financial commitments for its proportionate share of 125 megawatts of cumulative rated generating capacity from existing bioenergy projects pursuant to this section as it was enacted by Chapter 368 of the Statutes of 2016.
(B)The utilitys financial commitments referenced in subparagraph (A) include, (1) a contract with a facility operator that was, on June 1, 2022, in a bankruptcy or other insolvency proceeding, or (2) a contract for a project that does not deliver energy to the utility.
(c)For the purpose of contracts entered into pursuant to subdivision (b), commission Resolution E-4770 (March 17, 2016), and commission Resolution E-4805 (October 13, 2016), Tier 1 and Tier 2 high hazard zone fuel or feedstock shall also include biomass fuels removed from fuel reduction operations exempt from timber harvesting plan requirements pursuant to subdivisions (a), (f), (j), and (k) of Section 4584 of the Public Resources Code, as those subdivisions read on January 1, 2024.
(d)The commission shall require an electrical corporation that has entered into a contract pursuant to subdivision (b), commission Resolution E-4770 (March 17, 2016), or commission Resolution E-4805 (October 13, 2016) to allow fuel or feedstock reporting requirements to be based on a monthly or annual basis, and a bioenergy facility providing generation pursuant to that contract shall have the right to opt out of the mandated fuel or feedstock usage levels in any particular month upon providing written notice to the electrical corporation in the month of operation. For months in which a bioenergy facility opts out of the mandated fuel or feedstock usage levels or misses the mandated fuel or feedstock targets, that facility shall be paid the alternate price adopted by the commission in commission Resolution E-4770 for all megawatthours generated during that month. Contracts shall continue in force through the end of the contracted term without creating an event of default for missing mandated fuel or feedstock usage levels and without giving rise to a termination right in favor of the electrical corporation.
(e)(1)For each electrical corporation, the commission shall allocate its proportionate share of the 125 megawatts based on the ratio of the electrical corporations peak demand to the total statewide peak demand.
(2)Procurement by an electrical corporation of generation capacity pursuant to a contract under the commissions Resolution E-4770 (March 17, 2016) that is in excess of the requirement of that electrical corporation under that resolution shall count towards meeting the electrical corporations proportionate share allocated pursuant to paragraph (1).
(f)The commission may direct each electrical corporation to develop standard contract terms and conditions that reflect the operational characteristics of the bioenergy projects and to provide a streamlined contracting process or may require the electrical corporations to use the mechanism established pursuant to the commissions Resolution E-4770 (March 17, 2016) to meet the requirements of subdivision (e). The procurement pursuant to the developed standard contract shall occur on an expedited basis due to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(g)A local publicly owned electric utility serving more than 100,000 customers shall procure its proportionate share, based on the ratio of the utilitys peak demand to the total statewide peak demand, of 125 megawatts of cumulative rated capacity from existing bioenergy projects described in subdivision (b) subject to terms of at least five years.
(h)The commission shall ensure that the costs of any contract procured by an electrical corporation to satisfy the requirements of this section are recoverable from all customers on a nonbypassable basis.
(i)The Procurement Review Group within the commission shall advise the commission on the cost of the generation procured pursuant to this section and its impact on ratepayers.
(j)For purposes of this section, any incremental procurement of electricity products from bioenergy resources by a new contract or contract extension of five years or longer in duration shall be from a resource that meets emission limits equivalent to, or more stringent than, the applicable best available retrofit control technology, as determined by the local air pollution control district or air quality management district. The determination shall be made before the start of the operating period under the new contract or contract extension.
Upon determining that this exemption is consistent with the purposes of this chapter, the board may exempt from this chapter, or portions of this chapter, a person engaged in forest management whose activities are limited to any of the following:
(a)The cutting or removal of trees for the purpose of constructing or maintaining a right-of-way for utility lines.
(b)The planting, growing, nurturing, shaping, shearing, removal, or harvest of immature trees for Christmas trees or other ornamental purposes or minor forest products, including fuelwood.
(c)The cutting or removal of dead, dying, or diseased trees of any size.
(d)Site preparation.
(e)Maintenance of drainage facilities and soil stabilization treatments.
(f)Timber operations on land managed by the Department of Parks and Recreation.
(g)(1)The one-time conversion of less than three acres to a nontimber use. A person, whether acting as an individual, as a member of a partnership, or as an officer or employee of a corporation or other legal entity, shall not obtain more than one exemption pursuant to this subdivision in a five-year period. If a partnership has as a member, or if a corporation or other legal entity has as an officer or employee, a person who has received this exemption within the past five years, whether as an individual, as a member of a partnership, or as an officer or employee of a corporation or other legal entity, then that partnership, corporation, or other legal entity is not eligible for this exemption. Person, for purposes of this subdivision, means an individual, partnership, corporation, or other legal entity.
(2)(A)Notwithstanding Section 4554.5, the board shall adopt regulations that do all of the following:
(i)Identify the required documentation of a bona fide intent to complete the conversion that an applicant will need to submit in order to be eligible for the exemption in paragraph (1).
(ii)Authorize the department to inspect the sites approved in conversion applications that have been approved on or after January 1, 2002, in order to determine that the conversion was completed within the two-year period described in subparagraph (B) of paragraph (2) of subdivision (a) of Section 1104.1 of Title 14 of the California Code of Regulations.
(iii)Require the exemption pursuant to this subdivision to expire if there is a change in timberland ownership. The person who originally submitted an application for an exemption pursuant to this subdivision shall notify the department of a change in timberland ownership on or before five calendar days after a change in ownership.
(iv)The board may adopt regulations allowing a waiver of the five-year limitation described in paragraph (1) upon finding that the imposition of the five-year limitation would impose an undue hardship on the applicant for the exemption. The board may adopt a process for an appeal of a denial of a waiver.
(v)The board may adopt regulations allowing a waiver of the one-time limitation described in paragraph (1) upon finding that the imposition of the one-time limitation would impose an undue hardship on the applicant. The board may adopt a process for an appeal of a denial of a waiver.
(B)The application form for the exemption pursuant to paragraph (1) shall prominently advise the public that a violation of the conversion exemption, including a conversion applied for in the name of someone other than the person or entity implementing the conversion in bona fide good faith, is a violation of this chapter and penalties may accrue up to ten thousand dollars ($10,000) for each violation pursuant to Article 8 (commencing with Section 4601).
(h)An easement granted by a right-of-way construction agreement administered by the federal government if timber sales and operations within or affecting the area are reviewed and conducted pursuant to the federal National Environmental Policy Act of 1969 (42 U.S.C. Sec. 4321 et seq.).
(i)(1)The cutting or removal of trees in compliance with Sections 4290 and 4291 that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break for a distance of not more than 150 feet on each side from an approved and legally permitted structure that complies with the California Building Standards Code, when that cutting or removal is conducted in compliance with this subdivision. For purposes of this subdivision, an approved and legally permitted structure includes only structures that are designed for human occupancy, garages, barns, stables, and structures used to enclose fuel tanks.
(2)(A)The cutting or removal of trees pursuant to this subdivision is limited to cutting or removal that will result in a reduction in the rate of fire spread, fire duration and intensity, fuel ignitability, or ignition of the tree crowns and shall be in accordance with any regulations adopted by the board pursuant to this section.
(B)Trees shall not be cut or removed pursuant to this subdivision by the clearcutting regeneration method, by the seed tree removal step of the seed tree regeneration method, or by the shelterwood removal step of the shelterwood regeneration method.
(3)(A)All fuel treatments conducted pursuant to this subdivision that do not comply with board rules and regulations may be determined to be a nuisance and subject to abatement by the department or the city or county having jurisdiction.
(B)The costs incurred by the department, city, or county, as the case may be, to abate the nuisance upon a parcel of land subject to the timber operations, including, but not limited to, investigation, boundary determination, measurement, and other related costs, may be recovered by special assessment and lien against the parcel of land by the department, city, or county. The assessment may be collected at the same time and in the same manner as ordinary ad valorem taxes, and shall be subject to the same penalties and the same procedure and sale in case of delinquency as is provided for ad valorem taxes.
(4)All timber operations conducted pursuant to this subdivision shall conform to applicable city or county general plans, city or county implementing ordinances, and city or county zoning ordinances. This paragraph does not authorize the cutting, removal, or sale of timber or other solid wood forest products within an area where timber harvesting is prohibited or otherwise restricted pursuant to the rules or regulations adopted by the board.
(5)(A)The board shall adopt regulations, initially as emergency regulations in accordance with subparagraph (B), that the board considers necessary to implement and to obtain compliance with this subdivision.
(B)The emergency regulations adopted pursuant to subparagraph (A) shall be adopted in accordance with the Administrative Procedure Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code). The adoption of emergency regulations shall be deemed to be an emergency and necessary for the immediate preservation of the public peace, health, and safety, or general welfare.
(j)(1)The cutting or removal of trees on the persons property that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break. An exemption pursuant to this subdivision shall be known as the Small Timberland Owner Exemption. The cutting or removal of trees in compliance with this subdivision shall be subject to all of the following conditions:(A)The notice of exemption is prepared, signed, and submitted by a registered professional forester to the department.(B)The residual stocking standards are consistent with the following standards and shall be achieved through uneven-aged management, as defined in Section 895.1 of Title 14 of the California Code of Regulations excluding group selection:(i)On Site I lands at least 150 square feet of basal area shall be retained within the coast forest district, as defined in Section 907 of Title 14 of the California Code of Regulations, while at least 100 square feet of basal area shall be retained within the northern and southern districts, as defined in Section 908 or 909, respectively, of Title 14 of the California Code of Regulations.(ii)On Site II lands at least 100 square feet of basal area shall be retained within the coast district, while at least 75 square feet of basal area shall be retained within the northern and southern districts.(iii)On Site III lands at least 75 square feet of basal area shall be retained.(C)(i)Forest management activities will increase the quadratic mean diameter of the stand.(ii)Increases in quadratic mean diameter shall only consider trees greater than eight inches in diameter at breast height. The registered professional forester responsible for preparation of the notice of exemption shall report the expected postharvest increase in quadratic mean diameter.(D)(i)The residual stand consists primarily of healthy and vigorous dominant and codominant trees from the preharvest stand, well distributed through the harvested area.(ii)No trees of the genus quercus that are greater than 26 inches in diameter at stump height, measured 8 inches above ground level, shall be harvested under a notice of exemption submitted pursuant to this subdivision.(iii)No trees greater than 32 inches in diameter at stump height, measured 8 inches above ground level, shall be harvested under a notice of exemption submitted pursuant to this subdivision.(iv)The six largest trees per acre within the boundaries of a notice of exemption submitted pursuant to this subdivision shall not be harvested.(v)The postharvest composition of tree species shall be representative of the preharvest stand condition and demonstrate progression towards climax forest conditions, unless the registered professional forester provides justification explaining how modification of species diversity will benefit forest health and resiliency.(E)The submitted notice of exemption shall include a description of the preharvest stand structure and a statement of the minimum expected postharvest stocking.(F)All trees harvested or all trees retained shall be marked by, or under the supervision of, a registered professional forester before felling operations begin.(G)The board shall adopt regulations for the treatment of understory vegetation and standing dead fuels, canopy closure, clearance to base of live crown, or ladder fuels, that could promote the spread of wildfire. A fuel reduction effort conducted under a submitted notice of exemption pursuant to this subdivision shall comply with the canopy closure regulations adopted by the board on June 10, 2004, and as those regulations may be amended.(H)A notice of exemption submitted to the department that is within the coast forest district is submitted for a small forestland owner who owns 60 acres or less of timberland within a single planning watershed.(I)A notice of exemption submitted to the department that is within the northern forest district or the southern forest district is submitted for a small forestland owner who owns 100 acres or less of timberland within a single planning watershed.(2)(A)All timber operations conducted pursuant to this subdivision may only occur once on any given acre per any 10-year period of time. The department shall only grant a maximum of three exemptions under the Small Timberland Owner Exemption per landowner.(B)Except for the harvesting of dead, diseased, or dying trees, during this 10-year period the department shall not approve a plan, as defined in Section 895.1 of Title 14 of the California Code of Regulations, that allows even-aged silviculture prescriptions. During this 10-year period of time a registered professional forester shall not submit a notice of exemption pursuant to subdivision (k) on portions of the property subject to an exemption pursuant to this subdivision.(3)The department may conduct an onsite inspection to determine compliance with this subdivision. The department may notify the regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey before conducting the onsite inspection. The regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey may conduct an inspection with the department.(4)This subdivision shall become inoperative on January 1, 2031.(k)(j)(1)The harvesting of trees, limited to those trees that eliminate the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns, for the purpose of reducing the rate of fire spread, duration and intensity, fuel ignitability, or ignition of tree crowns. An exemption pursuant to this paragraph shall be known as the Forest Fire Prevention Resilience Exemption.
(2)The board may authorize an exemption pursuant to paragraph (1) only if the tree harvesting will decrease fuel continuity and increase the quadratic mean diameter of the stand, and the tree harvesting area will not exceed 300 500 acres. Increases in quadratic mean diameter shall only consider trees greater than eight inches in diameter at breast height. The notice of exemption may be authorized only if all of the conditions specified in paragraphs (3) to (9), inclusive, are met.
(3)A registered professional forester shall prepare the notice of exemption and submit it to the director.
(4)(A)The submitted notice of exemption shall include a description of the preharvest stand structure and a statement of the postharvest stand stocking levels and the expected postharvest increase in quadratic mean diameter.
(B)The level of residual stocking shall be consistent with maximum sustained production of high-quality timber products. The residual stand shall consist primarily of healthy and vigorous dominant and codominant trees from the preharvest stand. Stocking shall not be reduced below the standards required by the following provisions that apply to the exemption at issue:
(i)Clauses 1 to 4, inclusive, of subparagraph (A) of paragraph (1) of subdivision (a) of Sections 913.3, 933.3, and 953.3 of Title 14 of the California Code of Regulations, where appropriate. or clauses 1 to 4, inclusive, of subparagraph (A) of paragraph (2) of subdivision (a) of Sections 913.2, 933.2, and 953.2 of Title 14 of the California Code of Regulations.
(ii)The registered professional forester responsible for preparing the notice of exemption shall identify the designated postharvest stocking within the notice of exemption. The selected stocking shall be applicable to, and consistent with, silviculture that would apply to the preharvest stand condition provided pursuant to subparagraph (A).
(iii)Additional information on preharvest stand conditions, including, but not limited to, stand ages, stand structure, past management activities, and landowner goals and objectives shall also be provided by the registered professional forester preparing and submitting the exemption that substantiates the selection of postharvest stocking.
(C)If Within the coast district, if the preharvest dominant and codominant crown canopy is occupied by trees less than 14 inches in diameter at breast height, a minimum of 100 trees over four 4 inches in diameter at breast height shall be retained per acre for Site I, II, and III lands, and a minimum of 75 trees over four 4 inches in diameter at breast height shall be retained per acre for Site IV and V lands.
(D)Within the northern district and southern district, if the preharvest dominant and codominant crown canopy is occupied by trees less than 14 inches in diameter at breast height, a minimum of 65 trees over 4 inches in diameter at breast height shall be retained.
(D)(E)All trees that are harvested or all trees that are retained shall be marked or sample marked by, or under the supervision of, a registered professional forester before felling operations begin. The board shall adopt regulations for sample marking for this section in Title 14 of the California Code of Regulations. Sample marking shall be limited to homogenous forest stand conditions typical of plantations.
(F)The board may adopt specific regulations for the removal of dead and dying trees in amounts less than 10 percent of the average volume per acre for trees up to 36 inches in diameter at breast height. Regulations adopted by the board shall consider safety, fuel hazard abatement, mortality capture, the adequacy and retention of wildlife trees, especially those trees over 30 inches in diameter at breast height, and standards of enforceability for the department. All trees over 30 inches in diameter at breast height that are harvested pursuant to this paragraph shall be marked by, or under the supervision of, a registered professional forester before felling. The registered professional forester shall consult with the director before felling any dead or dying trees in excess of 30 inches in diameter at breast height.
(G)All trees harvested pursuant to this paragraph shall be marked by, or under the supervision of, a registered professional forester before felling operations begin.
(H)The six largest trees per acre within the boundaries of a notice of exemption submitted pursuant to this subdivision shall not be harvested.
(I)No trees of the genus Quercus that are greater than 22 inches in diameter at breast height shall be harvested under a notice of exemption submitted pursuant to this subdivision, except for those trees that need to be removed to mitigate safety.
(5)(A)The board shall adopt regulations for the treatment of understory vegetation and standing dead fuels, canopy closure, clearance to base of live crown, or ladder fuels, that could promote the spread of wildfire. A fuel reduction effort conducted under a submitted notice of exemption pursuant to this subdivision shall comply with the canopy closure regulations adopted by the board on June 10, 2004, and as those regulations may be amended. The board may adopt regulations pertaining to canopy closure if determined appropriate and necessary.
(B)The postharvest stand shall not contain more than 200 trees over three inches in diameter per acre.(C)Vertical spacing shall be achieved by treating dead fuels to a minimum clearance distance of eight feet measured from the base of the live crown of the postharvest dominant and codominant trees to the top of the dead surface fuels.(B)Slash and woody debris within 50 feet of a public road or critical infrastructure, as defined by the board, shall be chipped, burned, or removed.
(D)(C)The standards required by subparagraphs (A) to (C), inclusive, and (B) shall be achieved on approximately 80 percent of the treated area.
(6) Before the submission of a notice of exemption to the department, the registered professional forester responsible for submitting the notice shall designate temporary road locations, landing locations, tractor road crossings of class Class III watercourses, unstable areas, or connected headwall swales on the ground and map their locations.
(7)The construction or reconstruction of temporary roads on slopes of 30 percent or less shall be allowed if all of the following conditions are met:
(A)Temporary roads or landings shall not be located on unstable areas, as defined in Section 895.1 of Title 14 of the California Code of Regulations.
(B)Temporary roads shall be single-lane in width.
(C)Temporary roads shall not be located across a connected headwall swale, as defined in Section 895.1 of Title 14 of the California Code of Regulations.
(D)Construction or reconstruction of temporary roads, landings, or watercourse crossings shall not occur during the winter operating period. Pursuant to subdivision (g) of Sections 923.6, 943.6, and 963.6, as applicable, of Title 14 of the California Code of Regulations, roads and landings used for log hauling or other heavy equipment uses during the winter period shall occur on a stable operating surface and, where necessary, be surfaced with rock to a depth and quantity sufficient to maintain the stable operating surface. Use shall be prohibited on roads that are not hydrologically disconnected and exhibit saturated soil conditions. Timber operations during the winter period shall comply with paragraphs (1) and (2) of subdivision (c) of Sections 914.7, 934.7, and 954.7, as applicable, of Title 14 of the California Code of Regulations.
(E)Use of temporary roads shall comply with the operational provisions of Article 12 (commencing with Section 923) of Subchapter 4 of Chapter 4 of Division 1.5 of Title 14 of the California Code of Regulations, and recognize guidance on hydrologic disconnection in Technical Rule Addendum Number 5.
(F)No logging road or landings construction or reconstruction activities of any kind shall occur within 200 feet of class Class I and class Class II watercourses or within 50 feet of a class Class III watercourse.
(G)The landowner shall retain a registered professional forester who is available to provide professional advice to the licensed timber operator and timberland owner throughout the active timber operations. The name, address, telephone number, and registration number of the retained registered professional forester shall be provided on the submitted notice of exemption. This professional advice shall include overseeing the construction or reconstruction of any temporary roads or landings and advising on necessary mitigation to avoid potential impacts to associated watershed and forest resources. The registered professional forester shall also comply with Section 1035.2 of Title 14 of the California Code of Regulations, relating to interaction between the licensed timber operator and the registered professional forester.
(H)The registered professional forester responsible for submitting the notice of exemption shall affirm that the construction or reconstruction of each temporary road is necessary to provide access to harvest areas where no feasible alternative exists. The submitted notice of exemption shall include the number and cumulative length of temporary roads that will be constructed or reconstructed.
(I)(i)Temporary road construction or reconstruction, reconsruction shall be limited to no more than two miles of road per ownership in a planning watershed per any five-year period.
(ii)For each exemption affecting less than 40 acres, all temporary roads constructed or reconstructed under this exemption shall not exceed a cumulative length of 300 feet.
(iii)For each exemption affecting between 40 and 80 acres, all temporary roads constructed or reconstructed under this exemption shall not exceed a cumulative length of between 300 and 600 feet, as determined on a pro rata basis by the total acreage affected by the exemption.
(iv)For each exemption affecting over 80 acres, all temporary roads constructed or reconstructed under the exemption shall not exceed a cumulative length of 600 feet. The submitted notice of exemption shall list the number of acres affected and the cumulative length of the road in feet.
(v)Temporary roads constructed or reconstructed under this exemption shall not be connected to other temporary roads constructed under previous or subsequent exemptions filed under this paragraph.
(vi)All temporary roads shall be abandoned using proactive measures that have been applied to effectively remove them from the permanent road network, in accordance with the definition of abandoned road as defined in Section 895.1 of Title 14 of the California Code of Regulations.
(vii)This paragraph shall not be interpreted to permit road construction or reconstruction except as authorized under the Forest Fire Prevention Resilience Exemption, pursuant to this paragraph.
(viii)No trees larger than 36 inches in diameter at stump height, measured 8 inches above ground level, 30 inches in diameter at breast height shall be removed for the purposes of road construction or reconstruction under a notice of exemption submitted pursuant to this subdivision. A tree that is between 30 and 36 inches in diameter at stump height, measured 8 inches above ground level, may be removed for the purposes of road construction or reconstruction under a notice of exemption submitted pursuant to this subdivision only if there are no feasible alternatives for the road placement.
(8)Except within constructed or reconstructed temporary road prisms, only trees less than 30 inches in stump diameter, measured at eight inches above ground level, may be removed. Only trees less than 30 inches in diameter at breast height may be removed. The board, in consultation with the department, shall develop clearly written guidance documents on inspection and enforceability standards relating to standards set forth in this paragraph.
(9)All timber operations conducted pursuant to this subdivision shall only occur within the most recent version of the departments Fire Hazard Severity Zone Map in the moderate, high, and very high fire threat zones.
(10)If pesticides or herbicides will be used within the boundaries of an area covered by a notice of exemption pursuant to this paragraph within one year of director acceptance, the timberland owner shall notify the appropriate regional water quality control board 10 days before application of any pesticides or herbicides.
(11)After the timber operations are complete, the department shall conduct an onsite inspection to determine compliance with this subdivision and whether appropriate enforcement action should be initiated. The department shall notify the appropriate regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey seven days prior to conducting the onsite inspection. The regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey may conduct an inspection with the department.
(12)This subdivision shall become inoperative on January 1, 2031.
(l)(k)The cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands, if all of the following requirements are met:
(1)A registered professional forester shall prepare the notice of exemption and submit it to the director. The notice shall include all of the following:
(A)A certification signed by the registered professional forester that a minimum of 35 square feet of basal area per acre of California black or Oregon white oak, or both, occupy the proposed treatment area at the time the notice is prepared and the timber operation is designed to restore and conserve California black and Oregon white oak woodlands and associated grasslands.
(B)A description of the preharvest stand structure and a statement of the postharvest stand stocking levels.
(2)No tree larger than 26 inches in diameter at stump height shall be harvested for commercial purposes, which includes use for saw logs, posts and poles, fuel wood, biomass, or other forest products.
(3)Only conifers within 300 feet of a California black or Oregon white oak that are at minimum four inches in diameter at breast height may be harvested.
(4)The total area exempted pursuant to this subdivision shall not exceed 300 acres per property per five-year period.
(5)Conifer shall be reduced to less than 25 percent of the combined hardwood and conifer postharvest stand stocking levels.
(6)No more than 20 percent of the total basal area of preexisting oak stock shall be cut or removed during harvest and a minimum of 35 square feet of basal area per acre of California black or Oregon white oak, or both, shall be maintained postharvest.
(7)Slash shall be configured so as to minimize the risk of fire mortality to the remaining oak trees.
(8)The board shall adopt regulations to implement this subdivision.(9)(8)This subdivision shall not apply to the Southern Subdistrict of the Coast Forest District, as defined in Section 895.1 of Title 14 of the California Code of Regulations, or the Southern Forest District, as defined in Section 909 of Title 14 of the California Code of Regulations.
(m)(l)(1)The board may exempt from this chapter, or portions of this chapter, a person engaged in forest management whose activities are limited to the cutting or removal of trees on the persons property in compliance with Sections 4290 and 4291 that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuelbreak fuel break for a distance of not more than 300 feet on each side from an approved and legally permitted habitable structure, when that cutting or removal is conducted in compliance with this subdivision and all of the following conditions are met:
(A)The notice of exemption is prepared, signed, and submitted by a registered professional forester to the department.
(B)For the areas between 150 and 300 feet from the habitable structure, the operations meet all of the following provisions:
(i)The residual stocking standards are consistent with Sections 913.2, 933.2, and 953.2 of Title 14 of the California Code of Regulations, as appropriate.
(ii)Activities within this area will increase the quadratic mean diameter of the stand.
(iii)The residual stand consists primarily of healthy and vigorous dominant and codominant trees from the preharvest stand, well distributed throughout the harvested area.
(iv)Postharvest slash treatment and stand conditions will lead to more moderate fire behavior in the professional judgment of the registered professional forester who submits the notice of exemption.
(v)Any additional guidance for slash treatment and postharvest stand conditions and any other issues deemed necessary that are consistent with this section, as established by the board.
(2)For purposes of this subdivision, habitable structure means a building that contains one or more dwelling units or that can be occupied for residential use. Buildings occupied for residential use include single-family homes, multidwelling structures, mobile and manufactured homes, and condominiums. For purposes of this subdivision, habitable structure does not include commercial, industrial, or incidental buildings such as detached garages, barns, outdoor sanitation facilities, and sheds.
(3)This subdivision shall become inoperative on January 1, 2031.
SEC. 2.Section 4584.1 of the Public Resources Code is amended to read:4584.1.Rules and regulations adopted by the board pursuant to Section 4584, except subdivision (k) of Section 4584, shall comply with the following standards, as determined appropriate and necessary by the board:
(a)Notices of exemption that are prepared and submitted to the director shall include a map of the area of operations that complies with the requirements of paragraphs (1), (3), and (4), subparagraphs (A), (B), (D), and (E) of paragraph (5), paragraphs (7) to (12), inclusive, and paragraph (14) of subdivision (x) of Section 1034 of Title 14 of the California Code of Regulations.
(b)Notices of exemption that are prepared and submitted to the director shall provide a confidential archaeological letter that includes all the information required by paragraphs (2) and (7) to (11), inclusive, of subdivision (c) of Sections 929.1, 949.1 and 969.1, as applicable, of Title 14 of the California Code of Regulations, and site records if required pursuant to subdivision (g) of that section or pursuant to Section 929.5 of Title 14 of the California Code of Regulations. This subdivision shall not apply to activities described in subdivision (i) or (m) of Section 4584.
(c)All fuel treatments required by the board shall be completed within one year from the date the director receives the notice, with the exception of burning. This shall include treatment of surface fuels, wood debris, and slash, which shall be lopped, removed, chipped, piled for burning, or otherwise treated. Burning shall be completed within two years from the date the director receives the notice of exemption.
(d)Slash and woody debris shall be treated to achieve a maximum post harvest depth of 18 inches above the ground except within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code. Surface fuels, slash, and woody debris within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code shall be chipped, piled piled, and burned, or removed.
(e)Timber operations shall comply with the requirements of paragraphs (1) to (10), inclusive, of subdivision (b) of Section 1038 of Title 14 of the California Code of Regulations.
(f)All timber operations conducted in Lake Tahoe Region must shall have a valid Tahoe Basin Tree Removal Permit, as defined by the Tahoe Regional Planning Agency (TRPA), or shall be conducted under a valid TRPA Memorandum of Understanding, when such a permit is required by TRPA.
(g)The submitted notice of exemption shall include selection criteria for the trees to be harvested or the trees to be retained.
(h)The department shall provide the appropriate regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey with copies of notices of exemption when they are submitted.
(i)The submitted notice of exemption shall include the tentative commencement date of timber operations.
(j)Within a 15-day period, the registered professional forester or person responsible for the submittal of the notice of exemption shall notify the department, the Department of Fish and Game, Wildlife, the appropriate regional water quality control board, and the California Geologic Survey of the actual date of commencement of timber operations.
(k)Timber operations pursuant to an exemption may not commence for 10 working days from the date of the directors receipt of the notice of exemption unless this delay is waived by the director. The director shall determine whether the notice of exemption is complete, and if so, shall send a copy of a notice of acceptance to the submitter. If the notice of exemption is not complete and accurate, it shall be returned to the submitter and the timber operator may not proceed. If the director does not act within 10 days of receipt of the notice of exemption, timber operations may commence.
(l)(1)No large old trees, defined as a tree that existed before 1800 AD or is greater than 60 inches in diameter at stump height for Sierra or Coast Redwoods, and 48 inches in diameter at stump height for all other tree species or Decadent and Deformed Trees with Value to Wildlife, as defined in Section 895.1 of Title 14 of the California Code of Regulations, shall be harvested unless the following apply:
(A)The tree is not critical for the maintenance of a Late Successional Stand.
(B)A registered professional forester attached to the submitted notice of exemption a written explanation and justification for the harvest of the tree based on the registered professional foresters finding of any of the following:
(i)The tree is a hazard to safety or property.
(ii)The removal of the tree is necessary for the construction of a building as approved by the appropriate local jurisdiction and shown on the county or city approved site plan, which shall be attached to the submitted notice of exemption.
(iii)The tree is dead or likely to die within one year of the date of the proposed removal, as determined by a registered professional forester.
(2)A registered professional forester-written explanation or justification need not be attached to the submitted notice of exemption if an approved Habitat Conservation Plan, Sustained Yield Plan, or plan, as that term is as defined in Section 895.1 of Title 14 of the California Code of Regulations addresses large old tree retention for the area in which the large old tree is proposed for removal and the removal is in compliance with the retention standards of that document.
(3)Any tree harvested pursuant to this subdivision shall be shown on a map provided with the submitted notice of exemption to the department.
(4)This subdivision shall not apply to or be used in conjunction with either the Small Timberland Owner Exemption created pursuant to subdivision (j) of Section 4584 or with the Forest Fires Prevention the Forest Resilience Exemption created pursuant to subdivision (k) (j) of Section 4584.
(m)Helicopter yarding shall be prohibited.
(n)All applicable provisions of the Professional Foresters Law, including, but not limited to, Sections 775 to 779, inclusive, of this code, as well as all applicable provisions of Registration of Professional Forester Rules, including, but not limited to, Sections 1612 to 1614, inclusive, of Title 14 of the California Code of Regulations, shall apply to the practice of professional forestry as it relates to this section.
SEC. 3.Section 4584.2 of the Public Resources Code is amended to read:4584.2.Rules and regulations adopted by the board pursuant to subdivision (k) (j) of Section 4584, shall comply with the following standards:
(a)Notices of exemption that are prepared and submitted to the director shall include a map of the area of operations that complies with the requirements of paragraphs (1), (3), and (4), subparagraphs (A), (B), (D), and (E) of paragraph (5), paragraphs (7) to (12), inclusive, and paragraph (14) of subdivision (x) of Section 1034 of Title 14 of the California Code of Regulations.
(b)Notices of exemption that are prepared and submitted to the director shall provide a confidential archaeological letter that includes all the information required by paragraphs (2) and (7) to (11), inclusive, of subdivision (c) of Sections 929.1, 949.1 and 969.1, as applicable, of Title 14 of the California Code of Regulations, and site records if required pursuant to subdivision (g) of that section or pursuant to Section 929.5 of Title 14 of the California Code of Regulations.
(c)All fuel treatments required by the board shall be completed within one year from the date the director receives the notice, with the exception of burning. This shall include treatment of surface fuels, wood debris, and slash, which shall be lopped, removed, chipped, piled for burning, or otherwise treated. Burning shall be completed within two years from the date the director receives the notice of exemption.
(d)Slash and woody debris shall be treated to achieve a maximum post harvest depth of 18 inches above the ground except within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code. Surface fuels, slash, and woody debris within 150 feet from any point of an approved and legally permitted structure that complies with the California Building Code shall be chipped, burned, or removed.
(e)Timber operations shall comply with the requirements of paragraphs (1) to (4), inclusive, and (6) to (10), inclusive, of subdivision (b) of Section 1038 of Title 14 of the California Code of Regulations.
(f)All timber operations conducted in Lake Tahoe Region must have a valid Tahoe Basin Tree Removal Permit, as defined by the Tahoe Regional Planning Agency (TRPA), or shall be conducted under a valid TRPA Memorandum of Understanding, when such a permit is required by TRPA.
(g)The submitted notice of exemption shall include selection criteria for the trees to be harvested or the trees to be retained.
(h)The department shall provide the appropriate regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey with copies of notices of exemption when they are submitted.
(i)The submitted notice of exemption shall include the tentative commencement date of timber operations.
(j)Within a 15-day period, the registered professional forester responsible for the submittal of the notice of exemption shall notify the department, the Department of Fish and Game, Wildlife, the appropriate regional water quality control board, and the California Geologic Survey of the actual date of commencement of timber operations.
(k)Operations pursuant to an exemption may not commence for 10 working days from the date of the directors receipt of the notice of exemption unless this delay is waived by the director. The director shall determine whether the notice of exemption is complete, and if so, shall send a copy of a notice of acceptance to the submitter. If the notice of exemption is not complete and accurate, it shall be returned to the submitter and the timber operator may not proceed. If the director does not act within five days of receipt of the notice of exemption, timber operations may commence.
(l)(1)No Decadent and Deformed Trees with Value to Wildlife, as defined in Section 895.1 of Title 14 of the California Code of Regulations, shall be harvested unless all the following apply:
(A)The tree is not critical for the maintenance of a Late Successional Stand.
(B)A registered professional forester attached to the submitted notice of exemption a written explanation and justification for the harvest of the tree based on the registered professional foresters finding of any of the following:
(i)The tree is a hazard to safety or property.
(ii)The removal of the tree is necessary for the construction of a building as approved by the appropriate local jurisdiction and shown on the county or city approved site plan which shall be attached to the submitted notice of exemption.
(iii)The tree is dead or likely to die within one year of the date of the proposed removal, as determined by a registered professional forester.
(2)A registered professional foresters written explanation or justification need not be attached to the submitted notice of exemption if an approved Habitat Conservation Plan, Sustained Yield Plan, or plan as that term is defined in Section 895.1 of Title 14 of the California Code of Regulations addresses large old tree retention for the area in which the large old tree is proposed for removal and the removal is in compliance with the retention standards of that document.
(3)Any tree harvested pursuant to this subdivision shall be shown on a map provided with the submitted notice of exemption to the department.
(4)This subdivision shall not apply to or be used in conjunction with either the Small Timberland Owner Exemption created pursuant to subdivision (j) of Section 4584 or with the Forest Fires Prevention the Forest Resilience Exemption created pursuant to subdivision (k) (j) of Section 4584.
(m)Helicopter yarding shall be prohibited.
(n)All applicable provisions of the Professional Foresters Law, including, but not limited to, Sections 775 to 779, inclusive, of this code, as well as all applicable provisions of Registration of Professional Forester Rules, including, but not limited to, Sections 1612 to 1614, inclusive, of Title 14 of the California Code of Regulations apply to the practice of professional forestry as it relates to this section.
SEC. 4.Section 4589 of the Public Resources Code is amended to read:4589.(a)The department and board, in consultation with the Department of Fish and Wildlife, and the State Water Resources Control Board, shall commencing December 31, 2019, and annually thereafter, review and submit a report to the Legislature on the trends in the use of, compliance with, and effectiveness of, the exemptions and emergency notice provisions described in Sections 4584 and 4592 of this code and Sections 1038 and 1052 of Title 14 of the California Code of Regulations. The report shall include an analysis of exemption use and whether the exemptions are having the intended effect. The report shall also include recommendations to improve the use of those exemptions and emergency notice provisions, information on the linear distance of road constructed or reconstructed under notices of exemption by individual ownerships, within a representative sample of planning watersheds from each forest practice district as defined in Sections 907 to 909, inclusive, of Title 14 of the California Code of Regulations, and violations associated with road reconstruction. The report shall include information on the number and type of violations and enforcement actions taken on each notice of exemption and emergency notice. The report shall also contain the number of post-treatment posttreatment onsite inspections that occur and whether those inspections were attended by a representative of the Department of Fish and Wildlife and a representative of the State Water Resources Control Board. The report submitted on December 31, 2025, shall include recommendations necessary for revisions to diameter limits at stump heights of harvestable trees under subdivisions (j) and (k) of Section 4584. 4584, as those subdivisions read on January 1, 2024.
(b)The public shall be provided opportunities to participate in the review and the development of the report.
(c)The report shall be submitted pursuant to Section 9795 of the Government Code.
(d)(A)This section shall be operative for a period of five years after the effective date of emergency regulations as adopted by the board and as of that date is inoperative.
(B)The board shall notify the Secretary of State when emergency regulations have been adopted.
SEC. 5.Section 399.20.3 of the Public Utilities Code is amended to read:399.20.3.(a)For purposes of this section, the following definitions apply:
(1)Bioenergy has the same meaning as set forth in paragraph (6) of subdivision (f) of Section 399.20.
(2)Tier 1 high hazard zone includes areas where wildlife and falling trees threaten electrical transmission and distribution lines, roads, and other evacuation corridors, critical community infrastructure, or other existing structures, as designated by the Department of Forestry and Fire Protection pursuant to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(3)Tier 2 high hazard zone includes watersheds that have significant tree mortality combined with community and natural resource assets, as designated by the Department of Forestry and Fire Protection pursuant to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(b)(1)In addition to the requirements of subdivision (f) of Section 399.20, by December 1, 2023, electrical corporations shall collectively procure, through financial commitments of 5 to 15 years, inclusive, their proportionate share of 125 megawatts of cumulative rated generating capacity from existing bioenergy projects that commenced operations before June 1, 2013. At least 80 percent of the feedstock of an eligible facility, on an annual basis, shall be a byproduct of sustainable forestry management, which includes removal of dead and dying trees from Tier 1 and Tier 2 high hazard zones and is not that from lands that have been clear cut. At least 60 percent of this feedstock shall be from Tier 1 and Tier 2 high hazard zones.
(2)Paragraph (1) shall not apply to a utility subject to subdivision (g) if both of the following apply:
(A)The utility, either directly or through a joint powers authority, entered into five-year financial commitments for its proportionate share of 125 megawatts of cumulative rated generating capacity from existing bioenergy projects pursuant to this section as it was enacted by Chapter 368 of the Statutes of 2016.
(B)The utilitys financial commitments referenced in subparagraph (A) include, (1) a contract with a facility operator that was, on June 1, 2022, in a bankruptcy or other insolvency proceeding, or (2) a contract for a project that does not deliver energy to the utility.
(c)For the purpose of contracts entered into pursuant to subdivision (b), commission Resolution E-4770 (March 17, 2016), and commission Resolution E-4805 (October 13, 2016), Tier 1 and Tier 2 high hazard zone fuel or feedstock shall also include biomass fuels removed from fuel reduction operations exempt from timber harvesting plan requirements pursuant to subdivisions (a), (f), (j), and (k) of Section 4584 of the Public Resources Code. Code, as those subdivisions read on January 1, 2024.
(d)The commission shall require an electrical corporation that has entered into a contract pursuant to subdivision (b), commission Resolution E-4770 (March 17, 2016), or commission Resolution E-4805 (October 13, 2016) to allow fuel or feedstock reporting requirements to be based on a monthly or annual basis, and a bioenergy facility providing generation pursuant to that contract shall have the right to opt out of the mandated fuel or feedstock usage levels in any particular month upon providing written notice to the electrical corporation in the month of operation. For months in which a bioenergy facility opts out of the mandated fuel or feedstock usage levels or misses the mandated fuel or feedstock targets, that facility shall be paid the alternate price adopted by the commission in commission Resolution E-4770 for all megawatthours generated during that month. Contracts shall continue in force through the end of the contracted term without creating an event of default for missing mandated fuel or feedstock usage levels and without giving rise to a termination right in favor of the electrical corporation.
(e)(1)For each electrical corporation, the commission shall allocate its proportionate share of the 125 megawatts based on the ratio of the electrical corporations peak demand to the total statewide peak demand.
(2)Procurement by an electrical corporation of generation capacity pursuant to a contract under the commissions Resolution E-4770 (March 17, 2016) that is in excess of the requirement of that electrical corporation under that resolution shall count towards meeting the electrical corporations proportionate share allocated pursuant to paragraph (1).
(f)The commission may direct each electrical corporation to develop standard contract terms and conditions that reflect the operational characteristics of the bioenergy projects and to provide a streamlined contracting process or may require the electrical corporations to use the mechanism established pursuant to the commissions Resolution E-4770 (March 17, 2016) to meet the requirements of subdivision (e). The procurement pursuant to the developed standard contract shall occur on an expedited basis due to the Proclamation of a State of Emergency on Tree Mortality declared by the Governor on October 30, 2015.
(g)A local publicly owned electric utility serving more than 100,000 customers shall procure its proportionate share, based on the ratio of the utilitys peak demand to the total statewide peak demand, of 125 megawatts of cumulative rated capacity from existing bioenergy projects described in subdivision (b) subject to terms of at least five years.
(h)The commission shall ensure that the costs of any contract procured by an electrical corporation to satisfy the requirements of this section are recoverable from all customers on a nonbypassable basis.
(i)The Procurement Review Group within the commission shall advise the commission on the cost of the generation procured pursuant to this section and its impact on ratepayers.
(j)For purposes of this section, any incremental procurement of electricity products from bioenergy resources by a new contract or contract extension of five years or longer in duration shall be from a resource that meets emission limits equivalent to, or more stringent than, the applicable best available retrofit control technology, as determined by the local air pollution control district or air quality management district. The determination shall be made before the start of the operating period under the new contract or contract extension.
Upon determining that this exemption is consistent with the purposes of this chapter, the board may exempt from this chapter, or portions of this chapter, a person engaged in forest management whose activities are limited to any of the following:
(a)The cutting or removal of trees for the purpose of constructing or maintaining a right-of-way for utility lines.
(b)The planting, growing, nurturing, shaping, shearing, removal, or harvest of immature trees for Christmas trees or other ornamental purposes or minor forest products, including fuelwood.
(c)The cutting or removal of dead, dying, or diseased trees of any size.
(d)Site preparation.
(e)Maintenance of drainage facilities and soil stabilization treatments.
(f)Timber operations on land managed by the Department of Parks and Recreation.
(g)(1)The one-time conversion of less than three acres to a nontimber use. A person, whether acting as an individual, as a member of a partnership, or as an officer or employee of a corporation or other legal entity, shall not obtain more than one exemption pursuant to this subdivision in a five-year period. If a partnership has as a member, or if a corporation or other legal entity has as an officer or employee, a person who has received this exemption within the past five years, whether as an individual, as a member of a partnership, or as an officer or employee of a corporation or other legal entity, then that partnership, corporation, or other legal entity is not eligible for this exemption. Person, for purposes of this subdivision, means an individual, partnership, corporation, or other legal entity.
(2)(A)Notwithstanding Section 4554.5, the board shall adopt regulations that do all of the following:
(i)Identify the required documentation of a bona fide intent to complete the conversion that an applicant will need to submit in order to be eligible for the exemption in paragraph (1).
(ii)Authorize the department to inspect the sites approved in conversion applications that have been approved on or after January 1, 2002, in order to determine that the conversion was completed within the two-year period described in subparagraph (B) of paragraph (2) of subdivision (a) of Section 1104.1 of Title 14 of the California Code of Regulations.
(iii)Require the exemption pursuant to this subdivision to expire if there is a change in timberland ownership. The person who originally submitted an application for an exemption pursuant to this subdivision shall notify the department of a change in timberland ownership on or before five calendar days after a change in ownership.
(iv)The board may adopt regulations allowing a waiver of the five-year limitation described in paragraph (1) upon finding that the imposition of the five-year limitation would impose an undue hardship on the applicant for the exemption. The board may adopt a process for an appeal of a denial of a waiver.
(v)The board may adopt regulations allowing a waiver of the one-time limitation described in paragraph (1) upon finding that the imposition of the one-time limitation would impose an undue hardship on the applicant. The board may adopt a process for an appeal of a denial of a waiver.
(B)The application form for the exemption pursuant to paragraph (1) shall prominently advise the public that a violation of the conversion exemption, including a conversion applied for in the name of someone other than the person or entity implementing the conversion in bona fide good faith, is a violation of this chapter and penalties may accrue up to ten thousand dollars ($10,000) for each violation pursuant to Article 8 (commencing with Section 4601).
(h)An easement granted by a right-of-way construction agreement administered by the federal government if timber sales and operations within or affecting the area are reviewed and conducted pursuant to the federal National Environmental Policy Act of 1969 (42 U.S.C. Sec. 4321 et seq.).
(i)(1)The cutting or removal of trees in compliance with Sections 4290 and 4291 that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break for a distance of not more than 150 feet on each side from an approved and legally permitted structure that complies with the California Building Standards Code, when that cutting or removal is conducted in compliance with this subdivision. For purposes of this subdivision, an approved and legally permitted structure includes only structures that are designed for human occupancy, garages, barns, stables, and structures used to enclose fuel tanks.
(2)(A)The cutting or removal of trees pursuant to this subdivision is limited to cutting or removal that will result in a reduction in the rate of fire spread, fire duration and intensity, fuel ignitability, or ignition of the tree crowns and shall be in accordance with any regulations adopted by the board pursuant to this section.
(B)Trees shall not be cut or removed pursuant to this subdivision by the clearcutting regeneration method, by the seed tree removal step of the seed tree regeneration method, or by the shelterwood removal step of the shelterwood regeneration method.
(3)(A)All fuel treatments conducted pursuant to this subdivision that do not comply with board rules and regulations may be determined to be a nuisance and subject to abatement by the department or the city or county having jurisdiction.
(B)The costs incurred by the department, city, or county, as the case may be, to abate the nuisance upon a parcel of land subject to the timber operations, including, but not limited to, investigation, boundary determination, measurement, and other related costs, may be recovered by special assessment and lien against the parcel of land by the department, city, or county. The assessment may be collected at the same time and in the same manner as ordinary ad valorem taxes, and shall be subject to the same penalties and the same procedure and sale in case of delinquency as is provided for ad valorem taxes.
(4)All timber operations conducted pursuant to this subdivision shall conform to applicable city or county general plans, city or county implementing ordinances, and city or county zoning ordinances. This paragraph does not authorize the cutting, removal, or sale of timber or other solid wood forest products within an area where timber harvesting is prohibited or otherwise restricted pursuant to the rules or regulations adopted by the board.
(5)(A)The board shall adopt regulations, initially as emergency regulations in accordance with subparagraph (B), that the board considers necessary to implement and to obtain compliance with this subdivision.
(B)The emergency regulations adopted pursuant to subparagraph (A) shall be adopted in accordance with the Administrative Procedure Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code). The adoption of emergency regulations shall be deemed to be an emergency and necessary for the immediate preservation of the public peace, health, and safety, or general welfare.
(j)(1)The cutting or removal of trees on the persons property that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break. An exemption pursuant to this subdivision shall be known as the Small Timberland Owner Exemption. The cutting or removal of trees in compliance with this subdivision shall be subject to all of the following conditions:
(A)The notice of exemption is prepared, signed, and submitted by a registered professional forester to the department.
(B)The residual stocking standards are consistent with the following standards and shall be achieved through uneven-aged management, as defined in Section 895.1 of Title 14 of the California Code of Regulations excluding group selection:
(i)On Site I lands at least 150 square feet of basal area shall be retained within the coast forest district, as defined in Section 907 of Title 14 of the California Code of Regulations, while at least 100 square feet of basal area shall be retained within the northern and southern districts, as defined in Section 908 or 909, respectively, of Title 14 of the California Code of Regulations.
(ii)On Site II lands at least 100 square feet of basal area shall be retained within the coast district, while at least 75 square feet of basal area shall be retained within the northern and southern districts.
(iii)On Site III lands at least 75 square feet of basal area shall be retained.
(C)(i)Forest management activities will increase the quadratic mean diameter of the stand.
(ii)Increases in quadratic mean diameter shall only consider trees greater than eight inches in diameter at breast height. The registered professional forester responsible for preparation of the notice of exemption shall report the expected postharvest increase in quadratic mean diameter.
(D)(i)The residual stand consists primarily of healthy and vigorous dominant and codominant trees from the preharvest stand, well distributed through the harvested area.
(ii)No trees of the genus quercus that are greater than 26 inches in diameter at stump height, measured 8 inches above ground level, shall be harvested under a notice of exemption submitted pursuant to this subdivision.
(iii)No trees greater than 32 inches in diameter at stump height, measured 8 inches above ground level, shall be harvested under a notice of exemption submitted pursuant to this subdivision.
(iv)The six largest trees per acre within the boundaries of a notice of exemption submitted pursuant to this subdivision shall not be harvested.
(v)The postharvest composition of tree species shall be representative of the preharvest stand condition and demonstrate progression towards climax forest conditions, unless the registered professional forester provides justification explaining how modification of species diversity will benefit forest health and resiliency.
(E)The submitted notice of exemption shall include a description of the preharvest stand structure and a statement of the minimum expected postharvest stocking.
(F)All trees harvested or all trees retained shall be marked by, or under the supervision of, a registered professional forester before felling operations begin.
(G)The board shall adopt regulations for the treatment of understory vegetation and standing dead fuels, canopy closure, clearance to base of live crown, or ladder fuels, that could promote the spread of wildfire. A fuel reduction effort conducted under a submitted notice of exemption pursuant to this subdivision shall comply with the canopy closure regulations adopted by the board on June 10, 2004, and as those regulations may be amended.
(H)A notice of exemption submitted to the department that is within the coast forest district is submitted for a small forestland owner who owns 60 acres or less of timberland within a single planning watershed.
(I)A notice of exemption submitted to the department that is within the northern forest district or the southern forest district is submitted for a small forestland owner who owns 100 acres or less of timberland within a single planning watershed.
(2)(A)All timber operations conducted pursuant to this subdivision may only occur once on any given acre per any 10-year period of time. The department shall only grant a maximum of three exemptions under the Small Timberland Owner Exemption per landowner.
(B)Except for the harvesting of dead, diseased, or dying trees, during this 10-year period the department shall not approve a plan, as defined in Section 895.1 of Title 14 of the California Code of Regulations, that allows even-aged silviculture prescriptions. During this 10-year period of time a registered professional forester shall not submit a notice of exemption pursuant to subdivision (k) on portions of the property subject to an exemption pursuant to this subdivision.
(3)The department may conduct an onsite inspection to determine compliance with this subdivision. The department may notify the regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey before conducting the onsite inspection. The regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey may conduct an inspection with the department.
(4)(A)This subdivision shall be operative for a period of five years after the effective date of emergency regulations as adopted by the board and as of that date is inoperative.(B)The board shall notify the Secretary of State when emergency regulations have been adopted.(4)This subdivision shall become inoperative on January 1, 2031.
(k)(1)The harvesting of trees, limited to those trees that eliminate the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns, for the purpose of reducing the rate of fire spread, duration and intensity, fuel ignitability, or ignition of tree crowns. An exemption pursuant to this paragraph shall be known as the Forest Fire Prevention Exemption.
(2)The board may authorize an exemption pursuant to paragraph (1) only if the tree harvesting will decrease fuel continuity and increase the quadratic mean diameter of the stand, and the tree harvesting area will not exceed 300 acres. Increases in quadratic mean diameter shall only consider trees greater than eight inches in diameter at breast height. The notice of exemption may be authorized only if all of the conditions specified in paragraphs (3) to (9), inclusive, are met.
(3)A registered professional forester shall prepare the notice of exemption and submit it to the director.
(4)(A)The submitted notice of exemption shall include a description of the preharvest stand structure and a statement of the postharvest stand stocking levels and the expected postharvest increase in quadratic mean diameter.
(B)The level of residual stocking shall be consistent with maximum sustained production of high-quality timber products. The residual stand shall consist primarily of healthy and vigorous dominant and codominant trees from the preharvest stand. Stocking shall not be reduced below the standards required by the following provisions that apply to the exemption at issue:
(i)Clauses 1 to 4, inclusive, of subparagraph (A) of paragraph (1) of subdivision (a) of Sections 913.3, 933.3, and 953.3 of Title 14 of the California Code of Regulations, where appropriate.
(C)If the preharvest dominant and codominant crown canopy is occupied by trees less than 14 inches in diameter at breast height, a minimum of 100 trees over four inches in diameter at breast height shall be retained per acre for Site I, II, and III lands, and a minimum of 75 trees over four inches in diameter at breast height shall be retained per acre for Site IV and V lands.
(D)All trees that are harvested or all trees that are retained shall be marked or sample marked by, or under the supervision of, a registered professional forester before felling operations begin. The board shall adopt regulations for sample marking for this section in Title 14 of the California Code of Regulations. Sample marking shall be limited to homogenous forest stand conditions typical of plantations.
(5)(A)The board shall adopt regulations for the treatment of understory vegetation and standing dead fuels, canopy closure, clearance to base of live crown, or ladder fuels, that could promote the spread of wildfire. A fuel reduction effort conducted under a submitted notice of exemption pursuant to this subdivision shall comply with the canopy closure regulations adopted by the board on June 10, 2004, and as those regulations may be amended.
(B)The postharvest stand shall not contain more than 200 trees over three inches in diameter per acre.
(C)Vertical spacing shall be achieved by treating dead fuels to a minimum clearance distance of eight feet measured from the base of the live crown of the postharvest dominant and codominant trees to the top of the dead surface fuels.
(D)The standards required by subparagraphs (A) to (C), inclusive, shall be achieved on approximately 80 percent of the treated area.
(6) Before the submission of a notice of exemption to the department, the registered professional forester responsible for submitting the notice shall designate temporary road locations, landing locations, tractor road crossings of class III watercourses, unstable areas, or connected headwall swales on the ground and map their locations.
(7)The construction or reconstruction of temporary roads on slopes of 30 percent or less shall be allowed if all of the following conditions are met:
(A)Temporary roads or landings shall not be located on unstable areas, as defined in Section 895.1 of Title 14 of the California Code of Regulations.
(B)Temporary roads shall be single-lane in width.
(C)Temporary roads shall not be located across a connected headwall swale, as defined in Section 895.1 of Title 14 of the California Code of Regulations.
(D)Construction or reconstruction of temporary roads, landings, or watercourse crossings shall not occur during the winter operating period. Pursuant to subdivision (g) of Sections 923.6, 943.6, and 963.6, as applicable, of Title 14 of the California Code of Regulations, roads and landings used for log hauling or other heavy equipment uses during the winter period shall occur on a stable operating surface and, where necessary, be surfaced with rock to a depth and quantity sufficient to maintain the stable operating surface. Use shall be prohibited on roads that are not hydrologically disconnected and exhibit saturated soil conditions. Timber operations during the winter period shall comply with paragraphs (1) and (2) of subdivision (c) of Sections 914.7, 934.7, and 954.7, as applicable, of Title 14 of the California Code of Regulations.
(E)Use of temporary roads shall comply with the operational provisions of Article 12 (commencing with Section 923) of Subchapter 4 of Chapter 4 of Division 1.5 of Title 14 of the California Code of Regulations, and recognize guidance on hydrologic disconnection in Technical Rule Addendum Number 5.
(F)No logging road or landings construction or reconstruction activities of any kind shall occur within 200 feet of class I and class II watercourses or within 50 feet of a class III watercourse.
(G)The landowner shall retain a registered professional forester who is available to provide professional advice to the licensed timber operator and timberland owner throughout the active timber operations. The name, address, telephone number, and registration number of the retained registered professional forester shall be provided on the submitted notice of exemption. This professional advice shall include overseeing the construction or reconstruction of any temporary roads or landings and advising on necessary mitigation to avoid potential impacts to associated watershed and forest resources. The registered professional forester shall also comply with Section 1035.2 of Title 14 of the California Code of Regulations, relating to interaction between the licensed timber operator and the registered professional forester.
(H)The registered professional forester responsible for submitting the notice of exemption shall affirm that the construction or reconstruction of each temporary road is necessary to provide access to harvest areas where no feasible alternative exists. The submitted notice of exemption shall include the number and cumulative length of temporary roads that will be constructed or reconstructed.
(I)(i)Temporary road construction or reconstruction, shall be limited to no more than two miles of road per ownership in a planning watershed per any five-year period.
(ii)For each exemption affecting less than 40 acres, all temporary roads constructed or reconstructed under this exemption shall not exceed a cumulative length of 300 feet.
(iii)For each exemption affecting between 40 and 80 acres, all temporary roads constructed or reconstructed under this exemption shall not exceed a cumulative length of between 300 and 600 feet, as determined on a pro rata basis by the total acreage affected by the exemption.
(iv)For each exemption affecting over 80 acres, all temporary roads constructed or reconstructed under the exemption shall not exceed a cumulative length of 600 feet. The submitted notice of exemption shall list the number of acres affected and the cumulative length of the road in feet.
(v)Temporary roads constructed or reconstructed under this exemption shall not be connected to other temporary roads constructed under previous or subsequent exemptions filed under this paragraph.
(vi)All temporary roads shall be abandoned using proactive measures that have been applied to effectively remove them from the permanent road network, in accordance with the definition of abandoned road as defined in Section 895.1 of Title 14 of the California Code of Regulations.
(vii)This paragraph shall not be interpreted to permit road construction or reconstruction except as authorized under the Forest Fire Prevention Exemption, pursuant to this paragraph.
(viii)No trees larger than 36 inches in diameter at stump height, measured 8 inches above ground level, shall be removed for the purposes of road construction or reconstruction under a notice of exemption submitted pursuant to this subdivision. A tree that is between 30 and 36 inches in diameter at stump height, measured 8 inches above ground level, may be removed for the purposes of road construction or reconstruction under a notice of exemption submitted pursuant to this subdivision only if there are no feasible alternatives for the road placement.
(8)Except within constructed or reconstructed temporary road prisms, only trees less than 30 inches in stump diameter, measured at eight inches above ground level, may be removed.
(9)All timber operations conducted pursuant to this subdivision shall only occur within the most recent version of the departments Fire Hazard Severity Zone Map in the moderate, high, and very high fire threat zones.
(10)If pesticides or herbicides will be used within the boundaries of an area covered by a notice of exemption pursuant to this paragraph within one year of director acceptance, the timberland owner shall notify the appropriate regional water quality control board 10 days before application of any pesticides or herbicides.
(11)After the timber operations are complete, the department shall conduct an onsite inspection to determine compliance with this subdivision and whether appropriate enforcement action should be initiated. The department shall notify the appropriate regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey seven days prior to conducting the onsite inspection. The regional water quality control board, the Department of Fish and Wildlife, and the California Geologic Survey may conduct an inspection with the department.
(12)This subdivision shall become inoperative on January 1, 2026. 2031.
(l)The cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands, if all of the following requirements are met:
(1)A registered professional forester shall prepare the notice of exemption and submit it to the director. The notice shall include all of the following:
(A)A certification signed by the registered professional forester that a minimum of 35 square feet of basal area per acre of California black or Oregon white oak, or both, occupy the proposed treatment area at the time the notice is prepared and the timber operation is designed to restore and conserve California black and Oregon white oak woodlands and associated grasslands.
(B)A description of the preharvest stand structure and a statement of the postharvest stand stocking levels.
(2)No tree larger than 26 inches in diameter at stump height shall be harvested for commercial purposes, which includes use for saw logs, posts and poles, fuel wood, biomass, or other forest products.
(3)Only conifers within 300 feet of a California black or Oregon white oak that are at minimum four inches in diameter at breast height may be harvested.
(4)The total area exempted pursuant to this subdivision shall not exceed 300 acres per property per five-year period.
(5)Conifer shall be reduced to less than 25 percent of the combined hardwood and conifer postharvest stand stocking levels.
(6)No more than 20 percent of the total basal area of preexisting oak stock shall be cut or removed during harvest and a minimum of 35 square feet of basal area per acre of California black or Oregon white oak, or both, shall be maintained postharvest.
(7)Slash shall be configured so as to minimize the risk of fire mortality to the remaining oak trees.
(8)The board shall adopt regulations to implement this subdivision.
(9)This subdivision shall not apply to the Southern Subdistrict of the Coast Forest District, as defined in Section 895.1 of Title 14 of the California Code of Regulations, or the Southern Forest District, as defined in Section 909 of Title 14 of the California Code of Regulations.
(m)(1)The board may exempt from this chapter, or portions of this chapter, a person engaged in forest management whose activities are limited to the cutting or removal of trees on the persons property in compliance with Sections 4290 and 4291 that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuelbreak for a distance of not more than 300 feet on each side from an approved and legally permitted habitable structure, when that cutting or removal is conducted in compliance with this subdivision and all of the following conditions are met:
(A)The notice of exemption is prepared, signed, and submitted by a registered professional forester to the department.
(B)For the areas between 150 and 300 feet from the habitable structure, the operations meet all of the following provisions:
(i)The residual stocking standards are consistent with Sections 913.2, 933.2, and 953.2 of Title 14 of the California Code of Regulations, as appropriate.
(ii)Activities within this area will increase the quadratic mean diameter of the stand.
(iii)The residual stand consists primarily of healthy and vigorous dominant and codominant trees from the preharvest stand, well distributed throughout the harvested area.
(iv)Postharvest slash treatment and stand conditions will lead to more moderate fire behavior in the professional judgment of the registered professional forester who submits the notice of exemption.
(v)Any additional guidance for slash treatment and postharvest stand conditions and any other issues deemed necessary that are consistent with this section, as established by the board.
(2)For purposes of this subdivision, habitable structure means a building that contains one or more dwelling units or that can be occupied for residential use. Buildings occupied for residential use include single-family homes, multidwelling structures, mobile and manufactured homes, and condominiums. For purposes of this subdivision, habitable structure does not include commercial, industrial, or incidental buildings such as detached garages, barns, outdoor sanitation facilities, and sheds.
(3)This subdivision shall become inoperative on January 1, 2026. 2031.
All matter omitted in this version of the bill appears in the bill as introduced in the Assembly, February 8, 2024. (JR11)The Energy Commission shall maintain information on the local education agencies and community college districts that receive grants, loans, or other financial assistance under pursuant to this chapter. The publicly available and searchable database shall include relevant metrics, to be determined by the Energy Commission, for electric, gas, and cost savings of the projects.
|
Date
|
Status
|
|---|---|
| Sep 22, 2024 | Chaptered by Secretary of State - Chapter 388, Statutes of 2024. |
| Sep 22, 2024 | Approved by the Governor. |
| Sep 5, 2024 | Enrolled and presented to the Governor at 4 p.m. |
| Aug 27, 2024 | Senate amendments concurred in. To Engrossing and Enrolling. (Ayes 77. Noes 0.). |
| Aug 27, 2024 | Assembly Rule 77 suspended. |
| Aug 26, 2024 | In Assembly. Concurrence in Senate amendments pending. May be considered on or after August 28 pursuant to Assembly Rule 77. |
| Aug 26, 2024 | Read third time. Passed. Ordered to the Assembly. (Ayes 39. Noes 0.). |
| Aug 20, 2024 | Read second time. Ordered to third reading. |
| Aug 19, 2024 | Read third time and amended. Ordered to second reading. |
| Jun 27, 2024 | Ordered to third reading. |
| Jun 27, 2024 | From Consent Calendar. |
| Jun 25, 2024 | Read second time. Ordered to Consent Calendar. |
| Jun 24, 2024 | From committee: Be ordered to second reading file pursuant to Senate Rule 28.8 and ordered to Consent Calendar. |
| Jun 12, 2024 | Read second time and amended. Re-referred to Com. on APPR. |
| Jun 11, 2024 | From committee: Amend, and do pass as amended and re-refer to Com. on APPR with recommendation: To Consent Calendar. (Ayes 11. Noes 0.) (June 11). |
| Jun 3, 2024 | From committee chair, with author's amendments: Amend, and re-refer to committee. Read second time, amended, and re-referred to Com. on N.R. & W. |
| May 22, 2024 | Referred to Com. on N.R. & W. |
| May 9, 2024 | In Senate. Read first time. To Com. on RLS. for assignment. |
| May 9, 2024 | Read third time. Passed. Ordered to the Senate. (Ayes 65. Noes 0. Page 5159.) |
| May 2, 2024 | Read second time. Ordered to Consent Calendar. |
| May 1, 2024 | From committee: Do pass. To Consent Calendar. (Ayes 14. Noes 0.) (May 1). |
| Apr 23, 2024 | From committee: Do pass and re-refer to Com. on APPR. with recommendation: To Consent Calendar. (Ayes 11. Noes 0.) (April 22). Re-referred to Com. on APPR. |
| Apr 18, 2024 | Re-referred to Com. on NAT. RES. |
| Apr 17, 2024 | From committee chair, with author's amendments: Amend, and re-refer to Com. on NAT. RES. Read second time and amended. |
| Mar 6, 2024 | In committee: Set, first hearing. Hearing canceled at the request of author. |
| Feb 27, 2024 | Re-referred to Com. on NAT. RES. |
| Feb 26, 2024 | From committee chair, with author's amendments: Amend, and re-refer to Com. on NAT. RES. Read second time and amended. |
| Feb 26, 2024 | Referred to Com. on NAT. RES. |
| Feb 9, 2024 | From printer. May be heard in committee March 10. |
| Feb 8, 2024 | Read first time. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Aug 27, 2024 | AB 2276 Wood Concurrence in Senate Amendments | Assembly Floor |
Passed |
|
| Aug 26, 2024 | Assembly 3rd Reading AB2276 Wood By Dodd | Senate Floor |
Passed |
|
| Jun 11, 2024 | Do pass as amended, but first amend, and re-refer to the Committee on [Appropriations] with the recommendation: To Consent Calendar | Senate Standing Committee on Natural Resources and Water |
Passed |
|
| May 9, 2024 | AB 2276 Wood Consent Calendar Second Day Regular Session | Assembly Floor |
Passed |
|
| May 1, 2024 | Do pass. To Consent Calendar. | Assembly Standing Committee on Appropriations |
Passed |
|
| Apr 22, 2024 | Do pass and be re-referred to the Committee on [Appropriations] with recommendation: To Consent Calendar | Assembly Standing Committee on Natural Resources |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| American Forest Foundation | ** Support | |
| Associated California Loggers | ** Support | |
| Association Of California Water Agencies | ** Support | |
| Auten Resource Consulting | ** Support | |
| California Farm Bureau Federation | ** Support | |
| California Forestry Association | ** Support | |
| California Licensed Foresters Association | ** Support | |
| California Native Plant Society | ** Support | |
| California State Association Of Counties | ** Support | |
| California Wilderness Coalition | ** Support | |
| Central Sierra Environmental Resource Center | ** Support | |
| Defenders Of Wildlife | ** Support | |
| Environmental Defense Fund | ** Support | |
| Forest Landowners Of California | ** Support | |
| Humboldt County Prescribed Burn Association | ** Support | |
| Humboldt Redwood Company LLC | ** Support | |
| Mattole Restoration Council | ** Support | |
| Mendocino Redwood Company LLC | ** Support | |
| Northcoast Regional Land Trust | ** Support | |
| Pacific Forest Trust | ** Support | |
| Rural County Representatives of California | ** Support | |
| Sierra Business Council | ** Support | |
| Sierra Cascade Logging Conference | ** Support | |
| Sierra Forest Legacy | ** Support | |
| Sierra Institute for Community and Environment | ** Support | |
| The Buckeye Conservancy | ** Support | |
| The Fire Restoration Group | ** Support | |
| University of California Cooperative Extension - Humboldt and Del Norte Counties | ** Support |
CONCURRENCE IN SENATE AMENDMENTS
CSA1 Bill Id:AB 2276
Author:(Wood)
As Amended Ver:August 19, 2024
Majority vote
SUMMARY
Repeals the Small Timberland Owner Exemption, renames the Forest Fire Prevention Exemption the Forest Resilience Exemption (FRE), revises the standards and criteria for qualifying for that exemption, extends that exemption until January 1, 2031, and extends until January 1, 2031, the other aforementioned exemption.
Senate Amendments
- Revise requirements governing compliance with cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands, including prohibiting any California black or Oregon white oak tree larger than 30 inches in diameter at breast height shall be harvested for commercial purposes.
- Require, under the FRE, the notice of exemption to include the postharvest composition of tree species shall be representative of the preharvest stand condition and demonstrate progression towards climax forest conditions, unless the registered professional forester provides information explaining how modification of species diversity will benefit forest health and resiliency.
- Require the Board of Forestry and Fire Protection to adopt regulations, initially as emergency regulations, that the board considers necessary to implement and to obtain compliance with the FRE requirements.
- Include chaptering out amendments to AB 2750 (Gallagher) by amending Public Utilities Code 399.20.3.
COMMENTS
Past logging and decades of fire suppression have left unnaturally dense forests that lack the large, old, fire-resilient trees that once characterized the forests of the Sierra, Cascade, and North Coast. Those historic forests were shaped by frequent fires, both from lightning and Indigenous burning, that helped maintain the open characteristics where John Muir described being able to ride a horse through the forest without a branch knocking off his hat. Dense, young forests now extend mile after mile, providing the continuous fuel for large-scale fires burning with extremely damaging outcomes. Forest health is critical to managing wildfire prevention.
Timber harvesting operations on private lands in California must file THPs, which detail how timber operations (e.g., felling and harvest of trees, related road construction and maintenance, and preparing ground for planting of seedlings) are to occur. SB 901 (Dodd), Chapter 626, Statutes of 2018, divided timber harvest exemptions into two land owner-sized categories. To increase the utility of the exemptions, AB 2276 makes various changes to the Forest Practices Act to consolidate and update exemptions, and extends specified exemption sunset dates
According to the Author
The wildfire hazard in California has grown exponentially over the past decade. In an effort to mitigate this hazard, the state has set a goal of treating 500,000 acres of state land a year by increasing the pace and scale of forest management, among other tools. AB 2276 will contribute to California's goal by extending and increasing the utility of timber harvest plan exemptions, making it more economically feasible to complete wildfire mitigation projects that provide for healthier and more resilient forests. With the budget challenges facing the state, it is important that we implement smart solutions that take advantage of existing partnerships and shared goals of private landowners, forest managers, environmental stewards, and state agencies.
Arguments in Support
The California Forestry Association writes that the combined changes in AB 2276 strike an appropriate balance between environmental conservation and economic benefit and will lead to driving resiliency within non-federal forests across the state. These changes resulted from thoughtful discussion between landowners, forestry experts, and NGOs and incorporate many of the recommendations offered by CALFIRE within the recent monitoring report (Forest Fire Prevention, or Forest Resiliency) from January 2023.
Arguments in Opposition
None on file.
FISCAL COMMENTS
According to the Senate Appropriations Committee, this bill presents negligible state costs.
VOTES:
ASM NATURAL RESOURCES: 11-0-0
YES: Bryan, Flora, Bauer-Kahan, Friedman, Hoover, Kalra, Joe Patterson, Muratsuchi, Pellerin, Wicks, Wood
ASM APPROPRIATIONS: 14-0-1
YES: Wicks, Sanchez, Arambula, Bryan, Calderon, Wendy Carrillo, Dixon, Mike Fong, Grayson, Haney, Hart, Pellerin, Ta, Villapudua
ABS, ABST OR NV: Jim Patterson
ASSEMBLY FLOOR: 65-0-15
YES: Addis, Aguiar-Curry, Alanis, Alvarez, Arambula, Bauer-Kahan, Bennett, Berman, Boerner, Bonta, Bryan, Calderon, Juan Carrillo, Wendy Carrillo, Chen, Connolly, Davies, Dixon, Essayli, Mike Fong, Vince Fong, Friedman, Gallagher, Garcia, Gipson, Hart, Holden, Hoover, Irwin, Jackson, Jones-Sawyer, Kalra, Lackey, Lee, Lowenthal, Maienschein, McCarty, McKinnor, Muratsuchi, Ortega, Pacheco, Papan, Jim Patterson, Joe Patterson, Pellerin, Quirk-Silva, Ramos, Rendon, Reyes, Rodriguez, Blanca Rubio, Sanchez, Santiago, Soria, Ta, Valencia, Villapudua, Waldron, Ward, Weber, Wicks, Wilson, Wood, Zbur, Robert Rivas
ABS, ABST OR NV: Bains, Cervantes, Megan Dahle, Flora, Gabriel, Grayson, Haney, Low, Mathis, Stephanie Nguyen, Petrie-Norris, Luz Rivas, Schiavo, Ting, Wallis
SENATE FLOOR: 40-0-0
YES: Allen, Alvarado-Gil, Archuleta, Ashby, Atkins, Becker, Blakespear, Bradford, Caballero, Cortese, Dahle, Dodd, Durazo, Eggman, Glazer, Gonzalez, Grove, Hurtado, Jones, Laird, Limón, McGuire, Menjivar, Min, Newman, Nguyen, Niello, Ochoa Bogh, Padilla, Portantino, Roth, Rubio, Seyarto, Skinner, Smallwood-Cuevas, Stern, Umberg, Wahab, Wiener, Wilk
UPDATED
VERSION: August 19, 2024
CONSULTANT: Paige Brokaw / NAT. RES. / (916) 319-2092 FN: 0004736
CONCURRENCE IN SENATE AMENDMENTS
CSA1 Bill Id:AB 2276
Author:(Wood)
As Amended Ver:August 19, 2024
Majority vote
SUMMARY
Repeals the Small Timberland Owner Exemption, renames the Forest Fire Prevention Exemption the Forest Resilience Exemption (FRE), revises the standards and criteria for qualifying for that exemption, extends that exemption until January 1, 2031, and extends until January 1, 2031, the other aforementioned exemption.
Senate Amendments
- Revise requirements governing compliance with cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands, including prohibiting any California black or Oregon white oak tree larger than 30 inches in diameter at breast height shall be harvested for commercial purposes.
- Require, under the FRE, the notice of exemption to include the postharvest composition of tree species shall be representative of the preharvest stand condition and demonstrate progression towards climax forest conditions, unless the registered professional forester provides information explaining how modification of species diversity will benefit forest health and resiliency.
- Require the Board of Forestry and Fire Protection to adopt regulations, initially as emergency regulations, that the board considers necessary to implement and to obtain compliance with the FRE requirements.
- Include chaptering out amendments to AB 2750 (Gallagher) by amending Public Utilities Code 399.20.3.
COMMENTS
Past logging and decades of fire suppression have left unnaturally dense forests that lack the large, old, fire-resilient trees that once characterized the forests of the Sierra, Cascade, and North Coast. Those historic forests were shaped by frequent fires, both from lightning and Indigenous burning, that helped maintain the open characteristics where John Muir described being able to ride a horse through the forest without a branch knocking off his hat. Dense, young forests now extend mile after mile, providing the continuous fuel for large-scale fires burning with extremely damaging outcomes. Forest health is critical to managing wildfire prevention.
Timber harvesting operations on private lands in California must file THPs, which detail how timber operations (e.g., felling and harvest of trees, related road construction and maintenance, and preparing ground for planting of seedlings) are to occur. SB 901 (Dodd), Chapter 626, Statutes of 2018, divided timber harvest exemptions into two land owner-sized categories. To increase the utility of the exemptions, AB 2276 makes various changes to the Forest Practices Act to consolidate and update exemptions, and extends specified exemption sunset dates
According to the Author
The wildfire hazard in California has grown exponentially over the past decade. In an effort to mitigate this hazard, the state has set a goal of treating 500,000 acres of state land a year by increasing the pace and scale of forest management, among other tools. AB 2276 will contribute to California's goal by extending and increasing the utility of timber harvest plan exemptions, making it more economically feasible to complete wildfire mitigation projects that provide for healthier and more resilient forests. With the budget challenges facing the state, it is important that we implement smart solutions that take advantage of existing partnerships and shared goals of private landowners, forest managers, environmental stewards, and state agencies.
Arguments in Support
The California Forestry Association writes that the combined changes in AB 2276 strike an appropriate balance between environmental conservation and economic benefit and will lead to driving resiliency within non-federal forests across the state. These changes resulted from thoughtful discussion between landowners, forestry experts, and NGOs and incorporate many of the recommendations offered by CALFIRE within the recent monitoring report (Forest Fire Prevention, or Forest Resiliency) from January 2023.
Arguments in Opposition
None on file.
FISCAL COMMENTS
According to the Senate Appropriations Committee, this bill presents negligible state costs.
VOTES:
ASM NATURAL RESOURCES: 11-0-0
YES: Bryan, Flora, Bauer-Kahan, Friedman, Hoover, Kalra, Joe Patterson, Muratsuchi, Pellerin, Wicks, Wood
ASM APPROPRIATIONS: 14-0-1
YES: Wicks, Sanchez, Arambula, Bryan, Calderon, Wendy Carrillo, Dixon, Mike Fong, Grayson, Haney, Hart, Pellerin, Ta, Villapudua
ABS, ABST OR NV: Jim Patterson
ASSEMBLY FLOOR: 65-0-15
YES: Addis, Aguiar-Curry, Alanis, Alvarez, Arambula, Bauer-Kahan, Bennett, Berman, Boerner, Bonta, Bryan, Calderon, Juan Carrillo, Wendy Carrillo, Chen, Connolly, Davies, Dixon, Essayli, Mike Fong, Vince Fong, Friedman, Gallagher, Garcia, Gipson, Hart, Holden, Hoover, Irwin, Jackson, Jones-Sawyer, Kalra, Lackey, Lee, Lowenthal, Maienschein, McCarty, McKinnor, Muratsuchi, Ortega, Pacheco, Papan, Jim Patterson, Joe Patterson, Pellerin, Quirk-Silva, Ramos, Rendon, Reyes, Rodriguez, Blanca Rubio, Sanchez, Santiago, Soria, Ta, Valencia, Villapudua, Waldron, Ward, Weber, Wicks, Wilson, Wood, Zbur, Robert Rivas
ABS, ABST OR NV: Bains, Cervantes, Megan Dahle, Flora, Gabriel, Grayson, Haney, Low, Mathis, Stephanie Nguyen, Petrie-Norris, Luz Rivas, Schiavo, Ting, Wallis
UPDATED
VERSION: August 19, 2024
CONSULTANT: Paige Brokaw / NAT. RES. / (916) 319-2092 FN: 0004736
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | AB 2276 |
THIRD READING
Bill No: AB 2276
Author: Wood (D)
Amended: 8/19/24 in Senate
Vote: 21
SENATE NATURAL RES. & WATER COMMITTEE: 11-0, 6/11/24
AYES: Min, Seyarto, Allen, Dahle, Eggman, Grove, Hurtado, Laird, Limón, Padilla, Stern
SENATE APPROPRIATIONS COMMITTEE: Senate Rule 28.8
ASSEMBLY FLOOR: 65-0, 5/9/24 (Consent) - See last page for vote
SUBJECT: Forestry: timber harvesting plans: exemptions
SOURCE: California Forestry Association
DIGEST:
This bill makes various changes to certain exemptions under the Forest Practice Act, including to consolidate the Small Timberland Owner Exemption and the Forest Fire Prevention Exemption under a new exemption called the Forest Resilience Exemption, revise the Oak Woodland Exemption, and extend specified exemption sunset dates.
Senate Floor amendments of 8/19/24 incorporate “chaptering” amendments for Public Utilities Code (PUC) section 399.20.3 proposed by AB 2750 (Gallagher). The amendments extend a deadline and make other technical and non-substantive changes.
ANALYSIS:
Existing law:
- Establishes CalFire in the California Natural Resources Agency (CNRA) under the control of the CalFire director. CalFire is responsible for the fire protection, fire prevention, maintenance, and enhancement of the state’s forest, range, and brushland resources, contract fire protection, associated emergency services, and assistance in civil disasters and other nonfire emergencies. (Public Resources Code (PRC) §701 and §713)
- Establishes the State Board of Forestry and Fire Protection (Board) in CalFire, consisting of nine members appointed by the Governor, subject to confirmation by the Senate. Among others, the Board is responsible for adopting and continuously reviewing and revising forest practice rules. (PRC §730, §4551, and §4553)
- Establishes the Z’berg-Nejedly Forest Practice Act of 1973 (Forest Practice Act), which prohibits a person from conducting timber operations unless a THP prepared by an RPF has been submitted to, and approved by, the CalFire director. A THP is the functional equivalent of an environmental impact report under the California Environmental Quality Act (CEQA). (PRC §§4511 et seq.)
- Authorizes the Board to exempt certain tree removal activities from the Forest Practice Act or portions of the Act (PRC §4854), including:
- The Small Timberland Owner exemption, which provides an exemption, until December 2023, for the cutting or removal of trees that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns to reduce flammable materials and maintain a fuel break, if certain conditions are met. This exemption is limited to small forestland owners, defined to mean those who own 60 acres or less of timberland in the coast forest district or 100 acres of less in the northern or southern forest districts, as specified.
- The Forest Fire Prevention exemption, which provides an exemption, until January 1, 2026, for the harvesting of trees that eliminate the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns to reduce the rate of fire spread, duration and intensity, fuel ignitability, or ignition of tree crowns, if certain conditions are met. This exemption is limited to a tree harvesting area of up to 300 acres in moderate, high, and very high fire threat zones, as specified.
- The 150–300 Foot Fire Safe Clearance exemption, which provides an exemption, until January 1, 2026, for the cutting or removal of trees in compliance with defensible space requirements in the State Responsibility Area that eliminate the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns to reduce flammable materials and maintain a fuelbreak, if certain conditions are met. This exemption is limited to areas between 150 and 300 feet from the habitable structure, as specified.
- The Oak Woodland exemption, which provides an exemption for the cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands, if certain requirements are met.
This bill:
- Eliminates the Small Timberland Owner exemption.
- Consolidates the Small Timberland Owner and Forest Fire Prevention exemptions under a new exemption named the Forest Resilience exemption. This new exemption:
- Expands requirements for the submitted notice of exemption to include identifying the designated postharvest stocking, as specified, and providing additional information on preharvest stand conditions, as specified, and landowner goals and objectives that substantiates the selection of postharvest stocking, as specified.
- Limits the allowable tree harvesting area to 500 acres.
- Requires all harvested trees to be marked by an RPF before felling.
- Prohibits harvest of:
- The six largest trees per acre within the boundaries of a notice of exemption.
- Trees larger than 30 inches in diameter at breast height, including for the purposes of road construction or reconstruction, as specified, and except as specified for dead and dying trees.
- Any oak tree greater than 22 inches in diameter at breast height under a notice of exemption, unless for safety.
- Requires the postharvest composition of tree species to be representative of the preharvest stand condition and demonstrate progression towards climax forest conditions, as specified.
- Requires, within the northern and southern districts, if the preharvest dominant and codominant crown canopy is occupied by trees less than 14 inches in diameter at breast height, retention of a minimum of 65 trees greater than four inches in diameter at breast height.
- Requires slash and woody debris within 50 feet of a public road or critical infrastructure, as specified, to be chipped, burned, or removed.
- Authorizes the Board to adopt regulations for the removal of dead and dying trees in amounts less than 10% of the average volume per acre for trees up to 36 inches in diameter at breast height. Requires the Board to consider specified factors if adopting regulations.
- Directs the Board to develop clearly written guidance on inspection and enforceability standards relating to standards for only harvesting of trees less than 30 inches in diameter at breast height.
- Requires the Board to adopt regulations, initially as emergency regulations in accordance the Administrative Procedure Act (APA), that the Board considers necessary to implement and obtain compliance with the Forest Resilience Exemption, as specified.
- Sunsets this exemption on January 1, 2031.
- Revises the Oak Woodland exemption, as follows:
- Clarifies that an RPF must certify that the timber operation is designed to restore and conserve California black and Oregon white oak woodlands and associated grasslands encroached upon by conifers.
- Clarifies the Board’s responsibility to confirm that there is a minimum level of coverage California black and Oregon white oak in the treatment area prior to treatment.
- Generally prohibits harvest of trees larger than 30 inches in diameter at breast height for commercial purposes.
- Removes the limitation that conifers must be four inches in diameter at breast height or larger to be harvested.
- Limits the harvest area to 300 acres per ownership, rather than property, in a planning watershed in a five-year period.
- Provides that decadent (e.g. dead or broken) and deformed trees of wildlife value that are retained do not count toward basal area requirements.
- Authorizes the Board to establish minimum postharvest basal area requirements for California black or Oregon white oak.
- Removes the prohibition on using this exemption in the Southern Subdistrict of the Coast Forest District and the Southern Forest District.
- Requires the Board to adopt regulations, initially as emergency regulations in accordance the APA, that the Board considers necessary to implement and to obtain compliance with this exemption.
- Extends the sunset for the 150–300 Foot Fire Safe Clearance exemption to January 1, 2031.
- Incorporates “chaptering” amendments for Public Utilities Code section 399.20.3 proposed by AB 2750 (Gallagher).
- Makes technical, nonsubstantive, and conforming changes.
Comments
- Small Timberland Owner exemption. This exemption, which sunset last year, allowed a person to engage in specified forest management activities without a THP to reduce flammable materials and maintain a fuel break. The exemption was limited to small forestland owners, defined to mean those who own 60 acres or less of timberland in the coast forest district or 100 acres of less in the northern or southern forest districts, as specified.
According to the Board’s 2021 Annual Report, in 2020/21, there were only eight notices to use this exemption to treat a total of 165 acres. In fact, since its inception in 2019, this exemption has been used only 19 times, treating only 481 acres over five years.
This bill would eliminate this exemption and instead combine components of it with the proposed Forest Resilience exemption in order to make it easier to use this type of exemption to support forest resilience treatments.
- Forest Fire Prevention exemption. AB 2420 (La Malfa, Chapter 712, Statutes of 2004) established this exemption. The Legislature has revised this exemption over the years, including by AB 744 (Dahle and Gordon, Chapter 647, Statutes of 2013) and SB 901 (Dodd, Chapter 626, Statutes of 2018) in order to improve its utility.
According to CalFire, since the SB 901-revised Forest Fire Prevention exemption became effective in February 2019, RFPs have submitted 186 notices to use this exemption. Based on the acreage provided in these notices, the use of this exemption would have treated (or will treat) 15,867 acres. According to the Board, the average exemption project is about 95 acres, with projects ranging in size from two acres to 299 acres, distributed throughout the Coast, Cascade, Sierra, and Southern Areas. As noted by the sponsor, CalForests, in their letter, while this exemption certainly contributes somewhat to the state’s goal to treat 500,000 acres per year, it represents a small fraction of that goal and pales in comparison to recent catastrophic wildfires, which have burned over four million acres over the past several years.
To increase the utility of the exemptions focused on reducing fuel loads and supporting forest health, this bill would replace the Forest Fire Prevention exemption with a Forest Resilience exemption and combine aspects of the eliminated Small Timberland Owner exemption into this new exemption. In particular, this bill would, among other provisions, increase the maximum treatment size to 500 acres, update the stocking standards to reflect geographic diversity better, and allow the Board to determine necessary canopy closure metrics through rulemaking.
This bill also includes language to strengthen environmental protections and better protect egress routes and critical infrastructure to balance the provisions that seek to increase utility of this new exemption. Specifically, this bill would require retention of the six largest trees on each acre treated under the exemption, provide new protections for oak trees, prevent removal of larger (older) trees for temporary road construction, and impose new treatment standards for slash and woody debris within close proximity to public roads and critical infrastructure.
According to the sponsor, these changes will make it easier for stakeholders to utilize the new exemption in a way that will support achievement of the state’s 500,000-acre treatment goal. This is especially important as the state navigates an era of budget challenges in which there may be less state funding available for crucial fuel reduction projects. The sponsor also notes that the changes proposed in this bill resulted from thoughtful discussion between landowners, forestry experts, and NGOs, and incorporate many of the recommendations offered by CalFire and the Board within the January 2023 monitoring report.[1]
- Oak Woodland exemption. According to Yana Valachovic, the County Director and Forest Advisor for UC Cooperative Extension in Humboldt and Del Norte Counties, this exemption enables both the protection and restoration of two deciduous oak species – California black and Oregon white oak woodlands – that suffer from the loss of frequent fire. In particular, fire suppression policies have allowed conifers, like Douglas-firs, to encroach into oak habitat with negative consequences for the oaks. Research shows that Douglas-fir stand dominance can occur in as little as fifty years, leading to accelerated oak mortality, decreased understory diversity, and severely compromised oak health in encroached stands. Essentially, fir encroachment due to a lack of fire in oak woodland areas is causing slow type conversion of these areas, eliminating important oak woodland forests.
According to Ms. Valachovic, her research has documented that the exemption’s rules regarding the size of trees that may be harvested to support oak woodland restoration have limited the utility of this exemption. In her work with landowners and foresters, she has continually heard requests to increase the diameter limits for conifer removal and suggests harmonizing and increasing the diameter limits to meet the same standards of the Forest Resiliency Exemption. This bill would do that and it provides other clarifying and streamlining changes to the exemption.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: No
SUPPORT: (Verified 8/19/24)
California Forestry Association (source)
American Forest Foundation
Associated California Loggers
Association of California Water Agencies
Auten Resource Consulting
California Farm Bureau Federation
California Licensed Foresters Association
California Native Plant Society
California State Association of Counties
California Wilderness Coalition
Central Sierra Environmental Resource Center
Defenders of Wildlife
Environmental Defense Fund
Forest Landowners of California
Humboldt County Prescribed Burn Association
Humboldt Redwood Company LLC
Mattole Restoration Council
Mendocino Redwood Company LLC
Northcoast Regional Land Trust
Pacific Forest Trust
Rural County Representatives of California
Sierra Business Council
Sierra Cascade Logging Conference
Sierra Forest Legacy
Sierra Institute for Community and Environment
The Buckeye Conservancy
The Fire Restoration Group
1 individual
OPPOSITION: (Verified 8/19/24)
None received
ARGUMENTS IN SUPPORT: According to the author, “The wildfire hazard in California has grown exponentially over the past decade. In an effort to mitigate this hazard, the state has set a goal of treating 500,000 acres of state land a year by increasing the pace and scale of forest management, among other tools. AB 2276 will contribute to California’s goal by extending and increasing the utility of timber harvest plan exemptions, making it more economically feasible to complete wildfire mitigation projects that provide for healthier and more resilient forests. With the budget challenges facing the state, it is important that we implement smart solutions that take advantage of existing partnerships and shared goals of private landowners, forest managers, environmental stewards, and state agencies.”
ASSEMBLY FLOOR: 65-0, 5/9/24
AYES: Addis, Aguiar-Curry, Alanis, Alvarez, Arambula, Bauer-Kahan, Bennett, Berman, Boerner, Bonta, Bryan, Calderon, Juan Carrillo, Wendy Carrillo, Chen, Connolly, Davies, Dixon, Essayli, Mike Fong, Vince Fong, Friedman, Gallagher, Garcia, Gipson, Hart, Holden, Hoover, Irwin, Jackson, Jones-Sawyer, Kalra, Lackey, Lee, Lowenthal, Maienschein, McCarty, McKinnor, Muratsuchi, Ortega, Pacheco, Papan, Jim Patterson, Joe Patterson, Pellerin, Quirk-Silva, Ramos, Rendon, Reyes, Rodriguez, Blanca Rubio, Sanchez, Santiago, Soria, Ta, Valencia, Villapudua, Waldron, Ward, Weber, Wicks, Wilson, Wood, Zbur, Robert Rivas
NO VOTE RECORDED: Bains, Cervantes, Megan Dahle, Flora, Gabriel, Grayson, Haney, Low, Mathis, Stephanie Nguyen, Petrie-Norris, Luz Rivas, Schiavo, Ting, Wallis
Prepared by: Catherine Baxter / N.R. & W. / (916) 651-4116
8/20/24 16:01:47
**** END ****
See report “Forest Fire Prevention, or Forest Resiliency?” ↑
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | AB 2276 |
THIRD READING
Bill No: AB 2276
Author: Wood (D)
Amended: 6/12/24 in Senate
Vote: 21
SENATE NATURAL RES. & WATER COMMITTEE: 11-0, 6/11/24
AYES: Min, Seyarto, Allen, Dahle, Eggman, Grove, Hurtado, Laird, Limón, Padilla, Stern
SENATE APPROPRIATIONS COMMITTEE: Senate Rule 28.8
ASSEMBLY FLOOR: 65-0, 5/9/24 (Consent) - See last page for vote
SUBJECT: Forestry: timber harvesting plans: exemptions
SOURCE: California Forestry Association
DIGEST:
This bill makes various changes to certain exemptions under the Forest Practice Act, including to consolidate the Small Timberland Owner Exemption and the Forest Fire Prevention Exemption under a new exemption called the Forest Resilience Exemption, revise the Oak Woodland Exemption, and extend specified exemption sunset dates.
ANALYSIS:
Existing law:
- Establishes CalFire in the California Natural Resources Agency (CNRA) under the control of the CalFire director. CalFire is responsible for the fire protection, fire prevention, maintenance, and enhancement of the state’s forest, range, and brushland resources, contract fire protection, associated emergency services, and assistance in civil disasters and other nonfire emergencies. (Public Resources Code (PRC) §701 and §713)
- Establishes the State Board of Forestry and Fire Protection (Board) in CalFire, consisting of nine members appointed by the Governor, subject to confirmation by the Senate. Among others, the Board is responsible for adopting and continuously reviewing and revising forest practice rules. (PRC §730, §4551, and §4553)
- Establishes the Z’berg-Nejedly Forest Practice Act of 1973 (Forest Practice Act), which prohibits a person from conducting timber operations unless a THP prepared by an RPF has been submitted to, and approved by, the CalFire director. A THP is the functional equivalent of an environmental impact report under the California Environmental Quality Act (CEQA). (PRC §§4511 et seq.)
- Authorizes the Board to exempt certain tree removal activities from the Forest Practice Act or portions of the Act (PRC §4854), including:
- The Small Timberland Owner exemption, which provides an exemption, until December 2023, for the cutting or removal of trees that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns to reduce flammable materials and maintain a fuel break, if certain conditions are met. This exemption is limited to small forestland owners, defined to mean those who own 60 acres or less of timberland in the coast forest district or 100 acres of less in the northern or southern forest districts, as specified.
- The Forest Fire Prevention exemption, which provides an exemption, until January 1, 2026, for the harvesting of trees that eliminate the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns to reduce the rate of fire spread, duration and intensity, fuel ignitability, or ignition of tree crowns, if certain conditions are met. This exemption is limited to a tree harvesting area of up to 300 acres in moderate, high, and very high fire threat zones, as specified.
- The 150–300 Foot Fire Safe Clearance exemption, which provides an exemption, until January 1, 2026, for the cutting or removal of trees in compliance with defensible space requirements in the State Responsibility Area that eliminate the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns to reduce flammable materials and maintain a fuelbreak, if certain conditions are met. This exemption is limited to areas between 150 and 300 feet from the habitable structure, as specified.
- The Oak Woodland exemption, which provides an exemption for the cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands, if certain requirements are met.
This bill:
- Eliminates the Small Timberland Owner exemption.
- Consolidates the Small Timberland Owner and Forest Fire Prevention exemptions under a new exemption named the Forest Resilience exemption. This new exemption:
- Expands requirements for the submitted notice of exemption to include identifying the designated postharvest stocking, as specified, and providing additional information on preharvest stand conditions, as specified, and landowner goals and objectives that substantiates the selection of postharvest stocking, as specified.
- Limits the allowable tree harvesting area to 500 acres.
- Requires all harvested trees to be marked by an RPF before felling.
- Prohibits harvest of:
- The six largest trees per acre within the boundaries of a notice of exemption.
- Trees larger than 30 inches in diameter at breast height, including for the purposes of road construction or reconstruction, as specified, and except as specified for dead and dying trees.
- Any oak tree greater than 22 inches in diameter at breast height under a notice of exemption, unless for safety.
- Requires the postharvest composition of tree species to be representative of the preharvest stand condition and demonstrate progression towards climax forest conditions, as specified.
- Requires, within the northern and southern districts, if the preharvest dominant and codominant crown canopy is occupied by trees less than 14 inches in diameter at breast height, retention of a minimum of 65 trees greater than four inches in diameter at breast height.
- Requires slash and woody debris within 50 feet of a public road or critical infrastructure, as specified, to be chipped, burned, or removed.
- Authorizes the Board to adopt regulations for the removal of dead and dying trees in amounts less than 10% of the average volume per acre for trees up to 36 inches in diameter at breast height. Requires the Board to consider specified factors if adopting regulations.
- Directs the Board to develop clearly written guidance on inspection and enforceability standards relating to standards for only harvesting of trees less than 30 inches in diameter at breast height.
- Requires the Board to adopt regulations, initially as emergency regulations in accordance the Administrative Procedure Act (APA), that the Board considers necessary to implement and obtain compliance with the Forest Resilience Exemption, as specified.
- Sunsets this exemption on January 1, 2031.
- Revises the Oak Woodland exemption, as follows:
- Clarifies that an RPF must certify that the timber operation is designed to restore and conserve California black and Oregon white oak woodlands and associated grasslands encroached upon by conifers.
- Clarifies the Board’s responsibility to confirm that there is a minimum level of coverage California black and Oregon white oak in the treatment area prior to treatment.
- Generally prohibits harvest of trees larger than 30 inches in diameter at breast height for commercial purposes.
- Removes the limitation that conifers must be four inches in diameter at breast height or larger to be harvested.
- Limits the harvest area to 300 acres per ownership, rather than property, in a planning watershed in a five-year period.
- Provides that decadent (e.g. dead or broken) and deformed trees of wildlife value that are retained do not count toward basal area requirements.
- Authorizes the Board to establish minimum postharvest basal area requirements for California black or Oregon white oak.
- Removes the prohibition on using this exemption in the Southern Subdistrict of the Coast Forest District and the Southern Forest District.
- Requires the Board to adopt regulations, initially as emergency regulations in accordance the APA, that the Board considers necessary to implement and to obtain compliance with this exemption.
- Extends the sunset for the 150–300 Foot Fire Safe Clearance exemption to January 1, 2031.
- Makes technical, nonsubstantive, and conforming changes.
Comments
- Small Timberland Owner exemption. This exemption, which sunset last year, allowed a person to engage in specified forest management activities without a THP to reduce flammable materials and maintain a fuel break. The exemption was limited to small forestland owners, defined to mean those who own 60 acres or less of timberland in the coast forest district or 100 acres of less in the northern or southern forest districts, as specified.
According to the Board’s 2021 Annual Report, in 2020/21, there were only eight notices to use this exemption to treat a total of 165 acres. In fact, since its inception in 2019, this exemption has been used only 19 times, treating only 481 acres over five years.
This bill would eliminate this exemption and instead combine components of it with the proposed Forest Resilience exemption in order to make it easier to use this type of exemption to support forest resilience treatments.
- Forest Fire Prevention exemption. AB 2420 (La Malfa, Chapter 712, Statutes of 2004) established this exemption. The Legislature has revised this exemption over the years, including by AB 744 (Dahle and Gordon, Chapter 647, Statutes of 2013) and SB 901 (Dodd, Chapter 626, 2018) in order to improve its utility.
According to CalFire, since the SB 901-revised Forest Fire Prevention exemption became effective in February 2019, RFPs have submitted 186 notices to use this exemption. Based on the acreage provided in these notices, the use of this exemption would have treated (or will treat) 15,867 acres. According to the Board, the average exemption project is about 95 acres, with projects ranging in size from two acres to 299 acres, distributed throughout the Coast, Cascade, Sierra, and Southern Areas. As noted by the sponsor, CalForests, in their letter, while this exemption certainly contributes somewhat to the state’s goal to treat 500,000 acres per year, it represents a small fraction of that goal and pales in comparison to recent catastrophic wildfires, which have burned over four million acres over the past several years.
To increase the utility of the exemptions focused on reducing fuel loads and supporting forest health, this bill would replace the Forest Fire Prevention exemption with a Forest Resilience exemption and combine aspects of the eliminated Small Timberland Owner exemption into this new exemption. In particular, this bill would, among other provisions, increase the maximum treatment size to 500 acres, update the stocking standards to reflect geographic diversity better, and allow the Board to determine necessary canopy closure metrics through rulemaking.
This bill also includes language to strengthen environmental protections and better protect egress routes and critical infrastructure to balance the provisions that seek to increase utility of this new exemption. Specifically, this bill would require retention of the six largest trees on each acre treated under the exemption, provide new protections for oak trees, prevent removal of larger (older) trees for temporary road construction, and impose new treatment standards for slash and woody debris within close proximity to public roads and critical infrastructure.
According to the sponsor, these changes will make it easier for stakeholders to utilize the new exemption in a way that will support achievement of the state’s 500,000-acre treatment goal. This is especially important as the state navigates an era of budget challenges in which there may be less state funding available for crucial fuel reduction projects. The sponsor also notes that the changes proposed in this bill resulted from thoughtful discussion between landowners, forestry experts, and NGOs, and incorporate many of the recommendations offered by CalFire and the Board within the January 2023 monitoring report.[1]
- Oak Woodland exemption. According to Yana Valachovic, the County Director and Forest Advisor for UC Cooperative Extension in Humboldt and Del Norte Counties, this exemption enables both the protection and restoration of two deciduous oak species – California black and Oregon white oak woodlands – that suffer from the loss of frequent fire. In particular, fire suppression policies have allowed conifers, like Douglas-firs, to encroach into oak habitat with negative consequences for the oaks. Research shows that Douglas-fir stand dominance can occur in as little as fifty years, leading to accelerated oak mortality, decreased understory diversity, and severely compromised oak health in encroached stands. Essentially, fir encroachment due to a lack of fire in oak woodland areas is causing slow type conversion of these areas, eliminating important oak woodland forests.
According to Ms. Valachovic, her research has documented that the exemption’s rules regarding the size of trees that may be harvested to support oak woodland restoration have limited the utility of this exemption. In her work with landowners and foresters, she has continually heard requests to increase the diameter limits for conifer removal and suggests harmonizing and increasing the diameter limits to meet the same standards of the Forest Resiliency Exemption. This bill would do that and it provides other clarifying and streamlining changes to the exemption.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: No
SUPPORT: (Verified 6/21/24)
California Forestry Association (source)
American Forest Foundation
Associated California Loggers
Association of California Water Agencies
Auten Resource Consulting
California Farm Bureau Federation
California Licensed Foresters Association
California Native Plant Society
California State Association of Counties
California Wilderness Coalition
Central Sierra Environmental Resource Center
Defenders of Wildlife
Environmental Defense Fund
Forest Landowners of California
Humboldt County Prescribed Burn Association
Humboldt Redwood Company LLC
Mattole Restoration Council
Mendocino Redwood Company LLC
Northcoast Regional Land Trust
Pacific Forest Trust
Rural County Representatives of California
Sierra Business Council
Sierra Cascade Logging Conference
Sierra Forest Legacy
Sierra Institute for Community and Environment
The Buckeye Conservancy
The Fire Restoration Group
1 individual
OPPOSITION: (Verified 6/21/24)
None received
ARGUMENTS IN SUPPORT: According to the author, “The wildfire hazard in California has grown exponentially over the past decade. In an effort to mitigate this hazard, the state has set a goal of treating 500,000 acres of state land a year by increasing the pace and scale of forest management, among other tools. AB 2276 will contribute to California’s goal by extending and increasing the utility of timber harvest plan exemptions, making it more economically feasible to complete wildfire mitigation projects that provide for healthier and more resilient forests. With the budget challenges facing the state, it is important that we implement smart solutions that take advantage of existing partnerships and shared goals of private landowners, forest managers, environmental stewards, and state agencies.”
ASSEMBLY FLOOR: 65-0, 5/9/24
AYES: Addis, Aguiar-Curry, Alanis, Alvarez, Arambula, Bauer-Kahan, Bennett, Berman, Boerner, Bonta, Bryan, Calderon, Juan Carrillo, Wendy Carrillo, Chen, Connolly, Davies, Dixon, Essayli, Mike Fong, Vince Fong, Friedman, Gallagher, Garcia, Gipson, Hart, Holden, Hoover, Irwin, Jackson, Jones-Sawyer, Kalra, Lackey, Lee, Lowenthal, Maienschein, McCarty, McKinnor, Muratsuchi, Ortega, Pacheco, Papan, Jim Patterson, Joe Patterson, Pellerin, Quirk-Silva, Ramos, Rendon, Reyes, Rodriguez, Blanca Rubio, Sanchez, Santiago, Soria, Ta, Valencia, Villapudua, Waldron, Ward, Weber, Wicks, Wilson, Wood, Zbur, Robert Rivas
NO VOTE RECORDED: Bains, Cervantes, Megan Dahle, Flora, Gabriel, Grayson, Haney, Low, Mathis, Stephanie Nguyen, Petrie-Norris, Luz Rivas, Schiavo, Ting, Wallis
Prepared by: Catherine Baxter / N.R. & W. / (916) 651-4116
6/27/24 15:38:51
**** END ****
See report “Forest Fire Prevention, or Forest Resiliency?” ↑
SENATE COMMITTEE ON NATURAL RESOURCES AND WATER
Senator Dave Min, Chair
2023 - 2024 Regular
Bill No: AB 2276 Hearing Date: June 11, 2024
Author: | Wood | ||
Version: | June 3, 2024 Amended | ||
Urgency: | No | Fiscal: | Yes |
Consultant: | Catherine Baxter | ||
Subject: Forestry: timber harvesting plans: exemptions
SUMMARY
This bill would make various changes to certain exemptions under the Forest Practice Act, including to consolidate the Small Timberland Owner Exemption and the Forest Fire Prevention Exemption under a new exemption called the Forest Resilience Exemption, revise the Black and White Oak Exemption, and extend specified exemption sunset dates.
BACKGROUND AND EXISTING LAW
Forest Management. Past logging and decades of fire suppression have left unnaturally dense forests that lack the large, old, fire-resilient trees that once characterized the forests of the Sierra, Cascade, and North Coast. Those historic forests were shaped by frequent fires, both from lightning and Indigenous burning, that helped maintain the open characteristics where John Muir described being able to ride a horse through the forest without a branch knocking off his hat. Dense, young forests now extend mile after mile, providing the continuous fuel for large-scale fires burning with extremely damaging outcomes. Forest health is critical to managing wildfire prevention.
The Forest Practice Act. The stated intent of the Forest Practice Act is to create and maintain an effective and comprehensive system of regulation and use of all timberlands to restore, enhance, and maintain the productivity of timberlands to achieve maximum sustained production of high-quality timber products while giving consideration to carbon dioxide sequestration, recreation, watershed, wildlife, range and forage, fisheries, regional economic vitality, employment, and aesthetic enjoyment values.
Timber harvest operations on private lands in California are subject to the Forest Practice Act. Before timber operations may commence, a registered professional forester (RPF) must prepare and the director of the Department of Forestry and Fire Protection (CalFire) must approve a timber harvesting plan (THP) for the operations. The THP details how timber operations (e.g., felling and harvest of trees, related road construction and maintenance, and preparing ground for planting of seedlings) are to occur. THPs are rich in detail and nuance, and have long-standing requirements for forest management.
According to Pacific Forest Trust, to create healthy forests that are resilient to wildfire, the state needs to focus on reducing forest density by removing small diameter trees and surface fuels, while retaining the largest trees. This presents a challenge for the traditional THP process because it typically costs tens to hundreds of thousands of dollars to prepare a THP and go through the approval process. In order to recoup those costs, the landowner would need to harvest the largest, most valuable trees. In other words, for many landowners, it is cost prohibitive and potentially a financial loss to prepare a THP in order to thin their forests to make them more resilient to wildfire, consistent with the state’s goals. Certain exemptions, discussed further below, seek to address this issue by removing the requirement for a THP for certain types of forest management activities.
SB 901. In 2018, the Legislature passed SB 901 (Dodd, Chapter 626, Statutes of 2018), which sought to establish a comprehensive framework to address and prevent catastrophic wildfires, including prevention and planning by the state's electric utilities, management of the state's forests, chaparral, and other lands to prevent and defend against wildfires, and standards to stabilize electric utilities in the event of extensive liability resulting from claims under inverse condemnation.
SB 901 included reforms to the Forest Practice Act and associated exemptions, including by adding, revising, and extending several wildfire-related THP exemptions. In particular, SB 901 created a Small Timberland Owner exemption; substantially revised the Forest Fire Prevention exemption to permit limited construction of temporary roads and harvest of larger diameter trees, and extend the operation of this exemption; and streamlined some requirements for the Oak Woodland exemption. The Small Timberland Owner and Forest Fire Prevention exemptions are intended to help reduce fuel loading in forestlands by focusing the removal on small and mid-sized trees that are currently over-stocked. The Oak Woodland exemption is intended to support conservation and restoration of California black and Oregon white oak woodlands in areas where conifers have encroached on their habitat as a result of a history of fire suppression.
Existing law:
- Establishes CalFire in the California Natural Resources Agency (CNRA) under the control of the CalFire director. CalFire is responsible for the fire protection, fire prevention, maintenance, and enhancement of the state’s forest, range, and brushland resources, contract fire protection, associated emergency services, and assistance in civil disasters and other nonfire emergencies. Public Resources Code (PRC) §701 and §713, respectively.
- Establishes the State Board of Forestry and Fire Protection (Board) in CalFire, consisting of nine members appointed by the Governor, subject to confirmation by the Senate. Among others, the Board is responsible for adopting and continuously reviewing and revising forest practice rules. PRC §730, §4551, and §4553.
- Establishes the Z’berg-Nejedly Forest Practice Act of 1973 (Forest Practice Act), which prohibits a person from conducting timber operations unless a THP prepared by an RPF has been submitted to, and approved by, the CalFire director. A THP is the functional equivalent of an environmental impact report under the California Environmental Quality Act (CEQA). PRC §§4511 et seq.
- Authorizes the Board to exempt certain tree removal activities from the Forest Practice Act or portions of the Act (PRC §4854), including:
- The Small Timberland Owner exemption, which provides an exemption, until December 2023, for the cutting or removal of trees that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns to reduce flammable materials and maintain a fuel break, if certain conditions are met. This exemption is limited to small forestland owners, defined to mean those who own 60 acres or less of timberland in the coast forest district or 100 acres of less in the northern or southern forest districts, as specified.
- The Forest Fire Prevention exemption, which provides an exemption, until January 1, 2026, for the harvesting of trees that eliminate the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns to reduce the rate of fire spread, duration and intensity, fuel ignitability, or ignition of tree crowns, if certain conditions are met. This exemption is limited to a tree harvesting area of up to 300 acres in moderate, high, and very high fire threat zones, as specified.
- The 150–300 Foot Fire Safe Clearance exemption, which provides an exemption, until January 1, 2026, for the cutting or removal of trees in compliance with defensible space requirements in the State Responsibility Area that eliminate the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns to reduce flammable materials and maintain a fuelbreak, if certain conditions are met. This exemption is limited to areas between 150 and 300 feet from the habitable structure, as specified.
- The Oak Woodland exemption, which provides an exemption for the cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands, if certain requirements are met.
PROPOSED LAW
This bill would:
- Eliminate the Small Timberland Owner exemption.
- Rename the Forest Fire Prevention exemption to the Forest Resilience exemption, and consolidate this new exemption with some of the conditions, rules, and limitations from the Small Timberland Owner exemption. Specifically:
- Expand requirements for the submitted notice of exemption to including identifying the designated postharvest stocking, as specified, and providing additional information on preharvest stand conditions, as specified, and landowner goals and objectives that substantiates the selection of postharvest stocking, as specified.
- Limit the allowable tree harvesting area to 500 acres.
- Require all harvested trees to be marked by an RPF before felling.
- Prohibit harvest of:
- The six largest trees per acre within the boundaries of a notice of exemption.
- Trees larger than 30 inches in diameter at breast height, including for the purposes of road construction or reconstruction, as specified, and except as specified for dead and dying trees.
- Any oak tree greater than 22 inches in diameter at breast height under a notice of exemption, unless for safety.
- Require, within the northern and southern districts, if the preharvest dominant and codominant crown canopy is occupied by trees less than 14 inches in diameter at breast height, retention of a minimum of 65 trees greater than four inches in diameter at breast height.
- Require slash and woody debris within 50 feet of a public road or critical infrastructure, as specified, to be chipped, burned, or removed.
- Authorize the Board to adopt regulations:
- For the removal of dead and dying trees in amounts less than 10% of the average volume per acre for trees up to 36 inches in diameter at breast height. Require the Board to consider specified factors if adopting regulations.
- Pertaining to canopy closure if determined appropriate and necessary.
- Direct the Board to develop clearly written guidance on inspection and enforceability standards relating to standards for only harvesting of trees less than 30 inches in diameter at breast height.
- Require the Board to adopt regulations, initially as emergency regulations in accordance the Administrative Procedure Act (APA), that the Board considers necessary to implement and obtain compliance with the Forest Resilience Exemption, as specified.
- Sunset this exemption on January 1, 2031.
- Revise the Oak Woodland exemption, as follows:
- Clarify that an RPF must certify that the timber operation is designed to restore and conserve California black and Oregon white oak woodlands and associated grasslands encroached upon by conifers.
- Clarify the Board’s responsibility to confirm that there is a minimum level of coverage California black and Oregon white oak in the treatment area prior to treatment.
- Generally prohibit harvest of trees larger than 30 inches in diameter at breast height for commercial purposes.
- Remove the limitation that conifers must be four inches in diameter at breast height or larger to be harvested.
- Limit the harvest area to 300 acres per ownership, rather than property, in a planning watershed in a five-year period.
- Provide that decadent (e.g. dead or broken) and deformed trees of wildlife value that are retained do not count toward basal area requirements.
- Authorize the Board to establish minimum postharvest basal area requirements for California black or Oregon white oak.
- Remove the prohibition on using this exemption in the Southern Subdistrict of the Coast Forest District and the Southern Forest District.
- Require the Board to adopt regulations, initially as emergency regulations in accordance the APA, that the Board considers necessary to implement and to obtain compliance with this exemption.
- Extend the sunset for the 150–300 Foot Fire Safe Clearance exemption to January 1, 2031.
- Make technical, nonsubstantive, and conforming changes.
ARGUMENTS IN SUPPORT
According to the author, “The wildfire hazard in California has grown exponentially over the past decade. In an effort to mitigate this hazard, the state has set a goal of treating 500,000 acres of state land a year by increasing the pace and scale of forest management, among other tools. AB 2276 will contribute to California’s goal by extending and increasing the utility of timber harvest plan exemptions, making it more economically feasible to complete wildfire mitigation projects that provide for healthier and more resilient forests. With the budget challenges facing the state, it is important that we implement smart solutions that take advantage of existing partnerships and shared goals of private landowners, forest managers, environmental stewards, and state agencies.”
ARGUMENTS IN OPPOSITION
None received.
COMMENTS
Small Timberland Owner exemption. This exemption, which sunset last year, allowed a person to engage in specified forest management activities without a THP to reduce flammable materials and maintain a fuel break. The exemption was limited to small forestland owners, defined to mean those who own 60 acres or less of timberland in the coast forest district or 100 acres of less in the northern or southern forest districts, as specified.
According to the Board’s 2021 Annual Report, in 2020/21, there were only eight notices to use this exemption to treat a total of 165 acres. In fact, since its inception in 2019, this exemption has been used only 19 times, treating only 481 acres over five years.
This bill would eliminate this exemption and instead combine components of it with the proposed Forest Resilience exemption in order to make it easier to use this type of exemption to support forest resilience treatments.
Forest Fire Prevention exemption. AB 2420 (La Malfa, Chapter 712, Statutes of 2004) established this exemption. The Legislature has revised this exemption over the years, including by AB 744 (Dahle and Gordon, Chapter 647, Statutes of 2013) and SB 901 (Dodd, Chapter 626, 2018) in order to improve its utility.
According to CalFire, since the SB 901-revised Forest Fire Prevention exemption became effective in February 2019, RFPs have submitted 186 notices to use this exemption. Based on the acreage provided in these notices, the use of this exemption would have treated (or will treat) 15,867 acres. According to the Board, the average exemption project is about 95 acres, with projects ranging in size from two acres to 299 acres, distributed throughout the Coast, Cascade, Sierra, and Southern Areas. As noted by the sponsor, CalForests, in their letter, while this exemption certainly contributes somewhat to the state’s goal to treat 500,000 acres per year, it represents a small fraction of that goal and pales in comparison to recent catastrophic wildfires, which have burned over four million acres over the past several years.
To increase the utility of the exemptions focused on reducing fuel loads and supporting forest health, this bill would replace the Forest Fire Prevention exemption with a Forest Resilience exemption and combine aspects of the eliminated Small Timberland Owner exemption into this new exemption. In particular, the bill would, among other provisions, increase the maximum treatment size to 500 acres, update the stocking standards to reflect geographic diversity better, and allow the Board to determine necessary canopy closure metrics through rulemaking.
The bill also includes language to strengthen environmental protections and better protect egress routes and critical infrastructure to balance the provisions that seek to increase utility of this new exemption. Specifically, the bill would require retention of the six largest trees on each acre treated under the exemption, provide new protections for oak trees, prevent removal of larger (older) trees for temporary road construction, and impose new treatment standards for slash and woody debris within close proximity to public roads and critical infrastructure.
According to the sponsor, these changes will make it easier for stakeholders to utilize the new exemption in a way that will support achievement of the state’s 500,000-acre treatment goal. This is especially important as the state navigates an era of budget challenges in which there may be less state funding available for crucial fuel reduction projects. The sponsor also notes that the changes proposed in this bill resulted from thoughtful discussion between landowners, forestry experts, and NGOs, and incorporate many of the recommendations offered by CalFire and the Board within the January 2023 monitoring report.[1]
Oak Woodland exemption. According to Yana Valachovic, the County Director and Forest Advisor for UC Cooperative Extension in Humboldt and Del Norte Counties, this exemption enables both the protection and restoration of two deciduous oak species – California black and Oregon white oak woodlands – that suffer from the loss of frequent fire. In particular, fire suppression policies have allowed conifers, like Douglas-firs, to encroach into oak habitat with negative consequences for the oaks. Research shows that Douglas-fir stand dominance can occur in as little as fifty years, leading to accelerated oak mortality, decreased understory diversity, and severely compromised oak health in encroached stands. Essentially, fir encroachment due to a lack of fire in oak woodland areas is causing slow type conversion of these areas, eliminating important oak woodland forests.
According to Ms. Valachovic, her research has documented that the exemption’s rules regarding the size of trees that may be harvested to support oak woodland restoration have limited the utility of this exemption. In her work with landowners and foresters, she has continually heard requests to increase the diameter limits for conifer removal and suggests harmonizing and increasing the diameter limits to meet the same standards of the Forest Resiliency Exemption. This bill would do that and it provides other clarifying and streamlining changes to the exemption.
Committee amendments. Should the bill move forward, the Committee may wish to consider adopting the following technical amendments.
Postharvest species composition. The Small Timberland Owner exemption requires the postharvest composition of tree species to be representative of the preharvest stand condition and demonstrate progression towards climax forest conditions, unless justified by the RPF. The bill does not carry this requirement over into the new Forest Resilience exemption. Changing the species composition of a stand represents a significant impact, raising the question of whether it should qualify for inclusion in an exemption or be assessed through the full THP process. Instead, amend the bill to carryover this requirement from the Small Timberland Owner exemption to the new Forest Resilience exemption.
Canopy closure. This bill would eliminate the requirement for the Board to adopt regulations related to canopy closure, replacing it with language that states the Board “may adopt regulations pertaining to canopy closure if determined appropriate and necessary.” Canopy retention is an important metric for maintaining wildlife habitat and structural heterogeneity in treated stands. Opening canopies could have impacts on species that rely on closed canopy stands. Instead, amend the bill to retain the requirement for the Board to adopt regulations related to canopy closure. [See Amendment 2]
Missing text. PRC §4584 (j)(4)(D)(iv) contains a typographical error, omitting “per acre.” Amend the bill to add this in.
Related legislation.
AB 522 (Fong, Chapter 491, Statutes of 2022) extended the sunset for the Forest Fire Prevention exemption until January 1, 2026.
AB 431 (Patterson, Chapter 230, Statutes of 2021) extended the sunset date for the 150–300 Foot Fire Safe Clearance exemption until January 1, 2026.
SB 901 (Dodd, Chapter 626, Statutes of 2018), among other provisions, created a Small Timberland Owner exemption; substantially revised the Forest Fire Prevention exemption; and streamlined some requirements for the Oak Woodland exemption.
SUGGESTED AMENDMENTS
AMENDMENT 1
Amend PRC §4584 to add clause (x) to (j)(1)(D), as follows:
(x) The postharvest composition of tree species shall be representative of the preharvest stand condition and demonstrate progression towards climax forest conditions, unless the registered professional forester provides information explaining how modification of species diversity will benefit forest health and resiliency.
AMENDMENT 2
Amend PRC §4584, as follows:
(j)(1)(E)(i) The board shall adopt regulations for the treatment of understory vegetation and standing dead fuels, canopy closure, clearance to base of live crown, or ladder fuels, that could promote the spread of wildfire. The board may adopt regulations pertaining to canopy closure if determined appropriate and necessary.
AMENDMENT 3
Amend PRC §4584(j)(4)(D)(iv), as follows:
(iv) Within the northern district and southern district, if the preharvest dominant and codominant crown canopy is occupied by trees less than 14 inches in diameter at breast height, a minimum of 65 trees per acre over 4 inches in diameter at breast height shall be retained.
SUPPORT
California Forestry Association (sponsor)
American Forest Foundation
Associated California Loggers
Association of California Water Agencies
Auten Resource Consulting
Buckeye Conservancy, the
California Licensed Foresters Association
California Native Plant Society
California State Association of Counties
California Wilderness Coalition
Central Sierra Environmental Resource Center
Defenders of Wildlife
Environmental Defense Fund
Fire Restoration Group, the
Forest Landowners of California
Humboldt County Prescribed Burn Association
Humboldt Redwood Company LLC
Mattole Restoration Council
Mendocino Redwood Company LLC
Northcoast Regional Land Trust
Pacific Forest Trust
Rural County Representatives of California
Sierra Business Council
Sierra Cascade Logging Conference
Sierra Forest Legacy
Sierra Institute for Community and Environment
One individual
OPPOSITION
None Received
-- END --
See report “Forest Fire Prevention, or Forest Resiliency?” ↑
Date of Hearing: May 1, 2024
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Buffy Wicks, Chair
ABPCA Bill Id:AB 2276
Author:(Wood) – As Amended Ver:April 17, 2024
Policy Committee: | Natural Resources | Vote: | 11 - 0 |
|
| ||
|
|
Urgency: No State Mandated Local Program: No Reimbursable: No
SUMMARY:
This bill makes various changes to the Forest Practice Act (Act) to consolidate and update exemptions, and extends specified exemption sunset dates.
Specifically, this bill, among other things:
- Deletes the Small Timberland Owner Exemption and its associated conditions from the Act.
- Renames the Forest Fire Prevention Exemption the Forest Resilience Exemption and consolidates the new exemption with conditions from the Small Timberland Owner Exemption, as specified.
- Deletes, under the exemption for the cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands, the requirement for the State Board of Forestry and Fire Protection (Board) to adopt regulations.
- Establishes a sunset date of January 1, 2031, for the newly developed Forest Resilience Exemption and extends the sunset for an existing structure protection exemption under the Act from January 1, 2026, to January 1, 2031.
FISCAL EFFECT:
Minor and absorbable costs to the California Department of Forestry and Fire Protection (CAL FIRE). CAL FIRE does not anticipate that the consolidation and reconfiguration of the aforementioned exemptions will result in any substantive changes to its staffing, workload, or resource needs.
COMMENTS:
1) Purpose. According to the author:
The wildfire hazard in California has grown exponentially over the past decade. In an effort to mitigate this hazard, the state has set a goal of treating 500,000 acres of state land a year by increasing the pace and scale of forest management, among other tools. AB 2276 will contribute to California’s goal by extending and increasing the utility of timber harvest plan exemptions, making it more economically feasible to complete wildfire mitigation projects that provide for healthier and more resilient forests. With the budget challenges facing the state, it is important that we implement smart solutions that take advantage of existing partnerships and shared goals of private landowners, forest managers, environmental stewards, and state agencies.
2) Background. Timber harvesting operations on private lands in California must file timber harvesting plans (THPs), which detail how timber operations are to occur. THPs are rich in detail and nuance and have longstanding requirements for forest management. According to Pacific Forest Trust (PFT) and other organizations in support of this bill, to create more fire-resilient forests, the state needs to focus on reducing density by removing small trees and surface fuels while retaining the largest trees. This presents a challenge for the traditional THP permit because it typically costs tens of thousands of dollars, and landowners need to recoup that cost by cutting down large, valuable trees. The coalition contends, “There needs to be a more cost-effective way to do ecological thinning where we can retain the largest, most important trees.”
This bill, among other things, revises, improves, and reauthorizes an exemption first created in 2004 which provides an alternative to the THP process. It allows relatively light-touch logging activities (compared to what could be done under a THP) subject to numerous protective constraints but provides a more economical and easier way to do generally beneficial activities.
To increase the utility of the new Forest Resilience Exemption for private landowners and others, this bill increases the maximum project size to 500 acres, revises the maximum allowable diameter of trees that can be removed to allow field professionals to make more accurate determinations of tree size in the field, updates the stocking standards to better reflect geographic diversity, and allows the Board to determine necessary canopy closure metrics through rulemaking.
To balance the expanded exemption with environmental protections, the bill also requires, under the Forest Resilience Exemption, retention of the six largest trees on each acre treated under the exemption, provides for new protections for oak trees, prevents larger (older) trees from being removed for temporary road construction, and imposes new treatment standards for slash and woody debris within close proximity to public roads and critical infrastructure.
Analysis Prepared by: Nikita Koraddi / APPR. / (916) 319-2081
Date of Hearing: April 22, 2024
ASSEMBLY COMMITTEE ON NATURAL RESOURCES
Isaac G. Bryan, Chair
ABPCA Bill Id:AB 2276 (
Author:Wood) – As Amended Ver:April 17, 2024
SUBJECT: Forestry: timber harvesting plans: exemptions.
SUMMARY: Makes various changes to the Forest Practices Act to consolidate and update exemptions, and extends specified exemption sunset dates.
EXISTING LAW, pursuant to the Z’berg-Nejedly Forest Practice Act (Act) of 1973 (Public Resources Code 4511-4630.2):
- Prohibits a person from conducting timber operations unless a timber harvesting plan (THP) prepared by a registered professional forester (RPF) has been submitted to, and approved by, the Department of Forestry and Fire Protection (CAL FIRE).
- Authorizes the State Board of Forestry and Fire Protection (Board) to exempt from some or all of those provisions of the Act a person engaging in specified forest management activities, including, among others:
- For a period of 5 years following the adoption of emergency regulations, the cutting or removal of trees on the person’s property that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break, known as the Small Timberland Owner Exemption.
- Until January 1, 2026, the harvesting of those trees that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for specified purposes, known as the Forest Fire Prevention Exemption (FPPE).
THIS BILL:
- Deletes the Small Timberland Owner Exemption from the Act and its associated conditions.
- Renames the FFPE the Forest Resilience Exemption and consolidates the new exemption with conditions from the Small Timberland Owner Exemption as follows:
- Requires the responsible RPF to identify the designated postharvest stocking within the notice of exemption. Requires the selected stocking to be applicable to, and consistent with, silviculture that would apply to the preharvest stand condition.
- Requires additional information on preharvest stand conditions.
- Requires, within the northern and southern districts, if the preharvest dominant and codominant crown canopy is occupied by trees less than 14 inches in diameter at breast height, a minimum of 65 trees greater than 4 inches in diameter at breast height shall be retained.
- Authorizes the Board to adopt specific regulations for the removal of dead and dying trees in amounts less than 10% of the average volume per acre for trees up to 36 inches in diameter at breast height. Requires the Board to consider specified factors if adopting regulations.
- Requires all harvested trees to be marked by am RPF before felling.
- Prohibits the six largest trees per acre within the boundaries of a notice of exemption from being harvested.
- Prohibits any oak tree that is greater than 22 inches in diameter at breast height from being harvested under a notice of exemption, unless for safety.
- Authorizes the Board to adopt regulations pertaining to canopy closure if determined appropriate and necessary.
- Provides that slash and woody debris within 50 feet of a public road or critical infrastructure, as defined by the Board, shall be chipped, burned, or removed.
- Deletes, under the exemption for the cutting or removal of trees to restore and conserve California black or Oregon white oak woodlands and associated grasslands, the requirement for the Board to adopt regulations.
- Establishes a sunset date of January 1, 2031 for the newly developed Forest Resiliency Exemption and extends the sunset for an existing structure protection exemption under the Act from January 1, 2026, to January 1, 2031.
- Makes technical, nonsubstantive changes.
FISCAL EFFECT: Unknown
COMMENTS:
- Author’s statement:
The wildfire hazard in California has grown exponentially over the past decade. In an effort to mitigate this hazard, the state has set a goal of treating 500,000 acres of state land a year by increasing the pace and scale of forest management, among other tools. AB 2276 will contribute to California’s goal by extending and increasing the utility of timber harvest plan exemptions, making it more economically feasible to complete wildfire mitigation projects that provide for healthier and more resilient forests. With the budget challenges facing the state, it is important that we implement smart solutions that take advantage of existing partnerships and shared goals of private landowners, forest managers, environmental stewards, and state agencies.
- Forest Management. Past logging and decades of fire suppression have left unnaturally dense forests that lack the large, old, fire-resilient trees that once characterized the forests of the Sierra, Cascade, and North Coast. Those historic forests were shaped by frequent fires, both from lightning and Indigenous burning, that helped maintain the open characteristics where John Muir described being able to ride a horse through the forest without a branch knocking off his hat. Dense, young forests now extend mile after mile, providing the continuous fuel for large-scale fires burning with extremely damaging outcomes. Forest health is critical to managing wildfire prevention.
- THPs. Timber harvesting operations on private lands in California must file THPs, which detail how timber operations (e.g., felling and harvest of trees, related road construction and maintenance, and preparing ground for planting of seedlings) are to occur. THPs are rich in detail and nuance, and have long-standing requirements for forest management.
According to Pacific Forest Trust, to create more fire-resilient forests, the state needs to focus on reducing density by removing small trees and surface fuels, while retaining the largest trees. This presents a challenge for the traditional THP permit because it typically costs tens of thousands of dollars, and landowners need to recoup that cost by cutting down the large, valuable trees. There needs to be a more cost-effective way to do ecological thinning where we can retain the largest, most important trees.
- THP exemptions. SB 901 (Dodd), Chapter 626, Statutes of 2018, intended to addresses numerous issues concerning wildfire prevention, response and recovery, including funding for mutual aid, fuel reduction and forestry policies, wildfire mitigation plans by electric utilities, and cost recovery by electric corporations of wildfire-related damages.
Among its provisions, the bill divided new timber harvest exemptions into two landownership categories: 1) small private landowners with of 60-acres or less within a single planning watershed along coastal forests and 100-acres or less within a single planning watershed inland, and 2) landowners with up to 300 acres within moderate, high, or very high severity fire zones. The intent with these exemptions was to provide regulatory relief to conduct fuel treatments on private forestlands by focusing the removal on small and mid-sized trees that are currently over-stocked.
Both of the exemptions were set to sunset in five years in order to provide the Legislature an opportunity to evaluate and assess their effectiveness.
- Small Timberland Owner Exemption. This exemption allows a person to engage in specified forest management activities without a THP, including the cutting or removal of trees on the person’s property that eliminates the vertical continuity of vegetative fuels and the horizontal continuity of tree crowns for the purpose of reducing flammable materials and maintaining a fuel break. The exemption is applicable to small forestland owners within the northern forest district or the southern forest district who own 100 acres or less of timberland within a single planning watershed. Property owners can use the exemption only once per any given acre within a 10-year period, and landowners are limited to 3 exemptions under the Act.
According to the Board’s 2021 Annual Report, in 2020/21, there were only 8 notices of exemption for a total of 165 acres. In fact, since its inception in 2019, the notification of exemption has only been used 19 times, treating only 481 acres over 5 years.
- Forest Fire Prevention Exemption. SB 901 created the FFPE to allow two miles of temporary roads on slopes up to 30% per ownership in a single planning watershed for any five-year period, and sunset the exemption five years after the effective date of emergency regulations.
Established in 2004 [AB 2420 (La Malfa) Chapter 713, Statutes of 2004], the FFPE provides limited exemptions from the THP process for projects aimed at reducing the risk of catastrophic wildfires. SB 901 made amendments that resulted in some increased utility of this exemption, with approximately 6,000 acres treated over the course of the last five years. While any increase in the number of acres treated helps reduce wildfire risk, the work done each year under the FFPE contributes a small fraction to the state’s share of the cooperative federal and state million-acre treatment strategy and pales in comparison to recent catastrophic wildfires which have burned more than 4 million acres over the past several years.
According to CAL FIRE, since the SB 901-revised FFPE became effective in February 2019, RFPs have submitted 186 notices of exemption. Based on the acreage provided in the notices of exemption, the use of this exemption since 2019 would have treated (or will treat) 15,867 acres. According to the Board, the average exemption project is about 95 acres, with projects ranging in size from two acres to 299 acres, distributed throughout the Coast, Cascade, Sierra, and Southern Areas.
Since the FFPE was adopted, it has been implemented most in the Coast and Cascade areas, with 46% submitted on the Coast, and 47% in the Cascades (5% in the Sierras and 2% in the Southern Area). The exemption is effective for one year, which limits the feasibility of harvesting more than 300 acres under a single permit within the year, then treating (burning) the significant amount of slash within the allowed additional year.
- This bill. To increase the utility of the new Forest Resiliency Exemption for private landowners and others, AB 2276 increases the maximum project size to 500 acres, revises maximum allowable diameter of trees that can be removed to allow field professionals to make more accurate determinations on tree size in the field, updates the stocking standards to better reflect geographic diversity, and allows the Board to determine necessary canopy closure metrics through rulemaking.
To balance the expanded exemption with environmental protections, the bill also requires, under the Forest Resiliency Exemption, retention of the six largest trees on each acre treated under the exemption, provides for new protections for oak trees, prevents larger (older) trees from being removed for temporary road construction, and imposes new treatment standards for slash and woody debris within close proximity to public roads and critical infrastructure.
REGISTERED SUPPORT / OPPOSITION:
Support
American Forest Foundation
Auten Resource Consulting
California Forestry Association
California Licensed Foresters Association
California Native Plant Society
California State Association of Counties
California Wilderness Coalition
Central Sierra Environmental Resource Center
Defenders of Wildlife
Environmental Defense Fund
Forest Landowners of California
Humboldt County Prescribed Burn Association
Humboldt Redwood Company LLC
Mattole Restoration Council
Northcoast Regional Land Trust
Pacific Forest Trust
Rural County Representatives of California
Sierra Business Council
Sierra Cascade Logging Conference
Sierra Forest Legacy
Sierra Institute for Community and Environment
The Buckeye Conservancy
The Fire Restoration Group
University of California Cooperative Extension - Humboldt and Del Norte Counties
Opposition
None on file
Analysis Prepared by: Paige Brokaw / NAT. RES. /
Discussed in Hearing
View Older HearingsBill Author
Bill Co-Author(s):