AB 2779: Independent System Operator: transmission planning.
- Session Year: 2023-2024
- House: Assembly
- Latest Version Date: 2024-09-27
Current Status:
Passed
(2024-09-27: Chaptered by Secretary of State - Chapter 741, Statutes of 2024.)
Introduced
In Committee
First Chamber
In Committee
Second Chamber
Enacted
Existing law establishes the Independent System Operator as a nonprofit, public benefit corporation to manage the transmission grid and related energy markets, as provided.
This bill would require the Independent System Operator, upon approval of each transmission plan, to report to the Public Utilities Commission and to the relevant policy committees of each house of the Legislature any new use of any grid enhancing technology that is deemed reasonable by the Independent System Operator in that plan and the cost and efficiency savings of the deployment of that grid enhancing technology.
Existing law establishes the Independent System Operator as a nonprofit, public benefit corporation to manage the transmission grid and related energy markets, as provided.
This bill would require the Independent System Operator, upon approval of each transmission plan, to report to the Public Utilities Commission and to the relevant policy committees of each house of the Legislature any new use of any grid enhancing technology that is deemed reasonable by the Independent System Operator in that plan and the cost and efficiency savings of the deployment of that grid enhancing technology.
Existing law establishes the Independent System operator as a nonprofit, public benefit corporation to manage the transmission grid and related energy markets, as provided.
This bill would require the Independent System Operator, upon approval of each transmission plan, to report to the Public Utilities Commission and to the relevant policy committees of each house of the Legislature any new use of any grid enhancing technology that is deemed reasonable by the Independent System Operator in that plan and the cost or and efficiency savings of the deployment of that grid enhancing technology.
Existing law establishes the Independent System operator as a nonprofit, public benefit corporation to manage the transmission grid and related energy markets, as provided.
This bill would require the Independent System Operator, upon approval of each transmission plan, to report to the Public Utilities Commission and to the relevant policy committees of each house of the Legislature any new use of any grid enhancing technology that is deemed reasonable by the Independent System Operator in that plan and the cost or efficiency savings of the deployment of that grid enhancing technology.
Existing law requires the Public Utilities Commission to adopt a process for each load-serving entity to file an integrated resource plan and a schedule for periodic updates to the plan to ensure that it meets, among other things, the states targets for reducing emissions of greenhouse gases and the requirement to procure at least 60% of its electricity from eligible renewable energy resources by December 31, 2030. In furtherance of these requirements, existing law requires the commission to consider the role of existing renewable generation, grid operational efficiencies, energy storage, and distributed energy resources, including energy efficiency, in helping to ensure each load-serving entity meets energy needs and reliability needs in hours to encompass the hour of peak demand of electricity, as specified.This bill would make a nonsubstantive change to the latter requirement.Existing law requires the Public Utilities Commission to adopt a process for each load-serving entity to file an integrated resource plan and a schedule for periodic updates to the plan to ensure that it meets, among other things, the states targets for reducing emissions of greenhouse gases and the requirement to procure at least 60% of its electricity from eligible renewable energy resources by December 31, 2030. In furtherance of these requirements, existing law requires the commission to consider the role of existing renewable generation, grid operational efficiencies, energy storage, and distributed energy resources, including energy efficiency, in helping to ensure each load-serving entity meets energy needs and reliability needs in hours to encompass the hour of peak demand of electricity, as specified.
This bill would make a nonsubstantive change to the latter requirement.
(a)Notwithstanding Section 10231.5 of the Government Code, upon approval by the Independent System Operator of each transmission plan produced through the transmission planning process, or a successor process, the Independent System Operator shall report to the commission and the relevant policy committees of both houses of the Legislature any new use of any grid enhancing technology that is deemed reasonable by the Independent System Operator in that plan and the costs and efficiency savings of the deployment of that grid enhancing technology.
(b)The report submitted to the relevant policy committees of the Legislature pursuant to subdivision (a) shall be submitted in accordance with Section 9795 of the Government Code.
(a)Notwithstanding Section 10231.5 of the Government Code, upon approval by the Independent System Operator of each transmission plan produced through the transmission planning process, or a successor process, the Independent System Operator shall report to the commission and the relevant policy committees of both houses of the Legislature any new use of any grid enhancing technology that is deemed reasonable by the Independent System Operator in that plan and the costs and efficiency savings of the deployment of that grid enhancing technology.
(b)The report submitted to the relevant policy committees of the Legislature pursuant to subdivision (a) shall be submitted in accordance with Section 9795 of the Government Code.
(a)Notwithstanding Section 10231.5 of the Government Code, upon approval by the Independent System Operator of each transmission plan produced through the transmission planning process, or a successor process, the Independent System Operator shall report to the commission and the relevant policy committees of both houses of the Legislature any new use of any grid enhancing technology that is deemed reasonable by the Independent System Operator in that plan and the costs or and efficiency savings of the deployment of that grid enhancing technology.
(b)The report submitted to the relevant policy committees of the Legislature pursuant to subdivision (a) shall be submitted in accordance with Section 9795 of the Government Code.
(a)Notwithstanding Section 10231.5 of the Government Code, upon approval by the Independent System Operator of each transmission plan produced through the transmission planning process, or a successor process, the Independent System Operator shall report to the commission and the relevant policy committees of both houses of the Legislature any new use of any grid enhancing technology that is deemed reasonable by the Independent System Operator in that plan and the costs or efficiency savings of the deployment of that grid enhancing technology.
(b)The report submitted to the relevant policy committees of the Legislature pursuant to subdivision (a) shall be submitted in accordance with Section 9795 of the Government Code.
SECTION 1.Section 454.52 of the Public Utilities Code is amended to read:454.52.(a)(1)Beginning in 2017, and to be updated regularly thereafter, the commission shall adopt a process for each load-serving entity to file an integrated resource plan, and a schedule for periodic updates to the plan, and shall ensure that load-serving entities do all of the following:(A)Meet the greenhouse gas emissions reduction targets established by the State Air Resources Board, in coordination with the commission and the Energy Commission, for the electricity sector and each load-serving entity that reflect the electricity sectors percentage in achieving the economywide greenhouse gas emissions reductions pursuant to Section 38566 of the Health and Safety Code.(B)Procure at least 60 percent eligible renewable energy resources by December 31, 2030, consistent with the state policy specified in Section 454.53 and Article 16 (commencing with Section 399.11) of Chapter 2.3.(C)Enable each electrical corporation to fulfill its obligation to serve its customers at just and reasonable rates.(D)Minimize impacts on ratepayers bills.(E)Ensure system and local reliability on a near-term, mid-term, and long-term basis, including meeting the near-term and forecast long-term resource adequacy requirements of Section 380, and require sufficient, predictable resource procurement and development to avoid unplanned energy supply shortfalls by taking into account impacts due to climate change, forecasted levels of building and transportation electrification, and other factors that can result in those shortfalls.(F)Comply with paragraph (1) of subdivision (b) of Section 399.13.(G)Strengthen the diversity, sustainability, and resilience of the bulk transmission and distribution systems, and local communities.(H)Enhance distribution systems and demand-side energy management.(I)Minimize localized air pollutants and other greenhouse gas emissions, with early priority on disadvantaged communities identified pursuant to Section 39711 of the Health and Safety Code.(J)Maintain a diverse portfolio of energy resources, which may include eligible energy resources procured by the Department of Water Resources.(2)(A)The commission may authorize all source procurement for load-serving entities that includes various resource types including demand-side resources, supply-side resources, and resources that may be either demand-side resources or supply-side resources, taking into account the differing load-serving entities geographic service areas, to ensure that each load-serving entity meets the goals set forth in paragraph (1).(B)The commission may approve procurement of resource types that will reduce the overall emissions of greenhouse gases from the electricity sector and meet the other goals specified in paragraph (1), but due to the nature of the technology or fuel source may not compete favorably in price against other resources over the time period of the integrated resource plan.(3)In furtherance of the requirements of paragraph (1), the commission shall consider the role of existing renewable generation, grid operational efficiencies, energy storage, and distributed energy resources, including energy efficiency, in helping to ensure each load-serving entity meets energy needs and reliability needs in hours to encompass the hour of peak demand of electricity, excluding demand met by variable renewable generation directly connected to a California balancing authority, as defined in subdivision (d) of Section 399.12, while reducing the need for new electricity generation resources and new transmission resources in achieving the states energy goals at the least cost to ratepayers.(4)(A)On or before September 1, 2024, and consistent with the process and schedule adopted pursuant to paragraph (1), the commission, in consultation with the Energy Commission and the Independent System Operator, shall determine if there is a need for the procurement of eligible energy resources based on a review of the integrated resource plans submitted by load-serving entities in compliance with the requirements of this section and Section 454.53 and the progress towards meeting the portfolio of resources identified pursuant to subdivision (a) of Section 454.51.(B)If the commission determines that there is a need for the procurement of eligible energy resources, the commission shall specify the eligible energy resources that should be procured to meet that need.(C)Within six months of determining that there is a need for the procurement of eligible energy resources, the commission may request the Department of Water Resources to exercise its central procurement function to procure those eligible energy resources specified pursuant to subparagraph (B) that meet the portfolio of resources identified in subdivision (a) of Section 454.51.(D)(i)Upon receiving a request pursuant to subparagraph (C), the Department of Water Resources, before January 1, 2035, may exercise its central procurement function to conduct one or more competitive solicitations and enter into contracts to procure eligible energy resources in order to achieve the policy of the state specified in Section 454.53.(ii)Any contract entered into by the Department of Water Resources pursuant to clause (i) and approved by the commission pursuant to Section 80821 of the Water Code before January 1, 2035, shall remain in force for the duration of the contract.(E)The Department of Water Resources exercising of its central procurement function to procure eligible energy resources pursuant to this paragraph shall be conducted in accordance with Division 29.5 (commencing with Section 80800) of the Water Code.(b)(1)Each load-serving entity shall prepare and file an integrated resource plan consistent with paragraph (2) of subdivision (a) on a time schedule directed by the commission and subject to commission review.(2)Each electrical corporations plan shall follow Section 454.5.(3)The plan of a community choice aggregator shall be submitted to its governing board for approval and provided to the commission for certification, consistent with paragraph (5) of subdivision (a) of Section 366.2, and shall achieve all of the following:(A)Economic, reliability, environmental, security, and other benefits and performance characteristics that are consistent with the goals set forth in paragraph (1) of subdivision (a).(B)A diversified procurement portfolio consisting of short-term and long-term electricity, electricity-related, and demand reduction products.(C)The resource adequacy requirements established pursuant to Section 380.(4)The plan of an electric service provider shall achieve the goals set forth in paragraph (1) of subdivision (a) through a diversified portfolio consisting of short-term and long-term electricity, electricity-related, and demand reduction products.(c)To the extent that additional procurement is authorized for the electrical corporation in the integrated resource plan or the procurement process authorized pursuant to Section 454.5, the commission shall ensure that the costs are allocated in a fair and equitable manner to all customers consistent with Section 454.51, that there is no cost shifting among customers of load-serving entities, and that community choice aggregators may self-provide renewable integration resources consistent with Section 454.51. The commission may order the procurement of resources with specific attributes by load-serving entities as a result of the integrated resource planning process and shall enforce any resource procurement requirements on a nondiscriminatory basis. Enforcement may include the assessment of penalties for noncompliance.(d)To eliminate redundancy and increase efficiency, the process adopted pursuant to subdivision (a) shall incorporate, and not duplicate, any other planning processes of the commission.(e)This section applies to an electrical cooperative, as defined in Section 2776, only if the electrical cooperative has an annual electrical demand exceeding 700 gigawatthours, as determined based on a three-year average commencing with January 1, 2013.(f)(1)The commission shall not include the energy, capacity, or any attribute from Diablo Canyon Unit 1 beyond November 1, 2024, or Unit 2 beyond August 26, 2025, in the adopted integrated resource plan portfolios, resource stacks, or preferred system plans.(2)The commission shall disallow a load-serving entity from including in their adopted integrated resource plan any energy, capacity, or any attribute from the Diablo Canyon Unit 1 beyond November 1, 2024, or Unit 2 beyond August 26, 2025.(g)For a thermal powerplant that uses nuclear fission technology not constructed in the twenty-first century, all resource attributes shall be retired on January 1, 2031, and shall be reported as a separate, line item resource for purposes of complying with Section 398.4.(h)(1)Only a new energy resource that meets all of the following requirements is eligible to be procured by the Department of Water Resources pursuant to this section:(A)The resource directly supports attainment of the goals specified in Section 454.53 without increasing the states dependence on any fossil fuel-based resources.(B)The resource is determined by the commission to not be under contract at sufficient levels as shown in load-serving entities most recent individual integrated resource plans submitted to and reviewed by the commission pursuant to this section to achieve the goals specified in Section 454.53.(C)The resource has a construction and development lead time of at least five years.(D)The resource does not generate electricity using fossil fuels or fuels derived from fossil fuels.(E)The resource does not use combustion to generate electricity, unless that combustion use is ancillary and necessary to facilitate geothermal electricity generation.(2)Resources from a pump hydroelectric facility may be procured by the Department of Water Resources pursuant to this section if the pump hydroelectric facility does not exceed 500 megawatts and has been directly appropriated funding by the state before January 1, 2023.(i)For purposes of this section, load-serving entity has the same meaning as defined in Section 380.(a)(1)Beginning in 2017, and to be updated regularly thereafter, the commission shall adopt a process for each load-serving entity to file an integrated resource plan, and a schedule for periodic updates to the plan, and shall ensure that load-serving entities do all of the following:
(A)Meet the greenhouse gas emissions reduction targets established by the State Air Resources Board, in coordination with the commission and the Energy Commission, for the electricity sector and each load-serving entity that reflect the electricity sectors percentage in achieving the economywide greenhouse gas emissions reductions pursuant to Section 38566 of the Health and Safety Code.
(B)Procure at least 60 percent eligible renewable energy resources by December 31, 2030, consistent with the state policy specified in Section 454.53 and Article 16 (commencing with Section 399.11) of Chapter 2.3.
(C)Enable each electrical corporation to fulfill its obligation to serve its customers at just and reasonable rates.
(D)Minimize impacts on ratepayers bills.
(E)Ensure system and local reliability on a near-term, mid-term, and long-term basis, including meeting the near-term and forecast long-term resource adequacy requirements of Section 380, and require sufficient, predictable resource procurement and development to avoid unplanned energy supply shortfalls by taking into account impacts due to climate change, forecasted levels of building and transportation electrification, and other factors that can result in those shortfalls.
(F)Comply with paragraph (1) of subdivision (b) of Section 399.13.
(G)Strengthen the diversity, sustainability, and resilience of the bulk transmission and distribution systems, and local communities.
(H)Enhance distribution systems and demand-side energy management.
(I)Minimize localized air pollutants and other greenhouse gas emissions, with early priority on disadvantaged communities identified pursuant to Section 39711 of the Health and Safety Code.
(J)Maintain a diverse portfolio of energy resources, which may include eligible energy resources procured by the Department of Water Resources.
(2)(A)The commission may authorize all source procurement for load-serving entities that includes various resource types including demand-side resources, supply-side resources, and resources that may be either demand-side resources or supply-side resources, taking into account the differing load-serving entities geographic service areas, to ensure that each load-serving entity meets the goals set forth in paragraph (1).
(B)The commission may approve procurement of resource types that will reduce the overall emissions of greenhouse gases from the electricity sector and meet the other goals specified in paragraph (1), but due to the nature of the technology or fuel source may not compete favorably in price against other resources over the time period of the integrated resource plan.
(3)In furtherance of the requirements of paragraph (1), the commission shall consider the role of existing renewable generation, grid operational efficiencies, energy storage, and distributed energy resources, including energy efficiency, in helping to ensure each load-serving entity meets energy needs and reliability needs in hours to encompass the hour of peak demand of electricity, excluding demand met by variable renewable generation directly connected to a California balancing authority, as defined in subdivision (d) of Section 399.12, while reducing the need for new electricity generation resources and new transmission resources in achieving the states energy goals at the least cost to ratepayers.
(4)(A)On or before September 1, 2024, and consistent with the process and schedule adopted pursuant to paragraph (1), the commission, in consultation with the Energy Commission and the Independent System Operator, shall determine if there is a need for the procurement of eligible energy resources based on a review of the integrated resource plans submitted by load-serving entities in compliance with the requirements of this section and Section 454.53 and the progress towards meeting the portfolio of resources identified pursuant to subdivision (a) of Section 454.51.
(B)If the commission determines that there is a need for the procurement of eligible energy resources, the commission shall specify the eligible energy resources that should be procured to meet that need.
(C)Within six months of determining that there is a need for the procurement of eligible energy resources, the commission may request the Department of Water Resources to exercise its central procurement function to procure those eligible energy resources specified pursuant to subparagraph (B) that meet the portfolio of resources identified in subdivision (a) of Section 454.51.
(D)(i)Upon receiving a request pursuant to subparagraph (C), the Department of Water Resources, before January 1, 2035, may exercise its central procurement function to conduct one or more competitive solicitations and enter into contracts to procure eligible energy resources in order to achieve the policy of the state specified in Section 454.53.
(ii)Any contract entered into by the Department of Water Resources pursuant to clause (i) and approved by the commission pursuant to Section 80821 of the Water Code before January 1, 2035, shall remain in force for the duration of the contract.
(E)The Department of Water Resources exercising of its central procurement function to procure eligible energy resources pursuant to this paragraph shall be conducted in accordance with Division 29.5 (commencing with Section 80800) of the Water Code.
(b)(1)Each load-serving entity shall prepare and file an integrated resource plan consistent with paragraph (2) of subdivision (a) on a time schedule directed by the commission and subject to commission review.
(2)Each electrical corporations plan shall follow Section 454.5.
(3)The plan of a community choice aggregator shall be submitted to its governing board for approval and provided to the commission for certification, consistent with paragraph (5) of subdivision (a) of Section 366.2, and shall achieve all of the following:
(A)Economic, reliability, environmental, security, and other benefits and performance characteristics that are consistent with the goals set forth in paragraph (1) of subdivision (a).
(B)A diversified procurement portfolio consisting of short-term and long-term electricity, electricity-related, and demand reduction products.
(C)The resource adequacy requirements established pursuant to Section 380.
(4)The plan of an electric service provider shall achieve the goals set forth in paragraph (1) of subdivision (a) through a diversified portfolio consisting of short-term and long-term electricity, electricity-related, and demand reduction products.
(c)To the extent that additional procurement is authorized for the electrical corporation in the integrated resource plan or the procurement process authorized pursuant to Section 454.5, the commission shall ensure that the costs are allocated in a fair and equitable manner to all customers consistent with Section 454.51, that there is no cost shifting among customers of load-serving entities, and that community choice aggregators may self-provide renewable integration resources consistent with Section 454.51. The commission may order the procurement of resources with specific attributes by load-serving entities as a result of the integrated resource planning process and shall enforce any resource procurement requirements on a nondiscriminatory basis. Enforcement may include the assessment of penalties for noncompliance.
(d)To eliminate redundancy and increase efficiency, the process adopted pursuant to subdivision (a) shall incorporate, and not duplicate, any other planning processes of the commission.
(e)This section applies to an electrical cooperative, as defined in Section 2776, only if the electrical cooperative has an annual electrical demand exceeding 700 gigawatthours, as determined based on a three-year average commencing with January 1, 2013.
(f)(1)The commission shall not include the energy, capacity, or any attribute from Diablo Canyon Unit 1 beyond November 1, 2024, or Unit 2 beyond August 26, 2025, in the adopted integrated resource plan portfolios, resource stacks, or preferred system plans.
(2)The commission shall disallow a load-serving entity from including in their adopted integrated resource plan any energy, capacity, or any attribute from the Diablo Canyon Unit 1 beyond November 1, 2024, or Unit 2 beyond August 26, 2025.
(g)For a thermal powerplant that uses nuclear fission technology not constructed in the twenty-first century, all resource attributes shall be retired on January 1, 2031, and shall be reported as a separate, line item resource for purposes of complying with Section 398.4.
(h)(1)Only a new energy resource that meets all of the following requirements is eligible to be procured by the Department of Water Resources pursuant to this section:
(A)The resource directly supports attainment of the goals specified in Section 454.53 without increasing the states dependence on any fossil fuel-based resources.
(B)The resource is determined by the commission to not be under contract at sufficient levels as shown in load-serving entities most recent individual integrated resource plans submitted to and reviewed by the commission pursuant to this section to achieve the goals specified in Section 454.53.
(C)The resource has a construction and development lead time of at least five years.
(D)The resource does not generate electricity using fossil fuels or fuels derived from fossil fuels.
(E)The resource does not use combustion to generate electricity, unless that combustion use is ancillary and necessary to facilitate geothermal electricity generation.
(2)Resources from a pump hydroelectric facility may be procured by the Department of Water Resources pursuant to this section if the pump hydroelectric facility does not exceed 500 megawatts and has been directly appropriated funding by the state before January 1, 2023.
(i)For purposes of this section, load-serving entity has the same meaning as defined in Section 380.
|
Date
|
Status
|
|---|---|
| Sep 27, 2024 | Chaptered by Secretary of State - Chapter 741, Statutes of 2024. |
| Sep 27, 2024 | Approved by the Governor. |
| Sep 11, 2024 | Enrolled and presented to the Governor at 4 p.m. |
| Aug 29, 2024 | Senate amendments concurred in. To Engrossing and Enrolling. (Ayes 76. Noes 0.). |
| Aug 28, 2024 | Assembly Rule 77 suspended. |
| Aug 28, 2024 | In Assembly. Concurrence in Senate amendments pending. May be considered on or after August 30 pursuant to Assembly Rule 77. |
| Aug 27, 2024 | Read third time. Passed. Ordered to the Assembly. (Ayes 38. Noes 0.). |
| Jun 18, 2024 | Read second time. Ordered to third reading. |
| Jun 17, 2024 | From committee: Be ordered to second reading pursuant to Senate Rule 28.8. |
| Jun 10, 2024 | Read second time and amended. Re-referred to Com. on APPR. |
| Jun 6, 2024 | From committee: Amend, and do pass as amended and re-refer to Com. on APPR. (Ayes 17. Noes 0.) (June 4). |
| May 22, 2024 | Referred to Com. on E., U. & C. |
| May 9, 2024 | In Senate. Read first time. To Com. on RLS. for assignment. |
| May 9, 2024 | Read third time. Passed. Ordered to the Senate. (Ayes 65. Noes 0. Page 5161.) |
| May 2, 2024 | Read second time. Ordered to Consent Calendar. |
| May 1, 2024 | From committee: Do pass. To Consent Calendar. (Ayes 14. Noes 0.) (May 1). |
| Apr 18, 2024 | From committee: Do pass and re-refer to Com. on APPR. with recommendation: To Consent Calendar. (Ayes 16. Noes 0.) (April 17). Re-referred to Com. on APPR. |
| Apr 1, 2024 | Re-referred to Com. on U. & E. |
| Mar 21, 2024 | From committee chair, with author's amendments: Amend, and re-refer to Com. on U. & E. Read second time and amended. |
| Mar 21, 2024 | Referred to Com. on U. & E. |
| Feb 16, 2024 | From printer. May be heard in committee March 17. |
| Feb 15, 2024 | Read first time. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Aug 29, 2024 | AB 2779 Petrie-Norris Concurrence in Senate Amendments | Assembly Floor |
Passed |
|
| Aug 27, 2024 | Assembly 3rd Reading AB2779 Petrie-Norris By Padilla | Senate Floor |
Passed |
|
| Jun 4, 2024 | Do pass as amended, but first amend, and re-refer to the Committee on [Appropriations] | Senate Standing Committee on Energy, Utilities and Communications |
Passed |
|
| May 9, 2024 | AB 2779 Petrie-Norris Consent Calendar Second Day Regular Session | Assembly Floor |
Passed |
|
| May 1, 2024 | Do pass. To Consent Calendar. | Assembly Standing Committee on Appropriations |
Passed |
|
| Apr 17, 2024 | Do pass and be re-referred to the Committee on [Appropriations] with recommendation: To Consent Calendar | Assembly Standing Committee on Utilities and Energy |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| Advanced Energy Economy | ** Support | |
| California Farm Bureau Federation | ** Support | |
| California State Association Of Electrical Workers | ** Support | |
| Coalition of California Utility Employees | ** Support | |
| Environment California | ** Support |
CONCURRENCE IN SENATE AMENDMENTS
CSA1 Bill Id:AB 2779
Author:(Petrie-Norris)
As Amended Ver:June 10, 2024
Majority vote
SUMMARY
Requires the California Independent System Operator (CAISO) to report to the California Public Utilities Commission (CPUC) and to relevant policy committees in the Legislature any new use of any grid-enhancing technology (GET) and its associated cost and efficiency savings.
Senate Amendments
Requires CAISO to report both the efficiency and cost savings, rather than one or the other, of the use of GETs.
COMMENTS
California has ambitious clean energy goals: 100% renewable and zero-carbon energy-producing resources by December 31, 2045. Consequently, electricity demand in California is expected to nearly double by 2040, requiring heavy investment in the state's power grid to meet its net zero goals.
In order for the state to meet its clean energy goals, electric transmission capacity will likely need to grow significantly. The CAISO conducts its annual TPP to identify potential transmission system limitations and opportunities for system reinforcements that improve reliability and efficiency. The CAISO identifies projects that address grid reliability requirements, identify upgrades needed to successfully meet California's policy goals, and explore projects that can bring economic benefits to consumers.
To facilitate the clean energy transition, GETs have been posed by researchers and industry leaders as an interim, cost-effective solution to unlock transmission capacity in the near term and buy time for long-term transmission planning. GETs encompass a suite of technologies – such as advanced conductors, dynamic line ratings, and analytical tools – that can be used to maximize the transmission of electricity across existing lines. According to the Federal Energy Regulatory Commission (FERC), GETs can cost less than 10% of the cost of investing in new transmission lines, and can save millions in annual congestion costs.
Though supporters of GETs are concerned that the technologies have yet to be widely adopted in California and the U.S., the CAISO has considered GETs as potential alternatives in the TPP for many years. They note particular success in selecting flow controllers in a number of cases in past plans and approving for the first time a project employing advanced conductors in the 2022-23 TPP; in the 2023-24 TPP, CAISO recommended GETs to increase resiliency in the Humboldt area.
This bill proposes CAISO to report any GETs it selects in its TPP, in line with their ongoing review of this technology to date. Such reporting will provide transparency and reassurance that the state is actively considering short-term and cost-effective solutions to ensure grid resiliency, resource adequacy, and clean power generation.
According to the Author
"Given the urgency for the state to meet its clean energy goals, a shorter-term solution is needed to maximize transmission capacity. Grid-enhancing technologies (GETs) encompass a suite of technologies that increase the capacity and efficiency of the existing transmission system. Given that GETs can be deployed faster than building new transmission infrastructure, they allow California to better utilize its existing infrastructure and provide short-term solutions to temporary operational challenges, such as during outages or when new lines are under construction. GETs may also serve an important role of bridging a gap until a permanent transmission expansion is completed. [This bill] will provide transparency on the frequency and best use of GETs under consideration in the CAISO TPP, by having the CAISO report on their usage."
Arguments in Support
The Coalition of California Utility Employees and the California State Association of Electrical Workers write in support, "GETs are used widely in Europe and have been used to a limited extent in California and other states, but there is much untapped potential. This bill would establish a reporting process so that the CPUC and the Legislature can monitor the extent to which the CAISO is utilizing cost-effective GETs in its transmission planning process. Deploying cost-effective GETs is a no-regrets policy which could yield lower costs for consumers while increasing California's ability to meet its carbon reduction goals."
Arguments in Opposition
None on file.
FISCAL COMMENTS
According to the Assembly Committee on Appropriations, costs of this bill to the state are minor since CAISO is funded by charges on electricity transmission, not from state funds.
VOTES:
ASM UTILITIES AND ENERGY: 16-0-0
YES: Petrie-Norris, Jim Patterson, Bauer-Kahan, Calderon, Chen, Connolly, Friedman, Holden, Joe Patterson, Reyes, Santiago, Schiavo, Ting, Wallis, Wood, Zbur
ASM APPROPRIATIONS: 14-0-1
YES: Wicks, Sanchez, Arambula, Bryan, Calderon, Wendy Carrillo, Dixon, Mike Fong, Grayson, Haney, Hart, Pellerin, Ta, Villapudua
ABS, ABST OR NV: Jim Patterson
ASSEMBLY FLOOR: 65-0-15
YES: Addis, Aguiar-Curry, Alanis, Alvarez, Arambula, Bauer-Kahan, Bennett, Berman, Boerner, Bonta, Bryan, Calderon, Juan Carrillo, Wendy Carrillo, Chen, Connolly, Davies, Dixon, Essayli, Mike Fong, Vince Fong, Friedman, Gallagher, Garcia, Gipson, Hart, Holden, Hoover, Irwin, Jackson, Jones-Sawyer, Kalra, Lackey, Lee, Lowenthal, Maienschein, McCarty, McKinnor, Muratsuchi, Ortega, Pacheco, Papan, Jim Patterson, Joe Patterson, Pellerin, Quirk-Silva, Ramos, Rendon, Reyes, Rodriguez, Blanca Rubio, Sanchez, Santiago, Soria, Ta, Valencia, Villapudua, Waldron, Ward, Weber, Wicks, Wilson, Wood, Zbur, Robert Rivas
ABS, ABST OR NV: Bains, Cervantes, Megan Dahle, Flora, Gabriel, Grayson, Haney, Low, Mathis, Stephanie Nguyen, Petrie-Norris, Luz Rivas, Schiavo, Ting, Wallis
SENATE FLOOR: 38-0-2
YES: Allen, Alvarado-Gil, Archuleta, Ashby, Atkins, Becker, Blakespear, Bradford, Caballero, Cortese, Dodd, Durazo, Eggman, Glazer, Gonzalez, Grove, Hurtado, Jones, Laird, Limón, McGuire, Menjivar, Min, Newman, Niello, Ochoa Bogh, Padilla, Portantino, Roth, Rubio, Seyarto, Skinner, Smallwood-Cuevas, Stern, Umberg, Wahab, Wiener, Wilk
ABS, ABST OR NV: Dahle, Nguyen
UPDATED
VERSION: June 10, 2024
CONSULTANT: Kathleen Chen / U. & E. / (916) 319-2083 FN: 0004786
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | AB 2779 |
THIRD READING
Bill No: AB 2779
Author: Petrie-Norris (D)
Amended: 6/10/24 in Senate
Vote: 21
SENATE ENERGY, U. & C. COMMITTEE: 17-0, 6/4/24
AYES: Bradford, Dahle, Ashby, Becker, Caballero, Dodd, Durazo, Eggman, Gonzalez, Grove, Limón, Min, Newman, Rubio, Seyarto, Skinner, Stern
NO VOTE RECORDED: Wilk
SENATE APPROPRIATIONS COMMITTEE: Senate Rule 28.8
ASSEMBLY FLOOR: 65-0, 5/9/24 (Consent) - See last page for vote
SUBJECT: Independent System Operator: transmission planning
SOURCE: Author
DIGEST:
This bill requires the California Independent System Operator (CAISO), upon approval of the annual transmission plan, to report on any new use of any grid enhancing technology and its associated cost and efficiency savings.
ANALYSIS:
Existing law:
- Establishes that U.S. Federal Energy Regulatory Commission (FERC) has exclusive jurisdiction over the transmission of electric energy in interstate commerce. Also establishes the process and procedures for establishing transmission of electric energy in interstate commerce by public utilities, i.e., the rates, terms & conditions of interstate electric transmission by public utilities. (Federal Power Act §§§201, 205, 206 (16 USC 824, 824d, 824e))
- Establishes and vests the California Public Utilities Commission (CPUC) with regulatory authority over public utilities, including electrical corporations. (Article XII of the California Constitution)
- Establishes the CAISO as a nonprofit, public benefit corporation to manage the transmission grid and related energy markets, as provided. (Public Utilities Code §345 et seq.)
- Provides that the CPUC may supervise and regulate every public utility in the state and may do all things, whether specifically designated or in addition, which are necessary and convenient in the exercise of such power and jurisdiction. (Public Utilities Code §701)
- Prohibits an electrical corporation from beginning the construction of a line, plant, or system, or of any extension thereof, without having first obtained from the CPUC a certificate that the present or future public convenience and necessity require or will require its construction. Provides that the extension, expansion, upgrade, or other modification of an existing electrical transmission facility, including transmission lines and substations, does not require a certificate that the present or future public convenience and necessity requires or will require its construction. (Public Utilities Code §1001)
This bill:
- Requires the CAISO, upon approval of each transmission plan, to report to the CPUC and to the relevant policy committees of each house of the Legislature any new use of any grid enhancing technology that is deemed reasonable by the CAISO in that plan and the cost or efficiency savings of the deployment of that grid enhancing technology.
- Requires the report to be submitted in accordance with requirements on reports submitted by agencies, including to submit to the Secretary of the Senate, the Chief Clerk of the Assembly, and the Legislative Counsel, as prescribed.
- Provides that the requirement to provide the reports are not subject to a sunset.
Background
- Transmission projects. Electric transmission lines are generally high voltage lines that move electricity from generation resources (power plants) to distribution lines in neighborhoods. Companies, usually electric investor-owned utilities (IOUs), proposing the construction of new transmission, are required to obtain a permit from the CPUC for construction of specified infrastructure listed under Public Utilities Code §1001, including transmission projects. In the case of interstate transmission lines, FERC has exclusive jurisdiction as to the costs and rates approved for the use of these lines.
- Need for expanded transmission capacity. In order for the state to meet its clean energy goals, including achieving 100 percent clean energy by 2045, electric transmission capacity will likely need to grow significantly. The CAISO conducts its annual transmission planning process to identify potential transmission system limitations and opportunities for system reinforcements that improve reliability and efficiency. The CAISO identifies projects that address grid reliability requirements, identify upgrades needed to successfully meet California’s policy goals, and explore projects that can bring economic benefits to consumers. In 2021, the CAISO created a 20-Year Transmission Outlook for the electric grid, in collaboration with the CPUC and the California Energy Commission (CEC), with the goal of exploring the longer-term grid requirements and options for meeting the state’s SB 100 (De León, Chapter 312, Statutes of 2018) clean energy goals reliably and cost-effectively. The 20-Year Transmission Outlook estimates a significant amount, about $30 billion, to construct and expand transmission facilities. In subsequent transmission plans, the CAISO has approved over $16 billion worth of about 100 transmission projects. Transmission owners recover the costs of CAISO-approved projects through the Transmission Access Charge (TAC). The transmission owner submits an application to FERC to recover project costs. FERC approves just and reasonable costs and rate of return. CAISO charges transmission customers based on FERC-approved costs. These costs are collected from electric utility customers as part of the transmission and distribution portion of the electric utility bill.
- Grid-enhancing technologies (GETs). GETs, generally, are a combination of hardware and software that can increase transmission capacity, decrease congestion, and improve reliability on transmission lines. An April 2023 Brattle Group white paper, Building a Better Grid: How Grid-enhancing Technologies Complement Transmission Buildouts, discusses how GETs can help improve transmission capacity and efficiency. The paper notes that transmission transfer capability depends on where and how new transmission lines are connected to the rest of the electrical grid system – the topology of the transmission network (including the points of injection and withdrawal of energy). Both the transfer capability of lines (and other components of the grid) and network topology determine how, where, and the quantity of the power flows. Many GETs are built on either of two applications to increase transfer capability: one that explores enhanced and flexible application of the pre-determined transfer capability, and the other that focuses on flexible and dynamic control of transmission systems.
Examples of GETs include dynamic line ratings, advanced power flow controls, and advanced topology control. Dynamic line ratings (DLRs) try to better address individual line transfer capability based on actual conditions. Advanced power flow controls (generally hardware) and advanced topology control (generally software) direct electricity away from overloaded lines and onto underutilized lines, such as by opening or closing circuit breakers. As noted in the Brattle Group paper: The comparative advantages of GETs include their portability and scalability, speed to deploy, and lower costs. Importantly, per the report, “GETs rarely replace transmission, rather, they enhance transmission…”
- Advanced reconductoring. The CAISO also defines GETs to include advanced reconductoring which is the replacement of a transmission line’s existing conductors with advanced conductors, essentially swapping out the Aluminum Conductor Steel Reinforced (ACSR) for a smaller composite core conductors that enable higher operating temperatures. According to a November 2023 Energy Institute at Haas paper, “Accelerating Transmission Expansion by Using Advanced Conductors in Existing Right-of-Way” by Emilia Chojkiewicz, et al. (Energy Institute WP 343), reconductoring holds significant potential for rapid transmission expansion. The advanced conductors can carry approximately twice as much power as conventional conductors. Advanced conductors use existing transmission towers and rights of way, thereby circumventing the land acquisition and permitting processes that can impede construction of new transmission lines. However, replacing conventional conductors with advanced conductors requires taking circuits out of service during the replacement or conducting live-line work, which carries additional risks, especially safety risks for the workforce and surrounding areas. Either approach can be challenging, and in some cases infeasible, when transmission constraints exist.
Comments
- Need for this bill. The author contends that the urgency for California to meet its clean energy and carbon reduction goals will require a rapid and costly expansion of the transmission system. According to the author:
GETs encompasses a suite of technologies that can be deployed faster than building new transmission infrastructure and, as a result, increase the capacity and efficiency of the existing transmission system. AB 2779 can therefore help provide information on the frequency and best use of GETs under consideration in the CAISO transmission planning process by having the CAISO report on their usage.
- Current use of GETs and advanced conductors. The two papers noted above, along with others, comment on the more prevalent use of GETs and advanced conductors in other countries, particularly in Europe and India. These papers generally state that the use of these technologies has not been as quickly embraced in the United States. In California, advanced conductors have been deployed, particularly by Southern California Edison (SCE) who has deployed reconductoring projects, including the Big Creek-Ventura 220kV network. Additionally, the CAISO shared that they have considered GETs in the annual transmission planning process for many years. Specifically, the CAISO shared they typically consider advanced conductors and power flow controllers as planning tools providing alternatives to capital expenditures, as well as, dynamic thermal line ratings, and topology optimizations to access operational benefits through additional capacity. In addition to the Big Creek-Ventura line, the CAISO approved a phase shifting transformer flow controller installation at the Imperial Valley Substation. More recently, there are two projects under development in San Jose with flow controls. In its most recent transmission plan, the CAISO listed out 17 approved transmission projects since 2013-14 transmission plan to deploy GETS, particularly flow controllers, advanced conductors, and dynamic voltage controls.
- Federal efforts to encourage use of GETs and advanced conductors. At the federal level, the FERC recently adopted (May 13, 2024) a transmission and cost allocation rule, Order No. 1920, “Building for the Future Through Electric Regional Transmission Planning and Cost Allocation and Generator Interconnection” (RM21-17-000) which among its provisions requires public utility transmission providers to more fully consider the use of GETs, such as dynamic line ratings, advanced power flow control devices, advanced conductors and transmission switching, in their transmission planning. The CPUC has also shared that they, along with the CEC, CAISO, Pacific Gas & Electric, SCE, and Energy Institute at Haas are currently pursuing a Department of Energy Grid Resilience and Innovation Partnership program (GRIP) grant (eight years long) to deploy advanced conductors and two other GETs technologies: dynamic line rating and real-time short circuit duty monitoring. More recently, on May 28th, the White House announced the launch of a Federal-State Modern Grid Deployment Initiative to accelerate improvements to the electric transmission and distribution network to help meet “the country’s objectives for affordable, clean, reliable, and resilient power.” The Initiative involves a commitment from the Federal government and 21 states, including California, to work together to increase cooperation on transmission planning, including specific commitments to expand the use of GETS and advanced conductors. This Initiative is intended to build up last month’s Department of Energy announcement to expand a categorical exclusion under the National Environmental Policy Act for upgrading and rebuilding transmission lines, including for reconductoring.
- Impacts to ratepayers. The actual savings benefits for the use of GETs and advanced conductors will vary by transmission line. Both the Brattle Group and Energy Institute papers cite opportunities for savings and efficiency benefits from the use of GETs and advanced conductors. With regards to GETs, these technologies can be deployed on existing transmission lines to enhance efficiency, with the potential to reduce congestion by 40 percent. Such level of efficiency can provide savings to ratepayers in the form of reducing the need to build additional transmission lines which can be very costly. Advanced conductors have a higher up-front cost as compared to conventional aluminum conductors – roughly two to three times the costs – though they have the potential for long-term savings given the potential to double the capacity of conventional conductors. As stated in the Energy Institute paper, “Transmission networks are complex, and the actual increase in power transfer capacity offered by reconductoring is determined by a multitude of factors beyond the scope of this analysis. We recommend that transmission owners, ISOs, and RTOs perform more detailed studies…to evaluate the wide-scale deployment of advanced conductors in their networks.”
Related/Prior Legislation
SB 1006 (Padilla, 2024) would require electrical transmission utilities, by January 1, 2026, to develop a strategic plan for grid-enhancing technologies to cost-effectively increase transmission capacity and to complete an evaluation to identify which of its transmission and distribution lines can be reconductored with advanced reconductors. Requires these plans and evaluations are submitted to the CPUC and made publicly available. The bill is pending in the Assembly.
SB 319 (McGuire, Chapter 390, Statutes of 2023) required the CEC and the CPUC, in coordination with the CAISO, to better and regularly coordinate planning and permitting of energy transmission infrastructure to ensure the state meets its clean energy goals and to evaluate and report on that planning and related infrastructure development.
SB 529 (Hertzberg, Chapter 357, Statutes of 2022) exempted an extension, expansion, upgrade, or other modification of an existing transmission line or substations from the requirement of a CPCN and directed the CPUC to revise its GO, by January 1, 2024, to instead use its permit to construct process for these approvals.
SB 887 (Becker, Chapter 358, Statutes of 2022) required 15-year projections of energy resource portfolios and energy demand to inform transmission planning to achieve the state’s clean energy goals, and requires the CAISO to consider approval for specified transmission projects as part of the 2022-23 transmission planning process.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: No
SUPPORT: (Verified 6/17/24)
Advanced Energy United
Ava Community Energy
California Community Choice Association
California Farm Bureau
California State Association of Electrical Workers
Coalition of California Utility Employees
Environment California
San José Clean Energy
OPPOSITION: (Verified 6/17/24)
None received
ARGUMENTS IN SUPPORT: The entities in support of this bill general express enthusiasm for the opportunity to expand transmission capacity and efficiency by deploying GETs to help the state achieve its clean energy goals, particularly to help reduce transmission costs. Many supporters also acknowledge the use of GETs alone will not remedy all the state’s transmission needs, but can provide another effective tool to help the state meet its climate and clean energy goals. In support of this bill, the California State Association of Electrical Workers and Coalition of California Utility Employees state:
California must dramatically increase the total capacity of its transmission system to supply the vastly increased demand for electricity needed to meet our carbon neutrality goals. This will certainly require many new transmission lines. … GETs can improve the reliability, safety, and efficiency of existing power lines. They are typically very low-cost enhancements to existing transmission lines that increase the capacity of the lines while reducing fire risk. …This bill would establish a reporting process so that the CPUC and the Legislature can monitor the extent to which the CAISO is utilizing cost-effective GETs in its transmission planning process.
ASSEMBLY FLOOR: 65-0, 5/9/24
AYES: Addis, Aguiar-Curry, Alanis, Alvarez, Arambula, Bauer-Kahan, Bennett, Berman, Boerner, Bonta, Bryan, Calderon, Juan Carrillo, Wendy Carrillo, Chen, Connolly, Davies, Dixon, Essayli, Mike Fong, Vince Fong, Friedman, Gallagher, Garcia, Gipson, Hart, Holden, Hoover, Irwin, Jackson, Jones-Sawyer, Kalra, Lackey, Lee, Lowenthal, Maienschein, McCarty, McKinnor, Muratsuchi, Ortega, Pacheco, Papan, Jim Patterson, Joe Patterson, Pellerin, Quirk-Silva, Ramos, Rendon, Reyes, Rodriguez, Blanca Rubio, Sanchez, Santiago, Soria, Ta, Valencia, Villapudua, Waldron, Ward, Weber, Wicks, Wilson, Wood, Zbur, Robert Rivas
NO VOTE RECORDED: Bains, Cervantes, Megan Dahle, Flora, Gabriel, Grayson, Haney, Low, Mathis, Stephanie Nguyen, Petrie-Norris, Luz Rivas, Schiavo, Ting, Wallis
Prepared by: Nidia Bautista / E., U. & C. / (916) 651-4107
6/18/24 10:59:46
**** END ****
SENATE COMMITTEE ON ENERGY, UTILITIES AND COMMUNICATIONS
Senator Steven Bradford, Chair
2023 - 2024 Regular
Bill No: Hearing Date: 6/4/2024
Author: | |||
Version: | Amended | ||
Urgency: | Fiscal: | ||
Consultant: | |||
SUBJECT:
DIGEST: This bill requires the California Independent System Operator (CAISO), upon approval of the annual transmission plan, to report on any new use of any grid enhancing technology and its associated cost or efficiency savings.
ANALYSIS:
Existing law:
- Establishes that U.S. Federal Energy Regulatory Commission (FERC) has exclusive jurisdiction over the transmission of electric energy in interstate commerce. Also establishes the process and procedures for establishing transmission of electric energy in interstate commerce by public utilities, i.e., the rates, terms & conditions of interstate electric transmission by public utilities. (Federal Power Act §§§201, 205, 206 (16 USC 824, 824d, 824e))
- Establishes and vests the California Public Utilities Commission (CPUC) with regulatory authority over public utilities, including electrical corporations. (Article XII of the California Constitution)
- Establishes the CAISO as a nonprofit, public benefit corporation to manage the transmission grid and related energy markets, as provided. (Public Utilities Code §345 et seq.)
- Provides that the CPUC may supervise and regulate every public utility in the state and may do all things, whether specifically designated or in addition, which are necessary and convenient in the exercise of such power and jurisdiction. (Public Utilities Code §701)
- Prohibits an electrical corporation from beginning the construction of a line, plant, or system, or of any extension thereof, without having first obtained from the CPUC a certificate that the present or future public convenience and necessity require or will require its construction. Provides that the extension, expansion, upgrade, or other modification of an existing electrical transmission facility, including transmission lines and substations, does not require a certificate that the present or future public convenience and necessity requires or will require its construction. (Public Utilities Code §1001)
This bill:
- Requires the CAISO, upon approval of each transmission plan, to report to the CPUC and to the relevant policy committees of each house of the Legislature any new use of any grid enhancing technology that is deemed reasonable by the CAISO in that plan and the cost or efficiency savings of the deployment of that grid enhancing technology.
- Requires the report to be submitted in accordance with requirements on reports submitted by agencies, including to submit to the Secretary of the Senate, the Chief Clerk of the Assembly, and the Legislative Counsel, as prescribed.
- Provides that the requirement to provide the reports are not subject to a sunset.
Background
- Transmission projects. Electric transmission lines are generally high voltage lines that move electricity from generation resources (power plants) to distribution lines in neighborhoods. Companies, usually electric investor-owned utilities (IOUs), proposing the construction of new transmission, are required to obtain a permit from the CPUC for construction of specified infrastructure listed under Public Utilities Code §1001, including transmission projects. In the case of interstate transmission lines, FERC has exclusive jurisdiction as to the costs and rates approved for the use of these lines.
- Need for expanded transmission capacity. In order for the state to meet its clean energy goals, including achieving 100 percent clean energy by 2045, electric transmission capacity will likely need to grow significantly. The CAISO conducts its annual transmission planning process to identify potential transmission system limitations and opportunities for system reinforcements that improve reliability and efficiency. The CAISO identifies projects that address grid reliability requirements, identify upgrades needed to successfully meet California’s policy goals, and explore projects that can bring economic benefits to consumers. In 2021, the CAISO created a 20-Year Transmission Outlook for the electric grid, in collaboration with the CPUC and the California Energy Commission (CEC), with the goal of exploring the longer-term grid requirements and options for meeting the state’s SB 100 clean energy goals reliably and cost-effectively. The 20-Year Transmission Outlook estimates a significant amount, about $30 billion, to construct and expand transmission facilities. In subsequent transmission plans, the CAISO has approved over $16 billion worth of about 100 transmission projects. Transmission owners recover the costs of CAISO-approved projects through the Transmission Access Charge (TAC). The transmission owner submits an application to FERC to recover project costs. FERC approves just and reasonable costs and rate of return. CAISO charges transmission customers based on FERC-approved costs. These costs are collected from electric utility customers as part of the transmission and distribution portion of the electric utility bill.
- Grid-enhancing technologies (GETs). GETs, generally, are a combination of hardware and software that can increase transmission capacity, decrease congestion, and improve reliability on transmission lines. An April 2023 Brattle Group white paper, Building a Better Grid: How Grid-enhancing Technologies Complement Transmission Buildouts, discusses how GETs can help improve transmission capacity and efficiency. The paper notes that transmission transfer capability depends on where and how new transmission lines are connected to the rest of the electrical grid system – the topology of the transmission network (including the points of injection and withdrawal of energy). Both the transfer capability of lines (and other components of the grid) and network topology determine how, where, and the quantity of the power flows. Many GETs are built on either of two applications to increase transfer capability: one that explores enhanced and flexible application of the pre-determined transfer capability, and the other that focuses on flexible and dynamic control of transmission systems.
Examples of GETs include dynamic line ratings, advanced power flow controls, and advanced topology control. Dynamic line ratings (DLRs) try to better address individual line transfer capability based on actual conditions. Advanced power flow controls (generally hardware) and advanced topology control (generally software) direct electricity away from overloaded lines and onto underutilized lines, such as by opening or closing circuit breakers. As noted in the Brattle Group paper: The comparative advantages of GETs include their portability and scalability, speed to deploy, and lower costs. Importantly, per the report, “GETs rarely replace transmission, rather, they enhance transmission…”
- Advanced reconductoring. The CAISO also defines GETs to include advanced reconductoring which is the replacement of a transmission line’s existing conductors with advanced conductors, essentially swapping out the Aluminum Conductor Steel Reinforced (ACSR) for a smaller composite core conductors that enable higher operating temperatures. According to a November 2023 Energy Institute at Haas paper, “Accelerating Transmission Expansion by Using Advanced Conductors in Existing Right-of-Way” by Emilia Chojkiewicz, et al. (Energy Institute WP 343), reconductoring holds significant potential for rapid transmission expansion. The advanced conductors can carry approximately twice as much power as conventional conductors. Advanced conductors use existing transmission towers and rights of way, thereby circumventing the land acquisition and permitting processes that can impede construction of new transmission lines. However, replacing conventional conductors with advanced conductors requires taking circuits out of service during the replacement or conducting live-line work, which carries additional risks, especially safety risks for the workforce and surrounding areas. Either approach can be challenging, and in some cases infeasible, when transmission constraints exist.
Comments
- Need for this bill. The author contends that the urgency for California to meet its clean energy and carbon reduction goals will require a rapid and costly expansion of the transmission system. The author states:
GETs encompasses a suite of technologies that can be deployed faster than building new transmission infrastructure and, as a result, increase the capacity and efficiency of the existing transmission system. AB 2779 can therefore help provide information on the frequency and best use of GETs under consideration in the CAISO transmission planning process by having the CAISO report on their usage.
- Current use of GETs and advanced conductors. The two papers noted above, along with others, comment on the more prevalent use of GETs and advanced conductors in other countries, particularly in Europe and India. These papers generally state that the use of these technologies has not been as quickly embraced in the United States. In California, advanced conductors have been deployed, particularly by Southern California Edison (SCE) who has deployed reconductoring projects, including the Big Creek-Ventura 220kV network. Additionally, the CAISO shared that they have considered GETs in the annual transmission planning process for many years. Specifically, the CAISO shared they typically consider advanced conductors and power flow controllers as planning tools providing alternatives to capital expenditures, as well as, dynamic thermal line ratings, and topology optimizations to access operational benefits through additional capacity. In addition to the Big Creek-Ventura line, the CAISO approved a phase shifting transformer flow controller installation at the Imperial Valley Substation. More recently, there are two projects under development in San Jose with flow controls. In its most recent transmission plan, the CAISO listed out 17 approved transmission projects since 2013-14 transmission plan to deploy GETS, particularly flow controllers, advanced conductors, and dynamic voltage controls.
- Federal efforts to encourage use of GETs and advanced conductors. At the federal level, the FERC recently adopted (May 13, 2024) a transmission and cost allocation rule, Order No. 1920, “Building for the Future Through Electric Regional Transmission Planning and Cost Allocation and Generator Interconnection” (RM21-17-000) which among its provisions requires public utility transmission providers to more fully consider the use of GETs, such as dynamic line ratings, advanced power flow control devices, advanced conductors and transmission switching, in their transmission planning. The CPUC has also shared that they, along with the CEC, CAISO, Pacific Gas & Electric, SCE, and Energy Institute at Haas are currently pursuing a Department of Energy Grid Resilience and Innovation Partnership program (GRIP) grant (eight years long) to deploy advanced conductors and two other GETs technologies: dynamic line rating and real-time short circuit duty monitoring. More recently, on May 28th, the White House announced the launch of a Federal-State Modern Grid Deployment Initiative to accelerate improvements to the electric transmission and distribution network to help meet “the country’s objectives for affordable, clean, reliable, and resilient power.” The Initiative involves a commitment from the Federal government and 21 states, including California, to work together to increase cooperation on transmission planning, including specific commitments to expand the use of GETS and advanced conductors. This Initiative is intended to build up last month’s Department of Energy announcement to expand a categorical exclusion under the National Environmental Policy Act for upgrading and rebuilding transmission lines, including for reconductoring.
- Impacts to ratepayers. The actual savings benefits for the use of GETs and advanced conductors will vary by transmission line. Both the Brattle Group and Energy Institute papers cite opportunities for savings and efficiency benefits from the use of GETs and advanced conductors. With regards to GETs, these technologies can be deployed on existing transmission lines to enhance efficiency, with the potential to reduce congestion by 40 percent. Such level of efficiency can provide savings to ratepayers in the form of reducing the need to build additional transmission lines which can be very costly. Advanced conductors have a higher up-front cost as compared to conventional aluminum conductors – roughly two to three times the costs – though they have the potential for long-term savings given the potential to double the capacity of conventional conductors. As stated in the Energy Institute paper, “Transmission networks are complex, and the actual increase in power transfer capacity offered by reconductoring is determined by a multitude of factors beyond the scope of this analysis. We recommend that transmission owners, ISOs, and RTOs perform more detailed studies…to evaluate the wide-scale deployment of advanced conductors in their networks.”
Need for amendments. In order to ensure the CAISO reports on both the cost savings and efficiency savings, the author and committee may wish to amend this bill to replace the “or” with “and” in reference to reporting the “efficiency or cost savings” of the use of GETs.
Prior/Related Legislation
SB 1006 (Padilla) requires electrical transmission utilities, by January 1, 2026, to develop a strategic plan for grid-enhancing technologies to cost-effectively increase transmission capacity and to complete an evaluation to identify which of its transmission and distribution lines can be reconductored with advanced reconductors. Requires these plans and evaluations are submitted to the CPUC and made publicly available. The bill is pending in the Assembly.
SB 319 (McGuire, Chapter 390, Statutes of 2023) required the CEC and the CPUC, in coordination with the CAISO, to better and regularly coordinate planning and permitting of energy transmission infrastructure to ensure the state meets its clean energy goals and to evaluate and report on that planning and related infrastructure development.
SB 529 (Hertzberg, Chapter 357, Statutes of 2022) exempted an extension, expansion, upgrade, or other modification of an existing transmission line or substations from the requirement of a CPCN and directed the CPUC to revise its GO, by January 1, 2024, to instead use its permit to construct process for these approvals.
SB 887 (Becker, Chapter 358, Statutes of 2022) required 15-year projections of energy resource portfolios and energy demand to inform transmission planning to achieve the state’s clean energy goals, and requires the CAISO to consider approval for specified transmission projects as part of the 2022-23 transmission planning process.
FISCAL EFFECT: Appropriation: Fiscal Com.: Local:
SUPPORT:
Advanced Energy United
Ava Community Energy
California Community Choice Association
California Farm Bureau
California State Association of Electrical Workers
Coalition of California Utility Employees
Environment California
San José Clean Energy
OPPOSITION:
None received
ARGUMENTS IN SUPPORT: The entities in support of the bill general express enthusiasm for the opportunity to expand transmission capacity and efficiency by deploying GETs to help the state achieve its clean energy goals, particularly to help reduce transmission costs. Many supporters also acknowledge the use of GETs alone will not remedy all the state’s transmission needs, but can provide another effective tool to help the state meet its climate and clean energy goals. In support of this bill, the California State Association of Electrical Workers and Coalition of California Utility Employees state:
California must dramatically increase the total capacity of its transmission system to supply the vastly increased demand for electricity needed to meet our carbon neutrality goals. This will certainly require many new transmission lines. … GETs can improve the reliability, safety, and efficiency of existing power lines. They are typically very low-cost enhancements to existing transmission lines that increase the capacity of the lines while reducing fire risk. …This bill would establish a reporting process so that the CPUC and the Legislature can monitor the extent to which the CAISO is utilizing cost-effective GETs in its transmission planning process.
-- END --
Date of Hearing: May 1, 2024
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Buffy Wicks, Chair
ABPCA Bill Id:AB 2779
Author:(Petrie-Norris) – As Amended Ver:March 21, 2024
Policy Committee: | Utilities and Energy | Vote: | 16 - 0 |
|
| ||
|
|
Urgency: No State Mandated Local Program: No Reimbursable: No
SUMMARY:
This bill requires the California Independent System Operator (CAISO), upon CAISO’s approval of each transmission plan produced through the transmission planning process (TPP), or a successor process, report to the California Public Utilities Commission (CPUC) and the relevant policy committees of both houses of the Legislature any new use of any grid-enhancing technology that is deemed reasonable by CAISO in the transmission plan and the costs or efficiency savings of the deployment of that grid-enhancing technology.
FISCAL EFFECT:
Minor state costs as CAISO is funded by charges on electricity transmission, not from state funds.
COMMENTS:
To achieve the state’s clean energy goals, California will need considerable amounts of new transmission to be developed, quickly. The cost of this new transmission is likely in the billions of dollars.
The state’s energy infrastructure planning and permitting processes is complex and involves inter-related activities by multiple parties and state agencies. This complexity and inter-relation is demonstrated by the Assembly Utilities and Energy Committee analysis of this bill, which described the process, more or less, as follows:
- The Air Resources Board’s Scoping Plan establishes a target range for the electricity sector’s greenhouse gas (GHG) emission reductions.
- The Energy Commission’s Integrated Energy Policy Report (IEPR) provides a demand forecast to anticipate statewide load in the next decade or longer.
- The CPUC’s integrated resource plan (IRP) forecasts system generation resource needs to meet the customer demand forecast by the IEPR 10 years in the future.
- The CPUC’s resources adequacy (RA) process identifies resources needed to meet customer demand and ensure reliability today.
- CAISO’s TPP identifies the transmission needs to interconnect and balance the system supply described by the IRP with the customer demand projected by the IEPR.
- The TPP relies on the CPUC’s IRP planning targets. CAISO receives the IRP results as inputs into its TPP. The CAISO also considers recommendations from the Energy Commission’s IEPR. The plan is updated annually, and culminates in a CAISO Board of Governors-approved transmission plan that identifies the needed transmission solutions and authorizes cost recovery through CAISO transmission rates, subject to federal regulatory approval.
“Grid-enhancing technologies” (GETs) is a term that encompasses much. Generally, GETs augment the performance of a transmission line or increases the line’s efficiency. Examples include sensors and conductors. Recently, there has been interest in pushing utilities to consider or utilize such technologies instead of developing new transmission lines. Notably, Allison Clements, Federal Energy Regulatory Commission commissioner asserted the following at a conference in La Quinta, as reported by Utility Dive:
Let’s together require the transmission-owning utilities to use them [grid-enhancing technologies] and then let’s encourage them or … figure out ways that help them overcome some of the barriers that they have to getting it done…the investments are modest, and the impacts are significant…We need to make the utilities, who have this great opportunity to invest in new transmission, do it smartly, together with this grid-enhancing technology opportunity.
An investor-owned utility generally make profits from long-term investments in physical capital, on which it earns a rate of return. Therefore, arguably, such a utility has an incentive towards building new transmission lines and away from less-costly GET. This bill may allow the Legislature and the regulator to better understand CAISO’s consideration of these technologies. As the author puts it:
Grid-enhancing technologies (GETs) encompass a suite of technologies that increase the capacity and efficiency of the existing transmission system. Given that GETs can be deployed faster than building new transmission infrastructure, they allow California to better utilize its existing infrastructure and provide short-term solutions to temporary operational challenges, such as during outages or when new lines are under construction. GETs may also serve an important role of bridging a gap until a permanent transmission expansion is completed. AB 2779 will provide transparency on the frequency and best use of GETs under consideration in the CAISO TPP, by having the CAISO report on their usage.
Analysis Prepared by: Jay Dickenson / APPR. / (916) 319-2081
Date of Hearing: April 17, 2024
ASSEMBLY COMMITTEE ON UTILITIES AND ENERGY
Cottie Petrie-Norris, Chair
ABPCA Bill Id:AB 2779 (
Author:Petrie-Norris) – As Amended Ver:March 21, 2024
SUBJECT: Independent System Operator: transmission planning
SUMMARY: Requires the California Independent System Operator (CAISO) to report to the California Public Utilities Commission (CPUC) and to relevant policy committees in the Legislature any new use of and cost savings derived from the deployment of grid enhancing technologies (GETs) deemed reasonable in the Transmission Planning Process (TPP).
EXISTING LAW:
- Establishes the CAISO as a nonprofit public benefit corporation and requires the CAISO to ensure efficient use and reliable operation of the electrical transmission grid consistent with achieving planning and operating reserve criteria. (Public Utilities Code § 345.5)
- Requires the CPUC to consider in its Certificate of Public Convenience and Necessity review cost-effective alternatives to a transmission facility, including targeted energy efficiency, ultraclean distributed generation, and other demand reduction resources. (Public Utilities Code § 1002.3)
FISCAL EFFECT: Unknown. This bill is keyed fiscal and will be referred to the Committee on Appropriations for its review.
BACKGROUND:
California’s climate goals – SB 100 (de León, Chapter 312, Statutes of 2018) established the state policy that renewable and zero-carbon resources supply 100% of retail sales and electricity procured to serve all state agencies by 2045 (the 100% Clean Energy Policy).[1] This policy was updated under SB 1020 (Laird, Chapter 361, Statutes of 2022) which accelerated the requirement on state agencies to 100% by 2035, and established interim targets to meet the sector-wide 100% goal. California’s clean power goals parallel the state’s goals for achieving net zero greenhouse gas (GHG) emissions and 100% new zero-emission vehicle sales by 2035.[2],[3] Taken together, electricity demand in California is expected to nearly double by 2040,[4] requiring heavy investment in the state’s power grid to meet its net zero goals. These ambitious climate targets establish the planning goal that informs all subsequent electricity procurement and transmission planning.
Transmission Planning – Transmission lines carry electric energy from one point to another in an electric power system. As the transmission system is the connecting point between generation resources (supply) and consumers (demand), planning for transmission construction – both new and upgrading old – requires an understanding of both future generation resource needs (capacity and location) and consumer demand changes. Therefore, transmission planning requires a robust planning process that considers all aspects of electricity supply and demand.
California has a complicated but robust electric planning and procurement regime spread across the California Air Resources Board (CARB), the CPUC, the California Energy Commission (CEC), and the CAISO. Much of this regime focuses on resource procurement needed to meet our clean energy goals, however, the direct downstream effect of the procurement planning is planning for the transmission needed to accommodate the new generation. The main elements of the regime are the Scoping Plan at CARB, the Integrated Energy Policy Report (IEPR) at the CEC, the Integrated Resource Plans (IRP) and Resource Adequacy (RA) process at the CPUC, and finally the Transmission Planning Process (TPP) at the CAISO.
Briefly:
- The Scoping Plan establishes a target range for the electricity sector’s greenhouse gas (GHG) emission reductions;
- The IEPR, among other considerations and actions, provides a demand forecast to anticipate statewide load in the next decade or longer;
- The IRP forecasts system generation resource needs to meet the customer demand forecast by the IEPR 10 years in the future;
- The RA identifies resources needed to meet customer demand and ensure reliability today; and
- The TPP identifies the transmission needs to interconnect and balance the system supply provided by the IRP with the customer demand provided by the IEPR.
CAISO’s TPP is updated annually and culminates in a CAISO Board of Governors approved transmission plan that identifies the needed transmission solutions and authorizes cost recovery through CAISO transmission rates, subject to federal regulatory approval. Following the CAISO Board’s approval of a TPP, new projects that are identified as necessary go through a competitive solicitation process. Transmission developers apply for the project solicitation and those applications are evaluated on a number of qualifying criteria, including cost. Most recently, the CAISO released its 2023-2024 TPP draft on April 1, 2024,[5] and identified 26 projects – at an estimated $6.1 billion – needed for reliability and to meet state policy goals; two of these projects are expected to be eligible for competitive solicitation.
GETs – According to the U.S. Department of Energy (DOE), an estimated 70% of transmission and distribution lines in the U.S. are well into the second half of their 50-year life expectancy.[6] As transmission lines age, they become more inefficient, increasing the likelihood of congested power lines, which can force operators to reroute power through less optimal paths and rely on more expensive or less clean power generation.[7] Extreme cases of transmission constraints may even overload transmission systems, forcing utilities to employ periodic load shedding tactics (i.e., rolling blackouts).
To facilitate the clean energy transition, GETs have been posed by researchers and industry leaders as an interim, cost-effective solution to unlock transmission capacity in the near term and buy time for long-term transmission planning. GETs encompass a suite of technologies – such as advanced conductors,[8] dynamic line ratings,[9] advanced power flow control devices,[10] and analytical tools – that can be used to maximize the transmission of electricity across existing lines. According to the Federal Energy Regulatory Commission (FERC), GETs can cost less than 10% of the cost of investing in new transmission lines, and can save millions in annual congestion costs.[11] As a result, FERC has recently taken steps to push for consideration and adoption of GETs, through incentive programs supported by the federal Bipartisan Infrastructure Law.[12]
COMMENTS:
- Author’s statement. According to the author, “Given the urgency for the state to meet its clean energy goals, a shorter-term solution is needed to maximize transmission capacity. Grid-enhancing technologies (GETs) encompass a suite of technologies that increase the capacity and efficiency of the existing transmission system. Given that GETs can be deployed faster than building new transmission infrastructure, they allow California to better utilize its existing infrastructure and provide short-term solutions to temporary operational challenges, such as during outages or when new lines are under construction. GETs may also serve an important role of bridging a gap until a permanent transmission expansion is completed. AB 2779 will provide transparency on the frequency and best use of GETs under consideration in the CAISO TPP, by having the CAISO report on their usage.”
- Small steps today for giant leaps tomorrow. Years-long permitting processes across multiple agencies, community opposition, and high costs mean it can take a decade to build new transmission infrastructure. While the state is recontemplating its permitting processes to get new transmission projects built and connected, more interim solutions may be needed to meet increasing energy demand in the short-term given the urgency for the state to meet its clean energy goals. GETs may offer a method to maximize existing transmission capacity in a relatively cost-effective way.11 For example, recent research by the University of California, Berkeley’s Energy Institute at Haas found that replacing existing power lines with advanced conductors, or reconductoring, could roughly double the capacity of the electric grid in many parts of the country, making room for more wind and solar power.[13]
Though supporters of GETs are concerned that the technologies have yet to be widely adopted in California and the U.S., the CAISO has considered GETs as potential alternatives in the TPP for many years. They note particular success in selecting flow controllers in a number of cases in past plans and approving for the first time a project employing advanced conductors in the 2022-2023 TPP; in the 2023-2024 draft TPP, CAISO recommended GETs to increase resiliency in the Humboldt area.5
The electric investor-owned utilities (IOUs), at the prompting of CAISO’s recommendations and their own acknowledgment that the high stakes for addressing climate change requires grid modernization and optimization,[14],[15] are also actively researching and considering GETs. San Diego Gas and Electric (SDG&E) reports that they have deployed phase shifting transformers at one of their substations; they are currently testing dynamic line rating devices; and they are currently pursuing a grant application for the implementation of advanced conductors on a 138 kV reconductor project.[16]
This bill proposes CAISO to report any GETs it selects in its TPP, in line with their ongoing review of this technology to date. Such reporting will provide transparency and reassurance that the state is actively considering short-term and cost-effective solutions to ensure grid resiliency, resource adequacy, and clean power generation.
- Related legislation.
AB 3246 (Garcia) would require the CPUC to update its General Order 131-D to provide exemptions from certain approvals and environmental assessments for GETs, specifically advanced reconductoring, as specified. Status: set for hearing in this committee on April 17th, 2024.
SB 1006 (Padilla) would require IOUs to jointly prepare a GETs strategic plan, aimed towards cost-effectively increasing transmission capacity and interconnection of renewable and zero-carbon energy resources, by January 1, 2026. Would require each IOU to complete an evaluation every 4 years of the benefits and cost-effectiveness of reconductoring their transmission and distribution lines with advanced conductors. Status: set for hearing in the Senate Committee on Energy, Utilities and Communications on April 16th, 2024.
- Prior legislation.
SB 1020 (Laird) accelerated the 100% Clean Energy Policy to require electricity procured to serve all state agencies be 100% clean energy by 2035, and established interim targets to meet the sector-wide 100% goal. Status: Chapter 361, Statutes of 2022.
AB 1279 (Muratsuchi) declared the policy of the state to achieve net zero GHG emissions by 2045 and to ensure that, by 2045, statewide anthropogenic GHGs are reduced to at least 85% below 1990 levels. Status: Chapter 337, Statutes of 2022.
SB 100 (de León) established the state policy that renewable and zero-carbon resources supply 100% of retail sales and electricity procured to serve all state agencies and California end-use customers by 2045. Status: Chapter 312, Statutes of 2018.
REGISTERED SUPPORT / OPPOSITION:
Support
Advanced Energy Economy
California Farm Bureau Federation
California State Association of Electrical Workers
Coalition of California Utility Employees
Environment California
Opposition
None on file.
Analysis Prepared by: Kathleen Chen / U. & E. / (916) 319-2083
Public Utilities Code § 454.53 ↑
AB 1279 (Muratsuchi, Chapter 337, Statutes of 2022) ↑
Executive Order N-79-20 ↑
CAISO; 20-Year Transmission Outlook; January2022. ↑
CAISO; 2023-2024 Transmission Plan Draft; April 2024. ↑
DOE; “What does it take to modernize the U.S. electric grid?”; https://www.energy.gov/gdo/articles/what-does-it-take-modernize-us-electric-grid; October 2023. ↑
DOE; Grid-Enhancing Technologies: A Case Study on Ratepayer Impact; February 2022. ↑
Advanced conductors enable higher operating temperatures, higher capacity for electrical current, and reduced line sag. ↑
Dynamic line ratings adjust thermal line ratings based on actual weather conditions, including ambient air temperature and wind speed/direction. ↑
Advanced power-flow control devices swiftly control the impedance, or opposition to current, in real time to ensure that power is delivered on lines that have the capacity to carry it. ↑
Utility Dive; “Regulators need to require utilities to use grid-enhancing technologies: FERC’s Clements”; https://www.utilitydive.com/news/transmission-grid-enhancing-technologies-gets-utilities-naruc-ferc-clements/699686/; November 2023. ↑
DOE; “Grid Resilience and Innovation Partnerships (GRIP) Program”; https://www.energy.gov/gdo/grid-resilience-and-innovation-partnerships-grip-program. ↑
WP 343R, Energy Institute at Haas; “Accelerating Transmission Expansion by Using Advanced Conductors in Existing Right-of-Way”; February 2024. ↑
Southern California Edison; Smart Grid Strategy & Roadmap; https://www.google.com/url?sa=t&source=web&rct=j&opi=89978449&url=https://www.smartgrid.gov/files/documents/Southern_California_Edison_Smart_Grid_Strategy_Roadmap_201012.pdf&ved=2ahUKEwjO4Jmn1biFAxUQIDQIHceGAQkQFnoECB8QAQ&usg=AOvVaw0dQV7eYsK-mpFbs2UjujaB. ↑
Pacific Gas & Electric; PG&E R&D Strategy Report; June 2023. ↑
Per data request from SDG&E on February 9th, 2024. ↑