Existing law prescribes various requirements regarding the formation, content, and enforcement of state and local public contracts. Existing law applicable to state public contracts generally requires that the resolution of claims related to those contracts be subject to arbitration. Existing law applicable to local agency contracts prescribes a process for the resolution of claims related to those contracts of $375,000 or less.
This bill would establish, for contracts entered into on or after January 1, 2017, a claim resolution process applicable to any claim by a contractor in connection with a public works project. The bill would define a claim as a separate demand by the contractor for one or more of the following: a time extension for relief from damages or penalties for delay, payment of money or damages arising from work done pursuant to the contract for a public work, or payment of an amount disputed by the public entity, as specified.
This bill would require a public entity, defined to exclude certain state entities, upon receipt of a claim sent by registered or certified mail, to review it and, within 45 days, provide a written statement identifying the disputed and undisputed portions of the claim. The bill would authorize the 45-day period to be extended by mutual agreement. The bill would require any payment due on an undisputed portion of the claim to be processed within 60 days, as specified. The bill would require that the claim be deemed rejected in its entirety if the public entity fails to issue the written statement.
This bill would authorize, if the claimant disputes the public entitys written response or if the public entity fails to respond to a claim within the time prescribed, the claimant to demand to meet and confer for settlement of the issues in dispute. The bill would require any disputed portion of the claim that remains in dispute after the meet and confer conference to be subject to nonbinding mediation, as specified. The bill would provide that unpaid claim amounts accrue interest at 7% per annum. The bill would prescribe a procedure by which a subcontractor or lower tier contractor may make a claim through the contractor.
This bill would require the text of these provisions, or a summary, to be set forth in the plans or specifications for any public work which may give rise to a claim. The bill would specify that a waiver of these rights is void and contrary to public policy, except as specified. The bill would also specify that it does not impose liability on a public entity that makes loans or grants available through a competitive application process, for the failure of an awardee to meet its contractual obligations.
By increasing the duties of local agencies and officials, this bill would impose a state-mandated local program.
This bill would, on January 1, 2020, repeal the provision establishing the claim resolution process.
This bill would specify that these provisions constitute a matter of statewide concern.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that, if the Commission on State Mandates determines that the bill contains costs mandated by the state, reimbursement for those costs shall be made pursuant to these statutory provisions.
Existing law prescribes various requirements regarding the formation, content, and enforcement of state and local public contracts. Existing law applicable to state public contracts generally requires that the resolution of claims related to those contracts be subject to arbitration. Existing law applicable to local agency contracts prescribes a process for the resolution of claims related to those contracts of $375,000 or less.
This bill would establish, for contracts entered into on or after January 1, 2017, a claim resolution process applicable to any claim by a contractor in connection with a public works project. The bill would define a claim as a separate demand by the contractor for one or more of the following: a time extension for relief from damages or penalties for delay, payment of money or damages arising from work done pursuant to the contract for a public work, or payment of an amount disputed by the public entity, as specified.
This bill would require a public entity, defined to exclude certain state entities, upon receipt of a claim sent by registered or certified mail, to review it and, within 45 days, provide a written statement identifying the disputed and undisputed portions of the claim. The bill would authorize the 45-day period to be extended by mutual agreement. The bill would require any payment due on an undisputed portion of the claim to be processed within 60 days, as specified. The bill would require that the claim be deemed rejected in its entirety if the public entity fails to issue the written statement.
This bill would authorize, if the claimant disputes the public entitys written response or if the public entity fails to respond to a claim within the time prescribed, the claimant to demand to meet and confer for settlement of the issues in dispute. The bill would require any disputed portion of the claim that remains in dispute after the meet and confer conference to be subject to nonbinding mediation, as specified. The bill would provide that unpaid claim amounts accrue interest at 7% per annum. The bill would prescribe a procedure by which a subcontractor or lower tier contractor may make a claim through the contractor.
This bill would require the text of these provisions, or a summary, to be set forth in the plans or specifications for any public work which may give rise to a claim. The bill would specify that a waiver of these rights is void and contrary to public policy, except as specified. The bill would also specify that it does not impose liability on a public entity that makes loans or grants available through a competitive application process, for the failure of an awardee to meet its contractual obligations.
By increasing the duties of local agencies and officials, this bill would impose a state-mandated local program.
This bill would, on January 1, 2020, repeal the provision establishing the claim resolution process.
This bill would specify that these provisions constitute a matter of statewide concern.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that, if the Commission on State Mandates determines that the bill contains costs mandated by the state, reimbursement for those costs shall be made pursuant to these statutory provisions.
Existing law prescribes various requirements regarding the formation, content, and enforcement of state and local public contracts. Existing law applicable to state public contracts generally requires that the resolution of claims related to those contracts be subject to arbitration. Existing law applicable to local agency contracts prescribes a process for the resolution of claims related to those contracts of $375,000 or less.
This bill would establish, for contracts entered into on or after January 1, 2017, a claim resolution process applicable to any claim by a contractor in connection with a public works project. The bill would define a claim as a separate demand by the contractor for one or more of the following: a time extension for relief from damages or penalties for delay, payment of money or damages arising from work done pursuant to the contract for a public work, or payment of an amount disputed by the public entity, as specified.
This bill would require a public entity, defined to exclude certain state entities, upon receipt of a claim sent by registered or certified mail, to review it and, within 45 days, provide a written statement identifying the disputed and undisputed portions of the claim. The bill would authorize the 45-day period to be extended by mutual agreement. The bill would require any payment due on an undisputed portion of the claim to be processed within 60 days, as specified. The bill would require that the claim be deemed rejected in its entirety if the public entity fails to issue the written statement.
This bill would authorize, if the claimant disputes the public entitys written response or if the public entity fails to respond to a claim within the time prescribed, the claimant to demand to meet and confer for settlement of the issues in dispute. The bill would require any disputed portion of the claim that remains in dispute after the meet and confer conference to be subject to nonbinding mediation, as specified. The bill would provide that unpaid claim amounts accrue interest at 7% per annum. The bill would prescribe a procedure by which a subcontractor or lower tier contractor may make a claim through the contractor.
This bill would require the text of these provisions, or a summary, to be set forth in the plans or specifications for any public work which may give rise to a claim. The bill would specify that a waiver of these rights is void and contrary to public policy, except as specified. The bill would also specify that it does not impose liability on a public entity that makes loans or grants available through a competitive application process, for the failure of an awardee to meet its contractual obligations.
By increasing the duties of local agencies and officials, this bill would impose a state-mandated local program.
This bill would, on January 1, 2020, repeal the provision establishing the claim resolution process.
This bill would specify that these provisions constitute a matter of statewide concern.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that, if the Commission on State Mandates determines that the bill contains costs mandated by the state, reimbursement for those costs shall be made pursuant to these statutory provisions.
Existing law prescribes various requirements regarding the formation, content, and enforcement of state and local public contracts. Existing law applicable to state public contracts generally requires that the resolution of claims related to those contracts be subject to arbitration. Existing law applicable to local agency contracts prescribes a process for the resolution of claims related to those contracts of $375,000 or less.
This bill would establish, for contracts entered into on or after January 1, 2017, a claim resolution process applicable to any claim by a contractor in connection with a public works project. The bill would define a claim as a separate demand by the contractor for one or more of the following: a time extension for relief from damages or penalties for delay, payment of money or damages arising from work done pursuant to the contract for a public work, or payment of an amount disputed by the public entity, as specified.
This bill would require a public entity, defined to exclude certain state entities, upon receipt of a claim sent by registered or certified mail, to review it and, within 45 days, provide a written statement identifying the disputed and undisputed portions of the claim. The bill would authorize the 45-day period to be extended by mutual agreement. The bill would require any payment due on an undisputed portion of the claim to be processed within 60 days, as specified. The bill would require that the claim be deemed rejected in its entirety if the public entity fails to issue the written statement.
This bill would authorize, if the claimant disputes the public entitys written response or if the public entity fails to respond to a claim within the time prescribed, the claimant to demand to meet and confer for settlement of the issues in dispute. The bill would require any disputed portion of the claim that remains in dispute after the meet and confer conference to be subject to nonbinding mediation, as specified. The bill would provide that unpaid claim amounts accrue interest at 7% per annum. The bill would prescribe a procedure by which a subcontractor or lower tier contractor may make a claim through the contractor.
This bill would require the text of these provisions, or a summary, to be set forth in the plans or specifications for any public work which may give rise to a claim. The bill would specify that a waiver of these rights is void and contrary to public policy, except as specified. The bill would also specify that it does not impose liability on a public entity that makes loans or grants available through a competitive application process, for the failure of an awardee to meet its contractual obligations.
By increasing the duties of local agencies and officials, this bill would impose a state-mandated local program.
This bill would, on January 1, 2020, repeal the provision establishing the claim resolution process.
This bill would specify that these provisions constitute a matter of statewide concern.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that, if the Commission on State Mandates determines that the bill contains costs mandated by the state, reimbursement for those costs shall be made pursuant to these statutory provisions.
Existing law establishes the California Community Colleges under the administration of the Board of Governors of the California Community Colleges. Existing law establishes community college districts, which provide instruction to students at campuses throughout the state.
Existing law provides that, until specified statutory provisions are implemented regarding program-based funding, community college districts that have less than 75% of their hours of credit instruction taught by full-time instructors shall apply a portion of their program improvement allocations toward reaching that 75% standard, as specified. Existing law requires the board of governors to adopt regulations for the effective administration of the law concerning the appropriate percentage of hours of credit instruction taught by full-time instructors. Existing law requires the Chancellor of the California Community Colleges to compute the number of full-time faculty required to be secured using program improvement allocations, as specified, to determine the extent to which each community college district has hired that number of full-time faculty, and, to the extent that the cumulative number of full-time faculty have not been retained, to reduce the districts base budget for 199192 and subsequent fiscal years in accordance with a certain formula.
This bill would require the office of the Chancellor of the California Community Colleges to convene a group of stakeholders on or before July 1, 2016, and every 4 years thereafter, to develop recommendations on funding strategies to enable the community colleges to achieve the 75% standard and increase district participation in the support of part-time faculty. The bill would require the chancellors office to report these recommendations to the Legislature, as specified.
(1)Existing
Existing law establishes the California Community Colleges under the administration of the Board of Governors of the California Community Colleges. Existing law establishes community college districts, which provide instruction to students at campuses throughout the state.
Existing law provides that, until specified statutory provisions are implemented regarding program-based funding, community college districts that have less than 75% of their hours of credit instruction taught by full-time instructors shall apply a portion of their program improvement allocations toward reaching that 75% standard, as specified. Existing law requires the board of governors to adopt regulations for the effective administration of the law concerning the appropriate percentage of hours of credit instruction taught by full-time instructors. Existing law requires the Chancellor of the California Community Colleges to compute the number of full-time faculty required to be secured using program improvement allocations, as specified, to determine the extent to which each community college district has hired that number of full-time faculty, and, to the extent that the cumulative number of full-time faculty have not been retained, to reduce the districts base budget for 199192 and subsequent fiscal years in accordance with a certain formula.
This bill would repeal the requirement to expend a portion of the program improvement allocation to increase the ratio of full-time to part-time faculty and, with respect to community college districts that have not reached the 75% standard referenced above, would require similar expenditures of Student Success and Support Program funds to increase that ratio, and to support part-time faculty. The bill would specify purposes for which allocations of these funds could be made by community college districts that had not reached the 75% standard. To the extent that this provision would impose new duties on community college districts, it would constitute a state-mandated local program.
The bill would express the intent of the Legislature that the board of governors work together with the Academic Senate for California Community Colleges and other relevant entities to develop goals for the full-time to part-time faculty ratio in noncredit education.
(2)The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that, if the Commission on State Mandates determines that the bill contains costs mandated by the state, reimbursement for those costs shall be made pursuant to these statutory provisions.
This bill would require the office of the Chancellor of the California Community Colleges to convene a group of stakeholders on or before July 1, 2016, and every 4 years thereafter, to develop recommendations on funding strategies to enable the community colleges to achieve the 75% standard and increase district participation in the support of part-time faculty. The bill would require the chancellors office to report these recommendations to the Legislature, as specified.
(1)Existing law establishes the California Community Colleges under the administration of the Board of Governors of the California Community Colleges. Existing law establishes community college districts, which provide instruction to students at campuses throughout the state.
Existing law provides that, until specified statutory provisions are implemented regarding program-based funding, community college districts that have less than 75% of their hours of credit instruction taught by full-time instructors shall apply a portion of their program improvement allocations toward reaching that 75% standard, as specified. Existing law requires the board of governors to adopt regulations, as provided, regulations for the effective administration of the law concerning the appropriate percentage of hours of credit instruction taught by full-time instructors. Existing law requires the Chancellor of the California Community Colleges to compute the number of full-time faculty required to be secured using program improvement allocations, as specified, to determine the extent to which each community college district has hired that number of full-time faculty, and, to the extent that the cumulative number of full-time faculty have not been retained, to reduce the districts base budget for 199192 and subsequent fiscal years in accordance with a certain formula.
This bill would repeal the requirement to expend a portion of the program improvement allocation to increase the ratio of full-time to part-time faculty and, with respect to community college districts that have not reached the 75% standard referenced above, would require similar expenditures of Student Success and Support Program funds to increase that ratio, and to support part-time faculty. The bill would specify purposes for which allocations of these funds could be made by community college districts that had not reached the 75% standard. To the extent that this provision would impose new duties on community college districts, it would constitute a state-mandated local program.
The bill would express the intent of the Legislature that the board of governors work together with the Academic Senate for California Community Colleges and other relevant entities to develop goals for the full-time to part-time faculty ratio in noncredit education.
(2)The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that, if the Commission on State Mandates determines that the bill contains costs mandated by the state, reimbursement for those costs shall be made pursuant to these statutory provisions.
Existing
(1)Existing law establishes the California Community Colleges under the administration of the Board of Governors of the California Community Colleges. Existing law establishes community college districts, which provide instruction to students at campuses throughout the state.
Existing law requires the board of governors to adopt regulations that establish minimum standards regarding the percentage of hours of credit instruction to be taught by full-time instructors.
Existing law provides that, until specified statutory provisions are implemented regarding program-based funding, community college districts that have less than 75% of their hours of credit instruction taught by full-time instructors shall apply a portion of their program improvement allocations toward reaching that 75% standard, as specified. Existing law requires the board of governors to adopt regulations, as provided, for the effective administration of the law concerning the appropriate percentage of hours of credit instruction taught by full-time instructors. Existing law requires the Chancellor of the California Community Colleges to compute the number of full-time faculty required to be secured using program improvement allocations, as specified, to determine the extent to which each community college district has hired that number of full-time faculty, and, to the extent that the cumulative number of full-time faculty have not been retained, to reduce the districts base budget for 199192 and subsequent fiscal years in accordance with a certain formula.
This bill would make nonsubstantive changes to that requirement. would repeal the requirement to expend a portion of the program improvement allocation to increase the ratio of full-time to part-time faculty and, with respect to community college districts that have not reached the 75% standard referenced above, would require similar expenditures of Student Success and Support Program funds to increase that ratio. The bill would specify purposes for which allocations of these funds could be made by community college districts that had not reached the 75% standard. To the extent that this provision would impose new duties on community college districts, it would constitute a state-mandated local program.
The bill would express the intent of the Legislature that the board of governors work together with the Academic Senate for California Community Colleges and other relevant entities to develop goals for the full-time to part-time faculty ratio in noncredit education.
(2)The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that, if the Commission on State Mandates determines that the bill contains costs mandated by the state, reimbursement for those costs shall be made pursuant to these statutory provisions.
Existing law establishes the California Community Colleges under the administration of the Board of Governors of the California Community Colleges. Existing law establishes community college districts, which provide instruction to students at campuses throughout the state.
Existing law requires the board of governors to adopt regulations that establish minimum standards regarding the percentage of hours of credit instruction to be taught by full-time instructors.
This bill would make nonsubstantive changes to that requirement.
(a)The Legislature finds and declares that it is in the best interests of the state and its citizens to ensure that all construction business performed on a public works project in the state that is complete and not in dispute is paid in full and in a timely manner.
(b)Notwithstanding any other law, including, but not limited to, Article 7.1 (commencing with Section 10240) of Chapter 1 of Part 2, Chapter 10 (commencing with Section 19100) of Part 2, and Article 1.5 (commencing with Section 20104) of Chapter 1 of Part 3, this section shall apply to any claim by a contractor in connection with a public works project.
(c)For purposes of this section:
(1)Claim means a separate demand by a contractor sent by registered mail or certified mail with return receipt requested, for one or more of the following:
(A)A time extension, including, without limitation, for relief from damages or penalties for delay assessed by a public entity under a contract for a public works project.
(B)Payment by the public entity of money or damages arising from work done by, or on behalf of, the contractor pursuant to the contract for a public works project and payment for which is not otherwise expressly provided or to which the claimant is not otherwise entitled.
(C)Payment of an amount that is disputed by the public entity.
(2)Contractor means any type of contractor within the meaning of Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code who has entered into a direct contract with a public entity for a public works project.
(3)(A)Public entity means, without limitation, except as provided in subparagraph (B), a state agency, department, office, division, bureau, board, or commission, the California State University, the University of California, a city, including a charter city, county, including a charter county, city and county, including a charter city and county, district, special district, public authority, political subdivision, public corporation, or nonprofit transit corporation wholly owned by a public agency and formed to carry out the purposes of the public agency.
(B)Public entity shall not include the following:
(i)The Department of Water Resources as to any project under the jurisdiction of that department.
(ii)The Department of Transportation as to any project under the jurisdiction of that department.
(iii)The Department of Parks and Recreation as to any project under the jurisdiction of that department.
(iv)The Department of Corrections and Rehabilitation with respect to any project under its jurisdiction pursuant to Chapter 11 (commencing with Section 7000) of Title 7 of Part 3 of the Penal Code.
(v)The Military Department as to any project under the jurisdiction of that department.
(vi)The Department of General Services as to all other projects.
(vii)The High-Speed Rail Authority.
(4)Public works project means the erection, construction, alteration, repair, or improvement of any public structure, building, road, or other public improvement of any kind.
(5)Subcontractor means any type of contractor within the meaning of Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code who either is in direct contract with a contractor or is a lower tier subcontractor.
(d)(1)(A)Upon receipt of a claim pursuant to this section, the public entity to which the claim applies shall conduct a reasonable review of the claim and, within a period not to exceed 45 days, shall provide the claimant a written statement identifying what portion of the claim is disputed and what portion is undisputed. Upon receipt of a claim, a public entity and a contractor may, by mutual agreement, extend the time period provided in this subdivision.
(B)The claimant shall furnish reasonable documentation to support the claim.
(C)If the public entity needs approval from its governing body to provide the claimant a written statement identifying the disputed portion and the undisputed portion of the claim, and the governing body does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a claim sent by registered mail or certified mail, return receipt requested, the public entity shall have up to three days following the next duly publicly noticed meeting of the governing body after the 45-day period, or extension, expires to provide the claimant a written statement identifying the disputed portion and the undisputed portion.
(D)Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after the public entity issues its written statement. If the public entity fails to issue a written statement, paragraph (3) shall apply.
(2)(A)If the claimant disputes the public entitys written response, or if the public entity fails to respond to a claim issued pursuant to this section within the time prescribed, the claimant may demand in writing an informal conference to meet and confer for settlement of the issues in dispute. Upon receipt of a demand in writing sent by registered mail or certified mail, return receipt requested, the public entity shall schedule a meet and confer conference within 30 days for settlement of the dispute.
(B)Within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the public entity shall provide the claimant a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after the public entity issues its written statement. Any disputed portion of the claim, as identified by the contractor in writing, shall be submitted to nonbinding mediation, with the public entity and the claimant sharing the associated costs equally. The public entity and claimant shall mutually agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing. If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the claim. Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator. If mediation is unsuccessful, the parts of the claim remaining in dispute shall be subject to applicable procedures outside this section.
(C)For purposes of this section, mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this section.
(D)Unless otherwise agreed to by the public entity and the contractor in writing, the mediation conducted pursuant to this section shall excuse any further obligation under Section 20104.4 to mediate after litigation has been commenced.
(E)This section does not preclude a public entity from requiring arbitration of disputes under private arbitration or the Public Works Contract Arbitration Program, if mediation under this section does not resolve the parties dispute.
(3)Failure by the public entity to respond to a claim from a contractor within the time periods described in this subdivision or to otherwise meet the time requirements of this section shall result in the claim being deemed rejected in its entirety. A claim that is denied by reason of the public entitys failure to have responded to a claim, or its failure to otherwise meet the time requirements of this section, shall not constitute an adverse finding with regard to the merits of the claim or the responsibility or qualifications of the claimant.
(4)Amounts not paid in a timely manner as required by this section shall bear interest at 7 percent per annum.
(5)If a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against a public entity because privity of contract does not exist, the contractor may present to the public entity a claim on behalf of a subcontractor or lower tier subcontractor. A subcontractor may request in writing, either on his or her own behalf or on behalf of a lower tier subcontractor, that the contractor present a claim for work which was performed by the subcontractor or by a lower tier subcontractor on behalf of the subcontractor. The subcontractor requesting that the claim be presented to the public entity shall furnish reasonable documentation to support the claim. Within 45 days of receipt of this written request, the contractor shall notify the subcontractor in writing as to whether the contractor presented the claim to the public entity and, if the original contractor did not present the claim, provide the subcontractor with a statement of the reasons for not having done so.
(e)The text of this section or a summary of it shall be set forth in the plans or specifications for any public works project that may give rise to a claim under this section.
(f)A waiver of the rights granted by this section is void and contrary to public policy, provided, however, that (1) upon receipt of a claim, the parties may mutually agree to waive, in writing, mediation and proceed directly to the commencement of a civil action or binding arbitration, as applicable; and (2) a public entity may prescribe reasonable change order, claim, and dispute resolution procedures and requirements in addition to the provisions of this section, so long as the contractual provisions do not conflict with or otherwise impair the timeframes and procedures set forth in this section.
(g)This section applies to contracts entered into on or after January 1, 2017.
(h)Nothing in this section shall impose liability upon a public entity that makes loans or grants available through a competitive application process, for the failure of an awardee to meet its contractual obligations.
(i)This section shall remain in effect only until January 1, 2020, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2020, deletes or extends that date.
SEC. 2.The Legislature finds and declares that it is of statewide concern to require a charter city, charter county, or charter city and county to follow a prescribed claims resolution process to ensure there are uniform and equitable procurement practices.
SEC. 3.If the Commission on State Mandates determines that this act contains costs mandated by the state, reimbursement to local agencies and school districts for those costs shall be made pursuant to Part 7 (commencing with Section 17500) of Division 4 of Title 2 of the Government Code.
(a)The Legislature finds and declares that it is in the best interests of the state and its citizens to ensure that all construction business performed on a public works project in the state that is complete and not in dispute is paid in full and in a timely manner.
(b)Notwithstanding any other law, including, but not limited to, Article 7.1 (commencing with Section 10240) of Chapter 1 of Part 2, Chapter 10 (commencing with Section 19100) of Part 2, and Article 1.5 (commencing with Section 20104) of Chapter 1 of Part 3, this section shall apply to any claim by a contractor in connection with a public works project.
(c)For purposes of this section:
(1)Claim means a separate demand by a contractor sent by registered mail or certified mail with return receipt requested, for one or more of the following:
(A)A time extension, including, without limitation, for relief from damages or penalties for delay assessed by a public entity under a contract for a public works project.
(B)Payment by the public entity of money or damages arising from work done by, or on behalf of, the contractor pursuant to the contract for a public works project and payment for which is not otherwise expressly provided or to which the claimant is not otherwise entitled.
(C)Payment of an amount that is disputed by the public entity.
(2)Contractor means any type of contractor within the meaning of Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code who has entered into a direct contract with a public entity for a public works project.
(3)(A)Public entity means, without limitation, except as provided in subparagraph (B), a state agency, department, office, division, bureau, board, or commission, the California State University, the University of California, a city, including a charter city, county, including a charter county, city and county, including a charter city and county, district, special district, public authority, political subdivision, public corporation, or nonprofit transit corporation wholly owned by a public agency and formed to carry out the purposes of the public agency.
(B)Public entity shall not include the following:
(i)The Department of Water Resources as to any project under the jurisdiction of that department.
(ii)The Department of Transportation as to any project under the jurisdiction of that department.
(iii)The Department of Parks and Recreation as to any project under the jurisdiction of that department.
(iv)The Department of Corrections and Rehabilitation with respect to any project under its jurisdiction pursuant to Chapter 11 (commencing with Section 7000) of Title 7 of Part 3 of the Penal Code.
(v)The Military Department as to any project under the jurisdiction of that department.
(vi)The Department of General Services as to all other projects.
(vii)The High-Speed Rail Authority.
(4)Public works project means the erection, construction, alteration, repair, or improvement of any public structure, building, road, or other public improvement of any kind.
(5)Subcontractor means any type of contractor within the meaning of Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code who either is in direct contract with a contractor or is a lower tier subcontractor.
(d)(1)(A)Upon receipt of a claim pursuant to this section, the public entity to which the claim applies shall conduct a reasonable review of the claim and, within a period not to exceed 45 days, shall provide the claimant a written statement identifying what portion of the claim is disputed and what portion is undisputed. Upon receipt of a claim, a public entity and a contractor may, by mutual agreement, extend the time period provided in this subdivision.
(B)The claimant shall furnish reasonable documentation to support the claim.
(C)If the public entity needs approval from its governing body to provide the claimant a written statement identifying the disputed portion and the undisputed portion of the claim, and the governing body does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a claim sent by registered mail or certified mail, return receipt requested, the public entity shall have up to three days following the next duly publicly noticed meeting of the governing body after the 45-day period, or extension, expires to provide the claimant a written statement identifying the disputed portion and the undisputed portion.
(D)Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after the public entity issues its written statement. If the public entity fails to issue a written statement, paragraph (3) shall apply.
(2)(A)If the claimant disputes the public entitys written response, or if the public entity fails to respond to a claim issued pursuant to this section within the time prescribed, the claimant may demand in writing an informal conference to meet and confer for settlement of the issues in dispute. Upon receipt of a demand in writing sent by registered mail or certified mail, return receipt requested, the public entity shall schedule a meet and confer conference within 30 days for settlement of the dispute.
(B)Within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the public entity shall provide the claimant a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after the public entity issues its written statement. Any disputed portion of the claim, as identified by the contractor in writing, shall be submitted to nonbinding mediation, with the public entity and the claimant sharing the associated costs equally. The public entity and claimant shall mutually agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing. If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the claim. Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator. If mediation is unsuccessful, the parts of the claim remaining in dispute shall be subject to applicable procedures outside this section.
(C)For purposes of this section, mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this section.
(D)Unless otherwise agreed to by the public entity and the contractor in writing, the mediation conducted pursuant to this section shall excuse any further obligation under Section 20104.4 to mediate after litigation has been commenced.
(E)This section does not preclude a public entity from requiring arbitration of disputes under private arbitration or the Public Works Contract Arbitration Program, if mediation under this section does not resolve the parties dispute.
(3)Failure by the public entity to respond to a claim from a contractor within the time periods described in this subdivision or to otherwise meet the time requirements of this section shall result in the claim being deemed rejected in its entirety. A claim that is denied by reason of the public entitys failure to have responded to a claim, or its failure to otherwise meet the time requirements of this section, shall not constitute an adverse finding with regard to the merits of the claim or the responsibility or qualifications of the claimant.
(4)Amounts not paid in a timely manner as required by this section shall bear interest at 7 percent per annum.
(5)If a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against a public entity because privity of contract does not exist, the contractor may present to the public entity a claim on behalf of a subcontractor or lower tier subcontractor. A subcontractor may request in writing, either on his or her own behalf or on behalf of a lower tier subcontractor, that the contractor present a claim for work which was performed by the subcontractor or by a lower tier subcontractor on behalf of the subcontractor. The subcontractor requesting that the claim be presented to the public entity shall furnish reasonable documentation to support the claim. Within 45 days of receipt of this written request, the contractor shall notify the subcontractor in writing as to whether the contractor presented the claim to the public entity and, if the original contractor did not present the claim, provide the subcontractor with a statement of the reasons for not having done so.
(e)The text of this section or a summary of it shall be set forth in the plans or specifications for any public works project that may give rise to a claim under this section.
(f)A waiver of the rights granted by this section is void and contrary to public policy, provided, however, that (1) upon receipt of a claim, the parties may mutually agree to waive, in writing, mediation and proceed directly to the commencement of a civil action or binding arbitration, as applicable; and (2) a public entity may prescribe reasonable change order, claim, and dispute resolution procedures and requirements in addition to the provisions of this section, so long as the contractual provisions do not conflict with or otherwise impair the timeframes and procedures set forth in this section.
(g)This section applies to contracts entered into on or after January 1, 2017.
(h)Nothing in this section shall impose liability upon a public entity that makes loans or grants available through a competitive application process, for the failure of an awardee to meet its contractual obligations.
(i)This section shall remain in effect only until January 1, 2020, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2020, deletes or extends that date.
SEC. 2.The Legislature finds and declares that it is of statewide concern to require a charter city, charter county, or charter city and county to follow a prescribed claims resolution process to ensure there are uniform and equitable procurement practices.
SEC. 3.If the Commission on State Mandates determines that this act contains costs mandated by the state, reimbursement to local agencies and school districts for those costs shall be made pursuant to Part 7 (commencing with Section 17500) of Division 4 of Title 2 of the Government Code.
(a)The Legislature finds and declares that it is in the best interests of the state and its citizens to ensure that all construction business performed on a public works project in the state that is complete and not in dispute is paid in full and in a timely manner.
(b)Notwithstanding any other law, including, but not limited to, Article 7.1 (commencing with Section 10240) of Chapter 1 of Part 2, Chapter 10 (commencing with Section 19100) of Part 2, and Article 1.5 (commencing with Section 20104) of Chapter 1 of Part 3, this section shall apply to any claim by a contractor in connection with a public works project.
(c)For purposes of this section:
(1)Claim means a separate demand by a contractor sent by registered mail or certified mail with return receipt requested, for one or more of the following:
(A)A time extension, including, without limitation, for relief from damages or penalties for delay assessed by a public entity under a contract for a public works project.
(B)Payment by the public entity of money or damages arising from work done by, or on behalf of, the contractor pursuant to the contract for a public works project and payment for which is not otherwise expressly provided or to which the claimant is not otherwise entitled.
(C)Payment of an amount that is disputed by the public entity.
(2)Contractor means any type of contractor within the meaning of Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code who has entered into a direct contract with a public entity for a public works project.
(3)(A)Public entity means, without limitation, except as provided in subparagraph (B), a state agency, department, office, division, bureau, board, or commission, the California State University, the University of California, a city, including a charter city, county, including a charter county, city and county, including a charter city and county, district, special district, public authority, political subdivision, public corporation, or nonprofit transit corporation wholly owned by a public agency and formed to carry out the purposes of the public agency.
(B)Public entity shall not include the following:
(i)The Department of Water Resources as to any project under the jurisdiction of that department.
(ii)The Department of Transportation as to any project under the jurisdiction of that department.
(iii)The Department of Parks and Recreation as to any project under the jurisdiction of that department.
(iv)The Department of Corrections and Rehabilitation with respect to any project under its jurisdiction pursuant to Chapter 11 (commencing with Section 7000) of Title 7 of Part 3 of the Penal Code.
(v)The Military Department as to any project under the jurisdiction of that department.
(vi)The Department of General Services as to all other projects.
(vii)The High-Speed Rail Authority.
(4)Public works project means the erection, construction, alteration, repair, or improvement of any public structure, building, road, or other public improvement of any kind.
(5)Subcontractor means any type of contractor within the meaning of Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code who either is in direct contract with a contractor or is a lower tier subcontractor.
(d)(1)(A)Upon receipt of a claim pursuant to this section, the public entity to which the claim applies shall conduct a reasonable review of the claim and, within a period not to exceed 45 days, shall provide the claimant a written statement identifying what portion of the claim is disputed and what portion is undisputed. Upon receipt of a claim, a public entity and a contractor may, by mutual agreement, extend the time period provided in this subdivision.
(B)The claimant shall furnish reasonable documentation to support the claim.
(C)If the public entity needs approval from its governing body to provide the claimant a written statement identifying the disputed portion and the undisputed portion of the claim, and the governing body does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a claim sent by registered mail or certified mail, return receipt requested, the public entity shall have up to three days following the next duly publicly noticed meeting of the governing body after the 45-day period, or extension, expires to provide the claimant a written statement identifying the disputed portion and the undisputed portion.
(D)Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after the public entity issues its written statement. If the public entity fails to issue a written statement, paragraph (3) shall apply.
(2)(A)If the claimant disputes the public entitys written response, or if the public entity fails to respond to a claim issued pursuant to this section within the time prescribed, the claimant may demand in writing an informal conference to meet and confer for settlement of the issues in dispute. Upon receipt of a demand in writing sent by registered mail or certified mail, return receipt requested, the public entity shall schedule a meet and confer conference within 30 days for settlement of the dispute.
(B)Within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the public entity shall provide the claimant a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after the public entity issues its written statement. Any disputed portion of the claim, as identified by the contractor in writing, shall be submitted to nonbinding mediation, with the public entity and the claimant sharing the associated costs equally. The public entity and claimant shall mutually agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing. If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the claim. Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator. If mediation is unsuccessful, the parts of the claim remaining in dispute shall be subject to applicable procedures outside this section.
(C)For purposes of this section, mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this section.
(D)Unless otherwise agreed to by the public entity and the contractor in writing, the mediation conducted pursuant to this section shall excuse any further obligation under Section 20104.4 to mediate after litigation has been commenced.
(E)This section does not preclude a public entity from requiring arbitration of disputes under private arbitration or the Public Works Contract Arbitration Program, if mediation under this section does not resolve the parties dispute.
(3)Failure by the public entity to respond to a claim from a contractor within the time periods described in this subdivision or to otherwise meet the time requirements of this section shall result in the claim being deemed rejected in its entirety. A claim that is denied by reason of the public entitys failure to have responded to a claim, or its failure to otherwise meet the time requirements of this section, shall not constitute an adverse finding with regard to the merits of the claim or the responsibility or qualifications of the claimant.
(4)Amounts not paid in a timely manner as required by this section shall bear interest at 7 percent per annum.
(5)If a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against a public entity because privity of contract does not exist, the contractor may present to the public entity a claim on behalf of a subcontractor or lower tier subcontractor. A subcontractor may request in writing, either on his or her own behalf or on behalf of a lower tier subcontractor, that the contractor present a claim for work which was performed by the subcontractor or by a lower tier subcontractor on behalf of the subcontractor. The subcontractor requesting that the claim be presented to the public entity shall furnish reasonable documentation to support the claim. Within 45 days of receipt of this written request, the contractor shall notify the subcontractor in writing as to whether the contractor presented the claim to the public entity and, if the original contractor did not present the claim, provide the subcontractor with a statement of the reasons for not having done so.
(e)The text of this section or a summary of it shall be set forth in the plans or specifications for any public works project that may give rise to a claim under this section.
(f)A waiver of the rights granted by this section is void and contrary to public policy, provided, however, that (1) upon receipt of a claim, the parties may mutually agree to waive, in writing, mediation and proceed directly to the commencement of a civil action or binding arbitration, as applicable; and (2) a public entity in its public works contracts may include dispute resolution provisions that comply with this section, including the timeframes set forth herein, and that prescribe additional reasonable and equitable terms regarding actions or procedures to be taken by the parties. may prescribe reasonable change order, claim, and dispute resolution procedures and requirements in addition to the provisions of this section, so long as the contractual provisions do not conflict with or otherwise impair the timeframes and procedures set forth in this section.
(g)This section applies to contracts entered into on or after January 1, 2017.
(h)Nothing in this section shall impose liability upon a public entity that makes loans or grants available through a competitive application process, for the failure of an awardee to meet its contractual obligations.
(i)This section shall remain in effect only until January 1, 2020, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2020, deletes or extends that date.
SEC. 2.The Legislature finds and declares that it is of statewide concern to require a charter city, charter county, or charter city and county to follow a prescribed claims resolution process to ensure there are uniform and equitable procurement practices.
SEC. 3.If the Commission on State Mandates determines that this act contains costs mandated by the state, reimbursement to local agencies and school districts for those costs shall be made pursuant to Part 7 (commencing with Section 17500) of Division 4 of Title 2 of the Government Code.
(a)The Legislature finds and declares that it is in the best interests of the state and its citizens to ensure that all construction business performed on a public works project in the state that is complete and not in dispute is paid in full and in a timely manner.
(b)Notwithstanding any other law, including, but not limited to, Article 7.1 (commencing with Section 10240) of Chapter 1 of Part 2, Chapter 10 (commencing with Section 19100) of Part 2, and Article 1.5 (commencing with Section 20104) of Chapter 1 of Part 3, this section shall apply to any claim by a contractor in connection with a public works project.
(c)For purposes of this section:
(1)Claim means a separate demand by a contractor sent by registered mail or certified mail with return receipt requested, for one or more of the following:
(A)A time extension, including, without limitation, for relief from damages or penalties for delay assessed by a public entity under a contract for a public works project.
(B)Payment by the public entity of money or damages arising from work done by, or on behalf of, the contractor pursuant to the contract for a public works project and payment for which is not otherwise expressly provided or to which the claimant is not otherwise entitled.
(C)Payment of an amount that is disputed by the public entity.
(2)Contractor means any type of contractor within the meaning of Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code who has entered into a direct contract with a public entity for a public works project.
(3)(A)Public entity means, without limitation, except as provided in subparagraph (B), a state agency, department, office, division, bureau, board, or commission, the California State University, the University of California, a city, including a charter city, county, including a charter county, city and county, including a charter city and county, district, special district, public authority, political subdivision, public corporation, or nonprofit transit corporation wholly owned by a public agency and formed to carry out the purposes of the public agency.
(B)Public entity shall not include the following:
(i)The Department of Water Resources as to any project under the jurisdiction of that department.
(ii)The Department of Transportation as to any project under the jurisdiction of that department.
(iii)The Department of Parks and Recreation as to any project under the jurisdiction of that department.
(iv)The Department of Corrections and Rehabilitation with respect to any project under its jurisdiction pursuant to Chapter 11 (commencing with Section 7000) of Title 7 of Part 3 of the Penal Code.
(v)The Military Department as to any project under the jurisdiction of that department.
(vi)The Department of General Services as to all other projects.
(vii)The High-Speed Rail Authority.
(4)Public works project means the erection, construction, alteration, repair, or improvement of any public structure, building, road, or other public improvement of any kind.
(5)Subcontractor means any type of contractor within the meaning of Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code who either is in direct contract with a contractor or is a lower tier subcontractor.
(d)(1)(A)Upon receipt of a claim pursuant to this section, the public entity to which the claim applies shall conduct a reasonable review of the claim and, within a period not to exceed 45 days, shall provide the claimant a written statement identifying what portion of the claim is disputed and what portion is undisputed. Upon receipt of a claim, a public entity and a contractor may, by mutual agreement, extend the time period provided in this subdivision.
(B)The claimant shall furnish reasonable documentation to support the claim.
(C)If the public entity needs approval from its governing body to provide the claimant a written statement identifying the disputed portion and the undisputed portion of the claim, and the governing body does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a claim sent by registered mail or certified mail, return receipt requested, the public entity shall have up to three days following the next duly publicly noticed meeting of the governing body after the 45-day period, or extension, expires to provide the claimant a written statement identifying the disputed portion and the undisputed portion.
(D)Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after the public entity issues its written statement. If the public entity fails to issue a written statement, paragraph (3) shall apply.
(2)(A)If the claimant disputes the public entitys written response, or if the public entity fails to respond to a claim issued pursuant to this section within the time prescribed, the claimant may demand in writing an informal conference to meet and confer for settlement of the issues in dispute. Upon receipt of a demand in writing sent by registered mail or certified mail, return receipt requested, the public entity shall schedule a meet and confer conference within 30 days for settlement of the dispute.
(B)Within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the public entity shall provide the claimant a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after the public entity issues its written statement. Any disputed portion of the claim, as identified by the contractor in writing, shall be submitted to nonbinding mediation, with the public entity and the claimant sharing the associated costs equally. The public entity and claimant shall mutually agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing. If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the claim. Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator. If mediation is unsuccessful, the parts of the claim remaining in dispute shall be subject to applicable procedures outside this section.
(C)For purposes of this section, mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this section.
(D)Unless otherwise agreed to by the public entity and the contractor in writing, the mediation conducted pursuant to this section shall excuse any further obligation under Section 20104.4 to mediate after litigation has been commenced.
(E)This section does not preclude a public entity from requiring arbitration of disputes under private arbitration or the Public Works Contract Arbitration Program, if mediation under this section does not resolve the parties dispute.
(3)Failure by the public entity to respond to a claim from a contractor within the time periods described in this subdivision or to otherwise meet the time requirements of this section shall result in the claim being deemed rejected in its entirety. A claim that is denied by reason of the public entitys failure to have responded to a claim, or its failure to otherwise meet the time requirements of this section, shall not constitute an adverse finding with regard to the merits of the claim or the responsibility or qualifications of the claimant.
(4)Amounts not paid in a timely manner as required by this section shall bear interest at 7 percent per annum.
(5)If a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against a public entity because privity of contract does not exist, the contractor may present to the public entity a claim on behalf of a subcontractor or lower tier subcontractor. A subcontractor may request in writing, either on his or her own behalf or on behalf of a lower tier subcontractor, that the contractor present a claim for work which was performed by the subcontractor or by a lower tier subcontractor on behalf of the subcontractor. The subcontractor requesting that the claim be presented to the public entity shall furnish reasonable documentation to support the claim. Within 45 days of receipt of this written request, the contractor shall notify the subcontractor in writing as to whether the contractor presented the claim to the public entity and, if the original contractor did not present the claim, provide the subcontractor with a statement of the reasons for not having done so.
(e)The text of this section or a summary of it shall be set forth in the plans or specifications for any public works project that may give rise to a claim under this section.
(f)A waiver of the rights granted by this section is void and contrary to public policy, provided, however, that (1) upon receipt of a claim, the parties may mutually agree to waive, in writing, mediation and proceed directly to the commencement of a civil action or binding arbitration, as applicable; and (2) a public entity in its public works contracts may include dispute resolution provisions that comply with this section, including the timeframes set forth herein, and that prescribe additional reasonable and equitable terms regarding actions or procedures to be taken by the parties.
(g)This section applies to contracts entered into on or after January 1, 2017.
(h)Nothing in this section shall impose liability upon a public entity that makes loans or grants available through a competitive application process, for the failure of an awardee to meet its contractual obligations.
(i)This section shall remain in effect only until January 1, 2020, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2020, deletes or extends that date.
SEC. 2.The Legislature finds and declares that it is of statewide concern to require a charter city, charter county, or charter city and county to follow a prescribed claims resolution process to ensure there are uniform and equitable procurement practices.
SEC. 3.If the Commission on State Mandates determines that this act contains costs mandated by the state, reimbursement to local agencies and school districts for those costs shall be made pursuant to Part 7 (commencing with Section 17500) of Division 4 of Title 2 of the Government Code.
SECTION 1.The Legislature finds and declares all of the following:
(a)In 1988, the Education Code was amended to read that the Legislature wishes to recognize and make efforts to address longstanding policy of the board of governors that at least 75 percent of the hours of credit instruction in the California Community Colleges, as a system, should be taught by full-time instructors.
(b)The expectations for full-time faculty go beyond classroom instruction to include, among other full-service activities, all of the following: developing and evaluating academic programs; holding office hours and participating in meetings after classes; student advising; participation in institutional governance; and accreditation-related responsibilities such as the assessment of departmental and student learning outcomes, curriculum development, and preparing institutional self-studies.
(c)In 2014, the percentage of credit courses taught by full-time faculty in the system was only 56.14 percent.
(d)The Legislature acknowledged the commitment of the Board of Governors of the California Community Colleges, through its regular budget process, to evaluate resource needs and seek funding for essential educational priorities that contribute to student success. These priorities include, but are not necessarily limited to, the hiring of more full-time faculty and increasing support for part-time faculty.
(e)In the Seymour-Campbell Student Success Act of 2012, the Legislature acknowledged the importance of counselors, who, along with librarians, are considered to be faculty for purposes of the 75-percent goal.
(f)Students enrolled in noncredit education are most often deprived of the benefit of working with full-time faculty, as statewide goals relating to the ratio of full-time to part-time faculty have yet to be developed with respect to noncredit courses.
SEC. 2.Section 87482.6 of the Education Code is amended to read:87482.6.(a)Until the provisions of Section 84750.5 regarding program-based funding are implemented by a standard adopted by the board of governors that establishes the appropriate percentage of hours of credit instruction that should be taught by full-time instructors, the Legislature wishes to recognize and make efforts to address longstanding policy of the board of governors that at least 75 percent of the hours of credit instruction in the California Community Colleges, as a system, should be taught by full-time instructors. To this end, community college districts that have less than 75 percent of their hours of credit instruction taught by full-time instructors shall apply a portion of the program improvement allocation received pursuant to Section 84755 as follows:
(1)Districts that, in the prior fiscal year, had between 67 percent and 75 percent of their hours of credit instruction taught by full-time instructors shall apply up to 33 percent of this allocation as necessary to reach the 75-percent standard. If a district in this category chooses instead not to improve its percentage, the board of governors shall withhold 33 percent of this allocation.
(2)Districts that, in the prior fiscal year, had less than 67 percent of their hours of credit instruction taught by full-time instructors shall apply up to 40 percent of this allocation as necessary to reach the 75-percent standard. If a district in this category chooses instead not to improve its percentage, the board of governors shall withhold 40 percent of this allocation.
(3)Districts that maintain 75 percent or more of their hours of credit instruction taught by full-time instructors shall otherwise be free to use their program improvement allocation for any of the purposes specified in Section 84755.
(b)The board of governors shall adopt regulations for the effective administration of this section. Unless and until amended by the board of governors, the regulations shall provide as follows:
(1)In computing the percentage of hours of credit instruction taught by full-time instructors, the hours of overload teaching by full-time instructors shall be excluded from both the total hours of credit instruction taught by full-time and part-time instructors and the total hours of instruction taught by full-time instructors.
(2)A full-time instructor shall be defined as any regular and contract faculty member teaching credit instruction.
(3)(A)The chancellor shall compute and report to each community college district the number of full-time faculty (FTF) which are to be secured through the use of the prescribed portion of program improvement revenue allocated to each district. This computation shall be made by dividing the applicable portion of program improvement revenue (0 percent, 33 percent, or 40 percent of the program improvement allocation), by the statewide average replacement cost (a figure which represents the statewide average faculty salary plus benefits, minus the statewide average hourly rate of compensation for part-time instructors times the statewide average full-time teaching load). If the quotient is not a whole number, then the quotient shall be rounded down to the nearest whole number. If this quotient, once applied, will result in the district exceeding the 75-percent standard, the chancellor shall further reduce the quotient to a whole number that will leave the district as close as possible to, but in excess of, the 75-percent standard.
(B)By March 15 of each year, the chancellor shall report to each district an estimate of the number of FTF to be secured based upon the appropriation of revenues contained in the annual Budget Bill.
(4)On or before December 31, 1991, the chancellor shall determine the extent to which each district, by September 30, 1991, has hired the number of FTF determined pursuant to paragraph (3) for the 198990 and 199091 fiscal years. To the extent that the cumulative number of FTF have not been retained, the chancellor shall reduce the districts base budget for 199192 and subsequent fiscal years by an amount equivalent to the average replacement cost times the deficiency in the number of FTF.
(c)The office of the Chancellor of the California Community Colleges shall convene a group of stakeholders, which shall include faculty and students, on or before July 1, 2016, and every four years thereafter, to develop recommendations on funding strategies to enable the community colleges to achieve the 75-percent standard and increase the participation of districts in the support of part-time faculty, including, but not limited to, support of part-time faculty office hours. The office of the chancellor shall report the recommendations developed by the stakeholder group to the Legislature, as provided in Section 9795 of the Government Code, on or before March 1, 2017, and every four years thereafter.
SEC. 3.It is the intent of the Legislature that the office of the Chancellor of the California Community Colleges work together with the Academic Senate for California Community Colleges and other relevant entities to develop goals for the full-time to part-time faculty ratio in noncredit education.
The Legislature finds and declares all of the following:
(a)In 1988, the Education Code was amended to read that the Legislature wishes to recognize and make efforts to address longstanding policy of the board of governors that at least 75 percent of the hours of credit instruction in the California Community Colleges, as a system, should be taught by full-time instructors.
(b)The expectations for full-time faculty go beyond classroom instruction to include, among other full-service activities, all of the following: developing and evaluating academic programs; holding office hours and participating in meetings after classes; student advising; participation in institutional governance; and accreditation-related responsibilities such as the assessment of departmental and student learning outcomes, curriculum development, and preparing institutional self-studies.
(c)In 2014, the percentage of credit courses taught by full-time faculty in the system was only 56.14 percent.
(d)The Legislature acknowledged the commitment of the Board of Governors of the California Community Colleges, through its regular budget process, to evaluate resource needs and seek funding for essential educational priorities that contribute to student success. These priorities include, but are not necessarily limited to, the hiring of more full-time faculty and increasing support for part-time faculty.
(e)In the Seymour-Campbell Student Success Act of 2012, the Legislature acknowledged the importance of counselors, who, along with librarians, are considered to be faculty for purposes of the 75-percent goal.
(f)Students enrolled in noncredit education are most often deprived of the benefit of working with full-time faculty, as statewide goals relating to the ratio of full-time to part-time faculty have yet to be developed with respect to noncredit courses.
SEC. 2.Section 87482.6 of the Education Code is amended to read:87482.6.(a)Until the provisions of Section 84750 84750.5 regarding program-based funding are implemented by a standard adopted by the board of governors that establishes the appropriate percentage of hours of credit instruction that should be taught by full-time instructors, the Legislature wishes to recognize and make efforts to address longstanding policy of the board of governors that at least 75 percent of the hours of credit instruction in the California Community Colleges, as a system, should be taught by full-time instructors. To this end, community college districts which that have less than 75 percent of their hours of credit instruction taught by full-time instructors shall apply a portion of the program improvement allocation received pursuant to Section 84755 as follows:
(1)Districts which, that, in the prior fiscal year, had between 67 percent and 75 percent of their hours of credit instruction taught by full-time instructors shall apply up to 33 percent of their program improvement this allocation as necessary to reach the 75 percent 75-percent standard. If a district in this category chooses instead not to improve its percentage, the board of governors shall withhold 33 percent of the districts program improvement this allocation.
(2)Districts which, that, in the prior fiscal year, had less than 67 percent of their hours of credit instruction taught by full-time instructors shall apply up to 40 percent of their program improvement this allocation as necessary to reach the 75 percent 75-percent standard. If a district in this category chooses instead not to improve its percentage, the board of governors shall withhold 40 percent of the districts program improvement this allocation.
Districts which
(3)Districts that maintain 75 percent or more of their hours of credit instruction taught by full-time instructors shall otherwise be free to use their program improvement allocation for any of the purposes specified in Section 84755.
(b)The board of governors shall adopt regulations for the effective administration of this section. Unless and until amended by the board of governors, the regulations shall provide as follows:
(1)In computing the percentage of hours of credit instruction taught by full-time instructors, the hours of overload teaching by full-time instructors shall be excluded from both the total hours of credit instruction taught by full-time and part-time instructors and the total hours of instruction taught by full-time instructors.
(2)A full-time instructor shall be defined as any regular and contract faculty member teaching credit instruction.
(3)(A)The chancellor shall compute and report to each community college district the number of full-time faculty (FTF) which are to be secured through the use of the prescribed portion of program improvement revenue allocated to each district. This computation shall be made by dividing the applicable portion of program improvement revenue (0 percent, 33 percent, or 40 percent of the program improvement allocation), by the statewide average replacement cost (a figure which represents the statewide average faculty salary plus benefits, minus the statewide average hourly rate of compensation for part-time instructors times the statewide average full-time teaching load). If the quotient is not a whole number, then the quotient shall be rounded down to the nearest whole number. If this quotient, once applied, will result in the district exceeding the 75 percent 75-percent standard, the chancellor shall further reduce the quotient to a whole number that will leave the district as close as possible to, but in excess of, the 75 percent 75-percent standard.
By
(B)By March 15th 15 of each year, the chancellor shall report to each district an estimate of the number of FTF to be secured based upon the appropriation of revenues contained in the annual Budget Bill.
(4)On or before December 31, 1991, the chancellor shall determine the extent to which each district, by September 30, 1991, has hired the number of FTF determined pursuant to paragraph (3) for the 198990 and 199091 fiscal years. To the extent that the cumulative number of FTF have not been retained, the chancellor shall reduce the districts base budget for 199192 and subsequent fiscal years by an amount equivalent to the average replacement cost times the deficiency in the number of FTF.
(c)The office of the Chancellor of the California Community Colleges shall convene a group of stakeholders, which shall include faculty and students, on or before July 1, 2016, and every four years thereafter, to develop recommendations on funding strategies to enable the community colleges to achieve the 75-percent standard and increase the participation of districts in the support of part-time faculty, including, but not limited to, support of part-time faculty office hours. The office of the chancellor shall report the recommendations developed by the stakeholder group to the Legislature, as provided in Section 9795 of the Government Code, on or before March 1, 2017, and every four years thereafter.
SEC. 3.It is the intent of the Legislature that the office of the Chancellor of the California Community Colleges work together with the Academic Senate for California Community Colleges and other relevant entities to develop goals for the full-time to part-time faculty ratio in noncredit education.
SEC. 2.Section 87482.6 of the Education Code is amended to read:87482.6.(a)It has long been the intent of the Legislature to improve the equity and predictability of community college funding in order to enhance the ability of both the full-time and part-time faculty of the California Community Colleges to provide high-quality instructional services.
(b)Notwithstanding any other law, until the provisions of Section 84750.5 regarding program-based funding are implemented by a standard adopted by the board of governors that establishes the appropriate percentage of hours of credit instruction that should be taught by full-time instructors, the Legislature wishes to recognize and make efforts to address longstanding policy of the board of governors that at least 75 percent of the hours of credit instruction in the California Community Colleges, as a system, should be taught by full-time instructors. To this end, community college districts that have less than 75 percent of their hours of credit instruction taught by full-time instructors shall be subject to both of the following:
(1)In a fiscal year when funds are specifically appropriated for purposes of the Student Success and Support Program under Article 1 (commencing with Section 78210) of Chapter 2 of Part 48, and in which funds have not been specifically designated to increase the ratio of full-time faculty to part-time faculty, and to support part-time faculty, in programs, which may include but are not necessarily limited to, the Community College Part-Time Faculty Office Hours Program established by Article 10 (commencing with Section 87880), one-half of the amount of the district match requirement under subdivision (b) of Section 78216 shall be allocated in the following manner:
(A)Districts that, in the prior fiscal year, had between 67 percent and 75 percent of their hours of credit instruction taught by full-time instructors shall apply up to 33 percent of this allocation as necessary to reach the 75 percent standard. Districts that, in the prior fiscal year, had less than 67 percent of their hours of credit instruction taught by full-time instructors shall apply up to 40 percent of this allocation as necessary to reach the 75 percent standard.
(B)The funds remaining after allocations are made pursuant to subparagraph (A) shall, to the extent feasible, and in a manner consistent with an applicable collective bargaining agreement, be divided between expenditures in support of functions performed by full-time faculty and expenditures in support of functions performed by part-time faculty, with the allocations for part-time faculty support used, to the extent feasible, for the funding of the participation of part-time faculty in areas that contribute to student success, which may include office hours, as determined locally.
(2)Notwithstanding paragraph (1), in a fiscal year when funds are specifically appropriated for purposes of the Student Success and Support Program under Article 1 (commencing with Section 78210) of Chapter 2 of Part 48, and in which funds have not been specifically designated to increase the ratio of full-time faculty to part-time faculty, and to support part-time faculty, in programs which may include, but are not necessarily limited to, the Community College Part-time Faculty Office Hours Program established by Article 10 (commencing with Section 87880), but in which, notwithstanding subdivision (b) of Section 78216, there is no district matching requirement, one-half of the Student Success and Support Program funds received by the district shall be allocated as indicated in subparagraphs (A) and (B) of paragraph (1).
(3)Once a district has achieved the goal of at least 75 percent of credit instruction hours being taught by full-time faculty, with part-time faculty being fully supported for those activities that contribute to student success as determined locally, the district may use the funds referenced in paragraphs (1) and (2) for other purposes that are consistent with the Student Success and Support Program.
(c)The board of governors shall adopt regulations for the effective administration of this section. Unless and until amended by the board of governors, the regulations shall provide as follows:
(1)In computing the percentage of hours of credit instruction taught by full-time instructors, the hours of overload teaching by full-time instructors shall be excluded from both the total hours of credit instruction taught by full-time and part-time instructors and the total hours of instruction taught by full-time instructors.
(2)A full-time instructor shall be defined as any regular and contract faculty member teaching credit instruction.
(3)The chancellor shall compute and report to each community college district the number of full-time faculty (FTF) which are to be secured through the use of the prescribed portion of the Student Success and Support Program revenue allocated to each district, or district matching funds, as applicable. This computation shall be made by dividing the revenue required to be expended pursuant to paragraph (1) or (2) of subdivision (b) by the statewide average replacement cost (a figure which represents the statewide average faculty salary plus benefits, minus the statewide average hourly rate of compensation for part-time instructors times the statewide average full-time teaching load). If the quotient is not a whole number, then the quotient shall be rounded down to the nearest whole number. If this quotient, once applied, will result in the district exceeding the 75 percent standard, the chancellor shall further reduce the quotient to a whole number that will leave the district as close as possible to, but in excess of, the 75 percent standard.
(4)By March 15 of each year, the chancellor shall report to each district an estimate of the number of FTF to be secured based upon the appropriation of revenues contained in the annual Budget Bill and the district match requirement.
(5)On or before December 31, 1991, the chancellor shall determine the extent to which each district, by September 30, 1991, has hired the number of FTF determined pursuant to paragraph (3) for the 198990 and 199091 fiscal years. To the extent that the cumulative number of FTF have not been retained, the chancellor shall reduce the districts base budget for 199192 and subsequent fiscal years by an amount equivalent to the average replacement cost times the deficiency in the number of FTF.
(d)It is the intent of the Legislature that the board of governors work together with the Academic Senate for California Community Colleges and other relevant entities to develop goals for the full-time to part-time faculty ratio in noncredit education.
SEC. 3.If the Commission on State Mandates determines that this act contains costs mandated by the state, reimbursement to local agencies and school districts for those costs shall be made pursuant to Part 7 (commencing with Section 17500) of Division 4 of Title 2 of the Government Code.
The Legislature finds and declares all of the following:
(a)In 1988, the Education Code was amended to read that the Legislature wishes to recognize and make efforts to address longstanding policy of the board of governors that at least 75 percent of the hours of credit instruction in the California Community Colleges, as a system, should be taught by full-time instructors.
(b)The expectations for full-time faculty go beyond classroom instruction to include, among other full-service activities, all of the following: developing and evaluating academic programs; holding office hours and participating in meetings after classes; student advising; participation in institutional governance; and accreditation-related responsibilities such as the assessment of departmental and student learning outcomes, curriculum development, and preparing institutional self-studies.
(c)In 2013, 2014, the percentage of credit courses taught by full-time faculty in the system was only 56.14 percent.
(d)The Legislature acknowledged the commitment of the Board of Governors of the California Community Colleges, through its regular budget process, to evaluate resource needs and seek funding for essential educational priorities that contribute to student success. These priorities include, but are not necessarily limited to, the hiring of more full-time faculty and increasing support for part-time faculty.
(e)In the Seymour-Campbell Student Success Act of 2012, the Legislature acknowledged the importance of counselors, who, along with librarians, are considered to be faculty for purposes of the 75-percent goal.
(f)Students enrolled in noncredit education are most often deprived of the benefit of working with full-time faculty, as statewide goals relating to the ratio of full-time to part-time faculty have yet to be developed with respect to noncredit courses.
SEC. 2.Section 87482.6 of the Education Code is amended to read:87482.6.(a)It has long been the intent of the Legislature to improve the equity and predictability of community college funding in order to enhance the ability of both the full-time and part-time faculty of the California Community Colleges to provide high-quality instructional services.
(b)Notwithstanding any other law, until the provisions of Section 84750.5 regarding program-based funding are implemented by a standard adopted by the board of governors that establishes the appropriate percentage of hours of credit instruction that should be taught by full-time instructors, the Legislature wishes to recognize and make efforts to address longstanding policy of the board of governors that at least 75 percent of the hours of credit instruction in the California Community Colleges, as a system, should be taught by full-time instructors. To this end, community college districts that have less than 75 percent of their hours of credit instruction taught by full-time instructors shall be subject to both of the following:
(1)In a fiscal year when funds are specifically appropriated for purposes of the Student Success and Support Program under Article 1 (commencing with Section 78210) of Chapter 2 of Part 48, and in which no funds have not been specifically designated to increase the ratio of full-time faculty to part-time faculty, and to support part-time faculty, in programs including, which may include but are not necessarily limited to, the Community College Part-Time Faculty Office Hours Program established by Article 10 (commencing with Section 87880), one-half of the amount of the district match requirement under subdivision (b) of Section 78216 shall be allocated in the following manner:
(A)Districts that, in the prior fiscal year, had between 67 percent and 75 percent of their hours of credit instruction taught by full-time instructors shall apply up to 33 percent of this allocation as necessary to reach the 75 percent standard. Districts that, in the prior fiscal year, had less than 67 percent of their hours of credit instruction taught by full-time instructors shall apply up to 40 percent of this allocation as necessary to reach the 75 percent standard.
(B)The funds remaining after allocations are made pursuant to subparagraph (A) shall, to the extent feasible, and in a manner consistent with an applicable collective bargaining agreement, be divided equally between expenditures in support of functions performed by full-time faculty and expenditures in support of functions performed by part-time faculty, with the allocations for part-time faculty support used, to the extent feasible, for the funding of the participation of part-time faculty in office hours areas that contribute to student success, which may include office hours, as determined locally.
(2)Notwithstanding paragraph (1), in a fiscal year when funds are specifically appropriated for purposes of the Student Success and Support Program under Article 1 (commencing with Section 78210) of Chapter 2 of Part 48, and in which no funds have not been specifically designated to increase the ratio of full-time faculty to part-time faculty, and to support part-time faculty, in programs including which may include, but are not necessarily limited to, the Community College Part-time Faculty Office Hours Program established by Article 10 (commencing with Section 87880), but in which, notwithstanding subdivision (b) of Section 78216, there is no district matching requirement, one-half of the Student Success and Support Program funds received by the district shall be allocated as indicated in subparagraphs (A) and (B) of paragraph (1).
(3)Once a district has achieved the goal of at least 75 percent of credit instruction hours being taught by full-time faculty, with part-time faculty being fully supported for those activities that contribute to student success as determined locally, the district may use the funds referenced in paragraphs (1) and (2) for other purposes that are consistent with the Student Success and Support Program.
(c)The board of governors shall adopt regulations for the effective administration of this section. Unless and until amended by the board of governors, the regulations shall provide as follows:
(1)In computing the percentage of hours of credit instruction taught by full-time instructors, the hours of overload teaching by full-time instructors shall be excluded from both the total hours of credit instruction taught by full-time and part-time instructors and the total hours of instruction taught by full-time instructors.
(2)A full-time instructor shall be defined as any regular and contract faculty member teaching credit instruction.
(3)The chancellor shall compute and report to each community college district the number of full-time faculty (FTF) which are to be secured through the use of the prescribed portion of the Student Success and Support Program revenue allocated to each district, or district matching funds, as applicable. This computation shall be made by dividing the revenue required to be expended pursuant to paragraph (1) or (2) of subdivision (b) by the statewide average replacement cost (a figure which represents the statewide average faculty salary plus benefits, minus the statewide average hourly rate of compensation for part-time instructors times the statewide average full-time teaching load). If the quotient is not a whole number, then the quotient shall be rounded down to the nearest whole number. If this quotient, once applied, will result in the district exceeding the 75 percent standard, the chancellor shall further reduce the quotient to a whole number that will leave the district as close as possible to, but in excess of, the 75 percent standard.
(4)By March 15 of each year, the chancellor shall report to each district an estimate of the number of FTF to be secured based upon the appropriation of revenues contained in the annual Budget Bill and the district match requirement.
(5)On or before December 31, 1991, the chancellor shall determine the extent to which each district, by September 30, 1991, has hired the number of FTF determined pursuant to paragraph (3) for the 198990 and 199091 fiscal years. To the extent that the cumulative number of FTF have not been retained, the chancellor shall reduce the districts base budget for 199192 and subsequent fiscal years by an amount equivalent to the average replacement cost times the deficiency in the number of FTF.
(d)It is the intent of the Legislature that the board of governors work together with the Academic Senate for California Community Colleges and other relevant entities to develop goals for the full-time to part-time faculty ratio in noncredit education.
SEC. 3.If the Commission on State Mandates determines that this act contains costs mandated by the state, reimbursement to local agencies and school districts for those costs shall be made pursuant to Part 7 (commencing with Section 17500) of Division 4 of Title 2 of the Government Code.
The Legislature finds and declares all of the following:
(a)In 1988, the Education Code was amended to read that the Legislature wishes to recognize and make efforts to address longstanding policy of the board of governors that at least 75 percent of the hours of credit instruction in the California Community Colleges, as a system, should be taught by full-time instructors.
(b)The expectations for full-time faculty go beyond classroom instruction to include, among other full-service activities, all of the following: developing and evaluating academic programs; holding office hours and participating in meetings after classes; student advising; participation in institutional governance; and accreditation-related responsibilities such as the assessment of departmental and student learning outcomes, curriculum development, and preparing institutional self-studies.
(c)In 2013, the percentage of credit courses taught by full-time faculty in the system was only 56.14 percent.
(d)The Legislature acknowledged the commitment of the Board of Governors of the California Community Colleges, through its regular budget process, to evaluate resource needs and seek funding for essential educational priorities that contribute to student success. These priorities include, but are not necessarily limited to, the hiring of more full-time faculty and increasing support for part-time faculty.
(e)In the Seymour-Campbell Student Success Act of 2012, the Legislature acknowledged the importance of counselors, who, along with librarians, are considered to be faculty for purposes of the 75-percent goal.
(f)Students enrolled in noncredit education are most often deprived of the benefit of working with full-time faculty, as statewide goals relating to the ratio of full-time to part-time faculty have yet to be developed with respect to noncredit courses.
SEC. 2.Section 87482.6 of the Education Code is amended to read:87482.6.(a)Until It has long been the intent of the Legislature to improve the equity and predictability of community college funding in order to enhance the ability of both the full-time and part-time faculty of the California Community Colleges to provide high-quality instructional services.
(b)Notwithstanding any other law, until the provisions of Section 84750 84750.5 regarding program-based funding are implemented by a standard adopted by the board of governors that establishes the appropriate percentage of hours of credit instruction that should be taught by full-time instructors, the Legislature wishes to recognize and make efforts to address longstanding policy of the board of governors that at least 75 percent of the hours of credit instruction in the California Community Colleges, as a system, should be taught by full-time instructors. To this end, community college districts which that have less than 75 percent of their hours of credit instruction taught by full-time instructors shall apply a portion of the program improvement allocation received pursuant to Section 84755 as follows: be subject to both of the following:
(1)In a fiscal year when funds are specifically appropriated for purposes of the Student Success and Support Program under Article 1 (commencing with Section 78210) of Chapter 2 of Part 48, and in which no funds have been specifically designated to increase the ratio of full-time faculty to part-time faculty in programs including but not necessarily limited to, the Community College Part-Time Faculty Office Hours Program established by Article 10 (commencing with Section 87880), one-half of the amount of the district match requirement under subdivision (b) of Section 78216 shall be allocated in the following manner:
(1)
(A)Districts which, that, in the prior fiscal year, had between 67 percent and 75 percent of their hours of credit instruction taught by full-time instructors shall apply up to 33 percent of their program improvement this allocation as necessary to reach the 75 percent standard. If a district in this category chooses instead not to improve its percentage, the board of governors shall withhold 33 percent of the districts program improvement allocation. Districts that, in the prior fiscal year, had less than 67 percent of their hours of credit instruction taught by full-time instructors shall apply up to 40 percent of this allocation as necessary to reach the 75 percent standard.
(2)Districts which, in the prior fiscal year, had less than 67 percent of their hours of credit instruction taught by full-time instructors shall apply up to 40 percent of their program improvement allocation as necessary to reach the 75 percent standard. If a district in this category chooses instead not to improve its percentage, the board of governors shall withhold 40 percent of the districts program improvement allocation.
Districts which maintain 75 percent or more of their hours of credit instruction taught by full-time instructors shall otherwise be free to use their program improvement allocation for any of the purposes specified in Section 84755.
(B)The funds remaining after allocations are made pursuant to subparagraph (A) shall, to the extent feasible, and in a manner consistent with an applicable collective bargaining agreement, be divided equally between expenditures in support of functions performed by full-time faculty and expenditures in support of functions performed by part-time faculty, with the allocations for part-time faculty support used, to the extent feasible, for the funding of the participation of part-time faculty in office hours.
(2)Notwithstanding paragraph (1), in a fiscal year when funds are specifically appropriated for purposes of the Student Success and Support Program under Article 1 (commencing with Section 78210) of Chapter 2 of Part 48, and in which no funds have been specifically designated to increase the ratio of full-time faculty to part-time faculty in programs including but not necessarily limited to, the Community College Part-time Faculty Office Hours Program established by Article 10 (commencing with Section 87880), but in which, notwithstanding subdivision (b) of Section 78216, there is no district matching requirement, one-half of the Student Success and Support Program funds received by the district shall be allocated as indicated in subparagraphs (A) and (B) of paragraph (1).
(3)Once a district has achieved the goal of at least 75 percent of credit instruction hours being taught by full-time faculty, with part-time faculty being fully supported for those activities that contribute to student success as determined locally, the district may use the funds referenced in paragraphs (1) and (2) for other purposes that are consistent with the Student Success and Support Program.
(b)
(c)The board of governors shall adopt regulations for the effective administration of this section. Unless and until amended by the board of governors, the regulations shall provide as follows:
(1)In computing the percentage of hours of credit instruction taught by full-time instructors, the hours of overload teaching by full-time instructors shall be excluded from both the total hours of credit instruction taught by full-time and part-time instructors and the total hours of instruction taught by full-time instructors.
(2)A full-time instructor shall be defined as any regular and contract faculty member teaching credit instruction.
(3)The chancellor shall compute and report to each community college district the number of full-time faculty (FTF) which are to be secured through the use of the prescribed portion of program improvement the Student Success and Support Program revenue allocated to each district. district, or district matching funds, as applicable. This computation shall be made by dividing the applicable portion of program improvement revenue (0 percent, 33 percent, or 40 percent of the program improvement allocation), revenue required to be expended pursuant to paragraph (1) or (2) of subdivision (b) by the statewide average replacement cost (a figure which represents the statewide average faculty salary plus benefits, minus the statewide average hourly rate of compensation for part-time instructors times the statewide average full-time teaching load). If the quotient is not a whole number, then the quotient shall be rounded down to the nearest whole number. If this quotient, once applied, will result in the district exceeding the 75 percent standard, the chancellor shall further reduce the quotient to a whole number that will leave the district as close as possible to, but in excess of, the 75 percent standard.
By March 15th
(4)By March 15 of each year, the chancellor shall report to each district an estimate of the number of FTF to be secured based upon the appropriation of revenues contained in the annual Budget Bill and the district match requirement.
(4)
(5)On or before December 31, 1991, the chancellor shall determine the extent to which each district, by September 30, 1991, has hired the number of FTF determined pursuant to paragraph (3) for the 198990 and 199091 fiscal years. To the extent that the cumulative number of FTF have not been retained, the chancellor shall reduce the districts base budget for 199192 and subsequent fiscal years by an amount equivalent to the average replacement cost times the deficiency in the number of FTF.
(d)It is the intent of the Legislature that the board of governors work together with the Academic Senate for California Community Colleges and other relevant entities to develop goals for the full-time to part-time faculty ratio in noncredit education.
SEC. 3.If the Commission on State Mandates determines that this act contains costs mandated by the state, reimbursement to local agencies and school districts for those costs shall be made pursuant to Part 7 (commencing with Section 17500) of Division 4 of Title 2 of the Government Code.
SECTION 1.Section 87482.7 of the Education Code is amended to read:87482.7.(a)The board of governors shall, pursuant to paragraph (6) of subdivision (b) of Section 70901, adopt regulations to establish minimum standards regarding the percentage of hours of credit instruction that shall be taught by full-time instructors.
(b)Upon notification by the board of governors, the Department of Finance shall transfer any amount of money deducted from district apportionments pursuant to the regulations adopted under this section. This money shall be transferred to the Employment Opportunity Fund pursuant to Section 87107.
(a)The board of governors shall, pursuant to paragraph (6) of subdivision (b) of Section 70901, adopt regulations that to establish minimum standards regarding the percentage of hours of credit instruction that shall be taught by full-time instructors.
(b)Upon notification by the board of governors, the Department of Finance shall transfer any amount of money deducted from district apportionments pursuant to the regulations adopted under this section. This money shall be transferred to the Employment Opportunity Fund pursuant to Section 87107.
|
Date
|
Status
|
|---|---|
| Sep 8, 2016 | Enrolled and presented to the Governor at 4 p.m. |
| Aug 30, 2016 | Senate amendments concurred in. To Engrossing and Enrolling. (Ayes 79. Noes 0. Page 6434.). |
| Aug 30, 2016 | Senate amendments concurred in. To Engrossing and Enrolling. |
| Aug 25, 2016 | In Assembly. Concurrence in Senate amendments pending. May be considered on or after August 28 pursuant to Assembly Rule 77. |
| Aug 23, 2016 | Read third time. Passed. Ordered to the Assembly. (Ayes 39. Noes 0. Page 5313.). |
| Aug 23, 2016 | Read third time. Passed. Ordered to the Assembly. |
| Aug 22, 2016 | Read second time. Ordered to third reading. |
| Aug 19, 2016 | Read third time and amended. Ordered to second reading. |
| Aug 15, 2016 | Read second time. Ordered to third reading. |
| Aug 11, 2016 | From committee: Do pass. (Ayes 7. Noes 0.) (August 11). |
| Aug 1, 2016 | In committee: Referred to APPR. suspense file. |
| Jun 29, 2016 | From committee: Do pass and re-refer to Com. on APPR. (Ayes 7. Noes 0.) (June 28). Re-referred to Com. on APPR. |
| Jun 16, 2016 | Re-referred to Com. on JUD. |
| Jun 15, 2016 | Re-referred to Com. on RLS. |
| Jun 15, 2016 | Withdrawn from committee. |
| Jun 8, 2016 | From committee chair, with author's amendments: Amend, and re-refer to committee. Read second time, amended, and re-referred to Com. on ED. |
| Jul 1, 2015 | In committee: Set, first hearing. Hearing canceled at the request of author. |
| Jun 18, 2015 | Referred to Com. on ED. |
| Jun 3, 2015 | In Senate. Read first time. To Com. on RLS. for assignment. |
| Jun 3, 2015 | Read third time. Passed. Ordered to the Senate. (Ayes 55. Noes 24. Page 1868.) |
| Jun 3, 2015 | Read third time. Passed. Ordered to the Senate. |
| Jun 2, 2015 | Read second time. Ordered to third reading. |
| Jun 1, 2015 | Read second time and amended. Ordered returned to second reading. |
| May 28, 2015 | From committee: Amend, and do pass as amended. (Ayes 12. Noes 4.) (May 28). |
| May 6, 2015 | In committee: Set, first hearing. Referred to APPR. suspense file. |
| Apr 22, 2015 | From committee: Do pass and re-refer to Com. on APPR. (Ayes 11. Noes 2.) (April 21). Re-referred to Com. on APPR. |
| Apr 14, 2015 | Re-referred to Com. on HIGHER ED. |
| Apr 13, 2015 | From committee chair, with author's amendments: Amend, and re-refer to Com. on HIGHER ED. Read second time and amended. |
| Apr 6, 2015 | Re-referred to Com. on HIGHER ED. |
| Mar 26, 2015 | From committee chair, with author's amendments: Amend, and re-refer to Com. on HIGHER ED. Read second time and amended. |
| Mar 26, 2015 | Referred to Com. on HIGHER ED. |
| Feb 25, 2015 | From printer. May be heard in committee March 27. |
| Feb 24, 2015 | Read first time. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Aug 30, 2016 | AB 626 CHIU Concurrence in Senate Amendments | Assembly Floor |
Passed |
|
| Aug 23, 2016 | Assembly 3rd Reading AB626 Chiu By Hertzberg | Senate Floor |
Passed |
|
| Aug 11, 2016 | Do pass | Senate Standing Committee on Appropriations |
Passed |
|
| Aug 1, 2016 | Placed on suspense file | Senate Standing Committee on Appropriations |
Passed |
|
| Jun 28, 2016 | Do pass, but first be re-referred to the Committee on [Appropriations] | Senate Standing Committee on Judiciary |
Passed |
|
| Jun 3, 2015 | AB 626 LOW Assembly Third Reading | Assembly Floor |
Passed |
|
| May 28, 2015 | Do pass as amended. | Assembly Standing Committee on Appropriations |
Passed |
|
| Apr 21, 2015 | Do pass and be re-referred to the Committee on [Appropriations] | Assembly Standing Committee on Higher Education |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
CONCURRENCE IN SENATE AMENDMENTS
CSA1 Bill Id:AB 626
Author:(Chiu and Low)
As Amended Ver:August 19, 2016
Majority vote
ASSEMBLY: |
| (June 3, 2015) | SENATE: | 39-0 | (August 23, 2016) |
(vote not relevant)
Original Committee Reference: HIGHER ED.
SUMMARY: Establishes, with specified exceptions, a claim resolution process for public works projects with local and state public entities.
The Senate amendments delete the Assembly version of this bill, and instead:
- State that it is in the interest of the state to ensure that a payment is made in a timely manner for the undisputed construction costs of a public works projects.
- Define a claim as a demand sent by a contractor to a public entity that includes, among others, a payment of an amount that is disputed by the public entity.
- Require a public entity to review and respond in writing to a claim within 45 days, and identify the portions that are disputed and undisputed.
- Require public entities to pay undisputed amounts within 60 days of the written response.
- Allow the contractor to demand an informal conference to meet and confer for settlement of disputed issues if the contractor disputes the written response or the public entity fails to respond.
- Require the public entity to respond within 10 business days after the meet and confer conference with a written statement specifying disputed and undisputed items.
- Require the undisputed amounts that are agreed to after the conference to be paid within 60 days.
- Require the remaining disputed portions of a claim to be submitted to nonbinding mediation, and the contractor and public entity to share mediation costs equally.
- Allow other specified processes if mediation is not successful.
- Set a 7% annual interest rate for amounts not paid in a timely manner.
- Allow a subcontractor to use the claim resolution process by working through the contractor.
- Exclude several specified state public entities from requirements of this bill.
- Sunset requirements of this bill on January 1, 2020.
EXISTING LAW specifies:
- That state public works contract disputes are generally subject to arbitration.
- That local entity public works contract disputes proscribe a resolution process for contracts of $375,000 or less.
FISCAL EFFECT: According to the Senate Appropriations Committee:
- State agencies: Potential costs (General Fund) to state agencies not specifically exempted from the bill's provisions, including the University of California and the California State University, that engage in public works contracts for claims review and resolution, which will result in additional administrative costs to review, evaluate, and respond to claims within 45 days, and for mandated mediation. State agencies are currently not subject to any statutory timelines for claims review and resolution, and unresolved claims are subject to arbitration. Staff notes the state agencies with numerous public works contracts and/or large-scale projects (i.e., Department of Transportation (CalTrans), Department of Water Resources (DWR), Department of General Services (DGS), High Speed Rail Authority) have been exempted from the bill's provisions.
- Local agencies: Potentially major state-reimbursable costs in the millions of dollars (General Fund) to local agencies engaged in public works projects to the extent this new process results in higher administrative costs, including any increase in administrative costs incurred under the existing process for resolution of claims under $375,000.
- Interest: Additional costs to state and local agencies for additional interest costs accrued on late payments under the timelines prescribed in this bill.
COMMENTS: This bill establishes a claim resolution process for public works projects for state and local public entities. It specifies that contractors can submit claims to public entities. According to the author, the intent of this bill is to ensure that undisputed portions of claims are paid in a timely manner and that there is a mechanism in place to resolve disputed items. The author explains that long-standing disputes have placed some contractors in difficult financial circumstances.
This bill requires public entities to provide a written response to claims within 45 days that details disputed and undisputed amounts. Further, it requires the payment of undisputed amounts and sets a process to resolve remaining disputes. Contractors can demand a meet and confer conference with the entity for remaining disputes. Items not resolved during the conference are submitted to nonbinding mediation.
The following state entities are excluded from the requirements in this bill:
- DWR, as to any project under its jurisdiction.
- CalTrans, as to any project under its jurisdiction.
- The Department of Parks and Recreation, as to any project under its jurisdiction.
- The Department of Corrections and Rehabilitation, with respect to any project under its jurisdiction, as specified.
- The Military Department, as to any project under its jurisdiction.
- DGS, as to all other projects.
- The High-Speed Rail Authority.
The requirements of this bill sunset on January 1, 2020.
This bill is substantially similar to the author's AB 1347 in 2015, which was vetoed by Governor Brown. According to the author, this bill is the result of various stakeholder meetings to resolve earlier-identified issues while AB 1347 was under consideration.
Analysis Prepared by: Scott Herbstman / A. & A.R. / (916) 319-3600 FN: 0004885
Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | AB |
THIRD READING
Bill No: AB 626
:
SENATE JUDICIARY COMMITTEE: 7-0, 6/28/16
AYES: Jackson, Moorlach, Anderson, Hertzberg, Leno, Monning, Wieckowski
SENATE APPROPRIATIONS COMMITTEE: 7-0, 8/11/16
AYES: Lara, Bates, Beall, Hill, McGuire, Mendoza, Nielsen
ASSEMBLY FLOOR: 55-24, 6/3/15 - See last page for vote
DIGEST: This bill, until January 1, 2020, establishes, for public works contracts entered into on or after January 1, 2017, a claim resolution procedure by which a general contractor can seek public agency review of the claim.
Senate Floor Amendments of 8/19/16 change the provision of the bill that provides that a waiver of the rights granted by this bill is void and contrary to public policy, provided, however, that (1) upon receipt of a claim, the parties may mutually agree to waive, in writing, mediation and proceed directly to the commencement of a civil action or binding arbitration, as applicable; and (2) a public entity in its public works contracts may include dispute resolution provisions that comply with this section, including the timeframes set forth herein, and that prescribe additional reasonable and equitable terms regarding actions or procedures to be taken by the parties. This clarifying amendment changes the wording in exception (2) above and instead state that a public entity may prescribe reasonable change order, claim, and dispute resolution procedures and requirements in addition to the provisions of this section, so long as the contractual provisions do not conflict with or otherwise impair the timeframes and procedures set forth in this section. The amendments also add a co-author.
Existing law:
- Provides that, in the event that a dispute arises between the local public entity and the contractor whether the conditions materially differ, or involve hazardous waste, or cause a decrease or increase in the contractor’s cost of, or time required for, performance of any part of the work, the contractor is not excused from any scheduled completion date provided for by the contract.
- Provides that the contractor retains any and all rights provided either by contract or by law which pertain to the resolution of disputes and protests between the contracting parties.
- Authorizes public agencies to make changes in construction contracts for public improvements in the course of construction, and requires the contractor to be paid for the changes in accordance with the provisions of the contract governing payment for changes in the work.
- Authorizes, pursuant to contract terms and by mutual consent of the contracting parties, any public agency to terminate, amend, or modify any contract within the scope of such authority; however, this provision does not apply to contracts entered into pursuant to any statute expressly requiring that contracts be let or awarded on the basis of competitive bids.
- Prohibits, except as otherwise provided, a suit for money or damages against a public entity on a cause of action for which a claim is required to be presented until a written claim therefor has been presented to the public entity and has been acted upon or rejected by the board.
- Prescribes a contract claims resolution process for contracts entered into with a state agency and requires arbitration of a claim, as defined.
- Authorizes a claimant to initiate arbitration no later than 90 days after the date of personal or mail service on the claimant of the final written decision by the appropriate public agency department on the claim; however, this limitation does not apply to any claim founded on any cost audit, latent defect, warranty, or guarantee under the contract.
- Prohibits arbitration until the claimant pursues diligently and exhausts, as to the claim, the required administrative procedures set forth in the contract under which the claim arose, as specified.
- Authorizes a party to the contract to join in the arbitration as a party, any supplier, subcontractor, design professional, surety, or other person who has so agreed and if the joinder is necessary to prevent a substantial risk of the party otherwise being subjected to inconsistent obligations or decisions.
This bill:
- Requires, upon receipt of a claim, the public entity to which the claim applies to conduct a reasonable review of the claim and, within a period not to exceed 45 days, provide the claimant a written statement identifying what portion of the claim is disputed and what portion is undisputed. However, a public entity and a contractor may, by mutual agreement, extend the time period.
- Requires the claimant to furnish reasonable documentation to support the claim, and provides, if the public entity needs approval from its governing body to provide the claimant a written statement identifying the disputed portion and the undisputed portion of the claim, and the governing body does not meet within the 45 days following receipt of a claim sent by registered mail, the public entity up to three days following the next duly publicly noticed meeting after the 45 day period, or extension expires to provide the claimant the written statement.
- Requires any payment due on an undisputed portion of the claim to be processed and made within 60 days after the public entity issues its written statement; if the public entity fails to issue a written statement, the claim would be deemed rejected in its entirety.
- Authorizes, if the claimant disputes the public entity’s written response, or if the public entity fails to respond to a claim issued within the time prescribed, the claimant to demand in writing an informal conference to meet and confer for settlement of the issues in dispute, and, upon receipt of a demand in writing sent by registered mail or certified mail, return receipt requested, the public entity would be required to schedule a meet and confer conference within 30 days for settlement of the dispute.
- Requires, within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the public entity to provide the claimant a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed.
- Requires any payment due on an undisputed portion of the claim to be processed and made within 60 days after the public entity issues its written statement, and any disputed portion of the claim, as identified by the contractor in writing, would be required to be submitted to nonbinding mediation, with the public entity and the claimant sharing the associated costs equally.
- Requires the public entity and claimant to mutually agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing, and, if the parties cannot agree upon a mediator, each party would select a mediator and those mediators would select a qualified neutral third party to mediate with regard to the disputed portion of the claim.
- Provides that if the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate the disputed portion of the claim, and each party shall bear the fees and costs charged by their respective mediators in selecting the neutral mediator.
- Provides that if mediation is unsuccessful, the parts of the claim remaining in dispute would be subject to other applicable claim resolution procedures.
- Specifies that mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation, and any mediation utilized must conform to the time frames provided in this bill.
- Requires the mediation conducted pursuant to this bill to excuse any further obligation under Section 20104.4 to mediate (meet and confer) after litigation has been commenced, unless otherwise agreed to by the public entity and the contractor in writing.
- Does not preclude a public entity from requiring arbitration of disputes under private arbitration or the Public Works Contract Arbitration Program, if under this bill, mediation does not resolve the parties’ dispute.
- Specifies that failure by the public entity to respond to a claim from a contractor within the time periods described in this bill or to otherwise meet the time requirements of this bill would result in the entire claim deemed rejected and provides that a claim that is denied by reason of the public entity’s failure to have responded to a claim or its failure to otherwise meet the time requirements of this section shall not constitute an adverse finding with regard to the merits of the claim or the responsibility or qualifications of the claims.
- Requires amounts not paid timely to bear interest at 7 percent per annum.
- Authorizes, if a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against a public entity because privity of contract does not exist, the contractor to present to the public entity a claim on behalf of a subcontractor or lower tier subcontractor.
- Authorizes a subcontractor to request in writing, either on his or her own behalf or on behalf of a lower tier subcontractor, that the contractor present a claim for work which was performed by the subcontractor or by a lower tier subcontractor on behalf of the subcontractor, and requires the subcontractor requesting that the claim be presented to the public entity to furnish reasonable documentation to support the claim.
- Requires, within 45 days of receipt of that written request, the contractor to notify the subcontractor in writing as to whether the contractor presented the claim to the public entity and, if the original contractor did not present the claim, provide the subcontractor with a statement of the reasons for not having done so.
- Requires the text of the provisions provided under this bill or a summary of it to be set forth in the plans or specifications for any public works project that may give rise to a claim under this bill.
- Makes a waiver of the rights granted by this bill void and contrary to public policy, provided, however, that upon receipt of a claim, the parties may mutually agree to waive, in writing, mediation and proceed directly to the commencement of a civil action or binding arbitration as applicable; and allows a public entity to prescribe reasonable change order, claim, and dispute resolution procedures and requirements in addition to the provisions of this section, so long as the contractual provisions do not conflict with or otherwise impair the timeframes and procedures set forth in this section.
- Applies to contracts entered into on or after January 1, 2017 and sunsets on January 1, 2020.
- Provides that nothing in the bill shall impose liability upon a public entity that makes loans or grants available through a competitive application process, for the failure of an awardee to meet its contractual obligations.
Background
In general, public works refers to construction, alteration, demolition, installation, or repair work (including maintenance) of any public structure, building, road, or other improvement done under contract and paid by public funds, or if private funds are used, more than 50 percent of the square footage is leased to a public entity. Because of this, there are laws regarding many aspects of the construction projects to protect the public’s interest. Public works projects do not include those done by a public agency with its own employees.
On public works projects, a public agency contracts with a general contractor, who has submitted a bid or estimated cost to provide the materials and services for the construction, alteration, demolition, installation, or repair work. At times, the cost of the materials and services is more than the general contractor’s bid due to changes in the project, which may be attributed to inaccurate or incomplete project plans and specifications, the public agency orders extra work to be performed, or unexpected difficulties arise. These increases in costs may be submitted to the public agency for payment. Typically, unless a change order is issued by the public agency or its legislative body or appropriate department approving the increase in cost, the general contractor, who may not be responsible for the underlying cause of the increase in costs but has accrued the expense for the sake of completing the project, will be unable to resolve a claim dispute outside of arbitration or civil action. Further, a subcontractor, who has performed additional services or provided materials outside the scope of the original contract with the general contractor but necessary to the completion of the project, may be seeking payment from the public agency. Delays in payment for the extra work provided by the contractor or subcontractor may place the contractor or subcontractor at financial risk with their employees or continued work on the public work. Additionally, the failure of the public agency to issue a change order or the denial of claims has resulted in costly litigation for the public agency, contractors, and subcontractors.
Comments
The author writes:
There is no law in place requiring agencies to pay claims, in a timely manner, made by contractors for extra work performed and approved by the agency, even when the public agency acknowledges that it owes the contractor for work performed. This places contractors and their workers in difficult financial circumstances.
Furthermore, there is a lack in uniformity for disputing a claim. In many cases, some public agencies have no requirements to respond to a claim or respond to a claim in a timely manner. The breakdown of communication between the public agency and the contractor adds to the burden on the contractor and meeting their payroll obligations. AB 626, [. . .] creates a process that requires agencies to respond to a contractor’s claim, to pay out portions of the work they acknowledge and agree they owe the contractor, and to resolve disputed portions of payment through non-binding mediation.
FISCAL EFFECT: Appropriation: Fiscal Com.: Local:
According to the Senate Appropriations Committee there are potential costs (General Fund) to state agencies not specifically exempted from the bill’s provisions, including the University of California and the California State University, that engage in public works contracts for claims review and resolution, which will result in additional administrative costs to review, evaluate, and respond to claims within 45 days, and for mandated mediation. State agencies are currently not subject to any statutory timelines for claims review and resolution, and unresolved claims are subject to arbitration. There are also major state-reimbursable costs in the millions of dollars (General Fund) to local agencies engaged in public works projects to the extent this new process results in higher administrative costs, including any increase in administrative costs incurred under the existing process for resolution of claims under $375,000. There are also additional costs to state and local agencies for additional interest costs accrued on late payments under the timelines prescribed in this bill.
According to the Senate Appropriations Committee there are potential costs (General Fund) to state agencies not specifically exempted from the bill’s provisions, including the University of California and the California State University, that engage in public works contracts for claims review and resolution, which will result in additional administrative costs to review, evaluate, and respond to claims within 45 days, and for mandated mediation. State agencies are currently not subject to any statutory timelines for claims review and resolution, and unresolved claims are subject to arbitration. There are also major state-reimbursable costs in the millions of dollars (General Fund) to local agencies engaged in public works projects to the extent this new process results in higher administrative costs, including any increase in administrative costs incurred under the existing process for resolution of claims under $375,000. There are also additional costs to state and local agencies for additional interest costs accrued on late payments under the timelines prescribed in this bill.
SUPPORT: (Verified 8/12/16)
Air Conditioning Sheet Metal Association
Air-Conditioning & Refrigeration Contractors Association
Advanced Cable Solutions, Inc.
Architectural Glass& Aluminum
Associated General Contractors
Ayoob & Perry Plumbing Co.
Baker Electric
Big Sky Electric
California Chapters of the National Electrical Contractors Association
California Legislative Conference of the Plumbing
California-Nevada Conference of Operating Engineers
California State Association of Electrical Workers
California State Pipe Trades Council
Collins Electrical Company, Inc.
Creative Shower Door Corp.
Cupertino Electric, Inc.
Electro Construction Corp.
Finishing Contractors Association of Southern California
Fuller Electric
Giroux Glass, Inc.
Heating and Piping Industry
International Union of Elevator Constructors
KBI Painting, Inc.
Mike Cox Electric Company, Inc.
Morrow-Meadows Corporation
Neal Electric Corp.
Neubauer Electric, Inc.
Northern California Allied Trades
Pacific Glazing Contractors
Painting and Decorating Contractors Association of Sacramento
Piping Industry Progress & Education Trust Fund
Pyramid Painting, Inc.
Roundtree Glass Company
Santa Barbara Glass Company
Schetter Electric, Inc.
Smith and Sons Electric, Inc.
State Building and Construction Trades Council, AFL-CIO
TNT Industrial Contractors, Inc.
Wall and Ceiling Alliance
Western States Council of Sheet Metal Workers
44 individuals
OPPOSITION: (Verified 8/21/16)
San Diego County Regional Airport Authority
ASSEMBLY FLOOR: 55-24, 6/3/15
AYES: Achadjian, Alejo, Bloom, Bonilla, Bonta, Brown, Burke, Calderon, Campos, Chau, Chávez, Chiu, Chu, Cooley, Cooper, Dababneh, Daly, Dodd, Eggman, Frazier, Cristina Garcia, Eduardo Garcia, Gatto, Gipson, Gomez, Gonzalez, Gordon, Gray, Roger Hernández, Holden, Irwin, Jones-Sawyer, Levine, Linder, Lopez, Low, McCarty, Medina, Mullin, Nazarian, O'Donnell, Perea, Quirk, Rendon, Ridley-Thomas, Rodriguez, Salas, Santiago, Mark Stone, Ting, Weber, Wilk, Williams, Wood, Atkins
NOES: Travis Allen, Baker, Bigelow, Brough, Chang, Dahle, Beth Gaines, Gallagher, Grove, Hadley, Harper, Jones, Kim, Lackey, Maienschein, Mathis, Mayes, Melendez, Obernolte, Olsen, Patterson, Steinorth, Wagner, Waldron
NO VOTE RECORDED: Thurmond
Prepared by: Margie Estrada / JUD. / (916) 651-4113
8/22/16 20:38:06
Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | AB 626 |
THIRD READING
Bill No: AB 626
Author: Chiu (D) and Low (D), et al.
Amended: 6/8/16 in Senate
SENATE JUDICIARY COMMITTEE: 7-0, 6/28/16
AYES: Jackson, Moorlach, Anderson, Hertzberg, Leno, Monning, Wieckowski
SENATE APPROPRIATIONS COMMITTEE: 7-0, 8/11/16
AYES: Lara, Bates, Beall, Hill, McGuire, Mendoza, Nielsen
ASSEMBLY FLOOR: 55-24, 6/3/15 - See last page for vote
SUBJECT: Public contracts: claim resolution
DIGEST: This bill, until January 1, 2020, establishes, for public works contracts entered into on or after January 1, 2017, a claim resolution procedure by which a general contractor can seek public agency review of the claim.
Existing law:
- Provides that, in the event that a dispute arises between the local public entity and the contractor whether the conditions materially differ, or involve hazardous waste, or cause a decrease or increase in the contractor’s cost of, or time required for, performance of any part of the work, the contractor is not excused from any scheduled completion date provided for by the contract.
- Provides that the contractor retains any and all rights provided either by contract or by law which pertain to the resolution of disputes and protests between the contracting parties.
- Authorizes public agencies to make changes in construction contracts for public improvements in the course of construction, and requires the contractor to be paid for the changes in accordance with the provisions of the contract governing payment for changes in the work.
- Authorizes, pursuant to contract terms and by mutual consent of the contracting parties, any public agency to terminate, amend, or modify any contract within the scope of such authority; however, this provision does not apply to contracts entered into pursuant to any statute expressly requiring that contracts be let or awarded on the basis of competitive bids.
- Prohibits, except as otherwise provided, a suit for money or damages against a public entity on a cause of action for which a claim is required to be presented until a written claim therefor has been presented to the public entity and has been acted upon or rejected by the board.
- Prescribes a contract claims resolution process for contracts entered into with a state agency and requires arbitration of a claim, as defined.
- Authorizes a claimant to initiate arbitration no later than 90 days after the date of personal or mail service on the claimant of the final written decision by the appropriate public agency department on the claim; however, this limitation does not apply to any claim founded on any cost audit, latent defect, warranty, or guarantee under the contract.
- Prohibits arbitration until the claimant pursues diligently and exhausts, as to the claim, the required administrative procedures set forth in the contract under which the claim arose, as specified.
- Authorizes a party to the contract to join in the arbitration as a party, any supplier, subcontractor, design professional, surety, or other person who has so agreed and if the joinder is necessary to prevent a substantial risk of the party otherwise being subjected to inconsistent obligations or decisions.
This bill:
- Requires, upon receipt of a claim, the public entity to which the claim applies to conduct a reasonable review of the claim and, within a period not to exceed 45 days, provide the claimant a written statement identifying what portion of the claim is disputed and what portion is undisputed. However, a public entity and a contractor may, by mutual agreement, extend the time period.
- Requires the claimant to furnish reasonable documentation to support the claim, and provides, if the public entity needs approval from its governing body to provide the claimant a written statement identifying the disputed portion and the undisputed portion of the claim, and the governing body does not meet within the 45 days following receipt of a claim sent by registered mail, the public entity up to three days following the next duly publicly noticed meeting after the 45 day period, or extension expires to provide the claimant the written statement.
- Requires any payment due on an undisputed portion of the claim to be processed and made within 60 days after the public entity issues its written statement; if the public entity fails to issue a written statement, the claim would be deemed rejected in its entirety.
- Authorizes, if the claimant disputes the public entity’s written response, or if the public entity fails to respond to a claim issued within the time prescribed, the claimant to demand in writing an informal conference to meet and confer for settlement of the issues in dispute, and, upon receipt of a demand in writing sent by registered mail or certified mail, return receipt requested, the public entity would be required to schedule a meet and confer conference within 30 days for settlement of the dispute.
- Requires, within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the public entity to provide the claimant a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed.
- Requires any payment due on an undisputed portion of the claim to be processed and made within 60 days after the public entity issues its written statement, and any disputed portion of the claim, as identified by the contractor in writing, would be required to be submitted to nonbinding mediation, with the public entity and the claimant sharing the associated costs equally.
- Requires the public entity and claimant to mutually agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing, and, if the parties cannot agree upon a mediator, each party would select a mediator and those mediators would select a qualified neutral third party to mediate with regard to the disputed portion of the claim.
- Provides that if the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate the disputed portion of the claim, and each party shall bear the fees and costs charged by their respective mediators in selecting the neutral mediator.
- Provides that if mediation is unsuccessful, the parts of the claim remaining in dispute would be subject to other applicable claim resolution procedures.
- Specifies that mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation, and any mediation utilized must conform to the time frames provided in this bill.
- Requires the mediation conducted pursuant to this bill to excuse any further obligation under Section 20104.4 to mediate (meet and confer) after litigation has been commenced, unless otherwise agreed to by the public entity and the contractor in writing.
- Does not preclude a public entity from requiring arbitration of disputes under private arbitration or the Public Works Contract Arbitration Program, if under this bill, mediation does not resolve the parties’ dispute.
- Specifies that failure by the public entity to respond to a claim from a contractor within the time periods described in this bill or to otherwise meet the time requirements of this bill would result in the entire claim deemed rejected and provides that a claim that is denied by reason of the public entity’s failure to have responded to a claim or its failure to otherwise meet the time requirements of this section shall not constitute an adverse finding with regard to the merits of the claim or the responsibility or qualifications of the claims.
- Requires amounts not paid timely to bear interest at 7 percent per annum.
- Authorizes, if a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against a public entity because privity of contract does not exist, the contractor to present to the public entity a claim on behalf of a subcontractor or lower tier subcontractor.
- Authorizes a subcontractor to request in writing, either on his or her own behalf or on behalf of a lower tier subcontractor, that the contractor present a claim for work which was performed by the subcontractor or by a lower tier subcontractor on behalf of the subcontractor, and requires the subcontractor requesting that the claim be presented to the public entity to furnish reasonable documentation to support the claim.
- Requires, within 45 days of receipt of that written request, the contractor to notify the subcontractor in writing as to whether the contractor presented the claim to the public entity and, if the original contractor did not present the claim, provide the subcontractor with a statement of the reasons for not having done so.
- Requires the text of the provisions provided under this bill or a summary of it to be set forth in the plans or specifications for any public works project that may give rise to a claim under this bill.
- Makes a waiver of the rights granted by this bill void and contrary to public policy, provided, however, that upon receipt of a claim, the parties may mutually agree to waive, in writing, mediation and proceed directly to the commencement of a civil action or binding arbitration as applicable; and allows a public entity in its public works contracts to include dispute resolution provisions that comply with this section, including timeframes set forth herein, and that prescribe additional reasonable and equitable terms regarding actions or procedures to be taken by the parties.
- Applies to contracts entered into on or after January 1, 2017 and sunsets on January 1, 2020.
- Provides that nothing in the bill shall impose liability upon a public entity that makes loans or grants available through a competitive application process, for the failure of an awardee to meet its contractual obligations.
Background
In general, public works refers to construction, alteration, demolition, installation, or repair work (including maintenance) of any public structure, building, road, or other improvement done under contract and paid by public funds, or if private funds are used, more than 50 percent of the square footage is leased to a public entity. Because of this, there are laws regarding many aspects of the construction projects to protect the public’s interest. Public works projects do not include those done by a public agency with its own employees.
On public works projects, a public agency contracts with a general contractor, who has submitted a bid or estimated cost to provide the materials and services for the construction, alteration, demolition, installation, or repair work. At times, the cost of the materials and services is more than the general contractor’s bid due to changes in the project, which may be attributed to inaccurate or incomplete project plans and specifications, the public agency orders extra work to be performed, or unexpected difficulties arise. These increases in costs may be submitted to the public agency for payment. Typically, unless a change order is issued by the public agency or its legislative body or appropriate department approving the increase in cost, the general contractor, who may not be responsible for the underlying cause of the increase in costs but has accrued the expense for the sake of completing the project, will be unable to resolve a claim dispute outside of arbitration or civil action. Further, a subcontractor, who has performed additional services or provided materials outside the scope of the original contract with the general contractor but necessary to the completion of the project, may be seeking payment from the public agency. Delays in payment for the extra work provided by the contractor or subcontractor may place the contractor or subcontractor at financial risk with their employees or continued work on the public work. Additionally, the failure of the public agency to issue a change order or the denial of claims has resulted in costly litigation for the public agency, contractors, and subcontractors.
Comments
The author writes:
There is no law in place requiring agencies to pay claims, in a timely manner, made by contractors for extra work performed and approved by the agency, even when the public agency acknowledges that it owes the contractor for work performed. This places contractors and their workers in difficult financial circumstances.
Furthermore, there is a lack in uniformity for disputing a claim. In many cases, some public agencies have no requirements to respond to a claim or respond to a claim in a timely manner. The breakdown of communication between the public agency and the contractor adds to the burden on the contractor and meeting their payroll obligations. AB 626, [. . .] creates a process that requires agencies to respond to a contractor’s claim, to pay out portions of the work they acknowledge and agree they owe the contractor, and to resolve disputed portions of payment through non-binding mediation.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
According to the Senate Appropriations Committee there are potential costs (General Fund) to state agencies not specifically exempted from the bill’s provisions, including the University of California and the California State University, that engage in public works contracts for claims review and resolution, which will result in additional administrative costs to review, evaluate, and respond to claims within 45 days, and for mandated mediation. State agencies are currently not subject to any statutory timelines for claims review and resolution, and unresolved claims are subject to arbitration. There are also major state-reimbursable costs in the millions of dollars (General Fund) to local agencies engaged in public works projects to the extent this new process results in higher administrative costs, including any increase in administrative costs incurred under the existing process for resolution of claims under $375,000. There are also additional costs to state and local agencies for additional interest costs accrued on late payments under the timelines prescribed in this bill.
Air Conditioning Sheet Metal Association
Air-Conditioning & Refrigeration Contractors Association
Advanced Cable Solutions, Inc.
Architectural Glass& Aluminum
Associated General Contractors
Ayoob & Perry Plumbing Co.
Baker Electric
Big Sky Electric
California Chapters of the National Electrical Contractors Association
California Legislative Conference of the Plumbing
California-Nevada Conference of Operating Engineers
California State Association of Electrical Workers
California State Pipe Trades Council
Collins Electrical Company, Inc.
Creative Shower Door Corp.
Cupertino Electric, Inc.
Electro Construction Corp.
Finishing Contractors Association of Southern California
Fuller Electric
Giroux Glass, Inc.
Heating and Piping Industry
International Union of Elevator Constructors
KBI Painting, Inc.
Mike Cox Electric Company, Inc.
Morrow-Meadows Corporation
Neal Electric Corp.
Neubauer Electric, Inc.
Northern California Allied Trades
Pacific Glazing Contractors
Painting and Decorating Contractors Association of Sacramento
Piping Industry Progress & Education Trust Fund
Pyramid Painting, Inc.
Roundtree Glass Company
Santa Barbara Glass Company
Schetter Electric, Inc.
Smith and Sons Electric, Inc.
State Building and Construction Trades Council, AFL-CIO
TNT Industrial Contractors, Inc.
Wall and Ceiling Alliance
Western States Council of Sheet Metal Workers
44 individuals
OPPOSITION: (Verified 8/12/16)
San Diego County Regional Airport Authority
ASSEMBLY FLOOR: 55-24, 6/3/15
AYES: Achadjian, Alejo, Bloom, Bonilla, Bonta, Brown, Burke, Calderon, Campos, Chau, Chávez, Chiu, Chu, Cooley, Cooper, Dababneh, Daly, Dodd, Eggman, Frazier, Cristina Garcia, Eduardo Garcia, Gatto, Gipson, Gomez, Gonzalez, Gordon, Gray, Roger Hernández, Holden, Irwin, Jones-Sawyer, Levine, Linder, Lopez, Low, McCarty, Medina, Mullin, Nazarian, O'Donnell, Perea, Quirk, Rendon, Ridley-Thomas, Rodriguez, Salas, Santiago, Mark Stone, Ting, Weber, Wilk, Williams, Wood, Atkins
NOES: Travis Allen, Baker, Bigelow, Brough, Chang, Dahle, Beth Gaines, Gallagher, Grove, Hadley, Harper, Jones, Kim, Lackey, Maienschein, Mathis, Mayes, Melendez, Obernolte, Olsen, Patterson, Steinorth, Wagner, Waldron
NO VOTE RECORDED: Thurmond
Prepared by: Margie Estrada / JUD. / (916) 651-4113
8/15/16 19:36:03
SENATE COMMITTEE ON
Senator Ricardo Lara, Chair
2015 - 2016 Regular Session
AB 626 (Chiu) - Public contracts: claim resolution
Version: | Policy Vote: |
Urgency: | Mandate: |
Hearing Date: | Consultant: |
This bill meets the criteria for referral to the Suspense File.
Bill Summary:
AB 626 would, until January 1, 2020, establish a claims resolution process for public works contracts entered into on or after January 1, 2017, by which a general contractor may seek a public entity’s review of the claim.
Fiscal Impact:
- State agencies: Potential costs (General Fund) to state agencies not specifically exempted from the bill’s provisions, including the University of California and the California State University, that engage in public works contracts for claims review and resolution, which will result in additional administrative costs to review, evaluate, and respond to claims within 45 days, and for mandated mediation. State agencies are currently not subject to any statutory timelines for claims review and resolution, and unresolved claims are subject to arbitration. Staff notes the state agencies with numerous public works contracts and/or large-scale projects (i.e., CalTrans, DWR, DGS, High Speed Rail Authority) have been exempted from the bill’s provisions.
- Local agencies: Potentially major state-reimbursable costs in the millions of dollars (General Fund) to local agencies engaged in public works projects to the extent this new process results in higher administrative costs, including any increase in administrative costs incurred under the existing process for resolution of claims under $375,000.
- Interest: Additional costs to state and local agencies for additional interest costs accrued on late payments under the timelines prescribed in this bill.
Background:
Existing law prescribes various requirements regarding the formation, content, and enforcement of state and local public contracts. Existing law applicable to state public contracts generally requires that the resolution of claims related to those contracts be subject to arbitration. Existing law for local agency public works requires all claims made for work arising out of the contract, but not expressly provided for in that contract, that are $375,000 or less to first be resolved through administrative resolution procedures. However, if the contract provides for arbitration, the claim will have to be arbitrated according to express arbitration statutes. The arbitration statutes apply to both local agency and state agency public work contracts.
This bill prescribes a new claims resolution process by which a contractor can submit a claim to a public entity.
Proposed Law:
This bill would establish a claims resolution process for public works contracts entered into on or after January 1, 2017, as follows:
- Precludes any other claim resolution provision and applies to any claim by a contractor in connection with a public works project.
- Provides the following definitions:
- “Claim” means a separate demand by the contractor sent by registered or certified mail for one or more of the following: (a) a time extension, including, without limitation, for relief from damages or penalties for delay assessed by a public entity under a contract for a public works project; (b) payment by the public entity of money or damages arising from work done by, or on behalf of, the contractor pursuant to the contract for a public works project and payment for which is not otherwise expressly provided or to which the claimant is not otherwise entitled; or (c) payment of an amount that is disputed by the public entity;
- “Contractor” means any type of contractor subject to the Contractor’s State License Law who has entered into a direct contract with a public entity for a public works project;
- “Public entity” means, without limitation, except as provided, a state agency, department, office, division, bureau, board, or commission, the California State University, the University of California, a city, including a charter city, county, including a charter county, city and county, including a charter city and county, district, special district, public authority, political subdivision, public corporation, or nonprofit transit corporation wholly owned by a public agency and formed to carry out the purposes of the public agency;
- “Public entity” shall not include the following:
- The Department of Water Resources (DWR), as to any project under its jurisdiction.
- The Department of Transportation (CalTrans), as to any project under its jurisdiction.
- The Department of Parks and Recreation, as to any project under its jurisdiction.
- The Department of Corrections and Rehabilitation (CDCR), with respect to any project under its jurisdiction, as specified.
- The Military Department, as to any project under its jurisdiction.
- The Department of General Services (DGS) as to all other projects.
- The High-Speed Rail Authority.
- “Public works project” means the erection, construction, alteration, repair, or improvement of any public structure, building, road, or other public improvement of any kind;
- “Subcontractor” means any type of contractor subject to the Contractor’s State License Law who either is in direct contract with a contractor or is a lower tier subcontractor.
- Upon receipt of a claim, requires a public entity to which the claim applies to conduct a reasonable review of the claim and, within a period not to exceed 45 days, provide the claimant a written statement identifying what portion of the claim is disputed and what portion is undisputed. Authorizes a public entity and a contractor to, by mutual agreement, extend the 45-day time period.
- If the public entity needs approval from its governing body to provide the claimant the written statement, and the governing body does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a claim sent by registered mail or certified mail, return receipt requested, provides the public agency up to three days following the next duly publicly noticed meeting of the governing body after the 45-day period, or extension, expires to provide the claimant a written statement identifying the disputed portion and the undisputed portion.
- Requires any payment due on an undisputed portion of the claim to be processed and made within 60 days after the public entity issues its written statement; if the public entity fails to issue a written statement, the claim would be deemed rejected in its entirety.
- Requires any payment due on an undisputed portion of the claim to be processed and made within 60 days after the public entity issues its written statement, and any disputed portion of the claim, as identified by the contractor in writing, would be required to be submitted to nonbinding mediation, with the public entity and the claimant sharing the associated costs equally.
- Requires the public entity and claimant to mutually agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing, and, if the parties cannot agree upon a mediator, each party would select a mediator and those mediators would select a qualified neutral third party to mediate with regard to the disputed portion of the claim.
- Requires each party to bear the fees and costs charged by its respective mediator, as specified. If mediation is unsuccessful, requires the parts of the claim remaining in dispute to be subject to other applicable claim resolution procedures.
- Unless otherwise agreed to by the public entity and the contractor in writing, requires the mediation conducted pursuant to this bill to excuse any further obligation to mediate after litigation has been commenced.
- Does not preclude a public entity from requiring arbitration of disputes under private arbitration or the Public Works Contract Arbitration Program, if mediation does not resolve the parties’ dispute.
- Specifies that failure by the public entity to respond to a claim from a contractor within the time periods described would result in the claim being deemed rejected in its entirety. Provides that a claim denied by reason of a public entity’s failure to have responded to a claim, or its failure to otherwise meet the time requirements shall not constitute an adverse finding with regard to the merits of the claim or the responsibility or qualifications of the claimant.
- Requires amounts not paid in a timely manner to bear interest at 7 percent per annum.
- If a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against a public entity because privity of contract does not exist, authorizes the contractor to present to the public entity a claim on behalf of a subcontractor or lower tier subcontractor.
- Authorizes a subcontractor to request in writing, either on his or her own behalf or on behalf of a lower tier subcontractor, that the contractor present a claim for work which was performed by the subcontractor or by a lower tier subcontractor on behalf of the subcontractor.
- Requires the subcontractor requesting that the claim be presented to the public entity to furnish reasonable documentation to support the claim.
- Within 45 days of receipt of that written request, requires the contractor to notify the subcontractor in writing as to whether the contractor presented the claim to the public entity and, if the original contractor did not present the claim, provide the subcontractor with a statement of the reasons for not having done so.
- Requires the text of the provisions provided under this bill or a summary of it to be set forth in the plans or specifications for any public works project that may give rise to a claim under this bill.
- Makes a waiver of the rights granted by this bill void and contrary to public policy, subject to specified conditions.
- Provides that nothing in this bill shall impose a liability upon a public entity that makes loans or grants available through a competitive application process, for the failure of the awardee to meet its contractual obligations.
- Sunsets the bill’s provisions on January 1, 2020.
Related Legislation:
AB 1347 (Chiu) 2015 was substantially similar to this bill when it was heard by this Committee, with the exception that the exemption for the Department of Transportation was not provided for in AB 1347 (but was later amended to exempt CalTrans prior to the bill being presented to the Governor). This bill was vetoed by the Governor with the following message:
I am returning Assembly Bill 1347 without my signature. This bill creates, for three years, a new dispute resolution process under which contractors could seek public agency review of claims that arise during public works projects.
Contractors who perform work for public agencies should be paid promptly. Swift resolution of payment disputes is in the best interest of contractors, workers, and the public agencies that are charged with efficiently managing taxpayer funds. I'm not convinced, however, that the procedures contemplated by this bill are an improvement over current law.
I am committed, however, to ensuring timely payment for work ordered by public agencies. In the interest of furthering that goal I am directing my departments to immediately work with industry partners and the proponents of this bill on ways of improving our prompt payment policies.
Prior Legislation: AB 2471 (Frazier) 2014 would have required state and local public entities engaged in a public works contract awarded to the lowest bidder to promptly issue change orders when extra work was required of the contractor or subcontractor. This bill stalled in this Committee without a hearing.
AB 2096 (Miller) 2010 would have allowed a public agency and a contractor to mutually agree to resolve a claim through independent arbitration. This bill failed passage in the Assembly Committee on Judiciary.
Staff Comments:
By requiring state agencies not otherwise exempted to adhere to the claims resolution process specified in this measure, the provisions of this bill could result in significant personnel costs (General Fund) for evaluation, response, coordination, and oversight activities related to submitted claims requiring action within the prescribed timeframes of this measure. Although the bill exempts specified state agencies involved with numerous public works projects and/or large-scale projects (i.e., CalTrans, DWR, DGS, High Speed Rail Authority), this bill still applies its requirements upon all other public entities not specifically exempted, including but not limited to the UC and California State University. The number of claims potentially submitted by contractors for public works projects entered into by non-exempted public entities cannot be known with certainty, and as a result, the costs are unknown, but potentially significant.
In addition to one-time costs to rewrite specifications, policy, construction and oversight manuals, forms, and provide training, ongoing resource needs could be required to address the workload involved with submitted claims.
This bill requires that the "associated cost" of mediation to be shared equally between the public entity and the claimant. In the absence of a definition, however, it is unclear to what extent “associated costs” would extend or what costs it would include.
By requiring local agencies to adhere to the claims resolution process specified in this measure, this bill creates a state-mandated local program, potentially resulting in major state-reimbursable costs in the millions of dollars (General Fund) through the three-year operative period to local agencies engaged in public works projects. While the magnitude of costs to local agencies cannot be estimated with certainty, given the volume of local public works projects and claims subject to this resolution process, costs are potentially substantial.
-- END --
Senator Hannah-Beth Jackson, Chair
2015-2016 Regular Session
Bill No: AB 626 (Author:Chiu)
Version: June 8, 2016
Hearing Date: June 28, 2016
Fiscal: Yes
Urgency: No
Consultant: TMW/me
SUBJECT
Public contracts: claim resolution
DESCRIPTION
This bill, until January 1, 2020, would establish, for public works contracts entered into on or after January 1, 2017, a claim resolution procedure by which a general contractor can seek public agency review of the claim. This bill would also prescribe a procedure by which a subcontractor or lower tier contractor may make a claim against the public agency through the general contractor.
BACKGROUND
In general, public works refers to construction, alteration, demolition, installation, or repair work (including maintenance) of any public structure, building, road, or other improvement done under contract and paid by public funds, or if private funds are used, more than 50 percent of the square footage is leased to a public entity. Because of this, there are laws regarding many aspects of the construction projects to protect the public’s interest. Public works projects do not include those done by a public agency with its own employees.
On public works projects, a public agency contracts with a general contractor, who has submitted a bid or estimated cost to provide the materials and services for the construction, alteration, demolition, installation, or repair work. At times, the cost of the materials and services is more than the general contractor’s bid due to changes in the project, which may be attributed to inaccurate or incomplete project plans and specifications, the public agency orders extra work to be performed, or unexpected difficulties arise. These increases in costs may be submitted to the public agency for payment. Typically, unless a change order is issued by the public agency or its legislative body or appropriate department approving the increase in cost, the general contractor, who may not be responsible for the underlying cause of the increase in costs but has accrued the expense for the sake of completing the project, will be unable to resolve a claim dispute outside of arbitration or civil action. Further, a subcontractor, who has performed additional services or provided materials outside the scope of the original contract with the general contractor but necessary to the completion of the project, may be seeking payment from the public agency. Delays in payment for the extra work provided by the contractor or subcontractor may place the contractor or subcontractor at financial risk with their employees or continued work on the public work. Additionally, the failure of the public agency to issue a change order or the denial of claims has resulted in costly litigation for the public agency, contractors, and subcontractors. Multiple legislative attempts to address pre-litigation claim disputes have failed.
Existing law authorizes state agencies to arbitrate claim disputes, while local agencies are subject to a different claims resolution process. Subcontractors must rely on submitting their claims for payment through the general contractor or other subcontractor through which they have contracted for services or materials to be provided on the public works project. However, depending upon the general contractor and its desire, on one hand, to help the subcontractor get paid, or, on the other hand, to maintain positive relations with the public agency, the subcontractor may or may not receive an answer from the general contractor as to whether the claim was submitted to the public agency.
This bill seeks to provide a simplified, cost-effective claims resolution procedure to resolve contractor claims prior to arbitration or civil action. This bill would also provide a clear process for a subcontractor to submit claims through a general contractor in order to provide the subcontractor with information as to whether the general contractor has rejected the request to submit the subcontractor’s claim to the public agency.
CHANGES TO EXISTING LAW
Existing law prohibits a local public entity, charter city, or charter county from requiring a bidder (i.e., general contractor) to assume responsibility for the completeness and accuracy of architectural or engineering plans and specifications on public works projects, except on clearly designated design build projects. (Pub. Contract Code Sec. 1104.) However, the local public entity, charter city, or charter county may require a bidder to review architectural or engineering plans and specifications prior to submission of a bid, and report any errors and omissions noted by the contractor to the architect or owner. (Id.) The review by the contractor shall be confined to the contractor’s capacity as a contractor, and not as a licensed design professional. (Id.)
Existing law, prior to the commencement of the public work costing more than $15,000, other than maintenance work or work occasioned by emergency, requires the engineer to prepare and file in his office either full, complete and accurate plans and specifications or a work authorization approved by the engineer describing the work to be performed, and an estimate of the cost thereof, except where other and adequate provision is made by law requiring the preparation and filing of such plans, specifications and estimates of cost by some other officer or in some other office. (Gov. Code Sec. 4004.)
Existing law requires any public works contract of a local public entity which involves digging trenches or other excavations that extend deeper than four feet below the surface to contain a clause which provides the following:
- that the contractor shall promptly, and before the following conditions are disturbed, notify the local public entity, in writing, of any material that may be hazardous waste, as specified, subsurface or latent physical conditions at the site differing from those indicated by information about the site made available to bidders prior to the deadline for submitting bids, and unknown physical conditions at the site of any unusual nature, different materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the contract;
- that the local public entity shall promptly investigate the conditions, and if it finds that the conditions do materially so differ, or do involve hazardous waste, and cause a decrease or increase in the contractor’s cost of, or the time required for, performance of any part of the work shall issue a change order under the procedures described in the contract; and
- that, in the event that a dispute arises between the local public entity and the contractor whether the conditions materially differ, or involve hazardous waste, or cause a decrease or increase in the contractor’s cost of, or time required for, performance of any part of the work, the contractor shall not be excused from any scheduled completion date provided for by the contract, but shall proceed with all work to be performed under the contract. (Pub. Contract Code Sec. 7104.)
Existing law provides that the contractor retains any and all rights provided either by contract or by law which pertain to the resolution of disputes and protests between the contracting parties. (Pub. Contract Code Sec. 7104.)
Existing law prohibits a public agency, including the state, the Regents of the University of California, a city, county, district, public authority, public agency, municipal utility, and any other political subdivision or public corporation of the state, from requiring the contractor to be responsible for the cost of repairing or restoring damage to the work, which damage is determined to have been proximately caused by an act of God (earthquakes in excess of a magnitude of 3.5 on the Richter Scale and tidal waves) in excess of 5 percent of the contracted amount, provided, that the work damaged is built in accordance with accepted and applicable building standards and the plans and specifications of the awarding authority. (Pub. Contract Code Sec. 7105(a).)
Existing law authorizes public agencies to make changes in construction contracts for public improvements in the course of construction to bring the completed improvements into compliance with environmental requirements or standards established by state and federal statutes and regulations enacted after the contract has been awarded or entered into. The contractor is required to be paid for the changes in accordance with the provisions of the contract governing payment for changes in the work or, if no provisions are set forth in the contract, payment shall be as agreed to by the parties. (Pub. Contract Code Sec. 7105(c).)
Existing law provides that where authority to contract is vested in any public agency, excluding the state, the authority includes the power, by mutual consent of the contracting parties, to terminate, amend, or modify any contract within the scope of such authority. (Pub. Contract Code Sec. 7105(d).) However, this provision does not apply to contracts entered into pursuant to any statute expressly requiring that contracts be let or awarded on the basis of competitive bids. (Id.) Contracts of public agencies, excluding the state, required to be let or awarded on the basis of competitive bids pursuant to any statute may be terminated, amended, or modified only if the termination, amendment, or modification is so provided in the contract or is authorized under provision of law. (Id.)
Existing law provides that the compensation payable, if any, for amendments and modifications shall be determined as provided in the contract, and the compensation payable, if any, in the event the contract is so terminated shall be determined as provided in the contract or applicable statutory provision providing for the termination. (Pub. Contract Code Sec. 7105(d).)
Existing law, except as otherwise provided, prohibits a suit for money or damages against a public entity on a cause of action for which a claim is required to be presented until a written claim therefor has been presented to the public entity and has been acted upon by the board, or has been deemed to have been rejected by the board. (Gov. Code Sec. 945.4.)
Existing law prescribes a contract claims resolution process for contracts entered into with a state agency. (Pub. Contract Code Sec. 10240 et seq.)
Existing law requires arbitration of a claim, defined to mean a demand for monetary compensation or damages, arising under or relating to the performance of contracts with a state agency. (Pub. Contract Code Sec. 10240.)
Existing law authorizes a claimant to initiate arbitration no later than 90 days after the date of personal or mail service on the claimant of the final written decision by the appropriate public agency department on the claim; however, this limitation does not apply to any claim founded on any cost audit, latent defect, warranty, or guarantee under the contract. (Pub. Contract Code Sec. 10240.1.)
Existing law prohibits arbitration until the claimant pursues diligently and exhausts, as to the claim, the required administrative procedures set forth in the contract under which the claim arose, unless more than 240 days have elapsed since acceptance of the work by the department. (Pub. Contract Code Sec. 10240.2.)
Existing law provides that unless otherwise agreed by the parties, the arbitration shall be conducted by a single arbitrator selected by the parties from the certified list created by the Public Works Contract Arbitration Committee. (Pub. Contract Code Sec. 10240.3.) If the parties cannot agree on the arbitrator, either party may petition the superior court to appoint one from the panel of arbitrators certified by the Public Works Contract Arbitration Committee. (Id.)
Existing law specifies that no decision made by a department shall be conclusive on any issue in the arbitration. (Pub. Contract Code Sec. 10240.4.)
Existing law requires the Departments of General Services, Transportation, and Water Resources to jointly adopt and may, from time to time, modify, revise, or repeal uniform regulations to implement arbitration provisions and may include, but need not be limited to:
- the method of initiating arbitration;
- the place of hearing based upon the convenience of the parties;
- procedures for the selection of a neutral arbitrator;
- the form and content of any pleading;
- procedure for conducting hearings;
- the providing of experts to assist the arbitrator in the event the assistance is needed;
- the content of the award; and
- simplified procedures for claims of fifty thousand dollars ($50,000) or less. (Pub. Contract Code Sec. 10240.5.)
Existing law authorizes a party to the contract to join in the arbitration as a party, any supplier, subcontractor, design professional, surety, or other person who has so agreed and if the joinder is necessary to prevent a substantial risk of the party otherwise being subjected to inconsistent obligations or decisions. (Pub. Contract Code Sec. 10240.9.)
Existing law does not prevent the parties to the contract, after the claim has arisen, from mutually agreeing in writing to waive the arbitration statutes and to have the claim litigated in a court of competent jurisdiction. (Pub. Contract Code Sec. 10240.10.)
Existing law, within the applicable time periods and upon specified grounds, authorizes a party to petition the court to confirm, correct, or vacate the award rendered by the arbitrator; however, no department may petition to vacate an award without the prior written authorization of its agency secretary. (Pub. Contract Code Sec. 10240.12.) Except where the parties agree not to have the arbitration decision rendered as specified, a court shall vacate the award, or part thereof, if it determines either that the award, or part thereof, is not supported by substantial evidence or that it is not decided under or in accordance with the laws of this state, in which case, the court may order a rehearing before the original arbitrator or remand to the original arbitrator that portion of the dispute which the court concludes the arbitrator failed to determine. (Id.)
Existing law provides that the costs of conducting the arbitration shall be borne equally by the parties, but the arbitrator may allow the prevailing party to recover its costs and necessary disbursements, with interest, other than attorney’s fees, on the same basis as is allowed in civil actions. (Pub. Contract Code Sec. 10240.13.)
Existing law provides a public entity with full authority to compromise or otherwise settle any claim relating to a contract at any time. (Pub. Contract Code Sec. 9201(a).) The public entity is required to include provisions in a public works contract for timely notification of the contractor of the receipt of any third-party claim relating to the contract. (Pub. Contract Code Sec. 9201(b).)
This bill would preclude, until January 1, 2020, any other claim resolution provision and apply to all claims by contractors in connection with public works.
This bill would provide the following definitions:
- “claim” means a separate demand by a contractor by registered mail or certified mail with return receipt requested, for one or more of the following: (a) a time extension, including, without limitation, for relief from damages or penalties for delay assessed by a public entity under a contract for a public works project; (b) payment by the public entity of money or damages or penalties arising from work done by, or on behalf of, the contractor pursuant to the contract for a public works project and payment for which is not otherwise expressly provided or to which the claimant is not otherwise entitled; or (c) payment of an amount that is disputed by the public entity;
- “contractor” means any type of contractor subject to the Contractor’s State License Law who has entered into a direct contract with a public entity for a public works project;
- “public entity” means, without limitation, a state agency, department, office, division, bureau, board, or commission, the California State University, the University of California, a city, including a charter city, county, including a charter county, city and county, including a charter city and county, district, special district, public authority, political subdivision, public corporation, or nonprofit transit corporation wholly owned by a public agency and formed to carry out the purposes of the public agency;
- “public entity” shall not include the Department of Water Resources as to any project under the jurisdiction of that department, the Department of Transportation as to any project under the jurisdiction of that department; the Department of Parks and Recreation as to any project under the jurisdiction of that department, the Department of Corrections and Rehabilitation, as specified, the Military Department as to any project under the jurisdiction of that department, the Department of General Services as to all other projects, and the High-Speed Rail Authority;
- “public works project” means the erection, construction, alteration, repair, or improvement of any public structure, building, road, or other public improvement of any kind; and
- “subcontractor” means any type of contractor subject to the Contractor’s State License Law who either is in direct contract with a contractor or is a lower tier subcontractor.
This bill, upon receipt of a claim, would require the public entity to which the claim applies to conduct a reasonable review of the claim and, within a period not to exceed 45 days, provide the claimant a written statement identifying what portion of the claim is disputed and what portion is undisputed. However, a public entity and a contractor may, by mutual agreement, extend the time period.
This bill would require the claimant to furnish reasonable documentation to support the claim.
This bill, if the public entity needs approval from its governing body to provide the claimant a written statement identifying the disputed portion and the undisputed portion of the claim, and the governing body does not meet within the 45 days following receipt of a claim sent by registered mail, would provide the public entity up to three days following the next duly publicly noticed meeting of the governing body after the 45 day period, or extension expires to provide the claimant a written statement identifying the disputed portion and the undisputed portion.
This bill would require any payment due on an undisputed portion of the claim to be processed and made within 60 days after the public entity issues its written statement; if the public entity fails to issue a written statement, the claim would be deemed rejected in its entirety.
This bill, if the claimant disputes the public entity’s written response, or if the public entity fails to respond to a claim issued within the time prescribed, would authorize the claimant to demand in writing an informal conference to meet and confer for settlement of the issues in dispute, and, upon receipt of a demand in writing sent by registered mail or certified mail, return receipt requested, , the public entity would be required to schedule a meet and confer conference within 30 days for settlement of the dispute.
This bill, within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, would require the public entity to provide the claimant a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed.
This bill would require any payment due on an undisputed portion of the claim to be processed and made within 60 days after the public entity issues its written statement, and any disputed portion of the claim, as identified by the contractor in writing, would be required to be submitted to nonbinding mediation, with the public entity and the claimant sharing the associated costs equally.
This bill would require the public entity and claimant to mutually agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing, and, if the parties cannot agree upon a mediator, each party would select a mediator and those mediators would select a qualified neutral third party to mediate with regard to the disputed portion of the claim.
This bill would provide that if the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the claim, and each party shall bear the fees and costs charged by their respective mediators in selecting the neutral mediator.
This bill would provide that if mediation is unsuccessful, the parts of the claim remaining in dispute would be subject to other applicable claim resolution procedures.
This bill would specify that mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation, and any mediation utilized must conform to the time frames provided in this bill.
This bill would require the mediation conducted pursuant to this bill to excuse any further obligation under Section 20104.4 to mediate (meet and confer) after litigation has been commenced, unless otherwise agreed to by the public entity and the contractor in writing.
This bill would not preclude a public entity from requiring arbitration of disputes under private arbitration or the Public Works Contract Arbitration Program, if under this bill, mediation does not resolve the parties’ dispute.
This bill would specify that failure by the public entity to respond to a claim from a contractor within the time periods described in this bill or to otherwise meet the time requirements of this bill would result in the claim being deemed rejected in its entirety.
This bill would provide that a claim that is denied by reason of the public entity’s failure to have responded to a claim or its failure to otherwise meet the time requirements of this section, shall not constitute an adverse finding with regard to the merits of the claim or the responsibility or qualifications of the claims.
This bill would require amounts not paid in a timely manner to bear interest at 7 percent per annum.
This bill, if a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against a public entity because privity of contract does not exist, would authorize the contractor to present to the public entity a claim on behalf of a subcontractor or lower tier subcontractor.
This bill would authorize a subcontractor to request in writing, either on his or her own behalf or on behalf of a lower tier subcontractor, that the contractor present a claim for work which was performed by the subcontractor or by a lower tier subcontractor on behalf of the subcontractor.
This bill would require the subcontractor requesting that the claim be presented to the public entity to furnish reasonable documentation to support the claim.
This bill, within 45 days of receipt of that written request, would require the contractor to notify the subcontractor in writing as to whether the contractor presented the claim to the public entity and, if the original contractor did not present the claim, provide the subcontractor with a statement of the reasons for not having done so.
This bill would require the text of the provisions provided under this bill or a summary of it to be set forth in the plans or specifications for any public works project that may give rise to a claim under this bill.
This bill would make a waiver of the rights granted by this bill void and contrary to public policy, provided, however, that upon receipt of a claim, the parties may mutually agree to waive, in writing, mediation and proceed directly to the commencement of a civil action or binding arbitration as applicable; and (2) a public entity in its public works contracts may include dispute resolution provisions that comply with this section, including timeframes set forth herein, and that prescribe additional reasonable and equitable terms regarding actions or procedures to be taken by the parties. .
This bill would apply to contracts entered into on or after January 1, 2017.
This bill would find and declare that it is in the best interests of the state and its citizens to ensure that all construction business performed on a public works project in the state that is complete and not in dispute is paid in full and in a timely manner, and that it is of statewide concern to require a charter city, charter county, or charter city and county to follow a prescribed claims resolution process to ensure they are uniform and equitable procurement practices.
This bill would provide that nothing in this bill shall impose liability upon a public entity that makes loans or grants available through a competitive application process, for the failure of an awardee to meet its contractual obligations.
This bill provides that the provisions sunset on January 1, 2020.
COMMENT
1. Stated need for the bill
The author writes:
This bill closes an unfair loophole in the law that allows agencies to indefinitely delay payments to contractors for money owed to them. This is a particular threat to small businesses and minority owned businesses in our state.
There is no law in place requiring agencies to pay claims, in a timely manner, made by contractors for extra work performed and approved by the agency, even when the public agency acknowledges that it owes the contractor for work performed. This places contractors and their workers in difficult financial circumstances.
Furthermore, there is a lack in uniformity for disputing a claim. In many cases, some public agencies have no requirements to respond to a claim or respond to a claim in a timely manner. The breakdown of communication between the public agency and the contractor adds to the burden on the contractor and meeting their payroll obligations.
AB 626, a bill very similar to AB 1347 of 2015, which passed out of this committee unanimously, creates a process that requires agencies to respond to a contractor’s claim, to pay out portions of the work they acknowledge and agree they owe the contractor, and to resolve disputed portions of payment through non-binding mediation.
Specifically, the bill would require a public agency to respond in 45 days to a claim. If the public agency does not respond within 45 days then the claim is deemed denied. If the contractor wishes to continue the claim, then the contractor must respond via registered mail. The public agency then has 30 days to meet & confer with the contractor.
If there is no agreement with the claim during the meet and confer process, if requested by the contractor, again via registered mail, then the public agency and contractor has 10 days to find a mutually agreed upon mediator and set a mediation date. If mediation doesn’t settle the claim, then current practice takes over, which is a civil lawsuit and what this bill is attempting to avoid. Nothing in this measure requires an agency to pay for work they do not approve or agree with.
Many public agencies have removed their opposition as we have worked diligently to address their concerns and establish a fair and equitable process.
To address the Governor’s veto [of AB 1347 (Chiu, 2015)], the bill removes California state agencies from the requirements of AB 626.
2. Public works contracts and change orders
Change orders are at the heart of the controversy involving this bill. When a public work requires extra work unanticipated by the contractor, a change order may be necessary, signed by the public agency and the contractor, to amend the contract to provide that the contractor is performing additional work for which the public agency will pay. When a change order is not executed by the public agency, or its governing body or responsible department, the contractor, having provided the necessary extra work or materials, submits a claim to the public agency alleging the public agency owes the contractor payment for the extra work.
Several cases provide the responsibilities of the contracting parties that emerge when a public work requires additional material or services than originally expected by the contractor. First, case law has established that “a contractor that has agreed to a particular performance at a specified price may not avoid its contractual obligations or seek additional compensation for performing them because unanticipated difficulties are encountered.” (United States v. Spearin (1918) 248 U.S. 132, 136.) However, case law has also settled that a “contractor of public works who, acting reasonably, is misled by incorrect plans and specifications issued by the public authorities as the basis for bids and who, as a result, submits a bid which is lower than he would have otherwise made may recover in a contract action for extra work or expenses necessitated by the conditions being other than as represented.” (Suiza & McCue Constr. Co. v. Superior Court (1962) 57 Cal.2d 508, 510.) Although Public Contract Code Section 7104 requires change orders related to unanticipated difficulties from site conditions to be included in public work contracts, there is no statute requiring change orders resulting from other kinds of unanticipated conditions to be included in public work contracts. Specifically, case law has established that there are two types of differing site conditions that a public entity cannot circumvent or otherwise disclaim liability for through other provisions in the contract: (1) Type 1 differing site conditions, in which the actual site conditions differ from those originally described to bidders; and (2) Type 2 differing site conditions, in which the actual site conditions differ from the conditions ordinarily encountered in the particular type of work in the particular locality. (Condon-Johnson & Associates v. Sacramento Municipal Utility District (2007) 149 Cal.App.4th 1384.) For other unanticipated difficulties not associated with the site conditions for which a change order is not executed, the contractor is left to file a claim for the work performed.
3. Providing informal procedures to submit claims to public agency
Existing law prescribes various requirements regarding the formation, content, and enforcement of state and local public contracts. Existing law applicable to state public contracts generally requires that the resolution of claims related to those contracts be subject to arbitration. Existing law for local agency public works requires all claims made for work arising out of the contract, but not expressly provided for in that contract, that are $375,000 or less to first be resolved through administrative resolution procedures. However, if the contract provides for arbitration, the claim will have to be arbitrated according to express arbitration statutes. The arbitration statutes apply to both local agency and state agency public work contracts.
This bill would prescribe a new claims resolution process by which a contractor can submit a claim to a public entity as follows:
- applies to all claims submitted by a contractor to a public entity, as specified;
- the contractor must furnish reasonable documentation to support the claim;
- the public entity must conduct a reasonable review of the claim and, within 45 days, provide the contractor with a written statement identifying what portion of the claim is disputed and what portion is undisputed;
- the time frame may be extended by mutual agreement or if the public entity needs approval from its governing body to provide the claimant a written statement identifying the disputed portion and the undisputed portion of the claim, then the public entity may have additional time, as specified;
- any payment due on an undisputed portion of the claim must be processed and made within 60 days of issuance of the written statement;
- if no statement is issued by the public agency, the claim is rejected in its entirety;
- the claimant may demand an informal meet-and-confer conference for settlement of the issues in dispute, as specified,; and
- establishes time frames for payment of settled claims and provide for nonbinding mediation for disputed claims.
Proponents of this bill state that existing laws protect public agencies from having to pay any unfair or unjust claims made by a contractor. However, proponents argue, these conflict resolution statutes do not require the public agency to pay contractors in a timely manner for extra work performed on public works contracts, even when that work was requested by the owner and subsequently performed by the contract in good faith. Proponents contend that “contractors who perform extra work put themselves in great financial risk. California public works contractors often have to wait months, and in some cases up to years, for payment for work. Contractors who perform this work to the benefit of the public agency must still pay for their construction materials, employee wages and benefits and their overhead. Not being compensated in a timely manner can result in a contractor being forced to reduce capacity, or worse, close their business.”
Proponents contend that this bill would put a process in place that requires public agencies to respond to a contractor claim, would require the agency to pay out portions of the work they acknowledge or agree they owe to the contractor, and implements a fair process for resolving any disputed portions of the claim. The proponents note that this bill does not require public agencies to pay for any work it does not request, accept, or approve but allows the public agency to deny or dispute any claim for payment. Yet, the delay of trust fund contributions with respect to trade unions can cause the loss of health insurance due to a contractor’s inability to make payments, and the lack of prompt payment for extra work leaves many contractors without the necessary resources needed to bid the next project and continue doing business, which ultimately diminishes work opportunities.
4. Providing clarity for subcontractor pass-through claims
On public work projects, the public entity typically contracts directly with a general contractor to perform the work. The general contractor then contracts with subcontractors, such as roofers, excavators, and plumbers, who perform specialized work on the project. In this way, a subcontractor does not have a direct contract with the public agency and therefore lacks privity of contract. Accordingly, the subcontractor seeking payment on extra work performed must rely on one of a few methods for payment.
First, the subcontractor may attempt to recover payment from the general contractor. However, depending upon the public agency’s position on which party is responsible for the extra work needed to continue or complete the project, the public agency may have failed to pay the general contractor for extra work, and the general contractor may be unable to pay the subcontractor for the extra work.
Second, the subcontractor may submit a stop notice to the public entity to withhold a portion of the construction funds sufficient to satisfy the subcontractor’s claim. Rather than attaching to real property, the stop notice attaches to the construction loan fund, or to money in the hands of the public entity that otherwise is to be paid to the general contractor. The stop notice has the effect of intercepting these funds, and the ultimate result of the enforcement of a stop notice is entry of a judgment against the public agency for the amount claimed in the stop notice. This procedure is not preferred as it does not provide payment to the subcontractor in a timely fashion. As discussed above, a subcontractor who is unable to recover payment for work or materials provided in a good faith effort to keep the public project moving forward or reaching completion puts himself or herself at risk if the payment is necessary to pay employees, purchase materials, or bid on other contracts.
Another method for recovering payment is to request the claim be presented to the public agency through the general contractor, known as a “pass-through” claim. Case law provides that “[a]s a matter of law, a general contractor can present a subcontractor’s claim on a pass-through basis. (Maurice L. Bein, Inc. v. Housing Authority (1958) 157 Cal.App.2d 670. . . .) When a public agency breaches a construction contract with a contractor, damage often ensues to a subcontractor. In such a situation, the subcontractor may not have legal standing to assert a claim directly against the public agency due to a lack of privity of contract, but may assert a claim directly against the general contractor. In such a case, a general contractor is permitted to present a pass-through claim on behalf of the subcontractor against the public agency. (Citation omitted.)” (Howard Contracting, Inc. v. G.A. MacDonald Construction Co., Inc. (1998) 71 Cal.App.4th 38, 60.) In the Howard case, the City of Los Angeles was held to have failed to disclose material information to the general contractor and its subcontractors concerning project restrictions and difficulties, failed to timely obtain construction permits from regulatory agencies, and failed to provide access to the work site. (Id. at p. 48.) The Howard case provides a poignant example of the types of situations in which the general contractor and subcontractor has performed their duties under their respective contracts in good faith, yet the public agency created delays that required the extra work performed, then failed and refused to pay the general contractor work performed, who had then failed to pay the subcontractor.
In these situations, the quickest method for a subcontractor to receive payment for extra work performed is to request that the general contractor submit the claim for payment to the public agency. Although a subcontractor can already attempt this line of recourse, the general contractor is under no obligation to submit the claim to the public agency. Further, the general contractor, who may also be attempting to recover payment for extra work from the public agency, may decide against submitting the claim in order to maintain positive communication with the public agency. The general contractor is under no obligation to advise the subcontractor whether or not the claim was submitted to the public agency for payment. Accordingly, this bill would allow the subcontractor to submit the claim through the general contractor, but establish a timeframe of 45 days of receipt of the written request for the general contractor to notify the subcontractor whether the general contractor presented the claim to the public agency. Further, if the general contractor opted against presenting the claim to the public agency, the bill would require the general contractor to provide the subcontractor a statement of reasons for not presenting the claim. These provisions would provide better clarity of the claim review process and important claim information for general contractors and subcontractors.
5. “Home Rule” Doctrine
The California Constitution, Article XI, Section 7, provides that a county or city may make and enforce within its limits all local, policy, sanitary, and other ordinances and regulations not in conflict with general laws. However, a charter city is provided the ability to make and enforce all ordinances and regulations in respect to municipal affairs, subject only to restrictions and limitations provided in its several charters, and, in respect to other matters, the charter city is subject to general laws. (Cal. Const., art. XI, sec. 5.) A city charter or municipal law which may have precedence over a conflicting state statute purporting to regulate a municipal matter is known as the “home rule” doctrine.
In Dibbs v. County of San Diego (1994) 8 Cal.4th 1200, the California Supreme Court in contracting the home rule authority of charter cities and chartered counties stated that, whereas charter county “home rule” authority is limited to matters concerning the structure and operation of local government, the version of “home rule” afforded to a charter city is substantially more expansive. However, the California Constitution does not define what constitutes a municipal affair. Accordingly, courts must determine whether the facts of each case implicate a matter under municipal or state concern. (County of Riverside v. Superior Court (2003) 30 Cal.4th 278, 292.)
The “home rule” doctrine becomes important in a public work if the public agency is a charter city asserting that a state statute does not apply to the charter city. Such was the case in Howard Contracting, Inc. v. G.A. MacDonald Construction Co. (1998) 71 Cal.App.4th 38, 51, in which the City of Los Angeles claimed not to be subject to a state law interfering with the City’s public work contract. At issue was Public Contract Code Section 7102, which provides that contract provisions in public works construction contracts, and the subcontracts thereunder, which attempt to limit the public entity’s liability for delays it causes, do not preclude the recovery of damages by the contractor or subcontractor. The statute also provides that a public agency cannot require the waiver, alteration, or limitation of the applicability of this section. However, the statute cannot be construed to void any provision in a public works construction contract that requires notice of delays or provides for liquidated damages.
In the Howard case, the court discussed the City’s claim under the home rule doctrine of immunity from liability for damages caused by its own delays:
In California Federal, the Supreme Court established a test to determine whether the state has infringed upon a charter city’s sovereignty under the “home rule” doctrine. (54 Cal. 3d at pp. 16-18.) Under the first prong of the test, the existence of an actual conflict between a state statute and a local measure must be ascertained. Once a conflict is found to exist, a further determination must be made whether the subject matter of the statutory enactment is more properly characterized as a local or statewide concern.
In this case, the purported conflict with a provision of a state statute does not relate to a charter provision or municipal enactment, but to a “no damage for delay” clause contained in the Standard Specifications of the contract between MacDonald Construction and the City. Because the City fails to establish a conflict between the Public Contract Code and any charter provision or municipal enactment, Public Contract Code section 7102 applies. As a consequence, the contract clause purporting to exempt the City from liability for damages resulting from delays caused by the City is unenforceable under section 7102. (Id.)
Because the Howard case established that charter city public work contracts are subject to state statutes under the Public Contract Code, the provisions in this bill would likely not be superseded by a city’s charter or municipal laws because the provisions of the bill involve a statewide concern, are not solely aimed at regulating charter cities, and the bill’s provisions likely do not relate to a city’s charter or municipal laws but rather relate to public work contracts and obligations thereon.
Support: Air Conditioning Sheet Metal Association; Air-Conditioning & Refrigeration Contractors Association; Advanced Cable Solutions, Inc.; Architectural Glass& Aluminum; Associated General Contractors (AGC); Ayoob & Perry Plumbing Co.; Baker Electric; Big Sky Electric; California Chapters of the National Electrical Contractors Association (NECA); California Legislative Conference of the Plumbing; California-Nevada Conference of Operating Engineers; California State Association of Electrical Workers; California State Pipe Trades Council; Carter, Wetch & Associates; Collins Electrical Company, Inc.; Creative Shower Door Corp.; Cupertino Electric, Inc.; Electro Construction Corp.; Finishing Contractors Association of Southern California; Fuller Electric; Giroux Glass, Inc.; Heating and Piping Industry; International Union of Elevator Constructors; KBI Painting, Inc.; Mike Cox Electric Company, Inc.; Morrow-Meadows Corporation; Neal Electric Corp.; Neubauer Electric, Inc.; Northern California Allied Trades; Pacific Glazing Contractors; Painting and Decorating Contractors Association of Sacramento; Piping Industry Progress & Education Trust Fund; Pyramid Painting, Inc.; Roundtree Glass Company; Santa Barbara Glass Company; Schetter Electric, Inc.; Smith and Sons Electric, Inc.; State Building and Construction Trades Council, AFL-CIO; TNT Industrial Contractors, Inc.; Wall and Ceiling Alliance; Western States Council of Sheet Metal Workers; 44 individuals
Opposition: None Known
HISTORY
Source: California State Council of Laborers; United Contractors
Related Pending Legislation: None Known
Prior Legislation:
AB 1347 (Chiu, 2015) nearly identical to this bill. This bill was vetoed by the Governor.
AB 2471 (Frazier, 2014) would have required state and local public entities engaged in a public works contract awarded to the lowest bidder to promptly issue change orders when extra work is required of the contractor or subcontractor. AB 2471 died in the Senate Appropriations Committee without a hearing.
AB 2096 (Miller, 2010) would have allowed a public agency and a contractor to mutually agree to resolve a claim through independent arbitration. AB 2096 died in the Assembly Judiciary Committee without a hearing.
AB 541 (Duvall, 2009) was substantially similar to AB 2096 and died in the Assembly Judiciary Committee without a hearing.
AB 216 (Beall, 2009) would have reformed pre-litigation claims resolution procedures for local public works projects. AB 216 was held under submission in the Assembly Appropriations Committee.
SB 1642 (Yee, 2008) would have established alternative dispute resolution procedures for local public works projects costing over $50,000. SB 1642 was held under submission in the Senate Appropriations Committee.
Prior Vote:
Assembly Floor (Ayes 55, Noes 24)
Assembly Appropriations Committee (Ayes 12, Noes 4)
Assembly Higher Education Committee (Ayes 11, Noes 2)
**************
AB 626
Page 3
ASSEMBLY THIRD READING
AB 626
(Low)
As Amended June 1, 2015
Majority vote
Committee |
Votes |
Ayes |
Noes |
Higher Education |
11-2 |
Medina, Bloom, Chávez, Irwin, Jones-Sawyer, Levine, Linder, Low, Santiago, Weber, Williams |
Baker, Harper |
Appropriations |
12-4 |
Gomez, Bonta, Calderon, Daly, Eggman, Eduardo Garcia, Gordon, Holden, Quirk, Rendon, Weber, Wood |
Bigelow, Gallagher, Jones, Wagner |
SUMMARY: Requires the California Community Colleges (CCC) Chancellor's Office (CCCCO) to convene a group of stakeholders to develop recommendations on funding strategies in order for CCC districts (CCDs) to achieve the statutory goal of 75% full-time (F/T) to 25% part-time (P/T) faculty teaching at CCCs. Specifically, this bill:
Finds and declares the following intent of the Legislature:
In 1988, the Education Code was amended to read that "the Legislature wishes to recognize and make efforts to address longstanding policy of the board of governors that at least 75 percent of the hours of credit instruction in the California Community Colleges, as a system, should be taught by full-time instructors;"
The expectations for F/T faculty go beyond classroom instruction to include, among other full-service activities, all of the following: developing and evaluating academic programs; holding office hours and participating in meetings after classes; student advising; participation in institutional governance; and, accreditation-related responsibilities such as the assessment of departmental and student learning outcomes, curriculum development, and preparing institutional self-studies;
In 2014, the percentage of credit courses taught by F/T faculty in the system was only 56.14%;
The Legislature acknowledged the commitment of the CCC Board of Governors (BOG), through its regular budget process, to evaluate resource needs and seek funding for essential educational priorities that contribute to student success. These priorities include, but are not necessarily limited to, the hiring of more F/T faculty and increasing support for P/T faculty;
In the Seymour-Campbell Student Success Act of 2012, the Legislature acknowledged the importance of counselors, who, along with librarians, are considered to be faculty for purposes of the 75% goal;
Students enrolled in noncredit education are most often deprived of the benefit of working with F/T faculty, as statewide goals relating to the ratio of F/T to P/T faculty have yet to be developed with respect to noncredit courses; and,
The CCC BOG work together with the Academic Senate for the CCC and other relevant entities to develop goals for the F/T to P/T faculty ratio in noncredit education.
Requires the CCCCO to convene a group of stakeholders, which shall include faculty and students, on or before July 1, 2016, and every four years thereafter, to develop recommendations on funding strategies to enable the community colleges to achieve the 75% standard and increase the participation of districts in the support of P/T faculty, including, but not limited to, support of P/T faculty office hours.
Requires the CCCCO, on or before March 1, 2017, and every four years thereafter, to report the recommendations developed by the stakeholder group to the Legislature.
Makes technical and clarifying changes to existing law.
EXISTING LAW:
Defines "faculty" as those employees of CCD who are employed in academic positions that are not designated as supervisory or management, as specified. Faculty include, but are not limited to, instructors, librarians, counselors, community college health services professionals, handicapped student programs and services professionals, and extended opportunity programs and services professionals (Education Code Section 87003).
Defines any person who is employed to teach for not more than 67% of the hours per week considered a full-time assignment to be a temporary (P/T) employee (EC Sections 87482.5 and 87882).
Requires the CCC BOG to adopt regulations regarding the percent of credit instruction taught by F/T faculty and authorizes CCDs with less than 75% F/T instructors to apply a portion of their "program improvement" funds toward reaching the 75 percent goal (commonly referred as "75/25") (EC Section 87482.6).
The state has stopped providing program improvement funds and the BOG has since required CCDs to provide a portion of their growth funds to hiring more F/T faculty.
FISCAL EFFECT: According to the Appropriations Committee, absorbable costs for the Chancellor's Office to convene the stakeholders and report to the Legislature.
COMMENTS: Background. The Education Code, in 1988, was amended to read, "The Legislature wishes to recognize and make efforts to address longstanding policy of the board of governors that at least 75 percent of the hours of credit instruction in the California Community Colleges, as a system, should be taught by full-time instructors." As stated in the Legislative findings of this measure, in 2014, the percent of credit courses taught by F/T faculty was only 56.14%, indicating the system has not come close to reaching the goal of 75%.
Part-time faculty have been expected to provide the same high quality instruction as their F/T colleagues, but they often times are not able to provide regular student office hours and are not necessarily compensated for professional responsibilities linked to student success.
The Seymour-Campbell Student Success Act of 2012 specifies that hiring of F/T faculty, including counselors, and providing for P/T faculty support, are "essential educational priorities that contribute to student success."
Analysis Prepared by: Jeanice Warden / HIGHER ED. / (916) 319-3960 FN: 0000756
AB 626
Page 2
Date of Hearing: May 6, 2015
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Jimmy Gomez, Chair
AB 626
(Low) – As Amended April 13, 2015
Policy Committee: |
Higher Education |
Vote: |
11 - 2 |
|
|
|
|
|
|
|
|
Urgency: No State Mandated Local Program: Yes Reimbursable: Yes
SUMMARY:
This bill requires, under specified circumstances, that community college districts (CCDs) to provide funding specifically to increase their full-time/part-time (FT/PT) faculty ratio and increase support for PT faculty, as specified. Specifically, this bill:
Requires CCDs, when state funds are specifically appropriated for the Student Success and Support Program (SSSP), and funds have not been specifically designated in the budget to increase the FT/PT faculty ratio and to support PT faculty, if:
There is a district matching requirement for the SSSP fund, to allocate one-half of districts' matching funds as follows:
Districts with between 67% and 75% of credit instruction hours taught by FT faculty in the prior fiscal year must use up to 33% of the allocation as needed to reach the 75% state standard for this measure.
Districts with less than 67% of credit instruction hours taught by FT faculty in the prior fiscal year must use up to 40% of the allocation as needed to reach the 75% state standard for this measure.
Requires funds remaining after the allocations in (a) and (b), to the extent feasible, and consistent with an applicable collective bargaining agreement, to be divided between expenditures in support of functions performed by FT faculty and those in support of functions performed by PT faculty in areas that contribute to student success.
There is no district matching requirement for the SSSP funding, to allocate one-half of the state SSSP funds they receive as indicated in (i) or (ii), as applicable, and (iii).
Specifies that, once a district has achieved at least a 75% FT/PT faculty ratio and PT faculty are fully-supported for those activities contributing to student success, as determined by the district, the funds referred to in (a) and (b) may be allocated for other purposes consistent with the SSSP.
Requires the California Community Colleges (CCC) Board of Governors (BOG) to adopt regulations to implement the above.
States legislative intent that the BOG work with the Academic Senate of the CCC and others to develop goals for the FT/PT faculty ratio in noncredit instruction.
FISCAL EFFECT:
The bill could result in a reallocation of community college funding, and would depend on (a) the amount of state funds designated for SSSP and whether state funds are also directed for increasing the FT/PT ratio and for supporting PT faculty, and (b) the amount of district matching funds for SSSP. For example, in the current-year, state SSSP funding totals $200 million, there is no designated funding to increase the FT/PT ratio, and the districts' SSSP totals $400 million. Therefore, under the bill, $200 million of the districts' match would have been reallocated to increase the FT/PT ratio (almost $80 million) and to support FT and PT faculty ($120 million). (In 2014, only three districts' FT/PT ratio exceeded 75% and in only six districts did the ratio exceed 67%.)
The total cost statewide to reach 75% for FT/PT and to provide more support to PT faculty would be up to several hundred million dollars.
COMMENTS:
Background. The Education Code, states “The Legislature wishes to recognize and make efforts to address longstanding policy of the board of governors that at least 75 percent of the hours of credit instruction in the California Community Colleges, as a system, should be taught by full-time instructors.” As stated in the Legislative findings of this measure, in 2014, the percent of credit courses taught by F/T faculty statewide was only 56.14%, indicating the system has not come close to reaching the goal of 75%.
Purpose. According to the author, with F/T faculty and P/T faculty support being "essential educational priorities that contribute to student success," "logic follows that if there are no other state directed monies for purposes of improving the "75/25", full-time hiring or part-time support, that SSSP funds should be used for these purposes." The author contends this measure follows current Education Code that outlines a differentiated amount of spending for districts based on their local "75/25" ratio.
Related Legislation. SB 373 (Pan), pending in Senate Appropriations, caps the number of PT faculty and requires CCDs to only hire FT faculty until they reach the 75% threshold.
Analysis Prepared by: Chuck Nicol / APPR. / (916) 319-2081
AB 626
Page 5
Date of Hearing: April 21, 2015
ASSEMBLY COMMITTEE ON HIGHER EDUCATION
Jose Medina, Chair
AB 626
(Low) – As Amended April 13, 2015
SUBJECT: Community colleges: employees
SUMMARY: Repeals the requirement of existing law to expend a portion of the program improvement allocation to increase the ratio of full-time (F/T) to part-time (P/T) faculty and, with respect to California Community College (CCC) districts (CCD) that have not reached the 75% standard, would require similar expenditures of Student Success and Support Program (SSSP) funds to increase the ratio, and to support P/T faculty. Specifically, this bill:
Finds and declares the following intent of the Legislature:
In 1988, the Education Code was amended to read that “the Legislature wishes to recognize and make efforts to address longstanding policy of the board of governors that at least 75 percent of the hours of credit instruction in the California Community Colleges, as a system, should be taught by full-time instructors;”
The expectations for F/T faculty go beyond classroom instruction to include, among other full-service activities, all of the following: developing and evaluating academic programs; holding office hours and participating in meetings after classes; student advising; participation in institutional governance; and, accreditation-related responsibilities such as the assessment of departmental and student learning outcomes, curriculum development, and preparing institutional self-studies;
In 2014, the percentage of credit courses taught by F/T faculty in the system was only 56.14%;
The Legislature acknowledged the commitment of the CCC Board of Governors (BOG), through its regular budget process, to evaluate resource needs and seek funding for essential educational priorities that contribute to student success. These priorities include, but are not necessarily limited to, the hiring of more F/T faculty and increasing support for P/T faculty;
In the Seymour-Campbell Student Success Act of 2012, the Legislature acknowledged the importance of counselors, who, along with librarians, are considered to be faculty for purposes of the 75% goal;
Students enrolled in noncredit education are most often deprived of the benefit of working with F/T faculty, as statewide goals relating to the ratio of F/T to P/T faculty have yet to be developed with respect to noncredit courses; and,
The CCC BOG work together with the Academic Senate for the CCC and other relevant entities to develop goals for the F/T to P/T faculty ratio in noncredit education.
Reiterates the long standing intent of the Legislature to improve the equity and predictability of community college funding in order to enhance the ability of both the F/T and P/T faculty of the CCC to provide high-quality instructional services.
Specifies that until the provisions of existing law regarding program-based funding are implemented by a standard adopted by the BOG, CCDs that have less than 75% of their hours of credit instruction taught by F/T instructors shall be subject to both of the following:
In a fiscal year when funds are specifically appropriated for purposes of the SSSP, as specified, and in which funds have not been specifically designated to increase the ratio of F/T faculty to P/T faculty, and to support P/T faculty in programs, one-half of the amount of the district match requirement, as specified, shall be allocated in the following manner: i) districts that, in the prior fiscal year, had between 67% and 75% of their hours of credit instruction taught by F/T instructors shall apply up to 33% of this allocation as necessary to reach the 75% standard. Districts that, in the prior fiscal year, had less than 67% of their hours of credit instruction taught by F/T instructors shall apply up to 40% of this allocation as necessary to reach the 75% standard; and, ii) the funds remaining after allocations are made, as specified, shall, to the extent feasible, and in a manner consistent with an applicable collective bargaining agreement, be divided between expenditures in support of functions performed by F/T faculty and expenditures in support of functions performed by P/T faculty, with the allocations for P/T faculty support used, to the extent feasible, for the funding of the participation of P/T faculty in areas that contribute to student success, which may include office hours, as determined locally; and,
In a fiscal year when funds are specifically appropriated for purposes of the SSSP, as specified, and in which funds have not been specifically designated to increase the ratio of F/T faculty to P/T faculty, and to support P/T faculty in programs, but in which there is no district matching requirement, one-half of the SSSP funds received by the district shall be allocated, as specified.
Once a district has achieved the goal of at least 75% of credit instruction hours being taught by F/T faculty, with P/T faculty being fully supported for those activities that contribute to student success as determined locally, the district may use the funds, as specified, for other purposes that are consistent with the SSSP.
Specifies that the BOG shall adopt regulations for the effective administration of this section. Unless and until amended by the board of governors, the regulations shall provide as follows:
Specifies CCC Chancellor shall compute and report to each CCD the number of F/T faculty which are to be secured through the use of the prescribed portion of the SSSP revenue allocated to each district, or district matching funds, as applicable. This computation shall be made by dividing revenue required to be expended, as specified; and,
Specifies by March 15 of each year, the CCC Chancellor shall report to each district an estimate of the number of F/T faculty to be secured based upon the appropriation of revenues contained in the annual Budget Bill and the district match requirement.
Requires, should the Commission on State Mandates determine this measure contains state mandated costs, that the appropriate entities receive reimbursement.
Makes technical and clarifying changes to existing law.
EXISTING LAW:
Defines “faculty” as those employees of CCD who are employed in academic positions that are not designated as supervisory or management, as specified. Faculty include, but are not limited to, instructors, librarians, counselors, community college health services professionals, handicapped student programs and services professionals, and extended opportunity programs and services professionals (Education Code Section 87003).
Defines any person who is employed to teach for not more than 67% of the hours per week considered a full-time assignment to be a temporary (P/T) employee (EC Sections 87482.5 and 87882).
Requires the CCC BOG to adopt regulations regarding the percent of credit instruction taught by F/T faculty and authorizes CCDs with less than 75% F/T instructors to apply a portion of their "program improvement" funds toward reaching the 75% goal (commonly referred as "75/25") (EC Section 87482.6).
The state has stopped providing program improvement funds and the BOG has since required CCDs to provide a portion of their growth funds to hiring more F/T faculty.
FISCAL EFFECT: Unknown
COMMENTS: Background. The Education Code, in 1988, was amended to read, “The Legislature wishes to recognize and make efforts to address longstanding policy of the board of governors that at least 75 percent of the hours of credit instruction in the California Community Colleges, as a system, should be taught by full-time instructors.” As stated in the Legislative findings of this measure, in 2014, the percent of credit courses taught by F/T faculty was only 56.14%, indicating the system has not come close to reaching the goal of 75%.
Part-time faculty have been expected to provide the same high quality instruction as their F/T colleagues, but they often times are not able to provide regular student office hours and are not necessarily compensated for professional responsibilities linked to student success.
The Seymour-Campbell Student Success Act of 2012 specifies that hiring of F/T faculty, including counselors, and providing for P/T faculty support, are "essential educational priorities that contribute to student success."
Purpose of the measure. According to the author, with F/T faculty and P/T faculty support being "essential educational priorities that contribute to student success," "logic follows that if there are no other state directed monies for purposes of improving the "75/25", full-time hiring or part-time support, that SSSP funds should be used for these purposes." The author contends this measure follows current Education Code that outlines a differentiated amount of spending for districts based on their local "75/25" ratio.
AB 626 suggests that when a local match is required for districts to secure their SSSP funds, then one-half of the match would be used to advance on the "75/25" scale and support P/T faculty. In years where there is no match, then one-half of the state allocation of the SSSP funds would be used for the full- and part-time faculty support. Once a district reaches the 75% goal and supports P/T faculty consistent with local needs, then all new SSSP monies would be applied consistent with the Student Success and Support Act.
Policy consideration. Existing funding for the SSSP is targeted to fully implement core services: orientation; assessment; counseling; advising; and other education planning services needed to assist a student in making an informed decision about his/her education goal and course of study and to develop an education plan; and, follow up for at-risk students. Additionally, SSSP funds may only be used for core services and any CCD or college receiving SSSP funding must agree to implement the CCC BOG's system of common assessment.
This bill stipulates that in a fiscal year when funds are specifically appropriated for purposes of the SSSP, and in which funds have not been specifically designated to increase the ratio of F/T faculty to P/T faculty, and to support P/T faculty in programs, one-half of the amount of the district match requirement shall be allocated, as specified, to increasing the ratio of F/T faculty. It is presently unclear as to what core services may not receive full funding if a CCD has to use one-half of its SSSP match requirement for the sole purpose of increasing the ratio of F/T faculty.
The author and Committee may wish to consider lowering the amount of the CCD match requirement having to be allocated for purposes of increasing the ratio of F/T faculty.
REGISTERED SUPPORT / OPPOSITION:
Support
Academic Senate for California Community Colleges
California Community College Independents
California Federation of Teachers
Opposition
None on file.
Analysis Prepared by: Jeanice Warden / HIGHER ED. / (916) 319-3960
Bill Author
Bill Co-Author(s):