SB 1006: Electricity: transmission capacity: reconductoring and grid-enhancing technologies.
- Session Year: 2023-2024
- House: Senate
- Latest Version Date: 2024-09-25
Current Status:
Passed
(2024-09-25: Chaptered by Secretary of State. Chapter 597, Statutes of 2024.)
Introduced
In Committee
First Chamber
In Committee
Second Chamber
Enacted
Existing law establishes the policy of the state that eligible renewable energy resources and zero-carbon resources supply 90% of all retail sales of electricity to California end-use customers by December 31, 2035, 95% of all retail sales of electricity to California end-use customers by December 31, 2040, 100% of all retail sales of electricity to California end-use customers by December 31, 2045, and 100% of electricity procured to serve all state agencies by December 31, 2035.
This bill would require each transmission utility, as defined, on or before January 1, 2026, and every 2 years thereafter, to prepare a study of the feasibility of projects using grid-enhancing technologies to achieve, among other purposes, increased capacity to connect new renewable energy and zero-carbon resources, as provided. The bill would require each transmission utility, on or before January 1, 2026, and at least every 4 years thereafter, to prepare a study of which of its transmission lines can be reconductored with advanced conductors to achieve, among other purposes, increased capacity to connect new renewable energy and zero-carbon resources, as provided. The bill would, upon completion of those studies, require each transmission utility to submit the studies to the Independent System Operator, as specified, and would require each transmission utility to request that the Independent System Operator review the results of the studies as part of the annual transmission planning process for economic, reliability, and policy goals. The bill would, upon submission to the Independent System Operator, require the transmission utilities to make their studies publicly available. The bill would specify that information in the studies that is determined by the Independent System Operator, in consultation with the transmission utilities, to be necessary to protect the security of the electrical transmission system is to be withheld from public disclosure.
Under existing law, a violation of the Public Utilities Act is a crime.
Because the above-described requirements would be a part of the act, a violation of which would be a crime, this bill would impose a state-mandated local program.
Existing constitutional provisions require that a statute that limits the right of access to the meetings of public bodies or the writings of public officials and agencies be adopted with findings demonstrating the interest protected by the limitation and the need for protecting that interest.
This bill would make legislative findings to that effect.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law establishes the policy of the state that eligible renewable energy resources and zero-carbon resources supply 90% of all retail sales of electricity to California end-use customers by December 31, 2035, 95% of all retail sales of electricity to California end-use customers by December 31, 2040, 100% of all retail sales of electricity to California end-use customers by December 31, 2045, and 100% of electricity procured to serve all state agencies by December 31, 2035.
This bill would require each transmission utility, as defined, on or before January 1, 2026, and every 2 years thereafter, to prepare a study of the feasibility of projects using grid-enhancing technologies to achieve, among other purposes, increased capacity to connect new renewable energy and zero-carbon resources, as provided. The bill would require each transmission utility, on or before January 1, 2026, and at least every 4 years thereafter, to prepare a study of which of its transmission lines can be reconductored with advanced conductors to achieve, among other purposes, increased capacity to connect new renewable energy and zero-carbon resources, as provided. The bill would, upon completion of those studies, require each transmission utility to submit the studies to the Independent System Operator, as specified, and would require each transmission utility to request that the Independent System Operator review the results of the studies as part of the annual transmission planning process for economic, reliability, and policy goals. The bill would, upon submission to the Independent System Operator, require the transmission utilities to make their studies publicly available. The bill would specify that information in the studies that is determined by the Independent System Operator, in consultation with the transmission utilities, to be necessary to protect the security of the electrical transmission system is to be withheld from public disclosure.
Under existing law, a violation of the Public Utilities Act is a crime.
Because the above-described requirements would be a part of the act, a violation of which would be a crime, this bill would impose a state-mandated local program.
Existing constitutional provisions require that a statute that limits the right of access to the meetings of public bodies or the writings of public officials and agencies be adopted with findings demonstrating the interest protected by the limitation and the need for protecting that interest.
This bill would make legislative findings to that effect.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law vests the Public Utilities Commission with jurisdiction over public utilities, including electrical corporations. Existing law establishes the policy of the state that eligible renewable energy resources and zero-carbon resources supply 90% of all retail sales of electricity to California end-use customers by December 31, 2035, 95% of all retail sales of electricity to California end-use customers by December 31, 2040, 100% of all retail sales of electricity to California end-use customers by December 31, 2045, and 100% of electricity procured to serve all state agencies by December 31, 2035.
This bill would require each transmission utilities, utility, as defined, on or before January 1, 2026, and every 2 years thereafter, to prepare a study of the feasibility of projects using grid-enhancing technologies to achieve, among other purposes, increased capacity to connect new renewable energy and zero-carbon resources, as provided. The bill would require each transmission utility, on or before January 1, 2026, and at least every 4 years thereafter, to prepare a study of which of its transmission lines can be reconductored with advanced conductors to achieve, among other purposes, increased capacity to connect new renewable energy and zero-carbon resources, as provided. The bill would, upon completion of those studies, require the each transmission utilities utility to submit the studies to the Independent System Operator, as specified, and would require the each transmission utility to request that the Independent System Operator review the results of the studies as part of the annual transmission planning process for economic, reliability, and policy goals. The bill would, upon submission to the Independent System Operator, require the transmission utilities to make their studies publicly available. The bill would specify that information in the studies that is determined by the Independent System Operator Operator, in consultation with the transmission utilities, to be necessary to protect the security of the electrical transmission system is to be withheld from public disclosure.
Under existing law, a violation of the Public Utilities Act is a crime.
Because the above-described requirements would be a part of the act, a violation of which would be a crime, this bill would impose a state-mandated local program.
Existing constitutional provisions require that a statute that limits the right of access to the meetings of public bodies or the writings of public officials and agencies be adopted with findings demonstrating the interest protected by the limitation and the need for protecting that interest.
This bill would make legislative findings to that effect.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law vests the Public Utilities Commission with jurisdiction over public utilities, including electrical corporations. Existing law establishes the policy of the state that eligible renewable energy resources and zero-carbon resources supply 90% of all retail sales of electricity to California end-use customers by December 31, 2035, 95% of all retail sales of electricity to California end-use customers by December 31, 2040, 100% of all retail sales of electricity to California end-use customers by December 31, 2045, and 100% of electricity procured to serve all state agencies by December 31, 2035. Under existing law, a violation of the Public Utilities Act is a crime.
This bill would require transmission utilities, as defined, on or before January 1, 2026, to jointly prepare a grid-enhancing technologies strategic plan that is designed to, among other things, cost-effectively increase transmission capacity and increase capacity to connect new renewable energy and zero-carbon resources. and every 2 years thereafter, to prepare a study of the feasibility of projects using grid-enhancing technologies to achieve, among other purposes, increased capacity to connect new renewable energy and zero-carbon resources, as provided. The bill would require each transmission utility, on or before January 1, 2026, and at least every 4 years thereafter, to complete an evaluation prepare a study of which of its transmission and distribution lines can be reconductored with advanced conductors in a cost-effective manner to, among other things, increase transmission or distribution capacity and increase capacity to connect new renewable energy and zero-carbon resources. to achieve, among other purposes, increased capacity to connect new renewable energy and zero-carbon resources, as provided. The bill would, upon completion of the plan and the evaluation, those studies, require the transmission utilities to submit the plan and evaluation to the commission and to make the plan and evaluation publicly available. The bill would require the plan and evaluation to include a timeline for implementation, as specified. The bill would require each transmission utility to report the progress in implementing the plan in its integrated resource plan. studies to the Independent System Operator, as specified, and would require the transmission utility to request that the Independent System Operator review the results of the studies as part of the annual transmission planning process for economic, reliability, and policy goals. The bill would, upon submission to the Independent System Operator, require the transmission utilities to make their studies publicly available. The bill would specify that information in the studies that is determined by the Independent System Operator to be necessary to protect the security of the electrical transmission system is to be withheld from public disclosure.
Under existing law, a violation of the Public Utilities Act is a crime.
Because the above-described requirements would be a part of the act, a violation of which would be a crime, this bill would impose a state-mandated local program.
Existing constitutional provisions require that a statute that limits the right of access to the meetings of public bodies or the writings of public officials and agencies be adopted with findings demonstrating the interest protected by the limitation and the need for protecting that interest.
This bill would make legislative findings to that effect.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law vests the Public Utilities Commission with jurisdiction over public utilities, including electrical corporations. Existing law establishes the policy of the state that eligible renewable energy resources and zero-carbon resources supply 90% of all retail sales of electricity to California end-use customers by December 31, 2035, 95% of all retail sales of electricity to California end-use customers by December 31, 2040, 100% of all retail sales of electricity to California end-use customers by December 31, 2045, and 100% of electricity procured to serve all state agencies by December 31, 2035. Under existing law, a violation of the Public Utilities Act is a crime.
This bill would require transmission utilities, as defined, on or before January 1, 2026, to jointly prepare a grid-enhancing technologies strategic plan that is designed to, among other things, cost-effectively increase transmission capacity and increase capacity to connect new renewable energy and zero-carbon resources. The bill would require each transmission utility, on or before January 1, 2026, and at least every 4 years thereafter, to complete an evaluation of which of its transmission and distribution lines can be reconductored with advanced conductors in a cost-effective manner to, among other things, increase transmission or distribution capacity and increase capacity to connect new renewable energy and zero-carbon resources. The bill would, upon completion of the plan and the evaluation, require the transmission utilities to submit the plan and evaluation to the commission and to make the plan and evaluation publicly available. The bill would require the plan and evaluation to include a timeline for implementation, as specified. The bill would require each transmission utility to report the progress in implementing the plan in its integrated resource plan.
Because the above-described requirements would be a part of the act, a violation of which would be a crime, this bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law vests the Public Utilities Commission with jurisdiction over public utilities, including electrical corporations. Existing law establishes the policy of the state that eligible renewable energy resources and zero-carbon resources supply 90% of all retail sales of electricity to California end-use customers by December 31, 2035, 95% of all retail sales of electricity to California end-use customers by December 31, 2040, 100% of all retail sales of electricity to California end-use customers by December 31, 2045, and 100% of electricity procured to serve all state agencies by December 31, 2035. Under existing law, a violation of the Public Utilities Act is a crime.
This bill would require transmission utilities, as defined, on or before January 1, 2026, to jointly prepare a grid-enhancing technologies strategic plan that is designed to to, among other things, cost-effectively increase transmission capacity and increase capacity to connect new renewable energy and zero-carbon resources, among other things. resources. The bill would require each transmission utility, on or before January 1, 2026, and at least every 4 years thereafter, to complete an evaluation of which of its transmission and distribution lines can be reconductored with advanced conductors in a cost-effective manner to, among other things, increase transmission or distribution capacity and increase capacity to connect new renewable energy and zero-carbon resources. The bill would, upon completion of the plan and the evaluation, require the transmission utilities to submit the plan and evaluation to the commission and to make the plan and evaluation publicly available. The bill would authorize the commission to redact portions of the plan and evaluation if the redaction is necessary to protect system security. The bill would require the plan and evaluation to include a timeline for implementation, as specified. The bill would require each transmission utility to report the progress in implementing the plan in its integrated resource plan.
Because the above-described requirements would be a part of the act, a violation of which would be a crime, this bill would impose a state-mandated local program.
Existing constitutional provisions require that a statute that limits the right of access to the meetings of public bodies or the writings of public officials and agencies be adopted with findings demonstrating the interest protected by the limitation and the need for protecting that interest.This bill would make legislative findings to that effect.The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law vests the Public Utilities Commission with jurisdiction over public utilities, including electrical corporations. Existing law establishes the policy of the state that eligible renewable energy resources and zero-carbon resources supply 90% of all retail sales of electricity to California end-use customers by December 31, 2035, 95% of all retail sales of electricity to California end-use customers by December 31, 2040, 100% of all retail sales of electricity to California end-use customers by December 31, 2045, and 100% of electricity procured to serve all state agencies by December 31, 2035. Under existing law, a violation of an order, decision, rule, direction, demand, or requirement of the commission the Public Utilities Act is a crime.
This bill would require the commission to ensure that the state is on track to deliver specified transmission capacities by certain dates. To the extent that the commission would issue an order, decision, rule, direction, demand, or requirement to implement this requirement, a violation of which would be a crime, this bill would impose a state-mandated local program. The bill would require the commission to annually submit a report to the Legislature that describes the progress made towards achieving those transmission capacity goals, identifies challenges to achieving those goals, and makes recommendations on legislation necessary to overcome those challenges.This bill would require the commission, on or before November 1, 2026, to conduct a study on the cost savings and efficiencies that may result from using reconductoring and other grid enhancing technologies to improve grid reliability. The bill would require the commission to post the results of the study on its internet website and to submit to the Legislature a report on the results of the study.This bill would require transmission utilities, as defined, on or before January 1, 2026, to jointly prepare a grid-enhancing technologies strategic plan that is designed to cost-effectively increase transmission capacity and increase capacity to connect new renewable energy and zero-carbon resources, among other things. The bill would require each transmission utility, on or before January 1, 2026, and at least every 4 years thereafter, to complete an evaluation of which of its transmission and distribution lines can be reconductored with advanced conductors in a cost-effective manner to, among other things, increase transmission or distribution capacity and increase capacity to connect new renewable energy and zero-carbon resources. The bill would, upon completion of the plan and the evaluation, require the transmission utilities to submit the plan and evaluation to the commission and to make the plan and evaluation publicly available. The bill would authorize the commission to redact portions of the plan and evaluation if the redaction is necessary to protect system security. The bill would require the plan and evaluation to include a timeline for implementation, as specified. The bill would require each transmission utility to report the progress in implementing the plan in its integrated resource plan.
Because the above-described requirements would be a part of the act, a violation of which would be a crime, this bill would impose a state-mandated local program.
Existing constitutional provisions require that a statute that limits the right of access to the meetings of public bodies or the writings of public officials and agencies be adopted with findings demonstrating the interest protected by the limitation and the need for protecting that interest.
This bill would make legislative findings to that effect.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law vests the Public Utilities Commission with jurisdiction over public utilities, including electrical corporations. Existing law establishes the policy of the state that eligible renewable energy resources and zero-carbon resources supply 90% of all retail sales of electricity to California end-use customers by December 31, 2035, 95% of all retail sales of electricity to California end-use customers by December 31, 2040, 100% of all retail sales of electricity to California end-use customers by December 31, 2045, and 100% of electricity procured to serve all state agencies by December 31, 2035. Under existing law, a violation of an order, decision, rule, direction, demand, or requirement of the commission is a crime.
This bill would require the commission to ensure that the state is on track to deliver specified transmission capacities by certain dates. To the extent that the commission would issue an order, decision, rule, direction, demand, or requirement to implement this requirement, a violation of which would be a crime, this bill would impose a state-mandated local program. The bill would require the commission to annually submit a report to the Legislature that describes the progress made towards achieving those transmission capacity goals, identifies challenges to achieving those goals, and makes recommendations on legislation necessary to overcome those challenges.
This bill would require the commission, on or before November 1, 2026, to conduct a study on the cost savings and efficiencies that may result from using reconductoring and other grid enhancing technologies to improve grid reliability. The bill would require the commission to post the results of the study on its internet website and to submit to the Legislature a report on the results of the study.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
(a)The Legislature finds and declares all of the following:
(1)California must dramatically increase the capacity of its electrical transmission and distribution systems to meet the goals of Section 454.53 and to decarbonize its economy.
(2)The increase in transmission and distribution capacity must be done rapidly and cost effectively.
(3)California transmission utilities and the Independent System Operator can jointly explore opportunities to advance technologies that may quickly and cost effectively increase transmission capacity.
(4)Reconductoring existing transmission lines with advanced conductors and installing grid-enhancing technologies, such as advanced power flow control systems, dynamic line rating systems, and topology optimization software, can quickly and cost effectively increase transmission capacity.
(5)The benefits of these technologies include lower electricity rates, less wildfire risk, increased reliability, less transmission line congestion, less curtailment of renewable generation resources, and increased capacity to interconnect new renewable generation, storage, and other zero-carbon resources.
(6)Grid-enhancing technologies may expand and accelerate transmission capacity at a lower cost as compared to traditional transmission technologies.
(7)Reconductoring existing transmission lines with advanced conductors in existing rights-of-way can be accomplished at a fraction of the cost of building new transmission lines and are therefore often quite cost effective.
(8)Grid-enhancing technologies can be deployed within months and reconductoring with advanced conductors can be accomplished within one or two years. Other types of transmission capacity increases can take many years.
(9)The current transmission planning process assesses the value of transmission investments based strictly on the needs of a single assumed planning scenario of specific resources and geographies over a 10-year planning horizon, and does not appropriately incorporate the value that increased transmission capacity can provide in reducing risks surrounding major technology and permitting uncertainties, expanding optionality for load-serving entities, and delivering benefits over a longer time horizon.
(b)For purposes of this section, the following definitions apply:
(1)Grid-enhancing technologies means hardware and software that increases the capacity of electrical lines and improves the efficiency, reliability, and safety of the grid. Grid-enhancing technologies include, but are not limited to, dynamic line rating systems, advanced power flow control systems, and topology optimization software.
(2)Reconductored with advanced conductors means replacing the existing electric conductor with a conductor that has a direct current electrical resistance at least 10 percent lower than existing conductors of a similar diameter on the system and may include rebuilding support structures or other associated facilities.
(3)Transmission utility means an electrical corporation that is a participating transmission owner that has turned over operation of its transmission system to the Independent System Operator.
(c)(1)On or before January 1, 2026, and every two years thereafter, each transmission utility shall prepare a study of the feasibility of projects using grid-enhancing technologies to achieve one or more of the purposes listed in paragraph (2). The transmission utility shall provide information on feasibility, cost, rating, implementation time, and any other necessary information to the Independent System Operator at the same time as any other projects proposed to be part of the Independent System Operators annual transmission planning process. The transmission utility shall request the Independent System Operator to review the results of the study as part of its annual transmission planning process for economic, reliability, and policy goals, and shall request the Independent System Operator to include grid-enhancing technologies in all transmission planning studies and analyses.
(2)The study shall be designed to identify projects using grid-enhancing technologies that can achieve one or more of the following:
(A)Increase transmission capacity.
(B)Reduce transmission system congestion.
(C)Reduce curtailment of renewable and zero-carbon resources.
(D)Increase reliability.
(E)Reduce the risk of igniting wildfire, by means of investments that are consistent with the transmission utilitys approved wildfire mitigation plan.
(F)Increase capacity to connect new renewable energy and zero-carbon resources.
(G)Increase flexibility to reduce risks surrounding technology and permitting uncertainties in statewide electrical system planning and improve optionality for load-serving entities.
(d)(1)On or before January 1, 2026, and at least every four years thereafter, each transmission utility shall prepare a study of which of its transmission lines can be reconductored with advanced conductors to achieve one or more of the purposes listed in paragraph (2). The transmission utility shall provide information on feasibility, cost, rating, implementation time, and any other necessary information to the Independent System Operator at the same time as any other projects proposed to be part of the Independent System Operators annual transmission planning process. Each transmission utility shall request that the Independent System Operator review the results of the study as part of its annual transmission planning process for economic, reliability, and policy goals, and shall request the Independent System Operator to include reconductoring with advanced technologies in all transmission planning studies and analyses.
(2)The study shall identify electrical lines where reconductoring with advanced conductors can achieve one or more of the following:
(A)Significantly increase transmission capacity.
(B)Reduce transmission system congestion.
(C)Reduce curtailment of renewable and zero-carbon resources.
(D)Increase reliability.
(E)Reduce the risk of igniting wildfire, where the investment is consistent with the transmission utilitys approved wildfire mitigation plan.
(F)Increase capacity to connect new renewable energy and zero-carbon resources.
(G)Reduce line losses.
(H)Increase the ability to quickly energize new customers or serve increased customer load.
(I)Increase flexibility to reduce risks surrounding technology and permitting uncertainties and improve optionality.
(e)(1)Upon submitting the study to the Independent System Operator pursuant to subdivision (c) or (d) and except as provided in paragraph (2), each transmission utility shall make the study publicly available.
(2)Information in the study that is determined by the Independent System Operator, in consultation with the transmission utilities, to be necessary to protect the security of the electrical transmission system shall be withheld from public disclosure.
(f)Each electrical corporation operating a distribution system shall consider grid-enhancing technologies and reconductoring with advanced conductors as part of its annual distribution planning process.
(g)This section does not affect the right of a transmission utility to implement self-approved projects.
(h)This section does not affect any project previously approved by the Independent System Operator.
SEC. 2.The Legislature finds and declares that Section 1 of this act, which adds Section 454.58 of the Public Utilities Code, imposes a limitation on the publics right of access to the meetings of public bodies or the writings of public officials and agencies within the meaning of Section 3 of Article I of the California Constitution. Pursuant to that constitutional provision, the Legislature makes the following findings to demonstrate the interest protected by this limitation and the need for protecting that interest:
To protect information determined to be necessary to protect the security of the electrical transmission system, it is necessary that this act limit the publics right to access that information.
SEC. 3.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
(a)The Legislature finds and declares all of the following:
(1)California must dramatically increase the capacity of its electrical transmission and distribution systems to meet the goals of Section 454.53 and to decarbonize its economy.
(2)The increase in transmission and distribution capacity must be done rapidly and cost effectively.
(3)California transmission utilities and the Independent System Operator can jointly explore opportunities to advance technologies that may quickly and cost effectively increase transmission capacity.
(4)Reconductoring existing transmission lines with advanced conductors and installing grid-enhancing technologies, such as advanced power flow control systems, dynamic line rating systems, and topology optimization software, can quickly and cost effectively increase transmission capacity.
(5)The benefits of these technologies include lower electricity rates, less wildfire risk, increased reliability, less transmission line congestion, less curtailment of renewable generation resources, and increased capacity to interconnect new renewable generation, storage, and other zero-carbon resources.
(6)Grid-enhancing technologies may expand and accelerate transmission capacity at a lower cost as compared to traditional transmission technologies.
(7)Reconductoring existing transmission lines with advanced conductors in existing rights-of-way can be accomplished at a fraction of the cost of building new transmission lines and are therefore often quite cost effective.
(8)Grid-enhancing technologies can be deployed within months and reconductoring with advanced conductors can be accomplished within one or two years. Other types of transmission capacity increases can take many years.
(9)The current transmission planning process assesses the value of transmission investments based strictly on the needs of a single assumed planning scenario of specific resources and geographies over a 10-year planning horizon, and does not appropriately incorporate the value that increased transmission capacity can provide in reducing risks surrounding major technology and permitting uncertainties, expanding optionality for load-serving entities, and delivering benefits over a longer time horizon.
(b)For purposes of this section, the following definitions apply:
(1)Grid-enhancing technologies means hardware and software that increases the capacity of electrical lines and improves the efficiency, reliability, and safety of the grid. Grid-enhancing technologies include, but are not limited to, dynamic line rating systems, advanced power flow control systems, and topology optimization software.
(2)Reconductored with advanced conductors means replacing the existing electric conductor with a conductor that has a direct current electrical resistance at least 10 percent lower than existing conductors of a similar diameter on the system and may include rebuilding support structures or other associated facilities.
(3)Transmission utility means an electrical corporation that is a participating transmission owner that has turned over operation of its transmission system to the Independent System Operator.
(c)(1)On or before January 1, 2026, and every two years thereafter, each transmission utility shall prepare a study of the feasibility of projects using grid-enhancing technologies to achieve one or more of the purposes listed in paragraph (2). The transmission utility shall provide information on feasibility, cost, rating, implementation time, and any other necessary information to the Independent System Operator at the same time as any other projects proposed to be part of the Independent System Operators annual transmission planning process. The transmission utility shall request the Independent System Operator to review the results of the study as part of its annual transmission planning process for economic, reliability, and policy goals, and shall request the Independent System Operator to include grid-enhancing technologies in all transmission planning studies and analyses.
(2)The study shall be designed to identify projects using grid-enhancing technologies that can achieve one or more of the following:
(A)Increase transmission capacity.
(B)Reduce transmission system congestion.
(C)Reduce curtailment of renewable and zero-carbon resources.
(D)Increase reliability.
(E)Reduce the risk of igniting wildfire, by means of investments that are consistent with the transmission utilitys approved wildfire mitigation plan.
(F)Increase capacity to connect new renewable energy and zero-carbon resources.
(G)Increase flexibility to reduce risks surrounding technology and permitting uncertainties in statewide electrical system planning and improve optionality for load-serving entities.
(d)(1)On or before January 1, 2026, and at least every four years thereafter, each transmission utility shall prepare a study of which of its transmission lines can be reconductored with advanced conductors to achieve one or more of the purposes listed in paragraph (2). The transmission utility shall provide information on feasibility, cost, rating, implementation time, and any other necessary information to the Independent System Operator at the same time as any other projects proposed to be part of the Independent System Operators annual transmission planning process. Each transmission utility shall request that the Independent System Operator review the results of the study as part of its annual transmission planning process for economic, reliability, and policy goals, and shall request the Independent System Operator to include reconductoring with advanced technologies in all transmission planning studies and analyses.
(2)The study shall identify electrical lines where reconductoring with advanced conductors can achieve one or more of the following:
(A)Significantly increase transmission capacity.
(B)Reduce transmission system congestion.
(C)Reduce curtailment of renewable and zero-carbon resources.
(D)Increase reliability.
(E)Reduce the risk of igniting wildfire, where the investment is consistent with the transmission utilitys approved wildfire mitigation plan.
(F)Increase capacity to connect new renewable energy and zero-carbon resources.
(G)Reduce line losses.
(H)Increase the ability to quickly energize new customers or serve increased customer load.
(I)Increase flexibility to reduce risks surrounding technology and permitting uncertainties and improve optionality.
(e)(1)Upon submitting the study to the Independent System Operator pursuant to subdivision (c) or (d) and except as provided in paragraph (2), each transmission utility shall make the study publicly available.
(2)Information in the study that is determined by the Independent System Operator, in consultation with the transmission utilities, to be necessary to protect the security of the electrical transmission system shall be withheld from public disclosure.
(f)Each electrical corporation operating a distribution system shall consider grid-enhancing technologies and reconductoring with advanced conductors as part of its annual distribution planning process.
(g)This section does not affect the right of a transmission utility to implement self-approved projects.
(h)This section does not affect any project previously approved by the Independent System Operator.
SEC. 2.The Legislature finds and declares that Section 1 of this act, which adds Section 454.58 of the Public Utilities Code, imposes a limitation on the publics right of access to the meetings of public bodies or the writings of public officials and agencies within the meaning of Section 3 of Article I of the California Constitution. Pursuant to that constitutional provision, the Legislature makes the following findings to demonstrate the interest protected by this limitation and the need for protecting that interest:
To protect information determined to be necessary to protect the security of the electrical transmission system, it is necessary that this act limit the publics right to access that information.
SEC. 3.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
(a)The Legislature finds and declares all of the following:
(1)California must dramatically increase the capacity of its electrical transmission and distribution systems to meet the goals of Section 454.53 and to decarbonize its economy.
(2)The increase in transmission and distribution capacity must be done rapidly and cost effectively.
(3)California transmission utilities and the Independent System Operator can jointly explore opportunities to advance technologies that may quickly and cost effectively increase transmission capacity.
(4)Reconductoring existing transmission lines with advanced conductors and installing grid-enhancing technologies, such as advanced power flow control systems, dynamic line rating systems, and topology optimization software, can quickly and cost effectively increase transmission capacity.
(5)The benefits of these technologies include lower electricity rates, less wildfire risk, increased reliability, less transmission line congestion, less curtailment of renewable generation resources, and increased capacity to interconnect new renewable generation, storage, and other zero-carbon resources.
(6)Grid-enhancing technologies may expand and accelerate transmission capacity at a lower cost as compared to traditional transmission technologies.
(7)Reconductoring existing transmission lines with advanced conductors in existing rights-of-way can be accomplished at a fraction of the cost of building new transmission lines and are therefore often quite cost effective.
(8)Grid-enhancing technologies can be deployed within months and reconductoring with advanced conductors can be accomplished within one or two years. Other types of transmission capacity increases can take many years.
(9)The current transmission planning process assesses the value of transmission investments based strictly on the needs of a single assumed planning scenario of specific resources and geographies over a 10-year planning horizon, and does not appropriately incorporate the value that increased transmission capacity can provide in reducing risks surrounding major technology and permitting uncertainties, expanding optionality for load-serving entities, and delivering benefits over a longer time horizon.
(b)For purposes of this section, the following definitions apply:
(1)Grid-enhancing technologies means hardware and software that increases the capacity of electrical lines and improves the efficiency, reliability, and safety of the grid. Grid-enhancing technologies include, but are not limited to, dynamic line rating systems, advanced power flow control systems, and topology optimization software.
(2)Reconductored with advanced conductors means replacing the existing electric conductor with a conductor that has a direct current electrical resistance at least 10 percent lower than existing conductors of a similar diameter on the system and may include rebuilding support structures or other associated facilities.
(3)Transmission utility means an electrical corporation that is a participating transmission owner that has turned over operation of its transmission system to the Independent System Operator.
(c)(1)On or before January 1, 2026, and every two years thereafter, each transmission utility shall prepare a study of the feasibility of projects using grid-enhancing technologies to achieve one or more of the purposes listed in paragraph (2). The transmission utility shall provide information on feasibility, cost, rating, implementation time, and any other necessary information to the Independent System Operator at the same time as any other projects proposed to be part of the Independent System Operators annual transmission planning process. The transmission utility shall request the Independent System Operator to review the results of the study as part of its annual transmission planning process for economic, reliability, and policy goals, and shall request the Independent System Operator to include grid-enhancing technologies in all transmission planning studies and analyses.
(2)The study shall be designed to identify projects using grid-enhancing technologies that can achieve one or more of the following:
(A)Increase transmission capacity.
(B)Reduce transmission system congestion.
(C)Reduce curtailment of renewable and zero-carbon resources.
(D)Increase reliability.
(E)Reduce the risk of igniting wildfire, by means of investments that are consistent with the transmission utilitys approved wildfire mitigation plan.
(F)Increase capacity to connect new renewable energy and zero-carbon resources.
(G)Increase flexibility to reduce risks surrounding technology and permitting uncertainties in statewide electrical system planning and improve optionality for load-serving entities.
(d)(1)On or before January 1, 2026, and at least every four years thereafter, each transmission utility shall prepare a study of which of its transmission lines can be reconductored with advanced conductors to achieve one or more of the purposes listed in paragraph (2). The transmission utility shall provide information on feasibility, cost, rating, implementation time, and any other necessary information to the Independent System Operator at the same time as any other projects proposed to be part of the Independent System Operators annual transmission planning process. Each transmission utility shall request that the Independent System Operator review the results of the study as part of its annual transmission planning process for economic, reliability, and policy goals, and shall request the Independent System Operator to include reconductoring with advanced technologies in all transmission planning studies and analyses.
(2)The study shall identify electrical lines where reconductoring with advanced conductors can achieve one or more of the following:
(A)Significantly increase transmission capacity.
(B)Reduce transmission system congestion.
(C)Reduce curtailment of renewable and zero-carbon resources.
(D)Increase reliability.
(E)Reduce the risk of igniting wildfire, where the investment is consistent with the transmission utilitys approved wildfire mitigation plan.
(F)Increase capacity to connect new renewable energy and zero-carbon resources.
(G)Reduce line losses.
(H)Increase the ability to quickly energize new customers or serve increased customer load.
(I)Increase flexibility to reduce risks surrounding technology and permitting uncertainties and improve optionality.
(e)(1)Upon submitting the study to the Independent System Operator pursuant to subdivision (c) or (d) and except as provided in paragraph (2), each transmission utility shall make the study publicly available.
(2)Information in the study that is determined by the Independent System Operator Operator, in consultation with the transmission utilities, to be necessary to protect the security of the electrical transmission system shall be withheld from public disclosure.
(f)Each electrical corporation operating a distribution system shall consider grid-enhancing technologies and reconductoring with advanced conductors as part of its annual distribution planning process.
(g)This section does not affect the right of a transmission utility to implement self-approved projects.
(h)This section does not affect any project previously approved by the Independent System Operator.
SEC. 2.The Legislature finds and declares that Section 1 of this act, which adds Section 454.58 of the Public Utilities Code, imposes a limitation on the publics right of access to the meetings of public bodies or the writings of public officials and agencies within the meaning of Section 3 of Article I of the California Constitution. Pursuant to that constitutional provision, the Legislature makes the following findings to demonstrate the interest protected by this limitation and the need for protecting that interest:
To protect information determined to be necessary to protect the security of the electrical transmission system, it is necessary that this act limit the publics right to access that information.
SEC. 3.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
(a)The Legislature finds and declares all of the following:
(1)California must dramatically increase the capacity of its electrical transmission and distribution systems to meet the goals of Section 454.53 and to decarbonize its economy.
(2)The increase in transmission and distribution capacity must be done rapidly and cost-effectively. cost effectively.
(3)California transmission utilities and the Independent System Operator may not be fully using available technology that can jointly explore opportunities to advance technologies that may quickly and cost-effectively cost effectively increase transmission capacity.
(4)Reconductoring existing transmission lines with advanced conductors and installing grid-enhancing technologies, such as advanced power flow control systems, dynamic line rating systems, and topology optimization software, can quickly and cost-effectively cost effectively increase transmission capacity.
(5)The benefits of these technologies include lower electricity rates, less wildfire risk, increased reliability, less transmission line congestion, less curtailment of renewable generation resources, and increased capacity to interconnect new renewable generation, storage, and other zero-carbon resources.
(6)Grid-enhancing technologies are usually very low cost hardware and software items that can pay for themselves very quickly. may expand and accelerate transmission capacity at a lower cost as compared to traditional transmission technologies.
(7)Reconductoring existing transmission lines with advanced conductors in existing rights-of-way can be accomplished at a fraction of the cost of building new transmission lines and are therefore often quite cost effective.
(8)Grid-enhancing technologies can be deployed within months and reconductoring with advanced conductors can be accomplished within one or two years. Other types of transmission capacity increases can take many years.
(9)The current transmission planning process assesses the value of transmission investments based strictly on the needs of a single assumed planning scenario of specific resources and geographies over a 10-year planning horizon, and does not appropriately incorporate the value that increased transmission capacity can provide in reducing risks surrounding major technology and permitting uncertainties, expanding optionality for load-serving entities, and delivering benefits over a longer time horizon.
(b)For purposes of this section, the following definitions apply:
(1)Cost effective means the financial benefits outweigh the cost borne by customers of a project under consideration, as evaluated under multiple potential future planning scenarios.(2)(1)Grid-enhancing technologies means hardware and software that dynamically increases the capacity of electrical lines and improves the efficiency, reliability, and safety of the grid. Grid-enhancing technologies include, but are not limited to, dynamic line rating systems, advanced power flow control systems, and topology optimization software.
(3)(2)Reconductored with advanced conductors means replacing the existing electric conductor with a conductor that has a direct current electrical resistance at least 10 percent lower than existing conductors of a similar diameter on the system and may include rebuilding support structures or other associated facilities.
(4)(3)Transmission utilities means electrical corporations that are participating transmission owners that have utility means an electrical corporation that is a participating owner that has turned over operation of their transmission systems its transmission system to the Independent System Operator.
(c)(1)On or before January 1, 2026, the transmission utilities shall jointly prepare a grid-enhancing technologies strategic plan. The transmission utilities shall request the Independent System Operator to participate in preparing the plan.(2)Upon completion of the plan, the transmission utilities shall submit the plan to the commission and make the plan publicly available.(3)The plan shall include a timeline for implementation. As part of each subsequent integrated resource plan filed by the transmission utilities pursuant to Section 454.52, each transmission utility shall report its progress in implementing the plan.(4)The plan shall be designed to achieve all of the following that are cost effective:(c)(1)On or before January 1, 2026, and every two years thereafter, each transmission utility shall prepare a study of the feasibility of projects using grid-enhancing technologies to achieve one or more of the purposes listed in paragraph (2). The transmission utility shall provide information on feasibility, cost, rating, implementation time, and any other necessary information to the Independent System Operator at the same time as any other projects proposed to be part of the Independent System Operators annual transmission planning process. The transmission utility shall request the Independent System Operator to review the results of the study as part of its annual transmission planning process for economic, reliability, and policy goals, and shall request the Independent System Operator to include grid-enhancing technologies in all transmission planning studies and analyses.
(2)The study shall be designed to identify projects using grid-enhancing technologies that can achieve one or more of the following:
(A)Increase transmission capacity.
(B)Reduce transmission system congestion.
(C)Reduce curtailment of renewable and zero-carbon resources.
(D)Increase reliability.
(E)Reduce the risk of igniting wildfire, by means of investments that are consistent with the transmission utilitys approved wildfire mitigation plan.
(F)Increase capacity to connect new renewable energy and zero-carbon resources.
(G)Increase flexibility to reduce risks surrounding technology and permitting uncertainties in statewide electrical system planning and improve optionality for load-serving entities.
(d)(1)Beginning January 1, 2026, and at least every four years thereafter, each transmission utility shall complete an evaluation of which of its transmission and distribution lines can be reconductored with advanced conductors in a cost-effective manner. Each transmission utility shall request that the Independent System Operator participate in evaluating the transmission lines.(2)The evaluation shall include a timeline for implementing distribution projects and self-approved transmission projects, and shall include a plan for proposing to the Independent System Operator projects for approval where that approval is required.(3)The evaluation shall identify electrical lines where reconductoring with advanced conductors can cost-effectively achieve one or more of the following:(d)(1)On or before January 1, 2026, and at least every four years thereafter, each transmission utility shall prepare a study of which of its transmission lines can be reconductored with advanced conductors to achieve one or more of the purposes listed in paragraph (2). The transmission utility shall provide information on feasibility, cost, rating, implementation time, and any other necessary information to the Independent System Operator at the same time as any other projects proposed to be part of the Independent System Operators annual transmission planning process. Each transmission utility shall request that the Independent System Operator review the results of the study as part of its annual transmission planning process for economic, reliability, and policy goals, and shall request the Independent System Operator to include reconductoring with advanced technologies in all transmission planning studies and analyses.
(2)The study shall identify electrical lines where reconductoring with advanced conductors can achieve one or more of the following:
(A)Increase Significantly increase transmission or distribution capacity.
(B)Reduce transmission or distribution system congestion.
(C)Reduce curtailment of renewable and zero-carbon resources.
(D)Increase reliability.
(E)Reduce the risk of igniting wildfire, where the investment is consistent with the transmission utilitys approved wildfire mitigation plan.
(F)Increase capacity to connect new renewable energy and zero-carbon resources.
(G)Reduce line losses.
(H)Increase the ability to quickly energize new customers or serve increased customer load.
(I)Increase flexibility to reduce risks surrounding technology and permitting uncertainties and improve optionality.
(4)Upon completion of the evaluation, each transmission utility shall submit the evaluation to the commission and make it publicly available.(e)The commission shall request the Independent System Operator to consider the results of the plan prepared pursuant to subdivision (c) and each evaluation prepared pursuant to subdivision (d) as part of its transmission planning process for economic, reliability, and policy analysis.(e)(1)Upon submitting the study to the Independent System Operator pursuant to subdivision (c) or (d) and except as provided in paragraph (2), each transmission utility shall make the study publicly available.
(2)Information in the study that is determined by the Independent System Operator to be necessary to protect the security of the electrical transmission system shall be withheld from public disclosure.
(f)Each electrical corporation operating a distribution system shall consider grid-enhancing technologies and reconductoring with advanced conductors as part of its annual distribution planning process.
(g)This section does not affect the right of a transmission utility to implement self-approved projects.
(h)This section does not affect any project previously approved by the Independent System Operator.
SEC. 2.The Legislature finds and declares that Section 1 of this act, which adds Section 454.58 of the Public Utilities Code, imposes a limitation on the publics right of access to the meetings of public bodies or the writings of public officials and agencies within the meaning of Section 3 of Article I of the California Constitution. Pursuant to that constitutional provision, the Legislature makes the following findings to demonstrate the interest protected by this limitation and the need for protecting that interest:
To protect information determined to be necessary to protect the security of the electrical transmission system, it is necessary that this act limit the publics right to access that information.
SEC. 2.SEC. 3.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
(a)The Legislature finds and declares all of the following:
(1)California must dramatically increase the capacity of its electrical transmission and distribution systems to meet the goals of Section 454.53 and to decarbonize its economy.
(2)The increase in transmission and distribution capacity must be done rapidly and cost-effectively.
(3)California transmission utilities and the Independent System Operator may not be fully using available technology that can quickly and cost-effectively increase transmission capacity.
(4)Reconductoring existing transmission lines with advanced conductors and installing grid-enhancing technologies, such as advanced power flow control systems, dynamic line rating systems, and topology optimization software, can quickly and cost-effectively increase transmission capacity.
(5)The benefits of these technologies include lower electricity rates, less wildfire risk, increased reliability, less transmission line congestion, less curtailment of renewable generation resources, and increased capacity to interconnect new renewable generation, storage, and other zero-carbon resources.
(6)Grid-enhancing technologies are usually very low cost hardware and software items that can pay for themselves very quickly.
(7)Reconductoring existing transmission lines with advanced conductors in existing rights-of-way can be accomplished at a fraction of the cost of building new transmission lines and are therefore often quite cost effective.
(8)Grid-enhancing technologies can be deployed within months and reconductoring with advanced conductors can be accomplished within one or two years. Other types of transmission capacity increases can take many years.
(9)The current transmission planning process assesses the value of transmission investments based strictly on the needs of a single assumed planning scenario of specific resources and geographies over a 10-year planning horizon, and does not appropriately incorporate the value that increased transmission capacity can provide in reducing risks surrounding major technology and permitting uncertainties, expanding optionality for load-serving entities, and delivering benefits over a longer time horizon.
(b)For purposes of this section, the following definitions apply:
(1)Cost effective means the financial benefits outweigh the cost borne by customers of a project under consideration, as evaluated under multiple potential future planning scenarios.
(1)(2)Grid-enhancing technologies means hardware and software that dynamically increases the capacity of electrical lines and improves the efficiency, reliability, and safety of the grid. Grid-enhancing technologies include, but are not limited to, dynamic line rating systems, advanced power flow control systems, and topology optimization software.
(2)(3)Reconductored with advanced conductors means replacing the existing electric conductor with a conductor that has a direct current electrical resistance at least 10 percent lower than existing conductors of a similar diameter on the system and may include rebuilding support structures or other associated facilities.
(3)(4)Transmission utilities means electrical corporations that are participating transmission owners that have turned over operation of their transmission systems to the Independent System Operator.
(c)(1)On or before January 1, 2026, the transmission utilities shall jointly prepare a grid-enhancing technologies strategic plan. The transmission utilities shall request the Independent System Operator to participate in preparing the plan.
(2)Upon completion of the plan, the transmission utilities shall submit the plan to the commission and make the plan publicly available.
(3)The plan shall include a timeline for implementation. As part of each subsequent integrated resource plan filed by the transmission utilities pursuant to Section 454.52, each transmission utility shall report its progress in implementing the plan.
(4)The plan shall be designed to achieve all of the following that are cost effective:
(A)Increase transmission capacity.
(B)Reduce transmission system congestion.
(C)Reduce curtailment of renewable and zero-carbon resources.
(D)Increase reliability.
(E)Reduce the risk of igniting wildfire, by means of investments that are consistent with the transmission utilitys approved wildfire mitigation plan.
(F)Increase capacity to connect new renewable energy and zero-carbon resources.
(G)Increase flexibility to reduce risks surrounding technology and permitting uncertainties in statewide electrical system planning and improve optionality for load-serving entities.
(d)(1)Beginning January 1, 2026, and at least every four years thereafter, each transmission utility shall complete an evaluation of which of its transmission and distribution lines can be reconductored with advanced conductors in a cost-effective manner. Each transmission utility shall request that the Independent System Operator participate in evaluating the transmission lines.
(2)The evaluation shall include a timeline for implementing distribution projects and self-approved transmission projects, and shall include a plan for proposing to the Independent System Operator projects for approval where that approval is required.
(3)The evaluation shall identify electrical lines where reconductoring with advanced conductors can cost-effectively achieve one or more of the following:
(A)Increase transmission or distribution capacity.
(B)Reduce transmission or distribution system congestion.
(C)Reduce curtailment of renewable and zero-carbon resources.
(D)Increase reliability.
(E)Reduce the risk of igniting wildfire, where the investment is consistent with the transmission utilitys approved wildfire mitigation plan.
(F)Increase capacity to connect new renewable energy and zero-carbon resources.
(G)Reduce line losses.
(H)Increase the ability to quickly energize new customers or serve increased customer load.
(I)Increase flexibility to reduce risks surrounding technology and permitting uncertainties and improve optionality.
(4)Upon completion of the evaluation, each transmission utility shall submit the evaluation to the commission and make it publicly available.
(e)The commission shall request the Independent System Operator to consider the results of the plan prepared pursuant to subdivision (c) and each evaluation prepared pursuant to subdivision (d) as part of its transmission planning process for economic, reliability, and policy analysis.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
(a)The Legislature finds and declares all of the following:
(1)California must dramatically increase the capacity of its electrical transmission and distribution systems to meet the goals of Section 454.53 and to decarbonize its economy.
(2)The increase in transmission and distribution capacity must be done rapidly and cost-effectively.
(3)California transmission utilities and the Independent System Operator are not may not be fully using available technology that can quickly and cost-effectively increase transmission capacity.
(4)Reconductoring existing transmission lines with advanced conductors and installing grid-enhancing technologies, such as advanced power flow control systems, dynamic line rating systems, and topology optimization software, can quickly and cost-effectively increase transmission capacity.
(5)The benefits of these technologies include lower electricity rates, less wildfire risk, increased reliability, less transmission line congestion, less curtailment of renewable generation resources, and increased capacity to interconnect new renewable generation, storage, and other zero-carbon resources.
(6)Grid-enhancing technologies are usually very low cost hardware and software items that can pay for themselves very quickly.
(7)Reconductoring existing transmission lines with advanced conductors in existing rights-of-way can be accomplished at a fraction of the cost of building new transmission lines and are therefore often quite cost-effective. cost effective.
(8)Grid-enhancing technologies can be deployed within months and reconductoring with advanced conductors can be accomplished within one or two years. Other types of transmission capacity increases can take many years.
(b)For purposes of this section, the following definitions apply:
(1)Grid-enhancing technologies means hardware and software that dynamically increases the capacity of electrical lines and improves the efficiency, reliability, and safety of the grid. Grid-enhancing technologies include, but are not limited to, dynamic line rating systems, advanced power flow control systems, and topology optimization software.
(2)Reconductored with advanced conductors means replacing the existing electric conductor with a conductor that has a direct current electrical resistance at least 10 percent lower than existing conductors of a similar diameter on the system and may include rebuilding support structures or other associated facilities.
(3)Transmission utilities means electrical corporations that are participating transmission owners that have turned over operation of their transmission systems to the Independent System Operator.
(c)(1)On or before January 1, 2026, the transmission utilities shall jointly prepare a grid-enhancing technologies strategic plan. The transmission utilities shall request the Independent System Operator to participate in preparing the plan.
(2)Upon completion of the plan, the transmission utilities shall submit the plan to the commission and make the plan publicly available. The commission may authorize portions of the plan to be redacted if necessary to protect system security.
(3)The plan shall include a timeline for implementation. As part of each subsequent integrated resource plan filed by the transmission utilities pursuant to Section 454.52, each transmission utility shall report its progress in implementing the plan.
(4)The plan shall be designed to achieve all of the following that are cost-effective: cost effective:
(A)Increase transmission capacity.
(B)Reduce transmission system congestion.
(C)Reduce curtailment of renewable and zero-carbon resources.
(D)Increase reliability.
(E)Reduce the risk of igniting wildfire. wildfire, by means of investments that are consistent with the transmission utilitys approved wildfire mitigation plan.
(F)Increase capacity to connect new renewable energy and zero-carbon resources.
(d)(1)Beginning January 1, 2026, and at least every four years thereafter, each transmission utility shall complete an evaluation of which of its transmission and distribution lines can be reconductored with advanced conductors in a cost-effective manner. Each transmission utility shall request that the Independent System Operator participate in evaluating the transmission lines.
(2)The evaluation shall include a timeline for implementing distribution projects and self-approved transmission projects, and shall include a plan for proposing to the Independent System Operator projects for approval where that approval is required.
(3)The evaluation shall identify electrical lines where reconductoring with advanced conductors can cost-effectively achieve one or more of the following:
(A)Increase transmission or distribution capacity.
(B)Reduce transmission or distribution system congestion.
(C)Reduce curtailment of renewable and zero-carbon resources.
(D)Increase reliability.
(E)Reduce the risk of igniting wildfire. wildfire, where the investment is consistent with the transmission utilitys approved wildfire mitigation plan.
(F)Increase capacity to connect new renewable energy and zero-carbon resources.
(G)Reduce line losses.
(H)Increase the ability to quickly energize new customers or serve increased customer load.
(4)Upon completion of the evaluation, each transmission utility shall submit the evaluation to the commission and make it publicly available. The commission may authorize portions of the evaluation to be redacted if necessary to protect system security.
(e)The commission shall request the Independent System Operator to consider the results of the plan prepared pursuant to subdivision (c) and each evaluation prepared pursuant to subdivision (d) as part of its transmission planning process for economic, reliability, and policy analysis.
SEC. 2.The Legislature finds and declares that Section 1 of this act, which adds Section 454.58 of the Public Utilities Code, imposes a limitation on the publics right of access to the meetings of public bodies or the writings of public officials and agencies within the meaning of Section 3 of Article I of the California Constitution. Pursuant to that constitutional provision, the Legislature makes the following findings to demonstrate the interest protected by this limitation and the need for protecting that interest:To ensure system security of the electrical transmission and distribution systems, it is in the interest of the state to prevent the public disclosure of information that may compromise the system security of those systems.SEC. 3.SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
(a)The Legislature finds and declares all of the following:
(1)California must dramatically increase the capacity of its electrical transmission and distribution systems to meet the goals of Section 454.53 and to decarbonize its economy.
(2)The increase in transmission and distribution capacity must be done rapidly and cost-effectively.
(3)California transmission utilities and the Independent System Operator are not fully using available technology that can quickly and cost-effectively increase transmission capacity.
(4)Reconductoring existing transmission lines with advanced conductors and installing grid-enhancing technologies, such as advanced power flow control systems, dynamic line rating systems, and topology optimization software, can quickly and cost-effectively increase transmission capacity.
(5)The benefits of these technologies include lower electricity rates, less wildfire risk, increased reliability, less transmission line congestion, less curtailment of renewable generation resources, and increased capacity to interconnect new renewable generation, storage, and other zero-carbon resources.
(6)Grid-enhancing technologies are usually very low cost hardware and software items that pay for themselves very quickly.
(7)Reconductoring existing transmission lines with advanced conductors in existing rights-of-way can be accomplished at a fraction of the cost of building new transmission lines and are therefore often quite cost-effective.
(8)Grid-enhancing technologies can be deployed within months and reconductoring with advanced conductors can be accomplished within one or two years. Other types of transmission capacity increases can take many years.
(b)For purposes of this section, the following definitions apply:
(1)Grid-enhancing technologies means hardware and software that dynamically increases the capacity of electrical lines and improves the efficiency, reliability, and safety of the grid. Grid-enhancing technologies include, but are not limited to, dynamic line rating systems, advanced power flow control systems, and topology optimization software.
(2)Reconductored with advanced conductors means replacing the existing electric conductor with a conductor that has a direct current electrical resistance at least 10 percent lower than existing conductors of a similar diameter on the system and may include rebuilding support structures or other associated facilities.
(3)Transmission utilities means electrical corporations that are participating transmission owners that have turned over operation of their transmission systems to the Independent System Operator.
(c)(1)On or before January 1, 2026, the transmission utilities shall jointly prepare a grid-enhancing technologies strategic plan. The transmission utilities shall request the Independent System Operator to participate in preparing the plan.
(2)Upon completion of the plan, the transmission utilities shall submit the plan to the commission and make the plan publicly available. The commission may authorize portions of the plan to be redacted if necessary to protect system security.
(3)The plan shall include a timeline for implementation. As part of each subsequent integrated resource plan filed by the transmission utilities pursuant to Section 454.52, each transmission utility shall report its progress in implementing the plan.
(4)The plan shall be designed to achieve all of the following that are cost-effective:
(A)Increase transmission capacity.
(B)Reduce transmission system congestion.
(C)Reduce curtailment of renewable and zero-carbon resources.
(D)Increase reliability.
(E)Reduce the risk of igniting wildfire.
(F)Increase capacity to connect new renewable energy and zero-carbon resources.
(d)(1)Beginning January 1, 2026, and at least every four years thereafter, each transmission utility shall complete an evaluation of which of its transmission and distribution lines can be reconductored with advanced conductors in a cost-effective manner. Each transmission utility shall request that the Independent System Operator participate in evaluating the transmission lines.
(2)The evaluation shall include a timeline for implementing distribution projects and self-approved transmission projects, and shall include a plan for proposing to the Independent System Operator projects for approval where that approval is required.
(3)The evaluation shall identify electrical lines where reconductoring with advanced conductors can cost-effectively achieve one or more of the following:
(A)Increase transmission or distribution capacity.
(B)Reduce transmission or distribution system congestion.
(C)Reduce curtailment of renewable and zero-carbon resources.
(D)Increase reliability.
(E)Reduce the risk of igniting wildfire.
(F)Increase capacity to connect new renewable energy and zero-carbon resources.
(G)Reduce line losses.
(H)Increase the ability to quickly energize new customers or serve increased customer load.
(4)Upon completion of the evaluation, each transmission utility shall submit the evaluation to the commission and make it publicly available. The commission may authorize portions of the evaluation to be redacted if necessary to protect system security.
(e)The commission shall request the Independent System Operator to consider the results of the plan prepared pursuant to subdivision (c) and each evaluation prepared pursuant to subdivision (d) as part of its transmission planning process for economic, reliability, and policy analysis.
SEC. 2.The Legislature finds and declares that Section 1 of this act, which adds Section 454.58 of the Public Utilities Code, imposes a limitation on the publics right of access to the meetings of public bodies or the writings of public officials and agencies within the meaning of Section 3 of Article I of the California Constitution. Pursuant to that constitutional provision, the Legislature makes the following findings to demonstrate the interest protected by this limitation and the need for protecting that interest:
To ensure system security of the electrical transmission and distribution systems, it is in the interest of the state to prevent the public disclosure of information that may compromise the system security of those systems.
SEC. 3.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
SECTION 1.Section 454.58 is added to the Public Utilities Code, to read:454.58.Consistent with the Independent System Operators transmission planning process, the commission shall ensure that the state is on track to deliver 85 gigawatts of transmission capacity by December 31, 2035, 125 gigawatts of transmission capacity by December 31, 2040, and 165 gigawatts of transmission capacity by December 31, 2045.SEC. 2.Section 913.7 is added to the Public Utilities Code, to read:913.7.Notwithstanding Section 10231.5 of the Government Code, the commission shall annually submit a report to the Legislature that describes the progress made towards achieving the goals specified in Section 454.58, identifies any challenges to achieving those goals, and makes recommendations on legislation that may be necessary to overcome those challenges.SEC. 3.Section 913.16 is added to the Public Utilities Code, to read:913.16.(a)On or before November 1, 2026, the commission shall conduct a study on the cost savings and efficiencies that may result from using reconductoring and other grid enhancing technologies to improve grid reliability.(b)The commission shall post the results of the study on its internet website.(c)(1)The commission shall submit to the Legislature a report on the results of the study.(2)Pursuant to Section 10231.5 of the Government Code, this section is repealed on January 1, 2031.SEC. 4.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.Consistent with the Independent System Operators transmission planning process, the commission shall ensure that the state is on track to deliver 85 gigawatts of transmission capacity by December 31, 2035, 125 gigawatts of transmission capacity by December 31, 2040, and 165 gigawatts of transmission capacity by December 31, 2045.
SEC. 2.Section 913.7 is added to the Public Utilities Code, to read:913.7.Notwithstanding Section 10231.5 of the Government Code, the commission shall annually submit a report to the Legislature that describes the progress made towards achieving the goals specified in Section 454.58, identifies any challenges to achieving those goals, and makes recommendations on legislation that may be necessary to overcome those challenges.
SEC. 3.Section 913.16 is added to the Public Utilities Code, to read:913.16.(a)On or before November 1, 2026, the commission shall conduct a study on the cost savings and efficiencies that may result from using reconductoring and other grid enhancing technologies to improve grid reliability.
(b)The commission shall post the results of the study on its internet website.
(c)(1)The commission shall submit to the Legislature a report on the results of the study.
(2)Pursuant to Section 10231.5 of the Government Code, this section is repealed on January 1, 2031.
SEC. 4.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
|
Date
|
Status
|
|---|---|
| Sep 25, 2024 | Chaptered by Secretary of State. Chapter 597, Statutes of 2024. |
| Sep 25, 2024 | Approved by the Governor. |
| Sep 9, 2024 | Enrolled and presented to the Governor at 3 p.m. |
| Aug 29, 2024 | Assembly amendments concurred in. (Ayes 40. Noes 0. Page 5638.) Ordered to engrossing and enrolling. |
| Aug 28, 2024 | In Senate. Concurrence in Assembly amendments pending. |
| Aug 28, 2024 | Read third time. Passed. (Ayes 77. Noes 0. Page 6692.) Ordered to the Senate. |
| Aug 15, 2024 | Ordered to third reading. |
| Aug 15, 2024 | Read third time and amended. |
| Aug 8, 2024 | Ordered to third reading. |
| Aug 8, 2024 | From consent calendar on motion of Assembly Member Aguiar-Curry. |
| Aug 8, 2024 | Read second time. Ordered to consent calendar. |
| Aug 7, 2024 | From committee: Do pass. Ordered to consent calendar. (Ayes 14. Noes 0.) (August 7). |
| Jun 24, 2024 | Read second time and amended. Re-referred to Com. on APPR. |
| Jun 20, 2024 | From committee: Do pass as amended and re-refer to Com. on APPR. with recommendation: To consent calendar. (Ayes 16. Noes 0.) (June 19). |
| Jun 5, 2024 | June 5 set for first hearing canceled at the request of author. |
| May 29, 2024 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on U. & E. |
| May 28, 2024 | Referred to Com. on U. & E. |
| May 21, 2024 | In Assembly. Read first time. Held at Desk. |
| May 20, 2024 | Read third time. Passed. (Ayes 39. Noes 0. Page 4024.) Ordered to the Assembly. |
| May 16, 2024 | Read second time. Ordered to third reading. |
| May 16, 2024 | From committee: Do pass. (Ayes 7. Noes 0. Page 3968.) (May 16). |
| May 10, 2024 | Set for hearing May 16. |
| Apr 29, 2024 | April 29 hearing: Placed on APPR suspense file. |
| Apr 22, 2024 | Set for hearing April 29. |
| Apr 18, 2024 | Re-referred to Com. on APPR. |
| Apr 18, 2024 | Withdrawn from committee. |
| Apr 17, 2024 | Read second time and amended. Re-referred to Com. on RLS. |
| Apr 16, 2024 | From committee: Do pass as amended and re-refer to Com. on RLS. (Ayes 18. Noes 0. Page 3631.) (April 16). |
| Apr 4, 2024 | Set for hearing April 16. |
| Mar 18, 2024 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on E., U. & C. |
| Feb 14, 2024 | Referred to Com. on E., U. & C. |
| Feb 2, 2024 | From printer. May be acted upon on or after March 3. |
| Feb 1, 2024 | Introduced. Read first time. To Com. on RLS. for assignment. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Aug 29, 2024 | Unfinished Business SB1006 Padilla Concurrence | Senate Floor |
Passed |
|
| Aug 28, 2024 | SB 1006 Padilla Senate Third Reading By Petrie-Norris | Assembly Floor |
Passed |
|
| Aug 7, 2024 | Do pass. To Consent Calendar. | Assembly Standing Committee on Appropriations |
Passed |
|
| Jun 19, 2024 | Do pass as amended, and be re-referred to the Committee on [Appropriations] with recommendation: To Consent Calendar | Assembly Standing Committee on Utilities and Energy |
Passed |
|
| May 20, 2024 | Senate 3rd Reading SB1006 Padilla | Senate Floor |
Passed |
|
| May 16, 2024 | Do pass | Senate Standing Committee on Appropriations |
Passed |
|
| Apr 29, 2024 | Placed on suspense file | Senate Standing Committee on Appropriations |
Passed |
|
| Apr 16, 2024 | Do pass as amended, but first amend, and re-refer to the Committee on [Rules] | Senate Standing Committee on Energy, Utilities and Communications |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| 350 Humboldt: Grass Roots Climate Action | ** Support | |
| Advanced Energy Economy | ** Support | |
| Advanced Energy United | ** Support | |
| An individual | ** Support | |
| California Energy Storage Alliance | ** Support | |
| California Environmental Voters | ** Support | |
| California Farm Bureau Federation | ** Support | |
| California State Association Of Electrical Workers | ** Support | |
| California Wind Energy Association | ** Support | |
| Center for Energy Efficiency and Renewable Technologies | ** Support | |
| Ceres | ** Support | |
| Citizens' Climate Lobby California | ** Support | |
| Clean Power Campaign | ** Support | |
| Coalition of California Utility Employees | ** Support | |
| Environmental Protection Information Center | ** Support | |
| Environment California | ** Support | |
| Environment Defense Fund | ** Support | |
| FissionTransition | ** Support | |
| Independent Energy Producers Association | ** Support | |
| Large-Scale Solar Association | ** Support | |
| Los Angeles Business Council | ** Support | |
| Natural Resources Defense Council | ** Support | |
| San Diego Community Power | ** Support | |
| Sierra Club California | ** Support | |
| Solar Energy Industries Association | ** Support | |
| Sonoma Clean Power | ** Support | |
| The Climate Reality Project, Bay Area Chapter | ** Support | |
| Union Of Concerned Scientists | ** Support | |
| WATT Coalition | ** Support | |
| West LA Democratic Club | ** Support |
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 1006 |
UNFINISHED BUSINESS
Bill No: SB 1006
Author: Padilla (D)
Amended: 8/15/24
Vote: 21
SENATE ENERGY, U. & C. COMMITTEE: 18-0, 4/16/24
AYES: Bradford, Dahle, Ashby, Becker, Caballero, Dodd, Durazo, Eggman, Gonzalez, Grove, Limón, Min, Newman, Rubio, Seyarto, Skinner, Stern, Wilk
SENATE APPROPRIATIONS COMMITTEE: 7-0, 5/16/24
AYES: Caballero, Jones, Ashby, Becker, Bradford, Seyarto, Wahab
SENATE FLOOR: 39-0, 5/20/24
AYES: Allen, Alvarado-Gil, Archuleta, Ashby, Atkins, Becker, Blakespear, Bradford, Caballero, Cortese, Dahle, Dodd, Durazo, Eggman, Glazer, Gonzalez, Grove, Hurtado, Jones, Laird, Limón, McGuire, Menjivar, Newman, Nguyen, Niello, Ochoa Bogh, Padilla, Portantino, Roth, Rubio, Seyarto, Skinner, Smallwood-Cuevas, Stern, Umberg, Wahab, Wiener, Wilk
NO VOTE RECORDED: Min
ASSEMBLY FLOOR: 77-0, 8/28/24 - See last page for vote
SUBJECT: Electricity: transmission capacity: reconductoring and grid-enhancing technologies
SOURCE: Author
DIGEST:
This bill requires electrical transmission utilities, by January 1, 2026, to develop studies on the feasibility of using grid-enhancing technologies and advanced reconductors, and specifies the content and cadence of those studies.
Assembly Amendments
recast language that would have required a strategic plan and an evaluation and instead requires studies on the feasibility of using grid-enhancing technologies (GETs) and advanced reconductors within the transmission and distribution planning processes. Additional amendments make related clarifying and technical changes and include provisions that limit information from public disclosure that affects the security of the electrical system.
ANALYSIS:
Existing law:
- Establishes that U.S. Federal Energy Regulatory Commission (FERC) has exclusive jurisdiction over the transmission of electric energy in interstate commerce. Also establishes the process and procedures for establishing transmission of electric energy in interstate commerce by public utilities, i.e., the rates, terms & conditions of interstate electric transmission by public utilities. (Federal Power Act §§§201, 205, 206 (16 USC 824, 824d, 824e))
- Establishes the California Independent System Operator (CAISO) as a nonprofit, public benefit corporation to manage the transmission grid and related energy markets, as provided. (Public Utilities Code §345 et seq.)
- Provides that the California Public Utilities Commission (CPUC) may supervise and regulate every public utility in the state and may do all things, whether specifically designated or in addition, which are necessary and convenient in the exercise of such power and jurisdiction. (Public Utilities Code §701)
- Prohibits an electrical corporation from beginning the construction of a line, plant, or system, or of any extension thereof, without having first obtained from the CPUC a certificate that the present or future public convenience and necessity require or will require its construction. Provides that the extension, expansion, upgrade, or other modification of an existing electrical transmission facility, including transmission lines and substations, does not require a certificate that the present or future public convenience and necessity requires or will require its construction. (Public Utilities Code §1001)
This bill:
- Makes several findings and declarations regarding the potential of GETs and advanced conductors to quickly and cost-effectively increase transmission capacity.
- Requires each transmission utility, defined as electrical corporations that are participating transmission owners that have turned over operation to the CAISO, to, on or before January 1, 2026, and every two years thereafter, to prepare a study of the feasibility of projects using GETs to achieve, among other purposes, increased capacity to connect new renewable energy and zero-carbon resources, reduce transmission system congestion, reduce curtailment of renewable and zero-carbon resources, increase reliability, and reduce the risk of igniting wildfires.
- Requires each transmission utility, on or before January 1, 2026, and at least every four years thereafter, to prepare a study of which of its transmission lines can be reconductored with advanced conductors to achieve, among other purposes, increased capacity to connect new renewable energy and zero-carbon resources.
- Requires, upon completion of the studies, each transmission utility to submit the studies to the CAISO, and requires each transmission utility to request the CAISO review the results of the studies as part of the annual transmission planning process for economic, reliability, and policy goals.
- Requires the transmission utilities, upon submission to the CAISO, to make their studies publicly available. Specifies that information in the studies that is determined by the CAISO, in consultation with the transmission utilities, to be necessary to protect the security of the electrical transmission system is to be withheld from public disclosure and makes legislative findings to that effect.
- Requires each electrical corporation operating a distribution system to consider GETs and consider reconductoring with advanced conductors as part of its annual distribution planning process.
Background
- Transmission projects. Electric transmission lines are generally high voltage lines that move electricity from generation resources (power plants) to distribution lines in neighborhoods. Companies, usually electric investor-owned utilities (IOUs), proposing the construction of new transmission, are required to obtain a permit from the CPUC for construction of specified infrastructure listed under Public Utilities Code §1001, including transmission projects.
- Need for expanded transmission capacity. In order for the state to meet its clean energy goals, including achieving 100 percent clean energy by 2045, electric transmission capacity will likely need to grow significantly. The CAISO conducts its annual transmission planning process to identify potential transmission system limitations and opportunities for system reinforcements that improve reliability and efficiency. The CAISO identifies projects that address grid reliability requirements, identify upgrades needed to successfully meet California’s policy goals, and explore projects that can bring economic benefits to consumers. In 2021, the CAISO created a 20-Year Transmission Outlook for the electric grid, in collaboration with the CPUC and the California Energy Commission (CEC), with the goal of exploring the longer-term grid requirements and options for meeting the state’s SB 100 clean energy goals reliably and cost-effectively. The 20-Year Transmission Outlook estimates a significant amount, and expense, to construct and expand transmission facilities, including an estimated $10.74 billion in upgrades to existing facilities.
- Grid-enhancing technologies. GETs, generally, are a combination of hardware and software that can increase transmission capacity, decrease congestion, and improve reliability on transmission lines. An April 2023 Brattle Group white paper, Building a Better Grid: How Grid-enhancing Technologies Complement Transmission Buildouts, discusses how GETs can help improve transmission capacity and efficiency. The paper notes that transmission transfer capability depends on where and how new transmission lines are connected to the rest of the electrical grid system – the topology of the transmission network (including the points of injection and withdrawal of energy). Both the transfer capability of lines (and other components of the grid) and network topology determine how, where, and the quantity of the power flows. Many GETs are built on either of two applications to increase transfer capability: one that explores enhanced and flexible application of the pre-determined transfer capability, and the other that focuses on flexible and dynamic control of transmission systems. Examples of GETs include dynamic line ratings, advanced power flow controls, and advanced topology control. Dynamic line ratings (DLRs) try to better address individual line transfer capability based on actual conditions. Advanced power flow controls (generally hardware) and advanced topology control (generally software) direct electricity away from overloaded lines and onto underutilized lines, such as by opening or closing circuit breakers. As noted in the Brattle Group paper: The comparative advantages of GETs include their portability and scalability, speed to deploy, and lower costs. Importantly, per the report, “GETs rarely replace transmission, rather, they enhance transmission…”
- Advanced reconductoring. Reconductoring is the replacement of a transmission line’s existing conductors with advanced conductors, essentially swapping out the Aluminum Conductor Steel Reinforced (ACSR) for a smaller composite core conductors that enable higher operating temperatures. According to a November 2023 Energy Institute at Haas paper, “Accelerating Transmission Expansion by Using Advanced Conductors in Existing Right-of-Way” by Emilia Chojkiewicz, et al. (Energy Institute WP 343), reconductoring holds significant potential for rapid transmission expansion. The advanced conductors can carry approximately twice as much power as conventional conductors. Advanced conductors use existing transmission towers and rights of way, thereby circumventing the land acquisition and permitting processes that can impede construction of new transmission lines. However, replacing conventional conductors with advanced conductors requires taking circuits out of service during the replacement or conducting live-line work, which carries additional risks. Either approach can be challenging, and in some cases infeasible, when transmission constraints exist.
Comments
- Need for this bill. Supporters of this bill note the need for the state to upgrade and expand its electric transmission infrastructure to meet its clean energy goals. They contend the increasing demand placed on California’s electric grid as more vehicles and homes are powered by electricity. They express concerns that the transmission grid is not keeping pace with demand, as transmission lines can take more than a decade to site, permit, and build. They point to the opportunities with GETs and advanced conductors to help the state “enhance the existing transmission infrastructure to its maximum potential and make it more efficient, resilient, and cost-effective.”
- Current use of GETs and advanced conductors. The two papers noted above, along with others, comment on the more prevalent use of GETs and advanced conductors in other countries, particularly in Europe and India. These papers generally state that the use of these technologies has not been as quickly embraced in the United States. In California, advanced conductors have been deployed, particularly by Southern California Edison (SCE) who has deployed reconductoring projects, including the Big Creek-Ventura 220kV network. Additionally, the CAISO shared that they have considered GETs in the annual transmission planning process for many years. Specifically, the CAISO shared they typically consider advanced conductors and power flow controllers as planning tools providing alternatives to capital expenditures, as well as, dynamic thermal line ratings, and topology optimizations to access operational benefits through additional capacity. In addition to the Big Creek-Ventura line, the CAISO approved a phase shifting transformer flow controller installation at the Imperial Valley Substation. More recently, there are two projects under development in San Jose with flow controls. In its most recent transmission plan, the CAISO listed out 17 approved transmission projects since 2013-14 transmission plan to deploy GETS, particularly flow controllers, advanced conductors, and dynamic voltage controls.
- Federal requirements adopted to require use of GETs and advanced conductors. At the federal level, FERC just adopted (May 13, 2024) a transmission and cost allocation rule, Order No. 1920, “Building for the Future Through Electric Regional Transmission Planning and Cost Allocation and Generator Interconnection” (RM21-17-000) which among its provisions requires public utility transmission providers to more fully consider the use of GETs, such as dynamic line ratings, advanced power flow control devices, advanced conductors and transmission switching, in their transmission planning. Recently, the CPUC along with the CEC, CAISO, Pacific Gas & Electric, SCE, and Energy Institute at Haas have been awarded a Department of Energy GRIP grant (eight years long) to deploy advanced conductors and two other GETs technologies: dynamic line rating and real-time short circuit duty monitoring. More recently, on May 28th, the White House announced the launch of a Federal-State Modern Grid Deployment Initiative to accelerate improvements to the electric transmission and distribution network to help meet “the country’s objectives for affordable, clean, reliable, and resilient power.” The Initiative involves a commitment from the Federal government and 21 states, including California, to work together to increase cooperation on transmission planning, including specific commitments to expand the use of GETs and advanced conductors. This Initiative is intended to build up last month’s Department of Energy announcement to expand a categorical exclusion under the National Environmental Policy Act for upgrading and rebuilding transmission lines, including for reconductoring.
- Impacts to ratepayers. The actual savings benefits for the use of GETs and advanced conductors will vary by transmission line. Both the Brattle Group and Energy Institute papers cite opportunities for savings from the use of GETs and advanced conductors. With regards to GETs, these technologies can be deployed on existing transmission lines to enhance efficiency, with the potential to reduce congestion by 40 percent. Such level of efficiency can provide savings to ratepayers in the form of reducing the need to build additional transmission lines which can be very costly. Advanced conductors have a higher up-front cost as compared to conventional aluminum conductors – roughly two to three times the costs – though they have the potential for long-term savings given the potential to double the capacity of conventional conductors. As stated in the Energy Institute paper, “Transmission networks are complex, and the actual increase in power transfer capacity offered by reconductoring is determined by a multitude of factors beyond the scope of this analysis. We recommend that transmission owners, ISOs, and RTOs perform more detailed studies…to evaluate the wide-scale deployment of advanced conductors in their networks.”
- Protecting the security of the electrical transmission system. Author amendments in the Assembly added a provision to limit public disclosure of information in the studies submitted by transmission utilities where the CAISO has determined the information is necessary to protect the security of the electrical transmission system. Through its existing tariffs and practices, the CAISO limits disclosure of information that is necessary to protect the security of the electrical grid (among other security concerns, including market manipulation). As a result, it is not clear additional language is necessary. However, the author intends to make explicit that such protection is afforded to the studies required in this bill.
Related/Prior Legislation
AB 2779 (Petrie-Norris, 2024) requires the CAISO, upon approval of the annual transmission plan, to report on any new use of any grid enhancing technology and its associated cost and efficiency savings. The bill is pending on the Senate Floor.
SB 319 (McGuire, Chapter 390, Statutes of 2023) required the CEC and the CPUC, in coordination with the CAISO, to better and regularly coordinate planning and permitting of energy transmission infrastructure to ensure the state meets its clean energy goals and to evaluate and report on that planning and related infrastructure development. The bill also required these state energy agencies to jointly develop an electrical transmission infrastructure development guidebook.
SB 529 (Hertzberg, Chapter 357, Statutes of 2022) exempted an extension, expansion, upgrade, or other modification of an existing transmission line or substations from the requirement of a CPCN and directed the CPUC to revise its GO, by January 1, 2024, to instead use its permit to construct process for these approvals.
SB 887 (Becker, Chapter 358, Statutes of 2022) required 15-year projections of energy resource portfolios and energy demand to inform transmission planning to achieve the state’s clean energy goals, and requires the CAISO to consider approval for specified transmission projects as part of the 2022-23 transmission planning process.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
According to the Assembly Committee on Appropriations, there will be minor state costs, if any, as this bill make no requirements of a state agency, and does not indirectly result in a state agency taking on additional workload.
SUPPORT: (Verified 8/19/24)
350 Humboldt: Grass Roots Climate Action
Advanced Energy United
California Energy Storage Alliance
California Environmental Voters
California Farm Bureau Federation
California State Association of Electrical Workers
California Wind Energy Association
Center for Energy Efficiency and Renewable Technologies
Ceres
Clean Power Campaign
Citizens' Climate Lobby California
Coalition of California Utility Employees
Environment California
Environment Defense Fund
Environmental Protection Information Center
Fission Transition
Independent Energy Producers Association
Large-scale Solar Association
Los Angeles Business Council
Natural Resources Defense Council
San Diego Community Power
Sierra Club California
Solar Energy Industries Association
Sonoma Clean Power
The Climate Reality Project: Bay Area Chapter
WATT Coalition
Union of Concerned Scientists
WATT Coalition
West LA Democratic Club
One individual
OPPOSITION: (Verified 8/19/24)
None received
ARGUMENTS IN SUPPORT: In support of this bill, the Coalition of California Utility Employees and the California State Association of Electrical Workers state:
California must dramatically increase the total capacity of its transmission system to supply the vastly increased demand for electricity needed to meet our carbon neutrality goals. This will certainly require many new transmission lines. But in addition to new lines, new technology can enable us to get much more capacity out of existing transmission lines and transmission corridors, and to get that capacity much more quickly. ,,,Fully evaluating opportunities to deploy GETS and advanced conductors is a no-regrets policy which could yield lower costs for consumers while increasing California’s ability to meet its carbon reduction goals.
ASSEMBLY FLOOR: 77-0, 8/28/24
AYES: Addis, Aguiar-Curry, Alanis, Alvarez, Arambula, Bains, Bauer-Kahan, Bennett, Berman, Boerner, Bonta, Bryan, Calderon, Juan Carrillo, Wendy Carrillo, Chen, Connolly, Megan Dahle, Davies, Dixon, Essayli, Flora, Mike Fong, Friedman, Gabriel, Gallagher, Garcia, Gipson, Grayson, Haney, Hart, Holden, Hoover, Irwin, Jackson, Jones-Sawyer, Kalra, Lackey, Lee, Low, Lowenthal, Maienschein, Mathis, McCarty, McKinnor, Muratsuchi, Stephanie Nguyen, Pacheco, Papan, Jim Patterson, Joe Patterson, Pellerin, Petrie-Norris, Quirk-Silva, Ramos, Rendon, Reyes, Luz Rivas, Rodriguez, Blanca Rubio, Sanchez, Santiago, Schiavo, Soria, Ta, Ting, Valencia, Villapudua, Waldron, Wallis, Ward, Weber, Wicks, Wilson, Wood, Zbur, Robert Rivas
NO VOTE RECORDED: Cervantes, Ortega
Prepared by: Nidia Bautista / E., U. & C. / (916) 651-4107
8/29/24 8:58:17
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 1006 |
UNFINISHED BUSINESS
Bill No: SB 1006
Author: Padilla (D)
Amended: 8/15/24
Vote: 21
SENATE ENERGY, U. & C. COMMITTEE: 18-0, 4/16/24
AYES: Bradford, Dahle, Ashby, Becker, Caballero, Dodd, Durazo, Eggman, Gonzalez, Grove, Limón, Min, Newman, Rubio, Seyarto, Skinner, Stern, Wilk
SENATE APPROPRIATIONS COMMITTEE: 7-0, 5/16/24
AYES: Caballero, Jones, Ashby, Becker, Bradford, Seyarto, Wahab
SENATE FLOOR: 39-0, 5/20/24
AYES: Allen, Alvarado-Gil, Archuleta, Ashby, Atkins, Becker, Blakespear, Bradford, Caballero, Cortese, Dahle, Dodd, Durazo, Eggman, Glazer, Gonzalez, Grove, Hurtado, Jones, Laird, Limón, McGuire, Menjivar, Newman, Nguyen, Niello, Ochoa Bogh, Padilla, Portantino, Roth, Rubio, Seyarto, Skinner, Smallwood-Cuevas, Stern, Umberg, Wahab, Wiener, Wilk
NO VOTE RECORDED: Min
ASSEMBLY FLOOR: 58-0, - Roll call vote not available
SUBJECT: Electricity: transmission capacity: reconductoring and grid-enhancing technologies
SOURCE: Author
DIGEST:
This bill requires electrical transmission utilities, by January 1, 2026, to develop studies on the feasibility of using grid-enhancing technologies and advanced reconductors, and specifies the content and cadence of those studies.
Assembly Amendments
recast language that would have required a strategic plan and an evaluation and instead requires studies on the feasibility of using grid-enhancing technologies (GETs) and advanced reconductors within the transmission and distribution planning processes. Additional amendments make related clarifying and technical changes and include provisions that limit information from public disclosure that affects the security of the electrical system.
ANALYSIS:
Existing law:
- Establishes that U.S. Federal Energy Regulatory Commission (FERC) has exclusive jurisdiction over the transmission of electric energy in interstate commerce. Also establishes the process and procedures for establishing transmission of electric energy in interstate commerce by public utilities, i.e., the rates, terms & conditions of interstate electric transmission by public utilities. (Federal Power Act §§§201, 205, 206 (16 USC 824, 824d, 824e))
- Establishes the California Independent System Operator (CAISO) as a nonprofit, public benefit corporation to manage the transmission grid and related energy markets, as provided. (Public Utilities Code §345 et seq.)
- Provides that the California Public Utilities Commission (CPUC) may supervise and regulate every public utility in the state and may do all things, whether specifically designated or in addition, which are necessary and convenient in the exercise of such power and jurisdiction. (Public Utilities Code §701)
- Prohibits an electrical corporation from beginning the construction of a line, plant, or system, or of any extension thereof, without having first obtained from the CPUC a certificate that the present or future public convenience and necessity require or will require its construction. Provides that the extension, expansion, upgrade, or other modification of an existing electrical transmission facility, including transmission lines and substations, does not require a certificate that the present or future public convenience and necessity requires or will require its construction. (Public Utilities Code §1001)
This bill:
- Makes several findings and declarations regarding the potential of GETs and advanced conductors to quickly and cost-effectively increase transmission capacity.
- Requires each transmission utility, defined as electrical corporations that are participating transmission owners that have turned over operation to the CAISO, to, on or before January 1, 2026, and every two years thereafter, to prepare a study of the feasibility of projects using GETs to achieve, among other purposes, increased capacity to connect new renewable energy and zero-carbon resources, reduce transmission system congestion, reduce curtailment of renewable and zero-carbon resources, increase reliability, and reduce the risk of igniting wildfires.
- Requires each transmission utility, on or before January 1, 2026, and at least every four years thereafter, to prepare a study of which of its transmission lines can be reconductored with advanced conductors to achieve, among other purposes, increased capacity to connect new renewable energy and zero-carbon resources.
- Requires, upon completion of the studies, each transmission utility to submit the studies to the CAISO, and requires each transmission utility to request the CAISO review the results of the studies as part of the annual transmission planning process for economic, reliability, and policy goals.
- Requires the transmission utilities, upon submission to the CAISO, to make their studies publicly available. Specifies that information in the studies that is determined by the CAISO, in consultation with the transmission utilities, to be necessary to protect the security of the electrical transmission system is to be withheld from public disclosure and makes legislative findings to that effect.
- Requires each electrical corporation operating a distribution system to consider GETs and consider reconductoring with advanced conductors as part of its annual distribution planning process.
Background
- Transmission projects. Electric transmission lines are generally high voltage lines that move electricity from generation resources (power plants) to distribution lines in neighborhoods. Companies, usually electric investor-owned utilities (IOUs), proposing the construction of new transmission, are required to obtain a permit from the CPUC for construction of specified infrastructure listed under Public Utilities Code §1001, including transmission projects.
- Need for expanded transmission capacity. In order for the state to meet its clean energy goals, including achieving 100 percent clean energy by 2045, electric transmission capacity will likely need to grow significantly. The CAISO conducts its annual transmission planning process to identify potential transmission system limitations and opportunities for system reinforcements that improve reliability and efficiency. The CAISO identifies projects that address grid reliability requirements, identify upgrades needed to successfully meet California’s policy goals, and explore projects that can bring economic benefits to consumers. In 2021, the CAISO created a 20-Year Transmission Outlook for the electric grid, in collaboration with the CPUC and the California Energy Commission (CEC), with the goal of exploring the longer-term grid requirements and options for meeting the state’s SB 100 clean energy goals reliably and cost-effectively. The 20-Year Transmission Outlook estimates a significant amount, and expense, to construct and expand transmission facilities, including an estimated $10.74 billion in upgrades to existing facilities.
- Grid-enhancing technologies. GETs, generally, are a combination of hardware and software that can increase transmission capacity, decrease congestion, and improve reliability on transmission lines. An April 2023 Brattle Group white paper, Building a Better Grid: How Grid-enhancing Technologies Complement Transmission Buildouts, discusses how GETs can help improve transmission capacity and efficiency. The paper notes that transmission transfer capability depends on where and how new transmission lines are connected to the rest of the electrical grid system – the topology of the transmission network (including the points of injection and withdrawal of energy). Both the transfer capability of lines (and other components of the grid) and network topology determine how, where, and the quantity of the power flows. Many GETs are built on either of two applications to increase transfer capability: one that explores enhanced and flexible application of the pre-determined transfer capability, and the other that focuses on flexible and dynamic control of transmission systems. Examples of GETs include dynamic line ratings, advanced power flow controls, and advanced topology control. Dynamic line ratings (DLRs) try to better address individual line transfer capability based on actual conditions. Advanced power flow controls (generally hardware) and advanced topology control (generally software) direct electricity away from overloaded lines and onto underutilized lines, such as by opening or closing circuit breakers. As noted in the Brattle Group paper: The comparative advantages of GETs include their portability and scalability, speed to deploy, and lower costs. Importantly, per the report, “GETs rarely replace transmission, rather, they enhance transmission…”
- Advanced reconductoring. Reconductoring is the replacement of a transmission line’s existing conductors with advanced conductors, essentially swapping out the Aluminum Conductor Steel Reinforced (ACSR) for a smaller composite core conductors that enable higher operating temperatures. According to a November 2023 Energy Institute at Haas paper, “Accelerating Transmission Expansion by Using Advanced Conductors in Existing Right-of-Way” by Emilia Chojkiewicz, et al. (Energy Institute WP 343), reconductoring holds significant potential for rapid transmission expansion. The advanced conductors can carry approximately twice as much power as conventional conductors. Advanced conductors use existing transmission towers and rights of way, thereby circumventing the land acquisition and permitting processes that can impede construction of new transmission lines. However, replacing conventional conductors with advanced conductors requires taking circuits out of service during the replacement or conducting live-line work, which carries additional risks. Either approach can be challenging, and in some cases infeasible, when transmission constraints exist.
Comments
- Need for this bill. Supporters of this bill note the need for the state to upgrade and expand its electric transmission infrastructure to meet its clean energy goals. They contend the increasing demand placed on California’s electric grid as more vehicles and homes are powered by electricity. They express concerns that the transmission grid is not keeping pace with demand, as transmission lines can take more than a decade to site, permit, and build. They point to the opportunities with GETs and advanced conductors to help the state “enhance the existing transmission infrastructure to its maximum potential and make it more efficient, resilient, and cost-effective.”
- Current use of GETs and advanced conductors. The two papers noted above, along with others, comment on the more prevalent use of GETs and advanced conductors in other countries, particularly in Europe and India. These papers generally state that the use of these technologies has not been as quickly embraced in the United States. In California, advanced conductors have been deployed, particularly by Southern California Edison (SCE) who has deployed reconductoring projects, including the Big Creek-Ventura 220kV network. Additionally, the CAISO shared that they have considered GETs in the annual transmission planning process for many years. Specifically, the CAISO shared they typically consider advanced conductors and power flow controllers as planning tools providing alternatives to capital expenditures, as well as, dynamic thermal line ratings, and topology optimizations to access operational benefits through additional capacity. In addition to the Big Creek-Ventura line, the CAISO approved a phase shifting transformer flow controller installation at the Imperial Valley Substation. More recently, there are two projects under development in San Jose with flow controls. In its most recent transmission plan, the CAISO listed out 17 approved transmission projects since 2013-14 transmission plan to deploy GETS, particularly flow controllers, advanced conductors, and dynamic voltage controls.
- Federal requirements adopted to require use of GETs and advanced conductors. At the federal level, FERC just adopted (May 13, 2024) a transmission and cost allocation rule, Order No. 1920, “Building for the Future Through Electric Regional Transmission Planning and Cost Allocation and Generator Interconnection” (RM21-17-000) which among its provisions requires public utility transmission providers to more fully consider the use of GETs, such as dynamic line ratings, advanced power flow control devices, advanced conductors and transmission switching, in their transmission planning. Recently, the CPUC along with the CEC, CAISO, Pacific Gas & Electric, SCE, and Energy Institute at Haas have been awarded a Department of Energy GRIP grant (eight years long) to deploy advanced conductors and two other GETs technologies: dynamic line rating and real-time short circuit duty monitoring. More recently, on May 28th, the White House announced the launch of a Federal-State Modern Grid Deployment Initiative to accelerate improvements to the electric transmission and distribution network to help meet “the country’s objectives for affordable, clean, reliable, and resilient power.” The Initiative involves a commitment from the Federal government and 21 states, including California, to work together to increase cooperation on transmission planning, including specific commitments to expand the use of GETs and advanced conductors. This Initiative is intended to build up last month’s Department of Energy announcement to expand a categorical exclusion under the National Environmental Policy Act for upgrading and rebuilding transmission lines, including for reconductoring.
- Impacts to ratepayers. The actual savings benefits for the use of GETs and advanced conductors will vary by transmission line. Both the Brattle Group and Energy Institute papers cite opportunities for savings from the use of GETs and advanced conductors. With regards to GETs, these technologies can be deployed on existing transmission lines to enhance efficiency, with the potential to reduce congestion by 40 percent. Such level of efficiency can provide savings to ratepayers in the form of reducing the need to build additional transmission lines which can be very costly. Advanced conductors have a higher up-front cost as compared to conventional aluminum conductors – roughly two to three times the costs – though they have the potential for long-term savings given the potential to double the capacity of conventional conductors. As stated in the Energy Institute paper, “Transmission networks are complex, and the actual increase in power transfer capacity offered by reconductoring is determined by a multitude of factors beyond the scope of this analysis. We recommend that transmission owners, ISOs, and RTOs perform more detailed studies…to evaluate the wide-scale deployment of advanced conductors in their networks.”
- Protecting the security of the electrical transmission system. Author amendments in the Assembly added a provision to limit public disclosure of information in the studies submitted by transmission utilities where the CAISO has determined the information is necessary to protect the security of the electrical transmission system. Through its existing tariffs and practices, the CAISO limits disclosure of information that is necessary to protect the security of the electrical grid (among other security concerns, including market manipulation). As a result, it is not clear additional language is necessary. However, the author intends to make explicit that such protection is afforded to the studies required in this bill.
Related/Prior Legislation
AB 2779 (Petrie-Norris, 2024) requires the CAISO, upon approval of the annual transmission plan, to report on any new use of any grid enhancing technology and its associated cost and efficiency savings. The bill is pending on the Senate Floor.
SB 319 (McGuire, Chapter 390, Statutes of 2023) required the CEC and the CPUC, in coordination with the CAISO, to better and regularly coordinate planning and permitting of energy transmission infrastructure to ensure the state meets its clean energy goals and to evaluate and report on that planning and related infrastructure development. The bill also required these state energy agencies to jointly develop an electrical transmission infrastructure development guidebook.
SB 529 (Hertzberg, Chapter 357, Statutes of 2022) exempted an extension, expansion, upgrade, or other modification of an existing transmission line or substations from the requirement of a CPCN and directed the CPUC to revise its GO, by January 1, 2024, to instead use its permit to construct process for these approvals.
SB 887 (Becker, Chapter 358, Statutes of 2022) required 15-year projections of energy resource portfolios and energy demand to inform transmission planning to achieve the state’s clean energy goals, and requires the CAISO to consider approval for specified transmission projects as part of the 2022-23 transmission planning process.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
According to the Assembly Committee on Appropriations, there will be minor state costs, if any, as this bill make no requirements of a state agency, and does not indirectly result in a state agency taking on additional workload.
SUPPORT: (Verified 8/19/24)
350 Humboldt: Grass Roots Climate Action
Advanced Energy United
California Energy Storage Alliance
California Environmental Voters
California Farm Bureau Federation
California State Association of Electrical Workers
California Wind Energy Association
Center for Energy Efficiency and Renewable Technologies
Ceres
Clean Power Campaign
Citizens' Climate Lobby California
Coalition of California Utility Employees
Environment California
Environment Defense Fund
Environmental Protection Information Center
Fission Transition
Independent Energy Producers Association
Large-scale Solar Association
Los Angeles Business Council
Natural Resources Defense Council
San Diego Community Power
Sierra Club California
Solar Energy Industries Association
Sonoma Clean Power
The Climate Reality Project: Bay Area Chapter
WATT Coalition
Union of Concerned Scientists
WATT Coalition
West LA Democratic Club
One individual
OPPOSITION: (Verified 8/19/24)
None received
ARGUMENTS IN SUPPORT: In support of this bill, the Coalition of California Utility Employees and the California State Association of Electrical Workers state:
California must dramatically increase the total capacity of its transmission system to supply the vastly increased demand for electricity needed to meet our carbon neutrality goals. This will certainly require many new transmission lines. But in addition to new lines, new technology can enable us to get much more capacity out of existing transmission lines and transmission corridors, and to get that capacity much more quickly. ,,,Fully evaluating opportunities to deploy GETS and advanced conductors is a no-regrets policy which could yield lower costs for consumers while increasing California’s ability to meet its carbon reduction goals.
Prepared by: Nidia Bautista / E., U. & C. / (916) 651-4107
8/28/24 22:09:23
**** END ****
SENATE THIRD READING
STR Bill Id:SB 1006
Author:(Padilla)
As Amended Ver:August 15, 2024
Majority vote
SUMMARY
Requires a transmission utility to periodically study (a) the feasibility of using "grid-enhancing technologies" (GETs) and (b) the potential to reconductor its transmission lines with advanced conductors, and to provide the results of the studies to the California Independent System Operator (CAISO) for review and, possibly, inclusion in CAISO's transmission planning studies and analyses.
Major Provisions
- Requires each transmission utility – meaning an investor-owned electrical utility (IOU) that is a participating owner of transmission infrastructure, the control of which has been turned over to CAISO – to prepare a study, before January 1, 2026, and every two years thereafter, of the feasibility of projects using GETs – meaning hardware and software that increases the capacity of electrical lines and improves the efficiency, reliability, and safety of the grid – to achieve specified goals that include efficiency, capacity, connectivity to renewable and zero-carbon resources.
- Requires each transmission utility to prepare a study, before January 1, 2026, and every four years thereafter, of which of its transmission lines can be reconductored with advanced conductors to achieve one or more specified goals, which include increased efficiency, capacity, and connectivity to renewable and zero-carbon resources.
- Specifies that information in the studies of transmission lines by a transmission utility as determined by the CAISO, shall be done in consultation with a transmission utility, to protect the security of the electrical transmission system.
COMMENTS
State of Transmission Lines. According to the U.S. Department of Energy (DOE), an estimated 70% of transmission and distribution lines in the U.S. are well into the second half of their 50-year life expectancy. As transmission lines age, they become more inefficient, increasing the likelihood of congested power lines, which can force grid operators to reroute power through less optimal paths and rely on more expensive or less clean power generation. More so, extreme cases of transmission constraints may even overload transmission systems, forcing utilities to employ periodic load shedding tactics (i.e., rolling blackouts).
GETS. To facilitate the clean energy transition, GETs have been posed by researchers and industry leaders as an interim, cost-effective solution to unlock transmission capacity in the near term and buy time for long-term transmission planning. GETs encompass a suite of technologies – such as advanced conductors, dynamic line ratings, advanced power flow control devices, and analytical tools – that can be used to maximize the transmission of electricity across existing lines. According to the Federal Energy Regulatory Commission (FERC), GETs can cost less than 10% of the cost of investing in new transmission lines, and can save millions in annual congestion costs. As a result, FERC has recently taken steps to push for consideration and adoption of GETs, through incentive programs supported by the Federal Bipartisan Infrastructure Law.
GETs Deployment in California – According to the 2023- 2024 Transmission Plan, CAISO supports the deployment of GETs, and has considered them on a case by case basis in past annual transmission planning processes. For instance, advanced conductors and power flow controllers are considered as planning tools and provide alternatives to capital expenditures. Dynamic thermal line ratings, and topology optimizations provide operational benefits through additional capacity. CAISO has also approved a phase shifting transformer flow controller installation at the Imperial Valley Substation. More recently, there are two projects under development in San Jose with flow controls.
GRIP Program – Specifically, as part of the Bipartisan Infrastructure Law, the Grid Resilience and Innovation Partnerships (GRIP) Program at the Department of Energy (DOE) program provides up to $10.5 billion in funding for projects to improve the reliability and resilience of the electric grid. In October 2023, DOE announced $ 3.5 billion for projects including those that incorporate GETs.
According to the Author
According to the author, "CAISO estimates 7,000 megawatts of new transmission capacity is needed each year for the next decade, but California is nowhere near achieving it. Two new studies demonstrate that reconductoring and GETs can nearly double grid capacity in a cost effective manner. To add transmission capacity in a cost effective and timely way, California must advance reconductoring and grid-enhancing technologies to modernize the grid and meet clean energy goals. We simply cannot rely on the grid of our grandparents to power our grandchildren's future."
Arguments in Support
This legislation is supported by various environmental, solar, wind and labor groups among others. They contend that GETs can maximize existing grid infrastructure and alleviate existing transmission constraints, as well as future constraints from expected shifts in power supply and demand. As such, they assert," the state must quickly make use of all available tools and technologies if it is to meet its ambitious goals and successfully transition to a sustainable energy system."
Arguments in Opposition
None on file.
FISCAL COMMENTS
VOTES
SENATE FLOOR: 39-0-1
YES: Allen, Alvarado-Gil, Archuleta, Ashby, Atkins, Becker, Blakespear, Bradford, Caballero, Cortese, Dahle, Dodd, Durazo, Eggman, Glazer, Gonzalez, Grove, Hurtado, Jones, Laird, Limón, McGuire, Menjivar, Newman, Nguyen, Niello, Ochoa Bogh, Padilla, Portantino, Roth, Rubio, Seyarto, Skinner, Smallwood-Cuevas, Stern, Umberg, Wahab, Wiener, Wilk
ABS, ABST OR NV: Min
ASM UTILITIES AND ENERGY: 16-0-0
YES: Petrie-Norris, Jim Patterson, Bauer-Kahan, Boerner, Calderon, Chen, Friedman, Hart, Holden, Joe Patterson, Reyes, Santiago, Ting, Wallis, Wood, Zbur
ASM APPROPRIATIONS: 14-0-1
YES: Wicks, Sanchez, Arambula, Bryan, Calderon, Wendy Carrillo, Dixon, Mike Fong, Grayson, Haney, Hart, Jim Patterson, Pellerin, Ta
ABS, ABST OR NV: Villapudua
UPDATED
VERSION: August 15, 2024
CONSULTANT: Lina V. Malova / U. & E. / (916) 319-2083 FN: 0003836
SENATE THIRD READING
STR Bill Id:SB 1006
Author:(Padilla)
As Amended Ver:June 24, 2024
Majority vote
SUMMARY
Requires a transmission utility to periodically study a) the feasibility of using "grid-enhancing technologies" (GETs) and b) the potential to reconductor its transmission lines with advanced conductors, and to provide the results of the studies to the California Independent System Operator (CAISO) for review and, possibly, inclusion in CAISO's transmission planning studies and analyses.
Major Provisions
- Requires each transmission utility – meaning an investor-owned electrical utility (IOU) that is a participating owner of transmission infrastructure, the control of which has been turned over to CAISO – to prepare a study, before January 1, 2026, and every two years thereafter, of the feasibility of projects using GETs – meaning hardware and software that increases the capacity of electrical lines and improves the efficiency, reliability, and safety of the grid – to achieve specified goals that include efficiency, capacity, connectivity to renewable and zero-carbon resources.
- Requires each transmission utility to prepare a study, before January 1, 2026, and every four years thereafter, of which of its transmission lines can be reconductored with advanced conductors to achieve one or more specified goals, which include increased efficiency, capacity, and connectivity to renewable and zero-carbon resources.
COMMENTS
State of Transmission Lines. According to the U.S. Department of Energy (DOE), an estimated 70% of transmission and distribution lines in the U.S. are well into the second half of their 50-year life expectancy. As transmission lines age, they become more inefficient, increasing the likelihood of congested power lines, which can force grid operators to reroute power through less optimal paths and rely on more expensive or less clean power generation. More so, extreme cases of transmission constraints may even overload transmission systems, forcing utilities to employ periodic load shedding tactics (i.e., rolling blackouts).
GETS. To facilitate the clean energy transition, GETs have been posed by researchers and industry leaders as an interim, cost-effective solution to unlock transmission capacity in the near term and buy time for long-term transmission planning. GETs encompass a suite of technologies – such as advanced conductors, dynamic line ratings, advanced power flow control devices, and analytical tools – that can be used to maximize the transmission of electricity across existing lines. According to the Federal Energy Regulatory Commission (FERC), GETs can cost less than 10% of the cost of investing in new transmission lines, and can save millions in annual congestion costs. As a result, FERC has recently taken steps to push for consideration and adoption of GETs, through incentive programs supported by the Federal Bipartisan Infrastructure Law.
GETs Deployment in California – According to the 2023- 2024 Transmission Plan, CAISO supports the deployment of GETs, and has considered them on a case by case basis in past annual transmission planning processes. For instance, advanced conductors and power flow controllers are considered as planning tools and provide alternatives to capital expenditures. Dynamic thermal line ratings, and topology optimizations provide operational benefits through additional capacity. CAISO has also approved a phase shifting transformer flow controller installation at the Imperial Valley Substation. More recently, there are two projects under development in San Jose with flow controls.
GRIP Program – Specifically, as part of the Bipartisan Infrastructure Law, the Grid Resilience and Innovation Partnerships (GRIP) Program at the Department of Energy (DOE) program provides up to $10.5 billion in funding for projects to improve the reliability and resilience of the electric grid. In October 2023, DOE announced $3.5 billion for projects including those that incorporate GETs.
According to the Author
According to the author, "CAISO estimates 7,000 megawatts of new transmission capacity is needed each year for the next decade, but California is nowhere near achieving it. Two new studies demonstrate that reconductoring and GETs can nearly double grid capacity in a cost effective manner. To add transmission capacity in a cost effective and timely way, California must advance reconductoring and grid-enhancing technologies to modernize the grid and meet clean energy goals. We simply cannot rely on the grid of our grandparents to power our grandchildren's future."
Arguments in Support
This legislation is supported by various environmental, solar, wind and labor groups among others. They contend that GETs can maximize existing grid infrastructure and alleviate existing transmission constraints, as well as future constraints from expected shifts in power supply and demand. As such, they assert," the state must quickly make use of all available tools and technologies if it is to meet its ambitious goals and successfully transition to a sustainable energy system."
Arguments in Opposition
None on file.
FISCAL COMMENTS
According to the Assembly Appropriations Committee, there will be minor state costs, if any, as this bill makes no requirements of a state agency, and does not indirectly result in a state agency taking on additional workload.
VOTES
SENATE FLOOR: 39-0-1
YES: Allen, Alvarado-Gil, Archuleta, Ashby, Atkins, Becker, Blakespear, Bradford, Caballero, Cortese, Dahle, Dodd, Durazo, Eggman, Glazer, Gonzalez, Grove, Hurtado, Jones, Laird, Limón, McGuire, Menjivar, Newman, Nguyen, Niello, Ochoa Bogh, Padilla, Portantino, Roth, Rubio, Seyarto, Skinner, Smallwood-Cuevas, Stern, Umberg, Wahab, Wiener, Wilk
ABS, ABST OR NV: Min
ASM UTILITIES AND ENERGY: 16-0-0
YES: Petrie-Norris, Jim Patterson, Bauer-Kahan, Boerner, Calderon, Chen, Friedman, Hart, Holden, Joe Patterson, Reyes, Santiago, Ting, Wallis, Wood, Zbur
ASM APPROPRIATIONS: 14-0-1
YES: Wicks, Sanchez, Arambula, Bryan, Calderon, Wendy Carrillo, Dixon, Mike Fong, Grayson, Haney, Hart, Jim Patterson, Pellerin, Ta
ABS, ABST OR NV: Villapudua
UPDATED
VERSION: June 24, 2024
CONSULTANT: Lina V. Malova / U. & E. / (916) 319-2083 FN: 0003807
Date of Hearing: August 7, 2024
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Buffy Wicks, Chair
SBPCA Bill Id:SB 1006
Author:(Padilla) – As Amended Ver:June 24, 2024
Policy Committee: | Utilities and Energy | Vote: | 16 - 0 |
|
| ||
|
|
Urgency: No State Mandated Local Program: Yes Reimbursable: No
SUMMARY:
This bill requires each “transmission utility” to periodically study (a) the feasibility of using “grid-enhancing technologies” (GETs) and (b) the potential to reconductor its transmission lines with advanced conductors, and to provide the results of the studies to the California Independent System Operator (CAISO) for review and, possibly, inclusion in CAISO’s transmission planning studies and analyses.
Specifically, this bill:
- Requires each transmission utility—meaning an investor-owned electrical utility (IOU) that is a participating owner of transmission infrastructure, the control of which has been turned over to CAISO—to prepare a study, before January 1, 2026, and every two years thereafter, of the feasibility of projects using GETs—meaning hardware and software that increases the capacity of electrical lines and improves the efficiency, reliability, and safety of the grid—to achieve specified goals, generally including increased efficiency, capacity, connectivity to renewable and zero-carbon resources, operationalization or safety, among other goals. The utility is to provide information on feasibility, cost, rating, implementation time, and any other necessary information to CAISO and to request CAISO (a) review the results of the study for economic, reliability and policy goals and (b) include GETs in all transmission planning studies and analyses.
- Requires each transmission utility to prepare a study, before January 1, 2026, and every four years thereafter, of which of its transmission lines can be reconductored with advanced conductors to achieve one or more specified goals, generally including increased efficiency, capacity, connectivity to renewable and zero-carbon resources, operationalization or safety, among other goals. The transmission utility is to provide information on feasibility, cost, rating, implementation time and any other necessary information to CAISO and to request CAISO (a) review the results of the study for economic, reliability and policy goals and (b) include reconductoring with advanced technologies in all transmission planning studies and analyses.
- Provides a transmission utility is to make the studies public upon submission to CAISO.
- Directs an IOU that operates a distribution system to consider GETs and reconductoring with advanced conductors as part of its annual distribution planning process.
FISCAL EFFECT:
Minor state costs, if any, as this bill make no requirements of a state agency, and does not indirectly result in a state agency taking on additional workload.
COMMENTS:
California will need a massive expansion of its electricity transmission and distribution systems to enable the state to meet its clean energy goals. This expansion will cost in the tens of billions of dollars and occur over decades.
Yet, much of the state’s electric wires are old and less efficient at moving electricity that they could be. The term “GETs” describes a broad range of technologies that can increase the efficiency of these wires. As described by the U.S. Department of Energy:
Grid-enhancing technologies (GETs) maximize the transmission of electricity across the existing system through a family of technologies that include sensors, power flow control devices, and analytical tools. This report establishes an assessment methodology and outlines key findings with respect to an identified case study region on how GETs can be applied today to save ratepayers money while the grid transitions to a cleaner generation mix. (“Grid-Enhancing Technologies: as case study on ratepayer impacts,” February 2022.)
Similarly, “reconductoring” refers to replacing existing electrical wires with wires made of alternative materials that are more efficient at moving electricity than the existing wires.
The California Public Utilities Commission and CAISO report being generally supportive of the use of GETs and reconductoring, and federal money is available to help California pay for their deployment.
Analysis Prepared by: Jay Dickenson / APPR. / (916) 319-2081
Date of Hearing: June 19, 2024
ASSEMBLY COMMITTEE ON UTILITIES AND ENERGY
Cottie Petrie-Norris, Chair
SBPCA Bill Id:SB 1006
Author:(Padilla) – As Amended Ver:May 29, 2024
SENATE VOTE: 39-0
SUBJECT: Electricity: transmission capacity: reconductoring and grid-enhancing technologies
SUMMARY: Requires transmission utilities to jointly prepare a grid-enhancing technologies (GETs) strategic plan that is designed to cost-effectively increase transmission capacity to support the connection of new renewable energy and zero-carbon resources, as well as for each transmission utility to evaluate reconductoring of its transmission and distribution lines, as specified.
Specifically, this bill:
- Requires each transmission utility, as defined, on or before January 1, 2026, and at least every 4 years thereafter, to complete an evaluation of which of its transmission and distribution lines can be reconductored with advanced conductors in a cost-effective manner to increase transmission or distribution capacity to support the connection of new renewable energy and zero-carbon resources.
- Requires the transmission utilities to submit a GETs strategic plan and evaluation to the California Public Utilities Commission (CPUC) and to make the plan and evaluation publicly available.
- Requires the plan and evaluation to include a timeline for implementation, as specified.
- Requires each transmission utility to report the progress in implementing the plan in its integrated resource plan.
EXISTING LAW:
- Vests the CPUC with jurisdiction over public utilities, including electrical corporations. (Article XII of the California Constitution)
- Requires the CPUC to consider in its Certificate of Public Convenience and Necessity review cost-effective alternatives to a transmission facility, including targeted energy efficiency, ultraclean distributed generation, and other demand reduction resources. (Public Utilities Code § 1002.3)
- Prohibits an electrical corporation from beginning the construction of a line, plant, system, or any extension without having first obtained from the CPUC a certificate that the present or future public convenience and necessity require or will require its construction. (Public Utilities Code § 1001(a))
- Provides that the extension, expansion, upgrade, or other modification of an existing electrical transmission facility, including transmission lines and substations, does not require a certificate that the present or future public convenience and necessity requires or will require its construction. (Public Utilities Code § 1001(b))
- Requires the CPUC, by January 1, 2024, to update General Order (GO)131-D to authorize each public utility electrical corporation to use the permit-to-construct process or claim an exemption under Section III(B) of that general order to seek approval to construct an extension, expansion, upgrade, or other modification to its existing electrical transmission facilities, including electric transmission lines and substations within existing transmission easements, rights of way, or franchise agreements, irrespective of whether the electrical transmission facility is above a 200-kilovolt voltage (kV) level. (Public Utilities Code § 564)
- Establishes the policy (100% Clean Energy Policy, or SB 100 Policy) of the state that eligible renewable energy resources and zero-carbon resources supply 90% of all retail sales of electricity to California end-use customers by December 31, 2035, 95% of all retail sales of electricity to California end-use customers by December 31, 2040, 100% of all retail sales of electricity to California end-use customers by December 31, 2045, and 100% of electricity procured to serve all state agencies by December 31, 2035. (Public Utilities Code § 454.53)
- Establishes the California Independent System Operator (CAISO) as a nonprofit public benefit corporation and requires the CAISO to ensure efficient use and reliable operation of the electrical transmission grid consistent with achieving planning and operating reserve criteria. (Public Utilities Code § 345.5)
FISCAL EFFECT: According to the Senate Appropriations Committee, the CPUC estimates ongoing costs of approximately $255,000 annually in ratepayer funds to make recommendations based on its evaluation of the strategic plans and evaluations submitted as this bill provides. The CPUC would need to request the CAISO consider the results of the strategic plans and each evaluation as part of its transmission planning process (TPP). According to CPUC, this would require additional analysis – a highly technical engineering review – of those reports and additional coordination with the CAISO to make recommendations as part of its TPP transmittals.
BACKGROUND:
Integrated Resource Planning (IRP) Framework – CPUC – To achieve procurement targets for the Renewables Portfolio Standard and statewide emission reduction policies, the CPUC, has adopted an Integrated Resource Plan (IRP) planning process that runs on a two-year cycle. In this process, the CPUC oversees long-term procurement for its regulated load-serving entities (electrical corporations, community choice aggregators, and electric service providers), which serve approximately 75% of the state.[1] The first year of the IRP cycle develops the Reference System Plan by evaluating the appropriate greenhouse gas (GHG) emission planning goal for the electric sector and load-serving entities (LSEs), and identifies the optimal mix of electricity resources to meet state GHG emissions and reliability goals in a cost-effective manner. Simply put, the Reference System Plan produces an estimate of what LSEs should be procuring. The second year of the IRP cycle develops the Preferred System Plan by aggregating the generation resources proposed by LSEs into a single system-wide portfolio to meet the state’s GHG emissions and reliability goals cost-effectively. The Preferred System Plan that is produced by the IRP process is the basis for a number of additional planning processes, including the TPP by the CAISO.
In February 2024, the CPUC adopted its latest Preferred System Plan by setting a statewide 25 million metric ton (MMT) GHG goal for the electric sector by 2035.[2] The decision represents the most aggressive end of the range identified by CARB, and has identified 56 gigawatts (GW) of new clean resources needed by 2035. Delivering on these ambitious targets will require corresponding new transmission build outs and upgrades.
Transmission Planning Process (TPP) – Each year, the CAISO conducts its TPP to identify potential system limitations as well as transmission projects in need of upgrades or new transmission infrastructure in need of construction to improve reliability and efficiency.[3] The TPP fulfills the CAISO’s core responsibility to identify and develop solutions to meet the future needs of the electricity grid. The TPP relies on the CPUC’s IRP to identify the optimal mix of system-wide resources. CAISO receives the IRP results as inputs into its TPP.
California’s Transmission Delays – In April 2024, CAISO issued its Draft 2023-2024 Transmission Plan targeting a goal of 85 GW of new clean generating capacity by 2035 reflecting the state’s goals and load growth including the potential for increased electrification. The plan also identifies 26 new projects, including the first wave of transmission infrastructure needed to deliver clean North Coast wind energy to the CAISO grid. As demonstrated earlier, the state’s transmission system must expand to match the unprecedented build out of renewables. However, California’s transmission development process can be lengthy and complicated taking over a decade from concept to construction.
GETs – According to the U.S. Department of Energy (DOE), an estimated 70% of transmission and distribution lines in the U.S. are well into the second half of their 50-year life expectancy.[4] As transmission lines age, they become more inefficient, increasing the likelihood of congested power lines, which can force operators to reroute power through less optimal paths and rely on more expensive or less clean power generation.[5] Extreme cases of transmission constraints may even overload transmission systems, forcing utilities to employ periodic load shedding tactics (i.e., rolling blackouts).
To facilitate the clean energy transition, GETs have been posed by researchers and industry leaders as an interim, cost-effective solution to unlock transmission capacity in the near term and buy time for long-term transmission planning. GETs encompass a suite of technologies – such as advanced conductors,[6] dynamic line ratings,[7] advanced power flow control devices,[8] and analytical tools – that can be used to maximize the transmission of electricity across existing lines. According to the Federal Energy Regulatory Commission (FERC), GETs can cost less than 10% of the cost of investing in new transmission lines, and can save millions in annual congestion costs.[9] As a result, FERC has recently taken steps to push for consideration and adoption of GETs, through incentive programs supported by the federal Bipartisan Infrastructure Law.[10]
GETs Deployment in California – According to the 2023- 2024 Transmission Plan, CAISO supports the deployment of GETs, and has considered them on a case by case basis in past annual transmission planning processes.[11] For instance, advanced conductors and power flow controllers are considered as planning tools and provide alternatives to capital expenditures. Dynamic thermal line ratings, and topology optimizations provide operational benefits through additional capacity. Southern California Edison (SCE) has deployed more than two dozen reconductoring projects, including the Big Creek-Ventura 220kV network. In addition, CAISO approved a phase shifting transformer flow controller installation at the Imperial Valley Substation. More recently, there are two projects under development in San Jose with flow controls.
Recent FERC Orders – Relatively recent orders issued by FERC also reflect the importance that the agency ascribes to GETs in achieving US renewable energy goals—and that their use is required to ensure just and reasonable rates for ratepayers:
- In May 2023, FERC Order issued Order 2023 requiring transmission owners to incorporate specific alternative transmission technologies into the interconnection study process. According to FERC, these technologies “can provide substantial benefits to optimize the transmission system in specific scenarios because they can be deployed both more quickly and at lower costs.”[12]
- In May 2024, FERC issued Order 1920 with requirements addressing how transmission providers must conduct long-term planning for regional transmission facilities. Specifically, the order requires transmission providers in each transmission planning region to consider dynamic line ratings, advanced power flow control devices, advanced conductors, and transmission switching in their long-term regional transmission planning processes. The requirement refers to both new facilities and upgrades for existing facilities.
Federal-State Modern Grid Deployment Initiative – In May 2024, the Biden-Harris Administration launched the Federal-State Modern Grid Deployment Initiative (“the Initiative”) to accelerate improvements to the transmission and distribution system, to support the country’s objectives for affordable, clean, and reliable power.[13] Twenty-one states including California, Arizona, Kentucky, New York, Massachusetts, and Washington committed to the following initiative among others:
- Facilitate pathways to spur adoption of high-performance conductors and GETs;
- Maximize the use of available Federal financial and technical assistance;
- Share successes, challenges, lessons learned, and best practices with other states.
The Federal government has committed to various initiatives including providing technical assistance support and ensuring states have access to financial assistance resources. However, the Federal government and the states mutually also recognize that there will not be a “one-size-fits-all” approach to maximizing the opportunities and overcoming the challenges each state may be facing with grid technology deployment.[14]
GRIP Program. The Grid Resilience and Innovation Partnerships (GRIP) Program is a Department of Energy (DOE) program under the 2021 Bipartisan Infrastructure Law that provides up to $10.5 billion in funding for projects to improve the reliability and resilience of the electric grid. In October 2023, DOE announced $ 3.5 billion for projects including those that incorporate GETs.[15]
COMMENTS:
- Author’s Statement. According to the author, “CAISO estimates 7,000 megawatts of new transmission capacity is needed each year for the next decade, but California is nowhere near achieving it. Two new studies demonstrate that reconductoring and GETs can nearly double grid capacity in a cost effective manner. To add transmission capacity in a cost effective and timely way, California must advance reconductoring and grid-enhancing technologies to modernize the grid and meet clean energy goals. We simply cannot rely on the grid of our grandparents to power our grandchildren’s future.”
- Complimentary Solutions. California has established ambitious clean energy and climate change goals. Energy planners are increasingly looking for opportunities to meet these goals, while facing a myriad of challenges arising from projected growth on the demand-side, line congestion, interconnection delays, siting and permitting, reliability risks due to extreme weather and climate events. All these challenges intersect with transmission capacity. While progress has been made to address challenges, complimentary solutions like GETs can rapidly and affordably be deployed to improve transmission capacity, performance, and resilience.
The author and supporters of the bill contend that GETs are under-deployed in the U.S as compared to other regions like Europe. As such, transmission owners may need guidance, as provided by this bill that encourages them to take proactive steps to incorporate GETs into their system planning and operations.
- Definitions. This bill defines, “grid-enhancing technologies” to mean hardware and software that dynamically increase the capacity of electrical lines and improve the efficiency, reliability, and safety of the grid.” According to the Department of Energy, a formal definition of GETs is yet to be adopted.[16] Similarly, no formal definition exists for reconductoring with advanced conductors, which this bill also defines. It is unclear whether the definitions provided in this measure may be too prescriptive or may require further modification as technology and innovation evolves in this field to incorporate new technologies, and new industry perspectives.
- Strategic Plan vs. Feasibility Study. This bill requires transmission utilities to jointly prepare a GETs strategic plan that is designed to cost-effectively increase transmission capacity to support the integration of clean energy resources. However, application of GETs depends on specific local/regional needs, resource availability, and cost/benefit considerations and there's no "one-size-fits-all" solution. As such, requiring transmission utilities to develop a strategic plan for GETs may be challenging. Instead, the author and committee recommend amending the bill such that each transmission utility prepare a study of the feasibility of projects using grid-enhancing technologies, and a study of which transmission lines can be reconductored with advanced conductors. The author and committee also recommend changing the involvement of the CAISO in the studies in the bill, from having them participate directly in the evaluations to having the utility request CAISO review the studies.
- Integrated Resource Plan Vs Transmission Planning Process. As eluded earlier, the IRP is a biennial process developed to implement California’s clean energy policies. In this process, the CPUC examines a utility’s current and planned electricity generation to ensure that California’s electric sector meets its GHG reduction goals while maintaining reliability at the lowest possible costs. Whereas, the CAISO’s TPP involves systematically assessing current and future transmission needs to improve reliability, decarbonization goals and efficiency. This bill requires transmission utilities, upon completion of the GETs strategic plan to submit the plan to the CPUC as part of the IRP. Given the IRP process focuses on generation and procurement of energy resources, not optimizing transmission and distribution infrastructure, the author and committee recommends striking language of the bill relating to the IRP and rather submit their findings to the CAISO and have them considered in the TPP.
- Clarification for Studies - Transmission Line Vs Distribution Line. Transmission lines are connected to substations that "step-down" the power to a lower-voltage so that it can be delivered to customers through distribution lines, although some large industrial customers receive their electricity at transmission or sub-transmission voltage. The distinction in voltage level between the transmission and distribution grid differ across the utilities, and are set at the discretion of the utility. Nevertheless, the transmission system carries the electric energy at relatively high voltages, usually above 69 kilovolts (kV).[17] As illustrated in the background, GETs, are hardware and software that are mainly and currently deployed to increase the capacity, efficiency and resiliency of the current transmission system. As such, the author and committee recommend narrowing the study of the implementation of conductors to only transmission lines and not both transmission lines and distribution lines.
- Recent Actions. As previously discussed, in May 2024, FERC issued Order 1920 which requires transmission providers in each transmission planning region to consider specific GETs – dynamic line ratings, advanced power flow control devices, advanced conductors, and transmission switching – in their long-term regional transmission planning processes. FERC declined to require consideration of topology optimization because it is technically much more challenging to implement. This bill, however, defines GETs inclusive of topology optimization software. Given this difference, it is unclear how the GETs strategic plans, as put forward under this bill, would interact with these federal policies.
Related Legislation
SB 1165 (Padilla) authorizes an electrical corporation that applies to the CPUC to authorize construction of a high voltage electrical transmission line, rated at 138kV or greater, to apply to the CEC for certification of the facility pursuant to the CEQA, instead of the CPUC conducting the CEQA review. This bill provides that the CEC certification authorizes the project to be eligible for the CEQA judicial streamlining afforded to Environmental Leadership Development Projects and the CEC’s “Opt-in” permitting process. Status: Held in Senate Committee on Appropriations
AB 2779 (Petrie-Norris) would require the CAISO, upon approval of each transmission plan, to report to the CPUC and the Legislature any new use of grid-enhancing technology in the plan and the associated cost or efficiency savings of that deployment. Status: pending hearing in the Assembly Committee on Utilities and Energy. Status: pending hearing in the Senate Committee on Energy, Utilities, and Communications.
AB 2292 (Petrie-Norris) repeals the requirement that the California Public Utilities Commission (CPUC) should consider alternatives to prospective transmission projects before issuing an approval. Repealing this requirement will remove a duplicative process that currently slows down transmission development in the state. Status: pending referral in the Senate Committee on Rules.
AB 3246 (Garcia) would require by January 1, 2026, the CPUC to update General Order 131-D to provide an electrical corporation with an exemption from the requirement to receive a Permit to Construct (PTC) and instead authorize the approval of advanced reconductoring of transmission projects through the informal Tier 2 advice letter process, regardless of whether the voltage of the facility being modified exceeds 200 kilovolts (kV). Status: pending hearing in the Senate Committee on Energy, Utilities, and Communications.
AB 3238 (Garcia) among other requirements, exempts projects that would require a certificate of public necessity and convenience (CPCN) from the California Public Utilities Commission (CPUC) and any other electrical infrastructure projects, as defined, from existing requirements to compare prospective projects with cost-effective alternatives such as energy efficiency, distributed generation, and demand response resources. Status: pending hearing in the Senate Committee on Energy, Utilities, and Communications.
Prior Legislation
SB 619 (Padilla, 2023) would have authorized an electrical corporation that applies to the CPUC to authorize construction of a high voltage electrical transmission line, rated at 138 kV or greater, to apply to the CEC for certification of the facility pursuant to the CEQA, instead of the CPUC conducting the CEQA review. The bill provides that the CEC certification authorizes the project to be eligible for the CEQA judicial streamlining afforded to Environmental Leadership Development Projects (ELDPs) and the CEC’s “Opt-in” permitting process. Status: The bill was vetoed by the Governor.
SB 420 (Becker, 2023) would have exempted construction of certain low-voltage electrical lines and associated equipment from the need to receive a discretionary permit from the CPUC. Status: The bill was vetoed by the Governor.
SB 149 (Caballero) among its provisions, revised the procedures regarding CEQA administrative records and expedited administrative and judicial review procedures for ELDPs for specified projects, including transmission projects, that required the courts to resolve CEQA litigation within 270 days to the extent feasible and extends the ELDP sunset to January 1, 2034. Status: Chapter 60, Statutes of 2023.
SB 319 (McGuire) required the CEC and the CPUC, in coordination with the CAISO, to better and regularly coordinate planning and permitting of energy transmission infrastructure to ensure the state meets its clean energy goals and to evaluate and report on that planning and related infrastructure development. The bill also required these state energy agencies to jointly develop an electrical transmission infrastructure development guidebook. Status: Chapter 390, Statutes of 2023.
SB 529 (Hertzberg) exempted an extension, expansion, upgrade, or other modification of an existing transmission line or substations from the requirement of a CPCN and directed the CPUC to revise its GO, by January 1, 2024, to instead use its permit to construct process for these approvals. Status: Chapter 357, Statutes of 2022.
SB 887 (Becker) requires 15-year projections of energy resource portfolios and energy demand to inform transmission planning to achieve the state’s clean energy goals, and requires the CAISO to consider approval for specified transmission projects as part of the 2022-23 transmission planning process. Status: Chapter 358, Statutes of 2022.
AB 205 (Committee on Budget) allowed certain energy projects, including electric transmission lines between certain non-fossil fuel energy generation facilities to become certified leadership projects under the Jobs and Economic Improvement Through Environmental Leadership Act of 2021 through a certification process through the CEC. With this certification, actions or proceedings related to the certification of an environmental impact report need to be resolved within 270 days to the extent feasible. Status: Chapter 21, Statutes of 2022.
REGISTERED SUPPORT / OPPOSITION:
Support
Advanced Energy United
California Energy Storage Alliance
California Farm Bureau Federation
California State Association of Electrical Workers
California Wind Energy Association
Center for Energy Efficiency and Renewable Technologies
Clean Power Campaign
Climate Reality San Francisco Bay Area Chapter
Environment California
Environmental Defense Fund
Environmental Protection Information Center
Independent Energy Producers Association
Junior Philanthropists Foundation
Large-scale Solar Association
Los Angeles Business Council
Natural Resources Defense Council (NRDC)
San Diego Community Power
Sierra Club of California
Solano County Democratic Central Committee
Solar Energy Industries Association
Sonoma Clean Power
The California Wind Energy Association (CALWEA)
Union of Concerned Scientists
Watt Coalition
Opposition
None on file.
Analysis Prepared by: Lina V. Malova / U. & E. / (916) 319-2083
Public Utilities Code § 454.51-454.53 ↑
Proposed Decision issued 2/15/2021 in IRP Proceeding, Rulemaking 20-05-003 ↑
There are other transmission planning efforts, including local capacity requirements, special studies, interregional transmission project, and others that are not mentioned here for sake of clarity. ↑
DOE; “What does it take to modernize the U.S. electric grid?”; https://www.energy.gov/gdo/articles/what-does-it-take-modernize-us-electric-grid; October 2023. ↑
DOE; Grid-Enhancing Technologies: A Case Study on Ratepayer Impact; February 2022. ↑
Advanced conductors enable higher operating temperatures, higher capacity for electrical current, and reduced line sag. ↑
Dynamic line ratings adjust thermal line ratings based on actual weather conditions, including ambient air temperature and wind speed/direction. ↑
Advanced power-flow control devices swiftly control the impedance, or opposition to current, in real time to ensure that power is delivered on lines that have the capacity to carry it. ↑
Utility Dive; “Regulators need to require utilities to use grid-enhancing technologies: FERC’s Clements”; https://www.utilitydive.com/news/transmission-grid-enhancing-technologies-gets-utilities-naruc-ferc-clements/699686/; November 2023. ↑
DOE; “Grid Resilience and Innovation Partnerships (GRIP) Program”; https://www.energy.gov/gdo/grid-resilience-and-innovation-partnerships-grip-program. ↑
California ISO; PG 24, “2023-2024 Transmission Plan”; May 23, 2024 ↑
FERC. Docket No. RM22-14-000; Order No. 2023 (July 2023). ↑
The White House; Pg. 3, “Federal-State Modern Grid Deployment Initiative.” May 2024 ↑
The White House; Pg. 5, “Federal-State Modern Grid Deployment Initiative.” May 2024 ↑
DOE, “Biden-Harris Administration Announces $3.5 Billion for Largest Ever Investment in America’s Electric Grid, Deploying More Clean Energy, Lowering Costs, and Creating Union Jobs;” https://www.energy.gov/articles/biden-harris-administration-announces-35-billion-largest-ever-investment-americas-electric ↑
Department of Energy; Pg. 4, “Grid-Enhancing Technologies”; February 2022 ↑
Though this is not a hard-and-fast rule, some utilities designate circuits >60kV “transmission.” >69kV is NERC’s definition, as provided by the U.S. Energy Information Administration glossary of terms. https://www.eia.gov/tools/glossary/index.php?id=T ↑
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 1006 |
THIRD READING
Bill No: SB 1006
Author: Padilla (D)
Amended: 4/17/24
Vote: 21
SENATE ENERGY, U. & C. COMMITTEE: 18-0, 4/16/24
AYES: Bradford, Dahle, Ashby, Becker, Caballero, Dodd, Durazo, Eggman, Gonzalez, Grove, Limón, Min, Newman, Rubio, Seyarto, Skinner, Stern, Wilk
SENATE APPROPRIATIONS COMMITTEE: 7-0, 5/16/24
AYES: Caballero, Jones, Ashby, Becker, Bradford, Seyarto, Wahab
SUBJECT: Electricity: transmission capacity: reconductoring and grid-enhancing technologies
SOURCE: Author
DIGEST:
This bill requires electrical transmission utilities, by January 1, 2026, to develop a strategic plan for grid-enhancing technologies to cost-effectively increase transmission capacity and to complete an evaluation to identify which of its transmission and distribution lines can be reconductored with advanced reconductors. Requires these plans and evaluations are submitted to the California Public Utilities Commission (CPUC) and made publicly available.
ANALYSIS:
Existing law:
- Establishes and vests the CPUC with jurisdiction over public utilities, including electrical corporations. (Article XII of the California Constitution)
- Establishes the policy of the state that eligible renewable energy resources and zero-carbon resources supply 90 percent of all retail sales of electricity to California end-use customers by December 31, 2035, 95 percent of all retail sales of electricity to California end-use customers by December 31, 2040, 100 percent of all retail sales of electricity to California end-use customers by December 31, 2045, and 100 percent of electricity procured to serve all state agencies by December 31, 2035. (Public Utilities Code §454.53)
- Provides that the CPUC may supervise and regulate every public utility in the state and may do all things, whether specifically designated or in addition, which are necessary and convenient in the exercise of such power and jurisdiction. (Public Utilities Code §701)
- Prohibits an electrical corporation from beginning the construction of a line, plant, or system, or of any extension thereof, without having first obtained from the CPUC a certificate that the present or future public convenience and necessity require or will require its construction. Provides that the extension, expansion, upgrade, or other modification of an existing electrical transmission facility, including transmission lines and substations, does not require a certificate that the present or future public convenience and necessity requires or will require its construction. (Public Utilities Code §1001)
This bill:
- Makes several findings and declarations regarding the potential of grid-enhancing technologies and advanced conductors to quickly and cost-effectively increase transmission capacity.
- Requires transmission utilities, defined as electrical corporations that are participating transmission owners, on or before January 1, 2026, to jointly prepare a grid-enhancing technologies strategic plan that is designed to cost-effectively increase transmission capacity and increase capacity to connect new renewable energy and zero-carbon resources, reduce transmission system congestion, reduce curtailment of renewable and zero-carbon resources, increase reliability, and reduce the risk of igniting wildfires.
- Requires each transmission utility, on or before January 1, 2026, and at least every four years thereafter, to complete an evaluation of which of its transmission and distribution lines can be reconductored with advanced conductors in a cost-effective manner to, among other things, increase transmission or distribution capacity and increase capacity to connect new renewable energy and zero-carbon resources.
- Requires, upon completion of the plan and the evaluation, the transmission utilities to submit the plan and evaluation to the CPUC and to make the plan and evaluation publicly available.
- Requires the plan and evaluation to include a timeline for implementation. Requires transmission utilities to report on their progress in implementing the plan as part of each subsequent integrated resources plan. Requires the evaluation to include a plan for proposing to the California Independent System Operator (CAISO) projects for approval where that approval is required.
Background
- Transmission projects. Electric transmission lines are generally high voltage lines that move electricity from generation resources (power plants) to distribution lines in neighborhoods. Companies, usually electric investor-owned utilities (IOUs), proposing the construction of new transmission, are required to obtain a permit from the CPUC for construction of specified infrastructure listed under Public Utilities Code §1001, including transmission projects.
- Need for expanded transmission capacity. In order for the state to meet its clean energy goals, including achieving 100 percent clean energy by 2045, electric transmission capacity will likely need to grow significantly. The CAISO conducts its annual transmission planning process to identify potential transmission system limitations and opportunities for system reinforcements that improve reliability and efficiency. The CAISO identifies projects that address grid reliability requirements, identify upgrades needed to successfully meet California’s policy goals, and explore projects that can bring economic benefits to consumers. In 2021, the CAISO created a 20-Year Transmission Outlook for the electric grid, in collaboration with the CPUC and the California Energy Commission (CEC), with the goal of exploring the longer-term grid requirements and options for meeting the state’s SB 100 clean energy goals reliably and cost-effectively. The 20-Year Transmission Outlook estimates a significant amount, and expense, to construct and expand transmission facilities, including an estimated $10.74 billion in upgrades to existing facilities.
- Grid-enhancing technologies (GETs). GETs, generally, are a combination of hardware and software that can increase transmission capacity, decrease congestion, and improve reliability on transmission lines. An April 2023 Brattle Group white paper, Building a Better Grid: How Grid-enhancing Technologies Complement Transmission Buildouts, discusses how GETs can help improve transmission capacity and efficiency. The paper notes that transmission transfer capability depends on where and how new transmission lines are connected to the rest of the electrical grid system – the topology of the transmission network (including the points of injection and withdrawal of energy). Both the transfer capability of lines (and other components of the grid) and network topology determine how, where, and the quantity of the power flows. Many GETs are built on either of two applications to increase transfer capability: one that explores enhanced and flexible application of the pre-determined transfer capability, and the other that focuses on flexible and dynamic control of transmission systems. Examples of GETs include dynamic line ratings, advanced power flow controls, and advanced topology control. Dynamic line ratings (DLRs) try to better address individual line transfer capability based on actual conditions. Advanced power flow controls (generally hardware) and advanced topology control (generally software) direct electricity away from overloaded lines and onto underutilized lines, such as by opening or closing circuit breakers. As noted in the Brattle Group paper: The comparative advantages of GETs include their portability and scalability, speed to deploy, and lower costs. Importantly, per the report, “GETs rarely replace transmission, rather, they enhance transmission…”
- Advanced reconductoring. Reconductoring is the replacement of a transmission line’s existing conductors with advanced conductors, essentially swapping out the Aluminum Conductor Steel Reinforced (ACSR) for a smaller composite core conductors that enable higher operating temperatures. According to a November 2023 Energy Institute at Haas paper, “Accelerating Transmission Expansion by Using Advanced Conductors in Existing Right-of-Way” by Emilia Chojkiewicz, et al. (Energy Institute WP 343), reconductoring holds significant potential for rapid transmission expansion. The advanced conductors can carry approximately twice as much power as conventional conductors. Advanced conductors use existing transmission towers and rights of way, thereby circumventing the land acquisition and permitting processes that can impede construction of new transmission lines. However, replacing conventional conductors with advanced conductors requires taking circuits out of service during the replacement or conducting live-line work, which carries additional risks. Either approach can be challenging, and in some cases infeasible, when transmission constraints exist.
Comments
- Need for this bill. Supporters of this bill note the need for the state to upgrade and expand its electric transmission infrastructure to meet its clean energy goals. They contend the increasing demand placed on California’s electric grid as more vehicles and homes are powered by electricity. They express concerns that the transmission grid is not keeping pace with demand, as transmission lines can take more than a decade to site, permit, and build. They point to the opportunities with GETs and advanced conductors to help the state “enhance the existing transmission infrastructure to its maximum potential and make it more efficient, resilient, and cost-effective.”
- Current use of GETs and advanced conductors. The two papers noted above, along with others, comment on the more prevalent use of GETs and advanced conductors in other countries, particularly in Europe and India. These papers generally state that the use of these technologies has not been as quickly embraced in the United States. In California, advanced conductors have been deployed, particularly by Southern California Edison (SCE) who has more than two dozen reconductoring projects, including the Big Creek-Ventura 220kV network. Additionally, the CAISO shared that they have considered GETs in the annual transmission planning process for many years. Specifically, the CAISO contends they typically consider advanced conductors and power flow controllers as planning tools providing alternatives to capital expenditures, as well as, dynamic thermal line ratings, and topology optimizations to access operational benefits through additional capacity. In addition to the Big Creek-Ventura line, the CAISO approved a phase shifting transformer flow controller installation at the Imperial Valley Substation. More recently, there are two projects under development in San Jose with flow controls.
- Federal requirements just adopted to require use of GETs and advanced conductors. At the federal level, the Federal Energy Regulatory Commission (FERC) just adopted (May 13, 2024) a transmission and cost allocation rule, Order No. 1920, “Building for the Future Through Electric Regional Transmission Planning and Cost Allocation and Generator Interconnection” (RM21-17-000) which among its provisions requires public utility transmission providers to more fully consider the use of GETs, such as dynamic line ratings, advanced power flow control devices, advanced conductors and transmission switching, in their transmission planning. The CPUC has also shared that they, along with the CEC, CAISO, Pacific Gas & Electric, SCE, and Energy Institute at Haas are currently pursuing a Department of Energy GRIP grant (eight years long) to deploy advanced conductors and two other GETs technologies: dynamic line rating and real-time short circuit duty monitoring.
- Impacts to ratepayers. The actual savings benefits for the use of GETs and advanced conductors will vary by transmission line. Both the Brattle Group and Energy Institute papers cite opportunities for savings from the use of GETs and advanced conductors. With regards to GETs, these technologies can be deployed on existing transmission lines to enhance efficiency, with the potential to reduce congestion by 40 percent. Such level of efficiency can provide savings to ratepayers in the form of reducing the need to build additional transmission lines which can be very costly. Advanced conductors have a higher up-front cost as compared to conventional aluminum conductors – roughly two to three times the costs – though they have the potential for long-term savings given the potential to double the capacity of conventional conductors. As stated in the Energy Institute paper, “Transmission networks are complex, and the actual increase in power transfer capacity offered by reconductoring is determined by a multitude of factors beyond the scope of this analysis. We recommend that transmission owners, ISOs, and RTOs perform more detailed studies…to evaluate the wide-scale deployment of advanced conductors in their networks.”
- Is a strategic plan and evaluation necessary? This bill proposes to require electrical corporations who have turned over operation of their transmission to the CAISO to prepare a strategic plan for GETs and an evaluation of the use of advanced conductors. Given the need for increased transmission capacity, the desire to explore opportunities with GETs and advanced conductors in order to optimize existing transmission is generally prudent. However, as noted in a recently released Energy Innovation and GridLab report, “Supporting Advanced Conductor Deployment: Barriers and Policy Solutions,” reconductoring is not a panacea, and one may add neither are GETs. As this bill moves forward, the author may wish to consider whether the recent FERC decision to require the consideration of GETs and advanced conductors may necessitate additional changes to the requirements of this bill while advancing the goals of savings for ratepayers.
Related/Prior Legislation
SB 319 (McGuire, Chapter 390, Statutes of 2023) required the CEC and the CPUC, in coordination with the CAISO, to better and regularly coordinate planning and permitting of energy transmission infrastructure to ensure the state meets its clean energy goals and to evaluate and report on that planning and related infrastructure development. The bill also required these state energy agencies to jointly develop an electrical transmission infrastructure development guidebook.
SB 529 (Hertzberg, Chapter 357, Statutes of 2022) exempted an extension, expansion, upgrade, or other modification of an existing transmission line or substations from the requirement of a CPCN and directed the CPUC to revise its GO, by January 1, 2024, to instead use its permit to construct process for these approvals.
SB 887 (Becker, Chapter 358, Statutes of 2022) required 15-year projections of energy resource portfolios and energy demand to inform transmission planning to achieve the state’s clean energy goals, and requires the CAISO to consider approval for specified transmission projects as part of the 2022-23 transmission planning process.
(NOTE: See policy committee analysis for fuller List of related legislation)
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
According to the Senate Appropriations Committee, the CPUC estimates ongoing costs of approximately $255,000 annually (ratepayer funds) to make recommendations based on its evaluation of the strategic plans and evaluations submitted as a result of this bill. The CPUC would need to request the California Independent System Operator (CAISO) consider the results of the strategic plans and each evaluation as part of its transmission planning process (TPP). According to CPUC, this would require additional analysis (a highly technical engineering review) of those reports and additional coordination with the CAISO to make recommendations as part of its TPP transmittals.
SUPPORT: (Verified 5/15/24)
350 Humboldt
Advanced Energy United
California Energy Storage Alliance
California Environmental Voters
California Farm Bureau Federation
California State Association of Electrical Workers
California Wind Energy Association
Center for Energy Efficiency and Renewable Technologies
Ceres
Clean Power Campaign
Citizens' Climate Lobby California
Coalition of California Utility Employees
Environment California
Environment Defense Fund
Fission Transition
Independent Energy Producers Association
Large-scale Solar Association
Natural Resources Defense Council
San Diego Community Power
Solar Energy Industries Association
Union of Concerned Scientists
WATT Coalition
West LA Democratic Club
An individual
OPPOSITION: (Verified 5/15/24)
None received
ARGUMENTS IN SUPPORT: In support of this bill, the Coalition of California Utility Employees and the California State Association of Electrical Workers state:
California must dramatically increase the total capacity of its transmission system to supply the vastly increased demand for electricity needed to meet our carbon neutrality goals. This will certainly require many new transmission lines. But in addition to new lines, new technology can enable us to get much more capacity out of existing transmission lines and transmission corridors, and to get that capacity much more quickly. ,,,Fully evaluating opportunities to deploy GETS and advanced conductors is a no-regrets policy which could yield lower costs for consumers while increasing California’s ability to meet its carbon reduction goals.
Prepared by: Nidia Bautista / E., U. & C. / (916) 651-4107
5/17/24 11:56:23
SENATE COMMITTEE ON
Senator Anna Caballero, Chair
2023 - 2024 Regular Session
SB 1006 (Padilla) - Electricity: transmission capacity: reconductoring and grid-enhancing technologies
Version: | Policy Vote: |
Urgency: | Mandate: |
Hearing Date: | Consultant: |
Bill Summary:
This bill would require transmission utilities to develop a strategic plan for grid-enhancing technologies to cost-effectively increase transmission capacity and to complete an evaluation to identify which of its transmission and distribution lines can be reconductored with advanced reconductors. The bill would require that these plans and evaluations be submitted to the California Public Utilities Commission (CPUC) and made publicly available.
Fiscal Impact:
- The CPUC estimates ongoing costs of approximately $255,000 annually (ratepayer funds) to make recommendations based on its evaluation of the strategic plans and evaluations submitted as a result of this bill. The CPUC would need to request the California Independent System Operator (CAISO) consider the results of the strategic plans and each evaluation as part of its transmission planning process (TPP). According to CPUC, this would require additional analysis (a highly technical engineering review) of those reports and additional coordination with the CAISO to make recommendations as part of its TPP transmittals.
Background:
Transmission projects. Electric transmission lines are generally high voltage lines that move electricity from generation resources (power plants) to distribution lines in neighborhoods. Companies, usually electric investor-owned utilities (IOUs), proposing the construction of new transmission, are required to obtain a permit from the CPUC for construction of certain specified infrastructure listed under Public Utilities Code §1001, including transmission projects. The CPUC reviews permit applications under two concurrent processes: (1) an environmental review pursuant to California Environmental Quality Act (CEQA), and (2) the review of project need and costs pursuant to Public Utilities Code §1001 and GO 131-D (Certificate of Public Convenience and Necessity (CPCN)).
Need for expanded transmission capacity. In order for the state to meet its clean energy goals, including achieving 100 percent clean energy by 2045, electric transmission capacity will likely need to grow significantly. The CAISO conducts its transmission planning process to identify potential transmission system limitations as well as opportunities for system reinforcements that improve reliability and efficiency. The annual transmission plan fulfills the CAISO’s core responsibility to identify and plan the development of solutions, transmission or otherwise, to meet the future needs of the electricity grid. The CAISO identifies projects that address grid reliability requirements, identify upgrades needed to successfully meet California’s policy goals, and explore projects that can bring economic benefits to consumers. In 2021, the CAISO created a 20-Year Transmission Outlook for the electric grid, in collaboration with the CPUC and the California Energy Commission (CEC), with the goal of exploring the longer-term grid requirements and options for meeting the state’s SB 100 clean energy objectives reliably and cost-effectively. The 20-Year Transmission Outlook estimates a significant amount, and expense, to construct and expand transmission facilities, including an estimated $10.74 billion in upgrades to existing facilities.
Grid-enhancing technologies (GETs). GETs, generally, are a combination of hardware and software that can increase transmission capacity, decrease congestion, and improve reliability. An April 2023 Brattle Group white paper, Building a Better Grid: How Grid-enhancing Technologies Complement Transmission Buildouts, discusses how GETs can help improve transmission capacity and efficiency. The paper notes that transmission transfer capability depends on where and how new transmission lines are connected to the rest of the system – the topology of the transmission network (including the points of injection and withdrawal of energy). Both the transfer capability of lines (and other components of the grid) and network topology determine how, where, and the quantity of the power flows. Many GETs are built on either of two applications to increase transfer capability: one that explores enhanced and flexible application of the pre-determined transfer capability; and the other that focuses on flexible and dynamic control of transmission systems. Examples of GETs include dynamic line ratings, advanced power flow controls, and advanced topology control. Dynamic line ratings (DLRs) try to better address individual line transfer capability based on actual conditions. Advanced power flow controls (generally hardware) and advanced topology control (generally software) direct electricity away from overloaded lines and onto underutilized lines, such as by opening or closing circuit breakers. As noted in the Brattle Group paper:
The comparative advantages of GETs include their portability and scalability (i.e., they can be added in phases without committing to a larger project), speed to deploy (i.e., they can be put into service much faster), and lower costs (i.e., they can be deployed often for a small fraction of the cost). GETs rarely replace transmission, rather, they enhance transmission…”
Advanced reconductoring. Reconductoring is the replacement of a transmission line’s existing conductors with advanced conductors, essentially swapping out the Aluminum Conductor Steel Reinforced (ACSR) for a smaller composite core conductors that enable higher operating temperatures. According to a November 2023 Energy Institute at Haas paper, “Accelerating Transmission Expansion by Using Advanced Conductors in Existing Right-of-Way” by Emilia Chojkiewicz, et. al (Energy Institute WP 343), reconductoring holds significant potential for rapid transmission expansion. The advanced conductors can carry approximately twice as much power as conventional conductors. Yet, advanced conductors use existing transmission towers and rights of way, thereby circumventing the land acquisition and permitting processes that can impede construction of new transmission lines. However, replacing conventional conductors with advanced conductors requires taking circuits out of service during the replacement or conducting live-line work, which carries additional risks. Either approach can be challenging, and in some cases infeasible, when transmission constraints exist.
Proposed Law:
This bill would require transmission utilities, by January 1, 2026, to develop a strategic plan for grid-enhancing technologies to cost-effectively increase transmission capacity and to complete an evaluation to identify which of its transmission and distribution lines can be reconductored with advanced reconductors. Specifically, this bill would:
- Make several findings and declarations regarding the potential of grid-enhancing technologies and advanced conductors to quickly and cost-effectively increase transmission capacity.
- Require transmission utilities, defined as electrical corporations that are participating transmission owners, on or before January 1, 2026, to jointly prepare a grid-enhancing technologies strategic plan that is designed to cost-effectively increase transmission capacity and increase capacity to connect new renewable energy and zero-carbon resources, reduce transmission system congestion, reduce curtailment of renewable and zero-carbon resources, increase reliability, and reduce the risk of igniting wildfire, as specified.
- Require each transmission utility, on or before January 1, 2026, and at least every four years thereafter, to complete an evaluation of which of its transmission and distribution lines can be reconductored with advanced conductors in a cost-effective manner to, among other things, increase transmission or distribution capacity and increase capacity to connect new renewable energy and zero-carbon resources.
- Require, upon completion of the plan and the evaluation, the transmission utilities to submit the plan and evaluation to the CPUC and to make the plan and evaluation publicly available.
- Require the plan and evaluation to include a timeline for implementation. Require transmission utilities to report on their progress in implementing the plan as part of each subsequent integrated resources plan. Require the evaluation to include a plan for proposing to the California Independent System Operator (CAISO) projects for approval where that approval is required.
Related Legislation:
SB 1165 (Padilla, 2024) would authorize an electrical corporation that applies to the CPUC to authorize construction of a high voltage electrical transmission line, rated at 138kV or greater, to apply to the CEC for certification of the facility pursuant to the CEQA, instead of the CPUC conducting the CEQA review. This bill would provide that the CEC certification authorizes the project to be eligible for the CEQA judicial streamlining afforded to Environmental Leadership Development Projects and the CEC’s “Opt-in” permitting process.
SB 619 (Padilla, 2023) would have authorized an electrical corporation that applies to the CPUC to authorize construction of a high voltage electrical transmission line, rated at 138 kV or greater, to apply to the CEC for certification of the facility pursuant to the CEQA, instead of the CPUC conducting the CEQA review. The bill would have provided that the CEC certification authorizes the project to be eligible for the CEQA judicial streamlining afforded to Environmental Leadership Development Projects (ELDPs) and the CEC’s “Opt-in” permitting process. This bill was vetoed.
SB 149 (Caballero, Chapter 60, Statutes of 2023) among its provisions, revised the procedures regarding CEQA administrative records and expedited administrative and judicial review procedures for ELDPs for specified projects, including transmission projects, that required the courts to resolve CEQA litigation within 270 days to the extent feasible and extends the ELDP sunset to January 1, 2034.
SB 319 (McGuire, Chapter 390, Statutes of 2023) required the CEC and the CPUC, in coordination with the CAISO, to better and regularly coordinate planning and permitting of energy transmission infrastructure to ensure the state meets its clean energy goals and to evaluate and report on that planning and related infrastructure development. The bill also required these state energy agencies to jointly develop an electrical transmission infrastructure development guidebook.
SB 420 (Becker, 2023) would have exempted construction of certain low-voltage electrical lines and associated equipment from the need to receive a discretionary permit from the CPUC. This bill was vetoed.
SB 529 (Hertzberg, Chapter 357, Statutes of 2022) exempted an extension, expansion, upgrade, or other modification of an existing transmission line or substations from the requirement of a CPCN and directed the CPUC to revise its GO, by January 1, 2024, to instead use its permit to construct process for these approvals.
SB 887 (Becker, Chapter 358, Statutes of 2022) requires 15-year projections of energy resource portfolios and energy demand to inform transmission planning to achieve the state’s clean energy goals, and requires the CAISO to consider approval for specified transmission projects as part of the 2022-23 transmission planning process.
AB 205 (Committee on Budget, Chapter 21, Statutes of 2022) allowed certain energy projects, including electric transmission lines between certain non-fossil fuel energy generation facilities to become certified leadership projects under the Jobs and Economic Improvement Through Environmental Leadership Act of 2021 through a certification process through the CEC. With this certification, actions or proceedings related to the certification of an environmental impact report need to be resolves within 270 days to the extent feasible.
-- END --
SENATE COMMITTEE ON ENERGY, UTILITIES AND COMMUNICATIONS
Senator Steven Bradford, Chair
2023 - 2024 Regular
Bill No: SB 1006 Hearing Date: 4/16/2024
Author: | Padilla | ||
Version: | 3/18/2024 Amended | ||
Urgency: | No | Fiscal: | Yes |
Consultant: | Nidia Bautista | ||
SUBJECT: Electricity: transmission capacity: reconductoring and grid-enhancing technologies
DIGEST: This bill requires transmission utilities, by January 1, 2026, to develop a strategic plan for grid-enhancing technologies to cost-effectively increase transmission capacity and to complete an evaluation to identify which of its transmission and distribution lines can be reconductored with advanced reconductors. Requires these plans and evaluations are submitted to the California Public Utilities Commission (CPUC) and made publicly available.
ANALYSIS:
Existing law:
- Establishes and vests the CPUC with jurisdiction over public utilities, including electrical corporations. (Article XII of the California Constitution)
- Establishes the policy of the state that eligible renewable energy resources and zero-carbon resources supply 90 percent of all retail sales of electricity to California end-use customers by December 31, 2035, 95 percent of all retail sales of electricity to California end-use customers by December 31, 2040, 100 percent of all retail sales of electricity to California end-use customers by December 31, 2045, and 100 percent of electricity procured to serve all state agencies by December 31, 2035. (Public Utilities Code §454.53)
- Provides that the CPUC may supervise and regulate every public utility in the state and may do all things, whether specifically designated or in addition, which are necessary and convenient in the exercise of such power and jurisdiction. (Public Utilities Code §701)
- Prohibits an electrical corporation from beginning the construction of a line, plant, or system, or of any extension thereof, without having first obtained from the CPUC a certificate that the present or future public convenience and necessity require or will require its construction. (Public Utilities Code §1001(a))
- Provides that the extension, expansion, upgrade, or other modification of an existing electrical transmission facility, including transmission lines and substations, does not require a certificate that the present or future public convenience and necessity requires or will require its construction. (Public Utilities Code §1001(b))
- Requires the CPUC, by January 1, 2024, to update General Order (GO)131-D to authorize each public utility electrical corporation to use the permit-to-construct process or claim an exemption under Section III(B) of that general order to seek approval to construct an extension, expansion, upgrade, or other modification to its existing electrical transmission facilities, including electric transmission lines and substations within existing transmission easements, rights of way, or franchise agreements, irrespective of whether the electrical transmission facility is above a 200-kilovolt voltage (kV) level. (Public Utilities Code §564)
This bill:
- Makes several findings and declarations regarding the potential of grid-enhancing technologies and advanced conductors to quickly and cost-effectively increase transmission capacity.
- Requires transmission utilities, defined as electrical corporations that are participating transmission owners, on or before January 1, 2026, to jointly prepare a grid-enhancing technologies strategic plan that is designed to cost-effectively increase transmission capacity and increase capacity to connect new renewable energy and zero-carbon resources, reduce transmission system congestion, reduce curtailment of renewable and zero-carbon resources, increase reliability, and reduce the risk of igniting wildfires.
- Requires each transmission utility, on or before January 1, 2026, and at least every four years thereafter, to complete an evaluation of which of its transmission and distribution lines can be reconductored with advanced conductors in a cost-effective manner to, among other things, increase transmission or distribution capacity and increase capacity to connect new renewable energy and zero-carbon resources.
- Requires, upon completion of the plan and the evaluation, the transmission utilities to submit the plan and evaluation to the CPUC and to make the plan and evaluation publicly available.
- Authorizes the CPUC to redact portions of the plan and evaluation if the redaction is necessary to protect electrical system security.
- Requires the plan and evaluation to include a timeline for implementation. Requires transmission utilities to report on their progress in implementing the plan as part of each subsequent integrated resources plan. Requires the evaluation to include a plan for proposing to the California Independent System Operator (CAISO) projects for approval where that approval is required.
- Makes legislative findings that it is the interest of the state to prevent the public disclosure of information that may compromise security of electrical transmission and distribution systems.
Background
Transmission projects. Electric transmission lines are generally high voltage lines that move electricity from generation resources (power plants) to distribution lines in neighborhoods. Companies, usually electric investor-owned utilities (IOUs), proposing the construction of new transmission, are required to obtain a permit from the CPUC for construction of certain specified infrastructure listed under Public Utilities Code §1001, including transmission projects. The CPUC reviews permit applications under two concurrent processes: (1) an environmental review pursuant to California Environmental Quality Act (CEQA), and (2) the review of project need and costs pursuant to Public Utilities Code §1001 and GO 131-D (Certificate of Public Convenience and Necessity (CPCN)).
Need for expanded transmission capacity. In order for the state to meet its clean energy goals, including achieving 100 percent clean energy by 2045, electric transmission capacity will likely need to grow significantly. The CAISO conducts its transmission planning process to identify potential transmission system limitations as well as opportunities for system reinforcements that improve reliability and efficiency. The annual transmission plan fulfills the CAISO’s core responsibility to identify and plan the development of solutions, transmission or otherwise, to meet the future needs of the electricity grid. The CAISO identifies projects that address grid reliability requirements, identify upgrades needed to successfully meet California’s policy goals, and explore projects that can bring economic benefits to consumers. In 2021, the CAISO created a 20-Year Transmission Outlook for the electric grid, in collaboration with the CPUC and the California Energy Commission (CEC), with the goal of exploring the longer-term grid requirements and options for meeting the state’s SB 100 clean energy objectives reliably and cost-effectively. The 20-Year Transmission Outlook estimates a significant amount, and expense, to construct and expand transmission facilities, including an estimated $10.74 billion in upgrades to existing facilities.
Grid-enhancing technologies (GETs). GETs, generally, are a combination of hardware and software that can increase transmission capacity, decrease congestion, and improve reliability. An April 2023 Brattle Group white paper, Building a Better Grid: How Grid-enhancing Technologies Complement Transmission Buildouts, discusses how GETs can help improve transmission capacity and efficiency. The paper notes that transmission transfer capability depends on where and how new transmission lines are connected to the rest of the system – the topology of the transmission network (including the points of injection and withdrawal of energy). Both the transfer capability of lines (and other components of the grid) and network topology determine how, where, and the quantity of the power flows. Many GETs are built on either of two applications to increase transfer capability: one that explores enhanced and flexible application of the pre-determined transfer capability; and the other that focuses on flexible and dynamic control of transmission systems. Examples of GETs include dynamic line ratings, advanced power flow controls, and advanced topology control. Dynamic line ratings (DLRs) try to better address individual line transfer capability based on actual conditions. Advanced power flow controls (generally hardware) and advanced topology control (generally software) direct electricity away from overloaded lines and onto underutilized lines, such as by opening or closing circuit breakers. As noted in the Brattle Group paper:
The comparative advantages of GETs include their portability and scalability (i.e., they can be added in phases without committing to a larger project), speed to deploy (i.e., they can be put into service much faster), and lower costs (i.e., they can be deployed often for a small fraction of the cost). GETs rarely replace transmission, rather, they enhance transmission…”
Advanced reconductoring. Reconductoring is the replacement of a transmission line’s existing conductors with advanced conductors, essentially swapping out the Aluminum Conductor Steel Reinforced (ACSR) for a smaller composite core conductors that enable higher operating temperatures. According to a November 2023 Energy Institute at Haas paper, “Accelerating Transmission Expansion by Using Advanced Conductors in Existing Right-of-Way” by Emilia Chojkiewicz, et. al (Energy Institute WP 343), reconductoring holds significant potential for rapid transmission expansion. The advanced conductors can carry approximately twice as much power as conventional conductors. Yet, advanced conductors use existing transmission towers and rights of way, thereby circumventing the land acquisition and permitting processes that can impede construction of new transmission lines. However, replacing conventional conductors with advanced conductors requires taking circuits out of service during the replacement or conducting live-line work, which carries additional risks. Either approach can be challenging, and in some cases infeasible, when transmission constraints exist.
Comments
Need for this bill. Supporters of this bill note the need for the state to upgrade and expand its electric transmission infrastructure to meet its clean energy goals. They state there will be increasing demand placed on California’s electric grid as more vehicles and homes are powered by electricity. They express concerns that the transmission grid is not keeping pace with demand, as transmission lines can take more than a decade to site, permit, and build. In this regard, they point to the opportunities with GETs and advanced conductors to help the state “enhance the existing transmission infrastructure to its maximum potential and make it more efficient, resilient, and cost-effective.”
Current use of GETs and advanced conductors. The two papers noted above, along with others, comment on the more prevalent use of GETs and advanced conductors in other countries, particularly in Europe and India. These papers, and others, state that the use of these technologies has not been as quickly embraced in the United States. In California, advanced conductors have been deployed, particularly by Southern California Edison (SCE) who has more than two dozen reconductoring projects, including the Big Creek-Ventura 220kV network. Additionally, the CAISO shared that they have considered GETs in the annual transmission planning process for many years. Specifically, the CAISO shared that they typically consider advanced conductors and power flow controllers as planning tools providing alternatives to capital expenditures, as well as, dynamic thermal line ratings, and topology optimizations to access operational benefits through additional capacity. In addition to the Big Creek-Ventura line, the CAISO approved a phase shifting transformer flow controller installation at the Imperial Valley Substation. More recently, there are two projects under development in San Jose with flow controls.
At the federal level, the Federal Energy Regulatory Commission (FERC) issued a Notice of Proposed Rulemaking (“NOPR”) in April 2022 titled “Building for the Future Through Electric Regional Transmission Planning and Cost Allocation and Generator Interconnection” (RM21-17-000) which proposes to require that public utility transmission providers more fully consider GETs in their planning. The CPUC has also shared that they along with the CEC, CAISO, Pacific Gas & Electric, SCE, and Energy Institute at Haas are currently pursuing a Department of Energy GRIP grant (eight years long) to deploy advanced conductors and two other GETs technologies: dynamic line rating and real-time short circuit duty monitoring.
Impacts to ratepayers. Both the Brattle Group and Energy Institute papers cite opportunities for savings from the use of GETs and advanced conductors. With regards to GETs, these technologies can be deployed on existing transmission lines to enhance efficiency and the potential to reduce congestion by 40 percent. Such level of efficiency can provide savings to ratepayers in the form of reducing the need for additional lines. However, the benefits of GETs will vary by transmission line. In the case of advanced conductors, these conductors have a higher up front cost as compared to conventional aluminum conductors – roughly two to three times the costs – though they have the potential for long-term savings given the potential to double the capacity of conventional conductors. However, here again, the savings will vary by transmission line. As stated in the Energy Institute paper, “Transmission networks are complex, and the actual increase in power transfer capacity offered by reconductoring is determined by a multitude of factors beyond the scope of this analysis. We recommend that transmission owners, ISOs, and RTOs perform more detailed studies…to evaluate the wide-scale deployment of advanced conductors in their networks.”
Is a strategic plan and evaluation necessary? This bill proposes to require electrical corporations who have turned over operation of their transmission to the CAISO to prepare a strategic plan for GETs and an evaluation of the use of advanced conductors. Given the need for increased transmission capacity, the desire to explore further opportunities with GETs and advanced conductors in order to optimize existing transmission is generally prudent. However, as noted in a just released Energy Innovation and GridLab report, “Supporting Advanced Conductor Deployment: Barriers and Policy Solutions,” reconductoring is not a panacea, and one may add neither are GETs. As this bill moves forward, the author may wish to consider how more flexibility can be retained in the development of the strategic plan and evaluation while helping to overcome barriers that will achieve the goal of more efficient and cost-effective transmission – and ultimately savings for ratepayers.
Need for amendments. Currently, the CPUC and CAISO have the ability to limit disclosure of information that could pose security risks to the electrical system. As such, the author and committee may wish to delete sections of this bill in Section 454.58(c)(2) and (d)(4) that authorize the CPUC to redact information from public disclosure in the required reports. Additionally, while wildfire risk reduction is an important consideration, it should be considered within the framework of the electric utilities’ wildfire mitigation plans. In this regard, the author and committee may wish to add clarifying language to this effect. Lastly, the author and committee may wish to make clarifying changes to the findings and declarations regarding the potential and use of GETs and advanced conductors.
Re-referral. Should this bill be approved by this committee, it will be re-referred to the Senate Committee on Rules.
Prior/Related Legislation
SB 1165 (Padilla, 2024) authorizes an electrical corporation that applies to the CPUC to authorize construction of a high voltage electrical transmission line, rated at 138kV or greater, to apply to the CEC for certification of the facility pursuant to the CEQA, instead of the CPUC conducting the CEQA review. This bill provides that the CEC certification authorizes the project to be eligible for the CEQA judicial streamlining afforded to Environmental Leadership Development Projects and the CEC’s “Opt-in” permitting process.
SB 619 (Padilla, 2023) would have authorized an electrical corporation that applies to the CPUC to authorize construction of a high voltage electrical transmission line, rated at 138 kV or greater, to apply to the CEC for certification of the facility pursuant to the CEQA, instead of the CPUC conducting the CEQA review. The bill provides that the CEC certification authorizes the project to be eligible for the CEQA judicial streamlining afforded to Environmental Leadership Development Projects (ELDPs) and the CEC’s “Opt-in” permitting process. The bill was vetoed.
SB 149 (Caballero, Chapter 60, Statutes of 2023) among its provisions, revised the procedures regarding CEQA administrative records and expedited administrative and judicial review procedures for ELDPs for specified projects, including transmission projects, that required the courts to resolve CEQA litigation within 270 days to the extent feasible and extends the ELDP sunset to January 1, 2034.
SB 319 (McGuire, Chapter 390, Statutes of 2023) required the CEC and the CPUC, in coordination with the CAISO, to better and regularly coordinate planning and permitting of energy transmission infrastructure to ensure the state meets its clean energy goals and to evaluate and report on that planning and related infrastructure development. The bill also required these state energy agencies to jointly develop an electrical transmission infrastructure development guidebook.
SB 420 (Becker, 2023) would have exempted construction of certain low-voltage electrical lines and associated equipment from the need to receive a discretionary permit from the CPUC. The bill was vetoed.
SB 529 (Hertzberg, Chapter 357, Statutes of 2022) exempted an extension, expansion, upgrade, or other modification of an existing transmission line or substations from the requirement of a CPCN and directed the CPUC to revise its GO, by January 1, 2024, to instead use its permit to construct process for these approvals.
SB 887 (Becker, Chapter 358, Statutes of 2022) requires 15-year projections of energy resource portfolios and energy demand to inform transmission planning to achieve the state’s clean energy goals, and requires the CAISO to consider approval for specified transmission projects as part of the 2022-23 transmission planning process.
AB 205 (Committee on Budget, Chapter 21, Statutes of 2022) allowed certain energy projects, including electric transmission lines between certain non-fossil fuel energy generation facilities to become certified leadership projects under the Jobs and Economic Improvement Through Environmental Leadership Act of 2021 through a certification process through the CEC. With this certification, actions or proceedings related to the certification of an environmental impact report need to be resolves within 270 days to the extent feasible.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
SUPPORT:
Advanced Energy Economy
California Energy Storage Alliance
California Environmental Voters
California Farm Bureau Federation
California State Association of Electrical Workers
California Wind Energy Association
Center for Energy Efficiency and Renewable Technologies
Clean Power Campaign
Citizens' Climate Lobby California
Coalition of California Utility Employees
Environment California
Fission Transition
Independent Energy Producers Association
Large-scale Solar Association
Natural Resources Defense Council
Solar Energy Industries Association
Union of Concerned Scientists
WATT Coalition
OPPOSITION:
None received
ARGUMENTS IN SUPPORT: In support of this bill, the Coalition of California Utility Employees and the California State Association of Electrical Workers state:
California must dramatically increase the total capacity of its transmission system to supply the vastly increased demand for electricity needed to meet our carbon neutrality goals. This will certainly require many new transmission lines. But in addition to new lines, new technology can enable us to get much more capacity out of existing transmission lines and transmission corridors, and to get that capacity much more quickly. ,,,Fully evaluating opportunities to deploy GETS and advanced conductors is a no-regrets policy which could yield lower costs for consumers while increasing California’s ability to meet its carbon reduction goals.
-- END --