SB 1018: Electricity.
- Session Year: 2023-2024
- House: Senate
- Latest Version Date: 2024-07-03
Current Status:
Failed
(2024-08-15: August 15 hearing: Held in committee and under submission.)
Introduced
In Committee
First Chamber
In Committee
Second Chamber
Enacted
The Public Utilities Act vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations. The act defines electrical corporation to include every corporation or person owning, controlling, operating, or managing any electric plant for compensation within this state, except as specified. The act authorizes the commission to fix the rates and charges for every public utility and requires that those rates and charges be just and reasonable.
This bill would revise the definition of electrical corporation to exclude a corporation or person employing certain solar or wind generating technology if electricity is transmitted exclusively and directly through private electrical lines to a single facility owned by a different corporation or person that uses the electricity only for new load, not for departing load, and for an electrolytic hydrogen production facility, as defined, or a facility using the electricity to provide industrial process heat, or both.
This bill would require private electric lines located on property other than the property on which a single electrolytic hydrogen production facility or industrial process heat facility or solar or wind generating technology is located to be subject to all applicable General Orders, as determined by the commission, except as provided, and would require corporations or persons employing private electric lines that are subject to those requirements to file wildfire mitigation plans if any part of the private electric lines are located in high fire threat districts, as specified.
This bill would require the commission, on or before July 1, 2026, in a new or existing proceeding, to evaluate and, if just and reasonable, establish a tariff for qualified self-generation projects with a generating capacity exceeding 80,000 kilowatts. The bill would require the commission to structure the tariff so that an electrical corporation serves as a contractual an intermediary between the electrical generation and energy storage facilities providing the electricity and the customer. qualified self-generation project. The bill would require the commission to structure rates for qualified self-generation projects to administer the purchase and resale of the electricity from the electrical generation and energy storage facilities solely at cost, as specified. The bill would also require a customer to meet various requirements to be considered a qualified self-generation project, including, among other requirements, that the customer uses electricity from specified sources and the electricity is transmitted exclusively and directly through private electric lines to the customers facility. The bill would require any cost associated with the tariff to be paid solely by participating customers such that nonparticipating customers bear no additional costs, and would require private electric lines located on property other than the property on which a single electrolytic hydrogen production facility or industrial process heat facility or solar or wind generating technology is located to be subject to all applicable General Orders, as determined by the commission, except as provided.
Under existing law, a violation of the act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.
Because the provisions of this bill would be a part of the act and because a violation of a commission action implementing the bills requirements would be a crime, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
The Public Utilities Act vests the Public Utilities Commission has with regulatory authority over public utilities, including electrical corporations. Electrical The act defines electrical corporation is defined for that purpose to include every corporation or person owning, controlling, operating, or managing any electric plant for compensation within this state, except as specified. Existing law The act authorizes the commission to fix the rates and charges for every public utility and requires that those rates and charges be just and reasonable.
This bill would revise the definition of electrical corporation to exclude a corporation or person employing certain solar or wind generating technology if the electrical energy electricity is transmitted exclusively and directly through private electric electrical lines to a single facility owned by a different corporation or person that uses the energy electricity only for new load, not for departing load, and for (1) an electrolyzer technology facility that produces hydrogen from water, an electrolytic hydrogen production facility, as defined, or (2) a facility using the electricity to provide industrial process heat, or both.
This bill would require the commission, on or before July 1, 2026, in a new or existing proceeding, to evaluate and, if just and reasonable, establish a tariff for qualified self-generation projects with a generating capacity exceeding 80,000 kilowatts. The bill would require the commission to structure the tariff so that an electrical corporation serves as a contractual intermediary between the electrical generation and energy storage facilities providing the electricity and the customer. The bill would require the commission to structure rates for qualified self-generation projects to administer the purchase and resale of the electricity from the electrical generation and energy storage facilities solely at cost, as specified. The bill would also require a customer to meet various requirements to be considered a qualified self-generation project, including, among other requirements, that the customer uses certain electricity, that, in the aggregate, is synchronized with the customers load, as defined, and electricity from specified sources and the electricity is transmitted directly to the customers facility.
Under existing law, a violation of the Public Utilities Act act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.
Because the provisions of this bill would be a part of the act and because a violation of a commission action implementing the bills requirements would be a crime, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Under existing law, the Public Utilities Commission has regulatory authority over public utilities, including electrical corporations. Electrical corporation is defined for that purpose to include every corporation or person owning, controlling, operating, or managing any electric plant for compensation within this state, except as specified. Existing law authorizes the commission to fix the rates and charges for every public utility and requires that those rates and charges be just and reasonable.
This bill would revise the definition of electrical corporation to exclude a corporation or person employing certain solar or wind generating technology if the electrical energy is transmitted exclusively and directly through private electric lines to a single facility owned by a different corporation or person that uses the energy only for new load, not for departing load, and for (1) an electrolyzer technology facility that produces hydrogen from water, or (2) a facility using the electricity to provide industrial process heat, but not for departing electric load, as specified. The bill would also make various nonsubstantive changes. or both.
This bill would require the commission, on or before July 1, 2026, in a new or existing proceeding, to evaluate and, if just and reasonable, establish a tariff for qualified self-generation projects with a generating capacity exceeding 80,000 kilowatts. The bill would require the commission to structure the tariff so that an electrical corporation serves as a contractual intermediary between the electrical generation and energy storage facilities providing the electricity and the customer. The bill would require the commission to structure rates for qualified self-generation projects to administer the purchase and resale of the electricity from the electrical generation and energy storage facilities solely at cost, as specified. The bill would also require a customer to meet various requirements to be considered a qualified self-generation project, including, among other requirements, that the customer uses certain electricity, that, in the aggregate, is synchronized with the customers load, as defined, and transmitted directly to the customers facility.
Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.
Because the provisions of this bill would be a part of the act and because a violation of a commission action implementing the bills requirements would be a crime, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Under existing law, the Public Utilities Commission has regulatory authority over public utilities, including electrical corporations. Electrical corporation is defined for that purpose to include every corporation or person owning, controlling, operating, or managing any electric plant for compensation within this state, except as specified.
This bill would revise the definition of electrical corporation to exclude a corporation or person employing certain solar or wind generating technology if the electrical energy is transmitted exclusively and directly through private electric lines to a facility owned by a different corporation or person that uses the energy only for (1) an electrolyzer technology facility that produces hydrogen from water, or (2) a facility using the electricity to provide industrial process heat, but not for departing electric load, as specified. The bill would also make various nonsubstantive changes.
(a)Electrical corporation includes every corporation or person owning, controlling, operating, or managing any electric plant for compensation within this state, except where electricity is generated on or distributed by the producer through private property solely for its own use or the use of its tenants and not for sale or transmission to others.
(b)Electrical corporation does not include a corporation or person employing cogeneration technology or producing power from other than a conventional power source for the generation of electricity solely for one or more of the following purposes:
(1)Its own use or the use of its tenants.
(2)The use of or sale to not more than two other corporations or persons solely for use on the real property on which the electricity is generated or on real property immediately adjacent thereto, unless there is an intervening public street constituting the boundary between the real property on which the electricity is generated and the immediately adjacent property and one or more of the following applies:
(A)The real property on which the electricity is generated and the immediately adjacent real property is not under common ownership or control, or that common ownership or control was gained solely for purposes of sale of the generated electricity and not for other business purposes.
(B)The useful thermal output of the facility generating the electricity is not used on the immediately adjacent property for petroleum production or refining.
(C)The electricity furnished to the immediately adjacent property is not used by a subsidiary or affiliate of the corporation or person generating the electricity.
(3)Sale or transmission to an electrical corporation or state or local public agency, but not for sale or transmission to others, unless the corporation or person is otherwise an electrical corporation.
(c)Electrical corporation does not include a corporation or person employing landfill gas technology for the generation of electricity for one or more of the following purposes:
(1)Its own use or the use of not more than two of its tenants located on the real property on which the electricity is generated.
(2)The use of or sale to not more than two other corporations or persons solely for use on the real property on which the electricity is generated.
(3)Sale or transmission to an electrical corporation or state or local public agency.
(d)Electrical corporation does not include a corporation or person employing digester gas technology for the generation of electricity for one or more of the following purposes:
(1)Its own use or the use of not more than two of its tenants located on the real property on which the electricity is generated.
(2)The use of or sale to not more than two other corporations or persons solely for use on the real property on which the electricity is generated.
(3)Sale or transmission to an electrical corporation or state or local public agency, if the sale or transmission of the electricity service to a retail customer is provided through the transmission system of the existing local publicly owned electric utility or electrical corporation of that retail customer.
(e)Electrical corporation does not include an independent solar energy producer, as defined in Article 3 (commencing with Section 2868) of Chapter 9 of Part 2.
(f)Electrical corporation does not include a corporation or person employing solar or wind generating technology of not less than five megawatts, which may have associated on-site battery energy storage technology, if the electrical energy electricity is transmitted exclusively and directly through private electric lines to a single facility owned by a different corporation or person that uses the energy only for new load, not for departing load, and for one or more of the following uses, including de minimis consumption necessary for the management and control of these uses:
(1)An electrolytic hydrogen production facility, as defined in Section 740.25.
(2)A facility using the electricity to provide industrial process heat, including through the use of a thermal energy storage system.
(g)The amendments made to this section at the 1987 portion of the 198788 Regular Session of the Legislature do not apply to any corporation or person employing cogeneration technology or producing power from other than a conventional power source for the generation of electricity that physically produced electricity before January 1, 1989, and furnished that electricity to immediately adjacent real property for use on that real property before January 1, 1989.
SEC. 2.Section 218.1 is added to the Public Utilities Code, to read:218.1.(a)(1)Private electric lines located on property other than the property on which a single electrolytic hydrogen production facility or industrial process heat facility or solar or wind generating technology is located, as described in subdivision (f) of Section 218, shall be subject to all applicable General Orders, as determined by the commission.
(2)The requirements of paragraph (1) shall not apply if all of the property is owned by the same corporation or person owning the electrolytic hydrogen production facility or the industrial process heat facility.
(b)Corporations or persons employing private electric lines that are subject to the requirements of subdivision (a) shall file wildfire mitigation plans if any part of the private electric lines are located in high fire threat districts as identified in the commissions fire-threat map. Wildfire mitigation plans required pursuant to this subdivision shall, to the extent feasible, be consistent with the requirements of Section 8386, as determined by the Office of Energy Infrastructure Safety.
(c)As used in this section, the following definitions apply:
(1)Electrolytic hydrogen production facility is as defined pursuant to Section 740.25.
(2)Industrial process heat facility means a facility described in paragraph (2) of subdivision (f) of Section 218.
(3)Solar or wind generating technology means the solar or wind generating technology described in subdivision (f) of Section 218.
SEC. 2.SEC. 3.Section 740.25 is added to the Public Utilities Code, to read:740.25.(a)On or before July 1, 2026, the commission shall, in a new or existing proceeding, evaluate and, if just and reasonable, establish a tariff for qualified self-generation projects with a generating capacity exceeding 80,000 kilowatts.
(b)The commission shall structure the tariff so that the electrical corporation serves as a contractual an intermediary between the electrical generation and energy storage facilities providing the electricity and the customer qualified self-generation project for purposes of providing retail service and allowing the electrical generation and energy storage facilities to be considered exempt wholesale generators as defined in Section 366.1 of Title 18 of the Code of Federal Regulations.
(c)The commission shall structure rates for qualified self-generation projects to administer the purchase and resale of the electricity from the electrical generation and energy storage facilities solely at cost and then add on the incremental administrative or operational costs of the electrical corporation serving as a contractual an intermediary.
(d)Nothing in this section shall prevent customers qualified self-generation projects from taking supplemental service under a standard offer tariff with separate metering or submetering, as determined by the commission.
(e)Nothing in this section shall authorize or prohibit electrical generation or energy storage facilities that are providing electricity to a qualified self-generation project from also participating in wholesale electricity markets.
(f)As used in this section, the following definitions apply:
(1)Qualified self-generation project means a customer that meets all of the following requirements:
(A)The customer uses electricity from one or both of the following sources that is transmitted exclusively and directly through private electric lines to the customers facility:
(i)Electricity from an electrical generation facility using solar or wind technology.
(ii)Electricity from an energy storage facility that stores energy exclusively from a facility using solar or wind technology.
(B)The customer bears responsibility for the cost of any infrastructure constructed for the purpose of connecting the customers facility with the electrical generation or energy storage facility, whether built by the customer or by the electrical corporation.
(C)The customer consumes the electricity for one or both of the following uses, including de minimis consumption necessary for management and control of those uses:
(i)Using electricity to power an electrolytic hydrogen production facility.
(ii)Using electricity to provide industrial process heat, including through the use of a thermal energy storage system.
(D)The customer consumes the electricity only for new load, and not for departing load.
(E)The customer files wildfire mitigation plans if any part of the private electric lines that are subject to the requirements of subdivision (h) are located in high fire threat districts as identified in the commissions fire-threat map. Wildfire mitigation plans required pursuant to this subdivision shall, to the extent feasible, be consistent with the requirements of Section 8386, as determined by the Office of Energy Infrastructure Safety.
(2)Electrolytic hydrogen production facility means a facility that makes hydrogen by electrolysis of water, including electrolyzers for producing hydrogen and any auxiliary systems within the facility, including pumps, compressors, liquefiers, and other systems for moving or storing water or hydrogen or preparing hydrogen for transport.
(g)Any cost associated with this section shall be paid solely by participating customers such that nonparticipating customers bear no additional costs.
(h)Private electric lines located on property other than the property on which a single electrolytic hydrogen production facility or industrial process heat facility or solar or wind generating technology are located shall be subject to all applicable General Orders, as determined by the commission, except in circumstances where all the property is owned by the same corporation or person owning the electrolytic hydrogen production facility or industrial process heat facility.
SEC. 3.SEC. 4.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
(a)Electrical corporation includes every corporation or person owning, controlling, operating, or managing any electric plant for compensation within this state, except where electricity is generated on or distributed by the producer through private property solely for its own use or the use of its tenants and not for sale or transmission to others.
(b)Electrical corporation does not include a corporation or person employing cogeneration technology or producing power from other than a conventional power source for the generation of electricity solely for one or more of the following purposes:
(1)Its own use or the use of its tenants.
(2)The use of or sale to not more than two other corporations or persons solely for use on the real property on which the electricity is generated or on real property immediately adjacent thereto, unless there is an intervening public street constituting the boundary between the real property on which the electricity is generated and the immediately adjacent property and one or more of the following applies:
(A)The real property on which the electricity is generated and the immediately adjacent real property is not under common ownership or control, or that common ownership or control was gained solely for purposes of sale of the generated electricity and not for other business purposes.
(B)The useful thermal output of the facility generating the electricity is not used on the immediately adjacent property for petroleum production or refining.
(C)The electricity furnished to the immediately adjacent property is not used by a subsidiary or affiliate of the corporation or person generating the electricity.
(3)Sale or transmission to an electrical corporation or state or local public agency, but not for sale or transmission to others, unless the corporation or person is otherwise an electrical corporation.
(c)Electrical corporation does not include a corporation or person employing landfill gas technology for the generation of electricity for one or more of the following purposes:
(1)Its own use or the use of not more than two of its tenants located on the real property on which the electricity is generated.
(2)The use of or sale to not more than two other corporations or persons solely for use on the real property on which the electricity is generated.
(3)Sale or transmission to an electrical corporation or state or local public agency.
(d)Electrical corporation does not include a corporation or person employing digester gas technology for the generation of electricity for one or more of the following purposes:
(1)Its own use or the use of not more than two of its tenants located on the real property on which the electricity is generated.
(2)The use of or sale to not more than two other corporations or persons solely for use on the real property on which the electricity is generated.
(3)Sale or transmission to an electrical corporation or state or local public agency, if the sale or transmission of the electricity service to a retail customer is provided through the transmission system of the existing local publicly owned electric utility or electrical corporation of that retail customer.
(e)Electrical corporation does not include an independent solar energy producer, as defined in Article 3 (commencing with Section 2868) of Chapter 9 of Part 2.
(f)Electrical corporation does not include a corporation or person employing solar or wind generating technology of not less than five megawatts, which may have associated on-site battery energy storage technology, if the electrical energy is transmitted exclusively and directly through private electric lines to a single facility owned by a different corporation or person that uses the energy only for new load, not for departing load, and for one or more of the following uses, including de minimis consumption necessary for the management and control of these uses:
(1)An electrolyzer technology facility that produces hydrogen from water.(1)An electrolytic hydrogen production facility, as defined in Section 740.25.
(2)A facility using the electricity to provide industrial process heat, including through the use of a thermal energy storage system.
(g)The amendments made to this section at the 1987 portion of the 198788 Regular Session of the Legislature do not apply to any corporation or person employing cogeneration technology or producing power from other than a conventional power source for the generation of electricity that physically produced electricity before January 1, 1989, and furnished that electricity to immediately adjacent real property for use on that real property before January 1, 1989.
SEC. 2.Section 740.25 is added to the Public Utilities Code, to read:740.25.(a)On or before July 1, 2026, the commission shall, in a new or existing proceeding, evaluate and, if just and reasonable, establish a tariff for qualified self-generation projects with a generating capacity exceeding 80,000 kilowatts.
(b)The commission shall structure the tariff so that the electrical corporation serves as a contractual intermediary between the electrical generation and energy storage facilities providing the electricity and the customer for purposes of providing retail service and allowing the electrical generation and energy storage facilities to be considered exempt wholesale generators as defined in Section 366.1 of Title 18 of the Code of Federal Regulations.
(c)The commission shall structure rates for qualified self-generation projects to administer the purchase and resale of the electricity from the electrical generation and energy storage facilities solely at cost and then add on the incremental administrative or operational costs of the electrical corporation serving as a contractual intermediary.
(d)Nothing in this section shall prevent customers from taking supplemental service for auxiliary equipment or loads that are not part of the qualified self-generation project under a standard offer tariff with separate metering or submetering, as determined by the commission.
(e)Nothing in this section shall prohibit electrical generation or energy storage facilities that are providing electricity to a qualified self-generation project from also participating in wholesale electricity markets.
(f)As used in this section, the following definitions apply:
(1)Qualified self-generation project means a customer that meets all of the following requirements:
(A)The customer uses electricity from one or both of the following sources that, in the aggregate, is synchronized with the customers load and that is transmitted directly to the customers facility:
(i)Electricity from an electrical generation facility using solar or wind technology.
(ii)Electricity from an energy storage facility that stores energy exclusively from a facility using solar or wind technology.
(B)The customer bears responsibility for the cost of any infrastructure constructed for the purpose of connecting the customers facility with the electrical generation or energy storage facility, whether built by the customer or by the electrical corporation.
(C)The customer consumes the electricity for one or both of the following uses, including de minimis consumption necessary for management and control of those uses:
(i)Producing hydrogen using an electrolysis of water.(i)Using electricity to power an electrolytic hydrogen production facility.
(ii)Using electricity to provide industrial process heat, including through the use of a thermal energy storage system.
(2)Synchronized with the customers load means that supply and demand between the electrical generation and energy storage facilities and the customers consumption are temporally balanced in a manner that avoids the use of the bulk power system and that the customers load shall not use electricity from the electrical corporations transmission, distribution, or generation assets except for incidental, emergency, or testing purposes.(2)Electrolytic hydrogen production facility means a facility that makes hydrogen by electrolysis of water, including electrolyzers for producing hydrogen and any auxiliary systems within the facility, including pumps, compressors, liquefiers, and other systems for moving or storing water or hydrogen or preparing hydrogen for transport.
SEC. 3.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
(a)Electrical corporation includes every corporation or person owning, controlling, operating, or managing any electric plant for compensation within this state, except where electricity is generated on or distributed by the producer through private property solely for its own use or the use of its tenants and not for sale or transmission to others.
(b)Electrical corporation does not include a corporation or person employing cogeneration technology or producing power from other than a conventional power source for the generation of electricity solely for one or more of the following purposes:
(1)Its own use or the use of its tenants.
(2)The use of or sale to not more than two other corporations or persons solely for use on the real property on which the electricity is generated or on real property immediately adjacent thereto, unless there is an intervening public street constituting the boundary between the real property on which the electricity is generated and the immediately adjacent property and one or more of the following applies:
(A)The real property on which the electricity is generated and the immediately adjacent real property is not under common ownership or control, or that common ownership or control was gained solely for purposes of sale of the generated electricity and not for other business purposes.
(B)The useful thermal output of the facility generating the electricity is not used on the immediately adjacent property for petroleum production or refining.
(C)The electricity furnished to the immediately adjacent property is not used by a subsidiary or affiliate of the corporation or person generating the electricity.
(3)Sale or transmission to an electrical corporation or state or local public agency, but not for sale or transmission to others, unless the corporation or person is otherwise an electrical corporation.
(c)Electrical corporation does not include a corporation or person employing landfill gas technology for the generation of electricity for one or more of the following purposes:
(1)Its own use or the use of not more than two of its tenants located on the real property on which the electricity is generated.
(2)The use of or sale to not more than two other corporations or persons solely for use on the real property on which the electricity is generated.
(3)Sale or transmission to an electrical corporation or state or local public agency.
(d)Electrical corporation does not include a corporation or person employing digester gas technology for the generation of electricity for one or more of the following purposes:
(1)Its own use or the use of not more than two of its tenants located on the real property on which the electricity is generated.
(2)The use of or sale to not more than two other corporations or persons solely for use on the real property on which the electricity is generated.
(3)Sale or transmission to an electrical corporation or state or local public agency, if the sale or transmission of the electricity service to a retail customer is provided through the transmission system of the existing local publicly owned electric utility or electrical corporation of that retail customer.
(e)Electrical corporation does not include an independent solar energy producer, as defined in Article 3 (commencing with Section 2868) of Chapter 9 of Part 2.
(f)Electrical corporation does not include a corporation or person employing solar or wind generating technology of not less than five megawatts, which may have associated on-site battery energy storage technology, if the electrical energy is transmitted exclusively and directly through private electric lines to a single facility owned by a different corporation or person that uses the energy only for new load, not for departing load, and for one or more of the following, but not for departing electric load: following uses, including de minimis consumption necessary for the management and control of these uses:
(1)An electrolyzer technology facility that produces hydrogen from water.
(2)A facility using the electricity to provide industrial process heat, including through the use of a thermal energy storage system.
(g)The amendments made to this section at the 1987 portion of the 198788 Regular Session of the Legislature do not apply to any corporation or person employing cogeneration technology or producing power from other than a conventional power source for the generation of electricity that physically produced electricity before January 1, 1989, and furnished that electricity to immediately adjacent real property for use on that real property before January 1, 1989.
SEC. 2.Section 740.25 is added to the Public Utilities Code, to read:740.25.(a)On or before July 1, 2026, the commission shall, in a new or existing proceeding, evaluate and, if just and reasonable, establish a tariff for qualified self-generation projects with a generating capacity exceeding 80,000 kilowatts.
(b)The commission shall structure the tariff so that the electrical corporation serves as a contractual intermediary between the electrical generation and energy storage facilities providing the electricity and the customer for purposes of providing retail service and allowing the electrical generation and energy storage facilities to be considered exempt wholesale generators as defined in Section 366.1 of Title 18 of the Code of Federal Regulations.
(c)The commission shall structure rates for qualified self-generation projects to administer the purchase and resale of the electricity from the electrical generation and energy storage facilities solely at cost and then add on the incremental administrative or operational costs of the electrical corporation serving as a contractual intermediary.
(d)Nothing in this section shall prevent customers from taking supplemental service for auxiliary equipment or loads that are not part of the qualified self-generation project under a standard offer tariff with separate metering or submetering, as determined by the commission.
(e)Nothing in this section shall prohibit electrical generation or energy storage facilities that are providing electricity to a qualified self-generation project from also participating in wholesale electricity markets.
(f)As used in this section, the following definitions apply:
(1)Qualified self-generation project means a customer that meets all of the following requirements:
(A)The customer uses electricity from one or both of the following sources that, in the aggregate, is synchronized with the customers load and transmitted directly to the customers facility:
(i)Electricity from an electrical generation facility using solar or wind technology.
(ii)Electricity from an energy storage facility that stores energy exclusively from a facility using solar or wind technology.
(B)The customer bears responsibility for the cost of any infrastructure constructed for the purpose of connecting the customers facility with the electrical generation or energy storage facility, whether built by the customer or by the electrical corporation.
(C)The customer consumes the electricity for one or both of the following uses, including de minimis consumption necessary for management and control of those uses:
(i)Producing hydrogen using an electrolysis of water.
(ii)Using electricity to provide industrial process heat, including through the use of a thermal energy storage system.
(2)Synchronized with the customers load means that supply and demand between the electrical generation and energy storage facilities and the customers consumption are temporally balanced in a manner that avoids the use of the bulk power system and that the customers load shall not use electricity from the electrical corporations transmission, distribution, or generation assets except for incidental, emergency, or testing purposes.
SEC. 3.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
(a)Electrical corporation includes every corporation or person owning, controlling, operating, or managing any electric plant for compensation within this state, except where electricity is generated on or distributed by the producer through private property solely for its own use or the use of its tenants and not for sale or transmission to others.
(b)Electrical corporation does not include a corporation or person employing cogeneration technology or producing power from other than a conventional power source for the generation of electricity solely for any one or more of the following purposes:
(1)Its own use or the use of its tenants.
(2)The use of or sale to not more than two other corporations or persons solely for use on the real property on which the electricity is generated or on real property immediately adjacent thereto, unless there is an intervening public street constituting the boundary between the real property on which the electricity is generated and the immediately adjacent property and one or more of the following applies:
(A)The real property on which the electricity is generated and the immediately adjacent real property is not under common ownership or control, or that common ownership or control was gained solely for purposes of sale of the generated electricity so generated and not for other business purposes.
(B)The useful thermal output of the facility generating the electricity is not used on the immediately adjacent property for petroleum production or refining.
(C)The electricity furnished to the immediately adjacent property is not utilized used by a subsidiary or affiliate of the corporation or person generating the electricity.
(3)Sale or transmission to an electrical corporation or state or local public agency, but not for sale or transmission to others, unless the corporation or person is otherwise an electrical corporation.
(c)Electrical corporation does not include a corporation or person employing landfill gas technology for the generation of electricity for any one or more of the following purposes:
(1)Its own use or the use of not more than two of its tenants located on the real property on which the electricity is generated.
(2)The use of or sale to not more than two other corporations or persons solely for use on the real property on which the electricity is generated.
(3)Sale or transmission to an electrical corporation or state or local public agency.
(d)Electrical corporation does not include a corporation or person employing digester gas technology for the generation of electricity for any one or more of the following purposes:
(1)Its own use or the use of not more than two of its tenants located on the real property on which the electricity is generated.
(2)The use of or sale to not more than two other corporations or persons solely for use on the real property on which the electricity is generated.
(3)Sale or transmission to an electrical corporation or state or local public agency, if the sale or transmission of the electricity service to a retail customer is provided through the transmission system of the existing local publicly owned electric utility or electrical corporation of that retail customer.
(e)Electrical corporation does not include an independent solar energy producer, as defined in Article 3 (commencing with Section 2868) of Chapter 9 of Part 2.
(f)Electrical corporation does not include a corporation or person employing solar or wind generating technology of not less than five megawatts, which may have associated on-site battery energy storage technology, if the electrical energy is transmitted exclusively and directly through private electric lines to a facility owned by a different corporation or person that uses the energy only for one of the following, but not for departing electric load:
(1)An electrolyzer technology facility that produces hydrogen from water.
(2)A facility using the electricity to provide industrial process heat, including through the use of a thermal energy storage system.
(f)(g)The amendments made to this section at the 1987 portion of the 198788 Regular Session of the Legislature do not apply to any corporation or person employing cogeneration technology or producing power from other than a conventional power source for the generation of electricity that physically produced electricity prior to before January 1, 1989, and furnished that electricity to immediately adjacent real property for use thereon prior to on that real property before January 1, 1989.
|
Date
|
Status
|
|---|---|
| Aug 15, 2024 | August 15 hearing: Held in committee and under submission. |
| Aug 7, 2024 | August 7 set for first hearing. Placed on suspense file. |
| Jul 3, 2024 | Read second time and amended. Re-referred to Com. on APPR. |
| Jul 2, 2024 | From committee: Do pass as amended and re-refer to Com. on APPR. (Ayes 14. Noes 0.) (July 1). |
| Jun 20, 2024 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on U. & E. |
| Jun 4, 2024 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on U. & E. |
| May 28, 2024 | Referred to Com. on U. & E. |
| May 22, 2024 | In Assembly. Read first time. Held at Desk. |
| May 21, 2024 | Read third time. Passed. (Ayes 30. Noes 8. Page 4077.) Ordered to the Assembly. |
| Apr 30, 2024 | Read second time. Ordered to third reading. |
| Apr 29, 2024 | From committee: Be ordered to second reading pursuant to Senate Rule 28.8. |
| Apr 22, 2024 | Set for hearing April 29. |
| Apr 16, 2024 | From committee: Do pass and re-refer to Com. on APPR. (Ayes 14. Noes 3. Page 3632.) (April 16). Re-referred to Com. on APPR. |
| Apr 4, 2024 | Set for hearing April 16. |
| Feb 14, 2024 | Referred to Com. on E., U. & C. |
| Feb 6, 2024 | From printer. May be acted upon on or after March 7. |
| Feb 5, 2024 | Introduced. Read first time. To Com. on RLS. for assignment. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Jul 1, 2024 | Do pass as amended and be re-referred to the Committee on [Appropriations] | Assembly Standing Committee on Utilities and Energy |
Passed |
|
| May 21, 2024 | Senate 3rd Reading SB1018 Becker | Senate Floor |
Passed |
|
| Apr 16, 2024 | Do pass, but first be re-referred to the Committee on [Appropriations] | Senate Standing Committee on Energy, Utilities and Communications |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| 350 Humboldt | ** Support | |
| 350 Humboldt: Grass Roots Climate Action | ** Support | |
| 350 Sacramento | ** Support | |
| Advanced Energy Economy | ** Support | |
| Advanced Energy United | ** Support | |
| California Hydrogen Coalition | ** Support | |
| California State Association Of Electrical Workers | ** Support | |
| California State Pipe Trades Council | ** Support | |
| Climate Action California | ** Support | |
| Coalition of California Utility Employees | ** Support | |
| Green Hydrogen Coalition | ** Support | |
| Industrious Labs | ** Support | |
| Intersect Power | ** Support | |
| Menlo Spark | ** Support | |
| Natural Resources Defense Council | ** Support | |
| Nrdc Action Fund | ** Support | |
| Pacific Gas And Electric Company | ** Against | |
| Project 2030 | ** Support | |
| Public Advocates Office | ** Against | |
| Rondo Energy | ** Support | |
| San Diego Gas and Electric Company | ** Against | |
| Sierra Club | ** Support | |
| Solar Energy Industry Association | ** Support | |
| Southern California Edison | ** Against | |
| The Climate Center | ** Support | |
| The Climate Reality Project, Silicon Valley | ** Support | |
| Western States Council Sheet Metal, Air, Rail And Transportation | ** Support |
Date of Hearing: August 7, 2024
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Buffy Wicks, Chair
SBPCA Bill Id:SB 1018
Author:(Becker) – As Amended Ver:July 3, 2024
Policy Committee: | Utilities and Energy | Vote: | 14 - 0 |
|
| ||
|
|
Urgency: No State Mandated Local Program: Yes Reimbursable: No
SUMMARY:
This bill provides two exemptions from existing law for an entity that sells electricity generated from solar or wind energy if the entity supplies the electricity exclusively for electrolytic hydrogen production and electrifying industrial heat processes.
Among other things, this bill creates the two exemptions, as follows:
- Exemption from state law governing regulation of electrical corporations. Exempts from the definition of “electrical corporation” under California law an entity selling electricity generated by a solar or wind electric generation facility of at least five megawatts (MW), provided the electricity is transmitted solely using private electric lines to a separate facility owned by a different entity that uses the electricity exclusively to produce hydrogen from electrolysis or for industrial process heat, including the use of a thermal energy storage system. In effect, this exemption removes the electricity generating facility from regulation by the California Public Utilities Commission (CPUC).
- Exemption from federal Public Utility Holding Company rules.
- Defines “qualified self-generation project” (QSGP) as a customer that (i) uses electricity from either solar or wind technology, or storage facilities exclusively charging from solar or wind technology, that is transmitted exclusively and directly on private transmission lines for use by the customer to power either an electrolytic hydrogen production facility or to provide industrial heat process heat; (ii) bears responsibility for the cost of any infrastructure constructed for the purpose of connecting the QSGP with the generation or storage facility; (iii) uses the electricity for only new load and not for departing load; and (iv) files wildfire mitigation plans (WMPs) if any part of the private electric lines are located in high fire threat districts as identified in the CPUC’s fire threat map.
- Requires the CPUC to establish a tariff by July 1, 2026, if just and reasonable, that allows for a solar or wind electricity generation facility, and associated storage, greater than 80 MWs and providing retail service to QSGP to be exempt from federal Public Utility Holding Company Act (PUHCA) rules due to the generation facility’s designation as an exempt wholesale generator, so that an electrical corporation (also known as investor-owned utility, or IOU) may serve as a contractual intermediary between the generation facility and the customer, where the rates for both purchasing and reselling the electricity will be at cost, but include an adder for incremental administrative or operational costs to be paid to the IOU serving as the intermediary.
- Explicitly states that (i) the customer may take supplemental service under standard tariffs, (ii) the generation facility may also participate in wholesale electricity markets and (iii) any costs associated with this exemption are to be paid solely by the participating customer such that nonparticipating customers bear no additional cost.
- Applicable to each exemption:
- States that private electric lines located on property other than the property on which a single electrolytic hydrogen production facility or industrial process heat facility or solar or wind generating technology are located are subject to all applicable CPUC general orders, as determined by the CPUC, except in circumstances where all the property is owned by the same corporation or person owning the electrolytic hydrogen production facility or industrial process heat facility.
- Requires an entity that owns private electric lines for the purposes described above to file WMPs if any part of the private electric lines are located in high fire threat districts as identified in the CPUC’s fire threat map.
FISCAL EFFECT:
While this bill exempts certain electricity generating facilities from CPUC regulation, it also creates new work for the CPUC. Specifically, the bill requires the CPUC to establish a tariff, if just and reasonable, that allows for a solar or wind electricity generation facility, and associated storage, greater than 80 MWs and providing retail service to QSGPs to be exempt from federal PUHCA rules. In addition, it requires the CPUC to determine whether applicable CPUC general orders apply to private electric lines located on property other than the property on which a single electrolytic hydrogen production facility or industrial process heat facility or solar or wind generating technology are located. The CPUC anticipates ongoing annual costs of approximately $725,000 (likely funded by the Public Utilities Commission Utilities Reimbursement Account) for three new positions, as follows:
- An attorney ($250,000 annually) to represent the commission in a preceding to implement the new tariff and other requirements of the bill, and to represent the CPUC’s Safety Enforcement Division in enforcement actions and investigations.
- A utilities engineer ($255,000 annually) to conduct audits and inspections of the private power lines to ensure the safety of the public and infrastructure.
- A regulatory analyst ($210,000 annually) to support the commission’s proceeding to establish the new tariff and to assess proposals for alternative special tariff designs to support eligible solar and wind projects operated in conjunction with storage facilities to power large customers developing electrolytic hydrogen and industrial process heat.
- Associated travel and equipment costs of less than $10,000 annually.
COMMENTS:
- Purpose. The author intends this bill to create a “narrow” exemption to existing law to allow “green” hydrogen production facilities to directly connect with renewable energy resources without coming under regulation as a utility, thereby lowering production costs. According to the author:
Powering hydrogen production or thermal batteries by connecting them directly to renewable energy (“off-grid”) would give them access to some of the cheapest sources of energy. It would also guarantee that the hydrogen or heat is powered by clean energy without adding stress to the grid. Unfortunately, this off-grid option is blocked today. SB 1018 solves this problem by creating a narrow, new exception that allows a large solar or wind generator … to sell their output directly to a single customer who will use that power for producing hydrogen or providing industrial heat. It also directs the PUC to create a workaround for large projects that could be regulated as public utility holding companies under federal law if they both provide electricity directly to an affiliated hydrogen facility…and also sell excess electricity into the wholesale market. These changes will support the growth of green hydrogen and industrial electrification in a way that will ensure it makes use of clean energy and does not impact electricity rates or grid reliability.
- Background. Production and use of hydrogen—made using carbon-free resources—is likely key to the state achieving its clean energy goals. The Air Resources Board’s “2022 Scoping Plan for Achieving Carbon Neutrality” calls for the supply of “renewable” hydrogen to increase by 1,700 times from current levels.
Hydrogen is extraordinarily abundant in the natural environment; however, isolating and conditioning it for industrial use is energy intensive and, therefore, costly. Hydrogen may be produced through the use of electricity supplied by the interconnected electrical grid. Doing so, however, means the electricity used is generated, in part, using greenhouse gas-emitting resources (at least for the foreseeable future). It also means the retail price of the electricity has numerous costs embedded into it beyond just the cost to generate the electricity. These costs include utility profits, charges to support low-income utility customers and expenses to “harden” electrical wires and equipment so they are less likely to spark fires, among many others.
The author envisions using renewable energy supplied directly to a hydrogen production facility through privately owned cables. Doing so ensures the electricity used to produce the hydrogen is 100% renewable, with minimal, if any, associated greenhouse gas emissions. It also means the electricity is, generally, cheaper than grid-supplied electricity as it is not subject to the many charges, described in the preceding paragraph, that are applied to grid-supplied electricity.
Existing law, however, prevents realization of this vision. This is because existing law, generally, considers an entity that generates electricity and sells it to another party for use to be an electrical corporation, subject to regulation by the CPUC. This bill provides an exemption from this regulation, for the most part, as described above.
Customers of the state’s electric IOUs have financial incentives to shed the many charges that are bundled into the rates for each kilowatt of electricity, approved by the CPUC and charged by the IOUs. And many customers have, or have attempted, to do so. Yet one customer successfully avoiding these charges oftentimes creates problems for the IOU customers who are left to pay the costs that are recovered through those charges, which remain unchanged. This phenomenon is commonly known as a “cost shift” and has been the subject of intense debate for well over a decade.
Arguably, this bill will not shift costs to nonparticipating IOU customers (though not all informed parties agree, as evidenced by the arguments of the Public Advocates Office, summarized below). This is because the bill does not apply to existing IOU customers who currently pay those costs, and who could use the exemption provided by this bill to escape them. Rather, the bill applies to facilities not yet in operation and that will not use the IOU electrical grid (at least not for the electricity used to produce hydrogen).
However, to the extent electricity users avoid using the electrical grid, those users avoid the generally shared burden of supporting the greater electrical system. This bill is narrowly targeted—its provisions apply only to one favored industrial activity, green hydrogen production. But there are many industrial activities that further state goals and generally benefit the state. The Legislature may want to encourage general modifications to the way the state funds its electrical system so that users may make economically rational decisions about their use of electricity, rather than approving one-offs that allow one type of electricity user or users to escape costs borne by all other electricity users.
- Support and Opposition. This bill is supported by numerous parties representing industrial, labor and environmental organizations. For example, the Natural Resources Defense Council supports the bill, arguing SB 1018 provides “an option for new industrial technologies to be powered entirely by renewable energy while minimizing emissions and impacts on the grid” and “could bring renewables online more quickly by having them matched directly with loads, allowing them to bypass rather than bog down the lengthy interconnection queue process.”
The bill is opposed by the state’s large electric IOUs, who contend SB 1018 “will create a market for unregulated utilities and lacks customer protections” and “would undermine grid planning, reliability, and safety.”
The bill is also opposed by the Public Advocates Office—an independent ratepayer advocate within the CPUC—which asserts the bill “could result in utility costs being shifted unfairly to non-participating customers…raises safety implications…and creates reliability concerns.”
Analysis Prepared by: Jay Dickenson / APPR. / (916) 319-2081
Date of Hearing: July 1, 2024
ASSEMBLY COMMITTEE ON UTILITIES AND ENERGY
Cottie Petrie-Norris, Chair
SBPCA Bill Id:SB 1018
Author:(Becker) – As Amended Ver:June 20, 2024
SENATE VOTE: 30-8
SUBJECT: Electricity
SUMMARY: Provides two exemptions – one from state and one from federal rules regulating utilities – for entities that engage in selling electricity from solar and wind generation if those entities provide electric generation exclusively for electrolytic hydrogen production and electrifying industrial heat processes. Specifically, this bill:
- Exempts from the definition of “electrical corporation” under California law an entity selling solar or wind electric generation of at least five megawatts (MW), if the generated electricity is transmitted solely using private electric lines to a separate facility owned by a different entity that uses the electricity exclusively for either:
- Producing hydrogen from electrolysis.
- Providing industrial process heat, including the use of a thermal energy storage system.
- Specifies that exempt solar and wind generation facilities may have associated battery storage on-site, and may not serve departing load.
- Requires the California Public Utilities Commission (CPUC) to establish a tariff by July 1, 2026, that allows for solar and wind generation facilities, and associated storage, greater than 80 MWs providing retail service to qualified self-generation projects (QSGP), as defined, to be exempt from federal Public Utility Holding Company Act (PUHCA) rules due to designation as an exempt wholesale generator.
- Specifies the tariff shall be structured such that electrical corporations serve as contractual intermediaries between the generation facilities and the customer, where the rates for both purchasing and reselling the electricity will be at cost, but including an adder for incremental administrative or operational costs to be paid to the electrical corporation serving as the intermediary.
- Specifies customers may take supplemental service under standard tariffs, and that generation facilities may also participate in wholesale electricity markets.
- Defines “qualified self-generation project” (QSGP) as a customer that meets all of the following:
- Uses electricity from either solar or wind technology, or storage facilities exclusively charging from solar or wind technology, that is transmitted directly to the customer’s QSGP;
- Bears responsibility for the cost of any infrastructure constructed for the purpose of connecting the QSGP with the generation facilities;
- Consumes the electricity for electrolytic hydrogen production or industrial process heat.
EXISTING LAW:
- Authorizes the California Public Utilities Commission (CPUC) to regulate public utilities, including electric and natural gas corporations and establish rates for these utilities. (Public Utilities Code § 201 et. seq.)
- Defines an “electrical corporation” as every corporation or person owning, controlling, operating, or managing any electric plant for compensation in the state, except where electricity is generated on or distributed by the producer through private property solely for its own use or the use of its tenants and not for sale or transmission to others; establishes limited exemptions to the definition of an electrical corporation; and generally designates any entity that sells electricity to more than two contiguous parcels or across the street as an “electrical corporation.” (Public Utilities Code § 218)
- Subjects entities who directly, or indirectly through affiliates or holding companies, own or operate facilities used for the generation, transmission, or distribution of electric energy or natural gas for sale to various regulations under the Federal Energy Regulatory Commission (FERC), including requiring access to books and records, requiring specified record keeping and accounting practices, and federal rate regulation. (Public Utility Holding Company Act of 2005 [18 Code of Federal Regulations 365-366, Vol. 71 FR 28457])
- Exempts specified Qualifying Facilities (those under 80 megawatts [MWs]), Exempt Wholesale Generators, and foreign utility companies from the Public Utility Holding Company Act of 2005. (18 Code of Federal Regulations § 366.3)
- Defines an “exempt wholesale generator” (EWG) as any person determined by FERC to be engaged directly, or indirectly through one or more affiliates, and exclusively in the business of owning or operating (or both) eligible facilities and selling electric energy at wholesale. Specifies an “affiliate” for these purposes as any company in which the person claiming EWG status owns 5% or greater voting interest. (18 Code of Federal Regulations § 366.1)
FISCAL EFFECT: Unknown. This measure has not received a fiscal committee hearing, due to a determination by the Senate Committee on Appropriations, pursuant to Senate Rule 28.8, that the cost of implementing this bill is not significant. However, amendments taken in this house added new requirements on the CPUC to develop a tariff that may result in new costs to the state.
BACKGROUND:
Over-the-Fence – The definition of “electrical corporations” provided in Public Utilities Code § 218 is the subject of a long-standing point of division colloquially known as the “over-the-fence” rule. Current statute limits the ability of an entity to serve multiple customers (greater than two on adjacent properties) if that entity is not an electric utility. Statute ensures regulatory oversight of a private entity providing electric service for compensation, that is not otherwise a corporation or person employing cogeneration, landfill gas technology, or digester gas technology. The implications for defining an electrical corporation are to ensure adequate regulatory oversight, including the bedrock principles of safe, reliable, and affordable service. The CPUC has regulatory oversight of all electrical corporations, maintaining broad authority, including the ability to review books, set rates, fine and penalize, and to revoke licenses to operate. However, many private entities seeking unique electrical generation arrangements – such as microgrid developers – see these legal limitations as a hurdle to deploying greater use of emergent technologies.
Costs of Hydrogen Production – Most of the continued operations costs to developers for producing hydrogen in California will arise from the purchase of electricity, and vary by the utility serving the hydrogen production facility. A recent study by the National Renewable Energy Lab projected the cheapest way to produce hydrogen in California is to have the hydrogen production plant connected directly to the California Independent System Operator (CAISO) transmission system.[1] Such a scenario, under 2019 tariffs and rates, would be approximately $3 per kg,[2] or $24 per million British thermal units (MMBtu).[3] (For comparison, fossil natural gas prices in the state average around $9.40/MMBtu, while biomethane prices average around $17.70/MMBtu.[4] So even these “cheapest” hydrogen prices are costly.) The statewide cap on direct access currently prevents this pathway from new development in California, but it served as a base case for the study.[5]
The next cheapest pathway found in the study involved hydrogen production directly connected to onsite renewable generation, via an electrolyzer combined with a wind plant operating under a Pacific Gas and Electric time-of-use tariff, at $4.29/kg or $34.3/MMBtu.[6] If colocation of a renewable resource was not considered, the cheapest pathway was a hydrogen production facility taking grid power under Southern California Edison’s real-time pricing tariff, at $4.7/kg or $37.6/MMBtu. (Note these models optimized for the large IOU rates; they did not run the models against the publicly owned utility rates, which are typically lower.) These pathways differ largely in how the electric upgrade costs will be borne by the hydrogen facility. In the colocation scenario, the obligation to install onsite renewable generation would fall on the hydrogen developer, presumably as part of the financing for the hydrogen facility. In the grid-connected scenario, any additional electricity needed to serve the load of the hydrogen production facility would presumably be paid for by utility ratepayers.
Industrial Process Heat – According to the Department of Energy, industrial process heat is the use of thermal energy to produce, treat, or alter manufactured goods. This process often employs steam, hot water, or other hot gases. Process heating systems raise or maintain the temperature of materials involved in the manufacturing process, such as the melting of scrap in electric arc furnaces to make steel, separating components of crude oil in petroleum refining, drying paint in automobile manufacturing, or processing food for safe consumption. Application temperatures range from 80°C, used to pasteurize milk and cream, to well over 1000°C to make cement. Process heat is the most significant source of energy use and greenhouse gas emissions in the industrial sector, accounting for about 50% of all onsite energy use and 30% of greenhouse gas emissions.[7] The high energy demand of industrial process heat applications makes any effort to decarbonize the process extremely sensitive to electricity price signals.
COMMENTS:
- Author’s Statement. According to the author, “As California transitions to net-zero emissions, some of the toughest challenges are in reducing greenhouse gas emissions from “hard-to-abate” industrial or transportation uses. Green hydrogen and thermal batteries are two of the most promising options for tackling those hard-to-abate emissions, but to be successful as climate solutions, both need access to very large amounts of low-cost, clean electricity – while avoiding adding cost or putting additional stress on the grid. Powering hydrogen production or thermal batteries by connecting them directly to renewable energy (“off-grid”) would give them access to some of the cheapest sources of energy. It would also guarantee that the hydrogen or heat is powered by clean energy without adding stress to the grid. Unfortunately, this off-grid option is blocked today. SB 1018 solves this problem by creating a narrow, new exception that allows a large solar or wind generator (spread across many parcels) to sell their output directly to a single customer who will use that power for producing hydrogen or providing industrial heat. It also directs the PUC to create a work-around for large projects that could be regulated as public utility holding companies under federal law if they both provide electricity directly to an affiliated hydrogen facility (under the new PUC 218 exception) and also sell excess electricity into the wholesale market. These changes will support the growth of green hydrogen and industrial electrification in a way that will ensure it makes use of clean energy and does not impact electricity rates or grid reliability.”
- Need for the bill. This bill provides two avenues for regulatory relaxation – one of state rules, through an outright exemption and one of federal rules, through a contractual work-around – for specified hydrogen production and industrial heat processing powered by solar or wind facilities. The author motivates the need for these avenues for these specified project types because of the projects’ sensitivity to electricity prices, as both electrolytic hydrogen production and industrial process electrification require a substantial amount of electricity. The author likewise raises the ability to connect these facilities “off-grid” with renewables as the cheapest way to ensure projects are zero-emission, as they would bypass the extra costs for transmission, distribution, taxes, fees, and utility profits, while ensuring the clean power is delivered directly to the production facility.
However, the economics of how such an arrangement – where the production facilities, generating facilities, and electrical lines are all privately owned and presumably part of the capitalized cost of the project – compares against the cost to take directly from the grid is unclear. As noted above for hydrogen production facilities, unique arrangements that colocate resources near production facilities actually are modeled to provide cheaper electricity than arrangements utilizing California grid power. As California’s investor-owned utility electric rates continue to rise, the economics may further advantage non-traditional onsite generator arrangements for these high load applications.
- Peering Over the Fence. Existing law generally classifies any entity selling electricity to more than two adjacent parcels as an electrical corporation, subject to full regulation by the CPUC. While existing law establishes very limited exemptions to this definition, those exemptions generally only apply to electricity generated for on-site energy consumption or electricity provided to no more than two parcels that are contiguous to the property on which the electricity is generated. These restrictions are generally known as the “over-the-fence” rules due to the requirement that parcels be adjacent to each other. This bill establishes a new exemption to the “over-the-fence” rules for certain wind and solar projects that provide electricity solely over private lines to another entity exclusively for producing electrolytic hydrogen and electrifying industrial heat process. This bill specifies that this exemption can only be provided for generation serving new electrical loads; as a result, this exemption may not be used to enable an existing electrical customer to leave their existing utility service. In this way, the exemption provided under this bill is unique from past “over-the-fence” efforts, where often departing loads were the intended recipient of the new arrangement and the cost savings were provided to these loads through bypassing traditional departing load charges. To the extent that a hydrogen production or industrial facility seeks to co-locate new renewable generation to support their activities, it may not be feasible to site a sufficient amount of generation on just two adjacent parcels even when such parcels are available.
- Eroding CPUC Oversight. The CPUC’s “over-the-fence” rules have been the subject of intense debate in recent legislation and CPUC decisions.[8] The over-the-fence exclusion established under this bill constitutes a substantial departure from existing policy by allowing certain generators to sell electricity to off-takers that are not on adjacent properties without those generators being classified as an electrical corporation. As a result, this bill prevents those generators and their facilities from facing CPUC regulation; regulation that seeks to protect consumers from unfair prices, unsafe or unreliable infrastructure, or unscrupulous marketers. This bill specifies the off-taking customers will be commercial operations, presumably savvy enough in their understanding of electricity pricing and contracting that foregoing CPUC rate protections or remedies is an absorbable corporate risk.
This bill’s exemption also applies solely to those facilities that deliver the generation entirely over private electrical facilities. This limitation may reduce the likelihood that developers will establish generation facilities in distant locations from their off-takers; however, this bill does not require generation facilities to be located within a certain distance from associated off-takers. While both public and private electrical facilities have ignited catastrophic wildfires in the past, the CPUC’s authority over electrical corporations enables them to direct electrical corporations to take certain steps to mitigate the potential for ignitions and catastrophic fires. As we have found in the wildfire context, the safety of utility infrastructure goes beyond the safety of the owner or purchaser of that electricity, but serves the safety of the general public as well. As such, the committee recommends requiring these private electrical lines, if located beyond the property where the generator or project are located, be subject to all applicable CPUC general orders, and that the developer be subject to wildfire mitigation plan filings as required for other private transmission operators if the lines are located in high fire threat districts.
- What’s Up Your Sleeve? The second avenue to bypass regulatory oversight provided under this bill is through a contractual arrangement where an electrical corporation serves as an intermediary on paper to take financial ownership but not the physical delivery of the electricity; although this arrangement is not explicit in the bill and is left for the CPUC to articulate in establishing a tariff. Such an arrangement is known as a “sleeve” transaction. This avenue is available under this bill to any solar or wind generating facility greater than 80 MWs, as facilities under 80 MW are considered Qualifying Facilities already exempt from most FERC regulations. This arrangement would seemingly allow for generating facilities to oversize their production so that some would be sent to the electricity grid wholesale, with the facility acting as a traditional exempt wholesale generator, while a portion would be sent to the electrolyzer or industrial heat facility to serve that load at retail. Otherwise, if they exported all their power onto the grid, the generator would already be considered a EWG and exempt from FERC regulation; and if they only sent their power to the retail load via private lines they would only need the over-the-fence exemption provided in this measure.
It is this secondary retail arrangement alongside the wholesale exporting of power that would subject the facility to FERC regulation under the Public Utility Holding Company Act of 2005. As a result, the scheme envisioned by this bill would ask the electrical corporation to be the financial intermediary of the retail transaction, so that on paper, the generating facility is not technically serving retail customers (i.e. the hydrogen or industrial heat facility), and thus bypassing FERC rules. Supporters of this arrangement evoke a similarity between what is being proposed and traditional self-generation arrangements like rooftop solar, with the distinction being the magnitude of the MWs.[9] However, the legal robustness of the proposed arrangement is unknown. The committee is unaware how and where this arrangement might be deployed to date, or whether FERC has issued any guidance or rulings that such sleeve transactions are permitted. (FERC has issued guidance and does allow for sleeve transactions in other circumstances.)[10]
An additional concern with such an arrangement is whether it is operating as a “sham transaction,” which is forbidden under the Federal Power Act (FPA). Sham transactions occur when an entity financially trades electricity and obtains wheeling services without actually owning any facilities that distribute the electricity. FPA § 212(h)(1) precludes FERC from issuing any order that requires the transmission of energy directly to an ultimate consumer (direct retail wheeling). FPA § 212(h)(2) prohibits sham transactions that are intended to evade the ban on direct retail wheeling.[11] The "sham" prohibition precludes FERC from issuing any order under the FPA that is conditioned upon or requires the transmission of electric energy to, or for the benefit of, an entity if such electric energy would be sold by that entity directly to an ultimate consumer, unless certain conditions are met. One of those conditions is if the entity “utilizes transmission or distribution facilities that it owns or controls to deliver all such electric energy.”[12] In the circumstance envisioned by this bill, electrical corporations would potentially be running the “sham transaction,” unless some element of the electricity from the generating facility to the electrolyzer or industrial heat facility utilizes the IOU’s facilities.
To the committee’s knowledge, the arrangement contemplated under this measure would be unique in California law, uncertain in federal preemption, and provide special treatment to these generators, resulting in large uncertainty and risk as to the consequence of granting such statutory favor. These provisions, however, are subject to the CPUC development of a tariff that expressly mandates the arrangement must be “just and reasonable.” Just how the CPUC may contemplate such a directive in this arrangement is also uncertain.
- Further Amendments. Many customer protections – such as requiring that the generator only serves new load or that only private utility lines are utilized – are present in the over-the-fence exemption but absent in the tariff provisions of this bill. The author has expressed this was unintentional. Moreover, given the unique financial arrangement envisioned by the tariff, it may be prudent to expressly require that no cost shift occurs between participants and nonparticipants. Finally, additional drafting issues are needed to clarify elements of the tariff, such as the striking of “contractual” and restating the “customer” as the QSGP. The committee recommends adopting all of these amendments.
- Related Legislation.
AB 2083 (Berman, 2024) requires the California Energy Commission (CEC) to assess the state’s potential to reduce emissions from high-heat industrial processes. Status: set for hearing on July 3rd, in the Senate Committee on Environmental Quality.
AB 3107 (Connolly) requires the CEC to conduct a study on the benefits of microgrids for local governments and communities, and submit a report on the study to the Legislature by January 1, 2027. Prior version of the measure exempted microgrid operators from the statutory definition of “electrical corporation.” Status: Held in the Assembly Committee on Appropriations.
AB 3111 (Calderon) requires various reporting from distributed energy resources (DER) and aggregations of those resources. A prior version of the measure required DER applicants to attest, under penalty of perjury, to a prescribed definition of “electrical corporation.” Status: set for hearing on July 2nd, in the Senate Committee on Energy, Utilities and Communications.
SB 1420 (Caballero) provides for expedited California Environmental Quality Act (CEQA) and California Energy Commission (CEC) review for hydrogen production facilities that have received state or federal funding. Status: set for hearing on July 1st, in the Assembly Committee on Natural Resources.
SB 993 (Becker) requires the CPUC to consider establishing a new tariff to encourage new grid-responsive electricity consumption for electrolytic hydrogen production and electrifying industrial heat processes. Status: Held in the Senate Committee on Appropriations.
- Previous Legislation.
AB 841 (Berman, 2023) would have required the CEC to develop an Industrial Heat Electrification Roadmap to identify opportunities to decarbonize certain high-heat industrial processes through electrification. Status: Held in the Senate Committee on Appropriations.
SB 1339 (Stern) required the CPUC and local publicly owned electric utilities to take a number of steps to encourage the commercialization of microgrids, including adopting tariffs to support microgrids. Status: Chapter 556, Statutes of 2018.
REGISTERED SUPPORT / OPPOSITION:
Support
350 Humboldt
350 Humboldt: Grass Roots Climate Action
350 Sacramento
Advanced Energy Economy
Advanced Energy United
California Hydrogen Coalition
California State Association of Electrical Workers
California State Pipe Trades Council
Climate Action California
Coalition of California Utility Employees
Green Hydrogen Coalition
Industrious Labs
Intersect Power
Menlo Spark
Nrdc Action Fund
Project 2030
Rondo Energy
Sierra Club
Solar Energy Industry Association
The Climate Center
The Climate Reality Project: Silicon Valley
Western States Council Sheet Metal, Air, Rail and Transportation
Opposition
Pacific Gas and Electric Company
Public Advocates Office
San Diego Gas and Electric Company
Southern California Edison
Analysis Prepared by: Laura Shybut / U. & E. / (916) 319-2083
The actual cheapest pathway was a scenario of the hydrogen production facility using federal hydropower; however the author’s noted it is institutionally complicated and may be legally infeasible. Nevertheless it produced costs approaching the U.S. DOE’s $1/kg target. Pg. 25, Guerra Fernández, O.J., et al., NREL, Integrating Hydrogen Production and Electricity Markets: Analytical Insights from California, June 2022; https://www.nrel.gov/docs/fy22osti/80902.pdf ↑
Guerra Fernández, O.J., et al., NREL, 2022, Ibid. ↑
Using the conversion of $1/kg = ~$8/MMBtu; Seeking Alpha, ”Hydrogen vs. Natural Gas for Electric Power Generation;” December, 2, 2020; https://seekingalpha.com/article/4392471-hydrogen-vs-natural-gas-for-electric-power-generation https://seekingalpha.com/article/4392471-hydrogen-vs-natural-gas-for-electric-power-generation ↑
D. 22-02-025, Decision Implementing Senate Bill 1440 Biomethane Procurement Program, R. 13-02-008, February 24, 2022; https://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M454/K335/454335009.PDF ↑
PUC § 365.1 ↑
Pg. v, Guerra Fernández, O.J., et al., NREL, 2022. Ibid. ↑
2018 Manufacturing Energy and Carbon Footprints; https://www.energy.gov/eere/iedo/manufacturing-energy-and-carbon-footprints-2018-mecs ↑
D. 21-01-018 ↑
Orders of magnitude difference in this case. Residential rooftop solar averages below 10kW; these generators are over 80MW. ↑
ConocoPhillips Co., 175 FERC ¶ 61,226 (2021) (Guidance Order) ↑
16 U.S.C. § 824k(h)(2) (1994) ↑
16 U.S.C. § 824k(h)(2)(B); https://www.law.cornell.edu/uscode/text/16/824k ↑
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 1018 |
THIRD READING
Bill No: SB 1018
Author: Becker (D)
Introduced: 2/5/24
Vote: 21
SENATE ENERGY, U. & C. COMMITTEE: 14-3, 4/16/24
AYES: Bradford, Ashby, Becker, Caballero, Dodd, Durazo, Eggman, Gonzalez, Limón, Min, Newman, Rubio, Skinner, Stern
NOES: Dahle, Seyarto, Wilk
NO VOTE RECORDED: Grove
SENATE APPROPRIATIONS COMMITTEE: Senate Rule 28.8
SUBJECT: Electrical corporation: definition: exclusion of certain solar or wind generating technologies
SOURCE: Author
DIGEST:
This bill exempts certain entities selling solar and wind electrical generation from the definition of an “electrical corporation” if those entities provide electric generation solely over private lines exclusively for electrolytic hydrogen production and electrifying industrial heat processes.
ANALYSIS:
Existing law:
- Authorizes the California Public Utilities Commission (CPUC) to regulate public utilities, including electric and natural gas corporations and establish rates for these utilities. (Public Utilities Code §201 et. seq.)
- Defines an “electrical corporation” as every corporation or person owning, controlling, operating, or managing any electric plant for compensation in the state, except where electricity is generated on or distributed by the producer through private property solely for its own use or the use of its tenants and not for sale or transmission to others; establishes limited exemptions to the definition of an electrical corporation; and generally designates any entity that sells electricity to more than two contiguous parcels or across the street as an “electrical corporation.” (Public Utilities Code §218)
This bill:
- Exempts an entity selling solar or wind electric generation of at least five megawatts (MW) from the definition of an electrical corporation, if the electricity is transmitted solely using private electric lines to a separate facility owned by a different entity that uses the electricity exclusively for the one of following:
- Producing hydrogen from electrolysis.
- Providing industrial process heat, including the use of a thermal energy storage system.
- Specifies that exempt solar and wind generation facilities may have associated battery storage on-site, and exempt generation may not serve departing load.
Background
- Bill aims to modify “over-the-fence” rules for certain new loads. Existing law generally classifies any entity selling electricity to more than two adjacent parcels as an electrical corporation, subject to full regulation by the CPUC. While existing law establishes very limited exemptions to this definition, those exemptions generally only apply to electricity generated for on-site energy consumption or electricity provided to no more than two parcels that are contiguous to the property on which the electricity is generated. These restrictions are generally known as the “over-the-fence” rules due to the requirement that parcels be adjacent to each other. This bill establishes a new exemption to the “over-the-fence” rules for certain wind and solar projects that provide electricity solely over private lines to another entity exclusively for producing electrolytic hydrogen and electrifying industrial heat process. This bill specifies that this exemption can only be provided for generation serving new electrical loads; as a result, this exemption may not be used to enable an existing electrical customer to use this exemption to remove existing demand from electric utilities’ existing load profiles.
Both electrolytic hydrogen production and industrial process electrification require a substantial amount of electricity. To the extent that a hydrogen production or industrial facility seeks to co-locate new renewable generation to support their activities, it may not be feasible to site a sufficient amount of generation on just two adjacent parcels even when such parcels are available. The over-the-fence exclusion established under this bill constitutes a substantial departure from existing policy by allowing certain generators to sell electricity to off-takers that are not on adjacent properties without those generators being classified as an electrical corporation. As a result, this bill prevents those generators and their facilities from facing CPUC regulation. This bill’s exemption applies solely to those facilities that deliver the generation entirely over private electrical facilities. This limitation may reduce the likelihood that developers will establish generation facilities in distant locations from their off-takers; however, this bill does not require generation facilities to be located within a certain distance from associated off-takers.
- Many obligations and protections are baked into CPUC regulatory powers. The CPUC’s “over-the-fence” rules have been the subject of intense debate in recent legislation and CPUC decisions. Following the passage of SB 1339 (Stern, Chapter 556, Statutes of 2018), the CPUC opened a proceeding to implement the bill’s requirements (Rulemaking R.19-09-009). As part of this proceeding, multiple parties attempted to assert that the CPUC should limit the application of the “over-the-fence” rule for determining the number of parcels a microgrid can serve. In its decision adopting measures to implement SB 1339, the CPUC responded to parties’ assertions that the over-the-fence rules unduly limited microgrid deployment. The CPUC’s decision (D. 21-01-018) states:
Without our oversight, there is no way to ensure these entities operate their assets safely and reliably and are not charging unreasonable rates when providing this essential service. Yet, that is precisely the outcome sought by some. We reject their push to permit – through this docket – the establishment of private utilities to sell power under contractual arrangements to nearby third-parties without any Commission oversight and without regard to the existing regulatory and legislative requirements that are reflected in Section 218 and other parts of the Public Utilities Code.
The CPUC’s decision underscores the extent to which a number of obligations and protections in the energy sector stem from the CPUC’s authority to regulate electrical corporations. While this bill directly addresses the statutory requirements of Public Utilities Code Section 218 and is not related to microgrid commercialization, it poses similar questions about the extent to which broader exemptions to over-the-fence requirements weaken CPUC oversight and limit the extent to which the state can ensure that certain facilities and electricity consumption are aligned with state goals. Concerns about expanding over-the-fence exemptions to properties that are not contiguous may be particularly acute for utility safety requirements. While both public and private electrical facilities have ignited catastrophic wildfires in the past, the CPUC’s authority over electrical corporations enables the commission to direct electrical corporations to take certain steps to mitigate the potential for ignitions and catastrophic fires. It is unclear if the interests of project developers wishing to create larger off-site generation opportunities without CPUC regulation can be balanced against the manner in which regulatory oversight in the electric utility sector is the primary mechanism through which the state ensures the reliability, safety and affordability of electrical services and facilities.
Related/Prior Legislation
SB 993 (Becker, 2024) requires the CPUC to consider establishing a new tariff to encourage new grid-responsive electricity consumption for electrolytic hydrogen production and electrifying industrial heat processes. The bill is pending in the Senate Appropriations Committee.
AB 2083 (Berman, 2024) requires the California Energy Commission (CEC) to assess the state’s potential to reduce emissions from high-heat industrial processes. The bill is pending in the Assembly Appropriations Committee.
AB 841 (Berman, 2023) would have required the CEC to develop an Industrial Heat Electrification Roadmap to identify opportunities to decarbonize certain high-heat industrial processes through electrification. The bill was held in the Senate Appropriations Committee.
AB 2667 (Friedman, 2022) would have established an incentive program to encourage the development of distributed energy generation. The bill also included provisions affirming the definition of an electrical corporation in Public Utilities Code Section 218. The bill failed passage on the Senate Floor.
SB 1339 (Stern, Chapter 556, Statutes of 2018) required the CPUC and local publicly owned electric utilities to take a number of steps to encourage the commercialization of microgrids, including adopting tariffs to support microgrids.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: No
SUPPORT: (Verified 4/30/24)
350 Humboldt
350 Sacramento
Advanced Energy Economy
California Hydrogen Coalition
California State Association of Electrical Workers
California State Pipe Trades Council
Climate Action California
Coalition of California Utility Employees
Green Hydrogen Coalition
Industrious Labs
Intersect Power
Menlo Spark
Natural Resources Defense Council
NRDC Action Fund
Project 2030
Rondo Energy
Sierra Club California
Solar Energy Industries Association
The Climate Center
The Climate Reality Project: Silicon Valley
OPPOSITION: (Verified 4/30/24)
Pacific Gas and Electric Company
San Diego Gas and Electric Company
Southern California Edison
ARGUMENTS IN SUPPORT: According to the author:
Powering hydrogen production or thermal batteries by connecting them directly to renewable energy (“off-grid”) would give them access to some of the cheapest sources of energy. It would also guarantee that the hydrogen or heat is powered by clean energy without adding stress to the grid. Unfortunately, this off-grid option is blocked today. Renewable energy can only be supplied directly “behind-the-meter” if it falls within one of the exceptions within PUC 218, the so-called “over-the-fence rule.” Otherwise, the renewable generator is treated as a public utility, subject to extensive regulatory oversight. Today, this is generally restricted to generation that is on the same parcel of land or an adjacent parcel (“over-the-fence”). That works fine for rooftop solar on a home but is not sufficient for the megawatts of solar, spread across many acres of land, that would be needed for even a modest hydrogen facility.
SB 1018 solves this problem by creating a narrow, new exception within PUC 218 that allows a large solar or wind generator (spread across many parcels) to sell their output directly to a single customer who will use that power for producing hydrogen or providing industrial heat. This change will support the growth of green hydrogen and industrial electrification in a way that will ensure it makes use of clean energy and does not impact electricity rates or grid reliability.
ARGUMENTS IN OPPOSITION: Pacific Gas and Electric Company, San Diego Gas and Electric Company, and Southern California Edison, the three large electric investor-owned utilities (IOUs) oppose this bill. They argue that it would create a market for unregulated utilities, limit consumer protections, and undermine grid reliability and safety. In opposition, the IOUs state:
The bill would enable any number of private companies that generate wind and solar to run private power lines without limitations to service area boundaries. This could severely hamper the Joint Utilities’ ability to forecast for increased demand or construct new facilities to connect future energy resources that would service the vast majority of Californians who remain utility customers. State policy has historically focused on building an efficient, safe grid that will meet customer needs. This bill directly contradicts that policy and could threaten reliability and clean energy goals.
SB 1018 attempts to achieve a number of objectives toward a clean energy future—promotion of on-site hydrogen production and clean industrial process heat—that can be addressed through existing pathways.
For example, the Joint Utilities already provide renewable energy to customers, subject to the amount in their procurement portfolios. There is no need to modify the scope of “electrical corporation” and threaten reliability and clean energy goals.
Prepared by: Sarah Smith / E., U. & C. / (916) 651-4107
5/1/24 12:28:32
SENATE COMMITTEE ON ENERGY, UTILITIES AND COMMUNICATIONS
Senator Steven Bradford, Chair
2023 - 2024 Regular
Bill No: Hearing Date: 4/16/2024
Author: | |||
Version: | Introduced | ||
Urgency: | Fiscal: | ||
Consultant: | |||
SUBJECT:
DIGEST: This bill exempts certain entities selling solar and wind electrical generation from the definition of an “electrical corporation” if those entities provide electric generation solely over private lines exclusively for electrolytic hydrogen production and electrifying industrial heat processes.
ANALYSIS:
Existing law:
- Authorizes the California Public Utilities Commission (CPUC) to regulate public utilities, including electric and natural gas corporations and establish rates for these utilities. (Public Utilities Code §201 et. seq.)
- Defines an “electrical corporation” as every corporation or person owning, controlling, operating, or managing any electric plant for compensation in the state, except where electricity is generated on or distributed by the producer through private property solely for its own use or the use of its tenants and not for sale or transmission to others. Existing law establishes limited exemptions to the definition of an electrical corporation. Existing law generally designates any entity that sells electricity to more than two contiguous parcels or across the street as an “electrical corporation.” (Public Utilities Code §218)
This bill:
- Exempts an entity selling solar or wind electric generation of at least five megawatts (MW) from the definition of an electrical corporation, if the electricity is transmitted solely using private electric lines to a separate facility owned by a different entity that uses the electricity exclusively for the one of following:
- Producing hydrogen from electrolysis.
- Providing industrial process heat, including the use of a thermal energy storage system.
- This bill specifies that exempt solar and wind generation facilities may have associated battery storage on-site, and exempt generation may not serve departing load.
Background
Bill aims to modify “over-the-fence” rules for certain new loads. Existing law generally classifies any entity selling electricity to more than two adjacent parcels as an electrical corporation, subject to full regulation by the CPUC. While existing law establishes very limited exemptions to this definition, those exemptions generally only apply to electricity generated for on-site energy consumption or electricity provided to no more than two parcels that are contiguous to the property on which the electricity is generated. These restrictions are generally known as the “over-the-fence” rules due to the requirement that parcels be adjacent to each other. This bill would establish a new exemption to the “over-the-fence” rules for certain wind and solar projects that provide electricity solely over private lines to another entity exclusively for producing electrolytic hydrogen and electrifying industrial heat process. This bill specifies that this exemption can only be provided for generation serving new electrical loads; as a result, this exemption may not be used to enable an existing electrical customer to use this exemption to remove existing demand from electric utilities’ existing load profiles.
Both electrolytic hydrogen production and industrial process electrification require a substantial amount of electricity. To the extent that a hydrogen production or industrial facility seeks to co-locate new renewable generation to support their activities, it may not be feasible to site a sufficient amount of generation on just two adjacent parcels even when such parcels are available. The over-the-fence exclusion established under this bill would constitute a substantial departure from existing policy by allowing certain generators to sell electricity to off-takers that are not on adjacent properties without those generators being classified as an electrical corporation. As a result, this bill would prevent those generators and their facilities from facing CPUC regulation. This bill’s exemption applies solely to those facilities that deliver the generation entirely over private electrical facilities. This limitation may reduce the likelihood that developers will establish generation facilities in distant locations from their off-takers; however, this bill does not require generation facilities to be located within a certain distance from associated off-takers.
Many obligations and protections are baked into CPUC regulatory powers. The CPUC’s “over-the-fence” rules have been the subject of intense debate in recent legislation and CPUC decisions. Following the passage of SB 1339 (Stern, Chapter 556, Statutes of 2018), the CPUC opened a proceeding to implement the bill’s requirements (Rulemaking R.19-09-009). As part of this proceeding, multiple parties attempted to assert that the CPUC should limit the application of the “over-the-fence” rule for determining the number of parcels a microgrid can serve. In its decision adopting measures to implement SB 1339, the CPUC responded to parties’ assertions that the over-the-fence rules unduly limited microgrid deployment. The CPUC’s decision (D. 21-01-018) states:
Without our oversight, there is no way to ensure these entities operate their assets safely and reliably and are not charging unreasonable rates when providing this essential service. Yet, that is precisely the outcome sought by some. We reject their push to permit – through this docket – the establishment of private utilities to sell power under contractual arrangements to nearby third-parties without any Commission oversight and without regard to the existing regulatory and legislative requirements that are reflected in Section 218 and other parts of the Public Utilities Code.
The CPUC’s decision underscores the extent to which a number of obligations and protections in the energy sector stem from the CPUC’s authority to regulate electrical corporations. While this bill directly addresses the statutory requirements of Public Utilities Code §218 and is not related to microgrid commercialization, it poses similar questions about the extent to which broader exemptions to over-the-fence requirements weaken CPUC oversight and limit the extent to which the state can ensure that certain facilities and electricity consumption are aligned with state goals. Concerns about expanding over-the-fence exemptions to properties that are not contiguous may be particularly acute for utility safety requirements. While both public and private electrical facilities have ignited catastrophic wildfires in the past, the CPUC’s authority over electrical corporations enables the commission to direct electrical corporations to take certain steps to mitigate the potential for ignitions and catastrophic fires. It is unclear if the interests of project developers wishing to create larger off-site generation opportunities without CPUC regulation can be balanced against the manner in which regulatory oversight in the electric utility sector is the primary mechanism through which the state ensures the reliability, safety and affordability of electrical services and facilities.
Prior/Related Legislation
SB 993 (Becker, 2024) requires the CPUC to consider establishing a new tariff to encourage new grid-responsive electricity consumption for electrolytic hydrogen production and electrifying industrial heat processes. The bill is pending in the Senate Energy, Utilities and Communications Committee.
AB 2083 (Berman, 2024) requires the California Energy Commission (CEC) to assess the state’s potential to reduce emissions from high-heat industrial processes. The bill is currently pending in the Assembly.
AB 841 (Berman, 2023) would have required the CEC to develop an Industrial Heat Electrification Roadmap to identify opportunities to decarbonize certain high-heat industrial processes through electrification. The bill was held in the Senate Appropriations Committee.
AB 2667 (Friedman, 2022) would have established an incentive program to encourage the development of distributed energy generation. The bill also included provisions affirming the definition of an electrical corporation in Public Utilities Code §218.
SB 1339 (Stern, Chapter 556, Statutes of 2018) required the CPUC and local publicly owned electric utilities to take a number of steps to encourage the commercialization of microgrids, including adopting tariffs to support microgrids.
FISCAL EFFECT: Appropriation: Fiscal Com.: Local:
SUPPORT:
350 Humboldt
350 Sacramento
Advanced Energy Economy
California Hydrogen Coalition
California State Association of Electrical Workers
California State Pipe Trades Council
Climate Action California
Coalition of California Utility Employees
Green Hydrogen Coalition
Industrious Labs
Intersect Power
Natural Resources Defense Council and NRDC Action Fund
Rondo Energy
Sierra Club California
The Climate Reality Project: Silicon Valley
OPPOSITION:
Pacific Gas and Electric Company
San Diego Gas and Electric Company
Southern California Edison
ARGUMENTS IN SUPPORT: According to the author:
Powering hydrogen production or thermal batteries by connecting them directly to renewable energy (“off-grid”) would give them access to some of the cheapest sources of energy. It would also guarantee that the hydrogen or heat is powered by clean energy without adding stress to the grid. Unfortunately, this off-grid option is blocked today. Renewable energy can only be supplied directly “behind-the-meter” if it falls within one of the exceptions within PUC 218, the so-called “over-the-fence rule.” Otherwise, the renewable generator is treated as a public utility, subject to extensive regulatory oversight. Today, this is generally restricted to generation that is on the same parcel of land or an adjacent parcel (“over-the-fence”). That works fine for rooftop solar on a home but is not sufficient for the megawatts of solar, spread across many acres of land, that would be needed for even a modest hydrogen facility.
SB 1018 solves this problem by creating a narrow, new exception within PUC 218 that allows a large solar or wind generator (spread across many parcels) to sell their output directly to a single customer who will use that power for producing hydrogen or providing industrial heat. This change will support the growth of green hydrogen and industrial electrification in a way that will ensure it makes use of clean energy and does not impact electricity rates or grid reliability.
ARGUMENTS IN OPPOSITION: The three large electric investor-owned utilities (IOUs) oppose this bill, and they argue that it would create a market for unregulated utilities, limit consumer protections, and undermine grid reliability and safety. In opposition, the IOUs state:
The bill would enable any number of private companies that generate wind and solar to run private power lines without limitations to service area boundaries. This could severely hamper the Joint Utilities’ ability to forecast for increased demand or construct new facilities to connect future energy resources that would service the vast majority of Californians who remain utility customers. State policy has historically focused on building an efficient, safe grid that will meet customer needs. This bill directly contradicts that policy and could threaten reliability and clean energy goals.
SB 1018 attempts to achieve a number of objectives toward a clean energy future—promotion of on-site hydrogen production and clean industrial process heat—that can be addressed through existing pathways. For example, the Joint Utilities already provide renewable energy to customers, subject to the amount in their procurement portfolios. There is no need to modify the scope of “electrical corporation” and threaten reliability and clean energy goals.
-- END --
Discussed in Hearing
Assembly Standing Committee on Utilities and Energy
Senate Floor
Senate Standing Committee on Energy, Utilities and Communications
Bill Author
Bill Co-Author(s):