SB 319: Electricity: transmission planning and permitting.
- Session Year: 2023-2024
- House: Senate
- Latest Version Date: 2023-10-07
Current Status:
Passed
(2023-10-07: Chaptered by Secretary of State. Chapter 390, Statutes of 2023.)
Introduced
In Committee
First Chamber
In Committee
Second Chamber
Enacted
Existing law requires the Public Utilities Commission (PUC), in consultation with the State Energy Resources Conservation and Development Commission (Energy Commission), on or before March 31, 2024, to provide transmission-focused guidance to the Independent System Operator about resource portfolios of expected future renewable energy resources and zero-carbon resources, including the allocation of those resources by region based on technical feasibility and commercial interest in each region to allow the Independent System Operator to identify and approve transmission facilities needed to interconnect resources and reliably serve the needs of load centers, as specified.
On December 23, 2022, the PUC, Energy Commission, and Independent System Operator entered into a memorandum of understanding related to resource and transmission planning, transmission development and permitting, procurement, and interconnections in order to achieve reliability and policy needs and to coordinate the timely development of resources, resource interconnections, and needed transmission infrastructure.
This bill would require the Energy Commission and PUC, in coordination with the Independent System Operator, every 5 years, to review the memorandum of understanding and a related workplan to ensure the memorandum and workplan reflect the coordination that is needed to help meet the states energy goals.
This bill would require the Energy Commission, PUC, and Independent System Operator, on or before July 1, 2025, to jointly develop an electrical transmission infrastructure development guidebook that describes the states electrical transmission infrastructure planning and permitting processes conducted by the Energy Commission, PUC, and Independent System Operator, and to provide an opportunity for stakeholder input and public comment on the guidebook, as specified.
This bill would require the PUC, in consultation with California balancing authorities, on or before December 1, 2024, and biennially thereafter, to submit a report to the Legislature that includes specified information related to electrical transmission projects.
Existing law requires the Public Utilities Commission (PUC), in consultation with the State Energy Resources Conservation and Development Commission (Energy Commission), on or before March 31, 2024, to provide transmission-focused guidance to the Independent System Operator about resource portfolios of expected future renewable energy resources and zero-carbon resources, including the allocation of those resources by region based on technical feasibility and commercial interest in each region to allow the Independent System Operator to identify and approve transmission facilities needed to interconnect resources and reliably serve the needs of load centers, as specified.
On December 23, 2022, the PUC, Energy Commission, and Independent System Operator entered into a memorandum of understanding related to resource and transmission planning, transmission development and permitting, procurement, and interconnections in order to achieve reliability and policy needs and to coordinate the timely development of resources, resource interconnections, and needed transmission infrastructure.
This bill would require the Energy Commission and PUC, in coordination with the Independent System Operator, every 5 years, to review the memorandum of understanding and a related workplan to ensure the memorandum and workplan reflect the coordination that is needed to help meet the states energy goals.
This bill would require the Energy Commission, PUC, and Independent System Operator, on or before July 1, 2025, to jointly develop an electrical transmission infrastructure development guidebook that describes the states electrical transmission infrastructure planning and permitting processes conducted by the Energy Commission, PUC, and Independent System Operator, and to provide an opportunity for stakeholder input and public comment on the guidebook, as specified.
This bill would require the PUC, in consultation with California balancing authorities, on or before December 1, 2024, and biennially thereafter, to submit a report to the Legislature that includes specified information related to electrical transmission projects.
Existing law requires the Public Utilities Commission (PUC), in consultation with the State Energy Resources Conservation and Development Commission (Energy Commission), on or before March 31, 2024, to provide transmission-focused guidance to the Independent System Operator about resource portfolios of expected future renewable energy resources and zero-carbon resources, including the allocation of those resources by region based on technical feasibility and commercial interest in each region to allow the Independent System Operator to identify and approve transmission facilities needed to interconnect resources and reliably serve the needs of load centers, as specified.
On December 23, 2022, the PUC, Energy Commission, and Independent System Operator entered into a memorandum of understanding related to resource and transmission planning, transmission development and permitting, procurement, and interconnections in order to achieve reliability and policy needs and to coordinate the timely development of resources, resource interconnections, and needed transmission infrastructure.
This bill would require the Energy Commission and PUC, in coordination with the Independent System Operator, every 5 years, to review the memorandum of understanding and a related workplan to ensure the memorandum and workplan reflect the coordination that is needed to help meet the states energy goals.
This bill would require the Energy Commission, PUC, and Independent System Operator Operator, on or before July 1, 2025, to jointly develop and recommend an expedited permitting roadmap that describes timeframes and milestones for a coordinated, comprehensive, and efficient permitting process for electrical transmission infrastructure, an electrical transmission infrastructure development guidebook that describes the states electrical transmission infrastructure planning and permitting processes conducted by the Energy Commission, PUC, and Independent System Operator, and to provide an opportunity for stakeholder input and public comment, comment on the guidebook, as specified. The bill would require the Energy Commission, PUC, and Independent System Operator, on or before December 31, 2024, to complete and submit the recommended framework for the expedited permitting roadmap to the Natural Resources Agency and the relevant fiscal and policy committees of the Legislature.
This bill would require the PUC to require each electrical corporation to annually review its long-term transmission infrastructure needs for the subsequent 10 years, based on the interconnection requests it receives, to annually report to the PUC on that review, and to ensure those needs incorporate each local governments present and future needs for new service connections and capacity service upgrades that may require transmission system upgrades. When an electrical corporation completes a transmission infrastructure project, the bill would require the electrical corporation to report the final cost of the project to the PUC. The bill would require the PUC, in consultation with California balancing authorities, on or before December 1, 2024, and annually biennially thereafter, to submit a report to the Legislature that evaluates certain transmission and resource planning that has been conducted or implemented, including pursuant to the memorandum of understanding and related workplan, as specified. includes specified information related to electrical transmission projects.
Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the PUC is a crime.Because certain of the above provisions would be part of the act and a violation of a PUC action implementing this bills requirements would be a crime, the bill would impose a state-mandated local program.The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.This bill would provide that no reimbursement is required by this act for a specified reason.Existing law requires the Public Utilities Commission (PUC), in consultation with the State Energy Resources Conservation and Development Commission (Energy Commission), on or before March 31, 2024, to provide transmission-focused guidance to the Independent System Operator about resource portfolios of expected future renewable energy resources and zero-carbon resources, including the allocation of those resources by region based on technical feasibility and commercial interest in each region to allow the Independent System Operator to identify and approve transmission facilities needed to interconnect resources and reliably serve the needs of load centers, as specified.
On December 23, 2022, the PUC, Energy Commission, and Independent System Operator entered into a memorandum of understanding related to resource and transmission planning, transmission development and permitting, procurement, and interconnections in order to achieve reliability and policy needs and to coordinate the timely development of resources, resource interconnections, and needed transmission infrastructure.
This bill would require the Energy Commission, Commission and PUC, and in coordination with the Independent System Operator to coordinate and implement a joint workplan through specified proceedings and other resource planning activities led by the Energy Commission, and to agree on principles for forecast cases and a single recommended forecast set and use it consistently in transmission planning and resource procurement cycles to the extent possible. The bill would require the PUC to incorporate long-term statewide resource planning efforts led by the Energy Commission into its proceedings for resource portfolios developed for resource procurement and transmission planning purposes. The bill would require the Independent System Operator to provide the PUC with an assessment of transmission planning needs and estimates spanning the Independent System Operator balancing authority area for resource planning purposes, and to coordinate with the Energy Commission on transmission needs in support of long-term informational analysis. The bill would require the PUC to incorporate Independent System Operator-provided transmission information into its considerations in developing resource portfolios and to map the resulting portfolio resources to specific electrical locations through a joint effort with the Energy Commission and Independent System Operator. The bill would require the Independent System Operator, in its transmission planning process, to conduct a stakeholder process that enables meaningful public participation to ensure that appropriate study assumptions and scenarios are identified to support development of its final transmission plan, as specified. The bill would require the PUC, in authorizing or requiring procurement of resources by electrical corporations, electric service providers, or community choice aggregators, to provide direction to pursue resources with the operational characteristics and geographic locations consistent with the resource planning conducted by the Energy Commission and PUC and the transmission planning conducted by the Independent System Operator based on that resource planning. The bill would require the Independent System Operator to prioritize interconnection process activities that support resources with operational characteristics and geographic locations consistent with that resource planning and its transmission planning based on that resource planning, and to coordinate with the Energy Commission and PUC to manage the resource interconnections and network upgrade projects in the interconnection process and provide transparency to ensure timely interconnection to the extent possible. Operator, every 5 years, to review the memorandum of understanding and a related workplan to ensure the memorandum and workplan reflect the coordination that is needed to help meet the states energy goals.
This bill would require the Energy Commission, PUC, and Independent System Operator to jointly develop and recommend an expedited permitting roadmap that describes timeframes and milestones for a coordinated, comprehensive, and efficient permitting process for electrical transmission infrastructure, and to provide an opportunity for stakeholder input and public comment, as specified. The bill would require the Energy Commission, PUC, and Independent System Operator, on or before December 31, 2024, to complete and submit the recommended framework for the expedited permitting roadmap to the Natural Resources Agency and the relevant fiscal and policy committees of the Legislature.
This bill would require the PUC to require each electrical corporation to annually review its long-term transmission infrastructure needs for the subsequent 10 years, based on the interconnection requests it receives, to annually report to the PUC on that review, and to coordinate with local governments to identify ensure those needs incorporate each local governments present and future interconnection needs. needs for new service connections and capacity service upgrades that may require transmission system upgrades. When an electrical corporation completes a transmission infrastructure project, the bill would require the electrical corporation to report the final cost of the project to the PUC. The bill would require the PUC, in consultation with California balancing authorities, on or before December 1, 2024, and annually thereafter, to submit a report to the Legislature that evaluates certain transmission and resource planning that has been conducted or implemented, including pursuant to the memorandum of understanding and related workplan, as specified.
Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the PUC is a crime.
Because certain of the above provisions would be part of the act and a violation of a PUC action implementing this bills requirements would be a crime, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law vests requires the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations. The Public Utilities Act prohibits any electrical corporation from beginning the construction of, among other things, a line, plant, or system, or of any extension thereof, without having first obtained from the commission a certificate that the present or future public convenience and necessity require or will require that construction. (PUC), in consultation with the State Energy Resources Conservation and Development Commission (Energy Commission), on or before March 31, 2024, to provide transmission-focused guidance to the Independent System Operator about resource portfolios of expected future renewable energy resources and zero-carbon resources, including the allocation of those resources by region based on technical feasibility and commercial interest in each region to allow the Independent System Operator to identify and approve transmission facilities needed to interconnect resources and reliably serve the needs of load centers, as specified.
This bill would state the intent of the Legislature to enact subsequent legislation related to electrical transmission. require the Energy Commission, PUC, and Independent System Operator to coordinate and implement a joint workplan through specified proceedings and other resource planning activities led by the Energy Commission, and to agree on principles for forecast cases and a single recommended forecast set and use it consistently in transmission planning and resource procurement cycles to the extent possible. The bill would require the PUC to incorporate long-term statewide resource planning efforts led by the Energy Commission into its proceedings for resource portfolios developed for resource procurement and transmission planning purposes. The bill would require the Independent System Operator to provide the PUC with an assessment of transmission planning needs and estimates spanning the Independent System Operator balancing authority area for resource planning purposes, and to coordinate with the Energy Commission on transmission needs in support of long-term informational analysis. The bill would require the PUC to incorporate Independent System Operator-provided transmission information into its considerations in developing resource portfolios and to map the resulting portfolio resources to specific electrical locations through a joint effort with the Energy Commission and Independent System Operator. The bill would require the Independent System Operator, in its transmission planning process, to conduct a stakeholder process that enables meaningful public participation to ensure that appropriate study assumptions and scenarios are identified to support development of its final transmission plan, as specified. The bill would require the PUC, in authorizing or requiring procurement of resources by electrical corporations, electric service providers, or community choice aggregators, to provide direction to pursue resources with the operational characteristics and geographic locations consistent with the resource planning conducted by the Energy Commission and PUC and the transmission planning conducted by the Independent System Operator based on that resource planning. The bill would require the Independent System Operator to prioritize interconnection process activities that support resources with operational characteristics and geographic locations consistent with that resource planning and its transmission planning based on that resource planning, and to coordinate with the Energy Commission and PUC to manage the resource interconnections and network upgrade projects in the interconnection process and provide transparency to ensure timely interconnection to the extent possible.
This bill would require the Energy Commission, PUC, and Independent System Operator to jointly develop and recommend an expedited permitting roadmap that describes timeframes and milestones for a coordinated, comprehensive, and efficient permitting process for electrical transmission infrastructure, and to provide an opportunity for stakeholder input and public comment, as specified. The bill would require the Energy Commission, PUC, and Independent System Operator, on or before December 31, 2024, to complete and submit the recommended framework for the expedited permitting roadmap to the Natural Resources Agency and the relevant fiscal and policy committees of the Legislature.
This bill would require the PUC to require each electrical corporation to annually review its long-term transmission infrastructure needs for the subsequent 10 years, based on the interconnection requests it receives, to annually report to the PUC on that review, and to coordinate with local governments to identify each local governments present and future interconnection needs. When an electrical corporation completes a transmission infrastructure project, the bill would require the electrical corporation to report the final cost of the project to the PUC. The bill would require the PUC, in consultation with California balancing authorities, on or before December 1, 2024, and annually thereafter, to submit a report to the Legislature that evaluates certain transmission and resource planning that has been conducted or implemented, as specified.
Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the PUC is a crime.
Because certain of the above provisions would be part of the act and a violation of a PUC action implementing this bills requirements would be a crime, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations. The Public Utilities Act prohibits any electrical corporation from beginning the construction of, among other things, a line, plant, or system, or of any extension thereof, without having first obtained from the commission a certificate that the present or future public convenience and necessity require or will require that construction.
This bill would state the intent of the Legislature to enact subsequent legislation related to electrical transmission.
The commission and Public Utilities Commission, in coordination with the Independent System Operator, every five years, shall review and update as necessary the Memorandum of Understanding Between the California Public Utilities Commission (CPUC) and the California Energy Commission (CEC) and the California Independent System Operator (ISO) Regarding Transmission and Resource Planning and Implementation (December 23, 2022) and the related workplan to ensure the memorandum and workplan reflect the coordination that is needed to help meet the states energy goals, including those goals described in Section 454.53 of the Public Utilities Code.
SEC. 2.Section 25308.5 is added to the Public Resources Code, to read:25308.5.(a)On or before July 1, 2025, the commission, Public Utilities Commission, and Independent System Operator shall jointly develop an electrical transmission infrastructure development guidebook that describes the states electrical transmission infrastructure planning and permitting processes conducted by the commission, Public Utilities Commission, and Independent System Operator.
(b)In developing the electrical transmission infrastructure development guidebook, the commission, Public Utilities Commission, and Independent System Operator shall make a reasonable and good faith effort to consult with all relevant local, state, tribal, and federal agencies.
(c)The electrical transmission infrastructure development guidebook shall include a description of the different stages of electrical transmission infrastructure development, an analysis of the average timeframes for electrical transmission infrastructure planning and permitting by the commission, Public Utilities Commission, and Independent System Operator, clearly identify and describe the roles, responsibilities, and decisionmaking authority of federal agencies and state agencies, including the commission, Public Utilities Commission, and Independent System Operator, and include interfaces with federal agencies, including timing, sequence, and coordination with federal permitting agencies, and coordination between reviews under the California Environmental Quality Act (Division 13 (commencing with Section 21000)) and the federal National Environmental Policy Act of 1969 (42 U.S.C. Sec. 4321 et seq.).
(d)The commission, Public Utilities Commission, and Independent System Operator shall provide an opportunity for stakeholder input in the development and communication of the electrical transmission infrastructure development guidebook and an opportunity for public comment on a draft electrical transmission infrastructure development guidebook.
(e)For purposes of this section, electrical transmission infrastructure means electrical transmission facilities and equipment used to convey electricity from an electrical generation facility or energy storage system to the electrical distribution system or transmission-voltage load.
(f)This section shall remain in effect only until January 1, 2028, and as of that date is repealed.
SEC. 3.Section 913.12 is added to the Public Utilities Code, to read:913.12.On or before December 1, 2024, and biennially thereafter, the commission, in consultation with California balancing authorities, as defined in Section 399.12, shall submit a report to the Legislature that includes all of the following:
(a)A description of the electrical transmission project applications submitted to the commission for certificates of public convenience and necessity in the preceding two-year period.
(b)The number of electrical transmission projects that were issued certificates of public convenience and necessity in the preceding two-year period.
(c)The number of electrical transmission projects that, in the preceding two-year period, went into operation, were approved by the Independent System Operator, and did not require the issuance of certificates of public convenience and necessity.
(d)The estimated transmission capital cost added to the rate base for each electrical transmission project that was, in the preceding two-year period, either approved by the Independent System Operator or issued a certificate of public convenience and necessity.
The commission and Public Utilities Commission, in coordination with the Independent System Operator, every five years, shall review and update as necessary the Memorandum of Understanding Between the California Public Utilities Commission (CPUC) and the California Energy Commission (CEC) and the California Independent System Operator (ISO) Regarding Transmission and Resource Planning and Implementation (December 23, 2022) and the related workplan to ensure the memorandum and workplan reflect the coordination that is needed to help meet the states energy goals, including those goals described in Section 454.53 of the Public Utilities Code.
SEC. 2.Section 25308.5 is added to the Public Resources Code, to read:25308.5.(a)On or before July 1, 2025, the commission, Public Utilities Commission, and Independent System Operator shall jointly develop an electrical transmission infrastructure development guidebook that describes the states electrical transmission infrastructure planning and permitting processes conducted by the commission, Public Utilities Commission, and Independent System Operator.
(b)In developing the electrical transmission infrastructure development guidebook, the commission, Public Utilities Commission, and Independent System Operator shall make a reasonable and good faith effort to consult with all relevant local, state, tribal, and federal agencies.
(c)The electrical transmission infrastructure development guidebook shall include a description of the different stages of electrical transmission infrastructure development, an analysis of the average timeframes for electrical transmission infrastructure planning and permitting by the commission, Public Utilities Commission, and Independent System Operator, clearly identify and describe the roles, responsibilities, and decisionmaking authority of federal agencies and state agencies, including the commission, Public Utilities Commission, and Independent System Operator, and include interfaces with federal agencies, including timing, sequence, and coordination with federal permitting agencies, and coordination between reviews under the California Environmental Quality Act (Division 13 (commencing with Section 21000)) and the federal National Environmental Policy Act of 1969 (42 U.S.C. Sec. 4321 et seq.).
(d)The commission, Public Utilities Commission, and Independent System Operator shall provide an opportunity for stakeholder input in the development and communication of the electrical transmission infrastructure development guidebook and an opportunity for public comment on a draft electrical transmission infrastructure development guidebook.
(e)For purposes of this section, electrical transmission infrastructure means electrical transmission facilities and equipment used to convey electricity from an electrical generation facility or energy storage system to the electrical distribution system or transmission-voltage load.
(f)This section shall remain in effect only until January 1, 2028, and as of that date is repealed.
SEC. 3.Section 913.12 is added to the Public Utilities Code, to read:913.12.On or before December 1, 2024, and biennially thereafter, the commission, in consultation with California balancing authorities, as defined in Section 399.12, shall submit a report to the Legislature that includes all of the following:
(a)A description of the electrical transmission project applications submitted to the commission for certificates of public convenience and necessity in the preceding two-year period.
(b)The number of electrical transmission projects that were issued certificates of public convenience and necessity in the preceding two-year period.
(c)The number of electrical transmission projects that, in the preceding two-year period, went into operation, were approved by the Independent System Operator, and did not require the issuance of certificates of public convenience and necessity.
(d)The estimated transmission capital cost added to the rate base for each electrical transmission project that was, in the preceding two-year period, either approved by the Independent System Operator or issued a certificate of public convenience and necessity.
The commission and Public Utilities Commission, in coordination with the Independent System Operator, every five years, shall review and update as necessary the Memorandum of Understanding Between the California Public Utilities Commission (CPUC) and the California Energy Commission (CEC) and the California Independent System Operator (ISO) Regarding Transmission and Resource Planning and Implementation (December 23, 2022) and the related workplan to ensure the memorandum and workplan reflect the coordination that is needed to help meet the states energy goals, including those goals described in Section 454.53 of the Public Utilities Code.
SEC. 2.Section 25308.5 is added to the Public Resources Code, to read:25308.5.(a)The On or before July 1, 2025, the commission, Public Utilities Commission, and Independent System Operator shall jointly develop and recommend an expedited permitting roadmap that describes timeframes and milestones for a coordinated, comprehensive, and efficient permitting process for electrical transmission infrastructure. an electrical transmission infrastructure development guidebook that describes the states electrical transmission infrastructure planning and permitting processes conducted by the commission, Public Utilities Commission, and Independent System Operator.
(b)In developing the expedited permitting roadmap, electrical transmission infrastructure development guidebook, the commission, Public Utilities Commission, and Independent System Operator shall make a reasonable and good faith effort to consult and meaningfully collaborate with all relevant local, state, tribal, and federal agencies.
(c)The expedited permitting roadmap electrical transmission infrastructure development guidebook shall include a goal for the permitting timeframe, clearly define state and federal agency description of the different stages of electrical transmission infrastructure development, an analysis of the average timeframes for electrical transmission infrastructure planning and permitting by the commission, Public Utilities Commission, and Independent System Operator, clearly identify and describe the roles, responsibilities, and decisionmaking authority, authority of federal agencies and state agencies, including the commission, Public Utilities Commission, and Independent System Operator, and include interfaces with federal agencies, including timing, sequence, and coordination with federal permitting agencies, and coordination between reviews under the California Environmental Quality Act (Division 13 (commencing with Section 21000)) and the federal National Environmental Policy Act of 1969 (42 U.S.C. Sec. 4321 et seq.).
(d)The commission, Public Utilities Commission, and Independent System Operator shall provide an opportunity for stakeholder input in the development and communication of the expedited permitting roadmap electrical transmission infrastructure development guidebook and an opportunity for public comment on a draft permitting roadmap. electrical transmission infrastructure development guidebook.
(e)On or before December 31, 2024, the commission, Public Utilities Commission, and Independent System Operator shall complete and submit the recommended framework for the expedited permitting roadmap to the Natural Resources Agency and the relevant fiscal and policy committees of the Legislature.(e)For purposes of this section, electrical transmission infrastructure means electrical transmission facilities and equipment used to convey electricity from an electrical generation facility or energy storage system to the electrical distribution system or transmission-voltage load.
(f)This section shall remain in effect only until January 1, 2028, and as of that date is repealed.
SEC. 3.Section 454.58 is added to the Public Utilities Code, to read:454.58.(a)(1)The commission shall require each electrical corporation to annually review its long-term transmission infrastructure needs for the subsequent 10 years, based on the interconnection requests it receives.(2)Each electrical corporation shall annually report to the commission on its review conducted pursuant to paragraph (1).(b)The commission shall require each electrical corporation to ensure the long-term transmission infrastructure needs incorporate each local governments present and future needs for new service connections and capacity service upgrades that may require transmission system upgrades.(c)When an electrical corporation completes a transmission infrastructure project, the electrical corporation shall report the final cost of the project to the commission.SEC. 4.SEC. 3.Section 913.12 is added to the Public Utilities Code, to read:913.12.(a)On or before December 1, 2024, and annually biennially thereafter, the commission, in consultation with California balancing authorities, as defined in Section 399.12, shall submit a report to the Legislature that evaluates the transmission and resource planning conducted pursuant to, and the implementation of, Section 454.53, and the memorandum of understanding and related workplan described in Section 25308 of the Public Resources Code, including includes all of the following:
(1)The current average timeframes for new customer energization and generator interconnections.(2)The expected improvements to system and local interconnections over the next 5 and 10 years as a result of that transmission and resource planning.(3)Any challenges and gaps, if any, to achieving system and local interconnections.(4)Any annual issuances of certificates of public convenience and necessity and the reasons that the issuance of those certificates was necessary.(b)The report submitted pursuant to subdivision (a) shall also include the final costs of transmission infrastructure projects completed during the preceding year, as reported to the commission pursuant to Section 454.58.(a)A description of the electrical transmission project applications submitted to the commission for certificates of public convenience and necessity in the preceding two-year period.
(b)The number of electrical transmission projects that were issued certificates of public convenience and necessity in the preceding two-year period.
(c)The number of electrical transmission projects that, in the preceding two-year period, went into operation, were approved by the Independent System Operator, and did not require the issuance of certificates of public convenience and necessity.
(d)The estimated transmission capital cost added to the rate base for each electrical transmission project that was, in the preceding two-year period, either approved by the Independent System Operator or issued a certificate of public convenience and necessity.
SEC. 5.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.The commission and Public Utilities Commission, in coordination with the Independent System Operator, every five years, shall review and update as necessary the Memorandum of Understanding Between the California Public Utilities Commission (CPUC) and the California Energy Commission (CEC) and the California Independent System Operator (ISO) Regarding Transmission and Resource Planning and Implementation (December 23, 2022) and the related workplan to ensure the memorandum and workplan reflect the coordination that is needed to help meet the states energy goals, including those goals described in Section 454.53 of the Public Utilities Code.
SEC. 2.Section 25308.5 is added to the Public Resources Code, to read:25308.5.(a)The commission, Public Utilities Commission, and Independent System Operator shall jointly develop and recommend an expedited permitting roadmap that describes timeframes and milestones for a coordinated, comprehensive, and efficient permitting process for electrical transmission infrastructure.
(b)In developing the expedited permitting roadmap, the commission, Public Utilities Commission, and Independent System Operator shall consult and meaningfully collaborate with all relevant local, state, tribal, and federal agencies.
(c)The expedited permitting roadmap shall include a goal for the permitting timeframe, clearly define state and federal agency roles, responsibilities, and decisionmaking authority, and include interfaces with federal agencies, including timing, sequence, and coordination with federal permitting agencies, and coordination between reviews under the California Environmental Quality Act (Division 13 (commencing with Section 21000)) and the federal National Environmental Policy Act of 1969 (42 U.S.C. Sec. 4321 et seq.).
(d)The commission, Public Utilities Commission, and Independent System Operator shall provide an opportunity for stakeholder input in the development and communication of the expedited permitting roadmap and an opportunity for public comment on a draft permitting roadmap.
(e)On or before December 31, 2024, the commission, Public Utilities Commission, and Independent System Operator shall complete and submit the recommended framework for the expedited permitting roadmap to the Natural Resources Agency and the relevant fiscal and policy committees of the Legislature.
(f)This section shall remain in effect only until January 1, 2028, and as of that date is repealed.
SEC. 3.Section 454.58 is added to the Public Utilities Code, to read:454.58.(a)(1)The commission shall require each electrical corporation to annually review its long-term transmission infrastructure needs for the subsequent 10 years, based on the interconnection requests it receives.
(2)Each electrical corporation shall annually report to the commission on its review conducted pursuant to paragraph (1).
(b)The commission shall require each electrical corporation to coordinate with local governments to identify ensure the long-term transmission infrastructure needs incorporate each local governments present and future interconnection needs. needs for new service connections and capacity service upgrades that may require transmission system upgrades.
(c)When an electrical corporation completes a transmission infrastructure project, the electrical corporation shall report the final cost of the project to the commission.
SEC. 4.Section 913.12 is added to the Public Utilities Code, to read:913.12.(a)On or before December 1, 2024, and annually thereafter, the commission, in consultation with California balancing authorities, as defined in Section 399.12, shall submit a report to the Legislature that evaluates the transmission and resource planning conducted pursuant to, and the implementation of, Section 25308 of the Public Resources Code and Section 454.53, and the memorandum of understanding and related workplan described in Section 25308 of the Public Resources Code, including all of the following:
(1)The current average timeframes for new customer energization and generator interconnections.
(2)The expected improvements to system and local interconnections over the next 5 and 10 years as a result of that transmission and resource planning.
(3)Any challenges and gaps, if any, to achieving system and local interconnections.
(4)Any annual issuances of certificates of public convenience and necessity and the reasons that the issuance of those certificates was necessary.
(b)The report submitted pursuant to subdivision (a) shall also include the final costs of transmission infrastructure projects completed during the preceding year, as reported to the commission pursuant to Section 454.58.
SEC. 5.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
(a)(1)The commission, Public Utilities Commission, and Independent System Operator shall coordinate and implement a joint workplan through integrated energy policy report proceedings, proceedings related to Chapter 312 of the Statutes of 2018, including the policy of the state described in Section 454.53 of the Public Utilities Code, and other resource planning activities led by the commission.
(2)The joint workplan shall do all of the following:
(A)Align the key milestones of the demand forecasting process with the commissions, Public Utilities Commissions, and Independent System Operators transmission planning and policy deliberations.
(B)Clarify data flows between the commission, Public Utilities Commission, and Independent System Operator.
(C)Highlight timing needs for key deliverables and areas for collaboration.
(D)Clarify how the commission, Public Utilities Commission, and Independent System Operator may each use forecasts in their own deliberations.
(b)After the commission finalizes demand and load modifier forecasts and scenarios, the commission, Public Utilities Commission, and Independent System Operator shall agree on principles for forecast cases and a single recommended forecast set and use it consistently in transmission planning and resource procurement cycles to the extent possible given the sequencing of those entities different processes.
(c)(1)The Public Utilities Commission shall incorporate long-term statewide resource planning efforts led by the commission into its proceedings for resource portfolios developed for resource procurement and transmission planning purposes.
(2)The commission shall use relevant resource information resulting from the Public Utilities Commissions planning proceedings for resource portfolios in its subsequent resource planning efforts.
(d)The Independent System Operator shall use the results of its planning process, interconnection cluster study reports, and any long-term informational planning exercises it conducts to provide the Public Utilities Commission with an assessment of transmission planning needs and estimates spanning the Independent System Operator balancing authority area for resource planning purposes, and shall coordinate with the commission on transmission needs in support of long-term informational analysis.
(e)The Public Utilities Commission shall incorporate Independent System Operator-provided transmission information into its considerations in developing resource portfolios and shall map the resulting portfolio resources to specific electrical locations, including busbars, through a joint effort with the commission and Independent System Operator.
(f)If the Public Utility Commissions resource portfolios meet parameters agreed to by the Public Utilities Commission and Independent System Operator with regards to the number, timing, and format of the resource portfolios, the Independent System Operator shall assess and incorporate into its annual transmission plan the resource portfolios developed in relevant Public Utilities Commission processes to the maximum extent practical given the goal of identifying needed transmission capacity.
(g)(1)In the Independent System Operators transmission planning process, the Independent System Operator shall conduct a stakeholder process that complies with Federal Energy Regulatory Commission Order Numbers 890 and 1000, and any subsequent relevant Federal Energy Regulatory Commission orders, and enables meaningful public participation to ensure that appropriate study assumptions and scenarios are identified to support development of the final transmission plan.
(2)Stakeholders shall have opportunities to comment on published drafts of the transmission plan, including the final draft transmission plan that will be submitted for approval to the Independent System Operator board of governors.
(3)The final transmission plan for the Independent System Operator balancing authority area shall reflect the Independent System Operators consideration of all stakeholder comments and recommendations received during the planning process.
(4)The Independent System Operators final transmission plan shall identify specific needed transmission facilities and shall distinguish, for policy-driven transmission projects, between Category 1 facilities that merit unconditional approval and Category 2 facilities that may be needed depending on future generation development and are expected to be needed in future planning cycles.
(5)The Independent System Operators transmission planning process shall consider and incorporate the scenarios and resource portfolios developed by the Public Utilities Commission with input from the commission, and the subsequent Public Utilities Commission siting and permitting process shall give substantial weight to project applications that are consistent with the Independent System Operators final transmission plan.
(h)In authorizing or requiring procurement of resources by load-serving entities, as defined in Section 380 of the Public Utilities Code, the Public Utilities Commission shall provide direction, to the extent appropriate, to pursue resources with the operational characteristics and geographic locations consistent with the resource planning conducted by the commission and Public Utilities Commission and the transmission planning conducted by the Independent System Operator based on that resource planning.
(i)The Independent System Operator shall prioritize interconnection process activities that support resources with operational characteristics and geographic locations consistent with the resource planning conducted by the commission and Public Utilities Commission and the transmission planning conducted by the Independent System Operator based on that resource planning.
(j)The Independent System Operator shall coordinate with the commission and Public Utilities Commission to manage the resource interconnections and network upgrade projects in the interconnection process and provide transparency to ensure timely interconnection to the extent possible.
SEC. 2.Section 25308.5 is added to the Public Resources Code, to read:25308.5.(a)The commission, Public Utilities Commission, and Independent System Operator shall jointly develop and recommend an expedited permitting roadmap that describes timeframes and milestones for a coordinated, comprehensive, and efficient permitting process for electrical transmission infrastructure.
(b)In developing the expedited permitting roadmap, the commission, Public Utilities Commission, and Independent System Operator shall consult and meaningfully collaborate with all relevant local, state, tribal, and federal agencies.
(c)The expedited permitting roadmap shall include a goal for the permitting timeframe, clearly define state and federal agency roles, responsibilities, and decisionmaking authority, and include interfaces with federal agencies, including timing, sequence, and coordination with federal permitting agencies, and coordination between reviews under the California Environmental Quality Act (Division 13 (commencing with Section 21000)) and the federal National Environmental Policy Act of 1969 (42 U.S.C. Sec. 4321 et seq.).
(d)The commission, Public Utilities Commission, and Independent System Operator shall provide an opportunity for stakeholder input in the development and communication of the expedited permitting roadmap and an opportunity for public comment on a draft permitting roadmap.
(e)On or before December 31, 2024, the commission, Public Utilities Commission, and Independent System Operator shall complete and submit the recommended framework for the expedited permitting roadmap to the Natural Resources Agency and the relevant fiscal and policy committees of the Legislature.
(f) This section shall remain in effect only until January 1, 2028, and as of that date is repealed.
SEC. 3.Section 454.58 is added to the Public Utilities Code, to read:454.58.(a)(1)The commission shall require each electrical corporation to annually review its long-term transmission infrastructure needs for the subsequent 10 years, based on the interconnection requests it receives.
(2)Each electrical corporation shall annually report to the commission on its review conducted pursuant to paragraph (1).
(b)The commission shall require each electrical corporation to coordinate with local governments to identify each local governments present and future interconnection needs.
(c)When an electrical corporation completes a transmission infrastructure project, the electrical corporation shall report the final cost of the project to the commission.
SEC. 4.Section 913.12 is added to the Public Utilities Code, to read:913.12.(a)On or before December 1, 2024, and annually thereafter, the commission, in consultation with California balancing authorities, as defined in Section 399.12, shall submit a report to the Legislature that evaluates the transmission and resource planning conducted pursuant to, and the implementation of, Section 25308 of the Public Resources Code and Section 454.53, including all of the following:
(1)The current average timeframes for new customer and generator interconnections.
(2)The expected improvements to system and local interconnections over the next 5 and 10 years as a result of that transmission and resource planning.
(3)Any challenges and gaps, if any, to achieving system and local interconnections.
(4)Any annual issuances of certificates of public convenience and necessity and the reasons that the issuance of those certificates was necessary.
(b)The report submitted pursuant to subdivision (a) shall also include the final costs of transmission infrastructure projects completed during the preceding year, as reported to the commission pursuant to Section 454.58.
SEC. 5.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
SECTION 1.It is the intent of the Legislature to enact subsequent legislation related to electrical transmission.It is the intent of the Legislature to enact subsequent legislation related to electrical transmission.
|
Date
|
Status
|
|---|---|
| Oct 7, 2023 | Chaptered by Secretary of State. Chapter 390, Statutes of 2023. |
| Oct 7, 2023 | Approved by the Governor. |
| Sep 21, 2023 | Enrolled and presented to the Governor at 4 p.m. |
| Sep 14, 2023 | Assembly amendments concurred in. (Ayes 40. Noes 0. Page 2832.) Ordered to engrossing and enrolling. |
| Sep 13, 2023 | In Senate. Concurrence in Assembly amendments pending. |
| Sep 13, 2023 | Read third time. Passed. (Ayes 80. Noes 0. Page 3398.) Ordered to the Senate. |
| Sep 5, 2023 | Read second time. Ordered to third reading. |
| Sep 1, 2023 | Read second time and amended. Ordered to second reading. |
| Sep 1, 2023 | From committee: Do pass as amended. (Ayes 12. Noes 0.) (September 1). |
| Aug 16, 2023 | August 16 set for first hearing. Placed on suspense file. |
| Jul 13, 2023 | From committee: Do pass and re-refer to Com. on APPR. with recommendation: To consent calendar. (Ayes 14. Noes 0.) (July 12). Re-referred to Com. on APPR. |
| Jun 8, 2023 | Referred to Com. on U. & E. |
| May 25, 2023 | In Assembly. Read first time. Held at Desk. |
| May 25, 2023 | Read third time. Passed. (Ayes 40. Noes 0. Page 1298.) Ordered to the Assembly. |
| May 23, 2023 | Ordered to special consent calendar. |
| May 18, 2023 | Read second time. Ordered to third reading. |
| May 18, 2023 | From committee: Do pass. (Ayes 7. Noes 0. Page 1165.) (May 18). |
| May 16, 2023 | Set for hearing May 18. |
| May 15, 2023 | May 15 hearing: Placed on APPR suspense file. |
| May 5, 2023 | Set for hearing May 15. |
| May 3, 2023 | Read second time and amended. Re-referred to Com. on APPR. |
| May 2, 2023 | From committee: Do pass as amended and re-refer to Com. on APPR. (Ayes 16. Noes 0. Page 870.) (April 24). |
| Apr 18, 2023 | Set for hearing April 24. |
| Apr 17, 2023 | April 18 set for first hearing canceled at the request of author. |
| Apr 10, 2023 | Set for hearing April 18. |
| Mar 29, 2023 | Re-referred to Com. on E., U. & C. |
| Mar 22, 2023 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on RLS. |
| Feb 15, 2023 | Referred to Com. on RLS. |
| Feb 7, 2023 | From printer. May be acted upon on or after March 9. |
| Feb 6, 2023 | Introduced. Read first time. To Com. on RLS. for assignment. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Sep 14, 2023 | Unfinished Business SB319 McGuire Concurrence | Senate Floor |
Passed |
|
| Sep 13, 2023 | SB 319 McGuire Senate Third Reading By Garcia | Assembly Floor |
Passed |
|
| Sep 1, 2023 | Do pass as amended. | Assembly Standing Committee on Appropriations |
Passed |
|
| Jul 12, 2023 | Do pass and be re-referred to the Committee on [Appropriations] with recommendation: To Consent Calendar | Assembly Standing Committee on Utilities and Energy |
Passed |
|
| May 25, 2023 | Special Consent SB319 McGuire | Senate Floor |
Passed |
|
| May 18, 2023 | Do pass | Senate Standing Committee on Appropriations |
Passed |
|
| May 15, 2023 | Placed on suspense file | Senate Standing Committee on Appropriations |
Passed |
|
| Apr 24, 2023 | Do pass as amended, but first amend, and re-refer to the Committee on [Appropriations] | Senate Standing Committee on Energy, Utilities and Communications |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| Clean Air Task Force | ** Support | |
| County of Humboldt | ** Support | |
| Large Scale Solar Association | ** Support | |
| Sempra Energy And Its Affiliates: San Diego Gas & Electric Company And Southern California Gas Company | ** Support | |
| Sonoma Clean Power | ** Support | |
| The Climate Center | ** Support |
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 319 |
UNFINISHED BUSINESS
Bill No: SB 319
Author: McGuire (D)
Amended: 9/1/23
Vote: 21
SENATE ENERGY, U. & C. COMMITTEE: 16-0, 4/24/23
AYES: Bradford, Ashby, Becker, Caballero, Dodd, Durazo, Eggman, Gonzalez, McGuire, Min, Newman, Rubio, Seyarto, Skinner, Stern, Wilk
NO VOTE RECORDED: Dahle, Grove
SENATE APPROPRIATIONS COMMITTEE: 7-0, 5/18/23
AYES: Portantino, Jones, Ashby, Bradford, Seyarto, Wahab, Wiener
SENATE FLOOR: 40-0, 5/25/23
AYES: Allen, Alvarado-Gil, Archuleta, Ashby, Atkins, Becker, Blakespear, Bradford, Caballero, Cortese, Dahle, Dodd, Durazo, Eggman, Glazer, Gonzalez, Grove, Hurtado, Jones, Laird, Limón, McGuire, Menjivar, Min, Newman, Nguyen, Niello, Ochoa Bogh, Padilla, Portantino, Roth, Rubio, Seyarto, Skinner, Smallwood-Cuevas, Stern, Umberg, Wahab, Wiener, Wilk
ASSEMBLY FLOOR: 80-0, 9/13/23 - See last page for vote
SUBJECT: Electricity: transmission planning and permitting
SOURCE: Author
DIGEST:
This bill requires specified actions related to electric transmission planning, including: requires a review and update to a December 2022 memorandum of understanding and related workplan among California energy agencies and California Independent System Operator (CAISO), the development of an electrical transmission infrastructure guidebook; and a report to the Legislature regarding the status of transmission projects.
Assembly Amendments
require the state energy agencies and CAISO develop an electrical transmission guidebook; delete the requirements that electrical corporations annually review their long-term transmission infrastructure needs; delete and clarify the reporting requirements related to transmission projects and interconnections; and change the timing of when the California Public Utilities Commission (CPUC) must submit their report to the Legislature from annually to biennially.
ANALYSIS:
Existing law:
- Establishes that U.S. Federal Energy Regulatory Commission (FERC) has exclusive jurisdiction over the transmission of electric energy in interstate commerce. (Federal Power Act §§§201, 205, 206 (16 USC 824, 824d, 824e))
- Establishes the CPUC with jurisdiction over all public utilities, including electrical and gas corporations. (Article XII of the California Constitution)
- Requires the California Energy Commission (CEC) to conduct assessments and forecasts of all aspects of energy industry supply, production, transportation, delivery and distribution, demand, and prices and to use these assessments and forecasts to develop and evaluate energy policies and programs that conserve resources, protect the environment, ensure energy reliability, enhance the state's economy, and protect public health and safety. (Public Resources Code §25301(a))
- Establishes the CAISO as a nonprofit public benefit corporation, and requires the CAISO to ensure the efficient use and reliable operation of the electrical transmission grid consistent with the achievement of planning and operating reserve criteria, as specified. (Public Utilities Code §345.5)
- Requires the CPUC, in consultation with the CEC on or before March 31, 2024, to provide transmission-focused guidance to the CAISO about resource portfolios of expected future renewable energy resources and zero-carbon resources, including the allocation of those resources by region based on technical feasibility and commercial interest in each region to allow the CAISO to identify and approve transmission facilities needed to interconnect resources and reliably serve the needs of load centers. (Public Utilities Code §454.57)
This bill:
- Requires the CEC and CPUC, in coordination with the CAISO, every five years, to review the memorandum of understanding and a related workplan to ensure the memorandum and workplan reflect the coordination that is needed to help meet the state’s energy goals.
- Requires the CEC, CPUC, and CAISO, on or before July 1, 2025, to jointly develop an electrical transmission infrastructure development guidebook that describes the state’s electrical transmission infrastructure planning and permitting processes conducted by the CEC, CPUC, and CAISO.
- Requires the guidebook to include a description of the different stages of electrical transmission infrastructure development, an analysis of the average timeframes for electrical transmission planning and permitting, and the authority of federal agencies, and other requirements.
- Requires the agencies and CAISO to provide an opportunity for stakeholder input and public comment on the guidebook, including consultation with local, state, tribal, and federal agencies.
- Requires the CPUC, in consultation with California balancing authorities, on or before December 1, 2024, and biennially thereafter, to submit a report to the Legislature that includes information related to electrical transmission projects, including:
- Description of project applications for certificates of public convenience and necessity from the preceding two years.
- The number of projects issued CPCNs.
- The number of projects that went into service and did not require CPCNs.
- Estimated transmission capital cost added to the rate base for each transmission projects that was approved by the CAISO or issued a CPCN.
Background
SB 100/SB 1020 clean energy goals. With the adoption of SB 100 (De León, Chapter 312, Statutes of 2018) and SB 1020 (Laird, Chapter 361, Statutes of 2022) statute establishes the policy of the state that eligible renewable energy resources and zero-carbon resources supply 90 percent of all retail sales of electricity to California end-use customers by December 31, 2035, 95 percent of all retail sales of electricity to California end-use customers by December 31, 2040, 100 percent of all retail sales of electricity to California end-use customers by December 31, 2045, and 100 percent of electricity procured to serve all state agencies by December 31, 2035.
In March 2021, the CEC, CPUC and the California Air Resources Board (CARB) released the joint agency SB 100 report, to determine how best to implement the 100% clean energy policy, and found that in order to meet the state’s energy goals, California will need to roughly triple its current electricity power capacity. Most of California's electric transmission system was built four decades ago to deliver electricity from fossil, nuclear, and hydroelectric generation. As such, upgrades are needed to meet our zero-carbon and renewable energy future. Currently, many reforms are underway; either through better coordination amongst the energy entities to streamline planning, or through efforts to expedite permitting, including much focus on environmental review, or through reforms to the interconnection process to ensure new resources can be delivered.
CAISO transmission planning. The CAISO conducts its transmission planning process to identify potential system limitations, as well as, opportunities for system reinforcements that improve reliability and efficiency. The annual transmission plan fulfills the CAISO’s core responsibility to identify and plan the development of solutions, transmission or otherwise, to meet the future needs of the electricity grid. In 2021, the CAISO created a 20-Year Transmission Outlook for the electric grid with the goal of exploring the longer-term grid requirements and options for meeting the state’s SB 100 clean energy objectives reliably and cost-effectively. The 20-Year Transmission Outlook estimates a significant amount, and expense, to construct and expand transmission facilities, including an estimated $10.74 billion in upgrades to existing facilities.
CAISO Annual Transmission Planning Process (TPP) which evaluates the electricity system’s needs based on energy resource portfolios developed by the CPUC, and in consultation with the CEC, identifies the necessary new transmission lines and upgrades to existing transmission lines required to assure reliability and to further public policy goals. The most recent 2023-24 TPP Portfolios were transmitted to CAISO planning for approximately 86 gigawatts of new resources by 2035.
Transmission Development Forum. The Transmission Development Forum is a more recent joint effort between the CAISO and the CPUC to discuss and track Participating Transmission Owners’ expansion and network upgrade projects and schedules. The Transmission Development Forum creates a single forum to track the status of transmission network upgrade projects that affect generators and all other transmission projects approved in the CAISO’s transmission planning process. The effort allows for increased transparency for all stakeholders about transmission projects and enhances accountability of transmission owners by having them explain schedule changes, delays, and address stakeholders’ questions.
Tracking Energy Development (TED) Task Force. The TED Taskforce is another more recent joint effort of the CPUC, CEC, CAISO, and Office of Business and Economic Development (GO-Biz) to track new energy projects under development. According to the CPUC, the objective is to build on the success of the ad hoc 2021 efforts to provide energy resource project development support, as appropriate, and identify barriers and mitigation strategies to accelerate energy project development.
December 2022 Memorandum of Understanding (MOU). The CPUC, CEC, and CAISO entered an updated MOU, replacing the 2010 MOU, in order to better coordinate their respective and shared efforts for the timely development of resources needed to achieve the state’s clean energy goals reliably and economically. The MOU focuses on linkages between forecasting, planning, procurement direction, and the interconnections process, among others, including those related to transmission.
Comments
This bill attempts to address the need for the expanded buildout of the electric transmission system serving the CAISO balancing authority area, including the capacity limitations on existing transmission in the northern coast of the state. By requiring more regular review and updates to the December 2022 MOU and related workplan, this bill is intended to ensure the MOU remains current to better reflect any changes to conditions. By requiring a guidebook on transmission development infrastructure planning and biennially reports on the status of transmission projects, this bill would help provide greater transparency as to the state’s ability to advance transmission projects to meet the state’s clean energy goals.
Related/Prior Legislation
SB 420 (Becker, 2023) allows, among its provisions, exempt construction of a new electrical transmission facility, as specified, from the requirement to obtain a discretionary permit from the CPUC, if the electrical transmission facility meets certain requirements.
SB 619 (Padilla, 2023) authorizes an electrical corporation that applies to the CPUC to authorize a construction of a high voltage electrical transmission line, rated at 138 kilovolts or greater, to apply to the CEC for certification of the facility pursuant to the California Environmental Quality Act (CEQA).
SB 664 (Stern, 2023), among its provisions, requires the CEC and CPUC to report on the status of electric infrastructure projects as part of the joint Reliability Planning Assessment.
SB 149 (Caballero, Chapter 60, Statutes of 2023), among its provisions, revised the procedures regarding CEQA administrative records and expedited administrative and judicial review procedures for ELDPs for specified projects, including transmission projects, that required the courts to resolve CEQA litigation within 270 days to the extent feasible and extended the ELDP sunset to January 1, 2034.
SB 529 (Hertzberg, Chapter 357, Statutes of 2022) exempted an extension, expansion, upgrade, or other modification of an existing transmission line or substations from the requirement of a CPCN and directs the CPUC to revise its general orders, by January 1, 2024, to instead use its permit to construct process for these approvals.
SB 887 (Becker, Chapter 358, Statutes of 2022) directed, among other provisions, the CPUC, on or before January 15, 2023, to request CAISO to identify the highest priority anticipated transmission facilities that are needed to deliver renewable energy resources or zero-carbon resources.
SB 1174 (Herzberg, Chapter 229, Statutes of 2022) required certain CPUC reports and assessments, including reporting relating to the California Renewables Portfolio Standard Program, to consider the role of transmission.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: No
According to the Assembly Appropriations Committee:
- The CPUC estimates it will need $918,000 annually for two regulatory analysts ($210,000 annually and $179,000 annually) and one utilities engineer ($209,000 annually) to, among other things, develop an expedited permitting roadmap and an annual report on transmission planning conducted pursuant to that roadmap, and to oversee utilities’ annual review of their 10-year transmission plans, including ensuring that the 10-year plans include local governments’ needs. The total also includes $250,000 annually for a contract with a third party to support tracking, road-mapping, outreach to local governments and other tasks, as well as $30,000 annually for staff training, $30,000 annually for staff travel and $10,000 annually for hardware and software costs. (Public Utilities Commission Utilities Reimbursement Account.)
- The CEC anticipates needing one permanent program specialist at an annual cost of $229,000 to help develop an expedited permitting roadmap (Energy Resources Programs Account (ERPA)).
SUPPORT: (Verified 9/13/23)
Clean Air Task Force
County of Humboldt
Sonoma Clean Power
The Climate Center
OPPOSITION: (Verified 9/13/23)
None received
ARGUMENTS IN SUPPORT: According to the author:
The Golden State is staring down some extraordinary deadlines to meet our climate goals, and electricity transmission – the backbone of our power system – is the key to clean, cost-effective, and reliable electricity delivery to all Californians.
It's become abundantly clear that PG&E has some pretty significant constraints surrounding capacity and an antiquated transmission system. The state is also about to do two large offshore wind projects and the energy harnessed by those projects has to get into the grid, but our current transmission infrastructure doesn't support that. SB 319 will ensure the Golden State and our IOUs are coordinating to better meet our transmission needs in the future.
ASSEMBLY FLOOR: 80-0, 9/13/23
AYES: Addis, Aguiar-Curry, Alanis, Alvarez, Arambula, Bains, Bauer-Kahan, Bennett, Berman, Boerner, Bonta, Bryan, Calderon, Juan Carrillo, Wendy Carrillo, Cervantes, Chen, Connolly, Megan Dahle, Davies, Dixon, Essayli, Flora, Mike Fong, Vince Fong, Friedman, Gabriel, Gallagher, Garcia, Gipson, Grayson, Haney, Hart, Holden, Hoover, Irwin, Jackson, Jones-Sawyer, Kalra, Lackey, Lee, Low, Lowenthal, Maienschein, Mathis, McCarty, McKinnor, Muratsuchi, Stephanie Nguyen, Ortega, Pacheco, Papan, Jim Patterson, Joe Patterson, Pellerin, Petrie-Norris, Quirk-Silva, Ramos, Rendon, Reyes, Luz Rivas, Rodriguez, Blanca Rubio, Sanchez, Santiago, Schiavo, Soria, Ta, Ting, Valencia, Villapudua, Waldron, Wallis, Ward, Weber, Wicks, Wilson, Wood, Zbur, Robert Rivas
Prepared by: Nidia Bautista / E., U. & C. / (916) 651-4107
9/14/23 9:55:10
**** END ****
SENATE THIRD READING
STR Bill Id:SB 319
Author:(McGuire)
As Amended Ver:September 1, 2023
Majority vote
SUMMARY
Requires the state energy agencies – in this case, the California Energy Commission (CEC) and the California Public Utilities Commission (CPUC), in coordination with the California Independent System Operator (CAISO) – to better and regularly coordinate planning and permitting of energy transmission infrastructure to ensure the state meets its clean energy goals and to evaluate and report on that planning and related infrastructure development. The bill also requires these state energy agencies to jointly develop an electrical transmission infrastructure development guidebook that describes the state's electrical transmission infrastructure planning and permitting process.
Major Provisions
- Requires the CEC and the CPUC, in coordination with CAISO, every five years, to review and update as necessary the agreement known as the "Memorandum of Understanding Between the California Public Utilities Commission (CPUC) and the California Energy Commission (CEC) and the California Independent System Operator (ISO) Regarding Transmission and Resource Planning and Implementation" (MOU), originally entered into in December of 2022, and the related work plan to ensure the MOU and work plan reflect work needed to meet the state's energy goals.
- Requires the CEC, CPUC, and CAISO on or before July 1, 2025 to jointly develop an electrical transmission infrastructure development guidebook that describes the state's electrical transmission infrastructure planning and permitting process, and provide an opportunity for stakeholder input and public comment.
- Requires the state energy agencies in developing the electrical transmission infrastructure development guidebook, to make a reasonable and good faith effort to consult and meaningfully collaborate with all relevant local, state, tribal, and federal agencies.
- Requires the CPUC, in consultation with California balancing authorities, on or before December 1, 2024, and biennially thereafter, to submit a report to the Legislature that includes descriptions of electrical transmission project applications, the number of electrical transmission projects that were issued, and transmission capital costs among other requirements.
COMMENTS
California's Ambitious Goals. In 2018, the Legislature passed SB 100 (De León), Chapter 312, Statutes of 2018 which established the state policy that renewable and zero-carbon resources supply 100% of retail sales and electricity procured to serve all state agencies by 2045. In March 2021, the CEC, CPUC and the California Air Resources Board (CARB) released the SB 100 report, to determine how best to implement the 100% Clean Energy Policy, and found that in order to meet the state’s energy goals, California will need to roughly triple its current electricity power capacity. Most of California's electric transmission system was built four decades ago to deliver electricity from fossil, nuclear, and hydroelectric generation. As such, upgrades are needed to meet our renewable energy future. Currently, many reforms are underway; either through better coordination amongst the energy entities to streamline planning, or through efforts to expedite permitting, including much focus on environmental review, or through reforms to the interconnection process to ensure new resources can be delivered.
2022 Memorandum of Understanding. As California's electric grid rapidly evolves to accommodate new and distributed clean energy resources to meet energy and climate goals and reliability needs, it is becoming increasingly clear that new approaches are fundamental in planning and managing the transmission infrastructure. The current transmission development process is marked with delays and on average, can take a decade to build. In December 2022, the CPUC, CAISO, and the CEC signed an updated MOU to enhance coordination of their shared responsibilities in transmission planning, resource development, interconnection process, and resource procurement. By tightening the linkage between these processes, these agencies hope to accelerate build out of transmission capacity in the state.
Phases of Transmission Development Process. The transmission development process is marked by three key phases summarized as i) Planning Phase, ii) Permitting Phase: The CPUC various types of permitting processes depending on project size and iii) Construction Phase. Each step of this process may introduce delays that are unique to the various transmission projects. Once a transmission project is built new generation resources seeking to utilize the transmission infrastructure must engage in the interconnection process—also at the CAISO—to physically connect to the transmission line. The resource interconnection process informs subsequent rounds of CAISO transmission planning, and the cycle of transmission development replicates.
According to the Author
According to the author, "The Golden State is staring down some extraordinary deadlines to meet our climate goals, and electricity transmission – the backbone of our power system – is the key to clean, cost-effective, and reliable electricity delivery to all Californians. We know there are concerns related to the lack of reliability in our power grid. We have capacity and distribution issues, and a transmission system that is struggling to keep up with current capacity needs. Several of our towns on the North Coast were literally told they would not be able to hook up new homes to electricity for the next several years. In another instance this fall, a newly built hospital was told there was no way it would be hooked up to power. It's become abundantly clear that PG&E has some pretty significant constraints surrounding capacity and an antiquated transmission system. The state is also about to do two large offshore wind projects and the energy harnessed by those projects has to get into the grid, but our current transmission infrastructure doesn't support that. SB 319 will ensure the Golden State and our IOUs are coordinating to better meet our transmission needs in the future."
Arguments in Support
The bill is supported by Clean Air Task Force which argues, "SB 319 will bring three agencies together to develop a roadmap for expediting transmission permitting, develop a workplan on transmission planning and require utilities to report their final transmission project costs. Together, these important provisions will keep California on schedule to meet our ambitious climate goals."
Arguments in Opposition
While not formally opposed, the Large-Scale Solar Association has expressed concerns regarding whether additional planning processes as specified in the bill are necessary, given the progress already underway at the regulatory agencies.
FISCAL COMMENTS
According to the Assembly Appropriations Committee, this bill will result in costs to both the CPUC and the CEC of an unknown, but significant amount, likely in the low to mid hundreds of thousands of dollar each, in fiscal years 2023-24 and 2024-25 to, along with CAISO, jointly develop the electrical transmission infrastructure development guidebook.
In addition, the CPUC will experience ongoing costs of an unknown amount, likely in the tens of thousands of dollars to the low hundreds of thousands of dollars annually, starting in the 2023-24 fiscal year, to, in consultation with California balancing authorities, biennially submit a report to the Legislature on electrical transmission projects and applications. The CEC anticipates needing one permanent program specialist at an annual cost of $229,000 to help develop an expedited permitting roadmap.
VOTES
SENATE FLOOR: 40-0-0
YES: Allen, Alvarado-Gil, Archuleta, Ashby, Atkins, Becker, Blakespear, Bradford, Caballero, Cortese, Dahle, Dodd, Durazo, Eggman, Glazer, Gonzalez, Grove, Hurtado, Jones, Laird, Limón, McGuire, Menjivar, Min, Newman, Nguyen, Niello, Ochoa Bogh, Padilla, Portantino, Roth, Rubio, Seyarto, Skinner, Smallwood-Cuevas, Stern, Umberg, Wahab, Wiener, Wilk
ASM UTILITIES AND ENERGY: 14-0-1
YES: Jim Patterson, Bauer-Kahan, Wendy Carrillo, Chen, Connolly, Hart, Mathis, Muratsuchi, Reyes, Santiago, Schiavo, Ting, Wallis, Wood
ABS, ABST OR NV: Garcia
ASM APPROPRIATIONS: 12-0-4
YES: Holden, Bryan, Calderon, Wendy Carrillo, Mike Fong, Hart, Lowenthal, Mathis, Papan, Pellerin, Weber, Wilson
ABS, ABST OR NV: Megan Dahle, Dixon, Sanchez, Soria
UPDATED
VERSION: September 1, 2023
CONSULTANT: Lina V. Malova / U. & E. / (916) 319-2083 FN: 0001624
Date of Hearing: August 16, 2023
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Chris Holden, Chair
SBPCA Bill Id:SB 319
Author:(McGuire) – As Amended Ver:May 3, 2023
Policy Committee: | Utilities and Energy | Vote: | 14 - 0 |
|
| ||
|
|
Urgency: No State Mandated Local Program: Yes Reimbursable: No
SUMMARY:
This bill requires the state energy agencies—in this case, the California Energy Commission (CEC) and the California Public Utilities Commission (CPUC), in coordination with the California Independent System Operator (CAISO)—to better and regularly coordinate planning and permitting of energy transmission infrastructure to ensure the state meets its clean energy goals and to evaluate and report on that planning and related infrastructure development.
Specifically, this bill:
- Requires regular updates of an existing memorandum of understanding.
- Requires the CEC and the CPUC, in coordination with CAISO, every five years, to review and update as necessary the agreement known as “Memorandum of Understanding Between the California Public Utilities Commission (CPUC) and the California Energy Commission (CEC) and the California Independent System Operator (ISO) Regarding Transmission and Resource Planning and Implementation” (MOU), originally entered into in December of 2022, and the related workplan to ensure the MOU and workplan reflect work needed to meet the state’s energy goals.
- Requires joint development of an expedited permitting roadmap.
- Requires the CEC, the CPUC and CAISO, in consultation and collaboration with all relevant local, state, tribal and federal agencies, to jointly develop and recommend an expedited permitting roadmap that describes timeframes, milestones and associated goals for a coordinated, comprehensive and efficient permitting process for electrical transmission infrastructure.
- Requires the energy agencies to submit the recommended framework for the expedited permitting roadmap to the Natural Resources Agency and the Legislature.
- Requires annual planning for long-term infrastructure needs.
- Directs the CPUC to require each investor-owned electric utility (IOU) to annually review its long-term transmission infrastructure needs for next 10 years, based on interconnection requests, and to report annually on its review to the CPUC.
- Requires the CPUC to ensure each IOU’s long-terms transmission infrastructure needs incorporate each local government’s present and future needs for new service connections and capacity service upgrades that may require transmission system upgrades.
- Requires each IOU to report the cost of each completed transmission infrastructure project to the CPUC.
- Requires an annual report to Legislature that evaluates transmission and resource planning and infrastructure development.
- Directs the CPUC, in consultation with the state’s balancing authorities, by January 1, 2024, and annually thereafter, to submit a report to the Legislature that evaluates the transmission and resource planning conducted pursuant to the state’s clean energy goals, the MOU and related workplan required by this bill.
- Requires the report to include (a) the current average timeframes for new customer energization and generator interconnections, (b) the expected improvements to system and local interconnections over the next five and 10 years as a result of that transmission and resource planning, (3) challenges and gaps, if any, to achieving system and local interconnections, (4) any annual issuances of certificates of public convenience and necessity and the reasons the issuance was necessary, and (5) the final costs of transmission infrastructure projects completed during the preceding year.
FISCAL EFFECT:
- The CPUC estimates it will need $918,000 annually for two regulatory analysts ($210,000 annually and $179,000 annually) and one utilities engineer ($209,000 annually) to, among other things, develop an expedited permitting roadmap and an annual report on transmission planning conducted pursuant to that roadmap, and to oversee utilities’ annual review of their 10-year transmission plans, including ensuring that the 10-year plans include local governments’ needs. The total also includes $250,000 annually for a contract with a third party to support tracking, road-mapping, outreach to local governments and other tasks, as well as $30,000 annually for staff training, $30,000 annually for staff travel and $10,000 annually for hardware and software costs. (Public Utilities Commission Utilities Reimbursement Account.)
- The CEC anticipates needing one permanent program specialist at an annual cost of $229,000 to help develop an expedited permitting roadmap (Energy Resources Programs Account (ERPA)).
COMMENTS:
- Purpose. The author intends this bill to facilitate development of the state’s electric transmission system to enable California to meet its clean energy goals.
- Background.
Clean Energy, Transmission, Electrification and Energization. California has ambitious clean energy goals. Statute commits the state to getting all of it electricity from renewable and zero-emission resources by 2045 and requires state agencies to do so by 2035. And key to the state’s clean energy strategy is the electrification of nearly everything. So, not only will the state need electricity from clean resources; it will need a lot more of it. For California to meet its goals, unprecedented amounts of renewable generation, electricity storage and electricity transmission will need to be developed in the coming decade.
Broadly put, energization refers to when customer load, such as a house or other building, is connected to the electrical grid and begins to receive electrical service from it. Energization is always important to the utility customer awaiting electric service. Recently, backlogs for utilities to fulfill requests for energization have grown, especially—though not only—in the service territory of Pacific Gas and Electric (PG&E).
The author of this bill, too, complains of the time it has taken PG&E to provide electric service to customers, or the time PG&E projects it will take to provide such service. The author describes situations in the North Coast, where, according to the author, several towns were “literally told they would not be able to hook up new homes to electricity for the next several years” and “a newly built hospital was told there was no way it would be hooked up to power.”
Other bills introduced this session to address the lag between request for service and energization have addressed the issue directly. For example, AB 50 (Wood) directs the CPUC to establish criteria governing timely energization service and, in the meantime, establishes interim energization service requirements.
This bill seeks to address the same problem, but does so by taking a step upstream to address the transmission planning and permitting processes to ensure, as the author puts it, that clean electricity can “get into the grid.” The bill does so, generally, by requiring coordinated transmission planning by the state’s energy agencies: calling on the CEC, CPUC and CAISO to regularly update an existing MOU on transmission and resource planning and implementation; requiring them to jointly develop and recommend an expedited permitting roadmap that describes timeframes, milestones and associated goals for a coordinated, comprehensive and efficient permitting process for electrical transmission infrastructure; directing energy utilities to regularly review long-term transmission infrastructure needs based on demonstrated customer demand and task the CPUC with ensuring the utilities are adequately planning to meet local demand; and requires the CPUC to report to the Legislature.
This bill does not cover new ground. The state energy agencies undertake many activities with the intent of ensuring the state has, and is planning for, adequate electrical supply and a sufficient, robust electrical grid. For example, the CAISO annually conducts a transmission planning process (TPP) to identify inadequacies of the grid and upgrades needed to ensure reliability and meet state policy goals, such as renewable energy procurement. The CPUC, as directed by statute, regularly develops integrated resource plans (IRPs) to “identify a diverse and balanced portfolio of resources needed to ensure a reliable electricity supply that provides optimal integration of renewable energy in a cost-effective manner.” The CPUC’s IRPs are input to the CAISO’s TPP. Foundational to the work of both the CAISO and the CPUC is the CEC’s forecast of demand for electricity and natural gas, both for California as a whole, but also by regions and subregions. Building off of, but distinct from these processes, the CAISO, in collaboration with the CPUC and CEC, published its “CAISO 20-year Transmission Outlook.” In addition, as the bill acknowledges, in December 2022, the CPUC, CAISO and the CEC signed an updated MOU to enhance coordination of their shared responsibilities in transmission planning, resource development, interconnection process and resource procurement.
Nonetheless, there is no opposition to this bill, including, at this date, none from the state energy agencies. It seems unlikely the requirements of this bill will conflict with the transmission and resource planning activities already underway at the state energy agencies. And it might just complement them.
Differing Implementation Cost Estimates. It is not clear why the CPUC’s estimate of the resources needed to implement this bill is so much greater than the CEC’s estimate. It is true the commissions have differing statutory roles and administrative processes. However, the work this bill requires of each commission seems comparable.
ERPA Structural Deficit. ERPA was established to provide funds for ongoing energy programs and energy projects, including the operations of the CEC. The ERPA fund is supported by a statutory surcharge on electricity consumption. The surcharge was increased to its statutory maximum—from $0.00029 to $0.0003 per kilowatt-hour (kWh)—by the CEC effective January 1, 2019. The surcharge generated approximately $67.5 million in 2017-18 and costs the average household $2.01 annually.
ERPA is in a structural deficit and, as a result, the CEC has overspent revenues by more than $17.4 million since fiscal year 2014-15. The CEC attributes the structural deficit to the CEC’s growing role in implementing aggressive climate policies that reduce electricity consumption, thereby reducing ERPA revenues. This structural deficit limits ERPA’s ability to support new programs.
Analysis Prepared by: Jay Dickenson / APPR. / (916) 319-2081
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 319 |
THIRD READING
Bill No: SB 319
Author: McGuire (D)
Amended: 5/3/23
Vote: 21
SENATE ENERGY, U. & C. COMMITTEE: 16-0, 4/24/23
AYES: Bradford, Ashby, Becker, Caballero, Dodd, Durazo, Eggman, Gonzalez, McGuire, Min, Newman, Rubio, Seyarto, Skinner, Stern, Wilk
NO VOTE RECORDED: Dahle, Grove
SENATE APPROPRIATIONS COMMITTEE: 7-0, 5/18/23
AYES: Portantino, Jones, Ashby, Bradford, Seyarto, Wahab, Wiener
SUBJECT: Electricity: transmission planning
SOURCE: Author
DIGEST:
This bill requires specified actions related to electric transmission planning, including requiring a review and update to a December 2022 memorandum of understanding and related workplan among California energy agencies and California Independent System Operator (CAISO), and the development of a permit streamlining roadmap for transmission projects, among other requirements.
ANALYSIS:
Existing law:
- Establishes that U.S. Federal Energy Regulatory Commission (FERC) has exclusive jurisdiction over the transmission of electric energy in interstate commerce. Also establishes the process and procedures for establishing transmission of electric energy in interstate commerce by public utilities, i.e., the rates, terms & conditions of interstate electric transmission by public utilities. (Federal Power Act §§§201, 205, 206 (16 USC 824, 824d, 824e))
- Establishes the California Public Utilities Commission (CPUC) with jurisdiction over all public utilities, including electrical and gas corporations. Grants the CPUC certain general powers over all public utilities, subject to control by the Legislature. (Article XII of the California Constitution)
- Requires the California Energy Commission (CEC) to conduct assessments and forecasts of all aspects of energy industry supply, production, transportation, delivery and distribution, demand, and prices and to use these assessments and forecasts to develop and evaluate energy policies and programs that conserve resources, protect the environment, ensure energy reliability, enhance the state's economy, and protect public health and safety. (Public Resources Code §25301(a))
- Establishes the CAISO as a nonprofit public benefit corporation, and requires the CAISO to ensure the efficient use and reliable operation of the electrical transmission grid consistent with the achievement of planning and operating reserve criteria, as specified. (Public Utilities Code §345.5)
- Requires the CPUC, as part of the Public Utilities Act, to identify a diverse and balanced portfolio of resources needed to ensure a reliable electricity supply that provides optimal integration of renewable energy in a cost-effective manner. The act also requires the CPUC, in consultation with the CEC, to identify all potentially achievable cost-effective electricity efficiency savings and establish efficiency targets for an electrical corporation, as specified. (Public Utilities Code §§454.51 and 454.55)
- Requires the CPUC, in consultation with the CEC on or before March 31, 2024, to provide transmission-focused guidance to the CAISO about resource portfolios of expected future renewable energy resources and zero-carbon resources, including the allocation of those resources by region based on technical feasibility and commercial interest in each region to allow the CAISO to identify and approve transmission facilities needed to interconnect resources and reliably serve the needs of load centers, as specified. (Public Utilities Code §454.57)
This bill:
- Requires the CPUC, CEC, and the CAISO, every five years, to review the December 2022 memorandum of understanding and related workplan to ensure the memorandum and workplan reflect the coordination that is needed to help meet the state’s energy goals.
- Requires the CEC, CPUC, and CAISO to jointly develop and recommend an expedited permitting roadmap that describes timeframes and milestones for a coordinated, comprehensive, and efficient permitting process for electrical transmission infrastructure, and to provide an opportunity for stakeholder input and public comment. Requires the CEC, CPUC, and CAISO, on or before December 31, 2024, to complete and submit the recommended framework for the expedited permitting roadmap to the Natural Resources Agency and the relevant fiscal and policy committees of the Legislature.
- Requires the CPUC to require each electrical corporation to annually review its long-term transmission infrastructure needs for the subsequent 10 years, based on the interconnection requests it receives, to annually report to the CPUC on that review, and to ensure those needs incorporate each local government’s present and future needs for new service connections and capacity service upgrades that may require transmission upgrades.
- Requires the electrical corporation, when an electrical corporation completes a transmission infrastructure project, to report the final cost of the project to the CPUC. Requires the CPUC, in consultation with California balancing authorities, on or before December 1, 2024, and annually thereafter, to submit a report to the Legislature that evaluates transmission and resource planning that has been conducted or implemented, including pursuant to the memorandum of understanding and related workplan.
Background
Transmission planning process. Each year, the CAISO conducts its transmission planning process to identify potential system limitations, as well as, opportunities for system reinforcements that improve reliability and efficiency. The transmission plan fulfills the CAISO’s core responsibility to identify and plan the development of solutions, transmission or otherwise, to meet the future needs of the electricity grid. The CAISO Transmission Plan provides a comprehensive evaluation of the CAISO transmission grid to address grid reliability requirements, identify upgrades needed to successfully meet California’s policy goals, and explore projects that can bring economic benefits to consumers. The plan relies heavily on key inputs from state agencies in translating legislative policy into actionable policy driven inputs. Transmission owners recover the costs of CAISO-approved projects through the Transmission Access Charge (TAC). The transmission owner submits an application to FERC to recover project costs. FERC approves just and reasonable costs and rate of return. CAISO charges transmission customers based on FERC-approved costs. These costs are collected from electric utility customers as part of the transmission and distribution portion of the electric utility bill.
The development of the transmission plan entails annual public stakeholder process that is conducted pursuant to the CAISO’s FERC-approved tariff. It includes a three phase process that leads to annual CAISO Board of Governor approval of transmission plan and associated transmission projects. The plan is prepared in the larger context of supporting important energy and environmental policies while maintaining reliability through a resilient electric system.
There are three main categories of CAISO approved transmission projects:
- Reliability projects to meet federal standards;
- Policy projects to meet state policy goals (i.e., renewable portfolio standard);
- Economic projects that reduce congestion, production costs, transmission losses, capacity requirements or other electric supply costs.
Additionally, there are other transmission planning efforts, including local capacity requirements, special studies, interregional transmission project, and others. Transmission owners recover the costs of ISO-approved projects through the TAC. The transmission owner submits an application to FERC to recover project costs. FERC approves just and reasonable costs and rate of return. The CAISO charges transmission customers based on FERC-approved costs.
Forecasting by CEC and supply-side inputs by CPUC. The CEC conducts energy demand forecast used to inform several planning processes, including the CAISO’s transmission planning process. The demand forecast is often a 10-year outlook for electricity and natural gas sales, consumption, and peak and hourly electricity demand. The most recent demand forecast update, is a 13-year forecast. Additionally, the CPUC provides energy resource supply-side inputs, including an annual resource portfolio, to inform the transmission planning by the CAISO.
CAISO Annual Transmission Planning Process (TPP) which evaluates the electricity system’s needs based on portfolios developed by the CPUC and in consultation with the CEC, identifies the necessary new transmission lines and upgrades to existing transmission lines required to assure reliability and to further public policy goals. The most recent 2023-24 TPP Portfolios were transmitted to CAISO planning for approximately 86 gigawatts of new resources by 2035.
SB 100 (De León, Chapter 312, Statutes of 2018). SB 100 established the 100 Percent Clean Energy Act of 2017 which increases the Renewables Portfolio Standard (RPS) requirement from 50 percent by 2030 to 60 percent, and created the policy of planning to meet all of the state's retail electricity supply with a mix of RPS-eligible and zero-carbon resources by December 31, 2045, for a total of 100 percent clean energy. SB 100 also required California Air Resources Board, CEC, and CPUC to issue a joint report by January 1, 2021, and at least every four years, that describes technologies, forecasts, affordability, and system and local reliability. The report is required to include an evaluation of costs and benefits to customer rate impacts, as well as, barriers to achieving the SB 100 policy. The first Joint Agency report was issued in 2021 and found that the state may need upwards of three times the energy resource capacity to meet the SB 100 goals.
CAISO 20-Year Transmission Outlook. In September 2021, the CAISO released a 20-Year Transmission Outlook for the electric grid, in collaboration with the CPUC and the CEC, with the goal of exploring the longer-term grid requirements and options for meeting the State’s SB 100 clean energy objectives reliably and cost-effectively. The 20-Year Transmission Outlook intends for the expanded planning horizon to provide valuable input for resource planning processes conducted by the CPUC and CEC, and to provide a longer-term context and framing of pertinent issues in the CAISO’s ongoing annual 10-Year Transmission Plan.
Transmission Development Forum. The Transmission Development Forum is a more recent joint effort between the CAISO and the CPUC to discuss and track Participating Transmission Owners expansion and network upgrade projects and schedules. The Transmission Development Forum creates a single forum to track the status of transmission network upgrade projects that affect generators and all other transmission projects approved in the CAISO’s transmission planning process. The effort allows for increased transparency for all stakeholders about transmission projects and enhances accountability of transmission owners by having them explain schedule changes, delays, and address stakeholders’ questions.
Tracking Energy Development (TED) Task Force. The TED Taskforce is also a recent joint effort of the CPUC, CEC, CAISO, and Office of Business and Economic Development (GO-Biz) to track new energy projects under development. According to the CPUC, the objective is to build on the success of ad hoc 2021 efforts to provide energy resource project development support, as appropriate, and identify barriers and mitigation strategies to accelerate energy project development. Currently, the TED Taskforce is focused on near-term projects, roughly 200 contracted projects needed for summer reliability in 2022 and 2023.
December 2022 Memorandum of Understanding (MOU). The CPUC, CEC, and CAISO entered an updated MOU, replacing the 2010 MOU, in order to better coordinate their respective and shared efforts for the timely development of resources needed to achieve the state’s clean energy goals reliably and economically, and focuses on:
- Establishing or reaffirming linkages between the CEC’s Integrated Energy Policy Report and SB 100 activities, the CPUC’s Integrated Resource Planning process and the ISO’s 20-Year Transmission Outlook and annual transmission planning and approval process.
- Affirming the commitment to tighten linkages between planning, procurement direction, and the ISO interconnection process - and local planning - to the greatest extent possible; and,
- Folding the existing state agency and single forecast coordination into the MOU.
Permitting transmission projects. Electric transmission lines are generally high voltage lines that move electricity from generation resources (power plants) to distribution lines in neighborhoods. Companies, usually electric investor-owned utilities, proposing the construction of new transmission serving the CAISO balancing authority area are required to obtain a permit from the CPUC for construction of certain specified infrastructure listed under Public Utilities Code §1001, including transmission projects. The CPUC reviews permit applications under two concurrent processes: (1) an environmental review pursuant to the California Environmental Quality Act (CEQA), and (2) the review of project need and costs pursuant to Public Utilities Code §1001 and General Order (GO) 131-D (Certificate of Public Necessity and Convenience (CPCN)).
CPUC’s GO 131-D. GO 131-D specifically addresses the procedures to be followed in applications for siting of electric transmission infrastructure. In essence, it implements the requirements of Public Utilities Code Section 1001. Under GO 131-D, the CPUC has established the criteria that would trigger the need for a permit to build or renovate electrical facilities, including transmission lines and substations. Of the hundreds of major capital electric transmission projects completed in California each year, on average one-two per year may trigger a permit, and thus CEQA. Most projects are reviewed through the CPUC’s advice letter approval process, which tends to be more simplified and expedient than a full application for a CPCN.
The level of analysis performed by the CPUC varies with the size (measured in voltage) of the transmission project.
Comments
This bill attempts to address challenges with the need for the expanded buildout of the electric transmission system serving the CAISO balancing authority area, including the capacity limitations on existing transmission in the northern coast of the state. By requiring more regular review and updates to the December 2022 MOU and related workplan, this bill is intended to ensure the MOU remains current to better reflect any changes to conditions. Additionally, this bill requires the CPUC, CEC, and CASIO to jointly develop and recommend an expedited permitting roadmap with timeframes and milestones for permitting electrical transmission infrastructure. This bill also attempts to ensure that local needs are informing the development of transmission planning, as currently the Humboldt area of the state is experiencing capacity limitations on the electrical system, in part, due to limited transmission capacity.
Related/Prior Legislation
SB 420 (Becker, 2023) allows transmission projects, identified by an agency chosen by the governor to be necessary for reliability and to meet the state’s clean energy goals, to become environmental leadership development projects eligible for CEQA streamlining. The bill is pending on the Senate Floor.
SB 619 (Padilla, 2023) requires the CEC to give priority to applications for eligible electrical transmission facilities applying for the opt-in permit streamlining, if the applicant certifies that a capital investment of at least $250,000,000 will be made over a period of five years. The bill is pending on the Senate Floor.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
According to the Senate Appropriations Committee:
- The CEC estimates ongoing costs of about $230,000 annually (General Fund or special fund) and one position to develop an expedited permitting roadmap.
- The CPUC expects no fiscal impact resulting from this bill.
SUPPORT: (Verified 5/18/23)
Clean Air Task Force
Humboldt County
Sonoma Clean Power
OPPOSITION: (Verified 5/18/23)
None received
ARGUMENTS IN SUPPORT: According to the author, “It's become abundantly clear that PG&E has some pretty significant constraints surrounding capacity and an antiquated transmission system. We also need to conduct a system-wide capacity analysis of PG&E to learn about issues like insufficient transmission infrastructure and head off problems like those that occurred in Humboldt County. This has gone on for far too long and this State has to put a stop to it. That’s why we’re advancing critical legislation, SB 319, which would force PG&E to do their job connecting homes, businesses and green power projects with safe and reliable distribution and transmission lines along with advancing a long term fix-it plan for their antiquated system. The bill will require utilities to analyze challenges with providing service to individual customers and what shortfalls they have in capacity to provide power across their service area.”
Prepared by: Nidia Bautista / E., U. & C. / (916) 651-4107
5/20/23 12:44:27
**** END ****
SENATE COMMITTEE ON
Senator Anthony Portantino, Chair
2023 - 2024 Regular Session
SB 319 (McGuire) - Electricity: transmission planning
Version: | Policy Vote: |
Urgency: | Mandate: |
Hearing Date: | Consultant: |
Bill Summary:
This bill would require the California Public Utilities Commission (CPUC) and California Energy Commission (CEC), in coordination with the California Independent System Operator (CAISO), to review every five years their December 2022 memorandum of understanding (MOU), as well as to develop a permit streamlining roadmap for transmission projects.
Fiscal Impact:
- The CEC estimates ongoing costs of about $230,000 annually (General Fund or special fund) and one position to develop an expedited permitting roadmap.
- The CPUC expects no fiscal impact resulting from this bill.
Background:
Transmission project permitting. Electric transmission lines are generally high voltage lines that move electricity from generation resources (power plants) to distribution lines in neighborhoods. Companies, usually electric investor-owned utilities, proposing the construction of new transmission, are required to obtain a permit from the CPUC for construction of certain specified infrastructure listed under Public Utilities Code §1001, including transmission projects. The CPUC reviews permit applications under two concurrent processes: (1) an environmental review pursuant to the California Environmental Quality Act (CEQA), and (2) the review of project need and costs pursuant to Public Utilities Code §1001 and General Order (GO) 131-D (Certificate of Public Necessity and Convenience (CPCN)).
Under CPUC’s GO 131-D, the CPUC has established the criteria that would trigger the need for a permit to build or renovate electrical facilities, including transmission lines and substations. Of the hundreds of major capital electric transmission projects completed in California each year, on average one-two per year may trigger a permit, and thus CEQA. Most projects are reviewed through the CPUC’s advice letter approval process, which tends to be more simplified and expedient than a full application for a CPCN.
Transmission planning process. Each year, the CAISO conducts its transmission planning process to identify potential system limitations as well as opportunities for system reinforcements that improve reliability and efficiency. The transmission plan fulfills the CAISO’s core responsibility to identify and plan the development of solutions, transmission or otherwise, to meet the future needs of the electricity grid. The CAISO Transmission Plan provides a comprehensive evaluation of the CAISO transmission grid to address grid reliability requirements, identify upgrades needed to successfully meet California’s policy goals, and explore projects that can bring economic benefits to consumers. The plan relies heavily on key inputs from state agencies in translating legislative policy into actionable policy driven inputs. Transmission owners recover the costs of CAISO-approved projects through the Transmission Access Charge (TAC). The transmission owner submits an application to FERC to recover project costs. FERC approves just and reasonable costs and rate of return. CAISO charges transmission customers based on FERC-approved costs. These costs are collected from electric utility customers as part of the transmission and distribution portion of the electric utility bill.
CAISO Annual Transmission Planning Process (TPP) evaluates the electricity system’s needs based on portfolios developed by the CPUC and in consultation with the CEC, identifies the necessary new transmission lines and upgrades to existing transmission lines required to assure reliability and to further public policy goals. The most recent 2023-24 TPP Portfolios were transmitted to CAISO last month, planning for approximately 86 gigawatts of new resources by 2035.
SB 100 (De León, Chapter 312, Statutes of 2018). SB 100 established the 100 Percent Clean Energy Act of 2017 which increases the Renewables Portfolio Standard (RPS) requirement from 50 percent by 2030 to 60 percent, and created the policy of planning to meet all of the state's retail electricity supply with a mix of RPS-eligible and zero-carbon resources by December 31, 2045, for a total of 100 percent clean energy. SB 100 also required California Air Resources Board, CEC, and CPUC to issue a joint report by January 1, 2021, and at least every four years, that describes technologies, forecasts, affordability, and system and local reliability. The report is required to include an evaluation of costs and benefits to customer rate impacts, as well as, barriers to achieving the SB 100 policy. The first Joint Agency report was issued January 2021 and found that the state may need upwards of three times the energy resource capacity to meet the SB 100 goals.
December 2022 MOU. The CPUC, CEC, and CAISO entered an updated MOU, replacing a prior 2010 MOU in order to better coordinate their respective and shared efforts for the timely development of resources needed to achieve the state’s clean energy goals reliably and economically, and focuses on:
- Establishing or reaffirming linkages between the CEC’s Integrated Energy Policy Report and SB 100 activities, the CPUC’s Integrated Resource Planning process and the ISO’s 20-Year Transmission Outlook and annual transmission planning and approval process.
- Affirming the commitment to tighten linkages between planning, procurement direction, and the ISO interconnection process - and local planning - to the greatest extent possible; and,
- Folding the existing state agency and single forecast coordination into the MOU.
Proposed Law:
This bill would require the CPUC, CEC, and the CAISO to review every five years a December 2022 MOU between them, as well as to develop a permit streamlining roadmap for transmission projects. Specifically, this bill would:
- Require the CPUC and the CEC, in coordination with the CAISO, to review every five years a December 2022 MOU between them and a related workplan to ensure they reflect the coordination that is needed to help meet the state’s energy goals.
- Require the CEC, CPUC, and CAISO to jointly develop and recommend an expedited permitting roadmap that describes timeframes and milestones for a coordinated, comprehensive, and efficient permitting process for electrical transmission infrastructure, and to provide an opportunity for stakeholder input and public comment. Require the CEC, CPUC, and CAISO, on or before December 31, 2024, to complete and submit the recommended framework for the expedited permitting roadmap to the Natural Resources Agency and the relevant fiscal and policy committees of the Legislature.
- Require the CPUC to require each electrical corporation to annually review its long-term transmission infrastructure needs for the subsequent 10 years, based on the interconnection requests it receives, to annually report to the CPUC on that review, and to ensure those needs incorporate each local government’s present and future needs for new service connections and capacity service upgrades that may require transmission system upgrades.
- Require the electrical corporation, when an electrical corporation completes a transmission infrastructure project, to report the final cost of the project to the CPUC. Requires the CPUC, in consultation with California balancing authorities, on or before December 1, 2024, and annually thereafter, to submit a report to the Legislature that evaluates transmission and resource planning that has been conducted or implemented, including pursuant to the MOU and related workplan, as specified.
Related Legislation:
SB 420 (Becker, 2023) would allow transmission projects, identified by an agency chosen by the governor to be necessary for reliability and to meet the state’s clean energy goals, to become environmental leadership development projects eligible for CEQA streamlining.
SB 619 (Padilla, 2023) would require the CEC to give priority to applications for eligible electrical transmission facilities applying for the opt-in permit streamlining, if the applicant certifies that a capital investment of at least $250,000,000 will be made over a period of five years.
-- END --
SENATE COMMITTEE ON ENERGY, UTILITIES AND COMMUNICATIONS
Senator Steven Bradford, Chair
2023 - 2024 Regular
Bill No: Hearing Date: 4/24/2023
Author: | |||
Version: | Amended | ||
Urgency: | Fiscal: | ||
Consultant: | |||
SUBJECT:
DIGEST: This bill codifies a December 2022 memorandum of understanding (MOU) between the California Public Utilities Commission (CPUC), California Energy Commission (CEC), and the California Independent System Operator (CAISO) regarding transmission and resource planning and implementation. This bill also requires the three entities to develop a permit streamlining roadmap for transmission projects.
ANALYSIS:
Existing law:
- Establishes that U.S. Federal Energy Regulatory Commission (FERC) has exclusive jurisdiction over the transmission of electric energy in interstate commerce. Also establishes the process and procedures for establishing transmission of electric energy in interstate commerce by public utilities, i.e., the rates, terms & conditions of interstate electric transmission by public utilities. (Federal Power Act §§§201, 205, 206 (16 USC 824, 824d, 824e))
- Establishes the CAISO as a nonprofit public benefit corporation, and requires the CAISO to ensure the efficient use and reliable operation of the electrical transmission grid consistent with the achievement of planning and operating reserve criteria, as specified. (Public Utilities Code §345.5)
- Establishes the CPUC with jurisdiction over all public utilities, including electrical and gas corporations. Grants the CPUC certain general powers over all public utilities, subject to control by the Legislature. (Article XII of the California Constitution)
- Requires the CEC to conduct assessments and forecasts of all aspects of energy industry supply, production, transportation, delivery and distribution, demand, and prices and to use these assessments and forecasts to develop and evaluate energy policies and programs that conserve resources, protect the environment, ensure energy reliability, enhance the state's economy, and protect public health and safety. (Public Resources Code §25301(a))
- Requires the CPUC, as part of the Public Utilities Act, to identify a diverse and balanced portfolio of resources needed to ensure a reliable electricity supply that provides optimal integration of renewable energy in a cost-effective manner. The act also requires the CPUC, in consultation with the CEC, to identify all potentially achievable cost-effective electricity efficiency savings and establish efficiency targets for an electrical corporation, as specified. (Public Utilities Code §§454.51 and 454.55)
- Requires the CPUC, in consultation with the CEC on or before March 31, 2024, to provide transmission-focused guidance to the CAISO about resource portfolios of expected future renewable energy resources and zero-carbon resources, including the allocation of those resources by region based on technical feasibility and commercial interest in each region to allow the CAISO to identify and approve transmission facilities needed to interconnect resources and reliably serve the needs of load centers, as specified. (Public Utilities Code §454.57)
This bill:
- Codifies a December 2022 MOU between the CPUC, CEC, and the CAISO regarding transmission and resource planning and implementation.
- Requires the CEC, CPUC, and CAISO to coordinate and implement a joint workplan through specified proceedings and other resource planning activities led by the CEC, and to agree on principles for forecast cases and a single recommended forecast set and use it consistently in transmission planning and resource procurement cycles to the extent possible.
- Requires the CPUC to incorporate long-term statewide resource planning efforts led by the CEC into its proceedings for resource portfolios developed for resource procurement and transmission planning purposes. Requires the CAISO to provide the CPUC with an assessment of transmission planning needs and estimates spanning the CAISO balancing authority area for resource planning purposes, and to coordinate with the CEC on transmission needs in support of long-term informational analysis.
- Requires the CPUC to incorporate CAISO-provided transmission information into its considerations in developing resource portfolios and to map the resulting portfolio resources to specific electrical locations through a joint effort with the CEC and CAISO.
- Requires the CAISO, in its transmission planning process, to conduct a stakeholder process that enables meaningful public participation to ensure that appropriate study assumptions and scenarios are identified to support development of its final transmission plan, as specified.
- Requires the CPUC, in authorizing or requiring procurement of resources by electrical corporations, electric service providers, or community choice aggregators, to provide direction to pursue resources with the operational characteristics and geographic locations consistent with the resource planning conducted by the CEC and CPUC and the transmission planning conducted by the CAISO based on that resource planning.
- Requires the CAISO to prioritize interconnection process activities that support resources with operational characteristics and geographic locations consistent with that resource planning and its transmission planning based on that resource planning, and to coordinate with the CEC and CPUC to manage the resource interconnections and network upgrade projects in the interconnection process and provide transparency to ensure timely interconnection to the extent possible.
- Requires the CEC, CPUC, and CAISO to jointly develop and recommend an expedited permitting roadmap that describes timeframes and milestones for a coordinated, comprehensive, and efficient permitting process for electrical transmission infrastructure, and to provide an opportunity for stakeholder input and public comment. Requires the CEC, CPUC, and CAISO, on or before December 31, 2024, to complete and submit the recommended framework for the expedited permitting roadmap to the Natural Resources Agency and the relevant fiscal and policy committees of the Legislature.
- Requires the CPUC to require each electrical corporation to annually review its long-term transmission infrastructure needs for the subsequent 10 years, based on the interconnection requests it receives, to annually report to the CPUC on that review, and to coordinate with local governments to identify each local government’s present and future interconnection needs.
- Requires the electrical corporation, when an electrical corporation completes a transmission infrastructure project, to report the final cost of the project to the CPUC. Requires the CPUC, in consultation with California balancing authorities, on or before December 1, 2024, and annually thereafter, to submit a report to the Legislature that evaluates transmission and resource planning that has been conducted or implemented.
Background
Transmission projects. Electric transmission lines are generally high voltage lines that move electricity from generation resources (power plants) to distribution lines in neighborhoods. Companies, usually electric investor-owned utilities, proposing the construction of new transmission, are required to obtain a permit from the CPUC for construction of certain specified infrastructure listed under Public Utilities Code §1001, including transmission projects. The CPUC reviews permit applications under two concurrent processes: (1) an environmental review pursuant to the California Environmental Quality Act (CEQA), and (2) the review of project need and costs pursuant to Public Utilities Code §1001 and General Order (GO) 131-D (Certificate of Public Necessity and Convenience (CPCN)).
CPUC’s GO 131-D. GO 131-D specifically addresses the procedures to be followed in applications for siting of electric transmission infrastructure. In essence, it implements the requirements of Public Utilities Code §1001. Under GO 131-D, the CPUC has established the criteria that would trigger the need for a permit to build or renovate electrical facilities, including transmission lines and substations. Of the hundreds of major capital electric transmission projects completed in California each year, on average one-two per year may trigger a permit, and thus CEQA. Most projects are reviewed through the CPUC’s advice letter approval process, which tends to be more simplified and expedient than a full application for a CPCN.
The level of analysis performed by the CPUC varies with the size (measured in voltage) of the transmission project.
- Projects below 50 kilovolts (kV) are considered distribution projects, rather than transmission projects, and in general do not require CPUC approval.
- Projects between 50 kV and 200 kV require a Permit to Construct from the CPUC, which consists primarily of an environmental review pursuant to CEQA. The CPUC process generally does not require a detailed analysis of the need for or economics of these projects.
- Projects over 200 kV require a CPCN from the CPUC. The CPCN process analyzes the need for the project and the economics of the project, as well as, the environmental impacts of the project.
Transmission planning process. Each year, the CAISO conducts its transmission planning process to identify potential system limitations as well as opportunities for system reinforcements that improve reliability and efficiency. The transmission plan fulfills the CAISO’s core responsibility to identify and plan the development of solutions, transmission or otherwise, to meet the future needs of the electricity grid. The CAISO Transmission Plan provides a comprehensive evaluation of the CAISO transmission grid to address grid reliability requirements, identify upgrades needed to successfully meet California’s policy goals, and explore projects that can bring economic benefits to consumers. The plan relies heavily on key inputs from state agencies in translating legislative policy into actionable policy driven inputs. Transmission owners recover the costs of CAISO-approved projects through the Transmission Access Charge (TAC). The transmission owner submits an application to FERC to recover project costs. FERC approves just and reasonable costs and rate of return. CAISO charges transmission customers based on FERC-approved costs. These costs are collected from electric utility customers as part of the transmission and distribution portion of the electric utility bill.
The development of the transmission plan entails annual public stakeholder process that is conducted pursuant to the CAISO’s FERC-approved tariff. It includes a three phase process that leads to annual CAISO Board of Governor approval of transmission plan and associated transmission projects. The plan is prepared in the larger context of supporting important energy and environmental policies while maintaining reliability through a resilient electric system.
There are three main categories of CAISO approved transmission projects:
- Reliability projects to meet federal standards;
- Policy projects to meet state policy goals (i.e., renewable portfolio standard);
- Economic projects that reduce congestion, production costs, transmission losses, capacity requirements or other electric supply costs.
Additionally, there are other transmission planning efforts, including local capacity requirements, special studies, interregional transmission project, and others. Transmission owners recover the costs of ISO-approved projects through the TAC. The transmission owner submits an application to FERC to recover project costs. FERC approves just and reasonable costs and rate of return. The CAISO charges transmission customers based on FERC-approved costs.
Forecasting by CEC and supply-side inputs by CPUC. The CEC conducts energy demand forecast used to inform several planning processes, including the CAISO’s transmission planning process. The demand forecast is often a 10-year outlook for electricity and natural gas sales, consumption, and peak and hourly electricity demand. The most recent demand forecast update, is a 13-year forecast. Additionally, the CPUC provides energy resource supply-side inputs, including an annual resource portfolio, to inform the transmission planning by the CAISO.
CAISO Annual Transmission Planning Process (TPP) which evaluates the electricity system’s needs based on portfolios developed by the CPUC and in consultation with the CEC, identifies the necessary new transmission lines and upgrades to existing transmission lines required to assure reliability and to further public policy goals. The most recent 2023-24 TPP Portfolios were transmitted to CAISO last month, planning for approximately 86 gigawatts of new resources by 2035.
SB 100 (De León, Chapter 312, Statutes of 2018). SB 100 established the 100 Percent Clean Energy Act of 2017 which increases the Renewables Portfolio Standard (RPS) requirement from 50 percent by 2030 to 60 percent, and created the policy of planning to meet all of the state's retail electricity supply with a mix of RPS-eligible and zero-carbon resources by December 31, 2045, for a total of 100 percent clean energy. SB 100 also required California Air Resources Board, CEC, and CPUC to issue a joint report by January 1, 2021, and at least every four years, that describes technologies, forecasts, affordability, and system and local reliability. The report is required to include an evaluation of costs and benefits to customer rate impacts, as well as, barriers to achieving the SB 100 policy. The first Joint Agency report was issued January 2021 and found that the state may need upwards of three times the energy resource capacity to meet the SB 100 goals.
CAISO 20-Year Transmission Outlook. The CAISO created a 20-Year Transmission Outlook for the electric grid, in collaboration with the CPUC and the CEC, with the goal of exploring the longer-term grid requirements and options for meeting the State’s SB 100 clean energy objectives reliably and cost-effectively. The 20-Year Transmission Outlook was released in September 2021 and the CAISO intends for the expanded planning horizon to provide valuable input for resource planning processes conducted by the CPUC and CEC, and to provide a longer-term context and framing of pertinent issues in the CAISO’s ongoing annual 10-Year Transmission Plan.
Transmission Development Forum. The Transmission Development Forum is a recent joint effort between the CAISO and the CPUC to discuss and track Participating Transmission Owners expansion and network upgrade projects and schedules. The Transmission Development Forum creates a single forum to track the status of transmission network upgrade projects that affect generators and all other transmission projects approved in the CAISO’s transmission planning process. The effort allows for increased transparency for all stakeholders about transmission projects and enhances accountability of transmission owners by having them explain schedule changes, delays, and address stakeholders’ questions.
Tracking Energy Development (TED) Task Force. The TED Taskforce is also a recent joint effort of the CPUC, CEC, CAISO, and Office of Business and Economic Development (GO-Biz) to track new energy projects under development. According to the CPUC, the objective is to build on the success of ad hoc 2021 efforts to provide energy resource project development support, as appropriate, and identify barriers and mitigation strategies to accelerate energy project development. Currently, the TED Taskforce is focused on near-term projects, roughly 200 contracted projects needed for summer reliability in 2022 and 2023.
December 2022 MOU. The CPUC, CEC, and CAISO entered an updated MOU, replacing the 2010 MOU, in order to better coordinate their respective and shared efforts for the timely development of resources needed to achieve the state’s clean energy goals reliably and economically, and focuses on:
- Establishing or reaffirming linkages between the CEC’s Integrated Energy Policy Report and SB 100 activities, the CPUC’s Integrated Resource Planning process and the ISO’s 20-Year Transmission Outlook and annual transmission planning and approval process.
- Affirming the commitment to tighten linkages between planning, procurement direction, and the ISO interconnection process - and local planning - to the greatest extent possible; and,
- Folding the existing state agency and single forecast coordination into the MOU.
Comments
This bill codifies the December 2022 MOU into the statute. Entities have raised concerns that codifying the MOU could limit the ability of the agencies and CAISO to remain nimble to changing conditions. The author has expressed his desire to avoid limiting the agencies and CAISO unnecessarily by codifying the MOU. With this in mind, the author and committee may wish to amend this bill to delete the language related to the MOU and joint workplan, and instead, replace with language requiring the CPUC and CEC, in consultation with the CAISO, review the MOU and related workplan every five years to ensure it reflects the coordination that is needed to meet the state’s goals.
This bill also requires the CPUC, CEC, and CASIO to jointly develop and recommend an expedited permitting roadmap with timeframes and milestones for permitting electrical transmission infrastructure. San Diego Gas & Electric (SDG&E) supports this bill’s efforts to streamline permitting and recommends that this bill be revised to require the agencies to set a maximum limit on the entire permitting process of two to three years.
Amendments needed. The language in this bill needs clarification between the need to address transmission interconnections or energization of new customers. The author and committee may wish to amend this bill to reflect these distinctions, including the role of coordination with local governments as it pertains to both.
Prior/Related Legislation
SB 420 (Becker, 2023) allows transmission projects, identified by an agency chosen by the governor to be necessary for reliability and to meet the state’s clean energy goals, to become environmental leadership development projects eligible for CEQA streamlining. The bill is pending in this committee.
SB 619 (Padilla, 2023) requires the CEC to give priority to applications for eligible electrical transmission facilities applying for the opt-in permit streamlining, if the applicant certifies that a capital investment of at least $250,000,000 will be made over a period of five years. The bill is pending in this committee.
FISCAL EFFECT: Appropriation: Fiscal Com.: Local:
SUPPORT:
Clean Air Task Force
County of Humboldt
Sonoma Clean Power
OPPOSITION:
San Diego Gas & Electric, unless amended
ARGUMENTS IN SUPPORT: According to the author:
It's become abundantly clear that PG&E has some pretty significant constraints surrounding capacity and an antiquated transmission system. We also need to conduct a system-wide capacity analysis of PG&E to learn about issues like insufficient transmission infrastructure and head off problems like those that occurred in Humboldt County. This has gone on for far too long and this State has to put a stop to it. That’s why we’re advancing critical legislation, SB 319, which would force PG&E to do their job connecting homes, businesses and green power projects with safe and reliable distribution and transmission lines along with advancing a long term fix-it plan for their antiquated system. The bill will require utilities to analyze challenges with providing service to individual customers and what shortfalls they have in capacity to provide power across their service area.
ARGUMENTS IN OPPOSITION: SDG&E opposes this bill arguing it would limit flexibility in transmission planning by codifying the MOU between the CEC, CPUC, and CAISO. Additionally, SDG&E contends that load serving entities already plan for the needs of their customers through the CPUC’s Integrated Resource Planning process, therefore, they believe the elements of the bill related to coordinating with local governments are not necessary. Lastly, SDG&E “recommends that this bill be revised to require the agencies to set a maximum limit on the entire permitting process of two years, or three years at most.”