SB 586: Flood management: Sacramento-San Joaquin Valley.
- Session Year: 2023-2024
- House: Senate
- Latest Version Date: 2024-04-30
Current Status:
Passed
(2024-04-30: Chaptered by Secretary of State. Chapter 10, Statutes of 2024.)
Introduced
In Committee
First Chamber
In Committee
Second Chamber
Enacted
Existing law provides that unless a city or county within the Sacramento-San Joaquin Valley makes certain findings after the effective date of specified amendments to its general plan and zoning ordinance, the Planning and Zoning Law prohibits a city or county from entering into a development agreement for property located in a flood hazard zone; approving a discretionary permit, ministerial permit, or other discretionary entitlement for a project that is located within a flood hazard zone, as specified; or approving a tentative map, or a parcel map for which a tentative map was not required, for a subdivision that is located within a flood hazard zone. Those findings include, among others, that the local flood management agency has made adequate progress on the construction of a flood protection system that will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas. Existing law further requires urban and urbanizing areas protected by any levee that is part of the facilities of the State Plan of Flood Control to achieve the urban level of flood protection by 2025, with a specified exception to the deadline for the Mossdale Tract to achieve the urban level of flood protection by 2028 and for the City of West Sacramento to achieve the urban level of flood protection by 2030.
Existing law authorizes the Department of Water Resources to require the San Joaquin Area Flood Control Agency and the West Sacramento Area Flood Control Agency to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties unreasonably approving any new development in the Mossdale Tract between the years 2025 and 2028 and the City of West Sacramento between the years 2025 and 2030, respectively.
This bill would extend the specified exception to the deadline for the Mossdale Tract and the City of West Sacramento to achieve the urban level of flood protection to 2040. The bill would also extend the Department of Water Resources authority to require the San Joaquin Area Flood Control Agency and the West Sacramento Area Flood Control Agency to contribute its fair and reasonable share of property damage, as described above, to between the years 2025 and 2040.
This bill would require, on or before December 31, 2028, and every 5 years thereafter until December 31, 2038, the West Sacramento Area Flood Control Agency and the San Joaquin Area Flood Control Agency to provide a report to the Senate Natural Resources and Water Committee, the Assembly Water, Parks, and Wildlife Committee, the Senate Budget Subcommittee No. 2, and the Assembly Budget Subcommittee No. 4 describing plans and actions taken to improve flood protection in the preceding 5 years in the City of West Sacramento and the Mossdale Tract, as specified. The bill would repeal these reporting requirements on January 1, 2039.
This bill would make legislative findings and declarations as to the necessity of a special statute for the Sacramento-San Joaquin Valley.
This bill would declare that it is to take effect immediately as an urgency statute.
Existing law provides that unless a city or county within the Sacramento-San Joaquin Valley makes certain findings after the effective date of specified amendments to its general plan and zoning ordinance, the Planning and Zoning Law prohibits a city or county from entering into a development agreement for property located in a flood hazard zone; approving a discretionary permit, ministerial permit, or other discretionary entitlement for a project that is located within a flood hazard zone, as specified; or approving a tentative map, or a parcel map for which a tentative map was not required, for a subdivision that is located within a flood hazard zone. Those findings include, among others, that the local flood management agency has made adequate progress on the construction of a flood protection system that will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas. Existing law further requires urban and urbanizing areas protected by any levee that is part of the facilities of the State Plan of Flood Control to achieve the urban level of flood protection by 2025, with a specified exception to the deadline for the Mossdale Tract to achieve the urban level of flood protection by 2028 and for the City of West Sacramento to achieve the urban level of flood protection by 2030.
Existing law authorizes the Department of Water Resources to require the San Joaquin Area Flood Control Agency and the West Sacramento Area Flood Control Agency to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties unreasonably approving any new development in the Mossdale Tract between the years 2025 and 2028 and the City of West Sacramento between the years 2025 and 2030, respectively.
This bill would extend the specified exception to the deadline for the Mossdale Tract and the City of West Sacramento to achieve the urban level of flood protection to 2040. The bill would also extend the Department of Water Resources authority to require the San Joaquin Area Flood Control Agency and the West Sacramento Area Flood Control Agency to contribute its fair and reasonable share of property damage, as described above, to between the years 2025 and 2040.
This bill would require, on or before December 31, 2028, and every 5 years thereafter until December 31, 2038, the West Sacramento Area Flood Control Agency and the San Joaquin Area Flood Control Agency to provide a report to the Senate Natural Resources and Water Committee, the Assembly Water, Parks, and Wildlife Committee, the Senate Budget Subcommittee No. 2, and the Assembly Budget Subcommittee No. 4 describing plans and actions taken to improve flood protection in the preceding 5 years in the City of West Sacramento and the Mossdale Tract, as specified. The bill would repeal these reporting requirements on January 1, 2039.
This bill would make legislative findings and declarations as to the necessity of a special statute for the Sacramento-San Joaquin Valley.
This bill would declare that it is to take effect immediately as an urgency statute.
Existing law provides that unless a city or county within the Sacramento-San Joaquin Valley makes certain findings after the effective date of specified amendments to its general plan and zoning ordinance, the Planning and Zoning Law prohibits a city or county from entering into a development agreement for property located in a flood hazard zone; approving a discretionary permit, ministerial permit, or other discretionary entitlement for a project that is located within a flood hazard zone, as specified; or approving a tentative map, or a parcel map for which a tentative map was not required, for a subdivision that is located within a flood hazard zone. Those findings include, among others, that the local flood management agency has made adequate progress on the construction of a flood protection system that will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas. Existing law further requires urban and urbanizing areas protected by any levee that is part of the facilities of the State Plan of Flood Control to achieve the urban level of flood protection by 2025, with a specified exception to the deadline for the Mossdale Tract to achieve the urban level of flood protection by 2028 and for the City of West Sacramento to achieve the urban level of flood protection by 2030.
Existing law authorizes the Department of Water Resources to require the San Joaquin Area Flood Control Agency and the West Sacramento Area Flood Control Agency to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties unreasonably approving any new development in the Mossdale Tract between the years 2025 and 2028 and the City of West Sacramento between the years 2025 and 2030, respectively.
This bill would extend the specified exception to the deadline for the Mossdale Tract and the City of West Sacramento to achieve the urban level of flood protection to 2040. The bill would also extend the Department of Water Resources authority to require the San Joaquin Area Flood Control Agency and the West Sacramento Area Flood Control Agency to contribute its fair and reasonable share of property damage, as described above, to between the years 2025 and 2040.
This bill would require, on or before December 31, 2028, and every 5 years thereafter until December 31, 2038, the West Sacramento Area Flood Control Agency and the San Joaquin Area Flood Control Agency to provide a report to the Senate Natural Resources and Water Committee, the Assembly Water, Parks, and Wildlife Committee, the Senate Budget Subcommittee No. 2, and the Assembly Budget Subcommittee No. 4 describing plans and actions taken to improve flood protection in the preceding 5 years in the City of West Sacramento and the Mossdale Tract, as specified. The bill would repeal these reporting requirements on January 1, 2039.
This bill would make legislative findings and declarations as to the necessity of a special statute for the Sacramento-San Joaquin Valley.
This bill would declare that it is to take effect immediately as an urgency statute.
Existing law provides that unless a city or county within the Sacramento-San Joaquin Valley makes certain findings after the effective date of specified amendments to its general plan and zoning ordinance, the Planning and Zoning Law prohibits a city or county from entering into a development agreement for property located in a flood hazard zone; approving a discretionary permit, ministerial permit, or other discretionary entitlement for a project that is located within a flood hazard zone, as specified; or approving a tentative map, or a parcel map for which a tentative map was not required, for a subdivision that is located within a flood hazard zone. Those findings include, among others, that the local flood management agency has made adequate progress on the construction of a flood protection system that will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas. Existing law further requires urban and urbanizing areas protected by any levee that is part of the facilities of the State Plan of Flood Control to achieve the urban level of flood protection by 2025, with a specified exception to the deadline for the Mossdale Tract to achieve the urban level of flood protection by 2028. 2028 and for the City of West Sacramento to achieve the urban level of flood protection by 2030.
Existing law authorizes the Department of Water Resources to require the San Joaquin Area Flood Control Agency and the West Sacramento Area Flood Control Agency to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties unreasonably approving any new development in the Mossdale Tract between the years 2025 and 2028. 2028 and the City of West Sacramento between the years 2025 and 2030, respectively.
This bill would extend the specified exception to the deadline for the Mossdale Tract and the City of West Sacramento to achieve the urban level of flood protection to 2030. 2040. The bill would also extend the Department of Water Resourcess Resources authority to require the San Joaquin Area Flood Control Agency and the West Sacramento Area Flood Control Agency to contribute its fair and reasonable share of property damage, as described above, to between the years 2025 and 2030. 2040.
This bill would make legislative findings and declarations as to the necessity of a special statute for the Mossdale Tract. Sacramento-San Joaquin Valley.
This bill would declare that it is to take effect immediately as an urgency statute.
Existing law provides that unless a city or county within the Sacramento-San Joaquin Valley makes certain findings after the effective date of specified amendments to its general plan and zoning ordinance, the Planning and Zoning Law prohibits a city or county from entering into a development agreement for property located in a flood hazard zone; approving a discretionary permit, ministerial permit, or other discretionary entitlement for a project that is located within a flood hazard zone, as specified; or approving a tentative map, or a parcel map for which a tentative map was not required, for a subdivision that is located within a flood hazard zone. Those findings include, among others, that the local flood management agency has made adequate progress on the construction of a flood protection system that will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas. Existing law further requires urban and urbanizing areas protected by any levee that is part of the facilities of the State Plan of Flood Control to achieve the urban level of flood protection by 2025, with a specified exception to the deadline for the Mossdale Tract to achieve the urban level of flood protection by 2028.
Existing law authorizes the Department of Water Resources to require the San Joaquin Area Flood Control Agency to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties unreasonably approving any new development in the Mossdale Tract between the years 2025 and 2028.
This bill would extend the specified exception to the deadline for the Mossdale Tract to achieve the urban level of flood protection to 2030. The bill would also extend the Department of Water Resourcess authority to require the San Joaquin Area Flood Control Agency to contribute its fair and reasonable share of property damage, as described above, to between the years 2025 and 2030.
This bill would make legislative findings and declarations as to the necessity of a special statute for the Mossdale Tract.
Existing law provides that unless a city or county within the Sacramento-San Joaquin Valley makes certain findings after the effective date of specified amendments to its general plan and zoning ordinance, the Planning and Zoning Law prohibits a city or county from entering into a development agreement for property located in a flood hazard zone; approving a discretionary permit, ministerial permit, or other discretionary entitlement for a project that is located within a flood hazard zone, as specified; or approving a tentative map, or a parcel map for which a tentative map was not required, for a subdivision that is located within a flood hazard zone. Those findings include, among others, that the local flood management agency has made adequate progress on the construction of a flood protection system that will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas. Existing law further requires urban and urbanizing areas protected by any levee that is part of the facilities of the State Plan of Flood Control to achieve the urban level of flood protection by 2025, with specified exceptions to the deadline for the Mossdale Tract and West Sacramento.This bill would remove the specified exceptions to the deadline for the Mossdale Tract and West Sacramento, and instead provide that the deadline to achieve an urban level of protection, or to make adequate progress on the construction of a flood system providing an urban level of protection, does not apply to the Mossdale Tract and West Sacramento so long as a flood management agency has an active federal study, a completed federal study, or an authorized federal project receiving or awaiting the receipt of federal appropriations to advance design, construction, or project closeout activities, as specified. By changing the deadline for the Mossdale Tract and West Sacramento to achieve the urban level of flood protection, or to make adequate progress on the construction of a flood system providing an urban level of protection, the bill would impose a state-mandated local program.Existing law absolves cities and counties from the requirement to contribute their fair and reasonable share of the property damage caused by a flood to the extent that the city or county has increased the states exposure to liability for property damage by unreasonably approving new development in a previously undeveloped area that is protected by a state flood control project in specified circumstances.This bill would specify that, notwithstanding those provisions, the San Joaquin Area Flood Control Agency or the West Sacramento Area Flood Control Agency may be required to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties that unreasonably approve any new development in those areas between January 1, 2025, and when urban level flood protection is achieved.This bill would make legislative findings and declarations as to the necessity of a special statute for the Sacramento-San Joaquin Valley.The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.This bill would provide that, if the Commission on State Mandates determines that the bill contains costs mandated by the state, reimbursement for those costs shall be made pursuant to the statutory provisions noted above.Existing law provides that unless a city or county within the Sacramento-San Joaquin Valley makes certain findings after the effective date of specified amendments to its general plan and zoning ordinance, the Planning and Zoning Law prohibits a city or county from entering into a development agreement for property located in a flood hazard zone; approving a discretionary permit, ministerial permit, or other discretionary entitlement for a project that is located within a flood hazard zone, as specified; or approving a tentative map, or a parcel map for which a tentative map was not required, for a subdivision that is located within a flood hazard zone. Those findings include, among others, that the local flood management agency has made adequate progress on the construction of a flood protection system that will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas. Existing law further requires urban and urbanizing areas protected by any levee that is part of the facilities of the State Plan of Flood Control to achieve the urban level of flood protection by 2025, with specified exceptions to the deadline for the Mossdale Tract and West Sacramento.
This bill would remove the specified exceptions to the deadline for the Mossdale Tract and West Sacramento, and instead provide that the deadline to achieve an urban level of protection protection, or to make adequate progress on the construction of a flood system providing an urban level of protection, does not apply to the Mossdale Tract and West Sacramento so long as a flood management agency has an active federal project in the planning, design, construction, or project closeout phase, study, a completed federal feasibility study awaiting congressional authorization, study, or an authorized federal project receiving or awaiting the receipt of federal appropriations to advance design, construction, or project closeout activities. activities, as specified. By changing the deadline for the Mossdale Tract and West Sacramento to achieve the urban level of flood protection, or to make adequate progress on the construction of a flood system providing an urban level of protection, the bill would impose a state-mandated local program.
Existing law absolves cities and counties from the requirement to contribute their fair and reasonable share of the property damage caused by a flood to the extent that the city or county has increased the states exposure to liability for property damage by unreasonably approving new development in a previously undeveloped area that is protected by a state flood control project in specified circumstances.
This bill would specify that, notwithstanding those provisions, the San Joaquin Area Flood Control Agency or the West Sacramento Area Flood Control Agency may be required to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties that unreasonably approve any new development in those areas between January 1, 2025, and when urban level flood protection is achieved.
This bill would make legislative findings and declarations as to the necessity of a special statute for the Sacramento-San Joaquin Valley.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that, if the Commission on State Mandates determines that the bill contains costs mandated by the state, reimbursement for those costs shall be made pursuant to the statutory provisions noted above.
Existing law provides that unless a city or county within the Sacramento-San Joaquin Valley makes certain findings after the effective date of specified amendments to its general plan and zoning ordinance, the Planning and Zoning Law prohibits a city or county from entering into a development agreement for property located in a flood hazard zone; approving a discretionary permit, ministerial permit, or other discretionary entitlement for a project that is located within a flood hazard zone, as specified; or approving a tentative map, or a parcel map for which a tentative map was not required, for a subdivision that is located within a flood hazard zone. Those findings include, among others, that the local flood management agency has made adequate progress on the construction of a flood protection system that will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas. Existing law further requires urban and urbanizing areas protected by any levee that is part of the facilities of the State Plan of Flood Control to achieve the urban level of flood protection by 2025, with specified exceptions to the deadline for the Mossdale Tract and West Sacramento.
This bill would remove the specified exceptions to the deadline for the Mossdale Tract and West Sacramento, and instead provide that the deadline to achieve an urban level of protection does not apply to the Mossdale Tract and West Sacramento so long as a flood management agency has an active federal project in the planning, design, construction, or project closeout phase, a completed federal feasibility study awaiting congressional authorization, or an authorized federal project awaiting the receipt of federal appropriations to advance design, construction, or project closeout activities. By changing the deadline for the Mossdale Tract and West Sacramento to achieve the urban level of flood protection, the bill would impose a state-mandated local program.
Existing law absolves cities and counties from the requirement to contribute their fair and reasonable share of the property damage caused by a flood to the extent that the city or county has increased the states exposure to liability for property damage by unreasonably approving new development in a previously undeveloped area that is protected by a state flood control project in specified circumstances.
This bill would specify that, notwithstanding those provisions, the San Joaquin Area Flood Control Agency or the West Sacramento Area Flood Control Agency may be required to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties that unreasonably approve any new development in those areas between January 1, 2025, and when urban level flood protection is achieved.
This bill would make legislative findings and declarations as to the necessity of a special statute for the Sacramento-San Joaquin Valley.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that, if the Commission on State Mandates determines that the bill contains costs mandated by the state, reimbursement for those costs shall be made pursuant to the statutory provisions noted above.
Existing law provides that unless a city or county within the Sacramento-San Joaquin Valley makes certain findings after the effective date of specified amendments to its general plan and zoning ordinance, the Planning and Zoning Law prohibits a city or county from entering into a development agreement for property located in a flood hazard zone; approving a discretionary permit, ministerial permit, or other discretionary entitlement for a project that is located within a flood hazard zone, as specified; or approving a tentative map, or a parcel map for which a tentative map was not required, for a subdivision that is located within a flood hazard zone. Those findings include, among others, that the local flood management agency has made adequate progress on the construction of a flood protection system that will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas. Existing law further requires urban and urbanizing areas protected by any levee that is part of the facilities of the State Plan of Flood Control to achieve the urban level of flood protection by 2025, with specified exceptions to the deadline for the Mossdale Tract and West Sacramento.
This bill would remove the specified exceptions to the deadline for the Mossdale Tract and West Sacramento, and instead provide that the deadline to achieve an urban level of protection does not apply, apply to the Mossdale Tract and West Sacramento so long as a flood management agency has an active federal project in the planning, design, construction, or project closeout phase, a completed federal feasibility study awaiting congressional authorization, or an authorized federal project awaiting the receipt of federal appropriations to advance design, construction, or project closeout activities. By changing the deadline for the Mossdale Tract and West Sacramento to achieve the urban level of flood protection, this the bill would impose a state-mandated local program.
Existing law absolves cities and counties from the requirement to contribute their fair and reasonable share of the property damage caused by a flood to the extent that the city or county has increased the states exposure to liability for property damage by unreasonably approving new development in a previously undeveloped area that is protected by a state flood control project in specified circumstances.
This bill would specify that, notwithstanding those provisions, the San Joaquin Area Flood Control Agency or the West Sacramento Area Flood Control Agency may be required to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties that unreasonably approve any new development in those areas between January 1, 2025, and when urban level flood protection is achieved.
This bill would make legislative findings and declarations as to the necessity of a special statute for the Sacramento-San Joaquin Valley.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that, if the Commission on State Mandates determines that the bill contains costs mandated by the state, reimbursement for those costs shall be made pursuant to the statutory provisions noted above.
Existing law provides that unless a city or county within the Sacramento-San Joaquin Valley makes certain findings after the effective date of specified amendments to its general plan and zoning ordinance, the Planning and Zoning Law prohibits a city or county from entering into a development agreement for property located in a flood hazard zone; approving a discretionary permit, ministerial permit, or other discretionary entitlement for a project that is located within a flood hazard zone, as specified; or approving a tentative map, or a parcel map for which a tentative map was not required, for a subdivision that is located within a flood hazard zone. Those findings include, among others, that the local flood management agency has made adequate progress on the construction of a flood protection system that will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas. Existing law further requires urban and urbanizing areas protected by any levee that is part of the facilities of the State Plan of Flood Control to achieve the urban level of flood protection by 2025, with specified exceptions to the deadline for the Mossdale Tract and West Sacramento.
This bill would remove the specified exceptions to the deadline for the Mossdale Tract and West Sacramento, and instead provide that the deadline to achieve an urban level of protection does not apply, so long as a flood management agency has an active federal project in the planning, design, construction, or project closeout phase, a completed federal feasibility study awaiting congressional authorization, or an authorized federal project awaiting the receipt of federal appropriations to advance design, construction, or project closeout activities. By changing the deadline for the Mossdale Tract and West Sacramento to achieve the urban level of flood protection, this bill would impose a state-mandated local program.
This bill would make legislative findings and declarations as to the necessity of a special statute for the Sacramento-San Joaquin Valley.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that, if the Commission on State Mandates determines that the bill contains costs mandated by the state, reimbursement for those costs shall be made pursuant to the statutory provisions noted above.
(a)For purposes of Sections 65865.5, 65962, and 66474.5, the Mossdale Tract shall achieve the urban level of flood protection by 2040.
(b)For purposes of this section, Mossdale Tract means an area of land identified as Reclamation District No. 17 on page 144 of Bulletin No. 37 (1930) of the Department of Water Resources, along with such contiguous urban and urbanizing areas to the east of the tract as would be subject to flooding from the San Joaquin River at an urban level of flood protection.
(c)Notwithstanding Section 8307 of the Water Code, the San Joaquin Area Flood Control Agency may be required to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties unreasonably approving, as defined in Section 8307 of the Water Code, any new development in the Mossdale Tract between the years 2025 and 2040.
SEC. 2.Section 65962.2 of the Government Code is amended to read:65962.2.(a)For purposes of Sections 65865.5, 65962, and 66474.5, the City of West Sacramento shall achieve the urban level of flood protection by 2040.
(b)For purposes of this section, City of West Sacramento means the incorporated area in the County of Yolo as identified in Resolution No. 86-112 of the County of Yolo Board of Supervisors at Yolo County Official Records Book 1801, pages 384 to 403, inclusive, and Book 1801, pages 368 to 382, inclusive.
(c)Notwithstanding Section 8307 of the Water Code, the West Sacramento Area Flood Control Agency may be required to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties unreasonably approving, as defined in Section 8307 of the Water Code, any new development in the City of West Sacramento between January 1, 2025, and December 31, 2040.
SEC. 3.Section 65962.3 is added to the Government Code, to read:65962.3.(a)Notwithstanding Sections 9795 and 10231.5, on or before December 31, 2028, and every five years thereafter until December 31, 2038, the West Sacramento Area Flood Control Agency and the San Joaquin Area Flood Control Agency shall provide a report to the Senate Natural Resources and Water Committee, the Assembly Water, Parks, and Wildlife Committee, the Senate Budget Subcommittee No. 2, and the Assembly Budget Subcommittee No. 4 describing plans and actions taken to improve flood protection in the preceding five years in the City of West Sacramento and the Mossdale Tract pursuant to Sections 65962.1 and 65962.2, respectively.
(b)In order to minimize duplication, the report described in subdivision (a) may be composed of materials developed to meet other reporting requirements.
(c)This section shall remain in effect only until January 1, 2039, and as of that date is repealed.
SEC. 4.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the unique land use planning considerations relative to flood hazard zones in the Sacramento-San Joaquin Valley.
SEC. 5.This act is an urgency statute necessary for the immediate preservation of the public peace, health, or safety within the meaning of Article IV of the California Constitution and shall go into immediate effect. The facts constituting the necessity are:
In order to expedite completion of 200-year flood control projects protecting life and property in San Joaquin County and West Sacramento, and to assure a continuing funding stream, and in order to expedite and increase the likelihood of significant federal financial participation in development of the projects, it is necessary that the bill take effect immediately.
(a)For purposes of Sections 65865.5, 65962, and 66474.5, the Mossdale Tract shall achieve the urban level of flood protection by 2040.
(b)For purposes of this section, Mossdale Tract means an area of land identified as Reclamation District No. 17 on page 144 of Bulletin No. 37 (1930) of the Department of Water Resources, along with such contiguous urban and urbanizing areas to the east of the tract as would be subject to flooding from the San Joaquin River at an urban level of flood protection.
(c)Notwithstanding Section 8307 of the Water Code, the San Joaquin Area Flood Control Agency may be required to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties unreasonably approving, as defined in Section 8307 of the Water Code, any new development in the Mossdale Tract between the years 2025 and 2040.
SEC. 2.Section 65962.2 of the Government Code is amended to read:65962.2.(a)For purposes of Sections 65865.5, 65962, and 66474.5, the City of West Sacramento shall achieve the urban level of flood protection by 2040.
(b)For purposes of this section, City of West Sacramento means the incorporated area in the County of Yolo as identified in Resolution No. 86-112 of the County of Yolo Board of Supervisors at Yolo County Official Records Book 1801, pages 384 to 403, inclusive, and Book 1801, pages 368 to 382, inclusive.
(c)Notwithstanding Section 8307 of the Water Code, the West Sacramento Area Flood Control Agency may be required to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties unreasonably approving, as defined in Section 8307 of the Water Code, any new development in the City of West Sacramento between January 1, 2025, and December 31, 2040.
SEC. 3.Section 65962.3 is added to the Government Code, to read:65962.3.(a)Notwithstanding Sections 9795 and 10231.5, on or before December 31, 2028, and every five years thereafter until December 31, 2038, the West Sacramento Area Flood Control Agency and the San Joaquin Area Flood Control Agency shall provide a report to the Senate Natural Resources and Water Committee, the Assembly Water, Parks, and Wildlife Committee, the Senate Budget Subcommittee No. 2, and the Assembly Budget Subcommittee No. 4 describing plans and actions taken to improve flood protection in the preceding five years in the City of West Sacramento and the Mossdale Tract pursuant to Sections 65962.1 and 65962.2, respectively.
(b)In order to minimize duplication, the report described in subdivision (a) may be composed of materials developed to meet other reporting requirements.
(c)This section shall remain in effect only until January 1, 2039, and as of that date is repealed.
SEC. 4.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the unique land use planning considerations relative to flood hazard zones in the Sacramento-San Joaquin Valley.
SEC. 5.This act is an urgency statute necessary for the immediate preservation of the public peace, health, or safety within the meaning of Article IV of the California Constitution and shall go into immediate effect. The facts constituting the necessity are:
In order to expedite completion of 200-year flood control projects protecting life and property in San Joaquin County and West Sacramento, and to assure a continuing funding stream, and in order to expedite and increase the likelihood of significant federal financial participation in development of the projects, it is necessary that the bill take effect immediately.
(a)For purposes of Sections 65865.5, 65962, and 66474.5, the Mossdale Tract shall achieve the urban level of flood protection by 2040.
(b)For purposes of this section, Mossdale Tract means an area of land identified as Reclamation District No. 17 on page 144 of Bulletin No. 37 (1930) of the Department of Water Resources, along with such contiguous urban and urbanizing areas to the east of the tract as would be subject to flooding from the San Joaquin River at an urban level of flood protection.
(c)Notwithstanding Section 8307 of the Water Code, the San Joaquin Area Flood Control Agency may be required to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties unreasonably approving, as defined in Section 8307 of the Water Code, any new development in the Mossdale Tract between the years 2025 and 2040.
SEC. 2.Section 65962.2 of the Government Code is amended to read:65962.2.(a)For purposes of Sections 65865.5, 65962, and 66474.5, the City of West Sacramento shall achieve the urban level of flood protection by 2040.
(b)For purposes of this section, City of West Sacramento means the incorporated area in the County of Yolo as identified in Resolution No. 86-112 of the County of Yolo Board of Supervisors at Yolo County Official Records Book 1801, pages 384 to 403, inclusive, and Book 1801, pages 368 to 382, inclusive.
(c)Notwithstanding Section 8307 of the Water Code, the West Sacramento Area Flood Control Agency may be required to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties unreasonably approving, as defined in Section 8307 of the Water Code, any new development in the City of West Sacramento between January 1, 2025, and December 31, 2040.
SEC. 3.Section 65962.3 is added to the Government Code, to read:65962.3.(a)Notwithstanding Sections 9795 and 10231.5, on or before December 31, 2028, and every five years thereafter until December 31, 2038, the West Sacramento Area Flood Control Agency and the San Joaquin Area Flood Control Agency shall provide a report to the Senate Natural Resources and Water Committee, the Assembly Water, Parks, and Wildlife Committee, the Senate Budget Subcommittee No. 2, and the Assembly Budget Subcommittee No. 4 describing plans and actions taken to improve flood protection in the preceding five years in the City of West Sacramento and the Mossdale Tract pursuant to Sections 65962.1 and 65962.2, respectively.
(b)In order to minimize duplication, the report described in subdivision (a) may be composed of materials developed to meet other reporting requirements.
(c)This section shall remain in effect only until January 1, 2039, and as of that date is repealed.
SEC. 3.SEC. 4.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the unique land use planning considerations relative to flood hazard zones in the Sacramento-San Joaquin Valley.
SEC. 4.SEC. 5.This act is an urgency statute necessary for the immediate preservation of the public peace, health, or safety within the meaning of Article IV of the California Constitution and shall go into immediate effect. The facts constituting the necessity are:
In order to expedite completion of 200-year flood control projects protecting life and property in San Joaquin County and West Sacramento, and to assure a continuing funding stream, and in order to expedite and increase the likelihood of significant federal financial participation in development of the projects, it is necessary that the bill take effect immediately.
(a)For purposes of Sections 65865.5, 65962, and 66474.5, the Mossdale Tract shall achieve the urban level of flood protection by 2030. 2040.
(b)For purposes of this section, Mossdale Tract means an area of land identified as Reclamation District No. 17 on page 144 of Bulletin No. 37 (1930) of the Department of Water Resources, along with such contiguous urban and urbanizing areas to the east of the tract as would be subject to flooding from the San Joaquin River at an urban level of flood protection.
(c)Notwithstanding Section 8307 of the Water Code, the San Joaquin Area Flood Control Agency may be required to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties unreasonably approving, as defined in Section 8307 of the Water Code, any new development in the Mossdale Tract between the years 2025 and 2030. 2040.
SEC. 2.Section 65962.2 of the Government Code is amended to read:65962.2.(a)For purposes of Sections 65865.5, 65962, and 66474.5, the City of West Sacramento shall achieve the urban level of flood protection by 2030. 2040.
(b)For purposes of this section, City of West Sacramento means the incorporated area in the County of Yolo as identified in Resolution No. 86-112 of the County of Yolo Board of Supervisors at Yolo County Official Records Book 1801, pages 384 to 403, inclusive, and Book 1801, pages 368 to 382, inclusive.
(c)Notwithstanding Section 8307 of the Water Code, the West Sacramento Area Flood Control Agency may be required to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties unreasonably approving, as defined in Section 8307 of the Water Code, any new development in the City of West Sacramento between January 1, 2025, and December 31, 2030. 2040.
SEC. 2.SEC. 3.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the unique land use planning considerations relative to flood hazard zones in the Mossdale Tract. Sacramento-San Joaquin Valley.
SEC. 4.This act is an urgency statute necessary for the immediate preservation of the public peace, health, or safety within the meaning of Article IV of the California Constitution and shall go into immediate effect. The facts constituting the necessity are:
In order to expedite completion of 200-year flood control projects protecting life and property in San Joaquin County and West Sacramento, and to assure a continuing funding stream, and in order to expedite and increase the likelihood of significant federal financial participation in development of the projects, it is necessary that the bill take effect immediately.
(a)For purposes of Sections 65865.5, 65962, and 66474.5, the Mossdale Tract shall achieve the urban level of flood protection by 2028. 2030.
(b)For purposes of this section, Mossdale Tract means an area of land identified as Reclamation District No. 17 on page 144 of Bulletin No. 37 (1930) of the Department of Water Resources, along with such contiguous urban and urbanizing areas to the east of the tract as would be subject to flooding from the San Joaquin River at an urban level of flood protection.
(c)Notwithstanding Section 8307 of the Water Code, the San Joaquin Area Flood Control Agency may be required to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties unreasonably approving, as defined in Section 8307 of the Water Code, any new development in the Mossdale Tract between the years 2025 and 2028. 2030.
SEC. 2.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the unique land use planning considerations relative to flood hazard zones in the Mossdale Tract.
SECTION 1.Section 65865.5 of the Government Code is amended to read:65865.5.(a)Notwithstanding any other law, after the amendments required by Sections 65302.9 and 65860.1 have become effective, the legislative body of a city or county within the Sacramento-San Joaquin Valley shall not enter into a development agreement for property that is located within a flood hazard zone unless the city or county finds, based on substantial evidence in the record, one of the following:(1)The facilities of the State Plan of Flood Control or other flood management facilities protect the property to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.(2)The city or county has imposed conditions on the development agreement that will protect the property to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.(3)The local flood management agency has made adequate progress on the construction of a flood protection system that will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas for property located within a flood hazard zone, intended to be protected by the system. Except as provided in Section 65962.1, for urban and urbanizing areas protected by project levees, the urban level of flood protection shall be achieved by 2025.(4)The property in an undetermined risk area has met the urban level of flood protection based on substantial evidence in the record.(b)The effective date of amendments referred to in this section shall be the date upon which the statutes of limitation specified in subdivision (c) of Section 65009 have run or, if the amendments and any associated environmental documents are challenged in court, the validity of the amendments and any associated environmental documents has been upheld in a final decision.(c)This section does not change or diminish existing requirements of local flood plain management laws, ordinances, resolutions, or regulations necessary to local agency participation in the national flood insurance program.SEC. 2.Section 65962 of the Government Code is amended to read:65962.(a)Notwithstanding any other law, after the amendments required by Sections 65302.9 and 65860.1 have become effective, each city and county within the Sacramento-San Joaquin Valley shall not approve a discretionary permit or other discretionary entitlement that would result in the construction of a new building or construction that would result in an increase in allowed occupancy for an existing building, or a ministerial permit that would result in the construction of a new residence, for a project that is located within a flood hazard zone unless the city or county finds, based on substantial evidence in the record, one of the following:(1)The facilities of the State Plan of Flood Control or other flood management facilities protect the project to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.(2)The city or county has imposed conditions on the permit or discretionary entitlement that will protect the project to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.(3)The local flood management agency has made adequate progress on the construction of a flood protection system which will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas for property located within a flood hazard zone, intended to be protected by the system. Except as provided in Section 65962.1, for urban and urbanizing areas protected by project levees, the urban level of flood protection shall be achieved by 2025.(4)The property in an undetermined risk area has met the urban level of flood protection based on substantial evidence in the record.(b)The effective date of amendments referred to in this section shall be the date upon which the statutes of limitation specified in subdivision (c) of Section 65009 have run or, if the amendments and any associated environmental documents are challenged in court, the validity of the amendments and any associated environmental documents has been upheld in a final decision.(c)This section does not change or diminish existing requirements of local flood plain management laws, ordinances, resolutions, or regulations necessary to local agency participation in the national flood insurance program.SEC. 3.Section 65962.1 of the Government Code is amended to read:65962.1.(a)For purposes of Sections 65865.5, 65962, and 66474.5, the deadline to achieve an urban level of protection, or to make adequate progress on the construction of a flood system providing an urban level of protection, shall not apply, so long as the flood management agency has one of the following:(1)An active federal study, provided that the study has received federal appropriations in the current or previous two federal fiscal years.(2)A completed federal study delivered to Congress and awaiting congressional authorization for less than four years from the date of transmittal.(3)An authorized federal project receiving or awaiting the receipt of federal appropriations to advance design, construction, or project closeout activities, provided that the project has received federal appropriations in the current or one of the previous three federal fiscal years.(b)If the conditions described in subdivision (a) are not met, the deadline shall be the deadline as set forth in Sections 65865.5, 65926, and 66474.5. (c)Notwithstanding Section 8307 of the Water Code, the San Joaquin Area Flood Control Agency or the West Sacramento Area Flood Control Agency may be required to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties that unreasonably approve, as defined in paragraph (3) of subdivision (c) of Section 8307 of the Water Code, any new development in those areas between January 1, 2025, and when urban level flood protection is achieved.(d)This section shall only apply to the City of West Sacramento and Mossdale Tract.(e)For purposes of this section, the following terms have the following meanings:(1)City of West Sacramento means the incorporated area in the County of Yolo as defined by Resolution No. 86-112 of the County of Yolo Board of Supervisors at the Yolo County Official Records Book 1801, pages 384 to 403, inclusive, and Book 1801, pages 368 to 382, inclusive.(2)Mossdale Tract means the area of land identified as Reclamation District No. 17, on page 144 of Bulletin No. 37 (1930) of the Department of Water Resources, and contiguous urban and urbanizing areas east of the tract that would be subject to flooding from the San Joaquin River at the urban level of flood protection.SEC. 4.Section 65962.2 of the Government Code is repealed.SEC. 5.Section 66474.5 of the Government Code is amended to read:66474.5.(a)Notwithstanding any other law, after the amendments required by Sections 65302.9 and 65860.1 have become effective, the legislative body of each city and county within the Sacramento-San Joaquin Valley shall deny approval of a tentative map, or a parcel map for which a tentative map was not required, for a subdivision that is located within a flood hazard zone unless the city or county finds, based on substantial evidence in the record, one of the following:(1)The facilities of the State Plan of Flood Control or other flood management facilities protect the subdivision to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.(2)The city or county has imposed conditions on the subdivision that will protect the project to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.(3)The local flood management agency has made adequate progress on the construction of a flood protection system which will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas for property located within a flood hazard zone, intended to be protected by the system. Except as provided in Section 65962.1, for urban and urbanizing areas protected by project levees, the urban level of flood protection shall be achieved by 2025.(4)The property in an undetermined risk area has met the urban level of flood protection based on substantial evidence in the record.(b)The effective date of amendments referred to in this section shall be the date upon which the statutes of limitation specified in subdivision (c) of Section 65009 have run or, if the amendments and any associated environmental documents are challenged in court, the validity of the amendments and any associated environmental documents has been upheld in a final decision.(c)This section does not change or diminish existing requirements of local flood plain management laws, ordinances, resolutions, or regulations necessary to local agency participation in the national flood insurance program.SEC. 6.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the unique land use planning considerations relative to flood hazard zones in the Sacramento-San Joaquin Valley.SEC. 7.If the Commission on State Mandates determines that this act contains costs mandated by the state, reimbursement to local agencies and school districts for those costs shall be made pursuant to Part 7 (commencing with Section 17500) of Division 4 of Title 2 of the Government Code.(a)Notwithstanding any other law, after the amendments required by Sections 65302.9 and 65860.1 have become effective, the legislative body of a city or county within the Sacramento-San Joaquin Valley shall not enter into a development agreement for property that is located within a flood hazard zone unless the city or county finds, based on substantial evidence in the record, one of the following:
(1)The facilities of the State Plan of Flood Control or other flood management facilities protect the property to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(2)The city or county has imposed conditions on the development agreement that will protect the property to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(3)The local flood management agency has made adequate progress on the construction of a flood protection system that will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas for property located within a flood hazard zone, intended to be protected by the system. Except as provided in Section 65962.1, for urban and urbanizing areas protected by project levees, the urban level of flood protection shall be achieved by 2025.
(4)The property in an undetermined risk area has met the urban level of flood protection based on substantial evidence in the record.
(b)The effective date of amendments referred to in this section shall be the date upon which the statutes of limitation specified in subdivision (c) of Section 65009 have run or, if the amendments and any associated environmental documents are challenged in court, the validity of the amendments and any associated environmental documents has been upheld in a final decision.
(c)This section does not change or diminish existing requirements of local flood plain management laws, ordinances, resolutions, or regulations necessary to local agency participation in the national flood insurance program.
SEC. 2.Section 65962 of the Government Code is amended to read:65962.(a)Notwithstanding any other law, after the amendments required by Sections 65302.9 and 65860.1 have become effective, each city and county within the Sacramento-San Joaquin Valley shall not approve a discretionary permit or other discretionary entitlement that would result in the construction of a new building or construction that would result in an increase in allowed occupancy for an existing building, or a ministerial permit that would result in the construction of a new residence, for a project that is located within a flood hazard zone unless the city or county finds, based on substantial evidence in the record, one of the following:
(1)The facilities of the State Plan of Flood Control or other flood management facilities protect the project to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(2)The city or county has imposed conditions on the permit or discretionary entitlement that will protect the project to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(3)The local flood management agency has made adequate progress on the construction of a flood protection system which will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas for property located within a flood hazard zone, intended to be protected by the system. Except as provided in Section 65962.1, for urban and urbanizing areas protected by project levees, the urban level of flood protection shall be achieved by 2025.
(4)The property in an undetermined risk area has met the urban level of flood protection based on substantial evidence in the record.
(b)The effective date of amendments referred to in this section shall be the date upon which the statutes of limitation specified in subdivision (c) of Section 65009 have run or, if the amendments and any associated environmental documents are challenged in court, the validity of the amendments and any associated environmental documents has been upheld in a final decision.
(c)This section does not change or diminish existing requirements of local flood plain management laws, ordinances, resolutions, or regulations necessary to local agency participation in the national flood insurance program.
SEC. 3.Section 65962.1 of the Government Code is amended to read:65962.1.(a)For purposes of Sections 65865.5, 65962, and 66474.5, the deadline to achieve an urban level of protection protection, or to make adequate progress on the construction of a flood system providing an urban level of protection, shall not apply, so long as the flood management agency has one of the following:
(1)An active federal project in the planning, design, construction, or project closeout phase. study, provided that the study has received federal appropriations in the current or previous two federal fiscal years.
(2)A completed federal feasibility study awaiting congressional authorization. study delivered to Congress and awaiting congressional authorization for less than four years from the date of transmittal.
(3)An authorized federal project receiving or awaiting the receipt of federal appropriations to advance design, construction, or project closeout activities. activities, provided that the project has received federal appropriations in the current or one of the previous three federal fiscal years.
(b)If the conditions described in subdivision (a) are not met, the deadline shall be the deadline as set forth in Sections 65865.5, 65926, and 66474.5.
(b)(c)Notwithstanding Section 8307 of the Water Code, the San Joaquin Area Flood Control Agency or the West Sacramento Area Flood Control Agency may be required to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties that unreasonably approve, as defined in paragraph (3) of subdivision (c) of Section 8307 of the Water Code, any new development in those areas between January 1, 2025, and when urban level flood protection is achieved.
(c)(d)This section shall only apply to the City of West Sacramento and Mossdale Tract.
(d)(e)For purposes of this section, the following terms have the following meanings:
(1)City of West Sacramento means the incorporated area in the County of Yolo as defined by Resolution No. 86-112 of the County of Yolo Board of Supervisors at the Yolo County Official Records Book 1801, pages 384 to 403, inclusive, and Book 1801, pages 368 to 382, inclusive.
(2)Mossdale Tract means the area of land identified as Reclamation District No. 17, on page 144 of Bulletin No. 37 (1930) of the Department of Water Resources, and contiguous urban and urbanizing areas east of the tract that would be subject to flooding from the San Joaquin River at the urban level of flood protection.
SEC. 4.Section 65962.2 of the Government Code is repealed.SEC. 5.Section 66474.5 of the Government Code is amended to read:66474.5.(a)Notwithstanding any other law, after the amendments required by Sections 65302.9 and 65860.1 have become effective, the legislative body of each city and county within the Sacramento-San Joaquin Valley shall deny approval of a tentative map, or a parcel map for which a tentative map was not required, for a subdivision that is located within a flood hazard zone unless the city or county finds, based on substantial evidence in the record, one of the following:
(1)The facilities of the State Plan of Flood Control or other flood management facilities protect the subdivision to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(2)The city or county has imposed conditions on the subdivision that will protect the project to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(3)The local flood management agency has made adequate progress on the construction of a flood protection system which will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas for property located within a flood hazard zone, intended to be protected by the system. Except as provided in Section 65962.1, for urban and urbanizing areas protected by project levees, the urban level of flood protection shall be achieved by 2025.
(4)The property in an undetermined risk area has met the urban level of flood protection based on substantial evidence in the record.
(b)The effective date of amendments referred to in this section shall be the date upon which the statutes of limitation specified in subdivision (c) of Section 65009 have run or, if the amendments and any associated environmental documents are challenged in court, the validity of the amendments and any associated environmental documents has been upheld in a final decision.
(c)This section does not change or diminish existing requirements of local flood plain management laws, ordinances, resolutions, or regulations necessary to local agency participation in the national flood insurance program.
SEC. 6.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the unique land use planning considerations relative to flood hazard zones in the Sacramento-San Joaquin Valley.
SEC. 7.If the Commission on State Mandates determines that this act contains costs mandated by the state, reimbursement to local agencies and school districts for those costs shall be made pursuant to Part 7 (commencing with Section 17500) of Division 4 of Title 2 of the Government Code.
(a)Notwithstanding any other law, after the amendments required by Sections 65302.9 and 65860.1 have become effective, the legislative body of a city or county within the Sacramento-San Joaquin Valley shall not enter into a development agreement for property that is located within a flood hazard zone unless the city or county finds, based on substantial evidence in the record, one of the following:
(1)The facilities of the State Plan of Flood Control or other flood management facilities protect the property to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(2)The city or county has imposed conditions on the development agreement that will protect the property to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(3)The local flood management agency has made adequate progress on the construction of a flood protection system that will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas for property located within a flood hazard zone, intended to be protected by the system. Except as provided in Section 65962.1, for urban and urbanizing areas protected by project levees, the urban level of flood protection shall be achieved by 2025.
(4)The property in an undetermined risk area has met the urban level of flood protection based on substantial evidence in the record.
(b)The effective date of amendments referred to in this section shall be the date upon which the statutes of limitation specified in subdivision (c) of Section 65009 have run or, if the amendments and any associated environmental documents are challenged in court, the validity of the amendments and any associated environmental documents has been upheld in a final decision.
(c)This section does not change or diminish existing requirements of local flood plain management laws, ordinances, resolutions, or regulations necessary to local agency participation in the national flood insurance program.
SEC. 2.Section 65962 of the Government Code is amended to read:65962.(a)Notwithstanding any other law, after the amendments required by Sections 65302.9 and 65860.1 have become effective, each city and county within the Sacramento-San Joaquin Valley shall not approve a discretionary permit or other discretionary entitlement that would result in the construction of a new building or construction that would result in an increase in allowed occupancy for an existing building, or a ministerial permit that would result in the construction of a new residence, for a project that is located within a flood hazard zone unless the city or county finds, based on substantial evidence in the record, one of the following:
(1)The facilities of the State Plan of Flood Control or other flood management facilities protect the project to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(2)The city or county has imposed conditions on the permit or discretionary entitlement that will protect the project to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(3)The local flood management agency has made adequate progress on the construction of a flood protection system which will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas for property located within a flood hazard zone, intended to be protected by the system. Except as provided in Section 65962.1, for urban and urbanizing areas protected by project levees, the urban level of flood protection shall be achieved by 2025.
(4)The property in an undetermined risk area has met the urban level of flood protection based on substantial evidence in the record.
(b)The effective date of amendments referred to in this section shall be the date upon which the statutes of limitation specified in subdivision (c) of Section 65009 have run or, if the amendments and any associated environmental documents are challenged in court, the validity of the amendments and any associated environmental documents has been upheld in a final decision.
(c)This section does not change or diminish existing requirements of local flood plain management laws, ordinances, resolutions, or regulations necessary to local agency participation in the national flood insurance program.
SEC. 3.Section 65962.1 of the Government Code is amended to read:65962.1.(a)For purposes of Sections 65865.5, 65962, and 66474.5, the deadline to achieve an urban level of protection shall not apply, so long as the flood management agency has one of the following:
(1)An active federal project in the planning, design, construction, or project closeout phase.
(2)A completed federal feasibility study awaiting congressional authorization.
(3)An authorized federal project awaiting the receipt of federal appropriations to advance design, construction, or project closeout activities.
(b)Notwithstanding Section 8307 of the Water Code, the San Joaquin Area Flood Control Agency or the West Sacramento Area Flood Control Agency may be required to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties that unreasonably approve, as defined in paragraph (3) of subdivision (c) of Section 8307 of the Water Code, any new development in those areas between January 1, 2025, and when urban level flood protection is achieved.
(c)This section shall only apply to the City of West Sacramento and Mossdale Tract.
(d)For purposes of this section, the following terms have the following meanings:
(1)City of West Sacramento means the incorporated area in the County of Yolo as defined by Resolution No. 86-112 of the County of Yolo Board of Supervisors at the Yolo County Official Records Book 1801, pages 384 to 403, inclusive, and Book 1801, pages 368 to 382, inclusive.
(2)Mossdale Tract means the area of land identified as Reclamation District No. 17, on page 144 of Bulletin No. 37 (1930) of the Department of Water Resources, ad and contiguous urban and urbanizing areas east of the tract that would be subject to flooding from the San Joaquin River at the urban level of flood protection.
SEC. 4.Section 65962.2 of the Government Code is repealed.SEC. 5.Section 66474.5 of the Government Code is amended to read:66474.5.(a)Notwithstanding any other law, after the amendments required by Sections 65302.9 and 65860.1 have become effective, the legislative body of each city and county within the Sacramento-San Joaquin Valley shall deny approval of a tentative map, or a parcel map for which a tentative map was not required, for a subdivision that is located within a flood hazard zone unless the city or county finds, based on substantial evidence in the record, one of the following:
(1)The facilities of the State Plan of Flood Control or other flood management facilities protect the subdivision to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(2)The city or county has imposed conditions on the subdivision that will protect the project to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(3)The local flood management agency has made adequate progress on the construction of a flood protection system which will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas for property located within a flood hazard zone, intended to be protected by the system. Except as provided in Section 65962.1, for urban and urbanizing areas protected by project levees, the urban level of flood protection shall be achieved by 2025.
(4)The property in an undetermined risk area has met the urban level of flood protection based on substantial evidence in the record.
(b)The effective date of amendments referred to in this section shall be the date upon which the statutes of limitation specified in subdivision (c) of Section 65009 have run or, if the amendments and any associated environmental documents are challenged in court, the validity of the amendments and any associated environmental documents has been upheld in a final decision.
(c)This section does not change or diminish existing requirements of local flood plain management laws, ordinances, resolutions, or regulations necessary to local agency participation in the national flood insurance program.
SEC. 6.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the because of the unique land use planning considerations relative to flood hazard zones in the Sacramento-San Joaquin Valley.
SEC. 7.If the Commission on State Mandates determines that this act contains costs mandated by the state, reimbursement to local agencies and school districts for those costs shall be made pursuant to Part 7 (commencing with Section 17500) of Division 4 of Title 2 of the Government Code.
(a)Notwithstanding any other law, after the amendments required by Sections 65302.9 and 65860.1 have become effective, the legislative body of a city or county within the Sacramento-San Joaquin Valley shall not enter into a development agreement for property that is located within a flood hazard zone unless the city or county finds, based on substantial evidence in the record, one of the following:
(1)The facilities of the State Plan of Flood Control or other flood management facilities protect the property to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(2)The city or county has imposed conditions on the development agreement that will protect the property to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(3)The local flood management agency has made adequate progress on the construction of a flood protection system that will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas for property located within a flood hazard zone, intended to be protected by the system. Except as provided in Section 65962.1, for urban and urbanizing areas protected by project levees, the urban level of flood protection shall be achieved by 2025.
(4)The property in an undetermined risk area has met the urban level of flood protection based on substantial evidence in the record.
(b)The effective date of amendments referred to in this section shall be the date upon which the statutes of limitation specified in subdivision (c) of Section 65009 have run or, if the amendments and any associated environmental documents are challenged in court, the validity of the amendments and any associated environmental documents has been upheld in a final decision.
(c)This section does not change or diminish existing requirements of local flood plain management laws, ordinances, resolutions, or regulations necessary to local agency participation in the national flood insurance program.
SEC. 2.Section 65962 of the Government Code is amended to read:65962.(a)Notwithstanding any other law, after the amendments required by Sections 65302.9 and 65860.1 have become effective, each city and county within the Sacramento-San Joaquin Valley shall not approve a discretionary permit or other discretionary entitlement that would result in the construction of a new building or construction that would result in an increase in allowed occupancy for an existing building, or a ministerial permit that would result in the construction of a new residence, for a project that is located within a flood hazard zone unless the city or county finds, based on substantial evidence in the record, one of the following:
(1)The facilities of the State Plan of Flood Control or other flood management facilities protect the project to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(2)The city or county has imposed conditions on the permit or discretionary entitlement that will protect the project to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(3)The local flood management agency has made adequate progress on the construction of a flood protection system which will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas for property located within a flood hazard zone, intended to be protected by the system. Except as provided in Section 65962.1, for urban and urbanizing areas protected by project levees, the urban level of flood protection shall be achieved by 2025.
(4)The property in an undetermined risk area has met the urban level of flood protection based on substantial evidence in the record.
(b)The effective date of amendments referred to in this section shall be the date upon which the statutes of limitation specified in subdivision (c) of Section 65009 have run or, if the amendments and any associated environmental documents are challenged in court, the validity of the amendments and any associated environmental documents has been upheld in a final decision.
(c)This section does not change or diminish existing requirements of local flood plain management laws, ordinances, resolutions, or regulations necessary to local agency participation in the national flood insurance program.
SEC. 3.Section 65962.1 of the Government Code is amended to read:65962.1.(a)For purposes of Sections 65865.5, 65962, and 66474.5, the deadline to achieve an urban level of protection shall not apply, so long as the flood management agency has one of the following:
(a)(1)An active federal project in the planning, design, construction, or project closeout phase.
(b)(2)A completed federal feasibility study awaiting congressional authorization.
(c)(3)An authorized federal project awaiting the receipt of federal appropriations to advance design, construction, or project closeout activities.
(b)Notwithstanding Section 8307 of the Water Code, the San Joaquin Area Flood Control Agency or the West Sacramento Area Flood Control Agency may be required to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties that unreasonably approve, as defined in paragraph (3) of subdivision (c) of Section 8307 of the Water Code, any new development in those areas between January 1, 2025, and when urban level flood protection is achieved.
(c)This section shall only apply to the City of West Sacramento and Mossdale Tract.
(d)For purposes of this section, the following terms have the following meanings:
(1)City of West Sacramento means the incorporated area in the County of Yolo as defined by Resolution No. 86-112 of the County of Yolo Board of Supervisors at the Yolo County Official Records Book 1801, pages 384 to 403, inclusive, and Book 1801, pages 368 to 382, inclusive.
(2)Mossdale Tract means the area of land identified as Reclamation District No. 17, on page 144 of Bulletin No. 37 (1930) of the Department of Water Resources, ad contiguous urban and urbanizing areas east of the tract that would be subject to flooding from the San Joaquin River at the urban level of flood protection.
SEC. 4.Section 65962.2 of the Government Code is repealed.SEC. 5.Section 66474.5 of the Government Code is amended to read:66474.5.(a)Notwithstanding any other law, after the amendments required by Sections 65302.9 and 65860.1 have become effective, the legislative body of each city and county within the Sacramento-San Joaquin Valley shall deny approval of a tentative map, or a parcel map for which a tentative map was not required, for a subdivision that is located within a flood hazard zone unless the city or county finds, based on substantial evidence in the record, one of the following:
(1)The facilities of the State Plan of Flood Control or other flood management facilities protect the subdivision to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(2)The city or county has imposed conditions on the subdivision that will protect the project to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(3)The local flood management agency has made adequate progress on the construction of a flood protection system which will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas for property located within a flood hazard zone, intended to be protected by the system. Except as provided in Section 65962.1, for urban and urbanizing areas protected by project levees, the urban level of flood protection shall be achieved by 2025.
(4)The property in an undetermined risk area has met the urban level of flood protection based on substantial evidence in the record.
(b)The effective date of amendments referred to in this section shall be the date upon which the statutes of limitation specified in subdivision (c) of Section 65009 have run or, if the amendments and any associated environmental documents are challenged in court, the validity of the amendments and any associated environmental documents has been upheld in a final decision.
(c)This section does not change or diminish existing requirements of local flood plain management laws, ordinances, resolutions, or regulations necessary to local agency participation in the national flood insurance program.
SEC. 6.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the because of the unique land use planning considerations relative to flood hazard zones in the Sacramento-San Joaquin Valley.
SEC. 7.If the Commission on State Mandates determines that this act contains costs mandated by the state, reimbursement to local agencies and school districts for those costs shall be made pursuant to Part 7 (commencing with Section 17500) of Division 4 of Title 2 of the Government Code.
(a)Notwithstanding any other law, after the amendments required by Sections 65302.9 and 65860.1 have become effective, the legislative body of a city or county within the Sacramento-San Joaquin Valley shall not enter into a development agreement for property that is located within a flood hazard zone unless the city or county finds, based on substantial evidence in the record, one of the following:
(1)The facilities of the State Plan of Flood Control or other flood management facilities protect the property to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(2)The city or county has imposed conditions on the development agreement that will protect the property to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(3)The local flood management agency has made adequate progress on the construction of a flood protection system that will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas for property located within a flood hazard zone, intended to be protected by the system. Except as provided in Sections 65962.1 and 65962.2, Section 65962.1, for urban and urbanizing areas protected by project levees, the urban level of flood protection shall be achieved by 2025.
(4)The property in an undetermined risk area has met the urban level of flood protection based on substantial evidence in the record.
(b)The effective date of amendments referred to in this section shall be the date upon which the statutes of limitation specified in subdivision (c) of Section 65009 have run or, if the amendments and any associated environmental documents are challenged in court, the validity of the amendments and any associated environmental documents has been upheld in a final decision.
(c)This section does not change or diminish existing requirements of local flood plain management laws, ordinances, resolutions, or regulations necessary to local agency participation in the national flood insurance program.
SEC. 2.Section 65962 of the Government Code is amended to read:65962.(a)Notwithstanding any other law, after the amendments required by Sections 65302.9 and 65860.1 have become effective, each city and county within the Sacramento-San Joaquin Valley shall not approve a discretionary permit or other discretionary entitlement that would result in the construction of a new building or construction that would result in an increase in allowed occupancy for an existing building, or a ministerial permit that would result in the construction of a new residence, for a project that is located within a flood hazard zone unless the city or county finds, based on substantial evidence in the record, one of the following:
(1)The facilities of the State Plan of Flood Control or other flood management facilities protect the project to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(2)The city or county has imposed conditions on the permit or discretionary entitlement that will protect the project to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(3)The local flood management agency has made adequate progress on the construction of a flood protection system which will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas for property located within a flood hazard zone, intended to be protected by the system. Except as provided in Sections 65962.1 and 65962.2, Section 65962.1, for urban and urbanizing areas protected by project levees, the urban level of flood protection shall be achieved by 2025.
(4)The property in an undetermined risk area has met the urban level of flood protection based on substantial evidence in the record.
(b)The effective date of amendments referred to in this section shall be the date upon which the statutes of limitation specified in subdivision (c) of Section 65009 have run or, if the amendments and any associated environmental documents are challenged in court, the validity of the amendments and any associated environmental documents has been upheld in a final decision.
(c)This section does not change or diminish existing requirements of local flood plain management laws, ordinances, resolutions, or regulations necessary to local agency participation in the national flood insurance program.
SEC. 3.Section 65962.1 of the Government Code is amended to read:65962.1.(a)For purposes of Sections 65865.5, 65962, and 66474.5, the Mossdale Tract shall achieve the urban level of flood protection by 2028.
(b)For purposes of this section, Mossdale Tract means an area of land identified as Reclamation District No. 17 on page 144 of Bulletin No. 37 (1930) of the Department of Water Resources, along with such contiguous urban and urbanizing areas to the east of the tract as would be subject to flooding from the San Joaquin River at an urban level of flood protection.(c)Notwithstanding Section 8307 of the Water Code, the San Joaquin Area Flood Control Agency may be required to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties unreasonably approving, as defined in Section 8307 of the Water Code, any new development in the Mossdale Tract between the years 2025 and 2028.the deadline to achieve an urban level of protection shall not apply, so long as the flood management agency has one of the following:
(a)An active federal project in the planning, design, construction, or project closeout phase.
(b)A completed federal feasibility study awaiting congressional authorization.
(c)An authorized federal project awaiting the receipt of federal appropriations to advance design, construction, or project closeout activities.
SEC. 4.Section 65962.2 of the Government Code is repealed.65962.2.(a)For purposes of Sections 65865.5, 65962, and 66474.5, the City of West Sacramento shall achieve the urban level of flood protection by 2030.(b)For purposes of this section, City of West Sacramento means the incorporated area in the County of Yolo as identified in Resolution No. 86-112 of the County of Yolo Board of Supervisors at Yolo County Official Records Book 1801, pages 384 to 403, inclusive, and Book 1801, pages 368 to 382, inclusive.(c)Notwithstanding Section 8307 of the Water Code, the West Sacramento Area Flood Control Agency may be required to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the states exposure to liability for property damage has been increased by cities or counties unreasonably approving, as defined in Section 8307 of the Water Code, any new development in the City of West Sacramento between January 1, 2025, and December 31, 2030.SEC. 5.Section 66474.5 of the Government Code is amended to read:66474.5.(a)Notwithstanding any other law, after the amendments required by Sections 65302.9 and 65860.1 have become effective, the legislative body of each city and county within the Sacramento-San Joaquin Valley shall deny approval of a tentative map, or a parcel map for which a tentative map was not required, for a subdivision that is located within a flood hazard zone unless the city or county finds, based on substantial evidence in the record, one of the following:
(1)The facilities of the State Plan of Flood Control or other flood management facilities protect the subdivision to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(2)The city or county has imposed conditions on the subdivision that will protect the project to the urban level of flood protection in urban and urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas.
(3)The local flood management agency has made adequate progress on the construction of a flood protection system which will result in flood protection equal to or greater than the urban level of flood protection in urban or urbanizing areas or the national Federal Emergency Management Agency standard of flood protection in nonurbanized areas for property located within a flood hazard zone, intended to be protected by the system. Except as provided in Sections 65962.1 and 65962.2, Section 65962.1, for urban and urbanizing areas protected by project levees, the urban level of flood protection shall be achieved by 2025.
(4)The property in an undetermined risk area has met the urban level of flood protection based on substantial evidence in the record.
(b)The effective date of amendments referred to in this section shall be the date upon which the statutes of limitation specified in subdivision (c) of Section 65009 have run or, if the amendments and any associated environmental documents are challenged in court, the validity of the amendments and any associated environmental documents has been upheld in a final decision.
(c)This section does not change or diminish existing requirements of local flood plain management laws, ordinances, resolutions, or regulations necessary to local agency participation in the national flood insurance program.
SEC. 6.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the because of the unique land use planning considerations relative to flood hazard zones in the Sacramento-San Joaquin Valley.
SEC. 7.If the Commission on State Mandates determines that this act contains costs mandated by the state, reimbursement to local agencies and school districts for those costs shall be made pursuant to Part 7 (commencing with Section 17500) of Division 4 of Title 2 of the Government Code.
|
Date
|
Status
|
|---|---|
| Apr 30, 2024 | Chaptered by Secretary of State. Chapter 10, Statutes of 2024. |
| Apr 30, 2024 | Approved by the Governor. |
| Apr 23, 2024 | Enrolled and presented to the Governor at 2 p.m. |
| Apr 18, 2024 | Assembly amendments concurred in. (Ayes 39. Noes 0. Page 3673.) Ordered to engrossing and enrolling. |
| Apr 18, 2024 | Urgency clause adopted. |
| Apr 17, 2024 | Ordered to special consent calendar. |
| Apr 11, 2024 | In Senate. Concurrence in Assembly amendments pending. |
| Apr 11, 2024 | Read third time. Urgency clause adopted. Passed. (Ayes 73. Noes 0. Page 4745.) Ordered to the Senate. |
| Apr 4, 2024 | Read third time and amended. |
| Apr 4, 2024 | Ordered to third reading. |
| Mar 14, 2024 | Ordered to third reading. |
| Mar 14, 2024 | Read third time and amended. |
| Jan 30, 2024 | Ordered to third reading. |
| Jan 30, 2024 | From inactive file. |
| Jan 29, 2024 | Notice of intention to remove from inactive file given by Assembly Member Aguiar-Curry. |
| Sep 12, 2023 | Ordered to inactive file on request of Assembly Member Hart. |
| Sep 5, 2023 | Read second time. Ordered to third reading. |
| Sep 1, 2023 | Read second time and amended. Ordered to second reading. |
| Sep 1, 2023 | From committee: Do pass as amended. (Ayes 11. Noes 0.) (September 1). |
| Aug 23, 2023 | August 23 set for first hearing. Placed on suspense file. |
| Jun 20, 2023 | From committee: Do pass and re-refer to Com. on APPR. (Ayes 15. Noes 0.) (June 20). Re-referred to Com. on APPR. |
| May 26, 2023 | Referred to Com. on W., P., & W. |
| May 23, 2023 | In Assembly. Read first time. Held at Desk. |
| May 22, 2023 | Read third time. Passed. (Ayes 40. Noes 0. Page 1212.) Ordered to the Assembly. |
| May 9, 2023 | Read second time. Ordered to third reading. |
| May 8, 2023 | From committee: Be ordered to second reading pursuant to Senate Rule 28.8. |
| May 2, 2023 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on APPR. |
| May 1, 2023 | Set for hearing May 8. |
| Apr 27, 2023 | May 1 hearing postponed by committee. |
| Apr 25, 2023 | Set for hearing May 1. |
| Apr 20, 2023 | Read second time and amended. Re-referred to Com. on APPR. |
| Apr 19, 2023 | From committee: Do pass as amended and re-refer to Com. on APPR. (Ayes 8. Noes 0. Page 795.) (April 19). |
| Apr 10, 2023 | Set for hearing April 19. |
| Mar 29, 2023 | Read second time and amended. Re-referred to Com. on GOV. & F. |
| Mar 28, 2023 | From committee: Do pass as amended and re-refer to Com. on GOV. & F. (Ayes 9. Noes 0. Page 547.) (March 28). |
| Mar 7, 2023 | Set for hearing March 28. |
| Feb 22, 2023 | Referred to Coms. on N.R. & W. and GOV. & F. |
| Feb 16, 2023 | From printer. May be acted upon on or after March 18. |
| Feb 15, 2023 | Introduced. Read first time. To Com. on RLS. for assignment. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Apr 18, 2024 | Special Consent SB586 Eggman et al. Urgency Clause | Senate Floor |
Passed |
|
| Apr 11, 2024 | SB 586 Eggman Third Reading Urgency By Aguiar-Curry | Assembly Floor |
Passed |
|
| Sep 1, 2023 | Do pass as amended. | Assembly Standing Committee on Appropriations |
Passed |
|
| Jun 20, 2023 | Do pass and be re-referred to the Committee on [Appropriations] | Assembly Standing Committee on Water, Parks, and Wildlife |
Passed |
|
| May 22, 2023 | Senate 3rd Reading SB586 Eggman | Senate Floor |
Passed |
|
| Apr 19, 2023 | Do pass as amended, but first amend, and re-refer to the Committee on [Appropriations] | Senate Standing Committee on Governance and Finance |
Passed |
|
| Mar 28, 2023 | Do pass as amended, but first amend, and re-refer to the Committee on [Governance and Finance] | Senate Standing Committee on Natural Resources and Water |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| Business Council San Joaquin County | ** Support | |
| California Building Industry Association | ** Support | |
| California Central Valley Flood Control Association | ** Support | |
| City Of Lathrop | ** Support | |
| City of Manteca | ** Support | |
| City of Stockton | ** Support | |
| city of west sacramento | ** Support | |
| County of San Joaquin | ** Support | |
| San Joaquin Area Flood Control Agency | ** Support | |
| West Sacramento Area Flood Control Agency | ** Support |
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 586 |
UNFINISHED BUSINESS
Bill No: SB 586
Author: Eggman (D), et al.
Amended: 4/4/24
Vote: 27 - Urgency
SENATE NATURAL RES. & WATER COMMITTEE: 9-0, 3/28/23
AYES: Min, Allen, Becker, Eggman, Grove, Hurtado, Laird, Limón, Padilla
NO VOTE RECORDED: Seyarto, Dahle
SENATE GOVERNANCE & FIN. COMMITTEE: 8-0, 4/19/23
AYES: Caballero, Seyarto, Blakespear, Dahle, Durazo, Glazer, Skinner, Wiener
SENATE APPROPRIATIONS COMMITTEE: Senate Rule 28.8
SENATE FLOOR: 40-0, 5/22/23
AYES: Allen, Alvarado-Gil, Archuleta, Ashby, Atkins, Becker, Blakespear, Bradford, Caballero, Cortese, Dahle, Dodd, Durazo, Eggman, Glazer, Gonzalez, Grove, Hurtado, Jones, Laird, Limón, McGuire, Menjivar, Min, Newman, Nguyen, Niello, Ochoa Bogh, Padilla, Portantino, Roth, Rubio, Seyarto, Skinner, Smallwood-Cuevas, Stern, Umberg, Wahab, Wiener, Wilk
ASSEMBLY FLOOR: 73-0, 4/11/24 - See last page for vote
SUBJECT: Flood management: Sacramento-San Joaquin Valley
SOURCE: San Joaquin Area Flood Control Agency
West Sacramento Area Flood Control Agency
DIGEST:
This bill extends the deadline to meet the urban level of flood protection to 2040 for the Mossdale Tract and the City of West Sacramento, as provided.
Assembly Amendments
extend the deadline for the Mossdale Tract and the City of West Sacramento to meet the urban level of flood protection to 2040 and add a legislative reporting requirement, instead of eliminating the deadlines and replacing them with a requirement that flood management agencies for these areas to demonstrate ongoing engagement with the federal government to complete necessary projects.
ANALYSIS:
Existing law:
- Defines the urban level of flood protection to be “the level of protection that is necessary to withstand flooding that has a 1-in-200 chance of occurring in any given year …” This is sometimes referred to as a 200 year level of protection.
- Prohibits a city or county within the Sacramento-San Joaquin Valley from entering into a development agreement for property within a flood hazard zone unless the city or county finds one of the following:
- The facilities of the property are protected to the appropriate level of flood protection in urban and nonurbanized areas.
- The city or county has imposed conditions on the development agreement that will protect the property to the appropriate level of flood protection in urban and nonurbanized areas.
- The local flood management agency has made “adequate progress” on the construction of a flood protection system that will result in the appropriate level of flood protection in urban and nonurbanized areas. For urban and urbanizing areas protected by project levees, the urban level of flood protection shall be achieved by 2025.
- Extends the date for the Mossdale Tract to reach an urban level of flood protection to 2028. The Mossdale Tract includes Reclamation District 17 (16,110 acres), portions the Cities of Stockton, Lathrop, Manteca, and unincorporated San Joaquin County, and the principal flood risk is posed by the San Joaquin River.
- Extends the date for the City of West Sacramento to achieve an urban level of flood protection to 2030.
This bill extends the deadline to meet the urban level of flood protection to 2040 for the Mossdale Tract and the City of West Sacramento, as provided.
Specifically, this bill:
- Extends the date for the Mossdale Tract and the City of West Sacramento to reach the urban level of flood protection to 2040.
- Requires a legislative report to the two budget sub-committees and policy committees with jurisdiction every five years starting on December 31, 2028 on progress in the Mossdale Tract and the City of West Sacramento towards meeting flood protection requirements.
- Declares that a special statute is necessary to Mossdale Tract and City of West Sacramento, as provided.
- Declares that this bill must take effect immediately as an urgency statute for specified reasons.
Background
In 2007, the Legislature passed and then-Governor Schwarzenegger signed a comprehensive package of flood bills – SB 5 (Machado, Chapter 364, Statutes of 2007), SB 17 (Florez, Chapter 365, Statutes of 2007), AB 5 (Wolk, Chapter 366, Statutes of 2007), AB 70 (Jones, Chapter 367, Statutes of 2007), AB 156 (Laird, Chapter 368, Statutes of 2007), and AB 162 (Wolk, Chapter 369, Statutes of 2007).
The over-arching concept underpinning these flood bills was to:
- Stop putting people in harm’s way.
- Determine where the greatest risk of harm is.
- Develop and implement plans to reduce that risk.
Among other things, SB 5 defined the urban level of flood protection to be “the level of protection that is necessary to withstand flooding that has a 1-in-200 chance of occurring in any given year …” (Government Code (GOV) §65007). This is sometimes referred to as a 200-year level of protection. SB 5 also set the national Federal Emergency Management Act flood protection standard of 100 year protection as the objective for nonurbanized areas.
Further, SB 5 prohibited a city or county within the Sacramento-San Joaquin Valley from entering into a development agreement for property within a flood hazard zone unless the city or county finds one of the following: (GOV §65865.5)
- The facilities of the property are protected to the appropriate level of flood protection in urban and nonurbanized areas.
- The city or county has imposed conditions on the development agreement that will protect the property to the appropriate level of flood protection in urban and nonurbanized areas.
- The local flood management agency has made “adequate progress” on the construction of a flood protection system that will result in the appropriate level of flood protection in urban and nonurbanized areas. For urban and urbanizing areas protected by project levees[1], the urban level of flood protection shall be achieved by 2025.
- The property is in an undetermined risk area and has met the urban level of flood protection based on substantial evidence[2].
SB 5 further defined “adequate progress” to mean all of the following (GOV §65007):
- The total project scope, schedule, and cost of the completed flood protection system have been developed to meet the appropriate standard of protection.
- Revenues that are sufficient to fund each year of the project schedule have been identified and, in any given year and consistent with that schedule, at least 90 percent of the revenues scheduled to be received by that year have been appropriated and are currently being expended. (There is an exception where state funding was not appropriated consistent with a funding agreement between a state agency and a local flood management agency.)
- Critical features of the flood protection system are under construction, and each critical feature is progressing as indicated by the actual expenditure of the construction budget funds.
- The city or county has not been responsible for a significant delay in the completion of the system.
- The local flood management agency provides the Department of Water Resources (DWR) and the Central Valley Flood Protection Board (CVFPB) with required specified information sufficient to determine substantial completion of the required flood protection.
SB 5 defined the Sacramento-San Joaquin Valley as the area subject to flooding by the Sacramento or San Joaquin Rivers or their tributaries, not including Tulare Lake basin or the Kings River (GOV §65007).
Similarly, cities and counties within the Sacramento-San Joaquin Valley are prohibited from approving a discretionary permit or other discretionary entitlement that would result in the construction of a new building or construction that would result in an increase in allowed occupancy of an existing building, or a ministerial permit that would result in the construction of a new residence for projects located within a flood hazard zone and are required to deny a tentative map or parcel map for a subdivision located within a flood hazard zone unless certain findings are made, including that the local flood management agency has made adequate progress on the construction of a flood protection system (GOV §§65962, 66474.5).
The 2007 flood bill package were in response to the Paterno decision (Paterno v. State of California (2003) 114 Cal.App.4th 308). In Paterno, the court determined that the State of California can be liable for failure of levees if the state fails to have a “reasonable plan” for operating and maintaining the levees in the Sacramento and San Joaquin Valleys. The court reasoned that the levees were a public improvement, thus placing liability on the state for any damage that resulted from the improvement, including potential levee failure.
SB 5’s prohibition against new development or increased occupancy in flood hazard zones without the urban level of flood protection, unless the development met one of four categories, appears to be the Legislature’s response to the court’s “responsible plan” ruling.
The 2007 flood package also included provisions to ensure that local agencies shared in the liability should development decisions made at the local level result in future flood damages. While the state, generally, assumes liability for flood damages, Water Code §8307 authorizes the state to impose liability on local agencies in the event a local agency unreasonably approved a new development project in a Central Valley floodplain “without appropriately considering significant risks of flooding made known to the approving agency as of the time of approval and without taking reasonable and feasible action to mitigate the potential property damage to the new development resulting from a flood.” However, if the development falls into one of the four categories that would permit development, the locals are not required to contribute and the state is solely responsible.
As the 2025 urban level of flood protection deadline loomed, legislation provided extensions to specific areas within the Sacramento-San Joaquin Valley. These include the Mossdale Tract (AB 838 (Eggman, Chapter 208, Statutes of 2020)) and the City of West Sacramento (SB 901 (Pan, Chapter 708, Statutes of 2022)) that must meet relevant flood protection standards by 2028, and 2030, respectively. These bills included language that provided that the relevant local flood control agency might be required to contribute its “fair and reasonable” share of any property damage caused by a flood to the extent the state’s exposure to liability had been increased due to the approval of new development (see GOV §65962.1c, §65962.2c).
Comments
Allows new development to continue. This bill allows the City of West Sacramento and local jurisdictions within the Mossdale Tract to continue approving new development through 2040 so long as adequate progress to achieve the urban level of flood protection continues.
Meeting the urban flood protection level is a combined local/state/federal effort. There is substantial ongoing federal effort to improve flood protection in both the City of West Sacramento and the Mossdale Tract. A federal study is underway for the Mossdale Tract and is expected to be completed by 2026. Federal authorization and appropriations would follow at a future date. In addition, the West Sacramento flood control project is, according to the US Army Corps of Engineers, due to be completed in 2035. It is a fair point that decisions at the federal level are outside of state and local control and have a significant impact on the ability of these areas to meet the existing deadlines for the urban level of flood control.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: No
According to the Assembly Appropriations Committee, this bill could result in higher liability exposure for the state, possibly in the tens of millions to hundreds of millions of dollars, or more (General Fund). By providing Mossdale Tract with an additional 12 years and the City of West Sacramento an additional 10 years to achieve urban level of flood protection, this bill could extend and potentially increase the state’s liability for flood damages in these areas
SUPPORT: (Verified 4/11/24)
San Joaquin Area Flood Control Agency (co-source)
West Sacramento Area Flood Control Agency (co-source)
California Building Industry Association
California Central Valley Flood Control Association
City of Lathrop
City of Manteca
City of Stockton
City of West Sacramento
County of San Joaquin
OPPOSITION: (Verified 4/11/24)
None received
ARGUMENTS IN SUPPORT: According to the author, “…[B]ecause of the sluggishness of the USACE [United States Army Corps of Engineers] and the federal process, many of the projects in areas like Lathrop, Manteca, Sacramento, Stockton, and West Sacramento are in danger of missing the 2025 deadline and failing to achieve the 200-year standard of flood protection required under SB 5 altogether. LFMAs [Local flood management agencies] struggle to demonstrate adequate progress while engaged in this collaborative approach through no fault of their own because of the pace of USACE.”
According to the California Central Valley Flood Control Association (CCVFCA), “CCVFCA supports the construction, repair, rehabilitation, and replacement of flood control facilities to provide and maintain a 200-year urban level of protection for people, buildings, and the environment in urban and urbanizing areas. Local flood control agencies confront many challenges in meeting statutory deadlines, including obtaining Federal and State project approvals and permits and securing financing for projects. It is the latter, for example, that often relies on the improvement of real property like new housing projects to raise money for local agency cost sharing of project costs. The imposition of a building moratorium during the course of project development would halt progress toward completing a project.”
ASSEMBLY FLOOR: 73-0, 4/11/24
AYES: Addis, Aguiar-Curry, Alanis, Alvarez, Arambula, Bains, Bennett, Berman, Boerner, Bonta, Bryan, Calderon, Juan Carrillo, Wendy Carrillo, Cervantes, Chen, Connolly, Davies, Dixon, Essayli, Flora, Mike Fong, Vince Fong, Friedman, Gabriel, Gallagher, Garcia, Gipson, Haney, Hart, Holden, Hoover, Irwin, Jackson, Jones-Sawyer, Kalra, Lackey, Lee, Low, Lowenthal, Maienschein, McCarty, McKinnor, Muratsuchi, Stephanie Nguyen, Ortega, Pacheco, Papan, Jim Patterson, Joe Patterson, Pellerin, Petrie-Norris, Quirk-Silva, Ramos, Reyes, Luz Rivas, Rodriguez, Blanca Rubio, Sanchez, Santiago, Schiavo, Soria, Ta, Ting, Valencia, Wallis, Ward, Weber, Wicks, Wilson, Wood, Zbur, Robert Rivas
NO VOTE RECORDED: Bauer-Kahan, Megan Dahle, Grayson, Mathis, Rendon, Villapudua, Waldron
Prepared by: Katharine Moore / N.R. & W. / (916) 651-4116
4/12/24 13:50:56
**** END ****
SENATE THIRD READING
STR Bill Id:SB 586
Author:(Eggman)
As Amended Ver:March 14, 2024
2/3 vote. Urgency
SUMMARY
Extends the date for Mossdale Tract to reach the urban level of flood protection from 2028 to 2040 and for the City of West Sacramento from 2030 to 2040.
Major Provisions
- Extends the date for Mossdale Tract (in San Joaquin County) to reach the urban level of flood protection from 2028 to 2040.
- Extends the date for the City of West Sacramento to reach the urban level of flood protection from 2030 to 2040.
- Declares that this is an urgency bill necessary to foster completion of flood control projects to protect communities in San Joaquin County and the City of West Sacramento.
- Requires the West Sacramento Area Flood Control Agency and San Joaquin Area Flood Control Agency to report to the Legislature on progress made in achieving the urban level of flood protection beginning December 31, 2028, and every five years thereafter.
COMMENTS
The level of flood risk in California’s Central Valley is among the highest in the nation. According to the CV Flood Plan 2022 Update, 1.23 million people and more than $223 billion in structures and property are at risk from flooding. With historic storms like the Great Flood of 1862 and even more recent events like the series of atmospheric river-fed storms from winter 2023, human-made flood management efforts struggle to compete against the natural state of the Central Valley. Analysis done as part of ARkStorm 2.0 indicates that climate change has already increased the frequency and magnitude of severe storms that result in “megaflood” events (Huang and Swain, 2022). Perhaps more concerning relative to this bill, the researchers that produced ARkStorm 2.0 conclude “that extremely severe winter storm sequences once thought to be exceptionally rare events are likely to become much more common under essentially all plausible future climate trajectories—suggesting the 20th century hazard mapping, emergency response plans, and even physical infrastructure design standards may already be out of date in a warmer 21st century climate” (Huang and Swain, 2022).
Urban level of flood protection. Cities and counties in the Sacramento-San Joaquin Valley that are protected by the State Plan of Flood Control are prohibited from approving new development or increasing the housing density within existing developments unless there is flood protection that meets the "urban level of flood protection," the level of protection necessary to withstand a flood event that has a 1-in-200 chance of occurring in any given year (sometimes referred to as a “200-year flood”). Areas that do not have urban levels of flood protection must achieve, or make adequate progress towards achieving, the urban level of flood protection by 2025. These requirements were enacted by the Legislature in 2007 as part of a comprehensive flood package resulting from increased awareness of the flood threat to Central Valley communities in the wake of Hurricane Katrina.
Recently, the Legislature passed AB 838 (Eggman) in 2020 and SB 901 (Pan) in 2022 to extend the deadlines to meet the urban level of flood protection for Mossdale Tract (in San Joaquin County) and the City of West Sacramento because the flood management agencies for these areas had experienced unforeseen delays in making progress toward achieving the urban level of flood protection. AB 838 extended the deadline for Mossdale Tract by three years to 2028, and SB 901 extended the deadline for the City of West Sacramento by five years to 2030. Under AB 838 and SB 901, the flood management agencies for Mossdale Tract and the City of West Sacramento are liable for their "fair and reasonable share of any property damage caused by a flood" that occurs between 2025 and the new deadlines. This bill extends the deadlines for Mossdale Tract by an additional 12 years (from 2028 to 2030) and the City of West Sacramento by an additional 10 years (from 2030 to 2040).
Mossdale Tract Area Urban Flood Risk Reduction Project. Mossdale Tract consists of 22,400 acres and includes portions of Reclamation District 17 (RD 17), Stockton, Lathrop, Manteca, and unincorporated San Joaquin County. According to the San Joaquin Area Flood Control Agency (SJAFCA), the existing levees for the Mossdale Tract area do not provide 200-year flood protection as required by state law. To address this deficiency, SJAFCA is working with RD 17 to improve Mossdale Tract’s levees through an ongoing Levee Seepage Repair Project, levee improvements, and an extension of exiting levees in Manteca. SJAFCA has completed a feasibility study for this project and is now performing a design and environmental impact report for the project. Additionally, SJAFCA and DWR are partnering with U.S. Army Corps of Engineers to obtain federal construction funding. In 2022, a federal study was initiated and must be completed and presented to Congress for authorization and appropriations. The study is expected to be completed in 2026.
West Sacramento Project for flood risk reduction. This project encompasses upgrades to over 50 miles of levees that protect the City of West Sacramento and its more than 50,000 residents from flooding that has a 1-in-200 chance of occurring in a given year. The estimated cost for the West Sacramento Project is $1.2 billion. The original federal authorization was in the Water Resource Development Act of 1992 (PL 102-580). The U.S. Army Corps of Engineers reassessed this project in the General Reevaluation Report (GRR) that was submitted to Congress in January 2016; subsequently, the Water Resources Infrastructure Improvement for the Nation Act of 2016 updated the Project’s federal authorization to reflect changes recommended by the GRR.
According to the Author
The author maintains that local flood management agencies benefit from working with the U.S. Army Corps of Engineers and federal government on flood protection projects because the federal government will cover up to 65% of a flood protection project’s cost. However, the author notes that this federal process can be sluggish and flood projects in areas like Lathrop, Manteca, Sacramento, Stockton, and West Sacramento are in danger of missing the deadline to achieve urban level of flood protection, as a result: local flood management agencies “struggle to demonstrate adequate progress while engaged in this collaborative approach through no fault of their own because of the pace of the [U.S. Army Corps of Engineers].”
Arguments in Support
The California Central Valley Flood Control Association (CCVFCA) supports this bill arguing that local flood control agencies face many challenges in meeting statutory deadlines to complete flood protection projects due to delays in obtaining federal authorization, project funding, and permit approvals. To finance flood protection projects, local agencies often rely “on the improvement of real property like new housing projects to raise money for local agency cost sharing of project costs.” Given this, CCVFCA asserts that “the imposition of a building moratorium during the course of project development would halt progress toward completing a project.”
Arguments in Opposition
None on file.
FISCAL COMMENTS
According to the Assembly Appropriations Committee, this bill could result in higher liability exposure for the state, possibly in the tens of millions to hundreds of millions of dollars, or more (General Fund). By providing Mossdale Tract with an additional 12 years and the City of West Sacramento and additional 10 years to achieve urban level of flood protection, this bill could extend and potentially increase the state’s liability for flood damages in these areas.
VOTES
SENATE FLOOR: 40-0-0
YES: Allen, Alvarado-Gil, Archuleta, Ashby, Atkins, Becker, Blakespear, Bradford, Caballero, Cortese, Dahle, Dodd, Durazo, Eggman, Glazer, Gonzalez, Grove, Hurtado, Jones, Laird, Limón, McGuire, Menjivar, Min, Newman, Nguyen, Niello, Ochoa Bogh, Padilla, Portantino, Roth, Rubio, Seyarto, Skinner, Smallwood-Cuevas, Stern, Umberg, Wahab, Wiener, Wilk
ASM WATER, PARKS, AND WILDLIFE: 15-0-0
YES: Bauer-Kahan, Mathis, Alanis, Bennett, Megan Dahle, Davies, Friedman, Hart, Kalra, Pellerin, Blanca Rubio, Schiavo, Villapudua, Ward, Weber
ASM APPROPRIATIONS: 11-0-5
YES: Holden, Bryan, Calderon, Wendy Carrillo, Mike Fong, Hart, Lowenthal, Papan, Pellerin, Weber, Wilson
ABS, ABST OR NV: Megan Dahle, Dixon, Mathis, Sanchez, Soria
UPDATED
VERSION: March 14, 2024
CONSULTANT: Pablo Garza / W., P., & W. / (916) 319-2096 FN: 0002681
SENATE THIRD READING
STR Bill Id:SB 586
Author:(Eggman)
As Amended Ver:March 14, 2024
Majority vote. Urgency
SUMMARY
Extends the date for Mossdale Tract to reach the urban level of flood protection from 2028 to 2040 and for the City of Sacramento from 2030 to 2040.
Major Provisions
- Extends the date for Mossdale Tract (in San Joaquin County) to reach the urban level of flood protection from 2028 to 2040.
- Extends the date for the City of West Sacramento to reach the urban level of flood protection from 2030 to 2040.
- Declares that this is an urgency bill necessary to foster completion of flood control projects to protect communities in San Joaquin County and the City of West Sacaramento.
COMMENTS
The level of flood risk in California's Central Valley is among the highest in the nation. According to the CV Flood Plan 2022 Update, 1.23 million people and more than $223 billion in structures and property are at risk from flooding. With historic storms like the Great Flood of 1862 and even more recent events like the series of atmospheric river-fed storms from winter 2023, human-made flood management efforts struggle to compete against the natural state of the Central Valley. Analysis done as part of ARkStorm 2.0 indicates that climate change has already increased the frequency and magnitude of severe storms that result in "megaflood" events (Huang and Swain, 2022). Perhaps more concerning relative to this bill, the researchers that produced ARkStorm 2.0 conclude "that extremely severe winter storm sequences once thought to be exceptionally rare events are likely to become much more common under essentially all plausible future climate trajectories—suggesting the 20th century hazard mapping, emergency response plans, and even physical infrastructure design standards may already be out of date in a warmer 21st century climate" (Huang and Swain, 2022).
Urban level of flood protection. Cities and counties in the Sacramento-San Joaquin Valley that are protected by the State Plan of Flood Control are prohibited from approving new development or increasing the housing density within existing developments unless there is flood protection that meets the "urban level of flood protection," the level of protection necessary to withstand a flood event that has a 1-in-200 chance of occurring in any given year (sometimes referred to as a "200-year flood"). Areas that do not have urban level of flood protection must achieve, or make adequate progress towards achieving, the urban level of flood protection by 2025. These requirements were enacted by the Legislature in 2007 as part of a comprehensive flood package resulting from increased awareness of the flood threat to Central Valley communities in the wake of Hurricane Katrina.
Recently, the Legislature passed AB 838 (Eggman) Chapter 208, Statutes of 2020 and SB 901 (Pan) Chapter 708, Statues of 2022 to extend the deadlines to meet urban level of flood protection for Mossdale Tract (in San Joaquin County) and the City of West Sacramento because the flood management agencies for these areas had experienced unforeseen delays in making progress toward achieving the urban level of flood protection. AB 838 extended the deadline for Mossdale Tract by three years to 2028 and SB 901 extended the deadline for the City of West Sacramento by five years to 2030. Under AB 838 and SB 901, the flood management agencies for Mossdale Tract and the City of West Sacramento are liable for their "fair and reasonable share of any property damage caused by a flood" that occurs between 2025 and the new deadlines. This bill extends the deadlines for Mossdale Tract by an additional two years from 2028 to 2030.Mossdale Tract Area Urban Flood Risk Reduction Project. Mossdale Tract consists of 22,400 acres and includes portions of Reclamation District 17 (RD 17), Stockton, Lathrop, Manteca, and unincorporated San Joaquin County. According to the San Joaquin Area Flood Control Agency (SJAFCA), the existing levees for the Mossdale Tract area do not provide 200-year flood protection as required by state law. To address this deficiency, SJAFCA is working with RD 17 to improve Mossdale Tract's levees through an ongoing Levee Seepage Repair Project, levee improvements, and an extension of exiting levee in Manteca. SJAFCA has completed a feasibility study for this project and is now performing a design and environmental impact report for the project. Additionally, SJAFCA and DWR are partnering with U.S. Army Corps of Engineers to obtain federal construction funding. In 2022, a federal study was initiated and must be completed and presented to Congress for authorization and appropriations. The study is expected to be completed in 2026.
West Sacramento Project for flood risk reduction. This project encompasses upgrades to over 50 miles of levees that protect the City of West Sacramento and its more than 50,000 residents from flooding that has a 1-in-200 chance of occurring in a given year. The estimated cost for the West Sacramento Project is $1.2 billion. The original federal authorization was in the Water Resource Development Act of 1992 (PL 102-580). The U.S. Army Corps of Engineers reassessed this project in the General Reevaluation Report (GRR) that was submitted to Congress in January 2016; subsequently, the Water Resources Infrastructure Improvement for the Nation Act of 2016 updated the Project's federal authorization to reflect changes recommended by the GRR.
According to the Author
The author maintains that local flood management agencies benefit from working with the U.S. Army Corps of Engineers and federal government on flood protection projects because the federal government will cover up to 65% of a flood protection project's cost. However, the author notes that this federal process can be sluggish and flood projects in areas like Lathrop, Manteca, Sacramento, Stockton, and West Sacramento are in danger of missing the deadline to achieve urban level of flood protection; as a result: local flood management agencies "struggle to demonstrate adequate progress while engaged in this collaborative approach through no fault of their own because of the pace of the [U.S. Army Corps of Engineers]."
Arguments in Support
The California Central Valley Flood Control Association (CCVFCA) supports this bill arguing that local flood control agencies face many challenges in meeting statutory deadlines to complete flood protection projects due to delays in obtaining federal authorization, project funding, and permit approvals. To finance flood protection projects, local agencies often rely "on the improvement of real property like new housing projects to raise money for local agency cost sharing of project costs." Given this, CCVFCA asserts that "the imposition of a building moratorium during the course of project development would halt progress toward completing a project."
Arguments in Opposition
None on file.
FISCAL COMMENTS
According to the Assembly Appropriations Committee, this bill could result in higher liability exposure for the state, possibly in the tens of millions to hundreds of millions of dollars, or more (General Fund). By providing Mossdale Tract with an additional 12 years and the City of West Sacramento an additional 10 years to achieve urban level of flood protection, this bill could extend and potentially increase the state's liability for flood damages in these areas.
VOTES
SENATE FLOOR: 40-0-0
YES: Allen, Alvarado-Gil, Archuleta, Ashby, Atkins, Becker, Blakespear, Bradford, Caballero, Cortese, Dahle, Dodd, Durazo, Eggman, Glazer, Gonzalez, Grove, Hurtado, Jones, Laird, Limón, McGuire, Menjivar, Min, Newman, Nguyen, Niello, Ochoa Bogh, Padilla, Portantino, Roth, Rubio, Seyarto, Skinner, Smallwood-Cuevas, Stern, Umberg, Wahab, Wiener, Wilk
ASM WATER, PARKS, AND WILDLIFE: 15-0-0
YES: Bauer-Kahan, Mathis, Alanis, Bennett, Megan Dahle, Davies, Friedman, Hart, Kalra, Pellerin, Blanca Rubio, Schiavo, Villapudua, Ward, Weber
ASM APPROPRIATIONS: 11-0-5
YES: Holden, Bryan, Calderon, Wendy Carrillo, Mike Fong, Hart, Lowenthal, Papan, Pellerin, Weber, Wilson
ABS, ABST OR NV: Megan Dahle, Dixon, Mathis, Sanchez, Soria
UPDATED
VERSION: March 14, 2024
CONSULTANT: Pablo Garza / W., P., & W. / (916) 319-2096 FN: 0002659
SENATE THIRD READING
STR Bill Id:SB 586
Author:(Eggman)
As Amended Ver:September 1, 2023
Majority vote
SUMMARY
Extends the date for the Mossdale Tract to reach the urban level of flood protection from 2028 to 2030.
Major Provisions
- Extends the date for the Mossdale Tract to reach the urban level of flood protection from 2028 to 2030.
- Declares that a special statute is necessary due to the unique land use planning considerations relative to Mossdale Tract.
COMMENTS
The level of flood risk in California's Central Valley is among the highest in the nation. According to the CV Flood Plan 2022 Update, 1.23 million people and more than $223 billion in structures and property are at risk from flooding. With historic storms like the Great Flood of 1862 and even more recent events like the series of atmospheric river-fed storms from winter 2023, human-made flood management efforts struggle to compete against the natural state of the Central Valley. Analysis done as part of ARkStorm 2.0 indicates that climate change has already increased the frequency and magnitude of severe storms that result in "megaflood" events (Huang and Swain, 2022). Perhaps more concerning relative to this bill, the researchers that produced ARkStorm 2.0 conclude "that extremely severe winter storm sequences once thought to be exceptionally rare events are likely to become much more common under essentially all plausible future climate trajectories—suggesting the 20th century hazard mapping, emergency response plans, and even physical infrastructure design standards may already be out of date in a warmer 21st century climate" (Huang and Swain, 2022).
Urban level of flood protection. Cities and counties in the Sacramento-San Joaquin Valley that are protected by the State Plan of Flood Control are prohibited from approving new development or increasing the housing density within existing developments unless there is flood protection that meets the "urban level of flood protection," the level of protection necessary to withstand a flood event that has a 1-in-200 chance of occurring in any given year (sometimes referred to as a "200-year flood"). Areas that do not have urban level of flood protection must achieve, or make adequate progress towards achieving, the urban level of flood protection by 2025. These requirements were enacted by the Legislature in 2007 as part of a comprehensive flood package resulting from increased awareness of the flood threat to Central Valley communities in the wake of Hurricane Katrina.
Recently, the Legislature passed AB 838 (Eggman), Chapter 208, Statutes of 2020, and SB 901 (Pan), Chapter 708, Statutes of 2022, to extend the deadlines to meet urban level of flood protection for Mossdale Tract (in San Joaquin County) and the City of West Sacramento because the flood management agencies for these areas had experienced unforeseen delays in making progress toward achieving the urban level of flood protection. AB 838 extended the deadline for Mossdale Tract by three years to 2028 and SB 901 extended the deadline for the City of West Sacramento by five years to 2030. Under AB 838 and SB 901, the flood management agencies for Mossdale Tract and the City of West Sacramento are liable for their "fair and reasonable share of any property damage caused by a flood" that occurs between 2025 and the new deadlines. This bill extends the deadlines for Mossdale Tract an additional two years from 2028 to 2030.
Mossdale Tract Area Urban Flood Risk Reduction Project. Mossdale Tract consists of 22,400 acres and includes portions of Reclamation District 17 (RD 17), Stockton, Lathrop, Manteca, and unincorporated San Joaquin County. According to the San Joaquin Area Flood Control Agency (SJAFCA), the existing levees for the Mossdale Tract area do not provide 200-year flood protection as required by state law. To address this deficiency, SJAFCA is working with RD 17 to improve Mossdale Tract's levees through an ongoing Levee Seepage Repair Project, levee improvements, and an extension of exiting levee in Manteca. SJAFCA has completed a feasibility study for this project and is now performing a design and environmental impact report for the project. Additionally, SJAFCA and DWR are partnering with U.S. Army Corps of Engineers to obtain federal construction funding. In 2022, a federal study was initiated and must be completed and presented to Congress for authorization and appropriations. The study is expected to be completed in 2026.
According to the Author
The author maintains that local flood management agencies benefit from working with the U.S. Army Corps of Engineers and federal government on flood protection projects because the federal government will cover up to 65% of a flood protection project's cost. However, the author notes that this federal process can be sluggish and flood projects in areas like Lathrop, Manteca, Sacramento, Stockton, and West Sacramento are in danger of missing the deadline to achieve urban level of flood protection as a result: local flood management agencies "struggle to demonstrate adequate progress while engaged in this collaborative approach through no fault of their own because of the pace of the [U.S. Army Corps of Engineers]."
Arguments in Support
The California Central Valley Flood Control Association (CCVFCA) supports this bill arguing that local flood control agencies face many challenges in meeting statutory deadlines to complete flood protection projects due to delays in obtaining federal authorization, project funding, and permit approvals. To finance flood protection projects, local agencies often rely "on the improvement of real property like new housing projects to raise money for local agency cost sharing of project costs." Given this, CCVFCA asserts that "the imposition of a building moratorium during the course of project development would halt progress toward completing a project."
Arguments in Opposition
None on file.
FISCAL COMMENTS
According to the Assembly Appropriations Committee, this bill could result in higher liability exposure for the state, possibly in the tens of millions to hundreds of millions of dollars, or more (General Fund). Under current law, Mossdale Tract is required to achieve urban level of flood protection by 2028. By providing Mossdale Tract an additional two years to comply, this bill could extend and potentially increase the state's liability for flood damages in the area, particularly if the San Joaquin Area Flood Control Agency successfully demonstrates that the development projects were not "unreasonably" approved and, therefore, avoids sharing in any damages from a flood event.
VOTES
SENATE FLOOR: 40-0-0
YES: Allen, Alvarado-Gil, Archuleta, Ashby, Atkins, Becker, Blakespear, Bradford, Caballero, Cortese, Dahle, Dodd, Durazo, Eggman, Glazer, Gonzalez, Grove, Hurtado, Jones, Laird, Limón, McGuire, Menjivar, Min, Newman, Nguyen, Niello, Ochoa Bogh, Padilla, Portantino, Roth, Rubio, Seyarto, Skinner, Smallwood-Cuevas, Stern, Umberg, Wahab, Wiener, Wilk
ASM WATER, PARKS, AND WILDLIFE: 15-0-0
YES: Bauer-Kahan, Mathis, Alanis, Bennett, Megan Dahle, Davies, Friedman, Hart, Kalra, Pellerin, Blanca Rubio, Schiavo, Villapudua, Ward, Weber
ASM APPROPRIATIONS: 11-0-5
YES: Holden, Bryan, Calderon, Wendy Carrillo, Mike Fong, Hart, Lowenthal, Papan, Pellerin, Weber, Wilson
ABS, ABST OR NV: Megan Dahle, Dixon, Mathis, Sanchez, Soria
UPDATED
VERSION: September 1, 2023
CONSULTANT: Pablo Garza / W., P., & W. / (916) 319-2096 FN: 0001616
Date of Hearing: August 23, 2023
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Chris Holden, Chair
SBPCA Bill Id:SB 586
Author:(Eggman) – As Amended Ver:May 2, 2023
Policy Committee: | Water, Parks and Wildlife | Vote: | 15 - 0 |
|
| ||
|
|
Urgency: No State Mandated Local Program: Yes Reimbursable: Yes
SUMMARY:
This bill permits Mossdale Tract and the City of West Sacramento to approve development in flood hazard areas that have not achieved the urban level of flood protection or that are not making adequate progress on achieving this standard provided the local flood management agency demonstrates ongoing engagement with the federal government to complete a project to meet the urban level of flood protection.
Specifically, this bill, among other things:
- Deletes the 2028 deadline for Mossdale Tract and the 2030 deadline for the City of West Sacramento to achieve the urban level of flood protection.
- Provides that Mossdale Tract and the City of West Sacramento do not need to meet their deadlines to achieve the urban level of protection, or make adequate progress on achieving this standard, so long as the flood management agency has one of the following:
- An active federal study, provided the study has received federal appropriations in the current or previous two federal fiscal years.
- A completed federal study awaiting congressional authorization for less than four years from the date of transmittal.
- An authorized federal project receiving or awaiting the receipt of federal appropriations to advance design, construction, or project closeout activities, provided the study has received federal appropriations in the current or previous three federal fiscal years.
- Provides that if the conditions described in 2, above, are not met, the 2025 deadline in current law shall apply.
- Provides that the San Joaquin Area Flood Control Agency or West Sacramento Area Flood Control Agency may be required to contribute its fair and reasonable share of any property damage caused by a flood to the extent the state’s exposure to liability has been increased by cities or counties that unreasonably approve any new development in those areas between January 1, 2025, and when urban level flood protection is achieved.
FISCAL EFFECT:
This bill could result in higher liability exposure for the state, possibly in the tens of millions to hundreds of millions of dollars, or more. This bill provides that the local flood control agencies may be required to contribute their fair and reasonable share of any property damage caused by a flood to the extent the state’s exposure to liability has been increased by cities or counties that “unreasonably approve” any new development in those areas between January 1, 2025, and when urban level flood protection is achieved. “Unreasonably approved” is defined as approving a new development project without “appropriately considering significant risks of flooding made known to the approving agency as of the time of approval and without taking reasonable and feasible action to mitigate the potential property damage to the new development resulting from a flood.”
Under current law, Mossdale Tract and the City of West Sacramento are required to achieve urban level of flood protection by 2028 and 2030, respectively. By substituting concrete deadlines with a demonstration of ongoing engagement with the federal government to complete a project, development projects that may not otherwise be built should the local flood control agencies miss their current 2028 and 2030 deadlines could – under this bill – proceed and for a much longer period. This could extend and potentially increase the state’s liability for flood damages in those areas, particularly if the locals successfully demonstrate that the projects were not unreasonably approved and avoid sharing in any damages.
COMMENTS:
1) Purpose. According to the author:
Because of the sluggishness of the USACE and the federal process, many of the projects in areas like Lathrop, Manteca, Stockton, and West Sacramento are in danger of missing the 2025 deadline and failing to achieve the 200-year standard of flood protection required under SB 5 altogether. LFMAs struggle to demonstrate adequate progress while engaged in this collaborative approach through no fault of their own because of the pace of USACE. If the adequate progress standard is not updated to allow more time and flexibility to LFMAs working with USACE, the State risks losing out on billions of dollars of federal investments, and puts vulnerable communities at risk of catastrophic flood damage which is an inevitability given current climate change projections.
2) Background.
Urban Level of Flood Protection. SB 5 (Machado), Chapter 364, Statutes of 2007, prohibits cities and counties in the Sacramento-San Joaquin Valley that are protected by the State Plan of Flood Control from approving new development or increasing the housing density within existing developments unless there is flood protection that meets the "urban level of flood protection" – the level of protection necessary to withstand a flood event that has a 1-in-200 chance of occurring in any given year – unless the city of county makes specified findings. Areas that do not have urban level of flood protection must achieve, or make adequate progress towards achieving, the urban level of flood protection by 2025. These requirements were enacted by the Legislature in 2007 as part of a comprehensive flood package resulting from increased awareness of the flood threat to Central Valley communities in the wake of Hurricane Katrina.
AB 838 (Eggman), Chapter 208, Statutes of 2020, and SB 901 (Pan), Chapter 708, Statutes of 2022, extended the deadlines for Mossdale Tract (in San Joaquin County) and the City of West Sacramento to meet urban level of flood protection because the flood management agencies for these areas had experienced unforeseen delays in making progress. AB 838 extended the deadline for Mossdale Tract by three years to 2028, and SB 901 extended the deadline for the City of West Sacramento by five years to 2030.
Mossdale Tract Area Urban Flood Risk Reduction Project. Mossdale Tract consists of 22,400 acres and includes portions of Reclamation District 17 (RD 17), Stockton, Lathrop, Manteca, and unincorporated San Joaquin County. According to the San Joaquin Area Flood Control Agency (SJAFCA), the existing levees for the Mossdale Tract area do not provide 200-year flood protection as required by state law. To address this deficiency, SJAFCA is working with RD 17 to improve Mossdale Tract’s levees through an ongoing Levee Seepage Repair Project, levee improvements, and an extension of exiting levee in Manteca. SJAFCA has completed a feasibility study for this project and is now performing a design and environmental impact report for the project. Additionally, SJAFCA and the Department of Water Resources (DWR) are partnering with U.S. Army Corps of Engineers to obtain federal construction funding. In 2022, the U.S. Army Corps of Engineers initiated a study, which must be completed and presented to Congress for authorization and appropriations. The Army Corps expects to complete this study in 2026. According to DWR, the state has contributed $52 million toward the project thus far.
West Sacramento Project for Flood Risk Reduction. This project encompasses upgrades to over 50 miles of levees that protect the City of West Sacramento and its more than 50,000 residents from flooding that has a 1-in-200 chance of occurring in a given year. The estimated cost for the West Sacramento Project is $1.2 billion. The original federal authorization was in the Water Resource Development Act of 1992 (PL 102-580). The U.S. Army Corps of Engineers reassessed this project in the General Reevaluation Report (GRR) that was submitted to Congress in January 2016; subsequently, the Water Resources Infrastructure Improvement for the Nation Act of 2016 updated the Project’s federal authorization to reflect changes recommended by the GRR. According to DWR, the state has contributed $206 million to the project thus far, and the state’s total cost-share commitment is approximately $517 million.
This bill removes the (extended) deadlines for these two areas to achieve urban level of flood protection and, instead, imposes a requirement that so long as the flood management agencies for these areas are working with the federal government on a flood protection project for the area, they may continue to develop. The bill’s sponsors argue the current statutory deadlines are problematic, because (a) delays are often out of control of the local agency and project progress is in the hands of the federal government, (b) it is uncertain if the project would qualify as making “adequate progress,” causing developers to take their projects elsewhere, and (c) the local jurisdiction needs the development fees from the development projects to be able to finance the flood work.
Liability. In Paterno v. State of California (2003) 114 Cal.App.4th 308, the court determined that the State of California can be liable for failure of levees in the Sacramento and San Joaquin Valleys if the state fails to have a “reasonable plan” for operating and maintaining the levees. The court reasoned that the levees were a public improvement, thus placing liability on the state for any damage that resulted from the improvement, including potential levee failure.
The 2007 package of flood bills mentioned above, including SB 5, were in response to the Paterno decision. SB 5’s prohibition against new development or increased occupancy in flood hazard zones without the urban level of flood protection, unless the development met one of four categories, appears to be the Legislature’s response to the court’s “responsible plan” ruling. The flood package also included provisions to ensure that local agencies shared in the liability should development decisions made at the local level result in future flood damages. While the state, generally, assumes liability for flood damages, Water Code §8307 authorizes the state to impose liability on local agencies in the event a local agency unreasonably approved a new development project in a Central Valley floodplain, as previously defined. However, if the development falls into one of the categories that would permit development, locals are not required to contribute and the state is solely responsible.
Support. Among others in support, the City of West Sacramento writes:
The City and WSAFCA have been proactive in seeking federal authorization, completing project design, lobbying for construction funds, and utilizing local funding sources to partner with the state on the advanced construction of several projects, including the Southport Setback Levee Project.
Despite the City’s prioritization of the project and progress to date, the reality is that the federal government is responsible for the majority of project funding and construction. This means that the City and WSAFCA have relatively little control over meeting the state-mandated deadline. The Legislature and Governor recognized this when they enacted prior extensions to that deadline. SB 586 would clarify that communities taking reasonable steps to meet the mandated level of flood protection should not be punished for delays in federal funding and construction.
Analysis Prepared by: Nikita Koraddi / APPR. / (916) 319-2081
Date of Hearing: June 20, 2023
ASSEMBLY COMMITTEE ON WATER, PARKS, AND WILDLIFE
Rebecca Bauer-Kahan, Chair
SBPCA Bill Id:SB 586
Author:(Eggman) – As Amended Ver:May 2, 2023
SENATE VOTE: 40-0
SUBJECT: Flood management: deadlines
SUMMARY: Eliminates deadlines for Mossdale Tract and the City of West Sacramento to meet urban level of flood protection and replaces them with a requirement that flood management agencies for these areas demonstrate ongoing engagement with the federal government to complete a project to meet urban level of flood protection. Specifically, this bill:
- Deletes the 2028 deadline for Mossdale Tract to achieve urban level of flood protection.
- Deletes the 2030 deadline for the City of West Sacramento to achieve urban level of flood protection.
- Provides that Mossdale Tract and City of West Sacramento do not need to meet the deadline to achieve urban level of protection, or make adequate progress on achieving this standard, so long as the flood management agency has one of the following:
- An active federal study;
- A completed federal study awaiting congressional authorization; or
- An authorized federal project awaiting federal appropriations.
- Provides that the San Joaquin Area Flood Control Agency or West Sacramento Area Flood Control Agency shall assume a fair and reasonable share of flood liability for Mossdale Tract and the City of West Sacramento beginning January 1, 2025 and ending when urban level of flood protection for those areas is achieved.
- Defines “City of West Sacramento” and “Mossdale Tract” for purposes of this bill.
- Makes technical and conforming changes.
EXISTING LAW:
- Provides the Department of Water Resources (DWR) with authority to plan and fund projects to protect lands subject to flooding and to maintain and operate specified facilities of the Sacramento River Flood Control Project (Water Code §§ 8330 et seq. and 8360 et seq.).
- Defines “State Plan of Flood Control” as the state and federal flood control works, lands, programs, plans, conditions, and modes of maintenance and operations of the Sacramento River Flood Control Project and authorizes flood control projects in the Sacramento River and San Joaquin River watersheds for which the Central Valley Flood Protection Board (CVFPB) or DWR has provided the assurances of nonfederal cooperation to the United States (Public Resources Code § 5096.805).
- Provides that a city or county may be required to contribute its fair and reasonable share of the property damage caused by a flood to the extent to which that city or county has increased the state’s exposure to liability for property damage by unreasonably approving a new development in an area protected by a state flood control project (Water Code § 8307).
- Charges CVFPB with ensuring that appropriate standards are met for the construction, maintenance, and protection of flood infrastructure for the Central Valley (Water Code § 8590 et seq.).
- Requires CVFPB to adopt the Central Valley Flood Protection Plan (CV Flood Plan) prepared by DWR after holding two public hearings by January 1, 2012 and to update the CV Flood Plan every five years thereafter (Water Code § 9603 et seq.).
- Defines “urban level of flood protection” as the level of protection necessary to withstand a flood event that has a 1-in-200 chance of occurring in any given year (Water Code § 9602).
- Prohibits a city or county in the Sacramento-San Joaquin Valley from approving a new subdivision, a new development, or an increase in housing density within an existing development unless the city or county finds that flood management facilities protect the property where one of those actions is proposed to the “urban level of flood protection” or that the local flood management agency has made “adequate progress” towards achieving “urban level of flood protection” (Government Code §§ 65865.5 and 65962).
- Requires urban or urbanizing areas protected by a levee that is part of the State Plan of Flood Control (generally, throughout the Sacramento-San Joaquin Valley) to achieve “urban level of flood protection” by 2025 (Government Code § 65962).
- Permits Mossdale Tract to achieve the urban level of flood protection standard in 2028 (Government Code § 65962.1) and the City of West Sacramento to achieve it in 2030 (Government Code § 65962.2).
FISCAL EFFECT: Unknown. This bill is keyed fiscal.
COMMENTS:
- Purpose of this bill. According to the author, local flood management agencies benefit from working with the U.S. Army Corps of Engineers and federal government on flood protection projects because the federal government will cover up to 65% of a flood protection project’s cost. However, the author notes that this federal process can be sluggish and flood projects in areas like Lathrop, Manteca, Sacramento, Stockton, and West Sacramento are in danger of missing the deadline to achieve urban level of flood protection as a result: local flood management agencies “struggle to demonstrate adequate progress while engaged in this collaborative approach through no fault of their own because of the pace of the [U.S. Army Corps of Engineers].” The author argues this bill is necessary because if “the adequate progress standard is not updated to allow more time and flexibility to [local flood management agencies], the state risks losing out on billions of dollars of federal investments and puts vulnerable communities at risk of catastrophic flood damage which is an inevitability given current climate change projections.”
- Background. Today, the level of flood risk in California’s Central Valley is among the highest in the nation. According to the CV Flood Plan 2022 Update, 1.23 million people and more than $223 billion in structures and property are at risk from flooding. With historic storms like the Great Flood of 1862 and even more recent events like the series of atmospheric river-fed storms from winter 2023, human-made flood management efforts struggle to compete against the natural state of the Central Valley. Analysis done as part of ARkStorm 2.0 indicates that climate change has already increased the frequency and magnitude of severe storms that result in “megaflood” events.[1] Perhaps more concerning relative to this bill, the researchers that produced ARkStorm 2.0 conclude “that extremely severe winter storm sequences once thought to be exceptionally rare events are likely to become much more common under essentially all plausible future climate trajectories—suggesting the 20th century hazard mapping, emergency response plans, and even physical infrastructure design standards may already be out of date in a warmer 21st century climate.”[2]
Urban level of flood protection. Cities and counties in the Sacramento-San Joaquin Valley that are protected by the State Plan of Flood Control are prohibited from approving new development or increasing the housing density within existing developments unless there is flood protection that meets the "urban level of flood protection" (i.e., the level of protection necessary to withstand a flood event that has a 1-in-200 chance of occurring in any given year). Areas that do not have urban level of flood protection must achieve, or make adequate progress towards achieving, the urban level of flood protection by 2025. These requirements were enacted by the Legislature in 2007 as part of a comprehensive flood package resulting from increased awareness of the flood threat to Central Valley communities in the wake of Hurricane Katrina.
Recently, the Legislature passed AB 838 (Eggman) in 2020 and SB 901 (Pan) in 2022 to extend the deadlines to meet urban level of flood protection for Mossdale Tract (in San Joaquin County) and the City of West Sacramento because the flood management agencies for these areas had experienced unforeseen delays in making progress toward achieving the urban level of flood protection. AB 838 extended the deadline for Mossdale by three years to 2028 and SB 901 extended the deadline for the City of West Sacramento by five years to 2030. Under AB 838 and SB 901, the flood management agencies for Mossdale Tract and the City of West Sacramento are liable for their "fair and reasonable share of any property damage caused by a flood" that occurs between 2025 and the new deadlines. This bill removes the (extended) deadlines for these two areas to achieve urban level of flood protection and, instead, imposes a requirement that so long as the flood management agencies for these areas are working with the federal government on a flood protection project for the area, they may continue to develop.
Mossdale Tract Area Urban Flood Risk Reduction Project. Mossdale Tract consists of 22,400 acres and includes portions of Reclamation District 17 (RD 17), Stockton, Lathrop, Manteca, and unincorporated San Joaquin County. According to the San Joaquin Area Flood Control Agency (SJAFCA), the existing levees for the Mossdale Tract area do not provide 200-year flood protection as required by state law. To address this deficiency, SJAFCA is working with RD 17 to improve Mossdale Tract’s levees through an ongoing Levee Seepage Repair Project, levee improvements, and an extension of exiting levee in Manteca. SJAFCA has completed a feasibility study for this project and is now performing a design and environmental impact report for the project. Additionally, SJAFCA and DWR are partnering with U.S. Army Corps of Engineers to obtain federal construction funding. In 2022, a federal study was initiated and must be completed and presented to Congress for authorization and appropriations. The study is expected to be completed in 2026.
West Sacramento Project for flood risk reduction. This project encompasses upgrades to over 50 miles of levees that protect the City of West Sacramento and its more than 50,000 residents from flooding that has a 1-in-200 chance of occurring in a given year. The estimated cost for the West Sacramento Project is $1.2 billion. The original federal authorization was in the Water Resource Development Act of 1992 (PL 102-580). The U.S. Army Corps of Engineers reassessed this project in the General Reevaluation Report (GRR) that was submitted to Congress in January 2016; subsequently, the Water Resources Infrastructure Improvement for the Nation Act of 2016 updated the Project’s federal authorization to reflect changes recommended by the GRR. - Arguments in support. The California Central Valley Flood Control Association (CCVFCA) supports this bill arguing that local flood control agencies face many challenges in meeting statutory deadlines to complete flood protection projects due to delays in obtaining federal authorization, project funding, and permit approvals. To finance flood protection projects, local agencies often rely “on the improvement of real property like new housing projects to raise money for local agency cost sharing of project costs.” Given this, CCVFCA asserts that “the imposition of a building moratorium during the course of project development would halt progress toward completing a project.”
- Related legislation. SB 901 (Pan), Chapter 708, Statutes of 2022, updates the authorization for the West Sacramento Project for flood risk reduction and extends the deadline for the City of West Sacramento to achieve urban level of flood protection to 2030.
AB 838 (Eggman), Chapter 208, Statutes of 2020, extends the date for the Mossdale Tract in San Joaquin County to reach urban level of flood protection from 2025 to 2028.
SB 580 (Pan), Chapter 309, Statutes of 2017, revises the authorization for the flood control project along the American and Sacramento Rivers, and the Natomas Basin, as further modified by Congress.
SB 5 (Machado), Chapter 364, Statutes of 2007, requires DWR and CVFPB to prepare and adopt a CV Flood Plan by 2012, and establishes certain flood protection requirements for certain local land-use decisions consistent with the CV Flood Plan.
REGISTERED SUPPORT / OPPOSITION:
Support
Business Council San Joaquin County
California Building Industry Association
California Central Valley Flood Control Association
City of Manteca
Opposition
None on file
Analysis Prepared by: Pablo Garza / W., P., & W. / (916) 319-2096
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 586 |
THIRD READING
Bill No: SB 586
Author: Eggman (D)
Amended: 5/2/23
Vote: 21
SENATE NATURAL RES. & WATER COMMITTEE: 9-0, 3/28/23
AYES: Min, Allen, Becker, Eggman, Grove, Hurtado, Laird, Limón, Padilla
NO VOTE RECORDED: Seyarto, Dahle
SENATE GOVERNANCE & FIN. COMMITTEE: 8-0, 4/19/23
AYES: Caballero, Seyarto, Blakespear, Dahle, Durazo, Glazer, Skinner, Wiener
SENATE APPROPRIATIONS COMMITTEE: Senate Rule 28.8
SUBJECT: Flood management: deadlines
SOURCE: San Joaquin Area Flood Control Agency
West Sacramento Area Flood Control Agency
DIGEST:
This bill permits Mossdale Tract and the City of West Sacramento to approve development in flood hazard areas that do not have an urban level of flood protection or that are not making adequate progress, as defined in existing law, on a flood protection system as long as the local flood control agency has an active federal project, as specified.
ANALYSIS:
Existing law:
- Defines the urban level of flood protection to be “the level of protection that is necessary to withstand flooding that has a 1-in-200 chance of occurring in any given year …” This is sometimes referred to as a 200 year level of protection.
- Prohibits a city or county within the Sacramento-San Joaquin Valley from entering into a development agreement for property within a flood hazard zone unless the city or county finds one of the following:
- The facilities of the property are protected to the appropriate level of flood protection in urban and nonurbanized areas.
- The city or county has imposed conditions on the development agreement that will protect the property to the appropriate level of flood protection in urban and nonurbanized areas.
- The local flood management agency has made “adequate progress” on the construction of a flood protection system that will result in the appropriate level of flood protection in urban and nonurbanized areas. For urban and urbanizing areas protected by project levees, the urban level of flood protection shall be achieved by 2025.
- Defines “adequate progress” to mean all of the following:
- The total project scope, schedule, and cost of the completed flood protection system have been developed to meet the appropriate standard of protection.
- Revenues that are sufficient to fund each year of the project schedule have been identified and, in any given year and consistent with that schedule, at least 90 percent of the revenues scheduled to be received by that year have been appropriated and are currently being expended. (There is an exception where state funding was not appropriated consistent with a funding agreement between a state agency and a local flood management agency.)
- Critical features of the flood protection system are under construction, and each critical feature is progressing as indicated by the actual expenditure of the construction budget funds.
- The city or county has not been responsible for a significant delay in the completion of the system.
- The local flood management agency provides the Department of Water Resources (DWR) and the Central Valley Flood Protection Board (CVFPB) with the required information specified in this subdivision sufficient to determine substantial completion of the required flood protection.
- Extends the deadline for the City of West Sacramento to achieve the urban level of flood protection from 2025 to 2030.
- Extends the date for the Mossdale Tract to reach an urban level of flood protection from 2025 to 2028.
This bill:
- Provides that the deadline to achieve an urban level of flood protection, and the requirement to make adequate progress on the construction of a flood system providing an urban level of flood protection, does not apply to the City of West Sacramento and Mossdale Tract as long as the flood management agency has one of the following:
- An active federal study, as specified.
- A completed federal study delivered to Congress and awaiting congressional authorization, as specified.
- An authorized federal project receiving or awaiting the receipt of federal appropriations to advance design, construction, or project closeout activities, as specified.
- Provides that the San Joaquin Area Flood Control Agency or the West Sacramento Area Flood Control Agency may be required to contribute its fair and reasonable share of any property damage caused by a flood to the extent that the state’s exposure to liability for property damage has been increased by cities or counties that unreasonably approve any new development, as specified.
Background
Overview of SB 5 (2007). In 2007, the Legislature passed and the Governor signed a comprehensive package of flood bills. [SB 5 (Machado, Chapter 364, Statutes of 2007), SB 17 (Florez, Chapter 365, Statutes of 2007), AB 5 (Wolk, Chapter 366, Statutes of 2007), AB 70 (Jones, Chapter 367, Statutes of 2007), AB 156 (Laird, Chapter 368, Statutes of 2007), and AB 162 (Wolk, Chapter 369, Statutes of 2007)]
The over-arching concept behind these bills was:
1st Stop putting people in harm’s way.
2nd Determine where the greatest risk of harm is.
3rd Develop and implement plans to reduce that risk.
Among other things, SB 5 defined the urban level of flood protection to be “the level of protection that is necessary to withstand flooding that has a 1-in-200 chance of occurring in any given year …” (Government Code (Govt. C.) §65007). SB 5 also set the national Federal Emergency Management Act (FEMA) standard of flood protection of 100 year protection as the objective for nonurbanized areas.
SB 5 prohibits a city or county within the Sacramento-San Joaquin Valley from entering into a development agreement for property within a flood hazard zone unless the city or county finds one of the following: (Govt. C. §65865.5)
- The facilities of the property are protected to the appropriate level of flood protection in urban and nonurbanized areas.
- The city or county has imposed conditions on the development agreement that will protect the property to the appropriate level of flood protection in urban and nonurbanized areas.
- The local flood management agency has made “adequate progress” on the construction of a flood protection system that will result in the appropriate level of flood protection in urban and nonurbanized areas. For urban and urbanizing areas protected by project levees, the urban level of flood protection shall be achieved by 2025.
- The property is in an undetermined risk area and has met the urban level of flood protection based on substantial evidence. (Added by subsequent legislation).
“Adequate progress” is defined to mean all of the following: (Govt. C. §65007)
- The total project scope, schedule, and cost of the completed flood protection system have been developed to meet the appropriate standard of protection.
- Revenues that are sufficient to fund each year of the project schedule have been identified and, in any given year and consistent with that schedule, at least 90 percent of the revenues scheduled to be received by that year have been appropriated and are currently being expended. (There is an exception where state funding was not appropriated consistent with a funding agreement between a state agency and a local flood management agency.)
- Critical features of the flood protection system are under construction, and each critical feature is progressing as indicated by the actual expenditure of the construction budget funds.
- The city or county has not been responsible for a significant delay in the completion of the system.
- The local flood management agency provides the DWR and the CVFPB with required specified information sufficient to determine substantial completion of the required flood protection.
Similarly, cities and counties within the Sacramento-San Joaquin Valley are prohibited from approving a discretionary permit or other discretionary entitlement that would result in the construction of a new building or construction that would result in an increase in allowed occupancy of an existing building, or a ministerial permit that would result in the construction of a new residence for projects located within a flood hazard zone and are required to deny a tentative map or parcel map for a subdivision located within a flood hazard zone unless certain findings are made, including that the local flood management agency (LFMA) has made adequate progress on the construction of a flood protection system. (Govt. C. §§65962, 66474.5).
Comments
- According to the author, “In the year’s following the devastation of Hurricane Katrina in New Orleans, California took action to address the seriously outdated flood infrastructure in our state through a package of bills with the ultimate goal of raising our state’s overall flood protection levels. SB 5 was a centerpiece of that package, which sought to motivate local agencies to achieve higher levels of flood protection as quickly as possible, and set a deadline to achieve a 200-year standard of flood protection by 2025. Local flood management agencies (LFMAs) are required to demonstrate a project is on schedule to achieve this standard of protection by submitting annual “adequate progress” reports. Any LFMA who fails to demonstrate adequate progress is prohibited from approving future development approvals, and cannot resume development until an LFMA can demonstrate progress is back on schedule. The fees associated with such development are what typically fund the LFMA’s upfront costs associated with flood projects. To make these flood projects pencil out, LFMAs work with state and federal partners to share the cost burdens of these critically needed flood projects. While this collaborative approach is very time consuming, United States Army Corps of Engineers (USACE) projects bring significant federal investment to the project covering around 65% of total costs. This strategy of partnering with USACE, encouraged by the Department of Water Resources, has brought billions of dollars of federal investments to our state and significantly reduced State and local costs. However, because of the sluggishness of the USACE and the federal process, many of the projects in areas like Lathrop, Manteca, Stockton, and West Sacramento are in danger of missing the 2025 deadline and failing to achieve the 200-year standard of flood protection required under SB 5 altogether. LFMAs struggle to demonstrate adequate progress while engaged in this collaborative approach through no fault of their own because of the pace of USACE. If the adequate progress standard is not updated to allow more time and flexibility to LFMAs working with USACE, the State risks losing out on billions of dollars of federal investments, and puts vulnerable communities at risk of catastrophic flood damage which is an inevitability given current climate change projections.”
- Back so soon? Recent legislation gave specific areas within the Sacramento-San Joaquin Valley region an extension on to achieve the urban level of flood protection. AB 838 (Eggman, Chapter 208, Statutes of 2020) gave Mossdale Tract an additional three years, until 2028. SB 901 (Pan, Chapter 708, Statutes of 2022) gave the City of West Sacramento an additional five years, from 2025 to 2030, for urban and urbanizing areas protected by West Sacramento Flood Project levees.
Rather than impose specific deadlines to achieve the urban level of flood protection, SB 586 proposes to substitute the deadline and the adequate progress on a construction of a flood system requirement with the presence of a USACE project. As long as the flood management agency has either (1) an active federal study, as specified; (2) a completed federal study delivered to Congress and awaiting congressional authorization, as specified; or (3) an authorized federal project receiving or awaiting the receipt of federal appropriations to advance design, construction, or project closeout activities, as specified, the deadline to achieve the urban level of flood protection and the requirement for adequate progress on the construction of a flood system does not apply.
The sponsors provide 3 reasons why the previous extensions from prior legislation have been inadequate: (1) delays are often out of control of the local agency and project progress is in the hands of the federal government, (2) it is uncertain if the project would qualify as making “adequate progress,” causing developers to take their projects elsewhere, and (3) the local jurisdiction needs the development fees from the development projects to be able to finance the flood work.
- Here comes the rain again. In Paterno v. State of California (2003) 114 Cal.App.4th 308, the court determined that the State of California can be liable for failure of levees if the state fails to have a “reasonable plan” for operating and maintaining the levees in the Sacramento and San Joaquin Valleys. The state responded to Paterno by adopting the Central Valley Flood Protection Plan and enacting SB 5, which allowed development in flood hazard areas only when specified conditions are met, including when the local flood control management agency could make a finding based on substantial evidence in the record that it had made adequate progress on construction of a flood control project that will achieve an urban level of flood protection by 2025.
While the state, generally, assumes liability for flood damages, Water Code §8307 authorizes the state to impose liability on local agencies in the event a local agency unreasonably approved a new development project in a Central Valley floodplain “without appropriately considering significant risks of flooding made known to the approving agency … and without taking reasonable and feasible action to mitigate the potential property damage to the new development resulting from a flood.” However, if the development falls into one of the four categories that would permit development, the locals are not required to contribute and the state is solely responsible.
Under SB 586, development that would not otherwise be built could proceed and could extend the state’s liability for flood damages in those areas.
Related/Prior Legislation
SB 23 (Caballero) requires the California Department of Fish and Wildlife, for flood risk reduction projects and water supply projects that are subject to lake and streambed alterations agreements, to issue the final agreement within specified timeframes if the project proponent meets certain conditions. SB 23 would also require the State Water Resources Control Board (SWRCB) and regional water quality control boards, when issuing water quality certifications under the Federal Clean Water Act for flood risk reduction projects and water supply projects, to adhere to specified procedures in reviewing the application. SB 23 is pending before the Senate Appropriations Committee.
AB 921 (McCarty, 2022) would have extended the deadline for the City of West Sacramento to achieve the urban level of flood protection from 2025 to 2030, revised and updated the state authorization for the West Sacramento Flood Risk Reduction Project, and consolidated entities responsible for levee maintenance. AB 921 was held in Senate Natural Resources and Water Committee.
AB 2108 (Eggman, 2014) would have made a number of changes to the statutes relating to flood management in the Sacramento-San Joaquin Valley, including, among others, allowing the CVFPB to determine that preconstruction planning or design activities of a flood protection system by a LFMA are sufficient to constitute adequate progress, amending the definition of “adequate progress” by adding that critical features of the flood protection system are being planned or designed and certain determinations made by the CVFPB have not expired, and allows discretionary permits be issued if it would not result in more than a 50% increase in building occupancy. AB 2108 was held in the Senate Natural Resources and Water Committee.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
SUPPORT: (Verified 5/8/23)
San Joaquin Area Flood Control Agency (co-source)
West Sacramento Area Flood Control Agency (co-source)
California Building Industry Association
California Central Valley Flood Control Association
County of San Joaquin
City of Lathrop
City of Manteca
City of Stockton
City of West Sacramento
OPPOSITION: (Verified 5/8/23)
None received
ARGUMENTS IN SUPPORT: According to the California Central Valley Flood Control Association (CCVFCA), “CCVFCA supports the construction, repair, rehabilitation, and replacement of flood control facilities to provide and maintain a 200-year urban level of protection for people, buildings, and the environment in urban and urbanizing areas. Local flood control agencies confront many challenges in meeting statutory deadlines, including obtaining Federal and State project approvals and permits and securing financing for projects. It is the latter, for example, that often relies on the improvement of real property like new housing projects to raise money for local agency cost sharing of project costs. The imposition of a building moratorium during the course of project development would halt progress toward completing a project.”
Prepared by: Genevieve Wong / N.R. & W. / (916) 651-4116
5/10/23 15:29:18
SENATE COMMITTEE ON GOVERNANCE AND FINANCE
Senator Anna M. Caballero, Chair
2023 - 2024 Regular
Bill No: | SB 586 | Hearing Date: | 4/19/23 |
Author: | Eggman | Tax Levy: | No |
Version: | 3/29/23 | Fiscal: | Yes |
Consultant: | Grinnell | ||
Flood management: deadlines
Provides that the deadlines to achieve an urban level of flood protection necessary for housing development do not apply to Mossdale Tract and the City of West Sacramento when the local flood control agency has an active federal project, as defined.
Background
The Planning and Zoning Law requires every county and city to adopt a general plan that sets out planned uses for all of the area covered by the plan. Cities’ and counties’ major land use decisions—including development permitting—must be consistent with their general plans. In this way, the general plan is a blueprint for future development.
In 2007, the Legislature enacted a package of five bills designed to increase protection from damaging flood waters. Those bills included requirements for local governments in the Sacramento-San Joaquin Valley to improve local land use and other planning decisions by strengthening the link between land use and flood management. One bill in the package, SB 5 (Machado, 2007), required the Department of Water Resources (DWR) and the Central Valley Flood Protection Board (CVFPB) to prepare and adopt a Central Valley Flood Protection Plan by 2012, and established certain flood protection requirements for certain local land-use decisions consistent with the Central Valley Protection Plan.
SB 5 required each city and county within the Sacramento-San Joaquin Valley to amend its general plan within two years of the CVFPB adopting the Flood Plan. A city or county within the Sacramento-San Joaquin Valley must amend its zoning ordinance to make it consistent with its general plan within 36 months of the Board's adopting the Flood Plan.
Under SB 5, cities and counties in the Sacramento-San Joaquin Valley cannot approve new development or increase the housing density within existing developments unless they find one of the following conditions based on substantial evidence in the record:
- There is flood protection that meets the "urban level of flood protection" (the level of protection necessary to withstand a flood event that has a 1-in-200 chance of occurring in any given year).
- The city or county has imposed conditions on the development agreement that meets the urban level of flood protection in urbanized and nonurbanized areas, or the national Federal Emergency Management Area standard for nonurbanized areas.
- The local flood management agency has made “adequate progress” towards meeting the urban level of flood protection by 2025.
- The property in an undetermined risk area has met the urban level of flood protection.
SB 5 further defined “adequate progress” to mean all of the following:
- The total project scope, schedule, and cost of the completed flood protection system have been developed to meet the appropriate standard of protection.
- Revenues that are sufficient to fund each year of the project schedule have been identified and, in any given year and consistent with that schedule, at least 90 percent of the revenues scheduled to be received by that year have been appropriated and are currently being expended. (There is an exception where state funding was not appropriated consistent with a funding agreement between a state agency and a local flood management agency.)
- Critical features of the flood protection system are under construction, and each critical feature is progressing as indicated by the actual expenditure of the construction budget funds.
- The city or county has not been responsible for a significant delay in the completion of the system.
- The local flood management agency provides the DWR and the CVFPB with required specified information sufficient to determine substantial completion of the required flood protection.
In recent years, the Legislature altered the application of SB 5 in two areas: Mossdale Tract and the City of West Sacramento.
Mossdale Tract. State law defines Mossdale Tract as an area of land identified as Reclamation District No. 17 on page 144 of Bulletin No. 37 (1930) of the DWR, along with such contiguous urban and urbanizing areas to the east of the tract. The San Joaquin Area Flood Control Area (SJAFCA) initially designed a project to be completed in time to meet the 2025 date; however, a 2017 hydrology study completed in 2017 by DWR concluded that climate change would triple the flows on the San Joaquin River by 2065 in a 200-year event, practically requiring SJAFCA to start over planning the project. In response, the Legislature extended the year by which Mossdale Tract must achieve the urban level of flood protection from 2025 to 2028 (AB 838 Eggman, 2020). SJAFCA indicates that it has completed a feasibility study and is now performing a design and environmental impact report for the project, created an Enhanced Infrastructure Finance District and imposed development impact fees to partially finance the project. Additionally, SJAFCA states that it and DWR are partnering with U.S. Army Corps of Engineers (USACE) to obtain federal construction funding. In 2022, a federal study was initiated and must be completed and presented to Congress for authorization and appropriations. SJAFCA expects the study to be completed in 2026.
West Sacramento. State law defines West Sacramento as the incorporated area in the County of Yolo as defined by Resolution No. 86-112 of the County of Yolo Board of Supervisors at the Yolo County Official Records Book 1801, pages 384 to 403, inclusive, and Book 1801, pages 368 to 382, inclusive. SB 901 (Pan, 2022) extended the deadline for the City of West Sacramento by an additional five years, from 2025 to 2030, for urban and urbanizing areas protected by West Sacramento Flood Project levees. Although SB 901 extended West Sacramento’s deadline to 2030, its flood control project now has an expected completion date in 2035.
Both AB 838 and SB 901 included provisions stating that where development occurred, each city or county may be required to contribute their fair and reasonable share of any property damage caused by a flood to the extent that the state’s exposure to liability for property damage has been increased by unreasonably approving any new development. The provisions used a definition in the Water Code for “unreasonably approving,” to mean approving a new development project without appropriately considering significant risks of flooding made known to the approving agency as of the time of approval and without taking reasonable and feasible action to mitigate the potential property damage to the new development resulting from a flood.
The author wants to revise the deadlines previously extended by the Legislature for Mossdale Tract and the City of West Sacramento to allow for development while the USACE projects are proceeding.
Proposed Law
Senate Bill 586 provides that the deadlines to achieve an urban level of flood protection initially set by SB 5, and then extended by AB 838 and SB 901, do not apply, so long as the appropriate flood management agency has one of the following:
- An active federal project in the planning, design, construction, or project closeout phase.
- A completed federal feasibility study awaiting congressional authorization.
- An authorized federal project awaiting the receipt of federal appropriations to advance design, construction, or project closeout activities.
The bill adds provisions identical to AB 838 and SB 901 that state that local agencies where development occurred may be required to contribute their fair and reasonable share of any property damage caused by a flood to the extent that the state’s exposure to liability for property damage has been increased by unreasonably approving any new development, linking to the same definition in the Water Code.
The measure consolidates the two sections added by AB 838 and SB 901 into one, and makes conforming changes to the development limitation sections added by SB 5 for development agreements, discretionary permits and entitlements, and subdivision maps.
The bill states that it only applies to the City of West Sacramento and Mossdale Tract, and includes a legislative finding and declaration stating the need for special legislation.
State Revenue Impact
No estimate.
Comments
1. Purpose of the bill. According to the author, “In the year’s following the devastation of Hurricane Katrina in New Orleans, California took action to address the seriously outdated flood infrastructure in our state through a package of bills with the ultimate goal of raising our state’s overall flood protection levels. SB 5 was a centerpiece of that package, which sought to motivate local agencies to achieve higher levels of flood protection as quickly as possible, and set a deadline to achieve a 200-year standard of flood protection by 2025. Local flood management agencies (LFMAs) are required to demonstrate a project is on schedule to achieve this standard of protection by submitting annual “adequate progress” reports. Any LFMA who fails to demonstrate adequate progress is prohibited from approving future development approvals, and cannot resume development until an LFMA can demonstrate progress is back on schedule. The fees associated with such development are what typically fund the LFMA’s upfront costs associated with flood projects. To make these flood projects pencil out, LFMAs work with state and federal partners to share the cost burdens of these critically needed flood projects. While this collaborative approach is very time consuming, United States Army Corps of Engineers (USACE) projects bring significant federal investment to the project covering around 65% of total costs. This strategy of partnering with USACE, encouraged by the Department of Water Resources, has brought billions of dollars of federal investments to our state and significantly reduced State and local costs. However, because of the sluggishness of the USACE and the federal process, many of the projects in areas like Lathrop, Manteca, Stockton, and West Sacramento are in danger of missing the 2025 deadline and failing to achieve the 200-year standard of flood protection required under SB 5 altogether. LFMAs struggle to demonstrate adequate progress while engaged in this collaborative approach through no fault of their own because of the pace of USACE. If the adequate progress standard is not updated to allow more time and flexibility to LFMAs working with USACE, the State risks losing out on billions of dollars of federal investments, and puts vulnerable communities at risk of catastrophic flood damage which is an inevitability given current climate change projections.”
2. Here comes the rain again. In Paterno v. State of California (2003) 114 Cal.App.4th 308, the court determined that the State of California can be liable for failure of levees if the state fails to have a “reasonable plan” for operating and maintaining the levees in the Sacramento and San Joaquin Valleys. The state responded to Paterno by adopting the Central Valley Flood Protection Plan and enacting SB 5, which allowed development in flood hazard areas only when specified conditions are met, including when the local flood control management agency could make a finding based on substantial evidence in the record that it had made adequate progress on construction of a flood control project that will achieve an urban level of flood protection by 2025. The Legislature has previously extended deadlines for the two areas – Mossdale Tract and West Sacramento - where USACE projects are underway at differing stages, but not yet completed, which SB 586 would extend further. Both extensions stated that local agencies where development occurred may be required to contribute their fair and reasonable share of any property damage caused by a flood to the extent that the state’s exposure to liability for property damage has been increased by unreasonably approving any new development. While the same language is incorporated in SB 586, any development made possible by the bill is in a current flood hazard area, and therefore could be impacted by catastrophic flood. The Committee may wish to consider the progress being made on the projects that will someday achieve the urban level of flood protection, and whether allowing development to occur amid the progress is worth the risk.
3. Incoming! The Committee on Natural Resources approved SB 586 by a vote of 9 to 0 on March 28th. The Committee on Governance and Finance is hearing the measure as the committee of second reference.
4. Special legislation. Section 16 of Article Four of the California Constitution prohibits special legislation when a general law can apply. SB 586 contains findings and declarations explaining the need for legislation that applies only to Mossdale Tract and the City of West Sacramento.
5. Mandate. The California Constitution requires the state to reimburse local governments for the costs of new or expanded state mandated local programs. Because SB 82 requires local agencies to contribute their fair share for any property damage, Legislative Counsel says that it may impose a new state mandate. The measure states that should the Commission on State Mandates determine that the bill imposes a reimbursable mandate, reimbursement must be made pursuant to existing statutory provisions.
6. Technical. Committee staff recommends amending SB 586 on Page 6, Line 8, to strike “ad” and insert “and.”
Support and Opposition
(4/14/23)
Support:
San Joaquin Area Flood Control Agency (Co-Sponsor)
California Building Industry Association
California Central Valley Flood Control Association
City of Lathrop
City of Stockton
City of West Sacramento
County of San Joaquin
Opposition: None submitted
-- END --
SENATE COMMITTEE ON NATURAL RESOURCES AND WATER
Senator Dave Min, Chair
2023 - 2024 Regular
Bill No: SB Hearing Date: March 28, 2023
Author: | Eggman | ||
Version: | February 15, 2023 Introduced | ||
Urgency: | No | Fiscal: | Yes |
Consultant: | Genevieve Wong | ||
Subject: Flood management: deadlines
BACKGROUND AND EXISTING LAW
Overview of SB 5 (2007). In 2007, the Legislature passed and the Governor signed a comprehensive package of flood bills. [SB 5 (Machado) (Stat. 2007, Ch. 364), SB 17 (Florez) (Stat. 2007, Ch. 365), AB 5 (Wolk) (Stat. 2007, Ch. 366), AB 70 (Jones) (Stat. 2007, Ch. 367), AB 156 (Laird) (Stat. 2007, Ch. 368), and AB 162 (Wolk) (Stat. 2007, Ch. 369).]
The over-arching concept behind these bills was:
1st Stop putting people in harm’s way.
2nd Determine where the greatest risk of harm is.
3rd Develop and implement plans to reduce that risk.
Among other things, SB 5 defined the urban level of flood protection to be “the level of protection that is necessary to withstand flooding that has a 1-in-200 chance of occurring in any given year …” (Government Code (Govt. C.) §65007). This is sometimes referred to as a 200-year level of protection. SB 5 also set the national Federal Emergency Management Act (FEMA) standard of flood protection of 100 year protection as the objective for nonurbanized areas.
Additionally, SB 5 prohibits a city or county within the Sacramento-San Joaquin Valley from entering into a development agreement for property within a flood hazard zone unless the city or county finds one of the following: (Govt. C. §65865.5)
- The facilities of the property are protected to the appropriate level of flood protection in urban and nonurbanized areas.
- The city or county has imposed conditions on the development agreement that will protect the property to the appropriate level of flood protection in urban and nonurbanized areas.
- The local flood management agency has made “adequate progress” on the construction of a flood protection system that will result in the appropriate level of flood protection in urban and nonurbanized areas. For urban and urbanizing areas protected by project levees, the urban level of flood protection shall be achieved by 2025.
- The property is in an undetermined risk area and has met the urban level of flood protection based on substantial evidence. (Added by subsequent legislation).
SB 5 further defined “adequate progress” to mean all of the following: (Govt. C. §65007)
- The total project scope, schedule, and cost of the completed flood protection system have been developed to meet the appropriate standard of protection.
- Revenues that are sufficient to fund each year of the project schedule have been identified and, in any given year and consistent with that schedule, at least 90 percent of the revenues scheduled to be received by that year have been appropriated and are currently being expended. (There is an exception where state funding was not appropriated consistent with a funding agreement between a state agency and a local flood management agency.)
- Critical features of the flood protection system are under construction, and each critical feature is progressing as indicated by the actual expenditure of the construction budget funds.
- The city or county has not been responsible for a significant delay in the completion of the system.
- The local flood management agency provides the Department of Water Resources (DWR) and the Central Valley Flood Protection Board (CVFPB) with required specified information sufficient to determine substantial completion of the required flood protection.
SB 5 defined the Sacramento-San Joaquin Valley as the area subject to flooding by the Sacramento or San Joaquin Rivers or their tributaries, not including Tulare Lake basin or the Kings River. (Govt. C. §65007).
Similarly, cities and counties within the Sacramento-San Joaquin Valley are prohibited from approving a discretionary permit or other discretionary entitlement that would result in the construction of a new building or construction that would result in an increase in allowed occupancy of an existing building, or a ministerial permit that would result in the construction of a new residence for projects located within a flood hazard zone and are required to deny a tentative map or parcel map for a subdivision located within a flood hazard zone unless certain findings are made, including that the local flood management agency (LFMA) has made adequate progress on the construction of a flood protection system. (Govt. C. §§65962, 66474.5).
PROPOSED LAW
This bill removes the extensions that gave Mossdale Tract and City of West Sacramento until 2028 and 2030, respectively, to achieve the urban level of flood protection, and instead provides that the deadline to achieve the urban level of flood protection does not apply to the Sacramento-San Joaquin Valley as long as the flood management agency has either:
- An active federal project in the planning, design, construction, or project closeout phase;
- A completed federal feasibility study awaiting congressional authorization; or
- An authorized federal project awaiting the receipt of federal appropriations to advance design, construction, or project closeout activities.
ARGUMENTS IN SUPPORT
According to the author, “…[B]ecause of the sluggishness of the USACE [United States Army Corps of Engineers] and the federal process, many of the projects in areas like Lathrop, Manteca, Sacramento, Stockton, and West Sacramento are in danger of missing the 2025 deadline and failing to achieve the 200-year standard of flood protection required under SB 5 altogether. LFMAs [Local flood management agencies] struggle to demonstrate adequate progress while engaged in this collaborative approach through no fault of their own because of the pace of USACE.”
“If the adequate progress standard is not updated to allow more time and flexibility to LFMAs working with USACE, the State risks losing out on billions of dollars of federal investments, and puts vulnerable communities at risk of catastrophic flood damage which is an inevitability given current climate change projections.”
According to the California Central Valley Flood Control Association (CCVFCA), “CCVFCA supports the construction, repair, rehabilitation, and replacement of flood control facilities to provide and maintain a 200-year urban level of protection for people, buildings, and the environment in urban and urbanizing areas. Local flood control agencies confront many challenges in meeting statutory deadlines, including obtaining Federal and State project approvals and permits and securing financing for projects. It is the latter, for example, that often relies on the improvement of real property like new housing projects to raise money for local agency cost sharing of project costs. The imposition of a building moratorium during the course of project development would halt progress toward completing a project.”
ARGUMENTS IN OPPOSITION
None received
COMMENTS
What’s changed? Recent legislation gave specific areas within the Sacramento-San Joaquin Valley region an extension on their deadlines to achieve the urban level of flood protection. AB 838 (Eggman, Chapter 208, Statutes of 2020) gives Mossdale Tract, as defined by AB 838, an additional three years, until 2028.
Last year, SB 901 (Pan, Chapter 708, Statutes of 2022) gave the City of West Sacramento an additional five years, from 2025 to 2030, for urban and urbanizing areas protected by West Sacramento Flood Project levees. According to the Senate Floor Analysis, the USACE, at the time, estimated that the end date of the West Sacramento Flood Project is December 31, 2030.
Rather than impose specific deadlines to achieve the urban level of flood protection, SB 856 proposes to substitute the deadline with the presence of a USACE project. As long as the flood management agency has either (1) an active federal project in the planning, design, construction, or project closeout phase; (2) a completed federal feasibility study awaiting congressional authorization; or (3) an authorized federal project awaiting the receipt of federal appropriations to advance design, construction, or project closeout activities, the deadline to achieve the urban level of flood protection does not apply.
The sponsors provide 3 reasons why the previous deadlines have been problematic: (1) delays are often out of control of the local agency and project progress is in the hands of the federal government, (2) it is uncertain if the project would qualify as making “adequate progress,” causing developers to take their projects elsewhere, and (3) the local jurisdiction needs the development fees from the development projects to be able to finance the flood work.
The whole enchilada. There are three areas that are working towards the urban level of flood protection and/or could benefit from SB 586 – Mossdale Tract, West Sacramento, and Sacramento. Mossdale Tract and West Sacramento have been subject to previous legislation (described above). Sacramento anticipates substantially completing the work necessary to achieve the urban level of flood protection by 2025.
Rather than targeting specific areas already identified as at-risk to missing the deadline, the author proposes to permit the entire Sacramento-San Joaquin Valley to not be subject to the urban level of flood protection as long as a USACE project is underway. As discussed above, the Sacramento-San Joaquin Valley includes areas subject to flooding by the Sacramento or San Joaquin Rivers or their tributaries, not including Tulare Lake basin or the Kings River. A question may arise if the solution fits the problem. The Committee may wish to consider amending the bill to narrow the scope. (See Amendment 1)
Supa Dupa Flood (I can’t stand the rain). Extending the time to reach the urban level of flood protection would extend the amount of time residents and businesses within the Sacramento-San Joaquin Valley might be vulnerable to a 200-year flood event.
While acknowledging the likelihood of project delays, it is still important to ensure that areas are making headway towards achieving the proper levels of flood protection. Without a defined deadline, an area - hypothetically - could go without an urban level of flood protection indefinitely as projects can be delayed for various reasons, especially if the project is subject to federal appropriations, authorizations, or other actions. SB 586, by allowing areas to rely on a federal project that could be in various stages, including planning or design, would allow areas within the Sacramento-San Joaquin Valley to go unchecked and potentially at risk. This seems to be at tension with the intent of SB 5 and the 2007 flood package. The author may wish to consider ways to provide the Legislature with periodic check-ins and oversight of the impacted areas to ensure that areas do not remain at risk for unreasonable amounts of time. This could include inserting a hard deadline, instead of an open-ended situation, as was done with previous requests for extensions, or building in a reporting requirement.
Is it necessary? According to information provided by the author and San Joaquin Area Flood Control Agency (SJAFCA) on the progress of Mossdale Tract, SJAFCA has completed a feasibility study and is now performing a design and environmental impact report (EIR) for the project. Additionally, SJAFCA and DWR are partnering with USACE to obtain federal construction funding. In 2022, a federal study was initiated and must be completed and presented to Congress for authorization and appropriations. The study is expected to be completed in 2026.
Although SB 901 extended West Sacramento’s deadline to 2030 last year, the project now has an expected completion date in 2035, according to the USACE Sacramento District program manager. Given that West Sacramento project does have an expected completion date, although later than previously thought, it is unclear why an open-ended deadline to achieve the urban level of flood protection is needed for this area. The author may wish to consider other ways to give these projects extensions that are more closely aligned with their anticipated project completion dates.
Sharing is caring. In Paterno v. State of California (2003) 114 Cal.App.4th 308, the court determined that the State of California can be liable for failure of levees if the state fails to have a “reasonable plan” for operating and maintaining the levees in the Sacramento and San Joaquin Valleys. The court reasoned that the levees were a public improvement, thus placing liability on the state for any damage that resulted from the improvement, including potential levee failure.
The 2007 package of flood bills discussed above, including SB 5, were in response to the Paterno decision. SB 5’s prohibition against new development or increased occupancy in flood hazard zones without the urban level of flood protection, unless the development met one of four categories, appears to be the Legislature’s response to the court’s “responsible plan” ruling. The flood package also included provisions to ensure that local agencies shared in the liability should development decisions made at the local level result in future flood damages. While the state, generally, assumes liability for flood damages, Water Code §8307 authorizes the state to impose liability on local agencies in the event a local agency unreasonably approved a new development project in a Central Valley floodplain “without appropriately considering significant risks of flooding made known to the approving agency as of the time of approval and without taking reasonable and feasible action to mitigate the potential property damage to the new development resulting from a flood.” However, if the development falls into one of the four categories that would permit development, the locals are not required to contribute and the state is solely responsible.
One of the goals of SB 586 is to allow local entities within the Sacramento-San Joaquin Valley to permit development despite the area being within a flood hazard zone that lacks 200-year flood protection and a flood prevention project that, presumably without this bill, is not making “adequate progress” towards achieving 200-year flood protection. By substituting the deadline to achieve the urban level of flood protection with the existence of an USACE project, development that would not otherwise be built could proceed and could extend the state’s liability for flood damages in those areas. This imposes risk on all California taxpayers for the flooding that occurs within the Sacramento-San Joaquin Valley. AB 838 and SB 901, when providing the extensions for Mossdale Tract and West Sacramento, respectively, also included provisions that reduced the state’s exposure to damages that might arise from cities or counties unreasonably approving any new development in those areas. Accordingly, the Committee may wish to consider amending the bill to reduce the state’s exposure to damages that might arise from cities or counties unreasonably approving any new development in Mossdale Tract or West Sacramento between 2025 and when urban level of flood protection is achieved. (See Amendment 2).
To be continued. According to the author, additional amendments are planned to address various concerns brought up by committee staff and stakeholders, including the implications of relying on an uncompleted or paused USACE project as a measure of adequate flood protection or as a “go-ahead” to approve development. The committee may wish to require the author to continue to work with committee staff on these issues and reserves the right to bring the bill back before the committee if it feels that the issues and concerns in this analysis have not been adequately addressed.
Double Referred to Senate Governance & Finance Committee. Elements of this bill under the jurisdiction of the Senate Governance & Finance Committee are included here for context and completeness only and will be discussed before that Committee.
Related legislation.
SB 23 (Caballero) requires the California Department of Fish and Wildlife, for flood risk reduction projects and water supply projects that are subject to lake and streambed alterations agreements, to issue the final agreement within 180 days if the project proponent meets certain conditions. SB 23 would also require the State Water Resources Control Board (SWRCB) and regional water quality control boards, when issuing water quality certifications for flood risk reduction projects and water supply projects, to adhere to specified procedures in reviewing the application. The bill would require SWRCB, by January 1, 2025, to review and adopt general water quality certifications for general nationwide permits issued by USACE within the state for discharge of dredge and fill material in connection with water supply projects and flood risk reduction projects. SB 23 is pending before this committee.
Prior legislation.
SB 901 (Pan, Chapter 708, Statutes of 2022) authorizes state participation in the City of West Sacramento Flood Risk Reduction Project, sets boundaries for Reclamation District 900, and extends the deadline for the City of West Sacramento to achieve the urban level of flood protection from 2025 to 2030.
AB 921 (McCarty, 2022) would have extended the deadline for the City of West Sacramento to achieve the urban level of flood protection from 2025 to 2030, revised and updated the state authorization for the West Sacramento Flood Risk Reduction Project, and consolidated entities responsible for levee maintenance. AB 921 was held in this committee.
AB 838 (Eggman, Chapter 208, Statutes of 2020) extends the date for the Mossdale Tract to reach an urban level of flood protection from 2025 to 2028.
AB 2108 (Eggman, 2014) would have made a number of changes to the statutes relating to flood management in the Sacramento-San Joaquin Valley, including, among others, allowing the CVFPB to determine that preconstruction planning or design activities of a flood protection system by a LFMA are sufficient to constitute adequate progress, amending the definition of “adequate progress” by adding that critical features of the flood protection system are being planned or designed and certain determinations made by the CVFPB have not expired, and allows discretionary permits be issued if it would not result in more than a 50% increase in building occupancy. AB 2108 was held in this committee.
SUGGESTED AMENDMENTS
AMENDMENT 1
Limit the bill’s application to West Sacramento and Mossdale Tract.
AMENDMENT 2
Limit the State’s liability, similar to language in AB 838 and SB 901.
SUPPORT
San Joaquin Area Flood Control Agency (sponsor)
California Building Industry Association
California Central Valley Flood Control Association
West Sacramento; City of
OPPOSITION
None Received
-- END --
Discussed in Hearing
Assembly Floor
Assembly Standing Committee on Water, Parks, and Wildlife
Senate Floor
Senate Standing Committee on Governance and Finance
Senate Standing Committee on Natural Resources and Water
Bill Author