AB 1191: California Renewables Portfolio Standard Program: hydroelectric generation.
- Session Year: 2025-2026
- House: Assembly
- Latest Version Date: 2025-02-21
Current Status:
Failed
(2026-02-02: From committee: Filed with the Chief Clerk pursuant to Joint Rule 56.)
Introduced
In Committee
Awaiting First Chamber Vote
Passed First Chamber
In Committee
Awaiting Second Chamber Vote
Passed Second Chamber
Enacted
Existing law establishes the California Renewables Portfolio Standard Program, which requires the Public Utilities Commission to implement annual procurement targets for the procurement of eligible renewable energy resources, as defined, for all retail sellers, as defined, and requires local publicly owned electric utilities to adopt and implement renewable energy resources procurement plans to achieve the targets and goals of the program. Under existing law, eligible renewable energy resources include small hydroelectric generation facilities of 30 megawatts or less that meet specified criteria.
This bill would revise the definition of an eligible renewable energy resource for the purposes of the California Renewables Portfolio Standard Program to include all hydroelectric generating facilities and would make conforming changes.
(a)For the purposes of this section, the following terms mean the following: definitions apply:
(1)Local publicly owned electric utility has the same meaning as defined in Section 224.3 of the Public Utilities Code.
(2)Retail seller has the same meaning as set forth in subdivision (j) of Section 399.12 of the Public Utilities Code.
(3)Transportation electrification has the same meaning as set forth in Section 237.5 of the Public Utilities Code.
(b)The state board shall identify and adopt appropriate policies, rules, or regulations to remove regulatory disincentives preventing retail sellers and local publicly owned electric utilities from facilitating the achievement of greenhouse gas emission reductions in other sectors through increased investments in transportation electrification. Policies to be considered shall include, but are not limited to, an allocation of greenhouse gas emissions allowances to retail sellers and local publicly owned electric utilities, or other regulatory mechanisms, to account for increased greenhouse gas emissions in the electric electricity sector from transportation electrification.
SEC. 2.Section 399.12 of the Public Utilities Code is amended to read:399.12.For purposes of this article, the following terms have the following meanings:
(a)Conduit hydroelectric facility means a facility for the generation of electricity that uses only the hydroelectric potential of an existing pipe, ditch, flume, siphon, tunnel, canal, or other manmade conduit that is operated to distribute water for a beneficial use.(b)(a)Balancing authority means the responsible entity that integrates resource plans ahead of time, maintains load-interchange generation balance within a balancing authority area, and supports interconnection frequency in real time.
(c)(b)Balancing authority area means the collection of generation, transmission, and loads within the metered boundaries of the area within which the balancing authority maintains the electrical load-resource balance.
(d)(c)California balancing authority is means a balancing authority with control over a balancing authority area primarily located in this state and operating for retail sellers and local publicly owned electric utilities subject to the requirements of this article and includes the Independent System Operator (ISO) and a local publicly owned electric utility operating a transmission grid that is not under the operational control of the ISO. A California balancing authority is responsible for the operation of the transmission grid within its metered boundaries boundaries, which is not limited by the political boundaries of the State of California.
(e)(d)(1)Eligible renewable energy resource means an a hydroelectric generating facility or any electrical generating facility that meets the definition of a renewable electrical generation facility in Section 25741 of the Public Resources Code, subject to the following: Code.
(1)(A)An existing small hydroelectric generation facility of 30 megawatts or less shall be eligible only if a retail seller or local publicly owned electric utility procured the electricity from the facility as of December 31, 2005. A new hydroelectric facility that commences generation of electricity after December 31, 2005, is not an eligible renewable energy resource if it will cause an adverse impact on instream beneficial uses or cause a change in the volume or timing of streamflow.(B)Notwithstanding subparagraph (A), a conduit hydroelectric facility of 30 megawatts or less that commenced operation before January 1, 2006, is an eligible renewable energy resource. A conduit hydroelectric facility of 30 megawatts or less that commences operation after December 31, 2005, is an eligible renewable energy resource so long as it does not cause an adverse impact on instream beneficial uses or cause a change in the volume or timing of streamflow.(C)A facility approved by the governing board of a local publicly owned electric utility prior to June 1, 2010, for procurement to satisfy renewable energy procurement obligations adopted pursuant to former Section 387, shall be certified as an eligible renewable energy resource by the Energy Commission pursuant to this article, if the facility is a renewable electrical generation facility as defined in Section 25741 of the Public Resources Code.(D)(i)A small hydroelectric generation unit with a nameplate capacity not exceeding 40 megawatts that is operated as part of a water supply or conveyance system is an eligible renewable energy resource only for the retail seller or local publicly owned electric utility that procured the electricity from the unit as of December 31, 2005. No unit shall be eligible pursuant to this subparagraph if an application for certification is submitted to the Energy Commission after January 1, 2013. Only one retail seller or local publicly owned electric utility shall be deemed to have procured electricity from a given unit as of December 31, 2005.(ii)Notwithstanding clause (i), a local publicly owned electric utility that meets the criteria of subdivision (j) of Section 399.30 may sell to another local publicly owned electric utility electricity from small hydroelectric generation units that qualify as eligible renewable energy resources under clause (i), and that electricity may be used by the local publicly owned electric utility that purchased the electricity to meet its renewables portfolio standard procurement requirements. The total of all those sales from the utility shall be no greater than 100,000 megawatthours of electricity.(iii)The amendments made to this subdivision by the act adding this subparagraph are intended to clarify existing law and apply from December 10, 2011.(2)(A)A facility engaged in the combustion of municipal solid waste shall not be considered an eligible renewable energy resource.
(B)Subparagraph (A) does not apply to generation before January 1, 2017, from a facility located in the County of Stanislaus County that was operational prior to before September 26, 1996.
(f)(e)Procure means to acquire through ownership or contract.
(g)(f)Procurement entity means any person or corporation authorized by the commission to enter into contracts to procure eligible renewable energy resources on behalf of customers of a retail seller pursuant to subdivision (f) of Section 399.13.
(h)(g)(1)Renewable energy credit means a certificate of proof associated with the generation of electricity from an eligible renewable energy resource, issued through the accounting system established by the Energy Commission pursuant to Section 399.25, that one unit of electricity was generated and delivered by an eligible renewable energy resource.
(2)Renewable energy credit includes all renewable and environmental attributes associated with the production of electricity from the eligible renewable energy resource, except for an emissions reduction credit issued pursuant to Section 40709 of the Health and Safety Code and any credits or payments associated with the reduction of solid waste and treatment benefits created by the utilization usage of biomass or biogas fuels.
(3)(A)Electricity generated by an eligible renewable energy resource attributable to the use of nonrenewable fuels, beyond a de minimis quantity used to generate electricity in the same process through which the facility converts renewable fuel to electricity, shall not result in the creation of a renewable energy credit. The Energy Commission shall set the de minimis quantity of nonrenewable fuels for each renewable energy technology at a level of no more than 2 percent of the total quantity of fuel used by the technology to generate electricity. The Energy Commission may adjust the de minimis quantity for an individual facility, up to a maximum of 5 percent, if it finds that all of the following conditions are met:
(i)The facility demonstrates that the higher quantity of nonrenewable fuel will lead to an increase in generation from the eligible renewable energy facility that is significantly greater than generation from the nonrenewable fuel alone.
(ii)The facility demonstrates that the higher quantity of nonrenewable fuels will reduce the variability of its electrical output in a manner that results in net environmental benefits to the state.
(iii)The higher quantity of nonrenewable fuel is limited to either natural gas or hydrogen derived by reformation of a fossil fuel.
(B)Electricity generated by a small hydroelectric generation facility shall not result in the creation of a renewable energy credit unless the facility meets the requirements of subparagraph (A) or (D) of paragraph (1) of subdivision (e).(C)Electricity generated by a conduit hydroelectric generation facility shall not result in the creation of a renewable energy credit unless the facility meets the requirements of subparagraph (B) of paragraph (1) of subdivision (e).(D)(B)Electricity generated by a facility engaged in the combustion of municipal solid waste shall not result in the creation of a renewable energy credit. This subparagraph does not apply to renewable energy credits that were generated before January 1, 2017, by a facility engaged in the combustion of municipal solid waste located in the County of Stanislaus County that was operational prior to before September 26, 1996, and sold pursuant to contacts entered into before January 1, 2017.
(i)(h)Renewables portfolio standard means the specified percentage of electricity generated by eligible renewable energy resources that a retail seller or a local publicly owned electric utility is required to procure pursuant to this article.
(j)(i)Retail seller means an entity engaged in the retail sale of electricity to end-use customers located within the state, including any of the following:
(1)An electrical corporation, as defined in Section 218.
(2)A community choice aggregator. A community choice aggregator shall participate in the renewables portfolio standard program subject to the same terms and conditions applicable to an electrical corporation.
(3)An electric service provider, as defined in Section 218.3. The electric service provider shall be subject to the same terms and conditions applicable to an electrical corporation pursuant to this article. This paragraph does not impair a contract entered into between an electric service provider and a retail customer prior to before the suspension of direct access by the commission pursuant to Section 80110 of the Water Code.
(4)Retail seller does not include any of the following:
(A)A corporation or person employing cogeneration technology or producing electricity consistent with subdivision (b) of Section 218.
(B)The Department of Water Resources acting in its capacity pursuant to Division 27 (commencing with Section 80000) of the Water Code.
(C)A local publicly owned electric utility.
(k)(j)WECC means the Western Electricity Coordinating Council of the North American Electric Reliability Corporation, or a successor to the corporation.
SEC. 3.Section 399.12.5 of the Public Utilities Code is repealed.399.12.5.(a)Notwithstanding subdivision (e) of Section 399.12, a small hydroelectric generation facility that satisfies the criteria for an eligible renewable energy resource pursuant to Section 399.12 shall not lose its eligibility if efficiency improvements undertaken after January 1, 2008, cause the generating capacity of the facility to exceed 30 megawatts, and the efficiency improvements do not result in an adverse impact on instream beneficial uses or cause a change in the volume or timing of streamflow. The entire generating capacity of the facility shall be eligible.(b)Notwithstanding subdivision (e) of Section 399.12, the incremental increase in the amount of electricity generated from a hydroelectric generation facility as a result of efficiency improvements at the facility, is electricity from an eligible renewable energy resource, without regard to the electrical output of the facility, if all of the following conditions are met:(1)The incremental increase is the result of efficiency improvements from a retrofit that do not result in an adverse impact on instream beneficial uses or cause a change in the volume or timing of streamflow.(2)The hydroelectric generation facility meets one of the following certification mechanisms:(A)The hydroelectric generation facility has, within the immediately preceding 15 years, received certification from the State Water Resources Control Board pursuant to Section 401 of the federal Clean Water Act (33 U.S.C. Sec. 1341), or has received certification from a regional board to which the state board has delegated authority to issue certification, unless the facility is not subject to certification because there is no potential for discharge into waters of the United States.(B)If the hydroelectric facility is not located in California, the certification pursuant to Section 401 of the federal Clean Water Act (33 U.S.C. Sec. 1341) may be received from the applicable state board or agency or from a regional board to which the state board has delegated authority to issue the certification.(C)If the hydroelectric generation facility is the Rock Creek Powerhouse, Federal Energy Regulatory Commission Project Number 1962, the efficiency improvements have received any necessary incremental certification from the State Water Resources Control Board.(3)The hydroelectric generation facility is owned by a retail seller or a local publicly owned electric utility, was operational prior to January 1, 2007, the efficiency improvements are initiated on or after January 1, 2008, the efficiency improvements are not the result of routine maintenance activities, as determined by the Energy Commission, and the efficiency improvements were not included in any resource plan sponsored by the facility owner prior to January 1, 2008.(4)All of the incremental increase in electricity resulting from the efficiency improvements are demonstrated to result from a long-term financial commitment by the retail seller or local publicly owned electric utility. For purposes of this paragraph, long-term financial commitment means either new ownership investment in the facility by the retail seller or local publicly owned electric utility or a new or renewed contract with a term of 10 or more years, which includes procurement of the incremental generation.(c)The incremental increase in the amount of electricity generated from a hydroelectric generation facility as a result of efficiency improvements at the facility are not eligible for supplemental energy payments pursuant to the Renewable Energy Resources Program (Chapter 8.6 (commencing with Section 25740) of Division 15 of the Public Resources Code), or a successor program.(d)Notwithstanding subdivision (e) of Section 399.12 and subdivisions (a) and (b), a hydroelectric generation facility that is an eligible renewable energy resource pursuant to this article as of January 1, 2010, shall not lose its eligibility if the facility causes a change in the volume or timing of streamflow required by license conditions approved pursuant to the Federal Power Act (Chapter 12 (commencing with Section 791a) of Title 16 of the United States Code) on or after January 1, 2010.SEC. 4.Section 399.20.5 of the Public Utilities Code is repealed.399.20.5.(a)Notwithstanding paragraph (1) of subdivision (b) and paragraph (2) of subdivision (j) of Section 399.20, a conduit hydroelectric facility with an effective capacity of up to four megawatts that otherwise meets the requirements of Section 399.20 shall be eligible for the standard contract or tariff established pursuant to subdivision (c) of Section 399.20 if the electric generation facility meets all the following additional requirements:(1)It was operational as of January 1, 1990.(2)It delivers no more than three megawatts to the grid at any time.(3)It complies with the electrical corporations Electric Rule 21 tariff or other distribution access tariff.(b)A facility meeting the requirements of subdivision (a) shall receive payment pursuant to paragraph (1) of subdivision (d) of Section 399.20, provided that no payment shall be made for any electricity delivered to the grid in excess of three megawatts at any time.SEC. 5.Section 399.25 of the Public Utilities Code is amended to read:399.25.The Energy Commission shall do all of the following:
(a)Certify eligible renewable energy resources that it determines meet the criteria described in subdivision (e) (d) of Section 399.12.
(b)Design and implement an accounting system to verify compliance with the renewables portfolio standard by retail sellers and local publicly owned electric utilities, to ensure that electricity generated by an eligible renewable energy resource is counted only once for the purpose of meeting the renewables portfolio standard of this state or any other state, to certify renewable energy credits produced by eligible renewable energy resources, and to verify retail product claims in this state or any other state. In establishing the guidelines governing this accounting system, the Energy Commission shall collect data from electricity market participants that it deems necessary to verify compliance of retail sellers and local publicly owned electric utilities, in accordance with the requirements of this article and the California Public Records Act (Division 10 (commencing with Section 7920.000) of Title 1 of the Government Code). In seeking data from electrical corporations, the Energy Commission shall request data from the commission. The commission shall collect data from electrical corporations and remit the data to the Energy Commission within 90 days of the request.
(c)Establish a system for tracking and verifying renewable energy credits that, through the use of independently audited data, verifies the generation of electricity associated with each renewable energy credit and protects against multiple counting of the same renewable energy credit. The Energy Commission shall consult with other western states and with the WECC in the development of this system.
(d)Certify, for purposes of compliance with the renewables portfolio standard requirements by a retail seller, the eligibility of renewable energy credits associated with eligible renewable energy resources procured by a local publicly owned electric utility, if the Energy Commission determines that all of the conditions of Section 399.31 have been met.
SEC. 6.Section 399.30 of the Public Utilities Code is amended to read:399.30.(a)(1)To fulfill unmet long-term generation resource needs, each local publicly owned electric utility shall adopt and implement a renewable energy resources procurement plan that requires the utility to procure a minimum quantity of electricity products from eligible renewable energy resources, including renewable energy credits, as a specified percentage of total kilowatthours sold to the utilitys retail end-use customers, each compliance period, to achieve the targets of subdivision (c).
(2)Beginning January 1, 2019, a local publicly owned electric utility subject to Section 9621 shall incorporate the renewable energy resources procurement plan required by this section as part of a broader integrated resource plan developed and adopted pursuant to Section 9621.
(b)The governing board shall implement procurement targets for a local publicly owned electric utility that require the utility to procure a minimum quantity of eligible renewable energy resources for each of the following compliance periods:
(1)January 1, 2011, to December 31, 2013, inclusive.
(2)January 1, 2014, to December 31, 2016, inclusive.
(3)January 1, 2017, to December 31, 2020, inclusive.
(4)January 1, 2021, to December 31, 2024, inclusive.
(5)January 1, 2025, to December 31, 2027, inclusive.
(6)January 1, 2028, to December 31, 2030, inclusive.
(c)The governing board of a local publicly owned electric utility shall ensure all of the following:
(1)The quantities of eligible renewable energy resources to be procured for the compliance period from January 1, 2011, to December 31, 2013, inclusive, are equal to an average of 20 percent of retail sales.
(2)The quantities of eligible renewable energy resources to be procured for all other compliance periods reflect reasonable progress in each of the intervening years sufficient to ensure that the procurement of electricity products from eligible renewable energy resources achieves 25 percent of retail sales by December 31, 2016, 33 percent by December 31, 2020, 44 percent by December 31, 2024, 52 percent by December 31, 2027, and 60 percent by December 31, 2030. The Energy Commission shall establish appropriate multiyear compliance periods for all subsequent years that require the local publicly owned electric utility to procure not less than 60 percent of retail sales of electricity products from eligible renewable energy resources.
(3)A local publicly owned electric utility shall adopt procurement requirements consistent with Section 399.16.
(4)Beginning January 1, 2014, in calculating the procurement requirements under this article, a local publicly owned electric utility may exclude from its total retail sales the kilowatthours generated by an eligible renewable energy resource that is credited to a participating customer pursuant to a voluntary green pricing or shared renewable generation program. Any exclusion shall be limited to electricity products that do not meet the portfolio content criteria set forth in paragraph (2) or (3) of subdivision (b) of Section 399.16. Any renewable energy credits associated with electricity credited to a participating customer shall not be used for compliance with procurement requirements under this article, shall be retired on behalf of the participating customer, and shall not be further sold, transferred, or otherwise monetized for any purpose. To the extent possible for generation that is excluded from retail sales under this subdivision, a local publicly owned electric utility shall seek to procure those eligible renewable energy resources that are located in reasonable proximity to program participants.
(d)(1)The governing board of a local publicly owned electric utility shall adopt procurement requirements consistent with subparagraph (B) of paragraph (5) of subdivision (a) of, and paragraph (1) of subdivision (b) of, Section 399.13.
(2)The governing board of a local publicly owned electric utility may adopt the following measures:
(A)Conditions that allow for delaying timely compliance consistent with subdivision (b) of Section 399.15.
(B)Cost limitations for procurement expenditures consistent with subdivision (c) of Section 399.15.
(e)The governing board of the local publicly owned electric utility shall adopt a program for the enforcement of this article. The program shall be adopted at a publicly noticed meeting offering all interested parties an opportunity to comment. Not less than 30 days notice shall be given to the public of any meeting held for purposes of adopting the program. Not less than 10 days notice shall be given to the public before any meeting is held to make a substantive change to the program.
(f)Each local publicly owned electric utility shall annually post notice, in accordance with the Ralph M. Brown Act (Chapter 9 (commencing with Section 54950) of Part 1 of Division 2 of Title 5 of the Government Code), whenever its governing body will deliberate in public on its renewable energy resources procurement plan.
(g)A public utility district that receives all of its electricity pursuant to a preference right adopted and authorized by the United States Congress pursuant to Section 4 of the Trinity River Division Act of August 12, 1955 (Public Law 84-386), shall be in compliance with the renewable energy procurement requirements of this article.
(h)For a local publicly owned electric utility that was in existence on or before January 1, 2009, that provides retail electric service to 15,000 or fewer customer accounts in California, and is interconnected to a balancing authority located outside this state but within the WECC, an eligible renewable energy resource includes a facility that is located outside California that is connected to the WECC transmission system, if all of the following conditions are met:
(1)The electricity generated by the facility is procured by the local publicly owned electric utility, is delivered to the balancing authority area in which the local publicly owned electric utility is located, and is not used to fulfill renewable energy procurement requirements of other states.
(2)The local publicly owned electric utility participates in, and complies with, the accounting system administered by the Energy Commission pursuant to this article.
(3)The Energy Commission verifies that the electricity generated by the facility is eligible to meet the renewables portfolio standard procurement requirements.
(i)Notwithstanding subdivision (a), for a local publicly owned electric utility that is a joint powers authority of districts established pursuant to state law on or before January 1, 2005, that furnishes electric services other than to residential customers, and is formed pursuant to the Irrigation District Law (Division 11 (commencing with Section 20500) of the Water Code), the percentage of total kilowatthours sold to the districts retail end-use customers, upon which the renewables portfolio standard procurement requirements in subdivision (b) are calculated, shall be based on the authoritys average retail sales over the previous seven years. If the authority has not furnished electric service for seven years, then the calculation shall be based on average retail sales over the number of completed years during which the authority has provided electric service.
(j)A local publicly owned electric utility in a city and county that only receives greater than 67 percent of its electricity sources from hydroelectric generation located within the state that it owns and operates, and that does not meet the definition of a renewable electrical generation facility pursuant to Section 25741 of the Public Resources Code, shall be required to procure eligible renewable energy resources, including renewable energy credits, to meet only the electricity demands unsatisfied by its hydroelectric generation in any given year, in order to satisfy its renewable energy procurement requirements.(k)(1)For purposes of this subdivision, large hydroelectric generation means electricity generated from an existing hydroelectric facility located within the state that does not qualify as an eligible renewable energy resource and, as of January 1, 2018, was owned by a local publicly owned electric utility, the federal government as a part of the federal Central Valley Project, or a joint powers agency formed and created pursuant to the Joint Exercise of Powers Act (Chapter 5 (commencing with Section 6500) of Division 7 of Title 1 of the Government Code).(2)If, during a year within a compliance period set forth in subdivision (b), a local publicly owned electric utility receives more than 40 percent of its retail sales from large hydroelectric generation under an ownership agreement or contract in effect as of January 1, 2018, it is not required to procure eligible renewable energy resources that exceed the lesser of the following for that year:(A)The portion of the local publicly owned electric utilitys retail sales unsatisfied by the local publicly owned electric utilitys large hydroelectric generation.(B)The soft target adopted by the Energy Commission for the intervening years of the relevant compliance period.(3)An extension or renewal of a procurement agreement shall not be eligible to count towards the determination that the local publicly owned electric utility receives more than 40 percent of its retail sales from large hydroelectric generation in any year. This paragraph shall not apply to any agreement in effect on January 1, 2015, between a local publicly owned electric utility and the Western Area Power Administration or federal government as part of the federal Central Valley Project.(4)The Energy Commission shall adjust the total quantities of eligible renewable energy resources to be procured by a local publicly owned electric utility for a compliance period to reflect any reductions required pursuant to paragraph (2).(5)This subdivision does not modify the compliance obligation of a local publicly owned electric utility to satisfy the requirements of subdivision (c) of Section 399.16.(l)(j)(1)(A)For purposes of this subdivision, unavoidable long-term contracts and ownership agreements means commitments for electricity from a coal-fired powerplant, located outside the state, originally entered into by a local publicly owned electric utility before June 1, 2010, that is not subsequently modified to result in an extension of the duration of the agreement or result in an increase in total quantities of energy delivered during any compliance period set forth in subdivision (b).
(B)The governing board of a local publicly owned electric utility shall demonstrate in its renewable energy resources procurement plan required pursuant to subdivision (a) that any cancellation or divestment of the commitment would result in significant economic harm to its retail customers that cannot be substantially mitigated through resale, transfer to another entity, early closure of the facility, or other feasible measures.
(2)For the compliance period set forth in paragraph (4) of subdivision (b), a local publicly owned electric utility meeting the requirement of subparagraph (B) of paragraph (1) may adjust its renewable energy procurement targets to ensure that the procurement of additional electricity from eligible renewable energy resources, in combination with the procurement of electricity from unavoidable long-term contracts and ownership agreements, does not exceed the total retail sales of the local publicly owned electric utility during that compliance period. The local publicly owned electric utility may limit its procurement of eligible renewable energy resources for that compliance period to no less than an average of 33 percent of its retail sales.
(3)The Energy Commission shall approve any reductions in procurement targets proposed by a local publicly owned electric utility if it determines that the requirements of this subdivision are satisfied.
(m)(k)A local publicly owned electric utility shall retain discretion over both of the following:
(1)The mix of eligible renewable energy resources procured by the utility and those additional generation resources procured by the utility for purposes of ensuring resource adequacy and reliability.
(2)The reasonable costs incurred by the utility for eligible renewable energy resources owned by the utility.
(n)(l)The Energy Commission shall adopt regulations specifying procedures for enforcement of this article. The regulations shall include a public process under which the Energy Commission may issue a notice of violation and correction against a local publicly owned electric utility for failure to comply with this article, and for referral of violations to the State Air Resources Board for penalties pursuant to subdivision (o). (m).
(o)(m)(1)Upon a determination by the Energy Commission that a local publicly owned electric utility has failed to comply with this article, the Energy Commission shall refer the failure to comply with this article to the State Air Resources Board, which may impose penalties to enforce this article consistent with Part 6 (commencing with Section 38580) of Division 25.5 of the Health and Safety Code. Any penalties imposed shall be comparable to those adopted by the commission for noncompliance by retail sellers.
(2)Any penalties collected by the State Air Resources Board pursuant to this article shall be deposited in the Air Pollution Control Fund and, upon appropriation by the Legislature, shall be expended for reducing emissions of air pollution or greenhouse gases within the same geographic area as the local publicly owned electric utility.
|
Date
|
Status
|
|---|---|
| Feb 2, 2026 | From committee: Filed with the Chief Clerk pursuant to Joint Rule 56. |
| Jan 31, 2026 | Died pursuant to Art. IV, Sec. 10(c) of the Constitution. |
| Apr 2, 2025 | In committee: Set, first hearing. Failed passage. Reconsideration granted. |
| Mar 10, 2025 | Referred to Coms. on U. & E. and NAT. RES. |
| Feb 24, 2025 | Read first time. |
| Feb 22, 2025 | From printer. May be heard in committee March 24. |
| Feb 21, 2025 | Introduced. To print. |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| American Clean Power California | ** Against | |
| California Biomass Energy Alliance | ** Against | |
| California Energy Storage Alliance | ** Against | |
| California State Association Of Electrical Workers | ** Against | |
| California Wind Energy Association | ** Against | |
| Coalition of California Utility Employees | ** Against | |
| Independent Energy Producers Association | ** Against | |
| Kings River Conservation District | ** Support | |
| Kings River Water Association | ** Support | |
| Large-Scale Solar Association | ** Against | |
| Modesto Irrigation District | ** Support | |
| Sierra Club | ** Against | |
| The Utility Reform Network | ** Against | |
| Turlock Irrigation District | ** Support |
Date of Hearing: April 2, 2025
ASSEMBLY COMMITTEE ON UTILITIES AND ENERGY
Cottie Petrie-Norris, Chair
ABPCA Bill Id:AB 1191 (
Author:Tangipa) – As Introduced Ver:February 21, 2025
SUBJECT: California Renewables Portfolio Standard Program: hydroelectric generation
SUMMARY: Includes hydroelectric generation resources greater than 30 megawatts (MWs), i.e., “large hydro,” as eligible renewable resources in California’s Renewables Portfolio Standard (RPS). Deletes current allowances to RPS eligibility for specified, legacy large hydro or upgraded small hydro resources.
EXISTING LAW:
- Establishes the California RPS Program which requires investor-owned utilities (IOUs), publicly owned utilities (POUs), community choice aggregators (CCAs), and energy service providers (ESPs) to increase purchases of renewable energy such that they each procure a minimum quantity of electricity products from eligible renewable energy resources, as defined, so that the total kilowatt hours (kWh) of those products sold to their retail end-use customers achieves 25% of retail sales by December 31, 2016, 33% by December 31, 2020, 44% by December 31, 2024, 52% by December 31, 2027, and 60% by December 31, 2030. (Public Utilities Code §§ 399.11, 399.13, 399.15, 399.30)
- Establishes the policy that all of the state's retail electricity be supplied with a mix of RPS-eligible and zero-carbon resources by December 31, 2045, for a total of 100% clean energy. Sets interim targets of 90% mix of RPS-eligible and zero-carbon resources by December 31, 2035 and 95% by December 31, 2040. Requires the California Public Utilities Commission (CPUC), in consultation with the California Energy Commission (CEC), California Air Resources Board (CARB), and all California balancing authorities, to issue a joint report to the Legislature by January 1, 2021, and every four years thereafter, reviewing and evaluating the 100% clean energy policy. (Public Utilities Code § 454.53)
- Defines a “renewable electrical generation facility” as one that, among other requirements, uses biomass, solar thermal, photovoltaic, wind, geothermal, fuel cells using renewable fuels, small hydroelectric generation of 30 megawatts (MW) or less, digester gas, municipal solid waste conversion, landfill gas, ocean wave, ocean thermal, or tidal current, and any additions or enhancements to the facility using that technology. (Public Resources Code § 25741)
- Defines eligible renewable energy resources to include small hydroelectric generation facilities of 30 MW or less and conduit hydroelectric facilities. (Public Utilities Code § 399.12)
- Permits small hydroelectric generation facilities that undertake efficiency improvements after January 1, 2008, that cause generating capacity to exceed 30 MWs to keep their RPS eligibility. It requires multiple conditions to be met including ensuring no adverse impacts to streams and streamflow, and permits the entire generating capacity of the facility to be RPS eligible. (Public Utilities Code § 399.12.5)
- Authorizes the governing board of a POU to adopt a cost limitation optional compliance to satisfy their RPS requirements. Requires the limitation to be set at a level that prevents disproportionate rate impacts. (Public Utilities Code § 399.30 (d)(B))
- Authorizes POUs that receive 67% or more of their electricity from large hydro that they own and operate to only meet their RPS compliance for “electricity demands unsatisfied by its hydroelectric generation in any given year.” (Public Utilities Code § 399.30(j))
- Reduces a POUs obligation to procure renewable resources for the subsequent year, if the POU receives more than 40% of its retail sales from large hydroelectric generation under specified circumstances. (Public Utilities Code § 399.30(k))
- Establishes the Private Energy Producers Act to promote the rapid development of new electric energy sources. Specifically defines “conventional power sources” as nuclear, fossil fuel combustion, or hydropower greater than 30 MWs, and limits program eligibility to facilities other than the conventional power sources. This Act predates the RPS. (Public Utilities Code §§ 2801-2829)
BACKGROUND:
California’s Resource Mix – According to the CEC, in 2023 total generation for California was 281,141 gigawatt-hours (GWh). Approximately 58% was due to zero-carbon generation (nuclear, hydroelectric, and renewables); while almost 12% was due solely to large hydro generation, as shown in Table 1 below. [1]
Table 1: 2023 Total System Electric Generation[2]
Fuel Type | In state Generation (GWh) | % in state | Total Imports (GWh) | Total Energy Mix (GWh) | % of Total Mix |
Coal | 257 | 0.12 | 4,724 | 4,981 | 1.77 |
Natural Gas | 94,192 | 43.68 | 8,582 | 102,774 | 36.56 |
Oil | 36 | 0.02 | 0 | 36 | 0.01 |
Other (Waste Heat / Petroleum Coke) | 206 | 0.10 | 0 | 206 | 0.07 |
Unspecified | - |
| 10,373 | 10,373 | 3.69 |
|
|
|
|
|
|
Biomass | 5,037 | 2.34 | 753 | 5,790 | 2.06 |
Geothermal | 10,999 | 5.10 | 2,569 | 13,567 | 4.83 |
Large Hydro | 27,066 | 12.55 | 5,821 | 32,886 | 11.70 |
Nuclear | 17,714 | 8.22 | 8,558 | 26,272 | 9.34 |
Small Hydro | 4,853 | 2.25 | 135 | 4,988 | 1.77 |
Solar | 41,344 | 19.17 | 6,525 | 47,869 | 17.03 |
Wind | 13,920 | 6.46 | 17,479 | 31,399 | 11.17 |
Total Zero Carbon | 120,933 | 56.09 | 41,840 | 162,771 | 57.90 |
|
|
|
|
|
|
California Total | 215,623 |
|
| 281,141 |
|
California’s Transition to 100% Clean Electricity – SB 100 (De León, Chapter 312, Statutes of 2018) established the state policy that renewable and zero-carbon resources should supply 100% of retail sales and electricity procured in the state by 2045.[3] This policy was recently updated under SB 1020 (Laird, Chapter 361, Statutes of 2022) which accelerated the requirement on state agencies to 100% by 2035, and established interim targets of 90% by 2035 and 95% by 2040 for all other entities. California has made progress in decarbonizing its energy sector, almost 58% of the state’s electricity mix arising from zero-carbon resources, as shown in Table 1. Solar energy has been the dominant source of California’s renewable energy resources. This growth is largely attributed by the cheaper prices of solar photovoltaics in recent years and California’s abundant solar capacity. However, as solar generation increases in California, the mismatch between when energy is generated and when it is needed poses challenges for grid stability and operation. As a result, California’s retail electric providers often need to purchase electricity to serve both RPS and reliability compliance (capacity) obligations.
RPS and Large Hydroelectric Generation – California’s RPS program, and other energy programs predating RPS,[4] have distinguished between smaller and larger hydroelectric facilities as those that are either at or below (small) or over (large) 30 MW – enough electricity to power nearly 30,000 households.[5] These distinctions have reflected state policy concerning natural river habitats which discourage more damming of rivers, as well as to encourage the development of new, alternative renewable energy projects. Curiously, RPS eligibility is tied to the scale of the generating station (30 MWs) and not the water capacity of the dam; these two dam features do not always scale together. For instance, the Monticello Dam built in 1957 in Napa County, has a reservoir (Lake Berryessa) with a capacity of approximately 1.6 million acre feet; [6] this is the seventh-largest man-made lake in California. Its hydroelectric plant, built in the 1980s, is 11.5 MWs.[7]
The recent passage of SB 100 (De León, Chapter 312, Statutes of 2018) and SB 1020 (Laird, 2022), as noted above, expands statewide clean energy planning beyond the RPS, to now include 100% of “zero-carbon resources” by 2045. Though undefined in statute, the expectation is that existing large hydroelectric facilities would count towards the 40% of “zero-carbon resources” that would be needed after the 60% RPS compliance target is met in 2030. For many POUs, especially irrigation districts and municipal utilities in Northern California, and Pacific Gas & Electric (PG&E) Company, much of this 40% obligation will likely be served by legacy hydro generation resources already in these utilities’ portfolios.
Where is all the Hydro? – As shown below in Figure 1,[8] hydroelectric facilities exist in nearly every county of the state, with the exception of counties along the Central Coast and some in Northern California. Many of these large hydro facilities were built during the federal dam-building boom almost a century ago,[9] and the California-specific boom in the 1950s-1960s as water and flood management.[10]
As shown in both Table 1 and Figure 1, the amount of large hydro in the state greatly eclipses the amount of small hydro, at 11.7% and 1.7% of the state’s energy, respectively.[11] Many utilities also contract for out-of-state hydro, largely from large dams in the Pacific Northwest.[12]
Figure 1: Hydroelectric Capacity by County, 20226
FISCAL EFFECT: Unknown. This bill is keyed fiscal and will be referred to the Assembly Committee on Appropriations for its review.
CONSUMER COST IMPACTS: Unclear and likely mixed. This bill will lower (or eradicate) future RPS obligations of some electric utilities, resulting in lower procurement costs and potential – but not guaranteed – lower bills for those utility customers. These same utilities may stand to make money, due to selling of excess Renewable Energy Credits (RECs), thus further lowering their costs. The cost impacts of this bill for utilities lacking large hydroelectric generation resources is less clear, as discussed below.
COMMENTS:
- Author’s Statement. According to the author, “By broadening eligibility in the Renewables Portfolio Standard, AB 1191 helps to stabilize our grid and cuts reliance on expensive alternatives This bill ensures affordable, sustainable power, advancing California’s 100% clean energy goal by 2045 while keeping electricity costs down for Californians.”
- Purpose of the RPS. The California RPS program began with a mandate to all retail sellers to provide 20% RPS-eligible generation by the end of 2017.[13] The initial RPS statute sought to establish a market for renewables, by financially incentivizing long term contracting of these (otherwise expensive) resources. This mandate sought market stimulation, creation of a local economy, and a modicum of environmental benefits. Policies to directly address the impacts of climate change came after the first RPS bills. It was not until 2011 that the RPS program incorporated greenhouse gas (GHG) reduction into its purpose.[14] Thus, the resource-specific qualification, or the “who’s-in-versus-who’s-out” nature of the RPS, has long been a point of division.
In the past 23 years since the original RPS mandate was adopted, not only has the retail landscape of renewable energy changed dramatically, but so has the conversation to urge action to address climate change and electric affordability. As noted above, the Legislature has modified the goals and details of the RPS program several times since the original enactment. The most recent major change occurred by SB 100 (, Chapter 312, Statutes of 2018), which set a new obligation of 60% of retail sales from RPS-eligible generation by 2030; a deadline now only 5 years away. SB 100 also offered an opportunity to think slightly beyond the RPS, by contemplating future resource procurement for the remaining 40% that was not solely from RPS-eligible resources.
- Progress in Meeting the RPS – IOUs and CCAs. As shown in Table 2 below, and in contrast with previous compliance periods, the three large IOUs no longer forecast having excess RPS procurement for the next three years. This change is primarily due to portfolio optimization efforts, some increasing load due to transportation electrification, and the impact of mandated procurement to meet other requirements.[15] IOUs expecting shortfalls may choose to meet compliance requirements through additional procurement or by applying excess RECs banked from procurement in prior years. Not all IOUs are facing the same degree of shortfall, however, and some may still choose to further optimize their portfolio through sales of renewable electricity and associated RECs.
Table 2: Retail Seller Compliance in Meeting RPS targets
Selected Retail Sellers | % RPS Procurement in 2023 (RPS Obligation: 44% by 2024) | % Gross RPS Procurement Forecasted to 2027[16] (RPS Obligation: 52% by 2027) |
Pacific Gas & Electric (PG&E)[17] | 41 % | 47% (aggregated; excluding impact of banked RECs – see footnote 16) |
Southern California Edison (SCE)17 | 41 % | |
San Diego Gas & Electric (SDG&E)17 | 48 % | |
Marin Clean Energy[18] | 68 % | 69% (aggregated; excluding impact of banked RECs – see footnote 16) |
Sonoma Clean Power18 | 54 % | |
Clean Power Alliance18 | 73 % |
Given that the IOUs have historically had significant excess RPS procurement to apply in later years, they did not conduct annual RPS procurement solicitations from 2016 to 2022.[19] In 2023, both SCE and PG&E held solicitations, but neither resulted in any contracts.[20]
- Progress in Meeting the RPS – POUs. For POUs, the most recently verified RPS compliance is for the 2017-2020 period. The statutory requirement for that period is 33% by the end of 2020. As noted in Table 3 below, many POUs did not meet the statutory RPS obligation through gross procurement,16 but rather alternative compliance paths.
Table 3: POU Compliance in Meeting RPS targets
Selected POUs | % RPS Procurement in 2020 (RPS Obligation: 33% by 2020) | Noted Exemptions |
Merced Irrigation District[21] | 17 % | *large hydro exemption[22] *cost limitation optional compliance measure |
Modesto Irrigation District[23] | 30 % | |
Turlock Irrigation District[24] | 30 % | |
Sacramento Municipal Utilities District[25] | 28 % |
The low POU percentages in Table 3 are by design. The RPS provides POUs additional compliance options, including: 1) allowing those with a large hydroelectric facility representing more than 40% of the utility’s portfolio to count that generation towards satisfying their RPS obligation, and 2) a cost limitation optional compliance pathway if their ratepayers are disproportionately affected by the RPS. As shown in Table 3, Merced Irrigation District elected to exercise the cost limitation optional compliance during the last reported compliance period. This optional compliance was utilized by five other POUs, including: Biggs, Redding, Victorville, Moreno Valley, and Cerritos.[26] Per CEC requirements, as long as the POU’s governing board adopts its own rules for the cost limitation by no later than the last day of the three year RPS compliance period and the utility follows its own self-imposed cost limitation rule, the CEC would deem that in compliance with RPS. The level of discretion and deference afforded to POUs to utilize this optional compliance mechanism allows a POU to adopt a rule that even just $1 of additional cost to comply with the RPS is a disproportionate impact to their ratepayers. As long as the utility followed its rules and they were adopted by the utility prior to the end of the compliance period, then the CEC would deem this approach to be in compliance with the RPS under existing statutory requirements.
- Purpose and Impact of Bill. Hydropower is a zero-carbon resource that, depending on weather conditions, can provide significant flexibility to grid operations.[27] This bill seeks to amend the RPS program to allow all hydroelectric resources, regardless of size, age, or location, to be eligible resources and receive associated RECs.[28] The author characterizes this as an affordability measure. The bill’s supporters – multiple Central Valley water and irrigation districts – note that the practical impact of the bill would be to render the remaining RPS compliance targets as met. A coalition of renewable developers writing in opposition agree, noting “adding large hydro to the RPS …would flood the market with cheap compliance credits… [and] immediately discourage the development of new renewable resources and the thousands of jobs they support.”[29] This RPS eligibility would not just extend to the existing 12.2 gigawatts (GWs) of existing, in-state large hydro owned and operated by the utilities, but also to any out-of-state large hydro sold into California’s market, as well as large hydro owned and operated by federal agencies and the Department of Water Resources.
The scale of this is quite significant. As shown in Table 1 above, nearly 12% of California’s 2023 resource mix was made up of large hydro. The statutory RPS obligation in 2024 was 44%, just 16% shy of the 60% by 2030 final RPS target. At a systems-level, injecting 12% of newly-eligible large hydro would have a chilling impact on the existing RPS procurement market.
- An Uncertain Path to Affordability. According to the CPUC, in 2023, the IOUs’ average cost of RPS-eligible energy was 10.0 ¢/kWh and the average cost of non-RPS energy was 8.3 ¢/kWh. Using this metric, IOUs’ renewable energy procurement likely added a premium of 1.7 ¢/kWh on average for the renewable energy procured to meet their RPS requirements.[30] One might speculate that if RPS compliance could instead be met with existing, large hydro resources these RPS premiums might be reduced or eliminated, leading to the lower costs the author is seeking from this measure. However, this “RPS-premium” is not universal. SDG&E, the CCAs, and even the ESPs saw lower RPS procurement costs relative to non-RPS procurement costs in 2023.[31] Most renewable contracts signed today are much cheaper than a decade ago; however, it is unclear to this committee how the cost of these cheaper renewables would compare to existing large hydro. At minimum, the sudden inclusion of over 26,000 GWhs of newly-eligible large hydro into the RPS market would likely give RPS-resource buyers more options, potentially driving down compliance costs.
For POUs, relief from RPS procurement requirements may be achieved without this bill, through the cost limitation optional mechanism. As noted above, that mechanism affords POUs significant deference in determining their RPS compliance is too cost burdensome and permitting waiving of their compliance requirements. Existing law also affords optional compliance pathways for certain legacy large hydro facilities owned by the POUs. This suggests it is not the relief from buying RPS resources, but the selling of excess large hydro RECs which may benefit the POUs most.
Utilities have an additional opportunity to drive down costs under this measure by selling their excess hydroelectricity, given that most of these assets are utility-owned and fully depreciated. The state’s RPS works by setting up a marketplace where renewable power plants gain RECs for producing renewable energy. The state runs a marketplace where RECs can be bought and sold, and requires electricity providers to meet a certain percentage standard by turning in enough RECs as compared to their total electricity generation. However, not every utility has large hydro in its portfolio; so not every customer stands to benefit for selling excess large hydro. Moreover, resources only have value when they’re generating, and for hydro that requires wet weather. The continued drought cycles in California can greatly impact hydro productivity, and may lead to hydro imports from the Pacific Northwest and Canada growing more competitive and garnering higher prices. As a result, any “cost-savings” may only be present for a subset of utilities.
- Winners and Losers. In fact, PG&E stands to benefit significantly from this measure, as it owns over 62 powerhouses located on watersheds in the Sierra Nevada, Cascade, and Coastal mountain ranges, totaling approximately 3.8 GWs.[32] The likely immediate impact would be a halting of PG&E’s RPS procurement solicitations, as was the case in 2016-2022 before the CPUC ordered the IOUs to sell their excess procurement. In aggregate, the IOUs sold approximately 25,000 GWhs of RPS energy from 2020-2023, and plan to sell additional RPS energy in 2024 and 2025 from authorized REC sales and approved optimization efforts.[33] This bill would likely expand the volume of those offerings. The actual customer impact of these sales is unknown to the committee.
The same is likely true for many POUs with significant volumes of large hydro in their portfolios, such as the supporters of this measure. However, all of these utilities – IOUs and POUs alike – will still need to procure enough RPS-eligible and zero-carbon resources to meet their 90%-by-2035 SB 100 compliance, even if this bill were to pass. Such an obligation is just 10 years away. For the POUs, if all their large hydro is considered RPS-eligible, the optional RPS-compliance pathways – as Merced exercised in 2020, shown in Table 3 – may no longer be available; and the large hydro that they could use to meet their 90% SB 100 obligation would instead be used for current RPS-compliance. This may inadvertently increase costs in the long-term. Given the varied portfolios, procurement strategies, and compliance exemptions available to the IOUs, POUs, CCAs, and ESPs subject to the RPS, the impact of this legislation will likely be unique depending on the entity. However, for the current RPS-eligible energy developers – solar, wind, biomass, geothermal, etc. – this bill is likely to significantly impact their businesses.
- Related Legislation.
AB 59 (Aguiar-Curry, 2025) makes permanent the authority of Reclamation District No. 108 (RD 108) to generate and sell hydroelectric power. Status: Assembly Floor – Third Reading.
AB 1095 (Papan, 2025) includes “waste heat energy” used for serving data center energy demand as an eligible resource under the RPS. Status: Referred to the Assembly Committees on Utilities and Energy and Natural Resources.
- Prior Legislation.
SB 1020 (Laird) establishes interim targets for the statewide 100% clean energy policy that all of the state's retail electricity be supplied with a mix of RPS-eligible and zero-carbon resources by December 31, 2045. Sets interim targets of 90% mix of RPS-eligible and zero-carbon resources by December 31, 2035 and 95% by December 31, 2040. Additionally requires state agencies to accelerate their 100% clean energy policy goal by 10 years. Status: Chapter 361, Statutes of 2022.
AB 1941 (Gallagher, 2020) would revise the definition of an RPS-eligible resource to include all hydroelectric generating facilities in operation as of January 1, 2021, and nuclear facilities, among other program revisions. Status: Died – Assembly Committee on Utilities and Energy.
ACA 17 (Gray, 2019) state the intent that hydroelectric generation be treated as the most environmentally protective and carbon-neutral electrical energy resource, and requires state programs to include hydroelectric generation. Status: Assembly – Died at Desk.
SB 386 (Caballero, 2019) limits the RPS obligations for Turlock and Modesto Districts to the electricity demands that are unsatisfied by the Don Pedro Hydroelectric (DPH) Project, and in exchange requires the districts to procure energy storage, as specified. Status: Died – Senate Committee on Energy, Utilities, and Communications.
AB 2809 (Patterson, 2018) largely similar to this bill; requires large hydroelectric facilities greater than 30MW to be eligible resources in the Renewables Portfolio Standard. Status: Died – Assembly Committee on Utilities and Energy.
SB 100 (De León) established the 100 Percent Clean Energy Act of 2017 which increases the RPS requirement from 50% by 2030 to 60%, and creates the policy of planning to meet all of the state's retail electricity supply with a mix of RPS-eligible and zero-carbon resources by December 31, 2045, for a total of 100% clean energy. Status: Chapter 312, Statutes of 2018.
SB 591 (Cannella) limits the Merced Irrigation District’s RPS obligation to the electricity demands that are unsatisfied by the New Exchequer Dam. Status: Chapter 520, Statutes of 2013.
- Double Referral. This bill is double-referred. Should it pass out of this committee, it will be referred to the Assembly Committee on Natural Resources for its review.
REGISTERED SUPPORT / OPPOSITION:
Support
Kings River Conservation District
Kings River Water Association
Modesto Irrigation District
Turlock Irrigation District
Oppose
American Clean Power- California
California Biomass Energy Alliance
California Energy Storage Alliance
California State Association of Electrical Workers
California Wind Energy Association
Coalition of California Utility Employees
Independent Energy Producers Association
Large-scale Solar Association
Sierra Club
The Utility Reform Network (TURN)
Analysis Prepared by: Laura Shybut / U. & E. / (916) 319-2083
CEC “2023 Total System Electric Generation;” website; accessed 03.25.2025; https://www.energy.ca.gov/data-reports/energy-almanac/california-electricity-data/2023-total-system-electric-generation#:~:text=In%202023%2C%20total%20generation%20for,percent%20in%202022.%20California's%20wide ↑
Reproduced from Citation #1 ↑
Public Utilities Code §454.53 ↑
The Private Energy Producers Act, Public Utilities Code §§ 2801-2829 ↑
National Renewable Energy Laboratory, “Small Hydropower Systems;” July 2001; DOE/GO-102001-1173; https://www.nrel.gov/docs/fy01osti/29065.pdf ↑
U.S. Bureau of Reclamation, “Berryessa Facts” January 28, 2014; https://web.archive.org/web/20140422141850/http://www.usbr.gov/mp/berryessa/facts.html ↑
Ibid. ↑
CEC dataset; updated July 7, 2023; https://cecgis-caenergy.opendata.arcgis.com/documents/8d0dc02feee048038a9bad3fd6e8487c/explore ↑
Lee, Gabriel. “Overview: The Big Dam Era.” Energy History Online. Yale University. 2023. https://energyhistory.yale.edu/the-big-dam-era/. ↑
UC Berkeley, “Number of California dams built per decade;” https://www.cnr.berkeley.edu/departments/espm/env-hist/projects/calif_dams/ca_dams_per_decade.htm ↑
Note differences in values between Figure 1 and Table 1 of total in state hydro MW are likely due to Figure 1 being utility-specific; i.e., not reporting hydro resources owned by the U.S. Bureau of Reclamation or the California Department of Water Resources, which are not utilities but do own significant hydro capacity in the state. ↑
U.S. Energy Information Administration, “California was the largest net electricity importer of any state in 2019;” December 7, 2020; https://www.eia.gov/todayinenergy/detail.php?id=46156 ↑
SB 1078 (Sher, Chapter 516, Statutes of 2002) ↑
SB X1-2 (Simitian, Chapter 1, Statutes of 2011) ↑
such as those added by SB 1020 (Laird, Chapter 361, Statues of 2022) and the Integrated Resource Planning (IRP) proceeding’s mid-term reliability procurement orders. ↑
Gross RPS percentages reflect physical deliveries only – does not include the usage of banked RECs. Many entities report exceeding state mandates through 2027 if allowable usage of banked RECs is counted. ↑
Pg. 11, Table 1; CPUC; 2024 California Renewables Portfolio Standard Annual Report; November 2024; https://www.cpuc.ca.gov/-/media/cpuc-website/industries-and-topics/documents/energy/rps/2024/2024-rps-annual-report-to-the-legislature.pdf ↑
Pg. 17, Table 5; CPUC; 2024 California Renewables Portfolio Standard Annual Report; November 2024; https://www.cpuc.ca.gov/-/media/cpuc-website/industries-and-topics/documents/energy/rps/2024/2024-rps-annual-report-to-the-legislature.pdf ↑
Pg. 12, Ibid. ↑
All three IOUs have procured for IRP mid-term reliability requirements during this time period, however, including for some RPS-eligible resources. ↑
CEC Final Report, RPS Verification Results, Merced Irrigation District CP3 2017-2020; January 2024; file:///C:/Users/shybutla/Downloads/TN254130_20240125T154820_Merced%20Irrigation%20District%20-%20Final%20RPS%20Verification%20Results%20Report%20for%20Comp.pdf ↑
20 CCR section 3204 (b)(6) of the RPS POU Regulations; The qualifying hydroelectric generation had the effect of reducing Merced Irrigation District’s 2017 soft target from 137,150 RECs to 16,828 RECs and the total Compliance Period 3 target from 615,028 RECs to 494,706 RECs. ↑
CEC Final Report, RPS Verification Results, Modesto Irrigation District CP3 2017-2020; August 2024; file:///C:/Users/shybutla/Downloads/TN258600_20240820T162738_Modesto%20Irrigation%20District%20-%20Final%20RPS%20Verification%20Results%20Report%20for%20Com%20(1).pdf ↑
CEC Final Report, RPS Verification Results, Turlock Irrigation District CP3 2017-2020; August 2024; file:///C:/Users/shybutla/Downloads/TN258591_20240820T162754_Turlock%20Irrigation%20District%20-%20Final%20RPS%20Verification%20Results%20Report%20for%20Com.pdf ↑
CEC Final Report, RPS Verification Results, SMUD CP3 2017-2020; January 2024; file:///C:/Users/shybutla/Downloads/TN254133_20240125T154825_Sacramento%20Municipal%20Utility%20District%20-%20Final%20RPS%20Verification%20Results%20Repo.pdf ↑
https://www.energy.ca.gov/programs-and-topics/programs/renewables-portfolio-standard/renewables-portfolio-standard-6 ↑
Department of Energy, “Benefits of Hydropower;” https://www.energy.gov/eere/water/benefits-hydropower ↑
Locational constraints of the RPS program would still apply; i.e., Renewable generation facilities may be located anywhere within the WECC region and sell energy and /or RECs to a California retail seller of electricity to meet its RPS obligation, provided the facility meets all RPS-eligibility criteria established by the CEC. However, after 2020 less than 10% of RECs could be associated with Category 3, meaning no physical delivery of energy, just the REC itself was exchanged. ↑
Jackson, A., et al, March 26, 2025 AB 1191 Opposition Letter to Chair Petrie-Norris. ↑
Pg. 20, CPUC, 2024 Padilla Report; May 2024; https://www.cpuc.ca.gov/-/media/cpuc-website/divisions/office-of-governmental-affairs-division/reports/2024/2024-padilla-reportvfinal.pdf ↑
Pg. 25-29, 2024 Padilla Report; Ibid. ↑
CPUC Decision 24-05-004, Decision Denying Application, A.22-09-018, May 10, 2024; http://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M531/K375/531375060.PDF ↑
Pg. 28, 2024 California Renewables Portfolio Standard Annual Report; November 2024; https://www.cpuc.ca.gov/-/media/cpuc-website/industries-and-topics/documents/energy/rps/2024/2024-rps-annual-report-to-the-legislature.pdf ↑