AB 1772: Fish and wildlife: invasive species: invasive mussels.
- Session Year: 2025-2026
- House: Assembly
- Latest Version Date: 2026-06-25
Current Status:
In Progress
(2026-08-13: In committee: Held under submission.)
Introduced
In Committee
Awaiting First Chamber Vote
Passed First Chamber
In Committee
Awaiting Second Chamber Vote
Passed Second Chamber
Enacted
(1)Existing law, until January 1, 2030, generally prohibits a person from possessing, importing, shipping, or transporting in the state, or from placing, planting, or causing to be placed or planted in any water in the state, invasive mussels, and authorizes the Director of Fish and Wildlife or the directors designee to engage in various enforcement activities, including ordering the areas in conveyance that contain water be drained, dried, or decontaminated, as provided. Existing law requires a public or private agency that operates a water supply system to cooperate with the Department of Fish and Wildlife to implement measures to avoid infestation by invasive mussels and to control or eradicate any infestation that may occur in a water supply system. Existing law requires, if invasive mussels are detected, the operator of a water supply system to, in cooperation with the department, prepare and implement a plan to control or eradicate invasive mussels within the system, and eliminate or minimize any potential downstream transport of an invasive mussel. Existing law requires, on or before December 31, 2026, the department to review all approved plans and require all plans that do not specifically address all invasive mussel species known to be present in bodies of water in the state as of January 1, 2026, to be updated or revised appropriately to include all invasive mussel species, on or before September 30, 2027. Existing law requires every invasive mussel species to be addressed in a plan no later than 180 days from the date that the species is listed in a certain regulation. Existing law defines invasive mussel for these purposes as any nonnative detrimental mussel, as provided.
Under existing law, except as otherwise provided, any violation of the Fish and Game Code, or of any rule, regulation, or order made or adopted under the code, is a crime.
This bill would prohibit a conveyance from being launched until a specified drying period has completed, as provided. By expanding the scope of a crime, this bill would impose a state-mandated local program. The bill would require the department to require water supply system operators to update their plans to address all invasive mussel species present in the operators water system as of January 1, 2026, as provided. The bill would require a plan to address every invasive mussel species detected in a water supply system after January 1, 2026, no later than 180 days from the date the species is detected. The bill would require a plan to minimize or eliminate the spread of invasive mussels. The bill would revise the definition of invasive mussel to mean any nonnative biofouling mussel, as provided. By expanding the scope of a crime, the bill would impose a state-mandated local program.
This bill would enact a comprehensive inspection and decontamination program to be administered by the department under which the department would license inspection and decontamination stations with qualified inspectors to inspect and decontaminate conveyances for aquatic invasive species and issue certificates of compliance or notices of noncompliance, as prescribed by standards adopted by the department. The bill would establish a length of 2 years for those licenses and qualifications and would impose related application fees. The bill would impose requirements on various entities as part of the program, including requiring inspection and decontamination stations and waterbody managers to use a specified data sharing system for tracking the movement of conveyances, equipment, and other vectors among California waterbodies. Because a violation of these provisions would be a crime, the bill would impose a state-mandated local program.
(2)Existing law establishes a registration fee and a renewal fee for vessels, and imposes an additional fee, known as the invasive mussel infestation prevention fee, on a vessel required to pay the registration fee or renewal fee, as provided. Existing law requires the Division of Boating and Waterways to issue a vessel an invasive mussel infestation prevention sticker to the vessel owner upon payment of the invasive mussel infestation prevention fee. Existing law authorizes a vessel operator to be issued a citation for operating a vessel or a recreational vessel in nonmarine waters without a valid state-issued invasive mussel infestation prevention sticker.
This bill would enact similar provisions that would impose an additional invasive mussel infestation prevention fee of $20 per nonmotorized vessel every 2 years, as specified. The bill would require the Department of Fish and Wildlife to issue an invasive mussel infestation prevention sticker to be affixed to the nonmotorized vessel upon payment of the invasive mussel infestation prevention fee. The bill would authorize a vessel operator to be issued a citation for operating a nonmotorized vessel without that valid state-issued invasive mussel infestation prevention sticker.
This bill would require the $20 fee to be deposited into the Nonmotorized Vessel Invasive Mussel Infestation Prevention Account, which the bill would create within the Harbors and Watercraft Revolving Fund. Moneys in the account would be available, upon appropriation by the Legislature, for reasonable regulatory costs of the department and the division and for specified grants. The bill would require any citation moneys to be deposited into the Nonmotorized Vessel Invasive Mussel Infestation Prevention Penalty Account, which the bill would create within the Harbors and Watercraft Revolving Fund. Moneys in the penalty account would be available, upon appropriation by the Legislature, for specified grants and to expend on certain educational materials and signage.
(3)The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
(4)Existing constitutional provisions require that a statute that limits the right of access to the meetings of public bodies or the writings of public officials and agencies be adopted with findings demonstrating the interest protected by the limitation and the need for protecting that interest.
This bill would make legislative findings to that effect.
(1)Existing law, until January 1, 2030, generally prohibits a person from possessing, importing, shipping, or transporting in the state, or from placing, planting, or causing to be placed or planted in any water in the state, invasive mussels, and authorizes the Director of Fish and Wildlife or the directors designee to engage in various enforcement activities, including ordering the areas in conveyance that contain water be drained, dried, or decontaminated, as provided. Existing law requires a public or private agency that operates a water supply system to cooperate with the Department of Fish and Wildlife to implement measures to avoid infestation by invasive mussels and to control or eradicate any infestation that may occur in a water supply system. Existing law requires, if invasive mussels are detected, the operator of a water supply system to, in cooperation with the department, prepare and implement a plan to control or eradicate invasive mussels within the system, and eliminate or minimize any potential downstream transport of an invasive mussel. Existing law requires, on or before December 31, 2026, the department to review all approved plans and require all plans that do not specifically address all invasive mussel species known to be present in bodies of water in the state as of January 1, 2026, to be updated or revised appropriately to include all invasive mussel species, on or before September 30, 2027. Existing law requires every invasive mussel species to be addressed in a plan no later than 180 days from the date that the species is listed in a certain regulation. Existing law defines invasive mussel for these purposes as any nonnative detrimental mussel, as provided.
Under existing law, except as otherwise provided, any violation of the Fish and Game Code, or of any rule, regulation, or order made or adopted under the code, is a crime.
This bill would prohibit a conveyance from being launched until a specified drying period has completed, as provided. By expanding the scope of a crime, this bill would impose a state-mandated local program. The bill would require the department to require water supply system operators to update their plans to address all invasive mussel species present in the operators water system as of January 1, 2026, as provided. The bill would require a plan to address every invasive mussel species detected in a water supply system after January 1, 2026, no later than 180 days from the date the species is detected. The bill would require a plan to minimize or eliminate the spread of invasive mussels. The bill would revise the definition of invasive mussel to mean any nonnative biofouling mussel, as provided. By expanding the scope of a crime, the bill would impose a state-mandated local program.
This bill would authorize the department to decontaminate or order decontamination of a conveyance found or reasonably believed to harbor aquatic invasive species and would require the department to establish standards and protocols for decontaminating conveyances and disposing of organisms and organic materials, as specified. The bill would authorize a law enforcement officer to detain or impound a conveyance if a person refuses to submit to a decontamination or, due to personal hardship, is unable to immediately accompany the conveyance for decontamination. The bill would authorize the department to issue an inspection, decontamination, or quarantine certificate to the owner or person in possession of a conveyance that has been inspected for adult or larval invasive mussels, and would authorize the department to attach a tamper-proof device to the conveyance to prevent the conveyance from coming into contact with waters of the state without being broken. Because a violation of these decontamination provisions would be a crime, the bill would impose a state-mandated local program.This bill would enact a comprehensive inspection and decontamination program to be administered by the department under which the department would license inspection and decontamination stations with qualified inspectors to inspect and decontaminate conveyances for aquatic invasive species and issue certificates of compliance or notices of noncompliance, as prescribed by standards adopted by the department. The bill would establish a length of 2 years for those licenses and qualifications and would impose related application fees. The bill would impose requirements on various entities as part of the program, including requiring inspection and decontamination stations and waterbody managers to use a specified data sharing system for tracking the movement of conveyances, equipment, and other vectors among California waterbodies. Because a violation of these provisions would be a crime, the bill would impose a state-mandated local program.
(2)Existing law establishes a registration fee and a renewal fee for vessels, and imposes an additional fee, known as the invasive mussel infestation prevention fee, on a vessel required to pay the registration fee or renewal fee, as provided. Existing law requires the Division of Boating and Waterways to issue a vessel an invasive mussel infestation prevention sticker to the vessel owner upon payment of the invasive mussel infestation prevention fee. Existing law authorizes a vessel operator to be issued a citation for operating a vessel or a recreational vessel in nonmarine waters without a valid state-issued invasive mussel infestation prevention sticker.
This bill would enact similar provisions that would impose an additional invasive mussel infestation prevention fee of $20 per nonmotorized vessel every 2 years, as specified. The bill would require the Department of Fish and Wildlife to issue an invasive mussel infestation prevention sticker to be affixed to the nonmotorized vessel upon payment of the invasive mussel infestation prevention fee. The bill would authorize a vessel operator to be issued a citation for operating a nonmotorized vessel without that valid state-issued invasive mussel infestation prevention sticker.
This bill would require the $20 fee to be deposited into the Nonmotorized Vessel Invasive Mussel Infestation Prevention Account, which the bill would create within the Harbors and Watercraft Revolving Fund. Moneys in the account would be available, upon appropriation by the Legislature, for reasonable regulatory costs of the department and the division and for specified grants. The bill would require any citation moneys to be deposited into the Nonmotorized Vessel Invasive Mussel Infestation Prevention Penalty Account, which the bill would create within the Harbors and Watercraft Revolving Fund. Moneys in the penalty account would be available, upon appropriation by the Legislature, for specified grants and to expend on certain educational materials and signage.
The(3)The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law, until January 1, 2030, generally prohibits a person from possessing, importing, shipping, or transporting in the state, or from placing, planting, or causing to be placed or planted in any water in the state, invasive mussels. mussels, and authorizes the Director of Fish and Wildlife or the directors designee to engage in various enforcement activities, including ordering the areas in conveyance that contain water be drained, dried, or decontaminated, as provided. Existing law requires a public or private agency that operates a water supply system to cooperate with the Department of Fish and Wildlife to implement measures to avoid infestation by invasive mussels and to control or eradicate any infestation that may occur in a water supply system. Existing law requires, if invasive mussels are detected, the operator of a water supply system to, in cooperation with the department, prepare and implement a plan to control or eradicate invasive mussels within the system, and eliminate or minimize any potential downstream transport of an invasive mussel. Existing law requires, on or before December 31, 2026, the department to review all approved plans and require all plans that do not specifically address all invasive mussel species known to be present in bodies of water in the state as of January 1, 2026, to be updated or revised appropriately to include all invasive mussel species, on or before September 30, 2027. Existing law requires every invasive mussel species to be addressed in a plan no later than 180 days from the date that the species is listed in a certain regulation. Existing law defines invasive mussel for these purposes as any nonnative detrimental mussel, as provided.
Under existing law, except as otherwise provided, any violation of the Fish and Game Code, or of any rule, regulation, or order made or adopted under the code, is a crime.
This bill would prohibit a conveyance from being launched until a specified drying period has completed, as provided. By expanding the scope of a crime, this bill would impose a state-mandated local program. The bill would require the department to require water supply system operators to update their plans to address all invasive mussel species present in the operators water system as of January 1, 2026, as provided. The bill would require a plan to address every invasive mussel species detected in a water supply system after January 1, 2026, no later than 180 days from the date the species is detected. The bill would require a plan to minimize or eliminate the spread of invasive mussels. The bill would revise the definition of invasive mussel to mean any nonnative biofouling mussel, as provided. By expanding the scope of a crime, the bill would impose a state-mandated local program.
This bill would authorize the department to decontaminate or order decontamination of a conveyance found or reasonably believed to harbor aquatic invasive species and would require the department to establish standards and protocols for decontaminating conveyances and disposing of organisms and organic materials, as specified. The bill would authorize a law enforcement officer to detain or impound a conveyance if a person refuses to submit to a decontamination or, due to personal hardship, is unable to immediately accompany the conveyance for decontamination. The bill would authorize the department to issue an inspection, decontamination, or quarantine certificate to the owner or person in possession of a conveyance that has been inspected for adult or larval invasive mussels, and would authorize the department to attach a tamper-proof device to the conveyance to prevent the conveyance from coming into contact with waters of the state without being broken. Because a violation of these decontamination provisions would be a crime, the bill would impose a state-mandated local program.
This bill would require the department, in consultation with the Department of Parks and Recreation and the Department of Food and Agriculture, to develop a voluntary framework to prevent the overland spread of invasive mussels through the conveyance of watercraft overland. The bill would require the framework to include specified elements, including, among other elements, minimum standards for watercraft inspection, decontamination, and quarantine and a banding program or other mechanisms by which to confirm the inspection, decontamination, or quarantine status of a watercraft.The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law, until January 1, 2030, generally prohibits a person from possessing, importing, shipping, or transporting in the state, or from placing, planting, or causing to be placed or planted in any water in the state, invasive mussels. Existing law requires a public or private agency that operates a water supply system to cooperate with the Department of Fish and Wildlife to implement measures to avoid infestation by invasive mussels and to control or eradicate any infestation that may occur in a water supply system. Existing law requires, if invasive mussels are detected, the operator of a water supply system to, in cooperation with the department, prepare and implement a plan to control or eradicate invasive mussels within the system, and eliminate or minimize any potential downstream transport of an invasive mussel. Existing law requires, on or before December 31, 2026, the department to review all approved plans and require all plans that do not specifically address all invasive mussel species known to be present in bodies of water in the state as of January 1, 2026, to be updated or revised appropriately to include all invasive mussel species, on or before September 30, 2027. Existing law requires every invasive mussel species to be addressed in a plan no later than 180 days from the date that the species is listed in a certain regulation. Existing law defines invasive mussel for these purposes as any nonnative detrimental mussel, as provided.
Under existing law, except as otherwise provided, any violation of the Fish and Game Code, or of any rule, regulation, or order made or adopted under the code, is a crime.
This bill would require the department to require water supply system operators to update their plans to address all invasive mussel species present in the operators water system as of January 1, 2026, as provided. The bill would require a plan to address every invasive mussel species detected in a water supply system after January 1, 2026, no later than 180 days from the date the species is detected. The bill would require a plan to minimize or eliminate the spread of invasive mussels. The bill would revise the definition of invasive mussel to mean any nonnative biofouling mussel, as provided. By expanding the scope of a crime, the bill would impose a state-mandated local program.
This bill would require the department, in consultation with the Department of Parks and Recreation and the Department of Food and Agriculture, to develop a voluntary framework to prevent the overland spread of invasive mussels through the conveyance of watercraft overland. The bill would require the framework to include specified elements, including, among other elements, minimum standards for watercraft inspection, decontamination, and quarantine and a banding program or other mechanisms by which to confirm the inspection, decontamination, or quarantine status of a watercraft.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law generally prohibits a person from possessing, importing, shipping, or transporting in the state, or from placing, planting, or causing to be placed or planted in any water within the state, invasive mussels and authorizes the Director of Fish and Wildlife or the directors designee to engage in various enforcement activities with regard to invasive mussels, as provided. Existing law requires specified entities that own or manage a reservoir, as defined, where certain activities are permitted to monitor and prevent the introduction of invasive mussel species, as specified, and requires any entity that discovers invasive mussels in the state to report the discovery immediately to the department.This bill would provide that it is the intent of the Legislature to enact subsequent legislation to, among other things, address and prevent the spread of aquatic invasive species, including, but not limited to, the golden mussel, in Californias waterbodies and water infrastructure systems. The bill would also make various findings and declarations relating to aquatic invasive species.Existing law generally prohibits a person from possessing, importing, shipping, or transporting in the state, or from placing, planting, or causing to be placed or planted in any water within the state, invasive mussels and authorizes the Director of Fish and Wildlife or the directors designee to engage in various enforcement activities with regard to invasive mussels, as provided. Existing law requires specified entities that own or manage a reservoir, as defined, where certain activities are permitted to monitor and prevent the introduction of invasive mussel species, as specified, and requires any entity that discovers invasive mussels in the state to report the discovery immediately to the department.
This bill would provide that it is the intent of the Legislature to enact subsequent legislation to, among other things, address and prevent the spread of aquatic invasive species, including, but not limited to, the golden mussel, in Californias waterbodies and water infrastructure systems. The bill would also make various findings and declarations relating to aquatic invasive species.
(a)The Legislature finds and declares all of the following:
(1)Aquatic invasive species, including the golden mussel, threaten the ecological health, recreational value, and operational integrity of Californias lakes, rivers, reservoirs, and water conveyance facilities.
(2)Efforts to control or prevent the spread of the golden mussel and other aquatic invasive species result in extensive operational and economic impacts to water delivery and hydropower, and have impacted public access to recreational opportunities such as boating, fishing, and other water-dependent activities.
(3)No single entity can bear the increasing costs of managing the impacts of golden mussels. The recreational boating community faces increasing costs related to decontamination, quarantine requirements, and aquatic invasive species sticker fees, while water managers face significant costs related to implementing costly prevention and control measures. Without efforts to contain the spread of golden mussels, costs will continue to rise leading to impacts on water affordability for ratepayers.
(4)The effects of golden mussels on Californias water systems are currently being studied, and improvements in prevention and mitigation efforts will need to incorporate the latest scientific advancements to effectively respond to the issue.
(5)The Harbors and Watercraft Revolving Fund, established in Section 85 of the Harbors and Navigation Code, is structurally imbalanced and remains in deficit, thereby requiring the identification and adoption of alternative and sustainable funding sources to support statewide aquatic invasive species prevention and mitigation programs.
(6)Establishing uniform statewide standards for vessel decontamination, including standards applicable to both motorized and nonmotorized paddlecraft, along with a system of tracking compliance with standards, monitoring watercraft launches, and information sharing and voluntary reciprocity among waterbodies, will improve efficiency, protect natural resources, and support Californias economic and recreational interests.
(7)Inspection programs help prevent the spread of aquatic species via transportation conveyances. These programs provide for the inspection and decontamination of conveyances, as well as an opportunity for outreach and education on the risks posed by the introduction and spread of aquatic invasive species. The programs protect both the environmental and recreational values of the states waters, infrastructure, and economy.
(8)The transportation of recreational watercraft and associated equipment from one waterbody to another is a primary vector for the spread of aquatic invasive species.
(b)It is the intent of the Legislature in enacting this bill to accomplish all of the following:
(1)Require the use of a single, statewide database to track the movement of vessels, equipment, and other vectors among California waterbodies, providing waterbody managers with accurate information on the prior contamination status of these vessels.
(2)Provide uniform decontamination standards and certification of decontamination for vessels and equipment moving between noninfested waterbodies, thereby facilitating safe recreational access.
(3)Promote a system of voluntary reciprocity between waterbodies.
SEC. 2.Section 2301 of the Fish and Game Code is amended to read:2301.(a)(1)Except as authorized by the department, a person shall not possess, import, ship, or transport in the state, or place, plant, or cause to be placed or planted in any water within the state, invasive mussels.
(2)The director or the directors designee may do all of the following:
(A)Conduct inspections of conveyances, which include vehicles, boats and other watercraft, containers, and trailers, that may carry or contain adult or larval invasive mussels. Included as part of this authority to conduct inspections is the authority to temporarily stop conveyances that may carry or contain adult or larval invasive mussels on any roadway or waterway in order to conduct inspections.
(B)(i)Order that areas in a conveyance that contain water be drained, dried, or decontaminated pursuant to procedures approved by the department.
(ii)An order to dry pursuant to clause (i) may require the owner or person in possession of the conveyance to dry the conveyance for a designated period of time before launching into waters of the state. A conveyance shall not be launched until the required drying period has been completed.
(iii)If issued an order to dry pursuant to clause (i), an owner or person in possession of the conveyance may retain possession of the conveyance during the drying period, subject to any requirements established by the department such as attaching a tamper-proof device to the conveyance that prevents the conveyance from coming into contact with water without being broken.
(C)Impound or quarantine conveyances in locations designated by the department for the period of time necessary to ensure that invasive mussels can no longer live on or in the conveyance.
(D)(i)Conduct inspections of waters of the state and facilities located within waters of the state that may contain invasive mussels. If invasive mussels are detected or may be present, the director or the directors designee may order the affected waters or facilities closed to conveyances or otherwise restrict access to the affected waters or facilities, and shall order that conveyances removed from, or introduced to, the affected waters or facilities be inspected, quarantined, or disinfected in a manner and for a duration necessary to detect and prevent the spread of invasive mussels within the state.
(ii)For the purpose of implementing clause (i), the director or the directors designee shall order the closure or quarantine of, or restrict access to, these waters, areas, or facilities in a manner and duration necessary to detect and prevent the spread of invasive mussels within the state. A closure, quarantine, or restriction shall not be authorized by the director or the directors designee without the concurrence of the Secretary of the Natural Resources Agency. If a closure lasts longer than seven days, the department shall update the operator of the affected facility every 10 days on efforts to address the invasive mussel infestation. The department shall provide these updates in writing and also post these updates on the departments internet website in an easily accessible manner.
(iii)The department shall develop procedures to ensure proper notification of affected local and federal agencies, and, as appropriate, the Department of Water Resources, the Department of Parks and Recreation, and the State Lands Commission in the event of a decision to close, quarantine, or restrict a facility pursuant to this paragraph. These procedures shall include the reasons for the closure, quarantine, or restriction, and methods for providing updated information to those affected. These procedures shall also include protocols for the posting of the notifications on the departments internet website required by clause (ii).
(iv)When deciding the scope, duration, level, and type of restrictions, and specific location of a closure or quarantine, the director shall consult with the agency, entity, owner, or operator with jurisdiction, control, or management responsibility over the marina, boat launch facility, or other facility, in order to focus the closure or quarantine to specific areas and facilities so as to avoid or minimize disruption of economic or recreational activity in the vicinity.
(b)(1)Upon a determination by the director that it would further the purposes of this section, other parties or state agencies, including, but not limited to, the Department of Parks and Recreation, the Department of Water Resources, the Department of Food and Agriculture, and the State Lands Commission, may exercise the authority, or portions of that authority, granted to the department in subdivision (a).
(2)A determination made pursuant to paragraph (1) shall be in writing and shall remain in effect until withdrawn, in writing, by the director.
(c)(1)Except as provided in paragraph (2), Division 13 (commencing with Section 21000) of the Public Resources Code does not apply to the implementation of this section.
(2)An action undertaken pursuant to subparagraph (B) of paragraph (2) of subdivision (a) involving the use of chemicals other than salt or hot water to decontaminate a conveyance or a facility is subject to Division 13 (commencing with Section 21000) of the Public Resources Code.
(d)(1)A public or private agency that operates a water supply system shall cooperate with the department to implement measures to avoid infestation by invasive mussels and to control or eradicate any infestation that may occur in a water supply system. If invasive mussels are detected, the operator of the water supply system, in cooperation with the department, shall prepare and implement a plan to control or eradicate invasive mussels within the system to minimize or eliminate the spread of an invasive mussel. The approved plan shall contain the following minimum elements:
(A)Methods for delineation of infestation, including both adult mussels and veligers.
(B)Methods for control or eradication of adult mussels and decontamination of water containing larval mussels.
(C)A systematic monitoring program to determine any changes in conditions.
(D)The requirement that the operator of the water supply system permit inspections by the department as well as cooperate with the department to update or revise control or eradication measures in the approved plan to address scientific advances in the methods of controlling or eradicating mussels and veligers.
(2)If the operator of water delivery and storage facilities for public water supply purposes has prepared, initiated, and is in compliance with all the elements of an approved plan to control or eradicate invasive mussels in accordance with paragraph (1), the requirements of subdivision (a) do not apply to the operation of those water delivery and storage facilities, and the operator is not subject to any civil or criminal liability for the introduction of invasive mussel species as a result of those operations. The department may require the operator of a facility to update its plan, and if the plan is not updated or revised as described in this subdivision, subdivision (a) shall apply to the operation of the water delivery and storage facilities covered by the plan until the operator updates or revises the plan and initiates and complies with all of the elements of the updated or revised plan.
(3)On or before December 31, 2026, the department shall review all approved plans pursuant to this subdivision. The department shall require water supply system operators to update the plans to address all invasive mussel species present in their system as of January 1, 2026, on or before September 30, 2027.
(4)Every invasive mussel species detected in a water supply system after January 1, 2026, shall be addressed in a plan pursuant to this subdivision no later than 180 days from the date the species is detected. The department shall approve plans or provide written comments and suggestions on plan deficiencies within 180 days from the date of plan submission.
(e)Any entity that discovers invasive mussels within this state shall immediately report the discovery to the department.
(f)(1)In addition to any other penalty provided by law, any person who violates this section, violates any verbal or written order or regulation adopted pursuant to this section, or who resists, delays, obstructs, or interferes with the implementation of this section, is subject to a penalty, in an amount not to exceed one thousand dollars ($1,000), that is imposed administratively by the department.
(2)A penalty shall not be imposed pursuant to paragraph (1) unless the department has adopted regulations specifying the amount of the penalty and the procedure for imposing and appealing the penalty.
(g)The department may adopt regulations to carry out this section.
(h)Pursuant to Section 818.4 of the Government Code, the department and any other state agency exercising authority under this section shall not be liable with regard to any determination or authorization made pursuant to this section.
(i)This section shall remain in effect only until January 1, 2030, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2030, deletes or extends that date.
SEC. 3.Section 2301.1 is added to the Fish and Game Code, to read:2301.1.(a)(1)Inspection and decontamination of conveyances for aquatic invasive species in the state shall be performed in accordance with uniform standards and procedures that the department shall establish for decontaminating conveyances and the treatment and disposal of water, organism, and organic materials yielded from the decontamination process. These standards and procedures shall be effective at removing or destroying invasive mussels and shall be performed in a manner that ensures no viable invasive mussels remain on or in the conveyance before launch.
(2)At a minimum, decontamination shall include all of the following:
(A)Removal of all visible plant materials, mud, and organisms from the conveyance and any associated equipment, including equipment that transports the conveyance.
(B)Draining and treatment of all water-containing compartments, including, but not limited to, bilges, ballast tanks, live wells, and engine cooling systems.
(C)Treatment of exterior surfaces and all water-contact components using heated water or other department-approved methods demonstrated to achieve mortality of invasive species.
(D)Flushing or treatment of internal systems, including engines, ballast systems, and plumbing, in a manner sufficient to eliminate viable invasive mussels.
(3)(A)Standards and procedures established by the department shall, at a minimum, be compliant with the Uniform Minimum Protocols and Standards for Watercraft Interception Programs for Dreissenid Mussels in the Western United States prepared by the Pacific States Marine Fisheries Commission that have been developed for invasive dreissenid mussels.
(B)The standards and procedures shall be informed by the best available science.
(C)The department may consult with water agencies and recreational boaters to develop the standards and procedures.
(4)The department shall implement this chapter in a manner consistent with the requirements for decontamination described in paragraph (2) regardless of whether the department has adopted standards and procedures for decontamination pursuant to paragraph (1).
(b)Before launch into the waters of the state, a conveyance shall be subject to decontamination or quarantine if a qualified inspector determines under this chapter that any of the following conditions exist:
(1)Invasive mussels are detected or reasonably suspected to be present on or in the conveyance.
(2)The conveyance has been operated in or transported from an infested waterbody.
(3)The conveyance contains water in compartments, systems, or structures that cannot be completely drained.
(c)If a person refuses to submit to decontamination or quarantine of a conveyance pursuant to subdivision (b) found or reasonably believed to harbor aquatic invasive species, or due to personal hardship is unable to immediately accompany the conveyance for decontamination, a law enforcement officer may detain or impound the conveyance until the decontamination is complete.
(d)The owner of a conveyance that is decontaminated or detained due to failure to cooperate by the owner or person in possession of the conveyance is liable for all costs associated with the decontamination or impoundment, in accordance with the applicable rules promulgated by the department.
(e)Pursuant to Section 818.4 of the Government Code, the department and any other state agency exercising authority under this section shall not be liable with regard to any determination or authorization made pursuant to this section, provided the department adhered to all standards, procedures, and regulations promulgated by the department under this chapter.
(f)The department may adopt regulations to implement this section.
(g)Notwithstanding any other law, the operator of a water supply system with an approved control plan pursuant to Section 2301 and who operates or contracts for the operation of their own inspection and decontamination station for their own water supply system may choose to continue to use their own inspection and decontamination station dedicated to their water supply system upon notification to the department. An operator using their own inspection and decontamination station in this manner shall provide to the department documentation of the inspection, decontamination, and other relevant processes and procedures used to prevent the introduction of invasive mussel species to their water supply system.
SEC. 4.Section 2301.2 is added to the Fish and Game Code, to read:2301.2.(a)A licensed inspection and decontamination station may issue an inspection, decontamination, or quarantine certificate to the owner or person in possession of a conveyance that has been inspected pursuant to Section 2301. The certificate shall reflect all of the following:
(1)The name of the station and of the qualified inspector who conducted the inspection.
(2)The date, place, and time of the inspection.
(3)Any preventative measures performed or ordered.
(4)Any decontamination performed.
(b)If the station issues an inspection, decontamination, or quarantine certificate to the owner or person in possession of the conveyance, the station shall attach a tamper-proof device to the conveyance. The device may be a seal, tag, or band that prevents the conveyance from coming into contact with waters of the state without being broken.
(c)The department shall establish a minimum retention period for inspection and decontamination certificates issued under this section.
(d)The department may recognize, by reciprocity, an inspection or decontamination certificate issued by another government entity, if the other governmental entity adheres to the minimum standards for inspection, decontamination, and quarantine established pursuant to Section 2301.1.
(e)Pursuant to Section 818.4 of the Government Code, the department and any other state agency exercising authority under this section shall not be liable with regard to any determination or authorization made pursuant to this section, provided the department adhered to all standards, procedures, and regulations promulgated by the department under this chapter.
(f) The department may adopt regulations to implement this section.
SEC. 5.Section 2301.3 is added to the Fish and Game Code, to read:2301.3.(a)The department shall have the sole and exclusive authority within the state for developing and implementing a statewide program for the inspection and decontamination of conveyances for aquatic invasive species in accordance with this chapter. The inspection and decontamination program shall consist of licensed inspection and decontamination stations with qualified inspectors that inspect and decontaminate conveyances and issue certificates of compliance to conveyances that meet the requirements of this chapter or notices of noncompliance to conveyances that do not meet the requirements of this chapter.
(b)(1)The inspection and decontamination program shall only be conducted at inspection and decontamination stations licensed by the department and by inspectors who are qualified pursuant to subdivision (a) of Section 2301.4.
(2)A licensed inspection and decontamination station shall do all of the following:
(A)Comply with standards, procedures, and regulations adopted by the department pursuant to this chapter.
(B)Only permit inspection and decontamination by qualified inspectors.
(C)Employ the use of department-approved decontamination equipment, certification documentation, and tamper-proof devices pursuant to subdivision (b) of Section 2301.2.
(D)Use the WID Data Sharing System pursuant to Section 2301.6.
(E)Maintain educational materials regarding aquatic invasive species identification and initiatives such as the clean, drain, dry standard.
(F)Display an identifying sign prescribed by the department in a manner conspicuous to the public that indicates the current qualification status of the station.
(G)Permit the department, or an authorized representative, to access the station for purposes of examining equipment, records, inspection logs, decontamination records, tamper-proof devices, certifications, and related program materials.
(c)(1)The department shall develop standards for the licensing of inspection and decontamination stations. Inspection and decontamination services at the station shall only be performed by a qualified inspector to achieve the standards adopted pursuant to Section 2301.1.
(2)The department shall establish performance standards for a licensed inspection and decontamination station for which compliance is determined through periodic inspections.
(3)The department shall develop and implement a quality assurance program, such as a secret shopper program, to audit inspection and decontamination stations and ensure compliance with department-established standards and procedures pursuant to this chapter.
(d)(1)The license of an inspection and decontamination station shall expire after two years. The department may require passage of a licensing test and ongoing training to renew a stations license.
(2)Failure at any time of a licensed inspection and decontamination station to meet standards established pursuant to this chapter applicable to inspection and decontamination stations shall result in revocation of the stations license.
(3)The department shall provide a licensed inspection and decontamination station with written or electronic notice before revoking its license pursuant to paragraph (2). The notice shall specify the grounds for the revocation.
(4)The department shall develop a process and timeline for a station to contest a license revocation.
(e)The department shall encourage the establishment of a sufficient number of licensed inspection and decontamination stations in locations to ensure reasonable accessibility and convenience of boaters and the control of the spread of invasive mussels.
(f)The department shall post on its internet website a list, compiled by region, of licensed inspection and decontamination stations and identify stations that have been found to be noncompliant with departmental standards and have had their licenses revoked.
(g)A licensed inspection and decontamination station shall annually report to the department all of the following information:
(1)The number of certificates issued to conveyances that meet the requirements of this chapter.
(2)The number of notices of noncompliance issued to conveyances that do not meet the requirements of this chapter.
(3)The number of each invasive species intercepted at the station.
(4)Any other information the department requires.
(h)Licensing fees for inspection and decontamination stations under this section shall be imposed by the department in an amount that does not exceed the reasonable regulatory costs of administering the licensing program.
(i)The department may adopt regulations to implement this section.
SEC. 6.Section 2301.4 is added to the Fish and Game Code, to read:2301.4.(a)To qualify as a qualified inspector, an inspector shall pass a qualification test administered by the department, in addition to meeting any minimum experience and training criteria established by the department.
(b)The department shall establish standards for training, equipment, performance, and data collection for inspection and decontamination stations. The department may do either of the following:
(1)(A)Develop, in consultation with interested stakeholders, a training program and accompanying materials to be used to qualify individuals who apply to perform inspections and decontaminations. The departments training program and accompanying materials shall, at a minimum, align with the Pacific States Marine Fisheries Commissions watercraft inspection and decontamination Level 2 training program.
(B)If the department develops its own training program pursuant to subparagraph (A), the department shall grant qualified inspector status to both of the following upon application of the individual:
(i)An individual with a current Level 2 Inspector and Decontaminator or an Advanced Decontamination training certificate issued by the Pacific States Marine Fisheries Commission.
(ii)An individual with a current training certificate of a training program that adheres to the minimum standards for inspection, decontamination, and quarantine established in the Uniform Minimum Protocols and Standards for Watercraft Interception Programs for Dreissenid Mussels in the Western United States prepared by the Pacific States Marine Fisheries Commission.
(2)In lieu of developing its own training program pursuant to paragraph (1), grant qualified inspector status to individuals who have completed the Pacific States Marine Fisheries Commissions watercraft inspection and decontamination Level 2 training program.
(c)The department shall prescribe training and periodic retraining courses for qualified inspectors.
(d)(1)A qualified inspectors qualification shall expire after two years. The department may require passage of a qualification test and ongoing training to renew an inspectors qualification.
(2)Failure at any time of a qualified inspector to meet standards established pursuant to this chapter applicable to qualified inspectors shall result in disqualification to inspect and decontaminate conveyances.
(3)The department shall provide a qualified inspector and the relevant licensed inspection and decontamination station with written or electronic notice before imposing a disqualification pursuant to paragraph (2). The notice shall specify the grounds for the disqualification.
(4)The department shall develop a process and timeline for a qualified inspector to contest a disqualification.
(e)The department shall develop standards for qualifying institutions and instructors for purposes of providing training of qualified inspectors. The standards shall include criteria for manuals, textbooks, equipment, exercises, hands-on work, examinations, and other matters the department determines necessary for a course of instruction. The standards shall also specify the conditions under which an institution or instructor may be disqualified to train qualified instructors, and how a disqualified institution or instructor may regain qualification. The department shall make the standards available on its internet website.
(f)Qualification fees for qualified inspectors under subdivision (a) and qualified institutions and instructors under subdivision (e) shall be imposed by the department in an amount that does not exceed the reasonable regulatory costs of administering the qualification program.
(g)The department may adopt regulations to implement this section.
SEC. 7.Section 2301.6 is added to the Fish and Game Code, to read:2301.6.(a)The department shall use the Regional Watercraft Inspection and Decontamination (WID) Data Sharing System managed by the Colorado Parks and Wildlife Division of the Colorado Department of Natural Resources for tracking the movement of conveyances, equipment, and other vectors among California waterbodies.
(b)An inspection and decontamination station shall enter each inspected, decontaminated, or quarantined conveyance into the WID Data Sharing System.
(c)The manager of a waterbody of the state that has a staffed launch point shall register each launching conveyance into the WID Data Sharing System.
(d)The department shall provide guidance to entities that own or manage reservoirs, as defined in Section 6004.5 of the Water Code, or other launch points, on how to track decontaminated and inspected conveyances in the WID Data Sharing System.
(e)The department shall encourage the use of the WID Data Sharing System across the state.
(f)Data gathered by the WID Data Sharing System or its equivalent shall be used solely for the purposes of the prevention of invasive mussel species infestations of the states waterbodies and shall not be sold, bartered, or provided to other public or private parties, or used in any other way for any other purpose.
SEC. 8.Section 2301.7 is added to the Fish and Game Code, to read:2301.7.(a)The department shall encourage public or private agencies that operate a water supply system to enter into reciprocity agreements with other agencies to allow the launch of conveyances without quarantine or decontamination for conveyances moving between waterbodies operated by those agencies. Participation by a public or private agency in any reciprocity agreement is voluntary.
(b)A public or private agency that operates a water supply system shall notify the department of a reciprocity agreement entered into pursuant to subdivision (a).
(c)The department shall maintain a comprehensive list of reciprocity agreements on its internet website.
SEC. 9.Section 2303 of the Fish and Game Code is amended to read:2303.For purposes of this chapter, the following definitions apply:
(a)Invasive mussel means any nonnative biofouling mussel species that is capable of spreading in freshwater and is listed in a regulation adopted by the commission pursuant to Section 2118.
(b)Licensed inspection and decontamination station means an inspection and decontamination station that has been licensed by the department pursuant to paragraph (1) of subdivision (c) of Section 2301.3.
(c)Qualified inspector means an inspector that passes a qualification test administered by the department, in addition to meeting any minimum experience and training criteria established by the department pursuant to subdivision (a) of Section 2301.4.
(d)WID Data Sharing System means the Regional Watercraft Inspection and Decontamination Data Sharing System managed by the Colorado Parks and Wildlife Division of the Colorado Department of Natural Resources described in subdivision (a) of Section 2301.6.
SEC. 10.Chapter 3.6 (commencing with Section 2305) is added to Division 3 of the Fish and Game Code, to read:3.6.Nonmotorized Vessel Invasive Mussel Infestation Prevention Fee2305.(a)(1)On or before January 1, 2028, the department shall collect, in addition to any other fee imposed under existing law, an invasive mussel infestation prevention fee from each nonmotorized vessel owner for each nonmotorized vessel launched into waters of the state.
(2)The fee shall be twenty dollars ($20) per nonmotorized vessel every two years.
(3)The amount in paragraph (2) shall be adjusted for inflation every odd-numbered year using the California Consumer Price Index to the nearest whole dollar value.
(4)Notwithstanding paragraphs (2) and (3), the fee shall not exceed the reasonable regulatory costs of the state to implement this chapter.
(b)Upon payment of the invasive mussel infestation prevention fee pursuant to subdivision (a), the department shall issue an invasive mussel infestation prevention sticker to the vessel owner, to be affixed to the nonmotorized vessel in a manner deemed appropriate by the division.
(c)(1)A nonmotorized vessel operator may be issued a citation for operating the vessel in nonmarine waters without a valid state-issued invasive mussel infestation prevention sticker. A citation issued pursuant to this section shall not exceed twice the cost of the sticker.
(2)Section 12000 does not apply to a violation of this chapter.
(d)Any evidence of tampering with the invasive mussel infestation prevention sticker shall void the sticker.
(e)(1)All revenues collected from the fee pursuant to subdivision (a) shall be deposited into the Nonmotorized Vessel Invasive Mussel Infestation Prevention Account, which is hereby created within the Harbors and Watercraft Revolving Fund. Upon appropriation by the Legislature, moneys in the account shall be expended solely for the purposes set forth in subdivision (a) of Section 2306. None of the revenues collected from the fee pursuant to subdivision (a) shall be used for any purpose other than those explicitly authorize authorized by subdivision (a) of Section 2306.
(2)Revenues collected from any citation issued under subdivision (c) shall be deposited into the Nonmotorized Vessel Invasive Mussel Infestation Prevention Penalty Account, which is hereby created within the Harbors and Watercraft Revolving Fund. Upon appropriation by the Legislature, moneys in the account shall be expended solely for the purposes set forth in subdivision (c) of Section 2306.
(f)The department may contract with another state agency, a vendor, or an authorized license agent for the issuance of the sticker described in subdivision (b).
(g)The division shall develop educational materials to be provided before issuance of the sticker described in subdivision (b).
2306.(a)Moneys deposited into the Nonmotorized Vessel Invasive Mussel Infestation Prevention Account pursuant to Section 2305 shall be available, upon appropriation by the Legislature, for the following purposes:
(1)For reasonable regulatory costs, not to exceed 15 percent of the revenues deposited into the account, of the department or other entity issuing stickers pursuant to subdivision (b) of Section 2306 and of administering this chapter.
(2)For the divisions reasonable regulatory costs, not to exceed 10 percent of the revenues deposited into the account, to administer the grants pursuant to paragraph (3).
(3)For an amount not less than 40 percent of the remaining revenues deposited into the account for grants to entities subject to subdivision (a) of Section 2302 for the reasonable regulatory costs incident to the implementation of an invasive mussel infestation prevention plan that is consistent with the requirements of Section 2302. For purposes of this paragraph, reasonable regulatory costs include costs associated with the investigation and inspection of a nonmotorized vessel for the presence of invasive mussels before contact with a reservoir.
(b)For purposes of awarding grants pursuant to paragraph (3) of subdivision (a), the division shall do all of the following:
(1)Give priority to invasive mussel infestation prevention that is consistent with Section 2302 and that also includes visual and manual inspection standards and other infestation prevention procedures consistent with either the Natural Resources Agencys Invasive Mussel Guidebook for Recreational Water Managers and Users, dated September 2010, or the Natural Resources Agencys California Aquatic Invasive Species Management Plan, dated January 2008, or similar guidebooks and management plans subsequently adopted by the Natural Resources Agency.
(2)Take into consideration the benefits of regional-scale invasive mussel infestation prevention plans and coordination to contain the spread of invasive mussels.
(3)Take into consideration the unique economic, ecological, and recreational impacts to rural and urban reservoirs from invasive mussel infestation.
(4)Take into consideration the value of continued recreational access and public use of the recreational areas.
(c)Moneys deposited into the Nonmotorized Vessel Invasive Mussel Infestation Prevention Penalty Account pursuant to Section 2305 shall be available, upon appropriation by the Legislature, for both of the following:
(1)For grants to entities who have an approved control plan pursuant to subdivision (d) of Section 2301 for activities that reduce the risk of the overland spread of invasive mussels.
(2)For the division to generate and distribute educational materials and signage that do all of the following:
(A)Inform vessel operators and the public about the impact of invasive mussels on the environment and the waterways of the state.
(B)Encourage vessel operators to enact behaviors that reduce the risk of invasive mussel infestation, including the clean, drain, dry standard.
(C)Support the development of educational materials provided pursuant to subdivision (g) of Section 2305.
(d)As a condition of receiving grant funding pursuant to this section, an entity receiving funding shall report to the division data, as deemed appropriate by the division, regarding invasive mussel prevention and inspection programs and control programs implemented with the funding.
2307.For purposes of this chapter, the following definitions apply:
(a)Division means the Division of Boating and Waterways within the Department of Parks and Recreation.
(b)(1)Nonmotorized vessel means an inflatable or rigid vessel, including any of the following:
(A)Canoe.
(B)Kayak.
(C)Rowing boat.
(D)Sailboat shorter than eight feet.
(E)Sailboard or parasail.
(F)Raft.
(G)Paddleboard.
(2)Nonmotorized vessel does not include either of the following:
(A)A vessel that will only be in marine waters.
(B)A vessel required to be registered pursuant to Chapter 2 (commencing with Section 9850) of Division 3.5 of the Vehicle Code.
(c)Harbors and Watercraft Revolving Fund means the Harbors and Watercraft Revolving Fund created pursuant to Section 85 of the Harbors and Navigation Code.
(d)Marine waters means those waters subject to tidal influence.
(e)Reservoir has the same meaning as defined in Section 6004.5 of the Water Code.
(f)Waters of this state means any waters within the territorial limits of this state.
SEC. 11.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
SEC. 12.The Legislature finds and declares that Section 7 of this act, which adds Section 2301.6 to the Fish and Game Code, imposes a limitation on the publics right of access to the meetings of public bodies or the writings of public officials and agencies within the meaning of Section 3 of Article I of the California Constitution. Pursuant to that constitutional provision, the Legislature makes the following findings to demonstrate the interest protected by this limitation and the need for protecting that interest:
In order to protect the sensitive information contained in the Regional Watercraft Inspection and Decontamination Data Sharing System and ensure the data is only used for the prevention of invasive mussel species infestations of the states waterbodies, it is necessary that this act limit the publics right of access to that information.
(a)The Legislature finds and declares all of the following:
(1)Aquatic invasive species, including the golden mussel, threaten the ecological health, recreational value, and operational integrity of Californias lakes, rivers, reservoirs, and water conveyance facilities.
(2)Efforts to control or prevent the spread of the golden mussel and other aquatic invasive species result in extensive operational and economic impacts to water delivery and hydropower, and have increasingly limited impacted public access to recreational opportunities such as boating, fishing, and other water-dependent activities.
(3)The increasing costs of mandatory decontamination, quarantine requirements, and aquatic invasive species fees are disproportionately paid for by the recreational boating community, which cannot bear alone the financial responsibility of managing this statewide threat.(3)No single entity can bear the increasing costs of managing the impacts of golden mussels. The recreational boating community faces increasing costs related to decontamination, quarantine requirements, and aquatic invasive species sticker fees, while water managers face significant costs related to implementing costly prevention and control measures. Without efforts to contain the spread of golden mussels, costs will continue to rise leading to impacts on water affordability for ratepayers.
(4)The effects of golden mussels on Californias water systems are currently being studied, and improvements in prevention and mitigation efforts will need to incorporate the latest scientific advancements to effectively respond to the issue.
(4)(5)The Harbors and Watercraft Revolving Fund, established in Section 85 of the Harbors and Navigation Code, is structurally imbalanced and remains in deficit, thereby requiring the identification and adoption of alternative and sustainable funding sources to support statewide aquatic invasive species prevention and mitigation programs.
(5)(6)Establishing uniform statewide standards for vessel decontamination, including standards applicable to both motorized and nonmotorized paddlecraft, along with a system of tracking compliance with standards, monitoring watercraft launches, and information sharing and voluntary reciprocity among waterbodies, will improve efficiency, protect natural resources, and support Californias economic and recreational interests.
(6)(7)Inspection programs help prevent the spread of aquatic species via transportation conveyances. These programs provide for the inspection and decontamination of conveyances, as well as an opportunity for outreach and education on the risks posed by the introduction and spread of aquatic invasive species. The programs protect both the environmental and recreational values of the states waters, infrastructure, and economy.
(8)The transportation of recreational watercraft and associated equipment from one waterbody to another is a primary vector for the spread of aquatic invasive species.
(b)It is the intent of the Legislature in enacting this bill to accomplish both all of the following:
(1)Create a statewide Require the use of a single, statewide database to voluntarily track the movement of vessels, equipment, and other vectors among California waterbodies, providing waterbody managers with accurate information on the prior contamination status of these vessels.
(2)Develop a system of reciprocity that recognizes and honors certifications Provide uniform decontamination standards and certification of decontamination for vessels and equipment moving between noninfested waterbodies, thereby facilitating safe recreational access.
(c)It is the intent of the Legislature to subsequently amend this bill to identify and implement, to the extent feasible, alternative and equitable funding sources beyond fees imposed on the recreational boating community, such as assessments on commercial activities, including on international cargo shipping operations that may impact the introduction of aquatic invasive species to California waters.(3)Promote a system of voluntary reciprocity between waterbodies.
SEC. 2.Section 2301 of the Fish and Game Code is amended to read:2301.(a)(1)Except as authorized by the department, a person shall not possess, import, ship, or transport in the state, or place, plant, or cause to be placed or planted in any water within the state, invasive mussels.
(2)The director or the directors designee may do all of the following:
(A)Conduct inspections of conveyances, which include vehicles, boats and other watercraft, containers, and trailers, that may carry or contain adult or larval invasive mussels. Included as part of this authority to conduct inspections is the authority to temporarily stop conveyances that may carry or contain adult or larval invasive mussels on any roadway or waterway in order to conduct inspections.
(B)(i)Order that areas in a conveyance that contain water be drained, dried, or decontaminated pursuant to procedures approved by the department.
(ii)An order to dry pursuant to clause (i) may require the owner or person in possession of the conveyance to dry the conveyance for a designated period of time, not to exceed 30 days, time before launching into waters of the state. A conveyance shall not be launched until the required drying period has been completed.
(iii)If issued an order to dry pursuant to clause (i), an owner or person in possession of the conveyance may retain possession of the conveyance during the drying period, subject to any requirements established by the department. department such as attaching a tamper-proof device to the conveyance that prevents the conveyance from coming into contact with water without being broken.
(C)Impound or quarantine conveyances in locations designated by the department for the period of time necessary to ensure that invasive mussels can no longer live on or in the conveyance.
(D)(i)Conduct inspections of waters of the state and facilities located within waters of the state that may contain invasive mussels. If invasive mussels are detected or may be present, the director or the directors designee may order the affected waters or facilities closed to conveyances or otherwise restrict access to the affected waters or facilities, and shall order that conveyances removed from, or introduced to, the affected waters or facilities be inspected, quarantined, or disinfected in a manner and for a duration necessary to detect and prevent the spread of invasive mussels within the state.
(ii)For the purpose of implementing clause (i), the director or the directors designee shall order the closure or quarantine of, or restrict access to, these waters, areas, or facilities in a manner and duration necessary to detect and prevent the spread of invasive mussels within the state. A closure, quarantine, or restriction shall not be authorized by the director or the directors designee without the concurrence of the Secretary of the Natural Resources Agency. If a closure lasts longer than seven days, the department shall update the operator of the affected facility every 10 days on efforts to address the invasive mussel infestation. The department shall provide these updates in writing and also post these updates on the departments internet website in an easily accessible manner.
(iii)The department shall develop procedures to ensure proper notification of affected local and federal agencies, and, as appropriate, the Department of Water Resources, the Department of Parks and Recreation, and the State Lands Commission in the event of a decision to close, quarantine, or restrict a facility pursuant to this paragraph. These procedures shall include the reasons for the closure, quarantine, or restriction, and methods for providing updated information to those affected. These procedures shall also include protocols for the posting of the notifications on the departments internet website required by clause (ii).
(iv)When deciding the scope, duration, level, and type of restrictions, and specific location of a closure or quarantine, the director shall consult with the agency, entity, owner, or operator with jurisdiction, control, or management responsibility over the marina, boat launch facility, or other facility, in order to focus the closure or quarantine to specific areas and facilities so as to avoid or minimize disruption of economic or recreational activity in the vicinity.
(b)(1)Upon a determination by the director that it would further the purposes of this section, other parties or state agencies, including, but not limited to, the Department of Parks and Recreation, the Department of Water Resources, the Department of Food and Agriculture, and the State Lands Commission, may exercise the authority, or portions of that authority, granted to the department in subdivision (a).
(2)A determination made pursuant to paragraph (1) shall be in writing and shall remain in effect until withdrawn, in writing, by the director.
(c)(1)Except as provided in paragraph (2), Division 13 (commencing with Section 21000) of the Public Resources Code does not apply to the implementation of this section.
(2)An action undertaken pursuant to subparagraph (B) of paragraph (2) of subdivision (a) involving the use of chemicals other than salt or hot water to decontaminate a conveyance or a facility is subject to Division 13 (commencing with Section 21000) of the Public Resources Code.
(d)(1)A public or private agency that operates a water supply system shall cooperate with the department to implement measures to avoid infestation by invasive mussels and to control or eradicate any infestation that may occur in a water supply system. If invasive mussels are detected, the operator of the water supply system, in cooperation with the department, shall prepare and implement a plan to control or eradicate invasive mussels within the system to minimize or eliminate the spread of an invasive mussel. The approved plan shall contain the following minimum elements:
(A)Methods for delineation of infestation, including both adult mussels and veligers.
(B)Methods for control or eradication of adult mussels and decontamination of water containing larval mussels.
(C)A systematic monitoring program to determine any changes in conditions.
(D)The requirement that the operator of the water supply system permit inspections by the department as well as cooperate with the department to update or revise control or eradication measures in the approved plan to address scientific advances in the methods of controlling or eradicating mussels and veligers.
(2)If the operator of water delivery and storage facilities for public water supply purposes has prepared, initiated, and is in compliance with all the elements of an approved plan to control or eradicate invasive mussels in accordance with paragraph (1), the requirements of subdivision (a) do not apply to the operation of those water delivery and storage facilities, and the operator is not subject to any civil or criminal liability for the introduction of invasive mussel species as a result of those operations. The department may require the operator of a facility to update its plan, and if the plan is not updated or revised as described in this subdivision, subdivision (a) shall apply to the operation of the water delivery and storage facilities covered by the plan until the operator updates or revises the plan and initiates and complies with all of the elements of the updated or revised plan.
(3)On or before December 31, 2026, the department shall review all approved plans pursuant to this subdivision. The department shall require water supply system operators to update the plans to address all invasive mussel species present in their system as of January 1, 2026, on or before September 30, 2027.
(4)Every invasive mussel species detected in a water supply system after January 1, 2026, shall be addressed in a plan pursuant to this subdivision no later than 180 days from the date the species is detected. The department shall approve plans or provide written comments and suggestions on plan deficiencies within 180 days from the date of plan submission.
(e)Any entity that discovers invasive mussels within this state shall immediately report the discovery to the department.
(f)(1)In addition to any other penalty provided by law, any person who violates this section, violates any verbal or written order or regulation adopted pursuant to this section, or who resists, delays, obstructs, or interferes with the implementation of this section, is subject to a penalty, in an amount not to exceed one thousand dollars ($1,000), that is imposed administratively by the department.
(2)A penalty shall not be imposed pursuant to paragraph (1) unless the department has adopted regulations specifying the amount of the penalty and the procedure for imposing and appealing the penalty.
(g)The department may adopt regulations to carry out this section.
(h)Pursuant to Section 818.4 of the Government Code, the department and any other state agency exercising authority under this section shall not be liable with regard to any determination or authorization made pursuant to this section.
(i)This section shall remain in effect only until January 1, 2030, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2030, deletes or extends that date.
SEC. 3.Section 2301.1 is added to the Fish and Game Code, to read:2301.1.(a)The department, including personnel authorized by the department, may decontaminate or order the decontamination of a conveyance found or reasonably believed to harbor aquatic invasive species after an inspection conducted pursuant to Section 2301.(b)(1)The2301.1.(a)(1)Inspection and decontamination of conveyances for aquatic invasive species in the state shall be performed in accordance with uniform standards and procedures that the department shall establish standards and procedures for decontaminating conveyances and disposing of organisms and organic materials. the treatment and disposal of water, organism, and organic materials yielded from the decontamination process. These standards and procedures shall be effective at removing or destroying invasive mussels and shall be performed in a manner that ensures no viable invasive mussels remain on or in the conveyance before launch.
(2)At a minimum, decontamination shall include all of the following:
(A)Removal of all visible plant materials, mud, and organisms from the conveyance and any associated equipment. equipment, including equipment that transports the conveyance.
(B)Draining and treatment of all water-containing compartments, including, but not limited to, bilges, ballast tanks, live wells, and engine cooling systems.
(C)Treatment of exterior surfaces and all water-contact components using heated water or other department-approved methods demonstrated to achieve mortality of invasive species.
(D)Flushing or treatment of internal systems, including engines, ballast systems, and plumbing, in a manner sufficient to eliminate viable invasive mussels.
(3)(A)Standards and procedures established by the department shall, at a minimum, be compliant with the Uniform Minimum Protocols and Standards for Watercraft Interception Programs for Dreissenid Mussels in the Western United States prepared by the Pacific States Marine Fisheries Commission that have been developed for invasive dreissenid mussels.
(B)The standards and procedures shall be informed by the best available science.
(C)The department may consult with water agencies and recreational boaters to develop the standards and procedures.
(3)(4)The department shall implement subdivision (a) this chapter in a manner consistent with the requirements for decontamination described in paragraph (2) regardless of whether the department has adopted standards and procedures for decontamination pursuant to paragraph (1).
(c)(b)Before launch into the waters of the state, a conveyance shall be subject to decontamination or quarantine if a qualified inspector determines under this chapter that any of the following conditions exist:
(1)Invasive mussels are detected or reasonably suspected to be present on or in the conveyance.
(2)The conveyance has been operated in or transported from an infested waterbody.
(3)The conveyance contains water in compartments, systems, or structures that cannot be completely drained.
(4)The inspecting authority determines that the conveyance presents a risk of introducing invasive mussels into waters of the state.(d)(c)If a person refuses to submit to decontamination or quarantine of a conveyance pursuant to subdivision (b) found or reasonably believed to harbor aquatic invasive species, or due to personal hardship is unable to immediately accompany the conveyance for decontamination, a law enforcement officer may detain or impound the conveyance until the decontamination is complete.
(e)(d)The owner of a conveyance that is decontaminated or detained due to failure to cooperate by the owner or person in possession of the conveyance is liable for all costs associated with the decontamination or impoundment, in accordance with the applicable rules promulgated by the department.
(f)(e)Pursuant to Section 818.4 of the Government Code, the department and any other state agency exercising authority under this section shall not be liable to any person for any loss resulting from damage to conveyances as the result of inspection or decontamination, with regard to any determination or authorization made pursuant to this section, provided the department adhered to all rules standards, procedures, and regulations promulgated by the department under this section. chapter.
(f)The department may adopt regulations to implement this section.
SEC. 4.Section 2301.2 is added to the Fish and Game Code, to read:2301.2.(a)The department, including personnel authorized by the department, A licensed inspection and decontamination station may issue an inspection, decontamination, or quarantine certificate to the owner or person in possession of a conveyance that has been inspected pursuant to Section 2301. The certificate shall reflect all of the following:
(1)The name of the department station and of the person qualified inspector who conducted the inspection.
(2)The date, place, and time of the inspection.
(3)Any preventative measures performed or ordered.
(4)Any decontamination performed.
(b)If the department station issues an inspection, decontamination, or quarantine certificate to the owner or person in possession of the conveyance, the department may station shall attach a tamper-proof device to the conveyance. The device may be a seal, tag, or band that prevents the conveyance from coming into contact with waters of the state without being broken.
(c)The department shall establish a required minimum retention period for inspection and decontamination certificates issued under this section.
(d)The department may recognize, by reciprocity, an inspection or decontamination certificate issued by another government entity, if the other governmental entity adheres to the minimum standards for inspection, decontamination, and quarantine established in agreed-upon standard protocols, such as the Uniform Minimum Protocols and Standards for Watercraft Interception Programs for Dreissenid Mussels in the Western United States prepared by the Pacific States Marine Fisheries Commission. pursuant to Section 2301.1.
(e)Pursuant to Section 818.4 of the Government Code, the department and any other state agency exercising authority under this section shall not be liable to any person for any loss resulting from damage to conveyances as the result of inspection or decontamination, with regard to any determination or authorization made pursuant to this section, provided the department adhered to all rules standards, procedures, and regulations promulgated by the department under this section. chapter.
(f) The department may adopt regulations to implement this section.
SEC. 5.Section 2301.3 is added to the Fish and Game Code, to read:2301.3.(a)The department shall have the sole and exclusive authority within the state for developing and implementing a statewide program for the inspection and decontamination of conveyances for aquatic invasive species in accordance with this chapter. The inspection and decontamination program shall consist of licensed inspection and decontamination stations with qualified inspectors that inspect and decontaminate conveyances and issue certificates of compliance to conveyances that meet the requirements of this chapter or notices of noncompliance to conveyances that do not meet the requirements of this chapter.
(b)(1)The inspection and decontamination program shall only be conducted at inspection and decontamination stations licensed by the department and by inspectors who are qualified pursuant to subdivision (a) of Section 2301.4.
(2)A licensed inspection and decontamination station shall do all of the following:
(A)Comply with standards, procedures, and regulations adopted by the department pursuant to this chapter.
(B)Only permit inspection and decontamination by qualified inspectors.
(C)Employ the use of department-approved decontamination equipment, certification documentation, and tamper-proof devices pursuant to subdivision (b) of Section 2301.2.
(D)Use the WID Data Sharing System pursuant to Section 2301.6.
(E)Maintain educational materials regarding aquatic invasive species identification and initiatives such as the clean, drain, dry standard.
(F)Display an identifying sign prescribed by the department in a manner conspicuous to the public that indicates the current qualification status of the station.
(G)Permit the department, or an authorized representative, to access the station for purposes of examining equipment, records, inspection logs, decontamination records, tamper-proof devices, certifications, and related program materials.
(c)(1)The department shall develop standards for the licensing of inspection and decontamination stations. Inspection and decontamination services at the station shall only be performed by a qualified inspector to achieve the standards adopted pursuant to Section 2301.1.
(2)The department shall establish performance standards for a licensed inspection and decontamination station for which compliance is determined through periodic inspections.
(3)The department shall develop and implement a quality assurance program, such as a secret shopper program, to audit inspection and decontamination stations and ensure compliance with department-established standards and procedures pursuant to this chapter.
(d)(1)The license of an inspection and decontamination station shall expire after two years. The department may require passage of a licensing test and ongoing training to renew a stations license.
(2)Failure at any time of a licensed inspection and decontamination station to meet standards established pursuant to this chapter applicable to inspection and decontamination stations shall result in revocation of the stations license.
(3)The department shall provide a licensed inspection and decontamination station with written or electronic notice before revoking its license pursuant to paragraph (2). The notice shall specify the grounds for the revocation.
(4)The department shall develop a process and timeline for a station to contest a license revocation.
(e)The department shall encourage the establishment of a sufficient number of licensed inspection and decontamination stations in locations to ensure reasonable accessibility and convenience of boaters and the control of the spread of invasive mussels.
(f)The department shall post on its internet website a list, compiled by region, of licensed inspection and decontamination stations and identify stations that have been found to be noncompliant with departmental standards and have had their licenses revoked.
(g)A licensed inspection and decontamination station shall annually report to the department all of the following information:
(1)The number of certificates issued to conveyances that meet the requirements of this chapter.
(2)The number of notices of noncompliance issued to conveyances that do not meet the requirements of this chapter.
(3)The number of each invasive species intercepted at the station.
(4)Any other information the department requires.
(h)Licensing fees for inspection and decontamination stations under this section shall be imposed by the department in an amount that does not exceed the reasonable regulatory costs of administering the licensing program.
(i)The department may adopt regulations to implement this section.
SEC. 6.Section 2301.4 is added to the Fish and Game Code, to read:2301.4.(a)To qualify as a qualified inspector, an inspector shall pass a qualification test administered by the department, in addition to meeting any minimum experience and training criteria established by the department.
(b)The department shall establish standards for training, equipment, performance, and data collection for inspection and decontamination stations. The department may do either of the following:
(1)(A)Develop, in consultation with interested stakeholders, a training program and accompanying materials to be used to qualify individuals who apply to perform inspections and decontaminations. The departments training program and accompanying materials shall, at a minimum, align with the Pacific States Marine Fisheries Commissions watercraft inspection and decontamination Level 2 training program.
(B)If the department develops its own training program pursuant to subparagraph (A), the department shall grant qualified inspector status to both of the following upon application of the individual:
(i)An individual with a current Level 2 Inspector and Decontaminator or an Advanced Decontamination training certificate issued by the Pacific States Marine Fisheries Commission.
(ii)An individual with a current training certificate of a training program that adheres to the minimum standards for inspection, decontamination, and quarantine established in the Uniform Minimum Protocols and Standards for Watercraft Interception Programs for Dreissenid Mussels in the Western United States prepared by the Pacific States Marine Fisheries Commission.
(2)In lieu of developing its own training program pursuant to paragraph (1), grant qualified inspector status to individuals who have completed the Pacific States Marine Fisheries Commissions watercraft inspection and decontamination Level 2 training program.
(c)The department shall prescribe training and periodic retraining courses for qualified inspectors.
(d)(1)A qualified inspectors qualification shall expire after two years. The department may require passage of a qualification test and ongoing training to renew an inspectors qualification.
(2)Failure at any time of a qualified inspector to meet standards established pursuant to this chapter applicable to qualified inspectors shall result in disqualification to inspect and decontaminate conveyances.
(3)The department shall provide a qualified inspector and the relevant licensed inspection and decontamination station with written or electronic notice before imposing a disqualification pursuant to paragraph (2). The notice shall specify the grounds for the disqualification.
(4)The department shall develop a process and timeline for a qualified inspector to contest a disqualification.
(e)The department shall develop standards for qualifying institutions and instructors for purposes of providing training of qualified inspectors. The standards shall include criteria for manuals, textbooks, equipment, exercises, hands-on work, examinations, and other matters the department determines necessary for a course of instruction. The standards shall also specify the conditions under which an institution or instructor may be disqualified to train qualified instructors, and how a disqualified institution or instructor may regain qualification. The department shall make the standards available on its internet website.
(f)Qualification fees for qualified inspectors under subdivision (a) and qualified institutions and instructors under subdivision (e) shall be imposed by the department in an amount that does not exceed the reasonable regulatory costs of administering the qualification program.
(g)The department may adopt regulations to implement this section.
SEC. 7.Section 2301.6 is added to the Fish and Game Code, to read:2301.6.(a)The department shall use the Regional Watercraft Inspection and Decontamination (WID) Data Sharing System managed by the Colorado Parks and Wildlife Division of the Colorado Department of Natural Resources for tracking the movement of conveyances, equipment, and other vectors among California waterbodies.
(b)An inspection and decontamination station shall enter each inspected, decontaminated, or quarantined conveyance into the WID Data Sharing System.
(c)The manager of a waterbody of the state that has a staffed launch point shall register each launching conveyance into the WID Data Sharing System.
(d)The department shall provide guidance to entities that own or manage reservoirs, as defined in Section 6004.5 of the Water Code, or other launch points, on how to track decontaminated and inspected conveyances in the WID Data Sharing System.
(e)The department shall encourage the use of the WID Data Sharing System across the state.
SEC. 8.Section 2301.7 is added to the Fish and Game Code, to read:2301.7.(a)The department shall encourage public or private agencies that operate a water supply system to enter into reciprocity agreements with other agencies to allow the launch of conveyances without quarantine or decontamination for conveyances moving between waterbodies operated by those agencies.
(b)A public or private agency that operates a water supply system shall notify the department of a reciprocity agreement entered into pursuant to subdivision (a).
(c)The department shall maintain a comprehensive list of reciprocity agreements on its internet website.
SEC. 5.SEC. 9.Section 2303 of the Fish and Game Code is amended to read:2303.For purposes of this chapter, invasive the following definitions apply:
(a)Invasive mussel means any nonnative biofouling mussel species that is capable of spreading in freshwater and is listed in a regulation adopted by the commission pursuant to Section 2118.
(b)Licensed inspection and decontamination station means an inspection and decontamination station that has been licensed by the department pursuant to paragraph (1) of subdivision (c) of Section 2301.3.
(c)Qualified inspector means an inspector that passes a qualification test administered by the department, in addition to meeting any minimum experience and training criteria established by the department pursuant to subdivision (a) of Section 2301.4.
(d)WID Data Sharing System means the Regional Watercraft Inspection and Decontamination Data Sharing System managed by the Colorado Parks and Wildlife Division of the Colorado Department of Natural Resources described in subdivision (a) of Section 2301.6.
SEC. 10.Chapter 3.6 (commencing with Section 2305) is added to Division 3 of the Fish and Game Code, to read:3.6.Nonmotorized Vessel Invasive Mussel Infestation Prevention Fee2305.(a)(1)On or before January 1, 2028, the department shall collect, in addition to any other fee imposed under existing law, an invasive mussel infestation prevention fee from each nonmotorized vessel owner for each nonmotorized vessel launched into waters of the state.
(2)The fee shall be twenty dollars ($20) per nonmotorized vessel every two years.
(3)The amount in paragraph (2) shall be adjusted for inflation every odd-numbered year using the California Consumer Price Index to the nearest whole dollar value.
(4)Notwithstanding paragraphs (2) and (3), the fee shall not exceed the reasonable regulatory costs of the state to implement this chapter.
(b)Upon payment of the invasive mussel infestation prevention fee pursuant to subdivision (a), the department shall issue an invasive mussel infestation prevention sticker to the vessel owner, to be affixed to the nonmotorized vessel in a manner deemed appropriate by the division.
(c)(1)A nonmotorized vessel operator may be issued a citation for operating the vessel in nonmarine waters without a valid state-issued invasive mussel infestation prevention sticker. A citation issued pursuant to this section shall not exceed twice the cost of the sticker.
(2)Section 12000 does not apply to a violation of this chapter.
(d)Any evidence of tampering with the invasive mussel infestation prevention sticker shall void the sticker.
(e)(1)All revenues collected from the fee pursuant to subdivision (a) shall be deposited into the Nonmotorized Vessel Invasive Mussel Infestation Prevention Account, which is hereby created within the Harbors and Watercraft Revolving Fund. Upon appropriation by the Legislature, moneys in the account shall be expended solely for the purposes set forth in subdivision (a) of Section 2306. None of the revenues collected from the fee pursuant to subdivision (a) shall be used for any purpose other than those explicitly authorize by subdivision (a) of Section 2306.
(2)Revenues collected from any citation issued under subdivision (c) shall be deposited into the Nonmotorized Vessel Invasive Mussel Infestation Prevention Penalty Account, which is hereby created within the Harbors and Watercraft Revolving Fund. Upon appropriation by the Legislature, moneys in the account shall be expended solely for the purposes set forth in subdivision (c) of Section 2306.
(f)The department may contract with another state agency, a vendor, or an authorized license agent for the issuance of the sticker described in subdivision (b).
(g)The division shall develop educational materials to be provided before issuance of the sticker described in subdivision (b).
2306.(a)Moneys deposited into the Nonmotorized Vessel Invasive Mussel Infestation Prevention Account pursuant to Section 2305 shall be available, upon appropriation by the Legislature, for the following purposes:
(1)For reasonable regulatory costs, not to exceed 15 percent of the revenues deposited into the account, of the department or other entity issuing stickers pursuant to subdivision (b) of Section 2306 and of administering this chapter.
(2)For the divisions reasonable regulatory costs, not to exceed 10 percent of the revenues deposited into the account, to administer the grants pursuant to paragraph (3).
(3)For an amount not less than 40 percent of the remaining revenues deposited into the account for grants to entities subject to subdivision (a) of Section 2302 for the reasonable regulatory costs incident to the implementation of an invasive mussel infestation prevention plan that is consistent with the requirements of Section 2302. For purposes of this paragraph, reasonable regulatory costs include costs associated with the investigation and inspection of a nonmotorized vessel for the presence of invasive mussels before contact with a reservoir.
(b)For purposes of awarding grants pursuant to paragraph (3) of subdivision (a), the division shall do all of the following:
(1)Give priority to invasive mussel infestation prevention that is consistent with Section 2302 and that also includes visual and manual inspection standards and other infestation prevention procedures consistent with either the Natural Resources Agencys Invasive Mussel Guidebook for Recreational Water Managers and Users, dated September 2010, or the Natural Resources Agencys California Aquatic Invasive Species Management Plan, dated January 2008, or similar guidebooks and management plans subsequently adopted by the Natural Resources Agency.
(2)Take into consideration the benefits of regional-scale invasive mussel infestation prevention plans and coordination to contain the spread of invasive mussels.
(3)Take into consideration the unique economic, ecological, and recreational impacts to rural and urban reservoirs from invasive mussel infestation.
(4)Take into consideration the value of continued recreational access and public use of the recreational areas.
(c)Moneys deposited into the Nonmotorized Vessel Invasive Mussel Infestation Prevention Penalty Account pursuant to Section 2305 shall be available, upon appropriation by the Legislature, for both of the following:
(1)For grants to entities who have an approved control plan pursuant to subdivision (d) of Section 2301 for activities that reduce the risk of the overland spread of invasive mussels.
(2)For the division to generate and distribute educational materials and signage that do all of the following:
(A)Inform vessel operators and the public about the impact of invasive mussels on the environment and the waterways of the state.
(B)Encourage vessel operators to enact behaviors that reduce the risk of invasive mussel infestation, including the clean, drain, dry standard.
(C)Support the development of educational materials provided pursuant to subdivision (g) of Section 2305.
(d)As a condition of receiving grant funding pursuant to this section, an entity receiving funding shall report to the division data, as deemed appropriate by the division, regarding invasive mussel prevention and inspection programs and control programs implemented with the funding.
2307.For purposes of this chapter, the following definitions apply:
(a)Division means the Division of Boating and Waterways within the Department of Parks and Recreation.
(b)(1)Nonmotorized vessel means an inflatable or rigid vessel, including any of the following:
(A)Canoe.
(B)Kayak.
(C)Rowing boat.
(D)Sailboat shorter than eight feet.
(E)Sailboard or parasail.
(F)Raft.
(G)Paddleboard.
(2)Nonmotorized vessel does not include either of the following:
(A)A vessel that will only be in marine waters.
(B)A vessel required to be registered pursuant to Chapter 2 (commencing with Section 9850) of Division 3.5 of the Vehicle Code.
(c)Harbors and Watercraft Revolving Fund means the Harbors and Watercraft Revolving Fund created pursuant to Section 85 of the Harbors and Navigation Code.
(d)Marine waters means those waters subject to tidal influence.
(e)Reservoir has the same meaning as defined in Section 6004.5 of the Water Code.
(f)Waters of this state means any waters within the territorial limits of this state.
SEC. 6.SEC. 11.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
(a)The Legislature finds and declares all of the following:
(1)Aquatic invasive species, including the golden mussel, threaten the ecological health, recreational value, and operational integrity of Californias lakes, rivers, reservoirs, and water conveyance facilities.
(2)Efforts to control or prevent the spread of the golden mussel and other aquatic invasive species result in extensive operational and economic impacts to water delivery and hydropower, and have increasingly limited public access to recreational opportunities such as boating, fishing, and other water-dependent activities.
(3)The increasing costs of mandatory decontamination, quarantine requirements, and aquatic invasive species fees are disproportionately paid for by the recreational boating community, which cannot bear alone the financial responsibility of managing this statewide threat.
(4)The Harbors and Watercraft Revolving Fund, established in Section 85 of the Harbors and Navigation Code, is structurally imbalanced and remains in deficit, thereby requiring the identification and adoption of alternative and sustainable funding sources to support statewide aquatic invasive species prevention and mitigation programs.
(5)Establishing uniform statewide standards for vessel decontamination, including standards applicable to both motorized and nonmotorized paddlecraft, along with a system of information sharing and reciprocity among waterbodies, will improve efficiency, protect natural resources, and support Californias economic and recreational interests.
(6)Inspection programs help prevent the spread of aquatic species via transportation conveyances. These programs provide for the inspection and decontamination of conveyances, as well as an opportunity for outreach and education on the risks posed by the introduction and spread of aquatic invasive species. The programs protect both the environmental and recreational values of the states waters, infrastructure, and economy.
(b)It is the intent of the Legislature in enacting this bill to accomplish both of the following:
(1)Create a statewide database to voluntarily track the movement of vessels, equipment, and other vectors among California waterbodies, providing waterbody managers with accurate information on the prior contamination status of these vessels.
(2)Develop a system of reciprocity that recognizes and honors certifications of decontamination for vessels and equipment moving between noninfested waterbodies, thereby facilitating safe recreational access.
(c)It is the intent of the Legislature to subsequently amend this bill to identify and implement, to the extent feasible, alternative and equitable funding sources beyond fees imposed on the recreational boating community, such as assessments on commercial activities, including on international cargo shipping operations that may impact the introduction of aquatic invasive species to California waters.
SEC. 2.Section 2301 of the Fish and Game Code is amended to read:2301.(a)(1)Except as authorized by the department, a person shall not possess, import, ship, or transport in the state, or place, plant, or cause to be placed or planted in any water within the state, invasive mussels.
(2)The director or the directors designee may do all of the following:
(A)Conduct inspections of conveyances, which include vehicles, boats and other watercraft, containers, and trailers, that may carry or contain adult or larval invasive mussels. Included as part of this authority to conduct inspections is the authority to temporarily stop conveyances that may carry or contain adult or larval invasive mussels on any roadway or waterway in order to conduct inspections.
(B)(i)Order that areas in a conveyance that contain water be drained, dried, or decontaminated pursuant to procedures approved by the department.
(ii)An order to dry pursuant to clause (i) may require the owner or person in possession of the conveyance to dry the conveyance for a designated period of time, not to exceed 30 days, before launching into waters of the state. A conveyance shall not be launched until the required drying period has been completed.
(iii)If issued an order to dry pursuant to clause (i), an owner or person in possession of the conveyance may retain possession of the conveyance during the drying period, subject to any requirements established by the department.
(C)Impound or quarantine conveyances in locations designated by the department for the period of time necessary to ensure that invasive mussels can no longer live on or in the conveyance.
(D)(i)Conduct inspections of waters of the state and facilities located within waters of the state that may contain invasive mussels. If invasive mussels are detected or may be present, the director or the directors designee may order the affected waters or facilities closed to conveyances or otherwise restrict access to the affected waters or facilities, and shall order that conveyances removed from, or introduced to, the affected waters or facilities be inspected, quarantined, or disinfected in a manner and for a duration necessary to detect and prevent the spread of invasive mussels within the state.
(ii)For the purpose of implementing clause (i), the director or the directors designee shall order the closure or quarantine of, or restrict access to, these waters, areas, or facilities in a manner and duration necessary to detect and prevent the spread of invasive mussels within the state. A closure, quarantine, or restriction shall not be authorized by the director or the directors designee without the concurrence of the Secretary of the Natural Resources Agency. If a closure lasts longer than seven days, the department shall update the operator of the affected facility every 10 days on efforts to address the invasive mussel infestation. The department shall provide these updates in writing and also post these updates on the departments internet website in an easily accessible manner.
(iii)The department shall develop procedures to ensure proper notification of affected local and federal agencies, and, as appropriate, the Department of Water Resources, the Department of Parks and Recreation, and the State Lands Commission in the event of a decision to close, quarantine, or restrict a facility pursuant to this paragraph. These procedures shall include the reasons for the closure, quarantine, or restriction, and methods for providing updated information to those affected. These procedures shall also include protocols for the posting of the notifications on the departments internet website required by clause (ii).
(iv)When deciding the scope, duration, level, and type of restrictions, and specific location of a closure or quarantine, the director shall consult with the agency, entity, owner, or operator with jurisdiction, control, or management responsibility over the marina, boat launch facility, or other facility, in order to focus the closure or quarantine to specific areas and facilities so as to avoid or minimize disruption of economic or recreational activity in the vicinity.
(b)(1)Upon a determination by the director that it would further the purposes of this section, other parties or state agencies, including, but not limited to, the Department of Parks and Recreation, the Department of Water Resources, the Department of Food and Agriculture, and the State Lands Commission, may exercise the authority, or portions of that authority, granted to the department in subdivision (a).
(2)A determination made pursuant to paragraph (1) shall be in writing and shall remain in effect until withdrawn, in writing, by the director.
(c)(1)Except as provided in paragraph (2), Division 13 (commencing with Section 21000) of the Public Resources Code does not apply to the implementation of this section.
(2)An action undertaken pursuant to subparagraph (B) of paragraph (2) of subdivision (a) involving the use of chemicals other than salt or hot water to decontaminate a conveyance or a facility is subject to Division 13 (commencing with Section 21000) of the Public Resources Code.
(d)(1)A public or private agency that operates a water supply system shall cooperate with the department to implement measures to avoid infestation by invasive mussels and to control or eradicate any infestation that may occur in a water supply system. If invasive mussels are detected, the operator of the water supply system, in cooperation with the department, shall prepare and implement a plan to control or eradicate invasive mussels within the system to minimize or eliminate the spread of an invasive mussel. The approved plan shall contain the following minimum elements:
(A)Methods for delineation of infestation, including both adult mussels and veligers.
(B)Methods for control or eradication of adult mussels and decontamination of water containing larval mussels.
(C)A systematic monitoring program to determine any changes in conditions.
(D)The requirement that the operator of the water supply system permit inspections by the department as well as cooperate with the department to update or revise control or eradication measures in the approved plan to address scientific advances in the methods of controlling or eradicating mussels and veligers.
(2)If the operator of water delivery and storage facilities for public water supply purposes has prepared, initiated, and is in compliance with all the elements of an approved plan to control or eradicate invasive mussels in accordance with paragraph (1), the requirements of subdivision (a) do not apply to the operation of those water delivery and storage facilities, and the operator is not subject to any civil or criminal liability for the introduction of invasive mussel species as a result of those operations. The department may require the operator of a facility to update its plan, and if the plan is not updated or revised as described in this subdivision, subdivision (a) shall apply to the operation of the water delivery and storage facilities covered by the plan until the operator updates or revises the plan and initiates and complies with all of the elements of the updated or revised plan.
(3)On or before December 31, 2026, the department shall review all approved plans pursuant to this subdivision. The department shall require water supply system operators to update the plans to address all invasive mussel species present in their system as of January 1, 2026, on or before September 30, 2027.
(4)Every invasive mussel species detected in a water supply system after January 1, 2026, shall be addressed in a plan pursuant to this subdivision no later than 180 days from the date the species is detected. The department shall approve plans or provide written comments and suggestions on plan deficiencies within 180 days from the date of plan submission.
(e)Any entity that discovers invasive mussels within this state shall immediately report the discovery to the department.
(f)(1)In addition to any other penalty provided by law, any person who violates this section, violates any verbal or written order or regulation adopted pursuant to this section, or who resists, delays, obstructs, or interferes with the implementation of this section, is subject to a penalty, in an amount not to exceed one thousand dollars ($1,000), that is imposed administratively by the department.
(2)A penalty shall not be imposed pursuant to paragraph (1) unless the department has adopted regulations specifying the amount of the penalty and the procedure for imposing and appealing the penalty.
(g)The department may adopt regulations to carry out this section.
(h)Pursuant to Section 818.4 of the Government Code, the department and any other state agency exercising authority under this section shall not be liable with regard to any determination or authorization made pursuant to this section.
(i)This section shall remain in effect only until January 1, 2030, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2030, deletes or extends that date.
SEC. 3.Section 2301.1 is added to the Fish and Game Code, to read:2301.1.(a)The department, including personnel authorized by the department, may decontaminate or order the decontamination of a conveyance found or reasonably believed to harbor aquatic invasive species after an inspection conducted pursuant to Section 2301.
(b)(1)The department shall establish standards and procedures for decontaminating conveyances and disposing of organisms and organic materials. These standards and procedures shall be effective at removing or destroying invasive mussels and shall be performed in a manner that ensures no viable invasive mussels remain on or in the conveyance before launch.
(2)At a minimum, decontamination shall include all of the following:
(A)Removal of all visible plant materials, mud, and organisms from the conveyance and any associated equipment.
(B)Draining of all water-containing compartments, including, but not limited to, bilges, ballast tanks, live wells, and engine cooling systems.
(C)Treatment of exterior surfaces and all water-contact components using heated water or other department-approved methods demonstrated to achieve mortality of invasive species.
(D)Flushing or treatment of internal systems, including engines, ballast systems, and plumbing, in a manner sufficient to eliminate viable invasive mussels.
(3)The department shall implement subdivision (a) in a manner consistent with the requirements for decontamination described in paragraph (2) regardless of whether the department has adopted standards and procedures for decontamination pursuant to paragraph (1).
(c)Before launch into the waters of the state, a conveyance shall be subject to decontamination if any of the following conditions exist:
(1)Invasive mussels are detected or reasonably suspected to be present on or in the conveyance.
(2)The conveyance has been operated in or transported from an infested waterbody.
(3)The conveyance contains water in compartments, systems, or structures that cannot be completely drained.
(4)The inspecting authority determines that the conveyance presents a risk of introducing invasive mussels into waters of the state.
(d)If a person refuses to submit to decontamination of a conveyance found or reasonably believed to harbor aquatic invasive species, or due to personal hardship is unable to immediately accompany the conveyance for decontamination, a law enforcement officer may detain or impound the conveyance until the decontamination is complete.
(e)The owner of a conveyance that is decontaminated or detained due to failure to cooperate by the owner or person in possession of the conveyance is liable for all costs associated with the decontamination or impoundment, in accordance with the applicable rules promulgated by the department.
(f)Pursuant to Section 818.4 of the Government Code, the department and any other state agency exercising authority under this section shall not be liable to any person for any loss resulting from damage to conveyances as the result of inspection or decontamination, provided the department adhered to all rules promulgated by the department under this section.
SEC. 4.Section 2301.2 is added to the Fish and Game Code, to read:2301.2.(a)The department, including personnel authorized by the department, may issue an inspection, decontamination, or quarantine certificate to the owner or person in possession of a conveyance that has been inspected pursuant to Section 2301. The certificate shall reflect all of the following:
(1)The name of the department and of the person who conducted the inspection.
(2)The date, place, and time of the inspection.
(3)Any preventative measures performed or ordered.
(4)Any decontamination performed.
(b)If the department issues an inspection, decontamination, or quarantine certificate to the owner or person in possession of the conveyance, the department may attach a tamper-proof device to the conveyance. The device may be a seal, tag, or band that prevents the conveyance from coming into contact with waters of the state without being broken.
(c)The department shall establish a required retention period for inspection and decontamination certificates issued under this section.
(d)The department may recognize, by reciprocity, an inspection or decontamination certificate issued by another government entity, if the other governmental entity adheres to the minimum standards for inspection, decontamination, and quarantine established in agreed-upon standard protocols, such as the Uniform Minimum Protocols and Standards for Watercraft Interception Programs for Dreissenid Mussels in the Western United States prepared by the Pacific States Marine Fisheries Commission.
(e)Pursuant to Section 818.4 of the Government Code, the department and any other state agency exercising authority under this section shall not be liable to any person for any loss resulting from damage to conveyances as the result of inspection or decontamination, provided the department adhered to all rules promulgated by the department under this section.
SEC. 3.SEC. 5.Section 2303 of the Fish and Game Code is amended to read:2303.For purposes of this chapter, invasive mussel means any nonnative biofouling mussel species that is capable of spreading in freshwater and is listed in a regulation adopted by the commission pursuant to Section 2118.
SEC. 4.Section 2304 is added to the Fish and Game Code, to read:2304.The department, in consultation with the Department of Parks and Recreation and the Department of Food and Agriculture, shall develop a voluntary framework to prevent the overland spread of invasive mussels through the conveyance of watercraft overland. The framework shall include all of the following:(a)Minimum standards for watercraft inspection, decontamination, and quarantine based on best available science and aligned with national standards as feasible.(b)A banding program or other mechanisms by which to confirm the inspection, decontamination, or quarantine status of a watercraft.(c)Training and quality assurance metrics to encourage consistent inspection, decontamination, and tracking of vessels across waterbodies.(d)A publicly available list of participating inspection and decontamination services statewide.(e)Education and outreach opportunities and materials to reduce the spread of invasive mussels and encourage compliance with and participation in the framework.SEC. 5.SEC. 6.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
(a)The Legislature finds and declares all of the following:
(1)Aquatic invasive species, including the golden mussel, threaten the ecological health, recreational value, and operational integrity of Californias lakes, rivers, reservoirs, and water conveyance facilities.
(2)Efforts to control or prevent the spread of the golden mussel and other aquatic invasive species result in extensive operational and economic impacts to water delivery and hydropower, and have increasingly limited public access to recreational opportunities such as boating, fishing, and other water-dependent activities.
(3)The increasing costs of mandatory decontamination, quarantine requirements, and aquatic invasive species fees are disproportionately paid for by the recreational boating community, which cannot bear alone the financial responsibility of managing this statewide threat.
(4)The Harbors and Watercraft Revolving Fund, established in Section 85 of the Harbors and Navigation Code, is structurally imbalanced and remains in deficit, thereby requiring the identification and adoption of alternative and sustainable funding sources to support statewide aquatic invasive species prevention and mitigation programs.
(5)Establishing uniform statewide standards for vessel decontamination, including standards applicable to both motorized and nonmotorized paddlecraft, along with a system of information sharing and reciprocity among waterbodies, will improve efficiency, protect natural resources, and support Californias economic and recreational interests.
(b)It is the intent of the Legislature to enact subsequent legislation that would in enacting this bill to accomplish all both of the following:
(1)Address and prevent the spread of aquatic invasive species, including, but not limited to, the golden mussel, which currently represents an urgent and significant threat to the states water resources, in Californias waterbodies and water infrastructure systems.(2)Establish a statewide standard for the decontamination of all waterborne vessels and equipment, including motorized vessels, paddlecraft, and other potential vectors capable of transmitting aquatic invasive species, including the golden mussel.(3)(1)Create a statewide database to voluntarily track the movement of vessels, equipment, and other vectors among California waterbodies, providing waterbody managers with accurate information on the prior contamination status of these vessels.
(4)(2)Develop a system of reciprocity that recognizes and honors certifications of decontamination for vessels and equipment moving between noninfested waterbodies, thereby facilitating safe recreational access.
(5)Identify and implement, to the extent feasible, alternative and equitable funding sources beyond fees imposed on the recreational boating community, such as assessments on commercial activities, including on international cargo shipping operations that may impact the introduction of aquatic invasive species to California waters.(c)It is the intent of the Legislature to subsequently amend this bill to identify and implement, to the extent feasible, alternative and equitable funding sources beyond fees imposed on the recreational boating community, such as assessments on commercial activities, including on international cargo shipping operations that may impact the introduction of aquatic invasive species to California waters.
SEC. 2.Section 2301 of the Fish and Game Code is amended to read:2301.(a)(1)Except as authorized by the department, a person shall not possess, import, ship, or transport in the state, or place, plant, or cause to be placed or planted in any water within the state, invasive mussels.
(2)The director or the directors designee may do all of the following:
(A)Conduct inspections of conveyances, which include vehicles, boats and other watercraft, containers, and trailers, that may carry or contain adult or larval invasive mussels. Included as part of this authority to conduct inspections is the authority to temporarily stop conveyances that may carry or contain adult or larval invasive mussels on any roadway or waterway in order to conduct inspections.
(B)Order that areas in a conveyance that contain water be drained, dried, or decontaminated pursuant to procedures approved by the department.
(C)Impound or quarantine conveyances in locations designated by the department for the period of time necessary to ensure that invasive mussels can no longer live on or in the conveyance.
(D)(i)Conduct inspections of waters of the state and facilities located within waters of the state that may contain invasive mussels. If invasive mussels are detected or may be present, the director or the directors designee may order the affected waters or facilities closed to conveyances or otherwise restrict access to the affected waters or facilities, and shall order that conveyances removed from, or introduced to, the affected waters or facilities be inspected, quarantined, or disinfected in a manner and for a duration necessary to detect and prevent the spread of invasive mussels within the state.
(ii)For the purpose of implementing clause (i), the director or the directors designee shall order the closure or quarantine of, or restrict access to, these waters, areas, or facilities in a manner and duration necessary to detect and prevent the spread of invasive mussels within the state. A closure, quarantine, or restriction shall not be authorized by the director or the directors designee without the concurrence of the Secretary of the Natural Resources Agency. If a closure lasts longer than seven days, the department shall update the operator of the affected facility every 10 days on efforts to address the invasive mussel infestation. The department shall provide these updates in writing and also post these updates on the departments internet website in an easily accessible manner.
(iii)The department shall develop procedures to ensure proper notification of affected local and federal agencies, and, as appropriate, the Department of Water Resources, the Department of Parks and Recreation, and the State Lands Commission in the event of a decision to close, quarantine, or restrict a facility pursuant to this paragraph. These procedures shall include the reasons for the closure, quarantine, or restriction, and methods for providing updated information to those affected. These procedures shall also include protocols for the posting of the notifications on the departments internet website required by clause (ii).
(iv)When deciding the scope, duration, level, and type of restrictions, and specific location of a closure or quarantine, the director shall consult with the agency, entity, owner, or operator with jurisdiction, control, or management responsibility over the marina, boat launch facility, or other facility, in order to focus the closure or quarantine to specific areas and facilities so as to avoid or minimize disruption of economic or recreational activity in the vicinity.
(b)(1)Upon a determination by the director that it would further the purposes of this section, other parties or state agencies, including, but not limited to, the Department of Parks and Recreation, the Department of Water Resources, the Department of Food and Agriculture, and the State Lands Commission, may exercise the authority, or portions of that authority, granted to the department in subdivision (a).
(2)A determination made pursuant to paragraph (1) shall be in writing and shall remain in effect until withdrawn, in writing, by the director.
(c)(1)Except as provided in paragraph (2), Division 13 (commencing with Section 21000) of the Public Resources Code does not apply to the implementation of this section.
(2)An action undertaken pursuant to subparagraph (B) of paragraph (2) of subdivision (a) involving the use of chemicals other than salt or hot water to decontaminate a conveyance or a facility is subject to Division 13 (commencing with Section 21000) of the Public Resources Code.
(d)(1)A public or private agency that operates a water supply system shall cooperate with the department to implement measures to avoid infestation by invasive mussels and to control or eradicate any infestation that may occur in a water supply system. If invasive mussels are detected, the operator of the water supply system, in cooperation with the department, shall prepare and implement a plan to control or eradicate invasive mussels within the system, and system to minimize or eliminate or minimize any potential downstream transport the spread of an invasive mussel. The approved plan shall contain the following minimum elements:
(A)Methods for delineation of infestation, including both adult mussels and veligers.
(B)Methods for control or eradication of adult mussels and decontamination of water containing larval mussels.
(C)A systematic monitoring program to determine any changes in conditions.
(D)The requirement that the operator of the water supply system permit inspections by the department as well as cooperate with the department to update or revise control or eradication measures in the approved plan to address scientific advances in the methods of controlling or eradicating mussels and veligers.
(2)If the operator of water delivery and storage facilities for public water supply purposes has prepared, initiated, and is in compliance with all the elements of an approved plan to control or eradicate invasive mussels in accordance with paragraph (1), the requirements of subdivision (a) do not apply to the operation of those water delivery and storage facilities, and the operator is not subject to any civil or criminal liability for the introduction of invasive mussel species as a result of those operations. The department may require the operator of a facility to update its plan, and if the plan is not updated or revised as described in this subdivision, subdivision (a) shall apply to the operation of the water delivery and storage facilities covered by the plan until the operator updates or revises the plan and initiates and complies with all of the elements of the updated or revised plan.
(3)On or before December 31, 2026, the department shall review all approved plans pursuant to this subdivision and require all plans that do not specifically address all invasive mussel species known to be present in bodies of water in the state subdivision. The department shall require water supply system operators to update the plans to address all invasive mussel species present in their system as of January 1, 2026, to be updated or revised appropriately to include all invasive mussel species, on or before on or before September 30, 2027.
(4)Every invasive mussel species detected in a water supply system after January 1, 2026, shall be addressed in a plan pursuant to this subdivision no later than 180 days from the date that the species is listed in a regulation as described in Section 2303. detected. The department shall approve plans or provide written comments and suggestions on plan deficiencies within 180 days from the date of plan submission.
(e)Any entity that discovers invasive mussels within this state shall immediately report the discovery to the department.
(f)(1)In addition to any other penalty provided by law, any person who violates this section, violates any verbal or written order or regulation adopted pursuant to this section, or who resists, delays, obstructs, or interferes with the implementation of this section, is subject to a penalty, in an amount not to exceed one thousand dollars ($1,000), that is imposed administratively by the department.
(2)A penalty shall not be imposed pursuant to paragraph (1) unless the department has adopted regulations specifying the amount of the penalty and the procedure for imposing and appealing the penalty.
(g)The department may adopt regulations to carry out this section.
(h)Pursuant to Section 818.4 of the Government Code, the department and any other state agency exercising authority under this section shall not be liable with regard to any determination or authorization made pursuant to this section.
(i)This section shall remain in effect only until January 1, 2030, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2030, deletes or extends that date.
SEC. 3.Section 2303 of the Fish and Game Code is amended to read:2303.For purposes of this chapter, invasive mussel means any nonnative detrimental biofouling mussel species that is capable of spreading in freshwater and is listed in a regulation adopted by the commission pursuant to Section 2118.
SEC. 4.Section 2304 is added to the Fish and Game Code, to read:2304.The department, in consultation with the Department of Parks and Recreation and the Department of Food and Agriculture, shall develop a voluntary framework to prevent the overland spread of invasive mussels through the conveyance of watercraft overland. The framework shall include all of the following:
(a)Minimum standards for watercraft inspection, decontamination, and quarantine based on best available science and aligned with national standards as feasible.
(b)A banding program or other mechanisms by which to confirm the inspection, decontamination, or quarantine status of a watercraft.
(c)Training and quality assurance metrics to encourage consistent inspection, decontamination, and tracking of vessels across waterbodies.
(d)A publicly available list of participating inspection and decontamination services statewide.
(e)Education and outreach opportunities and materials to reduce the spread of invasive mussels and encourage compliance with and participation in the framework.
SEC. 5.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
(a)The Legislature finds and declares all of the following:
(1)Aquatic invasive species, including the golden mussel, threaten the ecological health, recreational value, and operational integrity of Californias lakes, rivers, reservoirs, and water conveyance facilities.
(2)Efforts to control or prevent the spread of the golden mussel and other aquatic invasive species result in extensive operational and economic impacts to water delivery and hydropower, and have increasingly limited public access to recreational opportunities such as boating, fishing, and other water-dependent activities.
(3)The increasing costs of mandatory decontamination, quarantine requirements, and aquatic invasive species fees are disproportionately paid for by the recreational boating community, which cannot bear alone the financial responsibility of managing this statewide threat.
(4)The Harbors and Watercraft Revolving Fund, established in Section 85 of the Harbors and Navigation Code, is structurally imbalanced and remains in deficit, thereby requiring the identification and adoption of alternative and sustainable funding sources to support statewide aquatic invasive species prevention and mitigation programs.
(5)Establishing uniform statewide standards for vessel decontamination, including standards applicable to both motorized and nonmotorized paddlecraft, along with a system of information sharing and reciprocity among waterbodies, will improve efficiency, protect natural resources, and support Californias economic and recreational interests.
(b)It is the intent of the Legislature to enact subsequent legislation that would accomplish all of the following:
(1)Address and prevent the spread of aquatic invasive species, including, but not limited to, the golden mussel, which currently represents an urgent and significant threat to the states water resources, in Californias waterbodies and water infrastructure systems.
(2)Establish a statewide standard for the decontamination of all waterborne vessels and equipment, including motorized vessels, paddlecraft, and other potential vectors capable of transmitting aquatic invasive species, including the golden mussel.
(3)Create a statewide database to voluntarily track the movement of vessels, equipment, and other vectors among California waterbodies, providing waterbody managers with accurate information on the prior contamination status of these vessels.
(4)Develop a system of reciprocity that recognizes and honors certifications of decontamination for vessels and equipment moving between noninfested waterbodies, thereby facilitating safe recreational access.
(5)Identify and implement, to the extent feasible, alternative and equitable funding sources beyond fees imposed on the recreational boating community, such as assessments on commercial activities, including on international cargo shipping operations that may impact the introduction of aquatic invasive species to California waters.
|
Date
|
Status
|
|---|---|
| Aug 13, 2026 | In committee: Held under submission. |
| Aug 3, 2026 | In committee: Referred to APPR. suspense file. |
| Jul 1, 2026 | From committee: Do pass and re-refer to Com. on APPR. (Ayes 13. Noes 0.) (June 30). Re-referred to Com. on APPR. |
| Jun 25, 2026 | From committee chair, with author's amendments: Amend, and re-refer to committee. Read second time, amended, and re-referred to Com. on JUD. |
| Jun 24, 2026 | From committee: Do pass and re-refer to Com. on JUD. (Ayes 6. Noes 0.) (June 23). Re-referred to Com. on JUD. |
| Jun 15, 2026 | From committee chair, with author's amendments: Amend, and re-refer to committee. Read second time, amended, and re-referred to Com. on N.R. & W. |
| Jun 10, 2026 | Referred to Coms. on N.R. & W. and JUD. |
| May 28, 2026 | In Senate. Read first time. To Com. on RLS. for assignment. |
| May 27, 2026 | Read third time. Passed. Ordered to the Senate. (Ayes 79. Noes 0. Page 5449.) |
| May 27, 2026 | Read third time. Passed. Ordered to the Senate. (Ayes 79. Noes 0.) |
| May 27, 2026 | Read third time. Passed. Ordered to the Senate. |
| May 18, 2026 | Read second time. Ordered to third reading. |
| May 14, 2026 | Joint Rule 62(a), file notice suspended. (Page 5030.) |
| May 14, 2026 | From committee: Do pass. (Ayes 15. Noes 0.) (May 14). |
| May 14, 2026 | Joint Rule 62(a), file notice suspended. |
| May 13, 2026 | In committee: Set, first hearing. Referred to APPR. suspense file. |
| Apr 28, 2026 | Re-referred to Com. on APPR. |
| Apr 27, 2026 | Read second time and amended. |
| Apr 23, 2026 | From committee: Amend, and do pass as amended and re-refer to Com. on APPR. (Ayes 12. Noes 0.) (April 23). |
| Mar 24, 2026 | Re-referred to Com. on W., P., & W. |
| Mar 23, 2026 | From committee chair, with author's amendments: Amend, and re-refer to Com. on W., P., & W. Read second time and amended. |
| Mar 23, 2026 | Referred to Com. on W., P., & W. |
| Feb 10, 2026 | From printer. May be heard in committee March 12. |
| Feb 9, 2026 | Read first time. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Aug 3, 2026 | Placed on suspense file | Senate Standing Committee on Appropriations |
Passed |
|
| Jun 30, 2026 | Do pass, but first be re-referred to the Committee on [Appropriations] | Senate Standing Committee on Judiciary |
Passed |
|
| Jun 23, 2026 | Do pass, but first be re-referred to the Committee on [Judiciary] | Senate Standing Committee on Natural Resources and Water |
Passed |
|
| May 27, 2026 | AB 1772 Papan Assembly Third Reading | Assembly Floor |
Passed |
|
| May 14, 2026 | Do pass. | Assembly Standing Committee on Appropriations |
Passed |
|
| Apr 23, 2026 | Do pass as amended and be re-referred to the Committee on [Appropriations] | Assembly Standing Committee on Water, Parks, and Wildlife |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| Association Of California Water Agencies | ** Support | |
| Boat Owners Association of the United States (unless amended) | ** Against | |
| Boat Owners Association U.S. | ** Against | |
| California Tahoe Alliance | ** Support | |
| County of San Joaquin | ** Support | |
| County of Siskiyou | ** Support | |
| Filoli | ** Support | |
| National Marine Manufacturers Association | ** Support | |
| Recreational Boaters Of California | ** Against | |
| Recreational Boaters of California (unless amended) | ** Against | |
| SePRO Corporation | ** Support | |
| South San Joaquin Irrigation District | ** Support | |
| Upper San Gabriel Municipal Water District | ** Support | |
| Upper San Gabriel Valley Municipal Water District | ** Support | |
| Valley Ag Water Coalition | ** Support |
SENATE COMMITTEE ON
Senator Sabrina Cervantes, Chair
2025 - 2026 Regular Session
AB 1772 (Papan) - Fish and wildlife: invasive species: invasive mussels
Version: | Policy Vote: |
Urgency: | Mandate: |
Hearing Date: | Consultant: |
Bill Summary:
This bill would establish standards and licensing for a statewide network of recreational vessel inspection and decontamination stations staffed by trained inspectors to prevent the spread of invasive mussels, as provided. The bill would establish the use of a recreational vessel tracking system, and a new biannual nonmotorized recreational vessel invasive mussel infestation prevention fee to help fund invasive mussel prevention efforts, as provided.
Fiscal Impact:
- The California Department of Fish and Wildlife (CDFW) estimates ongoing costs of $86.2 million in fiscal year 2027-28 and $74.9 million annually thereafter (General Fund) for 559 full-time positions to decontaminate or order the decontamination of conveyances with invasive species, in accordance with requirements specified in the bill, and to establish standards and procedures for decontaminating conveyances and disposing of organisms and organic materials so that no viable invasive mussels remain on or in the conveyance before launch.
- The Department of Parks and Recreation (State Parks) estimates ongoing costs of $30 million annually (General Fund) to support inspection and decontamination stations, associated staff, equipment, and materials for reservoirs operated/managed by the department, which includes $5 million to support implementation of the statewide database (WID) as required in the bill. State Parks notes that its actual costs would be contingent upon program standards and procedures to be determined by CDFW, as required by the bill.
Background:
Since 2007, California has been working to control and eradicate two species of invasive, freshwater mussels in state waters—the quagga and zebra (dreissenid) mussels—due to their ability to impede the operations of water supply infrastructure. Existing law makes the zebra mussel a restricted species, which prohibits a person from possessing, importing, shipping, transporting, or introducing such a mussel into any water within the state, unless authorized by the California Department of Fish and Wildlife (CDFW) through a restricted species permit. Water managers are required to work with CDFW to develop protocols to prevent infestation and control plans to prevent the spread of the invasive mussels should the water system become infested. Last year, the Legislature expanded existing law to include any invasive mussel, including the golden mussel. (AB 149 (Committee on Budget, Ch. 106, Stats. 2025.))
Golden mussels have proven to be much more difficult for the state and water managers to control than quagga and zebra mussels. Golden mussels have high reproductive rates and form dense colonies. This mass colonization of surfaces (i.e. “biofouling”) blocks, impairs, and, in many cases, inhibits the functionality of manmade surfaces including underwater intakes, structures, and mechanisms. A photo of an encrusted sampling plate is included on the next page to illustrate the impacts to water infrastructure in particular. Biofouling also coats the hulls and external components of watercraft and recreational facilities, and natural objects such as rocks, fallen trees, even other sedentary bivalves. Nearly every fresh and brackish waterbody in California is suitable habitat for golden mussels.
The presence of the golden mussel poses a significant and immediate threat to the ecological health of the Delta and all waters of the state, water conveyance systems, infrastructure, and water quality. Environmental impacts of the golden mussel include disruption of ecosystems, contributions to the conditions that cause harmful algal blooms, and loss of native and game fish through competition for food sources. It is estimated that a single mussel can filter up to a liter of water a day, which would remove critical nutrients and microbes that support ecosystem health. Impacts of the mussel to recreation include waterbody closures, mandatory boat inspections, increased launch and/or entry fees, and reduced numbers of fish and shellfish for consumption.
Economic impacts include costly repairs and maintenance (e.g., boats, water infrastructure, hydroelectric facilities); reduced water flow affecting food production and water delivery to homes; and impacts to flood control infrastructure. “Tens of millions of dollars are being spent to stop the mussels.” The Arvin-Edison water district, for example, recently spent $2.8 million to perform a chemical treatment that killed all of the golden mussels present. Estimates of ongoing costs to the district range as high as $10 million depending upon the frequency and method of treatment required which remains unknown. Additional treatment methods being evaluated by water suppliers include ultraviolet lights and mechanical scraping.
For recreational motor boaters, “Clean, Drain, Dry” is the general method to eradicate mussels on or in the boats. Approximately 30 lakes across the state instituted recreational boat inspections for mussels and their free-swimming larvae (known as veligers) after discovery of the golden mussel, and several required at least a 30-day quarantine prior to boat launch. The state mussel infestation fee assessed from recreational motor boaters in freshwater increased to $16 annually. Lake County requires the purchase of an additional Lake County mussel infestation sticker for $20 for recreational motor boaters. In the Lake Tahoe area, boat inspection sites have been upgraded, and there is an extensive public education and outreach effort underway, including outreach to users of nonmotorized vessels, such as paddleboards and kayaks, that can also be a vector for the transport of mussels between waterbodies.
Proposed Law:
This bill would strengthen California's invasive mussel prevention framework by barring a conveyance from launching until a specified drying period is complete, broadening the definition of "invasive mussel" and requiring water supply system operators to update their control plans to cover every species present or newly detected, establishing a departmentally licensed inspection and decontamination station program with qualified inspectors, application fees, two-year licenses, and mandatory use of a shared conveyance-tracking data system, and imposing a $20 biennial invasive mussel infestation prevention fee and sticker on nonmotorized vessels, with fee and citation revenue deposited into two new accounts in the Harbors and Watercraft Revolving Fund for regulatory costs, grants, and educational materials.
This bill would:
- Require that the inspection and decontamination of conveyances for aquatic invasive species be performed in the state in accordance with uniform standards and procedures established by CDFW for decontaminating conveyances effective at removing or destroying invasive mussels, as provided.
- Provide that CDFW would have sole authority for developing and implementing the program.
- Provide that CDFW and any other state agency exercising authority under the program would not be liable with regard to any determination or authorization made pursuant to the program consistent with the immunity granted under the Government Claims Act, provided CDFW adhered to all standards, procedures, and regulations promulgated by CDFW.
- Authorize a licensed inspection and decontamination station to issue an inspection, decontamination, or quarantine certificate to an owner of or person in possession of an inspected conveyance. Would require the certificate to contain certain information, such as any decontamination performed and the time and place of the inspection, as provided.
- Require CDFW, on or before January 1, 2028, to collect an invasive mussel infestation prevention fee of $20 every two years from each nonmotorized vessel owner for each nonmotorized vessel launched into waters of the state. Would require indexing of the fee every odd-numbered year using the California Consumer Price Index to the nearest whole dollar. Would require that the fee not exceed the reasonable regulatory costs of CDFW for implementation.
- Require CDFW to use the Regional Watercraft Inspection and Decontamination (WID) Data Sharing System managed by the Colorado Department of Natural Resources for tracking the movement of conveyances, equipment, and other vectors among California waterbodies.
- Require an inspection and decontamination station to enter each inspected, decontaminated, or quarantined conveyance into the WID Data Sharing System.
- Require the manager of a state waterbody with a staffed launch point to register each launching conveyance into the WID Data Sharing System.
- Require CDFW to provide guidance to entities that own or manage reservoirs or other launch points on how to track decontaminated and inspected conveyances in the WID Data Sharing System, and would require CDFW to encourage use of the WID Data Sharing System across the state.
- Provide that data gathered by the WID Data Sharing System or its equivalents would be used solely for preventing invasive mussel species infestations of the state's waterbodies and would not be sold, bartered, or provided to other public or private parties, or used in any other way for any other purpose.
Related Legislation:
AB 2032 (Ransom, 2026) would exempt a public or private agency that operates a water supply system from certain CDFW permitting requirements until an invasive mussel control plan is submitted, approved, or denied, as applicable; require at least quarterly updating of an online map of golden mussel observations by CDFW; and require the California Department of Food and Agriculture and the State Water Resources Control Board to quickly and efficiently respond to the threat of golden mussels, among other provisions, as provided.
AB 2787 (Assembly Water, Parks, and Wildlife Committee, 2026) among other things, provides that a person who operates a Nevada-registered vessel on the waters of Lake Tahoe or Topaz Lake shall not be cited for operation of a vessel without a valid state-issued invasive mussel sticker, provided that Nevada has a program in effect for the management of aquatic invasive species.
AB 1894 (B. Rubio, 2026) would prevent a public agency from prohibiting imported water deliveries for groundwater replenishment due to invasive mussels unless there is substantial, documented evidence of a proven health and safety risk as a result of the invasive mussels.
AB 149 (Assembly Budget Committee, Chapter 106, Statutes of 2025), among other things, expanded statute and programs from “dreissenid mussels” to “invasive mussels,” establishes a requirement for CDFW to review and approve updated invasive mussel control plans, and increased the invasive mussel fee.
AB 1150 (Assembly Water, Parks, and Wildlife Committee, Chapter 831, Statutes of 2023), among other things, distinguished that the issuance and collection of the quagga and zebra mussel infestation and prevention fee from the biennial registration renewal.
AB 2443 (Williams, Chapter 485, Statutes of 2012), establishes the quagga and zebra mussel infestation prevention program, which required payment of the invasive mussel fee on vessels and permitted the use of the funds for, among other things, a grant program.
AB 1929 (Hall, Chapter 152, Statutes of 2010) determines that a water operator is indemnified from the penalty of possessing and transporting a restricted species, if the water operator is in compliance with an approved control plan.
AB 2065 (Hancock, Chapter 667, Statutes of 2008) requires reservoir managers to undertake certain measures to prevent invasive mussel infestation in reservoirs in which invasives mussels have not been detected.
AB 1683 (Wolk, Chapter 419, Statutes of 2007) prohibits a person to possess, import, ship, or transport in the state, or place, plant, or cause to be placed or planted in any water within the state, dreissenid mussels, unless authorized by CDFW. Additionally, authorizes the Director of CDFW, or the Director’s designee, to conduct inspections of conveyances (e.g., vehicles and boats), order that the conveyance be drained, dried, or decontaminated, impound or quarantine conveyances, and conduct inspections of waters of the state and facilities that may contain invasive mussels. Further, requires water operators to implement measures to avoid dreissenid mussel infestation and develop a control plan upon infestation, among other things.
Staff Comments:
CDFW has longstanding budget concerns which have persisted despite repeated efforts over multiple decades to address them. When the state has significant fiscal concerns – as it does now – ensuring consistent and sustained funding for CDFW is particularly challenging. Recently, at legislative direction, CDFW undertook a “service-based” budgeting effort to identify the personnel needed to perform the services required by its mandates. CDFW’s services were separated into eight general programs for analysis. In 2021, the initial results of this effort were released and revealed that CDFW’s funding was inadequate to meet its “mission” service level. Most of the programs were funded at about one-third of the level necessary. The Newsom Administration proposed, and the Legislature approved, significant one-time General Fund moneys to support CDFW’s activities in the near-term. Some progress in addressing the gaps in service were subsequently made, although this was offset, at least in part, by new duties.
Unfortunately, a recent update (for fiscal year 2024/2025) shows that most programs have not received a substantial change in funding. While addressing the presence and spread of golden mussels in the state is clearly a CDFW priority, this effort will require substantial additional funding.
-- END --
Senator Thomas Umberg, Chair
2025-2026 Regular Session
Bill No: AB 1772 (Author:Papan)
Version: June 25, 2026
Hearing Date: June 30, 2026
Fiscal: Yes
Urgency: No
Consultant: AM
SUBJECT
Fish and wildlife: invasive species: invasive mussels
DIGEST
This bill establishes standards and licensing for a statewide network of recreational vessel inspection and decontamination stations manned by trained inspectors to prevent the spread of invasive mussels, as provided. The bill establishes the use of a recreational vessel tracking system, and a new biannual nonmotorized recreational vessel invasive mussel infestation prevention fee to help fund invasive mussel prevention efforts, as provided.
EXECUTIVE SUMMARY
Since 2007, California has been working to control and eradicate two species of invasive, freshwater mussels in state waters—the quagga and zebra (dreissenid) mussels—due to their ability to impede the operations of water supply infrastructure. Existing law makes the zebra mussel a restricted species, which prohibits a person from possessing, importing, shipping, transporting, or introducing such a mussel into any water within the state, unless authorized by the California Department of Fish and Wildlife (CDFW) through a restricted species permit. Water managers are required to work with CDFW to develop protocols to prevent infestation and control plans to prevent the spread of the invasive mussels should the water system become infested. Last year, the Legislature expanded existing law to include any invasive mussel, including the golden mussel. (AB 149 (Committee on Budget, Ch. 106, Stats. 2025.))
The bill is author-sponsored and supported by the County of San Joaquin, the National Marine Manufacturers Association, the Sepro Corporation, and the Upper San Gabriel Valley Municipal Water District. The bill is opposed by Boat Owners Association U.S. and Recreational Boaters of California. The bill passed the Senate Natural Resources and Water Committee with a vote of 6 to 0.
PROPOSED CHANGES TO THE LAW
Existing law:
- Prohibits, until January 1, 2030, a person from possessing, importing, shipping, or transporting in the state, or placing, planting, or causing to be placed or planted in any water within the state, invasive mussels. (Fish & G. Code § 2301(a).)[1]
- Provides the Director of CDFW, or a designee of the Director, the authority to conduct inspections of conveyances (vehicles and boats), order that the conveyance be drained, dried, or decontaminated, impound or quarantine conveyances, and conduct inspections of waters of the state and facilities that may contain invasive mussels. (Ibid.)
- Requires a public or private agency that operates a water supply system (water operator) to cooperate with CDFW to implement measures to avoid infestation by invasive mussels and to control or eradicate any infestation that may occur in a water supply system. If invasive mussels are detected, the water operator, in cooperation with CDFW, shall prepare and implement a plan to control or eradicate invasive mussels within the system, and eliminate or minimize any potential downstream transport of an invasive mussel. (Id. at subd. (d).)
- Requires an entity that discovers invasive mussels within this state to immediately report the discovery to CDFW. (Id. at subd. (e).)
- Establishes an administrative penalty for any violation of these requirements not to exceed $1,000. (Id. at subd. (f).)
- Provides that CDFW and any other state agency exercising authority under these requirements with regard to any determination or authorization made pursuant to this section is not liable with regard to any determination or authorization made pursuant to Section 818.4 of the Government Claims Act. (Id. at subd. (h).)
- Requires any person, or federal, state, or local agency, district, or authority that owns or manages a reservoir (reservoir manager) to undertake certain measures to prevent invasive mussel infestation in reservoirs in which invasives mussels have not been detected. (§ 2302(a).)
- Defines “invasive mussel” to mean any nonnative detrimental mussel species that is capable of spreading in freshwater and is listed in a regulation adopted by the Fish and Game Commission. (FGC § 2303)
This bill:
- Requires that the inspection and decontamination of conveyances for aquatic invasive species be performed in the state in accordance with uniform standards and procedures established by CDFW for decontaminating conveyances effective at removing or destroying invasive mussels, as provided.
- Provides that CDFW has the sole authority for developing and implementing the program
- Provides that CDFW and any other state agency exercising authority under the program is not liable with regard to any determination or authorization made pursuant to the program consistent with the immunity granted under the Government Claims Act, provided CDFW adhered to all standards, procedures, and regulations promulgated by CDFW.
- Authorizes a licensed inspection and decontamination station to issue an inspection, decontamination, or quarantine certificate to an owner of or person in possession of an inspected conveyance. Requires the certificate to contain certain information such as any decontamination performed and the time and place of the inspection, as provided.
- On or before January 1, 2028, requires CDFW to collect an invasive mussel infestation prevention fee of $20 every two years from each nonmotorized vessel owner for each nonmotorized vessel launched into waters of the state. Require indexing of the fee every odd-numbered year using the California Consumer Price Index to the nearest whole dollar. Require the fee not to exceed the reasonable regulatory costs of CDFW for implementation.
- Requires CDFW to use the Regional Watercraft Inspection and Decontamination (WID) Data Sharing System managed by the Colorado Department of Natural Resources for tracking the movement of conveyances, equipment, and other vectors among California waterbodies.
- Requires an inspection and decontamination station to enter each inspected, decontaminated, or quarantined conveyance into the WID Data Sharing System.
- Requires the manager of a state waterbody with a staffed launch point to register each launching conveyance into the WID Data Sharing System.
- Requires CDFW to provide guidance to entities that own or manage reservoirs or other launch points on how to track decontaminated and inspected conveyances in the WID Data Sharing System. Requires CDFW to encourage the use of the WID Data Sharing System across the state.
- Provides that data gathered by the WID Data Sharing System or its equivalents shall be used solely for the purposes of the prevention of invasive mussel species infestations of the state’s waterbodies and shall not be sold, bartered, or provided to other public or private parties, or used in any other way for any other purpose.
COMMENTS
- Author statement
The author writes:
AB 1772 will establish a long-term, stakeholder-driven framework to address both the rapid spread of invasive golden mussels and future aquatic invasive species, protecting California’s environment, water infrastructure, recreation, and economy.
First detected in California in 2024, golden mussels are more adaptable than previous invasive mussels, enabling rapid spread and devastating impacts: clogging water systems, increasing infrastructure costs, disrupting recreation, and harming native ecosystems.
While recent legislation has taken important first steps, California still lacks a coordinated, forward-looking strategy to manage this growing threat. AB 1772 will establish a framework for statewide coordination, including consistent decontamination standards, reciprocity across waterbodies, and additional funding mechanisms, shifting the state from short-term fixes to a proactive, long-term approach to managing the threat of invasive species.
- Background
The Senate Natural Resources and Water Committee analysis of this bill provides a detailed background of the golden mussel, why it is an invasive species, and the potential harm it can cause to the states waterways. That committee’s analysis states:
Golden mussels have proven to be much more difficult for the state and water managers to control than quagga and zebra mussels. Golden mussels have high reproductive rates and form dense colonies. This mass colonization of surfaces (i.e. “biofouling”) blocks, impairs, and, in many cases, inhibits the functionality of manmade surfaces including underwater intakes, structures, and mechanisms. A photo of an encrusted sampling plate is included on the next page to illustrate the impacts to water infrastructure in particular. Biofouling also coats the hulls and external components of watercraft and recreational facilities, and natural objects such as rocks, fallen trees, even other sedentary bivalves. Nearly every fresh and brackish waterbody in California is suitable habitat for golden mussels.
The presence of the golden mussel poses a significant and immediate threat to the ecological health of the Delta and all waters of the state, water conveyance systems, infrastructure, and water quality. Environmental impacts of the golden mussel include disruption of ecosystems, contributions to the conditions that cause harmful algal blooms, and loss of native and game fish through competition for food sources. It is estimated that a single mussel can filter up to a liter of water a day, which would remove critical nutrients and microbes that support ecosystem health. Impacts of the mussel to recreation include waterbody closures, mandatory boat inspections, increased launch and/or entry fees, and reduced numbers of fish and shellfish for consumption.
Economic impacts include costly repairs and maintenance (e.g., boats, water infrastructure, hydroelectric facilities); reduced water flow affecting food production and water delivery to homes; and impacts to flood control infrastructure. “Tens of millions of dollars are being spent to stop the mussels.” The Arvin-Edison water district, for example, recently spent $2.8 million to perform a chemical treatment that killed all of the golden mussels present. Estimates of ongoing costs to the district range as high as $10 million depending upon the frequency and method of treatment required which remains unknown. Additional treatment methods being evaluated by water suppliers include ultraviolet lights and mechanical scraping.
For recreational motor boaters, “Clean, Drain, Dry” is the general method to eradicate mussels on or in the boats. Approximately 30 lakes across the state instituted recreational boat inspections for mussels and their free-swimming larvae (known as veligers) after discovery of the golden mussel, and several required at least a 30 day quarantine prior to boat launch. The state mussel infestation fee assessed from recreational motor boaters in freshwater increased to $16 annually. Lake County requires the purchase of an additional Lake County mussel infestation sticker for $20 for recreational motor boaters. In the Lake Tahoe area, boat inspection sites have been upgraded, and there is an extensive public education and outreach effort underway, including outreach to users of nonmotorized vessels, such as paddleboards and kayaks, that can also be a vector for the transport of mussels between waterbodies. […][2]
- This bill establishes an inspection and decontamination program for boats to address invasive species and specifies that CDFW is not liable for exercising authority under the program pursuant to the Government Claims Act
The bill establishes an inspection and decontamination program for vessels and conveyances for aquatic invasive species in the state to be performed in accordance with uniform standards and procedures adopted by CDFW. Under the bill, CDFW and any other state agency exercising authority under the program is not liable with regard to any determination or authorization made pursuant to the program consistent with the immunity granted under the Government Claims Act, provided CDFW adhered to all standards, procedures, and regulations promulgated by CDFW. The Government Claims Act provides that a public entity is not liable for an injury caused by the issuance, denial, suspension or revocation of, or by the failure or refusal to issue, deny, suspend, or revoke, any permit, license, certificate, approval, order, or similar authorization where the public entity or an employee of the public entity is authorized to determine whether or not such authorization should be issued, denied, suspended or revoked. (Gov. Code § 818.4.) This immunity is intended to protect public employees for liability when making discretionary decisions. Arguably, the provisions of the Government Claim Act would apply, regardless of whether this bill specifically stated it did.
The bill also provides that the data gathered by the WID Data Sharing System is to be used solely for purposes of prevention and is not to be sold, bartered, or provided to other parties for any other purpose. This language acts as a limitation on the access to public records under the California Public Records Act. The bill states it is necessary to protect this sensitive information to ensure the data is used solely for the prevention of invasive mussel species infestation. In light of the sensitive information contained in the database and need to protect Califronai’s waterways, this limitation on access to public records seems warranted.
- Stakeholder statements
The Upper San Gabriel Municipal Water District writes in support stating:
AB 1772 strengthens California's efforts to prevent the spread of invasive mussel species by creating a statewide inspection, decontamination, tracking, and certification program for watercrafts. The bill authorizes the Department of Fish and Wildlife to require drying periods, inspections, quarantines, and decontamination of vessels moving between waterbodies and establishes a statewide database to track vessel movements.
The bill also imposes a new $20 biennial invasive mussel prevention fee on nonmotorized vessels, requires a state-issued sticker for those vessels, and uses the revenue to fund invasive mussel prevention, inspection, and education programs throughout California.
This commonsense legislation addresses the challenges facing recreational boating and water management communities in the prevention and decontamination of invasive mussels, while also identifying and implementing alternative and equitable funding sources. to address public safety concerns affecting those who coexist with listed species.
The Association of California Water Agencies (ACWA), writes in support if amended stating:
Firstly, while we appreciate the intent and rationale of having uniform standards and procedures for inspection and decontamination of conveyances in the state, ACWA strongly believes that water managers need autonomy to impose localized standards and procedures to accurately prevent the introduction of golden mussels into their water bodies. Different water bodies face different risk levels where golden mussels are concerned, including physical hydrology and water quality, proximity to the Sacramento-San Joaquin River Delta, infrastructure and equipment, and more. Water managers across California are undertaking various efforts, including inspecting, decontaminating, and/or quarantining watercraft, in addition to conducting monitoring and public outreach, to prevent the introduction of golden mussels into their waters. Providing water managers with the flexibility to fine-tune prevention efforts in ways that make sense for their water bodies and water systems is critical. As such, we respectfully request that the bill be amended to explicitly clarify that nothing in the bill prohibits a local agency or owner or operator of a waterbody or reservoir from conducting prevention measures, including but not limited to inspection and decontamination conveyances, that are more stringent than the standards and procedures established by CDFW.
Secondly, ACWA strongly believes that public water agencies should have the flexibility to opt-in to a statewide program. As mentioned above, when determining what prevention efforts to apply, a water manager begins by evaluating the individual water body’s unique level of risk. Some water managers may be comfortable with uniform standards for decontamination and allowing watercraft to launch in their waters if decontaminated by a licensed third-party business. To these managers, the statewide program could be incredibly helpful, allowing them to direct staff time and resources to other priorities. However, other water managers may not be as confident in the system, especially within its early years of implementation. […]
[A] statewide program that imposes a one-size-fits-all approach and that does not provide the requisite time to develop confidence in the system could result in water managers further restricting or closing water bodies to recreational opportunities. Ensuring that water managers can opt in to a statewide program, instead of requiring them to participate, will be crucial to its success.
Boat Owners Association U.S. and the Recreational Boaters of California write in opposition unless amended:
Our organizations have been engaged in a collaborative process as AB 1772 has moved through the Assembly as an acknowledged work in progress. Today we received confirmation of the amendments the author will be making to the bill for consideration in the Senate Committee on Natural Resources and Water.
These amendments do not address several key issues that are critical to the recreational boat-ing community and present concerns as well. The issues and concerns are of such significance that we have adopted a position in opposition to the measure unless it is amended to resolve them. We would support the bill if it were to be so amended.
It is important to recognize that the Department of Fish and Wildlife [DFW] is already engaged and is leading the effort to develop a uniform standard and procedures for decontaminating conveyances, even without the enactment of AB 1772. The legislation adds a comprehensive inspection and decontamination program and imposes an additional invasive mussel infestation prevention fee of $20 per nonmotorized vessel every 2 years.
They seek amendments to address several issues including, among others: imposing financial responsibility on parties responsible for introduction of invasive species by commercial vessels, ensuring reciprocity between bodies of water, providing for termination of the program, the ability to refuse to submit to decontamination or quarantine and be able to depart the location, and require entities that receive funding to implement an invasive mussel prevention and inspection program.
SUPPORT
County of San Joaquin
National Marine Manufacturers Association
Sepro Corporation
Upper San Gabriel Valley Municipal Water District
OPPOSITION
Boat Owners Association U.S.
Recreational Boaters of California
PRIOR VOTES
Senate Natural Resources and Water Committee (Ayes 6, Noes 0)
Assembly Floor (Ayes 79, Noes 0)
Assembly Appropriations Committee (Ayes 15, Noes 0)
Assembly Water, Parks and Wildlife Committee (Ayes 12, Noes 0)
**************
SENATE COMMITTEE ON NATURAL RESOURCES AND WATER
Senator Josh Becker, Chair
2025 - 2026 Regular
Bill No: AB Hearing Date: June 23, 2026
Author: | |||
Version: | Amended | ||
Urgency: | Fiscal: | ||
Consultant: | |||
Subject: Fish and wildlife: invasive species: invasive mussels
SUMMARY
This bill would establish state standards and licensing for a statewide network of recreational vessel inspection and decontamination stations with trained inspectors to prevent the spread of invasive mussels, establish the use of a recreational vessel tracking system, and establish a new biannual nonmotorized recreational vessel invasive mussel infestation prevention fee to help fund invasive mussel prevention efforts, among other provisions.
BACKGROUND AND EXISTING LAW
Invasive mussels in California’s waters
Since 2007, California has been working to control and eradicate two species of invasive, freshwater mussels in state waters: quagga and zebra (dreissenid) mussels.[1] Multiple bills subsequently became law that established the dreissenid mussels as a restricted species and granted the California Department of Fish and Wildlife (CDFW) with various authorities to stem the spread of the mussels, including to inspect, order treatment of, and quarantine vessels, such as recreational motor boats. As a restricted species, a person is prohibited from possessing, importing, shipping, transporting, or introducing an invasive species into any water within the state, unless authorized by CDFW through a restricted species permit.[2]
Further, statute requires water managers to work with CDFW to develop measures to avoid infestation, as well as requires water managers to develop control plans to prevent the spread of the invasive mussels should the water system become infested with the mussels. The benefit of developing a control plan is that water managers enjoy liability protections from the unintentional transportation or introduction of dreissenid mussels to the water system once the control plan is approved by CDFW.
Until last year, law and regulation to prevent invasive mussel infestation was specific to quagga and zebra mussels. AB 149 (Committee on Budget, Chapter 106, Statutes of 2025) expanded the dreissenid mussel programs and authorities to include any invasive mussel, including the golden mussel.
Golden mussels
On October 17, 2024, Department of Water Resources (DWR) staff discovered golden mussels in the Port of Stockton. Soon after the initial discovery, the golden mussel was quickly found at additional sites within the Sacramento-San Joaquin Delta (Delta). The golden mussel is a freshwater bivalve native to China and Southeast Asia, but it has established itself outside of its native range in several countries. The discovery in Stockton was the first detection of the species in the United States. The California Fish and Game Commission (commission) quickly took emergency action to add “Limnoperna fortunei (golden mussel)” to the list of restricted species by regulation. Since then, the golden mussel has been detected throughout the Delta and the State Water Project, and as far south as San Diego. CDFW maintains an online map showing confirmed observations of golden mussels. Sacramento, Kern and other Counties have recently declared states of local emergency due to the spread of golden mussels. The commission is expected to begin the process to take additional regulatory action regarding golden mussels this summer.
There are no socially and environmentally benign methods currently available to eliminate invasive mussels once they are present. Adult mussels can survive days, even weeks, when removed from water. Larval mussels can survive a week or longer in small volumes of water. Eradication from large, interconnected bodies of water is likely impossible. Therefore, containing mussels within infested areas is the only means to minimize additional new, widespread impacts.
Golden mussels have proven to be much more difficult for the state and water managers to control than quagga and zebra mussels. Golden mussels have high reproductive rates and form dense colonies. This mass colonization of surfaces (i.e. “biofouling”) blocks, impairs, and, in many cases, inhibits the functionality of manmade surfaces including underwater intakes, structures, and mechanisms. A photo of an encrusted sampling plate is included on the next page to illustrate the impacts to water infrastructure in particular.[3] Biofouling also coats the hulls and external components of watercraft and recreational facilities, and natural objects such as rocks, fallen trees, even other sedentary bivalves. Nearly every fresh and brackish waterbody in California is suitable habitat for golden mussels.
The presence of the golden mussel poses a significant and immediate threat to the ecological health of the Delta and all waters of the state, water conveyance systems, infrastructure, and water quality. Environmental impacts of the golden mussel include disruption of ecosystems, contributions to the conditions that cause harmful algal blooms, and loss of native and game fish through competition for food sources. It is estimated that a single mussel can filter up to a liter of water a day, which would remove critical nutrients and microbes that support ecosystem health. Impacts of the mussel to recreation include waterbody closures, mandatory boat inspections, increased launch and/or entry fees, and reduced numbers of fish and shellfish for consumption.
Economic impacts include costly repairs and maintenance (e.g., boats, water infrastructure, hydroelectric facilities); reduced water flow affecting food production and water delivery to homes; and impacts to flood control infrastructure. “Tens of millions of dollars are being spent to stop the mussels.”[4] The Arvin-Edison water district, for example, recently spent $2.8 million to perform a chemical treatment that killed all of the golden mussels present. Estimates of ongoing costs to the district range as high as $10 million depending upon the frequency and method of treatment required which remains unknown.[5] Additional treatment methods being evaluated by water suppliers include ultraviolet lights and mechanical scraping.
For recreational motor boaters, “Clean, Drain, Dry” is the general method to eradicate mussels on or in the boats. Approximately 30 lakes across the state instituted recreational boat inspections for mussels and their free-swimming larvae (known as veligers) after discovery of the golden mussel, and several required at least a 30 day quarantine prior to boat launch.[6] The state mussel infestation fee assessed from recreational motor boaters in freshwater increased to $16 annually. Lake County
requires the purchase of an additional Lake County mussel infestation sticker for $20 for recreational motor boaters. In the Lake Tahoe area, boat inspection sites have been upgraded, and there is an extensive public education and outreach effort underway, including outreach to users of nonmotorized vessels, such as paddleboards and kayaks, that can also be a vector for the transport of mussels between waterbodies. In a letter to the author’s office, the California Tahoe Alliance reports that invasive mussels could result in $33 million in annual losses in the Lake Tahoe region impacting tourism, property values, and maintenance costs.
Invasive mussels control plan.
Public and private agencies that operate a water supply system are required to cooperate with CDFW to implement measures to avoid infestation by invasive mussels and to control or eradicate any infestation that may occur in the system. If invasive mussels are detected, the operator of the water supply system is required to prepare a plan, subject to CDFW approval, to control or eradicate invasive mussels in the system and eliminate or minimize any potential downstream transport of an invasive mussel. The plans are required to include methods for delineation of infestation; methods for control or eradication of adult mussels and decontamination of water containing larval mussels; a system monitoring program; and a requirement that the operator of the water supply system allows CDFW inspections as well as cooperates with CDFW to update or revise control or eradication measures in the plan to address scientific advances.
Control plans, once approved, can provide or facilitate the necessary permitting for water managers working within their mussel-infested water supply system to handle golden mussels so long as a description of the plans for handling the invasive mussels are included.
Existing law:
- Until January 1, 2030, prohibits a person from possessing, importing, shipping, or transporting in the state, or placing, planting, or causing to be placed or planted in any water within the state, invasive mussels.
- Provides the Director of CDFW, or a designee of the Director, the authority to conduct inspections of conveyances (e.g., vehicles and boats), order that the conveyance be drained, dried, or decontaminated, impound or quarantine conveyances, and conduct inspections of waters of the state and facilities that may contain invasive mussels. Permits the Director of CDFW to determine that other parties or state agencies, including State Parks, the Department of Water Resources (DWR), and the State Lands Commission, and others may exercise those authorities as well.
- Exempts from the California Environmental Quality Act (CEQA), any action taken to drain, dry, or decontaminate a conveyance and conduct inspections, except for the use of chemicals other than salt or hot water to decontaminate a conveyance or facility.
- Requires a public or private agency that operates a water supply system (water operator) to cooperate with CDFW to implement measures to avoid infestation by invasive mussels and to control or eradicate any infestation that may occur in a water supply system. If invasive mussels are detected, the water operator, in cooperation with CDFW, shall prepare and implement a plan to control or eradicate invasive mussels within the system, and eliminate or minimize any potential downstream transport of an invasive mussel. Requires the approved plan to contain the following minimum elements:
- Methods for delineation of infestation, including both adult mussels and veligers;
- Methods for control or eradication of adult mussels and decontamination of water containing veligers;
- A systematic monitoring program to determine any changes in conditions; and
- The requirement that the water operator permit inspections by CDFW as well as cooperate with CDFW to update or revise control or eradication measures in the approved plan to address scientific advances in the methods of controlling or eradicating mussels and veligers.
- Provides that if the water operator has prepared, initiated, and is in compliance with all the elements of an approved plan to control or eradicate invasive mussels, the water operator is not subject to any civil or criminal liability for the introduction of invasive mussel species as a result of those operations, among other provisions. Authorizes CDFW to require the water operator to update its plan. Authorizes CDFW to apply the restrictions on a water operator if the plan is not updated or revised, until the water operator updates or revises the plan.
- Requires CDFW, on or before December 31, 2026, to review all approved plans pursuant (c) and requires all plans that do not specifically address all invasive mussel species known to be present in bodies of water in the state as of January 1, 2026, to be updated or revised appropriately to include all invasive mussel species, on or before September 30, 2027.
- Requires every invasive mussel species to be addressed in a plan no later than 180 days from the date that the species is listed in a regulation. Requires CDFW to approve plans or provide written comments and suggestions on plan deficiencies within 180 days from the date of plan submission.
- Requires an entity that discovers invasive mussels within this state to immediately report the discovery to CDFW.
- Establishes an additional penalty for any violation of these requirements with a penalty not to exceed $1,000.
- Allows CDFW to adopt regulations to carry out these requirements.
- Indemnifies CDFW and any other state agency exercising authority under these requirements with regard to any determination or authorization made pursuant to this section. (Fish and Game Code (FGC) § 2301)
- Provides the Director of CDFW, or a designee of the Director, the authority to conduct inspections of conveyances (e.g., vehicles and boats), order that the conveyance be drained, dried, or decontaminated, impound or quarantine conveyances, and conduct inspections of waters of the state and facilities that may contain invasive mussels. Permits the Director of CDFW to determine that other parties or state agencies, including State Parks, the Department of Water Resources (DWR), and the State Lands Commission, and others may exercise those authorities as well.
- Requires any person, or federal, state, or local agency, district, or authority that owns or manages a reservoir (reservoir manager) to undertake certain measures to prevent invasive mussel infestation, in reservoirs in which invasives mussels have not been detected.
- Requires a reservoir manager responsible for a reservoir, where recreational, boating, or fishing activities are permitted, except a privately owned reservoir that is not open to the public, to:
- Assess the vulnerability of the reservoir for the introduction of invasive mussel species; and
- Develop and implement a program designed to prevent the introduction of invasive mussel species. Requires the program to, at a minimum, include public education, monitoring, and management of those recreational, boating, or fishing activities that are permitted.
- Requires a reservoir manager responsible for a reservoir, where recreational, boating, or fishing activities of any kind are not permitted, to include visual monitoring for the presence of mussels as part of its routine field activities, based on its available resources and staffing.
- Allows a reservoir manager, except a privately owned reservoir that is not open to the public, to refuse the planting of fish in that reservoir by CDFW unless CDFW can demonstrate that the fish planting does not present a risk of introducing invasive mussels.
- Establishes a civil penalty, not to exceed $1,000 per violation of 2). Authorizes CDFW to adopt regulations to implement and enforce requirements on reservoir managers to the extent funds are available. (FGC §2302)
- Requires a reservoir manager responsible for a reservoir, where recreational, boating, or fishing activities are permitted, except a privately owned reservoir that is not open to the public, to:
- Defines “invasive mussel” to mean any nonnative detrimental mussel species that is capable of spreading in freshwater and is listed in a regulation adopted by the Fish and Game Commission. (FGC § 2303)
- Requires the Department of Motor Vehicles (DMV) to collect for resident and nonresident vessel owners, separate from the registration fee, an invasive mussel infestation prevention fee (invasive mussel fee) in an amount established by the Division of Boating and Waterways (DBW).
- Requires DMV to issue an invasive mussel infestation prevention sticker (invasive mussel sticker) to the vessel owner, upon payment of the mussel fee.
- Authorizes the citation of a vessel operator for operating a recreational vessel in nonmarine waters without a valid state-issued invasive mussel infestation prevention sticker. (Vehicle Code §9853)
- Requires the invasive mussel fee to be paid to DBW.
- Establishes the invasive mussel fee to be between $30 and $42, every other year. Requires those values to be adjusted for inflation. Requires DBW to establish and consult with a technical advisory group to determine the fee.
- Permits DBW to adopt emergency regulations to manage the collection and use of the invasive mussel fees.
- Requires all revenue from the invasive mussel fee to be deposited into the Harbors and Watercraft Revolving Fund.
- Clarifies that a vessel operator may be issued a citation for operating a recreational vessel in nonmarine waters without a valid state-issued invasive mussel sticker. (Harbors and Navigation Code (HNC) §675)
- Establishes how revenues from the invasive mussel fee may be used.
- Requires the moneys deposited into the Harbors and Watercraft Revolving Fund be used for:
- The reasonable costs incurred by DBW associated with determining the invasive mussel fee and adoption of regulations and with administering the grants.
- The reasonable costs, not to exceed 15% of the remaining revenues, of CDFW for implementation of invasive mussel regulations in those areas of the state where an invasive mussel infestation prevention plan has not been implemented.
- Grants to reservoir managers subject for the reasonable regulatory costs incident to the implementation of an invasive mussel infestation prevention plan. At least 85% of the revenue must be used for this purpose.
- Requires DBW, when awarding grants, to:
- Give priority to invasive mussel infestation prevention plans that meet requirements and that also include visual and manual inspection standards and other infestation prevention procedures consistent with established or future state adopted guidebooks and management plans;
- Take into consideration the benefits of regional-scale invasive mussel infestation prevention plans; and
- Take into consideration the unique economic, ecological, and recreational impacts to rural and urban reservoirs from invasive mussel infestation.
- Prohibits the use of invasive mussel fees for any purpose other than those explicitly authorized. (HNC §676)
- Requires the moneys deposited into the Harbors and Watercraft Revolving Fund be used for:
- Prohibits the importation, transportation, possession, or live release of specified wild animals into this state except under a revocable, nontransferable restricted species permit issued by CDFW, as provided. (FGC §§2116 et seq.)
- Provides civil and criminal penalties for violations of invasive mussel restrictions and any permit conditions. (FGC §§2125, 12000)
Existing regulation:
- Designates the golden mussel as a restricted species. (14 CCR §671)
- Prohibits any person or federal, state or local agency, district or authority that owns or manages a reservoir where recreational boating or fishing activities are permitted to operate without developing and implementing a dressenid mussel prevention program, as provided. Requires the mussel prevention program to include an assessment of the vulnerability of the reservoir to mussel introduction, a monitoring program for the mussel, and management of recreational activities to prevent the introduction of the mussels to the waterbody and to keep the mussels from being moved from the waterbody, if present. (14 CCR §672.1(a), (b))
- Provides that tags, stickers, or other methods used to identify a conveyance as quarantined following an inspection for dressenid mussels shall not be tampered with or destroyed prior to the conveyance being released from quarantine by CDFW. (14 CCR §672.1(c))
- Provides for penalty and appeal procedures for dressenid mussel violations. (14 CCR §672.2)
PROPOSED LAW
This bill would:
- Modify the existing authority for CDFW or other entities to order the drying of a conveyance following any drain, dry, or decontamination procedure, as provided. Specify that a conveyance cannot be launched into waters of the state until the required drying time has been completed.
- Authorize the owner or person in possession of the conveyance to retain possession of the conveyance during the drying period subject to any requirements, such as attaching a tamper-proof device that prevents the conveyance from coming into contact with water without being broken.
- Require the inspection and decontamination of conveyances for aquatic invasive species be performed in the state in accordance with uniform standards and procedures established by CDFW for decontaminating conveyances effective at removing or destroying invasive mussels, as provided.
- Require decontamination to include removal of all visible plant materials, the draining and treatment of all water-containing compartments in the conveyance, treatment of surfaces by hot water or other CDFW-approved methods, and flushing or treatment of internal systems, as provided.
- Require CDFW-approved standards and procedures to at a minimum be compliance with the Uniform Minimum Protocols and Standards for Watercraft Interception Programs for Dreissenid Mussels in the Western United States prepared by the Pacific State Marine Fisheries Commission.
- Require the standards and procedures to be informed by the best available science. Authorize CDFW to consult with water agencies and recreational boaters in standard development.
- Require CDFW to implement these requirements consistently with the requirements for decontamination noted above regardless of whether CDFW has adopted standards and procedures for decontamination, as provided.
- Require a conveyance prior to launching into the waters of the state to be subject to decontamination or quarantine if a qualified inspector determines that invasive mussels are detected, the conveyance has been operated in or transported from an infested waterbody, or the conveyance contains water in compartments that cannot be completely drained.
- Authorize a law enforcement officer to detain or impound the conveyance until decontamination is complete if a person refuses to submit the conveyance for decontamination or quarantine or if there is hardship. Require the owner of the conveyance to be liable for all costs associated with decontamination or impoundment due to the failure to cooperate by the owner or the person in possession of the conveyance.
- Exempt CDFW and any other state agency exercising authority under 2) from liability, as provided.
- Authorize a licensed inspection and decontamination station to issue an inspection, decontamination or quarantine certificate to an owner of or person in possession of an inspected conveyance. Require the certificate to contain certain information such as any decontamination performed and the time and place of the inspection, as provided.
- Require the station issuing a certificate to attach a tamper-proof device to the conveyance, as provided, that prevents the conveyance from coming into contact with waters of the state without being broken.
- Require CDFW to establish a minimum retention period for inspection and decontamination certificates.
- Authorize CDFW to recognize an inspection or decontamination certificate issued by another government entity if that government entity adheres to the minimum standards for inspection, decontamination and quarantine established herein.
- Provide that CDFW and any other state entity exercising authority under 3) shall not be liable for any determination or authorization made pursuant to 3), as provided.
- Require that CDFW has the sole and exclusive authority within the state for developing and implementing a statewide program for the inspection and decontamination of conveyances for aquatic invasive species. Require the inspection and decontamination program to consist of licensed inspection and decontamination stations with qualified inspectors that issue certificates of compliance or notices of noncompliance to conveyances following inspection and decontamination, as provided.
- Require the inspection and decontamination program to only be conducted at inspection and decontamination stations licensed by CDFW and by qualified inspectors.
- Require a licensed inspection and decontamination station to comply with standards, procedures, and regulations adopted by CDFW; only permit inspection and decontamination by qualified inspectors; employ the use of CDFW-approved decontamination equipment, certification documentation, and tamper-proof devices; use the WID Data Sharing System developed by the State of Colorado (see 6) below for more information); maintain relevant education materials; display an identifying sign at the station that indicates its qualifying status; and authorize CDFW or its authorized representative to access the station for purposes of examining logs, and equipment, as provided.
- Require CDFW to develop standards for the licensing of inspection and decontamination stations. Require that inspection and decontamination services at the station only be performed by qualified inspectors. Require CDFW to establish performance standards for a licensed inspection and decontamination station for which compliance is determined through periodic inspections. Require CDFW to develop and implement a quality assurance program, such as a secret shopper program, to audit inspection and decontamination stations and ensure compliance to standards, as provided.
- Set the expiration date at two years for a valid license for an inspection and decontamination station. Authorize CDFW to require passage of a licensing test and ongoing training to renew a station’s license. Require license revocation if the inspection and decontamination station fails to meet applicable standards at any time. Require CDFW provide written or electronic notice before revoking a station’s license, as specified. Require CDFW to develop a process and timeline for a station to contest license revocation.
- Require CDFW to encourage the establishment of a sufficient number of licensed inspection and decontamination stations to ensure reasonably accessibility and convenience of boaters and to control the spread of invasive mussels.
- Require CDFW to post a list of licensed inspection and decontamination stations by region as provided.
- Require a licensed inspection and decontamination station to annually report to CDFW specified information regarding station activities.
- Require CDFW to impose licensing fees for inspection and decontamination stations in an amount that does not exceed the reasonable regulatory costs of administering the licensing program.
- Require an inspector to pass a qualification test and meet any minimum experience or training criteria established by CDFW to qualify as a licensed inspector.
- Require CDFW to establish standards for training, equipment, performance and data collection for inspection and decontamination stations. Authorize CDFW to develop a training program to be used to qualify individuals to perform inspections and decontaminations using training materials that align with the Pacific States Marine Fisheries Commission’s watercraft inspection and decontamination Level 2 training program, or, if CDFW develops its own program, grant qualified inspector status to individuals who holds certain certifications issued by or meeting the standards of the Pacific States Marine Fisheries Commission.
- Require CDFW to prescribe training and periodic retraining courses for qualified inspectors. Require the licensing to expire after two years. Authorize CDFW to require passage of a qualification test and ongoing training to renew an inspector’s qualification. Failure by a qualified inspector to meet standards at any time shall result in disqualification. Require CDFW to provide written or electronic notice before imposing a disqualification, as provided. Require CDFW to develop a process and timeline for a qualified inspector to contest a disqualification.
- Require CDFW to develop standards for qualifying institutions and instructors for purposes of providing training for qualified inspectors. Require these to include criteria for training manuals, and other materials, as provided. Require the standards to specify conditions under which an institution or instructor may be disqualified to train others and how to seek reinstatement. Require posting on CDFW’s website.
- Require CDFW to impose qualification fees for qualified inspections and qualified institutions and instructors in an amount not to exceed the reasonable regulatory costs of administering the program.
- Require CDFW to use the Regional Watercraft Inspection and Decontamination (WID) Data Sharing System managed by the Colorado Department of Natural Resources for tracking the movement of conveyances, equipment, and other vectors among California waterbodies.
- Require an inspection and decontamination station to enter each inspected, decontaminated, or quarantined conveyance into the WID Data Sharing System.
- Require the manager of a state waterbody with a staffed launch point to register each launching conveyance into the WID Data Sharing System.
- Require CDFW to provide guidance to entities that own or manage reservoirs or other launch points on how to track decontaminated and inspected conveyances in the WID Data Sharing System. Require CDFW to encourage the use of the WID Data Sharing System across the state.
- Require CDFW to encourage public or private agencies that operate a water supply system to enter into reciprocity agreements with other agencies to allow the launch of conveyances without quarantine or decontamination for conveyances moving between waterbodies operated by those agencies.
- Require an agency that enters into a reciprocity agreement to notify CDFW.
- Require CDFW to maintain a comprehensive list of reciprocity agreements on its internet website.
- On or before January 1, 2028, require CDFW to collect an invasive mussel infestation prevention fee of $20 every two years from each nonmotorized vessel owner for each nonmotorized vessel launched into waters of the state. Require indexing of the fee every odd-numbered year using the California Consumer Price Index to the nearest whole dollar. Require the fee not to exceed the reasonable regulatory costs of CDFW for implementation.
- Require CDFW upon receipt of payment of the fee, to issue an invasive mussel infestation prevention sticker to be affixed to the nonmotorized vessel.
- Authorize issuance of a citation for operating a nonmotorized vessel in nonmarine waters without a valid invasive mussel infestation prevention sticker, as provided.
- Void the sticker if there is evidence of tampering.
- Require all revenues from the fee to be deposited in the Nonmotorized Vessel Invasive Mussel Infestation Prevention Account (Prevention Account) established within the Harbors and Watercraft Revolving Fund. Require all revenue from citations to be deposited in the Nonmotorized Vessel Invasive Mussel Infestation Prevention Penalty Account (Penalty Account) established within the Harbors and Watercraft Revolving Fund.
- Require, upon legislative appropriation, all monies in the Prevention Account shall too be used for reasonable regulatory costs of CDFW or others for issuing the stickers (up to 15%), for the reasonably regulatory costs of CDFW in administering the grant program (up to 10%), grants to water operators for the reasonable regulatory costs incident to the implementation of an invasive mussel control plan (at least 40%), as provided.
- Require, upon legislative appropriation, all monies in the Penalty Account to be used for grants to entities with approved invasive mussel control plans for activities that reduce the risk of the overland spread of invasive mussels, and for DBW to generate and distribute educational materials, as provided.
- Require an entity receiving grant funding to provide data to DBW regarding invasive mussel prevention, inspection, and control plans, as provided.
- Authorize CDFW to contract with others for the issuance of the sticker.
- Require CDFW to develop educational materials be provided before issuing the sticker.
- Authorize regulations to implement 2), 3), 4), and 5) above.
- Define relevant terms, including that a nonmotorized vessel means an inflatable or rigid vessel, such as a kayak, operated in nonmarine waters, and make numerous relevant legislative findings and declarations.
- State that no reimbursement is required to a local agency or school district, as provided.
ARGUMENTS IN SUPPORT
According to the author, “AB 1772 will establish a long-term, stakeholder-driven framework to address both the rapid spread of invasive golden mussels and future aquatic invasive species, protecting California’s environment, water infrastructure, recreation, and economy.”
“First detected in California in 2024, golden mussels are more adaptable than previous invasive mussels, enabling rapid spread and devastating impacts: clogging water systems, increasing infrastructure costs, disrupting recreation, and harming native ecosystems.”
“While recent legislation has taken important first steps, California still lacks a coordinated, forward-looking strategy to manage this growing threat. AB 1772 will establish a framework for statewide coordination, including consistent decontamination standards, reciprocity across waterbodies, and additional funding mechanisms, shifting the state from short-term fixes to a proactive, long-term approach to managing the threat of invasive species.”
The County of San Joaquin writes in support, “California, specifically the Delta, is ground zero for this invasive species, so the State must move swiftly to help protect against a possible nationwide outbreak.”
Filoli adds “Protecting California’s water systems is inseparable from protecting our landscapes, wildlife, and communities. Our historic garden and natural lands depend on healthy, resilient ecosystems and reliable water resources. Preventing the introduction and spread of invasive species is far more effective, and far less costly, than attempting to manage them after establishment.”
ARGUMENTS IN OPPOSITION
Taking an “oppose unless amended” position, the Recreational Boaters of California (RBOC) write that they “embrace the objectives of AB 1772 to enhance the current efforts to prevent the infestation of nonnative, invasive golden mussels” and note that this a “challenging issue.”
According to the RBOC, the bill does not “address several key issues that are critical to the recreational boating community and present concerns as well.” They argue that the bill does not:
- impose responsibility and financial accountability on commercial vessels for the introduction of golden mussels into state waters,
- identify and implement alternative and equitable funding sources for prevention and control measures beyond fees imposed on the recreational boating community,
- ensure reciprocity between water bodies,
- provide for the anticipated future when most water bodies are infested,
- provide for a potential termination of the program when no new infestations are observed, and
- provide a vessel operator the opportunity to refuse to submit to inspection or quarantine and depart the location without being quarantined or impounded.
In addition to various technical issues, they also object to non-governmental inspection and decontamination stations having the authority to issue a quarantine certificate.
COMMENTS
The bill is double-referred. This bill is referred to both this Committee and the Senate Judiciary Committee for review. This Committee is the Committee of first referral. Elements of this bill under the Senate Judiciary Committee’s jurisdiction are included here for completeness and context only and will be discussed before that Committee.
Ambitious bill to address a serious issue confronting the state’s water infrastructure. This bill is an ambitious effort to establish state standards and licensing for a statewide network of recreational vessel inspection and decontamination stations with trained inspectors, establish the use of a recreational vessel tracking system, and establish a new biannual nonmotorized recreational vessel mussel infestation prevention fee to help fund prevention efforts, among other provisions. Recent amendments have substantially increased the complexity of the bill’s solution to potential infestation, and raised a number of concerns and loose ends that should be addressed.
That written, multiple support letters note that AB 1772 is an “intent bill” designed to reach consensus solutions, and CDFW is expected to release a substantial set of proposed regulations addressing golden mussels imminently. In view of this, the author may wish to continue working on the bill’s content, and the Committee may wish to direct staff to assist in that effort.
The Association of California Water Agencies (ACWA) in their recent “support if amended” letter supported the development of a statewide inspection and decontamination program, if voluntary, that meets many of the key features of the program proposed in this bill. ACWA compares the proposed program to the existing smog check program and emphasized that the success of the program would require strong oversight and accountability, as well as dedicated resources and staffing at CDFW.
Impacts of golden mussel infestation on water ratepayers. As described above, water suppliers are already spending millions of dollars to seek to prevent golden mussel infestation and treat infected infrastructure. Infestation has the potential to result in millions of dollars in added costs for a water supply system indefinitely. This is likely to increase water rates and further decrease water affordability throughout the state. Efforts that prevent the introduction and infestation of golden mussels into a water supply system delays when those significant annual treatment expenditures will be necessary. Setting up an inspection and decontamination station – as some water suppliers have done for the water bodies they manage – appears to be a good investment to protect water ratepayers.
Recreational motorized boaters have faced quarantines to launch into certain water bodies, which may effectively mean that certain water bodies are unavailable to them. Boaters have likely had to take additional steps to plan recreational activities or pay for inspection and decontamination procedures. This may well have resulted in a redistribution of or reduction in recreational boating activity across the state. To be sure, nonmotorized vessels are also capable of transporting golden mussels between water bodies, as the bill recognizes by instituting the bi-annual fee and sticker program for them.
Who pays. While recreational boaters had their invasive mussel fees raised, CDFW received $20 million from the Proposition 4 bond to address golden mussel infestation last year. These bond monies will be repaid by the state’s taxpayers.
Adding an additional fee to commercial ongoing vessels to fund golden mussel prevention programs would likely constitute a tax under California law which would require a two-thirds vote of the Legislature.
Local control. Numerous water supply system operators have set up their own recreational watercraft inspection and decontamination stations or taken other steps to protect their systems from infestation. Different operators use different techniques, and the best methods to use remain under investigation. In the future, there may be widespread confidence in the statewide system of inspection and decontamination stations proposed herein, the quality and consistency of their inspections, and their “tamper proof” seals, but it remains to be seen how long it will take for that confidence to develop. Trust cannot be legislated.
It would likely take CDFW a considerable amount of time to develop the programs required by this bill, and for them to be adopted and stations built out across the state. Given the costs associated with infestation and a water supply system operator’s level of risk tolerance, it should be up to each water supply system to determine whether to follow their own protocols for inspection, decontamination, drying and quarantine.
In view of this, the Committee may wish to amend the bill to authorize water supply operators who run their own inspection and decontamination stations to continue to use them. [Amendment #1]
Reciprocity. Reciprocity is a complicated issue. Certainly water bodies that wish to establish reciprocity between themselves for recreational vessels transiting between them should be welcome to do so. There is a potential role for the state in ensuring that information is readily-available in some form so boating trips can be planned. However, as noted by the California Tahoe Alliance in a letter to the author, broad application of reciprocity can raise concerns. The examples they cited were the potential transmission of a native species from one water body to another where it would be considered an invasive species (as different water bodies are likely to have different aquatic invasive species present) and the extensive monitoring requirements necessary to establish that an aquatic invasive species is not present. Perspectives on reciprocity may evolve over time as more is learned about the golden mussels and the best methods to prevent their spread.
In view of this, the Committee may wish to clarify that participation in reciprocity is voluntary. [Amendment #2]
Tracking boats. The bill requires the use of a boat tracking system developed by the State of Colorado which has extensive state efforts underway to minimize the transmission of invasive species between waterbodies by recreational watercraft. The idea is that a boat, once inspected and/or decontaminated in California, is added to the tracking system. When the boat is launched from a staffed launch site, the launch of the boat and its location is uploaded to the tracking system. In this manner, the movement of boats and whether they are clean or not can be tracked among participating water bodies. While this system has worked well in Colorado (with approximately 83,000 registered recreational motorized watercraft), it is less clear what the implementation challenges would be in California (with approximately 800,000 registered recreational motorized watercraft). Additionally, this system would not be tracking nonmotorized watercraft, and not all waterbodies have staffed launch points. There would be a lot of potential gaps in the collected data. There could be useful information provided regarding exposure of a waterbody to golden mussels, although a water supply system operator is likely monitoring already for golden mussels. The use of a boat tracking system also raises personal privacy concerns. While the Colorado system does not currently retain personal data, it is unclear if any future alternative system would do the same.
In view of this, the Committee may wish to amend the bill to protect the privacy of recreational boat owners. [Amendment #3]
Establishing Performance Standards. Rather than focusing on a method to eradicate invasive mussel species from the hull of a recreational watercraft, statute should focus on establishing the performance standards (i.e. eradication) and be neutral on the technology or methods employed to spur innovation and recognize that the characteristics of different water bodies may require different techniques.
Additionally, the downside of identifying certain methods in statute is that statute has to be changed if new methods are developed. The performance goals, however, are less likely to change as frequently. The author may wish to consider removing explicit references to methods in the bill and instituting performance standards. There can be instances where it is necessary to be explicit about referenced standards in statute, for example to override a standard designated in regulation. However, particularly in the absence of CDFW’s regulations and as technology and methods are still being developed to address golden mussels, it is unclear that this is needed in this bill.
“Tamper-proof.” It is unclear how tamper-proof any seal or similar device will be in the age of YouTube, ebay and 3-D printers if a person is determined to tamper with it.
Underground regulations. Several of the proposed sections in the bill include authorization to CDFW to develop regulations. While elements of these sections are very prescriptive, there is room for interpretation of various requirements, such as drying times. The development of regulations is necessary in this instance to ensure consistency in application and implementation, and to avoid inadvertent underground regulations.
Program roll out. As currently written, the bill establishes the inspection and decontamination station program and relevant licensing requirements. However, the bill does not address the time needed to develop and implement these programs. The author may wish to consider providing a deadline by which the regulations governing the station and licensing programs shall be developed. A working group or advisory body of some form could be helpful in the development of the programs, although that could be organized without statutory direction. Then perhaps establish a pilot program in a few locations after the regulations are developed and roll it out over the course of a year or two. There could be some kind of evaluation mechanism built-in to the pilot program so observations in the field can be incorporated into either regulation or statute. A dedicated grant program might help with the costs of infrastructure build out for the stations. It is unclear if 3rd parties will find the inspection and decontamination station business worth engaging in. It is also unclear that it is necessary to put into the bill a trigger to phase-out the inspection and decontamination station in the future. There could be a trigger to evaluate whether a phase-out is needed at a future date.
Public outreach and education. The bill includes multiple references to educational materials. Addressing golden mussel infestation will take a substantial and sustained public outreach effort by CDFW, water supply operators, and others beyond the recreational motorized boating community to those that occasionally engage in water sports in the state’s nonmarine waters. For example, volunteers are trained to engage with paddle boarders and others on Lake Tahoe’s beaches about the risk of invasive mussel species transmission.
Lake Oroville. DWR recently announced that Lake Oroville would not screen for golden mussels. According to a study they commissioned, the depths of Lake Oroville are too cold for golden mussels to live in. They anticipate that the golden mussels will live in the warmer waters near the surface, and will be exposed along the shoreline when the water depth declines and die.
Underfunded and overmandated. CDFW has longstanding budget concerns which have persisted despite repeated efforts over multiple decades to address them. When the state has significant fiscal concerns – as it does now – ensuring consistent and sustained funding for CDFW is particularly challenging. Recently, at legislative direction, CDFW undertook a “service-based” budgeting effort to identify the personnel needed to perform the services required by its mandates. CDFW’s services were separated into eight general programs for analysis. In 2021, the initial results of this effort were released and revealed that CDFW’s funding was inadequate to meet its “mission” service level. Most of the programs were funded at about one-third of the level necessary. The Newsom Administration proposed, and the Legislature approved, significant one-time General Fund moneys to support CDFW’s activities in the near-term. Some progress in addressing the gaps in service were subsequently made, although this was offset, at least in part, by new duties.
Unfortunately, a recent update (for fiscal year 2024/2025) shows that most programs have not received a substantial change in funding. While addressing the presence and spread of golden mussels in the state is clearly a CDFW priority, this effort will require additional funding.
Recent related legislation
AB 2032 (Ransom, 2026) would exempt a public or private agency that operates a water supply system from certain CDFW permitting requirements until an invasive mussel control plan is submitted, approved, or denied, as applicable; require at least quarterly updating of an online map of golden mussel observations by CDFW; and require the California Department of Food and Agriculture and the State Water Resources Control Board to quickly and efficiently respond to the threat of golden mussels, among other provisions, as provided. (This bill is pending before this Committee.)
AB 2787 (Assembly Water, Parks, and Wildlife Committee, 2026) among other things, provides that a person who operates a Nevada-registered vessel on the waters of Lake Tahoe or Topaz Lake shall not be cited for operation of a vessel without a valid state-issued invasive mussel sticker, provided that Nevada has a program in effect for the management of aquatic invasive species. (This bill is pending before this Committee.)
AB 1894 (B. Rubio, 2026) would prevent a public agency from prohibiting imported water deliveries for groundwater replenishment due to invasive mussels unless there is substantial, documented evidence of a proven health and safety risk as a result of the invasive mussels. (This bill is pending before the Senate Appropriations Committee.)
AB 149 (Assembly Budget Committee, Chapter 106, Statutes of 2025), among other things, expanded statute and programs from “dreissenid mussels” to “invasive mussels,” establishes a requirement for CDFW to review and approve updated invasive mussel control plans, and increased the invasive mussel fee.
AB 1150 (Assembly Water, Parks, and Wildlife Committee, Chapter 831, Statutes of 2023), among other things, distinguished that the issuance and collection of the quagga and zebra mussel infestation and prevention fee from the biennial registration renewal.
AB 2443 (Williams, Chapter 485, Statutes of 2012), establishes the quagga and zebra mussel infestation prevention program, which required payment of the invasive mussel fee on vessels and permitted the use of the funds for, among other things, a grant program.
AB 1929 (Hall, Chapter 152, Statutes of 2010) determines that a water operator is indemnified from the penalty of possessing and transporting a restricted species, if the water operator is in compliance with an approved control plan.
AB 2065 (Hancock, Chapter 667, Statutes of 2008) requires reservoir managers to undertake certain measures to prevent invasive mussel infestation in reservoirs in which invasives mussels have not been detected.
AB 1683 (Wolk, Chapter 419, Statutes of 2007) prohibits a person to possess, import, ship, or transport in the state, or place, plant, or cause to be placed or planted in any water within the state, dreissenid mussels, unless authorized by CDFW. Additionally, authorizes the Director of CDFW, or the Director’s designee, to conduct inspections of conveyances (e.g., vehicles and boats), order that the conveyance be drained, dried, or decontaminated, impound or quarantine conveyances, and conduct inspections of waters of the state and facilities that may contain invasive mussels. Further, requires water operators to implement measures to avoid dreissenid mussel infestation and develop a control plan upon infestation, among other things.
Committee amendments and the legislative calendar. As noted above, this bill is double referred to this Committee and the Senate Judiciary Committee. Due to the time necessary to process committee amendments, any amendments committed to by the author in this Committee, will be formally taken in the Senate Judiciary Committee in order to ensure that the Senate Judiciary Committee gains possession of the bill in a timely manner.
SUGGESTED AMENDMENTS
AMENDMENT 1
Add proposed FGC §2301.1(g):
(g) The operator of a water supply system with an approved control plan pursuant to section 2301 and who operates or contracts for the operation of their own inspection and decontamination stations for their own water supply system may choose to continue to use the inspection and decontamination stations dedicated to their water supply system upon notification to the department. The operators shall provide to the department documentation of the inspection, decontamination and other relevant processes and procedures used to prevent the introduction of invasive mussel species to their water supply system.
AMENDMENT 2
Add to the end of proposed FGC §2301.7(a): “Participation by a public or private agency in any reciprocity agreement is voluntary.”
AMENDMENT 3
Add proposed FGC §2301.6(f):
(f) Data gathered by the WID Data Sharing System or its equivalent shall be used solely for the purposes of the prevention of invasive mussel species infestations of the state’s waterbodies and shall not be sold, bartered, or provided to other public or private parties, or used in any other way for any other purpose.
SUPPORT
Association of California Water Agencies (if amended)
County of San Joaquin
County of Siskiyou
Filoli
National Marine Manufacturers Association
SePRO Corporation
South San Joaquin Irrigation District
Upper San Gabriel Valley Municipal Water District
Valley Ag Water Coalition
OPPOSITION
Boat Owners Association of the United States (unless amended)
Recreational Boaters of California (unless amended)
-- END --
There are and have been additional invasive bivalves in state waters beyond the quagga and zebra mussels, but these two were of particular interest due to their ability to clog pipes and cover and inhibit the operation of water supply infrastructure. ↑
Restricted species permitting is located in Title 14, California Code of Regulations, §§671 et seq. Specifically for dreissenid mussels, state regulation authorizes a dressenid mussel permit to possess the species in prescribed circumstances (Title 14, California Code of Regulations, §672 or 14 CCR §672). ↑
Image from “California scales back golden mussel safeguards at vital reservoir, alarming experts” by Rachel Becker in CalMatters, dated June 12, 2026. ↑
From “California’s waterways could get clogged by a problem that didn’t exist two years ago” by Kurt Alexander in the San Francisco Chronicle, dated June 14, 2026. ↑
“Responses to ballooning mussel infestation range from full-on combat to getting ready to make a plan” by Lois Henry in SJV Water, dated April 24, 2026. ↑
“California must step up to fight the costly golden mussel infestation” opinion by Michelle Paul, in the Sacramento Bee, dated May 23, 2026. ↑
ASSEMBLY THIRD READING
ATR Bill Id:AB 1772
Author:(Papan)
As Amended Ver:April 27, 2026
Majority vote
SUMMARY
Authorizes the California Department of Fish and Wildlife (CDFW) to decontaminate or order the decontamination of a conveyance found or reasonably believed to harbor aquatic invasive species and specifies other actions to help combat the spread of invasive golden mussels in the state.
Major Provisions
- Extends the authority of the director of CDFW to require a conveyance be dried for not more than 30 days, before launching into waters of the state and allows the owner to retain possession of the conveyance during the drying period, subject to any requirements established by CDFW.
- Authorizes CDFW to decontaminate or order the decontamination of a conveyance found or reasonably believed to harbor aquatic invasive species after an inspection conducted pursuant to existing law. Further, requires CDFW to establish standards and procedures for decontaminating conveyances and disposing of organisms and organic materials and requires specific outcomes of those standards and procedures.
- Prohibits a conveyance from being launched into the waters of the state under specified conditions.
- Permits a law enforcement officer to detain or impound the conveyance until the decontamination is complete and determines that the owner of a conveyance is liable for all costs associated with the decontamination or impoundment if the owner fails to cooperate.
- Allows CDFW to issue an inspection, decontamination, or quarantine certificate to the owner or possessor of a conveyance that has been inspected and requires the certificate to reflect certain information and specifies numerous requirements and authorities for CDFW related to inspection and decontamination certificates.
COMMENTS
On October 17, 2024, Department of Water Resources staff discovered golden mussels in the Port of Stockton. Soon after the initial discovery, the golden mussel was quickly found at additional sites within the Sacramento-San Joaquin Delta (Delta). The golden mussel is a freshwater bivalve native to the rivers and creeks of China and Southeast Asia, but it has established itself outside of its native range in several countries. The discovery in Stockton was the first detection of the species in the United States. The Fish and Game Commission quickly took emergency action to add "Limnoperna fortunei (golden mussel)" to the list of restricted species (species that cannot be imported, transported, or possessed within the state, except by a restricted species permit). Since then, the golden mussel has been detected throughout the Delta and the State Water Project. The presence of the species poses a significant and immediate threat to the ecological health of the Delta and all waters of the state, water conveyance systems, infrastructure, and water quality.
Golden mussels have proven to be much more difficult for the state and water managers to control. Golden mussels have high reproductive rates and form dense colonies. This mass colonization of surfaces (termed "biofouling") blocks, impairs, and, in many cases, inhibits the functionality of manmade surfaces including underwater intakes, structures, and mechanisms. Biofouling also coats the hulls and external components of watercraft and recreational facilities, and natural objects such as rocks, fallen trees, even other sedentary bivalves. In addition, mass colonies of golden mussels alter ecological processes of the natural environment resulting in detrimental impacts to native and game species and water quality. Nearly every fresh and brackish waterbody in California is suitable for golden mussels. Indeed, the Water, Parks, and Wildlife Committee has heard of countless examples of the issues golden mussel infestation has been causing for water infrastructure and the recreational boating industry. Even the fear of infestation has resulted in water operators heavily restricting, or even prohibiting, water access for public recreation.
There are no socially and environmentally benign methods currently available to eliminate invasive mussels once they are present. Adult mussels can survive days, even weeks, when removed from water. Larval mussels can survive a week or longer in small volumes of water. Eradication from large, interconnected bodies of water is likely impossible. Therefore, containing mussels within infested areas is the only means to minimize additional new, widespread impacts.
While the spread of invasive mussels in interconnected waters cannot be prevented without restricting navigation, their overland spread, attached to and within watercraft and equipment (vessels), can be prevented. If a vessel carrying live invasive mussels is launched into an un-infested waterbody, it can result in a new mussel infestation. The risk that any given vessel poses for spreading invasive mussels is dependent on the type of conveyance, and the behavior of the boater. Depending on the type of watercraft and when it will be next launched, preventing the overland spread of mussels can be as simple as boaters draining water upon exit from a waterbody and allowing their watercraft to dry prior to their next launch, or a rigorous professional cleaning, which requires labor- and time-intensive hot-water, high-pressure washing, or weeks out of water, depending on the season, waiting for entrapped mussels to die.
When golden mussels were first discovered in the Delta, some water managers stood up inspection programs that imposed a variety of requirements before an individual could launch a vessel, including a minimum dry period of 30 days prior to launch. Watercraft that did not pass their inspection were turned away. Water managers that already had watercraft inspection programs in place continued to conduct inspections as they always had, while some increased the requirements for watercraft to launch (including mandatory decontamination if the prior launch was at that same waterbody). Access to reservoirs throughout the state is controlled by water managers, and the management of that access varies considerably across different waterbodies. As a result, public boating access has been significantly disrupted since October 2024, affecting recreational boaters and anglers, tourism, and local economies. To date, CDFW is aware of four watercraft intercepted by these programs with adult golden mussel attached.
The Western Regional Panel on Aquatic Nuisance Species and partners have produced two primary guidance documents for managing vessel inspection and decontamination processes and standards. These are the Uniform Minimum Protocols and Standards for Inspection and Decontamination Programs for Dreissenid Mussels in the Western United States (UMPS) and Watercraft Inspection and Decontamination (WID) Manual. WID outlines science-based prevention and containment protocols and procedures to reduce the risk of invasive mussels and other aquatic invasive species being introduced or spread in a system. WID is informed by UMPS, which uses best available science to establish a consistent, quality standard that the Western U.S. may adopt to reduce invasive species spread. For example, UMPS elucidates specifications for the most effective mussel decontamination from vessels, including the temperatures, duration, volume, and force of water necessary to decontaminate a vessel and trailer.
According to the Author
"[This bill] will use a long-term, stakeholder-driven framework to address both the rapid spread of invasive golden mussels and future aquatic invasive species, protecting California's environment, water infrastructure, recreation, and economy. First detected in California in 2024, golden mussels are more adaptable than previous invasive mussels, enabling rapid spread and devastating impacts: clogging water systems, increasing infrastructure costs, disrupting recreation, and harming native ecosystems.
Arguments in Support
Several entities write in support of this bill. The National Marine Manufacturers Association (NMMA) writes that "The discovery of golden mussel in California's Sacramento–San Joaquin Delta was a turning point for our state's water resources, natural ecosystems, and recreational boating communities. This destructive species can rapidly outcompete native mussels, clog water infrastructure, impair water quality, and ultimately lead to public agencies closing water access to boaters and non-motorized paddle craft. These closures have immediate consequences for local economies, outdoor recreation, and the hundreds of thousands of Californians whose livelihood relies on boating and fishing." Further NMMA writes in support of the stakeholder process the author is employing to "build the best framework to address this growing threat."
The California Tahoe Alliance (Alliance) supports the intent of this bill and notes that the introduction of invasive mussels, such as the golden mussel, could have devastating consequences on Lake Tahoe's famed clarity, delicate ecosystem, and $5 billion annual recreation and tourism-based economy. They share that a 2009 estimate by the Army Corps of Engineers indicated that invasive mussels could lead to annual losses of $22 million ($33 million in 2025 dollars) in the Lake Tahoe Region, impacting tourism, property values, and maintenance costs. The Alliance also indicates that the Tahoe Regional Planning Agency has implemented boat inspection procedures that prevented 72 boats with aquatic invasive species (including one boat with golden mussels) from entering Lake Tahoe in 2025 alone.
Several water agencies also write in support. Upper San Gabriel Municipal Water District summarizes their positions with "This commonsense legislation addresses the challenges facing recreational boating and water management communities in the prevention and decontamination of invasive mussels, while also identifying and implementing alternative and equitable funding sources."
Arguments in Opposition
None on file.
FISCAL COMMENTS
According to the Assembly Appropriations Committee, this bill has the following fiscal impact:
- CDFW will incur significant ongoing annual General Fund costs, possibly in the tens of millions of dollars, to decontaminate or order the decontamination of conveyances with invasive species, in accordance with requirements specified in this bill, and to establish standards and procedures for decontaminating conveyances and disposing of organisms and organic materials so that no viable invasive mussels remain on or in the conveyance before launch.
For its part, CDFW estimates General Fund costs of approximately $68.5 million in fiscal year (FY) 2027-28 for 82 positions, vehicles, equipment, decontamination stations, and other one-time costs, followed by ongoing annual General Fund costs of about $43 million for the 82 positions (one senior environmental scientist specialist, three environmental scientists, one analyst, one marketing specialist, two research scientists, 65 fish and wildlife technicians, and nine lieutenant specialists). CDFW contends these positions are needed to decontaminate every conveyance used in infested waterbodies and for related enforcement (particularly in the Delta and Southern California). CDFW notes it would need to lease, site, and install hot water dip tanks and high-pressure hot water decontamination stations at 65 sites around mussel-infested waters and maintain such equipment. Other tasks include conducting golden mussel research to inform management decision-making, enforcing invasive species regulations, supporting local agency prevention programs, deploying K9 scent teams for conveyance inspections, conducting outreach, developing messaging and material tailored to niche user groups educating them on preventing the spread of mussels, providing local invasive mussel expertise to water managers and the public, providing technical assistance and training to water managers implementing watercraft inspection programs and encouraging their participation in the reciprocal program, implementing early detection monitoring for invasive mussels, quarantining conveyances, and other related tasks.
As part of the Governor’s proposed FY 2026-27 budget, CDFW is requesting eight permanent positions to add invasive mussel containment capacity primarily to Central and Northern California to ensure conveyances leaving the Delta do not move golden mussels to un-infested waters statewide through complementary actions implemented by the CDFW, the public, and federal, state, and local agencies. The administration intends to fund these positions for three years from $20 million appropriated to CDFW in the 2025 Budget Act. It is not clear if any of these resources, if approved by the Legislature this year, may be used to implement some of the requirements of this bill.
- The Department of Parks and Recreation (State Parks), which oversees the Division of Boating and Waterways (DBW), estimates ongoing annual General Fund costs of $30 million to support inspection and decontamination stations, associated staff, equipment, and materials for reservoirs operated or managed by State Parks. State Parks notes its estimate may evolve and is contingent on program standards and procedures to be determined by CDFW, as required by the bill.
While this bill puts CDFW in the lead, State Parks notes that as the operator or manager of ten lakes and reservoirs, State Parks is responsible for invasive mussel inspection and prevention efforts, pursuant to the Fish and Game Code, which requires owners and managers of reservoirs to assess the vulnerability of the reservoir for the introduction of invasive mussel species and develop and implement a program (including public education, monitoring, and management of permitted recreational, boating, or fishing activities) designed to prevent the introduction of invasive mussel species. For this reason, State Parks expects to incur significant costs to implement the control measures outlined in the bill and to expand State Parks' current inspection and prevention efforts to additional lakes and reservoirs.
DBW administers an invasive mussel prevention grant program, which is currently being revised through emergency regulations to include golden mussel prevention; however, given the magnitude of the golden mussel infestation challenge and the associated costs, the invasive mussel fee is not a reliable funding source for agencies’ workload and implementation costs.
- The State Water Resources Control Board and Department of Justice anticipate any costs to be minor and absorbable.
The Legislative Analyst's Office recently warned of General Fund structural deficits of around $35 billion per year in the 2027-28 FY and ongoing.
VOTES
ASM WATER, PARKS, AND WILDLIFE: 12-0-1
YES: Papan, Jeff Gonzalez, Alanis, Alvarez, Ávila Farías, Bains, Bennett, Boerner, Caloza, Gallagher, Hart, Rogers
ABS, ABST OR NV: Celeste Rodriguez
ASM APPROPRIATIONS: 15-0-0
YES: Wicks, Hoover, Aguiar-Curry, Calderon, Caloza, Dixon, Fong, Mark González, Krell, Pacheco, Pellerin, Sharp-Collins, Solache, Ta, Tangipa
UPDATED
VERSION: April 27, 2026
CONSULTANT: Stephanie Mitchell / W., P., & W. / (916) 319-2096 FN: 0002700
Date of Hearing: May 13, 2026
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Buffy Wicks, Chair
ABPCA Bill Id:AB 1772
Author:(Papan) – As Amended Ver:April 27, 2026
Policy Committee: | Water, Parks and Wildlife | Vote: | 12 - 0 |
|
| ||
|
|
Urgency: No State Mandated Local Program: Yes Reimbursable: No
SUMMARY:
This bill, among other things, authorizes the California Department of Fish and Wildlife (CDFW) to decontaminate or order the decontamination of a conveyance found or reasonably believed to harbor aquatic invasive species and specifies other actions to help combat the spread of invasive golden mussels in the state.
Specifically, this bill, among other things:
1) For an order by the director of CDFW that areas in a conveyance (that may carry or contain invasive mussels) that contain water be dried, pursuant to procedures approved by the department:
(a) Allows the order to require the owner or person in possession of the conveyance to dry the conveyance for a designated period of time, not to exceed 30 days, before launching into waters of the state. A conveyance shall not be launched until the required drying period has been completed.
b) Authorizes an owner or person in possession of the conveyance, if issued an order to dry, to retain possession of the conveyance during the drying period, subject to any requirements established by CDFW.
2) Directs CDFW to require water supply system operators to update their plans to address all invasive mussel species present in the operator’s water system as of January 1, 2026, as provided; requires a plan to address every invasive mussel species detected in a water supply system after January 1, 2026, no later than 180 days from the date the species is detected; requires a plan to minimize or eliminate the spread of invasive mussels; and changes the definition of “invasive mussel” to mean a nonnative biofouling mussel species.
3) (a) Authorizes CDFW to decontaminate or order the decontamination of a conveyance found or reasonably believed to harbor aquatic invasive species after an inspection conducted pursuant to existing law; (b) requires CDFW to establish standards and procedures for decontaminating conveyances and disposing of organisms and organic materials; (c) requires these standards and procedures to be effective at removing or destroying invasive mussels and to be performed in a manner that ensures no viable invasive mussels remain on or in the conveyance before launch; (d) requires decontamination to include at least four measures specified in the bill; and (e) requires CDFW to implement (a) in a manner consistent with the requirements for decontamination in (d) regardless of whether the department has adopted standards and procedures for decontamination pursuant to (c).
4) Requires that a conveyance, before launch into the waters of the state, be subject to decontamination if any of four specified conditions exist.
5) Provides that (a) if a person refuses to submit to decontamination of a conveyance or due to personal hardship is unable to immediately accompany the conveyance for decontamination, a law enforcement officer may detain or impound the conveyance until the decontamination is complete; (b) the owner of a conveyance that is decontaminated or detained due to failure to cooperate by the owner or person in possession of the conveyance is liable for all costs associated with the decontamination or impoundment, in accordance with applicable rules promulgated by CDFW; and (c) pursuant to existing law, CDFW and any other state agency exercising authority under specified sections of this bill are not liable to any person for any loss resulting from damage to conveyances as the result of inspection or decontamination, provided CDFW adhered to all rules promulgated by the department under this bill.
6) Allows CDFW to issue an inspection, decontamination, or quarantine certificate to the owner or person in possession of a conveyance that has been inspected pursuant to existing law, requires the certificate to reflect certain information, and specifies numerous requirements and authorities for CDFW related to inspection and decontamination certificates.
7) States the intent of the Legislature to subsequently amend this bill to identify and implement, to the extent feasible, alternative and equitable funding sources beyond fees imposed on the recreational boating community, such as assessments on commercial activities, including on international cargo shipping operations that may impact the introduction of aquatic invasive species to California waters.
FISCAL EFFECT:
1) CDFW will incur significant ongoing annual General Fund costs, possibly in the tens of millions of dollars, to decontaminate or order the decontamination of conveyances with invasive species, in accordance with requirements specified in the bill, and to establish standards and procedures for decontaminating conveyances and disposing of organisms and organic materials so that no viable invasive mussels remain on or in the conveyance before launch.
For its part, CDFW estimates General Fund costs of approximately $68.5 million in fiscal year (FY) 2027-28 for 82 positions, vehicles, equipment, decontamination stations, and other one-time costs, followed by ongoing annual General Fund costs of about $43 million for the 82 positions (one senior environmental scientist specialist, three environmental scientists, one analyst, one marketing specialist, two research scientists, 65 fish and wildlife technicians, and nine lieutenant specialists). CDFW contends these positions are needed to decontaminate every conveyance used in infested waterbodies and for related enforcement (particularly in the Sacramento-San Joaquin Delta (Delta) and Southern California). CDFW notes it would need to lease, site, and install hot water dip tanks and high-pressure hot water decontamination stations at 65 sites around mussel-infested waters and maintain such equipment. Other tasks include conducting golden mussel research to inform management decisionmaking, enforcing invasive species regulations, supporting local agency prevention programs, deploying K9 scent teams for conveyance inspections, conducting outreach, developing messaging and material tailored to niche user groups educating them on preventing the spread of mussels, providing local invasive mussel expertise to water managers and the public, providing technical assistance and training to water managers implementing watercraft inspection programs and encouraging their participation in the reciprocal program, implementing early detection monitoring for invasive mussels, quarantining conveyances, and other related tasks.
As part of the Governor’s proposed FY 2026-27 budget, CDFW is requesting eight permanent positions to add invasive mussel containment capacity primarily to Central and Northern California to ensure conveyances leaving the Delta do not move golden mussels to un-infested waters statewide through complementary actions implemented by the department, the public, and federal, state, and local agencies. The administration intends to fund these positions for three years from $20 million appropriated to CDFW in the 2025 Budget Act. It is not clear to the committee if any of these resources, if approved by the Legislature this year, may be used to implement some of the requirements of this bill.
2) The Department of Parks and Recreation (State Parks), which oversees the Division of Boating and Waterways (DBW), estimates ongoing annual General Fund costs of $30 million to support inspection and decontamination stations, associated staff, equipment, and materials for reservoirs operated or managed by State Parks. The department notes its estimate may evolve and is contingent on program standards and procedures to be determined by CDFW, as required by the bill.
While this bill puts CDFW in the lead, State Parks notes that as the operator or manager of 10 lakes and reservoirs, State Parks is responsible for invasive mussel inspection and prevention efforts, pursuant to the Fish and Game Code, which requires owners and managers of reservoirs to assess the vulnerability of the reservoir for the introduction of invasive mussel species and develop and implement a program (including public education, monitoring, and management of permitted recreational, boating, or fishing activities) designed to prevent the introduction of invasive mussel species. For this reason, State Parks expects to incur significant costs to implement the control measures outlined in the bill and to expand State Parks’ current inspection and prevention efforts to additional lakes and reservoirs.
As discussed in the background, DBW administers an invasive mussel prevention grant program, which is currently being revised through emergency regulations to include golden mussel prevention; however, given the magnitude of the golden mussel infestation challenge and the associated costs, the invasive mussel fee is not a reliable funding source for agencies’ workload and implementation costs.
The author may wish to more clearly define and delineate the roles and responsibilities of different state agencies, particularly CDFW and State Parks, to reduce costs and avoid duplication of efforts.
3) The State Water Resources Control Board and Department of Justice anticipate any costs to be minor and absorbable.
The Legislative Analyst’s Office recently warned of General Fund structural deficits of around $35 billion per year in the 2027-28 FY and ongoing.
COMMENTS:
1) Purpose. According to the author:
[This bill] will use a long-term, stakeholder-driven framework to address both the rapid spread of invasive golden mussels and future aquatic invasive species, protecting California’s environment, water infrastructure, recreation, and economy…While recent legislation has taken important first steps, California still lacks a coordinated, forward-looking strategy to manage this growing threat.
2) Background. According to CDFW, golden mussels are an invasive bivalve. Adult mussels form byssal threads that enable them to attach to surfaces and spawn multiple times each year, producing thousands of offspring. In October 2024, golden mussels were discovered in the Delta – the first known occurrence in North America. Since then, golden mussels have been detected throughout the Delta and the State Water Project (SWP).
Golden mussels have been linked to a loss of native and game fish, because they compete for the same food sources, and contribute to harmful fish-killing algal blooms. Recreational impacts include waterbody closures, mandatory inspections, increased boat launch or entry fees, and reduced numbers of fish and shellfish for consumption. Economic impacts include costly repairs and maintenance (boats, water infrastructure, hydroelectric facilities) and reduced water flow affecting food production, water delivery to homes, and flood control.
The most common way invasive mussels move between waterbodies is by hitchhiking on watercraft and equipment. According to CDFW, there are no socially and environmentally benign methods currently available to eliminate invasive mussels once they are present. Therefore, containing mussels within infested areas is the only means to minimize additional new, widespread impacts. While the spread of invasive mussels in interconnected waters cannot be prevented without restricting navigation, their overland spread, attached to and within watercraft and equipment, may be prevented.
Since the discovery of golden mussels in the state, CDFW has been coordinating with other agencies to survey the extent of infestation in the Delta, sample for golden mussels in waters statewide, and update existing outreach and educational material to include golden mussels. CDFW also formed an interagency Golden Mussel Task Force that developed a statewide Golden Mussel Response Framework in April 2025. This proposal to respond to golden mussels builds on the department’s existing capacity within the Invasive Species Program’s Quagga and Zebra Mussel Project, which works to contain and limit the spread of these invasive species in the state.
Under this project, motorized boats pay an infestation prevention fee (via a sticker issued by the Department of Motor Vehicles), and revenues from the fee are primarily used for grants distributed by DBW. The current sticker is collected every two years, and as of January 2026, the fee for the sticker is $16 and expires at the same time as the vessel registration renewal sticker. To date, in FY 2025-26, CDFW has collected approximately $2.5 million in fees, and DBW expects to award up to $2 million in grants to eligible applicants in 2026.
Budget trailer language in 2025, among other things, extended the state’s quagga and zebra mussel protections to golden mussels, expanded the current mussel sticker fee to include golden mussels, and allowed the fee to increase from up to $30 to up to $42. To date, sticker fees have not been used for golden mussels; however, DBW is promulgating emergency regulations to comply with last year’s budget trailer language – specifically to change the name of the current grant program to add golden mussels and to establish a technical advisory group to increase the sticker fee to enable a more robust response to the invasion of golden mussels. Currently, affected water agencies are required to submit golden mussel control plans to CDFW; agencies are in the process of completing these plans.
The author contends this bill creates a “platform for broad stakeholder engagement to develop durable, widely supported strategies to combat golden mussels and future aquatic invasive species.” The author notes the bill accomplishes this objective by establishing a statewide decontamination standard for waterborne vessels, developing a system of reciprocity that recognizes and honors certifications of decontamination for vessels and equipment moving between non-infested waterbodies, and identifying alternative funding sources beyond the recreational boating community.
Analysis Prepared by: Nikita Koraddi / APPR. / (916) 319-2081
Date of Hearing: April 23, 2026
ASSEMBLY COMMITTEE ON WATER, PARKS, AND WILDLIFE
Diane Papan, Chair
ABPCA Bill Id:AB 1772 (
Author:Papan) – As Amended Ver:March 23, 2026
SUBJECT: Fish and wildlife: invasive mussels
SUMMARY: Requires the California Department of Fish and Wildlife (CDFW) to develop a voluntary framework to prevent the overland spread of invasive mussels via watercraft. Specifically, this bill:
- Requires CDFW, in consultation with the Department of Parks and Recreation (State Parks) and the Department of Food and Agriculture (CDFA), to develop a voluntary framework to prevent the overland spread of invasive mussels through the conveyance of watercraft overland. Requires the framework to include all of the following:
- Minimum standards for watercraft inspection, decontamination, and quarantine based on best available science and aligned with national standards as feasible;
- A banding program or other mechanisms by which to confirm the inspection, decontamination, or quarantine status of a watercraft;
- Training and quality assurance metrics to encourage consistent inspection, decontamination, and tracking of vessels across waterbodies;
- A publicly available list of participating inspection and decontamination services statewide; and
- Education and outreach opportunities and materials to reduce the spread of invasive mussels and encourage compliance with and participation in the framework;
- Changes the definition of “invasive mussel” to mean a nonnative biofouling mussel species.
- Makes technical changes.
- Finds and declares that aquatic invasive species, such as the golden mussel, threaten the ecological health, recreational value, and operational integrity of California’s lakes, rivers, reservoirs, and water conveyance facilities.
- States that it is the intent of the Legislature that:
- This bill create a statewide database to voluntarily track the movement of vessels, equipment, and other vectors among California waterbodies, providing waterbody managers with accurate information on the prior contamination status of these vessels.
- This bill develop a system of reciprocity that recognizes and honors certifications of decontamination for vessels and equipment moving between noninfested waterbodies, thereby facilitating safe recreational access.
- This bill be amended to identify and implement, to the extent feasible, alternative and equitable funding sources beyond fees imposed on the recreational boating community, such as assessments on commercial activities, including on international cargo shipping operations, that may impact the introduction of aquatic invasive species to California waters.
EXISTING LAW:
- Until January 1, 2030, prohibits a person from possessing, importing, shipping, or transporting in the state, or placing, planting, or causing to be placed or planted in any water within the state, invasive mussels, unless authorized by CDFW.
- Provides the Director of CDFW, or a designee of the Director, the authority to conduct inspections of conveyances (e.g., vehicles and boats), order that the conveyance be drained, dried, or decontaminated, impound or quarantine conveyances, and conduct inspections of waters of the state and facilities that may contain invasive mussels. Permits the Director of CDFW to determine that other parties or state agencies, including State Parks, the Department of Water Resources (DWR), CDFA, and the State Lands Commission, may exercise those authorities as well.
- Exempts from the California Environmental Quality Act (CEQA), any action in Existing Law #1, above, but does not exempt from CEQA the use of chemicals, other than salt or hot water, to decontaminate a conveyance or facility.
- Requires a public or private agency that operates a water supply system (water operator) to cooperate with CDFW to implement measures to avoid infestation by invasive mussels and to control or eradicate any infestation that may occur in a water supply system. If invasive mussels are detected, the water operator, in cooperation with CDFW, shall prepare and implement a plan to control or eradicate invasive mussels within the system, and eliminate or minimize any potential downstream transport of an invasive mussel. Requires the approved plan to contain the following minimum elements:
- Methods for delineation of infestation, including both adult mussels and veligers;
- Methods for control or eradication of adult mussels and decontamination of water containing veligers;
- A systematic monitoring program to determine any changes in conditions; and
- The requirement that the water operator permit inspections by CDFW as well as cooperate with CDFW to update or revise control or eradication measures in the approved plan to address scientific advances in the methods of controlling or eradicating mussels and veligers.
- If the water operator has prepared, initiated, and is in compliance with all the elements of an approved plan to control or eradicate invasive mussels in accordance with Existing Law #1 (b), the restrictions of Existing Law #1, above, do not apply to the operation of those water delivery and storage facilities, and the water operator is not subject to any civil or criminal liability for the introduction of invasive mussel species as a result of those operations. Authorizes CDFW to require the water operator to update its plan. Authorizes CDFW to apply the restrictions on a water operator if the plan is not updated or revised, until the water operator updates or revises the plan.
- Requires CDFW, on or before December 31, 2026, to review all approved plans pursuant (c) and requires all plans that do not specifically address all invasive mussel species known to be present in bodies of water in the state as of January 1, 2026, to be updated or revised appropriately to include all invasive mussel species, on or before September 30, 2027.
- Requires every invasive mussel species to be addressed in a plan no later than 180 days from the date that the species is listed in a regulation. Requires CDFW to approve plans or provide written comments and suggestions on plan deficiencies within 180 days from the date of plan submission.
- Requires an entity that discovers invasive mussels within this state to immediately report the discovery to CDFW.
- Establishes an additional penalty for any violation of Existing Law #1 with a penalty not to exceed $1,000.
- Allows CDFW to adopt regulations to carry out the restrictions in Existing Law #1.
- Indemnifies CDFW and any other state agency exercising authority under Existing Law #1 with regard to any determination or authorization made pursuant to this section [Fish and Game Code (FGC) § 2301]
- Requires any person, or federal, state, or local agency, district, or authority that owns or manages a reservoir (reservoir manager) to undertake certain measures to prevent invasive mussel infestation, in reservoirs in which invasives mussels have not been detected.
- Requires a reservoir manager responsible for a reservoir, where recreational, boating, or fishing activities are permitted, except a privately owned reservoir that is not open to the public, to:
- Assess the vulnerability of the reservoir for the introduction of invasive mussel species; and
- Develop and implement a program designed to prevent the introduction of invasive mussel species. Requires the program to, at a minimum, include public education, monitoring, and management of those recreational, boating, or fishing activities that are permitted.
- Requires a reservoir manager responsible for a reservoir, where recreational, boating, or fishing activities of any kind are not permitted, to include visual monitoring for the presence of mussels as part of its routine field activities, based on its available resources and staffing.
- Allows a reservoir manager, except a privately owned reservoir that is not open to the public, to refuse the planting of fish in that reservoir by CDFW unless CDFW can demonstrate that the fish planting does not present a risk of introducing invasive mussels.
- Establishes a civil penalty, not to exceed $1,000 per violation of Existing Law #2, above. Authorizes CDFW to adopt regulations to implement and enforce requirements on reservoir managers to the extent funds are available (FGC § 2302).
- Requires a reservoir manager responsible for a reservoir, where recreational, boating, or fishing activities are permitted, except a privately owned reservoir that is not open to the public, to:
- Defines “invasive mussel” to mean any nonnative detrimental mussel species that is capable of spreading in freshwater and is listed in a regulation adopted by the Fish and Game Commission (FGC § 2303).
- Requires the Department of Motor Vehicles (DMV) to collect for resident and nonresident vessel owners, separate from the registration fee, an invasive mussel infestation prevention fee (invasive mussel fee) in an amount established by the Division of Boating and Waterways (DBW).
- Requires DMV to issue an invasive mussel infestation prevention sticker (invasive mussel sticker) to the vessel owner, upon payment of the mussel fee.
- Authorizes the citation of a vessel operator for operating a recreational vessel in nonmarine waters without a valid state-issued invasive mussel infestation prevention sticker (Vehicle Code § 9853).
- Requires the invasive mussel fee to be paid to DBW.
- Establishes the invasive mussel fee to be between $30 and $42, every other year. Requires those values to be adjusted for inflation. Requires DBW to establish and consult with a technical advisory group to determine the fee.
- Permits DBW to adopt emergency regulations to manage the collection and use of the invasive mussel fees.
- Requires all revenue from the invasive mussel fee to be deposited into the Harbors and Watercraft Revolving Fund.
- Clarifies that a vessel operator may be issued a citation for operating a recreational vessel in nonmarine waters without a valid state-issued invasive mussel sticker [Harbors and Navigation Code (HNC) § 675].
- Establishes how revenues from the invasive mussel fee may be used.
- Requires the moneys deposited into the Harbors and Watercraft Revolving Fund be used for:
- The reasonable costs incurred by DBW associated with determining the invasive mussel fee and adoption of regulations and with administering the grants.
- The reasonable costs, not to exceed 15% of the remaining revenues, of CDFW for implementation of invasive mussel regulations in those areas of the state where an invasive mussel infestation prevention plan has not been implemented.
- Grants to reservoir managers subject for the reasonable regulatory costs incident to the implementation of an invasive mussel infestation prevention plan. At least 85% of the revenue must be used for this purpose.
- Requires DBW, when awarding grants, to:
- Give priority to invasive mussel infestation prevention plans that meet requirements and that also include visual and manual inspection standards and other infestation prevention procedures consistent with established or future state adopted guidebooks and management plans;
- Take into consideration the benefits of regional-scale invasive mussel infestation prevention plans; and
- Take into consideration the unique economic, ecological, and recreational impacts to rural and urban reservoirs from invasive mussel infestation.
- Prohibits the use of invasive mussel fees for any purpose other than those explicitly authorized (HNC § 676).
- Requires the moneys deposited into the Harbors and Watercraft Revolving Fund be used for:
- Prohibits the importation, transportation, possession, or live release of specified wild animals into this state except under a revocable, nontransferable restricted species permit issued by CDFW, in cooperation with CDFA (FGC § 2116 et seq.; 14 California Code of Regulations 14 § 671 et seq.).
- Provides civil and criminal penalties for violations of invasive mussel restrictions and any permit conditions (FGC § 2125 and § 12000).
FISCAL EFFECT: Unknown. This bill is keyed fiscal.
COMMENTS:
- Purpose of this bill. According to the author, “[This bill] will use a long-term, stakeholder-driven framework to address both the rapid spread of invasive golden mussels and future aquatic invasive species, protecting California’s environment, water infrastructure, recreation, and economy. First detected in California in 2024, golden mussels are more adaptable than previous invasive mussels, enabling rapid spread and devastating impacts: clogging water systems, increasing infrastructure costs, disrupting recreation, and harming native ecosystems.
While recent legislation has taken important first steps, California still lacks a coordinated, forward-looking strategy to manage this growing threat. As it is further developed, [this bill] will establish a framework for statewide coordination, including consistent decontamination standards, reciprocity across waterbodies, and more sustainable funding mechanisms, shifting the state from short-term fixes to a proactive, long-term approach to managing the threat of invasive species.”
Background. On October 17, 2024, DWR staff discovered golden mussels in the Port of Stockton. Soon after the initial discovery, the golden mussel was quickly found at additional sites within the Sacramento-San Joaquin Delta (Delta). The golden mussel is a freshwater bivalve native to the rivers and creeks of China and Southeast Asia, but it has established itself outside of its native range in several countries. The discovery in Stockton was the first detection of the species in the United States. The Fish and Game Commission quickly took emergency action to add “Limnoperna fortunei (golden mussel)” to the list of restricted species (species that cannot be imported, transported, or possessed within the state, except by a restricted species permit). Since then, the golden mussel has been detected throughout the Delta and the State Water Project.
The presence of the species poses a significant and immediate threat to the ecological health of the Delta and all waters of the state, water conveyance systems, infrastructure, and water quality. Environmental impacts of the golden mussel include loss of native and game fish through competition for food sources as well as a contribution to harmful algal blooms. It is estimated that a single mussel can filter up to a liter of water a day, which would remove critical nutrients and microbes that support ecosystem health. Recreational impacts of this mussel include waterbody closures, mandatory inspections, increased launch and/or entry fees, and reduced numbers of fish and shellfish for consumption. Economic impacts include costly repairs and maintenance (e.g., boats, water infrastructure, hydroelectric facilities), reduced water flow affecting food production, water delivery to homes, and flood control. According to the Administration’s budget change proposal regarding golden mussels, “if allowed to spread further, golden mussel will affect every household in California, and every sector of our economy.”
Invasive mussel legislative history. Since 2007, California has been working to control and eradicate two other species of invasive, freshwater mussels in state waters: quagga and zebra (dreissenid) mussels. In response to dreissenid mussel infestation, the Legislature has passed a series of bills that established the dreissenid mussels as restricted species, granted CDFW with authorities to inspect, order treatment, and quarantine water vessels. Since dreissenid mussels are restricted species, a person is prohibited from possessing, importing, shipping, transporting or introducing the dreissenid mussels in any water within the state, unless authorized by CDFW through a restricted species permit.
Further, statute requires water managers to work with CDFW to develop measures to avoid infestation, as well as requires water managers to develop control plans to prevent the spread of the invasive mussels should the water system become infested with the mussels. The benefit of developing a control plan is that water managers enjoy liability protections from the unintentional transportation or introduction of dreissenid mussels to the water system once the control plan is approved by CDFW.
Several years later, the Legislature established the Quagga and Zebra Mussel Infestation Program. Under the current program, an additional fee is charged to motorized boats in the state since motor boat recreation is thought to be the most likely cause of over-land aquatic invasive species spreading. Revenues from the fee are primarily used for grants distributed by DBW. The next round of grants for the program are currently open, and DBW expects to distribute up to $2 million dollars. The grants are available to entities that own or manage any aspect of water in a reservoir that is open for public recreation and is mussel-free. The funds must be used for prevention projects, such as planning, watercraft inspection stations and inspectors, launch monitors, watercraft decontamination units, educational signage, and outreach.
Until last year, statute, and therefore state programming, was specific to quagga and zebra mussels. In AB 149 (see Related Legislation, below), the dreissenid mussel programs and authorities were expanded to include any invasive mussel, which includes the golden mussel.
Don’t move a mussel. Golden mussels have proven to be much more difficult for the state and water managers to control. Golden mussels have high reproductive rates and form dense colonies. This mass colonization of surfaces (termed “biofouling”) blocks, impairs, and, in many cases, inhibits the functionality of manmade surfaces including underwater intakes, structures, and mechanisms. Biofouling also coats the hulls and external components of watercraft and recreational facilities, and natural objects such as rocks, fallen trees, even other sedentary bivalves. In addition, mass colonies of golden mussels alter ecological processes of the natural environment resulting in detrimental impacts to native and game species and water quality. Nearly every fresh and brackish waterbody in California is suitable for golden mussels. Indeed, this Committee has heard of countless examples of the issues golden mussel infestation has been causing for water infrastructure and the recreational boating industry. Even the fear of infestation has resulted in water operators heavily restricting, or even prohibiting, water access for public recreation.
There are no socially and environmentally benign methods currently available to eliminate invasive mussels once they are present. Adult mussels can survive days, even weeks, when removed from water. Larval mussels can survive a week or longer in small volumes of water. Eradication from large, interconnected bodies of water is likely impossible. Therefore, containing mussels within infested areas is the only means to minimize additional new, widespread impacts.
Clean, drain, dry. While the spread of invasive mussels in interconnected waters cannot be prevented without restricting navigation, their overland spread, attached to and within watercraft and equipment (vessels), can be prevented. If a vessel carrying live invasive mussels is launched into an un-infested waterbody, it can result in a new mussel infestation. The risk that any given vessel poses for spreading invasive mussels is dependent on the type of conveyance, and the behavior of the boater. Depending on the type of watercraft and when it will be next launched, preventing the overland spread of mussels can be as simple as boaters draining water upon exit from a waterbody and allowing their watercraft to dry prior to their next launch, or a rigorous professional cleaning, which requires labor- and time-intensive hot-water, high-pressure washing, or weeks out of water, depending on the season, waiting for entrapped mussels to die.
Invasive Species Program. The mission of CDFW’s Invasive Species Program is to reduce the negative effects of non-native invasive species on the wildlands and waterways of California. The program works to prevent the introduction of these species into the state, detect and respond to introductions when they occur, and prevent the spread of invasive species that have become established. Work is conducted in close coordination with other government agencies, non-governmental organizations, and the public to protect the state’s natural environment, economy, and human health. The Invasive Species Program produces an annual internal report that summarizes statewide accomplishments including watercraft quarantines, releases, inspections, decontaminations, finalized mussel prevention and control plans, monitoring efforts, lab, analyses, new mussel detections, outreach events, etc.
Statewide decontamination framework. When golden mussels were first discovered in the Delta, some water managers stood up inspection programs that imposed a variety of requirements before an individual could launch a vessel, including a minimum dry period of 30 days prior to launch. Watercraft that did not pass their inspection were turned away. Water managers that already had watercraft inspection programs in place continued to conduct inspections as they always had, while some increased the requirements for watercraft to launch (including mandatory decontamination if the prior launch was at that same waterbody). Access to reservoirs throughout the state is controlled by water managers, and the management of that access varies considerably across different waterbodies. As a result, public boating access has been significantly disrupted since October 2024, affecting recreational boaters and anglers, tourism, and local economies. To date, CDFW is aware of four watercraft intercepted by these programs with adult golden mussel attached.
The Western Regional Panel on Aquatic Nuisance Species and partners have produced two primary guidance documents for managing vessel inspection and decontamination processes and standards. These are the Uniform Minimum Protocols and Standards for Inspection and Decontamination Programs for Dreissenid Mussels in the Western United States (UMPS) and Watercraft Inspection and Decontamination (WID) Manual. WID outlines science-based prevention and containment protocols and procedures to reduce the risk of invasive mussels and other aquatic invasive species being introduced or spread in a system. WID is informed by UMPS, which uses best available science to establish a consistent, quality standard that the Western U.S. may adopt to reduce invasive species spread. For example, UMPS elucidates specifications for the most effected mussel decontamination from vessels, including the temperatures, duration, volume, and force of water necessary to decontaminate a vessel and trailer.
- Proposed committee amendments. To further detail the structure of an inspection and decontamination framework in the state, the author may wish to make the following amendments:
Addition to findings and declarations:
(6) Inspection programs help prevent the spread of aquatic species via transportation conveyances. These programs provide for the inspection and decontamination of conveyances, as well as an opportunity for outreach and education on the risks posed by the introduction and spread of aquatic invasive species. The programs protect both the environmental and recreational values of the state’s waters and infrastructure and economy.
Amend FGC § 2301:
(B) (i) Order that areas in a conveyance that contain water be drained, dried, or decontaminated pursuant to procedures approved by the department.
(ii) An order to dry pursuant to clause (i) may require the owner or person in possession of the conveyance to dry the conveyance for a designated period of time, not to exceed 30 days, before launching in waters. A conveyance shall not be launched until the required drying period has been completed.
(iii) If issued an order to dry pursuant to clause (i), an owner or person in possession of the conveyance may retain possession of the conveyance during the drying period, subject to any requirements established by the department.
Add sections 2301.1 to FGC:
(a) The department, including personnel authorized by the department, may decontaminate or order the decontamination of a conveyance found or reasonably believed to harbor aquatic invasive species after an inspection conducted pursuant to Section 2301.
(b) (1) The department shall establish standards and procedures for decontaminating conveyances and disposing of organisms and organic materials. These standards and procedures shall be effective at removing or destroying invasive mussels and performed in a manner that ensures no viable invasive mussels remain on or in the conveyance prior to launch.
(2) At a minimum, decontamination shall include all of the following:
(A)Removal of all visible plant materials, mud, and organisms from the conveyance and any associated equipment.
(B)Draining of all water-containing compartments, including, but not limited to, bilges, ballast tanks, live wells, and engine cooling systems.
(C)Treatment of exterior surfaces and all water-contact components using heated water or other department-approved methods demonstrated to achieve morality of invasive species.
(D)Flushing or treatment of internal systems, including engines, ballast systems, and plumbing, in a manner sufficient to eliminate viable invasive mussels.
(3) The department shall implement subdivision (a) in a manner consistent with the requirements for decontamination described in paragraph (2) regardless of whether the department has adopted standards and procedures for decontamination pursuant to paragraph (1).
(c) A conveyance shall be subject to decontamination prior to launch if any of the following conditions exist:
(1) Invasive mussels are detected or reasonably suspected to be present on or in the conveyance.
(2) The conveyance has been operated in or transported from an infested waterbody.
(3) The conveyance contains water in compartments, systems, or structures that cannot be completely drained.
(4) The inspecting authority determines that the conveyance presents a risk of introducing invasive mussels into waters of the state.
(d) If a person refuses to submit to decontamination of a conveyance found or reasonably believed to harbor aquatic invasive species, or due to personal hardship is unable to immediately accompany the conveyance for decontamination, a law enforcement officer may detain or impound the conveyance until the decontamination is complete.
(e) The owner of a conveyance that is decontaminated or detained due to failure to cooperate by the owner or person in possession of the conveyance is liable for all costs associated with the decontamination or impoundment, in accordance with the applicable rules promulgated by the department.
(f) Pursuant to Section 818.4 of the Government Code, the department and any other state agency exercising authority under this section shall not be liable to any person for any loss resulting from damage to conveyances as the result of inspection or decontamination provided the department adhered to all rules promulgated by the department under this section.
Add sections 2301.2 to FGC:
(a) The department, including personnel authorized by the department, may issue an inspection, decontamination, or quarantine certificate to the owner or person in possession of a conveyance that has been inspected pursuant to Section 2301. The certificate shall reflect all of the following:
(1) The name of the department and of the person who conducted the inspection.
(2) The date, place, and time of the inspection.
(3) Any preventative measures performed or ordered.
(4) Any decontamination performed.
(b) If the department issues an inspection, decontamination, or quarantine certificate to the owner or person in possession of the conveyance, the department may attach a tamper-proof device to the conveyance. The device may be a seal, tag, or band that prevents the conveyance from coming in contact with water without being broken.
(c) The department shall establish required retention period for inspection and decontamination certificates issued under this section.
(d) The department may recognize, by reciprocity, an inspection or decontamination certificate issued by another government entity, if the other governmental entity adheres to the minimum standards for inspection, decontamination, and quarantine established in agreed upon standard protocols, such as the Uniform Minimum Protocols and Standards for Watercraft Interception Programs.
(e) Pursuant to Section 818.4 of the Government Code, the department and any other state agency exercising authority under this section shall not be liable to any person for any loss resulting from damage to conveyances as the result of inspection or decontamination provided the department adhered to all rules promulgated by the department under this section.
- Arguments in support. Several entities write in support of this bill. The National Marine Manufacturers Association (NMMA) writes that “The discovery of golden mussel in California’s Sacramento–San Joaquin Delta was a turning point for our state’s water resources, natural ecosystems, and recreational boating communities. This destructive species can rapidly outcompete native mussels, clog water infrastructure, impair water quality, and ultimately lead to public agencies closing water access to boaters and non-motorized paddle craft. These closures have immediate consequences for local economies, outdoor recreation, and the hundreds of thousands of Californians whose livelihood relies on boating and fishing.” Further NMMA writes in support of the stakeholder process the author is employing to “build the best framework to address this growing threat.”
The California Tahoe Alliance (Alliance) supports the intent of this bill and notes that the introduction of invasive mussels, such as the golden mussel, could have devastating consequences on Lake Tahoe’s famed clarity, delicate ecosystem, and $5 billion annual recreation and tourism-based economy. They share that a 2009 estimate by the Army Corps of Engineers indicated that invasive mussels could lead to annual losses of $22 million ($33 million in 2025 dollars) in the Lake Tahoe Region, impacting tourism, property values, and maintenance costs. The Alliance also indicate that the Tahoe Regional Planning Agencies has implemented boat inspection procedures that prevented 72 boats with aquatic invasive species (including one boat with golden mussels) from entering Lake Tahoe in 2025 alone.
Several water agencies also write in support. Upper San Gabriel Municipal Water District summarizes their positions with “This commonsense legislation addresses the challenges facing recreational boating and water management communities in the prevention and decontamination of invasive mussels, while also identifying and implementing alternative and equitable funding sources.”
The Association of California Water Agencies (ACWA) writes with a Support if Amended position as they further engage with the development of this bill to further address public water agency challenges related to invasive golden mussels. They share that should a reciprocity framework be established in this bill, that framework would need to be deeply considered with robust requirements. Further, ACWA writes that the costs of performing routine inspections in one reservoir of the State Water Project alone are upwards of $12 million annually, so the cost of managing golden mussels may reach $300 - $500 million dollars.
- Related legislation. AB 1894 (Rubio) of the current legislative session prohibits a public agency from prohibiting imported water deliveries for groundwater replenishment due to invasive mussels unless there is substantial, documented evidence of a proven health and safety risk as a result of the invasive mussel. AB 1894 is pending in the Assembly Appropriations Committee.
AB 2032 (Ransom) of the current legislative session establishes exemptions for restricted species permits and scientific collection permits, for water operators with respect to golden mussels. Additionally, requires CDFW to develop guidance for invasive mussel control plans. Further, requires CDFA and the State and Regional Water Control Boards to quickly respond to the golden mussel threat, allow for the rapid use of identified tools and processes, and coordinate efforts between regional boards. AB 2032 is pending in the Assembly Appropriations Committee.
AB 2787 (Committee on Water, Parks, and Wildlife) of the current legislative session, among other things, provides that a person who operates a Nevada-registered vessel on the waters of Lake Tahoe or Topaz Lake shall not be cited for operation of a vessel without a valid state-issued invasive mussel sticker, provided that Nevada has a program in effect for the management of aquatic invasive species. AB 2787 is pending in the Assembly Appropriations Committee.
AB 149 (Committee on Budget), Chapter 106, Statutes of 2025, among other things, expanded statue and programs from “dreissenid mussels” to “invasive mussels,” establishes a requirement for CDFW to review and approve updated invasive mussel control plans, and increased the invasive mussel fee.
AB 1150 (Committee on Water, Parks, and Wildlife), Chapter 831, Statutes of 2023, among other things, distinguished that the issuance and collection of the quagga and zebra mussel infestation and prevention fee from the biennial registration renewal.
AB 2443 (Williams), Chapter 485, Statutes of 2012, establishes the quagga and zebra mussel infestation prevention program, which required payment of the invasive mussel fee on vessels and permitted the use of the funds for, among other things, a grant program.
AB 1929 (Hall), Chapter 152, Statutes of 2010, determines that a water operator is indemnified from the penalty of possessing and transporting a restricted species, if the water operator is in compliance with an approved control plan.
AB 2065 (Hancock), Chapter 667, Statutes of 2008, requires reservoir managers to undertake certain measures to prevent invasive mussel infestation in reservoirs in which invasives mussels have not been detected.
AB 1683 (Wolk), Chapter 419, Statutes of 2007, prohibits a person to possess, import, ship, or transport in the state, or place, plant, or cause to be placed or planted in any water within the state, dreissenid mussels, unless authorized by CDFW. Additionally, authorizes the Director of CDFW, or the Director’s designee, to conduct inspections of conveyances (e.g., vehicles and boats), order that the conveyance be drained, dried, or decontaminated, impound or quarantine conveyances, and conduct inspections of waters of the state and facilities that may contain invasive mussels. Further, requires water operators to implement measures to avoid dreissenid mussel infestation and develop a control plan upon infestation, among other things.
REGISTERED SUPPORT / OPPOSITION:
Support
California Tahoe Alliance
County of San Joaquin
National Marine Manufacturers Association
South San Joaquin Irrigation District
Upper San Gabriel Valley Municipal Water District
Support If Amended
Association of California Water Agencies
Opposition
None on file
Analysis Prepared by: Stephanie Mitchell / W., P., & W. / (916) 319-2096
Discussed in Hearing
Senate Standing Committee on Appropriations
Senate Standing Committee on Judiciary
Senate Standing Committee on Natural Resources and Water
Assembly Floor
Assembly Standing Committee on Water, Parks, and Wildlife
Bill Author
Bill Co-Author(s):