AB 2272: State contracting: subcontractors: prompt payment.
- Session Year: 2025-2026
- House: Assembly
- Latest Version Date: 2026-08-27
Current Status:
Passed
(2026-08-27: Chaptered by Secretary of State - Chapter 139, Statutes of 2026.)
Introduced
In Committee
Awaiting First Chamber Vote
Passed First Chamber
In Committee
Awaiting Second Chamber Vote
Passed Second Chamber
Enacted
Existing law, the California Prompt Payment Act, requires a state agency that acquires property or services pursuant to a contract with a business to make payment to the person or business on the date required by the contract and as specified, or be subject to a late payment penalty. Existing law requires state agencies to encourage claimants to promptly pay their subcontractors and suppliers, especially those that are small businesses.
This bill would authorize a subcontractor or supplier performing work under a state contract to request payment status information from the awarding state agency regarding invoices submitted by the prime contractor, and would require a prime contractor to provide confirmation to the awarding agency, upon the agencys request, regarding payments made to subcontractors.
Existing law, the California Prompt Payment Act, requires a state agency that acquires property or services pursuant to a contract with a business to make payment to the person or business on the date required by the contract and as specified, or be subject to a late payment penalty. Existing law requires state agencies to encourage claimants to promptly pay their subcontractors and suppliers, especially those that are small businesses.
This bill would authorize a subcontractor or supplier performing work under a state contract to request payment status information from the awarding state agency regarding invoices submitted by the prime contractor, and would require a prime contractor to provide confirmation to the awarding agency, upon the agencys request, regarding payments made to subcontractors.
Existing law, the California Prompt Payment Act, requires a state agency that acquires property or services pursuant to a contract with a business to make payment to the person or business on the date required by the contract and as specified, or be subject to a late payment penalty.
Existing penalty. Existing law requires state agencies to encourage claimants to promptly pay their subcontractors and suppliers, especially those that are small businesses.
This bill would recast those provisions to instead require prime contractors to pay, for payments by the state to prime contractors made on or after January 1, 2027, their subcontractors, suppliers, and other vendors within 45 days of receiving payment from the state. For payments made by the state to prime contractors made prior to January 1, 2027, but that have not been remitted to subcontractors, suppliers, and other vendors as of January 1, 2027, the bill would require prime contractors to remit payment by February 15, 2027.This bill would require the Department of General Services to monitor compliance with this requirement, as specified. The bill would impose a demerit system, in which noncompliant prime contractors lose eligibility for state contracts for a specified period of time, as described. For contracts entered into or renewed with the state on or after January 1, 2027, the bill would authorize the department to review and rescind a prime contractors existing contracts if the prime contractor repeatedly fails to comply. The bill would require the department to adopt rules and regulations to administer these provisions, and would make conforming changes.This bill would authorize a subcontractor or supplier performing work under a state contract to request payment status information from the awarding state agency regarding invoices submitted by the prime contractor, and would require a prime contractor to provide confirmation to the awarding agency, upon the agencys request, regarding payments made to subcontractors.
Existing law, the California Prompt Payment Act, requires a state agency that acquires property or services pursuant to a contract with a business to make payment to the person or business on the date required by the contract and as specified, or be subject to a late payment penalty.
Existing law requires state agencies to encourage claimants to promptly pay their subcontractors and suppliers, especially those that are small businesses.
This bill would recast those provisions to instead require prime contractors to pay, for payments by the state to prime contractors made on or after January 1, 2027, their subcontractors, suppliers, and other vendors within 45 days of receiving payment from the state. For payments made by the state to prime contractors made prior to January 1, 2027, but that have not been remitted to subcontractors, suppliers, and other vendors as of January 1, 2027, the bill would require prime contractors to remit payment by February 15, 2027.
This bill would require the Department of General Services to monitor compliance with this requirement, as specified. The bill would impose a demerit system, in which noncompliant prime contractors lose eligibility for state contracts for a specified period of time, as described. For contracts entered into or renewed with the state on or after January 1, 2027, the bill would authorize the department to review and rescind a prime contractors existing contracts if the prime contractor repeatedly fails to comply. The bill would require the department to adopt rules and regulations to administer these provisions, and would make conforming changes.
(a)State agencies shall encourage claimants to promptly pay their subcontractors and suppliers, especially those that are small businesses. In furtherance of this policy, state agencies shall utilize expedited payment processes to enable faster payment by prime contractors to their subcontractors and suppliers, and shall promptly respond to any subcontractor or supplier inquiries regarding the status of payments made to prime contractors.
(b)A subcontractor or supplier performing work under a state contract may request payment status information from the awarding state agency regarding invoices submitted by the prime contractor.
(c)A prime contractor shall provide confirmation to the awarding agency, upon the agencys request, regarding payments made to subcontractors.
(a)State agencies shall encourage claimants to promptly pay their subcontractors and suppliers, especially those that are small businesses. In furtherance of this policy, state agencies shall utilize expedited payment processes to enable faster payment by prime contractors to their subcontractors and suppliers, and shall promptly respond to any subcontractor or supplier inquiries regarding the status of payments made to prime contractors.
(b)A subcontractor or supplier performing work under a state contract may request payment status information from the awarding state agency regarding invoices submitted by the prime contractor.
(c)A prime contractor shall provide confirmation to the awarding agency, upon the agencys request, regarding payments made to subcontractors.
(a)State agencies shall encourage claimants to promptly pay their subcontractors and suppliers, especially those that are small businesses. In furtherance of this policy, state agencies shall utilize expedited payment processes to enable faster payment by prime contractors to their subcontractors and suppliers, and shall promptly respond to any subcontractor or supplier inquiries regarding the status of payments made to prime contractors.
(b)A subcontractor or supplier performing work under a state contract may request payment status information from the awarding state agency regarding invoices submitted by the prime contractor.
(c)A prime contractor shall provide confirmation to the awarding agency, upon the agencys request, regarding payments made to subcontractors.
SECTION 1.Section 927.10 of the Government Code is amended to read:927.10.(a)(1)For all payments made by the state to prime contractors on or after January 1, 2027, prime contractors shall pay their subcontractors, suppliers, and other vendors within 45 days of receiving payment from the state.(2)For payments made from the state to prime contractors prior to January 1, 2027, but that have not been remitted to subcontractors, suppliers, and other vendors as of January 1, 2027, prime contractors shall remit such payment by February 15, 2027.(b)State agencies shall utilize expedited payment processes to enable faster payment by prime contractors to their subcontractors, suppliers, and other vendors, and shall promptly respond to any subcontractor, supplier, or vendor inquiries regarding the status of payments made to prime contractors.(c)(1)The Department of General Services shall monitor compliance with subdivision (a).(2)Prime contractors that fail to comply with subdivision (a) shall receive a demerit, which shall negatively affect the claimants eligibility for all subsequent bids for contracts, other contract requests, and contract renewals with the state. At minimum, the following penalties shall apply:(A)Prime contractors that fail to comply with subdivision (a) for five payments within a three-year period shall be prohibited from renewing or entering into contracts with the state for six months.(B)Prime contractors that fail to comply with subdivision (a) for 10 payments within a three-year period shall be prohibited from renewing or entering into contracts with the state for one year.(3)For contracts entered into or renewed with the state on or after January 1, 2027, the Department of General Services may review and rescind a prime contractors existing contracts if the prime contractor repeatedly fails to comply with subdivision (a).(d)The Department of General Services shall adopt any rules and regulations to administer this section, including, but not limited to, a demerit tracking system and coordination with state agencies for penalty enforcement.State agencies shall encourage claimants to promptly (a)(1)For all payments made by the state to prime contractors on or after January 1, 2027, prime contractors shall pay their subcontractors and subcontractors, suppliers, especially those that are small businesses. In furtherance of this policy, state and other vendors within 45 days of receiving payment from the state.
(2)For payments made from the state to prime contractors prior to January 1, 2027, but that have not been remitted to subcontractors, suppliers, and other vendors as of January 1, 2027, prime contractors shall remit such payment by February 15, 2027.
(b)State agencies shall utilize expedited payment processes to enable faster payment by prime contractors to their subcontractors and subcontractors, suppliers, and other vendors, and shall promptly respond to any subcontractor or supplier subcontractor, supplier, or vendor inquiries regarding the status of payments made to prime contractors.
(c)(1)The Department of General Services shall monitor compliance with subdivision (a).
(2)Prime contractors that fail to comply with subdivision (a) shall receive a demerit, which shall negatively affect the claimants eligibility for all subsequent bids for contracts, other contract requests, and contract renewals with the state. At minimum, the following penalties shall apply:
(A)Prime contractors that fail to comply with subdivision (a) for five payments within a three-year period shall be prohibited from renewing or entering into contracts with the state for six months.
(B)Prime contractors that fail to comply with subdivision (a) for 10 payments within a three-year period shall be prohibited from renewing or entering into contracts with the state for one year.
(3)For contracts entered into or renewed with the state on or after January 1, 2027, the Department of General Services may review and rescind a prime contractors existing contracts if the prime contractor repeatedly fails to comply with subdivision (a).
(d)The Department of General Services shall adopt any rules and regulations to administer this section, including, but not limited to, a demerit tracking system and coordination with state agencies for penalty enforcement.
|
Date
|
Status
|
|---|---|
| Aug 27, 2026 | Chaptered by Secretary of State - Chapter 139, Statutes of 2026. |
| Aug 27, 2026 | Approved by the Governor. |
| Aug 18, 2026 | Enrolled and presented to the Governor at 3:30 p.m. |
| Aug 11, 2026 | In Assembly. Ordered to Engrossing and Enrolling. |
| Aug 10, 2026 | Read third time. Passed. Ordered to the Assembly. (Ayes 39. Noes 0. Page 5323.). |
| Aug 10, 2026 | Read third time. Passed. Ordered to the Assembly. (Ayes 39. Noes 0.). |
| Aug 4, 2026 | Read second time. Ordered to Consent Calendar. |
| Aug 3, 2026 | From committee: Be ordered to second reading file pursuant to Senate Rule 28.8 and ordered to Consent Calendar. |
| Jun 23, 2026 | From committee: Do pass and re-refer to Com. on APPR. with recommendation: To Consent Calendar. (Ayes 14. Noes 0.) (June 23). Re-referred to Com. on APPR. |
| May 27, 2026 | Referred to Com. on G.O. |
| May 14, 2026 | In Senate. Read first time. To Com. on RLS. for assignment. |
| May 14, 2026 | Read third time. Passed. Ordered to the Senate. (Ayes 77. Noes 0. Page 5055.) |
| May 14, 2026 | Read third time. Passed. Ordered to the Senate. (Ayes 77. Noes 0.) |
| May 7, 2026 | Read second time. Ordered to Consent Calendar. |
| May 6, 2026 | From committee: Do pass. To Consent Calendar. (Ayes 14. Noes 0.) (May 6). |
| Apr 23, 2026 | From committee: Do pass and re-refer to Com. on APPR. with recommendation: To Consent Calendar. (Ayes 21. Noes 0.) (April 22). Re-referred to Com. on APPR. |
| Apr 20, 2026 | Re-referred to Com. on G.O. |
| Apr 16, 2026 | From committee chair, with author's amendments: Amend, and re-refer to Com. on G.O. Read second time and amended. |
| Apr 8, 2026 | In committee: Set, first hearing. Hearing canceled at the request of author. |
| Mar 9, 2026 | Referred to Com. on G.O. |
| Feb 20, 2026 | From printer. May be heard in committee March 22. |
| Feb 19, 2026 | Read first time. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Aug 10, 2026 | Consent Calendar 2nd AB2272 Caloza | Senate Floor |
Passed |
|
| Jun 23, 2026 | Do pass, but first be re-referred to the Committee on [Appropriations] with the recommendation: To Consent Calendar | Senate Standing Committee on Governmental Organization |
Passed |
|
| May 14, 2026 | AB 2272 Caloza Consent Calendar Second Day Regular Session | Assembly Floor |
Passed |
|
| May 6, 2026 | Do pass. To Consent Calendar. | Assembly Standing Committee on Appropriations |
Passed |
|
| Apr 22, 2026 | Do pass and be re-referred to the Committee on [Appropriations] with recommendation: To Consent Calendar | Assembly Standing Committee on Governmental Organization |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| CAMEO Network | ** Support | |
| Construction Employers’ Association | ** Against | |
| Hispanas Organized for Political Equality | ** Support | |
| National Small Business Advocacy Council | ** Support | |
| Western Electrical Contractors Association | ** Support |
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-4171 | AB 2272 |
CONSENT
Bill No: AB 2272
Author: Caloza (D)
Amended: 4/16/26 in Assembly
Vote: 21
SENATE GOVERNMENTAL ORG. COMMITTEE: 14-0, 6/23/26
AYES: Rubio, Valladares, Archuleta, Ashby, Blakespear, Cervantes, Dahle, Hurtado, Ochoa Bogh, Padilla, Richardson, Smallwood-Cuevas, Wahab, Weber Pierson
NO VOTE RECORDED: Alvarado-Gil
SENATE APPROPRIATIONS COMMITTEE: Senate Rule 28.8
ASSEMBLY FLOOR: 77-0, 5/14/26 (Consent) - See last page for vote
SUBJECT: State contracting: subcontractors: prompt payment
SOURCE: Author
DIGEST:
This bill 1) authorizes a subcontractor or supplier performing work under a state contract to request payment status information from the awarding state agency regarding invoices submitted by the prime contractor; and 2) requires a prime contractor to provide confirmation to the awarding agency, upon the agency’s request, regarding payments made to subcontractors, as specified.
ANALYSIS:
Existing law:
- Requires, pursuant to the California Prompt Payment Act (CPPA), a state agency that acquires property or services pursuant to a contract with a business to make payment to the person or business on the date required by the contract and as specified, or be subject to a late payment.
- Requires state agencies to encourage claimants to promptly pay their subcontractors and suppliers, especially those that are small businesses, as specified.
This bill:
- Authorizes a subcontractor or supplier performing work under a state contract to request payment status information from the awarding state agency regarding invoices submitted by the prime contractor.
- Requires a prime contractor to provide confirmation to the awarding agency, upon the agency’s request, regarding payments made to subcontractors, as specified.
Background
Author Statement. According to the author’s office, “AB 2272 strengthens California’s Prompt Payment Act by improving accountability and transparency to help ensure that timely payments made by the state flow more reliably through prime contractors to the subcontractors and small businesses performing the work. When subcontractors are not paid on time, they are forced to cover payroll, materials, and operating costs out of pocket, often taking on debt or delaying growth, which can threaten their ability to stay in business and participate in future public projects. By promoting more consistent and transparent payment practices, this bill supports the stability of small businesses, protects jobs, and strengthens the overall integrity of the state’s contracting system.”
California’s Prompt Payment Act. Under the CPPA, state agencies that acquire property or services pursuant to a contract with a business are required to make payment on the date required by the contract, or within 45 days of the state agency's receipt of an undisputed invoice. If this requirement is not met, state agencies must automatically calculate and pay appropriate late payment penalties as specified in Government Code Section 927, et seq. Late payments may occur for a variety of reasons, including administrative decisions relating to cash flow, bond sales, or delays in meeting conditions set forth in federal legislation.
Existing law specifies that state agencies pay applicable penalties, without requiring the claimant to submit an additional invoice for these amounts, whenever the state agency fails to submit a correct claim to the Controller by the required payment approval date and payment is not issued within 45 calendar days from the state agency receipt of an undisputed invoice. Penalties paid by a state agency to a certified small business, nonprofit organization, nonprofit public benefit corporation, and a small business or nonprofit that provides services or equipment under Medi-Cal shall be calculated at a rate of 10% above the United State Prime Rate on June 30th of the prior year.
Additionally, the CPPA provides that if the Controller fails to make payment within 15 calendar days of receipt of the claim from a state agency, and payment is not issued within 45 calendar days from the state agency receipt of an undisputed invoice, the Controller shall pay applicable penalties to the claimant without requiring that the claimant submit an invoice for these amounts. If the claimant is a resource conservation district, a certified small business, a nonprofit organization, a nonprofit benefit corporation, or a small business or nonprofit organization that provides services or equipment under the Medi-Cal program, the Controller must pay a penalty at a rate of 10% above the United State Prime Rate on June 30 of the prior fiscal year, as specified.
However, existing law specifies that for the late payment penalty provisions of the PPA described above, a nonprofit organization is only eligible to receive a penalty payment if the contract or grant is an amount less than $500,000. Since 2013, DGS has overseen the CPPA to ensure that government agencies, in a timely manner, pay their contracts awarded to a certified small business or nonprofit. The CPPA indicates that nonprofits are only eligible to receive a penalty payment if the grant or contract awarded is an amount less than $500,000. Hence, the CPPA only applies to a limited set of grants, excluding numerous nonprofits that provide essential services to California communities.
Existing law requires state agencies to encourage claimants to promptly pay their subcontractors and suppliers, especially those that are small businesses. In furtherance of this state policy, state agencies are required to utilize expedited payment processes to enable faster payment by prime contractors to their subcontractors and suppliers, and to promptly respond to any subcontractor or supplier inquiry regarding the status of payments made to prime contractors.
This bill authorizes a subcontractor or supplier that is performing work under a state contract to request payment status information from the awarding state agency regarding invoices submitted by the prime contractor. Additionally, this bill requires a prime contractor to provide confirmation to the awarding agency, upon the agency’s request, regarding payments made to subcontractors.
Related/Prior Legislation
AB 880 (Bennett, 2025) would have revised the CPPA by requiring state agencies to reimburse a nonprofit grantee’s indirect costs at specified rates and remove the $500,000 cap that previously exempted certain Medi-Cal-related payments from penalty provisions. Additionally, this bill would have narrowed the circumstances under which the state can dispute an invoice and expands the definition of “grant” to include agreements with nonprofit organizations, as specified. (Never heard in the Senate Appropriations Committee)
SB 1246 (Limón, 2024) would have deleted, for the purposes of the CPPA, the definition of the term “grant” from the CPPA and deletes the $500,000 exception in existing law and provides that only specified late payment penalties apply to a signed final agreement for a grant, as specified, or a grant by any state agency to a nonprofit organization. (Vetoed by Governor Newsom)
AB 1223 (Caballero, Chapter 585, Statutes of 2017) required, within 10 days of making a construction contract payment, a state agency that maintains an Internet Web site to post on its Internet Web site the project for which the payment was made, the name of the construction contractor or company paid, the date the payment was made, the payment application number or other identifying information, and the amount paid.
SB 293 (Padilla, Chapter 700, Statutes of 2011) established a four-year limit on retention in public works projects, with specified exceptions, and modified provisions regarding payments to subcontractors and provisions regarding subcontractor claims for nonpayment.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: No
SUPPORT: (Verified 8/3/2026)
CAMEO Network
Hispanas Organized for Political Equality
National Small Business Advocacy Council
Western Electrical Contractors Association
OPPOSITION: (Verified 8/3/2026)
None received
ARGUMENTS IN SUPPORT: In support of the bill, CAMEO Network, writes in part, “[s]mall businesses are the backbone of California’s economy, and many play a critical role as subcontractors supporting prime contractors on state-funded projects. These businesses deliver essential goods and services, drive innovation, and create jobs in communities across the state. Yet far too often, they face delayed payments that strain their cash flow, limit their ability to grow, and in some cases, threaten their very survival.”
ASSEMBLY FLOOR: 77-0, 5/14/26
AYES: Addis, Aguiar-Curry, Ahrens, Alanis, Alvarez, Ávila Farías, Bains, Bauer-Kahan, Bennett, Berman, Boerner, Bonta, Bryan, Calderon, Caloza, Carrillo, Castillo, Chen, Connolly, Davies, DeMaio, Dixon, Elhawary, Ellis, Fong, Gabriel, Gallagher, Garcia, Gipson, Jeff Gonzalez, Mark González, Hadwick, Haney, Harabedian, Hart, Hoover, Irwin, Jackson, Johnson, Kalra, Krell, Lackey, Lee, Lowenthal, Macedo, McKinnor, Muratsuchi, Nguyen, Ortega, Pacheco, Papan, Patel, Patterson, Pellerin, Petrie-Norris, Quirk-Silva, Ramos, Ransom, Michelle Rodriguez, Rogers, Blanca Rubio, Sanchez, Schiavo, Schultz, Sharp-Collins, Solache, Soria, Stefani, Ta, Tangipa, Valencia, Wallis, Ward, Wicks, Wilson, Zbur, Rivas
NO VOTE RECORDED: Arambula, Flora, Celeste Rodriguez
Prepared by: Brian Duke / G.O. / (916) 651-1530
8/5/26 15:04:35
**** END ****
SENATE COMMITTEE ON GOVERNMENTAL ORGANIZATION
Senator Susan Rubio
Chair
2025 - 2026 Regular
Bill No: Hearing Date: 6/23/2026
Author: | |||
Version: | Amended | ||
Urgency: | Fiscal: | ||
Consultant: | |||
SUBJECT:
DIGEST: This bill authorizes a subcontractor or supplier performing work under a state contract to request payment status information from the awarding state agency regarding invoices submitted by the prime contractor. Additionally, this bill requires a prime contractor to provide confirmation to the awarding agency, upon the agency’s request, regarding payments made to subcontractors, as specified.
ANALYSIS:
Existing law:
- Requires, pursuant to the California Prompt Payment Act (CPPA), a state agency that acquires property or services pursuant to a contract with a business to make payment to the person or business on the date required by the contract and as specified, or be subject to a late payment.
- Requires state agencies to encourage claimants to promptly pay their subcontractors and suppliers, especially those that are small businesses, as specified.
This bill:
- Authorizes a subcontractor or supplier performing work under a state contract to request payment status information from the awarding state agency regarding invoices submitted by the prime contractor.
- Requires a prime contractor to provide confirmation to the awarding agency, upon the agency’s request, regarding payments made to subcontractors, as specified.
Background
Author Statement. According to the author’s office, “AB 2272 strengthens California’s Prompt Payment Act by improving accountability and transparency to help ensure that timely payments made by the state flow more reliably through prime contractors to the subcontractors and small businesses performing the work. When subcontractors are not paid on time, they are forced to cover payroll, materials, and operating costs out of pocket, often taking on debt or delaying growth, which can threaten their ability to stay in business and participate in future public projects. By promoting more consistent and transparent payment practices, this bill supports the stability of small businesses, protects jobs, and strengthens the overall integrity of the state’s contracting system.”
California’s Prompt Payment Act. Under the CPPA, state agencies that acquire property or services pursuant to a contract with a business are required to make payment on the date required by the contract, or within 45 days of the state agency's receipt of an undisputed invoice. If this requirement is not met, state agencies must automatically calculate and pay appropriate late payment penalties as specified in Government Code Section 927, et seq. Late payments may occur for a variety of reasons, including administrative decisions relating to cash flow, bond sales, or delays in meeting conditions set forth in federal legislation.
Existing law specifies that state agencies pay applicable penalties, without requiring the claimant to submit an additional invoice for these amounts, whenever the state agency fails to submit a correct claim to the Controller by the required payment approval date and payment is not issued within 45 calendar days from the state agency receipt of an undisputed invoice. Penalties paid by a state agency to a certified small business, nonprofit organization, nonprofit public benefit corporation, and a small business or nonprofit that provides services or equipment under Medi-Cal shall be calculated at a rate of 10% above the United State Prime Rate on June 30th of the prior year.
Additionally, the CPPA provides that if the Controller fails to make payment within 15 calendar days of receipt of the claim from a state agency, and payment is not issued within 45 calendar days from the state agency receipt of an undisputed invoice, the Controller shall pay applicable penalties to the claimant without requiring that the claimant submit an invoice for these amounts. If the claimant is a resource conservation district, a certified small business, a nonprofit organization, a nonprofit benefit corporation, or a small business or nonprofit organization that provides services or equipment under the Medi-Cal program, the Controller must pay a penalty at a rate of 10% above the United State Prime Rate on June 30 of the prior fiscal year, as specified.
However, existing law specifies that for the late payment penalty provisions of the PPA described above, a nonprofit organization is only eligible to receive a penalty payment if the contract or grant is an amount less than $500,000. Since 2013, DGS has overseen the CPPA to ensure that government agencies, in a timely manner, pay their contracts awarded to a certified small business or nonprofit. The CPPA indicates that nonprofits are only eligible to receive a penalty payment if the grant or contract awarded is an amount less than $500,000. Hence, the CPPA only applies to a limited set of grants, excluding numerous nonprofits that provide essential services to California communities.
Existing law requires state agencies to encourage claimants to promptly pay their subcontractors and suppliers, especially those that are small businesses. In furtherance of this state policy, state agencies are required to utilize expedited payment processes to enable faster payment by prime contractors to their subcontractors and suppliers, and to promptly respond to any subcontractor or supplier inquiry regarding the status of payments made to prime contractors.
This bill authorizes a subcontractor or supplier that is performing work under a state contract to request payment status information from the awarding state agency regarding invoices submitted by the prime contractor. Additionally, this bill requires a prime contractor to provide confirmation to the awarding agency, upon the agency’s request, regarding payments made to subcontractors.
Prior/Related Legislation
AB 880 (Bennett, 2025) would have revised the CPPA by requiring state agencies to reimburse a nonprofit grantee’s indirect costs at specified rates and remove the $500,000 cap that previously exempted certain Medi-Cal-related payments from penalty provisions. Additionally, this bill would have narrowed the circumstances under which the state can dispute an invoice and expands the definition of “grant” to include agreements with nonprofit organizations, as specified. (Never heard in the Senate Appropriations Committee)
SB 1246 (Limón, 2024) would have deleted, for the purposes of the CPPA, the definition of the term “grant” from the CPPA and deletes the $500,000 exception in existing law and provides that only specified late payment penalties apply to a signed final agreement for a grant, as specified, or a grant by any state agency to a nonprofit organization. (Vetoed by Governor Newsom)
AB 1223 (Caballero, Chapter 585, Statutes of 2017) Required, within 10 days of making a construction contract payment, a state agency that maintains an Internet Web site to post on its Internet Web site the project for which the payment was made, the name of the construction contractor or company paid, the date the payment was made, the payment application number or other identifying information, and the amount paid.
SB 293 (Padilla, Chapter 700, Statutes of 2011) established a four-year limit on retention in public works projects, with specified exceptions, and modified provisions regarding payments to subcontractors and provisions regarding subcontractor claims for nonpayment.
FISCAL EFFECT: Appropriation: Fiscal Com.: Local:
SUPPORT:
CAMEO Network
Hispanas Organized for Political Equality
National Small Business Advocacy Council
Western Electrical Contractors Association
OPPOSITION:
None received
ARGUMENTS IN SUPPORT: In support of the bill, CAMEO Network writes in part – that, “[s]mall businesses are the backbone of California’s economy, and many play a critical role as subcontractors supporting prime contractors on state-funded projects. These businesses deliver essential goods and services, drive innovation, and create jobs in communities across the state. Yet far too often, they face delayed payments that strain their cash flow, limit their ability to grow, and in some cases, threaten their very survival.
Date of Hearing: May 6, 2026
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Buffy Wicks, Chair
ABPCA Bill Id:AB 2272
Author:(Caloza) – As Amended Ver:April 16, 2026
Policy Committee: | Governmental Organization | Vote: | 21 - 0 |
|
| ||
|
|
Urgency: No State Mandated Local Program: No Reimbursable: No
SUMMARY:
This bill authorizes a subcontractor or supplier performing work under certain state contracts to request payment status information from the awarding state agency.
This bill also requires a prime contractor to provide confirmation of payments made to subcontractors to the awarding agency requesting such information.
FISCAL EFFECT:
Minor and absorbable costs to the Department of General Services (DGS) to provide and request payment information upon request to contracting entities. Similarly, likely minor and absorbable costs to other state agencies that award contracts subject to the Prompt Payment Act (PPA).
COMMENTS:
- Purpose. According to the author:
When subcontractors are not paid on time, they are forced to cover payroll, materials, and operating costs out of pocket, often taking on debt or delaying growth, which can threaten their ability to stay in business and participate in future public projects. By promoting more consistent and transparent payment practices, this bill supports the stability of small businesses, protects jobs, and strengthens the overall integrity of the state’s contracting system.
This bill is supported by small business organizations.
- PPA. The PPA requires a state agency that acquires property or services pursuant to a contract with a business to pay undisputed invoices within 45 days of receipt or be subject to a late payment penalty. The late payment penalty amount depends on the type of claimant.
Under the PPA, a state agency must also encourage a claimant to promptly pay its subcontractors and suppliers, especially those that are small businesses. In furtherance of this policy, the PPA requires a state agency to: (a) utilize expedited payment processes to enable faster payment by a prime contractor to its subcontractors and suppliers and (b) promptly respond to subcontractor or supplier inquiries regarding the status of the agency’s payment to the prime contractor. However, unlike the relationship between a state agency and a prime contractor, a prime contractor does not need to pay a subcontractor within a certain timeframe and is not liable for a late payment penalty to a subcontractor. To further encourage prompt payment to a subcontractor or supplier, this bill explicitly authorizes a subcontractor or supplier to request payment status information regarding the prime contractor’s invoices from the awarding state agency and requires a prime contractor to confirm to the awarding agency that the prime contractor has paid a subcontractor. However, this bill does not require the awarding agency to make such an inquiry.
- Recent Amendments. The introduced version of this bill would have imposed strict prompt payment timelines for a prime contractor and was opposed by various contractor associations. Recent amendments to this bill address opposition concerns, with the Construction Employers’ Association and potentially other groups removing opposition to this bill.
Analysis Prepared by: Irene Ho / APPR. / (916) 319-2081
Date of Hearing: April 22, 2026
ASSEMBLY COMMITTEE ON GOVERNMENTAL ORGANIZATION
Blanca Rubio, Chair
ABPCA Bill Id:AB 2272 (
Author:Caloza) – As Amended Ver:April 16, 2026
SUBJECT: State contracting: subcontractors: prompt payment.
SUMMARY: This bill would authorize a subcontractor or supplier performing work under a state contract to request payment status information from the awarding state agency regarding invoices submitted by the prime contractor, and would require a prime contractor to provide confirmation to the awarding agency, upon the agency’s request, regarding payments made to subcontractors. Specifically, this bill:
1) Provides a subcontractor or supplier performing work under a state contract may request payment status information from the awarding state agency regarding invoices submitted by the prime contractor.
2) Provides a prime contractor shall provide confirmation to the awarding agency, upon the agency’s request, regarding payments made to subcontractors.
EXISTING LAW:
1) Creates the Department of General Services (DGS) to provide centralized services including, but not limited to, planning, acquisition, construction, and maintenance of state buildings and property; purchasing; printing; architectural services; administrative hearings; government claims; and accounting services. Requires DGS to develop, institute, and enforce policy and procedures to assure effective operation of all functions performed by DGS and to conserve the rights and interests of the state. (Government Code § 14600)
2) Provides state agencies shall encourage claimants to promptly pay their subcontractors and suppliers, especially those that are small businesses. In furtherance of this policy, state agencies shall utilize expedited payment processes to enable faster payment by prime contractors to their subcontractors and suppliers, and shall promptly respond to any subcontractor or supplier inquiries regarding the status of payments made to prime contractors.
3) Requires, under the California Prompt Payment Act (CPPA), a state agency that awards a grant or that acquires property or services pursuant to a contract to make timely payments pursuant to the grant or contract. Provides if a state agency or the Controller fails to take certain timely actions and payment is not issued within 45 calendar days from the state agency receipt of an undisputed invoice, the CPPA requires the state agency or the Controller, as applicable, to pay certain penalties.
4) Requires a state agency to issue a payment request for an undisputed invoice to the State
Controller's Office (SCO) within 30 days of receipt. The Controller shall pay claimants within 15 calendar days of receipt of a correct claim from the state agency.
5) Requires, within 10 days of making a construction contract payment, a state agency that maintains an Internet Website to post on its Internet Website the project for which the payment was made, the name of the construction contractor or company paid, the date the payment was made or the date the state agency transmitted instructions to the Controller or other payer to make the payment, the payment application number or other identifying information, and the amount of the payment.
6) Provides the CPPA requires that departments report annually to the Director of DGS the number and amount of late payment interest penalty payments paid to suppliers each fiscal year. Agencies may also choose to report Performance Measurement Information. In accordance with the Act, penalty payment data is collected, compiled, and reported to the Director.
FISCAL EFFECT: This bill is keyed fiscal by Legislative Counsel.
COMMENTS:
Purpose of the bill. According to the author, “AB 2272 will improve accountability and transparency to help ensure that timely payments made by the state flow more reliably through prime contractors to the subcontractors and small businesses performing the work. When subcontractors are not paid on time, they are forced to cover payroll, materials, and operating costs out of pocket, often taking on debt or delaying growth, which can threaten their ability to stay in business and participate in future public projects. By promoting more consistent and transparent payment practices, this bill supports the stability of small businesses, protects jobs, and strengthens the overall integrity of the state’s contracting system.”
Background.
What problem does this bill solve? Under current law, state agencies are required to encourage claimants to promptly pay their subcontractors and suppliers, with particular attention to small businesses. To support this policy, state agencies must use expedited payment processes to facilitate faster payments from prime contractors to their subcontractors and suppliers, and must also respond quickly to any inquiries from subcontractors or suppliers regarding the status of payments made to prime contractors.
However, this framework means prime contractors are only “encouraged” to pay subcontractors promptly. As a result, even though state agencies must pay prime contractors according to strict guidelines and deadlines, prime contractors themselves are merely encouraged, not obligated, to promptly pay subcontractors and suppliers, even after receiving state funds. Subcontractors are not entitled to payment penalties or required to be paid within a certain time frame.
AB 2272 tackles a long‑standing issue in public contracting: prime contractors delaying payment to subcontractors even after receiving funds from the state. By ensuring that payments flow more promptly down the chain, this bill will provide added mechanisms for small businesses, which are often the most vulnerable to cash‑flow disruptions.
California Prompt Payment Act (Gov. Code §927 et seq.). The state of California regulates prompt payment on both private and public construction projects. Upon receipt of a progress payment request form the prime contractor, the public entity must release payment within 30 days. This deadline is extended to 39 days if the work was contracted by a state university. As for final/retainage payments, the public entity must release payment within 60 days after the completion of the project.
Prompt payment obligations do not stop with the prime contractor. Once a prime contractor has received any payment from the public entity, they must pay their subcontractors and suppliers within 7 days. But, if the payment is received from a public utility, then the deadline is extended to 21 days after the prime received payment. As for all other payments, they are due within 7 days of receipt, unless the contract terms say otherwise.
If there is a bona fide dispute over the amount due, no more than 150% of the amount in dispute. If not, and payment is late or wrongfully withheld, interest will accrue. The rate of interest depends on whether it’s a payment from the public entity to the prime, or payment other payments.
State departments shall pay penalties if a correct claim is not submitted to the Controller within 30 calendar days and payment is not issued within 45 calendar days. The Controller shall pay penalties if payment is not issued with 15 calendar days of receipt of a correct claim and payment is not issued within 45 calendar days.
What does DGS do? The DGS is a California state agency within the Government Operations Agency that acts as the business manager for the state government. It provides support services to state agencies, including procurement and purchasing, real estate management, environmentally friendly transportation, printing and web services, administrative hearings, legal services, building standards, and oversight of safety and accessibility for public school construction. DGS also helps manage funding for school construction and disability access programs.
The DGS Procurement Division establishes state purchasing policies and provides procurement services. Its responsibilities include delegating purchasing authority, certifying small and disabled veteran businesses to work with the state, supporting related business councils, and developing cost-effective purchasing methods to save taxpayer money.
DGS also publishes the State Contracting Manual (SCM), which provides guidelines and procedures for state contracting and payment processes used by California agencies.
In support. CAMEO Network writes, “Small businesses are the backbone of California’s economy, and many play a critical role as subcontractors supporting prime contractors on state-funded projects. Yet far too often, they face delayed payments that strain their cash flow, limit their ability to grow, and in some cases, threaten their very survival. AB 2272 addresses this fundamental challenge. By strengthening prompt payment protections and accountability within state contracting, this bill ensures that small business subcontractors are paid in a timely and reliable manner for the work they have already completed. When subcontractors are paid on time, projects move more efficiently, partnerships are more stable, and taxpayer-funded investments yield stronger outcomes.”
Related legislation. SB 1366 (S. Rubio) of 2026. This bill would require the Public Utilities Commission (PUC) and the Energy Commission, in administering or approving programs, to comply with the CPPA and to ensure that payment timelines, advance payment structures, and accountability measures required under the act are incorporated into program designs, implementation plans, and cost recovery authorizations. It also mandates minimum advance payments to nonprofits: At least 25% upfront for all nonprofits or 100% upfront for nonprofits that have been in good standing with the state for at least three years, unless an exception applies.
Prior legislation. SB 1246 (Limón) of 2024. This bill would have deleted, for the purposes of the CPPA, the definition of the term “grant” from the CPPA and deletes the $500,000 exception in existing law and provides that only specified late payment penalties apply to a signed final agreement for a grant, as specified, or a grant by any state agency to a nonprofit organization. (Vetoed by the Governor)
AB 1223 (Caballero), Chapter 585, Statutes of 2017. Required, within 10 days of making a construction contract payment, a state agency that maintains an Internet Web-site to post on its Internet Web site the project for which the payment was made, the name of the construction contractor or company paid, the date the payment was made, the payment application number or other identifying information, and the amount paid.
SB 293 (Padilla), Chapter 700, Statutes of 2011. Established a four-year limit on retention in public works project, with specified exceptions, and modified provisions regarding payments to subcontractors and provisions regarding subcontractor claims for nonpayment.
REGISTERED SUPPORT / OPPOSITION:
Support
CAMEO Network (California Association for Micro Enterprise Opportunity)
National Small Business Advocacy Council
Opposition
None on file
Analysis Prepared by: Eric Johnson / G.O. / (916) 319-2531
Bill Author
Bill Co-Author(s):