AB 783: Public contracts: construction materials: disaster relief.
- Session Year: 2025-2026
- House: Assembly
- Latest Version Date: 2025-05-01
Current Status:
Failed
(2026-02-02: From committee: Filed with the Chief Clerk pursuant to Joint Rule 56.)
Introduced
In Committee
Awaiting First Chamber Vote
Passed First Chamber
In Committee
Awaiting Second Chamber Vote
Passed Second Chamber
Enacted
Existing law authorizes the Department of General Services to enter into contracts on a bid or negotiated basis with manufacturers and suppliers of single source or multisource drugs, and to obtain from them discounts, rebates, or refunds as permissible under federal law.
This bill would, until January 1, 2031, authorize the department to negotiate and enter into contracts on a bid or negotiated basis for construction materials commonly used in residential structures that may include price discounts, rebates, refunds, or other strategies aimed at lowering the cost of these materials. The bill would require that these materials be offered at cost or with minimal administrative fees added to homeowners, contractors, nonprofit organizations, and local governments in any area affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster, as specified. The bill would require that the materials only be used for recovery efforts that are directly linked to housing losses caused by a state of emergency.
This bill would require the department to coordinate with local governments, housing agencies, and nonprofit organizations to establish sufficient distribution of the materials within areas affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster. prohibit its provisions from being interpreted to require the department to store or distribute materials. The bill would also require the department to report annually to specified committees of the Legislature on the implementation, cost savings, and effectiveness of these provisions.
Existing law authorizes the Department of General Services to enter into contracts on a bid or negotiated basis with manufacturers and suppliers of single source or multisource drugs, and to obtain from them discounts, rebates, or refunds as permissible under federal law.
This bill would would, until January 1, 2031, authorize the department to negotiate and enter into contracts on a bid or negotiated basis for construction materials commonly used in residential structures that may include price discounts, rebates, refunds, or other strategies aimed at lowering the cost of these materials. The bill would require that these materials be offered at cost or with minimal administrative fees added to homeowners, contractors, nonprofit organizations, and local governments in any area affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster, as specified. The bill would require that the materials only be used for recovery efforts that are directly linked to housing losses caused by a state of emergency.
This bill would require the department to coordinate with local governments, housing agencies, and nonprofit organizations to establish sufficient distribution of the materials within areas affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster. The bill would also require the department to report annually to the Legislature on the implementation, cost savings, and effectiveness of these provisions.
Existing law authorizes the Department of General Services to enter into contracts on a bid or negotiated basis with manufacturers and suppliers of single source or multisource drugs, and to obtain from them discounts, rebates, or refunds as permissible under federal law.
This bill would authorize the department to negotiate and enter into contracts on a bid or negotiated basis for construction materials commonly used in residential structures that may include price discounts, rebates, refunds, or other strategies aimed at lowering the cost of these materials. The bill would require that these materials be offered at cost or with minimal administrative fees added to homeowners, contractors, nonprofit organizations, and local governments in any area affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster, as specified. The bill would require that the materials only be used for recovery efforts that are directly linked to housing losses caused by a state of emergency.
This bill would require the department to coordinate with local governments, housing agencies, and nonprofit organizations to establish sufficient distribution of the materials within areas affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster. The bill would also require the department to report annually to the Legislature on the implementation, cost savings, and effectiveness of these provisions.
The purpose of this chapter is to authorize the Department of General Services to act as a bulk purchaser of essential construction materials to ensure timely and cost-effective rebuilding of housing lost as a result of natural disasters with the goal of reducing the cost of, and streamlining access to, these materials, and to expedite rebuilding efforts in communities affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster.
14983.1.As used in this chapter, department means the Department of General Services.
14983.2.(a)Notwithstanding any other provision, the department may negotiate and enter into exclusive or nonexclusive contracts on a bid or negotiated basis for construction materials commonly used in residential structures. Contracts entered into pursuant to this chapter may include price discounts, rebates, refunds, or other strategies aimed at lowering the cost of these materials. The materials may include, but are not limited to, all of the following:
(1)Structural materials, such as lumber, concrete, rebar, and steel beams.
(2)Insulation and weatherproofing materials, including, but not limited to, roofing supplies.
(3)Interior and flashing materials, such as drywall, paint, windows, doors, and fasteners.
(4)Mechanical and electrical systems, including, but not limited to, wiring and fixtures.
(b)The department shall, if possible, give priority to sustainable and locally sourced materials.
(c)Contracts under this chapter shall be exempt from Chapter 2 (commencing with Section 10290) of Part 2 of Division 2 of the Public Contract Code.
14983.3.(a)The materials procured by the department pursuant to this chapter shall be made available to homeowners, contractors, nonprofit organizations, and local governments in any area affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster declared by the President of the United States or the Governor, or upon the declaration of a local emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster by the executive officer of any county, city, or city and county for a period of five years following that proclamation or declaration.
(b)The materials shall only be used for recovery efforts that are directly linked to housing losses caused by a state of emergency.
(c)The materials shall be offered to homeowners, contractors, nonprofit organizations, and local governments at cost or with minimal administrative fees added in order to ensure affordability for disaster survivors.
14983.4.The department shall coordinate with local governments, housing agencies, and nonprofit organizations to establish sufficient distribution of the materials within areas affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster.14983.4.Nothing in this chapter shall be interpreted to require the department to store or distribute materials.
14983.5.(a)The department shall maintain transparency in procuring construction materials pursuant to this chapter and, notwithstanding Section 10231.5, report annually to the Legislature Assembly Committee on Emergency Management and the Senate Committee on Governmental Organization on the implementation, cost savings, and effectiveness of this chapter. The report shall include, but not be limited to, all both of the following:
(1)Quantities purchased.
(2)Distribution metrics. (3)(2)Rebuilding outcomes in areas affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster.
(b)A report to be submitted pursuant to subdivision (a) shall be submitted in compliance with Section 9795 of the Government Code.
14983.6.This chapter shall remain in effect only until January 1, 2031, and as of that date is repealed.
The purpose of this chapter is to authorize the Department of General Services to act as a bulk purchaser of essential construction materials to ensure timely and cost-effective rebuilding of housing lost as a result of natural disasters with the of goal of reducing the cost of, and streamlining access to, these materials, and to expedite rebuilding efforts in communities affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster.
14983.1.As used in this chapter, department means the Department of General Services.
14983.2.(a)Notwithstanding any other provision, the department may negotiate and enter into exclusive or nonexclusive contracts on a bid or negotiated basis for construction materials commonly used in residential structures. Contracts entered into pursuant to this chapter may include price discounts, rebates, refunds, or other strategies aimed at lowering the cost of these materials. The materials may include, but are not limited to, all of the following:
(1)Structural materials, such as lumber, concrete, rebar, and steel beams.
(2)Insulation and weatherproofing materials, including, but not limited to, roofing supplies.
(3)Interior and flashing materials, such as drywall, paint, windows, doors, and fasteners.
(4)Mechanical and electrical systems, including, but not limited to, wiring and fixtures.
(b)The department shall, if possible, give priority to sustainable and locally sourced materials.
(c)Contracts under this chapter shall be exempt from Chapter 2 (commencing with Section 10290) of Part 2 of Division 2 of the Public Contract Code.
14983.3.(a)The materials procured by the department pursuant to this chapter shall be made available to homeowners, contractors, nonprofit organizations, and local governments in any area affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster declared by the President of the United States or the Governor, or upon the declaration of a local emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster by the executive officer of any county, city, or city and county for a period of five years following that proclamation or declaration.
(b)The materials shall only be used for recovery efforts that are directly linked to housing losses caused by a state of emergency.
(c)The materials shall be offered to homeowners, contractors, nonprofit organizations, and local governments at cost or with minimal administrative fees added in order to ensure affordability for disaster survivors.
14983.4.The department shall coordinate with local governments, housing agencies, and nonprofit organizations to establish sufficient distribution of the materials within areas affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster.
14983.5.(a)The department shall maintain transparency in procuring construction materials pursuant to this chapter and, notwithstanding Section 10231.5, report annually to the Legislature on the implementation, cost savings, and effectiveness of this chapter. The report shall include, but not be limited to, all of the following:
(1)Quantities purchased.
(2)Distribution metrics.
(3)Rebuilding outcomes in areas affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster.
(b)A report to be submitted pursuant to subdivision (a) shall be submitted in compliance with Section 9795 of the Government Code.
14983.6.This chapter shall remain in effect only until January 1, 2031, and as of that date is repealed.
The purpose of this chapter is to authorize the Department of General Services to act as a bulk purchaser of essential construction materials to ensure timely and cost-effective rebuilding of housing lost as a result of natural disasters with the of goal reducing the cost of, and streamlining access to, these materials, and to expedite rebuilding efforts in communities affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster.
14983.1.As used in this chapter, department means the Department of General Services.
14983.2.(a)Notwithstanding any other provision, the department may negotiate and enter into exclusive or nonexclusive contracts on a bid or negotiated basis for construction materials commonly used in residential structures. Contracts entered into pursuant to this chapter may include price discounts, rebates, refunds, or other strategies aimed at lowering the cost of these materials. The materials may include, but are not limited to, all of the following:
(1)Structural materials, such as lumber, concrete, rebar, and steel beams.
(2)Insulation and weatherproofing materials, including, but not limited to, roofing supplies.
(3)Interior and flashing materials, such as drywall, paint, windows, doors, and fasteners.
(4)Mechanical and electrical systems, including, but not limited to, wiring and fixtures.
(b)The department shall, if possible, give priority to sustainable and locally sourced materials.
(c)Contracts under this chapter shall be exempt from Chapter 2 (commencing with Section 10290) of Part 2 of Division 2 of the Public Contract Code.
14983.3.(a)The materials procured by the department pursuant to this chapter shall be made available to homeowners, contractors, nonprofit organizations, and local governments in any area affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster declared by the President of the United States or the Governor, or upon the declaration of a local emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster by the executive officer of any county, city, or city and county for a period of five years following that proclamation or declaration.
(b)The materials shall only be used for recovery efforts that are directly linked to housing losses caused by a state of emergency.
(c)The materials shall be offered to homeowners, contractors, nonprofit organizations, and local governments at cost or with minimal administrative fees added in order to ensure affordability for disaster survivors.
14983.4.The department shall coordinate with local governments, housing agencies, and nonprofit organizations to establish sufficient distribution of the materials within areas affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster.
14983.5.(a)The department shall maintain transparency in procuring construction materials pursuant to this chapter and, notwithstanding Section 10231.5, report annually to the Legislature on the implementation, cost savings, and effectiveness of this chapter. The report shall include, but not be limited to, all of the following:
(1)Quantities purchased.
(2)Distribution metrics.
(3)Rebuilding outcomes in areas affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster.
(b)A report to be submitted pursuant to subdivision (a) shall be submitted in compliance with Section 9795 of the Government Code.
|
Date
|
Status
|
|---|---|
| Feb 2, 2026 | From committee: Filed with the Chief Clerk pursuant to Joint Rule 56. |
| Jan 31, 2026 | Died pursuant to Art. IV, Sec. 10(c) of the Constitution. |
| May 23, 2025 | In committee: Held under submission. |
| May 14, 2025 | In committee: Set, first hearing. Referred to APPR. suspense file. |
| May 5, 2025 | Re-referred to Com. on APPR. |
| May 1, 2025 | Read second time and amended. |
| Apr 30, 2025 | From committee: Amend, and do pass as amended and re-refer to Com. on APPR. (Ayes 5. Noes 1.) (April 28). |
| Apr 9, 2025 | Re-referred to Com. on E.M. |
| Apr 8, 2025 | Read second time and amended. |
| Apr 7, 2025 | From committee: Amend, and do pass as amended and re-refer to Com. on E.M. (Ayes 16. Noes 3.) (April 2). |
| Mar 10, 2025 | Referred to Coms. on G.O. and E.M. |
| Feb 19, 2025 | From printer. May be heard in committee March 21. |
| Feb 18, 2025 | Read first time. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Apr 28, 2025 | Amendments (Committee's) | Assembly Standing Committee on Emergency Management |
Passed |
|
| Apr 28, 2025 | Do pass as amended and be re-referred to the Committee on [Appropriations] | Assembly Standing Committee on Emergency Management |
Passed |
|
| Apr 2, 2025 | Do pass as amended and be re-referred to the Committee on [Emergency Management] | Assembly Standing Committee on Governmental Organization |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| Construction Employers' Association | ** Against | |
| LeadingAge California | ** Support |
Date of Hearing: May 14, 2025
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Buffy Wicks, Chair
ABPCA Bill Id:AB 783
Author:(Caloza) – As Amended Ver:May 1, 2025
Policy Committee: | Governmental Organization | Vote: | 16 - 3 |
Emergency Management | 5 - 1 | ||
|
|
Urgency: No State Mandated Local Program: No Reimbursable: No
SUMMARY:
This bill authorizes the Department of General Services (DGS) to negotiate and enter into contracts for construction materials commonly used in residential structures, and require such materials be offered at cost to certain entities in an area affected by certain states of emergency.
Specifically, this bill:
- Authorizes, until January 1, 2031, DGS to negotiate and enter into contracts on a bid or negotiated basis for construction materials commonly used in residential structures, which may include price discounts, rebates, refunds, or other strategies aimed at lowering the cost of materials. DGS must give priority to sustainable and locally sourced materials, if possible.
- Exempts the contracts from certain existing laws governing public procurement, such as competitive bidding.
- Requires the materials be offered at cost or with the addition of minimal administrative fees to homeowners, contractors, non-profit organizations, and local governments in any area affected by a state of emergency resulting from a natural disaster. The materials must be used only for recovery efforts directly linked to housing losses caused by the state of emergency.
- Requires DGS to annually report related performance metrics to the Legislature.
FISCAL EFFECT:
Annual costs of approximately $3.4 million to DGS for up to 20 positions to develop, implement, monitor, and facilitate this procurement program (General Fund or special fund). DGS notes that considerable time is needed to hire, train, and situate these new positions. DGS does not have the resources to begin implementation of this bill within its existing budget, so the best-case scenario is DGS beginning implementation activities by January 1, 2027, with full implementation not realized until the end of the year. Thus, DGS would have, at most, four years to complete the actual purchasing of materials before the program sunsets on January 1, 2031.
Additionally, DGS notes that this bill does not provide guidance regarding which entity would screen homeowners for eligibility to ensure that materials are used only for rebuilding efforts directly linked to housing losses caused by a state of emergency. DGS does not have sufficient data to make informed purchasing decisions on behalf of homeowners, contractors, non-profit organizations, or local governments. If DGS is responsible for resolving these issues, DGS may incur sizeable additional administrative costs, potentially in the millions of dollars.
COMMENTS:
- Purpose. According to the author:
California communities devastated by wildfires, earthquakes, floods and natural disasters often face significant financial barriers to rebuilding, including high construction costs and limited access to essential materials. AB 783 takes a proactive approach to disaster recovery by authorizing the DGS to negotiate discounted contracts for commonly used materials and make them available at cost or with minimal administrative fees. This bill will ensure a more efficient and cost-effective rebuilding process for those in our state recovering from disaster.
- Bulk Purchasing. DGS’s Procurement Division acts as a bulk purchaser for state and local government agencies, allowing local agencies to leverage the state’s buying power and make purchases directly from suppliers through the Procurement Division’s existing contracts and agreements, without further competitive bidding. Before utilizing a Leveraged Procurement Agreement, a local agency must review the contract user instructions to determine whether the contract is available for use by their agency and follow order procedures. DGS charges an administrative fee for use of these contracts. This bill similarly authorizes DGS to serve as a bulk purchaser of essential residential construction materials commonly and allows local governments to directly utilize the contracts, as well as homeowners, contractors, and non-profit organizations, if the entities are in an area affected by a state of emergency resulting from a natural disaster and the materials are used for related housing recovery.
- Support and Opposition. This bill is supported by housing groups and local government entities, with the Housing Action Coalition arguing, “There is no centralized system for bulk purchasing and distributing essential construction materials at affordable prices for post-disaster rebuilding efforts” and this this bill “provides a meaningful solution.”
This bill is opposed by the Construction Employers’ Association, which argues:
Public agencies, private developers, etc., do not purchase construction materials directly, the contractors they employ do the purchasing as per the specifications, and those costs are included in the bids. Your measure would have the state front the money for construction materials to be used by local agencies, non-profits and residential developers, though it’s unclear how those materials would be priced given that structural steel, concrete, windows, doors, etc., are all manufactured to specifications.
Analysis Prepared by: Irene Ho / APPR. / (916) 319-2081
Date of Hearing: April 28, 2025
ASSEMBLY COMMITTEE ON EMERGENCY MANAGEMENT
Rhodesia Ransom, Chair
ABPCA Bill Id:AB 783 (
Author:Caloza) – As Amended Ver:April 8, 2025
SUBJECT: Public contracts: construction materials: disaster relief
SUMMARY: Authorizes the Department of General Services (DGS) to serve as a bulk purchaser of essential construction materials to support and accelerate post-disaster housing recovery efforts, as specified. Specifically, this bill:
1) Authorizes the DGS to act as a bulk purchaser of essential construction materials to ensure timely and cost-effective rebuilding of housing lost as a result of natural disasters with the goal of reducing the cost of, and streamlining access to, these materials, and to expedite rebuilding efforts in communities affected by a state of emergency, as specified.
2) Provides, the DGS may negotiate and enter into exclusive or nonexclusive contracts on a bid or negotiated basis for construction materials commonly used in residential structures. Contracts entered into pursuant to this chapter may include price discounts, rebates, refunds, or other strategies aimed at lowering the cost of these materials. The materials may include, but are not limited to, all of the following:
- Structural materials, such as lumber, concrete, rebar, and steel beams.
- Insulation and weatherproofing materials, including, but not limited to, roofing supplies.
- Interior and flashing materials, such as drywall, paint, windows, doors, and fasteners.
- Mechanical and electrical systems, including, but not limited to, wiring and fixtures.
3) Provides the DGS shall, if possible, give priority to sustainable and locally sourced materials.
4) States that the materials procured by the DGS pursuant to this bill shall be made available to homeowners, contractors, nonprofit organizations, and local governments in any area affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster declared by the President of the United States or the Governor, or upon the declaration of a local emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster by the executive officer of any county, city, or city and county for a period of five years following that proclamation or declaration.
5) Provides the materials shall only be used for recovery efforts that are directly linked to housing losses caused by a state of emergency.
6) Provides the materials shall be offered to homeowners, contractors, nonprofit organizations, and local governments at cost or with minimal administrative fees added in order to ensure affordability for disaster survivors.
7) Provides the DGS shall coordinate with local governments, housing agencies, and nonprofit organizations to establish sufficient distribution of the materials within areas affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster.
8) Provides the DGS shall maintain transparency in procuring construction materials pursuant to this bill and report annually to the Legislature on the implementation, cost savings, and effectiveness of this chapter. The report shall include, but not be limited to, all of the following:
- Quantities purchased.
- Distribution metrics.
- Rebuilding outcomes in areas affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster.
9) Provides specified reporting requirements, as specified.
10) Repeals the above provisions on January 1, 2031
EXISTING LAW:
- Establishes the DGS in the Government Operations Agency for purposes of providing centralized services of state government, as provided. (Government Code Section 14600)
- Authorizes DGS to oversee and manage the acquisition of goods and services for state agencies, ensuring efficiency and cost-effectiveness in procurement processes. . (Government Code Section 14612)
- Specifies that for IT goods and services, an emergency exists when immediate acquisition is necessary for the protection of public health, welfare, or safety. (Public Contract Code (PCC) 12102)
- Authorizes, during an emergency, the immediate purchase of non-IT goods without bid when necessary for the protection of public health, welfare, or safety. (PCC 10302)
- Under the California Emergency Services Act, establishes the California Office of Emergency Services (Cal OES) within the office of the Governor for the purpose of mitigating the effects of natural, manmade, or war-caused emergencies. (Government Code Section 8550)
- Under the California Emergency Services Act, provides Cal OES to be responsible for the state’s emergency and disaster response services for natural, technological, or man-made disasters and emergencies, including responsibility for activities necessary to prevent, respond to, recover from, and mitigate the effects of emergencies and disasters to people and property. (Government Code Section 8585)
2) Under the California Disaster Assistance Act, requires the Director of Cal OES to provide financial assistance to local agencies for their personnel costs, equipment costs, and the cost of supplies and materials used during disaster response activities, incurred as a result of a state of emergency proclaimed by the Governor, subject to specified criteria. (Government Code Section 8680)
3) Provides the California Disaster Assistance Act continuously appropriates moneys in the Disaster Assistance Fund and its subsidiary account, the Earthquake Emergency Investigations Account, without regard to fiscal year. (Government Code Section 8690.25)
4) Under the Federal Robert T. Stafford Disaster Relief and Emergency Assistance Act, authorizes the Federal Emergency Management Agency (FEMA) to provide emergency assistance to states and local entities impacted by disasters. In any emergency, the President may, among other things, authorize public assistance programs aimed at providing essential emergency assistance, repairing and restoring damaged public facilities and removing debris. (Public Law 100707)
5) Under the Sandy Recovery Improvement Act of 2013, requires FEMA, in cooperation with State, local, and Tribal emergency management agencies, to review, update, and revise through rulemaking the factors that FEMA uses to determine whether to recommend provision of Individual Assistance (IA) during a major disaster. (Public Law 113-2, Section 1109).
6) Under Title I of the Housing and Community Development Act of 1974, authorizes the Community Development Block Grant - Disaster Recovery (CDBG-DR). (Subsequent Public Laws are the appropriation acts that provide funding for each disaster. In addition to any requirements cited in the appropriation acts, the CDBG regulations in 24 CFR 570 apply to CDBG-DR funds.)
FISCAL EFFECT: Unknown. A fiscal committee has not yet heard this bill.
COMMENTS:
Purpose of this bill: According to the author, “California communities devastated by wildfires, earthquakes, floods and natural disasters often face significant financial barriers to rebuilding, including high construction costs and limited access to essential materials. AB 783 takes a proactive approach to disaster recovery by authorizing the Department of General services to negotiate discounted contracts for commonly used materials and make them available at cost or with minimal administrative fees. This bill will ensure a more efficient and cost-effective rebuilding process for those in our state recovering from disaster.”
Equity Impact: According to the author’s staff, “AB 783 addresses barriers to disaster recovery by making essential construction materials more affordable and accessible for those impacted by declared disasters. Historically, low-income homeowners, marginalized communities, and smaller contractors face greater challenges in rebuilding due to financial constraints, supply shortages, and market-driven price spikes.”
2025 Los Angeles Fires: In January 2025, Los Angeles County experienced the second and third most destructive fires in California history: the Palisades Fire and Eaton Fire. AccuWeather estimates these fires' total damage and economic loss to be between $250 billion and $275 billion.
At its height, the fires placed an estimated 331,335 people on an evacuation advisory, with nearly 192,000 residents facing mandatory evacuation and roughly 140,000 subject to warnings. The blazes burned a combined 37,469 acres and leveled entire communities in the Pacific Palisades and Altadena neighborhoods of LA County.
The Eaton Fire became the second most destructive fire in California history after destroying 9,418 buildings, 1,074 structures damaged, and 17 confirmed civilian fatalities. The Palisades Fire is the third most destructive fire in state history, with 6,837 structures destroyed, 973 structures damaged, and 12 confirmed civilian fatalities.
As firefighters were battling the largest conflagrations, additional fires broke out in the Los Angeles area. Crews were able to stop the forward spread and contain the blazes. These fires included the Lidia, Archer, Woodley, Sunset, Kenneth, Hurst, and Auto fires, which burned close to 2,400 acres between them. Two weeks after the initial fires, the Hughes Fire began near Castaic Lake in northern Los Angeles County on January 22 and grew to over 10,000 acres. Firefighters fully contained the fire on January 30 after covering 10,425 acres.
Rebuilding Executive Orders: In response to the widespread destruction caused by the January 2025 Los Angeles-area wildfires, Governor Newsom issued two executive orders to expedite the rebuilding of critical infrastructure in Altadena, Malibu, and Pacific Palisades:
Executive Order N-4-25 (January 12, 2025): Suspended the California Environmental Quality Act (CEQA) and California Coastal Act (CCA) permitting requirements for the repair or replacement of electric, gas, water, sewer, and telecommunications infrastructure that was damaged or destroyed by the fires.
Executive Order N-24-25 (March 27, 2025): Expanded the suspensions authorized under N-4-25 to cover undergrounding, upgrading, or relocating electric and telecommunications infrastructure damaged by the fires; Related infrastructure projects in adjacent areas; and Additional utility infrastructure projects (e.g., gas, water, sewer) that can be completed concurrently at the same excavation site.
Department of General Services (DGS) Procurement Division: The DGS Procurement Division sets state procurement policies and provides purchasing services. It delegates purchasing authority; certifies small and/or disabled veteran businesses to do business with the state; sponsors the Small Business Council; participates in the Disabled Veterans Business Enterprise Council; and provides innovative purchasing methods that save taxpayers' dollars, integrating quality solutions to meet customers' needs.
The DGS Procurement Division has specific guidelines and procedures for emergency purchases during natural disasters. In such emergencies, departments are not required to conduct competitive solicitations. Emergency contracts can be entered into immediately but are still subject to applicable statutory approval and reporting requirements.
Disasters and Housing: Disasters compound existing housing market challenges. Constrained housing supply has led to increased housing cost burdens, especially among populations vulnerable to disaster. A myriad of recovery assistance programs and timelines, and restrictions on what disasters qualify for support coalesce with these steady state challenges to slow community housing recovery efforts.
The Federal Emergency Management Agency (FEMA) is responsible for interim housing recovery efforts, and the U.S. Department of Housing and Urban Development (HUD) is responsible for those long-term recovery efforts that may extend over several years. At the state level, housing development agencies are working to address housing challenges as a normal course of action.
Disaster Recovery: In late 2019, Cal OES finalized the California Disaster Recovery Framework (CDRF) and accompanying Recovery Support Function (RSF) Annexes for long-term recovery. Similar to the organization of the ESFs, the RSFs are led by a state coordinating agency, and in conjunction with the federal government, serve to coordinate recovery-specific resources and guidance to local and tribal communities impacted by disasters.
Federal guidance on recovery planning: Recent federal guidance from FEMA, recommend States and local jurisdictions prioritize three areas in disaster recovery planning: (1) disaster housing planning; (2) state disaster recovery coordinator; and (3) disaster financial management policies and procedures.
Disaster Housing Planning: FEMA recommends the establishment of a State-Led Disaster Housing Task Force (SLDHTF) based on lessons learned from recent disasters to develop a disaster housing plan as part of the SEP or as a standalone document and update this plan at least once every two years. FEMA suggests SLDHTFs lead and coordinate state, local, private sector, and community-based actions to assess housing impacts, identify appropriate post-disaster housing options, and establish processes for expediting post-disaster housing delivery.
SLDHTF plans should clearly identify the roles, responsibilities, composition, and mobilization procedures for the SLDHTF, and how the SLDHTF integrates into the incident command structure. To have a successful SLDHTF plan, FEMA encourages recipients to complete a state housing strategy template and establish a State Disaster Recovery Coordinator.
State Disaster Recovery Coordinator: FEMA provides a Pre-Disaster Recovery Planning Guide to help states prepare for recovery by developing pre-disaster recovery plans that follow a process to engage members of the whole community, develop recovery capabilities, and create an organizational framework for recovery efforts. It is strongly recommended that states establish a State Disaster Recovery Coordinator (SDRC), as an effective pre-disaster recovery plan and process is crucial to help recipients prepare for major disaster incidents, recover effectively, and enable state leadership to better organize and identify gaps in the state’s recovery capabilities.
Arguments in Support: LeadingAge California writes in support, “California has faced devastating natural disasters, including wildfires, earthquakes, and mudslides, resulting in the destruction of countless homes and displacing vulnerable residents — including older adults. In the wake of these tragedies, rapid and cost-effective rebuilding is crucial to restoring communities and ensuring displaced residents can return to safe, stable housing. However, high construction costs and material shortages remain significant barriers to recovery efforts, especially for low-income seniors and nonprofit housing providers.”
They continue, “AB 783 directly addresses these challenges by empowering the Department of General Services to negotiate contracts for commonly used construction materials, incorporating price discounts, rebates, and other cost-saving measures. The bill ensures these materials are made available to homeowners, contractors, nonprofit organizations, and local governments at cost or with minimal administrative fees — a vital step in reducing the financial burdens associated with post-disaster rebuilding.”
Arguments in Opposition: The Construction Employers' Association writes in opposition, “Public agencies, private developers, etc., do not purchase construction materials directly, the contractors they employ do the purchasing as per the specifications, and those costs are included in the bids. This measure would have the state front the money for construction materials to be used by local agencies, non-profits, and residential developers, though it is unclear how the materials would be priced given that structural steel, concrete, windows, doors etc., are all manufactured to specifications. Then there’s the matter of liability. Today, if construction materials fail or if the delivery is delayed, the relevant contractor or subcontractor is liable for defects or delay damages. If the state were the purchasing agent, the state would need to assume this liability.”
Double Referral: This bill passed the Assembly Committee on Governmental Organization with a 16-3-3 vote on April 2, 2025.
Committee Amendments:
14983. The purpose of this chapter is to authorize the Department of General Services to act as a bulk purchaser of essential construction materials to ensure timely and cost-effective rebuilding of housing lost as a result of natural disasters with the goal of reducing the cost of, and streamlining access to, these materials, and to expedite rebuilding efforts in communities affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster.
14983.3. (a) The materials procured by the department pursuant to this chapter shall be made available to homeowners, contractors, nonprofit organizations, and local governments in any area affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster declared by the President of the United States or the Governor, or upon the declaration of a local emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster by the executive officer of any county, city, or city and county for a period of five years following that proclamation or declaration.
14983.4. The department shall coordinate with local governments, housing agencies, and nonprofit organizations to establish sufficient distribution of the materials within areas affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster. Nothing in this chapter shall be interpreted to require the department to store or distribute materials.
14983.5. (a) The department shall maintain transparency in procuring construction materials pursuant to this chapter and, notwithstanding Section 10231.5, report annually to the Legislature Assembly Committee on Emergency Management and the Senate Committee on Governmental Organization on the implementation, cost savings, and effectiveness of this chapter. The report shall include, but not be limited to, all of the following:
(1) Quantities purchased.
(2) Distribution metrics.
(3) Rebuilding outcomes in areas affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster.
Related Legislation:
AB 239 (Harabedian) of this session. Establishes the State-Led County of Los Angeles Disaster Housing Task Force (Assembly Appropriations)
AB 1284 (Committee on Emergency Management) of this Session. Requires recovery frameworks to be developed for catastrophic planning scenarios in California. (Assembly Appropriations)
Previous legislation: AB 1567 (Committee on Emergency Management) of the 2021-2022 Session. Would have required Cal OES to develop a state recovery framework and assist local governments in the development of regional recovery frameworks for California’s catastrophic plans. Held in the Assembly Committee on Appropriations
REGISTERED SUPPORT / OPPOSITION:
Support
LeadingAge California
Opposition
Construction Employers' Association
Analysis Prepared by: Ryan Fleming / E.M. / (916) 319-3802
Date of Hearing: April 2, 2025
ASSEMBLY COMMITTEE ON GOVERNMENTAL ORGANIZATION
Blanca Rubio, Chair
ABPCA Bill Id:AB 783 (
Author:Caloza) – As Introduced Ver:February 18, 2025
SUBJECT: Public contracts: construction materials: disaster relief
SUMMARY: This bill would authorize the Department of General Services (DGS) to negotiate and enter into contracts on a bid or negotiated basis for construction materials commonly used in residential structures that may include price discounts, rebates, refunds, or other strategies aimed at lowering the cost of these materials. The bill would require that these materials be offered at cost or with minimal administrative fees added to homeowners, contractors, nonprofit organizations, and local governments in any area affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster, as specified. The bill would require that the materials only be used for recovery efforts that are directly linked to housing losses caused by a state of emergency.
Additionally, this bill would require the DGS to coordinate with local governments, housing agencies, and nonprofit organizations to establish sufficient distribution of the materials within areas affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster. Specifically, this bill:
1) Authorizes the DGS to act as a bulk purchaser of essential construction materials to ensure timely and cost-effective rebuilding of housing lost as a result of natural disasters with the of goal reducing the cost of, and streamlining access to, these materials, and to expedite rebuilding efforts in communities affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster.
2) Provides, the DGS may negotiate and enter into exclusive or nonexclusive contracts on a bid or negotiated basis for construction materials commonly used in residential structures. Contracts entered into pursuant to this chapter may include price discounts, rebates, refunds, or other strategies aimed at lowering the cost of these materials. The materials may include, but are not limited to, all of the following:
- Structural materials, such as lumber, concrete, rebar, and steel beams.
- Insulation and weatherproofing materials, including, but not limited to, roofing supplies.
- Interior and flashing materials, such as drywall, paint, windows, doors, and fasteners.
- Mechanical and electrical systems, including, but not limited to, wiring and fixtures.
3) Provides the DGS shall, if possible, give priority to sustainable and locally sourced materials.
4) States that the materials procured by the DGS pursuant to this bill shall be made available to homeowners, contractors, nonprofit organizations, and local governments in any area affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster declared by the President of the United States or the Governor, or upon the declaration of a local emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster by the executive officer of any county, city, or city and county for a period of five years following that proclamation or declaration.
5) Provides the materials shall only be used for recovery efforts that are directly linked to housing losses caused by a state of emergency.
6) Provides the materials shall be offered to homeowners, contractors, nonprofit organizations, and local governments at cost or with minimal administrative fees added in order to ensure affordability for disaster survivors.
7) Provides the DGS shall coordinate with local governments, housing agencies, and nonprofit organizations to establish sufficient distribution of the materials within areas affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster.
8) Provides the DGS shall maintain transparency in procuring construction materials pursuant to this bill and report annually to the Legislature on the implementation, cost savings, and effectiveness of this chapter. The report shall include, but not be limited to, all of the following:
- Quantities purchased.
- Distribution metrics.
- Rebuilding outcomes in areas affected by a state of emergency resulting from an earthquake, flood, fire, riot, storm, or other natural disaster.
9) Provides specified reporting requirements, as specified.
EXISTING LAW:
1) Establishes the DGS in the Government Operations Agency for purposes of providing centralized services of state government, as provided.
2) Provides that DGS serves the public by providing a variety of services to state agencies through procurement and acquisition solutions; real estate management and design; environmentally friendly transportation; professional printing, design and web services; administrative hearings; legal services; building standards; oversight of structural safety, fire/life safety and accessibility for the design and construction of K-12 public schools and community colleges; funding for school construction; and disability access.
3) Authorizes the DGS to enter into contracts on a bid or negotiated basis with manufacturers and suppliers of single source or multisource drugs, and to obtain from them discounts, rebates, or refunds as permissible under federal law.
FISCAL EFFECT: This bill is keyed fiscal by Legislative Counsel
COMMENTS:
Purpose of the bill. According to the author’s office, “California communities devastated by wildfires, earthquakes, floods and natural disasters often face significant financial barriers to rebuilding, including high construction costs and limited access to essential materials. AB 783 takes a proactive approach to disaster recovery by authorizing the DGS to negotiate discounted contracts for commonly used materials and make them available at cost or with minimal administrative fees. This bill will ensure a more efficient and cost-effective rebuilding process for those in our state recovering from disaster.”
What problem does this bill solve? California is prone to natural disasters such as wildfires, earthquakes, and mudslides, which often result in significant damage to housing and infrastructure. Swift rebuilding efforts are crucial for restoring affected communities and enabling residents to reclaim their lives and property. Recent wildfires in Los Angeles, coupled with severe flooding across the state, underscore the urgent need for a more affordable and efficient approach to reconstructing homes in disaster-stricken areas. The author states, “these challenges are further compounded by rising construction costs and recent U.S. tariffs on Canadian lumber and other imported materials, which are expected to significantly increase the costs of rebuilding in Los Angeles and other disaster impacted areas.”
Background.
The California Department of General Services Procurement Division (DGSPD) acts as a bulk purchaser for state and local governmental entities, offering innovative purchasing methods and access to state contracts to leverage buying power and save taxpayer dollars.
The DGSPD provides innovative purchasing methods to meet the needs of any California governmental entity (state, city, county, district, or other local governmental body or corporation including the California State Universities and University of California systems, K-12 schools and community colleges) empowered to expend public funds to utilize designated State contracts, per Public Contract Code Section 10298, et. seq. This law allows entities described above, to leverage the State's buying power and purchase directly from suppliers through existing contracts and agreements, without further competitive bidding. Before utilizing a contract, local agencies must review the contract user instructions to determine whether the contract is available for use by their agency and following the order procedures, as outlined within the document. The DGSPD charges suppliers an administrative fee for the use of its established contracts. All applicable fees are identified in the contract user instructions.
The DGSPD sets state procurement policies, provides purchasing services and training, and certifies small and/or disabled veteran businesses, including those related to wildfire response. The DGSPD has specific guidelines and procedures for emergency purchases, which may be relevant in the context of wildfires.
State and local agencies can search for Leveraged Procurement Agreements (LPAs) such as cooperative agreements, statewide commodity contracts, statewide food contracts, master agreements, software licensing program contracts, state price schedules, and California Multiple Award Schedules. LPAs allow departments to buy directly from suppliers through existing contracts and agreements. LPAs are available to California's state, county, city, special district, education, and other government entities.
AB 783 seeks to authorize the DGS to serve as a bulk purchaser of essential construction materials. The goal is to ensure the timely and cost-effective rebuilding of housing lost due to natural disasters. By reducing costs, streamlining access to these materials, and expediting rebuilding efforts, the bill aims to support communities affected by a state of emergency caused by earthquakes, floods, fires, riots, storms, or other natural disasters. This measure aims to expedite rebuilding and reduce costs for affected communities.
It should be noted that bulk purchasing is a common practice in the construction industry to reduce costs and streamline procurement. This approach is often adopted by contractors and developers to leverage economies of scale and ensure timely availability of materials.
Wildfires in California. California has experienced a significant surge in destructive wildfires, with many of the largest and most devastating incidents occurring within the last decade. This trend has culminated in an especially severe outbreak in recent years, marking some of the worst wildfires in the state's history. Notably, the January 2025 wildfires—often referred to as "firestorms" due to the hurricane-force winds that fueled their rapid spread—resulted in the destruction of over 16,000 structures. These fires caused widespread hardship for affected victims and surrounding communities.
According to an analysis by the Los Angeles Times, real estate losses from the two largest fires, the Palisades and Eaton fires, are projected to exceed $30 billion. Additionally, approximately 13,000 households were displaced as a result of these disasters.
Executive order in response to Los Angeles County wildfires. In January 2025, to help Los Angeles continue to recover and rebuild, Governor Gavin Newsom issued an executive order to support small business owners and workers impacted by Los Angeles-area wildfires. The executive order provided relief to help local businesses recover quickly by deferring ABC annual licensure fees for workers and businesses and waiving other requirements that may impose barriers to recovery.
The cost and struggle to rebuild. After a natural disaster, first responders and recovery teams are the first to arrive, assisting with cleanup and demolition efforts. Once this initial phase is complete, the focus shifts to rebuilding homes, businesses, and infrastructure. Construction workers play a crucial role in this recovery process, contributing significantly to the community's return to normalcy. However, widespread damage can strain resources, leading to shortages of both building materials and skilled labor.
Thousands of residents in Los Angeles County will need their homes and businesses rebuilt following the recent wildfires. Significant natural disasters often leave local construction markets in a difficult position. Increased demand for building materials, particularly lumber and cement, can drive up prices. Other essential items, such as drywall, concrete, and steel, also tend to become scarce after a natural disaster. The need to ship these materials to affected areas further raises costs and complicates the rebuilding process. While infrastructure and residential needs typically take priority, the same factors contributing to higher rebuilding costs—like supply and labor shortages—also lead to construction delays. Large-scale reconstruction efforts can lead to price inflation across construction markets, even in unaffected areas. Additionally, the high cost of living in affected cities may make hiring contractors a challenge.
Rebuilding after disasters often requires adhering to defined safety standards and building codes, which can add complexity and cost to projects.
Price increases in the construction industry often persist much longer than anticipated. For instance, following Hurricane Katrina, elevated costs lingered for several years. Rebuilding efforts can also become prolonged, with no clear resolution in sight. Meanwhile, affected residents face the dual burden of navigating insurance claims and rebuilding their lives amidst ongoing uncertainty.
Double-referred. In addition to this Committee, this bill is referred to the Assembly Committee on Emergency Management.
Policy consideration. It is the Committee’s general practice, when considering legislation to establish a new state government program, to request a sunset date. This allows for future review of the measure's intent and ensures the designated state entity is efficiently and effectively providing its intended services. Consequently, the Committee may consider proposing an amendment to this bill to include a 5-year sunset provision.
In support. LeadingAge California writes, “California has faced devastating natural disasters, including wildfires, earthquakes, and mudslides, resulting in the destruction of countless homes and displacing vulnerable residents — including older adults. In the wake of these tragedies, rapid and cost-effective rebuilding is crucial to restoring communities and ensuring displaced residents can return to safe, stable housing. However, high construction costs and material shortages remain significant barriers to recovery efforts, especially for low-income seniors and nonprofit housing providers. By creating a centralized system for bulk purchasing, this bill will streamline rebuilding efforts, lower costs, and expedite the recovery process for communities hardest hit by disasters.”
In opposition. The Construction Employers' Association writes, “Public agencies, private developers, etc., do not purchase construction materials directly, the contractors they employ do the purchasing as per the specifications, and those costs are included in the bids. This measure would have the state front the money for construction materials to be used by local agencies, non-profits, and residential developers, though it is unclear how the materials would be priced given that structural steel, concrete, windows, doors etc., are all manufactured to specifications. Then there’s the matter of liability. Today, if construction materials fail or if the delivery is delayed, the relevant contractor or subcontractor is liable for defects or delay damages. If the state were the purchasing agent, the state would need to assume this liability.”
REGISTERED SUPPORT / OPPOSITION:
Support
LeadingAge California
Opposition
Construction Employers' Association
Analysis Prepared by: Eric Johnson / G.O. / (916) 319-2531