SB 440: Private Works Change Order Fair Payment Act.
- Session Year: 2025-2026
- House: Senate
- Latest Version Date: 2025-10-10
Current Status:
Passed
(2025-10-10: Chaptered by Secretary of State. Chapter 583, Statutes of 2025.)
Introduced
In Committee
Awaiting First Chamber Vote
Passed First Chamber
In Committee
Awaiting Second Chamber Vote
Passed Second Chamber
Enacted
Existing law contains various provisions relating to contracts for the performance of private works of improvement, including provisions applicable to a retention withholding by an owner from a direct contractor or by a direct contractor from a subcontractor.
This bill would establish, until January 1, 2030, for contracts entered into on or after January 1, 2026, a claim resolution process, as specified, applicable to any claim by a contractor or subcontractor, as described, in connection to a work of improvement or site improvement, except as specified. The bill would define a claim for these purposes as a separate demand by the contractor or subcontractor, as described, sent by registered mail or certified mail with return receipt requested, for, among other things, a time extension for relief from damages or penalties for delay assessed by an owner under contract for a work of improvement or site of improvement. The bill would make related findings and declarations.
Existing law contains various provisions relating to contracts for the performance of private works of improvement, including provisions applicable to a retention withholding by an owner from a direct contractor or by a direct contractor from a subcontractor.
This bill would establish, until January 1, 2030, for contracts entered into on or after January 1, 2026, a claim resolution process, as specified, applicable to any claim by a contractor or subcontractor, as described, in connection to a work of improvement or site improvement, except as specified. The bill would define a claim for these purposes as a separate demand by the contractor or subcontractor, as described, sent by registered mail or certified mail with return receipt requested, for, among other things, a time extension for relief from damages or penalties for delay assessed by an owner under contract for a work of improvement or site of improvement. The bill would make related findings and declarations.
Existing law contains various provisions relating to contracts for the performance of private works of improvement, including provisions applicable to a retention withholding by an owner from a direct contractor or by a direct contractor from a subcontractor.
This bill would establish, until January 1, 2030, for contracts entered into on or after January 1, 2026, a claim resolution process, as specified, applicable to any claim by a contractor or subcontractor, as described, in connection to a work of improvement or site improvement, except as specified. The bill would define a claim for these purposes as a timely and separate demand by the contractor or subcontractor, as described, sent by registered mail or certified mail with return receipt requested, for, among other things, a time extension for relief from damages or penalties for delay assessed by an owner under contract for a work of improvement or site of improvement. The bill would require a contractor or subcontractor bringing a claim under these provisions to bear the burden of proof, by a preponderance of the evidence, to demonstrate that any disputed claim was agreed upon by the owner or project manager, as specified. The bill would make related findings and declarations.
Existing law contains various provisions relating to contracts for the performance of private works of improvement, including provisions applicable to a retention withholding by an owner from a direct contractor or by a direct contractor from a subcontractor.
This bill would establish, until January 1, 2030, for contracts entered into on or after January 1, 2026, a claim resolution process, as specified, applicable to any claim by a contractor or subcontractor, as described, in connection to a public work of improvement or site improvement. improvement, except as specified. The bill would define a claim for these purposes as a timely and separate demand by the contractor or subcontractor, as described, sent by registered mail or certified mail with return receipt requested, for, among other things, a time extension for relief from damages or penalties for delay assessed by an owner of property under contract for a work of improvement or site of improvement. The bill would require a contractor or subcontractor bringing a claim under these provisions to bear the burden of proof, by a preponderance of the evidence, to demonstrate that any disputed claim was agreed upon by the owner or project manager, as specified. The bill would make related findings and declarations.
Existing law contains various provisions relating to contracts for the performance of private works of improvement, including provisions applicable to a retention withholding by an owner from a direct contractor or by a direct contractor from a subcontractor.
This bill would establish, until January 1, 2030, for contracts entered into on or after January 1, 2026, a claim resolution process, as specified, applicable to any claim by a contractor in connection to a public work of improvement or site improvement. The bill would define a claim for these purposes as a separate demand by the contractor sent by registered mail or certified mail with return receipt requested, for, among other things, a time extension for relief from damages or penalties for delay assessed by an owner of property under contract for a work of improvement or site of improvement. The bill would make related findings and declarations.
This act may be cited as the Private Works Change Order Fair Payment Act.
SEC. 2.Article 4 (commencing with Section 8850) is added to Chapter 8 of Title 2 of Part 6 of Division 4 of the Civil Code, to read:4.Claims and Disputes 8850.(a)The Legislature finds and declares all of the following:
(1)It is in the best interests of the state and its citizens to ensure that all construction business performed on a private works project in the state that is complete and not in dispute is paid in full and in a timely manner.
(2)Delays in payment for works of improvement and site improvements impose significant financial hardships on contractors, particularly small businesses, disadvantaged business enterprises, and disabled veteran business enterprises.
(3)The lack of clear procedures for resolving disputes related to change orders often leads to costly litigation where a predetermined method could avoid such costs.
(4)Prompt and fair payment promotes economic stability within the construction industry and ensures efficient project completion.
(b)Notwithstanding any other law, this section shall apply to any claim by a contractor, or where authorized pursuant to this article, a subcontractor, in connection to a work of improvement or site improvement.
(c)For purposes of this section, the following terms apply:
(1)Claim means a separate demand by a contractor, or where authorized pursuant to this article, a subcontractor, sent by registered mail or certified mail with return receipt requested, for one or more of the following:
(A)A time extension, including, without limitation, for relief from damages or penalties for delay assessed by an owner under contract for a work of improvement or site improvement.
(B)Payment by the owner of money or damages arising from work done by, or on behalf of, the contractor pursuant to the contract for a work of improvement or site improvement project and payment for which is not otherwise expressly provided or to which the claimant is not otherwise entitled.
(C)Payment of an amount that is disputed by the owner.
(2)(A)Owner means the owner who causes a building, improvement, or structure to be constructed, altered, or repaired, or that persons successor in interest at the date a notice of completion is recorded, whether the interest or estate of the owner be in fee, as vendee under a contract of purchase, as lessee, or other interest or estate less than the fee. Where the interest or estate is held by two or more persons as joint tenants or tenants in common, any one or more of the cotenants may be deemed to be the owner within the meaning of this section.
(B)Owner shall not include a state agency, department, office, division, bureau, board, or commission, the California State University, the University of California, a city, including a charter city, county, including a charter county, city and county, including a charter city and county, district, special district, public authority, political subdivision, public corporation, or nonprofit transit corporation wholly owned by a public agency and formed to carry out the purposes of the public agency.
(C)An owner shall have the right to a designated representative.
(3)(A)Project manager means a person, partnership, corporation, or other legal entity that is designated by the owner to direct construction and represent the owner during the performance of the services covered under the construction contract and is authorized to make changes, adjustments, and interpretations of the contract in order to facilitate the completion of the project.
(B)In the absence of the appointment of a project manager by the owner, the owner shall serve as project manager on a project.
(d)(1)(A)Upon receipt of a claim pursuant to this section, the owner to which the claim applies shall perform a reasonable review of the claim and, within a period not to exceed 30 days, shall provide the claimant a written statement identifying what portion of the claim is disputed and what portion of the claim is undisputed.
(B)The claimant shall furnish reasonable documentation to support the claim.
(2)Upon receipt of a claim, an owner and a contractor may, by mutual agreement, extend the time period provided in this subdivision in writing.
(3)Payment of any undisputed portion of the claim shall be processed and made within 60 days after the owner issues its written statement.
(e)(1)If the claimant disputes all or any portion of the owners written response to the claim, or if the owner fails to respond to a claim issued within the timeframe prescribed, the claimant may demand in writing an informal conference to meet and confer for settlement of the issues in dispute.
(2)Upon receipt of a demand in writing sent by registered mail or certified mail, return receipt requested, the owner shall schedule a meet and confer conference with the claimant within 30 days for settlement of the dispute.
(3)Within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the owner shall provide the claimant a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed.
(4)Payment of any undisputed portion of the claim shall be processed and made within 60 days after the owner issues its written statement.
(f)(1)If, following the informal conference, there remains any disputed portion of the claim, the remaining disputed portion of the claim shall be submitted to nonbinding mediation, with the owner and the claimant sharing the associated costs equally.
(2)The owner and claimant shall mutually agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing.
(3)(A)If the parties cannot agree upon a mediator within the time allotted, the contractor may select the mediator to be used.
(B)If the owner refuses mediation, the contractor may carry out the process described in subdivision (k).
(4)If mediation is unsuccessful, the parts of the claim remaining in dispute shall be subject to the dispute resolution procedures elected in the written contract of the parties, or, if no such election exists, by final judgment or by operation of law.
(g)(1)Failure by the owner to respond to a claim within the time periods described in this section or to otherwise meet the requirements of this section shall result in the claim being deemed denied in its entirety.
(2)A claim that is denied by reason of the owners failure to have responded to a claim, or its failure to otherwise meet the time requirements of the section, shall not constitute an adverse finding with regard to the merits of the claim or the responsibility or qualifications of the claim.
(h)(1)Undisputed amounts not paid in a timely manner as required by this section shall bear interest at 2 percent per month.
(2)Disputed amounts which are later found to be owed through the dispute resolution procedures elected in the written contract of the parties, or, if no such election exists, by final judgment or by operation of law, shall bear interest at 2 percent per month, beginning from the date on which those amounts would have been due had they not been disputed.
(i)Nothing in this section shall prevent either party from submitting, or otherwise limit the applicability of, a statutory offer of settlement under Section 998 of the Code of Civil Procedure.
(j)(1)If a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against an owner because privity of contract does not exist, except as provided in paragraph (4), the contractor shall present to the owner a claim on behalf of a subcontractor or lower tier subcontractor.
(2)A subcontractor may request in writing, either on their own behalf or on behalf of a lower tier subcontractor, that the contractor present a claim for work that was performed by the subcontractor or by a lower tier subcontractor on behalf of the subcontractor.
(3)(A)The subcontractor requesting that the claim be presented to the owner shall furnish the contractor with timely and reasonable documentation to support the subcontractors claim to enable the contractor to meet their obligations under subdivision (d) and shall thereafter cooperate with the contractor in the informal conference, mediation, and dispute resolution processes required pursuant to this section relating to the subcontractors claim.
(B)The contractor shall exercise good faith in fulfilling their obligations on behalf of the subcontractor under subdivisions (d), (e), and (f) and shall make no settlement of any claim to which the subcontractor does not approve, in writing.
(4)Within 30 days of receipt of this written request, the contractor shall notify the subcontractor in writing as to whether the contractor presented the claim to the owner and, if the contractor did not present the claim, provide the subcontractor with a statement of the reasons for not doing so.
(5)Nothing in this subdivision precludes a subcontractor from exercising its lien rights and its stop work notice rights.
(k)The contractor and subcontractors shall have the right to suspend performance of their work, without penalty, until payment is received if the following procedure is followed:
(1)The owner is informed by registered mail or certified mail, return receipt requested, that payment is due pursuant to this section, or where the claim is deemed denied pursuant to subdivision (g).
(2)Thirty days after the notice that payment was due pursuant to paragraph (1) is sent to the owner, the contractor or subcontractor sends a 10-day written notice of intent to stop work to the owner by registered mail or certified mail, return receipt requested.
(l)Any disputed amount which the owner, at any point, agrees to pay, or is found to owe through dispute resolution, by final judgment, or by operation of law, shall, from the date of the agreement or finding, be considered an undisputed amount for the purpose of any timelines or processes established under this article.
(m)(1)A waiver of the rights granted by this section is void and contrary to public policy.
(2)Notwithstanding paragraph (1), all of the following apply:
(A)Upon receipt of a claim, the parties may mutually agree to waive, in writing, the informal conference and mediation provisions in this section and proceed directly to the commencement of a civil action or binding arbitration, as applicable.
(B)Owners, contractors, and subcontractors may agree to reasonable change order, claim, and dispute resolution procedures and requirements in addition to the provisions of this section, so long as the contractual provisions do not conflict with or otherwise impair the timeframes and procedures set forth in this section.
(n)This section shall apply to contracts entered into on or after January 1, 2026.
(o)This section shall not apply to the construction of a residential project if the project is not mixed use and does not exceed four stories.
8851.This article shall remain in effect only until January 1, 2030, and as of that date is repealed.
This act may be cited as the Private Works Change Order Fair Payment Act.
SEC. 2.Article 4 (commencing with Section 8850) is added to Chapter 8 of Title 2 of Part 6 of Division 4 of the Civil Code, to read:4.Claims and Disputes 8850.(a)The Legislature finds and declares all of the following:
(1)It is in the best interests of the state and its citizens to ensure that all construction business performed on a private works project in the state that is complete and not in dispute is paid in full and in a timely manner.
(2)Delays in payment for works of improvement and site improvements impose significant financial hardships on contractors, particularly small businesses, disadvantaged business enterprises, and disabled veteran business enterprises.
(3)The lack of clear procedures for resolving disputes related to change orders often leads to costly litigation where a predetermined method could avoid such costs.
(4)Prompt and fair payment promotes economic stability within the construction industry and ensures efficient project completion.
(b)Notwithstanding any other law, this section shall apply to any claim by a contractor, or where authorized pursuant to this article, a subcontractor, in connection to a work of improvement or site improvement.
(c)For purposes of this section, the following terms apply:
(1)Claim means a separate demand by a contractor, or where authorized pursuant to this article, a subcontractor, sent by registered mail or certified mail with return receipt requested, for one or more of the following:
(A)A time extension, including, without limitation, for relief from damages or penalties for delay assessed by an owner under contract for a work of improvement or site improvement.
(B)Payment by the owner of money or damages arising from work done by, or on behalf of, the contractor pursuant to the contract for a work of improvement or site improvement project and payment for which is not otherwise expressly provided or to which the claimant is not otherwise entitled.
(C)Payment of an amount that is disputed by the owner.
(2)(A)Owner means the owner who causes a building, improvement, or structure to be constructed, altered, or repaired, or that persons successor in interest at the date a notice of completion is recorded, whether the interest or estate of the owner be in fee, as vendee under a contract of purchase, as lessee, or other interest or estate less than the fee. Where the interest or estate is held by two or more persons as joint tenants or tenants in common, any one or more of the cotenants may be deemed to be the owner within the meaning of this section.
(B)Owner shall not include a state agency, department, office, division, bureau, board, or commission, the California State University, the University of California, a city, including a charter city, county, including a charter county, city and county, including a charter city and county, district, special district, public authority, political subdivision, public corporation, or nonprofit transit corporation wholly owned by a public agency and formed to carry out the purposes of the public agency.
(C)An owner shall have the right to a designated representative.
(3)(A)Project manager means a person, partnership, corporation, or other legal entity that is designated by the owner to direct construction and represent the owner during the performance of the services covered under the construction contract and is authorized to make changes, adjustments, and interpretations of the contract in order to facilitate the completion of the project.
(B)In the absence of the appointment of a project manager by the owner, the owner shall serve as project manager on a project.
(d)(1)(A)Upon receipt of a claim pursuant to this section, the owner to which the claim applies shall perform a reasonable review of the claim and, within a period not to exceed 30 days, shall provide the claimant a written statement identifying what portion of the claim is disputed and what portion of the claim is undisputed.
(B)The claimant shall furnish reasonable documentation to support the claim.
(2)Upon receipt of a claim, an owner and a contractor may, by mutual agreement, extend the time period provided in this subdivision in writing.
(3)Payment of any undisputed portion of the claim shall be processed and made within 60 days after the owner issues its written statement.
(e)(1)If the claimant disputes all or any portion of the owners written response to the claim, or if the owner fails to respond to a claim issued within the timeframe prescribed, the claimant may demand in writing an informal conference to meet and confer for settlement of the issues in dispute.
(2)Upon receipt of a demand in writing sent by registered mail or certified mail, return receipt requested, the owner shall schedule a meet and confer conference with the claimant within 30 days for settlement of the dispute.
(3)Within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the owner shall provide the claimant a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed.
(4)Payment of any undisputed portion of the claim shall be processed and made within 60 days after the owner issues its written statement.
(f)(1)If, following the informal conference, there remains any disputed portion of the claim, the remaining disputed portion of the claim shall be submitted to nonbinding mediation, with the owner and the claimant sharing the associated costs equally.
(2)The owner and claimant shall mutually agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing.
(3)(A)If the parties cannot agree upon a mediator within the time allotted, the contractor may select the mediator to be used.
(B)If the owner refuses mediation, the contractor may carry out the process described in subdivision (k).
(4)If mediation is unsuccessful, the parts of the claim remaining in dispute shall be subject to the dispute resolution procedures elected in the written contract of the parties, or, if no such election exists, by final judgment or by operation of law.
(g)(1)Failure by the owner to respond to a claim within the time periods described in this section or to otherwise meet the requirements of this section shall result in the claim being deemed denied in its entirety.
(2)A claim that is denied by reason of the owners failure to have responded to a claim, or its failure to otherwise meet the time requirements of the section, shall not constitute an adverse finding with regard to the merits of the claim or the responsibility or qualifications of the claim.
(h)(1)Undisputed amounts not paid in a timely manner as required by this section shall bear interest at 2 percent per month.
(2)Disputed amounts which are later found to be owed through the dispute resolution procedures elected in the written contract of the parties, or, if no such election exists, by final judgment or by operation of law, shall bear interest at 2 percent per month, beginning from the date on which those amounts would have been due had they not been disputed.
(i)Nothing in this section shall prevent either party from submitting, or otherwise limit the applicability of, a statutory offer of settlement under Section 998 of the Code of Civil Procedure.
(j)(1)If a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against an owner because privity of contract does not exist, except as provided in paragraph (4), the contractor shall present to the owner a claim on behalf of a subcontractor or lower tier subcontractor.
(2)A subcontractor may request in writing, either on their own behalf or on behalf of a lower tier subcontractor, that the contractor present a claim for work that was performed by the subcontractor or by a lower tier subcontractor on behalf of the subcontractor.
(3)(A)The subcontractor requesting that the claim be presented to the owner shall furnish the contractor with timely and reasonable documentation to support the subcontractors claim to enable the contractor to meet their obligations under subdivision (d) and shall thereafter cooperate with the contractor in the informal conference, mediation, and dispute resolution processes required pursuant to this section relating to the subcontractors claim.
(B)The contractor shall exercise good faith in fulfilling their obligations on behalf of the subcontractor under subdivisions (d), (e), and (f) and shall make no settlement of any claim to which the subcontractor does not approve, in writing.
(4)Within 30 days of receipt of this written request, the contractor shall notify the subcontractor in writing as to whether the contractor presented the claim to the owner and, if the contractor did not present the claim, provide the subcontractor with a statement of the reasons for not doing so.
(5)Nothing in this subdivision precludes a subcontractor from exercising its lien rights and its stop work notice rights.
(k)The contractor and subcontractors shall have the right to suspend performance of their work, without penalty, until payment is received if the following procedure is followed:
(1)The owner is informed by registered mail or certified mail, return receipt requested, that payment is due pursuant to this section, or where the claim is deemed denied pursuant to subdivision (g).
(2)Thirty days after the notice that payment was due pursuant to paragraph (1) is sent to the owner, the contractor or subcontractor sends a 10-day written notice of intent to stop work to the owner by registered mail or certified mail, return receipt requested.
(l)Any disputed amount which the owner, at any point, agrees to pay, or is found to owe through dispute resolution, by final judgment, or by operation of law, shall, from the date of the agreement or finding, be considered an undisputed amount for the purpose of any timelines or processes established under this article.
(m)(1)A waiver of the rights granted by this section is void and contrary to public policy.
(2)Notwithstanding paragraph (1), all of the following apply:
(A)Upon receipt of a claim, the parties may mutually agree to waive, in writing, the informal conference and mediation provisions in this section and proceed directly to the commencement of a civil action or binding arbitration, as applicable.
(B)Owners, contractors, and subcontractors may agree to reasonable change order, claim, and dispute resolution procedures and requirements in addition to the provisions of this section, so long as the contractual provisions do not conflict with or otherwise impair the timeframes and procedures set forth in this section.
(n)This section shall apply to contracts entered into on or after January 1, 2026.
(o)This section shall not apply to the construction of a residential project if the project is not mixed use and does not exceed four stories.
8851.This article shall remain in effect only until January 1, 2030, and as of that date is repealed.
This act may be cited as the Private Works Construction Fair Payment and Dispute Resolution Change Order Fair Payment Act.
SEC. 2.Article 4 (commencing with Section 8850) is added to Chapter 8 of Title 2 of Part 6 of Division 4 of the Civil Code, to read:4.Claims and Disputes 8850.(a)The Legislature finds and declares all of the following:
(1)It is in the best interests of the state and its citizens to ensure that all construction business performed on a private works project in the state that is complete and not in dispute is paid in full and in a timely manner.
(2)Delays in payment of amounts due and owing for works of improvement and site improvements impose significant financial hardships on contractors, particularly small businesses, disadvantaged business enterprises, and disabled veteran business enterprises.
(3)The lack of clear procedures for resolving disputes related to change orders often leads to costly litigation where a predetermined method could avoid such costs.
(4)Prompt and fair payment promotes economic stability within the construction industry and ensures efficient project completion.
(b)Notwithstanding any other law, this section shall apply to any claim by a contractor, or where authorized pursuant to this article, a subcontractor, in connection to a work of improvement or site improvement.
(c)For purposes of this section, the following terms apply:
(1)Claim means a separate and timely demand by a contractor, or where authorized pursuant to this article, a subcontractor, sent by registered mail or certified mail with return receipt requested, for either one or more of the following:
(A)A time extension, including, without limitation, for relief from damages or penalties for delay assessed by an owner under contract for a work of improvement or site improvement.
(B)Payment of additional compensation by an owner for approved changes to the contractors scope of work in connection with a work of improvement or site improvement, whether disputed or undisputed. by the owner of money or damages arising from work done by, or on behalf of, the contractor pursuant to the contract for a work of improvement or site improvement project and payment for which is not otherwise expressly provided or to which the claimant is not otherwise entitled.
(C)Payment of an amount that is disputed by the owner.
(2)(A)Owner means the owner who causes a building, improvement, or structure to be constructed, altered, or repaired, or that persons successor in interest at the date a notice of completion is recorded, whether the interest or estate of the owner be in fee, as vendee under a contract of purchase, as lessee, or other interest or estate less than the fee. Where the interest or estate is held by two or more persons as joint tenants or tenants in common, any one or more of the cotenants may be deemed to be the owner within the meaning of this section.
(B)Owner shall not include a public entity, as defined in paragraph (3) of subdivision (c) of Section 9204 of the Public Contract Code. state agency, department, office, division, bureau, board, or commission, the California State University, the University of California, a city, including a charter city, county, including a charter county, city and county, including a charter city and county, district, special district, public authority, political subdivision, public corporation, or nonprofit transit corporation wholly owned by a public agency and formed to carry out the purposes of the public agency.
(C)An owner shall have the right to a designated representative.
(3)(A)Project manager means a person, partnership, corporation, or other legal entity that is designated by the owner to direct construction and represent the owner during the performance of the services covered under the construction contract and is authorized to make changes, adjustments, and interpretations of the contract in order to facilitate the completion of the project.
(B)In the absence of the appointment of a project manager by the owner, the owner shall serve as project manager on a project.
(4)Type V construction has the same meaning as that term is defined in Section 602.5 of Title 24 of the California Code or Regulations.(d)(1)(A)Upon receipt of a claim pursuant to this section, the owner to which the claim applies shall perform a reasonable review of the claim and, within a period not to exceed 30 days, shall provide the claimant a written statement identifying what portion of the claim is disputed and what portion of the claim is undisputed.
(2)(A)The claimant shall furnish all claims within 60 days of the basis for the claim being discovered and shall include, at a minimum, both of the following:(i)The reason for the claim.(ii)The method of calculating the time or additional compensation sought.(B)The owner, contractor, and subcontractor may agree to additional documentation which shall be included in support of a claim and to the use of standardized forms for the submission of claims.(B)The claimant shall furnish reasonable documentation to support the claim.
(3)(2)Upon receipt of a claim, an owner and a contractor may, by mutual agreement, extend the time periods period provided in paragraphs (1) and (2), this subdivision in writing.
(4)(3)Payment of any undisputed portion of the claim, less retention where authorized by contract, claim shall be processed and made within 60 days after the owner issues its written statement.
(e)(1)If the claimant disputes all or any portion of the owners written response to the claim, or if the owner fails to respond to a claim issued within the timeframe prescribed, the claimant may demand in writing an informal conference to meet and confer for settlement of the issues in dispute.
(2)Upon receipt of a demand in writing sent by registered mail or certified mail, return receipt requested, the owner shall schedule a meet and confer conference with the claimant within 30 days for settlement of the dispute.
(3)Within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the owner shall provide the claimant a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed.
(4)Payment of any undisputed portion of the claim, less retention where authorized by contract, claim shall be processed and made within 60 days after the owner issues its written statement.
(f)(1)If, following the informal conference, there remains any disputed portion of the claim, the remaining disputed portion of the claim shall be submitted to nonbinding mediation, with the owner and the claimant sharing the associated costs equally.
(2)The owner and claimant shall mutually agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing.
(3)(A)If the parties cannot agree upon a mediator within the time allotted, the contractor may select the mediator to be used.
(B)If the owner refuses mediation, the contractor may carry out the process described in subdivision (k).
(4)If mediation is unsuccessful, the parts of the claim remaining in dispute shall be subject to the dispute resolution procedures elected in the written contract of the parties, or, if no such election exists, by final judgment or by operation of law.
(g)(1)Failure by the owner to respond to a claim within the time periods described in this section or to otherwise meet the requirements of this section shall result in the claim being deemed denied in its entirety.
(2)A claim that is denied by reason of the owners failure to have responded to a claim, or its failure to otherwise meet the time requirements of the section, shall not constitute an adverse finding with regard to the merits of the claim or the responsibility or qualifications of the claim.
(h)(1)Undisputed amounts not paid in a timely manner as required by this section shall bear interest at 2 percent per month.
(2)Disputed amounts which are later found to be owed through the dispute resolution procedures elected in the written contract of the parties, or, if no such election exists, by final judgment or by operation of law, shall bear interest at 2 percent per month, beginning from the date on which those amounts would have been due had they not been disputed.
(i)Nothing in this section shall prevent either party from submitting, or otherwise limit the applicability of, a statutory offer of settlement under Section 998 of the Code of Civil Procedure.
(j)(1)If a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against an owner because privity of contract does not exist, except as provided in paragraph (4), the contractor shall present to the owner a claim on behalf of a subcontractor or lower tier subcontractor.
(2)A subcontractor may request in writing, either on their own behalf or on behalf of a lower tier subcontractor, that the contractor present a claim for work that was performed by the subcontractor or by a lower tier subcontractor on behalf of the subcontractor.
(3)(A)The subcontractor requesting that the claim be presented to the owner shall furnish the contractor with timely and reasonable documentation to support the subcontractors claim to enable the contractor to meet their obligations under subdivision (d) and shall thereafter cooperate with the contractor in the informal conference, mediation, and dispute resolution processes required pursuant to this section relating to the subcontractors claim.
(B)The contractor shall exercise good faith in fulfilling their obligations on behalf of the subcontractor under subdivisions (d), (e), and (f) and shall make no settlement of any claim to which the subcontractor does not approve, in writing.
(4)Within 30 days of receipt of this written request, the contractor shall notify the subcontractor in writing as to whether the contractor presented the claim to the owner and, if the contractor did not present the claim, provide the subcontractor with a statement of the reasons for not doing so.
(5)Nothing in this subdivision precludes a subcontractor from exercising its lien rights and its stop work notice rights.
(k)The contractor and subcontractor subcontractors shall have the right to suspend performance of their work, without penalty, if the owner fails to make payment of undisputed amounts due when and as required under this section, until the payment is received if the following procedure is followed:
(1)The owner is informed by registered mail or certified mail, return receipt requested, that an undisputed payment is past due pursuant to this section, or where the claim is deemed denied pursuant to subdivision (g).
(2)Thirty days after the notice of late payment that payment was due pursuant to paragraph (1) is sent to the owner, the contractor or subcontractor sends a 10-day written notice of intent to stop work to the owner by registered mail or certified mail, return receipt requested.
(l)Any disputed amount which the owner, at any point, agrees to pay, or is found to owe through dispute resolution, by final judgment, or by operation of law, shall, from the date of the agreement or finding, be considered an undisputed amount for the purpose of any timelines or processes established under this article.
(m)A contractor or subcontractor bringing a claim under this article shall bear the burden of proof, by a preponderance of the evidence, to demonstrate either of the following:(1)Any disputed claim was agreed upon by the owner, or an agent of an owner who was reasonably believed, by the contractor or subcontractor, to have the authority to amend the construction contract.(2)Any disputed claim was agreed upon by the project manager in the case of minor changes that are not inconsistent with the intent of the original construction contract. (n)(m)(1)A waiver of the rights granted by this section is void and contrary to public policy.
(2)Notwithstanding paragraph (1), all of the following apply:
(A)Upon receipt of a claim, the parties may mutually agree to waive, in writing, the informal conference and mediation provisions in this section and proceed directly to the commencement of a civil action or binding arbitration, as applicable.
(B)Owners, contractors, and subcontractors may agree to reasonable change order, claim, and dispute resolution procedures and requirements in addition to the provisions of this section, so long as the contractual provisions do not conflict with or otherwise impair the timeframes and procedures set forth in this section.
(o)(n)This section shall apply to contracts entered into on or after January 1, 2026.
(p)(o)This section shall not apply to the construction of residential or multifamily dwellings, nor Type V construction. a residential project if the project is not mixed use and does not exceed four stories.
8851.This article shall remain in effect only until January 1, 2030, and as of that date is repealed.
This act may be cited as the Private Works Construction Fair Payment and Dispute Resolution Act.
SEC. 2.Article 4 (commencing with Section 8850) is added to Chapter 8 of Title 2 of Part 6 of Division 4 of the Civil Code, to read:4.Claims and Disputes 8850.(a)The Legislature finds and declares all of the following:
(1)It is in the best interests of the state and its citizens to ensure that all construction business performed on a private works project in the state that is complete and not in dispute is paid in full and in a timely manner.
(2)Delays in payment of amounts due and owing for works of improvement and site improvements impose significant financial hardships on contractors, particularly small businesses, disadvantaged business enterprises, and disabled veteran business enterprises.
(3)The lack of clear procedures for resolving disputes related to change orders often leads to costly litigation where a predetermined method could avoid such costs.
(4)Prompt and fair payment promotes economic stability within the construction industry and ensures efficient project completion.
(b)Notwithstanding any other law, this section shall apply to any claim by a contractor contractor, or where authorized pursuant to this article, a subcontractor, in connection to a work of improvement or site improvement.
(c)For purposes of this section, the following terms apply:
(1)Claim means a separate and timely demand by a contractor contractor, or where authorized pursuant to this article, a subcontractor, sent by registered mail or certified mail with return receipt requested, for one or more either of the following:
(A)A time extension, including, without limitation, for relief from damages or penalties for delay assessed by an owner of property under contract for a work of improvement or site improvement.
(B)Payment by the owner of property of money or damages arising from work done by, or on behalf of, the contractor pursuant to the contract for a work of improvement or site improvement project and payment for which is not otherwise expressly provided or to which the claimant is not otherwise entitled. of additional compensation by an owner for approved changes to the contractors scope of work in connection with a work of improvement or site improvement, whether disputed or undisputed.
(C)Payment of an amount that is disputed by the owner of property.(2)(A)Owner means the owner who causes a building, improvement, or structure to be constructed, altered, or repaired, or that persons successor in interest at the date a notice of completion is recorded, whether the interest or estate of the owner be in fee, as vendee under a contract of purchase, as lessee, or other interest or estate less than the fee. Where the interest or estate is held by two or more persons as joint tenants or tenants in common, any one or more of the cotenants may be deemed to be the owner within the meaning of this section.
(B)Owner shall not include a public entity, as defined in paragraph (3) of subdivision (c) of Section 9204 of the Public Contract Code.
(C)An owner shall have the right to a designated representative.
(3)(A)Project manager means a person, partnership, corporation, or other legal entity that is designated by the owner to direct construction and represent the owner during the performance of the services covered under the construction contract and is authorized to make changes, adjustments, and interpretations of the contract in order to facilitate the completion of the project.
(B)In the absence of the appointment of a project manager by the owner, the owner shall serve as project manager on a project.
(4)Type V construction has the same meaning as that term is defined in Section 602.5 of Title 24 of the California Code or Regulations.
(d)(1)(A)Upon receipt of a claim pursuant to this section, the owner to which the claim applies shall conclude perform a reasonable review of the claim and, within a period not to exceed 30 days, shall provide the claimant a written statement identifying what portion of the claim is disputed and what portion of the claim is undisputed.
(B)(i)(2)(A)The claimant shall furnish reasonable documentation to support the claim. all claims within 60 days of the basis for the claim being discovered and shall include, at a minimum, both of the following:
(i)The reason for the claim.
(ii)The method of calculating the time or additional compensation sought.
(B)The owner, contractor, and subcontractor may agree to additional documentation which shall be included in support of a claim and to the use of standardized forms for the submission of claims.
(ii)(3)Upon receipt of a claim, an owner and a contractor may, by mutual agreement, extend the time period periods provided in this subdivision. paragraphs (1) and (2), in writing.
(C)Any payment due on an(4)Payment of any undisputed portion of the claim claim, less retention where authorized by contract, shall be processed and made within 60 days after the owner issues its written statement.
(2)(A)(i)(e)(1)If the claimant disputes all or any portion of the owners written response, response to the claim, or if the owner fails to respond to a claim issued pursuant to this section with within the timeframe prescribed, the claimant may demand in writing an informal conference to meet and confer for settlement of the issues in dispute.
(ii)(2)Upon receipt of a demand in writing sent by registered mail or certified mail, return receipt requested, the owner shall schedule a meet and confer conference with the claimant within 30 days for settlement of the dispute.
(B)(i)(3)Within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the owner shall provide the claimant a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed.
(ii)Any payment due on an(4)Payment of any undisputed portion of the claim claim, less retention where authorized by contract, shall be processed and made within 60 days after the owner issues its written statement.
(iii)(I)Any(f)(1)If, following the informal conference, there remains any disputed portion of the claim, as identified by the contractor in writing, the remaining disputed portion of the claim shall be submitted to nonbinding mediation, with the owner and the claimant sharing the associated costs equally.
(II)(2)The owner and claimant shall mutually agree to a mediator within 10 business days after the disputed operation portion of the claim has been identified in writing.
(III)(3)(A)If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the claim. mediator within the time allotted, the contractor may select the mediator to be used.
(B)If the owner refuses mediation, the contractor may carry out the process described in subdivision (k).
(IV)Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator. (V)(4)If mediation is unsuccessful, the parts of the claim remaining in dispute shall be subject to applicable procedures outside this section. the dispute resolution procedures elected in the written contract of the parties, or, if no such election exists, by final judgment or by operation of law.
(3)(A)(g)(1)Failure by the owner to respond to a claim from a contractor within the time periods described in this subdivision section or to otherwise meet the time requirements of this section shall result in the claim being deemed rejected denied in its entirety.
(B)(2)A claim that is denied by reason of the owners failure to have responded to a claim, or its failure to otherwise meet the time requirements of the section, shall not constitute an adverse finding with regard to the merits of the claim or the responsibility or qualifications of the claim.
(4)Amounts(h)(1)Undisputed amounts not paid in a timely manner as required by this section shall bear interest at 2 percent per month.
(5)A court or arbitrator shall award reasonable attorneys costs and fees, including expert witness fees, to a contractor if any of the following apply: (A)The court or arbitrator determines that an owner failed to comply with any of the timeframes established in this section. (B)The contractor makes an offer to settle any disputed portion of the claim that is not accepted and the owner fails to obtain a more favorable judgment or award.(2)Disputed amounts which are later found to be owed through the dispute resolution procedures elected in the written contract of the parties, or, if no such election exists, by final judgment or by operation of law, shall bear interest at 2 percent per month, beginning from the date on which those amounts would have been due had they not been disputed.
(i)Nothing in this section shall prevent either party from submitting, or otherwise limit the applicability of, a statutory offer of settlement under Section 998 of the Code of Civil Procedure.
(6)(A)(i)(j)(1)If a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against an owner because privity of contract does not exist, except as provided in paragraph (4), the contractor shall present to the owner a claim on behalf of a subcontractor or lower tier subcontractor.
(ii)(2)A subcontractor may request in writing, either on their own behalf or on behalf of a lower tier subcontractor, that the contractor present a claim for work that was performed by the subcontractor or by a lower tier subcontractor on behalf of the subcontractor.
(iii)(3)(A)The subcontractor requesting that the claim be presented to the owner shall furnish the contractor with timely and reasonable documentation to support the claim. subcontractors claim to enable the contractor to meet their obligations under subdivision (d) and shall thereafter cooperate with the contractor in the informal conference, mediation, and dispute resolution processes required pursuant to this section relating to the subcontractors claim.
(B)The contractor shall exercise good faith in fulfilling their obligations on behalf of the subcontractor under subdivisions (d), (e), and (f) and shall make no settlement of any claim to which the subcontractor does not approve, in writing.
(iv)(4)Within 30 days of receipt of this written request, the contractor shall notify the subcontractor in writing as to whether the contractor presented the claim to the owner and, if the original contractor did not present the claim, provide the subcontractor with a statement of the reasons for not doing so.
(B)(5)Nothing in this paragraph subdivision precludes a subcontractor from exercising its lien rights and its stop work notice rights.
(7)(k)The contractors contractor and the subcontractors subcontractor shall have the right to suspend performance, of any performance of their work, without penalty, if the owner fails to make payment of undisputed amounts due when and as required under this section, until the payment is received if the following procedure is followed:
(A)(1)The owner is informed by registered mail or certified mail, return receipt requested, that a an undisputed payment is past due pursuant to the terms of the construction contract was not received. this section, or where the claim is deemed denied pursuant to subdivision (g).
(B)(2)Thirty days after the notice of late payment is sent to the owner, the contractor or subcontractor sends a 10-day written notice of intent to stop work to the owner. owner by registered mail or certified mail, return receipt requested.
(e)The text of this section or a summary of it shall be set forth in the plans and specifications for any work of improvement or site improvement that may give rise to a claim under this section.(l)Any disputed amount which the owner, at any point, agrees to pay, or is found to owe through dispute resolution, by final judgment, or by operation of law, shall, from the date of the agreement or finding, be considered an undisputed amount for the purpose of any timelines or processes established under this article.
(m)A contractor or subcontractor bringing a claim under this article shall bear the burden of proof, by a preponderance of the evidence, to demonstrate either of the following:
(1)Any disputed claim was agreed upon by the owner, or an agent of an owner who was reasonably believed, by the contractor or subcontractor, to have the authority to amend the construction contract.
(2)Any disputed claim was agreed upon by the project manager in the case of minor changes that are not inconsistent with the intent of the original construction contract.
(f)(n)(1)A waiver of the rights granted by this section is void and contrary to public policy, provided, however, that (1) upon receipt policy.
(2)Notwithstanding paragraph (1), all of the following apply:
(A)Upon receipt of a claim, the parties may mutually agree to waive, in writing, the informal conference and mediation provisions in this section and proceed directly to the commencement of a civil action or binding arbitration, as applicable; and (2) an owner may prescribe reasonable applicable.
(B)Owners, contractors, and subcontractors may agree to reasonable change order, claim, and dispute resolution procedures and requirements in addition to the provisions of this section, so long as the contractual provisions do not conflict with or otherwise impair the timeframes and procedures set forth in this section.
(g)(o)This section shall apply to contracts entered into on or after January 1, 2026.
(p)This section shall not apply to the construction of residential or multifamily dwellings, nor Type V construction.
8851.This article shall remain in effect only until January 1, 2030, and as of that date is repealed.
This act may be cited as the Private Works Construction Fair Payment and Dispute Resolution Act.
SEC. 2.Article 4 (commencing with Section 8850) is added to Chapter 8 of Title 2 of Part 6 of Division 4 of the Civil Code, to read:4.Claims and Disputes 8850.(a)The Legislature finds and declares all of the following:
(1)It is in the best interests of the state and its citizens to ensure that all construction business performed on a private works project in the state that is complete and not in dispute is paid in full and in a timely manner.
(2)Delays in payment for works of improvement and site improvements impose significant financial hardships on contractors, particularly small businesses, disadvantaged business enterprises, and disabled veteran business enterprises.
(3)The lack of clear procedures for resolving disputes related to change orders often leads to costly litigation where a predetermined method could avoid such costs.
(4)Prompt and fair payment promotes economic stability within the construction industry and ensures efficient project completion.
(b)Notwithstanding any other law, this section shall apply to any claim by a contractor in connection to a work of improvement or site improvement.
(c)For purposes of this section, the following terms apply:
(1)Claim means a separate demand by a contractor sent by registered mail or certified mail with return receipt requested, for one or more of the following:
(A)A time extension, including, without limitation, for relief from damages or penalties for delay assessed by an owner of property under contract for a work of improvement or site improvement.
(B)Payment by the owner of property of money or damages arising from work done by, or on behalf of, the contractor pursuant to the contract for a work of improvement or site improvement project and payment for which is not otherwise expressly provided or to which the claimant is not otherwise entitled.
(C)Payment of an amount that is disputed by the owner of property.
(2)(A)Owner means the owner who causes a building, improvement, or structure to be constructed, altered, or repaired, or that persons successor in interest at the date a notice of completion is recorded, whether the interest or estate of the owner be in fee, as vendee under a contract of purchase, as lessee, or other interest or estate less than the fee. Where the interest or estate is held by two or more persons as joint tenants or tenants in common, any one or more of the cotenants may be deemed to be the owner within the meaning of this section.
(B)Owner shall not include a public entity, as defined in paragraph (3) of subdivision (c) of Section 9204 of the Public Contract Code.
(C)An owner shall have the right to a designated representative.
(d)(1)(A)Upon receipt of a claim pursuant to this section, the owner to which the claim applies shall conclude a reasonable review of the claim and, within a period not to exceed 30 days, shall provide the claimant a written statement identifying what portion of the claim is disputed and what portion of the claim is undisputed.
(B)(i)The claimant shall furnish reasonable documentation to support the claim.
(ii)Upon receipt of a claim, an owner and a contractor may, by mutual agreement, extend the time period provided in this subdivision.
(C)Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after the owner issues its written statement.
(2)(A)(i)If the claimant disputes the owners written response, or if the owner fails to respond to a claim issued pursuant to this section with the timeframe prescribed, the claimant may demand in writing an informal conference to meet and confer for settlement of the issues in dispute.
(ii)Upon receipt of a demand in writing sent by registered mail or certified mail, return receipt requested, the owner shall schedule a meet and confer conference within 30 days for settlement of the dispute.
(B)(i)Within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the owner shall provide the claimant a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed.
(ii)Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after the owner issues its written statement.
(iii)(I)Any disputed portion of the claim, as identified by the contractor in writing, shall be submitted to nonbinding mediation, with the owner and the claimant sharing the associated costs equally.
(II)The owner and claimant shall mutually agree to a mediator within 10 business days after the disputed operation of the claim has been identified in writing.
(III)If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the claim.
(IV)Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator.
(V)If mediation is unsuccessful, the parts of the claim remaining in dispute shall be subject to applicable procedures outside this section.
(3)(A)Failure by the owner to respond to a claim from a contractor within the time periods described in this subdivision or to otherwise meet the time requirements of this section shall result in the claim being deemed rejected in its entirety.
(B)A claim that is denied by reason of the owners failure to have responded to a claim, or its failure to otherwise meet the time requirements of the section, shall not constitute an adverse finding with regard to the merits of the claim or the responsibility or qualifications of the claim.
(4)Amounts not paid in a timely manner as required by this section shall bear interest at 2 percent per month.
(5)A court or arbitrator shall award reasonable attorneys costs and fees, including expert witness fees, to a contractor if any of the following apply:
(A)The court or arbitrator determines that an owner failed to comply with any of the timeframes established in this section.
(B)The contractor makes an offer to settle any disputed portion of the claim that is not accepted and the owner fails to obtain a more favorable judgment or award.
(6)(A)(i)If a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against an owner because privity of contract does not exist, the contractor shall present to the owner a claim on behalf of a subcontractor or lower tier subcontractor.
(ii)A subcontractor may request in writing, either on their own behalf or on behalf of a lower tier subcontractor, that the contractor present a claim for work that was performed by the subcontractor or by a lower tier subcontractor on behalf of the subcontractor.
(iii)The subcontractor requesting that the claim be presented to the owner shall furnish reasonable documentation to support the claim.
(iv)Within 30 days of receipt of this written request, the contractor shall notify the subcontractor in writing as to whether the contractor presented the claim to the owner and, if the original contractor did not present the claim, provide the subcontractor with a statement of the reasons for not doing so.
(B)Nothing in this paragraph precludes a subcontractor from exercising its lien rights and its stop work notice rights.
(7)The contractors and the subcontractors shall have the right to suspend performance, of any work, without penalty, until payment is received if the following procedure is followed:
(A)The owner is informed by registered mail or certified mail, return receipt requested, that a payment due pursuant to the terms of the construction contract was not received.
(B)Thirty days after the notice of late payment is sent to the owner, the contractor or subcontractor sends a 10-day written notice of intent to stop work to the owner.
(e)The text of this section or a summary of it shall be set forth in the plans and specifications for any work of improvement or site improvement that may give rise to a claim under this section.
(f)A waiver of the rights granted by this section is void and contrary to public policy, provided, however, that (1) upon receipt of a claim, the parties may mutually agree to waive, in writing, mediation and proceed directly to the commencement of a civil action or binding arbitration, as applicable; and (2) an owner may prescribe reasonable change order, claim, and dispute resolution procedures and requirements in addition to the provisions of this section, so long as the contractual provisions do not conflict with or otherwise impair the timeframes and procedures set forth in this section.
(g)This section shall apply to contracts entered into on or after January 1, 2026.
8851.This article shall remain in effect only until January 1, 2030, and as of that date is repealed.
|
Date
|
Status
|
|---|---|
| Oct 10, 2025 | Chaptered by Secretary of State. Chapter 583, Statutes of 2025. |
| Oct 10, 2025 | Approved by the Governor. |
| Sep 5, 2025 | Enrolled and presented to the Governor at 2 p.m. |
| Aug 29, 2025 | Assembly amendments concurred in. (Ayes 37. Noes 0. Page 2287.) Ordered to engrossing and enrolling. |
| Aug 27, 2025 | Ordered to special consent calendar. |
| Aug 21, 2025 | In Senate. Concurrence in Assembly amendments pending. |
| Aug 21, 2025 | Read third time. Passed. (Ayes 77. Noes 0. Page 2705.) Ordered to the Senate. |
| Jul 17, 2025 | Read second time. Ordered to consent calendar. |
| Jul 16, 2025 | From committee: Do pass. Ordered to consent calendar. (Ayes 12. Noes 0.) (July 15). |
| Jun 23, 2025 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on JUD. |
| Jun 10, 2025 | June 17 set for first hearing canceled at the request of author. |
| May 29, 2025 | Referred to Com. on JUD. |
| May 15, 2025 | In Assembly. Read first time. Held at Desk. |
| May 15, 2025 | Read third time. Passed. (Ayes 34. Noes 0. Page 1089.) Ordered to the Assembly. |
| May 8, 2025 | Read second time. Ordered to consent calendar. |
| May 7, 2025 | From committee: Do pass. Ordered to consent calendar. (Ayes 12. Noes 0. Page 1026.) (May 6). |
| Apr 28, 2025 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on JUD. |
| Apr 11, 2025 | Set for hearing May 6. |
| Feb 26, 2025 | Referred to Com. on JUD. |
| Feb 19, 2025 | From printer. May be acted upon on or after March 21. |
| Feb 18, 2025 | Introduced. Read first time. To Com. on RLS. for assignment. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Aug 29, 2025 | Special Consent SB440 Ochoa Bogh et al. | Senate Floor |
Passed |
|
| Aug 21, 2025 | SB 440 Ochoa Bogh Consent Calendar Second Day Regular Session | Assembly Floor |
Passed |
|
| Jul 15, 2025 | Do pass. To Consent Calendar. | Assembly Standing Committee on Judiciary |
Passed |
|
| May 15, 2025 | Consent Calendar 2nd SB440 Ochoa Bogh et al. | Senate Floor |
Passed |
|
| May 6, 2025 | Do pass and be ordered to the Consent Calendar | Senate Standing Committee on Judiciary |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| American Subcontractors Association-California | ** Support | |
| Association | ** Support | |
| California Association of Sheet Metal & Air Conditioning Contractors National | ** Support | |
| CALIFORNIA ASSOCIATION OF SHEET METAL & AIR CONDITIONING CONTRACTORS NATIONAL ASSOCIATION | ** Support | |
| California Legislative Conference Of Plumbing, Heating & Piping Industry | ** Support | |
| Finishing Contractors Association Of Southern California | ** Support | |
| International Union of Operating Engineers, Cal-Nevada Conference | ** Support | |
| National Electrical Contractors Association | ** Support | |
| Northern California Allied Trades | ** Support | |
| Northern California Floor Covering Association | ** Support | |
| Southern California Association of Scaffold Contractors | ** Support | |
| Southern California Association of Scaffold Contractors (source) | ** Support | |
| Southern California Contractors Association | ** Support | |
| Southern California Glass Management Association | ** Support | |
| United Contractors | ** Support | |
| Wall and Ceiling Alliance | ** Support | |
| Western Painting and Coating Contractors Association | ** Support | |
| Western Wall And Ceiling Contractors Association | ** Support |
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 440 |
UNFINISHED BUSINESS
Bill No: SB 440
Author: Ochoa Bogh (R), et al.
Amended: 6/23/25 in Assembly
Vote: 21
SENATE JUDICIARY COMMITTEE: 12-0, 5/6/25
AYES: Umberg, Niello, Allen, Arreguín, Ashby, Caballero, Durazo, Laird, Stern, Wahab, Weber Pierson, Wiener
NO VOTE RECORDED: Valladares
SENATE FLOOR: 34-0, 5/15/25 (Consent)
AYES: Allen, Archuleta, Arreguín, Ashby, Becker, Blakespear, Cabaldon, Caballero, Choi, Cortese, Dahle, Durazo, Gonzalez, Grayson, Hurtado, Jones, Laird, Limón, McGuire, McNerney, Menjivar, Niello, Ochoa Bogh, Pérez, Richardson, Seyarto, Smallwood-Cuevas, Stern, Strickland, Umberg, Valladares, Wahab, Weber Pierson, Wiener
NO VOTE RECORDED: Alvarado-Gil, Cervantes, Grove, Padilla, Reyes, Rubio
ASSEMBLY FLOOR: 77-0, 8/21/25 (Consent) - See last page for vote
SUBJECT: Private Works Change Order Fair Payment Act
SOURCE: Southern California Association of Scaffold Contractors
DIGEST:
This bill creates a process, until January 1, 2030, by which disputes between an owner, direct contractor, or subcontractor regarding extensions of time and payment of additional compensation for approved changes to the contractor’s scope of work may be resolved through an informal conference and mediation.
Assembly Amendments
of 6/23/25 make various changes to the definitions of “claim” and “owner” for the purposes of this bill’s provisions; eliminates the requirement that the claim be furnished within 60 days of the basis for the claim being discovered; simplify the requirements for a claim to require reasonable documentation to support the claim; removes provisions requiring the claimant to bear the burden of proof to demonstrate that a disputed claim was agreed upon by the owner or project manager, as specified; and specify that its provisions do not apply to the construction of a residential project if the project is not mixed use and does not exceed four stories.
ANALYSIS:
Existing law:
- Defines a “work of improvement” as including, but not limited to: construction, alteration, repair, demolition, or removal, in whole or in part, of, or addition to, a building, wharf, bridge, ditch, flume, aqueduct, well, tunnel, fence, machinery, railroad, or road; seeding, sodding or planting for landscaping purposes; and filling, leveling, or grading real property. (Civil (Civ.) Code § 8050.)
- Specifies that a work of improvement is a private work of improvement when it is not contracted for by a public entity. (Civ. Code §§ 8160, 9000.)
- Defines an “admitted surety insurer” as having the meaning provided in Section 995.120 of the Code of Civil Procedure. (Civ. Code § 8002.)
- Defines “direct contractor” as a contractor that has a direct contractual relationship with an owner. (Civ. Code § 8018.)
- Defines “subcontractor” as a contractor that does not have a direct contractual relationship with an owner, and as including a contractor that has a contractual relationship with a direct contractor or with another subcontractor. (Civ. Code § 8046.)
- Permits the retention of a portion of the payment due a direct contractor or due a subcontractor, and specifies that, if any owner withholds a retention from a direct contractor, the owner must pay the retention to the contractor within 45 days after completion of the work of improvement. Specifies that, if a work of improvement ultimately will become the property of a public entity, the owner may condition payment of the retention allocable to that part upon the acceptance of that part of the work by the public entity. Specifies that the owner may withhold from a final payment up to 150% of any disputed amount when there is a good faith dispute between the owner and the direct contractor regarding the retention payment due. (Civ. Code § 8812.)
- Requires that, if the direct contractor gives the owner, or a subcontractor gives the direct contractor, a notice that work that is in dispute has been completed, the owner or direct contractor must notify the party within 10 days whether the disputed work is accepted or rejected. Specifies that, if the disputed work is accepted, the owner or direct contractor must pay the portion of the retention that relates to the disputed work. (Civ. Code § 8816.)
- Specifies that, if a direct contractor is not paid the amount due pursuant to a written contract within 35 days after the date payment is due, and there is no dispute as to the satisfactory performance of the contractor, the contractor may give the owner a stop work notice, as specified. (Civ. Code § 8832.)
- Specifies that a contractor that gives an owner a stop work notice must also post a notice of intent to give a stop work notice at least five days before providing a stop work notice, and that the contractor must give a copy of any stop work notice to all subcontractors with whom the contractor has a direct contractual relationship at the same time that they give the stop work notice to the owner. (Civ. Code § 8834.)
- Specifies that, if payment of the amount claimed in the stop work notice is not made within 10 days of when the contractor provided the stop work notice, the direct contractor, their surety, or an owner may seek judicial determination of liability for the amount due through an expedited proceeding. (Civ. Code § 8844.)
This bill:
- Makes various findings and declarations related to construction projects and the need for clear procedures for resolving disputes.
- Specifies that its provisions apply to any claim by a contractor, or where authorized, a subcontractor, in connection to a work of improvement or site improvement.
- Specifies that, upon receipt of a claim pursuant to its provisions, the owner to which the claim applies must perform a reasonable review of the claim and, within 30 days, provide the claimant a written statement identifying what portion of the claim is disputed and what is not.
- Requires the claimant to furnish reasonable documentation to support the claim.
- Permits the parties, by mutual agreement, to extend the time period described in its provisions.
- Specifies that, if a claimant disputes all or part of an owner’s written response to the claim, or if the owner fails to respond to the claim within the required timeframe, the claimant may demand in writing an informal conference to meet and confer for settlement.
- Specifies that, upon receipt of a demand for an informal conference, the owner must schedule the meet and confer conference with the claimant within 30 days.
- Specifies that, within 10 days of the conclusion of the meet and confer conference, if the claim or any part thereof remains in dispute, the owner must provide the claimant a written statement identifying the portion that remains in dispute.
- Specifies that any remaining disputed claims after the informal conference must be submitted to nonbinding mediation, with the owner and the claimant sharing the costs equally. Requires the parties to mutually agree to a mediator within 10 business days after the remaining disputed portion of the claim has been identified in writing, and that, if the parties cannot agree on a mediator within this time period, the contractor may select the mediator.
- Specifies that, if mediation is unsuccessful, the remaining dispute shall be subject to the dispute resolution procedures in the written contract, or by final judgment or operation of law if no dispute resolution procedures exist in the contract.
- Specifies that an owner’s failure to respond to a claim within the time periods required, or to otherwise fail to meet the requirements of its provisions, shall result in the claim being deemed denied in its entirety. However, specifies that this denial shall not constitute an adverse finding with regard to the merits of any claim.
- Requires undisputed amounts of a claim to be paid within 60 days, and that undisputed amounts not paid in a timely manner will bear two percent interest per month. Specifies that disputed amounts found to be owed through the contract’s dispute resolution procedures or by final judgment or operation of law also shall bear interest at two percent per month.
- Specifies that, if a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against the owner because they do not have privity of contract with the owner, the contractor must present the claim to the owner on the subcontractor’s behalf. Permits a subcontractor to request in writing that the contractor present a claim for work that was performed by the subcontractor or lower tier subcontractor. Requires a subcontractor requesting their claim be furnished to the owner must furnish the contractor with timely and reasonable documentation to support the claim in order for the contractor to meet their obligations, and that the subcontractor must cooperate with the contractor in the informal conference, mediation, and dispute resolution processes required. Requires the contractor to exercise good faith in presenting the subcontractor’s claim, and prohibits the contractor from making any settlement of a claim to which the subcontractor does not approve. Requires the contractor to notify the subcontractor within 30 days of receiving their request to present their claim to the owner whether the contractor presented the claim and, if not, a statement why the contractor did not.
- Clarifies that the process in (13), above, does not preclude a subcontractor from exercising their lien rights and stop work notice rights.
- Provides that a contractor and subcontractors have the right to suspend performance of their work, without penalty, until the payment is received if: the contractor or subcontractor informs the owner by registered or certified mail that payment is due pursuant to the bill’s provisions, or where the claim is deemed denied; 30 days have passed since this notice of due payment is sent to the owner; and the contractor or subcontractor sends a 10-day written notice of intent to stop work.
- Specifies that any disputed amount which the owner agrees to pay, or which the owner is found to owe, shall, from the date of the agreement or finding, be considered an undisputed amount.
- Specifies that a waiver of the rights provided by these provisions is void and contrary to public policy. Specifies that the parties may mutually agree to waive, in writing, the informal conference and mediation provisions and proceed directly to the commencement of a civil action or binding arbitration.
- Specifies that contractors, owners, and subcontractors may agree to reasonable change order, claim, and dispute resolution procedures and requirements in addition to these provisions as long as those contractual provisions do not conflict with or impair the timeframes and procedures provided.
- For the purposes of the bill’s provisions, defines the following terms:
- “Claim” to mean a separate demand by a contractor, or, where authorized, sent by registered mail or certified mail with return receipt requested, for one or more of the following:
- a time extension, including, without limitation, for relief from damages or penalties for delay assessed by an owner under contract for a work of improvement or site improvement;
- payment by the owner of money or damages arising from work done by, or on behalf of, the contractor pursuant to a contract for a work of improvement or site improvement project and payment for which is not otherwise expressly provided or to which the claimant is not otherwise entitled; or
- payment of an amount that is disputed by the owner.
- “Owner” to mean an owner who causes a building, improvement, or structure to be constructed, altered, or repaired, or that person’s successor in interest at the date a notice of completion is recorded, whether the interest or estate of the owner be in fee, as vendee under a contract of purchase, as lessee, or other interest or estate less than the fee. Specifies that, where the interest or estate is held by two or more persons as joint tenants or tenants in common, any one or more of the cotenants may be deemed to be the “owner” within the meaning of this section. Specifies that “owner” does not include a state agency, department, office, division, bureau, board, or commission, the CSU, UC, a city, county, city and county, district, special district, public authority, political subdivision, public corporation, or nonprofit transit corporation, as specified.
- “Claim” to mean a separate demand by a contractor, or, where authorized, sent by registered mail or certified mail with return receipt requested, for one or more of the following:
- Specifies that these provisions do apply to contracts entered into on or after January 1, 2026, and that these provisions are repealed as of January 1, 2030.
- Exempts from its provisions the construction of a residential project if the project is not mixed use and does not exceed four stories.
FISCAL EFFECT: Appropriation: No Fiscal Com.: No Local: No
SUPPORT: (Verified 8/22/25)
Southern California Association of Scaffold Contractors (source)
American Subcontractors Association- California
California Association of Sheet Metal & Air Conditioning Contractors National
Association
California Legislative Conference of Plumbing, Heating & Piping Industry
Finishing Contractors Association of Southern California
International Union of Operating Engineers, Cal-Nevada Conference
National Electrical Contractors Association
Northern California Allied Trades
Northern California Floor Covering Association
Southern California Contractors Association
Southern California Glass Management Association
United Contractors
Wall and Ceiling Alliance
Western Painting and Coating Contractors Association
Western Wall and Ceiling Contractors Association
OPPOSITION: (Verified 8/22/25)
None received
ARGUMENTS IN SUPPORT:
According to the Southern California Association of Scaffold Contractors (SCASC), which is the source of SB 440:
SB 440 establishes a fair and prudent process for contractors to follow for approved change orders on construction projects. This process will reduce litigation, protect subcontractors, and mitigate construction delays.
Contractors that perform change orders on private works construction projects frequently face extended payment delays for approved change orders leading to financial instability, increased credit dependency and, in extreme cases, business failure. Power imbalances between the project owner, general contractor and subcontractor can create exploitive practices where subcontractors can be leveraged to reduce their value of their change order if it wants to continue a future business relationship.
SB 440 levels the playing field for contractors, especially subcontractors, by ensuring a fair change order process and providing for timely payments. This process reduces unnecessary hardship on lower tier contractors, especially disadvantaged business enterprises, disabled veteran business enterprises, and small business enterprises.
ARGUMENTS IN OPPOSITION:
ASSEMBLY FLOOR: 77-0, 8/21/25
AYES: Aguiar-Curry, Ahrens, Alanis, Alvarez, Arambula, Ávila Farías, Bains, Bauer-Kahan, Bennett, Berman, Boerner, Bonta, Bryan, Calderon, Caloza, Carrillo, Castillo, Chen, Connolly, Davies, DeMaio, Dixon, Elhawary, Ellis, Flora, Fong, Gabriel, Gallagher, Garcia, Gipson, Jeff Gonzalez, Mark González, Hadwick, Haney, Harabedian, Hart, Hoover, Irwin, Jackson, Kalra, Krell, Lackey, Lee, Lowenthal, Macedo, McKinnor, Muratsuchi, Nguyen, Ortega, Pacheco, Papan, Patel, Patterson, Pellerin, Petrie-Norris, Quirk-Silva, Ramos, Celeste Rodriguez, Michelle Rodriguez, Rogers, Blanca Rubio, Sanchez, Schiavo, Schultz, Sharp-Collins, Solache, Soria, Stefani, Ta, Tangipa, Valencia, Wallis, Ward, Wicks, Wilson, Zbur, Rivas
NO VOTE RECORDED: Addis, Ransom
Prepared by: Ian Dougherty / JUD. / (916) 651-4113
8/22/25 15:36:02
**** END ****
Date of Hearing: July 15, 2025
ASSEMBLY COMMITTEE ON JUDICIARY
Ash Kalra, Chair
SBPCA Bill Id:SB 440
Author:(Ochoa Bogh) – As Amended Ver:June 23, 2025
PROPOSED CONSENT
SENATE VOTE: 34-0
SUBJECT: PRIVATE WORKS CHANGE ORDER FAIR PAYMENT ACT
KEY ISSUE: IN ORDER TO STREAMLINE DISPUTES IN CONSTRUCTION CONTRACTS FOR PRIVATE WORKS, SHOULD THE LEGISLATURE ESTABLISH THE PRIVATE WORKS CHANGE ORDER FAIR PAYMENT ACT?
SYNOPSIS
Construction projects are infamously prone to contention between owners and contractors, often prompting debate over the duration, cost, or result of the project. In some cases, one party will complete a change order, which typically refers to a modification to an existing construction contract that adjusts the contractor’s scope of work. Construction contracts typically incorporate a “changes in the work” clause within the original contract that provides the procedure for change orders. However, the shift in the original terms of the contract can give rise to additional costs for materials and labor. In the event there is any dispute about the terms of the change order and given the owner’s authority to withhold retention payments, change orders can result in significant financial burdens on contractors. In 2016, AB 626 (Chiu, Chap. 810, Stat.. 2016) created a claims resolution process for any claim by a contractor engaged in a contract for a public works project. This bill seeks to mirror the process established in AB 626 for disputes arising from contracts for private works.
This bill is sponsored by the Southern California Association of Scaffold Contractors. It is supported by the International Union of Operating Engineers, Cal-Nevada Congress and various building industry advocates, including the National Electrical Contractors Association and United Contractors.
SUMMARY: Establishes the Private Works Change Order Fair Payment Act. Specifically, this bill:
- Makes relevant findings and declarations regarding the impact of delays in private works projects.
- Establishes the Private Works Change Order Fair Payment Act (Act) and applies its provisions to any claim by a contractor, or where authorized, a subcontractor, in connection to a work of improvement or site improvement.
- Defines the following:
- “Claim” means a separate demand by a contractor, or where authorized pursuant to this article, a subcontractor, sent by registered mail or certified mail with return receipt requested, for either of the following:
- A time extension, including, without limitation, for relief from damages or penalties for delay assessed by an owner under contract for a work of improvement or site improvement;
- Payment by the owner of money or damages arising from work done by, or on behalf of, the contractor pursuant to the contract for a work of improvement or site improvement project and payment for which is not otherwise expressly provided or to which the claimant is not otherwise entitled;
- Payment of an amount that is disputed by the owner.
- “Owner” means the owner who causes a building, improvement, or structure to be constructed, altered, or repaired, or that person’s successor in interest at the date a notice of completion is recorded, whether the interest or estate of the owner be in fee, as vendee under contract of purchase, as lessee, or other interest or estate less than the fee. Where the interest or estate is held by two or more persons as joint tenants or tenants in common, any one or more of the cotenants may be deemed to be the “owner.” An owner shall have the right to a designated representative. “Owner” does not include a state agency, department, office, division, bureau, board, or commission, the California State University, the University of California, a city, including a charter city, county, including a charter county, city and county, including a charter city and county, district, special district, public authority, political subdivision, public corporation, or nonprofit transit corporation wholly owned by a public agency and formed to carry out the purposes of the public agency.
- “Project manager” means a person, partnership, corporation, or other legal entity that is designated by the owner to direct construction and represent the owner during the performance of the services covered under the construction contract and is authorized to make changes, adjustments, and interpretations of the contract in order to facilitate the completion of the project. In the absence of the appointment of a project manager by the owner, the owner shall serve as a project manager on a project.
- “Claim” means a separate demand by a contractor, or where authorized pursuant to this article, a subcontractor, sent by registered mail or certified mail with return receipt requested, for either of the following:
- Requires the owner to which the claim applies to, upon receipt of a claim, to perform a reasonable review of the claim and, within a period not to exceed 30 days, provide the claimant a written statement identifying what portion of the claim is disputed and what portion is undisputed.
- Requires the claimant to furnish reasonable documentation to support the claim.
- Authorizes an owner and contractor to extend the specified time periods by mutual agreement.
- Requires payment of any undisputed portion of the claim to be processed and made within 60 days after the owner issues its written statement.
- Authorizes the claimant to demand in writing an informal conference to meet and confer for settlement of the issues in dispute if the claimant disputes all or any portion of the owner’s written response to the claim, or if the owner fails to respond to a claim issued within the timeframe prescribed.
- Requires the owner to schedule a meet and confer conference with the claimant for settlement of the dispute within 30 days of receiving a demand in writing sent by registered mail or certified mail, return receipt requested.
- Requires, if the claim or any portion of the claim remains in dispute, the owner to provide the claimant a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed within 10 days following the conclusion of the meet and confer conference.
- Requires payment of any undisputed portion of the claim identified in the written statement to be processed and made within 60 days after the owner issues its written statement.
- Requires the remaining disputed portion of the claim, if one exists following the informal conference, to be submitted to nonbinding mediation, with the owner and the claimant sharing the associated costs equally.
- Requires the owner and claimant to mutually agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing. Authorizes the contractor to select the mediator to be used if the parties cannot agree upon a mediator within the time allotted.
- Authorizes the contractor, if the owner refuses mediation, to suspend work on the project, as specified.
- If mediation is unsuccessful, makes the parts of the claim remaining in dispute subject to the dispute resolution procedures elected in the written contract of the parties, or, if no such election exists, by final judgment or by operation of law.
- Deems the claim denied in its entirety if the owner fails to respond to a claim within the time periods described or to otherwise meet the requirements of this section. A claim that is denied by reason of the owner’s failure to have responded to a claim, or its failure to otherwise meet the time requirements of this section, shall not constitute an adverse finding with regard to the merits of the claim or the responsibility or qualifications of the claim.
- Imposes interest at 2 percent per month on any undisputed amounts not paid in a timely manner as required by these provisions. Imposes interest at 2 percent per month on disputed amounts which are later found to be owed through the dispute resolution procedures elected in the written contract of the parties, or, if no such election exists, by final judgment or by operation of law, beginning from the date on which those amounts would have been due had they not been disputed.
- Establishes that nothing in this bill’s provisions prevents either party from submitting, or otherwise limit the applicability of, a statutory offer of settlement under Section 998 of the Code of Civil Procedure.
- Requires the contractor to present to the owner a claim on behalf of a subcontractor or lower tier subcontractor if a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against an owner because privity of contract does not exist, except as specified.
- Authorizes a subcontractor to request in writing, either on their own behalf or on behalf of a lower tier subcontractor, that the contractor present a claim for work that was performed by the subcontractor or by a lower tier subcontractor on behalf of the subcontractor.
- Requires the subcontractor requesting that the claim be presented to the owner to furnish the contractor with timely and reasonable documentation to support the subcontractor’s claim to enable the contractor to meet their specified obligations and to thereafter cooperate with the contractor in the informal conference, mediation, and dispute resolution processes required pursuant to this section relating to the subcontractor’s claim.
- Requires the contractor to exercise good faith in fulfilling their obligations on behalf of the subcontractor and prohibits them from making a settlement of any claim to which the subcontractor does not approve, in writing.
- Requires the contractor to notify the subcontractor in writing within 30 days of receipt of the written request as to whether the contractor presented the claim to the owner and, if the contractor did not present the claim, provide the subcontractor with a statement of the reasons for not doing so.
- Clarifies that nothing in the bill’s provisions precludes a subcontractor from exercising its lien rights and its stop work notice rights.
- Grants the contractor and subcontractors the right to suspend performance of their work, without penalty, until the payment is received if the following procedure is followed:
- The owner is informed by registered mail or certified mail, return receipt requested, that payment is due pursuant to the provisions of this bill, or where the claim is deemed denied;
- 30 days after the notice of late payment is sent to the owner, the contractor or subcontractor sends a 10-day written notice of intent to stop work to the owner, by registered mail or certified mail, return receipt requested.
- Requires any disputed amount which the owner, at any point, agrees to pay, or is found to owe through dispute resolution, by final judgment, or by operation of law, from the date of the agreement or finding, to be considered an undisputed amount for the purpose of any timelines or processes established by this bill.
- Makes a waiver of rights granted by these provisions void and contrary to public policy.
- Notwithstanding 29), all of the following apply:
- Upon receipt of a claim, the parties may mutually agree to waive, in writing, the informal conference and mediation provisions in this section and proceed directly to the commencement of a civil action or binding arbitration, as applicable;
- Owners, contractors, and subcontractors may agree to reasonable change order, claim, and dispute resolution procedures and requirements in addition to the provisions of this bill, so long as the contractual provisions do not conflict with or otherwise impair the timeframes and procedures set forth.
- Applies the Act’s provisions to contracts entered into on or after January 1, 2026. Excludes construction of residential projects if the project is not mixed use and does not exceed four stories from the Act.
- Repeals the Act effective January 1, 2030.
EXISTING LAW:
- Defines a “work of improvement” as including, but not limited to: construction, alteration, repair, demolition, or removal, in whole or in part, of, or addition to, a building, wharf, bridge, ditch, flume, aqueduct, well, tunnel, fence, machinery, railroad, or road; seeding, sodding or planting for landscaping purposes; and filling, leveling, or grading real property. (Civil Code Section 8050. All further references are to the Civil Code unless otherwise noted.)
- Specifies that a work of improvement is a private work of improvement when it is not contracted for by a public entity. (Sections 8160, 9000.)
- Defines an “admitted surety insurer” as having the meaning provided in Section 995.120 of the Code of Civil Procedure. (Section 8002.)
- Defines “direct contractor” as a contractor that has a direct contractual relationship with an owner. (Section 8018.)
- Defines “subcontractor” as a contractor that does not have a direct contractual relationship with an owner, and as including a contractor that has a contractual relationship with a direct contractor or with another subcontractor. (Section 8046.)
- Permits the retention of a portion of the payment due a direct contractor or due a subcontractor, and specifies that, if any owner withholds a retention from a direct contractor, the owner must pay the retention to the contractor within 45 days after completion of the work of improvement. Specifies that, if a work of improvement ultimately will become the property of a public entity, the owner may condition payment of the retention allocable to that part upon the acceptance of that part of the work by the public entity. Specifies that the owner may withhold from a final payment up to 150% of any disputed amount when there is a good faith dispute between the owner and the direct contractor regarding the retention payment due. (Section 8812.)
- Requires that, if the direct contractor gives the owner, or a subcontractor gives the direct contractor, a notice that work that is in dispute has been completed, the owner or direct contractor must notify the party within 10 days whether the disputed work is accepted or rejected. Specifies that, if the disputed work is accepted, the owner or direct contractor must pay the portion of the retention that relates to the disputed work. (Section 8816.)
- Specifies that, if a direct contractor is not paid the amount due pursuant to a written contract within 35 days after the date payment is due, and there is no dispute as to the satisfactory performance of the contractor, the contractor may give the owner a stop work notice, as specified. (Section 8832.)
- Specifies that a contractor that gives an owner a stop work notice must also post a notice of intent to give a stop work notice at least five days before providing a stop work notice, and that the contractor must give a copy of any stop work notice to all subcontractors with whom the contractor has a direct contractual relationship at the same time that they give the stop work notice to the owner. (Section 8834.)
- Specifies that, if payment of the amount claimed in the stop work notice is not made within 10 days of when the contractor provided the stop work notice, the direct contractor, their surety, or an owner may seek judicial determination of liability for the amount due through an expedited proceeding. (Section 8844.)
FISCAL EFFECT: As currently in print this bill is keyed non-fiscal.
COMMENTS: Construction projects are infamously prone to contention between owners and contractors, often prompting debate over the duration, cost, or result of the project. In some cases, one party will complete a change order, which typically refers to a modification to an existing construction contract that adjusts the contractor’s scope of work. Construction contracts typically incorporate a “changes in the work” clause within the original contract that provides the procedure for change orders. However, the shift in the original terms of the contract can give rise to additional costs for materials and labor. In the event there is any dispute about the terms of the change order, given the owner’s authority to withhold retention payments, change orders can result in significant financial burdens on contractors. According to the author:
SB 440 establishes a fair and timely payment process for construction change orders arising from contract modifications, adjustments in project scope, unplanned work requirements, contractual work revisions, construction adaptations and other similar types of routine changes that accompany construction projects. This process will prevent unjust and completely avoidable financial strains on small construction businesses and entrepreneurs. Without the protections inherent in SB 440’s process, many are pushed to the brink of bankruptcy. The need for reform is urgent, as the widespread abuse enabled by the absence of a clear change order process is not only prevalent but increasing across the industry.
Specifically, contractors and subcontractors often face extended payment delays for approved change orders, leading to financial instability, increased credit dependency, and, in extreme cases, business failure. Additionally, contractors bear financial and operational risks when required to perform additional work without clear payment guarantees. Power imbalances between the project owner, general contractor and subcontractor can create exploitive practices where subcontractors can be leveraged to reduce the value of their change order if they want to continue a future business relationship. All of this can, regrettably, lead to costly litigation, delaying project completion and increasing expenses for all parties.
SB 440 levels the playing field for contractors, especially subcontractors, by ensuring a fair change order process and providing for timely payments. This process reduces unnecessary hardship on lower-tier contractors, especially disadvantaged business enterprises, disabled veteran business enterprises, and small business enterprises.
The process established by SB 440 is based on AB 626 (Chiu, 2016), which passed unanimously in the Assembly and Senate.
Public Contracts Code Section 9204, enacted via AB 626 (Chiu, Chap. 810, Stats. 2016), provides a claims resolution process for any claim by a contractor engaged in a contract for a public works project. Under its provisions, a contractor can submit a claim for a time extension, including a relief from damages or penalties for the delay, payment of money or damages arising from work done by the contractor pursuant to the contract, and payment of an amount disputed by the public entity. Once the contractor submits the claim, the public entity has 45 days to conduct a “reasonable review” of the claim and provide a written statement identifying which portion of the claim is undisputed, and which remains in dispute. Parties must then complete an informal conference to discuss the remaining issues at dispute, followed by nonbinding mediation. Contractors are also authorized to present a claim pursuant to its provisions on behalf of a subcontractor that lacks the legal standing to assert a claim against the public entity.
This bill mirrors AB 626 for private works contracts. A “private work of improvement,” as opposed to a “public work,” refers to construction projects on private property. Civil Code Section 8050 defines a “work of improvement” as work to construct, alter, repair, demolish, or remove, in whole or in part, or add to, various structures including a building, wharf, well, machinery, or fence. (Civil Code Section 8050.) Within 30 days of receiving a claim from a contractor, an owner must perform a reasonable review of the claim and return a written statement identifying which portions are disputed and which are not. The claimant is required to provide “reasonable documentation” to support their claim, and the timeline can be extended upon mutual agreement. The owner must then pay any undisputed portion of the contractor’s claim within 60 days after their written statement. In the event there is any remaining dispute, those portions are then submitted to nonbinding mediation where both parties share the cost of mediation equally. Any remaining disputes are adjudicated pursuant to the dispute resolution procedures identified in the underlying contract or, absent such agreement, by final judgment or operation of law. Each phase in the process has its own relevant timeline by which the owner must issue a written statement admitting or denying the claim, in whole or in part.
This bill also mirrors Section 9204 by establishing that an owner’s failure to respond to a claim within any of the time periods identified will result in the denial of the claim in its entirety, but that the denial, or failure to meet the required timelines, does not constitute an adverse finding to the merits of the claim. Also like Section 9204, SB 440 allows for a subcontractor to request that a contractor present a claim to the owner on their behalf if they lack standing through privity of contract. For a claim presented by a contractor on behalf of a subcontractor, the same timelines and obligations apply as to a claim submitted by a contractor on their own behalf. Additionally, a contractor is required to notify a subcontractor within 30 days of receiving the request from the subcontractor, as compared to 45 days in Section 9204, if they presented the claim to the owner and, if they did not, they must provide a statement explaining their decision. Like Section 9204, SB 440 imposes interest on unpaid undisputed amounts. However, while Section 9204 imposes seven percent monthly interest, SB 440 imposes 2 percent monthly interest.
This bill also permits a contractor or subcontractor to suspend work on a contract without penalty if the owner fails to pay any of the undisputed amounts. In order to avoid the penalties resulting from pausing work, either the contractor or subcontractor is required to notify the owner that payment is due and after 30 days have elapsed, provide the owner a 10-day written notice of their intent to stop work. In total, owners would have 40 days under this provision to provide payment due to the contractor or subcontractor before either could pause work on a contract.
In sum, this bill provides an alternative method to resolve disputes in contracts for private works of construction. It is not the only potential avenue for dispute resolution, and such conflicts can continue to be resolved through existing mechanisms, including through a civil action or binding arbitration if there is mutual agreement. Because the bill sunsets the Act in 2030, the Legislature will be prompted to evaluate its efficacy. If, after five years, the program indeed functions to streamline dispute resolution for private works, the Legislature may opt to make it permanent at that time.
ARGUMENTS IN SUPPORT: This bill is sponsored by the Southern California Association of Scaffold Contractors. It is supported by the International Union of Operating Engineers, Cal-Nevada Congress and various building industry advocates, including the National Electrical Contractors Association and United Contractors. In support of the bill, the sponsor submits:
SB 440 establishes a fair and prudent process for contractors to follow for approved change orders on construction projects. This process will reduce litigation, protect subcontractors, and mitigate construction delays.
Contractors that perform change orders on private works construction projects frequently face extended payment delays for approved change orders leading to financial instability, increased credit dependency and, in extreme cases, business failure. Power imbalances between the project owner, general contractor and subcontractor can create exploitive practices where subcontractors can be leveraged to reduce their value of their change order if it wants to continue a future business relationship.
SB 440 levels the playing field for contractors, especially subcontractors, by ensuring a fair change order process and providing for timely payments. This process reduces unnecessary hardship on lower tier contractors, especially disadvantaged business enterprises, disabled veteran business enterprises, and small business enterprises.
REGISTERED SUPPORT / OPPOSITION:
Support
Southern California Association of Scaffold Contractors (sponsor)
American Subcontractors Association-California
California Association of Sheet Metal & Air Conditioning Contractors National Association
California Legislative Conference of Plumbing, Heating & Piping Industry
Finishing Contractors Association of Southern California
International Union of Operating Engineers, Cal-Nevada Conference
National Electrical Contractors Association (NECA)
Northern California Allied Trades
Northern California Floor Covering Association
Southern California Contractors Association
Southern California Glass Management Association (SCGMA)
United Contractors (UCON)
Wall and Ceiling Alliance
Western Painting and Coating Contractors Association
Western Wall and Ceiling Contractors Association (WWCCA)
Opposition
None on file
Analysis Prepared by: Manuela Boucher-de la Cadena / JUD. / (916) 319-2334
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 440 |
CONSENT
Bill No: SB 440
Author: Ochoa Bogh (R), et al.
Amended: 4/28/25
Vote: 21
SENATE JUDICIARY COMMITTEE: 12-0, 5/6/25
AYES: Umberg, Niello, Allen, Arreguín, Ashby, Caballero, Durazo, Laird, Stern, Wahab, Weber Pierson, Wiener
NO VOTE RECORDED: Valladares
SUBJECT: Private Works Construction Fair Payment and Dispute Resolution Act
SOURCE: Southern California Association of Scaffold Contractors
DIGEST:
This bill creates a process, until January 1, 2030, by which disputes between an owner, direct contractor, or subcontractor regarding extensions of time and payment of additional compensation for approved changes to the contractor’s scope of work may be resolved through an informal conference and mediation.
ANALYSIS:
Existing law:
- Defines a “work of improvement” as including, but not limited to: construction, alteration, repair, demolition, or removal, in whole or in part, of, or addition to, a building, wharf, bridge, ditch, flume, aqueduct, well, tunnel, fence, machinery, railroad, or road; seeding, sodding or planting for landscaping purposes; and filling, leveling, or grading real property. (Civil (Civ.) Code § 8050.)
- Specifies that a work of improvement is a private work of improvement when it is not contracted for by a public entity. (Civ. Code §§ 8160, 9000.)
- Defines an “admitted surety insurer” as having the meaning provided in Section 995.120 of the Code of Civil Procedure. (Civ. Code § 8002.)
- Defines “direct contractor” as a contractor that has a direct contractual relationship with an owner. (Civ. Code § 8018.)
- Defines “subcontractor” as a contractor that does not have a direct contractual relationship with an owner, and as including a contractor that has a contractual relationship with a direct contractor or with another subcontractor. (Civ. Code § 8046.)
- Permits the retention of a portion of the payment due a direct contractor or due a subcontractor, and specifies that, if any owner withholds a retention from a direct contractor, the owner must pay the retention to the contractor within 45 days after completion of the work of improvement. Specifies that, if a work of improvement ultimately will become the property of a public entity, the owner may condition payment of the retention allocable to that part upon the acceptance of that part of the work by the public entity. Specifies that the owner may withhold from a final payment up to 150% of any disputed amount when there is a good faith dispute between the owner and the direct contractor regarding the retention payment due. (Civ. Code § 8812.)
- Requires that, if the direct contractor gives the owner, or a subcontractor gives the direct contractor, a notice that work that is in dispute has been completed, the owner or direct contractor must notify the party within 10 days whether the disputed work is accepted or rejected. Specifies that, if the disputed work is accepted, the owner or direct contractor must pay the portion of the retention that relates to the disputed work. (Civ. Code § 8816.)
- Specifies that, if a direct contractor is not paid the amount due pursuant to a written contract within 35 days after the date payment is due, and there is no dispute as to the satisfactory performance of the contractor, the contractor may give the owner a stop work notice, as specified. (Civ. Code § 8832.)
- Specifies that a contractor that gives an owner a stop work notice must also post a notice of intent to give a stop work notice at least five days before providing a stop work notice, and that the contractor must give a copy of any stop work notice to all subcontractors with whom the contractor has a direct contractual relationship at the same time that they give the stop work notice to the owner. (Civ. Code § 8834.)
- Specifies that, if payment of the amount claimed in the stop work notice is not made within 10 days of when the contractor provided the stop work notice, the direct contractor, their surety, or an owner may seek judicial determination of liability for the amount due through an expedited proceeding. (Civ. Code § 8844.)
This bill:
- Makes various findings and declarations related to construction projects and the need for clear procedures for resolving disputes.
- Specifies that its provisions apply to any claim by a contractor, or where authorized, a subcontractor, in connection to a work of improvement or site improvement.
- Specifies that, upon receipt of a claim pursuant to its provisions, the owner to which the claim applies must perform a reasonable review of the claim and, within 30 days, provide the claimant a written statement identifying what portion of the claim is disputed and what is not.
- Requires the claimant to furnish all claims within 60 days of when the basis for the claim was discovered, and requires a claim to include: the reason for the claim and the method of calculating the time and additional compensation sought.
- Permits the parties, by mutual agreement, to extend the time periods described in its provisions.
- Specifies that, if a claimant disputes all or part of an owner’s written response to the claim, or if the owner fails to respond to the claim within the required timeframe, the claimant may demand in writing an informal conference to meet and confer for settlement.
- Specifies that, upon receipt of a demand for an informal conference, the owner must schedule the meet and confer conference with the claimant within 30 days.
- Specifies that, within 10 days of the conclusion of the meet and confer conference, if the claim or any part thereof remains in dispute, the owner must provide the claimant a written statement identifying the portion that remains in dispute.
- Specifies that any remaining disputed claims after the informal conference must be submitted to nonbinding mediation, with the owner and the claimant sharing the costs equally. Requires the parties to mutually agree to a mediator within 10 business days after the remaining disputed portion of the claim has been identified in writing, and that, if the parties cannot agree on a mediator within this time period, the contractor may select the mediator.
- Specifies that, if mediation is unsuccessful, the remaining dispute shall be subject to the dispute resolution procedures in the written contract, or by final judgment or operation of law if no dispute resolution procedures exist in the contract.
- Specifies that an owner’s failure to respond to a claim within the time periods required, or to otherwise fail to meet the requirements of its provisions, shall result in the claim being deemed denied in its entirety. However, specifies that this denial shall not constitute an adverse finding with regard to the merits of any claim.
- Requires undisputed amounts of a claim to be paid within 60 days, and that undisputed amounts not paid in a timely manner will bear two percent interest per month. Specifies that disputed amounts found to be owed through the contract’s dispute resolution procedures or by final judgment or operation of law also shall bear interest at two percent per month.
- Specifies that, if a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against the owner because they do not have privity of contract with the owner, the contractor must present the claim to the owner on the subcontractor’s behalf. Permits a subcontractor to request in writing that the contractor present a claim for work that was performed by the subcontractor or lower tier subcontractor. Requires a subcontractor requesting their claim be furnished to the owner must furnish the contractor with timely and reasonable documentation to support the claim in order for the contractor to meet their obligations, and that the subcontractor must cooperate with the contractor in the informal conference, mediation, and dispute resolution processes required. Requires the contractor to exercise good faith in presenting the subcontractor’s claim, and prohibits the contractor from making any settlement of a claim to which the subcontractor does not approve. Requires the contractor to notify the subcontractor within 30 days of receiving their request to present their claim to the owner whether the contractor presented the claim and, if not, a statement why the contractor did not.
- Clarifies that the process in (13), above, does not preclude a subcontractor from exercising their lien rights and stop work notice rights.
- Provides that a contractor and subcontractor have the right to suspend performance of their work, without penalty, if the owner fails to make payment of the undisputed amounts due, until the payment is received if: the contractor or subcontractor informs the owner by registered or certified mail that an undisputed payment is past due; 30 days has passed since this notice of late payment is sent to the owner; and the contractor or subcontractor sends a 10-day written notice of intent to stop work.
- Specifies that any disputed amount which the owner agrees to pay, or which the owner is found to owe, shall, from the date of the agreement or finding, be considered an undisputed amount.
- Specifies that a contractor or subcontractor bringing a claim under its provisions bears the burden of proof, by a preponderance of the evidence, to demonstrate either:
- That any disputed claim was agreed upon by the owner, or any agent of the owner who was reasonably believed to have authority to amend the construction contract; or
- Any disputed claim was agreed upon by the project manager in the case of minor changes that are not inconsistent with the intent of the original construction contract.
- Specifies that a waiver of the rights provided by these provisions is void and contrary to public policy. Specifies that the parties may mutually agree to waive, in writing, the informal conference and mediation provisions and proceed directly to the commencement of a civil action or binding arbitration.
- Specifies that contractors, owners, and subcontractors may agree to reasonable change order, claim, and dispute resolution procedures and requirements in addition to these provisions as long as those contractual provisions do not conflict with or impair the timeframes and procedures provided.
- For the purposes of the bill’s provisions, defines the following terms:
- “Claim” to mean a separate and timely demand by a contractor, or, where authorized, sent by registered mail or certified mail with return receipt requested, for either of the following:
- A time extension, including, without limitation, for relief from damages or penalties for delay assessed by an owner under contract for a work of improvement or site improvement; or
- Payment of additional compensation by an owner for approved changes to the contractor’s scope of work in connection with a work of improvement or site improvement, whether disputed or undisputed.
- “Owner” to mean an owner who causes a building, improvement, or structure to be constructed, altered, or repaired, or that person’s successor in interest at the date a notice of completion is recorded, whether the interest or estate of the owner be in fee, as vendee under a contract of purchase, as lessee, or other interest or estate less than the fee. Specifies that, where the interest or estate is held by two or more persons as joint tenants or tenants in common, any one or more of the cotenants may be deemed to be the “owner” within the meaning of this section.
- “Claim” to mean a separate and timely demand by a contractor, or, where authorized, sent by registered mail or certified mail with return receipt requested, for either of the following:
- Specifies that these provisions do apply to contracts entered into on or after January 1, 2026, and that these provisions are repealed as of January 1, 2030.
- Exempts from its provisions the construction of residential or multi-family dwellings, and Type V construction, as defined.
FISCAL EFFECT: Appropriation: No Fiscal Com.: No Local: No
SUPPORT: (Verified 5/8/25)
Southern California Association of Scaffold Contractors (source)
American Subcontractors Association-California
California Association of Sheet Metal & Air Conditioning Contractors National
Association
California Legislative Conference of Plumbing, Heating & Piping Industry
Finishing Contractors Association of Southern California
International Union of Operating Engineers, Cal-Nevada Conference
National Electrical Contractors Association
Northern California Allied Trades
Northern California Floor Covering Association
Southern California Contractors Association
Southern California Glass Management Association
United Contractors
Wall and Ceiling Alliance
Western Painting and Coating Contractors Association
Western Wall and Ceiling Contractors Association
OPPOSITION: (Verified 5/8/25)
None received
ARGUMENTS IN SUPPORT:
According to the Southern California Association of Scaffold Contractors, which is the sponsor of SB 440:
SB 440 establishes a fair and prudent process for contractors to follow for approved change orders on construction projects. This process will reduce litigation, protect subcontractors, and mitigate construction delays.
Contractors that perform change orders on private works construction projects frequently face extended payment delays for approved change orders leading to financial instability, increased credit dependency and, in extreme cases, business failure. Power imbalances between the project owner, general contractor and subcontractor can create exploitive practices where subcontractors can be leveraged to reduce their value of their change order if it wants to continue a future business relationship.
SB 440 levels the playing field for contractors, especially subcontractors, by ensuring a fair change order process and providing for timely payments. This process reduces unnecessary hardship on lower tier contractors, especially disadvantaged business enterprises, disabled veteran business enterprises, and small business enterprises.
Prepared by: Ian Dougherty / JUD. / (916) 651-4113
5/12/25 16:06:18
**** END ****
Senator Thomas Umberg, Chair
2025-2026 Regular Session
Bill No: SB 440 (Author:Ochoa Bogh)
Version: April 28, 2025
Hearing Date: May 6, 2025
Fiscal: No
Urgency: No
Consultant: ID
SUBJECT
Private Works Construction Fair Payment and Dispute Resolution Act
DIGEST
This bill creates a process, until January 1, 2030, by which disputes between an owner, direct contractor, or subcontractor regarding extensions of time and payment of additional compensation for approved changes to the contractor’s scope of work may be resolved through an informal conference and mediation.
EXECUTIVE SUMMARY
A private work of improvement is work to construct, alter, repair, demolish, or remove buildings, bridges, and other structures, or to conduct other work on real property like leveling, grading, or landscaping, that is contracted for by a private entity. Often, the owner of a private work of improvement project contracts with a direct contractor for the work, and the direct contractor contracts with subcontractors for completion of specific components of the project. Sometimes, a change in the contractor or subcontractor’s work, or the timeline for completing the project, occurs during the middle of the project. When they do, the parties can agree to what is called a change order for that new or extra work or deviation from the contract. Because the change order was not in the original contract, and may not be a written agreement, disputes sometimes arise regarding payment for the extra work, with contractors and subcontractors often suffering due to late or only partial payment for their work under the change order.
SB 440 creates a process through which a party may submit a claim related to an extension of time or additional compensation under a change order for resolution through an informal conference or mediation procedures. SB 440 is sponsored by the Southern California Association of Scaffold Contractors, and is supported by various contractors’ and subcontractors’ organizations and trade associations. The Committee has received no timely letters of opposition.
PROPOSED CHANGES TO THE LAW
Existing law:
- Defines a “work of improvement” as including, but not limited to: construction, alteration, repair, demolition, or removal, in whole or in part, of, or addition to, a building, wharf, bridge, ditch, flume, aqueduct, well, tunnel, fence, machinery, railroad, or road; seeding, sodding or planting for landscaping purposes; and filling, leveling, or grading real property. (Civ. Code § 8050.)
- Specifies that a work of improvement is a private work of improvement when it is not contracted for by a public entity. (Civ. Code §§ 8160, 9000.)
- Defines an “admitted surety insurer” as having the meaning provided in Section 995.120 of the Code of Civil Procedure. (Civ. Code § 8002.)
- Defines “direct contractor” as a contractor that has a direct contractual relationship with an owner. (Civ. Code § 8018.)
- Defines “subcontractor” as a contractor that does not have a direct contractual relationship with an owner, and as including a contractor that has a contractual relationship with a direct contractor or with another subcontractor. (Civ. Code § 8046.)
- Permits the retention of a portion of the payment due a direct contractor or due a subcontractor, and specifies that, if any owner withholds a retention from a direct contractor, the owner must pay the retention to the contractor within 45 days after completion of the work of improvement. Specifies that, if a work of improvement ultimately will become the property of a public entity, the owner may condition payment of the retention allocable to that part upon the acceptance of that part of the work by the public entity. Specifies that the owner may withhold from a final payment up to 150% of any disputed amount when there is a good faith dispute between the owner and the direct contractor regarding the retention payment due. (Civ. Code § 8812.)
- Requires that, if the direct contractor gives the owner, or a subcontractor gives the direct contractor, a notice that work that is in dispute has been completed, the owner or direct contractor must notify the party within 10 days whether the disputed work is accepted or rejected. Specifies that, if the disputed work is accepted, the owner or direct contractor must pay the portion of the retention that relates to the disputed work. (Civ. Code § 8816.)
- Specifies that, if a direct contractor is not paid the amount due pursuant to a written contract within 35 days after the date payment is due, and there is no dispute as to the satisfactory performance of the contractor, the contractor may give the owner a stop work notice, as specified. (Civ. Code § 8832.)
- Specifies that a contractor that gives an owner a stop work notice must also post a notice of intent to give a stop work notice at least five days before providing a stop work notice, and that the contractor must give a copy of any stop work notice to all subcontractors with whom the contractor has a direct contractual relationship at the same time that they give the stop work notice to the owner. (Civ. Code § 8834.)
- Specifies that, if payment of the amount claimed in the stop work notice is not made within 10 days of when the contractor provided the stop work notice, the direct contractor, their surety, or an owner may seek judicial determination of liability for the amount due through an expedited proceeding. (Civ. Code § 8844.)
This bill:
- Makes various findings and declarations related to construction projects and the need for clear procedures for resolving disputes.
- Specifies that its provisions apply to any claim by a contractor, or where authorized, a subcontractor, in connection to a work of improvement or site improvement.
- Specifies that, upon receipt of a claim pursuant to its provisions, the owner to which the claim applies must perform a reasonable review of the claim and, within 30 days, provide the claimant a written statement identifying what portion of the claim is disputed and what is not.
- Requires the claimant to furnish all claims within 60 days of when the basis for the claim was discovered, and requires a claim to include: the reason for the claim and the method of calculating the time and additional compensation sought.
- Permits the parties, by mutual agreement, to extend the time periods described in its provisions.
- Specifies that, if a claimant disputes all or part of an owner’s written response to the claim, or if the owner fails to respond to the claim within the required timeframe, the claimant may demand in writing an informal conference to meet and confer for settlement.
- Specifies that, upon receipt of a demand for an informal conference, the owner must schedule the meet and confer conference with the claimant within 30 days.
- Specifies that, within 10 days of the conclusion of the meet and confer conference, if the claim or any part thereof remains in dispute, the owner must provide the claimant a written statement identifying the portion that remains in dispute.
- Specifies that any remaining disputed claims after the informal conference must be submitted to nonbinding mediation, with the owner and the claimant sharing the costs equally. Requires the parties to mutually agree to a mediator within 10 business days after the remaining disputed portion of the claim has been identified in writing, and that, if the parties cannot agree on a mediator within this time period, the contractor may select the mediator.
- Specifies that, if mediation is unsuccessful, the remaining dispute shall be subject to the dispute resolution procedures in the written contract, or by final judgment or operation of law if no dispute resolution procedures exist in the contract.
- Specifies that an owner’s failure to respond to a claim within the time periods required, or to otherwise fail to meet the requirements of its provisions, shall result in the claim being deemed denied in its entirety. However, specifies that this denial shall not constitute an adverse finding with regard to the merits of any claim.
- Requires undisputed amounts of a claim to be paid within 60 days, and that undisputed amounts not paid in a timely manner will bear two percent interest per month. Specifies that disputed amounts found to be owed through the contract’s dispute resolution procedures or by final judgment or operation of law also shall bear interest at two percent per month.
- Specifies that, if a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against the owner because they do not have privity of contract with the owner, the contractor must present the claim to the owner on the subcontractor’s behalf. Permits a subcontractor to request in writing that the contractor present a claim for work that was performed by the subcontractor or lower tier subcontractor. Requires a subcontractor requesting their claim be furnished to the owner must furnish the contractor with timely and reasonable documentation to support the claim in order for the contractor to meet their obligations, and that the subcontractor must cooperate with the contractor in the informal conference, mediation, and dispute resolution processes required. Requires the contractor to exercise good faith in presenting the subcontractor’s claim, and prohibits the contractor from making any settlement of a claim to which the subcontractor does not approve. Requires the contractor to notify the subcontractor within 30 days of receiving their request to present their claim to the owner whether the contractor presented the claim and, if not, a statement why the contractor did not.
- Clarifies that the process in (13), above, does not preclude a subcontractor from exercising their lien rights and stop work notice rights.
- Provides that a contractor and subcontractor have the right to suspend performance of their work, without penalty, if the owner fails to make payment of the undisputed amounts due, until the payment is received if: the contractor or subcontractor informs the owner by registered or certified mail that an undisputed payment is past due; 30 days has passed since this notice of late payment is sent to the owner; and the contractor or subcontractor sends a 10-day written notice of intent to stop work.
- Specifies that any disputed amount which the owner agrees to pay, or which the owner is found to owe, shall, from the date of the agreement or finding, be considered an undisputed amount.
- Specifies that a contractor or subcontractor bringing a claim under its provisions bears the burden of proof, by a preponderance of the evidence, to demonstrate either:
- That any disputed claim was agreed upon by the owner, or any agent of the owner who was reasonably believed to have authority to amend the construction contract; or
- Any disputed claim was agreed upon by the project manager in the case of minor changes that are not inconsistent with the intent of the original construction contract.
- Specifies that a waiver of the rights provided by these provisions is void and contrary to public policy. Specifies that the parties may mutually agree to waive, in writing, the informal conference and mediation provisions and proceed directly to the commencement of a civil action or binding arbitration.
- Specifies that contractors, owners, and subcontractors may agree to reasonable change order, claim, and dispute resolution procedures and requirements in addition to these provisions as long as those contractual provisions do not conflict with or impair the timeframes and procedures provided.
- For the purposes of the bill’s provisions, defines the following terms:
- “Claim” to mean a separate and timely demand by a contractor, or, where authorized, sent by registered mail or certified mail with return receipt requested, for either of the following:
- a time extension, including, without limitation, for relief from damages or penalties for delay assessed by an owner under contract for a work of improvement or site improvement; or
- payment of additional compensation by an owner for approved changes to the contractor’s scope of work in connection with a work of improvement or site improvement, whether disputed or undisputed.
- “Owner” to mean an owner who causes a building, improvement, or structure to be constructed, altered, or repaired, or that person’s successor in interest at the date a notice of completion is recorded, whether the interest or estate of the owner be in fee, as vendee under a contract of purchase, as lessee, or other interest or estate less than the fee. Specifies that, where the interest or estate is held by two or more persons as joint tenants or tenants in common, any one or more of the cotenants may be deemed to be the “owner” within the meaning of this section.
- “Claim” to mean a separate and timely demand by a contractor, or, where authorized, sent by registered mail or certified mail with return receipt requested, for either of the following:
- Specifies that these provisions do apply to contracts entered into on or after January 1, 2026, and that these provisions are repealed as of January 1, 2030.
- Exempts from its provisions the construction of residential or multi-family dwellings, and Type V construction, as defined.
COMMENTS
- Author’s statement
According to the author:
SB 440 establishes a fair and timely payment process for construction change orders arising from contract modifications, adjustments in project scope, unplanned work requirements, contractual work revisions, construction adaptations and other similar types of routine changes that accompany construction projects. This process will prevent unjust and completely avoidable financial strains on small construction businesses and entrepreneurs. Without the protections inherent in SB 440’s process, many are pushed to the brink of bankruptcy. The need for reform is urgent, as the widespread abuse enabled by the absence of a clear change order process is not only prevalent but increasing across the industry.
Specifically, contractors and subcontractors often face extended payment delays for approved change orders, leading to financial instability, increased credit dependency, and, in extreme cases, business failure. Additionally, contractors bear financial and operational risks when required to perform additional work without clear payment guarantees. Power imbalances between the project owner, general contractor and subcontractor can create exploitive practices where subcontractors can be leveraged to reduce the value of their change order if they want to continue a future business relationship. All of this can, regrettably, lead to costly litigation, delaying project completion and increasing expenses for all parties.
SB 440 levels the playing field for contractors, especially subcontractors, by ensuring a fair change order process and providing for timely payments. This process reduces unnecessary hardship on lower-tier contractors, especially disadvantaged business enterprises, disabled veteran business enterprises, and small business enterprises.
The process established by SB 440 is based on AB 626 (Chiu) from 2016. AB 626 unanimously passed the Assembly and Senate.
- Public works of improvement
A “work of improvement” is work to construct, alter, repair, demolish, or remove buildings, bridges, and other structures, or to conduct work such as leveling, grading, or landscaping real property. (Civ. Code § 8050.) Residential or mixed-use and commercial projects can be a work of improvement. When a work of improvement is contracted for by a public entity, it is considered a public work of improvement, while all other works of improvement are private works of improvement. (Civ. Code §§ 8160, 9000.) Often, works of improvement are quite complex, as they require different tasks and types of construction work be completed for the same project, such as laying a building’s foundation, erecting the building’s frame, and installing electrical components. Thus, the owner of the project often contracts with direct contractors for the work, and direct contractors contract with subcontractors for completion of specific components of the project. Because subcontractors work under the direct contractor (or even another subcontractor), they do not have a contractual relationship with the owner.
Owners and direct contractors contracting for subcontract work often require the contractor or subcontractor to obtain a performance bond, which guarantees that the work contracted for will be performed. In a performance bond, the contractor obtains the bond from a surety, and if the contractor fails to perform the work contracted for, the surety will be responsible for ensuring the work is completed. While performance bonds are required in public works of improvement, they are not required for private works of improvement. In addition, owners also often require a retention from the contract amount for the project to ensure that the work contracted for is completed satisfactorily, which are specified amounts withheld from payments under the contract until the work is completed in order to ensure the work is completed as contracted.
Sometimes, a change to the work to be completed under a contract for work on a construction project must be made mid-way through the project. This could be because the owner determined that additional work is needed to complete the project, because different or additional materials are needed, or more time is needed to complete the project. When this happens, the parties agree to what is called a change order.
- The law relating to public works of improvement
Works of improvement typically include progress payments to the contractors involved as various stages of the work is being completed. California law requires that an owner of a private work of improvement pay a direct contractor a progress payment for the work completed within 30 days after the direct contractor demands the progress payment pursuant to the contract, unless the parties agree otherwise in writing. (Civ. Code § 8800.) If there is a good faith dispute between the owner and the direct contractor regarding the progress payment, the owner may withhold up to 150% of the disputed amount. An owner that violates those requirements or pays a direct contractor late is liable for a penalty of two percent per month of the amount of the payment wrongfully withheld.
If an owner or a direct contractor withholds a retention payment, California law also outlines specific requirements for that retention payment. When an owner withholds a retention from a direct contractor, the owner must pay the retention within 45 days after the completion of the work of improvement, unless there is a good faith dispute regarding the retention payment due. (Civ. Code § 8812.) If a direct contractor withholds a retention from a subcontractor, the direct contractor must pay the retention due to the subcontractor within 10 days after receiving all or part of a retention payment the direct contractor receives from the owner. (Civ. Code § 8814.) Like with progress payments, an owner or a direct contractor may withhold from a retention payment up to 150% of a disputed amount when a good faith dispute exists between the owner and direct contractor or the direct contractor and the subcontractor. When an owner or direct contractor does not make a retention payment within the timelines required, they are liable to the party to which the payment is owed for a penalty of two percent per month of the amount wrongfully withheld. (Civ. Code § 8818.) If the party due payment brings a civil action to collect the amount wrongfully withheld, the prevailing party is entitled to the costs of the action and their reasonable attorney’s fees.
Current law provides a number of remedies for when direct contractors and subcontractors and their employees are not paid. If the owner of a construction project does not pay a direct contractor the amount due to the written contract within 35 days after the date that the payment was due, and there is no dispute regarding the direct contractor’s satisfactory completion of the work, the direct contractor may cease work on the project. (Civ. Code § 8832.) To do so, the direct contractor must provide the owner with a stop work notice that states that the direct contractor will stop work if the amount owed is not paid within 10 days after the notice is given. (Civ. Code § 8830.) At least five days before giving the stop work notice, the contractor also must post a notice of their intent to give a stop work notice. If payment is not made within 10 days, the direct contractor giving the stop work notice, the direct contractor, their surety, or an owner may seek a judicial determination of liability for the amount due in an expedited proceeding in court. (Civ. Code §8844.) In addition to the stop work notice remedy, many private construction projects include payment bonds, which guarantee that subcontractors, suppliers, or workers will be paid for their work and materials. The payment bond is a financial guarantee on which the subcontractor or worker who is the beneficiary on the bond may file a claim with the surety for the payment guaranteed by the bond when they are not paid.
Every worker on a construction project also has a right to a mechanics’ lien on the property on which they worked. The mechanic’s lien is available to a direct contractor, subcontractor, material supplier, laborer, and others who provided work authorized for a work of improvement. (Civ. Code § 8400.) Unlike some of the above-described remedies, the mechanic’s lien is applicable not just when there is a written contract, but rather when work is provided at the request or agreement of the owner, or is provided or authorized by a direct contractor, subcontractor, or other person that has charge of all or part of the construction project. (Civ. Code § 8404.) A claimant may enforce the lien if they have first given notice, and have recorded a claim of lien on the property within a certain amount of time of ceasing work or completing the project. (Civ. Code §§ 8412-8414.) This tool allows the worker or contractor to obtain what they are owed for their work by placing the lien on the title of the property of the construction, and foreclosing on the lien to obtain payment.
In addition to the above-described remedies and tools for ensuring payment, contractors and subcontractors on any construction project always have standard contract law remedies available in order to recover what they are owed under the agreement through a civil action.
- SB 440 creates a process by which disputes regarding change orders may be resolved
The authors assert that the current process for private works of improvement projects is insufficient to ensure that direct contractors and subcontractors can be paid what they are owed when there are change orders on a project. According the author, this is because change orders are in addition to, or a change to, the original written contract. These change orders also may not be written themselves, and thus fall outside some of the statutory remedies like the stop work notice process or a claim upon the payment bond. They assert that, currently, contractors and subcontractors suffer financially because of long delays in payment for change orders, and that power inequities between the parties pushes subcontractors to negotiate for a fraction of their pay on change orders than they were due.
To address this, SB 440 creates a procedure through which parties in a private work of improvement can resolve a dispute regarding a time extension, including for relief from contractual damages or penalties for delay, and regarding payment of additional compensation for approved changes to the contractor’s scope of work. The process provided by SB 440 is similar to a dispute resolution process created for public works of improvement by AB 626 (Chiu, Ch. 810, Stats. 2016) in 2016.
Under SB 440’s process, a party may file a claim with the owner within 60 days of when the basis for the claim is discovered. The owner must review the claim within 30 days and provide a written statement identifying what portions of the claim are disputed and undisputed. Any undisputed portions of the claim, less any authorized retention, must be paid within 60 days after the owner issues its written statement. If the claimant disputes any part of the owner’s written response, or if the owner fails to respond to the claim, the claimant may demand an informal conference with the owner. The owner must schedule this informal conference within 30 days of the claimant requesting it, and the owner must provide a written statement of any remaining portion of the claim still in dispute within 10 days of the informal conference. SB 440 then provides that the parties must submit the remaining disputed claim to nonbinding mediation. The claimant and the owner must agree to a mediator within 10 business days after the remaining dispute is identified after the informal conference, but if the parties cannot agree to a mediator in that time, SB 440 provides that the direct contractor may select the mediator. If portions of the claim remain in dispute after mediation, the dispute can be resolved through the procedures in the parties’ written contract or as provided for in law.
SB 440 permits a contractor or subcontractor to suspend work without penalty if the owner fails to pay any undisputed amounts when due. However, it specifies that such suspension of work can only happen if the owner is informed by registered or certified mail, 30 days have passed since the notice of late payment is provided to the owner, and the contractor or subcontractor sends a 10-day written notice of intent to stop work.
SB 440 also provides a process by which a direct contractor can “pass through” a subcontractor’s claim directly to the owner. This process is important because subcontractors often do not have a contractual relationship with the owner, and thus cannot enforce payment upon the owner. SB 440 requires that, if a subcontractor lacks legal standing to assert a claim against an owner because they do not have privity of contract, the direct contractor must present the claim to the owner on behalf of the subcontractor. The subcontractor must request in writing that the contractor present their claim for work performed, and must furnish to the contractor timely and reasonable documentation to support their claim. The subcontractor then must go through the dispute resolution process under SB 440 with the contractor and the owner. SB 440 specifies that this process does not preclude a subcontractor from exercising its lien rights or stop work notice rights.
SB 440’s process would be a dispute resolution process, within specified time frames, to take place outside of a legal process. Its provisions may not be waived, except that the parties may mutually agree in writing to waive the informal conference and mediation procedures, and proceed directly to a civil action or binding arbitration upon receipt of a claim. If one of the parties does not agree to proceed directly to a civil action, the parties would be required to follow SB 440’s dispute resolution process first. However, SB 440 does permit owners, contractors, and subcontractors to agree to reasonable change order, claim, and dispute resolution procedures that are in addition to SB 440’s provisions, so long as they do not conflict with or impair the timelines and procedures in SB 440.
SB 440 would repeal its provisions on January 1, 2030.
SUPPORT
Southern California Association of Scaffold Contractors (sponsor)
American Subcontractors Association-California
California Association of Sheet Metal & Air Conditioning Contractors National Association
California Legislative Conference of Plumbing, Heating & Piping Industry
Finishing Contractors Association of Southern California
International Union of Operating Engineers, Cal-Nevada Conference
National Electrical Contractors Association (NECA)
Northern California Allied Trades
Northern California Floor Covering Association
Southern California Contractors Association
Southern California Glass Management Association (SCGMA)
United Contractors (UCON)
Wall and Ceiling Alliance
Western Painting and Coating Contractors Association
Western Wall and Ceiling Contractors Association (WWCCA)
OPPOSITION
None received
RELATED LEGISLATION
Pending Legislation: SB 61 (Cortese, 2025) prohibits an owner, direct contractor, or a subcontractor of a private work of improvement from withholding a retention payment from a direct contractor or subcontractor of more than five percent, except as specified. SB 61 is currently awaiting referral in the Assembly.
Prior Legislation:
AB 626 (Chiu, Ch., Stats. 2016) created a claim resolution process applicable to any claim by a contractor in connection with a public works project for a: a time extension for relief from damages or penalties for delay; payment of money or damages arising from work done pursuant to the contract for a public work; or payment of an amount disputed by the public entity, as specified. Required a public entity, excluding certain state entities, upon receipt of a claim to review it and, within 45 days, provide a written statement identifying the disputed and undisputed portions of the claim. Required any payment due on an undisputed portion of the claim to be processed within 60 days, as specified, and required that the claim be deemed rejected in its entirety if the public entity fails to issue the written statement. Authorized, if the claimant disputed the public entity’s written response or if the public entity failed to respond to a claim within the time prescribed, the claimant to demand to meet and confer for settlement of the issues in dispute, and required any disputed portion of the claim that remains in dispute after the meet and confer conference to be subject to nonbinding mediation, as specified. Provided that unpaid claim amounts accrue interest at 7% annually, and provided a procedure by which a subcontractor or lower tier contractor may make a claim through the contractor.
SB 189 (Lowenthal, Ch. 697, Stats. 2010) established the provisions related to retention payments in private works of improvement that specify the timelines for when retention payments must be paid, and the penalties for an owner or direct contractor’s violation of its provisions.
**************