SB 598: Public contracts: local water infrastructure projects: Construction Manager/General Contractor project delivery method.
- Session Year: 2025-2026
- House: Senate
- Latest Version Date: 2025-10-11
Current Status:
Passed
(2025-10-11: Chaptered by Secretary of State. Chapter 655, Statutes of 2025.)
Introduced
In Committee
Awaiting First Chamber Vote
Passed First Chamber
In Committee
Awaiting Second Chamber Vote
Passed Second Chamber
Enacted
Existing law defines the Construction Manager/General Contractor project delivery method (CM/GC method) as a project delivery method in which a construction manager is procured to provide preconstruction services during the design phase of a project and construction services during the construction phase of the project. Under existing law, the method allows the contract for construction services to be entered into at the same time as the contract for preconstruction services or at a later time. Existing law authorizes the Metropolitan Water District of Southern California to utilize the CM/GC method for regional recycled water projects or other water infrastructure projects under specified conditions. Pursuant to existing law, certain information required to be submitted as part of the CM/GC method is required to be verified under oath. Existing law makes the provisions described above pertaining to the CM/GC method effective only until January 1, 2028, and inoperative as of that date.
This bill would, until January 1, 2031, authorize a local agency, as defined, upon approval of its governing body, to similarly use the CM/GC method for a regional recycled water project or other water infrastructure project undertaken by the district to alleviate water supply shortages attributable to drought or climate change. The bill would require that authorization to apply to no more than 15 capital outlay projects for each local agency and would require a local agency to award a contract pursuant to the bill on a best value basis or to the lowest responsible bidder. Because the bill would expand the crime of perjury, it would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law defines the Construction Manager/General Contractor project delivery method (CM/GC method) as a project delivery method in which a construction manager is procured to provide preconstruction services during the design phase of a project and construction services during the construction phase of the project. Under existing law, the method allows the contract for construction services to be entered into at the same time as the contract for preconstruction services or at a later time. Existing law authorizes the Metropolitan Water District of Southern California to utilize the CM/GC method for regional recycled water projects or other water infrastructure projects under specified conditions. Pursuant to existing law, certain information required to be submitted as part of the CM/GC method is required to be verified under oath. Existing law makes the provisions described above pertaining to the CM/GC method effective only until January 1, 2028, and inoperative as of that date.
This bill would, until January 1, 2031, authorize a local agency, as defined, upon approval of its governing body, to similarly use the CM/GC method for a regional recycled water project or other water infrastructure project undertaken by the district to alleviate water supply shortages attributable to drought or climate change. The bill would require that authorization to apply to no more than 15 capital outlay projects for each local agency and would require a local agency to award a contract pursuant to the bill on a best value basis or to the lowest responsible bidder. Because the bill would expand the crime of perjury, it would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law defines the Construction Manager/General Contractor project delivery method (CM/GC method) as a project delivery method in which a construction manager is procured to provide preconstruction services during the design phase of a project and construction services during the construction phase of the project. Under existing law, the method allows the contract for construction services to be entered into at the same time as the contract for preconstruction services or at a later time. Existing law authorizes the Metropolitan Water District of Southern California to utilize the CM/GC method for regional recycled water projects or other water infrastructure projects under specified conditions. Pursuant to existing law, certain information required to be submitted as part of the CM/GC method is required to be verified under oath. Existing law makes the provisions described above pertaining to the CM/GC method effective only until January 1, 2028, and inoperative as of that date.
This bill would, until January 1, 2031, authorize a local agency, as defined, upon approval of its governing body, to similarly use the CM/GC method for a regional recycled water project or other water infrastructure project undertaken by the district to alleviate water supply shortages attributable to drought or climate change. The bill would require that authorization to apply to no more than 15 capital outlay projects for each local agency and would require a local agency to award a contract pursuant to the bill on a best value basis or to the lowest responsible bidder. Because the bill would expand the crime of perjury, it would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law defines the Construction Manager/General Contractor project delivery method (CM/GC method) as a project delivery method in which a construction manager is procured to provide preconstruction services during the design phase of a project and construction services during the construction phase of the project. Under existing law, the method allows the contract for construction services to be entered into at the same time as the contract for preconstruction services or at a later time. Existing law authorizes the Metropolitan Water District of Southern California to utilize the CM/GC method for regional recycled water projects or other water infrastructure projects under specified conditions. Pursuant to existing law, certain information required to be submitted as part of the CM/GC method is required to be verified under oath. Existing law makes the provisions described above pertaining to the CM/GC method effective only until January 1, 2028, and inoperative as of that date.
This bill would, until January 1, 2031, authorize a local agency, as defined, upon approval of its governing body, to similarly use the CM/GC method for a regional recycled water project or other water infrastructure project undertaken by the district to alleviate water supply shortages attributable to drought or climate change. Because the bill would expand the crime of perjury, it would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law, the Cortese-Knox-Hertzberg Local Government Reorganization Act of 2000, provides the exclusive authority and procedure for the initiation, conduct, and completion of changes of organization and reorganization for cities and districts, except as specified.This bill would make a nonsubstantive change to the provision naming the act.Existing law, the Cortese-Knox-Hertzberg Local Government Reorganization Act of 2000, provides the exclusive authority and procedure for the initiation, conduct, and completion of changes of organization and reorganization for cities and districts, except as specified.
This bill would make a nonsubstantive change to the provision naming the act.
As used in this chapter:
(a)Best value means a value determined by evaluation of objective criteria that relate to price, features, functions, life-cycle costs, experience, and past performance. A best value determination may involve the selection of the lowest cost proposal meeting the interests of the local agency and meeting the objectives of the project.
(b)Construction manager means a partnership, corporation, or other legal entity that is a licensed contractor pursuant to Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code and that is able to provide appropriately licensed contracting and engineering services as needed pursuant to a Construction Manager/General Contractor method contract.
(c)Construction Manager/General Contractor method means a project delivery method in which a construction manager is procured to provide preconstruction services during the design phase of the project and construction services during the construction phase of the project. The contract for construction services may be entered into at the same time as the contract for preconstruction services or at a later time. The execution of the design and the construction of the project may be in sequential phases or concurrent phases.
(d)Local agency means a city, county, city and county, or special district authorized by law to provide for the production, storage, supply, treatment, or distribution of any water from any source.
(e)Preconstruction services means advice during the design phase, including, but not limited to, scheduling, pricing, and phasing to assist the local agency to design a more constructible project.
(f)Project means a public work necessary for the construction of a recycled water facility or infrastructure designed specifically to alleviate water shortages attributable to drought, climate change, or other environmental factors.
22199.6.(a)Upon approval by its governing body, a local agency may use, in addition to other methods of project delivery otherwise allowable by law, the Construction Manager/General Contractor method of project delivery for a regional recycled water project or other water infrastructure project undertaken to alleviate water supply shortages attributable to drought or climate change. The local agency shall follow the procedures described in Sections 21568.5 to 21568.10, inclusive.
(b)The authorization under this section shall apply to no more than 15 capital outlay projects for each local agency.
(c)A local agency shall award a contract pursuant to this section on a best value basis or to the lowest responsible bidder.
(d)(1)The provisions of this chapter shall remain in effect only until January 1, 2031, and as of that date are inoperative.
(2)A contract awarded pursuant to this chapter before it becomes inoperative, but after Sections 21568.5 to 21568.10, inclusive, become inoperative pursuant to Section 21568.11, shall continue in full force and effect until completion, including any subsequently executed changes to the contract, or termination.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
As used in this chapter:
(a)Best value means a value determined by evaluation of objective criteria that relate to price, features, functions, life-cycle costs, experience, and past performance. A best value determination may involve the selection of the lowest cost proposal meeting the interests of the local agency and meeting the objectives of the project.
(b)Construction manager means a partnership, corporation, or other legal entity that is a licensed contractor pursuant to Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code and that is able to provide appropriately licensed contracting and engineering services as needed pursuant to a Construction Manager/General Contractor method contract.
(c)Construction Manager/General Contractor method means a project delivery method in which a construction manager is procured to provide preconstruction services during the design phase of the project and construction services during the construction phase of the project. The contract for construction services may be entered into at the same time as the contract for preconstruction services or at a later time. The execution of the design and the construction of the project may be in sequential phases or concurrent phases.
(d)Local agency means a city, county, city and county, or special district authorized by law to provide for the production, storage, supply, treatment, or distribution of any water from any source.
(e)Preconstruction services means advice during the design phase, including, but not limited to, scheduling, pricing, and phasing to assist the local agency to design a more constructible project.
(f)Project means a public work necessary for the construction of a recycled water facility or infrastructure designed specifically to alleviate water shortages attributable to drought, climate change, or other environmental factors.
22199.6.(a)Upon approval by its governing body, a local agency may use, in addition to other methods of project delivery otherwise allowable by law, the Construction Manager/General Contractor method of project delivery for a regional recycled water project or other water infrastructure project undertaken to alleviate water supply shortages attributable to drought or climate change. The local agency shall follow the procedures described in Sections 21568.5 to 21568.10, inclusive.
(b)The authorization under this section shall apply to no more than 15 capital outlay projects for each local agency.
(c)A local agency shall award a contract pursuant to this section on a best value basis or to the lowest responsible bidder.
(d)(1)The provisions of this chapter shall remain in effect only until January 1, 2031, and as of that date are inoperative.
(2)A contract awarded pursuant to this chapter before it becomes inoperative, but after Sections 21568.5 to 21568.10, inclusive, become inoperative pursuant to Section 21568.11, shall continue in full force and effect until completion, including any subsequently executed changes to the contract, or termination.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
As used in this chapter:
(a)Best value means a value determined by evaluation of objective criteria that relate to price, features, functions, life-cycle costs, experience, and past performance. A best value determination may involve the selection of the lowest cost proposal meeting the interests of the local agency and meeting the objectives of the project.
(b)Construction manager means a partnership, corporation, or other legal entity that is a licensed contractor pursuant to Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code and that is able to provide appropriately licensed contracting and engineering services as needed pursuant to a Construction Manager/General Contractor method contract.
(c)Construction Manager/General Contractor method means a project delivery method in which a construction manager is procured to provide preconstruction services during the design phase of the project and construction services during the construction phase of the project. The contract for construction services may be entered into at the same time as the contract for preconstruction services or at a later time. The execution of the design and the construction of the project may be in sequential phases or concurrent phases.
(d)Local agency means a city, county, city and county, or special district authorized by law to provide for the production, storage, supply, treatment, or distribution of any water from any source.
(e)Preconstruction services means advice during the design phase, including, but not limited to, scheduling, pricing, and phasing to assist the local agency to design a more constructible project.
(f)Project means a public work necessary for the construction of a recycled water facility or infrastructure designed specifically to alleviate water shortages attributable to drought, climate change, or other environmental factors.
22199.5.22199.6.(a)Upon approval by its governing body, a local agency may use, in addition to other methods of project delivery otherwise allowable by law, the Construction Manager/General Contractor method, as defined in subdivision (c) of Section 21568.2, method of project delivery for a regional recycled water project or other water infrastructure project undertaken to alleviate water supply shortages attributable to drought or climate change. The local agency shall follow the procedures described in Sections 21568.5 to 21568.10, inclusive, except that they shall not be required to complete the report described in subdivision (e) of Section 21568.5. inclusive.
(b)For purposes of this section, local agency means a city, county, city and county, or special district authorized by law to provide for the production, storage, supply, treatment, or distribution of any water from any source.(b)The authorization under this section shall apply to no more than 15 capital outlay projects for each local agency.
(c)A local agency shall award a contract pursuant to this section on a best value basis or to the lowest responsible bidder.
(c)(d)(1)The provisions of this chapter shall remain in effect only until January 1, 2031, and as of that date are inoperative.
(2)A contract awarded pursuant to this chapter before it becomes inoperative, but after Sections 21568.5 to 21568.10, inclusive, become inoperative pursuant to Section 21568.11, shall continue in full force and effect until completion, including any subsequently executed changes to the contract, or termination.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
(a)Upon approval by its governing body, a local agency may use, in addition to other methods of project delivery otherwise allowable by law, the Construction Manager/General Contractor method, as defined in subdivision (c) of Section 21568.2, of project delivery for a regional recycled water project or other water infrastructure project undertaken to alleviate water supply shortages attributable to drought or climate change. The local agency shall follow the procedures described in Sections 21568.5 to 21568.10, inclusive, except that they shall not be required to complete the report described in subdivision (e) of Section 21568.5.
(b)For purposes of this section, local agency means a city, county, city and county, or special district authorized by law to provide for the production, storage, supply, treatment, or distribution of any water from any source.
(c)(1)The provisions of this chapter shall remain in effect only until January 1, 2031, and as of that date are inoperative.
(2)A contract awarded pursuant to this chapter before it becomes inoperative, but after Sections 21568.5 to 21568.10, inclusive, become inoperative pursuant to Section 21568.11, shall continue in full force and effect until completion, including any subsequently executed changes to the contract, or termination.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
SECTION 1.Section 56000 of the Government Code is amended to read:56000.This division shall be known, and may be cited, as the Cortese-Knox-Hertzberg Local Government Reorganization Act of 2000.This division shall be known and may be cited known, and may be cited, as the Cortese-Knox-Hertzberg Local Government Reorganization Act of 2000.
|
Date
|
Status
|
|---|---|
| Oct 11, 2025 | Chaptered by Secretary of State. Chapter 655, Statutes of 2025. |
| Oct 11, 2025 | Approved by the Governor. |
| Sep 5, 2025 | Enrolled and presented to the Governor at 2 p.m. |
| Aug 29, 2025 | Assembly amendments concurred in. (Ayes 37. Noes 0. Page 2287.) Ordered to engrossing and enrolling. |
| Aug 27, 2025 | Ordered to special consent calendar. |
| Aug 21, 2025 | In Senate. Concurrence in Assembly amendments pending. |
| Aug 21, 2025 | Read third time. Passed. (Ayes 77. Noes 0. Page 2706.) Ordered to the Senate. |
| Jul 17, 2025 | Read second time. Ordered to consent calendar. |
| Jul 16, 2025 | From committee: Do pass. Ordered to consent calendar. (Ayes 13. Noes 0.) (July 16). |
| Jul 7, 2025 | Read second time and amended. Re-referred to Com. on APPR. |
| Jul 3, 2025 | From committee: Do pass as amended and re-refer to Com. on APPR. with recommendation: To consent calendar. (Ayes 10. Noes 0.) (July 2). |
| May 19, 2025 | Referred to Com. on L. GOV. |
| May 8, 2025 | In Assembly. Read first time. Held at Desk. |
| May 8, 2025 | Read third time. Passed. (Ayes 36. Noes 0. Page 1051.) Ordered to the Assembly. |
| May 6, 2025 | Read second time. Ordered to consent calendar. |
| May 5, 2025 | From committee: Be ordered to second reading pursuant to Senate Rule 28.8 and ordered to consent calendar. |
| Apr 25, 2025 | Set for hearing May 5. |
| Apr 23, 2025 | From committee: Do pass and re-refer to Com. on APPR. with recommendation: To consent calendar. (Ayes 7. Noes 0. Page 871.) (April 23). Re-referred to Com. on APPR. |
| Apr 4, 2025 | Set for hearing April 23. |
| Apr 2, 2025 | Re-referred to Com. on L. GOV. |
| Mar 24, 2025 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on RLS. |
| Mar 5, 2025 | Referred to Com. on RLS. |
| Feb 21, 2025 | From printer. May be acted upon on or after March 23. |
| Feb 20, 2025 | Introduced. Read first time. To Com. on RLS. for assignment. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Aug 29, 2025 | Special Consent SB598 Durazo | Senate Floor |
Passed |
|
| Aug 21, 2025 | SB 598 Durazo Consent Calendar Second Day Regular Session | Assembly Floor |
Passed |
|
| Jul 16, 2025 | Do pass. To Consent Calendar. | Assembly Standing Committee on Appropriations |
Passed |
|
| Jul 2, 2025 | Do pass as amended, and be re-referred to the Committee on [Appropriations] with recommendation: To Consent Calendar | Assembly Standing Committee on Local Government |
Passed |
|
| May 8, 2025 | Consent Calendar 2nd SB598 Durazo | Senate Floor |
Passed |
|
| Apr 23, 2025 | Do pass, but first be re-referred to the Committee on [Appropriations] with the recommendation: To Consent Calendar | Senate Standing Committee on Local Government |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| Association Of California Water Agencies | ** Support | |
| California Groundwater Coalition | ** Support | |
| California-Nevada Conference Of Operating Engineers | ** Support | |
| California State Council Of Laborers | ** Support | |
| City Of Vernon | ** Support | |
| District Council Of Iron Workers Of The State Of California And Vicinity | ** Support | |
| El Dorado Irrigation District | ** Support | |
| Los Angeles County Sanitation Districts | ** Support | |
| State Building & Construction Trades Council Of California | ** Support | |
| Stockton East Water District | ** Support | |
| Water Collaborative Delivery Association (Source) | ** Support |
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 598 |
UNFINISHED BUSINESS
Bill No: SB 598
Author: Durazo (D)
Amended: 7/7/25 in Assembly
Vote: 21
SENATE LOCAL GOVERNMENT COMMITTEE: 7-0, 4/23/25
AYES: Durazo, Choi, Arreguín, Cabaldon, Laird, Seyarto, Wiener
SENATE APPROPRIATIONS COMMITTEE: Senate Rule 28.8
SENATE FLOOR: 36-0, 5/8/25 (Consent)
AYES: Allen, Alvarado-Gil, Archuleta, Arreguín, Ashby, Becker, Blakespear, Cabaldon, Caballero, Cervantes, Choi, Cortese, Dahle, Durazo, Gonzalez, Grayson, Grove, Jones, Laird, Limón, McGuire, McNerney, Menjivar, Niello, Ochoa Bogh, Padilla, Pérez, Richardson, Seyarto, Smallwood-Cuevas, Stern, Strickland, Umberg, Wahab, Weber Pierson, Wiener
NO VOTE RECORDED: Hurtado, Reyes, Rubio, Valladares
ASSEMBLY FLOOR: 77-0, 8/21/25 (Consent) - See last page for vote
SUBJECT: Public contracts: local water infrastructure projects: Construction Manager/General Contractor project delivery method
SOURCE: Water Collaborative Delivery Association
DIGEST:
This bill authorizes a local agency to use the construction manager/general contractor (CM/GC) project delivery method for specified water infrastructure projects until January 1, 2031.
Assembly Amendments
of 7/7/25 limit the authority to no more than 15 capital outlay projects for each local agency.
ANALYSIS:
Existing law:
- Requires, pursuant to the Local Agency Public Construction Act, local agencies to invite bids for construction projects and award contracts to the lowest responsible bidder.
- Authorizes the Metropolitan Water District of Southern California to use CM/GC project delivery method, until January 1, 2028:
- CM/GC means project delivery method in which a construction manager is procured to provide preconstruction services during the design phase of the project and construction services during the construction phase of the project. The contract for construction services may be entered into at the same time as the contract for preconstruction services or at a later time. The execution of the design and the construction of the project may be in sequential phases or concurrent phases.
This bill:
- Authorizes, upon approval of its governing body, a local agency to use the CM/GC method of project delivery, as defined, for a regional recycled water project or other water infrastructure project undertaken to alleviate water supply shortages attributable to drought or climate change.
- Defines “local agency” to mean a city, county, city and county, or special district authorized by law to provide for the production, storage, supply, treatment, or distribution of any water from any source.
- Requires a local agency to follow the procedures specified in existing law for the use of CM/GC by the Metropolitan Water District of Southern California, which include, among other items, contracting procedures, the use of a skilled and trained workforce, and reporting requirements.
- Limits the authority under this bill to no more than 15 capital outlay projects for each local agency.
- Requires a local agency to award a contract pursuant to this authorization on a best value basis or to the lowest responsible bidder.
- Sunsets this bill’s provisions on January 1, 2031.
Background
Contracting. Local agencies typically use the traditional design-bid-build method for constructing public works. This approach splits construction projects into two distinct phases: design and construction. During the design phase, the local agency prepares detailed project plans and specifications using its own employees or by hiring outside architects and engineers. Once project designs are complete, local agencies invite bids from the construction community and award the contract to the lowest responsible bidder. Over the last couple of decades, legislators have gradually expanded local agencies’ authority to procure construction projects using various alternatives to the design-bid-build project delivery method.
CM/GC. The CM/GC project-delivery method allows an agency to engage a construction manager during the design process to provide assistance to the design team, which can ultimately lead to a more constructible project. When design is nearly complete, the agency and the construction manager negotiate a guaranteed maximum price for the construction of the project based on the defined scope and schedule. If this price is acceptable to both parties, they execute a contract for construction services, and the construction manager becomes the general contractor. CM/GC can lead to less costly or more expediently delivered projects because of the construction manager’s involvement in the design process.
Comments
Purpose of this bill. According to the author, “I have worked my entire life to make California more equitable. Now, in the midst of a seismic change in our economy, we cannot afford to make the same mistakes of the past. A commitment to climate means a commitment to workers. We must take bold steps to modernize and fortify our water infrastructure to prepare for the intensifying challenges of climate change. SB 598 provides a practical, cost-effective pathway for achieving this goal by allowing local agencies to leverage CM/GC’s advantages in project planning and execution. My bill ensures that water infrastructure projects utilize a highly skilled, trained workforce, reinforcing California’s commitment to strong labor standards.”
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
According to the Assembly Appropriations Committee, no state costs.
SUPPORT: (Verified 8/22/25)
Water Collaborative Delivery Association (Source)
Association of California Water Agencies
Calfornia-Nevada Conference of Operating Engineers
California Groundwater Coalition
California State Council of Laborers
City of Vernon
District Council of Iron Workers of the State of California and Vicinity
El Dorado Irrigation District
Los Angeles County Sanitation Districts
State Building & Construction Trades Council of California
Stockton East Water District
OPPOSITION: (Verified 8/22/25)
None received
ASSEMBLY FLOOR: 77-0, 8/21/25
AYES: Aguiar-Curry, Ahrens, Alanis, Alvarez, Arambula, Ávila Farías, Bains, Bauer-Kahan, Bennett, Berman, Boerner, Bonta, Bryan, Calderon, Caloza, Carrillo, Castillo, Chen, Connolly, Davies, DeMaio, Dixon, Elhawary, Ellis, Flora, Fong, Gabriel, Gallagher, Garcia, Gipson, Jeff Gonzalez, Mark González, Hadwick, Haney, Harabedian, Hart, Hoover, Irwin, Jackson, Kalra, Krell, Lackey, Lee, Lowenthal, Macedo, McKinnor, Muratsuchi, Nguyen, Ortega, Pacheco, Papan, Patel, Patterson, Pellerin, Petrie-Norris, Quirk-Silva, Ramos, Celeste Rodriguez, Michelle Rodriguez, Rogers, Blanca Rubio, Sanchez, Schiavo, Schultz, Sharp-Collins, Solache, Soria, Stefani, Ta, Tangipa, Valencia, Wallis, Ward, Wicks, Wilson, Zbur, Rivas
NO VOTE RECORDED: Addis, Ransom
Prepared by: Itzel Vargas / L. GOV. / (916) 651-4119
8/25/25 11:49:48
**** END ****
Date of Hearing: July 16, 2025
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Buffy Wicks, Chair
SBPCA Bill Id:SB 598
Author:(Durazo) – As Amended Ver:July 7, 2025
Policy Committee: | Local Government | Vote: | 10 - 0 |
|
| ||
|
|
Urgency: No State Mandated Local Program: Yes Reimbursable: No
SUMMARY:
This bill authorizes a local agency to use the construction manager/general contractor (CM/GC) project delivery method for specified water infrastructure projects until January 1, 2031.
Specifically, this bill:
- Authorizes, upon approval of its governing body, a local agency to use the CM/GC method of project delivery, as defined, for a regional recycled water project or other water infrastructure project undertaken to alleviate water supply shortages attributable to drought or climate change.
- Defines “local agency” to mean a city, county, city and county, or special district authorized by law to provide for the production, storage, supply, treatment, or distribution of any water from any source.
- Requires a local agency to follow the procedures specified in existing law for the use of CM/GC by the Metropolitan Water District of Southern California (MWD), which include, among other items, contracting procedures, the use of a skilled and trained workforce, and reporting requirements.
- Limits the authority under this bill to no more than 15 capital outlay projects for each local agency.
- Requires a local agency to award a contract pursuant to this authorization on a best value basis or to the lowest responsible bidder.
- Sunsets the bill’s provisions on January 1, 2031.
FISCAL EFFECT:
No state costs.
COMMENTS:
- Purpose. According to the author:
I have worked my entire life to make California more equitable. Now, in the midst of a seismic change in our economy, we cannot afford to make the same mistakes of the past. A commitment to climate means a commitment to workers as we take bold steps to modernize and fortify our water infrastructure to prepare for the intensifying challenges of climate change.
[This bill] provides a practical, cost-effective pathway for achieving this goal by allowing local agencies to leverage CM/GC’s advantages in project planning and execution. My bill ensures that water infrastructure projects utilize a highly skilled, trained workforce, reinforcing California’s commitment to strong labor standards.
This bill is sponsored by the Water Collaborative Delivery Association and is supported by various water-related districts and labor organizations. There is no registered opposition.
- Background. The Local Agency Public Construction Act generally requires local agencies use the traditional design-bid-build method for constructing public works. Under this process, a public agency fully completes the design of a project prior to awarding a construction contract and must award the contract to the “lowest responsible bidder.” This process is to ensure the project is built for the lowest possible cost. However, critics of the traditional design-bid-build method claim this method can be inefficient and costly, delaying the implementation of urgently needed projects.
Existing law authorizes various state and local entities to use certain project delivery methods, including design-build, design-sequencing, and CM/GC, as alternatives to the traditional design-bid-build method for certain projects. For example, existing law authorizes MWD to utilize the CM/GC method for regional recycled water projects or other water infrastructure projects under specified conditions until January 1, 2028 (AB 1845 (Calderon), Chapter 275, Statutes of 2022).
The CM/GC project-delivery method allows an agency to engage a construction manager during the design process to provide assistance to the design team. The agency selects the construction manager on the basis of qualifications, past experience, or a best-value basis. When design is nearly complete, the agency and the construction manager negotiate a guaranteed maximum price for the construction of the project. If this price is acceptable to both parties, they execute a contract and the construction manager becomes the general contractor. Because the contractor is familiar with the project design during the construction phase, the CM/GC method may result in reduced overall project costs and more expedient project delivery.
This bill, similar to the authorization for MWD, authorizes cities, counties, and water districts, upon approval of the governing body, to use the CM/GC method for a regional recycled water project or other water infrastructure projects undertaken to alleviate water supply shortages attributable to drought or climate change. The bill requires a local agency to follow the contracting procedures in existing law for MWD and contains a sunset date of January 1, 2031.
Analysis Prepared by: Jennifer Swenson / APPR. / (916) 319-2081
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 598 |
CONSENT
Bill No: SB 598
Author: Durazo (D)
Amended: 3/24/25
Vote: 21
SENATE LOCAL GOVERNMENT COMMITTEE: 7-0, 4/23/25
AYES: Durazo, Choi, Arreguín, Cabaldon, Laird, Seyarto, Wiener
SENATE APPROPRIATIONS COMMITTEE: Senate Rule 28.8
SUBJECT: Public contracts: local water infrastructure projects: Construction Manager/General Contractor project delivery method
SOURCE: Water Collaborative Delivery Association
DIGEST:
This bill allows local agencies to use construction manager/general contractor project delivery method on local water infrastructure projects.
ANALYSIS:
Existing law:
- Requires, pursuant to the Local Agency Public Construction Act, local agencies to invite bids for construction projects and award contracts to the lowest responsible bidder.
- Authorizes the Metropolitan Water District of Southern California currently has the authority to use Construction Manager/General Contractor (CM/GC) project delivery method, until January 1, 2028:
- CM/GC means project delivery method in which a construction manager is procured to provide preconstruction services during the design phase of the project and construction services during the construction phase of the project. The contract for construction services may be entered into at the same time as the contract for preconstruction services or at a later time. The execution of the design and the construction of the project may be in sequential phases or concurrent phases.
This bill:
- Allows for local agencies that provide for the production, storage, supply, treatment, or distribution of water to use CM/GC project delivery method for projects.
- Outlines specific procedures for local agencies to use CM/GC, and requires them to award these contracts on a best value or qualifications basis, or to the lowest responsible bidder.
- Requires local agencies to do the following:
- Establish a procedure for the evaluation and selection of a construction manager by developing a request for qualifications (RFQ) that includes specified information on the project and the bidder.
- For each RFQ, the local agency must generate a final list of qualified persons or firms before it can enter into contract negotiations. For each contract in the RFQ, the local agency must enter into negotiations for the contract with the highest qualified person or firm on the final list. If the RFQ is for multiple contracts, there can be a single negotiation for all the contracts. When making its decision, the local agency must take into account the value, scope, complexity, and nature of the services the entity will render.
- If negotiations are unsuccessful, the local agency can move onto the next most qualified person or firm.
- If a contract is entered into, and includes preconstruction services, the local agency must enter into a written contract with the CM for these preconstruction services under which the district pays the CM an agreed upon fee. The preconstruction services can include fees for services to be performed during the construction contract, but the district must not request or a obtain a fixed or guaranteed maximum price for the construction contract until after it has entered into a preconstruction services contract, which provides for subsequent negotiation of any or all phases of the project.
- A local agency must award a construction contract after the plans have been sufficiently developed and either a fixed or guaranteed maximum price has been successfully negotiated. If negotiations are unsuccessful, it must not enter into the contract and is not required to enter into a construction contract. Construction must not commence until the local agency and the CM agree to a fixed or guaranteed maximum price.
- Includes other provisions that govern this type of contracts, this bill authorizes:
- Requires local agencies to develop guidelines for a conflict-of-interest policy;
- Requires that an enforceable commitment that the entity will use a skilled-and-trained workforce for all work on a project, unless the local agency has entered into a project labor agreement that requires the use of such a workforce;
- Requires local agencies to perform construction inspection services for all projects, and use district employees to the fullest extent possible, and contract for any remaining work;
- Provides that retention proceeds local agencies withhold must not exceed 5% of project costs if it requires a performance and payment bond issued by an admitted surety insurer;
- Sunsets the authority for local agencies to use CM/GC on January 1, 2031.
- Sunset date does not affect contracts already entered into, including any subsequent changes or terminations of those contracts.
Background
Contracting. Local agencies typically use the traditional design-bid-build method for constructing public works. This approach splits construction projects into two distinct phases: design and construction. During the design phase, the local agency prepares detailed project plans and specifications using its own employees or by hiring outside architects and engineers. Once project designs are complete, local agencies invite bids from the construction community and award the contract to the lowest responsible bidder. Over the last couple of decades, legislators have gradually expanded local agencies’ authority to procure construction projects using various alternatives to the design-bid-build project delivery method.
Construction Manager/General Contractor. The CM/GC project-delivery method allows an agency to engage a construction manager during the design process to provide assistance to the design team, which can ultimately lead to a more constructible project. When design is nearly complete, the agency and the construction manager negotiate a guaranteed maximum price for the construction of the project based on the defined scope and schedule. If this price is acceptable to both parties, they execute a contract for construction services, and the construction manager becomes the general contractor. CM/GC can lead to less costly or more expediently delivered projects because of the construction manager’s involvement in the design process.
Comments
Purpose of the bill. According to the author, “I have worked my entire life to make California more equitable. Now, in the midst of a seismic change in our economy, we cannot afford to make the same mistakes of the past. A commitment to climate means a commitment to workers. We must take bold steps to modernize and fortify our water infrastructure to prepare for the intensifying challenges of climate change. SB 598 provides a practical, cost-effective pathway for achieving this goal by allowing local agencies to leverage CM/GC’s advantages in project planning and execution. My bill ensures that water infrastructure projects utilize a highly skilled, trained workforce, reinforcing California’s commitment to strong labor standards.”
Risky business. All procurement methods contain some element of risk. Most commonly, local agencies using the lowest bidder for highly complicated projects can sometimes lead local agencies to sacrifices in quality or significant change orders. Also, when methods require a different firm for design and construction, there can be inconsistencies between the two firms, leading to additional costs and delays. CM/GC tries to solve this problem by having the construction manager’s involvement in the design process, which can help expedite delivery or allow for collaborative problem solving. However, since local agencies in California have limited experience with CM/GC, there is some additional risk to using this new procurement method. For example, this method may limit competition for bids, potentially allowing a construction manager to convince a local agency, and by extension, its constituents, to pay a higher price than the local agency initially intended. SB 598 attempts to mitigate the risk of overpaying in a few ways. For one, SB 598 includes provisions that allow local agencies to move on to other entities if the agency does not agree on a contract with the design entity. This gives a local agency the option to compare bids for the project and see if a lower price is available. Also, SB 598 has a sunset provision that makes local agencies come back to the Legislature to continue using the contract authority. This provision allows the Legislature to exercise oversight over the contracting authority and therefore may encourage local agencies to exercise caution when using it. The Committee may wish to consider if SB 598 has sufficient protections to mitigate any potential risks of the CM/GC project-delivery method.
Related/Prior Legislation
SB 991 (Newman, Chapter 243, Statutes of 2022) authorizes, until January 1, 2029, specified local agencies that provide for the production, storage, supply, treatment, or distribution of any water from any source, to use the progressive design-build process for public works projects in excess of $5 million.
AB 1845 (Calderon, Chapter 275, Statutes of 2022) authorizes, until January 1, 2027, Metropolitan Water District to use CM/GC contracting authority for public works projects.
SB 626 (Dodd, Chapter 247, Statutes of 2021) authorizes, until January 1, 2033, the Department of Water Resources to use the design-build and CM/GC project delivery methods for facilities of the State Water Project, excluding through Delta conveyance, as specified
SB 1262 (Beall, Chapter 465, Statutes of 2018) eliminated the restriction on the number of projects Caltrans can procure through the CM/GC procurement method.
AB 1171 (Linder, Chapter 413, Statutes of 2015) authorizes regional transportation agencies (RTAs) to use CM/GC contracts, under limited circumstances.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
SUPPORT: (Verified 5/5/25)
Water Collaborative Delivery Association (Source)
California-Nevada Conference of Operating Engineers
California State Council of Laborers
District Council of Iron Workers of the State of California and Vicinity
Los Angeles County Sanitation Districts
State Building & Construction Trades Council of California
OPPOSITION: (Verified 5/5/25)
None received
Prepared by: Itzel Vargas / L. GOV. / (916) 651-4119
5/7/25 16:05:30
**** END ****
SENATE COMMITTEE ON LOCAL GOVERNMENT
Senator María Elena Durazo, Chair
2025 - 2026 Regular
Revised
Bill No: | SB 598 | Hearing Date: | 4/23/25 |
Author: | Durazo | Fiscal: | Yes |
Version: | 3/24/25 | Consultant: | Vargas |
Public contracts: local water infrastructure projects: Construction Manager/General Contractor project delivery method
Allows local agencies to use construction manager/general contractor project delivery method on local water infrastructure projects.
Background
Contracting. The Local Agency Public Construction Act generally requires local agencies to invite bids for construction projects and award contracts to the lowest responsible bidder. Local agencies typically use the traditional design-bid-build method for constructing public works. This approach splits construction projects into two distinct phases: design and construction. During the design phase, the local agency prepares detailed project plans and specifications using its own employees or by hiring outside architects and engineers. Once project designs are complete, local agencies invite bids from the construction community and award the contract to the lowest responsible bidder. Over the last couple of decades, legislators have gradually expanded local agencies’ authority to procure construction projects using various alternatives to the design-bid-build project delivery method.
Construction Manager/General Contractor (CM/GC). The CM/GC project-delivery method allows an agency to engage a construction manager during the design process to provide assistance to the design team, which can ultimately lead to a more constructible project. When design is nearly complete, the agency and the construction manager negotiate a guaranteed maximum price for the construction of the project based on the defined scope and schedule. If this price is acceptable to both parties, they execute a contract for construction services, and the construction manager becomes the general contractor. CM/GC can lead to less costly or more expediently delivered projects because of the construction manager’s involvement in the design process.
The Water Collaborative Delivery Association (WCDA) wants local agencies to have the authority to use CM/GC project-delivery method for water infrastructure projects.
Proposed Law
Senate Bill 598 allows, until January 1, 2031, local agencies that provide for the production, storage, supply, treatment, or distribution of water to use CM/GC project-delivery method for their projects.
SB 598 sets out specific procedures to use CM/GC and requires local agencies to award these contracts on a best value or qualifications basis, or to the lowest responsible bidder.
To use CM/GC, local agencies must establish a procedure for the evaluation and selection of a construction manager (CM) by developing a request for qualifications (RFQ) that includes at least the following:
- Information on the owners of the entity, their experience, credentials and licenses, and safety record;
- Evidence that establishes the design-build entity’s capacity to obtain requirement payment and performance bonding, liability insurance, and errors and omission insurance;
- Any prior serious or willful violations of state and federal occupational safety laws settled against any manager of the CM, and information concerning workers’ compensation experience and worker safety programs; and
- Information concerning instances of previous construction contract violations, license violations, bankruptcies, defaults, and other claims, disputes, and lawsuits.
For each RFQ, the local agency must generate a final list of qualified persons or firms before it can enter into contract negotiations. For each contract in the RFQ, the local agency must enter into negotiations for the contract with the highest qualified person or firm on the final list. If the RFQ is for multiple contracts, there can be a single negotiation for all the contracts. When making its decision, the local agency must take into account the value, scope, complexity, and nature of the services the entity will render. If negotiations are unsuccessful, the local agency can move onto the next most qualified person or firm.
If a contract is entered into, and includes preconstruction services, the local agency must enter into a written contract with the CM for these preconstruction services under which the district pays the CM an agreed upon fee. The preconstruction services can include fees for services to be performed during the construction contract, but the district must not request or a obtain a fixed or guaranteed maximum price for the construction contract until after it has entered into a preconstruction services contract, which provides for subsequent negotiation of any or all phases of the project.
A local agency must award a construction contract after the plans have been sufficiently developed and either a fixed or guaranteed maximum price has been successfully negotiated. If negotiations are unsuccessful, it must not enter into the contract and is not required to enter into a construction contract. Construction must not commence until the local agency and the CM agree to a fixed or guaranteed maximum price.
SB 598 also includes other provisions that govern the contracting process the bill authorizes, including that:
- The local agency must develop guidelines for a conflict-of-interest policy;
- The contractor must provide an enforceable commitment that it will use a skilled-and-trained workforce for all work on a project, unless the local agency has entered into a project labor agreement that requires the use of such a workforce;
- The local agency must perform construction inspection services for all projects, and use district employees to the fullest extent possible, and contract for any remaining work; and
- The local agency cannot withhold more than 5% of the cost of the contract as an incentive to guarantee performance by the contractor.
The authority for local agencies to use CM/GC delivery-method sunsets on January 1, 2031. The sunset date does not affect contracts already entered into, including any subsequent changes or terminations of those contracts.
Comments
1. Purpose of the bill. According to the author, “I have worked my entire life to make California more equitable. Now, in the midst of a seismic change in our economy, we cannot afford to make the same mistakes of the past. A commitment to climate means a commitment to workers. We must take bold steps to modernize and fortify our water infrastructure to prepare for the intensifying challenges of climate change. SB 598 provides a practical, cost-effective pathway for achieving this goal by allowing local agencies to leverage CM/GC’s advantages in project planning and execution. My bill ensures that water infrastructure projects utilize a highly skilled, trained workforce, reinforcing California’s commitment to strong labor standards.”
2. Risky business. All procurement methods contain some element of risk. Most commonly, local agencies using the lowest bidder for highly complicated projects can sometimes lead local agencies to sacrifices in quality or significant change orders. Also, when methods require a different firm for design and construction, there can be inconsistencies between the two firms, leading to additional costs and delays. CM/GC tries to solve this problem by having the construction manager’s involvement in the design process, which can help expedite delivery or allow for collaborative problem solving. However, since local agencies in California have limited experience with CM/GC, there is some additional risk to using this new procurement method. For example, this method may limit competition for bids, potentially allowing a construction manager to convince a local agency, and by extension, its constituents, to pay a higher price than the local agency initially intended. SB 598 attempts to mitigate the risk of overpaying in a few ways. For one, SB 598 includes provisions that allow local agencies to move on to other entities if the agency does not agree on a contract with the design entity. This gives a local agency the option to compare bids for the project and see if a lower price is available. Also, SB 598 has a sunset provision that makes local agencies come back to the Legislature to continue using the contract authority. This provision allows the Legislature to exercise oversight over the contracting authority and therefore may encourage local agencies to exercise caution when using it. The Committee may wish to consider if SB 598 has sufficient protections to mitigate any potential risks of the CM/GC project-delivery method.
3. Previous legislation. The Legislature recently has seen these other changes to contracting authority related to CM/GC or water projects:
- SB 991 (Newman, 2022) authorizes, until January 1, 2029, specified local agencies that provide for the production, storage, supply, treatment, or distribution of any water from any source, to use the progressive design-build process for public works projects in excess of $5,000,000.
- AB 1845 (Calderon, 2022) authorizes, until January 1, 2027, Metropolitan Water District to use CM/GC contracting authority for public works projects.
- SB 626 (Dodd, 2021) authorizes, until January 1, 2033, the Department of Water Resources to use the design-build and CM/GC project delivery methods for facilities of the State Water Project, excluding through Delta conveyance, as specified
- SB 1262 (Beall, 2018) eliminated the restriction on the number of projects Caltrans can procure through the CM/GC procurement method.
- AB 1171 (Linder, 2015) authorizes regional transportation agencies (RTAs) to use CM/GC contracts, under limited circumstances.
Support and Opposition
(4/18/2025)
Support: Water Collaborative Delivery Association (Sponsor)
California-Nevada Conference of Operating Engineers
California State Council of Laborers
District Council of Iron Workers of the State of California and Vicinity
Los Angeles County Sanitation Districts
State Building & Construction Trades Council of California
Opposition: None Submitted
-- END --
SENATE COMMITTEE ON LOCAL GOVERNMENT
Senator María Elena Durazo, Chair
2025 - 2026 Regular
Bill No: | SB 598 | Hearing Date: | 4/23/25 |
Author: | Durazo | Fiscal: | Yes |
Version: | 3/24/25 | Consultant: | Vargas |
Public contracts: local water infrastructure projects: Construction Manager/General Contractor project delivery method
Allows local agencies to use construction manager/general contractor project delivery method on local water infrastructure projects.
Background
Contracting. The Local Agency Public Construction Act generally requires local agencies to invite bids for construction projects and award contracts to the lowest responsible bidder. Local agencies typically use the traditional design-bid-build method for constructing public works. This approach splits construction projects into two distinct phases: design and construction. During the design phase, the local agency prepares detailed project plans and specifications using its own employees or by hiring outside architects and engineers. Once project designs are complete, local agencies invite bids from the construction community and award the contract to the lowest responsible bidder. Over the last couple of decades, legislators have gradually expanded local agencies’ authority to procure construction projects using various alternatives to the design-bid-build project delivery method.
Construction Manager/General Contractor (CM/GC). The CM/GC project-delivery method allows an agency to engage a construction manager during the design process to provide assistance to the design team, which can ultimately lead to a more constructible project. When design is nearly complete, the agency and the construction manager negotiate a guaranteed maximum price for the construction of the project based on the defined scope and schedule. If this price is acceptable to both parties, they execute a contract for construction services, and the construction manager becomes the general contractor. CM/GC can lead to less costly or more expediently delivered projects because of the construction manager’s involvement in the design process.
The Water Collaborative Delivery Association (WCDA) wants local agencies to have the authority to use CM/GC project-delivery method for water infrastructure projects.
Proposed Law
Senate Bill 598 allows, until January 1, 2032, local agencies that provide for the production, storage, supply, treatment, or distribution of water to use CM/GC project-delivery method for their projects.
SB 598 sets out specific procedures to use CM/GC and requires local agencies to award these contracts on a best value or qualifications basis, or to the lowest responsible bidder.
To use CM/GC, local agencies must establish a procedure for the evaluation and selection of a construction manager (CM) by developing a request for qualifications (RFQ) that includes at least the following:
- Information on the owners of the entity, their experience, credentials and licenses, and safety record;
- Evidence that establishes the design-build entity’s capacity to obtain requirement payment and performance bonding, liability insurance, and errors and omission insurance;
- Any prior serious or willful violations of state and federal occupational safety laws settled against any manager of the CM, and information concerning workers’ compensation experience and worker safety programs; and
- Information concerning instances of previous construction contract violations, license violations, bankruptcies, defaults, and other claims, disputes, and lawsuits.
For each RFQ, the local agency must generate a final list of qualified persons or firms before it can enter into contract negotiations. For each contract in the RFQ, the local agency must enter into negotiations for the contract with the highest qualified person or firm on the final list. If the RFQ is for multiple contracts, there can be a single negotiation for all the contracts. When making its decision, the local agency must take into account the value, scope, complexity, and nature of the services the entity will render. If negotiations are unsuccessful, the local agency can move onto the next most qualified person or firm.
If a contract is entered into, and includes preconstruction services, the local agency must enter into a written contract with the CM for these preconstruction services under which the district pays the CM an agreed upon fee. The preconstruction services can include fees for services to be performed during the construction contract, but the district must not request or a obtain a fixed or guaranteed maximum price for the construction contract until after it has entered into a preconstruction services contract, which provides for subsequent negotiation of any or all phases of the project.
A local agency must award a construction contract after the plans have been sufficiently developed and either a fixed or guaranteed maximum price has been successfully negotiated. If negotiations are unsuccessful, it must not enter into the contract and is not required to enter into a construction contract. Construction must not commence until the local agency and the CM agree to a fixed or guaranteed maximum price.
SB 598 also includes other provisions that govern the contracting process the bill authorizes, including that:
- The local agency must develop guidelines for a conflict-of-interest policy;
- The contractor must provide an enforceable commitment that it will use a skilled-and-trained workforce for all work on a project, unless the local agency has entered into a project labor agreement that requires the use of such a workforce;
- The local agency must perform construction inspection services for all projects, and use district employees to the fullest extent possible, and contract for any remaining work; and
- The local agency cannot withhold more than 5% of the cost of the contract as an incentive to guarantee performance by the contractor.
The authority for local agencies to use CM/GC delivery-method sunsets on January 1, 2032. The sunset date does not affect contracts already entered into, including any subsequent changes or terminations of those contracts.
Comments
1. Purpose of the bill. According to the author, “I have worked my entire life to make California more equitable. Now, in the midst of a seismic change in our economy, we cannot afford to make the same mistakes of the past. A commitment to climate means a commitment to workers. We must take bold steps to modernize and fortify our water infrastructure to prepare for the intensifying challenges of climate change. SB 598 provides a practical, cost-effective pathway for achieving this goal by allowing local agencies to leverage CM/GC’s advantages in project planning and execution. My bill ensures that water infrastructure projects utilize a highly skilled, trained workforce, reinforcing California’s commitment to strong labor standards.”
2. Risky business. All procurement methods contain some element of risk. Most commonly, local agencies using the lowest bidder for highly complicated projects can sometimes lead local agencies to sacrifices in quality or significant change orders. Also, when methods require a different firm for design and construction, there can be inconsistencies between the two firms, leading to additional costs and delays. CM/GC tries to solve this problem by having the construction manager’s involvement in the design process, which can help expedite delivery or allow for collaborative problem solving. However, since local agencies in California have limited experience with CM/GC, there is some additional risk to using this new procurement method. For example, this method may limit competition for bids, potentially allowing a construction manager to convince a local agency, and by extension, its constituents, to pay a higher price than the local agency initially intended. SB 598 attempts to mitigate the risk of overpaying in a few ways. For one, SB 598 includes provisions that allow local agencies to move on to other entities if the agency does not agree on a contract with the design entity. This gives a local agency the option to compare bids for the project and see if a lower price is available. Also, SB 598 has a sunset provision that makes local agencies come back to the Legislature to continue using the contract authority. This provision allows the Legislature to exercise oversight over the contracting authority and therefore may encourage local agencies to exercise caution when using it. The Committee may wish to consider if SB 598 has sufficient protections to mitigate any potential risks of the CM/GC project-delivery method.
3. Previous legislation. The Legislature recently has seen these other changes to contracting authority related to CM/GC or water projects:
- SB 991 (Newman, 2022) authorizes, until January 1, 2029, specified local agencies that provide for the production, storage, supply, treatment, or distribution of any water from any source, to use the progressive design-build process for public works projects in excess of $5,000,000.
- AB 1845 (Calderon, 2022) authorizes, until January 1, 2027, Metropolitan Water District to use CM/GC contracting authority for public works projects.
- SB 626 (Dodd, 2021) authorizes, until January 1, 2033, the Department of Water Resources to use the design-build and CM/GC project delivery methods for facilities of the State Water Project, excluding through Delta conveyance, as specified
- SB 1262 (Beall, 2018) eliminated the restriction on the number of projects Caltrans can procure through the CM/GC procurement method.
- AB 1171 (Linder, 2015) authorizes regional transportation agencies (RTAs) to use CM/GC contracts, under limited circumstances.
Support and Opposition
(4/18/2025)
Support: Water Collaborative Delivery Association (Sponsor)
California-Nevada Conference of Operating Engineers
California State Council of Laborers
District Council of Iron Workers of the State of California and Vicinity
Los Angeles County Sanitation Districts
State Building & Construction Trades Council of California
Opposition: None Submitted
-- END --