SB 886: California Technology Innovation and Ratepayer Protection Act.
- Session Year: 2025-2026
- House: Senate
- Latest Version Date: 2026-09-21
Current Status:
Passed
(2026-09-21: Chaptered by Secretary of State. Chapter 438, Statutes of 2026.)
Introduced
In Committee
Awaiting First Chamber Vote
Passed First Chamber
In Committee
Awaiting Second Chamber Vote
Passed Second Chamber
Enacted
Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations. Existing law authorizes the commission to fix the rates and charges for every public utility and requires that those rates and charges be just and reasonable.
This bill, the California Technology Innovation and Ratepayer Protection Act, would require the commission, on or before January 1, 2028, to establish new tariffs or update existing electric rules for the interconnection of participating customer facilities and the provision of retail electric service, transmission, distribution, and generation services to participating customers, as specified. The bill would require the commission, as part of establishing and updating electric rules, to, at a minimum, evaluate the risks and benefits of the tariffs to nonparticipating customers, ensure that the tariffs prevent the creation of stranded costs for, or cost shifts to, nonparticipating customers, and, for unbundled customers, ensure that charges generally included in the generation component of the unbundled customers consolidated bill are assessed as a separate line item on their bill. The bill would require, as part of a new or existing proceeding, the commission to establish a tariff for the interconnection of a participating customer seeking to receive retail electric service at the transmission level that meets certain requirements, as specified. The bill would authorize a participating customer to participate in a new demand response program authorized by the commission, as specified. The bill would authorize an electrical corporation to submit an exceptional case filing to approve a contract between the electrical corporation and a data center seeking interconnection at the transmission level for those facilities that seek to obtain retail electric service after January 1, 2027, but before the commission has approved the tariff, as specified.
Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.
Because the above provisions would be a part of the act, and a violation of a commission action implementing this bills requirements would be a crime, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations. Existing law authorizes the commission to fix the rates and charges for every public utility and requires that those rates and charges be just and reasonable.
This bill, the California Technology Innovation and Ratepayer Protection Act, would require the commission, on or before January 1, 2028, to establish new tariffs or update existing electric rules for the interconnection of participating customer facilities and the provision of retail electric service, transmission, distribution, and generation services to participating customers, as specified. The bill would require the commission, as part of establishing and updating electric rules, to, at a minimum, evaluate the risks and benefits of the tariffs to nonparticipating customers, ensure that the tariffs prevent the creation of stranded costs for, or cost shifts to, nonparticipating customers, and, for unbundled customers, ensure that charges generally included in the generation component of the unbundled customers consolidated bill are assessed as a separate line item on their bill. The bill would require, as part of a new or existing proceeding, the commission to establish a tariff for the interconnection of a participating customer seeking to receive retail electric service at the transmission level that meets certain requirements, as specified. The bill would authorize a participating customer to participate in a new demand response program authorized by the commission, as specified. The bill would authorize an electrical corporation to submit an exceptional case filing to approve a contract between the electrical corporation and a data center seeking interconnection at the transmission level for those facilities that seek to obtain retail electric service after January 1, 2027, but before the commission has approved the tariff, as specified.
Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.
Because the above provisions would be a part of the act, and a violation of a commission action implementing this bills requirements would be a crime, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations. Existing law authorizes the commission to fix the rates and charges for every public utility and requires that those rates and charges be just and reasonable.
This bill, the California Technology Innovation and Ratepayer Protection Act, would require the commission, on or before July 1, 2027, January 1, 2028, to establish separate new tariffs or update existing electric rules for the interconnection of the participating customer facilities and the provision of retail electric service, transmission, distribution, and optional generation services to participating customers, as specified. The bill would require the commission, as part of establishing the separate tariffs, and updating electric rules, to, at a minimum, evaluate the risks and benefits of the separate tariffs to nonparticipating customers, ensure that the separate tariffs prevent the creation of stranded costs for, or cost shifts to, nonparticipating customers, and, for unbundled customers, ensure that charges generally included in the generation component of the unbundled customers consolidated bill are assessed as a separate line item on their bill. The bill would require that the interconnection tariff, among other things, require a participating customer that submits an application for interconnection of a data center to an electrical corporation to disclose whether an application for the same data center has been submitted in other electrical corporation service territories or other jurisdictions and to disclose each instance in which an application for the same data center has been submitted, assign cost responsibility for all transmission facility upgrades triggered by a new facility interconnection to the applicable participating customer, and require an early termination fee to be assessed against a participating customer under specified circumstances. The bill would require, for the generation tariff, a participating customer to prefund a contract of at least 10 years in duration through the load-serving entity, as defined, for the costs of procurement necessary to serve the participating customer, as provided. The bill would also require each electrical corporation to publish and update maps showing locations where participating customers can interconnect without the need for significant, costly, and time-consuming transmission upgrades. require, as part of a new or existing proceeding, the commission to establish a tariff for the interconnection of a participating customer seeking to receive retail electric service at the transmission level that meets certain requirements, as specified. The bill would authorize a participating customer to participate in a new demand response program authorized by the commission, as specified. The bill would authorize an electrical corporation to submit an exceptional case filing to approve a contract between the electrical corporation and a data center seeking interconnection at the transmission level for those facilities that seek to obtain retail electric service after January 1, 2027, but before the commission has approved the tariff, as specified.
Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.
Because the above provisions would be a part of the act, and a violation of a commission action implementing this bills requirements would be a crime, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations. Existing law authorizes the commission to fix the rates and charges for every public utility and requires that those rates and charges be just and reasonable.
This bill, the California Technology Innovation and Ratepayer Protection Act, would require the commission, on or before July 1, 2027, to establish separate tariffs for the interconnection of the participating customer facilities and the provision of transmission, distribution, and optional generation services to participating customers, as specified. The bill would require the commission, as part of establishing the separate tariffs, to, at a minimum, evaluate the risks and benefits of the separate tariffs to nonparticipating customers, ensure that the separate tariffs prevent the creation of stranded costs for, or cost shifts to, nonparticipating customers, and, for unbundled customers, ensure that charges generally included in the generation component of the unbundled customers consolidated bill are assessed as a separate line item on their bill. The bill would require that the interconnection tariff, among other things, require a participating customer that submits an application for interconnection of a data center to an electrical corporation to disclose whether an application for the same data center has been submitted in other electrical corporation service territories or other jurisdictions and to disclose each instance in which an application for the same data center has been submitted, assign cost responsibility for all transmission facility upgrades triggered by a new facility interconnection to the applicable participating customer, and require an early termination fee to be assessed against a participating customer under specified circumstances. The bill would require, for the generation tariff, a participating customer to prefund a contract of at least 10 years in duration through the load-serving entity, as defined, for the costs of procurement necessary to serve the participating customer, as provided. The bill would also require each electrical corporation to publish and update maps showing locations where participating customers can interconnect without the need for significant, costly, and time-consuming transmission upgrades.
Under existing law, a violation of any order, decision, rule, direction, demand, or requirement of the commission is a crime.
Because a violation of a commission action implementing this bills requirements would be a crime, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations. Existing law authorizes the commission to fix the rates and charges for every public utility and requires that those rates and charges be just and reasonable.
This bill, the California Technology Innovation and Ratepayer Protection Act, would require the commission, on or before July 1, 2027, to establish a rate structure that includes an electrical corporation tariff separate tariffs for the interconnection of the participating customer facilities and the provision of transmission, distribution, and optional generation services to participating customers, as specified. The bill would require the commission, as part of establishing the electrical corporation tariff, separate tariffs, to, at a minimum, establish eligibility criteria for participating customers, evaluate the risks and benefits of the electrical corporation tariff separate tariffs to nonparticipating customers, ensure that the electrical corporation tariff prevents separate tariffs prevent the creation of stranded costs for, or cost shifts to, nonparticipating customers, and, for unbundled customers, ensure that charges generally included in the generation component of their bills the unbundled customers consolidated bill are assessed separately from charges generally included in the transmission and distribution components of their bills. as a separate line item on their bill. The bill would require that the electrical corporation tariff the interconnection tariff, among other things, require a participating customer that submits an application for interconnection of a facility data center to an electrical corporation to disclose whether an application for the same facility data center has been submitted in other electrical corporation service territories or other jurisdictions and to disclose each instance in which an application for the same facility data center has been submitted. The bill would also require that the electrical corporation tariff, among other things, submitted, assign cost responsibility for all transmission facility upgrades triggered by a new facility interconnection to the applicable participating customer and customer, require an early termination fee to be assessed against a participating customer under specified circumstances. The bill would require require, for the generation tariff, a participating customer to prefund a contract of at least 15 10 years in duration through the electrical corporation, community choice aggregator, or electric service provider load-serving entity, as defined, for the installation of new, incremental, zero-carbon energy resources, and to participate in a new demand response program authorized by the commission, costs of procurement necessary to serve the participating customer, as provided. The bill would also require each electrical corporation to publish and update maps showing locations where participating customers can interconnect without the need for significant, costly, and time-consuming transmission upgrades.
Under existing law, a violation of any order, decision, rule, direction, demand, or requirement of the commission is a crime.
Because a violation of a commission action implementing this bills requirements would be a crime, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations, while local publicly owned electric utilities are under the direction of their governing boards. corporations. Existing law authorizes the commission to fix the rates and charges for every public utility and requires that those rates and charges be just and reasonable.
This bill, the California Technology Innovation and Ratepayer Protection Act, would require the commission, on or before July 1, 2027, to establish a rate structure that includes an electrical corporation tariff for the interconnection of the participating customer facilities and the provision of transmission, distribution, and generation services to participating customers, as specified. The bill would require the commission, as part of establishing the electrical corporation tariff, to, at a minimum, establish eligibility criteria for participating customer, customers, evaluate the risks and benefits of the electrical corporation tariff to nonparticipating customers, ensure that the electrical corporation tariff prevents the creation of stranded costs for, or cost shifts to, nonparticipating customers, and, for unbundled customers, ensure that charges generally included in the generation component of their bills are assessed separately from charges generally included in the transmission and distribution components of their bills. The bill would require that the electrical corporation tariff require a participating customer that submits an application for interconnection of a facility to an electrical corporation to disclose whether an application for the same facility has been submitted in other electrical corporation service territories or other jurisdictions and to disclose each instance in which an application for the same facility has been submitted. The bill would also require that the electrical corporation tariff, among other things, assign cost responsibility for all transmission facility upgrades triggered by a new facility interconnection to the applicable participating customer and require an early termination fee to be assessed against a participating customer under specified circumstances. The bill would require a participating customer to prefund a contract of at least 15 years in duration through the electrical corporation, community choice aggregator, or electric service provider for the installation of new, incremental, zero-carbon energy resources, and to participate in a new demand response program authorized by the commission, as provided. The bill would also require each electrical corporation to publish and update maps showing locations where participating customers can interconnect without the need for significant, costly, and time-consuming transmission upgrades.
This bill would encourage each local publicly owned electric utility to develop a tariff that is similar to the electrical corporation tariff described above and ensures, among other things, that costs are not shifted from a customer that is not subject to that tariff to a customer that is subject to that tariff, and that the costs of investments in infrastructure made by a customer that is subject to that tariff are not recoverable from other customers that are not subject to that tariff.Under existing law, a violation of any order, decision, rule, direction, demand, or requirement of the commission is a crime.
Because a violation of a commission action implementing this bills requirements would be a crime, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations, while local publicly owned electric utilities are under the direction of their governing boards. Existing law authorizes the commission to fix the rates and charges for every public utility and requires that those rates and charges be just and reasonable.
This bill, the California Technology Innovation and Ratepayer Protection Act, would require the commission, on or before July 1, 2027, to establish or modify a rate structure that includes an electrical corporation tariff for the interconnection of the participating customer facilities and the provision of transmission, distribution, and generation services to participating customers, as specified. The bill would require the commission, as part of establishing or modifying the electrical corporation tariff, to, at a minimum, establish eligibility criteria for large load customers, as defined, and facilities, participating customer, evaluate the risks and benefits of the electrical corporation tariff to nonparticipating customers, and ensure that the electrical corporation tariff prevents the creation of stranded costs for, or cost shifts, to shifts to, nonparticipating customers. customers, and, for unbundled customers, ensure that charges generally included in the generation component of their bills are assessed separately from charges generally included in the transmission and distribution components of their bills. The bill would require that the electrical corporation tariff require a large load participating customer that submits an application for interconnection of a facility to an electrical corporation to disclose whether an application for the same facility has been submitted in other electrical corporation service territories or other jurisdictions and to disclose each instance in which an application for the same facility has been submitted. The bill would also require that the electrical corporation tariff, among other things, assign cost responsibility for all transmission facility upgrades triggered by a new facility interconnection to the applicable participating customer and require an early termination fee to be assessed against a participating customer under specified circumstances. The bill would require a participating customer to prefund a contract of at least 15 years in duration through the electrical corporation, community choice aggregator, or electric service provider for the installation of new, incremental, zero-carbon energy resources, and to participate in a new demand response program authorized by the commission, as provided. The bill would also require each participating customer to install onsite zero-carbon energy storage, as provided, and each electrical corporation to publish and update maps showing locations where large load participating customers can interconnect without the need for significant, costly, and time-consuming transmission upgrades.
This bill would encourage each local publicly owned electric utility to develop a tariff that is similar to the electrical corporation tariff described above and ensures ensures, among other things, that costs are not shifted from a large load customer that is subject to the local publicly owned electric utilitys tariff to a large load a customer that is not subject to that tariff to a customer that is subject to that tariff, and that the costs of investments in infrastructure made by a large load customer that is subject to the that tariff are not recoverable from other nonparticipating ratepayers. customers that are not subject to that tariff.
Under existing law, a violation of any order, decision, rule, direction, demand, or requirement of the commission is a crime.
Because a violation of a commission action implementing this bills requirements would be a crime, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations, while local publicly owned electric utilities are under the direction of their governing boards. Existing law authorizes the commission to fix the rates and charges for every public utility and requires that those rates and charges be just and reasonable.
This bill, the California Technology Innovation and Ratepayer Protection Act, would require the commission, on or before July 1, 2027, to establish or modify an electrical corporation tariff for the interconnection of the participating customer facilities and the provision of transmission, distribution, and generation services to participating customers, as specified. The bill would require the commission, as part of establishing or modifying the electrical corporation tariff, to, at a minimum, establish eligibility criteria for large load customers, as defined, and facilities, evaluate the risks and benefits of this the electrical corporation tariff to nonparticipating ratepayers, customers, and ensure that the electrical corporation tariff prevents the creation of stranded costs for, or cost shifts, to nonparticipating ratepayers. customers. The bill would require that the electrical corporation tariff to require a large load customer that submits an application for interconnection of a facility to an electrical corporation to disclose whether an application for the same facility has been submitted in other electrical corporation service territories or other jurisdictions and to disclose each instance in which an application for the same facility has been submitted. The bill would also require that the tariff to, tariff, among other things, assign cost responsibility for all transmission facility upgrades triggered by a facility interconnection to the applicable participating customer and to require an early termination fee to be assessed against any a participating customer under specified circumstances. The bill would also require each participating customer to install onsite zero-carbon energy storage, as provided, and each electrical corporation to publish and update maps showing locations where large load customers can interconnect without the need for significant, costly, and time-consuming transmission upgrades.
This bill would encourage each local publicly owned electric utility to develop a tariff that is similar to the electrical corporation tariff described above and ensures that costs are not shifted from a large load customer that is subject to the local publicly owned electric utilitys tariff to a large load customer that is not subject to that tariff, and that the costs of investments in infrastructure made by a large load customer that is subject to the tariff are not recoverable from other nonparticipating ratepayers.
Under existing law, a violation of any order, decision, rule, direction, demand, or requirement of the commission is a crime.
Because a violation of a commission action implementing this bills requirements would be a crime, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations, while local publicly owned electric utilities are under the direction of their governing boards. Existing law authorizes the commission to fix the rates and charges for every public utility and requires that those rates and charges be just and reasonable.
This bill, the California Technology Innovation and Ratepayer Protection Act, would require the commission, on or before July 1, 2027, to establish or modify an electrical corporation tariff for the interconnection of the participating customer facilities and the transmission, distribution, and generation services to participating customers, as specified. The bill would require the commission, as part of establishing or modifying the electrical corporation tariff, to, at a minimum, establish eligibility criteria for large load customers, as defined, and facilities, evaluate the risks and benefits of this tariff to nonparticipating ratepayers, and ensure that the tariff prevents the creation of stranded costs for, or cost shifts, to nonparticipating ratepayers. The bill would require the tariff to require a large load customer that submits an application for interconnection of a facility to an electrical corporation to disclose whether an application for the same facility has been submitted in other electrical corporation service territories or other jurisdictions and to disclose each instance in which an application for the same facility has been submitted. The bill would also require the tariff to, among other things, assign cost responsibility for all transmission facility upgrades triggered by a facility interconnection to the applicable participating customer and to require an early termination fee to be assessed against any participating customer under specified circumstances. The bill would also require each participating customer to install onsite zero-carbon energy storage, as provided, and each electrical corporation to publish and update maps showing locations where large load customers can interconnect without the need for significant, costly, and time-consuming transmission upgrades.
This bill would encourage each local publicly owned electric utility to develop a tariff that is similar to the electrical corporation tariff described above and ensures that costs are not shifted from a customer that is subject to the local publicly owned electric utilitys tariff to a customer that is not subject to that tariff, and that the costs of investments in infrastructure made by a large load customer that is subject to the tariff are not recoverable from other nonparticipating ratepayers.
Under existing law, a violation of any order, decision, rule, direction, demand, or requirement of the commission is a crime.
Because a violation of a commission action implementing this bills requirements would be a crime, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
This article shall be known, and may be cited, as the California Technology Innovation and Ratepayer Protection Act.
945.2.(a)On or before January 1, 2028, the commission shall establish new tariffs or update existing electric rules for the interconnection of participating customer facilities and the provision of retail electric service, transmission, distribution, and generation services to participating customers.(b)The commission, as part of establishing and updating electric rules pursuant to this article, shall do, at a minimum, all of the following:(1)Evaluate the risks and benefits of the tariffs to nonparticipating customers.(2)Ensure that the tariffs prevent the creation of stranded costs for, or cost shifts to, nonparticipating customers.(3)For an unbundled customer, ensure that charges generally included in the generation component of the unbundled customers consolidated bill are assessed as a separate line item on the unbundled customers bill.945.3.(a)As part of a new or existing proceeding, the commission shall establish a tariff for the interconnection of a participating customer seeking to receive retail electric service at the transmission level. A tariff established pursuant to this section shall do all the following:
(1)Ensure the interconnection tariff is consistent with Section 945.2.
(2)Require a participating customer that submits an application for interconnection of a data center to an electrical corporation to disclose whether an application for the same data center has been submitted in other electrical corporation service territories or other jurisdictions and to disclose each instance in which an application for the same data center has been submitted.
(3)Assign cost responsibility for all transmission facility upgrades and usage to the applicable participating customer based on a methodology to be determined by the commission. To the extent permitted under federal law, these costs should include shared transmission grid network upgrades needed to accommodate the interconnection of the participating customers facility or increase the flow of electricity across the electrical grid.
(4)Allow a participating customer to receive refunds of a portion of its initial nominal dollar contributions to interconnection costs only to the extent that actual annual net revenues received by the electrical corporation cover the costs of energization, the costs of providing electrical service, and other costs allocated by the commission to the participating customer. The refund shall be based on the materialization of the participating customers load and shall not exceed 75 percent of the annual net transmission revenue received by the electrical corporation from the participating customer. This limitation may delay the timing of the full recovery of refunds by the participating customer.
(5)For a participating customer, require an early termination fee to be assessed against a participating customer that departs the electrical system within 10 years of the initial interconnection of the facility or fails to achieve adequate load ramp up, as determined by the commission. The early termination fee should not be less than the revenue gap associated with the originally projected demand and energy consumption of the facility over the minimum 10-year term.
(b)A participating customer shall certify to the commission that its facility meets the requirements of subdivisions (a) and (b) of Section 25545.3.3 of, and subdivisions (a) to (e), inclusive, of Section 25545.3.5 of, the Public Resources Code, notwithstanding the definition of covered project in Section 25545.3 of the Public Resources Code.
(c)The commission shall require each electrical corporation to publish and update maps showing locations where participating customers can interconnect without the need for significant, costly, and time-consuming transmission upgrades.
(d)This section shall only apply to a data center that enters into a new interconnection agreement to receive retail electric service at the transmission level on or after January 1, 2027.
945.7.A participating customer may participate in a new demand response program authorized by the commission that does not result in any net costs to a nonparticipating customer and supports load shifting, reliability, resource adequacy, and greenhouse gas emission reduction objectives, as determined by the commission.
945.9.An electrical corporation may submit an exceptional case filing to approve a contract between the electrical corporation and a data center seeking interconnection at the transmission level for those facilities that seek to obtain retail electric service after January 1, 2027, but before the commission has approved a tariff filed pursuant to Section 945.3. A contract established pursuant to this section shall be consistent with the requirements of this article.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
This article shall be known, and may be cited, as the California Technology Innovation and Ratepayer Protection Act.
945.2.(a)On or before January 1, 2028, the commission shall establish new tariffs or update existing electric rules for the interconnection of participating customer facilities and the provision of retail electric service, transmission, distribution, and generation services to participating customers.(b)The commission, as part of establishing and updating electric rules pursuant to this article, shall do, at a minimum, all of the following:(1)Evaluate the risks and benefits of the tariffs to nonparticipating customers.(2)Ensure that the tariffs prevent the creation of stranded costs for, or cost shifts to, nonparticipating customers.(3)For an unbundled customer, ensure that charges generally included in the generation component of the unbundled customers consolidated bill are assessed as a separate line item on the unbundled customers bill.945.3.(a)As part of a new or existing proceeding, the commission shall establish a tariff for the interconnection of a participating customer seeking to receive retail electric service at the transmission level. A tariff established pursuant to this section shall do all the following:
(1)Ensure the interconnection tariff is consistent with Section 945.2.
(2)Require a participating customer that submits an application for interconnection of a data center to an electrical corporation to disclose whether an application for the same data center has been submitted in other electrical corporation service territories or other jurisdictions and to disclose each instance in which an application for the same data center has been submitted.
(3)Assign cost responsibility for all transmission facility upgrades and usage to the applicable participating customer based on a methodology to be determined by the commission. To the extent permitted under federal law, these costs should include shared transmission grid network upgrades needed to accommodate the interconnection of the participating customers facility or increase the flow of electricity across the electrical grid.
(4)Allow a participating customer to receive refunds of a portion of its initial nominal dollar contributions to interconnection costs only to the extent that actual annual net revenues received by the electrical corporation cover the costs of energization, the costs of providing electrical service, and other costs allocated by the commission to the participating customer. The refund shall be based on the materialization of the participating customers load and shall not exceed 75 percent of the annual net transmission revenue received by the electrical corporation from the participating customer. This limitation may delay the timing of the full recovery of refunds by the participating customer.
(5)For a participating customer, require an early termination fee to be assessed against a participating customer that departs the electrical system within 10 years of the initial interconnection of the facility or fails to achieve adequate load ramp up, as determined by the commission. The early termination fee should not be less than the revenue gap associated with the originally projected demand and energy consumption of the facility over the minimum 10-year term.
(b)A participating customer shall certify to the commission that its facility meets the requirements of subdivisions (a) and (b) of Section 25545.3.3 of, and subdivisions (a) to (e), inclusive, of Section 25545.3.5 of, the Public Resources Code, notwithstanding the definition of covered project in Section 25545.3 of the Public Resources Code.
(c)The commission shall require each electrical corporation to publish and update maps showing locations where participating customers can interconnect without the need for significant, costly, and time-consuming transmission upgrades.
(d)This section shall only apply to a data center that enters into a new interconnection agreement to receive retail electric service at the transmission level on or after January 1, 2027.
945.7.A participating customer may participate in a new demand response program authorized by the commission that does not result in any net costs to a nonparticipating customer and supports load shifting, reliability, resource adequacy, and greenhouse gas emission reduction objectives, as determined by the commission.
945.9.An electrical corporation may submit an exceptional case filing to approve a contract between the electrical corporation and a data center seeking interconnection at the transmission level for those facilities that seek to obtain retail electric service after January 1, 2027, but before the commission has approved a tariff filed pursuant to Section 945.3. A contract established pursuant to this section shall be consistent with the requirements of this article.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
This chapter article shall be known, and may be cited, as the California Technology Innovation and Ratepayer Protection Act.
8541.For purposes of this chapter, all of the following definitions apply:(a)(1)Data center means a facility, or a part of a facility, that houses computing infrastructure, including graphics and central processing units, servers, storage devices, networking equipment, and associated power and cooling systems, for the primary purpose of processing, storing, or distributing electronic data, except as specified in paragraph (2).(2)Data center does not include a publicly funded research facility, public safety facility, national security facility, publicly owned facility, or other utility facility, including, but not limited to, an asset of a facilities-based telecommunications provider.(b)Electrical corporation has the same meaning as defined in Section 218, but does not include an electrical cooperative, as defined in Section 2776.(c)Facility means a physical property, a plant, a building, a structure, or stationary equipment, located on one or more contiguous or adjacent properties in actual physical contact or separated solely by a public roadway or public right-of-way and under common ownership or common control.(d)Load-Serving entity has the meaning set forth in Section 380.(e)Nonparticipating customer means a customer who does not receive electrical service pursuant to a tariff established pursuant to subdivision (a) of Section 8542.(f)Participating customer means a data center with a minimum peak demand, as determined by the commission. The minimum peak demand determined by the commission shall not exceed 25 megawatts and, in making that determination, the commission shall consider the extent to which facility load has a material impact on electrical corporation costs.(g)Separate tariffs means the tariffs established by the commission pursuant to subdivision (a) of Section 8542 and includes the transmission, distribution, generation, and interconnection tariffs described in Section 8542.(h)Unbundled customer means a customer receiving the generation component of their electrical service from an entity that is different from the entity providing the transmission and distribution components of the customers electrical service.8542.945.2.(a)On or before July 1, 2027, January 1, 2028, the commission shall establish separate tariffs new tariffs or update existing electric rules for the interconnection of participating customer facilities and the provision of retail electric service, transmission, distribution, and optional generation services to participating customers.(b)The commission, as part of establishing the separate tariffs, and updating electric rules pursuant to this article, shall do, at a minimum, all of the following:(1)Evaluate the risks and benefits of the separate tariffs to nonparticipating customers.(2)Ensure that the separate tariffs prevent the creation of stranded costs for, or cost shifts to, nonparticipating customers.(3)For an unbundled customer, ensure that charges generally included in the generation component of the unbundled customers consolidated bill are assessed as a separate line item on the unbundled customers bill.(c)In establishing the transmission and distribution tariffs, the commission shall do both of the following:(1)Ensure the transmission and distribution tariffs are consistent with subdivision (b).(2)Ensure the participating customer pays a reasonable share of the costs relating to wildfire mitigation, wildfire liability, electrification and environmental programs, and other societal cost obligations typically collected from distribution-level ratepayers.(d)In establishing the generation tariff, the commission shall do all of the following:(1)Ensure the generation tariff is consistent with subdivision (b).(2)Ensure the procurement of generation resources that support a load-serving entitys ability to meet procurement requirements set forth by the commission, the clean energy targets set forth in Sections 399.15 and 454.52, and other state clean energy policies.(3)Ensure the generation tariff assigns a participating customer any unique wholesale energy costs, including ancillary and reliability service costs attributable to rapid fluctuations in demand by the participating customer.(4)(A)Require a participating customer to prefund a contract of at least 10 years in duration through a load-serving entity for the costs of procurement necessary to serve the participating customer. The procurement of resources to serve the participating customer shall be consistent with paragraph (2).(B)Authorize a participating customer to reduce the requirement to prefund a contract by installing zero-emission resources behind its meter, as determined by the load-serving entity.(e)In establishing the interconnection tariff, the commission shall do all of the following:945.3.(a)As part of a new or existing proceeding, the commission shall establish a tariff for the interconnection of a participating customer seeking to receive retail electric service at the transmission level. A tariff established pursuant to this section shall do all the following:
(1)Ensure the interconnection tariff is consistent with subdivision (b). Section 945.2.
(2)Require a participating customer that submits an application for interconnection of a data center to an electrical corporation to disclose whether an application for the same data center has been submitted in other electrical corporation service territories or other jurisdictions and to disclose each instance in which an application for the same data center has been submitted.
(3)Assign cost responsibility for all transmission facility upgrades triggered by a new facility interconnection and usage to the applicable participating customer. customer based on a methodology to be determined by the commission. To the extent permitted under federal law, these costs should include shared transmission grid network upgrades needed to accommodate the interconnection of the participating customers facility or increase the flow of electricity across the electrical grid.
(4)Allow a participating customer to receive refunds of a portion of its initial nominal dollar contributions to interconnection costs only to the extent that actual annual net revenues received by the electrical corporation cover the costs of energization, the costs of providing electrical service, and other costs allocated by the commission to the participating customer. On an annual basis, the The refund shall not be more than be based on the materialization of the participating customers load and shall not exceed 75 percent of the annual net transmission revenue received by the electrical corporation from the participating customer. This limitation may delay the timing of the full recovery of refunds by the participating customer.
(5)For a participating customer, require an early termination fee to be assessed against a participating customer that departs the electrical system within 10 years of the initial interconnection of the facility or fails to achieve adequate load ramp up, as determined by the commission. The early termination fee should not be less than the revenue gap associated with the originally projected demand and energy consumption of the facility over the minimum 10-year term.
(f)(b)A participating customer shall certify to the commission that its facility meets the requirements of subdivisions (a) and (b) of Section 25545.3.3 of, and subdivisions (a) to (e), inclusive, of Section 25545.3.5 of, the Public Resources Code, notwithstanding the definition of covered project in Section 25545.3 of the Public Resources Code.
(g)(c)The commission shall require each electrical corporation to publish and update maps showing locations where participating customers can interconnect without the need for significant, costly, and time-consuming transmission upgrades.
(h)This section does not modify the limits on direct transactions established pursuant to Section 365.1.(i)This section does not authorize the commission to regulate the rates or terms and conditions of service offered by a community choice aggregator, consistent with Section 366.2, or an electric service provider, consistent with Section 394.(d)This section shall only apply to a data center that enters into a new interconnection agreement to receive retail electric service at the transmission level on or after January 1, 2027.
8543.945.7.A participating customer shall may participate in a new demand response program authorized by the commission that does not result in any net costs to a nonparticipating customer and supports load shifting, reliability, resource adequacy, and greenhouse gas emission reduction objectives. objectives, as determined by the commission.
8544.This chapter does not limit or restrict the ability of a data center to receive generation services from an electric service provider or community choice aggregator. Generation services provided to a data center by an electric service provider or community choice aggregator shall meet the requirements specified in subdivision (d) of Section 8542.945.9.An electrical corporation may submit an exceptional case filing to approve a contract between the electrical corporation and a data center seeking interconnection at the transmission level for those facilities that seek to obtain retail electric service after January 1, 2027, but before the commission has approved a tariff filed pursuant to Section 945.3. A contract established pursuant to this section shall be consistent with the requirements of this article.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
This chapter shall be known, and may be cited, as the California Technology Innovation and Ratepayer Protection Act.
8541.For purposes of this chapter, all of the following definitions apply:
(a)(1)Data center means a facility, or a part of a facility, that houses computing infrastructure, including graphics and central processing units, servers, storage devices, networking equipment, and associated power and cooling systems, for the primary purpose of processing, storing, or distributing electronic data, except as specified in paragraph (2).
(2)Data center does not include a publicly funded research facility, public safety facility, national security facility, publicly owned facility, or other utility facility, including, but not limited to, an asset of a facilities-based telecommunications provider.
(b)Electrical corporation has the same meaning as defined in Section 218, but does not include an electrical cooperative, as defined in Section 2776.
(c)Facility means a physical property, a plant, a building, a structure, or stationary equipment, located on one or more contiguous or adjacent properties in actual physical contact or separated solely by a public roadway or public right-of-way and under common ownership or common control.
(d)Load-Serving entity has the meaning set forth in Section 380.
(e)Nonparticipating customer means a customer who does not receive electrical service pursuant to a tariff established pursuant to subdivision (a) of Section 8542.
(f)Participating customer means a data center with a minimum peak demand, as determined by the commission. The minimum peak demand determined by the commission shall not exceed 25 megawatts and, in making that determination, the commission shall consider the extent to which facility load has a material impact on electrical corporation costs.
(g)Separate tariffs means the tariffs established by the commission pursuant to subdivision (a) of Section 8542 and includes the transmission, distribution, generation, and interconnection tariffs described in Section 8542.
(h)Unbundled customer means a customer receiving the generation component of their electrical service from an entity that is different from the entity providing the transmission and distribution components of the customers electrical service.
8542.(a)On or before July 1, 2027, the commission shall establish separate tariffs for the interconnection of participating customer facilities and the provision of transmission, distribution, and optional generation services to participating customers.
(b)The commission, as part of establishing the separate tariffs, shall do, at a minimum, all of the following:
(1)Evaluate the risks and benefits of the separate tariffs to nonparticipating customers.
(2)Ensure that the separate tariffs prevent the creation of stranded costs for, or cost shifts to, nonparticipating customers.
(3)For an unbundled customer, ensure that charges generally included in the generation component of the unbundled customers consolidated bill are assessed as a separate line item on the unbundled customers bill.
(c)In establishing the transmission and distribution tariffs, the commission shall do both of the following:
(1)Ensure the transmission and distribution tariffs are consistent with subdivision (b).
(2)Ensure the participating customer pays a reasonable share of the costs relating to wildfire mitigation, wildfire liability, electrification and environmental programs, and other societal cost obligations typically collected from distribution-level ratepayers.
(d)In establishing the generation tariff, the commission shall do all of the following:
(1)Ensure the generation tariff is consistent with subdivision (b).
(2)Ensure the procurement of generation resources that support a load-serving entitys ability to meet procurement requirements set forth by the commission, the clean energy targets set forth in Sections 399.15 and 454.52, and other state clean energy policies.
(3)Ensure the generation tariff assigns a participating customer any unique wholesale energy costs, including ancillary and reliability service costs attributable to rapid fluctuations in demand by the participating customer.
(4)(A)Require a participating customer to prefund a contract of at least 10 years in duration through a load-serving entity for the costs of procurement necessary to serve the participating customer. The procurement of resources to serve the participating customer shall be consistent with paragraph (2).
(B)Authorize a participating customer to reduce the requirement to prefund a contract by installing comparable zero-emission resources behind its meter, as determined by the load-serving entity.
(e)In establishing the interconnection tariff, the commission shall do all of the following:
(1)Ensure the interconnection tariff is consistent with subdivision (b).
(2)Require a participating customer that submits an application for interconnection of a data center to an electrical corporation to disclose whether an application for the same data center has been submitted in other electrical corporation service territories or other jurisdictions and to disclose each instance in which an application for the same data center has been submitted.
(3)Assign cost responsibility for all transmission facility upgrades triggered by a new facility interconnection to the applicable participating customer. To the extent permitted under federal law, these costs should include shared transmission grid network upgrades needed to accommodate the interconnection of the participating customers facility or increase the flow of electricity across the electrical grid.
(4)Allow a participating customer to receive refunds of a portion of its initial nominal dollar contributions to interconnection costs only to the extent that actual annual net revenues received by the electrical corporation cover the costs of energization, the costs of providing electrical service, and other costs allocated by the commission to the participating customer. On an annual basis, the refund shall not be more than 75 percent of the annual net transmission revenue received by the electrical corporation from the participating customer. This limitation may delay the timing of the full recovery of refunds by the participating customer.
(5)For a participating customer, require an early termination fee to be assessed against a participating customer that departs the electrical system within 10 years of the initial interconnection of the facility or fails to achieve adequate load ramp up, as determined by the commission. The early termination fee should not be less than the revenue gap associated with the originally projected demand and energy consumption of the facility over the minimum 10-year term.
(f)A participating customer shall certify to the commission that its facility meets the requirements of subdivisions (a) and (b) of Section 25545.3.3 of, and subdivisions (a) to (e), inclusive, of Section 25545.3.5 of, the Public Resources Code, notwithstanding the definition of covered project in Section 25545.3 of the Public Resources Code.
(g)The commission shall require each electrical corporation to publish and update maps showing locations where participating customers can interconnect without the need for significant, costly, and time-consuming transmission upgrades.
(h)This section does not modify the limits on direct transactions established pursuant to Section 365.1.
(i)This section does not authorize the commission to regulate the rates or terms and conditions of service offered by a community choice aggregator, consistent with Section 366.2, or an electric service provider, consistent with Section 394.
8543.A participating customer shall participate in a new demand response program authorized by the commission that does not result in any net costs to a nonparticipating customer and supports load shifting, reliability, resource adequacy, and greenhouse gas emission reduction objectives.
8544.This chapter does not limit or restrict the ability of a data center to receive generation services from an electric service provider or community choice aggregator. Generation services provided to a data center by an electric service provider or community choice aggregator shall meet the requirements specified in subdivision (d) of Section 8542.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
REVISIONS: HeadingLines 4 and 5.This chapter shall be known, and may be cited, as the California Technology Innovation and Ratepayer Protection Act.
8541.For purposes of this chapter, all of the following definitions apply:
(a)(1)Data center means a facility that primarily contains electronic equipment used to process, store, and transmit digital information, which may be a free-standing structure or a facility within a larger structure, that uses environmental control equipment to maintain the proper conditions for the operation of electronic equipment, facility, or a part of a facility, that houses computing infrastructure, including graphics and central processing units, servers, storage devices, networking equipment, and associated power and cooling systems, for the primary purpose of processing, storing, or distributing electronic data, except as specified in paragraph (2).
(2)Data center does not include a publicly funded research facility, public safety facility, national security facility, publicly owned facility, or other utility facility, including, but not limited to, an asset of a facilities-based telecommunications provider.
(b)Electrical corporation has the same meaning as defined in Section 218. 218, but does not include an electrical cooperative, as defined in Section 2776.
(c)Electrical corporation tariff means an electrical corporation tariff included as part of the rate structure established pursuant to subdivision (a) of Section 8542.(d)(c)Facility means a physical property, a plant, a building, a structure, a source, or stationary equipment, located on one or more contiguous or adjacent properties in actual physical contact or separated solely by a public roadway or public right-of-way and under common ownership or common control.
(d)Load-Serving entity has the meaning set forth in Section 380.
(e)(e)Nonparticipating customer means a customer who does not receive electrical service pursuant to an electrical corporation tariff. a tariff established pursuant to subdivision (a) of Section 8542.
(f)(1)Participating customer means a customer who receives electrical service pursuant to an electrical corporation tariff.(2)For the purpose of the interconnection components of an electrical corporation tariff, participating customer means a data center taking transmission level electrical service with an estimated peak demand of at least 25 megawatts. For the other components of an electrical corporation tariff, the commission shall determine an appropriate minimum peak demand for participating customers, not to exceed 25 megawatts, that considers the(f)Participating customer means a data center with a minimum peak demand, as determined by the commission. The minimum peak demand determined by the commission shall not exceed 25 megawatts and, in making that determination, the commission shall consider the extent to which facility load has a material impact on electrical corporation costs.
(3)Participating customer does not include a publicly funded research facility, public safety facility, national security facility, publicly owned facility, and other utility facility, including, but not limited to, an asset of a facilities-based telecommunications provider.(g)Separate tariffs means the tariffs established by the commission pursuant to subdivision (a) of Section 8542 and includes the transmission, distribution, generation, and interconnection tariffs described in Section 8542.
(g)(h)Unbundled customer means a customer receiving the generation component of their electrical service from an entity that is different from the entity providing the transmission and distribution components of the customers electrical service.
8542.(a)On or before July 1, 2027, the commission shall establish a rate structure that includes an electrical corporation tariff separate tariffs for the interconnection of participating customer facilities and the provision of transmission, distribution, and optional generation services to participating customers.
(b)The commission, as part of establishing an electrical corporation tariff, the separate tariffs, shall do, at a minimum, all of the following:
(1)Establish eligibility criteria for participating customers. The interconnection components of an electrical corporation tariff shall only apply to a facility for which a new transmission interconnection agreement is established after the establishment of the rate structure pursuant to this chapter by the commission or after a later date specified by the commission.(2)(1)Evaluate the risks and benefits of an electrical corporation tariff the separate tariffs to nonparticipating customers.
(3)(2)Ensure that an electrical corporation tariff prevents the separate tariffs prevent the creation of stranded costs for, or cost shifts to, nonparticipating customers.
(4)(3)For an unbundled customer, ensure that charges generally included in the generation component of the unbundled customers consolidated bill are assessed separately from charges generally included in the transmission and distribution components of the as a separate line item on the unbundled customers bill.
(c)An electrical corporation tariff In establishing the transmission and distribution tariffs, the commission shall incorporate all do both of the following criteria: following:
(1)For customers taking generation services from the electrical corporation, the electrical corporation tariff shall assign participating customers any unique wholesale energy costs, including ancillary and reliability services costs attributable to rapid fluctuations in demand by the participating customer.(1)Ensure the transmission and distribution tariffs are consistent with subdivision (b).
(2)The electrical corporation tariff shall include Ensure a reasonable share of the costs relating to wildfire mitigation, wildfire liability, electrification and environmental programs, and other societal cost obligations typically collected from distribution-level ratepayers.
(d)In establishing the generation tariff, the commission shall do all of the following:
(1)Ensure the generation tariff is consistent with subdivision (b).
(2)Ensure the procurement of generation resources that support a load-serving entitys ability to meet procurement requirements set forth by the commission, the clean energy targets set forth in Sections 399.15 and 454.52, and other state clean energy policies.
(3)Ensure the generation tariff assigns a participating customer any unique wholesale energy costs, including ancillary and reliability service costs attributable to rapid fluctuations in demand by the participating customer.
(3)(4)(A)A Require a participating customer shall to prefund a contract of at least 15 10 years in duration through an electrical corporation, community choice aggregator, or electric service provider for the installation of new, incremental, zero-carbon energy resources sufficient to do both of the following: a load-serving entity for the costs of procurement necessary to serve the participating customer. The procurement of resources to serve the participating customer shall be consistent with paragraph (2).
(i)Provide at least 50 percent of the participating customers hourly energy needs.(ii)Provide dispatchable reliability assets within the electrical corporations, community choice aggregators, or electric service providers service territory.(B)A Authorize a participating customer may meet to reduce the requirement to prefund the installation of those energy resources a contract by installing comparable energy resources zero-emission resources behind its meter. The use of this onsite generation to meet the criteria of this paragraph shall be limited to zero-emission resources. meter, as determined by the load-serving entity.
(4)A participating customer shall participate in a new demand response program authorized by the commission that does not result in any net costs to a nonparticipating customer and supports load shifting, reliability, resource adequacy, and greenhouse gas emission reduction objectives.(5)The interconnection provisions of the electrical corporation tariff shall do all of the following:(e)In establishing the interconnection tariff, the commission shall do all of the following:
(1)Ensure the interconnection tariff is consistent with subdivision (b).
(A)(2)Require a participating customer that submits an application for interconnection of a facility data center to an electrical corporation to disclose whether an application for the same facility data center has been submitted in other electrical corporation service territories or other jurisdictions and to disclose each instance in which an application for the same facility data center has been submitted.
(B)(3)Assign cost responsibility for all transmission facility upgrades triggered by a new facility interconnection to the applicable participating customer. To the extent permitted under federal law, these costs should include shared transmission grid network upgrades needed to accommodate the interconnection of the participating customers facility or increase the flow of electricity across the electrical grid.
(C)(4)Allow a participating customer to receive refunds of a portion of its initial nominal dollar contributions to interconnection costs only to the extent that actual annual net revenues received by the electrical corporation cover the costs of energization, the costs of providing electrical service, and other costs allocated by the commission to the participating customer. On an annual basis, the refund shall not be more than 75 percent of the annual net transmission revenue received by the electrical corporation from the participating customer. This limitation may delay the timing of the full recovery of refunds by the participating customer.
(D)(5)For a participating customer, require an early termination fee to be assessed against a participating customer that departs the electrical system within 15 10 years of the initial interconnection of the facility or fails to achieve full adequate load ramp up. up, as determined by the commission. The early termination fee should not be less than the revenue gap associated with the originally projected demand and energy consumption of the facility over the minimum 15-year 10-year term.
(6)(f)A participating customer shall certify to the commission that its facility meets the requirements of subdivisions (a) and (b) of Section 25545.3.3 of, and subdivisions (a) to (e), inclusive, of Section 25545.3.5 of, the Public Resources Code, notwithstanding the definition of covered project in Section 25545.3 of the Public Resources Code.
(d)Each(g)The commission shall require each electrical corporation shall be required to publish and update maps showing locations where participating customers can interconnect without the need for significant, costly, and time-consuming transmission upgrades.
(e)(h)This section does not modify the limits on direct transactions established pursuant to Section 365.1.
(i)This section does not authorize the commission to regulate the rates or terms and conditions of service offered by a community choice aggregator, consistent with Section 366.2, or an electric service provider, consistent with Section 394.
8543.A participating customer shall participate in a new demand response program authorized by the commission that does not result in any net costs to a nonparticipating customer and supports load shifting, reliability, resource adequacy, and greenhouse gas emission reduction objectives.
8544.This chapter does not limit or restrict the ability of a data center to receive generation services from an electric service provider or community choice aggregator. Generation services provided to a data center by an electric service provider or community choice aggregator shall meet the requirements specified in subdivision (d) of Section 8542.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
This chapter shall be known, and may be cited, as the California Technology Innovation and Ratepayer Protection Act.
8541.For purposes of this chapter, all of the following definitions apply:
(a)(1)Data center means a facility that primarily contains electronic equipment used to process, store, and transmit digital information, which may be a free-standing structure or a facility within a larger structure, that uses environmental control equipment to maintain the proper conditions for the operation of electronic equipment. equipment, except as specified in paragraph (2).
(2)Data center does not include a publicly funded research facility, public safety facility, national security facility, publicly owned facility, or other utility facility, including, but not limited to, an asset of a facilities-based telecommunications provider.
(b)Electrical corporation has the same meaning as defined in Section 218.
(c)Electrical corporation tariff means an electrical corporation tariff included as part of the rate structure established pursuant to subdivision (a) of Section 8542.
(d)Facility means a physical property, a plant, a building, a structure, a source, or stationary equipment, located on one or more contiguous or adjacent properties in actual physical contact or separated solely by a public roadway or public right-of-way and under common ownership or common control.
(e)Local publicly owned electric utility has the same meaning as defined in Section 224.3.(f)(e)Nonparticipating customer means a customer who does not receive electrical service pursuant to an electrical corporation tariff.
(g)(f)(1)Participating customer means a customer who receives electrical service pursuant to an electrical corporation tariff.
(2)For the purpose of the interconnection components of an electrical corporation tariff, participating customer means a data center taking transmission level electrical service with an estimated peak demand of at least 25 megawatts. For the other components of an electrical corporation tariff, the commission shall determine an appropriate minimum peak demand for participating customers, not to exceed 25 megawatts, that considers the extent to which facility load has a material impact on electrical corporation costs.
(3)Participating customer does not include a publicly funded research facility, public safety facility, national security facility, publicly owned facility, and other utility facility, including, but not limited to, an asset of a facilities-based telecommunications provider.
(h)(g)Unbundled customer means a customer receiving the generation component of their electrical service from an entity that is different from the entity providing the transmission and distribution components of the customers electrical service.
8542.(a)On or before July 1, 2027, the commission shall establish a rate structure that includes an electrical corporation tariff for the interconnection of participating customer facilities and the provision of transmission, distribution, and generation services to participating customers.
(b)The commission, as part of establishing an electrical corporation tariff, shall do, at a minimum, all of the following:
(1)Establish eligibility criteria for participating customers. The interconnection components of an electrical corporation tariff shall only apply to a facility for which a new transmission interconnection agreement is established after the establishment of the rate structure pursuant to this chapter by the commission or after a later date specified by the commission.
(2)Evaluate the risks and benefits of an electrical corporation tariff to nonparticipating customers.
(3)Ensure that an electrical corporation tariff prevents the creation of stranded costs for, or cost shifts to, nonparticipating customers.
(4)For an unbundled customer, ensure that charges generally included in the generation component of the customers bill are assessed separately from charges generally included in the transmission and distribution components of the customers bill.
(c)An electrical corporation tariff shall incorporate all of the following criteria:
(1)For customers taking generation services from the electrical corporation, the electrical corporation tariff shall assign participating customers any unique wholesale energy costs, including ancillary and reliability services costs attributable to rapid fluctuations in demand by the participating customer.
(2)The electrical corporation tariff shall include a reasonable share of the costs relating to wildfire mitigation, wildfire liability, electrification and environmental programs, and other societal cost obligations typically collected from distribution-level ratepayers.
(3)(A)A participating customer shall prefund a contract of at least 15 years in duration through an electrical corporation, community choice aggregator, or electric service provider for the installation of new, incremental, zero-carbon energy resources sufficient to do both of the following:
(i)Provide at least 50 percent of the participating customers hourly energy needs.
(ii)Provide dispatchable reliability assets within the electrical corporations, community choice aggregators, or electric service providers service territory.
(B)A participating customer may meet the requirement to prefund the installation of those energy resources by installing comparable energy resources behind its meter. The use of this onsite generation to meet the criteria of this paragraph shall be limited to zero-emission resources.
(4)A participating customer shall participate in a new demand response program authorized by the commission that does not result in any net costs to a nonparticipating customer and supports load shifting, reliability, resource adequacy, and greenhouse gas emission reduction objectives.
(5)The interconnection provisions of the electrical corporation tariff shall do all of the following:
(A)Require a participating customer that submits an application for interconnection of a facility to an electrical corporation to disclose whether an application for the same facility has been submitted in other electrical corporation service territories or other jurisdictions and to disclose each instance in which an application for the same facility has been submitted.
(B)Assign cost responsibility for all transmission facility upgrades triggered by a new facility interconnection to the applicable participating customer. To the extent permitted under federal law, these costs should include shared transmission grid network upgrades needed to accommodate the interconnection of the participating customers facility or increase the flow of electricity across the electrical grid.
(C)Allow a participating customer to receive refunds of a portion of its initial nominal dollar contributions to interconnection costs only to the extent that actual annual net revenues cover the costs of energization, the costs of providing electrical service, and other costs allocated by the commission to the participating customer. On an annual basis, the refund shall not be more than 75 percent of the annual net revenue received by the electrical corporation from the participating customer. This limitation may delay the timing of the full recovery of refunds by the participating customer.
(D)For a participating customer, require an early termination fee to be assessed against a participating customer that departs the electrical system within 15 years of the initial interconnection of the facility or fails to achieve full load ramp up. The early termination fee should not be less than the revenue gap associated with the originally projected demand and energy consumption of the facility over the minimum 15-year term.
(6)A participating customer shall certify to the commission that its facility meets the requirements of subdivisions (a) and (b) of Section 25545.3.3 of, and subdivisions (a) to (e), inclusive, of Section 25545.3.5 of, the Public Resources Code, notwithstanding the definition of covered project in Section 25545.3 of the Public Resources Code.
(d)Each electrical corporation shall be required to publish and update maps showing locations where participating customers can interconnect without the need for significant, costly, and time-consuming transmission upgrades.
(e)This section does not modify the limits on direct transactions established pursuant to Section 365.1.
8543.A local publicly owned electric utility is encouraged, before connecting a facility to the electrical grid, to develop a tariff that is similar to an electrical corporation tariff and ensures all of the following:(a)The costs are not shifted from a customer that is subject to the tariff of a local publicly owned electric utility to a customer that is not subject to that tariff.(b)The costs of investments in infrastructure made by a customer that is subject to the tariff of a local publicly owned electric utility are not recoverable from other customers that are not subject to that tariff.(c)Each customer that is subject to the tariff of a local publicly owned electric utility certifies to the local publicly owned electric utility that its facility meets the requirements of subdivisions (a) and (b) of Section 25545.3.3 of, and subdivisions (a) to (e), inclusive, of Section 25545.3.5 of, the Public Resources Code, notwithstanding the definition of covered project in Section 25545.3 of the Public Resources Code.SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
This chapter shall be known, and may be cited, as the California Technology Innovation and Ratepayer Protection Act.
8541.For purposes of this chapter, all of the following definitions apply:
(a)Data center means a facility that primarily contains electronic equipment used to process, store, and transmit digital information, which may be a free-standing structure or a facility within a larger structure, that uses environmental control equipment to maintain the proper conditions for the operation of electronic equipment.
(a)(b)Electrical corporation has the same meaning as defined in Section 218.
(b)Large load customer means a customer connecting transmission-level electricity service with an estimated peak demand of at least 75 megawatts. Large load customer excludes an existing customer that introduces a new load as a result of switching from fossil fuels to renewable fuels or transportation electrification activities.(c)Electrical corporation tariff means an electrical corporation tariff included as part of the rate structure established pursuant subdivision (a) of Section 8542.
(d)Facility means a physical property, a plant, a building, a structure, a source, or stationary equipment, located on one or more contiguous or adjacent properties in actual physical contact or separated solely by a public roadway or public right-of-way and under common ownership or common control.
(c)(e)Local publicly owned electric utility has the same meaning as defined in Section 224.3.
(d)(f)Nonparticipating customer means a customer who does not receive electrical service pursuant to the an electrical corporation tariff established or modified pursuant to subdivision (a) of Section 8542. tariff.
(e)(g)(1)Participating customer means a customer who receives electrical service pursuant to the an electrical corporation tariff established or modified pursuant to subdivision (a) of Section 8542. tariff.
(2)For the purpose of the interconnection components of an electrical corporation tariff, participating customer means a data center taking transmission level electrical service with an estimated peak demand of at least 25 megawatts. For the other components of an electrical corporation tariff, the commission shall determine an appropriate minimum peak demand for participating customers, not to exceed 25 megawatts, that considers the extent to which facility load has a material impact on electrical corporation costs.
(3)Participating customer does not include a publicly funded research facility, public safety facility, national security facility, publicly owned facility, and other utility facility, including, but not limited to, an asset of a facilities-based telecommunications provider.
(h)Unbundled customer means a customer receiving the generation component of their electrical service from an entity that is different from the entity providing the transmission and distribution components of the customers electrical service.
8542.(a)On or before July 1, 2027, the commission shall establish or modify, in a rulemaking or in an electrical corporation specific application, a rate structure that includes an electrical corporation tariff for the interconnection of participating customer facilities and the provision of transmission, distribution, and generation services to participating customers.
(b)The commission, as part of establishing or modifying the electrical corporation an electrical corporation tariff, shall do, at a minimum, all of the following:
(1)Establish eligibility criteria for large load customers and facilities. participating customers. The interconnection components of an electrical corporation tariff shall only apply to a facility for which a new transmission interconnection agreement is established after the establishment of the rate structure pursuant to this chapter by the commission or after a later date specified by the commission.
(2)Evaluate the risks and benefits of this an electrical corporation tariff to nonparticipating customers.
(3)Ensure that the an electrical corporation tariff prevents the creation of stranded costs for, or cost shifts to, nonparticipating customers.
(4)For an unbundled customer, ensure that charges generally included in the generation component of the customers bill are assessed separately from charges generally included in the transmission and distribution components of the customers bill.
(c)The An electrical corporation tariff shall incorporate all of the following criteria:
(1)For customers taking generation services from the electrical corporation, the electrical corporation tariff shall assign participating customers any unique wholesale energy costs, including ancillary and reliability services costs attributable to rapid fluctuations in demand by the participating customer.
(2)The electrical corporation tariff shall include a reasonable share of the costs relating to wildfire mitigation, wildfire liability, electrification and environmental programs, and other societal cost obligations typically collected from distribution-level ratepayers.
(3)(A)A participating customer shall prefund a contract of at least 15 years in duration through an electrical corporation, community choice aggregator, or electric service provider for the installation of new, incremental, zero-carbon energy resources sufficient to do both of the following:
(i)Provide at least 50 percent of the participating customers hourly energy needs.
(ii)Provide dispatchable reliability assets within the electrical corporations, community choice aggregators, or electric service providers service territory.
(B)A participating customer may meet the requirement to prefund the installation of those energy resources by installing comparable energy resources behind its meter. The use of this onsite generation to meet the criteria of this paragraph shall be limited to zero-emission resources.
(4)A participating customer shall participate in a new demand response program authorized by the commission that does not result in any net costs to nonparticipating customer and supports load shifting, reliability, resource adequacy, and greenhouse gas emission reduction objectives.
(3)(5)The interconnection provisions of the electrical corporation tariff shall do all of the following:
(A)Require a large load participating customer that submits an application for interconnection of a facility to an electrical corporation to disclose whether an application for the same facility has been submitted in other electrical corporation service territories or other jurisdictions and to disclose each instance in which an application for the same facility has been submitted.
(B)Assign cost responsibility for all transmission facility upgrades triggered by a new facility interconnection to the applicable participating customer. To the extent permitted under federal law, these costs should include shared transmission grid network upgrades needed to accommodate the interconnection of the participating customers facility or increase the flow of electricity across the electrical grid.
(C)Allow a participating customer to receive refunds of a portion of its initial nominal dollar contributions to interconnection costs only to the extent that actual annual net revenues cover the costs of energization, the costs of providing electrical service, and other costs allocated by the commission to the participating customer. An annual On an annual basis, the refund shall not be more than 75 percent of the annual net revenue received by the electrical corporation from the participating customer. This limitation may delay the timing of the full recovery of refunds by the participating customer.
(D)Require For a participating customer, require an early termination fee to be assessed against any a participating customer that departs the electrical system within 15 years of the initial interconnection of the facility or fails to achieve full load ramp up. The early termination fee should not be less than the revenue gap associated with the originally projected demand and energy consumption of the facility over the minimum 15-year term.
(4)Each participating customer shall be required to install onsite zero-carbon energy storage with at least four hours of capacity at no less than 50 percent of forecasted peak demand. Storage capacity shall be dispatchable by the electrical corporation or Independent System Operator to address emergency conditions on the electrical grid.(5)Each participating customer shall participate in existing demand response programs authorized by the commission, including participation through third-party aggregators, as determined by the commission. The use of onsite generation to meet the requirements of a demand response program that is subject to this paragraph shall be limited to zero emission resources.(6)Each A participating customer shall certify to the commission that its facility meets the requirements of subdivisions (a) and (b) of Section 25545.3.3 of, and subdivisions (a) to (e), inclusive, of Section 25545.3.5 of, the Public Resources Code, notwithstanding the definition of covered project in Section 25545.3 of the Public Resources Code.
(d)Each electrical corporation shall be required to publish and update maps showing locations where large load participating customers can interconnect without the need for significant, costly, and time-consuming transmission upgrades.
(e)This section does not modify the limits on direct transactions established pursuant to Section 365.1.
8543.A local publicly owned electric utility is encouraged, before connecting a facility to the electrical grid, to develop a tariff that is similar to the an electrical corporation tariff established or modified pursuant to subdivision (a) of Section 8542 and ensures all of the following:
(a)The costs are not shifted from a large load customer that is subject to the tariff to a large load a customer that is subject to the tariff of a local publicly owned electric utility to a customer that is not subject to the that tariff.
(b)The costs of investments in infrastructure made by a large load customer that is subject to the tariff of a local publicly owned electric utility are not recoverable from other nonparticipating ratepayers. customers that are not subject to that tariff.
(c)Each participating ratepayer customer that is subject to the tariff of a local publicly owned electric utility certifies to the local publicly owned electric utility that its facility meets the requirements of subdivisions (a) and (b) of Section 25545.3.3 of, and subdivisions (a) to (e), inclusive, of Section 25545.3.5 of, the Public Resources Code, notwithstanding the definition of covered project in Section 25545.3 of the Public Resources Code.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
This chapter shall be known, and may be cited, as the California Technology Innovation and Ratepayer Protection Act.
8541.For purposes of this chapter, all of the following definitions apply:
(a)Electrical corporation has the same meaning as defined in Section 218.
(b)Large load customer means a customer connecting transmission-level electricity service with an estimated peak demand of at least 75 megawatts. Large load customer excludes an existing customer that introduces a new load as a result of switching from fossil fuels to renewable fuels or transportation electrification activities.
(c)Local publicly owned electric utility has the same meaning as defined in Section 224.3.
(d)Nonparticipating customer means a customer who does not receive electrical service pursuant to the electrical corporation tariff established or modified pursuant to subdivision (a) of Section 8542.
(e)Participating customer means a customer who receives electrical service pursuant to the electrical corporation tariff established or modified pursuant to subdivision (a) of Section 8542.
8542.(a)On or before July 1, 2027, the commission shall establish or modify, in a rulemaking or in an electrical corporation specific application, an electrical corporation tariff for the interconnection of participating customer facilities and the provision of transmission, distribution, and generation services to participating customers.
(b)The commission, as part of establishing or modifying the electrical corporation tariff, shall do, at a minimum, all of the following:
(1)Establish eligibility criteria for large load customers and facilities.
(2)Evaluate the risks and benefits of this tariff to nonparticipating ratepayers. customers.
(3)Ensure that the tariff prevents the creation of stranded costs for, or cost shifts to, nonparticipating ratepayers. customers.
(c)The electrical corporation tariff shall incorporate all of the following criteria:
(1)The For customers taking generation services from the electrical corporation, the electrical corporation tariff shall assign participating customers any unique wholesale energy costs, including ancillary and reliability services costs attributable to rapid fluctuations in demand by the participating customer.
(2)The electrical corporation tariff shall include a reasonable share of the costs relating to wildfire mitigation, wildfire liability, electrification and environmental programs, and other societal cost obligations typically collected from distribution-level ratepayers.
(3)The interconnection provisions of the electrical corporation tariff shall do all of the following:
(A)Require a large load customer that submits an application for interconnection of a facility to an electrical corporation to disclose whether an application for the same facility has been submitted in other electrical corporation service territories or other jurisdictions and to disclose each instance in which an application for the same facility has been submitted.
(B)Assign cost responsibility for all transmission facility upgrades triggered by a facility interconnection to the applicable participating customer. To the extent permitted under federal law, these costs should include shared transmission grid network upgrades needed to accommodate the interconnection of the participating customers facility or increase the flow of electricity across the electrical grid.
(C)Allow a participating customer to receive refunds of a portion of its initial nominal dollar contributions to interconnection costs only to the extent that actual annual net revenues cover the costs of energization, the costs of providing electric electrical service, and other costs allocated by the commission to the participating customer. An annual refund shall not be more than 75 percent of the annual net revenue received by the electrical corporation from the participating customer.
(D)Require an early termination fee to be assessed against any participating customer that departs the electrical system within 15 years of the initial interconnection of the facility or fails to achieve full load ramp up. The early termination fee should not be less than the revenue gap associated with the originally projected demand and energy consumption of the facility over the minimum 15-year term.
(4)Each participating customer shall be required to install onsite zero-carbon energy storage with at least four hours of capacity at no less than 50 percent of forecasted peak demand. Storage capacity shall be dispatchable by the electrical corporation or Independent System Operator to address emergency conditions on the electrical grid.
(5)Each participating customer shall participate in existing demand response programs authorized by the commission, including participation through third-party aggregators, as determined by the commission. The use of onsite generation to meet the requirements of a demand response program that is subject to this paragraph shall be limited to zero emission resources.
(6)Each participating customer shall certify to the commission that its facility meets the requirements of subdivisions (a) and (b) of Section 25545.3.3 of, and subdivisions (a) to (e), inclusive, of Section 25545.3.5 of, the Public Resources Code, notwithstanding the definition of covered project in Section 25545.3 of the Public Resources Code.
(d)Each electrical corporation shall be required to publish and update maps showing locations where large load customers can interconnect without the need for significant, costly, and time-consuming transmission upgrades.
8543.A local publicly owned electric utility is encouraged, before connecting a facility to the electrical grid, to develop a tariff that is similar to the electrical corporation tariff established or modified pursuant to subdivision (a) of Section 8542 and ensures both all of the following:
(a)The costs are not shifted from a large load customer that is subject to the tariff to a large load customer that is not subject to the tariff.
(b)The costs of investments in infrastructure made by a large load customer that is subject to the tariff are not recoverable from other nonparticipating ratepayers.
(c)Each participating ratepayer certifies to the local publicly owned electric utility that its facility meets the requirements of subdivisions (a) and (b) of Section 25545.3.3 of, and subdivisions (a) to (e), inclusive, of Section 25545.3.5 of, the Public Resources Code, notwithstanding the definition of covered project in Section 25545.3 of the Public Resources Code.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
This chapter shall be known, and may be cited, as the California Technology Innovation and Ratepayer Protection Act.
8541.For purposes of this chapter, all of the following definitions apply:
(a)Electrical corporation has the same meaning as defined in Section 218.
(b)Large load customer means a customer connecting transmission-level electricity service with an estimated peak demand of at least 75 megawatts. Large load customer excludes an existing customer that introduces a new load as a result of switching from fossil fuels to renewable fuels or transportation electrification activities.
(c)Local publicly owned electric utility has the same meaning as defined in Section 224.3.
(d)Nonparticipating customer means a customer who does not receive electrical service pursuant to the electrical corporation tariff established or modified pursuant to subdivision (a) of Section 8542.
(e)Participating customer means a customer who receives electrical service pursuant to the electrical corporation tariff established or modified pursuant to subdivision (a) of Section 8542.
8542.(a)On or before July 1, 2027, the commission shall establish or modify, in a rulemaking or in an electrical corporation specific application, an electrical corporation tariff for the interconnection of participating customer facilities and the provision of transmission, distribution, and generation services to participating customers.
(b)The commission, as part of establishing or modifying the electrical corporation tariff, shall do, at a minimum, all of the following:
(1)Establish eligibility criteria for large load customers and facilities.
(2)Evaluate the risks and benefits of this tariff to nonparticipating ratepayers.
(3)Ensure that the tariff prevents the creation of stranded costs for, or cost shifts to, nonparticipating ratepayers.
(c)The electrical corporation tariff shall incorporate all of the following criteria:
(1)The electrical corporation tariff shall assign participating customers any unique wholesale energy costs, including ancillary and reliability services costs attributable to rapid fluctuations in demand by the participating customer.
(2)The electrical corporation tariff shall include a reasonable share of the costs relating to wildfire mitigation, wildfire liability, electrification and environmental programs, and other societal cost obligations typically collected from distribution-level ratepayers.
(3)The interconnection provisions of the electrical corporation tariff shall do all of the following:
(A)Require a large load customer that submits an application for interconnection of a facility to an electrical corporation to disclose whether an application for the same facility has been submitted in other electrical corporation service territories or other jurisdictions and to disclose each instance in which an application for the same facility has been submitted.
(B)Assign cost responsibility for all transmission facility upgrades triggered by a facility interconnection to the applicable participating customer. To the extent permitted under federal law, these costs should include shared transmission grid network upgrades needed to accommodate the interconnection of the participating customers facility or increase the flow of electricity across the electrical grid.
(C)Allow a participating customer to receive refunds of a portion of its initial nominal dollar contributions to interconnection costs only to the extent that actual annual net revenues cover the costs of energization, the costs of providing electric service, and other costs allocated by the commission to the participating customer.
(D)Require an early termination fee to be assessed against any participating customer that departs the electrical system within 15 years of the initial interconnection of the facility or fails to achieve full load ramp up. The early termination fee should not be less than the revenue gap associated with the originally projected demand and energy consumption of the facility over the minimum 15-year term.
(4)Each participating customer shall be required to install onsite zero-carbon energy storage with at least four hours of capacity at no less than 50 percent of forecasted peak demand. Storage capacity shall be dispatchable by the electrical corporation or Independent System Operator to address emergency conditions on the electrical grid.
(5)Each participating customer shall participate in demand response programs as determined by the commission.
(d)Each electrical corporation shall be required to publish and update maps showing locations where large load customers can interconnect without the need for significant, costly, and time-consuming transmission upgrades.
8543.A local publicly owned electric utility is encouraged, before connecting a facility to the electrical grid, to develop a tariff that is similar to the electrical corporation tariff established or modified pursuant to subdivision (a) of Section 8542 and ensures both of the following:
(a)The costs are not shifted from a large load customer that is subject to the tariff to a large load customer that is not subject to the tariff.
(b)The costs of investments in infrastructure made by a large load customer that is subject to the tariff are not recoverable from other nonparticipating ratepayers.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
|
Date
|
Status
|
|---|---|
| Sep 21, 2026 | Chaptered by Secretary of State. Chapter 438, Statutes of 2026. |
| Sep 21, 2026 | Approved by the Governor. |
| Sep 9, 2026 | Enrolled and presented to the Governor at 2 p.m. |
| Aug 31, 2026 | Assembly amendments concurred in. (Ayes 28. Noes 10.) Ordered to engrossing and enrolling. |
| Aug 31, 2026 | Unanimous consent granted to take up without reference to file. |
| Aug 31, 2026 | In Senate. Concurrence in Assembly amendments pending. |
| Aug 31, 2026 | Read third time. Passed. (Ayes 62. Noes 7. Page 7065.) Ordered to the Senate. |
| Aug 31, 2026 | Read third time. Passed. Ordered to the Senate. |
| Aug 28, 2026 | Joint Rule 61(b)(16) suspended. (Ayes 57. Noes 1. Page 6819.) |
| Aug 28, 2026 | Ordered to third reading. |
| Aug 28, 2026 | Read third time and amended. |
| Aug 28, 2026 | Joint Rule 61(b)(16) suspended. |
| Aug 13, 2026 | Read second time. Ordered to third reading. |
| Aug 13, 2026 | From committee: Do pass. (Ayes 12. Noes 2.) (August 13). |
| Aug 13, 2026 | Coauthors revised. |
| Aug 13, 2026 | Assembly Rule 63 suspended. |
| Aug 5, 2026 | August 5 set for first hearing. Placed on suspense file. |
| Jul 2, 2026 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on APPR. |
| Jun 29, 2026 | Read second time and amended. Re-referred to Com. on APPR. |
| Jun 25, 2026 | From committee: Do pass as amended and re-refer to Com. on APPR. (Ayes 14. Noes 0.) (June 24). |
| Jun 10, 2026 | June 10 hearing postponed by committee. |
| Jun 1, 2026 | Referred to Com. on U. & E. |
| May 26, 2026 | In Assembly. Read first time. Held at Desk. |
| May 26, 2026 | Read third time. Passed. (Ayes 28. Noes 8. Page 4446.) Ordered to the Assembly. |
| May 26, 2026 | Read third time. Passed. (Ayes 28. Noes 8.) Ordered to the Assembly. |
| May 18, 2026 | Read second time. Ordered to third reading. |
| May 14, 2026 | From committee: Do pass as amended. (Ayes 5. Noes 2. Page 4255.) (May 14). |
| May 14, 2026 | Read second time and amended. Ordered to second reading. |
| May 14, 2026 | From committee: Do pass as amended. (Ayes 5. Noes 2.) (May 14). |
| May 8, 2026 | Set for hearing May 14. |
| Apr 13, 2026 | April 13 hearing: Placed on APPR. suspense file. |
| Mar 27, 2026 | Set for hearing April 13. |
| Mar 25, 2026 | Read second time and amended. Re-referred to Com. on APPR. |
| Mar 24, 2026 | From committee: Do pass as amended and re-refer to Com. on APPR. (Ayes 12. Noes 4. Page 3588.) (March 17). |
| Mar 24, 2026 | From committee: Do pass as amended and re-refer to Com. on APPR. (Ayes 12. Noes 4.) (March 17). |
| Mar 9, 2026 | Set for hearing March 17. |
| Mar 5, 2026 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on E., U & C. |
| Feb 11, 2026 | Referred to Com. on E., U & C. |
| Jan 14, 2026 | From printer. May be acted upon on or after February 13. |
| Jan 13, 2026 | Introduced. Read first time. To Com. on RLS. for assignment. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Aug 31, 2026 | W/O REF. TO FILE SB886 Padilla | Senate Floor |
Passed |
|
| Aug 31, 2026 | SB 886 Padilla Senate Third Reading By Papan | Assembly Floor |
Passed |
|
| Aug 13, 2026 | Do pass. | Assembly Standing Committee on Appropriations |
Passed |
|
| Jun 24, 2026 | Do pass as amended and be re-referred to the Committee on [Appropriations] | Assembly Standing Committee on Utilities and Energy |
Passed |
|
| May 26, 2026 | Senate 3rd Reading SB886 Padilla et al. | Senate Floor |
Passed |
|
| May 14, 2026 | Do pass as amended | Senate Standing Committee on Appropriations |
Passed |
|
| Apr 13, 2026 | Placed on suspense file | Senate Standing Committee on Appropriations |
Passed |
|
| Mar 17, 2026 | Do pass as amended, but first amend, and re-refer to the Committee on [Appropriations] | Senate Standing Committee on Energy, Utilities and Communications |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| 21 Individuals | ** Support | |
| 350 Humboldt, Grassroots Climate Action | ** Support | |
| AARP | ** Support | |
| African American Chamber of Commerce | ** Support | |
| Bay Area Council | ** Against | |
| Bay Front Chamber of Commerce | ** Support | |
| Biancoverde Restaurant | ** Support | |
| Bloom Energy | ** Against | |
| brawley chamber of commerce | ** Support | |
| Brightline Defense | ** Support | |
| Brightline Defense, if amended | ** Support | |
| Building Owners and Managers Association of California | ** Against | |
| CalAsian Chamber of Commerce | ** Against | |
| California African American Chamber Of Commerce | ** Against | |
| California Business Properties Association | ** Against | |
| California Chamber Of Commerce | ** Against | |
| California Environmental Voters | ** Support | |
| California Hispanic Chamber Of Commerce | ** Against | |
| California Large Energy Consumers Association | ** Against | |
| California Large Energy Consumers Association, unless amended | ** Against | |
| California Manufacturers And Technology Association | ** Against | |
| California Multicultural Business Association | ** Support | |
| California State Association Of Electrical Workers | ** Support | |
| California State Pipe Trades Council | ** Support | |
| Center For Biological Diversity | ** Support | |
| Center on Race, Poverty, and the Environment | ** Support | |
| Central Orange County Democratic Club | ** Support | |
| Central Valley Yemen Society | ** Support | |
| Citizens Climate Lobby Orange County Central Chapter | ** Support | |
| Citizens’ Climate Lobby, Orange County Central Chapter | ** Support | |
| City of Buena Park | ** Support | |
| City of Imperial | ** Support | |
| City of Monterey Park | ** Support | |
| City of Westmorland | ** Support | |
| Clever Community Development | ** Support | |
| Climate Action California | ** Support | |
| Climate Action Campaign | ** Support | |
| Coalition of California Utility Employees | ** Support | |
| Coalition of Filipino American Chamber of Commerce | ** Support | |
| Coalition of Utility Employees | ** Support | |
| College Democrats at UCI | ** Support | |
| College Democrats At UC Irvine | ** Support | |
| Comité de Acción del Valle Inc. | ** Support | |
| Community Action Marin | ** Support | |
| County Of San Diego | ** Support | |
| Data Center Coalition | ** Against | |
| DEMOCRATS OF GREATER IRVINE | ** Support | |
| E2 | ** Support | |
| Earthjustice, if amended | ** Support | |
| Enchanted Rock | ** Against | |
| Fair and Equitable Housing Alliance | ** Support | |
| Filipino American Chamber of Commerce of Greater Los Angeles | ** Support | |
| Filipino American Chamber of Commerce of Greater San Diego | ** Support | |
| Herber Public Utility District | ** Support | |
| Hercules/Rodeo Rotary Club | ** Support | |
| HOM Coffee | ** Support | |
| Imperial; City of | ** Support | |
| Imperial Valley Equity & Justice | ** Support | |
| International Brotherhood of Electrical Workers, Local Union 569 | ** Support | |
| Irvine Valley College Democrats | ** Support | |
| Jesse Miranda Center for Hispanic Leadership | ** Support | |
| Kapor Center Advocacy | ** Support | |
| Kuhn Hay, Inc. | ** Support | |
| Latin Business Association | ** Support | |
| Leadership Council for Justice and Accountability | ** Support | |
| Leadership Council for Justice and Accountability, if amended | ** Support | |
| League Of Women Voters Of California | ** Support | |
| Little Hoover Commission | ** Support | |
| Los Amigos De LA Comunidad, INC. | ** Support | |
| Mainspring Energy | ** Against | |
| Modyn Studios | ** Support | |
| Naiop California | ** Against | |
| National Consumers Law Center | ** Support | |
| Natural Resources Defense Council | ** Support | |
| NET-ZERO CALIFORNIA | ** Support | |
| New Beginnings | ** Support | |
| NextGen California | ** Support | |
| Nrdc Action Fund | ** Support | |
| Orange County Climate Voter Guide | ** Support | |
| Orange County Young Democrats | ** Support | |
| Pacific Gas & Electric Company | ** Against | |
| Refreshed Barbershop | ** Support | |
| Regenesis Health Solutions | ** Support | |
| SanDiego 350 | ** Support | |
| San Diego Gas & Electric | ** Against | |
| Sierra Club California | ** Support | |
| Silicon Valley Leadership Group | ** Against | |
| Sunrise Movement Orange County | ** Support | |
| Sustainable Rossmoor | ** Support | |
| Techca | ** Against | |
| Technet | ** Against | |
| The Utility Reform Network | ** Support | |
| Time in Destiny | ** Support | |
| Two Hundred for Homeownership | ** Support | |
| Union Of Concerned Scientists | ** Support | |
| United Nations Association, Orange County | ** Support | |
| Victoria Homes | ** Support | |
| Western States Council Sheet Metal, Air, Rail And Transportation | ** Support | |
| Western States Petroleum Association | ** Against | |
| Wester States Council of Sheet Metal Workers | ** Support | |
| Women for American Values and Ethics | ** Support | |
| WOMEN FOR AMERICAN VALUES AND ETHICS (WAVE) | ** Support | |
| Women in Business Connections | ** Support |
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-4171 | SB 886 |
UNFINISHED BUSINESS
Bill No: SB 886
Author: Padilla (D) and McNerney (D), et al.
Amended: 8/28/26
Vote: 21
SENATE ENERGY, U. & C. COMMITTEE: 12-4, 3/17/26
AYES: Allen, Archuleta, Arreguín, Becker, Gonzalez, Hurtado, McNerney, Reyes, Richardson, Rubio, Stern, Wahab
NOES: Ochoa Bogh, Dahle, Grove, Strickland
NO VOTE RECORDED: Caballero
SENATE APPROPRIATIONS COMMITTEE: 5-2, 5/14/26
AYES: Cervantes, Cabaldon, Grayson, Richardson, Wahab
NOES: Seyarto, Dahle
SENATE FLOOR: 28-8, 5/26/26
AYES: Allen, Archuleta, Arreguín, Ashby, Becker, Blakespear, Cabaldon, Caballero, Cervantes, Durazo, Grayson, Hurtado, Laird, Limón, McGuire, McNerney, Menjivar, Padilla, Pérez, Reyes, Richardson, Rubio, Smallwood-Cuevas, Stern, Umberg, Wahab, Weber Pierson, Wiener
NOES: Alvarado-Gil, Choi, Grove, Jones, Ochoa Bogh, Seyarto, Strickland, Valladares
NO VOTE RECORDED: Cortese, Dahle, Gonzalez, Niello
ASSEMBLY FLOOR: 62-7, 8/31/26 - See last page for vote
SUBJECT: California Technology Innovation and Ratepayer Protection Act
SOURCE: Net-Zero California
The Utility Reform Network
DIGEST:
This bill requires the California Public Utilities Commission (CPUC) to adopt new tariffs and update existing electric rules to ensure that utility costs for serving data centers are not shifted to other ratepayers. This bill requires the CPUC to adopt a transmission interconnection tariff for data centers seeking retail electric service at the transmission level and specifies requirements this tariff must include. The bill also authorizes tariffed data centers to participate in a demand response program established for data centers by the CPUC. This bill specifies that this demand response program shall not result in any net costs to non-tariffed electric customers.
Assembly Amendments
remove provisions related to generation tariffs and specific generation procurement requirements, shift data centers’ participation in demand response programs from mandatory to permissive, and make various clarifications.
ANALYSIS:
Existing law:
- Authorizes the CPUC to supervise and regulate every public utility in the state and permits the CPUC to do anything that is necessary and convenient to exercise its power and jurisdiction. (Public Utilities Code §701)
- Authorizes the CPUC to set rates for public utilities and specifies that every cost charged by utilities to customers must be just and reasonable. (Public Utilities Code §451)
- Defines an electrical corporation as every corporation or person owning, controlling, operating, or managing any electric plant for compensation within this state, except where electricity is generated on or distributed by the producer through private property solely for its own use or the use of its tenants and not for sale or transmission to others. (Public Utilities Code §218)
- Defines a “retail seller” as an entity engaged in the retail sale of electricity to end-use customers located within the state. This definition expressly includes investor-owned utilities (IOUs), community choice aggregators (CCAs), and energy service providers (ESPs); however, this definition does not include the Department of Water Resources (DWR), publicly owned utilities (POUs), or co-generation facilities. (Public Utilities Code §399.12(j))
- Creates the Renewables Portfolio Standard (RPS) by establishing a state goal of procuring at least 60% of total retail sales of electricity from renewable energy resources by December 31, 2030, with specified benchmarks up to that date. Existing law requires the CPUC to oversee electrical corporations’ compliance with renewable energy procurement mandates and requires the California Energy Commission (CEC) to oversee POU renewable energy procurement compliance. (Public Utilities Code §399.11 et. seq.)
- Establishes a policy to source 100% of all in-state retail electricity sales from zero-carbon resources by December 31, 2045. Existing law requires the CPUC, CEC and the California Air Resources Board (CARB) to incorporate this policy into all relevant plans. (Public Utilities Code §454.53)
- Authorizes the CPUC to assess the extent to which electrical corporation costs for new loads from data centers result in cost shifts to other electrical corporation customers. Existing law specifies that this assessment must be published by January 1, 2027, and it must include the following:
- An analysis of potential electrical corporation costs associated with utility procurement for data center electricity consumption.
- An analysis of potential electrical corporation costs associated with new transmission and distribution assets to serve new data centers or expansions of existing data centers, as specified.
- Identification of opportunities to address any substantial cost shifts. (Public Utilities Code §913.22)
- Establishes an opt-in permitting process at the CEC for certain non-fossil fueled power generation facilities. Existing law specifies certain criteria a facility must meet in order to qualify for this opt-in certification. These criteria include, but are not limited to, meeting certain labor standards for the construction of the facility seeking certification. Existing law specifies requirements regarding the use of a prevailing wage and skilled and trained workforce for opt-in permitting eligibility. (Public Resource Code §25545 et. seq.)
This bill:
- Requires the CPUC to adopt new tariffs and update existing electric rules by January 1, 2028, for the interconnection of data centers and the provision of retail electric service, transmission, distribution, and generation services to those data centers. This bill requires the CPUC to do all the following when adopting new tariffs and updating electric rules pursuant to this bill:
- Evaluate the risks and benefits of this tariff to nonparticipating ratepayers.
- Ensure that the tariff prevents the creation of stranded costs for, or cost shifts to, nonparticipating ratepayers.
- Ensure, for unbundled customers, that costs generally included in the generation component of a customer’s bill are assessed separate from charges generally included in the transmission and distribution components of this bill.
- Requires the CPUC to establish a tariff for the interconnection of a data center seeking to receive retail electric service at the transmission level. This bill specifies that this tariff must comply with the following requirements:
- Require a data center submitting an interconnection application to disclose each instance in which the data center has submitted an application for that facility in other electrical corporation service territories or jurisdictions.
- Assign cost responsibility for all transmission facility upgrades and usage to the tariffed data center. To the extent permitted under federal law, these costs should include shared transmission grid network upgrades needed to accommodate the interconnection of the data center or increase the flow of electricity across the electrical grid.
- Allow a tariffed data center to receive refunds of a portion of its initial nominal dollar contributions to interconnection costs only to the extent that actual annual net revenues cover the costs of energization, the costs of providing electric service, and other costs allocated by the CPUC to the tariffed customer. This bill specifies that refunds must be based on the materialization of the tariffed customer’s load and shall not exceed 75% of the annual transmission revenue received from the tariffed customer.
- Include an early termination fee to be assessed against any tariffed data center that departs the electrical system within 10 years of the initial interconnection of the facility or fails to achieve full load ramp up. The early termination fee should not be less than the revenue gap associated with the originally projected demand and energy consumption of the facility over the minimum 10-year term.
- Specifies that the interconnection tariff required by this bill shall only apply to a data center that enters into a new transmission interconnection agreement on or after January 1, 2027.
- Requires each electrical corporation to publish and update maps showing locations where data centers customers can interconnect without the need for significant, costly, and time-consuming transmission upgrades.
- Requires every data center tariffed under this bill to certify that it meets specified labor requirements generally applied to certain non-fossil fueled power facilities, including prevailing wage and skilled and trained workforce requirements.
- Authorizes a tariffed data center to participate in a new demand response program established by the CPUC to support load shifting, reliability, resource adequacy, and greenhouse gas emission reduction goals. This bill specifies that this demand response program may not result in net costs to other ratepayers.
Background
Rapid data center growth has been linked to ratepayer concerns in a number of states. The growth of data centers – particularly those data centers that support generative artificial intelligence (AI) – is leading to increased energy costs in many US states. This growth is expected to accelerate in the near future. According to a May 2024 report from the CEC, data centers comprise approximately 2% of the state’s total annual electricity demand. The CEC anticipates that data centers’ electricity consumption may double in the next 10 years without implementation of any additional energy efficiency measures. In December 2024, the United States Department of Energy released a report by the Lawrence Berkeley National Laboratory on data centers’ energy use. The report shows that data centers’ electricity use comprised approximately 4.4% of the United States’ total electricity consumption in 2024. The report also estimates that data centers may comprise between 6.7% to 12% of national electricity consumption by 2028.
As electricity demands from data centers increase, grid and utility costs are also increasing. Pennsylvania – New Jersey – Maryland Interconnection (PJM) operates the largest regional grid in the United States. In January 2026, data from PJM indicated that 40% of its expected increased electricity demand will come from data centers. With this increase in electricity demands, PJM has seen record high costs for electricity to meet future reliability needs in addition to new transmission costs. Consumers in four states within PJM territory paid over $4 billion in 2024 alone for transmission projects serving data centers. Currently, the majority of California’s data center load growth has occurred in service territories of local POUs and those of CCAs. However, the IOUs have also seen a recent increase in load growth from data centers and a substantial increase in applications for transmission-level interconnection.
Bill overlaps with ongoing CPUC proceedings. In November 2024, Pacific Gas & Electric (PG&E) filed an application at the CPUC to establish a new electric rule for retail electricity customers seeking interconnection at the transmission level. (Application 24-11-007). According to PG&E’s filings, data centers were 67% of the 34 transmission interconnection applications that PG&E received between 2023 and November 2024. In July 2025, the CPUC issued an initial decision (D. 25-07-039) that approved an interim PG&E electric rule for data centers that pre-pay the cost of interconnection. In February 2026, the CPUC issued a schedule for the next phase of the proceeding to consider additional electric rule requirements for transmission interconnection, including mechanisms for covering utility costs. Certain provisions of this bill overlap with issues that are currently included in the ongoing Rule 30 proceeding. Some provisions also mirror certain provisions of prior CPUC resolutions regarding specific transmission interconnection advice letters. For example, this bill caps at 75% the annual amount that an IOU can re-pay a large-load customer for any advance loan that the customer provides to the IOU to cover costs for the transmission and distribution interconnection. This bill’s limit on repayments is identical to a limit included in a CPUC resolution (E-5420) approving and modifying an advice letter (AL 7569-E) submitted by PG&E regarding the transmission interconnection of a 90 megawatts (MW) data center in San Jose. On April 9, 2026, the CPUC started the process to open a rulemaking (R.26-04-009) on the California Advanced Electric Rate Design. As part of this proceeding the CPUC intends to explore opportunities to address affordability challenges associated with rapid load growth, including load from data centers. The CPUC intends to explore rate designs and tariffs for data center customers to address affordability issues in this proceeding. The CPUC intends to publish a staff proposal on rate reform as part of this proceeding in the 3rd Quarter of 2026. To the extent that the CPUC adopts decisions in the ongoing proceeding that conflict with this bill, this bill may require the CPUC to revise its decisions.
Bill addresses infrastructure costs associated with interconnecting large new data centers. Increasingly, large load data centers are requesting retail electricity service from utilities through transmission interconnections. Transmission upgrades, new infrastructure, and downstream distribution facilities needed to serve these transmission-connected data centers have triggered large costs for other electricity customers, particularly since transmission and distribution costs are assessed to all electricity customers. Unlike distribution interconnections, the CPUC lacks standard rules for interconnecting retail electricity customers to transmission facilities. Transmission interconnection generally requires substantially greater infrastructure installation at much higher costs than those required to connect a customer to distribution lines. For example, a transmission interconnection for a large load generally requires a dedicated substation. Even when new substations may not be required, transmission upgrade costs frequently exceed comparable distribution upgrades. This bill requires the CPUC to establish a tariff that ensures that data centers interconnecting at the transmission level pay for the transmission infrastructure installation and upgrades required to serve those data centers. By prohibiting electrical corporations from shifting any of these costs associated with data centers’ transmission interconnection to other ratepayers, this bill would prevent California ratepayers from experiencing the large transmission infrastructure-related cost shifts experienced in other states.
Getting the most from large megawatts. This bill authorizes a tariffed data center to participate in a demand response program created by the CPUC for data centers, provided that the demand response program does not increase costs for other ratepayers and helps achieve environmental and grid benefits. A number of stakeholders, including utilities and research institutions, are identifying and developing mechanisms to support more demand responsive large loads that can respond to grid conditions and lower procurement costs. On June 22, 2026, the CEC approved grants for more than $21 million from the Electric Program Investment Charge to fund projects – including a project to develop of a flexible data center load capacity tool – to support beneficial electrification while increasing grid capacity and flexibility. Beneficial electrification can occur with large loads interconnecting in locations where excess capacity exists on the grid. Increasingly policymakers are seeking mechanisms to use large MW procurements for these beneficial electrification projects to lower overall electricity rates. The CPUC’s Public Advocate’s Office states the following regarding beneficial electrification’s potential for ratepayer benefits:
Expanding electrification can lower the average cost of electricity, provided it does not strain the system in ways that compromise reliability or require expensive upgrades. Policies should promote “beneficial electrification,” by considering when and where energy is used to maintain safety, system reliability, control costs, and prevent inequities.
Beneficial electrification necessarily requires a large load to interconnect and take service at a specific location in coordination with the electric utility. Large loads that interconnect in locations that do not have excess capacity can exacerbate rate impacts by straining already limited resources. Data centers’ need for a continuous electricity supply poses unique challenges to creating tariffs that encourage large load flexibility. To the extent that data centers locate in areas without excess capacity, this continuous demand can increase net peak load when electricity costs are highest, a larger mix of the supply is generated from fossil fuels, and where shortages are most likely to occur. Other large loads may be able to more readily adopt demand response technologies to the extent that they do not need a similar continuous supply of electricity from the grid.
Bill is linked to AB 2383 (Zbur), of the current legislative session. Both this bill and AB 2383 require the CPUC to establish tariffs to address utility costs associated with data centers. AB 2383 requires the CPUC to establish a transmission and distribution service tariff as well as a generation tariff for data centers. AB 2383 also sets requirements for CCA and ESP generation tariffs. This bill requires the CPUC to establish a transmission interconnection tariff and authorizes the establishment of a demand response program for data centers. This bill also sets CPUC duties when establishing all the data center tariffs in both AB 2383 and SB 886. While SB 886 and AB 2383 are not expressly contingent upon each other, the bills’ requirements do not conflict with each other. Together, SB 886 and AB 2383 establish the California Technology Innovation and Ratepayer Protection Act as a single article in the Public Utilities Code.
Related/Prior Legislation
SB 887 (Padilla, 2026) establishes certain permitting permissions for data centers that meet specified criteria. These criteria include provisions similar to the requirements for the tariff specified in this bill. The bill is pending in the Senate.
SB 978 (Pérez, 2026) would have required the CPUC to create a special rate structure for large data centers prevent cost shifts to other customers. The bill would have established labor requirements for the construction of facilities subject to the bill. The bill would have expanded existing CPUC reporting requirements to include a specified assessment about data center impacts to renewable procurement goals. The bill was held by the Senate Appropriations Committee.
AB 2383 (Zbur, 2026) requires the CPUC to establish electrical corporation tariffs by January 1, 2028, for transmission and distribution and generation services for certain data centers. The bill specifies requirements for these tariffs and requires CCAs and ESPs to adopt generation tariffs for data centers that provide protections similar to those required for electrical corporation data center tariffs. The bill is pending in the Senate.
SB 57 (Padilla, Chapter 647, Statutes of 2025) authorized the CPUC to assess the extent to which electrical corporation costs for new loads from data centers result in cost shifts to other electrical corporation customers. The bill also required the CPUC to publish and submit a report regarding its assessment to the relevant legislative policy committees by January 1, 2027.
AB 222 (Bauer-Kahan, 2025) would have required the CPUC to assess the extent to which electrical corporation costs for serving data centers result in cost shifts to other customers. The bill also required the CEC to establish a process for data centers to submit specified energy efficiency data to the CEC, and it required the CEC to assess data centers’ energy consumption. The bill was held by the Senate Appropriations Committee.
SB 1298 (Cortese, 2024) would have increased the amount of thermal generation a data center could use as backup power from 100 MW to 150 MW without triggering the CEC’s power plant siting process. The bill would have also created conditions for data centers to use this exemption. The bill died in the Assembly.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
According to the Assembly Appropriations Committee, the CPUC estimates costs of approximately $1 million annually (Public Utilities Commission Utilities Reimbursement Account) for five positions—four regulatory analysts ($190,000 to $240,000 each, depending on experience and expertise) and one attorney ($267,000)—and roughly $40,000 in training and travel expenses.
SUPPORT: (Verified 8/30/26)
Net-Zero California (co-source)
The Utility Reform Network (co-source)
350 Humboldt, Grassroots Climate Action
AARP
African American Chamber of Commerce
Bay Front Chamber of Commerce
Brawley Chamber of Commerce
Biancoverde Restaurant
Brightline Defense, if amended
California Environmental Voters
California Multicultural Business Association
California State Association of Electrical Workers
California State Pipe Trades Council
Center for Biological Diversity
Central Orange County Democratic Club
Central Valley Yemen Society
Citizens’ Climate Lobby, Orange County Central Chapter
City of Buena Park
City of Imperial
City of Monterey Park
City of Westmorland
Clever Community Development
Climate Action California
Climate Action Campaign
Coalition of California Utility Employees
Coalition of Filipino American Chamber of Commerce
College Democrats at UCI
Comité de Acción del Valle Inc.
Community Action Marin
County of San Diego
Democrats of Greater Irvine
E2
Earthjustice, if amended
Fair and Equitable Housing Alliance
Filipino American Chamber of Commerce of Greater Los Angeles
Filipino American Chamber of Commerce of Greater San Diego
Herber Public Utility District
Hercules/Rodeo Rotary Club
HOM Coffee
Imperial Valley Equity & Justice
International Brotherhood of Electrical Workers, Local Union 569
Irvine Valley College Democrats
Jesse Miranda Center for Hispanic Leadership
Kapor Center Advocacy
Kuhn Hay, Inc.
Latin Business Association
Leadership Council for Justice and Accountability
League of Women Voters of California
Little Hoover Commission
Los Amigos de la Comunidad, Inc.
Modyn Studios
National Consumers Law Center
Natural Resources Defense Council
New Beginnings
NRDC Action Fund
Orange County Climate Voter Guide
Refreshed Barbershop
Regenesis Health Solutions
SanDiego 350
Sierra Club California
Sunrise Movement Orange County
Sustainable Rossmoor
Time in Destiny
Two Hundred for Homeownership
Union of Concerned Scientists
United Nations Association, Orange County
Victoria Homes
Western States Council Sheet Metal, Air, Rail and Transportation
Women for American Values and Ethics
Women in Business Connections
21 Individuals
OPPOSITION: (Verified 8/30/26)
Bay Area Council
Bloom Energy
Building Owners and Managers Association of California
CalAsian Chamber of Commerce
California African American Chamber of Commerce
California Business Properties Association
California Chamber of Commerce
California Hispanic Chamber of Commerce
California Large Energy Consumers Association
California Manufacturers and Technology Association
Data Center Coalition
Enchanted Rock
Mainspring Energy
NAIOP California
Pacific Gas & Electric Company
San Diego Gas & Electric
Silicon Valley Leadership Group
TechCa
TechNet
Western States Petroleum Association
ARGUMENTS IN SUPPORT: According to the Author:
Multiple studies have found data centers increase costs for ordinary ratepayers as they drive skyrocketing demand without corresponding growth in supply. Moreover, these high intensity energy users require expensive infrastructure upgrades that ordinary ratepayers are paying for. Without taking steps to mitigate these cost shifts, rates are estimated to go up 8%. Microsoft, Meta, and Anthropic have stated they will pay for the cost of interconnection to their data centers, and this bill puts these commitments into law.
ARGUMENTS IN OPPOSITION: In opposition, the California Chamber of Commerce states:
California is competing with other states to attract advanced manufacturing, data centers, and other electricity-intensive industries that support economic growth and technological innovation. Policies that impose unusually burdensome infrastructure requirements while also limiting operational control over privately financed energy assets risk discouraging the development of these facilities in California. Grid flexibility and reliability are important goals, but they should be pursued through voluntary programs and market incentives rather than mandates that deter new investment in the state’s electricity system. For these reasons, the California Chamber of Commerce respectfully urges the Legislature to reject SB 886.
ASSEMBLY FLOOR: 62-7, 8/31/26
AYES: Addis, Aguiar-Curry, Ahrens, Alvarez, Arambula, Ávila Farías, Bains, Bauer-Kahan, Bennett, Berman, Boerner, Bonta, Bryan, Calderon, Caloza, Carrillo, Castillo, Connolly, Elhawary, Fong, Gabriel, Garcia, Gipson, Jeff Gonzalez, Mark González, Haney, Harabedian, Hart, Irwin, Jackson, Kalra, Krell, Lee, Lowenthal, McKinnor, Muratsuchi, Nguyen, Ortega, Pacheco, Papan, Patel, Pellerin, Petrie-Norris, Ramos, Ransom, Celeste Rodriguez, Michelle Rodriguez, Rogers, Sanchez, Schiavo, Schultz, Sharp-Collins, Solache, Soria, Stefani, Ta, Valencia, Ward, Wicks, Wilson, Zbur, Rivas
NOES: DeMaio, Dixon, Ellis, Hadwick, Johnson, Macedo, Tangipa
NO VOTE RECORDED: Alanis, Chen, Davies, Flora, Hoover, Lackey, Patterson, Quirk-Silva, Blanca Rubio, Wallis
Prepared by: Sarah Smith / E., U. & C. / (916) 651-4107
9/22/26 12:02:28
**** END ****
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-4171 | SB 886 |
UNFINISHED BUSINESS
Bill No: SB 886
Author: Padilla (D) and McNerney (D), et al.
Amended: 8/28/26
Vote: 21
SENATE ENERGY, U. & C. COMMITTEE: 12-4, 3/17/26
AYES: Allen, Archuleta, Arreguín, Becker, Gonzalez, Hurtado, McNerney, Reyes, Richardson, Rubio, Stern, Wahab
NOES: Ochoa Bogh, Dahle, Grove, Strickland
NO VOTE RECORDED: Caballero
SENATE APPROPRIATIONS COMMITTEE: 5-2, 5/14/26
AYES: Cervantes, Cabaldon, Grayson, Richardson, Wahab
NOES: Seyarto, Dahle
SENATE FLOOR: 28-8, 5/26/26
AYES: Allen, Archuleta, Arreguín, Ashby, Becker, Blakespear, Cabaldon, Caballero, Cervantes, Durazo, Grayson, Hurtado, Laird, Limón, McGuire, McNerney, Menjivar, Padilla, Pérez, Reyes, Richardson, Rubio, Smallwood-Cuevas, Stern, Umberg, Wahab, Weber Pierson, Wiener
NOES: Alvarado-Gil, Choi, Grove, Jones, Ochoa Bogh, Seyarto, Strickland, Valladares
NO VOTE RECORDED: Cortese, Dahle, Gonzalez, Niello
ASSEMBLY FLOOR: Passed, 8/31/26
SUBJECT: California Technology Innovation and Ratepayer Protection Act
SOURCE: Net-Zero California
The Utility Reform Network
DIGEST:
This bill requires the California Public Utilities Commission (CPUC) to adopt new tariffs and update existing electric rules to ensure that utility costs for serving data centers are not shifted to other ratepayers. This bill requires the CPUC to adopt a transmission interconnection tariff for data centers seeking retail electric service at the transmission level and specifies requirements this tariff must include. The bill also authorizes tariffed data centers to participate in a demand response program established for data centers by the CPUC. This bill specifies that this demand response program shall not result in any net costs to non-tariffed electric customers.
Assembly Amendments
remove provisions related to generation tariffs and specific generation procurement requirements, shift data centers’ participation in demand response programs from mandatory to permissive, and make various clarifications.
ANALYSIS:
Existing law:
- Authorizes the CPUC to supervise and regulate every public utility in the state and permits the CPUC to do anything that is necessary and convenient to exercise its power and jurisdiction. (Public Utilities Code §701)
- Authorizes the CPUC to set rates for public utilities and specifies that every cost charged by utilities to customers must be just and reasonable. (Public Utilities Code §451)
- Defines an electrical corporation as every corporation or person owning, controlling, operating, or managing any electric plant for compensation within this state, except where electricity is generated on or distributed by the producer through private property solely for its own use or the use of its tenants and not for sale or transmission to others. (Public Utilities Code §218)
- Defines a “retail seller” as an entity engaged in the retail sale of electricity to end-use customers located within the state. This definition expressly includes investor-owned utilities (IOUs), community choice aggregators (CCAs), and energy service providers (ESPs); however, this definition does not include the Department of Water Resources (DWR), publicly owned utilities (POUs), or co-generation facilities. (Public Utilities Code §399.12(j))
- Creates the Renewables Portfolio Standard (RPS) by establishing a state goal of procuring at least 60% of total retail sales of electricity from renewable energy resources by December 31, 2030, with specified benchmarks up to that date. Existing law requires the CPUC to oversee electrical corporations’ compliance with renewable energy procurement mandates and requires the California Energy Commission (CEC) to oversee POU renewable energy procurement compliance. (Public Utilities Code §399.11 et. seq.)
- Establishes a policy to source 100% of all in-state retail electricity sales from zero-carbon resources by December 31, 2045. Existing law requires the CPUC, CEC and the California Air Resources Board (CARB) to incorporate this policy into all relevant plans. (Public Utilities Code §454.53)
- Authorizes the CPUC to assess the extent to which electrical corporation costs for new loads from data centers result in cost shifts to other electrical corporation customers. Existing law specifies that this assessment must be published by January 1, 2027, and it must include the following:
- An analysis of potential electrical corporation costs associated with utility procurement for data center electricity consumption.
- An analysis of potential electrical corporation costs associated with new transmission and distribution assets to serve new data centers or expansions of existing data centers, as specified.
- Identification of opportunities to address any substantial cost shifts. (Public Utilities Code §913.22)
- Establishes an opt-in permitting process at the CEC for certain non-fossil fueled power generation facilities. Existing law specifies certain criteria a facility must meet in order to qualify for this opt-in certification. These criteria include, but are not limited to, meeting certain labor standards for the construction of the facility seeking certification. Existing law specifies requirements regarding the use of a prevailing wage and skilled and trained workforce for opt-in permitting eligibility. (Public Resource Code §25545 et. seq.)
This bill:
- Requires the CPUC to adopt new tariffs and update existing electric rules by January 1, 2028, for the interconnection of data centers and the provision of retail electric service, transmission, distribution, and generation services to those data centers. This bill requires the CPUC to do all the following when adopting new tariffs and updating electric rules pursuant to this bill:
- Evaluate the risks and benefits of this tariff to nonparticipating ratepayers.
- Ensure that the tariff prevents the creation of stranded costs for, or cost shifts to, nonparticipating ratepayers.
- Ensure, for unbundled customers, that costs generally included in the generation component of a customer’s bill are assessed separate from charges generally included in the transmission and distribution components of this bill.
- Requires the CPUC to establish a tariff for the interconnection of a data center seeking to receive retail electric service at the transmission level. This bill specifies that this tariff must comply with the following requirements:
- Require a data center submitting an interconnection application to disclose each instance in which the data center has submitted an application for that facility in other electrical corporation service territories or jurisdictions.
- Assign cost responsibility for all transmission facility upgrades and usage to the tariffed data center. To the extent permitted under federal law, these costs should include shared transmission grid network upgrades needed to accommodate the interconnection of the data center or increase the flow of electricity across the electrical grid.
- Allow a tariffed data center to receive refunds of a portion of its initial nominal dollar contributions to interconnection costs only to the extent that actual annual net revenues cover the costs of energization, the costs of providing electric service, and other costs allocated by the CPUC to the tariffed customer. This bill specifies that refunds must be based on the materialization of the tariffed customer’s load and shall not exceed 75% of the annual transmission revenue received from the tariffed customer.
- Include an early termination fee to be assessed against any tariffed data center that departs the electrical system within 10 years of the initial interconnection of the facility or fails to achieve full load ramp up. The early termination fee should not be less than the revenue gap associated with the originally projected demand and energy consumption of the facility over the minimum 10-year term.
- Specifies that the interconnection tariff required by this bill shall only apply to a data center that enters into a new transmission interconnection agreement on or after January 1, 2027.
- Requires each electrical corporation to publish and update maps showing locations where data centers customers can interconnect without the need for significant, costly, and time-consuming transmission upgrades.
- Requires every data center tariffed under this bill to certify that it meets specified labor requirements generally applied to certain non-fossil fueled power facilities, including prevailing wage and skilled and trained workforce requirements.
- Authorizes a tariffed data center to participate in a new demand response program established by the CPUC to support load shifting, reliability, resource adequacy, and greenhouse gas emission reduction goals. This bill specifies that this demand response program may not result in net costs to other ratepayers.
Background
Rapid data center growth has been linked to ratepayer concerns in a number of states. The growth of data centers – particularly those data centers that support generative artificial intelligence (AI) – is leading to increased energy costs in many US states. This growth is expected to accelerate in the near future. According to a May 2024 report from the CEC, data centers comprise approximately 2% of the state’s total annual electricity demand. The CEC anticipates that data centers’ electricity consumption may double in the next 10 years without implementation of any additional energy efficiency measures. In December 2024, the United States Department of Energy released a report by the Lawrence Berkeley National Laboratory on data centers’ energy use. The report shows that data centers’ electricity use comprised approximately 4.4% of the United States’ total electricity consumption in 2024. The report also estimates that data centers may comprise between 6.7% to 12% of national electricity consumption by 2028.
As electricity demands from data centers increase, grid and utility costs are also increasing. Pennsylvania – New Jersey – Maryland Interconnection (PJM) operates the largest regional grid in the United States. In January 2026, data from PJM indicated that 40% of its expected increased electricity demand will come from data centers. With this increase in electricity demands, PJM has seen record high costs for electricity to meet future reliability needs in addition to new transmission costs. Consumers in four states within PJM territory paid over $4 billion in 2024 alone for transmission projects serving data centers. Currently, the majority of California’s data center load growth has occurred in service territories of local POUs and those of CCAs. However, the IOUs have also seen a recent increase in load growth from data centers and a substantial increase in applications for transmission-level interconnection.
Bill overlaps with ongoing CPUC proceedings. In November 2024, Pacific Gas & Electric (PG&E) filed an application at the CPUC to establish a new electric rule for retail electricity customers seeking interconnection at the transmission level. (Application 24-11-007). According to PG&E’s filings, data centers were 67% of the 34 transmission interconnection applications that PG&E received between 2023 and November 2024. In July 2025, the CPUC issued an initial decision (D. 25-07-039) that approved an interim PG&E electric rule for data centers that pre-pay the cost of interconnection. In February 2026, the CPUC issued a schedule for the next phase of the proceeding to consider additional electric rule requirements for transmission interconnection, including mechanisms for covering utility costs. Certain provisions of this bill overlap with issues that are currently included in the ongoing Rule 30 proceeding. Some provisions also mirror certain provisions of prior CPUC resolutions regarding specific transmission interconnection advice letters. For example, this bill caps at 75% the annual amount that an IOU can re-pay a large-load customer for any advance loan that the customer provides to the IOU to cover costs for the transmission and distribution interconnection. This bill’s limit on repayments is identical to a limit included in a CPUC resolution (E-5420) approving and modifying an advice letter (AL 7569-E) submitted by PG&E regarding the transmission interconnection of a 90 megawatts (MW) data center in San Jose. On April 9, 2026, the CPUC started the process to open a rulemaking (R.26-04-009) on the California Advanced Electric Rate Design. As part of this proceeding the CPUC intends to explore opportunities to address affordability challenges associated with rapid load growth, including load from data centers. The CPUC intends to explore rate designs and tariffs for data center customers to address affordability issues in this proceeding. The CPUC intends to publish a staff proposal on rate reform as part of this proceeding in the 3rd Quarter of 2026. To the extent that the CPUC adopts decisions in the ongoing proceeding that conflict with this bill, this bill may require the CPUC to revise its decisions.
Bill addresses infrastructure costs associated with interconnecting large new data centers. Increasingly, large load data centers are requesting retail electricity service from utilities through transmission interconnections. Transmission upgrades, new infrastructure, and downstream distribution facilities needed to serve these transmission-connected data centers have triggered large costs for other electricity customers, particularly since transmission and distribution costs are assessed to all electricity customers. Unlike distribution interconnections, the CPUC lacks standard rules for interconnecting retail electricity customers to transmission facilities. Transmission interconnection generally requires substantially greater infrastructure installation at much higher costs than those required to connect a customer to distribution lines. For example, a transmission interconnection for a large load generally requires a dedicated substation. Even when new substations may not be required, transmission upgrade costs frequently exceed comparable distribution upgrades. This bill requires the CPUC to establish a tariff that ensures that data centers interconnecting at the transmission level pay for the transmission infrastructure installation and upgrades required to serve those data centers. By prohibiting electrical corporations from shifting any of these costs associated with data centers’ transmission interconnection to other ratepayers, this bill would prevent California ratepayers from experiencing the large transmission infrastructure-related cost shifts experienced in other states.
Getting the most from large megawatts. This bill authorizes a tariffed data center to participate in a demand response program created by the CPUC for data centers, provided that the demand response program does not increase costs for other ratepayers and helps achieve environmental and grid benefits. A number of stakeholders, including utilities and research institutions, are identifying and developing mechanisms to support more demand responsive large loads that can respond to grid conditions and lower procurement costs. On June 22, 2026, the CEC approved grants for more than $21 million from the Electric Program Investment Charge to fund projects – including a project to develop of a flexible data center load capacity tool – to support beneficial electrification while increasing grid capacity and flexibility. Beneficial electrification can occur with large loads interconnecting in locations where excess capacity exists on the grid. Increasingly policymakers are seeking mechanisms to use large MW procurements for these beneficial electrification projects to lower overall electricity rates. The CPUC’s Public Advocate’s Office states the following regarding beneficial electrification’s potential for ratepayer benefits:
Expanding electrification can lower the average cost of electricity, provided it does not strain the system in ways that compromise reliability or require expensive upgrades. Policies should promote “beneficial electrification,” by considering when and where energy is used to maintain safety, system reliability, control costs, and prevent inequities.
Beneficial electrification necessarily requires a large load to interconnect and take service at a specific location in coordination with the electric utility. Large loads that interconnect in locations that do not have excess capacity can exacerbate rate impacts by straining already limited resources. Data centers’ need for a continuous electricity supply poses unique challenges to creating tariffs that encourage large load flexibility. To the extent that data centers locate in areas without excess capacity, this continuous demand can increase net peak load when electricity costs are highest, a larger mix of the supply is generated from fossil fuels, and where shortages are most likely to occur. Other large loads may be able to more readily adopt demand response technologies to the extent that they do not need a similar continuous supply of electricity from the grid.
Bill is linked to AB 2383 (Zbur), of the current legislative session. Both this bill and AB 2383 require the CPUC to establish tariffs to address utility costs associated with data centers. AB 2383 requires the CPUC to establish a transmission and distribution service tariff as well as a generation tariff for data centers. AB 2383 also sets requirements for CCA and ESP generation tariffs. This bill requires the CPUC to establish a transmission interconnection tariff and authorizes the establishment of a demand response program for data centers. This bill also sets CPUC duties when establishing all the data center tariffs in both AB 2383 and SB 886. While SB 886 and AB 2383 are not expressly contingent upon each other, the bills’ requirements do not conflict with each other. Together, SB 886 and AB 2383 establish the California Technology Innovation and Ratepayer Protection Act as a single article in the Public Utilities Code.
Related/Prior Legislation
SB 887 (Padilla, 2026) establishes certain permitting permissions for data centers that meet specified criteria. These criteria include provisions similar to the requirements for the tariff specified in this bill. The bill is pending in the Senate.
SB 978 (Pérez, 2026) would have required the CPUC to create a special rate structure for large data centers prevent cost shifts to other customers. The bill would have established labor requirements for the construction of facilities subject to the bill. The bill would have expanded existing CPUC reporting requirements to include a specified assessment about data center impacts to renewable procurement goals. The bill was held by the Senate Appropriations Committee.
AB 2383 (Zbur, 2026) requires the CPUC to establish electrical corporation tariffs by January 1, 2028, for transmission and distribution and generation services for certain data centers. The bill specifies requirements for these tariffs and requires CCAs and ESPs to adopt generation tariffs for data centers that provide protections similar to those required for electrical corporation data center tariffs. The bill is pending in the Senate.
SB 57 (Padilla, Chapter 647, Statutes of 2025) authorized the CPUC to assess the extent to which electrical corporation costs for new loads from data centers result in cost shifts to other electrical corporation customers. The bill also required the CPUC to publish and submit a report regarding its assessment to the relevant legislative policy committees by January 1, 2027.
AB 222 (Bauer-Kahan, 2025) would have required the CPUC to assess the extent to which electrical corporation costs for serving data centers result in cost shifts to other customers. The bill also required the CEC to establish a process for data centers to submit specified energy efficiency data to the CEC, and it required the CEC to assess data centers’ energy consumption. The bill was held by the Senate Appropriations Committee.
SB 1298 (Cortese, 2024) would have increased the amount of thermal generation a data center could use as backup power from 100 MW to 150 MW without triggering the CEC’s power plant siting process. The bill would have also created conditions for data centers to use this exemption. The bill died in the Assembly.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
According to the Assembly Appropriations Committee, the CPUC estimates costs of approximately $1 million annually (Public Utilities Commission Utilities Reimbursement Account) for five positions—four regulatory analysts ($190,000 to $240,000 each, depending on experience and expertise) and one attorney ($267,000)—and roughly $40,000 in training and travel expenses.
SUPPORT: (Verified 8/30/26)
Net-Zero California (co-source)
The Utility Reform Network (co-source)
350 Humboldt, Grassroots Climate Action
AARP
African American Chamber of Commerce
Bay Front Chamber of Commerce
Brawley Chamber of Commerce
Biancoverde Restaurant
Brightline Defense, if amended
California Environmental Voters
California Multicultural Business Association
California State Association of Electrical Workers
California State Pipe Trades Council
Center for Biological Diversity
Central Orange County Democratic Club
Central Valley Yemen Society
Citizens’ Climate Lobby, Orange County Central Chapter
City of Buena Park
City of Imperial
City of Monterey Park
City of Westmorland
Clever Community Development
Climate Action California
Climate Action Campaign
Coalition of California Utility Employees
Coalition of Filipino American Chamber of Commerce
College Democrats at UCI
Comité de Acción del Valle Inc.
Community Action Marin
County of San Diego
Democrats of Greater Irvine
E2
Earthjustice, if amended
Fair and Equitable Housing Alliance
Filipino American Chamber of Commerce of Greater Los Angeles
Filipino American Chamber of Commerce of Greater San Diego
Herber Public Utility District
Hercules/Rodeo Rotary Club
HOM Coffee
Imperial Valley Equity & Justice
International Brotherhood of Electrical Workers, Local Union 569
Irvine Valley College Democrats
Jesse Miranda Center for Hispanic Leadership
Kapor Center Advocacy
Kuhn Hay, Inc.
Latin Business Association
Leadership Council for Justice and Accountability
League of Women Voters of California
Little Hoover Commission
Los Amigos de la Comunidad, Inc.
Modyn Studios
National Consumers Law Center
Natural Resources Defense Council
New Beginnings
NRDC Action Fund
Orange County Climate Voter Guide
Refreshed Barbershop
Regenesis Health Solutions
SanDiego 350
Sierra Club California
Sunrise Movement Orange County
Sustainable Rossmoor
Time in Destiny
Two Hundred for Homeownership
Union of Concerned Scientists
United Nations Association, Orange County
Victoria Homes
Western States Council Sheet Metal, Air, Rail and Transportation
Women for American Values and Ethics
Women in Business Connections
21 Individuals
OPPOSITION: (Verified 8/30/26)
Bay Area Council
Bloom Energy
Building Owners and Managers Association of California
CalAsian Chamber of Commerce
California African American Chamber of Commerce
California Business Properties Association
California Chamber of Commerce
California Hispanic Chamber of Commerce
California Large Energy Consumers Association
California Manufacturers and Technology Association
Data Center Coalition
Enchanted Rock
Mainspring Energy
NAIOP California
Pacific Gas & Electric Company
San Diego Gas & Electric
Silicon Valley Leadership Group
TechCa
TechNet
Western States Petroleum Association
ARGUMENTS IN SUPPORT: According to the Author:
Multiple studies have found data centers increase costs for ordinary ratepayers as they drive skyrocketing demand without corresponding growth in supply. Moreover, these high intensity energy users require expensive infrastructure upgrades that ordinary ratepayers are paying for. Without taking steps to mitigate these cost shifts, rates are estimated to go up 8%. Microsoft, Meta, and Anthropic have stated they will pay for the cost of interconnection to their data centers, and this bill puts these commitments into law.
ARGUMENTS IN OPPOSITION: In opposition, the California Chamber of Commerce states:
California is competing with other states to attract advanced manufacturing, data centers, and other electricity-intensive industries that support economic growth and technological innovation. Policies that impose unusually burdensome infrastructure requirements while also limiting operational control over privately financed energy assets risk discouraging the development of these facilities in California. Grid flexibility and reliability are important goals, but they should be pursued through voluntary programs and market incentives rather than mandates that deter new investment in the state’s electricity system. For these reasons, the California Chamber of Commerce respectfully urges the Legislature to reject SB 886.
Prepared by: Sarah Smith / E., U. & C. / (916) 651-4107
8/31/26 22:53:30
**** END ****
SENATE THIRD READING
STR Bill Id:SB 886
Author:(Padilla and McNerney)
As Amended Ver:August 28, 2026
Majority vote
SUMMARY
This bill requires the California Public Utilities Commission (CPUC) to establish new tariffs or update existing electric rules that for transmission, distribution, generation, and interconnection services for data centers.
Major Provisions
- Requires the CPUC, by January 1, 2028, to establish a tariff for each of the following: (a) interconnection of a data center to the electrical grid, (b) procurement of electricity generation resources to serve a data center's demand for electricity ("load") and (c) the transmission and distribution services used to deliver electricity to a data center.
- Regarding establishment of any of the data center-specific tariffs, requires the CPUC to (a) evaluate the risks and benefits of the tariffs to "nonparticipating customers" (customers other than data center customers subject to the tariffs) and ensure the tariffs prevent the creation of stranded costs for, or cost shifts to, nonparticipating customers
- Regarding establishment of the interconnection tariff, requires the CPUC, among other things, to assign cost responsibility for all transmission facility upgrades and usage applicable to a participating data center customer and require an early termination fee to be assessed if the data center departs within 10 years of the initial interconnection or fails to achieve adequate load ramp up.
- Directs the CPUC to require each electrical corporation (also known as an investor-owned utility (IOU)) to publish and update maps showing locations where participating data centers can interconnect without the need for significant, costly and time-consuming transmission upgrades.
- Requires the CPUC to create a new demand response program that does not result in any net costs to a nonparticipating customer and supports various demand management and clean energy objectives for voluntary participation from data centers.
- Allows an IOU to submit an exceptional case filing to establish a contract with a data center seeking to obtain service after January 1, 2027, but before the CPUC has approved a tariff established pursuant to this bill, so long as the contract meets the requirements of this bill.
COMMENTS
The rapid expansion of data centers – driven by cloud computing, artificial intelligence, and digital services – has introduced a fast-growing and geographically concentrated source of electricity demand in California. Data centers are characterized by high, sometimes continuous (24/7) loads with often relatively limited demand flexibility, placing sustained pressure on transmission and distribution infrastructure. Recent analyses by the CEC indicate that data center electricity consumption is increasing, with projections suggesting significant growth in demand over the next decade. This growth may require large-scale infrastructure upgrades. In the 2024-2025 Draft Transmission Plan, the California Independent System Operator (CAISO) identified billions of dollars in transmission upgrades needed over the next decade to serve anticipated load growth, in part driven by new data centers. Particularly, the clustering of data centers in specific regions (like the Bay Area) can strain local transmission capacity and necessitate costly upgrades for new service lines, raising broader questions of who pays for these upgrades and how to properly plan for these incoming loads. And once energized, questions remain about how these entities adequately cover their cost of service, especially to protect against rising costs for other ratepayers.
In California, action is underway by the CPUC to address costs of new electrical loads, including data centers. On April 9, 2026, the CPUC opened a rulemaking on the California Advanced Electric Rate Design. As part of this proceeding, the CPUC intends to explore opportunities to address affordability challenges associated with wildfire costs and rapid load growth, including load from data centers. Specifically, this proceeding, in coordination with the assessment required by SB 57 (Padilla, Chapter 647, Statutes of 2025), will consider issues such as stranded costs and cost shifts for new and emerging large loads with a focus on data centers. The order instituting rulemaking indicates that the CPUC intends to publish a staff proposal on residential rate reform as part of this proceeding in the 3rd Quarter of 2026. Additionally, the CPUC recently approved interim implementation of PG&E's Electric Rule 30, which establishes a new tariff for large load interconnecting on the transmission grid. The decision requires new transmission-level customers to be responsible for the initial costs of all transmission facilities, rather than those costs being borne by ratepayers and was sought by PG&E to address an influx of customers requesting this type of service. In June 2026, the Federal Energy Regulatory Commission ordered all six regional grid operators to justify or reform tariffs for data centers and other large energy users as they relate to interconnection and transmission costs. Under the orders, each operator and its transmission owners have 60 days to either justify why their current tariffs remain just and reasonable, or to file tariff changes.
Therefore, many actions are underway to try to ensure those with a greater burden on the electrical grid pay their "fair share" of service needs. The goal of this bill is to do just that, requiring the CPUC to establish a new tariffs for data centers that more appropriately allocates the costs of providing energization and serving these large load customers.
According to the Author
According to the author, "As data centers construction has boomed across the country, ratepayers have been forced to pay for the infrastructure of these high energy facilities. Utilities borrow billions to meet this demand with ordinary ratepayers footing the bill. PJM, the East Coast utility provider for 67 million customers, recently reported rates rose 76% due to data centers energy demands. In a meeting with President Trump in the White House, Microsoft, Meta, Anthropic all promised to pay for the cost of interconnection to their data centers, this bill puts these commitments into law."
Arguments in Support
The Utility Reform Network and Net-Zero California, sponsors of this bill, along with a coalition of other supporters including the Coalition of California Utility Employees and Union of Concerned Scientists share that this bill protects ratepayers by requiring data centers to pay for new grid infrastructure and network upgrades. Moreover, supporters note that this bill is consistent with President Trump's Ratepayer Protection Pledge and follows recommendations from entities such as the Little Hoover Commission.
Arguments in Opposition
The Data Center Coalition, along with other including organizations such as TechNet and Silicon Valley Leadership Group, writes that "Any rate design that focuses on a single end use, without showing a measurable difference in service requirements or cost responsibility, risks creating unjustified distinctions among similar customers." Therefore, they see this bill as singling out data center customers, who are not the sole large energy users in the state. The opposition also points to the CPUC as "most appropriately suited to ensure appropriate cost allocations" and that this bill is overly prescriptive in CPUC direction regarding these new tariffs for data centers.
FISCAL COMMENTS
According to the Assembly Committee on Appropriations, the CPUC estimates approximately $1 million in annual costs to develop the data center-specific tariffs.
VOTES
SENATE FLOOR: 28-8-4
YES: Allen, Archuleta, Arreguín, Ashby, Becker, Blakespear, Cabaldon, Caballero, Cervantes, Durazo, Grayson, Hurtado, Laird, Limón, McGuire, McNerney, Menjivar, Padilla, Pérez, Reyes, Richardson, Rubio, Smallwood-Cuevas, Stern, Umberg, Wahab, Weber Pierson, Wiener
NO: Alvarado-Gil, Choi, Grove, Jones, Ochoa Bogh, Seyarto, Strickland, Valladares
ABS, ABST OR NV: Cortese, Dahle, Gonzalez, Niello
ASM UTILITIES AND ENERGY: 14-0-4
YES: Petrie-Norris, Boerner, Calderon, Mark González, Harabedian, Hart, Irwin, Kalra, Papan, Rogers, Schiavo, Schultz, Ta, Zbur
ABS, ABST OR NV: Patterson, Chen, Davies, Wallis
ASM APPROPRIATIONS: 12-2-1
YES: Wicks, Arambula, Calderon, Caloza, Fong, Mark González, Krell, Pacheco, Pellerin, Sharp-Collins, Solache, Ta
NO: Dixon, Tangipa
ABS, ABST OR NV: Hoover
UPDATED
VERSION: August 28, 2026
CONSULTANT: Alexa Cohill-Milanick / U. & E. / (916) 319-2083 FN: 0004456
SENATE THIRD READING
STR Bill Id:SB 886
Author:(Padilla and McNerney)
As Amended Ver:July 2, 2026
Majority vote
SUMMARY
This bill requires the California Public Utilities Commission (CPUC) to establish tariffs that address costs associated with transmission, distribution, generation, and interconnection services for data centers.
Major Provisions
- Defines a data center subject to the tariffs ("participating customer") as a facility, or a part of a facility, that houses computing infrastructure, including graphics and central processing units, servers, storage devices, networking equipment, and associated power and cooling systems, for the primary purpose of processing, storing, or distributing electronic data and a facility with a minimum peak demand as determined by the CPUC, but no more than 25 megawatts and with consideration of the data center's material impact on electrical corporation costs.
- Exempts the following facilities from this definition: publicly funded research facilities, public safety facilities, national security facilities, publicly owned facilities, and utility facilities, including but not limited to, an asset of a facilities-based telecommunications provider.
- Requires the CPUC, by July 1, 2027, to establish a tariff for each of the following: (a) interconnection of a data center to the electrical grid, (b) procurement of electricity generation resources to serve a data center's demand for electricity ("load") and (c) the transmission and distribution services used to deliver electricity to a data center.
- Regarding establishment of any of the data center-specific tariffs, requires the CPUC to (a) evaluate the risks and benefits of the separate tariffs to "nonparticipating customers" (customers other than data center customers subject to the tariffs) and ensure the separate tariffs prevent the creation of stranded costs for, or cost shifts to, nonparticipating customers.
- Regarding establishment of the interconnection tariff, requires the CPUC, among other things, to assign cost responsibility for all transmission facility upgrades triggered by a new facility interconnection to the applicable participating data center customer and require an early termination fee to be assessed if the data center departs within 10 years of the initial interconnection or fails to achieve adequate load ramp up.
- Regarding establishment of the generation tariff, requires the CPUC to, among other things, (a) ensure data center procurement of generation resources support achievement of CPUC procurement requirements and the state's clean energy targets and policies and (b) require a data center to prefund a contract of at least 10 years with the load-serving entity (LSE), such as the utility or community choice aggregator (CCA), to cover the costs of procurement for the data center.
- Regarding establishment of the transmission and distribution tariffs, requires the CPUC to ensure a participating data center pays a reasonable share of the costs relating to wildfire mitigation, wildfire liability, electrification and environmental programs, and other societal cost obligations typically collected from distribution-level ratepayers.
- Directs the CPUC to require each electrical corporation (also known as an investor-owned utility (IOU)) to publish and update maps showing locations where participating data centers can interconnect without the need for significant, costly and time-consuming transmission upgrades.
- Requires a participating data center to take part in a new demand response program authorized by the CPUC that does not result in any net costs to a nonparticipating customer and supports various demand management and clean energy objectives.
COMMENTS
California is experiencing a structural shift in electricity demand driven by the emergence of large energy loads associated with digital infrastructure, transportation electrification, and industrial decarbonization. These large loads can materially affect grid planning by increasing peak demand, accelerating the need for new transmission and distribution infrastructure, and complicate procurement requirements. All these factors can have a direct effect on costs borne by ratepayers. At the same time, certain large loads may provide opportunities for demand flexibility, load shifting, or co-location with clean generation resources, suggesting potential for the net impact on the grid to be neutral, and possibly even positive. This will depend on how these loads are integrated into state planning and regulatory frameworks.
The rapid expansion of data centers – driven by cloud computing, artificial intelligence, and digital services – has introduced a fast-growing and geographically concentrated source of electricity demand in California. Data centers are characterized by high, sometimes continuous (24/7) loads with often relatively limited demand flexibility, placing sustained pressure on transmission and distribution infrastructure. Recent analyses by the California Energy Commission (CEC) indicate that data center electricity consumption is increasing, with projections suggesting significant growth in demand over the next decade. This growth may require large-scale infrastructure upgrades. In the 2024-2025 Draft Transmission Plan, the California Independent System Operator (CAISO) identified billions of dollars in transmission upgrades needed over the next decade to serve anticipated load growth, in part driven by new data centers. Particularly, the clustering of data centers in specific regions (like the Bay Area) can strain local transmission capacity and necessitate costly upgrades for new service lines, raising broader questions of who pays for these upgrades and how to properly plan for these incoming loads. And once energized, questions remain about how these entities adequately cover their cost of service, especially to protect against rising costs for other ratepayers.
In California, action is underway by the CPUC to address costs of new electrical loads, including data centers. On April 9, 2026, the CPUC opened a rulemaking on the California Advanced Electric Rate Design. As part of this proceeding, the CPUC intends to explore opportunities to address affordability challenges associated with wildfire costs and rapid load growth, including load from data centers. Specifically, this proceeding, in coordination with the assessment required by SB 57 (Padilla, Chapter 647, Statutes of 2025), will consider issues such as stranded costs and cost shifts for new and emerging large loads with a focus on data centers. The order instituting rulemaking indicates that the CPUC intends to publish a staff proposal on residential rate reform as part of this proceeding in the third Quarter of 2026. Additionally, the CPUC recently approved interim implementation of PG&E's Electric Rule 30, which establishes a new tariff for large load interconnecting on the transmission grid. The decision requires new transmission-level customers to be responsible for the initial costs of all transmission facilities, rather than those costs being borne by ratepayers and was sought by PG&E to address an influx of customers requesting this type of service. In June 2026, the Federal Energy Regulatory Commission ordered all six regional grid operators to justify or reform tariffs for data centers and other large energy users as they relate to interconnection and transmission costs. Under the orders, each operator and its transmission owners have 60 days to either justify why their current tariffs remain just and reasonable, or to file tariff changes.
Therefore, many actions are underway to try to ensure those with a greater burden on the electrical grid pay their "fair share" of service needs. The goal of this bill is to do just that, requiring the CPUC to establish a new tariffs for data centers that more appropriately allocates the costs of providing energization and serving these large load customers.
According to the Author
According to the author, "As data centers construction has boomed across the country, ratepayers have been forced to pay for the infrastructure of these high energy facilities. Utilities borrow billions to meet this demand with ordinary ratepayers footing the bill. PJM, the East Coast utility provider for 67 million customers, recently reported rates rose 76% due to data centers energy demands. In a meeting with President Trump in the White House, Microsoft, Meta, Anthropic all promised to pay for the cost of interconnection to their data centers, this bill puts these commitments into law."
Arguments in Support
The California State Pipe Trades Council, State Association of Electrical Workers, Coalition of Utility Employees, and the Wester States Council of Sheet Metal Workers, along with support from individual local representatives, share that this bill "strikes the perfect balances between accommodating the economic engine that data centers represent while protecting and benefitting other ratepayers" and ensuring high quality jobs. The support also notes the risk of inaction should this bill not pass, which could be stranded assets and cost shifts onto other ratepayers.
Arguments in Opposition
The Data Center Coalition, along with other including organizations such as TechNet and Silicon Valley Leadership Group, writes that "Any rate design that focuses on a single end use, without showing a measurable difference in service requirements or cost responsibility, risks creating unjustified distinctions among similar customers." Therefore, they see this bill as singling out data center customers, who are not the sole large energy users in the state. The opposition also points to the CPUC as "most appropriately suited to ensure appropriate cost allocations" and that this bill is overly prescriptive in CPUC direction regarding these new tariffs for data centers.
FISCAL COMMENTS
According to the Assembly Committee on Appropriations, the CPUC estimates approximately $1 million in annual costs to develop data center-specific tariffs.
VOTES
SENATE FLOOR: 28-8-4
YES: Allen, Archuleta, Arreguín, Ashby, Becker, Blakespear, Cabaldon, Caballero, Cervantes, Durazo, Grayson, Hurtado, Laird, Limón, McGuire, McNerney, Menjivar, Padilla, Pérez, Reyes, Richardson, Rubio, Smallwood-Cuevas, Stern, Umberg, Wahab, Weber Pierson, Wiener
NO: Alvarado-Gil, Choi, Grove, Jones, Ochoa Bogh, Seyarto, Strickland, Valladares
ABS, ABST OR NV: Cortese, Dahle, Gonzalez, Niello
ASM UTILITIES AND ENERGY: 14-0-4
YES: Petrie-Norris, Boerner, Calderon, Mark González, Harabedian, Hart, Irwin, Kalra, Papan, Rogers, Schiavo, Schultz, Ta, Zbur
ABS, ABST OR NV: Patterson, Chen, Davies, Wallis
ASM APPROPRIATIONS: 12-2-1
YES: Wicks, Arambula, Calderon, Caloza, Fong, Mark González, Krell, Pacheco, Pellerin, Sharp-Collins, Solache, Ta
NO: Dixon, Tangipa
ABS, ABST OR NV: Hoover
UPDATED
VERSION: July 2, 2026
CONSULTANT: Alexa Cohill-Milanick / U. & E. / (916) 319-2083 FN: 0003476
Date of Hearing: August 5, 2026
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Buffy Wicks, Chair
SBPCA Bill Id:SB 886
Author:(Padilla) – As Amended Ver:July 2, 2026
Policy Committee: | Utilities and Energy | Vote: | 14 - 0 |
|
| ||
|
|
Urgency: No State Mandated Local Program: Yes Reimbursable: No
SUMMARY:
This bill requires the California Public Utilities Commission (CPUC) to establish pricing and rules (tariffs) applicable to the provision of electrical service to data centers.
Specifically, this bill:
- Defines a data center subject to the tariffs (“participating customer”) as one with a minimum peak demand as determined by the CPUC, but no more than 25 megawatts and in consideration of the data center’s material impact on electrical corporation costs.
- Requires the CPUC, by July 1, 2027, to establish a tariff for each of the following: (a) interconnection of a data center to the electrical grid, (b) procurement of electricity generation resources to serve a data center’s demand for electricity (“load”) and (c) the transmission and distribution infrastructure used to deliver electricity to a data center.
- Regarding establishment of any of the data center-specific tariffs, requires the CPUC to (a) evaluate the risks and benefits of the separate tariffs to “nonparticipating customers”(customers other than data center customers subject to the tariffs), (b) ensure the separate tariffs prevent the creation of stranded costs for, or cost shifts to, nonparticipating customers, and (c) for a customer that receives electrical generation service and electrical transmission and distribution service from different entities (“unbundled customer”), ensure that charges generally included in the generation component of the unbundled customer’s consolidated bill are assessed as a separate line item on the unbundled customer’s bill.
- Regarding establishment of the interconnection tariff, requires the CPUC, among other things, to assign cost responsibility for all transmission facility upgrades triggered by a new facility interconnection to the applicable participating data center customer.
- Regarding establishment of the generation tariff, requires the CPUC to, among other things, (a) ensure data center procurement of generation resources support achievement of CPUC procurement requirements and the state’s clean energy targets and policies and (b) require a data center to prefund a contract of at least 10 years with the load-serving entity (LSE), such as the utility or community choice aggregator (CCA), to cover the costs of serving the data center.
- Regarding establishment of the transmission and distribution tariffs, requires the CPUC to ensure a participating data center pays a reasonable share of the costs relating to wildfire mitigation, wildfire liability, electrification and environmental programs, and other societal cost obligations typically collected from distribution-level ratepayers.
- Directs the CPUC to require each electrical corporation (also known as an investor-owned utility (IOU)) to publish and update maps showing locations where participating data centers can interconnect without the need for significant, costly and time-consuming transmission upgrades.
- Requires a participating data center take part in a new demand response program authorized by the CPUC that does not result in any net costs to a nonparticipating customer and supports various demand management and clean energy objectives.
FISCAL EFFECT:
This bill creates significant new analytical, regulatory and legal work of the CPUC to develop the data center-specific tariff. The CPUC estimates costs of approximately $1 million annually (Public Utilities Commission Utilities Reimbursement Account) for five positions—four regulatory analysts ($190,000 to $240,000 each, depending on experience and expertise) and one attorney ($267,000)—and roughly $40,000 in training and travel expenses.
COMMENTS:
- Background. Data centers—facilities that house servers, storage devices and other computer-related infrastructure—are generally, by their nature, energy intensive: it takes a great deal of electricity to power such large concentrations of electronic equipment. California is home to many data centers, especially in and near the Silicon Valley region of Santa Clara County. Many expect data center development, and the associated demand for electricity, to continue and accelerate as the artificial intelligence (AI) industry grows.
Under existing practice, the CPUC generally considers costs for serving new large loads (such as factories, office buildings and housing developments) under tariffs, specifically “Electric Rule 15” and “Electric Rule 16,” where the requesting customer typically pays the incremental costs of interconnection. As part of consideration, the CPUC generally seeks to minimize the shifting of costs from the requesting customer to other customers or customer classes, though the law does not explicitly require that the CPUC do so.
Historically, these CPUC rules have governed interconnection of customers at the distribution level, that is, at level that draws relatively less electricity than that carried by electricity transmission lines. Many utilities, including and especially Pacific Gas and Electric (PG&E), report an increase in requests for new service at the transmission level, that is, in the case of PG&E, service that would draw 50 kilovoltz or more of electricity. For this reason, PG&E proposed to the CPUC a new transmission-level service request rule, “Electric Rule 30.”
Last year, the CPUC approved interim implementation of Electric Rule 30, applicable to PG&E only, to streamline and accelerate electric grid connections at the transmission level for high-energy users, such as AI data centers and electric vehicle (EV) charging stations within the PG&E service territory. The CPUC describes its action on the interim electric rule as a partial approval of PG&E’s proposed Electric Rule 30 that offers an “accelerated pathway” for a customer seeking transmission-level services, provided the customer agrees to pay for necessary transmission infrastructure work upfront. The CPUC further reports it will determine terms and cost allocation in a future decision.
More recently, in April of this year, the CPUC opened a rulemaking on the California Advanced Electric Rate Design to explore opportunities to address affordability challenges associated with wildfire costs and rapid load growth, including load from data centers. The proceeding, along with the assessment required by (Padilla), Chapter 647, Statutes of 2025, will consider issues such as stranded costs and cost shifts for new and emerging large loads with a focus on data centers.
Despite these ongoing efforts, the author contends state law must be explicit in requiring data centers and other very large electricity users to cover cost of providing them with electric service.
- Support and Opposition. Several organizations representing labor, environmental advocacy and other interests echo the author’s arguments. In addition, the Little Hoover Commission, expresses support for the bill, describing it carrying out recommendations from its 2026 report, “Data Centers and California Electricity Policy.”
A coalition of technology, industry and business organizations—including the Bay Area Council, the Silicon Valley Leadership Group and TechNet—sees the issue differently, critiquing SB 886 as introducing “ambiguity” that “could hamper efforts to ensure costs are appropriately allocated.” Instead of this bill, the opponents advocate letting the CPUC sort the matter, asserting, “We believe the CPUC, in its regulatory role, is most appropriately suited to ensure appropriate cost allocation through public proceedings that are evidence-based, transparent, carefully considered, and open to stakeholder participation.”
- Related Legislation. The Legislature is considering, or has considered, several bills related to data centers. Bills actively under consideration in the current legislative session include AB 1577 (Bauer-Kahan), AB 2383 (Zbur), AB (Papan) and AB 2619 (Papan), each of which is pending consideration in the Senate Committee on Appropriations, and SB 887 (Padilla) and SB 1168 (McNerney), both of which are pending consideration in this committee.
Analysis Prepared by: Jay Dickenson / APPR. / (916) 319-2081
Date of Hearing: June 24, 2026
ASSEMBLY COMMITTEE ON UTILITIES AND ENERGY
Cottie Petrie-Norris, Chair
SBPCA Bill Id:SB 886
Author:(Padilla) – As Amended Ver:May 14, 2026
SENATE VOTE: 28-8
SUBJECT: California Technology Innovation and Ratepayer Protection Act
SUMMARY: Requires the California Public Utilities Commission (CPUC) to establish an electrical corporation tariff that addresses costs associated with transmission, distribution, and generation services for data centers. Specifically, this bill:
- Defines a data center as a facility that primarily contains electronic equipment used to process, store, and transmit digital information, which may be a free-standing structure or a facility within a larger structure, that uses environmental control equipment to maintain the proper conditions for the operation of electronic equipment. This definition also clarifies that this does not apply to the following facilities:
- Publicly funded research facility
- Public safety facility
- National security facility
- Publicly owned facility
- Utility facility, including but not limited to, an asset of a facilities-based telecommunications provider
- Directs the CPUC, on or before July 1, 2027, to establish a rate structure that includes an electrical corporation tariff for the interconnection of data center facilities and the provisions of transmission, distribution, and generation services.
- Specifies that the interconnection components of the tariff should apply to data centers taking transmission level electrical service with an estimated peak demand of at least 25 megawatts (MW).
- Directs the CPUC to determine the appropriate minimum peak demand for data center customers, but not exceeding 25 MW and consider the extent to which the facility load has a material impact on electrical corporation costs for the remaining aspects of the tariff.
- Requires the CPUC to do all of the following when establishing an electrical corporation tariff:
- Evaluate the risks and benefits of an electrical corporation tariff to nonparticipating customers.
- Ensure the tariff prevents the creation of stranded costs for, or cost shifts to, nonparticipating customers.
- Requires the tariff to do all of the following:
- For the generation component of the tariff, assign any unique wholesale energy costs to the data center customer.
- Include a reasonable share of the costs relating to wildfire mitigation, wildfire liability, electrification and environmental programs, and other societal cost obligations typically collected from distribution-level ratepayers.
- Require data centers to prefund a contract of at least 15 years in duration for the installation of new, incremental, zero-carbon energy resources sufficient to do both of the following:
- Provide at least 50 percent of the participating customer’s hourly energy needs.
- Provide dispatchable reliability assets within the load-serving entities service territory.
- Allows the contract requirement of (c) to also be met by the data center through installation of comparable energy resources behind its meter, limited to zero-emission resources.
- Requires participation in a new demand response program authorized by the CPUC that does not result in any net costs to a nonparticipating customer and supports load shifting, reliability, resource adequacy, and greenhouse gas emission reduction objectives.
- Requires the interconnection provisions of the tariff to do the following:
- Requires a data center to disclose whether an application for interconnection has already been submitted to another load-serving entity.
- Assign cost responsibility for all transmission facility upgrades triggered by a new facility interconnection to the data center customer.
- Allow participating customers to receive refunds for a portion of the initial nominal dollar contributions to interconnection costs. These refunds will apply only to the extent that actual annual net revenues cover the cost of energization, costs of providing electrical service, or other costs allocated by the CPUC to the data center.
- Requires an early termination fee to be assessed if the data center departs within 15 years of initial interconnection or fails to achieve full load ramp up.
- Requires the data center to certify it meets specified labor requirements with the CPUC.
- Requires electrical corporations to publish and update maps showing locations where participating customers can interconnect without the need for significant, costly, and time-consuming transmission upgrades.
EXISTING LAW:
- Requires that all rates for any service or product charged by an electrical corporation be just and reasonable. (Public Utilities Code § 451)
- Requires the CPUC to ensure that rates are sufficient to enable IOUs to recover a just and reasonable amount of revenue from residential customers as a class, while observing the principle that electricity and gas services are necessities, for which a low, affordable rate is desirable, and while observing the principle that conservation is desirable in order to maintain an affordable bill. (Public Utilities Code § 739)
- Requires the CPUC to establish rates using cost allocation principles that fairly and reasonably assign to different customer classes the costs of providing service to those customer classes, consistent with the policies of affordability and conservation. (Public Utilities Code § 739.6)
- Authorizes the CPUC to require a public utility to correct any rates, practices, equipment, or behavior that is unjust, unreasonable, unsafe, improper, inadequate, or insufficient. (Public Utilities Code § 761)
- Defines an electrical corporation as every corporation or person owning, controlling, operating, or managing any electric plant for compensation within this state, except where electricity is generated on or distributed by the producer through private property solely for its own use or the use of its tenants and not for sale or transmission to others. (Public Utilities Code § 218)
- Establishes a policy to source 100% of all in-state retail electricity sales from zero-carbon and renewable resources by December 31, 2045. Existing law requires the CPUC, California Energy Commission (CEC), and the California Air Resources Board (CARB) to incorporate this policy into all relevant plans. (Public Utilities Code § 454.53)
- Authorizes the CPUC to assess the extent to which electrical corporation costs for new loads from data centers result in cost shifts to other electrical corporation customers. (Public Utilities Code § 913.22)
FISCAL EFFECT: According to the Senate Appropriations Committee, the CPUC estimates one-time costs likely between $750,000 and $2 million spread over two years as well as ongoing costs ranging from approximately $500,000 to $1.2 million annually to establish and implement a new tariff and regulatory framework.
BACKGROUND:
Large Energy Loads – California is experiencing a structural shift in electricity demand driven by the emergence of large energy loads associated with digital infrastructure, transportation electrification, and industrial decarbonization.[1],[2] These large loads can materially affect grid planning by increasing peak demand, accelerating the need for new transmission and distribution infrastructure, and complicate procurement requirements. [3] All these factors can have a direct effect on costs borne by ratepayers.[4] At the same time, certain large loads may provide opportunities for demand flexibility, load shifting, or co-location with clean generation resources, suggesting a potential for the net impact on the grid to be neutral, and possibly even positive.[5] This will depend on how these loads are integrated into state planning and regulatory frameworks.
Data Center Growth – The rapid expansion of data centers – driven by cloud computing, artificial intelligence, and digital services – has introduced a fast-growing and geographically concentrated source of electricity demand in California.[6] Data centers are characterized by high, sometimes continuous (24/7) loads with often relatively limited demand flexibility, placing sustained pressure on transmission and distribution infrastructure. Recent analyses by the CEC indicate that data center electricity consumption is increasing, with projections suggesting significant growth in demand over the next decade.[7] This growth may require large-scale infrastructure upgrades. In the 2024-2025 Draft Transmission Plan, the California Independent System Operator (CAISO) identified billions of dollars in transmission upgrades needed over the next decade to serve anticipated load growth,[8] in part driven by new data centers. Particularly, the clustering of data centers in specific regions (like the Bay Area [9]) can strain local transmission capacity and necessitate costly upgrades for new service lines, raising broader questions of who pays for these upgrades and how to properly plan for these incoming loads. And once energized, questions remain about how these entities adequately cover their cost of service, especially to protect against rising costs for other ratepayers.
Impacts of data center growth across the U.S. – In response to the growing data center demand, states across the U.S. are grappling with how to fairly allocate the costs of this new load. For example, various states have adopted strategies to make data center developers provide more upfront investments to avoid passing those costs onto ratepayers. In Illinois, developers are required to provide a $1 million deposit.[10] In Indiana and Ohio, long-term take-or-pay contracts are required where developers pay for at least 85% of the transmission service they request for at least 10 years, even if their actual usage is less.[11] The PJM Interconnection – the largest power grid operator in the U.S., serving approximately 67 million customers from Chicago to New Jersey, including the “data center alley” of Northern Virginia – was ordered by the Federal Energy Regulatory Commission (FERC) in 2025 to update its tariff to provide interconnection of customers serving co-located load (i.e., data centers with onsite generation).[12]
In June 2026, FERC ordered all six regional grid operators[13] to justify or reform tariffs for data centers and other large energy users as they relate to interconnection and transmission costs.[14] Under the orders, each operator and its transmission owners have 60 days to either justify why their current tariffs remain just and reasonable, or to file tariff changes that address the issues identified by FERC, including the following:
- Develop efficient transmission service applications and study processes, including consideration of alternative transmission technologies.
- Prevent cost shifting and requiring transparency into transmission costs.
- Accommodate co-location agreements and behind-the-meter generation.
- Provide new transmission services for flexible large loads.
- Develop a process to study generating facilities that serve electrically proximate large loads and co-located loads.
This order represents the first significant federal regulatory response to the concerns from data center load growth. The timelines put in place by the order are quick – 60 days for justification or filing of tariffs and just 30 days to submit an information report. Therefore, within the coming months there is likely to be a flurry of new information on how entities across the U.S. are responding to the challenges posed by data center energy demand.
Regulatory response to data center growth – In California, action is underway by the CPUC to address costs of new electrical loads, including data centers. On April 9, 2026, the CPUC opened a rulemaking on the California Advanced Electric Rate Design.[15] As part of this proceeding, the CPUC intends to explore opportunities to address affordability challenges associated with wildfire costs and rapid load growth, including load from data centers. Specifically, this proceeding, in coordination with the assessment required by SB 57 (Padilla, Chapter 647, Statutes of 2025), will consider issues such as stranded costs and cost shifts for new and emerging large loads with a focus on data centers. The order instituting rulemaking indicates that the CPUC intends to publish a staff proposal on residential rate reform as part of this proceeding in the 3rd Quarter of 2026.
Additionally, the CPUC recently approved interim implementation of PG&E’s Electric Rule 30, which establishes a new tariff for large load interconnecting on the transmission grid.[16] The decision requires new transmission-level customers to be responsible for the initial costs of all transmission facilities, rather than those costs being borne by ratepayers and was sought by PG&E to address an influx of customers requesting this type of service.
Distinctions Between Interconnection, Energization, and Cost of Service – In utility regulation, “interconnection,” “energization,” and “cost of service” address distinct, though related, aspects of how large load customers are integrated into the grid. “Interconnection” refers to the set of rules that a new electricity generator must follow to connect to the electrical grid and deliver energy to customers.[17] It is the process of connecting generators (i.e., supply) to the grid. In California, this process is overseen and regulated by the Federal Energy Regulatory Commission (FERC), CAISO, and the CPUC, in partnership with the utilities, energy generators, and stakeholders.
“Energization” is the process by which new customer loads get connected to the grid, including necessary upgrades to transmission or distribution infrastructure to ensure safe and reliable service. It is the process of connecting load (i.e., demand) to the grid. In California, energization policies for IOUs are governed by utility tariffs (e.g., Rule 15 and Rule 16), which are largely focused on customers connecting to the distribution grid.[18] Recently, as mentioned above, the CPUC approved interim implementation of PG&E’s Electric Rule 30, which is focused on transmission-level energization.[19] In 2024, the CPUC set new statewide energization timelines and targets for timely grid connections.[20] And recently, the proceeding entered its Phase 2 Scoping Memo and Ruling as energization timelines continue to delay customer service.
Finally, “cost of service” pertains to how the ongoing costs of providing electric service, including generation, transmission, distribution, and public purpose programs, are allocated among different classes of customers through rates. Cost-of-service considerations are what largely make customer rates, addressed through general rate cases and rate design proceedings at the CPUC. Overall, while energization determines the upfront and infrastructure-related costs required to connect new large loads, cost-of-service frameworks govern how those customers contribute to the long-term costs of maintaining and operating the grid.
COMMENTS:
- Author’s Statement. According to the author, “As data centers construction has boomed across the country, ratepayers have been forced to pay for the infrastructure of these high energy facilities. Utilities borrow billions to meet this demand with ordinary ratepayers footing the bill. PJM, the East Coast utility provider for 67 million customers, recently reported rates rose 76% due to data centers energy demands. In a meeting with President Trump in the White House, Microsoft, Meta, Anthropic all promised to pay for the cost of interconnection to their data centers, this bill puts these commitments into law.”
- Purpose of the bill. As discussed above, many actions are underway to try to ensure those with a greater burden on the electrical grid pay their “fair share” of service needs. The goal of this bill is to do just that, requiring the CPUC to establish a new tariff for data centers that more appropriately allocates the costs of providing energization and serving these large load customers.
Rate design is an essential mitigation tool to ensure costs are fairly allocated and not shifted to other ratepayers. The treatment of data centers under retail ratemaking presents a challenge, as the pace of retail design has traditionally been aligned with smaller, incremental load growth. Transmission-level customers, such as large data centers, typically pay rates about 14-17¢ less than distribution-level customers.[21] Distribution rates also contain statewide policy costs, such as wildfire mitigation, net energy metering, and public purpose program costs. Customers connecting at the transmission level do pay certain distribution costs, including a portion of wildfire-related costs,[22] but not nearly as significantly as distribution-level customers. The primary way large loads reduce bills for other ratepayers is by (a) minimizing or avoiding infrastructure upgrades that would otherwise be socialized – either by limiting the need for new infrastructure or requiring large load customer to pay those costs upfront – and/or (b) ensuring that large-load customers provide stable, long-term revenue over the life of any required upgrades, sufficient to cover not only fixed capital costs but also ongoing operations, maintenance, depreciation, and associated generation procurement costs. Ensuring that data centers adequately cover the cost of energization and service, as is the goal of this bill, will potentially help to ensure these entities are paying for an equitable portion of their energy impact.
- Clarification of participating customers. This bill requires a new tariff to be established for “participating customers,” defined differently for the interconnection vs. other rate components. For interconnection components of the tariff, the bill defines “participating customer” as a data center taking transmission level electrical service with an estimated peak demand of at least 25 megawatts. For the other components of the tariff (transmission, distribution, generation) the bill includes a much broader pool of customers, directing the CPUC to determine an appropriate minimum peak demand for “participating customers” as one that should not exceed 25 megawatts and should consider the extent to which facility load has material impact on electrical corporation costs but does not define a specific category of customer that should be included. It is unclear how and why the same tariff would have differing definitions of “participating customers.” For example, as currently written, the interconnection components of the tariff would only apply to data centers and not other large loads. The author has shared this was not the intent of the language, but rather that all elements of the bill be specific to data centers. Therefore, the committee recommends establishing a uniform definition of “participating customer,” as a data center with a minimum peak demand, as determined by the commission (but not greater than 25 MW). Additionally, the committee recommends clarifying the definition of a data center to include specific equipment characteristics and intended purposes of the facility.
- Who is exempt? Data centers come in many shapes and sizes and are vital to many aspects of daily life. For example, enterprise data centers are company owned and operated for proprietary digital operations (such as for banks, healthcare, governments, etc.). Other data center facilities, such as hyperscalers, are large-scale operations that deliver rapid computing power and cloud-based storage to support AI and other data-intensive applications. To address the different types and applications of data centers, the bill makes exemptions for the types of facilities that this new tariff should not apply to, exempting entities such as publicly funded research facilities and national security facilities. However, these definitions may pose loopholes or unintentionally leave desired groups out. For example, the increased reliance of AI on matters of national security may allow hyperscale facilities to fall under the exemption of national security facilities, as currently written. In a recent example, the U.S. Department of Justice halted an air pollution lawsuit against a data center in Mississippi, citing that the data center was playing a crucial role in the ongoing Iran war.[23]
Individuals representing private universities in the state have also raised concerns that their status as a private institution may unintentionally prohibit them from the exemption detailed for publicly funded research facilities. Additionally, telecommunication, cable, and internet service providers have also raised concerns that the current language does not adequately exempt data centers associated with their services. Altogether, this highlights the challenges of appropriately including in statute exemptions for an industry as expansive and pervasive in daily life as data centers. The author may wish to revisit and refine this list of exempted facilities to ensure it is an accurate reflection of the intended scope.
- Tariff structure. As previously mentioned, this bill covers aspects of electrical service including interconnection (used to refer to energization), transmission, distribution, and generation services. Placing all these elements under one tariff structure creates inconsistencies and confusion. Moreover, it would be a departure from how tariffs are currently structured (i.e., Rule 30 for PG&E is specific to energization costs and procedures) and would miss including other load-serving entities that do not provide the full suite of tariffs to customers. Therefore, the committee recommends that the bill be restructured to clarify the elements that are specific to separate tariffs for interconnection, transmission, distribution, and generation services. This requires minor clarifications to the bill language and separating the components of the bill into the relevant tariffs.
- Generation requirements. In addition to the structural changes mentioned above, the committee recommends changes to the specific provisions related to generation services. As currently written, the bill requires data centers to prefund a contract for the installation of new, incremental zero-carbon energy resources that will provide at least 50% of the participating customers’ hourly energy needs and provide dispatchable reliability assets within the load serving entity’s service territory. This language seeks a dual purpose: ensuring large loads pay their full costs of generation service and ensuring that generation is as clean as possible. While laudable, this language may add unnecessary barriers in holding data centers accountable for their energy needs. For example, the CPUC recently directed load-serving entities to procure additional resources to meet the load forecast in the Integrated Energy Policy Report.[24] Therefore, it is unclear if load serving entities would need to procure additional new resources to adequately serve data center customers, at least in the immediate future. The over procurement of new resources could raise the risk of these costs being passed on to other ratepayers. Additionally, there is ambiguity in what resources qualify as a “zero-carbon” post-2030 in the SB 100 statute,[25] making planning for this requirement uncertain. Given the rapidly evolving landscape of data center demand growth, it seems prudent to focus efforts on protecting ratepayers from potential cost increases. Therefore, the committee recommends removing the bill’s existing procurement language and instead directing contract provisions to cover the costs of procurement necessary to serve the participating customer – yielding generation services that prevent over procurement of resources that may yield additional costs borne by other ratepayers.
Another way to reduce procurement and generation needs is for data centers to invest in onsite generation. To encourage the adoption of more behind-the-meter resources and ensure they are aligned with clean energy goals, the committee recommends retaining the bill’s allowance for data centers to reduce the requirement to prefund generation costs by installing zero-emission resources onsite.
Finally, the bill currently directs, as part of the tariff structure, data centers to participate in a new demand response program established by the CPUC. As not specific to any tariff component, the committee recommends retaining the demand response requirement but moving it outside of the tariff structure.
- Stranded assets protection. As detailed above, demand from data centers is rapidly growing across California. Often these facilities have the resources to seek out favorable agreements with an energy provider for service and can have inquiries across different service providers. While there is nothing inherently wrong with competition in the market, the ability for these facilities to “shop around” inserts uncertainty into planning frameworks. For example, recent forecasting from the CEC highlights the range of uncertainty from incoming data center demand, ranging from most certain (with agreements) to largely unknown (from inquiries).[26]
Furthermore, energy providers are required to enter long-term procurement contracts to address the State’s resource adequacy and reliability requirements. Therefore, the risk of stranded assets, and ultimately increased costs to ratepayers, is high, especially if large load customers can shop around without consequence. Contract requirements provide a way to ensure that ratepayers are protected against the risk of stranded assets by placing responsibility with the large energy use facilities for the resources and upgrades necessary to serve their needs. In the present bill, this is in the form of prefunded minimum duration contract and upfront costs for transmission facility upgrades.
One argument against the contract terms applying equally across load-serving entities is that it diminishes competition from entities interested in attracting data center customers. However, the contract terms as outlined are specific to protections against stranded assets and do not limit, for example, CCAs from continuing to provide these large loads generation services at prices deemed appropriate by their governing boards. For clarity, the committee recommends specifying that the terms related to the generation tariff, including the contract minimum, be a requirement of all load-serving entities, ensuring that the tariff requirements protect ratepayers across entities.
- Interconnection tariff. The bill requires that an interconnection tariff assign cost responsibility for all transmission facility upgrades triggered by a new data center. In covering those costs, the bill also grants data centers the ability to receive refunds for a portion of its contribution to the interconnection costs. These refunds are tied to the extent that the actual annual revenues cover the costs of energization. However, the bill does not specific what revenues this refund is associated with. Therefore, the committee recommends clarifying language that specifies the refunds are tied to the transmission revenues received by the electrical corporation. Additionally, the committee recommends clarifying that an early termination fee can be assessed if a data center fails to achieve adequate load ramp up, as determined by the CPUC.
- Additional clarifying amendments. The committee recommends further amendments to clarify the bill or make changes at the request of the author. These include specifying that electric corporation does not include electric co-ops for the purposes of the tariff, changing the prefunded contract terms from 15 years to 10 years, clarifying the language specific to unbundled customer billing, and adding protective language related to the autonomy of service provided by other load-serving entities.
- Related Legislation.
AB 1577 (Bauer-Kahan) requires data centers to report monthly energy usage and efficiency information to the CEC. The CEC must integrate this data into the 2029 Integrated Energy Policy Report (IEPR) and annually publish the data in an anonymized and aggregated format for the public. Additionally, data centers must submit similar energy and efficiency information to local agencies when requesting authorization to construct or operate a data center. Status: Set for hearing in the Senate Energy, Utilities, and Communications Committee on June 24th.
AB 2383 (Zbur) requires the CPUC to establish a retail electricity classification for large energy use facilities, defined as facilities connected under a retail transmission tariff and broadly meeting the definition of a data center. Additionally, electrical corporations must submit to the CPUC for approval a tariff that covers the provisions of transmission, distribution, and generation, as applicable for large energy use facilities. Load serving entities providing generation service must all meet the same tariff requirements. Status: Set for hearing in the Senate Energy, Utilities, and Communications Committee on June 30th.
AB 2469 (Papan) prohibits a local agency from approving construction of a new, or expansion of an existing, data center unless an applicant for a data center project provides the local agency with detailed information regarding the data center′s water use and meets other requirements related to workforce and infrastructure for the data center. Status: Set for hearing in the Senate Natural Resources and Water Committee on June 23rd.
AB 2505 (Carillo) requires the CPUC to establish a new tariff or rule for electrical corporations to establish separately metered electrical service to heavy-duty hydrogen refueling stations. Status: Set for hearing in the Senate Energy, Utilities, and Communications Committee on June 24th.
AB 2619 (Papan) requires data center developers to provide information on water use to water suppliers and local governments prior to being issued a business license and upon renewal of a business license, and requires urban water suppliers to consider data center demand in water shortage planning. Status: Set for hearing in the Senate Natural Resources and Water Committee on June 23rd.
SB 887 (Padilla) provides that the California Environmental Quality Act (CEQA) applies to data center projects, as defined. Adds data center projects meeting specified conditions and geothermal projects to existing streamlining provisions for Environmental Leadership Development Projects (ELDPs). Status: Set for hearing in this committee on June 24th.
SB 978 (Pérez) requires the CPUC to establish a special rate structure for data centers taking transmission level electrical service with an estimated peak demand of at least 75 megawatts, as specified. This bill requires a contractor who enters a contract to perform work on a data center facility to abide by specified public works requirements and use a skilled and trained workforce. Status: Held in the Senate Appropriations Committee.
SB 1168 (McNerney) requires the CPUC to assess opportunities for rate structures to address specified rate impacts associated with data centers, including paying a reasonable share of costs associated with transmission and distribution needs, paying for a proportionate share of load increases and procurement needs, and alleviating cost pressures on residential ratepayers. Status: Set for hearing in this committee on June 24th.
- Prior Legislation.
AB 222 (Bauer-Kahan, 2025) required the CEC to collect and analyze data center energy consumption trends and include those findings in the 2027 IEPR. This bill also required the CPUC to determine if data center loads resulted in cost shifts to other customers and to submit an assessment to the Legislature. Status: Held in the Senate Appropriations Committee.
AB 93 (Papan, 2025) required a data center operator to provide its estimated or actual water use to its water supplier as a condition of obtaining or renewing a business license issued by a city or county. Status: Vetoed
SB 57 (Padilla) authorizes the CPUC to assess the extent to which utility costs associated with new loads from data centers result in cost shifts to other utility customers and generate a report to the Legislature by January 1, 2027. This assessment may include costs associated with growing load demand, consideration of stranded asset costs, and mechanisms to prevent or mitigate cost shifts to ratepayers. Status: Chapter 647, Statutes of 2025.
REGISTERED SUPPORT / OPPOSITION:
Support
350 Humboldt: Grass Roots Climate Action
AARP
California State Association of Electrical Workers
California State Pipe Trades Council
Climate Action California
Coalition of California Utility Employees
Imperial; City of
League of Women Voters of California
Little Hoover Commission
Natural Resources Defense Council (NRDC)
Net-zero California
The Utility Reform Network (TURN)
Union of Concerned Scientists
Western States Council Sheet Metal, Air, Rail and Transportation
Support If Amended
Brightline Defense
California Environmental Voters
Center for Biological Diversity
Center on Race, Poverty, and the Environment
Central Orange County Democratic Club
Citizens Climate Lobby Orange County Central Chapter
Climate Action Campaign
College Democrats At UC Irvine
Democrats of Greater Irvine
Earthjustice
Irvine Valley College Democrats
Leadership Council for Justice and Accountability
Nextgen California
Orange County Climate Voter Guide
Orange County Young Democrats
Sierra Club California
Sunrise Movement Orange County
United Nations Association, Orange County
Women for American Values and Ethics (WAVE)
Oppose
Bay Area Council
Calasian Chamber of Commerce
California African American Chamber of Commerce
California Chamber of Commerce
California Hispanic Chambers of Commerce (CHCC)
California Manufacturers & Technology Association (CMTA)
Data Center Coalition
Pacific Gas and Electric Company
Silicon Valley Leadership Group (SVLG)
Techca
Technet
Analysis Prepared by: Alexa Cohill-Milanick / U. & E. / (916) 319-2083
NERC, 2024 Long-Term Reliability Assessment, Demand Trends and Implications https://www.nerc.com/globalassets/our-work/assessments/2024-ltra_corrected_july_2025.pdf ↑
Slide 10: Main Drivers of Peak Load Growth, Item 6: Resolution Adopting the California
Energy Demand Forecast, 2025-2045, https://www.energy.ca.gov/filebrowser/download/9328?fid=9328 ↑
Shehabi, A., et al., 2024 United States Data Center Energy Usage Report. Lawrence Berkeley National Laboratory. Report #: LBNL-2001637. http://dx.doi.org/10.71468/P1WC7Q ↑
Hieta, K and Rodriguez, E., 2025. “How Will Data Center Growth Impact California Ratepayers?,” The Public Advocates Office, https://www.publicadvocates.cpuc.ca.gov/press-room/commentary/251027-how-will-data-center-growth-impact-california-ratepayers ↑
Norris, T.H., et al., 2025. Rethinking Load Growth: Assessing the Potential for Integration of Large Flexible Loads in US Power Systems. NI R 25-01. Durham, NC: Nicholas Institute for Energy, Environment & Sustainability, Duke University. https://nicholasinstitute.duke.edu/publications/rethinking-load-growth ↑
Shehabi, et al. Ibid ↑
Slide 8-9: Data Center Demand Growth, from CEC 2025 IEPR Forecast, https://www.energy.ca.gov/sites/default/files/2026-01/2026-01-05_DAWG_Mtg_Slides-Combined_ada.pdf ↑
2024-2025 Transmission Plan, CAISO ↑
Slide 20: Data Center Projection Pipeline, from PG&E 2024 Investor Update, https://s21.q4cdn.com/673114418/files/doc_events/2024/06/1/2024-Investor-Update-Presentation_Final.pdf ↑
John Pletz, “AI gold rush fuels ComEd crackdown on data center speculators,” Chicago Business, June 24, 2025;
https://www.chicagobusiness.com/utilities/comed-seeks-bigger-deposits-ai-era-data-centers ↑
Nick Evans, “Ohio Manufacturers’ Association challenges new utility billing for data centers,” Ohio Capital Journal, November 13, 2025; https://ohiocapitaljournal.com/2025/11/13/ohio-manufacturers-association-challenges-new-utility-billing-for-data-centers/ ↑
FERC Order to PJM, December 18, 2025, Docket EL25-49-000; https://www.ferc.gov/media/e-1-el25-49-000-0# ↑
PJM Interconnection, Midcontinent Independent System Operator, Southwest Poer Pool, California Independent System Operator, ISO New England, New York Independent System Operator ↑
FERC Launchs Aggressive Targeted Action to Speed Large Load Integration, https://www.ferc.gov/news-events/news/ferc-launches-aggressive-targeted-action-speed-large-load-integration ↑
R 26-04-009 ↑
A.24-11-007 ↑
Interconnection 101, American Clean Power Association , https://cleanpower.org/wp-content/uploads/gateway/2023/06/ACP_Interconnection_FactSheet_0623.pdf ↑
https://www.cpuc.ca.gov/industries-and-topics/electrical-energy/infrastructure/electric-reliability/undergrounding-program-description/rule-20/cpuc-rule-20-undergrounding-programs-current-proceeding-r1705010/electric-tariff-rules-15-and-16-distribution-line-and-service-extensions ↑
A.24-11-007 ↑
R.24-01-018 ↑
Pg. 26, “Little Hoover Commission Study to Review Data Centers and California Energy Policy, Pt. II,” December 11, 2025. https://lhc.ca.gov/wp-content/uploads/Revised-Commissioner-Information-12-11-25.pd ↑
Michael Medieros, “PG&E Written Testimony;” Letter to the Little Hoover Commission; December 8, 2025.
https://lhc.ca.gov/wp-content/uploads/PGE-LHC-Written-Testimony.pdf ↑
Daly, M., & Condon, B., In boost to Musk, Justice Department seeks to dismiss air pollution lawsuit against xAI data center. June 16, 2026, https://apnews.com/article/musk-xai-data-center-memphis-pollution-naacp-0e981ca0508d7e4144662392d9d66ab2 ↑
D.26-02-057 ↑
Public Utilities Code § 454.53 ↑
Slide 5, presentation by CEC Manager of Demand Analysis Heidi Javanbakht to the Little Hoover Commission, December 11, 2025; https://lhc.ca.gov/wp-content/uploads/5-Heidi-Javanbakht-CEC.pdf ↑
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-4171 | SB 886 |
THIRD READING
Bill No: SB 886
Author: Padilla (D), et al.
Amended: 5/14/26
Vote: 21
SENATE ENERGY, U. & C. COMMITTEE: 12-4, 3/17/26
AYES: Allen, Archuleta, Arreguín, Becker, Gonzalez, Hurtado, McNerney, Reyes, Richardson, Rubio, Stern, Wahab
NOES: Ochoa Bogh, Dahle, Grove, Strickland
NO VOTE RECORDED: Caballero
SENATE APPROPRIATIONS COMMITTEE: 5-2, 5/14/26
AYES: Cervantes, Cabaldon, Grayson, Richardson, Wahab
NOES: Seyarto, Dahle
SUBJECT: California Technology Innovation and Ratepayer Protection Act
SOURCE: Net-Zero California
The Utility Reform Network
DIGEST:
This bill requires the California Public Utilities Commission (CPUC) to establish an electrical corporation tariff that addresses utility costs for serving data centers that interconnect at the transmission level and have peak electricity demands of at least 25 megawatts (MW). This bill specifies components that must be included in the tariff, and it encourages local publicly owned electrical utilities (POUs) to adopt similar tariffs.
ANALYSIS:
Existing law:
- Authorizes the CPUC to supervise and regulate every public utility in the state and permits the CPUC to do anything that is necessary and convenient to exercise its power and jurisdiction. (Public Utilities Code §701)
- Authorizes the CPUC to set rates for public utilities and specifies that every cost charged by utilities to customers must be just and reasonable. (Public Utilities Code §451)
- Defines an electrical corporation as every corporation or person owning, controlling, operating, or managing any electric plant for compensation within this state, except where electricity is generated on or distributed by the producer through private property solely for its own use or the use of its tenants and not for sale or transmission to others. (Public Utilities Code §218)
- Defines a “retail seller” as an entity engaged in the retail sale of electricity to end-use customers located within the state. This definition expressly includes investor-owned utilities (IOUs), community choice aggregators (CCAs), and energy service providers (ESPs); however, this definition does not include the Department of Water Resources (DWR), POUs, or co-generation facilities. (Public Utilities Code §399.12(j))
- Creates the Renewables Portfolio Standard (RPS) by establishing a state goal of procuring at least 60% of total retail sales of electricity from renewable energy resources by December 31, 2030, with specified benchmarks up to that date. Existing law requires the CPUC to oversee electrical corporations’ compliance with renewable energy procurement mandates and requires the California Energy Commission (CEC) to oversee POU renewable energy procurement compliance. (Public Utilities Code §399.11 et. seq.)
- Establishes a policy to source 100% of all in-state retail electricity sales from zero-carbon resources by December 31, 2045. Existing law requires the CPUC, CEC and the California Air Resources Board (CARB) to incorporate this policy into all relevant plans. (Public Utilities Code §454.53)
- Authorizes the CPUC to assess the extent to which electrical corporation costs for new loads from data centers result in cost shifts to other electrical corporation customers. Existing law specifies that this assessment must be published by January 1, 2027, and it must include the following:
- An analysis of potential electrical corporation costs associated with utility procurement for data center electricity consumption.
- An analysis of potential electrical corporation costs associated with new transmission and distribution assets to serve new data centers or expansions of existing data centers, as specified.
- Identification of opportunities to address any substantial cost shifts. (Public Utilities Code §913.22)
- Establishes an opt-in permitting process at the CEC for certain non-fossil fueled power generation facilities. Existing law specifies certain criteria a facility must meet in order to qualify for this opt-in certification. These criteria include, but are not limited to, meeting certain labor standards for the construction of the facility seeking certification. Existing law specifies requirements regarding the use of a prevailing wage and skilled and trained workforce for opt-in permitting eligibility. (Public Resource Code §25545 et. seq.)
This bill:
- Defines a “data center” as a facility that primarily contains electronic equipment used to process, store, and transmit digital information. Data centers may be individual buildings or facilities within buildings that use environmental control equipment to maintain the proper conditions for the operation of electronic equipment.
- Clarifies that the following types of facilities are exempt from this bill’s requirements: publicly funded research facilities, public safety facilities, national security facilities, publicly owned facilities, and other utility facilities, including, but not limited to, assets of facilities-based telecommunications providers.
- Requires the CPUC to establish a rate structure by July 1, 2027, that includes an electrical corporation tariff addressing utility costs associated with providing electrical service to data centers taking electrical service at the transmission level with an estimated peak load of at least 25 MW. This bill specifies that interconnection components of a tariff shall only apply to data center facilities for which a new transmission interconnection agreement is established on or after the adoption of the tariff and associated rate structure required by this bill.
- Requires the CPUC to do all the following in establishing the data center tariff:
- Establish eligibility criteria for data center facilities.
- Evaluate the risks and benefits of this tariff to nonparticipating ratepayers.
- Ensure that the tariff prevents the creation of stranded costs for, or cost shifts to, nonparticipating ratepayers.
- Ensure that costs generally included in the generation component of a customer’s bill are assessed separate from charges generally included in the transmission and distribution components of the bill.
- Requires the tariff established by the CPUC to do all the following:
- For customers taking generation services from the electrical corporation, assign to a tariffed customer any unique wholesale energy cost, including ancillary and reliability services costs attributable to rapid fluctuations in demand by the participating customer.
- Include a reasonable share of costs typically collected from distribution customers, including costs for wildfire mitigation, wildfire liability, electrification and environmental programs, and other societal cost obligations generally collected through distribution rates.
- Require a data center to pre-fund a 15-year contract for the installation of new, incremental, zero-carbon resources sufficient to provide at least 50% of the facility’s hourly energy needs and provide dispatchable reliability assets within the facility’s utility service territory. A data center may meet this requirement by installing similar zero-emission resources behind the meter.
- Require a data center to participate in a new demand response program that does not result in net costs to other ratepayers.
- Require a data center submitting an interconnection application to disclose each instance in which the data center has submitted an application for that facility in other electrical corporation service territories or jurisdictions.
- Assign cost responsibility for all transmission facility upgrades triggered by a facility interconnection to the data center. To the extent permitted under federal law, these costs should include shared transmission grid network upgrades needed to accommodate the interconnection of the data center or increase the flow of electricity across the electrical grid.
- Allow a tariffed data center to receive refunds of a portion of its initial nominal dollar contributions to interconnection costs only to the extent that actual annual net revenues cover the costs of energization, the costs of providing electric service, and other costs allocated by the CPUC to the tariffed customer. This bill caps refunds to no more than 75% of the annual net revenue received by the electrical corporation from the tariffed customer.
- Include an early termination fee to be assessed against any tariffed data center that departs the electrical system within 15 years of the initial interconnection of the facility or fails to achieve full load ramp up. The early termination fee should not be less than the revenue gap associated with the originally projected demand and energy consumption of the facility over the minimum 15-year term.
- Requires each electrical corporation to publish and update maps showing locations where data centers customers can interconnect without the need for significant, costly, and time-consuming transmission upgrades.
- Requires every tariffed data center to certify that it meets specified labor requirements generally applied to certain non-fossil fueled power facilities, including prevailing wage and skilled and trained workforce requirements.
Background
Rapid data center growth has been linked to ratepayer concerns in a number of states. The growth of data centers – particularly those data centers that support generative artificial intelligence (AI) – is leading to increased energy costs in many US states. This growth is expected to accelerate in the near future. According to a May 2024 report from the CEC, data centers comprise approximately two percent of the state’s total annual electricity demand. The CEC anticipates that data centers’ electricity consumption may double in the next 10 years without implementation of any additional energy efficiency measures. In December 2024, the United States Department of Energy released a report by the Lawrence Berkeley National Laboratory on data centers’ energy use. The report shows that data centers’ electricity use comprised approximately 4.4% of the United States’ total electricity consumption in 2024. The report also estimates that data centers may comprise between 6.7% to 12% of national electricity consumption by 2028.
As electricity demands from data centers increase, grid and utility costs are also increasing. Pennsylvania – New Jersey – Maryland Interconnection (PJM) operates the largest regional grid in the United States. In January 2026, data from PJM indicated that 40% of its expected increased electricity demand will come from data centers. With this increase in electricity demands, PJM has seen record high costs for electricity to meet future reliability needs in addition to new transmission costs. Consumers in four states within PJM territory paid over $4 billion in 2024 alone for transmission projects serving data centers. Currently, the majority of California’s data center load growth has occurred in service territories of local POUs and those of CCAs. However, the IOUs have also seen a recent increase in load growth from data centers and a substantial increase in applications for transmission-level interconnection.
Bill overlaps with ongoing CPUC proceedings. In November 2024, PG&E filed an application at the CPUC to establish a new electric rule for retail electricity customers seeking interconnection at the transmission level. (Application 24-11-007). According to PG&E’s filings, data centers were 67% of the 34 transmission interconnection applications that PG&E received between 2023 and November 2024. In July 2025, the CPUC issued an initial decision (D. 25-07-039) that approved an interim PG&E electric rule for data centers that pre-pay the cost of interconnection. In February 2026, the CPUC issued a schedule for the next phase of the proceeding to consider additional electric rule requirements for transmission interconnection, including mechanisms for covering utility costs. Certain provisions of this bill overlap with issues that are currently included in the ongoing Rule 30 proceeding. Some provisions also mirror certain provisions of prior CPUC resolutions regarding specific transmission interconnection advice letters. For example, this bill caps at 75% the annual amount that an IOU can re-pay a large-load customer for any advance loan that the customer provides to the IOU to cover costs for the transmission and distribution interconnection. This bill’s limit on repayments is identical to a limit included in a CPUC resolution (E-5420) approving and modifying an advice letter (AL 7569-E) submitted by PG&E regarding the transmission interconnection of a 90 MW data center in San Jose. On April 9, 2026, the CPUC started the process to open a rulemaking (R.26-04-009) on the California Advanced Electric Rate Design. As part of this proceeding the CPUC intends to explore opportunities to address affordability challenges associated with rapid load growth, including load from data centers. The CPUC intends to explore rate designs and tariffs for data center customers to address affordability issues in this proceeding. The CPUC intends to publish a staff proposal on rate reform as part of this proceeding in the 3rd Quarter of 2026. To the extent that the CPUC adopts decisions in the ongoing proceeding that conflict with this bill, this bill may require the CPUC to revise its decisions.
Data centers are growing in California, but other facilities may have larger electricity impacts over time. California has experienced load growth associated with data center expansion; however, this growth has been more gradual than the increased demand experienced by some other states. The CEC, CPUC and California Independent System Operator (CAISO) have all projected varying increases in load from data centers. In forecasts focusing on near term demand, the CEC has shown that CAISO may experience a 1.8 gigawatt (GW) load growth from data centers by 2030. However, the CEC’s energy demand forecast covering 2025 through 2045 indicates that vehicle electrification will be the largest driver of peak electricity demand in the state by 2045. While data centers are expected to increase peak electricity demand by 4.7 GW by 2045, electric vehicles (EVs) may contribute approximately 8.2 GW to peak demand. Regardless of the sector contributing to the largest share of future energy costs, serving these future loads will necessarily require additional resources. To address these needs, the CPUC has ordered utilities under its jurisdiction to collectively procure 6 GW of new zero emissions energy resources by 2032. This 6 GW procurement is intended to cover near-term load growth and account for delays in delivering previously planned renewable resources, including off-shore wind resources. While the CPUC’s California Advanced Electric Rate Design proceeding will address cost drivers across multiple sectors that include businesses with large energy demands, this bill focuses on establishing a rate structure to specifically address costs associated with data centers that interconnect at the transmission level.
One tariff does not necessarily fit all. This bill is aimed at establishing a mechanism to prevent utility costs triggered by interconnecting and serving data centers from impacting the utility bills of other customers. For example, this bill requires the transmission interconnection provisions of the tariff to include early termination fees that cover revenue gaps associated with 15-year electric generation procurement contracts. For bundled customers of an IOU that receive transmission, distribution, and retail electric service from the IOU, it is possible that a tariff could address all the IOU costs associated with serving that customer; however, for unbundled customers receiving retail service from a CCA, the CCA would be responsible for procuring electric generation resources to serve the tariffed customer. While IOUs own transmission and distribution facilities, CCAs do not currently own these facilities. As a result, a transmission interconnection tariff cannot effectively include costs for retail electric service provided by a CCA, and CCAs do not file tariffs with the CPUC. For those data centers that are unbundled customers of CCA, it is unclear how a single tariff filed by an IOU can effectively govern costs associated with generation services arranged through a CCA. This bill requires the tariff to ensure that generation elements of a customer’s bill can be assessed separately from costs generally included in the transmission and distribution costs. However, this bill applies the interconnection provisions of the tariff to only those facilities with at least 25 MW of peak electricity demand that interconnect at the transmission level. Not all data centers with 25 MW of load will interconnect at the transmission level and a substantial number of large data centers are not IOU customers. While this bill’s provisions related to transmission costs may only apply to larger data centers that establish new transmission interconnections, other provisions of this bill may apply to any data center, including existing data centers that are not seeking any upgrades or changes to electrical facilities or services.
Prior/Related Legislation
SB 887 (Padilla) of 2026, establishes certain permitting permissions for data centers that meet specified criteria. These criteria include provisions similar to the requirements for the tariff specified in this bill. The bill is pending in the Senate.
SB 978 (Pérez) of 2026, would have required the CPUC to create a special rate structure for large data centers prevent cost shifts to other customers. The bill would have established labor requirements for the construction of facilities subject to the bill. The bill would have expanded existing CPUC reporting requirements to include a specified assessment about data center impacts to renewable procurement goals. The bill was held by the Senate Appropriations Committee.
SB 57 (Padilla, Chapter 647, Statutes of 2025) authorized the CPUC to assess the extent to which electrical corporation costs for new loads from data centers result in cost shifts to other electrical corporation customers. The bill also required the CPUC to publish and submit a report regarding its assessment to the relevant legislative policy committees by January 1, 2027.
AB 222 (Bauer-Kahan) of 2025, would have required the CPUC to assess the extent to which electrical corporation costs for serving data centers result in cost shifts to other customers. The bill also required the CEC to establish a process for data centers to submit specified energy efficiency data to the CEC, and it required the CEC to assess data centers’ energy consumption. The bill was held by the Senate Appropriations Committee.
SB 1298 (Cortese) of 2024, would have increased the amount of thermal generation a data center could use as backup power from 100 MW to 150 MW without triggering the CEC’s power plant siting process. The bill would have also created conditions for data centers to use this exemption. The bill died in the Assembly.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
According to the Senate Appropriations Committee:
- The CPUC estimates one-time costs likely between $750,000 and $2 million spread over two years as well as ongoing costs ranging from approximately $500,000 to $1.2 million annually (ratepayer funds) for additional staff and administrative resources needed to establish and implement a new tariff and regulatory framework.
- To the extent that this bill increases electricity costs for ratepayer-funded facilities, this bill could result in cost shifts to those ratepayers.
SUPPORT: (Verified 5/14/26)
Net-Zero California (Co-source)
The Utility Reform Network (Co-source)
AARP
Brawley Chamber of Commerce
Brightline Defense
California Environmental Voters
California State Association of Electrical Workers
California State Pipe Trades Council
Center for Biological Diversity
City of Buena Park
City of Imperial
City of Monterey Park
Climate Action California
Coalition of California Utility Employees
Comité de Acción del Valle Inc.
E2
Earthjustice
Herber Public Utility District
Imperial Valley Equity & Justice
International Brotherhood of Electrical Workers, Local Union 569
Kapor Center Advocacy
Kuhn Hay, Inc.
Leadership Council for Justice and Accountability
Little Hoover Commission
Los Amigos de la Comunidad, Inc.
Natural Resources Defense Council
NRDC Action Fund
Sierra Club California
Sustainable Rossmoor
Victoria Homes
Western States Council Sheet Metal, Air, Rail and Transportation
OPPOSITION: (Verified 5/14/26)
Bay Area Council
Bloom Energy
CalAsian Chamber of Commerce
California African American Chamber of Commerce
California Chamber of Commerce
California Hispanic Chamber of Commerce
California Large Energy Consumers Association
California Manufacturers and Technology Association
Data Center Coalition
Enchanted Rock
Mainspring Energy
Pacific Gas & Electric Company
San Diego Gas & Electric
Silicon Valley Leadership Group
TechCa
TechNet
Western States Petroleum Association
ARGUMENTS IN SUPPORT: According to the Author:
Multiple studies have found data centers increase costs for ordinary ratepayers as they drive skyrocketing demand without corresponding growth in supply. Moreover, these high intensity energy users require expensive infrastructure upgrades that ordinary ratepayers are paying for. Without taking steps to mitigate these cost shifts, rates are estimated to go up 8%. Microsoft, Meta, and Anthropic have stated they will pay for the cost of interconnection to their data centers, and this bill puts these commitments into law.
ARGUMENTS IN OPPOSITION: A coalition of technology, manufacturing, and business associations oppose this bill, arguing that the bill is unnecessary, may negatively impact economic development and decarbonization goals, and would conflict with the CPUC’s ongoing rulemaking regarding PG&E’s Rule 30 application. In opposition, the California Chamber of Commerce states:
California is competing with other states to attract advanced manufacturing, data centers, and other electricity-intensive industries that support economic growth and technological innovation. Policies that impose unusually burdensome infrastructure requirements while also limiting operational control over privately financed energy assets risk discouraging the development of these facilities in California. Grid flexibility and reliability are important goals, but they should be pursued through voluntary programs and market incentives rather than mandates that deter new investment in the state’s electricity system. For these reasons, the California Chamber of Commerce respectfully urges the Legislature to reject SB 886.
Prepared by: Sarah Smith / E., U. & C. / (916) 651-4107
5/18/26 15:03:41
**** END ****
SENATE COMMITTEE ON
Senator Sabrina Cervantes, Chair
2025 - 2026 Regular Session
SB 886 (Padilla) - California Technology Innovation and Ratepayer Protection Act
Version: | Policy Vote: |
Urgency: | Mandate: |
Hearing Date: | Consultant: |
Bill Summary:
This bill would require the California Public Utilities Commission (CPUC) to establish an electrical corporation tariff that addresses costs associated with transmission, distribution, and generation services for “participating customers,” as defined, and would require a participating customer to prefund a contract of at least 15 years in duration for the installation of new, incremental, zero-carbon energy resources, and to participate in a new demand response program, as provided. It would also encourage local publicly owned electrical utilities (POUs) to adopt similar tariffs.
*********** ANALYSIS ADDENDUM – SUSPENSE FILE ***********
The following information is revised to reflect amendments
adopted by the committee on May 14, 2026
Fiscal Impact:
- The CPUC estimates one-time costs likely between $750,000 and $2 million spread over two years as well as ongoing costs ranging from approximately $500,000 to $1.2 million annually (ratepayer funds) for additional staff and administrative resources needed to establish and implement a new tariff and regulatory framework.
- To the extent that this bill increases electricity costs for ratepayer-funded facilities, this bill could result in cost shifts to those ratepayers.
Committee Amendments:
Committee amendments would:
1. Remove provisions related to the POUs.
2. Clarify certain terms and definitions to ensure that the definition of a “data center” subject to the requirements of the bill is consistent throughout.
-- END --
SENATE COMMITTEE ON
Senator Sabrina Cervantes, Chair
2025 - 2026 Regular Session
SB 886 (Padilla) - California Technology Innovation and Ratepayer Protection Act
Version: | Policy Vote: |
Urgency: | Mandate: |
Hearing Date: | Consultant: |
Bill Summary:
This bill would require the California Public Utilities Commission (CPUC) to establish an electrical corporation tariff that addresses costs associated with transmission, distribution, and generation services for “participating customers,” as defined, and would require a participating customer to prefund a contract of at least 15 years in duration for the installation of new, incremental, zero-carbon energy resources, and to participate in a new demand response program, as provided. It would also encourage local publicly owned electrical utilities (POUs) to adopt similar tariffs.
Fiscal Impact:
- The CPUC estimates one-time costs likely between $750,000 and $2 million spread over two years as well as ongoing costs ranging from approximately $500,000 to $1.2 million annually (ratepayer funds) for additional staff and administrative resources needed to establish and implement a new tariff and regulatory framework.
- To the extent that this bill increases electricity costs for ratepayer-funded and publicly funded facilities, this bill could result in cost shifts to those ratepayers and public programs.
Background:
The growth of data centers – particularly those data centers that support generative artificial intelligence (AI) – is leading to increased energy costs in many US states. This growth is expected to accelerate in the near future. According to a May 2024 report from the CEC, data centers comprise approximately two percent of the state’s total annual electricity demand. The CEC anticipates that data centers’ electricity consumption may double in the next 10 years without implementation of any additional energy efficiency measures. In December 2024, the United States Department of Energy released a report by the Lawrence Berkeley National Laboratory on data centers’ energy use. The report shows that data centers’ electricity use comprised approximately 4.4% of the United States’ total electricity consumption in 2024. The report also estimates that data centers may comprise between 6.7% to 12% of national electricity consumption by 2028.
As electricity demands from data centers increase, grid and utility costs are also increasing. Pennsylvania – New Jersey – Maryland Interconnection (PJM) operates the largest regional grid in the United States. In January 2026, data from PJM indicated that 40% of its expected increased electricity demand will come from data centers. With this increase in electricity demands, PJM has seen record high costs for electricity to meet future reliability needs in addition to new transmission costs. Consumers in four states within PJM territory paid over $4 billion in 2024 alone for transmission projects serving data centers. California has not experienced the level of data center growth seen in some other states; however, a number of California’s utilities are projecting substantial data center load growth in the next four years. Currently, the majority of California’s data center load growth has occurred in service territories of local POUs and those of CCAs. However, the IOUs have also seen a recent increase in load growth from data centers and a substantial increase in applications for transmission-level interconnection.
Proposed Law:
This bill would require the CPUC to establish an electrical corporation tariff that addresses costs associated with transmission, distribution, and generation services for participating customers, among other things. Specifically, this bill would:
- Require the CPUC, on or before July 1, 2027, to establish a rate structure that includes an electrical corporation tariff for the interconnection of the participating customer facilities and the provision of transmission, distribution, and generation services to participating customers, as specified.
- Require the CPUC, as part of establishing the electrical corporation tariff, to, at a minimum, establish eligibility criteria for participating customers and facilities, as defined; evaluate the risks and benefits of the electrical corporation tariff to nonparticipating customers; and ensure that the electrical corporation tariff prevents the creation of stranded costs for, or cost shifts to nonparticipating customers, and, for unbundled customers, ensure that charges generally included in the generation component of their bills are assessed separately from charges generally included in the transmission and distribution components of their bills.
- Require that the electrical corporation tariff require a participating customer that submits an application for interconnection of a facility to an electrical corporation to disclose whether an application for the same facility has been submitted in other electrical corporation service territories or other jurisdictions and to disclose each instance in which an application for the same facility has been submitted.
- Require that the electrical corporation tariff, among other things, assign cost responsibility for all transmission facility upgrades triggered by a new facility interconnection to the applicable participating customer and require an early termination fee to be assessed against a participating customer under specified circumstances.
- Require a participating customer to prefund a contract of at least 15 years in duration through the electrical corporation, community choice aggregator, or electric service provider for the installation of new, incremental, zero-carbon energy resources, and to participate in a new demand response program authorized by the commission, as provided.
- Require each electrical corporation to publish and update maps showing locations where large load participating customers can interconnect without the need for significant, costly, and time-consuming transmission upgrades.
- Encourage each local publicly owned electric utility to develop a tariff that is similar to the electrical corporation tariff described above and ensures, among other things, that costs are not shifted from a customer that is not subject to that tariff to a customer that is subject to that tariff, and that the costs of investments in infrastructure made by a customer that is subject to that tariff are not recoverable from other customers that are not subject to that tariff.
- Provide that under existing law, a violation of any order, decision, rule, direction, demand, or requirement of the commission is a crime. State that because a violation of a commission action implementing this bill’s requirements would be a crime, the bill would impose a state-mandated local program.
Related Legislation:
SB 887 (Padilla) of 2026, would establish certain permitting permissions for data centers that meet specified criteria. These criteria include provisions similar to the requirements for the tariff specified in this bill.
SB 978 (Pérez) of 2026, would require the CPUC to create a special rate structure for certain large energy users with capacities of at least 75 MW to prevent cost shifts to other customers. The bill would also establish labor requirements for the construction of facilities subject to the bill. The bill would expand existing CPUC reporting requirements about large loads to include a specified assessment about increased load impacts to renewable procurement goals.
SB 57 (Padilla, Chapter 647, Statutes of 2025) authorized the CPUC to assess the extent to which electrical corporation costs for new loads from data centers result in cost shifts to other electrical corporation customers. The bill also required the CPUC to publish and submit a report regarding its assessment to the relevant legislative policy committees by January 1, 2027.
AB 222 (Bauer-Kahan) of 2025, would have required the CPUC to assess the extent to which electrical corporation costs for serving data centers result in cost shifts to other customers. The bill also required the CEC to establish a process for data centers to submit specified energy efficiency data to the CEC, and it required the CEC to assess data centers’ energy consumption. The bill was held by the Senate Appropriations Committee.
SB 1298 (Cortese) of 2024, would have increased the amount of thermal generation a data center could use as backup power from 100 MW to 150 MW without triggering the CEC’s power plant siting process. The bill would have also created conditions for data centers to use this exemption. The bill died in the Assembly.
-- END --
SENATE COMMITTEE ON ENERGY, UTILITIES AND COMMUNICATIONS
Senator Benjamin Allen, Chair
2025 - 2026 Regular
Bill No: Hearing Date: 3/17/2026
Author: | |||
Version: | Amended | ||
Urgency: | Fiscal: | ||
Consultant: | |||
SUBJECT:
DIGEST: This bill requires the California Public Utilities Commission (CPUC) to establish an electrical corporation tariff that addresses costs associated with transmission, distribution, and generation services for new large electrical customers that interconnect at the transmission level and have peak electricity demands of at least 75 megawatts (MW). This bill specifies components that must be included in the tariff, and it encourages local publicly owned electrical utilities (POUs) to adopt similar tariffs.
ANALYSIS:
Existing law:
- Authorizes the CPUC to supervise and regulate every public utility in the state and permits the CPUC to do anything that is necessary and convenient to exercise its power and jurisdiction. (Public Utilities Code §701)
- Authorizes the CPUC to set rates for public utilities and specifies that every cost charged by utilities to customers must be just and reasonable. (Public Utilities Code §451)
- Defines an electrical corporation as every corporation or person owning, controlling, operating, or managing any electric plant for compensation within this state, except where electricity is generated on or distributed by the producer through private property solely for its own use or the use of its tenants and not for sale or transmission to others. (Public Utilities Code §218)
- Defines a “retail seller” as an entity engaged in the retail sale of electricity to end-use customers located within the state. This definition expressly includes investor-owned utilities (IOUs), community choice aggregators (CCAs), and energy service providers (ESPs); however, this definition does not include the Department of Water Resources (DWR), POUs, or co-generation facilities. (Public Utilities Code §399.12(j))
- Creates the Renewables Portfolio Standard (RPS) by establishing a state goal of procuring at least 60% of total retail sales of electricity from renewable energy resources by December 31, 2030, with specified benchmarks up to that date. Existing law requires the CPUC to oversee electrical corporations’ compliance with renewable energy procurement mandates and requires the California Energy Commission (CEC) to oversee POU renewable energy procurement compliance. (Public Utilities Code §399.11 et. seq.)
- Establishes a policy to source 100% of all in-state retail electricity sales from zero-carbon resources by December 31, 2045. Existing law requires the CPUC, CEC and the California Air Resources Board (CARB) to incorporate this policy into all relevant plans. (Public Utilities Code §454.53)
- Authorizes the CPUC to assess the extent to which electrical corporation costs for new loads from data centers result in cost shifts to other electrical corporation customers. Existing law specifies that this assessment must be published by January 1, 2027, and it must include the following:
- An analysis of potential electrical corporation costs associated with utility procurement for data center electricity consumption.
- An analysis of potential electrical corporation costs associated with new transmission and distribution assets to serve new data centers or expansions of existing data centers, as specified.
- Identification of opportunities to address any substantial cost shifts. (Public Utilities Code §913.22)
- Establishes an opt-in permitting process at the CEC for certain non-fossil fueled power generation facilities. Existing law specifies certain criteria a facility must meet in order to qualify for this opt-in certification. These criteria include, but are not limited to, meeting certain labor standards for the construction of the facility seeking certification. Existing law specifies requirements regarding the use of a prevailing wage and skilled and trained workforce for opt-in permitting eligibility. (Public Resource Code §25545 et. seq.)
This bill:
- Defines a “large load customer” as a customer connecting at the transmission level with an estimated peak demand of at least 75 MW. This definition excludes an existing customer that adds load as a result of switching from fossil fuels to renewable fuels or transportation electrification activities.
- Requires the CPUC to establish an electrical corporation tariff for large load customers seeking transmission interconnection.
- Requires this tariff to govern large load customers’ transmission, distribution, and generation services.
- Requires the CPUC to do all the following in establishing the large load customer tariff:
- Establish eligibility criteria for large load customers and facilities.
- Evaluate the risks and benefits of this tariff to nonparticipating ratepayers.
- Ensure that the tariff prevents the creation of stranded costs for, or cost shifts to, nonparticipating ratepayers.
- Requires the tariff established by the CPUC to do all the following:
- For customers taking generation services from the electrical corporation, assign to a tariffed customer any unique wholesale energy cost, including ancillary and reliability services costs attributable to rapid fluctuations in demand by the participating customer.
- Include a reasonable share of costs typically collected from distribution customers, including costs for wildfire mitigation, wildfire liability, electrification and environmental programs, and other societal cost obligations generally collected through distribution rates.
- Require a large load customer submitting an interconnection application to disclose each instance in which the customer has submitted an application for that facility in other electrical corporation service territories or jurisdictions.
- Assign cost responsibility for all transmission facility upgrades triggered by a facility interconnection to the tariffed customer. To the extent permitted under federal law, these costs should include shared transmission grid network upgrades needed to accommodate the interconnection of the participating customer’s facility or increase the flow of electricity across the electrical grid.
- Allow a participating customer to receive refunds of a portion of its initial nominal dollar contributions to interconnection costs only to the extent that actual annual net revenues cover the costs of energization, the costs of providing electric service, and other costs allocated by the CPUC to the tariffed customer. This bill caps refunds to no more than 75% of the annual net revenue received by the electrical corporation from the tariffed customer.
- Require an early termination fee to be assessed against any tariffed customer that departs the electrical system within 15 years of the initial interconnection of the facility or fails to achieve full load ramp up. The early termination fee should not be less than the revenue gap associated with the originally projected demand and energy consumption of the facility over the minimum 15-year term.
- Each tariffed customer shall be required to install onsite zero-carbon energy storage with at least four hours of capacity at no less than 50% of forecasted peak demand. Storage capacity shall be dispatchable by the electrical corporation or California Independent System Operator (CAISO) to address emergency conditions on the electrical grid.
- Each tariffed customer shall participate in demand response programs as determined by the CPUC.
- Each electrical corporation shall be required to publish and update maps showing locations where large load customers can interconnect without the need for significant, costly, and time-consuming transmission upgrades.
- Requires every tariffed facility to certify that it meets specified labor requirements generally applied to non-fossil fueled power plants certified by the CEC, including prevailing wage and skilled and trained workforce requirements.
- Encourages POUs to develop a tariff that ensures that costs associated with new large loads are not shifted on to other non-tariffed customers.
Background
Rapid data center growth has been linked to ratepayer concerns in a number of states. The growth of data centers – particularly those data centers that support generative artificial intelligence (AI) – is leading to increased energy costs in many US states. This growth is expected to accelerate in the near future. According to a May 2024 report from the CEC, data centers comprise approximately two percent of the state’s total annual electricity demand. The CEC anticipates that data centers’ electricity consumption may double in the next 10 years without implementation of any additional energy efficiency measures. In December 2024, the United States Department of Energy released a report by the Lawrence Berkeley National Laboratory on data centers’ energy use. The report shows that data centers’ electricity use comprised approximately 4.4% of the United States’ total electricity consumption in 2024. The report also estimates that data centers may comprise between 6.7% to 12% of national electricity consumption by 2028.
As electricity demands from data centers increase, grid and utility costs are also increasing. Pennsylvania – New Jersey – Maryland Interconnection (PJM) operates the largest regional grid in the United States. In January 2026, data from PJM indicated that 40% of its expected increased electricity demand will come from data centers. With this increase in electricity demands, PJM has seen record high costs for electricity to meet future reliability needs in addition to new transmission costs. Consumers in four states within PJM territory paid over $4 billion in 2024 alone for transmission projects serving data centers. California has not experienced the level of data center growth seen in some other states; however, a number of California’s utilities are projecting substantial data center load growth in the next four years. Currently, the majority of California’s data center load growth has occurred in service territories of local POUs and those of CCAs. However, the IOUs have also seen a recent increase in load growth from data centers and a substantial increase in applications for transmission-level interconnection.
Bill overlaps with ongoing CPUC proceeding on Pacific Gas & Electric’s (PG&E’s) Rule 30 application. In November 2024, PG&E filed an application at the CPUC to establish a new electric rule for retail electricity customers seeking interconnection at the transmission level. (Application 24-11-007). According to PG&E’s filings, data centers were 67% of the 34 transmission interconnection applications that PG&E received between 2023 and November 2024. In July 2025, the CPUC issued an initial decision (D. 25-07-039) that approved an interim PG&E electric rule for data centers that pre-pay the cost of interconnection. In February 2026, the CPUC issued a schedule for the next phase of the proceeding to consider additional electric rule requirements for transmission interconnection, including mechanisms for covering utility costs. Certain provisions of this bill overlap with issues that are currently included in the ongoing Rule 30 proceeding. Some provisions also mirror certain provisions of prior CPUC resolutions regarding specific transmission interconnection advice letters. For example, this bill caps at 75% the annual amount that an IOU can re-pay a large-load customer for any advance loan that the customer provides to the IOU to cover costs for the transmission and distribution interconnection. This limit on repayments is identical to a limit included in a CPUC resolution (E-5420) approving and modifying an advice letter (AL 7569-E) submitted by PG&E regarding the transmission interconnection of a 90 MW data center in San Jose. To the extent that the CPUC adopts decisions in the ongoing Rule 30 proceeding that conflict with this bill, this bill may require the CPUC to revise its decisions and extend the Rule 30 proceeding.
One tariff does not necessarily fit all. This bill is aimed at establishing a mechanism to prevent utility costs triggered by interconnecting and serving data centers from impacting the utility bills of other customers. While this bill only impacts certain large-load customers receiving transmission-level service, this bill requires the tariff to encompass costs beyond those typically recovered in transmission and distribution rates. For example, this bill requires the transmission interconnection provisions of the tariff to include early termination fees that cover revenue gaps associated with 15-year electric generation procurement contracts. For bundled customers of an IOU that receive transmission, distribution, and retail electric service from the IOU, it is possible that a tariff could address all the IOU costs associated with serving that customer; however, for unbundled customers receiving retail service from a CCA, the CCA would be responsible for procuring electric generation resources to serve the tariffed customer. While IOUs own transmission and distribution facilities, CCAs do not currently own these facilities. As a result, a transmission interconnection tariff cannot effectively include costs for retail electric service provided by a CCA.
What types of utility customers are impacted by this bill? This bill’s tariff would apply to large-load customers across a variety of sectors. While the majority of large-load customers requesting new transmission interconnections have been data centers, this bill does not solely apply to data centers. Facilities covered by this bill may include a number of commercial and industrial facilities in the state, including some local utility facilities such as water treatment plants and waste management operations. Additionally, this bill applies to all large-load facilities that meet the definition of a data center, including telecommunications facilities that comprise the state’s telecommunications network, state-owned and operated facilities, research institutions, and public safety and national security facilities. This bill requires the CPUC to establish eligibility criteria for the tariff; however, it is not clear whether the CPUC would exclude additional facilities from the tariff. To the extent that this bill increases electricity costs for ratepayer-funded and publicly funded facilities, this bill may result in cost shifts to those ratepayers and public programs.
Balancing emissions reduction goals with protecting ratepayer interests. This bill’s tariff would apply to facilities that have a capacity of at least 75 MW and interconnect at transmission voltages. This bill’s definition of a large-load customer subject to this bill’s tariff explicitly excludes existing utility customers whose load increases as a result of transportation electrification or decarbonization activities that increase the use of renewable energy to replace fossil fuels. To the extent that this bill would increase electrical costs for a customer covered by this bill’s tariff, this bill could serve as a disincentive to electrification for large commercial and industrial facilities that take transmission-level electric service. Under California’s emissions reduction policies, including Cap-and-Invest policies overseen by CARB, existing commercial and industrial facilities producing emissions may use a variety of mechanisms to reduce emissions to progressively lower limits. Certain commercial and industrial facilities may choose to electrify activities that are currently using fossil fuels in order to reduce their emissions. For example, facilities with high-heat processes may switch from burning fossil fuels to using electricity to generate heat. These fuel-switching activities may substantially increase electrical loads and may require transmission upgrades to facilitate the use of higher voltages. By excluding existing commercial and industrial customers that increase electricity use for decarbonization activities, this bill will allow existing facilities that are already customers of the electrical corporation to electrify without potentially paying higher electric bills that may be required of customers subject to the tariff. While this bill supports electrification for existing utility customers, this bill’s tariff would still apply to new utility customers. As a result, new large-load facilities that on-shore certain manufacturing processes or establish new large electric vehicle (EV) charging depots would be subject to the tariff unless exempted by the CPUC.
Trigger for applying the tariff is unclear. This bill requires the CPUC to establish a tariff for certain large-load customers interconnecting to transmission. This bill expressly requires the large-load customer to pay for transmission infrastructure costs, including upgrade costs, triggered by the interconnection; however, it is unclear if only customers requesting new transmission interconnections will trigger this bill’s tariff. Some transmission upgrades occur as a result of an existing transmission-interconnected customer increasing the voltage at which a facility receives power. A number of other transmission upgrades, including certain wildfire safety upgrades, occur at the initiative of the utility – not the customer.
Bill’s behind-the-meter generation siting requirements may be infeasible on a statewide basis. This bill requires customers subject to its tariff to install behind-the-meter zero-carbon energy storage with at least four hours of capacity for at least 50% of the facility’s peak electricity demand needs. This bill also requires this storage to be dispatchable by the utility or CAISO to serve as an emergency reliability grid asset. To provide this amount of behind-the-meter energy storage for a facility of 75 MW or more, a customer would likely need a parcel of at least several acres in order to site the energy storage and its associated business operations. Such large parcels are likely unavailable in certain parts of the state, which may discourage data center construction in-state or increase the likelihood that data centers will only locate in areas of the state where large parcels of land may be purchased.
Need for Amendments. As currently drafted, this bill would require IOUs to file tariffs that encompass costs and services generally included in CCA rates for unbundled customers. It is also unclear whether this bill applies when a new interconnection agreement is executed or when upgrades are made. This bill requires tariffed customers to participate in existing demand response programs; however, it is unclear if these existing demand response programs are structured to meet the requirements of these large load customers while providing ratepayer benefits. Additionally, this bill’s behind-the-meter energy storage requirements may be infeasible in portions of the state. This bill’s tariff may apply to other utility and public institutions in a manner that may increase costs for certain public programs and shift costs to other utility customers. For these reasons, the author and committee may wish to amend this bill to do the following:
- Narrow this bill to only apply to large load data centers.
- Recast this bill’s tariff requirements to instead require the CPUC to include a transmission and distribution tariff as part of a rate structure that addresses the potential cost shift posed by new large-load data centers taking transmission-level service.
- Clarify that this bill applies only to those facilities for which a new transmission interconnection agreement is established after the adoption of the rate structure created pursuant to this bill or on a later date specified by the CPUC.
- Remove provisions related to generation components of a customer bill from the items that must be included in a transmission tariff and instead require the CPUC to ensure that costs assigned to transmission services can be tariffed separately from items generally included in the generation component of a customer’s bill.
- Replace this bill’s behind-the-meter energy storage requirement with a requirement that the CPUC establish a process by which a customer covered by this bill can pre-fund a 15-year contract for new, incremental, zero-carbon energy resources to function as dispatchable reliability assets within the utility service territory.
- Replace the requirement that data centers participate in existing demand response programs with a requirement that the CPUC consider requiring tariffed facilities to participate in demand response programs if the CPUC determines that such requirements are in the best interest of ratepayers.
- Exempt publicly-funded research facilities, public safety facilities, national security facilities, publicly owned facilities, and other utility facilities – including facilities-based telecommunications assets from the bill.
Prior/Related Legislation
SB 887 (Padilla) of 2026, establishes certain permitting permissions for data centers that meet specified criteria. These criteria include provisions similar to the requirements for the tariff specified in this bill. The bill is pending in the Senate Environmental Quality Committee.
SB 978 (Pérez) of 2026, requires the CPUC to create a special rate structure for certain large energy users with capacities of at least 75 MW to prevent cost shifts to other customers. The bill would also establish labor requirements for the construction of facilities subject to the bill. The bill would expand existing CPUC reporting requirements about large loads to include a specified assessment about increased load impacts to renewable procurement goals. The bill is pending in the Senate Energy, Utilities, and Communications Committee.
SB 57 (Padilla, Chapter 647, Statutes of 2025) authorized the CPUC to assess the extent to which electrical corporation costs for new loads from data centers result in cost shifts to other electrical corporation customers. The bill also required the CPUC to publish and submit a report regarding its assessment to the relevant legislative policy committees by January 1, 2027.
AB 222 (Bauer-Kahan) of 2025, would have required the CPUC to assess the extent to which electrical corporation costs for serving data centers result in cost shifts to other customers. The bill also required the CEC to establish a process for data centers to submit specified energy efficiency data to the CEC, and it required the CEC to assess data centers’ energy consumption. The bill was held by the Senate Appropriations Committee.
SB 1298 (Cortese) of 2024, would have increased the amount of thermal generation a data center could use as backup power from 100 MW to 150 MW without triggering the CEC’s power plant siting process. The bill would have also created conditions for data centers to use this exemption. The bill died in the Assembly.
FISCAL EFFECT: Appropriation: Fiscal Com.: Local:
SUPPORT:
Net-Zero California (Co-sponsor)
The Utility Reform Network (Co-sponsor)
Brawley Chamber of Commerce
Brightline Defense, if amended
California Environmental Voters, if amended
Center for Biological Diversity, if amended
City of Imperial
City of Monterey Park
Climate Action California
Comité de Acción del Valle Inc.
E2
Earthjustice, if amended
International Brotherhood of Electrical Workers, Local Union 569
Kapor Center Advocacy
Kuhn Hay, Inc.
Leadership Council for Justice and Accountability, if amended
Los Amigos de la Comunidad, Inc.
Natural Resources Defense Council
NRDC Action Fund
Sierra Club California, if amended
Victoria Homes
OPPOSITION:
Bay Area Council, unless amended
Bloom Energy
CalAsian Chamber of Commerce
California African American Chamber of Commerce
California Chamber of Commerce
California Hispanic Chamber of Commerce
California Large Energy Consumers Association, unless amended
California Manufacturers and Technology Association
Data Center Coalition
Enchanted Rock
Mainspring Energy
Pacific Gas and Electric Company
Silicon Valley Leadership Group
TechCa
TechNet
Western States Petroleum Association, unless amended
ARGUMENTS IN SUPPORT: According to the Author:
Multiple studies have found data centers increase costs for ordinary ratepayers as they drive skyrocketing demand without corresponding growth in supply. Moreover, these high intensity energy users require expensive infrastructure upgrades that ordinary ratepayers are paying for. Without taking steps to mitigate these cost shifts, rates are estimated to go up 8%. Microsoft, Meta, and Anthropic have stated they will pay for the cost of interconnection to their data centers, and this bill puts these commitments into law.
ARGUMENTS IN OPPOSITION: A coalition of technology, manufacturing, and business associations oppose this bill, arguing that the bill is unnecessary, may negatively impact economic development and decarbonization goals, and would conflict with the CPUC’s ongoing rulemaking regarding PG&E’s Rule 30 application. In opposition, the California Chamber of Commerce states:
California is competing with other states to attract advanced manufacturing, data centers, and other electricity-intensive industries that support economic growth and technological innovation. Policies that impose unusually burdensome infrastructure requirements while also limiting operational control over privately financed energy assets risk discouraging the development of these facilities in California. Grid flexibility and reliability are important goals, but they should be pursued through voluntary programs and market incentives rather than mandates that deter new investment in the state’s electricity system. For these reasons, the California Chamber of Commerce respectfully urges the Legislature to reject SB 886.
-- END --
Discussed in Hearing
Senate Floor
Assembly Floor
Senate Standing Committee on Housing
Assembly Standing Committee on Utilities and Energy
Senate Floor
Senate Standing Committee on Energy, Utilities and Communications
Bill Author
Bill Co-Author(s):