SB 963: California Coastal Act of 1976: coastal development permits: appeal: de novo review.
- Session Year: 2025-2026
- House: Senate
- Latest Version Date: 2026-07-16
Current Status:
Passed
(2026-07-16: Chaptered by Secretary of State. Chapter 103, Statutes of 2026.)
Introduced
In Committee
Awaiting First Chamber Vote
Passed First Chamber
In Committee
Awaiting Second Chamber Vote
Passed Second Chamber
Enacted
Existing law establishes in the Natural Resources Agency the California Coastal Commission. Existing law requires the commission to have the primary responsibility for the implementation of the California Coastal Act of 1976 and designates it as the state coastal zone planning and management agency, as provided. Existing law, among other things, requires anyone wishing to perform or undertake any development in the coastal zone, in addition to obtaining any other permit required by law from any local government or from any state, regional, or local agency, to obtain a coastal development permit from the commission or a local government, as provided. Existing law authorizes an appeal to the commission for any action taken by a local government on coastal development permit applications, requires the commission to hear the appeal, and establishes specified appeal procedures, as provided. Existing law requires the commission to provide for a de novo public hearing on an application for a coastal development permit and an appeal brought pursuant to the act, as provided.
This bill would require an appeal of an action by a local government on a coastal development permit application to be considered properly submitted if the appealing party or parties submit to the executive director a completed, signed copy of the appeal form provided by the commission within the applicable timeline, as provided. The bill would require, for purposes of an appeal of an action on a coastal development permit application by a local government or a port governing body, the commission to provide for de novo review and a public hearing on the coastal development permit application, as provided, if the commission determines that a substantial issue exists with respect to the grounds on which the appeal has been filed.
Existing law establishes in the Natural Resources Agency the California Coastal Commission. Existing law requires the commission to have the primary responsibility for the implementation of the California Coastal Act of 1976 and designates it as the state coastal zone planning and management agency, as provided. Existing law, among other things, requires anyone wishing to perform or undertake any development in the coastal zone, in addition to obtaining any other permit required by law from any local government or from any state, regional, or local agency, to obtain a coastal development permit from the commission or a local government, as provided. Existing law authorizes an appeal to the commission for any action taken by a local government on coastal development permit applications, requires the commission to hear the appeal, and establishes specified appeal procedures, as provided. Existing law requires the commission to provide for a de novo public hearing on an application for a coastal development permit and an appeal brought pursuant to the act, as provided.
This bill would require an appeal of an action by a local government on a coastal development permit application to be considered properly submitted if the appealing party or parties submit to the executive director a completed, signed copy of the appeal form provided by the commission within the applicable timeline, as provided. The bill would require, for purposes of an appeal of an action on a coastal development permit application by a local government or a port governing body, the commission to provide for de novo review and a public hearing on the coastal development permit application, as provided, if the commission determines that a substantial issue exists with respect to the grounds on which the appeal has been filed.
Existing law establishes in the Natural Resources Agency the California Coastal Commission. Existing law requires the commission to have the primary responsibility for the implementation of the California Coastal Act of 1976 and designates it as the state coastal zone planning and management agency, as provided. Existing law, among other things, requires anyone wishing to perform or undertake any development in the coastal zone, in addition to obtaining any other permit required by law from any local government or from any state, regional, or local agency, to obtain a coastal development permit from the commission or a local government, as provided. Existing law authorizes an appeal to the commission for any action taken by a local government on coastal development permit applications, requires the commission to hear the appeal, and establishes specified appeal procedures, as provided. Existing law requires the commission to provide for a de novo public hearing on an application for a coastal development permit and an appeal brought pursuant to the act, as provided.
This bill would require an appeal of an action by a local government on a coastal development permit application to be considered properly submitted if the appealing party or parties submit to the executive director a completed, signed copy of the appeal form provided by the commission within the applicable timeline, as provided. The bill would require, for purposes of an appeal of an action on a coastal development permit application by a local government or a port governing body, the commission to provide for de novo review and a public hearing on the coastal development permit application, as provided, if the commission determines that a substantial issue exists with respect to the grounds on which the appeal has been filed.
Existing law establishes the Department of Parks under the control of the Director of Parks and Recreation. Existing law requires the director to, among other things, promote and regulate the use of the state park system in a manner that conserves the scenery, natural and historic resources, and wildlife in the individual units of the system for the enjoyment of future generations. Existing law requires the department, before any park or recreational area developmental plan is made, to prepare a land carrying capacity survey of the proposed park or recreational area.This bill would make nonsubstantive changes to the provisions regarding developmental plans.Existing law establishes the Department of Parks under the control of the Director of Parks and Recreation. Existing law requires the director to, among other things, promote and regulate the use of the state park system in a manner that conserves the scenery, natural and historic resources, and wildlife in the individual units of the system for the enjoyment of future generations. Existing law requires the department, before any park or recreational area developmental plan is made, to prepare a land carrying capacity survey of the proposed park or recreational area.
This bill would make nonsubstantive changes to the provisions regarding developmental plans.
(a)An appeal of an action by a local government on a coastal development permit application pursuant to Sections 30602 and 30603 shall be considered properly submitted if the appealing party or parties submit to the executive director a completed, signed copy of the appeal form provided by the commission within the applicable timeline established in commission regulations. The commission shall provide hard copies and digital copies of the appeal form upon request, and the form shall also be available on the commissions internet website.
(b)The appealing party or parties shall provide in writing the specific grounds for the appeal. The grounds for appeal shall be stated clearly in the appeal form. In describing the grounds for the appeal, the appealing party or parties shall identify the specific features of the proposed development and how they do not conform to the standards set forth in the certified local coastal program and the public access policies set forth in this division. Evidence supporting the grounds for appeal may be included as an attachment to the appeal form. Any grounds for appeal not based on the provisions of the certified local coastal program or the public access provisions of this division shall not be considered valid.
(c)The executive director may reject an appeal that is submitted in a form that is not consistent with the requirements of this section.
SEC. 2.Section 30629 is added to the Public Resources Code, to read:30629.(a)For purposes of an appeal of an action on a coastal development permit application by a local government or a port governing body, if the commission determines that a substantial issue exists with respect to the grounds on which the appeal has been filed, after the substantial issue hearing the commission shall provide for de novo review and a public hearing on the coastal development permit application that are consistent with the deadlines and procedures of this section.
(b)(1)Within 30 calendar days after the commission determines that a substantial issue exists, the executive director shall provide the permit applicant with a complete description of the information that is needed for the commission to complete a de novo review and hold a public hearing on the coastal development permit application.
(2)When the applicant submits information needed pursuant to paragraph (1), the executive director shall review the submitted information and, within 30 calendar days, shall either notify the applicant in writing that the submittal is complete or, if necessary, provide a complete description of any remaining information needed. Any information subsequently submitted by the applicant to the commission shall be processed in the same manner as the initial submittal.
(3)Once the executive director has received a complete submittal, the commission shall hold a de novo public hearing and act on the coastal development permit application within 180 calendar days.
(4)The time limits established in paragraph (3) may be extended once upon mutual written agreement of the project applicant and the executive director for a period not to exceed 90 calendar days from the date of the extension.
(c)Nothing in this section prohibits the commission from conducting a de novo review and public hearing on the same day that it determines that a substantial issue exists, if the executive director determines that the commission has the information necessary to do so.
(a)An appeal of an action by a local government on a coastal development permit application pursuant to Sections 30602 and 30603 shall be considered properly submitted if the appealing party or parties submit to the executive director a completed, signed copy of the appeal form provided by the commission within the applicable timeline established in commission regulations. The commission shall provide hard copies and digital copies of the appeal form upon request, and the form shall also be available on the commissions internet website.
(b)The appealing party or parties shall provide in writing the specific grounds for the appeal. The grounds for appeal shall be stated clearly in the appeal form. In describing the grounds for the appeal, the appealing party or parties shall identify the specific features of the proposed development and how they do not conform to the standards set forth in the certified local coastal program and the public access policies set forth in this division. Evidence supporting the grounds for appeal may be included as an attachment to the appeal form. Any grounds for appeal not based on the provisions of the certified local coastal program or the public access provisions of this division shall not be considered valid.
(c)The executive director may reject an appeal that is submitted in a form that is not consistent with the requirements of this section.
SEC. 2.Section 30629 is added to the Public Resources Code, to read:30629.(a)For purposes of an appeal of an action on a coastal development permit application by a local government or a port governing body, if the commission determines that a substantial issue exists with respect to the grounds on which the appeal has been filed, after the substantial issue hearing the commission shall provide for de novo review and a public hearing on the coastal development permit application that are consistent with the deadlines and procedures of this section.
(b)(1)Within 30 calendar days after the commission determines that a substantial issue exists, the executive director shall provide the permit applicant with a complete description of the information that is needed for the commission to complete a de novo review and hold a public hearing on the coastal development permit application.
(2)When the applicant submits information needed pursuant to paragraph (1), the executive director shall review the submitted information and, within 30 calendar days, shall either notify the applicant in writing that the submittal is complete or, if necessary, provide a complete description of any remaining information needed. Any information subsequently submitted by the applicant to the commission shall be processed in the same manner as the initial submittal.
(3)Once the executive director has received a complete submittal, the commission shall hold a de novo public hearing and act on the coastal development permit application within 180 calendar days.
(4)The time limits established in paragraph (3) may be extended once upon mutual written agreement of the project applicant and the executive director for a period not to exceed 90 calendar days from the date of the extension.
(c)Nothing in this section prohibits the commission from conducting a de novo review and public hearing on the same day that it determines that a substantial issue exists, if the executive director determines that the commission has the information necessary to do so.
(a)An appeal of an action by a local government on a coastal development permit application pursuant to Sections 30602 and 30603 shall be considered properly submitted if the appealing party or parties submit to the executive director a completed, signed copy of the appeal form provided by the commission within the applicable timeline established in commission regulations. The commission shall provide hard copies and digital copies of the appeal form upon request, and the form shall also be available on the commissions internet website.
(b)The appealing party or parties shall provide in writing the specific grounds for the appeal. The grounds for appeal shall be stated clearly in the appeal form. In describing the grounds for the appeal, the appealing party or parties shall identify the specific features of the proposed development and how they do not conform to the standards set forth in the certified local coastal program and the public access policies set forth in this division. Evidence supporting the grounds for appeal may be included as an attachment to the appeal form. Any grounds for appeal not based on the provisions of the certified local coastal program or the public access provisions of this division shall not be considered valid.
(c)The executive director may reject an appeal that is submitted in a form that is not consistent with the requirements of this section.
SEC. 2.Section 30629 is added to the Public Resources Code, to read:30629.(a)For purposes of an appeal of an action on a coastal development permit application by a local government or a port governing body, if the commission determines that a substantial issue exists with respect to the grounds on which the appeal has been filed, after the substantial issue hearing the commission shall provide for de novo review and a public hearing on the coastal development permit application that are consistent with the deadlines and procedures of this section.
(b)(1)Within 30 calendar days after the commission determines that a substantial issue exists, the executive director shall provide the permit applicant with a complete description of the information that is needed for the commission to complete a de novo review and hold a public hearing on the coastal development permit application.
(2)When the applicant submits information needed pursuant to paragraph (1), the executive director shall review the submitted information and, within 30 calendar days, shall either notify the applicant in writing that the submittal is complete or, if necessary, provide a complete description of any remaining information needed. Any information subsequently submitted by the applicant to the commission shall be processed in the same manner as the initial submittal.
(3)Once the executive director has received a complete submittal, the commission shall hold a de novo public hearing and act on the coastal development permit application within 180 calendar days.
(4)The time limits established in paragraph (3) may be extended once upon mutual written agreement of the project applicant and the executive director for a period not to exceed 90 calendar days from the date of the extension.
(c)Nothing in this section prohibits the commission from conducting a de novo review and public hearing on the same day that it determines that a substantial issue exists, if the executive director determines that the commission has the information necessary to do so.
SECTION 1.Section 5019.5 of the Public Resources Code is amended to read:5019.5.Before any park or recreational area developmental plan is made, the department shall prepare a land carrying capacity survey of the proposed park or recreational area that includes such factors as soil, moisture, and natural cover.Before any park or recreational area developmental plan is made, the department shall cause to be made prepare a land carrying capacity survey of the proposed park or recreational area, including in such survey area that includes such factors as soil, moisture, and natural cover.
|
Date
|
Status
|
|---|---|
| Jul 16, 2026 | Chaptered by Secretary of State. Chapter 103, Statutes of 2026. |
| Jul 16, 2026 | Approved by the Governor. |
| Jul 15, 2026 | Enrolled and presented to the Governor at 11 a.m. |
| Jul 2, 2026 | In Senate. Ordered to engrossing and enrolling. |
| Jul 2, 2026 | Read third time. Passed. (Ayes 70. Noes 0. Page 5985.) Ordered to the Senate. |
| Jul 2, 2026 | Read third time. Passed. Ordered to the Senate. |
| Jun 25, 2026 | Read second time. Ordered to consent calendar. |
| Jun 24, 2026 | From committee: Do pass. Ordered to consent calendar. (Ayes 15. Noes 0.) (June 24). |
| Jun 9, 2026 | From committee: Do pass and re-refer to Com. on APPR. with recommendation: To consent calendar. (Ayes 13. Noes 0.) (June 8). Re-referred to Com. on APPR. |
| May 18, 2026 | Referred to Com. on NAT. RES. |
| Apr 30, 2026 | In Assembly. Read first time. Held at Desk. |
| Apr 30, 2026 | Read third time. Passed. (Ayes 36. Noes 0. Page 4114.) Ordered to the Assembly. |
| Apr 30, 2026 | Read third time. Passed. (Ayes 36. Noes 0.) Ordered to the Assembly. |
| Apr 28, 2026 | Read second time. Ordered to consent calendar. |
| Apr 27, 2026 | From committee: Be ordered to second reading pursuant to Senate Rule 28.8 and ordered to consent calendar. |
| Apr 17, 2026 | Set for hearing April 27. |
| Apr 14, 2026 | From committee: Do pass and re-refer to Com. on APPR. with recommendation: To consent calendar. (Ayes 7. Noes 0. Page 3869.) (April 14). Re-referred to Com. on APPR. |
| Apr 14, 2026 | From committee: Do pass and re-refer to Com. on APPR. with recommendation: To consent calendar. (Ayes 7. Noes 0.) (April 14). Re-referred to Com. on APPR. |
| Apr 2, 2026 | Set for hearing April 14. |
| Mar 27, 2026 | April 7 set for first hearing canceled at the request of author. |
| Mar 24, 2026 | Set for hearing April 7. |
| Mar 18, 2026 | Re-referred to Com. on N.R. & W. |
| Mar 9, 2026 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on RLS. |
| Feb 11, 2026 | Referred to Com. on RLS. |
| Feb 4, 2026 | From printer. May be acted upon on or after March 6. |
| Feb 3, 2026 | Introduced. Read first time. To Com. on RLS. for assignment. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Jul 2, 2026 | SB 963 Laird Consent Calendar Second Day Regular Session | Assembly Floor |
Passed |
|
| Jun 24, 2026 | Do pass. To Consent Calendar. | Assembly Standing Committee on Appropriations |
Passed |
|
| Jun 8, 2026 | Do pass and be re-referred to the Committee on [Appropriations] with recommendation: To Consent Calendar | Assembly Standing Committee on Natural Resources |
Passed |
|
| Apr 30, 2026 | Consent Calendar 2nd SB963 Laird | Senate Floor |
Passed |
|
| Apr 14, 2026 | Do pass, but first be re-referred to the Committee on [Appropriations] with the recommendation: To Consent Calendar | Senate Standing Committee on Natural Resources and Water |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| Azul | ** Support | |
| Bay Area Council | ** Support | |
| California Apartment Association | ** Support | |
| California Business Properties Association | ** Support | |
| California Coastal Commission | ** Support | |
| California Coastal Protection Network | ** Support | |
| Environmental Action Committee of West Marin | ** Support | |
| Housing California | ** Support | |
| Los Angeles County | ** Support | |
| MidPen Housing Corporation | ** Support | |
| NAIOP SoCal | ** Support | |
| Pacific Legal Foundation | ** Support | |
| Save Our Shores | ** Support | |
| Surfrider Foundation | ** Support |
Date of Hearing: June 24, 2026
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Buffy Wicks, Chair
SBPCA Bill Id:SB 963
Author:(Laird) – As Amended Ver:March 9, 2026
Policy Committee: | Natural Resources | Vote: | 13 - 0 |
|
| ||
|
|
Urgency: No State Mandated Local Program: No Reimbursable: No
SUMMARY:
This bill sets certain time limits for the California Coastal Commission (Commission) to identify and review necessary data, newly (“de novo”) review, and hold a public hearing when a coastal development permit (CDP) issued by a local jurisdiction is appealed to the Commission and the Commission determines a substantial issue exists.
Specifically, this bill, among other things:
- Requires an appeal of an action by a local government on a CDP application pursuant to existing law be considered properly submitted if the appealing party or parties submit to the Commission’s executive director a completed, signed copy of the appeal form provided by the Commission within the applicable timeline established in Commission regulations, as specified.
- Requires the appealing party or parties to provide in writing the specific grounds for the appeal and requires the appealing party or parties, in describing the grounds for the appeal, to identify the specific features of the proposed development and how those features do not conform to the standards set forth in the certified local coastal program (LCP) and the public access policies in the Coastal Act, as specified.
- Requires the Commission, if it determines that a substantial issue exists with respect to the grounds on which the appeal has been filed, after the substantial issue hearing, to provide for de novo review and a public hearing on the CDP application consistent with relevant deadlines and procedures.
- Requires the executive director, within 30 calendar days after the Commission determines that a substantial issue exists, to provide the permit applicant with a complete description of the information needed for the Commission to complete a de novo review and hold a public hearing on the CDP application.
- Requires the executive director, when the applicant submits the requisite information, to review the submitted information and, within 30 calendar days, either notify the applicant in writing that the submittal is complete or, if necessary, provide a complete description of any remaining information needed.
- Requires the Commission, once the executive director has received a complete submittal, to hold a de novo public hearing and act on the CDP application within 180 calendar days and authorizes that time limit to be extended, as specified.
FISCAL EFFECT:
The Commission anticipates any costs associated with processing de novo appeals under the deadlines set forth in the bill to be minor and absorbable.
COMMENTS:
1) Purpose. According to the author:
If a local jurisdiction has a certified [LCP], they are responsible for issuing a CDP for a new development project in a coastal zone. In some cases, developers and other stakeholders may appeal the local agency’s decision on a CDP to the Commission. While the purpose of the appeals process is to ensure that projects in the most sensitive areas of the coast are in compliance with the local coastal program and the Coastal Act before they move forward, appeals can sometimes add delays in the permitting process, creating uncertainty for developers who are working to meet housing and infrastructure needs in coastal communities. SB 963 will reduce delays and uncertainty for developers while upholding our commitment to coastal protection and access.
2) Background. The Commission administers the Coastal Act and regulates proposed development along the coast and in nearby areas in the coastal zone. Generally, any development activity in the coastal zone requires a CDP from the Commission or local government with a certified LCP. In jurisdictions with certified LCPs, local governments issue CDPs with detailed planning and design standards.
Additionally, under specified circumstances, the applicant for the CDP or any “aggrieved person” may directly appeal to the Commission a permitting decision made by a local government with an approved LCP. In reviewing the permit, the Commission generally must defer to standards outlined in the LCP. For projects for which the Commission finds no substantial issue, the Commission rejects the appeal and the local approval stands. For those appeals that raise a substantial issue, the Commission considers the project in its entirety. In this “de novo” phase of the review, the Commission may either approve or deny the project with additional conditions necessary for compliance.
It takes the Commission, on average, two to three months to decide on an appeal that does not raise a substantial issue and six to eight months to decide on an appeal that raises a substantial issue. According to the Commission, it does its best to process appeals as quickly as possible, generally in the order they are received. Informational needs, complexity of issues, extent of public interest, applicant responsiveness, and staff workload all affect the timing of the appeal process. According to the author, the lack of statutory timelines governing de novo hearings increases costs and complicates project financing. The author argues this bill provides more certainty to anyone navigating the Commission appeals process by establishing clear timelines and ensuring that appealed projects move through the process in a standardized and timely manner.
Analysis Prepared by: Nikita Koraddi / APPR. / (916) 319-2081
ASSEMBLY COMMITTEE ON NATURAL RESOURCES
Isaac G. Bryan, Chair
SBPCA Bill Id:SB 963
Author:(Laird) – As Amended Ver:March 9, 2026
SENATE VOTE: 36-0
SUBJECT: California Coastal Act of 1976: coastal development permits: appeal: de novo review
SUMMARY: Requires an appeal of an action by a local government on a coastal development permit (CDP) application to be considered properly submitted if the appealing party or parties submit to the executive director of the California Coastal Commission (Commission) a completed, signed copy of the appeal form provided by the Commission within the applicable timeline, as provided. Requires the Commission to provide for de novo review and a public hearing on the CDP if the Commission determines that a substantial issue exists with respect to the grounds on which the appeal has been filed.
EXISTING LAW:
- Requires any person wishing to perform or undertake any development in the coastal zone, in addition to obtaining any other permit required by law from any local government or from any state, regional, or local agency, to obtain a CDP. (Public Resources Code (PRC) 30600)
- Requires each local government lying, in whole or in part, within the coastal zone to prepare a local coastal plan (LCP) for that portion of the coastal zone within its jurisdiction. (PRC 30500)
- Authorizes, prior to certification of its LCP, any action taken by a local government on a CDP application to be appealed by the executive director of the Commission, any person, including the applicant, or any two members of the Commission to the Commission. Requires the action to become final at the close of business on the 20th working day from the date of receipt of the requisite notice required, unless an appeal is submitted within that time. Regardless of whether an appeal is submitted, the local government’s action shall become final if an appeal fee is imposed and is not deposited with the Commission within the time prescribed. (PRC 30602)
- Authorizes, after certification of its LCP, an action taken by a local government on a CDP application to be appealed to the Commission for only the following types of developments:
- Developments approved by the local government between the sea and the first public road paralleling the sea or within 300 feet of the inland extent of any beach or of the mean high tideline of the sea where there is no beach, whichever is the greater distance;
- Developments approved by the local government not included within (a) that are located on tidelands, submerged lands, public trust lands, within 100 feet of any wetland, estuary, or stream, or within 300 feet of the top of the seaward face of any coastal bluff;
- Developments approved by the local government not included within paragraph (a) or (b) that are located in a sensitive coastal resource area;
- Any development approved by a coastal county that is not designated as the principal permitted use under the zoning ordinance or approved zoning district map; or,
- Any development which constitutes a major public works project or a major energy facility. (PRC 30603)
THIS BILL:
- Requires an appeal of an action by a local government on a CDP application pursuant to PRC 30602 and 30603 to be considered properly submitted if the appealing party or parties submit to the executive director a completed, signed copy of the appeal form provided by the Commission within the applicable timeline established in Commission regulations.
- Requires the Commission to provide hard copies and digital copies of the appeal form upon request, and requires the form to also be available on the Commission’s internet website.
- Requires the appealing party or parties to provide in writing the specific grounds for the appeal. In describing the grounds for the appeal, the appealing party or parties are required to identify the specific features of the proposed development and how they do not conform to the standards set forth in the certified LCP and the public access policies set forth in the Coastal Act
- Authorizes the executive director to reject an appeal that is submitted in a form that is not consistent with the specified requirements.
- Requires, if the Commission determines that a substantial issue exists with respect to the grounds on which the appeal has been filed, after the substantial issue hearing the Commission to provide for de novo review and a public hearing on the CDP application that are consistent with the relevant deadlines and procedures.
- Requires, within 30 calendar days after the Commission determines that a substantial issue exists, the executive director to provide the permit applicant with a complete description of the information that is needed for the Commission to complete a de novo review and hold a public hearing on the CDP application.
- Requires, when the applicant submits the requisite information, the executive director to review the submitted information and, within 30 calendar days, either notify the applicant in writing that the submittal is complete or, if necessary, provide a complete description of any remaining information needed.
- Requires, once the executive director has received a complete submittal, the Commission to hold a de novo public hearing and act on the CDP application within 180 calendar days. Authorizes that time limit to be extended.
- Provides that nothing in this bill prohibits the Commission from conducting a de novo review and public hearing on the same day that it determines that a substantial issue exists, if the executive director determines that the Commission has the information necessary to do so.
FISCAL EFFECT: The Senate Appropriations Committee determined this bill has negligible state costs pursuant to Senate Rule 28.8.
COMMENTS:
- Coastal Act jurisdiction. The Commission administers the Coastal Act and regulates proposed development along the coast and in nearby areas in the coastal zone. Generally, any development activity in the coastal zone requires a CDP from the Commission or local government with a certified LCP. In the jurisdictions with certified LCPs, local governments issue CDPs with detailed planning and design standards. About 88% of the coastal zone is governed by a certified LCP. There are 14 jurisdictions (out of 15 counties and 61 cities) without LCPs – also known as “uncertified” jurisdictions – where the Commission is still the permitting authority for CDPs. Additionally, permitting decisions made by a local government with an approved LCP can be appealed directly to the Commission under specified circumstances. In reviewing the permit, the Commission generally must defer to those standards outlined in the LCP. Jurisdictions with LCPs are empowered to control what to permit and how to permit coastal development.
- CDP appeals. The Coastal Act appeal process is intended to ensure that statewide interests in coastal resources are protected and appropriately balanced with competing local interests. The Coastal Act allows an action taken by a local government on a CDP application to be appealed to the Commission, on the grounds the action is inconsistent with the LCP or public access laws, on certain types of development, including those in designated areas between the sea and the first public road; developments located on tidelands, submerged lands, public trust lands, within 100 feet of any wetland, estuary, or stream, or within 300 feet of the top of the seaward face of any coastal bluff; developments located in a sensitive coastal resource area; and, major public works project or a major energy facility.
According to the California Coastal Commission Key Metrics Report 2025[1], some, but not all, CDPs approved by local governments are appealable to the Commission and only a small fraction of appealable projects actually gets appealed.
For projects found to raise no substantial issue, the appeal is rejected, and the local approval stands. For those appeals that raise a substantial issue, the Commission considers the project in its entirety. In this “de novo” phase of the review, the agency can either approve or deny the project with additional conditions necessary for compliance.
Any applicant or person who participates in the local permitting process for a project may file an appeal. The Commission’s regulations (Title 14 California Code of Regulations 13114) require an applicant to first exhaust all local appeals within the jurisdiction where the permit was issued before the Commission can consider a de novo appeal without being bound by the prior local decision.
The Commission’s consideration of appeals is a two-step process. The first step is determining whether the appeal raises a substantial issue that the Commission, in the exercise of its discretion, finds to be significant enough to warrant the Commission taking jurisdiction over the CDP application. The Commission is required to begin its hearing on an appeal, addressing at least the substantial issue question, within 49-working days of the filing of the appeal, unless the applicant has waived that requirement, in which case there is no deadline.
The average time for appeals that do not raise a substantial issue is two to three months. For appeals that raise a substantial issue, it takes approximately six to eight months on average to reach a final decision. According to the Commission, it does its best to process appeals as quickly as possible, generally in the order they are received. Informational needs, complexity of issues, extent of public interest, applicant responsiveness, and staff workload all affect the timing of the appeal process.
Of the 1,290 locally issued CDPs in 2025, ~3.5% were appealed to the Commission. Of those 44 appeals, 29 were dismissed for raising no substantial issue, and the remaining 15 were approved with conditions.
- This bill. According to the author, there is currently no statutory timeline for how quickly the Commission must hold a de novo hearing on an appeal following its finding that the appeal raises a substantial issue. For applicants, this lack of certainty increases costs and complicates project financing.
To create clear guidelines for appeal submissions, SB 963 requires an appeal of an action by a local government on a CDP application to be considered properly submitted if the appealing party or parties submit to the executive director a completed, signed copy of the appeal form provided by the Commission within the applicable timeline. The bill further requires, for purposes of an appeal of an action on a CDP application by a local government or a port governing body, the Commission to provide for de novo review and a public hearing on the CDP if the Commission determines that a substantial issue exists with respect to the grounds on which the appeal has been filed.
- Author’s statement:
SB 963 will provide more certainty to anyone navigating the Commission appeals process by establishing clear timelines and ensuring that appealed projects move through the process in a standardized and timely manner. If a local jurisdiction has a certified local coastal program, they are responsible for issuing a CDP for a new development project in a coastal zone. In some cases, developers and other stakeholders may appeal the local agency’s decision on a CDP to the Commission. While the purpose of the appeals process is to ensure that projects in the most sensitive areas of the coast are in compliance with the local coastal program and the Coastal Act before they move forward, appeals can sometimes add delays in the permitting process, creating uncertainty for developers who are working to meet housing and infrastructure needs in coastal communities. SB 963 will reduce delays and uncertainty for developers while upholding our commitment to coastal protection and access.
- Related legislation. SB 1092 (Blakespear), Chapter, Statutes of 2023, requires, on or before December 31, 2025, the Commission to provide a report to the Legislature that provides the specified information regarding appeals of local government CDP actions to the Commission that were filed pursuant to PRC 30602 or 30603 between January 1, 2021, and December 31, 2024.
REGISTERED SUPPORT / OPPOSITION:
Support
Azul
Bay Area Council
California Apartment Association
California Business Properties Association
California Coastal Commission
California Coastal Protection Network
Environmental Action Committee of West Marin
Housing California
Los Angeles County
Midpen Housing Corporation
Naiop Socal
Pacific Legal Foundation
Save Our Shores
Surfrider Foundation
Opposition
None on file
Analysis Prepared by: Paige Brokaw / NAT. RES. /
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-4171 | SB 963 |
CONSENT
Bill No: SB 963
Author: Laird (D)
Amended: 3/9/26
Vote: 21
SENATE NATURAL RES. & WATER COMMITTEE: 7-0, 4/14/26
AYES: Becker, Seyarto, Allen, Cabaldon, Cortese, Grove, Stern
SENATE APPROPRIATIONS COMMITTEE: Senate Rule 28.8
SUBJECT: California Coastal Act of 1976: coastal development permits: appeal: de novo review
SOURCE: Author
DIGEST:
This bill sets certain time limits for the California Coastal Commission (commission) to identify and review necessary data and hold a de novo and public hearing when a coastal development permit issued by a local jurisdiction is appealed to the commission and the commission determines a substantial issue exists, as provided.
ANALYSIS:
Existing law:
- Establishes the commission in the California Natural Resources Agency in the California Coastal Act of 1976 (Coastal Act) (Public Resources Code (PRC) §§30000 et seq., 30004).
- Includes legislative findings and declarations that:
- The coastal zone is a distinct and valuable natural resource of vital and enduring interest to all the people, the permanent protection of the state’s natural and scenic resources is a paramount concern to present and future residents, and existing uses and future developments that are carefully planned and developed consistent with the Coastal Act are essential to the economic and social well-of the people of the state (PRC §30001).
- The basic goals of the state for the coastal zone include to:
- Protect, maintain, and, where feasible, enhance and restore the overall quality of the coastal zone environment and its natural and artificial resources,
- Ensure orderly, balanced utilization and conservation of coastal zone resources taking into account the social and economic needs of the people of the state, and
- Maximize public access to and along the coast and maximize public recreational opportunities in the coastal zone consistent with sound resources conservation principles and constitutionally protected rights of private property owners, among other things (PRC §30001.5).
- Provides for the planning and regulation of development within the coastal zone, as defined.
- A person planning to perform or undertake any development in the coastal zone is required to obtain a coastal development permit (CDP) from the commission or local government enforcing a certified local coastal program (LCP) (PRC §30600).
- Development means, among other things, the placement or erection of any solid material or structure on land or in water. Structure means building, road, pipe, flume, conduit, and electrical power transmission and distribution lines, among other things (PRC §30106).
- The coastal zone means the coastal land and waters of California, and includes the lands that extend inland generally 1,000 yards from the mean high tide line, as specified, with various exceptions including the San Francisco Bay (PRC §30103).
- A person planning to perform or undertake any development in the coastal zone is required to obtain a coastal development permit (CDP) from the commission or local government enforcing a certified local coastal program (LCP) (PRC §30600).
- Requires a local government in the coastal zone to prepare an LCP. Requires the precise content of the LCP to be determined by the local government in full consultation with the commission and with full public participation. (PRC §30500). Provides for LCPs to be amended by the local government, but the amendment does not take effect until certified by the commission (PRC §30514).
- Prohibits the commission from exercising its review authority over any new development within the area to which the certified LCP, or any portion thereof, applies (PRC §30519).
- Authorizes an appeal to the commission of only the following developments approved by a local government with a certified LCP:
- Development between the sea and the first public road paralleling the sea or within 300 feet of the beach or mean high tideline, as provided.
- Development on certain tidelands, submerged lands, or public trust lands within 100 feet of any wetland, estuary or stream, or within 300 feet of the top of the seaward face of any coastal bluff.
- Developments in sensitive coastal areas other than those described in a) and b), as provided.
- Development approved by a coastal county that is not designated as a principal permitted use, as provided.
- Development that is a major public works or a major energy facility (PRC §30603).
- Requires that the standard of review used by the commission for the appeal of certain local CDPs is the applicable certified LCP or public access policies, as provided (PRC §30603).
This bill:
- Provides that an appeal of a local jurisdiction’s CDP is properly submitted if the appealing party or parties submit it a signed completed form to the commission’s executive director (executive director) within the established regulatory timeline. Requires the commission to provide the form to the public, as specified.
- Requires the appealing party or parties to provide in writing the specific grounds for the appeal. Requires the identification of specific features of the proposed development and how they do not conform to the standards in the certified LCP and Coastal Act public access policies, as specified.
- Authorizes the executive director to reject an appeal that is not properly submitted, as specified.
- In the event that a substantial issue exists with respect to the grounds on which an appeal has been filed and after the substantial issue hearing, requires the commission to provide for de novo review and a public hearing on the CDP application that are consistent with the following:
- Requires the executive director within 30 calendar days after the commission determines that a substantial issue exists to provide the permit applicant with a complete description of the information needed for the commission to complete a de novo review and hold a public hearing on the CDP application.
- Requires the executive director to review an applicant submittal pursuant to (a) above and within 30 days notify the applicant that the submittal is complete or provide a complete description of any remaining information needed. Requires subsequently provided information to be processed in the same manner.
- Requires the commission to hold a de novo public hearing and act on the CDP application within 180 calendar days once the executive director has received a complete submittal.
- Authorizes the time limits in c) above to be extended once upon mutual written agreement for a period not to exceed 90 calendar days, as specified.
- Authorizes the commission to conduct a de novo review and public hearing on the same day it determines a substantial issue exists if the executive director determines the commission has the information necessary to do so.
Background
The commission is an independent, quasi-judicial state agency, and its mission statement states that it “is committed to protecting and enhancing California’s coast and ocean for present and future generations.” The commission does so “through careful planning and regulation of environmentally sustainable development, rigorous use of science, strong public participation, education, and effective intergovernmental coordination.”
Development activities in the coastal zone generally require CDP issued by the commission or by a local government with an LCP certified by the commission. Coastal Act policies are the standards the commission uses to determine the permissibility of proposed developments subject to its jurisdiction.
In certain limited circumstances, the decision of a local government to issue a CDP can be appealed to the commission. There are 10 working days after the commission has received notice of the local jurisdiction issued CDP for that CDP to be appealed. The commission then has 49 days to hold a public hearing on the appeal. If the commission, using the certified LCP or its public access policies to evaluate the CDP, determines there is a “substantial issue” with conformity to the certified LCP or public access policies on appeal, the commission will resume authority over permitting and hold a “de novo” appeal hearing for the project. The commission may then approve or deny the project.
Beyond the time periods already cited, the appeals process to the commission is not currently subject to statutory requirements. Appeals are outside of the Permit Streamlining Act.
[NOTE: For additional information regarding this bill, please see the Senate Natural Resources and Water Committee’s analysis.]
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: No
SUPPORT: (Verified 4/27/26)
Azul
Bay Area Council
California Apartment Association
California Coastal Protection Network
Environmental Action Committee of West Marin
Pacific Legal Foundation
Save Our Shores
Surfrider Foundation
OPPOSITION: (Verified 4/27/26)
None received
ARGUMENTS IN SUPPORT: According to the author, “Senate Bill 963 will provide more certainty to anyone navigating the Coastal Commission appeals process by establishing clear timelines and ensuring that appealed projects move through the process in a standardized and timely manner. If a local jurisdiction has a certified local coastal program, they are responsible for issuing a Coastal Development Permit (CDP) for a new development project in a coastal zone. In some cases, developers and other stakeholders may appeal the local agency’s decision on a CDP to the Coastal Commission. While the purpose of the appeals process is to ensure that projects in the most sensitive areas of the coast are in compliance with the local coastal program and the Coastal Act before they move forward, appeals can sometimes add delays in the permitting process, creating uncertainty for developers who are working to meet housing and infrastructure needs in coastal communities. Senate Bill 963 will reduce delays and uncertainty for developers while upholding our commitment to coastal protection and access.”
Prepared by: Katharine Moore / N.R. & W. / (916) 651-4116
4/28/26 16:33:33
**** END ****
SENATE COMMITTEE ON NATURAL RESOURCES AND WATER
Senator Josh Becker, Chair
2025 - 2026 Regular
Bill No: SB Hearing Date: April 14, 2026
Author: | |||
Version: | Amended | ||
Urgency: | Fiscal: | ||
Consultant: | |||
Subject: California Coastal Act of 1976: coastal development permits: appeal: de novo review
SUMMARY
This bill would set certain time limits for the California Coastal Commission (commission) to identify and review necessary data and hold a de novo and public hearing when a coastal development permit issued by a local jurisdiction is appealed to the commission and the commission determines a substantial issue exists, as provided.
BACKGROUND AND EXISTING LAW
The California Coastal Commission (commission)
The commission was established by voter initiative, Proposition 20, in 1972. The Legislature later made the commission permanent through the adoption of the California Coastal Act of 1976 (Coastal Act) (Public Resources Code (PRC) §§30000 et seq.). The commission plans for and regulates the use of land and water in the coastal zone (which excludes the San Francisco Bay).
The commission is an independent, quasi-judicial state agency, and its mission statement states that it “is committed to protecting and enhancing California’s coast and ocean for present and future generations.” The commission does so “through careful planning and regulation of environmentally sustainable development, rigorous use of science, strong public participation, education, and effective intergovernmental coordination.”
Development activities in the coastal zone generally require a coastal development permit (CDP) issued by the commission or by a local government with a local coastal program (LCP) certified by the commission. Coastal Act policies are the standards the commission uses to determine the permissibility of proposed developments subject to its jurisdiction.
CDP appeals
In certain limited circumstances, the decision of a local government to issue a CDP can be appealed to the commission. There are 10 working days after the commission has received notice of the local jurisdiction issued CDP for that CDP to be appealed. The commission then has 49 days to hold a public hearing on the appeal. If the commission, using the certified LCP or its public access policies to evaluate the CDP, determines there is a “substantial issue” with conformity to the certified LCP or public access policies on appeal, the commission will resume authority over permitting and hold a “de novo” appeal hearing for the project. The commission may then approve or deny the project.
For a “de novo” hearing, the commission has the authority to address how the project conforms to all Coastal Act policies, not just the applicable LCP. This may involve requests for additional information from the applicant and other efforts. An applicant may seek a postponement of the “de novo” hearing after the staff recommendation is published.
Data obtained from the commission for 2021 – 2025 indicate that there were 6,710 local jurisdiction CDPs issued, of which about 56% (3,781) were appealable. Of those appealable CDPs, 286 were appealed (about 4.6%). For 2024 – 2025,[1] there were 89 approved appeal applications of which 55 (about 62%) were determined to raise no substantial issue. Of the 34 referred for a “de novo” hearing by the commission, 22 projects were approved with conditions, 5 projects were withdrawn, 1 was denied, and 6 remained pending. The percentage of projects denied or withdrawn under appeal was 0.2% of the total CDPs issued by local jurisdictions.
It is worth noting that some appeals and subsequent “de novo” hearing are not completed within the same calendar year. In its appeals FAQs, the commission states:
The time required to process a Commission appeal depends in part on the complexity and significance of the issues raised. The average time for appeals that do not raise a substantial issue is 2 to 3 months. For appeals that raise a substantial issue, it takes approximately 6-8 months on average to reach a final decision. It may take longer to resolve more complicated appeals. The Commission does its best to process appeals as quickly as possible, generally in the order they are received. Information needs, complexity of issues, extent of public interest, applicant responsiveness, and staff workload all affect the timing of the appeal process.
Beyond the time periods already cited, the appeals process to the commission is not currently subject to statutory requirements. Appeals are outside of the Permit Streamlining Act.
Existing law, pursuant to the Coastal Act:
- Establishes the commission in the California Natural Resources Agency (PRC §30004).
- Includes legislative findings and declarations that:
- The coastal zone is a distinct and valuable natural resource of vital and enduring interest to all the people, the permanent protection of the state’s natural and scenic resources is a paramount concern to present and future residents, and existing uses and future developments that are carefully planned and developed consistent with the Coastal Act are essential to the economic and social well-of the people of the state (PRC §30001).
- The basic goals of the state for the coastal zone include to:
- Protect, maintain, and, where feasible, enhance and restore the overall quality of the coastal zone environment and its natural and artificial resources,
- Ensure orderly, balanced utilization and conservation of coastal zone resources taking into account the social and economic needs of the people of the state, and
- Maximize public access to and along the coast and maximize public recreational opportunities in the coastal zone consistent with sound resources conservation principles and constitutionally protected rights of private property owners, among other things (PRC §30001.5).
- Provides for the planning and regulation of development within the coastal zone, as defined.
- A person planning to perform or undertake any development in the coastal zone is required to obtain a CDP from the Coastal Commission or local government enforcing a certified LCP (PRC §30600).
- Development means, among other things, the placement or erection of any solid material or structure on land or in water. Structure means building, road, pipe, flume, conduit, and electrical power transmission and distribution lines, among other things (PRC §30106).
- The coastal zone means the coastal land and waters of California, and includes the lands that extend inland generally 1,000 yards from the mean high tide line, as specified, with various exceptions including the San Francisco Bay (PRC §30103).
- A person planning to perform or undertake any development in the coastal zone is required to obtain a CDP from the Coastal Commission or local government enforcing a certified LCP (PRC §30600).
- Requires a local government in the coastal zone to prepare a LCP. Requires the precise content of the LCP to be determined by the local government in full consultation with the Coastal Commission and with full public participation. (PRC §30500). Provides for LCPs to be amended by the local government, but the amendment does not take effect until certified by the Coastal Commission (PRC §30514).
- Prohibits the Coastal Commission from exercising its review authority over any new development within the area to which the certified LCP, or any portion thereof, applies (PRC §30519).
- Authorizes an appeal to the Coastal Commission of only the following developments approved by a local government with a certified LCP:
- Development between the sea and the first public road paralleling the sea or within 300 feet of the beach or mean high tideline, as provided.
- Development on certain tidelands, submerged lands, or public trust lands within 100 feet of any wetland, estuary or stream, or within 300 feet of the top of the seaward face of any coastal bluff.
- Developments in sensitive coastal areas other than those described in a) and b), as provided.
- Development approved by a coastal county that is not designated as a principal permitted use, as provided.
- Development that is a major public works or a major energy facility (PRC §30603).
- Requires that the standard of review used by the Coastal Commission for the appeal of certain local CDPs is the applicable certified LCP or public access policies, as provided (PRC §30603).
PROPOSED LAW
This bill would:
- Provide that an appeal of a local jurisdiction’s CDP is properly submitted if the appealing party or parties submit it a signed completed form to the commission’s executive director (executive director) within the established regulatory timeline. Requires the commission to provide the form to the public, as specified.
- Require the appealing party or parties to provide in writing the specific grounds for the appeal. Require the identification of specific features of the proposed development and how they do not conform to the standards in the certified LCP and Coastal Act public access policies, as specified.
- Authorize the executive director to reject an appeal that is not properly submitted, as specified.
- In the event that a substantial issue exists with respect to the grounds on which an appeal has been filed and after the substantial issue hearing, require the commission to provide for de novo review and a public hearing on the CDP application that are consistent with the following:
- Require the executive director within 30 calendar days after the commission determines that a substantial issue exists to provide the permit applicant with a complete description of the information needed for the commission to complete a de novo review and hold a public hearing on the CDP application.
- Require the executive director to review an applicant submittal pursuant to (a) above and within 30 days notify the applicant that the submittal is complete or provide a complete description of any remaining information needed. Require subsequently provided information to be processed in the same manner.
- Require the commission to hold a de novo public hearing and act on the CDP application within 180 calendar days once the executive director has received a complete submittal.
- Authorize the time limits in (c) above to be extended once upon mutual written agreement for a period not to exceed 90 calendar days, as specified.
- Authorizes the commission to conduct a de novo review and public hearing on the same day it determines a substantial issue exists if the executive director determines the commission has the information necessary to do so.
ARGUMENTS IN SUPPORT
According to the author, “Senate Bill 963 will provide more certainty to anyone navigating the Coastal Commission appeals process by establishing clear timelines and ensuring that appealed projects move through the process in a standardized and timely manner. If a local jurisdiction has a certified local coastal program, they are responsible for issuing a Coastal Development Permit (CDP) for a new development project in a coastal zone. In some cases, developers and other stakeholders may appeal the local agency’s decision on a CDP to the Coastal Commission. While the purpose of the appeals process is to ensure that projects in the most sensitive areas of the coast are in compliance with the local coastal program and the Coastal Act before they move forward, appeals can sometimes add delays in the permitting process, creating uncertainty for developers who are working to meet housing and infrastructure needs in coastal communities. Senate Bill 963 will reduce delays and uncertainty for developers while upholding our commitment to coastal protection and access.”
ARGUMENTS IN OPPOSITION
None received
COMMENTS
Providing a clock for the CDP appeals process. The commission has historically been criticized for the length of time the appeals process takes for certain CDPs where the commission determines that a substantial issue exists, despite, as noted above, that very few CDPs issued by local jurisdictions are appealed annually and fewer than half of those are found to have a substantial issue. This proposal, by instituting specific timelines for needed information to be provided and processed, should help to keep the process moving forward to resolution. It is possible that the commission may require additional resources to adhere to the new timelines should this bill become law.
The author may wish to consider, should this bill move forward, if it is possible to provide additional transparency the status of projects in the appeals process, either individually or in aggregate. This might include an online dashboard and could include data such as the number of CDPs being appealed at any given time, the grounds for the appeal, and the amount of time it takes to resolve the CDP, among others.
Recent related legislation
SB 1318 (Allen, 2026) would seek to limit non-owner-occupied short-term rentals in the coastal zone, as provided. (This bill is pending before this Committee.)
SB 1229 (Allen, 2026) would seek to limit the applicability of the CDP waiver for rebuilding a structure destroyed in a disaster to the property owner of record at the time of the disaster, as provided. (This bill is pending before the Senate Appropriations Committee.)
SCR 136 (Laird, 2026) would recognize 50 years of coastal protection and affirm the state’s longstanding commitment to protecting its coastal waters, as specified. (This resolution is pending on the Senate Floor.)
ACR 149 (Hart, 2026) would recognize 50 years of coastal protection and affirm the state’s longstanding commitment to protecting its coastal waters, as specified. (This resolution is pending before the Assembly Natural Resources Committee.)
SB 484 (Laird, Chapter 416, Statutes of 2025) requires the commission to identify coastal zone infill areas in three jurisdictions where the commission retains coastal development permitting authority for a 10 year categorical exclusion from that permitting requirement for residential housing projects comprised entirely of very low, low, and moderate income housing units, as provided.
AB 462 (Lowenthal/Rivas, Chapter 491, Statutes of 2025) requires CDPs for accessory dwelling units to be approved or denied within 60 days, and eliminates the ability to appeal a local jurisdiction’s CDP for an accessory dwelling unit to the commission, among other provisions, as provided.
AB 130 (Budget Committee, Chapter 22, Statutes of 2025), the housing budget trailer bill, exempts multifamily housing projects of four or more units that are exclusively residential from the commission’s appeals jurisdiction in certain circumstances, as provided.
SB 1092 (Blakespear, 2024) would have required the commission to provide a report to the Legislature regarding appeals to the commission of local government decisions on coastal development permit (CDP) applications, as provided. (This bill was held on suspense in the Assembly Appropriations Committee.)
SB 951 (Wiener, Chapter 775, Statutes of 2024) would modify existing rezoning standards to add the requirement that jurisdictions within the coastal zone identify any necessary local coastal program updates, among other provisions.
SB 272 (Laird, Chapter 384, Statutes of 2023) requires a local government in the coastal zone or within the San Francisco Bay to develop a sea level rise plan as part of either a LCP or a shoreline resiliency plan that includes certain information, including sea level rise adaptation strategies and recommended projects, requires local governments to comply by January 1, 2034, as specified, and prioritizes funding for implementation of sea level rise adaptation strategies in approved plans, among other things.
SUGGESTED AMENDMENTS: none
SUPPORT
Bay Area Council
California Apartment Association
California Coastal Protection Network
Environmental Action Committee of West Marin
Surfrider Foundation
OPPOSITION
None received
-- END --