SB 1214: University of California: Best Value Construction Contracting Pilot Program.
- Session Year: 2015-2016
- House: Senate
- Latest Version Date: 2016-09-28
(1)Existing law authorizes, through January 1, 2017, a pilot program for the Regents of the University of California to contract for certain types of projects on the university of the University of California based on the best value procedures, as specified. Existing law defines the term university to mean the campuses of the University of California, including the medical centers. The law requires, on or before January 1, 2016, the Regents of the University of California to report to specific committees of the Legislature regarding the pilot program, including, among other information, a description of the projects awarded using the best value procedures.
This bill would extend the provisions of the pilot program until January 1, 2018, and would repeal the reporting requirement. This bill would modify the definition of the term university to mean all locations of the University of California.
(2)By extending the requirement that bidders verify specified information under oath, this bill would impose a state-mandated local program by expanding the scope of an existing crime.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
(1)Existing law authorizes, through January 1, 2017, a pilot program for the Regents of the University of California to contract for certain types of projects on the university of the University of California based on the best value procedures, as specified. Existing law defines the term university to mean the campuses of the University of California, including the medical centers. The law requires, on or before January 1, 2016, the Regents of the University of California to report to specific committees of the Legislature regarding the pilot program, including, among other information, a description of the projects awarded using the best value procedures.
This bill would extend the provisions of the pilot program until January 1, 2018, and would repeal the reporting requirement. This bill would modify the definition of the term university to mean all locations of the University of California.
(2)By extending the requirement that bidders verify specified information under oath, this bill would impose a state-mandated local program by expanding the scope of an existing crime.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
(1)Existing law authorizes, through January 1, 2017, a pilot program for the Regents of the University of California to contract for certain types of projects on the university of the University of California based on the best value procedures, as specified. Existing law defines the term university to mean the campuses of the University of California, including the medical centers. The law requires, on or before January 1, 2016, the Regents of the University of California to report to specific committees of the Legislature regarding the pilot program, including, among other information, a description of the projects awarded using the best value procedures.
This bill would make extend the provisions of pilot program effective indefinitely until January 1, 2018, as the Best Value Construction Contracting Pilot Program and would make conforming changes by repealing repeal the reporting requirement and references to a pilot program. requirement. This bill would modify the definition of the term university to mean all locations of the University of California.
(2)By extending the requirement that bidders verify specified information under oath, this bill would impose a state-mandated local program by expanding the scope of an existing crime.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
(1)Existing law authorizes, through January 1, 2017, a pilot program for the Regents of the University of California to contract for certain types of projects on the university of the University of California based on the best value procedures, as specified. Existing law defines the term university to mean the campuses of the University of California, including the medical centers. The law requires, on or before January 1, 2016, the Regents of the University of California to report to specific committees of the Legislature regarding the pilot program, including, among other information, a description of the projects awarded using the best value procedures.
This bill would make the provisions of pilot program effective indefinitely as the Best Value Construction Contracting Program and would make conforming changes by repealing the reporting requirement and references to a pilot program. This bill would modify the definition of the term university to mean all locations of the University of California.
(2)By extending the requirement that bidders verify specified information under oath, this bill would impose a state-mandated local program by expanding the scope of an existing crime.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law establishes the Department of Veterans Affairs within state government and sets forth its powers and duties, including, but not limited to, the administration of veterans benefits programs. Existing law requires the department to make available to family members of veterans returning from active duty user-friendly Internet resources that provide information on the signs of pertinent ailments from various conflicts, as specified, and printed material regarding those ailments at any public function of the department. Existing law requires the department to post information pertaining to benefit programs that are available to qualified homeless veterans on its Internet Web site.
This bill would require the Department of Veterans Affairs to develop and implement a plan, by January 1, 2018, to routinely analyze myCalVet data, as defined, to identify trends in the services veterans and their families indicate they are most interested in, and to incorporate the results of those analyses into its outreach efforts, as specified.
Existing law establishes the Department of Veterans Affairs within state government and sets forth its powers and duties, including, but not limited to, the administration of veterans benefits programs. Existing law requires the department to make available to family members of veterans returning from active duty user-friendly Internet resources that provide information on the signs of pertinent ailments from various conflicts, as specified, and printed material regarding those ailments at any public function of the department. Existing law requires the department to post information pertaining to benefit programs that are available to qualified homeless veterans on its Internet Web site.
This bill would require the Department of Veterans Affairs to develop and implement a plan, by January 1, 2018, to routinely analyze myCalVet data, as defined, to identify trends in the services veterans and their families indicate they are most interested in, and to incorporate the results of those analyses into its outreach efforts, as specified.
(a)This article provides the Best Value Construction Contracting Pilot Program for the Regents of the University of California for projects over one million dollars ($1,000,000).
(b)The Regents of the University of California shall let any contract for a project pursuant to this article to the lowest responsible bidder or else reject all bids.
(c)The lowest responsible bidder may be selected on the basis of the best value to the university, as defined in Section 10506.5. In order to implement this method of selection, the Regents of the University of California shall adopt and publish procedures and required guidelines for evaluating the qualifications of the bidders that ensure that best value selections by the university are conducted in a fair and impartial manner. These procedures and guidelines shall conform to the requirements of Sections 10506.6 and 10506.7 and shall be mandatory for the university when using best value selection.
(d)If one or more of the bids is substantially equal to the lowest bid, and at least one of those bidders is a disadvantaged business enterprise, a women business enterprise, or a disabled veteran business enterprise, the regents may award the contract in accordance with the policies and procedures adopted pursuant to Section 10500.5.
(e)If the regents deem it to be for the best interest of the university, the regents may, on the refusal or failure of the successful bidder for a project to execute a tendered contract, award it to the second lowest responsible bidder. If the second lowest bidder fails or refuses to execute the contract, the regents may likewise award it to the third lowest responsible bidder.
SEC. 3.Section 10506.5 of the Public Contract Code is amended to read:10506.5.For purposes of this article, the following definitions apply:
(a)Best value means a procurement process whereby the lowest responsible bidder may be selected on the basis of objective criteria for evaluating the qualifications of bidders with the resulting selection representing the best combination of price and qualifications.
(b)Best value contract means a contract entered into pursuant to the provisions of this article.
(c)Best value contractor means a properly licensed person, firm, or corporation that submits a bid for, or is awarded, a best value contract.
(d)Demonstrated management competency means the experience, competency, capability, and capacity of the proposed management staffing to complete projects of similar size, scope, or complexity.
(e)Financial condition means the financial resources needed to perform the contract. The criteria used to evaluate a bidders financial condition shall include, at a minimum, capacity to obtain all required payment bonds, performance bonds, and liability insurance.
(f)Labor compliance means the ability to comply with, and past performance with, contract and statutory requirements for the payment of wages and qualifications of the workforce. The criteria used to evaluate a bidders labor compliance shall include, as a minimum, the bidders ability to comply with the apprenticeship requirements of the California Apprenticeship Council and the Department of Industrial Relations, its past conformance with such requirements, and its past conformance with requirements to pay prevailing wages on public works projects.
(g)Qualifications means financial condition, relevant experience, demonstrated management competency, labor compliance, the safety record of the bidder, and, if required by the bidding documents, some or all of the preceding qualifications as they pertain to subcontractors proposed to be used by the bidder for designated portions of the work.
(h)Relevant experience means the experience, competency, capability, and capacity to complete projects of similar size, scope, or complexity.
(i)Safety record means the prior history concerning the safe performance of construction contracts. The criteria used to evaluate a bidders safety record shall include, as a minimum, its experience modification rate for the most recent three-year period, and its average total recordable injury or illness rate and average lost work rate for the most recent three-year period.
(j)University means all locations of the University of California.
SEC. 4.Section 10506.8 of the Public Contract Code is repealed.SEC. 5.Section 10506.9 of the Public Contract Code is amended to read:10506.9.This article shall remain in effect only until January 1, 2018, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2018, deletes or extends that date.
SEC. 6.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
(a)This article provides the Best Value Construction Contracting Pilot Program for the Regents of the University of California for projects over one million dollars ($1,000,000).
(b)The Regents of the University of California shall let any contract for a project pursuant to this article to the lowest responsible bidder or else reject all bids.
(c)The lowest responsible bidder may be selected on the basis of the best value to the university, as defined in Section 10506.5. In order to implement this method of selection, the Regents of the University of California shall adopt and publish procedures and required guidelines for evaluating the qualifications of the bidders that ensure that best value selections by the university are conducted in a fair and impartial manner. These procedures and guidelines shall conform to the requirements of Sections 10506.6 and 10506.7 and shall be mandatory for the university when using best value selection.
(d)If one or more of the bids is substantially equal to the lowest bid, and at least one of those bidders is a disadvantaged business enterprise, a women business enterprise, or a disabled veteran business enterprise, the regents may award the contract in accordance with the policies and procedures adopted pursuant to Section 10500.5.
(e)If the regents deem it to be for the best interest of the university, the regents may, on the refusal or failure of the successful bidder for a project to execute a tendered contract, award it to the second lowest responsible bidder. If the second lowest bidder fails or refuses to execute the contract, the regents may likewise award it to the third lowest responsible bidder.
SEC. 3.Section 10506.5 of the Public Contract Code is amended to read:10506.5.For purposes of this article, the following definitions apply:
(a)Best value means a procurement process whereby the lowest responsible bidder may be selected on the basis of objective criteria for evaluating the qualifications of bidders with the resulting selection representing the best combination of price and qualifications.
(b)Best value contract means a contract entered into pursuant to the provisions of this article.
(c)Best value contractor means a properly licensed person, firm, or corporation that submits a bid for, or is awarded, a best value contract.
(d)Demonstrated management competency means the experience, competency, capability, and capacity of the proposed management staffing to complete projects of similar size, scope, or complexity.
(e)Financial condition means the financial resources needed to perform the contract. The criteria used to evaluate a bidders financial condition shall include, at a minimum, capacity to obtain all required payment bonds, performance bonds, and liability insurance.
(f)Labor compliance means the ability to comply with, and past performance with, contract and statutory requirements for the payment of wages and qualifications of the workforce. The criteria used to evaluate a bidders labor compliance shall include, as a minimum, the bidders ability to comply with the apprenticeship requirements of the California Apprenticeship Council and the Department of Industrial Relations, its past conformance with such requirements, and its past conformance with requirements to pay prevailing wages on public works projects.
(g)Qualifications means financial condition, relevant experience, demonstrated management competency, labor compliance, the safety record of the bidder, and, if required by the bidding documents, some or all of the preceding qualifications as they pertain to subcontractors proposed to be used by the bidder for designated portions of the work.
(h)Relevant experience means the experience, competency, capability, and capacity to complete projects of similar size, scope, or complexity.
(i)Safety record means the prior history concerning the safe performance of construction contracts. The criteria used to evaluate a bidders safety record shall include, as a minimum, its experience modification rate for the most recent three-year period, and its average total recordable injury or illness rate and average lost work rate for the most recent three-year period.
(j)University means all locations of the University of California.
SEC. 4.Section 10506.8 of the Public Contract Code is repealed.SEC. 5.Section 10506.9 of the Public Contract Code is amended to read:10506.9.This article shall remain in effect only until January 1, 2018, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2018, deletes or extends that date.
SEC. 6.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
(a)This article provides the Best Value Construction Contracting Pilot Program for the Regents of the University of California for projects over one million dollars ($1,000,000).
(b)The Regents of the University of California shall let any contract for a project pursuant to this article to the lowest responsible bidder or else reject all bids.
(c)The lowest responsible bidder may be selected on the basis of the best value to the university, as defined in Section 10506.5. In order to implement this method of selection, the Regents of the University of California shall adopt and publish procedures and required guidelines for evaluating the qualifications of the bidders that ensure that best value selections by the university are conducted in a fair and impartial manner. These procedures and guidelines shall conform to the requirements of Sections 10506.6 and 10506.7 and shall be mandatory for the university when using best value selection.
(d)If one or more of the bids is substantially equal to the lowest bid, and at least one of those bidders is a disadvantaged business enterprise, a women business enterprise, or a disabled veteran business enterprise, the regents may award the contract in accordance with the policies and procedures adopted pursuant to Section 10500.5.
(e)If the regents deem it to be for the best interest of the university, the regents may, on the refusal or failure of the successful bidder for a project to execute a tendered contract, award it to the second lowest responsible bidder. If the second lowest bidder fails or refuses to execute the contract, the regents may likewise award it to the third lowest responsible bidder.
SEC. 3.Section 10506.5 of the Public Contract Code is amended to read:10506.5.For purposes of this article, the following definitions apply:
(a)Best value means a procurement process whereby the lowest responsible bidder may be selected on the basis of objective criteria for evaluating the qualifications of bidders with the resulting selection representing the best combination of price and qualifications.
(b)Best value contract means a contract entered into pursuant to the provisions of this article.
(c)Best value contractor means a properly licensed person, firm, or corporation that submits a bid for, or is awarded, a best value contract.
(d)Demonstrated management competency means the experience, competency, capability, and capacity of the proposed management staffing to complete projects of similar size, scope, or complexity.
(e)Financial condition means the financial resources needed to perform the contract. The criteria used to evaluate a bidders financial condition shall include, at a minimum, capacity to obtain all required payment bonds, performance bonds, and liability insurance.
(f)Labor compliance means the ability to comply with, and past performance with, contract and statutory requirements for the payment of wages and qualifications of the workforce. The criteria used to evaluate a bidders labor compliance shall include, as a minimum, the bidders ability to comply with the apprenticeship requirements of the California Apprenticeship Council and the Department of Industrial Relations, its past conformance with such requirements, and its past conformance with requirements to pay prevailing wages on public works projects.
(g)Qualifications means financial condition, relevant experience, demonstrated management competency, labor compliance, the safety record of the bidder, and, if required by the bidding documents, some or all of the preceding qualifications as they pertain to subcontractors proposed to be used by the bidder for designated portions of the work.
(h)Relevant experience means the experience, competency, capability, and capacity to complete projects of similar size, scope, or complexity.
(i)Safety record means the prior history concerning the safe performance of construction contracts. The criteria used to evaluate a bidders safety record shall include, as a minimum, its experience modification rate for the most recent three-year period, and its average total recordable injury or illness rate and average lost work rate for the most recent three-year period.
(j)University means all locations of the University of California.
SEC. 4.Section 10506.8 of the Public Contract Code is repealed.SEC. 5.Section 10506.9 of the Public Contract Code is repealed.SEC. 5.Section 10506.9 of the Public Contract Code is amended to read:10506.9.This article shall remain in effect only until January 1, 2017, 2018, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2017, 2018, deletes or extends that date.
SEC. 6.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
(a)This article provides for a pilot program the Best Value Construction Contracting Program for the Regents of the University of California for projects over one million dollars ($1,000,000).
(b)The Regents of the University of California shall let any contract for a project pursuant to this article to the lowest responsible bidder or else reject all bids.
(c)The lowest responsible bidder may be selected on the basis of the best value to the university, as defined in Section 10506.5. In order to implement this method of selection, the Regents of the University of California shall adopt and publish procedures and required guidelines for evaluating the qualifications of the bidders that ensure that best value selections by the university are conducted in a fair and impartial manner. These procedures and guidelines shall conform to the requirements of Sections 10506.6 and 10506.7 and shall be mandatory for the university when using best value selection.
(d)If one or more of the bids is substantially equal to the lowest bid, and at least one of those bidders is a disadvantaged business enterprise, a women business enterprise, or a disabled veteran business enterprise, the regents may award the contract in accordance with the policies and procedures adopted pursuant to Section 10500.5.
(e)If the regents deem it to be for the best interest of the university, the regents may, on the refusal or failure of the successful bidder for a project to execute a tendered contract, award it to the second lowest responsible bidder. If the second lowest bidder fails or refuses to execute the contract, the regents may likewise award it to the third lowest responsible bidder.
SEC. 3.Section 10506.5 of the Public Contract Code is amended to read:10506.5.For purposes of this article, the following definitions apply:
(a)Best value means a procurement process whereby the lowest responsible bidder may be selected on the basis of objective criteria for evaluating the qualifications of bidders with the resulting selection representing the best combination of price and qualifications.
(b)Best value contract means a contract entered into pursuant to the provisions of this article.
(c)Best value contractor means a properly licensed person, firm, or corporation that submits a bid for, or is awarded, a best value contract.
(d)Demonstrated management competency means the experience, competency, capability, and capacity of the proposed management staffing to complete projects of similar size, scope, or complexity.
(e)Financial condition means the financial resources needed to perform the contract. The criteria used to evaluate a bidders financial condition shall include, at a minimum, capacity to obtain all required payment bonds, performance bonds, and liability insurance.
(f)Labor compliance means the ability to comply with, and past performance with, contract and statutory requirements for the payment of wages and qualifications of the workforce. The criteria used to evaluate a bidders labor compliance shall include, as a minimum, the bidders ability to comply with the apprenticeship requirements of the California Apprenticeship Council and the Department of Industrial Relations, its past conformance with such requirements, and its past conformance with requirements to pay prevailing wages on public works projects.
(g)Qualifications means financial condition, relevant experience, demonstrated management competency, labor compliance, the safety record of the bidder, and, if required by the bidding documents, some or all of the preceding qualifications as they pertain to subcontractors proposed to be used by the bidder for designated portions of the work.
(h)Relevant experience means the experience, competency, capability, and capacity to complete projects of similar size, scope, or complexity.
(i)Safety record means the prior history concerning the safe performance of construction contracts. The criteria used to evaluate a bidders safety record shall include, as a minimum, its experience modification rate for the most recent three-year period, and its average total recordable injury or illness rate and average lost work rate for the most recent three-year period.
(j)University means all campuses locations of the University of California, including the medical centers. California.
SEC. 4.Section 10506.8 of the Public Contract Code is repealed.10506.8.On or before January 1, 2016, the Regents of the University of California shall submit a report to the appropriate policy committees of the Legislature and the Joint Legislative Budget Committee. The report shall include, but is not limited to, the following information:
(a)A description of the projects awarded using the best value procedures.
(b)The contract award amounts.
(c)The best value contractors awarded the projects.
(d)A description of any written protests concerning any aspect of the solicitation, bid, or award of the best value contracts, including the resolution of the protests.
(e)A description of the prequalification process.
(f)The criteria used to evaluate the bids, including the weighting of the criteria and an assessment of the effectiveness of the methodology.
(g)If a project awarded under this article has been completed, an assessment of the project performance, to include a summary of any delays or cost increases.
SEC. 5.Section 10506.9 of the Public Contract Code is repealed.10506.9.This article shall remain in effect only until January 1, 2017, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2017, deletes or extends that date.
SEC. 6.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
SECTION 1.Section 712.5 is added to the Military and Veterans Code, to read:712.5.(a)By January 1, 2018, the department shall develop and implement a plan to routinely analyze and use myCalVet data to identify trends in the services veterans and their families indicate they are most interested in, and to incorporate the results of that analyses into its outreach efforts.
(b)To determine the most successful methods for informing veterans and their families about the myCalVet Internet Web site, and to increase the number of registered users, the department shall evaluate myCalVet data to identify which outreach methods were most effective in informing registered users about the myCalVet Internet Web site.
(c)For purposes of this section:
(1)MyCalVet data means the data collected or accessed through the myCalVet Internet Web site.
(2)MyCalVet Internet Web site means the Internet Web site maintained by the department that allows veterans and family members to connect to veterans benefits and services through the creation of online profiles that provide access to information related to, among others, health care, education, housing, employment, advocacy, claims assistance, and service providers.
(a)By January 1, 2018, the department shall develop and implement a plan to routinely analyze and use myCalVet data to identify trends in the services veterans and their families indicate they are most interested in, and to incorporate the results of that analyses into its outreach efforts.
(b)To determine the most successful methods for informing veterans and their families about the myCalVet Internet Web site, and to increase the number of registered users, the department shall evaluate myCalVet data to identify which outreach methods were most effective in informing registered users about the myCalVet Internet Web site.
(c)For purposes of this section:
(1)MyCalVet data means the data collected or accessed through the myCalVet Internet Web site.
(2)MyCalVet Internet Web site means the Internet Web site maintained by the department that allows veterans and family members to connect to veterans benefits and services through the creation of online profiles that provide access to information related to, among others, health care, education, housing, employment, advocacy, claims assistance, and service providers.
|
Date
|
Status
|
|---|---|
| Sep 8, 2016 | Enrolled and presented to the Governor at 5 p.m. |
| Aug 29, 2016 | Assembly amendments concurred in. (Ayes 30. Noes 7. Page 5475.) Ordered to engrossing and enrolling. |
| Aug 29, 2016 | Assembly amendments concurred in. (Ayes 29. Noes 7.) Ordered to engrossing and enrolling. |
| Aug 25, 2016 | Read third time. Passed. (Ayes 66. Noes 12. Page 6270.) Ordered to the Senate. |
| Aug 25, 2016 | In Senate. Concurrence in Assembly amendments pending. |
| Aug 25, 2016 | Read third time. Passed. Ordered to the Senate. |
| Aug 4, 2016 | Read second time. Ordered to third reading. |
| Aug 3, 2016 | From committee: Do pass. (Ayes 17. Noes 3.) (August 3). |
| Jun 23, 2016 | Read second time and amended. Re-referred to Com. on APPR. |
| Jun 22, 2016 | From committee: Do pass as amended and re-refer to Com. on APPR. (Ayes 11. Noes 0.) (June 21). |
| Jun 14, 2016 | June 14 set for first hearing canceled at the request of author. |
| May 16, 2016 | Referred to Com. on HIGHER ED. |
| May 10, 2016 | In Assembly. Read first time. Held at Desk. |
| May 9, 2016 | Read third time. Passed. (Ayes 27. Noes 9. Page 3800.) Ordered to the Assembly. |
| May 9, 2016 | Read third time. Passed. (Ayes 27. Noes 9.) Ordered to the Assembly. |
| Apr 26, 2016 | Read second time. Ordered to third reading. |
| Apr 25, 2016 | From committee: Be ordered to second reading pursuant to Senate Rule 28.8. |
| Apr 15, 2016 | Set for hearing April 25. |
| Apr 13, 2016 | From committee: Do pass and re-refer to Com. on APPR. (Ayes 8. Noes 1. Page 3516.) (April 13). Re-referred to Com. on APPR. |
| Apr 13, 2016 | From committee: Do pass and re-refer to Com. on APPR. (Ayes 8. Noes 1.) (April 13). Re-referred to Com. on APPR. |
| Apr 8, 2016 | Set for hearing April 13. |
| Apr 7, 2016 | Re-referred to Com. on ED. |
| Apr 4, 2016 | Re-referred to Com. on RLS. |
| Apr 4, 2016 | Withdrawn from committee. |
| Mar 31, 2016 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on V.A. |
| Mar 3, 2016 | Referred to Coms. on V.A. and JUD. |
| Feb 19, 2016 | From printer. May be acted upon on or after March 20. |
| Feb 18, 2016 | Introduced. Read first time. To Com. on RLS. for assignment. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Aug 29, 2016 | Unfinished Business SB1214 Allen Concurrence | Senate Floor |
Passed |
|
| Aug 25, 2016 | SB 1214 Allen Senate Third Reading By CHIU | Assembly Floor |
Passed |
|
| Aug 3, 2016 | Do pass. | Assembly Standing Committee on Appropriations |
Passed |
|
| Jun 21, 2016 | Do pass as amended and be re-referred to the Committee on [Appropriations] | Assembly Standing Committee on Higher Education |
Passed |
|
| May 9, 2016 | Senate 3rd Reading SB1214 Allen | Senate Floor |
Passed |
|
| Apr 13, 2016 | Do pass, but first be re-referred to the Committee on [Appropriations] | Senate Standing Committee on Education |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB |
UNFINISHED BUSINESS
Bill No: SB 1214
:
SENATE EDUCATION COMMITTEE: 8-1, 4/13/16
AYES: Liu, Block, Hancock, Leyva, Mendoza, Monning, Pan, Vidak
NOES: Huff
SENATE APPROPRIATIONS COMMITTEE: Senate Rule 28.8
SENATE FLOOR: 27-9, 5/9/16
AYES: Allen, Beall, Block, De León, Galgiani, Glazer, Hall, Hancock, Hernandez, Hertzberg, Hill, Hueso, Jackson, Lara, Leno, Leyva, Liu, McGuire, Mendoza, Mitchell, Monning, Pan, Pavley, Roth, Vidak, Wieckowski, Wolk
NOES: Anderson, Berryhill, Cannella, Fuller, Moorlach, Morrell, Nguyen, Nielsen, Stone
NO VOTE RECORDED: Bates, Gaines, Huff, Runner
ASSEMBLY FLOOR: 66-12, 8/25/16 - See last page for vote
DIGEST: This bill extends the sunset date on the authority of the University of California (UC) to use the best value procurement method at all its campuses and medical centers to January 1, 2018.
Assembly Amendments extend the sunset to January 1, 2018, for UC to use the best value procurement method, rather than permanently extending that authority.
Existing law:
- Authorizes, until January 1, 2017, a pilot program at the UC to award construction contracts on a "best value" basis, rather than just to the lowest bid. (Public Contract Code §10506.4)
- Defines "best value," for purposes of the UC, as a procurement process whereby, the lowest responsible bidder may be selected on the basis of objective criteria with the resulting selection representing the best combination of price and qualifications. (Public Contract Code § 10506.5)
- Establishes a pilot program to authorize the Los Angeles Unified School District to use a best value procurement method, before December 31, 2020, for public projects that exceed $1 million, and requires submission of specified reports on the use of this procurement method. (Public Contract Code § 20119 - 20119.7)
This bill:
- Expands the authority of the UC to use best value contracting beyond its campuses and medical centers to include all locations of the UC.
- Deletes obsolete reporting requirements.
- Extends the sunset on the authority of the UC to use the best value procurement method to January 1, 2018.
- Makes several technical and conforming changes.
Comments
Need for the bill. The existing law which authorizes the UC Best Value Pilot program sunsets on January 1, 2017. According to the author, without this bill, the UC will forego the ability to employ a contractor selection method that provides significant opportunity for cost avoidance. The UC estimates that these projects were completed with a demonstrated savings of about 3 percent.
UC Best Value Pilot Program. SB 667 (Migden, Chapter 367, Statutes of 2006) established a Best Value Pilot program for the UC. Initially authorized for five years, the bill allowed the UC San Francisco to award contracts based on the best value for the university. Under this process, UC prequalifies bidders, then evaluates the bid based on answers to a separate best value questionnaire and assigns a qualification score. UC then divides each bidder's price by its qualification score. The lowest resulting cost per quality point represents the best value bid.
In a report to the Legislature, in January 2010, the UC reported that 23 contracts totaling $158.3 million were issued under the Best Value Pilot program. Of the 23 contracts, 12 contracts were low bid contracts. According to the report, the "University Representatives for all these projects [four completed and two almost completed projects] have been unanimous in their praise of this process that has already demonstrated numerous advantages such as decreased bid protests and communication problems, decreased the need for multiple inspections and re-work, decreased disputes, change order requests, claims and litigation and increased incentives for contractors to perform their work safety and to adhere to high labor and quality standards." UC concludes that the Best Value Pilot program fosters better quality work, less labor and safety problems, better qualified persons/contractors, better on-time completion, and better on-budget performance. In 2011, SB 835 (Wolk, Chapter 636, Statutes of 2011), expanded the authority to all UC campuses, including medical centers, and extended the sunset from January 1, 2012, to January 1, 2017.
In its December 18, 2015 report, the UC reports that of the 320 construction contracts awarded since January 1, 2012, 40 totaling $1.19 billion were awarded through the Best Value Pilot program, representing 13 percent of overall projects. The UC cites numerous advantages of this process including decreased bid protests, improved communication with contractors, reduced re-inspection and re-work, fewer disputes, change order requests, claims and litigation. The UC notes that the selection criteria it uses for best value procurement rewards contractors for maintaining strong safety and labor compliance standards and delivering high quality workmanship. The UC also notes that its best value contractor selection was met with nearly unanimous praise from the design and contracting community.
FISCAL EFFECT: Appropriation: Fiscal Com.: Local:
According to the Assembly Appropriations Committee, based on the results to date of UC's use of best value procurement, the university could realize additional significant savings in contract and contract administration costs for the additional year that this authority is extended under this bill.
State Building and Construction Trades Council
University of California
OPPOSITION: (Verified 8/25/16)
None received
ASSEMBLY FLOOR: 66-12, 8/25/16
AYES: Alejo, Arambula, Atkins, Baker, Bloom, Bonilla, Bonta, Brown, Calderon, Campos, Chang, Chau, Chávez, Chiu, Chu, Cooley, Cooper, Dababneh, Daly, Dodd, Eggman, Frazier, Gallagher, Cristina Garcia, Eduardo Garcia, Gatto, Gipson, Gomez, Gonzalez, Gordon, Gray, Hadley, Roger Hernández, Holden, Irwin, Jones-Sawyer, Kim, Lackey, Levine, Linder, Lopez, Low, Maienschein, McCarty, Medina, Mullin, Nazarian, Obernolte, O'Donnell, Olsen, Quirk, Ridley-Thomas, Rodriguez, Salas, Santiago, Steinorth, Mark Stone, Thurmond, Ting, Wagner, Waldron, Weber, Wilk, Williams, Wood, Rendon
NOES: Achadjian, Travis Allen, Bigelow, Brough, Dahle, Beth Gaines, Grove, Harper, Jones, Mathis, Melendez, Patterson
NO VOTE RECORDED: Burke, Mayes
8/25/16 17:30:40
**** END ****
SENATE THIRD READING
STR Bill Id:SB 1214
Author:(Allen)
As Amended Ver:June 23, 2016
Majority vote
SENATE VOTE: 27-9
Committee | Votes | Ayes | Noes |
Higher Education | 11-0 | Medina, Baker, Chávez, Irwin, Jones-Sawyer, Levine, Linder, Low, Santiago, Weber, Williams | |
Appropriations | 17-3 | Gonzalez, Bloom, Bonilla, Bonta, Calderon, Chang, Daly, Eggman, Gallagher, Eduardo Garcia, Holden, Obernolte, Quirk, Santiago, Weber, Wood, Chau | Bigelow, Jones, Wagner |
SUMMARY: Extends the sunset on the authority of the University of California (UC) to use the best value procurement method at all its campuses and medical centers. Specifically, this bill:
- Extends the sunset by one year, until January 1, 2018, on the authority of the UC Regents to use the best value procurement method for projects over $1 million at all its campuses and medical centers.
- Deletes obsolete reporting requirements.
- Makes several technical and conforming changes.
EXISTING LAW:
- Authorizes, until January 1, 2017, a pilot program at the UC to award construction contracts over $1 million, on a "best value" basis, rather than just to the lowest bid (Public Contract Code (PCC) Section 10506.4).
- Defines "best value," for purposes of the UC, as a procurement process whereby, the lowest responsible bidder may be selected on the basis of objective criteria with the resulting selection representing the best combination of price and qualifications (PCC Section 10506.5).
- Requires the UC Regents, on or before January 1, 2016, to submit a report to the appropriate policy committees of the Legislature and the Joint Legislative Budget Committee, regarding the UC's best value pilot (PCC Section 10506.8).
- Establishes a pilot program to authorize the Los Angeles Unified School District (LAUSD) to use a best value procurement method, before December 31, 2020, for public projects that exceed $1 million, and requires submission of specified reports on the use of this procurement method (PCC Sections 20119 - 20119.7).
FISCAL EFFECT: According to the Assembly Appropriations Committee, based on the results to date of UC's use of best value procurement, the university could realize additional significant savings in contract and contract administration costs for the additional year that this authority is extended under this bill.
COMMENTS: History of UC Best Value Pilot. SB 667 (Migden), Chapter 367, Statutes of 2006, created the UC Best Value Pilot, authorized for five years, solely at UC's San Francisco campus (UCSF). SB 667 allowed UCSF to award contracts based on the best value for the university. Under this process, UC prequalifies bidders, then evaluates the bid based on answers to a separate best value questionnaire and assigns a qualification score. UC then divides each bidder's price by its qualification score. The lowest resulting cost per quality point represents the best value bid.
Senate Bill 835 (Wolk), Chapter 636, Statutes of 2011, extended the sunset in SB 667 and expanded the best value pilot to all UC campuses and medical centers for five more years; with a status report due to the Joint Legislative Budget Committee, on or before January 1, 2016.
According to the UC "Report on the Best Value Construction Contract Pilot Program", issued in December 2015, since January 2012, UC awarded over 320 construction contracts totaling $4.05 billion. Forty of these contracts, or 13%, totaling $1.19 billion, utilized the best value construction authority. Additionally, the report finds that given the additional time and administrative requirements associated with the best value selection process, the UC screens its projects carefully to maximize the value obtained from said process.
To note, according to the author's office, when SB 835 was initially debated in the Legislature, some legislators expressed concerns that granting best value authority to the UC would allow for subjectivity and favoritism to enter into the selection process. However, according to the report, "To date, no bidder, or third-party for that matter, has protested any qualification score determined by the University's BV [best value] Contractor Selection scoring committees." Lastly, the report finds that UC's best value pilot has fostered improved cooperative project administration, better quality work, less labor and safety violations, better qualified contractors, more on-time completion of projects, and increased on-budget performance.
Need for the measure. According to the author, "Best Value contracting is far more effective at selecting contractors who will provide the lowest finished cost as opposed to selecting contractors on the basis of the lowest first cost." The author contends that best value contracting has been met with praise from the design and contracting community and that the loss of UC's authority to offer best value contracting would be to the detriment of students, patients, researchers, faculty, and the taxpayers of California.
Related legislation. SB 667 (Migden), SB 835 (Wolk) – as described in the "History of the UC Best Value Pilot" section of this analysis, and AB 1185 (Ridley-Thomas), Chapter 786, Statutes of 2015, which, among others, authorizes the Los Angeles Unified School District to utilize a best value procurement process as a pilot project until January 1, 2021, for construction projects over $1 million.
Analysis Prepared by: Jeanice Warden / HIGHER ED. / (916) 319-3960 FN: 0003786
Date of Hearing: August 3, 2016
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Lorena Gonzalez, Chair
SBPCA Bill Id:SB 1214
Author:(Allen) – As Amended Ver:June 23, 2016
Policy Committee: | Higher Education | Vote: | 11 - 0 |
|
| ||
|
|
Urgency: No State Mandated Local Program: Yes Reimbursable: No
SUMMARY:
This bill extends by one year, until January 1, 2018, the sunset on the University of California's (UC's) authority to use the best value procurement method at all its campuses and medical centers.
FISCAL EFFECT:
Based on the results to date of UC's use of best value procurement, the university could realize additional savings significant savings in contract and contract administration costs for the additional year that this authority is extended under this bill.
COMMENTS:
- Background. Best value procurement is an alternative to the traditional design-bid-build method of public works contracting. Under this program, UC prequalifies bidders, then evaluates the bid and assigns a qualification score based upon five factors, which include the bidder's financial condition, relevant experience, demonstrated management competency, labor compliance, and safety record. UC then divides each bidder's price by its qualification score, and the lowest resulting cost per quality point represents the best value bid.
SB 667 (Migden), Chapter 367, Statutes of 2006, established the five-year Best Value Pilot Program at UC San Francisco. SB 835 (Wolk), Chapter 636, Statutes of 2011, extended the sunset in SB 667 until January 1, 2017, and expanded the best value pilot to encompass all UC campuses and medical centers. In a December 2015 report on the pilot project, UC noted that, since January 2012, it had awarded over 320 construction contracts totaling $4 billion. Forty of these contracts, or 13 percent, totaling $1.2 billion, utilized the best value construction authority. UC reported that these contracts provided numerous benefits, including decreases in bid protests, disputes, change order requests and claims and reduced administrative oversight and contract/project management staff time.
- Purpose. Prior to the most recent amendments, this bill would have repealed the sunset on the best value program. In response to concerns expressed by the State Building and Construction Trades Council and the California Labor Federation that UC's best value statute does not conform to similar statutory authority provided to other public entities, the bill now just provides a one-year sunset extension.
Analysis Prepared by: Chuck Nicol / APPR. / (916) 319-2081
Date of Hearing: June 21, 2016
ASSEMBLY COMMITTEE ON HIGHER EDUCATION
Jose Medina, Chair
SBPCA Bill Id:SB 1214
Author:(Allen) – As Amended Ver:March 31, 2016
SENATE VOTE: 27-9
SUBJECT: University of California: Best Value Construction Contracting Program
SUMMARY: Eliminates the sunset on the authority of the University of California (UC) to use the best value procurement method at all its campuses and medical centers and permanently extends the authority of the UC to use this procurement method at all its locations. Specifically, this bill:
- Deletes the sunset on the authority of the UC Regents to use the best value procurement method for projects over $1 million.
- Expands the authority of the UC Regents to use best value contracting at all locations of the UC.
- Deletes obsolete reporting requirements.
- Makes several technical and conforming changes.
EXISTING LAW:
- Authorizes, until January 1, 2017, a pilot program at the UC to award construction contracts over $1 million, on a "best value" basis, rather than just to the lowest bid (Public Contract Code (PCC) Section 10506.4).
- Defines "best value," for purposes of the UC, as a procurement process whereby, the lowest responsible bidder may be selected on the basis of objective criteria with the resulting selection representing the best combination of price and qualifications (PCC Section 10506.5).
- Requires the UC Regents, on or before January 1, 2016, to submit a report to the appropriate policy committees of the Legislature and the Joint Legislative Budget Committee, regarding the UC's best value pilot (PCC Section 10506.8).
- Establishes a pilot program to authorize the Los Angeles Unified School District (LAUSD) to use a best value procurement method, before December 31, 2020, for public projects that exceed $1 million, and requires submission of specified reports on the use of this procurement method (PCC Sections 20119 - 20119.7).
FISCAL EFFECT: According to the Senate Appropriations Committee, pursuant to Senate Rule 28.8, negligible state costs.
COMMENTS: History UC Best Value Pilot. Senate Bill 667 (Migden), Chapter 367, Statutes of 2006, created the UC Best Value Pilot, authorized for five years, solely at UC's San Francisco campus (UCSF). SB 667 allowed UCSF to award contracts based on the best value for the university. Under this process, UC prequalifies bidders, then evaluates the bid based on answers to a separate best value questionnaire and assigns a qualification score. UC then divides each bidder's price by its qualification score. The lowest resulting cost per quality point represents the best value bid.
Senate Bill 835 (Wolk), Chapter 636, Statutes of 2011, extended the sunset in SB 667 and expanded the best value pilot to all UC campuses and medical centers for five more years; with a status report due to the Joint Legislative Budget Committee, on or before January 1, 2016.
According to the UC "Report on the Best Value Construction Contract Pilot Program", issued in December 2015, since January 2012, UC awarded over 320 construction contracts totaling $4.05 billion. Forty of these contracts, or 13 percent, totaling $1.19 billion, utilized the best value construction authority. Additionally, the report finds that given the additional time and administrative requirements associated with the best value selection process, the UC screens its projects carefully to maximize the value obtained from said process.
To note, according to the author's office, when SB 835 was initially debated in the Legislature, some legislators expressed concerns that granting best value authority to the UC would allow for subjectivity and favoritism to enter into the selection process. However, according to the report, "To date, no bidder, or third-party for that matter, has protested any qualification score determined by the University's BV [best value] Contractor Selection scoring committees." Lastly, the report finds that UC's best value pilot has fostered improved cooperative project administration, better quality work, less labor and safety violations, better qualified contractors, more on-time completion of projects, and increased on-budget performance.
Need for the measure. According to the author, "Best Value contracting is far more effective at selecting contractors who will provide the lowest finished cost as opposed to selecting contractors on the basis of the lowest first cost." The author contends that best value contracting has been met with praise from the design and contracting community and that the loss of UC's authority to offer best value contracting would be to the detriment of students, patients, researchers, faculty, and the taxpayers of California.
This measure seeks to permanently eliminate the sunset on UC's authority to be able to utilize a best value procurement process.
Arguments in Support. According to the UC, "the University continues to pursue increased efficiencies; use of best value has generated savings for UC campuses. These savings accrue from cost avoidance resulting from lack of bid protests, claims, and litigation." Additionally, UC contends that its experiences in utilizing best value has, "demonstrated that this method of contractor selection results in a higher success rate in terms of price, quality, and timely completion of capital projects. Removing the sunset on this program would allow UC to continue using best value for complex projects, such as those requiring a contract with unique skills or those where the performance of the contractor is critical in minimizing disruption to ongoing instruction, research, or healthcare activities."
Arguments in Opposition. According to State Building and Construction Trades Council, AFL-CIO (Building and Trades) and the California Labor Federation, "this measure does not contain important workforce requirements currently in law for other alternative delivery methods including best value." Building and Trades and the California Labor Federation contend that in recent years, legislation has been enacted that created uniform provisions for, "the Department of General Services, the California Department of Corrections and Rehabilitation, local agencies, cites, and counties who choose to use DB [design build]. Subsequent legislation added identical requirements to lease-back, DB, and best value for K-12 education facilities, as well as best value pilot program for several counties."
Requested amendment. Building and Trades and California Labor Federation argue that in the wake of SB 693 (Hueso), which is currently moving through the Legislative Process, and seeks to consolidate and create uniformity among the skilled and trained workforce statutes, the UC should only be granted a one year sunset on their best value program in order to allow all entities to, "partner on improvements to UC's best value program in the next Legislative Session."
10506.4. (a) This article provides the Best Value Construction Contracting pilot Program for the Regents of the University of California for projects over one million dollars ($1,000,000).
Section 10506.9 of the Public Contract Code is repealed. 10506.9. This article shall remain in effect only until January 1, 2018, and as of that date is repealed unless a later enacted statute, that is enacted before January 1, 2018, deletes or extends that date.
Related legislation. SB 667 (Migden), SB 835 (Wolk) – as described above, and AB 1185 (Ridley-Thomas), Chapter 786, Statutes of 2015, which, among others, authorizes the Los Angeles Unified School District to utilize a best value procurement process as a pilot project until January 1, 2021, for construction projects over $1 million.
REGISTERED SUPPORT / OPPOSITION:
Support
University of California
Opposition
California Chapters of the National Electrical Contractors Association
California Labor Federation
California State Association of Electrical Workers
California State Pipe Trades Council
International Union of Elevator Constructors
State Building and Construction Trades Council
Western States Council of Sheet Metal Workers
Analysis Prepared by: Jeanice Warden / HIGHER ED. / (916) 319-3960
Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB |
THIRD READING
Bill No: SB 1214
:
SENATE EDUCATION COMMITTEE: 8-1, 4/13/16
AYES: Liu, Block, Hancock, Leyva, Mendoza, Monning, Pan, Vidak
NOES: Huff
SENATE APPROPRIATIONS COMMITTEE: Senate Rule 28.8
DIGEST: This bill eliminates the sunset on the authority of the University of California (UC) to use the best value procurement method at all its campuses and medical centers and permanently extends the authority of the UC to use this procurement method at all its locations.
Existing law:
- Authorizes, until January 1, 2017, a pilot program at the UC to award construction contracts on a "best value" basis, rather than just to the lowest bid. (Public Contract Code §10506.4)
- Defines "best value," for purposes of the UC, as a procurement process whereby, the lowest responsible bidder may be selected on the basis of objective criteria with the resulting selection representing the best combination of price and qualifications. (Public Contract Code § 10506.5)
- Establishes a pilot program to authorize the Los Angeles Unified School District (LAUSD) to use a best value procurement method, before December 31, 2020, for public projects that exceed $1 million, and requires submission of specified reports on the use of this procurement method. (Public Contract Code § 20119 - 20119.7)
This bill:
- Expands the authority of the UC to use best value contracting beyond its campuses and medical centers to include all locations of the UC.
- Deletes obsolete reporting requirements.
- Deletes the sunset on the authority of the UC to use the best value procurement method, thereby extending this authority permanently.
- Makes several technical and conforming changes.
Comments
- Need for the bill. The existing law, which authorizes the University of California (UC) Best Value Pilot program sunsets on January 1, 2017. According to the author, without this bill, the UC will forego the ability to employ a contractor selection method that provides significant opportunity for cost avoidance. The UC estimates that these projects were completed with a demonstrated savings of about 3 percent.
- UC Best Value Pilot Program. SB 667 (Migden, Chapter 367, Statutes of 2006) established a Best Value Pilot program for the UC. Initially authorized for five years, the bill allowed the UC San Francisco to award contracts based on the best value for the university. Under this process, UC prequalifies bidders, then evaluates the bid based on answers to a separate best value questionnaire and assigns a qualification score. UC then divides each bidder's price by its qualification score. The lowest resulting cost per quality point represents the best value bid.
In a report to the Legislature, in January 2010, the UC reported that 23 contracts totaling $158.3 million were issued under the Best Value Pilot program. Of the 23 contracts, 12 contracts were low bid contracts. According to the report, the "University Representatives for all these projects [four completed and two almost completed projects] have been unanimous in their praise of this process that has already demonstrated numerous advantages such as decreased bid protests and communication problems, decreased the need for multiple inspections and re-work, decreased disputes, change order requests, claims and litigation and increased incentives for contractors to perform their work safety and to adhere to high labor and quality standards." UC concludes that the Best Value Pilot program fosters better quality work, less labor and safety problems, better qualified persons/contractors, better on-time completion, and better on-budget performance. In 2011, SB 835 (Wolk, Chapter 636, Statutes of 2011), expanded the authority to all UC campuses, including medical centers, and extended the sunset from January 1, 2012, to January 1, 2017.
In its December 18, 2015 report, the UC reports that of the 320 construction contracts awarded since January 1, 2012, 40 totaling $1.19 billion were awarded through the Best Value Pilot program, representing 13 percent of overall projects. The UC cites numerous advantages of this process including decreased bid protests, improved communication with contractors, reduced re-inspection and re-work, fewer disputes, change order requests, claims and litigation. The UC notes that the selection criteria it uses for best value procurement rewards contractors for maintaining strong safety and labor compliance standards and delivering high quality workmanship. The UC also notes that its best value contractor selection was met with nearly unanimous praise from the design and contracting community.
Prior Legislation
AB 1185 (Ridley-Thomas, Chapter 786, Statutes of 2015) established a Best Value Pilot program at the Los Angeles Unified School District (LAUSD). The provisions of AB 1185 were generally based upon provisions authorizing the Best Value Pilot program for the UC, but codified more prescriptive requirements around labor, contractors and subcontractors, and the weighting of certain factors in the evaluation of bids.
FISCAL EFFECT: Appropriation: Fiscal Com.: Local:
University of California
OPPOSITION: (Verified 4/26/16)
None received
4/27/16 15:57:26
**** END ****
SENATE COMMITTEE ON EDUCATION
Senator Carol Liu, Chair
2015 - 2016 Regular
Bill No: SB 1214
Author: | |||
Version: | March 31, 2016 Hearing Date: April 13, 2016 | ||
Urgency: | No | Fiscal: | Yes |
Consultant: | Kathleen Chavira | ||
Subject: University of California: Best Value Construction Contracting Program
SUMMARY
This bill eliminates the sunset on the authority of the University of California (UC) to use the best value procurement method at all its campuses and medical centers and permanently extends the authority of the UC to use this procurement method at all its locations.
BACKGROUND
Existing law, until January 1, 2017, authorizes a pilot program at the UC to award construction contracts on a "best value" basis, rather than just to the lowest bid.
(Public Contract Code §10506.4)
Existing law defines "best value," for purposes of the UC, as a procurement process whereby, the lowest responsible bidder may be selected on the basis of objective criteria with the resulting selection representing the best combination of price and qualifications. (Public Contract Code § 10506.5)
Existing law establishes a pilot program to authorize the Los Angeles Unified School District (LAUSD) to use a best value procurement method, before December 31, 2020, for public projects that exceed $1 million, and requires submission of specified reports on the use of this procurement method. (Public Contract Code § 20119 - 20119.7)
ANALYSIS
This bill:
- Expands the authority of the UC to use best value contracting beyond its campuses and medical centers to include all locations of the UC.
- Deletes obsolete reporting requirements.
- Deletes the sunset on the authority of the UC to use the best value procurement method, thereby extending this authority permanently.
- Makes several technical and conforming changes.
STAFF COMMENTS
- Need for the bill. The existing law, which authorizes the University of California (UC) Best Value Pilot program sunsets on January 1, 2017. According to the author, without this bill, the UC will forego the ability to employ a contractor selection method that provides significant opportunity for cost avoidance. The UC estimates that these projects were completed with a demonstrated savings of about 3 percent.
- UC Best Value Pilot Program. SB 667 (Migden, Chapter 367, Statutes of 2006) established a Best Value Pilot program for the UC. Initially authorized for five years, the bill allowed the UC San Francisco to award contracts based on the best value for the university. Under this process, UC prequalifies bidders, then evaluates the bid based on answers to a separate best value questionnaire and assigns a qualification score. UC then divides each bidder's price by its qualification score. The lowest resulting cost per quality point represents the best value bid.
In a report to the Legislature, in January 2010, the UC reported that 23 contracts totaling $158.3 million were issued under the Best Value Pilot program. Of the 23 contracts, 12 contracts were low bid contracts. According to the report, the "University Representatives for all these projects [four completed and two almost completed projects] have been unanimous in their praise of this process that has already demonstrated numerous advantages such as decreased bid protests and communication problems, decreased the need for multiple inspections and re-work, decreased disputes, change order requests, claims and litigation and increased incentives for contractors to perform their work safety and to adhere to high labor and quality standards." UC concludes that the Best Value Pilot program fosters better quality work, less labor and safety problems, better qualified persons/contractors, better on-time completion, and better on-budget performance. In 2011, SB 835 (Wolk, Chapter 636, Statutes of 2011), expanded the authority to all UC campuses, including medical centers, and extended the sunset from January 1, 2012, to January 1, 2017.
In its December 18, 2015 report, the UC reports that of the 320 construction contracts awarded since January 1, 2012, 40 totaling $1.19 billion were awarded through the Best Value Pilot program, representing 13 percent of overall projects. The UC cites numerous advantages of this process including decreased bid protests, improved communication with contractors, reduced re-inspection and re-work, fewer disputes, change order requests, claims and litigation. The UC notes that the selection criteria it uses for best value procurement rewards contractors for maintaining strong safety and labor compliance standards and delivering high quality workmanship. The UC also notes that its best value contractor selection was met with nearly unanimous praise from the design and contracting community.
- Prior legislation. AB 1185 (Ridley-Thomas, Chapter 786, Statutes of 2015) established a Best Value Pilot program at the Los Angeles Unified School District (LAUSD). The provisions of AB 1185 were generally based upon provisions authorizing the Best Value Pilot program for the UC, but codified more prescriptive requirements around labor, contractors and subcontractors, and the weighting of certain factors in the evaluation of bids.
SUPPORT
University of California
OPPOSITION
None received.
-- END --
Discussed in Hearing
Assembly Standing Committee on Revenue and Taxation
Senate Floor
Assembly Floor
Assembly Standing Committee on Appropriations
Senate Floor
Senate Standing Committee on Education
Bill Author
Bill Co-Author(s):