SB 630: Public contracts: bidders: cost overruns.
- Session Year: 2015-2016
- House: Senate
- Latest Version Date: 2015-04-21
Existing law prohibits a state agency or department, as specified, from awarding a public works or purchase contract to a bidder or contractor who has been convicted in the preceding 5 years of violating a state or federal law respecting the employment of undocumented aliens, and prohibits such bidder or contractor from being eligible to bid for or receive a public works or purchase contract.
This bill would additionally prohibit a state agency or department from awarding a public works or purchase contract to a bidder or contractor without requesting information from the bidder or contractor about cost overruns on previous public works projects or purchase contracts awarded to that bidder or contractor.
This bill would require a bidder or contractor bidding on a state public works contract to include with the bid a report of all cost overruns on public works projects or purchase contracts previously awarded by the state to that bidder or contractor.
Existing law prohibits a state agency or department, as specified, from awarding a public works or purchase contract to a bidder or contractor who has been convicted in the preceding 5 years of violating a state or federal law respecting the employment of undocumented aliens, and prohibits such bidder or contractor from being eligible to bid for or receive a public works or purchase contract.
This bill would additionally prohibit a state agency or department from awarding a public works or purchase contract to a bidder or contractor without requesting information from the bidder or contractor about cost overruns on previous public works projects or purchase contracts awarded to that bidder or contractor.
No state agency or department shall award a public works or purchase contract to a bidder or contractor without requesting information from the bidder or contractor about cost overruns on previous public works projects or purchase contracts awarded to that bidder or contractor.
6102.A bidder or contractor bidding on a state public works contract shall include with the bid a report of all cost overruns on public works projects or purchase contracts previously awarded by the state to that bidder or contractor.
No state agency or department shall award a public works or purchase contract to a bidder or contractor without requesting information from the bidder or contractor about cost overruns on previous public works projects or purchase contracts awarded to that bidder or contractor.
|
Date
|
Status
|
|---|---|
| Feb 1, 2016 | Returned to Secretary of Senate pursuant to Joint Rule 56. |
| Apr 28, 2015 | April 28 set for second hearing canceled at the request of author. |
| Apr 21, 2015 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on G.O. |
| Apr 8, 2015 | Set for hearing April 28. |
| Apr 7, 2015 | April 14 set for first hearing canceled at the request of author. |
| Mar 13, 2015 | Set for hearing April 14. |
| Mar 12, 2015 | Referred to Com. on G.O. |
| Mar 2, 2015 | Read first time. |
| Mar 2, 2015 | From printer. May be acted upon on or after April 1. |
| Feb 27, 2015 | Introduced. To Com. on RLS. for assignment. To print. |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
SB 630 (Hancock) Page 3 of 3
SENATE COMMITTEE ON GOVERNMENTAL ORGANIZATION
Senator Isadore Hall, III
Chair
2015 - 2016 Regular
Bill No: SB 630 Hearing Date: 4/28/2015
Author: |
Hancock |
||
Version: |
4/21/2015 |
||
Urgency: |
No |
Fiscal: |
Yes |
Consultant: |
Arthur Terzakis |
||
SUBJECT: Public contracts: bidders: cost overruns
DIGEST: This bill requires a contractor bidding on a state public works construction project to include with the bid a report of all cost overruns on public works projects or purchase contracts previously awarded by the state to that bidder or contractor.
ANALYSIS:
Existing law:
Establishes rules governing the awarding of contracts by state agencies, including general requirements for competitive bidding on contracts for construction projects, goods, services, and information technology.
Designates the Department of General Services (DGS) as the lead purchasing and procurement agency for the State of California and sets forth the various responsibilities of DGS and other state agencies in overseeing and implementing state contracting procedures and policies.
The State Contract Act regulates contracting between state agencies and private contractors, and outlines requirements for bidding and awarding of contracts for projects.
Contains a body of law, within the Public Contract Code, relating to contracts let by a public entity for the performance of public works of improvement, including provisions for the payment of progress payments and the disbursing and withholding of retention proceeds.
This bill adds a new provision to the Public Contract Code that requires a bidder or contractor bidding on a state public works contract to include with the bid a report of all cost overruns on public works projects or purchase contracts previously awarded by the state to that bidder or contractor.
Background
Purpose of SB 630: According to the author’s office, this measure is simply intended to require state agencies and departments to ask bidders and contractors, as part of the bidding process, to submit information about cost overruns on previous public works projects or purchase contracts that were awarded to that bidder or contractor. The author’s office believes SB 630 will help reduce future cost overruns and discourage low-ball bids by contractors.
The
author references an information technology project contract, managed
by Deloitte Consulting, which ballooned from an original bid cost of
$33 million in 2003 to $310 million by 2010 and was eventually
abandoned. Other recent cost overruns include a $250 million overrun
by SAP Public Services for overhauling the state’s payroll system
in 2013; San Francisco Bay Bridge construction costs rising to over
$6 billion; and, more than triple the projected costs for the BrEze
computer system for the Department of Consumer Affairs, rising from
$28 million to $96 million.
Prior/Related Legislation
AB 2471 (Frazier), 2013-14 Session. Among other things, would have required public entities, when additional work is needed, to issue change orders promptly, and generally not later than 60 days after the extra work is performed as long as the contractor submitted reasonable documentation to support the request for a change order. (Held in Senate Appropriations Committee)
SB 293 (Padilla), Chapter 700, Statutes of 2011. Among other things, prohibited a public entity from retaining more than 5% of a contract price until final completion and acceptance of a project, but allowed retention of higher amounts when a project is deemed “substantially complex.”
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: No
SUPPORT:
None received
OPPOSITION:
Air Conditioning Sheet Metal Association
Air-Conditioning & Refrigeration Contractors Association
American Subcontractors Association California, Inc.
Associate General Contractors
California Chapters of the National Electrical Contractors Association
California Legislative Conference of the Plumbing, Heating and Piping Industry
Construction Employers’ Association
Finishing Contractors Association of Southern California
United Contractors
ARGUMENTS IN OPPOSITION: Opponents note that the controversy surrounding information technology projects and the cost overruns associated with those projects have been well documented and that gathering additional information on those types of businesses that contract with the state makes perfect sense. However, opponents emphasize that “the construction industry functions in a completely different manner with respect to cost overruns.” Specifically, opponents point out that public works construction projects are performed in coordination and synchronization with many different parties, all of which could have an impact on the final cost of the project. This includes the owner, the engineer, the contractor, subcontractors, material suppliers and the labor force. Opponents contend that this bill “fails to distinguish between cost overruns caused by other parties such as change orders requested by project owners, flawed architectural or engineering plans, building code compliance, subcontractor failure, and labor strikes.” Furthermore, opponents believe that under SB 630, “contractors would effectively be tarnished due to the actions of any number of other parties.”