Existing law requires the Public Utilities Commission to determine appropriate targets for each load-serving entity to procure viable and cost-effective energy storage systems to be achieved by December 31, 2015, and December 31, 2020. Existing law requires the governing board of each local publicly owned electric utility to initiate a process to determine appropriate targets for the utility to procure viable cost-effective energy storage systems to be achieved by December 31, 2015, and December 31, 2020. Existing law requires the commission to adopt a process for each load-serving entity to file an integrated resource plan and a schedule for periodic updates to the plan to meet certain objectives. Existing law requires each publicly owned electric utility to prudently plan for and procure resources, including energy storage systems adequate to meet the 2015 and 2020 targets, to provide reliable electric service to its customers.
This bill would require load-serving entities, in developing and updating their integrated resource plans, to consider the benefits of procuring energy storage systems and would require the commission, in approving the plans, to require the procurement of energy storage systems before fossil-fuel-based generation in specified circumstances. The bill would require electrical corporations, by October 1, 2017, to develop appropriate tariffs or programs to provide incentives for customers to install grid-connected energy storage systems on the customer side of the electrical meter. The bill would require the commission to determine appropriate targets, if any, for each load-serving entity to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030, as specified. The bill would require the commission to require electrical corporations to offer time-of-use pricing or dynamic pricing to customers using energy storage at their premises. Because a violation of an order, decision, rule, direction, demand, or requirement of the commission is would be a crime, this bill would impose a state-mandated local program. The bill would require the governing board of each community choice aggregator, aggregator and each publicly owned electric utility, by July 1, 2018, to determine appropriate targets, if any, for the community choice aggregator or electric utility, as applicable, to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030. The bill would require the governing board of each local publicly owned electric utility, in planning for future procurement of resources, to consider the benefits of procuring energy storage systems and to procure energy storage systems before fossil-fuel-based generation in specified circumstances. The bill would require each of those governing boards, by July 1, 2018, or during its next open integrated resource plan process, to determine appropriate targets, if any, for the utility to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030. Because this bill would impose additional requirements on the governing boards of local publicly owned electric utilities and community choice aggregators, this bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for specified reasons.
Existing law requires the Public Utilities Commission to determine appropriate targets for each load-serving entity to procure viable and cost-effective energy storage systems to be achieved by December 31, 2015, and December 31, 2020. Existing law requires the governing board of each local publicly owned electric utility to initiate a process to determine appropriate targets for the utility to procure viable cost-effective energy storage systems to be achieved by December 31, 2015, and December 31, 2020. Existing law requires the commission to adopt a process for each load-serving entity to file an integrated resource plan and a schedule for periodic updates to the plan to meet certain objectives. Existing law requires each publicly owned electric utility to prudently plan for and procure resources, including energy storage systems adequate to meet the 2015 and 2020 targets, to provide reliable electric service to its customers.
This bill would require load-serving entities, in developing and updating their integrated resource plans, to consider the benefits of procuring energy storage systems and would require the commission, in approving the plans, to require the procurement of energy storage systems before fossil-fuel-based generation in specified circumstances. The bill would require electrical corporations, by October 1, 2017, to develop appropriate tariffs or programs to provide incentives to for customers to install grid-connected energy storage systems on the customer side of the electrical meter. The bill would require the commission to determine appropriate targets, if any, for each load-serving entity to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030, as specified. Because a violation of an order, decision, rule, direction, demand, or requirements requirement of a the commission is a crime, this bill would impose a state-mandated local program. The bill would require the governing board of each community choice aggregator, by July 1, 2018, to determine appropriate targets, if any, for the community choice aggregator to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030. The bill would require the governing board of each local publicly owned electric utility, in planning for future procurement of resources, to consider the benefits of procuring energy storage systems and to procure energy storage systems before fossil-fuel-based generation in specified circumstances. The bill would require the each of those governing boards, by July 1, 2018, or during its next open integrated resource plan process, to determine appropriate targets, if any, for the utility to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030. Because this bill would impose additional requirements on the governing board boards of a local publicly owned electric utility, utilities and community choice aggregators, this bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for specified reasons.
Existing law requires the Public Utilities Commission to determine appropriate targets for each load-serving entity to procure viable and cost-effective energy storage systems to be achieved by December 31, 2015, and December 31, 2020. Existing law requires the governing board of each local publicly owned electric utility to initiate a process to determine appropriate targets for the utility to procure viable cost-effective energy storage systems to be achieved by December 31, 2015, and December 31, 2020. Existing law requires the commission to adopt a process for each load-serving entity to file an integrated resource plan and a schedule for periodic updates to the plan to meet certain objectives. Existing law requires each publicly owned electric utility to prudently plan for and procure resources, including energy storage systems adequate to meet the 2015 and 2020 targets, to provide reliable electric service to its customers.
This bill would require load-serving entities, in developing and updating their integrated resource plans, to consider the full benefits of procuring energy storage systems and would require the commission, in approving the plans, to require the procurement of energy storage systems before fossil-fuel-based generation in specified circumstances. The bill would require electrical corporations, by October 1, 2017, to develop appropriate tariffs or programs to provide incentives to customers to install grid-connected energy storage systems on the customer side of the electrical meter. The bill would require the commission to adopt determine appropriate targets targets, if any, for each load-serving entity to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030, as specified. Because a violation of an order, decision, rule, direction, demand, or requirements of a commission is a crime, this bill would impose a state-mandated local program. The bill would require the governing board of each local publicly owned electric utility, in planning for future procurement of resources, to consider the benefits of procuring energy storage systems and to procure energy storage systems before fossil-fuel-based generation in specified circumstances. The bill would require the governing boards, by July 1, 2018, to adopt determine appropriate targets targets, if any, for the utility to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030. Because this bill would impose additional requirements on the governing board of a local publicly owned electric utility, this bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for specified reasons.
Existing law requires the Public Utilities Commission to determine appropriate targets for each load-serving entity to procure viable and cost-effective energy storage systems to be achieved by December 31, 2015, and December 31, 2020. Existing law requires the governing board of each local publicly owned electric utility to initiate a process to determine appropriate targets for the utility to procure viable cost-effective energy storage systems to be achieved by December 31, 2015, and December 31, 2020. Existing law requires the commission to adopt a process for each load-serving entity to file an integrated resource plan and a schedule for periodic updates to the plan to meet certain objectives. Existing law requires each publicly owned electric utility to prudently plan for and procure resources, including energy storage systems adequate to meet the 2015 and 2020 targets, to provide reliable electric service to its customers.
This bill would require the commission, by March 1, 2017, to require load-serving entities, in developing and updating their integrated resource plans, to consider the full benefits of procuring energy storage systems and to give priority to procuring would require the commission, in approving the plans, to require the procurement of energy storage systems over before fossil-fuel-based generation. generation in specified circumstances. The bill would require the commission on or before October 1, 2017, to require electrical corporations corporations, by October 1, 2017, to develop appropriate tariffs or programs to provide incentives to customers to install grid-connected energy storage systems on the customer side of the electrical meter. The bill would require the commission to adopt appropriate targets for each load-serving entity to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030, as specified. Because a violation of an order, decision, rule, direction, demand, or requirements of a commission is a crime, this bill would impose a state-mandated local program. The bill would require the governing board of each local publicly owned electric utility, in planning for future procurement of resources, to consider the benefits of procuring energy storage systems and to give priority to procuring procure energy storage systems over before fossil-fuel-based generation. generation in specified circumstances. The bill would require the governing boards, by July 1, 2018, to adopt appropriate targets for the utility to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030. Because this bill would impose additional requirements on the governing board of a local publicly owned electric utility, this bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for specified reasons.
Existing law requires the Public Utilities Commission to determine appropriate targets for each load-serving entity to procure viable and cost-effective energy storage systems to be achieved by December 31, 2015, and December 31, 2020. Existing law requires the governing board of each local publicly owned electric utility to initiate a process to determine appropriate targets for the utility to procure viable cost-effective energy storage systems to be achieved by December 31, 2015, and December 31, 2020. Existing law requires the commission to adopt a process for each load-serving entity to file an integrated resource plan and a schedule for periodic updates to the plan to meet certain objectives. Existing law requires each publicly owned electric utility to prudently plan for and procure resources, including energy storage systems adequate to meet the 2015 and 2020 targets, to provide reliable electric service to its customers.
This bill would require the commission, by March 1, 2017, to require load-serving entities, in developing and updating their integrated resource plans, to consider the benefits of procuring energy storage systems and to give priority to procuring energy storage systems over fossil-fuel-based generation. The bill would require the commission on or before October 1, 2017, to require electrical corporations to develop appropriate tariffs to provide incentives to customers to install grid-connected energy storage systems on the customer side of the electrical meter. Because a violation of an order, decision, rule, direction, demand, or requirements of a commission is a crime, this bill would impose a state-mandated local program. The bill would require the governing board of each local publicly owned electric utility, in planning for future procurement of resources, to consider the benefits of procuring energy storage systems and to give priority to procuring energy storage systems over fossil-fuel-based generation. Because this bill would impose additional requirements on the governing board of a local publicly owned electric utility, this bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for specified reasons.
(1)Under existing law, the Division of Oil, Gas, and Geothermal Resources in the Department of Conservation regulates the drilling, operation, maintenance, and abandonment of oil and gas wells in the state. Existing law requires the State Oil and Gas Supervisor to supervise the drilling, operation, maintenance, and abandonment of wells and the operation, maintenance, and removal or abandonment of tanks and facilities related to oil and gas production within an oil and gas field, so as to prevent damage to life, health, property, and natural resources, as provided; to permit owners and operators of wells to utilize all known methods and practices to increase the ultimate recovery of hydrocarbons; and to perform the supervisors duties in a manner that encourages the wise development of oil and gas resources to best meet oil and gas needs in this state. Under existing law, a person who fails to comply with certain requirements relating to the regulation of oil or gas operations is guilty of a misdemeanor.
This bill would require the supervisor to immediately institute a moratorium on injections of natural gas into any wells located within and serving the Aliso Canyon storage facility located in the County of Los Angeles until specified conditions are met. The bill would also require the supervisor to prohibit the production of natural gas by any well originally drilled earlier than 1954 at the Aliso Canyon storage facility located in the County of Los Angeles until specified conditions are met, except as specified. Because a violation of these requirements would be a crime, the bill would impose a state-mandated local program.
(2)Under existing law, the Public Utilities Commission is authorized to supervise and regulate every public utility in the state.
This bill would require the commission to determine the feasibility of minimizing or eliminating use of the Aliso Canyon natural gas storage facility located in the County of Los Angeles while still maintaining energy reliability for the region, and to consult with specified entities in making its determination.
(3)The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
(4)This bill would declare that it is to take effect immediately as an urgency statute.
(1)Under existing law, the Division of Oil, Gas, and Geothermal Resources in the Department of Conservation regulates the drilling, operation, maintenance, and abandonment of oil and gas wells in the state. Existing law requires the State Oil and Gas Supervisor to supervise the drilling, operation, maintenance, and abandonment of wells and the operation, maintenance, and removal or abandonment of tanks and facilities related to oil and gas production within an oil and gas field, so as to prevent damage to life, health, property, and natural resources, as provided; to permit owners and operators of wells to utilize all known methods and practices to increase the ultimate recovery of hydrocarbons; and to perform the supervisors duties in a manner that encourages the wise development of oil and gas resources to best meet oil and gas needs in this state. Under existing law, a person who fails to comply with certain requirements relating to the regulation of oil or gas operations is guilty of a misdemeanor.
This bill would require the supervisor to immediately institute a moratorium on injections of natural gas into any wells located within and serving the Aliso Canyon storage facility located in the County of Los Angeles until specified conditions are met. The bill would also require the supervisor to prohibit the production of natural gas by any well originally drilled earlier than 1954 at the Aliso Canyon storage facility located in the County of Los Angeles until specified conditions are met, except as specified. Because a violation of these requirements would be a crime, the bill would impose a state-mandated local program.
(2)Under existing law, the Public Utilities Commission is authorized to supervise and regulate every public utility in the state.
This bill would require the commission to determine the feasibility of minimizing or eliminating use of the Aliso Canyon natural gas storage facility located in the County of Los Angeles while still maintaining energy reliability for the region, and to consult with specified entities in making its determination.
(3)The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
(4)This bill would declare that it is to take effect immediately as an urgency statute.
(a)The commission shall require load-serving entities, in developing and updating their integrated resource plans pursuant to Section 454.52, to consider the benefits of procuring energy storage systems, as defined in Section 2835.
(b)Except as provided in subdivision (c), the commission, in approving an integrated resource plan for a load-serving entity shall require that, to the extent energy storage systems can meet resource needs as well as or better than fossil-fuel-based generation at reasonably equivalent or lower cost, the plan provide for the procurement of energy storage systems before fossil-fuel-based generation.
(c)In certifying an integrated resource plan for a community choice aggregator, the commission shall act in accordance with paragraph (3) of subdivision (b) of Section 454.52 and paragraph (5) of subdivision (a) of Section 366.2.
SEC. 2.SECTION 1.Section 455.6 is added to the Public Utilities Code, to read:455.6.The commission shall, in a new or existing proceeding, shall require each electrical corporation, by October 1, 2017, to propose new tariffs or programs to provide incentives to customers of the electrical corporation for installing corporation to offer time-of-use pricing or dynamic pricing to customers using energy storage systems on the customer side of an electric meter that is connected to the electrical grid. at their premises.
SEC. 3.SEC. 2.Section 2836.1 is added to the Public Utilities Code, to read:2836.1.(a)(1)Except as provided in subdivision (b), on or before January 1, 2018, the commission shall determine appropriate targets, if any, for each load-serving entity to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030. Energy storage systems procured pursuant to the targets shall be limited to those that reduce the need for fossil-fuel-based generation, provide benefits to the electrical grid, or support the integration of eligible renewable energy resources procured pursuant to the California Renewables Portfolio Standard Program (Article 16 (commencing with Section 399.11) of Chapter 2.3 of Part 1).
(2)This subdivision does not prohibit the commissions evaluation and approval of any application for funding or recovery for costs of any ongoing or new development, trial, or testing of energy storage projects or technologies outside the targets required by this chapter.
(b)On or before July 1, 2018, the governing board of each community choice aggregator shall determine appropriate targets, if any, for the community choice aggregator to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030. The governing board may consider a variety of policies to encourage cost-effective deployment of energy storage systems to reach the targets, including refinement of existing procurement methods to properly value energy storage systems.
(c)On or before July 1, 2018, or during its next open integrated resource plan process, the governing board of each local publicly owned electric utility shall determine appropriate targets, if any, for the utility to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030. The governing board may consider a variety of policies to encourage the cost-effective deployment of energy storage systems to reach the targets, including refinement of existing procurement methods to properly value energy storage systems.
SEC. 4.SEC. 3.Section 9620.5 is added to the Public Utilities Code, to read:9620.5.The governing board of each local publicly owned electric utility, in planning for future procurement of resources, shall consider the benefits of procuring energy storage systems, as defined in Section 2835, and, to the extent energy storage systems can meet resource needs as well as or better than fossil-fuel-based generation at reasonably equivalent or lower costs, procure energy storage systems before fossil-fuel-based generation.
SEC. 5.SEC. 4.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act or because costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
(a)The commission shall require load-serving entities, in developing and updating their integrated resource plans pursuant to Section 454.52, to consider the benefits of procuring energy storage systems, as defined in Section 2835. In approving an integrated resource plan, the commission shall require that, to the extent energy storage systems can meet resource needs as well as or better than fossil-fuel-based generation at reasonably equivalent or lower costs, the plans provide for the procurement of energy storage systems before fossil-fuel-based generation.
(b)Except as provided in subdivision (c), the commission, in approving an integrated resource plan for a load-serving entity shall require that, to the extent energy storage systems can meet resource needs as well as or better than fossil-fuel-based generation at reasonably equivalent or lower cost, the plan provide for the procurement of energy storage systems before fossil-fuel-based generation.
(c)In certifying an integrated resource plan for a community choice aggregator, the commission shall act in accordance with paragraph (3) of subdivision (b) of Section 454.52 and paragraph (5) of subdivision (a) of Section 366.2.
SEC. 2.Section 455.6 is added to the Public Utilities Code, to read:455.6.The commission shall, in a new or existing proceeding, require each electrical corporation, by October 1, 2017, to propose new tariffs or programs to provide incentives to customers of the electrical corporation for installing energy storage systems on the customer side of an electric meter that is connected to the electrical grid.
SEC. 3.Section 2836.1 is added to the Public Utilities Code, to read:2836.1.(a)(1)On Except as provided in subdivision (b), on or before January 1, 2018, the commission shall determine appropriate targets, if any, for each load-serving entity to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030. Energy storage systems procured pursuant to the targets shall be limited to those that reduce the need for fossil-fuel-based generation, provide benefits to the electrical grid, or support the integration of eligible renewable energy resources procured pursuant to the California Renewables Portfolio Standard Program (Article 16 (commencing with Section 399.11) of Chapter 2.3 of Part 1).
(2)This subdivision does not prohibit the commissions evaluation and approval of any application for funding or recovery for costs of any ongoing or new development, trial, or testing of energy storage projects or technologies outside the targets required by this chapter.
(b)On or before July 1, 2018, the governing board of each community choice aggregator shall determine appropriate targets, if any, for the community choice aggregator to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030. The governing board may consider a variety of policies to encourage cost-effective deployment of energy storage systems to reach the targets, including refinement of existing procurement methods to properly value energy storage systems.
(b)
(c)On or before July 1, 2018, or during its next open integrated resource plan process, the governing board of each local publicly owned electric utility shall determine appropriate targets, if any, for the utility to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030. The governing board may consider a variety of policies to encourage the cost-effective deployment of energy storage systems to reach the targets, including refinement of existing procurement methods to properly value energy storage systems.
SEC. 4.Section 9620.5 is added to the Public Utilities Code, to read:9620.5.The governing board of each local publicly owned electric utility, in planning for future procurement of resources, shall consider the benefits of procuring energy storage systems, as defined in Section 2835, and, to the extent energy storage systems can meet resource needs as well as or better than fossil-fuel-based generation at reasonably equivalent or lower costs, procure energy storage systems before fossil-fuel-based generation.
SEC. 5.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act or because costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
The commission shall require load-serving entities, in developing and updating their integrated resource plans pursuant to Section 454.52, to consider the full benefits of procuring energy storage systems, as defined in Section 2835. In approving an integrated resource plan, the commission shall require that, to the extent energy storage systems can meet resource needs as well as or better than fossil-fuel-based generation at reasonably equivalent or lower costs, the plans provide for the procurement of energy storage systems before fossil-fuel-based generation.
SEC. 2.Section 455.6 is added to the Public Utilities Code, to read:455.6.The commission shall, in a new or existing proceeding, require each electrical corporation, by October 1, 2017, to propose new tariffs or programs to provide incentives to customers of the electrical corporation for installing energy storage systems on the customer side of an electric meter that is connected to the electrical grid.
SEC. 3.Section 2836.1 is added to the Public Utilities Code, to read:2836.1.(a)(1)On or before January 1, 2018, the commission shall adopt determine appropriate targets targets, if any, for each load-serving entity to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030. Energy storage systems procured pursuant to the targets shall be limited to those that reduce the need for fossil-fuel-based generation, provide benefits to the electrical grid, or support the integration of eligible renewable energy resources procured pursuant to the California Renewables Portfolio Standard Program (Article 16 (commencing with Section 399.11) of Chapter 2.3 of Part 1).
(2)This subdivision does not prohibit the commissions evaluation and approval of any application for funding or recovery for costs of any ongoing or new development, trial, or testing of energy storage projects or technologies outside the targets required by this chapter.
(b)On or before July 1, 2018, the governing board of each local publicly owned electric utility shall adopt determine appropriate targets targets, if any, for the utility to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030. The governing board may consider a variety of policies to encourage the cost-effective deployment of energy storage systems to reach the targets, including refinement of existing procurement methods to properly value energy storage systems.
SEC. 4.Section 9620.5 is added to the Public Utilities Code, to read:9620.5.The governing board of each local publicly owned electric utility, in planning for future procurement of resources, shall consider the benefits of procuring energy storage systems, as defined in Section 2835, and, to the extent energy storage systems can meet resource needs as well as or better than fossil-fuel-based generation at reasonably equivalent or lower costs, procure energy storage systems before fossil-fuel-based generation.
SEC. 5.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act or because costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
On or before March 1, 2017, the commission shall, in a new proceeding or in an existing proceeding, require load-serving entities, in developing and updating their integrated resource plans as required by Section 454.52, to consider the benefits of procuring energy storage systems, as defined in Section 2835, and to give priority to procuring energy storage systems over fossil-fuel-based generation.
SEC. 2.Section 455.6 is added to the Public Utilities Code, to read:455.6.On or before October 1, 2017, the commission shall, in a new proceeding or in an existing proceeding, require each electrical corporation to develop appropriate tariffs to provide incentives to customers of the electrical corporation to install energy storage systems on the customer side of an electric meter that is connected to the electric grid.
SECTION 1.Section 454.53 is added to the Public Utilities Code, to read:454.53.The commission shall require load-serving entities, in developing and updating their integrated resource plans pursuant to Section 454.52, to consider the full benefits of procuring energy storage systems, as defined in Section 2835. In approving an integrated resource plan, the commission shall require that, to the extent energy storage systems can meet resource needs as well as or better than fossil-fuel-based generation at reasonably equivalent or lower costs, the plans provide for the procurement of energy storage systems before fossil-fuel-based generation.
SEC. 2.Section 455.6 is added to the Public Utilities Code, to read:455.6.The commission shall, in a new or existing proceeding, require each electrical corporation, by October 1, 2017, to propose new tariffs or programs to provide incentives to customers of the electrical corporation for installing energy storage systems on the customer side of an electric meter that is connected to the electrical grid.
SEC. 3.Section 2836.1 is added to the Public Utilities Code, to read:2836.1.(a)(1)On or before January 1, 2018, the commission shall adopt appropriate targets for each load-serving entity to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030. Energy storage systems procured pursuant to the targets shall be limited to those that reduce the need for fossil-fuel-based generation, provide benefits to the electrical grid, or support the integration of eligible renewable energy resources procured pursuant to the California Renewables Portfolio Standard Program (Article 16 (commencing with Section 399.11) of Chapter 2.3 of Part 1).
(2)This subdivision does not prohibit the commissions evaluation and approval of any application for funding or recovery for costs of any ongoing or new development, trial, or testing of energy storage projects or technologies outside the targets required by this chapter.
(b)On or before July 1, 2018, the governing board of each local publicly owned electric utility shall adopt appropriate targets for the utility to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030. The governing board may consider a variety of policies to encourage the cost-effective deployment of energy storage systems to reach the targets, including refinement of existing procurement methods to properly value energy storage systems.
SEC. 3.SEC. 4.Section 9620.5 is added to the Public Utilities Code, to read:9620.5.The governing board of each local publicly owned electric utility, in planning for future procurement of resources, shall consider the benefits of procuring energy storage systems, as defined in Section 2835, and shall give priority to procuring energy storage systems over fossil-fuel-based generation. and, to the extent energy storage systems can meet resource needs as well as or better than fossil-fuel-based generation at reasonably equivalent or lower costs, procure energy storage systems before fossil-fuel-based generation.
SEC. 4.SEC. 5.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act or because costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
On or before March 1, 2017, the commission shall, in a new proceeding or in an existing proceeding, require load-serving entities, in developing and updating their integrated resource plans as required by Section 454.52, to consider the benefits of procuring energy storage systems, as defined in Section 2835, and to give priority to procuring energy storage systems over fossil-fuel-based generation.
SEC. 2.Section 455.6 is added to the Public Utilities Code, to read:455.6.On or before October 1, 2017, the commission shall, in a new proceeding or in an existing proceeding, require each electrical corporation to develop appropriate tariffs to provide incentives to customers of the electrical corporation to install energy storage systems on the customer side of an electric meter that is connected to the electric grid.
SEC. 3.Section 9620.5 is added to the Public Utilities Code, to read:9620.5.The governing board of each local publicly owned electric utility, in planning for future procurement of resources, shall consider the benefits of procuring energy storage systems, as defined in Section 2835, and shall give priority to procuring energy storage systems over fossil-fuel-based generation.
SEC. 4.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act or because costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
SECTION 1.Section 3217 is added to the Public Resources Code, to read:3217.(a)The supervisor shall immediately institute a moratorium on injections of natural gas into any wells located within and serving the Aliso Canyon storage facility located in the County of Los Angeles until all of the following conditions are met:
(1)The integrity of each well has been quantitatively and objectively evaluated using state-of-art technology and the risks posed by well failure have been evaluated.
(A)The age, history, and condition of each well shall be specifically addressed, with particular emphasis on wells drilled prior to 2006.
(B)The technical methods and equipment used to evaluate well integrity and the risks posed by well failure shall be determined by the supervisor with input from independent experts and the public through a public process.
(2)Any well posing an enhanced risk of failure has been repaired to mitigate the enhanced risk or plugged and abandoned.
(3)The supervisor determines that the overall risk from well failure satisfies the supervisors duty pursuant to Section 3106 to prevent damage to life, health, property, and natural resources and other requirements.
(4)The Public Utilities Commission and the State Energy Resources Conservation and Development Commission concur with the supervisors determination in paragraph (3).
(b)The supervisor shall prohibit the production of natural gas by any well originally drilled earlier than 1954 at the Aliso Canyon storage facility located in the County of Los Angeles until after the integrity of and the risks associated with any of these wells have been evaluated and determinations by the supervisor, with the concurrence of the commissions, have been made pursuant to the process described in subdivision (a), except when necessary to do either of the following:
(1)Respond to the uncontrolled leak of natural gas from the Standard Sesnon 25 well (American Petroleum Institute identification number 03700776).
(2)Maintain regional energy reliability, at the written direction of the commissions.
SEC. 2.Section 713 is added to the Public Utilities Code, to read:713.The commission shall determine the feasibility of minimizing or eliminating use of the Aliso Canyon natural gas storage facility located in the County of Los Angeles while still maintaining energy reliability for the region. The commission shall consult with the State Energy Resources Conservation and Development Commission, the Independent System Operator, the Division of Oil, Gas, and Geothermal Resources in the Department of Conservation, and other relevant government entities, in making its determination.
SEC. 3.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
SEC. 4.This act is an urgency statute necessary for the immediate preservation of the public peace, health, or safety within the meaning of Article IV of the Constitution and shall go into immediate effect. The facts constituting the necessity are:
In order to mitigate, at the earliest possible time, ongoing harm from the gas leak at the Aliso Canyon storage facility, and to evaluate the integrity of and the risks associated with older wells at that facility, it is necessary that this act take effect immediately.
(a)The supervisor shall immediately institute a moratorium on injections of natural gas into any wells located within and serving the Aliso Canyon storage facility located in the County of Los Angeles until all of the following conditions are met:
(1)The integrity of each well has been quantitatively and objectively evaluated using state-of-art technology and the risks posed by well failure have been evaluated.
(A)The age, history, and condition of each well shall be specifically addressed, with particular emphasis on wells drilled prior to 2006.
(B)The technical methods and equipment used to evaluate well integrity and the risks posed by well failure shall be determined by the supervisor with input from independent experts and the public through a public process.
(2)Any well posing an enhanced risk of failure has been repaired to mitigate the enhanced risk or plugged and abandoned.
(3)The supervisor determines that the overall risk from well failure satisfies the supervisors duty pursuant to Section 3106 to prevent damage to life, health, property, and natural resources and other requirements.
(4)The Public Utilities Commission and the State Energy Resources Conservation and Development Commission concur with the supervisors determination in paragraph (3).
(b)The supervisor shall prohibit the production of natural gas by any well originally drilled earlier than 1954 at the Aliso Canyon storage facility located in the County of Los Angeles until after the integrity of and the risks associated with any of these wells have been evaluated and determinations by the supervisor, with the concurrence of the commissions, have been made pursuant to the process described in subdivision (a), except when necessary to do either of the following:
(1)Respond to the uncontrolled leak of natural gas from the Standard Sesnon 25 well (American Petroleum Institute identification number 03700776).
(2)Maintain regional energy reliability, at the written direction of the commissions.
SEC. 2.Section 713 is added to the Public Utilities Code, to read:713.The commission shall determine the feasibility of minimizing or eliminating use of the Aliso Canyon natural gas storage facility located in the County of Los Angeles while still maintaining energy reliability for the region. The commission shall consult with the State Energy Resources Conservation and Development Commission, the Independent System Operator, the Division of Oil, Gas, and Geothermal Resources in the Department of Conservation, and other relevant government entities, in making its determination.
SEC. 3.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
SEC. 4.This act is an urgency statute necessary for the immediate preservation of the public peace, health, or safety within the meaning of Article IV of the Constitution and shall go into immediate effect. The facts constituting the necessity are:
In order to mitigate, at the earliest possible time, ongoing harm from the gas leak at the Aliso Canyon storage facility, and to evaluate the integrity of and the risks associated with older wells at that facility, it is necessary that this act take effect immediately.
|
Date
|
Status
|
|---|---|
| Aug 11, 2016 | August 11 hearing. Held in committee and under submission. |
| Aug 11, 2016 | Joint Rule 62(a) suspended. |
| Aug 10, 2016 | August 10 set for first hearing. Placed on APPR. suspense file. |
| Aug 1, 2016 | Read second time and amended. Re-referred to Com. on APPR. |
| Jun 30, 2016 | From committee: Do pass as amended and re-refer to Com. on APPR. (Ayes 10. Noes 4.) (June 29). |
| Jun 9, 2016 | Referred to Com. on U. & C. |
| Jun 2, 2016 | In Assembly. Read first time. Held at Desk. |
| Jun 1, 2016 | Read third time. Passed. (Ayes 25. Noes 14. Page 4090.) Ordered to the Assembly. |
| Jun 1, 2016 | Read third time. Passed. (Ayes 25. Noes 14.) Ordered to the Assembly. |
| May 31, 2016 | Read second time and amended. Ordered to third reading. |
| May 27, 2016 | From committee: Do pass as amended. (Ayes 5. Noes 2. Page 3999.) (May 27). |
| May 27, 2016 | From committee: Do pass as amended. (Ayes 5. Noes 2.) (May 27). |
| May 24, 2016 | Set for hearing May 27. |
| May 23, 2016 | May 23 hearing: Placed on APPR. suspense file. (Ayes 7. Noes 0.) |
| May 13, 2016 | Set for hearing May 23. |
| May 12, 2016 | May 16 hearing postponed by committee. |
| May 6, 2016 | Set for hearing May 16. |
| Apr 26, 2016 | Read second time and amended. Re-referred to Com. on APPR. |
| Apr 25, 2016 | From committee: Do pass as amended and re-refer to Com. on APPR. (Ayes 8. Noes 3. Page 3593.) (April 19). |
| Apr 25, 2016 | From committee: Do pass as amended and re-refer to Com. on APPR. (Ayes 8. Noes 3.) (April 19). |
| Apr 12, 2016 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on E., U., & C. |
| Apr 1, 2016 | Set for hearing April 19. |
| Mar 31, 2016 | Re-referred to Com. on E., U., & C. |
| Mar 28, 2016 | Re-referred to Com. on RLS. |
| Mar 28, 2016 | Withdrawn from committee. |
| Mar 17, 2016 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on N.R. & W. |
| Jan 28, 2016 | Referred to Coms. on N.R. & W. and E., U., & C. |
| Jan 21, 2016 | From printer. May be acted upon on or after February 20. |
| Jan 20, 2016 | Introduced. Read first time. To Com. on RLS. for assignment. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Jun 29, 2016 | Do pass as amended and be re-referred to the Committee on [Appropriations] | Assembly Standing Committee on Utilities and Commerce |
Passed |
|
| Jun 1, 2016 | Senate 3rd Reading SB886 Pavley | Senate Floor |
Passed |
|
| May 27, 2016 | Do pass as amended | Senate Standing Committee on Appropriations |
Passed |
|
| May 23, 2016 | Placed on suspense file | Senate Standing Committee on Appropriations |
Passed |
|
| Apr 19, 2016 | Do pass as amended, but first amend, and re-refer to the Committee on [Appropriations] | Senate Standing Committee on Energy, Utilities and Communications |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
Date of Hearing: August 10, 2016
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Lorena Gonzalez, Chair
SBPCA Bill Id:SB 886
Author:(Pavley) – As Amended Ver:August 1, 2016
Policy Committee: | Utilities and Commerce | Vote: | 10 - 4 |
Urgency: No State Mandated Local Program: Yes Reimbursable: No
SUMMARY:
This bill requires the California Public Utilities Commission (PUC) to require each electrical corporation to offer time-of-use pricing or dynamic pricing to customers using energy storage at their premises. Additionally, this bill requires electricity providers to adopt energy storage procurement targets. Specifically, this bill:
- Requires the PUC, by January 1, 2018, to determine appropriate energy storage system procurement targets, if any, for each load-serving entity (LSE), to be achieved by December 31, 2030.
- Requires the governing board of each community choice aggregator (CCA) and each local publicly owned electrical utility (POU), by July 1, 2018, to determine appropriate energy storage procurement targets, if any, to be achieved by December 31, 2030. The respective governing boards may consider a variety of policies to encourage the cost-effective deployment of energy storage systems to reach the targets, including refinement of existing procurement methods to properly value storage systems.
- Requires the governing board of each POU, in planning for future procurement of resources, to consider the benefits of procuring energy storage systems and to procure comparably priced, equally effective energy storage systems before fossil-fuel-based generation.
FISCAL EFFECT:
Increased ongoing annual PUC costs of approximately $420,000 (Public Utilities Reimbursement Fund) to receive and evaluate TOU tariffs through a new or existing rate-setting proceeding and determine targets, if any are adopted, through a new or existing policy setting proceeding.
COMMENTS:
- Purpose. According to the author, the Aliso Canyon natural gas leak highlighted the states dependence on fossil fuels, and natural gas storage. This bill is intended to prevent this kind of problem from ever happening again through the diversification of our energy storage resources. The author further states, this bill asks utilities to consider energy storage systems ahead of fossil fuels in their planning process and asks the PUC to create an energy storage rate, which would send the right economic signal to businesses and homeowners that will enable them to take control of their energy future and save money on their energy bills.
- Background. Existing law directs the California Energy Commission (CEC) and the PUC to authorize the procurement of resources to provide grid reliability services that minimize reliance on system power and fossil fuel resources and, where feasible, increase the use of large- and small-scale energy storage. The PUC is required to determine appropriate targets, if any, for LSEs to procure energy storage systems and requires LSEs to meet any targets adopted by the PUC by 2015 and 2020. POUs are required to set their own targets and meet those targets by 2016 and 2021.
The general category of Time-of-Use (TOU) rates for electricity customers often refers to prices set in advance but varying over the day to capture expected impacts of changing electricity use. Generally, electricity rates are higher during pre-determined peak usage times and lower during off usage times.
Dynamic pricing, also referred to as surge pricing or demand pricing, is a pricing strategy in which businesses set flexible prices for products or services based on current market demands. With dynamic electricity pricing, rates vary by actual demand.
Current law provides funding for energy storage through the Self-Generation Incentives program. In addition, certain energy storage facilities are eligible to receive bill credits through the existing Net Energy Metering Programs. The PUC has also directed utilities to procure energy storage through both direct procurement and through "all-source" bids (where any energy resource may bid to provide electricity services).
The California Independent System Operator recently initiated a request for approval from the Federal Energy Regulatory Commission (FERC) to provide payments for energy storage that can assist with the reliability operation of the grid. In addition, the PUC recently authorized additional energy procurement to begin immediately to assist in addressing reliability problems that may occur as a result of the Aliso Canyon gas storage facility leak.
- Other Efforts to Reduce Methane Emissions. The PUC, as part of the Leak Abatement Order Instituting Rulemaking pursuant to SB 1371 (Leno, Chapter 525, Statutes of 2014) is aand in a cost-effective manner
Analysis Prepared by: Jennifer Galehouse / APPR. / (916) 319-2081
Date of Hearing: June 29, 2016
ASSEMBLY COMMITTEE ON UTILITIES AND COMMERCE
Mike Gatto, Chair
SBPCA Bill Id:SB 886
Author:(Pavley) – As Amended Ver:May 31, 2016
SENATE VOTE: 25-14
SUBJECT: Electricity: energy storage systems
SUMMARY: Requires the California Public Utilities Commission (CPUC) to adopt energy storage system procurement targets applicable to electrical corporations, community choice aggregators, and the governing board of each local publicly-owned electric utility (POU) to adopt comparable energy storage procurement targets; requires each load-serving entity and locally owned public electric utility to plan for the procurement of energy storage systems before fossil-fuel-based generation; and requires each electrical corporation to propose measures to encourage customers to install energy storage systems. Specifically, this bill:
- Requires the CPUC to adopt, by January 1, 2018, energy storage system procurement targets applicable to each load-serving entity (LSE), to be achieved by December 1, 2030.
- Directs the CPUC to require each investor-owned utility (IOU), by January 1, 2017, to propose new tariffs or programs to encourage customers to install energy storage systems on the customer side of the meter.
- Requires the CPUC, by March 1, 2017, to require each LSE, in developing its integrated resource plan (IRP), to consider the full benefits of procuring energy storage systems; requires the CPUC, in approving an LSE's IRP, to require the IRP to provide for the procurement of comparably priced, equally effective energy storage systems before fossil-fuel-based generation.
- Requires the governing board of each POU, in planning for future procurement of resources, to consider the benefits of procuring energy storage systems and to procure comparably priced, equally effective energy storage systems before fossil-fuel-based generation.
EXISTING LAW:
- Allows the CPUC to collect up to $83 million annually until December 31, 2019, and use these funds to provide incentives for for distributed energy resources, including energy storage systems, until January 1, 2021. (Public Utilities Code Section 379.6)
- Defines "LSE" as an electrical corporation (IOU), energy service providers (ESP) or community choice aggregators (CCA). (Public Utilities Code Section 380(k))
- Requires each LSE and local POU to increase purchases of renewable energy such that at least 50% of retail sales are procured from renewable energy resources by December 31, 2030. This is known as the Renewable Portfolio Standard (RPS). (Public Utilities Code Section 399.11 et seq.)
- Requires the CPUC to: a) identify a diverse and balanced portfolio of resources needed to ensure a reliable electricity supply that provides optimal integration of renewable energy in a cost-effective manner. The portfolio shall rely upon zero carbon-emitting resources to the maximum extent reasonable and be designed to achieve any statewide greenhouse gas emissions limit established pursuant to the California Global Warming Solutions Act of 2006; b) direct each electrical corporation to include, as part of its proposed procurement plan, a strategy for procuring best-fit and least-cost resources to satisfy the portfolio needs identified by the CPUC; and c) ensure that the net costs of any incremental renewable energy integration resources procured by an electrical corporation to satisfy the need identified by the CPUC . (Public Utilities Code Section 454.51)
- Requires the CPUC to adopt a process for each IOU to file an IRP to ensure IOUs meet the greenhouse gas (GHG) emissions reduction targets for the electricity sector; procure at least 50% eligible renewable energy resources by December 31, 2030; enable each IOU to fulfill its obligation to serve its customers at just and reasonable rates; minimize impacts on ratepayers' bills; ensure system and local reliability; strengthen the diversity, sustainability, and resilience of the bulk transmission and distribution systems, and local communities; enhance distribution systems and demand-side energy management; and minimize localized air pollutants and other GHG emissions, with early priority on disadvantaged communities. (Public Resources Code Section 454.52)
- Requires each POU to adopt and regularly update an IRP substantially similar required of the IRPs developed by LSEs, to be reviewed by the California Energy Commission (CEC). (Public Utilities Code Section 9321)
- Directs the CEC and the CPUC, where feasible, to authorize procurement of resources to provide grid reliability services that minimize reliance on system power and fossil fuel resources and, where feasible, cost effective, and consistent with other state policy objectives, increase the use of large- and small-scale energy storage. (Public Utilities Code Section 400)
- Requires the CPUC to determine appropriate targets, if any, for LSEs to procure energy storage systems. Requires LSEs to meet any targets adopted by the CPUC by 2015 and 2020. Requires POUs to set their own targets for the procurement of energy storage and then meet those targets by 2016 and 2021. (Public Utilities Code Section 2835 et seq.)
FISCAL EFFECT: Unknown.
COMMENTS:
- Author's Statement. "The Southern California Gas Company Aliso Canyon Disaster highlighted the states dangerous dependence on fossil fuels, and natural gas storage. The Disaster forced the displacement of thousands of families from their homes—many of whom remain in temporary housing—resulted in the largest single emission of methane gas (the equivalent in climate pollution to burning roughly a billion gallons of gasoline) in our country’s history, and has left 21 million people in the southland vulnerable this summer and winter to blackouts. SB 886 seeks a simple solution to prevent this kind of problem from ever happening again: diversification of our energy storage resources. The bill asks that utilities consider energy storage systems ahead of fossil fuels in their planning process, and that the CPUC consider updating its energy storage procurement target for the utilities. It also asks the CPUC to create an energy storage rate, which would send the right economic signal to consumers—businesses and homeowners—that will enable them to take control of their energy future and save money on their energy bills."
- Integrated Resource Planning: In 2015, SB 350 (De León), Chapter 547, Statutes of 2015, was enacted to increase the state's commitment to lowering greenhouse gas emissions, clean electric generation, energy efficiency, and transportation electrification. Included in the final version of the bill was a requirement for the CPUC and local POUs to prepare IRP. The CPUC is currently working on implementing the provision of this requirement.
According to the CPUC the integrated planning process considers the costs and benefits of both demand and supply side resources when developing the least total cost mix of utility resource options. Establishing a "carve out" in the IRPs for energy storage undermines the CPUC and utilities effort to find the least total cost mix of resource options. Instead it puts energy storage ahead of what might be one or more "least cost" solutions to meeting the requirement in statute with respect to lowering greenhouse gas emissions.
The author may wish to consider striking this provision in the bill.
- Energy Storage Incentives: Current law provides funding for energy storage through the Self-Generation Incentives program. In addition, certain energy storage facilities are eligible to receive bill credits through the existing Net Energy Metering Programs. The CPUC has also directed utilities to procure energy storage through both direct procurement and through "all-source" bids (where any energy resource may bid to provide electricity services). The California Independent System Operator recently initiated a request for approval from the Federal Energy Regulatory Commission (FERC) to provide payments for energy storage that can assist with the reliability operation of the grid.[1] In addition, the CPUC recently authorized additional energy procurement to begin immediately to assist in addressing reliability problems that may occur as a result of the Aliso Canyon gas storage facility leak.
The author may wish to consider alternative language to encourage electrical corporations to offer rate plans, based on time-of-use or dynamic pricing, to customers using energy storage.
- Suggested Amendment: It is unclear whether additional incentives are needed nor it is clear in the bill what type of incentive is envisioned, its purpose, or its funding levels. The author may wish to consider striking this provision in the bill.
SECTION 1. Section 454.53 is added to the Public Utilities Code, to read:
454.53. (a) The commission shall require load-serving entities, in developing and updating their integrated resource plans pursuant to Section 454.52, to consider the benefits of procuring energy storage systems, as defined in Section 2835.
(b) Except as provided in subdivision (c), the commission, in approving an integrated resource plan for a load-serving entity shall require that, to the extent energy storage systems can meet resource needs as well as or better than fossil-fuel-based generation at reasonably equivalent or lower cost, the plan provide for the procurement of energy storage systems before fossil-fuel-based generation.
(c) In certifying an integrated resource plan for a community choice aggregator, the commission shall act in accordance with paragraph (3) of subdivision (b) of Section 454.52 and paragraph (5) of subdivision (a) of Section 366.2.
SEC. 2. Section 455.6 is added to the Public Utilities Code, to read:
455.6. The commission shall, in a new or existing proceeding, require each electrical corporation, by October 1, 2017, to propose new tariffs or programs to provide incentives to customers of the electrical corporation for installing energy storage systems on the customer side of an electric meter that is connected to the electrical grid.
SEC. 2. Section [to be determined] is added to the Public Utilities Code, to read:
The commission shall require electrical corporations to offer "time of use pricing" or "dynamic pricing" to customers using energy storage at their premises.
SEC. 3. Section 2836.1 is added to the Public Utilities Code, to read:
2836.1. (a) (1) Except as provided in subdivision (b), on or before January 1, 2018, the commission shall determine appropriate targets, if any, for each load-serving entity to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030. Energy storage systems procured pursuant to the targets shall be limited to those that reduce the need for fossil-fuel-based generation, provide benefits to the electrical grid, or support the integration of eligible renewable energy resources procured pursuant to the California Renewables Portfolio Standard Program (Article 16 (commencing with Section 399.11) of Chapter 2.3 of Part 1).
(2) This subdivision does not prohibit the commission’s evaluation and approval of any application for funding or recovery for costs of any ongoing or new development, trial, or testing of energy storage projects or technologies outside the targets required by this chapter.
(b) On or before July 1, 2018, the governing board of each community choice aggregator shall determine appropriate targets, if any, for the community choice aggregator to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030. The governing board may consider a variety of policies to encourage cost-effective deployment of energy storage systems to reach the targets, including refinement of existing procurement methods to properly value energy storage systems.
(c) On or before July 1, 2018, or during its next open integrated resource plan process, the governing board of each local publicly owned electric utility shall determine appropriate targets, if any, for the utility to procure viable and cost-effective energy storage systems to be achieved by December 31, 2030. The governing board may consider a variety of policies to encourage the cost-effective deployment of energy storage systems to reach the targets, including refinement of existing procurement methods to properly value energy storage systems.
SEC. 4. Section 9620.5 is added to the Public Utilities Code, to read:
9620.5. The governing board of each local publicly owned electric utility, in planning for future procurement of resources, shall consider the benefits of procuring energy storage systems, as defined in Section 2835, and, to the extent energy storage systems can meet resource needs as well as or better than fossil-fuel-based generation at reasonably equivalent or lower costs, procure energy storage systems before fossil-fuel-based generation.
- Support and Opposition:
Supporters state that this bill will significantly advance California's ability to both promote and leverage energy storage resources in managing and supporting the electric grid and clean energy goals. A CCA provider noted that this bill was written in a way to increase energy storage while reflecting the procurement autonomy of a CCA Board.
Opponents raise various concerns about the cost implications of the provisions of this bill. Others state that this bill works against the goals enacted in SB 350. Other opponents state that this bill is unnecessary and contrary to policies passed in 2015.
REGISTERED SUPPORT / OPPOSITION:
Support
Association of California Water Agencies
California Energy Storage Alliance
California Solar Energy Industries Association
ElectIQEnvironmental Defense Fund
Green Charge Networks
Marin Clean Energy
Office of Ratepayer Advocates
Qnovo
NGK Insulators
San Diego County Water Authority (if amended)
Solar Energy Industries Association
Solar City
Stem
Opposition
California Chamber of Commerce
California Municipal Utilities Association
Pacific Gas and Electric Company
San Diego Gas and Electric
Southern California Edison
Analysis Prepared by: Sue Kateley / U. & C. / (916) 319-2083
Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB |
THIRD READING
Bill No: SB 886
:
SENATE ENERGY, U. & C. COMMITTEE: 8-3, 4/19/16
AYES: Hueso, Hertzberg, Hill, Lara, Leyva, McGuire, Pavley, Wolk
NOES: Morrell, Cannella, Gaines
SENATE APPROPRIATIONS COMMITTEE: 5-2, 5/27/16
AYES: Lara, Beall, Hill, McGuire, Mendoza
NOES: Bates, Nielsen
DIGEST: This bill requires appropriate energy storage system procurement targets; requires each load-serving entity and locally owned public electric utility to plan for the procurement of energy storage systems before fossil-fuel-based generation; and requires each electrical corporation to propose measures to encourage customers to install energy storage systems.
Existing law:
- Defines “load-serving entity” (LSE) as an electrical corporation (investor-owned utility, or IOU), energy service providers (ESP) or community choice aggregators (CCA). (Public Utilities Code §380(k))
- Requires each LSE and local publicly owned electric utility (POU) to increase purchases of renewable energy such that at least 50 percent of retail sales are procured from renewable energy resources by December 31, 2030. This is known as the Renewable Portfolio Standard (RPS). (Public Utilities Code §399.11 et seq.)
- Requires the California Public Utilities Commission (CPUC) to determine appropriate targets, if any, for LSEs to procure energy storage systems. Requires LSEs to meet any targets adopted by the CPUC by 2015 and 2020. Requires POUs to set their own targets for the procurement of energy storage and then meet those targets by 2016 and 2021. (Public Utilities Code §2835 et seq.)
- Requires the CPUC to adopt a process for each load-serving entity to file an integrated resource plan (IRP), to be approved by the CPUC, to ensure they meet the greenhouse gas emissions reduction targets for the electricity sector; procure at least 50 percent eligible renewable energy resources by December 31, 2030; and meet other statutory requirements. Requires the plan of a CCA be submitted to its governing board for approval and provided to the CPUC for certification. (Public Resources Code §454.52)
- Requires each POU to adopt and regularly update an IRP substantially similar required of the IRPs developed by LSEs, to be reviewed by the California Energy Commission (CEC). (Public Utilities Code §9321)
- Directs the CEC and the CPUC, where feasible, to authorize procurement of resources to provide grid reliability services that minimize reliance on system power and fossil fuel resources and, where feasible, cost effective, and consistent with other state policy objectives, increase the use of large- and small-scale energy storage. (Public Utilities Code §400)
This bill:
- Requires the CPUC to determine, by January 1, 2018, energy storage system procurement targets, if any, applicable to each LSE, to be achieved by December 1, 2030. Requires the governing board of each CCA to determine appropriate energy storage procurement targets, if any, applicable to the CCA.
- Directs the CPUC to require each IOU, by January 1, 2017, to propose new tariffs or programs to encourage customers to install energy storage systems on the customer side of the meter.
- Requires the CPUC, in approving an LSE’s IRP, to require the IRP to provide for the procurement of comparably priced, equally effective energy storage systems before fossil-fuel-based generation.
- States that the CPUC, in certifying an IRP of a CCA, to act according to existing law regarding CCAs, IRPs and energy resources procurement.
- Requires the governing board of each POU, in planning for future procurement of resources, to consider the benefits of procuring energy storage systems and to procure comparably priced, equally effective energy storage systems before fossil-fuel-based generation.
Background
California utilities have procured increasing amounts of electricity from renewable resources, in response to the state’s RPS mandates. Much of this electricity has come from solar and wind energy resources. Such resources can be described as intermittent, meaning that they are not available at all times of the day and can experience difficult-to-predict upward or downward swings in electricity production. This intermittency creates challenges for management of the electric grid, one of which is the need to quickly respond to changes in demand for energy.
According to the California Independent System Operator (CAISO), this energy resource intermittency and rapid ramping in demand create a number of challenging conditions for grid management, including short, steep ramps, risk of overgeneration, and decreased ability to automatically adjust electricity production to maintain grid reliability. [https://www.caiso.com/Documents/FlexibleResources HelpRenewables_FastFacts.pdf.] The CAISO reports that, to reliably manage the electricity grid under these conditions, it needs flexible resources with certain characteristics.
One flexible resource that provides many of the characteristics CAISO says will be needed to reliably manage the electricity grid is natural-gas-fired powerplants, especially “peaker plants” that can quickly ramp up and down. Another potential method to manage the electric grid of the future is through the use of energy storage systems.
This bill encourages the procurement of energy storage systems in a number of ways. Most significantly, it requires the CPUC to determine appropriate energy storage system targets, if any, for IOUs and ESPs, to be achieved by the end of 2030. This bill makes parallel requirements of the governing board of each CCA and POU. This bill also requires the same entities, when developing their IRPs – comprehensive planning documents all LSEs must prepare that detail how the LSE will achieve the state’s environmental and energy goals – to consider the benefits of energy storage systems. Finally, this bill requires IOUs to propose new tariffs or programs to encourage customers to install energy storage systems on the customer side of the meter.
If it becomes law, this bill would not represent the first time the Legislature has mandated the procurement of energy storage systems. AB 2514 (Skinner, 2010), similar to this bill, required CPUC to determine appropriate targets, if any, for LSEs to procure energy storage systems by 2015 and 2020, and directed POUs to set their own comparable energy storage system procurement targets. The state has also provided financial $42 million in incentives to nearly 1,200 to energy storage systems through the Self-Generation Incentive Program.
Related/Prior Legislation
AB 1258 (Skinner, 2013) would have required the CEC to perform a technical analysis of the potential uses of existing hydro-electric and pumped storage facilities to provide additional operational flexibility to integrate eligible renewable energy sources into the grid. The bill was held in the Assembly Committee on Appropriations.
AB 2514 (Skinner, Chapter 469, Statutes of 2010) required CPUC to determine appropriate targets, if any, for LSEs to procure energy storage systems. The bill required LSEs to meet any targets adopted by the CPUC by 2015 and 2020. The bill required POUs to set their own targets for the procurement of energy storage and then meet those targets by 2016 and 2021.
FISCAL EFFECT: Appropriation: Fiscal Com.: Local:
According to the Senate Appropriations Committee, there is a one-time cost up to $339,288 (Public Utilities Commission Utilities Reimbursement Account) for staffing necessary to determine cost-effective storage targets, review investor owned utility tariff filings, develop a policy for prioritizing storage procurement before fossil generation, monitor procurement filings, and to manage a new track of an existing proceeding or to manage a new proceeding.
California Energy Storage Alliance
Consumer Attorneys of California
Environmental Defense Fund
SolarCity
South Coast Air Quality Management District
OPPOSITION: (Verified 5/27/16)
California Chamber of Commerce
Pacific Gas and Electric Company
San Diego Gas & Electric
Southern California Edison
ARGUMENTS IN SUPPORT: According to the author, if the state is going to meet its RPS requirement, and its commitments under the Clean Power Plan, it will need to move away from fossil storage and thermal peakers. Cleaner storage, through batteries and renewable fuels, holds the promise of a smoother load curve and less reliance on facilities like Aliso Canyon to support electricity needs in Los Angeles and elsewhere in California.
ARGUMENTS IN OPPOSITION: Writing in opposition, the IOUs contend this bill makes unnecessary, redundant and premature requirements, muddies the nascent IRP process and fails to treat all LSEs equally.
5/31/16 21:58:36
**** END ****
SENATE COMMITTEE ON APPROPRIATIONS
Senator Ricardo Lara, Chair
2015 - 2016 Regular Session
SB 886 (Pavley) - Electricity: energy storage systems
Version: April 26, 2016 | Policy Vote: E., U., & C. 8 - 3 |
Urgency: No | Mandate: Yes |
Hearing Date: May 27, 2016 | Consultant: Narisha Bonakdar |
Bill Summary:
SB 886 requires the California Public Utilities Commission (CPUC) to determine energy storage system procurement targets applicable to every load-serving entity. The bill also requires the governing board of each local publicly owned electric utility to determine comparable energy storage procurement targets; requires each load-serving entity and locally owned public electric utility to plan for the procurement of energy storage systems before fossil-fuel-based generation; and requires each electrical corporation to propose measures to encourage customers to install energy storage systems.
*********** ANALYSIS ADDENDUM – SUSPENSE FILE ***********
The following information is revised to reflect amendments
adopted by the committee on May 27, 2016
Fiscal Impact:
One-time cost up to $339,288 (Public Utilities Commission Utilities Reimbursement Account) for staffing necessary to determine cost-effective storage targets, review investor owned utility tariff filings, develop a policy for prioritizing storage procurement before fossil generation, monitor procurement filings, and to manage a new track of an existing proceeding or to manage a new proceeding.
Author Amendments:
- Requires the governing board of each community choice aggregator, on or before July 1, 2018, to develop energy storage system procurement targets.
-- END --
SENATE COMMITTEE ON APPROPRIATIONS
Senator Ricardo Lara, Chair
2015 - 2016 Regular Session
SB 886 (Pavley) - Electricity: energy storage systems
Version: April 26, 2016 | Policy Vote: E., U., & C. 8 - 3 |
Urgency: No | Mandate: Yes |
Hearing Date: May 16, 2016 | Consultant: Narisha Bonakdar |
This bill meets the criteria for referral to the Suspense File.
Bill Summary:
SB 886 requires the California Public Utilities Commission (CPUC) to determine energy storage system procurement targets applicable to every load-serving entity. The bill also requires the governing board of each local publicly owned electric utility to determine comparable energy storage procurement targets; requires each load-serving entity and locally owned public electric utility to plan for the procurement of energy storage systems before fossil-fuel-based generation; and requires each electrical corporation to propose measures to encourage customers to install energy storage systems.
Fiscal Impact:
One-time cost up to $339,288 (Public Utilities Commission Utilities Reimbursement Account) for staffing necessary to determine cost-effective storage targets, review investor owned utility (IOU) tariff filings, develop a policy for prioritizing storage procurement before fossil generation, monitor procurement filings, and to manage a new track of an existing proceeding or to manage a new proceeding.
Background:
California utilities have procured increasing amounts of electricity from renewable resources, in response to the state’s Renewable Portfolio Standards (RPS) mandates. Much of this electricity has come from solar and wind energy resources.
The California Energy Commission (CEC), among other things, certifies eligible renewable resources procured by retail sellers (investor-owned utilities, electricity service providers, and community choice aggregators) that meet statutory requirements, tracks and verifies renewable energy output to ensure it is counted only once, specifies procedures for enforcement of the RPS for publicly owned utilities (POU), and certifies and verifies eligible renewable energy resources procured by POUs and to monitor their compliance with the RPS.
The CPUC is charged with, among other things, determining procurement targets and enforcing compliance, reviewing IOU’s contracts for RPS-eligible energy for rate recovery, calculating and administering a cost limitation on renewable procurement for investor-owned utilities, establishing the standard terms and conditions to be used by all IOUs in contracting for eligible renewable energy resources, implementing compliance rules with RPS procurement quantity requirements, and reviewing and approving each IOU’s procurement plan and its process for selecting the least cost bidders of renewable energy that best fit that utility’s resource needs. IOUs use these processes to select winning bidders from their solicitations to procure renewable electricity.
Technologies eligible for the RPS include photovoltaics; solar thermal electric; wind; certain biomass resources; geothermal electric; certain hydroelectric facilities; ocean wave, thermal and tidal energy; fuel cells using renewable fuels; landfill gas; and municipal solid waste conversion, not the direct combustion of municipal solid waste. The CEC voted in March 2012 to suspend the eligibility of biomethane, but biomethane contracts signed before March 29, 2012 are eligible for compliance if certain conditions are met.
Investor-owned utilities may enter into a combination of long-term and short-term contracts with renewable energy project developers for electricity and associated renewable energy credits to be used for compliance with the RPS. Beginning January 1, 2021, at least 65% of the procurements used by an investor-owned utility must come from contracts of 10 years or more in duration.
Proposed Law:
This bill:
- Requires the CPUC to determine, by January 1, 2018, energy storage system procurement targets applicable to each load serving entity (LSE), to be achieved by December 1, 2030.
- Directs the CPUC to require each IOU, by January 1, 2017, to propose new tariffs or programs to encourage customers to install energy storage systems on the customer side of the meter.
- Requires the CPUC, by March 1, 2017, to require each LSE, in developing its IRP, to consider the full benefits of procuring energy storage systems.
- Requires the CPUC, in approving an LSE’s integrated resource plan (IRP), to require the IRP to provide for the procurement of comparably priced, equally effective energy storage systems before fossil-fuel-based generation.
- Requires the governing board of each POU, in planning for future procurement of resources, to consider the benefits of procuring energy storage systems and to procure comparably priced, equally effective energy storage systems before fossil-fuel-based generation.
Related Legislation:
AB 2514 (Skinner, Chapter 469, Statutes of 2010) required CPUC to determine appropriate targets, if any, for LSEs to procure energy storage systems. The bill required LSEs to meet any targets adopted by the CPUC by 2015 and 2020. The bill required POU to set their own targets for the procurement of energy storage and then meet those targets by 2016 and 2021.
-- END --
Discussed in Hearing
Assembly Standing Committee on Utilities and Commerce
Senate Floor
Senate Standing Committee on Energy, Utilities and Communications
Bill Author
Bill Co-Author(s):