AB 734: California Environmental Quality Act: Oakland Sports and Mixed-Use Project.
- Session Year: 2017-2018
- House: Assembly
- Latest Version Date: 2018-09-30
The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of, an environmental impact report (EIR) on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment. CEQA establishes a procedure by which a person may seek judicial review of the decision of the lead agency made pursuant to CEQA. CEQA requires a court to make specified orders if it finds that any determination, finding, or decision of a public agency has been made without compliance with CEQA.
This bill would establish specified procedures for the administrative and judicial review of the environmental review and approvals granted for the Oakland Sports and Mixed-Use Project, as defined, located in the City of Oakland that is certified by the Governor as meeting certain requirements. Because a public agency would be required to comply with those new procedures, this bill would impose a state-mandated local program. The bill would apply certain rules of court establishing procedures requiring actions or proceedings seeking judicial review pursuant to CEQA or the granting of project approvals, including any appeals therefrom, to be resolved, to the extent feasible, within 270 days of the filing of the certified record of proceedings with the court to an action or proceeding seeking judicial review of the lead agencys action related to the Oakland Sports and Mixed-Use Project under CEQA.
This bill would make legislative findings and declarations as to the necessity of a special statute for the Oakland Sports and Mixed-Use Project.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of, an environmental impact report (EIR) on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment. CEQA establishes a procedure by which a person may seek judicial review of the decision of the lead agency made pursuant to CEQA. CEQA requires a court to make specified orders if it finds that any determination, finding, or decision of a public agency has been made without compliance with CEQA.
This bill would establish specified procedures for the administrative and judicial review of the environmental review and approvals granted for the Oakland Sports and Mixed-Use Project, as defined, located in the City of Oakland that is certified by the Governor as meeting certain requirements. Because a public agency would be required to comply with those new procedures, this bill would impose a state-mandated local program. The bill would apply certain rules of court establishing procedures requiring actions or proceedings seeking judicial review pursuant to CEQA or the granting of project approvals, including any appeals therefrom, to be resolved, to the extent feasible, within 270 days of the filing of the certified record of proceedings with the court to an action or proceeding seeking judicial review of the lead agencys action related to the Oakland Sports and Mixed-Use Project under CEQA.
This bill would make legislative findings and declarations as to the necessity of a special statute for the Oakland Sports and Mixed-Use Project.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of, an environmental impact report (EIR) on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment. CEQA establishes a procedure by which a person may seek judicial review of the decision of the lead agency made pursuant to CEQA. CEQA requires a court to make specified orders if it finds that any determination, finding, or decision of a public agency has been made without compliance with CEQA.
This bill would establish specified procedures for the administrative and judicial review of the environmental review and approvals granted for the Oakland Sports and Mixed-Use Project, as defined, located in the City of Oakland that is certified by the Governor as meeting certain requirements. Because a public agency would be required to comply with those new procedures, this bill would impose a state-mandated local program. The bill would apply certain rules of court establishing procedures requiring actions or proceedings seeking judicial review pursuant to CEQA or the granting of project approvals, including any appeals therefrom, to be resolved, to the extent feasible, within 270 days of the filing of the certified record of proceedings with the court to an action or proceeding seeking judicial review of the lead agencys action related to the Oakland Sports and Mixed-Use Project under CEQA.
This bill would make legislative findings and declarations as to the necessity of a special statute for the Oakland Sports and Mixed-Use Project.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of, an environmental impact report (EIR) on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment. CEQA establishes a procedure by which a person may seek judicial review of the decision of the lead agency made pursuant to CEQA. CEQA requires a court to make specified orders if it finds that any determination, finding, or decision of a public agency has been made without compliance with CEQA.
This bill would establish specified procedures for the administrative and judicial review of the environmental review and approvals granted for the Oakland Sports and Mixed-Use Project, as defined, located in the City of Oakland that is certified by the Governor as meeting certain requirements. Because a public agency would be required to comply with those new procedures, this bill would impose a state-mandated local program. The bill would apply certain rules of court establishing procedures requiring actions or proceedings seeking judicial review pursuant to CEQA or the granting of project approvals, including any appeals therefrom, to be resolved, to the extent feasible, within 270 days of the filing of the certified record of proceedings with the court to an action or proceeding seeking judicial review of the lead agencys action related to the Oakland Sports and Mixed-Use Project under CEQA.
This bill would make legislative findings and declarations as to the necessity of a special statute for the Oakland Sports and Mixed-Use Project.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of, an environmental impact report (EIR) on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment. CEQA establishes a procedure by which a person may seek judicial review of the decision of the lead agency made pursuant to CEQA. CEQA requires a court to make specified orders if it finds that any determination, finding, or decision of a public agency has been made without compliance with CEQA.
This bill would require a public agency, in conducting an establish specified procedures for the administrative and judicial review of the environmental review and approvals granted for the Oakland Sports and Mixed-Use Project, as defined, located in the City of Oakland that is certified by the Governor as meeting certain requirements, to comply with specified procedures. The bill would require the public agency to concurrently prepare the record of proceedings and to certify the record of proceeding for the project, as provided. requirements. Because a public agency would be required to comply with those new procedures, this bill would impose a state-mandated local program. The bill would require the Judicial Council, by July 1, 2019, to adopt a rule apply certain rules of court establishing procedures that require requiring actions or proceedings seeking judicial review of the certification or adoption of the environmental review document for the project pursuant to CEQA or the granting of project approvals, including any appeals therefrom, to be resolved, to the extent feasible, within 270 days of the filing of the certified record of proceedings with the court. The bill would prohibit a court form staying or enjoining the construction or operation of the Oakland Sports and Mixed-Use Project, except as provided. court to an action or proceeding seeking judicial review of the lead agencys action related to the Oakland Sports and Mixed-Use Project under CEQA.
This bill would make legislative findings and declarations as to the necessity of a special statute for the Oakland Sports and Mixed-Use Project.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of, an environmental impact report (EIR) on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment. CEQA establishes a procedure by which a person may seek judicial review of the decision of the lead agency made pursuant to CEQA. CEQA requires a court to make specified orders if it finds that any determination, finding, or decision of a public agency has been made without compliance with CEQA.
This bill would require a public agency, in conducting an environmental review for the Oakland Sports and Mixed-Use Project, as defined, located in the City of Oakland that is certified by the Governor as meeting certain requirements, to comply with specified procedures. The bill would require the public agency to concurrently prepare the record of proceedings and to certify the record of proceeding for the project, as provided. Because a public agency would be required to comply with those new procedures, this bill would impose a state-mandated local program. The bill would require the Judicial Council, by July 1, 2019, to adopt a rule of court establishing procedures that require actions or proceedings seeking judicial review of the certification or adoption of the environmental review document for the project pursuant to CEQA or the granting of project approvals, including any appeals therefrom, to be resolved, to the extent feasible, within 270 days of the filing of the certified record of proceedings with the court. The bill would prohibit a court form staying or enjoining the construction or operation of the Oakland Sports and Mixed-Use Project, except as provided.
This bill would make legislative findings and declarations as to the necessity of a special statute for the Oakland Sports and Mixed-Use Project.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law authorizes an infrastructure financing district to finance only public capital facilities of communitywide significance which provide significant benefits to an area larger than the area of the district, including, among others, highways, interchanges, ramps and bridges, arterial streets, parking facilities, transit facilities, facilities for the collection and treatment of water for urban uses, child care facilities, libraries, and facilities for the transfer and disposal of solid waste.This bill would additionally authorize an infrastructure financing district within the City of Oakland to finance public capital facilities or projects that include freight rail.This bill would make legislative findings and declarations as to the necessity of a special statute for the City of Oakland.Existing law authorizes an infrastructure financing district to finance only public capital facilities of communitywide significance which provide significant benefits to an area larger than the area of the district, including, among others, highways, interchanges, ramps and bridges, arterial streets, parking facilities, transit facilities, facilities for the collection and treatment of water for urban uses, child care facilities, libraries, and facilities for the transfer and disposal of solid waste.
This bill would additionally authorize an infrastructure financing district within the City of Oakland to finance public capital facilities or projects that include freight rail.
This bill would make legislative findings and declarations as to the necessity of a special statute for the City of Oakland.
Existing law authorizes counties and cities to create infrastructure financing districts in accordance with a prescribed procedure to finance public capital facilities that provide significant benefits to the area of the border development zone in the Mexican border region.This bill would make a nonsubstantive change to that provision.Existing law authorizes counties and cities to create infrastructure financing districts in accordance with a prescribed procedure to finance public capital facilities that provide significant benefits to the area of the border development zone in the Mexican border region.
This bill would make a nonsubstantive change to that provision.
The Legislature finds and declares all of the following:
(a)The California Environmental Quality Act (Division 13 (commencing with Section 21000) of the Public Resources Code) requires that the environmental impacts of development projects be identified and mitigated. The act also guarantees the public an opportunity to review and comment on the environmental impacts of a project and to participate meaningfully in the development of mitigation measures for potentially significant environmental impacts.
(b)The existing Oakland Coliseum is an aging facility with a maximum seating capacity of 59,326 seats that must be replaced to retain the Oakland Athletics baseball team. The City of Oakland desires to maintain the Oakland Athletics professional baseball franchise in the city by providing development opportunities that will allow the team to develop a state-of-the-art baseball park in the city, while maximizing the economic benefit of the sports team and its facilities for the city.
(c)The city has identified the Howard Terminal site owned by the Port of Oakland as a viable site for a new baseball park. The city seeks to capitalize on the development of a new baseball park to maximize the economic benefit of the team and its facilities for the city, county, and port, including critical transit and transportation infrastructure, affordable housing, open space, and job creation. Essential to the success and feasibility of the new baseball park is the development of complementary adjacent mixed-use residential, commercial, and retail uses that will support the baseball park and further the citys and regions goals for sustainable transit-oriented development, including an increase in supply of housing, including affordable housing.
(d)It is anticipated that the project will generate many thousands of full-time jobs, including employees hired during both construction and operation of the project. This employment estimate does not include the substantial job generation that will occur with the surrounding development uses, which will generate additional hospitality, office, restaurant, and retail jobs in the City of Oakland.
(e)Development of a new baseball park and mixed-use project at either location presents an unprecedented opportunity to invest in new and improved transit and transportation infrastructure and implement sustainability measures designed to improve air quality and mitigate the emissions of greenhouse gases resulting from the project. Both project sites are located in areas of the City of Oakland that are near bus, rail, or water transit facilities and will be designed to maximize opportunities for nonautomobile mode of travel, consistent with the policies and regional vision included in the Sustainable Communities Strategy Plan Bay Area 2040 adopted in July of 2017 by the Metropolitan Transportation Commission and the Association of Bay Area Governments pursuant of Section 65080 of the Government Code.
(f)The proposed baseball park and mixed-use development is the type of project that will create high-wage, highly skilled jobs that pay prevailing wages and living wages. It is the type of large-scale project that will benefit from a streamlined judicial review process and the procedures described in the California Environmental Quality Act. It is therefore in the interest of the state to expedite judicial review of the proposed project, as appropriate, while protecting the environment and the right of the public to review, comment on, and, if necessary, seek judicial review of, the adequacy of the environmental review of the project under the California Environmental Quality Act.
SEC. 2.Section 21168.6.7 is added to the Public Resources Code, to read:21168.6.7.(a)For purposes of this section, the following definitions apply:
(1)Applicant means a public or private entity or its affiliates that proposes the project and its successors, heirs, and assignees.
(2)City of Oaklands Bird Safety Measures means bird safe ordinance guidelines added in June 2013 by City of Oaklands planning staff to the citys standard building permit requirements to reduce bird collisions and other negative impacts to wildlife.
(3)Oakland Sports and Mixed-Use Project or project means the following components of a sports center and mixed-use project located at the Howard Terminal site in the City of Oakland, from demolition and site preparation through operation:
(A)A baseball park that will become the new home to the Oakland Athletics and adjacent residential, retail, commercial, cultural, entertainment, or recreational uses developed by the Oakland Athletics, and that meets all of the following:
(i)The baseball park receives Leadership in Energy and Environmental Design (LEED) Gold certification for new construction within one year after completion of the first baseball season and each new nonresidential building receives LEED Gold certification for new construction within one year after completion of the applicable nonresidential building. Any residential building shall achieve sustainability standards of at least a LEED Gold level or the comparable GreenPoint rating, including meeting sustainability standards for access to quality transit.
(ii)The project does not result in any net additional emissions of greenhouse gases, including greenhouse gas emissions from employee transportation, as determined by the State Air Resources Board pursuant to Division 25.5 (commencing with Section 38500) of the Health and Safety Code. To maximize public health, environmental, and employment benefits, the lead agency shall require measures that will reduce the emissions of greenhouse gases in the project area and in the neighboring communities of the baseball park. Not less than 50 percent of the greenhouse gas emissions reductions necessary to achieve the requirements of this clause, excluding the greenhouse gas emissions from residential uses of the project, shall be from local, direct greenhouse gas emissions reduction measures that give consideration to criteria air pollutant and toxic air contaminant emissions reductions, including, but not limited to, any of the following:
(I)Project design features or onsite reduction measures, or both design features and onsite reduction measures.
(II)Off-site reduction measures in the neighboring communities.
The applicant may obtain offset credits for up to 50 percent of the greenhouse gas emissions reductions necessary to achieve the requirement of this clause. The applicant shall, to the extent feasible, place the highest priority on the purchase of offset credits that produce emission reductions within the City of Oakland or the boundaries of the Bay Area Air Quality Management District. Any offset credits shall be verified by a third party accredited by the State Air Resources Board. In no event shall offset credits be used from a project located outside the United States.
(iii) The project has a transportation management plan or transportation demand management program, or both, that achieves a 20-percent reduction in the number of vehicle trips collectively by attendees, employees, visitors, and customers as compared to operations absent the transportation management plan or transportation demand management program, or both that plan and program. The plan or program for the baseball park shall achieve the 20-percent reduction within one-year after the completion of the first baseball season. The plan or program for the nonbaseball-park portion of the project shall achieve the 20-percent reduction within one year after the completion of that portion. The transportation management plan or transportation demand program shall include a menu of options designed to reduce the number of vehicle trips, including temporarily expanding the capacity of a public transit line, as appropriate, to serve the baseball park events, and participation in a transportation management association that will determine a range of services and programs designed to meet the 20-percent reduction, including providing incentives for transit usage and carpools, bicycle parking and support, signage, and real-time transit information.
(iv)The project is located within a priority development area identified in the sustainable communities strategy Plan Bay Area 2040 adopted by the Metropolitan Transportation Commission and the Association of Bay Area Governments.
(v)The project is subject to a comprehensive package of community benefits approved by the Port of Oakland or City Council of the City of Oakland, as applicable, which may include local employment and job training programs, local business and small business policies, public access and open space, affordable housing, transportation infrastructure, increased frequency of public transit, and transit accessibility and sustainable and healthy development measures for the surrounding community.
(B)Associated public spaces.
(C)Facilities and infrastructure for ingress, egress, and use of the baseball park and mixed-use development.
(b)As a condition of approval of the project, the lead agency shall require the applicant, with respect to any measures specific to the operation of the baseball park, to implement measures that will meet the requirements of this division by the end of the first baseball season.
(c)Rules 3.2220 to 3.2237, inclusive, of the California Rules of Court, as may be amended by the Judicial Council, shall apply to any action or proceeding brought to attack, review, set aside, void, or annul the certification or adoption of any environmental impact report for the project that is certified pursuant to subdivision (d) or the granting of any project approvals, to require the action or proceeding, including any potential appeals therefrom, to be resolved, to the extent feasible, within 270 days of the filing of the certified record of proceedings with the court. On or before September 1, 2019, the Judicial Council shall amend the California Rules of Court, as necessary, to implement this subdivision.
(d)The Governor may certify the project for streamlining pursuant to this section if it complies with all of the following conditions:
(1)The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment. For purposes of this subdivision, jobs that pay prevailing wages means that all construction workers employed in the execution of the project will receive at least the general prevailing rate of per diem wages for the type of work and geographic area, as determined by the Director of Industrial Relations pursuant to Sections 1773 and 1773.9 of the Labor Code. If the project is certified for streamlining, the project applicant shall include this requirement in all contracts for the performance of the work.
(2)(A)If the project is certified pursuant to this section, contractors and subcontractors shall pay to all construction workers employed in the execution of the project at least the general prevailing rate of per diem wages.
(B)Except as provided in subparagraph (C), the obligation of the contractors and subcontractors to pay prevailing wages pursuant to subparagraph (A) may be enforced by the Labor Commissioner through the issuance of a civil wage and penalty assessment pursuant to Section 1741 of the Labor Code, which may be reviewed pursuant to Section 1742 of the Labor Code within 18 months after the completion of the project, or by an underpaid worker through an administrative complaint or civil action. If a civil wage and penalty assessment is issued, the contractor, subcontractor, and surety on a bond or bonds issued to secure the payment of wages covered by the assessment shall be liable for liquidated damages pursuant to Section 1742.1 of the Labor Code.
(C)Subparagraph (B) does not apply if all contractors and subcontractors performing work on the project are subject to a project labor agreement that requires the payment of prevailing wages to all construction workers employed in the execution of the project and provides for enforcement of that obligation through an arbitration procedure. For purposes of this subparagraph, project labor agreement has the same meaning as set forth in paragraph (1) of subdivision (b) of Section 2500 of the Public Contract Code.
(3)The project applicant demonstrates compliance with clauses (i) to (iii), inclusive, of subparagraph (A) of paragraph (3) of subdivision (a) and mitigation measures, to the extent feasible, to reduce any additional greenhouse gas emissions from the project, including greenhouse gas emissions from employee transportation.
(4)The project applicant demonstrates compliance with the requirements of Chapter 12.8 (commencing with Section 42649) and Chapter 12.9 (commencing with Section 42649.8) of Part 3 of Division 30, as applicable.
(5)The project applicant has entered into a binding and enforceable agreement that all mitigation measures required pursuant to this division and any other environmental measures required by this section to certify the project under this chapter shall be conditions of approval of the project, and those conditions will be fully enforceable by the lead agency or another agency designated by the lead agency. In the case of environmental mitigation measures and any other environmental measures required by this section, the applicant agrees, as an ongoing obligation, that those measures will be monitored and enforced by the lead agency for the life of the obligation.
(6)The project applicant agrees to pay for any additional costs incurred by the courts in hearing and deciding any case brought pursuant to this section, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council, as provided in the rules of court adopted by the Judicial Council.
(7)The project applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with review and consideration of the project pursuant to this division, in a form and manner specified by the lead agency for the project.
(8)Project design and implementation will comply with the City of Oaklands Bird Safety Measures, adopted in 2013. Nighttime programming will apply best management practice strategies to avoid and reduce potential collision hazards for migratory and resident birds, to the extent feasible.
(9)The project meets the requirements of clauses (iv) and (v) of subparagraph (A) of paragraph (3) of subdivision (a).
(e)(1)Prior to certifying the project, the Governor shall make a determination that each of the conditions specified in subdivision (d) has been met. These findings are not subject to judicial review.
(2)The guidelines issued pursuant to Chapter 6.5 (commencing with Section 21178) apply to the implementation of this section, to the extent those guidelines are applicable and do not conflict with specific requirements of this section.
(f)(1)The draft and final environmental impact report shall include a notice in not less than 12-point type stating the following:
THIS ENVIRONMENTAL IMPACT REPORT IS SUBJECT TO SECTION 21168.6.7 OF THE PUBLIC RESOURCES CODE, WHICH PROVIDES, AMONG OTHER THINGS, THAT THE LEAD AGENCY NEED NOT CONSIDER CERTAIN COMMENTS FILED AFTER THE CLOSE OF THE PUBLIC COMMENT PERIOD, IF ANY, FOR THE DRAFT ENVIRONMENTAL IMPACT REPORT. ANY JUDICIAL ACTION CHALLENGING THE CERTIFICATION OR ADOPTION OF THE ENVIRONMENTAL IMPACT REPORT OR THE APPROVAL OF THE PROJECT DESCRIBED IN SECTION 21168.6.7 OF THE PUBLIC RESOURCES CODE IS SUBJECT TO THE PROCEDURES SET FORTH IN THAT SECTION. A COPY OF SECTION 21168.6.7 OF THE PUBLIC RESOURCES CODE IS INCLUDED IN THE APPENDIX TO THIS ENVIRONMENTAL IMPACT REPORT.
(2)The draft environmental impact report and final environmental impact report shall contain, as an appendix, the full text of this section.
(3)Within 10 days after the release of the draft environmental impact report, the lead agency shall conduct an informational workshop to inform the public of the key analyses and conclusions of that document.
(4)Within 10 days before the close of the public comment period, the lead agency shall hold a public hearing to receive testimony on the draft environmental impact report. A transcript of the hearing shall be included as an appendix to the final environmental impact report.
(5)(A)Within five days following the close of the public comment period, a commenter on the draft environmental impact report may submit to the lead agency a written request for nonbinding mediation. The lead agency and applicant shall participate in nonbinding mediation with all commenters who submitted timely comments on the draft environmental impact report and who requested the mediation. Mediation conducted pursuant to this paragraph shall end no later than 35 days after the close of the public comment period.
(B)A request for mediation shall identify all areas of dispute raised in the comment submitted by the commenter that are to be mediated.
(C)The lead agency shall select one or more mediators who shall be retired judges or recognized experts with at least five years experience in land use and environmental law or science, or mediation. The applicant shall bear the costs of mediation.
(D)A mediation session shall be conducted on each area of dispute with the parties requesting mediation on that area of dispute.
(E)The lead agency shall adopt, as a condition of approval, any measures agreed upon by the lead agency, the applicant, and any commenter who requested mediation. A commenter who agrees to a measure pursuant to this subparagraph shall not raise the issue addressed by that measure as a basis for an action or proceeding challenging the lead agencys decision to certify or to adopt the environmental impact report or to grant project approval.
(6)The lead agency need not consider written comments submitted after the close of the public comment period, unless those comments address any of the following:
(A)New issues raised in the response to comments by the lead agency.
(B)New information released by the public agency subsequent to the release of the draft environmental impact report, such as new information set forth or embodied in a staff report, proposed permit, proposed resolution, ordinance, or similar documents.
(C)Changes made to the project after the close of the public comment period.
(D)Proposed conditions for approval, mitigation measures, or proposed findings required by Section 21081 or a proposed reporting and monitoring program required by paragraph (1) of subdivision (a) of Section 21081.6, if the lead agency releases those documents subsequent to the release of the draft environmental impact report.
(E)New information that was not reasonably known and could not have been reasonably known during the public comment period.
(7)The lead agency shall file the notice required by subdivision (a) of Section 21152 within five days after the last initial project approval.
(g)(1)The lead agency shall prepare and certify the record of the proceedings in accordance with this subdivision and in accordance with Rule 3.1365 of the California Rules of Court. The applicant shall pay the lead agency for all costs of preparing and certifying the record of proceedings.
(2)No later than three business days following the date of the release of the draft environmental impact report, the lead agency shall make available to the public in a readily accessible electronic format the draft environmental impact report and all other documents submitted to or relied on by the lead agency in the preparation of the draft environmental impact report. A document prepared by the lead agency or submitted by the applicant after the date of the release of the draft environmental impact report that is a part of the record of the proceedings shall be made available to the public in a readily accessible electronic format within five business days after the document is prepared or received by the lead agency.
(3)Notwithstanding paragraph (2), documents submitted to or relied on by the lead agency that were not prepared specifically for the project and are copyright protected are not required to be made readily accessible in an electronic format. For those copyright protected documents, the lead agency shall make an index of the documents available in an electronic format no later than the date of the release of the draft environmental impact report, or within five business days if the document is received or relied on by the lead agency after the release of the draft environmental impact report. The index shall specify the libraries or lead agency offices in which hardcopies of the copyrighted materials are available for public review.
(4)The lead agency shall encourage written comments on the project to be submitted in a readily accessible electronic format, and shall make any such comments available to the public in a readily accessible electronic format within five days of their receipt.
(5)Within seven business days after the receipt of any comment that is not in an electronic format, the lead agency shall convert that comment into a readily accessible electronic format and make it available to the public in that format.
(6)The lead agency shall indicate in the record of the proceedings comments received that were not considered by the lead agency pursuant to paragraph (6) of subdivision (f) and need not include the content of the comments as a part of the record.
(7)Within five days after the filing of the notice required by subdivision (a) of Section 21152, the lead agency shall certify the record of the proceedings for the approval or determination and shall provide an electronic copy of the record to a party that has submitted a written request for a copy. The lead agency may charge and collect a reasonable fee from a party requesting a copy of the record for the electronic copy, which shall not exceed the reasonable cost of reproducing that copy.
(8)Within 10 days after being served with a complaint or a petition for a writ of mandate, the lead agency shall lodge a copy of the certified record of proceedings with the superior court.
(9)Any dispute over the content of the record of the proceedings shall be resolved by the superior court. Unless the superior court directs otherwise, a party disputing the content of the record shall file a motion to augment the record at the time it files its initial brief.
(10)The contents of the record of proceedings shall be as set forth in subdivision (e) of Section 21167.6.
SEC. 3.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the unique need for the development of a sports and mixed-use project in the City of Oakland in an expeditious manner.
SEC. 4.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
The Legislature finds and declares all of the following:
(a)The California Environmental Quality Act (Division 13 (commencing with Section 21000) of the Public Resources Code) requires that the environmental impacts of development projects be identified and mitigated. The act also guarantees the public an opportunity to review and comment on the environmental impacts of a project and to participate meaningfully in the development of mitigation measures for potentially significant environmental impacts.
(b)The existing Oakland Coliseum is an aging facility with a maximum seating capacity of 59,326 seats that must be replaced to retain the Oakland Athletics baseball team. The City of Oakland desires to maintain the Oakland Athletics professional baseball franchise in the city by providing development opportunities that will allow the team to develop a state-of-the-art baseball park in the city, while maximizing the economic benefit of the sports team and its facilities for the city.
(c)The city has identified the Howard Terminal site owned by the Port of Oakland as a viable site for a new baseball park. The city seeks to capitalize on the development of a new baseball park to maximize the economic benefit of the team and its facilities for the city, county, and port, including critical transit and transportation infrastructure, affordable housing, open space, and job creation. Essential to the success and feasibility of the new baseball park is the development of complementary adjacent mixed-use residential, commercial, and retail uses that will support the baseball park and further the citys and regions goals for sustainable transit-oriented development, including an increase in supply of housing, including affordable housing.
(d)It is anticipated that the project will generate many thousands of full-time jobs, including employees hired during both construction and operation of the project. This employment estimate does not include the substantial job generation that will occur with the surrounding development uses, which will generate additional hospitality, office, restaurant, and retail jobs in the City of Oakland.
(e)Development of a new baseball park and mixed-use project at either location presents an unprecedented opportunity to invest in new and improved transit and transportation infrastructure and implement sustainability measures designed to improve air quality and mitigate the emissions of greenhouse gases resulting from the project. Both project sites are located in areas of the City of Oakland that are near bus, rail, or water transit facilities and will be designed to maximize opportunities for nonautomobile mode of travel, consistent with the policies and regional vision included in the Sustainable Communities Strategy Plan Bay Area 2040 adopted in July of 2017 by the Metropolitan Transportation Commission and the Association of Bay Area Governments pursuant of Section 65080 of the Government Code.
(f)The proposed baseball park and mixed-use development is the type of project that will create high-wage, highly skilled jobs that pay prevailing wages and living wages. It is the type of large-scale project that will benefit from a streamlined judicial review process and the procedures described in the California Environmental Quality Act. It is therefore in the interest of the state to expedite judicial review of the proposed project, as appropriate, while protecting the environment and the right of the public to review, comment on, and, if necessary, seek judicial review of, the adequacy of the environmental review of the project under the California Environmental Quality Act.
SEC. 2.Section 21168.6.7 is added to the Public Resources Code, to read:21168.6.7.(a)For purposes of this section, the following definitions apply:
(1)Applicant means a public or private entity or its affiliates that proposes the project and its successors, heirs, and assignees.
(2)City of Oaklands Bird Safety Measures means bird safe ordinance guidelines added in June 2013 by City of Oaklands planning staff to the citys standard building permit requirements to reduce bird collisions and other negative impacts to wildlife.
(3)Oakland Sports and Mixed-Use Project or project means the following components of a sports center and mixed-use project located at the Howard Terminal site in the City of Oakland, from demolition and site preparation through operation:
(A)A baseball park that will become the new home to the Oakland Athletics and adjacent residential, retail, commercial, cultural, entertainment, or recreational uses developed by the Oakland Athletics, and that meets all of the following:
(i)The baseball park receives Leadership in Energy and Environmental Design (LEED) Gold certification for new construction within one year after completion of the first baseball season and each new nonresidential building receives LEED Gold certification for new construction within one year after completion of the applicable nonresidential building. Any residential building shall achieve sustainability standards of at least a LEED Gold level or the comparable GreenPoint rating, including meeting sustainability standards for access to quality transit.
(ii)The project does not result in any net additional emissions of greenhouse gases, including greenhouse gas emissions from employee transportation, as determined by the State Air Resources Board pursuant to Division 25.5 (commencing with Section 38500) of the Health and Safety Code. To maximize public health, environmental, and employment benefits, the lead agency shall require measures that will reduce the emissions of greenhouse gases in the project area and in the neighboring communities of the baseball park. Not less than 50 percent of the greenhouse gas emissions reductions necessary to achieve the requirements of this clause, excluding the greenhouse gas emissions from residential uses of the project, shall be from local, direct greenhouse gas emissions reduction measures that give consideration to criteria air pollutant and toxic air contaminant emissions reductions, including, but not limited to, any of the following:
(I)Project design features or onsite reduction measures, or both design features and onsite reduction measures.
(II)Off-site reduction measures in the neighboring communities.
The applicant may obtain offset credits for up to 50 percent of the greenhouse gas emissions reductions necessary to achieve the requirement of this clause. The applicant shall, to the extent feasible, place the highest priority on the purchase of offset credits that produce emission reductions within the City of Oakland or the boundaries of the Bay Area Air Quality Management District. Any offset credits shall be verified by a third party accredited by the State Air Resources Board. In no event shall offset credits be used from a project located outside the United States.
(iii) The project has a transportation management plan or transportation demand management program, or both, that achieves a 20-percent reduction in the number of vehicle trips collectively by attendees, employees, visitors, and customers as compared to operations absent the transportation management plan or transportation demand management program, or both that plan and program. The plan or program for the baseball park shall achieve the 20-percent reduction within one-year after the completion of the first baseball season. The plan or program for the nonbaseball-park portion of the project shall achieve the 20-percent reduction within one year after the completion of that portion. The transportation management plan or transportation demand program shall include a menu of options designed to reduce the number of vehicle trips, including temporarily expanding the capacity of a public transit line, as appropriate, to serve the baseball park events, and participation in a transportation management association that will determine a range of services and programs designed to meet the 20-percent reduction, including providing incentives for transit usage and carpools, bicycle parking and support, signage, and real-time transit information.
(iv)The project is located within a priority development area identified in the sustainable communities strategy Plan Bay Area 2040 adopted by the Metropolitan Transportation Commission and the Association of Bay Area Governments.
(v)The project is subject to a comprehensive package of community benefits approved by the Port of Oakland or City Council of the City of Oakland, as applicable, which may include local employment and job training programs, local business and small business policies, public access and open space, affordable housing, transportation infrastructure, increased frequency of public transit, and transit accessibility and sustainable and healthy development measures for the surrounding community.
(B)Associated public spaces.
(C)Facilities and infrastructure for ingress, egress, and use of the baseball park and mixed-use development.
(b)As a condition of approval of the project, the lead agency shall require the applicant, with respect to any measures specific to the operation of the baseball park, to implement measures that will meet the requirements of this division by the end of the first baseball season.
(c)Rules 3.2220 to 3.2237, inclusive, of the California Rules of Court, as may be amended by the Judicial Council, shall apply to any action or proceeding brought to attack, review, set aside, void, or annul the certification or adoption of any environmental impact report for the project that is certified pursuant to subdivision (d) or the granting of any project approvals, to require the action or proceeding, including any potential appeals therefrom, to be resolved, to the extent feasible, within 270 days of the filing of the certified record of proceedings with the court. On or before September 1, 2019, the Judicial Council shall amend the California Rules of Court, as necessary, to implement this subdivision.
(d)The Governor may certify the project for streamlining pursuant to this section if it complies with all of the following conditions:
(1)The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment. For purposes of this subdivision, jobs that pay prevailing wages means that all construction workers employed in the execution of the project will receive at least the general prevailing rate of per diem wages for the type of work and geographic area, as determined by the Director of Industrial Relations pursuant to Sections 1773 and 1773.9 of the Labor Code. If the project is certified for streamlining, the project applicant shall include this requirement in all contracts for the performance of the work.
(2)(A)If the project is certified pursuant to this section, contractors and subcontractors shall pay to all construction workers employed in the execution of the project at least the general prevailing rate of per diem wages.
(B)Except as provided in subparagraph (C), the obligation of the contractors and subcontractors to pay prevailing wages pursuant to subparagraph (A) may be enforced by the Labor Commissioner through the issuance of a civil wage and penalty assessment pursuant to Section 1741 of the Labor Code, which may be reviewed pursuant to Section 1742 of the Labor Code within 18 months after the completion of the project, or by an underpaid worker through an administrative complaint or civil action. If a civil wage and penalty assessment is issued, the contractor, subcontractor, and surety on a bond or bonds issued to secure the payment of wages covered by the assessment shall be liable for liquidated damages pursuant to Section 1742.1 of the Labor Code.
(C)Subparagraph (B) does not apply if all contractors and subcontractors performing work on the project are subject to a project labor agreement that requires the payment of prevailing wages to all construction workers employed in the execution of the project and provides for enforcement of that obligation through an arbitration procedure. For purposes of this subparagraph, project labor agreement has the same meaning as set forth in paragraph (1) of subdivision (b) of Section 2500 of the Public Contract Code.
(3)The project applicant demonstrates compliance with clauses (i) to (iii), inclusive, of subparagraph (A) of paragraph (3) of subdivision (a) and mitigation measures, to the extent feasible, to reduce any additional greenhouse gas emissions from the project, including greenhouse gas emissions from employee transportation.
(4)The project applicant demonstrates compliance with the requirements of Chapter 12.8 (commencing with Section 42649) and Chapter 12.9 (commencing with Section 42649.8) of Part 3 of Division 30, as applicable.
(5)The project applicant has entered into a binding and enforceable agreement that all mitigation measures required pursuant to this division and any other environmental measures required by this section to certify the project under this chapter shall be conditions of approval of the project, and those conditions will be fully enforceable by the lead agency or another agency designated by the lead agency. In the case of environmental mitigation measures and any other environmental measures required by this section, the applicant agrees, as an ongoing obligation, that those measures will be monitored and enforced by the lead agency for the life of the obligation.
(6)The project applicant agrees to pay for any additional costs incurred by the courts in hearing and deciding any case brought pursuant to this section, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council, as provided in the rules of court adopted by the Judicial Council.
(7)The project applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with review and consideration of the project pursuant to this division, in a form and manner specified by the lead agency for the project.
(8)Project design and implementation will comply with the City of Oaklands Bird Safety Measures, adopted in 2013. Nighttime programming will apply best management practice strategies to avoid and reduce potential collision hazards for migratory and resident birds, to the extent feasible.
(9)The project meets the requirements of clauses (iv) and (v) of subparagraph (A) of paragraph (3) of subdivision (a).
(e)(1)Prior to certifying the project, the Governor shall make a determination that each of the conditions specified in subdivision (d) has been met. These findings are not subject to judicial review.
(2)The guidelines issued pursuant to Chapter 6.5 (commencing with Section 21178) apply to the implementation of this section, to the extent those guidelines are applicable and do not conflict with specific requirements of this section.
(f)(1)The draft and final environmental impact report shall include a notice in not less than 12-point type stating the following:
THIS ENVIRONMENTAL IMPACT REPORT IS SUBJECT TO SECTION 21168.6.7 OF THE PUBLIC RESOURCES CODE, WHICH PROVIDES, AMONG OTHER THINGS, THAT THE LEAD AGENCY NEED NOT CONSIDER CERTAIN COMMENTS FILED AFTER THE CLOSE OF THE PUBLIC COMMENT PERIOD, IF ANY, FOR THE DRAFT ENVIRONMENTAL IMPACT REPORT. ANY JUDICIAL ACTION CHALLENGING THE CERTIFICATION OR ADOPTION OF THE ENVIRONMENTAL IMPACT REPORT OR THE APPROVAL OF THE PROJECT DESCRIBED IN SECTION 21168.6.7 OF THE PUBLIC RESOURCES CODE IS SUBJECT TO THE PROCEDURES SET FORTH IN THAT SECTION. A COPY OF SECTION 21168.6.7 OF THE PUBLIC RESOURCES CODE IS INCLUDED IN THE APPENDIX TO THIS ENVIRONMENTAL IMPACT REPORT.
(2)The draft environmental impact report and final environmental impact report shall contain, as an appendix, the full text of this section.
(3)Within 10 days after the release of the draft environmental impact report, the lead agency shall conduct an informational workshop to inform the public of the key analyses and conclusions of that document.
(4)Within 10 days before the close of the public comment period, the lead agency shall hold a public hearing to receive testimony on the draft environmental impact report. A transcript of the hearing shall be included as an appendix to the final environmental impact report.
(5)(A)Within five days following the close of the public comment period, a commenter on the draft environmental impact report may submit to the lead agency a written request for nonbinding mediation. The lead agency and applicant shall participate in nonbinding mediation with all commenters who submitted timely comments on the draft environmental impact report and who requested the mediation. Mediation conducted pursuant to this paragraph shall end no later than 35 days after the close of the public comment period.
(B)A request for mediation shall identify all areas of dispute raised in the comment submitted by the commenter that are to be mediated.
(C)The lead agency shall select one or more mediators who shall be retired judges or recognized experts with at least five years experience in land use and environmental law or science, or mediation. The applicant shall bear the costs of mediation.
(D)A mediation session shall be conducted on each area of dispute with the parties requesting mediation on that area of dispute.
(E)The lead agency shall adopt, as a condition of approval, any measures agreed upon by the lead agency, the applicant, and any commenter who requested mediation. A commenter who agrees to a measure pursuant to this subparagraph shall not raise the issue addressed by that measure as a basis for an action or proceeding challenging the lead agencys decision to certify or to adopt the environmental impact report or to grant project approval.
(6)The lead agency need not consider written comments submitted after the close of the public comment period, unless those comments address any of the following:
(A)New issues raised in the response to comments by the lead agency.
(B)New information released by the public agency subsequent to the release of the draft environmental impact report, such as new information set forth or embodied in a staff report, proposed permit, proposed resolution, ordinance, or similar documents.
(C)Changes made to the project after the close of the public comment period.
(D)Proposed conditions for approval, mitigation measures, or proposed findings required by Section 21081 or a proposed reporting and monitoring program required by paragraph (1) of subdivision (a) of Section 21081.6, if the lead agency releases those documents subsequent to the release of the draft environmental impact report.
(E)New information that was not reasonably known and could not have been reasonably known during the public comment period.
(7)The lead agency shall file the notice required by subdivision (a) of Section 21152 within five days after the last initial project approval.
(g)(1)The lead agency shall prepare and certify the record of the proceedings in accordance with this subdivision and in accordance with Rule 3.1365 of the California Rules of Court. The applicant shall pay the lead agency for all costs of preparing and certifying the record of proceedings.
(2)No later than three business days following the date of the release of the draft environmental impact report, the lead agency shall make available to the public in a readily accessible electronic format the draft environmental impact report and all other documents submitted to or relied on by the lead agency in the preparation of the draft environmental impact report. A document prepared by the lead agency or submitted by the applicant after the date of the release of the draft environmental impact report that is a part of the record of the proceedings shall be made available to the public in a readily accessible electronic format within five business days after the document is prepared or received by the lead agency.
(3)Notwithstanding paragraph (2), documents submitted to or relied on by the lead agency that were not prepared specifically for the project and are copyright protected are not required to be made readily accessible in an electronic format. For those copyright protected documents, the lead agency shall make an index of the documents available in an electronic format no later than the date of the release of the draft environmental impact report, or within five business days if the document is received or relied on by the lead agency after the release of the draft environmental impact report. The index shall specify the libraries or lead agency offices in which hardcopies of the copyrighted materials are available for public review.
(4)The lead agency shall encourage written comments on the project to be submitted in a readily accessible electronic format, and shall make any such comments available to the public in a readily accessible electronic format within five days of their receipt.
(5)Within seven business days after the receipt of any comment that is not in an electronic format, the lead agency shall convert that comment into a readily accessible electronic format and make it available to the public in that format.
(6)The lead agency shall indicate in the record of the proceedings comments received that were not considered by the lead agency pursuant to paragraph (6) of subdivision (f) and need not include the content of the comments as a part of the record.
(7)Within five days after the filing of the notice required by subdivision (a) of Section 21152, the lead agency shall certify the record of the proceedings for the approval or determination and shall provide an electronic copy of the record to a party that has submitted a written request for a copy. The lead agency may charge and collect a reasonable fee from a party requesting a copy of the record for the electronic copy, which shall not exceed the reasonable cost of reproducing that copy.
(8)Within 10 days after being served with a complaint or a petition for a writ of mandate, the lead agency shall lodge a copy of the certified record of proceedings with the superior court.
(9)Any dispute over the content of the record of the proceedings shall be resolved by the superior court. Unless the superior court directs otherwise, a party disputing the content of the record shall file a motion to augment the record at the time it files its initial brief.
(10)The contents of the record of proceedings shall be as set forth in subdivision (e) of Section 21167.6.
SEC. 3.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the unique need for the development of a sports and mixed-use project in the City of Oakland in an expeditious manner.
SEC. 4.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
The Legislature finds and declares all of the following:
(a)The California Environmental Quality Act (Division 13 (commencing with Section 21000) of the Public Resources Code) requires that the environmental impacts of development projects be identified and mitigated. The act also guarantees the public an opportunity to review and comment on the environmental impacts of a project and to participate meaningfully in the development of mitigation measures for potentially significant environmental impacts.
(b)The existing Oakland Coliseum is an aging facility with a maximum seating capacity of 59,326 seats that must be replaced to retain the Oakland Athletics baseball team. The City of Oakland desires to maintain the Oakland Athletics professional baseball franchise in the city by providing development opportunities that will allow the team to develop a state-of-the-art baseball park in the city, while maximizing the economic benefit of the sports team and its facilities for the city.
(c)The city has identified two viable sites for the new baseball park, the Oakland-Alameda County Coliseum site principally owned by the City of Oakland and the County of Alameda, and the Howard Terminal site owned by the Port of Oakland. Oakland as a viable site for a new baseball park. The city seeks to capitalize on the development of a new baseball park to maximize the economic benefit of the team and its facilities for the city, county, and port, including critical transit and transportation infrastructure, affordable housing, open space, and job creation. Essential to the success and feasibility of the new baseball park is the development of complementary adjacent mixed-use residential, commercial, and retail uses that will support the baseball park and further the citys and regions goals for sustainable transit-oriented development, including an increase in supply of housing, including affordable housing.
(d)It is anticipated that the project will generate many thousand thousands of full-time jobs, including employees hired during both construction and operation of the project. This employment estimate does not include the substantial job generation that will occur with the surrounding development uses, which will generate additional hospitality, office, restaurant, and retail jobs in the City of Oakland.
(e)Development of a new baseball park and mixed-use project at either location presents an unprecedented opportunity to invest in new and improved transit and transportation infrastructure and implement sustainability measures designed to improve air quality and mitigate the emissions of greenhouse gases resulting from the project. Both project sites are located in areas of the City of Oakland that are near bus, rail, or water transit facilities and will be designed to maximize opportunities for nonautomobile mode of travel, consistent with the policies and regional vision included in the Sustainable Communities Strategy Plan Bay Area 2040 adopted in July of 2017 by the Metropolitan Transportation Commission and the Association of Bay Area Governments pursuant of Section 65080 of the Government Code.
(f)The proposed baseball park and mixed-use development is the type of project that will create high-wage, highly skilled jobs that pay prevailing wages and living wages. It is the type of large-scale project that will benefit from a streamlined judicial review process and the procedures described in the California Environmental Quality Act. It is therefore in the interest of the state to expedite judicial review of the proposed project, as appropriate, while protecting the environment and the right of the public to review, comment on, and, if necessary, seek judicial review of, the adequacy of the environmental review of the project under the California Environmental Quality Act.
SEC. 2.Section 21168.6.7 is added to the Public Resources Code, to read:21168.6.7.(a)For purposes of this section, the following definitions apply:
(1)Applicant means a public or private entity or its affiliates that proposes the project and its successors, heirs, and assignees.
(2)City of Oaklands Bird Safety Measures means bird safe ordinance guidelines added in June 2013 by City of Oaklands planning staff to the citys standard building permit requirements to reduce bird collisions and other negative impacts to wildlife.
(3)Environmental review document means a negative declaration, a mitigated negative declaration, an environmental impact report, an addendum to a negative declaration, a mitigated negative declaration or environmental impact report, or any supplemental or subsequent environmental impact report.(4)(3)Oakland Sports and Mixed-Use Project or project means the following components of a sports center and mixed-use project located at the Howard Terminal site in the City of Oakland or the Oakland-Alameda County Coliseum site in the City of Oakland, from demolition and site preparation through operation:
(A)A baseball park that will become the new home to the Oakland Athletics and adjacent residential, retail, commercial, cultural, entertainment, or recreational uses developed by the Oakland Athletics, and that meets all of the following:
(i)The baseball park receives Leadership in Energy and Environmental Design (LEED) Gold certification for new construction within one year after completion of the first baseball season and each new nonresidential building achieves sustainability standards of at least a receives LEED Gold level certification for new construction within one year after completion. completion of the applicable nonresidential building. Any residential building shall achieve sustainability standards of at least a LEED Gold level or the comparable GreenPoint rating, including meeting sustainability standards for access to quality transit.
(ii)The baseball park project does not result in any net additional emissions of greenhouse gases, after deducting the emissions of greenhouse gases of the existing ballpark at the Oakland Coliseum assuming its full capacity baseball usage, including greenhouse gas emissions from employee transportation, as determined by the State Air Resources Board pursuant to Division 25.5 (commencing with Section 38500) of the Health and Safety Code. To maximize public health, environmental, and employment benefits, the lead agency shall require measures that will reduce the emissions of greenhouse gases in the project area and in the neighboring communities of the baseball park. Not less than 50 percent of the greenhouse gas emissions reductions necessary to achieve the requirements of this clause, excluding the greenhouse gas emissions from residential uses of the project, shall be from local, direct greenhouse gas emissions reduction measures that give consideration to criteria air pollutant and toxic air contaminant emissions reductions, including, but not limited to, any of the following:
(I)Project design features or onsite reduction measures, or both design features and onsite reduction measures.
(II)Off-site reduction measures in the neighboring communities.
The applicant may obtain offset credits for up to 50 percent of the greenhouse gas emissions reductions necessary to achieve the requirement of this clause. The applicant shall, to the extent feasible, place the highest priority on the purchase of offset credits that produce emission reductions within the City of Oakland or the boundaries of the Bay Area Air Quality Management District. Any offset credits shall be verified by a third party accredited by the State Air Resources Board. In no event shall offset credits be used from a project located outside the United States.
(iii)Minimization of operational traffic congestion and air quality impacts through either project design or the implementation of feasible mitigation measures or both design and implementation of feasible mitigation measures, including the adoption of a comprehensive transportation demand management plan designed to reduce single-occupancy vehicles and prioritize other modes of transportation, such as public transit, waterborne transportation, ride-share, bicycles, and pedestrians.(iii) The project has a transportation management plan or transportation demand management program, or both, that achieves a 20-percent reduction in the number of vehicle trips collectively by attendees, employees, visitors, and customers as compared to operations absent the transportation management plan or transportation demand management program, or both that plan and program. The plan or program for the baseball park shall achieve the 20-percent reduction within one-year after the completion of the first baseball season. The plan or program for the nonbaseball-park portion of the project shall achieve the 20-percent reduction within one year after the completion of that portion. The transportation management plan or transportation demand program shall include a menu of options designed to reduce the number of vehicle trips, including temporarily expanding the capacity of a public transit line, as appropriate, to serve the baseball park events, and participation in a transportation management association that will determine a range of services and programs designed to meet the 20-percent reduction, including providing incentives for transit usage and carpools, bicycle parking and support, signage, and real-time transit information.
(iv)The project is located within a priority development area identified in the sustainable communities strategy Plan Bay Area 2040 adopted by the Metropolitan Transportation Commission and the Association of Bay Area Governments.
(v)The project is subject to a comprehensive package of community benefits approved by the Port of Oakland or City Council of the City of Oakland, as applicable, which may include local employment and job training programs, local business and small business policies, public access and open space, affordable housing, transportation infrastructure, increased frequency of public transit, and transit accessibility and sustainable and healthy development measures for the surrounding community.
(B)Associated public spaces.
(C)Facilities and infrastructure for ingress, egress, and use of the baseball park and mixed-use development.
(b)As a condition of approval of the project, the lead agency shall require the applicant, with respect to any measures specific to the operation of the baseball park, to implement measures that will meet the requirements of this division by the end of the first baseball season.
(b)(c)Rules 3.2220 to 3.2237, inclusive, of the California Rules of Court, as may be amended by the Judicial Council, shall apply to any action or proceeding brought to attack, review, set aside, void, or annul the certification or adoption of any environmental review document impact report for the project that is certified pursuant to subdivision (c) (d) or the granting of any project approvals, to require the action or proceeding, including any potential appeals therefrom, to be resolved, to the extent feasible, within 270 days of the filing of the certified record of proceedings with the court. On or before September 1, 2019, the Judicial Council shall amend the California Rules of Court, as necessary, to implement this subdivision.
(c)(d)The Governor may certify the project for streamlining pursuant to this section if it complies with all of the following conditions:
(1)The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment. For purposes of this subdivision, jobs that pay prevailing wages means that all construction workers employed in the execution of the project will receive at least the general prevailing rate of per diem wages for the type of work and geographic area, as determined by the Director of Industrial Relations pursuant to Sections 1773 and 1773.9 of the Labor Code. If the project is certified for streamlining, the project applicant shall include this requirement in all contracts for the performance of the work.
(2)(A)If the project is certified pursuant to this section, contractors and subcontractors shall pay to all construction workers employed in the execution of the project at least the general prevailing rate of per diem wages.
(B)Except as provided in subparagraph (C), the obligation of the contractors and subcontractors to pay prevailing wages pursuant to subparagraph (A) may be enforced by the Labor Commissioner through the issuance of a civil wage and penalty assessment pursuant to Section 1741 of the Labor Code, which may be reviewed pursuant to Section 1742 of the Labor Code within 18 months after the completion of the project, or by an underpaid worker through an administrative complaint or civil action. If a civil wage and penalty assessment is issued, the contractor, subcontractor, and surety on a bond or bonds issued to secure the payment of wages covered by the assessment shall be liable for liquidated damages pursuant to Section 1742.1 of the Labor Code.
(C)Subparagraph (B) does not apply if all contractors and subcontractors performing work on the project are subject to a project labor agreement that requires the payment of prevailing wages to all construction workers employed in the execution of the project and provides for enforcement of that obligation through an arbitration procedure. For purposes of this subparagraph, project labor agreement has the same meaning as set forth in paragraph (1) of subdivision (b) of Section 2500 of the Public Contract Code.
(3)The project applicant demonstrates compliance with clauses (i) to (iii), inclusive, of subparagraph (A) of paragraph (4) (3) of subdivision (a) and mitigation measures, to the extent feasible, to reduce any additional greenhouse gas emissions from the project, including greenhouse gas emissions from employee transportation.
(4)The project applicant demonstrates compliance with the requirements of Chapter 12.8 (commencing with Section 42649) and Chapter 12.9 (commencing with Section 42649.8) of Part 3 of Division 30, as applicable.
(5)The project applicant has entered into a binding and enforceable agreement that all mitigation measures required pursuant to this division and any other environmental measures required by this section to certify the project under this chapter shall be conditions of approval of the project, and those conditions will be fully enforceable by the lead agency or another agency designated by the lead agency. In the case of environmental mitigation measures, measures and any other environmental measures required by this section, the applicant agrees, as an ongoing obligation, that those measures will be monitored and enforced by the lead agency for the life of the obligation.
(6)The project applicant agrees to pay for any additional costs incurred by the courts in hearing and deciding any case brought pursuant to this section, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council, as provided in the rules of court adopted by the Judicial Council.
(7)The project applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with review and consideration of the project pursuant to this division, in a form and manner specified by the lead agency for the project.
(8)Project design and implementation will comply with the City of Oaklands Bird Safety Measures, adopted in 2013. Nighttime programming will apply best management practice strategies to avoid and reduce potential collision hazards for migratory and resident birds, to the extent feasible.
(9)The project meets the requirements of clauses (iv) and (v) of subparagraph (A) of paragraph (4) (3) of subdivision (a).
(d)(e)(1)Prior to certifying the project, the Governor shall make a determination that each of the conditions specified in subdivision (c) (d) has been met. These findings are not subject to judicial review.
(2)The guidelines issued pursuant to Chapter 6.5 (commencing with Section 21178) apply to the implementation of this section. section, to the extent those guidelines are applicable and do not conflict with specific requirements of this section.
(e)As a condition of certification of the project pursuant to this section, the City of Oakland shall make a commitment to include in its Energy and Climate Action Plan measures that mitigate the net emissions of greenhouse gases from the project that are not otherwise mitigated or avoided pursuant to the environmental impact report for the project.(f)(1)The draft and final environmental review document impact report shall include a notice in not less than 12-point type stating the following:
THIS ENVIRONMENTAL REVIEW DOCUMENT IMPACT REPORT IS SUBJECT TO SECTION 21168.6.7 OF THE PUBLIC RESOURCES CODE, WHICH PROVIDES, AMONG OTHER THINGS, THAT THE LEAD AGENCY NEED NOT CONSIDER CERTAIN COMMENTS FILED AFTER THE CLOSE OF THE PUBLIC COMMENT PERIOD, IF ANY, FOR THE DRAFT ENVIRONMENTAL REVIEW DOCUMENT. IMPACT REPORT. ANY JUDICIAL ACTION CHALLENGING THE CERTIFICATION OR ADOPTION OF THE ENVIRONMENTAL REVIEW DOCUMENT IMPACT REPORT OR THE APPROVAL OF THE PROJECT DESCRIBED IN SECTION 21168.6.7 OF THE PUBLIC RESOURCES CODE IS SUBJECT TO THE PROCEDURES SET FORTH IN THAT SECTION. A COPY OF SECTION 21168.6.7 OF THE PUBLIC RESOURCES CODE IS INCLUDED IN THE APPENDIX TO THIS ENVIRONMENTAL REVIEW DOCUMENT. IMPACT REPORT.
(2)The draft environmental review document impact report and final environmental review document impact report shall contain, as an appendix, the full text of this section.
(3)Within 10 days after the release of the draft environmental review document, impact report, the lead agency shall conduct an informational workshop to inform the public of the key analyses and conclusions of that document.
(4)Within 10 days before the close of the public comment period, the lead agency shall hold a public hearing to receive testimony on the draft environmental review document. impact report. A transcript of the hearing shall be included as an appendix to the final environmental review document. impact report.
(5)(A)Within five days following the close of the public comment period, a commenter on the draft environmental review document impact report may submit to the lead agency a written request for nonbinding mediation. The lead agency and applicant shall participate in nonbinding mediation with all commenters who submitted timely comments on the draft environmental review document impact report and who requested the mediation. Mediation conducted pursuant to this paragraph shall end no later than 35 days after the close of the public comment period.
(B)A request for mediation shall identify all areas of dispute raised in the comment submitted by the commenter that are to be mediated.
(C)The lead agency shall select one or more mediators who shall be retired judges or recognized experts with at least five years experience in land use and environmental law or science, or mediation. The applicant shall bear the costs of mediation.
(D)A mediation session shall be conducted on each area of dispute with the parties requesting mediation on that area of dispute.
(E)The lead agency shall adopt, as a condition of approval, any measures agreed upon by the lead agency, the applicant, and any commenter who requested mediation. A commenter who agrees to a measure pursuant to this subparagraph shall not raise the issue addressed by that measure as a basis for an action or proceeding challenging the lead agencys decision to certify or to adopt the environmental review document impact report or to grant project approval.
(6)The lead agency need not consider written comments submitted after the close of the public comment period, unless those comments address any of the following:
(A)New issues raised in the response to comments by the lead agency.
(B)New information released by the public agency subsequent to the release of the draft environmental review document, impact report, such as new information set forth or embodied in a staff report, proposed permit, proposed resolution, ordinance, or similar documents.
(C)Changes made to the project after the close of the public comment period.
(D)Proposed conditions for approval, mitigation measures, or proposed findings required by Section 21081 or a proposed reporting and monitoring program required by paragraph (1) of subdivision (a) of Section 21081.6, if the lead agency releases those documents subsequent to the release of the draft environmental review document. impact report.
(E)New information that was not reasonably known and could not have been reasonably known during the public comment period.
(7)The lead agency shall file the notice required by subdivision (a) of Section 21152 within five days after the last initial project approval.
(8)Paragraphs (3) to (6), inclusive, do not apply to an addendum to an environmental impact report or an addendum to a negative declaration.(g)(1)The lead agency shall prepare and certify the record of the proceedings in accordance with this subdivision and in accordance with Rule 3.1365 of the California Rules of Court. The applicant shall pay the lead agency for all costs of preparing and certifying the record of proceedings.
(2)No later than three business days following the date of the release of the draft environmental review document, impact report, the lead agency shall make available to the public in a readily accessible electronic format the draft environmental review document impact report and all other documents submitted to or relied on by the lead agency in the preparation of the draft environmental review document. impact report. A document prepared by the lead agency or submitted by the applicant after the date of the release of the draft environmental review document impact report that is a part of the record of the proceedings shall be made available to the public in a readily accessible electronic format within five business days after the document is prepared or received by the lead agency.
(3)Notwithstanding paragraph (2), documents submitted to or relied on by the lead agency that were not prepared specifically for the project and are copyright protected are not required to be made readily accessible in an electronic format. For those copyright protected documents, the lead agency shall make an index of the documents available in an electronic format no later than the date of the release of the draft environmental review document, impact report, or within five business days if the document is received or relied on by the lead agency after the release of the draft environmental review document. impact report. The index shall specify the libraries or lead agency offices in which hardcopies of the copyrighted materials are available for public review.
(4)The lead agency shall encourage written comments on the project to be submitted in a readily accessible electronic format, and shall make any such comments available to the public in a readily accessible electronic format within five days of their receipt.
(5)Within seven business days after the receipt of any comment that is not in an electronic format, the lead agency shall convert that comment into a readily accessible electronic format and make it available to the public in that format.
(6)The lead agency shall indicate in the record of the proceedings comments received that were not considered by the lead agency pursuant to paragraph (6) of subdivision (e) (f) and need not include the content of the comments as a part of the record.
(7)Within five days after the filing of the notice required by subdivision (a) of Section 21152, the lead agency shall certify the record of the proceedings for the approval or determination and shall provide an electronic copy of the record to a party that has submitted a written request for a copy. The lead agency may charge and collect a reasonable fee from a party requesting a copy of the record for the electronic copy, which shall not exceed the reasonable cost of reproducing that copy.
(8)Within 10 days after being served with a complaint or a petition for a writ of mandate, the lead agency shall lodge a copy of the certified record of proceedings with the superior court.
(9)Any dispute over the content of the record of the proceedings shall be resolved by the superior court. Unless the superior court directs otherwise, a party disputing the content of the record shall file a motion to augment the record at the time it files its initial brief.
(10)The contents of the record of proceedings shall be as set forth in subdivision (e) of Section 21167.6.
(11)Paragraphs (2) to (10), inclusive, do not apply to an addendum to an environmental impact report or an addendum to a negative declaration.SEC. 3.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the unique need for the development of a sports and mixed-use project in the City of Oakland in an expeditious manner.
SEC. 4.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
The Legislature finds and declares all of the following:
(a)The California Environmental Quality Act (Division 13 (commencing with Section 21000) of the Public Resources Code) requires that the environmental impacts of development projects be identified and mitigated. The act also guarantees the public an opportunity to review and comment on the environmental impacts of a project and to participate meaningfully in the development of mitigation measures for potentially significant environmental impacts.
(b)The existing Oakland Coliseum is an aging facility with a maximum seating capacity of 59,326 seats that must be replaced to retain the Oakland Athletics baseball team. The City of Oakland desires to maintain the Oakland Athletics professional baseball franchise in the city by providing development opportunities that will allow the team to develop a state-of-the-art baseball park in the city, while maximizing the economic benefit of the sports team and its facilities for the city.
(c)The city has identified two viable sites for the new baseball park, the Oakland-Alameda County Coliseum site principally owned by the City of Oakland and the County of Alameda, and the Howard Terminal site owned by the Port of Oakland. The city seeks to capitalize on the development of a new baseball park to maximize the economic benefit of the team and its facilities for the city, county, and port, including critical transit and transportation infrastructure, affordable housing, open space, and job creation. Essential to the success and feasibility of the new baseball park is the development of complementary adjacent mixed-use residential, commercial, and retail uses that will support the baseball park and further the citys and regions goals for sustainable transit-oriented development, including an increase in supply of housing, including affordable housing.
(d)It is anticipated that the project will generate many thousand of full-time jobs, including employees hired during both construction and operation of the project. This employment estimate does not include the substantial job generation that will occur with the surrounding development uses, which will generate additional hospitality, office, restaurant, and retail jobs in the City of Oakland.
(e)Development of a new baseball park and mixed-use project at either location presents an unprecedented opportunity to invest in new and improved transit and transportation infrastructure and implement sustainability measures designed to improve air quality and mitigate the emissions of greenhouse gases resulting from the project. Both project sites are located in areas of the City of Oakland that are near bus, rail, or water transit facilities and will be designed to maximize opportunities for nonautomobile mode of travel, consistent with the policies and regional vision included in the Sustainable Communities Strategy Plan Bay Area 2040 adopted in July of 2017 by the Metropolitan Transportation Commission and the Association of Bay Area Governments pursuant of Section 65080 of the Government Code.
(f)The proposed baseball park and mixed-use development is the type of project that will create high-wage, highly skilled jobs that pay prevailing wages and living wages. It is the type of large-scale project that will benefit from a streamlined judicial review process and the procedures described in the California Environmental Quality Act. It is therefore in the interest of the state to expedite judicial review of the proposed project, as appropriate, while protecting the environment and the right of the public to review, comment on, and, if necessary, seek judicial review of, the adequacy of the environmental review of the project under the California Environmental Quality Act.
SEC. 2.Section 21168.6.7 is added to the Public Resources Code, to read:21168.6.7.(a)For purposes of this section, the following definitions apply:
(1)Applicant means a public or private entity or its affiliates that proposes the project and its successors, heirs, and assignees.
(2)City of Oaklands Bird Safety Measures means bird safe ordinance guidelines added in June 2013 by City of Oaklands planning staff to the citys standard building permit requirements to reduce bird collisions and other negative impacts to wildlife.
(2)(3)Environmental review document means a negative declaration, a mitigated negative declaration, an environmental impact report, an addendum to a negative declaration, a mitigated negative declaration or environmental impact report, or any supplemental or subsequent environmental impact report.
(3)(4)Oakland Sports and Mixed-Use Project or project means the following components of a sports center and mixed-use project located at the Howard Terminal site in the City of Oakland or the Oakland-Alameda County Coliseum site in the City of Oakland, from demolition and site preparation through operation:
(A)A baseball park that will become the new home to the Oakland Athletics and adjacent residential, retail, commercial, cultural, entertainment, or recreational uses developed by the Oakland Athletics, and that meets all of the following:
(i)The baseball park and each new nonresidential building achieves sustainability standards of at least a LEED Gold certification level for new construction after completion. Any residential building shall achieve sustainability standards of at least a LEED Gold rating level or the comparable GreenPoint Gold rated new home. rating, including meeting sustainability standards for access to quality transit.
(ii)The baseball park does not result in any net additional emissions of greenhouse gases, after deducting the emissions of greenhouse gases of the existing ballpark at the Oakland Coliseum assuming its full capacity baseball usage, including greenhouse gas emissions from employee transportation, as determined by the State Air Resources Board pursuant to Division 25.5 (commencing with Section 38500) of the Health and Safety Code.
(iii)The uses are subject to Minimization of operational traffic congestion and air quality impacts through either project design or the implementation of feasible mitigation measures or both design and implementation of feasible mitigation measures, including the adoption of a comprehensive transportation demand management plan designed to reduce single-occupancy vehicles and prioritize other modes of transportation, such as public transit, waterborne transportation, ride-share, bicycles, and pedestrians.
(iv)The project is located within a priority development area identified in the sustainable communities strategy Plan Bay Area 2040 adopted by the Metropolitan Transportation Commission and the Association of Bay Area Governments.
(v)The project is subject to a comprehensive package of community benefits approved by the Port of Oakland or City Council of the City of Oakland, as applicable, which may include local employment and job training programs, local business and small business policies, public access and open space, affordable housing, transportation infrastructure, increased frequency of public transit, and transit accessibility and sustainable and healthy development measures for the surrounding community.
(B)Associated public spaces.
(C)Facilities and infrastructure for ingress, egress, and use of the baseball park and mixed-use development.(b)Rules 3.2220 to 3.2237, inclusive, of the California Rules of Court, as may be amended by the Judicial Council, shall apply to any action or proceeding brought to attack, review, set aside, void, or annul the certification or adoption of any environmental review document for the project that is certified pursuant to subdivision (c) or the granting of any project approvals, to require the action or proceeding, including any potential appeals therefrom, to be resolved, to the extent feasible, within 270 days of the filing of the certified record of proceedings with the court. On or before July September 1, 2019, the Judicial Council shall amend the California Rules of Court, as necessary, to implement this subdivision.
(c)The Governor may certify the project for streamlining pursuant to this section if it complies with all of the following conditions:
(1)The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment. For purposes of this subdivision, jobs that pay prevailing wages means that all construction workers employed in the execution of the project will receive at least the general prevailing rate of per diem wages for the type of work and geographic area, as determined by the Director of Industrial Relations pursuant to Sections 1773 and 1773.9 of the Labor Code. If the project is certified for streamlining, the project applicant shall include this requirement in all contracts for the performance of the work.
(2)(A)If the project is certified pursuant to this section, contractors and subcontractors shall pay to all construction workers employed in the execution of the project at least the general prevailing rate of per diem wages.
(B)Except as provided in subparagraph (C), the obligation of the contractors and subcontractors to pay prevailing wages pursuant to subparagraph (A) may be enforced by the Labor Commissioner through the issuance of a civil wage and penalty assessment pursuant to Section 1741 of the Labor Code, which may be reviewed pursuant to Section 1742 of the Labor Code within 18 months after the completion of the project, or by an underpaid worker through an administrative complaint or civil action. If a civil wage and penalty assessment is issued, the contractor, subcontractor, and surety on a bond or bonds issued to secure the payment of wages covered by the assessment shall be liable for liquidated damages pursuant to Section 1742.1 of the Labor Code.
(C)Subparagraph (B) does not apply if all contractors and subcontractors performing work on the project are subject to a project labor agreement that requires the payment of prevailing wages to all construction workers employed in the execution of the project and provides for enforcement of that obligation through an arbitration procedure. For purposes of this subparagraph, project labor agreement has the same meaning as set forth in paragraph (1) of subdivision (b) of Section 2500 of the Public Contract Code.
(3)The project applicant demonstrates compliance with clauses (i) to (iii), inclusive, of subparagraph (A) of paragraph (4) of subdivision (a) and mitigation measures, to the extent feasible, to reduce any additional greenhouse gas emissions from the project, including greenhouse gas emissions from employee transportation.
(4)The project applicant demonstrates compliance with the requirements of Chapter 12.8 (commencing with Section 42649) and Chapter 12.9 (commencing with Section 42649.8) of Part 3 of Division 30, as applicable.
(5)The project applicant has entered into a binding and enforceable agreement that all mitigation measures required pursuant to this division to certify the project under this chapter shall be conditions of approval of the project, and those conditions will be fully enforceable by the lead agency or another agency designated by the lead agency. In the case of environmental mitigation measures, the applicant agrees, as an ongoing obligation, that those measures will be monitored and enforced by the lead agency for the life of the obligation.
(3)(6)The project applicant agrees to pay for any additional costs incurred by the courts in hearing and deciding any case brought pursuant to this section, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council, as provided in the rules of court adopted by the Judicial Council.
(4)(7)The project applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with review and consideration of the project pursuant to this division, in a form and manner specified by the lead agency for the project.
(8)Project design and implementation will comply with the City of Oaklands Bird Safety Measures, adopted in 2013. Nighttime programming will apply best management practice strategies to avoid and reduce potential collision hazards for migratory and resident birds, to the extent feasible.
(9)The project meets the requirements of clauses (iv) and (v) of subparagraph (A) of paragraph (4) of subdivision (a).
(d)(1)Prior to certifying the project, the Governor shall make a determination that each of the conditions specified in subdivision (c) has been met. These findings are not subject to judicial review.
(2)The guidelines issued pursuant to Chapter 6.5 (commencing with Section 21178) apply to the implementation of this section.
(e)As a condition of certification of the project pursuant to this section, the City of Oakland shall make a commitment to include in its Energy and Climate Action Plan measures that mitigate the net emissions of greenhouse gases from the project that are not otherwise mitigated or avoided pursuant to the environmental impact report for the project.
(e)(f)(1)The draft and final environmental review document shall include a notice in not less than 12-point type stating the following:
THIS ENVIRONMENTAL REVIEW DOCUMENT IS SUBJECT TO SECTION 21168.6.7 OF THE PUBLIC RESOURCES CODE, WHICH PROVIDES, AMONG OTHER THINGS, THAT THE LEAD AGENCY NEED NOT CONSIDER CERTAIN COMMENTS FILED AFTER THE CLOSE OF THE PUBLIC COMMENT PERIOD, IF ANY, FOR THE DRAFT ENVIRONMENTAL REVIEW DOCUMENT. ANY JUDICIAL ACTION CHALLENGING THE CERTIFICATION OR ADOPTION OF THE ENVIRONMENTAL REVIEW DOCUMENT OR THE APPROVAL OF THE PROJECT DESCRIBED IN SECTION 21168.6.7 OF THE PUBLIC RESOURCES CODE IS SUBJECT TO THE PROCEDURES SET FORTH IN THAT SECTION. A COPY OF SECTION 21168.6.7 OF THE PUBLIC RESOURCES CODE IS INCLUDED IN THE APPENDIX TO THIS ENVIRONMENTAL REVIEW DOCUMENT.
(2)The draft environmental review document and final environmental review document shall contain, as an appendix, the full text of this section.
(3)Within 10 days after the release of the draft environmental review document, the lead agency shall conduct an informational workshop to inform the public of the key analyses and conclusions of that document.
(4)Within 10 days before the close of the public comment period, the lead agency shall hold a public hearing to receive testimony on the draft environmental review document. A transcript of the hearing shall be included as an appendix to the final environmental review document.
(5)(A)Within five days following the close of the public comment period, a commenter on the draft environmental review document may submit to the lead agency a written request for nonbinding mediation. The lead agency and applicant shall participate in nonbinding mediation with all commenters who submitted timely comments on the draft environmental review document and who requested the mediation. Mediation conducted pursuant to this paragraph shall end no later than 35 days after the close of the public comment period.
(B)A request for mediation shall identify all areas of dispute raised in the comment submitted by the commenter that are to be mediated.
(C)The lead agency shall select one or more mediators who shall be retired judges or recognized experts with at least five years experience in land use and environmental law or science, or mediation. The applicant shall bear the costs of mediation.
(D)A mediation session shall be conducted on each area of dispute with the parties requesting mediation on that area of dispute.
(E)The lead agency shall adopt, as a condition of approval, any measures agreed upon by the lead agency, the applicant, and any commenter who requested mediation. A commenter who agrees to a measure pursuant to this subparagraph shall not raise the issue addressed by that measure as a basis for an action or proceeding challenging the lead agencys decision to certify or to adopt the environmental review document or to grant project approval.
(6)The lead agency need not consider written comments submitted after the close of the public comment period, unless those comments address any of the following:
(A)New issues raised in the response to comments by the lead agency.
(B)New information released by the public agency subsequent to the release of the draft environmental review document, such as new information set forth or embodied in a staff report, proposed permit, proposed resolution, ordinance, or similar documents.
(C)Changes made to the project after the close of the public comment period.
(D)Proposed conditions for approval, mitigation measures, or proposed findings required by Section 21081 or a proposed reporting and monitoring program required by paragraph (1) of subdivision (a) of Section 21081.6, if the lead agency releases those documents subsequent to the release of the draft environmental review document.
(E)New information that was not reasonably known and could not have been reasonably known during the public comment period.
(7)The lead agency shall file the notice required by subdivision (a) of Section 21152 within five days after the last initial project approval.
(8)Paragraphs (3) to (6), inclusive, do not apply to an addendum to an environmental impact report or an addendum to a negative declaration.
(f)(g)(1) The lead agency shall prepare and certify the record of the proceedings in accordance with this subdivision and in accordance with Rule 3.1365 of the California Rules of Court. The applicant shall pay the lead agency for all costs of preparing and certifying the record of proceedings.
(2)No later than three business days following the date of the release of the draft environmental review document, the lead agency shall make available to the public in a readily accessible electronic format the draft environmental review document and all other documents submitted to or relied on by the lead agency in the preparation of the draft environmental review document. A document prepared by the lead agency or submitted by the applicant after the date of the release of the draft environmental review document that is a part of the record of the proceedings shall be made available to the public in a readily accessible electronic format within five business days after the document is prepared or received by the lead agency.
(3)Notwithstanding paragraph (2), documents submitted to or relied on by the lead agency that were not prepared specifically for the project and are copyright protected are not required to be made readily accessible in an electronic format. For those copyright protected documents, the lead agency shall make an index of the documents available in an electronic format no later than the date of the release of the draft environmental review document, or within five business days if the document is received or relied on by the lead agency after the release of the draft environmental review document. The index shall specify the libraries or lead agency offices in which hardcopies of the copyrighted materials are available for public review.
(4)The lead agency shall encourage written comments on the project to be submitted in a readily accessible electronic format, and shall make any such comments available to the public in a readily accessible electronic format within five days of their receipt.
(5)Within seven business days after the receipt of any comment that is not in an electronic format, the lead agency shall convert that comment into a readily accessible electronic format and make it available to the public in that format.
(6)The lead agency shall indicate in the record of the proceedings comments received that were not considered by the lead agency pursuant to paragraph (6) of subdivision (e) and need not include the content of the comments as a part of the record.
(7)Within five days after the filing of the notice required by subdivision (a) of Section 21152, the lead agency shall certify the record of the proceedings for the approval or determination and shall provide an electronic copy of the record to a party that has submitted a written request for a copy. The lead agency may charge and collect a reasonable fee from a party requesting a copy of the record for the electronic copy, which shall not exceed the reasonable cost of reproducing that copy.
(8)Within 10 days after being served with a complaint or a petition for a writ of mandate, the lead agency shall lodge a copy of the certified record of proceedings with the superior court.
(9)Any dispute over the content of the record of the proceedings shall be resolved by the superior court. Unless the superior court directs otherwise, a party disputing the content of the record shall file a motion to augment the record at the time it files its initial brief.
(10)The contents of the record of proceedings shall be as set forth in subdivision (e) of Section 21167.6.
(11)Paragraphs (2) to (10), inclusive, do not apply to an addendum to an environmental impact report or an addendum to a negative declaration.
SEC. 3.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the unique need for the development of a sports and mixed-use project in the City of Oakland in an expeditious manner.
SEC. 4.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
The Legislature finds and declares all of the following:
(a)The California Environmental Quality Act (Division 13 (commencing with Section 21000) of the Public Resources Code) requires that the environmental impacts of development projects be identified and mitigated. The act also guarantees the public an opportunity to review and comment on the environmental impacts of a project and to participate meaningfully in the development of mitigation measures for potentially significant environmental impacts.
(b)The existing Oakland Coliseum is an aging facility with a maximum seating capacity of 59,326 seats that must be replaced to retain the Oakland Athletics baseball team. The City of Oakland desires to maintain the Oakland Athletics professional baseball franchise in the city by providing development opportunities that will allow the team to develop a state-of-the-art baseball park in the city, while maximizing the economic benefit of the sports team and its facilities for the city.
(c)The city has identified two viable sites for the new baseball park, the Oakland-Alameda County Coliseum site principally owned by the City of Oakland and the County of Alameda, and the Howard Terminal site owned by the Port of Oakland. The city seeks to capitalize on the development of a new baseball park to maximize the economic benefit of the team and its facilities for the city, county, and port, including critical transit and transportation infrastructure, affordable housing, open space, and job creation. Essential to the success and feasibility of the new baseball park is the development of complementary adjacent mixed-use residential, commercial, and retail uses that will support the baseball park and further the citys and regions goals for sustainable transit-oriented development, including an increase in supply of housing, including affordable housing.
(d)It is anticipated that the project will generate many thousand of full-time jobs, including employees hired during both construction and operation of the project. This employment estimate does not include the substantial job generation that will occur with the surrounding development uses, which will generate additional hospitality, office, restaurant, and retail jobs in the City of Oakland.
(e)Development of a new baseball park and mixed-use project at either location presents an unprecedented opportunity to invest in new and improved transit and transportation infrastructure and implement sustainability measures designed to improve air quality and mitigate the emissions of greenhouse gases resulting from the project. Both project sites are located in areas of the City of Oakland that are near bus, rail, or water transit facilities and will be designed to maximize opportunities for nonautomobile mode of travel, consistent with the policies and regional vision included in the Sustainable Communities Strategy Plan Bay Area 2040 adopted in July of 2017 by the Metropolitan Transportation Commission and the Association of Bay Area Governments pursuant of Section 65080 of the Government Code.
(f)The proposed baseball park and mixed-use development is the type of project that will create high-wage, highly skilled jobs that pay prevailing wages and living wages. It is the type of large-scale project that will benefit from a streamlined judicial review process and the procedures described in the California Environmental Quality Act. It is therefore in the interest of the state to expedite judicial review of the proposed project, as appropriate, while protecting the environment and the right of the public to review, comment on, and, if necessary, seek judicial review of, the adequacy of the environmental review of the project under the California Environmental Quality Act.
SEC. 2.Section 21168.6.7 is added to the Public Resources Code, to read:21168.6.7.(a)For purposes of this section, the following definitions apply:
(1)Applicant means a public or private entity or its affiliates that proposes the project and its successors, heirs, and assignees.
(2)Environmental review document means a negative declaration, a mitigated negative declaration, an environmental impact report, an addendum to a negative declaration, a mitigated negative declaration or environmental impact report, or any supplemental or subsequent environmental impact report.
(3)Oakland Sports and Mixed-Use Project or project means the following components of a sports center and mixed-use project located at the Howard Terminal site in the City of Oakland or the Oakland-Alameda County Coliseum site in the City of Oakland, from demolition and site preparation through operation:
(A)A baseball park that will become the new home to the Oakland Athletics and adjacent residential, retail, commercial, cultural, entertainment, or recreational uses developed by the Oakland Athletics, and that meets all of the following:
(i)The baseball park and each new mixed-use nonresidential building achieves at least LEED Silver Gold certification or its equivalent for new construction after completion or the project achieves at least completion. Any residential building shall achieve at least LEED Neighborhood Design Silver rating or its equivalent. Gold rating or GreenPoint Gold rated new home.
(ii)The baseball park does not result in any net additional emissions of greenhouse gases, including greenhouse gas emissions from employee transportation, as determined by the State Air Resources Board pursuant to Division 25.5 (commencing with Section 38500) of the Health and Safety Code.
(ii)(iii)The uses are subject to a comprehensive transportation demand management plan to reduce single-occupancy vehicles and prioritize other modes of transportation, such as public transit, waterborne transportation, ride-share, bicycles, and pedestrians.
(iii)(iv)The project is located within a priority development area identified in the sustainable communities strategy Plan Bay Area 2040 adopted by the Metropolitan Transportation Commission and the Association of Bay Area Governments.
(B)Associated public spaces.
(C)Facilities and infrastructure for ingress, egress, and use of the baseball park and mixed-use development.
(b)On or before July 1, 2019, the Judicial Council shall adopt a rule of court to establish procedures applicable to actions or proceedings brought to attack, review, set aside, void, or annul the certification or adoption of the environmental review document for the Oakland Sports and Mixed-Use Project that is certified by the Governor pursuant to this section or the granting of any project approvals that require the actions or proceedings, including any potential appeals therefrom, be resolved, to the extent feasible, within 270 days of the filing of the certified record of proceedings with the court.(b)Rules 3.2220 to 3.2237, inclusive, of the California Rules of Court, as may be amended by the Judicial Council, shall apply to any action or proceeding brought to attack, review, set aside, void, or annul the certification or adoption of any environmental review document for the project that is certified pursuant to subdivision (c) or the granting of any project approvals, to require the action or proceeding, including any potential appeals therefrom, to be resolved, to the extent feasible, within 270 days of the filing of the certified record of proceedings with the court. On or before July 1, 2019, the Judicial Council shall amend the California Rules of Court, as necessary, to implement this subdivision.
(c)The Governor may certify the project for streamlining pursuant to this section if it complies with all of the following conditions:
(1)The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment. For purposes of this subdivision, jobs that pay prevailing wages means that all construction workers employed in the execution of the project will receive at least the general prevailing rate of per diem wages for the type of work and geographic area, as determined by the Director of Industrial Relations pursuant to Sections 1773 and 1773.9 of the Labor Code. If the project is certified for streamlining, the project applicant shall include this requirement in all contracts for the performance of the work.
(2)(A)If the project is certified pursuant to this section, contractors and subcontractors shall pay to all construction workers employed in the execution of the project at least the general prevailing rate of per diem wages.
(B)Except as provided in subparagraph (C), the obligation of the contractors and subcontractors to pay prevailing wages pursuant to subparagraph (A) may be enforced by the Labor Commissioner through the issuance of a civil wage and penalty assessment pursuant to Section 1741 of the Labor Code, which may be reviewed pursuant to Section 1742 of the Labor Code within 18 months after the completion of the project, or by an underpaid worker through an administrative complaint or civil action. If a civil wage and penalty assessment is issued, the contractor, subcontractor, and surety on a bond or bonds issued to secure the payment of wages covered by the assessment shall be liable for liquidated damages pursuant to Section 1742.1 of the Labor Code.
(C)Subparagraph (B) does not apply if all contractors and subcontractors performing work on the project are subject to a project labor agreement that requires the payment of prevailing wages to all construction workers employed in the execution of the project and provides for enforcement of that obligation through an arbitration procedure. For purposes of this subparagraph, project labor agreement has the same meaning as set forth in paragraph (1) of subdivision (b) of Section 2500 of the Public Contract Code.
(3)The project applicant agrees to pay the for any additional costs of the Court of Appeal incurred by the courts in hearing and deciding any case brought pursuant to this division, section, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council, as provided in the rules of court adopted by the Judicial Council pursuant to Section 21185. Council.
(4)The project applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with review and consideration of the project pursuant to this division, in a form and manner specified by the lead agency for the project.
(d)(1)Prior to certifying the project, the Governor shall make a determination that each of the conditions specified in subdivision (c) has been met. These findings are not subject to judicial review.
(2)The Governor may issue guidelines regarding application for and certification of the project pursuant to this chapter. Any guidelines issued pursuant to this subdivision are not subject to the rulemaking provisions of the Administrative Procedures Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code).(2)The guidelines issued pursuant to Chapter 6.5 (commencing with Section 21178) apply to the implementation of this section.
(e)(1)The draft and final environmental review document shall include a notice in not less than 12-point type stating the following:
THIS ENVIRONMENTAL REVIEW DOCUMENT IS SUBJECT TO SECTION 21168.6.7 OF THE PUBLIC RESOURCES CODE, WHICH PROVIDES, AMONG OTHER THINGS, THAT THE LEAD AGENCY NEED NOT CONSIDER CERTAIN COMMENTS FILED AFTER THE CLOSE OF THE PUBLIC COMMENT PERIOD, IF ANY, FOR THE DRAFT ENVIRONMENTAL REVIEW DOCUMENT. ANY JUDICIAL ACTION CHALLENGING THE CERTIFICATION OR ADOPTION OF THE ENVIRONMENTAL REVIEW DOCUMENT OR THE APPROVAL OF THE PROJECT DESCRIBED IN SECTION 21168.6.7 OF THE PUBLIC RESOURCES CODE IS SUBJECT TO THE PROCEDURES SET FORTH IN THAT SECTION. A COPY OF SECTION 21168.6.7 OF THE PUBLIC RESOURCES CODE IS INCLUDED IN THE APPENDIX TO THIS ENVIRONMENTAL REVIEW DOCUMENT.
(2)The draft environmental review document and final environmental review document shall contain, as an appendix, the full text of this section.
(3)Within 10 days after the release of the draft environmental review document, the lead agency shall conduct an informational workshop to inform the public of the key analyses and conclusions of that document.
(4)Within 10 days before the close of the public comment period, the lead agency shall hold a public hearing to receive testimony on the draft environmental review document. A transcript of the hearing shall be included as an appendix to the final environmental review document.
(5)(A)Within five days following the close of the public comment period, a commenter on the draft environmental review document may submit to the lead agency a written request for nonbinding mediation. The lead agency and applicant shall participate in nonbinding mediation with all commenters who submitted timely comments on the draft environmental review document and who requested the mediation. Mediation conducted pursuant to this paragraph shall end no later than 35 days after the close of the public comment period.
(B)A request for mediation shall identify all areas of dispute raised in the comment submitted by the commenter that are to be mediated.
(C)The lead agency shall select one or more mediators who shall be retired judges or recognized experts with at least five years experience in land use and environmental law or science, or mediation. The applicant shall bear the costs of mediation.
(D)A mediation session shall be conducted on each area of dispute with the parties requesting mediation on that area of dispute.
(E)The lead agency shall adopt, as a condition of approval, any measures agreed upon by the lead agency, the applicant, and any commenter who requested mediation. A commenter who agrees to a measure pursuant to this subparagraph shall not raise the issue addressed by that measure as a basis for an action or proceeding challenging the lead agencys decision to certify or to adopt the environmental review document or to grant project approval.
(6)The lead agency need not consider written comments submitted after the close of the public comment period, unless those comments address any of the following:
(A)New issues raised in the response to comments by the lead agency.
(B)New information released by the public agency subsequent to the release of the draft environmental review document, such as new information set forth or embodied in a staff report, proposed permit, proposed resolution, ordinance, or similar documents.
(C)Changes made to the project after the close of the public comment period.
(D)Proposed conditions for approval, mitigation measures, or proposed findings required by Section 21081 or a proposed reporting and monitoring program required by paragraph (1) of subdivision (a) of Section 21081.6, if the lead agency releases those documents subsequent to the release of the draft environmental review document.
(E)New information that was not reasonably known and could not have been reasonably known during the public comment period.
(7)The lead agency shall file the notice required by subdivision (a) of Section 21152 within five days after the last initial project approval.
(8)Paragraphs (3) to (6), inclusive, do not apply to an addendum to an environmental impact report or an addendum to a negative declaration.
(f)(1) The lead agency shall prepare and certify the record of the proceedings in accordance with this subdivision and in accordance with Rule 3.1365 of the California Rules of Court. The applicant shall pay the lead agency for all costs of preparing and certifying the record of proceedings.
(2)No later than three business days following the date of the release of the draft environmental review document, the lead agency shall make available to the public in a readily accessible electronic format the draft environmental review document and all other documents submitted to or relied on by the lead agency in the preparation of the draft environmental review document. A document prepared by the lead agency or submitted by the applicant after the date of the release of the draft environmental review document that is a part of the record of the proceedings shall be made available to the public in a readily accessible electronic format within five business days after the document is prepared or received by the lead agency.
(3)Notwithstanding paragraph (2), documents submitted to or relied on by the lead agency that were not prepared specifically for the project and are copyright protected are not required to be made readily accessible in an electronic format. For those copyright protected documents, the lead agency shall make an index of the documents available in an electronic format no later than the date of the release of the draft environmental review document, or within five business days if the document is received or relied on by the lead agency after the release of the draft environmental review document. The index shall specify the libraries or lead agency offices in which hardcopies of the copyrighted materials are available for public review.
(4)The lead agency shall encourage written comments on the project to be submitted in a readily accessible electronic format, and shall make any such comments available to the public in a readily accessible electronic format within five days of their receipt.
(5)Within seven business days after the receipt of any comment that is not in an electronic format, the lead agency shall convert that comment into a readily accessible electronic format and make it available to the public in that format.
(6)The lead agency shall indicate in the record of the proceedings comments received that were not considered by the lead agency pursuant to paragraph (6) of subdivision (e) and need not include the content of the comments as a part of the record.
(7)Within five days after the filing of the notice required by subdivision (a) of Section 21152, the lead agency shall certify the record of the proceedings for the approval or determination and shall provide an electronic copy of the record to a party that has submitted a written request for a copy. The lead agency may charge and collect a reasonable fee from a party requesting a copy of the record for the electronic copy, which shall not exceed the reasonable cost of reproducing that copy.
(8)Within 10 days after being served with a complaint or a petition for a writ of mandate, the lead agency shall lodge a copy of the certified record of proceedings with the superior court.
(9)Any dispute over the content of the record of the proceedings shall be resolved by the superior court. Unless the superior court directs otherwise, a party disputing the content of the record shall file a motion to augment the record at the time it files its initial brief.
(10)The contents of the record of proceedings shall be as set forth in subdivision (e) of Section 21167.6.
(11)Paragraphs (2) to (10), inclusive, do not apply to an addendum to an environmental impact report or an addendum to a negative declaration.
(g)(1)(A)Except as provided in paragraph (2), in granting relief in an action or proceeding brought against the Oakland Sports and Mixed-Use Project pursuant to this division, the court shall not stay or enjoin the construction or operation of the Oakland Sports and Mixed-Use Project unless the court finds either of the following:(i)The continued construction or operation of the project presents an imminent threat to the public health and safety.(ii)The project site contains unforeseen important Native American artifacts or unforeseen important historical, archaeological, or ecological values that would be materially, permanently, and adversely affected by the continued construction or operation of the project unless the court stays or enjoins the construction or operation of the project.(B)If the court finds that clause (i) or (ii) of subparagraph (A) is satisfied, the court shall only enjoin those specific activities associated with the project that present an imminent threat to public health and safety or that materially, permanently, and adversely affect unforeseen important Native American artifacts or unforeseen important historical, archaeological, or ecological values.(2)Where an action or proceeding brought pursuant to this section challenges aspects of the project other than the baseball park component of the project and those portions or specific project activities are severable from the baseball park component, the court may enter an order as to aspects of the project other than the baseball park component of the project that includes one or more of the remedies set forth in Section 21168.9.SEC. 3.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the unique need for the development of a sports and mixed-use project in the City of Oakland in an expeditious manner.
SEC. 4.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
The Legislature finds and declares all of the following:
(a)The California Environmental Quality Act (Division 13 (commencing with Section 21000) of the Public Resources Code) requires that the environmental impacts of development projects be identified and mitigated. The act also guarantees the public an opportunity to review and comment on the environmental impacts of a project and to participate meaningfully in the development of mitigation measures for potentially significant environmental impacts.
(b)The existing Oakland Coliseum is an aging facility with a maximum seating capacity of 59,326 seats that must be replaced to retain the Oakland Athletics baseball team. The City of Oakland desires to maintain the Oakland Athletics professional baseball franchise in the city by providing development opportunities that will allow the team to develop a state-of-the-art baseball park in the city, while maximizing the economic benefit of the sports team and its facilities for the city.
(c)The city has identified two viable sites for the new baseball park, the Oakland-Alameda County Coliseum site principally owned by the City of Oakland and the County of Alameda, and the Howard Terminal site owned by the Port of Oakland. The city seeks to capitalize on the development of a new baseball park to maximize the economic benefit of the team and its facilities for the city, county, and port, including critical transit and transportation infrastructure, affordable housing, open space, and job creation. Essential to the success and feasibility of the new baseball park is the development of complementary adjacent mixed-use residential, commercial, and retail uses that will support the baseball park and further the citys and regions goals for sustainable transit-oriented development, including an increase in supply of housing, including affordable housing.
(d)It is anticipated that the project will generate many thousand of full-time jobs, including employees hired during both construction and operation of the project. This employment estimate does not include the substantial job generation that will occur with the surrounding development uses, which will generate additional hospitality, office, restaurant, and retail jobs in the City of Oakland.
(e)Development of a new baseball park and mixed-use project at either location presents an unprecedented opportunity to invest in new and improved transit and transportation infrastructure and implement sustainability measures designed to improve air quality and mitigate the emissions of greenhouse gases resulting from the project. Both project sites are located in areas of the City of Oakland that are near bus, rail, or water transit facilities and will be designed to maximize opportunities for nonautomobile mode of travel, consistent with the policies and regional vision included in the Sustainable Communities Strategy Plan Bay Area 2040 adopted in July of 2017 by the Metropolitan Transportation Commission and the Association of Bay Area Governments pursuant of Section 65080 of the Government Code.
(f)The proposed baseball park and mixed-use development is the type of project that will create high-wage, highly skilled jobs that pay prevailing wages and living wages. It is the type of large-scale project that will benefit from a streamlined judicial review process and the procedures described in the California Environmental Quality Act. It is therefore in the interest of the state to expedite judicial review of the proposed project, as appropriate, while protecting the environment and the right of the public to review, comment on, and, if necessary, seek judicial review of, the adequacy of the environmental review of the project under the California Environmental Quality Act.
SEC. 2.Section 21168.6.7 is added to the Public Resources Code, to read:21168.6.7.(a)For purposes of this section, the following definitions apply:
(1)Applicant means a public or private entity or its affiliates that proposes the project and its successors, heirs, and assignees.
(2)Environmental review document means a negative declaration, a mitigated negative declaration, an environmental impact report, an addendum to a negative declaration, a mitigated negative declaration or environmental impact report, or any supplemental or subsequent environmental impact report.
(3)Oakland Sports and Mixed-Use Project or project means the following components of a sports center and mixed-use project located at the Howard Terminal site in the City of Oakland or the Oakland-Alameda County Coliseum site in the City of Oakland, from demolition and site preparation through operation:
(A)A baseball park that will become the new home to the Oakland Athletics and adjacent residential, retail, commercial, cultural, entertainment, or recreational uses developed by the Oakland Athletics, and that meets all of the following:
(i)The baseball park and each new mixed-use building achieves at least LEED Silver certification or its equivalent for new construction after completion or the project achieves at least LEED Neighborhood Design Silver rating or its equivalent.
(ii)The uses are subject to a comprehensive transportation demand management plan to reduce single-occupancy vehicles and prioritize other modes of transportation, such as public transit, waterborne transportation, ride-share, bicycles, and pedestrians.
(iii)The project is located within a priority development area identified in the sustainable communities strategy Plan Bay Area 2040 adopted by the Metropolitan Transportation Commission and the Association of Bay Area Governments.
(B)Associated public spaces.
(C)Facilities and infrastructure for ingress, egress, and use of the baseball park and mixed-use development.
(b)On or before July 1, 2019, the Judicial Council shall adopt a rule of court to establish procedures applicable to actions or proceedings brought to attack, review, set aside, void, or annul the certification or adoption of the environmental review document for the Oakland Sports and Mixed-Use Project that is certified by the Governor pursuant to this section or the granting of any project approvals that require the actions or proceedings, including any potential appeals therefrom, be resolved, to the extent feasible, within 270 days of the filing of the certified record of proceedings with the court.
(c)The Governor may certify the project for streamlining pursuant to this section if it complies with all of the following conditions:
(1)The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment. For purposes of this subdivision, jobs that pay prevailing wages means that all construction workers employed in the execution of the project will receive at least the general prevailing rate of per diem wages for the type of work and geographic area, as determined by the Director of Industrial Relations pursuant to Sections 1773 and 1773.9 of the Labor Code. If the project is certified for streamlining, the project applicant shall include this requirement in all contracts for the performance of the work.
(2)(A)If the project is certified pursuant to this section, contractors and subcontractors shall pay to all construction workers employed in the execution of the project at least the general prevailing rate of per diem wages.
(B)Except as provided in subparagraph (C), the obligation of the contractors and subcontractors to pay prevailing wages pursuant to subparagraph (A) may be enforced by the Labor Commissioner through the issuance of a civil wage and penalty assessment pursuant to Section 1741 of the Labor Code, which may be reviewed pursuant to Section 1742 of the Labor Code within 18 months after the completion of the project, or by an underpaid worker through an administrative complaint or civil action. If a civil wage and penalty assessment is issued, the contractor, subcontractor, and surety on a bond or bonds issued to secure the payment of wages covered by the assessment shall be liable for liquidated damages pursuant to Section 1742.1 of the Labor Code.
(C)Subparagraph (B) does not apply if all contractors and subcontractors performing work on the project are subject to a project labor agreement that requires the payment of prevailing wages to all construction workers employed in the execution of the project and provides for enforcement of that obligation through an arbitration procedure. For purposes of this subparagraph, project labor agreement has the same meaning as set forth in paragraph (1) of subdivision (b) of Section 2500 of the Public Contract Code.
(3)The project applicant agrees to pay the costs of the Court of Appeal in hearing and deciding any case brought pursuant to this division, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council, as provided in the rules of court adopted by the Judicial Council pursuant to Section 21185.
(4)The project applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with review and consideration of the project pursuant to this division, in a form and manner specified by the lead agency for the project.
(d)(1)Prior to certifying the project, the Governor shall make a determination that each of the conditions specified in subdivision (c) has been met. These findings are not subject to judicial review.
(2)The Governor may issue guidelines regarding application for and certification of the project pursuant to this chapter. Any guidelines issued pursuant to this subdivision are not subject to the rulemaking provisions of the Administrative Procedures Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code).
(e)(1)The draft and final environmental review document shall include a notice in not less than 12-point type stating the following:
THIS ENVIRONMENTAL REVIEW DOCUMENT IS SUBJECT TO SECTION 21168.6.7 OF THE PUBLIC RESOURCES CODE, WHICH PROVIDES, AMONG OTHER THINGS, THAT THE LEAD AGENCY NEED NOT CONSIDER CERTAIN COMMENTS FILED AFTER THE CLOSE OF THE PUBLIC COMMENT PERIOD, IF ANY, FOR THE DRAFT ENVIRONMENTAL REVIEW DOCUMENT. ANY JUDICIAL ACTION CHALLENGING THE CERTIFICATION OR ADOPTION OF THE ENVIRONMENTAL REVIEW DOCUMENT OR THE APPROVAL OF THE PROJECT DESCRIBED IN SECTION 21168.6.7 OF THE PUBLIC RESOURCES CODE IS SUBJECT TO THE PROCEDURES SET FORTH IN THAT SECTION. A COPY OF SECTION 21168.6.7 OF THE PUBLIC RESOURCES CODE IS INCLUDED IN THE APPENDIX TO THIS ENVIRONMENTAL REVIEW DOCUMENT.
(2)The draft environmental review document and final environmental review document shall contain, as an appendix, the full text of this section.
(3)Within 10 days after the release of the draft environmental review document, the lead agency shall conduct an informational workshop to inform the public of the key analyses and conclusions of that document.
(4)Within 10 days before the close of the public comment period, the lead agency shall hold a public hearing to receive testimony on the draft environmental review document. A transcript of the hearing shall be included as an appendix to the final environmental review document.
(5)(A) Within five days following the close of the public comment period, a commenter on the draft environmental review document may submit to the lead agency a written request for nonbinding mediation. The lead agency and applicant shall participate in nonbinding mediation with all commenters who submitted timely comments on the draft environmental review document and who requested the mediation. Mediation conducted pursuant to this paragraph shall end no later than 35 days after the close of the public comment period.
(B)A request for mediation shall identify all areas of dispute raised in the comment submitted by the commenter that are to be mediated.
(C)The lead agency shall select one or more mediators who shall be retired judges or recognized experts with at least five years experience in land use and environmental law or science, or mediation. The applicant shall bear the costs of mediation.
(D)A mediation session shall be conducted on each area of dispute with the parties requesting mediation on that area of dispute.
(E)The lead agency shall adopt, as a condition of approval, any measures agreed upon by the lead agency, the applicant, and any commenter who requested mediation. A commenter who agrees to a measure pursuant to this subparagraph shall not raise the issue addressed by that measure as a basis for an action or proceeding challenging the lead agencys decision to certify or to adopt the environmental review document or to grant project approval.
(6)The lead agency need not consider written comments submitted after the close of the public comment period, unless those comments address any of the following:
(A)New issues raised in the response to comments by the lead agency.
(B)New information released by the public agency subsequent to the release of the draft environmental review document, such as new information set forth or embodied in a staff report, proposed permit, proposed resolution, ordinance, or similar documents.
(C)Changes made to the project after the close of the public comment period.
(D)Proposed conditions for approval, mitigation measures, or proposed findings required by Section 21081 or a proposed reporting and monitoring program required by paragraph (1) of subdivision (a) of Section 21081.6, if the lead agency releases those documents subsequent to the release of the draft environmental review document.
(E)New information that was not reasonably known and could not have been reasonably known during the public comment period.
(7)The lead agency shall file the notice required by subdivision (a) of Section 21152 within five days after the last initial project approval.
(8)Paragraphs (3) to (6), inclusive, do not apply to an addendum to an environmental impact report or an addendum to a negative declaration.
(f)(1) The lead agency shall prepare and certify the record of the proceedings in accordance with this subdivision and in accordance with Rule 3.1365 of the California Rules of Court. The applicant shall pay the lead agency for all costs of preparing and certifying the record of proceedings.
(2)No later than three business days following the date of the release of the draft environmental review document, the lead agency shall make available to the public in a readily accessible electronic format the draft environmental review document and all other documents submitted to or relied on by the lead agency in the preparation of the draft environmental review document. A document prepared by the lead agency or submitted by the applicant after the date of the release of the draft environmental review document that is a part of the record of the proceedings shall be made available to the public in a readily accessible electronic format within five business days after the document is prepared or received by the lead agency.
(3)Notwithstanding paragraph (2), documents submitted to or relied on by the lead agency that were not prepared specifically for the project and are copyright protected are not required to be made readily accessible in an electronic format. For those copyright protected documents, the lead agency shall make an index of the documents available in an electronic format no later than the date of the release of the draft environmental review document, or within five business days if the document is received or relied on by the lead agency after the release of the draft environmental review document. The index shall specify the libraries or lead agency offices in which hardcopies of the copyrighted materials are available for public review.
(4)The lead agency shall encourage written comments on the project to be submitted in a readily accessible electronic format, and shall make any such comments available to the public in a readily accessible electronic format within five days of their receipt.
(5)Within seven business days after the receipt of any comment that is not in an electronic format, the lead agency shall convert that comment into a readily accessible electronic format and make it available to the public in that format.
(6)The lead agency shall indicate in the record of the proceedings comments received that were not considered by the lead agency pursuant to paragraph (6) of subdivision (e) and need not include the content of the comments as a part of the record.
(7)Within five days after the filing of the notice required by subdivision (a) of Section 21152, the lead agency shall certify the record of the proceedings for the approval or determination and shall provide an electronic copy of the record to a party that has submitted a written request for a copy. The lead agency may charge and collect a reasonable fee from a party requesting a copy of the record for the electronic copy, which shall not exceed the reasonable cost of reproducing that copy.
(8)Within 10 days after being served with a complaint or a petition for a writ of mandate, the lead agency shall lodge a copy of the certified record of proceedings with the superior court.
(9)Any dispute over the content of the record of the proceedings shall be resolved by the superior court. Unless the superior court directs otherwise, a party disputing the content of the record shall file a motion to augment the record at the time it files its initial brief.
(10)The contents of the record of proceedings shall be as set forth in subdivision (e) of Section 21167.6.
(11)Paragraphs (2) to (10), inclusive, do not apply to an addendum to an environmental impact report or an addendum to a negative declaration.
(g)(1)(A)Except as provided in paragraph (2), in granting relief in an action or proceeding brought against the Oakland Sports and Mixed-Use Project pursuant to this division, the court shall not stay or enjoin the construction or operation of the Oakland Sports and Mixed-Use Project unless the court finds either of the following:
(i)The continued construction or operation of the project presents an imminent threat to the public health and safety.
(ii)The project site contains unforeseen important Native American artifacts or unforeseen important historical, archaeological, or ecological values that would be materially, permanently, and adversely affected by the continued construction or operation of the project unless the court stays or enjoins the construction or operation of the project.
(B)If the court finds that clause (i) or (ii) of subparagraph (A) is satisfied, the court shall only enjoin those specific activities associated with the project that present an imminent threat to public health and safety or that materially, permanently, and adversely affect unforeseen important Native American artifacts or unforeseen important historical, archaeological, or ecological values.
(2)Where an action or proceeding brought pursuant to this section challenges aspects of the project other than the baseball park component of the project and those portions or specific project activities are severable from the baseball park component, the court may enter an order as to aspects of the project other than the baseball park component of the project that includes one or more of the remedies set forth in Section 21168.9.
SEC. 3.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the unique need for the development of a sports and mixed-use project in the City of Oakland in an expeditious manner.
SEC. 4.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
SECTION 1.Section 53395.3.10 is added to the Government Code, to read:53395.3.10.In addition to the projects authorized by Section 53395.3, any infrastructure financing district within the City of Oakland may finance public capital facilities or projects that include freight rail.SEC. 2.The Legislature finds and declares that a special law is necessary and that a general law cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the unique circumstances applicable to the City of Oakland.In addition to the projects authorized by Section 53395.3, any infrastructure financing district within the City of Oakland may finance public capital facilities or projects that include freight rail.
SEC. 2.The Legislature finds and declares that a special law is necessary and that a general law cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the unique circumstances applicable to the City of Oakland.
SECTION 1.Section 53398.3 of the Government Code is amended to read:53398.3.(a)A district may finance (1) the purchase, construction, expansion, improvement, seismic retrofit, or rehabilitation of any real or other tangible property with an estimated useful life of 15 years or longer that satisfies the requirements of subdivision (b), (2) the planning and design work that is directly related to the purchase, construction, expansion, or rehabilitation of that property, and (3) the costs described in Sections 53398.5 and 53398.31. A district may only finance the purchase of facilities for which construction has been completed, as determined by the legislative body. The facilities need not be physically located within the boundaries of the district. A district may not finance routine maintenance, repair work, or the costs of any ongoing operation or providing services of any kind.(b)The district shall finance only public capital facilities that provide significant benefits to the area of the border development zone, including, but not limited to, all of the following:(1)Highways, interchanges, ramps and bridges, major and minor arterial streets, major and minor collector streets, parking facilities, and transit facilities. Phased road widening projects shall also be permitted.(2)Sewage collection, pumping, treatment and water reclamation plants and interceptor pipes.(3)Facilities for the collection and treatment of water for urban uses.(4)Flood control levees and dams, retention basins, and drainage facilities.(5)Child care facilities.(6)Libraries.(7)Parks, recreational facilities, and open space.(8)Facilities for the transfer and disposal of solid waste, including transfer stations and vehicles.(9)Public safety facilities.(c)Any district that constructs dwelling units shall set aside not less than 20 percent of those units to increase and improve the communitys supply of low- and moderate-income housing available at an affordable housing cost, as defined by Section 50052.5 of the Health and Safety Code, to persons and families of low and moderate income, as defined in Section 50093 of the Health and Safety Code.(d)A district may also finance the purchase of sewage treatment capacity that provides significant benefits to the area of the border development zone. The facility providing the sewage treatment capacity need not be physically located within the boundaries of the district.(a)A district may finance (1) the purchase, construction, expansion, improvement, seismic retrofit, or rehabilitation of any real or other tangible property with an estimated useful life of 15 years or longer that satisfies the requirements of subdivision (b), (2) the planning and design work that is directly related to the purchase, construction, expansion, or rehabilitation of that property, and (3) the costs described in Sections 53398.5 and 53398.31. A district may only finance the purchase of facilities for which construction has been completed, as determined by the legislative body. The facilities need not be physically located within the boundaries of the district. A district may not finance routine maintenance, repair work, or the costs of any ongoing operation or providing services of any kind.
(b)The district shall finance only public capital facilities that provide significant benefits to the area of the border development zone, including, but not limited to, all of the following:
(1)Highways, interchanges, ramps and bridges, major and minor arterial streets, major and minor collector streets, parking facilities, and transit facilities. Phased road widening projects shall also be permitted.
(2)Sewage collection, pumping, treatment and water reclamation plants and interceptor pipes.
(3)Facilities for the collection and treatment of water for urban uses.
(4)Flood control levees and dams, retention basins, and drainage facilities.
(5)Child care facilities.
(6)Libraries.
(7)Parks, recreational facilities, and open space.
(8)Facilities for the transfer and disposal of solid waste, including transfer stations and vehicles.
(9)Public safety facilities.
(c)Any district that constructs dwelling units shall set aside not less than 20 percent of those units to increase and improve the communitys supply of low- and moderate-income housing available at an affordable housing cost, as defined by Section 50052.5 of the Health and Safety Code, to persons and families of low and moderate income, as defined in Section 50093 of the Health and Safety Code.
(d)A district may also finance the purchase of sewage treatment capacity that provides significant benefits to the area of the border development zone. The facility providing the sewage treatment capacity need not be physically located within the boundaries of the district.
|
Date
|
Status
|
|---|---|
| Sep 30, 2018 | Chaptered by Secretary of State - Chapter 959, Statutes of 2018. |
| Sep 30, 2018 | Approved by the Governor. |
| Sep 11, 2018 | Enrolled and presented to the Governor at 4:30 p.m. |
| Aug 31, 2018 | Senate amendments concurred in. To Engrossing and Enrolling. |
| Aug 31, 2018 | Read third time. Passed. Ordered to the Assembly. |
| Aug 29, 2018 | Withdrawn from committee. |
| Aug 28, 2018 | Senate Rule 29.3(b) suspended. |
| Aug 21, 2018 | Read second time and amended. Ordered to third reading. |
| Aug 20, 2018 | From committee: Amend, and do pass as amended. (Ayes 7. Noes 0.) (August 16). |
| Aug 13, 2018 | In committee: Referred to APPR. suspense file. |
| Aug 6, 2018 | In committee: Hearing postponed by committee. |
| Jul 3, 2018 | Read second time and amended. Re-referred to Com. on APPR. |
| Jul 2, 2018 | From committee: Amend, and do pass as amended and re-refer to Com. on APPR. (Ayes 5. Noes 1.) (June 26). |
| Jun 21, 2018 | From committee: Do pass and re-refer to Com. on JUD. (Ayes 7. Noes 0.) (June 20). Re-referred to Com. on JUD. |
| Jun 13, 2018 | Re-referred to Coms. on EQ. and JUD. |
| Jun 6, 2018 | Withdrawn from committee. |
| Jun 4, 2018 | From committee chair, with author's amendments: Amend, and re-refer to committee. Read second time, amended, and re-referred to Com. on GOV. & F. |
| Jun 13, 2017 | In committee: Set, first hearing. Hearing canceled at the request of author. |
| May 24, 2017 | Referred to Coms. on GOV. & F. and T. & H. |
| May 11, 2017 | In Senate. Read first time. To Com. on RLS. for assignment. |
| May 11, 2017 | Read third time. Passed. Ordered to the Senate. (Ayes 63. Noes 9. Page 1479.) |
| May 8, 2017 | Read second time. Ordered to third reading. |
| May 4, 2017 | From committee: Do pass. (Ayes 8. Noes 0.) (May 3). |
| Mar 27, 2017 | Re-referred to Com. on L. GOV. |
| Mar 23, 2017 | From committee chair, with author's amendments: Amend, and re-refer to Com. on L. GOV. Read second time and amended. |
| Feb 16, 2017 | From printer. May be heard in committee March 18. |
| Feb 15, 2017 | Read first time. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Aug 31, 2018 | Assembly 3rd Reading AB734 Bonta et al. By Skinner | Senate Floor |
Passed |
|
| Aug 31, 2018 | AB 734 Bonta Concurrence in Senate Amendments | Assembly Floor |
Passed |
|
| Aug 31, 2018 | With recommendation: That Senate amendments be concurred in. | Assembly Standing Committee on Natural Resources |
Passed |
|
| Aug 16, 2018 | Do pass as amended | Senate Standing Committee on Appropriations |
Passed |
|
| Aug 13, 2018 | Placed on suspense file | Senate Standing Committee on Appropriations |
Passed |
|
| Jun 26, 2018 | Do pass as amended, but first amend, and re-refer to the Committee on [Appropriations] | Senate Standing Committee on Judiciary |
Passed |
|
| Jun 20, 2018 | Do pass, but first be re-referred to the Committee on [Judiciary] | Senate Standing Committee on Environmental Quality |
Passed |
|
| May 11, 2017 | AB 734 BONTA Assembly Third Reading | Assembly Floor |
Passed |
|
| May 3, 2017 | Do pass. | Assembly Standing Committee on Local Government |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
Date of Hearing: August 31, 2018
ASSEMBLY COMMITTEE ON NATURAL RESOURCES
Al Muratsuchi, Acting Chair
ABPCA Bill Id:AB 734 (
Author:Bonta) – As Amended Ver:August 28, 2018
SUBJECT: California Environmental Quality Act: Oakland Sports and Mixed-Use Project
SUMMARY: Establishes special procedures for California Environmental Quality Act (CEQA) review, additional conditions for certification, and expedited (270 day) judicial review for a proposed baseball park and mixed-use development in the City of Oakland.
Specifically, this bill:
- Applies to a project – consisting of a baseball park (proposed as the future home for the Oakland Athletics) and adjacent residential, retail, commercial, cultural, entertainment, or recreational uses located at the Howard Terminal (at the eastern edge of the Port of Oakland, near Jack London Square) – that meets the following conditions:
- The baseball park and other nonresidential buildings receive Leadership in Energy and Environmental Design (LEED) gold certification within one year of completion.
- Any residential buildings achieve sustainability standards of at least a LEED gold level or the comparable GreenPoint rating, including meeting sustainability standards for access to quality transit.
- The project does not result in any net additional greenhouse gas (GHG) emissions, including emissions from employee transportation, as determined by the Air Resources Board (ARB).
- Requires the lead agency, to maximize public health, environmental, and employment benefits, to require measures that will reduce GHG emissions in the project area and in the neighboring communities of the baseball park.
- Provides that not less than 50 percent of the GHG emissions reductions necessary to achieve zero net additional GHG emissions, excluding emissions from residential uses, shall be from local, direct GHG emissions reduction measures, including, but not limited to, any of the following:
- Project design features or onsite reduction measures, or both design features and onsite reduction measures.
- Off-site reduction measures in the neighboring communities.
- Permits the applicant to obtain offset credits for up to 50 percent of the GHG emissions reductions necessary to achieve zero net additional GHG emissions.
- Requires the applicant, to the extent feasible, to place the highest priority on the purchase of offset credits that produce emission reductions within the City of Oakland or the boundaries of the Bay Area Air Quality Management District.
- Requires any offset credits to be verified by a third party accredited by ARB.
- Prohibits the use of offset credits generated by a project located outside the United States.
- The project has a transportation management plan or transportation demand management program that achieves a 20-percent reduction in vehicle trips for the ballpark within one year of completion of the first baseball season and for each other portion of the projects within one year of completion of that portion.
- The project is located within a priority development area identified in the sustainable communities strategy Plan Bay Area 2040 adopted by the Metropolitan Transportation Commission and the Association of Bay Area Governments.
- The project is subject to a comprehensive package of community benefits approved by the Port of Oakland or the Oakland City Council.
- Requires the lead agency, as a condition of approval of the project, to require the applicant, with respect to any measures specific to the operation of the baseball park, to implement measures that will meet the requirements of CEQA by the end of the first baseball season.
- Provides that Rules of Court 3.2220 to 3.2237, adopted by the Judicial Council pursuant to AB 900 (Buchanan), Chapter 354, Statutes of 2011, apply to a lawsuit challenging the certification of the environmental impact report (EIR) or any project approvals for a certified project, requiring resolution of the lawsuit, including any appeals, within 270 days, to the extent feasible, of the filing of the certified record of proceedings with the court.
- Authorizes the Governor to certify the project for streamlining if all of the following conditions are met:
- The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment.
- Contractors and subcontractors pay to all construction workers employed in the execution of the project at least the general prevailing rate of per diem wages. Provides that this obligation may be enforced by the Labor Commissioner through the issuance of a civil wage and penalty assessment pursuant to relevant provisions of the Labor Code, unless all contractors and subcontractors performing work on the project are subject to a project labor agreement that requires the payment of prevailing wages and provides for enforcement through an arbitration procedure.
- The project applicant demonstrates compliance with the LEED, GHG neutrality, and trip reduction requirements listed above.
- The applicant demonstrates compliance with the requirement that generators of commercial solid waste and large amounts of organic waste arrange for recycling services for those materials.
- The project applicant has entered into a binding and enforceable agreement that all mitigation measures required under CEQA and any other environmental measures required by this bill shall be conditions of approval of the project, and those conditions will be fully enforceable by the lead agency or another agency designated by the lead agency. In the case of environmental mitigation measures and any other environmental measures required by this bill, the applicant agrees, as an ongoing obligation, that those measures will be monitored and enforced by the lead agency for the life of the obligation.
- The project applicant agrees to pay any additional costs incurred by the courts in hearing and deciding any case, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council.
- The project applicant agrees to pay the costs of preparing the administrative record for the project concurrent with review and consideration of the project pursuant to CEQA, in a form and manner specified by the lead agency for the project.
- Project design and implementation will comply with the City of Oakland's bird safety measures, as specified.
- Requires the Governor, prior to certifying the project, to make a determination that each of the conditions specified above has been met. These findings are not subject to judicial review.
- Provides that the guidelines issued for AB 900 apply to the extent they are applicable and do not conflict with specific requirements of this bill.
- Establishes special procedures for public participation in CEQA review of the project:
- Requires the project EIR to include a specified notice that the EIR is subject to the provisions of the section added by this bill.
- Requires the lead agency to conduct an informational workshop within 10 days of release of the Draft EIR and hold a public hearing within 10 days before close of the public comment period.
- Requires the lead agency and applicant to participate in nonbinding mediation with any party who submitted comments on the Draft EIR and requested mediation within five days of the close of the public comment period, with the cost to be paid by the applicant. Requires mediation to end within 35 days of the close of the public comment period.
- Requires the lead agency to adopt any measures agreed upon in mediation. Prohibits a commenter from raising an issue addressed by that measure in a lawsuit.
- Permits the lead agency to ignore written comments submitted after the close of the public comment period, with specified exceptions for materials addressing new information released after the close of the public comment period.
- Requires the project EIR to include a specified notice that the EIR is subject to the provisions of the section added by this bill.
- Establishes specified requirements for preparation and certification of the administrative record for the project. Requires the lead agency to prepare the record concurrently with the administrative process, provide all EIR documents and comments in an electronic format (with the exception of certain copyright-protected documents), certify the record within five days of filing the notice of determination, provide the record to a party upon written request, and provide the record to the superior court within 10 days of the filing of a petition for review.
EXISTING LAW:
- CEQA requires lead agencies with the principal responsibility for carrying out or approving a proposed project to prepare a negative declaration, mitigated negative declaration, or EIR for this action, unless the project is exempt from CEQA (CEQA includes various statutory exemptions, as well as categorical exemptions in the CEQA guidelines).
- Authorizes judicial review of CEQA actions taken by public agencies, following the agency's decision to carry out or approve the project. Challenges alleging improper determination that a project may have a significant effect on the environment, or alleging an EIR doesn't comply with CEQA, must be filed in the Superior Court within 30 days of filing of the notice of approval. The courts are required to give CEQA actions preference over all other civil actions.
- Pursuant to AB 900, establishes procedures for expedited judicial review (i.e., requiring the courts to resolve lawsuits within 270 days, to the extent feasible) for "environmental leadership" projects certified by the Governor and meeting specified conditions, including LEED gold-certified infill site projects achieving transportation efficiency 15 percent greater than comparable projects and zero net additional GHG emissions. AB 900 sunsets January 1, 2021.
FISCAL EFFECT: According to the Senate Appropriations Committee, this bill would have a fiscal impact of $172,000 (various funds) for ARB to evaluate the project with respect to whether it will result in a net increase of GHG emissions, minor and absorbable costs for Judicial Council to review and revise the rules of the court to meet the requirements of this bill and minor and absorbable costs for the Office of Planning and Research to process a judicial streamlining request.
COMMENTS:
- Author's statement:
The Oakland A’s have called the City of Oakland home for the last fifty years. With the impending loss of the Raiders to Las Vegas and the Golden State Warriors to San Francisco, it’s critically important to the city and entire East Bay region to retain a professional sports team. AB 734 is modeled closely on the legislation previously enacted for the Sacramento Kings and other environmental leadership projects under AB 900 by expediting judicial review for the adjudication of legal challenges within 270 days to the extent feasible. This will help provide certainty to the city and the Oakland A’s who have made a public commitment to staying in Oakland. Currently, the team is evaluating two potential sites to build a new, privately financed, state of the art ballpark and ancillary development that will bring thousands of jobs while providing a significant economic boost to the region. However, the benefits of this bill will only apply to the Howard Terminal site.
- Background. CEQA provides a process for evaluating the environmental effects of applicable projects undertaken or approved by public agencies. If a project is not exempt from CEQA, an initial study is prepared to determine whether the project may have a significant effect on the environment. If the initial study shows that there would not be a significant effect on the environment, the lead agency must prepare a negative declaration. If the initial study shows that the project may have a significant effect on the environment, the lead agency must prepare an EIR.
Generally, an EIR must accurately describe the proposed project, identify and analyze each significant environmental impact expected to result from the proposed project, identify mitigation measures to reduce those impacts to the extent feasible, and evaluate a range of reasonable alternatives to the proposed project. If mitigation measures are required or incorporated into a project, the agency must adopt a reporting or monitoring program to ensure compliance with those measures.
CEQA actions taken by public agencies can be challenged in Superior Court once the agency approves or determines to carry out the project. CEQA appeals are subject to unusually short statutes of limitations. Under current law, court challenges of CEQA decisions generally must be filed within 30 to 35 days, depending on the type of decision. The courts are required to give CEQA actions preference over all other civil actions. The petitioner must request a hearing within 90 days of filing the petition and, generally, briefing must be completed within 90 days of the request for hearing. There is no deadline specified for the court to render a decision.
In 2011, AB 900 and SB 292 (Padilla), Chapter 353, Statutes of 2011, established expedited CEQA judicial review procedures for a limited number of projects. For AB 900, it was large-scale projects meeting extraordinary environmental standards and providing significant jobs and investment. For SB 292, it was a proposed downtown Los Angeles football stadium and convention center project achieving specified traffic and air quality mitigations. For these eligible projects, the bills provided for original jurisdiction by the Court of Appeal and a compressed schedule requiring the court to render a decision on any lawsuit within 175 days. This promised to reduce the existing judicial review timeline by 100 days or more, while creating new burdens for the courts and litigants to meet the compressed schedule. AB 900's provision granting original jurisdiction to the Court of Appeal was invalidated in 2013 by a decision in Alameda Superior Court in Planning and Conservation League v. State of California. AB 900 was subsequently revised to restore jurisdiction to superior courts and require resolution of lawsuits within 270 days.
Only two projects have used the judicial review procedures enacted since 2011: the Sacramento Kings arena project under SB 743 (Steinberg), Chapter 386, Statutes of 2013; and the Golden State Warriors arena project in San Francisco under AB 900. CEQA lawsuits were filed against both projects, and the lawsuits, including appeals, were resolved, in favor of the applicants, within the 270-day timeline.
To date, 11 projects have been certified under AB 900:
- McCoy Solar Energy Project in Riverside County.
- Apple Campus 2 in Cupertino.
- Soitec Solar Energy Project in San Diego County.
- 8150 Sunset Boulevard, a mixed-use commercial and residential project in Hollywood.
- Event Center and Mixed-Use Development at Mission Bay Blocks (i.e., Warriors Arena) in San Francisco.
- Qualcomm Stadium Reconstruction Project in San Diego.
- 6701 Sunset/Crossroads, a mixed-use residential, hotel, and commercial project in Hollywood.
- Yucca-Argyle Project, a mixed-use residential, hotel, and commercial project in Hollywood.
- 10 Van Ness Avenue, a mixed-use commercial/residential redevelopment project in San Francisco.
- 1045 Olive Street Project, a mixed-use commercial/residential redevelopment project in downtown Los Angeles.
- Hollywood Center Project, a mixed-use project in Hollywood.
- Comparison to AB 900. This bill is substantially equivalent to AB 900 on key requirements – including LEED gold certification, GHG neutrality, traffic efficiency, and construction wages – with the following exceptions:
- LEED – This bill permits alternatives to LEED gold certification for the residential buildings in the project. A residential building must achieve sustainability standards of at least a LEED gold level or the comparable GreenPoint rating.
- GHG neutrality – This bill imposes additional conditions, requiring 50 percent of GHG reductions necessary to meet GHG neutrality, excluding residential uses, to come from on-site and local reduction measures, and limiting the use of offsets.
- Traffic efficiency – This bill requires a 20-percent reduction in vehicle trips for the ballpark within one year of completion of the first baseball season and for each other portion of the projects within one year of completion of that portion.
- Bill raises the bar on GHG mitigation and clean air. Following the enactment of AB 32 in 2006, SB 97 was enacted in 2007 to confirm the requirement to address environmental impacts of GHG emissions under CEQA and require the adoption of CEQA Guidelines for the mitigation of GHG emissions or the effects of GHG emissions, including effects associated with transportation or energy consumption. SB 97 requires the CEQA Guidelines to be periodically updated to incorporate new information or criteria established by ARB pursuant to AB 32.
Under CEQA Guidelines adopted pursuant to SB 97, a project’s GHG emissions can be reduced by “off-site measures, including offsets that are not otherwise required” and “measures that sequester greenhouse gases.” The CEQA Guidelines allow projects to reduce GHG emissions by relying on voluntary market offsets that are not otherwise required as well as other offsite and sequestration measures that result in GHG reductions.
When it was enacted in 2011, AB 900 required projects to achieve GHG neutrality, without specifying how. In practice, the AB 900 projects have relied heavily on voluntary offsets. Meanwhile, California's climate policy has focused increasingly on achieving local clean air co-benefits and reducing the reliance on offsets. Last year, the Legislature's extension of the cap-and-trade program, AB 398, included a reduction in total amount of offsets that may be used for compliance, coupled with a requirement that at least half of offsets result in environmental benefits within California. A companion measure, AB 617, focused on improving local air quality by updating pollution controls at large industrial facilities in the cap-and-trade program and implementing community-based emission reduction programs in the most pollution-burdened communities.
At the same time, CEQA practice has demonstrated the feasibility of GHG mitigation plans that incorporate significant on-site and local direct GHG reduction measures, rather than relying entirely on offsets to mitigate projects' GHG emissions. For example, Newhall Ranch, a large project of over 20,000 homes and related development in Los Angeles County near Santa Clarita, was approved in 2017 once the developer committed to "achieve zero net GHG emissions using feasible and reliable emission-reduction actions related to the land development project, the implementation of direct measures to reduce GHG emissions offsite, and the procurement of GHG offsets." To achieve net zero GHG, 13 mitigation measures were adopted for Newhall Ranch, including on-site, off-site and offsets. In total, approximately 55 percent of the GHG reductions will come from on-site and local direct reduction measures, with the balance from offset projects, including some located in California.
This bill, along with AB 987 (Kamlager-Dove), specifically requires on-site and local direct GHG reduction measures, and imposes specific limits on the use of offsets, in CEQA statute for the first time.
- Opposition arguments. Judicial Council:
Providing expedited judicial review for the specific projects covered by AB 734 while other cases proceed under the usual civil procedure rules and timelines undermines equal access to justice. The courts are charged with dispensing equal access to justice for each and every case on their dockets. Singling out this particular type of case for such preferential treatment is fundamentally at odds with how our justice system has historically functioned, and is an injustice to all of the other litigants who have important cases pending before the courts.
- Related legislation. AB 987 (Kamlager-Dove) establishes similar procedures and conditions, and 270 day judicial review, for a proposed basketball arena and related development in the City of Inglewood.
- Assembly Rule 77.2. This bill has been referred to this committee pursuant to Assembly Rule 77.2 for review of substantial Senate amendments. It may not be amended and, if it passes, will be returned to the Assembly Floor for a final concurrence vote.
REGISTERED SUPPORT / OPPOSITION:
Support
Bay Area Council
California Lieutenant Governor Gavin Newsom
California State Association of Electrical Workers
California State Pipe Trades Council
California Teamsters Public Affairs Council
City of Berkeley
City of Emeryville
City of Oakland
City of San Leandro
Downtown Oakland & Lake Merritt-Uptown Community Benefit Districts
Jack London Improvement District
Non-Profit Housing Association of Northern California
Northern California Sheet Metal Workers’ Local Union No. 104
Oakland African American Chamber of Commerce
Oakland Chamber of Commerce
Oakland Chinatown Chamber of Commerce
Port of Oakland
Save Oakland Sports
State Building and Construction Trades Council of California
Western States Council of Sheet Metal Workers
1 Individual
Opposition
Judicial Council of California
Sierra Club California
Analysis Prepared by: Lawrence Lingbloom / NAT. RES. /
CONCURRENCE IN SENATE AMENDMENTS
CSA2 Bill Id:AB 734
Author:(Bonta and Thurmond)
As Amended Ver:August 28, 2018
Majority vote
ASSEMBLY: | 63-9 | (May 11, 2017) | SENATE: | 33-0 | (August 31, 2018) |
COMMITTEE VOTE: | 6-2 | (August 31, 2018) | RECOMMENDATION: | concur |
(Nat. Res.)
Original Committee Reference: L. GOV.
SUMMARY: Establishes special procedures for California Environmental Quality Act (CEQA) review, additional conditions for certification, and expedited (270 day) judicial review for a proposed baseball park and mixed-use development in the City of Oakland. Specifically, this bill:
- Applies to a project – consisting of a baseball park (proposed as the future home for the Oakland Athletics) and adjacent residential, retail, commercial, cultural, entertainment, or recreational uses located at the Howard Terminal (at the eastern edge of the Port of Oakland, near Jack London Square) – that meets the following conditions:
- The baseball park and other nonresidential buildings receive Leadership in Energy and Environmental Design (LEED) gold certification within one year of completion.
- Any residential buildings achieve sustainability standards of at least a LEED gold level or the comparable GreenPoint rating, including meeting sustainability standards for access to quality transit.
- The project does not result in any net additional greenhouse gas (GHG) emissions, including emissions from employee transportation, as determined by the Air Resources Board (ARB).
- Requires the lead agency, to maximize public health, environmental, and employment benefits, to require measures that will reduce GHG emissions in the project area and in the neighboring communities of the baseball park.
- Provides that not less than 50% of the GHG emissions reductions necessary to achieve zero net additional GHG emissions, excluding emissions from residential uses, shall be from local, direct GHG emissions reduction measures, including, but not limited to, any of the following:
- Project design features or onsite reduction measures, or both design features and onsite reduction measures.
- Off-site reduction measures in the neighboring communities.
- Permits the applicant to obtain offset credits for up to 50% of the GHG emissions reductions necessary to achieve zero net additional GHG emissions.
- Requires the applicant, to the extent feasible, to place the highest priority on the purchase of offset credits that produce emission reductions within the City of Oakland or the boundaries of the Bay Area Air Quality Management District.
- Requires any offset credits to be verified by a third party accredited by ARB.
- Prohibits the use of offset credits generated by a project located outside the United States.
- The project has a transportation management plan or transportation demand management program that achieves a 20% reduction in vehicle trips for the ballpark within one year of completion of the first baseball season and for each other portion of the projects within one year of completion of that portion.
- The project is located within a priority development area identified in the sustainable communities strategy Plan Bay Area 2040 adopted by the Metropolitan Transportation Commission and the Association of Bay Area Governments.
- The project is subject to a comprehensive package of community benefits approved by the Port of Oakland or the Oakland City Council.
- Requires the lead agency, as a condition of approval of the project, to require the applicant, with respect to any measures specific to the operation of the baseball park, to implement measures that will meet the requirements of CEQA by the end of the first baseball season.
- Provides that Rules of Court 3.2220 to 3.2237, adopted by the Judicial Council pursuant to AB 900 (Buchanan), Chapter 354, Statutes of 2011, apply to a lawsuit challenging the certification of the environmental impact report (EIR) or any project approvals for a certified project, requiring resolution of the lawsuit, including any appeals, within 270 days, to the extent feasible, of the filing of the certified record of proceedings with the court.
- Authorizes the Governor to certify the project for streamlining if all of the following conditions are met:
- The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment.
- Contractors and subcontractors pay to all construction workers employed in the execution of the project at least the general prevailing rate of per diem wages. Provides that this obligation may be enforced by the Labor Commissioner through the issuance of a civil wage and penalty assessment pursuant to relevant provisions of the Labor Code, unless all contractors and subcontractors performing work on the project are subject to a project labor agreement that requires the payment of prevailing wages and provides for enforcement through an arbitration procedure.
- The project applicant demonstrates compliance with the LEED, GHG neutrality, and trip reduction requirements listed above.
- The applicant demonstrates compliance with the requirement that generators of commercial solid waste and large amounts of organic waste arrange for recycling services for those materials.
- The project applicant has entered into a binding and enforceable agreement that all mitigation measures required under CEQA and any other environmental measures required by this bill shall be conditions of approval of the project, and those conditions will be fully enforceable by the lead agency or another agency designated by the lead agency. In the case of environmental mitigation measures and any other environmental measures required by this bill, the applicant agrees, as an ongoing obligation, that those measures will be monitored and enforced by the lead agency for the life of the obligation.
- The project applicant agrees to pay any additional costs incurred by the courts in hearing and deciding any case, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council.
- The project applicant agrees to pay the costs of preparing the administrative record for the project concurrent with review and consideration of the project pursuant to CEQA, in a form and manner specified by the lead agency for the project.
- Project design and implementation will comply with the City of Oakland's bird safety measures, as specified.
- Requires the Governor, prior to certifying the project, to make a determination that each of the conditions specified above has been met. These findings are not subject to judicial review.
- Provides that the guidelines issued for AB 900 apply to the extent they are applicable and do not conflict with specific requirements of this bill.
- Establishes special procedures for public participation in CEQA review of the project:
- Requires the project EIR to include a specified notice that the EIR is subject to the provisions of the section added by this bill.
- Requires the lead agency to conduct an informational workshop within 10 days of release of the Draft EIR and hold a public hearing within 10 days before close of the public comment period.
- Requires the lead agency and applicant to participate in nonbinding mediation with any party who submitted comments on the Draft EIR and requested mediation within five days of the close of the public comment period, with the cost to be paid by the applicant. Requires mediation to end within 35 days of the close of the public comment period.
- Requires the lead agency to adopt any measures agreed upon in mediation. Prohibits a commenter from raising an issue addressed by that measure in a lawsuit.
- Permits the lead agency to ignore written comments submitted after the close of the public comment period, with specified exceptions for materials addressing new information released after the close of the public comment period.
- Establishes specified requirements for preparation and certification of the administrative record for the project. Requires the lead agency to prepare the record concurrently with the administrative process, provide all EIR documents and comments in an electronic format (with the exception of certain copyright-protected documents), certify the record within five days of filing the notice of determination, provide the record to a party upon written request, and provide the record to the superior court within 10 days of the filing of a petition for review.
EXISTING LAW:
- CEQA requires lead agencies with the principal responsibility for carrying out or approving a proposed project to prepare a negative declaration, mitigated negative declaration, or EIR for this action, unless the project is exempt from CEQA (CEQA includes various statutory exemptions, as well as categorical exemptions in the CEQA guidelines).
- Authorizes judicial review of CEQA actions taken by public agencies, following the agency's decision to carry out or approve the project. Challenges alleging improper determination that a project may have a significant effect on the environment, or alleging an EIR doesn't comply with CEQA, must be filed in the Superior Court within 30 days of filing of the notice of approval. The courts are required to give CEQA actions preference over all other civil actions.
- Pursuant to AB 900, establishes procedures for expedited judicial review (i.e., requiring the courts to resolve lawsuits within 270 days, to the extent feasible) for "environmental leadership" projects certified by the Governor and meeting specified conditions, including LEED gold-certified infill site projects achieving transportation efficiency 15% greater than comparable projects and zero net additional GHG emissions. AB 900 sunsets January 1, 2021.
FISCAL EFFECT: According to the Senate Appropriations Committee, this bill would have a fiscal impact of $172,000 (various funds) for ARB to evaluate the project with respect to whether it will result in a net increase of GHG emissions, minor and absorbable costs for Judicial Council to review and revise the rules of the court to meet the requirements of this bill and minor and absorbable costs for the Office of Planning and Research to process a judicial streamlining request.
COMMENTS:
- Author's statement:
The Oakland A's have called the City of Oakland home for the last fifty years. With the impending loss of the Raiders to Las Vegas and the Golden State Warriors to San Francisco, it's critically important to the city and entire East Bay region to retain a professional sports team. AB 734 is modeled closely on the legislation previously enacted for the Sacramento Kings and other environmental leadership projects under AB 900 by expediting judicial review for the adjudication of legal challenges within 270 days to the extent feasible. This will help provide certainty to the city and the Oakland A's who have made a public commitment to staying in Oakland. Currently, the team is evaluating two potential sites to build a new, privately financed, state of the art ballpark and ancillary development that will bring thousands of jobs while providing a significant economic boost to the region. However, the benefits of this bill will only apply to the Howard Terminal site.
- Background. CEQA provides a process for evaluating the environmental effects of applicable projects undertaken or approved by public agencies. If a project is not exempt from CEQA, an initial study is prepared to determine whether the project may have a significant effect on the environment. If the initial study shows that there would not be a significant effect on the environment, the lead agency must prepare a negative declaration. If the initial study shows that the project may have a significant effect on the environment, the lead agency must prepare an EIR.
Generally, an EIR must accurately describe the proposed project, identify and analyze each significant environmental impact expected to result from the proposed project, identify mitigation measures to reduce those impacts to the extent feasible, and evaluate a range of reasonable alternatives to the proposed project. If mitigation measures are required or incorporated into a project, the agency must adopt a reporting or monitoring program to ensure compliance with those measures.
CEQA actions taken by public agencies can be challenged in Superior Court once the agency approves or determines to carry out the project. CEQA appeals are subject to unusually short statutes of limitations. Under current law, court challenges of CEQA decisions generally must be filed within 30 to 35 days, depending on the type of decision. The courts are required to give CEQA actions preference over all other civil actions. The petitioner must request a hearing within 90 days of filing the petition and, generally, briefing must be completed within 90 days of the request for hearing. There is no deadline specified for the court to render a decision.
In 2011, AB 900 and SB 292 (Padilla), Chapter 353, Statutes of 2011, established expedited CEQA judicial review procedures for a limited number of projects. For AB 900, it was large-scale projects meeting extraordinary environmental standards and providing significant jobs and investment. For SB 292, it was a proposed downtown Los Angeles football stadium and convention center project achieving specified traffic and air quality mitigations. For these eligible projects, the bills provided for original jurisdiction by the Court of Appeal and a compressed schedule requiring the court to render a decision on any lawsuit within 175 days. This promised to reduce the existing judicial review timeline by 100 days or more, while creating new burdens for the courts and litigants to meet the compressed schedule. AB 900's provision granting original jurisdiction to the Court of Appeal was invalidated in 2013 by a decision in Alameda Superior Court in Planning and Conservation League v. State of California. AB 900 was subsequently revised to restore jurisdiction to superior courts and require resolution of lawsuits within 270 days.
Only two projects have used the judicial review procedures enacted since 2011: the Sacramento Kings arena project under SB 743 (Steinberg), Chapter 386, Statutes of 2013; and the Golden State Warriors arena project in San Francisco under AB 900. CEQA lawsuits were filed against both projects, and the lawsuits, including appeals, were resolved, in favor of the applicants, within the 270-day timeline.
To date, 11 projects have been certified under AB 900:
- 0
- Comparison to AB 900. This bill is substantially equivalent to AB 900 on key requirements – including LEED gold certification, GHG neutrality, traffic efficiency, and construction wages – with the following exceptions:
- LEED – This bill permits alternatives to LEED gold certification for the residential buildings in the project. A residential building must achieve sustainability standards of at least a LEED gold level or the comparable GreenPoint rating.
- GHG neutrality – This bill imposes additional conditions, requiring 50% of GHG reductions necessary to meet GHG neutrality, excluding residential uses, to come from on-site and local reduction measures, and limiting the use of offsets.
- Traffic efficiency – This bill requires a 20% reduction in vehicle trips for the ballpark within one year of completion of the first baseball season and for each other portion of the projects within one year of completion of that portion.
- Bill raises the bar on GHG mitigation and clean air. Following the enactment of AB 32 in 2006, SB 97 was enacted in 2007 to confirm the requirement to address environmental impacts of GHG emissions under CEQA and require the adoption of CEQA Guidelines for the mitigation of GHG emissions or the effects of GHG emissions, including effects associated with transportation or energy consumption. SB 97 requires the CEQA Guidelines to be periodically updated to incorporate new information or criteria established by ARB pursuant to AB 32.
Under CEQA Guidelines adopted pursuant to SB 97, a project's GHG emissions can be reduced by "off-site measures, including offsets that are not otherwise required" and "measures that sequester greenhouse gases." The CEQA Guidelines allow projects to reduce GHG emissions by relying on voluntary market offsets that are not otherwise required as well as other offsite and sequestration measures that result in GHG reductions.
When it was enacted in 2011, AB 900 required projects to achieve GHG neutrality, without specifying how. In practice, the AB 900 projects have relied heavily on voluntary offsets. Meanwhile, California's climate policy has focused increasingly on achieving local clean air co-benefits and reducing the reliance on offsets. Last year, the Legislature's extension of the cap-and-trade program, AB 398, included a reduction in total amount of offsets that may be used for compliance, coupled with a requirement that at least half of offsets result in environmental benefits within California. A companion measure, AB 617, focused on improving local air quality by updating pollution controls at large industrial facilities in the cap-and-trade program and implementing community-based emission reduction programs in the most pollution-burdened communities.
At the same time, CEQA practice has demonstrated the feasibility of GHG mitigation plans that incorporate significant on-site and local direct GHG reduction measures, rather than relying entirely on offsets to mitigate projects' GHG emissions. For example, Newhall Ranch, a large project of over 20,000 homes and related development in Los Angeles County near Santa Clarita, was approved in 2017 once the developer committed to "achieve zero net GHG emissions using feasible and reliable emission-reduction actions related to the land development project, the implementation of direct measures to reduce GHG emissions offsite, and the procurement of GHG offsets." To achieve net zero GHG, 13 mitigation measures were adopted for Newhall Ranch, including on-site, off-site and offsets. In total, approximately 55% of the GHG reductions will come from on-site and local direct reduction measures, with the balance from offset projects, including some located in California.
This bill, along with AB 987 (Kamlager-Dove), specifically requires on-site and local direct GHG reduction measures, and imposes specific limits on the use of offsets, in CEQA statute for the first time.
- Opposition arguments. Judicial Council:
Providing expedited judicial review for the specific projects covered by AB 734 while other cases proceed under the usual civil procedure rules and timelines undermines equal access to justice. The courts are charged with dispensing equal access to justice for each and every case on their dockets. Singling out this particular type of case for such preferential treatment is fundamentally at odds with how our justice system has historically functioned, and is an injustice to all of the other litigants who have important cases pending before the courts.
- Related legislation. AB 987 (Kamlager-Dove) establishes similar procedures and conditions, and 270 day judicial review, for a proposed basketball arena and related development in the City of Inglewood.
Analysis Prepared by: Lawrence Lingbloom / NAT. RES. / (916) 319-2092 FN: 0005228
Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | AB |
THIRD READING
Bill No: AB 734
Author: and Thurmond (D), et al.
: 8/28/18
SENATE ENVIRONMENTAL QUALITY COMMITTEE: 7-0, 6/20/18
AYES: Wieckowski, Stone, Gaines, Hill, Lara, Skinner, Stern
SENATE JUDICIARY COMMITTEE: 5-1, 6/26/18
AYES: Jackson, Anderson, Hertzberg, Stern, Wieckowski
NOES: Moorlach
NO VOTE RECORDED: Monning
SENATE APPROPRIATIONS COMMITTEE: 7-0, 8/16/18
AYES: Portantino, Bates, Beall, Bradford, Hill, Nielsen, Wiener
ASSEMBLY FLOOR: 63-9, 5/11/17 - See last page for vote
SUBJECT: California Environmental Quality Act: Oakland Sports and Mixed-Use Project
DIGEST:
This bill establishes procedures specific to the Oakland Sports and Mixed-Use Project in the City of Oakland that provide expedited administrative and judicial review procedures.
ANALYSIS:
Existing law, under the California Environmental Quality Act (CEQA):
- Requires lead agencies with the principal responsibility for carrying out or approving a proposed discretionary project to prepare a negative declaration, mitigated declaration, or environmental impact report (EIR) for this action, unless the project is exempt from CEQA (CEQA includes various statutory exemptions, as well as categorical exemptions in the CEQA guidelines). (Public Resources Code (PRC) §21000 et seq.).
- Requires courts to give CEQA-related actions or proceedings preference over all other civil actions so that the action or proceeding is quickly heard and determined. (PRC §21167.1).
- Establishes, under the Jobs and Economic Improvement Through Environmental Leadership Act of 2011 (AB 900, Buchanan and Gordon, Chapter 354, Statutes of 2011) (AB 900), CEQA administrative and judicial review procedures for an “environmental leadership development project.” (PRC §21178 et seq.).
- Establishes procedures for expedited judicial review (i.e., requiring the courts to resolve lawsuits within 270 days) for “environmental leadership” projects certified by the Governor and meeting specified conditions, including Leadership in Energy and Environmental Design (LEED) gold-certified infill site projects, clean renewable energy projects, and clean energy manufacturing projects.
- Defines “environmental leadership” project as a CEQA project.
- Authorizes the Governor to certify a leadership project if the Governor finds the project meets all of the specified conditions.
- Requires the Governor, prior to certifying a project, to make a determination that each of the conditions specified above has been met. These findings are not subject to judicial review.
- If the Governor determines that a leadership project is eligible for streamlining, requires the Governor to submit that determination, and any supporting information, to the Joint Legislative Budget Committee (JLBC) for review and concurrence or non-concurrence.
- Requires the JLBC to concur or non-concur in writing within 30 days of receiving the Governor’s determination.
- Deems the leadership project certified if the JLBC fails to concur or non-concur on a determination by the Governor within 30 days of the submittal.
- Authorizes the Governor to issue guidelines regarding application and certification of projects pursuant to AB 900. These guidelines are not subject to the rulemaking provisions of the Administrative Procedure Act.
- Requires the Judicial Council to adopt a rule of court to establish procedures that require resolution within 270 days, including any appeals, of a lawsuit challenging the certification of the EIR or any project approvals for a certified environmental leadership project.
- Prohibits AB 900 from applying to a leadership project if the applicant fails to notify a lead agency prior to the release of the draft EIR for public comment.
- Sets requirements for preparation and certification of the record of proceeding for a leadership project certified by the Governor.
- Requires the draft and final EIR to include a specified notice in no less than 12-point type regarding the draft and final EIR being subject to AB 900.
- Provides that provisions of AB 900 are severable.
- Provides that nothing in AB 900 affects the duty of any party to comply with CEQA, except as otherwise provided in AB 900.
- Prohibits AB 900 from applying to a leadership project if the Governor does not certify the project prior to January 1, 2020.
- Provides that certification of the leadership project expires and is no longer valid if the lead agency fails to approve the project prior to January 1, 2021.
This bill:
- Establishes specified administrative and judicial review procedures for the administrative and judicial review of the EIR and approvals granted for a project related to the development of a “Oakland Sports and Mixed-Use Project” in the City of Oakland meeting certain requirements.
- Defines “Oakland Sports and Mixed-Use Project” or “project” as the following components of a sports center and mixed-use project located at the Howard Terminal site in the City of Oakland from demolition and site preparation through operation:
- A baseball park that will become the new home to the Oakland Athletics and adjacent residential, retail, commercial, cultural, entertainment, or recreational uses developed by the Oakland Athletics, that meets all the following:
- The baseball park receives LEED Gold certification for new construction within one year after completion of the first baseball season and each new nonresidential building receives LEED Gold certification for new construction within one year after completion. Any residential building shall achieve sustainability standards of at least a LEED Gold level or the comparable GreenPoint rating, including meeting sustainability standards for access to quality transit.
- The project does not result in any net additional emissions of greenhouse gases, as specified by the California Air Resources Board (ARB), requires 50% of the greenhouse gas emissions reductions required be achieved from local direct measures and allows the applicant to achieve up to 50% of the greenhouse gas emissions reductions necessary through offset credits within the United States as specified.
- The project has a transportation management plan or transportation demand management program that achieves a 20% reduction in the number of vehicle trips compared to operations absent the plan or program, as specified.
- Requires that these projects be located on an infill site.
- Requires the project is located within a priority development area identified in the sustainable communities strategy Plan Bay Area 2040 adopted by the Metropolitan Transportation Commission and the Association of Bay Area Governments.
- Requires that the project is subject to a comprehensive package of community benefits approved by the Port of Oakland or City Council of the City of Oakland.
- Associated public spaces.
- Facilities and infrastructure for ingress, egress, and use of the baseball park and mixed-use development.
- A baseball park that will become the new home to the Oakland Athletics and adjacent residential, retail, commercial, cultural, entertainment, or recreational uses developed by the Oakland Athletics, that meets all the following:
- Provides, as a condition of approval of the project, the lead agency shall require the applicant to implement measures that will meet these requirements.
- Requires, on or before July 1, 2019, the Judicial Council adopt a rule of court to establish procedures applicable to actions or proceedings brought to attack, review, set aside, void, or annul the certification or adoption of the environmental review document for the Oakland Sports and Mixed-Use Project that is certified by the Governor pursuant to this bill or the granting of any project approvals that require the actions or proceedings, including any potential appeals therefrom, be resolved, to the extent feasible, within 270 days of the filing of the certified record of proceedings with the court.
- Provides that the Governor may certify the project for streamlining if specified conditions are met including:
- The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages.
- The project applicant demonstrates compliance with mitigation measures, to the extent feasible to reduce any additional greenhouse gas emissions from the project.
- Requires a project applicant to demonstrate compliance with the requirement that generators of commercial solid waste and large amounts of organic waste arrange for recycling services for those materials.
- The project applicant has entered into a binding and enforceable agreement that all mitigation measures required to certify the project shall be conditions of approval of the project.
- The project applicant agrees to pay for any additional costs occurred by the courts in any case brought pursuant to this bill.
- Project design will comply with the City of Oakland’s Bird Safety Measures.
Background
Previous, Related Bills for Large Projects
- AB 900 and SB 292. AB 900 (Buchanan and Gordon, Chapter 354, Statutes of 2011) and SB 292 (Padilla, Chapter 353, Statutes of 2011) established expedited CEQA judicial review procedures for a limited number of projects. For AB 900, it was large-scale projects meeting extraordinary environmental standards and providing significant jobs and investment. For SB 292, it was a proposed downtown Los Angeles football stadium and convention center project achieving specified traffic and air quality mitigations. The stadium project subject to SB 292 has not proceeded.
For these eligible projects, the bills provided for original jurisdiction by the Court of Appeal and a compressed schedule requiring the court to render a decision on any lawsuit within 175 days. This promised to reduce the existing judicial review timeline by 100 days or more, while creating new burdens for the courts and litigants to meet the shortened schedule.
AB 900’s provision granting original jurisdiction to the Court of Appeal was invalidated in 2013 by a decision in Alameda Superior Court in Planning and Conservation League v. State of California.
- SB 743. Subsequent to the Alameda Superior Court holding mentioned above, SB 743 (Steinberg, Chapter 386, Statutes of 2013) repealed the provision that gave original jurisdiction to the Court of Appeal and required Judicial Council to adopt a rule of court mandating lawsuits and any appeals to be resolved within 270 days.
Also, SB 743 established special CEQA procedures modeled on SB 292 for the Sacramento Kings arena project. Like SB 292, SB 743 applied to a single project and included specified traffic and air quality mitigations. CEQA lawsuits were filed against the Kings arena, and the lawsuits, including appeals, were resolved 267 days after certification of the record.
Comments
- Purpose of the bill. According to the author, “The Oakland A’s have called the City of Oakland home for the last fifty years. With the impending loss of the Raiders to Las Vegas and the Golden State Warriors to San Francisco it’s critically important to the city and entire East Bay region to retain a professional sports team.
“AB 734 is modeled closely on the legislation previously enacted for the Sacramento Kings and other environmental leadership projects under AB 900 by expediting judicial review for the adjudication of legal challenges within 270 days to the extent feasible.
“This will help provide certainty to the city and the Oakland A’s who have made a public commitment to staying in Oakland. Currently, the team is evaluating two potential sites to build a new, privately financed, state of the art ballpark that will bring thousands of jobs while providing a significant economic boost to the region. A study by the Bay Area Council Economic Institute in June 2017 estimated that a new ballpark would generate $3.05 billion of economic impact for the residents and businesses of the City of Oakland over the first ten years of operation.”
- Litigation shot clock. This bill provides for expedited judicial review procedures under CEQA for a proposed project within the City of Oakland.
- This bill does not guarantee all lawsuits on a project will be resolved within 270 days. Example: Golden State Warriors Arena and two lawsuits. One project subject to the AB 900 expedited judicial process is the Golden State Warriors Arena and related development at Mission Bay in San Francisco has been challenged under CEQA. One of the plaintiffs, Mission Bay Alliance, which is a coalition of University of California, San Francisco (UCSF) stakeholders, donors, faculty, and physicians, argued that the 18,500-seat arena would congest area streets with traffic, slowing down access to the UCSF Medical Center at Mission Bay, which is located across the street from the proposed arena. In addition, the plaintiff contended that the basketball arena in Mission Bay is at odds with the cluster of life science research and health care facilities that have been built in the neighborhood.
The case, Mission Bay Alliance et al. v Office of Community Investment and Infrastructure, was initially filed on January 7, 2016, in Sacramento County Superior Court. The Golden State Warriors moved for a change of venue and on February 3, 2016, the Sacramento Superior Court granted this request. On March 11, 2016, the CEQA case was received and filed in the San Francisco County Superior Court. On July 18, 2016, a trial court ruled in favor of the project sponsor, the Warriors. On November 29, 2016, the Court of Appeal issued its decision on the case, 327 days after the petition was initially filed. The decision was appealed; and ultimately, in January 2017, the California Supreme Court declined to hear the case.
In a second lawsuit, filed in Alameda County, the plaintiffs seek to invalidate an agreement between UCSF and the Warriors, which included a $10 million Mission Bay Transportation Improvement Fund for controlling traffic flow in the area. The plaintiffs contend that the UCSF Chancellor went beyond his authority in reaching this agreement without UC Regents approval. Although the CEQA case had concluded as of January, 2017, the second, non-CEQA-related case in Alameda was still pending at that time.
The Warriors team has stated that the lawsuits have delayed the opening of the arena by one year, to 2019. One lawsuit had special, fast-tracking CEQA-related litigation privileges and the other does not. Although AB 900 expedited the litigation process for the CEQA case, the second lawsuit demonstrates that CEQA is not the only body of law subject to civil litigation and that AB 900 does not guarantee a project from being litigation-free after 270 days. Rather, there is a cavalry of non-CEQA-related causes of action from which a plaintiff may choose and that are subject to standard civil procedure rules.
As demonstrated above, a special CEQA litigation process cannot expedite or insulate a project from non-CEQA-related litigation and cannot ensure that a project will be completed faster.
- Equal justice for all? Court calendar preference and guaranteed time frames. Current law requires the courts to give CEQA-related cases preference over “all other civil actions… so that the action or proceeding shall be quickly heard and determined.” (PRC §21167.1). In addition to this existing mandate, SB 734 provides that the courts must complete the judicial review process in a given time frame for certain CEQA-related actions or proceedings when specified criteria are met.
As a consequence, such mandates on a court delay access for other cases as well as potentially exacerbating a court’s backlog on civil documents such as filing a new civil complaint, processing answers and cross complaints, or processing a demurrer or summary judgment. As Judicial Council notes, “[S]etting an extremely tight timeline for deciding these cases has the practical effect of pushing other cases on the courts’ dockets to the back of the line. This means that other cases, including cases that have statutorily mandated calendar preferences, such as juvenile cases, criminal cases, and civil cases in which a party is at risk of dying, will take longer to decide.”
FISCAL EFFECT: Appropriation: Fiscal Com.: Local:
According to the Senate Appropriations Committee, this bill would have a fiscal impact of $172,000 (various funds) for the California Air Resources Board to evaluate the project with respect to whether it will result in a net increase of greenhouse gas emissions, minor and absorbable costs for Judicial Council to review and revise the rules of the court to meet the requirements of this bill and minor and absorbable costs for the Office of Planning and Research to process a judicial streamlining request.
City of Oakland (source)
Bay Area Council
Berkeley Mayor, Jesse Arreguin
California State Association of Electrical Workers
California State Pipe Trades Council
City of Emeryville
Downtown Oakland & Lake Merritt-Uptown Community Benefit Districts
Jack London Improvement District
Oakland African American Chamber of Commerce
Oakland Chinatown Chamber of Commerce
Oakland Metropolitan Chamber of Commerce
Port of Oakland
San Leandro Mayor, Pauline Cutter
Save Oakland Sports
State Building and Construction Trades Council of California
Teamsters Public Affairs Council
Western States Council of Sheet Metal Workers
OPPOSITION: (Verified 8/16/18)
Judicial Council of California
Sierra Club California
ASSEMBLY FLOOR: 63-9, 5/11/17
AYES: Aguiar-Curry, Arambula, Baker, Berman, Bloom, Bocanegra, Bonta, Burke, Caballero, Calderon, Cervantes, Chau, Chen, Chiu, Choi, Chu, Cooley, Cooper, Cunningham, Dababneh, Daly, Eggman, Flora, Frazier, Friedman, Cristina Garcia, Eduardo Garcia, Gipson, Gloria, Gomez, Gonzalez Fletcher, Gray, Grayson, Holden, Irwin, Jones-Sawyer, Kalra, Lackey, Levine, Limón, Low, Maienschein, McCarty, Medina, Mullin, Muratsuchi, Nazarian, Obernolte, Quirk, Reyes, Ridley-Thomas, Rodriguez, Rubio, Salas, Santiago, Steinorth, Mark Stone, Thurmond, Ting, Voepel, Weber, Wood, Rendon
NOES: Travis Allen, Brough, Chávez, Harper, Mathis, Mayes, Melendez, Quirk-Silva, Waldron
NO VOTE RECORDED: Acosta, Bigelow, Dahle, Fong, Gallagher, Kiley, O'Donnell, Patterson
8/29/18 23:33:26
**** END ****
Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | AB |
THIRD READING
Bill No: AB 734
: 8/21/18
SENATE ENVIRONMENTAL QUALITY COMMITTEE: 7-0, 6/20/18
AYES: Wieckowski, Stone, Gaines, Hill, Lara, Skinner, Stern
SENATE JUDICIARY COMMITTEE: 5-1, 6/26/18
AYES: Jackson, Anderson, Hertzberg, Stern, Wieckowski
NOES: Moorlach
NO VOTE RECORDED: Monning
SENATE APPROPRIATIONS COMMITTEE: 7-0, 8/16/18
AYES: Portantino, Bates, Beall, Bradford, Hill, Nielsen, Wiener
ASSEMBLY FLOOR: 63-9, 5/11/17 - See last page for vote
DIGEST:
This bill establishes procedures specific to the Oakland Sports and Mixed-Use Project in the City of Oakland that would provide expedited administrative and judicial review procedures.
ANALYSIS:
Existing law, under the California Environmental Quality Act (CEQA):
- Requires lead agencies with the principal responsibility for carrying out or approving a proposed discretionary project to prepare a negative declaration, mitigated declaration, or environmental impact report (EIR) for this action, unless the project is exempt from CEQA (CEQA includes various statutory exemptions, as well as categorical exemptions in the CEQA guidelines). (Public Resources Code (PRC) §21000 et seq.).
- Requires courts to give CEQA-related actions or proceedings preference over all other civil actions so that the action or proceeding is quickly heard and determined. (PRC §21167.1).
- Establishes, under the Jobs and Economic Improvement Through Environmental Leadership Act of 2011 (AB 900, Buchanan, Gordon, Chapter 354, Statutes of 2011) (AB 900), CEQA administrative and judicial review procedures for an “environmental leadership development project.” (PRC §21178 et seq.).
- Establishes procedures for expedited judicial review (i.e., requiring the courts to resolve lawsuits within 270 days) for “environmental leadership” projects certified by the Governor and meeting specified conditions, including Leadership in Energy and Environmental Design (LEED) gold-certified infill site projects, clean renewable energy projects, and clean energy manufacturing projects.
- Defines “environmental leadership” project as a CEQA project.
- Authorizes the Governor to certify a leadership project if the Governor finds the project meets all of the specified conditions.
- Requires the Governor, prior to certifying a project, to make a determination that each of the conditions specified above has been met. These findings are not subject to judicial review.
- If the Governor determines that a leadership project is eligible for streamlining, requires the Governor to submit that determination, and any supporting information, to the Joint Legislative Budget Committee (JLBC) for review and concurrence or non-concurrence.
- Requires the JLBC to concur or non-concur in writing within 30 days of receiving the Governor’s determination.
- Deems the leadership project certified if the JLBC fails to concur or non-concur on a determination by the Governor within 30 days of the submittal.
- Authorizes the Governor to issue guidelines regarding application and certification of projects pursuant to AB 900. These guidelines are not subject to the rulemaking provisions of the Administrative Procedure Act.
- Requires the Judicial Council to adopt a rule of court to establish procedures that require resolution within 270 days, including any appeals, of a lawsuit challenging the certification of the EIR or any project approvals for a certified environmental leadership project.
- Prohibits AB 900 from applying to a leadership project if the applicant fails to notify a lead agency prior to the release of the draft EIR for public comment.
- Sets requirements for preparation and certification of the record of proceeding for a leadership project certified by the Governor.
- Requires the draft and final EIR to include a specified notice in no less than 12-point type regarding the draft and final EIR being subject to AB 900.
- Provides that provisions of AB 900 are severable.
- Provides that nothing in AB 900 affects the duty of any party to comply with CEQA, except as otherwise provided in AB 900.
- Prohibits AB 900 from applying to a leadership project if the Governor does not certify the project prior to January 1, 2020.
- Provides that certification of the leadership project expires and is no longer valid if the lead agency fails to approve the project prior to January 1, 2021.
- Establishes procedures for expedited judicial review (i.e., requiring the courts to resolve lawsuits within 270 days) for “environmental leadership” projects certified by the Governor and meeting specified conditions, including Leadership in Energy and Environmental Design (LEED) gold-certified infill site projects, clean renewable energy projects, and clean energy manufacturing projects.
This bill:
- Establishes specified administrative and judicial review procedures for the administrative and judicial review of the EIR and approvals granted for a project related to the development of a “Oakland Sports and Mixed-Use Project” in the City of Oakland meeting certain requirements.
- Defines “Oakland Sports and Mixed-Use Project” or “project” as the following components of a sports center and mixed-use project located at the Howard Terminal site in the City of Oakland or the Oakland-Alameda County Coliseum site in the City of Oakland, from demolition and site preparation through operation:
- A baseball park that will become the new home to the Oakland Athletics and adjacent residential, retail, commercial, cultural, entertainment, or recreational uses developed by the Oakland Athletics, as specified.
- Associated public spaces.
- Facilities and infrastructure for ingress, egress, and use of the baseball park and mixed-use development.
- Requires, on or before July 1, 2019, the Judicial Council adopt a rule of court to establish procedures applicable to actions or proceedings brought to attack, review, set aside, void, or annul the certification or adoption of the environmental review document for the Oakland Sports and Mixed-Use Project that is certified by the Governor pursuant to this section or the granting of any project approvals that require the actions or proceedings, including any potential appeals therefrom, be resolved, to the extent feasible, within 270 days of the filing of the certified record of proceedings with the court.
- Provides that the Governor may certify the project for streamlining if specified conditions are met.
Background
- Previous, related bills for large projects.
- AB 900 and SB 292. AB 900 (Buchanan, Gordon, Chapter 354, Statutes of 2011) and SB 292 (Padilla, Chapter 353, Statutes of 2011) established expedited CEQA judicial review procedures for a limited number of projects. For AB 900, it was large-scale projects meeting extraordinary environmental standards and providing significant jobs and investment. For SB 292, it was a proposed downtown Los Angeles football stadium and convention center project achieving specified traffic and air quality mitigations. The stadium project subject to SB 292 has not proceeded.
For these eligible projects, the bills provided for original jurisdiction by the Court of Appeal and a compressed schedule requiring the court to render a decision on any lawsuit within 175 days. This promised to reduce the existing judicial review timeline by 100 days or more, while creating new burdens for the courts and litigants to meet the shortened schedule.
AB 900’s provision granting original jurisdiction to the Court of Appeal was invalidated in 2013 by a decision in Alameda Superior Court in Planning and Conservation League v. State of California. - SB 743 (Steinberg, Chapter 386, Statutes of 2013). Subsequent to the Alameda Superior Court holding mentioned above, SB 743 repealed the provision that gave original jurisdiction to the Court of Appeal and required Judicial Council to adopt a rule of court mandating lawsuits and any appeals to be resolved within 270 days.
Also, SB 743 established special CEQA procedures modeled on SB 292 for the Sacramento Kings arena project. Like SB 292, SB 743 applied to a single project and included specified traffic and air quality mitigations. CEQA lawsuits were filed against the Kings arena, and the lawsuits, including appeals, were resolved 267 days after certification of the record.
- AB 900 and SB 292. AB 900 (Buchanan, Gordon, Chapter 354, Statutes of 2011) and SB 292 (Padilla, Chapter 353, Statutes of 2011) established expedited CEQA judicial review procedures for a limited number of projects. For AB 900, it was large-scale projects meeting extraordinary environmental standards and providing significant jobs and investment. For SB 292, it was a proposed downtown Los Angeles football stadium and convention center project achieving specified traffic and air quality mitigations. The stadium project subject to SB 292 has not proceeded.
Comments
- Purpose of the bill. According to the author, “The Oakland A’s have called the City of Oakland home for the last fifty years. With the impending loss of the Raiders to Las Vegas and the Golden State Warriors to San Francisco it’s critically important to the city and entire East Bay region to retain a professional sports team.
AB 734 is modeled closely on the legislation previously enacted for the Sacramento Kings and other environmental leadership projects under AB 900 by expediting judicial review for the adjudication of legal challenges within 270 days to the extent feasible.
This will help provide certainty to the city and the Oakland A’s who have made a public commitment to staying in Oakland. Currently, the team is evaluating two potential sites to build a new, privately financed, state of the art ballpark that will bring thousands of jobs while providing a significant economic boost to the region. A study by the Bay Area Council Economic Institute in June 2017 estimated that a new ballpark would generate $3.05 billion of economic impact for the residents and businesses of the City of Oakland over the first ten years of operation.”
- Litigation shot clock. This bill provides for expedited judicial review procedures under CEQA for a proposed project within the City of Oakland.
- This bill does not guarantee all lawsuits on a project will be resolved within 270 days. Example: Golden State Warriors Arena and two lawsuits. One project subject to the AB 900 expedited judicial process is the Golden State Warriors Arena and related development at Mission Bay in San Francisco has been challenged under CEQA. One of the plaintiffs, Mission Bay Alliance, which is a coalition of University of California, San Francisco (UCSF) stakeholders, donors, faculty, and physicians, argued that the 18,500-seat arena would congest area streets with traffic, slowing down access to the UCSF Medical Center at Mission Bay, which is located across the street from the proposed arena. In addition, the plaintiff contended that the basketball arena in Mission Bay is at odds with the cluster of life science research and health care facilities that have been built in the neighborhood.
The case, Mission Bay Alliance et al. v Office of Community Investment and Infrastructure, was initially filed on January 7, 2016, in Sacramento County Superior Court. The Golden State Warriors moved for a change of venue and on February 3, 2016 the Sacramento Superior Court granted this request. On March 11, 2016, the CEQA case was received and filed in the San Francisco County Superior Court. On July 18, 2016, a trial court ruled in favor of the project sponsor, the Warriors. On November 29, 2016, the Court of Appeal issued its decision on the case, 327 days after the petition was initially filed. The decision was appealed; and ultimately, in January 2017, the California Supreme Court declined to hear the case.
In a second lawsuit, filed in Alameda County, the plaintiffs seek to invalidate an agreement between UCSF and the Warriors, which included a $10 million Mission Bay Transportation Improvement Fund for controlling traffic flow in the area. The plaintiffs contend that the UCSF Chancellor went beyond his authority in reaching this agreement without UC Regents approval. Although the CEQA case had concluded as of January, 2017, the second, non-CEQA-related case in Alameda was still pending at that time.
The Warriors team has stated that the lawsuits have delayed the opening of the arena by one year, to 2019. One lawsuit had special, fast-tracking CEQA-related litigation privileges and the other does not. Although AB 900 expedited the litigation process for the CEQA case, the second lawsuit demonstrates that CEQA is not the only body of law subject to civil litigation and that AB 900 does not guarantee a project from being litigation-free after 270 days. Rather, there is a cavalry of non-CEQA-related causes of action from which a plaintiff may choose and that are subject to standard civil procedure rules.
As demonstrated above, a special CEQA litigation process cannot expedite or insulate a project from non-CEQA-related litigation and cannot ensure that a project will be completed faster. - Equal justice for all? Court calendar preference and guaranteed time frames. Current law requires the courts to give CEQA-related cases preference over “all other civil actions… so that the action or proceeding shall be quickly heard and determined.” (PRC §21167.1). In addition to this existing mandate, SB 734 provides that the courts must complete the judicial review process in a given time frame for certain CEQA-related actions or proceedings when specified criteria are met.
As a consequence, such mandates on a court delay access for other cases as well as potentially exacerbating a court’s backlog on civil documents such as filing a new civil complaint, processing answers and cross complaints, or processing a demurrer or summary judgment. As Judicial Council notes, “[S]etting an extremely tight timeline for deciding these cases has the practical effect of pushing other cases on the courts’ dockets to the back of the line. This means that other cases, including cases that have statutorily mandated calendar preferences, such as juvenile cases, criminal cases, and civil cases in which a party is at risk of dying, will take longer to decide.”
- This bill does not guarantee all lawsuits on a project will be resolved within 270 days. Example: Golden State Warriors Arena and two lawsuits. One project subject to the AB 900 expedited judicial process is the Golden State Warriors Arena and related development at Mission Bay in San Francisco has been challenged under CEQA. One of the plaintiffs, Mission Bay Alliance, which is a coalition of University of California, San Francisco (UCSF) stakeholders, donors, faculty, and physicians, argued that the 18,500-seat arena would congest area streets with traffic, slowing down access to the UCSF Medical Center at Mission Bay, which is located across the street from the proposed arena. In addition, the plaintiff contended that the basketball arena in Mission Bay is at odds with the cluster of life science research and health care facilities that have been built in the neighborhood.
FISCAL EFFECT: Appropriation: Fiscal Com.: Local:
According to the Senate Appropriations Committee, this bill would have a fiscal impact of $172,000 (various funds) for the California Air Resources Board (CARB) to evaluate the project with respect to whether it will result in a net increase of greenhouse gas emissions, minor and absorbable costs for Judicial Council to review and revise the rules of the court to meet the requirements of this bill and minor and absorbable costs for the Office of Planning and Research to process a judicial streamlining request.
City of Oakland (source)
Bay Area Council
Berkeley Mayor, Jesse Arreguin
California State Association of Electrical Workers
California State Pipe Trades Council
City of Emeryville
Downtown Oakland & Lake Merritt-Uptown Community Benefit Districts
Jack London Improvement District
Oakland African American Chamber of Commerce
Oakland Chinatown Chamber of Commerce
Oakland Metropolitan Chamber of Commerce
Port of Oakland
San Leandro Mayor, Pauline Cutter
Save Oakland Sports
State Building and Construction Trades Council of California
Teamsters Public Affairs Council
Western States Council of Sheet Metal Workers
OPPOSITION: (Verified 8/16/18)
Judicial Council of California
Sierra Club California
ASSEMBLY FLOOR: 63-9, 5/11/17
AYES: Aguiar-Curry, Arambula, Baker, Berman, Bloom, Bocanegra, Bonta, Burke, Caballero, Calderon, Cervantes, Chau, Chen, Chiu, Choi, Chu, Cooley, Cooper, Cunningham, Dababneh, Daly, Eggman, Flora, Frazier, Friedman, Cristina Garcia, Eduardo Garcia, Gipson, Gloria, Gomez, Gonzalez Fletcher, Gray, Grayson, Holden, Irwin, Jones-Sawyer, Kalra, Lackey, Levine, Limón, Low, Maienschein, McCarty, Medina, Mullin, Muratsuchi, Nazarian, Obernolte, Quirk, Reyes, Ridley-Thomas, Rodriguez, Rubio, Salas, Santiago, Steinorth, Mark Stone, Thurmond, Ting, Voepel, Weber, Wood, Rendon
NOES: Travis Allen, Brough, Chávez, Harper, Mathis, Mayes, Melendez, Quirk-Silva, Waldron
NO VOTE RECORDED: Acosta, Bigelow, Dahle, Fong, Gallagher, Kiley, O'Donnell, Patterson
8/21/18 18:45:48
**** END ****
SENATE COMMITTEE ON APPROPRIATIONS
Senator Anthony Portantino, Chair
2017 - 2018 Regular Session
AB 734 (Bonta) - California Environmental Quality Act: Oakland Sports and Mixed-Use Project
Version: July 3, 2018 | Policy Vote: E.Q. 7 - 0, JUD. 5 - 1 |
Urgency: No | Mandate: Yes |
Hearing Date: August 16, 2018 | Consultant: Ashley Ames |
Bill Summary:
This bill would establish procedures specific the Oakland Sports and Mixed-Use Project in the City of Oakland that would provide expedited administrative and judicial review procedures.
*********** ANALYSIS ADDENDUM – SUSPENSE FILE ***********
The following information is revised to reflect amendments
adopted by the committee on August 16, 2018
Fiscal Impact:
- $172,000 (various funds) for the California Air Resources Board (CARB) to evaluate the project with respect to whether it will result in a net increase of greenhouse gas emissions.
- Minor and absorbable costs for Judicial Council to review and revise the rules of the court to meet the requirements of this bill.
- Minor and absorbable costs for the Office of Planning and Research to process a judicial streamlining request.
Author Amendments:
Clarify the requirements for the project to be able to use a streamlined judicial review process.
-- END --
SENATE COMMITTEE ON APPROPRIATIONS
Senator Anthony Portantino, Chair
2017 - 2018 Regular Session
AB 734 (Bonta) - California Environmental Quality Act: Oakland Sports and Mixed-Use Project
Version: July 3, 2018 | Policy Vote: E.Q. 7 - 0, JUD. 5 - 1 |
Urgency: No | Mandate: Yes |
Hearing Date: August 13, 2018 | Consultant: Ashley Ames |
This bill meets the criteria for referral to the Suspense File.
Bill Summary:
This bill would establish procedures specific the Oakland Sports and Mixed-Use Project in the City of Oakland that would provide expedited administrative and judicial review procedures.
Fiscal Impact:
- $172,000 (various funds) for the California Air Resources Board (CARB) to evaluate the project with respect to whether it will result in a net increase of greenhouse gas emissions.
- Minor and absorbable costs for Judicial Council to review and revise the rules of the court to meet the requirements of this bill.
- Minor and absorbable costs for the Office of Planning and Research to process a judicial streamlining request.
Background:
The California Environmental Quality Act (CEQA) requires state and local agencies to follow a set protocol in order to disclose and evaluate any significant environmental impacts associated with proposed projects and to adopt feasible measures to mitigate those impacts. Projects determined to have significant environmental impacts generally are required to create an Environmental Impact Report (EIR). The EIR must accurately describe the proposed project, identify and analyze each significant environmental impact expected to result from the proposed project, identify mitigation measures to reduce those impacts to the extent feasible, and evaluate a range of reasonable alternatives to the proposed project. To enforce the requirements of CEQA, a civil action may be brought under several code sections to attack, review, set aside, void, or annul the acts or decisions of a public agency for noncompliance.
Existing law provides a framework for expediting CEQA review of major projects. AB 900 (Buchanan, Ch. 354, Stats. 2011) established specified administrative and judicial review procedures for the review of the EIR and public agency approvals granted for designated residential, retail, commercial, sports, cultural, entertainment, or recreational use projects, or clean renewable energy or clean energy manufacturing projects. To qualify as a leadership project, the project must:
- exceed a cost of $100 million and not result in any net additional emissions of greenhouse gases;
- create high-wage, highly skilled jobs that pay prevailing and living wages and provide construction jobs and permanent jobs for Californians; and
- be subject to an agreement with the lead agency that all mitigation measures will be enforced and monitored.
Additionally, the applicant bears the burden of costs for any hearing or decision before the Court of Appeal. The Governor has the discretion to certify the project. If the Governor does so, the application is submitted to the Joint Legislative Budget Committee for its concurrence.
Proposed Law:
This bill would establish specified procedures for the administrative and judicial review of the EIR and approvals granted for a project related to the “Oakland Sports and Mixed-Use Project.” It would define “Oakland Sports and Mixed-Use Project” as a baseball park that will become the new home to the Oakland Athletics and adjacent residential, retail, commercial, cultural, entertainment, or recreational infrastructure to be developed by the Oakland Athletics, among other things.
Related Legislation:
AB 987 (Kamlager-Dove, 2018) would establish specified administrative and judicial review procedures for the EIR and approvals granted for a project related to the development of a specified sports and entertainment project in the City of Inglewood.
AB 2267 (Wood, 2018) would exempt the City of Santa Rosa from CEQA until January 1, 2024, with regard to the adoption or approval of amendments to land use plans that meet certain requirements. The bill would also authorize streamlined judicial review for the adoption or amendment of a specific plan, general plan, zoning ordinance, or other planning document by a local public agency for purposes related to promoting housing development and infill.
AB 3030 (Caballero, 2018) would exempt from CEQA a project that is financed by a qualified opportunity fund and that meets the certain requirements.
Staff Comments:
It makes sense to consider this bill in the context of several CEQA-related bills currently before this committee. There are several CEQA-related bills currently before this committee that staff recommends evaluating as a comprehensive package rather than on an individual basis. First, it makes sense for the committee to apply a uniform approach to all of the CEQA-related bills that it is considering. Second, these bills would require resources from the same program areas of the same departments. While the impact of each bill individually might be absorbable, some or all of the bills implemented collectively could result in significant cost pressure and a need for additional resources.
Project-Specific Processes Require Additional Department Resources. Regulations, necessary staff, and needed resources already exist for the typical CEQA process as well as alternatives that are codified, such as AB 900. However, bills that define new processes for individual projects create new workload for departments since the existing framework no longer applies to them.
Exemptions and Alternative Processes Could Reduce Protections Offered by CEQA. CEQA was enacted in order to offer specific environmental protections to both Californians and the California environment. Some projects, especially large-scale ones, can experience significant delays under the current CEQA process. Providing an exemption or alternative to some projects can make sense in certain circumstances when the overall public benefit of the project is clear. However, when that is the case, staff recommends ensuring that a similar level of environmental protection is required. The amendments proposed by the Senate Environmental Quality Committee sought to address this issue. However, some of them were not adopted.
-- END --
Senator Hannah-Beth Jackson, Chair
2017-2018 Regular Session
Bill No: AB 734 (Author:Bonta)
Version: June 4, 2018
Hearing Date: June 26, 2018
Fiscal: Yes
Urgency: No
JDTConsultant:
SUBJECT
California Environmental Quality Act: Oakland Sports and Mixed-Use Project
DESCRIPTION
This bill would establish expedited administrative and judicial review procedures for the administrative and judicial review of the environmental impact report and approvals granted for a project related to the development of the Oakland Sports and Mixed-Use Project in the City of Oakland.
This analysis reflects amendments previously agreed to in the Senate Environmental Quality Committee, but that are not in the print version of the bill. These amendments are described in Comment 2.
BACKGROUND
Enacted in 1970, the California Environmental Quality Act (CEQA) requires state and local agencies (public agencies) to follow a set protocol to disclose and evaluate the significant environmental impacts of proposed projects and to adopt feasible measures to mitigate those impacts. CEQA itself applies to “projects” undertaken or requiring approval by public agencies, and, if more than one agency is involved, CEQA requires one of the agencies to be designated as the “lead agency.” The environmental review process required by CEQA consists of: (1) determining if the activity is a project; (2) determining if the project is exempt from CEQA; and (3) performing an initial study to identify the environmental impacts and, depending on the findings, prepare either a Negative Declaration (for projects with no significant impacts), a Mitigated Negative Declaration (for projects with significant impacts but that are revised in some form to avoid or mitigate those impacts), or an Environmental Impact Report (for projects with significant impacts).
An Environmental Impact Report (EIR) must accurately describe the proposed project, identify and analyze each significant environmental impact expected to result from the proposed project, identify mitigation measures to reduce those impacts to the extent feasible, and evaluate a range of reasonable alternatives to the proposed project. Before approving any project that has received environmental review, an agency must make certain findings pertaining to the project’s environmental impact and any associated mitigation measures. If mitigation measures are required or incorporated into a project, the public agency must adopt a reporting or monitoring program to ensure compliance with those measures. To enforce the requirements of CEQA, a civil action may be brought under several code sections to attack, review, set aside, void, or annul the acts or decisions of a public agency for noncompliance with the act.
Existing law provides a framework for expediting CEQA review of major projects. AB 900 (Buchanan, Ch. 354, Stats. 2011), the Jobs and Economic Improvement Through Environmental Leadership Act of 2011, established specified administrative and judicial review procedures for the review of the EIR and public agency approvals granted for designated residential, retail, commercial, sports, cultural, entertainment, or recreational use projects, or clean renewable energy or clean energy manufacturing projects. To qualify as a leadership project, the project must:
- exceed $100 million and not result in any net additional emissions of greenhouse gases;
- create high-wage, highly skilled jobs that pay prevailing and living wages and provide construction jobs and permanent jobs for Californians; and
- be subject to an agreement with the lead agency that all mitigation measures will be enforced and monitored.
Additionally, the applicant bears the burden of costs for any hearing or decision before the Court of Appeal. The Governor has the discretion to certify the project. If the Governor does so, the application is submitted to the Joint Legislative Budget Committee for its concurrence.
This bill would establish separate expedited administrative and judicial review procedures for the administrative and judicial review of the EIR and approvals granted for a project related to the development of an Oakland Sports and Mixed-Use Project.
This bill was previously heard in the Senate Environmental Quality Committee, and passed by a vote of 7-0. This analysis reflects amendments that were agreed to in that committee, but that are not in the print version of the bill. These amendments are described in Comment 2.
CHANGES TO EXISTING LAW
Existing law, the California Environmental Quality Act (CEQA), requires a public agency to prepare, or cause to be prepared, and to certify the completion of, an environmental impact report (EIR) on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. (Pub. Res. Code Sec. 21100 et seq.)
Existing law defines “project” as an activity that may cause either a direct physical change in the environment, or a reasonably foreseeable indirect physical change in the environment, and which is any of the following:
- an activity directly undertaken by any public agency;
- an activity undertaken by a person which is supported, in whole or in part, through contracts, grants, subsidies, loans, or other forms of assistance from one or more public agencies; or
- an activity that involves the issuance to a person of a lease, permit, license, certificate, or other entitlement for use by one or more public agencies. (Pub. Res. Code Sec. 21065.)
Existing law provides that an action or proceeding to attack, review, set aside, void, or annul the acts or decisions of a public agency on the grounds of noncompliance with CEQA may be commenced when, among other things, it is alleged that:
- a public agency is carrying out or has approved a project that may have a significant effect on the environment without having determined whether the project may have a significant effect on the environment;
- a public agency has improperly determined whether a project may have a significant effect on the environment;
- an environmental impact report prepared by, or caused to be prepared by, a public agency does not comply with CEQA;
- a public agency has improperly determined that a project is not subject to CEQA; or
- another act or omission of a public agency does not comply with CEQA. (Pub. Res. Code Sec. 21167.)
Existing law requires a plaintiff or petitioner to file a request that the respondent public agency prepare the record of proceedings relating to the underlying subject of the action or proceeding to attack, review, set aside, void, or annul its acts or decisions on the grounds of noncompliance with CEQA. Such a request must be served personally within 10 business days from the filing of the action or proceeding. The public agency is then required to prepare a record of proceedings relating to the subject of the action or proceeding. The public agency’s record of proceedings shall include, among other things, any transcript or minutes of the proceedings at which the decisionmaking body of the public agency heard testimony on, or considered any environmental document on, the project, and any transcript or minutes of proceedings before any advisory body to the public agency that were presented to the decisionmaking body prior to action on the environmental documents or on the project. (Pub. Res. Code Sec. 21167.6.)
Existing law states that an action or proceeding to attack, review, set aside, void, or annul the acts or decisions of a public agency on the grounds of noncompliance with CEQA shall not be brought unless the alleged grounds for noncompliance were presented to the public agency orally or in writing by any person during the public comment period provided by CEQA or prior to the close of the public hearing on the project before the issuance of the notice of determination. (Pub. Res. Code Sec. 21177(a).)
Existing law states that a person shall not maintain an action or proceeding to attack, review, set aside, void, or annul the acts or decisions of a public agency on the grounds of noncompliance with CEQA unless that person objected to the approval of the project orally or in writing during the public comment period provided by CEQA or prior to the close of the public hearing on the project before the filing of the notice of determination. (Pub. Res. Code Sec. 21177(b).)
Existing law does not preclude any organization formed after the approval of a project from maintaining an action or proceeding to attack, review, set aside, void, or annul the acts or decisions of a public agency on the grounds of noncompliance with CEQA if a member of that organization has complied with the above two provisions. Existing law provides that the grounds for noncompliance may have been presented directly by a member or by a member agreeing with or supporting the comments of another person. (Pub. Res. Code Sec. 21177(c).)
Existing law provides that if a parcel has been zoned to accommodate a particular density of development or has been designated in a community plan to accommodate a particular density of development and an environmental impact report was certified for that zoning or planning action, the application of CEQA to the approval of any subdivision map or other project that is consistent with the zoning or community plan shall be limited to effects upon the environment which are peculiar to the parcel or to the project and which were not addressed as significant effects in the prior environmental impact report, or which substantial new information shows will be more significant than described in the prior environmental impact report. (Pub. Resources Code Sec. 21083.3(a).)
Existing law provides that if a development project is consistent with the general plan of a local agency and an environmental impact report was certified with respect to that general plan, the application of CEQA to the approval of that development project shall be limited to effects on the environment which are peculiar to the parcel or to the project and which were not addressed as significant effects in the prior environmental impact report, or which substantial new information shows will be more significant than described in the prior environmental impact report. (Pub. Res. Code Sec. 21083.3(b).)
Existing law, the Jobs and Economic Improvement Through Environmental Leadership Act of 2011 (AB 900, Buchanan, Gordon, Chapter 354, Statutes of 2011) (AB 900), which is part of CEQA, establishes CEQA administrative and judicial review procedures for an “environmental leadership development project.” (Pub. Res. Code Sec. 21178 et seq.).
Existing law, with regard to environmental leadership development projects, establishes procedures for expedited judicial review—specifically, courts must resolve lawsuits within 270 days—if the projects are certified by the Governor and meet specified conditions. (Pub. Res. Code Secs. 21178 & 21185.)
Existing law defines “environmental leadership development project” as a CEQA project that is one of the following:
- residential, retail, commercial, sports, cultural, entertainment, or recreational use project that is certified as LEED gold or better by the United States Green Building Council and, where applicable, that achieves a 15 percent or greater standard for transportation efficiency than for comparable projects, and that is located on an infill site, as prescribed;
- a clean renewable energy project that generates electricity exclusively through wind or solar, but not including waste incineration or conversion;
- a clean energy manufacturing project that manufactures products, equipment, or components used for renewable energy generation, energy efficiency, or for the production of clean alternative fuel vehicles. (Pub. Res. Code Sec. 21180(b).)
Existing law allows a person proposing to construct a leadership project to apply to the Governor for certification that the leadership project is eligible for streamlining. Existing law requires the person to supply evidence and materials that the Governor deems necessary to make a decision on the application. Existing law also requires any evidence or materials be made available to the public at least 15 days before the Governor certifies a project pursuant to AB 900. (Pub. Res. Code Sec. 21182.)
Existing law allows the Governor to certify a leadership project if the Governor finds the project meets all of the following conditions:
- the project will result in a minimum investment of $100 million in California upon completion of construction;
- the project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment;
- the project does not result in any net additional GHG emissions, including emissions from employee transportation, as determined by the Air Resources Board pursuant to the California Global Warming Solutions Act of 2006;
- the project applicant has entered into a binding and enforceable agreement that all mitigation measures required under CEQA shall be conditions of approval of the project, and those conditions will be fully enforceable by the lead agency or another agency designated by the lead agency;
- the project applicant agrees to pay the costs of the Court of Appeal in hearing and deciding any case, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council; and
- the project applicant agrees to pay the costs of preparing the administrative record for the project concurrent with review and consideration of the project pursuant to CEQA, in a form and manner specified by the lead agency for the project. (Pub. Res. Code Sec. 21183.)
Existing law requires the Governor, upon determining that a leadership project is eligible for streamlining, to submit that determination, and any supporting information, to the Joint Legislative Budget Committee for review and concurrence or non-concurrence. (Pub. Res. Code Sec. 21184(a)-(c).)
Existing law authorizes the Governor to issue guidelines regarding application and certification of projects pursuant to AB 900. These guidelines are not subject to the rulemaking provisions of the Administrative Procedure Act. (Pub. Res. Code Sec. 21184(d).)
Existing law requires the Judicial Council to adopt a rule of court to establish procedures that require resolution within 270 days, including any appeals, of a lawsuit challenging the certification of the EIR or any project approvals for a certified environmental leadership project. (Pub. Res. Code Sec. 21185.)
Existing law establishes requirements for preparation and certification of the record of proceeding for a leadership project certified by the Governor. (Pub. Res. Code Sec. 21186.)
Existing law provides that nothing in AB 900 affects the duty of any party to comply with CEQA, except as otherwise provided in AB 900. (Pub. Res. Code Sec. 21189.)
Existing law provides that AB 900 does not apply to a leadership project if the Governor does not certify the project prior to January 1, 2020. (Pub. Res. Code Sec. 21181.)
Existing law provides that certification of the leadership project expires and is no longer valid if the lead agency fails to approve the project prior to January 1, 2021. (Pub. Res. Code Sec. 21189.1.)
This bill would establish expedited administrative and judicial review procedures for the administrative and judicial review of the EIR and approvals granted for a project related to the development of the Oakland Sports and Mixed-Use Project.
This bill would define “Oakland Sports and Mixed-Use Project” or “project” as the following components of a sports center and mixed-use project located at the Howard Terminal site in the City of Oakland or the Oakland-Alameda County Coliseum site in the City of Oakland, from demolition and site preparation through operation:
- a baseball park that will become the new home to the Oakland Athletics and adjacent residential, retail, commercial, cultural, entertainment, or recreational uses developed by the Oakland Athletics, as specified;
- associated public spaces; and
- facilities and infrastructure for ingress, egress, and use of the baseball park and mixed-use development.
This bill would require that, on or before July 1, 2019, the Judicial Council adopt a rule of court to establish procedures applicable to actions or proceedings brought to attack, review, set aside, void, or annul the certification or adoption of the environmental review document for the Oakland Sports and Mixed-Use Project that is certified by the Governor pursuant to this section or the granting of any project approvals that require the actions or proceedings, including any potential appeals therefrom, be resolved, to the extent feasible, within 270 days of the filing of the certified record of proceedings with the court.
This bill would provide that the Governor may certify the project for streamlining if the project complies with all of the following:
- the project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment, as specified;
- the project applicant agrees to pay the costs of:
- the Court of Appeal in hearing and deciding any case brought under CEQA, including the costs for the appointment of a special master if deemed appropriate by the court, as specified; and
- preparing the record of the proceedings for the project concurrent with review and consideration of the project pursuant to CEQA.
This bill would require that, before certifying the project, the Governor make a determination that each of the conditions identified above have been met. This determination is not subject to judicial review. The bill would provide that the Governor may issue guidelines regarding application for and certification of the project pursuant to the bill’s provisions.
This bill would provide that, within 5 days after the close of the comment period, a commenter may request nonbinding mediation with the lead agency. Mediation must be completed within 35 days of the close of the comment period. The lead agency must adopt agreed upon measures, and a commenter cannot use that issue as a basis to challenge the certification of the environmental review document or project approval.
This bill would provide that the court may only enjoin specific activities associated with the project that present an imminent threat to public health and safety or that materially, permanently, or that adversely affect unforeseen important Native American artifacts or unforeseen important historical, archaeological, or ecological values, as specified.
COMMENT
1. Stated need for the bill
The author writes:
The Oakland A’s have called the City of Oakland home for the last fifty years. With the impending loss of the Raiders to Las Vegas and the Golden State Warriors to San Francisco it’s critically important to the city and entire East Bay region to retain a professional sports team.
AB 734 is modeled closely on the legislation previously enacted for the Sacramento Kings and other environmental leadership projects under AB 900 by expediting judicial review for the adjudication of legal challenges within 270 days to the extent feasible.
This will help provide certainty to the city and the Oakland A’s who have made a public commitment to staying in Oakland. Currently, the team is evaluating two potential sites to build a new, privately financed, state of the art ballpark that will bring thousands of jobs while providing a significant economic boost to the region. A study by the Bay Area Council Economic Institute in June 2017 estimated that a new ballpark would generate $3.05 billion of economic impact for the residents and businesses of the City of Oakland over the first ten years of operation.
2. Amendments taken in the Senate Environmental Quality Committee
This bill was previously heard in the Senate Environmental Quality Committee, and passed by a vote of 7-0. During the hearing, several amendments were agreed to as a condition of the bill’s passage. Due to time constraints, these amendments have not yet been adopted into the print version of the bill. Following that hearing, staff from the Senate Environmental Quality Committee emailed a description of the amendments to this Committee’s staff. That description, reproduced verbatim and in its entirety, is as follows:
A commitment was made in the Senate Committee on Environmental Quality to AB 734 (Bonta) in the judiciary committee to more closely align the bill with the AB 900 standards for leadership project designation. Specifically the agreed upon amendments are as follows:
- To require the portion of the project that applies to the arena, commercial and all building will achieve at least LEED Gold rating and the residential building within the project shall achieve at least LEED Silver rating.
- Specify that the ballpark shall achieve net zero greenhouse gas emissions.
- Remove language that prevents the court from staying or enjoining the construction or operation of the project.
In addition the author committed to continue to work with the committee on amendments as the bill moves forward to:
- More closely mirror AB 900 greenhouse gas emission reduction targets while accommodating the unique situation of Oakland and the potential site of the future ballpark at the Howard Terminal site by allowing reductions to be achieved but not requiring the reductions be achieved on site.
- Incorporate certification by the Governor as specified in AB 900.
This analysis is based on AB 734 as it would be changed by those amendments.
3. Major sports venues and CEQA
- Sports venues that were subjected to full CEQA review
Since the establishment of CEQA over 45 years ago, several sports venues have been proposed or built in California. A number of major league sports venues have been built and fully complied with CEQA, including:
- Avaya Stadium, Santa Clara (Opened in 2015);
- Levi Stadium, Santa Clara (2014);
- Petco Park, San Diego (2004);
- StubHub Center, Carson (2003);
- AT&T Park, San Francisco (2000);
- Staples Center and the LA Live complex, Los Angeles (1999);
- Honda Center, Anaheim (1993); and
- Sleep Train Arena, Sacramento (1988).
- Sports venues with unique exemptions from full CEQA review
Other sports venues have either bypassed, been exempted from, or granted fast-tracking provisions for, CEQA, including:
- Los Angeles Stadium at Hollywood Park, Inglewood, which includes a stadium for the future home to the NFL’s Rams and Chargers, and was not subject to CEQA due to a ballot box loophole (Proposed opening in 2020);
- Golden 1 Center, Sacramento (opened in 2016), which, under SB 743 (Steinberg, Chapter 386, Statutes of 2013), was granted a special administrative and judicial review procedures under CEQA for the arena, similar to the provisions of AB 734 currently in print;
- proposed Farmers Field in downtown Los Angeles, but a team was not found for this project; and
- proposed Los Angeles Stadium at Grand Crossing, City of Industry, but a team was not found for this project.
- Sports venues under the AB 900 framework
A framework for expediting certain major projects was established by AB 900 (Buchanan, Ch. 354, Stats. 2011), the Jobs and Economic Improvement Through Environmental Leadership Act of 2011. AB 900, which is part of CEQA, establishes CEQA administrative and judicial review procedures for an “environmental leadership development project” certified by the Governor and meeting specified conditions, including LEED silver-certified infill site projects, clean renewable energy projects, and clean energy manufacturing projects. (Pub. Res. Code Sec. 21178.)
According to the Office of Planning and Research, the following projects have had AB 900 applications submitted:
- McCoy Solar Energy Project (2012);
- Apple Campus 2 (2012);
- Soitec Solar Energy Project (2013);
- 8150 Sunset Boulevard (2014);
- Event Center and Mixed-Use Development at Mission Bay Blocks (The Golden State Warriors Arena) (2014);
- Qualcomm Stadium Reconstruction Project (2015);
- Crossroads Hollywood (2016);
- 6220 West Yucca Project (2017);
- 10 Van Ness Avenue Mixed-Use Project (2017);
- 1045 Olive Street Project (2018); and
- Hollywood Center Project (2018).
4. Comparison of this bill and the AB 900 framework
AB 900 was enacted to provide a set of minimum environmental and community benefit criteria that if achieved by a project would allow consideration as a Leadership Project. Such projects are subject to expedited CEQA administrative and judicial review procedures if they are certified by the Governor and meet specified conditions. These projects include LEED silver-certified infill site projects, clean renewable energy projects, and clean energy manufacturing projects. (Pub. Res. Code Sec. 21178.) AB 900 additionally provides that a leadership project:
- may be certified by the Governor only if it meets specified criteria, including all of the following:
- the project will result in a minimum investment of $100 million in California upon completion of construction;
- the project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment;
- the project does not result in any net additional GHG emissions; and
- the applicant has entered into a binding and enforceable agreement that all mitigation measures required under CEQA are conditions of approval of the project, and those conditions will be fully enforceable by the lead agency or another agency designated by the lead agency.
- the applicant bears the burden of costs for any hearing or decision before the Court of Appeal; and
- upon certification by the Governor, is submitted to the Joint Legislative Budget Committee for review and concurrence or non-concurrence (Pub. Res. Code Sec. 21184(a)-(c)); and
- upon certification of the EIR or any related project approvals, is subject to review, including any appeals, for 270 days, pursuant to rules adopted by the Judicial Council. (Pub. Res. Code Sec. 21185; Cal Rules of Court, Rule 3.2220 et seq.)
This bill would provide for expedited administrative and judicial review of environmental documents and approvals granted for a project related to the development of the Oakland Sports and Mixed-Use Project, if the project meets certain criteria. As amended in the Senate Environmental Quality Committee, the bill would require the project to be certified by the Governor before the project is eligible for the streamlined process. The bill also authorizes the Governor to issue guidelines regarding application and certification. Although the certification criteria in the bill are narrow—the project must provide for prevailing wages and the applicant bears the burden of costs for any hearing or decision before the Court of Appeal—the author committed to work with the staff of Senate Environmental Quality Committee to incorporate certification by the Governor as specified in AB 900.
The author contends that this project needs a separate framework because the project cannot meet 3 important parts of the AB 900 process:
- AB 900 expires in 2021 – for the A’s project, the statute would need to be extended to 2024 which this bill would address;
- a site-specific set of standards is needed because the Air Resources Board methodology for calculating net new emissions doesn’t work for the two proposed infill sites;
- AB 900 requires LEED Gold across the board for the project, but with this project the plan is to meet LEED Gold Standards for the ballpark and surrounding commercial development, but the residential development will be at the LEED Silver level.
5. Negative impacts on the courts and the environment
Existing law requires the courts to give CEQA-related cases preference over “all other civil actions… so that the action or proceeding shall be quickly heard and determined.” (Pub. Res. Code Sec. 21167.1). This bill would provide that any challenge against the certification of an EIR for the project or granting of any project approvals, in order to require the actions or proceeding, including any appeals, to be resolved, to the extent feasible, within 270 days of the certification of the record of proceedings, as specified.
Writing in opposition, the Judicial Council of California expresses concerns regarding the impact on courts and other litigants:
AB 734’s requirement that any CEQA lawsuit challenging the Oakland Sports and Mixed-Use Project, including any appeals therefrom, be resolved within 270 days is problematic for a number of reasons. First, CEQA actions are already entitled under current law to calendar preference in both the superior courts and the Courts of Appeal. Imposing a 270-day timeline on top of the existing preference is arbitrary and likely to be unworkable in practice.
Second, the expedited judicial review for the specific project covered by AB 734 will likely have an adverse impact on other cases. Like other types of calendar preferences, which the Judicial Council has historically opposed, setting an extremely tight timeline for deciding this particular type of case has the practical effect of pushing other cases on the courts’ dockets to the back of the line. This means that other cases, including cases that have statutorily mandated calendar preferences, such as juvenile cases, criminal cases, and civil cases in which a party is at risk of dying, will take longer to decide. Moreover, delays in the administration of justice that would likely result from any expansion of this expedited judicial review approach would be even more pronounced in light of the ongoing fiscal limitations faced by the judicial branch.
Finally, providing expedited judicial review for the specific project covered by AB 734 while other cases proceed under the usual civil procedure rules and timelines undermines equal access to justice. The courts are charged with dispensing equal access to justice for each and every case on their dockets. Singling out this particular type of case for such preferential treatment is fundamentally at odds with how our justice system has historically functioned.
6. Concerns expressed over the potential sites for the project
In opposition, Sierra Club writes:
AB 734 proposes weakening CEQA for two potential sites. One site is the existing Oakland-Alameda County Coliseum site, for which a specific plan update has already undergone environmental review. Existing tiering provisions already exist for such a project, making further CEQA weakening unwarranted.
The other site, Howard Terminal, has no such EIR in place. Many conditions of the site make weakening environmental standards unwise. The site is currently an industrial site, increasing chances that construction activities can lead to hazardous materials being exposed to the public and the environment. The site is located directly on the San Francisco Bay, meaning that there could be impacts from materials entering the water during construction or operation. Sea level rise will also be a problem.
Howard Terminal is also 1 mile from the West Oakland BART Station, and 1.5 miles from the 19th st BART Station, limiting the likelihood that people will be able to walk to the site. The site is also adjacent to at grade Amtrak lines, increasing potential impacts to public safety. The nature of this site makes it potentially highly impactful and weakening CEQA is highly inappropriate.
7. Should this project be subject to the AB 900 process?
Considering the issues raised above, the Committee may wish to consider whether this bill is prudent or whether it would be more appropriate that the City of Oakland consider applying for the AB 900 process, as was specifically provided for other similar projects. To that end, the AB 900 framework, which will sunset on January 1, 2021, could be extended specifically for this project.
Support: Bay Area Council; City of Emeryville, Mayor John Bauters; City of Berkeley; Mayor Jesse Arreguin; City of San Leandro; Oakland African American Chamber of Commerce; Oakland Chamber of Commerce; Oakland Chinatown Chamber of Commerce; Save Oakland Sports; State Building and Construction Trades Council; 1 Individual
Opposition: Judicial Council; Sierra Club
HISTORY
Source: Mayor Libby Schaaf and the City of Oakland
Related Pending Legislation: AB 987 (Kamlager-Dove) would establish expedited administrative and judicial review procedures for the administrative and judicial review of the environmental impact report and approvals granted for a project related to the development of a specified sports and entertainment project in the City of Inglewood. This bill is set to be heard in this Committee on June 26, 2018.
Prior Legislation:
SB 743 (Steinberg, Ch. 386, Stats. 2013) established specified administrative and judicial review procedures for review of the EIR and public agency approvals granted for a project related to the development of an entertainment and sports center in the City of Sacramento. Additionally, this bill provides that aesthetic and parking impacts of a residential, mixed-use residential, or employment center project on an infill site within a transit priority area shall not be considered significant impacts on the environment under CEQA, as specified.
AB 900 (Buchanan, Ch. 354, Stats. 2011), the Jobs and Economic Improvement Through Environmental Leadership Act of 2011, established specified administrative and judicial review procedures for the review of the EIR and public agency approvals granted for designated residential, retail, commercial, sports, cultural, entertainment, or recreational use projects, or clean renewable energy or clean energy manufacturing projects.
SB 292 (Padilla, Ch. 353, Stats. 2011) established specified administrative and judicial review procedures for review of the EIR and public agency approvals granted for a project related to the development of a stadium in the City of Los Angeles.
Prior Vote:
Senate Environmental Quality Committee (Ayes 7, Noes 0)
Assembly Floor (Ayes 63, Noes 9)
Assembly Local Government Committee (Ayes 8, Noes 0)
**************
SENATE COMMITTEE ON ENVIRONMENTAL QUALITY
Senator Wieckowski, Chair
2017 - 2018 Regular
Bill No: AB 734
Author: | Bonta | ||
Version: | 6/4/2018 | Hearing Date: | 6/20/2018 |
Urgency: | No | Fiscal: | Yes |
Consultant: | Rachel Machi Wagoner | ||
SUBJECT: California Environmental Quality Act: Oakland Sports and Mixed-Use Project
ANALYSIS:
Existing law, under the California Environmental Quality Act (CEQA):
- Requires lead agencies with the principal responsibility for carrying out or approving a proposed discretionary project to prepare a negative declaration, mitigated declaration, or environmental impact report (EIR) for this action, unless the project is exempt from CEQA (CEQA includes various statutory exemptions, as well as categorical exemptions in the CEQA guidelines). (Public Resources Code (PRC) §21000 et seq.).
- Sets requirements relating to preparation, review, comment, approval and certification of environmental documents, as well as procedures relating to an action or proceeding to attack, review, set aside, void, or annul various actions of a public agency on the grounds of noncompliance with CEQA.
- Requires courts to give CEQA-related actions or proceedings preference over all other civil actions so that the action or proceeding is quickly heard and determined. (PRC §21167.1).
- Under the Jobs and Economic Improvement Through Environmental Leadership Act of 2011 (AB 900, Buchanan, Gordon, Chapter 354, Statutes of 2011) (AB 900), which is part of CEQA, establishes CEQA administrative and judicial review procedures for an “environmental leadership development project.” (PRC §21178 et seq.).
- Establishes procedures for expedited judicial review (i.e., requiring the courts to resolve lawsuits within 270 days) for “environmental leadership” projects certified by the Governor and meeting specified conditions, including Leadership in Energy and Environmental Design (LEED) gold-certified infill site projects, clean renewable energy projects, and clean energy manufacturing projects.
- Defines “environmental leadership” project as a CEQA project that is one of the following:
- A residential, retail, commercial, sports, cultural, entertainment, or recreational use project that is certified as LEED gold or better by the United States Green Building Council and, where applicable, that achieves a 15% greater standard for transportation efficiency than for comparable projects.
- Requires that these projects be located on an infill site.
- Requires a project that is within a metropolitan planning organization for which a Sustainable Communities Strategy (SCS) or alternative planning strategy (APS) is in effect, to be consistent with specified policies in either the SCS or APS, which, if implemented, would achieve greenhouse gas emission (GHG) reduction targets.
- Requires a project applicant to demonstrate compliance with the requirement that generators of commercial solid waste and large amounts of organic waste arrange for recycling services for those materials.
- A clean renewable energy project that generates electricity exclusively through wind or solar, but not including waste incineration or conversion.
- A clean energy manufacturing project that manufactures products, equipment, or components used for renewable energy generation, energy efficiency, or for the production of clean alternative fuel vehicles.
- Allows a person proposing to construct a leadership project to apply to the Governor for certification that the leadership project is eligible for streamlining. Requires the person to supply evidence and materials that the Governor deems necessary to make a decision on the application. Requires any evidence or materials be made available to the public at least 15 days before the Governor certifies a project pursuant to AB 900.
- Authorizes the Governor to certify a leadership project if the Governor finds the project meets all of the following conditions:
- The project will result in a minimum investment of $100 million in California upon completion of construction.
- The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment.
- The project does not result in any net additional GHG emissions, including emissions from employee transportation, as determined by the Air Resources Board pursuant to the California Global Warming Solutions Act of 2006 (AB 32).
- The project applicant has entered into a binding and enforceable agreement that all mitigation measures required under CEQA shall be conditions of approval of the project, and those conditions will be fully enforceable by the lead agency or another agency designated by the lead agency. In the case of environmental mitigation measures, the applicant agrees, as an ongoing obligation, that those measures will be monitored and enforced by the lead agency for the life of the obligation.
- The project applicant agrees to pay the costs of the Court of Appeal in hearing and deciding any case, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council.
- The project applicant agrees to pay the costs of preparing the administrative record for the project concurrent with review and consideration of the project pursuant to CEQA, in a form and manner specified by the lead agency for the project.
- Requires the Governor, prior to certifying a project, to make a determination that each of the conditions specified above has been met. These findings are not subject to judicial review.
- If the Governor determines that a leadership project is eligible for streamlining, requires the Governor to submit that determination, and any supporting information, to the Joint Legislative Budget Committee (JLBC) for review and concurrence or non-concurrence.
- Requires the JLBC to concur or non-concur in writing within 30 days of receiving the Governor’s determination.
- Deems the leadership project certified if the JLBC fails to concur or non-concur on a determination by the Governor within 30 days of the submittal.
- Authorizes the Governor to issue guidelines regarding application and certification of projects pursuant to AB 900. These guidelines are not subject to the rulemaking provisions of the Administrative Procedure Act.
- Requires the Judicial Council to adopt a rule of court to establish procedures that require resolution within 270 days, including any appeals, of a lawsuit challenging the certification of the EIR or any project approvals for a certified environmental leadership project.
- Prohibits AB 900 from applying to a leadership project if the applicant fails to notify a lead agency prior to the release of the draft EIR for public comment.
- Sets requirements for preparation and certification of the record of proceeding for a leadership project certified by the Governor.
- Requires the draft and final EIR to include a specified notice in no less than 12-point type regarding the draft and final EIR being subject to AB 900.
- Provides that provisions of AB 900 are severable.
- Provides that nothing in AB 900 affects the duty of any party to comply with CEQA, except as otherwise provided in AB 900.
- Prohibits AB 900 from applying to a leadership project if the Governor does not certify the project prior to January 1, 2020.
- Provides that certification of the leadership project expires and is no longer valid if the lead agency fails to approve the project prior to January 1, 2021.
- Establishes procedures for expedited judicial review (i.e., requiring the courts to resolve lawsuits within 270 days) for “environmental leadership” projects certified by the Governor and meeting specified conditions, including Leadership in Energy and Environmental Design (LEED) gold-certified infill site projects, clean renewable energy projects, and clean energy manufacturing projects.
This bill:
- Establishes specified administrative and judicial review procedures for the administrative and judicial review of the EIR and approvals granted for a project related to the development of a “Oakland Sports and Mixed-Use Project” in the City of Oakland meeting certain requirements.
- Defines “Oakland Sports and Mixed-Use Project” or “project” as the following components of a sports center and mixed-use project located at the Howard Terminal site in the City of Oakland or the Oakland-Alameda County Coliseum site in the City of Oakland, from demolition and site preparation through operation:
- A baseball park that will become the new home to the Oakland Athletics and adjacent residential, retail, commercial, cultural, entertainment, or recreational uses developed by the Oakland Athletics, as specified.
- Associated public spaces.
- Facilities and infrastructure for ingress, egress, and use of the baseball park and mixed-use development.
- Provides, for an EIR for a project under this statute, that the lead agency need not consider comments filed after the close of the public comment period for the draft EIR and any judicial action challenging the certification of the EIR is subject to the specified procedures and limitations.
- On or before July 1, 2019, the Judicial Council adopt a rule of court to establish procedures applicable to actions or proceedings brought to attack, review, set aside, void, or annul the certification or adoption of the environmental review document for the Oakland Sports and Mixed-Use Project that is certified by the Governor pursuant to this section or the granting of any project approvals that require the actions or proceedings, including any potential appeals therefrom, be resolved, to the extent feasible, within 270 days of the filing of the certified record of proceedings with the court.
- Provides that the Governor may certify the project for streamlining if specified conditions are met.
- Provides that the court shall only enjoin those specific activities associated with the project that present an imminent threat to public health and safety or that materially, permanently, and adversely affect unforeseen important Native American artifacts or unforeseen important historical, archaeological, or ecological values, as specified.
Background
- Previous, related bills for large projects.
- AB 900 and SB 292. AB 900 (Buchanan, Gordon, Chapter 354, Statutes of 2011) and SB 292 (Padilla, Chapter 353, Statutes of 2011) and SB 246, Chapter 354 ,Statutes of 2017) established expedited CEQA judicial review procedures for a limited number of projects. For AB 900, it was large-scale projects meeting extraordinary environmental standards and providing significant jobs and investment. For SB 292, it was a proposed downtown Los Angeles football stadium and convention center project achieving specified traffic and air quality mitigations. The stadium project subject to SB 292 has not proceeded.
For these eligible projects, the bills provided for original jurisdiction by the Court of Appeal and a compressed schedule requiring the court to render a decision on any lawsuit within 175 days. This promised to reduce the existing judicial review timeline by 100 days or more, while creating new burdens for the courts and litigants to meet the shortened schedule.
AB 900’s provision granting original jurisdiction to the Court of Appeal was invalidated in 2013 by a decision in Alameda Superior Court in Planning and Conservation League v. State of California. - SB 743 (Steinberg, Chapter 386, Statutes of 2013). Subsequent to the Alameda Superior Court holding mentioned above, SB 743 repealed the provision that gave original jurisdiction to the Court of Appeal and required Judicial Council to adopt a rule of court mandating lawsuits and any appeals to be resolved within 270 days.
Also, SB 743 (Steinberg) established special CEQA procedures modeled on SB 292 for the Sacramento Kings arena project. Like SB 292, SB 743 applied to a single project and included specified traffic and air quality mitigations. CEQA lawsuits were filed against the Kings arena, and the lawsuits, including appeals, were resolved 267 days after certification of the record. - AB 900 projects to date. Six projects have been certified under AB 900. The deadline for AB 900 certification under current law has passed (which was January 1, 2016). According to the Office of Planning and Research, the following projects have had AB 900 applications submitted:
- McCoy Solar Energy Project (January 12, 2012);
- Apple Campus 2 (April 19, 2012);
- Soitec Solar Energy Project (January 7, 2013);
- 8150 Sunset Boulevard (January 31, 2014);
- Event Center and Mixed-Use Development at Mission Bay Blocks (The Golden State Warriors Arena) (February 17, 2014);
- Qualcomm Stadium Reconstruction Project (August 25, 2015);
- Crossroads Hollywood (August 29, 2016); and,
- 6220 West Yucca Project (April 17, 2017).
- 10 Van Ness Avenue Mixed-Use Project (October 4, 2017)
- 1045 Olive Street Project (December 19, 2018)
- Hollywood Center Project (May 2, 2018)
- AB 900 and SB 292. AB 900 (Buchanan, Gordon, Chapter 354, Statutes of 2011) and SB 292 (Padilla, Chapter 353, Statutes of 2011) and SB 246, Chapter 354 ,Statutes of 2017) established expedited CEQA judicial review procedures for a limited number of projects. For AB 900, it was large-scale projects meeting extraordinary environmental standards and providing significant jobs and investment. For SB 292, it was a proposed downtown Los Angeles football stadium and convention center project achieving specified traffic and air quality mitigations. The stadium project subject to SB 292 has not proceeded.
Comments
- Purpose of the bill. According to the author, “The Oakland A’s have called the City of Oakland home for the last fifty years. With the impending loss of the Raiders to Las Vegas and the Golden State Warriors to San Francisco it’s critically important to the city and entire East Bay region to retain a professional sports team.
AB 734 is modeled closely on the legislation previously enacted for the Sacramento Kings and other environmental leadership projects under AB 900 by expediting judicial review for the adjudication of legal challenges within 270 days to the extent feasible.
This will help provide certainty to the city and the Oakland A’s who have made a public commitment to staying in Oakland. Currently, the team is evaluating two potential sites to build a new, privately financed, state of the art ballpark that will bring thousands of jobs while providing a significant economic boost to the region. A study by the Bay Area Council Economic Institute in June 2017 estimated that a new ballpark would generate $3.05 billion of economic impact for the residents and businesses of the City of Oakland over the first ten years of operation.”
- Sports venues and CEQA. Since the establishment of CEQA over 45 years ago, several sports venues have been proposed or built in California. Some have fully abided by CEQA while others have not.
- A number of major league sports venues that have been built and fully complied with CEQA, include:
- Avaya Stadium, Santa Clara, which is home to the Major League Soccer (MLS) team, San Jose Earthquakes (Construction cost: $100M. Opened in 2015).
- Levi Stadium, Santa Clara, which is home to the National Football League (NFL) team, San Francisco 49ers (Construction cost: $1.3B. Opened in 2014).
- Petco Park, San Diego, which is home of the Major League Baseball (MLB) team, San Diego Padres (Construction cost: $453M. Opened in 2004).
- StubHub Center, Carson, which is home to the MLS team, LA Galaxy; and, the NFL team, Los Angeles Chargers (Construction cost: $150M. Opened in 2003). The Los Angeles Chargers will play at StubHub Center through 2019.
- AT&T Park, San Francisco, which is home to MLB team, San Francisco Giants (Construction cost: $357M. Opened in 2000).*
* Some people mistakenly believe that the San Francisco Giants’ baseball park was exempted from CEQA. SB 181 (Kopp), Chapter 4, Statutes of 1997, exempted from CEQA the relocation of occupants or uses from real property pursuant to the Relocation Assistance Act on property consisting of the site on which the San Francisco Giants Ballpark is located. It should be noted that SB 181 specified that the exemption could not affect the application of CEQA to any discretionary action by a public agency not otherwise exempted by this provision, including the ballpark construction. Also, SB 181 prohibited the exemption from restricting the ability or rights of relocated occupants to challenge or appeal the relocation options. - Staples Center and the LA Live complex, Los Angeles, which is home to the Women’s NBA team, Los Angeles Sparks; the NBA teams, Los Angeles Lakers and the Los Angeles Clippers; and, the National Hockey League (NHL) team, Los Angeles Kings. (Construction cost: $375M. Opened in 1999).
- Honda Center, Anaheim, which is home to the NHL team, Anaheim Ducks (Construction cost: $123M. Opened in 1993).
- Sleep Train Arena, Sacramento, which was home to the NBA team, Sacramento Kings (Construction cost: $40M. Opened in 1988).
- Avaya Stadium, Santa Clara, which is home to the Major League Soccer (MLS) team, San Jose Earthquakes (Construction cost: $100M. Opened in 2015).
- Other sports venues, which have either bypassed, been exempted from, or granted fast-tracking provisions to CEQA, include:
- Los Angeles Stadium at Hollywood Park, Inglewood, which includes a stadium for the future home to the NFL’s Rams and Chargers, was not subject to CEQA due to a ballot box loophole. The stadium project was subject to a ballot initiative. A voter-proposed initiative is not subject to CEQA. In this case, in February 2015, Inglewood City Council approved the ballot measure directly and avoided an election altogether, which denied voters the opportunity to even vote on the proposal. Although the 298-acre, 80,000 seat, and 10,000 parking space stadium project will likely have significant environmental impacts, those impacts likely go unmitigated without an environmental review. The sports and entertainment district is under construction. (Projected cost: $2.6B. Proposed opening in 2020.)
The Los Angeles Rams and Los Angeles Chargers were to open at the new stadium in 2019, but are delayed by one year until 2020 due to rainfall. - A proposed stadium in Carson City, which would have been home to the San Diego Chargers and Oakland Raiders, also would have bypassed CEQA altogether via the ballot box initiative process. After two months of public announcement of the stadium project and eight days to collect more than 15,000 signatures in March, 2015, the Carson City Council approved the stadium in April, 2015. Like Inglewood, the voters in Carson City were denied the opportunity to vote on the ballot initiative and the project was not subject to an environmental review or any potential mitigation. (Projected cost: $1.7B.)
Neither NFL team will be playing at the proposed stadium. In March, 2017, the NFL gave approval for the Oakland Raiders to relocate from Oakland to Las Vegas, Nevada. As noted above, the Los Angeles Chargers will begin playing at the Los Angeles Stadium at Hollywood Park in Inglewood, in 2020. - Chase Center Arena, San Francisco, which will be home to the Golden State Warriors in the future, is subject to AB 900, which expedites the CEQA judicial process. (Detailed background below on AB 900.) The arena broke ground in January, 2017, and is currently under construction. (Projected cost: $1B. Proposed opening in 2019)
In addition, AB 1273 (Ting, Chapter 381, Statutes of 2013) authorized the State Lands Commission (SLC) to approve a multi-use development on public trust lands in San Francisco (Pier 30-32) that included a multipurpose venue (for Golden State Warriors basketball games and other events), if SLC found that certain conditions were met. However, the Golden State Warriors abandoned their plan to build an arena on Piers 30-32. - Qualcomm Stadium Reconstruction Project, San Diego – This project was subject to an AB 900 expedited administrative and judicial review. (2015). The stadium was home to the San Diego Chargers, which moved from Qualcomm to the StubHub Center in Carson, California, following the 2016 NFL season.
(The Los Angeles Chargers will use the StubHub stadium from 2017 until the completion of the Los Angeles Stadium in Hollywood Park, which is planned to open in 2020.) - Golden 1 Center, Sacramento, which is home to NBA’s Sacramento Kings (Construction cost: $558.2M. Opened in 2016): SB 743 (Steinberg, Chapter 386, Statutes of 2013), among other things, established special administrative and judicial review procedures under CEQA for the arena.
- Proposed Farmers Field, downtown Los Angeles: SB 292 (Padilla, Chapter 353, Statutes of 2011), established expedited judicial review procedures and required implementation of specified traffic and air quality mitigation measures under CEQA for a proposed new sports arena and convention center, Anschutz Entertainment Group’s (AEG’s) Farmers Field, in downtown Los Angeles. It is questionable whether the Farmers Field stadium will actually be built. In late March 2013, Los Angeles officials agreed to pursue a parallel track for redeveloping the city’s convention center in the event that AEG and National Football League (NFL) failed to reach agreement on the Farmers Field stadium downtown.
AEG had until October 2014 to find a team before its project agreement with the city expired. A team was not found. - Proposed Los Angeles Stadium at Grand Crossing, City of Industry: ABx3 81 (Hall, Chapter 30, Statutes of 2009), waived environmental review and land use planning requirements as they applied to a proposed NFL football stadium project in the City of Industry. Proponents contended that absent the bill, the project would be delayed needlessly and would jeopardize the project’s financing and postpone the project’s economic benefits.
The project never broke ground. The proposal received approval from regulatory authorities but never found an NFL team willing to move into the proposed stadium.
- Los Angeles Stadium at Hollywood Park, Inglewood, which includes a stadium for the future home to the NFL’s Rams and Chargers, was not subject to CEQA due to a ballot box loophole. The stadium project was subject to a ballot initiative. A voter-proposed initiative is not subject to CEQA. In this case, in February 2015, Inglewood City Council approved the ballot measure directly and avoided an election altogether, which denied voters the opportunity to even vote on the proposal. Although the 298-acre, 80,000 seat, and 10,000 parking space stadium project will likely have significant environmental impacts, those impacts likely go unmitigated without an environmental review. The sports and entertainment district is under construction. (Projected cost: $2.6B. Proposed opening in 2020.)
- A number of major league sports venues that have been built and fully complied with CEQA, include:
As shown above, of the seven major league sports venues that obtained various short-cuts around CEQA, over half of them were either not built or will not house a major league sports team as hoped; and all for reasons unrelated to CEQA.
- Litigation shot clock. This bill provides for expedited judicial review procedures under CEQA for a proposed project within the City of Oakland.
- This bill does not guarantee all lawsuits on a project will be resolved within 270 days. Example: Golden State Warriors Arena and two lawsuits. One project subject to the AB 900 expedited judicial process is the Golden State Warriors Arena and related development at Mission Bay in San Francisco has been challenged under CEQA. One of the plaintiffs, Mission Bay Alliance, which is a coalition of University of California, San Francisco (UCSF) stakeholders, donors, faculty, and physicians, argued that the 18,500-seat arena would congest area streets with traffic, slowing down access to the UCSF Medical Center at Mission Bay, which is located across the street from the proposed arena. In addition, the plaintiff contended that the basketball arena in Mission Bay is at odds with the cluster of life science research and health care facilities that have been built in the neighborhood.
The case, Mission Bay Alliance et al. v Office of Community Investment and Infrastructure, was initially filed on January 7, 2016, in Sacramento County Superior Court. The Golden State Warriors moved for a change of venue and on February 3, 2016 the Sacramento Superior Court granted this request. On March 11, 2016, the CEQA case was received and filed in the San Francisco County Superior Court. On July 18, 2016, a trial court ruled in favor of the project sponsor, the Warriors. On November 29, 2016, the Court of Appeal issued its decision on the case, 327 days after the petition was initially filed. The decision was appealed; and ultimately, in January 2017, the California Supreme Court declined to hear the case.
The above lawsuit is one of two legal challenges filed by the Mission Bay Alliance in regards to the Warriors arena; the second of which is not CEQA-related.
In the second lawsuit, filed in Alameda County, the plaintiffs seek to invalidate an agreement between UCSF and the Warriors, which included a $10 million Mission Bay Transportation Improvement Fund for controlling traffic flow in the area. The plaintiffs contend that the UCSF Chancellor went beyond his authority in reaching this agreement without UC Regents approval. Although the CEQA case had concluded as of January, 2017, the second, non-CEQA-related case in Alameda was still pending at that time.
The Warriors team has stated that the lawsuits have delayed the opening of the arena by one year, to 2019. One lawsuit had special, fast-tracking CEQA-related litigation privileges and the other does not. Although AB 900 expedited the litigation process for the CEQA case, the second lawsuit demonstrates that CEQA is not the only body of law subject to civil litigation and that AB 900 does not guarantee a project from being litigation-free after 270 days. Rather, there is a cavalry of non-CEQA-related causes of action from which a plaintiff may choose and that are subject to standard civil procedure rules.
As demonstrated above, a special CEQA litigation process cannot expedite or insulate a project from non-CEQA-related litigation and cannot ensure that a project will be completed faster. - Equal justice for all? Court calendar preference and guaranteed time frames. Current law requires the courts to give CEQA-related cases preference over “all other civil actions… so that the action or proceeding shall be quickly heard and determined.” (PRC §21167.1). In addition to this existing mandate, SB 734 provides that the courts must complete the judicial review process in a given time frame for certain CEQA-related actions or proceedings when specified criteria are met.
As a consequence, such mandates on a court delay access for other cases as well as potentially exacerbating a court’s backlog on civil documents such as filing a new civil complaint, processing answers and cross complaints, or processing a demurrer or summary judgment. As Judicial Council notes, “[S]etting an extremely tight timeline for deciding these cases has the practical effect of pushing other cases on the courts’ dockets to the back of the line. This means that other cases, including cases that have statutorily mandated calendar preferences, such as juvenile cases, criminal cases, and civil cases in which a party is at risk of dying, will take longer to decide.”
This bill requires a court to make room on its calendar, potentially pushing other cases aside, to ensure that specified time frames are met on certain CEQA cases. Calendar preferences and guaranteed time frames create additional demands and burden on our courts that have very limited resources and a never-ending supply of cases to hear.
- This bill does not guarantee all lawsuits on a project will be resolved within 270 days. Example: Golden State Warriors Arena and two lawsuits. One project subject to the AB 900 expedited judicial process is the Golden State Warriors Arena and related development at Mission Bay in San Francisco has been challenged under CEQA. One of the plaintiffs, Mission Bay Alliance, which is a coalition of University of California, San Francisco (UCSF) stakeholders, donors, faculty, and physicians, argued that the 18,500-seat arena would congest area streets with traffic, slowing down access to the UCSF Medical Center at Mission Bay, which is located across the street from the proposed arena. In addition, the plaintiff contended that the basketball arena in Mission Bay is at odds with the cluster of life science research and health care facilities that have been built in the neighborhood.
- AB 900 vs AB 734 Comparison. AB 246 (Santiago 522, Chapter, Statutes of 2017) extends for two years the expedited CEQA judicial review procedures established by the Jobs and Economic Improvement Through Environmental Leadership Act (AB 900 (Buchanan, Chapter 354, Statutes of 2011). The statute now provides:
- That the Governor must certify a project prior to January 1, 2020, the project must be approved prior to January 1, 2021, and AB 900 sunsets January 1, 2021.
- Requires that a project achieve the LEED good certification.
- Requires transportation efficiency 15% greater than comparable projects.
- Requires a project applicant to demonstrate compliance with the requirement that generators of commercial solid waste and large amounts of organic waste arrange for recycling services for those materials.
- Requires the courts to resolve CEQA lawsuits on AB 900 projects within 270 days to the extent feasible from the date the certified record of proceedings is filed with the court.
This statute was enacted to provide a set of minimum environmental and community benefit criteria that if achieved by a project would allow consideration as a Leadership Project. The criteria provided under AB 734 is considerably weaker and provides greater relief from the CEQA statutes:
- Net Zero GHG Impacts.
AB 900 requires that a project must “not result in any net additional emission of greenhouse gases…”
AB 734 has no requirement to be GHG neutral. Instead makes findings that “Development of a new baseball park and mixed-use project at either location presents an unprecedented opportunity to invest in new and improved transit and transportation infrastructure and implement sustainability measures designed to improve air quality and mitigate the emissions of greenhouse gases resulting from the project.”
- Full Legal Remedies.
AB 900 expedites judicial review and requires lawsuits to be concluded within 270 days after the lead agency certifies the administrative record.
AB 734 dramatically limits judicial review of CEQA compliance. Under AB 734, courts may not stop the project’s construction or operation even if the EIR is seriously deficient. A court only may narrowly limit specific activities (rather than the entire project) that are an “imminent threat to public health” or Native American artifacts.
- LEED Certification.
AB 900 requires the project receive LEED gold certification.
AB 734 requires LEED silver certification, or its equivalent for the arena project, only.
- Conclusion. As noted above, other sports venues have abided by CEQA and still were able to successfully build stadiums and arenas. In fact, over half of the sports venues that sought ways around CEQA failed or were delayed for reasons other than CEQA.
Considering the issues raised above, the Committee may wish to consider whether this bill is prudent or whether it would be more appropriate that the City of Oakland consider applying for the AB 900 process, as was specifically provided for other similar projects.
Related/Prior Legislation
AB 987 (Kamlager-Dove, 2018) Establishes specified administrative and judicial review procedures for the administrative and judicial review of the EIR and approvals granted for a project related to the development of a specified sports and entertainment project in the City of Inglewood meeting certain requirements. Because the lead agency would be required to use these alternative procedures for administrative the bill would specify that the decisions of the lead agency regarding certain analyses and impacts shall not be considered as an abuse of discretion if certain conditions are met.
SB 789 (Bradford, 2017) exempts from the California Environmental Quality Act (CEQA) transportation projects related to the 2028 Los Angeles Olympic Games, as well as a fixed guideway transportation project within the Inglewood Sports and Entertainment Project (ISEP). Limits CEQA review and expedites judicial review of a basketball arena and other related projects within the ISEP. Authorizes the City of Inglewood to commence an eminent domain action against properties within the ISEP prior to completing CEQA review. This bill failed passage in the Assembly Natural Resources Committee.
DOUBLE REFERRAL:
If this measure is approved by the Senate Environmental Quality Committee, the do pass motion must include the action to re-refer the bill to the Senate Judiciary Committee.
SOURCE:
City of Oakland
SUPPORT:
Bay Area Council
City of Emeryville, Mayor John Bauters
City of Berkeley, Mayor Jesse Arreguin
City of San Leandro
Oakland African American Chamber of Commerce
Oakland Chamber of Commerce
Oakland Chinatown Chamber of Commerce
Save Oakland Sports
State Building and Construction Trades Council
1 Individual
OPPOSITION:
Sierra Club
Judicial Council
-- END --
ASSEMBLY THIRD READING
ATR Bill Id:AB 734
Author:(Bonta)
As Amended Ver:March 23, 2017
Majority vote
Committee | Votes | Ayes | Noes |
Local Government | 8-0 | Aguiar-Curry, Bloom, Caballero, Gonzalez Fletcher, Grayson, Lackey, Ridley-Thomas, Voepel |
SUMMARY: Authorizes an infrastructure financing district (IFD) within the City of Oakland to finance public capital facilities or projects that include freight rail. Specifically, this bill:
- Provides that in addition to the projects authorized under existing IFD law, any IFD within the City of Oakland may finance public capital facilities or projects that include freight rail.
- Finds and declares that a special law is necessary and that a general law cannot be made applicable within the meaning of the California Constitution Article IV, Section 16 because of the unique circumstances applicable to the City of Oakland.
EXISTING LAW:
- Authorizes cities and counties to create IFDs and issue bonds to pay for community scale public works: highways, transit, water systems, sewer projects, flood control, child care facilities, libraries, parks, and solid waste facilities.
- Allows an IFD to divert property tax increment revenues from other local governments, excluding school districts, for up to 30 years, in order to pay back bonds issued by the IFD.
- Requires that in order to form an IFD, a city or county must develop an infrastructure plan, send copies to every landowner, consult with other local governments, and hold a public hearing.
- Requires that when forming an IFD, local officials must find that its public facilities are of communitywide significance and provide significant benefits to an area larger than the IFD.
- Requires that every local agency who will contribute its property tax increment revenue to the IFD to approve the plan.
- Requires a two-thirds voter approval of the formation of the IFD and the issuance of bonds.
- Requires majority voter approval for setting the IFD's appropriations limits.
- Specifies that public agencies that own land in a proposed IFD may not vote on issues regarding the district.
- Authorizes IFDs to issue a variety of debt instruments, including bonds, certificates of participation, leases, and loans.
- Requires any IFD that constructs dwelling units to set aside not less than 20% of those units to increase and improve the community's supply of low- and moderate-income housing available at an affordable housing cost to persons and families of low- and moderate-income.
FISCAL EFFECT: None
COMMENTS:
- Bill Summary. This bill authorizes any IFD within the City of Oakland to finance public capital facilities or projects that include freight rail. This bill is sponsored by the City of Oakland.
- Author's Statement. According to the author, "As cities move beyond the dissolution of redevelopment agencies, the City of Oakland seeks to find new and innovative ways of supporting job growth and economic prosperity for our community. In Oakland, infrastructure financing districts have become more attractive especially to help finance public capital facilities such as highways, ramps and bridges, arterial streets and transit facilities.
"Allowing for freight rail to be an eligible beneficiary of IFDs, we will help enhance intermodal capacity for the City and the Port, emissions reduction due to expanded use of rail, and substantially increasing the economic competitiveness of the City."
According to the sponsor, the City of Oakland, "Our economic development agency has taken the steps to move forward on creating IFDs to support the long term, sustainable growth at our three major economic hubs in the City: the Oakland Army Base, the Howard Terminal site, and the area known as Coliseum City. However, to support our role as a port city, a member of the global economy, and enhance West Coast export capacity, we need to include freight rail as an eligible expense for IFDs."
- Prior Legislation. In 2014, AB 2292 (Bonta), Chapter 783, Statutes of 2014 would have allowed an IFD within the Oakland Army Base, the Howard Terminal, or the Coliseum City in the City of Oakland to finance public capital facilities or projects that include freight rail and was heard by this Committee. The bill was later amended into a different topic.
- Arguments in Support. The City of Oakland writes that "Allowing for freight rail to be an eligible beneficiary of IFDs, we will help enhance intermodal capacity for the City and the Port."
- Arguments in Opposition. None on file
Analysis Prepared by: Debbie Michel / L. GOV. / (916) 319-3958 FN: 0000264
Date of Hearing: May 3, 2017
ASSEMBLY COMMITTEE ON LOCAL GOVERNMENT
Cecilia Aguiar-Curry, Chair
ABPCA Bill Id:AB 734 (
Author:Bonta) – As Amended Ver:March 23, 2017
SUBJECT: Infrastructure financing districts: City of Oakland: freight rail.
SUMMARY: Authorizes an infrastructure financing district (IFD) within the City of Oakland to finance public capital facilities or projects that include freight rail. Specifically, this bill:
- Provides that in addition to the projects authorized under existing IFD law, any IFD within the City of Oakland may finance public capital facilities or projects that include freight rail.
- Finds and declares that a special law is necessary and that a general law cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the unique circumstances applicable to the City of Oakland.
EXISTING LAW:
- Authorizes cities and counties to create IFDs and issue bonds to pay for community scale public works: highways, transit, water systems, sewer projects, flood control, child care facilities, libraries, parks, and solid waste facilities.
- Allows an IFD to divert property tax increment revenues from other local governments, excluding school districts, for up to 30 years, in order to pay back bonds issued by the IFD.
- Requires that in order to form an IFD, a city or county must develop an infrastructure plan, send copies to every landowner, consult with other local governments, and hold a public hearing.
- Requires that when forming an IFD, local officials must find that its public facilities are of communitywide significance and provide significant benefits to an area larger than the IFD.
- Requires that every local agency who will contribute its property tax increment revenue to the IFD to approve the plan.
- Requires a two-thirds voter approval of the formation of the IFD and the issuance of bonds.
- Requires majority voter approval for setting the IFD's appropriations limits.
- Specifies that public agencies that own land in a proposed IFD may not vote on issues regarding the district.
- Authorizes IFDs to issue a variety of debt instruments, including bonds, certificates of participation, leases, and loans.
- Requires any IFD that constructs dwelling units to set aside not less than 20% of those units to increase and improve the community’s supply of low- and moderate-income housing available at an affordable housing cost to persons and families of low- and moderate-income.
FISCAL EFFECT: None
COMMENTS:
- Bill Summary. This bill authorizes any IFD within the City of Oakland to finance public capital facilities or projects that include freight rail. This bill is sponsored by the City of Oakland.
- Author’s Statement. According to the author, “As cities move beyond the dissolution of redevelopment agencies, the City of Oakland seeks to find new and innovative ways of supporting job growth and economic prosperity for our community. In Oakland, infrastructure financing districts have become more attractive especially to help finance public capital facilities such as highways, ramps and bridges, arterial streets and transit facilities.
“Allowing for freight rail to be an eligible beneficiary of IFDs, we will help enhance intermodal capacity for the City and the Port, emissions reduction due to expanded use of rail, and substantially increasing the economic competitiveness of the City.”
According to the sponsor, the City of Oakland, “Our economic development agency has taken the steps to move forward on creating IFDs to support the long term, sustainable growth at our three major economic hubs in the City: the Oakland Army Base, the Howard Terminal site, and the area known as Coliseum City. However, to support our role as a port city, a member of the global economy, and enhance West Coast export capacity, we need to include freight rail as an eligible expense for IFDs.”
- Prior Legislation. In 2014, AB 2292 (Bonta) would have allowed an IFD within the Oakland Army Base, the Howard Terminal, or the Coliseum City in the City of Oakland to finance public capital facilities or projects that include freight rail and was heard by this Committee. The bill was later amended into a different topic.
- Arguments in Support. The City of Oakland writes that “Allowing for freight rail to be an eligible beneficiary of IFDs, we will help enhance intermodal capacity for the City and the Port.”
- Arguments in Opposition. None on file
REGISTERED SUPPORT / OPPOSITION:
Support Opposition
City of Oakland [SPONSOR] None on file
Analysis Prepared by: Debbie Michel / L. GOV. / (916) 319-3958
Discussed in Hearing
Assembly Standing Committee on Natural Resources
Senate Floor
Assembly Floor
Senate Standing Committee on Appropriations
Senate Standing Committee on Judiciary
Assembly Floor
Bill Author
Bill Co-Author(s):