AB 2879: High-Speed Rail Authority: contracting.
- Session Year: 2023-2024
- House: Assembly
- Latest Version Date: 2024-09-14
Current Status:
Passed
(2024-09-14: Chaptered by Secretary of State - Chapter 248, Statutes of 2024.)
Introduced
In Committee
First Chamber
In Committee
Second Chamber
Enacted
The California High-Speed Rail Act creates the High-Speed Rail Authority, composed of 11 members, to develop and implement a high-speed rail system in the state, with specified powers and duties. The act authorizes the authority to enter into contracts with private or public entities for the design, construction, and operation of high-speed trains. The act requires the authority to appoint an executive director to administer the affairs of the authority as directed by the authority.
This bill, notwithstanding the authoritys ability to delegate power to the executive director, would require any contract change order with a value greater than $100,000,000 to be approved by the authority.
The California High-Speed Rail Act creates the High-Speed Rail Authority, composed of 11 members, to develop and implement a high-speed rail system in the state, with specified powers and duties. The act authorizes the authority to enter into contracts with private or public entities for the design, construction, and operation of high-speed trains. The act requires the authority to appoint an executive director to administer the affairs of the authority as directed by the authority.
This bill, notwithstanding the authoritys ability to delegate power to the executive director, would require any contract change order with a value greater than $100,000,000 to be approved by the authority.
The California High-Speed Rail Act creates the High-Speed Rail Authority, composed of 11 members, to develop and implement a high-speed rail system in the state, with specified powers and duties. The act authorizes the authority to enter into contracts with private or public entities for the design, construction, and operation of high-speed trains. The act requires the authority to appoint an executive director to administer the affairs of the authority as directed by the authority.
This bill, notwithstanding the authoritys ability to delegate power to the executive director, would require any contract change order with a value greater than $100,000,000 to be approved by the authority.
The California High-Speed Rail Act creates the High-Speed Rail Authority, composed of 11 members, to develop and implement a high-speed rail system in the state, with specified powers and duties. The act authorizes the authority to enter into contracts with private or public entities for the design, construction, and operation of high-speed trains. The act requires the authority to appoint an executive director to administer the affairs of the authority as directed by the authority.
This bill, notwithstanding the authoritys ability to delegate power to the executive director, would require any contract change order with a value greater than $100,000,000 to be approved by the authority.
Notwithstanding the authoritys ability to delegate power to the executive director pursuant to subdivision (a) of Section 185024, a contract change order with a value greater than one hundred million dollars ($100,000,000) shall be approved by the authority.
Notwithstanding the authoritys ability to delegate power to the executive director pursuant to subdivision (a) of Section 185024, a contract change order with a value greater than one hundred million dollars ($100,000,000) shall be approved by the authority.
Notwithstanding the authoritys ability to delegate power to the executive director pursuant to subdivision (a) of Section 185024, any a contract change order with a value greater than one hundred million dollars ($100,000,000) shall be approved by the authority.
Notwithstanding the authoritys ability to delegate power to the executive director pursuant to subdivision (a) of Section 185024, any contract change order with a value greater than one hundred million dollars ($100,000,000) shall be approved by the authority.
|
Date
|
Status
|
|---|---|
| Sep 14, 2024 | Chaptered by Secretary of State - Chapter 248, Statutes of 2024. |
| Sep 14, 2024 | Approved by the Governor. |
| Aug 26, 2024 | Enrolled and presented to the Governor at 4 p.m. |
| Aug 19, 2024 | Senate amendments concurred in. To Engrossing and Enrolling. (Ayes 75. Noes 0. Page 6364.). |
| Aug 15, 2024 | In Assembly. Concurrence in Senate amendments pending. May be considered on or after August 17 pursuant to Assembly Rule 77. |
| Aug 15, 2024 | Read third time. Passed. Ordered to the Assembly. (Ayes 37. Noes 0. Page 5081.). |
| Aug 13, 2024 | Read second time. Ordered to Consent Calendar. |
| Aug 12, 2024 | From committee: Be ordered to second reading file pursuant to Senate Rule 28.8 and ordered to Consent Calendar. |
| Jul 17, 2024 | In committee: Hearing postponed by committee. |
| Jun 26, 2024 | From committee: Do pass and re-refer to Com. on APPR with recommendation: To Consent Calendar. (Ayes 15. Noes 0.) (June 25). Re-referred to Com. on APPR. |
| Jun 12, 2024 | Re-referred to Com. on TRANS. |
| Jun 6, 2024 | From committee chair, with author's amendments: Amend, and re-refer to committee. Read second time, amended, and re-referred to Com. on RLS. |
| May 29, 2024 | Referred to Com. on RLS. |
| May 22, 2024 | In Senate. Read first time. To Com. on RLS. for assignment. |
| May 21, 2024 | Read third time. Passed. Ordered to the Senate. (Ayes 71. Noes 0. Page 5446.) |
| May 16, 2024 | Read second time. Ordered to Consent Calendar. |
| May 15, 2024 | From committee: Do pass. To Consent Calendar. (Ayes 15. Noes 0.) (May 15). |
| Apr 9, 2024 | From committee: Do pass and re-refer to Com. on APPR. with recommendation: To Consent Calendar. (Ayes 15. Noes 0.) (April 8). Re-referred to Com. on APPR. |
| Mar 4, 2024 | Referred to Com. on TRANS. |
| Feb 16, 2024 | From printer. May be heard in committee March 17. |
| Feb 15, 2024 | Read first time. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Aug 19, 2024 | AB 2879 Lackey Concurrence in Senate Amendments | Assembly Floor |
Passed |
|
| Aug 15, 2024 | Consent Calendar 2nd AB2879 Lackey | Senate Floor |
Passed |
|
| Jun 25, 2024 | Do pass, but first be re-referred to the Committee on [Appropriations] with the recommendation: To Consent Calendar | Senate Standing Committee on Transportation |
Passed |
|
| May 21, 2024 | AB 2879 Vince Fong Consent Calendar Second Day Regular Session | Assembly Floor |
Passed |
|
| May 15, 2024 | Do pass. To Consent Calendar. | Assembly Standing Committee on Appropriations |
Passed |
|
| Apr 8, 2024 | Do pass and be re-referred to the Committee on [Appropriations] with recommendation: To Consent Calendar | Assembly Standing Committee on Transportation |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
CONCURRENCE IN SENATE AMENDMENTS
CSA1 Bill Id:AB 2879
Author:(Lackey)
As Amended Ver:June 6, 2024
Majority vote
SUMMARY
Requires any contract change order with a value greater than $100 million be approved by the California High-Speed Rail Authority (CHSRA).
Senate Amendments
- Change bill author from Vince Fong to Assemblymember Lackey.
- Make a minor, technical change.
COMMENTS
"Change order" is the industry term for an amendment to a construction contract that changes the contractor's scope of work. Change orders are inevitable on public infrastructure projects, especially mega projects, due to the construction industry being a complicated, dynamic, and an uncertain business.
Most change orders modify the work required by contract documents (which, in turn, usually increases the contract cost) or adjust the amount of time the contractor has to complete the work, or both. For there to be a valid change order, the owner and contractor must both agree on all terms. On average, change orders account for approximately 8-14% of all capital construction costs.
Key causes of transportation infrastructure project change orders include contract administration, allowable contingencies, quantity omission or error, differing site conditions, and design changes.
SB 1420, (Kopp) Chapter 796, Statutes of 1996 established the California High-Speed Rail Authority (HSRA) to plan and construct a high‑speed rail system that would link the state's major population centers. In November 2008, voters approved Proposition 1A, which authorized the state to sell $10 billion in general obligation bonds to partially fund the system, as well as related projects. Construction of the rail line began in the Central Valley and work is actively underway to construct a double-track fully electrified high-speed rail line between Merced and Bakersfield.
As of the beginning of 2024, $11.7 billion has been spent on capital expenditures, of which, $10.1 billion has been for work between Merced and Bakersfield. Construction of a 22.5 mile segment in the Central Valley from the Tulare-Kern County line to Poplar Avenue in Kern County is substantially complete. Most of the right-of way for the Central Valley construction has been acquired and notable progress is being made to relocate utilities along the current construction segment. In addition, designs for the extensions to Merced and Bakersfield and the four Central Valley stations are on schedule and will reach the 30% design threshold in 2024.
Through 2023, nearly $2 billion has been spent on change orders, or approximately 17% of total capital construction costs. Of these change orders, 10 change orders have exceeded $100 million, three of which occurred in 2023. HSRA posts all of the change orders to the project since 2016 on its website https://hsr.ca.gov/about/transparency-accountability/change-orders/ .
Change orders for the high-speed rail project in 2023 range from $9,557 to fully compensate the contractor for the costs to remove unsuitable soil with concrete debris encountered during the excavation for the Union Pacific Railroad, Westside Shoofly; to $107 million to compensate the contractor for managing utility relocations for AT&T and PG&E; to $154 million for claims from Tutor Perini/Zachry/Parsons to completely resolve delays and time-related claims of the contractor and its subcontractors from 2/2/2021 through 8/1/2023. The largest change order to date was in 2020 for $199 million to compensate the contractor for construction of an intrusion protection barrier.
Currently, the HSRA's CEO approves all change orders under the authority the Board delegates to him. HSRA has an internal processes to approve change orders and the level of review increases as the dollar value of the change order increases. For example, all change orders exceeding $1 million and less than $5 million are approved by a senior contract manager. Change orders between $5 million and $20 million are approved by various high-level internal managers. Changer orders greater than $20 million are approved by the internal business oversight committee. The CEO approves change orders exceeding $25 million and reports them to the Board.
According to HSRA, as the project moves forward, most of the procurements are likely to be smaller in value and as a result it is less likely that HSRA contracts will experience change orders that exceed $100 million.
This bill potentially increases accountability, transparency, and oversight. However, there is a balance to be struck between what is the appropriate threshold to increase accountability and at the same time not be overly burdensome, so that approval of change orders might delay construction. Also, it is unclear if approval by the Board would result in a substantively different outcome than the CEO's approval. The Legislature also may want to consider if there is value in having a group more independent from the project approve change orders, such as the California Transportation Commission (CTC). The CTC approves all change orders for Caltrans projects if the cost increase is 10% greater than the contract amount.
In order to increase oversight of the high-speed rail project and change orders, it may be beneficial to require HSRA to provide more information about change orders on its website. Currently the same level of detail is provided (a few sentences at most) for a change order of several thousand dollars as a change order exceeding $100 million. It may also be useful to add functionality that would allow visitors to the website to be able to download the change order information.
According to the Author
"Fifteen years after the voters approved Proposition 1A, the High Speed Rail Authority has spent $10.4 billion and has yet to complete even 1 mile of total-track. So much money has been mismanaged that the Authority can no longer afford to build even one third of the total route without an infusion of billions of dollars. The public deserves transparency in how the Authority spends their money. Assembly Bill 2879 will require the High-Speed Rail Authority's Board to hold a public hearing and vote during their monthly meetings on change orders that will cost the state $100 million or more. The prolific use of change orders has allowed the High-Speed Rail project to balloon in cost without public oversight. AB 2879 will shed light on the High-Speed Rail change order process in an effort to bring more accountability and transparency into this project."
Arguments in Support
None on file.
Arguments in Opposition
None on file.
FISCAL COMMENTS
According to the Assembly Appropriations Committee "no state costs, in terms of a dollar amount. However, CHSRA contends the bill will delay approval of change orders that, under this bill, must be reported to the CHSRA board in a public hearing and may delay the execution of work while CHSRA awaits board approval before advancing the work in question."
VOTES:
ASM TRANSPORTATION: 15-0-0
YES: Wilson, Davies, Aguiar-Curry, Berman, Juan Carrillo, Hart, Hoover, Jackson, Lowenthal, Papan, Sanchez, Ting, Wallis, Ward, Wicks
ASM APPROPRIATIONS: 15-0-0
YES: Wicks, Sanchez, Arambula, Bryan, Calderon, Wendy Carrillo, Dixon, Mike Fong, Grayson, Haney, Hart, Jim Patterson, Pellerin, Ta, Villapudua
ASSEMBLY FLOOR: 71-0-9
YES: Addis, Aguiar-Curry, Alanis, Alvarez, Arambula, Bains, Bauer-Kahan, Bennett, Berman, Boerner, Bonta, Bryan, Juan Carrillo, Wendy Carrillo, Chen, Connolly, Davies, Dixon, Essayli, Flora, Mike Fong, Vince Fong, Gallagher, Garcia, Gipson, Grayson, Haney, Hart, Hoover, Irwin, Jackson, Jones-Sawyer, Kalra, Lackey, Lee, Low, Lowenthal, Maienschein, McCarty, McKinnor, Muratsuchi, Stephanie Nguyen, Ortega, Pacheco, Jim Patterson, Joe Patterson, Pellerin, Petrie-Norris, Quirk-Silva, Ramos, Rendon, Reyes, Rodriguez, Blanca Rubio, Sanchez, Santiago, Schiavo, Soria, Ta, Ting, Valencia, Villapudua, Waldron, Wallis, Ward, Weber, Wicks, Wilson, Wood, Zbur, Robert Rivas
ABS, ABST OR NV: Calderon, Cervantes, Megan Dahle, Friedman, Gabriel, Holden, Mathis, Papan, Luz Rivas
SENATE FLOOR: 37-0-3
YES: Alvarado-Gil, Archuleta, Ashby, Atkins, Becker, Blakespear, Bradford, Caballero, Cortese, Dahle, Dodd, Durazo, Eggman, Glazer, Gonzalez, Grove, Hurtado, Jones, Laird, Limón, McGuire, Menjivar, Min, Nguyen, Niello, Ochoa Bogh, Padilla, Portantino, Roth, Rubio, Seyarto, Skinner, Smallwood-Cuevas, Stern, Wahab, Wiener, Wilk
ABS, ABST OR NV: Allen, Newman, Umberg
UPDATED
VERSION: June 6, 2024
CONSULTANT: Farra Bracht / TRANS. / (916) 319-2093 FN: 0003986
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | AB 2879 |
CONSENT
Bill No: AB 2879
Author: Lackey (R)
Amended: 6/6/24 in Senate
Vote: 21
SENATE TRANSPORTATION COMMITTEE: 15-0, 6/25/24
AYES: Cortese, Niello, Allen, Archuleta, Becker, Blakespear, Dahle, Dodd, Gonzalez, Laird, Limón, Newman, Nguyen, Seyarto, Umberg
SENATE APPROPRIATIONS COMMITTEE: Senate Rule 28.8
ASSEMBLY FLOOR: 71-0, 5/21/24 (Consent) - See last page for vote
SUBJECT: High-Speed Rail Authority: contracting
SOURCE: Author
DIGEST:
This bill requires any contract change order with a value greater than $100 million to be approved by the High Speed Rail Authority.
ANALYSIS:
Existing law:
- The California High Speed Rail Act creates the High Speed Rail Authority, composed of an 11 member board of directors, oversees the planning, construction and operation of the high speed rail system. (Public Utilities Code (PUC) 18050)
- The authority appoints an executive director who serves at the pleasure of the authority, to administer the affairs of the authority as directed by the authority. (PUC 185024)
This bill prohibits the authority from delegating power to the executive director to approve any contract change order greater than $100 million.
Comments
- Author’s Statement. According to the author, “Fifteen years after the voters approved Proposition 1A, the High Speed Rail Authority has spent $10.4 billion and has yet to complete even 1 mile of total-track. So much money has been mismanaged that the Authority can no longer afford to build even one third of the total route without an infusion of billions of dollars. The public deserves transparency in how the Authority spends their money. Assembly Bill 2879 will require the High-Speed Rail Authority’s Board to hold a public hearing and vote during their monthly meetings on change orders that will cost the state $100 million or more. The prolific use of change orders has allowed the High-Speed Rail project to balloon in cost without public oversight. AB 2879 will shed light on the High-Speed Rail change order process in an effort to bring more accountability and transparency into this project.”
- Change orders. Change orders are issued for work that is added to or deleted from the original scope of work of these contracts. Change orders are not new contracts. They are amendments to the original or existing contracts.
- Scope of authority change orders. Through 2023, nearly $2 billion has been spent on change orders, or approximately 17 percent of total capital construction costs. Of these change orders, 10 change orders have exceeded $100 million, three of which occurred in 2023. Change orders for the high-speed rail project in 2023 range from $9,557 to compensate the contractor for the costs to remove unsuitable soil; to $107 million to compensate the contractor for managing utility relocations for AT&T and PG&E; to $154 million for claims from Tutor Perini/Zachry/Parsons (CP 1 contractor) to resolve delays and time-related claims of the contractor and its subcontractors from 2/2/21 through 8/1/23. The largest change order was in 2020 for $199 million to compensate the contractor for construction of an intrusion protection barrier. The authority posts all change orders to the project since 2016 on its website.
- Change order process. Currently, the executive director, also referred to as the chief executive officer, approves all change orders. The authority has internal processes to approve change orders and the level of review increases as the dollar value of the change order increases. For example, all change orders exceeding $1 million and less than $5 million are approved by a senior contract manager. Change orders between $5 million and $20 million are approved by various high-level internal managers. Changer orders greater than $20 million are approved by the internal business oversight committee.
The executive director approves change orders exceeding $25 million and reports them to the board of directors. The executive director approves and executes new contracts up to $25 million so long as they are consistent with the Program Baseline and Program Budget.
The board of directors reaffirmed this delegation in September 2021 (Board Policy HSRA 11-001). Changes to the executive director’s delegation of authority from the board of directors were made to improve the authority’s change order approval process to promote transparency and increase accountability by streamlining reviews and providing additional training to improve the quality of change order documentation. Changes included:
a) Creating a Change Control Committee for change orders of $1 million or more to review and verify merit earlier in the process.
b) Expanding the role of the Business Oversight Committee.
c) Changing the reporting threshold so all contract amendments and change orders for $25 million or more are reported to the board of directors.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: No
SUPPORT: (Verified 8/12/24)
None received
OPPOSITION: (Verified 8/12/24)
None received
ASSEMBLY FLOOR: 71-0, 5/21/24
AYES: Addis, Aguiar-Curry, Alanis, Alvarez, Arambula, Bains, Bauer-Kahan, Bennett, Berman, Boerner, Bonta, Bryan, Juan Carrillo, Wendy Carrillo, Chen, Connolly, Davies, Dixon, Essayli, Flora, Mike Fong, Vince Fong, Gallagher, Garcia, Gipson, Grayson, Haney, Hart, Hoover, Irwin, Jackson, Jones-Sawyer, Kalra, Lackey, Lee, Low, Lowenthal, Maienschein, McCarty, McKinnor, Muratsuchi, Stephanie Nguyen, Ortega, Pacheco, Jim Patterson, Joe Patterson, Pellerin, Petrie-Norris, Quirk-Silva, Ramos, Rendon, Reyes, Rodriguez, Blanca Rubio, Sanchez, Santiago, Schiavo, Soria, Ta, Ting, Valencia, Villapudua, Waldron, Wallis, Ward, Weber, Wicks, Wilson, Wood, Zbur, Robert Rivas
NO VOTE RECORDED: Calderon, Cervantes, Megan Dahle, Friedman, Gabriel, Holden, Mathis, Papan, Luz Rivas
Prepared by: Benjamin O'Brien-Hokanson / TRANS. / (916) 651-4121
8/14/24 15:50:39
**** END ****
SENATE COMMITTEE ON TRANSPORTATION
Senator Dave Cortese, Chair
2023 - 2024 Regular
Bill No: AB 2879 Hearing Date: 6/25/2024
Author: | Lackey | ||
Version: | 6/6/2024 Amended | ||
Urgency: | No | Fiscal: | Yes |
Consultant: | Bob Franzoia | ||
SUBJECT: High-Speed Rail Authority: contracting
DIGEST: This bill would require any contract change order with a value greater than $100 million to be approved by the High Speed Rail Authority.
ANALYSIS:
Existing law:
- The California High Speed Rail Act creates the High Speed Rail Authority, composed of an 11 member board of directors, oversees the planning, construction and operation of the high speed rail system. (PUC 18050)
- The authority appoints an executive director who serves at the pleasure of the authority, to administer the affairs of the authority as directed by the authority. (PUC 185024)
This bill:
- Would prohibit the authority from delegating power to the executive director to approve any contract change order greater than $100 million.
COMMENTS:
- Author’s Statement. According to the author, “Fifteen years after the voters approved Proposition 1A, the High Speed Rail Authority has spent $10.4 billion and has yet to complete even 1 mile of total-track. So much money has been mismanaged that the Authority can no longer afford to build even one third of the total route without an infusion of billions of dollars. The public deserves transparency in how the Authority spends their money. Assembly Bill 2879 will require the High-Speed Rail Authority’s Board to hold a public hearing and vote during their monthly meetings on change orders that will cost the state $100 million or more. The prolific use of change orders has allowed the High-Speed Rail project to balloon in cost without public oversight. AB 2879 will shed light on the High-Speed Rail change order process in an effort to bring more accountability and transparency into this project.”
- Change orders. Change orders are issued for work that is added to or deleted from the original scope of work of these contracts. Change orders are not new contracts. They are amendments to the original or existing contracts.
- Scope of authority change orders. Through 2023, nearly $2 billion has been spent on change orders, or approximately 17 percent of total capital construction costs. Of these change orders, 10 change orders have exceeded $100 million, three of which occurred in 2023. Change orders for the high-speed rail project in 2023 range from $9,557 to compensate the contractor for the costs to remove unsuitable soil; to $107 million to compensate the contractor for managing utility relocations for AT&T and PG&E; to $154 million for claims from Tutor Perini/Zachry/Parsons (CP 1 contractor) to resolve delays and time-related claims of the contractor and its subcontractors from 2/2/2021 through 8/1/2023. The largest change order was in 2020 for $199 million to compensate the contractor for construction of an intrusion protection barrier. The authority posts all change orders to the project since 2016 on its website.
- Change order process. Currently, the executive director, also referred to as the chief executive officer, approves all change orders. The authority has internal processes to approve change orders and the level of review increases as the dollar value of the change order increases. For example, all change orders exceeding $1 million and less than $5 million are approved by a senior contract manager. Change orders between $5 million and $20 million are approved by various high-level internal managers. Changer orders greater than $20 million are approved by the internal business oversight committee.
The executive director approves change orders exceeding $25 million and reports them to the board of directors. The executive director approves and executes new contracts up to $25 million so long as they are consistent with the Program Baseline and Program Budget.
The board of directors reaffirmed this delegation in September 2021 (Board Policy HSRA 11-001). Changes to the executive director’s delegation of authority from the board of directors were made to improve the authority’s change order approval process to promote transparency and increase accountability by streamlining reviews and providing additional training to improve the quality of change order documentation. Changes included:
a) Creating a Change Control Committee for change orders of $1 million or more to review and verify merit earlier in the process.
b) Expanding the role of the Business Oversight Committee.
c) Changing the reporting threshold so all contract amendments and change orders for $25 million or more are reported to the board of directors.
Related Legislation:
SB 198 (Budget, Chapter 71, Statutes of 2020). Required the authority to develop schedules for the delivery of specified tasks relating to the project for inclusion in the project update report and the business plan, required the authority to include certain other information in the project update report and the business plan relating to the Merced to Bakersfield segment of project and required the authority to notify the Legislature before submitting a federal grant application and before releasing a request for proposals after June 1, 2022, for contracts relating to specified aspects of the high-speed rail system. This bill established the High-Speed Rail Authority Office of the Inspector General and provided that the office is not a subdivision of any other governmental entity and authorized the inspector general to initiate audits and reviews related to the delivery of the high-speed rail project and the selection and oversight of contractors.
FISCAL EFFECT: Appropriation: Fiscal Com.: Local:
POSITIONS: (Communicated to the committee before noon on Wednesday,
June 19, 2024.)
SUPPORT:
None Received
OPPOSITION:
None Received
-- END --
Date of Hearing: May 15, 2024
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Buffy Wicks, Chair
ABPCA Bill Id:AB 2879
Author:(Vince Fong) – As Introduced Ver:February 15, 2024
Policy Committee: | Transportation | Vote: | 15 - 0 |
|
| ||
|
|
Urgency: No State Mandated Local Program: No Reimbursable: No
SUMMARY:
This bill requires any contract change order with a value greater than $100 million be approved by the California High-Speed Rail Authority (CHSRA).
FISCAL EFFECT:
No state costs, in terms of a dollar amount. However, CHSRA contends the bill will delay approval of change orders that, under this bill, must be reported to the CHSRA board in a public hearing and may delay the execution of work while CHSRA awaits board approval before advancing the work in question.
COMMENTS:
- Purpose. The author believes the High-Speed Rail Authority has “mismanaged” large amounts of money and intends this bill to make more transparent the authority’s fiscal decisions. According to the author:
The prolific use of change orders has allowed the High-Speed Rail project to balloon in cost without public oversight. AB 2879 will shed light on the High-Speed Rail change order process in an effort to bring more accountability and transparency into this project.
- Background. SB 1420 (Kopp), Chapter 796, Statutes of 1996, established the High-Speed Rail Authority to plan and construct a high‑speed rail system that would link the state’s major population centers. In November 2008, voters approved Proposition 1A, which authorized the state to sell $10 billion in general obligation bonds to partially fund the system, as well as related projects. Construction of the rail line began in the Central Valley and work is actively underway to construct a double-track fully electrified high-speed rail line between Merced and Bakersfield.
As of the beginning of 2024, $11.7 billion has been spent on capital expenditures, of which, $10.1 billion has been for work between Merced and Bakersfield.
A change order, in the context of construction projects, is, as the name implies, a change of any kind to the scope of work or terms of a construction contract. See, for, example, the description of “change order” provided by the Associated General Contractors of America:
A “change order” refers to an official change of any kind in the original scope of work or terms of a construction contract agreed to by the owner, contractor, and project designer. Change orders include work that must be added or removed from the original contract in order to best serve the finished product of a project. Depending on the magnitude of change that is needed, the original contract amount and terms may be significantly altered.
The high-speed rail project has had many change orders, perhaps predictably so, given the tremendous magnitude of the project. Helpfully, the CHSRA lists online every change order for the project, and the associated dollar amount, at https://hsr.ca.gov/about/transparency-accountability/change-orders/. According to the listing, the project has experienced nearly $2 billion in change orders since 2016. While some of these change orders are quite small, relative to overall project spending, at least 10 change orders have topped $100 million.
Consistent with statute, CHSRA has established a process for administrative review of change orders, according to which the authority’s chief executive officer (CEO) approves every change order, with review of an given change order occurring at different administrative levels within the authority, based on the dollar amount of the change order in question. For example, the authority’s processes require the CEO to review any change order with a dollar value of greater than $25 million.
The CHSRA board is made up of 11 members: five appointed by the Governor, two appointed by the Senate Committee on Rules, two appointed by the Speaker of the Assembly and one each ex-officio member appointed by the Senate and the Assembly. The CHSRA appoints the CEO, subject to Senate confirmation. The author intends to increase scrutiny—and the transparency of that scrutiny—of change orders of particularly large dollar amounts by requiring the authority itself to approve change order with a value greater than $100 million. However—and as noted in the policy committee analysis of this bill—it is reasonable to question whether the authority would make a decision on any given change order that differs from the decision the authority’s CEO would have made. For this reason, and, again, as suggested by the policy committee analysis of this bill, the author may wish to consider assigning review of very large change orders to an entity that is more independent from the authority than is the authority’s own CEO.
Analysis Prepared by: Jay Dickenson / APPR. / (916) 319-2081
Date of Hearing: April 8, 2024
ASSEMBLY COMMITTEE ON TRANSPORTATION
Lori D. Wilson, Chair
ABPCA Bill Id:AB 2879 (
Author:Vince Fong) – As Introduced Ver:February 15, 2024
SUBJECT: High-Speed Rail Authority: contracting.
SUMMARY: Requires the California High-Speed Rail Authority (HSRA) to approve any contract change order with a value greater than $100 million.
EXISTING LAW:
- Creates the HSRA in the California State Transportation Agency with 11 members: five appointed by the Governor, two appointed by Senate Committee on Rules, two appointed by the Speaker of the Assembly, and one each ex-officio member appointed by the Senate and Assembly. (Public Utilities Code Section 185020)
- Requires HSRA to direct the development and implementation of an intercity high-speed rail service. (PUC 185030)
- Authorizes the HSRA to enter into contracts with private or public entities for the design, construction, and operation of high-speed trains. (PUC 185036)
- Requires HSRA to appoint an executive director to administer the affairs of the authority. (PUC 185024)
FISCAL EFFECT: Unknown
COMMENTS: "Change order" is the industry term for an amendment to a construction contract that changes the contractor's scope of work. Change orders are inevitable on public infrastructure projects, especially mega projects, due to the construction industry being a complicated, dynamic, and an uncertain business.
Most change orders modify the work required by contract documents (which, in turn, usually increases the contract cost) or adjust the amount of time the contractor has to complete the work, or both. For there to be a valid change order, the owner and contractor must both agree on all terms. On average, change orders account for approximately 8-14% of all capital construction costs.
Key causes of transportation infrastructure project change orders include contract administration, allowable contingencies, quantity omission or error, differing site conditions, and design changes.
Chapter 796 of 1996 (SB 1420, Kopp) established HSRA to plan and construct a high‑speed rail system that would link the state’s major population centers. In November 2008, voters approved Proposition 1A, which authorized the state to sell $10 billion in general obligation bonds to partially fund the system, as well as related projects. Construction of the rail line began in the Central Valley and work is actively underway to construct a double-track fully electrified high-speed rail line between Merced and Bakersfield.
As of the beginning of 2024, $11.7 billion has been spent on capital expenditures, of which, $10.1 billion has been for work between Merced and Bakersfield. Construction of a 22.5 mile segment in the Central Valley from the Tulare-Kern County line to Poplar Avenue in Kern County is substantially complete. Most of the right-of way for the Central Valley construction has been acquired and notable progress is being made to relocate utilities along the current construction segment. In addition, designs for the extensions to Merced and Bakersfield and the four Central Valley stations are on schedule and will reach the 30% design threshold in 2024.
Through 2023, nearly $2 billion has been spent on change orders, or approximately 17% of total capital construction costs. Of these change orders, 10 change orders have exceeded $100 million, three of which occurred in 2023. HSRA posts all of the change orders to the project since 2016 on its website https://hsr.ca.gov/about/transparency-accountability/change-orders/ .
Change orders for the high-speed rail project in 2023 range from $9,557 to fully compensate the contractor for the costs to remove unsuitable soil with concrete debris encountered during the excavation for the Union Pacific Railroad, Westside Shoofly; to $107 million to compensate the contractor for managing utility relocations for AT&T and PG&E; to $154 million for claims from Tutor Perini/Zachry/Parsons to completely resolve delays and time-related claims of the contractor and its subcontractors from 2/2/2021 through 8/1/2023. The largest change order to date was in 2020 for $199 million to compensate the contractor for construction of an intrusion protection barrier.
Currently, the HSRA’s CEO approves all change orders under the authority the Board delegates to him. HSRA has an internal processes to approve change orders and the level of review increases as the dollar value of the change order increases. For example, all change orders exceeding $1 million and less than $5 million are approved by a senior contract manager. Change orders between $5 million and $20 million are approved by various high-level internal managers. Changer orders greater than $20 million are approved by the internal business oversight committee. The CEO approves change orders exceeding $25 million and reports them to the Board.
According to HSRA, as the project moves forward, most of the procurements are likely to be smaller in value and as a result it is less likely that HSRA contracts will experience change orders that exceed $100 million.
According to the author: “Fifteen years after the voters approved Proposition 1A, the High-Speed Rail Authority has spent $10.4 billion and has yet to complete even 1 mile of total-track. So much money has been mismanaged that the Authority can no longer afford to build even one-third of the total route without an infusion of billions of dollars. The public deserves transparency in how the Authority spends their money. Assembly Bill 2879 will require the High-Speed Rail Authority’s Board to hold a public hearing and vote during their monthly meetings on change orders that will cost the state $100 million or more. The prolific use of change orders has allowed the High-Speed Rail project to balloon in cost without public oversight. AB 2879 will shed light on the High-Speed Rail change order process in an effort to bring more accountability and transparency into this project.”
Committee Comments: While change orders are an essential part of the construction process, the high-speed rail project has experienced a magnitude of change orders that exceeds the industry norm. This may, in part, be due to the project being a mega-project. Mega-projects often encounter more significant challenges than less complicated projects where the state has years of experience.
This bill potentially increases accountability, transparency, and oversight. However, there is a balance to be struck between what is the appropriate threshold to increase accountability and at the same time not be overly burdensome, so that approval of change orders might delay construction. Also, it is unclear if approval by the Board would result in a substantively different outcome than the CEO’s approval. The Legislature also may want to consider if there is value in having a group more independent from the project approve change orders, such as the California Transportation Commission (CTC). The CTC approves all change orders for Caltrans projects if the cost increase is 10% greater than the contract amount.
In order to increase oversight of the high-speed rail project and change orders, it may be beneficial to require HSRA to provide more information about change orders on its website. Currently the same level of detail is provided (a few sentences at most) for a change order of several thousand dollars as a change order exceeding $100 million. It may also be useful to add functionality that would allow visitors to the website to be able to download the change order information.
Related legislation: AB 441 (Patterson) of 2013 requires the authority to provide, to the appropriate policy and fiscal committees of the Legislature, a copy of each contract entered into by the authority if the dollar value of the goods or services to be provided or performed under the contract is $25,000 or more, as well as a copy of each contract amendment and contract change order agreed to by the authority for $25,000 or more. (This bill died in the Assembly Transportation Committee.)
AB 463 (Logue) of 2013 requires the same reports as AB 441, but also for each contractor and subcontractor. (This bill died in the Assembly Transportation Committee.)
AB 456 (Chiu), Chapter 489, Statutes of 2019 extends the operations of the public contract claims resolution process until January 1, 2027. This claim process prescribes various requirements regarding the formation, content, and enforcement of state and local public contracts. It also makes a claim resolution process applicable to any claim by a contractor in connection with a public works project against a public entity.
AB 1235 (Patterson) of 2021 creates the Joint Legislative High-Speed Rail Oversight Committee to provide ongoing and independent oversight of the high-speed rail project by performing specified duties, and would require the committee to make recommendations to the appropriate standing policy and budget committees of both houses of the Legislature to guide decisions concerning the state’s programs, policies, and investments related to high-speed rail. The bill would require the authority to provide the committee with certain documents and information within prescribed timelines and change orders. (This bill died in the Assembly Transportation Committee).
REGISTERED SUPPORT / OPPOSITION:
Support
None on file
Opposition
None on file
Analysis Prepared by: Farra Bracht / TRANS. / (916) 319-2093