SB 385: Public Utilities Commission: reports: programs: studies: ex parte communications.
- Session Year: 2017-2018
- House: Senate
- Latest Version Date: 2017-10-02
(1)The California Constitution establishes the Public Utilities Commission and authorizes the commission to exercise ratemaking and rulemaking authority over all public utilities, as defined, subject to control by the Legislature. Existing law requires the commission to report various information to the Legislature.
This bill would move certain of the commissions reporting requirements within the Public Utilities Act to an article pertaining to reports by the commission to the Legislature and make other conforming changes.
(2)Existing law requires the commission to submit to the Legislature by January 1, 1993, and on each January 1 thereafter, a detailed budget for expenditure of railroad corporation fees for the ensuing budget year.
This bill would move that provision to the article within the Public Utilities Act pertaining to reports by the commission to the Legislature.
(3)Existing law requires the commission to report annually on its efforts to identify ratepayer-funded energy efficiency programs that are similar to programs administered by the State Energy Resources Conservation and Development Commission, the State Air Resources Board, and the California Alternative Energy and Advanced Transportation Financing Authority.
This bill would instead require the commission to, on or before December 31, 2018, and biennially thereafter, as part of a specified report, identify and report to the Legislature on electrical and gas corporation ratepayer-funded energy efficiency programs that are similar to programs administered by those state agencies.
(4)The Public Utilities Act requires the commission to determine whether a proceeding requires a hearing and, if so, to determine whether the matter requires a quasi-legislative, adjudication, or ratesetting hearing. Existing law regulates communications in matters before the commission and defines an ex parte communication as any oral or written communication between a decisionmaker and an interested person concerning any matter before the commission that the commission has not specified as being a procedural matter and that does not occur in a public hearing, workshop, or other public proceeding, or on the official record of the proceeding on the matter. The act provides that ex parte communications are prohibited in adjudication cases, and that ex parte communications are subject to specified disclosure requirements in ratesetting cases. The act provides that ex parte communications in quasi-legislative cases are permitted and not subject to those specified disclosure requirements, except when the commission determines otherwise.
This bill would revise various laws relating to ex parte communications in regard to commission proceedings.
(5)Under existing law, when the coordinator for California area code relief determines the need to establish a new area code, he or she is required to provide written notice to the commission regarding the need to establish the new area code. Existing law requires the coordinator and commission staff to conduct at least one meeting for representatives of local jurisdictions, and at least 3 public meetings in the affected geographical area, for specified purposes relating to transitioning phone service to a new area code.
This bill would require the coordinator and commission staff to notify representatives of local jurisdictions and the public in affected areas, and instead of requiring them would authorize them, at the discretion of the commission, to conduct one or more meetings both for representatives of local jurisdictions and for members of the public in affected geographic areas for those same purposes.
(6)This bill would repeal obsolete auditing, reporting, and other similar requirements on the commission.
(7)Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.
Because some of the provisions of this bill would be a part of the act and because a violation of an order or decision of the commission implementing its requirements would be a crime, the bill would impose a state-mandated local program by expanding the application of a crime.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
(1)The California Constitution establishes the Public Utilities Commission and authorizes the commission to exercise ratemaking and rulemaking authority over all public utilities, as defined, subject to control by the Legislature. Existing law requires the commission to report various information to the Legislature.
This bill would move certain of the commissions reporting requirements within the Public Utilities Act to an article pertaining to reports by the commission to the Legislature and make other conforming changes.
(2)Existing law requires the commission to submit to the Legislature by January 1, 1993, and on each January 1 thereafter, a detailed budget for expenditure of railroad corporation fees for the ensuing budget year.
This bill would move that provision to the article within the Public Utilities Act pertaining to reports by the commission to the Legislature.
(3)Existing law requires the commission to report annually on its efforts to identify ratepayer-funded energy efficiency programs that are similar to programs administered by the State Energy Resources Conservation and Development Commission, the State Air Resources Board, and the California Alternative Energy and Advanced Transportation Financing Authority.
This bill would instead require the commission to, on or before December 31, 2018, and biennially thereafter, as part of a specified report, identify and report to the Legislature on electrical and gas corporation ratepayer-funded energy efficiency programs that are similar to programs administered by those state agencies.
(4)The Public Utilities Act requires the commission to determine whether a proceeding requires a hearing and, if so, to determine whether the matter requires a quasi-legislative, adjudication, or ratesetting hearing. Existing law regulates communications in matters before the commission and defines an ex parte communication as any oral or written communication between a decisionmaker and an interested person concerning any matter before the commission that the commission has not specified as being a procedural matter and that does not occur in a public hearing, workshop, or other public proceeding, or on the official record of the proceeding on the matter. The act provides that ex parte communications are prohibited in adjudication cases, and that ex parte communications are subject to specified disclosure requirements in ratesetting cases. The act provides that ex parte communications in quasi-legislative cases are permitted and not subject to those specified disclosure requirements, except when the commission determines otherwise.
This bill would revise various laws relating to ex parte communications in regard to commission proceedings.
(5)Under existing law, when the coordinator for California area code relief determines the need to establish a new area code, he or she is required to provide written notice to the commission regarding the need to establish the new area code. Existing law requires the coordinator and commission staff to conduct at least one meeting for representatives of local jurisdictions, and at least 3 public meetings in the affected geographical area, for specified purposes relating to transitioning phone service to a new area code.
This bill would require the coordinator and commission staff to notify representatives of local jurisdictions and the public in affected areas, and instead of requiring them would authorize them, at the discretion of the commission, to conduct one or more meetings both for representatives of local jurisdictions and for members of the public in affected geographic areas for those same purposes.
(6)This bill would repeal obsolete auditing, reporting, and other similar requirements on the commission.
(7)Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.
Because some of the provisions of this bill would be a part of the act and because a violation of an order or decision of the commission implementing its requirements would be a crime, the bill would impose a state-mandated local program by expanding the application of a crime.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
(1)The California Constitution establishes the Public Utilities Commission and authorizes the commission to exercise ratemaking and rulemaking authority over all public utilities, as defined, subject to control by the Legislature. Existing law requires the commission to report various information to the Legislature.
This bill would move certain of the commissions reporting requirements within the Public Utilities Act to an article pertaining to reports by the commission to the Legislature and make other conforming changes.
(2)Existing law requires the commission to submit to the Legislature by January 1, 1993, and on each January 1 thereafter, a detailed budget for expenditure of railroad corporation fees for the ensuing budget year.
This bill would move that provision to the article within the Public Utilities Act pertaining to reports by the commission to the Legislature.
(3)Existing law requires the commission to report annually on its efforts to identify ratepayer-funded energy efficiency programs that are similar to programs administered by the State Energy Resources Conservation and Development Commission, the State Air Resources Board, and the California Alternative Energy and Advanced Transportation Financing Authority.
This bill would instead require the commission to, on or before December 31, 2018, and biennially thereafter, as part of a specified report, identify and report to the Legislature on electrical and gas corporation ratepayer-funded energy efficiency programs that are similar to programs administered by those state agencies.
(4)The Public Utilities Act requires the commission to determine whether a proceeding requires a hearing and, if so, to determine whether the matter requires a quasi-legislative, adjudication, or ratesetting hearing. Existing law regulates communications in matters before the commission and defines an ex parte communication as any oral or written communication between a decisionmaker and an interested person concerning any matter before the commission that the commission has not specified as being a procedural matter and that does not occur in a public hearing, workshop, or other public proceeding, or on the official record of the proceeding on the matter. The act provides that ex parte communications are prohibited in adjudication cases, and that ex parte communications are subject to specified disclosure requirements in ratesetting cases. The act provides that ex parte communications in quasi-legislative cases are permitted and not subject to those specified disclosure requirements, except when the commission determines otherwise.
This bill would revise various laws relating to ex parte communications in regard to commission proceedings.
(5)Under existing law, when the coordinator for California area code relief determines the need to establish a new area code, he or she is required to provide written notice to the commission regarding the need to establish the new area code. Existing law requires the coordinator and commission staff to conduct at least one meeting for representatives of local jurisdictions, and at least 3 public meetings in the affected geographical area, for specified purposes relating to transitioning phone service to a new area code.
This bill would require the coordinator and commission staff to notify representatives of local jurisdictions and the public in affected areas, and instead of requiring them would authorize them, at the discretion of the commission, to conduct one or more meetings both for representatives of local jurisdictions and for members of the public in affected geographic areas for those same purposes.
(6)This bill would repeal obsolete auditing, reporting, and other similar requirements on the commission.
(7)Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.
Because some of the provisions of this bill would be a part of the act and because a violation of an order or decision of the commission implementing its requirements would be a crime, the bill would impose a state-mandated local program by expanding the application of a crime.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
(1)The California Constitution establishes the Public Utilities Commission and authorizes the commission to exercise ratemaking and rulemaking authority over all public utilities, as defined, subject to control by the Legislature. Existing law requires the commission to report various information to the Legislature.
This bill would move certain of the commissions reporting requirements within the Public Utilities Act to an article pertaining to reports by the commission to the Legislature and make other conforming changes.
(2)Existing law requires the commission to submit to the Legislature by January 1, 1993, and on each January 1 thereafter, a detailed budget for expenditure of railroad corporation fees for the ensuing budget year.
This bill would move that provision to the article within the Public Utilities Act pertaining to reports by the commission to the Legislature.
(3)Existing law requires the commission to report annually on its efforts to identify ratepayer-funded energy efficiency programs that are similar to programs administered by the State Energy Resources Conservation and Development Commission, the State Air Resources Board, and the California Alternative Energy and Advanced Transportation Financing Authority.
This bill would instead require the commission to, on or before December 31, 2018, and biennially thereafter, as part of a specified report, identify and report to the Legislature on electrical and gas corporation ratepayer-funded energy efficiency programs that are similar to programs administered by those state agencies.
(4)The Public Utilities Act requires the commission to determine whether a proceeding requires a hearing and, if so, to determine whether the matter requires a quasi-legislative, adjudication, or ratesetting hearing. Existing law requires a commissioner assigned to a proceeding to prepare and issue by order or ruling a scoping memo that describes the issues to be considered and the applicable timetable for resolution, and, in adjudication and ratesetting proceedings, requires the assigned commissioner to additionally schedule a prehearing conference. Existing law regulates communications in matters before the commission and defines an ex parte communication as any oral or written communication between a decisionmaker and an interested person concerning any matter before the commission that the commission has not specified as being a procedural matter and that does not occur in a public hearing, workshop, or other public proceeding, or on the official record of the proceeding on the matter. Existing law requires the commission, by rule, to adopt and publish any requirements for written reporting of ex parte communications and appropriate sanctions for noncompliance with any rule proscribing ex parte communications. The act provides that ex parte communications are prohibited in adjudication cases, and that ex parte communications are subject to specified disclosure requirements in ratesetting cases. The act provides that ex parte communications in quasi-legislative cases are permitted and not subject to those specified disclosure requirements, except when the commission determines otherwise.
This bill would authorize the assigned commissioner in an uncontested adjudication or uncontested quasi-legislative proceeding to exercise his or her discretion to not prepare and issue a scoping memo or to not order a prehearing conference, as applicable. The bill would revise various laws relating to ex parte communications in regard to commission proceedings.
(5)Under existing law, when the coordinator for California area code relief determines the need to establish a new area code, he or she is required to provide written notice to the commission regarding the need to establish the new area code. Existing law requires the coordinator and commission staff to conduct at least one meeting for representatives of local jurisdictions, and at least 3 public meetings in the affected geographical area, for specified purposes relating to transitioning phone service to a new area code.
This bill would require the coordinator and commission staff to notify representatives of local jurisdictions and the public in affected areas, and instead of requiring them would authorize them, at the discretion of the commission, to conduct one or more meetings both for representatives of local jurisdictions and for members of the public in affected geographic areas for those same purposes.
(6)This bill would repeal obsolete auditing, reporting, and other similar requirements on the commission.
(7)Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.
Because some of the provisions of this bill would be a part of the act and because a violation of an order or decision of the commission implementing its requirements would be a crime, the bill would impose a state-mandated local program by expanding the application of a crime.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
(1)The California Constitution establishes the Public Utilities Commission and authorizes the commission to exercise ratemaking and rulemaking authority over all public utilities, as defined, subject to control by the Legislature. Existing law requires the commission to report various information to the Legislature.
This bill would recast move certain of the commissions reporting requirements to an article within the Public Utilities Act to an article pertaining to reports by the commission to the Legislature and make other conforming changes.
(2)Existing law requires the commission to submit to the Legislature by January 1, 1993, and on each January 1 thereafter, a detailed budget for expenditure of railroad corporation fees for the ensuing budget year.
This bill would recast move that provision to the article within the Public Utilities Act pertaining to reports by the commission to the Legislature.
(3)Existing law requires the commission or the California State Auditors Office, as specified, to, commencing with the 199394 fiscal year and in each subsequent fiscal year until the 19992000 fiscal year, conduct an audit of the expenditure of specified funds. Existing law requires the results of these audits to be reported, in writing, to the appropriate policy and budget committees of the respective houses of the Legislature.This bill would repeal those provisions.(4)Existing law requires the commission, in conjunction with the California Environmental Protection Agency, to request, no later than July 1, 1992, the appropriate federal agencies to take specified actions relating to hazardous substances and materials. Existing law requires the commission to report to the Legislature on the status of its requests no later than September 30, 1992, and every 6 months thereafter until September 30, 1995.This bill would repeal these provisions.(5)Existing law requires the commission to, in a single rulemaking or other appropriate proceeding, not to exceed 18 months in duration, consider the need for performance reliability standards for all backup power systems installed on the property of residential and small commercial customers by a facilities-based provider of telephony services. Existing law requires the commission, before January 1, 2008, to prepare and submit to the Legislature a report on the results of the proceeding.This bill would repeal these provisions.(6)Existing law requires the commission to, on or before February 1, 2001, issue an order initiating an investigation and opening a proceeding to examine the current and future definitions of universal service. Existing law requires the commission to complete its investigation and report to the Legislature its findings and recommendations on or before January 1, 2002.This bill would repeal the provision requiring the commission to take those actions on or before January 1, 2002.(7)(3)Existing law requires the commission to report annually on its efforts to identify ratepayer-funded energy efficiency programs that are similar to programs administered by the State Energy Resources Conservation and Development Commission, the State Air Resources Board, and the California Alternative Energy and Advanced Transportation Financing Authority.
This bill would instead require the commission to, on or before December 31, 2018, and biennially thereafter, as part of a specified report, identify and report to the Legislature on electrical and gas corporation ratepayer-funded energy efficiency programs that are similar to programs administered by those state agencies.
(8)Existing law provides that it is the intent of the Legislature that the commission may authorize specified pilot programs relating to rail crossings prior to January 1, 2003, and requires the commission to report to the Legislature by March 31, 2004, on the outcome of those pilot programs.This bill would repeal those provisions.(9)Existing law requires the commission to, on or before March 1, 2000, request from each telephone corporation doing business in this state that possesses one or more telephone number prefixes, or a portion thereof, the specific telephone numbers and the quantities within the possession of the provider, both in use and not in use. Existing law requires the commission to use that information and any other information required by the commission, to prepare and submit to the Legislature, on or before July 1, 2001, a study of telecommunications industry use rates.This bill would repeal those provisions.(4)The Public Utilities Act requires the commission to determine whether a proceeding requires a hearing and, if so, to determine whether the matter requires a quasi-legislative, adjudication, or ratesetting hearing. Existing law requires a commissioner assigned to a proceeding to prepare and issue by order or ruling a scoping memo that describes the issues to be considered and the applicable timetable for resolution, and, in adjudication and ratesetting proceedings, requires the assigned commissioner to additionally schedule a prehearing conference. Existing law regulates communications in matters before the commission and defines an ex parte communication as any oral or written communication between a decisionmaker and an interested person concerning any matter before the commission that the commission has not specified as being a procedural matter and that does not occur in a public hearing, workshop, or other public proceeding, or on the official record of the proceeding on the matter. Existing law requires the commission, by rule, to adopt and publish any requirements for written reporting of ex parte communications and appropriate sanctions for noncompliance with any rule proscribing ex parte communications. The act provides that ex parte communications are prohibited in adjudication cases, and that ex parte communications are subject to specified disclosure requirements in ratesetting cases. The act provides that ex parte communications in quasi-legislative cases are permitted and not subject to those specified disclosure requirements, except when the commission determines otherwise.
This bill would authorize the assigned commissioner in an uncontested adjudication or uncontested quasi-legislative proceeding to exercise his or her discretion to not prepare and issue a scoping memo or to not order a prehearing conference, as applicable. The bill would revise various laws relating to ex parte communications in regard to commission proceedings.
(5)Under existing law, when the coordinator for California area code relief determines the need to establish a new area code, he or she is required to provide written notice to the commission regarding the need to establish the new area code. Existing law requires the coordinator and commission staff to conduct at least one meeting for representatives of local jurisdictions, and at least 3 public meetings in the affected geographical area, for specified purposes relating to transitioning phone service to a new area code.
This bill would require the coordinator and commission staff to notify representatives of local jurisdictions and the public in affected areas, and instead of requiring them would authorize them, at the discretion of the commission, to conduct one or more meetings both for representatives of local jurisdictions and for members of the public in affected geographic areas for those same purposes.
(6)This bill would repeal obsolete auditing, reporting, and other similar requirements on the commission.
(7)Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.
Because some of the provisions of this bill would be a part of the act and because a violation of an order or decision of the commission implementing its requirements would be a crime, the bill would impose a state-mandated local program by expanding the application of a crime.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
(1)The California Constitution establishes the Public Utilities Commission and authorizes the commission to exercise ratemaking and rulemaking authority over all public utilities, as defined, subject to control by the Legislature. Existing law requires the commission to report various information to the Legislature.
This bill would recast certain of the commissions reporting requirements to an article within the Public Utilities Act pertaining to reports by the commission to the Legislature and make other conforming changes.
(2)Existing law requires the commission to submit to the Legislature by January 1, 1993, and on each January 1 thereafter, a detailed budget for expenditure of railroad corporation fees for the ensuing budget year.
This bill would recast that provision to the article within the Public Utilities Act pertaining to reports by the commission to the Legislature.
(3)Existing law requires the commission or the California State Auditors Office, as specified, to, commencing with the 199394 fiscal year and in each subsequent fiscal year until the 19992000 fiscal year, conduct an audit of the expenditure of specified funds. Existing law requires the results of these audits to be reported, in writing, to the appropriate policy and budget committees of the respective houses of the Legislature.
This bill would repeal those provisions.
(4)Existing law requires the commission, in conjunction with the California Environmental Protection Agency, to request, no later than July 1, 1992, the appropriate federal agencies to take specified actions relating to hazardous substances and materials. Existing law requires the commission to report to the Legislature on the status of its requests no later than September 30, 1992, and every 6 months thereafter until September 30, 1995.
This bill would repeal these provisions.
(5)Existing law requires the commission to, in a single rulemaking or other appropriate proceeding, not to exceed 18 months in duration, consider the need for performance reliability standards for all backup power systems installed on the property of residential and small commercial customers by a facilities-based provider of telephony services. Existing law requires the commission, before January 1, 2008, to prepare and submit to the Legislature a report on the results of the proceeding.
This bill would repeal these provisions.
(6)Existing law requires the commission to, on or before February 1, 2001, issue an order initiating an investigation and opening a proceeding to examine the current and future definitions of universal service. Existing law requires the commission to complete its investigation and report to the Legislature its findings and recommendations on or before January 1, 2002.
This bill would repeal the provision requiring the commission to take those actions on or before January 1, 2002.
(7)Existing law requires the commission to report annually on its efforts to identify ratepayer-funded energy efficiency programs that are similar to programs administered by the State Energy Resources Conservation and Development Commission, the State Air Resources Board, and the California Alternative Energy and Advanced Transportation Financing Authority.
This bill would instead require the commission to, on or before December 31, 2018, and biennially thereafter, as part of a specified report, identify and report to the Legislature on electrical and gas corporation ratepayer-funded energy efficiency programs that are similar to programs administered by those state agencies.
(8)Existing law provides that it is the intent of the Legislature that the commission may authorize specified pilot programs relating to rail crossings prior to January 1, 2003, and requires the commission to report to the Legislature by March 31, 2004, on the outcome of those pilot programs.
This bill would repeal those provisions.
(9)Existing law requires the commission to, on or before March 1, 2000, request from each telephone corporation doing business in this state that possesses one or more telephone number prefixes, or a portion thereof, the specific telephone numbers and the quantities within the possession of the provider, both in use and not in use. Existing law requires the commission to use that information and any other information required by the commission, to prepare and submit to the Legislature, on or before, before July 1, 2001, a study of telecommunications industry use rates.
This bill would repeal those provisions.
(1)The California Constitution establishes the Public Utilities Commission and authorizes the commission to exercise ratemaking and rulemaking authority over all public utilities, as defined, subject to control by the Legislature. Existing law requires the commission to report various information to the Legislature.
This bill would recast certain of the commissions reporting requirements to an article within the Public Utilities Act pertaining to reports by the commission to the Legislature and make other conforming changes.
(2)Existing law requires the commission to submit to the Legislature by January 1, 1993, and on each January 1 thereafter, a detailed budget for expenditure of railroad corporation fees for the ensuing budget year.
This bill would recast that provision to the article within the Public Utilities Act pertaining to reports by the commission to the Legislature.
(3)Existing law requires the commission or the California State Auditors Office, as specified, to, commencing with the 199394 fiscal year and in each subsequent fiscal year until the 19992000 fiscal year, conduct an audit of the expenditure of specified funds. Existing law requires the results of these audits to be reported, in writing, to the appropriate policy and budget committees of the respective houses of the Legislature.
This bill would repeal those provisions.
(4)Existing law requires the commission, in conjunction with the California Environmental Protection Agency, to request, no later than July 1, 1992, the appropriate federal agencies to take specified actions relating to hazardous substances and materials. Existing law requires the commission to report to the Legislature on the status of its requests no later than September 30, 1992, and every 6 months thereafter until September 30, 1995.
This bill would repeal these provisions.
(5)Existing law requires the commission to, in a single rulemaking or other appropriate proceeding, not to exceed 18 months in duration, consider the need for performance reliability standards for all backup power systems installed on the property of residential and small commercial customers by a facilities-based provider of telephony services. Existing law requires the commission, before January 1, 2008, to prepare and submit to the Legislature a report on the results of the proceeding.
This bill would repeal these provisions.
(6)Existing law requires the commission to, on or before February 1, 2001, issue an order initiating an investigation and opening a proceeding to examine the current and future definitions of universal service. Existing law requires the commission to complete its investigation and report to the Legislature its findings and recommendations on or before January 1, 2002.
This bill would repeal the provision requiring the commission to take those actions on or before January 1, 2002.
(7)Existing law requires the commission to report annually on its efforts to identify ratepayer-funded energy efficiency programs that are similar to programs administered by the State Energy Resources Conservation and Development Commission, the State Air Resources Board, and the California Alternative Energy and Advanced Transportation Financing Authority.
This bill would instead require the commission to, on or before December 31, 2018, and biennially thereafter, identify and report to the Legislature on electrical and gas corporation ratepayer-funded energy efficiency programs that are similar to programs administered by those state agencies.
(8)Existing law provides that it is the intent of the Legislature that the commission may authorize specified pilot programs relating to rail crossings prior to January 1, 2003, and requires the commission to report to the Legislature by March 31, 2004, on the outcome of those pilot programs.
This bill would repeal those provisions.
(9)Existing law requires the commission to, on or before March 1, 2000, request from each telephone corporation doing business in this state that possesses one or more telephone number prefixes, or a portion thereof, the specific telephone numbers and the quantities within the possession of the provider, both in use and not in use. Existing law requires the commission to use that information and any other information required by the commission, to prepare and submit to the Legislature, on or before, July 1, 2001, a study of telecommunications industry use rates.
This bill would repeal those provisions.
Under existing law, the Public Utilities Commission has regulatory authority over public utilities, including gas corporations. The Public Utilities Act prohibits any gas corporation from beginning the construction of, among other things, a line, plant, or system, or of any extension thereof, without having first obtained from the commission a certificate that the present or future public convenience and necessity require or will require that construction. Existing law requires, if a new underground gas storage facility is proposed, the commission to ensure that a risk assessment evaluating the potential impact of a leak from the facility on public and environmental health, safety, and welfare is conducted by the project proponent, as specified. Existing law requires that the findings of any risk assessment conducted pursuant to these provisions be subjected to peer review by independent experts and reported to the Legislature, as specifiedThis bill would move the requirement that the report be submitted to the Legislature to a part of the code where commission reports to the Legislature are listed.Under existing law, the Public Utilities Commission has regulatory authority over public utilities, including gas corporations. The Public Utilities Act prohibits any gas corporation from beginning the construction of, among other things, a line, plant, or system, or of any extension thereof, without having first obtained from the commission a certificate that the present or future public convenience and necessity require or will require that construction. Existing law requires, if a new underground gas storage facility is proposed, the commission to ensure that a risk assessment evaluating the potential impact of a leak from the facility on public and environmental health, safety, and welfare is conducted by the project proponent, as specified. Existing law requires that the findings of any risk assessment conducted pursuant to these provisions be subjected to peer review by independent experts and reported to the Legislature, as specified
This bill would move the requirement that the report be submitted to the Legislature to a part of the code where commission reports to the Legislature are listed.
The commission shall require an electrical or gas corporation to revise a ratepayer-funded energy efficiency program identified pursuant to Section 913.9 as necessary to ensure that the program complements and does not duplicate a program administered by a state agency.
SEC. 2.Section 421 of the Public Utilities Code is amended to read:421.(a)The commission shall annually determine a fee to be paid by every passenger stage corporation, charter-party carrier of passengers, pipeline corporation, for-hire vessel operator, common carrier vessel operator, railroad corporation, and commercial air operator, and every other common carrier and related business subject to the jurisdiction of the commission, except as otherwise provided in Article 3 (commencing with Section 431) of this chapter and Chapter 6 (commencing with Section 5001) of Division 2.
(b)The annual fee shall be established to produce a total amount equal to the amount established in the authorized commission budget for the same year, including adjustments appropriated by the Legislature and an appropriate reserve, to regulate common carriers and related businesses, less the amount to be paid from special accounts or funds pursuant to Section 403, reimbursements, federal funds, other revenues, and unencumbered funds from the preceding year.
(c)Notwithstanding any other provision of law, the fees paid by railroad corporations shall be used for state-funded railroad investigation and enforcement activities of the commission, other than the rail safety activities funded by the Transportation Planning and Development Account pursuant to Section 99315. The railroad fees shall be set annually at a level that generates not less than the amount sufficient to fund activities pursuant to Sections 765.5, 916.2, and 7712.
(d)Expenditures of the detailed budget for the expenditure of railroad corporation fees submitted to the Legislature pursuant to Section 916.5 shall be limited to the following items:
(1)Expenditures for employees occupying, and actually performing service in, railroad-safety personnel positions that are directly involved in inspecting railroads and enforcing rail safety regulations. The commission shall expend the funds budgeted pursuant to this subdivision for the salaries, per diem, and travel expenses of employees specified in this paragraph, unless, by statute, the commission is specifically prohibited from expending all or part of those funds.
(2)Expenditures for employees occupying, and actually performing service in, clerical and support staff positions that are directly associated with railroad-safety inspections.
(3)Expenditures for legal personnel who actually pursue violations of rail safety regulations beyond the informal complaint level.
(4)Expenditures for the pro rata share of the commissions overhead costs while state personnel are actually occupying the positions and are performing the duties specified in paragraphs (1) to (3), inclusive.
(e)The Department of Finance shall notify the Joint Legislative Budget Committee, pursuant to Section 28.00 of the annual Budget Act, prior to authorizing any change in the Budget Act appropriation for railroad corporation fees that is larger than one hundred thousand dollars ($100,000), or 10 percent of the amount budgeted, whichever is less.
(f)On or before January 1, 1994, the commission shall hire a minimum of four additional operating practices inspectors, exclusive of supervisory personnel, who are, or shall become by July 1, 1994, federally certified, for the purpose of enforcing compliance by railroads operating in this state with state and federal safety regulations.
(g)The commission, in performing its duties, shall limit the expenditure of funds for rail safety purposes to those railroad corporation fees collected pursuant to subdivision (d). In no event shall the commission fund railroad safety activities utilizing funds from other commission accounts unrelated to railroad safety.
SEC. 3.Section 765.7 of the Public Utilities Code is repealed.SEC. 4.Section 776 of the Public Utilities Code is amended to read:776.(a)The commission shall, upon making the determination pursuant to subdivision (c), develop and implement performance reliability standards for all backup power systems installed on the property of residential and small commercial customers by a facilities-based provider of telephony services. Those standards shall do all the following:
(1)Establish minimum operating life.
(2)Establish minimum periods of time during which a telephone system with a charged backup power system will provide the customer with sufficient electricity for emergency usage.
(3)Establish means to warn a customer when the backup power systems charge is low or when the system can no longer hold a charge.
(b)The commission, in developing and implementing any standards in accordance with subdivision (a), shall consider current best practices and technical feasibility for establishing battery backup requirements.
(c)The commission shall not implement standards in accordance with this section unless it determines that the benefits of the standards exceed the costs.
SEC. 5.Section 883 of the Public Utilities Code is amended to read:883.(a)The commission shall, on or before February 1, 2001, issue an order initiating an investigation and opening a proceeding to examine the current and future definitions of universal service. That proceeding shall include public hearings that encourage participation by a broad and diverse range of interests from all areas of the state, including, but not limited to, all of the following:
(1)Consumer groups.
(2)Communication service providers, including all providers of high-speed access services.
(3)Facilities-based telephone providers.
(4)Information service providers and Internet access providers.
(5)Rural and urban users.
(6)Public interest groups.
(7)Representatives of small and large businesses and industry.
(8)Local agencies.
(9)State agencies, including, but not limited to, all of the following:
(A)The Government Operations Agency.
(B)The State Department of Education.
(C)The State Department of Public Health.
(D)The California State Library.
(10)Colleges and universities.
(b)The objectives of the proceeding set forth in subdivision (a) shall include all of the following:
(1)To investigate the feasibility of redefining universal service in light of current trends toward accelerated convergence of voice, video, and data, with an emphasis on the role of basic telecommunications and Internet services in the workplace, in education and workforce training, access to health care, and increased public safety.
(2)To evaluate the extent to which technological changes have reduced the relevance of existing regulatory regimes given their current segmentation based upon technology.
(3)To receive broad-based input from a cross section of interested parties and make recommendations on whether video, data, and Internet service providers should be incorporated into an enhanced Universal Lifeline Service program, as specified, including relevant policy recommendations regarding regulatory and statutory changes and funding options that are consistent with the principles set forth in subdivision (c) of Section 871.7.
(4)To reevaluate prior definitions of basic service in a manner that will, to the extent feasible, effectively incorporate the latest technologies to provide all California residents with all of the following:
(A)Improved quality of life.
(B)Expanded access to public and private resources for education, training, and commerce.
(C)Increased access to public resources enhancing public health and safety.
(D)Assistance in bridging the digital divide through expanded access to new technologies by low income, disabled, or otherwise disadvantaged Californians.
(5)To assess projected costs of providing enhanced universal lifeline service in accordance with the intent of this article, and to delineate the subsidy support needed to maintain the redefined scope of universal service in a competitive market.
(6)To design and recommend an equitable and broad-based subsidy support mechanism for universal service in competitive markets in a manner that conforms with subdivision (c) of Section 871.7.
(7)To develop a process to periodically review and revise the definition of universal service to reflect new technologies and markets consistent with subdivision (c) of Section 871.7.
(8)To consider whether similar regulatory treatment for the provision of similar services is appropriate and feasible.
(c)In conducting its investigation, the commission shall take into account the role played by a number of diverse but convergent industries and providers, even though many of these entities are not subject to economic regulation by the commission or any other government entity.
(d)The recommendations of the commission shall be consistent with state policies for telecommunications as set forth in Section 709, and with all of the following principles:
(1)Universal service shall, to the extent feasible, be provided at affordable prices regardless of linguistic, cultural, ethnic, physical, financial, and geographic considerations.
(2)Consumers shall be provided access to all information needed to allow timely and informed choices about telecommunications products and services that are part of the universal service program and how best to use them.
(3)Education, health care, community, and government institutions shall be positioned as early recipients of new and emerging technologies so as to maximize the economic and social benefits of these services.
SEC. 6.Section 911.2 is added to the Public Utilities Code, to read:911.2.The commission shall report the findings of any risk assessment required by Section 1103 to the Legislature.
SEC. 7.Section 913.9 of the Public Utilities Code is amended to read:913.9.On or before December 31, 2018, and biennially thereafter, the commission shall, in its annual report prepared pursuant to Section 913, identify and report to the Legislature on electrical and gas corporation ratepayer-funded energy efficiency programs that are similar to programs administered by the Energy Commission, the State Air Resources Board, and the California Alternative Energy and Advanced Transportation Financing Authority, and on those programs revised pursuant to Section 381.4.
SEC. 8.Section 916.5 is added to the Public Utilities Code, to read:916.5.By January 1 of each year, the commission shall submit to the Legislature a detailed budget for the expenditure of railroad corporation fees for the ensuing budget year, consistent with Section 421.
SEC. 9.Section 1103 of the Public Utilities Code is amended to read:1103.(a)If a new underground gas storage facility is proposed, the commission shall ensure that a risk assessment evaluating the potential impact of a leak from the facility on public and environmental health, safety, and welfare is conducted by the project proponent. Both acute and chronic exposures from a range of expected emissions and emission rates shall be evaluated. The evaluation shall include consideration of population density in proximal communities, environmentally sensitive areas, emergency response times, evacuation times, possible leak duration, possible chemical species emitted, and local meteorology.
(b)In evaluating the potential risks and impacts of acute and chronic exposures from emissions from a proposed new gas storage facility, the project proponent shall assess or cause to be assessed risks associated with the proposed facilitys proximity to any living quarters, including private homes, condominiums, apartments, retirement homes, prisons, dormitories, or other housing; education resources, including preschools and schools operating kindergarten or any of grades 1 to 12, inclusive; day care centers; and health care facilities, including hospitals, nursing homes, and long-term care and hospice facilities. Based on the risk analysis, appropriate setbacks to the listed structure types shall be determined by the commission.
(c)The risk assessment conducted pursuant to this section shall be subjected to peer review by independent experts whose demonstrated expertise includes, but is not limited to, the fields of public health, epidemiology, and toxicology.
(d)The findings of any risk assessment required by this section shall be reported pursuant to Section 911.2.
SEC. 10.Section 1202 of the Public Utilities Code is amended to read:1202.The commission has the exclusive power:
(a)To determine and prescribe the manner, including the particular point of crossing, and the terms of installation, operation, maintenance, use, and protection of each crossing of one railroad by another railroad or street railroad, of a street railroad by a railroad, of each crossing of a public or publicly used road or highway by a railroad or street railroad, and of a street by a railroad or of a railroad by a street.
(b)To alter, relocate, or abolish by physical closing any crossing set forth in subdivision (a).
(c)To require, where in its judgment it would be practicable, a separation of grades at any crossing established and to prescribe the terms upon which the separation shall be made and the proportions in which the expense of the construction, alteration, relocation, or abolition of crossings or the separation of grades shall be divided between the railroad or street railroad corporations affected or between these corporations and the state, county, city, or other political subdivision affected.
(d)To authorize on an application-by-application basis and supervise the operation of pilot projects to evaluate proposed crossing warning devices, new technology, or other additional safety measures at designated crossings, with the consent of the local jurisdiction, the affected railroad, and other interested parties, including, but not limited to, represented railroad employees.
SEC. 11.Section 1701.1 of the Public Utilities Code is amended to read:1701.1.(a)The commission shall determine whether each proceeding is a quasi-legislative, an adjudication, or a ratesetting proceeding and, consistent with due process, public policy, and statutory requirements, determine whether the proceeding requires a hearing. The commissions decision as to the nature of the proceeding shall be subject to a request for rehearing within 10 days of the date of that decision or of any subsequent ruling that expands the scope of the proceeding. Only those parties who have requested a rehearing within that time period shall subsequently have standing for judicial review and that review shall only be available at the conclusion of the proceeding. The commission shall render its decision regarding the rehearing within 30 days. The commission shall establish rules regarding ex parte communication on case categorization issues.
(b)(1)The commission, upon initiating an adjudication proceeding or ratesetting proceeding, shall assign one or more commissioners to oversee the case and an administrative law judge when appropriate. The assigned commissioner shall schedule a prehearing conference and shall prepare and issue by order or ruling a scoping memo that describes the issues to be considered and the applicable timetable for resolution.
(2)The administrative law judge shall either preside over and conduct, or assist the assigned commissioner or commissioners in presiding over and conducting, any evidentiary or adjudication hearing that may be required.
(c)The commission, upon initiating a quasi-legislative proceeding, shall assign one or more commissioners to oversee the case and an administrative law judge, when appropriate, who may be assisted by a technical advisory staff member in conducting the proceeding. The assigned commissioner shall prepare and issue by order or ruling a scoping memo that describes the issues to be considered and the applicable timetable for resolution.
(d)(1)Quasi-legislative cases, for purposes of this article, are cases that establish policy, including, but not limited to, rulemakings and investigations that may establish rules affecting an entire industry.
(2)Adjudication cases, for purposes of this article, are enforcement cases and complaints except those challenging the reasonableness of any rates or charges as specified in Section 1702.
(3)Ratesetting cases, for purposes of this article, are cases in which rates are established for a specific company, including, but not limited to, general rate cases, performance-based ratemaking, and other ratesetting mechanisms.
(e)(1)(A)Ex parte communication, for purposes of this article, means any oral or written communication between a decisionmaker and an interested person concerning any matter before the commission that the commission has not specified in its Rules of Practice and Procedure as being a procedural matter and that does not occur in a public hearing, workshop, or other public proceeding, or on the official record of the proceeding on the matter. The commission shall specify in its Rules of Practice and Procedure, enacted by rulemaking, the types of issues considered procedural matters under this article.
(B)Interested person, for purposes of this article, means any of the following:
(i)Any applicant, an agent or an employee of the applicant, or a person receiving consideration for representing the applicant, or a participant in the proceeding on any matter before the commission.
(ii)Any person with a financial interest, as described in Article 1 (commencing with Section 87100) of Chapter 7 of Title 9 of the Government Code, in a matter before the commission, an agent or employee of the person with a financial interest, or a person receiving consideration for representing the person with a financial interest. A person involved in issuing credit ratings or advising entities or persons who invest in the shares or operations of any party to a proceeding is a person with a financial interest.
(iii)A representative acting on behalf of any civic, environmental, neighborhood, business, labor, trade, or similar organization who intends to influence the decision of a commission member on a matter before the commission.
(iv)Other categories of individuals deemed by the commission, by rule, to be an interested person.
(2)The commission shall by rule adopt and publish a definition of decisionmakers and interested persons for purposes of this article, along with any requirements for written reporting of ex parte communications and appropriate sanctions for noncompliance with any rule proscribing ex parte communications. The definition of decisionmakers shall include, but is not limited to: each commissioner; the personal staff of a commissioner if the staff is acting in a policy or legal advisory capacity; the chief administrative law judge of the commission; and the administrative law judge assigned to the proceeding. The commission shall, by rule, explicitly ban both of the following:
(A)The practice of one-way ex parte communications from a decisionmaker to an interested person.
(B)Any communication between an interested person and a decisionmaker regarding which commissioner or administrative law judge may be assigned to a matter before the commission.
(3)For adjudication cases, the rules shall provide that ex parte communications shall be prohibited, as required by this article. The rules shall provide that if an ex parte communication occurs that is prohibited by this article, or if an ex parte communication occurs in a ratesetting case, whether initiated by a decisionmaker or an interested person, all of the following shall be required:
(A)The interested person shall report the communication within three working days of the communication by filing a notice with the commission that includes all the following:
(i)The date, time, and location of the communication, whether the communication was oral or written, or a combination of both, and the communication medium used.
(ii)The identity of the decisionmaker, the identity of the person initiating the communication, and the identities of any other persons present.
(iii)The topic of the communication, including applicable proceeding numbers.
(iv)A substantive description of the interested persons communication and its content.
(v)A copy of any written material or text used during the communication.
(B)Any decisionmaker who participated in the communication shall promptly log the ex parte communication by filing a notice that includes all the following:
(i)The date, time, and location of the communication, whether the communication was oral or written, or a combination of both, and the communication medium used.
(ii)The identity of the interested person, the identity of the person initiating the communication, and the identities of any other persons present.
(iii)The topic of the communication, including any applicable proceeding numbers.
(iv)A brief description of the communication.
(C)If the interested person who participated in the communication has not timely submitted the notice required by subparagraph (A), the decisionmaker shall refer the matter to the attorney for the commission, and an assigned commissioner, by ruling, shall order the interested person to submit the required notice. The interested person shall be subject to any applicable penalties for the initial violation and, if the interested person does not submit the required notice within the time period specified in the assigned commissioners ruling, the interested person shall be subject to continuing violations pursuant to Section 2108.
(4)The requirements of paragraph (3) shall not apply to any oral ex parte communication occurring at a meeting if all parties are invited to participate and given not less than three working days notice.
(5)The commission shall not take any vote on a matter in which a notice of a prohibited ex parte communication has been filed pursuant to subparagraph (A) or (B) of paragraph (3) until all parties to the proceeding have been provided a reasonable opportunity to respond to the communication.
(6)If an ex parte communication is not disclosed as required by this subdivision until after the commission has issued a decision on the matter to which the communication pertained, a party not participating in the communication may file a petition to rescind or modify the decision. The party may seek a finding that the ex parte communication significantly influenced the decisions process or outcome as part of any petition to rescind or modify the decision. The commission shall process the petition in accordance with the commissions procedures for petitions for modification and shall issue a decision on the petition no later than 180 days after the filing of the petition.
(7)(A)Ex parte communications that occur at conferences and that are within the scope of an adjudication or ratesetting proceeding shall be subject to the requirements of this article.
(B)Ex parte communications that occur at conferences and that are within the scope of a quasi-legislative proceeding shall be governed by the ex parte communication disclosure requirements developed by the commission.
(C)For purposes of this section, ex parte communications that occur at conferences includes, but is not limited to, communications in a private setting or during meals, entertainment events, and tours, and informal discussions among conference attendees.
(8)The commission shall render its decisions based on the law and on the evidence in the record. Ex parte communications shall not be a part of the evidentiary record of the proceedings.
(f)The commission may meet in a closed session to discuss administrative matters so long as no collective consensus is reached or vote taken on any matter requiring a vote of the commissioners. The commission shall, by rule, adopt and publish a definition of administrative matters for purposes of this section.
(g)The commission shall permit written comments received from the public to be included in the record of its proceedings, but the comments shall not be treated as evidence. The commission shall provide parties to the proceeding a reasonable opportunity to respond to any public comments included in the record of proceedings.
(h)It is the intent of the Legislature that the commission, and any entity or person seeking to influence actions taken by the commission, shall be subject to all applicable ethical standards, including any applicable obligations under the Political Reform Act of 1974 (Title 9 (commencing with Section 81000) of the Government Code), including, but not limited to, any applicable lobbying obligations.
SEC. 12.Section 1701.3 of the Public Utilities Code is amended to read:1701.3.(a)This section shall apply only to ratesetting cases, except, if the commission pursuant to Section 1701.1 has determined that a ratesetting case does not require a hearing, the procedures prescribed by subdivisions (b), (d), (f), and (i) shall not apply.
(b)The assigned commissioner shall determine prior to the first hearing whether the commissioner or the assigned administrative law judge shall be designated as the principal hearing officer. The principal hearing officer shall be present for more than one-half of the hearing days. The decision of the principal hearing officer shall be the proposed decision.
(c)An alternate decision may be issued by the assigned commissioner or the assigned administrative law judge who is not the principal hearing officer. Any alternate decision may be filed with the commission and served upon all parties to the proceeding any time prior to issuance of a final decision by the commission, consistent with the requirements of Section 311.
(d)The commission shall establish a procedure for any party to request the presence of a commissioner at a hearing. The assigned commissioner shall be present at any closing arguments in the case.
(e)The principal hearing officer shall present the proposed decision to the full commission in a public meeting. The alternate decision, if any, shall also be presented to the full commission at that public meeting.
(f)The presentation to the full commission shall contain a record of the number of days of the hearing, the number of days that each commissioner was present, and whether the decision was completed on time.
(g)The commission shall provide by rule for peremptory challenges and challenges for cause of the administrative law judge. Challenges for cause shall include, but not be limited to, financial interests and prejudice. All parties shall be entitled to unlimited peremptory challenges in any case in which the administrative law judge has within the previous 12 months served in any capacity in an advocacy position at the commission, been employed by a regulated public utility, or has represented a party or has been an interested person in the case.
(h)(1)Ex parte communications in ratesetting cases are subject to the disclosure requirements of this article. The commission, by order or ruling, may prohibit ex parte communications in a ratesetting case.
(2)Oral communications may be permitted by a decisionmaker if all parties are given not less than three working days notice. No individual ex parte meetings shall be held during the three business days before the commissions scheduled vote on the decision.
(3)(A)If an ex parte communication meeting is granted to any party, all other parties, upon request, shall also be granted individual ex parte meetings of a substantially equal period of time and shall be sent a notice of that opportunity at the time the request is granted.
(B)Subparagraph (A) shall not apply if the decisionmaker participating in the ex parte communication meeting is a member of the personal staff of a commissioner acting in a policy or legal advisory capacity and no other decisionmaker to whom subparagraph (A) applies is a participant.
(4)Written ex parte communications by any interested person may be permitted if copies of the communication are transmitted to all parties on the same day as the original communication.
(5)Written and oral ex parte communications shall not be part of the evidentiary record of the proceeding.
(6)After a proposed decision or order is issued, the commission may establish a quiet period during which no oral or written ex parte communications may be permitted and the commission may meet in closed session during that period. That quiet period shall expire at the end of the commission meeting for which the matter was scheduled to be voted upon and shall not in any circumstance exceed 14 days. If the commission holds the decision, it may establish a subsequent quiet period during the second half of the hold period, which is the interval between the hold date and the date that the decision is calendared for final decision. If the subsequent quiet period is established, ex parte communications shall be allowed only during the first half of the hold period. The commission may meet in closed session for the second half of that period. Any meeting of the commission pursuant to this paragraph shall require a minimum of three days advance public notice.
(i)Any party has the right to present a final oral argument of its case before the commission. Those requests shall be scheduled in a timely manner. A quorum of the commission shall be present for the final oral arguments.
(j)The commission may, in issuing its decision, adopt, modify, or set aside the proposed decision or any part of the decision based on evidence in the record. The final decision of the commission shall be issued not later than 60 days after the issuance of the proposed decision. Under extraordinary circumstances the commission may extend this date for a reasonable period. The 60-day period shall be extended for 30 days if any alternate decision is proposed pursuant to Section 311.
SEC. 13.Section 7931 of the Public Utilities Code is amended to read:7931.(a)This chapter is applicable to telephone corporations, including resellers, and to paging companies, hereafter referred to as providers.
(b)For purposes of this chapter, coordinator means the coordinator for California area code relief as designated by the North American Numbering Council.
(c)Whenever the coordinator and providers evaluate the potential boundaries of a new area code, they shall consider rate area boundaries, municipal boundaries, communities of interest, and other appropriate criteria.
(d)When the coordinator determines the need to establish a new area code, at least 30 months prior to the projected opening of the new area code, the coordinator shall provide written notice to the commission regarding the need to establish the new area code.
(e)From the date the written notice required by subdivision (d) is received by the commission all of the following shall be done:
(1)Within three months all providers shall notify all affected customers in writing of the need to establish a new area code. Nothing in this paragraph requires a customer to receive in one bill more than one notice for each billed number.
(2)Within nine months the coordinator and the commission staff shall notify representatives of local jurisdictions and the public in affected geographic areas, and, at the discretion of the commission, may conduct one or more meetings both for representatives of local jurisdictions and for members of the public in affected geographic areas to inform them of the proposed area code relief options and of measures that may be taken to mitigate any potential disruptions, and to afford them the opportunity to discuss the potential impact of the proposed options.
(3)Within 11 months the coordinator shall file the results of the area code relief planning process with the commission requesting commission approval to implement a plan. Anyone may contest the results of the area code planning process by filing a written protest with the commission not later than 60 days after the results have been filed with the commission.
(f)Unless the commission determines otherwise, at least 12 months prior to the date adopted by the commission for opening the new area code, all of the following shall be done:
(1)The coordinator shall notify the general public of the specific geographic area to be included in both the old and new area codes. The notice shall include the schedule for any transitional dialing periods required by Section 7932.
(2)Each telephone provider serving the specific geographic area included in the existing area code shall give written notice to all its affected customers about the specific geographic area that will be included in the new area code. The notice shall include the schedule for any transitional dialing periods required by Section 7932, and the prefixes that will be contained in the new area code. Nothing in this paragraph requires a customer to receive in one bill more than one notice for each billed telephone number.
(g)Within three months prior to the adopted date for opening the new area code, each provider serving the existing area code shall give written notice to its affected customers of the specific geographic boundaries of the new area code. The notice shall include the schedule for any transitional periods required by Section 7932, and the prefixes that will be contained in the new area code. Nothing in this paragraph requires a customer to receive in one bill more than one notice for each billed number.
SEC. 14.Section 7937 of the Public Utilities Code is repealed.SEC. 15.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
The commission shall require an electrical or gas corporation to revise a ratepayer-funded energy efficiency program identified pursuant to Section 913.9 as necessary to ensure that the program complements and does not duplicate a program administered by a state agency.
SEC. 2.Section 421 of the Public Utilities Code is amended to read:421.(a)The commission shall annually determine a fee to be paid by every passenger stage corporation, charter-party carrier of passengers, pipeline corporation, for-hire vessel operator, common carrier vessel operator, railroad corporation, and commercial air operator, and every other common carrier and related business subject to the jurisdiction of the commission, except as otherwise provided in Article 3 (commencing with Section 431) of this chapter and Chapter 6 (commencing with Section 5001) of Division 2.
(b)The annual fee shall be established to produce a total amount equal to the amount established in the authorized commission budget for the same year, including adjustments appropriated by the Legislature and an appropriate reserve, to regulate common carriers and related businesses, less the amount to be paid from special accounts or funds pursuant to Section 403, reimbursements, federal funds, other revenues, and unencumbered funds from the preceding year.
(c)Notwithstanding any other provision of law, the fees paid by railroad corporations shall be used for state-funded railroad investigation and enforcement activities of the commission, other than the rail safety activities funded by the Transportation Planning and Development Account pursuant to Section 99315. The railroad fees shall be set annually at a level that generates not less than the amount sufficient to fund activities pursuant to Sections 765.5, 916.2, and 7712.
(d)Expenditures of the detailed budget for the expenditure of railroad corporation fees submitted to the Legislature pursuant to Section 916.5 shall be limited to the following items:
(1)Expenditures for employees occupying, and actually performing service in, railroad-safety personnel positions that are directly involved in inspecting railroads and enforcing rail safety regulations. The commission shall expend the funds budgeted pursuant to this subdivision for the salaries, per diem, and travel expenses of employees specified in this paragraph, unless, by statute, the commission is specifically prohibited from expending all or part of those funds.
(2)Expenditures for employees occupying, and actually performing service in, clerical and support staff positions that are directly associated with railroad-safety inspections.
(3)Expenditures for legal personnel who actually pursue violations of rail safety regulations beyond the informal complaint level.
(4)Expenditures for the pro rata share of the commissions overhead costs while state personnel are actually occupying the positions and are performing the duties specified in paragraphs (1) to (3), inclusive.
(e)The Department of Finance shall notify the Joint Legislative Budget Committee, pursuant to Section 28.00 of the annual Budget Act, prior to authorizing any change in the Budget Act appropriation for railroad corporation fees that is larger than one hundred thousand dollars ($100,000), or 10 percent of the amount budgeted, whichever is less.
(f)On or before January 1, 1994, the commission shall hire a minimum of four additional operating practices inspectors, exclusive of supervisory personnel, who are, or shall become by July 1, 1994, federally certified, for the purpose of enforcing compliance by railroads operating in this state with state and federal safety regulations.
(g)The commission, in performing its duties, shall limit the expenditure of funds for rail safety purposes to those railroad corporation fees collected pursuant to subdivision (d). In no event shall the commission fund railroad safety activities utilizing funds from other commission accounts unrelated to railroad safety.
SEC. 3.Section 765.7 of the Public Utilities Code is repealed.SEC. 4.Section 776 of the Public Utilities Code is amended to read:776.(a)The commission shall, upon making the determination pursuant to subdivision (c), develop and implement performance reliability standards for all backup power systems installed on the property of residential and small commercial customers by a facilities-based provider of telephony services. Those standards shall do all the following:
(1)Establish minimum operating life.
(2)Establish minimum periods of time during which a telephone system with a charged backup power system will provide the customer with sufficient electricity for emergency usage.
(3)Establish means to warn a customer when the backup power systems charge is low or when the system can no longer hold a charge.
(b)The commission, in developing and implementing any standards in accordance with subdivision (a), shall consider current best practices and technical feasibility for establishing battery backup requirements.
(c)The commission shall not implement standards in accordance with this section unless it determines that the benefits of the standards exceed the costs.
SEC. 5.Section 883 of the Public Utilities Code is amended to read:883.(a)The commission shall, on or before February 1, 2001, issue an order initiating an investigation and opening a proceeding to examine the current and future definitions of universal service. That proceeding shall include public hearings that encourage participation by a broad and diverse range of interests from all areas of the state, including, but not limited to, all of the following:
(1)Consumer groups.
(2)Communication service providers, including all providers of high-speed access services.
(3)Facilities-based telephone providers.
(4)Information service providers and Internet access providers.
(5)Rural and urban users.
(6)Public interest groups.
(7)Representatives of small and large businesses and industry.
(8)Local agencies.
(9)State agencies, including, but not limited to, all of the following:
(A)The Government Operations Agency.
(B)The State Department of Education.
(C)The State Department of Public Health.
(D)The California State Library.
(10)Colleges and universities.
(b)The objectives of the proceeding set forth in subdivision (a) shall include all of the following:
(1)To investigate the feasibility of redefining universal service in light of current trends toward accelerated convergence of voice, video, and data, with an emphasis on the role of basic telecommunications and Internet services in the workplace, in education and workforce training, access to health care, and increased public safety.
(2)To evaluate the extent to which technological changes have reduced the relevance of existing regulatory regimes given their current segmentation based upon technology.
(3)To receive broad-based input from a cross section of interested parties and make recommendations on whether video, data, and Internet service providers should be incorporated into an enhanced Universal Lifeline Service program, as specified, including relevant policy recommendations regarding regulatory and statutory changes and funding options that are consistent with the principles set forth in subdivision (c) of Section 871.7.
(4)To reevaluate prior definitions of basic service in a manner that will, to the extent feasible, effectively incorporate the latest technologies to provide all California residents with all of the following:
(A)Improved quality of life.
(B)Expanded access to public and private resources for education, training, and commerce.
(C)Increased access to public resources enhancing public health and safety.
(D)Assistance in bridging the digital divide through expanded access to new technologies by low income, disabled, or otherwise disadvantaged Californians.
(5)To assess projected costs of providing enhanced universal lifeline service in accordance with the intent of this article, and to delineate the subsidy support needed to maintain the redefined scope of universal service in a competitive market.
(6)To design and recommend an equitable and broad-based subsidy support mechanism for universal service in competitive markets in a manner that conforms with subdivision (c) of Section 871.7.
(7)To develop a process to periodically review and revise the definition of universal service to reflect new technologies and markets consistent with subdivision (c) of Section 871.7.
(8)To consider whether similar regulatory treatment for the provision of similar services is appropriate and feasible.
(c)In conducting its investigation, the commission shall take into account the role played by a number of diverse but convergent industries and providers, even though many of these entities are not subject to economic regulation by the commission or any other government entity.
(d)The recommendations of the commission shall be consistent with state policies for telecommunications as set forth in Section 709, and with all of the following principles:
(1)Universal service shall, to the extent feasible, be provided at affordable prices regardless of linguistic, cultural, ethnic, physical, financial, and geographic considerations.
(2)Consumers shall be provided access to all information needed to allow timely and informed choices about telecommunications products and services that are part of the universal service program and how best to use them.
(3)Education, health care, community, and government institutions shall be positioned as early recipients of new and emerging technologies so as to maximize the economic and social benefits of these services.
SEC. 6.Section 911.2 is added to the Public Utilities Code, to read:911.2.The commission shall report the findings of any risk assessment required by Section 1103 to the Legislature.
SEC. 7.Section 913.9 of the Public Utilities Code is amended to read:913.9.On or before December 31, 2018, and biennially thereafter, the commission shall, in its annual report prepared pursuant to Section 913, identify and report to the Legislature on electrical and gas corporation ratepayer-funded energy efficiency programs that are similar to programs administered by the Energy Commission, the State Air Resources Board, and the California Alternative Energy and Advanced Transportation Financing Authority, and on those programs revised pursuant to Section 381.4.
SEC. 8.Section 916.5 is added to the Public Utilities Code, to read:916.5.By January 1 of each year, the commission shall submit to the Legislature a detailed budget for the expenditure of railroad corporation fees for the ensuing budget year, consistent with Section 421.
SEC. 9.Section 1103 of the Public Utilities Code is amended to read:1103.(a)If a new underground gas storage facility is proposed, the commission shall ensure that a risk assessment evaluating the potential impact of a leak from the facility on public and environmental health, safety, and welfare is conducted by the project proponent. Both acute and chronic exposures from a range of expected emissions and emission rates shall be evaluated. The evaluation shall include consideration of population density in proximal communities, environmentally sensitive areas, emergency response times, evacuation times, possible leak duration, possible chemical species emitted, and local meteorology.
(b)In evaluating the potential risks and impacts of acute and chronic exposures from emissions from a proposed new gas storage facility, the project proponent shall assess or cause to be assessed risks associated with the proposed facilitys proximity to any living quarters, including private homes, condominiums, apartments, retirement homes, prisons, dormitories, or other housing; education resources, including preschools and schools operating kindergarten or any of grades 1 to 12, inclusive; day care centers; and health care facilities, including hospitals, nursing homes, and long-term care and hospice facilities. Based on the risk analysis, appropriate setbacks to the listed structure types shall be determined by the commission.
(c)The risk assessment conducted pursuant to this section shall be subjected to peer review by independent experts whose demonstrated expertise includes, but is not limited to, the fields of public health, epidemiology, and toxicology.
(d)The findings of any risk assessment required by this section shall be reported pursuant to Section 911.2.
SEC. 10.Section 1202 of the Public Utilities Code is amended to read:1202.The commission has the exclusive power:
(a)To determine and prescribe the manner, including the particular point of crossing, and the terms of installation, operation, maintenance, use, and protection of each crossing of one railroad by another railroad or street railroad, of a street railroad by a railroad, of each crossing of a public or publicly used road or highway by a railroad or street railroad, and of a street by a railroad or of a railroad by a street.
(b)To alter, relocate, or abolish by physical closing any crossing set forth in subdivision (a).
(c)To require, where in its judgment it would be practicable, a separation of grades at any crossing established and to prescribe the terms upon which the separation shall be made and the proportions in which the expense of the construction, alteration, relocation, or abolition of crossings or the separation of grades shall be divided between the railroad or street railroad corporations affected or between these corporations and the state, county, city, or other political subdivision affected.
(d)To authorize on an application-by-application basis and supervise the operation of pilot projects to evaluate proposed crossing warning devices, new technology, or other additional safety measures at designated crossings, with the consent of the local jurisdiction, the affected railroad, and other interested parties, including, but not limited to, represented railroad employees.
SEC. 11.Section 1701.1 of the Public Utilities Code is amended to read:1701.1.(a)The commission shall determine whether each proceeding is a quasi-legislative, an adjudication, or a ratesetting proceeding and, consistent with due process, public policy, and statutory requirements, determine whether the proceeding requires a hearing. The commissions decision as to the nature of the proceeding shall be subject to a request for rehearing within 10 days of the date of that decision or of any subsequent ruling that expands the scope of the proceeding. Only those parties who have requested a rehearing within that time period shall subsequently have standing for judicial review and that review shall only be available at the conclusion of the proceeding. The commission shall render its decision regarding the rehearing within 30 days. The commission shall establish rules regarding ex parte communication on case categorization issues.
(b)(1)The commission, upon initiating an adjudication proceeding or ratesetting proceeding, shall assign one or more commissioners to oversee the case and an administrative law judge when appropriate. The assigned commissioner shall schedule a prehearing conference and shall prepare and issue by order or ruling a scoping memo that describes the issues to be considered and the applicable timetable for resolution.
(2)The administrative law judge shall either preside over and conduct, or assist the assigned commissioner or commissioners in presiding over and conducting, any evidentiary or adjudication hearing that may be required.
(c)The commission, upon initiating a quasi-legislative proceeding, shall assign one or more commissioners to oversee the case and an administrative law judge, when appropriate, who may be assisted by a technical advisory staff member in conducting the proceeding. The assigned commissioner shall prepare and issue by order or ruling a scoping memo that describes the issues to be considered and the applicable timetable for resolution.
(d)(1)Quasi-legislative cases, for purposes of this article, are cases that establish policy, including, but not limited to, rulemakings and investigations that may establish rules affecting an entire industry.
(2)Adjudication cases, for purposes of this article, are enforcement cases and complaints except those challenging the reasonableness of any rates or charges as specified in Section 1702.
(3)Ratesetting cases, for purposes of this article, are cases in which rates are established for a specific company, including, but not limited to, general rate cases, performance-based ratemaking, and other ratesetting mechanisms.
(e)(1)(A)Ex parte communication, for purposes of this article, means any oral or written communication between a decisionmaker and an interested person concerning any matter before the commission that the commission has not specified in its Rules of Practice and Procedure as being a procedural matter and that does not occur in a public hearing, workshop, or other public proceeding, or on the official record of the proceeding on the matter. The commission shall specify in its Rules of Practice and Procedure, enacted by rulemaking, the types of issues considered procedural matters under this article.
(B)Interested person, for purposes of this article, means any of the following:
(i)Any applicant, an agent or an employee of the applicant, or a person receiving consideration for representing the applicant, or a participant in the proceeding on any matter before the commission.
(ii)Any person with a financial interest, as described in Article 1 (commencing with Section 87100) of Chapter 7 of Title 9 of the Government Code, in a matter before the commission, an agent or employee of the person with a financial interest, or a person receiving consideration for representing the person with a financial interest. A person involved in issuing credit ratings or advising entities or persons who invest in the shares or operations of any party to a proceeding is a person with a financial interest.
(iii)A representative acting on behalf of any civic, environmental, neighborhood, business, labor, trade, or similar organization who intends to influence the decision of a commission member on a matter before the commission.
(iv)Other categories of individuals deemed by the commission, by rule, to be an interested person.
(2)The commission shall by rule adopt and publish a definition of decisionmakers and interested persons for purposes of this article, along with any requirements for written reporting of ex parte communications and appropriate sanctions for noncompliance with any rule proscribing ex parte communications. The definition of decisionmakers shall include, but is not limited to: each commissioner; the personal staff of a commissioner if the staff is acting in a policy or legal advisory capacity; the chief administrative law judge of the commission; and the administrative law judge assigned to the proceeding. The commission shall, by rule, explicitly ban both of the following:
(A)The practice of one-way ex parte communications from a decisionmaker to an interested person.
(B)Any communication between an interested person and a decisionmaker regarding which commissioner or administrative law judge may be assigned to a matter before the commission.
(3)For adjudication cases, the rules shall provide that ex parte communications shall be prohibited, as required by this article. The rules shall provide that if an ex parte communication occurs that is prohibited by this article, or if an ex parte communication occurs in a ratesetting case, whether initiated by a decisionmaker or an interested person, all of the following shall be required:
(A)The interested person shall report the communication within three working days of the communication by filing a notice with the commission that includes all the following:
(i)The date, time, and location of the communication, whether the communication was oral or written, or a combination of both, and the communication medium used.
(ii)The identity of the decisionmaker, the identity of the person initiating the communication, and the identities of any other persons present.
(iii)The topic of the communication, including applicable proceeding numbers.
(iv)A substantive description of the interested persons communication and its content.
(v)A copy of any written material or text used during the communication.
(B)Any decisionmaker who participated in the communication shall promptly log the ex parte communication by filing a notice that includes all the following:
(i)The date, time, and location of the communication, whether the communication was oral or written, or a combination of both, and the communication medium used.
(ii)The identity of the interested person, the identity of the person initiating the communication, and the identities of any other persons present.
(iii)The topic of the communication, including any applicable proceeding numbers.
(iv)A brief description of the communication.
(C)If the interested person who participated in the communication has not timely submitted the notice required by subparagraph (A), the decisionmaker shall refer the matter to the attorney for the commission, and an assigned commissioner, by ruling, shall order the interested person to submit the required notice. The interested person shall be subject to any applicable penalties for the initial violation and, if the interested person does not submit the required notice within the time period specified in the assigned commissioners ruling, the interested person shall be subject to continuing violations pursuant to Section 2108.
(4)The requirements of paragraph (3) shall not apply to any oral ex parte communication occurring at a meeting if all parties are invited to participate and given not less than three working days notice.
(5)The commission shall not take any vote on a matter in which a notice of a prohibited ex parte communication has been filed pursuant to subparagraph (A) or (B) of paragraph (3) until all parties to the proceeding have been provided a reasonable opportunity to respond to the communication.
(6)If an ex parte communication is not disclosed as required by this subdivision until after the commission has issued a decision on the matter to which the communication pertained, a party not participating in the communication may file a petition to rescind or modify the decision. The party may seek a finding that the ex parte communication significantly influenced the decisions process or outcome as part of any petition to rescind or modify the decision. The commission shall process the petition in accordance with the commissions procedures for petitions for modification and shall issue a decision on the petition no later than 180 days after the filing of the petition.
(7)(A)Ex parte communications that occur at conferences and that are within the scope of an adjudication or ratesetting proceeding shall be subject to the requirements of this article.
(B)Ex parte communications that occur at conferences and that are within the scope of a quasi-legislative proceeding shall be governed by the ex parte communication disclosure requirements developed by the commission.
(C)For purposes of this section, ex parte communications that occur at conferences includes, but is not limited to, communications in a private setting or during meals, entertainment events, and tours, and informal discussions among conference attendees.
(8)The commission shall render its decisions based on the law and on the evidence in the record. Ex parte communications shall not be a part of the evidentiary record of the proceedings.
(f)The commission may meet in a closed session to discuss administrative matters so long as no collective consensus is reached or vote taken on any matter requiring a vote of the commissioners. The commission shall, by rule, adopt and publish a definition of administrative matters for purposes of this section.
(g)The commission shall permit written comments received from the public to be included in the record of its proceedings, but the comments shall not be treated as evidence. The commission shall provide parties to the proceeding a reasonable opportunity to respond to any public comments included in the record of proceedings.
(h)It is the intent of the Legislature that the commission, and any entity or person seeking to influence actions taken by the commission, shall be subject to all applicable ethical standards, including any applicable obligations under the Political Reform Act of 1974 (Title 9 (commencing with Section 81000) of the Government Code), including, but not limited to, any applicable lobbying obligations.
SEC. 12.Section 1701.3 of the Public Utilities Code is amended to read:1701.3.(a)This section shall apply only to ratesetting cases, except, if the commission pursuant to Section 1701.1 has determined that a ratesetting case does not require a hearing, the procedures prescribed by subdivisions (b), (d), (f), and (i) shall not apply.
(b)The assigned commissioner shall determine prior to the first hearing whether the commissioner or the assigned administrative law judge shall be designated as the principal hearing officer. The principal hearing officer shall be present for more than one-half of the hearing days. The decision of the principal hearing officer shall be the proposed decision.
(c)An alternate decision may be issued by the assigned commissioner or the assigned administrative law judge who is not the principal hearing officer. Any alternate decision may be filed with the commission and served upon all parties to the proceeding any time prior to issuance of a final decision by the commission, consistent with the requirements of Section 311.
(d)The commission shall establish a procedure for any party to request the presence of a commissioner at a hearing. The assigned commissioner shall be present at any closing arguments in the case.
(e)The principal hearing officer shall present the proposed decision to the full commission in a public meeting. The alternate decision, if any, shall also be presented to the full commission at that public meeting.
(f)The presentation to the full commission shall contain a record of the number of days of the hearing, the number of days that each commissioner was present, and whether the decision was completed on time.
(g)The commission shall provide by rule for peremptory challenges and challenges for cause of the administrative law judge. Challenges for cause shall include, but not be limited to, financial interests and prejudice. All parties shall be entitled to unlimited peremptory challenges in any case in which the administrative law judge has within the previous 12 months served in any capacity in an advocacy position at the commission, been employed by a regulated public utility, or has represented a party or has been an interested person in the case.
(h)(1)Ex parte communications in ratesetting cases are subject to the disclosure requirements of this article. The commission, by order or ruling, may prohibit ex parte communications in a ratesetting case.
(2)Oral communications may be permitted by a decisionmaker if all parties are given not less than three working days notice. No individual ex parte meetings shall be held during the three business days before the commissions scheduled vote on the decision.
(3)(A)If an ex parte communication meeting is granted to any party, all other parties, upon request, shall also be granted individual ex parte meetings of a substantially equal period of time and shall be sent a notice of that opportunity at the time the request is granted.
(B)Subparagraph (A) shall not apply if the decisionmaker participating in the ex parte communication meeting is a member of the personal staff of a commissioner acting in a policy or legal advisory capacity and no other decisionmaker to whom subparagraph (A) applies is a participant.
(4)Written ex parte communications by any interested person may be permitted if copies of the communication are transmitted to all parties on the same day as the original communication.
(5)Written and oral ex parte communications shall not be part of the evidentiary record of the proceeding.
(6)After a proposed decision or order is issued, the commission may establish a quiet period during which no oral or written ex parte communications may be permitted and the commission may meet in closed session during that period. That quiet period shall expire at the end of the commission meeting for which the matter was scheduled to be voted upon and shall not in any circumstance exceed 14 days. If the commission holds the decision, it may establish a subsequent quiet period during the second half of the hold period, which is the interval between the hold date and the date that the decision is calendared for final decision. If the subsequent quiet period is established, ex parte communications shall be allowed only during the first half of the hold period. The commission may meet in closed session for the second half of that period. Any meeting of the commission pursuant to this paragraph shall require a minimum of three days advance public notice.
(i)Any party has the right to present a final oral argument of its case before the commission. Those requests shall be scheduled in a timely manner. A quorum of the commission shall be present for the final oral arguments.
(j)The commission may, in issuing its decision, adopt, modify, or set aside the proposed decision or any part of the decision based on evidence in the record. The final decision of the commission shall be issued not later than 60 days after the issuance of the proposed decision. Under extraordinary circumstances the commission may extend this date for a reasonable period. The 60-day period shall be extended for 30 days if any alternate decision is proposed pursuant to Section 311.
SEC. 13.Section 7931 of the Public Utilities Code is amended to read:7931.(a)This chapter is applicable to telephone corporations, including resellers, and to paging companies, hereafter referred to as providers.
(b)For purposes of this chapter, coordinator means the coordinator for California area code relief as designated by the North American Numbering Council.
(c)Whenever the coordinator and providers evaluate the potential boundaries of a new area code, they shall consider rate area boundaries, municipal boundaries, communities of interest, and other appropriate criteria.
(d)When the coordinator determines the need to establish a new area code, at least 30 months prior to the projected opening of the new area code, the coordinator shall provide written notice to the commission regarding the need to establish the new area code.
(e)From the date the written notice required by subdivision (d) is received by the commission all of the following shall be done:
(1)Within three months all providers shall notify all affected customers in writing of the need to establish a new area code. Nothing in this paragraph requires a customer to receive in one bill more than one notice for each billed number.
(2)Within nine months the coordinator and the commission staff shall notify representatives of local jurisdictions and the public in affected geographic areas, and, at the discretion of the commission, may conduct one or more meetings both for representatives of local jurisdictions and for members of the public in affected geographic areas to inform them of the proposed area code relief options and of measures that may be taken to mitigate any potential disruptions, and to afford them the opportunity to discuss the potential impact of the proposed options.
(3)Within 11 months the coordinator shall file the results of the area code relief planning process with the commission requesting commission approval to implement a plan. Anyone may contest the results of the area code planning process by filing a written protest with the commission not later than 60 days after the results have been filed with the commission.
(f)Unless the commission determines otherwise, at least 12 months prior to the date adopted by the commission for opening the new area code, all of the following shall be done:
(1)The coordinator shall notify the general public of the specific geographic area to be included in both the old and new area codes. The notice shall include the schedule for any transitional dialing periods required by Section 7932.
(2)Each telephone provider serving the specific geographic area included in the existing area code shall give written notice to all its affected customers about the specific geographic area that will be included in the new area code. The notice shall include the schedule for any transitional dialing periods required by Section 7932, and the prefixes that will be contained in the new area code. Nothing in this paragraph requires a customer to receive in one bill more than one notice for each billed telephone number.
(g)Within three months prior to the adopted date for opening the new area code, each provider serving the existing area code shall give written notice to its affected customers of the specific geographic boundaries of the new area code. The notice shall include the schedule for any transitional periods required by Section 7932, and the prefixes that will be contained in the new area code. Nothing in this paragraph requires a customer to receive in one bill more than one notice for each billed number.
SEC. 14.Section 7937 of the Public Utilities Code is repealed.SEC. 15.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
The commission shall require an electrical or gas corporation to revise a ratepayer-funded energy efficiency program identified pursuant to Section 913.9 as necessary to ensure that the program complements and does not duplicate a program administered by a state agency.
SEC. 2.Section 421 of the Public Utilities Code is amended to read:421.(a)The commission shall annually determine a fee to be paid by every passenger stage corporation, charter-party carrier of passengers, pipeline corporation, for-hire vessel operator, common carrier vessel operator, railroad corporation, and commercial air operator, and every other common carrier and related business subject to the jurisdiction of the commission, except as otherwise provided in Article 3 (commencing with Section 431) of this chapter and Chapter 6 (commencing with Section 5001) of Division 2.
(b)The annual fee shall be established to produce a total amount equal to the amount established in the authorized commission budget for the same year, including adjustments appropriated by the Legislature and an appropriate reserve, to regulate common carriers and related businesses, less the amount to be paid from special accounts or funds pursuant to Section 403, reimbursements, federal funds, other revenues, and unencumbered funds from the preceding year.
(c)Notwithstanding any other provision of law, the fees paid by railroad corporations shall be used for state-funded railroad investigation and enforcement activities of the commission, other than the rail safety activities funded by the Transportation Planning and Development Account pursuant to Section 99315. The railroad fees shall be set annually at a level that generates not less than the amount sufficient to fund activities pursuant to Sections 765.5, 916.2, and 7712.
(d)Expenditures of the detailed budget for the expenditure of railroad corporation fees submitted to the Legislature pursuant to Section 916.5 shall be limited to the following items:
(1)Expenditures for employees occupying, and actually performing service in, railroad-safety personnel positions that are directly involved in inspecting railroads and enforcing rail safety regulations. The commission shall expend the funds budgeted pursuant to this subdivision for the salaries, per diem, and travel expenses of employees specified in this paragraph, unless, by statute, the commission is specifically prohibited from expending all or part of those funds.
(2)Expenditures for employees occupying, and actually performing service in, clerical and support staff positions that are directly associated with railroad-safety inspections.
(3)Expenditures for legal personnel who actually pursue violations of rail safety regulations beyond the informal complaint level.
(4)Expenditures for the pro rata share of the commissions overhead costs while state personnel are actually occupying the positions and are performing the duties specified in paragraphs (1) to (3), inclusive.
(e)The Department of Finance shall notify the Joint Legislative Budget Committee, pursuant to Section 28.00 of the annual Budget Act, prior to authorizing any change in the Budget Act appropriation for railroad corporation fees that is larger than one hundred thousand dollars ($100,000), or 10 percent of the amount budgeted, whichever is less.
(f)On or before January 1, 1994, the commission shall hire a minimum of four additional operating practices inspectors, exclusive of supervisory personnel, who are, or shall become by July 1, 1994, federally certified, for the purpose of enforcing compliance by railroads operating in this state with state and federal safety regulations.
(g)The commission, in performing its duties, shall limit the expenditure of funds for rail safety purposes to those railroad corporation fees collected pursuant to subdivision (d). In no event shall the commission fund railroad safety activities utilizing funds from other commission accounts unrelated to railroad safety.
SEC. 3.Section 765.7 of the Public Utilities Code is repealed.SEC. 4.Section 776 of the Public Utilities Code is amended to read:776.(a)The commission shall, upon making the determination pursuant to subdivision (c), develop and implement performance reliability standards for all backup power systems installed on the property of residential and small commercial customers by a facilities-based provider of telephony services. Those standards shall do all the following:
(1)Establish minimum operating life.
(2)Establish minimum periods of time during which a telephone system with a charged backup power system will provide the customer with sufficient electricity for emergency usage.
(3)Establish means to warn a customer when the backup power systems charge is low or when the system can no longer hold a charge.
(b)The commission, in developing and implementing any standards in accordance with subdivision (a), shall consider current best practices and technical feasibility for establishing battery backup requirements.
(c)The commission shall not implement standards in accordance with this section unless it determines that the benefits of the standards exceed the costs.
SEC. 5.Section 883 of the Public Utilities Code is amended to read:883.(a)The commission shall, on or before February 1, 2001, issue an order initiating an investigation and opening a proceeding to examine the current and future definitions of universal service. That proceeding shall include public hearings that encourage participation by a broad and diverse range of interests from all areas of the state, including, but not limited to, all of the following:
(1)Consumer groups.
(2)Communication service providers, including all providers of high-speed access services.
(3)Facilities-based telephone providers.
(4)Information service providers and Internet access providers.
(5)Rural and urban users.
(6)Public interest groups.
(7)Representatives of small and large businesses and industry.
(8)Local agencies.
(9)State agencies, including, but not limited to, all of the following:
(A)The Government Operations Agency.
(B)The State Department of Education.
(C)The State Department of Public Health.
(D)The California State Library.
(10)Colleges and universities.
(b)The objectives of the proceeding set forth in subdivision (a) shall include all of the following:
(1)To investigate the feasibility of redefining universal service in light of current trends toward accelerated convergence of voice, video, and data, with an emphasis on the role of basic telecommunications and Internet services in the workplace, in education and workforce training, access to health care, and increased public safety.
(2)To evaluate the extent to which technological changes have reduced the relevance of existing regulatory regimes given their current segmentation based upon technology.
(3)To receive broad-based input from a cross section of interested parties and make recommendations on whether video, data, and Internet service providers should be incorporated into an enhanced Universal Lifeline Service program, as specified, including relevant policy recommendations regarding regulatory and statutory changes and funding options that are consistent with the principles set forth in subdivision (c) of Section 871.7.
(4)To reevaluate prior definitions of basic service in a manner that will, to the extent feasible, effectively incorporate the latest technologies to provide all California residents with all of the following:
(A)Improved quality of life.
(B)Expanded access to public and private resources for education, training, and commerce.
(C)Increased access to public resources enhancing public health and safety.
(D)Assistance in bridging the digital divide through expanded access to new technologies by low income, disabled, or otherwise disadvantaged Californians.
(5)To assess projected costs of providing enhanced universal lifeline service in accordance with the intent of this article, and to delineate the subsidy support needed to maintain the redefined scope of universal service in a competitive market.
(6)To design and recommend an equitable and broad-based subsidy support mechanism for universal service in competitive markets in a manner that conforms with subdivision (c) of Section 871.7.
(7)To develop a process to periodically review and revise the definition of universal service to reflect new technologies and markets consistent with subdivision (c) of Section 871.7.
(8)To consider whether similar regulatory treatment for the provision of similar services is appropriate and feasible.
(c)In conducting its investigation, the commission shall take into account the role played by a number of diverse but convergent industries and providers, even though many of these entities are not subject to economic regulation by the commission or any other government entity.
(d)The recommendations of the commission shall be consistent with state policies for telecommunications as set forth in Section 709, and with all of the following principles:
(1)Universal service shall, to the extent feasible, be provided at affordable prices regardless of linguistic, cultural, ethnic, physical, financial, and geographic considerations.
(2)Consumers shall be provided access to all information needed to allow timely and informed choices about telecommunications products and services that are part of the universal service program and how best to use them.
(3)Education, health care, community, and government institutions shall be positioned as early recipients of new and emerging technologies so as to maximize the economic and social benefits of these services.
SEC. 6.Section 911.2 is added to the Public Utilities Code, to read:911.2.The commission shall report the findings of any risk assessment required by Section 1103 to the Legislature.
SEC. 7.Section 913.9 of the Public Utilities Code is amended to read:913.9.On or before December 31, 2018, and biennially thereafter, the commission shall, in its annual report prepared pursuant to Section 913, identify and report to the Legislature on electrical and gas corporation ratepayer-funded energy efficiency programs that are similar to programs administered by the Energy Commission, the State Air Resources Board, and the California Alternative Energy and Advanced Transportation Financing Authority, and on those programs revised pursuant to Section 381.4.
SEC. 8.Section 916.5 is added to the Public Utilities Code, to read:916.5.By January 1 of each year, the commission shall submit to the Legislature a detailed budget for the expenditure of railroad corporation fees for the ensuing budget year, consistent with Section 421.
SEC. 9.Section 1103 of the Public Utilities Code is amended to read:1103.(a)If a new underground gas storage facility is proposed, the commission shall ensure that a risk assessment evaluating the potential impact of a leak from the facility on public and environmental health, safety, and welfare is conducted by the project proponent. Both acute and chronic exposures from a range of expected emissions and emission rates shall be evaluated. The evaluation shall include consideration of population density in proximal communities, environmentally sensitive areas, emergency response times, evacuation times, possible leak duration, possible chemical species emitted, and local meteorology.
(b)In evaluating the potential risks and impacts of acute and chronic exposures from emissions from a proposed new gas storage facility, the project proponent shall assess or cause to be assessed risks associated with the proposed facilitys proximity to any living quarters, including private homes, condominiums, apartments, retirement homes, prisons, dormitories, or other housing; education resources, including preschools and schools operating kindergarten or any of grades 1 to 12, inclusive; day care centers; and health care facilities, including hospitals, nursing homes, and long-term care and hospice facilities. Based on the risk analysis, appropriate setbacks to the listed structure types shall be determined by the commission.
(c)The risk assessment conducted pursuant to this section shall be subjected to peer review by independent experts whose demonstrated expertise includes, but is not limited to, the fields of public health, epidemiology, and toxicology.
(d)The findings of any risk assessment required by this section shall be reported pursuant to Section 911.2.
SEC. 10.Section 1202 of the Public Utilities Code is amended to read:1202.The commission has the exclusive power:
(a)To determine and prescribe the manner, including the particular point of crossing, and the terms of installation, operation, maintenance, use, and protection of each crossing of one railroad by another railroad or street railroad, of a street railroad by a railroad, of each crossing of a public or publicly used road or highway by a railroad or street railroad, and of a street by a railroad or of a railroad by a street.
(b)To alter, relocate, or abolish by physical closing any crossing set forth in subdivision (a).
(c)To require, where in its judgment it would be practicable, a separation of grades at any crossing established and to prescribe the terms upon which the separation shall be made and the proportions in which the expense of the construction, alteration, relocation, or abolition of crossings or the separation of grades shall be divided between the railroad or street railroad corporations affected or between these corporations and the state, county, city, or other political subdivision affected.
(d)To authorize on an application-by-application basis and supervise the operation of pilot projects to evaluate proposed crossing warning devices, new technology, or other additional safety measures at designated crossings, with the consent of the local jurisdiction, the affected railroad, and other interested parties, including, but not limited to, represented railroad employees.
SEC. 11.Section 1701.1 of the Public Utilities Code is amended to read:1701.1.(a)The commission shall determine whether each proceeding is a quasi-legislative, an adjudication, or a ratesetting proceeding and, consistent with due process, public policy, and statutory requirements, determine whether the proceeding requires a hearing. The commissions decision as to the nature of the proceeding shall be subject to a request for rehearing within 10 days of the date of that decision or of any subsequent ruling that expands the scope of the proceeding. Only those parties who have requested a rehearing within that time period shall subsequently have standing for judicial review and that review shall only be available at the conclusion of the proceeding. The commission shall render its decision regarding the rehearing within 30 days. The commission shall establish rules regarding ex parte communication on case categorization issues.
(b)(1)The commission, upon initiating an adjudication proceeding or ratesetting proceeding, shall assign one or more commissioners to oversee the case and an administrative law judge when appropriate. The assigned commissioner shall schedule a prehearing conference and shall prepare and issue by order or ruling a scoping memo that describes the issues to be considered and the applicable timetable for resolution.
(2)The administrative law judge shall either preside over and conduct, or assist the assigned commissioner or commissioners in presiding over and conducting, any evidentiary or adjudication hearing that may be required.
(c)The commission, upon initiating a quasi-legislative proceeding, shall assign one or more commissioners to oversee the case and an administrative law judge, when appropriate, who may be assisted by a technical advisory staff member in conducting the proceeding. The assigned commissioner shall prepare and issue by order or ruling a scoping memo that describes the issues to be considered and the applicable timetable for resolution.
(d)(1)Quasi-legislative cases, for purposes of this article, are cases that establish policy, including, but not limited to, rulemakings and investigations that may establish rules affecting an entire industry.
(2)Adjudication cases, for purposes of this article, are enforcement cases and complaints except those challenging the reasonableness of any rates or charges as specified in Section 1702.
(3)Ratesetting cases, for purposes of this article, are cases in which rates are established for a specific company, including, but not limited to, general rate cases, performance-based ratemaking, and other ratesetting mechanisms.
(e)(1)(A)Ex parte communication, for purposes of this article, means any oral or written communication between a decisionmaker and an interested person concerning any matter before the commission that the commission has not specified in its Rules of Practice and Procedure as being a procedural matter and that does not occur in a public hearing, workshop, or other public proceeding, or on the official record of the proceeding on the matter. The commission shall specify in its Rules of Practice and Procedure, enacted by rulemaking, the types of issues considered procedural matters under this article.
(B)Interested person, for purposes of this article, means any of the following:
(i)Any applicant, an agent or an employee of the applicant, or a person receiving consideration for representing the applicant, or a participant in the proceeding on any matter before the commission.
(ii)Any person with a financial interest, as described in Article 1 (commencing with Section 87100) of Chapter 7 of Title 9 of the Government Code, in a matter before the commission, an agent or employee of the person with a financial interest, or a person receiving consideration for representing the person with a financial interest. A person involved in issuing credit ratings or advising entities or persons who invest in the shares or operations of any party to a proceeding is a person with a financial interest.
(iii)A representative acting on behalf of any civic, environmental, neighborhood, business, labor, trade, or similar organization who intends to influence the decision of a commission member on a matter before the commission.
(iv)Other categories of individuals deemed by the commission, by rule, to be an interested person.
(2)The commission shall by rule adopt and publish a definition of decisionmakers and interested persons for purposes of this article, along with any requirements for written reporting of ex parte communications and appropriate sanctions for noncompliance with any rule proscribing ex parte communications. The definition of decisionmakers shall include, but is not limited to: each commissioner; the personal staff of a commissioner if the staff is acting in a policy or legal advisory capacity; the chief administrative law judge of the commission; and the administrative law judge assigned to the proceeding. The commission shall, by rule, explicitly ban both of the following:
(A)The practice of one-way ex parte communications from a decisionmaker to an interested person. A communication made during the open session of a conference or other public meeting is not a one-way communication.
(B)Any communication between an interested person and a decisionmaker regarding which commissioner or administrative law judge may be assigned to a matter before the commission.
(3)For adjudication cases, the rules shall provide that ex parte communications shall be prohibited, as required by this article. The rules shall provide that if an ex parte communication occurs that is prohibited by this article, or if an ex parte communication occurs in a ratesetting case, whether initiated by a decisionmaker or an interested person, all of the following shall be required:
(A)The interested person shall report the communication within three working days of the communication by filing a notice with the commission that includes all the following:
(i)The date, time, and location of the communication, whether the communication was oral or written, or a combination of both, and the communication medium used.
(ii)The identity of the decisionmaker, the identity of the person initiating the communication, and the identities of any other persons present.
(iii)The topic of the communication, including applicable proceeding numbers.
(iv)A substantive description of the interested persons communication and its content.
(v)A copy of any written material or text used during the communication.
(B)Any decisionmaker who participated in the communication shall promptly provide notice of log the ex parte communication in a public log and ensure that any parties on the service list of any relevant proceeding are notified of that notice. Notification to the parties on the service list shall additionally be provided in the docket of any relevant proceeding. The notice in the public log shall include by filing a notice that includes all the following:
(i)The date, time, and location of the communication, whether the communication was oral or written, or a combination of both, and the communication medium used.
(ii)The identity of the interested person, the identity of the person initiating the communication, and the identities of any other persons present.
(iii)The topic of the communication, including any applicable proceeding numbers.
(iv)A brief description of the communication.
(C)If the interested person who participated in the communication has not timely submitted the notice required by subparagraph (A), the decisionmaker shall refer the matter to the attorney for the commission, and an assigned commissioner, by ruling, shall order the interested person to submit the required notice. The interested person shall be subject to any applicable penalties for the initial violation and, if the interested person does not submit the required notice within the time period specified in the assigned commissioners ruling, the interested person shall be subject to continuing violations pursuant to Section 2108.
(4)The requirements of paragraph (3) shall not apply to any oral ex parte communication occurring at a meeting if all parties are invited to participate and given not less than three working days notice.
(5)The commission shall not take any vote on a matter in which a notice of a prohibited ex parte communication has been filed pursuant to subparagraph (A) or (B) of paragraph (3) until all parties to the proceeding have been provided a reasonable opportunity to respond to the communication.
(6)If an ex parte communication is not disclosed as required by this subdivision until after the commission has issued a decision on the matter to which the communication pertained, a party not participating in the communication may file a petition to rescind or modify the decision. The party may seek a finding that the ex parte communication significantly influenced the decisions process or outcome as part of any petition to rescind or modify the decision. The commission shall process the petition in accordance with the commissions procedures for petitions for modification and shall issue a decision on the petition no later than 180 days after the filing of the petition.
(7)(A)Ex parte communications that occur at conferences and that are within the scope of an adjudication or ratesetting proceeding shall be subject to the requirements of this article, except that communications that occur during the open session of a conference are not ex parte communications. article.
(B)Ex parte communications that occur at conferences and that are within the scope of a quasi-legislative proceeding shall be governed by the ex parte communication disclosure requirements developed by the commission.
(C)For purposes of this section, ex parte communications that occur at conferences includes, but is not limited to, communications in a private setting or during meals, entertainment events, and tours, and informal discussions among conference attendees, but does not include communications that occur during the open session of a conference. attendees.
(8)The commission shall render its decisions based on the law and on the evidence in the record. Ex parte communications shall not be a part of the evidentiary record of the proceedings.
(f)The commission may meet in a closed session to discuss administrative matters so long as no collective consensus is reached or vote taken on any matter requiring a vote of the commissioners. The commission shall, by rule, adopt and publish a definition of administrative matters for purposes of this section.
(g)The commission shall permit written comments received from the public to be included in the record of its proceedings, but the comments shall not be treated as evidence. The commission shall provide parties to the proceeding a reasonable opportunity to respond to any public comments included in the record of proceedings.
(h)It is the intent of the Legislature that the commission, and any entity or person seeking to influence actions taken by the commission, shall be subject to all applicable ethical standards, including any applicable obligations under the Political Reform Act of 1974 (Title 9 (commencing with Section 81000) of the Government Code), including, but not limited to, any applicable lobbying obligations.
SEC. 12.Section 1701.3 of the Public Utilities Code is amended to read:1701.3.(a)This section shall apply only to ratesetting cases, except, if the commission pursuant to Section 1701.1 has determined that a ratesetting case does not require a hearing, the procedures prescribed by subdivisions (b), (d), (f), and (i) shall not apply.
(b)The assigned commissioner shall determine prior to the first hearing whether the commissioner or the assigned administrative law judge shall be designated as the principal hearing officer. The principal hearing officer shall be present for more than one-half of the hearing days. The decision of the principal hearing officer shall be the proposed decision.
(c)An alternate decision may be issued by the assigned commissioner or the assigned administrative law judge who is not the principal hearing officer. Any alternate decision may be filed with the commission and served upon all parties to the proceeding any time prior to issuance of a final decision by the commission, consistent with the requirements of Section 311.
(d)The commission shall establish a procedure for any party to request the presence of a commissioner at a hearing. The assigned commissioner shall be present at any closing arguments in the case.
(e)The principal hearing officer shall present the proposed decision to the full commission in a public meeting. The alternate decision, if any, shall also be presented to the full commission at that public meeting.
(f)The presentation to the full commission shall contain a record of the number of days of the hearing, the number of days that each commissioner was present, and whether the decision was completed on time.
(g)The commission shall provide by rule for peremptory challenges and challenges for cause of the administrative law judge. Challenges for cause shall include, but not be limited to, financial interests and prejudice. All parties shall be entitled to unlimited peremptory challenges in any case in which the administrative law judge has within the previous 12 months served in any capacity in an advocacy position at the commission, been employed by a regulated public utility, or has represented a party or has been an interested person in the case.
(h)(1)Ex parte communications in ratesetting cases are subject to the disclosure requirements of this article. The commission, by order or ruling, may prohibit ex parte communications in a ratesetting case.
(2)Oral communications may be permitted by a decisionmaker if all parties are given not less than three working days notice. No individual ex parte meetings shall be held during the three business days before the commissions scheduled vote on the decision.
(3)(A)If an ex parte communication meeting is granted to any party, all other parties, upon request, shall also be granted individual ex parte meetings of a substantially equal period of time and shall be sent a notice of that opportunity at the time the request is granted.
(B)Subparagraph (A) shall not apply if the decisionmaker participating in the ex parte communication meeting is a member of the personal staff of a commissioner acting in a policy or legal advisory capacity and no other decisionmaker to whom subparagraph (A) applies is a participant.
(4)Written ex parte communications by any interested person may be permitted if copies of the communication are transmitted to all parties on the same day as the original communication.
(5)Written and oral ex parte communications shall not be part of the evidentiary record of the proceeding.
(6)After a proposed decision or order is issued, the commission may establish a quiet period during which no oral or written ex parte communications may be permitted and the commission may meet in closed session during that period. That quiet period shall expire at the end of the commission meeting for which the matter was scheduled to be voted upon and shall not in any circumstance exceed 14 days. If the commission holds the decision, it may establish a subsequent quiet period during the second half of the hold period, which is the interval between the hold date and the date that the decision is calendared for final decision. If the subsequent quiet period is established, ex parte communications shall be allowed only during the first half of the hold period. The commission may meet in closed session for the second half of that period. Any meeting of the commission pursuant to this paragraph shall require a minimum of three days advance public notice.
(i)Any party has the right to present a final oral argument of its case before the commission. Those requests shall be scheduled in a timely manner. A quorum of the commission shall be present for the final oral arguments.
(j)The commission may, in issuing its decision, adopt, modify, or set aside the proposed decision or any part of the decision based on evidence in the record. The final decision of the commission shall be issued not later than 60 days after the issuance of the proposed decision. Under extraordinary circumstances the commission may extend this date for a reasonable period. The 60-day period shall be extended for 30 days if any alternate decision is proposed pursuant to Section 311.
SEC. 13.Section 1711 of the Public Utilities Code is amended to read:1711.(a)Where feasible and appropriate, except for adjudication cases, immediately after determining the scope of the proceeding, the commission shall seek the participation of those who are likely to be affected, including those who are likely to benefit from, and those who are potentially subject to, a decision in that proceeding. The commission shall demonstrate its efforts to comply with this section in the text of the proposed decision.(b)(1)The Policy and Planning Division of the commission shall undertake one or more studies of outreach efforts undertaken by other state and federal utility regulatory bodies and make recommendations to the commission to promote effective outreach, including metrics for use in evaluating success.(2)This subdivision shall remain in effect only until January 1, 2020, and shall have no force or effect on or after that date, unless a later enacted statute that is chaptered before January 1, 2020, deletes or extends that date.SEC. 14.SEC. 13.Section 7931 of the Public Utilities Code is amended to read:7931.(a)This chapter is applicable to telephone corporations, including resellers, and to paging companies, hereafter referred to as providers.
(b)For purposes of this chapter, coordinator means the coordinator for California area code relief as designated by the North American Numbering Council.
(c)Whenever the coordinator and providers evaluate the potential boundaries of a new area code, they shall consider rate area boundaries, municipal boundaries, communities of interest, and other appropriate criteria.
(d)When the coordinator determines the need to establish a new area code, at least 30 months prior to the projected opening of the new area code, the coordinator shall provide written notice to the commission regarding the need to establish the new area code.
(e)From the date the written notice required by subdivision (d) is received by the commission all of the following shall be done:
(1)Within three months all providers shall notify all affected customers in writing of the need to establish a new area code. Nothing in this paragraph requires a customer to receive in one bill more than one notice for each billed number.
(2)Within nine months the coordinator and the commission staff shall notify representatives of local jurisdictions and the public in affected geographic areas, and, at the discretion of the commission, may conduct one or more meetings both for representatives of local jurisdictions and for members of the public in affected geographic areas to inform them of the proposed area code relief options and of measures that may be taken to mitigate any potential disruptions, and to afford them the opportunity to discuss the potential impact of the proposed options.
(3)Within 11 months the coordinator shall file the results of the area code relief planning process with the commission requesting commission approval to implement a plan. Anyone may contest the results of the area code planning process by filing a written protest with the commission not later than 60 days after the results have been filed with the commission.
(f)Unless the commission determines otherwise, at least 12 months prior to the date adopted by the commission for opening the new area code, all of the following shall be done:
(1)The coordinator shall notify the general public of the specific geographic area to be included in both the old and new area codes. The notice shall include the schedule for any transitional dialing periods required by Section 7932.
(2)Each telephone provider serving the specific geographic area included in the existing area code shall give written notice to all its affected customers about the specific geographic area that will be included in the new area code. The notice shall include the schedule for any transitional dialing periods required by Section 7932, and the prefixes that will be contained in the new area code. Nothing in this paragraph requires a customer to receive in one bill more than one notice for each billed telephone number.
(g)Within three months prior to the adopted date for opening the new area code, each provider serving the existing area code shall give written notice to its affected customers of the specific geographic boundaries of the new area code. The notice shall include the schedule for any transitional periods required by Section 7932, and the prefixes that will be contained in the new area code. Nothing in this paragraph requires a customer to receive in one bill more than one notice for each billed number.
SEC. 15.SEC. 14.Section 7937 of the Public Utilities Code is repealed.SEC. 16.SEC. 15.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
The commission shall require an electrical or gas corporation to revise a ratepayer-funded energy efficiency program identified pursuant to Section 913.9 as necessary to ensure that the program complements and does not duplicate a program administered by a state agency.
SEC. 2.Section 421 of the Public Utilities Code is amended to read:421.(a)The commission shall annually determine a fee to be paid by every passenger stage corporation, charter-party carrier of passengers, pipeline corporation, for-hire vessel operator, common carrier vessel operator, railroad corporation, and commercial air operator, and every other common carrier and related business subject to the jurisdiction of the commission, except as otherwise provided in Article 3 (commencing with Section 431) of this chapter and Chapter 6 (commencing with Section 5001) of Division 2.
(b)The annual fee shall be established to produce a total amount equal to the amount established in the authorized commission budget for the same year, including adjustments appropriated by the Legislature and an appropriate reserve, to regulate common carriers and related businesses, less the amount to be paid from special accounts or funds pursuant to Section 403, reimbursements, federal funds, other revenues, and unencumbered funds from the preceding year.
(c)Notwithstanding any other provision of law, the fees paid by railroad corporations shall be used for state-funded railroad investigation and enforcement activities of the commission, other than the rail safety activities funded by the Transportation Planning and Development Account pursuant to Section 99315. The railroad fees shall be set annually at a level that generates not less than the amount sufficient to fund activities pursuant to Sections 765.5, 916.2, and 7712.
(d)Expenditures of the detailed budget for the expenditure of railroad corporation fees submitted to the Legislature pursuant to Section 916.5 shall be limited to the following items:
(1)Expenditures for employees occupying, and actually performing service in, railroad-safety personnel positions that are directly involved in inspecting railroads and enforcing rail safety regulations. The commission shall expend the funds budgeted pursuant to this subdivision for the salaries, per diem, and travel expenses of employees specified in this paragraph, unless, by statute, the commission is specifically prohibited from expending all or part of those funds.
(2)Expenditures for employees occupying, and actually performing service in, clerical and support staff positions that are directly associated with railroad-safety inspections.
(3)Expenditures for legal personnel who actually pursue violations of rail safety regulations beyond the informal complaint level.
(4)Expenditures for the pro rata share of the commissions overhead costs while state personnel are actually occupying the positions and are performing the duties specified in paragraphs (1) to (3), inclusive.
(e)The Department of Finance shall notify the Joint Legislative Budget Committee, pursuant to Section 28.00 of the annual Budget Act, prior to authorizing any change in the Budget Act appropriation for railroad corporation fees that is larger than one hundred thousand dollars ($100,000), or 10 percent of the amount budgeted, whichever is less.
(f)On or before January 1, 1994, the commission shall hire a minimum of four additional operating practices inspectors, exclusive of supervisory personnel, who are, or shall become by July 1, 1994, federally certified, for the purpose of enforcing compliance by railroads operating in this state with state and federal safety regulations.
(g)The commission, in performing its duties, shall limit the expenditure of funds for rail safety purposes to those railroad corporation fees collected pursuant to subdivision (d). In no event shall the commission fund railroad safety activities utilizing funds from other commission accounts unrelated to railroad safety.
SEC. 3.Section 765.7 of the Public Utilities Code is repealed.SEC. 4.Section 776 of the Public Utilities Code is amended to read:776.(a)The commission shall, upon making the determination pursuant to subdivision (c), develop and implement performance reliability standards for all backup power systems installed on the property of residential and small commercial customers by a facilities-based provider of telephony services. Those standards shall do all the following:
(1)Establish minimum operating life.
(2)Establish minimum periods of time during which a telephone system with a charged backup power system will provide the customer with sufficient electricity for emergency usage.
(3)Establish means to warn a customer when the backup power systems charge is low or when the system can no longer hold a charge.
(b)The commission, in developing and implementing any standards in accordance with subdivision (a), shall consider current best practices and technical feasibility for establishing battery backup requirements.
(c)The commission shall not implement standards in accordance with this section unless it determines that the benefits of the standards exceed the costs.
SEC. 5.Section 883 of the Public Utilities Code is amended to read:883.(a)The commission shall, on or before February 1, 2001, issue an order initiating an investigation and opening a proceeding to examine the current and future definitions of universal service. That proceeding shall include public hearings that encourage participation by a broad and diverse range of interests from all areas of the state, including, but not limited to, all of the following:
(1)Consumer groups.
(2)Communication service providers, including all providers of high-speed access services.
(3)Facilities-based telephone providers.
(4)Information service providers and Internet access providers.
(5)Rural and urban users.
(6)Public interest groups.
(7)Representatives of small and large businesses and industry.
(8)Local agencies.
(9)State agencies, including, but not limited to, all of the following:
(A)The Government Operations Agency.
(B)The State Department of Education.
(C)The State Department of Public Health.
(D)The California State Library.
(10)Colleges and universities.
(b)The objectives of the proceeding set forth in subdivision (a) shall include all of the following:
(1)To investigate the feasibility of redefining universal service in light of current trends toward accelerated convergence of voice, video, and data, with an emphasis on the role of basic telecommunications and Internet services in the workplace, in education and workforce training, access to health care, and increased public safety.
(2)To evaluate the extent to which technological changes have reduced the relevance of existing regulatory regimes given their current segmentation based upon technology.
(3)To receive broad-based input from a cross section of interested parties and make recommendations on whether video, data, and Internet service providers should be incorporated into an enhanced Universal Lifeline Service program, as specified, including relevant policy recommendations regarding regulatory and statutory changes and funding options that are consistent with the principles set forth in subdivision (c) of Section 871.7.
(4)To reevaluate prior definitions of basic service in a manner that will, to the extent feasible, effectively incorporate the latest technologies to provide all California residents with all of the following:
(A)Improved quality of life.
(B)Expanded access to public and private resources for education, training, and commerce.
(C)Increased access to public resources enhancing public health and safety.
(D)Assistance in bridging the digital divide through expanded access to new technologies by low income, disabled, or otherwise disadvantaged Californians.
(5)To assess projected costs of providing enhanced universal lifeline service in accordance with the intent of this article, and to delineate the subsidy support needed to maintain the redefined scope of universal service in a competitive market.
(6)To design and recommend an equitable and broad-based subsidy support mechanism for universal service in competitive markets in a manner that conforms with subdivision (c) of Section 871.7.
(7)To develop a process to periodically review and revise the definition of universal service to reflect new technologies and markets consistent with subdivision (c) of Section 871.7.
(8)To consider whether similar regulatory treatment for the provision of similar services is appropriate and feasible.
(c)In conducting its investigation, the commission shall take into account the role played by a number of diverse but convergent industries and providers, even though many of these entities are not subject to economic regulation by the commission or any other government entity.
(d)The recommendations of the commission shall be consistent with state policies for telecommunications as set forth in Section 709, and with all of the following principles:
(1)Universal service shall, to the extent feasible, be provided at affordable prices regardless of linguistic, cultural, ethnic, physical, financial, and geographic considerations.
(2)Consumers shall be provided access to all information needed to allow timely and informed choices about telecommunications products and services that are part of the universal service program and how best to use them.
(3)Education, health care, community, and government institutions shall be positioned as early recipients of new and emerging technologies so as to maximize the economic and social benefits of these services.
SEC. 6.Section 911.2 is added to the Public Utilities Code, to read:911.2.The commission shall report the findings of any risk assessment required by Section 1103 to the Legislature.
SEC. 7.Section 913.9 of the Public Utilities Code is amended to read:913.9.On or before December 31, 2018, and biennially thereafter, the commission shall, in its annual report prepared pursuant to Section 913, identify and report to the Legislature on electrical and gas corporation ratepayer-funded energy efficiency programs that are similar to programs administered by the Energy Commission, the State Air Resources Board, and the California Alternative Energy and Advanced Transportation Financing Authority, and on those programs revised pursuant to Section 381.4.
SEC. 8.Section 916.5 is added to the Public Utilities Code, to read:916.5.By January 1 of each year, the commission shall submit to the Legislature a detailed budget for the expenditure of railroad corporation fees for the ensuing budget year, consistent with Section 421.
SEC. 9.Section 1103 of the Public Utilities Code is amended to read:1103.(a)If a new underground gas storage facility is proposed, the commission shall ensure that a risk assessment evaluating the potential impact of a leak from the facility on public and environmental health, safety, and welfare is conducted by the project proponent. Both acute and chronic exposures from a range of expected emissions and emission rates shall be evaluated. The evaluation shall include consideration of population density in proximal communities, environmentally sensitive areas, emergency response times, evacuation times, possible leak duration, possible chemical species emitted, and local meteorology.
(b)In evaluating the potential risks and impacts of acute and chronic exposures from emissions from a proposed new gas storage facility, the project proponent shall assess or cause to be assessed risks associated with the proposed facilitys proximity to any living quarters, including private homes, condominiums, apartments, retirement homes, prisons, dormitories, or other housing; education resources, including preschools and schools operating kindergarten or any of grades 1 to 12, inclusive; day care centers; and health care facilities, including hospitals, nursing homes, and long-term care and hospice facilities. Based on the risk analysis, appropriate setbacks to the listed structure types shall be determined by the commission.
(c)The risk assessment conducted pursuant to this section shall be subjected to peer review by independent experts whose demonstrated expertise includes, but is not limited to, the fields of public health, epidemiology, and toxicology.
(d)The findings of any risk assessment required by this section shall be reported pursuant to Section 911.2.
SEC. 10.Section 1202 of the Public Utilities Code is amended to read:1202.The commission has the exclusive power:
(a)To determine and prescribe the manner, including the particular point of crossing, and the terms of installation, operation, maintenance, use, and protection of each crossing of one railroad by another railroad or street railroad, of a street railroad by a railroad, of each crossing of a public or publicly used road or highway by a railroad or street railroad, and of a street by a railroad or of a railroad by a street.
(b)To alter, relocate, or abolish by physical closing any crossing set forth in subdivision (a).
(c)To require, where in its judgment it would be practicable, a separation of grades at any crossing established and to prescribe the terms upon which the separation shall be made and the proportions in which the expense of the construction, alteration, relocation, or abolition of crossings or the separation of grades shall be divided between the railroad or street railroad corporations affected or between these corporations and the state, county, city, or other political subdivision affected.
(d)To authorize on an application-by-application basis and supervise the operation of pilot projects to evaluate proposed crossing warning devices, new technology, or other additional safety measures at designated crossings, with the consent of the local jurisdiction, the affected railroad, and other interested parties, including, but not limited to, represented railroad employees.
SEC. 11.Section 1701.1 of the Public Utilities Code is amended to read:1701.1.(a)The commission shall determine whether each proceeding is a quasi-legislative, an adjudication, or a ratesetting proceeding and, consistent with due process, public policy, and statutory requirements, determine whether the proceeding requires a hearing. The commissions decision as to the nature of the proceeding shall be subject to a request for rehearing within 10 days of the date of that decision or of any subsequent ruling that expands the scope of the proceeding. Only those parties who have requested a rehearing within that time period shall subsequently have standing for judicial review and that review shall only be available at the conclusion of the proceeding. The commission shall render its decision regarding the rehearing within 30 days. The commission shall establish rules regarding ex parte communication on case categorization issues.
(b)(1)The commission, upon initiating an adjudication proceeding or ratesetting proceeding, shall assign one or more commissioners to oversee the case and an administrative law judge when appropriate. The assigned commissioner shall schedule a prehearing conference and shall prepare and issue by order or ruling a scoping memo that describes the issues to be considered and the applicable timetable for resolution.
(2)Notwithstanding paragraph (1), for an uncontested adjudication proceeding, the assigned commissioner may exercise his or her discretion to not order a prehearing conference or not prepare and issue a scoping memo.(3)(2)The administrative law judge shall either preside over and conduct, or assist the assigned commissioner or commissioners in presiding over and conducting, any evidentiary or adjudication hearing that may be required.
(c)The commission, upon initiating a quasi-legislative proceeding, shall assign one or more commissioners to oversee the case and an administrative law judge, when appropriate, who may be assisted by a technical advisory staff member in conducting the proceeding. The assigned commissioner shall prepare and issue by order or ruling a scoping memo that describes the issues to be considered and the applicable timetable for resolution, except that, for an uncontested quasi-legislative proceeding, the assigned commissioner may exercise his or her discretion to not prepare and issue a scoping memo. resolution.
(d)(1)Quasi-legislative cases, for purposes of this article, are cases that establish policy, including, but not limited to, rulemakings and investigations that may establish rules affecting an entire industry.
(2)Adjudication cases, for purposes of this article, are enforcement cases and complaints except those challenging the reasonableness of any rates or charges as specified in Section 1702.
(3)Ratesetting cases, for purposes of this article, are cases in which rates are established for a specific company, including, but not limited to, general rate cases, performance-based ratemaking, and other ratesetting mechanisms.
(e)(1)(A)Ex parte communication, for purposes of this article, means any oral or written communication between a decisionmaker and an interested person concerning any matter before the commission that the commission has not specified in its Rules of Practice and Procedure as being a procedural matter and that does not occur in a public hearing, workshop, or other public proceeding, or on the official record of the proceeding on the matter. The commission shall specify in its Rules of Practice and Procedure, enacted by rulemaking, the types of issues considered procedural matters under this article.
(B)Interested person, for purposes of this article, means any of the following:
(i)Any applicant, an agent or an employee of the applicant, or a person receiving consideration for representing the applicant, or a participant in the proceeding on any matter before the commission.
(ii)Any person with a financial interest, as described in Article 1 (commencing with Section 87100) of Chapter 7 of Title 9 of the Government Code, in a matter before the commission, an agent or employee of the person with a financial interest, or a person receiving consideration for representing the person with a financial interest. A person involved in issuing credit ratings or advising entities or persons who invest in the shares or operations of any party to a proceeding is a person with a financial interest.
(iii)A representative acting on behalf of any civic, environmental, neighborhood, business, labor, trade, or similar organization who intends to influence the decision of a commission member on a matter before the commission.
(iv)Other categories of individuals deemed by the commission, by rule, to be an interested person.
(2)The commission shall by rule adopt and publish a definition of decisionmakers and interested persons for purposes of this article, along with any requirements for written reporting of ex parte communications and appropriate sanctions for noncompliance with any rule proscribing ex parte communications. The definition of decisionmakers shall include, but is not limited to: each commissioner; the personal staff of a commissioner if the staff is acting in a policy or legal advisory capacity; the chief administrative law judge of the commission; and the administrative law judge assigned to the proceeding. The commission shall, by rule, explicitly ban both of the following:
(A)The practice of one-way ex parte communications from a decisionmaker to an interested person. A communication made during the open session of a conference or other public meeting is not a one-way communication.
(B)Any communication between an interested person and a decisionmaker regarding which commissioner or administrative law judge may be assigned to a matter before the commission.
(3)For adjudication cases, the rules shall provide that ex parte communications shall be prohibited, as required by this article. The rules shall provide that if an ex parte communication occurs that is prohibited by this article, or if an ex parte communication occurs in a ratesetting case, whether initiated by a decisionmaker or an interested person, all of the following shall be required:
(A)The interested person shall report the communication within three working days of the communication by filing a notice with the commission that includes all the following:
(i)The date, time, and location of the communication, whether the communication was oral or written, or a combination of both, and the communication medium used.
(ii)The identity of the decisionmaker, the identity of the person initiating the communication, and the identities of any other persons present.
(iii)The topic of the communication, including applicable proceeding numbers.
(iv)A substantive description of the interested persons communication and its content.
(v)A copy of any written material or text used during the communication.
(B)Any decisionmaker who participated in the communication shall promptly provide notice of the ex parte communication in a public log and ensure that any parties on the service list of any relevant proceeding are notified of that notice. Notification to the parties on the service list shall additionally be provided in the docket of any relevant proceeding. The notice in the public log shall include all the following:
(i)The date, time, and location of the communication, whether the communication was oral or written, or a combination of both, and the communication medium used.
(ii)The identity of the interested person, the identity of the person initiating the communication, and the identities of any other persons present.
(iii)The topic of the communication, including any applicable proceeding numbers.
(iv)A brief description of the communication.
(C)If the interested person who participated in the communication has not timely submitted the notice required by subparagraph (A), the decisionmaker shall refer the matter to the attorney for the commission, and an assigned commissioner, by ruling, shall order the interested person to submit the required notice. The interested person shall be subject to any applicable penalties for the initial violation and, if the interested person does not submit the required notice within the time period specified in the assigned commissioners ruling, the interested person shall be subject to continuing violations pursuant to Section 2108.
(4)The requirements of paragraph (3) shall not apply to any oral ex parte communication occurring at a meeting if all parties are invited to participate and given not less than three working days notice.
(5)The commission shall not take any vote on a matter in which a notice of a prohibited ex parte communication has been filed pursuant to subparagraph (A) or (B) of paragraph (3) until all parties to the proceeding have been provided a reasonable opportunity to respond to the communication.
(6)If an ex parte communication is not disclosed as required by this subdivision until after the commission has issued a decision on the matter to which the communication pertained, a party not participating in the communication may file a petition to rescind or modify the decision. The party may seek a finding that the ex parte communication significantly influenced the decisions process or outcome as part of any petition to rescind or modify the decision. The commission shall process the petition in accordance with the commissions procedures for petitions for modification and shall issue a decision on the petition no later than 180 days after the filing of the petition.
(7)(A)Ex parte communications that occur at conferences and that are within the scope of an adjudication or ratesetting proceeding shall be subject to the requirements of this article, except that communications that occur during the open session of a conference are not ex parte communications.
(B)Ex parte communications that occur at conferences and that are within the scope of a quasi-legislative proceeding shall be governed by the ex parte communication disclosure requirements developed by the commission.
(C)For purposes of this section, ex parte communications that occur at conferences includes, but is not limited to, communications in a private setting or during meals, entertainment events, and tours, and informal discussions among conference attendees, but does not include communications that occur during the open session of a conference.
(8)The commission shall render its decisions based on the law and on the evidence in the record. Ex parte communications shall not be a part of the evidentiary record of the proceedings.
(f)The commission may meet in a closed session to discuss administrative matters and state legislative proposals so long as no collective consensus is reached or vote taken on any matter requiring a vote of the commissioners. The commission shall, by rule, adopt and publish a definition of administrative matters and state legislative proposals for purposes of this section.
(g)The commission shall permit written comments received from the public to be included in the record of its proceedings, but the comments shall not be treated as evidence. The commission shall provide parties to the proceeding a reasonable opportunity to respond to any public comments included in the record of proceedings.
(h)It is the intent of the Legislature that the commission, and any entity or person seeking to influence actions taken by the commission, shall be subject to all applicable ethical standards, including any applicable obligations under the Political Reform Act of 1974 (Title 9 (commencing with Section 81000) of the Government Code), including, but not limited to, any applicable lobbying obligations.
SEC. 12.Section 1701.3 of the Public Utilities Code is amended to read:1701.3.(a)This section shall apply only to ratesetting cases, except, if the commission pursuant to Section 1701.1 has determined that a ratesetting case does not require a hearing, the procedures prescribed by subdivisions (b), (d), (f), and (i) shall not apply.
(b)The assigned commissioner shall determine prior to the first hearing whether the commissioner or the assigned administrative law judge shall be designated as the principal hearing officer. The principal hearing officer shall be present for more than one-half of the hearing days. The decision of the principal hearing officer shall be the proposed decision.
(c)An alternate decision may be issued by the assigned commissioner or the assigned administrative law judge who is not the principal hearing officer. Any alternate decision may be filed with the commission and served upon all parties to the proceeding any time prior to issuance of a final decision by the commission, consistent with the requirements of Section 311.
(d)The commission shall establish a procedure for any party to request the presence of a commissioner at a hearing. The assigned commissioner shall be present at any closing arguments in the case.
(e)The principal hearing officer shall present the proposed decision to the full commission in a public meeting. The alternate decision, if any, shall also be presented to the full commission at that public meeting.
(f)The presentation to the full commission shall contain a record of the number of days of the hearing, the number of days that each commissioner was present, and whether the decision was completed on time.
(g)The commission shall provide by rule for peremptory challenges and challenges for cause of the administrative law judge. Challenges for cause shall include, but not be limited to, financial interests and prejudice. All parties shall be entitled to unlimited peremptory challenges in any case in which the administrative law judge has within the previous 12 months served in any capacity in an advocacy position at the commission, been employed by a regulated public utility, or has represented a party or has been an interested person in the case.
(h)(1)Ex parte communications in ratesetting cases are subject to the disclosure requirements of this article. The commission, by order or ruling, may prohibit ex parte communications in a ratesetting case.
(2)Oral communications may be permitted by a decisionmaker if all parties are given not less than three working days notice. No individual ex parte meetings shall be held during the three business days before the commissions scheduled vote on the decision.
(3)(A)If an ex parte communication meeting is granted to any party, all other parties, upon request, shall also be granted individual ex parte meetings of a substantially equal period of time and shall be sent a notice of that opportunity at the time the request is granted.
(B)Subparagraph (A) shall not apply if the decisionmaker participating in the ex parte communication meeting is a member of the personal staff of a commissioner acting in a policy or legal advisory capacity and no other decisionmaker to whom subparagraph (A) applies is a participant.
(4)Written ex parte communications by any interested person may be permitted if copies of the communication are transmitted to all parties on the same day as the original communication.
(5)Written and oral ex parte communications shall not be part of the evidentiary record of the proceeding.
(6)After a proposed decision or order is issued, the commission may establish a quiet period during which no oral or written ex parte communications may be permitted and the commission may meet in closed session during that period. That quiet period shall expire at the end of the commission meeting for which the matter was scheduled to be voted upon and shall not in any circumstance exceed 14 days. If the commission holds the decision, it may establish a subsequent quiet period during the second half of the hold period, which is the interval between the hold date and the date that the decision is calendared for final decision. If the subsequent quiet period is established, ex parte communications shall be allowed only during the first half of the hold period. The commission may meet in closed session for the second half of that period. Any meeting of the commission pursuant to this paragraph shall require a minimum of three days advance public notice.
(i)Any party has the right to present a final oral argument of its case before the commission. Those requests shall be scheduled in a timely manner. A quorum of the commission shall be present for the final oral arguments.
(j)The commission may, in issuing its decision, adopt, modify, or set aside the proposed decision or any part of the decision based on evidence in the record. The final decision of the commission shall be issued not later than 60 days after the issuance of the proposed decision. Under extraordinary circumstances the commission may extend this date for a reasonable period. The 60-day period shall be extended for 30 days if any alternate decision is proposed pursuant to Section 311.
SEC. 13.Section 1711 of the Public Utilities Code is amended to read:1711.(a)Where feasible and appropriate, except for adjudication cases, before the commission requests the final briefs by the parties in advance of issuing a proposed decision, immediately after determining the scope of the proceeding, the commission shall seek the participation of those who are likely to be affected, including those who are likely to benefit from, and those who are potentially subject to, a decision in that proceeding. The commission shall demonstrate its efforts to comply with this section in the text of the proposed decision.
(b)(1)The Policy and Planning Division of the commission shall undertake one or more studies of outreach efforts undertaken by other state and federal utility regulatory bodies and make recommendations to the commission to promote effective outreach, including metrics for use in evaluating success.
(2)This subdivision shall remain in effect only until January 1, 2020, and shall have no force or effect on or after that date, unless a later enacted statute that is chaptered before January 1, 2020, deletes or extends that date.
SEC. 14.Section 7931 of the Public Utilities Code is amended to read:7931.(a)This chapter is applicable to telephone corporations, including resellers, and to paging companies, hereafter referred to as providers.
(b)For purposes of this chapter, coordinator means the coordinator for California area code relief as designated by the North American Numbering Council.
(c)Whenever the coordinator and providers evaluate the potential boundaries of a new area code, they shall consider rate area boundaries, municipal boundaries, communities of interest, and other appropriate criteria.
(d)When the coordinator determines the need to establish a new area code, at least 30 months prior to the projected opening of the new area code, the coordinator shall provide written notice to the commission regarding the need to establish the new area code.
(e)From the date the written notice required by subdivision (d) is received by the commission all of the following shall be done:
(1)Within three months all providers shall notify all affected customers in writing of the need to establish a new area code. Nothing in this paragraph requires a customer to receive in one bill more than one notice for each billed number.
(2)Within nine months the coordinator and the commission staff shall notify representatives of local jurisdictions and the public in affected geographic areas, and, at the discretion of the commission, may conduct one or more meetings both for representatives of local jurisdictions and for members of the public in affected geographic areas to inform them of the proposed area code relief options and of measures that may be taken to mitigate any potential disruptions, and to afford them the opportunity to discuss the potential impact of the proposed options.
(3)Within 11 months the coordinator shall file the results of the area code relief planning process with the commission requesting commission approval to implement a plan. Anyone may contest the results of the area code planning process by filing a written protest with the commission not later than 60 days after the results have been filed with the commission.
(f)Unless the commission determines otherwise, at least 12 months prior to the date adopted by the commission for opening the new area code, all of the following shall be done:
(1)The coordinator shall notify the general public of the specific geographic area to be included in both the old and new area codes. The notice shall include the schedule for any transitional dialing periods required by Section 7932.
(2)Each telephone provider serving the specific geographic area included in the existing area code shall give written notice to all its affected customers about the specific geographic area that will be included in the new area code. The notice shall include the schedule for any transitional dialing periods required by Section 7932, and the prefixes that will be contained in the new area code. Nothing in this paragraph requires a customer to receive in one bill more than one notice for each billed telephone number.
(g)Within three months prior to the adopted date for opening the new area code, each provider serving the existing area code shall give written notice to its affected customers of the specific geographic boundaries of the new area code. The notice shall include the schedule for any transitional periods required by Section 7932, and the prefixes that will be contained in the new area code. Nothing in this paragraph requires a customer to receive in one bill more than one notice for each billed number.
SEC. 15.Section 7937 of the Public Utilities Code is repealed.SEC. 16.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
The commission shall require an electrical or gas corporation to revise a ratepayer-funded energy efficiency program identified pursuant to Section 913.9 as necessary to ensure that the program compliments complements and does not duplicate a program administered by a state agency.
SEC. 2.Section 421 of the Public Utilities Code is amended to read:421.(a)The commission shall annually determine a fee to be paid by every passenger stage corporation, charter-party carrier of passengers, pipeline corporation, for-hire vessel operator, common carrier vessel operator, railroad corporation, and commercial air operator, and every other common carrier and related business subject to the jurisdiction of the commission, except as otherwise provided in Article 3 (commencing with Section 431) of this chapter and Chapter 6 (commencing with Section 5001) of Division 2.
(b)The annual fee shall be established to produce a total amount equal to the amount established in the authorized commission budget for the same year, including adjustments appropriated by the Legislature and an appropriate reserve, to regulate common carriers and related businesses, less the amount to be paid from special accounts or funds pursuant to Section 403, reimbursements, federal funds, other revenues, and unencumbered funds from the preceding year.
(c)Notwithstanding any other provision of law, the fees paid by railroad corporations shall be used for state-funded railroad investigation and enforcement activities of the commission, other than the rail safety activities funded by the Transportation Planning and Development Account pursuant to Section 99315. The railroad fees shall be set annually at a level that generates not less than the amount sufficient to fund activities pursuant to Sections 765.5, 916.2, and 7712.
(d)Expenditures of the detailed budget for the expenditure of railroad corporation fees submitted to the Legislature pursuant to Section 916.5 shall be limited to the following items:
(1)Expenditures for employees occupying, and actually performing service in, railroad-safety personnel positions that are directly involved in inspecting railroads and enforcing rail safety regulations. The commission shall expend the funds budgeted pursuant to this subdivision for the salaries, per diem, and travel expenses of employees specified in this paragraph, unless, by statute, the commission is specifically prohibited from expending all or part of those funds.
(2)Expenditures for employees occupying, and actually performing service in, clerical and support staff positions that are directly associated with railroad-safety inspections.
(3)Expenditures for legal personnel who actually pursue violations of rail safety regulations beyond the informal complaint level.
(4)Expenditures for the pro rata share of the commissions overhead costs while state personnel are actually occupying the positions and are performing the duties specified in paragraphs (1) to (3), inclusive.
(e)The Department of Finance shall notify the Joint Legislative Budget Committee, pursuant to Section 28.00 of the annual Budget Act, prior to authorizing any change in the Budget Act appropriation for railroad corporation fees that is larger than one hundred thousand dollars ($100,000), or 10 percent of the amount budgeted, whichever is less.
(f)On or before January 1, 1994, the commission shall hire a minimum of four additional operating practices inspectors, exclusive of supervisory personnel, who are, or shall become by July 1, 1994, federally certified, for the purpose of enforcing compliance by railroads operating in this state with state and federal safety regulations.
(g)The commission, in performing its duties, shall limit the expenditure of funds for rail safety purposes to those railroad corporation fees collected pursuant to subdivision (d). In no event, event shall the commission fund railroad safety activities utilizing funds from other commission accounts unrelated to railroad safety.
SEC. 3.Section 765.7 of the Public Utilities Code is repealed.SEC. 4.Section 776 of the Public Utilities Code is amended to read:776.(a)The commission shall, upon making the determination pursuant to subdivision (c), develop and implement performance reliability standards for all backup power systems installed on the property of residential and small commercial customers by a facilities-based provider of telephony services. Those standards shall do all the following:
(1)Establish minimum operating life.
(2)Establish minimum periods of time during which a telephone system with a charged backup power system will provide the customer with sufficient electricity for emergency usage.
(3)Establish means to warn a customer when the backup power systems charge is low or when the system can no longer hold a charge.
(b)The commission, in developing and implementing any standards in accordance with subdivision (a), shall consider current best practices and technical feasibility for establishing battery backup requirements.
(c)The commission shall not implement standards in accordance with this section unless it determines that the benefits of the standards exceed the costs.
SEC. 5.Section 883 of the Public Utilities Code is amended to read:883.(a)The commission shall, on or before February 1, 2001, issue an order initiating an investigation and opening a proceeding to examine the current and future definitions of universal service. That proceeding shall include public hearings that encourage participation by a broad and diverse range of interests from all areas of the state, including, but not limited to, all of the following:
(1)Consumer groups.
(2)Communication service providers, including all providers of high-speed access services.
(3)Facilities-based telephone providers.
(4)Information service providers and Internet access providers.
(5)Rural and urban users.
(6)Public interest groups.
(7)Representatives of small and large businesses and industry.
(8)Local agencies.
(9)State agencies, including, but not limited to, all of the following:
(A)The Government Operations Agency.
(B)The State Department of Education.
(C)The State Department of Public Health.
(D)The California State Library.
(10)Colleges and universities.
(b)The objectives of the proceeding set forth in subdivision (a) shall include all of the following:
(1)To investigate the feasibility of redefining universal service in light of current trends toward accelerated convergence of voice, video, and data, with an emphasis on the role of basic telecommunications and Internet services in the workplace, in education and workforce training, access to health care, and increased public safety.
(2)To evaluate the extent to which technological changes have reduced the relevance of existing regulatory regimes given their current segmentation based upon technology.
(3)To receive broad-based input from a cross section of interested parties and make recommendations on whether video, data, and Internet service providers should be incorporated into an enhanced Universal Lifeline Service program, as specified, including relevant policy recommendations regarding regulatory and statutory changes and funding options that are consistent with the principles set forth in subdivision (c) of Section 871.7.
(4)To reevaluate prior definitions of basic service in a manner that will, to the extent feasible, effectively incorporate the latest technologies to provide all California residents with all of the following:
(A)Improved quality of life.
(B)Expanded access to public and private resources for education, training, and commerce.
(C)Increased access to public resources enhancing public health and safety.
(D)Assistance in bridging the digital divide through expanded access to new technologies by low income, disabled, or otherwise disadvantaged Californians.
(5)To assess projected costs of providing enhanced universal lifeline service in accordance with the intent of this article, and to delineate the subsidy support needed to maintain the redefined scope of universal service in a competitive market.
(6)To design and recommend an equitable and broad-based subsidy support mechanism for universal service in competitive markets in a manner that conforms with subdivision (c) of Section 871.7.
(7)To develop a process to periodically review and revise the definition of universal service to reflect new technologies and markets consistent with subdivision (c) of Section 871.7.
(8)To consider whether similar regulatory treatment for the provision of similar services is appropriate and feasible.
(c)In conducting its investigation, the commission shall take into account the role played by a number of diverse but convergent industries and providers, even though many of these entities are not subject to economic regulation by the commission or any other government entity.
(d)The recommendations of the commission shall be consistent with state policies for telecommunications as set forth in Section 709, and with all of the following principles:
(1)Universal service shall, to the extent feasible, be provided at affordable prices regardless of linguistic, cultural, ethnic, physical, financial, and geographic considerations.
(2)Consumers shall be provided access to all information needed to allow timely and informed choices about telecommunications products and services that are part of the universal service program and how best to use them.
(3)Education, health care, community, and government institutions shall be positioned as early recipients of new and emerging technologies so as to maximize the economic and social benefits of these services.
SEC. 6.Section 911.2 is added to the Public Utilities Code, to read:911.2.The commission shall report the findings of any risk assessment required by Section 1103 to the Legislature.
SEC. 7.Section 913.9 of the Public Utilities Code is amended to read:913.9.On or before December 31, 2018, and biennially thereafter, the commission shall, in its annual report prepared pursuant to Section 913, identify and report to the Legislature on electrical and gas corporation ratepayer-funded energy efficiency programs that are similar to programs administered by the Energy Commission, the State Air Resources Board, and the California Alternative Energy and Advanced Transportation Financing Authority, and on those programs revised pursuant to Section 381.4.
SEC. 8.Section 916.5 is added to the Public Utilities Code, to read:916.5.By January 1 of each year, the commission shall submit to the Legislature a detailed budget for the expenditure of railroad corporation fees for the ensuing budget year, consistent with Section 421.
SEC. 9.Section 1103 of the Public Utilities Code is amended to read:1103.(a)If a new underground gas storage facility is proposed, the commission shall ensure that a risk assessment evaluating the potential impact of a leak from the facility on public and environmental health, safety, and welfare is conducted by the project proponent. Both acute and chronic exposures from a range of expected emissions and emissions emission rates shall be evaluated. The evaluation shall include consideration of population density in proximal communities, environmentally sensitive areas, emergency response times, evacuation times, possible leak duration, possible chemical species emitted, and local meteorology.
(b)In evaluating the potential risks and impacts of acute and chronic exposures from emissions from a proposed new gas storage facility, the project proponent shall assess or cause to be assessed risks associated with the proposed facilitys proximity to any living quarters, including private homes, condominiums, apartments, retirement homes, prisons, dormitories, or other housing; education resources, including preschools and schools operating kindergarten or any of grades 1 to 12, inclusive; day care centers; and health care facilities, including hospitals, nursing homes, and long-term care and hospice facilities. Based on the risk analysis, appropriate setbacks to the listed structure types shall be determined by the commission.
(c)The risk assessment conducted pursuant to this section shall be subjected to peer review by independent experts whose demonstrated expertise includes, but is not limited to, the fields of public health, epidemiology, and toxicology.
(d)The findings of any risk assessment required by this section shall be reported pursuant to Section 911.2.
SEC. 10.Section 1202 of the Public Utilities Code is amended to read:1202.The commission has the exclusive power:
(a)To determine and prescribe the manner, including the particular point of crossing, and the terms of installation, operation, maintenance, use, and protection of each crossing of one railroad by another railroad or street railroad, of a street railroad by a railroad, of each crossing of a public or publicly used road or highway by a railroad or street railroad, and of a street by a railroad or of a railroad by a street.
(b)To alter, relocate, or abolish by physical closing any crossing set forth in subdivision (a).
(c)To require, where in its judgment it would be practicable, a separation of grades at any crossing established and to prescribe the terms upon which the separation shall be made and the proportions in which the expense of the construction, alteration, relocation, or abolition of crossings or the separation of grades shall be divided between the railroad or street railroad corporations affected or between these corporations and the state, county, city, or other political subdivision affected.
(d)To authorize on an application-by-application basis and supervise the operation of pilot projects to evaluate proposed crossing warning devices, new technology, or other additional safety measures at designated crossings, with the consent of the local jurisdiction, the affected railroad, and other interested parties, including, but not limited to, represented railroad employees.
SEC. 11.Section 1701.1 of the Public Utilities Code is amended to read:1701.1.(a)The commission shall determine whether each proceeding is a quasi-legislative, an adjudication, or a ratesetting proceeding and, consistent with due process, public policy, and statutory requirements, determine whether the proceeding requires a hearing. The commissions decision as to the nature of the proceeding shall be subject to a request for rehearing within 10 days of the date of that decision or of any subsequent ruling that expands the scope of the proceeding. Only those parties who have requested a rehearing within that time period shall subsequently have standing for judicial review and that review shall only be available at the conclusion of the proceeding. The commission shall render its decision regarding the rehearing within 30 days. The commission shall establish rules regarding ex parte communication on case categorization issues.
(b)(1)The commission, upon initiating an adjudication proceeding or ratesetting proceeding, shall assign one or more commissioners to oversee the case and an administrative law judge when appropriate. The assigned commissioner shall schedule a prehearing conference. The assigned commissioner shall conference and shall prepare and issue by order or ruling a scoping memo that describes the issues to be considered and the applicable timetable for resolution. The
(2)Notwithstanding paragraph (1), for an uncontested adjudication proceeding, the assigned commissioner may exercise his or her discretion to not order a prehearing conference or not prepare and issue a scoping memo.
(3)The administrative law judge shall either preside over and conduct, or assist the assigned commissioner or commissioners in presiding over and conducting, any evidentiary or adjudication hearing that may be required.
(c)The commission, upon initiating a quasi-legislative proceeding, shall assign one or more commissioners to oversee the case and an administrative law judge, when appropriate, who may be assisted by a technical advisory staff member in conducting the proceeding. The assigned commissioner shall prepare and issue by order or ruling a scoping memo that describes the issues to be considered and the applicable timetable for resolution. resolution, except that, for an uncontested quasi-legislative proceeding, the assigned commissioner may exercise his or her discretion to not prepare and issue a scoping memo.
(d)(1)Quasi-legislative cases, for purposes of this article, are cases that establish policy, including, but not limited to, rulemakings and investigations that may establish rules affecting an entire industry.
(2)Adjudication cases, for purposes of this article, are enforcement cases and complaints except those challenging the reasonableness of any rates or charges as specified in Section 1702.
(3)Ratesetting cases, for purposes of this article, are cases in which rates are established for a specific company, including, but not limited to, general rate cases, performance-based ratemaking, and other ratesetting mechanisms.
(e)(1)(A)Ex parte communication, for purposes of this article, means any oral or written communication between a decisionmaker and an interested person concerning any matter before the commission that the commission has not specified in its Rules of Practice and Procedure as being a procedural matter and that does not occur in a public hearing, workshop, or other public proceeding, or on the official record of the proceeding on the matter. The commission shall specify in its Rules of Practice and Procedure, enacted by rulemaking, the types of issues considered procedural matters under this article.
(B)Interested person, for purposes of this article, means any of the following:
(i)Any applicant, an agent or an employee of the applicant, or a person receiving consideration for representing the applicant, or a participant in the proceeding on any matter before the commission.
(ii)Any person with a financial interest, as described in Article 1 (commencing with Section 87100) of Chapter 7 of Title 9 of the Government Code, in a matter before the commission, an agent or employee of the person with a financial interest, or a person receiving consideration for representing the person with a financial interest. A person involved in issuing credit ratings or advising entities or persons who invest in the shares or operations of any party to a proceeding is a person with a financial interest.
(iii)A representative acting on behalf of any civic, environmental, neighborhood, business, labor, trade, or similar organization who intends to influence the decision of a commission member on a matter before the commission.
(iv)Other categories of individuals deemed by the commission, by rule, to be an interested person.
(2)The commission shall by rule adopt and publish a definition of decisionmakers and interested persons for purposes of this article, along with any requirements for written reporting of ex parte communications and appropriate sanctions for noncompliance with any rule proscribing ex parte communications. The definition of decisionmakers shall include, but is not limited to: each commissioner; the personal staff of a commissioner if the staff is acting in a policy or legal advisory capacity; the chief administrative law judge of the commission; and the administrative law judge assigned to the proceeding. The commission shall, by rule, explicitly ban both of the following:
(A)The practice of one-way ex parte communications from a decisionmaker to an interested person. A communication made during the open session of a conference or other public meeting is not a one-way communication.
(B)Any communication between an interested person and a decisionmaker regarding which commissioner or administrative law judge may be assigned to a matter before the commission.
(3)For adjudication cases, the rules shall provide that ex parte communications shall be prohibited, as required by this article. The rules shall provide that if an ex parte communication occurs that is prohibited by this article, or if an ex parte communication occurs in a ratesetting case, whether initiated by a decisionmaker or an interested person, all of the following shall be required:
(A)The interested person shall report the communication within three working days of the communication by filing a notice with the commission that includes all the following:
(i)The date, time, and location of the communication, whether the communication was oral or written, or a combination of both, and the communication medium used.
(ii)The identity of the decisionmaker, the identity of the person initiating the communication, and the identities of any other persons present.
(iii)The topic of the communication, including applicable proceeding numbers.
(iv)A substantive description of the interested persons communication and its content.
(v)A copy of any written material or text used during the communication.
(B)Any decisionmaker who participated in the communication shall promptly log provide notice of the ex parte communication by filing a notice that includes in a public log and ensure that any parties on the service list of any relevant proceeding are notified of that notice. The notice in the public log shall include all the following:
(i)The date, time, and location of the communication, whether the communication was oral or written, or a combination of both, and the communication medium used.
(ii)The identity of the interested person, the identity of the person initiating the communication, and the identities of any other persons present.
(iii)The topic of the communication, including any applicable proceeding numbers.
(iv)A brief description of the communication.
(C)If the interested person who participated in the communication has not timely submitted the notice required by subparagraph (A), the decisionmaker shall refer the matter to the attorney for the commission, and an assigned commissioner, by ruling, shall order the interested person to submit the required notice. The interested person shall be subject to any applicable penalties for the initial violation and, if the interested person does not submit the required notice within the time period specified in the assigned commissioners ruling, the interested person shall be subject to continuing violations pursuant to Section 2108.
(4)The requirements of paragraph (3) shall not apply to any oral ex parte communication occurring at a meeting if all parties are invited to participate and given not less than three working days notice.
(5)The commission shall not take any vote on a matter in which a notice of a prohibited ex parte communication has been filed pursuant to subparagraph (A) or (B) of paragraph (3) until all parties to the proceeding have been provided a reasonable opportunity to respond to the communication.
(6)If an ex parte communication is not disclosed as required by this subdivision until after the commission has issued a decision on the matter to which the communication pertained, a party not participating in the communication may file a petition to rescind or modify the decision. The party may seek a finding that the ex parte communication significantly influenced the decisions process or outcome as part of any petition to rescind or modify the decision. The commission shall process the petition in accordance with the commissions procedures for petitions for modification and shall issue a decision on the petition no later than 180 days after the filing of the petition.
(7)(A)Ex parte communications that occur at conferences and that are within the scope of an adjudication or ratesetting proceeding shall be subject to the requirements of this article. article, except that communications that occur during the open session of a conference are not ex parte communications.
(B)Ex parte communications that occur at conferences and that are within the scope of a quasi-legislative proceeding shall be governed by the ex parte communication disclosure requirements developed by the commission.
(C)For purposes of this section, ex parte communications that occur at conferences includes, but is not limited to, communications in a private setting or during meals, entertainment events, and tours, and informal discussions among conference attendees. attendees, but does not include communications that occur during the open session of a conference.
(8)The commission shall render its decisions based on the law and on the evidence in the record. Ex parte communications shall not be a part of the evidentiary record of the proceedings.
(f)The commission may meet in a closed session to discuss administrative matters and state legislative proposals so long as no collective consensus is reached or vote taken on any matter requiring a vote of the commissioners. The commission shall, by rule, adopt and publish a definition of administrative matters and state legislative proposals for purposes of this section.
(g)The commission shall permit written comments received from the public to be included in the record of its proceedings, but the comments shall not be treated as evidence. The commission shall provide parties to the proceeding a reasonable opportunity to respond to any public comments included in the record of proceedings.
(h)It is the intent of the Legislature that the commission, and any entity or person seeking to influence actions taken by the commission, shall be subject to all applicable ethical standards, including any applicable obligations under the Political Reform Act of 1974 (Title 9 (commencing with Section 81000) of the Government Code), including, but not limited to, any applicable lobbying obligations.
SEC. 12.Section 1701.3 of the Public Utilities Code is amended to read:1701.3.(a)This section shall apply only to ratesetting cases, except, if the commission pursuant to Section 1701.1 has determined that a ratesetting case does not require a hearing, the procedures prescribed by subdivisions (b), (d), (f), and (i) shall not apply.
(b)The assigned commissioner shall determine prior to the first hearing whether the commissioner or the assigned administrative law judge shall be designated as the principal hearing officer. The principal hearing officer shall be present for more than one-half of the hearing days. The decision of the principal hearing officer shall be the proposed decision.
(c)An alternate decision may be issued by the assigned commissioner or the assigned administrative law judge who is not the principal hearing officer. Any alternate decision may be filed with the commission and served upon all parties to the proceeding any time prior to issuance of a final decision by the commission, consistent with the requirements of Section 311.
(d)The commission shall establish a procedure for any party to request the presence of a commissioner at a hearing. The assigned commissioner shall be present at any closing arguments in the case.
(e)The principal hearing officer shall present the proposed decision to the full commission in a public meeting. The alternate decision, if any, shall also be presented to the full commission at that public meeting.
(f)The presentation to the full commission shall contain a record of the number of days of the hearing, the number of days that each commissioner was present, and whether the decision was completed on time.
(g)The commission shall provide by rule for peremptory challenges and challenges for cause of the administrative law judge. Challenges for cause shall include, but not be limited to, financial interests and prejudice. All parties shall be entitled to unlimited peremptory challenges in any case in which the administrative law judge has within the previous 12 months served in any capacity in an advocacy position at the commission, been employed by a regulated public utility, or has represented a party or has been an interested person in the case.
(h)(1)Ex parte communications in ratesetting cases are subject to the disclosure requirements of this article. The commission, by order or ruling, may prohibit ex parte communications in a ratesetting case.
(2)Oral communications may be permitted by a decisionmaker if all parties are given not less than three working days notice. No individual ex parte meetings shall be held during the three business days before the commissions scheduled vote on the decision.
(3)(A)If an ex parte communication meeting is granted to any party, all other parties, upon request, shall also be granted individual ex parte meetings of a substantially equal period of time and shall be sent a notice of that opportunity at the time the request is granted.
(B)Subparagraph (A) shall not apply if the decisionmaker participating in the ex parte communication meeting is a member of the personal staff of a commissioner acting in a policy or legal advisory capacity and no other decisionmaker to whom subparagraph (A) applies is a participant.
(4)Written ex parte communications by any interested person may be permitted if copies of the communication are transmitted to all parties on the same day as the original communication.
(5)Written and oral ex parte communications shall not be part of the evidentiary record of the proceeding.
(6)The After a proposed decision or order is issued, the commission may establish a period quiet period during which no oral or written ex parte communications may be permitted and the commission may meet in closed session during that period, which period. That quiet period shall expire at the end of the commission meeting for which the matter was scheduled to be voted upon and shall not in any circumstance exceed 14 days. If the commission holds the decision, it may permit ex parte communications during the first half of establish a subsequent quiet period during the second half of the hold period, which is the interval between the hold date and the date that the decision is calendared for final decision. If the subsequent quiet period is established, ex parte communications shall be allowed only during the first half of the hold period. The commission may meet in closed session for the second half of that interval. period. Any meeting of the commission pursuant to this paragraph shall require a minimum of three days advance public notice.
(i)Any party has the right to present a final oral argument of its case before the commission. Those requests shall be scheduled in a timely manner. A quorum of the commission shall be present for the final oral arguments.
(j)The commission may, in issuing its decision, adopt, modify, or set aside the proposed decision or any part of the decision based on evidence in the record. The final decision of the commission shall be issued not later than 60 days after the issuance of the proposed decision. Under extraordinary circumstances the commission may extend this date for a reasonable period. The 60-day period shall be extended for 30 days if any alternate decision is proposed pursuant to Section 311.
SEC. 13.Section 1711 of the Public Utilities Code is amended to read:1711.(a)Where feasible and appropriate, except for adjudication cases, before determining the scope of the proceeding, the commission requests the final briefs by the parties in advance of issuing a proposed decision, the commission shall seek the participation of those who are likely to be affected, including those who are likely to benefit from, and those who are potentially subject to, a decision in that proceeding. The commission shall demonstrate its efforts to comply with this section in the text of the initial scoping memo of the proceeding. proposed decision.
(b)(1)The Policy and Planning Division of the commission shall undertake one or more studies of outreach efforts undertaken by other state and federal utility regulatory bodies and make recommendations to the commission to promote effective outreach, including metrics for use in evaluating success.
(2)This subdivision shall remain in effect only until January 1, 2020, and shall have no force or effect on or after that date, unless a later enacted statute that is chaptered before January 1, 2020, deletes or extends that date.
SEC. 14.Section 7931 of the Public Utilities Code is amended to read:7931.(a)This chapter is applicable to telephone corporations, including resellers, and to paging companies, hereafter referred to as providers.
(b)For purposes of this chapter, coordinator means the coordinator for California area code relief as designated by the North American Numbering Council.
(c)Whenever the coordinator and providers evaluate the potential boundaries of a new area code, they shall consider rate area boundaries, municipal boundaries, communities of interest, and other appropriate criteria.
(d)When the coordinator determines the need to establish a new area code, at least 30 months prior to the projected opening of the new area code, the coordinator shall provide written notice to the commission regarding the need to establish the new area code.
(e)From the date the written notice required by subdivision (d) is received by the commission all of the following shall be done:
(1)Within three months all providers shall notify all affected customers in writing of the need to establish a new area code. Nothing in this paragraph requires a customer to receive in one bill more than one notice for each billed number.
(2)Within nine months the coordinator and the commission staff shall notify representatives of local jurisdictions and the public in affected geographic areas, and, at the discretion of the commission, may conduct at least one meeting or more meetings both for representatives of local jurisdictions and for members of the public in affected geographic areas to inform them of the proposed area code relief options, options and of measures that may be taken to mitigate any potential disruptions, and to afford them the opportunity to discuss the potential impact of the proposed options. Following the local jurisdiction meeting, the coordinator and the commission staff shall conduct at least three public meetings in the affected geographical area. The public meetings are to inform members of the public about the proposed area code relief options, and to afford affected customers an opportunity to discuss the potential impact of the proposed area code relief options and measures that may be taken to mitigate any potential disruptions. The commission may order additional public meetings to be held at any time.
(3)Within 11 months the coordinator shall file the results of the area code relief planning process with the commission requesting commission approval to implement a plan. Anyone may contest the results of the area code planning process by filing a written protest with the commission not later than 60 days after the results have been filed with the commission.
(f)Unless the commission determines otherwise, at least 12 months prior to the date adopted by the commission for opening the new area code, all of the following shall be done:
(1)The coordinator shall notify the general public of the specific geographic area to be included in both the old and new area codes. The notice shall include the schedule for any transitional dialing periods required by Section 7932.
(2)Each telephone provider serving the specific geographic area included in the existing area code shall give written notice to all its affected customers about the specific geographic area that will be included in the new area code. The notice shall include the schedule for any transitional dialing periods required by Section 7932, and the prefixes that will be contained in the new area code. Nothing in this paragraph requires a customer to receive in one bill more than one notice for each billed telephone number.
(g)Within three months prior to the adopted date for opening the new area code, each provider serving the existing area code shall give written notice to its affected customers of the specific geographic boundaries of the new area code. The notice shall include the schedule for any transitional periods required by Section 7932, and the prefixes that will be contained in the new area code. Nothing in this paragraph requires a customer to receive in one bill more than one notice for each billed number.
SEC. 11.SEC. 15.Section 7937 of the Public Utilities Code is repealed.SEC. 16.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
The commission shall require an electrical or gas corporation to revise a ratepayer-funded energy efficiency program identified pursuant to Section 913.9 as necessary to ensure that the program compliments and does not duplicate a program administered by a state agency.
SEC. 2.Section 421 of the Public Utilities Code is amended to read:421.(a)The commission shall annually determine a fee to be paid by every passenger stage corporation, charter-party carrier of passengers, pipeline corporation, for-hire vessel operator, common carrier vessel operator, railroad corporation, and commercial air operator, and every other common carrier and related business subject to the jurisdiction of the commission, except as otherwise provided in Article 3 (commencing with Section 431) of this chapter and Chapter 6 (commencing with Section 5001) of Division 2.
(b)The annual fee shall be established to produce a total amount equal to the amount established in the authorized commission budget for the same year, including adjustments appropriated by the Legislature and an appropriate reserve, to regulate common carriers and related businesses, less the amount to be paid from special accounts or funds pursuant to Section 403, reimbursements, federal funds, other revenues, and unencumbered funds from the preceding year.
(c)Notwithstanding any other provision of law, the fees paid by railroad corporations shall be used for state-funded railroad investigation and enforcement activities of the commission, other than the rail safety activities funded by the Transportation Planning and Development Account pursuant to Section 99315. The railroad fees shall be set annually at a level that generates not less than the amount sufficient to fund activities pursuant to Sections 765.5, 916.2, and 7712.
(d)Expenditures of the detailed budget for the expenditure of railroad corporation fees submitted to the Legislature pursuant to Section 916.5 shall be limited to the following items:
(1)Expenditures for employees occupying, and actually performing service in, railroad-safety personnel positions that are directly involved in inspecting railroads and enforcing rail safety regulations. The commission shall expend the funds budgeted pursuant to this subdivision for the salaries, per diem, and travel expenses of employees specified in this paragraph, unless, by statute, the commission is specifically prohibited from expending all or part of those funds.
(2)Expenditures for employees occupying, and actually performing service in, clerical and support staff positions that are directly associated with railroad-safety inspections.
(3)Expenditures for legal personnel who actually pursue violations of rail safety regulations beyond the informal complaint level.
(4)Expenditures for the pro rata share of the commissions overhead costs while state personnel are actually occupying the positions and are performing the duties specified in paragraphs (1) to (3), inclusive.
(e)The Department of Finance shall notify the Joint Legislative Budget Committee, pursuant to Section 28.00 of the annual Budget Act, prior to authorizing any change in the Budget Act appropriation for railroad corporation fees that is larger than one hundred thousand dollars ($100,000), or 10 percent of the amount budgeted, whichever is less.
(f)On or before January 1, 1994, the commission shall hire a minimum of four additional operating practices inspectors, exclusive of supervisory personnel, who are, or shall become by July 1, 1994, federally certified, for the purpose of enforcing compliance by railroads operating in this state with state and federal safety regulations.
(g)The commission, in performing its duties, shall limit the expenditure of funds for rail safety purposes to those railroad corporation fees collected pursuant to subdivision (d). In no event, shall the commission fund railroad safety activities utilizing funds from other commission accounts unrelated to railroad safety.
SEC. 3.Section 765.7 of the Public Utilities Code is repealed.SEC. 4.Section 776 of the Public Utilities Code is amended to read:776.(a)The commission shall, upon making the determination pursuant to subdivision (c), develop and implement performance reliability standards for all backup power systems installed on the property of residential and small commercial customers by a facilities-based provider of telephony services. Those standards shall do all the following:
(1)Establish minimum operating life.
(2)Establish minimum periods of time during which a telephone system with a charged backup power system will provide the customer with sufficient electricity for emergency usage.
(3)Establish means to warn a customer when the backup power systems charge is low or when the system can no longer hold a charge.
(b)The commission, in developing and implementing any standards in accordance with subdivision (a), shall consider current best practices and technical feasibility for establishing battery backup requirements.
(c)The commission shall not implement standards in accordance with this section unless it determines that the benefits of the standards exceed the costs.
SEC. 5.Section 883 of the Public Utilities Code is amended to read:883.(a)The commission shall, on or before February 1, 2001, issue an order initiating an investigation and opening a proceeding to examine the current and future definitions of universal service. That proceeding shall include public hearings that encourage participation by a broad and diverse range of interests from all areas of the state, including, but not limited to, all of the following:
(1)Consumer groups.
(2)Communication service providers, including all providers of high-speed access services.
(3)Facilities-based telephone providers.
(4)Information service providers and Internet access providers.
(5)Rural and urban users.
(6)Public interest groups.
(7)Representatives of small and large businesses and industry.
(8)Local agencies.
(9)State agencies, including, but not limited to, all of the following:
(A)The Government Operations Agency.
(B)The State Department of Education.
(C)The State Department of Public Health.
(D)The California State Library.
(10)Colleges and universities.
(b)The objectives of the proceeding set forth in subdivision (a) shall include all of the following:
(1)To investigate the feasibility of redefining universal service in light of current trends toward accelerated convergence of voice, video, and data, with an emphasis on the role of basic telecommunications and Internet services in the workplace, in education and workforce training, access to health care, and increased public safety.
(2)To evaluate the extent to which technological changes have reduced the relevance of existing regulatory regimes given their current segmentation based upon technology.
(3)To receive broad-based input from a cross section of interested parties and make recommendations on whether video, data, and Internet service providers should be incorporated into an enhanced Universal Lifeline Service program, as specified, including relevant policy recommendations regarding regulatory and statutory changes and funding options that are consistent with the principles set forth in subdivision (c) of Section 871.7.
(4)To reevaluate prior definitions of basic service in a manner that will, to the extent feasible, effectively incorporate the latest technologies to provide all California residents with all of the following:
(A)Improved quality of life.
(B)Expanded access to public and private resources for education, training, and commerce.
(C)Increased access to public resources enhancing public health and safety.
(D)Assistance in bridging the digital divide through expanded access to new technologies by low income, disabled, or otherwise disadvantaged Californians.
(5)To assess projected costs of providing enhanced universal lifeline service in accordance with the intent of this article, and to delineate the subsidy support needed to maintain the redefined scope of universal service in a competitive market.
(6)To design and recommend an equitable and broad-based subsidy support mechanism for universal service in competitive markets in a manner that conforms with subdivision (c) of Section 871.7.
(7)To develop a process to periodically review and revise the definition of universal service to reflect new technologies and markets consistent with subdivision (c) of Section 871.7.
(8)To consider whether similar regulatory treatment for the provision of similar services is appropriate and feasible.
(c)In conducting its investigation, the commission shall take into account the role played by a number of diverse but convergent industries and providers, even though many of these entities are not subject to economic regulation by the commission or any other government entity.
(d)The recommendations of the commission shall be consistent with state policies for telecommunications as set forth in Section 709, and with all of the following principles:
(1)Universal service shall, to the extent feasible, be provided at affordable prices regardless of linguistic, cultural, ethnic, physical, financial, and geographic considerations.
(2)Consumers shall be provided access to all information needed to allow timely and informed choices about telecommunications products and services that are part of the universal service program and how best to use them.
(3)Education, health care, community, and government institutions shall be positioned as early recipients of new and emerging technologies so as to maximize the economic and social benefits of these services.
SEC. 6.Section 911.2 is added to the Public Utilities Code, to read:911.2.The commission shall report the findings of any risk assessment required by Section 1103 to the Legislature.
SEC. 7.Section 913.9 of the Public Utilities Code is amended to read:913.9.On or before December 31, 2018, and biennially thereafter, the commission shall shall, in its annual report prepared pursuant to Section 913, identify and report to the Legislature on electrical and gas corporation ratepayer-funded energy efficiency programs that are similar to programs administered by the Energy Commission, the State Air Resources Board, and the California Alternative Energy and Advanced Transportation Financing Authority, and on those programs revised pursuant to Section 381.4.
SEC. 8.Section 916.5 is added to the Public Utilities Code, to read:916.5.By January 1 of each year, the commission shall submit to the Legislature a detailed budget for the expenditure of railroad corporation fees for the ensuing budget year, consistent with Section 421.
SEC. 9.Section 1103 of the Public Utilities Code is amended to read:1103.(a)If a new underground gas storage facility is proposed, the commission shall ensure that a risk assessment evaluating the potential impact of a leak from the facility on public and environmental health, safety, and welfare is conducted by the project proponent. Both acute and chronic exposures from a range of expected emissions and emissions rates shall be evaluated. The evaluation shall include consideration of population density in proximal communities, environmentally sensitive areas, emergency response times, evacuation times, possible leak duration, possible chemical species emitted, and local meteorology.
(b)In evaluating the potential risks and impacts of acute and chronic exposures from emissions from a proposed new gas storage facility, the project proponent shall assess or cause to be assessed risks associated with the proposed facilitys proximity to any living quarters, including private homes, condominiums, apartments, retirement homes, prisons, dormitories, or other housing; education resources, including preschools and schools operating kindergarten or any of grades 1 to 12, inclusive; day care centers; and health care facilities, including hospitals, nursing homes, and long-term care and hospice facilities. Based on the risk analysis, appropriate setbacks to the listed structure types shall be determined by the commission.
(c)The risk assessment conducted pursuant to this section shall be subjected to peer review by independent experts whose demonstrated expertise includes, but is not limited to, the fields of public health, epidemiology, and toxicology.
(d)The findings of any risk assessment required by this section shall be reported pursuant to Section 911.2.
SEC. 10.Section 1202 of the Public Utilities Code is amended to read:1202.The commission has the exclusive power:
(a)To determine and prescribe the manner, including the particular point of crossing, and the terms of installation, operation, maintenance, use, and protection of each crossing of one railroad by another railroad or street railroad, of a street railroad by a railroad, of each crossing of a public or publicly used road or highway by a railroad or street railroad, and of a street by a railroad or of a railroad by a street.
(b)To alter, relocate, or abolish by physical closing any crossing set forth in subdivision (a).
(c)To require, where in its judgment it would be practicable, a separation of grades at any crossing established and to prescribe the terms upon which the separation shall be made and the proportions in which the expense of the construction, alteration, relocation, or abolition of crossings or the separation of grades shall be divided between the railroad or street railroad corporations affected or between these corporations and the state, county, city, or other political subdivision affected.
(d)To authorize on an application-by-application basis and supervise the operation of pilot projects to evaluate proposed crossing warning devices, new technology, or other additional safety measures at designated crossings, with the consent of the local jurisdiction, the affected railroad, and other interested parties, including, but not limited to, represented railroad employees.
SEC. 11.Section 7937 of the Public Utilities Code is repealed.The commission shall require an electrical or gas corporation to revise a ratepayer-funded energy efficiency program identified pursuant to Section 913.9 as necessary to ensure that the program compliments and does not duplicate a program administered by a state agency.
SEC. 2.Section 421 of the Public Utilities Code is amended to read:421.(a)The commission shall annually determine a fee to be paid by every passenger stage corporation, charter-party carrier of passengers, pipeline corporation, for-hire vessel operator, common carrier vessel operator, railroad corporation, and commercial air operator, and every other common carrier and related business subject to the jurisdiction of the commission, except as otherwise provided in Article 3 (commencing with Section 431) of this chapter and Chapter 6 (commencing with Section 5001) of Division 2.
(b)The annual fee shall be established to produce a total amount equal to the amount established in the authorized commission budget for the same year, including adjustments appropriated by the Legislature and an appropriate reserve, to regulate common carriers and related businesses, less the amount to be paid from special accounts or funds pursuant to Section 403, reimbursements, federal funds, other revenues, and unencumbered funds from the preceding year.
(c)Notwithstanding any other provision of law, the fees paid by railroad corporations shall be used for state-funded railroad investigation and enforcement activities of the commission, other than the rail safety activities funded by the Transportation Planning and Development Account pursuant to Section 99315. The railroad fees shall be set annually at a level which that generates not less than the amount sufficient to fund activities pursuant to Sections 765.5, 916.2, and 7712.
(d)On January 1, 1992, the commission shall submit to the Legislature a detailed budget implementing this section for the 199293 fiscal year. The commission shall also submit to the Legislature by January 1, 1993, and on each January 1 thereafter, a detailed budget for expenditure of railroad corporation fees for the ensuing budget year. The budget for expenditure of railroad corporation fees, for each of the 199697 and 199798 fiscal years, shall not exceed the amount of three million dollars ($3,000,000). Expenditures of this the detailed budget for the expenditure of railroad corporation fees submitted to the Legislature pursuant to Section 916.5 shall be limited to the following items:
(1)Expenditures for employees occupying, and actually performing service in, railroad-safety personnel positions that are directly involved in inspecting railroads and enforcing rail safety regulations. The commission shall expend the funds budgeted pursuant to this subdivision for the salaries, per diem, and travel expenses of employees specified in this paragraph, unless, by statute, the commission is specifically prohibited from expending all or part of those funds.
(2)Expenditures for employees occupying, and actually performing service in, clerical and support staff positions that are directly associated with railroad-safety inspections.
(3)Expenditures for legal personnel who actually pursue violations of rail safety regulations beyond the informal complaint level.
(4)Expenditures for an audit by the California State Auditors Office pursuant to subdivision (f), not to exceed seventy-five thousand dollars ($75,000).(5)(4)Expenditures for the pro rata share of the commissions overhead costs while state personnel are actually occupying the positions, positions and are performing the duties specified in paragraphs (1) to (4), (3), inclusive.
(e)The Department of Finance shall notify the Joint Legislative Budget Committee, pursuant to Section 28.00 of the annual Budget Act, prior to authorizing any change in the Budget Act appropriation for railroad corporation fees that is larger than one hundred thousand dollars ($100,000), or 10 percent of the amount budgeted, whichever is less.
(f)Except as otherwise provided in this subdivision, commencing with the 199394 fiscal year, and in each subsequent fiscal year until the 19992000 fiscal year, the commission shall conduct an audit of the expenditure of the funds received pursuant to this section, except that for the 199697 fiscal year and fiscal years thereafter the audit shall be conducted by the California State Auditors Office. The results of this audit shall be reported, in writing, commencing on or before February 15, 1995, with respect to the audit for the 199394 fiscal year, and on or before January 15 of each year thereafter, with respect to the audit for the fiscal year ending on the previous June 30, to the appropriate policy and budget committees of the respective houses of the Legislature. The commission shall reimburse the California State Auditors Office for the costs of the audits beginning with the 199697 fiscal year.(g)(f)On or before January 1, 1994, the commission shall hire a minimum of four additional operating practices inspectors, exclusive of supervisory personnel, who are, or shall become by July 1, 1994, federally certified, for the purpose of enforcing compliance by railroads operating in this state with state and federal safety regulations.
(h)(g)The commission, in performing its duties, shall limit the expenditure of funds for rail safety purposes to those railroad corporation fees collected pursuant to subdivision (d). In no event, shall the commission fund railroad safety activities utilizing funds from other commission accounts unrelated to railroad safety.
SEC. 3.Section 765.7 of the Public Utilities Code is repealed.765.7.The commission, in conjunction with the California Environmental Protection Agency, shall request, no later than July 1, 1992, the appropriate federal agencies to do all of the following:(a)Investigate and review other chemical compounds not presently considered to be hazardous or toxic for possible reclassification as hazardous substances.(b)Require the use of safer cars in rail transportation of all hazardous materials.(c)Increase the amount of information required on the manifest with regard to any hazardous materials being transported so as to be capable of being understood by personnel involved in emergency, and include information on environmental effects.(d)The commission shall report to the Legislature on the status of its requests no later than September 30, 1992, and every six months thereafter until September 30, 1995.SEC. 4.Section 776 of the Public Utilities Code is amended to read:776.(a)The commission shall, in a single rulemaking or other appropriate proceeding, not to exceed 18 months in duration, consider the need for performance reliability standards and, upon making the determination pursuant to subdivision (c), develop and implement performance reliability standards, standards for all backup power systems installed on the property of residential and small commercial customers by a facilities-based provider of telephony services. Those standards shall do all the following:
(1)Establish minimum operating life.
(2)Establish minimum periods of time during which a telephone system with a charged backup power system will provide the customer with sufficient electricity for emergency usage.
(3)Establish means to warn a customer when the backup power systems charge is low or when the system can no longer hold a charge.
(b)The commission, in developing and implementing any standards in accordance with subdivision (a), shall consider current best practices and technical feasibility for establishing battery backup requirements.
(c)The commission shall not implement standards in accordance with this section unless it determines that the benefits of the standards exceed the costs.
(d)Before January 1, 2008, the commission shall prepare and submit to the Legislature a report on the results of the proceeding.SEC. 5.Section 883 of the Public Utilities Code is amended to read:883.(a)The commission shall, on or before February 1, 2001, issue an order initiating an investigation and opening a proceeding to examine the current and future definitions of universal service. That proceeding shall include public hearings that encourage participation by a broad and diverse range of interests from all areas of the state, including, but not limited to, all of the following:
(1)Consumer groups.
(2)Communication service providers, including all providers of high-speed access services.
(3)Facilities-based telephone providers.
(4)Information service providers and Internet access providers.
(5)Rural and urban users.
(6)Public interest groups.
(7)Representatives of small and large businesses and industry.
(8)Local agencies.
(9)State agencies, including, but not limited to, all of the following:
(A)The Government Operations Agency.
(B)The State Department of Education.
(C)The State Department of Public Health.
(D)The California State Library.
(10)Colleges and universities.
(b)The objectives of the proceeding set forth in subdivision (a) shall include all of the following:
(1)To investigate the feasibility of redefining universal service in light of current trends toward accelerated convergence of voice, video, and data, with an emphasis on the role of basic telecommunications and Internet services in the workplace, in education and workforce training, access to health care, and increased public safety.
(2)To evaluate the extent to which technological changes have reduced the relevance of existing regulatory regimes given their current segmentation based upon technology.
(3)To receive broad-based input from a cross section of interested parties and make recommendations on whether video, data, and Internet service providers should be incorporated into an enhanced Universal Lifeline Service program, as specified, including relevant policy recommendations regarding regulatory and statutory changes and funding options that are consistent with the principles set forth in subdivision (c) of Section 871.7.
(4)To reevaluate prior definitions of basic service in a manner that will, to the extent feasible, effectively incorporate the latest technologies to provide all California residents with all of the following:
(A)Improved quality of life.
(B)Expanded access to public and private resources for education, training, and commerce.
(C)Increased access to public resources enhancing public health and safety.
(D)Assistance in bridging the digital divide through expanded access to new technologies by low income, disabled, or otherwise disadvantaged Californians.
(5)To assess projected costs of providing enhanced universal lifeline service in accordance with the intent of this article, and to delineate the subsidy support needed to maintain the redefined scope of universal service in a competitive market.
(6)To design and recommend an equitable and broad-based subsidy support mechanism for universal service in competitive markets in a manner that conforms with subdivision (c) of Section 871.7.
(7)To develop a process to periodically review and revise the definition of universal service to reflect new technologies and markets consistent with subdivision (c) of Section 871.7.
(8)To consider whether similar regulatory treatment for the provision of similar services is appropriate and feasible.
(c)In conducting its investigation, the commission shall take into account the role played by a number of diverse but convergent industries and providers, even though many of these entities are not subject to economic regulation by the commission or any other government entity.
(d)The recommendations of the commission shall be consistent with state policies for telecommunications as set forth in Section 709, and with all of the following principles:
(1)Universal service shall, to the extent feasible, be provided at affordable prices regardless of linguistic, cultural, ethnic, physical, financial, and geographic considerations.
(2)Consumers shall be provided access to all information needed to allow timely and informed choices about telecommunications products and services that are part of the universal service program and how best to use them.
(3)Education, health care, community, and government institutions shall be positioned as early recipients of new and emerging technologies so as to maximize the economic and social benefits of these services.
(e)The commission shall complete its investigation and report to the Legislature its findings and recommendations on or before January 1, 2002.SECTION 1.SEC. 6.Section 911.2 is added to the Public Utilities Code, to read:911.2.The commission shall report the findings of any risk assessment required by Section 1103 to the Legislature.
SEC. 7.Section 913.9 of the Public Utilities Code is amended to read:913.9.The On or before December 31, 2018, and biennially thereafter, the commission shall identify and report annually on its efforts to identify to the Legislature on electrical and gas corporation ratepayer-funded energy efficiency programs that are similar to programs administered by the Energy Commission, the State Air Resources Board, and the California Alternative Energy and Advanced Transportation Financing Authority in its annual report prepared pursuant to Section 913 and to require revisions to ratepayer-funded programs as necessary to ensure that the ratepayer-funded programs complement and do not duplicate programs of other state agencies. Authority, and on those programs revised pursuant to Section 381.4.
SEC. 8.Section 916.5 is added to the Public Utilities Code, to read:916.5.By January 1 of each year, the commission shall submit to the Legislature a detailed budget for the expenditure of railroad corporation fees for the ensuing budget year, consistent with Section 421.
SEC. 2.SEC. 9.Section 1103 of the Public Utilities Code is amended to read:1103.(a)If a new underground gas storage facility is proposed, the commission shall ensure that a risk assessment evaluating the potential impact of a leak from the facility on public and environmental health, safety, and welfare is conducted by the project proponent. Both acute and chronic exposures from a range of expected emissions and emissions rates shall be evaluated. The evaluation shall include consideration of population density in proximal communities, environmentally sensitive areas, emergency response times, evacuation times, possible leak duration, possible chemical species emitted, and local meteorology.
(b)In evaluating the potential risks and impacts of acute and chronic exposures from emissions from a proposed new gas storage facility, the project proponent shall assess or cause to be assessed risks associated with the proposed facilitys proximity to any living quarters, including private homes, condominiums, apartments, retirement homes, prisons, dormitories, or other housing; education resources, including preschools and schools operating kindergarten or any of grades 1 to 12, inclusive; day care centers; and health care facilities, including hospitals, nursing homes, and long-term care and hospice facilities. Based on the risk analysis, appropriate setbacks to the listed structure types shall be determined by the commission.
(c)The risk assessment conducted pursuant to this section shall be subjected to peer review by independent experts whose demonstrated expertise includes, but is not limited to, the fields of public health, epidemiology, and toxicology.
(d)The findings of any risk assessment required by this section shall be reported pursuant to Section 911.2.
SEC. 10.Section 1202 of the Public Utilities Code is amended to read:1202.The commission has the exclusive power:
(a)To determine and prescribe the manner, including the particular point of crossing, and the terms of installation, operation, maintenance, use, and protection of each crossing of one railroad by another railroad or street railroad, and of a street railroad by a railroad, and of each crossing of a public or publicly used road or highway by a railroad or street railroad, and of a street by a railroad or of a railroad by a street.
(b)To alter, relocate, or abolish by physical closing any crossing set forth in subdivision (a).
(c)To require, where in its judgment it would be practicable, a separation of grades at any crossing established and to prescribe the terms upon which the separation shall be made and the proportions in which the expense of the construction, alteration, relocation, or abolition of crossings or the separation of grades shall be divided between the railroad or street railroad corporations affected or between these corporations and the state, county, city, or other political subdivision affected.
(d)(1)To authorize on an application-by-application basis and supervise the operation of pilot projects to evaluate proposed crossing warning devices, new technology, or other additional safety measures at designated crossings, with the consent of the local jurisdiction, the affected railroad, and other interested parties, including, but not limited to, represented railroad employees.
(2)The Legislature finds and declares that for the communities of the state that are traversed by railroads, there is a growing need to mitigate train horn noise without compromising the safety of the public. Therefore, it is the intent of the Legislature that the commission may authorize the following pilot projects, after an application is filed and approved by the commission:(A)To test the utility and safety of stationary, automated audible warning devices as an alternative to trains having to sound their horns as they approach highway-rail crossings in the communities of Roseville, Fremont, Newark, and Lathrop, and in any other location determined to be suitable by the commission.(B)To authorize supplementary safety measures, as defined in Section 20153 (a)(3) of Title 49 of the United States Code, for use on rail crossings.No new pilot project may be authorized after January 1, 2003. The commission shall report to the Legislature by March 31, 2004, on the outcome of this pilot project.(3)In light of the pending proposed ruling by the Federal Railroad Administration on the use of locomotive horns at all highway-rail crossings across the nation, it would be in the best interest of the state for the commission to expedite the pilot projects authorized under paragraph (2) in order to contribute data to the federal rulemaking process regarding the possible inclusion of stationary, automated warning devices as a safety measure option to the proposed federal rule.SEC. 11.Section 7937 of the Public Utilities Code is repealed.7937.(a)On or before March 1, 2000, the commission shall request from each telephone corporation doing business in this state that possesses one or more telephone number prefixes, or a portion thereof, the specific telephone numbers and the quantities within the possession of the provider, both in use and not in use. The commission, for the purpose of this section, shall define the terms in use and not in use. The commission shall determine the reporting requirements for the information provided to the commission pursuant to Section 7940.(b)Notwithstanding Section 7550.5 of the Government Code, the commission shall use the information obtained pursuant to subdivision (a) and any other information required by the commission, to prepare and submit to the Legislature, on or before, July 1, 2001, a study of telecommunications industry use rates.The commission shall report the findings of any risk assessment required by Section 1103 to the Legislature.
SEC. 2.Section 1103 of the Public Utilities Code is amended to read:1103.(a)If a new underground gas storage facility is proposed, the commission shall ensure that a risk assessment evaluating the potential impact of a leak from the facility on public and environmental health, safety, and welfare is conducted by the project proponent. Both acute and chronic exposures from a range of expected emissions and emissions rates shall be evaluated. The evaluation shall include consideration of population density in proximal communities, environmentally sensitive areas, emergency response times, evacuation times, possible leak duration, possible chemical species emitted, and local meteorology.
(b)In evaluating the potential risks and impacts of acute and chronic exposures from emissions from a proposed new gas storage facility, the project proponent shall assess or cause to be assessed risks associated with the proposed facilitys proximity to any living quarters, including private homes, condominiums, apartments, retirement homes, prisons, dormitories, or other housing; education resources, including preschools and schools operating kindergarten or any of grades 1 to 12, inclusive; day care centers; and health care facilities, including hospitals, nursing homes, and long-term care and hospice facilities. Based on the risk analysis, appropriate setbacks to the listed structure types shall be determined by the commission.
(c)The risk assessment conducted pursuant to this section shall be subjected to peer review by independent experts whose demonstrated expertise includes, but is not limited to, the fields of public health, epidemiology, and toxicology.
(d)The findings of any risk assessment required by this section shall be reported to the Legislature in accordance with Section 9795 of the Government Code. pursuant to Section 911.2.
|
Date
|
Status
|
|---|---|
| Oct 2, 2017 | Chaptered by Secretary of State. Chapter 425, Statutes of 2017. |
| Oct 2, 2017 | Approved by the Governor. |
| Sep 21, 2017 | Enrolled and presented to the Governor at 5:30 p.m. |
| Sep 14, 2017 | Assembly amendments concurred in. (Ayes 39. Noes 0.) Ordered to engrossing and enrolling. |
| Sep 12, 2017 | Ordered to special consent calendar. |
| Sep 11, 2017 | In Senate. Concurrence in Assembly amendments pending. |
| Sep 11, 2017 | Read third time. Passed. Ordered to the Senate. |
| Sep 8, 2017 | Read third time and amended. |
| Sep 1, 2017 | From consent calendar on motion of Assembly Member Calderon. |
| Aug 31, 2017 | Read second time. Ordered to consent calendar. |
| Aug 30, 2017 | From committee: Do pass. Ordered to consent calendar. (Ayes 15. Noes 0.) (August 30). |
| Jul 19, 2017 | Read second time and amended. Re-referred to Com. on APPR. |
| Jul 18, 2017 | From committee: Do pass as amended and re-refer to Com. on APPR. (Ayes 15. Noes 0.) (July 12). |
| Jul 5, 2017 | July 5 hearing postponed by committee. |
| Jun 28, 2017 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on U. & E. |
| Jun 21, 2017 | June 21 hearing postponed by committee. |
| Jun 8, 2017 | Referred to Com. on U. & E. |
| May 31, 2017 | In Assembly. Read first time. Held at Desk. |
| May 30, 2017 | Read third time. Passed. (Ayes 40. Noes 0. Page 1271.) Ordered to the Assembly. |
| May 26, 2017 | Read second time. Ordered to third reading. |
| May 25, 2017 | Read third time and amended. |
| May 2, 2017 | Read second time. Ordered to third reading. |
| May 1, 2017 | From committee: Be ordered to second reading pursuant to Senate Rule 28.8. |
| Apr 21, 2017 | Set for hearing May 1. |
| Apr 18, 2017 | From committee: Do pass and re-refer to Com. on APPR. (Ayes 11. Noes 0. Page 727.) (April 18). Re-referred to Com. on APPR. |
| Apr 7, 2017 | Set for hearing April 18. |
| Apr 6, 2017 | Re-referred to Com. on E., U. & C. |
| Apr 3, 2017 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on RLS. |
| Feb 23, 2017 | Referred to Com. on RLS. |
| Feb 15, 2017 | From printer. May be acted upon on or after March 17. |
| Feb 14, 2017 | Introduced. Read first time. To Com. on RLS. for assignment. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Sep 14, 2017 | Special Consent Calendar SB385 | Senate Floor |
Passed |
|
| Sep 11, 2017 | SB 385 Hueso Senate Third Reading By HOLDEN | Assembly Floor |
Passed |
|
| Aug 30, 2017 | Do pass. To Consent Calendar. | Assembly Standing Committee on Appropriations |
Passed |
|
| Jul 12, 2017 | Do pass as amended and be re-referred to the Committee on [Appropriations] | Assembly Standing Committee on Utilities and Energy |
Passed |
|
| May 30, 2017 | Senate 3rd Reading SB385 Hueso | Senate Floor |
Passed |
|
| Apr 18, 2017 | Do pass, but first be re-referred to the Committee on [Appropriations] | Senate Standing Committee on Energy, Utilities and Communications |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| California Public Utilities Commission | ** Support | Sep 12, 2017 |
Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB |
UNFINISHED BUSINESS
Bill No: SB 385
Amended: 9/8/17
SENATE ENERGY, U. & C. COMMITTEE: 11-0, 4/18/17
AYES: Hueso, Morrell, Bradford, Cannella, Hertzberg, Hill, McGuire, Skinner, Stern, Vidak, Wiener
SENATE APPROPRIATIONS COMMITTEE: Senate Rule 28.8
SENATE FLOOR: 40-0, 5/30/17
AYES: Allen, Anderson, Atkins, Bates, Beall, Berryhill, Bradford, Cannella, De León, Dodd, Fuller, Gaines, Galgiani, Glazer, Hernandez, Hertzberg, Hill, Hueso, Jackson, Lara, Leyva, McGuire, Mendoza, Mitchell, Monning, Moorlach, Morrell, Newman, Nguyen, Nielsen, Pan, Portantino, Roth, Skinner, Stern, Stone, Vidak, Wieckowski, Wiener, Wilk
ASSEMBLY FLOOR: 78-0, 9/11/17 - See last page for vote
SUBJECT: Public Utilities Commission: reports: programs: studies: ex parte communications
SOURCE: California Public Utilities Commission
DIGEST:
This bill provides technical clean-up of the Public Utilities Code, including modifying and clarifying existing statutes and repealing obsolete provisions.
Assembly Amendments repeal and modify requirements related to public meetings for proposed area code changes, clarify quiet periods during which the California Public Utilities Commission (CPUC) may meet in closed session, and include other technical clean-up amendments.
Existing law:
- Requires the CPUC to submit to the Legislature a detailed budget implementing transportation services related fees for the 1992-93 fiscal year. Requires the budget for expenditure of railroad corporation fees, for each of the 1996-97 and 1997-98 fiscal years, not to exceed the amount of $3 million. Requires the CPUC to conduct an audit of the expenditure of funds, commencing with the 1993-94 fiscal year, and in each subsequent fiscal year until the 1999-2000 fiscal year. Requires expenditures for an audit by the California State Auditor’s Office not to exceed $75,000. (Public Utilities Code §421)
- Requires the CPUC, in conjunction with the California Environmental Protection Agency, to request, no later than July 1, 1992, the federal agencies to investigate and review other chemical compounds not presently considered to be hazardous or toxic for possible reclassification as hazardous substances, require the use of safer cars in rail transportation of all hazardous material, and other requests. Requires the CPUC to report to the Legislature on the status of its request no later than September 30, 1992, and every six months thereafter until September 30, 1995. (Public Utilities Code §765.7)
- Requires the CPUC to, in a proceeding, not to exceed 18 months in duration, consider the need for performance reliability standards for all backup power systems installed on the property of residential and small commercial customers by a facilities-based provider of telephony services. Requires the CPUC to prepare and submit a report on the results of the proceeding before January 1, 2008. (Public Utilities Code §776)
- Requires the CPUC to complete its investigation and report regarding recommendations from its examination of the current and future definitions of universal service on or before January 1, 2002. (Public Utilities Code §883)
- Requires the CPUC to report annually on its efforts to identify ratepayer-funded energy efficiency programs that are similar to programs administered by the California Energy Commission, the State Air Resources Board, and the California Alternative Energy and Advanced Transportation Financing Authority in its annual report and to require revisions of ratepayer funded programs as necessary. (Public Utilities Code §913.9)
- Requires the CPUC to report to the Legislature the findings of any risk assessment for a proposed new underground gas storage facility. (Public Utilities Code §1103)
- Declares the intent of the Legislature that the CPUC authorize pilot projects to test the utility and safety of stationary, automated audible warning devices as an alternative to trains having to sound their horns as they approach highway rail crossings in specified communities. Prohibits new pilot projects from being authorized after January 1, 2003. Requires the CPUC to report to the Legislature by March 31, 2004, on the outcome of the pilot project. (Public Utilities Code §1202)
- Requires the CPUC, on or before March 1, 2009, to request from each telephone corporation doing business in this state that possesses one or more telephone number prefixes, the specific telephone numbers and quantities within the possession of the provider, both in use and not in use. Requires the CPUC to submit a report to the Legislature on or before, July 1, 2001, on a study of telecommunications industry use rates. (Public Utilities Code §7937)
This bill:
- Repeals several outdated provisions of the current statutes related to the CPUC, including requirements of the CPUC to:
- Conduct an audit, or have the State Auditor conduct an audit, of the expenditures of specified funds commencing with the 1993-94 fiscal year and in each subsequent year until the 1999-2000 fiscal year.
- In conjunction with the California Environmental Protection Agency, request no later than July 1, 1992, the appropriate federal agencies to take specified actions relating to hazardous substances and materials, and related status reports to the Legislature every six months beginning September 30, 1992, until September 30, 1995.
- Prepare and submit a report, before January 1, 2008, to the Legislature regarding performance reliability standards adopted for all backup commercial customers installed by a facilities-based provider of telephony services.
- Report to the Legislature its findings and recommendations, on or before January 1, 2002, related to examining the current and future definitions of universal service.
- Authorize specified pilot programs relating to rail crossings prior to January 1, 2003, and requirements to report to the Legislature by March 31, 2004, on the outcome of those pilot programs.
- Prepare and submit to the Legislature, on or before, July 1, 2001, a study of telecommunications industry use rates.
- Repeals a requirement that the CPUC conduct at least three public meetings in the affected geographical area where an area code change is proposed.
- Moves, to the part of the Public Utilities Code that lists all required reports, provisions of the statutes requiring reports to be submitted by the CPUC to the Legislature, including:
- The findings of any risk assessment completed to evaluate the potential impact of a leak from a proposed new underground gas storage facility.
- A detailed budget for the expenditure of railroad corporation fees for the ensuing budget year.
- Clarifies that an existing required report of the CPUC to the Legislature regarding energy efficiency programs applies to those programs of the investor-owned utilities and requires that information is included biennially in the Section 913 Electricity and Gas Utility Costs report beginning December 31, 2018.
- Clarifies the CPUC’s existing authority to establish periods where no ex parte communications can take place in advance of a decision by the CPUC and the commissioners are allowed to meet in closed session, but requires a minimum of three day’s advance public notice of the closed session meetings.
- Provides the CPUC with discretion to conduct one or more public meetings in affected geographic areas to inform the public of proposed area code changes and relief options.
Background
This bill is a clean-up of the codes that is an annual effort by the Legislature to help maintain consistency, relevance and accuracy of the Public Utilities Code statutes.
Current law makes several requirements of the CPUC related to reports that must be submitted to the Legislature. In many instances, these reports are required for specified time periods. However, the language requiring these reports is maintained in the statutes even after the provisions have become obsolete.
In recent years, there has been an effort to maintain all reports of the CPUC to the Legislature in one section of the Public Utilities Code, so as to better track report requirements. However, bills often get adopted without ensuring any required reports to the Legislature by the CPUC are appropriately placed in the codes.
This bill appropriately clarifies that the requirement of the CPUC to track existing energy efficiency programs and ensure minimal duplication with similar state programs is narrow to the CPUC’s oversight of investor-owned energy utilities and included every two years in an existing annual report.
This bill also provides the CPUC with discretion to conduct meetings in affected geographic areas to inform the public of proposed area code changes and relief options. Currently, the CPUC is required to conduct at least three public meetings in a geographic area that will be affected by an area code change. However, with the increasing volume of phone numbers and the increasing regularity of changes to area codes, the CPUC has noted that the public meetings have not been well-attended. As such, a requirement for three meeting results in unnecessary costs, including CPUC staff time and resources. The bill appropriately still requires notification to the public and local representatives, but provides discretion as to the number of public meetings.
FISCAL EFFECT: Appropriation: Fiscal Com.: Local: Yes
According to the Assembly Appropriations Committee, this bill incurs no additional state costs.
California Public Utilities Commission (source)
OPPOSITION: (Verified 9/11/17)
None received
ASSEMBLY FLOOR: 78-0, 9/11/17
AYES: Acosta, Aguiar-Curry, Travis Allen, Arambula, Baker, Berman, Bigelow, Bloom, Bocanegra, Bonta, Burke, Caballero, Calderon, Cervantes, Chau, Chávez, Chen, Chiu, Choi, Chu, Cooley, Cooper, Cunningham, Dababneh, Dahle, Daly, Eggman, Flora, Fong, Frazier, Friedman, Gallagher, Cristina Garcia, Eduardo Garcia, Gipson, Gloria, Gonzalez Fletcher, Gray, Grayson, Harper, Holden, Irwin, Jones-Sawyer, Kalra, Kiley, Lackey, Levine, Limón, Low, Maienschein, Mathis, Mayes, McCarty, Medina, Melendez, Mullin, Muratsuchi, Nazarian, Obernolte, O'Donnell, Patterson, Quirk, Quirk-Silva, Reyes, Ridley-Thomas, Rodriguez, Rubio, Salas, Santiago, Steinorth, Mark Stone, Thurmond, Ting, Voepel, Waldron, Weber, Wood, Rendon
NO VOTE RECORDED: Brough
9/12/17 9:53:58
**** END ****
SENATE THIRD READING
STR Bill Id:SB 385
Author:(Hueso)
As Amended Ver:September 8, 2017
Majority vote
SENATE VOTE: 40-0
Committee | Votes | Ayes | Noes |
Utilities | 15-0 | Holden, Patterson, Burke, Chávez, Chen, Dahle, Rodriguez, Fong, Cristina Garcia, Eduardo Garcia, Muratsuchi, Quirk, Reyes, Santiago, Ting |
|
Appropriations | 15-0 | Gonzalez Fletcher, Bigelow, Bloom, Bocanegra, Bonta, Calderon, Chau, Eggman, Fong, Friedman, Gallagher, Gray, Jones-Sawyer, Obernolte, Reyes |
|
SUMMARY: Modifies California Public Utilities Commission (CPUC) hearing and ex parte rules and makes various technical changes. Specifically, this bill:
- Names the period of time following issuance of proposed CPUC decisions or orders in ratesetting cases as "quiet periods," during which time ex parte communications are not permitted but closed sessions are allowed;
- Clarifies that an existing required report of the CPUC to the Legislature regarding energy efficiency programs applies to those programs of the investor-owned utilities and requires the report is submitted biennially beginning December 31, 2018.
- Eliminates mandatory public meetings in regions identified for area code changes; and
- Makes a number of technical changes, including centralizing CPUC reporting requirements, striking expired timelines, and deleting outdated provisions.
FISCAL EFFECT: According to the Assembly Appropriations Committee, this measure incurs no additional state costs.
COMMENTS:
- Purpose. This bill, sponsored by the CPUC, is an annual effort to help maintain consistency, relevance, and accuracy of the Public Utilities Code.
- Background. In recent years, there has been an effort by the CPUC to sponsor legislation to make technical changes to the code; this bill is a continuation of such effort. Most of the changes to code proposed by this bill are technical, such as moving reports to new code sections, striking outdated provisions, and making minor changes to programs and reporting.
Analysis Prepared by: Laura McWilliams / U. & E. / (916) 319-2083 FN: 0002158
SENATE THIRD READING
STR Bill Id:SB 385
Author:(Hueso)
As Amended Ver:July 19, 2017
Majority vote
SENATE VOTE: 40-0
Committee | Votes | Ayes | Noes |
Utilities | 15-0 | Holden, Patterson, Burke, Chávez, Chen, Dahle, Rodriguez, Fong, Cristina Garcia, Eduardo Garcia, Muratsuchi, Quirk, Reyes, Santiago, Ting | |
Appropriations | 15-0 | Gonzalez Fletcher, Bigelow, Bloom, Bocanegra, Bonta, Calderon, Chau, Eggman, Fong, Friedman, Gallagher, Gray, Jones-Sawyer, Obernolte, Reyes |
SUMMARY: Modifies California Public Utilities Commission (CPUC) hearing and ex parte rules and makes various technical changes. Specifically, this bill:
- Excludes open sessions of conferences and other public meetings from the definition of one-way communications and exempts comments made in open sessions of conferences from ex parte requirements;
- Permits ex parte notices to be filed in a centralized log rather than in each applicable proceeding;
- Names the period of time following issuance of proposed CPUC decisions or orders in ratesetting cases as "quiet periods," during which time ex parte communications are not permitted but closed sessions are allowed;
- Modifies the timeline for the CPUC to seek participation from affected parties to a proceeding to be immediately after determining the scope of the proceeding;
- Eliminates mandatory public meetings in regions identified for area code changes; and
- Makes a number of technical changes, including centralizing CPUC reporting requirements, striking expired timelines, and deleting outdated provisions.
FISCAL EFFECT: According to the Assembly Appropriations Committee, this measure incurs no additional state costs.
COMMENTS:
- Purpose. This bill, sponsored by the CPUC, is framed as an annual effort to help maintain consistency, relevance, and accuracy of the Public Utilities Code, but additionally modifies ex parte and open meeting rules adopted in recent years under a suite of CPUC reform bills that include SB 215 (Leno), Chapter 807, Statutes of 2016 and SB 512 (Hill) Chapter 808, Statutes of 2016.
- Background. In recent years, there has been an effort by the CPUC to sponsor legislation to make technical changes to the code; this bill is a continuation of such effort. Most of the changes to code proposed by this bill are technical – moving reports to new code sections, striking outdated provisions – but some make substantive changes to ex parte communication and open meeting rules.
Following a number of controversies, the law firm Strumwasser & Woocher was hired by the CPUC to provide independent counsel on ex parte rules and practices. In June of 2015, the firm issued a comprehensive report assessing the current laws and practices governing ex parte communications and comparing those to CPUC ex parte rules. The report outlined 28 recommended changes for the CPUC and Legislature to consider. As a result of this report and the preceding CPUC controversies, a suite of CPUC reform bills were passed by the Legislature in 2015 and 2016. Among them, SB 215 (Leno), Chapter 807, Statutes of 2016, provided a number of changes regarding CPUC hearings and ex parte rules. This bill modifies some of the ex parte provisions from SB 215.
Analysis Prepared by: Laura McWilliams / U. & E. / (916) 319-2083 FN: 0001635
Date of Hearing: August 30, 2017
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Lorena Gonzalez Fletcher, Chair
SBPCA Bill Id:SB 385
Author:(Hueso) – As Amended Ver:July 19, 2017
Policy Committee: | Utilities and Energy | Vote: | 15 - 0 |
|
| ||
|
|
Urgency: No State Mandated Local Program: Yes Reimbursable: No
SUMMARY:
This bill modifies the California Public Utilities Commission (PUC) hearing and ex parte rules and makes various technical changes by centralizing reporting requirements and deleting outdated timelines and other provisions. Specifically, this bill:
- Excludes open sessions of conferences and other public meetings from the definition of one-way communications, and exempts comments made in open sessions of conferences from ex parte requirements;
- Permits ex parte notices to be filed in a centralized log rather than in each applicable proceeding;
- Names the period of time following issuance of proposed PUC decisions or orders in ratesetting cases as “quiet periods,” during which time ex parte communications are not permitted but closed sessions are allowed; and
- Modifies the timeline for the PUC to seek participation from affected parties to a proceeding to be immediately after determining the scope of the proceeding.
- Provides discretion, rather than requires the PUC to conduct meetings in the geographic areas for which an area code change is proposed, as specified.
FISCAL EFFECT:
No additional state costs.
COMMENTS:
Background and Purpose. This bill, sponsored by the PUC, is an annual effort to help maintain consistency, relevance, and accuracy of the Public Utilities Code.
Current law makes several requirements of the PUC related to reports that must be submitted to the Legislature. In many instances, these reports are required for specified time periods, however, the language requiring these reports is kept in the code even after the provisions have become obsolete.
In recent years, there has been an effort to maintain all reports of the CPUC to the Legislature in one section of the Public Utilities Code, so as to better track report requirements. However, bills often get adopted without ensuring any required reports to the Legislature by the PUC are appropriately placed in the codes. This bill provides the necessary changes.
This bill also clarifies the requirement of the PUC to track existing energy efficiency programs and ensure minimal duplication with similar state programs.
Following a number of controversies, the law firm Strumwasser & Woocher was hired by the PUC to provide independent counsel on ex parte rules and practices. In June of 2015, the firm issued a comprehensive report assessing the current laws and practices governing ex parte communications and comparing those to PUC ex parte rules. The report outlined 28 recommended changes for the PUC and Legislature to consider. As a result of this report and the preceding PUC controversies, a suite of PUC reform bills were passed by the Legislature in 2015 and 2016. Among them, SB 215 (Leno, Hueso), Chapter 807, Statutes of 2016, provided a number of changes regarding PUC hearings and ex parte rules. This bill modifies some of the ex parte provisions from SB 215.
Analysis Prepared by: Jennifer Galehouse / APPR. / (916) 319-2081
Date of Hearing: July 12, 2017
ASSEMBLY COMMITTEE ON UTILITIES AND ENERGY
Chris Holden, Chair
SBPCA Bill Id:SB 385
Author:(Hueso) – As Amendedune Ver:June 28, 2017
SENATE VOTE: 40-0
SUBJECT: Public Utilities Commission: reports: programs: studies: ex parte communications
SUMMARY: Modifies California Public Utilities Commission (CPUC) hearing and ex parte rules both technically and substantively. Additionally, makes technical changes by centralizing CPUC reporting requirements, striking expired timelines, and deleting outdated provisions. Specific to CPUC hearings and ex parte, this bill:
- Makes prehearing conferences and scoping memos for uncontested adjudication proceedings, and scoping memos for uncontested quasi-legislative proceedings discretionary;
- Excludes open sessions of conferences and other public meetings from the definition of one-way communications, and exempts comments made in open sessions of conferences from ex parte requirements;
- Permits ex parte notices to be filed in a centralized log rather than in each applicable proceeding;
- Exempts from open meeting requirements discussions of state legislative proposals;
- Names the period of time following issuance of proposed CPUC decisions or orders in ratesetting cases as “quiet periods,” during which time no ex parte communications are permitted but closed sessions are allowed; and
- Modifies the timeline for the CPUC to seek participation from affected parties to a proceeding to be prior to the CPUC’s request for final briefs by the parties. Additionally, requires the CPUC to demonstrate its efforts to comply with this outreach in the proposed decision rather than the scoping memo.
EXISTING LAW:
- Requires the CPUC to report annually on its efforts to identify ratepayer-funded energy efficiency programs that are similar to programs administered by the California Energy Commission (CEC), the California Air Resources Board (CARB), and the California Alternative Energy and Advanced Transportation Financing Authority (CAEATFA) in its annual report and to revise ratepayer funded programs as necessary. (Public Utilities Code § 913.9)
- Requires the CPUC to submit to the Legislature a detailed budget implementing transportation service related fees for the 1992-93 fiscal year. Requires the budget for expenditure of railroad corporation fees, for each of the 1996-97 and 1997-98 fiscal years, not exceed the amount of three million dollars. Requires the CPUC to conduct an audit of the expenditure of funds, commencing with the 1993-94 fiscal year, and in each subsequent fiscal year until the 1999-2000 fiscal year. Requires expenditures for an audit by the California State Auditor’s Office does not exceed seventy-five thousand. (Public Utilities Code § 421)
- Requires the CPUC, in conjunction with the California Environmental Protection Agency, to request, no later than July 1, 1992, the federal agencies to investigate and review other chemical compounds not presently considered to be hazardous or toxic for possible reclassification as hazardous substances, require the use of safer cars in rail transportation of all hazardous material, and other requests. Requires the CPUC to report to the Legislature on the status of its request no later than September 30, 1992, and every six months thereafter until September 30, 1995. (Public Utilities Code § 765.7)
- Requires the CPUC to complete its investigation and report regarding recommendations from its examination of the current and future definitions of universal service on or before January 1, 2002. (Public Utilities Code § 883)
- Declares the intent of the Legislature that the CPUC authorize pilot projects to test the utility and safety of stationary, automated audible warning devices as an alternative to trains having to sound their horns as they approach highway rail crossings in specified communities. Prohibits new pilot projects from being authorized after January 1, 2003. Requires the CPUC to report to the Legislature by March 31, 2004, on the outcome of the pilot project. (Public Utilities Code § 1202)
- Requires the CPUC, on or before March 1, 2009, to request from each telephone corporation doing business in this state that possesses one or more telephone number prefixes, the specific telephone numbers and quantities within the possession of the provider, both in use and not in use. Requires the CPUC to submit a report to the Legislature on or before, July 1, 2001, on a study of telecommunications industry use rates. (Public Utilities Code § 7937)
- Requires the CPUC to, in a proceeding not to exceed 18 months in duration, consider the need for performance reliability standards for all backup power systems installed on the property of residential and small commercial customers by a facilities-based provider of telephony services. Requires the CPUC to prepare and submit a report on the results of the proceeding before January 1, 2008. (Public Utilities Code § 776)
- Requires the CPUC to report to the Legislature the findings of any risk assessment for a proposed new underground gas storage facility. (Public Utilities Code § 1103)
- Mandates the CPUC to conduct at least one meeting for representatives of local jurisdictions and at least three public meetings in the affected geographical area prior to adopting new telephone area codes. (Public Utilities Code § 7931[e][2])
- Requires the CPUC to determine the nature of a proceeding, specifically whether it is quasi-legislative, ratesetting, or adjudicatory and establishes definitions and rules related to each. Further, directs the CPUC to adopt rules to define decisionmakers and persons of interests for purposes of applying ex parte communication rules. (Public Utilities Code § 1701 et seq.)
- Provides rules governing each type of proceeding including prohibiting ex parte communication in adjudication cases, except communication with the assigned administrative law judge concerning procedural matters. (Public Utilities Code § 1701.2)
- Prohibits ex parte communication in ratesetting cases, but permits oral ex parte communication if (1) all-parties are invited with no less than three day notice (2) written ex parte communication provided copies are transmitted to all parties, and (3) when an ex parte meeting is granted to a party, all other parties are also granted individual ex parte for an equal duration of time. (Public Utilities Code § 1701.3)
- Permits the CPUC to establish a period of time following issuance of proposed decisions or orders in ratesetting cases during which no ex parte communication may be permitted but the CPUC may meet in closed session. These periods must be 14 days or less. Additionally, allows for a short time period of ex parte communication if the decision is held. (Public Utilities Code § 1701.3[h][6])
- Permits without restriction ex parte communication in quasi-legislative cases, unless the CPUC commissioners, by rule or order, determine otherwise. (Public Utilities Code § 1701.4)
- Mandates the CPUC to seek the participation of any affected parties to a case before the initial scoping memo of the proceeding is determined, except in adjudication cases. Further mandates the CPUC to study outreach efforts of other state and federal utility regulatory bodies, but sunsets the outreach requirement by January 1, 2020. (Public Utilities Code § 1711)
- Mandates rules by which public agencies, boards, and commissions must operate and deliberate in a publicly accessible manner, known as the Bagley-Keene Open Meeting Act. (Government Code §§ 11120-111321)
FISCAL EFFECT: This bill is keyed fiscal and will be referred to the Assembly Committee on Appropriations for its review.
BACKGROUND:
The Bagley-Keene Open Meeting Act – The Bagley-Keene Act, in Government Code §§ 11120-111321, applies to all state boards and commissions, including the CPUC. Generally, it requires these bodies to publicly notice meetings, prepare agendas, accept public testimony, and conduct meetings in public unless specifically authorized by Bagley-Keene to meet in closed session. The Bagley-Keene Act, in effect reserves a seat at the table for the public during convening of a public body.[1] By reserving this seat, statute provides the public with the ability to monitor and participate in the decision-making process, absent a specific reason to exclude public participation.
The issue of what constitutes a meeting is one of the more thorny and controversial issues under Bagley-Keene. A meeting occurs when a quorum of a body convenes, either serially or all together, to address issues under the body’s jurisdiction.[2] A meeting would clearly include a gathering where a quorum of members were debating issues or voting on them. But a meeting also includes situations where information is shared. This becomes complicated in the context of informal gatherings such as presentations, conferences, or briefings. State law permits closed sessions in very limited circumstances, which must be listed on the meeting agenda and properly noticed,[3] among other requirements.[4] For the CPUC, the Legislature has explicitly excluded – in the Public Utilities Code – closed sessions to deliberate adjudicatory and ratesetting cases[5] and administrative matters[6] from Bagley-Keene rules.
Ex Parte Communications – Substantive communication outside of the public record that occurs between a decisionmaker and a party with an interest in a CPUC proceeding are known as “ex parte” communications. Limits to ex parte communications depend on the content of what is being discussed, with some discussions strictly prohibited while others require disclosure. Current law directs the CPUC to adopt regulations that require reporting of ex parte communications. The regulations require reporting – by both the party and the decisionmaker – to include:
- The date, time, location, and medium of the communication, and whether it was oral, written, or a combination.
- The identity of the recipient and the person initiating the communication, as well as the identity of any persons present during the communication.
- The topic, including applicable proceeding numbers.
- Substantive descriptions of the party’s communication and its content; or brief descriptions of the decisionmaker’s communication.
- Copies of any written material or text.
Statute directs the CPUC to identify each of its proceedings according to one of three categories – adjudicatory, quasi-legislative, and ratesetting – and provides ex parte rules applicable to each type of proceeding, as follows:
- Adjudication cases – enforcement cases and complaints, except those challenging the reasonableness of rates or charges. Statute expressly prohibits ex parte communication.
- Quasi-legislative cases – those that establish policy, including, but not limited to, rulemakings and investigations which may establish rules affecting an entire industry. Statute allows for ex parte communication.
- Ratesetting cases – cases in which rates are established for a specific company. Statute expressly prohibits ex parte communication related to ratesetting cases, but also provides circumstances in which ex parte communication is permitted and procedures for reporting and managing such communication.
Evolving Ex Parte at the CPUC – Following a number of controversies, the law firm Strumwasser & Woocher was hired by the CPUC to provide independent counsel on ex parte rules and practices. In June of 2015, the firm issued a comprehensive report assessing the current laws and practices governing ex parte communications and comparing those to CPUC ex parte rules.[7] In the report, the firm noted: “It is clear that ex parte communications are a frequent, pervasive, and at least sometimes outcome-determinative in CPUC ratesetting cases. In general, these practices have the unavoidable effect of moving actual governmental decision-making out of the public eye. And we found that these practices are fundamentally unfair to the parties…” Additionally, the report outlined 28 recommended changes for the CPUC and Legislature to consider. As a result of this report and the preceding CPUC controversies, a suite of CPUC reform bills were passed by the Legislature in 2015 and 2016. Among them, SB 215 (Leno, Hueso, Chapter 807, Statutes of 2016) mandated a number of changes regarding CPUC hearings and ex parte rules. This bill modifies some of the provisions from SB 215; the differences are outlined in Table 1 below.
Table 1
Ex Parte Recommendations or Changes | ||
2015 Strumwasser & Woocher Report Recommendations | 2016 SB 215 | Current Bill |
“Substantive ex parte communications should not be permitted in CPUC adjudications and ratesetting proceedings” | Adjudication ex parte already prohibited under statutes; Ratesetting ex parte not addressed. | Permits adjudication and ratesetting discussions during open sessions of conferences. |
“When ex parte meetings are permitted, responsibility for reporting the substance of the meeting should rest with the decision-maker, who should be required to fully report what was said.” | Adopted proposed changes | Modifies statute to have reporting be in a public log |
“Written communications with Commissioners, with their advisors, and with the full Commission should be placed in the proceeding record.” | Adopted proposed changes | Modifies statute to have reporting be in a public log |
“Decision-makers should avoid attending industry-sponsored conferences where issues presented in pending adjudicatory or ratesetting proceedings are expected…” | Prohibited ex parte communications at conferences involving adjudication or ratesetting | Permits during “open session” of conferences (i.e. a speech) |
COMMENTS:
- Author’s Statement. This is an annual effort by the Legislature to help maintain consistency, relevance, and accuracy of the Public Utilities Code statutes.
- Annual CPUC effort. The author states that this bill is one in a series of annual bills sponsored by the CPUC to tidy the Public Utilities Code. Indeed, almost every year the CPUC sponsors legislation to make technical changes to the code; last year it was SB 1222 (Hertzberg, Chapter 842, Statutes of 2016). Most of the changes to code proposed by this bill are technical—moving reports to new code sections, striking outdated provisions—but some make substantive changes that require further examination.
The CPUC has been making a concerted effort to centralize the location in statute of all the reports it is mandated to prepare for the Legislature in order to better track them.[8] However, parts of the code still remain that have yet to be consolidated. This bill corrects a few of these misplaced reports by striking three from their previous sections and moving them to the appropriate article.
- Energy Efficiency Programs Every Two Years? The CPUC is mandated to report annually on its efforts to “identify ratepayer-funded energy efficiency programs” that duplicate programs at the CEC, CARB, and CAEATFA.[9] This bill changes this reporting requirement from every year to every two years, and specifies the energy efficiency programs are only those of “electrical and gas corporations.” The CPUC views the annual requirement for these reports as excessive, and states that only a small number of duplicative programs may exist, negating the need for such annual reports. The CPUC suggests moving the report to every two years instead of annually in order to better use CPUC resources. However, the original report mandated by the Legislature to be updated annually has yet to be delivered. As a result, determining the scope or the necessity of changing the reporting timeline is difficult and seemingly premature.
- Train Horn Rules. This bill strikes a provision in the CPUC’s authority to prescribe the manner and safety of railroad crossings in three pilot projects testing stationary horns – also known as “automated audible warning devices” – in lieu of train horns. These pilots were created in order to contribute data to a federal rulemaking regarding such stationary horn usage. In June 2005, the Federal Railroad Administration (FRA) established the Train Horn Rule[10] which describes a step-by-step process to determine what can be done to offset the lack of a train horn, to calculate risk reduction, and to formally document establishments of Quiet Zones. This federal rule is currently implemented by the CPUC’s Rail Crossings and Engineering Branch; as such, the need for these statutorily authorized pilot projects no longer exists.
- When Your Area Code Changes, Who Are You Going to Call? This bill makes optional the requirement that the CPUC must conduct four meetings – one for local officials and three for members of the public – in areas with proposed telephone area code changes. When the statute for these meetings was enacted[11] the demand for telephone numbers was on the rise and with that the need to open new area codes, which proved initially unusual and controversial. As a result, both federal and state agencies sought procedures to better inform the public of these rapid changes and to assist in facilitating new area code implementation. But during the past three area code change proposals – for area codes 805, 916, and 619 – fewer than a hundred members of the public attended the total 9 meetings across the affected areas. In all of the 9 meetings, the attendance was dominated by persons required to attend – service provider representatives, local officials, and media.[12] It could be argued that this bill, in limiting the number of these public meetings, enables the CPUC staff to shift money and attention to higher priority issues. However, meeting attendance is not the only metric for determining the need for CPUC outreach efforts. In non-English speaking communities, where area code changes have the potential to be more confusing, early outreach could preempt issues and negative impacts. In striking these meeting requirements, the CPUC shifts from being proactive to reactive.
- What is in a Log? In SB 215 (Leno, Hueso, Chapter 807, Statutes of 2016) the Legislature mandated decisionmakers at the CPUC to file a notice in the event of participating in ex parte communication. A “notice” at the CPUC is a specific document type that is filed directly in the proceeding to which the comment is related. The CPUC maintains a central list of all the documents filed for each proceeding, as a consolidated source for the activities of a proceeding. This file system seeks to maintain transparency and alert all stakeholders to events that are germane to the proceeding. However, prior to the passage of SB 215 in 2016 the CPUC – rather than filing a notice – maintained ex parte communications in a public log.[13] The public log maintained a list of all ex parte communications for all proceedings of the CPUC. The log was sortable, searchable, and downloadable; and included meeting dates, CPUC participants, interested party participants, the relevant proceeding numbers, a communication ID, and the subject matter of the communication. This log was disregarded as a result of SB 215’s passage.
The justification for mandating the CPUC ex parte notices be filed within each proceeding rather than the public log arose from a 2015 report on CPUC ex parte practices by Strumwasser & Woocher.[14] On page 156 of the report they state: “And even more importantly, making ex parte communications part of the public record will help ensure that the Commission’s decisions are reached on the basis of the record…Having access to written ex parte communications will enable parties to object to those that are unsupported or otherwise improper.” This bill allows for the CPUC’s communications log to be reinstated and used in lieu of filing notices within a proceeding. This bill does additionally mandate that any notice added to the log must also trigger notification to any interested parties to the relevant proceeding. Yet, in excluding documentation to a log and service list, these notices could miss stakeholders that are late to a proceeding. The author’s office has noted that the required notification sent to the service list should equally trigger a notice in the appropriate proceeding’s docket card that specifies this service list contact. This notice would inform those monitoring the proceeding’s documents that a relevant ex parte disclosure has been logged. However, this requirement is unclear in the current language of the bill. As a result, the committee may wish to consider clarifying that the notification to the service list will also trigger a notice listed on the proceeding’s docket card.
- Contesting the Uncontested. The CPUC is mandated to assign a commissioner to all proceedings. That commissioner must prepare a scoping memo that describes the issues to be considered and develop a schedule for the case. For adjudication and ratesetting proceedings, the commissioner also schedules a prehearing conference.[15] This bill, rather, allows commissioners to exercise discretion for issuing scoping memos or ordering prehearing conferences in uncontested proceedings, either adjudicatory or quasi-legislative. A few issues arise with these discretionary allowances. First, adjudicatory proceedings are, by statute,[16] “enforcement cases and complaints.” Thus by their nature, adjudicatory proceedings are contested proceedings. Second, scoping memos are intended to be a guiding document for proceedings, requiring the assigned commissioner to consider issues at the beginning of a proceeding and to set a timetable going forward. The scoping memo seeks to not just orient commissioners to a proceeding’s issues, but also provide transparency to the public to the nature and breadth being considered in the proceeding. This should be especially relevant in quasi-legislative proceedings, where the CPUC is establishing policy. Considering this, the committee may wish to consider an amendment striking these exclusions to scoping memos and prehearing conferences in statute.
- Open to All? This bill excludes open sessions of conferences and other public meetings from ex parte restrictions, and does not define open sessions as one-way communications. These omissions of open sessions of conferences from ex parte communication rules either permits communication that is currently prohibited outright (adjudication) or communication that is permitted but requires disclosure (ratesetting or quasi-legislative). This bill, in exempting open sessions of conferences from the definition of ex parte communications, in effect allows CPUC commissioners to speak at conferences without having to disclose where and to whom they were speaking. The desire for commissioners to participate at conferences is in line with recent public-engagement measures at the CPUC; however, the necessity for not disclosing commissioner conference attendance is not known at this time.
Moreover, in their 2015 report evaluating ex parte practices at the CPUC, Strumwasser and Woocher[17] recommended specific policies be adopted for conferences. Their comments were specific to industry-sponsored conferences, and spoke to ex parte communications broadly not the specific case of speeches at conferences. Nevertheless, they recommended decisionmakers should avoid conferences “where issues presented in pending adjudicatory or ratesetting proceedings are expected to be part of the program. …where such communications inadvertently occur, they should disclose them on the record…” These issues were discussed during the adoption of SB 215 during last year’s session, and the current statute detailing ex parte at conferences evolved from those discussions. This bill would modify statute to permit and not require disclosure of CPUC communication during open sessions of conferences, such as during speeches.
- When to Close the Door? The Bagley-Keene Open Meeting Act prohibits meetings of a majority of the members of a state body, either serially or formally, without proper public notice. Last year, SB 215 (Leno, Hueso, Chapter 807, Statutes of 2016) sought to make amendments to CPUC Bagley-Keene rules by allowing a majority of CPUC commissioners to serve together on subcommittees, but this provision was greatly scaled back as the bill moved forward. At its chaptering, SB 215 only exempted closed sessions discussing administrative matters from Bagley-Keene rules of the CPUC. This current bill expands on this provision in SB 215 by allowing closed sessions discussing “state legislative proposals” to also be allowable exemptions. Presumably such allowances will enable CPUC commissioners to discuss active legislation and impacts on CPUC programs and ratepayers. The CPUC staff point to the limitations imposed by Bagley-Keene making it difficult to formalize agency positions on active legislation. The provision in this current bill would not permit the commissioners to vote or reach consensus on legislation, just discuss as a group. However, the exclusion currently in statute for administrative discussions was permitted only after extensive negotiation. A scan of current open meeting laws shows exclusions for some state agencies for certain topics such as eminent domain discussions, consideration of criminal records, consideration of confidential tax returns, information regarding trade secrets, or security related topics, among others.[18] The Committee is unaware at this time of other boards or commissions allowed to meet in closed session to discuss legislative matters. Therefore, the committee may wish to consider an amendment to the bill striking the inclusion of “state legislative proposals” from permissible closed session discussions of the CPUC.
- The Timing is Everything. This bill modifies the timeline for the CPUC to seek participation from affected parties to a proceeding. Under SB 512 (Hill, Chapter 808, Statutes of 2016), the CPUC was mandated to seek the participation of all stakeholders prior to the initial scoping memo of the proceeding. The scoping memo is among the first CPUC documents of a proceeding, and sets the table for the context of the proceeding. The CPUC argues that it would be more meaningful to have the outreach occur after a longer period of time has elapsed, in order to gain input regarding which parties should be involved. This bill makes such an adjustment, by moving the required outreach to just before the request for final briefs by the parties. However in so moving, the outreach is now weighted at the end of the proceeding timeline to just before a proposed decision is issued. This change, in effect, will greatly ease CPUC efforts as affected parties are more likely to already be participating in the proceeding by the time of the final briefs. Yet, this move disregards the efforts made under SB 512 to force the CPUC to be proactive in its outreach to interested and affected parties, and forecloses early participation by those parties. As such, the committee may wish to consider an amendment to require the outreach after issuance of the scoping memo.
- Related Legislation.
SB 19 (Hill, 2017) establishes an ethics officer that shall provide training and confidential advice on limitations to ex parte communications, among other CPUC changes and reforms proposed. This bill is set to be heard in the Assembly Committee Judiciary on July 11, 2017.
SB 215 (Leno, Hueso, Chapter 807, Statutes of 2016) established a suite of reforms of the rules, operations, and procedures of the CPUC, including the laws and rules related to ex parte communications and the criteria and process for disqualification of commissioners to a proceeding.
SB 512 (Hill, Chapter 808, Statutes of 2016) required, among other provisions, the CPUC to seek the participation of all stakeholders prior to the initial scoping memo of the proceeding. Current statute dictates this provision of SB 512 will expire on January 1, 2020.
SB 1222 (Hertzberg, Chapter 842, Statutes of 2016) changed the date by which the CPUC must submit specified reports, change the contents of specified reports, and repeal provisions requiring the CPUC to submit specified reports.
AB 1023 (Rendon, 2015) required the CPUC to establish and maintain a weekly communications log summarizing all oral or written ex parte communications. This bill was vetoed by the Governor.
SB 660 (Leno, Hueso, 2015) proposed a suite of reforms of the governance, rules, operations, and procedures of the CPUC including reform of laws and rules related to ex parte communications, criteria and process for disqualification of commissioners to a proceeding, and authorizing the CPUC to appoint a chief administrative law judge. This bill was vetoed by the Governor.
SB 636 (Hill, Chapter 548, Statutes of 2014), among other changes, modified the prohibition on ex parte communication in adjudication cases at the CPUC.
AB 1494 (Eng, Chapter 150, Statutes of 2009) amends to the Bagley-Keene Open Meeting Act to prohibit a majority of the members of a state body from using a series of communications of any kind to discuss or deliberate on an item of business before the body.
REGISTERED SUPPORT / OPPOSITION:
Support
California Public Utilities Commission (Sponsor)
Opposition
None on file.
Analysis Prepared by: Laura McWilliams / U. & E. /
GOV §11120 ↑
GOV §11122.5 ↑
GOV § 11125(b) ↑
GOV § 11126 et seq. ↑
PUC § 1701.2 (h); 1701.3 (h)(6) ↑
PUC § 1701.1 (f) ↑
Strumwasser, M., et al. Report to the CPUC Regarding Ex Parte Communication and Related Practices. June 22, 2015. http://www.strumwooch.com/documents/Report-to-the-Commission.pdf ↑
Article 11. Reports to Legislature PUC §§910-920 ↑
Originally under AB 270 (Bradford, Chapter 610, Statutes of 2013) but moved to PUC § 913.9 under SB 697 (Hertzberg, Chapter 612, Statutes of 2015) ↑
Code of Federal Regulations Title 9, Part 222 ↑
Under AB 2716 (Martinez, Chapter 534, Statutes of 1998) ↑
CPUC Communications Division. “805 Area Code Public Participation Meetings Held in the Cities of Oxnard, Santa Barbara, and San Louis Obispo on August 22 and 23, 2016”. October 28, 2016.
CPUC Communications Division. “916 Area Code Public Participation Meetings Held in the Cities of Sacramento, Folsom, and Roseville on August 15 and 16, 2016”. October 28, 2016.
CPUC Communications Division. “619 Area Code Public Participation Meetings Held in the Cities of San Diego, Solana Beach, and Pine Valley on October 4 and 5, 2016”. November 10, 2016. ↑
https://apps.cpuc.ca.gov/apex/f?p=402:5:4601590288404::NO:RP ↑
Strumwasser, M., et al. Report to the CPUC Regarding Ex Parte Communication and Related Practices. June 22, 2015. http://www.strumwooch.com/documents/Report-to-the-Commission.pdf ↑
PUC § 1701.1(b,c) ↑
PUC § 1701.1 (d)(2) ↑
Strumwasser, M., et al. Report to the CPUC Regarding Ex Parte Communication and Related Practices. June 22, 2015. http://www.strumwooch.com/documents/Report-to-the-Commission.pdf ↑
See: https://ballotpedia.org/California_Open_Meeting_Act ↑
Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB |
THIRD READING
Bill No: SB 385
:
SENATE ENERGY, U. & C. COMMITTEE: 11-0, 4/18/17
AYES: Hueso, Morrell, Bradford, Cannella, Hertzberg, Hill, McGuire, Skinner, Stern, Vidak, Wiener
SENATE APPROPRIATIONS COMMITTEE: Senate Rule 28.8
SOURCE: California Public Utilities Commission
DIGEST:
This bill provides technical clean-up of the Public Utilities Code, including modifying and clarifying existing statutes and repealing obsolete provisions.
Senate Floor Amendments of 5/25/17 clarify where the California Public Utilities Commission must report information regarding similar energy efficiency programs.
Existing law:
- Requires the California Public Utilities Commission (CPUC) to submit to the Legislature a detailed budget implementing transportation services related fees for the 1992-93 fiscal year. Requires the budget for expenditure of railroad corporation fees, for each of the 1996-97 and 1997-98 fiscal years, not to exceed the amount of $3 million. Requires the CPUC to conduct an audit of the expenditure of funds, commencing with the 1993-94 fiscal year, and in each subsequent fiscal year until the 1999-2000 fiscal year. Requires expenditures for an audit by the California State Auditor’s Office not to exceed $75,000. (Public Utilities Code §421)
- Requires the CPUC, in conjunction with the California Environmental Protection Agency, to request, no later than July 1, 1992, the federal agencies to investigate and review other chemical compounds not presently considered to be hazardous or toxic for possible reclassification as hazardous substances, require the use of safer cars in rail transportation of all hazardous material, and other requests. Requires the CPUC to report to the Legislature on the status of its request no later than September 30, 1992, and every six months thereafter until September 30, 1995. (Public Utilities Code §765.7)
- Requires the CPUC to, in a proceeding, not to exceed 18 months in duration, consider the need for performance reliability standards for all backup power systems installed on the property of residential and small commercial customers by a facilities-based provider of telephony services. Requires the CPUC to prepare and submit a report on the results of the proceeding before January 1, 2008. (Public Utilities Code §776)
- Requires the CPUC to complete its investigation and report regarding recommendations from its examination of the current and future definitions of universal service on or before January 1, 2002. (Public Utilities Code §883)
- Requires the CPUC to report annually on its efforts to identify ratepayer-funded energy efficiency programs that are similar to programs administered by the California Energy Commission, the State Air Resources Board, and the California Alternative Energy and Advanced Transportation Financing Authority in its annual report and to require revisions of ratepayer funded programs as necessary. (Public Utilities Code §913.9)
- Requires the CPUC to report to the Legislature the findings of any risk assessment for a proposed new underground gas storage facility. (Public Utilities Code §1103)
- Declares the intent of the Legislature that the CPUC authorize pilot projects to test the utility and safety of stationary, automated audible warning devices as an alternative to trains having to sound their horns as they approach highway rail crossings in specified communities. Prohibits new pilot projects from being authorized after January 1, 2003. Requires the CPUC to report to the Legislature by March 31, 2004, on the outcome of the pilot project. (Public Utilities Code §1202)
- Requires the CPUC, on or before March 1, 2009, to request from each telephone corporation doing business in this state that possesses one or more telephone number prefixes, the specific telephone numbers and quantities within the possession of the provider, both in use and not in use. Requires the CPUC to submit a report to the Legislature on or before, July 1, 2001, on a study of telecommunications industry use rates. (Public Utilities Code §7937)
This bill:
- Repeals several outdated provisions of the current statutes related to the CPUC, including requirements of the CPUC to:
- Conduct an audit, or have the State Auditor conduct an audit, of the expenditures of specified funds commencing with the 1993-94 fiscal year and in each subsequent year until the 1999-2000 fiscal year.
- In conjunction with the California Environmental Protection Agency, request no later than July 1, 1992, the appropriate federal agencies to take specified actions relating to hazardous substances and materials, and related status reports to the Legislature every six months beginning September 30, 1992, until September 30, 1995.
- Prepare and submit a report, before January 1, 2008, to the Legislature regarding performance reliability standards adopted for all backup commercial customers installed by a facilities-based provider of telephony services.
- Report to the Legislature its findings and recommendations, on or before January 1, 2002, related to examining the current and future definitions of universal service.
- Authorize specified pilot programs relating to rail crossings prior to January 1, 2003, and requirements to report to the Legislature by March 31, 2004, on the outcome of those pilot programs.
- Prepare and submit to the Legislature, on or before, July 1, 2001, a study of telecommunications industry use rates.
- Moves, to the part of the Public Utilities Code that lists all required reports, provisions of the statutes requiring reports to be submitted by the CPUC to the Legislature, including:
- The findings of any risk assessment completed to evaluate the potential impact of a leak from a proposed new underground gas storage facility.
- A detailed budget for the expenditure of railroad corporation fees for the ensuing budget year.
- Clarifies that an existing required report of the CPUC to the Legislature regarding energy efficiency programs applies to those programs of the investor-owned utilities and requires that information is included biennially in the Section 913 Electricity and Gas Utility Costs report beginning December 31, 2018.
Background
Current law makes several requirements of the CPUC related to reports that must be submitted to the Legislature. In many instances, these reports are required for specified time periods. However, the language requiring these reports is maintained in the statutes even after the provisions have become obsolete.
In recent years, there has been an effort to maintain all reports of the CPUC to the Legislature in one section of the Public Utilities Code, so as to better track report requirements. However, bills often get adopted without ensuring any required reports to the Legislature by the CPUC are appropriately placed in the codes.
Lastly, this bill appropriately clarifies that the requirement of the CPUC to track existing energy efficiency programs and ensure minimal duplication with similar state programs is narrow to the CPUC’s oversight of investor-owned energy utilities and included every two years in an existing annual report.
Comments
This is an annual effort by the Legislature to help maintain consistency, relevance and accuracy of the Public Utilities Code statutes.
FISCAL EFFECT: Appropriation: Fiscal Com.: Local:
California Public Utilities Commission (source)
OPPOSITION: (Verified 5/26/17)
None received
5/27/17 17:52:25
**** END ****
Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB |
THIRD READING
Bill No: SB 385
:
SENATE ENERGY, U. & C. COMMITTEE: 11-0, 4/18/17
AYES: Hueso, Morrell, Bradford, Cannella, Hertzberg, Hill, McGuire, Skinner, Stern, Vidak, Wiener
SENATE APPROPRIATIONS COMMITTEE: Senate Rule 28.8
SOURCE: California Public Utilities Commission
DIGEST: This bill provides technical clean-up of the Public Utilities Code, including modifying and clarifying existing statutes and repealing obsolete provisions.
Existing law:
- Requires the California Public Utilities Commission (CPUC) to submit to the Legislature a detailed budget implementing transportation services related fees for the 1992-93 fiscal year. Requires the budget for expenditure of railroad corporation fees, for each of the 1996-97 and 1997-98 fiscal years, not to exceed the amount of $3 million. Requires the CPUC to conduct an audit of the expenditure of funds, commencing with the 1993-94 fiscal year, and in each subsequent fiscal year until the 1999-2000 fiscal year. Requires expenditures for an audit by the California State Auditor’s Office not to exceed $75,000. (Public Utilities Code §421)
- Requires the CPUC, in conjunction with the California Environmental Protection Agency, to request, no later than July 1, 1992, the federal agencies to investigate and review other chemical compounds not presently considered to be hazardous or toxic for possible reclassification as hazardous substances, require the use of safer cars in rail transportation of all hazardous material, and other requests. Requires the CPUC to report to the Legislature on the status of its request no later than September 30, 1992, and every six months thereafter until September 30, 1995. (Public Utilities Code §765.7)
- Requires the CPUC to, in a proceeding, not to exceed 18 months in duration, consider the need for performance reliability standards for all backup power systems installed on the property of residential and small commercial customers by a facilities-based provider of telephony services. Requires the CPUC to prepare and submit a report on the results of the proceeding before January 1, 2008. (Public Utilities Code §776)
- Requires the CPUC to complete its investigation and report regarding recommendations from its examination of the current and future definitions of universal service on or before January 1, 2002. (Public Utilities Code §883)
- Requires the CPUC to report annually on its efforts to identify ratepayer-funded energy efficiency programs that are similar to programs administered by the California Energy Commission, the State Air Resources Board, and the California Alternative Energy and Advanced Transportation Financing Authority in its annual report and to require revisions of ratepayer funded programs as necessary. (Public Utilities Code §913.9)
- Requires the CPUC to report to the Legislature the findings of any risk assessment for a proposed new underground gas storage facility. (Public Utilities Code §1103)
- Declares the intent of the Legislature that the CPUC authorize pilot projects to test the utility and safety of stationary, automated audible warning devices as an alternative to trains having to sound their horns as they approach highway rail crossings in specified communities. Prohibits new pilot projects from being authorized after January 1, 2003. Requires the CPUC to report to the Legislature by March 31, 2004, on the outcome of the pilot project. (Public Utilities Code §1202)
- Requires the CPUC, on or before March 1, 2009, to request from each telephone corporation doing business in this state that possesses one or more telephone number prefixes, the specific telephone numbers and quantities within the possession of the provider, both in use and not in use. Requires the CPUC to submit a report to the Legislature on or before, July 1, 2001, on a study of telecommunications industry use rates. (Public Utilities Code §7937)
This bill:
- Repeals several outdated provisions of the current statutes related to the CPUC, including requirements of the CPUC to:
- Conduct an audit, or have the State Auditor conduct an audit, of the expenditures of specified funds commencing with the 1993-94 fiscal year and in each subsequent year until the 1999-2000 fiscal year.
- In conjunction with the California Environmental Protection Agency, request no later than July 1, 1992, the appropriate federal agencies to take specified actions relating to hazardous substances and materials, and related status reports to the Legislature every six months beginning September 30, 1992, until September 30, 1995.
- Prepare and submit a report, before January 1, 2008, to the Legislature regarding performance reliability standards adopted for all backup commercial customers installed by a facilities-based provider of telephony services.
- Report to the Legislature its findings and recommendations, on or before January 1, 2002, related to examining the current and future definitions of universal service.
- Authorize specified pilot programs relating to rail crossings prior to January 1, 2003, and requirements to report to the Legislature by March 31, 2004, on the outcome of those pilot programs.
- Prepare and submit to the Legislature, on or before, July 1, 2001, a study of telecommunications industry use rates.
- Moves, to the part of the Public Utilities Code that lists all required reports, provisions of the statutes requiring reports to be submitted by the CPUC to the Legislature, including:
- The findings of any risk assessment completed to evaluate the potential impact of a leak from a proposed new underground gas storage facility.
- A detailed budget for the expenditure of railroad corporation fees for the ensuing budget year.
- Clarifies that an existing required report of the CPUC to the Legislature regarding energy efficiency programs applies to those programs of the investor-owned utilities and requires that the report be submitted biennially beginning December 31, 2018.
Background
Current law makes several requirements of the CPUC related to reports that must be submitted to the Legislature. In many instances, these reports are required for specified time periods, however, the language requiring these reports is kept in the code even after the provisions have become obsolete.
In recent years, there is an effort to maintain all reports of the CPUC to the Legislature in one section of the Public Utilities Code, so as to better track report requirements. However, bills often get adopted without ensuring any required reports to the Legislature by the CPUC are appropriately placed in the codes.
Lastly, this bill appropriately clarifies that the requirement of the CPUC to track existing energy efficiency programs and ensure minimal duplication with similar state programs is narrow to the CPUC’s oversight of investor-owned energy utilities.
Comments
This is an annual effort by the Legislature to help maintain consistency, relevance and accuracy of the Public Utilities Code statutes.
FISCAL EFFECT: Appropriation: Fiscal Com.: Local:
California Public Utilities Commission (source)
None received
5/3/17 14:47:08
SENATE COMMITTEE ON ENERGY, UTILITIES AND COMMUNICATIONS
Senator Ben Hueso, Chair
2017 - 2018 Regular
Bill No: Hearing Date: 4/18/2017
Author: | |||
Version: | As Amended | ||
Urgency: | Fiscal: | ||
Consultant: | |||
SUBJECT:
DIGEST: This bill would provide technical clean-up of the Public Utilities Code, including modifying and clarifying existing statutes and repealing obsolete provisions.
ANALYSIS:
Existing law:
- Requires the California Public Utilities Commission (CPUC) to submit to the Legislature a detailed budget implementing transportation services related fees for the 1992-93 fiscal year. Requires the budget for expenditure of railroad corporation fees, for each of the 1996-97 and 1997-98 fiscal years does not exceed the amount of three million dollars. Requires the CPUC to conduct an audit of the expenditure of funds, commencing with the 1993-94 fiscal year, and in each subsequent fiscal year until the 1999-2000 fiscal year. Requires expenditures for an audit by the California State Auditor’s Office does not exceed seventy-five thousand. (Public Utilities Code §421)
- Requires the CPUC, in conjunction with the California Environmental Protection Agency, to request, no later than July 1, 1992, the federal agencies to investigate and review other chemical compounds not presently considered to be hazardous or toxic for possible reclassification as hazardous substances, require the use of safer cars in rail transportation of all hazardous material, and other requests. Requires the CPUC to report to the Legislature on the status of its request no later than September 30, 1992, and every six months thereafter until September 30, 1995. (Public Utilities Code §765.7)
- Requires the CPUC to in a proceeding not to exceed 18 months in duration, consider the need for performance reliability standards for all backup power systems installed on the property of residential and small commercial customers by a facilities-based provider of telephony services. Requires the CPUC to prepare and submit a report on the results of the proceeding before January 1, 2008. (Public Utilities Code §776)
- Requires the CPUC to complete its investigation and report regarding recommendations from its examination of the current and future definitions of universal service on or before January 1, 2002. (Public Utilities Code §883)
- Requires the CPUC to report annually on its efforts to identify ratepayer-funded energy efficiency programs that are similar to programs administered by the California Energy Commission, the State Air Resources Board, and the California Alternative Energy and Advanced Transportation Financing Authority in its annual report and to require revisions of ratepayer funded programs as necessary. (Public Utilities Code §913.9)
- Requires the CPUC to report to the Legislature the findings of any risk assessment for a proposed new underground gas storage facility. (Public Utilities Code §1103)
- Declares the intent of the Legislature that the CPUC authorize pilot projects to test the utility and safety of stationary, automated audible warning devices as an alternative to train s having to sound their horns as they approach highway rail crossings in specified communities. Prohibits new pilot projects from being authorized after January 1, 2003. Requires the CPUC to report to the Legislature by March 31, 2004, on the outcome of the pilot project. (Public Utilities Code §1202)
- Requires the CPUC, on or before March 1, 2009, to request from each telephone corporation doing business in this state that possesses on or more telephone number prefixes, the specific telephone numbers and quantities within the possession of the provider, both in use and not in use. Requires the CPUC to submit a report to the Legislature on or before, July 1, 2001, on a study of telecommunications industry use rates. (Public Utilities Code §7937)
This bill:
- Repeals several outdated provisions of the current statutes related to the Public Utilities Commission, including requirements of the CPUC to:
- Conduct an audit, or have the State Auditor conduct an audit, of the expenditures of specified funds commencing with the 1993-94 fiscal year and in each subsequent year until the 1999-2000 fiscal year.
- In conjunction with the California Environmental Protection Agency, request no later than July 1, 1992, the appropriate federal agencies to take specified actions relating to hazardous substances and materials, and related status reports to the Legislature every six months beginning September 30, 1992 until September 30, 1995.
- Prepare and submit a report, before January 1, 2008, to the Legislature regarding performance reliability standards adopted for all backup commercial customers installed by a facilities-based provider of telephony services.
- Report to the Legislature its findings and recommendations, on or before January 1, 2002, related to examining the current and future definitions of universal service.
- Authorize specified pilot programs relating to rail crossings prior to January 1, 2003, and requirements to report the Legislature by March 31, 2004, on the outcome of those pilot programs.
- Prepare and submit to the Legislature, on or before, July 1, 2001, a study of telecommunications industry use rates.
- Moves, to the part of the Public Utilities Code that lists all required reports, provisions of the statutes requiring reports to be submitted by the CPUC to the Legislature, including:
- The findings of any risk assessment completed to evaluate the potential impact of a leak from a proposed new underground gas storage facility.
- A detailed budget for the expenditure of railroad corporation fees for the ensuing budget year.
- Clarifies that an existing required report of the CPUC to the Legislature regarding energy efficiency programs applies to those programs of the investor-owned utilities and requires the report is submitted biannually beginning December 31, 2018.
Background
Current law makes several requirements of the CPUC related to reports that must be submitted to the Legislature. In many instances, these reports are required for specified time periods, however, the language requiring these reports is kept in the code even after the provisions have become obsolete.
In recent years, there is an effort to maintain all reports of the CPUC to the Legislature in one section of the Public Utilities Code, so as to better track report requirements. However, bills often get adopted without ensuring any required reports to the Legislature by the CPUC are appropriately placed in the codes.
Lastly, this bill appropriately clarifies that the requirement of the CPUC to track existing energy efficiency programs and ensure minimal duplication with similar state programs is narrow to the CPUC’s oversight of investor-owned energy utilities.
FISCAL EFFECT: Appropriation: Fiscal Com.: Local:
SUPPORT:
California Public Utilities Commission (Source)
OPPOSITION:
None received
ARGUMENTS IN SUPPORT: This is an annual effort by the Legislature to help maintain consistency, relevance and accuracy of the Public Utilities Code statutes.
-- END --