SB 445: High-speed rail: third-party agreements, permits, and approvals: regulations.
- Session Year: 2025-2026
- House: Senate
- Latest Version Date: 2025-07-17
Current Status:
In Progress
(2025-08-29: August 29 hearing: Held in committee and under submission.)
Introduced
In Committee
Awaiting First Chamber Vote
Passed First Chamber
In Committee
Awaiting Second Chamber Vote
Passed Second Chamber
Enacted
What does this bill do?
The bill requires the High‑Speed Rail Authority to adopt rules that set standards and timelines for coordinating with utilities and local agencies on permits, approvals, and utility relocations, and to specify when cooperative agreements or a binding dispute‑resolution process (a way to settle disagreements that parties must follow) should be used. It also requires the authority and affected utilities to identify barriers and agree on preferred solutions to avoid project delays, and directs the Authority’s Office of Inspector General to confirm the rules are in place and later evaluate their effectiveness.
The summary is provided by generative AI which can make mistakes. For original language, please view the details in the table below.
The California High-Speed Rail Act creates the High-Speed Rail Authority (authority) to develop and implement a high-speed rail system in the state, with specified powers and duties, including the power to enter into contracts, relocate highways and utilities, and enter into cooperative or joint development agreements with local governments or private entities, as specified. The act establishes legal procedures for the relocation of publicly and privately owned utility facilities, as defined, when the authority requires any utility to remove any utility facility lawfully maintained in the right-of-way of any high-speed rail property to a location entirely outside the high-speed rail property right-of-way subject to specified conditions. The act authorizes the authority and any utility to enter into a specified agreement or contract to remove or relocate any utility facility that provides for, among other things, the respective amounts of the cost to be borne by each party or that apportions the obligations and costs of each party.
Existing law creates the High-Speed Rail Authority Office of the Inspector General (office) and authorizes the High-Speed Rail Authority Inspector General (inspector general) to initiate an audit or review regarding oversight related to delivery of the high-speed rail project undertaken by the authority and the selection and oversight of contractors related to that project. Existing law requires the inspector general to submit annual reports to the Legislature and Governor regarding its findings.
This bill would require the authority, on or before July 1, 2026, to develop and adopt internal rules, as defined, setting forth standards and timelines for the authority to engage utilities to ensure coordination and cooperation in relocating utility infrastructure or otherwise resolving utility conflicts affecting the delivery of the high-speed rail project. The bill would require the authority to ensure that the internal rules, among other things, identify the circumstances under which the authority would be required seek to enter into a cooperative agreement with a utility that, where relevant, identifies who is responsible for specific utility relocations, as specified.
This bill would require the authority, on or before January July 1, 2026, to develop and adopt regulations setting forth requirements governing third-party local agency permits and approvals that are necessary to deliver the high-speed rail project. The bill would require the authority to ensure that the regulations, among other things, identify the circumstances under which the authority would be required to seek to enter into a cooperative agreement with a third party, which the bill would define as a local agency or utility, that that, where relevant, identifies who is responsible for specific utility relocations and the costs associated with those relocations. The actions, as specified.
This bill would require the authority to consult with specified entities in developing the internal rules and regulations and would require the authority to hold at least 2 public hearings regarding the proposed internal rules and regulations.
This bill would prohibit the authority from implementing these regulations unless it completes delay the operation of these internal rules and regulations until the office determines that the authority has completed the development and implementation of a process to review third-party agreements in a timely manner as recommended by the office, as specified. The bill would require the office, beginning one year after the operative date of the internal rules and regulations, to conduct a review of the effectiveness of those rules and regulations and to make recommendations for their improvement. The bill would require the office, when it determines that the high-speed rail project is complete, to submit a report to the Legislature informing the Legislature of that fact. The bill would make the requirement to adopt these internal rules and regulations inoperative on the date that the office submits that report to the Legislature.
This bill would require the authority and specified utilities to identify existing barriers and agree to preferred solutions to those barriers by December 31, 2026, to ensure utility relocations do not result in unnecessary or foreseeable project delays, as specified.
This bill would declare its provisions to be severable.
To the extent this bill imposes additional duties on local entities, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
The California High-Speed Rail Act creates the High-Speed Rail Authority (authority) to develop and implement a high-speed rail system in the state, with specified powers and duties, including the power to enter into contracts, as specified. The act establishes legal procedures for the relocation of publicly and privately owned utility facilities, as defined, when the authority requires any utility to remove any utility facility lawfully maintained in the right-of-way of any high-speed rail property to a location entirely outside the high-speed rail property right-of-way subject to specified conditions. The act authorizes the authority and any utility to enter into a specified agreement or contract to remove or relocate any utility facility that provides for, among other things, the respective amounts of the cost to be borne by each party or that apportions the obligations and costs of each party.
Existing law creates the High-Speed Rail Authority Office of the Inspector General (office) and authorizes the High-Speed Rail Authority Inspector General (inspector general) to initiate an audit or review regarding oversight related to delivery of the high-speed rail project undertaken by the authority and the selection and oversight of contractors related to that project. Existing law requires the inspector general to submit annual reports to the Legislature and Governor regarding its findings.
This bill would require the authority, on or before January 1, 2026, to develop and adopt regulations setting forth requirements governing third-party permits and approvals that are necessary to deliver the high-speed rail project. The bill would require the authority to ensure that the regulations, among other things, identify the circumstances under which the authority would be required to seek to enter into a cooperative agreement with a third party, which the bill would define as a local agency or utility, that identifies who is responsible for specific utility relocations and the costs associated with those relocations. The bill would require the authority to consult with specified entities in developing the regulations and would require the authority to hold at least 2 public hearings regarding the proposed regulations.
This bill would prohibit the authority from implementing these regulations unless it completes the development and implementation of a process to review third-party agreements in a timely manner as recommended by the office, as specified. The bill would require the office, when it determines that the high-speed rail project is complete, to submit a report to the Legislature informing the Legislature of that fact. The bill would make the requirement to adopt these regulations inoperative on the date that the office submits that report to the Legislature.
This bill would declare its provisions to be severable.
To the extent this bill imposes additional duties on local entities, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law establishes the Transportation Agency in state government with various duties and responsibilities. The agency is under the supervision of the Secretary of Transportation, who has the power of general supervision over specified departments and offices.Existing law requires a local agency to comply with all applicable building ordinances and zoning ordinances of the county or city in which the territory of the local agency is situated and, for purposes of that requirement, excludes rapid transit districts and certain rail transit districts from the definition of a local agency.This bill would enact the Sustainable Transportation Project Delivery Reform Act. The bill would authorize the secretary to grant a waiver to a local agency, as defined, that is seeking to design and construct a sustainable transportation project, as defined, from any standards, criteria, specifications, requirements, or other conditions of a third party, as defined, applicable to the sustainable transportation project if the secretary determines that granting the waiver will assist the local agency in delivering the sustainable transportation project in a cost-efficient and timely manner. This bill would also require a third party, which is defined as a local agency or utility, to publish online by July 1, 2026, a list of every permit or approval that it may require for a facility rearrangement, as defined, and all objective standards, criteria, specifications, and requirements used in evaluating requests by lead agencies, as defined, for delivery of facility rearrangements, as specified. The bill would require the lead agency to provide a specified notice to each third party it reasonably expects it will need to get permits or approvals from or otherwise coordinate with to deliver the facility rearrangements. The bill would set forth a process for delivering the notice and responding to the notices, including by entering into a cooperative agreement or entering into a streamlined project delivery process, as described. The bill would, as part of the streamlined project delivery process, set forth timelines and specifications for submitting and responding to various information and documents for the facility rearrangements, among other things.This bill would require the lead agency to reimburse the third party for all reasonable third party review activities required by the streamlined project delivery process, among other things. The bill would also authorize a lead agency to invoke a binding dispute resolution process, as described, if a third party does not issue a permit or approval to a lead agency or does not take any other action that is necessary to facilitate the delivery of part or all of a sustainable transportation project. The bill would make its provisions severable and would make related legislative findings and declarations.By imposing additional duties on local entities, this bill would impose a state-mandated local program.The bill would include findings that changes proposed by this bill address a matter of statewide concern rather than a municipal affair and, therefore, apply to all cities, including charter cities.The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.This bill would provide that no reimbursement is required by this act for a specified reason.Existing law establishes the Transportation Agency in state government with various duties and responsibilities. The agency is under the supervision of the Secretary of Transportation, who has the power of general supervision over specified departments and offices.
Existing law requires a local agency to comply with all applicable building ordinances and zoning ordinances of the county or city in which the territory of the local agency is situated and, for purposes of that requirement, excludes rapid transit districts and certain rail transit districts from the definition of a local agency.
This bill would enact the Sustainable Transportation Project Delivery Reform Act. The bill would authorize the secretary to grant a waiver to a local agency, as defined, that is seeking to design and construct a sustainable transportation project, as defined, from any standards, criteria, specifications, requirements, or other conditions of a third party, as defined, applicable to the sustainable transportation project if the secretary determines that granting the waiver will assist the local agency in delivering the sustainable transportation project in a cost-efficient and timely manner.
This bill would also require a third party, which is defined as a local agency or utility, to publish online by July 1, 2026, a list of every permit or approval that it may require for a facility rearrangement, as defined, and all objective standards, criteria, specifications, and requirements used in evaluating requests by lead agencies, as defined, for delivery of facility rearrangements, as specified. The bill would require the lead agency to provide a specified notice to each third party it reasonably expects it will need to get permits or approvals from or otherwise coordinate with to deliver the facility rearrangements. The bill would set forth a process for delivering the notice and responding to the notices, including by entering into a cooperative agreement or entering into a streamlined project delivery process, as described. The bill would, as part of the streamlined project delivery process, set forth timelines and specifications for submitting and responding to various information and documents for the facility rearrangements, among other things.
This bill would require the lead agency to reimburse the third party for all reasonable third party review activities required by the streamlined project delivery process, among other things. The bill would also authorize a lead agency to invoke a binding dispute resolution process, as described, if a third party does not issue a permit or approval to a lead agency or does not take any other action that is necessary to facilitate the delivery of part or all of a sustainable transportation project. The bill would make its provisions severable and would make related legislative findings and declarations.
By imposing additional duties on local entities, this bill would impose a state-mandated local program.
The bill would include findings that changes proposed by this bill address a matter of statewide concern rather than a municipal affair and, therefore, apply to all cities, including charter cities.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law requires the Department of Transportation to improve and maintain the states highways. Existing law authorizes the department to issue encroachment permits and requires the department to either approve or deny an application from an applicant for an encroachment permit within 60 days of receiving a completed application, as provided. Existing law also requires the department, on or before January 1, 2027, to develop and adopt a project intake, evaluation, and encroachment permit review process for complete streets facilities that are sponsored by a local jurisdiction or a transit agency.This bill would instead require the department to develop and adopt the above-described project intake, evaluation, and encroachment review process on or before February 1, 2027. The bill would also state the intent of the Legislature to amend this bill with legislation that accelerates and makes more reliable third-party permits and approvals for preconstruction and construction activities on sustainable transportation projects. The bill would make related findings and declarations.Existing law requires the Department of Transportation to improve and maintain the states highways. Existing law authorizes the department to issue encroachment permits and requires the department to either approve or deny an application from an applicant for an encroachment permit within 60 days of receiving a completed application, as provided. Existing law also requires the department, on or before January 1, 2027, to develop and adopt a project intake, evaluation, and encroachment permit review process for complete streets facilities that are sponsored by a local jurisdiction or a transit agency.
This bill would instead require the department to develop and adopt the above-described project intake, evaluation, and encroachment review process on or before February 1, 2027. The bill would also state the intent of the Legislature to amend this bill with legislation that accelerates and makes more reliable third-party permits and approvals for preconstruction and construction activities on sustainable transportation projects. The bill would make related findings and declarations.
Existing law requires the Department of Transportation to improve and maintain the states highways. Existing law authorizes the department to issue encroachment permits and requires the department to either approve or deny an application from an applicant for an encroachment permit within 60 days of receiving a completed application, as provided. Existing law also requires the department, on or before January 1, 2027, to develop and adopt a project intake, evaluation, and encroachment permit review process for complete streets facilities that are sponsored by a local jurisdiction or a transit agency.
This bill would instead require the department to develop and adopt the above-described project intake, evaluation, and encroachment review process on or before February 1, 2027. The bill would also state the intent of the Legislature to amend this bill with legislation that accelerates and makes more reliable third-party permits and approvals for preconstruction and construction activities on sustainable transportation projects. The bill would make related findings and declarations.
Existing law, the Planning and Zoning Law, sets forth various requirements relating to the review of development project permit applications and the issuance of development permits for specified classes of development projects.The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of an environmental impact report on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment.CEQA, until January 1, 2030, exempts from its requirements certain transportation-related projects if specified requirements are met. CEQA includes within these exempt transportation-related projects a public project for the institution or increase of bus rapid transit, bus, or light rail service, which will be exclusively used by low-emission or zero-emission vehicles, on existing public rights-of-way or existing highway rights-of-way.This bill would require a lead agency to provide a written notice with specified information to a third-party entity, defined by the bill to mean a local agency, electrical corporation, or private telecommunications provider, regarding its need to use, relocate, alter, change, or otherwise improve facilities, publicly owned and managed utilities, public spaces, or other publicly or privately owned facilities under the third-party entitys jurisdiction or ownership for the implementation of a sustainable transportation project. This bill would define sustainable transportation project to mean a project where the lead agency is a state agency, operator, or local agency that proposes the construction or modification of facilities meeting at least one of several specified criteria, including that it is exempt from CEQA pursuant to the above-described provisions. The bill would define large sustainable transportation project to mean a sustainable transportation project that, based on the project engineers cost estimate at the time the lead agency completes environmental review, costs more than $25,000,000, and meets other specified criteria.This bill would require a lead agency to provide a written notice with specified information to a third-party entity regarding its need to use, relocate, alter, change, or otherwise improve facilities, publicly owned and managed utilities, public spaces, or other publicly or privately owned facilities under the third-party entitys jurisdiction or ownership for the implementation of a sustainable transportation project. Within 30 calendar days of receiving that notice, the bill would require the third-party entity to provide a written response to the lead agency, as provided, and, within 30 calendar days of determining the notice is complete, would require the third-party entity to take certain actions, including providing as-built plans to the lead agency for all third-party entity facilities that will be impacted by the work described in the written notice. The bill would also prohibit a third-party entity from requiring, among other things, as a condition for issuance of certain permits, conformance with or the performance of any conditions, except under certain circumstances.This bill would require a lead agency responsible for a large sustainable transportation project to seek to enter into a cooperative agreement with each third-party entity through which the project passes. The bill would also require the lead agency to provide a written notice with specified information to the third-party entity of its intent to enter into a cooperative agreement with the third-party entity. Within 30 calendar days of receiving the notice, the bill would require the third-party entity to provide a written response to the lead agency, as provided, and within 60 calendar days of determining the notice is complete, would require the third-party entity to enter into a cooperative agreement with the lead agency that contains certain provisions, including that it meets applicable federal requirements, standards, or guidelines. The bill would also prohibit a third-party entity from requiring, among other things, as a condition to the issuance of certain permits, conformance with or the performance of any conditions that the third-party entity could have lawfully imposed as a condition to the design or construction of the project after the process described above is completed.By imposing additional duties on local entities, this bill would impose a state-mandated local program.The bill would include findings that changes proposed by this bill address a matter of statewide concern rather than a municipal affair and, therefore, apply to all cities, including charter cities.The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.This bill would provide that no reimbursement is required by this act for a specified reason.Existing law, the Planning and Zoning Law, sets forth various requirements relating to the review of development project permit applications and the issuance of development permits for specified classes of development projects.
The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of an environmental impact report on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment.
CEQA, until January 1, 2030, exempts from its requirements certain transportation-related projects if specified requirements are met. CEQA includes within these exempt transportation-related projects a public project for the institution or increase of bus rapid transit, bus, or light rail service, which will be exclusively used by low-emission or zero-emission vehicles, on existing public rights-of-way or existing highway rights-of-way.
This bill would require a lead agency to provide a written notice with specified information to a third-party entity, defined by the bill to mean a local agency, electrical corporation, or private telecommunications provider, regarding its need to use, relocate, alter, change, or otherwise improve facilities, publicly owned and managed utilities, public spaces, or other publicly or privately owned facilities under the third-party entitys jurisdiction or ownership for the implementation of a sustainable transportation project. This bill would define sustainable transportation project to mean a project where the lead agency is a state agency, operator, or local agency that proposes the construction or modification of facilities meeting at least one of several specified criteria, including that it is exempt from CEQA pursuant to the above-described provisions. The bill would define large sustainable transportation project to mean a sustainable transportation project that, based on the project engineers cost estimate at the time the lead agency completes environmental review, costs more than $25,000,000, and meets other specified criteria.
This bill would require a lead agency to provide a written notice with specified information to a third-party entity regarding its need to use, relocate, alter, change, or otherwise improve facilities, publicly owned and managed utilities, public spaces, or other publicly or privately owned facilities under the third-party entitys jurisdiction or ownership for the implementation of a sustainable transportation project. Within 30 calendar days of receiving that notice, the bill would require the third-party entity to provide a written response to the lead agency, as provided, and, within 30 calendar days of determining the notice is complete, would require the third-party entity to take certain actions, including providing as-built plans to the lead agency for all third-party entity facilities that will be impacted by the work described in the written notice. The bill would also prohibit a third-party entity from requiring, among other things, as a condition for issuance of certain permits, conformance with or the performance of any conditions, except under certain circumstances.
This bill would require a lead agency responsible for a large sustainable transportation project to seek to enter into a cooperative agreement with each third-party entity through which the project passes. The bill would also require the lead agency to provide a written notice with specified information to the third-party entity of its intent to enter into a cooperative agreement with the third-party entity. Within 30 calendar days of receiving the notice, the bill would require the third-party entity to provide a written response to the lead agency, as provided, and within 60 calendar days of determining the notice is complete, would require the third-party entity to enter into a cooperative agreement with the lead agency that contains certain provisions, including that it meets applicable federal requirements, standards, or guidelines. The bill would also prohibit a third-party entity from requiring, among other things, as a condition to the issuance of certain permits, conformance with or the performance of any conditions that the third-party entity could have lawfully imposed as a condition to the design or construction of the project after the process described above is completed.
By imposing additional duties on local entities, this bill would impose a state-mandated local program.
The bill would include findings that changes proposed by this bill address a matter of statewide concern rather than a municipal affair and, therefore, apply to all cities, including charter cities.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
This act shall be known, and may be cited, as the High-Speed Rail Delivery Reform Act.
SEC. 2.(a)The Legislature finds and declares all of the following:
(a)(1)Utility relocation can become one of the greatest risk factors to greatly impact the scope, schedule, and cost of transit and rail projects.
(b)(2)The Federal Highway Administration finds that by addressing issues related to utility relocation proactively, construction projects can minimize the negative impacts on schedules, costs, and overall success.
(c)(3)The California high-speed rail project is important to state transportation priorities and the public good and it is critical that local government entities and state-regulated utility owners within the projects alignment make the timely completion of the project a high priority.
(d)(4)Third-party permits and approvals for preconstruction and construction activities, including utility relocations, design review, review and issuance of encroachment or other similar permits, and third-party agreements for utility relocations, have been a source of delay for the California high-speed rail project contributing to cost escalations and the project being built late and over budget.
(5)The High-Speed Rail Authority Office of the Inspector General, in Recommendation 25-R-02-02, proposed the High-Speed Rail Authority should complete the development and implementation of a process to review third-party agreements in a timely manner.
(b)It is the intent of the Legislature to establish a dispute resolution process applicable to utilities that appropriately balances the need to deliver the high-speed rail project on time and efficiently, with the need to provide utility service that prioritizes safety, reliability, and access.
SEC. 3.Chapter 6 (commencing with Section 185520) is added to Division 19.5 of the Public Utilities Code, to read:6.Regulations Rules Governing Third-Party Permits and Approvals Engagement185520.For purposes of this chapter, the following definitions apply:
(a)Electrical corporation has the same meaning as defined in Section 218.
(b)Gas corporation has the same meaning as defined in Section 222.
(c)High-speed rail project means the portion of the high-speed rail project identified in paragraph (2) of subdivision (b) of Section 2704.04 of the Streets and Highways Code.
(d)Internal rule means a regulation adopted by the authority that applies generally to the conduct of the business and affairs of the authority.
(e)Local agency means a city, county, city and county, or special district that is not a utility.
(f)Local publicly owned electric utility has the same meaning as defined in Section 224.3.
(g)Private telecommunications provider means a telephone corporation, as defined in Section 234, or a cable operator that is a holder of a state franchise, as defined in Section 5830.
(d)Third party means a local agency or utility, including,(h)Utility includes, but is not limited to, an electrical corporation, gas corporation, local publicly owned electric utility, or private telecommunications provider.
185522.On or before January July 1, 2026, the authority shall develop and adopt regulations setting forth requirements governing third-party permits and approvals that are necessary to deliver internal rules setting forth standards and timelines for the authority to engage utilities to ensure coordination and cooperation in relocating utility infrastructure or otherwise resolving utility conflicts affecting the delivery of the high-speed rail project. The authority shall ensure that the regulations internal rules do all of the following:
(a)Require early engagement between third parties and the authority. with utilities.
(b)Identify the circumstances under which the authority shall seek to enter into a cooperative agreement with each applicable third party utility that serves as the framework for all future project interactions between and among the authority and each applicable third party utility and, where relevant, identifies who is responsible for specific utility relocations and the costs associated with thoserelocations. A cooperative agreement shall define the roles and responsibilities of the authority and each applicable third party and clarify lines of communication so the decisionmaking process is understood. relocations.
(c)Require regular meetings with third parties utilities during the planning, design, and construction phases.
(d)Require the authority to establish cost estimates in coordination with each applicable utility with conservative contingency budgets for each utility relocation and to not oversimplify the utility costs and potential risks by bundling those costs into a single item. These cost estimates shall be established consistent with Chapter 5 (commencing with Section 185500).
(e)Require regular communication and with utilities, including by providing to utilities documentation of contracting terms, conditions, and decisions during construction.
(f)Define options that can govern a third-party review process for permits and approvals.(f)Provide options for utility review processes in order to prioritize the timely completion of the high-speed rail project.
(g)Consider ways to reduce permitting and approval delays. process delays or redundancy.
(h)Establish Provide options for establishing a binding dispute resolution process. process, including recommendations, provided in coordination with utilities, of independent administrators and neutral mediators to the resolution process.
(i)Exempt gas corporations and electrical corporations regulated by the Public Utilities Commission from the dispute resolution process established pursuant to subdivision (h).(j)Prohibit third-party entities from insisting on exactions or betterments from the authority that are unrelated to ensuring that health and safety standards are met, unless otherwise stipulated by a cooperative agreement, as a condition for permits and approvals.(k)Consider reimbursement of third-party staff time and third-party time and materials to relocate the utility.(l)Define the terms betterment and cooperative agreement for purposes of the regulation.(i)Identify, in coordination with the Public Utilities Commission, existing processes within the Public Utilities Commission that may provide a similar process and outcome for disputes with utilities regulated by the Public Utilities Commission instead of the process options provided pursuant to subdivision (h).
185524.On or before July 1, 2026, the authority shall develop and adopt regulations setting forth requirements governing local agency permits and approvals that are necessary to deliver the high-speed rail project. The authority shall ensure that the regulations do all of the following:
(a)Require early engagement between local agencies and the authority.
(b)Identify the circumstances under which the authority shall seek to enter into a cooperative agreement with each applicable local agency that serves as the framework for all future project interactions between and among the authority and each applicable local agency and, where relevant, identifies who is responsible for specific actions. A cooperative agreement shall define the roles and responsibilities of the authority and each applicable local agency and clarify lines of communication so the decisionmaking process is understood.
(c)Require regular meetings with local agencies during the planning, design, and construction phases.
(d)Require regular communication and documentation of contracting terms, conditions, and decisions during construction.
(e)Define options that can govern a local agency process for permits and approvals.
(f)Consider ways to reduce permitting and approval delays or redundancy.
(g)Establish a binding dispute resolution process.
(h)Prohibit local agencies from requesting exactions or betterments from the authority that are unrelated to ensuring that health, and safety standards are met.
(i)Define the terms betterment and cooperative agreement for purposes of the regulation described in subdivision (h).
185524.185526.(a)In developing the regulations internal rules required pursuant to Section 185522, and the regulations required pursuant to Section 185524, the authority shall consult with all of the following entities:
(1)The Department of Transportation. department.
(2)The Public Utilities Commission.
(3)Local government stakeholders. agencies.
(4)Local publicly owned electric utilities, gas corporations, and electrical corporations.
(5)Water districts.
(6)Telecommunications companies.(7)Passenger and freight railroads.(6)Private telecommunications providers.
(8)(7)Any other relevant entity identified by the authority that has expertise in transportation infrastructure project delivery. delivery or utility infrastructure relocation.
(b)Before adopting the internal rules and regulations required pursuant to Section 185522, Sections 185522 and 185524, the authority shall hold at least two public hearings regarding the proposed internal rules and regulations.
185526.185528.(a)The authority shall post a public notice on its internet website when it adopts the internal rules and regulations required pursuant to Section 185522. Sections 185522 and 185524. The authority shall not enter into a third-party agreement governed by this chapter until 30 days after the public notice is posted.
(b)The authority shall not implement regulations adopted pursuant to this chapter unless it completes the development and implementation of a process to review third-party agreements in a timely manner as recommended by the High-Speed Rail Authority Office of the Inspector General in Recommendation 25-R-02-02.(b)The internal rules and regulations adopted pursuant to this chapter shall not be operative until the High-Speed Rail Authority Office of the Inspector General determines that the authority has completed the development and implementation of a process to review third-party agreements in a timely manner as recommended by the High-Speed Rail Authority Office of the Inspector General in Recommendation 25-R-02-02.
(c)Beginning one year from the operative date of the internal rules and regulations described in subdivision (b), the High-Speed Rail Authority Office of the Inspector General shall evaluate the extent to which the authority is meeting its review deadlines and other applicable requirements in its adopted internal rules and regulations, and shall determine the extent to which the internal rules and regulations have been effective in limiting delays associated with third-party agreements. As part of this review, the High-Speed Rail Authority Office of the Inspector General shall gather and summarize the perspective of third parties on the effectiveness and impact of the internal rules and regulations and shall make recommendations for their improvement if necessary. The High-Speed Rail Authority Office of the Inspector General may post the results of the review conducted, and the recommendations made, pursuant to this subdivision on its internet website.
185530.(a)The authority and the utilities identified pursuant to Section 185526 shall identify existing barriers and agree to preferred solutions to those barriers by December 31, 2026, to ensure utility relocations do not result in unnecessary or foreseeable project delays.
(b)Preferred solutions shall include, but are not limited to, all of the following:
(1)Selecting specific outcomes from the options provided by the authority in subdivisions (f), (h), and (i) of Section 185522.
(2)Agreeing to preferred timelines for third-party design review or review of requests that vary based on the typical scope of work for each activity to which the timeline applies.
(3)Defining betterment, and ensuring requirements or conditions placed upon the authority unrelated to health, reliability, and safety standards are prohibited.
(4)Defining cooperative agreement and the terms of specified cooperative agreements. A cooperative agreement shall identify the roles and responsibilities of the authority and each applicable third party and clarify lines of communication so the decisionmaking process is understood.
185528.185532.This chapter shall become inoperative on the date that the High-Speed Rail Authority Office of the Inspector General submits a report pursuant to Section 187040, and, as of January 1 of the following year, is repealed.
SEC. 4.Section 187040 is added to the Public Utilities Code, to read:187040.(a)For purposes of determining the continued operation of Chapter 6 (commencing with Section 185520) of Division 19.5, when the office determines that the high-speed rail project, as defined in Section 185520, is complete, the office shall submit a report to the Legislature informing the Legislature of that fact.
(b)The report to be submitted pursuant to subdivision (a) shall be submitted in compliance with Section 9795 of the Government Code.
SEC. 5.The provisions of this measure are severable. If any provision of this measure or its application is held invalid, that invalidity shall not affect other provisions or applications that can be given effect without the invalid provision or application.
SEC. 6.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
This act shall be known, and may be cited, as the Sustainable Transportation Project High-Speed Rail Delivery Reform Act.
SEC. 2.The Legislature finds and declares all of the following:
(a)Sustainable transportation projects are critical for the growth of the state in a manner that reduces greenhouse gas emissions and helps address the states housing shortage.(a)Utility relocation can become one of the greatest risk factors to the scope, schedule, and cost of transit and rail projects.
(b)The Federal Highway Administration finds that by addressing issues related to utility relocation proactively, construction projects can minimize the negative impacts on schedules, costs, and overall success.
(c)The California high-speed rail project is important to state transportation priorities and the public good and it is critical that local government entities and state-regulated utility owners within the projects alignment make the timely completion of the project a high priority.
(b)(d)Third-party permits and approvals for preconstruction and construction activities, including utility relocations, design review, and issuance of encroachment or other similar permits, can be have been a source of delay for sustainable transportation projects, potentially resulting in the California high-speed rail project contributing to cost escalations and projects the project being built late and over budget.
SEC. 3.Section 13985 is added to the Government Code, to read:13985.(a)The secretary may grant a waiver to a local agency that is seeking to design and construct a sustainable transportation project from any standards, criteria, specifications, requirements, or other conditions of a third party applicable to the sustainable transportation project if the secretary determines that granting the waiver will assist the local agency in delivering the sustainable transportation project in a cost-efficient and timely manner.(b)The agency shall develop an application for local agencies to seek a waiver described in subdivision (a).(c)For purposes of this section, the following definitions apply:(1)Local agency has the same meaning as defined in Section 19001 of the Public Utilities Code.(2)Sustainable transportation project has the same meaning as defined in Section 19001 of the Public Utilities Code.(3)Third party has the same meaning as defined in Section 19001 of the Public Utilities Code.SEC. 4.Division 21 (commencing with Section 19001) is added to the Public Utilities Code, to read:21.Sustainable Transportation Project Delivery Requirements1.Definitions19001.For purposes of this division, the following definitions shall apply:(a)Advanced partial design unit means a portion of the design documentation for a facility rearrangement submitted to the third party for review and approval prior to submittal or approval of completed design documentation for that facility rearrangement.(b)(1)Betterment means work performed for a facility rearrangement that comprises an upgrade, change, or addition to a third-party facility, or to part of a third-party facility, that is requested by the third party, that provides for greater capacity, capability, durability, appearance, efficiency, or function or for another improvement of that third-party facility over that which is currently provided by the third-party facility, and that satisfies at least either of the following:(A)The third-party objective standards or third-party design and construction requirements applicable to that work are changed or supplemented after the date of the notice required by subdivision (a) of Section 19005.02.(B)Any other criteria, specifications, and requirements for facility rearrangements that the lead agency and third party mutually agree to are changed or supplemented after the date of the notice described in subdivision (c) of Section 19005.01.(2)Betterment shall exclude all of the following:(A)An upgrade, change, or addition to which the lead agency and third party agree will be of direct and principal benefit to the construction, operation, or maintenance of the sustainable transportation project.(B)An upgrade, change, or addition resulting from design or construction in accordance with the applicable third-party standards as of the date of the notice described in subdivision (a) of Section 19005.02, to the extent those third-party standards have not been adopted by the third party in breach of subdivision (f) of Section 19002.(C)An upgrade, change, or addition resulting from design or construction in accordance with the criteria, specifications, and requirements mutually agreed to and documented in the Stage 1 project scope document required by Stage 1.(D)Measures to mitigate environmental impacts required by a final environmental document pursuant to the California Environmental Quality Act (Division 13 (commencing with Section 21000) of the Public Resources Code) or National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.).(E)Replacement of devices or materials no longer regularly manufactured with the next highest grade or size.(F)An upgrade, change, or addition that is the consequence of changes made by the lead agency after the finalization of the Stage 1 project document for the sustainable transportation project.(c)Cooperative agreement means an agreement between a lead agency and one or more third parties establishing the entities respective obligations, roles and responsibilities, and processes and procedures to support the efficient, timely, and safe delivery of one or more sustainable transportation projects. The agreements provisions shall include, but are not limited to, the following:(1)Duration and scope of the agreement.(2)Governance for executing the cooperative agreement.(3)Provisions for cooperation and coordination to identify utility conflicts and ensure utility owners implement utility adjustments required to address utility conflicts.(4)Early involvement and coordination.(5)Responsibilities for design and construction.(6)Procedures for issue resolution.(7)Clear establishment of permitting or approval processes for facility rearrangements.(8)Evaluation of betterments within the project scope.(9)Inspection of work completed in compliance with applicable standards.(d)Coordination meeting means an informal meeting for the lead agency and third party to discuss the sustainable transportation project.(e)Design documentation means all specifications, reports, studies, working drawings, shop drawings, calculations, electronic files, records, submittals, and drawings, including plans, profiles, cross sections, notes, elevations, typical sections, details, and diagrams, that are necessary for, or related to, the design of facility rearrangements.(f)Facility rearrangement means the removal, restoration, alteration, reconstruction, support, or relocation of all or a portion of a third-party facility.(g)Final design documentation means design documentation for a facility rearrangement that is at 100-percent design level. Elements of final design documentation include final construction drawings, including plans, profiles, cross sections, notes, elevations, typical sections, details, diagrams, design criteria, specifications, reports, studies, calculations, electronic files, and other records.(h)Stage 1 means the process set forth in Article 1 (commencing with Section 19005.01) of Chapter 5 of this division.(i)Stage 1 design documentation means the design documentation required to be prepared in Stage 1, representing up to 15-percent design level.(j)Stage 2 means the process set forth in Article 2 (commencing with Section 19005.02) of Chapter 5 of this division.(k)Stage 2 design documentation means the design documentation required to be prepared in Stage 2, which advances design documentation from the design level required in Stage 1 design documentation, which is up to a 15-percent design level, to a 100-percent design level.(l)Sustainable transportation project means a project that consists of one or more of the following:(1)Any project identified in subdivision (b) of Section 21080.25 of the Public Resources Code.(2)A project whose primary purpose is the institution or improvement of public transit infrastructure, including, but not limited to, transit priority facilities, bus service, bus rapid transit, and passenger rail. For purposes of this paragraph, passenger rail includes, but is not limited to, light rail, commuter rail, regional rail, intercity rail, or heavy rail. Heavy rail includes rail transit, as defined in Section 99602.(m)Third party means a local agency or utility, including, but not limited to, an electrical corporation, public utility, or private telecommunications provider.(n)Third-party facility means a facility owned by a third party.(o)Lead agency means the public agency which has the principal responsibility for carrying out or approving a project. Lead agency also includes other parties whose services are procured by the lead agency, including, but not limited to, a private contractor or consultant.(p)Local agency means any public agency other than a state agency.(q)Third-party-located section means a portion of a sustainable transportation project that is located in the right-of-way of a third party.(r)Working day means any date that is not a Saturday, Sunday, or federal or state holiday.2.Transparent Objective Permitting and Approval Standards19002.(a)By July 1, 2026, a third party shall publish online a list of every permit or approval that it may require for a facility rearrangement. For each permit or approval, it shall publish online all objective standards, criteria, specifications, and requirements used by the third party when evaluating requests by lead agencies for delivery of facility rearrangements. These permits or approvals may include, but are not limited to, the following:(1)An encroachment permit.(2)A grading permit.(3)A tree removal permit.(4)A stormwater permit.(5)Construction staging plan approval.(b)If the third party modifies any of the above required permits or approvals, or objective standards, criteria, specifications, and requirements used by the third party when evaluating requests by lead agencies for delivery of facility rearrangements, the third party shall publish the modifications online promptly, but no later than within 15 working days of any modifications.(c)Except as otherwise provided by this division, a third party shall not inhibit a lead agencys delivery of a facility rearrangement that is consistent with the applicable objective standards, criteria, specifications, and requirements for permits or approvals it is required to identify pursuant to subdivision (a).(d)A third party shall not establish any standards, criteria, specifications, or requirements that are not objective in nature for purposes of evaluating requests by lead agencies for delivery of facility rearrangements.(e)Nothing in this act prohibits a lead agency and third party from mutually agreeing to construction conditions or facility rearrangements that are inconsistent with the applicable objective standards, criteria, specifications, and requirements for permits or approvals it is required to identify pursuant to subdivision (a).(f)A third party shall not adopt any new third-party standards or otherwise apply, amend, or supplement any existing third-party standards for the sole or primary purpose of affecting one or more sustainable transportation projects.3.Binding Dispute Resolution19003.(a)If a third party does not issue a permit or approval to a lead agency, or does not take any other action that is necessary to facilitate the delivery of part or all of a sustainable transportation project, the lead agency may elect to invoke the binding dispute resolution process described in subdivision (b).(b)The following binding dispute resolution process shall be administered by the Transportation Agency, which shall determine the schedule and duration of binding dispute resolution activities pursuant to this subdivision:(1)The state transportation agency shall designate a neutral mediator to work with the lead agency and third party to resolve the dispute or disputes that caused the lead agency to invoke the binding dispute resolution process described in this subdivision. If the dispute or disputes that caused the lead agency to invoke the binding dispute resolution process described in this subdivision involve matters related to utilities, the Public Utilities Commission shall designate an advisor with relevant experience to provide technical assistance to the neutral mediator for utility-related disputes. The resolution shall be recorded in a binding settlement agreement.(2)For the dispute or disputes that caused the lead agency to invoke the binding dispute resolution process described in this subdivision that were unresolved after the process described in paragraph (1), the neutral mediator shall become a neutral arbitrator, and shall resolve the remaining dispute or disputes following the arbitration processes described in Title 9 (commencing with Section 1280) of Part 3 of the Code of Civil Procedure, except as otherwise provided for in this subdivision.(3)The decision of the arbitrator shall be binding upon the lead agency and third party.(4)By mutual agreement, the lead agency and third party may select a different entity to serve as the neutral mediator and arbitrator pursuant to this subdivision.(5)By mutual agreement, the lead agency and third party may instead undergo the process described in paragraph (2), followed by the process described in paragraph (1). The judgment of the neutral arbitrator pursuant to paragraph (2) shall be sealed, and only unsealed and made binding if the subsequent process described in paragraph (1) does not result in resolution of the dispute or disputes.4.Pathways for Sustainable Transportation Project Delivery19004.(a)Once a lead agency is ready to transmit the notice described in subdivision (c) of Section 19005.01 for a specific sustainable transportation project, the lead agency shall compile a list of all third parties that it reasonably expects it will need to get permits or approvals from, or otherwise coordinate with, in order to deliver facility rearrangements.(b)Once the lead agency has compiled the list pursuant to subdivision (a), it shall elect one of the following courses of action for engagement with each listed third party:(1)Enter into a cooperative agreement related to the sustainable transportation project if it has not done so already.(2)Commence the streamlined project delivery process described in Chapter 5 (commencing with Section 19005.1) of this division.(3)Follow neither paragraph (1) nor paragraph (2).5.Streamlined Sustainable Transportation Project Delivery Process1.Early Engagement and Initial Design19005.01.(a)The lead agency shall reimburse the third party for all reasonable third-party review activities required by the streamlined project delivery process outlined in this chapter. The lead agency and third party shall agree to a reasonable rate of reimbursement for staff time.(b)The lead agency shall designate a point of contact to engage with the relevant third-party staff.(c)The lead agency shall provide a notice to each third party it identified pursuant to Section 19004. The notice shall contain at least all of the following:(1)Lead agency name.(2)Name of the sustainable transportation project.(3)Name and contact information for the point of contact described in subdivision (b).(4)A brief description of the sustainable transportation project.(5)An online link to the sustainable transportation project website, if one exists.(6)The current environmental review status of the sustainable transportation project under the California Environmental Quality Act (Division 13 (commencing with Section 21000) of the Public Resources Code) and National Environmental Policy Act of 1969 (42 U.S.C 4321 et seq.).(7)A high-level description or map, or both, of the anticipated project right-of-way in third-party-located sections.(8)Any other conceptual plans or maps relevant to the third-party-located sections.(9)The lead agencys probable project delivery method.(10)Proposed date for an initial coordination meeting.(11)Proposed date for finalizing the Stage 1 project scope document.(12)Anticipated date for issuance of the notice required in subdivision (a) of Section 19005.02.(13)A declaration of whether or not the lead agency seeks entry into a cooperative agreement with the third party. This does not preclude the lead agency from seeking entry into a cooperative agreement at any time later in the project delivery process. This also does not preclude the lead agency from continuing to engage in the streamlined project delivery process set forth in this division.(d)The lead agency shall forward a copy of each notice described in subdivision (c) to the Transportation Agency. For those notices issued to a third party regulated by the Public Utilities Commission, the lead agency shall also forward the notice to the Public Utilities Commission.19005.01.1.(a)(1)Within 10 working days of transmittal of the notice described in subdivision (c) of Section 19005.01, the third party shall respond to the lead agency and confirm whether the notice described in subdivision (c) of Section 19005.01 was complete. If incomplete, it will describe what information is necessary for the notice to be complete.(2)In its response, the third party shall inform the lead agency if it wishes to enter into a cooperative agreement with the lead agency. This does not preclude the third party from seeking entry into a cooperative agreement with the lead agency at any time later in the project delivery process.(b)The lead agency shall submit the information identified in subdivision (a) to make the notice described in subdivision (c) of Section 19005.01 complete, and the third party shall be required to review the notice for completeness pursuant to subdivision (a) of this section.(c)(1)No sooner than 5 working days and no later than 20 working days, or a different date as mutually agreed to by the lead agency and third party, after the third party finds the notice described in subdivision (c) of Section 19005.01 complete pursuant to subdivision (a) of this section, the lead agency shall convene the initial coordinating meeting described in paragraph (10) of subdivision (c) of Section 19005.01.(2)The third party may request a reasonable extension to the deadline to have the initial coordination meeting, which the lead agency shall reasonably accommodate. If the initial coordination meeting does not occur within 20 working days of delivery, or as otherwise mutually agreed to by the lead agency and third party, the requirement for the initial coordination meeting will be deemed met.(d)Within 10 working days after the third party confirms completeness of the notice described in subdivision (c) of Section 19005.01 pursuant to subdivision (a) of this section, it shall respond to the lead agency with all of the following:(1)Identification of any existing or planned third-party facilities in third-party-located sections of the sustainable transportation project that may conflict with the sustainable transportation project based on the level of information provided as required by this article. This requirement does not preclude the identification of additional conflicts as the lead agency updates the project scope, or advances design, in the third-party-located sections of the sustainable transportation project, provided that the identification of those third-party facilities is based on new information or design documentation from the lead agency and the third party could not have reasonably anticipated the conflicting facility with information previously provided by the lead agency.(2)Any as-built plans, utility maps, or other drawings and information regarding the conflicting third-party facilities that it is otherwise legally permitted by federal and state law to provide to the lead agency.(3)A written checklist of any information or documents necessary to review and approve preliminary and final designs necessary for facility rearrangements. This does not preclude the identification of additional information or documents necessary to review and approve preliminary and final designs as the lead agency updates the project scope, or advances design, in the third-party-located sections of the sustainable transportation project.(e)Failure of the third party to respond pursuant to subdivision (d) of Section 19005.01 shall relieve the lead agency of the responsibility to include the third partys information required by subdivision (d) of Section 19005.01 in the draft Stage 1 project scope document specified in subdivision (a) of Section 19005.01.2.(f)At its discretion, the lead agency may still include information provided in subdivision (d) of Section 19005.01 if provided by the third party after the deadline and prior to the completion of the draft Stage 1 project scope specified in subdivision (a) of Section 19005.01.2.(g)The lead agency shall submit advanced conceptual engineering design documentation for the sustainable transportation project. No later than 20 working days, or a different date as mutually agreed to by the lead agency and third party, after the lead agency submits advanced conceptual engineering design documentation, the lead agency will convene a preliminary design workshop. The third party may request a reasonable extension to the deadline to have the preliminary design workshop, which the lead agency shall reasonably accommodate. If the preliminary design workshop does not occur within 20 working days of delivery, or as otherwise mutually agreed to by the lead agency and third party, the requirement for the initial coordination meeting will be deemed met. In the preliminary design workshop, the lead agency and third party shall discuss all of the following:(1)The key aspects of the design or construction of the sustainable transportation project that impact the scope, objective standards, criteria, specifications, or requirements for those proposed facility rearrangements that form or are intended to form the basis of the project scope. Those shall include all of the following:(A)Any facility rearrangements which are necessary for the sustainable transportation project to comply with applicable law.(B)Any facility rearrangements which are necessary for the lead agency or third party to construct, operate, maintain, or remove for the sustainable transportation project.(C)Any new and required third-party facilities which are necessary to install in order for the sustainable transportation project to comply with applicable law and for any facility rearrangements to comply with applicable law and third-party objective standards, criteria, specifications, or requirements.(D)Any deviations from the third-party standards or design and construction requirements mutually agreed to by the lead agency and third party.(2)Identification of betterments.(3)Initial identification of utility conflicts.(A)The third party shall provide the lead agency with any location data or other information already in its possession regarding the location of utilities within the third-party-located section of the sustainable transportation project.(B)Discussion of objections by the lead agency to third-party standards on the basis of the standard being adopted, amended, supplemented, or applied, for the sole or primary purpose of affecting one or more sustainable transportation projects, or requests for deviations from third-party standards.(C)Construction requirements for delivery of the sustainable transportation project.(4)Anticipated schedule and timeline for project delivery activities, including the following:(A)Key milestones for percentage of design completion when the lead agency shall submit the design documentation described in subparagraphs (B) to (D), inclusive.(B)When the lead agency shall submit design documentation for each identified facility rearrangement.(C)Whether the lead agencys submission of design documentation for any given facility rearrangement shall be segmented into the submission of design documentation for more than one advanced partial design unit, and what the schedule of submission by the lead agency of each advanced partial design unit to the third party shall be.(D)When, provided timely submittal by the lead agency of the design documentation as identified in subparagraphs (B) and (C), the third party shall return comments on each design documentation and advanced partial design unit for each submission identified in subparagraphs (B) and (C), respectively, for each facility rearrangement.(E)Anticipated schedule for right-of-way acquisition, construction, testing, and commissioning, of the third-party-located section or sections of the sustainable transportation project.(h)Within 30 working days of the workshop described in subdivision (g), the third party shall submit in writing to the lead agency all written comments regarding the topics described in subdivision (g).19005.01.2.(a)(1)Following receipt of the comments described in subdivision (h) of Section 19005.01.1, and as informed by the information provided by each third party that the lead agency is required to engage with pursuant to this chapter, the lead agency shall prepare a draft Stage 1 project scope document. The document shall include the draft project scope, including all identified facility rearrangements, utility adjustments, and betterments, as determined by the early engagement required pursuant to this chapter. The document shall also include the lead agencys probable project delivery method, anticipated schedule of design, right-of-way acquisition, and construction activities, and as-built plans for third-party facilities or utilities, as applicable.(2)The lead agency shall circulate the draft Stage 1 project scope document to each third party for review.(3)Each third party shall have 60 working days to review the draft Stage 1 project scope document to confirm all the relevant information and comments are included and shall provide any additional comments on the document.(4)Failure of the third party to respond to the relevant information within the expected timeframe shall be considered confirmation that all relevant information provided by the third party pursuant to this chapter was accounted for.(b)(1)After the 60-working-day circulation period, the lead agency shall finalize the Stage 1 project scope document and circulate the final document with each identified third party, the Transportation Agency, and, if relevant, the Public Utilities Commission. The lead agency shall record any additional comments provided by the third party pursuant to subdivision (a) in the record of the final Stage 1 project scope, and may incorporate any of those comments into the final Stage 1 project scope at its discretion.(2)The finalized Stage 1 project scope document shall identify matters or issues not yet resolved between the lead agency and each third party. This may include any comments provided by each third party pursuant to paragraph (3) of subdivision (a) that the lead agency did not incorporate into the project scope at its discretion.(3)The Transportation Agency shall develop a standardized form for the relevant fields required by this section, and other relevant fields determined by the Transportation Agency, for the finalized Stage 1 project scope document.(c)If more than two years transpires between the time the lead agency received responses from all relevant third parties pursuant to subdivision (h) of Section 19005.01.1 and the lead agency takes the step in subdivision (b) of this section, the lead agency shall be required to repeat the steps in this section, including reaching out to third parties it already received responses from pursuant to this section.2.Design Engineering and Design Review19005.02.(a)After the lead agency finalizes the Stage 1 project scope document pursuant to the requirements of Stage 1, the lead agency shall provide a notice to the third party of its intent to prepare and submit Stage 2 design documentation, whether through its own staff or through procurement of design services, to the third party for its review, based on the requirements stipulated in the finalized Stage 1 project scope document.(b)The standards, criteria, and specifications adopted by the third party at the time the lead agency transmits the notice described in subdivision (a) shall be the applicable standards, criteria, and specifications that the third party shall use when reviewing, commenting, and approving Stage 2 design documentation, except where the lead agency and third party have mutually agreed to deviate from those standards, criteria, and specifications.(c)The lead agency shall be responsible for ensuring that it submits design documentation, including advanced partial design units, consistent with the level of detail required for that level of design development identified in the schedule included in the finalized Stage 1 project scope document, and the third party is responsible for reviewing submitted design documentation, including advanced partial design units, for compliance with the applicable third-party standards as agreed to in the finalized Stage 1 project scope document. The lead agency shall also ensure that each submission of design documentation, including advanced partial design units, identifies any material amendments made since any earlier submittal of that design documentation or advanced partial design unit.(d)Within 10 working days, or as otherwise prescribed in the schedule identified in the finalized Stage 1 project scope document, of receipt of design documentation or advanced partial design unit, the third party shall review each submission of design documentation or advanced partial design unit, and inform the lead agency if the submission does not meet appropriate agreed-upon design requirements, relevant third-party standards, or the scope, criteria, specifications, and requirements for the applicable facility rearrangements.(e)If the third party is reasonably able to commence its review of the design documentation or advanced partial design unit absent resubmitted materials from the lead agency, it shall do so.(f)The lead agency shall promptly resubmit the design documentation or advanced partial design unit and correct the deficiencies identified by the third party pursuant to subdivision (d). The third party shall review the documentation for completeness pursuant to subdivision (d).(g)If the third party does not deliver a notice of incomplete information pursuant to subdivision (d), the submission of design documentation or advanced partial design unit shall be deemed complete and acceptable for the purposes of design review.(h)(1)Once the design documentation or advanced partial design unit is considered complete pursuant to subdivision (d), the third party shall review it in accordance with the schedule identified in the finalized Stage 1 project scope document.(2)If the lead agency believes a third partys comment on the design of the sustainable transportation project that was not already identified as constituting a facility rearrangement or modification to the design documentation or advanced partial design unit that constitutes a betterment constitutes a betterment, it shall notify the third party of that within 20 working days of receipt of those comments.(3)Within 20 working days of this notice, the third party shall do one of the following:(A)Withdraw or amend the relevant comment.(B)Acknowledge the comment as a betterment.(C)Dispute the basis of the betterment. If the lead agency and third party cannot agree as to whether the facility is a betterment, the issue shall be resolved through the binding dispute resolution process described in Section 19003.(4)If the third party fails to respond within 20 working days of the notice, the comment shall be considered a betterment.(i)For all review of design documentation or advanced partial design units that require final approval by the third party, the third party shall determine the completeness of the design documentation, complete its review and do all of the following pursuant to the schedule identified in the Stage 1 project scope document, or as otherwise agreed between the parties:(1)Issue comments.(2)Confirm approval or rejection of final design documentation.(3)The third party may only reject the final design documentation if the documentation is incomplete or fails to comply with the requirements of this part. The third party must provide comments on the design documentation documenting the reason for the rejection pursuant to this part.(j)The lead agency must respond to a third-party rejection of final design documentation in one of the following ways:(1)Address the comments provided pursuant to paragraph (3) of subdivision (i) and resubmit the design documentation or advanced partial design unit.(2)Notify the third party that it objects to the rejection. If the third party and lead agency are unable to mutually agree on a path forward to a modification to the design to address the rejection, the issue shall be resolved through the binding dispute resolution process in Section 19003.(k)For design documentation or advanced partial design units described in subdivision (i), the third party shall not raise any new issues, or make any comments, which are inconsistent with its comments on earlier submittals, or with any changes already agreed to by the third party.(l)The third party shall not withhold approval of design documentation or advanced partial design units described in subdivision (i) if the submittal is complete and consistent with the most recent prior submittal for such facility rearrangement, modified as appropriate to respond to the third partys comments to such prior submittal, to the extent those comments were made pursuant to the requirements of this stage, and to reflect any subsequent changes agreed to by the lead agency and the third party.(m)The third party may raise new comments on design documentation or advanced partial design units described in subdivision (i) as a consequence of design changes made by the lead agency after the third partys review of the most recent prior submittal of designs for such rearrangement.(n)A betterment shall not be required to be constructed if it is not approved by the lead agency. The lead agency shall have a right to refuse a betterment that meets any of the following:(1)The betterment is incompatible with the sustainable transportation project.(2)The betterment cannot be constructed within the constraints of applicable law or the project schedule.(3)The betterment is a facility rearrangement that is requested after the finalization of the Stage 1 project scope document, unless the facility rearrangement was requested in accordance with the third partys objective standards, criteria, and specifications in effect at the time of the notice described in subdivision (a), and was requested in response to new information that was not available to the third party during the Stage 1 process.The cost of approved betterments shall be borne by the third party. This includes any increase in costs over the estimation of the cost of the betterment by the lead agency and cost of any mitigations of the betterment required as a result of the environmental review process.3.Permitting and Construction19005.03.(a)An approved-for-construction design is a design that meets all of the following:(1)The lead agency has approved the final design documentation.(2)The third party has approved the final design documentation.(3)The final design document has been signed and sealed by the engineer of record that is responsible for that final design documentation.(4)Any other conditions for the final design documentation to be ready for construction set out under the requirements of this act have been satisfied.(b)Commencement of a single or set of facility rearrangements for which an advanced partial design unit is at the final design stage may be approved for construction without all of the final design being approved for construction.(c)Prior to the commencement of construction of a facility rearrangement, the lead agency shall transmit a proposed construction staging plan for any construction work to be performed within the public rights-of-way in the third partys jurisdiction. The plan shall include, but not be limited to:(1)The handling of vehicular and pedestrian traffic, cyclist access, and circulation on streets adjacent to the construction with the construction phasing showing street closures, detours, warning devices, and temporary traffic signals.(2)Accessible routes for pedestrians with physical disabilities in compliance with applicable law.(3)Actions to maintain access to businesses, schools, and residences adjacent to the construction areas, as possible, and actions to ensure safe access and circulation for pedestrians and vehicular traffic as described in the traffic management plan.(4)Elements of public awareness as well as mechanisms to assist affected parties in complaint resolutions.(d)The third party shall review the submitted construction staging plan in accordance with its objective design standards and policies for such construction staging plans, and respond to the lead agency with a determination of whether the plan is complete or not. If incomplete, the third party will notify the lead agency of what aspects of the construction staging plan must be refined in order for the construction staging plan to be complete pursuant to the third partys applicable standards and policies. This response shall occur within 10 working days of receipt of the notice described in subdivision (c).(e)The lead agency shall promptly modify the construction staging plan based on the information cited in subdivision (d) and resubmit it to the third party. The third party shall review the resubmittal for completeness pursuant to subdivision (d).(f)Within 10 working days of the acknowledgment of completeness identified in subdivision (d), the third party shall provide comments, approve, or reject the construction staging plan.(g)The lead agency may update the construction staging plan after it has been approved by the third party and must promptly submit each updated construction staging plan to the third party for review in accordance with subdivision (d).(h)The third party shall impose only the minimum requirements for traffic management planning and construction sequencing that are necessary in order to provide for public health and safety, including, but not limited to, pedestrian and vehicular safety, and functionality, including, but not limited to, public and business access and circulation. This does not preclude the lead agency and third party from agreeing to additional traffic management planning and construction sequencing activities.(i)The lead agency shall provide 10 working days of advance written notice where construction work is to be performed in the public rights-of-way for approved street, traffic lane, or sidewalk closures.(j)If the lead agency fails to perform any construction work within the third partys public rights-of-way in accordance with the approved-for-construction final design documentation or construction staging plans approved by the third party pursuant to this section, the third party may issue a written notice of noncompliance from the third party and the lead agency must cure the noncompliance. If the lead agency and third party are unable to agree whether the work was performed correctly, the dispute shall be resolved via the binding dispute resolution process outlined in Section 19003.(k)For third-party communication facilities, the lead agency and third party shall agree to a schedule for such work that balances minimal system downtime and third-party network disruption while maintaining a reasonable project schedule. If the lead agency and third party are unable to agree on such a schedule, the matter will be resolved by the binding dispute resolution process described in Section 19003.(l)(1)A third party shall not unreasonably withhold the approval of the availability, location, and duration of the use of a third-party facility as a temporary facility to facilitate the construction of the sustainable transportation project, as otherwise permitted by state and federal law. Such approved use of a third-party facility shall be made in writing and without cost to the lead agency.(2)Upon completion of the related construction and lead agencys determination that the temporary facilities are no longer needed, the lead agency shall remove all temporary facilities and restore the area as nearly as practicable to its original condition unless the lead agency and third party agree to another arrangement.(3)If the lead agency believes that a third party is unreasonably withholding the approvals described in this subdivision and is unable to come to agreement with the third party on these approvals, it may elect to resolve the dispute through the binding dispute resolution process described in Section 19003.(m)For any other third-party permit or approval, identified in the finalized Stage 1 project scope document as necessary for the lead agency to construct the sustainable transportation project as identified in the project schedule, the lead agency shall submit a completed permit or approval request to the third party.(n)Within 10 working days of receipt of the permit or approval request, the third party shall review the permit or approval request in accordance with its objective standards and determine whether the permit or approval request is complete. If incomplete, the third party shall respond to the lead agency and notify the lead agency of what information is needed to make the request complete.(o)If determined incomplete pursuant to subdivision (n), the lead agency shall promptly respond with the relevant information noted by the third party in subdivision (n). The third party shall review the permit or approval request and respond to the lead agency pursuant to subdivision (n).(p)Within 20 working days of determining the request complete pursuant to subdivision (n), the third party shall review the relevant permit for compliance with all relevant written objective standards, specifications, and criteria that are applicable to the permit or approval request, or have been agreed to between the lead agency and third party, and shall grant approval of the permit or approval request, issue comments, or reject the permit or approval request.(q)The permit request may only be rejected for failure to meet the relevant objective standards, criteria, or specifications that apply to that permit or approval and are consistent with this section.SEC. 3.Chapter 6 (commencing with Section 185520) is added to Division 19.5 of the Public Utilities Code, to read:6.Regulations Governing Third-Party Permits and Approvals185520.For purposes of this chapter, the following definitions apply:
(a)Electrical corporation has the same meaning as defined in Section 218.
(b)Gas corporation has the same meaning as defined in Section 222.
(c)High-speed rail project means the portion of the high-speed rail project identified in paragraph (2) of subdivision (b) of Section 2704.04 of the Streets and Highways Code.
(d)Third party means a local agency or utility, including, but not limited to, an electrical corporation, gas corporation, local publicly owned utility, or private telecommunications provider.
185522.On or before January 1, 2026, the authority shall develop and adopt regulations setting forth requirements governing third-party permits and approvals that are necessary to deliver the high-speed rail project. The authority shall ensure that the regulations do all of the following:
(a)Require early engagement between third parties and the authority.
(b)Identify the circumstances under which the authority shall seek to enter into a cooperative agreement with each applicable third party that serves as the framework for all future project interactions between and among the authority and each applicable third party and, where relevant, identifies who is responsible for specific utility relocations and the costs associated with those relocations. A cooperative agreement shall define the roles and responsibilities of the authority and each applicable third party and clarify lines of communication so the decisionmaking process is understood.
(c)Require regular meetings with third parties during the planning, design, and construction phases.
(d)Require the authority to establish cost estimates with conservative contingency budgets for each utility relocation and to not oversimplify the utility costs and potential risks by bundling those costs into a single item.
(e)Require regular communication and documentation of contracting terms, conditions, and decisions during construction.
(f)Define options that can govern a third-party review process for permits and approvals.
(g)Consider ways to reduce permitting and approval delays.
(h)Establish a binding dispute resolution process.
(i)Exempt gas corporations and electrical corporations regulated by the Public Utilities Commission from the dispute resolution process established pursuant to subdivision (h).
(j)Prohibit third-party entities from insisting on exactions or betterments from the authority that are unrelated to ensuring that health and safety standards are met, unless otherwise stipulated by a cooperative agreement, as a condition for permits and approvals.
(k)Consider reimbursement of third-party staff time and third-party time and materials to relocate the utility.
(l)Define the terms betterment and cooperative agreement for purposes of the regulation.
185524.(a)In developing the regulations required pursuant to Section 185522, the authority shall consult with all of the following entities:
(1)The Department of Transportation.
(2)The Public Utilities Commission.
(3)Local government stakeholders.
(4)Local publicly owned utilities, gas corporations, and electrical corporations.
(5)Water districts.
(6)Telecommunications companies.
(7)Passenger and freight railroads.
(8)Any other relevant entity identified by the authority that has expertise in transportation infrastructure project delivery.
(b)Before adopting the regulations required pursuant to Section 185522, the authority shall hold at least two public hearings regarding the proposed regulations.
185526.(a)The authority shall post a public notice on its internet website when it adopts the regulations required pursuant to Section 185522. The authority shall not enter into a third-party agreement governed by this chapter until 30 days after the public notice is posted.
(b)The authority shall not implement regulations adopted pursuant to this chapter unless it completes the development and implementation of a process to review third-party agreements in a timely manner as recommended by the High-Speed Rail Authority Office of the Inspector General in Recommendation 25-R-02-02.
185528.This chapter shall become inoperative on the date that the High-Speed Rail Authority Office of the Inspector General submits a report pursuant to Section 187040, and, as of January 1 of the following year, is repealed.
SEC. 4.Section 187040 is added to the Public Utilities Code, to read:187040.(a)For purposes of determining the continued operation of Chapter 6 (commencing with Section 185520) of Division 19.5, when the office determines that the high-speed rail project, as defined in Section 185520, is complete, the office shall submit a report to the Legislature informing the Legislature of that fact.
(b)The report to be submitted pursuant to subdivision (a) shall be submitted in compliance with Section 9795 of the Government Code.
SEC. 5.The provisions of this measure are severable. If any provision of this measure or its application is held invalid, that invalidity shall not affect other provisions or applications that can be given effect without the invalid provision or application.
SEC. 6.The Legislature finds and declares that sustainable transportation projects foster the movement of people on a local and regional level for the benefit of the entire state and, for that reason, authorizing the Secretary of Transportation to expedite the implementation of sustainable transportation projects by waiving local regulation of the design and construction of those projects is a matter of statewide concern and is not a municipal affair as that term is used in Section 5 of Article XI of the California Constitution. Therefore, Sections 3 and 4 of this act adding Section 13985 to the Government Code and adding Division 21 (commencing with Section 19001) to the Public Utilities Code, respectively, apply to all cities, including charter cities.SEC. 7.SEC. 6.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
This act shall be known, and may be cited, as the Sustainable Transportation Project Delivery Reform Act.
SEC. 2.The Legislature finds and declares all of the following:
(a)Sustainable transportation projects are critical for the growth of the state in a manner that reduces greenhouse gas emissions and helps address the states housing shortage.
(b)Third-party permits and approvals for preconstruction and construction activities, including utility relocations, design review, and issuance of encroachment or other similar permits, can be a source of delay for sustainable transportation projects, potentially resulting in cost escalations and projects being built late and over budget.
SEC. 3.Section 13985 is added to the Government Code, to read:13985.(a)The secretary may grant a waiver to a local agency that is seeking to design and construct a sustainable transportation project from any standards, criteria, specifications, requirements, or other conditions of a third party applicable to the sustainable transportation project if the secretary determines that granting the waiver will assist the local agency in delivering the sustainable transportation project in a cost-efficient and timely manner.
(b)The agency shall develop an application for local agencies to seek a waiver described in subdivision (a).
(c)For purposes of this section, the following definitions apply:
(1)Local agency has the same meaning as defined in Section 19001 of the Public Utilities Code.
(2)Sustainable transportation project has the same meaning as defined in Section 19001 of the Public Utilities Code.
(3)Third party has the same meaning as defined in Section 19001 of the Public Utilities Code.
SEC. 4.Division 21 (commencing with Section 19001) is added to the Public Utilities Code, to read:21.Sustainable Transportation Project Delivery Requirements1.Definitions19001.For purposes of this division, the following definitions shall apply:
(a)Advanced partial design unit means a portion of the design documentation for a facility rearrangement submitted to the third party for review and approval prior to submittal or approval of completed design documentation for that facility rearrangement.
(b)(1)Betterment means work performed for a facility rearrangement that comprises an upgrade, change, or addition to a third-party facility, or to part of a third-party facility, that is requested by the third party, that provides for greater capacity, capability, durability, appearance, efficiency, or function or for another improvement of that third-party facility over that which is currently provided by the third-party facility, and that satisfies at least either of the following:
(A)The third-party objective standards or third-party design and construction requirements applicable to that work are changed or supplemented after the date of the notice required by subdivision (a) of Section 19005.02.
(B)Any other criteria, specifications, and requirements for facility rearrangements that the lead agency and third party mutually agree to are changed or supplemented after the date of the notice described in subdivision (c) of Section 19005.01.
(2)Betterment shall exclude all of the following:
(A)An upgrade, change, or addition to which the lead agency and third party agree will be of direct and principal benefit to the construction, operation, or maintenance of the sustainable transportation project.
(B)An upgrade, change, or addition resulting from design or construction in accordance with the applicable third-party standards as of the date of the notice described in subdivision (a) of Section 19005.02, to the extent those third-party standards have not been adopted by the third party in breach of subdivision (f) of Section 19002.
(C)An upgrade, change, or addition resulting from design or construction in accordance with the criteria, specifications, and requirements mutually agreed to and documented in the Stage 1 project scope document required by Stage 1.
(D)Measures to mitigate environmental impacts required by a final environmental document pursuant to the California Environmental Quality Act (Division 13 (commencing with Section 21000) of the Public Resources Code) or National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.).
(E)Replacement of devices or materials no longer regularly manufactured with the next highest grade or size.
(F)An upgrade, change, or addition that is the consequence of changes made by the lead agency after the finalization of the Stage 1 project document for the sustainable transportation project.
(c)Cooperative agreement means an agreement between a lead agency and one or more third parties establishing the entities respective obligations, roles and responsibilities, and processes and procedures to support the efficient, timely, and safe delivery of one or more sustainable transportation projects. The agreements provisions shall include, but are not limited to, the following:
(1)Duration and scope of the agreement.
(2)Governance for executing the cooperative agreement.
(3)Provisions for cooperation and coordination to identify utility conflicts and ensure utility owners implement utility adjustments required to address utility conflicts.
(4)Early involvement and coordination.
(5)Responsibilities for design and construction.
(6)Procedures for issue resolution.
(7)Clear establishment of permitting or approval processes for facility rearrangements.
(8)Evaluation of betterments within the project scope.
(9)Inspection of work completed in compliance with applicable standards.
(d)Coordination meeting means an informal meeting for the lead agency and third party to discuss the sustainable transportation project.
(e)Design documentation means all specifications, reports, studies, working drawings, shop drawings, calculations, electronic files, records, submittals, and drawings, including plans, profiles, cross sections, notes, elevations, typical sections, details, and diagrams, that are necessary for, or related to, the design of facility rearrangements.
(f)Facility rearrangement means the removal, restoration, alteration, reconstruction, support, or relocation of all or a portion of a third-party facility.
(g)Final design documentation means design documentation for a facility rearrangement that is at 100-percent design level. Elements of final design documentation include final construction drawings, including plans, profiles, cross sections, notes, elevations, typical sections, details, diagrams, design criteria, specifications, reports, studies, calculations, electronic files, and other records.
(h)Stage 1 means the process set forth in Article 1 (commencing with Section 19005.01) of Chapter 5 of this division.
(i)Stage 1 design documentation means the design documentation required to be prepared in Stage 1, representing up to 15-percent design level.
(j)Stage 2 means the process set forth in Article 2 (commencing with Section 19005.02) of Chapter 5 of this division.
(k)Stage 2 design documentation means the design documentation required to be prepared in Stage 2, which advances design documentation from the design level required in Stage 1 design documentation, which is up to a 15-percent design level, to a 100-percent design level.
(l)Sustainable transportation project means a project that consists of one or more of the following:
(1)Any project identified in subdivision (b) of Section 21080.25 of the Public Resources Code.
(2)A project whose primary purpose is the institution or improvement of public transit infrastructure, including, but not limited to, transit priority facilities, bus service, bus rapid transit, and passenger rail. For purposes of this paragraph, passenger rail includes, but is not limited to, light rail, commuter rail, regional rail, intercity rail, or heavy rail. Heavy rail includes rail transit, as defined in Section 99602.
(m)Third party means a local agency or utility, including, but not limited to, an electrical corporation, public utility, or private telecommunications provider.
(n)Third-party facility means a facility owned by a third party.
(o)Lead agency means the public agency which has the principal responsibility for carrying out or approving a project. Lead agency also includes other parties whose services are procured by the lead agency, including, but not limited to, a private contractor or consultant.
(p)Local agency means any public agency other than a state agency.
(q)Third-party-located section means a portion of a sustainable transportation project that is located in the right-of-way of a third party.
(r)Working day means any date that is not a Saturday, Sunday, or federal or state holiday.
2.Transparent Objective Permitting and Approval Standards19002.(a)By July 1, 2026, a third party shall publish online a list of every permit or approval that it may require for a facility rearrangement. For each permit or approval, it shall publish online all objective standards, criteria, specifications, and requirements used by the third party when evaluating requests by lead agencies for delivery of facility rearrangements. These permits or approvals may include, but are not limited to, the following:
(1)An encroachment permit.
(2)A grading permit.
(3)A tree removal permit.
(4)A stormwater permit.
(5)Construction staging plan approval.
(b)If the third party modifies any of the above required permits or approvals, or objective standards, criteria, specifications, and requirements used by the third party when evaluating requests by lead agencies for delivery of facility rearrangements, the third party shall publish the modifications online promptly, but no later than within 15 working days of any modifications.
(c)Except as otherwise provided by this division, a third party shall not inhibit a lead agencys delivery of a facility rearrangement that is consistent with the applicable objective standards, criteria, specifications, and requirements for permits or approvals it is required to identify pursuant to subdivision (a).
(d)A third party shall not establish any standards, criteria, specifications, or requirements that are not objective in nature for purposes of evaluating requests by lead agencies for delivery of facility rearrangements.
(e)Nothing in this act prohibits a lead agency and third party from mutually agreeing to construction conditions or facility rearrangements that are inconsistent with the applicable objective standards, criteria, specifications, and requirements for permits or approvals it is required to identify pursuant to subdivision (a).
(f)A third party shall not adopt any new third-party standards or otherwise apply, amend, or supplement any existing third-party standards for the sole or primary purpose of affecting one or more sustainable transportation projects.
3.Binding Dispute Resolution19003.(a)If a third party does not issue a permit or approval to a lead agency, or does not take any other action that is necessary to facilitate the delivery of part or all of a sustainable transportation project, the lead agency may elect to invoke the binding dispute resolution process described in subdivision (b).
(b)The following binding dispute resolution process shall be administered by the Transportation Agency, which shall determine the schedule and duration of binding dispute resolution activities pursuant to this subdivision:
(1)The state transportation agency shall designate a neutral mediator to work with the lead agency and third party to resolve the dispute or disputes that caused the lead agency to invoke the binding dispute resolution process described in this subdivision. If the dispute or disputes that caused the lead agency to invoke the binding dispute resolution process described in this subdivision involve matters related to utilities, the Public Utilities Commission shall designate an advisor with relevant experience to provide technical assistance to the neutral mediator for utility-related disputes. The resolution shall be recorded in a binding settlement agreement.
(2)For the dispute or disputes that caused the lead agency to invoke the binding dispute resolution process described in this subdivision that were unresolved after the process described in paragraph (1), the neutral mediator shall become a neutral arbitrator, and shall resolve the remaining dispute or disputes following the arbitration processes described in Title 9 (commencing with Section 1280) of Part 3 of the Code of Civil Procedure, except as otherwise provided for in this subdivision.
(3)The decision of the arbitrator shall be binding upon the lead agency and third party.
(4)By mutual agreement, the lead agency and third party may select a different entity to serve as the neutral mediator and arbitrator pursuant to this subdivision.
(5)By mutual agreement, the lead agency and third party may instead undergo the process described in paragraph (2), followed by the process described in paragraph (1). The judgment of the neutral arbitrator pursuant to paragraph (2) shall be sealed, and only unsealed and made binding if the subsequent process described in paragraph (1) does not result in resolution of the dispute or disputes.
4.Pathways for Sustainable Transportation Project Delivery19004.(a)Once a lead agency is ready to transmit the notice described in subdivision (c) of Section 19005.01 for a specific sustainable transportation project, the lead agency shall compile a list of all third parties that it reasonably expects it will need to get permits or approvals from, or otherwise coordinate with, in order to deliver facility rearrangements.
(b)Once the lead agency has compiled the list pursuant to subdivision (a), it shall elect one of the following courses of action for engagement with each listed third party:
(1)Enter into a cooperative agreement related to the sustainable transportation project if it has not done so already.
(2)Commence the streamlined project delivery process described in Chapter 5 (commencing with Section 19005.1) of this division.
(3)Follow neither paragraph (1) nor paragraph (2).
5.Streamlined Sustainable Transportation Project Delivery Process1.Early Engagement and Initial Design19005.01.(a)The lead agency shall reimburse the third party for all reasonable third-party review activities required by the streamlined project delivery process outlined in this chapter. The lead agency and third party shall agree to a reasonable rate of reimbursement for staff time.
(b)The lead agency shall designate a point of contact to engage with the relevant third-party staff.
(c)The lead agency shall provide a notice to each third party it identified pursuant to Section 19004. The notice shall contain at least all of the following:
(1)Lead agency name.
(2)Name of the sustainable transportation project.
(3)Name and contact information for the point of contact described in subdivision (b).
(4)A brief description of the sustainable transportation project.
(5)An online link to the sustainable transportation project website, if one exists.
(6)The current environmental review status of the sustainable transportation project under the California Environmental Quality Act (Division 13 (commencing with Section 21000) of the Public Resources Code) and National Environmental Policy Act of 1969 (42 U.S.C 4321 et seq.).
(7)A high-level description or map, or both, of the anticipated project right-of-way in third-party-located sections.
(8)Any other conceptual plans or maps relevant to the third-party-located sections.
(9)The lead agencys probable project delivery method.
(10)Proposed date for an initial coordination meeting.
(11)Proposed date for finalizing the Stage 1 project scope document.
(12)Anticipated date for issuance of the notice required in subdivision (a) of Section 19005.02.
(13)A declaration of whether or not the lead agency seeks entry into a cooperative agreement with the third party. This does not preclude the lead agency from seeking entry into a cooperative agreement at any time later in the project delivery process. This also does not preclude the lead agency from continuing to engage in the streamlined project delivery process set forth in this division.
(d)The lead agency shall forward a copy of each notice described in subdivision (c) to the Transportation Agency. For those notices issued to a third party regulated by the Public Utilities Commission, the lead agency shall also forward the notice to the Public Utilities Commission.
19005.01.1.(a)(1)Within 10 working days of transmittal of the notice described in subdivision (c) of Section 19005.01, the third party shall respond to the lead agency and confirm whether the notice described in subdivision (c) of Section 19005.01 was complete. If incomplete, it will describe what information is necessary for the notice to be complete.
(2)In its response, the third party shall inform the lead agency if it wishes to enter into a cooperative agreement with the lead agency. This does not preclude the third party from seeking entry into a cooperative agreement with the lead agency at any time later in the project delivery process.
(b)The lead agency shall submit the information identified in subdivision (a) to make the notice described in subdivision (c) of Section 19005.01 complete, and the third party shall be required to review the notice for completeness pursuant to subdivision (a) of this section.
(c)(1)No sooner than 5 working days and no later than 20 working days, or a different date as mutually agreed to by the lead agency and third party, after the third party finds the notice described in subdivision (c) of Section 19005.01 complete pursuant to subdivision (a) of this section, the lead agency shall convene the initial coordinating meeting described in paragraph (10) of subdivision (c) of Section 19005.01.
(2)The third party may request a reasonable extension to the deadline to have the initial coordination meeting, which the lead agency shall reasonably accommodate. If the initial coordination meeting does not occur within 20 working days of delivery, or as otherwise mutually agreed to by the lead agency and third party, the requirement for the initial coordination meeting will be deemed met.
(d)Within 10 working days after the third party confirms completeness of the notice described in subdivision (c) of Section 19005.01 pursuant to subdivision (a) of this section, it shall respond to the lead agency with all of the following:
(1)Identification of any existing or planned third-party facilities in third-party-located sections of the sustainable transportation project that may conflict with the sustainable transportation project based on the level of information provided as required by this article. This requirement does not preclude the identification of additional conflicts as the lead agency updates the project scope, or advances design, in the third-party-located sections of the sustainable transportation project, provided that the identification of those third-party facilities is based on new information or design documentation from the lead agency and the third party could not have reasonably anticipated the conflicting facility with information previously provided by the lead agency.
(2)Any as-built plans, utility maps, or other drawings and information regarding the conflicting third-party facilities that it is otherwise legally permitted by federal and state law to provide to the lead agency.
(3)A written checklist of any information or documents necessary to review and approve preliminary and final designs necessary for facility rearrangements. This does not preclude the identification of additional information or documents necessary to review and approve preliminary and final designs as the lead agency updates the project scope, or advances design, in the third-party-located sections of the sustainable transportation project.
(e)Failure of the third party to respond pursuant to subdivision (d) of Section 19005.01 shall relieve the lead agency of the responsibility to include the third partys information required by subdivision (d) of Section 19005.01 in the draft Stage 1 project scope document specified in subdivision (a) of Section 19005.01.2.
(f)At its discretion, the lead agency may still include information provided in subdivision (d) of Section 19005.01 if provided by the third party after the deadline and prior to the completion of the draft Stage 1 project scope specified in subdivision (a) of Section 19005.01.2.
(g)The lead agency shall submit advanced conceptual engineering design documentation for the sustainable transportation project. No later than 20 working days, or a different date as mutually agreed to by the lead agency and third party, after the lead agency submits advanced conceptual engineering design documentation, the lead agency will convene a preliminary design workshop. The third party may request a reasonable extension to the deadline to have the preliminary design workshop, which the lead agency shall reasonably accommodate. If the preliminary design workshop does not occur within 20 working days of delivery, or as otherwise mutually agreed to by the lead agency and third party, the requirement for the initial coordination meeting will be deemed met. In the preliminary design workshop, the lead agency and third party shall discuss all of the following:
(1)The key aspects of the design or construction of the sustainable transportation project that impact the scope, objective standards, criteria, specifications, or requirements for those proposed facility rearrangements that form or are intended to form the basis of the project scope. Those shall include all of the following:
(A)Any facility rearrangements which are necessary for the sustainable transportation project to comply with applicable law.
(B)Any facility rearrangements which are necessary for the lead agency or third party to construct, operate, maintain, or remove for the sustainable transportation project.
(C)Any new and required third-party facilities which are necessary to install in order for the sustainable transportation project to comply with applicable law and for any facility rearrangements to comply with applicable law and third-party objective standards, criteria, specifications, or requirements.
(D)Any deviations from the third-party standards or design and construction requirements mutually agreed to by the lead agency and third party.
(2)Identification of betterments.
(3)Initial identification of utility conflicts.
(A)The third party shall provide the lead agency with any location data or other information already in its possession regarding the location of utilities within the third-party-located section of the sustainable transportation project.
(B)Discussion of objections by the lead agency to third-party standards on the basis of the standard being adopted, amended, supplemented, or applied, for the sole or primary purpose of affecting one or more sustainable transportation projects, or requests for deviations from third-party standards.
(C)Construction requirements for delivery of the sustainable transportation project.
(4)Anticipated schedule and timeline for project delivery activities, including the following:
(A)Key milestones for percentage of design completion when the lead agency shall submit the design documentation described in subparagraphs (B) to (D), inclusive.
(B)When the lead agency shall submit design documentation for each identified facility rearrangement.
(C)Whether the lead agencys submission of design documentation for any given facility rearrangement shall be segmented into the submission of design documentation for more than one advanced partial design unit, and what the schedule of submission by the lead agency of each advanced partial design unit to the third party shall be.
(D)When, provided timely submittal by the lead agency of the design documentation as identified in subparagraphs (B) and (C), the third party shall return comments on each design documentation and advanced partial design unit for each submission identified in subparagraphs (B) and (C), respectively, for each facility rearrangement.
(E)Anticipated schedule for right-of-way acquisition, construction, testing, and commissioning, of the third-party-located section or sections of the sustainable transportation project.
(h)Within 30 working days of the workshop described in subdivision (g), the third party shall submit in writing to the lead agency all written comments regarding the topics described in subdivision (g).
19005.01.2.(a)(1)Following receipt of the comments described in subdivision (h) of Section 19005.01.1, and as informed by the information provided by each third party that the lead agency is required to engage with pursuant to this chapter, the lead agency shall prepare a draft Stage 1 project scope document. The document shall include the draft project scope, including all identified facility rearrangements, utility adjustments, and betterments, as determined by the early engagement required pursuant to this chapter. The document shall also include the lead agencys probable project delivery method, anticipated schedule of design, right-of-way acquisition, and construction activities, and as-built plans for third-party facilities or utilities, as applicable.
(2)The lead agency shall circulate the draft Stage 1 project scope document to each third party for review.
(3)Each third party shall have 60 working days to review the draft Stage 1 project scope document to confirm all the relevant information and comments are included and shall provide any additional comments on the document.
(4)Failure of the third party to respond to the relevant information within the expected timeframe shall be considered confirmation that all relevant information provided by the third party pursuant to this chapter was accounted for.
(b)(1)After the 60-working-day circulation period, the lead agency shall finalize the Stage 1 project scope document and circulate the final document with each identified third party, the Transportation Agency, and, if relevant, the Public Utilities Commission. The lead agency shall record any additional comments provided by the third party pursuant to subdivision (a) in the record of the final Stage 1 project scope, and may incorporate any of those comments into the final Stage 1 project scope at its discretion.
(2)The finalized Stage 1 project scope document shall identify matters or issues not yet resolved between the lead agency and each third party. This may include any comments provided by each third party pursuant to paragraph (3) of subdivision (a) that the lead agency did not incorporate into the project scope at its discretion.
(3)The Transportation Agency shall develop a standardized form for the relevant fields required by this section, and other relevant fields determined by the Transportation Agency, for the finalized Stage 1 project scope document.
(c)If more than two years transpires between the time the lead agency received responses from all relevant third parties pursuant to subdivision (h) of Section 19005.01.1 and the lead agency takes the step in subdivision (b) of this section, the lead agency shall be required to repeat the steps in this section, including reaching out to third parties it already received responses from pursuant to this section.
2.Design Engineering and Design Review19005.02.(a)After the lead agency finalizes the Stage 1 project scope document pursuant to the requirements of Stage 1, the lead agency shall provide a notice to the third party of its intent to prepare and submit Stage 2 design documentation, whether through its own staff or through procurement of design services, to the third party for its review, based on the requirements stipulated in the finalized Stage 1 project scope document.
(b)The standards, criteria, and specifications adopted by the third party at the time the lead agency transmits the notice described in subdivision (a) shall be the applicable standards, criteria, and specifications that the third party shall use when reviewing, commenting, and approving Stage 2 design documentation, except where the lead agency and third party have mutually agreed to deviate from those standards, criteria, and specifications.
(c)The lead agency shall be responsible for ensuring that it submits design documentation, including advanced partial design units, consistent with the level of detail required for that level of design development identified in the schedule included in the finalized Stage 1 project scope document, and the third party is responsible for reviewing submitted design documentation, including advanced partial design units, for compliance with the applicable third-party standards as agreed to in the finalized Stage 1 project scope document. The lead agency shall also ensure that each submission of design documentation, including advanced partial design units, identifies any material amendments made since any earlier submittal of that design documentation or advanced partial design unit.
(d)Within 10 working days, or as otherwise prescribed in the schedule identified in the finalized Stage 1 project scope document, of receipt of design documentation or advanced partial design unit, the third party shall review each submission of design documentation or advanced partial design unit, and inform the lead agency if the submission does not meet appropriate agreed-upon design requirements, relevant third-party standards, or the scope, criteria, specifications, and requirements for the applicable facility rearrangements.
(e)If the third party is reasonably able to commence its review of the design documentation or advanced partial design unit absent resubmitted materials from the lead agency, it shall do so.
(f)The lead agency shall promptly resubmit the design documentation or advanced partial design unit and correct the deficiencies identified by the third party pursuant to subdivision (d). The third party shall review the documentation for completeness pursuant to subdivision (d).
(g)If the third party does not deliver a notice of incomplete information pursuant to subdivision (d), the submission of design documentation or advanced partial design unit shall be deemed complete and acceptable for the purposes of design review.
(h)(1)Once the design documentation or advanced partial design unit is considered complete pursuant to subdivision (d), the third party shall review it in accordance with the schedule identified in the finalized Stage 1 project scope document.
(2)If the lead agency believes a third partys comment on the design of the sustainable transportation project that was not already identified as constituting a facility rearrangement or modification to the design documentation or advanced partial design unit that constitutes a betterment constitutes a betterment, it shall notify the third party of that within 20 working days of receipt of those comments.
(3)Within 20 working days of this notice, the third party shall do one of the following:
(A)Withdraw or amend the relevant comment.
(B)Acknowledge the comment as a betterment.
(C)Dispute the basis of the betterment. If the lead agency and third party cannot agree as to whether the facility is a betterment, the issue shall be resolved through the binding dispute resolution process described in Section 19003.
(4)If the third party fails to respond within 20 working days of the notice, the comment shall be considered a betterment.
(i)For all review of design documentation or advanced partial design units that require final approval by the third party, the third party shall determine the completeness of the design documentation, complete its review and do all of the following pursuant to the schedule identified in the Stage 1 project scope document, or as otherwise agreed between the parties:
(1)Issue comments.
(2)Confirm approval or rejection of final design documentation.
(3)The third party may only reject the final design documentation if the documentation is incomplete or fails to comply with the requirements of this part. The third party must provide comments on the design documentation documenting the reason for the rejection pursuant to this part.
(j)The lead agency must respond to a third-party rejection of final design documentation in one of the following ways:
(1)Address the comments provided pursuant to paragraph (3) of subdivision (i) and resubmit the design documentation or advanced partial design unit.
(2)Notify the third party that it objects to the rejection. If the third party and lead agency are unable to mutually agree on a path forward to a modification to the design to address the rejection, the issue shall be resolved through the binding dispute resolution process in Section 19003.
(k)For design documentation or advanced partial design units described in subdivision (i), the third party shall not raise any new issues, or make any comments, which are inconsistent with its comments on earlier submittals, or with any changes already agreed to by the third party.
(l)The third party shall not withhold approval of design documentation or advanced partial design units described in subdivision (i) if the submittal is complete and consistent with the most recent prior submittal for such facility rearrangement, modified as appropriate to respond to the third partys comments to such prior submittal, to the extent those comments were made pursuant to the requirements of this stage, and to reflect any subsequent changes agreed to by the lead agency and the third party.
(m)The third party may raise new comments on design documentation or advanced partial design units described in subdivision (i) as a consequence of design changes made by the lead agency after the third partys review of the most recent prior submittal of designs for such rearrangement.
(n)A betterment shall not be required to be constructed if it is not approved by the lead agency. The lead agency shall have a right to refuse a betterment that meets any of the following:
(1)The betterment is incompatible with the sustainable transportation project.
(2)The betterment cannot be constructed within the constraints of applicable law or the project schedule.
(3)The betterment is a facility rearrangement that is requested after the finalization of the Stage 1 project scope document, unless the facility rearrangement was requested in accordance with the third partys objective standards, criteria, and specifications in effect at the time of the notice described in subdivision (a), and was requested in response to new information that was not available to the third party during the Stage 1 process.
The cost of approved betterments shall be borne by the third party. This includes any increase in costs over the estimation of the cost of the betterment by the lead agency and cost of any mitigations of the betterment required as a result of the environmental review process.
3.Permitting and Construction19005.03.(a)An approved-for-construction design is a design that meets all of the following:
(1)The lead agency has approved the final design documentation.
(2)The third party has approved the final design documentation.
(3)The final design document has been signed and sealed by the engineer of record that is responsible for that final design documentation.
(4)Any other conditions for the final design documentation to be ready for construction set out under the requirements of this act have been satisfied.
(b)Commencement of a single or set of facility rearrangements for which an advanced partial design unit is at the final design stage may be approved for construction without all of the final design being approved for construction.
(c)Prior to the commencement of construction of a facility rearrangement, the lead agency shall transmit a proposed construction staging plan for any construction work to be performed within the public rights-of-way in the third partys jurisdiction. The plan shall include, but not be limited to:
(1)The handling of vehicular and pedestrian traffic, cyclist access, and circulation on streets adjacent to the construction with the construction phasing showing street closures, detours, warning devices, and temporary traffic signals.
(2)Accessible routes for pedestrians with physical disabilities in compliance with applicable law.
(3)Actions to maintain access to businesses, schools, and residences adjacent to the construction areas, as possible, and actions to ensure safe access and circulation for pedestrians and vehicular traffic as described in the traffic management plan.
(4)Elements of public awareness as well as mechanisms to assist affected parties in complaint resolutions.
(d)The third party shall review the submitted construction staging plan in accordance with its objective design standards and policies for such construction staging plans, and respond to the lead agency with a determination of whether the plan is complete or not. If incomplete, the third party will notify the lead agency of what aspects of the construction staging plan must be refined in order for the construction staging plan to be complete pursuant to the third partys applicable standards and policies. This response shall occur within 10 working days of receipt of the notice described in subdivision (c).
(e)The lead agency shall promptly modify the construction staging plan based on the information cited in subdivision (d) and resubmit it to the third party. The third party shall review the resubmittal for completeness pursuant to subdivision (d).
(f)Within 10 working days of the acknowledgment of completeness identified in subdivision (d), the third party shall provide comments, approve, or reject the construction staging plan.
(g)The lead agency may update the construction staging plan after it has been approved by the third party and must promptly submit each updated construction staging plan to the third party for review in accordance with subdivision (d).
(h)The third party shall impose only the minimum requirements for traffic management planning and construction sequencing that are necessary in order to provide for public health and safety, including, but not limited to, pedestrian and vehicular safety, and functionality, including, but not limited to, public and business access and circulation. This does not preclude the lead agency and third party from agreeing to additional traffic management planning and construction sequencing activities.
(i)The lead agency shall provide 10 working days of advance written notice where construction work is to be performed in the public rights-of-way for approved street, traffic lane, or sidewalk closures.
(j)If the lead agency fails to perform any construction work within the third partys public rights-of-way in accordance with the approved-for-construction final design documentation or construction staging plans approved by the third party pursuant to this section, the third party may issue a written notice of noncompliance from the third party and the lead agency must cure the noncompliance. If the lead agency and third party are unable to agree whether the work was performed correctly, the dispute shall be resolved via the binding dispute resolution process outlined in Section 19003.
(k)For third-party communication facilities, the lead agency and third party shall agree to a schedule for such work that balances minimal system downtime and third-party network disruption while maintaining a reasonable project schedule. If the lead agency and third party are unable to agree on such a schedule, the matter will be resolved by the binding dispute resolution process described in Section 19003.
(l)(1)A third party shall not unreasonably withhold the approval of the availability, location, and duration of the use of a third-party facility as a temporary facility to facilitate the construction of the sustainable transportation project, as otherwise permitted by state and federal law. Such approved use of a third-party facility shall be made in writing and without cost to the lead agency.
(2)Upon completion of the related construction and lead agencys determination that the temporary facilities are no longer needed, the lead agency shall remove all temporary facilities and restore the area as nearly as practicable to its original condition unless the lead agency and third party agree to another arrangement.
(3)If the lead agency believes that a third party is unreasonably withholding the approvals described in this subdivision and is unable to come to agreement with the third party on these approvals, it may elect to resolve the dispute through the binding dispute resolution process described in Section 19003.
(m)For any other third-party permit or approval, identified in the finalized Stage 1 project scope document as necessary for the lead agency to construct the sustainable transportation project as identified in the project schedule, the lead agency shall submit a completed permit or approval request to the third party.
(n)Within 10 working days of receipt of the permit or approval request, the third party shall review the permit or approval request in accordance with its objective standards and determine whether the permit or approval request is complete. If incomplete, the third party shall respond to the lead agency and notify the lead agency of what information is needed to make the request complete.
(o)If determined incomplete pursuant to subdivision (n), the lead agency shall promptly respond with the relevant information noted by the third party in subdivision (n). The third party shall review the permit or approval request and respond to the lead agency pursuant to subdivision (n).
(p)Within 20 working days of determining the request complete pursuant to subdivision (n), the third party shall review the relevant permit for compliance with all relevant written objective standards, specifications, and criteria that are applicable to the permit or approval request, or have been agreed to between the lead agency and third party, and shall grant approval of the permit or approval request, issue comments, or reject the permit or approval request.
(q)The permit request may only be rejected for failure to meet the relevant objective standards, criteria, or specifications that apply to that permit or approval and are consistent with this section.
SEC. 5.The provisions of this measure are severable. If any provision of this measure or its application is held invalid, that invalidity shall not affect other provisions or applications that can be given effect without the invalid provision or application.
SEC. 6.The Legislature finds and declares that sustainable transportation projects foster the movement of people on a local and regional level for the benefit of the entire state and, for that reason, authorizing the Secretary of Transportation to expedite the implementation of sustainable transportation projects by waiving local regulation of the design and construction of those projects is a matter of statewide concern and is not a municipal affair as that term is used in Section 5 of Article XI of the California Constitution. Therefore, Sections 3 and 4 of this act adding Section 13985 to the Government Code and adding Division 21 (commencing with Section 19001) to the Public Utilities Code, respectively, apply to all cities, including charter cities.
SEC. 7.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
SECTION 1.(a)The Legislature finds and declares the following:(1)Sustainable transportation projects are critical for the growth of the state in a manner that reduces greenhouse gas emissions and helps address the states housing shortage. It is in the interest of the state to accelerate the construction of sustainable transportation projects and avoid cost escalation, ensuring that more projects are built in a cost-effective manner.(2)Third-party permits and approvals for preconstruction and construction activities, including utility relocations, design review, and issuance of encroachment or other similar permits, can be a source of delay for sustainable transportation projects, potentially resulting in cost escalations and projects being built late and over budget.(b)It is the intent of the Legislature to amend this bill with legislation that accelerates and makes more reliable third-party permits and approvals for preconstruction and construction activities on sustainable transportation projects, including through requiring lead agencies engage early with third parties, setting timelines on design review activities to ensure prompt responses between parties, and limiting third-party requirements associated with permits and other approvals.SEC. 2.Section 671.5 of the Streets and Highways Code is amended to read:671.5.(a)The department shall either approve or deny an application from an applicant for an encroachment permit within 60 days of receiving a completed application, as determined by the department. An application for an encroachment permit is complete when all other statutory requirements, including the California Environmental Quality Act (Division 13 (commencing with Section 21000) of the Public Resources Code), have been complied with. The departments failure to notify the applicant within that 60-day period that the permit is denied shall be deemed to constitute approval of the permit. Thereafter, upon notifying the department, the applicant may act in accordance with its permit application, as if the permit had been approved.(b)All of the following shall apply to the departments review of an application for an encroachment permit for a broadband facility:(1)The department shall specify in writing all permit application criteria. It is the intent of the Legislature to ensure a streamlined, predictable, and expeditious process by which the department reviews broadband facility permit applications in order to achieve the rapid deployment of broadband facilities on highways.(2)Within 30 days after an application for an encroachment permit for a broadband facility is submitted, the department shall notify the applicant in writing whether the permit application is deemed complete. If the department does not notify the applicant within that 30-day period that the application is incomplete, the failure to notify shall be deemed to constitute a finding that the permit application is complete.(3)If the department deems a permit application incomplete, the department shall do all of the following:(A)At the time of notifying the applicant that the application is incomplete, furnish to the applicant a detailed explanation why the application is incomplete, with reference to the specific application criteria that the application does not meet.(B)Identify all supplemental information necessary to complete the application.(C)In a timely manner and no later than 14 days after a meeting is requested by the applicant, meet with the applicant to discuss any outstanding supplemental information necessary to complete the application. The department shall not be required to participate in more than three individual meetings with the applicant and shall not be required to meet in excess of four hours for each permit application.(D)Provide the applicant with no less than 30 days to resubmit its application with the supplemental information that the department identified in the notice. The applicants failure to respond with additional information during that period shall be deemed to constitute a withdrawal of the application.(4)Within 30 days after receiving supplemental information from an applicant pursuant to paragraph (3), the department shall approve or deny the application.(c)If the department denies an application for an encroachment permit, the department shall, at the time of notifying the applicant of the denial, furnish to the applicant a detailed explanation of the reason for the denial.(d)The department shall adopt regulations prescribing procedures for an applicant to appeal to the director for a final determination of the departments denial of an application. The appeal shall be made in writing to the director. There shall be a final written determination by the director within 60 calendar days after receipt of the applicants written appeal. The adopted regulations shall require the appellant to pay to the department a fee of not more than 50 percent of the estimated administrative cost to the department of conducting the appeal.(e)This section does not preclude an applicant and the department from mutually agreeing to an extension of any time limit provided by this section.(f)(1)On or before February 1, 2027, the department shall develop and adopt a process for project intake, project evaluation, and encroachment permit review for complete streets facilities, including pedestrian, bicycle, and transit priority facilities, that are sponsored by a local jurisdiction or a transit agency. The department shall design this process to enable the department to comply with subdivision (a).(2)The department shall report annually to the commission regarding project applications submitted pursuant to the process adopted pursuant to paragraph (1). The report shall include, but not be limited to, all of the following information:(A)The number of completed applications submitted.(B)The number of encroachment permits issued.(C)The number of days required to process each application.(3)The department shall post the report described in paragraph (2) on the departments internet website.(4)The department shall designate an encroachment permit manager in each district to ensure that applications for complete streets facilities are reviewed through the process adopted pursuant to paragraph (1). The encroachment permit manager shall have expertise in bicycle, pedestrian, and transit priority facilities.(a)The Legislature finds and declares the following:
(1)Sustainable transportation projects are critical for the growth of the state in a manner that reduces greenhouse gas emissions and helps address the states housing shortage. It is in the interest of the state to accelerate the construction of sustainable transportation projects and avoid cost escalation, ensuring that more projects are built in a cost-effective manner.
(2)Third-party permits and approvals for preconstruction and construction activities, including utility relocations, design review, and issuance of encroachment or other similar permits, can be a source of delay for sustainable transportation projects, potentially resulting in cost escalations and projects being built late and over budget.
(b)It is the intent of the Legislature to amend this bill with legislation that accelerates and makes more reliable third-party permits and approvals for preconstruction and construction activities on sustainable transportation projects, including through requiring lead agencies engage early with third parties, setting timelines on design review activities to ensure prompt responses between parties, and limiting third-party requirements associated with permits and other approvals.
SEC. 2.Section 671.5 of the Streets and Highways Code is amended to read:671.5.(a)The department shall either approve or deny an application from an applicant for an encroachment permit within 60 days of receiving a completed application, as determined by the department. An application for an encroachment permit is complete when all other statutory requirements, including the California Environmental Quality Act (Division 13 (commencing with Section 21000) of the Public Resources Code), have been complied with. The departments failure to notify the applicant within that 60-day period that the permit is denied shall be deemed to constitute approval of the permit. Thereafter, upon notifying the department, the applicant may act in accordance with its permit application, as if the permit had been approved.
(b)All of the following shall apply to the departments review of an application for an encroachment permit for a broadband facility:
(1)The department shall specify in writing all permit application criteria. It is the intent of the Legislature to ensure a streamlined, predictable, and expeditious process by which the department reviews broadband facility permit applications in order to achieve the rapid deployment of broadband facilities on highways.
(2)Within 30 days after an application for an encroachment permit for a broadband facility is submitted, the department shall notify the applicant in writing whether the permit application is deemed complete. If the department does not notify the applicant within that 30-day period that the application is incomplete, the failure to notify shall be deemed to constitute a finding that the permit application is complete.
(3)If the department deems a permit application incomplete, the department shall do all of the following:
(A)At the time of notifying the applicant that the application is incomplete, furnish to the applicant a detailed explanation why the application is incomplete, with reference to the specific application criteria that the application does not meet.
(B)Identify all supplemental information necessary to complete the application.
(C)In a timely manner and no later than 14 days after a meeting is requested by the applicant, meet with the applicant to discuss any outstanding supplemental information necessary to complete the application. The department shall not be required to participate in more than three individual meetings with the applicant and shall not be required to meet in excess of four hours for each permit application.
(D)Provide the applicant with no less than 30 days to resubmit its application with the supplemental information that the department identified in the notice. The applicants failure to respond with additional information during that period shall be deemed to constitute a withdrawal of the application.
(4)Within 30 days after receiving supplemental information from an applicant pursuant to paragraph (3), the department shall approve or deny the application.
(c)If the department denies an application for an encroachment permit, the department shall, at the time of notifying the applicant of the denial, furnish to the applicant a detailed explanation of the reason for the denial.
(d)The department shall adopt regulations prescribing procedures for an applicant to appeal to the director for a final determination of the departments denial of an application. The appeal shall be made in writing to the director. There shall be a final written determination by the director within 60 calendar days after receipt of the applicants written appeal. The adopted regulations shall require the appellant to pay to the department a fee of not more than 50 percent of the estimated administrative cost to the department of conducting the appeal.
(e)This section does not preclude an applicant and the department from mutually agreeing to an extension of any time limit provided by this section.
(f)(1)On or before February 1, 2027, the department shall develop and adopt a process for project intake, project evaluation, and encroachment permit review for complete streets facilities, including pedestrian, bicycle, and transit priority facilities, that are sponsored by a local jurisdiction or a transit agency. The department shall design this process to enable the department to comply with subdivision (a).
(2)The department shall report annually to the commission regarding project applications submitted pursuant to the process adopted pursuant to paragraph (1). The report shall include, but not be limited to, all of the following information:
(A)The number of completed applications submitted.
(B)The number of encroachment permits issued.
(C)The number of days required to process each application.
(3)The department shall post the report described in paragraph (2) on the departments internet website.
(4)The department shall designate an encroachment permit manager in each district to ensure that applications for complete streets facilities are reviewed through the process adopted pursuant to paragraph (1). The encroachment permit manager shall have expertise in bicycle, pedestrian, and transit priority facilities.
(a)The Legislature finds and declares the following:
(1)Sustainable transportation projects are critical for the growth of the state in a manner that reduces greenhouse gas emissions and helps address the states housing shortage. It is in the interest of the state to accelerate the construction of sustainable transportation projects and avoid cost escalation, ensuring that more projects are built in a cost-effective manner.
(2)Third-party permits and approvals for preconstruction and construction activities, including utility relocations, design review, and issuance of encroachment or other similar permits, can be a source of delay for sustainable transportation projects, potentially resulting in cost escalations and projects being built late and over budget.
(b)It is the intent of the Legislature to amend this bill with legislation that accelerates and makes more reliable third-party permits and approvals for preconstruction and construction activities on sustainable transportation projects, including through requiring lead agencies engage early with third parties, setting timelines on design review activities to ensure prompt responses between parties, and limiting third-party requirements associated with permits and other approvals.
SEC. 2.Section 671.5 of the Streets and Highways Code is amended to read:671.5.(a)The department shall either approve or deny an application from an applicant for an encroachment permit within 60 days of receiving a completed application, as determined by the department. An application for an encroachment permit is complete when all other statutory requirements, including the California Environmental Quality Act (Division 13 (commencing with Section 21000) of the Public Resources Code), have been complied with. The departments failure to notify the applicant within that 60-day period that the permit is denied shall be deemed to constitute approval of the permit. Thereafter, upon notifying the department, the applicant may act in accordance with its permit application, as if the permit had been approved.
(b)All of the following shall apply to the departments review of an application for an encroachment permit for a broadband facility:
(1)The department shall specify in writing all permit application criteria. It is the intent of the Legislature to ensure a streamlined, predictable, and expeditious process by which the department reviews broadband facility permit applications in order to achieve the rapid deployment of broadband facilities on highways.
(2)Within 30 days after an application for an encroachment permit for a broadband facility is submitted, the department shall notify the applicant in writing whether the permit application is deemed complete. If the department does not notify the applicant within that 30-day period that the application is incomplete, the failure to notify shall be deemed to constitute a finding that the permit application is complete.
(3)If the department deems a permit application incomplete, the department shall do all of the following:
(A)At the time of notifying the applicant that the application is incomplete, furnish to the applicant a detailed explanation why the application is incomplete, with reference to the specific application criteria that the application does not meet.
(B)Identify all supplemental information necessary to complete the application.
(C)In a timely manner and no later than 14 days after a meeting is requested by the applicant, meet with the applicant to discuss any outstanding supplemental information necessary to complete the application. The department shall not be required to participate in more than three individual meetings with the applicant and shall not be required to meet in excess of four hours for each permit application.
(D)Provide the applicant with no less than 30 days to resubmit its application with the supplemental information that the department identified in the notice. The applicants failure to respond with additional information during that period shall be deemed to constitute a withdrawal of the application.
(4)Within 30 days after receiving supplemental information from an applicant pursuant to paragraph (3), the department shall approve or deny the application.
(c)If the department denies an application for an encroachment permit, the department shall, at the time of notifying the applicant of the denial, furnish to the applicant a detailed explanation of the reason for the denial.
(d)The department shall adopt regulations prescribing procedures for an applicant to appeal to the director for a final determination of the departments denial of an application. The appeal shall be made in writing to the director. There shall be a final written determination by the director within 60 calendar days after receipt of the applicants written appeal. The adopted regulations shall require the appellant to pay to the department a fee of not more than 50 percent of the estimated administrative cost to the department of conducting the appeal.
(e)This section does not preclude an applicant and the department from mutually agreeing to an extension of any time limit provided by this section.
(f)(1)On or before January February 1, 2027, the department shall develop and adopt a process for project intake, project evaluation, and encroachment permit review for complete streets facilities, including pedestrian, bicycle, and transit priority facilities, that are sponsored by a local jurisdiction or a transit agency. The department shall design this process to enable the department to comply with subdivision (a).
(2)The department shall report annually to the commission regarding project applications submitted pursuant to the process adopted pursuant to paragraph (1). The report shall include, but not be limited to, all of the following information:
(A)The number of completed applications submitted.
(B)The number of encroachment permits issued.
(C)The number of days required to process each application.
(3)The department shall post the report described in paragraph (2) on the departments internet website.
(4)The department shall designate an encroachment permit manager in each district to ensure that applications for complete streets facilities are reviewed through the process adopted pursuant to paragraph (1). The encroachment permit manager shall have expertise in bicycle, pedestrian, and transit priority facilities.
All matter omitted in this version of the bill appears in the bill as introduced in the Senate, February 18, 2025. (JR11)For purposes of this article, the following definitions shall apply:
(a)(1)Large sustainable transportation project means a sustainable transportation project that, based on the project engineers cost estimate at the time the lead agency completes environmental review, costs more than twenty-five million dollars ($25,000,000), and that meets at least one of the following criteria:
(A)Be included in the most recently published State Rail Plan, pursuant to Section 14036, or the most recently published regional transportation plan, transportation improvement plan, or voter-approved local revenue measure expenditure plan of the regional or local jurisdiction or jurisdictions that the project passes through.
(B)Has completed environmental review pursuant to Division 13 (commencing with Section 21000) of the Public Resources Code, which may conclude with the adoption by the lead agency of a negative declaration, mitigated negative declaration, or determination of exemption from further environmental review.
(2)The cost estimate amount in paragraph (1) shall be adjusted pursuant to subdivision (j) of Section 21080.25 of the Public Resources Code.
(b)Master permitting lead agency means a lead agency that meets all of the following criteria:
(1)The lead agency has adopted a design criteria manual or design standards.
(2)The manual or standards described in paragraph (1) have been approved by relevant staff authorized by the Transportation Agency to approve the manual or standards.
(3)Operator has the same meaning as in Section 99210 of the Public Utilities Code.
(c)Sustainable transportation project means a project where the lead agency is a state agency, operator, or local agency that proposes the construction or modification of facilities that meet at least one of the following criteria:
(1)The project is exempt from Division 13 (commencing with Section 21000) of the Public Resources Code, pursuant to Section 21080.25 of the Public Resources Code.
(2)The projects primary purpose is to create, maintain, or improve active transportation infrastructure, including pedestrian and bicycle infrastructure.
(3)The projects primary purpose is to create, maintain, or improve public transit infrastructure, including, but not limited to, transit priority facilities, bus rapid transit facilities, or rail transit facilities, including facilities for rail transit, as defined in Section 99602 of the Public Utilities Code, commuter rail, regional rail, light rail transit, intercity rail, as defined in Section 99602 of the Public Utilities Code, or a rapid rail transit system, as defined in Section 92015.
(4)The projects primary purpose is to create, maintain, or improve other publicly owned or operated rail infrastructure.
(d)Third-party entity means a local agency, electrical corporation, or private telecommunications provider.
(e)Transit priority facility means a roadway facility, treatment, or improvement that helps transit buses and other transit vehicles avoid traffic congestion, reduce signal delays, and move more predictably and reliably, including the following:
(1)Dedicated lanes reserved for the exclusive use of transit vehicles and emergency vehicles.
(2)High-occupancy vehicle lanes for buses, motorcycles, or vehicles with three or more occupants.
(3)Bus stop or station placements and physical configurations, including, but not limited to, level boarding or bus bulbs, which are designed to maximize boarding, alighting efficiency, and reduce delays, or sidewalks and crosswalks to provide safe access to and from transit stops and stations.
(4)Transit signal priority, retiming, and preemption that adjusts traffic signal timing in real time to minimize delay of transit vehicles, including, but not limited to, reducing the length of a red light for a transit vehicle or extending an existing green light for an approaching transit vehicle.
(5)Turn restrictions and exceptions designed to minimize disruption to transit movements or to give transit vehicles and emergency vehicles special privileges to make otherwise restricted turns.
(6)Queue jump lanes to help transit vehicles move to the front of traffic waiting at a signal.
(7)Payment systems that reduce boarding times.
65964.61.(a)A lead agency shall provide written notice to a third-party entity of its need to use, relocate, alter, change, or otherwise improve facilities, publicly owned and managed utilities, public spaces, or other publicly or privately owned facilities under the third-party entitys jurisdiction or ownership for the implementation of a sustainable transportation project. In that written notice, the lead agency shall include materials with the following information regarding the sustainable transportation project:
(1)The sustainable transportation project name.
(2)A list of any cooperative agreements entered into between the lead agency and a third-party entity for the sustainable transportation project.
(3)A description of the scope of work to be performed on property owned by or within the jurisdiction of the third-party entity for the sustainable transportation project.
(4)A map of the sustainable transportation project limits that identifies locations of temporarily or permanently affected third-party entity facilities or public spaces impacted by the scope of work as described in paragraph (3).
(5)Construction education and outreach plans for businesses or residents impacted by project construction.
(6)Any safety and emergency service plans for project construction required by relevant state and federal laws and regulations.
(7)Draft plans for the scope of work described pursuant to paragraph (3), including construction plans, construction schedules, traffic and circulation management plans for all modes and for emergency vehicles, and other information related to the project.
(b)Within 30 calendar days of receiving the notice required by subdivision (a), the third-party entity shall provide a written response to the lead agency with all of the following:
(1)Notifying the lead agency in writing that it has received the notice and whether the notice complies with the requirements of subdivision (a).
(2)If the third-party entity determines that the lead agency has not provided information in the written notice as required by subdivision (a), then the third-party entity shall include in its written response to the lead agency an itemized list of specific information that was required by subdivision (a) but not provided. Upon receipt of an updated notice from the lead agency, the third-party entity shall review the notice for completeness pursuant to subdivisions (a) and (b).
(c)Within 30 calendar days of determining the notice required by subdivision (a) is complete pursuant to subdivision (b), the third-party entity shall do all of the following:
(1)Provide as-built plans to the lead agency for all third-party entity facilities that will be impacted by the work described in paragraph (3) of subdivision (a).
(2)(A)Provide any necessary permits, approvals, or permissions for the work to be completed and provide consolidated input and comments from all relevant departments, in writing, to the lead agency on all information provided pursuant to subdivision (a).
(B)If no input or comments are provided, all relevant permits are not provided, all relevant permissions to complete work on property owned by the third-party entity to accommodate the sustainable transportation project are not provided, or the third-party entity does not agree to complete all relevant work it is responsible for pursuant to a cooperative agreement required under Section 65964.62 on property it owns that is necessary to accommodate the sustainable transportation project, or fails to complete that work, upon the expiration of the 30-day deadline, the lead agency may begin construction or preconstruction activities on the property owned by or within the jurisdiction of the third-party entity in accordance with the materials provided in subdivision (a).
(C)A lead agency may only use the authority granted to it in subparagraph (B) if it is a master permitting lead agency.
(d)Except as provided under subdivision (g) of Section 65964.62, a third-party entity shall not require, as a condition for issuance of any construction, facility, encroachment, or other relevant permit for a sustainable transportation project, or as a condition for completing any relevant work on property owned by that third-party entity to accommodate the sustainable transportation project, conformance with or the performance of any conditions, unless the third-party entity makes a written finding, transmitted to the lead agency, that the conformance or performance of the condition is necessary for the safe construction, operation, or maintenance of a facility being constructed by the lead agency.
65964.62.(a)A lead agency responsible for a large sustainable transportation project shall seek to enter into a cooperative agreement with each third-party entity through which the project passes.
(b)The lead agency shall provide written notice to the third-party entity of its intent to enter into a cooperative agreement with the third-party entity. In that written notice, the lead agency shall include materials with the following information regarding the large sustainable transportation project:
(1)The large sustainable transportation project name.
(2)A description of the preliminary scope of work to be performed on the property owned by or within the jurisdiction of the third-party entity for the large sustainable transportation project.
(3)A map of the conceptual large sustainable transportation project limits that identifies locations of temporarily or permanently affected third-party entity facilities or public spaces impacted by the scope of work as described in paragraph (2).
(4)Draft plans for the scope of work described pursuant to paragraph (2), including construction plans, construction schedules, traffic and circulation management plans for all modes and for emergency vehicles, and other information related to the project.
(c)Within 30 calendar days of receiving the notice required by subdivision (b), the third-party entity shall provide a written response to the lead agency with all of the following:
(1)Notifying the lead agency in writing that they have received the notice and whether the notice complies with the requirements of subdivision (b).
(2)If the third-party entity determines that the lead agency has not provided information in the written notice as required by subdivision (b), then the third-party entity shall include in its written response to the lead agency an itemized list of specific information that was required by subdivision (b) but not provided. Upon receipt of an updated notice from the lead agency, the third-party entity shall review the notice for completeness pursuant to subdivisions (b) and (c).
(d)Within 60 calendar days of determining the notice required pursuant to subdivision (b) is complete pursuant to subdivision (c), the third-party entity shall enter into a cooperative agreement with the lead agency that, at a minimum, does all of the following:
(1)Meets applicable federal requirements, standards, or guidelines.
(2)Establishes the following:
(A)The scope of permits, permissions, and approvals required for the project on the property owned by or within the jurisdiction of the third-party entity.
(B)Timelines for design review, facility, construction, encroachment, or other relevant permit review and approval, or other relevant permissions and approvals, pursuant to the scope identified in subparagraph (A).
(C)Objective design and technical standards, provided that those standards shall not be adjusted once the cooperative agreement has been finalized unless both the lead agency and third-party entity agree to the modification of these standards.
(D)The funding relationship for the third-party entitys staff time spent on review and development of the large sustainable transportation project.
(e)If the third-party entity fails to enter into a cooperative agreement with the lead agency within the timeline required by subdivision (d), or if a cooperative agreement is entered into and the third-party entity violates the terms of the cooperative agreement, the lead agency may occupy the public spaces in the local jurisdiction without a facility, encroachment, construction, or other relevant permit, permission, or approval, or complete any work on property owned by the third-party entity that is needed to accommodate the sustainable transportation project.
(f)A lead agency may only use the authority granted it in subdivision (e) if it is a master permitting lead agency.
(g)A third-party entity shall not require, as a condition to the issuance of any construction, facility, encroachment, or other relevant permit for a large sustainable transportation project, or as a condition for completing any relevant work on property owned by that entity to accommodate the large sustainable transportation project, conformance with or the performance of any conditions that the third-party entity could have lawfully imposed as a condition to the design or construction of the project after the process described by subdivisions (a) to (f), inclusive, is completed. A third-party entity also shall not withhold or refuse to issue those permits, or refuse to provide other relevant approvals or permissions to conduct work on property owned by the third-party entity, for failure to conform with or perform any conditions that the third-party entity could have lawfully imposed as a condition to the design or construction of the project after the process described by subdivisions (a) to (f), inclusive, is completed.
SEC. 2.The Legislature finds and declares that accelerating sustainable transportation project delivery to address traffic fatalities and the climate crisis is a matter of statewide concern and is not a municipal affair as that term is used in Section 5 of Article XI of the California Constitution. Therefore, Section 1 of this act adding Article 7 (commencing with Section 65964.60) to Chapter 4.5 of Division 1 of Title 7 of the Government Code applies to all cities, including charter cities.
SEC. 3.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
|
Date
|
Status
|
|---|---|
| Aug 29, 2025 | August 29 hearing: Held in committee and under submission. |
| Aug 20, 2025 | August 20 set for first hearing. Placed on APPR. suspense file. |
| Jul 17, 2025 | Read second time and amended. Re-referred to Com. on APPR. |
| Jul 17, 2025 | From committee: Do pass as amended and re-refer to Com. on APPR. (Ayes 10. Noes 4.) (July 16). |
| Jul 17, 2025 | Assembly Rule 63 suspended. (Ayes 49. Noes 15. Page 2578.) |
| Jul 16, 2025 | From committee: Do pass and re-refer to Com. on U. & E. (Ayes 8. Noes 2.) (July 16). Re-referred to Com. on U. & E. |
| Jul 15, 2025 | From committee: Do pass and re-refer to Com. on L. GOV. (Ayes 10. Noes 3.) (July 14). Re-referred to Com. on L. GOV. |
| Jul 9, 2025 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on TRANS. |
| Jul 7, 2025 | Assembly Rule 56 suspended. |
| Jun 30, 2025 | Referred to Coms. on TRANS., L. GOV., and U. & E. |
| Jun 30, 2025 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on TRANS. |
| May 28, 2025 | In Assembly. Read first time. Held at Desk. |
| May 28, 2025 | Read third time. Passed. (Ayes 34. Noes 1. Page 1296.) Ordered to the Assembly. |
| May 6, 2025 | Read second time. Ordered to third reading. |
| May 5, 2025 | From committee: Be ordered to second reading pursuant to Senate Rule 28.8. |
| Apr 25, 2025 | Set for hearing May 5. |
| Apr 23, 2025 | Withdrawn from committee. |
| Apr 23, 2025 | Re-referred to Com. on APPR. |
| Apr 23, 2025 | From committee: Do pass and re-refer to Com. on L. GOV. (Ayes 13. Noes 0. Page 842.) (April 22). Re-referred to Com. on L. GOV. |
| Apr 10, 2025 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on TRANS. |
| Apr 9, 2025 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on TRANS. |
| Apr 8, 2025 | Set for hearing April 22. |
| Feb 26, 2025 | Referred to Coms. on TRANS. and L. GOV. |
| Feb 19, 2025 | From printer. May be acted upon on or after March 21. |
| Feb 18, 2025 | Introduced. Read first time. To Com. on RLS. for assignment. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Jul 16, 2025 | Do pass as amended and be re-referred to the Committee on [Appropriations] | Assembly Standing Committee on Utilities and Energy |
Passed |
|
| Jul 16, 2025 | Do pass and be re-referred to the Committee on [Utilities and Energy] | Assembly Standing Committee on Local Government |
Passed |
|
| Jul 14, 2025 | Do pass and be re-referred to the Committee on [Local Government] | Assembly Standing Committee on Transportation |
Passed |
|
| May 28, 2025 | Senate 3rd Reading SB445 Wiener et al. | Senate Floor |
Passed |
|
| Apr 22, 2025 | Do pass, but first be re-referred to the Committee on [Local Government] | Senate Standing Committee on Transportation |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| 350 Bay Area Action | ** Support | |
| Association Of California Water Agencies | ** Against | |
| BURBANK/BURBANK REDEVELOPMENT AGENCY; CITY OF | ** Against | |
| California Association Of Sanitation Agencies | ** Against | |
| California Broadband & Video Association (CalBroadband) | ** Against | |
| California Municipal Utilities Association | ** Against | |
| California Special Districts Association | ** Against | |
| California State Association Of Counties | ** Against | |
| California YIMBY | ** Support | |
| City of Arcata | ** Against | |
| City of Artesia | ** Against | |
| City of Artesia, California | ** Against | |
| City Of Burbank | ** Against | |
| City of Chino | ** Against | |
| City of Colton | ** Against | |
| city of Cypress | ** Against | |
| City of Downey | ** Against | |
| City of East Palo Alto | ** Against | |
| City of El Segundo | ** Against | |
| City of Grand Terrace | ** Against | |
| City of La Palma | ** Against | |
| city of laguna niguel | ** Against | |
| City of Lakewood | ** Against | |
| City of Lakewood CA | ** Against | |
| City of Los Alamitos | ** Against | |
| City of Manteca | ** Against | |
| City Of Menifee | ** Against | |
| City Of Merced | ** Against | |
| City Of Mission Viejo | ** Against | |
| City of Moreno Valley | ** Against | |
| City of Morgan Hill | ** Against | |
| City of Novato | ** Against | |
| City Of Ontario | ** Against | |
| City of Palm Desert | ** Against | |
| city of paramount | ** Against | |
| City of Rancho Cucamonga | ** Against | |
| City of San Luis Obispo | ** Against | |
| City of Stanton | ** Against | |
| City of Suisun City | ** Against | |
| City of Thousand Oaks | ** Against | |
| City of Torrance | ** Against | |
| City Of Tustin | ** Against | |
| City Of Vernon | ** Against | |
| Climate Action California | ** Support | |
| Cucamonga Valley Water District | ** Against | |
| DOWNEY; CITY OF | ** Against | |
| EL SEGUNDO, CITY OF | ** Against | |
| LAKEWOOD; CITY OF | ** Against | |
| League Of California Cities | ** Against | |
| Los Angeles County Sanitation Districts | ** Against | |
| Los Angeles Department of Water and Power | ** Against | |
| Marin County Council of Mayors and Councilmembers | ** Against | |
| Mission Viejo City Of | ** Against | |
| Move LA | ** Support | |
| ONTARIO; CITY OF | ** Against | |
| Pacific Gas And Electric Company | ** Against | |
| Rural County Representatives of California | ** Against | |
| San Diego Gas and Electric Company | ** Against | |
| SAN RAFAEL/MARIN COUNTY COUNCIL OF MAYORS & COUNCIL MEMBERS; CITY OF | ** Against | |
| Sempra Energy And Its Affiliates: San Diego Gas & Electric Company And Southern California Gas Company | ** Against | |
| Southern California Edison | ** Against | |
| Southern California Gas Company | ** Against | |
| SPUR | ** Support | |
| Streets for All | ** Support | |
| The current version of this bill, amended July 9, 2025, substantially amended the bill. Organizations listed in opposition submitted their positions to the prior version of this bill. | ** Against | |
| Town Of Mammoth Lakes | ** Against | |
| Tustin, City Of | ** Against | |
| Urban Counties of California | ** Against | |
| US High Speed Rail Association | ** Support | |
| USTelecom—The Broadband Association | ** Against | |
| WateReuse California | ** Against | |
| Writing in opposition, as amended on June 30, 2025, not based on the version in print which has been significantly amended. | ** Against |
Date of Hearing: August 20, 2025
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Buffy Wicks, Chair
SBPCA Bill Id:SB 445
Author:(Wiener) – As Amended Ver:July 17, 2025
Policy Committee: | Transportation | Vote: | 10 - 3 |
Utilities and Energy | 10 - 4 | ||
Local Government | 8 - 2 |
Urgency: No State Mandated Local Program: Yes Reimbursable: No
SUMMARY:
This bill directs the High-Speed Rail Authority (HSRA), in consultation with specified entities, to develop both internal rules governing HSRA’s engagement of specified utilities to ensure coordination and cooperation in relocating utility infrastructure and regulations governing local agency permits and approvals.
Among other things, the bill:
- Defines utilities, for purposes of this bill, as electrical and gas corporations (IOUs), local publicly owned utilities (POUs) and private telecommunications providers.
- As part of its development of internal rules, requires the HSRA to identify, in coordination with the California Public Utilities Commission (CPUC), existing processes within the CPUC that may provide a similar process and outcome for disputes with utilities regulated by the CPUC instead of processes HSRA may develop pursuant to this bill.
- Requires HSRA to hold at least two public hearings regarding the internal rules and the regulations before adopting either.
- Makes the internal rules and the regulations inoperative until the HSRA Office of the Inspector General (HSRA-OIG) determines the HSRA has completed development and implementation of a process to review third-party agreements in a timely manner.
- Directs the HSRA-OIG, beginning one year from the operative date of the internal rules and the regulations, to evaluate the extent to which the HSRA is meeting its review deadlines and other requirements and to determine the extent to which the internal rules and the regulations have been effective in limiting delays associated with third-party agreements.
- Requires the HSRA and the specified utilities, by December 1, 2026, to identify existing barriers and agree to preferred solutions to ensure utility relocations do not result in unnecessary or foreseeable project delays, including agreeing to a definition of “betterments” that prohibits requirements or conditions unrelated to health, reliability and safety standards.
FISCAL EFFECT:
This bill will require HSRA to undertake significant analytical and regulatory efforts, with resulting costs likely in the millions of dollars (special fund). HSRA estimates costs in the low millions of dollars and describes the associated work as drafting and adopting regulations and related policies and documents, conducting research and engaging external stakeholders. HSRA assumes a 12-month timeline to complete this work and that it will need to contract with outside experts to do so.
COMMENTS:
- Purpose. The author views the high-speed rail projects as “essential for an abundant, affordable, zero-emission future” and contends it is “imperative to help the project cut through permitting and approval-related red tape in order to prevent project cost increases and accelerate project delivery.” To that end, the author intends this bill to place in code recommendations of the HSRA-OIG that, the author asserts, will “cut red tape, streamline the project delivery process, curtail veto-points, and reduce and contain project costs.”
- Background. Statute in 1996 created the HSRA to plan and construct a high-speed rail system that would link the state’s major population centers. In November 2008, voters approved Proposition 1A, which authorized the state to sell $10 billion in general obligation bonds to partially fund the system, as well as related projects.
Over the years, the project has faced challenges, including inadequate funding (despite more than $14 billion in expenditures) and delays caused by right of way acquisition and utility relocations. To date, no high-speed train operates on the line.
In 2022, the Legislature created the HSRA-OIG. The Legislature provided the HSRA-OIG with broad oversight authority and assigned to it several specific duties, among them: (a) conduct independent fiscal estimates and reviews of HSRA’s plans and estimates for project advancement and make findings of their reasonableness, (b) conduct audits and investigations, (c) identify best practices and recommend policies to HSRA and (d) review HSARA’s contracts and contracting practices to determine whether they are executed consistent with state and federal laws and policies and are conducted in a fair and reasonable manner, providing the state with valued services at reasonable cost.
In February of this year, the HSRA-OIG released a report (“Report 25-R-01”) on its review of the HSRA’s progress on the Merced-to-Bakersfield segment of the high-speed rail corridor and the likelihood HSRA would complete the segment by the target set by HSRA, 2033. The HSRA-OIG warned of “the potential for significant uncertainty and risk” and concluded “staying within the 2033 schedule envelope is unlikely.” In a subsequent report published that same month (“Report 25-R-02”), the HSRA-OIG found HSRA “lacks leverage to help ensure that third parties do not themselves needlessly delay negotiations” and recommended HSRA work with the Legislature “to implement changes to state law to improve its ability to resolve third-party delays in a timely manner.”
- Support and Opposition. The author gutted-and-amended this bill after it left the Senate, and it then was heard by three Assembly policy committees—Transportation, Utilities and Energy, and Local Government. Several sources have indicated the author plans substantial amendments to the bill. This committee does not know how any such amendments, should they occur, would affect the position of various organizations. The following reflects support for and opposition to the bill when it was heard by the Assembly policy committees the second week of July.
This bill was supported by Streets for All and California YIMBY, the latter of which writes:
The transportation sector is the largest contributor to greenhouse gas emissions in the state, making the need for clean, sustainable transportation projects critical. However, these projects are often plagued by delays as lead agencies…navigate a balkanized post-environmental permitting and construction process. Permitting and other delays – such as utility relocations – result in increased project costs, and less transit being built at a greater cost.
SB 445 addresses these delays by imposing timelines on 3rd-party permit or other project construction activity permissions or approvals, and empowers lead agencies to be self-permitting and advance work should the timelines not be met.
In contrast, the bill was opposed by a long list of local governments and related associations, which described the bill as “leading to the near-total erosion of local authority to manage public infrastructure/assets.” In addition, USTelecom—The Broadband Association and the California Broadband & Video Association (CalBroadband) together described the bill as “confusing and complex,” “a solution in search of a problem” and “an ideal candidate to become a two-year bill, which will allow for more thoughtful analysis.”
Analysis Prepared by: Jay Dickenson / APPR. / (916) 319-2081
Date of Hearing: July 16, 2025
ASSEMBLY COMMITTEE ON LOCAL GOVERNMENT
Juan Carrillo, Chair
SBPCA Bill Id:SB 445
Author:(Wiener) – As Amended Ver:July 9, 2025
SENATE VOTE: 34-1
SUBJECT: High-speed rail: third-party permits and approvals: regulations
SUMMARY: Requires the California High-Speed Rail Authority (CHSRA) to develop and adopt regulations for governing third-party permits and approvals that are necessary to deliver the project. Specifically, this bill:
- Requires CHSRA, by January 1, 2026, to develop and adopt regulations for governing third-party permits and approvals that are necessary to deliver the high-speed rail project and ensure that the regulations do all of the following:
- Require early engagement between third parties and CHSRA.
- Identify the circumstances under which CHSRA shall seek to enter into a cooperative agreement with each applicable third party that serves as the framework for all future project interactions and, where relevant, identifies who is responsible for specific utility relocations and the associated costs.
- Require regular meetings with third parties during the planning, design, and construction phases.
- Require CHSRA to establish cost estimates with conservative contingency budgets for each utility relocation and to not oversimplify the utility costs and potential risks by bundling those costs into a single item.
- Require regular communication and documentation of contracting terms, conditions, and decisions during construction.
- Define options that can govern a third-party review process for permits and approvals.
- Consider ways to reduce permitting and approval delays.
- Establish a binding dispute resolution process.
- Exempt gas corporations and electrical corporations that the California Public Utilities Commission (CPUC) regulates from the dispute resolution process.
- Prohibit third-party entities from insisting on exactions or betterments from CHSRA that are unrelated to ensuring that health and safety standards are met, unless otherwise stipulated by a cooperative agreement, as a condition for permits and approvals.
- Consider reimbursement of third-party staff time and third-party time and materials to relocate the utility.
- Define the terms “betterment” and “cooperative agreement” for purposes of the regulation.
- Requires CHSRA to consult with all of the following entities when developing the regulations: California Department of Transportation (Caltrans); CPUC; local government stakeholders; local publicly owned utilities (POUs), gas corporations, and electrical corporations; water districts; telecommunications companies; passenger and freight railroads; and any other relevant entities with expertise in transportation infrastructure project delivery.
- Requires CHSRA to hold at least two public hearings regarding the proposed regulations before adopting them.
- Requires CHSRA to post a public notice on its website when it adopts the regulations and not enter into a third-party agreement until 30 days after the public notice is posted.
- Prohibits CHSRA from implementing these regulations until it completes the development and implementation of a process to review third-party agreements in a timely manner as recommended by the High-Speed Rail Authority Office of the Inspector General (OIG-HSR) in Recommendation 25-R-02-02.
- Contains a number of definitions, including that “third party” means a local agency or utility, including, but not limited to, an electrical corporation, gas corporation, local POU, or private telecommunications provider.
- Includes a severability clause.
- Contains findings and declarations regarding its purpose.
- Provides that no reimbursement is required by this bill pursuant to Section 6 of Article XIII B of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this bill, within the meaning of Section 17556 of the Government Code.
EXISTING LAW:
- Creates CHSRA in the California State Transportation Agency with 11 members: five appointed by the Governor, two appointed by the Senate Committee on Rules, two appointed by the Speaker of the Assembly, and one each ex-officio member appointed by the Senate and Assembly. (Public Utilities Code (PUC) §185020)
- Requires CHSRA to direct the development and implementation of an intercity high-speed rail service. (PUC § 185030)
- Requires CHSRA to reimburse utilities for relocation costs under specified circumstances. It also requires the utility “to move its facilities as soon as reasonable possible so as not to delay high-speed rail construction” under specified circumstances. (PUC § 185505)
- Requires Caltrans to specify for a utility relocation a reasonable time within which the work of relocation shall commence. (Streets and Highways Code (SHC) § 680)
- Establishes special provisions and requirements for Caltrans when relocating utilities within and outside freeways. (SHC §§ 700-707.5)
- Creates the OIG-HSR to initiate an audit or review regarding oversight related to delivery of the high-speed rail project undertaken by CHSRA, and the selection and oversight of contractors related to the project. (PUC § 187000, et seq.)
FISCAL EFFECT: This bill is keyed fiscal and contains a state-mandated local program.
COMMENTS:
- Bill Summary. This bill requires CHSRA to develop and adopt regulations for governing third-party permits and approvals that are necessary to deliver the high-speed rail project, with specified objectives, by January 1, 2026.
CHSRA must consult with all of the following entities when developing the regulations: Caltrans; CPUC; local government stakeholders; local publicly owned utilities, gas corporations, and electrical corporations; water districts; telecommunications companies; passenger and freight railroads; and any other relevant entities with expertise in transportation infrastructure project delivery.
CHSRA must hold at least two public hearings regarding the proposed regulations before adopting them, and must post a public notice on its website when it adopts the regulations and not enter into a third-party agreement until 30 days after the public notice is posted.
This bill prohibits CHSRA from implementing the regulations until it completes the development and implementation of a process to review third-party agreements in a timely manner as recommended by OIG-HSR in Recommendation 25-R-02-02.
This bill is sponsored by Streets for All.
- Author’s Statement. According to the author, “California High-Speed Rail is critical for our state’s future. The project is already combating climate change, fostering transit-oriented developing, and creating thousands of good-paying union jobs. The project is essential for an abundant, affordable, zero-emission future. It is imperative to help the project cut through permitting and approval-related red tape in order to prevent project cost increases and accelerate project delivery. It shouldn’t be this hard to go through design review and approvals or to relocate utilities. There shouldn’t be so many veto-points that empower project skeptics or opponents to stall the delivery – particularly after the voters approved funding for the project and design and construction are underway. SB 445 implements a High-Speed Rail inspector general recommendation to cut red tape, streamline the project delivery process, curtail veto-points, and reduce and contain project costs. The bill will result in improved and more cost-effective delivery of California High-Speed Rail, ensuring that public dollars are wisely spent on the project.”
- Background. Utility relocation poses risks to the scope, schedule, and cost of transit and rail projects. A wide variety of private, public, or cooperatively-owned utilities for water, natural gas, fuel, chemical feeds, stormwater, wastewater, electrical power, telephone, cable/TV/Internet fiber, street lighting, and traffic signaling are built under, on or over city streets and other rights-of-way. Some of these require special care such as fiber optic given the practice of threading the fiber through older, abandoned utilities such as gas lines. Projects with alignments near federal buildings such as court houses, or near public or law enforcement agencies may encounter communications lines or other infrastructure that are not readily identified. These buildings and their utilities require special handling.
Transit and rail projects often involve modification to existing underground and overhead infrastructure. The need to relocate or remove existing utilities on transit and rail project sets up encounters with known, unknown, unmarked, or abandoned utilities. The design of utility relocations must accommodate track slabs, rail-tie-ballast track roadbed, catenary poles, signal masts, gravity flow stormwater drainage, station platforms, signage, lighting, signaling, communications lines, power lines, bridge abutments and piers, earth retaining walls, noise walls, streetscaping, landscaping, and other new infrastructure. Relocation of utilities under intersections and sidewalks is even more complicated and overhead contact systems must consider the potential for electrical interference between the traction power wires and other overhead, non-transit, high voltage lines.
Pre-construction activities for transportation infrastructure projects—often referred to as early works— generally includes project sponsors negotiating agreements with various third parties, such as utility owners, railroad companies, and local jurisdictions, before initiating construction. Project sponsors must work with various third parties to acquire right of way and relocate utilities located in the system’s path, and manage betterments. A betterment is an improvement that occurs to the utility during the relocation process that increases capacity and is not otherwise required in order to successfully relocate the utility as a result of the project.
- Local Permitting. The California Constitution allows cities and counties to “make and enforce within its limits, all local, police, sanitary and other ordinances and regulations not in conflict with general laws.” It is from this fundamental power (commonly called the police power) that cities and counties derive their authority to regulate behavior to preserve the health, safety, and welfare of the public – including land use authority.
Cities and counties enforce their land use authority through zoning regulations and their control of the entitlement process, which is the process by which a city or county grants permission for a proposed development to be built (most often in the context of a housing project). Zoning and entitlement can both involve the process of issuing various types of permits, such as use permits, variances, encroachment permits, building permits, and so forth. Locally-owned utilities, also called POUs, frequently become involved in the process of issuing permits when a permit requires approvals for electric, water or other utility services or the approval of a utility to move or “relocate” any of its infrastructure.
- The Federal Transit Administration (FTA) Best Practices. The FTA Project Management Oversight Program, Utility Relocation - Challenges and Proposed Solutions report of March 2022 identified best practices to address utility relocation challenges. These include active, on-going implementation of mitigations such as meetings, tracking, following-up on action items to maintain accountability, schedule workarounds, communication, cost negotiations, enforcement of compliance with federal regulations, and dedicated attention throughout the project.
The FTA’s best practices for utility relocations include:
- Preplanning: early in a project, all project stakeholders draft and agree to the terms of a Third-Party Utility Relocation Agreement. This agreement serves as the groundwork for all future project interactions between and among the stakeholders and identifies who is responsible for specific utility relocations and the costs associated with those relocations.
- Meet regularly: Hold regular (weekly) meetings with utility companies during the planning, design, and construction phases.
- Cost estimates: Project Sponsors should establish cost estimates with conservative contingency budgets for each utility relocation and not oversimplify the utility costs and potential risks by “bundling” them into a single item.
- Partnering sessions: Define roles and responsibilities of the partners and clarify lines of communication so the decision-making process is understood.
- Segments: For above ground transit and rail projects costs, break the project into segments so that as a segment is cleared of existing utilities new construction can begin.
- Continue regular communication and documentation of contracting terms, conditions, and decisions during construction.
- CHSRA. SB 1420 (Kopp), Chapter 796, Statutes of 1996, established CHSRA to plan and construct a high speed rail system that would link the state’s major population centers. In November 2008, voters approved Proposition 1A, which authorized the state to sell $10 billion in general obligation bonds to partially fund the system, as well as related projects. Proposition 1A also specified certain criteria and conditions that the system must ultimately achieve. For example, the measure requires that the system be designed to be capable of specified travel times along certain routes, such as nonstop travel from San Francisco to Los Angeles within two hours and forty minutes.
Over the years, the project has faced many challenges largely stemming from a lack of adequate funding to complete even a segment of the project, and delays caused by right of way acquisition and utility relocations. As of May 31, 2025, $14.4 billion has been spent on the project, mostly on work between Merced and Bakersfield.
- OIG-HSR. SB 198 (Committee on Budget and Fiscal Review), Chapter 71, Statutes of 2022, established the OIG-HSR. Since its inception, OIG-HSR has completed six reviews of the high-speed rail project. In its February 21, 2025 review of “Preconstruction Activities for the Merced to Bakersfield Extensions” the OIG-HSR recommended that the Legislature authorize CHSRA to promulgate regulations governing third-party review and approval timeframes for agreements and designs.
The OIG-HSR found that “…procedures do not fundamentally improve the Authority’s ability to get third parties to engage in what can be a time-consuming process. As a potential result, early works on the Merced and Bakersfield extensions have been hindered by delays in executing utility-owner reimbursement agreements, which are generally necessary for utility owners to review and approve utility relocation designs before the Authority can begin construction. In fact, some negotiations have been ongoing for nearly two years without reaching agreement. The Authority’s often time-consuming internal review process, disagreement over contract terms, and little incentive for utility owners to engage in the process in a timely manner have caused the delays. Consequently, the Authority is currently proceeding with utility relocation designs without owner approval, which could lead to more redesigns later.”
The OIG-HSR also found, “During our review, Authority staff described what they believe are some causes of challenges in negotiating timely agreements with third parties. Authority staff responsible for working with third parties and overseeing design of the extensions indicated to us that delays result, in part, from third parties’ lack of incentive to engage in the process, which requires work on their part that they wouldn’t otherwise perform. Further, Authority staff overseeing the Central Valley region of the system explained to us that because utility owners, for example, are not under any particular time pressure, there is a resulting imbalance in these negotiations and the Authority’s other interactions with third parties.
“Additionally, Authority staff explained that, in the past, the Authority sometimes agreed to terms that put it in a disadvantageous position—for example, agreeing to compensate third parties for their attorney costs or agreeing to overly tight timelines for construction related to relocating individual utilities. We saw documentation of this type of issue in the example described in the previous section concerning attorney fee reimbursement. Authority staff also indicated that the lack of uniform agreement terms more generally increases difficulties in efficiently reaching and executing agreements. Authority staff expressed that, although the Authority has learned from and is now trying to avoid past mistakes, the legacy of those older agreements means that some third parties expect to receive the same terms as before, making current negotiations challenging.”
- Internal Processes at CHSRA. In its February 2025 review, the OIG-HSR found that third-party-related delays are partially attributable to CHRSA and its project management procedures being inadequate. The OIG-HSR found that CHSRA lacks defined negotiation timeframes, and “communicating those timeframes to third parties, would be helpful in making the process more efficient.”
The OIG-HSR recommended that “…by May 2025, the third-party agreements branch and the contracts and procurement branch should develop procedures with defined timeframes for their internal review processes. These should include defined timeframes for how long staff at each level should attempt to resolve an issue before escalating it.” OIG-HSR also recommended that CHSRA improve internal tracking tools and hire additional legal staff if needed by May 2025. CHSRA agreed with these recommendations.
- Policy Considerations. This bill was substantially amended on July 9, 2025, which provided very little time for stakeholders to update their positions on the current version of the bill. Concerns could include:
- Which “third-party entities” should be subject to regulations? Should regulations apply to all local agencies, or only to POUs? Should regulations apply to all utilities, or only to investor-owned utilities or POUs?
- Which permits or approvals should be subject to regulations? What does the evidence indicate regarding the types of permits or approvals that are actually or potentially delaying the high-speed rail project?
- Who is regulating? Should CHSRA or a different entity adopt regulations for the high-speed rail project?
- Should there be parameters around binding arbitration? Should this bill provide more details regarding what the binding arbitration process entails, who will administer it, and if it would include any appeals process?
- Who pays for utility relocations? Should this bill clarify who is responsible for the costs of utility relocations?
- What about reliability of service? Should this bill provide more specificity regarding the ability for a utility to continue delivering services reliably in the process of a utility relocation?
These and other debates could arise from the recent amendments to this bill. The Committee may wish to consider the extent to which additional amendments should be adopted moving forward to address any questions, concerns or opposition raised regarding the bill in print.
- Arguments in Support. Streets for All, sponsor of this bill, writes, “SB 445 requires the High-Speed Rail Authority to develop and adopt regulations that outline requirements for third party permits and approvals necessary for the project. In doing so, the bill helps the project get built faster and on budget, effectively spending public funds.
“The transportation sector is the largest contributor to greenhouse gas emissions in the state, and the high-speed rail project will drastically reduce these emissions by an estimated 84 to 102 million metric tons of carbon dioxide equivalent over the first 50 years of operation. In order for the project to be built on schedule and on budget, it is imperative that it not be held up by thousands of individual veto points after the decision has been made to fund, design, and construct the project.”
- Arguments in Opposition. The current version of this bill, amended July 9, 2025, substantially amended the bill. All opposition letters address the prior version of this bill, and it is unclear if opposition arguments remain relevant.
- Triple-Referral. This bill is triple-referred to the Transportation Committee, where it was heard on July 14, 2025, and the Utilities and Energy Committee, where it is scheduled to be heard on July 16, 2025.
REGISTERED SUPPORT / OPPOSITION:
Support
Streets for All [SPONSOR]
350 Bay Area Action (prior version)
California YIMBY (prior version)
SPUR (prior version)
Opposition
The current version of this bill, amended July 9, 2025, substantially amended the bill. Organizations listed in opposition submitted their positions to the prior version of this bill.
Association of California Water Agencies
CalBroadband
California Association of Sanitation Agencies
California Municipal Utilities Association
California Special Districts Association
California State Association of Counties
City of Arcata
City of Artesia
City of Burbank
City of Chino
City of Colton
City of Cypress
City of Downey
City of El Segundo
City of La Palma
City of Laguna Niguel
City of Lakewood
City of Los Alamitos
City of Manteca
City of Menifee
City of Merced
City of Mission Viejo
City of Moreno Valley
City of Morgan Hill
City of Novato
City of Ontario
City of Palm Desert
City of Rancho Cucamonga
City of San Luis Obispo
City of Stanton
City of Suisun City
City of Thousand Oaks
City of Torrance
City of Vernon
League of California Cities
Los Angeles County Sanitation Districts
Marin County Council of Mayors and Councilmembers
Pacific Gas and Electric Company
Rural County Representatives of California (RCRC)
San Diego Gas and Electric Company
Southern California Edison
Southern California Gas Company
Town of Mammoth Lakes
Urban Counties of California (UCC)
USTelecom - The Broadband Association
Watereuse California
Oppose Unless Amended
City of Tustin (prior version)
Analysis Prepared by: Angela Mapp / L. GOV. / (916) 319-3958
Date of Hearing: July 14, 2025
ASSEMBLY COMMITTEE ON TRANSPORTATION
Lori D. Wilson, Chair
SBPCA Bill Id:SB 445
Author:(Wiener) – As Amended Ver:June 30, 2025
SENATE VOTE: 34-1
SUBJECT: High-speed rail: third-party permits and approvals: regulations.
SUMMARY: Requires the California High-Speed Rail Authority (CHSRA) to develop and adopt regulations for governing third-party permits and approvals that are necessary to deliver the project. Specifically, this bill:
- Requires CHSRA by January 1, 2026 to develop and adopt regulations for governing third-party permits and approvals that are necessary to deliver the high-speed rail project and ensure that the regulations do all of the following:
- Require early engagement between third parties and CHSRA;
- Identify the circumstances under which CHSRA shall seek to enter into a cooperative agreement with each applicable third party that serves as the framework for all future project interactions and, where relevant, identifies who is responsible for specific utility relocations and the associated costs;
- Require regular meetings with third parties during the planning, design, and construction phases;
- Require the CHSRA to establish cost estimates with conservative contingency budgets for each utility relocation and to not oversimplify the utility costs and potential risks by bundling those costs into a single item;
- Require regular communication and documentation of contracting terms, conditions, and decisions during construction;
- Define options that can govern a third-party review process for permits and approvals;
- Consider ways to reduce permitting and approval delays;
- Establish a binding dispute resolution process;
- Exempt gas corporations and electrical corporations that the Public Utilities Commission (CPUC) regulates from the dispute resolution process;
- Prohibit third-party entities from insisting on exactions or betterments from CHSRA that are unrelated to ensuring that health and safety standards are met, unless otherwise stipulated by a cooperative agreement, as a condition for permits and approvals;
- Consider reimbursement of third-party staff time and third-party time and materials to relocate the utility; and,
- Define the terms “betterment” and “cooperative agreement” for purposes of the regulation.
- Requires CHSRA to consult with all of the following entities when developing the regulations: California Department of Transportation (Caltrans); CPUC; local government stakeholders; local publicly owned utilities, gas corporations, and electrical corporations; water districts; telecommunications companies; passenger and freight railroads; and any other relevant entities with expertise in transportation infrastructure project delivery.
- Requires CHSRA to hold at least two public hearings regarding the proposed regulations before adopting them.
- Requires CHSRA to post a public notice on its website when it adopts the regulations and not enter into a third-party agreement until 30 days after the public notice is posted.
- Prohibits CHSRA from implementing these regulations until it completes the development and implementation of a process to review third-party agreements in a timely manner as recommended by the High-Speed Rail Authority Office of the Inspector General (OIG-HSR) in Recommendation 25-R-02-02.
- Includes a severability clause.
EXISTING LAW:
- Creates CHSRA in the California State Transportation Agency with 11 members: five appointed by the Governor, two appointed by the Senate Committee on Rules, two appointed by the Speaker of the Assembly, and one each ex-officio member appointed by the Senate and Assembly. (Public Utilities Code (PUC) Section 185020)
- Requires CHSRA to direct the development and implementation of an intercity high-speed rail service. (PUC 185030)
- Requires CHSRA to reimburse utilities for relocation costs under specified circumstances. It also requires the utility “to move its facilities as soon as reasonable possible so as not to delay high-speed rail construction” under specified circumstances. (PUC 185505)
- Requires Caltrans to specify for a utility relocation a reasonable time within which the work of relocation shall commence. (Streets and Highways Code (SHC) Section 680)
- Establishes special provisions and requirements for Caltrans when relocating utilities within and outside freeways. (SHC Sections 700 through 707.5)
- Creates the OIG-HSR to initiate an audit or review regarding oversight related to delivery of the project, and the selection and oversight of contractors related to the project. (Public Utilities Code, Section 187000, et sec.)
FISCAL EFFECT:
Unknown
COMMENTS:
Utility relocation can be one of the greatest risk factors to the scope, schedule, and cost of transit and rail projects. City streets and other rights-of-way are underlain by a wide variety of privately, publicly, or cooperatively-owned utilities for water, natural gas, fuel, and chemical feeds; stormwater, wastewater, electrical power, telephone, cable/TV/Internet fiber, street lighting, and traffic signaling. Some of these require special care such as fiber optic given the practice of threading the fiber through older, abandoned utilities such as gas lines. Projects with alignments near federal buildings such as court houses, or near public or law enforcement agencies may encounter communications lines or other infrastructure that are not readily identified. These buildings and their utilities require special handling.
Transit and rail projects often involve modification to existing underground and overhead infrastructure. The need to relocate or remove existing utilities on transit and rail project sets up encounters with known, unknown, unmarked, or abandoned utilities. The design of utility relocations must accommodate track slabs, rail-tie-ballast track roadbed, catenary poles, signal masts, gravity flow stormwater drainage, station platforms, signage, lighting, signaling, communications lines, power lines, bridge abutments and piers, earth retaining walls, noise walls, streetscaping, landscaping, and other new infrastructure. Relocation of utilities under intersections and sidewalks is even more complicated and overhead contact systems must consider the potential for electrical interference between the traction power wires and other overhead, non-transit, high voltage lines.
Pre-construction activities for transportation infrastructure projects—often referred to as early works— generally includes project sponsors negotiating agreements with various third parties, such as utility owners, railroad companies, and local jurisdictions, before initiating construction. Project sponsors must work with various third parties to acquire right of way and relocate utilities located in the system’s path, and manage betterments. A betterment is an improvement that occurs to the utility during the relocation process that increases capacity and is not otherwise required in order to successfully relocate the utility as a result of the project.
Utility relocations increase project risk. Utilities may be discovered during construction that were not identified during the design phase, leading to unexpected relocations. Coordinating with multiple utility companies and managing their schedules can be complex, especially when dealing with varying permit processes, easement acquisitions, and communication breakdowns. Adjustments to the project's design during construction can trigger the need for utility relocations, causing further delays.
Utility relocations can cause delays. Utility relocations may not be directly included in the main construction contract, leading to delays in getting the work done and potential disputes over costs and responsibility. A utility conflict occurs when a utility must be relocated, adjusted, protected-in-place, or abandoned because of the project. To relocate the utilities that conflict with the guideway on the extensions, project sponsors have to design plans for the relocation of existing utilities and identify the needed right of way. Acquisition of the needed replacement right of way for relocated utility facilities may become a major obstacle to timely utility relocation. Securing the necessary permits and easements for utility relocation can be a time-consuming process, especially on private property. Delays can also be caused by disagreements over land rights or contract terms, and a lack of staff at the third party. Relocating a utility or business is inherently disruptive for the third party.
Delays increase project schedule, cost, and scope. Project delays typically lead to increased labor costs, material costs, and potential claims for damages. Utility relocations can push projects past their planned completion dates, impacting the overall project schedule. Utility work can disrupt traffic flow, especially in urban areas, causing inconvenience to the public. Relocating utilities, especially underground, can pose safety risks if not handled properly.
Effectively managing utility relocations is crucial for on-time and on-budget project completion. The Federal Transit Administration (FTA) Project Management Oversight Program, Utility Relocation - Challenges and Proposed Solutions report of March 2022 identified best practices to address inherent utility relocation challenges. These include active, on-going implementation of mitigations such as meetings, tracking, following-up on action items to maintain accountability, schedule workarounds, communication, cost negotiations, enforcement of compliance with federal regulations, and dedicated attention throughout the project.
FTA’s six best practices for utility relocations are:
- Preplanning: early in a project, all project stakeholders draft and agree to the terms of a Third-Party Utility Relocation Agreement. This agreement serves as the groundwork for all future project interactions between and among the stakeholders and identifies who is responsible for specific utility relocations and the costs associated with those relocations.
- Meet regularly: Hold regular (weekly) meetings with utility companies during the planning, design, and construction phases.
- Cost estimates: Project Sponsors should establish cost estimates with conservative contingency budgets for each utility relocation and not oversimplify the utility costs and potential risks by “bundling” them into a single item.
- Partnering sessions: Define roles and responsibilities of the partners and clarify lines of communication so the decision-making process is understood.
- Segments: For above ground transit and rail projects costs, break the project into segments so that as a segment is cleared of existing utilities new construction can begin.
- Continue regular communication and documentation of contracting terms, conditions, and decisions during construction.
CHSRA. Chapter 796 of 1996 (SB 1420, Kopp) established the CHSRA to plan and construct a high‑speed rail system that would link the state’s major population centers. In November 2008, voters approved Proposition 1A, which authorized the state to sell $10 billion in general obligation bonds to partially fund the system, as well as related projects. Proposition 1A also specified certain criteria and conditions that the system must ultimately achieve. For example, the measure requires that the system be designed to be capable of specified travel times along certain routes, such as nonstop travel from San Francisco to Los Angeles within two hours and forty minutes.
Over the years, the project has faced many challenges largely stemming from a lack of adequate funding to complete even a segment of the project, and delays caused by right of way acquisition and utility relocations. As of May 31, 2025, $14.4 billion has been spent on the project, mostly on work between Merced and Bakersfield.
SB 198 (Committee on Budget and Fiscal Review), Chapter 71, Statutes of 2022 established the OIG-HSR. Since its inception, it has completed six reviews of the project. In its February 21, 2025 review of “Preconstruction Activities for the Merced to Bakersfield Extensions” the OIG-HSR recommended that the Legislature authorize the HSRA to promulgate regulations governing third-party review and approval timeframes for agreements and designs.
The OIG-HSR found that “…procedures do not fundamentally improve the Authority’s ability to get third parties to engage in what can be a time-consuming process. As a potential result, early works on the Merced and Bakersfield extensions have been hindered by delays in executing utility-owner reimbursement agreements, which are generally necessary for utility owners to review and approve utility relocation designs before the Authority can begin construction. In fact, some negotiations have been ongoing for nearly two years without reaching agreement. The Authority’s often time-consuming internal review process, disagreement over contract terms, and little incentive for utility owners to engage in the process in a timely manner have caused the delays. Consequently, the Authority is currently proceeding with utility relocation designs without owner approval, which could lead to more redesigns later.”
The OIG-HSR also found “During our review, Authority staff described what they believe are some causes of challenges in negotiating timely agreements with third parties. Authority staff responsible for working with third parties and overseeing design of the extensions indicated to us that delays result, in part, from third parties’ lack of incentive to engage in the process, which requires work on their part that they wouldn’t otherwise perform. Further, Authority staff overseeing the Central Valley region of the system explained to us that because utility owners, for example, are not under any particular time pressure, there is a resulting imbalance in these negotiations and the Authority’s other interactions with third parties.
“Additionally, Authority staff explained that, in the past, the Authority sometimes agreed to terms that put it in a disadvantageous position—for example, agreeing to compensate third parties for their attorney costs or agreeing to overly tight timelines for construction related to relocating individual utilities. We saw documentation of this type of issue in the example described in the previous section concerning attorney fee reimbursement. Authority staff also indicated that the lack of uniform agreement terms more generally increases difficulties in efficiently reaching and executing agreements. Authority staff expressed that, although the Authority has learned from and is now trying to avoid past mistakes, the legacy of those older agreements means that some third parties expect to receive the same terms as before, making current negotiations challenging.”
Internal processes at CHSRA can cause delays. In its February 2025 review, the OIG-HSR found that third-party-related delays are partially attributable to CHRSA and its project management procedures being inadequate. The OIG-HSR found that HSRA lacks defined negotiation timeframes, and “communicating those timeframes to third parties, would be helpful in making the process more efficient.” The OIG-HSR recommended that “by May 2025, the third-party agreements branch and the contracts and procurement branch should develop procedures with defined timeframes for their internal review processes. These should include defined timeframes for how long staff at each level should attempt to resolve an issue before escalating it.” OIG-HSR also recommended that CHSRA improve internal tracking tools and hire additional legal staff if needed by May 2025. CHSRA agreed with these recommendations.
At the time this analysis was published, OIG-HSR has not fully implemented these recommendation. It is critical for CHSRA to fully address these recommendations.
Caltrans Freeway Master Contracts. In contrast to the HSRA, Caltrans has extensive documentation to guide its utility relocation process.
Caltrans’ Right of Way Utilities Branch is responsible for the coordination of relocating utilities that are in conflict with proposed highway projects. Following enactment of the Collier-Burns Act in 1947, which reformed the state's highway financing system and paved the way for the development of its freeway system, the accumulation of disputed right of way and utility relocation claims was of such magnitude as to threaten delay of the newly enacted freeway program. To meet the problem, the Legislature in 1951 enacted legislation which authorizes Caltrans to enter into contracts with utility owners that govern exclusively the apportionment of relocation costs.
Caltrans’ Freeway Master Contracts (FMCs) govern apportionment of the cost of rearranging facilities in connection with freeway projects in lieu of the provisions in state law. In other words, under FMCs, the relevant provisions of the Streets and Highways Code and other laws have no application to the rearrangement of the facilities on freeway projects and are replaced by the terms of the FMC. The contracts do not affect relocations on conventional highways.
These contracts define terms for considerations that often come up when needing to relocate utilities to accommodate a new freeway such as “betterment”, “wasted work”, and “relocation”. Caltrans practice is consistent with the Federal Highway Administration (FHWA) finding that by addressing these issues proactively, construction projects can minimize the impact of utility relocations on schedules, costs, and overall success.
According to the author, “California High-Speed Rail is critical for our state’s future. The project is already combating climate change, fostering transit-oriented developing, and creating thousands of good-paying union jobs. The project is essential for an abundant, affordable, zero-emission future. It is imperative to help the project cut through permitting and approval-related red tape in order to prevent project cost increases and accelerate project delivery. It shouldn’t be this hard to go through design review and approvals or to relocate utilities. There shouldn’t be so many veto-points that empower project skeptics or opponents to stall the delivery – particularly after the voters approved funding for the project and design and construction are underway. SB 445 implements a High-Speed Rail inspector general recommendation to cut red tape, streamline the project delivery process, curtail veto-points, and reduce and contain project costs. The bill will result in improved and more cost-effective delivery of California High-Speed Rail, ensuring that public dollars are wisely spent on the project.”
Writing in support, the sponsors of this bill, Streets for All states “SB 445 requires the High-Speed Rail Authority to develop and adopt regulations that outline requirements for third party permits and approvals necessary for the project. In doing so, the bill helps the project get built faster and on budget, effectively spending public funds.
“The transportation sector is the largest contributor to greenhouse gas emissions in the state, and the high-speed rail project will drastically reduce these emissions by an estimated 84 to 102 million metric tons of carbon dioxide equivalent over the first 50 years of operation. In order for the project to be built on schedule and on budget, it is imperative that it not be held up by thousands of individual veto points after the decision has been made to fund, design, and construct the project.”
Opposition has not been submitted based on the version of this bill in print on July 9, 2025.
Staff comments. HSRA is relatively new to the challenges and risks created by having to engage with third-parties to construct a major infrastructure project. In contrast, Caltrans has had decades to develop a process that works well when constructing new freeways. This bill acknowledges the impacts of utility relocations on the HSR project’s schedule, cost, and scope and gives CHSRA the authority to establish regulations for the third-party relocation process. The regulatory process is intended to give stakeholders an opportunity to inform the regulations that are established.
A very undeveloped version of this bill was passed out of the Senate and only recently this bill was amended with more substantive content, which since then was very significantly amended. This bill is still a work in progress and has not been thoroughly vetted with stakeholders and CHSRA.
Some outstanding issues the author may wish to address are:
- Is HSRA the appropriate entity to develop regulations or should a somewhat more neutral entity, such as the California State Transportation Agency, develop the regulations? A downside to this approach, may be that they lack HSR-project-specific expertise.
- Does the bill need to more clearly define which third-parties and local agencies would be impacted by the bill?
- Does this bill do enough to limit betterments?
In addition, it will be important to address concerns raised by the next two committees that hear this bill—Assembly Local Government and Assembly Utilities and Energy.
Related and prior legislation. AB 377 (Tangipa of 2025) requires the California High-Speed Rail Authority (CHSRA) as part of the business plan due on or before May 1, 2026, to provide a detailed funding plan for the Merced to Bakersfield segment. This bill is on the Assembly floor.
SB 960 (Wiener), Chapter 630, Statutes of 2024 included a section requiring Caltrans to implement a specific encroachment permit application, review, and approval process for specified complete streets facilities/projects on the departments right-of-way designed to meet existing statutory timelines for the department’s review and approval of such applications.
SB 410 (Becker), Chapter 394, Statutes of 2023 and AB 50 (Wood), Chapter 317, Statutes of 2023 required the CPUC to establish target timelines for energization – or extension of service – activities to customers for the three large Investor-Owned Utilities (IOUs). The CPUC adopted these timelines in September 2024. These timelines apply to energization for all customers – including High-Speed Rail.
SB 198 (Committee on Budget and Fiscal Review), Chapter 71, Statutes of 2022 established the Office of the Inspector General, High-Speed Rail (OIG-HSR) in addition to placing other requirements on HSRA and limiting construction of the project to the Merced to Bakersfield segment, until it is completed.
REGISTERED SUPPORT / OPPOSITION:
Support
350 Bay Area Action
California YIMBY
Streets for All
Opposition
Writing in opposition, as amended on June 30, 2025, not based on the version in print which has been significantly amended.
Association of California Water Agencies
City of Burbank/Burbank Redevelopment Agency
CalBroadband
California Association of Sanitation Agencies
California Municipal Utilities Association
California Special Districts Association
California State Association of Counties
City of Arcata
City of Artesia, California
City of Chino
City of Colton
City of Cypress
City of Downey
City of El Segundo
City of Lakewood
City of LA Palma
City of Laguna Niguel
City of Lakewood CA
City of Los Alamitos
City of Manteca
City of Menifee
City of Merced
City of Moreno Valley
City of Morgan Hill
City of Novato
City of Ontario
City of Palm Desert
City of Rancho Cucamonga
City of San Luis Obispo
City of Stanton
City of Suisun City
City of Thousand Oaks
City of Torrance
City of Vernon
Cucamonga Valley Water District
League of California Cities
Los Angeles County Sanitation Districts
Los Angeles Department of Water and Power
Pacific Gas and Electric Company
Rural County Representatives of California
San Diego Gas and Electric Company
City of San Rafael/Marin County Council of Mayors & Council Members
Sempra Energy and its Affiliates: San Diego Gas & Electric Company and Southern California Gas Company
Southern California Edison
Southern California Gas Company
Town of Mammoth Lakes
US Telecom-The Broadband Association
Urban Counties of California
WatereUse California
Oppose Unless Amended
City of Tustin
Analysis Prepared by: Farra Bracht / TRANS. / (916) 319-2093
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 445 |
THIRD READING
Bill No: SB 445
Author: Wiener (D), et al.
Amended: 4/10/25
Vote: 21
SENATE TRANSPORTATION COMMITTEE: 13-0, 4/22/25
AYES: Cortese, Strickland, Archuleta, Arreguín, Blakespear, Cervantes, Dahle, Gonzalez, Grayson, Limón, Menjivar, Richardson, Umberg
NO VOTE RECORDED: Seyarto, Valladares
SENATE APPROPRIATIONS COMMITTEE: Senate Rule 28.8
SUBJECT: Transportation: planning: complete streets facilities: sustainable transportation projects
SOURCE: Streets for All
DIGEST:
This bill (1) requires the California Department of Transportation (Caltrans) on or before February 1, 2027, instead of January 1, 2027, to develop and adopt a project intake, evaluation, and encroachment permit review process for complete streets facilities that are sponsored by a local jurisdiction or a transit agency. (2) Expresses the intent of the Legislature to amend this bill with legislation that accelerates and makes more reliable third-party permits and approvals for preconstruction and construction activities on sustainable transportation projects, as specified.
ANALYSIS:
Existing law:
- Vests Caltrans with the full possession and control of all state highways and all property and rights in property acquired for state highway purposes.
- Authorizes Caltrans to issue encroachment permits and requires Caltrans to either approve or deny an application from an applicant for an encroachment permit within 60 days of receiving a completed application, as provided.
- Requires Caltrans when notifying the applicant of the denial of an encroachment permit to furnish the applicant a detailed explanation of the reason for the denial.
- Requires Caltrans, on or before January 1, 2027, to develop and adopt a project intake, evaluation, and encroachment permit review process for complete streets facilities that are sponsored by a local jurisdiction or a transit agency.
- Requires Caltrans to annually report to the California Transportation Commission information about project applications pursuant to this process, including the number of applications submitted, permits issued, and days required to process each application.
- Requires Caltrans to appoint an encroachment permit manager in each district to ensure that applications for complete streets facilities are reviewed through the process adopted. Requires the encroachment permit manager to have expertise in bicycle, pedestrian, and transit priority facilities.
This bill:
- Finds and declares that sustainable transportation projects are critical for the growth of the state in a manner that reduces greenhouse gas emissions and helps address the state’s housing shortage. It is in the interest of the state to accelerate the construction of sustainable transportation projects and avoid cost escalation, ensuring that more projects are built in a cost-effective manner.
- Finds and declares that third-party permits and approvals for preconstruction and construction activities, including utility relocations, design review, and issuance of encroachment or other similar permits, can be a source of delay for sustainable transportation projects, potentially resulting in cost escalations and projects being built late and over budget.
- Expresses the intent of the Legislature to amend this bill with legislation that accelerates and makes more reliable third-party permits and approvals for preconstruction and construction activities on sustainable transportation projects, including through requiring lead agencies engage early with third parties, setting timelines on design review activities to ensure prompt responses between parties, and limiting third-party requirements associated with permits and other approvals.
- Requires Caltrans on or before February 1, 2027, instead of January 1, 2027, to develop and adopt a project intake, evaluation, and encroachment permit review process for complete streets facilities that are sponsored by a local jurisdiction or a transit agency.
Comments
- Purpose of this bill. According to the author, “Sustainable transportation projects – including public transportation projects like bus rapid transit, light rail, and passenger rail – are essential for an abundant, affordable, zero-emission future. However, these projects are often plagued by delays as lead agencies navigate a balkanized post-environmental permitting and construction process. Getting approvals and negotiating with 3rd-party entities for utility relocations and other work needed to support a project increases project risk and means we get less clean transportation improvements for more money.
“In its initial form, SB 445 cut red tape to streamline and improve 3rd-party permitting and approval timelines, reducing and containing project costs. Out of a desire to work more closely with the agencies that deliver these projects, the 3rd-party stakeholders whose approvals are necessary for projects to proceed, and the relevant policy committees, I have amended this bill for now to just make a minor change to an existing Caltrans complete streets encroachment permitting code section.”
- Transportation and climate change. Emissions from the transportation sector, the state’s largest source of greenhouse gases (GHGs), are still on the rise despite statewide GHG emission reduction efforts and increasingly ambitious targets. Shifting people to cleaner modes of transportation, such as transit or bicycle and walking, also serves as a major component of the state’s goal to reach carbon neutrality by 2045. According to the California Air Resource Board’s 2022 Scoping Plan, including the transition to cleaner vehicles and low-carbon fuels, the path to carbon neutrality by 2045 also depends on reducing the amount people drive or vehicle miles traveled by 25% by 2030 and 30% by 2045.
- Caltrans Encroachment permits. California has a large network of highways and local streets and roads, consisting of almost 400,000 lane-miles of pavement and over 25,000 bridges. The state highway system, owned and managed by Caltrans, is made up of roughly 50,000 lane miles and 13,000 bridges, including both federal and state highways. Whenever anyone, such as a local government, developer, utility company, or a private citizen wants to do work on any portion of the state’s right-of-way, they must obtain an encroachment permit from Caltrans. Caltrans must either approve or deny an encroachment permit application within 60 calendar days, upon determination that the application is complete. However, the actual time of the total permit process can take much longer based upon the scope and complexity of the proposed work and the completeness of all necessary environmental and other statutory requirements prior to official submittal of the application.
In practice, Caltrans, usually through one of the districts, works directly with the entity applying for the permit. In most instances the length of time for the development of the project and the application for the permit depends on the complexity of the proposed activity. Generally, if a project request is under $1 million in cost, the permit would be issued or denied within the 60 day time period. If a project is over $1 million, it would likely constitute a more complex oversight project, which would bring Caltrans into the project process earlier, such as assisting with design and environmental review, which can cause the permit process to take much longer.
- More complete streets and transit priority facilities on the state highway system. In an effort to facilitate mode shift, the Legislature approved and Governor Newsom signed into law SB 960 (Wiener, Chapter 630, Statutes of 2024), requiring Caltrans to better incorporate complete streets facilities into planning, design, and construction on the state highway system. Complete streets include bicycle and pedestrian facilities and transit priority facilities. Transit priority facilities are changes to the roadway layout and operations to improve transit efficiency, speed, and reliability.
SB 960 requires Caltrans to develop a transit priority policy and adopt guidance for defining performance measures to support the fast movement of transit vehicles on the state highway system. SB 960 also requires Caltrans to build complete streets into its project planning and asset management program. Additionally, Caltrans must commit to specific targets to incorporate complete streets into state highway reconstruction projects, including on entrances and exits that interact with local streets.
- Keeping up with the permits. As detailed above, Caltrans is required to approve or deny an encroachment permit in 60 days, but in practice it may take much longer depending on the size and scope of the project. To help expedite locally-sponsored complete street projects, SB 960 requires Caltrans, on or before January 1, 2027, to develop and adopt a process for project intake, project evaluation, and encroachment permit review for complete streets facilities. The projects must be sponsored by a local jurisdiction or a transit agency.
Additionally, Caltrans must report annually to the California Transportation Commission regarding project applications submitted through the new process. The report must include: the number of completed applications submitted, the number of encroachment permits issued, and the number of days required to process each application. Finally, Caltrans is required to designate an encroachment permit manager in each district to ensure that applications for complete streets facilities are reviewed through the new process. The encroachment permit manager must have expertise in bicycle, pedestrian, and transit priority facilities. SB 445 changes the date Caltrans has to develop and adopt the new process from January 1 to February 1, 2027.
- Author intends to continue working on project delivery streamlining. SB 445 contains findings and declarations regarding the critical need for sustainable transportation projects, including that it is the intent of the state to accelerate the construction of these projects and avoid costs escalations. Additionally, this bill declares that so-called third party permits and approvals for activities, such as utility relocations, design review, and the issuance of permits can be a source of delay for a project. Recent amendments to SB 445 removed language to require certain timeframes for third party agreements and permit and project approvals.
SB 445 also expresses the intent of the Legislature to amend this bill with legislation that accelerates and makes more reliable third-party permits and approvals for preconstruction and construction activities on sustainable transportation projects, including through requiring lead agencies engage early with third parties, setting timelines on design review activities to ensure prompt responses between parties, and limiting third-party requirements associated with permits and other approvals.
After SB 445 was substantially amended on April 9, 2025, the committee reached out to stakeholders to verify their position on this bill. Many stakeholders confirmed their position on the amended bill; however, those writing in support and opposition still speak to the original provisions of SB 445. The issues raised will help serve as the basis for further work as noted by the author. The organizations listed in this analysis confirmed to the committee their position on the amended bill.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: No
SUPPORT: (Verified 5/5/25)
Streets for All (Source)
California Yimby
Climate Action California
Move LA
U.S. High Speed Rail Association
OPPOSITION: (Verified 5/5/25)
Calbroadband
Pacific Gas and Electric Company
San Diego Gas and Electric Company
Southern California Edison
Southern California Gas Company
United States Telecom Association DBA UStelecom - the Broadband Association
Prepared by: Melissa White / TRANS. / (916) 651-4121
5/7/25 16:05:25
**** END ****
SENATE COMMITTEE ON TRANSPORTATION
Senator Dave Cortese, Chair
2025 - 2026 Regular
Bill No: SB 445 Hearing Date: 4/22/2025
Author: | Wiener | ||
Version: | 4/10/2025 Amended | ||
Urgency: | No | Fiscal: | Yes |
Consultant: | Melissa White | ||
SUBJECT: Transportation: planning: complete streets facilities: sustainable transportation projects
DIGEST: This bill requires the California Department of Transportation (Caltrans) on or before February 1, 2027, instead of January 1, 2027, to develop and adopt a project intake, evaluation, and encroachment permit review process for complete streets facilities that are sponsored by a local jurisdiction or a transit agency. Expresses the intent of the Legislature to amend this bill with legislation that accelerates and makes more reliable third-party permits and approvals for preconstruction and construction activities on sustainable transportation projects, as specified.
ANALYSIS:
Existing law:
- Vests Caltrans with the full possession and control of all state highways and all property and rights in property acquired for state highway purposes.
- Authorizes Caltrans to issue encroachment permits and requires Caltrans to either approve or deny an application from an applicant for an encroachment permit within 60 days of receiving a completed application, as provided.
- Requires Caltrans when notifying the applicant of the denial of an encroachment permit to furnish the applicant a detailed explanation of the reason for the denial.
- Requires Caltrans, on or before January 1, 2027, to develop and adopt a project intake, evaluation, and encroachment permit review process for complete streets facilities that are sponsored by a local jurisdiction or a transit agency.
- Requires Caltrans to annually report to the California Transportation Commission information about project applications pursuant to this process, including the number of applications submitted, permits issued, and days required to process each application.
- Requires Caltrans to appoint an encroachment permit manager in each district to ensure that applications for complete streets facilities are reviewed through the process adopted. Requires the encroachment permit manager to have expertise in bicycle, pedestrian, and transit priority facilities.
This bill:
- Finds and declares that sustainable transportation projects are critical for the growth of the state in a manner that reduces greenhouse gas emissions and helps address the state’s housing shortage. It is in the interest of the state to accelerate the construction of sustainable transportation projects and avoid cost escalation, ensuring that more projects are built in a cost-effective manner.
- Finds and declares that third-party permits and approvals for preconstruction and construction activities, including utility relocations, design review, and issuance of encroachment or other similar permits, can be a source of delay for sustainable transportation projects, potentially resulting in cost escalations and projects being built late and over budget.
- Expresses the intent of the Legislature to amend this bill with legislation that accelerates and makes more reliable third-party permits and approvals for preconstruction and construction activities on sustainable transportation projects, including through requiring lead agencies engage early with third parties, setting timelines on design review activities to ensure prompt responses between parties, and limiting third-party requirements associated with permits and other approvals.
- Requires Caltrans on or before February 1, 2027, instead of January 1, 2027, to develop and adopt a project intake, evaluation, and encroachment permit review process for complete streets facilities that are sponsored by a local jurisdiction or a transit agency.
COMMENTS:
- Purpose of the bill. According to the author, “Sustainable transportation projects – including public transportation projects like bus rapid transit, light rail, and passenger rail – are essential for an abundant, affordable, zero-emission future. However, these projects are often plagued by delays as lead agencies navigate a balkanized post-environmental permitting and construction process. Getting approvals and negotiating with 3rd-party entities for utility relocations and other work needed to support a project increases project risk and means we get less clean transportation improvements for more money.
In its initial form, SB 445 cut red tape to streamline and improve 3rd-party permitting and approval timelines, reducing and containing project costs. Out of a desire to work more closely with the agencies that deliver these projects, the 3rd-party stakeholders whose approvals are necessary for projects to proceed, and the relevant policy committees, I have amended the bill for now to just make a minor change to an existing Caltrans complete streets encroachment permitting code section.”
- Transportation and climate change. Emissions from the transportation sector, the state’s largest source of greenhouse gases (GHGs), are still on the rise despite statewide GHG emission reduction efforts and increasingly ambitious targets. Shifting people to cleaner modes of transportation, such as transit or bicycle and walking, also serves as a major component of the state’s goal to reach carbon neutrality by 2045. According to the California Air Resource Board’s (CARB) 2022 Scoping Plan, including the transition to cleaner vehicles and low-carbon fuels, the path to carbon neutrality by 2045 also depends on reducing the amount people drive or vehicle miles traveled (VMT) by 25% by 2030 and 30% by 2045.
- Caltrans Encroachment permits. California has a large network of highways and local streets and roads, consisting of almost 400,000 lane-miles of pavement and over 25,000 bridges. The state highway system, owned and managed by Caltrans, is made up of roughly 50,000 lane miles and 13,000 bridges, including both federal and state highways. Whenever anyone, such as a local government, developer, utility company, or a private citizen wants to do work on any portion of the state’s right-of-way, they must obtain an encroachment permit from Caltrans. Caltrans must either approve or deny an encroachment permit application within 60 calendar days, upon determination that the application is complete. However, the actual time of the total permit process can take much longer based upon the scope and complexity of the proposed work and the completeness of all necessary environmental and other statutory requirements prior to official submittal of the application.
In practice, Caltrans, usually through one of the districts, works directly with the entity applying for the permit. In most instances the length of time for the development of the project and the application for the permit depends on the complexity of the proposed activity. Generally, if a project request is under $1 million in cost, the permit would be issued or denied within the 60 day time period. If a project is over $1 million, it would likely constitute a more complex oversight project, which would bring Caltrans into the project process earlier, such as assisting with design and environmental review, which can cause the permit process to take much longer.
- More complete streets and transit priority facilities on the state highway system. In an effort to facilitate mode shift, the Legislature approved and Governor Newsom signed into law SB 960 (Wiener, Chapter 630, Statutes of 2024), requiring Caltrans to better incorporate complete streets facilities into planning, design, and construction on the state highway system. Complete streets include bicycle and pedestrian facilities and transit priority facilities. Transit priority facilities are changes to the roadway layout and operations to improve transit efficiency, speed, and reliability.
SB 960 requires Caltrans to develop a transit priority policy and adopt guidance for defining performance measures to support the fast movement of transit vehicles on the state highway system. SB 960 also requires Caltrans to build complete streets into its project planning and asset management program. Additionally, Caltrans must commit to specific targets to incorporate complete streets into state highway reconstruction projects, including on entrances and exits that interact with local streets.
- Keeping up with the permits. As detailed above, Caltrans is required to approve or deny an encroachment permit in 60 days, but in practice it may take much longer depending on the size and scope of the project. To help expedite locally-sponsored complete street projects, SB 960 requires Caltrans, on or before January 1, 2027, to develop and adopt a process for project intake, project evaluation, and encroachment permit review for complete streets facilities. The projects must be sponsored by a local jurisdiction or a transit agency.
Additionally, Caltrans must report annually to the California Transportation Commission regarding project applications submitted through the new process. The report must include: the number of completed applications submitted, the number of encroachment permits issued, and the number of days required to process each application. Finally, Caltrans is required to designate an encroachment permit manager in each district to ensure that applications for complete streets facilities are reviewed through the new process. The encroachment permit manager must have expertise in bicycle, pedestrian, and transit priority facilities.
SB 445 would change the date Caltrans has to develop and adopt the new process from January 1 to February 1, 2027.
- Author intends to continue working on permit streamlining. SB 445 contains findings and declarations regarding the critical need for sustainable transportation projects, including that it is the intent of the state to accelerate the construction of these projects and avoid costs escalations. Additionally, the bill declares that so-called third party permits and approvals for activities, such as utility relocations, design review, and the issuance of permits can be a source of delay for a project. Recent amendments to SB 445 removed language to require certain timeframes for third party agreements and permit and project approvals.
SB 445 also expresses the intent of the Legislature to amend the bill with legislation that accelerates and makes more reliable third-party permits and approvals for preconstruction and construction activities on sustainable transportation projects, including through requiring lead agencies engage early with third parties, setting timelines on design review activities to ensure prompt responses between parties, and limiting third-party requirements associated with permits and other approvals.
After recent amendments to the bill, the organizations writing in support and opposition still speak to the original provisions of SB 445. Should the bill be approved by this committee, the issues raised will help serve as the basis for further work as noted by the author. The organizations listed in this analysis confirmed to the committee their position on the amended bill.
- Double referral. This bill is double referred to the Senate Local Government Committee.
Related/PREVIOUS Legislation:
AB 1399 (Hoover, 2025) -- Would require Caltrans to perform additional actions for an encroachment permit application for a broadband facility, including, but not limited to, requiring the application and review process for the application to be uniform throughout the state, and would require a broadband facility encroachment permit application that is deemed complete to be deemed approved. This is pending in the Assembly Transportation Committee.
SB 960 (Wiener, Chapter 630, Statutes of 2024) -- Required Caltrans to include complete streets assets in its asset management plan, system highway management plan, and in the plain language performance report for the state highway operation and protection program (SHOPP). Required Caltrans to develop and adopt transit priority policy and guidelines. Required Caltrans to commit to specific 4-year targets to incorporate complete streets facilities in the SHOPP. Required Caltrans, on or before January 1, 2027, to develop and adopt a project intake, evaluation, and encroachment permit review process for complete streets facilities that are sponsored by a local jurisdiction or a transit agency.
SB 760 (Wiener, 2018) -- Would have restricted Caltrans from denying an application for a permit for work within the state highway right-of-way solely because the work will not be performed in accordance with Caltrans approved plans and specifications if the improvement would not affect the operation of the state highway and is instead performed in accordance with local agency plans and specifications. This bill died in the Assembly Transportation Committee.
FISCAL EFFECT: Appropriation: Fiscal Com.: Local:
POSITIONS: (Communicated to the committee before noon on Wednesday,
April 16, 2025.)
SUPPORT:
Streets for All (sponsor)
California Yimby
Climate Action California
Move LA
U.S. High Speed Rail Association
OPPOSITION:
Pacific Gas and Electric Company
San Diego Gas and Electric Company
Southern California Edison
Southern California Gas Company
-- END --
Discussed in Hearing
Assembly Standing Committee on Utilities and Energy
Assembly Standing Committee on Local Government
Assembly Standing Committee on Transportation
Senate Floor
Senate Standing Committee on Transportation
Bill Author
Bill Co-Author(s):