SB 706: Public contracts: progressive design-build: local agencies.
- Session Year: 2023-2024
- House: Senate
- Latest Version Date: 2023-10-08
Current Status:
Passed
(2023-10-08: Chaptered by Secretary of State. Chapter 500, Statutes of 2023.)
Introduced
In Committee
First Chamber
In Committee
Second Chamber
Enacted
Existing law authorizes the Director of General Services to use the progressive design-build procurement process for the construction of up to 3 capital outlay projects, as jointly determined by the Department of General Services and the Department of Finance, and prescribes that process. Existing law defines progressive design-build as a project delivery process in which both the design and construction of a project are procured from a single entity that is selected through a qualifications-based selection at the earliest feasible stage of the project.
Existing law, until January 1, 2029, authorizes local agencies, defined as any city, county, city and county, or special district authorized by law to provide for the production, storage, supply, treatment, or distribution of any water from any source, to use the progressive design-build process for up to 15 public works projects in excess of $5,000,000 for each project, similar to the progressive design-build process authorized for use by the Director of General Services.
Existing law requires a local agency that uses the progressive design-build process to submit, no later than January 1, 2028, to the appropriate policy and fiscal committees of the Legislature a report on the use of the progressive design-build process containing specified information, including a description of the projects awarded using the progressive design-build process. Existing law requires the design-build entity and its general partners or joint venture members to verify specified information under penalty of perjury.
This bill would, until January 1, 2030, provide additional authority for cities, counties, cities and counties, or special districts to use the progressive design-build process for up to 10 public works in excess of $5,000,000, not limited to water-related projects, excluding projects on state-owned or state-operated facilities. The bill would require information to be provided under penalty of perjury and would require similar reports due no later than December 31, 2028.
By expanding the crime of perjury, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law authorizes the Director of General Services to use the progressive design-build procurement process for the construction of up to 3 capital outlay projects, as jointly determined by the Department of General Services and the Department of Finance, and prescribes that process. Existing law defines progressive design-build as a project delivery process in which both the design and construction of a project are procured from a single entity that is selected through a qualifications-based selection at the earliest feasible stage of the project.
Existing law, until January 1, 2029, authorizes local agencies, defined as any city, county, city and county, or special district authorized by law to provide for the production, storage, supply, treatment, or distribution of any water from any source, to use the progressive design-build process for up to 15 public works projects in excess of $5,000,000 for each project, similar to the progressive design-build process authorized for use by the Director of General Services.
Existing law requires a local agency that uses the progressive design-build process to submit, no later than January 1, 2028, to the appropriate policy and fiscal committees of the Legislature a report on the use of the progressive design-build process containing specified information, including a description of the projects awarded using the progressive design-build process. Existing law requires the design-build entity and its general partners or joint venture members to verify specified information under penalty of perjury.
This bill would, until January 1, 2030, provide additional authority for cities, counties, cities and counties, or special districts to use the progressive design-build process for up to 10 public works in excess of $5,000,000, not limited to water-related projects, excluding projects on state-owned or state-operated facilities. The bill would require information to be provided under penalty of perjury and would require similar reports due no later than December 31, 2028.
By expanding the crime of perjury, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law authorizes the Director of General Services to use the progressive design-build procurement process for the construction of up to 3 capital outlay projects, as jointly determined by the Department of General Services and the Department of Finance, and prescribes that process. Existing law defines progressive design-build as a project delivery process in which both the design and construction of a project are procured from a single entity that is selected through a qualifications-based selection at the earliest feasible stage of the project.
Existing law, until January 1, 2029, authorizes local agencies, defined as any city, county, city and county, or special district authorized by law to provide for the production, storage, supply, treatment, or distribution of any water from any source, to use the progressive design-build process for up to 15 public works projects in excess of $5,000,000 for each project, similar to the progressive design-build process authorized for use by the Director of General Services.
Existing law requires a local agency that uses the progressive design-build process to submit, no later than January 1, 2028, to the appropriate policy and fiscal committees of the Legislature a report on the use of the progressive design-build process containing specified information, including a description of the projects awarded using the progressive design-build process. Existing law requires the design-build entity and its general partners or joint venture members to verify specified information under penalty of perjury.
This bill would authorize all would, until January 1, 2030, provide additional authority for cities, counties, city cities and counties, or special districts to use the progressive design-build process for other projects in addition up to 10 public works in excess of $5,000,000, not limited to water-related projects, excluding projects on state-owned or -operated state-operated facilities. The bill would extend these provisions until January 1, 2030. The bill would change the required reporting date to require information to be provided under penalty of perjury and would require similar reports due no later than December 31, 2028.
By extending the duration of the progressive design-build authorization for local agencies and expanding the projects that may use the progressive design-build process and thus expanding the crime of perjury, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law authorizes the Director of General Services to use the progressive design-build procurement process for the construction of up to 3 capital outlay projects, as jointly determined by the Department of General Services and the Department of Finance, and prescribes that process. Existing law defines progressive design-build as a project delivery process in which both the design and construction of a project are procured from a single entity that is selected through a qualifications-based selection at the earliest feasible stage of the project.
Existing law, until January 1, 2029, authorizes local agencies, defined as any city, county, city and county, or special district authorized by law to provide for the production, storage, supply, treatment, or distribution of any water from any source, to use the progressive design-build process for up to 15 public works projects in excess of $5,000,000 for each project, similar to the progressive design-build process authorized for use by the Director of General Services.
Existing law requires a local agency that uses the progressive design-build process to submit, no later than January 1, 2028, to the appropriate policy and fiscal committees of the Legislature a report on the use of the progressive design-build process containing specified information, including a description of the projects awarded using the progressive design-build process. Existing law requires the design-build entity and its general partners or joint venture members to verify specified information under penalty of perjury.
This bill would authorize all cities, counties, city and counties, or special districts to use the progressive design-build process for other projects in addition to water-related projects and projects, excluding projects on state-owned or -operated facilities. The bill would extend these provisions until January 1, 2030. The bill would change the required reporting date to no later than December 31, 2028.
By extending the duration of the progressive design-build authorization for local agencies and expanding the projects that may use the progressive design-build process and thus expanding the crime of perjury, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law authorizes the Director of General Services to use the progressive design-build procurement process for the construction of up to 3 capital outlay projects, as jointly determined by the Department of General Services and the Department of Finance, and prescribes that process. Existing law defines progressive design-build as a project delivery process in which both the design and construction of a project are procured from a single entity that is selected through a qualifications-based selection at the earliest feasible stage of the project.
Existing law, until January 1, 2029, authorizes local agencies, defined as any city, county, city and county, or special district authorized by law to provide for the production, storage, supply, treatment, or distribution of any water from any source, to use the progressive design-build process for up to 15 public works projects in excess of $5,000,000 for each project, similar to the progressive design-build process authorized for use by the Director of General Services.
Existing law requires a local agency that uses the progressive design-build process to submit, no later than January 1, 2028, to the appropriate policy and fiscal committees of the Legislature a report on the use of the progressive design-build process containing specified information, including a description of the projects awarded using the progressive design-build process. Existing law requires the design-build entity and its general partners or joint venture members to verify specified information under penalty of perjury.
This bill would authorize all cities, counties, city and counties, or special districts to use the progressive design-build process for other projects in addition to water-related projects. projects and would extend these provisions until January 1, 2030. The bill would change the required reporting date to no later than December 31, 2028.
By extending the duration of the progressive design-build authorization for local agencies and expanding the projects that may use the progressive design-build process and thus expanding the crime of perjury, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law authorizes the Director of General Services to use the progressive design-build procurement process for the construction of up to 3 capital outlay projects, as jointly determined by the Department of General Services and the Department of Finance, and prescribes that process. Existing law defines progressive design-build as a project delivery process in which both the design and construction of a project are procured from a single entity that is selected through a qualifications-based selection at the earliest feasible stage of the project.
Existing law, until January 1, 2029, authorizes local agencies, defined as any city, county, city and county, or special district authorized by law to provide for the production, storage, supply, treatment, or distribution of any water from any source, to use the progressive design-build process for up to 15 public works projects in excess of $5,000,000 for each project, similar to the progressive design-build process authorized for use by the Director of General Services.
Existing law requires a local agency that uses the progressive design-build process to submit, no later than January 1, 2028, to the appropriate policy and fiscal committees of the Legislature a report on the use of the progressive design-build process containing specified information, including a description of the projects awarded using the progressive design-build process. Existing law requires the design-build entity and its general partners or joint venture members to verify specified information under penalty of perjury.
This bill would remove the 15 project maximum and would authorize all cities, counties, city and counties, or special districts to use the progressive design-build process for other projects in addition to water-related projects. The bill would change the required reporting date to no later than December 31, 2028.
By expanding the projects that may use the progressive design-build process and thus expanding the crime of perjury, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law authorizes the Director of General Services to use the progressive design-build procurement process for the construction of up to 3 capital outlay projects, as jointly determined by the Department of General Services and the Department of Finance, and prescribes that process. Existing law defines progressive design-build as a project delivery process in which both the design and construction of a project are procured from a single entity that is selected through a qualifications-based selection at the earliest feasible stage of the project.
Existing law, until January 1, 2029, authorizes local agencies, defined as any city, county, city and county, or special district authorized by law to provide for the production, storage, supply, treatment, or distribution of any water from any source, to use the progressive design-build process for up to 15 public works projects in excess of $5,000,000 for each project, similar to the progressive design-build process authorized for use by the Director of General Services.
Existing law requires a local agency that uses the progressive design-build process to submit, no later than January 1, 2028, to the appropriate policy and fiscal committees of the Legislature a report on the use of the progressive design-build process containing specified information, including a description of the projects awarded using the progressive design-build process. Existing law requires the design-build entity and its general partners or joint venture members to verify specified information under penalty of perjury.
This bill would remove the 15 project maximum and would authorize all cities, counties, city and counties, or special districts to use the progressive design-build process for other projects in addition to water-related projects. The bill would change the required reporting date to no later than December 31, 2028.
By expanding the projects that may use the progressive design-build process and thus expanding the crime of perjury, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
For purposes of this chapter, the following definitions apply:
(a)(1)Best value means a value determined by evaluation of objective criteria that may include, but are not limited to, price, features, function, life-cycle costs, experience, and past performance.
(2)A best value determination may involve the selection of the lowest cost proposal meeting the interests of the local agency and the objectives of the project.
(b)Construction subcontract means each subcontract awarded by the design-build entity to a subcontractor that will perform work or labor or render service to the design-build entity in or about the construction of the work or improvement, or a subcontractor licensed by the State of California that, under subcontract to the design-build entity, specially fabricates and installs a portion of the work or improvement according to detailed drawings contained in the plans and specifications produced by the design-build team.
(c)Design-build entity means a corporation, limited liability company, partnership, joint venture, or other legal entity that is able to provide appropriately licensed contracting, architectural, and engineering services as needed pursuant to a design-build contract.
(d)Design-build project means any project using the progressive design-build construction procurement process described in this chapter, but does not include projects on state-owned or state-operated facilities.
(e)Design-build team means the design-build entity itself and the individuals and other entities identified by the design-build entity as members of its team. Members shall include the general contractor and, if utilized in the design of the project, all electrical, mechanical, and plumbing contractors.
(f)Guaranteed maximum price means the maximum payment amount agreed upon by the local agency and the design-build entity for the design-build entity to finish all remaining design, preconstruction, and construction activities sufficient to complete and close out the project.
(g)Local agency means a city, county, city and county, or special district.
(h)Progressive design-build means a project delivery process in which both the design and construction of a project are procured from a single entity that is selected through a qualifications-based selection at the earliest feasible stage of the project.
(i)Qualifications-based selection means the process by which the local agency solicits for services from the design-build entities and that price is not the sole factor as the basis of award.
22185.1.A local agency may procure progressive design-build contracts and use the progressive design-build contracting process described in this chapter for up to 10 public works projects in excess of five million dollars ($5,000,000) for each project.
22185.2.A local agency entering into design-build contracts authorized under this chapter shall develop guidelines for a standard organizational conflict-of-interest policy, consistent with applicable law, regarding the ability of a person or entity that performs services for the local agency relating to the solicitation of a design-build project, to submit a proposal as a design-build entity, or to join a design-build team.
22185.3.The procurement process for progressive design-build projects shall progress as follows:
(a)The local agency shall prepare and issue a request for qualifications in order to select a design-build entity to execute the project. The request for qualifications shall include, but is not limited to, the following elements:
(1)Documentation of the size, type, and desired design character of the project and any other information deemed necessary to describe adequately the local agencys needs, including the expected cost range, the methodology that will be used by the local agency to evaluate the design-build entitys qualifications, the procedure for final selection of the design-build entity, and any other information deemed necessary by the local agency to inform interested parties of the contracting opportunity.
(2)Significant factors that the local agency reasonably expects to consider in evaluating qualifications, including technical design and construction expertise, and all other non-price-related factors. The local agency may require that a preliminary cost estimate be included in the design-build entities responses and consider those costs in evaluating the statements of qualifications.
(3)The relative importance or the weight assigned to each of the factors identified in the request for qualifications.
(4)A standard template request for statements of qualifications prepared by the local agency. In preparing the standard template, the local agency may consult with the construction industry, the building trades and surety industry, and other local agencies interested in using the authorization provided by this chapter. The template shall require the following information:
(A)If the design-build entity is a privately held corporation, limited liability company, partnership, or joint venture, a listing of all of the entitys shareholders, partners, or members known at the time of the statement of qualification submission who will perform work on the project.
(B)Evidence that the members of the design-build team have completed, or have demonstrated the experience, competency, capability, and capacity to complete, projects of similar size, scope, or complexity, and that proposed key personnel have sufficient experience and training to competently manage and complete the design and construction of the project, and a financial statement that ensures that the design-build entity has the capacity to complete the project.
(C)The licenses, registration, and credentials required to design and construct the project, including, but not limited to, information on the revocation or suspension of any license, credential, or registration.
(D)Evidence that establishes that the design-build entity has the capacity to obtain all required payment and performance bonding, liability insurance, and errors and omissions insurance.
(E)Information concerning workers compensation experience history and a worker safety program.
(F)If the proposed design-build entity is a corporation, limited liability company, partnership, joint venture, or other legal entity, a copy of the organizational documents or agreement committing to form the organization.
(G)An acceptable safety record. A proposers safety record shall be deemed acceptable if its experience modification rate for the most recent three-year period is an average of 1.00 or less, and its average total recordable injury or illness rate and average lost work rate for the most recent three-year period does not exceed the applicable statistical standards for its business category or if the proposer is a party to an alternative dispute resolution system as provided for in Section 3201.5 of the Labor Code.
(5)The information required under this subdivision shall be certified under penalty of perjury by the design-build entity and its general partners or joint venture members.
(b)(1)A design-build entity shall not be evaluated for selection unless the entity provides an enforceable commitment to the local agency that the entity and its subcontractors at every tier will use a skilled and trained workforce to perform all work on the project or contract that falls within an apprenticeable occupation in the building and construction trades, in accordance with Chapter 2.9 (commencing with Section 2600) of Part 1.
(2)This subdivision shall not apply if one or more of the following requirements are met:
(A)The local agency has entered into a project labor agreement that will bind all contractors and subcontractors performing work on the project or contract to use a skilled and trained workforce, and the entity agrees to be bound by that project labor agreement.
(B)The project or contract is being performed under the extension or renewal of a project labor agreement that was entered into by the local agency before January 1, 2023.
(C)The entity has entered into a project labor agreement that will bind the entity and all its subcontractors at every tier performing the project or contract to use a skilled and trained workforce.
(3)For purposes of this subdivision, project labor agreement has the same meaning as provided in paragraph (1) of subdivision (b) of Section 2500.
(c)At the close of the solicitation period, the local agency shall review the submissions. The local agency may evaluate submissions based solely upon the information provided in each design-build entitys statement of qualifications. The local agency may also interview some or all of the design-build entities to further evaluate their qualifications for the project.
(d)Notwithstanding any other provision of this code, upon issuance of a contract award, the local agency shall publicly announce its award, identifying the design-build entity to which the award is made, along with a statement regarding the basis of the award. The statement regarding the local agencys contract award and the contract file shall provide sufficient information to satisfy an external audit.
22185.4.(a)The design-build entity shall provide payment and performance bonds for the project in the form and in the amount required by the local agency, and issued by a California admitted surety. The amount of the payment bond shall not be less than the amount of the performance bond.
(b)The design-build contract shall require errors and omissions insurance coverage for the design elements of the project.
(c)The local agency shall develop a standard form of payment and performance bond for its design-build projects.
22185.5.(a)After selecting a design-build entity based upon qualifications, the local agency may enter into a contract and direct the design-build entity to begin design and preconstruction activities sufficient to establish a guaranteed maximum price for the project.
(b)(1)Upon agreement of the guaranteed maximum price for the project, the local agency, at its sole and absolute discretion, may amend its contract with the design build entity to contract for the remaining design, preconstruction, and construction activities sufficient to complete and close out the project, consistent with the guaranteed maximum price. In the event that there are unforeseen site conditions, the local agency may amend its contract with the design build entity accordingly and consistent with the guaranteed maximum price, to enable the entity to complete the remaining design, preconstruction, and construction activities sufficient to complete and close out the project.
(2)If the cost for completing all remaining design, preconstruction, and construction activities sufficient to complete and close out the project exceed the guaranteed maximum price, the costs exceeding the guaranteed maximum price shall be the responsibility of the design-build entity. If the cost for these activities are less than the guaranteed maximum price, the design-build entity shall not be entitled to the difference between the cost and the guaranteed maximum price unless there is a prior written agreement concerning the sharing of these funds. For purposes of this section, cost shall include the design-build entitys direct costs, general conditions, overhead, and fee.
(c)(1)If the local agency and the design-build entity do not reach agreement on a guaranteed maximum price, or the local agency otherwise elects not to amend the design-build entitys contract to complete the remaining work, the local agency may solicit proposals to complete the project from firms that submitted statements of qualifications pursuant to Section 22185.3. The local agency may also, upon written determination that it is in the best interest of the city, county, city and county, or special district, as applicable, to do so, formally solicit proposals from other design-build entities, and contract award shall be made on a best value basis.
(2)The design professionals responsible for performing design services on behalf of a design-build entity that has been replaced pursuant to paragraph (1) shall have sole liability for their design errors and omissions, provided the local agency elects to use their complete and stamped designs with subsequent design-build entities or licensed contractors.
22185.6.(a)The local agency, in each design-build request for qualifications, may identify specific types of subcontractors that shall be included in the design-build entitys statement of qualifications. All construction subcontractors that are identified in the statement of qualifications shall be afforded the protections of Chapter 4 (commencing with Section 4100) of Part 1.
(b)Following award of the design-build contract, except for those construction subcontractors listed in the statement of qualifications, the design-build entity shall proceed as listed in this subdivision in awarding construction subcontracts with a value exceeding one-half of 1 percent of the contract price allocable to construction work for projects with a contract value of greater than or equal to ten million dollars ($10,000,000).
(1)Provide public notice of availability of work to be subcontracted in accordance with the publication requirements applicable to the competitive bidding process of the local agency, including a fixed date and time on which qualifications statements, bids, or proposals will be due.
(2)Establish reasonable qualification criteria and standards.
(3)Award the subcontract on a best value basis. The process may include prequalification or short-listing.
(c)Subcontractors awarded construction subcontracts under this subdivision shall be afforded all the protections of Chapter 4 (commencing with Section 4100) of Part 1.
(d)A construction subcontractor licensed pursuant to Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code that provides design services used on a project authorized by this chapter shall not be subject to any liability arising from their design if the construction subcontract for that design is not performed by that subcontractor.
22185.7.(a)If the local agency elects to award a project pursuant to this chapter, retention proceeds withheld by the local agency from the design-build entity shall not exceed 5 percent if a performance and payment bond, issued by an admitted surety insurer, is required in the solicitation. Work performed to establish the guaranteed maximum price shall not be subject to retention.
(b)In a contract between the design-build entity and a subcontractor, and in a contract between a subcontractor and any subcontractor thereunder, the percentage of the retention proceeds withheld shall not exceed the percentage specified in the contract between the local agency and the design-build entity. If the design-build entity provides written notice to any subcontractor that is not a member of the design-build entity, before or at the time the bid is requested, that a bond may be required, and the subcontractor subsequently is unable or refuses to furnish a bond to the design-build entity, then the design-build entity may withhold retention proceeds in excess of the percentage specified in the contract between the local agency and the design-build entity from any payment made by the design-build entity to the subcontractor.
22185.8.(a)Notwithstanding Section 10231.5 of the Government Code, no later than December 31, 2028, a local agency that uses the progressive design-build process pursuant to this chapter shall submit, to the appropriate policy and fiscal committees of the Legislature, a report on the use of the progressive design-build process.
(b)The report shall include, but is not limited to, the following information:
(1)A description of the project or projects awarded using the progressive design-build process.
(2)The contract award amounts.
(3)The design-build entities awarded the project or projects.
(4)A description of any written protests concerning any aspect of the solicitation, bid, or award of the contracts, including the resolution of the protests.
(5)A description of the prequalification process.
(6)The number of specialty subcontractors listed by construction trade type, on each project, that provided design services, but did not meet the target price for their scope of work, and therefore did not perform construction services on that project.
(7)Whether or not any portion of a design prepared by the specialty subcontractor that did not perform the construction work for that design was used by the local agency.
(8)The number of specialty subcontractors listed by construction trade type, on each project, that meet the definition of a small business, as specified in paragraph (1) of subdivision (d) of Section 14837 of the Government Code.
(9)The number of specialty subcontractors listed by construction trade type, on each project, that meet the definition of a microbusiness, as specified in paragraph (2) of subdivision (d) of Section 14837 of the Government Code.
(10)If a project awarded under this chapter has been completed, an assessment of the project performance, including, but not limited to, a summary of any delays or cost increases.
(c)The report submitted pursuant to subdivision (a) shall be submitted in compliance with Section 9795 of the Government Code.
22185.9.Nothing in this chapter authorizes a local agency to perform work on a state-owned or state-operated facility.
22185.10.Nothing in this chapter affects, expands, alters, or limits any rights or remedies otherwise available at law.
22185.11.This chapter shall remain in effect only until January 1, 2030, and as of that date is repealed.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
For purposes of this chapter, the following definitions apply:
(a)(1)Best value means a value determined by evaluation of objective criteria that may include, but are not limited to, price, features, function, life-cycle costs, experience, and past performance.
(2)A best value determination may involve the selection of the lowest cost proposal meeting the interests of the local agency and the objectives of the project.
(b)Construction subcontract means each subcontract awarded by the design-build entity to a subcontractor that will perform work or labor or render service to the design-build entity in or about the construction of the work or improvement, or a subcontractor licensed by the State of California that, under subcontract to the design-build entity, specially fabricates and installs a portion of the work or improvement according to detailed drawings contained in the plans and specifications produced by the design-build team.
(c)Design-build entity means a corporation, limited liability company, partnership, joint venture, or other legal entity that is able to provide appropriately licensed contracting, architectural, and engineering services as needed pursuant to a design-build contract.
(d)Design-build project means any project using the progressive design-build construction procurement process described in this chapter, but does not include projects on state-owned or state-operated facilities.
(e)Design-build team means the design-build entity itself and the individuals and other entities identified by the design-build entity as members of its team. Members shall include the general contractor and, if utilized in the design of the project, all electrical, mechanical, and plumbing contractors.
(f)Guaranteed maximum price means the maximum payment amount agreed upon by the local agency and the design-build entity for the design-build entity to finish all remaining design, preconstruction, and construction activities sufficient to complete and close out the project.
(g)Local agency means a city, county, city and county, or special district.
(h)Progressive design-build means a project delivery process in which both the design and construction of a project are procured from a single entity that is selected through a qualifications-based selection at the earliest feasible stage of the project.
(i)Qualifications-based selection means the process by which the local agency solicits for services from the design-build entities and that price is not the sole factor as the basis of award.
22185.1.A local agency may procure progressive design-build contracts and use the progressive design-build contracting process described in this chapter for up to 10 public works projects in excess of five million dollars ($5,000,000) for each project.
22185.2.A local agency entering into design-build contracts authorized under this chapter shall develop guidelines for a standard organizational conflict-of-interest policy, consistent with applicable law, regarding the ability of a person or entity that performs services for the local agency relating to the solicitation of a design-build project, to submit a proposal as a design-build entity, or to join a design-build team.
22185.3.The procurement process for progressive design-build projects shall progress as follows:
(a)The local agency shall prepare and issue a request for qualifications in order to select a design-build entity to execute the project. The request for qualifications shall include, but is not limited to, the following elements:
(1)Documentation of the size, type, and desired design character of the project and any other information deemed necessary to describe adequately the local agencys needs, including the expected cost range, the methodology that will be used by the local agency to evaluate the design-build entitys qualifications, the procedure for final selection of the design-build entity, and any other information deemed necessary by the local agency to inform interested parties of the contracting opportunity.
(2)Significant factors that the local agency reasonably expects to consider in evaluating qualifications, including technical design and construction expertise, and all other non-price-related factors. The local agency may require that a preliminary cost estimate be included in the design-build entities responses and consider those costs in evaluating the statements of qualifications.
(3)The relative importance or the weight assigned to each of the factors identified in the request for qualifications.
(4)A standard template request for statements of qualifications prepared by the local agency. In preparing the standard template, the local agency may consult with the construction industry, the building trades and surety industry, and other local agencies interested in using the authorization provided by this chapter. The template shall require the following information:
(A)If the design-build entity is a privately held corporation, limited liability company, partnership, or joint venture, a listing of all of the entitys shareholders, partners, or members known at the time of the statement of qualification submission who will perform work on the project.
(B)Evidence that the members of the design-build team have completed, or have demonstrated the experience, competency, capability, and capacity to complete, projects of similar size, scope, or complexity, and that proposed key personnel have sufficient experience and training to competently manage and complete the design and construction of the project, and a financial statement that ensures that the design-build entity has the capacity to complete the project.
(C)The licenses, registration, and credentials required to design and construct the project, including, but not limited to, information on the revocation or suspension of any license, credential, or registration.
(D)Evidence that establishes that the design-build entity has the capacity to obtain all required payment and performance bonding, liability insurance, and errors and omissions insurance.
(E)Information concerning workers compensation experience history and a worker safety program.
(F)If the proposed design-build entity is a corporation, limited liability company, partnership, joint venture, or other legal entity, a copy of the organizational documents or agreement committing to form the organization.
(G)An acceptable safety record. A proposers safety record shall be deemed acceptable if its experience modification rate for the most recent three-year period is an average of 1.00 or less, and its average total recordable injury or illness rate and average lost work rate for the most recent three-year period does not exceed the applicable statistical standards for its business category or if the proposer is a party to an alternative dispute resolution system as provided for in Section 3201.5 of the Labor Code.
(5)The information required under this subdivision shall be certified under penalty of perjury by the design-build entity and its general partners or joint venture members.
(b)(1)A design-build entity shall not be evaluated for selection unless the entity provides an enforceable commitment to the local agency that the entity and its subcontractors at every tier will use a skilled and trained workforce to perform all work on the project or contract that falls within an apprenticeable occupation in the building and construction trades, in accordance with Chapter 2.9 (commencing with Section 2600) of Part 1.
(2)This subdivision shall not apply if one or more of the following requirements are met:
(A)The local agency has entered into a project labor agreement that will bind all contractors and subcontractors performing work on the project or contract to use a skilled and trained workforce, and the entity agrees to be bound by that project labor agreement.
(B)The project or contract is being performed under the extension or renewal of a project labor agreement that was entered into by the local agency before January 1, 2023.
(C)The entity has entered into a project labor agreement that will bind the entity and all its subcontractors at every tier performing the project or contract to use a skilled and trained workforce.
(3)For purposes of this subdivision, project labor agreement has the same meaning as provided in paragraph (1) of subdivision (b) of Section 2500.
(c)At the close of the solicitation period, the local agency shall review the submissions. The local agency may evaluate submissions based solely upon the information provided in each design-build entitys statement of qualifications. The local agency may also interview some or all of the design-build entities to further evaluate their qualifications for the project.
(d)Notwithstanding any other provision of this code, upon issuance of a contract award, the local agency shall publicly announce its award, identifying the design-build entity to which the award is made, along with a statement regarding the basis of the award. The statement regarding the local agencys contract award and the contract file shall provide sufficient information to satisfy an external audit.
22185.4.(a)The design-build entity shall provide payment and performance bonds for the project in the form and in the amount required by the local agency, and issued by a California admitted surety. The amount of the payment bond shall not be less than the amount of the performance bond.
(b)The design-build contract shall require errors and omissions insurance coverage for the design elements of the project.
(c)The local agency shall develop a standard form of payment and performance bond for its design-build projects.
22185.5.(a)After selecting a design-build entity based upon qualifications, the local agency may enter into a contract and direct the design-build entity to begin design and preconstruction activities sufficient to establish a guaranteed maximum price for the project.
(b)(1)Upon agreement of the guaranteed maximum price for the project, the local agency, at its sole and absolute discretion, may amend its contract with the design build entity to contract for the remaining design, preconstruction, and construction activities sufficient to complete and close out the project, consistent with the guaranteed maximum price. In the event that there are unforeseen site conditions, the local agency may amend its contract with the design build entity accordingly and consistent with the guaranteed maximum price, to enable the entity to complete the remaining design, preconstruction, and construction activities sufficient to complete and close out the project.
(2)If the cost for completing all remaining design, preconstruction, and construction activities sufficient to complete and close out the project exceed the guaranteed maximum price, the costs exceeding the guaranteed maximum price shall be the responsibility of the design-build entity. If the cost for these activities are less than the guaranteed maximum price, the design-build entity shall not be entitled to the difference between the cost and the guaranteed maximum price unless there is a prior written agreement concerning the sharing of these funds. For purposes of this section, cost shall include the design-build entitys direct costs, general conditions, overhead, and fee.
(c)(1)If the local agency and the design-build entity do not reach agreement on a guaranteed maximum price, or the local agency otherwise elects not to amend the design-build entitys contract to complete the remaining work, the local agency may solicit proposals to complete the project from firms that submitted statements of qualifications pursuant to Section 22185.3. The local agency may also, upon written determination that it is in the best interest of the city, county, city and county, or special district, as applicable, to do so, formally solicit proposals from other design-build entities, and contract award shall be made on a best value basis.
(2)The design professionals responsible for performing design services on behalf of a design-build entity that has been replaced pursuant to paragraph (1) shall have sole liability for their design errors and omissions, provided the local agency elects to use their complete and stamped designs with subsequent design-build entities or licensed contractors.
22185.6.(a)The local agency, in each design-build request for qualifications, may identify specific types of subcontractors that shall be included in the design-build entitys statement of qualifications. All construction subcontractors that are identified in the statement of qualifications shall be afforded the protections of Chapter 4 (commencing with Section 4100) of Part 1.
(b)Following award of the design-build contract, except for those construction subcontractors listed in the statement of qualifications, the design-build entity shall proceed as listed in this subdivision in awarding construction subcontracts with a value exceeding one-half of 1 percent of the contract price allocable to construction work for projects with a contract value of greater than or equal to ten million dollars ($10,000,000).
(1)Provide public notice of availability of work to be subcontracted in accordance with the publication requirements applicable to the competitive bidding process of the local agency, including a fixed date and time on which qualifications statements, bids, or proposals will be due.
(2)Establish reasonable qualification criteria and standards.
(3)Award the subcontract on a best value basis. The process may include prequalification or short-listing.
(c)Subcontractors awarded construction subcontracts under this subdivision shall be afforded all the protections of Chapter 4 (commencing with Section 4100) of Part 1.
(d)A construction subcontractor licensed pursuant to Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code that provides design services used on a project authorized by this chapter shall not be subject to any liability arising from their design if the construction subcontract for that design is not performed by that subcontractor.
22185.7.(a)If the local agency elects to award a project pursuant to this chapter, retention proceeds withheld by the local agency from the design-build entity shall not exceed 5 percent if a performance and payment bond, issued by an admitted surety insurer, is required in the solicitation. Work performed to establish the guaranteed maximum price shall not be subject to retention.
(b)In a contract between the design-build entity and a subcontractor, and in a contract between a subcontractor and any subcontractor thereunder, the percentage of the retention proceeds withheld shall not exceed the percentage specified in the contract between the local agency and the design-build entity. If the design-build entity provides written notice to any subcontractor that is not a member of the design-build entity, before or at the time the bid is requested, that a bond may be required, and the subcontractor subsequently is unable or refuses to furnish a bond to the design-build entity, then the design-build entity may withhold retention proceeds in excess of the percentage specified in the contract between the local agency and the design-build entity from any payment made by the design-build entity to the subcontractor.
22185.8.(a)Notwithstanding Section 10231.5 of the Government Code, no later than December 31, 2028, a local agency that uses the progressive design-build process pursuant to this chapter shall submit, to the appropriate policy and fiscal committees of the Legislature, a report on the use of the progressive design-build process.
(b)The report shall include, but is not limited to, the following information:
(1)A description of the project or projects awarded using the progressive design-build process.
(2)The contract award amounts.
(3)The design-build entities awarded the project or projects.
(4)A description of any written protests concerning any aspect of the solicitation, bid, or award of the contracts, including the resolution of the protests.
(5)A description of the prequalification process.
(6)The number of specialty subcontractors listed by construction trade type, on each project, that provided design services, but did not meet the target price for their scope of work, and therefore did not perform construction services on that project.
(7)Whether or not any portion of a design prepared by the specialty subcontractor that did not perform the construction work for that design was used by the local agency.
(8)The number of specialty subcontractors listed by construction trade type, on each project, that meet the definition of a small business, as specified in paragraph (1) of subdivision (d) of Section 14837 of the Government Code.
(9)The number of specialty subcontractors listed by construction trade type, on each project, that meet the definition of a microbusiness, as specified in paragraph (2) of subdivision (d) of Section 14837 of the Government Code.
(10)If a project awarded under this chapter has been completed, an assessment of the project performance, including, but not limited to, a summary of any delays or cost increases.
(c)The report submitted pursuant to subdivision (a) shall be submitted in compliance with Section 9795 of the Government Code.
22185.9.Nothing in this chapter authorizes a local agency to perform work on a state-owned or state-operated facility.
22185.10.Nothing in this chapter affects, expands, alters, or limits any rights or remedies otherwise available at law.
22185.11.This chapter shall remain in effect only until January 1, 2030, and as of that date is repealed.
SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
For purposes of this chapter, the following definitions apply:
(a)(1)Best value means a value determined by evaluation of objective criteria that may include, but are not limited to, price, features, function, life-cycle costs, experience, and past performance.
(2)A best value determination may involve the selection of the lowest cost proposal meeting the interests of the local agency and the objectives of the project.
(b)Construction subcontract means each subcontract awarded by the design-build entity to a subcontractor that will perform work or labor or render service to the design-build entity in or about the construction of the work or improvement, or a subcontractor licensed by the State of California that, under subcontract to the design-build entity, specially fabricates and installs a portion of the work or improvement according to detailed drawings contained in the plans and specifications produced by the design-build team.
(c)Design-build entity means a corporation, limited liability company, partnership, joint venture, or other legal entity that is able to provide appropriately licensed contracting, architectural, and engineering services as needed pursuant to a design-build contract.
(d)Design-build project means any project using the progressive design-build construction procurement process described in this chapter, but does not include projects on state-owned or state-operated facilities.
(e)Design-build team means the design-build entity itself and the individuals and other entities identified by the design-build entity as members of its team. Members shall include the general contractor and, if utilized in the design of the project, all electrical, mechanical, and plumbing contractors.
(f)Guaranteed maximum price means the maximum payment amount agreed upon by the local agency and the design-build entity for the design-build entity to finish all remaining design, preconstruction, and construction activities sufficient to complete and close out the project.
(g)Local agency means a city, county, city and county, or special district.
(h)Progressive design-build means a project delivery process in which both the design and construction of a project are procured from a single entity that is selected through a qualifications-based selection at the earliest feasible stage of the project.
(i)Qualifications-based selection means the process by which the local agency solicits for services from the design-build entities and that price is not the sole factor as the basis of award.
22185.1.A local agency may procure progressive design-build contracts and use the progressive design-build contracting process described in this chapter for up to 10 public works projects in excess of five million dollars ($5,000,000) for each project.
22185.2.A local agency entering into design-build contracts authorized under this chapter shall develop guidelines for a standard organizational conflict-of-interest policy, consistent with applicable law, regarding the ability of a person or entity that performs services for the local agency relating to the solicitation of a design-build project, to submit a proposal as a design-build entity, or to join a design-build team.
22185.3.The procurement process for progressive design-build projects shall progress as follows:
(a)The local agency shall prepare and issue a request for qualifications in order to select a design-build entity to execute the project. The request for qualifications shall include, but is not limited to, the following elements:
(1)Documentation of the size, type, and desired design character of the project and any other information deemed necessary to describe adequately the local agencys needs, including the expected cost range, the methodology that will be used by the local agency to evaluate the design-build entitys qualifications, the procedure for final selection of the design-build entity, and any other information deemed necessary by the local agency to inform interested parties of the contracting opportunity.
(2)Significant factors that the local agency reasonably expects to consider in evaluating qualifications, including technical design and construction expertise, and all other non-price-related factors. The local agency may require that a preliminary cost estimate be included in the design-build entities responses and consider those costs in evaluating the statements of qualifications.
(3)The relative importance or the weight assigned to each of the factors identified in the request for qualifications.
(4)A standard template request for statements of qualifications prepared by the local agency. In preparing the standard template, the local agency may consult with the construction industry, the building trades and surety industry, and other local agencies interested in using the authorization provided by this chapter. The template shall require the following information:
(A)If the design-build entity is a privately held corporation, limited liability company, partnership, or joint venture, a listing of all of the entitys shareholders, partners, or members known at the time of the statement of qualification submission who will perform work on the project.
(B)Evidence that the members of the design-build team have completed, or have demonstrated the experience, competency, capability, and capacity to complete, projects of similar size, scope, or complexity, and that proposed key personnel have sufficient experience and training to competently manage and complete the design and construction of the project, and a financial statement that ensures that the design-build entity has the capacity to complete the project.
(C)The licenses, registration, and credentials required to design and construct the project, including, but not limited to, information on the revocation or suspension of any license, credential, or registration.
(D)Evidence that establishes that the design-build entity has the capacity to obtain all required payment and performance bonding, liability insurance, and errors and omissions insurance.
(E)Information concerning workers compensation experience history and a worker safety program.
(F)If the proposed design-build entity is a corporation, limited liability company, partnership, joint venture, or other legal entity, a copy of the organizational documents or agreement committing to form the organization.
(G)An acceptable safety record. A proposers safety record shall be deemed acceptable if its experience modification rate for the most recent three-year period is an average of 1.00 or less, and its average total recordable injury or illness rate and average lost work rate for the most recent three-year period does not exceed the applicable statistical standards for its business category or if the proposer is a party to an alternative dispute resolution system as provided for in Section 3201.5 of the Labor Code.
(5)The information required under this subdivision shall be certified under penalty of perjury by the design-build entity and its general partners or joint venture members.
(b)(1)A design-build entity shall not be evaluated for selection unless the entity provides an enforceable commitment to the local agency that the entity and its subcontractors at every tier will use a skilled and trained workforce to perform all work on the project or contract that falls within an apprenticeable occupation in the building and construction trades, in accordance with Chapter 2.9 (commencing with Section 2600) of Part 1.
(2)This subdivision shall not apply if one or more of the following requirements are met:
(A)The local agency has entered into a project labor agreement that will bind all contractors and subcontractors performing work on the project or contract to use a skilled and trained workforce, and the entity agrees to be bound by that project labor agreement.
(B)The project or contract is being performed under the extension or renewal of a project labor agreement that was entered into by the local agency before January 1, 2023.
(C)The entity has entered into a project labor agreement that will bind the entity and all its subcontractors at every tier performing the project or contract to use a skilled and trained workforce.
(3)For purposes of this subdivision, project labor agreement has the same meaning as provided in paragraph (1) of subdivision (b) of Section 2500.
(c)At the close of the solicitation period, the local agency shall review the submissions. The local agency may evaluate submissions based solely upon the information provided in each design-build entitys statement of qualifications. The local agency may also interview some or all of the design-build entities to further evaluate their qualifications for the project.
(d)Notwithstanding any other provision of this code, upon issuance of a contract award, the local agency shall publicly announce its award, identifying the design-build entity to which the award is made, along with a statement regarding the basis of the award. The statement regarding the local agencys contract award and the contract file shall provide sufficient information to satisfy an external audit.
22185.4.(a)The design-build entity shall provide payment and performance bonds for the project in the form and in the amount required by the local agency, and issued by a California admitted surety. The amount of the payment bond shall not be less than the amount of the performance bond.
(b)The design-build contract shall require errors and omissions insurance coverage for the design elements of the project.
(c)The local agency shall develop a standard form of payment and performance bond for its design-build projects.
22185.5.(a)After selecting a design-build entity based upon qualifications, the local agency may enter into a contract and direct the design-build entity to begin design and preconstruction activities sufficient to establish a guaranteed maximum price for the project.
(b)(1)Upon agreement of the guaranteed maximum price for the project, the local agency, at its sole and absolute discretion, may amend its contract with the design build entity to contract for the remaining design, preconstruction, and construction activities sufficient to complete and close out the project, consistent with the guaranteed maximum price. In the event that there are unforeseen site conditions, the local agency may amend its contract with the design build entity accordingly and consistent with the guaranteed maximum price, to enable the entity to complete the remaining design, preconstruction, and construction activities sufficient to complete and close out the project.
(2)If the cost for completing all remaining design, preconstruction, and construction activities sufficient to complete and close out the project exceed the guaranteed maximum price, the costs exceeding the guaranteed maximum price shall be the responsibility of the design-build entity. If the cost for these activities are less than the guaranteed maximum price, the design-build entity shall not be entitled to the difference between the cost and the guaranteed maximum price unless there is a prior written agreement concerning the sharing of these funds. For purposes of this section, cost shall include the design-build entitys direct costs, general conditions, overhead, and fee.
(c)(1)If the local agency and the design-build entity do not reach agreement on a guaranteed maximum price, or the local agency otherwise elects not to amend the design-build entitys contract to complete the remaining work, the local agency may solicit proposals to complete the project from firms that submitted statements of qualifications pursuant to Section 22185.3. The local agency may also, upon written determination that it is in the best interest of the city, county, city and county, or special district, as applicable, to do so, formally solicit proposals from other design-build entities, and contract award shall be made on a best value basis.
(2)The design professionals responsible for performing design services on behalf of a design-build entity that has been replaced pursuant to paragraph (1) shall have sole liability for their design errors and omissions, provided the local agency elects to use their complete and stamped designs with subsequent design-build entities or licensed contractors.
22185.6.(a)The local agency, in each design-build request for qualifications, may identify specific types of subcontractors that shall be included in the design-build entitys statement of qualifications. All construction subcontractors that are identified in the statement of qualifications shall be afforded the protections of Chapter 4 (commencing with Section 4100) of Part 1.
(b)Following award of the design-build contract, except for those construction subcontractors listed in the statement of qualifications, the design-build entity shall proceed as listed in this subdivision in awarding construction subcontracts with a value exceeding one-half of 1 percent of the contract price allocable to construction work for projects with a contract value of greater than or equal to ten million dollars ($10,000,000).
(1)Provide public notice of availability of work to be subcontracted in accordance with the publication requirements applicable to the competitive bidding process of the local agency, including a fixed date and time on which qualifications statements, bids, or proposals will be due.
(2)Establish reasonable qualification criteria and standards.
(3)Award the subcontract on a best value basis. The process may include prequalification or short-listing.
(c)Subcontractors awarded construction subcontracts under this subdivision shall be afforded all the protections of Chapter 4 (commencing with Section 4100) of Part 1.
(d)A construction subcontractor licensed pursuant to Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code that provides design services used on a project authorized by this chapter shall not be subject to any liability arising from their design if the construction subcontract for that design is not performed by that subcontractor.
22185.7.(a)If the local agency elects to award a project pursuant to this chapter, retention proceeds withheld by the local agency from the design-build entity shall not exceed 5 percent if a performance and payment bond, issued by an admitted surety insurer, is required in the solicitation. Work performed to establish the guaranteed maximum price shall not be subject to retention.
(b)In a contract between the design-build entity and a subcontractor, and in a contract between a subcontractor and any subcontractor thereunder, the percentage of the retention proceeds withheld shall not exceed the percentage specified in the contract between the local agency and the design-build entity. If the design-build entity provides written notice to any subcontractor that is not a member of the design-build entity, before or at the time the bid is requested, that a bond may be required, and the subcontractor subsequently is unable or refuses to furnish a bond to the design-build entity, then the design-build entity may withhold retention proceeds in excess of the percentage specified in the contract between the local agency and the design-build entity from any payment made by the design-build entity to the subcontractor.
22185.8.(a)Notwithstanding Section 10231.5 of the Government Code, no later than December 31, 2028, a local agency that uses the progressive design-build process pursuant to this chapter shall submit, to the appropriate policy and fiscal committees of the Legislature, a report on the use of the progressive design-build process.
(b)The report shall include, but is not limited to, the following information:
(1)A description of the project or projects awarded using the progressive design-build process.
(2)The contract award amounts.
(3)The design-build entities awarded the project or projects.
(4)A description of any written protests concerning any aspect of the solicitation, bid, or award of the contracts, including the resolution of the protests.
(5)A description of the prequalification process.
(6)The number of specialty subcontractors listed by construction trade type, on each project, that provided design services, but did not meet the target price for their scope of work, and therefore did not perform construction services on that project.
(7)Whether or not any portion of a design prepared by the specialty subcontractor that did not perform the construction work for that design was used by the local agency.
(8)The number of specialty subcontractors listed by construction trade type, on each project, that meet the definition of a small business, as specified in paragraph (1) of subdivision (d) of Section 14837 of the Government Code.
(9)The number of specialty subcontractors listed by construction trade type, on each project, that meet the definition of a microbusiness, as specified in paragraph (2) of subdivision (d) of Section 14837 of the Government Code.
(10)If a project awarded under this chapter has been completed, an assessment of the project performance, including, but not limited to, a summary of any delays or cost increases.
(c)The report submitted pursuant to subdivision (a) shall be submitted in compliance with Section 9795 of the Government Code.
22185.9.Nothing in this chapter authorizes a local agency to perform work on a state-owned or state-operated facility.
22185.10.Nothing in this chapter affects, expands, alters, or limits any rights or remedies otherwise available at law.
22185.11.This chapter shall remain in effect only until January 1, 2030, and as of that date is repealed.
SECTION 1.Section 22170 of the Public Contract Code is amended to read:22170.For purposes of this chapter, the following definitions apply:(a)(1)Best value means a value determined by evaluation of objective criteria that may include, but are not limited to, price, features, function, life-cycle costs, experience, and past performance.(2)A best value determination may involve the selection of the lowest cost proposal meeting the interests of the local agency and the objectives of the project.(b)Construction subcontract means each subcontract awarded by the design-build entity to a subcontractor that will perform work or labor or render service to the design-build entity in or about the construction of the work or improvement, or a subcontractor licensed by the State of California that, under subcontract to the design-build entity, specially fabricates and installs a portion of the work or improvement according to detailed drawings contained in the plans and specifications produced by the design-build team.(c)Design-build entity means a corporation, limited liability company, partnership, joint venture, or other legal entity that is able to provide appropriately licensed contracting, architectural, and engineering services as needed pursuant to a design-build contract.(d)Design-build project means any project using the progressive design-build construction procurement process described in this chapter, but does not include projects on state-owned or -operated facilities.(e)Design-build team means the design-build entity itself and the individuals and other entities identified by the design-build entity as members of its team. Members shall include the general contractor and, if utilized in the design of the project, all electrical, mechanical, and plumbing contractors.(f)Guaranteed maximum price means the maximum payment amount agreed upon by the local agency and the design-build entity for the design-build entity to finish all remaining design, preconstruction, and construction activities sufficient to complete and close out the project.(g)Local agency means a city, county, city and county, or special district.(h)Progressive design-build means a project delivery process in which both the design and construction of a project are procured from a single entity that is selected through a qualifications-based selection at the earliest feasible stage of the project.(i)Qualifications-based selection means the process by which the local agency solicits for services from the design-build entities and that price is not the sole factor as the basis of award.SEC. 2.Section 22172.5 of the Public Contract Code is amended to read:22172.5.(a)Notwithstanding Section 10231.5 of the Government Code, no later than December 31, 2028, a local agency that uses the progressive design-build process pursuant to this chapter shall submit, to the appropriate policy and fiscal committees of the Legislature, a report on the use of the progressive design-build process.(b)The report shall include, but is not limited to, the following information:(1)A description of the project or projects awarded using the progressive design-build process.(2)The contract award amounts.(3)The design-build entities awarded the project or projects.(4)A description of any written protests concerning any aspect of the solicitation, bid, or award of the contracts, including the resolution of the protests.(5)A description of the prequalification process.(6)The number of specialty subcontractors listed by construction trade type, on each project, that provided design services, but did not meet the target price for their scope of work, and therefore did not perform construction services on that project.(7)Whether or not any portion of a design prepared by the specialty subcontractor that did not perform the construction work for that design was used by the local agency.(8)The number of specialty subcontractors listed by construction trade type, on each project, that meet the definition of a small business, as specified in paragraph (1) of subdivision (d) of Section 14837 of the Government Code.(9)The number of specialty subcontractors listed by construction trade type, on each project, that meet the definition of a microbusiness, as specified in paragraph (2) of subdivision (d) of Section 14837 of the Government Code.(10)If a project awarded under this chapter has been completed, an assessment of the project performance, including, but not limited to, a summary of any delays or cost increases.(c)The report submitted pursuant to subdivision (a) shall be submitted in compliance with Section 9795 of the Government Code.SEC. 3.Section 22172.8 is added to the Public Contract Code, to read:22172.8.Nothing in this chapter authorizes a local agency to perform work on a state-owned or -operated facility.SEC. 4.Section 22174 of the Public Contract Code is amended to read:22174.This chapter shall remain in effect only until January 1, 2030, and as of that date is repealed.SEC. 5.SEC. 2.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
For purposes of this chapter, the following definitions apply:
(a)(1)Best value means a value determined by evaluation of objective criteria that may include, but are not limited to, price, features, function, life-cycle costs, experience, and past performance.
(2)A best value determination may involve the selection of the lowest cost proposal meeting the interests of the local agency and the objectives of the project.
(b)Construction subcontract means each subcontract awarded by the design-build entity to a subcontractor that will perform work or labor or render service to the design-build entity in or about the construction of the work or improvement, or a subcontractor licensed by the State of California that, under subcontract to the design-build entity, specially fabricates and installs a portion of the work or improvement according to detailed drawings contained in the plans and specifications produced by the design-build team.
(c)Design-build entity means a corporation, limited liability company, partnership, joint venture, or other legal entity that is able to provide appropriately licensed contracting, architectural, and engineering services as needed pursuant to a design-build contract.
(d)Design-build project means any project using the progressive design-build construction procurement process described in this chapter. chapter, but does not include projects on state-owned or -operated facilities.
(e)Design-build team means the design-build entity itself and the individuals and other entities identified by the design-build entity as members of its team. Members shall include the general contractor and, if utilized in the design of the project, all electrical, mechanical, and plumbing contractors.
(f)Guaranteed maximum price means the maximum payment amount agreed upon by the local agency and the design-build entity for the design-build entity to finish all remaining design, preconstruction, and construction activities sufficient to complete and close out the project.
(g)Local agency means a city, county, city and county, or special district.
(h)Progressive design-build means a project delivery process in which both the design and construction of a project are procured from a single entity that is selected through a qualifications-based selection at the earliest feasible stage of the project.
(i)Qualifications-based selection means the process by which the local agency solicits for services from the design-build entities and that price is not the sole factor as the basis of award.
SEC. 2.Section 22172.5 of the Public Contract Code is amended to read:22172.5.(a)Notwithstanding Section 10231.5 of the Government Code, no later than December 31, 2028, a local agency that uses the progressive design-build process pursuant to this chapter shall submit, to the appropriate policy and fiscal committees of the Legislature, a report on the use of the progressive design-build process.
(b)The report shall include, but is not limited to, the following information:
(1)A description of the project or projects awarded using the progressive design-build process.
(2)The contract award amounts.
(3)The design-build entities awarded the project or projects.
(4)A description of any written protests concerning any aspect of the solicitation, bid, or award of the contracts, including the resolution of the protests.
(5)A description of the prequalification process.
(6)The number of specialty subcontractors listed by construction trade type, on each project, that provided design services, but did not meet the target price for their scope of work, and therefore did not perform construction services on that project.
(7)Whether or not any portion of a design prepared by the specialty subcontractor that did not perform the construction work for that design was used by the local agency.
(8)The number of specialty subcontractors listed by construction trade type, on each project, that meet the definition of a small business, as specified in paragraph (1) of subdivision (d) of Section 14837 of the Government Code.
(9)The number of specialty subcontractors listed by construction trade type, on each project, that meet the definition of a microbusiness, as specified in paragraph (2) of subdivision (d) of Section 14837 of the Government Code.
(10)If a project awarded under this chapter has been completed, an assessment of the project performance, including, but not limited to, a summary of any delays or cost increases.
(c)The report submitted pursuant to subdivision (a) shall be submitted in compliance with Section 9795 of the Government Code.
SEC. 3.Section 22172.8 is added to the Public Contract Code, to read:22172.8.Nothing in this chapter authorizes a local agency to perform work on a state-owned or -operated facility.
SEC. 3.SEC. 4.Section 22174 of the Public Contract Code is amended to read:22174.This chapter shall remain in effect only until January 1, 2030, and as of that date is repealed.
SEC. 4.SEC. 5.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
For purposes of this chapter, the following definitions apply:
(a)(1)Best value means a value determined by evaluation of objective criteria that may include, but are not limited to, price, features, function, life-cycle costs, experience, and past performance.
(2)A best value determination may involve the selection of the lowest cost proposal meeting the interests of the local agency and the objectives of the project.
(b)Construction subcontract means each subcontract awarded by the design-build entity to a subcontractor that will perform work or labor or render service to the design-build entity in or about the construction of the work or improvement, or a subcontractor licensed by the State of California that, under subcontract to the design-build entity, specially fabricates and installs a portion of the work or improvement according to detailed drawings contained in the plans and specifications produced by the design-build team.
(c)Design-build entity means a corporation, limited liability company, partnership, joint venture, or other legal entity that is able to provide appropriately licensed contracting, architectural, and engineering services as needed pursuant to a design-build contract.
(d)Design-build project means any project using the progressive design-build construction procurement process described in this chapter.
(e)Design-build team means the design-build entity itself and the individuals and other entities identified by the design-build entity as members of its team. Members shall include the general contractor and, if utilized in the design of the project, all electrical, mechanical, and plumbing contractors.
(f)Guaranteed maximum price means the maximum payment amount agreed upon by the local agency and the design-build entity for the design-build entity to finish all remaining design, preconstruction, and construction activities sufficient to complete and close out the project.
(g)Local agency means a city, county, city and county, or special district.
(h)Progressive design-build means a project delivery process in which both the design and construction of a project are procured from a single entity that is selected through a qualifications-based selection at the earliest feasible stage of the project.
(i)Qualifications-based selection means the process by which the local agency solicits for services from the design-build entities and that price is not the sole factor as the basis of award.
SEC. 2.Section 22172.5 of the Public Contract Code is amended to read:22172.5.(a)Notwithstanding Section 10231.5 of the Government Code, no later than December 31, 2028, a local agency that uses the progressive design-build process pursuant to this chapter shall submit submit, to the appropriate policy and fiscal committees of the Legislature Legislature, a report on the use of the progressive design-build process.
(b)The report shall include, but is not limited to, the following information:
(1)A description of the project or projects awarded using the progressive design-build process.
(2)The contract award amounts.
(3)The design-build entities awarded the project or projects.
(4)A description of any written protests concerning any aspect of the solicitation, bid, or award of the contracts, including the resolution of the protests.
(5)A description of the prequalification process.
(6)The number of specialty subcontractors listed by construction trade type, on each project, that provided design services, but did not meet the target price for their scope of work, and therefore did not perform construction services on that project.
(7)Whether or not any portion of a design prepared by the specialty subcontractor that did not perform the construction work for that design was used by the local agency.
(8)The number of specialty subcontractors listed by construction trade type, on each project, that meet the definition of a small business, as specified in paragraph (1) of subdivision (d) of Section 14837 of the Government Code.
(9)The number of specialty subcontractors listed by construction trade type, on each project, that meet the definition of a microbusiness, as specified in paragraph (2) of subdivision (d) of Section 14837 of the Government Code.
(10)If a project awarded under this chapter has been completed, an assessment of the project performance, including, but not limited to, a summary of any delays or cost increases.
(c)The report submitted pursuant to subdivision (a) shall be submitted in compliance with Section 9795 of the Government Code.
SEC. 3.Section 22174 of the Public Contract Code is amended to read:22174.This chapter shall remain in effect only until January 1, 2029, 2030, and as of that date is repealed.
SEC. 3.SEC. 4.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
For purposes of this chapter, the following definitions apply:
(a)(1)Best value means a value determined by evaluation of objective criteria that may include, but are not limited to, price, features, function, life-cycle costs, experience, and past performance.
(2)A best value determination may involve the selection of the lowest cost proposal meeting the interests of the local agency and the objectives of the project.
(b)Construction subcontract means each subcontract awarded by the design-build entity to a subcontractor that will perform work or labor or render service to the design-build entity in or about the construction of the work or improvement, or a subcontractor licensed by the State of California that, under subcontract to the design-build entity, specially fabricates and installs a portion of the work or improvement according to detailed drawings contained in the plans and specifications produced by the design-build team.
(c)Design-build entity means a corporation, limited liability company, partnership, joint venture, or other legal entity that is able to provide appropriately licensed contracting, architectural, and engineering services as needed pursuant to a design-build contract.
(d)Design-build project means any project using the progressive design-build construction procurement process described in this chapter.
(e)Design-build team means the design-build entity itself and the individuals and other entities identified by the design-build entity as members of its team. Members shall include the general contractor and, if utilized in the design of the project, all electrical, mechanical, and plumbing contractors.
(f)Guaranteed maximum price means the maximum payment amount agreed upon by the local agency and the design-build entity for the design-build entity to finish all remaining design, preconstruction, and construction activities sufficient to complete and close out the project.
(g)Local agency means a city, county, city and county, or special district.
(h)Progressive design-build means a project delivery process in which both the design and construction of a project are procured from a single entity that is selected through a qualifications-based selection at the earliest feasible stage of the project.
(i)Qualifications-based selection means the process by which the local agency solicits for services from the design-build entities and that price is not the sole factor as the basis of award.
SEC. 2.Section 22171 of the Public Contract Code, as added by Section 1 of Chapter 243 of the Statutes of 2022, is amended to read:22171.A local agency may procure progressive design-build contracts and use the progressive design-build contracting process described in this chapter for public works projects in excess of five million dollars ($5,000,000) for each project.SEC. 3.SEC. 2.Section 22172.5 of the Public Contract Code, as added by Section 1 of Chapter 243 of the Statutes of 2022, is amended to read:22172.5.(a)Notwithstanding Section 10231.5 of the Government Code, no later than December 31, 2028, a local agency that uses the progressive design-build process pursuant to this chapter shall submit to the appropriate policy and fiscal committees of the Legislature a report on the use of the progressive design-build process.
(b)The report shall include, but is not limited to, the following information:
(1)A description of the project or projects awarded using the progressive design-build process.
(2)The contract award amounts.
(3)The design-build entities awarded the project or projects.
(4)A description of any written protests concerning any aspect of the solicitation, bid, or award of the contracts, including the resolution of the protests.
(5)A description of the prequalification process.
(6)The number of specialty subcontractors listed by construction trade type, on each project, that provided design services, but did not meet the target price for their scope of work, and therefore did not perform construction services on that project.
(7)Whether or not any portion of a design prepared by the specialty subcontractor that did not perform the construction work for that design was used by the local agency.
(8)The number of specialty subcontractors listed by construction trade type, on each project, that meet the definition of a small business, as specified in paragraph (1) of subdivision (d) of Section 14837 of the Government Code.
(9)The number of specialty subcontractors listed by construction trade type, on each project, that meet the definition of a microbusiness, as specified in paragraph (2) of subdivision (d) of Section 14837 of the Government Code.
(10)If a project awarded under this chapter has been completed, an assessment of the project performance, including, but not limited to, a summary of any delays or cost increases.
(c)The report submitted pursuant to subdivision (a) shall be submitted in compliance with Section 9795 of the Government Code.
SEC. 4.SEC. 3.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
For purposes of this chapter, the following definitions apply:
(a)(1)Best value means a value determined by evaluation of objective criteria that may include, but are not limited to, price, features, function, life-cycle costs, experience, and past performance.
(2)A best value determination may involve the selection of the lowest cost proposal meeting the interests of the local agency and the objectives of the project.
(b)Construction subcontract means each subcontract awarded by the design-build entity to a subcontractor that will perform work or labor or render service to the design-build entity in or about the construction of the work or improvement, or a subcontractor licensed by the State of California that, under subcontract to the design-build entity, specially fabricates and installs a portion of the work or improvement according to detailed drawings contained in the plans and specifications produced by the design-build team.
(c)Design-build entity means a corporation, limited liability company, partnership, joint venture, or other legal entity that is able to provide appropriately licensed contracting, architectural, and engineering services as needed pursuant to a design-build contract.
(d)Design-build project means any project that treats, pumps, stores, or conveys water, wastewater, recycled water, advanced treated water, or supporting facilities using the progressive design-build construction procurement process described in this chapter.
(e)Design-build team means the design-build entity itself and the individuals and other entities identified by the design-build entity as members of its team. Members shall include the general contractor and, if utilized in the design of the project, all electrical, mechanical, and plumbing contractors.
(f)Guaranteed maximum price means the maximum payment amount agreed upon by the local agency and the design-build entity for the design-build entity to finish all remaining design, preconstruction, and construction activities sufficient to complete and close out the project.
(g)Local agency means a city, county, city and county, or special district authorized by law to provide for the production, storage, supply, treatment, or distribution of any water from any source. district.
(h)Progressive design-build means a project delivery process in which both the design and construction of a project are procured from a single entity that is selected through a qualifications-based selection at the earliest feasible stage of the project.
(i)Qualifications-based selection means the process by which the local agency solicits for services from the design-build entities and that price is not the sole factor as the basis of award.
SEC. 2.Section 22171 of the Public Contract Code, as added by Section 1 of Chapter 243 of the Statutes of 2022, is amended to read:22171.A local agency may procure progressive design-build contracts and use the progressive design-build contracting process described in this chapter for up to 15 public works projects in excess of five million dollars ($5,000,000) for each project.
SEC. 3.Section 22172.5 of the Public Contract Code, as added by Section 1 of Chapter 243 of the Statutes of 2022, is amended to read:22172.5.(a)Notwithstanding Section 10231.5 of the Government Code, no later than January 1, 2028, December 31, 2028, a local agency that uses the progressive design-build process pursuant to this chapter shall submit to the appropriate policy and fiscal committees of the Legislature a report on the use of the progressive design-build process.
(b)The report shall include, but is not limited to, the following information:
(1)A description of the project or projects awarded using the progressive design-build process.
(2)The contract award amounts.
(3)The design-build entities awarded the project or projects.
(4)A description of any written protests concerning any aspect of the solicitation, bid, or award of the contracts, including the resolution of the protests.
(5)A description of the prequalification process.
(6)The number of specialty subcontractors listed by construction trade type, on each project, that provided design services, but did not meet the target price for their scope of work, and therefore did not perform construction services on that project.
(7)Whether or not any portion of a design prepared by the specialty subcontractor that did not perform the construction work for that design was used by the local agency.
(8)The number of specialty subcontractors listed by construction trade type, on each project, that meet the definition of a small business, as specified in paragraph (1) of subdivision (d) of Section 14837 of the Government Code.
(9)The number of specialty subcontractors listed by construction trade type, on each project, that meet the definition of a microbusiness, as specified in paragraph (2) of subdivision (d) of Section 14837 of the Government Code.
(10)If a project awarded under this chapter has been completed, an assessment of the project performance, including, but not limited to, a summary of any delays or cost increases.
(c)The report submitted pursuant to subdivision (a) shall be submitted in compliance with Section 9795 of the Government Code.
SEC. 4.No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
|
Date
|
Status
|
|---|---|
| Oct 8, 2023 | Chaptered by Secretary of State. Chapter 500, Statutes of 2023. |
| Oct 8, 2023 | Approved by the Governor. |
| Sep 7, 2023 | Enrolled and presented to the Governor at 4 p.m. |
| Sep 1, 2023 | Assembly amendments concurred in. (Ayes 37. Noes 0. Page 2241.) Ordered to engrossing and enrolling. |
| Aug 29, 2023 | Ordered to special consent calendar. |
| Aug 24, 2023 | In Senate. Concurrence in Assembly amendments pending. |
| Aug 24, 2023 | Read third time. Passed. (Ayes 73. Noes 0. Page 2802.) Ordered to the Senate. |
| Aug 17, 2023 | Read second time. Ordered to consent calendar. |
| Aug 16, 2023 | From committee: Do pass. Ordered to consent calendar. (Ayes 15. Noes 0.) (August 16). |
| Jun 28, 2023 | Read second time and amended. Re-referred to Com. on APPR. |
| Jun 27, 2023 | From committee: Do pass as amended and re-refer to Com. on APPR. (Ayes 8. Noes 0.) (June 21). |
| Jun 14, 2023 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on L. GOV. |
| May 4, 2023 | Referred to Com. on L. GOV. |
| Apr 27, 2023 | In Assembly. Read first time. Held at Desk. |
| Apr 27, 2023 | Read third time. Passed. (Ayes 38. Noes 0. Page 920.) Ordered to the Assembly. |
| Apr 18, 2023 | Read second time. Ordered to third reading. |
| Apr 17, 2023 | From committee: Be ordered to second reading pursuant to Senate Rule 28.8. |
| Apr 11, 2023 | Set for hearing April 17. |
| Apr 10, 2023 | Read second time and amended. Re-referred to Com. on APPR. |
| Mar 30, 2023 | From committee: Do pass as amended and re-refer to Com. on APPR. (Ayes 8. Noes 0. Page 573.) (March 29). |
| Mar 21, 2023 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on GOV. & F. |
| Mar 14, 2023 | Set for hearing March 29. |
| Mar 1, 2023 | Referred to Com. on GOV. & F. |
| Feb 17, 2023 | From printer. May be acted upon on or after March 19. |
| Feb 16, 2023 | Introduced. Read first time. To Com. on RLS. for assignment. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Sep 1, 2023 | Special Consent SB706 Caballero et al. | Senate Floor |
Passed |
|
| Aug 24, 2023 | SB 706 Caballero Consent Calendar Second Day Regular Session | Assembly Floor |
Passed |
|
| Aug 16, 2023 | Do pass. To Consent Calendar. | Assembly Standing Committee on Appropriations |
Passed |
|
| Jun 21, 2023 | Do pass as amended and be re-referred to the Committee on [Appropriations] | Assembly Standing Committee on Local Government |
Passed |
|
| Apr 27, 2023 | Senate 3rd Reading SB706 Caballero et al. | Senate Floor |
Passed |
|
| Mar 29, 2023 | Do pass as amended, but first amend, and re-refer to the Committee on [Appropriations] | Senate Standing Committee on Governance and Finance |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| Aaron Read & Associates | * Neutral | Jun 21, 2023 |
| Aecom | ** Support | |
| Aj Kirkwood and Associates, INC | ** Support | |
| Ameresco | ** Support | |
| AT&T | * Support | Mar 29, 2023 |
| Bernards | ** Support | |
| Bnbuilders | ** Support | |
| Bothman Construction | ** Support | |
| California Association Of Recreation & Park Districts | ** Support | |
| California Special Districts Association | ** Support | |
| California State Association Of Counties | ** Support | |
| California Strategies & Advocacy, LLC | * For If Amend | Jun 21, 2023 |
| CannonDesign | * Support | Mar 29, 2023 |
| CannonDesign | * Support | Jun 21, 2023 |
| City of Belmont | ** Support | |
| City of Roseville | ** Support | |
| City of San Marcos | ** Support | |
| City Of Visalia | ** Support | |
| Collin Construction Company | ** Support | |
| County of Contra Costa | ** Support | |
| County Of Los Angeles | ** Support | |
| County of Los Angeles Board of Supervisors | ** Support | |
| County of Merced | ** Support | |
| County of Orange | ** Support | |
| County Of Placer | ** Support | |
| County of San Bernardino | ** Support | |
| County Of San Diego | ** Support | |
| County of Solano | ** Support | |
| Critchfield Mechanical, INC | ** Support | |
| Design Build Institute of America | * Support | Mar 29, 2023 |
| Design Build Institute Of American Western Pacific Chapter | ** Support | |
| El Dorado Irrigation District | ** Support | |
| Elsinore Valley Municipal Water District | ** Support | |
| ENGIE | ** Support | |
| Flint Design Build | ** Support | |
| Fuscoe | ** Support | |
| Gilbane | ** Support | |
| Granite Construction | ** Support | |
| Johnson Controls | * For If Amend | Jun 21, 2023 |
| League Of California Cities | ** Support | |
| Los Angeles County Sanitation Districts | ** Support | |
| Los Angeles Sanitation Districts | ** Support | |
| Metropolitan Water District Of Southern California | * Support | Jun 21, 2023 |
| National Association of Energy Service Companies | * For If Amend | Jun 21, 2023 |
| National Association Of Energy Service Companies | ** Support | |
| Noresco | ** Support | |
| Orange County Transportation Authority | ** Support | |
| Pacificwest Energy Solutions | ** Support | |
| San Bernadino County | * Support | Jun 21, 2023 |
| San Gabriel Valley Council Of Governments | ** Support | |
| San Joaquin County Department of Public Works | * Support | Jun 21, 2023 |
| SitelogIQ | * For If Amend | Jun 21, 2023 |
| Southland Industries | * For If Amend | Jun 21, 2023 |
| Syserco Energy Solutions | ** Support | |
| Trane Technologies | ** Support | |
| United Industries Group, INC | ** Support | |
| Vanir Construction Management, Inc. | ** Support | |
| Veregy | ** Support | |
| Willdan Group, Inc. | ** Support | |
| Xl Construction | ** Support |
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 706 |
UNFINISHED BUSINESS
Bill No: SB 706
Author: Caballero (D), et al.
Amended: 6/28/23
Vote: 21
SENATE GOVERNANCE & FIN. COMMITTEE: 8-0, 3/29/23
AYES: Caballero, Seyarto, Blakespear, Dahle, Durazo, Glazer, Skinner, Wiener
SENATE APPROPRIATIONS COMMITTEE: Senate Rule 28.8
SENATE FLOOR: 38-0, 4/27/23
AYES: Allen, Archuleta, Ashby, Atkins, Becker, Blakespear, Bradford, Caballero, Cortese, Dahle, Dodd, Durazo, Eggman, Glazer, Gonzalez, Grove, Hurtado, Jones, Laird, Limón, McGuire, Menjivar, Min, Newman, Niello, Ochoa Bogh, Padilla, Portantino, Roth, Rubio, Seyarto, Skinner, Smallwood-Cuevas, Stern, Umberg, Wahab, Wiener, Wilk
NO VOTE RECORDED: Alvarado-Gil, Nguyen
ASSEMBLY FLOOR: 73-0, 8/24/23 (Consent) - See last page for vote
SUBJECT: Public contracts: progressive design-build: local agencies
SOURCE: California State Association of Counties
County of San Diego
Design Build Institute of America Western Pacific Chapter
League of California Cities
DIGEST:
This bill expands local agency progressive design-build authority to any type of project, not just water projects.
Assembly Amendments
recast provisions to reduce the number of projects local agencies can use progressive design-build procurement from 15 to 10 projects, and prohibit them from using this authority on state-owned or state-operated facilities.
ANALYSIS:
Existing law:
- Requires, pursuant to the Local Agency Public Construction Act, local officials to invite bids for construction projects and then award contracts to the lowest responsible bidder under the traditional design-bid-build project delivery system.
- Authorizes, until January 1, 2025, cities, counties, and specified special districts, transit and transportation agencies, and specified additional local agencies to use design-build for specified public works contracts in excess of $1 million using either a low bid or best value process.
- Provides the following parameters for cities and counties that use design-build:
- Allows design-build for the construction of a building or buildings and improvements directly related to the construction of a building or buildings, county sanitation wastewater treatment facilities, and park and recreational facilities;
- Allows cities and counties that operate wastewater facilities, solid waste management facilities, or water recycling facilities to use design-build for the construction of such facilities; and,
- Prohibits cities and counties from using design-build for the construction of other infrastructure, including, but not limited to, streets and highways, public rail transit, or water resources facilities and infrastructure.
- Provides that transit districts and special districts that operate wastewater facilities, solid waste management facilities, water recycling facilities, or fire protection facilities may also use design-build for specified projects.
- Requires design-build projects to use skilled labor, the issuance of performance bonds, insurance coverage, and identification of subcontractors that will complete at least one-half of 1% of the value of a design-build contract.
- Allows, until January 1, 2029, local agencies that provide for the production, storage, supply, treatment, or distribution of water to use progressive design-build (PDB) for up to 15 specified water projects each over $5 million.
- Outlines the PDB procurement process that eligible local agencies must use:
- The local agency must prepare a request for qualifications to select a design-build entity to complete the project with specified information.
- At the close of the solicitation period, the local agency must review the submissions based solely upon the information provided in the statement of qualifications. The local agency may also interview any of the design-build entities.
- Upon issuing a contract award, the local agency must publicly announce the award, the design-build entity, and the basis for the award.
- The local agency must develop guidelines to prevent conflicts of interest.
- The local agency must develop a standard form of payment and performance bond for its design-build projects.
- Requires the design-build entity to provide payment and performance bonds for the project as the local agency requires. The amount of the payment bond must not be less than the amount of the performance bond. Additionally, the design-build contract must require errors and omissions insurance coverage for the design elements of the project.
- Allows, after selecting a design-build entity, the local agency to enter into a contract to begin design and preconstruction activities to establish a guaranteed maximum price for the project. Once the local agency has agreed to a guaranteed maximum price with the design-build entity, it has the sole discretion to amend the contract as necessary to complete the project. In the event of unforeseen site conditions, the local agency can amend its contract with the design-build entity as specified.
- Provides that if, the costs for completing the project exceed the guaranteed maximum price, these excess costs become the design-build entity’s responsibility. If the cost for these activities are less than the guaranteed maximum price, the design-build entity is not entitled to the difference unless there is prior written agreement concerning the sharing of these funds.
- Provides that if the local agency and the design-build entity do not reach agreement on a guaranteed maximum price, or the local agency otherwise elects not to amend the design-build entity’s contract to complete the remaining work, the local agency can solicit proposals to complete the project from other entities. The design professionals responsible for performing design services on behalf of a design build entity that has been replaced shall have sole liability for their design errors and omissions, provided the local agency elects to use their complete and stamped designs with subsequent design build entities or licensed contractors.
- Provides that a licensed construction subcontractor that provides design services used on a PDB project must not be subject to any liability arising from their design if they do not perform construction for that design.
- Provides that design-build entities may award subcontracts once the local agency awards the contract. For subcontracts not listed in the initial proposal, design-build entities for projects of at least $10 million must provide public notice of the available work and information on the bidding process, including reasonable qualification criteria and standards, for subcontracts that complete at least one-half of 1% of the project. It may award the subcontract on a best value basis as specified.
- Allows a local agency that uses this authority to withhold up to 5% of project costs, less the work performed to establish the guaranteed maximum price, from the design-build entity if the solicitation requires a performance and payment bond. However, the percentage of retention proceeds must not exceed the percentage the local agency and design-build entity agreed to in their contract.
- Requires that local agencies who use this PDB authority to, no later than January 1, 2028, submit a report to the Legislature on the use of the methodology. This report must include specified information on these projects, the bidding process, subcontractors used, and assess the project’s performance.
This bill:
- Recasts provisions of existing PDB authority to create a new, nearly identical authorization for cities, counties, and special districts to use PDB for 10 projects of any type, each in excess of $5 million.
- Outlines the process and additional parameters for the use of this procurement method.
- Prohibits local agencies from using PDB on state-owned or state-operated facilities.
- Requires local agencies that use this authority to report specified information to the Legislature by December 31, 2028.
- Sunsets its provisions on January 1, 2030.
Background
PDB is a more recent variant on traditional design-build contracting. While there is some variation, the PDB model generally includes two phases. In the first phase, the awarding authority uses a best value process to select a design-build entity who completes preliminary plans and preconstruction services necessary to provide a cost estimate and final design proposal. The project then “progresses” to the second phase of the project, where the awarding authority and the design-build entity agree to a final design, project cost, and schedule. If they cannot agree, there is an “off ramp” between the two phases where the awarding authority can pursue other options, but still benefit from having the first phase work complete. This is different from traditional design-build where the awarding entity contracts with a single entity to design and construct a project at a set price before design work begins, and without a similar off ramp.
AB 137 (Committee on Budget, Chapter 77, Statutes of 2021) gave state agencies the authority to use PDB with Department of Finance and the State Public Works Board approval. AB 2551 (Gallagher, Chapter 760, Statutes of 2016) first gave local agencies the ability to use PDB, but only for specified water projects. Finally, the California Constitution allows cities that adopt charters to control their own “municipal affairs.” Some charter cities have used this authority to implement their own PDB process.
Comments
- Purpose of the bill. According to the author, “Local government infrastructure projects take years to plan, fund, and build because of the procurement requirements that ensure transparency and the lowest bid price. Current practices can cause delays and change orders that are costly and frustrating. Progressive design-build (PDB) is an important tool which allows local governments to build their infrastructure projects in a more efficient and timely manner. PDB allows local agencies to hire a team which includes an architect and building contractor to allow for collaboration between everyone from the beginning, which helps ensure projects meet agency needs, control costs, and remain on schedule. SB 706 allows local agencies to use PDB for any type of project that will benefit from this procurement tool. Importantly, the bill maintains key safeguards for this authority, including a $5 million minimum project threshold, and required reporting to the Legislature. These safeguards ensure that local agencies use this authority on the projects that are most likely to benefit from this approach.”
- Cart before the horse? SB 991 (Newman, Chapter 243, Statutes of 2022) gave cities, counties, and special districts that provide water service the authority to use PDB on up to 15 projects, each of which must meet or exceed $5 million. Since SB 991 only went into effect on January 1, 2023, it does not appear that anyone has had the opportunity to use this authority. Despite this, SB 706 grants PDB authority to all local agencies for up to ten local projects. Should the Legislature expand local agencies’ use of PDB before they report on its effectiveness? According to supporters, this expansion is necessary because local agencies have other projects besides water projects that stand to benefit from this more collaborative approach, and some public local, like charter cities, have already tested its use. Additionally, SB 706 includes key safeguards from SB 991, including limiting the number of PDB projects for any local agency, and the requirement to use PDB on projects over $5 million. This ensures that local agencies prioritize its use on more complicated projects that are more likely to benefit from the more collaborative, but potentially more staff-intensive, approach. Should the Legislature expand PDB before local agencies test its use on water projects?
Related/Prior Legislation
SB 617 (Newman, 2023) authorizes transit agencies, as specified, and regional transportation planning agencies, as specified, to utilize PDB for up to 10 projects, through January 1, 2029. The bill is awaiting concurrence on the Senate Floor.
AB 400 (Rubio, 2023) eliminates the sunset of January 1, 2025, for the authorization for the Department of General Services, the Department of Corrections and Rehabilitation, and local agencies, as defined, to use the design-build procurement process for specified public works. The bill is currently awaiting concurrence on Assembly Floor.
SB 146 (Gonzalez, Chapter 58, Statutes of 2023), approved in July 2023 as part of the Governor’s infrastructure package, authorized the California Department of Transportation and the Department of Water Resources, through January 1, 2034, to use PDB for eight projects with an estimated contract price that exceeds $25 million.
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
According to the Assembly Appropriations Committee:
- No state costs. This bill authorizes, but does not require, local agencies to use the PDB process. Costs incurred in its use are not reimbursable by the state.
- Potential local savings to the extent the use of the PDB process results in project cost reductions relative to other available procurement methods.
SUPPORT: (Verified 8/25/23)
California State Association of Counties (co-source)
County of San Diego (co-source)
Design Build Institute of America Western Pacific Chapter (co-source)
League of California Cities (co-source)
AJ Kirkwood and Associates, Inc.
Bernards
BNBuilders
Bothman Construction
California Association of Recreation & Park Districts
California Special Districts Association
City of Belmont
City of Roseville
City of San Marcos
City of Visalia
Collin Construction Company
County of Contra Costa
County of Los Angeles
County of Merced
County of Orange
County of Placer
County of San Bernardino
County of Solano
Critchfield Mechanical, Inc.
El Dorado Irrigation District
Elsinore Valley Municipal Water District
Flint Design Build
Fuscoe
Gilbane
Granite Construction
Los Angeles Sanitation Districts
Orange County Transportation Authority
San Gabriel Valley Council of Governments
United Industries Group, Inc.
Vanir Construction Management, Inc.
XL Construction
OPPOSITION: (Verified 8/25/23)
None received
ASSEMBLY FLOOR: 73-0, 8/24/23
AYES: Addis, Aguiar-Curry, Alanis, Alvarez, Arambula, Bains, Bauer-Kahan, Bennett, Berman, Boerner, Bryan, Calderon, Juan Carrillo, Wendy Carrillo, Cervantes, Chen, Connolly, Megan Dahle, Davies, Dixon, Essayli, Flora, Mike Fong, Vince Fong, Friedman, Gabriel, Gipson, Grayson, Haney, Hart, Holden, Hoover, Irwin, Jackson, Kalra, Lackey, Lee, Low, Lowenthal, Mathis, McCarty, Muratsuchi, Stephanie Nguyen, Ortega, Pacheco, Papan, Jim Patterson, Joe Patterson, Pellerin, Petrie-Norris, Quirk-Silva, Ramos, Rendon, Reyes, Luz Rivas, Rodriguez, Blanca Rubio, Sanchez, Santiago, Schiavo, Soria, Ta, Ting, Valencia, Villapudua, Waldron, Wallis, Weber, Wicks, Wilson, Wood, Zbur, Robert Rivas
NO VOTE RECORDED: Bonta, Gallagher, Garcia, Jones-Sawyer, Maienschein, McKinnor, Ward
Prepared by: Jonathan Peterson / GOV. & F. / (916) 651-4119
8/25/23 13:37:46
**** END ****
Date of Hearing: August 16, 2023
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Chris Holden, Chair
SBPCA Bill Id:SB 706
Author:(Caballero) – As Amended Ver:June 28, 2023
Policy Committee: | Local Government | Vote: | 8 - 0 |
|
| ||
|
|
Urgency: No State Mandated Local Program: Yes Reimbursable: No
SUMMARY:
This bill authorizes, until January 1, 2030, a city, county, or special district to use the progressive design-build process for up to 10 public works projects, not limited to water-related projects, in excess of $5 million. The bill also requires a local agency that uses the progressive design-build process to submit a report on its use of the process to the Legislature by December 31, 2028.
Specifically, this bill:
- Allows a local agency, defined as a city, county, city and county, or special district, to procure progressive design-build contracts and use the progressive design-build contracting process for up to 10 public works projects, each in excess of $5 million, not limited to water-related projects, and excluding projects on state-owned or state-operated facilities.
- Requires a local agency entering into a progressive design-build contract to develop guidelines for a standard organizational conflict-of-interest policy, consistent with applicable law, regarding the ability of a person or entity that performs services for the local agency relating to the solicitation of a design-build, to submit a proposal as a design-build entity, or to join a design-build team.
- Specifies guidelines and procedures for a local agency’s use of progressive design-build project delivery method.
- Requires, no later than December 31, 2028, a local agency that uses the progressive design-build process to submit a report to the appropriate policy and fiscal committees of the Legislature on the use of the progressive design-build process and specifies the contents of that report.
- Sunsets the bill’s provisions on January 1, 2030.
FISCAL EFFECT:
- No state costs. This bill authorizes, but does not require, local agencies to use the progressive design-build process. Costs incurred in its use are not reimbursable by the state.
- Potential local savings to the extent the use of the progressive design-build process results in project cost reductions relative to other available procurement methods.
COMMENTS:
- Purpose. The author seeks to provide a more efficient option for local agencies to invest in local infrastructure by authorizing cities, counties, and special districts to use the progressive design-build project delivery method for any type of project in excess of $5 million. According to the author:
Local government infrastructure projects take years to plan, fund, and build because of the procurement requirements that ensure transparency and the lowest bid price. Current practices can cause delays and change orders that are costly and frustrating. Progressive design-build (PDB) allows local agencies to hire a team which includes an architect and building contractor to allow for collaboration between everyone from the beginning, which helps ensure projects meet agency needs, control costs, and remain on schedule.
- Background. Most public agencies are required to use the “design-bid-build” contracting method to complete public works projects. Under this process, a public agency fully completes the design of a project prior to awarding a construction contract and must award the contract to the “lowest responsible bidder.” This process is intended to ensure the project is built for the lowest possible cost.
Under the “design-build” method, a single contract covers the design and construction of a project with a single company or consortium that acts as both the project designer and builder. The design-build entity arranges all architectural, engineering and construction services and is responsible for delivering the project at a guaranteed price and schedule based upon performance criteria set by the public agency. Local agencies, primarily water-related and healthcare districts, have statutory authority to use the design-build method in limited circumstances.
“Progressive design-build” is a stepped project delivery method where a qualified design-builder is retained early in the project for design and preconstruction activities. Generally, once the design is 40% to 60% complete, the public agency and design-builder negotiate a total maximum price and, if there is agreement, both parties proceed to the second phase of the project to complete project design and construction. If the public agency cannot come to terms with the design-builder, the public agency may use the design developed by the first design-builder, but enter into a new contract with another design-builder to complete the project.
AB 137 (Committee on Budget), Chapter 77, Statutes of 2021, authorized the Department of General Services (DGS) to use the progressive design-build process for the construction of up to three projects, and provided extensive parameters for its use.
Last year’s SB 991 (Newman), Chapter 243, Statutes of 2022, authorized, until January 1, 2029, cities, counties and special districts that provide production, storage, supply, treatment or distribution of water to use the progressive design-build process for up to 15 public works projects in excess of $5 million, similar to the progressive design-build process authorized for use by DGS. SB 991 also requires a local agency that uses the process to submit a report to the Legislature by January 1, 2028, containing specified information on the use of the process.
This bill expands the authority granted in last year’s SB 991, by authorizing, until January 1, 2030, cities, counties, and special districts to use the progressive design-build process for up to 10 public works projects of any type in excess of $5 million.
- Related Legislation. SB 617 (Newman), until January 1, 2029, allows transit districts and transportation agencies to use the progressive design-build process of project delivery for up to 10 public works projects in excess of $5 million. SB 617 is pending in this committee.
Analysis Prepared by: Jennifer Swenson / APPR. / (916) 319-2081
Date of Hearing: June 21, 2023
ASSEMBLY COMMITTEE ON LOCAL GOVERNMENT
Cecilia Aguiar-Curry, Chair
SBPCA Bill Id:SB 706
Author:(Caballero) – As Amended Ver:June 14, 2023
SENATE VOTE: 38-0
SUBJECT: Public contracts: progressive design-build: local agencies.
SUMMARY: Expands an existing authorization for local water agencies to use the progressive design-build method of project delivery for specified water projects to include any city, county or special district and any type of project. Specifically, this bill:
- Changes the definition of “local agency” as that term is used in existing law authorizing specified local agencies to use progressive design-build to include any city, county, city and county, or special district (expanding the authorization in existing law, which is limited to a city, county, city and county, or special district authorized by law to provide for the production, storage, supply, treatment, or distribution of any water from any source).
- Alters the definition of “design-build project” to include any project using the progressive design-build construction procurement process, except projects on state-owned or -operated facilities (removing the limitation in existing law to a project that treats, pumps, stores, or conveys water, wastewater, recycled water, advanced treated water, or supporting facilities).
- Extends, from January 1, 2028, to December 31, 2028, the date by which local agencies must report to the Legislature specified information on their use of progressive design-build.
- Extends, from January 1, 2029, to January 1, 2030, the sunset date on the authorization for local agencies to use progressive design-build.
- Provides that nothing in this bill and existing law authorizing local agencies to use progressive design-build authorizes a local agency to perform work on a state-owned or -operated facility.
- Provides that no reimbursement is required by this bill pursuant to Section 6 of Article XIII B of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this bill creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIII B of the California Constitution.
EXISTING LAW:
- Requires, pursuant to the Local Agency Public Construction Act (LAPC Act), local officials to invite bids for construction projects and then award contracts to the lowest responsible bidder under the traditional design-bid-build project delivery system. [Public Contract Code (PCC) §§ 20100 – 20929]
- Authorizes, until January 1, 2025, cities, counties, and specified special districts and transit agencies to use design-build for specified public works contracts in excess of $1 million using either a low bid or best value process, as specified. (PCC §§ 22160 – 22169)
- Authorizes the Department of General Services (DGS) to use the progressive design-build procurement process for up to three public works projects, as specified. (PCC §§ 10198 – 10198.8)
- Authorizes, until January 1, 2029, a city, county, city and county, or special district authorized to provide for the production, storage, supply, treatment, or distribution of water to use progressive design-build for up to 15 specified water projects each over $5 million, and outlines the process and additional parameters for the use of this procurement method. (PCC §§ 22170 – 22174)
- Requires local agencies that use the progressive design-build authority described in 4), above, to submit a report on its use to the Legislature by January 1, 2028, as specified. (PCC § 22172.5)
FISCAL EFFECT: According to the Senate Appropriations Committee, pursuant to Senate Rule 28.8, negligible state costs.
COMMENTS:
- Design-Build in California Law. California’s Legislature began granting design-build authority in the early 1990's, and has typically done so with specified parameters, such as the duration of the authority, the types of agencies allowed to use it, the types of projects for which it can be used, cost thresholds, and specified procedures that must be followed in preparing and awarding contracts. Over the years, this resulted in a number of statutes in a variety of code sections, which created confusion for public agencies and contractors alike.
In an effort to consolidate these statutes, SB 785 (Wolk), Chapter 931, Statutes of 2014, repealed existing law authorizing the DGS, the Department of Corrections and Rehabilitation (CDCR), and local agencies to use the design-build procurement process, and enacted uniform provisions authorizing DGS, CDCR, and specified local agencies to utilize the design-build procurement process for specified public works projects (with some exceptions, notably design-build authority for CalTrans). SB 785 created one set of codes for DGS and CDCR, and a separate set for specified local agencies, but with similar parameters.
Since SB 785 was enacted, the Legislature has authorized numerous additional local agencies or types of local agencies to use SB 785 design-build authority for additional projects or types of projects.
- Design-Build for Local Agencies. The LAPC Act generally requires local officials to invite bids for construction projects and then award contracts to the lowest responsible bidder. This design-bid-build method is the traditional approach to public works construction. However, California law also allows local agencies to use the design-build method, in which a single contract covers the design and construction of a project with a single company or consortium that acts as both the project designer and builder.
Existing law generally limits the use of design-build by counties and cities to the following types of projects:
- The construction of a building or buildings and improvements directly related to the construction of a building or buildings, county sanitation wastewater treatment facilities, and park and recreational facilities.
- Local and regional wastewater facilities, solid waste management facilities, or water recycling facilities (for cities and counties that operate such facilities).
Existing law expressly prohibits cities and counties from using design-build for the construction of other infrastructure, including, but not limited to, streets and highways, public rail transit, or water resources facilities and infrastructure (with some limited exceptions).
- Limits on Design-Build for Special Districts and Other Specified Agencies. Existing law also generally limits the use of design-build for special districts and a handful of other specified agencies by both type of district or agency and type of project. The agencies include: special districts that operate wastewater facilities, solid waste management facilities, water recycling facilities, or fire protection facilities; specified transit and transportation agencies; the San Diego Association of Governments (SANDAG); a few water agencies; and, healthcare districts.
For special districts that operate wastewater facilities, solid waste management facilities, water recycling facilities, or fire protection facilities, their use of design-build is limited to regional and local wastewater treatment facilities; regional and local solid waste facilities; regional and local water recycling facilities; and, fire protection facilities.
- Progressive Design-Build. Progressive design-build is a more recent variant on traditional design-build contracting. While there is some variation, the progressive design-build model generally includes two phases. In the first phase, the awarding authority uses a best value process to select a design-build entity that completes preliminary plans and preconstruction services necessary to provide a cost estimate and final design proposal. The project then “progresses” to the second phase, where the awarding authority and the design-build entity agree to a final design, project cost, and schedule. If they cannot agree, there is an “off ramp” between the two phases when the awarding authority can pursue other options, but still benefit from having the first phase of work complete. This is different from traditional design-build, where the awarding entity contracts with a single entity to design and construct a project at a set price before design work begins, and without a similar off ramp.
AB 137 (Committee on Budget), Chapter 77, Statutes of 2021, authorized the DGS to use the progressive design-build procurement process for up to three public works projects, and outlined extensive parameters for the department’s use of this procurement method. AB 2551 (Gallagher), Chapter 760, Statutes of 2016, authorized local agencies to use a number of alternative procurement methods, including progressive design-build, for any surface storage project that receives specified funding for water storage projects. Some charter cities have implemented their own progressive design-build process, relying on their Constitutional authority to control their own “municipal affairs.”
Last year, SB 991 (Newman), Chapter 243, Statutes of 2022, authorized a county, city, or special district that produces, stores, supplies, treats, or distributes water to use progressive design-build for up to 15 public works projects in excess of $5 million each that treat, pump, store, or convey water, wastewater, recycled water, advanced treated water, or supporting facilities. SB 991 outlined extensive requirements for the procurement process that must be followed, including provisions for the use of a skilled and trained workforce, protections for subcontractors, and other requirements. SB 991 required, no later than January 1, 2028, a local agency that uses the progressive design-build process authorized by the bill to submit a report to the Legislature on the use of the progressive design-build process, and specified the contents of that report. SB 991 sunsets on January 1, 2029.
- Bill Summary and Author’s Statement. This bill allows any city, county, or special district to use the progressive design-build authorization outlined in SB 991 by changing the definition of “local agency” in those statutes. This bill also changes the definition of “design-build project” in those statutes. It removes the existing limitation – projects that treat, pump, store, or convey water, wastewater, recycled water, advanced treated water, or supporting facilities – thereby allowing progressive design-build to be used for any type of project.
This bill also extends, from January 1, 2028, to December 31, 2028, the date by which local agencies must report specified information to the Legislature when they use progressive design-build. It also extends, from January 1, 2029, to January 1, 2030, the sunset date on the authorization for local agencies to use progressive design-build. This bill also clarifies that nothing in the bill or existing law authorizing local agencies to use progressive design-build authorizes a local agency to perform work on a state-owned or -operated facility.
This bill is sponsored by the California State Association of Counties, the County of San Diego, the Design Build Institute of America Western Pacific Chapter, and the League of California Cities.
According to the Author, “Local government infrastructure projects take years to plan, fund, and build because of the procurement requirements that ensure transparency and the lowest bid price. Current practices can cause delays and change orders that are costly and frustrating. Progressive design-build (PDB) is an important tool which allows local governments to build their infrastructure projects in a more efficient and timely manner. PDB allows local agencies to hire a team which includes an architect and building contractor to allow for collaboration between everyone from the beginning, which helps ensure projects meet agency needs, control costs, and remain on schedule. SB 706 allows local agencies to use PDB for any type of project that will benefit from this procurement tool. Importantly, the bill maintains key safeguards for this authority, including a $5 million minimum project threshold, and required reporting to the Legislature. These safeguards ensure that local agencies use this authority on the projects that are most likely to benefit from this approach.”
- Policy Considerations and Committee Amendment. The Committee may wish to consider the following: as summarized above, the Legislature approved SB 991 just last year. This Committee noted the following in its analysis of SB 991:
“Progressive design-build is a relatively new contracting method…the Legislature last year authorized DGS to use this method for up to three projects. This Committee also approved AB 1845 earlier this year, which allows the Metropolitan Water District of Southern California (MWD) to use the design-build, progressive design-build, and construction manager/general contractor (CM/GC) methods of project delivery for up to 15 regional water recycling projects or drought response projects.
“This bill does have some clearly-defined parameters. It limits the type of agency that may use progressive design-build (counties, cities and special districts that provide water service). It also specifies the kinds of projects that may be procured using progressive design-build (any public works project in excess of $5 million that treats, pumps, stores, or conveys water, wastewater, recycled water, advanced treated water, or supporting facilities). The bill also contains a sunset date and reporting requirements to the Legislature.
“However, this bill is the most expansive authorization of progressive design-build to date – according to the author’s statement, roughly 600 local water agencies could use the provisions of this bill. In addition, unlike other authorizations to use progressive design-build, this bill does not limit the number of projects that these local agencies may procure using progressive design-build. The Committee may wish to consider if any additional safeguards should be added to this bill.” (emphasis added)
This Committee subsequently amended SB 991 to limit its use to a maximum of 15 projects per agency.
This bill and SB 617 (Newman), which is also being heard by this Committee, expand the provisions of SB 991. As such, both bills represent even broader authorizations for the use of progressive design-build than the Legislature has previously approved. The Committee may wish to amend this bill (and SB 617) to apply a limit of 10 projects per agency to the expanded universe of agencies and projects that this bill and SB 617 propose to authorize, while retaining the 15-project limit in SB 991 for water projects undertaken by local water agencies. This would provide a greater restriction (10 projects per agency, instead of 15) on the expanded authorizations contained in this bill and SB 617, without clawing back the authorization the Legislature provided for water projects less than a year ago via SB 991. Amendments should also be drafted to address the chaptering issues between this bill and SB 617, which presently amend the same code section.
- Related Legislation. AB 400 (Blanca Rubio) extends the sunset date, from January 1, 2025, to January 1, 2031, on provisions of law authorizing local agencies to use the design-build contracting method, and expands the type of JPAs that may use design-build. AB 400 is pending in the Senate Governance and Finance Committee.
SB 617 (Newman) expands an existing authorization for local water agencies to use the progressive design-build method of project delivery for specified water projects to include transit and transportation agencies and any type of project. SB 617 is pending in this Committee.
- Previous Legislation. AB 1845 (Calderon), Chapter 275, Statutes of 2022, authorized MWD to use design-build, progressive design-build and CM/GC project delivery methods for up to 15 regional water recycling projects or drought response projects.
AB 2789 (Mullin), Chapter 214, Statutes of 2022, repealed the January 1, 2023, sunset date authorizing the Midpeninsula Regional Open Space District and the Santa Clara Valley Open-Space Authority to use the design-build process for the construction of facilities or other buildings, and authorized the East Bay Regional Park District to use the design-build process for the construction of facilities or other buildings.
SB 1354 (Jones), Chapter 900, Statutes of 2022, allowed counties and cities to use design-build contracting for projects that are necessary to comply with construction-related accessibility standards, as specified.
AB 137 (Committee on Budget), Chapter 77, Statutes of 2021, authorized DGS to use the progressive design-build procurement process for up to three public works projects, and outlined parameters for the department’s use of this procurement method.
SB 626 (Dodd), Chapter 247, Statutes of 2021, authorized the Department of Water Resources to use the design-build and CM/GC project delivery methods for facilities of the State Water Project, excluding through Delta conveyance, as specified.
AB 851 (Caballero and Gloria), Chapter 821, Statutes of 2017, allowed the Santa Clara Valley Water District to use the design-build procurement method for specified types of projects.
AB 994 (Muratsuchi), Chapter 321, Statutes of 2017, allowed the Beach Cities Health District to use the design-build procurement method to assign contracts for the construction of facilities or other buildings in the district.
AB 1523 (Obernolte and Reyes), Chapter 154, Statutes of 2017, authorized the San Bernardino County Transportation Authority to use design-build for the construction of the Mt. Vernon Avenue Viaduct project.
SB 373 (Cannella), Chapter 391, Statutes of 2017, allowed the Stanislaus Regional Water Authority to use design-build for its Regional Surface Water Supply Project.
SB 793 (Hill), Chapter 627, Statutes of 2017, allowed the Peninsula Health Care District, the Midpeninsula Regional Open Space District, and the Santa Clara Valley Open-Space Authority to use the design-build procurement method to assign contracts for the construction of facilities or other buildings in those districts.
SB 957 (Hueso), Chapter 212, Statutes of 2016, allowed health care districts that own or operate a hospital or clinic to use the design-build procedure to construct a building or improvements directly related to the construction of a hospital or health facility building.
AB 1290 (Dahle), Chapter 34, Statutes of 2015, allowed the Mayers Memorial Hospital District to use the design-build procedure to construct a building or improvements directly related to the construction of a hospital or health facility building in the district.
SB 374 (Hueso), Chapter 715, Statutes of 2015, allowed SANDAG to use the design-build procurement process for specified development projects related to transit facilities developed or jointly developed by SANDAG.
AB 155 (Alejo), Chapter 865, Statutes of 2014, allowed the Monterey County Water Resources Agency to use design-build contracting to construct a pipeline or tunnel that will connect two reservoirs that the agency owns and operates.
SB 268 (Gaines), Chapter 18, Statutes of 2014, allowed the Last Frontier Health Care District to use the design-build process when contracting for the construction of a building and improvements directly related to a hospital or health facility building at the Modoc Medical Center.
SB 785 (Wolk), Chapter 931, Statutes of 2014, repealed existing law authorizing DGS, CDCR, and local agencies to use the design-build procurement process, and enacted uniform provisions authorizing DGS, CDCR, and specified local agencies to utilize the design-build procurement process for specified public works projects.
- Arguments in Support. The California State Association of Counties, the County of San Diego, the Design Build Institute of America Western Pacific Chapter, and the League of California Cities, sponsors of this measure, write, “Due to the limitations of current PDB legislation, it would be in the public interest to expand the authority to additional agencies and different types of projects because PDB allows public agencies to complete public works projects more quickly and at a lower cost; thereby allowing public dollars to provide greater benefits to the public - especially federal dollars with strict use-it-or-lose-it timelines - without sacrificing important protections that the public expects. Progressive Design-Build entails use of a two-part award system allowing for confirmation of full scope of work, with fewer ambiguities, less time and cost in procurement, and more competitive pricing from trades.
“SB 706 will allow local agencies throughout the state to attract more proposers for their projects by significantly reducing the cost of responding to RFPs compared to other contracting methods. In addition to offering the advantage of a reduced project schedule and cost, it also increases partnering between the agency and contractor through the design process during the initial phase leading to more predictable project outcomes. California State has shown great leadership in the Design-Build space over the past 30 years and Design-Build is no longer an alternative form of project delivery, it is becoming the norm…Progressive Design-Build is the logical next step and will give local governments a proven option to expand and deliver.”
- Arguments in Opposition. None on file.
REGISTERED SUPPORT / OPPOSITION:
Support
California State Association of Counties [SPONSOR]
County of San Diego [SPONSOR]
Design Build Institute of America Western Pacific Chapter [SPONSOR]
League of California Cities [SPONSOR]
Aecom (if amended)
Aj Kirkwood and Associates, INC
Ameresco (if amended)
Bernards
Bnbuilders
Bothman Construction
California Association of Recreation & Park Districts
California Special Districts Association
City of Belmont
City of Roseville
City of San Marcos
Collin Construction Company
Contra Costa County
County of Los Angeles Board of Supervisors
County of Merced
County of Orange
County of Placer
Critchfield Mechanical, INC
El Dorado Irrigation District
Elsinore Valley Municipal Water District
Engie (if amended)
Flint Design Build
Fuscoe
Gilbane
Granite Construction
Johnson Controls, INC. (if amended)
Los Angeles County
Los Angeles County Sanitation Districts
National Association of Energy Service Companies (NAESCO) (if amended)
Noresco (if amended)
Orange County Transportation Authority
Pacificwest Energy Solutions (if amended)
San Bernardino County
San Gabriel Valley Council of Governments
Sitelogiq (if amended)
Solano County Board of Supervisors
Southland Industries (if amended)
Syserco Energy Solutions (if amended)
Trane Technologies (if amended)
United Industries Group, INC
Vanir Construction Management, INC
Veregy (if amended)
Willdan Group, INC. (if amended)
Xl Construction
Opposition
None on file
Analysis Prepared by: Angela Mapp / L. GOV. / (916) 319-3958
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 706 |
THIRD READING
Bill No: SB 706
Author: Caballero (D), et al.
Amended: 4/10/23
Vote: 21
SENATE GOVERNANCE & FIN. COMMITTEE: 8-0, 3/29/23
AYES: Caballero, Seyarto, Blakespear, Dahle, Durazo, Glazer, Skinner, Wiener
SENATE APPROPRIATIONS COMMITTEE: Senate Rule 28.8
SUBJECT: Public contracts: progressive design-build: local agencies
SOURCE: California State Association of Counties
County of San Diego
Design Build Institute of America Western Pacific Chapter
League of California Cities
DIGEST:
This bill expands local agency progressive design-build authority to any type of project, not just water projects.
ANALYSIS:
Existing law:
- Requires, pursuant to the Local Agency Public Construction Act, local officials to invite bids for construction projects and then award contracts to the lowest responsible bidder under the traditional design-bid-build project delivery system.
- Authorizes, until January 1, 2025, cities, counties, and specified special districts, transit and transportation agencies, and specified additional local agencies to use design-build for specified public works contracts in excess of $1 million using either a low bid or best value process.
- Provides the following parameters for cities and counties that use design-build:
- Allows design-build for the construction of a building or buildings and improvements directly related to the construction of a building or buildings, county sanitation wastewater treatment facilities, and park and recreational facilities;
- Allows cities and counties that operate wastewater facilities, solid waste management facilities, or water recycling facilities to use design-build for the construction of such facilities; and,
- Prohibits cities and counties from using design-build for the construction of other infrastructure, including, but not limited to, streets and highways, public rail transit, or water resources facilities and infrastructure.
- Provides that transit districts and special districts that operate wastewater facilities, solid waste management facilities, water recycling facilities, or fire protection facilities may also use design-build for specified projects.
- Requires design-build projects to use skilled labor, the issuance of performance bonds, insurance coverage, and identification of subcontractors that will complete at least one-half of 1% of the value of a design-build contract.
- Allows, until January 1, 2029, local agencies that provide for the production, storage, supply, treatment, or distribution of water to use progressive design-build for up to 15 specified water projects each over $5 million.
- Outlines the progressive design-build procurement process that eligible local agencies must use:
- The local agency must prepare a request for qualifications to select a design-build entity to complete the project with specified information.
- At the close of the solicitation period, the local agency must review the submissions based solely upon the information provided in the statement of qualifications. The local agency may also interview any of the design-build entities.
- Upon issuing a contract award, the local agency must publicly announce the award, the design-build entity, and the basis for the award.
- The local agency must develop guidelines to prevent conflicts of interest.
- The local agency must develop a standard form of payment and performance bond for its design-build projects.
- Requires the design-build entity to provide payment and performance bonds for the project as the local agency requires. The amount of the payment bond must not be less than the amount of the performance bond. Additionally, the design-build contract must require errors and omissions insurance coverage for the design elements of the project.
- Allows, after selecting a design-build entity, the local agency to enter into a contract to begin design and preconstruction activities to establish a guaranteed maximum price for the project. Once the local agency has agreed to a guaranteed maximum price with the design-build entity, it has the sole discretion to amend the contract as necessary to complete the project. In the event of unforeseen site conditions, the local agency can amend its contract with the design-build entity as specified.
- Provides that if, the costs for completing the project exceed the guaranteed maximum price, these excess costs become the design-build entity’s responsibility. If the cost for these activities are less than the guaranteed maximum price, the design-build entity is not entitled to the difference unless there is prior written agreement concerning the sharing of these funds.
- Provides that if the local agency and the design-build entity do not reach agreement on a guaranteed maximum price, or the local agency otherwise elects not to amend the design-build entity’s contract to complete the remaining work, the local agency can solicit proposals to complete the project from other entities. The design professionals responsible for performing design services on behalf of a design build entity that has been replaced shall have sole liability for their design errors and omissions, provided the local agency elects to use their complete and stamped designs with subsequent design build entities or licensed contractors.
- Provides that a licensed construction subcontractor that provides design services used on a progressive design-build project must not be subject to any liability arising from their design if they do not perform construction for that design.
- Provides that design-build entities may award subcontracts once the local agency awards the contract. For subcontracts not listed in the initial proposal, design-build entities for projects of at least $10 million must provide public notice of the available work and information on the bidding process, including reasonable qualification criteria and standards, for subcontracts that complete at least one-half of 1% of the project. It may award the subcontract on a best value basis as specified.
- Allows a local agency that uses this authority to withhold up to 5% of project costs, less the work performed to establish the guaranteed maximum price, from the design-build entity if the solicitation requires a performance and payment bond. However, the percentage of retention proceeds must not exceed the percentage the local agency and design-build entity agreed to in their contract.
- Requires that local agencies who use this progressive design-build authority to, no later than January 1, 2028, submit a report to the Legislature on the use of the methodology. This report must include specified information on these projects, the bidding process, subcontractors used, and assess the project’s performance.
This bill:
- Allows cities, counties, and special districts to use progressive design-build for any project, not just water projects.
- Extends progressive design-build reporting requirement and sunset date by one year.
Background
Progressive design-build is a more recent variant on traditional design-build contracting. While there is some variation, the progressive design-build model generally includes two phases. In the first phase, the awarding authority uses a best value process to select a design-build entity who completes preliminary plans and preconstruction services necessary to provide a cost estimate and final design proposal. The project then “progresses” to the second phase of the project, where the awarding authority and the design-build entity agree to a final design, project cost, and schedule. If they cannot agree, there is an “off ramp” between the two phases where the awarding authority can pursue other options, but still benefit from having the first phase work complete. This is different from traditional design-build where the awarding entity contracts with a single entity to design and construct a project at a set price before design work begins, and without a similar off ramp.
AB 137 (Committee on Budget, Chapter 77, Statutes of 2021) gave state agencies the authority to use progressive design-build with Department of Finance and the State Public Works Board approval. AB 2551 (Gallagher, Chapter 760, Statutes of 2016) first gave local agencies the ability to use progressive design-build, but only for specified water projects. Finally, the California Constitution allows cities that adopt charters to control their own “municipal affairs.” Some charter cities have used this authority to implement their own progressive design-build process.
Comments
- Purpose of the bill. According to the author, “Local government infrastructure projects take years to plan, fund, and build because of the procurement requirements that ensure transparency and the lowest bid price. Current practices can cause delays and change orders that are costly and frustrating. Progressive design-build (PDB) is an important tool which allows local governments to build their infrastructure projects in a more efficient and timely manner. PDB allows local agencies to hire a team which includes an architect and building contractor to allow for collaboration between everyone from the beginning, which helps ensure projects meet agency needs, control costs, and remain on schedule. SB 706 allows local agencies to use PDB for any type of project that will benefit from this procurement tool. Importantly, the bill maintains key safeguards for this authority, including a $5 million minimum project threshold, and required reporting to the Legislature. These safeguards ensure that local agencies use this authority on the projects that are most likely to benefit from this approach.”
- Cart before the horse? SB 991 (Newman, Chapter 243, Statutes of 2022) gives cities, counties, and special districts that provide water service the authority to use PDB on up to 15 projects, each of which must meet or exceed $5 million. Since SB 991 only went into effect on January 1, 2023, it does not appear that anyone has had the opportunity to use this authority. Despite this, SB 706 expands PDB authority to all local agencies for any project. Should the Legislature expand SB 991’s PDB before local agencies that use the authority report on its effectiveness? According to supporters, this expansion is necessary because public agencies have other projects besides water projects that stand to benefit from this more collaborative approach, and some public agencies, like charter cities, have already tested its use. Additionally, SB 706 maintains key safeguards from SB 991, including the 15-project limit for any local agency, and the requirement to use PDB on projects over $5 million. This ensures that local agencies prioritize its use on more complicated projects that are more likely to benefit from the more collaborative, but potentially more staff-intensive, approach. Should the Legislature expand SB 991 before local agencies test its use on water projects?
FISCAL EFFECT: Appropriation: No Fiscal Com.: Yes Local: Yes
SUPPORT: (Verified 4/19/23)
California State Association of Counties (co-source)
County of San Diego (co-source)
Design Build Institute of America Western Pacific Chapter (co-source)
League of California Cities (co-source)
AJ Kirkwood and Associates, Inc.
Bernards
BNBuilders
Bothman Construction
California Special Districts Association
Collin Construction Company
County of Los Angeles
County of Placer
County of San Bernardino
Critchfield Mechanical, Inc.
Flint Design Build
Fuscoe
Gilbane
Granite Construction
Los Angeles Sanitation Districts
Orange County Transportation Authority
United Industries Group, Inc.
Vanir Construction Management, Inc.
OPPOSITION: (Verified 4/19/23)
None received
Prepared by: Jonathan Peterson / GOV. & F. / (916) 651-4119
4/19/23 15:20:05
**** END ****
SENATE COMMITTEE ON GOVERNANCE AND FINANCE
Senator Anna M. Caballero, Chair
2023 - 2024 Regular
Bill No: | SB 706 | Hearing Date: | 3/29/23 |
Author: | Caballero | Tax Levy: | No |
Version: | 3/21/23 | Fiscal: | Yes |
Consultant: | Peterson | ||
Public contracts: progressive design-build: local agencies
Expands local agency progressive design-build authority to any type of project, not just water projects.
Background
Contracting. The Local Agency Public Construction Act generally requires local agencies to invite bids for construction projects and award contracts to the lowest responsible bidder. Local agencies typically use the traditional design-bid-build method for constructing public works. This approach splits construction projects into two distinct phases: design and construction. During the design phase, the local agency prepares detailed project plans and specifications using its own employees or by hiring outside architects and engineers. Once project designs are complete, local agencies invite bids from the construction community and award the contract to the lowest responsible bidder. Over the last couple of decades, legislators have gradually expanded local agencies’ authority to procure construction projects using various alternatives to the design-bid-build project delivery method.
Design-build. State law allows state and local officials, until January 1, 2025, to use the design-build method for contracts in excess of $1 million to procure both design and construction services from a single company before the development of complete plans and specifications. Under design-build, the owner contracts with a single entity—which can be a single firm, a consortium, or a joint venture—to design and construct a project. Before inviting bids, the owner prepares documents that describe the basic concept of the project, as opposed to a complete set of drawings and specifications of the final product. In the bidding phase, the owner typically evaluates bids on a best-value basis, incorporating technical factors, such as qualifications and design quality, in addition to price. The Department of General Services, the California Department of Corrections and Rehabilitation, cities, counties, transit districts, special districts operating wastewater, water recycling, or solid waste management facilities, and certain health care districts may use design-build.
Originally, the authorizations for state agencies and local governments to use design-build were dispersed throughout state law in separate code sections. In 2014, the Legislature consolidated these provisions into consistent, generally-applicable statutes (SB 785, Wolk, 2014). SB 785 outlines a standardized design-build procurement process in which the awarding authority may prepare a list of qualified or short-listed entities, based on specified criteria. Once a list of qualified or short-listed entities is complete, the awarding authority may prepare a request for proposals (RFP) that invites prequalified or short-listed entities to submit competitive sealed proposals in the manner the awarding authority prescribes.
For projects utilizing low bid as the selection method, the competitive bidding process must involve lump-sum bids by the prequalified or short-listed design-build entities. Local agencies must award contracts to the design-build entity that is the lowest responsible bidder.
For those projects utilizing best value as a selection method, local agencies must evaluate proposals using only the criteria and selection procedures specifically identified in the RFP. The awarding authority may reserve the right to request revisions and conduct negotiations with responsive proposers, if the authority specifies in the RFP how it will ensure that negotiations are conducted in good faith. The authority may hold discussions or negotiations with responsive proposers using the process the RFP specifies. The awarding authority ranks responsive proposers on value provided. The awarding authority must award the contract to the responsible design-build entity whose proposal is determined by the authority to have offered the best value to the public. Upon issuance of a contract award, the awarding authority must publicly announce its award, identifying the design-build entity it has awarded the contract to, along with a written decision supporting its contract award and stating the basis of the award.
The state’s design-build statutes also impose requirements for the use of skilled labor, the issuance of payment and performance bonds, insurance coverage, and identification of subcontractors that will complete at least one-half of 1% of the value of a contract.
Progressive design-build. Progressive design-build (PDB) is a more recent variant on traditional design-build contracting. While there is some variation, the progressive design-build model generally includes two phases. In the first phase, the awarding authority uses a best value process to select a design-build entity who completes preliminary plans and preconstruction services necessary to provide a cost estimate and final design proposal. The project then “progresses” to the second phase of the project, where the awarding authority and the design-build entity agree to a final design, project cost, and schedule. If they cannot agree, there is an “off ramp” between the two phases where the awarding authority can pursue other options, but still benefit from having the first phase work complete. This is different from traditional design-build where the awarding entity contracts with a single entity to design and construct a project at a set price before design work begins, and without a similar off ramp.
AB 137 (Committee on Budget, 2021) gave state agencies the authority to use progressive design-build with Department of Finance and the State Public Works Board approval. AB 2551 (Gallagher, 2016) first gave local agencies the ability to use progressive design-build, but only for specified water projects. To use this authority, AB 2551 provides that the local agency can consider minimum factors, such as price, technical design, and life-cycle costs, when appropriate for the procurement method, but not include them when the local agency determines they are not appropriate. Finally, the California Constitution allows cities that adopt charters to control their own “municipal affairs.” Some charter cities have used this authority to implement their own progressive design-build process.
SB 991 (Newman, 2022) authorizes, until January 1, 2029, local agencies that provide for the production, storage, supply, treatment, or distribution of water to use progressive design-build for up to 15 specified water projects each over $5 million. The bill outlined the progressive design-build procurement process that eligible local agencies must use:
- The local agency must prepare a request for qualifications to select a design-build entity to complete the project with specified information;
- At the close of the solicitation period, the local agency must review the submissions based solely upon the information provided in the statement of qualifications. The local agency may also interview any of the design-build entities;
- Upon issuing a contract award, the local agency must publicly announce the award, the design-build entity, and the basis for the award;
- The local agency must develop guidelines to prevent conflicts of interest; and
- The local agency must develop a standard form of payment and performance bond for its design-build projects.
After selecting a design-build entity, the local agency can enter into a contract to begin design and preconstruction activities to establish a guaranteed maximum price for the project. Once the local agency has agreed to a guaranteed maximum price with the design-build entity, it has the sole discretion to amend the contract as necessary to complete the project. In the event of unforeseen site conditions, the local agency can amend its contract with the design-build entity. If the costs for completing the project exceed the guaranteed maximum price, these excess costs become the design-build entity’s responsibility. If the cost for these activities are less than the guaranteed maximum price, the design-build entity is not entitled to the difference unless there is prior written agreement concerning the sharing of these funds. If the local agency and the design-build entity do not reach agreement on a guaranteed maximum price, or the local agency otherwise elects not to amend the design-build entity’s contract to complete the remaining work, the local agency can solicit proposals to complete the project from other entities.
SB 991 also requires that local agencies who use this progressive design-build authority to, no later than January 1, 2028, submit a report to the Legislature on the use of the methodology. This report must include specified information on these projects, the bidding process, subcontractors used, and assess the project’s performance.
SB 991 limits PDB’s use to water projects. The Design-Build Institute of America wants to allow cities, counties, and special districts to use PDB for all their projects, not just water projects.
Proposed Law
Senate Bill 706 allows cities, counties, and special districts to use progressive design-build for any project, not just water projects. The measure also changes the deadline for local agencies to submit required reports to the Legislature from January 1, 2028, to December 31, 2028.
State Revenue Impact
No estimate.
Comments
1. Purpose of the bill. According to the author, “Local government infrastructure projects take years to plan, fund, and build because of the procurement requirements that ensure transparency and the lowest bid price. Current practices can cause delays and change orders that are costly and frustrating. Progressive design-build (PDB) is an important tool which allows local governments to build their infrastructure projects in a more efficient and timely manner. PDB allows local agencies to hire a team which includes an architect and building contractor to allow for collaboration between everyone from the beginning, which helps ensure projects meet agency needs, control costs, and remain on schedule. SB 706 allows local agencies to use PDB for any type of project that will benefit from this procurement tool. Importantly, the bill maintains key safeguards for this authority, including a $5 million minimum project threshold, and required reporting to the Legislature. These safeguards ensure that local agencies use this authority on the projects that are most likely to benefit from this approach.”
2. Cart before the horse? SB 991 gives cities, counties, and special districts that provide water service the authority to use PDB on up to 15 projects, each of which must meet or exceed $5 million. Since SB 991 only went into effect on January 1, 2023, it does not appear that anyone has had the opportunity to use this authority. Despite this, SB 706 expands PDB authority to all local agencies for any project. Should the Legislature expand SB 991’s PDB before local agencies that use the authority report on its effectiveness? According to supporters, this expansion is necessary because public agencies have other projects besides water projects that stand to benefit from this more collaborative approach, and some public agencies, like charter cities, have already tested its use. Additionally, SB 706 maintains key safeguards from SB 991, including the 15-project limit for any local agency, and the requirement to use PDB on projects over $5 million. This ensures that local agencies prioritize its use on more complicated projects that are more likely to benefit from the more collaborative, but potentially more staff-intensive, approach. Should the Legislature expand SB 991 before local agencies test its use on water projects?
3. Lucky number. SB 991 limits each eligible agency’s use of PDB to 15 water projects. SB 706 expands this authority to any project, but still limits each agency to 15 projects. On the one hand, limiting the number of projects that can use this authority helps to ensure the authority can be tested, and reported upon, before its use becomes more widespread. On the other hand, expanding PDB to non-water projects could help local agencies identify more projects where its use yields more public benefits compared to other procurement methods. Should the Legislature reassess the 15-project limit if it decides that expanding PDB is justified?
4. Watching the sunset. SB 991 requires local agencies that use its authority to report to the Legislature by January 1, 2028, and sunsets the authority to use PDB on January 1, 2029. This allows the Legislature one year to review the report before deciding whether to extend the January 1, 2029 sunset, or make changes to the authority. SB 706 pushes back the reporting deadline one year to give local agencies more time to assess which projects will benefit from PDB’s use. However, SB 706 does not make a corresponding change to the authority for local agencies to use PDB. This means some local agencies may submit their reports the day before the authority sunsets, which does not give the Legislature time to review this information before deciding whether it should modify or extend PDB’s use. The Committee may wish to consider amending the bill to ensure that the Legislature still has time to review the report on PDB before the authority sunsets.
Support and Opposition
(3/24/23)
Support:
California State Association of Counties (Co-Sponsor)
County of San Diego (Co-Sponsor)
Design Build Institute of America Western Pacific Chapter (Co-Sponsor)
League of California Cities (Co-Sponsor)
Aj Kirkwood and Associates, INC
Bernards
Bnbuilders
Bothman Construction
California Special Districts Association
Collin Construction Company
Critchfield Mechanical, INC
Flint Design Build
Fuscoe
Gilbane
Granite Construction
San Bernardino County
United Industries Group, INC
Vanir Construction Management, INC
Opposition: None submitted
-- END --
Discussed in Hearing
Assembly Standing Committee on Local Government
Senate Floor
Senate Standing Committee on Governance and Finance
Bill Author
Bill Co-Author(s):