SB 272: San Mateo County Transit District: job order contracting: pilot program.
- Session Year: 2025-2026
- House: Senate
- Latest Version Date: 2025-10-03
Current Status:
Passed
(2025-10-03: Chaptered by Secretary of State. Chapter 310, Statutes of 2025.)
Introduced
In Committee
Awaiting First Chamber Vote
Passed First Chamber
In Committee
Awaiting Second Chamber Vote
Passed Second Chamber
Enacted
What does this bill do?
The bill allows the San Mateo County Transit District to run a pilot using job order contracting, a standing contract with unit prices for repetitive repair or remodeling work, capped at $5 million per contract and $1 million per individual job. The contracts must be competitively bid, follow a labor deal with the San Mateo Building Trades Council, require prevailing wages and independent cost estimates for each job, and reserve smaller jobs (up to $250,000) for certified small or disabled-veteran businesses when eligible.
The summary is provided by generative AI which can make mistakes. For original language, please view the details in the table below.
The Local Agency Public Construction Act sets forth procedures that a local agency is required to follow when procuring certain services or work. The act also sets forth specific public contracting requirements for certain transit districts, including the San Mateo County Transit District for construction work contracts. The act authorizes certain local agencies, including school districts and community college districts, to engage in job order contracting, as prescribed.
This bill would establish a pilot program to authorize the San Mateo County Transit District to use job order contracting as a procurement method. The bill would impose a $5,000,000 cap on awards under a single job order contract and a $1,000,000 cap on any single job order. The bill would limit the term of an initial contract to a maximum of 12 months, with extensions as prescribed. The bill would establish various procedures and requirements for the use of job order contracting under the pilot program. The bill would require the district, on or before January 1, 2030, to submit to the appropriate policy and fiscal committees of the Legislature a report on the use of job order contracting under the bill. The pilot program would be repealed on January 1, 2032.
This bill would make legislative findings and declarations as to the necessity of a special statute for the San Mateo County Transit District.
The Local Agency Public Construction Act sets forth procedures that a local agency is required to follow when procuring certain services or work. The act also sets forth specific public contracting requirements for certain transit districts, including the San Mateo County Transit District for construction work contracts. The act authorizes certain local agencies, including school districts and community college districts, to engage in job order contracting, as prescribed.
This bill would establish a pilot program to authorize the San Mateo County Transit District to use job order contracting as a procurement method. The bill would impose a $5,000,000 cap on awards under a single job order contract and a $1,000,000 cap on any single job order. The bill would limit the term of an initial contract to a maximum of 12 months, with extensions as prescribed. The bill would establish various procedures and requirements for the use of job order contracting under the pilot program. The bill would require the district, on or before January 1, 2030, to submit to the appropriate policy and fiscal committees of the Legislature a report on the use of job order contracting under the bill. The pilot program would be repealed on January 1, 2032.
This bill would make legislative findings and declarations as to the necessity of a special statute for the San Mateo County Transit District.
The Local Agency Public Construction Act sets forth procedures that a local agency is required to follow when procuring certain services or work. The act also sets forth specific public contracting requirements for certain transit districts, including the San Mateo County Transit District for construction work contracts. The act authorizes certain local agencies, including school districts and community college districts, to engage in job order contracting, as prescribed.
This bill would establish a pilot program to authorize the San Mateo County Transit District to use job order contracting as a procurement method. The bill would impose a $5,000,000 cap on awards under a single job order contract and a $1,000,000 cap on any single job order. The bill would limit the term of an initial contract to a maximum of 12 months, with extensions as prescribed. The bill would establish various procedures and requirements for the use of job order contracting under the pilot program. The bill would require the district, on or before January 1, 2030, to submit to the appropriate policy and fiscal committees of the Legislature a report on the use of job order contracting under the bill. The pilot program would be repealed on January 1, 2032.
This bill would make legislative findings and declarations as to the necessity of a special statute for the San Mateo County Transit District.
The Local Agency Public Construction Act sets forth procedures that a local agency is required to follow when procuring certain services or work. The act also sets forth specific public contracting requirements for certain transit districts, including the San Mateo County Transit District for construction work contracts. The act authorizes certain local agencies, including school districts and community college districts, to engage in job order contracting, as prescribed.
This bill would establish a pilot program to authorize the San Mateo County Transit District to use job order contracting as a procurement method. The bill would impose a $5,000,000 cap on awards under a single job order contract and a $1,000,000 cap on any single job order. The bill would limit the term of an initial contract to a maximum of 12 months, with extensions as prescribed. The bill would establish various procedures and requirements for the use of job order contracting under the pilot program. The bill would require the district, on or before January 1, 2030, to submit to the appropriate policy and fiscal committees of the Legislature a report on the use of job order contracting under the bill. The pilot program would be repealed on January 1, 2032.
This bill would make legislative findings and declarations as to the necessity of a special statute for the San Mateo County Transit District.
The Local Agency Public Construction Act sets forth procedures that a local agency is required to follow when procuring certain services or work. The act also sets forth specific public contracting requirements for certain transit districts, including the San Mateo County Transit District for construction work contracts. The act authorizes certain local agencies, including school districts and community college districts, to engage in job order contracting, as prescribed.
This bill would establish a pilot program to authorize the San Mateo County Transit District to use job order contracting as a procurement method. The bill would impose a $5,000,000 cap on awards under a single job order contract and a $1,000,000 cap on any single job order. The bill would limit the term of an initial contract to a maximum of 12 months, with extensions as prescribed. The bill would establish various procedures and requirements for the use of job order contracting under the pilot program. The bill would require the district, on or before January 1, 2030, to submit to the appropriate policy and fiscal committees of the Legislature a report on the use of job order contracting under the bill. The pilot program would be repealed on January 1, 2032.
This bill would make legislative findings and declarations as to the necessity of a special statute for the San Mateo County Transit District.
(a)(1)Notwithstanding Article 19 (commencing with Section 20330) of Chapter 1 of Part 3 of Division 2 of the Public Contract Code, the district may use the procurement method outlined in this article for a job order contract.
(2)The district shall not contract for work that is protected by applicable collective bargaining agreements. All job order contracts shall comply with all district collective bargaining agreements.
(3)Job order contracts of the district shall be competitively bid and awarded to bidders providing qualified responsive bids.
(4)Job order contracts shall be for repair, remodeling, or other repetitive work to be done according to unit prices. No annual contracts may be awarded for any new construction.
(5)A job order contract shall be subject to a project labor agreement between the district and the San Mateo Building Trades Council, or an amendment or extension to that agreement.
(b)Solicitations for job order contracts shall progress as follows:
(1)The district shall prepare a set of solicitation documents for job order contracts. The documents shall include a unit price catalog or other established unit prices, job order contract terms, job order contract technical specifications, and any other information the district deems necessary to adequately describe the districts needs.
(2)An architect, engineer, consultant, or contractor retained by the district to assist in the development of the job order contract solicitation documents shall not be eligible to bid or to participate in the preparation of a job order contract bid.
(3)The district may award multiple job order contracts in response to a single job order contract solicitation.
(c)The district shall develop a system for evaluating job order contract bids for awarding job order contracts.
(d)The award of a job order contract shall progress as follows:
(1)The district shall prepare a request for bids for job order contracts based on the solicitation documents prepared under paragraph (1) of subdivision (b) that invites job order contractors to submit sealed bids in the manner prescribed by the district.
(2)Each bidding job order contractor shall include in its bid one or more adjustment factors to the established unit prices provided in the request for bids based on the contracts technical specifications.
(3)Each bidding job order contractor shall agree to identify any subcontractors to be used for the job orders performed pursuant to the job order contract.
(4)The award of job order contracts, if any, shall be made to a job order contractor or to job order contractors that the district determines to be qualified and responsive based upon preestablished criteria to be determined by the district.
(5)The job order contractors shall comply with the districts project labor agreement, as applicable.
(6)Notwithstanding paragraph (4), the district, by a process determined by the district, may award any job order for repair or renovation work with a value equal to or less than two hundred fifty thousand dollars ($250,000) to a job order contractor that is also a certified small business enterprise, as established by the districts small business enterprise certification process or any similar certification process acceptable to the district, or to a job order contractor that is also a disabled veterans business enterprise, as certified by the Department of General Services.
103399.6.(a)The maximum total dollar amount that may be awarded under a single job order contract shall not exceed five million dollars ($5,000,000) in the initial contract term of the job order contract. No single job order may exceed one million dollars ($1,000,000).
(b)Job order contracts may be executed for an initial contract term of no more than 12 months and may be extended or renewed for two subsequent annual terms and a maximum of ten million dollars ($10,000,000) over the subsequent two terms of the contract.
(c)Work shall not be split or separated into smaller job orders for the purpose of evading the cost limits of the article.
(d)Dollar amounts specified in this section may be adjusted annually to reflect the percentage change in the California Consumer Price Index.
103399.7.(a)All work bid under job order contracts shall comply with Chapter 4 (commencing with Section 4100) of Part 1 of Division 2 of the Public Contract Code and is subject to all of the penalties and provisions set forth in that chapter.
(b)For purposes of this article, if a job order contractor chooses to use a subcontractor, the job order contractor shall verify that the subcontractor possesses and maintains the appropriate licenses and credentials required.
(c)If the district, after conducting an administrative due process review, determines that there has been a violation of Chapter 4 (commencing with Section 4100) of Part 1 of Division 2 of the Public Contract Code, including, but not limited to, bid shopping by the job order contractor, the district may terminate the job order contract, declare the contractor ineligible for future job order contracts for a period of time to be determined by the district, or withdraw authorization for the contractor to proceed with awarded work.
103399.8.(a)A job order contract shall set forth in the general conditions of the job order contract the party or parties responsible for seeing that Article 2 (commencing with Section 1770) of Chapter 1 of Part 7 of Division 2 of the Labor Code is complied with.
(b)For purposes of job order contracting, prevailing wages shall apply to all work ordered under the job order contract regardless of thresholds set forth in Section 1771.5 of the Labor Code.
(c)The job order contractor shall pay the prevailing wage in effect at the time the job order contract is issued by the district and all increases as published by the Department of Industrial Relations for the term of the job order contract, including all overtime, holiday, and shift provisions published by the Department of Industrial Relations.
(d)The district shall designate one individual to act as a monitor to inspect job sites for labor compliance violations at the request of the designated labor representative in its project labor agreement.
103399.9.In order to prevent fraud, waste, and abuse, the district shall prepare for each individual job order developed under a job order contract an independent cost estimate. The estimate shall be prepared before the receipt of any job order contractors estimate for the work and shall be compared to the job order contractors estimate to determine the reasonableness of that estimate before issuance of any job order. If the district finds the job order contractors estimate to perform work for a given job order to be unreasonable, not cost effective, or undesirable, the district may elect not to issue the job order to the job order contractor, and may, instead, use any other available procurement procedures or choose not to move forward with the work.
103399.10.(a)The district shall submit to the appropriate policy and fiscal committees of the Legislature, on or before January 1, 2030, a report on the use of job order contracting under this article. The report shall include, but shall not be limited to, all of the following information:
(1)A description of the districts system for evaluating job order contract bids for award of job order contracts, including, but not limited to, the criteria used by the district to determine a qualified and responsive job order contractor.
(2)A description of each job order contract awarded and the contractor awarded the contract.
(3)An assessment of the use of job order contracting under this article.
(b)A report to be submitted pursuant to subdivision (a) shall be submitted in compliance with Section 9795 of the Government Code.
103399.11.This article shall remain in effect only until January 1, 2032, and as of that date is repealed.
SEC. 2.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the need for a pilot program to determine the potential benefits of job order contracting to a large transportation agency without setting policy for smaller local agencies.
(a)(1)Notwithstanding Article 19 (commencing with Section 20330) of Chapter 1 of Part 3 of Division 2 of the Public Contract Code, the district may use the procurement method outlined in this article for a job order contract.
(2)The district shall not contract for work that is protected by applicable collective bargaining agreements. All job order contracts shall comply with all district collective bargaining agreements.
(3)Job order contracts of the district shall be competitively bid and awarded to bidders providing qualified responsive bids.
(4)Job order contracts shall be for repair, remodeling, or other repetitive work to be done according to unit prices. No annual contracts may be awarded for any new construction.
(5)A job order contract shall be subject to a project labor agreement between the district and the San Mateo Building Trades Council, or an amendment or extension to that agreement.
(b)Solicitations for job order contracts shall progress as follows:
(1)The district shall prepare a set of solicitation documents for job order contracts. The documents shall include a unit price catalog or other established unit prices, job order contract terms, job order contract technical specifications, and any other information the district deems necessary to adequately describe the districts needs.
(2)An architect, engineer, consultant, or contractor retained by the district to assist in the development of the job order contract solicitation documents shall not be eligible to bid or to participate in the preparation of a job order contract bid.
(3)The district may award multiple job order contracts in response to a single job order contract solicitation.
(c)The district shall develop a system for evaluating job order contract bids for awarding job order contracts.
(d)The award of a job order contract shall progress as follows:
(1)The district shall prepare a request for bids for job order contracts based on the solicitation documents prepared under paragraph (1) of subdivision (b) that invites job order contractors to submit sealed bids in the manner prescribed by the district.
(2)Each bidding job order contractor shall include in its bid one or more adjustment factors to the established unit prices provided in the request for bids based on the contracts technical specifications.
(3)Each bidding job order contractor shall agree to identify any subcontractors to be used for the job orders performed pursuant to the job order contract.
(4)The award of job order contracts, if any, shall be made to a job order contractor or to job order contractors that the district determines to be qualified and responsive based upon preestablished criteria to be determined by the district.
(5)The job order contractors shall comply with the districts project labor agreement, as applicable.
(6)Notwithstanding paragraph (4), the district, by a process determined by the district, may award any job order for repair or renovation work with a value equal to or less than two hundred fifty thousand dollars ($250,000) to a job order contractor that is also a certified small business enterprise, as established by the districts small business enterprise certification process or any similar certification process acceptable to the district, or to a job order contractor that is also a disabled veterans business enterprise, as certified by the Department of General Services.
103399.6.(a)The maximum total dollar amount that may be awarded under a single job order contract shall not exceed five million dollars ($5,000,000) in the initial contract term of the job order contract. No single job order may exceed one million dollars ($1,000,000).
(b)Job order contracts may be executed for an initial contract term of no more than 12 months and may be extended or renewed for two subsequent annual terms and a maximum of ten million dollars ($10,000,000) over the subsequent two terms of the contract.
(c)Work shall not be split or separated into smaller job orders for the purpose of evading the cost limits of the article.
(d)Dollar amounts specified in this section may be adjusted annually to reflect the percentage change in the California Consumer Price Index.
103399.7.(a)All work bid under job order contracts shall comply with Chapter 4 (commencing with Section 4100) of Part 1 of Division 2 of the Public Contract Code and is subject to all of the penalties and provisions set forth in that chapter.
(b)For purposes of this article, if a job order contractor chooses to use a subcontractor, the job order contractor shall verify that the subcontractor possesses and maintains the appropriate licenses and credentials required.
(c)If the district, after conducting an administrative due process review, determines that there has been a violation of Chapter 4 (commencing with Section 4100) of Part 1 of Division 2 of the Public Contract Code, including, but not limited to, bid shopping by the job order contractor, the district may terminate the job order contract, declare the contractor ineligible for future job order contracts for a period of time to be determined by the district, or withdraw authorization for the contractor to proceed with awarded work.
103399.8.(a)A job order contract shall set forth in the general conditions of the job order contract the party or parties responsible for seeing that Article 2 (commencing with Section 1770) of Chapter 1 of Part 7 of Division 2 of the Labor Code is complied with.
(b)For purposes of job order contracting, prevailing wages shall apply to all work ordered under the job order contract regardless of thresholds set forth in Section 1771.5 of the Labor Code.
(c)The job order contractor shall pay the prevailing wage in effect at the time the job order contract is issued by the district and all increases as published by the Department of Industrial Relations for the term of the job order contract, including all overtime, holiday, and shift provisions published by the Department of Industrial Relations.
(d)The district shall designate one individual to act as a monitor to inspect job sites for labor compliance violations at the request of the designated labor representative in its project labor agreement.
103399.9.In order to prevent fraud, waste, and abuse, the district shall prepare for each individual job order developed under a job order contract an independent cost estimate. The estimate shall be prepared before the receipt of any job order contractors estimate for the work and shall be compared to the job order contractors estimate to determine the reasonableness of that estimate before issuance of any job order. If the district finds the job order contractors estimate to perform work for a given job order to be unreasonable, not cost effective, or undesirable, the district may elect not to issue the job order to the job order contractor, and may, instead, use any other available procurement procedures or choose not to move forward with the work.
103399.10.(a)The district shall submit to the appropriate policy and fiscal committees of the Legislature, on or before January 1, 2030, a report on the use of job order contracting under this article. The report shall include, but shall not be limited to, all of the following information:
(1)A description of the districts system for evaluating job order contract bids for award of job order contracts, including, but not limited to, the criteria used by the district to determine a qualified and responsive job order contractor.
(2)A description of each job order contract awarded and the contractor awarded the contract.
(3)An assessment of the use of job order contracting under this article.
(b)A report to be submitted pursuant to subdivision (a) shall be submitted in compliance with Section 9795 of the Government Code.
103399.11.This article shall remain in effect only until January 1, 2032, and as of that date is repealed.
SEC. 2.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the need for a pilot program to determine the potential benefits of job order contracting to a large transportation agency without setting policy for smaller local agencies.
(a)(1)Notwithstanding Article 19 (commencing with Section 20330) of Chapter 1 of Part 3 of Division 2 of the Public Contract Code, the district may use the procurement method outlined in this article for a job order contracts. contract.
(2)The district shall not contract for work that is protected by applicable collective bargaining agreements. All job order contracts shall comply with all district collective bargaining agreements.
(3)Job order contracts of the district shall be competitively bid and awarded to bidders providing qualified responsive bids.
(4)Job order contracts shall be for repair, remodeling, or other repetitive work to be done according to unit prices. No annual contracts may be awarded for any new construction.
(5)A job order contract shall be subject to a project labor agreement between the district and the San Mateo Building Trades Council, or an amendment or extension to that agreement.
(b)Solicitations for job order contracts shall progress as follows:
(1)The district shall prepare a set of solicitation documents for job order contracts. The documents shall include a unit price catalog or other established unit prices, job order contract terms, job order contract technical specifications, and any other information the district deems necessary to adequately describe the districts needs.
(2)An architect, engineer, consultant, or contractor retained by the district to assist in the development of the job order contract solicitation documents shall not be eligible to bid or to participate in the preparation of a job order contract bid.
(3)The district may award multiple job order contracts in response to a single job order contract solicitation.
(c)The district shall develop a system for evaluating job order contract bids for awarding job order contracts.
(d)The award of a job order contract shall progress as follows:
(1)The district shall prepare a request for bids for job order contracts based on the solicitation documents prepared under paragraph (1) of subdivision (b) that invites job order contractors to submit sealed bids in the manner prescribed by the district.
(2)Each bidding job order contractor shall include in its bid one or more adjustment factors to the established unit prices provided in the request for bids based on the contracts technical specifications.
(3)Each bidding job order contractor shall agree to identify any subcontractors to be used for the job orders performed pursuant to the job order contract.
(4)The award of job order contracts, if any, shall be made to a job order contractor or to job order contractors that the district determines to be qualified and responsive based upon preestablished criteria to be determined by the district.
(5)The job order contractors shall comply with the districts project labor agreement, as applicable.
(6)Notwithstanding paragraph (4), the district, by a process determined by the district, may award any job order for repair or renovation work with a value equal to or less than two hundred fifty thousand dollars ($250,000) to a job order contractor that is also a certified small business enterprise, as established by the districts small business enterprise certification process or any similar certification process acceptable to the district, or to a job order contractor that is also a disabled veterans business enterprise, as certified by the Department of General Services.
103399.6.(a)The maximum total dollar amount that may be awarded under a single job order contract shall not exceed five million dollars ($5,000,000) in the initial contract term of the job order contract. No single job order may exceed one million dollars ($1,000,000).
(b)Job order contracts may be executed for an initial contract term of no more than 12 months and may be extended or renewed for two subsequent annual terms and a maximum of ten million dollars ($10,000,000) over the subsequent two terms of the contract.
(c)Work shall not be split or separated into smaller job orders for the purpose of evading the cost limits of the article.
(d)Dollar amounts specified in this section may be adjusted annually to reflect the percentage change in the California Consumer Price Index.
103399.7.(a)All work bid under job order contracts shall comply with Chapter 4 (commencing with Section 4100) of Part 1 of Division 2 of the Public Contract Code and is subject to all of the penalties and provisions set forth in that chapter.
(b)For purposes of this article, if a job order contractor chooses to use a subcontractor, the job order contractor shall verify that the subcontractor possesses and maintains the appropriate licenses and credentials required.
(c)If the district, after conducting an administrative due process review, determines that there has been a violation of Chapter 4 (commencing with Section 4100) of Part 1 of Division 2 of the Public Contract Code, including, but not limited to, bid shopping by the job order contractor, the district may terminate the job order contract, declare the contractor ineligible for future job order contracts for a period of time to be determined by the district, or withdraw authorization for the contractor to proceed with awarded work.
103399.8.(a)A job order contract shall set forth in the general conditions of the job order contract the party or parties responsible for seeing that Article 2 (commencing with Section 1770) of Chapter 1 of Part 7 of Division 2 of the Labor Code is complied with.
(b)For purposes of job order contracting, prevailing wages shall apply to all work ordered under the job order contract regardless of thresholds set forth in Section 1771.5 of the Labor Code.
(c)The job order contractor shall pay the prevailing wage in effect at the time the job order contract is issued by the district and all increases as published by the Department of Industrial Relations for the term of the job order contract, including all overtime, holiday, and shift provisions published by the Department of Industrial Relations.
(d)The district shall designate one individual to act as a monitor to inspect job sites for labor compliance violations at the request of the designated labor representative in its project labor agreement.
103399.9.In order to prevent fraud, waste, and abuse, the district shall prepare for each individual job order developed under a job order contract an independent cost estimate. The estimate shall be prepared before the receipt of any job order contractors estimate for the work and shall be compared to the job order contractors estimate to determine the reasonableness of that estimate before issuance of any job order. If the district finds the job order contractors estimate to perform work for a given job order to be unreasonable, not cost effective, or undesirable, the district may elect not to issue the job order to the job order contractor, and may, instead, use any other available procurement procedures or choose not to move forward with the work.
103399.10.(a)The district shall submit to the appropriate policy and fiscal committees of the Legislature, on or before January 1, 2030, a report on the use of job order contracting under this article. The report shall include, but shall not be limited to, all of the following information:
(1)A description of the districts system for evaluating job order contract bids for award of job order contracts, including, but not limited to, the criteria used by the district to determine a qualified and responsive job order contractor.
(2)A description of each job order contract awarded and the contractor awarded the contract.
(3)An assessment of the use of job order contracting under this article.
(b)A report to be submitted pursuant to subdivision (a) shall be submitted in compliance with Section 9795 of the Government Code.
103399.11.This article shall remain in effect only until January 1, 2032, and as of that date is repealed.
SEC. 2.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the need for a pilot program to determine the potential benefits of job order contracting to a large transportation agency without setting policy for smaller local agencies.
(a)(1)Notwithstanding Article 19 (commencing with Section 20330) of Chapter 1 of Part 3 of Division 2 of the Public Contract Code, the district may use the procurement method outlined in this article for job order contracts.
(2)The district shall not contract for work that is protected by applicable collective bargaining agreements. All job order contracts shall comply with all district collective bargaining agreements.
(3)Job order contracts of the district shall be competitively bid and awarded to bidders providing qualified responsive bids.
(4)Job order contracts shall be for repair, remodeling, or other repetitive work to be done according to unit prices. No annual contracts may be awarded for any new construction.
(5)A job order contract shall be subject to a project labor agreement between the district and the San Mateo Building Trades Council, or an amendment or extension to that agreement.
(b)Solicitations for job order contracts shall progress as follows:
(1)The district shall prepare a set of solicitation documents for job order contracts. The documents shall include a unit price catalog or other established unit prices, job order contract terms, job order contract technical specifications, and any other information the district deems necessary to adequately describe the districts needs.
(2)An architect, engineer, consultant, or contractor retained by the district to assist in the development of the job order contract solicitation documents shall not be eligible to bid or to participate in the preparation of a job order contract bid.
(3)The district may award multiple job order contracts in response to a single job order contract solicitation.
(c)The district shall develop a system for evaluating job order contract bids for awarding job order contracts.
(d)The award of a job order contract shall progress as follows:
(1)The district shall prepare a request for bids for job order contracts based on the solicitation documents prepared under paragraph (1) of subdivision (b) that invites job order contractors to submit sealed bids in the manner prescribed by the district.
(2)Each bidding job order contractor shall include in its bid one or more adjustment factors to the established unit prices provided in the request for bids based on the contracts technical specifications.
(3)Each bidding job order contractor shall agree to identify any subcontractors to be used for the job orders performed pursuant to the job order contract.
(4)The award of job order contracts, if any, shall be made to a job order contractor or to job order contractors that the district determines to be qualified and responsive based upon preestablished criteria to be determined by the district.
(5)The job order contractors shall comply with the districts project labor agreement, as applicable.
(6)Notwithstanding paragraph (4), the district, by a process determined by the district, may award any job order for repair or renovation work with a value equal to or less than two hundred fifty thousand dollars ($250,000) to a job order contractor that is also a certified small business enterprise, as established by the districts small business enterprise certification process or any similar certification process acceptable to the district, or to a job order contractor that is also a disabled veterans business enterprise, as certified by the Department of General Services.
103399.6.(a)The maximum total dollar amount that may be awarded under a single job order contract shall not exceed five million dollars ($5,000,000) in the initial contract term of the job order contract. No single job order may exceed one million dollars ($1,000,000).
(b)Job order contracts may be executed for an initial contract term of no more than 12 months and may be extended or renewed for two subsequent annual terms and a maximum of ten million dollars ($10,000,000) over the subsequent two terms of the contract.
(c)Work shall not be split or separated into smaller job orders for the purpose of evading the cost limits of the article.
(d)Dollar amounts specified in this section may be adjusted annually to reflect the percentage change in the California Consumer Price Index.
103399.7.(a)All work bid under job order contracts shall comply with Chapter 4 (commencing with Section 4100) of Part 1 of Division 2 of the Public Contract Code and is subject to all of the penalties and provisions set forth in that chapter.
(b)For purposes of this article, if a job order contractor chooses to use a subcontractor, the job order contractor shall verify that the subcontractor possesses and maintains the appropriate licenses and credentials required.
(c)If the district, after conducting an administrative due process review, determines that there has been a violation of Chapter 4 (commencing with Section 4100) of Part 1 of Division 2 of the Public Contract Code, including, but not limited to, bid shopping by the job order contractor, the district may terminate the job order contract, declare the contractor ineligible for future job order contracts for a period of time to be determined by the district, or withdraw authorization for the contractor to proceed with awarded work.
103399.8.(a)A job order contract shall set forth in the general conditions of the job order contract the party or parties responsible for seeing that Article 2 (commencing with Section 1770) of Chapter 1 of Part 7 of Division 2 of the Labor Code is complied with.
(b)For purposes of job order contracting, prevailing wages shall apply to all work ordered under the job order contract regardless of thresholds set forth in Section 1771.5 of the Labor Code.
(c)The job order contractor shall pay the prevailing wage in effect at the time the job order contract is issued by the district and all increases as published by the Department of Industrial Relations for the term of the job order contract, including all overtime, holiday, and shift provisions published by the Department of Industrial Relations.
(d)The district shall designate one individual to act as a monitor to inspect job sites for labor compliance violations at the request of the designated labor representative in its project labor agreement.
103399.9.In order to prevent fraud, waste, and abuse, the district shall prepare for each individual job order developed under a job order contract an independent cost estimate. The estimate shall be prepared before the receipt of any job order contractors estimate for the work and shall be compared to the job order contractors estimate to determine the reasonableness of that estimate before issuance of any job order. If the district finds the job order contractors estimate to perform work for a given job order to be unreasonable, not cost effective, or undesirable, the district may elect not to issue the job order to the job order contractor, and may, instead, use any other available procurement procedures or choose not to move forward with the work.
103399.10.(a)The district shall submit to the appropriate policy and fiscal committees of the Legislature, on or before January 1, 2030, a report on the use of job order contracting under this article. The report shall include, but shall not be limited to, all of the following information:
(1)A description of the districts system for evaluating job order contract bids for award of job order contracts, including, but not limited to, the criteria used by the district to determine a qualified and responsive job order contractor.
(2)A description of each job order contract awarded and the contractor awarded the contract.
(3)An assessment of the use of job order contracting under this article.
(b)A report to be submitted pursuant to subdivision (a) shall be submitted in compliance with Section 9795 of the Government Code.
103399.11.This article shall remain in effect only until January 1, 2032, and as of that date is repealed.
SEC. 2.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the need for a pilot program to determine the potential benefits of job order contracting to a large transportation agency without setting policy for smaller local agencies.
(a)(1)Notwithstanding Article 19 (commencing with Section 20330) of Chapter 1 of Part 3 of Division 2 of the Public Contract Code, the district may use the procurement method outlined in this article for job order contracts.
(2)The district shall not contract for work that is protected by applicable collective bargaining agreements. All job order contracts shall comply with all district collective bargaining agreements.
(3)Job order contracts of the district shall be competitively bid and awarded to bidders providing qualified responsive bids.
(4)Job order contracts shall be for repair, remodeling, or other repetitive work to be done according to unit prices. No annual contracts may be awarded for any new construction.
(b)Solicitations for job order contracts shall progress as follows:
(1)The district shall prepare a set of solicitation documents for job order contracts. The documents shall include a unit price catalog or other established unit prices, job order contract terms, job order contract technical specifications, and any other information the district deems necessary to adequately describe the districts needs.
(2)An architect, engineer, consultant, or contractor retained by the district to assist in the development of the job order contract solicitation documents shall not be eligible to bid or to participate in the preparation of a job order contract bid.
(3)The district may award multiple job order contracts in response to a single job order contract solicitation.
(c)The district shall develop a system for evaluating job order contract bids for awarding job order contracts.
(d)The award of a job order contract shall progress as follows:
(1)The district shall prepare a request for bids for job order contracts based on the solicitation documents prepared under paragraph (1) of subdivision (b) that invites job order contractors to submit sealed bids in the manner prescribed by the district.
(2)Each bidding job order contractor shall include in its bid one or more adjustment factors to the established unit prices provided in the request for bids based on the contracts technical specifications.
(3)Each bidding job order contractor shall agree to identify any subcontractors to be used for the job orders performed pursuant to the job order contract.
(4)The award of job order contracts, if any, shall be made to a job order contractor or to job order contractors that the district determines to be qualified and responsive based upon preestablished criteria to be determined by the district.
(5)The job order contractors shall comply with the districts project labor agreement, as applicable.
(6)Notwithstanding paragraph (4), the district, by a process determined by the district, may award any job order for repair or renovation work with a value equal to or less than two hundred fifty thousand dollars ($250,000) to a job order contractor that is also a certified small business enterprise, as established by the districts small business enterprise certification process or any similar certification process acceptable to the district, or to a job order contractor that is also a disabled veterans business enterprise, as certified by the Department of General Services.
103399.6.(a)The maximum total dollar amount that may be awarded under a single job order contract shall not exceed five million dollars ($5,000,000) in the initial contract term of the job order contract. No single job order may exceed one million dollars ($1,000,000).
(b)Job order contracts may be executed for an initial contract term of no more than 12 months and may be extended or renewed for two subsequent annual terms and a maximum of ten million dollars ($10,000,000) over the subsequent two terms of the contract.
(c)Work shall not be split or separated into smaller job orders for the purpose of evading the cost limits of the article.
(d)Dollar amounts specified in this section may be adjusted annually to reflect the percentage change in the California Consumer Price Index.
103399.7.(a)All work bid under job order contracts shall comply with Chapter 4 (commencing with Section 4100) of Part 1 of Division 2 of the Public Contract Code and is subject to all of the penalties and provisions set forth in that chapter.
(b)For purposes of this article, if a job order contractor chooses to use a subcontractor, the job order contractor shall verify that the subcontractor possesses and maintains the appropriate licenses and credentials required.
(c)If the district, after conducting an administrative due process review, determines that there has been a violation of Chapter 4 (commencing with Section 4100) of Part 1 of Division 2 of the Public Contract Code, including, but not limited to, bid shopping by the job order contractor, the district may terminate the job order contract, declare the contractor ineligible for future job order contracts for a period of time to be determined by the district, or withdraw authorization for the contractor to proceed with awarded work.
103399.8.(a)A job order contract shall set forth in the general conditions of the job order contract the party or parties responsible for seeing that Article 2 (commencing with Section 1770) of Chapter 1 of Part 7 of Division 2 of the Labor Code is complied with.
(b)For purposes of job order contracting, prevailing wages shall apply to all work ordered under the job order contract regardless of thresholds set forth in Section 1771.5 of the Labor Code.
(c)The job order contractor shall pay the prevailing wage in effect at the time the job order contract is issued by the district and all increases as published by the Department of Industrial Relations for the term of the job order contract, including all overtime, holiday, and shift provisions published by the Department of Industrial Relations.
(d)The district shall designate one individual to act as a monitor to inspect job sites for labor compliance violations at the request of the designated labor representative in its project labor agreement.
103399.9.In order to prevent fraud, waste, and abuse, the district shall prepare for each individual job order developed under a job order contract an independent cost estimate. The estimate shall be prepared before the receipt of any job order contractors estimate for the work and shall be compared to the job order contractors estimate to determine the reasonableness of that estimate before issuance of any job order. If the district finds the job order contractors estimate to perform work for a given job order to be unreasonable, not cost effective, or undesirable, the district may elect not to issue the job order to the job order contractor, and may, instead, use any other available procurement procedures or choose not to move forward with the work.
103399.10.(a)The district shall submit to the appropriate policy and fiscal committees of the Legislature, on or before January 1, 2030, a report on the use of job order contracting under this article. The report shall include, but shall not be limited to, all of the following information:
(1)A description of the districts system for evaluating job order contract bids for award of job order contracts, including, but not limited to, the criteria used by the district to determine a qualified and responsive job order contractor.
(2)A description of each job order contract awarded and the contractor awarded the contract.
(3)An assessment of the use of job order contracting under this article.
(b)A report to be submitted pursuant to subdivision (a) shall be submitted in compliance with Section 9795 of the Government Code.
103399.11.This article shall remain in effect only until January 1, 2032, and as of that date is repealed.
SEC. 2.The Legislature finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the need for a pilot program to determine the potential benefits of job order contracting to a large transportation agency without setting policy for smaller local agencies.
|
Date
|
Status
|
|---|---|
| Oct 3, 2025 | Chaptered by Secretary of State. Chapter 310, Statutes of 2025. |
| Oct 3, 2025 | Approved by the Governor. |
| Sep 9, 2025 | Enrolled and presented to the Governor at 2 p.m. |
| Sep 3, 2025 | Assembly amendments concurred in. (Ayes 40. Noes 0. Page 2442.) Ordered to engrossing and enrolling. |
| Aug 28, 2025 | In Senate. Concurrence in Assembly amendments pending. |
| Aug 28, 2025 | Read third time. Passed. (Ayes 75. Noes 1. Page 2765.) Ordered to the Senate. |
| Aug 20, 2025 | Read third time and amended. |
| Aug 20, 2025 | Ordered to third reading. |
| Jun 23, 2025 | Ordered to third reading. |
| Jun 23, 2025 | From consent calendar on motion of Assembly Member Aguiar-Curry. |
| Jun 19, 2025 | Read second time. Ordered to consent calendar. |
| Jun 18, 2025 | From committee: Do pass. Ordered to consent calendar. (Ayes 10. Noes 0.) (June 18). |
| May 12, 2025 | Referred to Com. on L. GOV. |
| Apr 1, 2025 | In Assembly. Read first time. Held at Desk. |
| Apr 1, 2025 | Read third time. Passed. (Ayes 39. Noes 0. Page 603.) Ordered to the Assembly. |
| Mar 27, 2025 | Read second time. Ordered to consent calendar. |
| Mar 26, 2025 | From committee: Do pass. Ordered to consent calendar. (Ayes 14. Noes 0. Page 534.) (March 25). |
| Mar 18, 2025 | From committee with author's amendments. Read second time and amended. Re-referred to Com. on TRANS. |
| Mar 11, 2025 | Set for hearing March 25. |
| Feb 14, 2025 | Referred to Com. on TRANS. |
| Feb 5, 2025 | From printer. May be acted upon on or after March 7. |
| Feb 4, 2025 | Introduced. Read first time. To Com. on RLS. for assignment. To print. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Sep 3, 2025 | Unfinished Business SB272 Becker et al. Concurrence | Senate Floor |
Passed |
|
| Aug 28, 2025 | SB 272 Becker Senate Third Reading By Stefani | Assembly Floor |
Passed |
|
| Jun 18, 2025 | Do pass. To Consent Calendar. | Assembly Standing Committee on Local Government |
Passed |
|
| Apr 1, 2025 | Consent Calendar 2nd SB272 Becker | Senate Floor |
Passed |
|
| Mar 25, 2025 | Do pass and be ordered to the Consent Calendar | Senate Standing Committee on Transportation |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| AMERICAN SOCIETY OF CIVIL ENGINEERS-REGION 9 | ** Support | |
| San Mateo County Transit District | ** Support | |
| Sourcewell | ** Support |
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 272 |
UNFINISHED BUSINESS
Bill No: SB 272
Author: Becker (D), et al.
Amended: 8/20/25
Vote: 21
SENATE TRANSPORTATION COMMITTEE: 14-0, 3/25/25
AYES: Cortese, Strickland, Archuleta, Arreguín, Blakespear, Cervantes, Gonzalez, Grayson, Limón, Menjivar, Richardson, Seyarto, Umberg, Valladares
NO VOTE RECORDED: Dahle
SENATE FLOOR: 39-0, 4/1/25 (Consent)
AYES: Allen, Alvarado-Gil, Archuleta, Arreguín, Ashby, Becker, Blakespear, Cabaldon, Caballero, Cervantes, Choi, Cortese, Dahle, Durazo, Gonzalez, Grayson, Grove, Hurtado, Jones, Laird, Limón, McGuire, McNerney, Menjivar, Niello, Ochoa Bogh, Padilla, Pérez, Richardson, Rubio, Seyarto, Smallwood-Cuevas, Stern, Strickland, Umberg, Valladares, Wahab, Weber Pierson, Wiener
NO VOTE RECORDED: Reyes
ASSEMBLY FLOOR: 75-1, 8/28/25 – See last page for vote
SUBJECT: San Mateo County Transit District: job order contracting: pilot program
SOURCE: San Mateo County Transit District
DIGEST:
This bill authorizes the San Mateo County Transit District (SamTrans) to enter into job order contracts (JOCs).
Assembly Amendments
of 8/20/25 were technical and added coauthors.
ANALYSIS:
Existing law requires, pursuant to the Local Agency Public Construction Act (LAPC Act), local officials to invite bids for construction projects and then award contracts to the lowest responsible bidder under the traditional design-bid-build project delivery system. Authorizes certain state and local agencies to enter into JOCs, including counties, school districts, community college districts, the California State University, the Santa Clara Valley Transportation Authority (VTA), the Los Angeles Metropolitan Transportation Agency (LA Metro) and the California Department of Transportation (Caltrans), as specified.
This bill:
- Authorizes SamTrans to use the procurement method outlined in this bill for JOCs.
- Prohibits SamTrans from contracting for work that is protected by applicable collective bargaining agreements. Requires all JOCs to comply with all SamTrans collective bargaining agreements.
- Requires JOCs of SamTrans to be competitively bid and awarded to bidders providing qualified responsive bids. Requires JOCs to be for construction that is repetitive, for repair or remodeling, to be done according to unit prices. Prohibits JOC annual contracts from being awarded for new construction.
- Requires JOCs to be subject to the project labor agreement (PLA) between SamTrans and the San Mateo Building Trades Council or an amendment or extension of that agreement.
- Specifies requirements for solicitations for JOCs to progress. Requires SamTrans to develop a system for evaluating JOC bids for award of JOCs. Specifies requirements for the award of a JOC to progress.
- Provides that the maximum total dollar amount that may be awarded under a single JOC shall not exceed $5 million dollars in the initial contract term of the JOC. No single job order may exceed $1 million.
- Provides that JOCs may be executed for a contract term of no more than 12 months and may be extended or renewed for two subsequent annual terms and a maximum of $10 million over the subsequent two terms of the contract. Prohibits work from being split or separated into smaller job orders for the purpose of evading the cost limitation provisions of this bill. Authorizes SamTrans to adjust the amounts in this bill to the California Consumer Price Index (CPI).
- Requires a JOC to set forth in the general conditions of the JOC the party or parties responsible for seeing that existing law governing prevailing wages on public works projects, Article 2 (commencing with Section 1770) of Chapter 1 of Part 7 of Division 2 of the Labor Code, is complied with.
- Requires, for purposes of job order contracting, prevailing wages to apply to all work ordered under the JOC regardless of thresholds set forth in Section 1771.5 of the Labor Code.
- Requires the job order contractor to pay the prevailing wage in effect at the time the job order is issued by SamTrans and all increases as published by the Department of Industrial Relations (DIR) for the term of the JOC, including all overtime, holiday, and shift provisions published by the DIR. Requires SamTrans to designate one individual to act as a monitor to inspect job sites for labor compliance violations at the request of the designated labor representative in its PLA.
- Requires, in order to prevent fraud, waste, and abuse, SamTrans to prepare for each individual job order developed under a JOC an independent cost estimate as specified. If SamTrans finds the job order contractor’s bid to perform work for a given job order to be unreasonable, not cost effective, or undesirable, SamTrans may elect not to issue the job order to the job order contractor, and may, instead, utilize any other available procurement procedures or choose not to move forward with the work.
- Requires SamTrans to submit to the appropriate policy and fiscal committees of the Legislature, on or before January 1, 2030, a report on the use of job order contracting under this bill, as specified.
- Provides a sunset date of January 1, 2032.
Comments
- Purpose of this bill. According to the author, “SB 272 provides the San Mateo County Transit District (SamTrans) with a proven, cost-effective procurement tool Job Order Contracting (JOC) to expedite small maintenance and repair projects while maintaining full compliance with public contracting laws. Other transit agencies, including LA Metro and VTA, already use JOC to streamline project delivery, reduce administrative burdens, and save taxpayer dollars. By authorizing a pilot program for SamTrans, this bill ensures that critical transit infrastructure can be maintained efficiently, improving service reliability and rider experience.”
- Who is SamTrans? SamTrans operates 76 bus routes throughout San Mateo County and into parts of San Francisco and Palo Alto. It began operating bus service in 1976 after consolidating 11 municipal transit services in the county into a coordinated network. In mid-1977, SamTrans inaugurated its mainline service from Palo Alto to San Francisco, previously operated by Greyhound.
Also in 1977, SamTrans initiated service for persons with mobility impairments through its Redi-Wheels program more than a decade before the passage of the Americans with Disabilities Act. The service, provided by Redi-Wheels on the bayside and RediCoast on the coastside, regularly provides more than 1,000 trips in a day. SamTrans also serves as the administrative body for Caltrain commuter rail and the San Mateo County Transportation Authority, who have contracted with SamTrans to serve as their managing agency, under the direction of their appointed boards.
- What is Job Order Contracting? A JOC is a competitively bid, fixed price, indefinite quantity contract for the performance of minor construction, as well as the renovation, alteration, painting, and repair of existing public facilities. A JOC is generally a multi-year contract that includes a base year and multiple "option years," and is awarded before the awarding agency has identified specific work that it needs the contractor to perform. A typical JOC involves a variety of tasks such as roofing, electrical work, plumbing, and painting that are required for all of a public agency's buildings for a period of years.
A JOC is a fixed price agreement in that it is based upon specified charges contained in a Unit Price Book (UPB), which is prepared by the public agency or by independent commercial sources. The UPB sets forth detailed repair and construction tasks, including task descriptions, specifications, units of measurement, and unit prices for each task. Unit price refers to the amount paid for a single unit of an item of work. A contractor's bid is expressed in terms of a percentage of the specified UPB charges. The UPB is then used to determine the costs of each proposed project during the term of the contract. As an example, if a procuring agency's per unit catalog price for an HVAC installation is $1,000, and a contractor submits a bid to do that work with an adjustment factor of 1.13, the contractor is agreeing to install the HVAC for $1,130.
The total JOC value may be specified as a range with a certain guaranteed minimum. The award of annual contracts on a unit price basis enables what would otherwise be multiple separately-bid projects to be combined into one bid. This contracting method is intended to reduce costs and accelerate completion of smaller projects. It is not generally viewed as an appropriate method of contracting for large, complex construction projects that require extensive or innovative design or are likely to encounter changes and revisions during construction. JOCs are typically used for well-defined, recurring or repetitive work where quick execution is essential, not for single larger projects.
- Job order contracting in California. The Legislature has authorized multiple agencies to use job order contracting, some state and some local, including counties, school districts, community college districts, and the California State University system. California counties have enjoyed the authority to use job order contracting since 1983. Counties may award annual JOCs of up to $3 million, adjusted annually to reflect the California CPI, to the lowest responsible bidder or using best value (for specified counties).
Additionally, as part of the 2021-2022 state budget, the Legislature authorized Caltrans to use JOC, but the authority was limited to the new Clean California Beautification Program. In 2023, as part of the Governor’s Infrastructure package Caltrans’ authority was expanded. SB 146 (Gonzalez, Chapter 58, Statutes of 2023), authorized Caltrans to use JOCs, through 2033, for general highway and traffic maintenance. Finally, the Legislature approved JOC authority for some regional transportation agencies including VTA in Santa Clara County, and most recently for LA Metro.
- SamTrans wants to join the party. SB 272 authorizes SamTrans to develop a process for and use JOCs. Specifically, this bill authorizes SamTrans to enter into JOCs on a competitive basis for construction that is repetitive, for repair, or for renovation or modification. The maximum total dollar amount that may be awarded under a single JOC shall not exceed $5 million dollars in the initial contract term, and no single job order may exceed $1 million. JOCs may be executed for a contract term of no more than 12 months and may be extended or renewed for two subsequent annual terms and a maximum of $10 million over the subsequent two terms of the contract. This bill also prohibits SamTrans from contracting for work that is protected by applicable collective bargaining agreements and requires all JOCs to comply with all SamTrans collective bargaining agreements. Finally, this bill requires SamTrans to submit to the appropriate policy and fiscal committees of the Legislature, on or before January 1, 2030, a report on its use of job order contracting, as specified; and provides a sunset date of January 1, 2032.
FISCAL EFFECT: Appropriation: No Fiscal Com.: No Local: No
SUPPORT: (Verified 8/28/25)
San Mateo County Transit District (Source)
American Society of Civil Engineers-Region 9
Sourcewell
OPPOSITION: (Verified 8/28/25)
None received
ARGUMENTS IN SUPPORT: According to SamTrans, “The District intends to use JOC for jobs like painting, bus shelter repairs, concrete/asphalt repairs, fencing repair and installation, lighting repairs, and elevator repair and rehabilitation. Implementation of JOC would also provide benefits to our local workers, including consistent work, predictable income, and reliable jobs for construction and building trades, including small and emerging contractors.
“As transit agencies across the state look for ways to reduce costs, enhance operations, and support the local economy, the District believes the use of JOC would advance these goals.”
ASSEMBLY FLOOR: 75-1, 8/28/25
AYES: Addis, Aguiar-Curry, Ahrens, Alanis, Arambula, Ávila Farías, Bains, Bauer-Kahan, Bennett, Boerner, Bonta, Bryan, Calderon, Caloza, Carrillo, Castillo, Chen, Connolly, Davies, Dixon, Elhawary, Ellis, Flora, Fong, Gabriel, Gallagher, Garcia, Gipson, Jeff Gonzalez, Mark González, Hadwick, Haney, Harabedian, Hart, Hoover, Irwin, Jackson, Kalra, Krell, Lackey, Lee, Lowenthal, Macedo, McKinnor, Muratsuchi, Nguyen, Ortega, Pacheco, Papan, Patel, Patterson, Pellerin, Petrie-Norris, Quirk-Silva, Ramos, Ransom, Celeste Rodriguez, Michelle Rodriguez, Rogers, Blanca Rubio, Sanchez, Schiavo, Schultz, Sharp-Collins, Solache, Soria, Stefani, Ta, Tangipa, Wallis, Ward, Wicks, Wilson, Zbur, Rivas
NOES: DeMaio
NO VOTE RECORDED: Alvarez, Berman, Valencia
Prepared by: Melissa White / TRANS. / (916) 651-4121
9/14/26 12:12:06
**** END ****
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 272 |
UNFINISHED BUSINESS
Bill No: SB 272
Author: Becker (D), et al.
Amended: 8/20/25 in Assembly
Vote: 21
SENATE TRANSPORTATION COMMITTEE: 14-0, 3/25/25
AYES: Cortese, Strickland, Archuleta, Arreguín, Blakespear, Cervantes, Gonzalez, Grayson, Limón, Menjivar, Richardson, Seyarto, Umberg, Valladares
NO VOTE RECORDED: Dahle
SENATE FLOOR: 39-0, 4/1/25 (Consent)
AYES: Allen, Alvarado-Gil, Archuleta, Arreguín, Ashby, Becker, Blakespear, Cabaldon, Caballero, Cervantes, Choi, Cortese, Dahle, Durazo, Gonzalez, Grayson, Grove, Hurtado, Jones, Laird, Limón, McGuire, McNerney, Menjivar, Niello, Ochoa Bogh, Padilla, Pérez, Richardson, Rubio, Seyarto, Smallwood-Cuevas, Stern, Strickland, Umberg, Valladares, Wahab, Weber Pierson, Wiener
NO VOTE RECORDED: Reyes
ASSEMBLY FLOOR: 75-1, 8/28/25 – See last page for vote
SUBJECT: San Mateo County Transit District: job order contracting: pilot program
SOURCE: San Mateo County Transit District
DIGEST:
This bill authorizes the San Mateo County Transit District (SamTrans) to enter into job order contracts (JOCs).
Assembly Amendments
of 8/20/25 were technical and added coauthors.
ANALYSIS:
Existing law requires, pursuant to the Local Agency Public Construction Act (LAPC Act), local officials to invite bids for construction projects and then award contracts to the lowest responsible bidder under the traditional design-bid-build project delivery system. Authorizes certain state and local agencies to enter into JOCs, including counties, school districts, community college districts, the California State University, the Santa Clara Valley Transportation Authority (VTA), the Los Angeles Metropolitan Transportation Agency (LA Metro) and the California Department of Transportation (Caltrans), as specified.
This bill:
- Authorizes SamTrans to use the procurement method outlined in this bill for JOCs.
- Prohibits SamTrans from contracting for work that is protected by applicable collective bargaining agreements. Requires all JOCs to comply with all SamTrans collective bargaining agreements.
- Requires JOCs of SamTrans to be competitively bid and awarded to bidders providing qualified responsive bids. Requires JOCs to be for construction that is repetitive, for repair or remodeling, to be done according to unit prices. Prohibits JOC annual contracts from being awarded for new construction.
- Requires JOCs to be subject to the project labor agreement (PLA) between SamTrans and the San Mateo Building Trades Council or an amendment or extension of that agreement.
- Specifies requirements for solicitations for JOCs to progress. Requires SamTrans to develop a system for evaluating JOC bids for award of JOCs. Specifies requirements for the award of a JOC to progress.
- Provides that the maximum total dollar amount that may be awarded under a single JOC shall not exceed $5 million dollars in the initial contract term of the JOC. No single job order may exceed $1 million.
- Provides that JOCs may be executed for a contract term of no more than 12 months and may be extended or renewed for two subsequent annual terms and a maximum of $10 million over the subsequent two terms of the contract. Prohibits work from being split or separated into smaller job orders for the purpose of evading the cost limitation provisions of this bill. Authorizes SamTrans to adjust the amounts in this bill to the California Consumer Price Index (CPI).
- Requires a JOC to set forth in the general conditions of the JOC the party or parties responsible for seeing that existing law governing prevailing wages on public works projects, Article 2 (commencing with Section 1770) of Chapter 1 of Part 7 of Division 2 of the Labor Code, is complied with.
- Requires, for purposes of job order contracting, prevailing wages to apply to all work ordered under the JOC regardless of thresholds set forth in Section 1771.5 of the Labor Code.
- Requires the job order contractor to pay the prevailing wage in effect at the time the job order is issued by SamTrans and all increases as published by the Department of Industrial Relations (DIR) for the term of the JOC, including all overtime, holiday, and shift provisions published by the DIR. Requires SamTrans to designate one individual to act as a monitor to inspect job sites for labor compliance violations at the request of the designated labor representative in its PLA.
- Requires, in order to prevent fraud, waste, and abuse, SamTrans to prepare for each individual job order developed under a JOC an independent cost estimate as specified. If SamTrans finds the job order contractor’s bid to perform work for a given job order to be unreasonable, not cost effective, or undesirable, SamTrans may elect not to issue the job order to the job order contractor, and may, instead, utilize any other available procurement procedures or choose not to move forward with the work.
- Requires SamTrans to submit to the appropriate policy and fiscal committees of the Legislature, on or before January 1, 2030, a report on the use of job order contracting under this bill, as specified.
- Provides a sunset date of January 1, 2032.
Comments
- Purpose of this bill. According to the author, “SB 272 provides the San Mateo County Transit District (SamTrans) with a proven, cost-effective procurement tool Job Order Contracting (JOC) to expedite small maintenance and repair projects while maintaining full compliance with public contracting laws. Other transit agencies, including LA Metro and VTA, already use JOC to streamline project delivery, reduce administrative burdens, and save taxpayer dollars. By authorizing a pilot program for SamTrans, this bill ensures that critical transit infrastructure can be maintained efficiently, improving service reliability and rider experience.”
- Who is SamTrans? SamTrans operates 76 bus routes throughout San Mateo County and into parts of San Francisco and Palo Alto. It began operating bus service in 1976 after consolidating 11 municipal transit services in the county into a coordinated network. In mid-1977, SamTrans inaugurated its mainline service from Palo Alto to San Francisco, previously operated by Greyhound.
Also in 1977, SamTrans initiated service for persons with mobility impairments through its Redi-Wheels program more than a decade before the passage of the Americans with Disabilities Act. The service, provided by Redi-Wheels on the bayside and RediCoast on the coastside, regularly provides more than 1,000 trips in a day. SamTrans also serves as the administrative body for Caltrain commuter rail and the San Mateo County Transportation Authority, who have contracted with SamTrans to serve as their managing agency, under the direction of their appointed boards.
- What is Job Order Contracting? A JOC is a competitively bid, fixed price, indefinite quantity contract for the performance of minor construction, as well as the renovation, alteration, painting, and repair of existing public facilities. A JOC is generally a multi-year contract that includes a base year and multiple "option years," and is awarded before the awarding agency has identified specific work that it needs the contractor to perform. A typical JOC involves a variety of tasks such as roofing, electrical work, plumbing, and painting that are required for all of a public agency's buildings for a period of years.
A JOC is a fixed price agreement in that it is based upon specified charges contained in a Unit Price Book (UPB), which is prepared by the public agency or by independent commercial sources. The UPB sets forth detailed repair and construction tasks, including task descriptions, specifications, units of measurement, and unit prices for each task. Unit price refers to the amount paid for a single unit of an item of work. A contractor's bid is expressed in terms of a percentage of the specified UPB charges. The UPB is then used to determine the costs of each proposed project during the term of the contract. As an example, if a procuring agency's per unit catalog price for an HVAC installation is $1,000, and a contractor submits a bid to do that work with an adjustment factor of 1.13, the contractor is agreeing to install the HVAC for $1,130.
The total JOC value may be specified as a range with a certain guaranteed minimum. The award of annual contracts on a unit price basis enables what would otherwise be multiple separately-bid projects to be combined into one bid. This contracting method is intended to reduce costs and accelerate completion of smaller projects. It is not generally viewed as an appropriate method of contracting for large, complex construction projects that require extensive or innovative design or are likely to encounter changes and revisions during construction. JOCs are typically used for well-defined, recurring or repetitive work where quick execution is essential, not for single larger projects.
- Job order contracting in California. The Legislature has authorized multiple agencies to use job order contracting, some state and some local, including counties, school districts, community college districts, and the California State University system. California counties have enjoyed the authority to use job order contracting since 1983. Counties may award annual JOCs of up to $3 million, adjusted annually to reflect the California CPI, to the lowest responsible bidder or using best value (for specified counties).
Additionally, as part of the 2021-2022 state budget, the Legislature authorized Caltrans to use JOC, but the authority was limited to the new Clean California Beautification Program. In 2023, as part of the Governor’s Infrastructure package Caltrans’ authority was expanded. SB 146 (Gonzalez, Chapter 58, Statutes of 2023), authorized Caltrans to use JOCs, through 2033, for general highway and traffic maintenance. Finally, the Legislature approved JOC authority for some regional transportation agencies including VTA in Santa Clara County, and most recently for LA Metro.
- SamTrans wants to join the party. SB 272 authorizes SamTrans to develop a process for and use JOCs. Specifically, this bill authorizes SamTrans to enter into JOCs on a competitive basis for construction that is repetitive, for repair, or for renovation or modification. The maximum total dollar amount that may be awarded under a single JOC shall not exceed $5 million dollars in the initial contract term, and no single job order may exceed $1 million. JOCs may be executed for a contract term of no more than 12 months and may be extended or renewed for two subsequent annual terms and a maximum of $10 million over the subsequent two terms of the contract. This bill also prohibits SamTrans from contracting for work that is protected by applicable collective bargaining agreements and requires all JOCs to comply with all SamTrans collective bargaining agreements. Finally, this bill requires SamTrans to submit to the appropriate policy and fiscal committees of the Legislature, on or before January 1, 2030, a report on its use of job order contracting, as specified; and provides a sunset date of January 1, 2032.
FISCAL EFFECT: Appropriation: No Fiscal Com.: No Local: No
SUPPORT: (Verified 8/28/25)
San Mateo County Transit District (Source)
American Society of Civil Engineers-Region 9
Sourcewell
OPPOSITION: (Verified 8/28/25)
None received
ARGUMENTS IN SUPPORT: According to SamTrans, “The District intends to use JOC for jobs like painting, bus shelter repairs, concrete/asphalt repairs, fencing repair and installation, lighting repairs, and elevator repair and rehabilitation. Implementation of JOC would also provide benefits to our local workers, including consistent work, predictable income, and reliable jobs for construction and building trades, including small and emerging contractors.
“As transit agencies across the state look for ways to reduce costs, enhance operations, and support the local economy, the District believes the use of JOC would advance these goals.”
Prepared by: Melissa White / TRANS. / (916) 651-4121
8/28/25 16:49:58
**** END ****
SENATE THIRD READING
STR Bill Id:SB 272
Author:(Becker)
As Amended Ver:August 20, 2025
Majority vote
SUMMARY
Authorizes the San Mateo County Transit District (SamTrans) to enter into job order contracts (JOCs).
Major Provisions
- Authorizes SamTrans to use the procurement method outlined in this bill for a JOC.
- Prohibits SamTrans from contracting for work that is protected by applicable collective bargaining agreements and requires all JOCs to comply with all SamTrans collective bargaining agreements.
- Requires JOCs to be competitively bid and awarded to bidders providing qualified responsive bids, and to be for construction that is repetitive, for repair or remodeling, to be done according to unit prices.
- Prohibits JOC annual contracts from being awarded for new construction.
- Requires JOCs to be subject to the project labor agreement (PLA) between SamTrans and the San Mateo Building Trades Council or an amendment or extension of that agreement.
- Specifies the solicitation and award process for JOCs and requires SamTrans to develop a system for evaluating JOC bids.
- Provides that the maximum total dollar amount that may be awarded under a single JOC shall not exceed $5 million dollars in the initial contract term of the JOC, and that no single job order may exceed $1 million.
- Provides that JOCs may be executed for a contract term of no more than 12 months and may be extended or renewed for two subsequent annual terms and a maximum of $10 million over the subsequent two terms of the contract.
- Prohibits work from being split or separated into smaller job orders for the purpose of evading the cost limitation provisions of this bill, and authorizes SamTrans to adjust the amounts in the bill to the California Consumer Price Index (CPI).
- Includes provisions related to prevailing wages, compliance with labor laws, and the prevention of fraud, waste and abuse, as specified.
- Requires SamTrans to submit to the appropriate policy and fiscal committees of the Legislature, on or before January 1, 2030, a report on the use of job order contracting under this bill, and specifies the contents of that report.
- Provides a sunset date of January 1, 2032.
COMMENTS
- Background. SamTrans operates 76 bus routes throughout San Mateo County and into parts of San Francisco and Palo Alto. It began operating bus service in 1976 after consolidating 11 municipal transit services in the county into a coordinated network. In mid-1977, SamTrans inaugurated its mainline service from Palo Alto to San Francisco, previously operated by Greyhound.
Also in 1977, SamTrans initiated service for persons with mobility impairments through its Redi-Wheels program more than a decade before the passage of the Americans with Disabilities Act. The service, provided by Redi-Wheels on the bayside and RediCoast on the coastside, regularly provides more than 1,000 trips in a day. SamTrans also serves as the administrative body for Caltrain commuter rail and the San Mateo County Transportation Authority, who have contracted with SamTrans to serve as their managing agency, under the direction of their appointed boards.
- Job Order Contracting. A JOC is a competitively bid, fixed price, indefinite quantity contract for the performance of minor construction, as well as the renovation, alteration, painting and repair of existing public facilities. A JOC is generally a multi-year contract that includes a base year and multiple "option years," and is awarded before the awarding agency has identified specific work that it needs the contractor to perform. A typical JOC involves a variety of tasks such as roofing, electrical work, plumbing and painting, that are required for all of a public agency's buildings for a period of years.
A JOC is a fixed price agreement in that it is based upon specified charges contained in a Unit Price Book (UPB), which is prepared by the public agency or by independent commercial sources. The UPB sets forth detailed repair and construction tasks, including task descriptions, specifications, units of measurement, and unit prices for each task ("Unit Price" means the amount paid for a single unit of an item of work). A contractor’s bid is expressed in terms of a percentage of the specified UPB charges. The UPB is then used to determine the costs of each proposed project during the term of the contract. As a an example, if a procuring agency’s per unit catalog price for an HVAC installation is $1,000, and a contractor submits a bid to do that work with an adjustment factor of 1.13, the contractor is agreeing to install the HVAC for $1,130.
The total JOC value may be specified as a range with a certain guaranteed minimum. The award of annual contracts on a unit price basis enables what would otherwise be multiple separately-bid projects to be combined into one bid. This contracting method is intended to reduce costs and accelerate completion of smaller projects. It is not generally viewed as an appropriate method of contracting for large, complex construction projects that require extensive or innovative design or are likely to encounter changes and revisions during construction. JOC are typically used for well-defined, recurring or repetitive work where quick execution is essential, not for single larger projects.
The Legislature has authorized multiple agencies to use JOC, some state and some local, including counties, school districts, community college districts, the California State University system, and Caltrans. California counties have enjoyed the authority to use JOC since 1983. Counties may award annual JOCs of up to $3 million, adjusted annually to reflect the California Consumer Price Index, to the lowest responsible bidder or using best value (for specified counties).
Additionally, as part of the 2021-2022 state budget, the Legislature authorized Caltrans to use JOC, but the authority was limited to the new Clean California Beautification Program. In 2023, as part of the Governor's Infrastructure package Caltrans' authority was expanded. SB 146 (Gonzalez), Chapter 58, Statutes of 2023, authorized Caltrans to use JOCs, through 2033, for general highway and traffic maintenance. Finally, the Legislature approved JOC authority for some regional transportation agencies including the Santa Clara Valley Transportation Authority and, most recently, for the Los Angeles County Metropolitan Transportation Authority (LA Metro).
According to the Author
SB 272 provides the San Mateo County Transit District (SamTrans) with a proven, cost-effective procurement tool Job Order Contracting (JOC) to expedite small maintenance and repair projects while maintaining full compliance with public contracting laws. Other transit agencies, including LA Metro and VTA, already use JOC to streamline project delivery, reduce administrative burdens, and save taxpayer dollars. By authorizing a pilot program for SamTrans, this bill ensures that critical transit infrastructure can be maintained efficiently, improving service reliability and rider experience.
Arguments in Support
SamTrans, sponsor of this bill, writes, "SamTrans is pleased to SPONSOR this important piece of legislation, which would authorize our agency to use Job Order Contracting (JOC), subject to the same standards applicable to other local transportation agencies using JOC and modeled after the authority recently established in AB 499 (Rivas, 2023). JOC is a competitively solicited, fixed-price contracting method used for small maintenance and repair work. JOC results in on-call construction service contracts under which public agencies issue work orders for specific jobs at pre-determined prices. JOC contracts can result in agencies saving time and staff resources when compared to typical bidding processes, allowing projects to begin faster than under traditional procurement methods.
"SB 272 would require consultation with local building trades and all work would be subject to a project labor agreement. SamTrans will use JOC to accelerate project delivery, reduce administrative costs, and lower direct construction costs while simultaneously meeting all federal, state, and local procurement requirements. SamTrans would use JOC for jobs like painting, bus shelter repairs, concrete/asphalt repairs, fencing repair and installation, lighting repairs, etc. JOC is not generally viewed as an appropriate method of contracting for large, complex construction projects that require extensive or innovative design, or that are likely to encounter changes and revisions during construction. As transit agencies across the state look for ways to reduce costs and enhance operations, SamTrans believes the use of JOC would support its efforts in this regard."
Arguments in Opposition
None on file.
FISCAL COMMENTS
None
VOTES
SENATE FLOOR: 39-0-1
YES: Allen, Alvarado-Gil, Archuleta, Arreguín, Ashby, Becker, Blakespear, Cabaldon, Caballero, Cervantes, Choi, Cortese, Dahle, Durazo, Gonzalez, Grayson, Grove, Hurtado, Jones, Laird, Limón, McGuire, McNerney, Menjivar, Niello, Ochoa Bogh, Padilla, Pérez, Richardson, Rubio, Seyarto, Smallwood-Cuevas, Stern, Strickland, Umberg, Valladares, Wahab, Weber Pierson, Wiener
ABS, ABST OR NV: Reyes
ASM LOCAL GOVERNMENT: 10-0-0
YES: Carrillo, Ta, Hoover, Pacheco, Ramos, Ransom, Blanca Rubio, Stefani, Haney, Wilson
UPDATED
VERSION: August 20, 2025
CONSULTANT: Angela Mapp / L. GOV. / (916) 319-3958 FN: 0001182
SENATE THIRD READING
STR Bill Id:SB 272
Author:(Becker)
As Amended Ver:March 18, 2025
Majority vote
SUMMARY
Authorizes the San Mateo County Transit District (SamTrans) to enter into job order contracts (JOCs).
Major Provisions
- Authorizes SamTrans to use the procurement method outlined in this bill for JOCs.
- Prohibits SamTrans from contracting for work that is protected by applicable collective bargaining agreements and requires all JOCs to comply with all SamTrans collective bargaining agreements.
- Requires JOCs to be competitively bid and awarded to bidders providing qualified responsive bids, and to be for construction that is repetitive, for repair or remodeling, to be done according to unit prices.
- Prohibits JOC annual contracts from being awarded for new construction.
- Requires JOCs to be subject to the project labor agreement (PLA) between SamTrans and the San Mateo Building Trades Council or an amendment or extension of that agreement.
- Specifies the solicitation and award process for JOCs and requires SamTrans to develop a system for evaluating JOC bids.
- Provides that the maximum total dollar amount that may be awarded under a single JOC shall not exceed $5 million dollars in the initial contract term of the JOC, and that no single job order may exceed $1 million.
- Provides that JOCs may be executed for a contract term of no more than 12 months and may be extended or renewed for two subsequent annual terms and a maximum of $10 million over the subsequent two terms of the contract.
- Prohibits work from being split or separated into smaller job orders for the purpose of evading the cost limitation provisions of this bill, and authorizes SamTrans to adjust the amounts in the bill to the California Consumer Price Index (CPI).
- Includes provisions related to prevailing wages, compliance with labor laws, and the prevention of fraud, waste and abuse, as specified.
- Requires SamTrans to submit to the appropriate policy and fiscal committees of the Legislature, on or before January 1, 2030, a report on the use of job order contracting under this bill, and specifies the contents of that report.
- Provides a sunset date of January 1, 2032.
COMMENTS
- Background. SamTrans operates 76 bus routes throughout San Mateo County and into parts of San Francisco and Palo Alto. It began operating bus service in 1976 after consolidating 11 municipal transit services in the county into a coordinated network. In mid-1977, SamTrans inaugurated its mainline service from Palo Alto to San Francisco, previously operated by Greyhound.
Also in 1977, SamTrans initiated service for persons with mobility impairments through its Redi-Wheels program more than a decade before the passage of the Americans with Disabilities Act. The service, provided by Redi-Wheels on the bayside and RediCoast on the coastside, regularly provides more than 1,000 trips in a day. SamTrans also serves as the administrative body for Caltrain commuter rail and the San Mateo County Transportation Authority, who have contracted with SamTrans to serve as their managing agency, under the direction of their appointed boards.
- Job Order Contracting. A JOC is a competitively bid, fixed price, indefinite quantity contract for the performance of minor construction, as well as the renovation, alteration, painting and repair of existing public facilities. A JOC is generally a multi-year contract that includes a base year and multiple "option years," and is awarded before the awarding agency has identified specific work that it needs the contractor to perform. A typical JOC involves a variety of tasks such as roofing, electrical work, plumbing and painting, that are required for all of a public agency's buildings for a period of years.
A JOC is a fixed price agreement in that it is based upon specified charges contained in a Unit Price Book (UPB), which is prepared by the public agency or by independent commercial sources. The UPB sets forth detailed repair and construction tasks, including task descriptions, specifications, units of measurement, and unit prices for each task ("Unit Price" means the amount paid for a single unit of an item of work). A contractor’s bid is expressed in terms of a percentage of the specified UPB charges. The UPB is then used to determine the costs of each proposed project during the term of the contract. As a an example, if a procuring agency’s per unit catalog price for an HVAC installation is $1,000, and a contractor submits a bid to do that work with an adjustment factor of 1.13, the contractor is agreeing to install the HVAC for $1,130.
The total JOC value may be specified as a range with a certain guaranteed minimum. The award of annual contracts on a unit price basis enables what would otherwise be multiple separately-bid projects to be combined into one bid. This contracting method is intended to reduce costs and accelerate completion of smaller projects. It is not generally viewed as an appropriate method of contracting for large, complex construction projects that require extensive or innovative design or are likely to encounter changes and revisions during construction. JOC are typically used for well-defined, recurring or repetitive work where quick execution is essential, not for single larger projects.
The Legislature has authorized multiple agencies to use JOC, some state and some local, including counties, school districts, community college districts, the California State University system, and Caltrans. California counties have enjoyed the authority to use JOC since 1983. Counties may award annual JOCs of up to $3 million, adjusted annually to reflect the California Consumer Price Index, to the lowest responsible bidder or using best value (for specified counties).
Additionally, as part of the 2021-2022 state budget, the Legislature authorized Caltrans to use JOC, but the authority was limited to the new Clean California Beautification Program. In 2023, as part of the Governor's Infrastructure package Caltrans' authority was expanded. SB 146 (Gonzalez), Chapter 58, Statutes of 2023, authorized Caltrans to use JOCs, through 2033, for general highway and traffic maintenance. Finally, the Legislature approved JOC authority for some regional transportation agencies including the Santa Clara Valley Transportation Authority and, most recently, for the Los Angeles County Metropolitan Transportation Authority (LA Metro).
According to the Author
SB 272 provides the San Mateo County Transit District (SamTrans) with a proven, cost-effective procurement tool Job Order Contracting (JOC) to expedite small maintenance and repair projects while maintaining full compliance with public contracting laws. Other transit agencies, including LA Metro and VTA, already use JOC to streamline project delivery, reduce administrative burdens, and save taxpayer dollars. By authorizing a pilot program for SamTrans, this bill ensures that critical transit infrastructure can be maintained efficiently, improving service reliability and rider experience.
Arguments in Support
SamTrans, sponsor of this bill, writes, "SamTrans is pleased to SPONSOR this important piece of legislation, which would authorize our agency to use Job Order Contracting (JOC), subject to the same standards applicable to other local transportation agencies using JOC and modeled after the authority recently established in AB 499 (Rivas, 2023). JOC is a competitively solicited, fixed-price contracting method used for small maintenance and repair work. JOC results in on-call construction service contracts under which public agencies issue work orders for specific jobs at pre-determined prices. JOC contracts can result in agencies saving time and staff resources when compared to typical bidding processes, allowing projects to begin faster than under traditional procurement methods.
"SB 272 would require consultation with local building trades and all work would be subject to a project labor agreement. SamTrans will use JOC to accelerate project delivery, reduce administrative costs, and lower direct construction costs while simultaneously meeting all federal, state, and local procurement requirements. SamTrans would use JOC for jobs like painting, bus shelter repairs, concrete/asphalt repairs, fencing repair and installation, lighting repairs, etc. JOC is not generally viewed as an appropriate method of contracting for large, complex construction projects that require extensive or innovative design, or that are likely to encounter changes and revisions during construction. As transit agencies across the state look for ways to reduce costs and enhance operations, SamTrans believes the use of JOC would support its efforts in this regard."
Arguments in Opposition
None on file.
FISCAL COMMENTS
None
VOTES
SENATE FLOOR: 39-0-1
YES: Allen, Alvarado-Gil, Archuleta, Arreguín, Ashby, Becker, Blakespear, Cabaldon, Caballero, Cervantes, Choi, Cortese, Dahle, Durazo, Gonzalez, Grayson, Grove, Hurtado, Jones, Laird, Limón, McGuire, McNerney, Menjivar, Niello, Ochoa Bogh, Padilla, Pérez, Richardson, Rubio, Seyarto, Smallwood-Cuevas, Stern, Strickland, Umberg, Valladares, Wahab, Weber Pierson, Wiener
ABS, ABST OR NV: Reyes
ASM LOCAL GOVERNMENT: 10-0-0
YES: Carrillo, Ta, Hoover, Pacheco, Ramos, Ransom, Blanca Rubio, Stefani, Haney, Wilson
UPDATED
VERSION: March 18, 2025
CONSULTANT: Angela Mapp / L. GOV. / (916) 319-3958 FN: 0000992
Date of Hearing: June 18, 2025
ASSEMBLY COMMITTEE ON LOCAL GOVERNMENT
Juan Carrillo, Chair
SBPCA Bill Id:SB 272
Author:(Becker) – As Amended Ver:March 18, 2025
SENATE VOTE: 39-0
SUBJECT: San Mateo County Transit District: job order contracting: pilot program.
SUMMARY: Authorizes the San Mateo County Transit District (SamTrans) to enter into job order contracts (JOCs). Specifically, this bill:
- Authorizes SamTrans to use the procurement method outlined in this bill for JOCs.
- Prohibits SamTrans from contracting for work that is protected by applicable collective bargaining agreements. Requires all JOCs to comply with all SamTrans collective bargaining agreements.
- Requires JOCs of SamTrans to be competitively bid and awarded to bidders providing qualified responsive bids.
- Requires JOCs to be for construction that is repetitive, for repair or remodeling, to be done according to unit prices.
- Prohibits JOC annual contracts from being awarded for new construction.
- Requires JOCs to be subject to the project labor agreement (PLA) between SamTrans and the San Mateo Building Trades Council or an amendment or extension of that agreement.
- Requires solicitations for JOCs to progress as follows:
- SamTrans shall prepare a set of solicitation documents for JOCs. The documents shall include a unit price catalog or other established unit prices, JOC terms, JOC technical specifications, and any other information SamTrans deems necessary to adequately describe SamTrans’ needs.
- An architect, engineer, consultant, or contractor retained by SamTrans to assist in the development of the JOC solicitation documents shall not be eligible to bid or to participate in the preparation of a JOC bid.
- SamTrans may award multiple JOCs in response to a single JOC solicitation.
- Requires SamTrans to develop a system for evaluating JOC bids for award of JOCs.
- Requires the award of a JOC to progress as follows:
- SamTrans shall prepare a request for bids for specific job orders based on the solicitation documents prepared under the solicitation process that invites job order contractors to submit sealed bids in the manner prescribed by SamTrans.
- Each bidding job order contractor shall include in its bid one or more adjustment factors to the established unit prices provided in the request for bids based on the contract technical specifications.
- The job order contractor’s bids for job orders shall identify any subcontractors to be used for the performance of the JOC.
- The award of the JOC, if any, shall be made to a job order contractor or to job order contractors that SamTrans determines to be qualified and responsive based upon pre-established criteria to be determined by SamTrans. However, SamTrans, by a process determined by SamTrans, may award any job order for repair or renovation work with a value equal to or less than $250,000 to a job order contractor that is also a certified small business enterprise (SBE), as established by SamTrans’ SBE certification process or any similar certification process acceptable to SamTrans, or to a job order contractor that is also a disabled veterans business enterprise (DVBE), as certified by the Department of General Services (DGS).
- The job order contractors shall comply with SamTrans’ PLA, as applicable.
- Provides that the maximum total dollar amount that may be awarded under a single JOC shall not exceed $5 million dollars in the initial contract term of the JOC. No single job order may exceed $1 million.
- Provides that JOCs may be executed for a contract term of no more than 12 months and may be extended or renewed for two subsequent annual terms and a maximum of $10 million over the subsequent two terms of the contract.
- Prohibits work from being split or separated into smaller job orders for the purpose of evading the cost limitation provisions of this bill.
- Authorizes SamTrans to adjust the amounts in the bill to the California Consumer Price Index (CPI).
- Requires a JOC to set forth in the general conditions of the JOC the party or parties responsible for seeing that existing law governing prevailing wages on public works projects, Article 2 (commencing with Section 1770) of Chapter 1 of Part 7 of Division 2 of the Labor Code, is complied with.
- Requires, for purposes of job order contracting, prevailing wages to apply to all work ordered under the JOC regardless of thresholds set forth in Section 1771.5 of the Labor Code.
- Requires the job order contractor to pay the prevailing wage in effect at the time the job order is issued by SamTrans and all increases as published by the Department of Industrial Relations (DIR) for the term of the JOC, including all overtime, holiday, and shift provisions published by the DIR.
- Requires SamTrans to designate one individual to act as a monitor to inspect job sites for labor compliance violations at the request of the designated labor representative in its PLA.
- Requires, in order to prevent fraud, waste, and abuse, SamTrans to prepare for each individual job order developed under a JOC an independent cost estimate. The estimate shall be prepared prior to the receipt of any job order contractor’s bid for the work and shall be compared to the job order contractor’s bid price to determine the reasonableness of that price before issuance of any job order. If SamTrans finds the job order contractor’s bid to perform work for a given job order to be unreasonable, not cost effective, or undesirable, SamTrans may elect not to issue the job order to the job order contractor, and may, instead, utilize any other available procurement procedures or choose not to move forward with the work.
- Requires SamTrans to submit to the appropriate policy and fiscal committees of the Legislature, on or before January 1, 2030, a report on the use of job order contracting under this bill. The report shall include, but shall not be limited to, all of the following information:
- A description of SamTrans’ system for evaluating JOC bids for award of JOCs, including, but not limited to, the criteria used by SamTrans to determine a qualified and responsive job order contractor.
- A description of each JOC awarded and the contractor awarded the contract.
- An assessment of the use of job order contracting under this bill.
- Provides a sunset date of January 1, 2032.
- Finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the need for a pilot program to determine the potential benefits of job order contracting to a large transportation agency without setting policy for smaller local agencies.
FISCAL EFFECT: None
COMMENTS:
- Author’s Statement. According to the author, “SB 272 provides the San Mateo County Transit District (SamTrans) with a proven, cost-effective procurement tool Job Order Contracting (JOC) to expedite small maintenance and repair projects while maintaining full compliance with public contracting laws. Other transit agencies, including LA Metro and VTA, already use JOC to streamline project delivery, reduce administrative burdens, and save taxpayer dollars. By authorizing a pilot program for SamTrans, this bill ensures that critical transit infrastructure can be maintained efficiently, improving service reliability and rider experience.”
- Background. SamTrans operates 76 bus routes throughout San Mateo County and into parts of San Francisco and Palo Alto. It began operating bus service in 1976 after consolidating 11 municipal transit services in the county into a coordinated network. In mid-1977, SamTrans inaugurated its mainline service from Palo Alto to San Francisco, previously operated by Greyhound.
Also in 1977, SamTrans initiated service for persons with mobility impairments through its Redi-Wheels program more than a decade before the passage of the Americans with Disabilities Act. The service, provided by Redi-Wheels on the bayside and RediCoast on the coastside, regularly provides more than 1,000 trips in a day. SamTrans also serves as the administrative body for Caltrain commuter rail and the San Mateo County Transportation Authority, who have contracted with SamTrans to serve as their managing agency, under the direction of their appointed boards.
- Job Order Contracting. A JOC is a competitively bid, fixed price, indefinite quantity contract for the performance of minor construction, as well as the renovation, alteration, painting and repair of existing public facilities. A JOC is generally a multi-year contract that includes a base year and multiple “option years,” and is awarded before the awarding agency has identified specific work that it needs the contractor to perform. A typical JOC involves a variety of tasks such as roofing, electrical work, plumbing and painting, that are required for all of a public agency’s buildings for a period of years.
A JOC is a fixed price agreement in that it is based upon specified charges contained in a Unit Price Book (UPB), which is prepared by the public agency or by independent commercial sources. The UPB sets forth detailed repair and construction tasks, including task descriptions, specifications, units of measurement, and unit prices for each task (“Unit Price” means the amount paid for a single unit of an item of work). A contractor’s bid is expressed in terms of a percentage of the specified UPB charges. The UPB is then used to determine the costs of each proposed project during the term of the contract. As a an example, if a procuring agency’s per unit catalog price for an HVAC installation is $1,000, and a contractor submits a bid to do that work with an adjustment factor of 1.13, the contractor is agreeing to install the HVAC for $1,130.
The total JOC value may be specified as a range with a certain guaranteed minimum. The award of annual contracts on a unit price basis enables what would otherwise be multiple separately-bid projects to be combined into one bid. This contracting method is intended to reduce costs and accelerate completion of smaller projects. It is not generally viewed as an appropriate method of contracting for large, complex construction projects that require extensive or innovative design or are likely to encounter changes and revisions during construction. JOC are typically used for well-defined, recurring or repetitive work where quick execution is essential, not for single larger projects.
The Legislature has authorized multiple agencies to use JOC, some state and some local, including counties, school districts, community college districts, the California State University system, and Caltrans. California counties have enjoyed the authority to use JOC since 1983. Counties may award annual JOCs of up to $3 million, adjusted annually to reflect the California Consumer Price Index, to the lowest responsible bidder or using best value (for specified counties).
Additionally, as part of the 2021-2022 state budget, the Legislature authorized Caltrans to use JOC, but the authority was limited to the new Clean California Beautification Program. In 2023, as part of the Governor’s Infrastructure package Caltrans’ authority was expanded. SB 146 (Gonzalez), Chapter 58, Statutes of 2023, authorized Caltrans to use JOCs, through 2033, for general highway and traffic maintenance. Finally, the Legislature approved JOC authority for some regional transportation agencies including the Santa Clara Valley Transportation Authority and, most recently, for the Los Angeles County Metropolitan Transportation Authority (LA Metro).
- Bill Summary. This bill authorizes SamTrans to enter into JOCs on a competitive basis for repair, remodeling, or other repetitive work according to unit prices. This bill prohibits JOCs from being awarded for any new construction.
The maximum total dollar amount that may be awarded under a single JOC shall not exceed $5 million dollars in the initial contract term, and no single job order may exceed $1 million. JOCs may be executed for an initial contract term of no more than 12 months and may be extended or renewed for two subsequent annual terms totaling a maximum of $10 million.
This bill prohibits SamTrans from contracting for work that is protected by applicable collective bargaining agreements, requires all JOCs to comply with all SamTrans collective bargaining agreements, and requires JOCs to be subject to a PLA between SamTrans and the San Mateo Building Trades Council, as specified.
This bill also provides for specified subcontracting practices, the payment of prevailing wages, and labor compliance consistent with existing law, as specified. The bill also outlines the process for SamTrans to follow in soliciting and awarding JOCs, including the ability to award job orders of $250,000 or less to SBE or DVBE contractors.
This bill requires SamTrans to submit to the appropriate policy and fiscal committees of the Legislature, on or before January 1, 2030, a report on its use of job order contracting, as specified. This bill provides a sunset date of January 1, 2032.
This bill is sponsored by SamTrans.
- Previous Legislation. AB 499 (Luz Rivas), Chapter 87, Statutes of 2023, authorized LA Metro to enter into job order contracts JOCs.
SB 146 (Gonzalez), Chapter 58, Statutes of 2023, expanded Caltrans authorization to use JOCs, through 2033, for general highway and traffic maintenance.
AB 2039 (Luz Rivas) of 2022 was nearly identical to AB 499. AB 2039 was held in the Senate Transportation Committee.
AB 2763 (Kalra), Chapter 803, Statutes of 2022, authorized the Santa Clara Valley Transportation Authority to enter into JOCs.
SB 1366 (McGuire) of 2022 would have authorized DGS to engage in job order contracting for certain public works projects, until July 1, 2027. SB 1366 was held on the Senate Floor.
AB 149 (Committee on Budget), Chapter 81, Statutes of 2021, among other things, authorized Caltrans to utilize job order contracting for the Clean California Beautification Program of 2021, as specified.
AB 846 (Low), Chapter 303, Statutes of 2021, extended the existing authority for school and community college districts to administer job order contracting, until January 1, 2027.
AB 618 (Low), Chapter 296, Statutes of 2017, authorized community college districts to enter into JOCs, until January 1, 2022.
SB 793 (Hill), Chapter 627, Statutes of 2017, allowed specified counties to use the best value construction contracting method to award JOCs for up to $3 million, adjusted for inflation.
AB 1431 (Gomez), Chapter 753, Statutes of 2015, authorized school districts to utilize job order contracting.
SB 744 (Hughes), Chapter 431, Statutes of 1997, increased the annual maximum contract amount that counties may award for county JOCs from $1 million to $3 million.
AB 680 (La Follette), Chapter 164, Statutes of 1983, authorized counties to award annual JOCs of up to $1 million.
- Arguments in Support. SamTrans, sponsor of this bill, writes, “SamTrans is pleased to SPONSOR this important piece of legislation, which would authorize our agency to use Job Order Contracting (JOC), subject to the same standards applicable to other local transportation agencies using JOC and modeled after the authority recently established in AB 499 (Rivas, 2023). JOC is a competitively solicited, fixed-price contracting method used for small maintenance and repair work. JOC results in on-call construction service contracts under which public agencies issue work orders for specific jobs at pre-determined prices. JOC contracts can result in agencies saving time and staff resources when compared to typical bidding processes, allowing projects to begin faster than under traditional procurement methods.
“SB 272 would require consultation with local building trades and all work would be subject to a project labor agreement. SamTrans will use JOC to accelerate project delivery, reduce administrative costs, and lower direct construction costs while simultaneously meeting all federal, state, and local procurement requirements. SamTrans would use JOC for jobs like painting, bus shelter repairs, concrete/asphalt repairs, fencing repair and installation, lighting repairs, etc. JOC is not generally viewed as an appropriate method of contracting for large, complex construction projects that require extensive or innovative design, or that are likely to encounter changes and revisions during construction. As transit agencies across the state look for ways to reduce costs and enhance operations, SamTrans believes the use of JOC would support its efforts in this regard.”
- Arguments in Opposition. None on file.
REGISTERED SUPPORT / OPPOSITION:
Support
San Mateo County Transit District [SPONSOR]
Sourcewell
Opposition
None on file
Analysis Prepared by: Angela Mapp / L. GOV. / (916) 319-3958
SENATE RULES COMMITTEE Office of Senate Floor Analyses (916) 651-1520 Fax: (916) 327-4478 | SB 272 |
CONSENT
Bill No: SB 272
Author: Becker (D)
Amended: 3/18/25
Vote: 21
SENATE TRANSPORTATION COMMITTEE: 14-0, 3/25/25
AYES: Cortese, Strickland, Archuleta, Arreguín, Blakespear, Cervantes, Gonzalez, Grayson, Limón, Menjivar, Richardson, Seyarto, Umberg, Valladares
NO VOTE RECORDED: Dahle
SUBJECT: San Mateo County Transit District: job order contracting: pilot program
SOURCE: San Mateo County Transit District
DIGEST:
This bill authorizes the San Mateo County Transit District (SamTrans) to enter into job order contracts (JOCs).
ANALYSIS:
Existing law requires, pursuant to the Local Agency Public Construction Act, local officials to invite bids for construction projects and then award contracts to the lowest responsible bidder under the traditional design-bid-build project delivery system. Authorizes certain state and local agencies to enter into JOCs, including counties, school districts, community college districts, the California State University, the Santa Clara Valley Transportation Authority (VTA), the Los Angeles Metropolitan Transportation Agency (LA Metro) and the California Department of Transportation (Caltrans), as specified.
This bill:
- Authorizes SamTrans to use the procurement method outlined in this bill for JOCs.
- Prohibits SamTrans from contracting for work that is protected by applicable collective bargaining agreements. Requires all JOCs to comply with all SamTrans collective bargaining agreements.
- Requires JOCs of SamTrans to be competitively bid and awarded to bidders providing qualified responsive bids. Requires JOCs to be for construction that is repetitive, for repair or remodeling, to be done according to unit prices. Prohibits JOC annual contracts from being awarded for new construction.
- Requires JOCs to be subject to the project labor agreement (PLA) between SamTrans and the San Mateo Building Trades Council or an amendment or extension of that agreement.
- Specifies requirements for solicitations for JOCs to progress. Requires SamTrans to develop a system for evaluating JOC bids for award of JOCs. Specifies requirements for the award of a JOC to progress.
- Provides that the maximum total dollar amount that may be awarded under a single JOC shall not exceed $5 million dollars in the initial contract term of the JOC. No single job order may exceed $1 million.
- Provides that JOCs may be executed for a contract term of no more than 12 months and may be extended or renewed for two subsequent annual terms and a maximum of $10 million over the subsequent two terms of the contract. Prohibits work from being split or separated into smaller job orders for the purpose of evading the cost limitation provisions of this bill. Authorizes SamTrans to adjust the amounts in the bill to the California Consumer Price Index (CPI).
- Requires a JOC to set forth in the general conditions of the JOC the party or parties responsible for seeing that existing law governing prevailing wages on public works projects, Article 2 (commencing with Section 1770) of Chapter 1 of Part 7 of Division 2 of the Labor Code, is complied with.
- Requires, for purposes of job order contracting, prevailing wages to apply to all work ordered under the JOC regardless of thresholds set forth in Section 1771.5 of the Labor Code.
- Requires the job order contractor to pay the prevailing wage in effect at the time the job order is issued by SamTrans and all increases as published by the Department of Industrial Relations (DIR) for the term of the JOC, including all overtime, holiday, and shift provisions published by the DIR. Requires SamTrans to designate one individual to act as a monitor to inspect job sites for labor compliance violations at the request of the designated labor representative in its PLA.
- Requires, in order to prevent fraud, waste, and abuse, SamTrans to prepare for each individual job order developed under a JOC an independent cost estimate as specified. If SamTrans finds the job order contractor’s bid to perform work for a given job order to be unreasonable, not cost effective, or undesirable, SamTrans may elect not to issue the job order to the job order contractor, and may, instead, utilize any other available procurement procedures or choose not to move forward with the work.
- Requires SamTrans to submit to the appropriate policy and fiscal committees of the Legislature, on or before January 1, 2030, a report on the use of job order contracting under this bill, as specified.
- Provides a sunset date of January 1, 2032.
Comments
- Purpose of the bill. According to the author, “SB 272 provides the SamTrans with a proven, cost-effective procurement tool Job Order Contracting (JOC) to expedite small maintenance and repair projects while maintaining full compliance with public contracting laws. Other transit agencies, including LA Metro and VTA, already use JOC to streamline project delivery, reduce administrative burdens, and save taxpayer dollars. By authorizing a pilot program for SamTrans, this bill ensures that critical transit infrastructure can be maintained efficiently, improving service reliability and rider experience.”
- Who is SamTrans? SamTrans operates 76 bus routes throughout San Mateo County and into parts of San Francisco and Palo Alto. It began operating bus service in 1976 after consolidating 11 municipal transit services in the county into a coordinated network. In mid-1977, SamTrans inaugurated its mainline service from Palo Alto to San Francisco, previously operated by Greyhound.
Also in 1977, SamTrans initiated service for persons with mobility impairments through its Redi-Wheels program more than a decade before the passage of the Americans with Disabilities Act. The service, provided by Redi-Wheels on the bayside and RediCoast on the coastside, regularly provides more than 1,000 trips in a day. SamTrans also serves as the administrative body for Caltrain commuter rail and the San Mateo County Transportation Authority, who have contracted with SamTrans to serve as their managing agency, under the direction of their appointed boards.
- What is Job Order Contracting? A JOC is a competitively bid, fixed price, indefinite quantity contract for the performance of minor construction, as well as the renovation, alteration, painting, and repair of existing public facilities. A JOC is generally a multi-year contract that includes a base year and multiple "option years," and is awarded before the awarding agency has identified specific work that it needs the contractor to perform. A typical JOC involves a variety of tasks such as roofing, electrical work, plumbing, and painting that are required for all of a public agency's buildings for a period of years.
A JOC is a fixed price agreement in that it is based upon specified charges contained in a Unit Price Book (UPB), which is prepared by the public agency or by independent commercial sources. The UPB sets forth detailed repair and construction tasks, including task descriptions, specifications, units of measurement, and unit prices for each task. Unit price refers to the amount paid for a single unit of an item of work. A contractor's bid is expressed in terms of a percentage of the specified UPB charges. The UPB is then used to determine the costs of each proposed project during the term of the contract. As an example, if a procuring agency's per unit catalog price for and heating, ventilation, and air conditioning (HVAC) installation is $1,000, and a contractor submits a bid to do that work with an adjustment factor of 1.13, the contractor is agreeing to install the HVAC for $1,130.
The total JOC value may be specified as a range with a certain guaranteed minimum. The award of annual contracts on a unit price basis enables what would otherwise be multiple separately-bid projects to be combined into one bid. This contracting method is intended to reduce costs and accelerate completion of smaller projects. It is not generally viewed as an appropriate method of contracting for large, complex construction projects that require extensive or innovative design or are likely to encounter changes and revisions during construction. JOCs are typically used for well-defined, recurring or repetitive work where quick execution is essential, not for single larger projects.
- Job order contracting in California. The Legislature has authorized multiple agencies to use job order contracting, some state and some local, including counties, school districts, community college districts, and the California State University system. California counties have enjoyed the authority to use job order contracting since 1983. Counties may award annual JOCs of up to $3 million, adjusted annually to reflect the California CPI, to the lowest responsible bidder or using best value (for specified counties).
Additionally, as part of the 2021-2022 state budget, the Legislature authorized Caltrans to use JOC, but the authority was limited to the new Clean California Beautification Program. In 2023, as part of the Governor’s Infrastructure package Caltrans’ authority was expanded. SB 146 (Gonzalez, Chapter 58, Statutes of 2023), authorized Caltrans to use JOCs, through 2033, for general highway and traffic maintenance. Finally, the Legislature approved JOC authority for some regional transportation agencies including VTA in Santa Clara County, and most recently for LA Metro.
- SamTrans wants to join the party. SB 272 authorizes SamTrans to develop a process for and use JOCs. Specifically, this bill authorizes SamTrans to enter into JOCs on a competitive basis for construction that is repetitive, for repair, or for renovation or modification. The maximum total dollar amount that may be awarded under a single JOC shall not exceed $5 million dollars in the initial contract term, and no single job order may exceed $1 million. JOCs may be executed for a contract term of no more than 12 months and may be extended or renewed for two subsequent annual terms and a maximum of $10 million over the subsequent two terms of the contract. This bill also prohibits SamTrans from contracting for work that is protected by applicable collective bargaining agreements and requires all JOCs to comply with all SamTrans collective bargaining agreements. Finally, this bill requires SamTrans to submit to the appropriate policy and fiscal committees of the Legislature, on or before January 1, 2030, a report on its use of job order contracting, as specified; and provides a sunset date of January 1, 2032.
FISCAL EFFECT: Appropriation: No Fiscal Com.: No Local: No
SUPPORT: (Verified 3/27/25)
San Mateo County Transit District
Sourcewell
OPPOSITION: (Verified 3/27/25)
None received
ARGUMENTS IN SUPPORT: According to SamTrans, “The District intends to use JOC for jobs like painting, bus shelter repairs, concrete/asphalt repairs, fencing repair and installation, lighting repairs, and elevator repair and rehabilitation. Implementation of JOC would also provide benefits to our local workers, including consistent work, predictable income, and reliable jobs for construction and building trades, including small and emerging contractors.
“As transit agencies across the state look for ways to reduce costs, enhance operations, and support the local economy, the District believes the use of JOC would advance these goals.”
Prepared by: Melissa White / TRANS. / (916) 651-4121
3/27/25 15:58:01
**** END ****
SENATE COMMITTEE ON TRANSPORTATION
Senator Dave Cortese, Chair
2025 - 2026 Regular
Bill No: SB 272 Hearing Date: 3/25/2025
Author: | Becker | ||
Version: | 3/18/2025 Amended | ||
Urgency: | No | Fiscal: | No |
Consultant: | Melissa White | ||
SUBJECT: San Mateo County Transit District: job order contracting: pilot program
DIGEST: This bill authorizes the San Mateo County Transit District (SamTrans) to enter into job order contracts (JOCs).
ANALYSIS:
Existing law:
- Requires, pursuant to the Local Agency Public Construction Act (LAPC Act), local officials to invite bids for construction projects and then award contracts to the lowest responsible bidder under the traditional design-bid-build project delivery system.
- Authorizes certain state and local agencies to enter into JOCs, including counties, school districts, community college districts, the California State University, the Santa Clara Valley Transportation Authority (VTA), the Los Angeles Metropolitan Transportation Agency (LA Metro) and the California Department of Transportation (Caltrans), as specified.
This bill:
- Authorizes SamTrans to use the procurement method outlined in this bill for JOCs.
- Prohibits SamTrans from contracting for work that is protected by applicable collective bargaining agreements. Requires all JOCs to comply with all SamTrans collective bargaining agreements.
- Requires JOCs of SamTrans to be competitively bid and awarded to bidders providing qualified responsive bids.
- Requires JOCs to be for construction that is repetitive, for repair or remodeling, to be done according to unit prices.
- Prohibits JOC annual contracts from being awarded for new construction.
- Requires JOCs to be subject to the project labor agreement (PLA) between SamTrans and the San Mateo Building Trades Council or an amendment or extension of that agreement.
- Requires solicitations for JOCs to progress as follows:
- SamTrans shall prepare a set of solicitation documents for JOCs. The documents shall include a unit price catalog or other established unit prices, JOC terms, JOC technical specifications, and any other information SamTrans deems necessary to adequately describe SamTrans’ needs.
- An architect, engineer, consultant, or contractor retained by SamTrans to assist in the development of the JOC solicitation documents shall not be eligible to bid or to participate in the preparation of a JOC bid.
- SamTrans may award multiple JOCs in response to a single JOC solicitation.
- Requires SamTrans to develop a system for evaluating JOC bids for award of JOCs.
- Requires the award of a JOC to progress as follows:
- SamTrans shall prepare a request for bids for specific job orders based on the solicitation documents prepared under the solicitation process that invites job order contractors to submit sealed bids in the manner prescribed by SamTrans.
- Each bidding job order contractor shall include in its bid one or more adjustment factors to the established unit prices provided in the request for bids based on the contract technical specifications.
- The job order contractor’s bids for job orders shall identify any subcontractors to be used for the performance of the JOC.
- The award of the JOC, if any, shall be made to a job order contractor or to job order contractors that SamTrans determines to be qualified and responsive based upon pre-established criteria to be determined by SamTrans. However, SamTrans, by a process determined by SamTrans, may award any job order for repair or renovation work with a value equal to or less than $250,000 to a job order contractor that is also a certified small business enterprise (SBE), as established by SamTrans’ SBE certification process or any similar certification process acceptable to SamTrans, or to a job order contractor that is also a disabled veterans business enterprise (DVBE), as certified by the Department of General Services (DGS).
- The job order contractors shall comply with SamTrans’ PLA, as applicable.
- Provides that the maximum total dollar amount that may be awarded under a single JOC shall not exceed $5 million dollars in the initial contract term of the JOC. No single job order may exceed $1 million.
- Provides that JOCs may be executed for a contract term of no more than 12 months and may be extended or renewed for two subsequent annual terms and a maximum of $10 million over the subsequent two terms of the contract.
- Prohibits work from being split or separated into smaller job orders for the purpose of evading the cost limitation provisions of this bill.
- Authorizes SamTrans to adjust the amounts in the bill to the California Consumer Price Index (CPI).
- Requires a JOC to set forth in the general conditions of the JOC the party or parties responsible for seeing that existing law governing prevailing wages on public works projects, Article 2 (commencing with Section 1770) of Chapter 1 of Part 7 of Division 2 of the Labor Code, is complied with.
- Requires, for purposes of job order contracting, prevailing wages to apply to all work ordered under the JOC regardless of thresholds set forth in Section 1771.5 of the Labor Code.
- Requires the job order contractor to pay the prevailing wage in effect at the time the job order is issued by SamTrans and all increases as published by the Department of Industrial Relations (DIR) for the term of the JOC, including all overtime, holiday, and shift provisions published by the DIR.
- Requires SamTrans to designate one individual to act as a monitor to inspect job sites for labor compliance violations at the request of the designated labor representative in its PLA.
- Requires, in order to prevent fraud, waste, and abuse, SamTrans to prepare for each individual job order developed under a JOC an independent cost estimate. The estimate shall be prepared prior to the receipt of any job order contractor’s bid for the work and shall be compared to the job order contractor’s bid price to determine the reasonableness of that price before issuance of any job order. If SamTrans finds the job order contractor’s bid to perform work for a given job order to be unreasonable, not cost effective, or undesirable, SamTrans may elect not to issue the job order to the job order contractor, and may, instead, utilize any other available procurement procedures or choose not to move forward with the work.
- Requires SamTrans to submit to the appropriate policy and fiscal committees of the Legislature, on or before January 1, 2030, a report on the use of job order contracting under this bill. The report shall include, but shall not be limited to, all of the following information:
- A description of SamTrans’ system for evaluating JOC bids for award of JOCs, including, but not limited to, the criteria used by SamTrans to determine a qualified and responsive job order contractor.
- A description of each JOC awarded and the contractor awarded the contract.
- An assessment of the use of job order contracting under this bill.
- Provides a sunset date of January 1, 2032.
- Finds and declares that a special statute is necessary and that a general statute cannot be made applicable within the meaning of Section 16 of Article IV of the California Constitution because of the need for a pilot program to determine the potential benefits of job order contracting to a large transportation agency without setting policy for smaller local agencies.
COMMENTS:
- Purpose of the bill. According to the author, “SB 272 provides the San Mateo County Transit District (SamTrans) with a proven, cost-effective procurement tool Job Order Contracting (JOC) to expedite small maintenance and repair projects while maintaining full compliance with public contracting laws. Other transit agencies, including LA Metro and VTA, already use JOC to streamline project delivery, reduce administrative burdens, and save taxpayer dollars. By authorizing a pilot program for SamTrans, this bill ensures that critical transit infrastructure can be maintained efficiently, improving service reliability and rider experience.”
- Who is SamTrans? SamTrans operates 76 bus routes throughout San Mateo County and into parts of San Francisco and Palo Alto. It began operating bus service in 1976 after consolidating 11 municipal transit services in the county into a coordinated network. In mid-1977, SamTrans inaugurated its mainline service from Palo Alto to San Francisco, previously operated by Greyhound.
Also in 1977, SamTrans initiated service for persons with mobility impairments through its Redi-Wheels program more than a decade before the passage of the Americans with Disabilities Act. The service, provided by Redi-Wheels on the bayside and RediCoast on the coastside, regularly provides more than 1,000 trips in a day. SamTrans also serves as the administrative body for Caltrain commuter rail and the San Mateo County Transportation Authority, who have contracted with SamTrans to serve as their managing agency, under the direction of their appointed boards.
- What is Job Order Contracting? A JOC is a competitively bid, fixed price, indefinite quantity contract for the performance of minor construction, as well as the renovation, alteration, painting, and repair of existing public facilities. A JOC is generally a multi-year contract that includes a base year and multiple "option years," and is awarded before the awarding agency has identified specific work that it needs the contractor to perform. A typical JOC involves a variety of tasks such as roofing, electrical work, plumbing, and painting that are required for all of a public agency's buildings for a period of years.
A JOC is a fixed price agreement in that it is based upon specified charges contained in a Unit Price Book (UPB), which is prepared by the public agency or by independent commercial sources. The UPB sets forth detailed repair and construction tasks, including task descriptions, specifications, units of measurement, and unit prices for each task. Unit price refers to the amount paid for a single unit of an item of work. A contractor's bid is expressed in terms of a percentage of the specified UPB charges. The UPB is then used to determine the costs of each proposed project during the term of the contract. As an example, if a procuring agency's per unit catalog price for an HVAC installation is $1,000, and a contractor submits a bid to do that work with an adjustment factor of 1.13, the contractor is agreeing to install the HVAC for $1,130.
The total JOC value may be specified as a range with a certain guaranteed minimum. The award of annual contracts on a unit price basis enables what would otherwise be multiple separately-bid projects to be combined into one bid. This contracting method is intended to reduce costs and accelerate completion of smaller projects. It is not generally viewed as an appropriate method of contracting for large, complex construction projects that require extensive or innovative design or are likely to encounter changes and revisions during construction. JOCs are typically used for well-defined, recurring or repetitive work where quick execution is essential, not for single larger projects.
- Job order contracting in California. The Legislature has authorized multiple agencies to use job order contracting, some state and some local, including counties, school districts, community college districts, and the California State University system. California counties have enjoyed the authority to use job order contracting since 1983. Counties may award annual JOCs of up to $3 million, adjusted annually to reflect the California CPI, to the lowest responsible bidder or using best value (for specified counties).
Additionally, as part of the 2021-2022 state budget, the Legislature authorized Caltrans to use JOC, but the authority was limited to the new Clean California Beautification Program. In 2023, as part of the Governor’s Infrastructure package Caltrans’ authority was expanded. SB 146 (Gonzalez, Chapter 58, Statutes of 2023), authorized Caltrans to use JOCs, through 2033, for general highway and traffic maintenance. Finally, the Legislature approved JOC authority for some regional transportation agencies including VTA in Santa Clara County, and most recently for LA Metro.
- SamTrans wants to join the party. SB 272 authorizes SamTrans to develop a process for and use JOCs. Specifically, the bill authorizes SamTrans to enter into JOCs on a competitive basis for construction that is repetitive, for repair, or for renovation or modification. The maximum total dollar amount that may be awarded under a single JOC shall not exceed $5 million dollars in the initial contract term, and no single job order may exceed $1 million. JOCs may be executed for a contract term of no more than 12 months and may be extended or renewed for two subsequent annual terms and a maximum of $10 million over the subsequent two terms of the contract.
The bill also prohibits SamTrans from contracting for work that is protected by applicable collective bargaining agreements and requires all JOCs to comply with all SamTrans collective bargaining agreements.
Additionally, the bill provides for the payment of prevailing wages and labor compliance consistent with existing law, as specified. The bill also outlines the process for SamTrans to follow in soliciting and awarding JOCs, including the ability to award job orders of $250,000 or less to SBE or DVBE contractors.
Finally, the bill requires SamTrans to submit to the appropriate policy and fiscal committees of the Legislature, on or before January 1, 2030, a report on its use of job order contracting, as specified; and provides a sunset date of January 1, 2032.
According to SamTrans, “The District intends to use JOC for jobs like painting, bus shelter repairs, concrete/asphalt repairs, fencing repair and installation, lighting repairs, and elevator repair and rehabilitation. Implementation of JOC would also provide benefits to our local workers, including consistent work, predictable income, and reliable jobs for construction and building trades, including small and emerging contractors.
“As transit agencies across the state look for ways to reduce costs, enhance operations, and support the local economy, the District believes the use of JOC would advance these goals.”
Related/PREVIOUS Legislation:
SB 146 (Gonzalez, Chapter 58, Statutes of 2023) – Expanded Caltrans authorization to use JOCs, through 2033, for general highway and traffic maintenance.
AB 499 (L. Rivas, Chapter 499, Statues of 2023) -- Authorized LA Metro to enter into job order contracts (JOCs).
AB 2039 (L. Rivas, 2022) – Would have authorized LA Metro to enter into job order contracts (JOCs). AB 2039 was held in this committee.
AB 2763 (Kalra, Chapter 803, Statutes of 2022) -- Authorized VTA to enter into job order contracts (JOCs).
SB 1366 (McGuire, 2022) -- Would have authorized the Department of General Services to engage in job order contracting as an alternative procurement procedure for certain public works projects, until July 1, 2027. This bill died on the Senate Inactive file.
AB 149 (Budget Committee, Chapter 81, Statutes of 2021) -- Among other things, authorized Caltrans to utilize job order contracting for the Clean California Beautification Program of 2021, as specified.
AB 846 (Low, Chapter 303, Statutes of 2021) – Extended the authorization to January 1, 2027, for job order contracting for school districts and community college districts.
SB 793 (Hill, Chapter 627, Statutes of 2017) – Allowed specified counties to use the best value construction contracting method to award JOCs for up to $3 million, adjusted for inflation.
SB 744 (Hughes, Chapter 431, Statutes of 1997) – Increased the annual maximum contract amount that counties may award for county JOCs from $1 million to $3 million.
AB 680 (La Follette, Chapter 164, Statutes of 1983) – Authorized counties to award annual JOCs of up to $1 million.
FISCAL EFFECT: Appropriation: Fiscal Com.: Local:
POSITIONS: (Communicated to the committee before noon on Wednesday,
March 19, 2025.)
SUPPORT:
San Mateo County Transit District (sponsor)
Sourcewell
OPPOSITION:
None received
-- END --